Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan [Original: April 2016]: Revision of Updated Procurement Plan, April 2017] 2. Date of General Procurement Notice: November 1 2016 3. Period covered by this procurement plan: The procurement period of project covered from year November 2016 to December 2017 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Threshold Comments US$ 1. ICB and LIB (Goods) Above US$ 4 million All 2. NCB (Goods) Above US$ 4 million All 3. ICB (Works) Above US$ 15 million All 4. NCB (Works) Above US$ 15 million All 5. (Non-Consultant Services) Above US$ 4 million 0 All 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan Ningbo Sustainable Urbanization Project 01/20/2016 issued by Ningbo PMO 4. Any Other Special Procurement Arrangements: None 5. Summary of the Procurement Packages planned during the first 18 months after project effectiveness (including those that are subject to retroactive financing and advanced procurement) July 9, 2010 1 2 3 4 5 6 7 Ref. Description Estimated Packag Domestic Review Comments No. Cost es Preference by US$ (yes/no) Bank million (Prior / Post) XGP3 purchase of 30 new- 2.344 1 No Prior energy buses (Goods) XCP3 Huancheng Road 34.7 1 No Prior West construction (from Danshan Road to Binhai Avenue): main road with total length 2952m, L652m/2300m, W36m/25m, and related municipal pipeline facilities. (Works) NCP1 Taoyuan Road 5.625 1 No Post Middle reconstruction: urban primary road, lenght 1.3km, width 60m/55m, cross section optimization, four motor lanes broden to six motor lanes, drainage inlet reconstruction, lighting facilites, greening and landscape (Works) XCP5 Overall renewal of 10.56 1 No Post Tian'an Road (Xiangshan Harbour Road to Binhai Avenue section), public space improvement along Dannan Road, commercial area renovation (Jianshe Road to Xiangshan Harbour Road). (Works) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: July 9, 2010 Selection Method Prior Review Threshold Comments 1. Competitive Methods (Firms) Above US$ 2,000,000 2. Single Source (Firms) All 3. Individual Above US$ 400,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: None 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description of Estimated Packages Review Comments Assignment Cost by Bank US$ (Prior / million Post) NBTA1 Project 1.2 1 Prior QCBS Management, Institutional Strengthening and Training July 9, 2010 PROCUREMENT China : Ningbo Sustainable Urbanization Project PLAN General Information Country: China Bank’s Approval Date of the Original Procurement Plan: 2016-09-27 2019-12-26 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P149485 GPN Date: 2016-11-01 Project Name: Ningbo Sustainable Urbanization Project Loan / Credit No: IBRD / 86220 Executing Agency(ies): Ningbo sustainable urbanization PMO WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NCP1 / Taoyuan Road Middle reconstruction: urban primary road, lenght 1.3km, width 60m/55m, cross section optimization, four motor Component 2: Urban Single Stage - One IBRD / 86220 Post Request for Bids Open - National 5,625,000.00 3,614,570.73 Signed 2017-01-16 2017-01-23 2017-03-06 2017-04-05 2017-05-10 2017-11-06 lanes broden to six motor Transport Envelope lanes, drainage inlet reconstruction, lighting facilites, greening and landscape XCP5 / Overall renewal of Tian'an Road (Xiangshan Harbour Road to Binhai Avenue section), public space Component 2: Urban Single Stage - One IBRD / 86220 Post Request for Bids Open - National 10,560,000.00 7,407,935.17 Signed 2017-08-07 2017-08-12 2017-09-23 2017-10-23 2017-11-27 2018-05-26 improvement along Dannan Transport Envelope Road, commercial area renovation (Jianshe Road to Xiangshan Harbour Road). XCP3 / Huancheng Road West construction (from Danshan Road to Binhai Avenue): main road with Component 2: Urban Single Stage - One IBRD / 86220 Prior Request for Bids Open - National 34,700,000.00 23,466,602.92 Signed 2017-08-14 2017-09-01 2017-10-13 2017-11-12 2017-12-17 2018-06-15 total length 2952m, Transport Envelope L652m/2300m, W36m/25m, and related municipal pipeline facilities. XCP7 / Tashan terminal Component 2: Urban Single Stage - One IBRD / 86220 Post Request for Bids Open - National 1,950,000.00 1,669,152.11 Signed 2017-11-01 2017-11-06 2017-12-18 2018-01-17 2018-02-21 2019-03-21 construction Transport Envelope NCP3 / Renmin Road reconstruction (from Taoyuan Component 2: Urban Single Stage - One IBRD / 86220 Post Request for Bids Open - National 5,110,000.00 4,379,951.50 Signed 2017-10-09 2017-10-14 2017-11-25 2017-12-25 2018-01-29 2019-01-31 Road Middle to Xinghai Transport Envelope Road Middle) NCP5 / Ninghai Central Urban Area bus terminal Component 2: Urban Single Stage - One IBRD / 86220 Post Request for Bids Open - National 1,310,000.00 798,107.68 Signed 2017-11-01 2017-11-06 2017-12-18 2018-01-17 2018-02-21 2019-02-28 construction: Qiaotouhu Transport Envelope Terminal FCP1 / Xikou old town public space improvement: Component 1: Urban Single Stage - One IBRD / 86220 Post Request for Bids Open - National 7,260,000.00 6,167,937.32 Signed 2017-09-30 2017-10-09 2017-11-20 2017-12-20 2018-01-24 2019-01-31 Wuling Road reconstruction Regeneration Envelope and improvement NCP4 / Qianhuang Component 2: Urban Single Stage - One IBRD / 86220 Post Request for Bids Open - National 750,000.00 0.00 Canceled 2018-08-06 2018-08-11 2018-09-22 2018-10-22 2018-11-26 2019-12-03 Terminal construction Transport Envelope Page 1 XCP3-1 / Huancheng Road West construction (from Danshan Road to Binhai Avenue): main road with Component 2: Urban Single Stage - One IBRD / 86220 Prior Request for Bids Limited 19,000,000.00 18,835,982.97 Signed 2019-01-31 2019-02-11 2019-03-04 2019-04-03 2019-05-08 2020-10-29 total length 2952m, Transport Envelope L652m/2300m, W36m/25m, and related municipal pipeline facilities. FCP2 / Wulinfang Area Under Component 1: Urban Single Stage - One reconstruction and IBRD / 86220 Post Request for Bids Open - National 2,907,000.00 0.00 Implementati 2019-08-30 2019-09-08 2019-10-20 2019-11-19 2019-12-24 2020-12-26 Regeneration Envelope improvement on Under XCP2 / Jinnan Street Component 1: Urban Single Stage - One IBRD / 86220 Post Request for Bids Open - National 2,946,000.00 2,780,670.98 Implementati 2019-08-30 2019-09-04 2019-10-16 2019-11-15 2019-12-20 2020-06-17 reconstruction Regeneration Envelope on NCP10 / Upper reach of Huailu River: Yonglin Line to Shenhai Expressway Under Component 3: Flood Risk Single Stage - One Section, 380 meters long, IBRD / 86220 Post Request for Bids Open - National 1,750,000.00 1,024,935.01 Implementati 2019-09-30 2019-10-08 2019-11-19 2019-12-19 2020-01-23 2020-07-21 Management Envelope with box culvert 183 meters, on open channel 199.6 meters, culvert laying, etc. NCP11 / Longyan Creek: The total length 2180m, of which the main river channel 1259m, the new diversion section 145m, and Under Component 3: Flood Risk Single Stage - One the tributary 776m; IBRD / 86220 Post Request for Bids Open - National 4,150,000.00 2,006,432.60 Implementati 2019-09-30 2019-10-08 2019-11-19 2019-12-19 2020-01-23 2021-01-22 Management Envelope construction of the on embankment 3450m, of which main channel 1984m, new diversion section 290m, the tributary 1176m. NCP9 / Zhuxi construction: dyke building, barrage construction, manhole works, Pending Component 3: Flood Risk Single Stage - One culvert and diversion IBRD / 86220 Post Request for Bids Open - National 3,100,000.00 0.00 Implementati 2020-01-02 2020-01-07 2020-02-18 2020-03-19 2020-04-23 2021-04-23 Management Envelope channel works, stairs design, on landscape and greening works GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual XGP3 / purchase of 30 new- Component 2: Urban Single Stage - One IBRD / 86220 Prior Request for Bids Open - National 2,344,000.00 2,142,527.84 Signed 2016-10-27 2016-11-01 2016-12-13 2017-01-12 2017-02-16 2017-06-16 energy buses Transport Envelope XGP1 / Traffic Component 2: Urban Single Stage - One management: intelligence IBRD / 86220 Prior Request for Bids Open - National 8,650,000.00 6,650,266.36 Signed 2017-11-01 2017-11-06 2017-12-18 2018-01-17 2018-02-21 2018-12-21 Transport Envelope traffic XGP4 / purchase of 65 new- Component 2: Urban Single Stage - One IBRD / 86220 Prior Request for Bids Open - National 7,300,000.00 0.00 Canceled 2018-08-20 2018-09-17 2018-10-29 2018-11-28 2019-01-02 2019-12-31 engery buses Transport Envelope Page 2 XGP1-1 / Traffic signal controller, platform software upgrade, mobile handheld terminal, vehicle GPS positioning equipment, Component 2: Urban IBRD / 86220 Post Direct Selection Direct 750,000.00 592,738.64 Signed 2018-11-12 2018-12-05 2019-01-12 2019-04-12 integrated video command Transport system, disaster recovery backup, signal timing optimization, traffic detection system XGP4-1 / Purchase of 65 Component 2: Urban Single Stage - One IBRD / 86220 Prior Request for Bids Open - National 7,300,000.00 7,000,790.00 Signed 2019-02-12 2019-03-12 2019-04-23 2019-05-23 2019-06-27 2020-01-13 new-engery buses Transport Envelope NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NBTA1 / Project Component 4: Technical Quality And Cost- Open - Management, Institutional IBRD / 86220 Assistance and Capacity Prior 1,200,000.00 1,073,666.18 Signed 2016-10-10 2016-10-31 2016-12-14 2017-01-11 2017-02-10 2017-03-17 2017-04-21 2020-12-31 Based Selection International Strengthening and Training Building NBTA3 / Study on Component 4: Technical Fenghua intelligence Quality And Cost- Open - IBRD / 86220 Assistance and Capacity Post 300,000.00 0.00 Canceled 2018-05-07 2018-05-28 2018-07-11 2018-08-08 2018-09-07 2018-10-12 2018-11-16 2019-11-16 transportation and pilot Based Selection International Building implementation NBTA3-1 / Study on Component 4: Technical Consultant Fenghua intelligence IBRD / 86220 Assistance and Capacity Post Qualification Open - National 250,000.00 251,921.08 Signed 2018-06-04 2018-06-25 2018-08-08 2018-09-07 2018-10-12 2019-04-10 transportation and pilot Building Selection implementation Component 4: Technical NBTA2 / Public facilities Quality And Cost- Open - IBRD / 86220 Assistance and Capacity Post 800,000.00 0.00 Canceled 2018-10-08 2018-10-29 2018-12-12 2019-01-09 2019-02-08 2019-03-15 2019-04-19 2022-12-29 and service fund support Based Selection International Building NBTA5 / Strategic study on Component 4: Technical Consultant Xiangshan public IBRD / 86220 Assistance and Capacity Post Qualification Open - National 200,000.00 0.00 Canceled 2018-09-10 2018-10-15 2018-11-28 2018-12-28 2019-02-01 2020-02-01 transportation development Building Selection NBTA5-1 / Strategic study Component 4: Technical Consultant on Xiangshan public IBRD / 86220 Assistance and Capacity Post Qualification Open - National 295,000.00 292,593.32 Signed 2018-11-19 2018-11-26 2019-01-09 2019-02-08 2019-03-15 2020-03-14 transportation development Building Selection INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NBTA6 / Flood Risk Component 4: Technical Assessment in Ninghai IBRD / 86220 Assistance and Capacity Post Direct Selection Direct 75,000.00 75,000.00 Signed 2019-01-04 2019-01-14 2019-03-20 2019-09-16 County Building Page 3