The World Bank Implementation Status & Results Report Jiangxi Farm Produce Distribution System Development (P147009) Jiangxi Farm Produce Distribution System Development (P147009) EAST ASIA AND PACIFIC | China | Agriculture and Food Global Practice | IBRD/IDA | Investment Project Financing | FY 2018 | Seq No: 6 | ARCHIVED on 03-Aug-2020 | ISR42214 | Implementing Agencies: People's Republic of China, Jiangxi Department of Agriculture and Rural Affairs Key Dates Key Project Dates Bank Approval Date: 15-Dec-2017 Effectiveness Date: 15-May-2018 Planned Mid Term Review Date: 22-Mar-2021 Actual Mid-Term Review Date: Original Closing Date: 31-Dec-2023 Revised Closing Date: 31-Dec-2023 pdoTable Project Development Objectives Project Development Objective (from Project Appraisal Document) The Project Development Objective (PDO) is to improve the distribution systems of selected farm products in participating counties of Jiangxi. Has the Project Development Objective been changed since Board Approval of the Project Objective? No Components Table Name Component 1: Strengthening production logistics:(Cost $38.46 M) Component 2: Improving Distribution Logistics:(Cost $140.25 M) Component 3: Support Services for the Whole Distribution System:(Cost $0.45 M) Component 4: Project Management, Monitoring and Evaluation:(Cost $5.18 M) Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO Satisfactory Satisfactory Overall Implementation Progress (IP) Moderately Satisfactory Moderately Satisfactory Overall Risk Rating Substantial Substantial Implementation Status and Key Decisions The project has made progress towards achieving the project development objectives. The project implementation has been made although COVID-19 related lockdowns, travel restrictions, and enforcement of social distancing requirements adversely impacted the implementation. 14 market facilitators have been hired in eight project counties. 35 farmer cooperatives in four counties and 42 e-commerce merchants in two counties were selected for project support. 133 village farmer information hubs in five counties were set up, 28 farm product certifications in five counties were obtained and six counties deposited funds into the special account of Jiangxi Rural Commercial Bank under the Partial Credit Guarantee scheme. While the construction of one market facility is underway in Yusha, bid selection for construction of agri-distribution and logistics infrastructure in Huichang was completed recently. The project also finalized the Management Information System modules and progressed on the baseline survey. The project mid-term review is scheduled to be in March 2021. 8/3/2020 Page 1 of 7 The World Bank Implementation Status & Results Report Jiangxi Farm Produce Distribution System Development (P147009) Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance Low Low Low Macroeconomic Moderate Moderate Moderate Sector Strategies and Policies Moderate Moderate Moderate Technical Design of Project or Program Substantial Substantial Substantial Institutional Capacity for Implementation and Substantial Substantial Substantial Sustainability Fiduciary Moderate Moderate Moderate Environment and Social Moderate Moderate Moderate Stakeholders Moderate Moderate Moderate Other -- -- Substantial Overall Substantial Substantial Substantial Results PDO Indicators by Objectives / Outcomes To improve the distribution system of selected farm products in participating counties of Jiangxi IN00855583 ►Farmers reached with agricultural assets or services (Number, Corporate) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 35,994.00 39,239.00 225,000.00 Date 01-Jan-2017 31-Dec-2019 30-Jun-2020 31-Dec-2023 IN00855584 Farmers reached with agricultural assets or services - Female (Number, Corporate Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 12,240.00 13,038.00 37,300.00 IN00855585 ►Increased number of farmer cooperatives with service access provided by the Project financed markets (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target 8/3/2020 Page 2 of 7 The World Bank Implementation Status & Results Report Jiangxi Farm Produce Distribution System Development (P147009) Value 0.00 0.00 20.00 700.00 Date 01-Jan-2017 31-Dec-2019 30-Jun-2020 31-Dec-2023 IN00855586 ►Increased producers direct sales of farm produce through Project financed markets (percentage) (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 25.00 Date 01-Jan-2017 31-Dec-2019 30-Jun-2020 31-Dec-2023 Intermediate Results Indicators by Components Component 1: Strengthening production logistics IN00855587 ►Number of farmer cooperatives supported by the proposed Project (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 10.00 35.00 186.00 Date 01-Jan-2017 31-Dec-2019 30-Jun-2020 31-Dec-2023 There has been a mistake in the methodology for data collection and reporting by CPMOs in the previous progress report. PPMO has since validated the results data and adjusted marginally downwards the Comments: achievement under this indicator in the current report. IN00855591 New (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 5.00 13.00 59.00 Date 01-Jan-2017 31-Dec-2019 30-Jun-2020 31-Dec-2023 IN00855593 Established (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 5.00 22.00 127.00 Date 01-Jan-2017 31-Dec-2019 30-Jun-2020 31-Dec-2023 IN00855595 ►Number of farmers (person days) receiving training (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 6,554.00 8,438.00 88,600.00 8/3/2020 Page 3 of 7 The World Bank Implementation Status & Results Report Jiangxi Farm Produce Distribution System Development (P147009) Date 01-Jan-2017 31-Dec-2019 30-Jun-2020 31-Dec-2023 There has been a mistake in the methodology for data collection and reporting by CPMOs in the previous progress report. PPMO has since validated the results data and adjusted marginally downwards the Comments: achievement under this indicator in the current report. IN00855597 Males (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 2,853.00 3,837.00 44,300.00 Date 01-Jan-2017 31-Dec-2019 30-Jun-2020 31-Dec-2023 IN00855598 Female (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 3,701.00 4,601.00 44,300.00 Date 01-Jan-2017 31-Dec-2019 30-Jun-2020 31-Dec-2023 IN00855599 ►Number of certified farm products (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 28.00 28.00 155.00 Date 01-Jan-2017 31-Dec-2019 30-Jun-2020 31-Dec-2023 IN00855600 ►Number of villages with farmer information hubs for the farmers (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 116.00 133.00 601.00 Date 01-Jan-2017 31-Dec-2019 30-Jun-2020 31-Dec-2023 IN00855601 ►Incremental Amount of portfolio made through leverage of the partial guarantee ($million) (Amount(USD), Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 1.44 0.00 60.00 Date 01-Jan-2017 31-Dec-2019 30-Jun-2020 31-Dec-2023 The previous data is incorrect. Comments: Component 2: Improving Distribution Logistics IN00855588 ►Number of markets/distribution centers constructed or rehabilitated (Number, Custom) 8/3/2020 Page 4 of 7 The World Bank Implementation Status & Results Report Jiangxi Farm Produce Distribution System Development (P147009) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 1.00 8.00 Date 01-Jan-2017 31-Dec-2019 30-Jun-2020 31-Dec-2023 IN00855592 Rehabilitated (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 1.00 Date 01-Jan-2017 31-Dec-2019 30-Jun-2020 31-Dec-2023 IN00855594 New (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 1.00 7.00 Date 01-Jan-2017 31-Dec-2019 30-Jun-2020 31-Dec-2023 IN00855596 ►Number of markets/distribution centers connected to provincial market information platform (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 8.00 Date 01-Jan-2017 31-Dec-2019 30-Jun-2020 31-Dec-2023 Component 3: Support Services for the Whole Distribution System IN00855589 ►Number of person days for training of market/distribution center managers, staff and traders (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 180.00 180.00 11,900.00 Date 01-Jan-2017 31-Dec-2019 30-Jun-2020 31-Dec-2023 Component 4: Project Management, Monitoring and Evaluation IN00855590 ►Percentage of residents in Project areas reporting that they are consulted about the Project (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 80.00 Date 01-Jan-2017 31-Dec-2019 30-Jun-2020 31-Dec-2023 8/3/2020 Page 5 of 7 The World Bank Implementation Status & Results Report Jiangxi Farm Produce Distribution System Development (P147009) Performance-Based Conditions Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P147009 IBRD-88000 Effective USD 150.00 150.00 0.00 11.38 138.62 7.6% Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P147009 IBRD-88000 Effective 15-Dec-2017 05-Mar-2018 15-May-2018 31-Dec-2023 31-Dec-2023 Cumulative Disbursements PBC Disbursement Achievement Disbursed amount in Disbursement % PBC ID PBC Type Description Coc PBC Amount Status Coc for PBC 8/3/2020 Page 6 of 7 The World Bank Implementation Status & Results Report Jiangxi Farm Produce Distribution System Development (P147009) Restructuring History There has been no restructuring to date. Related Project(s) There are no related projects. 8/3/2020 Page 7 of 7