Project name: Emergency 2007 Cyclone Recover Restoration Project AFII - BWDB Loan: ECRRP BWDB Procurement Plan Version: 2015-2 Status: Approved Date of Last Change of Status: 01/04/2015 Category Works: Activities ShowHide Description Reference # Rehabilitation of Polders 47/5 and 52/53B in ECRRP AFII -BWDB-1-NCB-O- Patuakhali District ECRRP/BWDB/W-01 Contract Completed Prior Review Rehabilitation of Polders 41/6B and 41/7B in ECRRP AFII -BWDB-31-NCB-O- Barguna District ECRRP/BWDB/W-02 Contract Completed Prior Review Rehabilitation of Polders 39/2A in Barguna ECRRP AFII -BWDB-32-NCB-O- District ECRRP/BWDB/W-03 Contract Completed Prior Review Rehabilitation of Polders 55/2C , 55/4 & ECRRP AFII -BWDB-33-NCB-O- 55/1in Patuakhali District ECRRP/BWDB/W-04 Contract Completed Prior Review Rehabilitation of Polder 46, 52/53 A, 54/A, ECRRP AFII -BWDB-34-NCB-O- 47/1 in Patuakhali District ECRRP/BWDB/W-05 Contract Completed Prior Review Rehabilitation of Polder 44(P) & 47/4 in ECRRP AFII -BWDB-35-NCB-O- Patuakhali District ECRRP/BWDB/W-06 Contract Completed Prior Review Rehabilitation of Polder 42 in Barguna ECRRP AFII -BWDB-36-NCB-O- District ECRRP/BWDB/W-07 Contract Completed Prior Review Rehabilitation of Polder 39/1D & 40/1 in ECRRP AFII -BWDB-37-NCB-O- Barguna District ECRRP/BWDB/W-10 Rehabilitation of Polder 39/1D & 40/1 in Barguna District Contract Completed Prior Review Rehabilitation of Polder 55/2B &50/51 ECRRP AFII -BWDB-38-NCB-O- Patuakhali District ECRRP/BWDB/W-14 Contract Completed Prior Review Additional Rehabilitation of Polder 41/6B, ECRRP AFII -BWDB-39-LPI-O- 52/53B, and 39/2A ECRRP/BWDB/W-18 Contract under execution Prior Review Rehabilitation of Polder 44/B, ECRRP AFII -BWDB-40-LPI-O- 55/2D,45,43/1, and 55/3 ECRRP/BWDB/W-19 Contract under execution Prior Review Rehabilitation of Polder 39/1A, 39/1C, ECRRP AFII -BWDB-41-LPI-O- 39/1B, 41/4, and 41/5 ECRRP/BWDB/W-20 Expected Prior Review Category Goods: Activities ShowHide Description Reference # Procurement of Motor Vehicles 4-WD ECRRP AFII -BWDB-6-NCB-B-BWDB/G-1 Jeep/Cross Country (6 Nos.) Contract Completed Post Review Procurement of Speed Boat with engine & ECRRP AFII -BWDB-7-NCB-B-BWDB/G-2 other accessories (Total 4 nos.) Contract Completed Post Review Procurement of Computers/UPS/IPS with ECRRP AFII -BWDB-8-NCB-B-BWDB/G-3 ancileries (Total 20 nos.) Contract Completed Post Review Engineering Instruments a) Telemeter 8 ECRRP AFII -BWDB-9-NCB-B-BWDB/G-4 Nos., b) Levelling instrument/theodolight with staff, ranging rod, tape with accessories 20 Nos. c) Drawing equipment sets 10 Nos. Contract Completed Post Review Office ecquipment with accessories ECRRP AFII -BWDB-10-NCB-B-BWDB/G-5 a)Photocopier 8 Nos.b) Fax-6 Nos.c) Scanner A3 Size 5 Nos.d) Spiral Binding machine 6 Nos e) Calculator 6 Nos.f)Plotter Ao Size 6 Nos. g) Color/Black & White Printer A3/A4 Size 6 Nos. Contract Completed Post Review Procurement of Computers/UPS/IPS with ECRRP AFII -BWDB-12-NCB-B-BWDB/G-7 ancileries (Total 20 nos.) Contract Completed Post Review Engineering Instruments a) Levelling ECRRP AFII -BWDB-13-NCB-B-BWDB/G-8 instrument/theodolight with staff, ranging rod, tape with accessories 8 Nos. b) GPS 2 Contract Completed Nos. Post Review Office ecquipment with accessories ECRRP AFII -BWDB-14-NCB-B-BWDB/G-9 a)Photocopier 4 Nos. b) Fax- 2 Nos. c) Scanner A3 Size 2 Nos. Contract Completed Post Review Procurement of Motor Vehicles 4-WD ECRRP AFII -BWDB-16-NCB-B-BWDB/G-11 Jeep/Cross Country (6 Nos.) Contract Completed Post Review Procurement of Speed Boat with engine & ECRRP AFII -BWDB-17-NCB-B-BWDB/G-12 other accessories (4 nos.) Termination of the Contract Post Review Procurement of Laptop and Desktop ECRRP AFII -BWDB-18-NCB-B-BWDB/G-13 Computer brand/clone (Intel Dual core-2 processors, Ram 4 GB) with accessories Contract Completed including UPS, Computer Table -25 sets. Post Review Engineering Instruments a) Telemeter 8 ECRRP AFII -BWDB-19-NCB-B-BWDB/G-14 Nos., b) Levelling instrument/theodolight with staff, ranging rod, tape with accessories 20 Nos. c) Drawing equipment sets 10 Nos. Contract Completed Post Review Procurement of Motor Cycle 25 nos ECRRP AFII -BWDB-21-NCB-B-BWDB/G-16 Contract Completed Post Review Purchase of Material testing ECRRP AFII -BWDB-23-NCB-B-BWDB/G-18 equipment/aparatus including installation /comissioning Activity Cancelled Post Review Procurement of Laptop and Desktop ECRRP AFII -BWDB-24-NCB-B-BWDB/G-19 Computer brand/clone (Intel Dual core-2 processors, Ram 4 GB) with accessories Contract Completed including UPS, Computer Table -25 sets. Post Review Office ecquipment with accessories ECRRP AFII -BWDB-25-NCB-B-BWDB/G-20 a)Photocopier 8 Nos.b) Fax-6 Nos.c) Scanner A3 Size 5 Nos.d) Spiral Binding machine 6 Nos e) Calculator 6 Nos.f)Plotter Ao Size 6 Nos. g) Color/Black & White Printer A3/A4 Size 6 Nos. h) IPS 5 Nos. i) AC 2 Nos. Contract Completed Post Review Procurement of Speed Boat with engine & ECRRP AFII -BWDB-26-NCB-B-BWDB/G-21 other accessories (4 nos.) Expected Post Review Engineering Instruments a) Telemeter 8 ECRRP AFII -BWDB-27-NCB-B-BWDB/G-22 Nos., b) Levelling instrument/theodolight with staff, ranging rod, tape with accessories 20 Nos. c) Drawing equipment sets 10 Nos. Expected Post Review Office ecquipment with accessories ECRRP AFII -BWDB-28-NCB-B-BWDB/G-23 a)Photocopier 8 Nos.b) Fax-6 Nos.c) Scanner A3 Size 5 Nos.d) Spiral Binding machine 6 Nos e) Calculator 6 Nos.f)Plotter Ao Size 6 Nos. g) Color/Black & White Printer A3/A4 Size 6 Nos. h) IPS 5 Nos. i) AC 2 Nos. Expected Post Review Office Building Repair and Maintenance ECRRP AFII -BWDB-30-NCB-B-BWDB/G-25 Expected Post Review Furniture's(For Project Director, ECRRP's ECRRP AFII -BWDB-11-CP-B-BWDB/G-6 BWDB Part office) Contract Completed Post Review Furniture's(For Project Director, ECRRP's ECRRP AFII -BWDB-15-CP-B-BWDB/G-10 BWDB Part office) Contract Completed Post Review Office equipment with accessories ECRRP AFII -BWDB-20-CP-B-BWDB/G-15 (Photocopier -8 nos., Fax- 6 nos., Scanner A3 size -5 nos., Spiral Binding Machine-6 nos., Color/black & White Printer A3/A4 size-6 nos., IPS-5 Nos. Air Conditioner- 2nos). Contract Completed Post Review Furniture's(For Project Director,ECRRP's ECRRP AFII -BWDB-22-CP-B-BWDB/G-17 BWDB Part office) Contract Completed Post Review Furniture's (For Project Director,ECRRP's ECRRP AFII -BWDB-29-CP-B-BWDB/G-24 BWDB Part office) Expected Post Review Category Consultants - Firms: Activities ShowHide Description Reference # Technical feasibility studies and detailed ECRRP AFII -BWDB-43-SBC-CF-BWDB/D2.1/S- design for River Bank Improvement Program 2 (RBIP) Contract under execution Prior Review Consultancy services for Project ECRRP AFII -BWDB-42-SBCC-CF-BWDB/C2/S- Management Design & Supervision of 1 Rehabilitation of Infrastructures damaged by cyclone SIDR in 3 (three) districts of Southern Bangladesh (including 2 (two) nos. individual consultants) Contract under execution Prior Review Technical feasibility studies and detailed ECRRP AFII -BWDB-46-SBCC-CF- design for Coastal Embankment BWDB/D2.2/S-3 Improvement Program (CEIP) Contract Completed Prior Review Overall Project and Preparatory Studies ECRRP AFII -BWDB-44-SSF-CF- Under bangladesh River Information and BWDB/D2.1/BRIC-1 (PPF-1) Conservation Program (BRIC) Contract Completed Prior Review Study on Geo-morphological Investigation ECRRP AFII -BWDB-45-SSF-CF- and Planform Analysis using Remote Sensing BWDB/D2.1/BRIC-2 Techniques and Environmental and Social Study of the Gorai River Restoration Project. Contract Completed Prior Review Category Consultants - Individuals: Activities ShowHide Description Reference # Consultancy Services for International ECRRP AFII -BWDB-61-SSF-CI-BWDB/D2.1/S- Procurement Expert as Individual Consultant 6 to assist PMO Office on the Procurement of Consultant (Main Consultant) of RBIP and others contract related matters. Contract Completed Prior Review Independent Reviewer for EIA under CEIP ECRRP AFII -BWDB-62-SSF-CI-BWDB/D2.2/S- 4 Contract Completed Post Review Independent Reviewer for SS & RAP under ECRRP AFII -BWDB-63-SSF-CI-BWDB/D2.2/S- CEIP 5 Contract Completed Post Review consultancy services of Individual Consultant ECRRP AFII -BWDB-47-IC-CI-BWDB/C2/S-1A for SIDR damage assessment [1st Contract]. Contract Completed Post Review consultancy services of Individual Consultant ECRRP AFII -BWDB-48-IC-CI-BWDB/C2/S-1B for SIDR damage assessment [1st Contract]. Contract Completed Post Review 2nd Contract in Continuation of 1st Contract. ECRRP AFII -BWDB-49-IC-CI-BWDB/C2/S-1A Contract Completed Post Review 2nd Contract in Continuation of 1st Contract. ECRRP AFII -BWDB-50-IC-CI-BWDB/C2/S-1B Contract Completed Post Review Engagement of Sr. individual Consultant to ECRRP AFII -BWDB-51-IC-CI-BWDB/C2/S-1C assist the Project Director (BWDB-Part) for different project activities throughout the project immplementation period. Ongoing Activity Post Review Sr.Consultant as Design Engineer (Team ECRRP AFII -BWDB-52-IC-CI-BWDB/C2/S-1D Leader). Contract Completed Post Review Sr.Consultant as Design Engineer ECRRP AFII -BWDB-53-IC-CI-BWDB/C2/S-1D1 Contract Completed Post Review Sr.Consultant as Design Engineer ECRRP AFII -BWDB-54-IC-CI-BWDB/C2/S-1D2 Contract Completed Post Review Sr.Consultant as Design Engineer (Team ECRRP AFII -BWDB-55-IC-CI-BWDB/C2/S- Leader). 2/D1 Contract Completed Post Review Sr Design Engineer - 1 ECRRP AFII -BWDB-56-IC-CI-BWDB/C2/S- 2/D2 Contract Completed Post Review Sr Design Engineer - 1 ECRRP AFII -BWDB-57-IC-CI-BWDB/C2/S- 2/D3 Contract Completed Post Review Procurement Specialist. ECRRP AFII -BWDB-58-IC-CI-BWDB/C2/S-2/P Contract Completed Post Review Land acquisition and resettlement Specialist. ECRRP AFII -BWDB-59-IC-CI-BWDB/C2/S-2/L Contract Completed Post Review Financial Management Specialist ECRRP AFII -BWDB-60-IC-CI-BWDB/C2/S-2/F Expected Post Review Independent Consultant to help the Project ECRRP AFII -BWDB-64-IC-CI-BWDB/D2.2/S-6 Director in Managing RBIP Consultants. Contract under execution Prior Review Land acquisition and resettlement Specialist. ECRRP AFII -BWDB-65-IC-CI-BWDB/C2/S-2/L- 1 Contract Completed Post Review Independent Panel of Experts (IPoE) as River ECRRP AFII -BWDB-66-IC-CI-BWDB/D2.3/S-6 morphologist and expert in river engineering work and/or Design Expert in Embankment and Hydraulic Structsures for the River Bank Improvement Project- Phase I (RBIP-I) under ECRRP (BWDB Part). River morphologist and expert in river Expected engineering work and/or Design Expert in Embankment and Hydraulic Structsures Post Review Independent Panel of Experts (IPoE) as Social ECRRP AFII -BWDB-67-IC-CI-BWDB/D2.4/S-6 Expert for the River Bank Improvement Project- Phase I (RBIP-I) under ECRRP (BWDB Part). Social Expert Expected Post Review Independent Panel of Experts (IPoE) as ECRRP AFII -BWDB-68-IC-CI-BWDB/D2.5/S-6 Environment, Water Management and Flood expert for the River Bank Improvement Project- Phase I (RBIP-I) under ECRRP (BWDB Part). Environment, Water Management and Flood Expected expert Post Review Independent Panel of Experts (IPoE) as River ECRRP AFII -BWDB-69-IC-CI-BWDB/D2.6/S-6 Engineering Expert for the River Bank Improvement Project- Phase I (RBIP-I) under ECRRP (BWDB Part). River Engineering Expert Expected Post Review Independent Environmental Reviewer for ECRRP AFII -BWDB-70-IC-CI-BWDB/D2.7/S-6 the River Bank Improvement Project Phase-I (RBIP-1) under ECRRP (BWDB Part) Ongoing Activity Post Review Consultancy Services for International ECRRP AFII -BWDB-71-IC-CI-BWDB/D2.8/S-6 Procurement Expert as Individual Consultant to assist PMO Office on the Procurement. Expected Post Review Land acquisition and resettlement Specialist. ECRRP AFII -BWDB-72-IC-CI-BWDB/C2/S-2/L- 2 Expected Post Review Sr Design Engineer ECRRP AFII -BWDB-73-IC-CI-BWDB/C2/S- 2/D4 Expected Post Review Environmental Management Specialist ECRRP AFII -BWDB-74-IC-CI-BWDB/D2.9/S-6 (Team Leader), Individual Consultant for Environmental Management Framework (EMF), Initial Environmental Examination (IEE) and Environmental Impact Assessment (EIA) of River Bank Improvement Project, Contract under execution Phase-I (RBIP-I) Post Review Social Development Specialist (Team ECRRP AFII -BWDB-75-IC-CI-BWDB/D2.10/S- Leader), Individual Consultant for supervise 6 and coordinate the Social Analysis (SA) of the 180 Km. RBIP and Remaining Works including field work carried out by KMC, with assistance from BDI, for the Priority Work (50 Km.) of River Bank Improvement Project, Phase-I (RBIP-I). Expected Post Review Sr. Design Engineer ECRRP AFII -BWDB-76-IC-CI-BWDB/C2/S- 2/D5 Expected Post Review Procurement Panel, Procurement Expert ECRRP AFII -BWDB-77-IC-CI-RBIP-1/D1/S2 (International). Expected Post Review Procurement Panel, Technical ECRRP AFII -BWDB-78-IC-CI-RBIP-1/D1/S3 Expert(International). Expected Post Review Procurement Panel, Procurement Expert ECRRP AFII -BWDB-79-IC-CI-RBIP-1/D1/S4 (National) Expected Post Review Independent Consultant to help the Project ECRRP AFII -BWDB-81-IC-CI-BWDB/D2.1/S- Director in Managing RBIP Consultants. 2.5 Expected Post Review Contract Management and Procurement ECRRP AFII -BWDB-82-IC-CI-BWDB/D2.1/S- Expert to help the Project Director 2.6 Expected Post Review Land acquisition and resettlement Specialist. ECRRP AFII -BWDB-83-IC-CI-BWDB/C2/S-2/L- 3 Expected Post Review Individual Consultant Environment Advisor ECRRP AFII -BWDB-84-IC-CI-BWDB/D2.11/S- (RBIP) 6 Contract under execution Post Review Environmental Management Specialist ECRRP AFII -BWDB-85-IC-CI-BWDB/D2.12/S- (Team Leader) RBIP 6 Expected Post Review New Activities Modified Activities Canceled Activities Activities without Modification Province/State E/A Amount in u$s No Objection Documents Barisâl Est. 1,620,875.00 12/07/10 Actual Barisâl Est. 1,404,937.50 01/08/10 Actual Barisâl Est. 709,250.00 10/10/10 Actual Barisâl Est. 2,350,800.00 04/11/10 Actual Barisâl Est. 2,334,000.00 17/10/10 Actual Barisâl Est. 2,929,825.00 28/06/11 Actual Barisâl Est. 1,027,750.00 27/06/11 Actual Barisâl Est. 1,134,125.00 18/07/11 Barisâl Est. 1,134,125.00 18/07/11 Actual Barisâl Est. 1,258,437.50 15/06/11 Actual Barisâl Est. 9,454,250.00 24/12/13 Actual Barisâl Est. 31,928,412.50 23/10/13 Actual Barisâl Est. 15,735,312.50 14/04/14 Actual Province/State E/A Amount in u$s No Objection Documents Dhaka Est. 275,000.00 N/A Actual Dhaka Est. 37,350.00 N/A Actual Dhaka Est. 7,137.50 N/A Actual Dhaka Est. 15,600.00 N/A Actual Dhaka Est. 7,787.50 N/A Actual Dhaka Est. 5,150.00 N/A Actual Dhaka Est. 2,825.00 N/A Actual Dhaka Est. 4,712.50 N/A Actual Dhaka Est. 469,377.93 N/A Actual Dhaka Est. 71,781.38 N/A Actual Dhaka Est. 7,500.00 N/A Actual Dhaka Est. 40,102.38 N/A Actual Dhaka Est. 50,000.00 N/A Actual Dhaka Est. 49,375.00 N/A Actual Dhaka Est. 2,162.50 N/A Actual Dhaka Est. 4,237.50 N/A Actual Dhaka Est. 64,256.00 N/A Actual Dhaka Est. 9,875.00 N/A Actual Dhaka Est. 4,443.75 N/A Actual Dhaka Est. 4,937.50 N/A Actual Dhaka Est. 3,125.00 N/A Actual Dhaka Est. 3,087.50 N/A Actual Dhaka Est. 1,775.00 N/A Actual Dhaka Est. 1,687.50 N/A Actual Dhaka Est. 1,481.25 N/A Actual Province/State E/A Amount in u$s Request for Proposal (RFP) and Short List Dhaka Est. 5,925,000.00 04/10/12 Actual Dhaka Est. 4,171,250.00 04/05/09 Actual 4,448,179.38 Dhaka Est. 2,577,500.00 08/10/09 Actual Dhaka Est. 599,600.00 18/03/11 Actual Dhaka Est. 252,762.50 15/03/11 Actual Province/State E/A Amount in u$s No Objection to the TOR P.P. - Executing Agency: 2015-2-BWDB - BWDB Method: SSS (Selection based on a single source) Dhaka Est. 147,937.50 13/11/12 Actual 13/11/12 Dhaka Est. 46,112.50 N/A Actual Dhaka Est. 46,112.50 N/A Actual Method: IC (Selection of Individual Consultants) Dhaka Est. 11,250.00 N/A Actual Dhaka Est. 11,250.00 N/A Actual Dhaka Est. 5,625.00 N/A Actual Dhaka Est. 5,625.00 N/A Actual Dhaka Est. 70,700.00 N/A Actual Dhaka Est. 10,312.50 N/A Actual Dhaka Est. 9,375.00 N/A Actual Dhaka Est. 9,375.00 N/A Actual Dhaka Est. 39,050.00 N/A Actual Dhaka Est. 35,725.00 N/A Actual Dhaka Est. 35,725.00 N/A Actual Dhaka Est. 10,450.00 N/A Actual Dhaka Est. 11,925.00 N/A Actual Dhaka Est. 14,137.50 N/A Actual Dhaka Est. 30,000.00 18/11/13 Actual 28/11/13 Dhaka Est. 20,475.00 N/A Actual Dhaka Est. 75,000.00 N/A Actual Dhaka Est. 118,750.00 N/A Actual Dhaka Est. 68,750.00 N/A Actual Dhaka Est. 162,500.00 N/A Actual Dhaka Est. 82,156.00 N/A Actual 17/03/14 Dhaka Est. 153,000.00 N/A Actual Dhaka Est. 22,500.00 N/A Actual Dhaka Est. 39,000.00 N/A Actual Dhaka Est. 60,625.00 N/A Actual Dhaka Est. 66,708.00 N/A Actual Dhaka Est. 20,000.00 N/A Actual Dhaka Est. 166,667.00 N/A Actual Dhaka Est. 64,103.00 N/A Actual Dhaka Est. 25,641.00 N/A Actual Dhaka Est. 115,385.00 N/A Actual Dhaka Est. 115,385.00 N/A Actual Dhaka Est. 23,077.00 N/A Actual Dhaka Est. 84,295.00 05/01/15 Actual 05/01/15 Dhaka Est. 95,257.00 01/01/15 Actual Publication / Invitation Bid Opening Evaluation of Bids P.P. - Executing Agency: 2015-2-BWDB - BWDB Method: NCB (National Competitive Bidding) 15/07/10 29/08/10 28/09/10 05/08/10 19/09/10 19/10/10 14/10/10 28/11/10 28/12/10 07/10/10 08/11/10 30/11/10 09/01/11 21/12/10 09/11/10 30/11/10 07/03/11 21/12/10 03/07/11 15/07/11 08/08/11 28/09/11 07/07/11 15/07/11 14/08/11 08/09/11 11/08/11 15/08/11 30/08/11 11/08/11 15/08/11 30/08/11 25/10/11 14/07/11 15/08/11 25/08/11 24/10/11 Method: ICB (International Competitive Bidding) 31/12/13 27/01/14 26/02/14 27/01/14 03/11/13 13/01/14 12/02/14 03/11/13 13/01/14 21/04/14 20/06/14 20/07/14 Publication / Invitation Bid Opening Evaluation of Bids P.P. - Executing Agency: 2015-2-BWDB - BWDB Method: NCB (National Competitive Bidding) 30/05/09 25/06/09 30/08/09 30/05/09 25/06/09 30/08/09 07/05/10 31/05/10 01/06/10 07/05/10 31/05/10 01/06/10 13/05/09 09/06/09 16/06/09 13/05/09 09/06/09 16/06/09 10/05/09 09/06/09 29/06/09 13/05/09 09/06/09 29/06/09 13/05/09 09/06/09 22/06/09 13/05/09 09/06/09 22/06/09 11/02/10 13/03/10 14/03/10 31/03/10 19/02/10 21/03/10 22/03/10 31/03/10 19/02/10 21/03/10 22/03/10 31/03/10 09/04/12 09/05/12 10/07/12 09/03/12 09/04/12 07/08/12 11/03/13 10/04/13 11/04/13 08/11/11 09/11/11 16/01/12 30/11/11 09/01/12 06/02/12 12/11/12 12/12/12 13/12/12 18/11/12 15/11/11 15/12/11 16/12/11 15/11/11 12/12/11 20/02/12 16/04/12 16/05/12 17/05/12 08/02/13 10/03/13 11/03/13 07/04/13 06/05/13 19/05/13 06/02/13 08/03/13 09/03/13 07/04/13 06/05/13 19/05/13 18/03/15 06/04/15 21/04/15 02/01/14 01/02/14 02/02/14 02/01/14 01/02/14 02/02/14 02/12/13 01/01/14 02/01/14 Method: SH (Shopping) 08/03/09 19/03/09 12/06/09 11/05/09 11/05/09 20/05/09 09/03/10 08/04/10 09/04/10 15/05/10 07/03/12 14/03/12 15/03/12 25/03/12 21/12/11 28/12/11 29/12/11 02/12/13 01/01/14 02/01/14 No Objection to RFP and Short List Invitation for RFP Bid Opening P.P. - Executing Agency: 2015-2-BWDB - BWDB Method: QBS (Quality Based Selection) 04/10/12 05/10/12 29/11/12 29/11/12 Method: QCBS (Quality and Cost Based Selection) 05/05/09 06/05/09 05/06/09 03/05/09 28/06/09 27/10/09 15/11/09 30/12/09 15/12/09 Method: SSS (Selection based on a single source) 30/03/11 20/04/11 30/05/11 22/03/11 19/04/11 27/05/11 Contract Signature Date Total days of Process End Date of Activity 2015-2-BWDB - BWDB sed on a single source) 03/12/12 30/06/14 03/12/12 30/06/14 12/08/12 04/09/12 12/08/12 04/09/12 04/08/12 05/09/12 04/08/12 05/09/12 ndividual Consultants) 03/03/09 02/09/09 03/03/09 02/09/09 03/03/09 02/09/09 03/03/09 02/09/09 01/11/09 31/01/10 01/11/09 31/01/10 01/11/09 31/01/10 01/11/09 31/01/10 14/08/12 30/06/14 20/06/11 20/10/11 20/06/11 20/10/11 20/06/11 20/10/11 20/06/11 20/10/11 20/06/11 20/10/11 20/06/11 20/10/11 03/11/11 30/06/14 03/11/11 30/06/14 03/11/11 30/06/14 03/11/11 30/06/14 03/11/11 30/06/14 03/11/11 30/06/14 20/11/11 30/06/14 20/11/11 31/12/13 12/12/11 30/06/14 12/12/11 28/02/13 28/08/12 30/06/14 31/12/13 31/12/15 31/12/13 09/04/13 30/04/14 22/05/13 05/03/14 25/05/14 25/05/16 25/05/14 25/05/16 25/05/14 25/05/16 25/05/14 25/05/16 25/05/14 31/12/14 31/07/14 31/12/17 31/07/14 31/07/15 31/07/14 31/07/15 01/06/14 31/03/15 23/06/14 01/05/14 31/01/15 31/07/14 30/06/15 09/02/15 09/01/16 09/02/15 09/01/16 09/02/15 09/01/16 01/01/15 31/08/16 17/06/15 31/12/17 01/10/15 30/09/16 29/01/15 31/12/15 29/01/15 01/02/15 31/12/15 No Objection to Evaluation Report Contract Signature Date DB - BWDB e Bidding) 18/10/10 07/11/10 25/10/10 07/11/10 20/10/10 25/11/10 25/10/10 25/11/10 30/12/10 10/01/11 05/01/11 03/02/11 25/01/11 20/02/11 14/02/11 03/03/11 20/06/11 30/07/11 26/06/11 25/07/11 02/10/11 05/10/11 19/01/12 13/09/11 05/10/11 03/02/12 11/09/11 30/09/11 11/09/11 30/09/11 30/01/12 21/09/11 05/11/11 19/01/12 ve Bidding) 13/03/14 15/04/14 20/05/14 27/02/14 28/04/14 18/08/14 04/08/14 04/08/14 No Objection to Evaluation Report Contract Signature Date DB - BWDB e Bidding) N/A 22/10/09 22/10/09 N/A 03/06/10 03/06/10 N/A 29/06/09 29/06/09 N/A 18/08/09 18/08/09 N/A 29/06/09 29/06/09 N/A 15/03/10 18/04/10 N/A 23/03/10 18/04/10 N/A 22/03/10 18/04/10 N/A 16/09/12 16/09/12 N/A 12/04/13 N/A 16/01/12 20/02/12 N/A 14/01/13 14/01/13 N/A 09/01/12 29/02/12 N/A 16/10/12 N/A 02/04/13 09/06/13 N/A 07/04/13 09/06/13 N/A 10/05/15 N/A 03/02/14 N/A 02/02/14 N/A 02/01/14 N/A 12/06/09 28/05/09 N/A 19/05/10 19/05/10 N/A 27/03/12 27/03/12 N/A 15/01/12 16/01/12 N/A 02/01/14 Technical Evaluation No Objection to Technical Evaluation Executing Agency: 2015-2-BWDB - BWDB Method: QBS (Quality Based Selection) 27/03/13 26/06/13 27/03/13 26/06/13 d: QCBS (Quality and Cost Based Selection) 06/06/09 07/06/09 16/02/10 28/02/10 24/02/10 10/03/10 od: SSS (Selection based on a single source) 28/06/11 11/07/11 17/07/11 29/07/11 Comment Add Comment Add Comment Add Comment Add Comment Add Comment Add Comment Add Comment Add Comment Add Comment Add Comment Add Comment Add Comment Add Comment Add Comment Add Comment Add Comment Add Comment Add Comment Add Comment Add Comment Add Comment Add Comment Add Comment Add Comment Add Comment Add Comment Add Comment Add Comment Add Comment Add Comment Add Comment Add Comment Add Comment Add Comment Add Comment Add Comment Add Comment Add Comment Total days of Process (between Bid Opening and Contract Signature Date) End of Contract (Completed) Comment 70 05/05/12 Add Comment 31/03/13 67 24/05/12 Add Comment 24/05/13 43 02/08/12 Add Comment 119 31/07/13 82 08/06/12 Add Comment 72 31/03/13 242 22/01/13 Add Comment 216 15/06/13 82 20/02/13 Add Comment 113 15/06/13 82 18/01/13 Add Comment 148 15/03/13 46 29/10/12 46 29/10/12 Add Comment 97 23/12/12 82 20/02/13 Add Comment 87 30/04/13 78 15/05/15 Add Comment 113 105 30/05/16 Add Comment 217 45 30/05/16 Add Comment Total days of Process (between Bid Opening and Contract Signature Date) End of Contract (Completed) Comment 119 14/11/09 Add Comment 119 14/11/09 3 29/06/10 Add Comment 3 29/06/10 20 30/06/09 Add Comment 20 30/06/09 70 14/09/09 Add Comment 70 06/09/09 20 30/06/09 Add Comment 20 30/06/09 2 20/04/10 Add Comment 18 04/06/14 2 20/04/10 Add Comment 18 04/06/10 1 20/04/10 Add Comment 18 04/06/10 130 27/11/12 Add Comment 160 27/11/12 2 18/05/13 Add Comment 68 06/02/12 Add Comment 42 29/03/12 33 11/02/13 Add Comment 57 11/02/13 25 15/02/12 Add Comment 79 04/05/12 153 18/11/12 Add Comment 23 12/05/13 Add Comment 34 18/06/13 30 19/05/13 Add Comment 34 18/06/13 34 18/05/15 Add Comment 2 30/03/14 Add Comment 1 31/03/14 Add Comment 1 28/02/14 Add Comment 85 30/06/09 Add Comment 17 30/06/09 41 30/05/10 Add Comment 4 30/05/10 13 31/03/12 Add Comment 2 31/03/12 18 12/02/12 Add Comment 21/03/12 1 28/02/14 Add Comment Final Evaluation and Negotiation No Objection to Contract Contract Signature Date 27/06/13 03/10/13 04/10/13 16/07/13 29/10/13 08/06/09 09/06/09 10/06/09 15/10/09 12/11/09 20/04/10 12/07/10 10/08/10 16/08/10 26/08/11 18/09/11 10/10/11 13/10/11 16/08/11 09/09/11 23/10/11 13/10/11 Total days of Process (between Bid Opening and Contract Signature Date) End of Contract (Completed) Comment 309 30/12/16 Add Comment 334 5 30/12/16 Add Comment 137 223 28/02/12 Add Comment 244 15/03/12 133 30/06/12 Add Comment 30/06/12 149 30/06/12 Add Comment 30/06/12