DEDICATED FREIGHT CORRIDOR CORPORATION OF INDIA LIMITED (Government of India Enterprise) FINAL REPORT End -Term RAP Impact Evaluation of Land Acquisition and R&R Implementation for EDFC-I (Khurja-Bhaupur) Section) JUNE 2020 LEA ASSOCIATES SOUTH ASIA PVT. LTD. New Delhi, India TABLE OF CONTENTS EXECUTIVE SUMMARY ............................................................................................................ 1 1. INTRODUCTION 1.1 Project Background .....................................................................................................................1 1.2 Approach and Methodology ........................................................................................................2 1.3 Structure of the Report ...............................................................................................................6 2. CHANGES IN SOCIO-ECONOMIC AND LIVING STANDARDS ............................................... 7 2.1 Changes in Occupational Profile ..................................................................................................7 2.2 Changes in Income level ..............................................................................................................7 2.3 Indebtedness ...............................................................................................................................8 2.4 Housing Condition .......................................................................................................................8 2.5 Change in Standard of Living .......................................................................................................8 2.6 Opinion of the respondents.........................................................................................................9 3. LAND ACQUISITION AND RESETTLEMENT IMPLEMENTATION OUTCOMES ..................... 13 3.1 Status of Private Land Acquisition .............................................................................................13 3.2 Disbursement of Compensation ................................................................................................13 3.3 Procedure and Timeline Followed for Land Acquisition as per RAA, 2008 ...............................13 3.4 Rehabilitation and Resettlement Assistance .............................................................................14 3.5 Level of Satisfaction of PAPs: .....................................................................................................15 3.6 Training of PAPs .........................................................................................................................15 3.7 Status of Land Handover and Impact on Construction .............................................................16 3.8 Impact on Common Property Resources...................................................................................17 3.9 Corporate Social Responsibility Activities .................................................................................17 3.10 Cost of Land Acquisition and Resettlement ............................................................................187 3.11 Grievance Committee’s Impact ...............................................................................................198 3.12 Arbitration and Court Cases ....................................................................................................209 3.13 Local Employment Creation.......................................................................................................21 3.14 Impact on Women ...................................................................................................................221 3.15 Institutional Arrangement for RAP Implementation ...............................................................232 4. CONCLUSION AND RECOMMENDATION .......................................................................254 4.1 Key Findings .............................................................................................................................254 4.2 Lessons Learnt .........................................................................................................................287 4.3 Outstanding Issues and Suggested Action Plan .......................................................................309 LIST OF TABLES Table 1-1: Summary of Land Acquisition and Resettlement Impact of EDFC 1 .............................................. 1 Table 1-2: Categorization of the land lost by the PAPs in the project ............................................................ 2 Table 2-1: Socio-Economic Indicators ............................................................................................................. 8 Table 2-2: Summary of Focus Group Discussions ........................................................................................... 9 Table 3-1: Item-wise expenditure for RAP Implementation of EDFC 1 ........................................................ 19 Table 3-2: Details of Cases Filed in Court..................................................................................................... 21 LIST OF FIGURES FIGURE 1: GPS Tagged Map of Survey Location: PAPs and Control Population ............................................. 5 CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST Page | i Final Report End-Term RAP Impact Evaluation of Land Acquisition and R&R Implementation for EDFC-1 (Khurja – Bhaupur Section) a) FIGURE 3: Timeline of Arbitration Cases....................................................................................................... 20 FIGURE 4: Cases Filed in Court and Cases Resolved ..................................................................................... 20 LIST OF ANNEXURES Annexure I : Project Detail Factsheet of EDFC-1 Annexure II : Detailed Scope of Work Annexure III : Sample Copy of Questionnaires of PAPs and Control Population Annexure IV : Sample Copies of Focus Group Discussion (FGD) Guidelines Annexure V : Photographs of FGDs conducted Annexure VI : Assessment of timeline based on village level case studies Annexure VII : Land acquired for NTH Annexure VIII (A) : Newspaper Excerpts and Camps Organized Annexure VIII (B) : Satisfaction Level of PAPs with respect to Awareness camps Annexure IX : Training to the PAPs and Employment (Newspaper Excerpts) Annexure X : Land Related Hindrances or Stoppage of Civil Works by Community Annexure XI : Onsite Observations of Common Property Resource Annexure XII : CSR activities of DFCCIL Annexure XIII : Procedure of handling Grievances by DFCCIL Annexure XIV : Local Employment Study Annexure XV : Outcomes of the data analysis on various indicators of RAP Implementation LIST OF ABBREVIATIONS BPL --- Below Poverty Level CII --- Confederation of Indian Industry CPM --- Chief Project Manager CPR --- Common Property Resource CSR --- Corporate Social Responsibility DFCCIL --- Dedicated Freight Corridor Corporation of India Limited EDFC --- Eastern Dedicated Freight Corridor EM --- Entitlement Matrix FGD --- Focus Group Discussion CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST Page | ii Final Report End-Term RAP Impact Evaluation of Land Acquisition and R&R Implementation for EDFC-1 (Khurja – Bhaupur Section) a) GoI --- Government of India GPS --- Global Positioning System GRC --- Grievance Redress Committee IBRD --- International Bank for Reconstruction and Development ITI --- Industrial Training Institute LA --- Land Acquisition LASA --- Lea Associates South Asia Private Limited NGO --- Non-Government Organisation NTH --- Non-Titleholder OFC --- Optical Fibre Cable PAPs --- Project Affected Persons PMC --- Project Management Consultant PWD --- Public Works Department QPR --- Quarterly Progress Report R&R --- Rehabilitation and Resettlement RAA --- Railway Amendment Act, 2008 RAP --- Resettlement Action Plan RCC --- Reinforced Cement Concrete Right to Fair Compensation and Transparency in Land Acquisition, RFCT-LARR --- Rehabilitation and Resettlement ROB --- Railway Over Bridge RoW --- Right of Way RPF --- Resettlement Policy Framework RUB --- Railway Under Bridge SC --- Scheduled Caste SDM --- Sub Divisional Magistrate SEMU --- Social and Environment Management Unit SPV --- Special Purpose Vehicle S&T --- Signal and Telegraph TH --- Titleholder ToR --- Terms of Reference WHH --- Women Headed Household CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST Page | iii Final Report End-Term RAP Impact Evaluation of Land Acquisition and R&R Implementation for EDFC-1 (Khurja – Bhaupur Section) EXECUTIVE SUMMARY 1. The Dedicated Freight Corridor Corporation of India Ltd. (DFCCIL), Ministry of Railways implemented the World Bank Funded Dedicated Freight Corridor Project from May 2011 to the end of 2019. End-term Impact Evaluation of Resettlement Action Plan (RAP) is an in-built component of the project which aims at assessing whether the affected persons and households are rehabilitated and resettled as per the RAP. Commissioned by DFCCIL, the study assessed the impact of the project on the project affected persons (PAPs) and control population. 2. The implementation of the Khurja-Bhaupur section (343.56 Km.) of EDFC-1 has triggered substantial land acquisition and resettlement impacts. RAP has envisaged 1442.15 ha. of land acquisition, which has reduced by 7% to 1339.35 ha. by end of the implementation period. The project has taken conscious efforts to minimize the impact on land. The number of PAPs was 56,651 as per RAP, estimated based on individual land-owners. The number of PAPs during implementation was 25,472, estimated based on single land-plot having multiple shareholders. In sum, the resettlement planning was near accurate. 3. The universe comprised 25,472 PAPs which included formal land-owners (‘Titleholders’), informal settlers (‘Non-Titleholders’), resident owners or tenants and vulnerable categories. Out of the total PAPs, 1216 PAPs (5% of the total PAPs) were selected for the impact assessment. The identification of PAPs followed proportionate sampling method. Apart from this, 284 households were chosen as control population. Out of the 27 Common Property Resources (CPRs), 6 were studied using purposive sampling. The project has acquired 1188.77 ha. of private land, which is 89% of the total land acquired and the remaining included Government land. A total of 24,687 land-owners (97%) received compensation. DFCCIL has disbursed compensation for 1178.38 ha. of land (99% of the total private land acquired). 4. On an average, a Project Affected Person (PAP) has lost 0.05 ha. of land to the project. As per the study, 87% PAPs has lost less than 0.1 ha. of land to the project. 5. Out of the total PAPs, 532 families (2.1%) were displaced. The displaced families were compensated for their affected structure and provided Rehabilitation and Resettlement (R&R) assistance as per the Entitlement Matrix. 6. As per the study, 31% PAPs utilised the compensation and assistance for construction/renovation of house and 8% utilised the money for purchasing land. 7. The PAPs as well as local community were satisfied with the relocation of common property resources and appreciated the efforts of DFCCIL in relocating the CPRs. 8. The average delay in handing over of the encumbrance-free land to the contractor as per the provision of civil contract: achieving first milestone (i.e. 80% handover) was delayed by 51 days and achieving the last milestone (i.e. 100% handover) was delayed by 1160 days. 9. The occupational profile of the PAPs remains unchanged in comparison to the baseline. Majority of the PAPs were engaged in agriculture and allied activities. The rate of unemployment has reduced CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST Page | 1 Final Report End-Term RAP Impact Evaluation of Land Acquisition and R&R Implementation for EDFC-1 (Khurja – Bhaupur Section) from 6% (during baseline) to 2%. Average income of the PAPs increased by 26% in real terms (adjusting for inflation). Average income of the BPL PAPs has increased by 1.4 times in comparison to the baseline1. Further, the study showed that the living standard of PAPs have enhanced. Out of the total PAPs, 91% intimated that they have constructed new house or renovated their existing residential structure with improvised area; 37% PAPs were able to pay their debts, spend on medical as well as educational needs and also on household chores. 10. Analysis of the sample cases of land acquisition awards revealed that notification and various procedures followed were in compliance to the Railway Amendment Act, 20082. The Award and further procedures were done in time, whereas the award (20F) of 54 villages was delayed and surpassed the prescribed period of one year. DFCCIL had paid the land-owners the value of award along with an interest (5% per month) for the delayed period. 11. The project has generated employment to 4193 persons since January 2014, which included jobs of watchmen, office-assistant, site-supervisor, laboratory-assistant, electrician, and construction-site labour. The average wages of these locally employed persons were about 15% more than the prescribed minimum-wage rages. 12. In essence, DFC has achieved its objectives to the maximum possible extent. The project affected persons improved their income earnings, even though not at par with the control population, they utilised the compensation and assistance amount for upgrading their living standards. Overall, the problems emanating from the project are minimal as the expectations of the PAPs were high. Project should provide additional resources to rectify the post-construction damages to residential structures and also to remedy the RUBs, approach or access roads which largely affected community life. 13. Land acquisition by government functionaries could be made more inclusive and time-bound, with DFCCIL taking more facilitative approach at higher level with line departments. While delay-interest is applicable for land compensation, resettlement assistance is disbursed without any delay-interest. Measures should be taken to provide delay-interest for resettlement assistance, in tune with the land compensation rules. 1 As per the baseline, the PAPs earning less than Rs.25,000 were considered below poverty line. Presently (2019) the BPL threshold income is Rs.27,000. 2 The major stages of notifications and awards as per RAA, 2008 includes: (i) 20A –Notification by Central Government declaring its intention to acquire land for execution of a special railway project briefly describing the land intended to be acquired and about the special railway project, (ii) 20E-The Central Government declares, by notification that the land is acquired for the purpose mentioned in section 20A. If no declaration is published within the period of one year from the date of publication of section 20A then the notification will cease to have any effect and, (iii) 20F- The amount to be paid as compensation (Award) to be determined by the Competent Authority within a period of one year from the date of publication of the declaration or the acquisition (20E) of the land will lapse. CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST Page | 2 Final Report End-Term RAP Impact Evaluation of Land Acquisition and R&R Implementation for EDFC-1 (Khurja – Bhaupur Section) 1. INTRODUCTION 1.1 Project Background 1. The Ministry of Railways, Government of India (GoI) has received financing from the International Bank for Reconstruction and Development (IBRD) towards the cost of Eastern Dedicated Freight Corridor Project (EDFC). The Dedicated Freight Corridor Corporation of India Ltd. (DFCCIL), the implementing agency has appointed LEA Associates South Asia Private Limited, New Delhi, for carrying out the “End- Term Impact Evaluation of Land Acquisition and Rehabilitation and Resettlement (R&R) implementation of the Khurja - Bhaupur section (343 Km.) of EDFC -1”. The stretch from New Bhadan to New Khurja (195 kms.) has been commissioned. 2. The two Resettlement Action Plans (RAPs) i.e. (i) Khurja - Bhaupur section and (ii) Tundla re- alignment, were prepared in March, 2011. As per the RAPs, the total length of the Bhaupur-Khurja corridor was 343 Kms. (Double line); of which 149 Kms. was in detour section and balance 194 Kms. was in parallel to the existing North Central Railway track. This section comprised of 4 junction stations and 6 crossing stations. As per RAP, the corridor traversed 8 districts and 291 villages of the state of Uttar Pradesh. The Right of Way (RoW) width was around 40 mtr. in the parallel section and 60 mtr. in detour. Out of 343 Km. of this stretch, Tundla detour was 71 Km. 3. The implementation of the Khurja-Bhaupur section (343.56 Km.) of EDFC-1 has triggered substantial land acquisition and resettlement impacts. The project has acquired 1,188.77 ha. of private land impacting 25,472 Project Affected Persons (PAPs). Project has provided resettlement assistance to a total of 10,260 PAPs. This included 532 physically displaced PAPs3 and rest 9728 PAPs in the category of livelihood support. A summary of land acquisition and resettlement impact of EDFC-1 is presented in Table 1-1, which shows that resettlement planning carried out, was near accurate. The detailed factsheet showing the updated status of EDFC-1 is at Annexure I. Table 1-1: Summary of Land Acquisition and Resettlement Impact of EDFC 1 Baseline Status (as End-term Impact No. Parameter per RAPs) Status (as on July, 2019) 1 RoW Length (in route Km.) 343 343.56 2 Total Land Acquisition (Ha.) 1442.15 1339.35 Project Affected Person [including Titleholders and Non- 56651* 25472 4 Titleholders] (Nos.) 5 PAP received R&R support (Nos.) - 10260 6 Physically DisplacedPAPs (Nos.) - 532 Source: DFCCIL, 2019 [*Note: As per RAP (Tundla Realignment of May 2011): “due to large number of representations, the alignment of Tundla detour was re-surveyed and mostly brought parallel. The Tundla detour was divided in 72 Km. parallel and about 29.56 Km. in detour portion. Furthermore, to avoid displacement of people, DFCCIL has undertaken certain technical efforts like minimizing track distance at selected locations and reducing embankment heights and slopes. 3 Data as on May 2020, Source: DFCCIL. CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST Page | 1 Final Report End-Term RAP Impact Evaluation of Land Acquisition and R&R Implementation for EDFC-1 (Khurja – Bhaupur Section) At many built-up locations land width has been reduced to as less as 22 mtr. which has resulted in reducing impact on residential as well as commercial structures”]. 4. It is seen from Table 1-1 that the length of the alignment has slightly increased. The total land acquisition has decreased by 102 ha. (7%), and the number of PAPs has also decreased by 55%. The reason for decrease in the number of PAPs in comparison to the area of land acquired is because during RAP preparation, the land-owners were individually taken into consideration, whereas during the RAP implementation the land having multiple shareholders were taken as a whole. 5. Taking into consideration, 25,472 Project Affected Persons (PAPs) in 1,188.77 ha. of private land acquired by the project, the average land of 0.05 ha. of one PAPs has been lost to the project. As per As per the study, 87% PAPs has lost less than 0.1 ha. of land to the project. Table 1-2: Categorization of the land lost by the PAPs in the project4 Category of land in ha. No. of PAPs % of PAPs Less than 0.1 22,225 87.25 0.1 - 0.5 3,180 12.48 0.5 and above 67 0.26 Total 25,472 100.0 Source: DFCCIL, 2020 6. The End-Term Impact Evaluation of land acquisition and rehabilitation & resettlement implementation process for EDFC-1 covers total length of 343.56 Kms. The stretch located in Uttar Pradesh includes Bhaupur - Khurja section (271.56 Kms.) and Tundla Re-alignment (72 Kms.). 7. The study aimed to assess whether the affected persons and households were rehabilitated and resettled as per RAP and the impact of the project on the PAPs and control population. The objective of the study is as under: Independently evaluate the land acquisition and rehabilitation and resettlement implementation process in the project. Assess the impact created by compensation and assistance provided to the project affected persons in improving their living standards. Evaluate the impact across all categories of project affected persons including formal land- owners (‘Titleholders’), informal settlers (‘Non-Titleholders’), resident owners or tenants and vulnerable categories. 8. The detailed scope of work is given at Annexure II. 1.2 Approach and Methodology 9. The end-term impact evaluation was done by comparing the present condition of the PAPs with the conditions that were prevalent during the baseline (2011). The impact on PAPs was also assessed in 4 Based on the analysis of the data received from the respective lots of DFCCIL. CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST Page | 2 Final Report End-Term RAP Impact Evaluation of Land Acquisition and R&R Implementation for EDFC-1 (Khurja – Bhaupur Section) comparison to a set of Control Population. Besides, level of satisfaction and perception of PAPs and local community with respect to the implementation of RAP was also studied. 10. The study involved both quantitative and qualitative data collection and analysis. The data for the study was collected through household-surveys, focus group discussions (FGD) with various target groups, and also institutional level discussions (DFCCIL, Project Management Consultant (PMC), Contractors, and Non-Government Organization (NGO). The evaluation entailed the following tasks: Review of available project documents and literature Sample selection and coverage Data collection Focus Group Discussion and Discussion with Stakeholders Data analysis and report preparation (a) Review of Project Documents and Literature 11. The various documents and records were collected from the DFCCIL such as Resettlement Action Plan (RAP), Award Copies, Payment of Compensation and Disbursement details, Micro Plans, Valuation Reports (structure, land and trees) and data related to Grievance Redress Committee (GRC). 12. In addition, data and information associated with time taken for various stages of land acquisition, reasons for delay in handing over of encumbrance-free land to the contractor as per the contract provision and its impacts on construction was collected and analysed. (b) Sample Selection and Coverage 13. Confirming the mandate of Terms of Reference (ToR), 1216 PAPs and 284 households (control population) were surveyed. The sampling considered the following parameters: Various affected categories of PAPs including formal land-owners (‘Titleholders’), informal settlers (‘Non-Titleholders’), resident owners or tenants and vulnerable categories. PAPs located in detour and parallel sections, PAPs located in respective Lots5, PAPs whose land is acquired as per Railway Amendment Act (RAA), 2008 and Uttar Pradesh Direct Land Purchase Policy, 2015, PAPs who have been provided R&R assistance based on Resettlement Policy Framework (RPF) disclosed in 2011 and as per revised RPF disclosed in 20156. 14. The Global Positioning System (GPS) tagged map showing the surveyed location of PAPs and control population is presented in Figure 1. 5 The civil contract of the project was carried out in three construction lots i.e. (i) Lot 101- Bhaupur to Etawah Bypass End (ii) Lot 102- Etawah Bypass End to Chamrola Bypadss End and (iii) Lot 103- Chamrola Bypadss End to Khurja 6 The revision of the RPF was in view of the new land acquisition Act – Right to Fair Compensation and Transparency in Land Acquisition and Rehabilitation and Resettlement (RFCT-LARR), 2013. This report uses the term ‘Entitlement Matrix (EM) 2011 and Entitlement Matrix (EM) 2015’ denoting the respective RPFs. CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST Page | 3 Final Report End-Term RAP Impact Evaluation of Land Acquisition and R&R Implementation for EDFC-1 (Khurja – Bhaupur Section) (c) Data Collection 15. Data at household level were collected applying direct interview method. A total number of 16 trained enumerators were deployed to collect the data, of which 5 were female. The enumerators were guided by 6 field supervisors. 16. A structured questionnaire was formulated covering the indicators for PAPs such as (i) compensation and R&R assistance received (ii) utilization of compensation amount (iii) income generation activities (iv) household/ individual income (v) debts (vi) household facilities (vii) grievance redress (viii) satisfaction level and (ix) feedback/ opinion on Land acquisition and R&R processes. A questionnaire for control population was also prepared covering the indicators such as (i) income and occupation (ii) Debts (iii) household facilities and (iv) feedback/ opinion on change of living condition. The sample copy of the questionnaire as well as control population is given at Annexure III. (d) Focus Group Discussion 17. Altogether, 12 FGDs were conducted. The objective of FGD was to assess the impact of RAP implementation. The focus groups included (i) physically displaced people, (ii) PAPs received compensation and R& R assistance, (iii) PAPs whose land acquired as per UP Direct Land Purchase Policy, (iv) PAPs filed Grievance cases, (v) Vulnerable Groups (SC, ST, BPL, WHH and Differently-Abled), (vi) Formal Settlers (Titleholders -THs) and informal settlers (Non-titleholders -NTHs), (vii) Civil Work Contractor, (viii) PAPs Employed by the Contractor, (ix) Community Representatives for Common Property Resources and Religious Structures, (x) Control Population, (xi) PAPs who filed Complaints to World Bank, and (xii) PMC. 18. The consultant team visited the project sites; interacted with PAPs, DFCCIL officials, implementing agencies (Contractor, PMC & NGO) and other concerned departments. Sample copy of the FGD guidelines is given at Annexure IV. CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST Page | 4 Final Report End-Term RAP Impact Evaluation of Land Acquisition and R&R Implementation for EDFC-1 (Khurja – Bhaupur Section) Figure 1: GPS Tagged Map of Survey Location: PAPs and Control Population CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST Page | 5 Final Report End-Term RAP Impact Evaluation of Land Acquisition and R&R Implementation for EDFC-1 (Khurja – Bhaupur Section) 1.3 Structure of the Report 19. This report consists of five chapters including the present one as Introduction. The list of the chapters in the report are: Chapter 1: Introduction Chapter 2: Changes in Socio-economic and Living Standards Chapter 3: Land Acquisition and Resettlement Implementation Outcomes Chapter 4: Conclusion and Recommendations CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST Page | 6 Final Report End-Term RAP Impact Evaluation of Land Acquisition and R&R Implementation for EDFC-1 (Khurja – Bhaupur Section) 2. CHANGES IN SOCIO-ECONOMIC AND LIVING STANDARDS 20. This chapter presents the comparative socio-economic background of project affected persons during the current period (2019) and baseline period (2011). The characteristics of control population have also been presented wherever required. 21. The key findings with respect to changes in occupation, changes in income level, indebtedness, housing condition, changes in living standard and opinion of the respondents (FGDs) are presented in subsequent sections. 2.1 Changes in Occupational Profile 22. The study has looked into the changes in the occupational profile of the PAPs from the baseline period to the current period. Agriculture was the main occupation of the PAPs. During 2011, 19% of the affected persons were engaged in agriculture. As per the study, majority of the PAPs (39%) were engaged in agriculture and allied activities. Further, 4% of the Project Affected Persons reported change in occupation. Rate of unemployment reduced to 2% during the end-term evaluation from 6% during baseline. 2.2 Changes in Income level 23. During 2011, the average income of the PAPs was Rs.31,875. In comparison to this, the average income (in real terms) of the PAPs was Rs.40,135 and that of control population was Rs.46,090. The study observed that the current income of the PAPs has increased by 26% over baseline income but is 15% lower compared to control population. 24. A comparison in the income of the PAPs who were compensated based on Railway Amendment Act (RAA), 2008 and Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act (RFCT-LARR), 2013 respectively were analysed. The average annual income (in real terms) of the PAPs who have received compensation as per RAA, 2008 was Rs.34,136 and the average annual income (in real terms) of the PAPs who have received compensation as per RFCT-LARR, 2013 was Rs.43,335. The study found that the difference in the annual income of the PAPs who were compensated as per RFCT-LARR, 2013 with that of the control population was 6%. The difference in the annual income of the PAPs who were compensated as per RAA, 2008 with that of the control population was 26%. PAPs under Below Poverty Line (BPL): As per the baseline (2011), 63% of total PAPs were considered as ‘Below the Poverty line (BPL)’ families; earning less than Rs.25,000 annually. Presently, the BPL threshold income is Rs.27,000 and accordingly 23% were BPL. The study observed that the average income (in real terms) of BPL PAPs was 1.4 times higher compared to baseline. CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST Page | 7 Final Report End-Term RAP Impact Evaluation of Land Acquisition and R&R Implementation for EDFC-1 (Khurja – Bhaupur Section) 2.3 Indebtedness 25. During 2011, 380 cases (81% of surveyed PAPs) of indebtedness were reported. As per the study, indebtedness was reported for 37% PAPs. In case of control population, indebtedness was reported for 31%. One-third of the PAPs have utilised the compensation amount in repaying a portion of their debt. 2.4 Housing Condition 26. The study has looked into the housing condition in terms of the nature of construction. During 2011, 97% of the PAPs had ‘pucca’ house (houses made of bricks, RCC permanent structure). The study did not observe major changes in the housing condition. 27. During 2011, 44% of the surveyed population were having separate kitchen and bathroom facilities each and the situation continues for both PAPs and control population during the study period. 2.5 Change in Standard of Living 28. The study revealed that the area of existing residential structure of 91% PAPs has increased and also the new houses were constructed. Further, 31% PAPs utilized the amount for construction/renovation of house followed by 8% for purchase of land and 3% for agricultural purpose. The study observed that 58% PAPs utilised the compensation amount and R&R assistance on repayment of loan, investment in new business and expenditure on improved medical as well as educational facilities. The living condition of 39% PAPs improved due to the project and 48% were able to construct new house. The remaining PAPs intimated that their living condition did not improve due to the reason such as: (i) compensation amount received was less and (ii) the amount received was spend on household chores. 29. The study observed that out of the total PAPs, 19% were physically displaced. The area of existing residential structure of 57% displaced PAPs has increased. Further, 66% PAPs utilized the amount for construction/renovation of house followed by 15% for purchase of land. The study also observed that 18% PAPs utilised the compensation amount and R&R assistance on repayment of loan and deposited in bank. The living condition of 81% displaced PAPs improved due to the project. the remaining informed that there was no change in the living condition as (i) compensation amount received was less (ii) invested their own saving in construction of new house and (iii) material for construction of house was expensive. 30. Table 2-1 below shows the various socio-economic indicators taken into account during the study. Table 2-1: Socio-Economic Indicators S.No. As per Controlled Project Affected Indicators Baseline Population Persons [PAPs] (2011) (2019) (2019) 1. Occupation (in %) Agriculture 19 37 39 Unemployed 6 0.3 2 Others 75 62.7 59 2. Average annual income (in Rs.) 31,875 46,090 40,135 3. Indebtedness (No. of cases: in %) 81 31 37 CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST Page | 8 Final Report End-Term RAP Impact Evaluation of Land Acquisition and R&R Implementation for EDFC-1 (Khurja – Bhaupur Section) S.No. As per Controlled Project Affected Indicators Baseline Population Persons [PAPs] (2011) (2019) (2019) Housing Condition 4. 97 - 95 (% having Pucca structures) 5. Separate Kitchen and bathroom facilities (in %) 44 - 44 6. Area increased (in %) - - 91 Source: RAP (2011) and Primary Survey (2019) 2.6 Opinion of the respondents 31. Focus Group Discussions (FGDs) were conducted with various groups to understand the impact of the project. FGDs were organised with 12 different groups in 69 locations wherein 637 people participated. The photographs of the Focus Group Discussion is presented at Annexure V. Outcome of the FGDs is summarised in Table 2-2. Table 2-2: Summary of Focus Group Discussions Sl.No. FGD Groups Name of Locations Outcome 1 Physically Naugawan, Displaced PAPs received enhanced compensation as per the Displaced People Sukhampur & decision of the GRC. Dekhiyapur (Auraiya The PAPs themselves relocated to new location with Number of District) external support received from DFCCIL and contractor. Consultations: 6 Barhan & Nagla Gokul The PAPs were allowed to salvage the construction (Agra District) materials. Number of Kirthra Mohmadpur PAPs were not satisfied with the timeframe of 3-months Participants: (Firozabad District) given for relocation. 57 PAPs expected employment opportunities for at least a person in each household as part of the project. 2 PAPs who Keshopur Jafori & Vulnerable PAPs (BPL, differently-abled and widow) received Doruchandpur expressed satisfaction for the special assistance they Compensation (Aligarh District) received. and R&R Datoji, Alampur PAPs who received compensation as per the Entitlement Assistance Jhapta, Latifpur, Matrix-2011 were not satisfied with the land rates as Dokeli, Rasedpur compared to the PAPs who received compensation as per Number of Kaneta, Aronj & the Entitlement Matrix-2015. Consultations: Galamai (Firozabad Majority of the PAPs utilized the compensation amount and 15 District) R&R assistance on repayment of debt, expenditure on Barhan, Nagla Gokul, improved medical and educational facilities. Number of Surehara Mustkil & Although it was planned initially to provide drain facility, Participants: Dehrera (Agra RCC road along the RUB, the same was not provided. This 117 District) created difficulty for the community people. Behta (Kanpur Dehat Majority of the PAPs have not filed any grievances due to District) lack of awareness regarding GRC. PAPs who approached the Court of Law for enhanced compensation received favourable decision. They received the enhanced compensation as well. Water logging in newly constructed RUB during rainy season. Improper rehabilitation of borrow area resulted in soil run- off and consequent damage to religious structure. CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST Page | 9 Final Report End-Term RAP Impact Evaluation of Land Acquisition and R&R Implementation for EDFC-1 (Khurja – Bhaupur Section) Sl.No. FGD Groups Name of Locations Outcome Community requested for making necessary drainage facilities. Few PAPs from Barhan, Nagla Gokul, Surehara Mustkil & Dehrera of Agra District have not received R&R assistance. PAPs received job-training from Industrial Training Institutes (ITIs). 3 PAPs involved in Shahpur Derapur PAPs expressed their satisfaction for the compensation Direct Land (Kanpur Dehat amount received. Purchase Process District) They were also satisfied with the R&R assistance provided as per Resettlement Policy Framework, following the provision Number of amended in 2018. Consultations: 1 PAPs purchased land utilizing the compensation amount and constructed house. Number of Participants: 17 4 PAPs who have Datoji, Latifpur, Majority grievances of the PAPs were submitted to the filed Grievance Dokeli, Rasedpur respective DFCCIL site offices only and the concerned Cases Kaneta & Kirthra officials resolved the cases at their level. Mohmadpur In case of claiming for higher compensation, PAPs with the Number of (Firozabad District) help of legal practitioner had filed case with arbitrator. Consultations: 7 Barhan & Nagla Gokul Few PAPs had filed cases with the arbitrator and was (Agra District) pending for decision. Number of Participants: 27 5 Vulnerable PAPs Bhanduwa Phaphood Participants comprised of members from Scheduled Castes & Purwasa (Auraiya (SC), BPL, Differently-abled and Women Headed Households Number of District) (WHHs). Consultations: Datoji, Alampur The participants expressed their satisfaction for the special 13 Jhapta, Kirthra assistance provided to vulnerable category. Mohmadpur, Bankat, PAPs intimated that DFCCIL assisted the PAPs in Number of Rampur, Dokeli, administrative formalities and filling of forms etc. Participants: Rasedpur Kaneta, Participants did not face any difficulty in receiving the 144 Aronj & Galamai compensation and R&R assistance amount. (Firozabad District) PAPs were satisfied with the assistance provided, even Surehara Mustkil & though they were not satisfied with the compensation Dehrera (Agra provided against lost land and assets. District) 6 Titleholders Doruchandpur & Participants were satisfied with the compensation and R&R (THs- Formal Khera Khush (Aligarh assistance provided. However, they were not satisfied for settlers) and District) not giving prior notice for demolition of structures. non-titleholders Kirthra Mohmadpur During construction frequent dust and water logging (NTHs-informal (Firozabad District) created difficulties for villages. settlers) Soil run-off from embankment to agricultural fields affected the standing crops. Number of Relocation of informal settlers in Doruchandpur village of Consultations: Aligarh: land-owner (formal settler) provided land for 3 constructing houses for informal settlers. The informal settlers demanded for alternate land for Number of relocation. Participants: 69 Few PAPs have not received R&R assistance. CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST Page | 10 Final Report End-Term RAP Impact Evaluation of Land Acquisition and R&R Implementation for EDFC-1 (Khurja – Bhaupur Section) Sl.No. FGD Groups Name of Locations Outcome 7 Civil Work Ritam (Etawah The contractor informed that job specific safety training was Contractor District) provided on periodic basis to the employees. Gari Bhakti (Agra DFFCIL has taken pro-active steps to resolve local issues Number of District) related to stoppage of construction activities due to delay in Consultations: disbursement of land compensation. 2 More than 1000 local people were deployed in different construction activities based on their experience and Number of knowledge as laboratory assistants, supervisor, electricians, Participants: 2 drivers, operators, office boys, office assistant, helpers and labourers. They were paid @ Rs.8,000/- to Rs.15,000 per month. Training and Corporate Social Responsibility (CSR) activities were adopted based on the mandate and corporate policy guidelines of the Contractor. 8 PAPs employed Hyatpur Bhaejara & PAPs and community people got employment opportunities by the Khera Khush Khabar which helped them to improve their income level and living Contractor (Aligarh District) standard. Mandrak (Ram Nagar) The contractors provided entrepreneurial opportunity to Number of & Dariyapur (Hatras local people in supplying construction materials, Consultations: District) construction vehicles and local labour. 7 Datoi & Alampur Local people were employed as drivers (for tractor trolley, Jhapta (Firozabad diesel vehicle) and security guards. Number of District) PAPs opined that they were satisfied with the job and were Participants: 68 Medidudhi (Etawaha receiving their remuneration consistently. District) 9 Community Kheriya, (Hathras The types of Common Property Recourses (CPRs) relocated Representatives District) were: educational and religious structures, crematorium, for Common Daruchandpur graveyard and public-well. Property (Aligarh District) Community people were satisfied with the relocation of Resources and Nagla Goal (Agra CPRs for the proactive approach adopted by DFCCIL. Religious District) Participation of community was observed from identifying Structures Latifpur (Firozabad sites for relocation till completion of CPR construction. District) In Kheriya village, Hathras district, community was not Number of Medidudhi & satisfied for the non-release of compensation against the Consultations: Bandhya Majro affected land of the religious structure. 6 (Etawah District) Soil run-off from the embankment and water logging had Raipalpur (Auraiya damaged the religious structure. Number of District) Participants: 47 CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST Page | 11 Final Report End-Term RAP Impact Evaluation of Land Acquisition and R&R Implementation for EDFC-1 (Khurja – Bhaupur Section) Sl.No. FGD Groups Name of Locations Outcome 10 Control Hajipur Chautta Most of the community people’s livelihood depended Population (Aligarh District) mainly upon agriculture. Datoji, Dokeli, Most of the participants working in agriculture, they were Number of Rasedpur Kaneta, employed as laborers. Consultations: Aronj, Galamai, During the rainy days, access to the village is blocked due to 9 Surehara Mustkil, water logging in newly constructed RUBs. Dehrera & Rahan Provision for adequate drainage facilities along newly Number of Khurad (Agra District) constructed RUBs should be provided before the completion Participants: 89 of construction work. Access roads in the village were badly damaged due to construction activities and movement of construction vehicles. Damaged roads have affected commuting to schools in Rahan Khurad village in Agra District. Community submitted written complaints to DFCCIL and District Administration; community requested for favorable action. Source: Focus Group Discussion conducted during Primary Survey-2019 CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST Page | 12 Final Report End-Term RAP Impact Evaluation of Land Acquisition and R&R Implementation for EDFC-1 (Khurja – Bhaupur Section) 3. LAND ACQUISITION AND RESETTLEMENT IMPLEMENTATION OUTCOMES 32. This part of the study presents detailed information related to land acquisition procedure which was followed, time taken for various stages of land acquisition, reasons for delay in handover of encumbrance-free land and its impacts on construction. The chapter also includes the perception of the PAPs and their satisfaction level on several aspects of RAP implementation. Outcome of the data analysis on various indicators are summarised and presented in tabular form at Annexure XV. 33. The land acquired was on the basis of the provisions of RAA, 2008 and Uttar Pradesh Direct Land Purchase Policy, 2015. The acquisition of land on behalf of DFCCIL was the responsibility of Revenue Department. The valuation of structures located within the affected land was responsibility of Public Works Department (PWD). The valuation of fruit bearing trees was carried out by Horticulture department and non-fruit bearing trees was carried out by Forest department. DFCCIL appointed Non-Government Organisations (NGOs) for facilitating RAP implementation. 3.1 Status of Private Land Acquisition 34. Total land acquired for the project was 1339.35 ha., of which 1188.77 ha. was private land affecting 25,472 PAPs. Out of the total acquired land, 4.72 ha., was acquired through Uttar Pradesh Direct Land Purchase Policy, 2015. DFCCIL adopted this policy for acquisition of land-plots missed out previously and those land required due to shift of alignment or for constructing drains, in order to reduce the timeline for acquisition under RAA-2008. Accordingly, DFCCIL has amended the Resettlement Policy Framework (RPF) in 2018. 3.2 Disbursement of Compensation 35. As on July 2019, a total of 24,687 (97%) land-owners received compensation for 1178.38 ha., of land (99%). Compensation was not disbursed for 785 land-owners (3%) for 10.39 ha., of land (1%). Disbursement processes are progressing for which DFCCIL is facilitating with the Revenue Department. 3.3 Procedure and Timeline Followed for Land Acquisition as per RAA, 200 8 36. As per Railway Amendment Act (RAA) 2008, after publication of the notification (20A) for land acquisition, declaration (20E) of the same should be published within a period of one year, or else the said notification will cease to have any effect. Also, the Competent Authority should make an award (20F) within a period of one year from the date of publication of the declaration (publication of 20E) or else the entire proceedings for the acquisition of the land lapses. 37. The process involved in land acquisition was analysed by studying random cases of Award procedures and respective timelines. The Award of fourteen villages were studied. The analysis of the sample cases of Awards revealed that notification and various procedures followed, were in compliance to RAA, 2008. The Award and further procedures were done within the prescribed timeframe of one year. The CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST Page | 13 Final Report End-Term RAP Impact Evaluation of Land Acquisition and R&R Implementation for EDFC-1 (Khurja – Bhaupur Section) average duration from 20A to 20E notification was observed to be 283 days and from 20E to 20F notification was 233 days. The assessment of timeline based on village level case studies is given at Annexure VI. 38. Apart from the villages studied above, it was observed that in 54 villages, 20F was delayed and surpassed the prescribed period of one year. DFCCIL had paid the land-owners the value of award along with an interest (5% per month) for the delayed period as per the RAA, 2008. 3.4 Rehabilitation and Resettlement Assistance 39. Disbursement of Rehabilitation and Resettlement (R&R) Assistance: A total of 10,260 PAPs were identified for disbursement of R&R assistance. Out of the total PAPs, 19% belonged to the vulnerable category. Till July 2019, disbursement was made to 9,449 PAPs (92%). 40. Stamp Duty Redemptions: A total 592 requisitions for stamp duty reimbursement were received of which 434 requisitions (73%) were considered and the remaining 158 requisitions (26%) were rejected. Reasons for rejections were (i) submission of requisition after the prescribed one-year, (ii) land was not purchased in the name of the entitled person, and (iii) claim submitted against the purchase of different category of land (other than the affected land category). 41. The study observed that 17% PAPs purchased land or assets with the compensation and R&R assistance in lieu of their lost assets. Further, out of the PAPs who had purchased land, 24% PAPs submitted requisition for stamp duty reimbursement within the stipulated timeframe and the respective claims were approved. The rejection of claim was reportedly due to the registry done in the name of dependents of the PAP. Also, the PAPs who did not claim for stamp duty stated that they were not aware of the provision of stamp duty redemption. 42. Resettlement Support: RAP insists that the project should provide adequate notification, counselling and assistance to affected persons so that they are able to move or give up their assets without undue hardship before commencement of civil works and after receiving the compensation. Taking into consideration the RAP, the study captured 19% of the PAPs who were relocated. Out of these PAPs, majority expressed that 3 months’ time was sufficient for relocation and stipulated time was given by the officials for relocation. The remaining PAPs were of the view that more than 3 months’ time should be provided for relocation. 43. Physical Displacement of Informal Settlers (NTHs): In Douru Chandpur village, Aligarh, 14 NTHs were displaced. The land-owner in whose land the NTHs were residing, was compensated. The structure compensation for the affected structure owned by the NTH along with R&R assistance were provided to respective NTHs. 44. Discussion with NTHs revealed that the land-owner has provided 1450 sq.m., of land towards relocation of the NTHs. The ownership of land provided for relocation remained with the land-owner. The NTHs have built their residential structure on that land. DFCCIL provided them shifting assistance of Rs.10,000, transitional allowance of Rs.4,000, assistance for displaced animal-shed of Rs.15,000 and CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST Page | 14 Final Report End-Term RAP Impact Evaluation of Land Acquisition and R&R Implementation for EDFC-1 (Khurja – Bhaupur Section) assistance for loss of livelihood of Rs.1,06,500 as per the EM, 2011. The photographs of the relocation site are at Annexure VII. 3.5 Level of Satisfaction of PAPs: 45. Satisfaction level regarding compensation amount: The study showed that 40% PAPs were satisfied with the compensation amount. Those who were not satisfied (60%) had demanded for enhanced compensation amount and opined that compensation amount was inadequate to replace lost assets. The excerpts of the camps organized for PAPs is given at Annexure VIII (A) and the satisfaction level of the PAPs with respect to the awareness camps is given at Annexure VIII (B). 46. As per the study, 15% PAPs intimated about the delay in disbursement of compensation amount and also informed that they frequently visited District Administration for availing the compensation. 47. Satisfaction level regarding R&R assistance: The study revealed that 75% PAPs were satisfied with the R&R assistance. The PAPs (25%) who were not satisfied with the assistance intimated that the amount was divided among family members. In case of the PAPs who were relocated, 72% were satisfied with the assistance provided for relocation. 48. PAPs also intimated some cases of severance of land and consequent difficulties faced. In two cases, tube wells owned by PAPs were located on the other side of the track and had to spend additional money to reinstall the same which included purchase of the tube well and boring cost (case of Hayatpur Bajhera and Khera Khushkhabar villages of Aligarh). 3.6 Training of PAPs 49. DFCCIL provided training to PAPs on various trades like helper, electrician, fitter and data entry operator. Altogether, 729 PAPs7 were given training. One of the trainings was provided by M/s Premvati Devi Private ITI situated in Bedai, Sadabad (Hathras District), UP. DFCCIL communicated to Skills Education Pvt. Ltd., an initiative under Ministry of Skill Development and Skill Education Pvt. Ltd., further entrusted Premvati Devi Private ITI for imparting training to the PAPs. Discussion with Premvati Devi Private ITI representatives revealed that 105 PAPs were trained (mostly belonging to BPL families) for duration of 4-5 months in the field of electrician (75% PAPs) and fitter (25% PAPs). Premvati Devi Private ITI had arranged for placement of 60% of the trained candidates. The ITI also forwarded the two-month’ salary-statement of respective candidates to DFCCIL. It was also reported that approximately Rs.1500 per candidate was obtained from Skill Education Pvt. Ltd., to Premvati Devi Private ITI for imparting training. 50. The study observed that 39 PAPs (3%) have received training, of which 37 PAPs received training through ITI which was empanelled by DFCCIL and 2 PAPs received training through contractor in the field of stone-pitching and trackman. These PAPs were employed by the contractor. PAPs have received training of fitter, welder and electrician. 7 Data as on May 2020, Source: DFCCIL. CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST Page | 15 Final Report End-Term RAP Impact Evaluation of Land Acquisition and R&R Implementation for EDFC-1 (Khurja – Bhaupur Section) 51. Further telephonic conversation with 9 trained candidates, who were in the list provided by DFCCIL, revealed that they had received training but had not received any job, one of the trainees said that he had rejected the job-offer due to low salary (Rs.4,000 - 5,000 per month). 52. These trainings were part of the income restoration measures aimed at restoring livelihood conditions of the PAPs. RAP provides for training assistance for income generation through NGOs and temporary employment in construction (with a condition, “if available for civil work and opted by the PAPs”). The facilitating NGO is mandated with responsibility of motivating PAPs to take part in the identified government sponsored income generation schemes. In Hathras District, the PAPs who received training had staged protests against the DFCCIL for not providing job ‘as promised’ during the time of land acquisition. The protested PAPs demanded job in the government sector. Newspaper excerpts of various protests are given in Annexure IX. 3.7 Status of Land Handover and Impact on Construction 53. Status of Land Handover: Focus Group Discussions carried out with the representatives of the Contractor and PMC revealed that the handing over of encumbrance-free land was delayed and was treated as one of the major delay-events while the Contractor computed the prolongation cost. 54. As per the Contract, the first milestone is possession of 80% of the land within 28 days of the contract. The second milestone is possession of 90% of the land within 91 days of the contract and the third milestone is possession of 100% of the land within 182 days of the contract. 55. Completion dates against respective milestones were computed based on the scheduled date of site-possession. In this regard, the delay in handing over of 80% of the land ranged from 1 day to 129 days (i.e. average delay of 51 days). Further, the delay in handing over of 100% of the land ranged from 240 days to 1778 days (i.e. average delay of 1160 days). 56. Other Delay-events: The Contractor also pointed out about various other delay-events including delay relating to shifting of utilities, delay in removal of Optical Fibre Cable (OFC) and Signal and Telegraph (S&T) cables in parallel sections, shifting of electric line, delay in appointment of PMC Engineer, civil disturbances arising from the non-payment/delayed payment of compensation to the villagers, etc. The cost incurred against the delay specifically due to the delay in handing over of encumbrance-free land was not available or not disclosed by the Contractor. The prolongation cost claimed is around 19% of the total contract value and the claim is pending for decision by Dispute Adjudication Board. 57. Obstruction by Local Community People: Perusal of the communication details of the contractor revealed that around 36 incidents of villagers’ agitation leading to stoppage of civil works were reported from the year 2014 to 2017. Out of these incidents, more than half of the reported cases were related to land acquisition or related compensation payments. Other than the land related agitations, the villagers’ also obstructed the work demanding re-sizing of RUB/minor structures or its location-changes and demand for access road or its maintenance, etc. Details of land-related hindrances as per the contractor’s communication one of the construction packages is given in Annexure X. ‘Offer of Jobs’ to project affected families against loss of livelihood was also reported to be one of the reasons. CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST Page | 16 Final Report End-Term RAP Impact Evaluation of Land Acquisition and R&R Implementation for EDFC-1 (Khurja – Bhaupur Section) 3.8 Impact on Common Property Resources 58. Common Property Resources (CPRs) have been relocated as observed during the visit to randomly selected CPRs in six (6) locations (Two in Agra and one each in Auraiya, Etawah, Hathras and Aligarh). Discussions with community people in various CPR locations showed that the impacted CPRs were relocated considering its existed structure and architecture and in many cases, enhanced facilities were also provided (Annexure XI). Overall, the community people were satisfied with the relocation of CPRs, and they appreciated the efforts taken by DFCCIL, except for the delay occurred for completing the work by the contractor as per agreed schedule, and that too even after the required land were made available to the contractor for relocation of affected CPRs. 59. The identified CPRs were grouped under two broad categories, ‘charted’ and ‘uncharted’. Those CPRs which were potentially impacted and that were identified before mobilisation of the civil work contract were all treated as Charted. Relocation of charted CPRs rests with the civil work Contractor. Those CPRs which were identified during the civil work implementation stage were all grouped under Uncharted. 60. Altogether 27 CPRs were identified for relocation, of which 24 were charted and 3 were uncharted. Out of the total, 11 CPRs were from Aligarh district, 5 CPRs from Hathras district, 4 CPRs were from Etawah, 3 CPRs from Firozabad district, 2 CPRs were from Kanpur Dehat district and one CPR each from Agra and Auraiya district. The impacted CPRs include religious structures like, temples and rest houses and also crematorium and graveyard. 3.9 Corporate Social Responsibility Activities 61. RAP states that “DFCCIL will take social responsibility for reconstruction of community structures and replacement of common property resources like temple, schools, colleges, roads, and hospitals in consultation with the community. The facilitating NGOs will organize public consultation with concern stakeholder‘s to decide the CSR work to be done by DFCCIL. However, the DFCCIL will follow GoI guidel ines to plan and carry out CSR”. DFCCIL’s CSR is envisioned as a commitment to meet its social obligations by contributing towards improving quality of life of the communities and stakeholders on a sustainable basis, preferably in the project areas where it is operating. 62. Overall CSR Activities in DFCCIL: CSR Policy was framed by DFCCIL in 2011-2012 based on the guidelines issued by Department of Public Enterprise in April 2010 and was issued formally to the Ministry/ Department for compliance in the Central Public Sector Enterprise (CPSEs). Accordingly, during 2011-2012 two key areas were identified (i) computer education and (ii) eco-sanitation, for providing input for development of persons residing in project affected areas. An amount of Rs. 20 lakh was spent on the said activity. During 2012-2013, vocational/ technical trainings were provided to 891 PAPs with a view to generate employment. An amount of Rs. 18 lakhs were spent on vocational/technical training. During 2013-2015, two key areas were identified (i) computer literacy (23 computers were provided in 15 schools under the jurisdiction of project affected areas) and (ii) Vocational training (651 PAPs were provided training with a total 35,032 man days) for providing input for development of persons residing in project affected areas. An amount of Rs. 18 lakhs were spent on vocational training. CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST Page | 17 Final Report End-Term RAP Impact Evaluation of Land Acquisition and R&R Implementation for EDFC-1 (Khurja – Bhaupur Section) 63. During 2014-2015, DFCCIL signed MoU with Confederation of Indian Industry (CII) on 18th November 2015 as a part of CSR Activity to provide vocational training to 1000 PAPs/BPL youth (also known as project ‘SAKSHAM’) at 4 CPM units including Tundla [(i) Allahabad West (ii) Tundla (iii) Mumbai and (iv) Jaipur]8. 64. Discussion with DFCCIL and Contractor has revealed that 13 CSR activities were undertaken in EDFC-1. 65. During 2014-2015, an amount of Rs. 2.50 lakhs were spent on construction of toilet blocks in a primary school under Swachh Vidhyalaya Campaign in Firozabad district. 66. In the year 2017-189, DFCCIL had allocated Rs. 10 lakhs for Tundla CPM unit as well as Ahmedabad (Western Dedicated Freight Corridor) for the provision of computers in schools/ computer literacy. Accordingly, office of the CPM, Tundla has purchased desktop computers, printers and computer accessories for Government schools located along the project affected villages in the districts of Firozabad, Etawah and Agra. The computer systems were distributed to Schools for providing computer training to the students. 67. In the year 2018-1910, as part of the CSR activities of DFCCIL, office of the CPM, Tundla had provided cash-assistance of Rs. 15 lakhs to the District Administration of Firozabad and Agra respectively towards construction of Public Conveniences. Contractor also gave support to schools located in project location by constructing building for library and providing books. 68. In the year 2019-2011, Skill Interventions in Schools to improve the employable skills and physical fitness of the students was conducted through CII in four CPM units including Tundla [(i) Greater Noida/ Meerut (ii) South Mumbai (iii) Ajmer/ Jaipur and (iv) Tundla]. DFCCIL allocated Rs 100 lakhs for the said activity. Details of CSR activities are given in Annexure XII. 3.10 Cost of Land Acquisition and Resettlement 69. During land acquisition, the total compensation amount disbursed to the PAPs was Rs.719.38 crores. R&R assistance of Rs.68 crore was allocated of which Rs.58 crore was disbursed to the PAPs. So far, 846 PAPs have been identified for the disbursement of the R&R Assistance amount (i.e. one-time resettlement allowance and annuity) which is in progress. 70. As per RAP, the total land requirement of the project was 1442.15 ha. The total project cost (cost of civil works, electric works, cost of land, R&R assistance, relocation cost of CPRs and implementation charges) was Rs.5761.83 crore. The cost estimate for land acquisition and R&R assistance includes cost of land, cost of structure, R&R assistance, relocation cost of CPRs and implementation charges. The total cost incurred for various activities related to RAP implementation is estimated to be Rs.1269.72 crore which includes cost of land, R&R assistance and cost of consultancy. Thus, 22% of the total project cost has been 8 Source: DFCCIL Letter No. HQ/HR/35/CSR/2015-16 dated 21.12.2015 9 Source: DFCCIL Letter No. HQ/HR/CSR Activities 2017-18 dated 31.07.2017 10 Source: DFCCIL Annual Report, 2018-19 and DFCCIL Letter No. HQ/HR/CSR Activities 2018-19 dated 21.08.2018 11 Source: DFCCIL Annual Report, 2018-19 and DFCCIL Letter No. HQ/HR/CSR 2019-20 dated 31.07.2019 CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST Page | 18 Final Report End-Term RAP Impact Evaluation of Land Acquisition and R&R Implementation for EDFC-1 (Khurja – Bhaupur Section) incurred towards land acquisition and resettlement. Also, compared to the estimated during RAP, the RAP implementation expenditure is higher by 1.6 times. This is attributed to the escalated cost of land compensation as per the new Act, RFCT-LARR 2013 and Uttar Pradesh Direct Land Purchase Policy and R&R assistance as per the EM-2015. Item wise expenditure of RAP implementation is given Table 3-1. Table 3-1: Item-wise expenditure for RAP Implementation of EDFC 1 S. Budget as per RAP Expenditure Item No. (Rs.in crore) ^ (Rs.in crore) 1 Cost of Land 322.18 1176.85 2 R&R Assistance 81.35 89.17 3 Relocation of CPR* 1.69 0.0 Implementation Charges (Training, Administration, 74.37 3.70 4 Management, Capacity building, Monitoring, NGOs etc.) Total 479.59 1269.72 Note: *The relocation cost of CPR is the part of the contract document of contractor. ^ The Budget as per RAP includes contingency @8%. Source: RAP-2011 and DFCCIL (as on November, 2019) 3.11 Grievance Committee’s Impact 71. Grievance Redress Committee (GRC) as mentioned in the RAP was formulated in all the districts. The GRC comprised the following members: District Collector of the concerned District, Chairman Zila Parishad Chairperson/ his or her nominee Concerned Competent Authority/ Administrator Concerned Assistant Project Manager of DFCCIL Representative from Civil Society/ a reputed local NGO 72. The grievances of the PAPs were regarding enhancement of compensation, delayed disbursement of compensation, compensation not provided of the additional land acquired, R&R and handicapped assistance not received, more land acquired than marked, community issues related to water logging, damaged access roads. The grievances were usually submitted to the DFCCIL site office, Head Quarter or to the Arbitrator. The cases filed with the Arbitrator were mostly done with the help of legal practitioners. 73. Till July 2019, a total of 1,581 grievance cases were recorded of which 1,570 cases (99%) were resolved. The decision has been pending for remaining 11 cases (1%). It is observed that most of these cases were not directed to GRC but were dealt and resolved within the site offices of DFCCIL. Study also observed that 16% of the PAPs were having adequate knowledge of various procedures for filing grievances with GRC. The detailed procedure of handling grievances by DFCCIL is given at Annexure XIII. 74. Study observed that, 151 PAPs (12%) have submitted grievance cases at various levels of District Administration and to the site offices of DFCCIL. Majority of the PAPs (67%) were satisfied with the decision. CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST Page | 19 Final Report End-Term RAP Impact Evaluation of Land Acquisition and R&R Implementation for EDFC-1 (Khurja – Bhaupur Section) 75. The Concurrent Monitoring Team appointed by the DFCCIL had observed that there was lack of awareness among the PAPs regarding grievance redress system. The GRC couldn’t be convened for resolving issues of aggrieved persons quickly due to its size. Accordingly, the Monitoring Team suggested for modifying the constitution of GRC in order to make it functional. The Monitoring Team also observed some hindrances to the smooth and efficient functioning of the grievance redress mechanism such as (i) lack of awareness among PAPs regarding who to approach for grievance redress, (ii) lack of direct communication with PAPs – and as a resolution the monitoring team had suggested coordination with respective Sarpanch and display of GRC information at prominent places, and (iii) delay in inter- departmental coordination for grievances requiring intervention of other state level departments. World Bank in its site-visit note (22-25 June 2018) noticed that communication and coordination between the DFCCIL, LA Authority and PAPs remained an issue in the Project, as PAPs were not aware of the entitlements, approval of supplementary micro plan, and disbursement of payments and availability of GRC. 76. Status of Complaints forwarded to the World Bank: There were 36 complaints by 28 PAPs submitted directly to the World Bank through e-mail. These complainants were from the districts of Auraiya and Etawah. The World Bank along with DFCCIL officials from Kanpur site office and Concurrent Monitoring Team conducted meetings with the complainants in project locations. DFCCIL had regularly updated the action taken against respective complaints to the World Bank. As per the data received from the site office, 30 complaints were resolved which pertained to (i) enhancement of compensation (ii) livelihood assistance as per new land acquisition Act (iii) discrepancy in measurement of affected area (iv) acquisition of residual land (v) non-receipt of compensation and R&R assistance (vi) request for construction of a culvert (vii) request for alignment change to avoid impacts. To understand the satisfaction level of the complainants, a discussion was conducted with 5 complainants wherein 4 PAPs intimated that they were satisfied with the decision and one PAP was not satisfied as his case for non- receipt of compensation was pending in Court of Law. 3.12 Arbitration and Court Cases 77. Arbitration Cases: As per Clause (6) of Section 20F of the Railway Act, 1989 (24 of 1989), Arbitrator has to be appointed for determining the payment of compensation to the PAP; when the PAP was not satisfied with the compensation provided. Commissioners of Kanpur, Agra and Aligarh were respectively appointed as Arbitrators. Till July 2019, 2879 Arbitration Cases were filed of which136 cases (5%) were pending. 78. Out of the 136 pending cases, 56% cases were pending for the last 12-24 months and 42% cases were pending for more than 24 months. The reason pointed for the delay in disposing the cases was inadequate time-availability of respective Commissioners. The absence of PAPs during the hearing has also delayed the processes. Most of the arbitration cases were filed for enhancing the compensation rates. CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST Page | 20 Final Report End-Term RAP Impact Evaluation of Land Acquisition and R&R Implementation for EDFC-1 (Khurja – Bhaupur Section) 76 Number of Cases 100 57 83 100 77 Number of Cases Total Number of 50 Cases 2 1 Number of Cases 0 50 Resolved <6 6-12 12-24 >24 9 1 2 0 months months months months old old old old 0 Timeline of Cases District Court High Court Supreme Court Figure 2: Timeline of Arbitration Cases Figure 3: Cases Filed in Court and Cases Resolved Source: DFCCIL, 2019 79. Court Cases: Till July 2019, there were 161 cases filed in various courts (District Court, High Court and Supreme Court), of which 151 cases were pending for decision. Cases were related to enhancing rate of compensation, demand for payment of interest rate due for delayed disbursement, appeal against the Arbitrator’s decision. Two cases were from Etawah which was under review of Supreme Court, filed by the PAPs demanding payment against the acquisition of their land declared under section 20E but not awarded under 20F. In this case, the High Court ruled in favour of DFCCIL referring to its communication which stated that Railways did not propose to utilize the land declared for acquisition under section 20E and also referring to section 20F (2) the said declaration stand lapsed. Table 3-2: Details of Cases Filed in Court District Court High Court Supreme Court Grand Total Filed Pending Filed Pending Filed Pending Filed Pending 77 68 83 82 1 1 161 151 Source: DFCCIL, 2019 80. Analysis of the timeline of filed cases in various Courts shows that 56% of cases were pending for more than 24 months and 20% cases were pending for more than a year. Overall, nearly 96% of cases filed were pending for decision. 81. As per the study, majority of the PAPs intimated to have hired legal practitioners for arbitration/ court cases. Out of the total PAPs, 21% submitted arbitration/court cases. Out of the PAPs who had submitted their cases, 26% intimated that the arbitrator’s/ court’s decision benefitted them as it was in their favour. Whereas, 42% intimated that the arbitrator’s/ court’s decision was not in their favour. The cases of remaining 32% PAPs were pending. 3.13 Local Employment Creation 82. The project has generated local employment to 4,193 persons12 since January 2014. Local entrepreneurs also emerged as part of the project for supply of local labour as well as construction materials, construction vehicles, etc. Majority of the PAPs were satisfied with the employment conditions, 12 Sources: (i) Employment Records of the Contractor, (ii) Discussion with DFCCIL Officials, (iii) FGD with the local people employed by the Contractor. CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST Page | 21 Final Report End-Term RAP Impact Evaluation of Land Acquisition and R&R Implementation for EDFC-1 (Khurja – Bhaupur Section) wages and facilities provided by the contractor. FGD was conducted with the PAPs employed by the contractor which is presented in Table 2-2, sl. no. 8 under ‘PAPs employed by the contractor’. The number of man-days vary from a day/week to a year or more depending on the project duration. Discussions with the local employed persons revealed that their average wages range between Rs.450-550 per day and for some jobs like watchmen, office assistant, site-supervisor, laboratory-assistant, electrician, stone-crushing and pitching, etc., the wages range between Rs.8,000-15,000 monthly respectively. Stone-crushing work involved heavy physical work and youngsters were usually preferred. One wagon of stone is rated at Rs.2000 and about 4 persons could complete 1 -2 wagons of stone. The study observed that the average wage of the local employed persons was 15% more than the minimum wage rates. The detailed study of the local employment is given at Annexure XIV. 3.14 Impact on Women 83. Development projects improve the living conditions of women by taking into account the women’s participation and as well as their real needs. The study has carried out the consultations with women groups in order to understand the impact of the project on the women community. 84. Till July 2019, out of a total of 25,472 PAPs, 3,345 (13%) were women PAPs. Out of these women PAPs, 94 (3%) were physically displaced. Out of the total physically displaced PAPs, women PAPs accounts for 18%. The compensation and R&R assistance were disbursed to 3344 women PAPs. The one physically displaced women PAP has not accepted the compensation as she has demanded for enhanced compensation and hence the R&R assistance is not yet disbursed. Further, out of 729 PAPs provided skill training, 70 PAPs (10%) were women. These women PAPs were provided training in garment making (from ITI Kanpur), welding and electric (from ITI Etawah). The study revealed the following: (i). Socio-economic changes: (a) Occupation: The occupation pattern of women remained unaltered. As per the baseline study, most of the women were housewives and the pattern continued during end-term evaluation study as well. The remaining women PAPs were engaged in various occupations such as agriculture, wage-labour, trade and service (in government and non-government organisations). (b) Income level: The average annual income (in real terms) of the women PAPs was Rs.31,640 and that of control population was Rs.34,480. The study observed that the annual income level of the women PAPs was 8% lower compared to control population. (c) Indebtedness: Indebtedness was reported for 22% women PAPs. Majority of the women PAPs utilised the compensation amount in repaying a portion of their debt. In case of control population, indebtedness was reported for 31%. (d) Standard of Living: The study revealed that the area of existing residential structure of both women PAPs (88%) and male PAPs (90%) has increased. Both intimated that the new houses constructed were better than the old houses. The living condition of 39% women PAPs have improved considerably as they were able to construct ‘pucca’ houses (houses made of bricks, RCC permanent CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST Page | 22 Final Report End-Term RAP Impact Evaluation of Land Acquisition and R&R Implementation for EDFC-1 (Khurja – Bhaupur Section) structure), renovate house, purchase cattle, repay part of their debt, spend on medical as well as educational needs and also on household chores and the situation was same for male PAPs. (ii). Awareness about Act/ Policy applicable for the project: Majority of the women PAPs (63%) were aware about the Act/ Policy through which their land was acquired. Awareness among women PAPs were at par with their men counterparts. (iii). Disbursement of compensation and R&R assistance: Out of the 176 women PAPs, all received the compensation and R&R assistance. They study revealed that 18% women PAPs have approached the Arbitrator/ Court cases for enhancement of compensation. (iv). Difficulty faced during receipt of entitlements: Majority of the PAPs (76%) intimated that they did not face any difficulty in receiving the entitlements. The remaining 24% intimated that they have faced difficulties such as (i) frequent visits to District Administration/DFCCIL for availing the entitlements, (ii) staging of protests for enhanced compensation and (iii) delayed payment of entitlements. (v). Level of Satisfaction: Out of the total women PAPs, 50% were satisfied with the entitlements provided. On the other hand, 40% men had expressed their satisfaction. Both men and women who expressed their satisfaction revealed that the entitlements have positively contributed towards improving their standard of living. Both were able to construct or renovate houses, repay part of their debt, spend on medical as well as educational needs and also on household chores. (vi). Physically displaced women PAPs: The study observed that no physically displaced women PAPs were provided employment. Out of the total Women PAPs, 56% were satisfied with the compensation amount as well as R&R assistance. The living conditions of 39% women PAPs have improved as they were able to construct house, purchased land and purchased cattle. They intimated that the compensation amount and R&R assistance received was adequate enough to replace their affected / lost asset. 3.15 Institutional Arrangement for RAP Implementation 85. Social and Environmental Management Unit (SEMU) was responsible for implementation of RAP in coordination with 3 Offices of Chief Project Managers (CPM) - DFCCIL at Agra, Kanpur and Aligarh respectively. There were 3 contractual employees in respective offices of CPM, who were reporting to Senior Executive Engineer. These employees were responsible for land acquisition processes, resettlement & rehabilitation and training procedures. In addition to the above-mentioned duties, the contractual employees were also responsible for handover of advance-notices to PAPs, liaising with revenue officials and disbursement of compensation/assistance amount. 86. The contractual staffs also included retired revenue officials who facilitated DFCCIL works. Two NGOs were contracted by DFCCIL for Aligarh, Kanpur and Agra respectively. However, the contract of the NGOs was concluded on prescribed dates and the remaining works were handled by DFCCIL officials. Discussion with various officials revealed that most of the staffs in the position of Project Managers and above were having technical background in engineering and lacks specific experience in land acquisition CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST Page | 23 Final Report End-Term RAP Impact Evaluation of Land Acquisition and R&R Implementation for EDFC-1 (Khurja – Bhaupur Section) and resettlement related aspects. Officials received training on social safeguard implementation through the training organized by NGO and Concurrent Monitoring Team. 87. RAP implementation by NGOs: Two NGOs were contracted by DFCCIL for Aligarh, Kanpur and Agra respectively. NGOs had supported the project by organizing camps to identify the affected persons. NGOs had also helped to disburse the R&R assistance by preparing Micro Plan. The support of NGO helped in smooth disbursement of the compensation to the PAPs. Further, the NGO liaisoned with PAPs to help them submit requisite documents for receiving the compensation and R&R assistance and also disseminated requisite project information. As per RAP, NGOs should work with the PAPs and the line departments to dovetail the government sponsored income generation schemes for the benefit of PAPs. However, such dovetailing had not taken place. NGOs had prepared the list of PAPs eligible for training. DFCCIL later arranged for the training in identified institutes. 88. Monitoring and Evaluation by Concurrent Monitoring Team: Consultants were appointed by the DFCCIL to carry out quarterly review of social and environmental safeguard activities implemented in the project. Three Consulting Agencies were contracted by DFCCIL since inception of the project. The Concurrent Monitoring Team had identified the gaps in the implementation of RAP and had suggested corrective measures. The major issues identified were related to (i) periodic progress on land acquisition, disbursement of compensation and R&R assistance, grievances and stamp duty redemptions (ii) institutional snags leading to impediments in the process of acquiring land, (iii) procedural delay in providing entitlements and (iv) opinion and suggestions of PAPs received through specific consultations and one-to-one interviews. The Concurrent Monitoring Team had also imparted training to the officials of DFCCIL, PMC, Contractor and NGO regarding implementation of RPF, RAP and its compliance. CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST Page | 24 Final Report End-Term RAP Impact Evaluation of Land Acquisition and R&R Implementation for EDFC-1 (Khurja – Bhaupur Section) 4. CONCLUSION AND RECOMMENDATION 89. The key findings, lessons learnt and outstanding issues along with recommendations are summarized in this section. Based on the impact evaluation, the study suggests remedial measures as required to meet out the objective of R&R implementation. The DFCCIL should monitor the outstanding actions beyond the impact evaluation study, which include disbursement of compensation and R&R assistance, rectifying post-construction damages to affected residential structures, approach roads and assurance on commuters’ safety. 4.1 Key Findings A. Socio-Economic Findings (a) Occupation Profile: Occupation pattern of the PAPs remained unaltered. Majority of the PAPs were engaged in agriculture and allied activities. A reduced level of unemployment was observed in comparison to the baseline. (b) Income Level: In comparison to the baseline, the income of PAPs has increased. The average annual income level of the PAPs have increased by 26% over baseline. The study also observed that the average annual income level of the PAPs was 15% lower than the Control Population. The average annual income of the PAPs who were compensated as per RFCT-LARR, 2013 was at par with control population (with a difference of 6%) than the PAPs who were compensated as per RAA, 2008 (with a difference of 26%). The average annual income of the PAPs who were compensated based on RFCT-LARR, 2013 fared better than the PAPs who were compensated based on RAA, 2008. The average annual income of PAPs below poverty line has increased 1.4 times as compared to the baseline. (c) Indebtedness Indebtedness reported for 37% of the PAPs against 81% of PAPs during baseline. One-third of the PAPs utilised the compensation amount and R&R assistance in repaying a portion of their debt. (d) Housing Condition: Housing condition of the PAPs remained unaltered. Majority of the PAPs were living in ‘pucca’ house (houses made of bricks, RCC permanent structure). In terms of facilities (i.e. having separate kitchen, bathroom and toilet), no change was observed in the study period in comparison to the baseline period. CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST Page | 25 Final Report End-Term RAP Impact Evaluation of Land Acquisition and R&R Implementation for EDFC-1 (Khurja – Bhaupur Section) (e) Standard of Living: The compensation money gave the PAPs an opportunity to purchase new lands, construct new houses or renovate their old houses. Study observed that 58% of the PAPs reported utilizing money for investment in new business and/or clearing the existing debts and spend on improved medical and educational facilities. B. Land acquisition and Rehabilitation & Resettlement Support i. Land Acquisition: Total land acquired for the project was 1339.35 ha., of which 1188.77 ha., was private land. The land acquisition followed RAA, 2008 except 4.72 ha., which was acquired through Uttar Pradesh Direct Land Purchase Policy, 2015. As on July 2019, 10.39 ha. of land was remaining to be acquired. On an average, one PAP has lost 0.05 ha. of land to the project. As per the study, 87% PAPs has lost less than 0.1 ha. of land to the project. ii. Timeline of Land Acquisition: The notification and various procedures followed for acquiring land was in compliance to the RAA, 2008 and the procedures were done within the prescribed timeframe. iii. Disbursement of Compensation and R&R Assistance: The disbursement of compensation and R&R assistance have largely progressed. As on July 2019, a total of 785 land owners (3%) are yet to receive compensation and 811 PAFs (8%) are yet to receive R&R assistance. The disbursement of compensation amount and R&R assistance for the remaining PAPs were in progress at the time of the study. iv. Resettlement Support: Stamp Duty Reimbursement: In case of stamp duty redemption, 26% claims were rejected due to various reasons such as (i) submission of requisition after the prescribed one-year, (ii) land was not purchased in the name of the entitled person, and (iii) claim submitted against the purchase of different category of land (other than the affected land category). Relocation time given to PAPs: PAPs were not satisfied with the timeframe of 3-months given for relocation. C. Satisfaction Level and Perceptions of the PAPs: Study showed that 40% of the PAPs were satisfied with the compensation amount. The remaining 60% of the PAPs who were not satisfied with the compensation amount opined that the compensation amount was not adequate to replace their lost assets. Three-fourth of the physically displaced PAPs expressed their satisfaction regarding the assistance provided. CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST Page | 26 Final Report End-Term RAP Impact Evaluation of Land Acquisition and R&R Implementation for EDFC-1 (Khurja – Bhaupur Section) D. Grievance Redress Mechanism: Grievance Redressal Committee as mentioned in the RAP was formulated in all the seven districts where the EDFC -1 traverses. The grievances of the PAPs were related to enhancement of compensation, delayed disbursement of compensation, compensation not provided of the additional land acquired, R&R and handicapped assistance not received, more land acquired than marked, community issues related to water logging, damaged access roads. Most of the grievance cases were not directed to GRC but were dealt and resolved within the site offices of DFCCIL. Study observed that 84% of the PAPs were not aware of the various procedures involved to file grievances with GRC. E. Local Employment: The project has generated local employment to 4,193 persons in various jobs like watchmen, office assistant, site-supervisor, laboratory-assistant, electrician, stone-crushing and pitching. Local entrepreneurs were also emerged and were engaged in supplying of local labour as well as construction materials and construction vehicles. F. Relocation of Common Property Resources: There were 27 CPRs relocated in this DFCC project stretch, of which 24 were categorised as ‘charted13’ and were relocated by the Contractor. The ‘uncharted14’ CPRs were relocated by DFCCIL. The community people were satisfied with the relocation of the CPRs. The participation of the community was evident in relocation of most of the CPRs. G. Impact on Women: Compensation and R&R assistance has been disbursed to all the women PAPs. They intimated that they did not face any difficulty in receiving the same. The overall distribution of income and indebtedness showed that women PAPs are economically at par with their counterpart in control population. The area of existing residential structure of both women PAPs (88%) and male PAPs (90%) has increased. Further, equal improvements were observed in the living standards of both women and male PAPs. H. Handing over of Encumbrance-Free Land to Contractors: Delay in handing over of land to the contractor was observed in all the three Lots of EDFC 1. Achieving 80% length, was delayed by average 51 days against the timeline as per contract. Achieving 100% length was delayed by average 1160 days against the timeline as per contract. 13 CPRs included under the scope of Civil Works Contract 14 CPRs not included under the scope of Civil Works Contract CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST Page | 27 Final Report End-Term RAP Impact Evaluation of Land Acquisition and R&R Implementation for EDFC-1 (Khurja – Bhaupur Section) 4.2 Lessons Learnt (a) Displaced persons/families who were not willing to relocate after the expiry of advance notice period posed challenges. Except few cases, relocation support was observed to be limited to disbursement of compensation amount and R&R assistance. To the best possible extent, an appropriate community system (involving local government bodies, social activists, knowledgeable persons) for smooth relocation of displaced persons/families should be developed for relocation purposes. Counselling support should be provided in order to minimize the inherent hardship faced by PAPs during relocation. (b) Relocation Support to Informal Settlers (NTH): As per EM-2011, informal settlers were eligible for structure compensation and R&R assistance. The study observed a case of Douru Chandpur village, Aligarh wherein the displaced informal settlers had not had any planned relocation site. The policy document (i.e. Acts/Entitlement Matrix 2011) does not have any provisions in such cases as elaborated above. As per the New Entitlement Matrix 2015, “those occupying village common lands/abadi lands prior to 1961 shall be eligible to be treated as ‘regularised land holders’ as permitted by law and shall be provided with alternative land or site allowance equivalent to land compensation”. This provision was not included in the EM 2011. Hence, the project should earnestly support the informal settlers whose land has been acquired and should provide equivalent support as in the case of title-holders to support and save their livelihoods. (c) Training of PAPs: DFCCIL has made very systematic arrangement for providing training to PAPs. Priority was given to those PAPs belonging to below-poverty-line (BPL) category through recognized institutes. It was observed that 60% of the trained candidates received job post-training and their two-month salary statements were also forwarded to DFCCIL. Many of the trainee PAPs rejected the job offer due to inadequacy in the remuneration offered. Many cases of protests by trainee PAPs were reported disrupting the overall project progress. Adequate communication regarding the entitlements – livelihood training related aspects requires to be clearly communicated to PAPs. Awareness campaigns in affected villages should be more transparent and should specifically include the details of proposed trainings. Post-training procedures adopted by the DFCCIL should be documented and disseminated in public domain. (d) Stamp duty redemption: Out of the total 592 requisitions for stamp duty reimbursements, 158 (26%) were rejected due to reasons such as (i) submission of requisition after the prescribed one- year, (ii) land was not purchased in the name of the entitled person, and (iii) claim submitted against the purchase of different category of land (other than the affected land category). Project should consider these rejected claims and include project-affected-families as unit of entitlement and should also include purchase of different category of land also as eligible. The time period for claim should be relaxed to at last two years or till end of the RAP implementation. (e) Corporate Social Responsibility: CSR activities carried out in project villages are appreciative; at the same time require a mechanism for follow-up for ensuring sustainable delivery of benefits. It is also noticed that the Computer Systems provided as part of the CSR activity of DFCCIL were taken away by interested parties thereby denying the intended benefits to students/schools. With CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST Page | 28 Final Report End-Term RAP Impact Evaluation of Land Acquisition and R&R Implementation for EDFC-1 (Khurja – Bhaupur Section) respect to transfer of fund to district administration, the details regarding utilization of specific fund by the District Administration for the intended purpose was not known. Appropriate institutional mechanism should be in place for sustainable delivery of benefits, especially during the project cycle. For instance, ownership of computer systems should be transferred to the beneficiary school only after a specific period. Follow-up with District Administration should be made mandatory to ensure the utilisation specific cash transfers made. (f) Delay in handover of encumbrance-free land: The delay in land acquisition and subsequent handover of encumbrance-free land were pointed out as major components included in the prolongation cost-claims of the Contactor. In view of this, the overall RAP implementation system requires strengthening in future projects and also the targets set forth for achieving right to access continuous stretch requires relaxation. (g) Institutional Arrangement: A dedicated institutional structure was in place at DFCCIL HQ as well as in project site offices for the smooth implementation of RAP. This institutional structure was a strong platform which facilitated various procedures related to land acquisition, rehabilitation and resettlement. Staff requirements were in compliance with the RPF and existing staff has dedicatedly worked towards achieving the objectives of RAP. (h) Reinstating approach roads in villages and access roads near RUBs: Focus group discussions carried out across locations have highlighted issues related to (i) difficulty in accessing approach roads, and (ii) waterlogging conditions in RUBs. Although DFCCIL has instructed the Contractor for case-by-case resolution, the villagers were generally not satisfied with the prevailing system. Delay in resolving case is rampant across project locations. Reinstating access-roads near RUBs and also those approach roads used for movement of construction vehicles should be made more efficient. The project should prepare a Restoration Plan in coordination with local governing bodies for all damaged approach roads and access near RUBs. The budgetary provisions along with responsibility of respective agencies should be clearly mentioned in the Restoration Plan. (i) Grievance Redressal Committee: It is important to disseminate project information with emphasis on grievance redress mechanism among people through awareness programs. (j) Court Cases: Considering that the disposal rate of cases in civil courts is taking long time, the Concurrent Monitoring Team suggested that it would be imperative to open other avenues of dispute resolutions like negotiations, meetings and focus consultations. Community participatory dispute resolution mechanism followed in one of the project locations (in Hathras district, Aligarh) is emulative. (k) Delayed payment of compensation for land includes interest for the period of delay (12% per annum). However, delayed payment of R&R assistance does not include any such delay-interest. Project should take measures to provide delay-interest for R&R assistance. Resettlement Policy Framework should be amended accordingly. (l) Delay in disbursement of R&R assistance varies from village to village and case to case due to various reasons such as delay in official procedures of line departments, delay in submission of requisite documents by PAPs. Project’s coordination with line departments should be CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST Page | 29 Final Report End-Term RAP Impact Evaluation of Land Acquisition and R&R Implementation for EDFC-1 (Khurja – Bhaupur Section) strengthened. Timely submission of requisite documents by PAPs also helps pacing up disbursement of R&R assistance, for which services and support from RAP implementing agency should be hired. (m) Damages to reconstructed houses / assets: Train movements along the new alignment and consequent vibrations have damaged certain residential structures. In this respect, the Project should strengthen the post-construction surveillance through regular and more frequent site inspections rectifying the impacts due to train movement and also to resolve incidents of damages happened to re-constructed houses or other assets. Project should evolve mechanisms to organize informed meetings with Local Governing Bodies and community representatives. 4.3 Outstanding Issues and Suggested Action Plan 90. Outstanding issues identified during the study have been documented along with the suggestions for rectification. This includes (i) disbursement of payments to PAPs as compensation and R&R assistance, (ii) community issues related to post-construction damages due to train movement and consequent vibration, drainage and water logging issues, embankment erosion and consequent damages to agricultural fields, safety of women during night-travel along newly constructed RUBs, damages caused to approach roads and access to RUBs: a) Compensation disbursement: Issues: Out of 25,472 PAPs, compensation requires to be disbursed for 785 (3%) PAPs. Suggestions: DFCCIL should take help from local NGO or community mobilisers and organise camps in respective villages. Awareness to be raised among the PAPs regarding updating ownership details, and other documentation requirements related to payment of compensation. Also prepare the list of non-resident PAPs and communicate with them in consultation with local governing bodies. b) R&R Assistance: Issues: A total of 10,260 PAPs were identified for R&R assistance, of which disbursement is pending for 1,657 (16%) PAPs. Suggestions: DFCCIL should take help from local NGO or community mobilisers/volunteers and organise camps in respective villages to disburse remaining R&R assistance. Awareness to be raised among the PAPs regarding various documents to be submitted for processing and disbursement of R&R assistance. c) Post-construction damages to residential structures: Issues: In Naugaon village, Auriya and Maharara village, Hathras, partial demolition of PAP’s structures have resultant cracks on the remaining portion of the structure. In Kheriya village, Hathras, demolition of house affected the nearby house as well due to train movement and consequent vibration. CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST Page | 30 Final Report End-Term RAP Impact Evaluation of Land Acquisition and R&R Implementation for EDFC-1 (Khurja – Bhaupur Section) Suggestions: To avoid structure damage due to demolition, engineering code manual/ scheme should be prepared for the people residing parallel to the track. In case of vibration, impact of vibration and following procedures to minimize the impact should be taken up by the Project. d) Rain water along with mud from embankments damages agricultural field Issues: In Aat village, Kanpur Dehat & MenduKhas village, Hathras, due to rain, the mud and water runs-off from the track and accumulated in the agricultural field of the PAPs resulting in damage of crops. Suggestions: DFCCIL should inspect such cases along the alignment. To minimise the mud and water run-off provision for construction of Gabion wall, Toe wall, stone pitching, turfing should be adopted. e) Safety of Commuters, especially women Issues: In Alipur village, Aligarh, community people were concerned about the safety of commuters, including women who were using the RUB especially during night. Suggestions: DFCCIL/ Contractor should undertake installation of street lights and provide access facilities (earthen road or footpaths) under their CSR activities. Alternatively, DFCCIL should forward the matter to the State Government/ District Administration to resolve the issue. f) Water Logging in RUB and drainage problem Issues: RUB and stagnant water issue was reported in many places. In Jatanpur Chikavati village, Aligarh, pond got severed due to track alignment and the rainwater accumulated and run-off to residential area impacting 20-25 houses. In Kheriya village, Hathras, soil run-off and water logging damaged the religious structures. In Douru Chandpur village, Aligarh, disruption of drainage due to alignment resulted in water logging on the road leading to nearby school. Suggestions: Contractor should install dewatering pumps during the O&M period and the same should be entrusted to the local governing bodies or community representatives. Permanent solution to the problem should be evolved in consultation with PWD/local governing body. CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST Page | 31 Annexures Final Report End-Term RAP Impact Evaluation of Land Acquisition and R&R Implementation for EDFC-1 (Khurja – Bhaupur Section) Annexure-I Project details factsheet of EDFC 1 Bhaupur- Etawah Bypass Chamrola Etawah End to Chamrola Bypass End to Description Bypass End Bypass End Total Khurja Section Section Section EDFC 1 EDFC 1 EDFC1 Project Overview Total PAPs (Nos.) 8946 7326 9200 25472 Title Holders PAPs (Nos.) 8852 7326 9118 25296 Non-Title Holders PAPs (Nos.) 94 0 82 176 PAPs Loosing structure (Nos.) 107 203 313 623 Total displaced and relocated PAFs (Nos.) 103 210 55 368 Contract Value (in INR Crores) 132.94 925.9 1012.14 2071 14th March, Commencement Date 2013 14th May, 2013 14th May, 2013 22th April, Contractual Completion Date 2017 21th May, 2017 22th April, 2017 TATA-ALDESA TATA-ALDESA TATA-ALDESA Contractor "JV" "JV" "JV" SAI-TYPSA PMC Engineer SAI-TYPSA "JV" SAI-TYPSA "JV" "JV" Start Chainage 1040 Km 1170 Km 1266 Km End Chainage 1170 Km 1266 Km 1370 Km Length Parallel (in km) 95 72 69 236 Bypass Length (in km) (Detour) 40 29.56 38 107.56 No. of Villages 110 76 100 286 No. of Districts 3 2 2 7 Details of Structures Total ROB’s (in No.) 10 8 2 20 ROB’s Under Construction (in No.) 9 3 2 14 ROB’s Yet to be started (in No.) 1 0 - 1 Total RUB’s (in No.) 15 18 20 53 RUB’s Under Construction (in No.) 1 4 0 5 Junctions Station (in No.) 1 1 2 4 Crossing Station (in No.) 3 2 1 6 Level Crossing (in No.) 27 28 32 87 Private Land (in ha.) 497.75 313.97 377.03 1188.75 Government Land (in ha.) 77.57 38 35.02 150.59 Total Land (in ha.) 575.32 352.43 412.05 1339.8 PAPs (in No.) 8946 7326 9200 25472 As per UP State Policy Land Acquired in ha. 4.50 7 0 4.72 PAPs (in No.) 330 5 0 335 Compensation Disbursement Details Award Area (in ha.) 497.75 311.76 368.85 1178.36 PAPs (in No.) 8929 7107 8651 24687 Award Amount (in crore) 225.22 195.8 298.36 719.38 CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST Page | 1 Final Report End-Term RAP Impact Evaluation of Land Acquisition and R&R Implementation for EDFC-1 (Khurja – Bhaupur Section) Annexure II Detailed scope of work A detailed scope of work was adopted for the proposed assignment. The detailed scope includes: i. Socio-economic Impacts: This scope of the assignment study outlined the comparative background of project affected households during current (study) period and baseline period at RAP stage. This formed the background for evaluation of project impacts with respect to relevant parameters like changes in demographic profile, income status, debts status, occupation pattern, housing conditions, asset ownership pattern, cropping pattern, living standard, accessibility of basic amenities, etc. resulting for the implementation of LA and R&R acts/policies (both old and new as applicable). ii. Land Acquisition Process and Compensation Payments: This part of the study encompassed the evaluation of various stages of private land acquisition with respect to civil contract work schedule and assessment of reasons for delay in land handing over of encumbrance free land to the contractor as per the contract provision. It also present the comparison of actual land hand over timing with the original contract schedule, impacts on construction due to delay in land acquisition, compensation payment to contractors due to non-handing over of land as per contract provision and implications on project due to delay in land handing over. It also covers the various compensation related aspects including adequacy to replace lost assets, way of spending compensation amounts; current status of disbursement of payments for land acquisition; status of payment for pending compensation and R&R assistance; methods of finalization and comparison of compensation rates under the old act, new act and direct purchase policy; satisfaction of PAPs on compensation rates and payments including PAPs who have not taken compensation due to dissatisfaction of rates. iii. R&R Process: This activity focused on the various components of R&R process covering both BPL and non BPL displaced families to understand the resettlement arrangements/alternative arrangements that were made for the displaced families including various types of livelihood support provided from the project to re-establish their housing as per New Entitlement matrix (EM) effective from January 1st 2015. It also provided detailed information on comparison of displacement methods adopted under the RFCT-LARR Act 2013 and direct purchase policy as well as assessment of satisfaction status of PAPs on R&R payments and resettlement support provided to them. iv. Cost of Land Acquisition and Resettlement: This section comprised of analysis of costs involved for various actions associated to land acquisition and resettlement as well as comparison with the overall project cost to draw conclusions on cost allied to land acquisition and resettlement. v. Grievance Committee’s Impact: The present assignment analyzed the functions and effectiveness of the various levels of Grievance Redressal Committee (i.e. DFCCIL, District and CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST Page | 2 Final Report End-Term RAP Impact Evaluation of Land Acquisition and R&R Implementation for EDFC-1 (Khurja – Bhaupur Section) Senior level committees) formed for resolving the grievances associated with land acquisition and RAP implementation. It also focused on the outcomes of grievances redressed in terms of the PAPs that have benefitted and drew lessons for the improvement of existing mechanism. It also included the assessment of satisfaction status and feedback of PAPs on performance of various levels of Grievance Redressal Committees. At this stage the study also assessed the appeals to arbitrator and cases in court on various aspects of Land Acquisition and Resettlement & Rehabilitation implementation. vi. Local Employment: This study involved coordination with various contractors hired for the project construction to understand the local employment opportunities provided to the PAPs by them, including number of man days/months of jobs and how the local people got benefitted from the jobs was also be documented. In this study, interviews were conducted with some PAPs who have worked with the contractors to know their views and to assess their satisfaction with employment conditions, wages and facilities provided to them by the contractors. vii. Implementation Outcomes: In this stage the overall outcome of the proposed study has been summarized covering all the above mentioned aspects related to land acquisition, resettlement, impacts of both title and non-title holders, cost incurred for various activities, staffing, PMC, NGOs and Social and Environment Safeguard Monitoring and Review Consultancy (SESMRC) role, grievance redressal mechanism, etc. This also covered some of the grievance cases (both positive & negative), lessons learnt, innovations made and challenges faced during the implementation of project. Based on this impact evaluation findings some follow-up remedial measures as required have also been proposed to meet out the objective of R&R implementation and to monitor the outstanding actions (if any) beyond the impact evaluation study. CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST Page | 3 Final Report End-Term RAP Impact Evaluation of Land Acquisition and R&R Implementation for EDFC-1 (Khurja – Bhaupur Section) CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST Page | 4 Final Report End-Term RAP Impact Evaluation of Land Acquisition and R&R Implementation for EDFC-1 (Khurja – Bhaupur Section) Annexure-III End Term Impact Evaluation Survey Questionnaire [Project Affected Persons] Dedicated Freight Corridor Corporation of India Limited Form No. __________Date____________ [A Government of India (Ministry of Railways) Enterprise] End-Term Impact Evaluation of Land Acquisition and R&R Name of Investigator_____________________ Implementation for EDFC-1 (Khurja-Bhaupur Section) Name of Supervisor______________________ Category (TH/NTH/BPL/SC/ST/Vulnerable):______________________________________________________________________ ID No. & Name: ___________________ Gender (M/F):________ Govt. ID No. (AADHAR/Voter/PAN/etc.):____________________ Mobile No.: _________________________Village: _______________________________Tehsil: __________________________ District: ____________State: _________EDFC 101/102/103:_________Chainage:_______________Parallel/Detour: __________ GPS Tagging: Location of affected land: ____________________________________________________________________ Residential location of PAP: __________________________________________________________________ 1. Compensation and R&R Assistance Received i If any compensation amount is pending to receive? 1 YES 2 NO ii If yes, for which item compensation amount is pending? 1 LAND 2 STRUCTURE iii If any R&R Assistance is pending to receive? 1 YES 2 NO If you ever faced any difficulty in receiving the compensation amount iv 1 YES 2 NO / R&R assistance? v If Yes, please state the type of difficulties faced Whether you are satisfied with the Compensation Rate/Amount vi 1 YES 2 NO received? vii If any special assistance provided to differently abled people? 1 YES 2 NO 3 NA viii If sufficient time (3 months) given for relocation 1 YES 2 NO 2. Utilization of Compensation Amount Where have you utilized/invested the maximum amount of i compensation received? Whether you have purchased land/asset from compensation ii 1 YES 2 NO amount? If Yes, have you claimed reimbursement of stamp duty within iii 1 YES 2 NO timeframe? vi If yes, how much amount claimed (Rs.) vii If No, please state the reason If Reimbursement of stamp duty and registration fee rejected, state viii the reason CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST Page | 5 Final Report End-Term RAP Impact Evaluation of Land Acquisition and R&R Implementation for EDFC-1 (Khurja – Bhaupur Section) 3. Income Generation Activities i Have you received any training? 1 YES 2 NO ii If yes, please state the type of training and provided by whom? iii Did you get any job after the training 1 YES 2 NO iv If yes, please state the type of job v If any employment provided by the Contractor 1 YES 2 NO vi If yes, please state the type of employment / job vii If No, please state the reason 4. Household / Individual Income i No. of Family members MALE FEMALE CHILDREN TOTAL ii No. of earning members MALE FEMALE TOTAL iii Occupation of family members MALE FEMALE iv Whether there is change in occupation due to project 1 YES 2 NO v If Yes, please state the present occupation vi Individual Monthly Income (Rs.) MALE FEMALE TOTAL vii Total Household Monthly Income (Rs.) viii Total Household Monthly Expenditure (Rs.) 5. Loans/Debts i Have you taken any loan? 1 YES 2 NO If yes, please state the amount (Rs.) and type (Bank/Private Money ii Lender) iii If you have cleared debts after receiving the compensation amount? 1 YES 2 NO iv If yes, please state the amount (Rs.) is pending for repayment 6. Household Facilities i If any change in the total area of household 1 YES 2 NO ii If yes, please mention the change in total area of household 1 AREA INCREASED 2 AREA DECREASED iii Is the household having separate Kitchen Room 1 YES 2 NO iv Is the household having separate Toilet 1 YES 2 NO v Is the household having separate Bathroom 1 YES 2 NO vi Type of construction KUCCHA PUKKA SEMI-PUKKA RCC STRUCTURE CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST Page | 6 Final Report End-Term RAP Impact Evaluation of Land Acquisition and R&R Implementation for EDFC-1 (Khurja – Bhaupur Section) 7. Grievance Redress i Have you ever submitted any grievance to GRC? 1 YES 2 NO ii If yes, please state the type of grievance iii Whether your grievance resolved by GRC? 1 YES 2 NO If Yes, please state that whether you are satisfied with decision of iv 1 YES 2 NO GRC? v If No, please state the reason Have you taken service of any legal practitioners to submit the vi 1 YES 2 NO grievance vii Have you ever submitted any grievance to Court/Arbitrator 1 YES 2 NO If yes, please state whether the Court/Arbitrator decision was viii 1 YES 2 NO positive 8. Satisfaction Level Whether you are satisfied with the Compensation Rate/Amount i 1 YES 2 NO received? Ii If No, please state the reason Whether you are satisfied with the assistance provided by DFCCIL Iii 1 YES 2 NO during relocation? iv If No, please state the reason v Whether you are satisfied with the received R&R assistance? 1 YES 2 NO vi If No, please state the reason Whether you are satisfied with the employment conditions, wages vii 1 YES 2 NO and facilities provided by the Contractor? viii If No, please state the reason 9. Feedback/Opinion on LA and R&R processes Whether the LA and R&R processes benefited in improving living I 1 YES 2 NO conditions Ii If yes, please provide details how? Iii If No, please state the reason Whether Compensation amount received was adequate enough to Iv 1 YES 2 NO replace affected / lost asset? v If No, please state the reason CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST Page | 7 Final Report End-Term RAP Impact Evaluation of Land Acquisition and R&R Implementation for EDFC-1 (Khurja – Bhaupur Section) End Term Impact Evaluation Survey Questionnaire [Control Population] Dedicated Freight Corridor Corporation of India Limited Form No. ___________Date___________ [A Government of India (Ministry of Railways) Enterprise] End-Term Impact Evaluation of Land Acquisition and R&R Name of Investigator____________________ Implementation for EDFC-1 (Khurja-Bhaupur Section) Name of Supervisor_____________________ Category (TH/NTH/BPL/SC/ST/Vulnerable): ______________________________________________________________________ ID No. & Name:_______________________Gender (M/F):________ Govt. ID No. (AADHAR/Voter/PAN/etc.):________________ Mobile No.: ______________________Village: ________________________________Tehsil: ______________________________ District: _____________State: ________EDFC 101/102/103:__________Chainage:_______________Parallel/Detour: _________ GPS Tagging: Location of affected land: _____________________________________________________________________ Residential location of PAP: __________________________________________________________________ 1. Income & Occupation i No. of Family members MALE FEMALE CHILDREN TOTAL ii No. of earning members MALE FEMALE TOTAL iii Occupation of family members MALE FEMALE iv Whether there is change in occupation due to project 1 YES 2 NO v If Yes, please sate the present occupation vi Individual Monthly Income (Rs.) MALE FEMALE TOTAL vii Total Household Monthly Income (Rs.) 2. Loans/Debts i If any loan/debt amount (Rs.) is pending for repayment 1 YES 2 NO If yes, please state the amount (Rs.) and type (Bank/Private Money ii Lender) 3. Household Facilities i If the household having separate Kitchen Room 1 YES 2 NO ii If the household having separate Bath Room 1 YES 2 NO iii If the household having separate Toilet 1 YES 2 NO 4. Feedback/Opinion on change of living condition i Whether you have benefited by the project in any form? Whether you have purchased any land/asset (shop, etc.) in the last ii 1 YES 2 NO 10 years? Please provide your opinion on change of living condition in the last iii 10 years CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST Page | 8 Final Report End-Term RAP Impact Evaluation of Land Acquisition and R&R Implementation for EDFC-1 (Khurja – Bhaupur Section) Annexure IV Group-wise Discussion points of FGDs 1. Physically displaced people Group Satisfaction level and feedback of PAPs Pre & Post Displacement. Alternative living arrangements during displacement process. Status of Higher Order Assets and comparison with control population on recall basis Verification of Resettlement site Other benefits provided by the DFCCIL. Any comments/Suggestions/recommendation for future planning 2. PAPs received compensation and R&R assistance Satisfaction level of PAPs regarding Land & Assets rates decided by authority. Satisfaction level of PAPs received Compensation and R&R Assistance. Status of Support provided to all PAPs. Views regarding entitlement Category as per Entitlement matrix. Status of Grievance case filed, if any. Any comments/Suggestions/recommendation for future planning 3. PAPs involved in direct land purchase process Satisfaction level of PAPs involved in direct land purchase process. Satisfaction level of PAPs regarding relocation of new resettlement site. Details of support provided to PAPs relocated to new resettlement site. Details of Support provided to all PAPs. Any comments/Suggestions/recommendation for future planning 4. PAPs refused to accept the compensation and R&R assistance Reasons for refusing to take the compensation and R&R assistance. Any Arbitration/Court case filed Status of Case/decision. Satisfaction level regarding decision. Any comments/Suggestions/recommendation for future planning 5. PAPs filed grievance cases Status of grievance case filed Status of resolved cases. Satisfaction level regarding decision. Duration of resolving cases. Any comments/Suggestions/recommendation for future planning CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST Page | 9 Final Report End-Term RAP Impact Evaluation of Land Acquisition and R&R Implementation for EDFC-1 (Khurja – Bhaupur Section) 6. Community representatives for Common Property Resources (CPRs) Types of CPR impacted Issues raised by the community Relocation/Reconstruction status of CPRs. Quality of construction of CPRs Satisfaction level of Community. Any comments/Suggestions/recommendation for future planning. 7. PAPs belongs to vulnerable groups (SC, ST, BPL, WHH and Differently abled) Satisfaction level regarding disbursement process of LA and R&R. Difficulty faced during process. Additional benefits/support provided by the DFCCIL. Any comments/Suggestions/recommendation for future planning. 8. Title holder (TH) PAPs and Non-title holder (NTH) PAPs Benefits/support provided to TH and NTH as per Entitlement Matrix. Satisfaction level of TH and NTH PAPs regarding compensation and R&R Assistance. Any comments/Suggestions/recommendation for future planning. 9. PAPs employed by the contractor Details of Employment provided by contractor. Type of Employment provided by the contractor. Satisfaction level of PAPs after employment. Status of income after employment. Training provided by the DFCCIL. Any comments/Suggestions/recommendation for future planning. 10. FGD with women groups Difficulties faced during implementation period. Status of employment before and during project implementation. Type of occupation Training provided by the DFCCIL. Status of income before and after project implementation. Any comments/Suggestions/recommendation for future planning. 11. FGDs with DFCCIL Land Handing over details from DFCCIL and Contractor Alternative living arrangements during displacement process. Other benefits provided by the DFCCIL. Budget allocated for LA and R&R Details of assistance provided to PAPs relocated to new resettlement site. Status of Arbitration/Court case filed and resolved CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST Page | 10 Final Report End-Term RAP Impact Evaluation of Land Acquisition and R&R Implementation for EDFC-1 (Khurja – Bhaupur Section) Status of grievance case filed and resolved Relocation/Reconstruction status of CPRs (Pre & Post Implementation). Benefits/support provided to TH and NTH as per Entitlement Matrix. No. of Women PAPs Training provided by the DFCCIL. Details of Employment provided by contractor. Type of Employment provided by the contractor Status of income after employment. Status of Women employment before and during project implementation. Status of Women income before and after project implementation. CSR activities adopted by the Contractor/DFCCIL. 12. FGDs with PMC Land Handing over details Alternative living arrangements during displacement process. Other benefits provided by the DFCCIL. Details of assistance provided to PAPs relocated to new resettlement site. Status of Arbitration/Court case filed and resolved Status of grievance case filed and resolved Relocation/Reconstruction status of CPRs (Pre & Post Implementation). Benefits/support provided to TH and NTH as per Entitlement Matrix. No. of Women PAPs Training provided by the DFCCIL. Details of Employment provided by contractor. Type of Employment provided by the contractor Status of Women employment before and during project implementation. Status of Women income before and after project implementation. CSR activities adopted by the Contractor/DFCCIL. 13. FGDs with Contractor Land Handing over details Civil work Schedule of contractor Comparison between Land Handing over and Civil work Schedule of contractor Alternative living arrangements during displacement process. Other benefits provided by the DFCCIL. Details of assistance provided to PAPs relocated to new resettlement site. Relocation/Reconstruction status of CPRs (Pre & Post Implementation). Status of Employment provided by contractor. Type of Employment provided by the contractor Status of Women employment before and during project implementation. Status of Women income before and after project implementation. CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST Page | 11 Final Report End-Term RAP Impact Evaluation of Land Acquisition and R&R Implementation for EDFC-1 (Khurja – Bhaupur Section) CSR activities adopted by the Contractor. Whether contract awarded without paying complete land compensation 14. FGDs with NGO Alternative living arrangements during displacement process. Other benefits provided by the DFCCIL. Details of assistance provided to PAPs relocated to new resettlement site. Status of Arbitration/Court case filed and resolved Status of grievance case filed and resolved Relocation/Reconstruction status of CPRs (Pre & Post Implementation). Benefits/support provided to TH and NTH as per Entitlement Matrix. No. of Women PAPs Training provided by the DFCCIL. CSR activities adopted by the Contractor/DFCCIL. 15. FGDs with Control Population in maximum impacted villages including Detour Section Occupation Status Income Status Living Condition Status of Landholding and Higher order Assets Overall Perception of Control Population Status of Loan/Debts Status of Household Facilities Feedback/Opinion on change of living condition 16. Discussion with complainants of Lot-101 Status of payment of compensation Status of Arbitration and Court Cases filed/Disposed Satisfaction of PAPs from Court Decisions CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST Page | 12 Final Report End-Term RAP Impact Evaluation of Land Acquisition and R&R Implementation for EDFC-1 (Khurja – Bhaupur Section) Annexure-V Photographs of Focus Group Discussion 1. Differently Abled People Sukhanpur village, Auraiya District Barhan village, Agra District Kirthra Mohmadpur village, Firozabad District CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST Page | 13 Final Report End-Term RAP Impact Evaluation of Land Acquisition and R&R Implementation for EDFC-1 (Khurja – Bhaupur Section) 2. PAPs received Compensation and R&R Assistance Doruchandpur and Keshopur villages, Aligarh District Datoji village, Firozabad District Dokeli village, Firozabad District Behta village, Kanpur Dehat District 3. PAPs whose Land acquired as per UP Direct Land Purchase Policy, 2015 Shahpur Derapur village, District Kanpur Dehat CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST Page | 14 Final Report End-Term RAP Impact Evaluation of Land Acquisition and R&R Implementation for EDFC-1 (Khurja – Bhaupur Section) 4. PAPs filed Grievance Cases Datoji village, Firozabad district Latifpur village, Firozabad district Dokeli village, Firozabad District Barhan village, Agra District 5. Vulnerable Groups (SC, ST, BPL, WHH and Differently Abled) Phaphood village, Auraiya District Purwasa village, Auraiya District Datoji village, Firozabad District Bankat village, Firozabad District CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST Page | 15 Final Report End-Term RAP Impact Evaluation of Land Acquisition and R&R Implementation for EDFC-1 (Khurja – Bhaupur Section) Dokeli village, Firozabad Surehara Mustkil village, Etmadpur, Agra 6. Titleholders (THs- Formal settlers) and non-titleholders (NTHs-informal settlers) Doruchandpur village, Aligarh District (FGD with NTHs) Khera Khushkhabar village, Aligarh District Kirthra Mohmadpur village, Firozabad District CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST Page | 16 Final Report End-Term RAP Impact Evaluation of Land Acquisition and R&R Implementation for EDFC-1 (Khurja – Bhaupur Section) 7. Civil Work Contractor Contractor’s office at Etawah District Contractor’s office at Gari Bhakti village, Agra District 8. PAPs Employed by the Contractor Hayatpur Bajheda village, Aligarh District Dariyapurva village, Hathras District - PAPs provided training by ITI CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST Page | 17 Final Report End-Term RAP Impact Evaluation of Land Acquisition and R&R Implementation for EDFC-1 (Khurja – Bhaupur Section) Mandrak village, Aligarh District Alampur Jhapta village, Firozabad District Medhidudhi village, Etawah District 9. Community Representatives for Common Property Resources and Religious Structures Kheriya village, Hathras District CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST Page | 18 Final Report End-Term RAP Impact Evaluation of Land Acquisition and R&R Implementation for EDFC-1 (Khurja – Bhaupur Section) Temple in Kheriya village, Hathras (to be Old well in Kheriya village, compensation demolished- compensation provided to the provided to the owner owner of the temple) Temple constructed after relocation of the existing temple in Daruchandpur village, Aligarh Nagla Goal village, Agra District Latifpur village, Firozabad District CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST Page | 19 Final Report End-Term RAP Impact Evaluation of Land Acquisition and R&R Implementation for EDFC-1 (Khurja – Bhaupur Section) Graveyard, Raipalpur, Kanpur Dehat District 10. Control Population Hajipur Chauhatta village, Aligarh District Dokeli village, Firozabad District Datoji village, Firozabad District CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST Page | 20 Final Report End-Term RAP Impact Evaluation of Land Acquisition and R&R Implementation for EDFC-1 (Khurja – Bhaupur Section) 11. PAPs who filed Complaints to World Bank Complainants in Debiyapur village, Auraiya District Complainants in Itgaon village, Etawah District CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST Page | 21 Final Report End-Term RAP Impact Evaluation of Land Acquisition and R&R Implementation for EDFC-1 (Khurja – Bhaupur Section) Annexure VI Assessment of timeline based on village level case studies Time to be Time Taken - 20A to 20 E Time Taken - 20E to 20 F taken notification notification S.No. Sample Cases Percentage No. of Percentage No. of Days No. of Days (%) Days (%) 1 Village 1 365 320 88 335 92 2 Village 2 365 328 90 291 80 3 Village 3 365 111 30 193 53 4 Village 4 365 277 76 323 88 5 Village 5 365 216 59 74 20 6 Village 6 365 201 55 348 95 7 Village 7 365 226 62 128 35 8 Village 8 365 314 86 310 85 9 Village 9 365 200 55 47 13 10 Village 10 365 332 91 266 73 11 Village 11 365 360 99 238 65 12 Village 12 365 360 99 238 65 13 Village 13 365 360 99 238 65 14 Village 14 365 360 99 238 65 Average Time taken 365 days 283 days 233 days Source: DFCCIL, 2019 CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST Page | 22 Final Report End-Term RAP Impact Evaluation of Land Acquisition and R&R Implementation for EDFC-1 (Khurja – Bhaupur Section) Annexure-VII Land Provided to NTH for Relocation Land provided to NTH for relocation and PAPs constructed structures from the R&R assistance provided to them in Village Dourauchanpur CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST Page | 23 Final Report End-Term RAP Impact Evaluation of Land Acquisition and R&R Implementation for EDFC-1 (Khurja – Bhaupur Section) Annexure-VIII (A) Excerpts of Camps organized for PAPs DFCCIL published on 02-05-19 regarding Camp was organized on 10-05-19 by DFCCIL in compensation in newspaper Amar Ujala Village Navalpur,District -Agra regarding R&R Assistance Camp organized on 13-04-19 by DFCCIL in Village Camp organized on 09-05-19 by DFCCIL in Village Nizampur, District- Firozabad regarding R&R Rasulpur,District- Agra regarding R&R assistance assistance and Relocation. CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST Page | 24 Final Report End-Term RAP Impact Evaluation of Land Acquisition and R&R Implementation for EDFC-1 (Khurja – Bhaupur Section) Annexure-VIII (B) Satisfaction level of PAPs with respect to Awareness Camps Majority of the PAPs (60%) were aware about the act/policy as per which there land was acquired. Out of the sampled PAPs, 74% intimated to have received the compensation amount. The PAPs who received compensation as per the Old Act were not satisfied with the land rates as compare to the PAPs whose land was acquired as per New Act. The disbursement of compensation to the PAPs was done through cheques as mentioned in the RAPs. For disbursement of compensation, where NGO was available, 36 camps were organized in 34 villages by the DFCCIL officials in the districts of Firozabad and Agra. A total 307 PAPs attended camps. After holding camps, 1757 applications were received for R&R assistance requisition, out of which 1238 applications were processed for payment and 519 applications were not eligible. As per the status received from DFCCIL HQ, out of the eligible PAPs, assistance was disbursed to 746 PAPs and payment to the remaining PAPs is under process. CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST Page | 25 Final Report End-Term RAP Impact Evaluation of Land Acquisition and R&R Implementation for EDFC-1 (Khurja – Bhaupur Section) CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST Page | 26 Final Report End-Term RAP Impact Evaluation of Land Acquisition and R&R Implementation for EDFC-1 (Khurja – Bhaupur Section) Annexure- IX Training provided to the PAPs Another identified institute which imparted training was the Technical Services Centre of the National Small Industries Corporation Ltd., and situated in Industrial Estate, Aligarh, UP. Training was provided on electrical home appliances, electrician, and entrepreneurship-orientation. The duration of the training was one month (from 02.12.2013 to 02.01.2014). The trainees informed that the DFCCIL had sponsored their training on free-of-cost basis. However, none of the trainees received any job as promised by DFCCIL prior to the training. Total 60 such trainees had protested in front of the Office of DFCCIL at New Delhi but their grievances remained unresolved. The PAPs demanded for jobs after training. Excerpts from the newspaper are presented below regarding demand of employment: Excerpts of Newspaper regarding provision of employment CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST Page | 27 Final Report End-Term RAP Impact Evaluation of Land Acquisition and R&R Implementation for EDFC-1 (Khurja – Bhaupur Section) Source: www.mospi.nic.in CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST Page | 28 Final Report End-Term RAP Impact Evaluation of Land Acquisition and R&R Implementation for EDFC-1 (Khurja – Bhaupur Section) Annexure-X Land Related Hindrances or Stoppage of Civil Works by Community People Land Related Hindrances Sl. No. Contractor’s Communication Categorization 1. Not able to carry out the collection of data with respect to Geotechnical RoW investigation and topographical survey due to resistance of locals/RoW pillars not fixed in various locations like Tundla detour, Firozabad detour, etc. (communication dated 01.07.2013) 2. Due to non-payment issues to the villagers, tree-cutting activity was Compensation interrupted in Firozabad district (communication dated 20.09.2013) 3. Near IR Ch.Km 1235/16-17, villagers demanded provision of RUB underpass/bridge to cross DFCC line and showed violent protest on the said issued and stopped the work (communicated dated 20.06.2014) 4. Land owners intervened and stopped the work at Ch.Km 10+300 to 10+500 Compensation in Tundla Detour due to the issue of compensation for land acquisition with DFCCIL (communication dated 26.06.2014) 5. Stoppage of work by land owners while doing Minor Bridge No.69 at IR Compensation Ch.Km 1194/5-7 and requested to resolve the land issue at the earliest (communication dated 07.08.2014) 6. Villagers continued to stop the work due to issues related to compensation Compensation for land with DFCCIL in Ch.Km 8+500 to 8+750 in Firozabad detour (communication dated 27.08.2014) 7. Work was stopped by the villagers, at Ch.Km 1185+760 to 1186+700, until Compensation the payment/compensation was made to them (communication dated 01.09.2014) 8. Villagers had stopped the work at Ch.Km 6+600 to 6+800 as the villagers RUB were demanding RUB at Ch.6+630 instead of already proposed location at Ch.6+833 (communication dated 12.09.2014) 9. Stoppage of work by villagers at IR Ch.Km 1197 to 1198+500, as the villagers Job offers had been promised by DFCCIL to provide jobs in the Railways/DFCCIL at the time of land acquisition. Villagers were demanding to provide jobs as promised until then they would not allow to start the work (communication dated 23.09.2014) CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST Page | 29 Final Report End-Term RAP Impact Evaluation of Land Acquisition and R&R Implementation for EDFC-1 (Khurja – Bhaupur Section) Land Related Hindrances Sl. No. Contractor’s Communication Categorization 10. Work at IR Ch.1184 to 1185+700 in Yadavpur village, Etawah, had been Compensation stopped by the villagers on account of payment of compensation at a revised rate (communication dated 26.09.2014) 11. Incurred problems relating to land acquisition for Gata no.356 at IR Ch.Km Compensation 1197. Villagers had stopped the work for reasons like less compensation against land acquisition (communication dated 18.12.2014) 12. Villagers had stopped the excavation activity of RUB RC-2 at Ch.Km RUB 3+355.800 demanding to increase the size of RUB (communication dated 24.02.2015) 13. Villagers had stopped the work of minor structures RUB 5A at Ch.Km 6+630 RUB for their demand to increase the size of RUB (communication dated 13.03.2015) 14. Affected land owners had stopped the work at Ch. Km 3+540 in Kuberpur Compensation due to the issue of compensation for land or fixing of RoW (communication dated 04.06.2015) 15. Work was stopped by the villagers of nearby village Basath of Minor Stagnant water Structure due to the construction of the bridge will cause stagnation of water in their farm (communication dated 02.07.2015) 16. Local villagers had stopped the ongoing work in Firozabad Detour for their RUB demand of RUB (communication dated 07.08.2015) 17. Land owner was not allowing to do the work on the pretext of wrongly Wrong acquisition acquired land from Ch.Km 6+680 to 8+180 at Bhikanpur Village (communication dated 11.08.2015) 18. Villagers had stopped the work of Minor structure – TD RUB-5 for their RUB demand to increase the size of RUB (communication dated 22.08.2015) 19. Stoppage of work at TD RC-2 by nearby villagers for their demand to RUB increase size of RUB (communication dated 22.08.2015) 20. Land owners where not allowing to proceed with the work in between Compensation Ch.Km 6+900 to 7+300 (communication dated 30.11.2015) 21. Could not do the work at Ch.Km 1239+585 to 1239+598 due to the fencing Compensation done by the land owner as he had not been paid compensation for the acquired land (communication dated 12.01.2016) CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST Page | 30 Final Report End-Term RAP Impact Evaluation of Land Acquisition and R&R Implementation for EDFC-1 (Khurja – Bhaupur Section) Land Related Hindrances Sl. No. Contractor’s Communication Categorization 22. Villagers on 05.02.2016 sat on ‘Dharna Pradarshan’ on prepared formation Access Road bed in DFC RoW at Ch.Km 1211+890 at Shikohabad Station area and stopped the work of ballast laying for whole day by stopping all machinery and vehicle movement for their demand of road (communication dated 06.02.2016) 23. Villagers on 16.02.2016 sat on ‘Dharna Pradarshan’ on prepared formation Access Road bed in DFC RoW at Ch.Km 1213/11 at Shikohabad Station area and stopped the formation work at pond area for whole day by stopping all machinery and vehicle movement for their demand of road (communication dated 17.02.2016) 24. Violent protestors had interrupted IR train operation as the protestors sat Access Road on IR track near 1213/11 for their demand of underpass and road (communication dated 22.02.2016) 25. An incident of ‘Dharna Pradarshan’ on 08.03.2016 in Firozabad Detour Compensation (communication dated 09.03.2016) 26. Villagers had stopped the work at Ch.Km 4+100 (Firozabad Detour), at RUB Ch.Km 0+388.858 (Tundla Detour) at Ch.Km6+058+042, due to their demand of increase in size of structures (communication dated 14.06.2016 and 15.06.2016) 27. Stoppage of work by farmers since 23.07.2016 for unsettled compensation compensation payment for their acquired land in Etawah District (IR Ch.Km 1186-1170). Villagers had also stopped vehicles transporting blanket material and even not allowing to unload the blanketing material (communication dated 27.07.2016) 28. Farmers attacked the sub-contractor while doing installation of Borewell at Compensation Ch.Km 1177+090 (communication dated 09.08.2016) 29. Works being stopped due to commotion created by farmers protesting Compensation construction of Retaining Wall at Barhan Detour and formation work at Kuberpur Link (communication dated 21.06.2017) 30. While evicting hindrances in Barhan Detour from Ch.3200 to Ch.3300, Compensation constrained to stop eviction due to non-realization of compensation payment to land losers – limiting the eviction to 50% (communication dated 03.08.2017) CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST Page | 31 Final Report End-Term RAP Impact Evaluation of Land Acquisition and R&R Implementation for EDFC-1 (Khurja – Bhaupur Section) Land Related Hindrances Sl. No. Contractor’s Communication Categorization 31. Ongoing works had been stopped in Kuberpur (Ch.Km 4100-4520) due to Compensation protest by land losers on account of compensation payment (communication dated 19.08.2017) 32. Land loser of Gata No. 123 were forbidding the JV to take the works at Compensation Ch.Km 11+123, as requisite compensation was yet to be disbursed which further drastically hampered backfilling works and formation works (communication dated 25.09.2017) 33. Requisite compensation was yet to be disbursed to the land losers, which Compensation prohibited the works in Ch.Km 5+500 to Ch.Km 5+600 (Kuberpur) (Communication dated 07.10.2017) 34. ‘No-objection’ from the landlord had been obtained for the execution of RoW difference works at ROW from Ch.Km 4+800 to Ch.Km 5+040, however the RoW differed from the initial proposed RoW as it had been shifted 6m away towards RHS and corresponding RoW pillars had also been shifted (communication dated 28.10.2017) 35. Villagers of Nagla Chenkur had stopped the works of TD RUB-4A and New RUB Tundla yard at Ch.Km 4+590 (Tundla Detour) (communication dated 28.12.2017) 36. At Kuberpur link, alignment was changed from Ch.2+900 to Ch.3+600 due to Alignment change land acquisition issue (communication dated 27.10.2017) Source: Contractor’s Documents Accessed during the Survey CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST Page | 32 Final Report End-Term RAP Impact Evaluation of Land Acquisition and R&R Implementation for EDFC-1 (Khurja – Bhaupur Section) Annexure-XI Onsite Observations of Common Property Resource Discussions with the DFCCIL officials revealed that all the affected CPRs were relocated, except one Temple in Kamalpur village, Kanpur Dehat district (LC-98). This Temple was built in private land by the land owners. The temple was located in the Aabadi land and the owners of the temple have now been declared as titleholders. DFCCIL is in process to take consent from respective land owners and proceeded for acquisition of the same under Direct Land Purchase Policy. Discussion with the land owners revealed that relocation of the Temple will be decided once they receive compensation from DFCCIL. Construction of a new graveyard in place of an affected graveyard (Gata no. 375) which was categorised as uncharted was being carried out by DFCCIL with active participation of community people. The new as well as the affected graveyard were located in Raipalpur village in Kanpur Dehat district. Compensation for affected graves was provided to five (5) PAPs, totaling to amount Rs.1,63,500 (Rs.32,700 each). The aggregate contract for relocation of the affected graveyard amounts to Rs. 5,48,677. DFCCIL had taken up the relocation work with the local community and construction works were progressing during the end- term impact evaluation survey. The affected graveyard was located in an area of 0.15 ha. of State Government land. Alternatively, new piece of land was sanctioned by the District Administration and the cost of land (i.e. Rs.26.28 lakh) was transferred to District Administration by DFCCIL. Location 1: Agra (village- Nagla Goal) The types of CPR impacted Temple includes Durga Mata Mandir, Shiv Mandir, Hanuman Mandir, Kitchen Room /Rosoi (1 No.), Bathroom (1 No.), Rooms (4 Nos.) with verandah, stair case for the access to the roof of the structure, bore well with submersible pump, landscaping with shrubs & flowering plants within the temple premises, fixing of celling fans (12 Nos.), fixing of brass metal temple bells (3 Nos.). Mr. Gajendra Singh, S/o Narotam Singh has donated approximately 1 Bigha of land for the construction of impacted Temple. The Contractor has not completed the works as per the scope (i.e. the items that was available in the impacted structures). In the year 2015 the land owner along with other villagers has also requested the Contractor M/s TATA-ALDESA "JV" in written to complete all the activities as per the scope. But the works are not yet taken up / completed by the Contractor. Door fitting for Kitchen and Bathroom yet to be done, fixing of ceiling fans and brass metal Temple bells yet to be fixed, Stair case for the access to the roof of the structure partially completed i.e. hand rails not yet fitted. CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST Page | 33 Final Report End-Term RAP Impact Evaluation of Land Acquisition and R&R Implementation for EDFC-1 (Khurja – Bhaupur Section) Old temple was demolished and constructed in village Nagla Goal ,District Agra Old rooms before the relocation in Village Nagla Goal, District Agra and the new construction of rooms with verandah within temple completed CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST Page | 34 Final Report End-Term RAP Impact Evaluation of Land Acquisition and R&R Implementation for EDFC-1 (Khurja – Bhaupur Section) Newly constructed staircase and bathroom are to be fitted with doors and handrails in staircase in the temple in village Nagla Goal, District Agra Location 2: Agra (Village - Latifpur) The types of CPR impacted includes Toilet (2 Nos.), Urinal (2 Nos.), Hand Pump (1 No.). The community is satisfied with the construction of Toilet (2 Nos.), Urinal (2 Nos.) and Bore well with submersible pump provided in lieu of hand pump by the Contractor. New construction of Toilet, Urinal and Water pump in the Village- Latifpur ,District -Agra Location 3: Auraiya (Raipalpur village) The type of CPR impacted is Graveyard Old CPR is in Raipalpur village, Auraiya and new one is also constructed in the same village There were 5 graves and compensation for graveyard is given to the respective families Total compensation given to the 5 PAPs are Rs. 163500 (Rs. 32,700 each) CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST Page | 35 Final Report End-Term RAP Impact Evaluation of Land Acquisition and R&R Implementation for EDFC-1 (Khurja – Bhaupur Section) The contract of relocation and reconstruction of the graveyard was given to local community people. They are provided with Rs. 54,8677 for the construction work. The construction work is under progress The graveyard is in Government land which is 0.1460 ha. The required land was suggested by the community to which District Administration agreed. Alternate land for relocation of Graveyard was arranged by the District Administration. DFCCIL had given the required cost of land to the District Administration. Physical possession of Graveyard at village - Raipalpur, Tehsil-Derapur, District-Kanpur Dehat and the new construction ongoing Location 4: Etawah (Village- Medhidudhi) The type of CPR impacted is Temple (Durga Mandir) No issues raised by the community; they are satisfied with the quality of construction. Temple is in private ownership of three shareholders. The affected temple in the Village Medhidudhi, District Etawah and the new structure being constructed CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST Page | 36 Final Report End-Term RAP Impact Evaluation of Land Acquisition and R&R Implementation for EDFC-1 (Khurja – Bhaupur Section) Location 5: Hathras (Village – Kheriya) The type of CPR impacted are: (1) Temple including dharamshala, (2) Well, (3) Graveyard, and (4) Crematorium Temple resettlement cost were received but the temple’s land compensation is pending Due to pending of land compensation amount, community could not construct the structure Compensation for well of Rs 1, 14,000 has been received but new one yet to be constructed. The old Temple with Dharamshala in Village- Kheriya, District- Hathras yet to be constructed Well in Kheria village, District- Hathras Impacted Graveyard and Cerematerium CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST Page | 37 Final Report End-Term RAP Impact Evaluation of Land Acquisition and R&R Implementation for EDFC-1 (Khurja – Bhaupur Section) Further two more temples were affected of which one temple was constructed by the contractor and for the other one, compensation amount was provided to the owner of the temple. Temple constructed in Kheriya by DFCCIL after relocation Temple constructed in Kheriya by the owner of the old temple affected in the alignment Location 6: Aligarh (Village- Daruchandpur ) The temple used by the community people was affected by the DFCCIL alignment. The village is located parallel to the track. The temple is categorized as uncharted and has been constructed by the Contractor adjacent to the track near the village. The newly constructed temple is similar to the affected temple. Temple constructed after relocation of the old temple affected in the alignment in Daruchandpur village, Aligarh CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST Page | 38 Final Report End-Term RAP Impact Evaluation of Land Acquisition and R&R Implementation for EDFC-1 (Khurja – Bhaupur Section) Annexure-XII CSR activities of DFCCIL As part of the CSR activities of DFCCIL, office of the CPM, Tundla had provided cash-assistance to the District Administration of Firozabad and Agra respectively. An amount of Rs.700,000 (dated 03.01.2019) and Rs. 800,000 (dated 02.04.2019) was transferred to the District Administration towards construction of Public Toilets. However, DFCCIL does not have any information regarding the utilisation of the transferred money to District Administration, although office of the CPM, Tundla while transferring the amount, had requested the District Administration to provide update on the construction of Public Toilets. In addition to this, the Contractor under CSR activity has organized blood donation and eye check-up camps and tree plantation and landscaping in SP Office. School Library in Douru Chandpur Village in Aligarh: Contractor has supported the School namely Saraswati Sishu Mandir functioning under the management of Rashtriya Swayamsevak Sangh (RSS), by constructing a building for library and also provided books. The library is great help to the teachers and students and they expressed their gratitude towards DFCCIL and Contractor. However, access to the School is disrupted due to water-clogging alongside the school which is due to track construction works. In this respect, the villagers and school authorities expressed their concern. School Library constructed by DFCCIL CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST Page | 39 Final Report End-Term RAP Impact Evaluation of Land Acquisition and R&R Implementation for EDFC-1 (Khurja – Bhaupur Section) Letter to CPM Units intimating the appointment of CII for conducting CSR activities in the four locations CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST Page | 40 Final Report End-Term RAP Impact Evaluation of Land Acquisition and R&R Implementation for EDFC-1 (Khurja – Bhaupur Section) CSR Activities proposed for the year 2017-2018 CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST Page | 41 Final Report End-Term RAP Impact Evaluation of Land Acquisition and R&R Implementation for EDFC-1 (Khurja – Bhaupur Section) CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST Page | 42 Final Report End-Term RAP Impact Evaluation of Land Acquisition and R&R Implementation for EDFC-1 (Khurja – Bhaupur Section) CSR Activities proposed for the year 2018-2019 CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST Page | 43 Final Report End-Term RAP Impact Evaluation of Land Acquisition and R&R Implementation for EDFC-1 (Khurja – Bhaupur Section) CSR Activities proposed for the year 2019-2020 CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST Page | 44 Final Report End-Term RAP Impact Evaluation of Land Acquisition and R&R Implementation for EDFC-1 (Khurja – Bhaupur Section) CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST Page | 45 Final Report End-Term RAP Impact Evaluation of Land Acquisition and R&R Implementation for EDFC-1 (Khurja – Bhaupur Section) CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST Page | 46 Final Report End-Term RAP Impact Evaluation of Land Acquisition and R&R Implementation for EDFC-1 (Khurja – Bhaupur Section) Annexure- XIII Procedure of handling Grievances by DFCCIL A Grievance Register is maintained in DFCCIL office, Agra wherein the date of receipt of the complaint, issue addressed and method of communication, etc., are systematically documented. However, information about the unresolved cases forwarded for resolution by GRC was not available. In discussion with DFCCIL officials, Aligarh, it was intimated that grievances were received at various levels of requisite Government Administrators like GM/LA, SLAO, CPM, ADM/LA, DFCCIL Head Quarter and directly from office of Railway Board. After which it is forwarded to the site office for understanding the matter. For example, in case of land related grievances received by SLAO and ADM/LA are forwarded to DFCCIL site offices, which after understanding the matter are further sent to the concerned SDM/ concerned Tehsil. A report is prepared by Tehsil on the matter to resolve the issue. PAP is intimated about the decision made by Tehsil in the report. Those grievances which were not redressed, as revealed during the discussion with the PAPs include, payment-returned due to PAP’s demise and consequent claim by PAP’s Widow, valuation of additionally affected portion of residence, movement of train causing cracks in the residential property, etc. These grievances were neither taken to the GRC for resolution nor is it resolved at the field level. A systematic procedure is followed in filing the grievance cases in DFCCIL and in resolving them. People either report their issues to the DFC site office or directly to the DFC headquarter. At the same time, PAPs felt more consistency with respect to the complaints forwarded directly to the World Bank. CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST Page | 47 Final Report End-Term RAP Impact Evaluation of Land Acquisition and R&R Implementation for EDFC-1 (Khurja – Bhaupur Section) Annexure- XIV Study on Local Employment Generation A detailed study on local employment generation was conducted. The summary of the study could be seen below: The ‘labour-sub contractors’ who are often the contact-point of the civil work Contractor, function as the local level entrepreneurs who happen to associate with the project for supply of construction-materials other than labour. Good quality stones were transported from Alwar in Rajasthan (about 200 km by road) to Aligarh and other project locations by these local-level entrepreneurs. Discussions with these entrepreneurs reveal that they earned Rs.700 per wagon/truck load and transport 40-60 wagon/truck of stone per day. On an average, Rs.35000 per day is the overall turnover of entrepreneurs and approximately 10 such local entrepreneurs, which adds a total turnover to Rs.520 million in a year. Out of the total surveyed PAPs, 34 PAPs (3%) intimated that they were provided employment by the contractor. The types of employment provided to these 34 PAPs include labourers, Supervisors, security guard, track man, turfing work, welder, master mason and night watchmen. The majority of the PAPs were satisfied with the employment conditions, wages and facilities provided by the contractor. The reasons for dissatisfaction of the remaining PAPs were less wages, delay in payment and job was not appropriate in comparison to the educational qualification. 26% 74% Satisfied Not satisfied 91. Satisfaction level of PAPs with employment provided by contractor CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST Page | 48 Final Report End-Term RAP Impact Evaluation of Land Acquisition and R&R Implementation for EDFC-1 (Khurja – Bhaupur Section) Annexure XV Outcomes of the Data Analysis on various indicators of RAP Implementation 1. Number of PAPs and Control Population Surveyed Number of PAPs Category % Number of Controlled population surveyed % Surveyed Male 1041 86 268 94 Female 175 14 16 6 Total 1216 100 284 100 Source: Primary Survey, 2019 2. Whether you have purchased land/asset from compensation amount? Category Number of PAPs % Yes 200 17 No 1010 83 Total 1210 100 Source: Primary Survey, 2019 Note: Remaining 6 PAPs have not yet received compensation amount 3. Have you claimed reimbursement of stamp duty within timeframe Category Number of PAPs % PAPs purchased land/assets 200 16 (of 1216) PAPs claimed Stamp Duty Reimbursement 47 24 within timeframe PAPs not claimed Stamp Duty Reimbursement 153 96 within timeframe Source: Primary Survey, 2019 4. If sufficient time (3 months) given for relocation Category Number of PAPs % Yes 222 95 No 12 5 Total 234 100 Source: Primary Survey, 2019 5. Whether you are satisfied with the Compensation Rate/Amount received? Category Number of PAPs % Satisfied 480 40 Not Satisfied 730 60 Total 1210 100 Source: Primary Survey, 2019 6. Whether you are satisfied with the received R&R assistance? Category Number of PAPs % Satisfied 583 75 Not Satisfied 192 25 Total 775 Source: Primary Survey, 2019 CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST Page | 49 Final Report End-Term RAP Impact Evaluation of Land Acquisition and R&R Implementation for EDFC-1 (Khurja – Bhaupur Section) 7. Whether you are satisfied with the assistance provided by DFCCIL during relocation? Category Number of PAPs % Satisfied 168 72 Not Satisfied 62 26 Unsure 4 2 Total 234 Source: Primary Survey, 2019 8. Have you received any training? Category Number of PAPs % Received 39 3 Not received 1177 97 Total 1216 Source: Primary Survey, 2019 9. Whether your grievance resolved by GRC? Category Number of PAPs % Grievance cases Resolved 24 8 Grievance cases not resolved 127 42 Grievance cases submitted 151 12 Source: Primary Survey, 2019 10. Satisfaction from Decision of District Administration Category Number of PAPs % Satisfied with the decision of GRC 18 67 Not satisfied with the decision of GRC 9 33 Total 27 100 Source: Primary Survey, 2019 11. Have you taken service of any legal practitioners to submit the grievance Category Number of PAPs % Yes 225 87 No 35 13 Total 260 100 Source: Primary Survey, 2019 12. Please state whether the Court/Arbitrator decision was positive Category Number of PAPs % Cases submitted 260 21 Arbitrator/ court’s decision positive 67 26 Arbitrator/ court’s decision negative 110 42 Cases pending 83 32 Source: Primary Survey, 2019 CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST Page | 50 Final Report End-Term RAP Impact Evaluation of Land Acquisition and R&R Implementation for EDFC-1 (Khurja – Bhaupur Section) 13. Socio-economic profile of women Project Affected Persons Indicators Controlled Population (2019) [PAPs] (2019) Occupation (in %) Housewife 91 69 Agriculture 4 19 Wage-Labour 3 6 Trade 1 6 Service 1 - Average annual income (in Rs.) 31,640 34,480 Indebtedness (No. of cases: in %) 22 31 Housing Condition (% having Pucca structures) 39 - Area increased (in %) 88 - Source: Primary Survey, 2019 14. Awareness about the Act/ Policy Category Number of PAPs % Yes 111 63 No 65 37 Total 176 100 Source: Primary Survey, 2019 15. Have you received compensation amount and R&R assistance Category Number of PAPs % Received 176 100 Not Received 0 0 Total 176 100 Source: Primary Survey, 2019 16. Have you ever submitted any grievance to Court/Arbitrator Category Number of PAPs % Yes 32 18 No 144 82 Total 176 100 Source: Primary Survey, 2019 17. If you ever faced any difficulty in receiving the compensation amount / R&R assistance? Category Number of PAPs % Yes 134 76 No 42 24 Total 176 100 Source: Primary Survey, 2019 18. Whether you are satisfied with the compensation amount and R&R assistance Category Number of PAPs % Satisfied 88 50 Not Satisfied 88 50 Total 176 100 Source: Primary Survey, 2019 CANADA | INDIA | ASIA | AFRICA | MIDDLE EAST Page | 51