VIETNAM Da Nang Sustainable City Development Project Textual Part of Procurement Plan I. General 1. Bank’s Approval Date of the Procurement Plan: Original: March 8, 2013. Latest Updated Procurement Plan: June 20, 2017 2. Date of General Procurement Notice: July 2, 2013 3. Period covered by this procurement plan: From June 2017 to June 2019 II. Applicable Rules and Procedures 1. Procurement for the proposed project shall be carried out in accordance with the World Bank’s “Guidelines: Procurement of Goods, Works and Non-Consulting Services Under IBRD Loans, IDA Credits & Grants by World Bank Borrowers” dated January 2011, revised July 2014 (referred to as the Procurement Guidelines) and “Guidelines: Selection and Employment of Consultants Under IBRD Loans, IDA Credits & Grants by World Bank Borrowers” dated January 2011, revised July 2014 (the Consultant Guidelines). III. Goods and Works and Non-Consulting Services 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement. These thresholds are subject to change by the Bank during the project implementation based on its assessment of the project procurement implementation capacity and risks: Procurement Method Prior Review Threshold Comments US$ 1. ICB and LIB (Goods) Above US$2 million All contracts above thresholds 2. NCB (Goods) Above US$2 million All contracts above thresholds 3. ICB (Works) Above US$10 million All contracts above thresholds 4. NCB (Works) Above US$10 million All contracts above thresholds 5. Shopping N/A No prior review 6. Direct Contracting (Goods) Above US$2 million All contracts above thresholds 7. Direct Contracting (Works) Above US$10 million All contracts above thresholds July 9, 2010 2. Prequalification: Not applicable. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: Not applicable. 4. Reference to Project Operational/Procurement Manual: The Project Implementation Manual dated March 1, 2013 and approved by the Da Nang City People’ Committee as referred to in the Financing Agreement. 5. Any Other Special Procurement Arrangements: No. III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants. These thresholds are subject to change by the Bank during the project implementation based on its assessment of the project procurement implementation capacity and risks: Selection Method Prior Review Threshold Comment 1. Competitive Methods (Firms) Above US$1 million All contracts above thresholds 2. Single Source (Firms) Above US$1 million All contracts above thresholds 3. Individuals Above US$300,000 All contracts above thresholds 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $500,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Reference to Project Operational/Procurement Manual: The Project Implementation Manual dated March 1, 2013 and approved by the Da Nang City People’ Committee as referred to in the Financing Agreement. 4. Any Other Special Selection Arrangements: Not applicable. July 9, 2010 PROCUREMENT Vietnam : Danang Sustainable City Development Project (SCDP) PLAN General Information Country: Vietnam Banks Approval Date of the Original Procurement Plan: 2017-10-31 Revised Plan Date(s): (comma delineated, leave blank if none) 2017-11-23 Project ID: P123384 GPN Date: Project Name: Danang Sustainable City Development Project (SCDP) Loan / Credit No: IDA / 52330, IDA / 60320 Executing Agency(ies): Da Nang Priority Infrastructure Investment Project Management Unit WORKS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 1. Drainage and Wastewater I mprovement 5. Transferred activities from Da Nang Priority Infrastructu Package 3.6 / Package 3.6: re Investment Project Single Stage - One Construction of Bridges on Hoa IDA / 52330 Prior Request for Bids Open - National N 0.00 7,601,093.44 Signed 2015-08-19 2015-09-18 Phuoc - Hoa Khuong Road 4. Technical Assistance and C Envelope apacity Building 3. Urban Strategic Roads 2. Bus Rapid Transit Develop ment 1. Drainage and Wastewater I mprovement 5. Transferred activities from 1.11 / Extension of Capacity of Da Nang Priority Infrastructu Hoa Xuan Wastewater Treatment re Investment Project Single Stage - One Plant and Operation and IDA / 52330 Prior Request for Bids Open - International N 0.00 7,638,205.48 Signed 2017-04-13 2017-05-22 Maintenance of the Plant for 5 4. Technical Assistance and C Envelope Years apacity Building 3. Urban Strategic Roads 2. Bus Rapid Transit Develop ment 1. Drainage and Wastewater I mprovement 5. Transferred activities from Package 1.2 / Construction of Da Nang Priority Infrastructu Lien Chieu Wastewater Treatment Plant and ancillary IDA / 52330 re Investment Project Single Stage - One Under Prior Request for Bids Open - International N 0.00 7,616,257.05 2017-07-20 works and Operation & IDA / 60320 4. Technical Assistance and C Envelope Implementation Maintenance of the Plant for 5 apacity Building Years 3. Urban Strategic Roads 2. Bus Rapid Transit Develop ment 1. Drainage and Wastewater I mprovement 5. Transferred activities from Da Nang Priority Infrastructu Package 3.5 / Package 3.5: re Investment Project Single Stage - One Construction of Hoa Phuoc - Hoa IDA / 52330 Prior Request for Bids Open - National N 0.00 12,767,083.33 Signed 2015-07-16 2015-08-03 Khuong Road 4. Technical Assistance and C Envelope apacity Building 3. Urban Strategic Roads 2. Bus Rapid Transit Develop ment 1. Drainage and Wastewater I mprovement 5. Transferred activities from Da Nang Priority Infrastructu 3.2 / Construction of Infrastructure of resettlement re Investment Project Single Stage - One IDA / 52330 Prior Request for Bids Open - National N 0.00 5,628,093.52 Signed 2014-04-23 2014-05-24 areas in the South of Danang 4. Technical Assistance and C Envelope City under SCDP apacity Building 3. Urban Strategic Roads 2. Bus Rapid Transit Develop ment 1. Drainage and Wastewater I mprovement 5. Transferred activities from Da Nang Priority Infrastructu B55b / Upgrading of Son Tra re Investment Project Single Stage - One IDA / 52330 Prior Request for Bids Open - International N 0.00 11,133,253.79 Signed 2015-01-28 2015-03-24 Wastewater Treatment Plant 4. Technical Assistance and C Envelope apacity Building 3. Urban Strategic Roads 2. Bus Rapid Transit Develop ment GOODS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 2-4-2-5 / Supply, installation of ticketing system, intelligent transport system for public 2. Bus Rapid Transit Develop Single Stage - One Under transport system and traffic IDA / 52330 Prior Request for Bids Open - International 14,313,734.00 0.00 2016-11-25 2016-11-25 2017-05-30 2017-10-30 2017-12-30 2018-01-15 2019-07-19 signal priority system for bus ment Envelope Implementation rapid transit (BRT) (including 2 lots) Page 1 4-7E / Procurement of 4. Technical Assistance and C Single Stage - One Pending equipment for monitoring and IDA / 52330 Post Request for Bids Open - National 149,383.00 0.00 2018-06-07 2018-06-07 2018-07-15 2018-09-20 2018-09-27 2019-03-26 managing public transport apacity Building Envelope Implementation 4-8 / Procurment of software for Da Nang Traffic Light and Public Transport Management Centre 4. Technical Assistance and C Request for Single Stage - One Pending IDA / 52330 Post Open - National 100,000.00 0.00 2018-05-25 2018-09-03 2019-03-02 (DATRAMAC) and departments apacity Building Quotations Envelope Implementation for management and operation of public transport system 4-9B / Procurement of office equipment for Project 4. Technical Assistance and C Request for Single Stage - One Pending IDA / 52330 Post Open - National 80,000.00 0.00 2018-05-14 2018-08-22 2018-11-20 Management Unit in project apacity Building Quotations Envelope Implementation implementation NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Technical Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 1. Drainage and Wastewater I mprovement 5. Transferred activities from Package 3.3: CSC Comp 2 and Da Nang Priority Infrastructu 3 / Package 3.3: Consulting Services for Contract re Investment Project Quality And Cost- IDA / 52330 Prior Open - International N 0.00 3,835,018.12 Canceled 2017-08-04 Management and Construction 4. Technical Assistance and C Based Selection Supervision for Component 2 and apacity Building 3 3. Urban Strategic Roads 2. Bus Rapid Transit Develop ment 1. Drainage and Wastewater I mprovement 5. Transferred activities from Da Nang Priority Infrastructu 2.1 Part 2 / On-Site Supervision of Equipment Installation and re Investment Project Consultant IDA / 52330 Prior Qualification Open - International N 0.00 2,945,937.29 Signed 2014-06-03 2014-11-14 Technical Assistance for 4. Technical Assistance and C Selection Operation of BRT System apacity Building 3. Urban Strategic Roads 2. Bus Rapid Transit Develop ment 1. Drainage and Wastewater I mprovement 5. Transferred activities from Da Nang Priority Infrastructu 4.14 / Consulting Services for re Investment Project Financial Audit for Phase I of the IDA / 52330 Prior Least Cost Selection Open - International N 0.00 19,939.88 Signed 2014-05-30 2014-06-05 Project 4. Technical Assistance and C apacity Building 3. Urban Strategic Roads 2. Bus Rapid Transit Develop ment 1. Drainage and Wastewater I mprovement Package 1.1, Part 2 / Package 5. Transferred activities from 1.1, Part 2: Consulting Services Da Nang Priority Infrastructu for Contract Management, re Investment Project Quality And Cost- Construction Supervision and IDA / 52330 Prior Open - International N 0.00 3,047,091.00 Signed 2014-08-28 2014-09-18 Procurement Support for 4. Technical Assistance and C Based Selection Component 1 (Drainage and apacity Building Wastewater Improvement) 3. Urban Strategic Roads 2. Bus Rapid Transit Develop ment 1. Drainage and Wastewater I mprovement 5. Transferred activities from 4.15 / Project performance audit, Da Nang Priority Infrastructu monitoring and evaluation of re Investment Project Quality And Cost- project outcomes under Danang IDA / 52330 Prior Open - International N 0.00 319,548.77 Signed 2015-03-27 2015-04-27 Sustainable City Development 4. Technical Assistance and C Based Selection Project apacity Building 3. Urban Strategic Roads 2. Bus Rapid Transit Develop ment 4-1 / Consulting services for study on transport system model 4. Technical Assistance and C Quality And Cost- Under IDA / 52330 Prior Open - International 5,000,000.00 0.00 2017-11-09 2017-11-11 2017-11-14 2018-04-09 2018-06-15 2018-07-15 2018-10-08 2018-10-15 2020-04-17 of the city after relocating the apacity Building Based Selection Implementation railway to the new alignment INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Contract Type Estimated Actual Amount Draft Negotiated Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 2 1. Drainage and Wastewater I mprovement 5. Transferred activities from Da Nang Priority Infrastructu 4.18 / Consulting Service of re Investment Project Individual Consultant IDA / 52330 Prior Open N 0.00 104,400.00 Signed 2014-06-24 2014-07-28 Internal Audit for the SCDP 4. Technical Assistance and C Selection apacity Building 3. Urban Strategic Roads 2. Bus Rapid Transit Develop ment Page 3