DEDICATED FREIGHT CORRIDOR
                           CORPORATION OF INDIA LIMITED
                            (Government of India Enterprise)



                            FINAL REPORT

End -Term RAP Impact Evaluation of Land Acquisition
and R&R Implementation for EDFC-I (Khurja-Bhaupur)
                             Section)




                                                               JUNE 2020
LEA ASSOCIATES SOUTH ASIA PVT. LTD.
New Delhi, India
                                                          TABLE OF CONTENTS
EXECUTIVE SUMMARY ............................................................................................................ 1
1. INTRODUCTION
        1.1     Project Background .....................................................................................................................1
        1.2     Approach and Methodology ........................................................................................................2
        1.3     Structure of the Report ...............................................................................................................6
2.      CHANGES IN SOCIO-ECONOMIC AND LIVING STANDARDS ............................................... 7
        2.1     Changes in Occupational Profile ..................................................................................................7
        2.2     Changes in Income level ..............................................................................................................7
        2.3     Indebtedness ...............................................................................................................................8
        2.4     Housing Condition .......................................................................................................................8
        2.5     Change in Standard of Living .......................................................................................................8
        2.6     Opinion of the respondents.........................................................................................................9
3.      LAND ACQUISITION AND RESETTLEMENT IMPLEMENTATION OUTCOMES ..................... 13
        3.1     Status of Private Land Acquisition .............................................................................................13
        3.2     Disbursement of Compensation ................................................................................................13
        3.3     Procedure and Timeline Followed for Land Acquisition as per RAA, 2008 ...............................13
        3.4     Rehabilitation and Resettlement Assistance .............................................................................14
        3.5     Level of Satisfaction of PAPs: .....................................................................................................15
        3.6     Training of PAPs .........................................................................................................................15
        3.7     Status of Land Handover and Impact on Construction .............................................................16
        3.8     Impact on Common Property Resources...................................................................................17
        3.9     Corporate Social Responsibility Activities .................................................................................17
        3.10    Cost of Land Acquisition and Resettlement ............................................................................187
        3.11    Grievance Committee’s Impact ...............................................................................................198
        3.12    Arbitration and Court Cases ....................................................................................................209
        3.13    Local Employment Creation.......................................................................................................21
        3.14    Impact on Women ...................................................................................................................221
        3.15    Institutional Arrangement for RAP Implementation ...............................................................232
4.      CONCLUSION AND RECOMMENDATION .......................................................................254
        4.1     Key Findings .............................................................................................................................254
        4.2     Lessons Learnt .........................................................................................................................287
        4.3     Outstanding Issues and Suggested Action Plan .......................................................................309



                                                               LIST OF TABLES
 Table 1-1: Summary of Land Acquisition and Resettlement Impact of EDFC 1 .............................................. 1
 Table 1-2: Categorization of the land lost by the PAPs in the project ............................................................ 2
 Table 2-1: Socio-Economic Indicators ............................................................................................................. 8
 Table 2-2: Summary of Focus Group Discussions ........................................................................................... 9
 Table 3-1: Item-wise expenditure for RAP Implementation of EDFC 1 ........................................................ 19
 Table 3-2: Details of Cases Filed in Court..................................................................................................... 21


                                                              LIST OF FIGURES
 FIGURE 1: GPS Tagged Map of Survey Location: PAPs and Control Population ............................................. 5


                       CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST                                                                               Page | i
                                                                                                                             Final Report
                                                                                 End-Term RAP Impact Evaluation of Land Acquisition and
                                                                               R&R Implementation for EDFC-1 (Khurja – Bhaupur Section)
                                                                         a)
FIGURE 3: Timeline of Arbitration Cases....................................................................................................... 20
FIGURE 4: Cases Filed in Court and Cases Resolved ..................................................................................... 20



                                                      LIST OF ANNEXURES
Annexure I                :    Project Detail Factsheet of EDFC-1
Annexure II               :    Detailed Scope of Work

Annexure III              :    Sample Copy of Questionnaires of PAPs and Control Population

Annexure IV               :    Sample Copies of Focus Group Discussion (FGD) Guidelines

Annexure V                :    Photographs of FGDs conducted

Annexure VI               :    Assessment of timeline based on village level case studies

Annexure VII              :    Land acquired for NTH

Annexure VIII (A)         :    Newspaper Excerpts and Camps Organized

Annexure VIII (B)         :    Satisfaction Level of PAPs with respect to Awareness camps

Annexure IX               :    Training to the PAPs and Employment (Newspaper Excerpts)

Annexure X                :    Land Related Hindrances or Stoppage of Civil Works by Community

Annexure XI               :    Onsite Observations of Common Property Resource

Annexure XII              :    CSR activities of DFCCIL

Annexure XIII             :    Procedure of handling Grievances by DFCCIL

Annexure XIV              :    Local Employment Study

Annexure XV               :    Outcomes of the data analysis on various indicators of RAP Implementation



                                                  LIST OF ABBREVIATIONS

BPL                           ---    Below Poverty Level
CII                           ---    Confederation of Indian Industry
CPM                           ---    Chief Project Manager
CPR                           ---    Common Property Resource
CSR                           ---    Corporate Social Responsibility
DFCCIL                        ---    Dedicated Freight Corridor Corporation of India Limited
EDFC                          ---    Eastern Dedicated Freight Corridor
EM                            ---    Entitlement Matrix
FGD                           ---    Focus Group Discussion


                        CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST                                                                      Page | ii
                                                                                           Final Report
                                                       End-Term RAP Impact Evaluation of Land Acquisition and
                                                     R&R Implementation for EDFC-1 (Khurja – Bhaupur Section)
                                                a)

GoI           ---   Government of India
GPS           ---   Global Positioning System
GRC           ---   Grievance Redress Committee
IBRD          ---   International Bank for Reconstruction and Development
ITI           ---   Industrial Training Institute
LA            ---   Land Acquisition
LASA          ---   Lea Associates South Asia Private Limited
NGO           ---   Non-Government Organisation
NTH           ---   Non-Titleholder
OFC           ---   Optical Fibre Cable
PAPs          ---   Project Affected Persons
PMC           ---   Project Management Consultant
PWD           ---   Public Works Department
QPR           ---   Quarterly Progress Report
R&R           ---   Rehabilitation and Resettlement
RAA           ---   Railway Amendment Act, 2008
RAP           ---   Resettlement Action Plan
RCC           ---   Reinforced Cement Concrete
                    Right to Fair Compensation and Transparency in Land Acquisition,
RFCT-LARR     ---
                    Rehabilitation and Resettlement
ROB           ---   Railway Over Bridge
RoW           ---   Right of Way
RPF           ---   Resettlement Policy Framework
RUB           ---   Railway Under Bridge
SC            ---   Scheduled Caste
SDM           ---   Sub Divisional Magistrate
SEMU          ---   Social and Environment Management Unit
SPV           ---   Special Purpose Vehicle
S&T           ---   Signal and Telegraph
TH            ---   Titleholder
ToR           ---   Terms of Reference
WHH           ---   Women Headed Household




            CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST                                             Page | iii
                                                                                               Final Report
                                                           End-Term RAP Impact Evaluation of Land Acquisition and
                                                         R&R Implementation for EDFC-1 (Khurja – Bhaupur Section)



EXECUTIVE SUMMARY
1.      The Dedicated Freight Corridor Corporation of India Ltd. (DFCCIL), Ministry of Railways
implemented the World Bank Funded Dedicated Freight Corridor Project from May 2011 to the end of
2019. End-term Impact Evaluation of Resettlement Action Plan (RAP) is an in-built component of the
project which aims at assessing whether the affected persons and households are rehabilitated and
resettled as per the RAP. Commissioned by DFCCIL, the study assessed the impact of the project on the
project affected persons (PAPs) and control population.

2.      The implementation of the Khurja-Bhaupur section (343.56 Km.) of EDFC-1 has triggered
substantial land acquisition and resettlement impacts. RAP has envisaged 1442.15 ha. of land acquisition,
which has reduced by 7% to 1339.35 ha. by end of the implementation period. The project has taken
conscious efforts to minimize the impact on land. The number of PAPs was 56,651 as per RAP, estimated
based on individual land-owners. The number of PAPs during implementation was 25,472, estimated
based on single land-plot having multiple shareholders. In sum, the resettlement planning was near
accurate.

3.       The universe comprised 25,472 PAPs which included formal land-owners (‘Titleholders’), informal
settlers (‘Non-Titleholders’), resident owners or tenants and vulnerable categories. Out of the total PAPs,
1216 PAPs (5% of the total PAPs) were selected for the impact assessment. The identification of PAPs
followed proportionate sampling method. Apart from this, 284 households were chosen as control
population. Out of the 27 Common Property Resources (CPRs), 6 were studied using purposive sampling.
The project has acquired 1188.77 ha. of private land, which is 89% of the total land acquired and the
remaining included Government land. A total of 24,687 land-owners (97%) received compensation.
DFCCIL has disbursed compensation for 1178.38 ha. of land (99% of the total private land acquired).

4.      On an average, a Project Affected Person (PAP) has lost 0.05 ha. of land to the project. As per the
study, 87% PAPs has lost less than 0.1 ha. of land to the project.

5.      Out of the total PAPs, 532 families (2.1%) were displaced. The displaced families were
compensated for their affected structure and provided Rehabilitation and Resettlement (R&R) assistance
as per the Entitlement Matrix.

6.     As per the study, 31% PAPs utilised the compensation and assistance for construction/renovation
of house and 8% utilised the money for purchasing land.

7.     The PAPs as well as local community were satisfied with the relocation of common property
resources and appreciated the efforts of DFCCIL in relocating the CPRs.

8.      The average delay in handing over of the encumbrance-free land to the contractor as per the
provision of civil contract: achieving first milestone (i.e. 80% handover) was delayed by 51 days and
achieving the last milestone (i.e. 100% handover) was delayed by 1160 days.

9.      The occupational profile of the PAPs remains unchanged in comparison to the baseline. Majority
of the PAPs were engaged in agriculture and allied activities. The rate of unemployment has reduced


                CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST                                           Page | 1
                                                                                                             Final Report
                                                                      End-Term RAP Impact Evaluation of Land Acquisition and
                                                                    R&R Implementation for EDFC-1 (Khurja – Bhaupur Section)


from 6% (during baseline) to 2%. Average income of the PAPs increased by 26% in real terms (adjusting
for inflation). Average income of the BPL PAPs has increased by 1.4 times in comparison to the baseline1.
Further, the study showed that the living standard of PAPs have enhanced. Out of the total PAPs, 91%
intimated that they have constructed new house or renovated their existing residential structure with
improvised area; 37% PAPs were able to pay their debts, spend on medical as well as educational needs
and also on household chores.

10.     Analysis of the sample cases of land acquisition awards revealed that notification and various
procedures followed were in compliance to the Railway Amendment Act, 20082. The Award and further
procedures were done in time, whereas the award (20F) of 54 villages was delayed and surpassed the
prescribed period of one year. DFCCIL had paid the land-owners the value of award along with an interest
(5% per month) for the delayed period.

11.     The project has generated employment to 4193 persons since January 2014, which included jobs
of watchmen, office-assistant, site-supervisor, laboratory-assistant, electrician, and construction-site
labour. The average wages of these locally employed persons were about 15% more than the prescribed
minimum-wage rages.

12.      In essence, DFC has achieved its objectives to the maximum possible extent. The project affected
persons improved their income earnings, even though not at par with the control population, they
utilised the compensation and assistance amount for upgrading their living standards. Overall, the
problems emanating from the project are minimal as the expectations of the PAPs were high. Project
should provide additional resources to rectify the post-construction damages to residential structures
and also to remedy the RUBs, approach or access roads which largely affected community life.

13.      Land acquisition by government functionaries could be made more inclusive and time-bound,
with DFCCIL taking more facilitative approach at higher level with line departments. While delay-interest
is applicable for land compensation, resettlement assistance is disbursed without any delay-interest.
Measures should be taken to provide delay-interest for resettlement assistance, in tune with the land
compensation rules.




1
  As per the baseline, the PAPs earning less than Rs.25,000 were considered below poverty line. Presently (2019) the BPL
threshold income is Rs.27,000.
2
  The major stages of notifications and awards as per RAA, 2008 includes: (i) 20A –Notification by Central Government declaring
its intention to acquire land for execution of a special railway project briefly describing the land intended to be acquired and
about the special railway project, (ii) 20E-The Central Government declares, by notification that the land is acquired for the
purpose mentioned in section 20A. If no declaration is published within the period of one year from the date of publication of
section 20A then the notification will cease to have any effect and, (iii) 20F- The amount to be paid as compensation (Award) to
be determined by the Competent Authority within a period of one year from the date of publication of the declaration or the
acquisition (20E) of the land will lapse.



                    CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST                                                      Page | 2
                                                                                                   Final Report
                                                               End-Term RAP Impact Evaluation of Land Acquisition and
                                                             R&R Implementation for EDFC-1 (Khurja – Bhaupur Section)




1.       INTRODUCTION
1.1 Project Background

1.      The Ministry of Railways, Government of India (GoI) has received financing from the International
Bank for Reconstruction and Development (IBRD) towards the cost of Eastern Dedicated Freight Corridor
Project (EDFC). The Dedicated Freight Corridor Corporation of India Ltd. (DFCCIL), the implementing
agency has appointed LEA Associates South Asia Private Limited, New Delhi, for carrying out the “End-
Term Impact Evaluation of Land Acquisition and Rehabilitation and Resettlement (R&R) implementation
of the Khurja - Bhaupur section (343 Km.) of EDFC -1”. The stretch from New Bhadan to New Khurja (195
kms.) has been commissioned.

2.       The two Resettlement Action Plans (RAPs) i.e. (i) Khurja - Bhaupur section and (ii) Tundla re-
alignment, were prepared in March, 2011. As per the RAPs, the total length of the Bhaupur-Khurja
corridor was 343 Kms. (Double line); of which 149 Kms. was in detour section and balance 194 Kms. was
in parallel to the existing North Central Railway track. This section comprised of 4 junction stations and 6
crossing stations. As per RAP, the corridor traversed 8 districts and 291 villages of the state of Uttar
Pradesh. The Right of Way (RoW) width was around 40 mtr. in the parallel section and 60 mtr. in detour.
Out of 343 Km. of this stretch, Tundla detour was 71 Km.

3.       The implementation of the Khurja-Bhaupur section (343.56 Km.) of EDFC-1 has triggered
substantial land acquisition and resettlement impacts. The project has acquired 1,188.77 ha. of private
land impacting 25,472 Project Affected Persons (PAPs). Project has provided resettlement assistance to a
total of 10,260 PAPs. This included 532 physically displaced PAPs3 and rest 9728 PAPs in the category of
livelihood support. A summary of land acquisition and resettlement impact of EDFC-1 is presented in
Table 1-1, which shows that resettlement planning carried out, was near accurate. The detailed factsheet
showing the updated status of EDFC-1 is at Annexure I.

                              Table 1-1: Summary of Land Acquisition and Resettlement Impact of EDFC 1
                                                                          Baseline Status (as  End-term Impact
No.                              Parameter                                    per RAPs)        Status (as on July,
                                                                                                     2019)
 1    RoW Length (in route Km.)                                                  343                343.56
 2    Total Land Acquisition (Ha.)                                             1442.15              1339.35
      Project Affected Person [including Titleholders and Non-                  56651‬*              25472
 4
      Titleholders] (Nos.)
 5    PAP received R&R support (Nos.)                                              -                 10260
 6    Physically DisplacedPAPs (Nos.)                                              -                  532
Source: DFCCIL, 2019
[*Note: As per RAP (Tundla Realignment of May 2011): “due to large number of representations, the alignment of
Tundla detour was re-surveyed and mostly brought parallel. The Tundla detour was divided in 72 Km. parallel and
about 29.56 Km. in detour portion. Furthermore, to avoid displacement of people, DFCCIL has undertaken certain
technical efforts like minimizing track distance at selected locations and reducing embankment heights and slopes.


3
    Data as on May 2020, Source: DFCCIL.


                     CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST                                          Page | 1
                                                                                                              Final Report
                                                                          End-Term RAP Impact Evaluation of Land Acquisition and
                                                                        R&R Implementation for EDFC-1 (Khurja – Bhaupur Section)


At many built-up locations land width has been reduced to as less as 22 mtr. which has resulted in reducing impact
on residential as well as commercial structures”].

4.       It is seen from Table 1-1 that the length of the alignment has slightly increased. The total land
acquisition has decreased by 102 ha. (7%), and the number of PAPs has also decreased by 55%. The
reason for decrease in the number of PAPs in comparison to the area of land acquired is because during
RAP preparation, the land-owners were individually taken into consideration, whereas during the RAP
implementation the land having multiple shareholders were taken as a whole.

5.      Taking into consideration, 25,472 Project Affected Persons (PAPs) in 1,188.77 ha. of private land
acquired by the project, the average land of 0.05 ha. of one PAPs has been lost to the project. As per As
per the study, 87% PAPs has lost less than 0.1 ha. of land to the project.

                         Table 1-2: Categorization of the land lost by the PAPs in the project4
            Category of land in ha.                                   No. of PAPs                            % of PAPs
             Less than 0.1                                               22,225                                87.25
                0.1 - 0.5                                                 3,180                                12.48
            0.5 and above                                                   67                                  0.26
                 Total                                                   25,472                                100.0
Source: DFCCIL, 2020


6.     The End-Term Impact Evaluation of land acquisition and rehabilitation & resettlement
implementation process for EDFC-1 covers total length of 343.56 Kms. The stretch located in Uttar
Pradesh includes Bhaupur - Khurja section (271.56 Kms.) and Tundla Re-alignment (72 Kms.).

7.      The study aimed to assess whether the affected persons and households were rehabilitated and
resettled as per RAP and the impact of the project on the PAPs and control population. The objective of
the study is as under:

            Independently evaluate the land acquisition and rehabilitation and resettlement implementation
            process in the project.
            Assess the impact created by compensation and assistance provided to the project affected
            persons in improving their living standards.
            Evaluate the impact across all categories of project affected persons including formal land-
            owners (‘Titleholders’), informal settlers (‘Non-Titleholders’), resident owners or tenants and
            vulnerable categories.

8.          The detailed scope of work is given at Annexure II.

1.2         Approach and Methodology

9.     The end-term impact evaluation was done by comparing the present condition of the PAPs with
the conditions that were prevalent during the baseline (2011). The impact on PAPs was also assessed in


4
    Based on the analysis of the data received from the respective lots of DFCCIL.


                       CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST                                                    Page | 2
                                                                                                                  Final Report
                                                                         End-Term RAP Impact Evaluation of Land Acquisition and
                                                                       R&R Implementation for EDFC-1 (Khurja – Bhaupur Section)


comparison to a set of Control Population. Besides, level of satisfaction and perception of PAPs and local
community with respect to the implementation of RAP was also studied.

10.    The study involved both quantitative and qualitative data collection and analysis. The data for the
study was collected through household-surveys, focus group discussions (FGD) with various target
groups, and also institutional level discussions (DFCCIL, Project Management Consultant (PMC),
Contractors, and Non-Government Organization (NGO). The evaluation entailed the following tasks:

       Review of available project documents and literature
       Sample selection and coverage
       Data collection
       Focus Group Discussion and Discussion with Stakeholders
       Data analysis and report preparation

(a) Review of Project Documents and Literature
11.     The various documents and records were collected from the DFCCIL such as Resettlement Action
Plan (RAP), Award Copies, Payment of Compensation and Disbursement details, Micro Plans, Valuation
Reports (structure, land and trees) and data related to Grievance Redress Committee (GRC).

12.      In addition, data and information associated with time taken for various stages of land
acquisition, reasons for delay in handing over of encumbrance-free land to the contractor as per the
contract provision and its impacts on construction was collected and analysed.

(b) Sample Selection and Coverage
13.     Confirming the mandate of Terms of Reference (ToR), 1216 PAPs and 284 households (control
population) were surveyed. The sampling considered the following parameters:

       Various affected categories of PAPs including formal land-owners (‘Titleholders’), informal settlers
       (‘Non-Titleholders’), resident owners or tenants and vulnerable categories.
       PAPs located in detour and parallel sections,
       PAPs located in respective Lots5,
       PAPs whose land is acquired as per Railway Amendment Act (RAA), 2008 and Uttar Pradesh Direct
       Land Purchase Policy, 2015,
       PAPs who have been provided R&R assistance based on Resettlement Policy Framework (RPF)
       disclosed in 2011 and as per revised RPF disclosed in 20156.

14.     The Global Positioning System (GPS) tagged map showing the surveyed location of PAPs and
control population is presented in Figure 1.




5
  The civil contract of the project was carried out in three construction lots i.e. (i) Lot 101- Bhaupur to Etawah Bypass End (ii) Lot
102- Etawah Bypass End to Chamrola Bypadss End and (iii) Lot 103- Chamrola Bypadss End to Khurja
6
  The revision of the RPF was in view of the new land acquisition Act – Right to Fair Compensation and Transparency in Land
Acquisition and Rehabilitation and Resettlement (RFCT-LARR), 2013. This report uses the term ‘Entitlement Matrix (EM) 2011 and
Entitlement Matrix (EM) 2015’ denoting the respective RPFs.


                     CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST                                                           Page | 3
                                                                                                Final Report
                                                            End-Term RAP Impact Evaluation of Land Acquisition and
                                                          R&R Implementation for EDFC-1 (Khurja – Bhaupur Section)


(c) Data Collection
15.     Data at household level were collected applying direct interview method. A total number of 16
trained enumerators were deployed to collect the data, of which 5 were female. The enumerators were
guided by 6 field supervisors.

16.     A structured questionnaire was formulated covering the indicators for PAPs such as
(i) compensation and R&R assistance received (ii) utilization of compensation amount (iii) income
generation activities (iv) household/ individual income (v) debts (vi) household facilities (vii) grievance
redress (viii) satisfaction level and (ix) feedback/ opinion on Land acquisition and R&R processes. A
questionnaire for control population was also prepared covering the indicators such as (i) income and
occupation (ii) Debts (iii) household facilities and (iv) feedback/ opinion on change of living condition. The
sample copy of the questionnaire as well as control population is given at Annexure III.

(d) Focus Group Discussion
17.     Altogether, 12 FGDs were conducted. The objective of FGD was to assess the impact of RAP
implementation. The focus groups included (i) physically displaced people, (ii) PAPs received
compensation and R& R assistance, (iii) PAPs whose land acquired as per UP Direct Land Purchase Policy,
(iv) PAPs filed Grievance cases, (v) Vulnerable Groups (SC, ST, BPL, WHH and Differently-Abled), (vi)
Formal Settlers (Titleholders -THs) and informal settlers (Non-titleholders -NTHs), (vii) Civil Work
Contractor, (viii) PAPs Employed by the Contractor, (ix) Community Representatives for Common
Property Resources and Religious Structures, (x) Control Population, (xi) PAPs who filed Complaints to
World Bank, and (xii) PMC.

18.    The consultant team visited the project sites; interacted with PAPs, DFCCIL officials,
implementing agencies (Contractor, PMC & NGO) and other concerned departments. Sample copy of the
FGD guidelines is given at Annexure IV.




                 CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST                                           Page | 4
                                                                                                 Final Report
                                                             End-Term RAP Impact Evaluation of Land Acquisition and
                                                           R&R Implementation for EDFC-1 (Khurja – Bhaupur Section)




 Figure 1: GPS Tagged Map of Survey Location: PAPs and Control Population


CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST                                                                          Page | 5
                                                                                             Final Report
                                                         End-Term RAP Impact Evaluation of Land Acquisition and
                                                       R&R Implementation for EDFC-1 (Khurja – Bhaupur Section)




1.3 Structure of the Report

19.    This report consists of five chapters including the present one as Introduction. The list of the
chapters in the report are:

Chapter 1:             Introduction

Chapter 2:             Changes in Socio-economic and Living Standards
Chapter 3:             Land Acquisition and Resettlement Implementation Outcomes

Chapter 4:             Conclusion and Recommendations




                CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST                                         Page | 6
                                                                                              Final Report
                                                          End-Term RAP Impact Evaluation of Land Acquisition and
                                                        R&R Implementation for EDFC-1 (Khurja – Bhaupur Section)




2.    CHANGES IN SOCIO-ECONOMIC AND LIVING STANDARDS
20.     This chapter presents the comparative socio-economic background of project affected persons
during the current period (2019) and baseline period (2011). The characteristics of control population have
also been presented wherever required.

21.    The key findings with respect to changes in occupation, changes in income level, indebtedness,
housing condition, changes in living standard and opinion of the respondents (FGDs) are presented in
subsequent sections.

2.1     Changes in Occupational Profile

22.     The study has looked into the changes in the occupational profile of the PAPs from the baseline
period to the current period. Agriculture was the main occupation of the PAPs. During 2011, 19% of the
affected persons were engaged in agriculture. As per the study, majority of the PAPs (39%) were engaged
in agriculture and allied activities. Further, 4% of the Project Affected Persons reported change in
occupation. Rate of unemployment reduced to 2% during the end-term evaluation from 6% during
baseline.

2.2     Changes in Income level

23.    During 2011, the average income of the PAPs was Rs.31,875. In comparison to this, the average
income (in real terms) of the PAPs was Rs.40,135 and that of control population was Rs.46,090. The study
observed that the current income of the PAPs has increased by 26% over baseline income but is 15% lower
compared to control population.

24.     A comparison in the income of the PAPs who were compensated based on Railway Amendment
Act (RAA), 2008 and Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and
Resettlement Act (RFCT-LARR), 2013 respectively were analysed. The average annual income (in real terms)
of the PAPs who have received compensation as per RAA, 2008 was Rs.34,136 and the average annual
income (in real terms) of the PAPs who have received compensation as per RFCT-LARR, 2013 was
Rs.43,335. The study found that the difference in the annual income of the PAPs who were compensated
as per RFCT-LARR, 2013 with that of the control population was 6%. The difference in the annual income of
the PAPs who were compensated as per RAA, 2008 with that of the control population was 26%.

PAPs under Below Poverty Line (BPL): As per the baseline (2011), 63% of total PAPs were considered as
‘Below the Poverty line (BPL)’ families; earning less than Rs.25,000 annually. Presently, the BPL threshold
income is Rs.27,000 and accordingly 23% were BPL. The study observed that the average income (in real
terms) of BPL PAPs was 1.4 times higher compared to baseline.




                CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST                                           Page | 7
                                                                                                  Final Report
                                                              End-Term RAP Impact Evaluation of Land Acquisition and
                                                            R&R Implementation for EDFC-1 (Khurja – Bhaupur Section)


2.3      Indebtedness

25.    During 2011, 380 cases (81% of surveyed PAPs) of indebtedness were reported. As per the study,
indebtedness was reported for 37% PAPs. In case of control population, indebtedness was reported for
31%. One-third of the PAPs have utilised the compensation amount in repaying a portion of their debt.

2.4      Housing Condition

26.    The study has looked into the housing condition in terms of the nature of construction. During
2011, 97% of the PAPs had ‘pucca’ house (houses made of bricks, RCC permanent structure). The study did
not observe major changes in the housing condition.

27.    During 2011, 44% of the surveyed population were having separate kitchen and bathroom facilities
each and the situation continues for both PAPs and control population during the study period.

2.5      Change in Standard of Living

28.     The study revealed that the area of existing residential structure of 91% PAPs has increased and
also the new houses were constructed. Further, 31% PAPs utilized the amount for construction/renovation
of house followed by 8% for purchase of land and 3% for agricultural purpose. The study observed that
58% PAPs utilised the compensation amount and R&R assistance on repayment of loan, investment in new
business and expenditure on improved medical as well as educational facilities. The living condition of 39%
PAPs improved due to the project and 48% were able to construct new house. The remaining PAPs
intimated that their living condition did not improve due to the reason such as: (i) compensation amount
received was less and (ii) the amount received was spend on household chores.

29.     The study observed that out of the total PAPs, 19% were physically displaced. The area of existing
residential structure of 57% displaced PAPs has increased. Further, 66% PAPs utilized the amount for
construction/renovation of house followed by 15% for purchase of land. The study also observed that 18%
PAPs utilised the compensation amount and R&R assistance on repayment of loan and deposited in bank.
The living condition of 81% displaced PAPs improved due to the project. the remaining informed that
there was no change in the living condition as (i) compensation amount received was less (ii) invested their
own saving in construction of new house and (iii) material for construction of house was expensive.

30.      Table 2-1 below shows the various socio-economic indicators taken into account during the study.

                                        Table 2-1: Socio-Economic Indicators
 S.No.                                                         As per        Controlled       Project Affected
                              Indicators                      Baseline       Population       Persons [PAPs]
                                                               (2011)          (2019)              (2019)
 1.       Occupation (in %)
              Agriculture                                       19              37                   39
              Unemployed                                         6             0.3                   2
              Others                                            75            62.7                  59
 2.       Average annual income (in Rs.)                       31,875         46,090               40,135
 3.       Indebtedness (No. of cases: in %)                      81              31                   37


                  CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST                                              Page | 8
                                                                                                  Final Report
                                                              End-Term RAP Impact Evaluation of Land Acquisition and
                                                            R&R Implementation for EDFC-1 (Khurja – Bhaupur Section)


 S.No.                                                         As per       Controlled        Project Affected
                             Indicators                       Baseline      Population        Persons [PAPs]
                                                               (2011)         (2019)               (2019)
          Housing Condition
  4.                                                             97               -                   95
          (% having Pucca structures)
  5.      Separate Kitchen and bathroom facilities (in %)        44               -                   44
  6.      Area increased (in %)                                   -               -                   91
Source: RAP (2011) and Primary Survey (2019)

2.6      Opinion of the respondents

31.     Focus Group Discussions (FGDs) were conducted with various groups to understand the impact of
the project. FGDs were organised with 12 different groups in 69 locations wherein 637 people participated.
The photographs of the Focus Group Discussion is presented at Annexure V. Outcome of the FGDs is
summarised in Table 2-2.

                                  Table 2-2: Summary of Focus Group Discussions
Sl.No.     FGD Groups         Name of Locations                                 Outcome
  1      Physically          Naugawan,                Displaced PAPs received enhanced compensation as per the
         Displaced People     Sukhampur &               decision of the GRC.
                              Dekhiyapur (Auraiya      The PAPs themselves relocated to new location with
         Number of            District)                 external support received from DFCCIL and contractor.
         Consultations: 6    Barhan & Nagla Gokul     The PAPs were allowed to salvage the construction
                              (Agra District)           materials.
         Number of           Kirthra Mohmadpur        PAPs were not satisfied with the timeframe of 3-months
         Participants:        (Firozabad District)      given for relocation.
         57                                            PAPs expected employment opportunities for at least a
                                                        person in each household as part of the project.
  2      PAPs       who      Keshopur Jafori &        Vulnerable PAPs (BPL, differently-abled and widow)
         received             Doruchandpur              expressed satisfaction for the special assistance they
         Compensation         (Aligarh District)        received.
         and        R&R      Datoji, Alampur          PAPs who received compensation as per the Entitlement
         Assistance           Jhapta, Latifpur,         Matrix-2011 were not satisfied with the land rates as
                              Dokeli, Rasedpur          compared to the PAPs who received compensation as per
         Number of            Kaneta, Aronj &           the Entitlement Matrix-2015.
         Consultations:       Galamai (Firozabad       Majority of the PAPs utilized the compensation amount and
         15                   District)                 R&R assistance on repayment of debt, expenditure on
                             Barhan, Nagla Gokul,      improved medical and educational facilities.
         Number of            Surehara Mustkil &       Although it was planned initially to provide drain facility,
         Participants:        Dehrera (Agra             RCC road along the RUB, the same was not provided. This
         117                  District)                 created difficulty for the community people.
                             Behta (Kanpur Dehat      Majority of the PAPs have not filed any grievances due to
                              District)                 lack of awareness regarding GRC.
                                                       PAPs who approached the Court of Law for enhanced
                                                        compensation received favourable decision. They received
                                                        the enhanced compensation as well.
                                                       Water logging in newly constructed RUB during rainy
                                                        season.
                                                       Improper rehabilitation of borrow area resulted in soil run-
                                                        off and consequent damage to religious structure.



                  CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST                                             Page | 9
                                                                                                 Final Report
                                                             End-Term RAP Impact Evaluation of Land Acquisition and
                                                           R&R Implementation for EDFC-1 (Khurja – Bhaupur Section)



Sl.No.     FGD Groups         Name of Locations                                 Outcome
                                                      Community requested for making necessary drainage
                                                       facilities.
                                                      Few PAPs from Barhan, Nagla Gokul, Surehara Mustkil &
                                                       Dehrera of Agra District have not received R&R assistance.
                                                      PAPs received job-training from Industrial Training Institutes
                                                       (ITIs).
  3      PAPs involved in    Shahpur Derapur         PAPs expressed their satisfaction for the compensation
         Direct      Land     (Kanpur Dehat            amount received.
         Purchase Process     District)               They were also satisfied with the R&R assistance provided as
                                                       per Resettlement Policy Framework, following the provision
         Number of                                     amended in 2018.
         Consultations: 1                             PAPs purchased land utilizing the compensation amount and
                                                       constructed house.
         Number of
         Participants:
         17
  4      PAPs who have       Datoji, Latifpur,       Majority grievances of the PAPs were submitted to the
         filed Grievance      Dokeli, Rasedpur         respective DFCCIL site offices only and the concerned
         Cases                Kaneta & Kirthra         officials resolved the cases at their level.
                              Mohmadpur               In case of claiming for higher compensation, PAPs with the
         Number of            (Firozabad District)     help of legal practitioner had filed case with arbitrator.
         Consultations: 7    Barhan & Nagla Gokul    Few PAPs had filed cases with the arbitrator and was
                              (Agra District)          pending for decision.
         Number of
         Participants:
         27
  5      Vulnerable PAPs     Bhanduwa Phaphood       Participants comprised of members from Scheduled Castes
                              & Purwasa (Auraiya       (SC), BPL, Differently-abled and Women Headed Households
         Number of            District)                (WHHs).
         Consultations:      Datoji, Alampur         The participants expressed their satisfaction for the special
         13                   Jhapta, Kirthra          assistance provided to vulnerable category.
                              Mohmadpur, Bankat,      PAPs intimated that DFCCIL assisted the PAPs in
         Number of            Rampur, Dokeli,          administrative formalities and filling of forms etc.
         Participants:        Rasedpur Kaneta,        Participants did not face any difficulty in receiving the
         144                  Aronj & Galamai          compensation and R&R assistance amount.
                              (Firozabad District)    PAPs were satisfied with the assistance provided, even
                             Surehara Mustkil &       though they were not satisfied with the compensation
                              Dehrera (Agra            provided against lost land and assets.
                              District)
  6      Titleholders        Doruchandpur &          Participants were satisfied with the compensation and R&R
         (THs- Formal         Khera Khush (Aligarh     assistance provided. However, they were not satisfied for
         settlers) and        District)                not giving prior notice for demolition of structures.
         non-titleholders    Kirthra Mohmadpur       During construction frequent dust and water logging
         (NTHs-informal       (Firozabad District)     created difficulties for villages.
         settlers)                                    Soil run-off from embankment to agricultural fields affected
                                                       the standing crops.
         Number of                                    Relocation of informal settlers in Doruchandpur village of
         Consultations:                                Aligarh: land-owner (formal settler) provided land for
         3                                             constructing houses for informal settlers.
                                                      The informal settlers demanded for alternate land for
         Number of                                     relocation.
         Participants: 69                             Few PAPs have not received R&R assistance.

                  CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST                                           Page | 10
                                                                                                Final Report
                                                            End-Term RAP Impact Evaluation of Land Acquisition and
                                                          R&R Implementation for EDFC-1 (Khurja – Bhaupur Section)



Sl.No.     FGD Groups         Name of Locations                                Outcome




  7      Civil Work          Ritam (Etawah          The contractor informed that job specific safety training was
         Contractor           District)               provided on periodic basis to the employees.
                             Gari Bhakti (Agra      DFFCIL has taken pro-active steps to resolve local issues
         Number of            District)               related to stoppage of construction activities due to delay in
         Consultations:                               disbursement of land compensation.
         2                                           More than 1000 local people were deployed in different
                                                      construction activities based on their experience and
         Number of                                    knowledge as laboratory assistants, supervisor, electricians,
         Participants: 2                              drivers, operators, office boys, office assistant, helpers and
                                                      labourers. They were paid @ Rs.8,000/- to Rs.15,000 per
                                                      month.
                                                     Training and Corporate Social Responsibility (CSR) activities
                                                      were adopted based on the mandate and corporate policy
                                                      guidelines of the Contractor.
  8      PAPs employed       Hyatpur Bhaejara &     PAPs and community people got employment opportunities
         by the               Khera Khush Khabar      which helped them to improve their income level and living
         Contractor           (Aligarh District)      standard.
                             Mandrak (Ram Nagar)    The contractors provided entrepreneurial opportunity to
         Number of            & Dariyapur (Hatras     local people in supplying construction materials,
         Consultations:       District)               construction vehicles and local labour.
         7                   Datoi & Alampur        Local people were employed as drivers (for tractor trolley,
                              Jhapta (Firozabad       diesel vehicle) and security guards.
         Number of            District)              PAPs opined that they were satisfied with the job and were
         Participants: 68    Medidudhi (Etawaha      receiving their remuneration consistently.
                              District)
  9      Community           Kheriya, (Hathras      The types of Common Property Recourses (CPRs) relocated
         Representatives      District)               were: educational and religious structures, crematorium,
         for Common          Daruchandpur            graveyard and public-well.
         Property             (Aligarh District)     Community people were satisfied with the relocation of
         Resources and       Nagla Goal (Agra        CPRs for the proactive approach adopted by DFCCIL.
         Religious            District)               Participation of community was observed from identifying
         Structures          Latifpur (Firozabad     sites for relocation till completion of CPR construction.
                              District)              In Kheriya village, Hathras district, community was not
         Number of           Medidudhi &             satisfied for the non-release of compensation against the
         Consultations:       Bandhya Majro           affected land of the religious structure.
         6                    (Etawah District)      Soil run-off from the embankment and water logging had
                             Raipalpur (Auraiya      damaged the religious structure.
         Number of            District)
         Participants: 47




                  CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST                                          Page | 11
                                                                                                   Final Report
                                                               End-Term RAP Impact Evaluation of Land Acquisition and
                                                             R&R Implementation for EDFC-1 (Khurja – Bhaupur Section)



Sl.No.     FGD Groups          Name of Locations                                 Outcome
 10      Control             Hajipur Chautta         Most of the community people’s livelihood depended
         Population           (Aligarh District)       mainly upon agriculture.
                             Datoji, Dokeli,         Most of the participants working in agriculture, they were
         Number of            Rasedpur Kaneta,         employed as laborers.
         Consultations:       Aronj, Galamai,         During the rainy days, access to the village is blocked due to
         9                    Surehara Mustkil,        water logging in newly constructed RUBs.
                              Dehrera & Rahan         Provision for adequate drainage facilities along newly
         Number of            Khurad (Agra District)   constructed RUBs should be provided before the completion
         Participants: 89                              of construction work.
                                                      Access roads in the village were badly damaged due to
                                                       construction activities and movement of construction
                                                       vehicles.
                                                      Damaged roads have affected commuting to schools in
                                                       Rahan Khurad village in Agra District. Community submitted
                                                       written complaints to DFCCIL and District Administration;
                                                       community requested for favorable action.
Source: Focus Group Discussion conducted during Primary Survey-2019




                  CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST                                             Page | 12
                                                                                               Final Report
                                                           End-Term RAP Impact Evaluation of Land Acquisition and
                                                         R&R Implementation for EDFC-1 (Khurja – Bhaupur Section)




3.    LAND ACQUISITION                    AND        RESETTLEMENT                  IMPLEMENTATION
      OUTCOMES

32.     This part of the study presents detailed information related to land acquisition procedure which
was followed, time taken for various stages of land acquisition, reasons for delay in handover of
encumbrance-free land and its impacts on construction. The chapter also includes the perception of the
PAPs and their satisfaction level on several aspects of RAP implementation. Outcome of the data analysis
on various indicators are summarised and presented in tabular form at Annexure XV.

33.     The land acquired was on the basis of the provisions of RAA, 2008 and Uttar Pradesh Direct Land
Purchase Policy, 2015. The acquisition of land on behalf of DFCCIL was the responsibility of Revenue
Department. The valuation of structures located within the affected land was responsibility of Public Works
Department (PWD). The valuation of fruit bearing trees was carried out by Horticulture department and
non-fruit bearing trees was carried out by Forest department. DFCCIL appointed Non-Government
Organisations (NGOs) for facilitating RAP implementation.

3.1     Status of Private Land Acquisition

34.      Total land acquired for the project was 1339.35 ha., of which 1188.77 ha. was private land
affecting 25,472 PAPs. Out of the total acquired land, 4.72 ha., was acquired through Uttar Pradesh Direct
Land Purchase Policy, 2015. DFCCIL adopted this policy for acquisition of land-plots missed out previously
and those land required due to shift of alignment or for constructing drains, in order to reduce the timeline
for acquisition under RAA-2008. Accordingly, DFCCIL has amended the Resettlement Policy Framework
(RPF) in 2018.

3.2     Disbursement of Compensation

35.    As on July 2019, a total of 24,687 (97%) land-owners received compensation for 1178.38 ha., of
land (99%). Compensation was not disbursed for 785 land-owners (3%) for 10.39 ha., of land (1%).
Disbursement processes are progressing for which DFCCIL is facilitating with the Revenue Department.

3.3     Procedure and Timeline Followed for Land Acquisition as per RAA, 200 8

36.      As per Railway Amendment Act (RAA) 2008, after publication of the notification (20A) for land
acquisition, declaration (20E) of the same should be published within a period of one year, or else the said
notification will cease to have any effect. Also, the Competent Authority should make an award (20F)
within a period of one year from the date of publication of the declaration (publication of 20E) or else the
entire proceedings for the acquisition of the land lapses.

37.    The process involved in land acquisition was analysed by studying random cases of Award
procedures and respective timelines. The Award of fourteen villages were studied. The analysis of the
sample cases of Awards revealed that notification and various procedures followed, were in compliance to
RAA, 2008. The Award and further procedures were done within the prescribed timeframe of one year. The


                CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST                                           Page | 13
                                                                                               Final Report
                                                           End-Term RAP Impact Evaluation of Land Acquisition and
                                                         R&R Implementation for EDFC-1 (Khurja – Bhaupur Section)


average duration from 20A to 20E notification was observed to be 283 days and from 20E to 20F
notification was 233 days. The assessment of timeline based on village level case studies is given at
Annexure VI.

38.     Apart from the villages studied above, it was observed that in 54 villages, 20F was delayed and
surpassed the prescribed period of one year. DFCCIL had paid the land-owners the value of award along
with an interest (5% per month) for the delayed period as per the RAA, 2008.

3.4     Rehabilitation and Resettlement Assistance

39.      Disbursement of Rehabilitation and Resettlement (R&R) Assistance: A total of 10,260 PAPs were
identified for disbursement of R&R assistance. Out of the total PAPs, 19% belonged to the vulnerable
category. Till July 2019, disbursement was made to 9,449 PAPs (92%).

40.    Stamp Duty Redemptions: A total 592 requisitions for stamp duty reimbursement were received
of which 434 requisitions (73%) were considered and the remaining 158 requisitions (26%) were rejected.
Reasons for rejections were (i) submission of requisition after the prescribed one-year, (ii) land was not
purchased in the name of the entitled person, and (iii) claim submitted against the purchase of different
category of land (other than the affected land category).

41.     The study observed that 17% PAPs purchased land or assets with the compensation and R&R
assistance in lieu of their lost assets. Further, out of the PAPs who had purchased land, 24% PAPs
submitted requisition for stamp duty reimbursement within the stipulated timeframe and the respective
claims were approved. The rejection of claim was reportedly due to the registry done in the name of
dependents of the PAP. Also, the PAPs who did not claim for stamp duty stated that they were not aware
of the provision of stamp duty redemption.

42.      Resettlement Support: RAP insists that the project should provide adequate notification,
counselling and assistance to affected persons so that they are able to move or give up their assets without
undue hardship before commencement of civil works and after receiving the compensation. Taking into
consideration the RAP, the study captured 19% of the PAPs who were relocated. Out of these PAPs,
majority expressed that 3 months’ time was sufficient for relocation and stipulated time was given by the
officials for relocation. The remaining PAPs were of the view that more than 3 months’ time should be
provided for relocation.

43.     Physical Displacement of Informal Settlers (NTHs): In Douru Chandpur village, Aligarh, 14 NTHs
were displaced. The land-owner in whose land the NTHs were residing, was compensated. The structure
compensation for the affected structure owned by the NTH along with R&R assistance were provided to
respective NTHs.

44.     Discussion with NTHs revealed that the land-owner has provided 1450 sq.m., of land towards
relocation of the NTHs. The ownership of land provided for relocation remained with the land-owner. The
NTHs have built their residential structure on that land. DFCCIL provided them shifting assistance of
Rs.10,000, transitional allowance of Rs.4,000, assistance for displaced animal-shed of Rs.15,000 and



                CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST                                           Page | 14
                                                                                               Final Report
                                                           End-Term RAP Impact Evaluation of Land Acquisition and
                                                         R&R Implementation for EDFC-1 (Khurja – Bhaupur Section)


assistance for loss of livelihood of Rs.1,06,500 as per the EM, 2011. The photographs of the relocation site
are at Annexure VII.

3.5         Level of Satisfaction of PAPs:

45.      Satisfaction level regarding compensation amount: The study showed that 40% PAPs were
satisfied with the compensation amount. Those who were not satisfied (60%) had demanded for enhanced
compensation amount and opined that compensation amount was inadequate to replace lost assets. The
excerpts of the camps organized for PAPs is given at Annexure VIII (A) and the satisfaction level of the PAPs
with respect to the awareness camps is given at Annexure VIII (B).

46.     As per the study, 15% PAPs intimated about the delay in disbursement of compensation amount
and also informed that they frequently visited District Administration for availing the compensation.

47.     Satisfaction level regarding R&R assistance: The study revealed that 75% PAPs were satisfied with
the R&R assistance. The PAPs (25%) who were not satisfied with the assistance intimated that the amount
was divided among family members. In case of the PAPs who were relocated, 72% were satisfied with the
assistance provided for relocation.

48.     PAPs also intimated some cases of severance of land and consequent difficulties faced. In two
cases, tube wells owned by PAPs were located on the other side of the track and had to spend additional
money to reinstall the same which included purchase of the tube well and boring cost (case of Hayatpur
Bajhera and Khera Khushkhabar villages of Aligarh).

3.6         Training of PAPs

49.     DFCCIL provided training to PAPs on various trades like helper, electrician, fitter and data entry
operator. Altogether, 729 PAPs7 were given training. One of the trainings was provided by M/s Premvati
Devi Private ITI situated in Bedai, Sadabad (Hathras District), UP. DFCCIL communicated to Skills Education
Pvt. Ltd., an initiative under Ministry of Skill Development and Skill Education Pvt. Ltd., further entrusted
Premvati Devi Private ITI for imparting training to the PAPs. Discussion with Premvati Devi Private ITI
representatives revealed that 105 PAPs were trained (mostly belonging to BPL families) for duration of 4-5
months in the field of electrician (75% PAPs) and fitter (25% PAPs). Premvati Devi Private ITI had arranged
for placement of 60% of the trained candidates. The ITI also forwarded the two-month’ salary-statement of
respective candidates to DFCCIL. It was also reported that approximately Rs.1500 per candidate was
obtained from Skill Education Pvt. Ltd., to Premvati Devi Private ITI for imparting training.

50.      The study observed that 39 PAPs (3%) have received training, of which 37 PAPs received training
through ITI which was empanelled by DFCCIL and 2 PAPs received training through contractor in the field of
stone-pitching and trackman. These PAPs were employed by the contractor. PAPs have received training of
fitter, welder and electrician.




7
    Data as on May 2020, Source: DFCCIL.


                     CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST                                      Page | 15
                                                                                                Final Report
                                                            End-Term RAP Impact Evaluation of Land Acquisition and
                                                          R&R Implementation for EDFC-1 (Khurja – Bhaupur Section)


51.     Further telephonic conversation with 9 trained candidates, who were in the list provided by
DFCCIL, revealed that they had received training but had not received any job, one of the trainees said that
he had rejected the job-offer due to low salary (Rs.4,000 - 5,000 per month).

52.      These trainings were part of the income restoration measures aimed at restoring livelihood
conditions of the PAPs. RAP provides for training assistance for income generation through NGOs and
temporary employment in construction (with a condition, “if available for civil work and opted by the
PAPs”). The facilitating NGO is mandated with responsibility of motivating PAPs to take part in the
identified government sponsored income generation schemes. In Hathras District, the PAPs who received
training had staged protests against the DFCCIL for not providing job ‘as promised’ during the time of land
acquisition. The protested PAPs demanded job in the government sector. Newspaper excerpts of various
protests are given in Annexure IX.

3.7     Status of Land Handover and Impact on Construction

53.     Status of Land Handover: Focus Group Discussions carried out with the representatives of the
Contractor and PMC revealed that the handing over of encumbrance-free land was delayed and was
treated as one of the major delay-events while the Contractor computed the prolongation cost.

54.     As per the Contract, the first milestone is possession of 80% of the land within 28 days of the
contract. The second milestone is possession of 90% of the land within 91 days of the contract and the
third milestone is possession of 100% of the land within 182 days of the contract.

55.      Completion dates against respective milestones were computed based on the scheduled date of
site-possession. In this regard, the delay in handing over of 80% of the land ranged from 1 day to 129 days
(i.e. average delay of 51 days). Further, the delay in handing over of 100% of the land ranged from 240 days
to 1778 days (i.e. average delay of 1160 days).

56.     Other Delay-events: The Contractor also pointed out about various other delay-events including
delay relating to shifting of utilities, delay in removal of Optical Fibre Cable (OFC) and Signal and Telegraph
(S&T) cables in parallel sections, shifting of electric line, delay in appointment of PMC Engineer, civil
disturbances arising from the non-payment/delayed payment of compensation to the villagers, etc. The
cost incurred against the delay specifically due to the delay in handing over of encumbrance-free land was
not available or not disclosed by the Contractor. The prolongation cost claimed is around 19% of the total
contract value and the claim is pending for decision by Dispute Adjudication Board.

57.     Obstruction by Local Community People: Perusal of the communication details of the contractor
revealed that around 36 incidents of villagers’ agitation leading to stoppage of civil works were reported
from the year 2014 to 2017. Out of these incidents, more than half of the reported cases were related to
land acquisition or related compensation payments. Other than the land related agitations, the villagers’
also obstructed the work demanding re-sizing of RUB/minor structures or its location-changes and demand
for access road or its maintenance, etc. Details of land-related hindrances as per the contractor’s
communication one of the construction packages is given in Annexure X. ‘Offer of Jobs’ to project affected
families against loss of livelihood was also reported to be one of the reasons.


                 CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST                                           Page | 16
                                                                                               Final Report
                                                           End-Term RAP Impact Evaluation of Land Acquisition and
                                                         R&R Implementation for EDFC-1 (Khurja – Bhaupur Section)


3.8     Impact on Common Property Resources

58.     Common Property Resources (CPRs) have been relocated as observed during the visit to randomly
selected CPRs in six (6) locations (Two in Agra and one each in Auraiya, Etawah, Hathras and Aligarh).
Discussions with community people in various CPR locations showed that the impacted CPRs were
relocated considering its existed structure and architecture and in many cases, enhanced facilities were
also provided (Annexure XI). Overall, the community people were satisfied with the relocation of CPRs, and
they appreciated the efforts taken by DFCCIL, except for the delay occurred for completing the work by the
contractor as per agreed schedule, and that too even after the required land were made available to the
contractor for relocation of affected CPRs.

59.     The identified CPRs were grouped under two broad categories, ‘charted’ and ‘uncharted’. Those
CPRs which were potentially impacted and that were identified before mobilisation of the civil work
contract were all treated as Charted. Relocation of charted CPRs rests with the civil work Contractor. Those
CPRs which were identified during the civil work implementation stage were all grouped under Uncharted.

60.     Altogether 27 CPRs were identified for relocation, of which 24 were charted and 3 were uncharted.
Out of the total, 11 CPRs were from Aligarh district, 5 CPRs from Hathras district, 4 CPRs were from
Etawah, 3 CPRs from Firozabad district, 2 CPRs were from Kanpur Dehat district and one CPR each from
Agra and Auraiya district. The impacted CPRs include religious structures like, temples and rest houses and
also crematorium and graveyard.

3.9     Corporate Social Responsibility Activities

61.     RAP states that “DFCCIL will take social responsibility for reconstruction of community structures
and replacement of common property resources like temple, schools, colleges, roads, and hospitals in
consultation with the community. The facilitating NGOs will organize public consultation with concern
stakeholder‘s to decide the CSR work to be done by DFCCIL. However, the DFCCIL will follow GoI guidel ines
to plan and carry out CSR”. DFCCIL’s CSR is envisioned as a commitment to meet its social obligations by
contributing towards improving quality of life of the communities and stakeholders on a sustainable basis,
preferably in the project areas where it is operating.

62.      Overall CSR Activities in DFCCIL: CSR Policy was framed by DFCCIL in 2011-2012 based on the
guidelines issued by Department of Public Enterprise in April 2010 and was issued formally to the Ministry/
Department for compliance in the Central Public Sector Enterprise (CPSEs). Accordingly, during 2011-2012
two key areas were identified (i) computer education and (ii) eco-sanitation, for providing input for
development of persons residing in project affected areas. An amount of Rs. 20 lakh was spent on the said
activity. During 2012-2013, vocational/ technical trainings were provided to 891 PAPs with a view to
generate employment. An amount of Rs. 18 lakhs were spent on vocational/technical training. During
2013-2015, two key areas were identified (i) computer literacy (23 computers were provided in 15 schools
under the jurisdiction of project affected areas) and (ii) Vocational training (651 PAPs were provided
training with a total 35,032 man days) for providing input for development of persons residing in project
affected areas. An amount of Rs. 18 lakhs were spent on vocational training.




                CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST                                           Page | 17
                                                                                                         Final Report
                                                                    End-Term RAP Impact Evaluation of Land Acquisition and
                                                                  R&R Implementation for EDFC-1 (Khurja – Bhaupur Section)


63.      During 2014-2015, DFCCIL signed MoU with Confederation of Indian Industry (CII) on 18th
November 2015 as a part of CSR Activity to provide vocational training to 1000 PAPs/BPL youth (also
known as project ‘SAKSHAM’) at 4 CPM units including Tundla [(i) Allahabad West (ii) Tundla (iii) Mumbai
and (iv) Jaipur]8.

64.     Discussion with DFCCIL and Contractor has revealed that 13 CSR activities were undertaken in
EDFC-1.

65.    During 2014-2015, an amount of Rs. 2.50 lakhs were spent on construction of toilet blocks in a
primary school under Swachh Vidhyalaya Campaign in Firozabad district.

66.     In the year 2017-189, DFCCIL had allocated Rs. 10 lakhs for Tundla CPM unit as well as Ahmedabad
(Western Dedicated Freight Corridor) for the provision of computers in schools/ computer literacy.
Accordingly, office of the CPM, Tundla has purchased desktop computers, printers and computer
accessories for Government schools located along the project affected villages in the districts of Firozabad,
Etawah and Agra. The computer systems were distributed to Schools for providing computer training to
the students.

67.     In the year 2018-1910, as part of the CSR activities of DFCCIL, office of the CPM, Tundla had
provided cash-assistance of Rs. 15 lakhs to the District Administration of Firozabad and Agra respectively
towards construction of Public Conveniences. Contractor also gave support to schools located in project
location by constructing building for library and providing books.

68.      In the year 2019-2011, Skill Interventions in Schools to improve the employable skills and physical
fitness of the students was conducted through CII in four CPM units including Tundla [(i) Greater Noida/
Meerut (ii) South Mumbai (iii) Ajmer/ Jaipur and (iv) Tundla]. DFCCIL allocated Rs 100 lakhs for the said
activity. Details of CSR activities are given in Annexure XII.

3.10     Cost of Land Acquisition and Resettlement

69.     During land acquisition, the total compensation amount disbursed to the PAPs was Rs.719.38
crores. R&R assistance of Rs.68 crore was allocated of which Rs.58 crore was disbursed to the PAPs. So far,
846 PAPs have been identified for the disbursement of the R&R Assistance amount (i.e. one-time
resettlement allowance and annuity) which is in progress.

70.      As per RAP, the total land requirement of the project was 1442.15 ha. The total project cost (cost
of civil works, electric works, cost of land, R&R assistance, relocation cost of CPRs and implementation
charges) was Rs.5761.83 crore. The cost estimate for land acquisition and R&R assistance includes cost of
land, cost of structure, R&R assistance, relocation cost of CPRs and implementation charges. The total cost
incurred for various activities related to RAP implementation is estimated to be Rs.1269.72 crore which
includes cost of land, R&R assistance and cost of consultancy. Thus, 22% of the total project cost has been

8
  Source: DFCCIL Letter No. HQ/HR/35/CSR/2015-16 dated 21.12.2015
9
  Source: DFCCIL Letter No. HQ/HR/CSR Activities 2017-18 dated 31.07.2017
10
   Source: DFCCIL Annual Report, 2018-19 and DFCCIL Letter No. HQ/HR/CSR Activities 2018-19 dated 21.08.2018
11
   Source: DFCCIL Annual Report, 2018-19 and DFCCIL Letter No. HQ/HR/CSR 2019-20 dated 31.07.2019


                   CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST                                                 Page | 18
                                                                                                           Final Report
                                                                       End-Term RAP Impact Evaluation of Land Acquisition and
                                                                     R&R Implementation for EDFC-1 (Khurja – Bhaupur Section)


incurred towards land acquisition and resettlement. Also, compared to the estimated during RAP, the RAP
implementation expenditure is higher by 1.6 times. This is attributed to the escalated cost of land
compensation as per the new Act, RFCT-LARR 2013 and Uttar Pradesh Direct Land Purchase Policy and R&R
assistance as per the EM-2015. Item wise expenditure of RAP implementation is given Table 3-1.

                           Table 3-1: Item-wise expenditure for RAP Implementation of EDFC 1
  S.                                                                       Budget as per RAP                Expenditure
                                         Item
 No.                                                                         (Rs.in crore) ^                (Rs.in crore)
  1      Cost of Land                                                                          322.18               1176.85
  2      R&R Assistance                                                                         81.35                  89.17
  3      Relocation of CPR*                                                                       1.69                      0.0
         Implementation Charges (Training, Administration,                                      74.37                   3.70
  4
         Management, Capacity building, Monitoring, NGOs etc.)
                                     Total                                                     479.59               1269.72
Note: *The relocation cost of CPR is the part of the contract document of contractor.
       ^ The Budget as per RAP includes contingency @8%.
Source: RAP-2011 and DFCCIL (as on November, 2019)

3.11     Grievance Committee’s Impact

71.    Grievance Redress Committee (GRC) as mentioned in the RAP was formulated in all the districts.
The GRC comprised the following members:

                District Collector of the concerned District, Chairman
                Zila Parishad Chairperson/ his or her nominee
                Concerned Competent Authority/ Administrator
                Concerned Assistant Project Manager of DFCCIL
                Representative from Civil Society/ a reputed local NGO

72.     The grievances of the PAPs were regarding enhancement of compensation, delayed disbursement
of compensation, compensation not provided of the additional land acquired, R&R and handicapped
assistance not received, more land acquired than marked, community issues related to water logging,
damaged access roads. The grievances were usually submitted to the DFCCIL site office, Head Quarter or to
the Arbitrator. The cases filed with the Arbitrator were mostly done with the help of legal practitioners.

73.     Till July 2019, a total of 1,581 grievance cases were recorded of which 1,570 cases (99%) were
resolved. The decision has been pending for remaining 11 cases (1%). It is observed that most of these
cases were not directed to GRC but were dealt and resolved within the site offices of DFCCIL. Study also
observed that 16% of the PAPs were having adequate knowledge of various procedures for filing
grievances with GRC. The detailed procedure of handling grievances by DFCCIL is given at Annexure XIII.

74.     Study observed that, 151 PAPs (12%) have submitted grievance cases at various levels of District
Administration and to the site offices of DFCCIL. Majority of the PAPs (67%) were satisfied with the
decision.




                    CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST                                                   Page | 19
                                                                                                Final Report
                                                            End-Term RAP Impact Evaluation of Land Acquisition and
                                                          R&R Implementation for EDFC-1 (Khurja – Bhaupur Section)


75.     The Concurrent Monitoring Team appointed by the DFCCIL had observed that there was lack of
awareness among the PAPs regarding grievance redress system. The GRC couldn’t be convened for
resolving issues of aggrieved persons quickly due to its size. Accordingly, the Monitoring Team suggested
for modifying the constitution of GRC in order to make it functional. The Monitoring Team also observed
some hindrances to the smooth and efficient functioning of the grievance redress mechanism such as (i)
lack of awareness among PAPs regarding who to approach for grievance redress, (ii) lack of direct
communication with PAPs – and as a resolution the monitoring team had suggested coordination with
respective Sarpanch and display of GRC information at prominent places, and (iii) delay in inter-
departmental coordination for grievances requiring intervention of other state level departments. World
Bank in its site-visit note (22-25 June 2018) noticed that communication and coordination between the
DFCCIL, LA Authority and PAPs remained an issue in the Project, as PAPs were not aware of the
entitlements, approval of supplementary micro plan, and disbursement of payments and availability of
GRC.

76.      Status of Complaints forwarded to the World Bank: There were 36 complaints by 28 PAPs
submitted directly to the World Bank through e-mail. These complainants were from the districts of
Auraiya and Etawah. The World Bank along with DFCCIL officials from Kanpur site office and Concurrent
Monitoring Team conducted meetings with the complainants in project locations. DFCCIL had regularly
updated the action taken against respective complaints to the World Bank. As per the data received from
the site office, 30 complaints were resolved which pertained to (i) enhancement of compensation (ii)
livelihood assistance as per new land acquisition Act (iii) discrepancy in measurement of affected area (iv)
acquisition of residual land (v) non-receipt of compensation and R&R assistance (vi) request for
construction of a culvert (vii) request for alignment change to avoid impacts. To understand the
satisfaction level of the complainants, a discussion was conducted with 5 complainants wherein 4 PAPs
intimated that they were satisfied with the decision and one PAP was not satisfied as his case for non-
receipt of compensation was pending in Court of Law.

3.12    Arbitration and Court Cases

77.      Arbitration Cases: As per Clause (6) of Section 20F of the Railway Act, 1989 (24 of 1989), Arbitrator
has to be appointed for determining the payment of compensation to the PAP; when the PAP was not
satisfied with the compensation provided. Commissioners of Kanpur, Agra and Aligarh were respectively
appointed as Arbitrators. Till July 2019, 2879 Arbitration Cases were filed of which136 cases (5%) were
pending.

78.    Out of the 136 pending cases, 56% cases were pending for the last 12-24 months and 42% cases
were pending for more than 24 months. The reason pointed for the delay in disposing the cases was
inadequate time-availability of respective Commissioners. The absence of PAPs during the hearing has also
delayed the processes. Most of the arbitration cases were filed for enhancing the compensation rates.




                CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST                                            Page | 20
                                                                                                                                                     Final Report
                                                                                          End-Term RAP Impact Evaluation of Land Acquisition and
                                                                                        R&R Implementation for EDFC-1 (Khurja – Bhaupur Section)




                                                      76
     Number of Cases




                       100                                         57                                                               83
                                                                                                   100              77




                                                                                        Number of Cases
                                                                                                                                              Total Number of
                        50                                                                                                                    Cases
                                  2          1                                                                                                Number of Cases
                         0
                                                                                                          50                                  Resolved
                               <6         6-12    12-24       >24                                                        9
                                                                                                                                         1           2 0
                              months     months   months     months
                               old         old     old        old                                          0
                                        Timeline of Cases                                                      District Court    High Court Supreme Court



                       Figure 2: Timeline of Arbitration Cases                       Figure 3: Cases Filed in Court and Cases Resolved
Source: DFCCIL, 2019

79.     Court Cases: Till July 2019, there were 161 cases filed in various courts (District Court, High Court
and Supreme Court), of which 151 cases were pending for decision. Cases were related to enhancing rate
of compensation, demand for payment of interest rate due for delayed disbursement, appeal against the
Arbitrator’s decision. Two cases were from Etawah which was under review of Supreme Court, filed by the
PAPs demanding payment against the acquisition of their land declared under section 20E but not awarded
under 20F. In this case, the High Court ruled in favour of DFCCIL referring to its communication which
stated that Railways did not propose to utilize the land declared for acquisition under section 20E and also
referring to section 20F (2) the said declaration stand lapsed.

                                                                 Table 3-2: Details of Cases Filed in Court
                         District Court                          High Court                  Supreme Court                                       Grand Total
                 Filed                 Pending         Filed             Pending                 Filed                 Pending               Filed          Pending
    77             68                                       83              82                            1                  1               161              151
Source: DFCCIL, 2019

80.    Analysis of the timeline of filed cases in various Courts shows that 56% of cases were pending for
more than 24 months and 20% cases were pending for more than a year. Overall, nearly 96% of cases filed
were pending for decision.

81.     As per the study, majority of the PAPs intimated to have hired legal practitioners for arbitration/
court cases. Out of the total PAPs, 21% submitted arbitration/court cases. Out of the PAPs who had
submitted their cases, 26% intimated that the arbitrator’s/ court’s decision benefitted them as it was in
their favour. Whereas, 42% intimated that the arbitrator’s/ court’s decision was not in their favour. The
cases of remaining 32% PAPs were pending.

3.13                         Local Employment Creation

82.    The project has generated local employment to 4,193 persons12 since January 2014. Local
entrepreneurs also emerged as part of the project for supply of local labour as well as construction
materials, construction vehicles, etc. Majority of the PAPs were satisfied with the employment conditions,

12
  Sources: (i) Employment Records of the Contractor, (ii) Discussion with DFCCIL Officials, (iii) FGD with the local people employed
by the Contractor.


                                       CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST                                                                         Page | 21
                                                                                               Final Report
                                                           End-Term RAP Impact Evaluation of Land Acquisition and
                                                         R&R Implementation for EDFC-1 (Khurja – Bhaupur Section)


wages and facilities provided by the contractor. FGD was conducted with the PAPs employed by the
contractor which is presented in Table 2-2, sl. no. 8 under ‘PAPs employed by the contractor’. The number
of man-days vary from a day/week to a year or more depending on the project duration. Discussions with
the local employed persons revealed that their average wages range between Rs.450-550 per day and for
some jobs like watchmen, office assistant, site-supervisor, laboratory-assistant, electrician, stone-crushing
and pitching, etc., the wages range between Rs.8,000-15,000 monthly respectively. Stone-crushing work
involved heavy physical work and youngsters were usually preferred. One wagon of stone is rated at
Rs.2000 and about 4 persons could complete 1 -2 wagons of stone. The study observed that the average
wage of the local employed persons was 15% more than the minimum wage rates. The detailed study of
the local employment is given at Annexure XIV.

3.14    Impact on Women

83.     Development projects improve the living conditions of women by taking into account the women’s
participation and as well as their real needs. The study has carried out the consultations with women
groups in order to understand the impact of the project on the women community.

84.      Till July 2019, out of a total of 25,472 PAPs, 3,345 (13%) were women PAPs. Out of these women
PAPs, 94 (3%) were physically displaced. Out of the total physically displaced PAPs, women PAPs accounts
for 18%. The compensation and R&R assistance were disbursed to 3344 women PAPs. The one physically
displaced women PAP has not accepted the compensation as she has demanded for enhanced
compensation and hence the R&R assistance is not yet disbursed. Further, out of 729 PAPs provided skill
training, 70 PAPs (10%) were women. These women PAPs were provided training in garment making (from
ITI Kanpur), welding and electric (from ITI Etawah). The study revealed the following:

 (i).   Socio-economic changes:

    (a) Occupation: The occupation pattern of women remained unaltered. As per the baseline study,
        most of the women were housewives and the pattern continued during end-term evaluation study
        as well. The remaining women PAPs were engaged in various occupations such as agriculture,
        wage-labour, trade and service (in government and non-government organisations).

    (b) Income level: The average annual income (in real terms) of the women PAPs was Rs.31,640 and
        that of control population was Rs.34,480. The study observed that the annual income level of the
        women PAPs was 8% lower compared to control population.

    (c) Indebtedness: Indebtedness was reported for 22% women PAPs. Majority of the women PAPs
        utilised the compensation amount in repaying a portion of their debt. In case of control population,
        indebtedness was reported for 31%.

    (d) Standard of Living: The study revealed that the area of existing residential structure of both women
        PAPs (88%) and male PAPs (90%) has increased. Both intimated that the new houses constructed
        were better than the old houses. The living condition of 39% women PAPs have improved
        considerably as they were able to construct ‘pucca’ houses (houses made of bricks, RCC permanent



                CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST                                           Page | 22
                                                                                               Final Report
                                                           End-Term RAP Impact Evaluation of Land Acquisition and
                                                         R&R Implementation for EDFC-1 (Khurja – Bhaupur Section)


         structure), renovate house, purchase cattle, repay part of their debt, spend on medical as well as
         educational needs and also on household chores and the situation was same for male PAPs.

(ii).    Awareness about Act/ Policy applicable for the project: Majority of the women PAPs (63%) were
         aware about the Act/ Policy through which their land was acquired. Awareness among women
         PAPs were at par with their men counterparts.

(iii).   Disbursement of compensation and R&R assistance: Out of the 176 women PAPs, all received the
         compensation and R&R assistance. They study revealed that 18% women PAPs have approached
         the Arbitrator/ Court cases for enhancement of compensation.

(iv).    Difficulty faced during receipt of entitlements: Majority of the PAPs (76%) intimated that they did
         not face any difficulty in receiving the entitlements. The remaining 24% intimated that they have
         faced difficulties such as (i) frequent visits to District Administration/DFCCIL for availing the
         entitlements, (ii) staging of protests for enhanced compensation and (iii) delayed payment of
         entitlements.

(v).     Level of Satisfaction: Out of the total women PAPs, 50% were satisfied with the entitlements
         provided. On the other hand, 40% men had expressed their satisfaction. Both men and women
         who expressed their satisfaction revealed that the entitlements have positively contributed
         towards improving their standard of living. Both were able to construct or renovate houses, repay
         part of their debt, spend on medical as well as educational needs and also on household chores.

(vi).    Physically displaced women PAPs: The study observed that no physically displaced women PAPs
         were provided employment. Out of the total Women PAPs, 56% were satisfied with the
         compensation amount as well as R&R assistance. The living conditions of 39% women PAPs have
         improved as they were able to construct house, purchased land and purchased cattle. They
         intimated that the compensation amount and R&R assistance received was adequate enough to
         replace their affected / lost asset.

3.15     Institutional Arrangement for RAP Implementation

85.     Social and Environmental Management Unit (SEMU) was responsible for implementation of RAP in
coordination with 3 Offices of Chief Project Managers (CPM) - DFCCIL at Agra, Kanpur and Aligarh
respectively. There were 3 contractual employees in respective offices of CPM, who were reporting to
Senior Executive Engineer. These employees were responsible for land acquisition processes, resettlement
& rehabilitation and training procedures. In addition to the above-mentioned duties, the contractual
employees were also responsible for handover of advance-notices to PAPs, liaising with revenue officials
and disbursement of compensation/assistance amount.

86.     The contractual staffs also included retired revenue officials who facilitated DFCCIL works. Two
NGOs were contracted by DFCCIL for Aligarh, Kanpur and Agra respectively. However, the contract of the
NGOs was concluded on prescribed dates and the remaining works were handled by DFCCIL officials.
Discussion with various officials revealed that most of the staffs in the position of Project Managers and
above were having technical background in engineering and lacks specific experience in land acquisition

                 CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST                                          Page | 23
                                                                                              Final Report
                                                          End-Term RAP Impact Evaluation of Land Acquisition and
                                                        R&R Implementation for EDFC-1 (Khurja – Bhaupur Section)


and resettlement related aspects. Officials received training on social safeguard implementation through
the training organized by NGO and Concurrent Monitoring Team.

87.     RAP implementation by NGOs: Two NGOs were contracted by DFCCIL for Aligarh, Kanpur and Agra
respectively. NGOs had supported the project by organizing camps to identify the affected persons. NGOs
had also helped to disburse the R&R assistance by preparing Micro Plan. The support of NGO helped in
smooth disbursement of the compensation to the PAPs. Further, the NGO liaisoned with PAPs to help them
submit requisite documents for receiving the compensation and R&R assistance and also disseminated
requisite project information. As per RAP, NGOs should work with the PAPs and the line departments to
dovetail the government sponsored income generation schemes for the benefit of PAPs. However, such
dovetailing had not taken place. NGOs had prepared the list of PAPs eligible for training. DFCCIL later
arranged for the training in identified institutes.

88.      Monitoring and Evaluation by Concurrent Monitoring Team: Consultants were appointed by the
DFCCIL to carry out quarterly review of social and environmental safeguard activities implemented in the
project. Three Consulting Agencies were contracted by DFCCIL since inception of the project. The
Concurrent Monitoring Team had identified the gaps in the implementation of RAP and had suggested
corrective measures. The major issues identified were related to (i) periodic progress on land acquisition,
disbursement of compensation and R&R assistance, grievances and stamp duty redemptions (ii)
institutional snags leading to impediments in the process of acquiring land, (iii) procedural delay in
providing entitlements and (iv) opinion and suggestions of PAPs received through specific consultations
and one-to-one interviews. The Concurrent Monitoring Team had also imparted training to the officials of
DFCCIL, PMC, Contractor and NGO regarding implementation of RPF, RAP and its compliance.




                CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST                                          Page | 24
                                                                                             Final Report
                                                         End-Term RAP Impact Evaluation of Land Acquisition and
                                                       R&R Implementation for EDFC-1 (Khurja – Bhaupur Section)




4.     CONCLUSION AND RECOMMENDATION

89.     The key findings, lessons learnt and outstanding issues along with recommendations are
summarized in this section. Based on the impact evaluation, the study suggests remedial measures as
required to meet out the objective of R&R implementation. The DFCCIL should monitor the outstanding
actions beyond the impact evaluation study, which include disbursement of compensation and R&R
assistance, rectifying post-construction damages to affected residential structures, approach roads and
assurance on commuters’ safety.

4.1      Key Findings

      A. Socio-Economic Findings
        (a) Occupation Profile:
             Occupation pattern of the PAPs remained unaltered. Majority of the PAPs were engaged in
                agriculture and allied activities.
             A reduced level of unemployment was observed in comparison to the baseline.

        (b) Income Level:
              In comparison to the baseline, the income of PAPs has increased. The average annual
                income level of the PAPs have increased by 26% over baseline. The study also observed
                that the average annual income level of the PAPs was 15% lower than the Control
                Population.
              The average annual income of the PAPs who were compensated as per RFCT-LARR, 2013
                was at par with control population (with a difference of 6%) than the PAPs who were
                compensated as per RAA, 2008 (with a difference of 26%). The average annual income of
                the PAPs who were compensated based on RFCT-LARR, 2013 fared better than the PAPs
                who were compensated based on RAA, 2008.
              The average annual income of PAPs below poverty line has increased 1.4 times as
                compared to the baseline.

        (c) Indebtedness
              Indebtedness reported for 37% of the PAPs against 81% of PAPs during baseline. One-third
                of the PAPs utilised the compensation amount and R&R assistance in repaying a portion of
                their debt.

        (d) Housing Condition:
             Housing condition of the PAPs remained unaltered. Majority of the PAPs were living in
                ‘pucca’ house (houses made of bricks, RCC permanent structure).
             In terms of facilities (i.e. having separate kitchen, bathroom and toilet), no change was
                observed in the study period in comparison to the baseline period.




                 CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST                                        Page | 25
                                                                                            Final Report
                                                        End-Term RAP Impact Evaluation of Land Acquisition and
                                                      R&R Implementation for EDFC-1 (Khurja – Bhaupur Section)




       (e) Standard of Living:
            The compensation money gave the PAPs an opportunity to purchase new lands, construct
               new houses or renovate their old houses. Study observed that 58% of the PAPs reported
               utilizing money for investment in new business and/or clearing the existing debts and
               spend on improved medical and educational facilities.

B. Land acquisition and Rehabilitation & Resettlement Support
 i.       Land Acquisition:
            Total land acquired for the project was 1339.35 ha., of which 1188.77 ha., was private land.
              The land acquisition followed RAA, 2008 except 4.72 ha., which was acquired through Uttar
              Pradesh Direct Land Purchase Policy, 2015.
            As on July 2019, 10.39 ha. of land was remaining to be acquired.
            On an average, one PAP has lost 0.05 ha. of land to the project. As per the study, 87% PAPs
              has lost less than 0.1 ha. of land to the project.
 ii.      Timeline of Land Acquisition:
            The notification and various procedures followed for acquiring land was in compliance to
              the RAA, 2008 and the procedures were done within the prescribed timeframe.

iii.      Disbursement of Compensation and R&R Assistance:
           The disbursement of compensation and R&R assistance have largely progressed.
           As on July 2019, a total of 785 land owners (3%) are yet to receive compensation and 811
              PAFs (8%) are yet to receive R&R assistance. The disbursement of compensation amount
              and R&R assistance for the remaining PAPs were in progress at the time of the study.

iv.       Resettlement Support:
            Stamp Duty Reimbursement: In case of stamp duty redemption, 26% claims were rejected
              due to various reasons such as (i) submission of requisition after the prescribed one-year,
              (ii) land was not purchased in the name of the entitled person, and (iii) claim submitted
              against the purchase of different category of land (other than the affected land category).
            Relocation time given to PAPs: PAPs were not satisfied with the timeframe of 3-months
              given for relocation.

C. Satisfaction Level and Perceptions of the PAPs:
              Study showed that 40% of the PAPs were satisfied with the compensation amount.
               The remaining 60% of the PAPs who were not satisfied with the compensation amount
               opined that the compensation amount was not adequate to replace their lost assets.
              Three-fourth of the physically displaced PAPs expressed their satisfaction regarding the
               assistance provided.




               CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST                                         Page | 26
                                                                                                       Final Report
                                                                   End-Term RAP Impact Evaluation of Land Acquisition and
                                                                 R&R Implementation for EDFC-1 (Khurja – Bhaupur Section)



       D. Grievance Redress Mechanism:
                    Grievance Redressal Committee as mentioned in the RAP was formulated in all the seven
                     districts where the EDFC -1 traverses.
                    The grievances of the PAPs were related to enhancement of compensation, delayed
                     disbursement of compensation, compensation not provided of the additional land
                     acquired, R&R and handicapped assistance not received, more land acquired than marked,
                     community issues related to water logging, damaged access roads.
                    Most of the grievance cases were not directed to GRC but were dealt and resolved within
                     the site offices of DFCCIL.
                    Study observed that 84% of the PAPs were not aware of the various procedures involved to
                     file grievances with GRC.

       E. Local Employment:
                    The project has generated local employment to 4,193 persons in various jobs like
                     watchmen, office assistant, site-supervisor, laboratory-assistant, electrician, stone-crushing
                     and pitching.
                    Local entrepreneurs were also emerged and were engaged in supplying of local labour as
                     well as construction materials and construction vehicles.

       F.    Relocation of Common Property Resources:
                 There were 27 CPRs relocated in this DFCC project stretch, of which 24 were categorised as
                   ‘charted13’ and were relocated by the Contractor. The ‘uncharted14’ CPRs were relocated by
                   DFCCIL.
                 The community people were satisfied with the relocation of the CPRs. The participation of
                   the community was evident in relocation of most of the CPRs.

       G. Impact on Women:
                    Compensation and R&R assistance has been disbursed to all the women PAPs. They
                     intimated that they did not face any difficulty in receiving the same.
                    The overall distribution of income and indebtedness showed that women PAPs are
                     economically at par with their counterpart in control population.
                    The area of existing residential structure of both women PAPs (88%) and male PAPs (90%)
                     has increased. Further, equal improvements were observed in the living standards of both
                     women and male PAPs.

       H. Handing over of Encumbrance-Free Land to Contractors:
                    Delay in handing over of land to the contractor was observed in all the three Lots of EDFC
                     1. Achieving 80% length, was delayed by average 51 days against the timeline as per
                     contract. Achieving 100% length was delayed by average 1160 days against the timeline as
                     per contract.
13
     CPRs included under the scope of Civil Works Contract
14
     CPRs not included under the scope of Civil Works Contract


                      CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST                                             Page | 27
                                                                                                 Final Report
                                                             End-Term RAP Impact Evaluation of Land Acquisition and
                                                           R&R Implementation for EDFC-1 (Khurja – Bhaupur Section)


4.2       Lessons Learnt

      (a) Displaced persons/families who were not willing to relocate after the expiry of advance notice
          period posed challenges. Except few cases, relocation support was observed to be limited to
          disbursement of compensation amount and R&R assistance. To the best possible extent, an
          appropriate community system (involving local government bodies, social activists, knowledgeable
          persons) for smooth relocation of displaced persons/families should be developed for relocation
          purposes. Counselling support should be provided in order to minimize the inherent hardship faced
          by PAPs during relocation.

      (b) Relocation Support to Informal Settlers (NTH): As per EM-2011, informal settlers were eligible for
          structure compensation and R&R assistance. The study observed a case of Douru Chandpur village,
          Aligarh wherein the displaced informal settlers had not had any planned relocation site. The policy
          document (i.e. Acts/Entitlement Matrix 2011) does not have any provisions in such cases as
          elaborated above. As per the New Entitlement Matrix 2015, “those occupying village common
          lands/abadi lands prior to 1961 shall be eligible to be treated as ‘regularised land holders’ as
          permitted by law and shall be provided with alternative land or site allowance equivalent to land
          compensation”. This provision was not included in the EM 2011. Hence, the project should
          earnestly support the informal settlers whose land has been acquired and should provide
          equivalent support as in the case of title-holders to support and save their livelihoods.

      (c) Training of PAPs: DFCCIL has made very systematic arrangement for providing training to PAPs.
          Priority was given to those PAPs belonging to below-poverty-line (BPL) category through
          recognized institutes. It was observed that 60% of the trained candidates received job post-training
          and their two-month salary statements were also forwarded to DFCCIL. Many of the trainee PAPs
          rejected the job offer due to inadequacy in the remuneration offered. Many cases of protests by
          trainee PAPs were reported disrupting the overall project progress.

          Adequate communication regarding the entitlements – livelihood training related aspects requires
          to be clearly communicated to PAPs. Awareness campaigns in affected villages should be more
          transparent and should specifically include the details of proposed trainings. Post-training
          procedures adopted by the DFCCIL should be documented and disseminated in public domain.

      (d) Stamp duty redemption: Out of the total 592 requisitions for stamp duty reimbursements, 158
          (26%) were rejected due to reasons such as (i) submission of requisition after the prescribed one-
          year, (ii) land was not purchased in the name of the entitled person, and (iii) claim submitted
          against the purchase of different category of land (other than the affected land category). Project
          should consider these rejected claims and include project-affected-families as unit of entitlement
          and should also include purchase of different category of land also as eligible. The time period for
          claim should be relaxed to at last two years or till end of the RAP implementation.

      (e) Corporate Social Responsibility: CSR activities carried out in project villages are appreciative; at
          the same time require a mechanism for follow-up for ensuring sustainable delivery of benefits. It is
          also noticed that the Computer Systems provided as part of the CSR activity of DFCCIL were taken
          away by interested parties thereby denying the intended benefits to students/schools. With



                  CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST                                           Page | 28
                                                                                            Final Report
                                                        End-Term RAP Impact Evaluation of Land Acquisition and
                                                      R&R Implementation for EDFC-1 (Khurja – Bhaupur Section)


    respect to transfer of fund to district administration, the details regarding utilization of specific
    fund by the District Administration for the intended purpose was not known.

    Appropriate institutional mechanism should be in place for sustainable delivery of benefits,
    especially during the project cycle. For instance, ownership of computer systems should be
    transferred to the beneficiary school only after a specific period. Follow-up with District
    Administration should be made mandatory to ensure the utilisation specific cash transfers made.

(f) Delay in handover of encumbrance-free land: The delay in land acquisition and subsequent
    handover of encumbrance-free land were pointed out as major components included in the
    prolongation cost-claims of the Contactor. In view of this, the overall RAP implementation system
    requires strengthening in future projects and also the targets set forth for achieving right to access
    continuous stretch requires relaxation.

(g) Institutional Arrangement: A dedicated institutional structure was in place at DFCCIL HQ as well as
    in project site offices for the smooth implementation of RAP. This institutional structure was a
    strong platform which facilitated various procedures related to land acquisition, rehabilitation and
    resettlement. Staff requirements were in compliance with the RPF and existing staff has
    dedicatedly worked towards achieving the objectives of RAP.

(h) Reinstating approach roads in villages and access roads near RUBs: Focus group discussions
    carried out across locations have highlighted issues related to (i) difficulty in accessing approach
    roads, and (ii) waterlogging conditions in RUBs. Although DFCCIL has instructed the Contractor for
    case-by-case resolution, the villagers were generally not satisfied with the prevailing system. Delay
    in resolving case is rampant across project locations. Reinstating access-roads near RUBs and also
    those approach roads used for movement of construction vehicles should be made more efficient.
    The project should prepare a Restoration Plan in coordination with local governing bodies for all
    damaged approach roads and access near RUBs. The budgetary provisions along with
    responsibility of respective agencies should be clearly mentioned in the Restoration Plan.

(i) Grievance Redressal Committee: It is important to disseminate project information with emphasis
    on grievance redress mechanism among people through awareness programs.

(j) Court Cases: Considering that the disposal rate of cases in civil courts is taking long time, the
    Concurrent Monitoring Team suggested that it would be imperative to open other avenues of
    dispute resolutions like negotiations, meetings and focus consultations. Community participatory
    dispute resolution mechanism followed in one of the project locations (in Hathras district, Aligarh)
    is emulative.

(k) Delayed payment of compensation for land includes interest for the period of delay (12% per
    annum). However, delayed payment of R&R assistance does not include any such delay-interest.
    Project should take measures to provide delay-interest for R&R assistance. Resettlement Policy
    Framework should be amended accordingly.

(l) Delay in disbursement of R&R assistance varies from village to village and case to case due to
    various reasons such as delay in official procedures of line departments, delay in submission of
    requisite documents by PAPs. Project’s coordination with line departments should be

            CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST                                            Page | 29
                                                                                               Final Report
                                                           End-Term RAP Impact Evaluation of Land Acquisition and
                                                         R&R Implementation for EDFC-1 (Khurja – Bhaupur Section)


         strengthened. Timely submission of requisite documents by PAPs also helps pacing up
         disbursement of R&R assistance, for which services and support from RAP implementing agency
         should be hired.

      (m) Damages to reconstructed houses / assets: Train movements along the new alignment and
          consequent vibrations have damaged certain residential structures. In this respect, the Project
          should strengthen the post-construction surveillance through regular and more frequent site
          inspections rectifying the impacts due to train movement and also to resolve incidents of damages
          happened to re-constructed houses or other assets. Project should evolve mechanisms to organize
          informed meetings with Local Governing Bodies and community representatives.

4.3      Outstanding Issues and Suggested Action Plan

90.      Outstanding issues identified during the study have been documented along with the suggestions
for rectification. This includes (i) disbursement of payments to PAPs as compensation and R&R assistance,
(ii) community issues related to post-construction damages due to train movement and consequent
vibration, drainage and water logging issues, embankment erosion and consequent damages to agricultural
fields, safety of women during night-travel along newly constructed RUBs, damages caused to approach
roads and access to RUBs:

a)    Compensation disbursement:
         Issues: Out of 25,472 PAPs, compensation requires to be disbursed for 785 (3%) PAPs.

          Suggestions: DFCCIL should take help from local NGO or community mobilisers and organise
          camps in respective villages. Awareness to be raised among the PAPs regarding updating
          ownership details, and other documentation requirements related to payment of compensation.
          Also prepare the list of non-resident PAPs and communicate with them in consultation with local
          governing bodies.

b)    R&R Assistance:
         Issues: A total of 10,260 PAPs were identified for R&R assistance, of which disbursement is
         pending for 1,657 (16%) PAPs.

          Suggestions: DFCCIL should take help from local NGO or community mobilisers/volunteers and
          organise camps in respective villages to disburse remaining R&R assistance. Awareness to be
          raised among the PAPs regarding various documents to be submitted for processing and
          disbursement of R&R assistance.

c)    Post-construction damages to residential structures:
         Issues: In Naugaon village, Auriya and Maharara village, Hathras, partial demolition of PAP’s
         structures have resultant cracks on the remaining portion of the structure. In Kheriya village,
         Hathras, demolition of house affected the nearby house as well due to train movement and
         consequent vibration.




                  CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST                                         Page | 30
                                                                                               Final Report
                                                           End-Term RAP Impact Evaluation of Land Acquisition and
                                                         R&R Implementation for EDFC-1 (Khurja – Bhaupur Section)


         Suggestions: To avoid structure damage due to demolition, engineering code manual/ scheme
         should be prepared for the people residing parallel to the track. In case of vibration, impact of
         vibration and following procedures to minimize the impact should be taken up by the Project.

d)   Rain water along with mud from embankments damages agricultural field
         Issues: In Aat village, Kanpur Dehat & MenduKhas village, Hathras, due to rain, the mud and
         water runs-off from the track and accumulated in the agricultural field of the PAPs resulting in
         damage of crops.

         Suggestions: DFCCIL should inspect such cases along the alignment. To minimise the mud and
         water run-off provision for construction of Gabion wall, Toe wall, stone pitching, turfing should be
         adopted.

e)   Safety of Commuters, especially women
         Issues: In Alipur village, Aligarh, community people were concerned about the safety of
         commuters, including women who were using the RUB especially during night.

         Suggestions: DFCCIL/ Contractor should undertake installation of street lights and provide access
         facilities (earthen road or footpaths) under their CSR activities. Alternatively, DFCCIL should
         forward the matter to the State Government/ District Administration to resolve the issue.

f)   Water Logging in RUB and drainage problem
        Issues: RUB and stagnant water issue was reported in many places. In Jatanpur Chikavati village,
        Aligarh, pond got severed due to track alignment and the rainwater accumulated and run-off to
        residential area impacting 20-25 houses. In Kheriya village, Hathras, soil run-off and water logging
        damaged the religious structures. In Douru Chandpur village, Aligarh, disruption of drainage due
        to alignment resulted in water logging on the road leading to nearby school.

         Suggestions: Contractor should install dewatering pumps during the O&M period and the same
         should be entrusted to the local governing bodies or community representatives. Permanent
         solution to the problem should be evolved in consultation with PWD/local governing body.




                CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST                                           Page | 31
Annexures
                                                                                                    Final Report
                                                               End-Term RAP Impact Evaluation of Land Acquisition and
                                                             R&R Implementation for EDFC-1 (Khurja – Bhaupur Section)




                                                                                                         Annexure-I
                                        Project details factsheet of EDFC 1
                                               Bhaupur-        Etawah Bypass
                                                                                     Chamrola
                                                Etawah        End to Chamrola
                                                                                   Bypass End to
                Description                   Bypass End         Bypass End                                Total
                                                                                   Khurja Section
                                                Section        Section EDFC 1
                                                                                      EDFC 1
                                                EDFC1
Project Overview
Total PAPs (Nos.)                                 8946              7326                9200               25472
Title Holders PAPs (Nos.)                         8852              7326                9118               25296
Non-Title Holders PAPs (Nos.)                       94                0                   82                176
PAPs Loosing structure (Nos.)                      107               203                 313                623
Total displaced and relocated PAFs (Nos.)          103               210                  55                368
Contract Value (in INR Crores)                   132.94             925.9              1012.14              2071
                                              14th March,
Commencement Date                                 2013         14th May, 2013      14th May, 2013
                                               22th April,
Contractual Completion Date                       2017         21th May, 2017      22th April, 2017
                                             TATA-ALDESA      TATA-ALDESA          TATA-ALDESA
Contractor
                                             "JV"             "JV"                 "JV"
                                             SAI-TYPSA
PMC Engineer                                                  SAI-TYPSA "JV"       SAI-TYPSA "JV"
                                             "JV"
Start Chainage                                  1040 Km           1170 Km             1266 Km
End Chainage                                    1170 Km           1266 Km             1370 Km
Length Parallel (in km)                             95               72                  69                 236
Bypass Length (in km) (Detour)                    40                29.56                 38              107.56
No. of Villages                                  110                 76                  100               286
No. of Districts                                   3                  2                   2                 7
Details of Structures
Total ROB’s (in No.)                              10                  8                  2                  20
ROB’s Under Construction (in No.)                  9                  3                  2                  14
ROB’s Yet to be started (in No.)                   1                  0                   -                 1
Total RUB’s (in No.)                              15                  18                 20                 53
RUB’s Under Construction (in No.)                  1                  4                  0                  5
Junctions Station (in No.)                         1                  1                  2                  4
Crossing Station (in No.)                          3                  2                  1                  6
Level Crossing (in No.)                           27                  28                 32                 87

Private Land (in ha.)                           497.75             313.97              377.03             1188.75
Government Land (in ha.)                        77.57                38                35.02              150.59
Total Land (in ha.)                             575.32             352.43              412.05             1339.8
PAPs (in No.)                                    8946               7326                9200               25472
As per UP State Policy
Land Acquired in ha.                             4.50                 7                   0                 4.72
PAPs (in No.)                                    330                  5                   0                 335
Compensation Disbursement Details
Award Area (in ha.)                             497.75             311.76              368.85             1178.36
PAPs (in No.)                                    8929               7107                8651               24687
Award Amount (in crore)                         225.22             195.8               298.36             719.38




                  CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST                                              Page | 1
                                                                                               Final Report
                                                           End-Term RAP Impact Evaluation of Land Acquisition and
                                                         R&R Implementation for EDFC-1 (Khurja – Bhaupur Section)




                                                                                                   Annexure II
                                            Detailed scope of work
A detailed scope of work was adopted for the proposed assignment. The detailed scope includes:
       i.    Socio-economic Impacts: This scope of the assignment study outlined the comparative
             background of project affected households during current (study) period and baseline period
             at RAP stage. This formed the background for evaluation of project impacts with respect to
             relevant parameters like changes in demographic profile, income status, debts status,
             occupation pattern, housing conditions, asset ownership pattern, cropping pattern, living
             standard, accessibility of basic amenities, etc. resulting for the implementation of LA and R&R
             acts/policies (both old and new as applicable).

       ii.   Land Acquisition Process and Compensation Payments: This part of the study encompassed
             the evaluation of various stages of private land acquisition with respect to civil contract work
             schedule and assessment of reasons for delay in land handing over of encumbrance free land
             to the contractor as per the contract provision. It also present the comparison of actual land
             hand over timing with the original contract schedule, impacts on construction due to delay in
             land acquisition, compensation payment to contractors due to non-handing over of land as per
             contract provision and implications on project due to delay in land handing over. It also covers
             the various compensation related aspects including adequacy to replace lost assets, way of
             spending compensation amounts; current status of disbursement of payments for land
             acquisition; status of payment for pending compensation and R&R assistance; methods of
             finalization and comparison of compensation rates under the old act, new act and direct
             purchase policy; satisfaction of PAPs on compensation rates and payments including PAPs who
             have not taken compensation due to dissatisfaction of rates.

      iii.   R&R Process: This activity focused on the various components of R&R process covering both
             BPL and non BPL displaced families to understand the resettlement arrangements/alternative
             arrangements that were made for the displaced families including various types of livelihood
             support provided from the project to re-establish their housing as per New Entitlement matrix
             (EM) effective from January 1st 2015. It also provided detailed information on comparison of
             displacement methods adopted under the RFCT-LARR Act 2013 and direct purchase policy as
             well as assessment of satisfaction status of PAPs on R&R payments and resettlement support
             provided to them.

      iv.    Cost of Land Acquisition and Resettlement: This section comprised of analysis of costs
             involved for various actions associated to land acquisition and resettlement as well as
             comparison with the overall project cost to draw conclusions on cost allied to land acquisition
             and resettlement.

       v.    Grievance Committee’s Impact: The present assignment analyzed the functions and
             effectiveness of the various levels of Grievance Redressal Committee (i.e. DFCCIL, District and


                 CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST                                           Page | 2
                                                                                         Final Report
                                                     End-Term RAP Impact Evaluation of Land Acquisition and
                                                   R&R Implementation for EDFC-1 (Khurja – Bhaupur Section)


       Senior level committees) formed for resolving the grievances associated with land acquisition
       and RAP implementation. It also focused on the outcomes of grievances redressed in terms of
       the PAPs that have benefitted and drew lessons for the improvement of existing mechanism. It
       also included the assessment of satisfaction status and feedback of PAPs on performance of
       various levels of Grievance Redressal Committees. At this stage the study also assessed the
       appeals to arbitrator and cases in court on various aspects of Land Acquisition and
       Resettlement & Rehabilitation implementation.

vi.     Local Employment: This study involved coordination with various contractors hired for the
       project construction to understand the local employment opportunities provided to the PAPs
       by them, including number of man days/months of jobs and how the local people got
       benefitted from the jobs was also be documented. In this study, interviews were conducted
       with some PAPs who have worked with the contractors to know their views and to assess their
       satisfaction with employment conditions, wages and facilities provided to them by the
       contractors.

vii.   Implementation Outcomes: In this stage the overall outcome of the proposed study has been
       summarized covering all the above mentioned aspects related to land acquisition,
       resettlement, impacts of both title and non-title holders, cost incurred for various activities,
       staffing, PMC, NGOs and Social and Environment Safeguard Monitoring and Review
       Consultancy (SESMRC) role, grievance redressal mechanism, etc. This also covered some of the
       grievance cases (both positive & negative), lessons learnt, innovations made and challenges
       faced during the implementation of project. Based on this impact evaluation findings some
       follow-up remedial measures as required have also been proposed to meet out the objective
       of R&R implementation and to monitor the outstanding actions (if any) beyond the impact
       evaluation study.




           CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST                                           Page | 3
                                                              Final Report
                          End-Term RAP Impact Evaluation of Land Acquisition and
                        R&R Implementation for EDFC-1 (Khurja – Bhaupur Section)




CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST                           Page | 4
                                                                                                                        Final Report
                                                                                 End-Term RAP Impact Evaluation of Land Acquisition and
                                                                               R&R Implementation for EDFC-1 (Khurja – Bhaupur Section)



                                                                                                                          Annexure-III

                 End Term Impact Evaluation Survey Questionnaire [Project Affected Persons]

Dedicated Freight Corridor Corporation of India Limited                                   Form No. __________Date____________
[A Government of India (Ministry of Railways) Enterprise]
End-Term Impact Evaluation of Land Acquisition and R&R
                                                                                          Name of Investigator_____________________
Implementation for EDFC-1 (Khurja-Bhaupur Section)

                                                                                          Name of Supervisor______________________
Category (TH/NTH/BPL/SC/ST/Vulnerable):______________________________________________________________________

ID No. & Name: ___________________ Gender (M/F):________ Govt. ID No. (AADHAR/Voter/PAN/etc.):____________________

Mobile No.: _________________________Village: _______________________________Tehsil: __________________________

District: ____________State: _________EDFC 101/102/103:_________Chainage:_______________Parallel/Detour: __________

GPS Tagging:             Location of affected land: ____________________________________________________________________

                         Residential location of PAP: __________________________________________________________________

1. Compensation and R&R Assistance Received

 i     If any compensation amount is pending to receive?                              1           YES               2             NO

 ii    If yes, for which item compensation amount is pending?                         1          LAND               2          STRUCTURE

iii    If any R&R Assistance is pending to receive?                                   1           YES               2             NO

       If you ever faced any difficulty in receiving the compensation amount
iv                                                                                    1           YES               2             NO
       / R&R assistance?

 v     If Yes, please state the type of difficulties faced

       Whether you are satisfied with the Compensation Rate/Amount
vi                                                                                    1           YES               2             NO
       received?


vii    If any special assistance provided to differently abled people?            1        YES          2      NO          3        NA


viii   If sufficient time (3 months) given for relocation                             1           YES               2             NO

2. Utilization of Compensation Amount

       Where have you utilized/invested the maximum amount of
 i
       compensation received?

       Whether you have purchased land/asset from compensation
 ii                                                                                   1           YES               2             NO
       amount?

       If Yes, have you claimed reimbursement of stamp duty within
iii                                                                                   1           YES               2             NO
       timeframe?

vi     If yes, how much amount claimed (Rs.)


vii    If No, please state the reason

       If Reimbursement of stamp duty and registration fee rejected, state
viii
       the reason



                          CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST                                                         Page | 5
                                                                                                                     Final Report
                                                                              End-Term RAP Impact Evaluation of Land Acquisition and
                                                                            R&R Implementation for EDFC-1 (Khurja – Bhaupur Section)


3. Income Generation Activities
 i     Have you received any training?                                             1           YES              2               NO


 ii    If yes, please state the type of training and provided by whom?

iii    Did you get any job after the training                                      1           YES              2               NO

iv     If yes, please state the type of job

 v     If any employment provided by the Contractor                                1           YES              2               NO

vi     If yes, please state the type of employment / job


vii    If No, please state the reason

4. Household / Individual Income
 i     No. of Family members                                                MALE          FEMALE          CHILDREN       TOTAL


 ii    No. of earning members                                                MALE               FEMALE                TOTAL


iii    Occupation of family members                                            MALE                          FEMALE

iv     Whether there is change in occupation due to project                        1           YES              2               NO


 v     If Yes, please state the present occupation

vi     Individual Monthly Income (Rs.)                                       MALE               FEMALE                TOTAL


vii    Total Household Monthly Income (Rs.)


viii   Total Household Monthly Expenditure (Rs.)

5. Loans/Debts
 i     Have you taken any loan?                                                    1           YES              2               NO

       If yes, please state the amount (Rs.) and type (Bank/Private Money
 ii
       Lender)

iii    If you have cleared debts after receiving the compensation amount?          1           YES              2               NO


iv     If yes, please state the amount (Rs.) is pending for repayment

6. Household Facilities

 i     If any change in the total area of household                                1           YES              2               NO


 ii    If yes, please mention the change in total area of household                1     AREA INCREASED         2       AREA DECREASED

iii    Is the household having separate Kitchen Room                               1           YES              2               NO

iv     Is the household having separate Toilet                                     1           YES              2               NO

 v     Is the household having separate Bathroom                                   1           YES              2               NO

vi     Type of construction                                                   KUCCHA          PUKKA        SEMI-PUKKA    RCC STRUCTURE




                         CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST                                                         Page | 6
                                                                                                                     Final Report
                                                                                End-Term RAP Impact Evaluation of Land Acquisition and
                                                                              R&R Implementation for EDFC-1 (Khurja – Bhaupur Section)


7. Grievance Redress
 i     Have you ever submitted any grievance to GRC?                               1             YES             2             NO

 ii    If yes, please state the type of grievance

iii    Whether your grievance resolved by GRC?                                     1             YES             2             NO

       If Yes, please state that whether you are satisfied with decision of
iv                                                                                 1             YES             2             NO
       GRC?

 v     If No, please state the reason

       Have you taken service of any legal practitioners to submit the
vi                                                                                 1             YES             2             NO
       grievance

vii    Have you ever submitted any grievance to Court/Arbitrator                   1             YES             2             NO

       If yes, please state whether the Court/Arbitrator decision was
viii                                                                               1             YES             2             NO
       positive

8. Satisfaction Level
       Whether you are satisfied with the Compensation Rate/Amount
 i                                                                                 1             YES             2             NO
       received?

 Ii    If No, please state the reason

       Whether you are satisfied with the assistance provided by DFCCIL
Iii                                                                                1             YES             2             NO
       during relocation?

iv     If No, please state the reason

 v     Whether you are satisfied with the received R&R assistance?                 1             YES             2             NO

vi     If No, please state the reason


       Whether you are satisfied with the employment conditions, wages
vii                                                                                1             YES             2             NO
       and facilities provided by the Contractor?


viii   If No, please state the reason

9. Feedback/Opinion on LA and R&R processes
       Whether the LA and R&R processes benefited in improving living
 I                                                                                 1             YES             2             NO
       conditions

 Ii    If yes, please provide details how?

Iii    If No, please state the reason

       Whether Compensation amount received was adequate enough to
Iv                                                                                 1             YES             2             NO
       replace affected / lost asset?


 v     If No, please state the reason




                         CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST                                                        Page | 7
                                                                                                                        Final Report
                                                                                End-Term RAP Impact Evaluation of Land Acquisition and
                                                                              R&R Implementation for EDFC-1 (Khurja – Bhaupur Section)




                        End Term Impact Evaluation Survey Questionnaire [Control Population]
Dedicated Freight Corridor Corporation of India Limited                                  Form No. ___________Date___________
[A Government of India (Ministry of Railways) Enterprise]
End-Term Impact Evaluation of Land Acquisition and R&R                                   Name of Investigator____________________
Implementation for EDFC-1 (Khurja-Bhaupur Section)                                       Name of Supervisor_____________________

Category (TH/NTH/BPL/SC/ST/Vulnerable): ______________________________________________________________________

ID No. & Name:_______________________Gender (M/F):________ Govt. ID No. (AADHAR/Voter/PAN/etc.):________________

Mobile No.: ______________________Village: ________________________________Tehsil: ______________________________

District: _____________State: ________EDFC 101/102/103:__________Chainage:_______________Parallel/Detour: _________

GPS Tagging:           Location of affected land: _____________________________________________________________________

                       Residential location of PAP: __________________________________________________________________

1. Income & Occupation
 i    No. of Family members                                                   MALE        FEMALE         CHILDREN          TOTAL

ii    No. of earning members                                                   MALE             FEMALE                  TOTAL

iii   Occupation of family members                                               MALE                           FEMALE

iv    Whether there is change in occupation due to project                           1             YES              2               NO

v     If Yes, please sate the present occupation

vi    Individual Monthly Income (Rs.)                                          MALE             FEMALE                  TOTAL

vii   Total Household Monthly Income (Rs.)

2. Loans/Debts

 i    If any loan/debt amount (Rs.) is pending for repayment                         1             YES              2               NO

      If yes, please state the amount (Rs.) and type (Bank/Private Money
ii
      Lender)

3. Household Facilities
 i    If the household having separate Kitchen Room                                  1             YES              2               NO

ii    If the household having separate Bath Room                                     1             YES              2               NO

iii   If the household having separate Toilet                                        1             YES              2               NO

4. Feedback/Opinion on change of living condition
 i    Whether you have benefited by the project in any form?

      Whether you have purchased any land/asset (shop, etc.) in the last
ii                                                                                   1             YES              2               NO
      10 years?
      Please provide your opinion on change of living condition in the last
iii
      10 years




                       CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST                                                                Page | 8
                                                                                         Final Report
                                                     End-Term RAP Impact Evaluation of Land Acquisition and
                                                   R&R Implementation for EDFC-1 (Khurja – Bhaupur Section)


                                                                                             Annexure IV

                           Group-wise Discussion points of FGDs

1. Physically displaced people Group
       Satisfaction level and feedback of PAPs Pre & Post Displacement.
       Alternative living arrangements during displacement process.
       Status of Higher Order Assets and comparison with control population on recall basis
       Verification of Resettlement site
       Other benefits provided by the DFCCIL.
       Any comments/Suggestions/recommendation for future planning

2. PAPs received compensation and R&R assistance
       Satisfaction level of PAPs regarding Land & Assets rates decided by authority.
       Satisfaction level of PAPs received Compensation and R&R Assistance.
       Status of Support provided to all PAPs.
       Views regarding entitlement Category as per Entitlement matrix.
       Status of Grievance case filed, if any.
       Any comments/Suggestions/recommendation for future planning

3. PAPs involved in direct land purchase process
       Satisfaction level of PAPs involved in direct land purchase process.
       Satisfaction level of PAPs regarding relocation of new resettlement site.
       Details of support provided to PAPs relocated to new resettlement site.
       Details of Support provided to all PAPs.
       Any comments/Suggestions/recommendation for future planning

4. PAPs refused to accept the compensation and R&R assistance
       Reasons for refusing to take the compensation and R&R assistance.
       Any Arbitration/Court case filed
       Status of Case/decision.
       Satisfaction level regarding decision.
       Any comments/Suggestions/recommendation for future planning

5. PAPs filed grievance cases
       Status of grievance case filed
       Status of resolved cases.
       Satisfaction level regarding decision.
       Duration of resolving cases.
       Any comments/Suggestions/recommendation for future planning




            CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST                                          Page | 9
                                                                                        Final Report
                                                    End-Term RAP Impact Evaluation of Land Acquisition and
                                                  R&R Implementation for EDFC-1 (Khurja – Bhaupur Section)


6. Community representatives for Common Property Resources (CPRs)
       Types of CPR impacted
       Issues raised by the community
       Relocation/Reconstruction status of CPRs.
       Quality of construction of CPRs
       Satisfaction level of Community.
       Any comments/Suggestions/recommendation for future planning.

7. PAPs belongs to vulnerable groups (SC, ST, BPL, WHH and Differently abled)
       Satisfaction level regarding disbursement process of LA and R&R.
       Difficulty faced during process.
       Additional benefits/support provided by the DFCCIL.
       Any comments/Suggestions/recommendation for future planning.

8. Title holder (TH) PAPs and Non-title holder (NTH) PAPs
         Benefits/support provided to TH and NTH as per Entitlement Matrix.
         Satisfaction level of TH and NTH PAPs regarding compensation and R&R Assistance.
         Any comments/Suggestions/recommendation for future planning.

9. PAPs employed by the contractor
        Details of Employment provided by contractor.
        Type of Employment provided by the contractor.
        Satisfaction level of PAPs after employment.
        Status of income after employment.
        Training provided by the DFCCIL.
        Any comments/Suggestions/recommendation for future planning.

10. FGD with women groups
        Difficulties faced during implementation period.
        Status of employment before and during project implementation.
        Type of occupation
        Training provided by the DFCCIL.
        Status of income before and after project implementation.
        Any comments/Suggestions/recommendation for future planning.

11. FGDs with DFCCIL
        Land Handing over details from DFCCIL and Contractor
        Alternative living arrangements during displacement process.
        Other benefits provided by the DFCCIL.
        Budget allocated for LA and R&R
        Details of assistance provided to PAPs relocated to new resettlement site.
        Status of Arbitration/Court case filed and resolved

            CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST                                        Page | 10
                                                                                        Final Report
                                                    End-Term RAP Impact Evaluation of Land Acquisition and
                                                  R&R Implementation for EDFC-1 (Khurja – Bhaupur Section)


          Status of grievance case filed and resolved
          Relocation/Reconstruction status of CPRs (Pre & Post Implementation).
          Benefits/support provided to TH and NTH as per Entitlement Matrix.
          No. of Women PAPs
          Training provided by the DFCCIL.
          Details of Employment provided by contractor.
          Type of Employment provided by the contractor
          Status of income after employment.
          Status of Women employment before and during project implementation.
          Status of Women income before and after project implementation.
          CSR activities adopted by the Contractor/DFCCIL.

12. FGDs with PMC
        Land Handing over details
        Alternative living arrangements during displacement process.
        Other benefits provided by the DFCCIL.
        Details of assistance provided to PAPs relocated to new resettlement site.
        Status of Arbitration/Court case filed and resolved
        Status of grievance case filed and resolved
        Relocation/Reconstruction status of CPRs (Pre & Post Implementation).
        Benefits/support provided to TH and NTH as per Entitlement Matrix.
        No. of Women PAPs
        Training provided by the DFCCIL.
        Details of Employment provided by contractor.
        Type of Employment provided by the contractor
        Status of Women employment before and during project implementation.
        Status of Women income before and after project implementation.
        CSR activities adopted by the Contractor/DFCCIL.

13. FGDs with Contractor
        Land Handing over details
        Civil work Schedule of contractor
        Comparison between Land Handing over and Civil work Schedule of contractor
        Alternative living arrangements during displacement process.
        Other benefits provided by the DFCCIL.
        Details of assistance provided to PAPs relocated to new resettlement site.
        Relocation/Reconstruction status of CPRs (Pre & Post Implementation).
        Status of Employment provided by contractor.
        Type of Employment provided by the contractor
        Status of Women employment before and during project implementation.
        Status of Women income before and after project implementation.


            CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST                                        Page | 11
                                                                                        Final Report
                                                    End-Term RAP Impact Evaluation of Land Acquisition and
                                                  R&R Implementation for EDFC-1 (Khurja – Bhaupur Section)


          CSR activities adopted by the Contractor.
          Whether contract awarded without paying complete land compensation

14. FGDs with NGO
        Alternative living arrangements during displacement process.
        Other benefits provided by the DFCCIL.
        Details of assistance provided to PAPs relocated to new resettlement site.
        Status of Arbitration/Court case filed and resolved
        Status of grievance case filed and resolved
        Relocation/Reconstruction status of CPRs (Pre & Post Implementation).
        Benefits/support provided to TH and NTH as per Entitlement Matrix.
        No. of Women PAPs
        Training provided by the DFCCIL.
        CSR activities adopted by the Contractor/DFCCIL.

15. FGDs with Control Population in maximum impacted villages including Detour Section
        Occupation Status
        Income Status
        Living Condition
        Status of Landholding and Higher order Assets
        Overall Perception of Control Population
        Status of Loan/Debts
        Status of Household Facilities
        Feedback/Opinion on change of living condition

16. Discussion with complainants of Lot-101
         Status of payment of compensation
         Status of Arbitration and Court Cases filed/Disposed
         Satisfaction of PAPs from Court Decisions




            CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST                                        Page | 12
                                                                          Final Report
                                      End-Term RAP Impact Evaluation of Land Acquisition and
                                    R&R Implementation for EDFC-1 (Khurja – Bhaupur Section)



                                                                              Annexure-V
         Photographs of Focus Group Discussion
                1.   Differently Abled People




            Sukhanpur village, Auraiya District




               Barhan village, Agra District




       Kirthra Mohmadpur village, Firozabad District




CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST                                      Page | 13
                                                                                         Final Report
                                                     End-Term RAP Impact Evaluation of Land Acquisition and
                                                   R&R Implementation for EDFC-1 (Khurja – Bhaupur Section)


                 2.   PAPs received Compensation and R&R Assistance




                  Doruchandpur and Keshopur villages, Aligarh District




Datoji village, Firozabad District                      Dokeli village, Firozabad District




                           Behta village, Kanpur Dehat District
     3.    PAPs whose Land acquired as per UP Direct Land Purchase Policy, 2015




                      Shahpur Derapur village, District Kanpur Dehat



          CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST                                           Page | 14
                                                                                            Final Report
                                                       End-Term RAP Impact Evaluation of Land Acquisition and
                                                     R&R Implementation for EDFC-1 (Khurja – Bhaupur Section)




                                4.    PAPs filed Grievance Cases




 Datoji village, Firozabad district                      Latifpur village, Firozabad district




Dokeli village, Firozabad District                          Barhan village, Agra District
            5.   Vulnerable Groups (SC, ST, BPL, WHH and Differently Abled)




Phaphood village, Auraiya District                        Purwasa village, Auraiya District




 Datoji village, Firozabad District                      Bankat village, Firozabad District


        CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST                                               Page | 15
                                                                                         Final Report
                                                     End-Term RAP Impact Evaluation of Land Acquisition and
                                                   R&R Implementation for EDFC-1 (Khurja – Bhaupur Section)




     Dokeli village, Firozabad                      Surehara Mustkil village, Etmadpur, Agra


6.   Titleholders (THs- Formal settlers) and non-titleholders (NTHs-informal settlers)




                  Doruchandpur village, Aligarh District (FGD with NTHs)




                      Khera Khushkhabar village, Aligarh District




                      Kirthra Mohmadpur village, Firozabad District




        CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST                                             Page | 16
                                                                                            Final Report
                                                        End-Term RAP Impact Evaluation of Land Acquisition and
                                                      R&R Implementation for EDFC-1 (Khurja – Bhaupur Section)




                                   7.    Civil Work Contractor




Contractor’s office at Etawah District              Contractor’s office at Gari Bhakti village, Agra
                                                                        District
                            8.   PAPs Employed by the Contractor




                          Hayatpur Bajheda village, Aligarh District




             Dariyapurva village, Hathras District - PAPs provided training by ITI




          CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST                                                 Page | 17
                                                                                         Final Report
                                                     End-Term RAP Impact Evaluation of Land Acquisition and
                                                   R&R Implementation for EDFC-1 (Khurja – Bhaupur Section)




                           Mandrak village, Aligarh District




                       Alampur Jhapta village, Firozabad District




                          Medhidudhi village, Etawah District


9.   Community Representatives for Common Property Resources and Religious Structures




                            Kheriya village, Hathras District



          CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST                                           Page | 18
                                                                                              Final Report
                                                          End-Term RAP Impact Evaluation of Land Acquisition and
                                                        R&R Implementation for EDFC-1 (Khurja – Bhaupur Section)




 Temple in Kheriya village, Hathras (to be            Old well in Kheriya village, compensation
demolished- compensation provided to the                         provided to the owner
          owner of the temple)




 Temple constructed after relocation of the existing temple in Daruchandpur village, Aligarh




                             Nagla Goal village, Agra District




                               Latifpur village, Firozabad District


             CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST                                             Page | 19
                                                                            Final Report
                                        End-Term RAP Impact Evaluation of Land Acquisition and
                                      R&R Implementation for EDFC-1 (Khurja – Bhaupur Section)




        Graveyard, Raipalpur, Kanpur Dehat District


                   10. Control Population




       Hajipur Chauhatta village, Aligarh District




             Dokeli village, Firozabad District




              Datoji village, Firozabad District




CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST                                        Page | 20
                                                                            Final Report
                                        End-Term RAP Impact Evaluation of Land Acquisition and
                                      R&R Implementation for EDFC-1 (Khurja – Bhaupur Section)




        11. PAPs who filed Complaints to World Bank




      Complainants in Debiyapur village, Auraiya District




        Complainants in Itgaon village, Etawah District




CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST                                        Page | 21
                                                                                            Final Report
                                                       End-Term RAP Impact Evaluation of Land Acquisition and
                                                     R&R Implementation for EDFC-1 (Khurja – Bhaupur Section)



                                                                                              Annexure VI
                         Assessment of timeline based on village level case studies

                               Time to be     Time Taken - 20A to 20 E          Time Taken - 20E to 20 F
                                 taken              notification                      notification
S.No.     Sample Cases
                                                              Percentage           No. of        Percentage
                              No. of Days     No. of Days
                                                                  (%)              Days              (%)

  1          Village 1            365            320                88              335               92

  2          Village 2            365            328                90              291               80

  3          Village 3            365            111                30              193               53

  4          Village 4            365            277                76              323               88

  5          Village 5            365            216                59               74               20

  6          Village 6            365            201                55              348               95

  7          Village 7            365            226                62              128               35

  8          Village 8            365            314                86              310               85

  9          Village 9            365            200                55               47               13

 10         Village 10            365            332                91              266               73

 11         Village 11            365            360                99              238               65

 12         Village 12            365            360                99              238               65

 13         Village 13            365            360                99              238               65

 14         Village 14            365            360                99              238               65

  Average Time taken           365 days                283 days                           233 days
Source: DFCCIL, 2019




               CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST                                        Page | 22
                                                                                                Final Report
                                                            End-Term RAP Impact Evaluation of Land Acquisition and
                                                          R&R Implementation for EDFC-1 (Khurja – Bhaupur Section)



                                                                                                  Annexure-VII
                                 Land Provided to NTH for Relocation




Land provided to NTH for relocation and PAPs constructed structures from the R&R assistance provided to
                                    them in Village Dourauchanpur




                CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST                                            Page | 23
                                                                                          Final Report
                                                      End-Term RAP Impact Evaluation of Land Acquisition and
                                                    R&R Implementation for EDFC-1 (Khurja – Bhaupur Section)



                                                                                       Annexure-VIII (A)

                               Excerpts of Camps organized for PAPs




    DFCCIL published on 02-05-19 regarding         Camp was organized on 10-05-19 by DFCCIL in
    compensation in newspaper Amar Ujala           Village Navalpur,District -Agra regarding R&R
                                                                    Assistance




Camp organized on 13-04-19 by DFCCIL in Village   Camp organized on 09-05-19 by DFCCIL in Village
  Nizampur, District- Firozabad regarding R&R     Rasulpur,District- Agra regarding R&R assistance
          assistance and Relocation.




               CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST                                        Page | 24
                                                                                        Final Report
                                                    End-Term RAP Impact Evaluation of Land Acquisition and
                                                  R&R Implementation for EDFC-1 (Khurja – Bhaupur Section)



                                                                                     Annexure-VIII (B)

                  Satisfaction level of PAPs with respect to Awareness Camps

Majority of the PAPs (60%) were aware about the act/policy as per which there land was acquired.
Out of the sampled PAPs, 74% intimated to have received the compensation amount. The PAPs
who received compensation as per the Old Act were not satisfied with the land rates as compare
to the PAPs whose land was acquired as per New Act. The disbursement of compensation to the
PAPs was done through cheques as mentioned in the RAPs. For disbursement of compensation,
where NGO was available, 36 camps were organized in 34 villages by the DFCCIL officials in the
districts of Firozabad and Agra. A total 307 PAPs attended camps. After holding camps, 1757
applications were received for R&R assistance requisition, out of which 1238 applications were
processed for payment and 519 applications were not eligible. As per the status received from
DFCCIL HQ, out of the eligible PAPs, assistance was disbursed to 746 PAPs and payment to the
remaining PAPs is under process.




              CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST                                      Page | 25
                                                              Final Report
                          End-Term RAP Impact Evaluation of Land Acquisition and
                        R&R Implementation for EDFC-1 (Khurja – Bhaupur Section)




CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST                          Page | 26
                                                                                               Final Report
                                                           End-Term RAP Impact Evaluation of Land Acquisition and
                                                         R&R Implementation for EDFC-1 (Khurja – Bhaupur Section)



                                                                                                 Annexure- IX

                                     Training provided to the PAPs

Another identified institute which imparted training was the Technical Services Centre of the National
Small Industries Corporation Ltd., and situated in Industrial Estate, Aligarh, UP. Training was provided on
electrical home appliances, electrician, and entrepreneurship-orientation. The duration of the training was
one month (from 02.12.2013 to 02.01.2014). The trainees informed that the DFCCIL had sponsored their
training on free-of-cost basis. However, none of the trainees received any job as promised by DFCCIL prior
to the training. Total 60 such trainees had protested in front of the Office of DFCCIL at New Delhi but their
grievances remained unresolved.

The PAPs demanded for jobs after training. Excerpts from the newspaper are presented below regarding
demand of employment:

                       Excerpts of Newspaper regarding provision of employment




                CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST                                           Page | 27
                                                                             Final Report
                                         End-Term RAP Impact Evaluation of Land Acquisition and
                                       R&R Implementation for EDFC-1 (Khurja – Bhaupur Section)




Source: www.mospi.nic.in




               CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST                          Page | 28
                                                                                                 Final Report
                                                             End-Term RAP Impact Evaluation of Land Acquisition and
                                                           R&R Implementation for EDFC-1 (Khurja – Bhaupur Section)



                                                                                                     Annexure-X

            Land Related Hindrances or Stoppage of Civil Works by Community People

                                              Land Related Hindrances
Sl. No.
                                 Contractor’s Communication                                      Categorization
 1.
          Not able to carry out the collection of data with respect to Geotechnical           RoW
          investigation and topographical survey due to resistance of locals/RoW
          pillars not fixed in various locations like Tundla detour, Firozabad detour,
          etc. (communication dated 01.07.2013)
 2.
          Due to non-payment issues to the villagers, tree-cutting activity was Compensation
          interrupted in Firozabad district (communication dated 20.09.2013)
 3.
          Near   IR     Ch.Km   1235/16-17,    villagers    demanded       provision     of RUB
          underpass/bridge to cross DFCC line and showed violent protest on the said
          issued and stopped the work (communicated dated 20.06.2014)
 4.
          Land owners intervened and stopped the work at Ch.Km 10+300 to 10+500               Compensation
          in Tundla Detour due to the issue of compensation for land acquisition with
          DFCCIL (communication dated 26.06.2014)
 5.
          Stoppage of work by land owners while doing Minor Bridge No.69 at IR                Compensation
          Ch.Km 1194/5-7 and requested to resolve the land issue at the earliest
          (communication dated 07.08.2014)
 6.
          Villagers continued to stop the work due to issues related to compensation Compensation
          for land with DFCCIL in Ch.Km 8+500 to 8+750 in Firozabad detour
          (communication dated 27.08.2014)
 7.
          Work was stopped by the villagers, at Ch.Km 1185+760 to 1186+700, until             Compensation
          the payment/compensation was made to them (communication dated
          01.09.2014)
 8.
          Villagers had stopped the work at Ch.Km 6+600 to 6+800 as the villagers             RUB
          were demanding RUB at Ch.6+630 instead of already proposed location at
          Ch.6+833 (communication dated 12.09.2014)
 9.
          Stoppage of work by villagers at IR Ch.Km 1197 to 1198+500, as the villagers        Job offers
          had been promised by DFCCIL to provide jobs in the Railways/DFCCIL at the
          time of land acquisition. Villagers were demanding to provide jobs as
          promised until then they would not allow to start the work (communication
          dated 23.09.2014)



                 CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST                                            Page | 29
                                                                                             Final Report
                                                         End-Term RAP Impact Evaluation of Land Acquisition and
                                                       R&R Implementation for EDFC-1 (Khurja – Bhaupur Section)



                                             Land Related Hindrances
Sl. No.
                                Contractor’s Communication                                   Categorization
 10.
          Work at IR Ch.1184 to 1185+700 in Yadavpur village, Etawah, had been Compensation
          stopped by the villagers on account of payment of compensation at a
          revised rate (communication dated 26.09.2014)
 11.
          Incurred problems relating to land acquisition for Gata no.356 at IR Ch.Km      Compensation
          1197. Villagers had stopped the work for reasons like less compensation
          against land acquisition (communication dated 18.12.2014)
 12.
          Villagers had stopped the excavation activity of RUB RC-2 at Ch.Km RUB
          3+355.800 demanding to increase the size of RUB (communication dated
          24.02.2015)
 13.
          Villagers had stopped the work of minor structures RUB 5A at Ch.Km 6+630        RUB
          for their demand to increase the size of RUB (communication dated
          13.03.2015)
 14.
          Affected land owners had stopped the work at Ch. Km 3+540 in Kuberpur Compensation
          due to the issue of compensation for land or fixing of RoW (communication
          dated 04.06.2015)
 15.
          Work was stopped by the villagers of nearby village Basath of Minor Stagnant water
          Structure due to the construction of the bridge will cause stagnation of
          water in their farm (communication dated 02.07.2015)
 16.
          Local villagers had stopped the ongoing work in Firozabad Detour for their      RUB
          demand of RUB (communication dated 07.08.2015)
 17.
          Land owner was not allowing to do the work on the pretext of wrongly            Wrong acquisition
          acquired land from Ch.Km 6+680 to 8+180 at Bhikanpur Village
          (communication dated 11.08.2015)
 18.
          Villagers had stopped the work of Minor structure – TD RUB-5 for their RUB
          demand to increase the size of RUB (communication dated 22.08.2015)
 19.
          Stoppage of work at TD RC-2 by nearby villagers for their demand to RUB
          increase size of RUB (communication dated 22.08.2015)
 20.
          Land owners where not allowing to proceed with the work in between Compensation
          Ch.Km 6+900 to 7+300 (communication dated 30.11.2015)
 21.
          Could not do the work at Ch.Km 1239+585 to 1239+598 due to the fencing          Compensation
          done by the land owner as he had not been paid compensation for the
          acquired land (communication dated 12.01.2016)


                CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST                                         Page | 30
                                                                                             Final Report
                                                         End-Term RAP Impact Evaluation of Land Acquisition and
                                                       R&R Implementation for EDFC-1 (Khurja – Bhaupur Section)



                                             Land Related Hindrances
Sl. No.
                                Contractor’s Communication                                   Categorization
 22.
          Villagers on 05.02.2016 sat on ‘Dharna Pradarshan’ on prepared formation Access Road
          bed in DFC RoW at Ch.Km 1211+890 at Shikohabad Station area and
          stopped the work of ballast laying for whole day by stopping all machinery
          and vehicle movement for their demand of road (communication dated
          06.02.2016)
 23.
          Villagers on 16.02.2016 sat on ‘Dharna Pradarshan’ on prepared formation Access Road
          bed in DFC RoW at Ch.Km 1213/11 at Shikohabad Station area and stopped
          the formation work at pond area for whole day by stopping all machinery
          and vehicle movement for their demand of road (communication dated
          17.02.2016)
 24.
          Violent protestors had interrupted IR train operation as the protestors sat Access Road
          on IR track near 1213/11 for their demand of underpass and road
          (communication dated 22.02.2016)
 25.
          An incident of ‘Dharna Pradarshan’ on 08.03.2016 in Firozabad Detour Compensation
          (communication dated 09.03.2016)
 26.
          Villagers had stopped the work at Ch.Km 4+100 (Firozabad Detour), at RUB
          Ch.Km 0+388.858 (Tundla Detour) at Ch.Km6+058+042, due to their
          demand of increase in size of structures (communication dated 14.06.2016
          and 15.06.2016)
 27.
          Stoppage of work by farmers since 23.07.2016 for unsettled compensation compensation
          payment for their acquired land in Etawah District (IR Ch.Km 1186-1170).
          Villagers had also stopped vehicles transporting blanket material and even
          not allowing to unload the blanketing material (communication dated
          27.07.2016)
 28.
          Farmers attacked the sub-contractor while doing installation of Borewell at Compensation
          Ch.Km 1177+090 (communication dated 09.08.2016)
 29.
          Works being stopped due to commotion created by farmers protesting Compensation
          construction of Retaining Wall at Barhan Detour and formation work at
          Kuberpur Link (communication dated 21.06.2017)
 30.
          While evicting hindrances in Barhan Detour from Ch.3200 to Ch.3300, Compensation
          constrained to stop eviction due to non-realization of compensation
          payment to land losers – limiting the eviction to 50% (communication dated
          03.08.2017)


                CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST                                         Page | 31
                                                                                               Final Report
                                                           End-Term RAP Impact Evaluation of Land Acquisition and
                                                         R&R Implementation for EDFC-1 (Khurja – Bhaupur Section)



                                              Land Related Hindrances
Sl. No.
                                 Contractor’s Communication                                    Categorization
 31.
          Ongoing works had been stopped in Kuberpur (Ch.Km 4100-4520) due to Compensation
          protest   by   land   losers   on   account   of   compensation       payment
          (communication dated 19.08.2017)
 32.
          Land loser of Gata No. 123 were forbidding the JV to take the works at            Compensation
          Ch.Km 11+123, as requisite compensation was yet to be disbursed which
          further drastically hampered backfilling works and formation works
          (communication dated 25.09.2017)
 33.
          Requisite compensation was yet to be disbursed to the land losers, which Compensation
          prohibited the works in Ch.Km 5+500 to Ch.Km 5+600 (Kuberpur)
          (Communication dated 07.10.2017)
 34.
          ‘No-objection’ from the landlord had been obtained for the execution of           RoW difference
          works at ROW from Ch.Km 4+800 to Ch.Km 5+040, however the RoW
          differed from the initial proposed RoW as it had been shifted 6m away
          towards RHS and corresponding RoW pillars had also been shifted
          (communication dated 28.10.2017)
 35.
          Villagers of Nagla Chenkur had stopped the works of TD RUB-4A and New RUB
          Tundla yard at Ch.Km 4+590 (Tundla Detour) (communication dated
          28.12.2017)
 36.
          At Kuberpur link, alignment was changed from Ch.2+900 to Ch.3+600 due to          Alignment change
          land acquisition issue (communication dated 27.10.2017)
Source: Contractor’s Documents Accessed during the Survey




                CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST                                           Page | 32
                                                                                               Final Report
                                                           End-Term RAP Impact Evaluation of Land Acquisition and
                                                         R&R Implementation for EDFC-1 (Khurja – Bhaupur Section)




                                                                                                   Annexure-XI
                           Onsite Observations of Common Property Resource

Discussions with the DFCCIL officials revealed that all the affected CPRs were relocated, except one Temple
in Kamalpur village, Kanpur Dehat district (LC-98). This Temple was built in private land by the land owners.
The temple was located in the Aabadi land and the owners of the temple have now been declared as
titleholders. DFCCIL is in process to take consent from respective land owners and proceeded for
acquisition of the same under Direct Land Purchase Policy. Discussion with the land owners revealed that
relocation of the Temple will be decided once they receive compensation from DFCCIL.

Construction of a new graveyard in place of an affected graveyard (Gata no. 375) which was categorised as
uncharted was being carried out by DFCCIL with active participation of community people. The new as well
as the affected graveyard were located in Raipalpur village in Kanpur Dehat district. Compensation for
affected graves was provided to five (5) PAPs, totaling to amount Rs.1,63,500 (Rs.32,700 each). The
aggregate contract for relocation of the affected graveyard amounts to Rs. 5,48,677. DFCCIL had taken up
the relocation work with the local community and construction works were progressing during the end-
term impact evaluation survey. The affected graveyard was located in an area of 0.15 ha. of State
Government land. Alternatively, new piece of land was sanctioned by the District Administration and the
cost of land (i.e. Rs.26.28 lakh) was transferred to District Administration by DFCCIL.

Location 1: Agra (village- Nagla Goal)
       The types of CPR impacted Temple includes Durga Mata Mandir, Shiv Mandir, Hanuman Mandir,
        Kitchen Room /Rosoi (1 No.), Bathroom (1 No.), Rooms (4 Nos.) with verandah, stair case for the
        access to the roof of the structure, bore well with submersible pump, landscaping with shrubs &
        flowering plants within the temple premises, fixing of celling fans (12 Nos.), fixing of brass metal
        temple bells (3 Nos.).
       Mr. Gajendra Singh, S/o Narotam Singh has donated approximately 1 Bigha of land for the
        construction of impacted Temple.
       The Contractor has not completed the works as per the scope (i.e. the items that was available in
        the impacted structures). In the year 2015 the land owner along with other villagers has also
        requested the Contractor M/s TATA-ALDESA "JV" in written to complete all the activities as per the
        scope. But the works are not yet taken up / completed by the Contractor.
       Door fitting for Kitchen and Bathroom yet to be done, fixing of ceiling fans and brass metal Temple
        bells yet to be fixed, Stair case for the access to the roof of the structure partially completed i.e.
        hand rails not yet fitted.




                CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST                                           Page | 33
                                                                                                  Final Report
                                                              End-Term RAP Impact Evaluation of Land Acquisition and
                                                            R&R Implementation for EDFC-1 (Khurja – Bhaupur Section)




                  Old temple was demolished and constructed in village Nagla Goal ,District Agra




Old rooms before the relocation in Village Nagla Goal, District Agra and the new construction of rooms with verandah
within temple completed




                 CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST                                             Page | 34
                                                                                                  Final Report
                                                              End-Term RAP Impact Evaluation of Land Acquisition and
                                                            R&R Implementation for EDFC-1 (Khurja – Bhaupur Section)




Newly constructed staircase and bathroom are to be fitted with doors and handrails in staircase in the temple in
village Nagla Goal, District Agra


Location 2: Agra (Village - Latifpur)

       The types of CPR impacted includes Toilet (2 Nos.), Urinal (2 Nos.), Hand Pump (1 No.).
       The community is satisfied with the construction of Toilet (2 Nos.), Urinal (2 Nos.) and Bore well
        with submersible pump provided in lieu of hand pump by the Contractor.




             New construction of Toilet, Urinal and Water pump in the Village- Latifpur ,District -Agra

Location 3: Auraiya (Raipalpur village)
       The type of CPR impacted is Graveyard
       Old CPR is in Raipalpur village, Auraiya and new one is also constructed in the same village
       There were 5 graves and compensation for graveyard is given to the respective families
       Total compensation given to the 5 PAPs are Rs. 163500 (Rs. 32,700 each)




                 CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST                                             Page | 35
                                                                                                 Final Report
                                                             End-Term RAP Impact Evaluation of Land Acquisition and
                                                           R&R Implementation for EDFC-1 (Khurja – Bhaupur Section)



       The contract of relocation and reconstruction of the graveyard was given to local community
        people. They are provided with Rs. 54,8677 for the construction work. The construction work is
        under progress
       The graveyard is in Government land which is 0.1460 ha. The required land was suggested by the
        community to which District Administration agreed.
       Alternate land for relocation of Graveyard was arranged by the District Administration. DFCCIL had
        given the required cost of land to the District Administration.




Physical possession of Graveyard at village - Raipalpur, Tehsil-Derapur, District-Kanpur Dehat and the new
construction ongoing

Location 4: Etawah (Village- Medhidudhi)
       The type of CPR impacted is Temple (Durga Mandir)
       No issues raised by the community; they are satisfied with the quality of construction.
       Temple is in private ownership of three shareholders.




The affected temple in the Village Medhidudhi, District Etawah and the new structure being constructed


                 CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST                                            Page | 36
                                                                                                   Final Report
                                                               End-Term RAP Impact Evaluation of Land Acquisition and
                                                             R&R Implementation for EDFC-1 (Khurja – Bhaupur Section)



Location 5: Hathras (Village – Kheriya)
        The type of CPR impacted are: (1) Temple including dharamshala, (2) Well, (3) Graveyard, and (4)
         Crematorium
         Temple resettlement cost were received but the temple’s land compensation is pending
         Due to pending of land compensation amount, community could not construct the structure
         Compensation for well of Rs 1, 14,000 has been received but new one yet to be constructed.




The old Temple with Dharamshala in Village- Kheriya, District- Hathras yet to be constructed




                                      Well in Kheria village, District- Hathras




                                      Impacted Graveyard and Cerematerium


                 CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST                                              Page | 37
                                                                                                  Final Report
                                                              End-Term RAP Impact Evaluation of Land Acquisition and
                                                            R&R Implementation for EDFC-1 (Khurja – Bhaupur Section)



       Further two more temples were affected of which one temple was constructed by the contractor
        and for the other one, compensation amount was provided to the owner of the temple.




Temple constructed in Kheriya by DFCCIL after relocation         Temple constructed in Kheriya by the owner
      of the old temple affected in the alignment

Location 6: Aligarh (Village- Daruchandpur )

The temple used by the community people was affected by the DFCCIL alignment. The village is
located parallel to the track. The temple is categorized as uncharted and has been constructed by
the Contractor adjacent to the track near the village. The newly constructed temple is similar to
the affected temple.




   Temple constructed after relocation of the old temple affected in the alignment in Daruchandpur village, Aligarh




                 CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST                                             Page | 38
                                                                                               Final Report
                                                           End-Term RAP Impact Evaluation of Land Acquisition and
                                                         R&R Implementation for EDFC-1 (Khurja – Bhaupur Section)



                                                                                                 Annexure-XII

                                         CSR activities of DFCCIL

As part of the CSR activities of DFCCIL, office of the CPM, Tundla had provided cash-assistance to the
District Administration of Firozabad and Agra respectively. An amount of Rs.700,000 (dated 03.01.2019)
and Rs. 800,000 (dated 02.04.2019) was transferred to the District Administration towards construction of
Public Toilets. However, DFCCIL does not have any information regarding the utilisation of the transferred
money to District Administration, although office of the CPM, Tundla while transferring the amount, had
requested the District Administration to provide update on the construction of Public Toilets. In addition to
this, the Contractor under CSR activity has organized blood donation and eye check-up camps and tree
plantation and landscaping in SP Office.

School Library in Douru Chandpur Village in Aligarh: Contractor has supported the School namely Saraswati
Sishu Mandir functioning under the management of Rashtriya Swayamsevak Sangh (RSS), by constructing a
building for library and also provided books. The library is great help to the teachers and students and they
expressed their gratitude towards DFCCIL and Contractor. However, access to the School is disrupted due
to water-clogging alongside the school which is due to track construction works. In this respect, the
villagers and school authorities expressed their concern.

                                   School Library constructed by DFCCIL




                CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST                                           Page | 39
                                                                                        Final Report
                                                    End-Term RAP Impact Evaluation of Land Acquisition and
                                                  R&R Implementation for EDFC-1 (Khurja – Bhaupur Section)



Letter to CPM Units intimating the appointment of CII for conducting CSR activities in the four
                                          locations




             CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST                                       Page | 40
                                                                     Final Report
                                 End-Term RAP Impact Evaluation of Land Acquisition and
                               R&R Implementation for EDFC-1 (Khurja – Bhaupur Section)



      CSR Activities proposed for the year 2017-2018




CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST                                 Page | 41
                                                              Final Report
                          End-Term RAP Impact Evaluation of Land Acquisition and
                        R&R Implementation for EDFC-1 (Khurja – Bhaupur Section)




CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST                          Page | 42
                                                                     Final Report
                                 End-Term RAP Impact Evaluation of Land Acquisition and
                               R&R Implementation for EDFC-1 (Khurja – Bhaupur Section)



      CSR Activities proposed for the year 2018-2019




CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST                                 Page | 43
                                                                     Final Report
                                 End-Term RAP Impact Evaluation of Land Acquisition and
                               R&R Implementation for EDFC-1 (Khurja – Bhaupur Section)




      CSR Activities proposed for the year 2019-2020




CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST                                 Page | 44
                                                              Final Report
                          End-Term RAP Impact Evaluation of Land Acquisition and
                        R&R Implementation for EDFC-1 (Khurja – Bhaupur Section)




CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST                          Page | 45
                                                              Final Report
                          End-Term RAP Impact Evaluation of Land Acquisition and
                        R&R Implementation for EDFC-1 (Khurja – Bhaupur Section)




CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST                          Page | 46
                                                                                                Final Report
                                                            End-Term RAP Impact Evaluation of Land Acquisition and
                                                          R&R Implementation for EDFC-1 (Khurja – Bhaupur Section)



                                                                                                 Annexure- XIII
                             Procedure of handling Grievances by DFCCIL

A Grievance Register is maintained in DFCCIL office, Agra wherein the date of receipt of the complaint,
issue addressed and method of communication, etc., are systematically documented. However,
information about the unresolved cases forwarded for resolution by GRC was not available.

In discussion with DFCCIL officials, Aligarh, it was intimated that grievances were received at various levels
of requisite Government Administrators like GM/LA, SLAO, CPM, ADM/LA, DFCCIL Head Quarter and
directly from office of Railway Board. After which it is forwarded to the site office for understanding the
matter. For example, in case of land related grievances received by SLAO and ADM/LA are forwarded to
DFCCIL site offices, which after understanding the matter are further sent to the concerned SDM/
concerned Tehsil. A report is prepared by Tehsil on the matter to resolve the issue. PAP is intimated about
the decision made by Tehsil in the report.

Those grievances which were not redressed, as revealed during the discussion with the PAPs include,
payment-returned due to PAP’s demise and consequent claim by PAP’s Widow, valuation of additionally
affected portion of residence, movement of train causing cracks in the residential property, etc. These
grievances were neither taken to the GRC for resolution nor is it resolved at the field level.

A systematic procedure is followed in filing the grievance cases in DFCCIL and in resolving them. People
either report their issues to the DFC site office or directly to the DFC headquarter. At the same time, PAPs
felt more consistency with respect to the complaints forwarded directly to the World Bank.




                CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST                                            Page | 47
                                                                                                   Final Report
                                                               End-Term RAP Impact Evaluation of Land Acquisition and
                                                             R&R Implementation for EDFC-1 (Khurja – Bhaupur Section)



                                                                                                    Annexure- XIV

                                Study on Local Employment Generation

A detailed study on local employment generation was conducted. The summary of the study could be seen
below:

The ‘labour-sub contractors’ who are often the contact-point of the civil work Contractor, function as the
local level entrepreneurs who happen to associate with the project for supply of construction-materials
other than labour. Good quality stones were transported from Alwar in Rajasthan (about 200 km by road)
to Aligarh and other project locations by these local-level entrepreneurs. Discussions with these
entrepreneurs reveal that they earned Rs.700 per wagon/truck load and transport 40-60 wagon/truck of
stone per day. On an average, Rs.35000 per day is the overall turnover of entrepreneurs and approximately
10 such local entrepreneurs, which adds a total turnover to Rs.520 million in a year. Out of the total
surveyed PAPs, 34 PAPs (3%) intimated that they were provided employment by the contractor. The types
of employment provided to these 34 PAPs include labourers, Supervisors, security guard, track man, turfing
work, welder, master mason and night watchmen. The majority of the PAPs were satisfied with the
employment conditions, wages and facilities provided by the contractor. The reasons for dissatisfaction of
the remaining PAPs were less wages, delay in payment and job was not appropriate in comparison to the
educational qualification.




                                          26%



                                                           74%




                                            Satisfied   Not satisfied
                     91.


                           Satisfaction level of PAPs with employment provided
                           by contractor




                CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST                                               Page | 48
                                                                                                Final Report
                                                            End-Term RAP Impact Evaluation of Land Acquisition and
                                                          R&R Implementation for EDFC-1 (Khurja – Bhaupur Section)



                                                                                                  Annexure XV

            Outcomes of the Data Analysis on various indicators of RAP Implementation

1. Number of PAPs and Control Population Surveyed
                   Number of PAPs
 Category                                    %          Number of Controlled population surveyed             %
                       Surveyed
   Male                  1041                86                            268                               94
  Female                  175                14                             16                                6
   Total                 1216               100                            284                              100
Source: Primary Survey, 2019

2. Whether you have purchased land/asset from compensation amount?
                   Category                             Number of PAPs                            %
                     Yes                                     200                                 17
                      No                                    1010                                 83
                    Total                                   1210                                 100
Source: Primary Survey, 2019
Note: Remaining 6 PAPs have not yet received compensation amount

3. Have you claimed reimbursement of stamp duty within timeframe
                  Category                            Number of PAPs                              %
PAPs purchased land/assets                                200                                16 (of 1216)
PAPs claimed Stamp Duty Reimbursement                      47                                     24
within timeframe
PAPs not claimed Stamp Duty Reimbursement                    153                                  96
within timeframe
Source: Primary Survey, 2019

4. If sufficient time (3 months) given for relocation
                  Category                            Number of PAPs                              %
                     Yes                                  222                                    95
                     No                                    12                                     5
                    Total                                 234                                    100
Source: Primary Survey, 2019

5. Whether you are satisfied with the Compensation Rate/Amount received?
                  Category                            Number of PAPs                              %
                  Satisfied                                  480                                  40
                Not Satisfied                                730                                  60
                    Total                                   1210                                 100
Source: Primary Survey, 2019

6. Whether you are satisfied with the received R&R assistance?
                  Category                            Number of PAPs                              %
                  Satisfied                                  583                                  75
                Not Satisfied                                192                                  25
                    Total                                    775
Source: Primary Survey, 2019


                 CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST                                           Page | 49
                                                                                             Final Report
                                                         End-Term RAP Impact Evaluation of Land Acquisition and
                                                       R&R Implementation for EDFC-1 (Khurja – Bhaupur Section)




7. Whether you are satisfied with the assistance provided by DFCCIL during relocation?
                  Category                          Number of PAPs                             %
                  Satisfied                             168                                    72
                 Not Satisfied                           62                                    26
                   Unsure                                 4                                    2
                    Total                               234
Source: Primary Survey, 2019

8. Have you received any training?
                  Category                          Number of PAPs                             %
                  Received                                  39                                  3
                Not received                                1177                               97
                    Total                                   1216
Source: Primary Survey, 2019

9. Whether your grievance resolved by GRC?
                  Category                          Number of PAPs                             %
          Grievance cases Resolved                       24                                     8
        Grievance cases not resolved                    127                                    42
         Grievance cases submitted                      151                                    12
Source: Primary Survey, 2019

10. Satisfaction from Decision of District Administration
                   Category                         Number of PAPs                              %
      Satisfied with the decision of GRC                 18                                    67
    Not satisfied with the decision of GRC                9                                    33
                     Total                               27                                    100
Source: Primary Survey, 2019

11. Have you taken service of any legal practitioners to submit the grievance
                  Category                          Number of PAPs                              %
                     Yes                                225                                    87
                     No                                  35                                    13
                    Total                               260                                    100
Source: Primary Survey, 2019

12. Please state whether the Court/Arbitrator decision was positive
                     Category                         Number of PAPs                           %
                 Cases submitted                          260                                  21
       Arbitrator/ court’s decision positive                  67                               26
       Arbitrator/ court’s decision negative                  110                              42
                  Cases pending                               83                               32
Source: Primary Survey, 2019




                  CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST                                       Page | 50
                                                                                            Final Report
                                                        End-Term RAP Impact Evaluation of Land Acquisition and
                                                      R&R Implementation for EDFC-1 (Khurja – Bhaupur Section)


13. Socio-economic profile of women
                                                 Project Affected Persons
                      Indicators                                                Controlled Population (2019)
                                                      [PAPs] (2019)
Occupation (in %)
     Housewife                                            91                                 69
       Agriculture                                         4                                 19
       Wage-Labour                                         3                                 6
       Trade                                               1                                 6
     Service                                               1                                  -
Average annual income (in Rs.)                           31,640                             34,480
Indebtedness (No. of cases: in %)                          22                                 31
Housing Condition (% having Pucca structures)              39                                  -
Area increased (in %)                                      88                                  -
Source: Primary Survey, 2019

14. Awareness about the Act/ Policy
                      Category                   Number of PAPs                               %
                        Yes                              111                                 63
                         No                               65                                 37
                       Total                              176                                100

Source: Primary Survey, 2019

15. Have you received compensation amount and R&R assistance
                    Category                     Number of PAPs                               %
                    Received                             176                                 100
                  Not Received                             0                                  0
                      Total                               176                                100
Source: Primary Survey, 2019

16. Have you ever submitted any grievance to Court/Arbitrator
                    Category                     Number of PAPs                               %
                        Yes                               32                                 18
                        No                               144                                 82
                      Total                               176                                100
Source: Primary Survey, 2019

17. If you ever faced any difficulty in receiving the compensation amount / R&R assistance?
                    Category                     Number of PAPs                               %
                        Yes                              134                                 76
                        No                                42                                 24
                      Total                               176                                100
Source: Primary Survey, 2019

18. Whether you are satisfied with the compensation amount and R&R assistance
                Category                      Number of PAPs                                  %
                Satisfied                               88                                   50
              Not Satisfied                             88                                   50
                 Total                                 176                                   100
Source: Primary Survey, 2019


                  CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST                                       Page | 51