The World Bank                                                                                     Implementation Status & Results Report
            Cote d'Ivoire: Education Service Delivery Enhancement Project (P163218)



Cote d'Ivoire: Education Service Delivery Enhancement Project (P163218)


 AFRICA | Cote d'Ivoire | Education Global Practice |
 Recipient Executed Activities | Investment Project Financing | FY 2018 | Seq No: 4 | ARCHIVED on 30-Jun-2020 | ISR42486 |


 Implementing Agencies: Ministry of Economy and Finance, Ministry of National Education and Technical and Vocational Education and Training



 Key Dates


  Key Project Dates

   Bank Approval Date: 04-Jun-2018                                              Effectiveness Date: 31-Jul-2018
   Planned Mid Term Review Date: 28-Sep-2020                                    Actual Mid-Term Review Date:
   Original Closing Date: 28-Jul-2022                                           Revised Closing Date: 28-Jul-2022
 pdoTable

 Project Development Objectives

  Project Development Objective (from Project Appraisal Document)
  The Project Development Objective is to increase access to pre-school and improve learning outcomes in beneficiary primary schools in
  participating regions

  Has the Project Development Objective been changed since Board Approval of the Project Objective?
  No


 Components Table

 Name
 Improving Conditions for Improved Learning Outcomes:(Cost $13.19 M)
 Strenghtening Sector Management and Accountability:(Cost $2.85 M)
 Improving Teaching and Learning Environment for Beneficiary Schools:(Cost $2.69 M)
 Project Implementation and Monitoring and Evaluation:(Cost $4.62 M)

 Overall Ratings

 Name                                                                         Previous Rating                           Current Rating

 Progress towards achievement of PDO                                          Moderately Satisfactory                  Moderately Satisfactory
 Overall Implementation Progress (IP)                                         Moderately Satisfactory                  Moderately Satisfactory
 Overall Risk Rating                                                          Substantial                              Moderate


 Implementation Status and Key Decisions

  Overview. The Cote d'Ivoire Education Service Delivery Enhancement Project (ESDEP) was approved on June 4, 2018. The Grant Agreement was
  signed on June 21, 2018, and the Project became effective on July 31, 2018. The Project has achieved key activities as detailed below before the
  school closure. The Project developed distance learning programs to ensure pedagogical continuity during the crisis. With school reopening, the
  Project is providing support to prevent and protect beneficiary schools from COVID-19 contamination.
  The Additional Financing (AF) has been submitted for approval to the Regional Vice President (Africa Region). The AF will: (i) scale up the
  coverage of project interventions, through an increase in the number of beneficiaries beyond those supported under the original project; (ii) finance
  previously identified activities that could not be adopted under original financing due to budget constraints; and (iii) respond to the COVID-19 crisis
  through the provision of distance learning and training programs and preparation of school reopening. The Project’s closing date is expected to be
  extended to December 31, 2023 in order to ensure that all activities—those included in the parent project as well as the AF—are fully implemented.


6/30/2020                                                                                                                       Page 1 of 9
            The World Bank                                                                                       Implementation Status & Results Report
            Cote d'Ivoire: Education Service Delivery Enhancement Project (P163218)



  The Project Development Objectives (PDO)--increased access to preschool and improve learning outcomes in beneficiary primary schools in
  participating regions (Bagoue, Bere, Bounkani, Kabadougou, Poro, and Tchologo), as well as the implementation arrangements, will remain the
  same as in the original project.
  Progress by components/Sub-components:
  Component 1: Improving Conditions for Improved Learning Outcomes.
  Sub-component 1.1: Improving Community Pre-schools and Pre-primary schools in participating Regions: The construction of 117
  Community Pre-school Centers (CPCs) has been completed and validated (114 at the end of December 2019, and 3 in February 2020). One
  hundred and ten (110) CPCs have opened during the 2019/2020 school year, and 7 new ones will open in September/October 2020. Educators and
  assistants are recruited for all the centers. The final training sessions are scheduled for August 2020 for: (i) staff from the 7 new CPCs (i.e., 14 pre-
  school educators and 14 assistants); and (ii) staff from the first 110 CPCs. Furniture and supplies have been delivered to all the centers. Only the
  ECD kits ordered and received by UNICEF will be delivered before the next school year. The administration of deworming is already effective in 186
  schools (CPC and primary schools) but has been discontinued due to COVID-19. A training module specific to parenting is being developed by
  UNICEF in coordination with the Ministry and in line with National Manual.
  Following the outbreak of COVID-19, the Government announced the end of the school year for the pre-school level. The project teams were
  already preparing for the start of the school year by ensuring the reinforcement of health guidelines. Thus, handwashing image boxes are already
  available in all preschool schools, children and their parents will be made aware as soon as classes resume. The Project Management Unit (PMU)
  worked with the Directorates of Schools, High Schools and Colleges (DELC) to prepare support for the public Pre-primary as part of the Additional
  Financing. The World Bank Implementation Support Mission of May 26-28, 2020 recommended: (i) collecting information on the impact of COVID-
  19 in the project's localities (CPC operations, household poverty, school dropouts, cognitive skills); (ii) defining, as quickly as possible, the quality
  standards of CPCs; and (iii) developing the strategy for the sustainability of the project's achievements and in particular the management of the
  various costs of CPCs after the project.
  Sub-component 1.2: Improved teaching and learning of reading and mathematics in beneficiary schools: The continuation of the Project's
  learning improvement activities was halted with the closure of classes as a result of COVID-19 pandemic. Thus, to continue the implementation of
  planned project activities, the Directorate of Education and Continuing Training (DPFC) has been mobilized for the development of distance courses
  (via radio/video/internet, pods/tablets). As at May 26-28, 2020, the production rate of the tablets was 100% (in reading), but these sheets have yet
  to be validated. With the announcement of the reopening of schools, it was decided to give priority to in-class activities and to focus on the
  resumption of teaching and preparation for the 2020/2021 school year. The ministry team will continue the production of the tablets and the planned
  distribution, for further introduction of distance learning programs as complementary to in-class activities.
  Regarding the monitoring of teachers, the first in-class observations were made in part before the schools closed. All Primary and Preschool
  Educational Advisors (CPPP) were equipped with tablets and trained to evaluate changes in class practice, but the dynamics started were halted by
  COVID-19 crisis. The apprenticeship evaluation (EGRA/EGMA), originally scheduled for May 2020, has been postponed until the start of 2020/2021
  school year. The May 26-28, 2020 World Bank Implementation Support Mission recommended: (i) assigning CP1 teachers of 2019/2020 to CP2
  classes in 2020/2021 to continue the learning started with students they know well, thus limit the potential negative impacts of the crisis on students'
  skills; (ii) thinking about new methods of teacher/training (particularly remotely), to be ready in the event of another crisis; (iii) studying the
  integration of new first-learning tools in national curricula; and (iv) collecting information on the impact of COVID-19 following the resumption of
  classes in the project schools.
  Component 2: Strengthening Management and Accountability in the Education Sector
  Sub-component 2.1: Citizen participation in school management: The dashboard (le tableau de bord) was delivered by the consultant with
  delays. The capacity of the inter-mediators on the exploitation of the tool has been strengthened, and 144 (out of 150) localities are now preparing
  for the practical organization (after COVID-19 crisis) of a citizen dialogue around its application. The central level, including the Directorate of
  Strategies, Planning and Statistics (DSPS) will be involved in data collection and processing to increase information sharing in a bottom-up rather
  than top-down approach. The May 2020 Mission recommended extending skills/capacity building to the remaining 6 locations as soon as possible
  for effective and widespread application of the tool.
  Sub-component 2.2: Results-Based Financing (School grants): The 150 schools received their grants to enable them to implement their action
  plans. Activity reports were being written and with the school reopening they would be available before the end of the extended school year (July
  30, 2020). Since the results of the tests (Apprenticeship Evaluation--EGRA and EGMA) were not available to assess performance, it was decided to
  allocate the same grant amount per school for the 2020/2021 school year.
  Sub-component 2.3: Building Capacity in Public Education Policies and Service Delivery: The Ministry's Task Force has produced a policy
  note (2019) to care for children living with disabilities in schools in Côte d'Ivoire. This note has been submitted to the MENETFP office for approval
  and publication. The Education-Training sector's Response Plan to COVID-19 is the first Education Policy Note in 2020. It was discussed between
  the government and its partners prior to its adoption and publication by the Ministry on May 15, 2020. The third Policy Note will focus on teachers
  (Terms of Reference being developed). The joint Education-Training sector review, originally scheduled for May 18-20, 2020, was postponed to a
  later date, due to the COVID-19 pandemic. The Mission recommended that: (i) the Policy Notes be widely disseminated and communicated to
  foster dialogue among all stakeholders to assist in effective decision-making; (ii) the institutionalized Task Force has substantial means to enable it
  to fully assume its role; and (iii) a new date for joint review of the Education-Training sector be identified quickly.
  Component 3: Improving teaching and learning environment in beneficiary schools
  Infrastructure work for primary schools, which was expected to lead to improved teaching and learning conditions, and to achieve the objectives set,
  continued in 92 schools benefiting from the project--this was considered a priority in view of their plight.
  Component 4: Project Implementation and Monitoring and Evaluation
  Sub-component 4.1: Project implementation: Monthly project follow-up reports are available on time. The Project Management Unit (PMU) has
  been strengthened with the recruitment of the social development (safeguard) specialist. It was observed the communication activities that helped to
  publicize the project are ongoing (i.e., website www.papse.ci Facebook page, newsletters, press articles, broadcast on the TV channel RTI 1,
  campaign to raise awareness of schooling via 7 local radio stations). The Mission recommended using all these channels of communication to
  further highlight the elements of the project including the determinants of the quality of teaching, the place and value of the teachers in the project,


6/30/2020                                                                                                                        Page 2 of 9
            The World Bank                                                                                     Implementation Status & Results Report
            Cote d'Ivoire: Education Service Delivery Enhancement Project (P163218)



  the quality and availability of dynamic and trained teaching tools and coaching teams, the essential role of parents of students and communities to
  support teachers' efforts and student achievements.
  Sub-component 4.2: Monitoring and Evaluation: Technical and financial offers from several firms, for the beneficiaries' satisfaction survey, are
  being analyzed within the Project Management Unit (PMU). The survey is expected to take place in early July 2020 and the final report would be
  delivered early September to inform the Mid Term Review. The survey of the communities that will benefit from the Additional Financing has been
  completed, and the list of sites, for conducting the comparative assessment, is available.




  Risks


 Systematic Operations Risk-rating Tool


  Risk Category                                              Rating at Approval              Previous Rating               Current Rating

  Political and Governance                                   Substantial                    Substantial                  Substantial
  Macroeconomic                                              Substantial                    Substantial                  Moderate
  Sector Strategies and Policies                             Moderate                       Substantial                  Moderate
  Technical Design of Project or Program                     Substantial                    Substantial                  Moderate
  Institutional Capacity for Implementation and
                                                             Substantial                    Substantial                  Moderate
  Sustainability
  Fiduciary                                                  Substantial                    Substantial                  Substantial
  Environment and Social                                     Moderate                       Moderate                     Moderate
  Stakeholders                                               Substantial                    Substantial                  Moderate
  Other                                                      --                              Substantial                  --
  Overall                                                    Substantial                    Substantial                  Moderate



  Results


 PDO Indicators by Objectives / Outcomes



   Increase access to preschool

    IN00863141
    ►Number of community preschools meeting quality standards (Number, Custom)

                                       Baseline                    Actual (Previous)            Actual (Current)           End Target

    Value                              0.00                        0.00                         0.00                       90.00

    Date                               01-Mar-2018                 03-Dec-2019                  23-Jun-2020               30-Sep-2022
                                        The community preschools opened in October 2019. Due to the COVID19 crisis the process for the
   Comments:                            development oft the standards is delayed. The indicator will be measured by the January 2021.




6/30/2020                                                                                                                       Page 3 of 9
            The World Bank                                                                                     Implementation Status & Results Report
            Cote d'Ivoire: Education Service Delivery Enhancement Project (P163218)




   Improve learning outcomes in beneficiary schools

   IN00863110
   ►Pupils in second grade of primary education with intermediate or high level score in mathematics, in beneficiary schools in poor and lagging
   communities (Percentage, Custom)

                                       Baseline                     Actual (Previous)            Actual (Current)          End Target

    Value                              24.00                       15.00                         15.00                     32.00

    Date                               01-Mar-2018                 03-Dec-2019                   23-Jun-2020               28-Jul-2022
                                        The actual value (15%) is from the EGMA test carried out in the beneficiary primary schools to establish
                                        the baseline value. As expected for the beneficiary primary schools the baseline value it is much lower
                                        than the baseline value at national level (24%) because the project is focusing on lagging regions.
   Comments:
                                        The EGMA test could not be implemented as planned in April-May 2020 because of school closure. The
                                        indicator will be updated by January 2021.

     IN00863142
     Of which girls, in second grade of primary education with intermediate or high level score in mathematics, in beneficiary schools in poor
     and lagging communities (Percentage, Custom Breakdown)

                                      Baseline                    Actual (Previous)            Actual (Current)            End Target

     Value                           47.00                        47.00                        47.00                       50.00

     Date                            01-Mar-2018                  03-Dec-2019                  23-Jun-2020                28-Jul-2022

    IN00863143
    ►Teachers recruited or trained (Number, Corporate)

                                       Baseline                     Actual (Previous)            Actual (Current)          End Target

    Value                              0.00                        890.00                        890.00                    1,350.00

    Date                               16-Apr-2018                 03-Dec-2019                   23-Jun-2020               28-Jul-2022
                                        This is the sum of the primary teacher trained (450) and the number of preschool teacher trained and
   Comments:                            recruited (440)

     IN00863144
     Number of teachers recruited (Number, Corporate Breakdown)

                                      Baseline                    Actual (Previous)            Actual (Current)            End Target

     Value                           0.00                         440.00                       440.00                      450.00

     Date                            16-Apr-2018                  03-Dec-2019                  23-Jun-2020                28-Jul-2022

     IN00863145
     Number of teachers trained (Number, Corporate Breakdown)

                                      Baseline                    Actual (Previous)            Actual (Current)            End Target

     Value                           0.00                         890.00                       890.00                      1,350.00

     Date                            16-Apr-2018                  03-Dec-2019                  23-Jun-2020                28-Jul-2022

     IN00863146
     Teachers recruited or trained - Female (RMS requirement) (Number, Corporate Supplement)

                                      Baseline                    Actual (Previous)            Actual (Current)            End Target

6/30/2020                                                                                                                     Page 4 of 9
            The World Bank                                                                                     Implementation Status & Results Report
            Cote d'Ivoire: Education Service Delivery Enhancement Project (P163218)




     Value                           0.00                         315.00                       315.00                      675.00

    IN00863147
    ►Students benefiting from direct interventions to enhance learning (Number, Corporate)

                                       Baseline                     Actual (Previous)            Actual (Current)          End Target

    Value                              0.00                         18,000.00                    18,000.00                 144,000.00

    Date                               16-Apr-2018                  03-Dec-2019                  23-Jun-2020               28-Jul-2022

                                        This is the sum of students in CP1, CP2 and CE1 in the 150 beneficiary school.
   Comments:

   IN00863148
   ►Pupils in second grade of primary education with intermediate or high level score in reading, in beneficiary primary schools in poor and
   lagging communities (Percentage, Custom)

                                       Baseline                     Actual (Previous)            Actual (Current)          End Target

    Value                              6.00                         1.00                         1.00                      15.00

    Date                               01-Mar-2018                  03-Dec-2019                  23-Jun-2020               28-Jul-2022
                                        The actual value (1%) is from the EGRA test carried out in the beneficiary primary schools to establish the
                                        baseline value. As expected the baseline value for the beneficiary schools is much lower than the baseline
                                        value (6%) at national level because the project is focusing on lagging regions.
   Comments:
                                        The EGRA test could not be implemented as planned in April-May 2020 because of school closure. The
                                        indicator will be updated by January 2021.

     IN00863149
     Of which girls, in second grade of primary education with intermediate or high level score in reading, in beneficiary primary schools in
     poor and lagging communities (Percentage, Custom Breakdown)

                                      Baseline                    Actual (Previous)             Actual (Current)           End Target

     Value                           47.00                        47.00                        47.00                       50.00

     Date                            01-Mar-2018                  03-Dec-2019                  23-Jun-2020                 28-Jul-2022

    IN00863150
    ►Teachers implementing at least three of the new teaching practices developed in the project, in beneficiary schools (Percentage, Custom)

                                       Baseline                     Actual (Previous)            Actual (Current)          End Target

    Value                              0.00                         0.00                         0.00                      80.00

    Date                               01-Mar-2018                  03-Dec-2019                  23-Jun-2020               28-Jul-2022
                                        Class observations could not be carried out because of school closure. This indicator will be measured
   Comments:                            and updated by January 2021.

     IN00863151
     Of which female, implementing at least three of the new teaching practices developed in the project, in beneficiary schools (Percentage,
     Custom Breakdown)

                                      Baseline                    Actual (Previous)             Actual (Current)           End Target

     Value                           0.00                         0.00                         0.00                        50.00

     Date                            01-Mar-2018                  03-Dec-2019                  23-Jun-2020                 28-Jul-2022


6/30/2020                                                                                                                      Page 5 of 9
            The World Bank                                                                                    Implementation Status & Results Report
            Cote d'Ivoire: Education Service Delivery Enhancement Project (P163218)




 Overall Comments PDO

  Information about three indicators are not available due to school closure. Information on (i) on students' score in reading and mathematics and
  (ii) teachers implementing on new teaching practices would be available after at leats three months of the beginning of the 2020/2021 school
  year. This will allow the project to implement the EGRA and EGMA tests and the class observations for all trained teachers.




 Intermediate Results Indicators by Components



   Improving Conditions for Improved Learning Outcomes

    IN00863153
    ►Number of children enrolled in community preschools built under the project (Number, Custom)

                                       Baseline                     Actual (Previous)            Actual (Current)         End Target

    Value                              0.00                        2,160.00                     6,792.00                  10,320.00

    Date                               01-Mar-2018                 03-Dec-2019                  23-Jun-2020               28-Jul-2022

     IN00863158
     Of which girls (Number, Custom Breakdown)

                                      Baseline                    Actual (Previous)            Actual (Current)           End Target

     Value                           0.00                         1,080.00                     3,427.00                   5,160.00

     Date                            01-Mar-2018                  03-Dec-2019                  23-Jun-2020                28-Jul-2022

   IN00863159
   ►Teachers receiving at least one supervision visit by inspectors or pedagogic advisers in beneficiary schools, per quarter (Percentage,
   Custom)

                                       Baseline                     Actual (Previous)            Actual (Current)         End Target

    Value                              0.00                        0.00                         0.00                      90.00

    Date                               01-Mar-2018                 03-Dec-2019                  23-Jun-2020               28-Jul-2022
                                        School visits could no be carried out because of school closure. This indicator will be measured and
   Comments:                            updated by January 2021.

    IN00863161
    ►Number of community preschools built by the project (Number, Custom)

                                       Baseline                     Actual (Previous)            Actual (Current)         End Target

    Value                              0.00                        86.00                        117.00                    117.00

    Date                               01-Mar-2018                 03-Dec-2019                  23-Jun-2020               28-Jul-2022

    IN00863162
    ►Number of teachers trained in beneficiary schools, based on classroom observations' results (Number, Custom)

                                       Baseline                     Actual (Previous)            Actual (Current)         End Target



6/30/2020                                                                                                                     Page 6 of 9
            The World Bank                                                                                       Implementation Status & Results Report
            Cote d'Ivoire: Education Service Delivery Enhancement Project (P163218)




    Value                              0.00                         0.00                           0.00                      900.00

    Date                               01-Mar-2018                  03-Dec-2019                    23-Jun-2020              28-Jul-2022
                                        Class observations could not be carried out because of school closure. This indicator will be updated by
   Comments:                            January 2021.

     IN00863163
     Of which female (Number, Custom Breakdown)

                                      Baseline                    Actual (Previous)               Actual (Current)          End Target

     Value                           0.00                         0.00                            0.00                      450.00

     Date                            01-Mar-2018                  03-Dec-2019                     23-Jun-2020               28-Jul-2022


   Strengthening Education Sector Management and Accountability

   IN00863154
   ►Public schools reporting school grants and student results through community briefings meetings, at least once a year, in beneficiary
   schools (Percentage, Custom)

                                       Baseline                     Actual (Previous)              Actual (Current)          End Target

    Value                              0.00                         100.00                         100.00                    90.00

    Date                               01-Mar-2018                  03-Dec-2019                    23-Jun-2020              28-Jul-2022
                                        All beneficiary schools reported on the provision of school grants. However, the EGRA and EGMA test
   Comments:                            could not be implemented, therefore student results will be available by January 2021.



   Improving Teaching and Learning Environment for Beneficiary Schools

    IN00863155
    ►Number of girls receiving complementary school kits (Number, Custom)

                                       Baseline                     Actual (Previous)              Actual (Current)          End Target

    Value                              0.00                         8,400.00                       8,921.00                  2,500.00

    Date                               01-Mar-2018                  03-Dec-2019                    23-Jun-2020              28-Jul-2022
                                        The number of girls in the beneficiary schools in much higher than the estimated number at project
                                        preparation. The assumption that girl’s enrollment in these remote areas would be very low was not borne
   Comments:
                                        out by the collected data.

    IN00863157
    ►Number of beneficiaries benefiting from Deworming (Number, Custom)

                                       Baseline                     Actual (Previous)              Actual (Current)          End Target

    Value                              0.00                         0.00                           42,080.00                 240,000.00

    Date                               01-Mar-2018                  03-Dec-2019                    23-Jun-2020              28-Jul-2022

                                        Distribution was interrupted because of school closure.
   Comments:

     IN00863160

6/30/2020                                                                                                                       Page 7 of 9
            The World Bank                                                                                        Implementation Status & Results Report
            Cote d'Ivoire: Education Service Delivery Enhancement Project (P163218)




     Of Which girls (Number, Custom Breakdown)

                                      Baseline                     Actual (Previous)            Actual (Current)             End Target

     Value                            0.00                         0.00                         22,000.00                    120,000.00

     Date                             01-Mar-2018                  09-Oct-2018                  23-Jun-2020                  28-Jul-2022


   Project Implementation and Monitoring and Evaluation

    IN00863152
    ►Number of policy notes published by the MENETFP (Number, Custom)

                                        Baseline                    Actual (Previous)               Actual (Current)          End Target

    Value                              0.00                         0.00                            1.00                      8.00

    Date                               01-Mar-2018                  03-Dec-2019                     23-Jun-2020              28-Jul-2022

                                        A second policy note is in the validation process.
   Comments:

    IN00863156
    ►Impact Evaluation report published by the MENETFP (Yes/No, Custom)

                                        Baseline                    Actual (Previous)               Actual (Current)          End Target

    Value                              No                           No                              No                        Yes

    Date                               01-Mar-2018                  03-Dec-2019                     23-Jun-2020              28-Jul-2022

                                        A first report is expected by the MTR, scheduled for December 2020.
   Comments:


 Overall Comments IR

  Information about three indicators are not available or lagging due to school closure. Information on (i) teachers receiving inspector
  visits, (ii) on teachers trained based on classroom observations, and (iii) beneficiaries benefiting from deworming would be provided or
  completed during the course of the 2020/2021 school year. This will allow the project to implement the classroom observations, the inspectors'
  visits and the completion of the deworming activities.




 Performance-Based Conditions



 Data on Financial Performance


 Disbursements (by loan)

 Project        Loan/Credit/TF     Status      Currency       Original     Revised      Cancelled        Disbursed     Undisbursed             % Disbursed


 P163218        TF-A7376           Effective   USD              23.35        23.35           0.00           13.48             9.87                    58%


 Key Dates (by loan)


6/30/2020                                                                                                                        Page 8 of 9
            The World Bank                                                                               Implementation Status & Results Report
            Cote d'Ivoire: Education Service Delivery Enhancement Project (P163218)




 Project         Loan/Credit/TF    Status      Approval Date     Signing Date    Effectiveness Date   Orig. Closing Date      Rev. Closing Date

 P163218         TF-A7376          Effective   04-Jun-2018       21-Jun-2018     31-Jul-2018          28-Jul-2022             28-Jul-2022


Cumulative Disbursements




 PBC Disbursement

                                                                                      Achievement     Disbursed amount in        Disbursement %
 PBC ID                     PBC Type     Description           Coc      PBC Amount
                                                                                      Status          Coc                        for PBC




  Restructuring History


  There has been no restructuring to date.


  Related Project(s)


 P169479-Cote d' Ivoire Education Services Delivery Enhancement Project Additional Financing




6/30/2020                                                                                                                  Page 9 of 9