The World Bank                                                                                      Implementation Status & Results Report
           Burundi Landscape Restoration and Resilience Project (P160613)



Burundi Landscape Restoration and Resilience Project (P160613)


 AFRICA EAST | Burundi | Environment, Natural Resources & the Blue Economy Global Practice |
 IBRD/IDA | Investment Project Financing | FY 2018 | Seq No: 7 | ARCHIVED on 05-Mar-2021 | ISR45499 |


 Implementing Agencies: Ministry of Finance, Budget, Cooperation and Economic Development, Ministry of Environment, Agriculture and Livestock



 Key Dates


  Key Project Dates

   Bank Approval Date: 11-Apr-2018                                             Effectiveness Date: 21-Sep-2018
   Planned Mid Term Review Date: 30-Jul-2021                                   Actual Mid-Term Review Date:
   Original Closing Date: 14-Mar-2023                                          Revised Closing Date: 14-Mar-2023
 pdoTable

 Project Development Objectives

  Project Development Objective (from Project Appraisal Document)
  The Project Development Objective is to restore land productivity in targeted degraded landscapes and, in the event of an eligible crisis or
  emergency, to provide immediate and effective response to said eligible crisis or emergency.

  Has the Project Development Objective been changed since Board Approval of the Project Objective?
  No


 Components Table

 Name
 Institutional Development and Capacity Building for Landscape Restoration and Resilience:(Cost $2.00 M)
 Sustainable Landscape Management Practices:(Cost $22.00 M)
 Improved Management of Protected Areas and Reserves:(Cost $3.00 M)
 Contingency Emergency Response (CERC)
 Project Management, Coordination, and Monitoring:(Cost $3.00 M)

 Overall Ratings

 Name                                                                        Previous Rating                           Current Rating

 Progress towards achievement of PDO                                         Moderately Satisfactory                  Moderately Satisfactory
 Overall Implementation Progress (IP)                                        Moderately Satisfactory                  Moderately Satisfactory
 Overall Risk Rating                                                         Substantial                              Substantial


 Implementation Status and Key Decisions

  The project is on course to delivery, with few results achieved to date, owed to the delayed initiation of field activities which only started in Nov
  2020. Feasibility studies in the first set of 12 collines are now underway and will determine the mapping of target project areas, types and extent of
  terracing, erosion control and landscape restoration work necessary, and the zoning of activities to be conducted on each colline landscape by other
  project contractors focused on community resilience activities (land certification, community mobilization, and farmer field schools), to
  be underpinned by colline-level action plans validated by target community beneficiaries.
  Related to the implementation of the three main components of this project, the following activities were realized during the reporting period.
  Under component 1:



3/5/2021                                                                                                                       Page 1 of 7
           The World Bank                                                                                         Implementation Status & Results Report
           Burundi Landscape Restoration and Resilience Project (P160613)



  A five-day training was organized by the University of Burundi with the University of Florence for technical support in landscape restoration targeting
  project staff and technical staff within MINEAGRIE. However, the University of Florence did not carry out a mission in Burundi due to the Covid-19
  pandemic (now planned in March 2021), restructuring their planning of activities to start with remote training in September 2020.
  Under component 2:
  Under the largest project component #2 dedicated to landscape restoration works implemented on a target of 22 hills (collines), technical feasibility
  studies on 12 hills are underway (led by SHER). In addition, all key contracts for service providers, selected on a competitive basis, to support the
  various critical contracts for the start of restoration activities planned on the first set of 12 hills have now been finalized, including contracts
  for community mobilization (ONG ACORD), land certification (implemented by IGNIFI), as well as contracts with FAO (support for the training of
  farmer field schools) and Bioversity International (supply of plant genetics and support to community nurseries), have now also been signed and
  completed, with invoices already submitted by all contractors. Some other contracts have been launched by the PIU during this reporting period
  (acquisition of cattle for the production of organic manure for radical terraces) but were recalled to ensure seamless sequencing of project activities.
  By November 2020, main project activities were initiated in a coordinated and synchronous way on the ground (community mobilization, technical
  feasibility studies, restoration works including Bioversity contract and FAO farmer field schools, land certification) with safeguards, GRM and M&E
  frameworks operational and deployed in the field.
  Specific results to report are below:
            Feasibility studies are currently underway on the first set of 12 hills. The contracted technical firm, SHER, has shared an inception report
             in early January outlining their methods and expected results. The next results report from SHER will be available in March 2021, with
             quarterly activity implementation reports thereafter.
            All other contractors have initiated activities on the ground as per their contractual agreements (FAO, ACORD, IGNIFI, BIOVERSITY
             International), pending confirmation on target sites during the feasibility studies being implemented by SHER. Furthermore, colline-level
             action plans (detailing plans for landscape restoration) will be initiated and finalized in collaboration with the NGO “ACORD” for community
             mobilization;
            FAO has featured however delays in submitting their invoices, impacting project disbursement levels. The project team has been following
             up daily with both FAO-Rome and FAO-Burundi to ensure expedited submission of their invoices, as well as supporting the PIU in
             submitting WAs in time.
             Continued coordination across project contractors and coherent central progress monitoring by the PIU will be critical for the continued
             success of the BLRRP. As the project cruises to achieve full speed in its implementation, the project team will need to ensure the project
             continues to achieve adequate disbursements levels.
  The MoU with the Burundi Office for the Environment (OBPE) signed in May 2020 to support the establishment of nurseries producing agroforestry,
  forestry, and bamboo seedlings was extended in December 2020 to also include the supervision of demonstrative plantation activities in the 7 hills
  of the Buhinyuza commune and in the 5 hills of the Isare commune. The Bank had requested that plantation activities be implemented only after 1)
  the GRM is operationalized in the targeted areas and 2) overall alignment is ensured with main activities starting, including community mobilization
  and restoration feasibility studies. Results to date include:
            In Buhinyuza: 27.9 ha of eucalyptus were planted on lands, and 22.6 km of trees along roadways
            In Isare: 25.3 ha of eucalyptus were planted on lands, and 10 km of trees along roadways. In addition, 7.25 km of bamboo were planted
             along riverbanks.
  Progress report for the 1st month (January 2021) indicates mixed results in some sites due to weather conditions (heat) and some seedlings having
  exceeded the planting stage. Replanting will be scheduled on all sites with a recovery rate of less than 80% with the return of the rains expected in
  March and early April.
  Under component 3:
  Park maintenance and livelihoods activities are underway with OBPE in the three target Protected Areas (PAs)and their periphery. Equipment for
  OPBE’s eco-guards working in the 3 PAs were delivered (after being blocked at customs since December 2020 which will allow Park’s
  management-supported activities to resume. In the context of activities supporting alternative livelihoods, 6 nursery sites were established with a
  forecast of 320,000 maracuja seedlings and 160,000 Japanese plum seedlings produced. The identification of the beneficiaries of these plants is in
  progress on the hills bordering the protected areas. Regarding activities in support to Batwa communities, to date 1497 Batwa, including 1081 in
  Kibira NP, 352 in Ruvubu NP and 64 in Bururi NWA, were involved in work to demarcate the boundaries of Protected Areas, maintain firebreaks
  and tourist trails during the period from July to December 2020.




  Risks


 Systematic Operations Risk-rating Tool


  Risk Category                                               Rating at Approval                Previous Rating               Current Rating

  Political and Governance                                    High                             Substantial                  Substantial


3/5/2021                                                                                                                         Page 2 of 7
            The World Bank                                                                                 Implementation Status & Results Report
            Burundi Landscape Restoration and Resilience Project (P160613)




  Macroeconomic                                             Substantial                  Substantial                 Substantial
  Sector Strategies and Policies                            Moderate                     Moderate                    Moderate
  Technical Design of Project or Program                    Substantial                  Substantial                 Substantial
  Institutional Capacity for Implementation and
                                                            Substantial                  Substantial                 Substantial
  Sustainability
  Fiduciary                                                 High                         High                        High
  Environment and Social                                    Substantial                  Substantial                 Substantial
  Stakeholders                                              Substantial                  Substantial                 Substantial
  Other                                                     Substantial                  Substantial                 Substantial
  Overall                                                   Substantial                  Substantial                 Substantial



  Results


 PDO Indicators by Objectives / Outcomes



   Restore land productivity in targeted degraded landscapes

    IN00953715
    ►Land productivity in targeted degraded landscapes (Number, Custom)

                                       Baseline                  Actual (Previous)           Actual (Current)          End Target

    Value                              100.00                    100.00                      100.00                    120.00

    Date                               16-Mar-2018               05-Jun-2019                 05-Jun-2019              29-Dec-2023

    IN00953736
    ►Land area under sustainable landscape management practices (Hectare(Ha), Corporate)

                                       Baseline                  Actual (Previous)           Actual (Current)          End Target

    Value                              0.00                      0.00                        0.00                      89,360.00

    Date                               16-Mar-2018               05-Jun-2019                 05-Jun-2019              29-Dec-2023

    IN00953737
    ►Share of targeted community members with rating ‘Satisfied’ or above on project interventions (Percentage, Custom)

                                       Baseline                  Actual (Previous)           Actual (Current)          End Target

    Value                              0.00                      0.00                        0.00                      70.00

    Date                               16-Mar-2018               05-Jun-2019                 05-Jun-2019              29-Dec-2023

     IN00953738
     Share of targeted community members with rating ‘Satisfied’ or above on project interventions (women) (Percentage, Custom
     Breakdown)

                                     Baseline                   Actual (Previous)          Actual (Current)           End Target

     Value                           0.00                       0.00                       0.00                       70.00


3/5/2021                                                                                                                  Page 3 of 7
           The World Bank                                                                                    Implementation Status & Results Report
           Burundi Landscape Restoration and Resilience Project (P160613)




     Date                           16-Mar-2018                05-Jun-2019                    05-Jun-2019               29-Dec-2023



 Intermediate Results Indicators by Components



   Institutional Development and Capacity Building for Landscape Restoration and Resilience

    IN00953739
    ►Guidelines to support watershed management planning and landscape restoration developed and disseminated (Number, Custom)

                                      Baseline                   Actual (Previous)             Actual (Current)          End Target

    Value                             0.00                       0.00                          0.00                      4.00

    Date                              16-Mar-2018                05-Jun-2019                   05-Jun-2019              29-Dec-2023



   Sustainable Landscape Management Practices

    IN00953740
    ►Collines restored according to defined criteria (Number, Custom)

                                      Baseline                   Actual (Previous)             Actual (Current)          End Target

    Value                             0.00                       0.00                          0.00                      22.00

    Date                              16-Mar-2018                05-Jun-2019                   05-Jun-2019              29-Dec-2023

    IN00953742
    ►Erosion in targeted degraded landscapes (Percentage, Custom)

                                      Baseline                   Actual (Previous)             Actual (Current)          End Target

    Value                             0.00                       0.00                          0.00                      50.00

    Date                              16-Mar-2018                05-Jun-2019                   05-Jun-2019              29-Dec-2023

    IN00953743
    ►Beneficiaries of job-focused interventions (Number, Corporate)

                                      Baseline                   Actual (Previous)             Actual (Current)          End Target

    Value                             0.00                       0.00                          0.00                      14,670.00

    Date                              16-Mar-2018                05-Jun-2019                   05-Jun-2019              29-Dec-2023

     IN00953744
     Beneficiaries of job-focused interventions - Female (Number, Corporate Supplement)

                                    Baseline                    Actual (Previous)             Actual (Current)          End Target

     Value                          0.00                       0.00                           0.00                      7,335.00

    IN00953745
    ►Farmers adopting improved agricultural technology (Number, Corporate)



3/5/2021                                                                                                                    Page 4 of 7
           The World Bank                                                                                   Implementation Status & Results Report
           Burundi Landscape Restoration and Resilience Project (P160613)




                                      Baseline                    Actual (Previous)           Actual (Current)          End Target

    Value                             0.00                       0.00                         0.00                      24,008.00

    Date                              16-Mar-2018                05-Jun-2019                  05-Jun-2019               29-Dec-2023

     IN00953746
     Farmers adopting improved agricultural technology - Female (Number, Corporate Supplement)

                                    Baseline                    Actual (Previous)            Actual (Current)           End Target

     Value                          0.00                        0.00                         0.00                       12,004.00

     IN00953747
     Farmers adopting improved agricultural technology - male (Number, Corporate Supplement)

                                    Baseline                    Actual (Previous)            Actual (Current)           End Target

     Value                          0.00                        0.00                         0.00                       12,004.00

    IN00953748
    ►Land certificates issued (Number, Custom)

                                      Baseline                    Actual (Previous)           Actual (Current)          End Target

    Value                             0.00                       0.00                         0.00                      14,080.00

    Date                              16-Mar-2018                05-Jun-2019                  05-Jun-2019               29-Dec-2023

     IN00953749
     Land certificates issued with women's name (Percentage, Custom Supplement)

                                    Baseline                    Actual (Previous)            Actual (Current)           End Target

     Value                          0.00                        0.00                         0.00                       50.00


   Improved Management of Protected Areas and Reserves

    IN00953741
    ►Management Effectiveness Tracking Tool (METT) for Protected Areas in targeted landscapes (Number, Custom)

                                      Baseline                    Actual (Previous)           Actual (Current)          End Target

    Value                             28.00                      28.00                        28.00                     45.00

    Date                              16-Mar-2018                05-Jun-2019                  05-Jun-2019               30-Dec-2022


 Overall Comments IR

  Mid-Term Review

  The project MTR process is planned to start in April 2021, with MTR Report expected to be made available by the Client in June 2021.
  Following this, the Task Team will conduct a MTR Mission (specific date to be confirmed).




 Performance-Based Conditions



3/5/2021                                                                                                                   Page 5 of 7
           The World Bank                                                                                  Implementation Status & Results Report
           Burundi Landscape Restoration and Resilience Project (P160613)




 Data on Financial Performance


 Disbursements (by loan)

 Project       Loan/Credit/TF    Status       Currency        Original   Revised     Cancelled     Disbursed     Undisbursed                % Disbursed


 P160613       IDA-D2760         Effective    USD               30.00      30.00           0.00         6.05           23.48                       20%


 Key Dates (by loan)

 Project        Loan/Credit/TF    Status      Approval Date       Signing Date     Effectiveness Date    Orig. Closing Date      Rev. Closing Date

 P160613        IDA-D2760         Effective   11-Apr-2018         24-May-2018      21-Sep-2018           14-Mar-2023             14-Mar-2023


Cumulative Disbursements




 PBC Disbursement

                                                                                        Achievement     Disbursed amount in         Disbursement %
 PBC ID                     PBC Type   Description             Coc       PBC Amount
                                                                                        Status          Coc                         for PBC




3/5/2021                                                                                                                      Page 6 of 7
           The World Bank                                                   Implementation Status & Results Report
           Burundi Landscape Restoration and Resilience Project (P160613)




  Restructuring History


  There has been no restructuring to date.


  Related Project(s)


  P171745-Burundi Landscape Restoration and Resilience Project




3/5/2021                                                                                   Page 7 of 7