P128534 Safety Nets Project Procurement Plan June 1st 2017 I. General 1. Bank’s approval Date of the procurement Plan: February 5, 2013 (initial): Revision 12 of Updated Procurement Plan, April 20, 2017 2. Date of General Procurement Notice: Nov 24, 2014 3. Period covered by this procurement plan: The procurement period of project covered from year November 2016 to March 2018 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Comments Threshold US$ 1. NCB (Goods) Above or equal US$ 10 million 2. NCB (Works) Above or equal US$ 10 million 3. NCB (Non-Consultant Above or equal Services) US$ 2 million 4. Individual (Goods) Above or equal Justification to be US$ 10 million included in the PP 5. Individual (Non Consultant Above or equal Justification to be Services) US$ 2 million included in the PP 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: 4. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for the Safety Nets Project issued on January 2014 by Project Coordination Unit. 1 5. Any Other Special Procurement Arrangements: Not Applicable 6. Summary of the Procurement Packages planned during the 18 months of the current Procurement Plan-November 2016 to March 2018 (including those that are subject to retroactive financing and advanced procurement) 1 2 3 4 5 6 7 Ref. Descripti Estimat Packages Dome Review Comme No. on ed stic by Bank nts Cost Prefe (Prior / US$ rence Post) million (yes/ no) 1 Summary 0 0 No No of the ICB (Works) 2 Summary 0 0 No No of the ICB (Goods) 3 Summary 0 0 No No of the NCB (Works) 4 Summary 1.5 18 No Post of the NCB (Goods) 5 Summary 0.74 2 No Prior of the NCB (Non- Consultant Services) 6 Summary 0.51 16 No Post of the NCB (Non- Consultant Services) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comments Threshold 1. Competitive Methods (Firms) Above or equal US$ 1 million 2 2 Competitive Methods Above or equal (Individual) US$ 0.3 million 3 Single Source (Firms) Above or equal Justification to be US$ 1 million included in the PP 4 Single Source (Individual) Above or equal Justification to be US$ 0.3 million included in the PP 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than US$_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: Not applicable 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description Estimat Package Review Comment of ed s by Bank s Assignmen Cost (Prior / t US$ Post) million 1 Summary 1.7 8 Prior LCS; SSS; of number CQS; of Individual contracts ; that will be let under other methods 2 Summary 2 72 Post SSS; of number CQS; of Individual contracts that will be let under other methods 3 4 PROCUREMENT Cameroon : Cameroon Social Safety Nets PLAN General Information Country: Cameroon Bank’s Approval Date of the Original Procurement Plan: 2017-02-14 Revised Plan Date(s): (comma delineated, leave blank if none)2021-10-14 Project ID: P128534 GPN Date: Project Name: Cameroon Social Safety Nets Loan / Credit No: IDA / 52240, IDA / 62230, IDA / D2980 Executing Agency(ies):UNITE DE GESTION DU PROJET FILETS SOCIAUX WORKS Activity Reference No. / Procurement Estimated Actual Draft Pre- Draft Bidding Bid Evaluation Report Loan / Credit Market Procurement Prequalificatio High SEA/SH Process Prequalification Specific Procurement Bidding Documents Proposal Submission Contract Description Component Review Type Method Document Amount Amount qualification Document / and Signed Contract No. Approach Process n (Y/N) Risk Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Completion Type (US$) (US$) Documents Justification Recommendation for Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PlannedAwardActual Planned Actual Planned CM-UGP-PFS-26069-CW- Laying the Foundations of RFQ / Aménagement des a Safety Net System and Demande de Single Stage - One 2018-04- 2018-08- 2018-04- 2018-10- 2018-05- IDA / 52240 A posteriori Limited 8,300.00 7,209.40 Achevé bureaux de l'antenne Supporting Project prix Envelope 01 29 24 05 15 régionale du Nord ouest Management GOODS Activity Reference No. / Draft Pre- Draft Bidding Bid Evaluation Report Loan / Credit Market Procurement Prequalificatio Estimated Actual Process Prequalification Specific Procurement Bidding Documents Proposal Submission Description Component Review Type Method qualification Document / and Signed Contract Contract Completion No. Approach Process n (Y/N) Amount (US$) Amount (US$) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Documents Justification Recommendation for Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PlannedAwardActual Planned Actual Planned Actual CM-UGP-PFS-5831-GO- Laying the Foundations of RFB / fourniture du matériel a Safety Net System and Single Stage - One 2017-01- 2017-02- 2017-01- 2017-03- 2017-01- 2017-04- 2017-02- 2017-05- 2017-04- 2017-11- 2017-05- informatique, de IDA / 52240 A posteriori Appel d'offres Open - National 253,000.00 243,616.43 Achevé Supporting Project Envelope 24 01 29 12 24 11 10 16 17 12 08 téléphonie, et d'équipement Management de bureau (en 3 lots distincts) CM-UGP-PFS-6172-GO- RFQ / Fourniture du matériel de la phase 3 des Demande de Single Stage - One 2017-02- 2017-02- 2017-04- 2017-03- 2017-05- 2017-04- THIMO dans 2 communes IDA / 52240 Public Works Program Pilot A posteriori Limited 188,000.00 159,198.65 Achevé prix Envelope 18 10 15 10 15 14 de la région de l'Extrême Nord et 2 communes de la région de l'EST CM-UGP-PFS-6231-GO- RFQ / Fourniture des boîtes à pharmacie de la phase 3 Demande de Single Stage - One 2017-02- 2017-03- 2017-04- 2017-04- 2017-05- 2017-04- des THIMO pour 2 IDA / 52240 Public Works Program Pilot A posteriori Limited 29,000.00 31,172.51 Achevé prix Envelope 20 03 17 07 01 14 communes de la région de l'Extrême Nord et 2 communes de la région de l'Est CM-UGP-PFS-6307-GO- Laying the Foundations of RFQ / Fourniture des a Safety Net System and Demande de Single Stage - One 2017-03- 2017-05- 2018-05- IDA / 52240 A posteriori Limited 60,000.00 0.00 Annulé fournitures de bureau au Supporting Project prix Envelope 20 15 10 Projet Filets Sociaux Management CM-UGP-PFS-7392-GO- Laying the Foundations of RFQ / Fourniture des a Safety Net System and Single Stage - One 2017-05- 2016-12- 2017-06- 2017-07- 2017-08- 2017-09- 2017-10- IDA / 52240 A posteriori Appel d'offres Open - National 130,000.00 0.00 Annulé consommables Supporting Project Envelope 31 12 05 17 16 20 20 informatiques Management CM-UGP-PFS-16931-GO- Laying the Foundations of RFQ / fourniture des pièces a Safety Net System and Demande de Single Stage - One 2017-06- 2017-08- 2017-07- 2017-08- 2017-08- IDA / 52240 A posteriori Open - National 37,500.00 32,502.70 Achevé de rechange pour véhicules Supporting Project prix Envelope 19 14 17 28 17 et motos du Projet Filets Management Sociaux CM-UGP-PFS-23000-GO- RFQ / fourniture des boites à pharmacie pour la phase Demande de Single Stage - One 2017-08- 2017-09- 2017-10- 2017-10- 2018-04- 2017-10- 4 des THIMO dans 2 IDA / 52240 Public Works Program Pilot A posteriori Limited 25,100.00 21,014.35 Achevé prix Envelope 15 04 13 16 11 24 communes de la région de l'Adamaoua et 1 commune de la région du Nord CM-UGP-PFS-25708-GO- Laying the Foundations of RFQ / Fourniture du a Safety Net System and Demande de Single Stage - One 2017-11- 2018-03- 2017-12- 2018-04- 2018-01- 2018-04- IDA / 52240 A posteriori Limited 8,300.00 6,813.69 Achevé mobilier de bureau de Supporting Project prix Envelope 09 22 12 06 02 12 l'antenne du Nord-Ouest Management CM-UGP-PFS-25990-GO- RFQ / Fourniture des boites à pharmacie de la phase 5 Demande de Single Stage - One 2017-10- 2018-03- 2017-11- 2018-04- 2017-12- 2018-04- des THIMO pour 2 IDA / 52240 Public Works Program Pilot A posteriori Limited 25,100.00 20,966.02 Achevé prix Envelope 12 01 10 03 01 13 communes de la région de l'Est et 2 communes de la région du Nord ouest CM-UGP-PFS-26037-GO- Laying the Foundations of RFQ / Fourniture des a Safety Net System and Demande de Single Stage - One 2017-09- 2018-06- 2017-10- 2018-07- 2017-10- 2018-07- IDA / 52240 A posteriori Limited 2,000.00 2,081.57 Achevé autocollants pour voitures Supporting Project prix Envelope 27 11 16 05 30 19 et motos au Projet Filets Management Sociaux CM-UGP-PFS-23003-GO- RFQ / Fourniture du matériel et des matériaux Demande de Single Stage - One 2017-09- 2017-09- 2017-10- 2017-10- 2017-10- 2017-11- IDA / 52240 Public Works Program Pilot A posteriori Limited 100,000.00 90,128.08 Achevé de travail pour la phase 4 prix Envelope 11 04 03 16 24 22 des THIMO dans 2 communes de la région de l'Adamaoua CM-UGP-PFS-25561-GO- Laying the Foundations of RFB / Fourniture du a Safety Net System and Single Stage - One 2017-09- 2017-04- 2017-09- 2017-09- 2017-06- 2017-09- 2017-07- 2017-09- 2017-08- 2017-10- matériel roulant autos et IDA / 52240 A posteriori Appel d'offres Open - National 162,000.00 143,614.65 Signé Supporting Project Envelope 01 28 01 01 29 01 07 08 31 08 motos au projet Filets Management Sociaux en deux lots distincts CM-UGP-PFS-25477-GO- Cash Transfer Program Demande de Single Stage - One 2017-10- 2017-11- 2017-11- 2017-12- 2017-11- 2018-01- RFQ / Fourniture des seaux IDA / 52240 with Accompanying A posteriori Limited 38,000.00 26,101.20 Achevé prix Envelope 09 13 06 20 27 24 au Projet Filets Sociaux Measures to Boost Household Productivity CM-UGP-PFS-25475-GO- RFQ / Fourniture du matériel et des matériaux Demande de Single Stage - One 2017-09- 2017-09- 2017-09- 2017-11- 2017-10- 2017-11- IDA / 52240 Public Works Program Pilot A posteriori Limited 61,000.00 50,255.93 Achevé de travail pour la phase 4 prix Envelope 02 04 24 14 15 23 des THIMO dans la région du nord , commune de Touboro CM-UGP-PFS-47595-GO- RFQ / Fourniture du matériel de la phase 6 des Demande de Single Stage - One 2018-06- 2018-08- 2018-07- 2018-09- 2018-08- 2018-10- IDA / 52240 Public Works Program Pilot A posteriori Limited 80,275.00 65,428.39 Achevé THIMO du Projet Filets prix Envelope 18 31 30 27 29 18 Sociaux dans les communes de Dembo et Bashéo, région du Nord CM-UGP-PFS-47606-GO- RFB / Fourniture et paramétrage d'un progiciel Cash Transfer Program de gestion intégré pour la with Accompanying Single Stage - One 2018-06- 2018-06- 2018-07- 2018-08- 2018-09- 2019-03- IDA / 52240 A posteriori Appel d'offres Open - National 167,500.00 0.00 Annulé planification, la Measures to Boost Envelope 21 26 27 17 14 13 programmation, la Household Productivity budgétisation, le suivi évaluation et la production des rapports et indicateurs CM-UGP-PFS-47608-GO- Cash Transfer Program RFQ / Fourniture des with Accompanying Demande de Single Stage - One 2018-03- 2018-05- 2018-05- IDA / 52240 A posteriori Limited 48,400.00 0.00 Annulé logiciels informatiques au Measures to Boost prix Envelope 27 08 29 projet Filets Sociaux Household Productivity CM-UGP-PFS-16933-GO- RFQ / Fourniture des Cash Transfer Program seaux, Tee shirt, casquettes with Accompanying Demande de Single Stage - One 2017-06- 2017-08- 2017-09- IDA / 52240 A posteriori Open - National 193,700.00 0.00 Annulé autocollants pour véhicules Measures to Boost prix Envelope 20 15 14 estampillés Projet Filets Household Productivity Sociaux CM-UGP-PFS-25989-GO- RFQ / Fourniture du matériel et des matériaux Demande de Single Stage - One 2018-04- 2018-03- 2018-05- 2018-04- 2018-06- 2018-04- IDA / 52240 Public Works Program Pilot A posteriori Limited 80,275.00 72,952.92 Achevé de travail pour la phase 5 prix Envelope 06 01 05 03 04 20 des THIMO dans 2 communes de la région du Nord ouest (Oku et Ako) CM-UGP-PFS-25987-GO- RFQ / Fourniture du matériel et des matériaux Demande de Single Stage - One 2018-04- 2018-03- 2018-05- 2018-04- 2018-06- 2018-04- IDA / 52240 Public Works Program Pilot A posteriori Limited 80,275.00 65,815.47 Achevé de travail pour la phase 5 prix Envelope 06 01 05 03 04 24 des THIMO dans 2 communes de la région de l'EST (Bétaré OYA et Batouri) CM-UGP-PFS-25491-GO- Laying the Foundations of RFQ / Fourniture du a Safety Net System and Demande de Single Stage - One 2018-04- 2018-05- 2019-05- IDA / 52240 A posteriori Limited 30,000.00 0.00 Annulé matériel de pause café au Supporting Project prix Envelope 19 24 24 Projet Filets Sociaux Management CM-UGP-PFS-47578-GO- Cash Transfer Program RFQ / Fourniture des pneus with Accompanying Demande de Single Stage - One 2018-06- 2019-01- 2018-07- 2019-03- 2018-08- 2019-03- IDA / 52240 A posteriori Limited 28,400.00 24,340.71 Achevé de recharge pour des autos Measures to Boost prix Envelope 04 24 16 04 06 28 et motos du Projet Household Productivity CM-UGP-PFS-25476-GO- Cash Transfer Program RFQ / Fourniture des tee- with Accompanying Demande de Single Stage - One 2017-12- 2018-01- 2017-12- 2018-03- 2018-01- 2018-03- shirts et casquettes IDA / 52240 A posteriori Limited 99,000.00 68,943.69 Achevé Measures to Boost prix Envelope 02 24 26 01 16 29 estampillés au Projet Filets Household Productivity Sociaux CM-UGP-PFS-25488-GO- Laying the Foundations of RFQ / fourniture des encres a Safety Net System and Demande de Single Stage - One 2018-01- 2018-03- 2018-02- 2018-05- 2019-02- 2018-12- IDA / 52240 A posteriori Limited 100,000.00 83,622.13 Achevé pour imprimantes et Supporting Project prix Envelope 03 29 10 22 10 20 photocopieurs Management CM-UGP-PFS-25487-GO- Laying the Foundations of RFQ / Fourniture des a Safety Net System and Demande de Single Stage - One 2017-09- 2017-10- 2018-10- IDA / 52240 A posteriori Limited 60,000.00 0.00 Annulé fournitures de bureau au Supporting Project prix Envelope 16 11 11 Projet Filets sociaux Management CM-UGP-PFS-67485-GO- RFQ / Fourniture du Laying the Foundations of matériel informatique et de a Safety Net System and Demande de Single Stage - One 2018-07- 2018-07- 2018-08- 2018-07- 2018-09- 2018-08- IDA / 52240 A posteriori Limited 8,250.00 6,993.13 Achevé bureautique de l'antenne Supporting Project prix Envelope 15 05 19 30 02 06 régionale du projet du Nord Management Ouest CM-UGP-PFS-67490-GO- Laying the Foundations of RFQ / Fourniture des a Safety Net System and Demande de Single Stage - One 2018-07- 2018-07- 2018-08- 2018-07- 2019-08- 2018-08- IDA / 52240 A posteriori Limited 8,250.00 3,525.35 Achevé polices d'assurance aux 40 Supporting Project prix Envelope 10 02 14 25 14 29 premières motos du projet Management CM-UGP-PFS-47597-GO- RFQ / Fourniture des boîtes Demande de Single Stage - One 2018-09- 2018-08- 2018-09- 2018-09- 2018-10- 2018-09- à pharmacie de la phase 6 IDA / 52240 Public Works Program Pilot A posteriori Limited 8,360.00 7,383.31 Achevé prix Envelope 09 29 30 14 07 19 des THIMO du Projet Filets Sociaux CM-UGP-PFS-75801-GO- Cash Transfer Program RFQ / Fourniture du with Accompanying Demande de Single Stage - One 2018-09- 2018-10- 2018-10- 2018-10- 2018-10- 2018-10- IDA / 52240 A posteriori Limited 8,360.00 7,144.10 Achevé matériel pour les crèches Measures to Boost prix Envelope 15 01 10 24 17 31 temporaires au PFS Household Productivity CM-UGP-PFS-130190-GO- RFQ / Fourniture des Laying the Foundations of licences pour la plateforme a Safety Net System and Demande de Single Stage - One 2019-10- 2019-09- 2019-12- 2019-11- 2020-06- tomate ( Licence IDA / 62230 A posteriori Limited 34,000.00 29,607.05 Signé Supporting Project prix Envelope 10 30 13 18 10 Multiprojet, Monosite et Management Multiposte Tom2pro, Tom2monitoring, Tom2paie et Tom2marché) CM-UGP-PFS-121205-GO- Laying the Foundations of RFB / Fourniture des a Safety Net System and Demande de Single Stage - One 2019-10- 2019-09- 2019-11- 2019-11- 2020-03- IDA / 52240 A posteriori Limited 80,000.00 62,547.39 Signé consommables Supporting Project prix Envelope 05 30 23 18 22 informatiques au Projet Management Filets Sociaux CM-UGP-PFS-121383-GO- Laying the Foundations of RFQ / Acquisition des a Safety Net System and Demande de Single Stage - One 2019-10- 2019-09- 2019-12- 2019-11- 2020-04- fournitures de bureaux et IDA / 62230 A posteriori Limited 40,000.00 26,447.17 Signé Supporting Project prix Envelope 14 30 16 18 14 des produits d'entretien de Management bureau en deux lots distincts CM-UGP-PFS-120445-GO- UN / FOURNITURE DE 756 TABLETTES BIOMETRIQUES Laying the Foundations of Passation de MOBILES et 756 BATTERIE a Safety Net System and marchés auprès 2019-11- 2019-07- 2019-12- 2019-06- 2020-02- 2019-11- 2020-08- EXTERNES TYPES IDA / 62230 A posteriori Direct 660,808.00 660,808.00 Signé Supporting Project des agences de 30 31 14 07 02 13 20 POWERBANK ET 756 SACS Management l'ONU PHOTOVOLTAÏQUES en deux tranches de 400 et 356 chacune CM-UGP-PFS-171977-GO- RFB / Fourniture du matériel THIMO de la Single Stage - One 2020-06- 2020-06- 2020-07- 2020-08- 2020-07- 2020-09- 2020-08- 2020-10- 2020-09- 2020-11- 2021-02- IDA / D2980 Public Works Program Pilot A posteriori Appel d'offres Open - National 267,580.00 187,352.13 Achevé phase 7 des Travaux à Envelope 30 17 05 16 28 15 14 20 21 10 16 Haute Intensité de Main d'œuvre en 4 lots distincts Page 1 CM-UGP-PFS-172000-GO- RFQ / Fourniture des boîtes Demande de Single Stage - One En attente 2020-06- 2020-08- 2020-09- IDA / D2980 Public Works Program Pilot A posteriori Limited 41,800.00 0.00 à pharmacie de la phase 7 prix Envelope d'exécution 20 26 09 des THIMO en 3 lots distincts CM-UGP-PFS-172036-GO- Laying the Foundations of RFQ / Fourniture de 50 a Safety Net System and Demande de Single Stage - One En cours 2020-06- 2020-08- 2020-08- 2020-09- IDA / 62230 A posteriori Limited 37,500.00 0.00 mini groupes électrogènes Supporting Project prix Envelope d'exécution 20 14 19 02 au Projet Filets Sociaux Management CM-UGP-PFS-172065-GO- Laying the Foundations of RFB / Fourniture des a Safety Net System and Single Stage - One En cours 2020-12- 2021-01- 2020-12- 2021-02- 2021-03- 2021-04- 2022-04- consommables IDA / 52240 A posteriori Appel d'offres Open - National 160,000.00 0.00 Supporting Project Envelope d'exécution 15 08 25 05 07 11 11 informatiques à l'unité de Management Gestion du Projet Filets Sociaux CM-UGP-PFS-172069-GO- Laying the Foundations of RFQ / Fourniture du a Safety Net System and Demande de Single Stage - One En attente 2021-01- 2021-03- 2021-03- mobilier de bureau et d’un IDA / 62230 A posteriori Limited 14,820.00 0.00 Supporting Project prix Envelope d'exécution 20 01 15 coffre-fort pour l’Unité de Management Gestion du Projet Filets Sociaux CM-UGP-PFS-172042-GO- Laying the Foundations of RFB / Fourniture de 4 a Safety Net System and Demande de Single Stage - One En cours 2021-01- 2021-03- 2021-04- IDA / 62230 A posteriori Open - National 200,000.00 0.00 véhicules pick up double Supporting Project prix Envelope d'exécution 06 10 09 cabine au Projet Filets Management Sociaux CM-UGP-PFS-172008-GO- RFQ / Fourniture et Demande de Single Stage - One 2020-05- 2020-07- 2020-08- équipement du matériel de IDA / D2980 Public Works Program Pilot A posteriori Limited 50,000.00 0.00 Annulé prix Envelope 20 26 09 crèche de la Phase 7 des THIMO en 3 lots CM-UGP-PFS-213727-GO- RFQ / Fourniture des boîtes à pharmacie des phases 8 Demande de Single Stage - One En cours 2021-05- 2021-04- 2021-06- 2021-07- et 9 des Travaux à Haute IDA / 62230 Public Works Program Pilot A posteriori Limited 50,160.00 0.00 prix Envelope d'exécution 05 08 30 30 intensité de main d'œuvre du Projet Filets Sociaux en deux 2 lots distincts CM-UGP-PFS-205171-GO- Cash Transfer Program RFQ / Recrutement du with Accompanying Demande de Single Stage - One En attente 2021-05- 2021-06- 2021-07- prestataire pour la IDA / D2980 A posteriori Limited 15,251.00 0.00 Measures to Boost prix Envelope d'exécution 05 30 14 fourniture des lecteurs MP3 Household Productivity et des baffles CM-UGP-PFS-217839-GO- Laying the Foundations of RFQ / Fourniture de deux a Safety Net System and Demande de Single Stage - One 2021-02- 2021-02- 2021-04- 2021-03- 2021-04- IDA / 62230 A posteriori Limited 8,380.00 7,603.68 Signé photocopieurs en Urgence Supporting Project prix Envelope 27 12 10 05 24 au Projet Filets Sociaux Management CM-UGP-PFS-211488-GO- RFB / Fourniture du Matériel des phases 8 et 9 Single Stage - One En attente 2021-02- 2021-02- 2021-03- 2021-04- 2021-06- 2021-07- IDA / 62230 Public Works Program Pilot A posteriori Appel d'offres Open - National 321,096.00 0.00 des Travaux à Haute Envelope d'exécution 10 15 29 28 02 02 Intensité de Main d'Œuvre (THIMO) en 4 lots distincts CM-UGP-PFS-222852-GO- Laying the Foundations of RFB / Acquisition des a Safety Net System and Single Stage - One En attente 2021-04- 2021-04- 2021-06- 2021-06- 2021-07- 2022-07- fournitures de bureaux et IDA / 62230 A posteriori Appel d'offres Open - National 269,944.00 0.00 Supporting Project Envelope d'exécution 15 20 04 19 24 24 des produits d'entretien de Management bureau en deux lots distincts CM-UGP-PFS-233020-GO- Laying the Foundations of RFQ / Fourniture et a Safety Net System and Demande de Single Stage - One En attente 2021-06- 2021-08- 2021-09- installation du dispositif de IDA / 62230 A posteriori Limited 27,600.00 0.00 Supporting Project prix Envelope d'exécution 25 21 20 vidéoconférence avec Management abonnement Zoom et webex CM-UGP-PFS-233101-GO- RFB / Fourniture du matériel de la phase 10 Single Stage - One En attente 2021-06- 2021-07- 2021-08- 2021-09- 2021-10- 2021-11- IDA / 62230 Public Works Program Pilot A posteriori Appel d'offres Open - National 227,443.00 0.00 des Travaux à Haute Envelope d'exécution 30 07 18 17 22 21 Intensité de Main d'œuvre du Projet Filets Sociaux en 2 lots distincts CM-UGP-PFS-241556-GO- RFQ / Fourniture du Cash Transfer Program matériel des crèches with Accompanying Demande de Single Stage - One En attente 2021-08- 2021-09- 2021-09- IDA / 62230 A posteriori Limited 8,384.00 0.00 temporaires des phases 8 Measures to Boost prix Envelope d'exécution 04 04 18 et 9 des Travaux à Haute Household Productivity Intensité de Main d'œuvre (THIMO) CM-UGP-PFS-233093-GO- RFQ / Fourniture des boîtes à pharmacie de phase 10 des Travaux à Haute Demande de Single Stage - One En attente 2021-08- 2021-10- 2021-11- IDA / 62230 Public Works Program Pilot A posteriori Limited 35,530.00 0.00 intensité de main d'œuvre prix Envelope d'exécution 30 25 24 du Projet Filets Sociaux dans les régions de l’Extrême Nord, du Nord et de l’Adamaoua CM-UGP-PFS-232884-GO- RFQ / Fourniture du 2150 Laying the Foundations of kits de formation et de a Safety Net System and Demande de Single Stage - One En attente 2021-08- 2021-10- 2021-11- travail, pour les équipes de IDA / D2980 A posteriori Limited 43,000.00 0.00 Supporting Project prix Envelope d'exécution 13 15 05 terrain dans le cadre de Management l'accompagnement des bénéficiaires CM-UGP-PFS-241685-GO- RFB / Fourniture du matériel de travail de la phase 10 des Travaux à Single Stage - One En attente 2021-08- 2021-09- 2021-10- 2021-11- 2021-12- 2022-02- IDA / 62230 Public Works Program Pilot A posteriori Appel d'offres Open - National 227,443.00 0.00 Haute intensité de main Envelope d'exécution 30 04 16 15 20 03 d'œuvre (THIMO) dans les régions de l'Adamaoua, du Nord et de l'Extrême Nord en 3 lots distincts CM-UGP-PFS-239622-GO- RFQ / Fourniture d'un Laying the Foundations of scanner et d'un copieur en a Safety Net System and Demande de Single Stage - One En attente 2021-08- 2021-09- 2021-10- IDA / 62230 A posteriori Limited 19,500.00 0.00 procédure d'urgence pour Supporting Project prix Envelope d'exécution 17 28 12 la passation des marchés Management du Projet Filets Sociaux CM-UGP-PFS-170601-GO- RFB / Fourniture du Laying the Foundations of matériel informatique, du a Safety Net System and Single Stage - One En attente 2021-10- 2021-10- 2021-11- 2021-12- 2022-02- 2022-03- IDA / 62230 A posteriori Appel d'offres Open - National 480,040.00 0.00 matériel de téléphonie et Supporting Project Envelope d'exécution 01 15 29 29 08 25 des logiciels informatiques Management au Projet Filets Sociaux en 3 lots distincts CM-UGP-PFS-172070-GO- Laying the Foundations of RFQ / Fourniture des Pneus a Safety Net System and Demande de Single Stage - One En attente 2021-11- 2021-12- 2022-01- et pièces de rechange des IDA / 62230 A posteriori Limited 28,386.00 0.00 Supporting Project prix Envelope d'exécution 04 23 06 véhicules du Projet Filets Management Sociaux CM-UGP-PFS-25491-GO- Laying the Foundations of RFQ-2 / Fourniture du a Safety Net System and Demande de Single Stage - One En attente 2021-12- 2022-01- 2023-01- IDA / 62230 A posteriori Limited 15,000.00 0.00 nécessaire de pause café au Supporting Project prix Envelope d'exécution 14 18 18 projet Filets Sociaux Management CM-UGP-PFS-172043-GO- RFB / Fourniture du matériel productif pour les Cash Transfer Program sanctions positives with Accompanying Single Stage - One En attente 2020-12- 2020-12- 2021-02- 2021-03- 2021-04- 2022-04- IDA / 62230 A posteriori Appel d'offres Open - National 482,400.00 0.00 (machettes et limes, Measures to Boost Envelope d'exécution 15 25 05 07 11 11 machines à écraser avec Household Productivity bancs, brouettes) au Projet Filets Sociaux en trois lots distincts NON CONSULTING SERVICES Activity Reference No. / Draft Pre- Draft Bidding Bid Evaluation Report Loan / Credit Market Procurement Prequalificatio Estimated Actual Process Prequalification Specific Procurement Bidding Documents Proposal Submission Description Component Review Type Method qualification Document / and Signed Contract Contract Completion No. Approach Process n (Y/N) Amount (US$) Amount (US$) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Documents Justification Recommendation for Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PlannedAwardActual Planned Actual Planned Actual CM-UGP-PFS-6232-NC- RFQ / Recrutement des Demande de Single Stage - One 2017-02- 2017-02- 2017-04- 2017-04- 2017-12- IDA / 52240 Public Works Program Pilot A posteriori Limited 60,000.00 61,263.97 Signé agences de paiement pour prix Envelope 15 10 12 24 08 les phases 3 et 4 des THIMO en lots CM-UGP-PFS-6233-NC- RFQ / Recrutement des agences de paiement pour le paiement de 19500 Cash Transfer Program ménages bénéficiaires du with Accompanying Demande de Single Stage - One 2017-03- 2017-05- 2019-04- cycle 2 des transferts IDA / 52240 A priori Limited 351,000.00 0.00 Annulé Measures to Boost prix Envelope 07 05 25 monétaires dont 7500 dans Household Productivity la région de l'Extrême Nord, 5500 dans les régions du Nord et de l'Adamaoua, et 6500 dans les régions de l'Est, du Nord CM-UGP-PFS-6315-NC- Cash Transfer Program Demande de Single Stage - One 2017-02- 2017-04- 2017-04- 2017-05- 2017-05- 2017-06- RFQ / Impression des IDA / 52240 with Accompanying A posteriori Limited 70,000.00 22,001.63 Achevé prix Envelope 25 21 22 26 06 19 documents du Projet Measures to Boost Household Productivity Laying the Foundations of CM-UGP-PFS-6306-NC- a Safety Net System and Demande de Single Stage - One 2017-03- 2017-03- 2017-04- 2017-06- 2018-04- 2018-06- RFQ / fourniture des IDA / 52240 A posteriori Limited 123,900.00 58,410.90 Achevé Supporting Project prix Envelope 03 06 28 07 23 08 polices d'assurance maladie Management CM-UGP-PFS-7385-NC- Laying the Foundations of RFQ / Fourniture des a Safety Net System and Demande de Single Stage - One 2017-03- 2017-03- 2017-04- 2017-06- 2018-04- 2018-06- IDA / 52240 A posteriori Limited 31,100.00 18,329.45 Achevé polices d'assurance Supporting Project prix Envelope 03 06 28 15 23 14 automobile Management CM-UGP-PFS-14464-NC- Laying the Foundations of RFQ / Renouvellement du a Safety Net System and Demande de Single Stage - One 2017-06- 2018-07- 2017-06- 2018-07- 2018-06- IDA / 52240 A posteriori Limited 8,250.00 3,553.09 Signé contrat d'assurance des 40 Supporting Project prix Envelope 13 17 19 25 14 motos en circulation Management Laying the Foundations of CM-UGP-PFS-25608-NC- a Safety Net System and Demande de Single Stage - One 2017-10- 2017-10- 2018-10- RFQ / Maintenance Autos IDA / 52240 A posteriori Limited 8,300.00 0.00 Annulé Supporting Project prix Envelope 04 31 31 UGP pour 1 an Management CM-UGP-PFS-25616-NC- Laying the Foundations of RFQ / Maintenance matériel a Safety Net System and Demande de Single Stage - One 2017-10- 2017-11- 2018-11- IDA / 52240 A posteriori Limited 8,300.00 0.00 Annulé bureautique et Supporting Project prix Envelope 07 07 07 informatique UGP pour 1 an Management CM-UGP-PFS-25623-NC- Laying the Foundations of RFQ / Maintenance froid et a Safety Net System and Demande de Single Stage - One 2017-10- 2017-11- 2018-11- IDA / 52240 A posteriori Limited 8,300.00 0.00 Annulé climatisation UGP pour 1 Supporting Project prix Envelope 11 09 09 an Management CM-UGP-PFS-25711-NC- Laying the Foundations of RFQ / Fourniture du service a Safety Net System and Demande de Single Stage - One 2017-12- 2018-04- 2018-01- 2018-07- 2019-01- IDA / 52240 A posteriori Limited 6,000.00 8,986.03 Signé de gardiennage pour Supporting Project prix Envelope 09 20 09 10 09 l'antenne régionale du Nord Management Ouest CM-UGP-PFS-25729-NC- Laying the Foundations of RFQ / Fourniture des a Safety Net System and Demande de Single Stage - One 2017-10- 2018-02- 2017-11- 2018-03- 2017-12- 2018-07- systèmes de sécurité et de IDA / 52240 A posteriori Limited 4,000.00 1,315.18 Achevé Supporting Project prix Envelope 15 20 15 12 15 02 GPS et du service de Management tracking pour les autos CM-UGP-PFS-25892-NC- Laying the Foundations of RFQ / Confection et la pose a Safety Net System and Demande de Single Stage - One 2017-09- 2017-11- 2018-02- 2017-12- 2018-04- des plaques signalétiques IDA / 52240 A posteriori Open - National 4,000.00 7,636.09 Achevé Supporting Project prix Envelope 30 10 08 01 09 (7 plaques directionnelles + Management 3 panneaux) CM-UGP-PFS-25980-NC- Laying the Foundations of RFQ / Avenant au contrat a Safety Net System and Demande de Single Stage - One 2017-09- 2016-09- 2017-09- 2016-10- 2018-09- IDA / 52240 A posteriori Limited 6,000.00 14,850.36 Signé de l'agence de gardiennage Supporting Project prix Envelope 11 26 23 31 23 de l'antenne régionale du Management Nord CM-UGP-PFS-25981-NC- Laying the Foundations of RFQ / Avenant au contrat a Safety Net System and Demande de Single Stage - One 2017-09- 2016-06- 2017-09- 2016-07- 2018-09- de l'agence de gardiennage IDA / 52240 A posteriori Limited 5,000.00 16,374.35 Signé Supporting Project prix Envelope 11 24 23 28 23 de l'antenne régionale de Management l'Extrême Nord CM-UGP-PFS-25983-NC- RFQ / Avenant au contrat Laying the Foundations of d'assurance du personnel a Safety Net System and Demande de Single Stage - One 2017-09- 2017-10- 2017-10- 2017-12- 2018-08- 2018-06- IDA / 52240 A posteriori Limited 39,000.00 24,386.04 Achevé en vu de la prise en compte Supporting Project prix Envelope 15 19 16 20 12 08 du personnel nouvellement Management recruté CM-UGP-PFS-30748-NC- DIR / recrutement d'une agence de paiement Cash Transfer Program Passation de chargée d'assurer les with Accompanying 2017-10- 2018-01- 2017-10- 2017-11- 2017-11- 2018-02- 2018-11- 2019-07- IDA / 52240 A posteriori marché de gré à Direct 36,000.00 30,643.76 Achevé transferts monétaires des Measures to Boost 04 04 09 27 16 13 16 24 gré bénéficiaires de la phase 2 Household Productivity des transferts monétaires d'urgence du Projet Filets Sociaux Page 2 CM-UGP-PFS-37510-NC- RFQ / avenant Lettre de Marché N°009/LM/MINEPAT/CTS/P FS/UGP/CAPM/2017 du 26 Passation de 2017-12- 2018-01- 2017-12- 2018-01- 2018-01- 2018-02- 2018-05- mai 2017 de l'agence de IDA / 52240 Public Works Program Pilot A posteriori marché de gré à Direct 6,000.00 22,354.79 Signé 18 04 25 08 15 13 15 paiement pour la gré réalisation des paiements des 6000 bénéficiaires des THIMO 5 dont 3000 dans le Nord-Ouest et 3000 dans l'Est CM-UGP-PFS-37511-NC- RFQ / Avenant au contrat Laying the Foundations of d'assurance véhicule Passation de a Safety Net System and 2017-12- 2017-12- 2017-12- 2017-12- 2018-01- 2018-02- 2018-07- LETTRE DE MARCHE IDA / 52240 A posteriori marché de gré à Direct 4,000.00 1,207.48 Signé Supporting Project 18 22 23 22 09 13 08 N°011/LM/MINEPAT/CTS/P gré Management FS/UGP/CAPM/2017 DU 08 JUIN 2017 CM-UGP-PFS-25853-NC- DIR / Avenant au contrat de l'agence de paiement chargée des transferts monetaires du cycle 2 à Demande de Single Stage - One 2017-09- 2018-01- 2017-11- 2018-02- 2018-05- IDA / 52240 Public Works Program Pilot A posteriori Limited 23,400.00 22,232.85 Signé l'Est, le Nord ouest, Douala prix Envelope 25 08 20 13 19 et Yaoundé pour la phase 5 des THIMO dont 3000 dans la région de l'Est et 3000 dans la région du Nord Ouest CM-UGP-PFS-47580-NC- Cash Transfer Program RFQ / Fourniture de polices with Accompanying Demande de Single Stage - One 2018-03- 2018-06- 2018-05- 2018-08- 2019-05- IDA / 52240 A posteriori Limited 28,000.00 14,785.79 Signé d'assurance autos au projet Measures to Boost prix Envelope 31 11 26 22 26 Filets Sociaux Household Productivity CM-UGP-PFS-47582-NC- Cash Transfer Program RFQ / Confection et pause with Accompanying Demande de Single Stage - One 2018-04- 2018-08- 2018-06- 2018-09- 2018-07- 2018-11- des plaques signalétiques IDA / 52240 A posteriori Limited 8,250.00 7,009.83 Achevé Measures to Boost prix Envelope 30 23 11 12 11 23 des réalisations du Projet Household Productivity Filets Sociaux dans les communes CM-UGP-PFS-47593-NC- RFQ / Agence de paiement chargée d'assurer le Cash Transfer Program paiement des 3000 with Accompanying Demande de Single Stage - One 2018-05- 2018-07- 2019-07- IDA / 52240 A posteriori Limited 19,170.00 0.00 Annulé bénéficiaires de la phase 3 Measures to Boost prix Envelope 23 18 18 des transferts monétaires Household Productivity d'urgence du du Projet Filets Sociaux dans le Nord Ouest CM-UGP-PFS-47602-NC- DIR / Avenant au contrat de l'agence de paiement chargée d'assurer les paiement des transfert Passation de 2018-06- 2018-06- 2018-07- 2018-07- 2018-09- 2019-01- 2019-02- monétaires du cycle 2 dans IDA / 52240 Public Works Program Pilot A posteriori marché de gré à Direct 11,700.00 10,227.50 Achevé 21 26 20 31 12 27 26 le Nord et l'Adamaoua pour gré les paiements de 3000 bénéficiaire de la phase 6 des THIMO dans la région du Nord, communes de Dembo et Bashéo CM-UGP-PFS-25707-NC- Laying the Foundations of RFQ / Maintenance froid et a Safety Net System and Demande de Single Stage - One 2017-10- 2017-11- 2018-11- IDA / 52240 A posteriori Limited 5,000.00 0.00 Annulé climatisation EN et NO Supporting Project prix Envelope 09 07 07 pour 1 an Management CM-UGP-PFS-25610-NC- Laying the Foundations of RFQ / Maintenance des a Safety Net System and Demande de Single Stage - One 2017-10- 2017-10- 2018-10- IDA / 52240 A posteriori Limited 5,000.00 0.00 Annulé Autos et Motos de Supporting Project prix Envelope 04 31 31 l'Extrême-Nord Management CM-UGP-PFS-25612-NC- Laying the Foundations of RFQ / Maintenance des a Safety Net System and Demande de Single Stage - One 2017-09- 2017-09- 2018-09- IDA / 52240 A posteriori Limited 5,000.00 0.00 Annulé Autos et Motos du Projet du Supporting Project prix Envelope 03 30 30 Nord Management CM-UGP-PFS-25618-NC- Laying the Foundations of RFQ / Maintenance matériel a Safety Net System and Demande de Single Stage - One 2017-10- 2017-11- 2018-11- IDA / 52240 A posteriori Limited 5,000.00 0.00 Annulé bureautique et Supporting Project prix Envelope 07 03 03 informatique EN et NO pour Management 1 an CM-UGP-PFS-47255-NC- Cash Transfer Program RFQ / Production et with Accompanying Demande de Single Stage - One 2018-03- 2018-02- 2018-04- 2018-03- 2018-04- 2018-03- multiplication des IDA / 52240 A posteriori Limited 7,567.00 7,132.71 Achevé Measures to Boost prix Envelope 16 23 10 08 24 12 documents des Pratiques Household Productivity familiales essentielles CM-UGP-PFS-26101-NC- Laying the Foundations of RFQ / Maintenance des a Safety Net System and Demande de Single Stage - One 2017-10- 2017-11- 2018-11- IDA / 52240 A posteriori Limited 5,000.00 0.00 Annulé Autos et Motos du Nord- Supporting Project prix Envelope 11 13 13 Ouest Management Laying the Foundations of CM-UGP-PFS-6311-NC- a Safety Net System and Demande de Single Stage - One 2018-04- 2018-03- 2018-05- 2018-03- 2019-05- 2018-08- RFQ / Fourniture de police IDA / 52240 A posteriori Limited 8,250.00 3,228.19 Achevé Supporting Project prix Envelope 06 02 11 26 06 28 d'assurance pour 20 motos Management CM-UGP-PFS-26060-NC- Laying the Foundations of RFQ / Fourniture des a Safety Net System and Demande de Single Stage - One 2018-05- 2018-03- 2018-06- 2018-03- 2018-06- 2018-03- IDA / 52240 A posteriori Limited 8,500.00 1,867.92 Achevé Systèmes de sécurité pour Supporting Project prix Envelope 01 05 01 26 22 29 les motos du projet (20) Management CM-UGP-PFS-37512-NC- RFQ / Avenant N°2 au contrat d'assurance du Cash Transfer Program personnel pour la prise en Passation de with Accompanying 2018-03- 2018-03- 2018-04- 2018-03- 2018-05- 2018-04- 2018-10- compte des relais IDA / 52240 A posteriori marché de gré à Direct 30,000.00 34,099.31 Signé Measures to Boost 30 19 06 22 04 24 31 communautaires recrutés gré Household Productivity dans le cadre de la sensibilisation sur les pratiques familiales essentielles CM-UGP-PFS-47572-NC- Cash Transfer Program RFB / Fourniture des with Accompanying Demande de Single Stage - One 2018-05- 2018-06- 2018-07- 2018-10- 2019-07- IDA / 52240 A posteriori Limited 130,000.00 127,074.00 Signé polices d'assurance au Measures to Boost prix Envelope 07 11 02 05 02 personnel du Projet Filets Household Productivity Sociaux CM-UGP-PFS-72576-NC- RFQ / Multiplication de certains documents pour la collecte des données sur Laying the Foundations of les PFE de la phase pilote a Safety Net System and Demande de Single Stage - One 2018-09- 2018-09- 2018-10- 2018-09- 2018-11- 2018-10- pour une période de 6 mois IDA / 52240 A posteriori Limited 8,250.00 7,116.25 Achevé Supporting Project prix Envelope 16 05 28 27 11 01 et des questionnaires et Management autres documents pour la collecte des données dans le cadre de la première évaluation interne du Projet CM-UGP-PFS-92192-NC- Cash Transfer Program RFQ / Multiplication de with Accompanying Demande de Single Stage - One 2019-01- 2019-01- 2019-02- 2019-02- 2020-02- certains documents de IDA / 52240 A posteriori Limited 6,500.00 5,551.26 Signé Measures to Boost prix Envelope 15 17 26 04 26 collecte de données des PFE Household Productivity pour une période d'un an MOF-CM-UGP-PFS-6233- NC-RFQ / Recrutement des Cash Transfer Program agences de paiement pour with Accompanying Demande de Single Stage - One 2017-02- 2017-03- 2017-05- 2017-05- 2019-10- le paiement de 19500 IDA / 52240 A posteriori Limited 351,000.00 142,058.17 Signé Measures to Boost prix Envelope 27 08 01 26 28 menages beneficiaires du Household Productivity cycle 2 des transferts monetaires en 3 lots CM-UGP-PFS-121194-NC- Laying the Foundations of RFQ / Fourniture des a Safety Net System and Demande de Single Stage - One 2019-09- 2019-09- 2019-11- 2020-11- IDA / 62230 A posteriori Limited 28,000.00 0.00 Annulé polices d'assurance pour Supporting Project prix Envelope 10 06 05 04 les autos du Projet Filets Management Sociaux CM-UGP-PFS-121367-NC- RFB / FOURNITURE D’UNE Laying the Foundations of POLICE D'ASSURANCE a Safety Net System and Single Stage - One 2019-08- 2019-10- 2019-09- 2019-10- 2019-11- 2019-11- 2019-12- 2019-12- 2020-12- MALADIE POUR UN AN EN IDA / 62230 A posteriori Appel d'offres Open - National 164,000.00 0.00 Annulé Supporting Project Envelope 30 09 14 26 13 25 27 23 22 FAVEUR DU PERSONNEL DU Management PROJET FILETS SOCIAUX ET LEURS FAMILLES (2019- 2020) CM-UGP-PFS-152342-NC- Laying the Foundations of RFQ / FOURNITURE DES a Safety Net System and Demande de Single Stage - One 2020-02- 2020-04- 2020-07- 2021-04- POLICES D'ASSURANCE IDA / 62230 A posteriori Open - National 28,000.00 9,512.73 Signé Supporting Project prix Envelope 10 14 20 14 POUR SIX (06) VEHICULES Management DU PROJET FILETS SOCIAUX CM-UGP-PFS-143130-NC- RFQ / Recrutement d'une agence de paiement pour le transfert des paiements aux Demande de Single Stage - One En attente 2020-07- 2020-09- 2021-03- IDA / D2980 Public Works Program Pilot A posteriori Limited 13,500.00 0.00 3000 bénéficiaires de la prix Envelope d'exécution 10 20 19 phase 7 des Travaux à Haute Intensité de Main d'œuvre dans la commune de Mokolo CM-UGP-PFS-172111-NC- RFB / Fourniture d'une Laying the Foundations of police d'assurance maladie a Safety Net System and Single Stage - One 2020-06- 2020-06- 2020-06- 2020-07- 2020-07- 2020-08- 2020-09- 2020-10- 2020-10- 2021-10- IDA / 62230 A posteriori Appel d'offres Open - National 164,000.00 123,171.65 Signé pour un an en faveur du Supporting Project Envelope 01 25 16 28 30 27 01 01 16 01 personnel du Projet Filets Management Sociaux et leur famille CM-UGP-PFS-175637-NC- DIR / Agence de paiement des 6000 bénéficiaires du Cycle 3 des transferts Cash Transfer Program Monétaires Ordinaires, des Passation de with Accompanying 2020-06- 2018-05- 2020-07- 2020-08- 2020-08- 2020-09- 2022-09- 2000 de la phase 3 des IDA / D2980 A posteriori marché de gré à Direct 165,240.00 86,914.08 Signé Measures to Boost 30 01 05 14 23 11 02 Transferts Monétaires gré Household Productivity d’Urgence et des 3000 de la phase 7 des THIMO dans les Régions de l’Adamaoua et de l’Est en 3 lots distinct CM-UGP-PFS-175721-NC- DIR / Agence de paiement des bénéficiaires du Cycle 3 des transferts Monétaires Cash Transfer Program Passation de Ordinaires, de la phase 3 with Accompanying 2020-06- 2018-05- 2020-07- 2020-08- 2020-08- 2020-09- 2022-09- IDA / 62230 A posteriori marché de gré à Direct 237,960.00 115,704.37 Signé des Transferts Monétaires Measures to Boost 30 01 05 14 23 11 02 gré d’Urgence, de la phase 7 Household Productivity des Travaux à Haute Intensité de Main d'œuvre, Régions de l’Extrême Nord et du Nord CM-UGP-PFS-175722-NC- DIR / Agence de Paiement des bénéficiaires du cycle 3 des Transferts Monétaires Cash Transfer Program Ordinaires dans la Région Passation de with Accompanying 2020-06- 2018-05- 2020-07- 2020-08- 2020-08- 2020-09- 2022-09- du Sud, Communes IDA / 62230 A posteriori marché de gré à Direct 129,600.00 62,469.50 Signé Measures to Boost 30 01 05 14 23 11 02 d'Ebolawa 2 (1000), gré Household Productivity Meyomessala (1000) Ma’an (1000) et dans les ville de Douala et yaoundé communes de Douala 5 (1500),Yaoundé 3 (1500), CM-UGP-PFS-175723-NC- DIR / Agence de Paiement des bénéficiaires de la Cash Transfer Program Passation de phase 3 des Transferts with Accompanying 2020-06- 2020-07- 2020-08- 2022-09- IDA / 62230 A posteriori marché de gré à Direct 16,200.00 0.00 Annulé Monétaires d’Urgence dans Measures to Boost 30 05 23 02 gré la Région du Sud-Ouest, Household Productivity Communes de Limbe1 (500), Limbe 2 (500) Limbe 3 (500) CM-UGP-PFS-175725-NC- DIR / Agence de Paiement des bénéficiaires de la Cash Transfer Program Passation de phase 3 des Transferts with Accompanying 2020-06- 2020-07- 2020-08- 2022-09- IDA / 62230 A posteriori marché de gré à Direct 21,600.00 0.00 Annulé Monétaires d’Urgence dans Measures to Boost 30 05 23 02 gré la Région du Nord-Ouest, Household Productivity Communes de Bamenda 1 (500), Bamenda 2 (500) Bamenda 3 (1000) CM-UGP-PFS-172073-NC- Laying the Foundations of RFB / Impression et a Safety Net System and Single Stage - One En cours 2020-07- 2020-07- 2020-08- 2020-09- 2020-10- 2020-11- 2021-11- IDA / 62230 A posteriori Appel d'offres Open - National 260,942.64 0.00 reprographie des Supporting Project Envelope d'exécution 30 20 04 15 15 19 19 documents pour le Projet Management Filets Sociaux CM-UGP-PFS-172057-NC- Laying the Foundations of RFQ / Confection et pause a Safety Net System and Demande de Single Stage - One En attente 2021-04- 2021-05- 2021-11- IDA / 62230 A posteriori Limited 24,000.00 0.00 des plaques signalitiques Supporting Project prix Envelope d'exécution 09 28 24 du Projet Filets Sociaux Management CM-UGP-PFS-172112-NC- Laying the Foundations of RFQ / Fourniture d'une a Safety Net System and Demande de Single Stage - One En attente 2021-01- 2021-03- 2022-03- IDA / 62230 A posteriori Limited 12,000.00 0.00 police d'assurance pour 60 Supporting Project prix Envelope d'exécution 04 07 07 motos du Projet Filets Management Sociaux Laying the Foundations of CM-UGP-PFS-206581-NC- a Safety Net System and Demande de Single Stage - One 2021-03- 2021-04- 2022-04- RFQ / Entretien des motos IDA / 62230 A posteriori Limited 40,000.00 0.00 Annulé Supporting Project prix Envelope 03 28 28 du projet Filets Sociaux Management Page 3 CM-UGP-PFS-206582-NC- Laying the Foundations of RFQ / Entretien des a Safety Net System and Demande de En attente 2021-03- 2021-04- 2022-04- IDA / 62230 A posteriori 22,000.00 0.00 véhicules du Projet Filets Supporting Project prix d'exécution 03 28 28 Sociaux Management CM-UGP-PFS-172015-NC- RFQ / Recrutement des Demande de Single Stage - One 2020-07- 2020-09- 2021-09- agences de paiement pour IDA / D2980 Public Works Program Pilot A posteriori Limited 45,000.00 0.00 Annulé prix Envelope 05 09 09 la phase 7 des THIMO en 3 lots distincts CM-UGP-PFS-143140-NC- RFQ / Recrutement d'une agence de paiement pour le paiement des bénéficiaires de la phase 7 des Travaux Demande de Single Stage - One 2020-07- 2020-09- 2021-03- à Haute Intensité de Main IDA / D2980 Public Works Program Pilot A posteriori Limited 22,500.00 0.00 Annulé prix Envelope 10 26 25 d'œuvre du PFS dont 1000 dans la commune de Dir région de l'Adamaoua et 4000 dans la commune deTouboro, région du Nord CM-UGP-PFS-143142-NC- RFQ / Recrutement d'une agence de paiement pour le paiement des bénéficiaires de la phase 7 des Travaux Demande de Single Stage - One 2020-07- 2020-09- 2021-03- IDA / D2980 Public Works Program Pilot A posteriori Limited 9,000.00 0.00 Annulé à Haute Intensité de Main prix Envelope 10 20 19 d'œuvre du PFS dans la région de l'Est dont 1000 dans la commune de Ngoura, et 1000 dans la commune de Mandjou CM-UGP-PFS-206863-NC- Laying the Foundations of RFQ / Maintenance du a Safety Net System and Demande de Single Stage - One En attente 2021-04- 2021-06- 2022-06- matériel et logiciels IDA / 62230 A posteriori Limited 8,250.00 0.00 Supporting Project prix Envelope d'exécution 20 15 15 informatique du Projet Management Filets Sociaux CM-UGP-PFS-220415-NC- Laying the Foundations of RFQ / Fourniture de service a Safety Net System and Demande de Single Stage - One En attente 2021-04- 2021-05- 2022-05- de gardiennage au bureau IDA / 62230 A posteriori Limited 8,640.00 0.00 Supporting Project prix Envelope d'exécution 04 05 05 de l'Unité de Gestion du Management Projet Filets Sociaux CM-UGP-PFS-232595-NC- Laying the Foundations of RFQ / Fourniture de service a Safety Net System and Demande de Single Stage - One En attente 2021-06- 2021-07- 2022-07- de gardiennage au bureau IDA / 62230 A posteriori Limited 5,760.00 0.00 Supporting Project prix Envelope d'exécution 30 31 31 de l'Antenne régionale du Management projet du Sud CM-UGP-PFS-232598-NC- Laying the Foundations of RFQ / Fourniture de service a Safety Net System and Demande de Single Stage - One En attente 2021-07- 2021-08- 2022-08- de gardiennage au bureau IDA / D2980 A posteriori Limited 5,760.00 0.00 Supporting Project prix Envelope d'exécution 10 10 10 de l'Antenne régionale du Management projet de l'Est CM-UGP-PFS-232599-NC- Laying the Foundations of RFQ / Fourniture de service a Safety Net System and Demande de Single Stage - One En attente 2021-07- 2021-08- 2022-08- de gardiennage au bureau IDA / D2980 A posteriori Limited 5,760.00 0.00 Supporting Project prix Envelope d'exécution 10 10 10 de l'Antenne régionale du Management projet de l'Adamaoua CM-UGP-PFS-232601-NC- Laying the Foundations of RFQ / Fourniture des a Safety Net System and Demande de Single Stage - One En attente 2021-07- 2021-08- 2022-08- systèmes de sécurité et de IDA / 62230 A posteriori Limited 9,760.00 0.00 Supporting Project prix Envelope d'exécution 05 05 05 GPS et du service de Management tracking pour les autos du projet CM-UGP-PFS-232878-NC- Laying the Foundations of RFQ / Fourniture d'une a Safety Net System and Demande de Single Stage - One En attente 2021-06- 2021-08- 2022-08- IDA / 62230 A posteriori Limited 18,400.00 0.00 police d'assurance pour les Supporting Project prix Envelope d'exécution 30 27 27 6 véhicules du projet Management CM-UGP-PFS-233113-NC- RFQ / Agences de paiement de la phase 10 des Travaux à Haute Intensité Demande de Single Stage - One En attente 2021-09- 2021-11- 2022-11- IDA / 62230 Public Works Program Pilot A posteriori Limited 38,250.00 0.00 de Main d'Œuvre dans les prix Envelope d'exécution 10 21 21 régions de l'Adamaoua, du Nord et de l'extrême Nord en deux lots distincts CM-UGP-PFS-233111-NC- RFQ / Recrutement de l'agence de paiement de la Demande de Single Stage - One En attente 2021-08- 2021-11- 2022-11- phase 10 des Travaux à IDA / 62230 Public Works Program Pilot A posteriori Limited 20,250.00 0.00 prix Envelope d'exécution 28 08 08 Haute Intensité de Main d'œuvre du Projet Filets Sociaux dans les régions de l'Extrême Nord CM-UGP-PFS-257346-NC- DIR / Recrutement par Entente Directe d'une Cash Transfer Program Passation de Agence de Paiement pour with Accompanying En attente 2021-10- 2021-11- 2021-12- 2023-12- IDA / 62230 A posteriori marché de gré à Direct 48,600.00 0.00 assurer les paiements des Measures to Boost d'exécution 29 03 22 22 gré bénéficiaires de la phase 4 Household Productivity des Transferts Monétaires d’Urgence du Projet Filets Sociaux CONSULTING FIRMS Activity Reference No. / Short List and Draft Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Process Expression of Request for Opening of Technical Evaluation of Description Component Review Type Method Terms of Reference Request for Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Status Interest Notice Proposals as Issued Proposals / Minutes Technical Proposal Proposals Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CM-UGP-PFS-6358-CS- CQS / ONG pour THIMO: 7000 bénéficiaires dans 2 Sélection fondée communes de l'Extrême sur les 2017-02- 2016-10- 2017-02- 2017-04- 2017-02- 2017-05- 2017-03- 2017-06- 2018-03- 2017-12- 2018-04- Nord, 2 communes de l'Est IDA / 52240 Public Works Program Pilot A posteriori Open - National 429,190.00 367,605.09 Achevé qualifications 07 07 28 13 22 13 03 17 23 14 10 pour la phase 3 et 6000 des consultants bénéficiaires: 2 communes Adamaoua, 1 commune Nord pour la phase 4 en 2017 (1 ONG par région) CM-UGP-PFS-54735-CS- CQS / Consultant pour le Cash Transfer Program Sélection fondée développement d'un with Accompanying sur les 2018-05- 2018-06- 2018-06- 2018-10- 2018-08- 2019-01- 2018-09- 2019-03- 2018-10- 2019-04- 2019-04- IDA / 52240 A posteriori Open - National 167,500.00 135,528.54 Signé progiciel de gestion intégré Measures to Boost qualifications 30 11 20 26 03 23 02 22 07 15 05 pour le système Household Productivity des consultants d'information du Projet Filets Sociaux CM-UGP-PFS-172238-CS- QCBS / Recrutement d'un Laying the Foundations of cabinet pour l'audit externe Sélection fondée a Safety Net System and En cours 2020-08- 2020-08- 2020-09- 2020-11- 2020-11- 2020-12- 2021-02- 2021-03- 2022-03- du Projet Filets Sociaux, IDA / 62230 A posteriori sur la qualité et Open - National 36,000.00 0.00 Supporting Project d'exécution 28 25 18 01 29 29 05 12 12 financement additionnel , le coût Management exercices 2019-2020 (18 mois) , 2021 CM-UGP-PFS-175920-CS- CQS / Recrutement d'une ONG pour la mise en œuvre des activités de la Phase 8 Sélection fondée des THIMO dans les sur les En attente 2020-12- 2021-01- 2021-03- 2021-04- 2021-05- 2021-11- IDA / 62230 Public Works Program Pilot A posteriori Open - National 89,678.22 0.00 régions du Nord Ouest, qualifications d'exécution 30 20 05 04 09 05 Commune de Santa (2000 des consultants bénéficiaires) et du Sud- Ouest, Communes de Buéa (1000 bénéficiaires) et de Limbé II (1500 bénéficiaires) CM-UGP-PFS-206866-CS- CQS / Recrutement d'une ONG chargée d'accompagner le Projet Sélection fondée Filets Sociaux dans la mise sur les En cours 2021-01- 2020-12- 2021-02- 2021-04- 2021-05- 2021-06- 2021-12- en œuvre de la phase 8 des IDA / 62230 Public Works Program Pilot A posteriori Open - National 165,070.00 0.00 qualifications d'exécution 30 11 20 05 05 09 06 THIMO dans la région de des consultants l'Adamaoua (Communes de Nganha et Nyambaka) et dans la région du Centre (Communes de Lembe Yezoum) CM-UGP-PFS-206867-CS- CQS / Recrutement d'une ONG chargée d'accompagner le Projet Sélection fondée Filets Sociaux dans la mise sur les En attente 2021-01- 2021-02- 2021-04- 2021-05- 2021-06- 2021-12- en œuvre de la phase 9 des IDA / 62230 Public Works Program Pilot A posteriori Open - National 231,098.00 0.00 qualifications d'exécution 30 20 05 05 09 06 THIMO dans les régions de des consultants l'Adamaoua (Commune de Meiganga), de l'Est (Commune de Kentzou), et du Sud (Communes de Sangmelima et d'Ebolowa 1) CM-UGP-PFS-206928-CS- CQS / Recrutement de la Cash Transfer Program Sélection fondée firme d'appui à la mise en with Accompanying sur les En cours 2021-01- 2021-01- 2021-02- 2021-03- 2021-04- 2021-05- 2022-05- IDA / D2980 A posteriori Open - National 160,000.00 0.00 œuvre des interventions Measures to Boost qualifications d'exécution 11 12 01 17 16 21 21 dans le cadre de l'étude Household Productivity des consultants quantitative sur les VBG CM-UGP-PFS-232639-CS- CQS / recrutement d'une ONG chargée Sélection fondée d'accompagner le projet sur les En attente 2021-07- 2021-08- 2021-10- 2021-11- 2021-12- 2022-06- IDA / 62230 Public Works Program Pilot A posteriori Open - National 148,563.00 0.00 dans la réalisation de la qualifications d'exécution 30 20 03 02 07 05 phase 10 des travaux à des consultants haute Intensité de Main d'Œuvre (THIMO) dans la région de l'Extrême Nord CM-UGP-PFS-232640-CS- CQS / Recrutement de l'ONG chargée Sélection fondée d'accompagner le projet sur les En attente 2021-07- 2021-08- 2021-10- 2021-11- 2021-12- 2022-06- IDA / 62230 Public Works Program Pilot A posteriori Open - National 132,056.00 0.00 dans la réalisation de la qualifications d'exécution 30 20 03 02 07 05 phase 10 des Travaux à des consultants Haute Intensité de main d'Œuvre (THIMO) dans les régions du Nord et de l'Adamaoua INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Process Draft Negotiated Description Component Review Type Method Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Status Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CM-UGP-PFS-6328-CS- Cash Transfer Program INDV / Consultant pour le with Accompanying 2017-02- 2016-12- 2017-03- 2017-04- 2017-05- 2017-05- 2017-01- 2017-06- ciblage et l'enregistrement IDA / 52240 A posteriori Individuel Open 12,950.00 10,372.40 Signé Measures to Boost 06 20 27 17 19 22 19 16 à Blangoua du cycle 2 des Household Productivity transferts monetaires CM-UGP-PFS-6334-CS- Cash Transfer Program INDV / Consultant pour le with Accompanying 2017-02- 2017-05- 2017-03- 2017-04- 2017-01- 2017-05- 2017-01- 2017-06- ciblage et l'enregistrement IDA / 52240 A posteriori Individuel Open 12,950.00 10,368.36 Signé Measures to Boost 06 15 27 17 13 22 19 16 à Goulfey du cycle 2 des Household Productivity transferts monetaires CM-UGP-PFS-6337-CS- Cash Transfer Program INDV / Consultant pour le with Accompanying 2017-02- 2017-05- 2017-03- 2017-04- 2017-06- 2017-05- 2017-01- 2017-06- ciblage et l'enregistrement IDA / 52240 A posteriori Individuel Open 15,500.00 12,422.62 Signé Measures to Boost 06 15 27 17 13 22 19 21 à Makari du cycle 2 des Household Productivity transferts monetaires CM-UGP-PFS-6339-CS- Cash Transfer Program INDV / Consultant pour le with Accompanying 2017-02- 2017-05- 2017-03- 2017-04- 2017-05- 2017-05- 2017-01- 2017-06- ciblage et l'enregistrement IDA / 52240 A posteriori Individuel Open 12,500.00 10,372.40 Signé Measures to Boost 06 17 27 17 19 22 19 16 à GOBO du cycle 2 des Household Productivity transferts monetaires CM-UGP-PFS-6340-CS- Cash Transfer Program INDV / Consultant pour le with Accompanying 2017-02- 2017-05- 2017-03- 2017-04- 2017-05- 2017-05- 2017-01- 2017-06- ciblage et l'enregistrement IDA / 52240 A posteriori Individuel Open 12,500.00 10,379.07 Signé Measures to Boost 06 15 27 17 16 22 19 16 à BOURRHA du cycle 2 des Household Productivity transferts monetaires CM-UGP-PFS-6341-CS- Cash Transfer Program INDV / Consultant pour le with Accompanying 2017-02- 2017-05- 2017-03- 2017-04- 2017-05- 2017-05- 2017-01- 2017-06- ciblage et l'enregistrement IDA / 52240 A posteriori Individuel Open 12,500.00 10,379.07 Signé Measures to Boost 06 15 27 17 16 22 19 16 à Koza du cycle 2 des Household Productivity transferts monetaires CM-UGP-PFS-6342-CS- Cash Transfer Program INDV / Consultant pour le with Accompanying 2017-02- 2017-05- 2017-02- 2017-02- 2017-05- 2017-02- 2017-01- 2017-03- ciblage et l'enregistrement IDA / 52240 A posteriori Individuel Open 12,500.00 10,372.40 Signé Measures to Boost 06 16 13 14 18 24 19 21 à Mogodé du cycle 2 des Household Productivity transferts monetaires CM-UGP-PFS-6344-CS- Cash Transfer Program INDV / Consultant pour le with Accompanying 2017-02- 2017-05- 2017-02- 2017-02- 2017-05- 2017-02- 2017-01- 2017-03- ciblage et l'enregistrement IDA / 52240 A posteriori Individuel Open 15,500.00 11,613.54 Signé Measures to Boost 06 15 13 14 17 24 26 26 à Banyo du cycle 2 des Household Productivity transferts monetaires Page 4 CM-UGP-PFS-6346-CS- Cash Transfer Program INDV / Consultant pour le with Accompanying 2017-02- 2017-05- 2017-02- 2017-02- 2017-06- 2017-02- 2017-01- 2017-03- ciblage et l'enregistrement IDA / 52240 A posteriori Individuel Open 12,500.00 10,381.76 Signé Measures to Boost 06 29 13 14 28 24 19 21 à Tcheboa du cycle 2 des Household Productivity transferts monetaires CM-UGP-PFS-6347-CS- Cash Transfer Program INDV / Consultant pour le with Accompanying 2017-02- 2017-05- 2017-02- 2017-02- 2017-02- 2017-01- 2017-03- ciblage et l'enregistrement IDA / 52240 A posteriori Individuel Open 12,500.00 9,829.76 Signé Measures to Boost 06 15 13 14 24 26 21 à Mayo Oulo du cycle 2 des Household Productivity transferts monetaires CM-UGP-PFS-6348-CS- Cash Transfer Program INDV / Consultant pour le with Accompanying 2017-02- 2017-05- 2017-02- 2017-02- 2017-05- 2017-02- 2017-01- 2017-03- ciblage et l'enregistrement IDA / 52240 A posteriori Individuel Open 12,500.00 9,707.50 Signé Measures to Boost 06 16 24 26 24 28 26 25 à Rey Bouba du cycle 2 des Household Productivity transferts monetaires CM-UGP-PFS-6349-CS- Cash Transfer Program INDV / Consultant pour le with Accompanying 2017-02- 2017-05- 2017-02- 2017-02- 2017-05- 2017-02- 2017-01- 2017-03- ciblage et l'enregistrement IDA / 52240 A posteriori Individuel Open 12,500.00 9,716.26 Signé Measures to Boost 06 22 09 10 26 12 26 09 à Touboro du cycle 2 des Household Productivity transferts monetaires CM-UGP-PFS-6350-CS- Cash Transfer Program INDV / Consultant pour le with Accompanying 2017-02- 2016-12- 2017-02- 2017-02- 2017-03- 2017-03- 2017-03- ciblage et l'enregistrement IDA / 52240 A posteriori Individuel Open 12,500.00 11,772.77 Signé Measures to Boost 06 20 18 28 04 14 29 à Kette du cycle 2 des Household Productivity transferts monetaires CM-UGP-PFS-6351-CS- Cash Transfer Program INDV / Consultant pour le with Accompanying 2017-02- 2017-05- 2017-02- 2017-02- 2017-05- 2017-03- 2017-03- 2017-03- ciblage et l'enregistrement IDA / 52240 A posteriori Individuel Open 12,500.00 9,713.75 Signé Measures to Boost 06 15 18 28 17 04 14 29 à Belo du cycle 2 des Household Productivity transferts monetaires CM-UGP-PFS-6352-CS- Cash Transfer Program INDV / Consultant pour le with Accompanying 2017-02- 2017-05- 2017-02- 2017-02- 2017-05- 2017-03- 2017-03- 2017-03- ciblage et l'enregistrement IDA / 52240 A posteriori Individuel Open 12,500.00 9,703.73 Signé Measures to Boost 06 15 18 28 16 04 14 29 à Menchum Valley du cycle Household Productivity 2 des transferts monetaires CM-UGP-PFS-6353-CS- Cash Transfer Program INDV / Consultant pour le with Accompanying 2017-02- 2016-12- 2017-02- 2017-02- 2017-02- 2017-03- 2017-03- 2017-03- 2017-03- 2017-08- ciblage et l'enregistrement IDA / 52240 A posteriori Individuel Open 15,500.00 9,020.07 Achevé Measures to Boost 06 20 18 23 28 10 04 14 29 01 à Douala 3 du cycle 2 des Household Productivity transferts monetaires CM-UGP-PFS-6354-CS- Cash Transfer Program INDV / Consultant pour le with Accompanying 2017-02- 2017-05- 2017-02- 2017-02- 2017-05- 2017-03- 2017-03- 2017-03- ciblage et l'enregistrement IDA / 52240 A posteriori Individuel Open 15,500.00 9,264.24 Signé Measures to Boost 06 17 18 28 24 04 14 29 à Yaoundé du cycle 2 des Household Productivity transferts monetaires CM-UGP-PFS-6355-CS- INDV / Consultant chargé d'améliorer les modules du volet économique Cash Transfer Program notamment formation en with Accompanying 2017-02- 2016-12- 2017-02- 2017-02- 2017-03- 2017-03- 2017-03- 2017-03- 2017-04- 2018-09- AGR ( agriculture, petit IDA / 52240 A posteriori Individuel Open 26,260.00 22,361.04 Achevé Measures to Boost 10 15 25 09 02 21 12 21 17 24 commerce, gestion de Household Productivity l'argent, élevage) et former les bénéficiaires dans ces modules à l'Extrême Nord dans le cadre de la phase 2 du cycle 1 CM-UGP-PFS-6356-CS- INDV / Consultant chargé d'améliorer les modules du volet économique : Cash Transfer Program formation en AGR ( with Accompanying 2017-02- 2016-12- 2017-02- 2017-02- 2017-03- 2017-03- 2017-03- 2017-03- 2017-04- 2018-09- agriculture,petit commerce, IDA / 52240 A posteriori Individuel Open 28,460.00 24,278.93 Achevé Measures to Boost 10 15 25 09 02 21 12 21 17 21 gestion de l'argent, Household Productivity élevage) et former les bénéficiaires dans ces modules dans le Nord et l'Adamaoua dans le cadre de la phase 2 du cycle 1 CM-UGP-PFS-6357-CS- INDV / Consultant chargé d'améliorer les modules du volet économique : Cash Transfer Program formation en AGR ( with Accompanying 2017-02- 2016-12- 2017-02- 2017-02- 2017-03- 2017-03- 2017-03- 2017-03- 2017-04- 2018-10- agriculture,petit commerce, IDA / 52240 A posteriori Individuel Open 31,400.00 26,919.25 Achevé Measures to Boost 10 15 25 09 02 21 12 21 17 25 gestion de l'argent, Household Productivity élevage) et former les bénéficiaires dans ces modules dans le Nord O, Est, Dla, Ydé dans le cadre de la phase 2 du cycle 1 CM-UGP-PFS-6421-CS- 2017-02- 2017-07- 2017-04- 2017-03- 2017-04- 2017-06- 2017-11- INDV / Expert IDA / 52240 Public Works Program Pilot A priori Individuel Open 63,840.00 0.00 Annulé 17 13 07 29 28 02 29 environnemental et social du PFS Laying the Foundations of CM-UGP-PFS-6423-CS- a Safety Net System and 2017-02- 2017-07- 2017-03- 2017-05- 2017-04- 2017-05- 2017-06- IDA / 52240 A priori Individuel Open 1,920.00 0.00 Annulé INDV / Assistant Comptable Supporting Project 07 13 28 09 18 23 28 Management Laying the Foundations of CM-UGP-PFS-6424-CS- a Safety Net System and 2017-02- 2017-07- 2017-03- 2017-03- 2017-04- 2017-05- 2017-06- IDA / 52240 A priori Individuel Open 1,920.00 0.00 Annulé INDV / Assistant SPM Supporting Project 07 13 28 21 18 23 28 Management CM-UGP-PFS-6327-CS- Cash Transfer Program Sélection de CDS / protocole d'accord with Accompanying 2017-02- 2017-02- 2017-03- 2017-09- IDA / 52240 A priori consultants par Direct 900,000.00 0.00 Annulé avec l'INS pour le Measures to Boost 06 16 03 29 entente directe dénombrement et l'enquête Household Productivity PMT du cycle 2 CM-UGP-PFS-14406-CS- INDV / Opérateur Terrain Cash Transfer Program commune Mayo Moskota with Accompanying 2017-05- 2017-06- 2017-06- 2017-10- 2017-06- 2017-10- 2017-06- 2017-10- 2019-06- IDA / 52240 A posteriori Individuel Open 12,960.00 7,006.15 Signé (Extrême Nord) pour les Measures to Boost 19 26 04 23 11 27 21 31 21 transferts monetaires Household Productivity d'urgence CM-UGP-PFS-14407-CS- Laying the Foundations of INDV / Renouvellement du a Safety Net System and 2017-05- 2015-01- 2017-05- 2017-05- 2017-05- 2017-06- 2017-05- 2017-06- 2019-05- IDA / 52240 A posteriori Individuel Open 24,000.00 81,097.42 Signé contrat de l'Assistante du Supporting Project 08 09 09 05 10 13 10 09 10 Coordonnateur du Projet Management CM-UGP-PFS-14409-CS- Laying the Foundations of INDV / Renouvellement du a Safety Net System and 2017-05- 2015-01- 2017-05- 2017-05- 2017-05- 2017-06- 2017-05- 2017-06- 2019-05- IDA / 52240 A posteriori Individuel Open 19,200.00 44,266.70 Signé contrat de la Secrétaire de Supporting Project 05 09 06 05 07 14 07 09 07 l'Unité de Gestion du Projet Management CM-UGP-PFS-14410-CS- Laying the Foundations of INDV / Renouvellement a Safety Net System and 2017-05- 2015-01- 2017-05- 2017-05- 2017-05- 2017-06- 2017-05- 2017-06- 2019-05- IDA / 52240 A posteriori Individuel Open 16,800.00 38,438.87 Signé contrat Chauffeur 1 de Supporting Project 05 09 06 05 07 09 07 09 07 l'Unité de Gestion du Projet Management CM-UGP-PFS-14411-CS- Laying the Foundations of INDV / Renouvellement a Safety Net System and 2017-05- 2015-06- 2017-05- 2015-05- 2017-05- 2017-06- 2017-05- 2017-06- 2019-05- IDA / 52240 A posteriori Individuel Open 16,800.00 38,438.87 Signé contrat Chauffeur 2 Unité Supporting Project 05 09 06 05 07 09 07 09 07 de Gestion du Projet Management CM-UGP-PFS-14412-CS- Laying the Foundations of INDV / Renouvellement du a Safety Net System and 2017-05- 2015-01- 2017-05- 2017-05- 2017-05- 2017-05- 2017-05- 2017-06- 2019-05- IDA / 52240 A posteriori Individuel Open 16,800.00 32,191.68 Signé contrat de l'Agent de Supporting Project 05 09 06 05 07 31 07 09 07 liaison de l'Unité de Gestion Management du Projet CM-UGP-PFS-14463-CS- Laying the Foundations of INDV / Avenant au contrat a Safety Net System and 2017-06- 2017-06- 2017-06- 2017-06- 2019-06- IDA / 52240 A posteriori Individuel Open 12,960.00 0.00 Annulé de l'operateur de terrain de Supporting Project 09 12 13 15 15 Yaoundé 7 Management CM-UGP-PFS-14460-CS- Laying the Foundations of INDV / Avenant au contrat a Safety Net System and 2017-06- 2017-06- 2017-06- 2017-06- 2017-12- IDA / 52240 A posteriori Individuel Open 3,240.00 0.00 Annulé de l'opératrice de terrain de Supporting Project 09 12 13 15 12 la commune de Douala 2 Management CM-UGP-PFS-14490-CS- Laying the Foundations of INDV / Avenant au contrat a Safety Net System and 2017-06- 2017-06- 2017-06- 2017-06- 2019-06- IDA / 52240 A posteriori Individuel Open 16,800.00 0.00 Annulé de Technicienne de surface Supporting Project 15 23 25 29 29 de l'UGP Management CM-UGP-PFS-14454-CS- Laying the Foundations of INDV / Avenant au contrat a Safety Net System and 2017-06- 2017-10- 2017-06- 2017-06- 2015-06- 2017-06- 2015-06- 2019-06- IDA / 52240 A posteriori Individuel Open 19,200.00 34,575.36 Résilié du point focal de la ville de Supporting Project 09 27 12 13 15 15 17 15 Douala Management CM-UGP-PFS-16811-CS- Laying the Foundations of INDV / renouvellement de a Safety Net System and 2017-06- 2017-06- 2017-06- 2017-06- 2017-06- 2017-06- 2017-06- 2019-06- IDA / 52240 A posteriori Individuel Direct 12,960.00 25,629.07 Signé contrat opérateur de terrain Supporting Project 09 11 07 12 09 13 09 03 1 commune de MOKOLO Management CM-UGP-PFS-16814-CS- Laying the Foundations of INDV / renouvellement a Safety Net System and 2017-06- 2017-06- 2017-06- 2017-06- 2017-06- 2017-06- 2017-06- 2019-06- IDA / 52240 A posteriori Individuel Direct 12,960.00 23,513.04 Signé contrat opérateur de terrain Supporting Project 09 12 07 13 09 14 09 04 2 commune de MOKOLO Management CM-UGP-PFS-16821-CS- Laying the Foundations of INDV / Renouvellement de a Safety Net System and 2017-06- 2017-06- 2017-06- 2017-06- 2017-06- 2017-06- 2017-06- 2019-06- contrat de l'opérateur de IDA / 52240 A posteriori Individuel Direct 12,960.00 23,513.04 Signé Supporting Project 09 12 07 13 09 15 09 05 terrain de la commune de Management MAGA CM-UGP-PFS-16823-CS- Laying the Foundations of INDV / Renouvellement du a Safety Net System and 2017-06- 2017-06- 2017-06- 2017-06- 2017-06- 2017-06- 2017-06- 2017-12- contrat de l'opérateur de IDA / 52240 A posteriori Individuel Direct 3,240.00 22,483.20 Signé Supporting Project 09 10 07 11 09 12 09 09 terrain de la commune de Management Kar Hay Laying the Foundations of CM-UGP-PFS-16925-CS- a Safety Net System and 2017-06- 2017-06- 2017-06- 2017-06- 2019-06- INDV / Avenant au contrat IDA / 52240 A priori Individuel Open 63,840.00 0.00 Annulé Supporting Project 12 15 19 21 11 du SPM du Projet Management Laying the Foundations of CM-UGP-PFS-14451-CS- a Safety Net System and 2017-06- 2017-07- 2017-06- 2017-06- 2017-06- 2019-06- INDV / Renouvellement du IDA / 52240 A priori Individuel Open 46,000.00 0.00 Annulé Supporting Project 09 19 10 14 15 15 contrat Comptable Management CM-UGP-PFS-14446-CS- Laying the Foundations of INDV / Renouvellement du a Safety Net System and 2017-06- 2017-07- 2017-06- 2017-06- 2017-06- 2019-06- contrat de l'Expert IDA / 52240 A priori Individuel Open 63,840.00 0.00 Annulé Supporting Project 09 19 09 10 15 15 Informatique et Management Responsable SIG du Projet CM-UGP-PFS-14452-CS- Laying the Foundations of INDV / Renouvellement du a Safety Net System and 2017-06- 2017-06- 2017-06- 2017-06- 2017-06- 2019-06- IDA / 52240 A priori Individuel Direct 38,400.00 0.00 Annulé contrat du Responsable Supporting Project 09 12 13 13 15 15 Régional Extrême Nord Management CM-UGP-PFS-25501-CS- Laying the Foundations of INDV / Recrutement du a Safety Net System and 2017-08- 2017-08- 2017-09- 2017-10- 2017-10- 2017-11- 2017-10- 2017-11- 2018-10- IDA / 52240 A posteriori Individuel Open 19,200.00 47,854.03 Signé responsable régional du Supporting Project 31 17 26 25 03 06 13 03 13 Nord ouest du projet Filets Management Sociaux CM-UGP-PFS-25504-CS- Laying the Foundations of INDV / Consultant chargé a Safety Net System and 2017-09- 2017-09- 2017-09- 2017-10- 2017-10- 2017-11- 2017-10- 2017-11- 2018-04- de la Conception et l' appui IDA / 52240 A posteriori Individuel Open 21,500.00 80,692.20 Signé Supporting Project 01 06 29 02 06 03 16 03 19 à la mise en œuvre du plan Management de communication CM-UGP-PFS-25520-CS- INDV / Recrutement de 4 consultants pour le ciblage des bénéficiaires de la phase 2 des transferts Laying the Foundations of monetaires d'urgence dans a Safety Net System and 2017-09- 2017-10- 2017-10- 2017-12- 2017-10- 2017-12- 2017-10- 2017-12- 2017-11- 2018-09- IDA / 52240 A posteriori Individuel Open 36,400.00 30,128.36 Achevé les département du Logone Supporting Project 07 05 12 05 19 11 27 12 16 17 et Chari (Communes de Management Blangoua, Goulfey, Makari) et dans le département du Mayo Tsanaga(commune de Mayo Moskota CM-UGP-PFS-25782-CS- Laying the Foundations of INDV / Avenant N°01 au a Safety Net System and 2017-09- 2014-10- 2017-09- 2017-06- 2017-09- 2017-06- 2017-09- 2017-08- 2018-09- contrat de l'Expert IDA / 52240 A posteriori Individuel Open 38,095.25 192,289.67 Signé Supporting Project 06 10 09 13 10 15 11 17 11 informatique et Management responsable SIG UGP CM-UGP-PFS-25786-CS- Laying the Foundations of INDV / Avenant N°02 au a Safety Net System and 2017-09- 2013-05- 2017-09- 2017-06- 2017-09- 2017-06- 2017-09- 2017-08- 2018-09- contrat du Spécialiste en IDA / 52240 A posteriori Individuel Open 38,095.25 71,473.92 Signé Supporting Project 06 29 09 19 10 22 11 17 11 passation des Marchés de Management l'UGP CM-UGP-PFS-25787-CS- Laying the Foundations of INDV / Avenant N°1 au a Safety Net System and 2017-09- 2014-10- 2017-09- 2017-06- 2017-09- 2017-06- 2017-09- 2017-08- 2018-09- IDA / 52240 A posteriori Individuel Open 35,555.57 167,336.95 Signé contrat du Comptable de Supporting Project 06 14 09 13 10 15 11 17 11 l'UGP Management Page 5 CM-UGP-PFS-25794-CS- Laying the Foundations of INDV / Avenant N°1 au a Safety Net System and 2017-09- 2015-04- 2017-09- 2017-06- 2017-09- 2017-06- 2017-09- 2017-08- 2018-09- contrat du Responsable IDA / 52240 A posteriori Individuel Open 19,200.00 107,596.50 Signé Supporting Project 06 14 09 13 10 16 11 17 11 régional du Projet Filets Management Sociaux dans l'Extrême Nord CM-UGP-PFS-25517-CS- INDV / Consultant chargé de la sensibilisation des Cash Transfer Program bénéficiaires du Cycle 2 (i) with Accompanying 2017-09- 2017-09- 2017-10- 2017-10- 2017-10- 2017-11- 2017-10- 2017-11- 2018-02- IDA / 52240 A posteriori Individuel Open 58,180.00 43,182.70 Signé à l'Extrême Nord, (ii) au Measures to Boost 07 06 12 25 19 01 27 01 24 Nord et à l'Adamaoua, (iii) à Household Productivity l'Est, au Nord-ouest, à Douala et à Yaoundé CM-UGP-PFS-6326-CS- Cash Transfer Program Sélection de CDS / Protocole d'accord with Accompanying 2017-08- 2017-09- 2017-08- 2017-09- 2017-09- 2018-05- IDA / 52240 A priori consultants par Direct 500,000.00 391,776.36 Signé avec l'INS pour la Measures to Boost 31 05 31 16 28 14 entente directe réalisation de l'enquête de Household Productivity base CM-UGP-PFS-25509-CS- INDV / Recrutement de 34 Cash Transfer Program relais communautaires with Accompanying 2017-11- 2017-10- 2017-12- 2017-11- 2018-01- 2017-11- 2018-01- 2017-12- 2019-01- 2019-05- dans la commune de Koza, IDA / 52240 A posteriori Individuel Open 40,800.00 49,307.71 Signé Measures to Boost 30 13 30 20 06 24 14 07 14 31 département du Mayo Household Productivity Tsanaga, Région de l'Extrême Nord CM-UGP-PFS-25508-CS- INDV / Recrutement de 34 Cash Transfer Program relais communautaires with Accompanying 2017-12- 2017-10- 2018-01- 2017-11- 2018-02- 2017-11- 2018-02- 2017-12- 2019-02- dans la commune de IDA / 52240 A posteriori Individuel Open 40,800.00 46,287.84 Signé Measures to Boost 30 13 29 24 03 27 11 05 11 Bourrha, département du Household Productivity Mayo Tsanaga, Région de l'Extrême Nord CM-UGP-PFS-25512-CS- INDV / Recrutement de 34 Cash Transfer Program relais communautaires with Accompanying 2017-11- 2017-10- 2017-12- 2017-11- 2018-01- 2017-11- 2018-01- 2017-12- 2019-01- dans la commune de IDA / 52240 A posteriori Individuel Open 40,800.00 69,189.81 Signé Measures to Boost 30 13 30 08 06 22 14 05 14 Mogode, département du Household Productivity Mayo Tsanaga, Région de l'Extrême Nord CM-UGP-PFS-25515-CS- INDV / Recrutement de 34 Cash Transfer Program relais communautaires with Accompanying 2017-11- 2017-10- 2018-01- 2017-11- 2018-01- 2017-11- 2018-01- 2017-12- 2019-01- IDA / 52240 A posteriori Individuel Open 40,800.00 50,528.89 Signé dans la commune de Mayo- Measures to Boost 30 13 02 24 09 28 17 05 17 Oulo, département du Mayo Household Productivity Louti, Région du Nord CM-UGP-PFS-25516-CS- INDV / Recrutement de 34 Cash Transfer Program relais communautaires with Accompanying 2017-11- 2017-10- 2018-01- 2017-12- 2018-01- 2017-12- 2018-01- 2017-12- 2019-01- IDA / 52240 A posteriori Individuel Open 40,800.00 68,555.87 Signé dans la commune de Measures to Boost 30 13 04 04 11 04 19 05 19 Tcheboa, département de la Household Productivity Bénoué, Région du Nord CM-UGP-PFS-37431-CS- Laying the Foundations of INDV / Chauffeur de a Safety Net System and 2017-12- 2018-01- 2018-01- 2018-02- 2018-01- 2018-03- 2018-01- 2018-03- 2019-01- IDA / 52240 A posteriori Individuel Open 6,840.00 10,274.36 Signé l'antenne régionale du Supporting Project 27 11 20 28 22 06 29 06 29 Projet du Nord- Ouest Management CM-UGP-PFS-37432-CS- Laying the Foundations of INDV / Secrétaire de a Safety Net System and 2017-12- 2018-01- 2018-01- 2018-02- 2018-01- 2018-03- 2018-02- 2018-03- 2019-02- IDA / 52240 A posteriori Individuel Open 9,600.00 15,722.34 Signé l'antenne régionale du Supporting Project 28 11 23 28 28 06 04 06 04 Projet du Nord Ouest Management Laying the Foundations of CM-UGP-PFS-37434-CS- a Safety Net System and 2017-11- 2018-01- 2017-12- 2018-02- 2017-12- 2018-03- 2017-12- 2018-03- 2018-12- INDV / Point focal du Projet IDA / 52240 A posteriori Individuel Open 9,600.00 14,584.42 Signé Supporting Project 30 11 22 28 26 29 28 29 28 de la ville de Douala Management CM-UGP-PFS-25972-CS- CQS / Avenant au contrat N°001/MINEPAT/CTS/PFS/ CAPM/2017 du 23 mars 2017 de l'ONG chargée de Sélection de 2017-12- 2017-12- 2017-12- 2017-12- 2018-01- 2018-02- 2018-07- 2019-05- la mise en œuvre des IDA / 52240 Public Works Program Pilot A posteriori consultants par Direct 99,042.50 93,748.34 Achevé 18 21 25 22 18 13 17 22 THIMO 3 dans l'Extrême entente directe Nord avec 4000 bénéficiaires pour la mise en œuvre des THIMO 5 avec 3000 bénéficiaires dans la région du Nord-ouest CM-UGP-PFS-25907-CS- CQS / Avenant au contrat N°002/MINEPAT/CTS/PFS/ CAPM/2017 du 23 mars 2017 de l'ONG chargée de Sélection de 2017-12- 2017-12- 2017-12- 2017-12- 2018-01- 2018-02- 2018-07- 2018-07- la mise en œuvre des IDA / 52240 Public Works Program Pilot A posteriori consultants par Direct 99,042.50 92,937.44 Achevé 18 21 25 22 18 13 17 27 THIMO 3 dans la région de entente directe l'Est avec 3000 bénéficiaires pour la mise en œuvre des THIMO 5 avec 3000 bénéficiaires dans la région de l'Est CM-UGP-PFS-47367-CS- INDV / Consultant 2018-03- 2018-04- 2018-04- 2018-04- 2018-05- individuel chargé IDA / 52240 Public Works Program Pilot A posteriori Individuel Limited 8,250.00 0.00 Annulé 30 04 18 28 28 d'actualiser la carte des THIMO du Projet Filets Sociaux CM-UGP-PFS-47368-CS- INDV / Consultants Cash Transfer Program individuels (3) chargés du with Accompanying 2018-04- 2018-05- 2018-05- 2018-06- 2018-07- ciblage des bénéficiaires de IDA / 52240 A posteriori Individuel Open 20,256.00 0.00 Annulé Measures to Boost 06 09 23 02 17 la phase 3 des transferts Household Productivity monétaires d'urgence dans la région du Nord Ouest CM-UGP-PFS-47363-CS- INDV / Consultants individuels (03) chargés de Cash Transfer Program compléter et d'améliorer les with Accompanying 2018-03- 2018-02- 2018-04- 2018-04- 2018-04- 2018-04- 2018-05- 2018-04- 2019-05- manuels de formation et de IDA / 52240 A posteriori Individuel Open 63,040.00 87,765.09 Signé Measures to Boost 09 02 14 06 28 13 12 18 12 former les bénéficiaires sur Household Productivity les AGR pour le cycle 2 des transferts monétaires du Projet Filets CM-UGP-PFS-47362-CS- Cash Transfer Program INDV / Consultant with Accompanying 2018-03- 2018-05- 2018-04- 2018-05- 2018-04- 2018-06- 2018-04- 2018-06- 2019-04- individuel chargé de la IDA / 52240 A posteriori Individuel Open 8,250.00 7,158.24 Signé Measures to Boost 15 15 17 23 24 01 30 01 30 traduction des documents Household Productivity du projet en anglais CM-UGP-PFS-25526-CS- INDV / Consultant chargé Laying the Foundations of de l'accompagnement en a Safety Net System and 2017-09- 2018-10- 2017-10- 2017-10- 2017-10- 2018-10- IDA / 52240 A posteriori Individuel Open 12,000.00 0.00 Annulé TOM2PRO, TOM2PAIE, Supporting Project 15 30 11 16 24 24 TOM2MONITORING et Management TOM2MARCHE CM-UGP-PFS-25881-CS- Laying the Foundations of INDV / Consultant chargé a Safety Net System and 2018-04- 2018-08- 2018-05- 2018-09- 2018-05- 2018-09- 2018-06- 2018-09- 2018-12- 2019-02- IDA / 52240 A posteriori Individuel Open 8,250.00 7,201.62 Achevé du développement du site Supporting Project 17 08 13 10 20 12 17 13 14 15 WEB Management Laying the Foundations of CM-UGP-PFS-16899-CS- a Safety Net System and 2017-10- 2014-10- 2017-10- 2017-10- 2017-09- 2017-10- 2017-11- 2019-10- INDV / Avenant au contrat IDA / 52240 A posteriori Individuel Open 76,190.00 71.57 Signé Supporting Project 02 14 13 18 08 23 01 13 de l'auditeur interne Management CM-UGP-PFS-47928-CS- Cash Transfer Program 2018-04- 2018-06- 2018-05- 2018-11- 2018-06- 2018-11- 2018-07- 2019-01- 2019-07- INDV / Assistant au suivi IDA / 52240 with Accompanying A posteriori Individuel Open 12,000.00 10,966.15 Signé 20 22 30 12 13 20 04 03 04 évaluation Measures to Boost Household Productivity CM-UGP-PFS-47923-CS- Cash Transfer Program INDV / Recrutement d'un with Accompanying 2018-04- 2018-03- 2018-05- 2018-10- 2018-05- 2018-10- 2018-06- 2018-10- 2019-06- IDA / 52240 A posteriori Individuel Open 12,000.00 26,092.28 Signé Spécialiste en Passation des Measures to Boost 04 26 07 01 21 10 18 11 18 Marché Assistant Household Productivity CM-UGP-PFS-54610-CS- INDV / consultant Cash Transfer Program individuel pour l'assistance with Accompanying 2018-04- 2018-03- 2018-04- 2018-05- 2018-06- 2018-12- IDA / 52240 A posteriori Individuel Limited 8,250.00 0.00 Annulé à la migration comptable Measures to Boost 16 26 21 12 16 13 vers le nouveau référentiel Household Productivity comptable SYSCOHADA révisé CM-UGP-PFS-54615-CS- INDV / consultant pour Cash Transfer Program assister l'UGP à l'utilisation with Accompanying 2018-04- 2018-10- 2018-04- 2018-11- 2018-05- 2018-12- 2018-06- 2018-12- 2019-06- IDA / 52240 A posteriori Individuel Limited 8,250.00 10,408.76 Signé optimale des logiciels Measures to Boost 20 30 25 19 16 06 20 07 20 TOM2PRO, TOM2PAIE et Household Productivity TOM2MARCHE CM-UGP-PFS-54616-CS- INDV / Consultant pour la Cash Transfer Program conception du masque de with Accompanying 2018-04- 2018-08- 2018-04- 2018-08- 2018-05- 2018-09- 2018-06- 2018-09- 2018-12- saisie, la supervision de la IDA / 52240 A posteriori Individuel Limited 8,250.00 7,097.50 Signé Measures to Boost 25 07 30 14 21 10 25 11 22 saisie et l'analyse des Household Productivity données de la première évaluation interne du Projet IDA CM-UGP-PFS-47366-CS- INDV / Consultant Cash Transfer Program individuel chargé with Accompanying 2018-04- 2018-05- 2018-05- 2018-05- 2018-06- IDA / 52240 A posteriori Individuel Limited 8,250.00 0.00 Annulé d'actualiser la carte de Measures to Boost 30 05 19 29 28 pauvreté pour les transferts Household Productivity monétaires du Projet Filets Sociaux CM-UGP-PFS-47370-CS- Cash Transfer Program INDV / Avenant au contrat Sélection de with Accompanying 2018-04- 2016-01- 2018-04- 2018-02- 2018-05- 2018-02- 2018-10- du point focal du Projet IDA / 52240 A posteriori consultants par Direct 3,600.00 3,181.63 Signé Measures to Boost 20 11 27 28 03 28 30 dans le Département du entente directe Household Productivity Mberé, région de l'Adamaoua CM-UGP-PFS-25974-CS- CQS / Contrat ONG pour la Sélection de phase 6 des THIMO pour 2018-05- 2018-07- 2018-06- 2018-07- 2018-07- 2018-09- 2019-01- 2019-02- IDA / 52240 Public Works Program Pilot A posteriori consultants par Direct 99,042.50 85,366.88 Achevé 3000 bénéficiaires dans 2 30 02 09 20 30 19 26 09 entente directe communes de la région du Nord CM-UGP-PFS-47376-CS- INDV / Avenant au contrat Cash Transfer Program de l'opérateur de terrain de Sélection de with Accompanying 2018-04- 2016-01- 2018-04- 2018-02- 2018-05- 2018-02- 2018-10- la commune de la IDA / 52240 A posteriori consultants par Direct 2,430.00 2,169.08 Signé Measures to Boost 24 11 28 28 04 28 31 commune de la commune entente directe Household Productivity de kai kai département du Mayo Danay, région de l'extrême Nord CM-UGP-PFS-47377-CS- INDV / Avenant au contrat Cash Transfer Program Sélection de de l'opérateur de terrain de with Accompanying 2018-04- 2016-01- 2018-04- 2018-02- 2018-05- 2018-02- 2018-10- IDA / 52240 A posteriori consultants par Direct 2,430.00 2,147.60 Signé la commune de Méri, Measures to Boost 24 11 28 28 04 28 31 entente directe département du Diamaré, Household Productivity région de l'Extrême Nord CM-UGP-PFS-47378-CS- INDV / Avenant au contrat Cash Transfer Program Sélection de de l'opérateur de terrain de with Accompanying 2018-04- 2016-01- 2018-04- 2018-02- 2018-05- 2018-02- 2018-10- IDA / 52240 A posteriori consultants par Direct 2,430.00 2,147.60 Signé la commune de Ndoukoula, Measures to Boost 24 11 28 28 04 28 31 entente directe département du Diamaré, Household Productivity région de l'Extrême Nord CM-UGP-PFS-47379-CS- INDV / Avenant au contrat Cash Transfer Program Sélection de de l'opérateur de terrain de with Accompanying 2018-04- 2016-01- 2018-04- 2018-02- 2018-05- 2018-02- 2018-10- IDA / 52240 A posteriori consultants par Direct 2,430.00 2,169.08 Signé la commune de Guider, Measures to Boost 24 11 28 28 04 28 31 entente directe département du Mayo Household Productivity Louti, région du Nord CM-UGP-PFS-47430-CS- INDV / Avenant au contrat Cash Transfer Program Sélection de de l'opérateur de terrain de with Accompanying 2018-04- 2016-01- 2018-04- 2018-02- 2018-05- 2018-02- 2018-10- IDA / 52240 A posteriori consultants par Direct 2,430.00 2,147.60 Signé la commune de Lagdo, Measures to Boost 24 11 28 28 04 28 31 entente directe département de la Bénoué, Household Productivity région du Nord CM-UGP-PFS-47431-CS- INDV / Avenant au contrat Cash Transfer Program de l'opérateur de terrain N° Sélection de with Accompanying 2018-04- 2016-01- 2018-04- 2018-02- 2018-05- 2018-02- 2018-10- 1 de la commune de Bibemi IDA / 52240 A posteriori consultants par Direct 2,430.00 2,147.60 Signé Measures to Boost 24 11 28 28 04 28 31 (ADAMOU Bienvenu), entente directe Household Productivity département de la Bénoué, région du Nord CM-UGP-PFS-47432-CS- INDV / Avenant au contrat Cash Transfer Program de l'opérateur de terrain N° Sélection de with Accompanying 2018-04- 2016-01- 2018-04- 2018-02- 2018-05- 2018-02- 2018-10- 2 de la commune de Bibemi IDA / 52240 A posteriori consultants par Direct 2,430.00 2,147.60 Signé Measures to Boost 24 11 28 28 04 28 31 (GOUDOUM GRANA entente directe Household Productivity Dieunedort), département de la Bénoué, région du Nord Page 6 CM-UGP-PFS-47433-CS- INDV / Avenant au contrat de l'opérateur de terrain de Cash Transfer Program Sélection de la commune de Kar Hay with Accompanying 2018-04- 2018-02- 2018-04- 2018-01- 2018-04- 2018-02- 2019-04- IDA / 52240 A posteriori consultants par Direct 8,100.00 8,495.18 Signé pour la commune de Measures to Boost 18 23 22 23 28 28 28 entente directe Makary dans le Household Productivity département du Logone et Chari, région de l'Extrême Nord CM-UGP-PFS-47434-CS- Cash Transfer Program Sélection de INDV / Avenant au contrat with Accompanying 2018-04- 2016-01- 2018-04- 2018-02- 2018-05- 2018-02- 2019-12- IDA / 52240 A posteriori consultants par Direct 16,800.00 15,497.59 Signé de la secrétaire de l'antenne Measures to Boost 24 11 28 28 04 28 30 entente directe régionale de l'Extrême Nord Household Productivity CM-UGP-PFS-47435-CS- Cash Transfer Program INDV / Avenant au contrat with Accompanying 2018-03- 2018-03- 2018-07- 2018-03- 2018-07- 2018-03- 2018-07- 2019-12- IDA / 52240 A posteriori Individuel Direct 11,340.00 7,980.91 Signé du chauffeur de l'antenne Measures to Boost 05 12 02 17 04 25 04 15 régionale du Nord Household Productivity CM-UGP-PFS-47369-CS- Cash Transfer Program INDV / Avenant au contrat Sélection de with Accompanying 2018-04- 2016-01- 2018-04- 2018-02- 2018-05- 2018-02- 2018-11- du point focal du IDA / 52240 A posteriori consultants par Direct 3,600.00 3,188.07 Signé Measures to Boost 25 11 29 28 05 28 01 département du Diamaré entente directe Household Productivity dans la région de l'Extrême Nord CM-UGP-PFS-47371-CS- INDV / Avenant au contrat Cash Transfer Program Sélection de de l'opérateur de terrain with Accompanying 2018-04- 2016-01- 2018-04- 2018-02- 2018-05- 2018-02- 2018-10- IDA / 52240 A posteriori consultants par Direct 2,430.00 2,147.60 Signé N°1 de la commune de DIR Measures to Boost 24 11 28 28 04 28 31 entente directe (HEBGASSO Jean Baptiste) Household Productivity département du Mbéré, région de l'Adamaoua CM-UGP-PFS-47372-CS- INDV / Avenant au contrat Cash Transfer Program Sélection de de l'opérateur de terrain N° with Accompanying 2018-04- 2016-01- 2018-04- 2018-02- 2018-05- 2018-02- 2018-10- IDA / 52240 A posteriori consultants par Direct 2,430.00 2,147.60 Signé 2 de la Commune de Dir Measures to Boost 24 11 28 28 04 28 31 entente directe (HOULAO Pierre) Household Productivity département du Mbéré, région de l'Adamoua CM-UGP-PFS-47375-CS- INDV / Avenant au contrat Cash Transfer Program de l'opérateur de terrain Sélection de with Accompanying 2018-04- 2018-01- 2018-04- 2018-02- 2018-05- 2018-02- 2018-10- N°2 de la commune de IDA / 52240 A posteriori consultants par Direct 2,430.00 2,147.60 Signé Measures to Boost 24 11 28 28 04 28 31 BOGO( Wanie Bernard) entente directe Household Productivity département du Diamaré, région de l'Extrême Nord CM-UGP-PFS-47373-CS- INDV / Avenant au contrat Cash Transfer Program Sélection de de l'opératrice de terrain with Accompanying 2018-04- 2016-01- 2018-04- 2018-02- 2018-05- 2018-02- 2018-10- IDA / 52240 A posteriori consultants par Direct 2,430.00 2,147.60 Signé N°1 de la commune de Measures to Boost 24 11 28 28 04 28 31 entente directe BOGO, département du Household Productivity Diamaré, région de l'Extrême Nord CM-UGP-PFS-59671-CS- Cash Transfer Program Sélection de 2018-04- 2016-01- 2018-05- 2018-05- 2018-05- 2018-05- 2018-11- CDS / Opérateur de terrain IDA / 52240 with Accompanying A posteriori consultants par Direct 3,240.00 2,391.05 Signé 30 11 10 30 19 31 15 de la commune de Douala 4 Measures to Boost entente directe Household Productivity CM-UGP-PFS-59673-CS- Cash Transfer Program INDV / Recrutement du with Accompanying 2018-05- 2018-06- 2018-06- 2018-10- 2018-06- 2018-11- 2018-06- 2018-12- 2019-06- Responsable régional de IDA / 52240 A posteriori Individuel Open 19,200.00 16,630.56 Signé Measures to Boost 04 12 06 10 13 16 22 03 22 l'antenne du Nord du Projet Household Productivity Filets Sociaux CM-UGP-PFS-59789-CS- CDS / Audit financier et comptable des comptes du Cash Transfer Program Projet de Remise à niveau Sélection de with Accompanying 2018-04- 2018-04- 2018-04- 2018-03- 2018-05- 2018-07- 2020-05- des Réseaux de Transport IDA / 52240 A posteriori consultants par Direct 54,000.00 46,581.42 Signé Measures to Boost 26 20 30 23 14 31 13 d'Electricité et Réforme du entente directe Household Productivity Secteur (PRRTERS): exercices 2017-2018 - 2019 et du Projet Filets Sociaux (PFS) : exercices 2017-2018 CM-UGP-PFS-67474-CS- CDS / Avenant au contrat Laying the Foundations of Sélection de de l'opérateur de terrain de a Safety Net System and 2018-06- 2015-12- 2018-07- 2018-05- 2018-07- 2018-05- 2019-01- IDA / 52240 A posteriori consultants par Direct 3,240.00 2,831.73 Signé la commune de Yaoundé Supporting Project 29 30 03 02 09 08 05 entente directe 1er NGO SICK ELEANOR Management RHOLY épouse KAM CM-UGP-PFS-67475-CS- CDS / Avenant au contrat Laying the Foundations of de l'opérateur de terrain de Sélection de a Safety Net System and 2018-06- 2015-12- 2018-07- 2018-05- 2018-07- 2018-05- 2019-01- la commune de Funfong, IDA / 52240 A posteriori consultants par Direct 3,240.00 2,831.73 Signé Supporting Project 29 30 03 02 09 08 05 département du Boyo entente directe Management région du Nord Ouest AGHA-AH EVARISTUS ALANJI CM-UGP-PFS-67477-CS- CDS / Avenant au contrat de l'opérateur de terrain de Laying the Foundations of Sélection de la commune de Balikumbat a Safety Net System and 2018-06- 2015-12- 2018-07- 2018-05- 2018-07- 2018-05- 2019-01- IDA / 52240 A posteriori consultants par Direct 3,240.00 2,831.73 Signé département du Ngo Supporting Project 29 30 03 02 09 08 05 entente directe Ketungja région du Nord Management Ouest TAJIPUKU ALPHONSE TAMIGHANG CM-UGP-PFS-67478-CS- CDS / avenant au contrat Laying the Foundations of de l'opérateur de terrain N1 Sélection de a Safety Net System and 2018-06- 2015-12- 2018-07- 2018-05- 2018-07- 2018-05- 2019-01- de la commune de IDA / 52240 A posteriori consultants par Direct 3,240.00 2,831.73 Signé Supporting Project 29 30 03 02 09 08 05 Messamena département entente directe Management du Haut Nyong région de l'Est TSALA MVOGO BERNARD JEAN CM-UGP-PFS-67479-CS- Laying the Foundations of CDS / Avenant au contrat Sélection de a Safety Net System and 2018-06- 2015-12- 2018-07- 2015-05- 2018-07- 2018-05- 2019-01- du point focal du IDA / 52240 A posteriori consultants par Direct 4,800.00 4,195.15 Signé Supporting Project 29 30 03 04 09 08 05 département du Haut entente directe Management Nyong région de l'Est MBILLA Pierre Valery CM-UGP-PFS-67481-CS- CDS / avenant au contrat Laying the Foundations of Sélection de de l'opérateur de terrain a Safety Net System and 2018-07- 2015-12- 2018-07- 2018-06- 2018-07- 2018-06- 2018-11- IDA / 52240 A posteriori consultants par Direct 2,160.00 1,887.82 Signé N°2 de la commune de Supporting Project 02 30 06 25 12 29 09 entente directe Messamena ESSOMBA Management YANNICK ALBERT NGUEM CM-UGP-PFS-67482-CS- CDS / Avenant au contrat Laying the Foundations of Sélection de de l'opérateur de terrain a Safety Net System and 2018-06- 2015-12- 2018-07- 2018-05- 2018-07- 2018-05- 2018-08- 2018-06- IDA / 52240 A posteriori consultants par Direct 540.00 471.95 Achevé N°2 de la commune de Supporting Project 29 30 03 10 08 15 07 30 entente directe Lagdo, département de la Management Bénoué, région du Nord SIRINA ELVIS CM-UGP-PFS-67517-CS- Laying the Foundations of Sélection de INDV / Responsable a Safety Net System and 2018-06- 2018-07- 2018-07- 2019-07- IDA / 52240 A posteriori consultants par Direct 38,095,248.00 0.00 Annulé Administratif et Financier Supporting Project 29 04 11 11 entente directe du Projet Management CM-UGP-PFS-72586-CS- Laying the Foundations of INDV / Recrutement d'un a Safety Net System and 2018-08- 2018-09- 2018-09- 2018-09- 2018-09- 2018-09- 2018-10- 2018-09- 2019-10- IDA / 52240 A posteriori Individuel Direct 5,940.00 5,136.94 Signé opérateur de terrain pour la Supporting Project 23 13 02 14 23 17 28 17 28 commune de Koza Management CM-UGP-PFS-81429-CS- INDV / consultants national sénior chargé d'appuyer la Laying the Foundations of Banque mondiale et le a Safety Net System and 2018-10- 2018-10- 2018-10- 2018-11- 2018-11- 2018-11- 2018-12- 2018-11- 2019-03- 2019-09- Projet Filets Sociaux dans la IDA / 52240 A posteriori Individuel Limited 24,600.00 21,307.91 Achevé Supporting Project 18 05 25 26 15 28 20 30 20 04 préparation d'une Management évaluation qualitative sur les Violences Basées sur le Genre (VBG) au Cameroun CM-UGP-PFS-83718-CS- Laying the Foundations of INDV / Responsable a Safety Net System and 2018-11- 2018-10- 2018-12- 2019-03- 2019-01- 2019-03- 2019-02- 2019-04- 2021-02- IDA / 52240 A posteriori Individuel Open 38,096.00 125,993.93 Signé Administratif et Financier Supporting Project 11 22 30 13 20 18 24 01 23 du Projet Filets Sociaux Management CM-UGP-PFS-83719-CS- Laying the Foundations of INDV / Expert en a Safety Net System and 2018-11- 2018-10- 2018-12- 2019-02- 2019-01- 2019-03- 2019-02- 2019-03- 2020-02- IDA / 52240 A posteriori Individuel Open 38,095.00 25,544.73 Signé sauvegardes sociales du Supporting Project 11 24 30 19 20 04 24 15 24 Projet Filets Sociaux Management CM-UGP-PFS-83720-CS- Laying the Foundations of INDV / coach du a Safety Net System and 2018-11- 2018-11- 2019-01- 2019-03- 2019-01- 2019-03- 2019-03- 2019-04- 2019-08- responsable des activités IDA / 52240 A posteriori Individuel Open 38,095.00 19,480.26 Résilié Supporting Project 18 01 06 07 27 11 03 17 30 d'accompagnement du Management Projet Filets Sociaux CM-UGP-PFS-83722-CS- Laying the Foundations of INDV / Assistant en Gestion a Safety Net System and 2018-11- 2018-11- 2019-01- 2019-02- 2019-01- 2019-02- 2019-03- 2019-02- 2020-03- IDA / 52240 A posteriori Individuel Open 14,400.00 10,329.66 Signé des Ressources Humaines Supporting Project 18 01 06 18 27 20 03 20 02 et du matériel Management CM-UGP-PFS-83723-CS- Laying the Foundations of INDV / Assistant au a Safety Net System and 2018-11- 2018-11- 2019-01- 2019-03- 2019-01- 2019-03- 2019-03- 2019-03- 2020-03- Responsable du Systeme IDA / 52240 A posteriori Individuel Open 14,400.00 9,119.51 Signé Supporting Project 18 13 06 01 27 06 03 06 02 d'Information Management du Projet Filets Sociaux MOF-CM-UGP-PFS-14460- Laying the Foundations of Sélection de CS-CDS / Avenant au a Safety Net System and 2017-06- 2017-06- 2017-06- 2017-06- 2017-06- 2017-12- IDA / 52240 A posteriori consultants par Direct 3,240.00 2,785.30 Signé contrat de l'opératrice de Supporting Project 09 13 09 16 17 13 entente directe terrain de la commune de Management Douala 2 MOF-UGP-PFS-14463-CS- Laying the Foundations of Sélection de CDS / Avenant au contrat a Safety Net System and 2017-01- 2017-06- 2017-06- 2017-06- 2017-06- 2019-06- IDA / 52240 A posteriori consultants par Direct 12,960.00 25,147.34 Signé de l'operateur de terrain de Supporting Project 12 12 09 23 15 23 entente directe Yaoundé 7 Management MOF-UGP-PFS-14490-CS- Laying the Foundations of Sélection de CDS / Avenant au contrat a Safety Net System and 2017-06- 2015-01- 2017-06- 2017-06- 2017-07- 2017-07- 2019-07- IDA / 52240 A posteriori consultants par Direct 16,800.00 14,442.29 Signé de Technicienne de surface Supporting Project 15 13 23 23 02 03 02 entente directe de l'UGP Management MOF-CM-UGP-PFS-6421- Laying the Foundations of CS-INDV / Expert a Safety Net System and 2017-02- 2017-02- 2017-04- 2017-05- 2017-04- 2017-05- 2017-06- 2017-06- 2019-06- IDA / 52240 A posteriori Individuel Open 63,840.00 110,857.53 Signé environnemental et social Supporting Project 17 10 07 17 28 18 02 09 02 du PFS Management Laying the Foundations of MOF-CM-UGP-PFS-6423- a Safety Net System and 2017-02- 2017-01- 2017-03- 2017-05- 2017-04- 2017-05- 2017-05- 2017-06- 2018-05- 2018-06- CS-INDV / Assistant IDA / 52240 A posteriori Individuel Open 9,600.00 27,305.89 Signé Supporting Project 07 11 28 17 18 17 23 13 23 13 Comptable Management Laying the Foundations of MOF-CM-UGP-PFS-6424- a Safety Net System and 2017-02- 2017-01- 2017-03- 2017-04- 2017-04- 2017-04- 2017-05- 2017-05- 2018-05- IDA / 52240 A posteriori Individuel Open 9,600.00 6,156.07 Résilié CS-INDV / Assistant SPM Supporting Project 07 11 28 12 18 21 23 10 23 Management Laying the Foundations of CM-UGP-PFS-108883-CS- a Safety Net System and 2019-04- 2019-03- 2019-06- 2019-08- 2019-07- 2019-08- 2019-08- 2019-09- 2020-08- INDV / Auditeur interne du IDA / 52240 A posteriori Individuel Open 45,714.00 29,878.57 Signé Supporting Project 19 24 16 08 07 13 04 09 03 Projet Filets Sociaux Management CM-UGP-PFS-111619-CS- CDS / Avenant N°01 au Cash Transfer Program Sélection de contrat de l'Opérateur de with Accompanying 2019-05- 2017-01- 2019-06- 2019-03- 2019-08- 2019-03- 2019-12- IDA / 52240 A posteriori consultants par Direct 2,160.00 1,832.99 Signé Terrain 1 de la Commune Measures to Boost 22 12 01 14 05 20 05 entente directe de Banyo, Département du Household Productivity Mayo Banyo, Région de l'Adamaoua CM-UGP-PFS-111629-CS- CDS / Avenant Contrat de Cash Transfer Program Sélection de l'Opérateur de Terrain 2 de with Accompanying 2019-05- 2017-01- 2019-06- 2019-03- 2019-08- 2019-03- 2019-12- IDA / 52240 A posteriori consultants par Direct 2,160.00 1,845.59 Signé la Commune de Banyo, Measures to Boost 22 12 01 14 05 20 05 entente directe Département du Mayo Household Productivity Banyo, Région de l'Adamaoua CM-UGP-PFS-111638-CS- CDS / Avenant contrat de Cash Transfer Program Sélection de l'Opérateur de Terrain de la with Accompanying 2019-05- 2017-01- 2019-06- 2019-03- 2019-08- 2019-03- 2020-01- IDA / 52240 A posteriori consultants par Direct 2,898.00 2,459.26 Signé Commune de Bélo, Measures to Boost 22 12 01 14 05 18 16 entente directe Département du Boyo, Household Productivity Région du Nord-Ouest CM-UGP-PFS-111640-CS- Cash Transfer Program Sélection de CDS / Avenant au contrat with Accompanying 2019-05- 2017-01- 2019-06- 2019-03- 2019-08- 2019-03- 2020-01- IDA / 52240 A posteriori consultants par Direct 2,898.00 15,181.83 Signé de l'Opérateur de Terrain 1 Measures to Boost 22 12 01 14 05 18 16 entente directe de Douala IIIe, Ville de Household Productivity Douala CM-UGP-PFS-111642-CS- Cash Transfer Program Sélection de CDS / Avenant de with Accompanying 2019-05- 2017-01- 2019-06- 2019-03- 2019-08- 2019-03- 2020-01- IDA / 52240 A posteriori consultants par Direct 2,898.00 15,181.83 Signé l'Opérateur de Terrain 2 de Measures to Boost 22 12 01 14 05 18 16 entente directe la Commune de Douala IIIe, Household Productivity Ville de Douala CM-UGP-PFS-111643-CS- Cash Transfer Program CDS / Avenant de Sélection de with Accompanying 2019-05- 2017-01- 2019-06- 2019-03- 2019-08- 2019-03- 2020-01- l'Opérateur de Terrain 1 de IDA / 52240 A posteriori consultants par Direct 2,898.00 15,181.83 Signé Measures to Boost 22 12 01 14 05 18 16 la Commune de Ketté, entente directe Household Productivity Département de la Kadey, Région de l'Est Page 7 CM-UGP-PFS-111658-CS- CDS / Avenant contrat de Cash Transfer Program Sélection de l'Opérateur de Terrain 2 de with Accompanying 2019-05- 2017-01- 2019-06- 2019-03- 2019-08- 2019-03- 2020-01- IDA / 52240 A posteriori consultants par Direct 2,898.00 15,181.83 Signé la Commune de Ketté, Measures to Boost 22 12 01 14 05 18 16 entente directe Département de la Kadey, Household Productivity Région de l'Est CM-UGP-PFS-111662-CS- Cash Transfer Program CDS / Avenant contrat de Sélection de with Accompanying 2019-05- 2017-01- 2019-06- 2019-03- 2019-08- 2019-03- 2020-01- l'Opératrice de Terrain 1 de IDA / 52240 A posteriori consultants par Direct 2,898.00 15,181.83 Signé Measures to Boost 22 12 01 14 05 18 16 la Commune de Yaoundé entente directe Household Productivity IIe, Ville de Yaoundé CM-UGP-PFS-111664-CS- CDS / Avenant contrat de Cash Transfer Program l'Opérateur de Terrain de la Sélection de with Accompanying 2019-05- 2017-01- 2019-06- 2019-03- 2019-08- 2019-03- 2019-11- Commune de Blangoua, IDA / 52240 A posteriori consultants par Direct 1,620.00 1,374.74 Signé Measures to Boost 22 12 01 14 05 20 04 Département du Logone et entente directe Household Productivity Chari, Région de l'Extrême- Nord CM-UGP-PFS-111670-CS- CDS / Avenant contrat de Cash Transfer Program l'Opérateur de Terrain de la Sélection de with Accompanying 2019-05- 2017-01- 2019-06- 2019-03- 2019-08- 2019-03- 2019-11- Commune de Bourha, IDA / 52240 A posteriori consultants par Direct 1,620.00 1,374.74 Signé Measures to Boost 22 12 01 14 05 20 04 Département du Mayo entente directe Household Productivity Tsanaga, Région de l'Extrême-Nord CM-UGP-PFS-111678-CS- CDS / Avenant contrat de Cash Transfer Program Sélection de l'Opérateur de Terrain de la with Accompanying 2019-05- 2017-01- 2019-06- 2019-03- 2019-08- 2019-03- 2019-11- IDA / 52240 A posteriori consultants par Direct 1,620.00 1,374.74 Signé Commune de Gobo, Measures to Boost 22 12 01 14 05 20 04 entente directe Département du Mayo Household Productivity Danay, Région de l'Extrême- Nord CM-UGP-PFS-111681-CS- CDS / Avenant contrat de Cash Transfer Program l'Opérateur de Terrain de la Sélection de with Accompanying 2019-05- 2017-01- 2019-06- 2019-03- 2019-08- 2019-03- 2019-11- Commune de Goulfey, IDA / 52240 A posteriori consultants par Direct 1,620.00 1,374.74 Signé Measures to Boost 22 12 01 14 05 20 04 Département du Logone et entente directe Household Productivity Chari, Région de l'Extrême- Nord CM-UGP-PFS-111685-CS- CDS / Avenant contrat de Cash Transfer Program l'Opérateur de Terrain de la Sélection de with Accompanying 2019-05- 2017-01- 2019-06- 2019-03- 2019-08- 2019-03- 2019-11- Commune de Koza, IDA / 52240 A posteriori consultants par Direct 1,620.00 1,374.74 Signé Measures to Boost 22 12 01 14 05 20 04 Département du Mayo entente directe Household Productivity Tsanaga, Région de l'Extrême-Nord CM-UGP-PFS-111688-CS- CDS / Avenant contrat de Cash Transfer Program l'Opérateur de Terrain de la Sélection de with Accompanying 2019-05- 2017-01- 2019-06- 2019-03- 2019-08- 2019-03- 2020-05- Commune de Makari, IDA / 52240 A posteriori consultants par Direct 4,860.00 4,124.22 Signé Measures to Boost 22 12 01 14 05 20 06 Département du Logone et entente directe Household Productivity Chari, Région de l'Extrême- Nord CM-UGP-PFS-111691-CS- CDS / Avenant de Cash Transfer Program Sélection de l'Opérateur de Terrain de la with Accompanying 2019-05- 2017-01- 2019-06- 2019-03- 2019-08- 2019-03- 2020-05- IDA / 52240 A posteriori consultants par Direct 4,860.00 4,124.22 Signé Commune de Mogodé, Measures to Boost 22 12 01 14 05 20 06 entente directe Département du Mayo Household Productivity Tsanaga, Région de l'Extrême-Nord CM-UGP-PFS-111692-CS- CDS / Avenant contrat de Cash Transfer Program Sélection de l'Opérateur de Terrain de la with Accompanying 2019-05- 2017-01- 2019-06- 2019-03- 2019-08- 2019-03- 2019-12- IDA / 52240 A posteriori consultants par Direct 2,160.00 1,832.99 Signé Commune de Mayo Oulo, Measures to Boost 22 12 01 14 05 20 05 entente directe Département du Mayo Household Productivity Louti, Région du Nord CM-UGP-PFS-111696-CS- Cash Transfer Program CDS / Avenant de Sélection de with Accompanying 2019-05- 2017-01- 2019-06- 2019-03- 2019-08- 2019-03- 2020-05- l'Opérateur de Terrain de la IDA / 52240 A posteriori consultants par Direct 4,860.00 4,124.22 Signé Measures to Boost 22 12 01 14 05 20 06 Commune de Rey Bouba, entente directe Household Productivity Département du Mayo Rey, Région du Nord CM-UGP-PFS-111698-CS- Cash Transfer Program CDS / Avenant de Sélection de with Accompanying 2019-05- 2017-01- 2019-06- 2019-03- 2019-08- 2019-03- 2020-05- l'Opérateur de Terrain de la IDA / 52240 A posteriori consultants par Direct 4,898.00 4,124.22 Signé Measures to Boost 22 12 01 14 05 20 06 Commune de Tchéboa, entente directe Household Productivity Département de la Bénoué, Région du Nord CM-UGP-PFS-111699-CS- Cash Transfer Program CDS / Avenant de Sélection de with Accompanying 2019-05- 2017-01- 2019-06- 2019-03- 2019-08- 2019-03- 2019-12- l'Opérateur de Terrain 1 de IDA / 52240 A posteriori consultants par Direct 2,160.00 1,832.99 Signé Measures to Boost 22 12 01 14 05 20 05 la Commune de Touboro, entente directe Household Productivity Département du Mayo Rey, Région du Nord CM-UGP-PFS-111725-CS- Cash Transfer Program CDS / Avenant contrat Point Sélection de with Accompanying 2019-05- 2017-01- 2019-06- 2019-03- 2019-08- 2019-03- 2020-01- Focal du Projet Filets IDA / 52240 A posteriori consultants par Direct 4,293.00 22,491.60 Signé Measures to Boost 22 12 01 14 05 18 16 Sociaux dans le entente directe Household Productivity Département de la Kadey, Région de l'Est CM-UGP-PFS-111726-CS- CDS / Avenant contrat Point Cash Transfer Program Sélection de Focal du Projet Filets with Accompanying 2019-05- 2017-01- 2019-06- 2019-03- 2019-08- 2019-03- 2020-05- IDA / 52240 A posteriori consultants par Direct 7,200.00 6,109.96 Signé Sociaux dans le Measures to Boost 22 12 01 14 05 20 06 entente directe Département du Logone et Household Productivity Chari, Région de l'Extrême- Nord CM-UGP-PFS-111727-CS- Cash Transfer Program CDS / Avenant contrat Point Sélection de with Accompanying 2019-05- 2017-01- 2019-06- 2019-03- 2019-08- 2019-03- 2019-12- Focal du Projet Filets IDA / 52240 A posteriori consultants par Direct 3,200.00 2,715.54 Signé Measures to Boost 22 12 01 14 05 20 05 Sociaux dans le entente directe Household Productivity Département du Mayo Banyo, Région de l'Adamaoua CM-UGP-PFS-111735-CS- CDS / Avenant contrat Point Cash Transfer Program Sélection de Focal du Projet Filets with Accompanying 2019-05- 2017-01- 2019-06- 2019-03- 2019-08- 2019-03- 2019-11- IDA / 52240 A posteriori consultants par Direct 2,400.00 2,036.65 Signé Sociaux dans le Measures to Boost 22 12 01 14 05 20 04 entente directe Département du Mayo Household Productivity Danay, Région de l'Extrême- Nord CM-UGP-PFS-111737-CS- CDS / Avenant contrat Point Cash Transfer Program Sélection de Focal du Projet Filets with Accompanying 2019-05- 2017-01- 2019-06- 2019-03- 2019-08- 2019-03- 2020-05- IDA / 52240 A posteriori consultants par Direct 7,200.00 6,109.96 Signé Sociaux dans le Measures to Boost 22 12 01 14 05 20 06 entente directe Département Mayo Household Productivity Tsanaga, Région de l'Extrême-Nord CM-UGP-PFS-111739-CS- Cash Transfer Program Sélection de CDS / Avenant contrat Point with Accompanying 2019-05- 2017-01- 2019-06- 2019-03- 2019-08- 2019-03- 2020-01- IDA / 52240 A posteriori consultants par Direct 4,293.00 22,491.60 Signé Focal du Projet Filets Measures to Boost 22 12 01 14 05 18 16 entente directe Sociaux dans la Ville de Household Productivity Yaoundé CM-UGP-PFS-121795-CS- CDS / Consultant chargé de Laying the Foundations of l'élaboration de la Sélection de a Safety Net System and En cours 2019-11- 2019-07- 2019-12- 2019-10- 2020-02- 2020-03- méthodologie de choix et IDA / 62230 A posteriori consultants par Direct 28,000.00 0.00 Supporting Project d'exécution 30 12 19 29 13 14 d’opérationnalisation du entente directe Management choix des communes bénéficiaires du Projet Filets Sociaux CM-UGP-PFS-141188-CS- INDV / Recrutement d'un Laying the Foundations of point Focal dans la ville a Safety Net System and 2019-12- 2020-02- 2020-02- 2020-03- 2022-03- IDA / 62230 A posteriori Individuel Open 19,200.00 0.00 Annulé de Douala, région du Supporting Project 10 04 25 31 31 littoral pour la phase 3 des Management Transferts Monétaires ordinaires CM-UGP-PFS-141191-CS- INDV / Recrutement d'un Laying the Foundations of Point Focal dans la ville de a Safety Net System and 2019-12- 2020-02- 2020-02- 2020-03- 2022-03- IDA / 62230 A posteriori Individuel Open 19,200.00 0.00 Annulé Yaoundé pour la cycle 3 Supporting Project 10 04 25 31 31 des Transferts Monétaires Management ordinaires CM-UGP-PFS-141758-CS- INDV / Recrutement d'un Consultant pour le ciblage Laying the Foundations of des 1000 bénéficiaires de a Safety Net System and En cours 2019-11- 2019-10- 2020-01- 2020-02- 2020-03- 2020-10- la Phase 3 des TMU du IDA / D2980 A posteriori Individuel Open 7,560.00 0.00 Supporting Project d'exécution 29 15 24 14 20 16 Projet Filets Sociaux dans la Management commune de Waza, département du Logone et Chari, région de l'Extrême- Nord CM-UGP-PFS-143558-CS- INDV / Recrutement de l'enquêteur Chercheur N°1 Laying the Foundations of de l'équipe septentrionale a Safety Net System and 2019-11- 2019-09- 2019-12- 2019-11- 2020-01- 2019-11- 2020-02- 2019-11- 2020-06- IDA / 62230 A posteriori Individuel Limited 5,394.00 4,942.86 Signé dans le cadre de la Supporting Project 29 27 20 25 03 26 07 27 06 préparation d'une Management évaluation qualitative sur les Violences Basées sur le Genre (VBG) au Cameroun CM-UGP-PFS-143560-CS- INDV / Recrutement de l'enquêteur Chercheur N°2 Laying the Foundations of de l'équipe septentrionale a Safety Net System and 2019-11- 2019-09- 2019-12- 2019-11- 2020-01- 2019-11- 2020-02- 2019-12- 2020-06- IDA / 62230 A posteriori Individuel Limited 5,394.00 4,942.86 Signé dans le cadre de la Supporting Project 29 27 20 26 03 26 07 06 06 préparation d'une Management évaluation qualitative sur les Violences Basées sur le Genre (VBG) au Cameroun CM-UGP-PFS-143562-CS- INDV / Recrutement de l'enquêteur Chercheur N°3 Laying the Foundations of de l'équipe septentrionale a Safety Net System and 2019-11- 2019-09- 2019-12- 2019-11- 2020-01- 2019-11- 2020-02- 2019-12- 2020-06- IDA / 62230 A posteriori Individuel Limited 5,394.00 4,942.86 Signé dans le cadre de la Supporting Project 29 27 20 26 03 26 07 16 06 préparation d'une Management évaluation qualitative sur les Violences Basées sur le Genre (VBG) au Cameroun CM-UGP-PFS-143563-CS- INDV / Recrutement de l'enquêteur Chercheur N°4 Laying the Foundations of de l'équipe septentrionale a Safety Net System and 2019-11- 2019-09- 2019-12- 2019-11- 2020-01- 2019-11- 2020-02- 2019-11- 2020-06- IDA / 62230 A posteriori Individuel Limited 5,394.00 7,719.29 Signé dans le cadre de la Supporting Project 29 27 20 26 03 26 07 27 06 préparation d'une Management évaluation qualitative sur les Violences Basées sur le Genre (VBG) au Cameroun CM-UGP-PFS-143564-CS- INDV / Recrutement de l'enquêteur Chercheur N°1 Laying the Foundations of de l'équipe Adamaoua-Est a Safety Net System and 2019-11- 2019-09- 2019-12- 2019-11- 2020-01- 2019-11- 2020-02- 2019-12- 2020-06- IDA / 62230 A posteriori Individuel Limited 4,902.00 4,529.24 Signé dans le cadre de la Supporting Project 29 27 20 25 03 26 07 06 06 préparation d'une Management évaluation qualitative sur les Violences Basées sur le Genre (VBG) au Cameroun CM-UGP-PFS-143565-CS- INDV / Recrutement de l'enquêteur Chercheur N°2 Laying the Foundations of de l'équipe Adamaoua-Est a Safety Net System and 2019-11- 2019-09- 2019-12- 2019-11- 2020-01- 2019-11- 2020-02- 2019-12- 2020-06- IDA / 62230 A posteriori Individuel Limited 4,902.00 4,529.24 Signé dans le cadre de la Supporting Project 29 27 20 25 03 26 07 06 06 préparation d'une Management évaluation qualitative sur les Violences Basées sur le Genre (VBG) au Cameroun CM-UGP-PFS-143567-CS- INDV / Recrutement de l'enquêteur Chercheur N°3 Laying the Foundations of de l'équipe Adamaoua-Est a Safety Net System and 2019-11- 2019-09- 2019-12- 2019-11- 2020-01- 2019-11- 2020-02- 2019-12- 2020-06- IDA / 62230 A posteriori Individuel Limited 4,902.00 4,529.24 Signé dans le cadre de la Supporting Project 29 27 20 25 03 26 07 13 06 préparation d'une Management évaluation qualitative sur les Violences Basées sur le Genre (VBG) au Cameroun CM-UGP-PFS-143568-CS- INDV / Recrutement de l'enquêteur Chercheur N°4 Laying the Foundations of de l'équipe Adamaoua-Est a Safety Net System and 2019-11- 2019-09- 2019-12- 2019-11- 2020-01- 2019-11- 2020-02- 2019-12- 2020-06- IDA / 62230 A posteriori Individuel Limited 4,394.00 4,529.24 Signé dans le cadre de la Supporting Project 29 27 20 25 03 26 07 06 06 préparation d'une Management évaluation qualitative sur les Violences Basées sur le Genre (VBG) au Cameroun CM-UGP-PFS-152346-CS- INDV / RECRUTEMENT DU CONSULTANT CHARGE Laying the Foundations of D’INSTALLER ET DE a Safety Net System and En cours 2020-01- 2020-01- 2020-02- 2020-01- 2020-02- 2020-02- 2020-04- 2020-07- PARAMETRER LES LOGICIELS IDA / 62230 A posteriori Individuel Limited 7,500.00 0.00 Supporting Project d'exécution 31 22 07 22 28 05 04 03 TOM2PRO, TOM2MARCHE Management ET TOM2PAIE D’UNE PART ET D’AUTRE PART DE RENFORCER LES CAPACITES DE L’UGP CM-UGP-PFS-142945-CS- CDS / Recrutement d'une ONG pour la mise en œuvre Sélection de En cours 2020-02- 2019-10- 2020-02- 2020-05- 2020-12- des activités de la Phase 7 IDA / D2980 Public Works Program Pilot A posteriori consultants par Direct 99,042.00 0.00 d'exécution 10 15 29 04 30 des THIMO dans la région entente directe de l'Extrême Nord, commune de Mokolo Page 8 CM-UGP-PFS-142946-CS- CDS / Recrutement d'une Sélection de ONG pour la mise en œuvre En cours 2020-02- 2020-02- 2020-02- 2020-05- 2020-12- IDA / D2980 Public Works Program Pilot A posteriori consultants par Direct 132,056.00 0.00 des activités de la Phase 7 d'exécution 10 28 29 04 30 entente directe des THIMO dans la région du Nord , commune de Touboro CM-UGP-PFS-142944-CS- CDS / Recrutement d'une ONG pour la mise en œuvre Sélection de des activités de la Phase 7 En cours 2020-02- 2019-10- 2020-02- 2020-05- 2020-12- IDA / D2980 Public Works Program Pilot A posteriori consultants par Direct 99,042.00 0.00 des THIMO dans les d'exécution 10 16 29 04 30 entente directe régions de l'Adamaoua (commune de Dir) et de l'Est (Communes de Ngoura et de Mandjou) CM-UGP-PFS-141791-CS- INDV / Recrutement d'un Consultant pour le ciblage Laying the Foundations of des 2000 bénéficiaires du a Safety Net System and En cours 2020-06- 2020-08- 2020-09- 2020-10- 2021-04- cycle 3 des TMO du Projet IDA / D2980 A posteriori Individuel Open 10,400.00 0.00 Supporting Project d'exécution 30 25 15 20 18 Filets Sociaux dans la Management commune de Garoua Boulaï , département du Lom et Djérem, région de l'Est CM-UGP-PFS-141143-CS- INDV / Recrutement de l' Opérateur de Terrain N°1 du Projet Filets Sociaux de Laying the Foundations of la Commune de Logone a Safety Net System and En attente 2020-06- 2020-08- 2020-09- 2020-10- 2022-10- IDA / D2980 A posteriori Individuel Open 12,960.00 0.00 Birni, département du Supporting Project d'exécution 30 25 15 20 20 Logone et Chari, région de Management l'Extrême Nord pour le cycle 3 des Transferts Monétaires Ordinaires CM-UGP-PFS-141192-CS- INDV / Recrutement d'un Consultant pour le ciblage Laying the Foundations of des 1000 bénéficiaires de a Safety Net System and En cours 2020-06- 2019-10- 2020-08- 2020-04- 2020-09- 2020-10- 2021-05- la Phase 3 des TMU du IDA / D2980 A posteriori Individuel Open 7,560.00 0.00 Supporting Project d'exécution 30 16 25 11 15 20 18 Projet Filets Sociaux dans la Management commune de Fotokol, département du Logone et Chari, région de l'Extrême- Nord CM-UGP-PFS-141091-CS- INDV / Recrutement d'un Laying the Foundations of Responsable Régional dans a Safety Net System and En cours 2020-06- 2019-10- 2020-08- 2020-09- 2020-10- 2022-10- IDA / D2980 A posteriori Individuel Open 38,400.00 0.00 la Région de l'Est pour la Supporting Project d'exécution 30 10 25 15 20 20 cycle 3 des Transferts Management Monétaires ordinaires CM-UGP-PFS-141718-CS- INDV / Recrutement de l'Opérateur de Terrain I de Laying the Foundations of la Commune de Meiganga, a Safety Net System and En cours 2020-06- 2019-10- 2020-08- 2020-09- 2020-10- 2022-10- IDA / D2980 A posteriori Individuel Open 12,960.00 0.00 département du Mbéré, Supporting Project d'exécution 30 10 25 15 20 20 région de l'Adamaoua pour Management le cycle 3 des Transferts Monétaires Ordinaires CM-UGP-PFS-141717-CS- INDV / Recrutement de l'Opérateur de Terrain N°2 Laying the Foundations of de la Commune de Logone a Safety Net System and En cours 2020-06- 2019-10- 2020-08- 2020-09- 2020-10- 2022-10- Birni, département du IDA / D2980 A posteriori Individuel Open 12,960.00 0.00 Supporting Project d'exécution 30 10 25 15 20 20 Logone et Chari, région de Management l'Extrême Nord pour le cycle 3 des Transferts Monétaires Ordinaires CM-UGP-PFS-141793-CS- INDV / Recrutement d'un Consultant pour le ciblage Laying the Foundations of des 3000 bénéficiaires du a Safety Net System and En cours 2020-06- 2019-10- 2020-08- 2020-09- 2020-10- 2022-10- IDA / D2980 A posteriori Individuel Open 12,950.00 0.00 cycle 3 des TMO du Projet Supporting Project d'exécution 30 15 25 15 20 20 Filets Sociaux dans la Management commune de Touboro, département du Mayo-Rey, région du Nord CM-UGP-PFS-141162-CS- INDV / Recrutement d'un Opérateur de Terrain dans Laying the Foundations of la Commune de a Safety Net System and En cours 2020-06- 2019-10- 2020-08- 2020-09- 2020-10- 2022-10- IDA / 62230 A posteriori Individuel Open 12,960.00 0.00 Meyomessala, Département Supporting Project d'exécution 30 10 25 15 20 20 du Dja et Lobo, région du Management Sud pour le cycle 3 des Transferts Monétaires Ordinaires CM-UGP-PFS-141731-CS- INDV / Recrutement de l'Opérateur de Terrain N°2 Laying the Foundations of du Projet Filets Sociaux a Safety Net System and 2020-06- 2019-10- 2020-08- 2020-05- 2020-09- 2020-05- 2020-10- 2020-06- 2022-10- dans la Commune de IDA / 62230 A posteriori Individuel Open 12,960.00 11,666.27 Signé Supporting Project 30 10 25 17 15 19 20 09 20 Moulvoudaye , département Management du Mayo Kani, région de l'Extrême- Nord pour le cycle 3 des Transferts Monétaires Ordinaires CM-UGP-PFS-141171-CS- INDV / Recrutement d'un Opérateur de Terrain dans Laying the Foundations of la Commune de Fotokol, a Safety Net System and En cours 2020-06- 2019-10- 2020-08- 2020-09- 2020-10- 2021-10- département du Logone et IDA / D2980 A posteriori Individuel Open 6,480.00 0.00 Supporting Project d'exécution 30 10 25 15 20 20 Chari, région de l'Extrême Management Nord pour la phase 3 des Transferts Monétaires d'Urgence CM-UGP-PFS-141780-CS- INDV / Recrutement d'un Consultant pour le ciblage Laying the Foundations of des 2000 bénéficiaires du a Safety Net System and En cours 2020-06- 2019-10- 2020-08- 2020-09- 2020-10- 2021-05- IDA / D2980 A posteriori Individuel Open 10,400.00 0.00 cycle 3 des TMO du Projet Supporting Project d'exécution 30 15 25 15 20 18 Filets Sociaux dans la Management commune de Meiganga , département du Mbéré, région de l'Adamaoua CM-UGP-PFS-141196-CS- INDV / Recrutement d'un Consultant pour le ciblage Laying the Foundations of des 2000 bénéficiaires du a Safety Net System and En cours 2020-06- 2019-10- 2020-08- 2020-09- 2020-10- 2021-05- IDA / 62230 A posteriori Individuel Open 10,400.00 0.00 cycle 3 des TMO du Projet Supporting Project d'exécution 30 15 25 15 20 18 Filets Sociaux dans la Management commune de Madringrin , département du Mayo-Rey, région du Nord CM-UGP-PFS-141170-CS- INDV / Recrutement d'un Opérateur de Terrain dans Laying the Foundations of la Commune de Waza, a Safety Net System and En cours 2020-06- 2019-10- 2020-08- 2020-09- 2020-10- 2021-10- département du Logone et IDA / D2980 A posteriori Individuel Open 6,480.00 0.00 Supporting Project d'exécution 30 10 25 15 20 20 Chari, région de l'Extrême Management Nord pour la phase 3 des Transferts Monétaires d'Urgence CM-UGP-PFS-141801-CS- INDV / Recrutement d'un Consultant pour le ciblage Laying the Foundations of des 1000 bénéficiaires du a Safety Net System and En cours 2020-06- 2019-10- 2020-08- 2020-09- 2020-10- 2021-05- IDA / 62230 A posteriori Individuel Open 6,320.00 0.00 cycle 3 des TMO du Projet Supporting Project d'exécution 30 15 25 15 20 18 Filets Sociaux dans la Management commune de Ma'an , département de la Valée du Ntem, région du Sud CM-UGP-PFS-141167-CS- INDV / Recrutement d'un Opérateur de Terrain dans Laying the Foundations of la Commune de Meiganga, a Safety Net System and En cours 2020-06- 2019-10- 2020-08- 2020-05- 2020-09- 2020-10- 2021-10- IDA / D2980 A posteriori Individuel Open 6,480.00 0.00 département du Mbéré, Supporting Project d'exécution 30 10 25 26 15 20 20 région de l'Adamaoua pour Management la phase 3 des Transferts Monétaires d'Urgence CM-UGP-PFS-141168-CS- INDV / Recrutement d'un Opérateur de Terrain dans Laying the Foundations of la Commune de Ngaoui, a Safety Net System and En cours 2020-06- 2019-10- 2020-08- 2020-09- 2020-10- 2021-10- IDA / D2980 A posteriori Individuel Open 6,480.00 0.00 département du Mbéré, Supporting Project d'exécution 30 10 25 15 20 20 région de l'Adamaoua pour Management la phase 3 des Transferts Monétaires d'Urgence CM-UGP-PFS-141160-CS- INDV / Recrutement de l'Opérateur de Terrain N°1 Laying the Foundations of de la la Commune de a Safety Net System and 2020-06- 2019-10- 2020-08- 2020-04- 2020-09- 2020-04- 2020-10- 2020-05- 2022-10- IDA / 62230 A posteriori Individuel Open 12,960.00 11,502.26 Signé Madingring , département Supporting Project 30 10 25 11 15 16 20 13 20 du Mayo Rey, région du Management Nord pour le cycle 3 des Transferts Monetaires Ordinaires CM-UGP-PFS-141755-CS- INDV / Recrutement d'un Consultant pour le ciblage Laying the Foundations of des 1000 bénéficiaires de a Safety Net System and En cours 2020-06- 2019-10- 2020-08- 2020-09- 2020-10- 2021-05- IDA / D2980 A posteriori Individuel Open 7,560.00 0.00 la Phase 3 des TMU du Supporting Project d'exécution 30 15 25 15 20 18 Projet Filets Sociaux dans la Management commune de Ngaoui, département du Mbéré, région de l'Adamaoua CM-UGP-PFS-141794-CS- INDV / Recrutement d'un Consultant pour le ciblage Laying the Foundations of des 1000 bénéficiaires du a Safety Net System and En cours 2020-06- 2019-10- 2020-08- 2020-03- 2020-09- 2020-10- 2021-05- IDA / 62230 A posteriori Individuel Open 6,320.00 0.00 cycle 3 des TMO du Projet Supporting Project d'exécution 30 16 25 16 15 20 18 Filets Sociaux dans la Management commune d' Ebolowa II, département de la Mvila, région du Sud CM-UGP-PFS-141184-CS- INDV / Recrutement d'un Laying the Foundations of Point Focal dans le a Safety Net System and En cours 2020-06- 2019-10- 2020-08- 2020-09- 2020-10- 2022-10- département du Mayo Rey, IDA / D2980 A posteriori Individuel Open 19,200.00 0.00 Supporting Project d'exécution 30 10 25 15 20 20 région du Nord pour la Management cycle 3 des Transferts Monétaires ordinaires CM-UGP-PFS-141145-CS- INDV / Recrutement de l'Opérateur de Terrain N°1 Laying the Foundations of du Projet Filets Sociaux a Safety Net System and En cours 2020-06- 2019-10- 2020-08- 2020-09- 2020-10- 2022-10- dans la Commune de Bétaré IDA / D2980 A posteriori Individuel Open 12,960.00 0.00 Supporting Project d'exécution 30 10 25 15 20 20 Oya, département du Lom Management et Djérem, région de l'Est pour le cycle 3 des Transferts Monétaires Ordinaires CM-UGP-PFS-141787-CS- INDV / Recrutement d'un Consultant pour le ciblage Laying the Foundations of des 1500 bénéficiaires du a Safety Net System and En cours 2020-06- 2019-10- 2020-08- 2020-09- 2020-10- 2021-05- cycle 3 des TMO du Projet IDA / D2980 A posteriori Individuel Open 7,850.00 0.00 Supporting Project d'exécution 30 15 25 15 20 18 Filets Sociaux dans la Management commune de Logone Birni, département du Logone et Chari, région de l'Extrême- Nord CM-UGP-PFS-141812-CS- INDV / Recrutement d'un Laying the Foundations of Consultant pour le ciblage a Safety Net System and En attente 2020-06- 2020-08- 2020-09- 2020-10- 2021-05- des 1500 bénéficiaires du IDA / 62230 A posteriori Individuel Open 7,850.00 0.00 Supporting Project d'exécution 30 25 15 20 18 cycle 3 des TMO du Projet Management Filets Sociaux dans la commune de Yaoundé III , Ville de Yaoundé CM-UGP-PFS-141727-CS- INDV / Recrutement de l'Opérateur de Terrain N°2 Laying the Foundations of du Projet Filets Sociaux a Safety Net System and En cours 2020-06- 2019-10- 2020-08- 2020-09- 2020-10- 2022-10- dans la Commune de Bétaré IDA / D2980 A posteriori Individuel Open 12,960.00 0.00 Supporting Project d'exécution 30 10 25 15 20 20 Oya, département du Lom Management et Djérem, région de l'Est pour le cycle 3 des Transferts Monétaires Ordinaires CM-UGP-PFS-141164-CS- INDV / Recrutement d'un Opérateur de Terrain dans Laying the Foundations of la Commune de Ma'am, a Safety Net System and En cours 2020-06- 2019-10- 2020-08- 2020-09- 2020-10- 2022-10- IDA / 62230 A posteriori Individuel Open 12,960.00 0.00 Département de la Vallée Supporting Project d'exécution 30 10 25 15 20 20 du Ntem, région du Sud Management pour le cycle 3 des Transferts Monétaires Ordinaires CM-UGP-PFS-141800-CS- INDV / Recrutement d'un Consultant pour le ciblage Laying the Foundations of des 1000 bénéficiaires du a Safety Net System and En cours 2020-06- 2019-10- 2020-08- 2020-09- 2020-10- 2021-05- IDA / 62230 A posteriori Individuel Open 6,320.00 0.00 cycle 3 des TMO du Projet Supporting Project d'exécution 30 15 25 15 20 18 Filets Sociaux dans la Management commune de Meyomessala, département du Dja et Lobo, région du Sud Page 9 CM-UGP-PFS-141159-CS- INDV / Recrutement de l'Opérateur de Terrain N°1 Laying the Foundations of du Projet Filets Sociaux a Safety Net System and 2020-06- 2019-10- 2020-08- 2020-05- 2020-09- 2020-05- 2020-10- 2020-06- 2022-10- dans la Commune de IDA / 62230 A posteriori Individuel Open 12,960.00 0.00 Signé Supporting Project 30 10 25 09 15 12 20 09 20 Moulvoudaye , département Management du Mayo Kani, région de l'Extrême- Nord pour le cycle 3 des Transferts Monétaires Ordinaires CM-UGP-PFS-141097-CS- INDV / Recrutement d'un Laying the Foundations of Responsable Régional dans a Safety Net System and En cours 2020-06- 2019-10- 2020-08- 2020-09- 2020-10- 2022-10- IDA / 62230 A posteriori Individuel Open 38,400.00 0.00 la Région du SUD pour la Supporting Project d'exécution 30 10 25 15 20 20 cycle 3 des Transferts Management Monétaires ordinaires CM-UGP-PFS-141163-CS- INDV / Recrutement d'un Opérateur de Terrain dans Laying the Foundations of la Commune d'Ebolowa II, a Safety Net System and En cours 2020-06- 2019-10- 2020-08- 2020-09- 2020-10- 2022-10- IDA / 62230 A posteriori Individuel Open 12,960.00 0.00 département de la Mvila, Supporting Project d'exécution 30 10 25 15 20 20 région du Sud pour le cycle Management 3 des Transferts Monétaires Ordinaires CM-UGP-PFS-141141-CS- INDV / Recrutement de l'Opérateur de Terrain N°1 Laying the Foundations of du Projet Filets Sociaux de a Safety Net System and En cours 2020-06- 2019-10- 2020-08- 2020-09- 2020-10- 2022-10- la Commune de Meiganga, IDA / D2980 A posteriori Individuel Open 12,960.00 0.00 Supporting Project d'exécution 30 10 25 15 20 20 département du Mbéré, Management région de l'Adamaoua pour le cycle 3 des Transferts Monétaires Ordinaires CM-UGP-PFS-141161-CS- INDV / Recrutement de 3 Opérateurs de Terrain Laying the Foundations of dans la Commune de a Safety Net System and En cours 2020-06- 2019-10- 2020-08- 2020-04- 2020-09- 2020-04- 2020-10- 2022-10- IDA / D2980 A posteriori Individuel Open 38,880.00 0.00 Touboro, département du Supporting Project d'exécution 30 10 25 24 15 30 20 20 Mayo-Rey, région du Nord Management pour le cycle 3 des Transferts Monétaires Ordinaires CM-UGP-PFS-141735-CS- INDV / Recrutement de l'Opérateur de Terrain N°2 Laying the Foundations of de la la Commune de a Safety Net System and 2020-06- 2019-10- 2020-08- 2020-04- 2020-09- 2020-04- 2020-10- 2020-05- 2022-10- IDA / 62230 A posteriori Individuel Open 12,960.00 11,567.97 Signé Madingring , département Supporting Project 30 10 25 11 15 17 20 13 20 du Mayo Rey, région du Management Nord pour le cycle 3 des Transferts Monetaires Ordinaires CM-UGP-PFS-141155-CS- INDV / Recrutement de l'Opérateur de Terrain N°1 Laying the Foundations of du Projet filets sociaux a Safety Net System and En cours 2020-06- 2019-10- 2020-08- 2020-09- 2020-10- 2022-10- dans la Commune de IDA / D2980 A posteriori Individuel Open 12,960.00 0.00 Supporting Project d'exécution 30 10 25 15 20 20 Garoua-Boulaï, Management département du Lom et Djérem, région de l'Est pour le cycle 3 des Transferts Monétaires Ordinaires CM-UGP-PFS-141785-CS- INDV / Recrutement d'un Consultant pour le ciblage Laying the Foundations of des 2000 bénéficiaires du a Safety Net System and En cours 2020-06- 2019-10- 2020-08- 2020-09- 2020-10- 2021-05- cycle 3 des TMO du Projet IDA / 62230 A posteriori Individuel Open 10,400.00 0.00 Supporting Project d'exécution 30 15 25 15 20 18 Filets Sociaux dans la Management commune de Moulvoudaye , département du Mayo Kani, région de l'Extrême- Nord CM-UGP-PFS-141183-CS- INDV / Recrutement d'un Point Focal dans le Laying the Foundations of département du Logone et a Safety Net System and En cours 2020-06- 2019-10- 2020-08- 2020-09- 2020-10- 2022-10- IDA / D2980 A posteriori Individuel Open 19,200.00 0.00 Chari, région de l'Extrême Supporting Project d'exécution 30 10 25 15 20 20 Nord pour la cycle 3 des Management Transferts Monétaires ordinaires CM-UGP-PFS-141804-CS- INDV / Recrutement d'un Consultant pour le ciblage Laying the Foundations of des1500 bénéficiaires du a Safety Net System and En attente 2020-06- 2020-08- 2020-09- 2020-10- 2021-05- IDA / 62230 A posteriori Individuel Open 7,850.00 0.00 cycle 3 des TMO du Projet Supporting Project d'exécution 30 25 15 20 18 Filets Sociaux dans la Management commune de Douala V , Ville de Douala CM-UGP-PFS-141187-CS- INDV / Recrutement d'un Laying the Foundations of Point Focal dans le a Safety Net System and En cours 2020-06- 2019-10- 2020-08- 2020-09- 2020-10- 2022-10- département du Mayo Kani, IDA / 62230 A posteriori Individuel Open 19,200.00 0.00 Supporting Project d'exécution 30 10 25 15 20 20 région de l'Extrême Nord Management pour la cycle 3 des Transferts Monétaires ordinaires CM-UGP-PFS-141084-CS- INDV / Recrutement d'un Laying the Foundations of Responsable Régional dans a Safety Net System and En cours 2020-06- 2019-10- 2020-08- 2020-09- 2020-10- 2022-10- IDA / D2980 A posteriori Individuel Open 38,400.00 0.00 la Région de l'Adamaoua Supporting Project d'exécution 30 10 25 15 20 20 pour la cycle 3 des Management Transferts Monétaires ordinaires CM-UGP-PFS-141729-CS- INDV / Recrutement de l'Opérateur de Terrain N°2 Laying the Foundations of du Projet filets sociaux a Safety Net System and En cours 2020-06- 2019-10- 2020-08- 2020-09- 2020-10- 2022-10- dans la Commune de IDA / D2980 A posteriori Individuel Open 12,960.00 0.00 Supporting Project d'exécution 30 10 25 15 20 20 Garoua-Boulaï, Management département du Lom et Djérem, région de l'Est pour le cycle 3 des Transferts Monétaires Ordinaires CM-UGP-PFS-141725-CS- INDV / Recrutement de l'Opérateur de Terrain N°2 Laying the Foundations of du Projet Filets Sociaux de a Safety Net System and En cours 2020-06- 2019-10- 2020-08- 2020-09- 2020-10- 2022-10- la Commune de Meiganga, IDA / D2980 A posteriori Individuel Open 12,960.00 0.00 Supporting Project d'exécution 30 10 25 15 20 20 département du Mbéré, Management région de l'Adamaoua pour le cycle 3 des Transferts Monétaires Ordinaires CM-UGP-PFS-141193-CS- INDV / Recrutement d'un Consultant pour le ciblage Laying the Foundations of des 2000 bénéficiaires du a Safety Net System and En attente 2020-06- 2020-08- 2020-09- 2020-10- 2021-05- IDA / D2980 A posteriori Individuel Open 10,400.00 0.00 cycle 3 des TMO du Projet Supporting Project d'exécution 30 25 15 20 18 Filets Sociaux dans la Management commune de Bétaré Oya , département du Lom et Djérem, région de l'Est Laying the Foundations of CM-UGP-PFS-172114-CS- a Safety Net System and En cours 2020-05- 2020-10- 2020-07- 2020-08- 2020-09- 2021-09- INDV / Recrutement d'un IDA / 62230 A posteriori Individuel Open 14,400.00 0.00 Supporting Project d'exécution 25 28 16 06 10 10 Assistant SPM Management CM-UGP-PFS-172210-CS- INDV / Recrutement d'un Laying the Foundations of consultant pour la a Safety Net System and En cours 2020-06- 2020-06- 2020-08- 2020-09- 2020-10- 2021-10- IDA / 62230 A posteriori Individuel Open 41,122.00 0.00 traduction des documents Supporting Project d'exécution 22 29 13 03 08 08 du Projet Filets Sociaux en Management Anglais/ Français CM-UGP-PFS-141752-CS- INDV / Recrutement d'un Consultant pour le ciblage Laying the Foundations of des 1000 bénéficiaires de a Safety Net System and En cours 2020-06- 2019-10- 2020-08- 2020-09- 2020-10- 2021-05- IDA / D2980 A posteriori Individuel Open 7,560.00 0.00 la Phase 3 des TMU du Supporting Project d'exécution 30 15 25 15 20 18 Projet Filets Sociaux dans la Management commune de Meiganga, département du Mbéré, région de l'Adamaoua CM-UGP-PFS-176264-CS- INDV / Recrutement par Entente Directe d'un Laying the Foundations of Consultant pour le ciblage a Safety Net System and En cours 2020-06- 2020-06- 2020-06- 2020-07- 2020-08- 2021-02- des 2000 bénéficiaires du IDA / D2980 A posteriori Individuel Direct 10,400.00 0.00 Supporting Project d'exécution 10 30 20 11 15 11 cycle 3 des TMO du Projet Management Filets Sociaux dans la commune de Meiganga , département du Mbéré, Région de l'Adamaoua CM-UGP-PFS-141174-CS- INDV / Recrutement d'un Opérateur de Terrain dans Laying the Foundations of la Commune de Bamenda II, a Safety Net System and 2020-06- 2020-08- 2020-09- 2020-10- 2021-10- IDA / 62230 A posteriori Individuel Open 6,480.00 0.00 Annulé département de MEZAM, Supporting Project 30 25 15 20 20 région du Nord-Ouest Management pour la phase 3 des Transferts Monétaires d'Urgence CM-UGP-PFS-141763-CS- INDV / Recrutement d'un Consultant pour le ciblage Laying the Foundations of des 500 bénéficiaires de la a Safety Net System and 2020-06- 2020-08- 2020-09- 2020-10- 2021-05- IDA / 62230 A posteriori Individuel Open 4,920.00 0.00 Annulé Phase 3 des TMU du Projet Supporting Project 30 25 15 20 18 Filets Sociaux dans la Management commune de Bamenda II , département de la Mezam, région du Nord-Ouest CM-UGP-PFS-141771-CS- INDV / Recrutement d'un Consultant pour le ciblage Laying the Foundations of des 500 bénéficiaires de la a Safety Net System and 2020-06- 2020-08- 2020-09- 2020-10- 2021-05- IDA / 62230 A posteriori Individuel Open 4,920.00 0.00 Annulé Phase 3 des TMU du Projet Supporting Project 30 25 15 20 18 Filets Sociaux dans la Management commune de Limbé III, département du Fako, région du Sud-Ouest CM-UGP-PFS-141765-CS- INDV / Recrutement d'un Consultant pour le ciblage Laying the Foundations of des 1000 bénéficiaires de a Safety Net System and 2020-06- 2020-08- 2020-09- 2020-10- 2021-05- la Phase 3 des TMU du IDA / 62230 A posteriori Individuel Open 7,560.00 0.00 Annulé Supporting Project 30 25 15 20 18 Projet Filets Sociaux dans la Management commune de Bamenda III , département de la Mezam, région du Nord-Ouest CM-UGP-PFS-141178-CS- INDV / Recrutement d'un Opérateur de Terrain dans Laying the Foundations of la Commune de Limbé I, a Safety Net System and 2020-06- 2020-08- 2020-09- 2020-10- 2021-10- IDA / 62230 A posteriori Individuel Open 6,480.00 0.00 Annulé département de Fako, Supporting Project 30 25 15 20 20 région du Sud-Ouest pour Management la phase 3 des Transferts Monétaires d'Urgence CM-UGP-PFS-141179-CS- INDV / Recrutement d'un Opérateur de Terrain dans Laying the Foundations of la Commune de Limbé II, a Safety Net System and 2020-06- 2020-08- 2020-09- 2020-10- 2021-10- IDA / 62230 A posteriori Individuel Open 6,480.00 0.00 Annulé département de Fako, Supporting Project 30 25 15 20 20 région du Sud-Ouest pour Management la phase 3 des Transferts Monétaires d'Urgence CM-UGP-PFS-141769-CS- INDV / Recrutement d'un Consultant pour le ciblage Laying the Foundations of des 500 bénéficiaires de la a Safety Net System and 2020-06- 2020-08- 2020-09- 2020-10- 2021-05- IDA / 62230 A posteriori Individuel Open 4,920.00 0.00 Annulé Phase 3 des TMU du Projet Supporting Project 30 25 15 20 18 Filets Sociaux dans la Management commune de Limbé II, département du Fako, région du Sud-Ouest CM-UGP-PFS-141197-CS- INDV / Recrutement d'un Consultant pour le ciblage Laying the Foundations of des 500 bénéficiaires de la a Safety Net System and 2020-06- 2020-08- 2020-09- 2020-10- 2021-05- IDA / 62230 A posteriori Individuel Open 4,920.00 0.00 Annulé Phase 3 des TMU du Projet Supporting Project 30 25 15 20 18 Filets Sociaux dans la Management commune de Bamenda I, département de la Mezam, région du Nord-Ouest CM-UGP-PFS-141173-CS- INDV / Recrutement d'un Opérateur de Terrain dans Laying the Foundations of la Commune de Bamenda I, a Safety Net System and 2020-06- 2020-08- 2020-09- 2020-10- 2021-10- IDA / 62230 A posteriori Individuel Open 6,480.00 0.00 Annulé département de MEZAM, Supporting Project 30 25 15 20 20 région du Nord-Ouest Management pour la phase 3 des Transferts Monétaires d'Urgence CM-UGP-PFS-141180-CS- INDV / Recrutement d'un Opérateur de Terrain dans Laying the Foundations of la Commune de Limbé III, a Safety Net System and 2020-06- 2020-08- 2020-09- 2020-10- 2021-10- IDA / 62230 A posteriori Individuel Open 6,480.00 0.00 Annulé département de Fako, Supporting Project 30 25 15 20 20 région du Sud-Ouest pour Management la phase 3 des Transferts Monétaires d'Urgence Page 10 CM-UGP-PFS-141176-CS- INDV / Recrutement d'un Opérateur de Terrain dans Laying the Foundations of la Commune de Bamenda a Safety Net System and 2020-06- 2020-08- 2020-09- 2020-10- 2021-10- IDA / 62230 A posteriori Individuel Open 6,480.00 0.00 Annulé III, département de MEZAM, Supporting Project 30 25 15 20 20 région du Nord-Ouest Management pour la phase 3 des Transferts Monétaires d'Urgence CM-UGP-PFS-141767-CS- INDV / Recrutement d'un Consultant pour le ciblage Laying the Foundations of des 500 bénéficiaires de la a Safety Net System and 2020-06- 2020-08- 2020-09- 2020-10- 2021-05- IDA / 62230 A posteriori Individuel Open 4,920.00 0.00 Annulé Phase 3 des TMU du Projet Supporting Project 30 25 15 20 18 Filets Sociaux dans la Management commune de Limbé I , département du Fako, région du Sud-Ouest CM-UGP-PFS-172022-CS- CDS / Convention avec l’INS Cash Transfer Program Sélection de pour l’enquête PMT du with Accompanying 2020-09- 2020-08- 2020-09- 2020-08- 2020-11- 2020-09- 2021-05- IDA / 62230 A posteriori consultants par Direct 937,708.53 828,613.11 Signé Cycle 3 et du Cycle G1 des Measures to Boost 15 19 27 26 11 29 10 entente directe transferts Monétaires Household Productivity Ordinaires du Projet Filets Sociaux; CM-UGP-PFS-200965-CS- Laying the Foundations of INDV / Recrutement d'un a Safety Net System and En cours 2020-11- 2020-10- 2021-02- 2021-02- 2021-03- 2023-03- IDA / 62230 A posteriori Individuel Open 63,983.20 0.00 Comptable pour le Projet Supporting Project d'exécution 30 19 06 11 05 05 Filets Sociaux Management CM-UGP-PFS-172276-CS- Laying the Foundations of INDV / Consultant pour la a Safety Net System and 2020-08- 2020-08- 2020-09- 2020-10- 2020-11- conception d'une affiche IDA / 62230 A posteriori Individuel Limited 3,000.00 0.00 Annulé Supporting Project 20 25 15 20 19 de communication et de Management sensibilisation sur le MGP CM-UGP-PFS-141118-CS- Laying the Foundations of INDV / Recrutement de la a Safety Net System and 2021-01- 2021-04- 2021-03- 2021-04- 2021-05- 2023-05- Secrétaire de l'antenne IDA / 62230 A posteriori Individuel Open 17,203.00 0.00 Annulé Supporting Project 20 04 17 07 12 12 régionale du Sud-Ouest du Management Projet Filets Sociaux CM-UGP-PFS-141133-CS- Laying the Foundations of INDV / Recrutement de la a Safety Net System and En cours 2021-01- 2021-04- 2021-03- 2021-04- 2021-05- 2023-05- Secrétaire de l'antenne IDA / D2980 A posteriori Individuel Open 17,203.00 0.00 Supporting Project d'exécution 20 04 17 07 12 12 régionale de l'Adamaoua du Management Projet Filets Sociaux CM-UGP-PFS-141134-CS- Laying the Foundations of INDV / Recrutement du a Safety Net System and En cours 2021-01- 2021-01- 2021-03- 2021-04- 2021-05- 2023-05- Chauffeur de l'antenne IDA / D2980 A posteriori Individuel Open 11,612.00 0.00 Supporting Project d'exécution 20 29 17 07 12 12 régionale de l'Adamaoua du Management Projet Filets Sociaux CM-UGP-PFS-141124-CS- Laying the Foundations of INDV / Recrutement de la a Safety Net System and En cours 2021-01- 2021-04- 2021-03- 2021-04- 2021-05- 2023-05- Secrétaire de l'antenne IDA / 62230 A posteriori Individuel Open 17,203.00 0.00 Supporting Project d'exécution 20 04 17 07 12 12 régionale Sud du Projet Management Filets Sociaux CM-UGP-PFS-141129-CS- Laying the Foundations of INDV / Recrutement du a Safety Net System and En cours 2021-01- 2021-01- 2021-03- 2021-04- 2021-05- 2023-05- Chauffeur de l'antenne IDA / 62230 A posteriori Individuel Open 11,612.00 0.00 Supporting Project d'exécution 20 29 17 07 12 12 régionale Sud du Projet Management Filets Sociaux CM-UGP-PFS-141131-CS- Laying the Foundations of INDV / Recrutement du a Safety Net System and En cours 2021-01- 2021-01- 2021-03- 2021-04- 2021-05- 2023-05- Chauffeur de l'antenne IDA / D2980 A posteriori Individuel Open 11,612.00 0.00 Supporting Project d'exécution 20 29 17 07 12 12 régionale de l'Est du Projet Management Filets Sociaux CM-UGP-PFS-141123-CS- Laying the Foundations of INDV / Recrutement du a Safety Net System and 2021-01- 2021-03- 2021-04- 2021-05- 2023-05- Chauffeur de l'antenne IDA / 62230 A posteriori Individuel Open 12,960.00 0.00 Annulé Supporting Project 20 17 07 12 12 régionale du Sud-Ouest du Management Projet Filets Sociaux CM-UGP-PFS-172280-CS- Laying the Foundations of INDV / Consultant pour la a Safety Net System and 2020-12- 2021-02- 2021-03- 2021-04- 2021-10- production des séries IDA / 62230 A posteriori Individuel Open 30,000.00 0.00 Annulé Supporting Project 21 11 04 08 05 radiophoniques pour la Management prévention des VBG CM-UGP-PFS-203028-CS- INDV / recrutement d’un Cash Transfer Program consultant individuel with Accompanying En cours 2020-11- 2020-11- 2020-12- 2020-12- 2021-01- 2021-02- IDA / 62230 A posteriori Individuel Limited 3,000.00 0.00 chargé de traduire en Measures to Boost d'exécution 30 30 05 26 30 14 images le contrat moral du Household Productivity Projet Filets Sociaux CM-UGP-PFS-141130-CS- Laying the Foundations of INDV / Recrutement de la a Safety Net System and En cours 2021-01- 2021-04- 2021-03- 2021-04- 2021-05- 2023-05- Secrétaire de l'antenne IDA / D2980 A posteriori Individuel Open 17,203.00 0.00 Supporting Project d'exécution 20 04 17 07 12 12 régionale de l'Est du Projet Management Filets Sociaux CM-UGP-PFS-187235-CS- Laying the Foundations of INDV / Recrutement du a Safety Net System and 2021-01- 2021-01- 2021-03- 2021-04- 2021-05- 2023-05- chauffeur de l'antenne IDA / 62230 A posteriori Individuel Open 11,612.00 0.00 Annulé Supporting Project 20 29 17 07 12 12 régionale du Sud ouest du Management Projet Filets Sociaux CM-UGP-PFS-172253-CS- INDV / Recrutement d’un Consultant pour une Laying the Foundations of évaluation sociale et une a Safety Net System and En cours 2020-11- 2020-11- 2020-12- 2020-12- 2021-01- 2021-07- consultation des IDA / 62230 A posteriori Individuel Limited 10,950.00 0.00 Supporting Project d'examen 30 30 05 26 30 29 populations '4B' en vue de Management l'élaboration d'un Plan d'action Peuple Autochtone (PPA) (IDA National) Laying the Foundations of CM-UGP-PFS-203162-CS- Sélection de a Safety Net System and En attente 2020-07- 2020-07- 2020-09- 2022-09- CDS / Spécialiste en IDA / 62230 A posteriori consultants par Direct 90,541.00 0.00 Supporting Project d'exécution 15 25 28 28 Passation des Marchés entente directe Management CM-UGP-PFS-203164-CS- Laying the Foundations of Sélection de CDS / Responsable a Safety Net System and En attente 2020-08- 2020-09- 2020-11- 2022-11- IDA / 62230 A posteriori consultants par Direct 39,787.00 0.00 Régional du Projet Filets Supporting Project d'exécution 26 05 09 09 entente directe Sociaux dans le Nord- Management Ouest Laying the Foundations of Sélection de CM-UGP-PFS-203161-CS- a Safety Net System and En attente 2020-09- 2020-09- 2020-12- 2022-12- IDA / 62230 A posteriori consultants par Direct 64,890.00 0.00 CDS / Auditeur Interne Supporting Project d'exécution 18 28 02 02 entente directe Management CM-UGP-PFS-205157-CS- INDV / Recrutement du Cash Transfer Program consultant pour la with Accompanying 2020-12- 2021-01- 2021-01- 2021-03- 2021-05- IDA / D2980 A posteriori Individuel Limited 14,447.00 0.00 Annulé production de 5 séries Measures to Boost 30 04 25 01 30 radiophoniques en 5 Household Productivity langues (français, arabe, Fufuldé, Arabe et Koto) CM-UGP-PFS-205176-CS- Cash Transfer Program INDV / Recrutement du with Accompanying En attente 2020-12- 2021-01- 2021-01- 2021-03- 2021-03- consultant pour la IDA / D2980 A posteriori Individuel Limited 8,127.00 0.00 Measures to Boost d'exécution 30 04 25 01 31 production des images Household Productivity pour la formation des couples CM-UGP-PFS-205281-CS- INDV / Recrutement de l'opérateur de terrain N°1 Laying the Foundations of de la Commune de Ngaoui a Safety Net System and En cours 2021-03- 2021-02- 2021-05- 2021-05- 2021-07- 2023-07- IDA / D2980 A posteriori Individuel Open 12,960.00 0.00 département du Mbere Supporting Project d'exécution 15 05 10 31 05 05 région de l'Adamaoua pour Management le cycle 4 des Transferts Monétaires ordinaires CM-UGP-PFS-205285-CS- INDV / Recrutement de l'opérateur de Terrain N°2 Laying the Foundations of de la Commune de Ngaoui, a Safety Net System and En cours 2021-03- 2021-02- 2021-05- 2021-05- 2021-07- 2023-07- département du Mbéré, IDA / D2980 A posteriori Individuel Open 12,960.00 0.00 Supporting Project d'exécution 15 05 10 31 05 05 Région de l'Adamaoua dans Management le cadre du cycle 4 des Transferts Monétaires Ordinaires du Projet filets Sociaux CM-UGP-PFS-205286-CS- INDV / Recrutement de l'opérateur de Terrain N°2 Laying the Foundations of de la Commune de a Safety Net System and En cours 2021-03- 2021-02- 2021-05- 2021-05- 2021-07- 2023-07- Njohong, département du IDA / D2980 A posteriori Individuel Open 12,960.00 0.00 Supporting Project d'exécution 15 05 10 31 05 05 Mbéré, Région de Management l'Adamaoua dans le cadre du cycle 4 des Transferts Monétaires Ordinaires du Projet filets Sociaux CM-UGP-PFS-205287-CS- INDV / Recrutement de l'opérateur de Terrain N°1 Laying the Foundations of de la Commune de a Safety Net System and En cours 2021-03- 2021-02- 2021-05- 2021-05- 2021-07- 2023-07- Njohong, département du IDA / D2980 A posteriori Individuel Open 12,960.00 0.00 Supporting Project d'exécution 15 05 10 31 05 05 Mbéré, Région de Management l'Adamaoua dans le cadre du cycle 4 des Transferts Monétaires Ordinaires du Projet filets Sociaux CM-UGP-PFS-205288-CS- INDV / Recrutement de l'Opérateur de Terrain N°1 de la Commune de Laying the Foundations of Mandjou, Département du a Safety Net System and En cours 2021-03- 2021-02- 2021-05- 2021-05- 2021-07- 2023-07- IDA / D2980 A posteriori Individuel Open 12,960.00 0.00 Lom et Djerem, Région de Supporting Project d'exécution 15 05 10 31 05 05 l'Est dans le cadre du cycle Management 4 des Transferts Monétaires Ordinaires du Projet filets Sociaux CM-UGP-PFS-205290-CS- INDV / Recrutement de l'Opérateur de Terrain N°2 de la Commune de Laying the Foundations of Mandjou, Département du a Safety Net System and En cours 2021-03- 2021-05- 2021-05- 2021-07- 2023-07- IDA / D2980 A posteriori Individuel Open 12,960.00 0.00 Lom et Djerem, Région de Supporting Project d'exécution 15 10 31 05 05 l'Est dans le cadre du cycle Management 4 des Transferts Monétaires Ordinaires du Projet filets Sociaux CM-UGP-PFS-205291-CS- INDV / Recrutement de l'Opérateur de Terrain N°1 Laying the Foundations of de la Commune de a Safety Net System and En cours 2021-03- 2021-02- 2021-05- 2021-05- 2021-07- 2023-07- Kentzou, Département de la IDA / D2980 A posteriori Individuel Open 12,960.00 0.00 Supporting Project d'exécution 15 05 10 31 05 05 Kadey, Région de l'Est dans Management le cadre du cycle 4 des Transferts Monétaires Ordinaires du Projet Filets Sociaux CM-UGP-PFS-205292-CS- INDV / Recrutement de l'Opérateur de Terrain N°2 Laying the Foundations of de la Commune de a Safety Net System and En cours 2021-03- 2021-02- 2021-05- 2021-05- 2021-07- 2023-07- Kentzou, Département de la IDA / D2980 A posteriori Individuel Open 12,960.00 0.00 Supporting Project d'exécution 15 05 10 31 05 05 Kadey, Région de l'Est dans Management le cadre du cycle 4 des Transferts Monétaires Ordinaires du Projet Filets Sociaux CM-UGP-PFS-205294-CS- INDV / Recrutement de l'Opérateur de Terrain N°1 de la Commune de Makary Laying the Foundations of Département du Logone et a Safety Net System and En cours 2021-03- 2021-02- 2021-05- 2021-05- 2021-06- 2023-06- IDA / D2980 A posteriori Individuel Open 12,960.00 0.00 Chari, Région de l'Extrême Supporting Project d'exécution 15 05 03 24 28 28 Nord dans le cadre du cycle Management 4 des Transferts Monétaires Ordinaires du Projet Filets Sociaux CM-UGP-PFS-205297-CS- INDV / Recrutement de l'Opérateur de Terrain N°2 de la Commune de Makary Laying the Foundations of Département du Logone et a Safety Net System and En cours 2021-03- 2021-02- 2021-05- 2021-05- 2021-06- 2023-06- IDA / D2980 A posteriori Individuel Open 12,960.00 0.00 Chari, Région de l'Extrême Supporting Project d'exécution 15 05 03 24 28 28 Nord dans le cadre du cycle Management 4 des Transferts Monétaires Ordinaires du Projet Filets Sociaux CM-UGP-PFS-205298-CS- INDV / Recrutement de l'Opérateur de Terrain N°1 de la Commune de Laying the Foundations of Tokomberé Département a Safety Net System and En cours 2021-03- 2021-02- 2021-05- 2021-05- 2021-06- 2023-06- IDA / 62230 A posteriori Individuel Open 12,960.00 0.00 du Mayo Sava, Région de Supporting Project d'exécution 15 05 03 24 28 28 l'Extrême Nord dans le Management cadre du cycle 4 des Transferts Monétaires Ordinaires du Projet Filets Sociaux Page 11 CM-UGP-PFS-205301-CS- INDV / Recrutement de l'Opérateur de Terrain N°2 de la Commune de Laying the Foundations of Tokomberé Département a Safety Net System and En cours 2021-03- 2021-02- 2021-05- 2021-05- 2021-06- 2023-06- IDA / 62230 A posteriori Individuel Open 12,960.00 0.00 du Mayo Sava, Région de Supporting Project d'exécution 15 05 03 24 28 28 l'Extrême Nord dans le Management cadre du cycle 4 des Transferts Monétaires Ordinaires du Projet Filets Sociaux CM-UGP-PFS-141107-CS- INDV / Recrutement d'un Laying the Foundations of Responsable Régional dans a Safety Net System and 2020-06- 2020-08- 2020-09- 2020-10- 2022-10- IDA / 62230 A posteriori Individuel Open 38,400.00 0.00 Annulé la Région du SUD-OUEST Supporting Project 30 25 15 20 20 pour la cycle 3 des Management Transferts Monétaires ordinaires CM-UGP-PFS-212970-CS- INDV / Recrutement de l'Opérateur de Terrain de la Commune de Mbé Laying the Foundations of Département de la VINA, a Safety Net System and En cours 2021-03- 2021-02- 2021-05- 2021-06- 2021-07- 2023-07- IDA / 62230 A posteriori Individuel Open 12,960.00 0.00 Région de l'Adamaoua dans Supporting Project d'exécution 31 05 19 09 14 14 le cadre du cycle 4 des Management Transferts Monétaires Ordinaires du Projet Filets Sociaux CM-UGP-PFS-212971-CS- INDV / Recrutement de l'Opérateur de Terrain de la Commune de Bankim Laying the Foundations of Département du Mayo- a Safety Net System and En cours 2021-03- 2021-02- 2021-05- 2021-06- 2021-07- 2023-07- IDA / 62230 A posteriori Individuel Open 12,960.00 0.00 Banyo, Région de Supporting Project d'exécution 31 05 19 09 14 14 l'Adamaoua dans le cadre Management du cycle 4 des Transferts Monétaires Ordinaires du Projet Filets Sociaux CM-UGP-PFS-212972-CS- INDV / Recrutement de l'Opérateur de Terrain de la Commune de Mayo Darlé Laying the Foundations of Département du Mayo- a Safety Net System and En cours 2021-03- 2021-02- 2021-05- 2021-06- 2021-07- 2023-07- IDA / 62230 A posteriori Individuel Open 12,960.00 0.00 Banyo, Région de Supporting Project d'exécution 31 05 19 09 14 14 l'Adamaoua dans le cadre Management du cycle 4 des Transferts Monétaires Ordinaires du Projet Filets Sociaux CM-UGP-PFS-212973-CS- INDV / Recrutement de l'Opérateur de Terrain de la Commune de Mindif Laying the Foundations of Département du Mayo- a Safety Net System and En cours 2021-03- 2021-02- 2021-05- 2021-06- 2021-07- 2023-07- IDA / 62230 A posteriori Individuel Open 12,960.00 0.00 Kani, Région de l'Extrême Supporting Project d'exécution 31 05 19 09 14 14 Nord dans le cadre du cycle Management 4 des Transferts Monétaires Ordinaires du Projet Filets Sociaux CM-UGP-PFS-212974-CS- INDV / Recrutement de l'Opérateur de Terrain de Laying the Foundations of la Commune de Djoum a Safety Net System and En cours 2021-03- 2021-02- 2021-05- 2021-06- 2021-07- 2023-07- Département du Dja et IDA / 62230 A posteriori Individuel Open 12,960.00 0.00 Supporting Project d'exécution 31 05 19 09 14 14 Lobo Région du Sud dans le Management cadre du cycle 4 des Transferts Monétaires Ordinaires du Projet Filets Sociaux CM-UGP-PFS-212976-CS- INDV / Recrutement de l'Opérateur de Terrain de Laying the Foundations of la Commune de a Safety Net System and En cours 2021-03- 2021-02- 2021-05- 2021-06- 2021-07- 2023-07- Meyomessala Département IDA / 62230 A posteriori Individuel Open 12,960.00 0.00 Supporting Project d'exécution 31 05 19 09 14 14 du Dja et Lobo, Région du Management Sud dans le cadre du cycle 4 des Transferts Monétaires Ordinaires du Projet Filets Sociaux CM-UGP-PFS-212977-CS- INDV / Recrutement de l'Opérateur de Terrain de Laying the Foundations of la Commune de Douala a Safety Net System and En cours 2021-03- 2021-02- 2021-05- 2021-06- 2021-07- 2023-07- IDA / 62230 A posteriori Individuel Open 12,960.00 0.00 2ème Ville de Douala dans Supporting Project d'exécution 31 05 19 09 14 14 le cadre du cycle 4 des Management Transferts Monétaires Ordinaires du Projet Filets Sociaux CM-UGP-PFS-212978-CS- INDV / Recrutement de l'Opérateur de Terrain de Laying the Foundations of la Commune de Yaoundé 7 a Safety Net System and En cours 2021-03- 2021-02- 2021-05- 2021-06- 2021-07- 2023-07- IDA / 62230 A posteriori Individuel Open 12,960.00 0.00 Ville de Yaoundé dans le Supporting Project d'exécution 31 05 19 09 14 14 cadre du cycle 4 des Management Transferts Monétaires Ordinaires du Projet Filets Sociaux CM-UGP-PFS-212979-CS- INDV / Recrutement de l'Opérateur de Terrain de la Commune de Mora, Laying the Foundations of Département du Mayo Sava, a Safety Net System and En cours 2021-03- 2021-02- 2021-05- 2021-06- 2021-07- 2023-07- IDA / D2980 A posteriori Individuel Open 12,960.00 0.00 Région de l'Extrême Nord Supporting Project d'exécution 31 05 19 09 14 14 dans le cadre du cycle 5 Management des Transferts Monétaires Ordinaires du Projet Filets Sociaux CM-UGP-PFS-212980-CS- INDV / Recrutement de l'Opérateur de Terrain de Laying the Foundations of la Commune de Ouli, a Safety Net System and En cours 2021-03- 2021-02- 2021-05- 2021-06- 2021-07- 2023-07- Département de la Kadey, IDA / D2980 A posteriori Individuel Open 12,960.00 0.00 Supporting Project d'exécution 31 05 19 09 14 14 Région de l'Est dans le Management cadre du cycle 5 des Transferts Monétaires Ordinaires du Projet Filets Sociaux CM-UGP-PFS-212981-CS- INDV / Recrutement de l'Opérateur de Terrain de Laying the Foundations of la Commune de Batouri, a Safety Net System and En cours 2021-03- 2021-02- 2021-05- 2021-06- 2021-07- 2023-07- Département de la Kadey, IDA / D2980 A posteriori Individuel Open 12,960.00 0.00 Supporting Project d'exécution 31 05 19 09 14 14 Région de l'Est dans le Management cadre du cycle 5 des Transferts Monétaires Ordinaires du Projet Filets Sociaux CM-UGP-PFS-212982-CS- INDV / Recrutement de l'Opérateur de Terrain de la Commune de Gari - Laying the Foundations of Gombo, Département de la a Safety Net System and En cours 2021-03- 2021-02- 2021-05- 2021-06- 2021-07- 2023-07- IDA / D2980 A posteriori Individuel Open 12,960.00 0.00 Boumba et Ngoko, Région Supporting Project d'exécution 31 05 19 09 14 14 de l'Est dans le cadre du Management cycle 5 des Transferts Monétaires Ordinaires du Projet Filets Sociaux CM-UGP-PFS-212983-CS- INDV / Recrutement de l'Opérateur de Terrain de la Commune de Laying the Foundations of Salapoumbe, Département a Safety Net System and En cours 2021-03- 2021-02- 2021-05- 2021-06- 2021-07- 2023-07- IDA / D2980 A posteriori Individuel Open 12,960.00 0.00 de la Boumba et Ngoko, Supporting Project d'exécution 31 05 19 09 14 14 Région de l'Est dans le Management cadre du cycle 5 des Transferts Monétaires Ordinaires du Projet Filets Sociaux CM-UGP-PFS-213101-CS- INDV / Recrutement de l'Opérateur de Terrain de la Laying the Foundations of Commune de Douala IV, a Safety Net System and En cours 2021-03- 2021-02- 2021-05- 2021-06- 2021-07- 2022-07- IDA / 62230 A posteriori Individuel Open 6,480.00 0.00 Ville de Douala dans le Supporting Project d'exécution 31 05 19 09 14 14 cadre de la phase 4 des Management Transferts Monétaires d'urgence du Projet Filets Sociaux CM-UGP-PFS-213102-CS- INDV / Recrutement de l'Opérateur de Terrain de la Laying the Foundations of Commune de Yaoundé III, a Safety Net System and En cours 2021-03- 2021-02- 2021-05- 2021-06- 2021-07- 2022-07- IDA / 62230 A posteriori Individuel Open 6,480.00 0.00 Ville de Yaoundé dans le Supporting Project d'exécution 31 05 19 09 14 14 cadre de la phase 4 des Management Transferts Monétaires d'urgence du Projet Filets Sociaux CM-UGP-PFS-213103-CS- INDV / Recrutement de l'Opérateur de Terrain de la Commune de Babadjou, Laying the Foundations of Département du a Safety Net System and En cours 2021-03- 2021-02- 2021-05- 2021-06- 2021-07- 2022-07- IDA / 62230 A posteriori Individuel Open 6,480.00 0.00 Bamboutos, Région de Supporting Project d'exécution 31 05 19 09 14 14 l'Ouest dans le cadre de la Management phase 4 des Transferts Monétaires d'urgence du Projet Filets Sociaux CM-UGP-PFS-213104-CS- INDV / Recrutement de l'Opérateur de Terrain de la Commune de Batcham, Laying the Foundations of Département du a Safety Net System and En cours 2021-03- 2021-02- 2021-05- 2021-06- 2021-07- 2022-07- IDA / 62230 A posteriori Individuel Open 6,480.00 0.00 Bamboutos, Région de Supporting Project d'exécution 31 05 19 09 14 14 l'Ouest dans le cadre de la Management phase 4 des Transferts Monétaires d'urgence du Projet Filets Sociaux CM-UGP-PFS-213105-CS- INDV / Recrutement de l'Opérateur de Terrain de la Commune de Galim, Laying the Foundations of Département du a Safety Net System and En cours 2021-03- 2021-02- 2021-05- 2021-06- 2021-07- 2022-07- IDA / 62230 A posteriori Individuel Open 6,480.00 0.00 Bamboutos, Région de Supporting Project d'exécution 31 05 19 09 14 14 l'Ouest dans le cadre de la Management phase 4 des Transferts Monétaires d'urgence du Projet Filets Sociaux CM-UGP-PFS-213106-CS- INDV / Recrutement de l'Opérateur de Terrain de la Laying the Foundations of Commune de foumban, a Safety Net System and En cours 2021-03- 2021-02- 2021-05- 2021-06- 2021-07- 2022-07- Département du Noun, IDA / 62230 A posteriori Individuel Open 6,480.00 0.00 Supporting Project d'exécution 31 05 19 09 14 14 Région de l'Ouest dans le Management cadre de la phase 4 des Transferts Monétaires d'urgence du Projet Filets Sociaux CM-UGP-PFS-213107-CS- INDV / Recrutement de l'Opérateur de Terrain de la Laying the Foundations of Commune de Touboro , a Safety Net System and En cours 2021-03- 2021-02- 2021-05- 2021-06- 2021-07- 2022-07- Département du Mayo Rey, IDA / D2980 A posteriori Individuel Open 6,480.00 0.00 Supporting Project d'exécution 31 05 19 09 14 14 Région du Nord dans le Management cadre de la phase 4 des Transferts Monétaires d'urgence du Projet Filets Sociaux CM-UGP-PFS-213108-CS- INDV / Recrutement de l'Opérateur de Terrain de la Laying the Foundations of Commune de kette, a Safety Net System and En cours 2021-03- 2021-02- 2021-05- 2021-06- 2021-07- 2022-07- Département de la Kadey, IDA / D2980 A posteriori Individuel Open 6,480.00 0.00 Supporting Project d'exécution 31 05 19 09 14 14 Région de l'Est dans le Management cadre de la phase 4 des Transferts Monétaires d'urgence du Projet Filets Sociaux CM-UGP-PFS-213110-CS- INDV / Recrutement de l'Opérateur de Terrain de la Commune de NGOURA, Laying the Foundations of Département du Lom et a Safety Net System and En cours 2021-03- 2021-02- 2021-05- 2021-06- 2021-07- 2022-07- IDA / D2980 A posteriori Individuel Open 6,480.00 0.00 Djerem, Région de l'Est Supporting Project d'exécution 31 05 19 09 14 14 dans le cadre de la phase 4 Management des Transferts Monétaires d'urgence du Projet Filets Sociaux CM-UGP-PFS-213111-CS- INDV / Recrutement de l'Opérateur de Terrain de la Commune de Garoua , Laying the Foundations of Département du Lom et a Safety Net System and En cours 2021-03- 2021-05- 2021-06- 2021-07- 2022-07- IDA / D2980 A posteriori Individuel Open 6,480.00 0.00 Djerem, Région de l'Est Supporting Project d'exécution 31 19 09 14 14 dans le cadre de la phase 4 Management des Transferts Monétaires d'urgence du Projet Filets Sociaux Page 12 CM-UGP-PFS-213113-CS- INDV / Consultant pour le ciblage des villages et ménages potentiellement Laying the Foundations of bénéficiaires du cycle 4 des a Safety Net System and En cours 2021-03- 2021-02- 2021-05- 2021-06- 2021-07- 2022-02- Transferts Monétaires IDA / D2980 A posteriori Individuel Open 10,400.00 0.00 Supporting Project d'exécution 31 05 19 09 14 09 Ordinaires du Projet Filets Management Sociaux dans la Commune de Ngaoui département du Mbere région de l'Adamaoua (2000 ménages bénéficiaires) CM-UGP-PFS-213114-CS- INDV / Consultant pour le ciblage des villages et ménages potentiellement Laying the Foundations of bénéficiaires du cycle 4 des a Safety Net System and En cours 2021-03- 2021-02- 2021-05- 2021-06- 2021-07- 2022-02- Transferts Monétaires IDA / D2980 A posteriori Individuel Open 10,400.00 0.00 Supporting Project d'exécution 31 05 19 09 14 09 Ordinaires du Projet Filets Management Sociaux dans la Commune de Njohong département du Mbere région de l'Adamaoua (2000 ménages bénéficiaires) CM-UGP-PFS-213115-CS- INDV / Consultant pour le ciblage des villages et ménages potentiellement Laying the Foundations of bénéficiaires du cycle 4 des a Safety Net System and En cours 2021-03- 2021-02- 2021-05- 2021-06- 2021-07- 2022-02- Transferts Monétaires IDA / 62230 A posteriori Individuel Open 6,300.00 0.00 Supporting Project d'exécution 31 05 19 09 14 09 Ordinaires du Projet Filets Management Sociaux dans la Commune de Mbe département de la Vina, région de l'Adamaoua (1000 ménages bénéficiaires) CM-UGP-PFS-213116-CS- INDV / Consultant pour le ciblage des villages et ménages potentiellement Laying the Foundations of bénéficiaires du cycle 4 des a Safety Net System and En cours 2021-03- 2021-02- 2021-05- 2021-06- 2021-07- 2022-02- Transferts Monétaires IDA / 62230 A posteriori Individuel Open 6,320.00 0.00 Supporting Project d'exécution 31 05 19 09 14 09 Ordinaires du Projet dans Management la Commune de Bankim, département du Mayo Banyo région de l'Adamaoua (1000 ménages bénéficiaires) CM-UGP-PFS-213117-CS- INDV / Consultant pour le ciblage des villages et ménages potentiellement Laying the Foundations of bénéficiaires du cycle 4 des a Safety Net System and En cours 2021-03- 2021-02- 2021-05- 2021-06- 2021-07- 2022-02- Transferts Monétaires IDA / 62230 A posteriori Individuel Open 6,320.00 0.00 Supporting Project d'exécution 31 05 19 09 14 09 Ordinaires du Projet dans Management la Commune de Mayo Darle, département du Mayo Banyo région de l'Adamaoua (1000 ménages bénéficiaires) CM-UGP-PFS-213118-CS- INDV / Consultant pour le ciblage des villages et ménages potentiellement Laying the Foundations of bénéficiaires du cycle 4 des a Safety Net System and En cours 2021-03- 2021-02- 2021-05- 2021-06- 2021-07- 2022-02- Transferts Monétaires IDA / D2980 A posteriori Individuel Open 10,400.00 0.00 Supporting Project d'exécution 31 05 19 09 14 09 Ordinaires du Projet dans Management la Commune de Manjou, département du Lom et Djerem région de l'Est (2000 ménages bénéficiaires) CM-UGP-PFS-213119-CS- INDV / Consultant pour le ciblage des villages et ménages potentiellement Laying the Foundations of bénéficiaires du cycle 4 des a Safety Net System and En cours 2021-03- 2021-02- 2021-05- 2021-06- 2021-07- 2022-02- Transferts Monétaires IDA / D2980 A posteriori Individuel Open 10,400.00 0.00 Supporting Project d'exécution 31 05 19 09 14 09 Ordinaires du Projet dans Management la Commune de Kenzou, département de la Kadey région de l'Est (2000 ménages bénéficiaires) CM-UGP-PFS-213120-CS- INDV / Consultant pour le ciblage des villages et ménages potentiellement Laying the Foundations of bénéficiaires du cycle 4 des a Safety Net System and En cours 2021-03- 2021-02- 2021-05- 2021-06- 2021-07- 2022-02- Transferts Monétaires IDA / D2980 A posteriori Individuel Open 7,850.00 0.00 Supporting Project d'exécution 31 05 19 09 14 09 Ordinaires du Projet dans Management la Commune de Makary, département du Logone et Chari région de l'Extrême Nord (1500 ménages bénéficiaires) CM-UGP-PFS-213121-CS- INDV / Consultant pour le ciblage des villages et ménages potentiellement Laying the Foundations of bénéficiaires du cycle 4 des a Safety Net System and En cours 2021-03- 2021-02- 2021-05- 2021-06- 2021-07- 2022-02- Transferts Monétaires IDA / 62230 A posteriori Individuel Open 10,400.00 0.00 Supporting Project d'exécution 31 05 19 09 14 09 Ordinaires du Projet dans Management la Commune de Tokombere, département du Mayo Sava région de l'Extrême Nord (2000 ménages bénéficiaires) CM-UGP-PFS-213122-CS- INDV / Consultant pour le ciblage des villages et ménages potentiellement Laying the Foundations of bénéficiaires du cycle 4 des a Safety Net System and En cours 2021-03- 2021-02- 2021-05- 2021-06- 2021-07- 2022-02- Transferts Monétaires IDA / 62230 A posteriori Individuel Open 6,320.00 0.00 Supporting Project d'exécution 31 05 19 09 14 09 Ordinaires du Projet dans Management la Commune de Mindif, département du Mayo Kani région de l'Extrême Nord (1000 ménages bénéficiaires) CM-UGP-PFS-213123-CS- INDV / Consultant pour le ciblage des villages et ménages potentiellement Laying the Foundations of bénéficiaires du cycle 4 des a Safety Net System and En cours 2021-03- 2021-02- 2021-05- 2021-06- 2021-07- 2022-02- Transferts Monétaires IDA / 62230 A posteriori Individuel Open 6,320.00 0.00 Supporting Project d'exécution 31 05 19 09 14 09 Ordinaires du Projet dans Management la Commune de Djoum, département du Dja et Lobo région du Sud (1000 ménages bénéficiaires) CM-UGP-PFS-213124-CS- INDV / Consultant pour le ciblage des villages et ménages potentiellement Laying the Foundations of bénéficiaires du cycle 4 des a Safety Net System and En cours 2021-03- 2021-02- 2021-05- 2021-06- 2021-07- 2022-02- Transferts Monétaires IDA / 62230 A posteriori Individuel Open 6,320.00 0.00 Supporting Project d'exécution 31 05 19 09 14 09 Ordinaires du Projet dans Management la Commune de Meyo Messala, département du Dja et Lobo région du Sud (1000 ménages bénéficiaires) CM-UGP-PFS-213125-CS- INDV / Consultant pour le ciblage des villages et ménages potentiellement Laying the Foundations of bénéficiaires du cycle 4 des a Safety Net System and En cours 2021-03- 2021-02- 2021-05- 2021-06- 2021-07- 2022-02- IDA / 62230 A posteriori Individuel Open 6,320.00 0.00 Transferts Monétaires Supporting Project d'exécution 31 05 19 09 14 09 Ordinaires du Projet dans Management la Commune de Douala 2ème, Ville de Douala (1000 ménages bénéficiaires) CM-UGP-PFS-213126-CS- INDV / Consultant pour le ciblage des villages et ménages potentiellement Laying the Foundations of bénéficiaires du cycle 4 des a Safety Net System and En cours 2021-03- 2021-02- 2021-05- 2021-06- 2021-07- 2022-02- IDA / 62230 A posteriori Individuel Open 6,320.00 0.00 Transferts Monétaires Supporting Project d'exécution 31 05 19 09 14 09 Ordinaires du Projet dans Management la Commune de Yaoundé 7, Ville de Yaoundé (1000 ménages bénéficiaires) CM-UGP-PFS-213127-CS- INDV / Consultant pour le ciblage des villages et ménages potentiellement Laying the Foundations of bénéficiaires du cycle 5 des a Safety Net System and En cours 2021-03- 2021-02- 2021-05- 2021-06- 2021-07- 2022-02- Transferts Monétaires IDA / D2980 A posteriori Individuel Open 6,320.00 0.00 Supporting Project d'exécution 31 05 19 09 14 09 Ordinaires du Projet dans Management la Commune de Mora , Département du Mayo Sava Région de l'Extrême Nord (1000 ménages bénéficiaires) CM-UGP-PFS-213129-CS- INDV / Consultant pour le ciblage des villages et ménages potentiellement Laying the Foundations of bénéficiaires du cycle 5 des a Safety Net System and En cours 2021-03- 2021-02- 2021-05- 2021-06- 2021-07- 2022-02- Transferts Monétaires IDA / D2980 A posteriori Individuel Open 6,320.00 0.00 Supporting Project d'exécution 31 05 19 09 14 09 Ordinaires du Projet dans Management la Commune de Ouli, Département de la Kadey de l'Est (1000 ménages bénéficiaires) CM-UGP-PFS-213135-CS- INDV / Consultant pour le ciblage des villages et ménages potentiellement Laying the Foundations of bénéficiaires du cycle 5 des a Safety Net System and En cours 2021-03- 2021-02- 2021-05- 2021-06- 2021-07- 2022-02- Transferts Monétaires IDA / D2980 A posteriori Individuel Open 6,320.00 0.00 Supporting Project d'exécution 31 05 19 09 14 09 Ordinaires du Projet dans Management la Commune de Batouri, Département de la Kadey de l'Est (1000 ménages bénéficiaires) CM-UGP-PFS-213136-CS- INDV / Consultant pour le ciblage des villages et ménages potentiellement Laying the Foundations of bénéficiaires du cycle 5 des a Safety Net System and En cours 2021-03- 2021-02- 2021-05- 2021-06- 2021-07- 2022-02- Transferts Monétaires IDA / D2980 A posteriori Individuel Open 6,320.00 0.00 Supporting Project d'exécution 31 05 19 09 14 09 Ordinaires du Projet dans Management la Commune de Gari Gombo, Département de la Boumba et Ngoko, Région de l'Est (1000 ménages bénéficiaires) CM-UGP-PFS-213137-CS- INDV / Consultant pour le ciblage des villages et ménages potentiellement Laying the Foundations of bénéficiaires du cycle 5 des a Safety Net System and En cours 2021-03- 2021-02- 2021-05- 2021-06- 2021-07- 2022-02- Transferts Monétaires IDA / D2980 A posteriori Individuel Open 6,320.00 0.00 Supporting Project d'exécution 31 05 19 09 14 09 Ordinaires du Projet dans Management la Commune de Salapoumbe, Département de la Boumba et Ngoko, Région de l'Est (1000 ménages bénéficiaires) CM-UGP-PFS-213138-CS- INDV / Consultant pour le ciblage des villages et ménages potentiellement Laying the Foundations of bénéficiaires de la phase 4 a Safety Net System and En cours 2021-03- 2021-02- 2021-05- 2021-06- 2021-07- 2022-02- des Transferts Monétaires IDA / D2980 A posteriori Individuel Open 7,560.00 0.00 Supporting Project d'exécution 31 05 19 09 14 09 d'urgence du PFS dans la Management Commune de Garoua boulaï, Département du Lom et Djerem, Région de l'Est (1000 ménages bénéficiaires) CM-UGP-PFS-213139-CS- INDV / Consultant pour le ciblage des villages et ménages potentiellement Laying the Foundations of bénéficiaires de la phase 4 a Safety Net System and En cours 2021-03- 2021-02- 2021-05- 2021-06- 2021-07- 2022-02- des Transferts Monétaires IDA / D2980 A posteriori Individuel Open 7,560.00 0.00 Supporting Project d'exécution 31 05 19 09 14 09 d'urgence du PFS dans la Management Commune de Ngoura, Département du Lom et Djerem, Région de l'Est (1000 ménages bénéficiaires) CM-UGP-PFS-213140-CS- INDV / Consultant pour le ciblage des villages et ménages potentiellement Laying the Foundations of bénéficiaires de la phase 4 a Safety Net System and En cours 2021-03- 2021-02- 2021-05- 2021-06- 2021-07- 2022-02- des Transferts Monétaires IDA / D2980 A posteriori Individuel Open 7,560.00 0.00 Supporting Project d'exécution 31 05 19 09 14 09 d'urgence du Projet dans la Management Commune de Kette, Département de la Kadey, Région de l'Est (1000 ménages bénéficiaires) Page 13 CM-UGP-PFS-213142-CS- INDV / Consultant pour le ciblage des villages et ménages potentiellement Laying the Foundations of bénéficiaires de la phase 4 a Safety Net System and En cours 2021-03- 2021-02- 2021-05- 2021-06- 2021-07- 2022-02- des Transferts Monétaires IDA / D2980 A posteriori Individuel Open 7,650.00 0.00 Supporting Project d'exécution 31 05 19 09 14 09 d'urgence du Projet dans la Management Commune de Touboro, Département du Mayo Rey, Région du Nord (1000 ménages bénéficiaires) CM-UGP-PFS-213143-CS- INDV / Consultant pour le ciblage des villages et ménages potentiellement Laying the Foundations of bénéficiaires de la phase 4 a Safety Net System and En cours 2021-03- 2021-02- 2021-05- 2021-06- 2021-07- 2022-02- des Transferts Monétaires IDA / 62230 A posteriori Individuel Open 7,560.00 0.00 Supporting Project d'exécution 31 05 19 09 14 09 d'urgence du Projet dans la Management Commune de Foumban, Département du Noun, Région de l'Ouest (1000 ménages bénéficiaires) CM-UGP-PFS-213144-CS- INDV / Consultant pour le ciblage des villages et ménages potentiellement Laying the Foundations of bénéficiaires de la phase 4 a Safety Net System and En cours 2021-03- 2021-02- 2021-05- 2021-06- 2021-07- 2022-02- des Transferts Monétaires IDA / 62230 A posteriori Individuel Open 4,920.00 0.00 Supporting Project d'exécution 31 05 19 09 14 09 d'urgence du Projet dans la Management Commune de Galim, Département du Bamboutos, Région de l'Ouest (500 ménages bénéficiaires) CM-UGP-PFS-213145-CS- INDV / Consultant pour le ciblage des villages et ménages potentiellement Laying the Foundations of bénéficiaires de la phase 4 a Safety Net System and En cours 2021-03- 2021-02- 2021-05- 2021-06- 2021-07- 2022-02- des Transferts Monétaires IDA / 62230 A posteriori Individuel Open 4,920.00 0.00 Supporting Project d'exécution 31 05 19 09 14 09 d'urgence du Projet dans la Management Commune de Batcham, Département du Bamboutos, Région de l'Ouest (500 ménages bénéficiaires) CM-UGP-PFS-213146-CS- INDV / Consultant pour le ciblage des villages et ménages potentiellement Laying the Foundations of bénéficiaires de la phase 4 a Safety Net System and En cours 2021-03- 2021-02- 2021-05- 2021-06- 2021-07- 2022-02- des Transferts Monétaires IDA / 62230 A posteriori Individuel Open 4,920.00 0.00 Supporting Project d'exécution 31 05 19 09 14 09 d'urgence du Projet dans la Management Commune de Babadjou, Département du Bamboutos, Région de l'Ouest (500 ménages bénéficiaires) CM-UGP-PFS-213147-CS- INDV / Consultant pour le ciblage des villages et ménages potentiellement Laying the Foundations of bénéficiaires de la phase 4 a Safety Net System and En cours 2021-03- 2021-02- 2021-05- 2021-06- 2021-07- 2022-02- IDA / 62230 A posteriori Individuel Open 7,560.00 0.00 des Transferts Monétaires Supporting Project d'exécution 31 05 19 09 14 09 d'urgence du Projet Filets Management Sociaux dans la Commune de Douala IV, Ville de Douala (1000 ménages bénéficiaires) CM-UGP-PFS-213148-CS- INDV / Consultant pour le ciblage des villages et ménages potentiellement Laying the Foundations of bénéficiaires de la phase 4 a Safety Net System and En cours 2021-03- 2021-02- 2021-05- 2021-06- 2021-07- 2022-02- IDA / 62230 A posteriori Individuel Open 7,560.00 0.00 des Transferts Monétaires Supporting Project d'exécution 31 05 19 09 14 09 d'urgence du Projet Filets Management Sociaux dans la Commune de Yaoundé III, Ville de Yaoundé (1000 ménages bénéficiaires) CM-UGP-PFS-203027-CS- Laying the Foundations of INDV / Consultant pour la a Safety Net System and En cours 2021-03- 2021-04- 2021-04- 2021-05- 2021-11- production des séries IDA / 62230 A posteriori Individuel Limited 30,000.00 0.00 Supporting Project d'exécution 31 05 26 31 27 radiophoniques pour la Management prévention des VBG CM-UGP-PFS-217843-CS- Laying the Foundations of INDV / Recrutement du a Safety Net System and En attente 2021-02- 2021-02- 2021-03- 2021-04- 2023-04- chauffeur N° 3 de l'Unité de IDA / 62230 A posteriori Individuel Limited 16,800.00 0.00 Supporting Project d'exécution 22 27 20 24 24 Gestion du Projet Filets Management Sociaux CM-UGP-PFS-218220-CS- INDV / Recrutement du Laying the Foundations of point focal du département a Safety Net System and En cours 2021-03- 2021-02- 2021-04- 2021-05- 2021-06- 2023-06- du Mbéré, région de IDA / D2980 A posteriori Individuel Open 19,200.00 0.00 Supporting Project d'exécution 02 17 27 18 22 22 l'Adamaoua dans le cadre Management des Cycles 4 et 5 des Transferts Monétaire Ordinaire CM-UGP-PFS-218223-CS- INDV / Recrutement du Laying the Foundations of point focal du département a Safety Net System and En cours 2021-03- 2021-02- 2021-04- 2021-05- 2021-06- 2023-06- du Mayo Banyo, région de IDA / 62230 A posteriori Individuel Open 19,200.00 0.00 Supporting Project d'exécution 02 17 27 18 22 22 l'Adamaoua dans le cadre Management des Cycles 4 et 5 des Transferts Monétaire Ordinaire CM-UGP-PFS-218225-CS- INDV / Recrutement du Laying the Foundations of point focal du département a Safety Net System and En cours 2021-03- 2021-02- 2021-04- 2021-05- 2021-06- 2023-06- de la Boumba et Ngoko, IDA / D2980 A posteriori Individuel Open 19,200.00 0.00 Supporting Project d'exécution 02 17 27 18 22 22 région de l'Est dans le Management cadre des Cycles 4 et 5 des Transferts Monétaire Ordinaire CM-UGP-PFS-218226-CS- INDV / Recrutement du Laying the Foundations of point focal du département a Safety Net System and En cours 2021-03- 2021-02- 2021-04- 2021-05- 2021-06- 2023-06- IDA / D2980 A posteriori Individuel Open 19,200.00 0.00 de la Kadey, région de l'Est Supporting Project d'exécution 02 17 27 18 22 22 dans le cadre des Cycles 4 Management et 5 des Transferts Monétaire Ordinaire CM-UGP-PFS-220028-CS- CDS / RECRUTEMENT DU CONSULTANT CHARGE DE L'ENQUETE DE BASE POUR Cash Transfer Program L'EVALUATION D'IMPACT Sélection de with Accompanying En attente 2021-03- 2021-03- 2021-05- 2022-01- DES MESURES IDA / D2980 A posteriori consultants par Direct 499,337.00 0.00 Measures to Boost d'exécution 15 25 29 24 D'ACCOMPAGNEMENT DU entente directe Household Productivity PROJET FILETS SOCIAUX AUPRES DES POPULATIONS HOTES ET DES REFUGIES AU CAMEROUN CM-UGP-PFS-227924-CS- Laying the Foundations of INDV / Recrutement d'un a Safety Net System and En cours 2021-04- 2021-04- 2021-06- 2021-07- 2021-08- 2022-08- IDA / 62230 A posteriori Individuel Open 9,600.00 0.00 assistant comptable au Supporting Project d'exécution 30 23 18 09 13 13 Projet Filets Sociaux Management CM-UGP-PFS-232625-CS- Laying the Foundations of INDV / recrutement d'un a Safety Net System and En attente 2021-06- 2021-06- 2021-07- 2021-08- 2022-08- technicien de surface pour IDA / D2980 A posteriori Individuel Limited 1,920.00 0.00 Supporting Project d'exécution 25 30 21 25 25 l'antenne régionale du Management projet de l'extrême Nord CM-UGP-PFS-232631-CS- Laying the Foundations of INDV / recrutement d'un a Safety Net System and En attente 2021-06- 2021-06- 2021-07- 2021-08- 2022-08- Technicien de surface pour IDA / D2980 A posteriori Individuel Limited 1,920.00 0.00 Supporting Project d'exécution 25 30 21 25 25 l'antenne Régionale du Management projet du Nord CM-UGP-PFS-232634-CS- Laying the Foundations of INDV / recrutement d'un a Safety Net System and En attente 2021-06- 2021-06- 2021-07- 2021-08- 2022-08- technicien de surface pour IDA / D2980 A posteriori Individuel Limited 1,920.00 0.00 Supporting Project d'exécution 25 30 21 25 25 l'antenne régionale du Management projet de l'Est CM-UGP-PFS-232635-CS- Laying the Foundations of INDV / recrutement d'un a Safety Net System and En attente 2021-06- 2021-06- 2021-07- 2021-08- 2022-08- technicien de surface pour IDA / D2980 A posteriori Individuel Limited 1,920.00 0.00 Supporting Project d'exécution 25 30 21 25 25 l'antenne régionale du Management projet de l'Adamaoua CM-UGP-PFS-232636-CS- Laying the Foundations of INDV / recrutement d'un a Safety Net System and En attente 2021-06- 2021-06- 2021-07- 2021-08- 2022-08- technicien de surface pour IDA / 62230 A posteriori Individuel Limited 1,920.00 0.00 Supporting Project d'exécution 25 30 21 25 25 l'antenne régionale du Management projet du sud CM-UGP-PFS-232637-CS- Laying the Foundations of INDV / recrutement d'un a Safety Net System and En attente 2021-06- 2021-06- 2021-07- 2021-08- 2022-08- deuxième technicien de IDA / 62230 A posteriori Individuel Limited 7,000.00 0.00 Supporting Project d'exécution 25 30 21 25 25 surface pour l'Unité de Management Gestion du Projet CM-UGP-PFS-234703-CS- CDS / Convention de partenariat avec l'Institut National de la Statistique Cash Transfer Program (INS) pour la réalisation de Sélection de with Accompanying En cours 2021-05- 2021-06- 2021-06- 2021-06- 2021-07- 2022-03- l’enquête Proxy Means Test IDA / 62230 A priori consultants par Direct 1,200,000.00 0.00 Measures to Boost d'exécution 31 06 15 07 30 27 (PMT) dans les communes entente directe Household Productivity bénéficiaires du programme de transferts monétaires ordinaires du cycle 4 et du cycle 5 du PFS CM-UGP-PFS-239536-CS- Laying the Foundations of INDV / Recrutement d'un a Safety Net System and En cours 2021-06- 2021-10- 2021-08- 2021-09- 2021-10- 2023-01- IDA / 62230 A posteriori Individuel Open 18,000.00 0.00 assistant du Responsable Supporting Project d'examen 30 12 18 08 13 13 Administratif et Financier Management CM-UGP-PFS-239633-CS- Laying the Foundations of INDV / Recrutement d'un a Safety Net System and En cours 2021-06- 2021-06- 2021-07- 2021-06- 2021-07- 2021-09- 2023-03- IDA / 62230 A posteriori Individuel Direct 22,857.00 0.00 assistant au Spécialiste en Supporting Project d'exécution 30 18 10 28 31 04 08 Passation des Marchés Management CM-UGP-PFS-249781-CS- INDV / Recrutement du consultant chargé de Laying the Foundations of l'Elaboration du Cadre de a Safety Net System and En cours 2021-09- 2021-09- 2021-10- 2021-10- 2021-12- 2022-01- gestion environnementale IDA / 62230 A posteriori Individuel Limited 18,000.00 0.00 Supporting Project d'exécution 29 13 06 27 01 30 et sociale (CGES), avec Management évaluation des risques de sécurité, et les risques de Violence Basée sur le Genre (VBG) CM-UGP-PFS-249790-CS- INDV / Recrutement du Laying the Foundations of consultant chargé de a Safety Net System and En cours 2021-09- 2021-09- 2021-10- 2021-10- 2021-12- 2022-01- IDA / 62230 A posteriori Individuel Limited 9,030.00 0.00 l'Elaboration du Plan de Supporting Project d'exécution 29 13 06 27 01 30 Gestion de la Main d’Œuvre Management (PGMO) CM-UGP-PFS-249794-CS- INDV / Recrutement d'un consultant chargé de Laying the Foundations of l'élaboration du Plan de a Safety Net System and En cours 2021-09- 2021-09- 2021-10- 2021-10- 2021-12- 2022-01- IDA / 62230 A posteriori Individuel Limited 9,030.00 0.00 Mobilisation des Parties Supporting Project d'exécution 29 13 06 27 01 30 Prenantes (PMPP) qui Management intégrera un mécanisme de gestion des plaintes. CM-UGP-PFS-255951-CS- INDV / Recrutement d'un consultant individuel pour l’élaboration de la Stratégie Laying the Foundations of de Passation de Marchés a Safety Net System and En attente 2021-10- 2021-10- 2021-11- 2021-12- 2022-01- IDA / 62230 A posteriori Individuel Limited 15,000.00 0.00 pour promouvoir le Supporting Project d'exécution 20 27 17 22 16 Développement (PPSD : Management Project Procurement Strategy for Development) du Projet Filets Sociaux adaptatif et d’Inclusion Economique Page 14