Independent Evaluation Group (IEG)                             Implementation Completion Report (ICR) Review
     Liaoning Coastal Economic Zone Project (P126611)



                                                                                 Report Number: ICRR0022097

1. Project Data



 Project ID                                 Project Name
 P126611                                    Liaoning Coastal Economic Zone Project

 Country                                    Practice Area(Lead)
 China                                      Urban, Resilience and Land


 L/C/TF Number(s)                           Closing Date (Original)               Total Project Cost (USD)
 IBRD-82360                                 30-Sep-2018                                        140,547,609.55

 Bank Approval Date                         Closing Date (Actual)
 20-Mar-2013                                30-Sep-2019

                                            IBRD/IDA (USD)                                     Grants (USD)

 Original Commitment                          150,000,000.00                                               0.00

 Revised Commitment                           140,547,609.55                                               0.00

 Actual                                       140,547,609.55                                               0.00




 Prepared by                Reviewed by                   ICR Review Coordinator         Group
 Cynthia Nunez-Ollero       Vibecke Dixon                 Christopher David Nelson       IEGSD (Unit 4)




2. Project Objectives and Components

DEVOBJ_TBL
a. Objectives
   According to the Financing Agreement (FA, p. 5) and the Project Appraisal Document (PAD, paragraph 17)
   the Project Development Objective (PDO) was "to improve the efficiency of urban transport and address water
   scarcity issues in selected cities in Liaoning Province."

   This PDO was revised during the 2016 restructuring (see below) "to improve transport connectivity and
   reclaim wastewater in selected cities in Liaoning Province."


                                                                                                  Page 1 of 19
     Independent Evaluation Group (IEG)                               Implementation Completion Report (ICR) Review
     Liaoning Coastal Economic Zone Project (P126611)



   This review has parsed the original PDO into:

          to improve the efficiency of urban transport in selected cities in Liaoning Province
          to address water scarcity issues in selected cities in Liaoning Province

   The revised PDO has been parsed into:

          to improve the transport connectivity in selected cities in Liaoning Province
          to reclaim wastewater in selected cities in Liaoning Province



b. Were the project objectives/key associated outcome targets revised during implementation?
  Yes

  Did the Board approve the revised objectives/key associated outcome targets?
  Yes

  Date of Board Approval
  19-May-2016

c. Will a split evaluation be undertaken?
   Yes

d. Components
   1. Improving Urban Transport Systems (US$107.8 million at appraisal, revised to US$117.1 million at
   restructuring, US$109 million actual). The project was to finance new roads and rehabilitate existing urban
   roads with designs for traffic management, traffic calming features, and facilities that promoted cleaner
   alternative transport modes, such as bicycling and walking. All road designs were to include underground
   urban utilities, traffic signs and management systems, landscaping, street furniture, and other ancillary
   facilities, and acquisition of road maintenance equipment. In addition, this component was to finance buses
   and improve bus depots of the Panjin Public Transport Company. Originally, these roads were in Chaoyang,
   Donggang, Kuandian, and Lingyuan, This project was designed to foster an integrated approach to public
   transport planning, combining infrastructure investments with traffic management improvements, better
   public transport services, and integrating transport in land use planning. This component was revised after
   the 2016 restructuring and dropped the activities related to improving transport systems in the Longcheng
   district in the city of Chaoyang.

   2. Improving Urban Wastewater Treatment and Reclamation (US$40.6 million at appraisal, revised to
   US$31.2 million at restructuring, US$29.9 million actual). This component would construct new wastewater
   plants in Lingyuan City, rehabilitate existing wastewater plants, construct new networks and separate
   sewage and drainage networks in Suizhong county, and replace groundwater with water reclamation supply
   systems. Water related subprojects in Lingyuan and Suizhong were designed to provide good examples of
   integrated investments to address critical water pollution and scarcity issues. The subproject in Suizhong
   was intended to address the water pollution and poor drainage due to encroachment of existing canals,




                                                                                                    Page 2 of 19
     Independent Evaluation Group (IEG)                             Implementation Completion Report (ICR) Review
     Liaoning Coastal Economic Zone Project (P126611)



   siltation, and reduced hydraulic flows. This component was reduced after the 2016 restructuring, with
   discontinued activities in Suizhong, which reduced the allocation for this component.

   3. Project Management and Capacity Building (US$1.65 million at appraisal, US$1.64 million
   actual). This component was to finance project management and supervision such as training
   in procurement, financial management, and contract supervision. In addition, to build the capacity of the
   local staff and officials involved in delivering water and urban transport services in participating cities,
   technical assistance would aid in preparing the following plans: (i) urban transport investment and
   management plans promoting public transport, pedestrian, bicycles, and traffic safety; (ii) comprehensive
   capital investment and asset management plans ensuring the sustainability of project investments; (iii)
   environmental management plans (EMPs); and (iv) resettlement action plans (RAPs). This component did
   not include the financing of project monitoring and evaluation (M&E) activities. The implementing entity, the
   Liaoning Provincial Management Office (LPMO) managed other World Bank projects and had existing
   procedures (PAD, paragraph 38).



e. Comments on Project Cost, Financing, Borrower Contribution, and Dates
   Project Cost: The total project cost reached US$150 million and disbursed US$140.5 million.

   Financing: The International Bank for Reconstruction and Development (IBRD) financed this investment
   project. There were no co-financiers.

   Borrower Contribution:The government committed US$189.5 million, revised to US$75.7 million and
   disbursed US$75.7 million. The reduced amount was due to two cities withdrawing from participation,
   reducing the needed counterpart financing (see Restructuring below).

   Dates:The project was approved on March 20, 2013 and was made effective on July 22, 2013. The Mid
   Term Review (MTR) was conducted on February 27, 2017. The original closing date was on September 30,
   2018 but was extended by 12 more months to end on September 30, 2019. There were two restructurings,
   one each of levels 1 and 2:

         On May 19, 2016, a level 1 restructuring to amend the PDOs, introduce changes to the results
          framework as a result, adjust the components and its allocation, reallocate among the disbursement
          categories in the financing plan, and amend the implementation schedule.
         On Sep 27, 2018, a level 2 restructuring to reduce from 15 to 5 the intermediate outcome target
          indicator for the number of industries connected to reclaimed wastewater in the results framework,
          extend the loan closing date, and amend the implementation schedule as a result of the extension.




3. Relevance of Objectives

Rationale
The PDOs of the Liaoning Coastal Economic Zone Urban Infrastructure and Environmental Management
Project were relevant to the five main areas of engagement under China's 13th Five Year Plan (FYP, 2016-


                                                                                                    Page 3 of 19
                                      Independent Evaluation Group (IEG)                         Implementation Completion Report (ICR) Review
                                      Liaoning Coastal Economic Zone Project (P126611)



               2020). The PDOs were substantially relevant to (i) innovation, (ii) coordinated development, (iii) green
               growth, (iv) openness, and (v) inclusive growth,

               The PDOs were also relevant to the World Bank Group’s Country Partnership Framework (CPF) for FYs
               2020-2025 for China. The three main areas of engagement were: (i) advancing market and fiscal reforms,
               (ii) promoting greener growth, and (iii) sharing the benefits of growth. The project addressed the CPF’s
               theme to promote greener growth by enhancing urban environmental services in the participating cities;
               promoting low-carbon urban transport; and demonstrating measures to reduce pollution. The innovative
               designs adopted in transport infrastructure promoted the use of public transport and non-motorized
               transport. In water supply reclaimed wastewater was used in place of groundwater extraction (ICR, footnote
               13). Relevance to sharing the benefits of growth was evident in the project's support to enhanced services
               and opportunities in the secondary cities in Liaoning as well as in promoting access and transport
               connectivity in less developed areas of the province.

               There was clear alignment between the PDOs and the country and World Bank strategies, but the
               objectives were formulated to a level of ambition that did not adequately reflect a potential solution to a
               development problem. For example, "reclaiming wastewater" was not outcome focused. The formulation did
               not help understand the development results of the project - e.g., how the outcomes would positively affect
               community livelihoods, employment, or economic productivity. These may be longer term targets but
               identifying and tracking them was an important aspect of a successful development operation (see Section
               8, Bank Performance, and Section 9, Monitoring and Evaluation below).


               Rating Relevance TBL




               Rating
               Substantial


   4. Achievement of Objectives (Efficacy)

EFFICACY_TBL




                             OBJECTIVE 1
                             Objective
                             to improve the efficiency of urban transport in selected cities in Liaoning Province

                             Rationale
                             The following were the inputs and activities: (i) rehabilitation and construction of new roads in Chaoyang,
                             Donggang, Kuandian, and Lingyuan; and (ii) acquisition of buses, piloting public transport bus routes,
                             improving bus depots, and procuring road maintenance equipment. These activities would lead to outputs
                             such as improved roads, maintained bus depots, increase in the number of passengers per year who would
                             use selected routes of the Panjin Public Transport Co. These outputs were expected to lead to outcomes
                             such as increased use of non-motorized transport. increased density of passengers using public transport,
                             increased lending to transport efficiency and improved access between lagging urban areas to more
                             progressive ones in Liaoning Province. These outcomes would in turn lead to greener growth and more
                             inclusive development. The underlying assumptions were sufficient capacity to implement project
                             investments, consistent support from the national and local governments, and availability of counterpart

                                                                                                                               Page 4 of 19
   Independent Evaluation Group (IEG)                               Implementation Completion Report (ICR) Review
   Liaoning Coastal Economic Zone Project (P126611)



financing. Direct attribution of outcomes to the project inputs were established for the pilot public transport
subprojects through improved services of the Panjin Public Transport Co. The rest of the project outcomes
were not direct measures of transport efficiency but together with other factors such as overall bus density,
frequency, ticketing system, and energy efficiency of services, they contributed to making transport services
more efficient (ICR, paragraph 27).

OUTPUTS:

      At closing, 50.7 km of new and rehabilitated streets with improved public transport and non motorized
       transport in Chaoyang, Donggang, Kuandian, and Lingyuan were achieved (original target 52 km,
       target almost achieved).
      At closing, the number of passengers increased to 62,122 passengers per year on selected bus
       routes in Panjin (original target 15,000, target exceeded.
      At closing, there was a 15 percent Increase in annual road maintenance budget in participating cities
       (original target 8 percent, exceeding target).
      At closing, 2 Revised local traffic management plans and capital investments plans were revised
       (original target 3, target almost achieved.

OUTCOMES:

      At closing, 99 percent of people walking and biking were satisfied with the new and improved facilities
       on selected roads in Chaoyang, Donggang, Kuandian and Lingyuan (target 70 percent, target
       exceeded).
      At closing, 98 percent of riders were satisfied with public transport services on selected routes in
       Panjin (target 60 percent, target exceeded).
      According to the ICR, these key outcome indicators did not directly measure efficiency (ICR,
       paragraph 27).



Rating
Modest


OBJECTIVE 1 REVISION 1
Revised Objective
to improve transport connectivity in selected cities in Liaoning Province

Revised Rationale
Theory of Change: The Longcheng district in the city of Chaoyang and the city of Suizhong dropped out of
the project in 2016 because of changing investment priorities of its new leaders. In addition, the Chinese
economy had slowed down, and new budget law amendments that became effective in August 2014 limited
the city's funding source for the required counterpart financing (ICR paragraph 21 and footnote 10). The
indicators of efficiency in transport investments were also deemed inappropriate and the PDO itself misstated.
As a result, the following activities and inputs were undertaken: (i) rehabilitation or construction of roads, and
(ii) implementing a pilot public transport system, construction of bus depots, and purchase of road
maintenance equipment. These inputs were to lead to outputs such as new and rehabilitated streets in

                                                                                                    Page 5 of 19
   Independent Evaluation Group (IEG)                                Implementation Completion Report (ICR) Review
   Liaoning Coastal Economic Zone Project (P126611)



Donggang, Kuandian, and Lingyan, reduced travel times, increased road densities, increased number of
passengers per year in selected Panjin bus routes, and increased use of non-motorized transport (walking
and biking). These outputs were expected to lead to outcomes such as optimized bus services, improved
regional connectivity, and the establishment of local networks This was then expected to foster, green growth
and inclusive development in Liaoning Province. The underlying assumptions under the original objective
remained the same.

OUTPUTS:

      50.70 km of new and rehabilitated streets with improved public transport and non-motorized
         transport in Donggang, Kuandian and Lingyuan (original target 52 km, revised target 31.68 km, target
         exceeded)
        13.65 km of non-rural roads were constructed (original target 10.55 km, target exceeded)
        37.05 km of non-rural roads were rehabilitated (original target 21.13 km, target exceeded)
        The number of passengers increased to 62,122 passengers per year on selected bus routes in
         Panjin (original target 5,100, target exceeded). The ICR cautioned against the reliability of the data
         submitted by the Provincial Project Management Office (ICR, Annex 1, p.38). However, footnote 18
         acknowledged that the target was likely exceeded even if the final numbers were flawed.
        There was a 15 percent increase in the annual road maintenance budgets of the participating cities
         (original target 8 percent, revised target 15 percent, target achieved)
        575 staff training days in traffic management planning, asset management planning, and project
         operations (target 340, target exceeded)
        2 Revised local traffic management plans and capital investment plans and a database for all four
         cities will be used in the future.

Donggang City

      1,466 m long x 45 m wide Zhanqian Avenue, segregated bus lanes were constructed. In addition,
       790.12 m of Gaotie Avenue was upgraded. and another 4,023.27 m of the following roads were
       constructed: Haiguanbei Road (1,227.6 m long x 30 m wide), Hengyi Road (1,081.16 m long x 18 m
       wide); Henger Road (1,197.29 x 30 m long x 30m wide) was constructed; and Hengsan
       Road (517.22 m long x 30m wide).
      18 road maintenance equipment were procured - one each of asphalt spreader, exaction truck, filling
       machine, spreader, double steel wheel vibrating roller, guardrail cleaning vehicle, and two each of
       high-altitude working vehicles, pipeline cleaning vehicles, sanitary suction trucks, road sweepers, road
       cleaning vehicles, and garbage trucks.

Kuandian County

      Rehabilitated 36 secondary access roads within the urban area (total of 21,460 m long x 4 – 21.5 m
         wide).
      Constructed 3 bridges (with a total of 176 m long and 9 – 12.5 m wide).
      Procured road maintenance and traffic management equipment (wheel loader, snow thrower,
         sprinkler, traffic signal control system, traffic signal machine and cabinet, signal machine and cabinet




                                                                                                     Page 6 of 19
   Independent Evaluation Group (IEG)                                 Implementation Completion Report (ICR) Review
   Liaoning Coastal Economic Zone Project (P126611)



         foundation, vehicle signal lamp, direction indicating signal lamp, lane light bracket, cantilever signal
         lamp pole and foundation, camera, etc.)

Lingyuan City

      Constructed 7 roads (total length 5157.90 m) and the southern section of East Binhe Road (1,895.51
         m), Wenyi Road (m)
      Constructed a bridge (31 m), Wuiu Bridge (135 m), and Wenyi Bridge (304.4 m)
      Rehabilitated 10 roads (total length 11871.3 m), Wuliu Da Road (956.85 m), and the northern section
       of East Binhe Road (2,520 m)
      Procured 24 sets of equipment for road maintenance and management.

Panjin City

      Constructed 2 bus maintenance depots, one at Shuangtaizi (2,4000 m2) and one at Xinglongtai
         (56,000 m2).
      Procured 40 new 8.5 m Liquefied Natural Gas (LNG) buses; 20 new 9.3 m LNG buses; 50 new 10.5 m
       LNG cum electric buses; and 30 new 12 m LNG cum electric buses.
      Replaced facilities and equipment for buses and depots.

OUTCOMES

      There were 350,340 direct beneficiaries (no baseline reported, original target 340,000, revised target
         213,200, target exceeded)
        There were 172,520 direct female beneficiaries (no baseline reported, original target 170,000, revised
         target 106,600, target exceeded)
        99 percent of people walking and biking were satisfied with new and improved facilities on selected
         roads in Donggang, Kuandian and Lingyuan (baseline 45 percent, original target 70 percent, target
         exceeded).
        98 percent increase in satisfaction by riders with public transport services on selected routes in Panjin
         (baseline 35 percent, original target 60 percent, target exceeded). The ICR cautioned that this
         increase in satisfaction may also be due to new destinations, new attractions, and improved
         attractiveness of the city itself (ICR, paragraph 37). According to the March 2019 satisfaction survey,
         99 percent of the Panjin respondents expressed satisfaction with safe services, 91 percent with
         sanitation conditions, 90 percent with the facilities conditions, 88 percent with the bus services, 81
         percent with the fares, 74 percent with travel speed. A few raised issues with discomfort such as
         crowding, bad attitudes of drivers and passengers, and traffic jams.
        Since the outcome indicators in the Results Framework measured beneficiary satisfaction and not the
         outcome of transport connectivity, the Project Management Office (PMO) gathered additional data to
         measure efficiency of connectivity such as reduced travel time, increased road density, public
         transport density and relation to land use.
        Regional connectivity was enhanced as reflected in the roads being connected to two China National
         Highways - one that runs from Beijing to Shenyang, and the other that runs from Inner Mongolia to
         Liaoning coastal cities.
        The connection of the improved roads to a newly constructed high speed railway station improved
         access to the city center and economic livelihood opportunities. Improved link between the old town

                                                                                                      Page 7 of 19
   Independent Evaluation Group (IEG)                              Implementation Completion Report (ICR) Review
   Liaoning Coastal Economic Zone Project (P126611)



         and city core, access to newly constructed residential areas, and access to industries all improved
         connectivity.
        Connectivity was measured by road density or the ratio of the total length of the road network to the
         overall land area.
        Road density increased by 47 percent in Donggang (from 5.32 to 7.81); by 48 percent in Kuandian
         (from 0.23 to 0.34); by 21 percent in Panjin (from 6.12 to 7.42) and by 58 percent in Lingyuan (from
         2.39 to 3.78).
        Connectivity between cities was measured by (i) connectivity between old town and city core, (ii)
         improved access of newly constructed residential areas south of Lingyuan River to the city core in the
         north of the river, and (iii) access to logistics industries in the industrial zone east of the city.
        Travel time was reduced by 30 minutes for Panjin passengers due to optimized bus routes
         and improved road quality. In Lingyuan, travel time was reduced in project-supported roads by 6
         minutes/km for autos, 11 minutes/km for bicycles. In Kundian, 30 minute travel time was saved due to
         road design (paved dirt roads).



Revised Rating
Substantial


OBJECTIVE 2
Objective
to address water scarcity issues in selected cities in Liaoning Province

Rationale
Theory of Change: Three activities were undertaken: (i) construction of new and rehabilitation of existing
wastewater plants; (ii) construction of new and rehabilitation of separate sewage and drainage networks; and
(iii) replacement of groundwater with water reclamation supply systems. These activities would lead to
outputs such as (i) industries that would connect to reclaimed water supply systems in Lingyuan, and (ii)
drainage pipes would be completed in Suizhong. These outputs would lead to outcomes such as increased
use of reclaimed wastewater in industrial parks and improved urban drainage system in Suizhong. Both
outcomes would address the water scarcity issues and lead to the higher level objective of greener and more
inclusive growth in the cities of Liaoning. However, the PDO outcome indicators lacked explicit definition of
water scarcity issues.

OUTPUTS:

      At closing, 6 industries were connected to reclaimed water system in Lingyuan (original target 20,
         target not achieved).
      At closing, no drainage pipes were completed in Suizhong because they dropped out of the project
         (original target 76 km).

OUTCOMES:

      At closing, Suizhong and its activities dropped out of the project, no urban area in Suizhong
         benefited from improved drainage system.

                                                                                                  Page 8 of 19
   Independent Evaluation Group (IEG)                                Implementation Completion Report (ICR) Review
   Liaoning Coastal Economic Zone Project (P126611)




      There was no reported impact on water scarcity.
      At closing, 78 percent of reclaimed wastewater was used in the industrial parks in Lingyuan, (original
         target 60 percent, target exceeded).
      At closing, there were 350,340 project beneficiaries (target 213,200, target exceeded), of whom 49.2
         percent (172,520) were female (original target 50 percent or 106,600 target almost achieved
         percentage wise).



Rating
Modest


OBJECTIVE 2 REVISION 1
Revised Objective
"to reclaim wastewater in selected cities in Liaoning Province."

Revised Rationale
Theory of Change: The objective was revised because the Suizhong subproject, which was supposed to
demonstrate the impact on water scarcity through its drainage and water pollution control activities, were no
longer part of the project. Only reusing the effluent of water treatment plans for the industries in Lingyuan city
remained. The project focused on three activities: (i) construction of new and rehabilitating existing
wastewater treatment plants; (ii) construction of new and rehabilitation of sewage and drainage systems; and
(iii) replacing the groundwater with reclaimed water supply systems. These activities led to outputs where
industries in Lingyuan were connected to reclaimed water systems, and the use of reclaimed wastewater in
industrial parks increased. These outputs led to outcomes that demonstrated impact on water scarcity by
resusing effluent water treatment plants for Lingyuan industries. These further contributed to greener growth
in the participant cities of Liaoning Province.

OUTPUTS:

      40.27 km of sewage collection networks were installed (baseline 0, original target 49.9 km, target
         almost achieved). According to the June 3, 2020 email from the Task Team to IEG, the final outputs
         for the new sewerage system were below targets because some pipelines were switched for domestic
         funding at the government's request.
        42.98 km of storm drainage networks were installed (baseline, original target 37.1 km, target
         exceeded)
        23.76 km of reclaimed wastewater networks were installed, including a pumping station of 30,000
         m3/day that connected the Waste Water Treatment Plant to the industrial park (baseline 0, original
         target 30.7 km, target almost achieved)
        A boosting pumping station with capacity of 30,000 m3/d was constructed to supply remote users from
         the network, achieving target.
        Wastewater, storm water, and reclaimed water facilities maintenance and management equipment
         were procured achieving target.
        6 Industries were connected to reclaimed water system in Lingyuan (baseline 0, original target 20,
         revised target 5, target exceeded)


                                                                                                     Page 9 of 19
                                 Independent Evaluation Group (IEG)                               Implementation Completion Report (ICR) Review
                                 Liaoning Coastal Economic Zone Project (P126611)




                                    575 staff training days in project financed training and TA activities (baseline 60, original target 460,
                                     revised target 340, target exceeded
                                    2 local traffic management plans and capital investment plans were revised (baseline 0, original target
                                     3, revised target 2, target achieved). The ICR noted that the PAD did not provide a clear definition for
                                     "revised plans." The ICR reported revised plans as improvements to any kind of local traffic
                                     management plans and asset management plan. The alternative would have included formal change
                                     in statutes of the plans.

                              OUTCOMES:

                                    78 percent of reclaimed wastewater was used in the industrial parks (original target 60 percent,
                                     revised target 50 percent, target exceeded).
                                    The 6 major industrial users signed up for long term agreements to buy 20,000 cubic meter per day of
                                     reclaimed water at full cost recovery and competitive price of US$0.36 per cubic meter or 60 percent
                                     of municipal tap water tariff for industrial users. According to the ICR, a call to an industrial user
                                     confirmed that the average use of reclaimed water in other parts of China was around 20-30 percent
                                     (ICR, footnote 27).
                                    Operating costs were fully recovered after 60 percent of treated municipal wastewater was reclaimed
                                     and 57 percent of that reclaimed water was sold to industries at the competitive price.



                              Revised Rating
                              Substantial


OVERALL EFF TBL




                  OBJ_TBL




                            OVERALL EFFICACY
                            Rationale
                            The efficacy of the original PDOs were modest after assessing outcomes at closing. The PDOs were revised
                            after disbursing only US$5.86 million of the project before the 2016 restructuring. Measuring the efficiency
                            gains from the transport investments proved difficult because of the indicators used. It was also difficult to
                            measure the impact on water scarcity issues because the water subproject in Suizhong was dropped in 2016.
                            Although the remainder of the subproject focused on reusing effluent of a wastewater treatment plan for
                            Industries in Lingyuan City.



                            Overall Efficacy Rating                                     Primary Reason
                            Modest                                                      Insufficient evidence
                  OBJR1_TBL




                            OVERALL EFFICACY REVISION 1
                            Overall Efficacy Revision 1 Rationale
                            With the revised objectives introduced during the 2016 restructuring, the outcome targets were all exceeded.
                            In addition, outcomes were directly attributed to the project. Outcomes contributed to greener growth as

                                                                                                                                  Page 10 of 19
      Independent Evaluation Group (IEG)                                Implementation Completion Report (ICR) Review
      Liaoning Coastal Economic Zone Project (P126611)



  evidenced by the increase in the number of industries that used reclaimed wastewater instead of extracted
  groundwater. Additional data provided by the LPMO included some measure of efficiency improvements in
  urban transport service delivery. Based on their experience with the Panjin bus project, the city issued an
  ordinance mandating housing developers to reserve lands for bus routes, bus stops to address access and
  mobility of future residents. This act supported feeder service to transit nodes near residences and reduced
  the cost of future land acquisition. Reclaimed water regenerated the urban landscape and increased urban
  biodiversity, reduced water pollution, and double access to municipal wastewater collection. However, the
  second revised objective was not clearly stated. The PDO did not reflect the ambition that would address the
  development problem (see Section 9, M&E Design, Implementation, and Utilization). In addition, the ICR
  acknowledged that the project did not sufficiently measure the impacts to greener growth and inclusive
  development of participant cities.



  Overall Efficacy Revision 1 Rating
  Substantial



 5. Efficiency
Economic Efficiency: At appraisal, cost benefit analysis evaluated the economic viability of the four urban road
rehabilitation and/or development sub-bprojects in the four cities, for the public transport investments in Panjin
City, and for the river channel rehabilitation and sewerage collection subproject in Suizhong County. Cost
effectiveness or least-cost analysis was applied to wastewater treatment and reclamation subproject in
Lingyuan City (PAD, paragraph 52). Direct and indirect economic benefits for roads were from savings in traffic
operating costs, reduced fuel consumption, reduced costs from daily maintenance, repair and administrative
expenditures; travel time saved for passengers using the newly built or rehabilitated roads; reduced working
capital from faster transport for vehicles carrying goods; reduced losses due to car accidents; and appreciation
of land values due to the convenience offered by improved roads and traffic.

At closing, for the roads subproject, economic benefits were derived from increased regional connectivity where
the project financed access roads from the city center to the high speed rail station. The EIRR for the road
projects ranged from 11.9 percent to 17.8 percent during appraisal, and at completion, 11.1 to 18.9 percent. The
Panjin public transit system subproject was at 15.3 percent at appraisal and slightly declined to 13.9 in EIRR at
closing. The Lingyuan urban road and wastewater reclamation registered and EIRR of 14.6 percent at appraisal
and improved to 19.3 at closing. The overall EIRR was 14.2 percent, higher than the social discount rate and
threshold of 8 percent established by the National Development and Reform Commission of China for its
construction projects (ICR, footnote 31).

Operational and Administrative Efficiency: There was an initial delay in implementation. After four years
of implementation only a third of the loan was disbursed. This was mainly due to lack of counterpart
financing from the participant cities (see Section 8 Bank Performance below) and a change in investment
priorities of the new leaders of Suizhong and Longchang district of Chaoyang. At that time, China was
experiencing an economic slowdown, and the amended budget laws affected the ability of the cities to borrow
for their counterpart funding needs. The estimated project cost of US$339.5 million at appraisal was revised to
US$216.3 million to reflect the withdrawal of the two cities from participating in the project. This reflected an
insufficient assessment of the risk in the availability of these funds at appraisal. The project was restructured by

                                                                                                       Page 11 of 19
       Independent Evaluation Group (IEG)                                 Implementation Completion Report (ICR) Review
       Liaoning Coastal Economic Zone Project (P126611)



2016 to amend the PDOs, updated the results framework, and reallocated resources among components. But
even after the restructuring, the indicators reflected in the revised results framework were not sufficiently clarified
(see Section 9, Monitoring and Evaluation below). As a result, the commitment for counterpart financing was
reduced from US$189.5 million to US$75.7 million. The project was implemented over 74 months to complete,
including a 12 month extension. At closing,the loan was 93 percent disbursed. According to the ICR, there was
a 20 percent savings due to competitive bidding (ICR, paragraph 62).

The efficiency of the project was rated modest even with high EIRRs because of the early setbacks
in operational efficiency and the ICR acknowledging that the project did not measure the impacts of the project
against greener growth and inclusive development (ICR, paragraph 49). The EIRRs used below refer to the
Lingyuan urban road development and wastewater reclamation component (ICR, Table 3 and Annex 3).


Efficiency Rating
Modest


a. If available, enter the Economic Rate of Return (ERR) and/or Financial Rate of Return (FRR) at appraisal
  and the re-estimated value at evaluation:
                                 Rate Available?              Point value (%)           *Coverage/Scope (%)
                                                                                        35.70
 Appraisal                                                   14.60
                                                                                         Not Applicable
                                                                                        40.60
 ICR Estimate                                                19.30
                                                                                         Not Applicable

* Refers to percent of total project cost for which ERR/FRR was calculated.

6. Outcome

A spilt rating was applied to the project because the 2016 level 1 restructuring revised the PDO. The outcome
was calculated below:

                                               Original    After Restructuring
 Relevance of Objective                        Substantial Substantial
 Efficacy
 Objective 1 – efficiency of urban transport   Modest
 Revised - to improve transport connectivity                Substantial
 Objective 2 – address water scarcity          Modest
 Revised – to reclaim wastewater                            Substantial
 Overall Efficacy                              Modest       Substantial
 Efficiency                                    Modest       Modest
 Outcome Rating                                MU           MS

                                                                                                        Page 12 of 19
     Independent Evaluation Group (IEG)                             Implementation Completion Report (ICR) Review
     Liaoning Coastal Economic Zone Project (P126611)



Outcome Value                               3            4
Disbursement Value (in US$M)                5.86         134.69
Share of disbursement to total (%)          3.9          96.1
Weighted Value of Outcome                   0.117        3.844
Total Value of Outcome                                   3.961 or 4.0
Overall Outcome Rating                                   MS




a. Outcome Rating
   Moderately Satisfactory


7. Risk to Development Outcome

The following pose risks to development outcome:

      Economic risks: The outbreak of the Covid 19 pandemic ravaging economies worldwide beginning
       in 2020 poses high risks for the sustainability of the outcome of this project. The disruptions caused
       by responding to the pandemic will likely pose bleak economic consequences locally, nationally, and
       globally. The province and the country will face massive competing priorities to restart economic
       activities that have been disrupted by actions adopted to slowdown the spread of the pandemic. This
       is an unprecedented situation facing every nation around the world and not just this project.
      Technological risks associated with unfunded future budgets for technological updates: Panjin
       adopted new technologies to optimize the use of public transport. The use of big data analyzed origin
       to destination points, riding modalities, and bus dispatching was optimized using the platform offered
       by internet networks to connect passengers with bus companies. Introducing new technologies
       normally require budgets for regularly updating such technologies. To mitigate this risk and further
       support the success of the Panjin urban public transport project, the Central government granted
       Panjin about US$3 million of green funds.
      Government commitment: Three of the four project city governments had no prior experience in
       implementing Bank financed project. Training and support improved their technical and managerial
       capacity in project management. Improved capacity and satisfaction with the interventions introduced
       led to improved statutory transport plans and comprehensive traffic asset management plans. These
       plans recognized the importance of O&M in meeting sustainability of investments. Training of staff
       and operators used international O&M best practices for facilities and equipment of constructed
       assets. Mitigating the risk of wavering commitment was signaled by the increase in annual road
       maintenance budgets from a baseline of 8 to 15 percent at closing. There is a risk that participating
       city governments may not continue to be committed to provide annual O&M budgets for these
       investments after closing.
      Financial risks: There remain risks to maintaining adequate tariffs to cover total costs including debt
       service by the wastewater treatment and water reclamation company. The Lingyuan Wastewater


                                                                                                  Page 13 of 19
     Independent Evaluation Group (IEG)                                 Implementation Completion Report (ICR) Review
     Liaoning Coastal Economic Zone Project (P126611)



       Treatment and Water Reclamation Company demonstrated its capacity to manage the company
       independently and become financially self-reliant. The financial and economic benefits generated
       from the project convinced the Lingyuan Government to construct a second wastewater treatment
       plant with water reclamation and recycling infrastructures to support its industrial water demands.




8. Assessment of Bank Performance

a. Quality-at-Entry
  The Bank team designed the project informed by lessons from previous Bank funded river basin and
  infrastructure operations in the province. Among the lessons learned were (i) consistency of the proposed
  activities with planned infrastructure networks; (ii) road designs appropriate to economic and population
  growth; (iii) training and technical assistance to accompany improved traffic management; (iv) ensuring
  the availability of counterpart funds; and (v) simplifying the institutional framework (PAD, paragraph 32).
  The Bank team assessed the procurement and financial management capacities of the implementing
  agencies and ensured that safeguard documents were developed and disclosed. The project was
  designed simply, with well defined components. However, a moderate shortcoming was reflected in the
  results framework as this lacked indicators to sufficiently measure the intended outcome (efficiency of
  transport services, water scarcity). Substantial risks were identified for capacity and governance and
  moderate risks for design, safeguards, and monitoring. To mitigate these risks, the Bank team provided
  experts in municipal engineering, wastewater management, economics, and safeguards compliance to
  assist at preparation. However, the Bank team did not assess the risks associated with the timely
  provision of counterpart funds, and a redirection of government priorities. There were moderate
  shortcomings in identification, preparation, or appraisal as evident in the acknowledged weaknesses in
  the indicators of the results framework, the inexperienced local staff to readily implement the project,
  and the differing availability of counterpart funds delayed implementation (see Quality of Supervision
  below).



  Quality-at-Entry Rating
  Moderately Satisfactory


b. Quality of supervision
 The Bank team focused on development impact evidenced by the 13 supervision missions over the 6 year
 implementation period. According to the ICR, these included site visits and support to the implementation
 units through high level discussions with the Liaoning Provincial Finance Department and the Liaoning
 Development & Reform Commission. The ICR noted that the Implementation Status and Results Reports
 were well documented and ratings were candid and fair. The project was delayed in the first 3 years of
 implementation due to: (i) lack of sufficient number and experienced staff at two local project management
 offices; (ii) lack of timely counterpart funds in Lingyuan City; and (iii) changes in local leadership, priorities,
 and policies. Participation was withdrawn, investments were dropped. The 2016 restructuring canceled the
 two subprojects, revised the PDOs, and amended the results framework accordingly. At this point,
 supervision and input processes could have been strengthened by the Bank team by (i) asking provincial

                                                                                                        Page 14 of 19
     Independent Evaluation Group (IEG)                              Implementation Completion Report (ICR) Review
     Liaoning Coastal Economic Zone Project (P126611)



 and local leaders to help resolve problems of counterpart financing, staffing problems and (ii) restructuring
 the project earlier than 2016 to solve emerging critical issues. In addition, the weaknesses in the results
 framework remained unaddressed. Project performance improved in the last two years of the project. The
 provincial government adopted institutional reform, assigned more experienced staff to its project
 management office and established better coordination between the provincial and the local implementing
 units. The Bank team reinforced these changes with improved and more frequent communication with the
 implementing agency and other stakeholders to proactively address problems such as technical design
 variations, land acquisition, and resettlement issues in a practical manner. With these moderate
 shortcomings in proactively identifying opportunities and resolving threats to achieving development
 outcomes, quality of supervision is rated moderately satisfactory.



  Quality of Supervision Rating
  Moderately Satisfactory

  Overall Bank Performance Rating
  Moderately Satisfactory


9. M&E Design, Implementation, & Utilization

a. M&E Design
 The original objectives were clearly stated. The theory of change documented how the key activities and
 outputs were expected to lead to outcomes. Output and outcome indicators were measurable and
 achievable within a specific time period and were reflected in the results framework. However, the selected
 indicators did not encompass all expected outcomes. The outcome indicators were only expressed as
 beneficiary satisfaction with the improved services under the project and did not measure the efficiency of
 transport services or the connectivity established by the project when the PDO was revised during the 2016
 restructuring (see Section 8. Bank Performance at Supervision above). In addition, indicators of the impact
 of the project to urban biodiversity, to improved urban planning, and reduced greenhouse gases were not
 in the results framework. The ICR reported these in the report footnotes. Intermediate results indicators and
 outputs adequately captured their contributions to project outcomes. Baselines, where relevant, and targets
 were available for all indicators. However, the second revised objective - to reclaim wastewater - did not
 clearly specify the ambition required to address the development problem. The M&E system was to be
 implemented by the local project management offices of the implementing agencies.



b. M&E Implementation
  The M&E system was implemented by the Liaoning Urban Construction and Renewal Project Office. The
  local project management offices of the participant cities reported on the indicators as reflected in the
  results framework and kept track of implementation progress, procurement, financial, and safeguards
  compliance. The primary outcome indicators, however, were not strengthened during implementation.
  Even after the May 2016 restructuring, the revised results framework suffered from the same
  weaknesses that featured in the original one. The Liaoning PMO provided additional data to the ICR to
  compensate for the weak indicators in the results framework. However, data provided were accepted with

                                                                                                    Page 15 of 19
     Independent Evaluation Group (IEG)                             Implementation Completion Report (ICR) Review
     Liaoning Coastal Economic Zone Project (P126611)



  caution on reliability (ICR, footnote 18). Beneficiary surveys were conducted with comparatively small
  number of sample sizes during the last two years of the project implementation (ICR, paragraph 79).
  There was no information regarding the continued use of the M&E functions in the participant cities after
  project closing.



c. M&E Utilization
  The Steering Committee and the PPMOs used the M&E data to determine the project outputs and
  outcomes. Results informed Lingyuan to invest in more water reclamation and recycling facilities while
  Panjin focused increased efforts in improving urban public transport and urban planning. Data from the
  M&E reports informed project restructuring, revising the objectives and updating the results framework.

  Overall, the above reflected a modest quality of M&E. The results framework had design weaknesses
  that were not addressed during implementation. The sample size of surveys were small and some data
  were noted as inaccurate.



  M&E Quality Rating
  Modest

10. Other Issues

a. Safeguards
   Environmental Safeguards: This project was assigned a Category B requiring a partial assessment. The
   following safeguards were triggered: OP 4.01 (Environmental Assessment) and OP 4.12 (Involuntary
   Resettlement). During project preparation, an Environmental Impact Assessment (EIA) and an
   Environmental Management Plan (EMP) were developed and disclosed as required. During the 2016
   restructuring, two new EIAs were prepared for two new subprojects (Kundian and Lingyuan). Local
   authorities approved these. The project's EMP was updated and disclosed. According to the ICR, the
   project complied with the EMP requirements. Local and provincial levels maintained satisfactory
   environmental management capacity. The six annual/semi-annual Environmental Monitoring
   reports indicated that environmental mitigation measures and environmental monitoring were implemented
   during subproject construction. There were no reports of environmental non compliance or occupational,
   health and safety incidents in any of the subprojects.

   Social Safeguards:The project triggered the Involuntary Resettlement policy (OP 4.12). Land acquisition
   and physical resettlement impacts across the participating cities/counties were anticipated. A consolidated
   Resettlement Action Plan (RAP) and site-specific RAPs, including land acquisition due diligence reports,
   were prepared for urban road improvement and wastewater treatment activities. Each city's project
   implementation unit established a resettlement office. All RAPs were disclosed locally on October 16, 2012
   and disclosed through the Bank’s InfoShop on December 14, 2012. During the 2018 restructuring, loan
   savings added activities in Kuandian but no RAP was required because the land for these new activities
   were acquired years earlier. A public consultation report was prepared for the new road rehabilitation
   activities in Lingyuan. The project complied with OP 4.12 as confirmed by a third-party external monitor (a
   Liaoning Social Academy consultant subsidiary). The project acquired a total of 760 cubic meter of

                                                                                                  Page 16 of 19
     Independent Evaluation Group (IEG)                               Implementation Completion Report (ICR) Review
     Liaoning Coastal Economic Zone Project (P126611)



   land affecting 1,843 persons or 492 households. 548 households were physically resettled and received
   appropriate compensation in a timely manner as confirmed by the Task Team in its June 3, 2020 email to
   IEG. Each project implementation unit operated a grievance redress mechanism. There were no reported
   appeal cases under the project. According to mission interviews, PIUs responded to questions from affected
   people through phone or site visit.




b. Fiduciary Compliance
   Financial Management: According to the ICR, the government complied with all financial management
   legal covenants. All audit reports, submitted on time, contained unqualified opinions and were without
   significant control weaknesses. In the first year, when Interim Unaudited Financial Reports (IUFRs) were
   submitted late, these issues were quickly resolved. The subsequent IUFRs were found acceptable. Delay
   in implementation was periodically addressed by on-the-job training and implementation support in
   financial management. Toward the last two years, financial management improved and disbursements
   accelerated (see Section 8 Assessment of Bank Performance, (b) Quality of Supervision above).

   Procurement: Procurement was conducted using agreed procedures. The following issues occurred
   during implementation: (i) a Lingyuan urban transport subproject experienced delays in contract award to
   resolve complaints from participating bidders; (ii) untimely releases of consultants' payments contributed to
   delayed/incomplete output delivery; (c) some shopping contracts showed unit prices higher than prevailing
   market prices; (iii) in a Lingyuan works contract, a contractor provided a performance security deposit that
   did not meet contract conditions. A post procurement review identified how these issues were resolved: (i)
   after payments due the consultants were released, work resumed; .(ii) the difference in unit prices were
   justified, documented, and accepted; and (iii) there was no need to replace the performance bank
   guarantee because the contracted work was completed.




c. Unintended impacts (Positive or Negative)
   ---

d. Other
   ---

11. Ratings
                                                                                  Reason for
Ratings                         ICR                     IEG
                                                                                  Disagreements/Comment
                                                                                  There were moderate
                                                                                  shortcomings in the project's
Outcome                         Satisfactory            Moderately Satisfactory
                                                                                  intended progress towards its'
                                                                                  outcomes.
                                Moderately
Bank Performance                                        Moderately Satisfactory
                                Satisfactory


                                                                                                    Page 17 of 19
    Independent Evaluation Group (IEG)                               Implementation Completion Report (ICR) Review
    Liaoning Coastal Economic Zone Project (P126611)



Quality of M&E                   Modest                Modest

Quality of ICR                   ---                   Substantial


12. Lessons

The operations offered five lessons and recommendations presented below that teams could
consider in similar future operations:

      Technical assistance interventions may benefit from early identification and adequate
         financing. In this project, just-in-time technical assistance in transport and asset
         management informed the Panjin Public Transport Authority how to deliver optimal bus
         services. Armed with a better appreciation for O&M needs in the investment life cycle,
         authorities increased the cities’ annual road maintenance budgets, from 8 to 15 percent at
         project closing. Interventions in transport services are best served by a menu of possible
         technical assistance needs and accompanied by sufficient budgetary resources to carry them
         out to coincide with opportunistic needs.
        Demonstrating cost effective solutions may boost local governments' resolve to
         champion support for green alternatives to conventional water supply. In this project, in
         Lingyuan, over 12 million cubic meter of reclaimed wastewater was sold to 6 large industries,
         equivalent to US$4.3 million in revenues for the local government and savings of around
         US$3.6 million in operating costs for the industries. Lingyuan decided to build a second
         wastewater treatment plant after the project closed. The local government experienced that
         using reclaimed wastewater mitigated urban water scarcity, improved efficiency in water use,
         reduced water pollution, minimized groundwater extraction, and improved water ecosystems.
         Their experience demonstrated that they could recover costs, facilitate savings for industries
         served by reclaimed waste water, and that together, the local government and industry could
         contribute to green growth. Other cities could follow their success in recycling municipal
         wastewater by adopting appropriate policies and enforceable regulations that allowed the
         government to recover their costs, generate revenues, and provide industries with savings.
        Critical assessment of the risks associated with the availability of counterpart funds
         may mitigate implementation challenges. In this project, two of the participant cities and
         one with a subcomponent critical to substantially achieving outcome dropped from the project
         because of the lack of access to counterpart funds. Critical assessment at appraisal may
         propose appropriate mitigating measures or identify alternative activities to replace project
         components that may drop to remain focused on achieving the project's objectives.
        Similarly sized cities may be encouraged to replicate the results of innovation in green
         mobility. In this project, the innovations adopted by Panjin City transformed its public
         transport systems through better routes, better services, and improved infrastructure. Less
         polluting buses also gave the national government a model for replication by similarly sized
         cities. These innovations in Panjin City demonstrated how other cities could pursue greener
         and more inclusive growth strategies.
        Improved surroundings may foster further improvements outside of the project. In this
         project, residents of Kundian saw that paved dirt roads around their homes allowed them
         increased access to major thoroughfares, signaling access to more developed urban areas
         but also improved their immediate surroundings. Residents because more conscious of


                                                                                                   Page 18 of 19
       Independent Evaluation Group (IEG)                            Implementation Completion Report (ICR) Review
       Liaoning Coastal Economic Zone Project (P126611)



         improving the appearance of the river near the roads. Residents reportedly discontinued
         dumping their waste in the river after seeing these improved roads. The Environment Bureau
         provided trash bins along the paved roads and made more frequent waste collection. The
         Water Resource Bureau provided proper embankment of the river outside of the project
         requirements. The improved surroundings introduced by the paved dirt roads led to
         improving the area surrounding the river beside those dirt roads.



13. Assessment Recommended?

  No

14. Comments on Quality of ICR

The ICR was concise while providing a detailed overview of the project. The report followed OPCS
guidelines. The narrative provided evidence to support the ratings, particularly with respect to the revised
objectives. The report was candid, discussing the shortcomings of the indicators used in the results framework,
the delays in early implementation, and the caution to the quality of evidence in reported outcomes. The
analysis in the report sufficiently linked outcomes to the evidence reported with plenty of anecdotal references
throughout. The stories provided in Annex 7 and the photos accompanying the project in Annex 8 were helpful
in demonstrating the outcomes of the project. The report was results oriented, providing story lines to support
the impact of the project interventions, such as those related to the Panjin public transport services. The
demonstration impact of generating revenues after recovering costs in support of using reclaimed wastewater
for industries was remarkable since the local government decided to continue with this green initiative post-
closing. Lessons were based on the evidence provided by the project interventions. However, the ICR did have
minor shortcomings including incomplete data in various places throughout the text. In addition, there was a
lack of information regarding compensation for displaced households. This meant IEG needed to ask the team
for the relevant missing information.



  a. Quality of ICR Rating
       Substantial




                                                                                                  Page 19 of 19