JM Foundations for Competitiveness & Growth Country: Jamaica Loan/Credit/TF No.: 8356-JM Project Name: Integrated Community Development Project Project ID: P146460 Name of Implementing Jamaica Social Investment Fund - JSIF Agency: Procurement Plan 1. General 1. Date of General Procurement Notice: N/A 2. Period covered by this procurement plan: The procurement period of project covered from April 2017 to March 2018 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Comments Threshold US$ 1. ICB and LIB (Goods, IT, NCS) Above US$ 1 million All 2. NCB (Goods) Above US$ 100,000 None 3. ICB (Works) Above US$ 7.5 million All 4. NCB (Works) Above US$ 200,000 None 2. Prequalification. N/A. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: N/A. III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comments Threshold 1. Competitive Methods (Firms) Above US$ 2 million 2. Single Source (Firms) Above US$ 1 million 3. Individual Above US$ 400,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than US$500,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. PROCUREMENT Jamaica : Jamaica Integrated Community Development Project PLAN General Information Country: Jamaica Bank’s Approval Date of the Original Procurement Plan: 2018-03-29 2020-12-18 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P146460 GPN Date: Project Name: Jamaica Integrated Community Development Project Loan / Credit No: IBRD / 83560 Jamaica Social Investment Fund Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned AS - 21 / Maxfield Park Construction of IIP packages Basic Infrastructure and Single Stage - One 2018-05- IBRD / 83560 Post Request for Bids Open - National 897,104.00 898,487.93 Completed 2017-07-22 2017-07-25 2017-07-27 2017-09-07 2017-08-31 2017-10-07 2017-09-20 2017-11-11 2018-03-21 for Water, Sanitation, Roads & Access to Services Envelope 10 Drainage AS - 22 / Barrett Town Construction of IIP packages Basic Infrastructure and Single Stage - One 2017-09- IBRD / 83560 Post Request for Bids Open - National 992,187.00 892,374.36 Completed 2016-12-03 2016-12-07 2016-12-08 2017-01-19 2017-01-24 2017-02-18 2017-02-09 2017-03-25 2017-06-16 for Water, Sanitation, Roads & Access to Services Envelope 21 Drainage AS - 23 / Wilton Gardens Construction of IIP packages Basic Infrastructure and Single Stage - One 2018-08- IBRD / 83560 Post Request for Bids Open - National 768,111.00 786,287.27 Completed 2017-08-01 2017-07-27 2017-08-06 2017-09-17 2017-09-05 2017-12-30 2017-10-12 2018-02-17 2018-03-21 for Water, Sanitation, Roads & Access to Services Envelope 16 Drainage AS - 24 / Tivoli Construction Basic Infrastructure and Single Stage - One 1,133,609.9 2018-01- of IIP packages for Water, IBRD / 83560 Post Request for Bids Open - National 865,859.00 Completed 2017-03-28 2017-03-28 2017-04-02 2017-05-14 2017-05-04 2017-06-13 2017-06-12 2017-07-18 2017-11-09 Access to Services Envelope 3 14 Sanitation, Roads & Drainage AS - 26 / Hannah Town Construction of IIP packages Basic Infrastructure and Single Stage - One 2018-02- IBRD / 83560 Post Request for Bids Open - National 768,248.00 808,374.96 Completed 2017-03-28 2017-03-28 2017-04-02 2017-06-11 2017-03-04 2017-07-27 2017-06-12 2017-08-31 2017-11-09 for Water, Sanitation, Roads & Access to Services Envelope 27 Drainage AS - 27 / Greenwich Town Construction of IIP packages Basic Infrastructure and Single Stage - One 1,259,087.9 2018-07- IBRD / 83560 Post Request for Bids Open - National 1,072,968.00 Completed 2017-09-12 2018-01-02 2017-09-17 2017-10-29 2018-02-27 2017-11-28 2018-03-19 2018-01-02 2018-12-14 for Water, Sanitation, Roads & Access to Services Envelope 1 01 Drainage AS - 28 / Rose Town Construction of IIP packages Basic Infrastructure and Single Stage - One 1,376,729.5 2019-03- IBRD / 83560 Post Request for Bids Open - National 1,344,093.00 Completed 2018-05-15 2018-08-23 2018-05-20 2018-07-01 2018-10-31 2018-07-31 2019-05-02 2018-09-04 2019-11-01 for Water, Sanitation, Roads & Access to Services Envelope 3 03 Drainage AS - 29 / Majesty Gardens Construction of IIP packages Basic Infrastructure and Single Stage - One 2018-10- IBRD / 83560 Post Request for Bids Open - National 500,000.00 511,985.35 Completed 2017-11-18 2017-11-21 2017-11-23 2018-02-01 2017-12-19 2018-03-19 2018-01-02 2018-04-23 2018-06-19 for Water, Sanitation, Roads & Access to Services Envelope 20 Drainage AS - 32 / York Town Construction of IIP packages Basic Infrastructure and Single Stage - One 2018-06- IBRD / 83560 Post Request for Bids Open - National 877,001.00 835,851.78 Completed 2017-07-22 2017-07-26 2017-07-27 2017-10-05 2017-08-29 2017-11-20 2017-09-18 2017-12-25 2018-04-14 for Water, Sanitation, Roads & Access to Services Envelope 23 Drainage AS - 33 / Steer Town Construction of IIP packages Basic Infrastructure and Single Stage - One 2018-11- IBRD / 83560 Post Request for Bids Open - National 567,773.00 975,079.57 Completed 2017-11-18 2017-11-10 2017-11-23 2018-01-04 2017-12-20 2018-04-20 2018-02-22 2018-06-01 2018-11-15 for Water, Sanitation, Roads & Access to Services Envelope 28 Drainage AS - 34 / Granville Construction of IIP packages Basic Infrastructure and Single Stage - One 2018-03- IBRD / 83560 Post Request for Bids Open - National 846,083.00 817,071.24 Completed 2017-04-18 2017-04-19 2017-04-23 2017-07-02 2017-05-25 2017-08-17 2017-06-26 2017-09-21 2018-01-24 for Water, Sanitation, Roads & Access to Services Envelope 20 Drainage AS - 35 / Retirement Construction of IIP packages Basic Infrastructure and Single Stage - One 2018-07- IBRD / 83560 Post Request for Bids Open - National 1,230,468.00 109,840.39 Completed 2017-09-12 2017-09-13 2017-09-17 2017-10-29 2018-02-21 2017-11-28 2018-04-16 2018-01-02 2018-12-14 for Water, Sanitation, Roads & Access to Services Envelope 01 Drainage AS - 37 / Russia Construction Basic Infrastructure and Single Stage - One 2018-12- of IIP packages for Water, IBRD / 83560 Post Request for Bids Open - National 738,496.00 716,987.09 Completed 2018-01-21 2017-01-25 2018-01-26 2018-04-06 2017-03-07 2018-05-22 2017-03-15 2018-06-26 2018-01-25 Access to Services Envelope 23 Sanitation, Roads & Drainage AS - 40-3 / Zinc Fence Basic Infrastructure and Single Stage - One 2018-06- Removal & Replacement - IBRD / 83560 Post Request for Bids Open - National 415,000.00 329,956.06 Completed 2017-09-02 2017-10-04 2017-09-07 2017-10-19 2017-10-25 2017-11-18 2017-11-09 2017-12-23 2017-12-21 Access to Services Envelope 21 Lots (Rose Town) 2 Lots AS - 71 / Treadlight Under Construction of IIP packages Basic Infrastructure and Single Stage - One 1,114,743.4 2019-06- IBRD / 83560 Post Request for Bids Open - National 1,607,407.00 Implementat 2018-08-27 2018-08-23 2018-09-01 2018-10-13 2018-10-31 2018-11-12 2018-11-27 2018-12-17 for Water, Sanitation, Roads & Access to Services Envelope 4 15 ion Drainage AS - 30 / Canaan Heights Construction of IIP packages Basic Infrastructure and Single Stage - One 1,201,796.0 2019-06- IBRD / 83560 Post Request for Bids Open - National 1,230,468.00 Completed 2018-08-14 2017-09-05 2018-08-19 2018-09-30 2017-10-05 2018-10-30 2018-02-22 2018-12-04 2019-01-14 for Water, Sanitation, Roads & Access to Services Envelope 7 02 Drainage AS - 25 / Denham Town Construction of IIP packages Basic Infrastructure and Single Stage - One 1,365,870.0 2019-06- IBRD / 83560 Post Request for Bids Open - National 1,893,023.00 Completed 2018-08-14 2018-01-02 2018-08-19 2018-09-30 2017-02-15 2018-10-30 2018-10-23 2018-12-04 2018-12-10 for Water, Sanitation, Roads & Access to Services Envelope 2 02 Drainage AS - 72 / Anchovy Construction of IIP packages Basic Infrastructure and Single Stage - One 2019-06- IBRD / 83560 Post Request for Bids Open - National 1,989,150.00 0.00 Canceled 2018-08-17 2018-08-23 2018-08-22 2018-10-03 2018-10-31 2018-11-02 2018-11-27 2018-12-07 for Water, Sanitation, Roads & Access to Services Envelope 05 Drainage Page 1 TA - 8 / Technical Support Institutional Strengthening Piloting of the Fukuoka Single Stage - One 2019-01- IBRD / 83560 for Urban Management and Post Request for Bids Open - National 155,000.00 0.00 Canceled 2018-04-07 2017-04-09 2018-04-12 2018-05-24 2018-05-03 2018-06-23 2018-05-14 2018-07-28 Landfill method at the dump Envelope 24 Public Safety in Retirement (Design & Build) AS - 28-1 / Rose Town IIP Basic Infrastructure and Single Stage - One 2019-06- package for Water Sanitation, IBRD / 83560 Post Request for Bids Open - National 1,671,670.00 0.00 Canceled 2018-08-31 2018-09-05 2018-10-17 2018-11-16 2018-12-21 Access to Services Envelope 19 Roads & Drainage TA - 16-3 / Restoration of Institutional Strengthening Community Driven 2019-05- composting structures - IBRD / 83560 for Urban Management and Post Direct 3,846.00 0.00 Canceled 2018-10-13 2018-10-18 2018-11-22 Development 21 stipend and materials Public Safety AS - 80 - 1 / ICDP Schools Basic Infrastructure and Single Stage - One 2020-10- Rehabilitation Package 4 - IBRD / 83560 Post Request for Bids Limited 92,000.00 85,468.95 Signed 2020-01-13 2020-02-17 2020-01-18 2020-02-17 2020-02-29 2020-03-02 2020-03-30 2020-04-20 2020-05-04 2020-09-14 Access to Services Envelope 31 Hazard Primary School AS - 80 - 2 / ICDP Schools Basic Infrastructure and Single Stage - One 2020-10- Rehabilitation Package 4 - IBRD / 83560 Post Request for Bids Limited 181,000.00 274,971.80 Signed 2020-01-13 2020-02-17 2020-01-18 2020-02-17 2020-02-29 2020-03-02 2020-03-30 2020-05-04 2020-05-04 2020-07-14 Access to Services Envelope 31 Treadlight Primary School AS - 80 - 3 / ICDP Schools Basic Infrastructure and Single Stage - One 2020-10- Rehabilitation - York Town IBRD / 83560 Post Request for Bids Limited 170,000.00 146,726.45 Signed 2020-01-13 2020-02-17 2020-01-18 2020-02-17 2020-02-29 2020-03-02 2020-03-30 2020-04-20 2020-05-04 2020-09-14 Access to Services Envelope 31 Primary School AS - 69 - 1 / The Supply and Installation of pump and tank Basic Infrastructure and Single Stage - One 2020-06- arrangement to supply water IBRD / 83560 Post Request for Bids Open - National 220,000.00 0.00 Canceled 2020-01-20 2020-01-25 2020-03-07 2020-04-06 2020-05-11 Access to Services Envelope 20 to High Rise Building - Wilton Gardens - Total – 11 AS - 47 / Wiring of Houses for Legal Connections Basic Infrastructure and Single Stage - One 2017-04- IBRD / 83560 Post Request for Bids Open - National 579,150.00 0.00 Canceled 2016-06-27 2016-07-02 2016-08-13 2016-09-12 2016-10-17 (multiple (#) communities - Access to Services Envelope 15 TBD) AS - 73-1 / Works contract - Mechanical, electrical, plumbing and civil works to Basic Infrastructure and Single Stage - One 2020-03- lift water beyond second floor IBRD / 83560 Post Request for Bids Open - National 390,000.00 0.00 Canceled 2019-06-10 2019-06-15 2019-07-27 2019-08-26 2019-09-30 Access to Services Envelope 28 of High Rise Buildings in Wilton Gardens and Hannah Town AS - 37 - 1 / Sterilization of Basic Infrastructure and Request for Single Stage - One 2020-04- Russia IIP Water Supply IBRD / 83560 Post Limited 8,000.00 0.00 Canceled 2020-01-25 2020-03-21 Access to Services Quotations Envelope 04 Network AS - 68 - 1 / The Supply and Installation of pump and tank Basic Infrastructure and Request for Single Stage - One 2020-04- arrangement to supply water IBRD / 83560 Post Limited 80,000.00 0.00 Canceled 2020-01-18 2020-03-14 Access to Services Quotations Envelope 13 for High Rise Building - Hannah Town - total – 53 AS - 64-1 / Construction Basic Infrastructure and Single Stage - One 2018-12- Works for the Upgrading of IBRD / 83560 Post Request for Bids Open - National 1,064,169.00 0.00 Canceled 2018-03-01 2018-03-06 2018-04-17 2018-05-17 2018-06-21 Access to Services Envelope 18 Community Sports Facilities AS - 40 / Zinc Fence Removal Basic Infrastructure and Request for Single Stage - One 2019-04- & Replacement - Lots (6 IBRD / 83560 Post Limited 450,000.00 0.00 Canceled 2018-08-25 2018-10-20 Access to Services Quotations Envelope 18 Communities/Lots) AS - 68 / Design and Build pump and tank arrangement Basic Infrastructure and Single Stage - Two 2019-08- to supply water for High Rise IBRD / 83560 Post Request for Bids Open - National 80,000.00 0.00 Canceled 2018-09-15 2019-03-14 2018-09-20 2018-11-01 2019-04-16 2019-01-14 2019-04-29 2019-02-18 Access to Services Envelope 17 Building - Hannah Town - total - 53 AS - 69 / Design and Build pump and tank arrangement Basic Infrastructure and Single Stage - Two 2019-08- to supply water to High Rise IBRD / 83560 Post Request for Bids Open - National 220,000.00 0.00 Canceled 2018-09-15 2019-03-14 2018-09-20 2018-11-01 2019-04-16 2019-01-14 2019-04-29 2019-02-18 Access to Services Envelope 17 Building - Wilton Gardens - Total - 11 AS - 53 / Rehabilitation Works for Community green spaces - landscaping, fencing, Basic Infrastructure and Single Stage - One 2018-09- IBRD / 83560 Post Request for Bids Open - National 810,000.00 0.00 Canceled 2017-11-28 2018-04-05 2017-12-03 2018-01-14 2018-04-26 2018-02-13 2019-01-28 2018-03-20 lighting, sanitary facilities, Access to Services Envelope 16 signage etc (Wilton, Hannah, Tivoli) AS - 40 - 4 / Steer Town Zinc Basic Infrastructure and Single Stage - One 2020-04- IBRD / 83560 Post Request for Bids Open - National 185,000.00 0.00 Canceled 2020-01-13 2020-02-28 2020-01-18 2020-02-08 2020-02-28 2020-02-22 2020-03-21 Fence Substitution Access to Services Envelope 30 AS - 40 – 4R / Steer Town Pending Basic Infrastructure and Single Stage - One 2021-05- Zinc Fence Substitution (Re- IBRD / 83560 Post Request for Bids Open - National 190,000.00 0.00 Implementat 2020-12-07 2020-12-12 2021-01-02 2021-02-20 2021-03-20 Access to Services Envelope 19 tender) ion GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual JM-JSIF-45098-GO-DIR / Basic Infrastructure and Provision of One (1) Garbage IBRD / 83560 Post Direct Selection Direct 164,000.00 136,124.95 Signed 2018-02-12 2018-04-03 2018-02-19 2018-05-24 2018-05-17 2018-09-10 2018-11-13 Access to Services Compactor Trucks (RBF) PM - 3 / Provision of Sports Utility Vehicle to support effective monitoring of a fast growing portfolio of projects Request for Single Stage - One under implementation as well IBRD / 83560 Project Administration Post Open - National 52,142.00 34,171.94 Signed 2018-03-31 2018-05-26 2018-11-15 2018-11-22 Quotations Envelope as being planned. Additionally to support training needs, stakeholder consultations, visibility etc. Page 2 PM - 5 / Office & Safety Request for Single Stage - One IBRD / 83560 Project Administration Post Open - National 17,500.00 0.00 Canceled 2018-04-02 2018-05-28 2018-11-24 Equipment Quotations Envelope TA - 1-3 / Equipment for JCF Institutional Strengthening Request for Single Stage - One - Rugged handhelds, Rugged IBRD / 83560 for Urban Management and Post Open - National 42,000.00 36,173.78 Signed 2017-04-15 2017-06-10 2017-09-14 2017-12-07 Quotations Envelope Tablets, GPS Units Public Safety Institutional Strengthening TA - 1-4 / Equipment for JCF Request for Single Stage - One IBRD / 83560 for Urban Management and Post Open - National 29,300.00 18,532.80 Signed 2017-04-15 2017-06-10 2017-03-09 2017-12-07 - Server, Computers, Laptops Quotations Envelope Public Safety Institutional Strengthening TA - 1-5 / Equipment for JCF Request for Single Stage - One IBRD / 83560 for Urban Management and Post Limited 2,800.00 3,062.21 Signed 2017-04-15 2017-01-11 2017-06-10 2017-03-09 2017-12-07 - UPS Quotations Envelope Public Safety Institutional Strengthening TA - 1-6 / Equipment for JCF Request for Single Stage - One IBRD / 83560 for Urban Management and Post Open - National 2,600.00 20,451.70 Signed 2017-04-15 2017-06-10 2017-06-16 2017-12-07 - Firewall Quotations Envelope Public Safety TA - 2 / Supply of Computers Institutional Strengthening Under and Computer related Request for Single Stage - One IBRD / 83560 for Urban Management and Post Open - National 503,875.00 0.00 Implementati 2017-06-10 2020-04-15 2017-08-05 2018-02-01 equipment Multiple lots - for Quotations Envelope Public Safety on the National Land Agency TA - 5-1 / Capacity Building (Equipping) for Municipal Institutional Strengthening Corporations, SDC, JCF and Request for Single Stage - One IBRD / 83560 for Urban Management and Post Open - National 270,703.00 64,272.02 Signed 2018-10-06 2018-12-01 2018-01-30 2019-05-30 2017-10-19 other entities to support Quotations Envelope Public Safety Urban Management and Public Safety - 7 ICDP parishes Under PS - 2-3-10 / YER 2018 Public Safety Enhancement Request for Single Stage - One IBRD / 83560 Post Open - National 45,000.00 0.00 Implementati 2018-04-07 2020-04-14 2018-06-02 2018-11-29 Gears and Alternative Livelihoods Quotations Envelope on PS - 2-3-12 / YER 2018 Public Safety Enhancement Request for Single Stage - One IBRD / 83560 Post Open - National 63,570.00 63,984.20 Completed 2018-04-06 2018-06-01 2019-07-18 2018-11-28 2019-07-18 Teaching Aides and Alternative Livelihoods Quotations Envelope PS - 5-2 / Training of CBOs and Capacity Building - Small office & administrative Public Safety Enhancement Request for Single Stage - One IBRD / 83560 Post Open - National 60,000.00 7,297.79 Signed 2017-10-06 2017-12-01 2018-04-09 2018-05-30 equipment to support and Alternative Livelihoods Quotations Envelope Community governance structures PS - 10-1 / School Governance & Ancillary Workers - First Aid & CPR Kits, Public Safety Enhancement Request for Single Stage - One IBRD / 83560 Post Open - National 52,000.00 24,187.35 Completed 2018-09-14 2018-11-09 2018-04-09 2019-05-08 2019-04-09 Posters, Extinguishers, and Alternative Livelihoods Quotations Envelope Signage, Tools & Supplies, etc.) AS - 41 / Garbage Skips (55) Basic Infrastructure and Request for Single Stage - One IBRD / 83560 Post Open - National 130,020.00 0.00 Canceled 2016-06-20 2016-08-15 2017-02-11 - Fabrication & Marking Access to Services Quotations Envelope AS - 44 / Compactor Trucks Basic Infrastructure and Request for Single Stage - One - 2 (incl. 24 mths IBRD / 83560 Post Open - National 264,000.00 254,828.89 Signed 2017-12-22 2018-05-23 2018-01-11 2018-11-19 Access to Services Quotations Envelope Maintenance & Parts) Basic Infrastructure and Request for Single Stage - One AS - 45 / Provision of Baler IBRD / 83560 Post Open - National 152,000.00 22,767.91 Completed 2018-03-12 2018-05-07 2018-08-28 2018-11-03 2018-08-28 Access to Services Quotations Envelope AS - 46 / Provision of Wood Basic Infrastructure and Request for Single Stage - One IBRD / 83560 Post Open - National 26,666.00 66,572.93 Completed 2016-05-06 2016-07-01 2016-04-28 2016-12-28 2016-07-29 Chippers Access to Services Quotations Envelope AS - 55 / SWM- Zika Project Basic Infrastructure and Request for Single Stage - One - Provision of mosquito nets IBRD / 83560 Post Limited 38,759.00 7,140.89 Completed 2016-11-08 2016-09-15 2017-01-03 2016-11-17 2017-07-02 2016-11-17 Access to Services Quotations Envelope and meshed drum covers AS - 60 / Provision of Units for community storage of Basic Infrastructure and Request for Single Stage - One IBRD / 83560 Post Open - National 100,852.00 97,091.49 Completed 2016-05-11 2016-07-06 2016-04-08 2017-01-02 2016-09-05 Waste i.e. 55-gallon Access to Services Quotations Envelope drums/bins AS - 70-1 / Supply and Basic Infrastructure and Request for Single Stage - One delivery of Polyethylene pipes IBRD / 83560 Post Open - National 290,708.00 71,193.86 Completed 2018-11-06 2019-01-01 2019-03-13 2019-06-30 2019-03-13 Access to Services Quotations Envelope - Greenwich Town IIP AS - 70 / Supply and delivery Basic Infrastructure and Request for Single Stage - One of Polyethylene pipes - IBRD / 83560 Post Open - National 92,111.00 17,157.05 Completed 2018-11-06 2019-01-01 2019-03-13 2019-06-30 2019-03-13 Access to Services Quotations Envelope Retirement IIP AS - 70-2 / Supply and Basic Infrastructure and Request for Single Stage - One delivery of Polyethylene pipes IBRD / 83560 Post Open - National 27,523.00 17,157.05 Completed 2018-11-06 2019-01-01 2019-03-13 2019-06-30 2019-03-13 Access to Services Quotations Envelope - Steer Town IIP AS - 77 / Equipping of Utility Basic Infrastructure and Request for Single Stage - One Wardens - leak detection kits IBRD / 83560 Post Limited 50,000.00 194,351.61 Completed 2019-06-22 2019-07-30 2019-08-17 2019-07-23 2020-02-13 2019-08-23 Access to Services Quotations Envelope etc TA - 5-8 / Equipping of Municipal Corporations / Institutional Strengthening Under Single Stage - One Regulatory Authorities to IBRD / 83560 for Urban Management and Post Request for Bids Open - National 250,000.00 0.00 Implementati 2019-08-05 2020-03-10 2019-08-10 2019-09-21 2020-03-30 2019-10-21 2020-09-07 2019-11-25 2020-05-23 Envelope enhance GIS System ( Public Safety on Computers, tablets etc) PS - 28 / ICDP Enterprise Development Project - Procurement of equipment (multiple contracts) for Public Safety Enhancement Single Stage - One IBRD / 83560 Post Request for Bids Open - National 120,000.00 0.00 Canceled 2019-07-22 2019-07-27 2019-09-07 2019-10-07 2019-11-11 2020-05-09 microenterpises e.g. sewing and Alternative Livelihoods Envelope machines, barber equipment, hair salon equipment, IT equiment for Internet cafes AS - 78 / Procurement of one Basic Infrastructure and Garbage (Compactor) Truck IBRD / 83560 Post Direct Selection Direct 136,000.00 137,887.52 Completed 2019-07-29 2018-03-29 2019-08-03 2018-05-24 2019-09-07 2018-11-27 2020-03-05 2018-11-27 Access to Services (RBF) Page 3 PM - 3 - 1 / Procurement of Request for Single Stage - One IBRD / 83560 Project Administration Post Open - National 80,000.00 87,839.94 Completed 2019-12-21 2020-02-22 2020-02-25 2020-08-20 2020-02-25 Motor Vehicles (2) Quotations Envelope PS - 2-3-11 / YER 2018 Public Safety Enhancement Request for Single Stage - One Musical Equipment / Art IBRD / 83560 Post Open - National 37,500.00 0.00 Canceled 2018-05-15 2018-07-10 2019-01-06 and Alternative Livelihoods Quotations Envelope Supplies Institutional Strengthening TA - 15-1 / Portable weigh Request for Single Stage - One IBRD / 83560 for Urban Management and Post Limited 2,308.00 0.00 Canceled 2018-09-18 2018-11-13 2019-05-12 scales - 30 scales Quotations Envelope Public Safety TA - 17-4 / School Environmental Programme Institutional Strengthening Replace styrofoam lunch box Request for Single Stage - One IBRD / 83560 for Urban Management and Post Open - National 75,385.00 0.00 Canceled 2018-08-17 2018-10-12 2019-04-10 with resusable utensils; Quotations Envelope Public Safety badges; t-shirts, plates and posters etc. PS - 7-1 / School Institutional Strengthening Request for Single Stage - One Environmental Programme - IBRD / 83560 for Urban Management and Post Limited 27,135.00 0.00 Canceled 2018-10-18 2018-12-13 2019-06-11 Quotations Envelope Equipment, prizes Public Safety PS - 13-2 / Sports Public Safety Enhancement Request for Single Stage - One Development - Gears and IBRD / 83560 Post Open - National 168,000.00 0.00 Canceled 2018-06-17 2018-08-12 2019-02-08 and Alternative Livelihoods Quotations Envelope Equipment AS -56 / SWM- Zika Project - School Programme, Goods for Basic Infrastructure and Request for Single Stage - One IBRD / 83560 Post Limited 16,666.00 0.00 Canceled 2018-08-22 2018-10-17 2019-04-15 Greenhouse construction - Access to Services Quotations Envelope lumber etc PS - 21 / Signage for Safe Passages in seven Public Safety Enhancement Request for Single Stage - One IBRD / 83560 Post Limited 32,000.00 0.00 Canceled 2019-08-05 2019-09-30 2020-03-28 communities - Supply & and Alternative Livelihoods Quotations Envelope Install PS - 23 / YER Cycle 3: School Enrichment - small equipping and supplies (small tools for development of and creation Public Safety Enhancement Request for Single Stage - One of therapeutic spaces as well IBRD / 83560 Post Limited 38,843.00 0.00 Canceled 2019-06-08 2019-08-03 2020-01-30 and Alternative Livelihoods Quotations Envelope as other activities for student enrichment eg. school farms, sports gears and equipment, etc.) AS - 61 / Provision of Tyre Basic Infrastructure and Request for Single Stage - One shredders (Reduce waste i.e IBRD / 83560 Post Open - National 155,038.00 0.00 Canceled 2018-02-10 2018-04-07 2018-10-04 Access to Services Quotations Envelope tyres volume) TA - 5-3-2 / Service contract Institutional Strengthening for the provision of Request for Single Stage - One IBRD / 83560 for Urban Management and Post Open - National 10,000.00 0.00 Canceled 2019-06-22 2019-08-17 2020-02-13 promotional items pens, Quotations Envelope Public Safety folders etc TA - 15 / Supply & Install Institutional Strengthening Request for Single Stage - One colour-coded bins for sorting IBRD / 83560 for Urban Management and Post Open - National 73,846.00 0.00 Canceled 2018-09-18 2018-11-13 2019-05-12 Quotations Envelope of solid waste - 1200 bins Public Safety AS - 49 / Provision of Energy efficient lighting (light bulbs Basic Infrastructure and Request for Single Stage - One for exchange as part of IBRD / 83560 Post Open - National 12,500.00 0.00 Canceled 2018-07-25 2018-09-19 2019-03-18 Access to Services Quotations Envelope Electification/Electricity Regularization) Institutional Strengthening TA - 15-2 / Cell Phones - 60 Request for Single Stage - One IBRD / 83560 for Urban Management and Post Limited 9,231.00 0.00 Canceled 2018-09-18 2018-11-13 2019-05-12 cell phones Quotations Envelope Public Safety PM - 6 - 1 / Procurement of Single Stage - One IBRD / 83560 Project Administration Post Request for Bids Open - National 120,000.00 88,883.70 Completed 2020-01-20 2020-01-21 2020-01-25 2020-04-14 2020-02-08 2020-02-04 2020-02-22 2020-02-19 2020-03-21 2020-03-11 2020-04-04 2020-04-01 IT Equipment (Computers) Envelope PS - 28 - 1 / ICDP Enterprise Public Safety Enhancement Request for Single Stage - One Development Project - Hair IBRD / 83560 Post Limited 9,000.00 17,949.34 Signed 2020-01-25 2020-01-22 2020-02-29 2020-08-26 2020-03-14 and Alternative Livelihoods Quotations Envelope and Nail Equipment PS - 28 - 2 / ICDP Enterprise Development Project - Public Safety Enhancement Request for Single Stage - One IBRD / 83560 Post Limited 11,000.00 7,465.58 Completed 2020-01-25 2020-01-22 2020-02-29 2020-05-21 2020-03-14 2020-05-21 Tailoring and Dress Making and Alternative Livelihoods Quotations Envelope Equipment PS - 2 - 3 -11R / YER 2018 Public Safety Enhancement Request for Single Stage - One IBRD / 83560 Post Open - National 88,000.00 174,169.76 Signed 2020-02-16 2020-04-14 2020-04-12 2020-06-03 2020-04-26 2020-06-03 Teaching Aides and Alternative Livelihoods Quotations Envelope TA - 23 / Stakeholder Capacity Building: Procurement of two Institutional Strengthening Under Single Stage - One Commercial Tipper (Dump) IBRD / 83560 for Urban Management and Post Request for Bids Open - National 322,000.00 0.00 Implementati 2020-02-12 2020-03-25 2020-02-17 2020-04-15 2020-03-09 2020-04-09 2020-03-16 2020-04-20 2020-04-27 Envelope trucks and two 4X4 Double Public Safety on cab pick- up trucks which will be done in lots. PS - 28 - 3 / ICDP Enterprise Public Safety Enhancement Single Stage - One Development Project - IT IBRD / 83560 Post Request for Bids Open - National 38,000.00 0.00 Canceled 2020-01-20 2020-01-21 2020-01-25 2020-02-15 2020-02-25 2020-02-29 2020-02-17 2020-03-21 2020-04-20 and Alternative Livelihoods Envelope equipment PS - 28 - 4 / ICDP Enterprise Public Safety Enhancement Request for Single Stage - One IBRD / 83560 Post Limited 9,000.00 0.00 Canceled 2020-01-25 2020-02-29 2020-03-14 Development Project - Boat and Alternative Livelihoods Quotations Envelope PM - 6 / IT Support, Request for Single Stage - One IBRD / 83560 Project Administration Post Open - National 47,619.00 0.00 Canceled 2018-04-02 2018-05-28 2018-11-24 Equipment, Software & Tools Quotations Envelope AS - 70-5 / Supply and Basic Infrastructure and Request for Single Stage - One delivery of Polyethylene pipes IBRD / 83560 Post Open - National 80,000.00 0.00 Canceled 2018-11-06 2019-01-01 2019-06-30 Access to Services Quotations Envelope - Hannah Town IIP AS - 70-3 / Supply and Basic Infrastructure and Request for Single Stage - One delivery of Polyethylene pipes IBRD / 83560 Post Open - National 62,307.00 0.00 Canceled 2018-11-06 2019-01-01 2019-06-30 Access to Services Quotations Envelope - Canaan Heights - IIP Page 4 AS - 70-6 / Supply and Basic Infrastructure and Request for Single Stage - One delivery of Polyethylene pipes IBRD / 83560 Post Open - National 220,000.00 0.00 Canceled 2018-11-06 2019-01-01 2019-06-30 Access to Services Quotations Envelope - Wilton Gardens IIP AS - 70-4 / Supply and Basic Infrastructure and Request for Single Stage - One delivery of Polyethylene pipes IBRD / 83560 Post Open - National 200,678.00 0.00 Canceled 2018-11-06 2019-01-01 2019-06-30 Access to Services Quotations Envelope - Denham Town IIP PS - 28 - 5 / ICDP Enterprise Public Safety Enhancement Request for Single Stage - One Development Project - IBRD / 83560 Post Limited 3,000.00 0.00 Canceled 2020-09-12 2020-10-17 2020-10-31 and Alternative Livelihoods Quotations Envelope Coolers/Igloos AS - 70-7 / Procurement of Polyethylene potable water Basic Infrastructure and Single Stage - One IBRD / 83560 Post Request for Bids Open - National 327,577.00 0.00 Canceled 2018-07-31 2018-08-05 2018-09-16 2018-10-16 2018-11-20 2019-05-19 pipes and fittings as Access to Services Envelope replacement for PVC pipes PM - 6 - 2 & PS - 28 - 3R / Under Procurement of IT Software Public Safety Enhancement Request for Single Stage - One IBRD / 83560 Post Limited 70,000.00 0.00 Implementati 2020-07-08 2020-06-22 2020-08-10 2020-08-17 and Equipment (Computers, and Alternative Livelihoods Quotations Envelope on tablets and printers) TA - 24 / ICDP Stakeholder Capacity Building Technical Institutional Strengthening Pending Request for Single Stage - One Assistance: Provision of IBRD / 83560 for Urban Management and Post Limited 4,500.00 0.00 Implementati 2021-01-02 2021-02-27 2021-03-29 Quotations Envelope equipment ( #5 drones) for Public Safety on Parish Councils PS - 28 - 6 / ICDP Enterprise Pending Development Project - Public Safety Enhancement Request for Single Stage - One IBRD / 83560 Post Limited 56,000.00 0.00 Implementati 2021-01-02 2021-03-01 2021-03-31 Procurement of Small and Alternative Livelihoods Quotations Envelope on equipment for Entrepreneurs NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TA - 3 / Training & Capacity Institutional Strengthening Pending Building related to the Crime Request for Single Stage - One IBRD / 83560 for Urban Management and Post Open - National 40,515.00 0.00 Implementati 2018-06-04 2018-07-30 2019-01-26 Observatory & Violence Quotations Envelope Public Safety on Reduction - MNS TA - 9 / Delivery of training via pre-designed modules for Institutional Strengthening Request for Single Stage - One mediators and Violence IBRD / 83560 for Urban Management and Post Open - National 117,187.00 0.00 Canceled 2018-06-06 2018-08-01 2019-01-28 Quotations Envelope Interruptors to support Public Safety increased Public Safety PS - 4-2 / Youth Skills Training - Landscaping, Animation, Construction et. al. - as per Labour Market Public Safety Enhancement Single Stage - One IBRD / 83560 Post Request for Bids Open - National 1,080,769.00 769,420.77 Completed 2018-03-11 2018-04-10 2018-03-16 2018-04-27 2018-04-25 2018-05-27 2018-05-21 2018-07-01 2018-06-26 2018-12-28 2018-06-26 assessments. Tuition fees are and Alternative Livelihoods Envelope paid directly to Institutions for beneficiaries. Annual Programme Cycles III PS - 6-3-3 / Social Marketing Public Safety Enhancement Request for Single Stage - One Campaign Roll Out - IBRD / 83560 Post Open - National 310,000.00 168,545.53 Completed 2018-04-15 2018-06-10 2018-06-19 2018-12-07 2018-06-19 and Alternative Livelihoods Quotations Envelope Billboards PS - 10 / School Governance Public Safety Enhancement Request for Single Stage - One & Ancillary Workers - CPR & IBRD / 83560 Post Open - National 23,076.00 31,918.68 Completed 2017-09-06 2017-11-01 2017-07-27 2018-04-30 2018-09-25 and Alternative Livelihoods Quotations Envelope First Aid Training TA - 3-1 / Training & Institutional Strengthening Capacity Building related to Request for Single Stage - One IBRD / 83560 for Urban Management and Post Limited 23,515.00 2,388.06 Completed 2018-08-25 2018-07-13 2018-10-20 2018-07-25 2019-04-18 2018-07-25 the Crime Observatory & Quotations Envelope Public Safety Violence reduction - JCF PS - 3 / Operation Certification - Registrar Public Safety Enhancement IBRD / 83560 Post Direct Selection Direct 65,000.00 93,854.76 Completed 2017-03-01 2016-11-22 2017-03-06 2017-01-16 2017-04-10 2017-01-23 2017-10-07 2017-12-29 Generals Department (RGD) and Alternative Livelihoods Cycle 1 PS - 17-3 / Skills Training for Youth Alternative Livelihood for Skills Development - Public Safety Enhancement Request for Single Stage - One Service Provider to deliver IBRD / 83560 Post Open - National 75,840.00 111,403.04 Completed 2019-06-22 2019-08-17 2019-10-07 2020-02-13 2019-10-07 and Alternative Livelihoods Quotations Envelope training for Blue Economy Sector - Underwater Film making PS - 17-1 / Skills Training for Youth Alternative Livelihood for Skills Development - Public Safety Enhancement Single Stage - One Service Provider to deliver IBRD / 83560 Post Request for Bids Open - National 102,960.00 147,761.26 Completed 2019-07-29 2019-08-06 2019-08-03 2019-09-14 2019-08-27 2019-10-14 2019-09-23 2019-11-18 2019-10-07 2020-05-16 2019-10-07 and Alternative Livelihoods Envelope training for Blue Economy Sector - Sports Equipment Handling and Repairs PS - 17 / Skills Training for Youth Alternative Livelihood for Skills Development - Service Provider to deliver Public Safety Enhancement Single Stage - One IBRD / 83560 Post Request for Bids Open - National 171,600.00 102,985.12 Signed 2019-07-29 2019-08-06 2019-08-03 2019-09-14 2019-08-27 2019-10-14 2019-09-30 2019-11-18 2019-10-07 2020-05-16 training for Blue Economy and Alternative Livelihoods Envelope Sector - Recreational Tourism with Boat Handling and Repairs PS - 17-2 / Skills Training for Youth Alternative Livelihood for Skills Development - Public Safety Enhancement Single Stage - One Service Provider to deliver IBRD / 83560 Post Request for Bids Open - National 171,600.00 147,388.13 Signed 2019-07-29 2019-08-06 2019-08-03 2019-09-14 2019-08-27 2019-10-14 2019-09-16 2019-11-18 2019-10-07 2020-05-16 and Alternative Livelihoods Envelope training for Blue Economy Sector - Life Guard and Diving Certification Page 5 TA - 5-3-3 / Service contract for the design, printing and Institutional Strengthening publication of conference Request for Single Stage - One IBRD / 83560 for Urban Management and Post Limited 10,000.00 0.00 Canceled 2019-06-08 2019-08-03 2020-01-30 materials i.e. books, Quotations Envelope Public Safety pamphlets, conference package, PS - 8-2 / Enterprise Institutional Strengthening Development (Venue, Request for Single Stage - One IBRD / 83560 for Urban Management and Post Open - National 166,154.00 0.00 Canceled 2018-10-18 2018-12-13 2019-06-11 Refreshments, Quotations Envelope Public Safety Accommodations) PS - 24 / Youth Education & Recreation Cycle 3: Venue, Public Safety Enhancement Request for Single Stage - One refreshments and IBRD / 83560 Post Limited 7,462.00 0.00 Canceled 2019-06-08 2019-08-03 2020-01-30 and Alternative Livelihoods Quotations Envelope consultations for two-day Numerto two day training PS - 6-8 / Communications- Fairs, Media, - development and publication of materials e.g. Brochures, Community Public Safety Enhancement Request for Single Stage - One IBRD / 83560 Post Open - National 213,200.00 0.00 Canceled 2016-06-10 2016-08-05 2017-02-01 Signage, Videos, Costs for and Alternative Livelihoods Quotations Envelope conferences & symposium on Best Practices etc. Billboard production & placement TA - 5-3-1 / Service contract Institutional Strengthening Request for Single Stage - One for the provision of materials IBRD / 83560 for Urban Management and Post Limited 10,000.00 0.00 Canceled 2019-06-08 2019-08-03 2020-01-30 Quotations Envelope - booth, banners Public Safety PS - 3-1 / Operation Public Safety Enhancement IBRD / 83560 Post Direct Selection Direct 10,539.00 0.00 Canceled 2018-08-20 2018-08-25 2018-09-29 2019-03-28 Certification - Police Records and Alternative Livelihoods PS - 12 / Service Contracts for Solid Waste Wardens: Public Safety Enhancement Community Driven IBRD / 83560 Post Direct 247,905.00 0.00 Canceled 2016-01-05 2016-01-10 2016-02-14 2016-08-12 Stipends for Wardens & CBOs: and Alternative Livelihoods Development YR 1 PS - 12-1 / Service Contracts for Solid Waste Wardens: Public Safety Enhancement Community Driven IBRD / 83560 Post Direct 273,680.00 0.00 Canceled 2018-01-05 2018-01-10 2018-02-14 2018-08-13 Stipends for Wardens & CBOs: and Alternative Livelihoods Development Yr 2 PS - 12-2 / Service Contracts for Solid Waste Wardens: Public Safety Enhancement Community Driven IBRD / 83560 Post Direct 284,594.00 0.00 Canceled 2019-01-05 2019-01-10 2019-02-14 2019-08-13 Stipends for Wardens & CBOs: and Alternative Livelihoods Development Yr 3 AS - 51 / Service Contracts Basic Infrastructure and Community Driven for Wardens: Yr 1 - Stipends IBRD / 83560 Post Open - National 362,325.00 0.00 Canceled 2016-10-02 2016-10-07 2016-11-18 2016-12-18 2017-01-22 2017-07-21 Access to Services Development for Wardens & CBOs TA - 5 / Capacity Building Institutional Strengthening (Training) for Municipal Request for Single Stage - One IBRD / 83560 for Urban Management and Post Open - National 20,703.00 0.00 Canceled 2018-10-06 2018-12-01 2019-05-30 Corporations - 7 ICDP Quotations Envelope Public Safety parishes TA - 5-4 / Institutional Strengthening Conference/Workshop/Semin Request for Single Stage - One IBRD / 83560 for Urban Management and Post Limited 50,000.00 0.00 Canceled 2019-06-08 2019-08-03 2020-01-30 ar Venue and refreshment Quotations Envelope Public Safety for Contractor/Consultant PS - 1-5-2 / Community Public Safety Enhancement Request for Single Stage - One Safety Project - Capacity IBRD / 83560 Post Open - National 156,000.00 0.00 Canceled 2018-04-20 2018-06-15 2018-12-12 and Alternative Livelihoods Quotations Envelope Building of Groups PS - 4-1 / Youth Skills Training - Landscaping, Animation, Construction et. al. - as per Labour Market Public Safety Enhancement Single Stage - One IBRD / 83560 Post Request for Bids Open - National 530,769.00 0.00 Canceled 2017-08-12 2017-08-17 2017-09-28 2017-10-28 2017-12-02 2018-05-31 assessments. Tuition fees are and Alternative Livelihoods Envelope paid directly to Institutions for beneficiaries. Annual Programme Cycles II CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PM - 1 / Community waste Consultant management assessment (IVA) IBRD / 83560 Project Administration Post Qualification Open - National 42,000.00 50,543.79 Signed 2017-11-01 2016-03-01 2017-11-22 2018-01-05 2016-04-12 2018-02-04 2016-08-18 2018-03-11 2016-08-18 2018-09-07 - Year 1 Selection PM - 1-1 / Community waste Consultant management assessment (IVA) IBRD / 83560 Project Administration Post Qualification Open - National 112,281.00 107,405.23 Completed 2018-11-01 2017-07-29 2018-11-22 2019-01-05 2017-09-07 2019-02-04 2017-10-17 2019-03-11 2017-10-24 2019-09-07 2017-10-24 - Year 2 Selection PM - 1-2 / Community waste Consultant management assessment (IVA) IBRD / 83560 Project Administration Post Qualification Open - National 120,000.00 94,228.38 Signed 2019-11-01 2018-07-28 2019-11-22 2020-01-05 2018-11-21 2020-02-04 2019-02-19 2020-03-10 2019-02-26 2020-09-06 - Year 3 Selection PM - 2 / Mid-Term Consultant Evaluation (Surveys - Focus IBRD / 83560 Project Administration Post Qualification Open - National 109,300.00 113,318.90 Signed 2018-02-12 2017-12-09 2018-03-05 2018-04-18 2018-01-08 2018-05-18 2018-03-01 2018-06-22 2018-03-08 2018-12-19 Groups, etc) Selection Consultant PS - 6 / Social Marketing Public Safety Enhancement IBRD / 83560 Post Qualification Open - National 55,000.00 71,579.54 Completed 2016-03-01 2015-09-08 2016-03-22 2016-05-05 2015-09-15 2016-06-04 2016-02-29 2016-07-09 2016-03-29 2017-01-05 2017-12-22 Strategy and Alternative Livelihoods Selection PS - 6-1 / Social Marketing Consultant Campaign Roll Out - Initial 6 Public Safety Enhancement IBRD / 83560 Post Qualification Open - National 22,500.00 0.00 Canceled 2017-04-01 2017-04-22 2017-06-05 2017-07-05 2017-08-09 2018-02-05 month Engagements of a and Alternative Livelihoods Selection i.Coordinator Page 6 AS - 1 / Maxfield Park Design Consultant Basic Infrastructure and of IIP packages for Water, IBRD / 83560 Post Qualification Open - National 64,666.00 83,492.71 Completed 2016-07-02 2015-09-01 2016-07-23 2016-09-05 2016-08-18 2016-10-05 2016-10-29 2016-11-09 2016-11-29 2017-05-08 2018-10-08 Access to Services Sanitation, Roads & Drainage Selection AS - 2 / Barrett Town Design Consultant Basic Infrastructure and of IIP packages for Water, IBRD / 83560 Post Qualification Open - National 80,158.00 102,959.36 Completed 2015-10-05 2015-10-10 2015-10-26 2015-12-09 2015-11-15 2016-01-08 2016-03-07 2016-02-12 2016-02-07 2016-08-10 2019-03-27 Access to Services Sanitation, Roads & Drainage Selection AS - 3 / Wilton Gardens Consultant Design of IIP packages for Basic Infrastructure and IBRD / 83560 Post Qualification Open - National 64,666.00 80,195.73 Completed 2015-11-23 2015-11-21 2015-12-14 2016-01-27 2016-01-11 2016-02-26 2016-08-26 2016-04-01 2016-09-01 2016-09-28 2016-09-16 Water, Sanitation, Roads & Access to Services Selection Drainage AS - 4 / Tivoli Gardens Consultant Design of IIP packages for Basic Infrastructure and IBRD / 83560 Post Qualification Open - National 80,539.00 73,608.52 Completed 2015-11-23 2015-11-21 2015-12-14 2016-01-27 2016-01-11 2016-02-26 2016-01-11 2016-04-01 2016-09-01 2016-09-28 2016-09-01 Water, Sanitation, Roads & Access to Services Selection Drainage AS - 5 / Denham Town Consultant Design of IIP packages for Basic Infrastructure and IBRD / 83560 Post Qualification Open - National 64,666.00 107,611.99 Completed 2015-11-23 2015-11-21 2015-12-14 2016-01-27 2016-01-18 2016-02-26 2016-01-18 2016-04-01 2016-09-01 2016-09-28 2016-09-01 Water, Sanitation, Roads & Access to Services Selection Drainage AS - 6 / Hannah Town Design Consultant Basic Infrastructure and of IIP packages for Water, IBRD / 83560 Post Qualification Open - National 64,666.00 74,454.25 Completed 2015-11-23 2015-11-03 2015-12-14 2016-01-27 2016-01-11 2016-02-26 2016-07-07 2016-04-01 2016-09-01 2016-09-28 2019-03-27 Access to Services Sanitation, Roads & Drainage Selection AS - 7 / Greenwich Town Consultant Design of IIP packages for Basic Infrastructure and IBRD / 83560 Post Qualification Open - National 64,666.00 97,862.21 Completed 2015-11-23 2015-11-23 2015-12-14 2016-01-27 2016-01-11 2016-02-26 2016-08-26 2016-04-01 2016-09-01 2016-09-28 2017-10-04 Water, Sanitation, Roads & Access to Services Selection Drainage AS - 8 / Rose Town Design of Consultant Basic Infrastructure and IIP packages for Water, IBRD / 83560 Post Qualification Open - National 64,666.00 78,166.52 Completed 2015-11-23 2015-11-21 2015-12-14 2016-01-27 2015-01-11 2016-02-26 2016-07-11 2016-04-01 2016-09-01 2016-09-28 2020-04-28 Access to Services Sanitation, Roads & Drainage Selection AS - 9 / Majesty Gardens Consultant Design of IIP packages for Basic Infrastructure and IBRD / 83560 Post Qualification Open - National 64,666.00 92,020.25 Completed 2015-11-23 2015-11-28 2015-12-14 2016-01-27 2016-01-21 2016-02-26 2016-01-21 2016-04-01 2016-09-01 2016-09-28 2016-09-01 Water, Sanitation, Roads & Access to Services Selection Drainage AS - 10 / Canaan Heights Consultant Design of IIP packages for Basic Infrastructure and IBRD / 83560 Post Qualification Open - National 64,666.00 127,563.75 Completed 2015-11-23 2015-11-18 2015-12-14 2016-01-27 2016-01-11 2016-02-26 2016-10-03 2016-04-01 2016-10-24 2016-09-28 2018-02-28 Water, Sanitation, Roads & Access to Services Selection Drainage AS - 11 / Treadlight Design Consultant Basic Infrastructure and of IIP packages for Water, IBRD / 83560 Post Qualification Open - National 64,666.00 119,019.65 Completed 2015-11-23 2015-11-28 2015-12-14 2016-01-27 2016-01-21 2016-02-26 2016-10-17 2016-04-01 2016-10-24 2016-09-28 2016-10-24 Access to Services Sanitation, Roads & Drainage Selection AS - 12 / York Town Design Consultant Basic Infrastructure and Pending of IIP packages for Water, IBRD / 83560 Post Qualification Open - National 187,500.00 0.00 2015-11-23 2015-12-14 2016-01-27 2016-02-26 2016-04-01 2016-09-28 Access to Services Implementation Sanitation, Roads & Drainage Selection AS - 13 / Steer Town Design Consultant Basic Infrastructure and Under of IIP packages for Water, IBRD / 83560 Post Qualification Open - National 64,666.00 0.00 2015-11-23 2016-01-15 2015-12-14 2016-01-27 2016-02-26 2016-04-01 2016-09-28 Access to Services Implementation Sanitation, Roads & Drainage Selection AS - 14 / Granville Design of Consultant Basic Infrastructure and IIP packages for Water, IBRD / 83560 Post Qualification Open - National 88,476.00 111,910.23 Completed 2015-11-23 2016-01-15 2015-12-14 2016-01-27 2016-01-15 2016-02-26 2016-09-12 2016-04-01 2016-09-26 2016-09-28 2018-03-24 Access to Services Sanitation, Roads & Drainage Selection AS - 15 / Retirement Design Consultant Basic Infrastructure and of IIP packages for Water, IBRD / 83560 Post Qualification Open - National 64,666.00 117,663.58 Completed 2015-11-23 2015-11-28 2015-12-14 2016-01-27 2016-01-15 2016-02-26 2016-05-09 2016-04-01 2016-09-26 2016-09-28 2019-09-04 Access to Services Sanitation, Roads & Drainage Selection AS - 16 / Anchovy Design of Consultant Basic Infrastructure and Under IIP packages for Water, IBRD / 83560 Post Qualification Open - National 112,285.00 0.00 2015-11-23 2015-12-14 2016-01-27 2016-02-26 2016-04-01 2016-09-28 Access to Services Implementation Sanitation, Roads & Drainage Selection AS - 17 / Russia Design of IIP Consultant Basic Infrastructure and packages for Water, IBRD / 83560 Post Qualification Open - National 64,666.00 93,969.28 Completed 2015-11-23 2015-11-28 2015-12-14 2016-01-27 2016-01-15 2016-02-26 2016-01-13 2016-04-01 2016-07-04 2016-09-28 2016-07-04 Access to Services Sanitation, Roads & Drainage Selection AS - 18 / Ellerslie Design of Consultant Basic Infrastructure and IIP packages for Water, IBRD / 83560 Post Qualification Open - National 48,793.00 35,480.42 Completed 2015-11-23 2015-11-28 2015-12-14 2016-01-27 2016-01-11 2016-02-26 2016-09-01 2016-04-01 2016-09-01 2016-09-28 2018-09-30 Access to Services Sanitation, Roads & Drainage Selection AS - 19 / Upgrading of Basic Infrastructure and Least Cost Under School Infrastructure - IBRD / 83560 Post Open - National 281,550.00 0.00 2018-02-15 2018-09-24 2018-03-08 2018-04-21 2018-05-19 2018-06-18 2018-07-23 2018-08-27 2019-02-23 Access to Services Selection Implementation Learning & Safety AS -64 / Supervision of Construction Works for the Basic Infrastructure and Least Cost Upgrading of Community IBRD / 83560 Post Open - National 44,169.00 21,365.72 Completed 2017-10-02 2018-03-07 2017-10-23 2017-12-06 2018-04-05 2018-01-03 2018-04-19 2018-02-02 2018-05-03 2018-03-09 2018-05-18 2018-04-13 2018-05-23 2018-10-10 2018-05-23 Access to Services Selection Sports Facilities (Maxfield Park) AS - 66 / Environment Consultant Monitoring & Reporting for IIP Basic Infrastructure and Under IBRD / 83560 Post Qualification Open - National 33,478.00 0.00 2017-10-20 2017-03-14 2017-11-10 2017-12-24 2018-01-23 2018-02-27 2018-08-26 Works - Water, Air,Noise Access to Services Implementation Selection quality Testing & Reporting AS - 66-1 / Environment Monitoring & Reporting for IIP Consultant Basic Infrastructure and Under Works - Water, Air,Noise IBRD / 83560 Post Qualification Open - National 91,173.00 0.00 2017-02-07 2019-10-11 2017-02-28 2017-04-13 2017-05-13 2017-06-17 2017-12-14 Access to Services Implementation quality Testing & Reporting (7 Selection communities) AS - 52 / Supervision of Construction for SWM Basic Infrastructure and Least Cost enclosures i.e. Skip & Drum IBRD / 83560 Post Open - National 139,108.00 22,040.41 Signed 2018-08-17 2016-01-01 2018-09-07 2018-10-21 2016-01-19 2018-11-18 2016-02-09 2018-12-18 2016-03-01 2019-01-22 2016-03-03 2019-02-26 2016-04-05 2019-08-25 Access to Services Selection enclosures, Recycle stations, Composting bins Page 7 TA - 5-2 / Consultant Firm to plan and execute Institutional Strengthening Least Cost Construction IBRD / 83560 for Urban Management and Post Open - National 35,000.00 28,789.18 Completed 2019-06-03 2019-11-01 2019-06-24 2019-08-07 2019-11-12 2019-09-04 2019-12-02 2019-10-04 2019-12-30 2019-11-08 2020-01-09 2019-12-13 2020-01-14 2020-06-10 2020-01-14 Selection Seminar/Workshop/conferenc Public Safety e TAS - 5 - 7 - 1 / Project Institutional Strengthening Consultant Manager Capacity Building for IBRD / 83560 for Urban Management and Post Qualification Open - National 25,000.00 23,399.52 Completed 2019-12-16 2019-10-30 2020-01-06 2020-02-19 2019-12-31 2020-03-20 2020-02-17 2020-04-24 2020-03-17 2020-10-21 2020-03-17 Entities (KSAMC) Public Safety Selection TA - 8-1 / Technical Support Institutional Strengthening Supervision Consultant - Least Cost IBRD / 83560 for Urban Management and Post Open - National 47,000.00 0.00 Canceled 2018-04-07 2018-06-11 2018-04-28 2018-06-11 2018-06-13 2018-07-09 2018-07-03 2018-08-08 2018-07-18 2018-09-12 2018-10-17 2019-04-15 Fukuoka Landfill Works at the Selection Public Safety dump in Retirement PS - 4 / Delivery of Training Modules in various areas, support for stipends, Training Public Safety Enhancement Least Cost IBRD / 83560 Post Open - National 187,500.00 0.00 Canceled 2019-08-05 2019-08-26 2019-10-09 2019-11-06 2019-12-06 2020-01-10 2020-02-14 2020-08-12 materials, refreshments and and Alternative Livelihoods Selection administration of Grants. Cycle I PS - 8-1 / Enterprise Public Safety Enhancement Least Cost Development (Gap Analysis - IBRD / 83560 Post Open - National 83,077.00 0.00 Canceled 2018-08-31 2018-09-21 2018-11-04 2018-12-02 2019-01-01 2019-02-05 2019-03-12 2019-09-08 and Alternative Livelihoods Selection Consultancy) Institutional Strengthening Consultant TA - 12 / Victimization IBRD / 83560 for Urban Management and Post Qualification Open - National 78,000.00 0.00 Canceled 2018-08-01 2018-08-22 2018-10-05 2018-11-04 2018-12-09 2019-06-07 Survey Public Safety Selection PS - 13-1 / Sports Consultant Public Safety Enhancement Development Consultancy - IBRD / 83560 Post Qualification Open - National 70,000.00 0.00 Canceled 2018-04-15 2018-05-06 2018-06-19 2018-07-19 2018-08-23 2019-02-19 and Alternative Livelihoods Event Coordinator Selection TA - 13 / Consultancy to review and integrate Public Institutional Strengthening Consultant Safety elements in to SDC IBRD / 83560 for Urban Management and Post Qualification Open - National 52,500.00 0.00 Canceled 2018-06-01 2018-06-22 2018-08-05 2018-09-04 2018-10-09 2019-04-07 Profiles AND Assess the Public Safety Selection methodology for effectively keeping profiles current Consultant PS - 13 / Sports Development Public Safety Enhancement IBRD / 83560 Post Qualification Open - National 80,000.00 0.00 Canceled 2018-04-15 2018-05-06 2018-06-19 2018-07-19 2018-08-23 2019-02-19 Consultancy - Soft Skills and Alternative Livelihoods Selection AS - 59 / Design & Supervision Services for Basic Infrastructure and Least Cost Community green spaces - IBRD / 83560 Post Open - National 64,000.00 0.00 Canceled 2016-05-06 2016-05-27 2016-07-10 2016-08-07 2016-09-06 2016-10-11 2016-11-15 2017-05-14 Access to Services Selection landscaping, fencing, lighting, sanitary facilities, signage etc TA - 22 / Consultancy Firm to develop costed metrics for Blue Print to support Urban Institutional Strengthening Quality And Cost- renewal through IBRD / 83560 for Urban Management and Post Open - International 402,150.00 0.00 Canceled 2019-07-29 2019-09-25 2019-08-19 2019-09-25 2019-10-02 2019-11-12 2019-10-30 2019-12-03 2019-11-29 2020-01-03 2020-02-07 2021-02-06 Based Selection research,analysis, Public Safety documentation and communication AS - 20 / Removal & Basic Infrastructure and Least Cost Replacement of Zinc Fences - IBRD / 83560 Post Open - National 155,574.00 0.00 Canceled 2017-03-31 2017-04-21 2017-06-04 2017-07-02 2017-08-01 2017-09-05 2017-10-10 2018-04-08 Access to Services Selection Consultant for Supervision TA - 10 / Consultancy to Institutional Strengthening Consultant assess models for low cost IBRD / 83560 for Urban Management and Post Qualification Open - National 73,000.00 0.00 Canceled 2018-06-01 2018-06-22 2018-08-05 2018-09-04 2018-10-09 2019-04-07 housing in Jamaica (Arch. Eng, Public Safety Selection QS) PS - 8 / Enterprise Consultant Public Safety Enhancement Development (Gap Analysis - IBRD / 83560 Post Qualification Open - National 83,077.00 0.00 Canceled 2018-03-09 2018-03-30 2018-05-13 2018-06-12 2018-07-17 2019-01-13 and Alternative Livelihoods Consultancy) Selection AS - 65 / Design / Consultant Basic Infrastructure and Supervision for Upgrading of IBRD / 83560 Post Qualification Open - National 60,231.00 0.00 Canceled 2017-10-02 2017-10-23 2017-12-06 2018-01-05 2018-02-09 2018-08-08 Access to Services Community Sports Facilities Selection PS - 7 / Group/Firm to support implementation of School Environmental Consultant Programme / Schools gardens Public Safety Enhancement IBRD / 83560 Post Qualification Open - National 56,201.00 0.00 Canceled 2017-08-12 2017-09-02 2017-10-16 2017-11-15 2017-12-20 2018-06-18 as well as community and Alternative Livelihoods Selection development & alternative livelihoods. School competitions etc. PS - 4 - 4 / Contracting Consultant Public Safety Enhancement Service Provider to Deliver IBRD / 83560 Post Qualification Open - National 180,000.00 0.00 Canceled 2020-07-27 2020-08-03 2020-08-24 2020-08-31 2020-09-21 2021-03-20 and Alternative Livelihoods Training re Health Services Selection PS - 4 - 3 / Contracting of service provider - Alternative Public Safety Enhancement Quality And Cost- Livelihood and Skills IBRD / 83560 Post Open - National 142,857.00 0.00 Canceled 2020-08-03 2020-08-17 2020-09-14 2020-09-14 2020-09-28 2020-10-05 2020-10-13 2021-03-12 and Alternative Livelihoods Based Selection Development - Online Based Skills Training INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual JM-JSIF-45414-CS-INDV / Crime Observatory Upgrades Institutional Strengthening Individual - Consultant (Crime Analyst) - IBRD / 83560 for Urban Management and Post Consultant Open 104,285.00 40,963.78 Completed 2018-02-12 2018-12-14 2018-04-02 2018-12-15 2018-04-23 2019-05-31 2018-05-28 2019-06-12 2018-11-24 2019-06-12 Phased contract: approx. 12 Public Safety Selection mths over 2 years PM - 4 / Team Training & Individual Capacity Building (Multiple IBRD / 83560 Project Administration Post Consultant Open 83,720.00 0.00 Canceled 2018-01-12 2018-03-02 2018-03-23 2018-04-27 2018-10-24 contracts) Selection Page 8 TA - 1-7 / Data Management Institutional Strengthening Individual Officers (contracted - Pending IBRD / 83560 for Urban Management and Post Consultant Open 83,720.00 0.00 2017-11-22 2018-01-10 2018-01-31 2018-03-07 2018-09-03 12mths) (possibility of Implementation Public Safety Selection extensions as needed) PS - 6-2 / Social Marketing Campaign Roll Out - Initial 6 Individual Public Safety Enhancement month Engagements of 2 IBRD / 83560 Post Consultant Open 32,558.00 10,268.44 Signed 2017-04-01 2017-02-01 2017-05-20 2017-02-01 2017-06-10 2017-03-06 2017-07-15 2017-03-06 2018-01-11 2017-03-06 and Alternative Livelihoods Graphic artist(s) and 2 Social Selection Media person(s) PS - 6-3-1 / Social Marketing Individual Campaign Roll Out - Initial 6 Public Safety Enhancement IBRD / 83560 Post Consultant Open 27,500.00 24,344.08 Completed 2018-04-01 2018-04-30 2018-05-20 2018-06-04 2018-06-10 2018-07-03 2018-07-15 2018-07-06 2019-01-11 2019-05-13 month Engagements of a and Alternative Livelihoods Selection i.Coordinator PS - 6-7 / Communications Individual Public Safety Enhancement Specialist - Digital Media & IBRD / 83560 Post Consultant Open 61,867.00 22,059.10 Signed 2017-03-05 2017-01-01 2017-04-23 2017-04-10 2017-05-14 2017-04-10 2017-06-18 2017-04-10 2017-12-15 2017-03-06 and Alternative Livelihoods Magazine Publication Selection AS - 67 / Supervision of Zinc Basic Infrastructure and Fence Removal & Replacement IBRD / 83560 Post Direct Selection Direct 145,859.00 12,453.15 Signed 2017-07-10 2017-02-22 2017-07-20 2017-03-06 2017-09-23 2017-04-07 2018-03-22 Access to Services Steer Town AS - 67-1 / Supervision (Direct contract of IIP design Basic Infrastructure and Consultant) of Zinc Fence IBRD / 83560 Post Direct Selection Direct 30,620.00 11,373.38 Completed 2017-07-10 2017-04-19 2017-07-20 2017-05-01 2017-09-23 2017-06-01 2018-03-22 2017-10-02 Access to Services Removal & Replacement (York Town, Maxfield Park, Russia) AS - 67-2 / Supervision (Direct contract of IIP design Basic Infrastructure and Consultant) of Zinc Fence IBRD / 83560 Post Direct Selection Direct 30,620.00 23,919.94 Completed 2017-07-10 2017-02-22 2017-07-20 2017-03-06 2017-09-23 2017-06-06 2018-03-22 2018-10-03 Access to Services Removal & Replacement (Barrett Town,Granville) AS - 67-3 / Supervision (Direct contract of IIP design Consultant) of Zinc Fence Basic Infrastructure and Removal & Replacement IBRD / 83560 Post Direct Selection Direct 45,930.00 20,434.19 Signed 2017-07-10 2017-07-28 2017-07-20 2017-07-28 2017-09-23 2017-10-26 2018-03-22 Access to Services (Hannah Town, Denham Town, Rose Town, Greenwich, Ellerslie etc) PS - 16 / Social worker to support School Wide Positive Individual Behavior Intervention System Public Safety Enhancement IBRD / 83560 Post Consultant Limited 23,076.00 22,032.03 Completed 2019-06-01 2019-04-26 2019-06-06 2019-04-26 2019-06-27 2019-09-18 2019-08-01 2019-09-25 2020-01-28 2019-09-25 (SWPBIS) within the MOE and Alternative Livelihoods Selection Region 1 ICDP secondary schools PS - 26 / Social Marketing Consultant to continue the execution of the campaign to Individual spread the message of good Public Safety Enhancement IBRD / 83560 Post Consultant Open 40,000.00 24,165.33 Completed 2019-06-12 2018-05-03 2019-07-31 2018-06-04 2019-08-21 2018-07-03 2019-09-25 2018-07-06 2020-03-23 2018-07-06 solid waste management and and Alternative Livelihoods Selection awareness and other positive behaviors to community residents. PS - 29 / ICDP Enterprise Development Project - Individual engagement of short term Public Safety Enhancement IBRD / 83560 Post Consultant Open 15,000.00 14,163.75 Completed 2019-06-03 2019-09-17 2019-07-22 2019-09-17 2019-08-12 2019-11-04 2019-09-16 2019-11-11 2020-03-14 2019-11-11 consultant to provide and Alternative Livelihoods Selection business development training to micro enterprise TA - 5-6 / Capacity Building for Entities - KSAMC - Development of Art District Consultancy - (Training and Institutional Strengthening Individual development of the concept IBRD / 83560 for Urban Management and Post Consultant Open 25,000.00 22,613.25 Completed 2019-06-24 2019-10-30 2019-08-12 2019-12-23 2019-09-02 2020-03-04 2019-10-07 2020-03-17 2020-04-04 2020-03-17 of an Art District and facilitate Public Safety Selection the maintenance and re- generation of towns in the KSAMC) TA - 5-7 / Capacity Building for Entities - KSAMC - Development of Art District Consultancy - (Training and Institutional Strengthening Individual development of the concept IBRD / 83560 for Urban Management and Post Consultant Open 25,000.00 24,029.84 Completed 2019-04-15 2019-10-23 2019-06-03 2019-11-13 2019-06-24 2019-11-13 2019-07-29 2020-02-25 2020-01-25 2020-02-25 of an Art District and facilitate Public Safety Selection the maintenance and re- generation of towns in the KSAMC) TA - 18 / Jamaica Crime Institutional Strengthening Individual Observatory Support - GIS IBRD / 83560 for Urban Management and Post Consultant Limited 52,000.00 35,837.21 Completed 2019-06-03 2019-06-22 2019-06-08 2019-08-23 2019-06-29 2019-11-06 2019-08-03 2019-11-07 2020-01-30 2019-11-07 Specialist / Analyst to Public Safety Selection enhance an assess GIS data TA - 19 / Jamaica Crime Observatory Support - Crime Institutional Strengthening Individual Analyst to analyze and IBRD / 83560 for Urban Management and Post Consultant Open 75,000.00 41,147.31 Completed 2019-06-17 2019-03-09 2019-08-05 2019-04-02 2019-08-26 2019-06-03 2019-09-30 2019-06-12 2020-03-28 2019-06-12 recommend based on crime Public Safety Selection trends TA - 20 / Jamaica Crime Observatory Support - Institutional Strengthening Individual Communications Specialist to IBRD / 83560 for Urban Management and Post Consultant Open 45,000.00 20,534.64 Completed 2019-06-18 2019-09-21 2019-08-06 2019-10-18 2019-08-27 2019-11-28 2019-10-01 2019-12-04 2020-03-29 2019-12-04 communicate to various Public Safety Selection stakeholders the data from the Observatory PS - 1-1 / Dispute Resolution Foundation for Mediators (payment for dispute Public Safety Enhancement resolution support, stipend IBRD / 83560 Post Direct Selection Direct 64,666.00 0.00 Canceled 2019-07-31 2019-08-10 2019-10-14 2020-04-11 and Alternative Livelihoods for mediators; Community, School, Work Sites, mediation training) - Phase I Page 9 AS - 75 / Consultant Firm to provide training and Basic Infrastructure and Internship Support for Data IBRD / 83560 Post Direct Selection Direct 100,000.00 91,518.79 Completed 2019-07-28 2019-07-30 2019-08-07 2019-07-30 2019-10-11 2019-08-23 2020-04-08 2019-08-23 Access to Services Collectors and Information Disseminators - ALSD Cycle 3 AS -76 / Firm to provide training and business support Basic Infrastructure and IBRD / 83560 Post Direct Selection Direct 188,000.00 193,294.00 Completed 2019-07-28 2019-07-30 2019-08-07 2019-07-30 2019-10-11 2019-08-23 2020-04-08 2019-08-23 for Utility Wardens (Alternative Access to Services Livelihood Cycle 3) PS - 18 / Youth Education & Recreational Cycle 3 Consultancy Firm to deliver Linda Mood Bell Learning Public Safety Enhancement IBRD / 83560 Post Direct Selection Direct 77,519.00 77,325.91 Completed 2019-06-02 2019-07-30 2019-06-12 2019-07-15 2019-08-16 2019-08-27 2020-02-12 2020-02-27 process. Teachers are trained and Alternative Livelihoods to diagnose and respond to language based learning disabilities. PM - 7 / Consultancy Firm to conduct a participatory final evaluation of the ICDP IBRD / 83560 Project Administration Post Direct Selection Direct 300,000.00 178,255.71 Completed 2019-10-15 2019-08-21 2019-10-25 2019-08-21 2019-12-29 2019-10-17 2020-06-26 2019-10-17 project's results, outcomes to determine if the project objectives have been achieved TA - 6-0-3 / Educational Specialist (Consultant) to Institutional Strengthening Individual Strengthen the capacity of IBRD / 83560 for Urban Management and Post Consultant Limited 12,000.00 14,568.47 Signed 2019-08-10 2020-03-04 2019-08-15 2019-10-23 2019-09-05 2020-04-09 2019-10-10 2020-03-06 2020-04-07 2020-03-06 schools in the ICDP Public Safety Selection communities to enhance literacy and numeracy TA - 6-0-4 / Educational Specialist (Consultant) to Institutional Strengthening Individual Strengthen the capacity of IBRD / 83560 for Urban Management and Post Consultant Limited 12,000.00 42,715.27 Signed 2019-08-10 2019-10-08 2019-08-15 2019-10-23 2019-09-05 2020-02-04 2019-10-10 2020-03-10 2020-04-07 schools in the ICDP Public Safety Selection communities to enhance literacy and numeracy PS - 1-3 / Dispute Resolution Foundation for Mediators Public Safety Enhancement (Community, School, Work IBRD / 83560 Post Direct Selection Direct 75,000.00 0.00 Canceled 2019-08-05 2019-08-15 2019-10-19 2020-04-16 and Alternative Livelihoods Sites, mediation training) Phase II - Practicum/stipends Institutional Strengthening Individual TA - 11 / Development of a IBRD / 83560 for Urban Management and Post Consultant Open 32,500.00 0.00 Canceled 2018-06-01 2018-07-20 2018-08-10 2018-09-14 2019-03-13 Safe Schools Guide Public Safety Selection PS - 5-3 / Training of CBOs Individual Public Safety Enhancement and Capacity Building - IBRD / 83560 Post Consultant Open 17,200.00 0.00 Canceled 2018-02-01 2018-03-22 2018-04-12 2018-05-17 2018-11-13 and Alternative Livelihoods Consultant to develop Manual Selection PS - 2-7 / Consultant to Individual Public Safety Enhancement provide Camp Safety Training IBRD / 83560 Post Consultant Limited 5,625.00 0.00 Canceled 2017-06-01 2017-06-06 2017-06-27 2017-08-01 2018-01-28 and Alternative Livelihoods Manual Selection TA - 6-1-1 / Financial Analyst to support DCFS's Institutional Strengthening Individual capacity to review and audit IBRD / 83560 for Urban Management and Post Consultant Limited 10,000.00 0.00 Canceled 2019-06-03 2019-06-08 2019-06-29 2019-08-03 2020-01-30 the financials of community Public Safety Selection groups for compliance TA - 14 / Review of the Statistics on Unattached Institutional Strengthening Individual Youths (numbers and IBRD / 83560 for Urban Management and Post Consultant Open 32,570.00 0.00 Canceled 2018-06-01 2018-07-20 2018-08-10 2018-09-14 2019-03-13 methodology) - input to Public Safety Selection stemming the "flow" AS - 67-4 / Canaan Heights Basic Infrastructure and Under Zinc Fence Substitution IBRD / 83560 Post Direct Selection Direct 6,000.00 0.00 2020-01-27 2020-02-10 2020-02-06 2020-02-27 2020-03-28 Access to Services Implementation Supervision Consultancy PS - 2-3-13 / YER 2018 Individual Public Safety Enhancement Consultancy for Use of IBRD / 83560 Post Consultant Open 2,604.00 0.00 Canceled 2018-10-05 2018-11-23 2018-12-14 2019-01-18 2019-07-17 and Alternative Livelihoods Teaching Aides Selection PS - 2-3-3 / GSAT Clinics & Individual Public Safety Enhancement Transition Seminars 2018 IBRD / 83560 Post Consultant Open 70,000.00 0.00 Canceled 2018-03-15 2018-05-03 2018-05-24 2018-06-28 2018-12-25 and Alternative Livelihoods (Manual - Consultancy Selection TA - 6-0 / Educational Specialist to strengthen the Institutional Strengthening Individual capacity of schools to IBRD / 83560 for Urban Management and Post Consultant Limited 12,000.00 0.00 Canceled 2019-08-12 2019-08-17 2019-09-07 2019-10-12 2020-04-09 enhance literacy and Public Safety Selection numeracy AS - 73 / Supervision services related to the execution of (plumbing & Basic Infrastructure and IBRD / 83560 Post Direct Selection Direct 20,000.00 0.00 Canceled 2019-05-17 2019-05-27 2019-07-31 2020-01-27 mechanical) works to lift Access to Services water to High Rise Buildings - Wilton Gardens AS - 74 / Supervision services related to the execution of (plumbing & Basic Infrastructure and IBRD / 83560 Post Direct Selection Direct 20,000.00 0.00 Canceled 2019-05-17 2019-05-27 2019-07-31 2020-01-27 mechanical) works to lift Access to Services water to High Rise Buildings - Hannah Town TA - 6-0-1 / Educational Specialist (Consultant) to Institutional Strengthening Individual Strengthen the capacity of IBRD / 83560 for Urban Management and Post Consultant Limited 12,000.00 0.00 Canceled 2019-08-10 2019-08-15 2019-09-05 2019-10-10 2020-04-07 schools in the ICDP Public Safety Selection communities to enhance literacy and numeracy Page 10 TA - 6-0-2 / Educational Specialist (Consultant) to Institutional Strengthening Individual Strengthen the capacity of IBRD / 83560 for Urban Management and Post Consultant Limited 12,000.00 0.00 Canceled 2019-08-10 2019-08-15 2019-09-05 2019-10-10 2020-04-07 schools in the ICDP Public Safety Selection communities to enhance literacy and numeracy PS - 1-5 / Community Safety Individual Public Safety Enhancement Project - Consultancy for IBRD / 83560 Post Consultant Open 35,125.00 0.00 Canceled 2018-04-15 2018-06-03 2018-06-24 2018-07-29 2019-01-25 and Alternative Livelihoods Manual update Selection Individual PS - 11 / Safe Passages (Soft Public Safety Enhancement IBRD / 83560 Post Consultant Open 13,076.00 0.00 Canceled 2018-02-12 2018-04-02 2018-04-23 2018-05-28 2018-11-24 Activities) - Consultancy and Alternative Livelihoods Selection TA - 6-1-2 / Financial Analyst to support DCFS's Institutional Strengthening Individual capacity to review and audit IBRD / 83560 for Urban Management and Post Consultant Limited 10,000.00 0.00 Canceled 2019-06-03 2019-06-08 2019-06-29 2019-08-03 2020-01-30 the financials of community Public Safety Selection groups for compliance TA - 6-1 / Financial Analyst to support DCFS's capacity to Institutional Strengthening Individual review and audit the financials IBRD / 83560 for Urban Management and Post Consultant Limited 10,000.00 0.00 Canceled 2019-06-03 2020-02-21 2019-06-08 2020-03-12 2019-06-29 2019-08-03 2020-01-30 of community groups for Public Safety Selection compliance TA - 6-1-1R / Financial Analyst to support DCFS's Institutional Strengthening Individual capacity to review and audit IBRD / 83560 for Urban Management and Post Consultant Limited 10,000.00 0.00 Canceled 2020-02-11 2020-02-16 2020-03-08 2020-04-12 2020-04-26 the financials of community Public Safety Selection groups for compliance Individual PS - 2-3-9 / YER 2018 GSAT Public Safety Enhancement IBRD / 83560 Post Consultant Open 25,000.00 0.00 Canceled 2018-10-01 2018-04-13 2018-11-19 2018-12-10 2019-01-14 2019-07-13 Consultancy and Alternative Livelihoods Selection TA - 6-1-1R-2 / Institutional Strengthening Individual Procurement of Financial IBRD / 83560 for Urban Management and Post Consultant Limited 10,000.00 0.00 Canceled 2020-07-27 2020-08-01 2020-08-22 2020-10-10 2021-01-11 Analyst Public Safety Selection Institutional Strengthening Individual TA - 6 - 1R / Procurement of IBRD / 83560 for Urban Management and Post Consultant Limited 10,000.00 0.00 Canceled 2020-07-27 2020-08-01 2020-08-22 2020-10-10 2021-01-08 Financial Analyst Public Safety Selection TA - 6 - 1 - 2R / Institutional Strengthening Individual Procurement of Financial IBRD / 83560 for Urban Management and Post Consultant Limited 10,000.00 0.00 Canceled 2020-07-27 2020-08-01 2020-08-22 2020-10-10 2021-01-11 Analyst Public Safety Selection AS -76-1 / Contacting of Basic Infrastructure and Under Supervision services - ICDP IBRD / 83560 Post Direct Selection Direct 110,000.00 0.00 2020-08-03 2020-09-23 2020-08-13 2020-09-23 2020-09-26 2021-03-25 Access to Services Implementation Utility Warden TA - 21 / Data management Officers - Data Entry Clerk to be employed to input data in the Jamaica Crime Institutional Strengthening Individual Observatory - Integrated Pending IBRD / 83560 for Urban Management and Post Consultant Limited 86,000.00 0.00 2020-09-07 2020-09-12 2020-10-03 2020-11-07 2021-05-06 Crime and Violence Implementation Public Safety Selection Information system and assist with the coding of crime reports in preparation for crime analysis and reporting. TA - 25 / Direct Contracting Institutional Strengthening of Development Options Pending IBRD / 83560 for Urban Management and Post Direct Selection Direct 56,000.00 0.00 2020-12-27 2021-01-15 2021-02-12 2021-03-29 Limited regarding Urban Implementation Public Safety Renewal Strategy Page 11