Document of The World Bank Report No: ICR2355 IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-38390) ON A CREDIT IN THE AMOUNT OF SDR 22.3 MILLION (US$32 MILLION EQUIVALENT) TO THE FEDERAL REPUBLIC OF NIGERIA FOR A MICRO, SMALL AND MEDIUM ENTERPRISE PROJECT June 26, 2012 Finance and Private Sector Development Western and Central Africa Africa Region CURRENCY EQUIVALENTS (Exchange Rate Effective as of May 14, 2012) Currency Unit = Nigerian Naira (NGN) US$ 1.00 = 155.3 NGN FISCAL YEAR January 1 – December 31 ABBREVIATIONS AND ACRONYMS ADR Alternative Dispute Resolution ATF Access to Finance BDS Business Development Services CAC Corporate Affairs Commission CB Credit Bureau CPS Country Partnership Strategy DCA Development Credit Agreement ELAN Equipment Leasing Association of Nigeria FIRS Federal Inland Revenue Service FM Financial Management GEL Grooming Enterprise Leadership Program ICR Implementation Completion Report IDA International Development Association IFC International Finance Corporation IRR Internal rate of return ISR Implementation Supervision Report M&E Monitoring and Evaluation MFI Micro-finance Institution MSME Micro, Small and Medium Enterprise NGO Non Government Organization NIPC Nigerian Investment Promotion Commission NPL Non-Performing Loan NPV Net present value PAD Project Appraisal Document PIU Project Implementation Unit PMU Project Management Unit PDO Project Development Objectives SIL Specific investment loan SME Small and Medium Scale Enterprises DA Development Agency of Nigeria TA Technical Assistance UNDP United Nations Development Program YouWiN Youth Enterprise with Innovation in Nigeria ii Vice President: Makhtar Diop Country Director: Marie Francoise Marie-Nelly Sector Manager: Paul Noumba Um Project Team Leader: Ismail Radwan ICR Team Leader: Andrej Popovic iii NIGERIA Micro, Small and Medium Enterprise CONTENTS Data Sheet A. Basic Information ....................................................................................................................... v B. Key Dates.................................................................................................................................... v C. Ratings Summary........................................................................................................................ v D. Sector and Theme Codes ........................................................................................................... vi E. Bank Staff .................................................................................................................................. vi F. Results Framework Analysis ..................................................................................................... vii G. Ratings of Project Performance in ISRs .................................................................................. xiii H. Restructuring (if any)................................................................................................................ xv I. Disbursement Profile................................................................................................................. xv 1. Project Context, Development Objectives and Design ....................................................... 1 2. Key Factors Affecting Implementation and Outcomes ....................................................... 5 3. Assessment of Outcomes ................................................................................................... 11 4. Assessment of Risk to Development Outcome ................................................................. 20 5. Assessment of Bank and Borrower Performance .............................................................. 21 6. Lessons learned ................................................................................................................. 25 7. Comments on Issues Raised by Borrower/Implementing Agencies/Partners ................... 27 Annex 1. Project Costs and Financing .......................................................................................... 28 Annex 2. Outputs by Component .................................................................................................. 29 Annex 3. Economic and Financial Analysis .................................................................................. 31 Annex 4. Bank Lending and Implementation Support Supervision Processes.............................. 35 Annex 5. Beneficiary Survey Results ............................................................................................ 37 Annex 6. Stakeholder Workshop Report and Results ................................................................... 41 Annex 7. Summary of Borrower‟s ICR and / or comments on Draft ICR .................................... 42 Annex 8. Comments of Co-financiers and Other Partners/Stakeholders ...................................... 47 Annex 9. List of Supporting Documents ....................................................................................... 48 Annex 10. List of sponsored events under each component of the Project ................................... 49 Nigeria Map................................................................................................................................... 54 iv A. Basic Information Nigeria Micro, Small Country: Nigeria Project Name: and Medium Enterprise Project Project ID: P083082 L/C/TF Number(s): IDA-38390 ICR Date: 05/15/2012 ICR Type: Core ICR Federal Government of Lending Instrument: SIL Borrower: Nigeria Original Total XDR 22.3 million Disbursed Amount: XDR 21.8 million Commitment: Revised Amount: - Environmental Category: C Implementing Agencies: Nigeria Investment Promotion Commission B. Key Dates Revised / Actual Process Date Process Original Date Date(s) Concept Review: 07/09/2003 Effectiveness: 06/15/2004 12/15/2004 Appraisal: 07/15/2003 Restructuring(s): N/A N/A Approval: 12/16/2003 Mid-term Review: 10/30/2006 05/19/2008 Closing: 06/30/2009 12/31/2011 C. Ratings Summary C.1 Performance Rating by ICR Outcomes: Moderately Satisfactory Risk to Development Outcome: Moderate Bank Performance: Moderately Satisfactory Borrower Performance: Moderately Satisfactory C.2 Detailed Ratings of Bank and Borrower Performance (by ICR) Bank Ratings Borrower Ratings Moderately Moderately Quality at Entry: Government: Satisfactory Unsatisfactory Moderately Implementing Moderately Quality of Supervision: Satisfactory Agency/Agencies: Satisfactory Overall Bank Moderately Overall Borrower Moderately Performance: Satisfactory Performance: Satisfactory v C.3 Quality at Entry and Implementation Performance Indicators Implementation QAG Assessments (if Indicators Rating Performance any) Potential Problem Project at Yes: Delayed Quality at Entry Moderately any time (Yes/No) Effectiveness (QEA): N/A Satisfactory Problem Project at any time Yes: Unsatisfactory Quality of Supervision Moderately (Yes/No): rating during 2005 (QSA): N/A Satisfactory DO rating before Satisfactory Closing/Inactive status: D. Sector and Theme Codes Original Actual Sector Code (as % of total Bank financing) Micro and SME Finance 60 60 Other Industry 15 15 Animal Production 13 13 Central government administration 7 7 Law and Justice 5 5 Theme Code (as % of total Bank financing) Regulation and competition policy 25 25 Micro, Small and Medium Enterprise support 25 25 Legal Institutions for a market economy 24 24 Judicial and other dispute resolution mechanisms 13 13 Other financial and private sector development 13 13 E. Bank Staff Positions At ICR At Approval Vice President: Makhtar Diop Callisto E. Madavo Country Director: Marie Francoise Marie-Nelly Mark D. Tomlinson Sector Manager: Paul Noumba Um Demba Ba Project Team Leader: Ismail Radwan Peter Mousley Andrej Popovic ICR Team Leader: Andrej Popovic ICR Primary Author: vi F. Results Framework Analysis Project Development Objectives The Micro, Small and Medium Enterprise (MSME) Project in Nigeria aimed to increase the performance and employment levels of MSMEs in selected non-oil industry sub-sectors and in three targeted states of the country. To achieve this, the project supported: (i) development of the capacity of local intermediaries to deliver financial and non-financial services to MSMEs; (ii) reduction of selected investment climate barriers that constrain MSME performance; and (iii) mobilization of increased private investments in MSMEs and intermediaries via (i) and (ii). Accordingly, the project had the following five components: access to finance, business development services, investment climate, public private sector partnership development, project management, monitoring and evaluation. The Project targeted three non-oil producing states (Lagos, Abia, and Kaduna), while part of the investment climate component also supported nationwide reforms. Two impact assessments were commissioned to gauge the direct impact on project beneficiaries of the two largest components - Access to Finance and Business Development Services. The assessments primarily focused on determining the impact that loans and business development services had on beneficiary MSMEs‟ sales and employment levels. To assess the impact of these components in terms of the PDO, sales revenue of beneficiary MSMEs (together with employment generated) was used as proxy indicators of their performance. While the PDO indicator was originally designed to capture MSME value added, in practice value added was difficult to calculate. More specifically, value-added is defined as the difference between sales revenues and purchased inputs. Given that the MSMEs did not use a standardized accounting approach for measuring these inputs, it was difficult to ensure reliable and comparable value added calculations. These data obstacles could be to some degree surmounted by tracking MSME sales which are generally a more reliable and easily estimated indicator of performance. Such data do not indicate profitability but combined with employment as a second indicator may better indicate value added. The achievement of the Project Development Objective was assessed primarily against the outcomes of the Access to Finance and Business Development Services components for three reasons. First, the intermediate outcome indicators for the Access to Finance and Business Development Services components were most closely related to the achievement of the PDO. Second, impact assessments were conducted for these components. Third, the Access to Finance and Business Development Services components were intended to account for two thirds of the project funding, i.e US$22 million of IDA funds versus US$6.2 million for the other two program components – Investment Climate and Public Private Sector Partnership Development. The actual disbursement to the BDS and Access to Finance components was in the end 47 percent of the total (US$15.3 million out of US$32.8 million) but they accounted for most of the project funding excluding implementation costs, versus US$8.9 million for the other two program components. vii (a) PDO Indicator(s) Original Target Formally Values (from Revised Actual Value Achieved at Completion Indicator Baseline Value approval Target or Target Years documents) Values Indicator 1: i) Growth of MSMEs‟ value-added in participating States and sectors i) Average monthly sales of MSMEs increased by 44% for microfinance Value borrowers and 84.4% for recipients of i) MSMEs‟ value quantitative or N/A business development services, while the added Qualitative) latter also experienced growth in employment of 41.7%1 Date achieved 15-Dec-2004 21-Feb-2008 and 09-July-2009 To assess progress towards the achievement of PDO, sales revenue of beneficiary MSMEs was used as a proxy to measure their performance, instead of originally planned value-added which proved difficult to calculate. This is justifiable as a first approximation on the basis that the aggregate value added percentage of output in the assisted MSMEs would not be subject to significant variation. The two independent impact assessment surveys on business development services (BDS) and Comments access to finance (ATF) components showed that MSMEs which benefitted from project (incl. % supported BDS increased employment levels by 41.7% (from 5.8 to 8.3) and expanded average achievement) monthly sales by 84.4% (from about N243,840.58 to N449,270.4) in the observed period. Sales of MSMEs which obtained loans from project supported MFI providers increased by 44% (by NGN 197,385) compared to pre-intervention time. While the surveys were conducted during the project (in 2008 and 2009), significant portion of planned grants supporting access to finance and BDS agenda had already been utilized. More detailed information about the findings of impact assessment studies can be found in Annex 5. (b) Intermediate Outcome Indicator(s) Original Target Values Formally Actual Value Achieved at Indicator Baseline Value (from approval Revised Target Completion or Target Years documents) Values Indicator 1: i) $15 million new private sector investments in microfinance institutions; 1 According to two independent studies: i) Impact Evaluation of Borrowers from Accion , Susu, and MIC Microfinance Banks , by Luba Shara, IFC with data collection conducted by: BDO OFO CONSULTING LTD, 2009; and ii) Impact Survey of MSME Beneficiares, by BDO OFO CONSULTING LTD, 2008. viii ii) At least two MFIs established; iii) Three commercial banks establish MSME downscaling programs iv) Portfolio at risk (arrears over 60 days) not greater than 5 percent after second year of operation for both MFIs and commercial banks v) Loan portfolio cumulative disbursed of $75 million each for MFIs and commercial banks i) $30.8 million (N 4.478 bn) of equity investment ii) 4 new MFIs established after some delay. i) $15 mn investments in iii) 1 commercial bank MFIs downscaled under the project There were no large ii) At least 2 MFIs; and at least 4 more followed Value scale self-sustainable iii) 3 commercial banks later without direct project quantitative or MFIs operating prior downscale; support but attributable iv) Qualitative) to project launch. iv) PAR at 60 days < PAR at 60 days for MFIs is 5% less than 2.5%2 and for the v) $ 75 mn loan portfolio commercial bank is 5.47% v) $49.6 mn for 4 MFIs (N 7.199bn) and $7.8 million (N 1.139 bn) for the commercial bank3 Date achieved 15-Dec-2004 30-Jun-2010 31-Dec-2011 This component surpassed its initial targets in regards to supporting creation of MFI sector in Nigeria although after some delay. While the initial target was to facilitate the creation of 2 MFIs, the project supported the establishment of 6 MFIs. Four of the six MFIs survived the 2008 crisis (i.e., Accion, Susu, Microcred and AB). Further, the original private sector investment targets were doubled for MFIs, and their PAR at 60 days was satisfactory. These achievements have to be regarded in the light of the length of time that the project required for completion, and the possibility that attributability weakened over time as other initiatives intervened. However the impact surveys provided good evidence of attribution. Comments The PAR of the microfinance portfolio of the commercial bank‟s (then Oceanic Bank) which (incl. % downscaled was higher than originally envisaged. The bank experienced difficulties as a result achievement) of the crisis and was recently bought by Ecobank. The new owner has however maintained the MSME focus of Oceanic Bank. The project was originally supposed to support downscaling of three commercial banks, but only Oceanic Bank expressed interest at the time. Hence, only one bank was included in the program. However, Oceanic Bank acted as a demonstrator and at least 4 additional banks (Stanbic, First Bank, Diamond, and UBA) downscaled their operations without direct project engagement. The outstanding loan portfolio for MFIs and the commercial bank is below the initial target, but the impact of the crisis needs to be taken in consideration when assessing this outcome. i) At least 1,000 MSMEs are supplied with BDS by participating BDS providers; Indicator 2: ii) Up to 4,000 new (including indirect) jobs in 3-5 supply chains in selected industries; 2 PAR at 60 days: AB 0.66%; Accion 2.3%; Microcred 0.29; Susu 1.84%, as reported by the four MFIs. 3 All financial indicators in this section were received directly from the four MFIs (Accion, Susu, Microcred and AB) and Oceanic Bank as of December 2011. ix i) Approximately 3,360 MSMEs received BDS, and a total of 20,161 MSME workers of which 17,358 were Value i) 1,000 MSMEs covered under the general quantitative or N/A ii) 4,000 new jobs BDS program and 2,803 in 4 Qualitative) supply chains ii) New direct jobs in supported supply chains estimated at around 1,1684 Date achieved 15-Dec-2004 31-Dec-2011 Based on the available data from the PMU records and project reports, this component exceeded the initial targets regarding the coverage of MSME beneficiaries of BDS services. While the project originally targeted 1,000 MSMEs, it facilitated BDS support to 20,161 microenterprise workers, or estimated 3,360 MSMEs (around 2,893 under general BDS and 467 under four value chains). The estimated number of MSMEs is based on the previously cited impact survey of BDS beneficiaries under the project, which stated that the target MSMEs on average employed around 6 people prior to the introduction of BDS. Comments The employment data for the supply chains could not be exactly measured due to lack of (incl. % accessible data. Since BDS targeted to specific supply chains are more intensive than general achievement) BDS the increase in employment per MSME attributable to the supply chain assistance would likely exceed that of general BDS. Since the BDS study concluded that recipients of BDS services under the project increased their employment levels from 5.8 to 8.3 employees - or on average adding 2.5 jobs per MSME - it could be estimated that the BDS services for 467 MSMEs in four value chains supported creation of 1,168 or more new jobs. To the extent that the total achieved is lower than the target of 4,000 jobs, one factor to be the financial crisis. In this case a counterfactual was estimated from the survey which suggested that the assisted MSMEs expanded employment significantly more than the sector as a whole. i) Under both the BDS Fund and industry supply chain, at least 20 BDS providers assisted by the Fund; ii) At least 75% cost recovery reached by participating BDS providers within a Indicator 3: specific time frame; iii) At least 20 products or services with sustained uptake improved or developed through support from the Fund i) 69 BDS providers (45 under general BDS Fund and 24 Value i) 20 BDS providers through 4 value chain quantitative or N/A ii) 75% cost recovery interventions) ii) 58% cost Qualitative) iii) 20 products/services recovery iii) 25 new products and services Date achieved 15-Dec-2004 30-Jun-2010 31-Dec-2011 Comments Based on the PMU records and project reports, the original targets were exceeded. The only 4 Estimate in line with the assumptions made based on the findings of Impact Survey of MSME Beneficiares, by BDO OFO CONSULTING LTD. Specifically, if estimated 467 beneficiary MSMEs under the value chain program added on average 2.5 jobs, new jobs could be estimated at 1,168. x (incl. % exception is the cost recovery which fell short of the target. The BDS providers reported achievement) difficulties in getting MSMEs to pay for BDS services, both due to lack of resources as well as perceptions that World Bank funded government programs should not require payments Also, some of the programs were implemented during and following the crisis, which put additional pressures on the MSME sector and could account for lower cost recovery. At the same time, according to the previously mentioned independent BDS study covering a sample of beneficiary MSMEs, 88% of respondents confirmed that they have actually paid for BDS. i) Secured transactions regime introduced in each target State ii) Regulatory framework updated for leasing industry; iii) Framework for credit bureau established; Indicator 4: iv) Alternative dispute resolution mechanisms developed and implemented in up to three States i) Law on Secured i)Secured transactions Transactions drafted, but not regime introduced in each adopted ii) This activity was i) No framework for target State dropped, as progress was secured transactions ii)Regulatory framework reportedly made by ELAN5 ii) No framework for updated for leasing and Central Bank of Nigeria Value leasing industry; iii) Credit Bureau (CB) quantitative or iii) No credit bureau iii)Framework for credit regulations in place and 3 new Qualitative) law bureau established; CBs operational iv) ADR iv) No Alternative iv)Alternative dispute Mechanism set up - 2 new Dispute Resolution resolution mechanisms multi-door court houses (ADR) developed and established in Kaduna and implemented in up to Abia States, while the existing three States ADR centers in Lagos received project support Date achieved 15-Dec-2004 31-Dec-2011 At least 50% of the expected results under this indicator were achieved and were attributable to the project. This may be regarded as a fair result in challenging circumstances. ADR mechanisms were established, credit bureau regulations were approved, and three credit Comments bureaus were established. The Law on Secured Transactions was not approved, but the Central (incl. % Bank has included it in the package of laws that it will submit for Parliamentary approval in achievement) 2012. The leasing law has been drafted and submitted to Parliament for approval. However, this activity was dropped during project implementation, as the Equipment Leasing Association of Nigeria (ELAN) and the Central Bank of Nigeria focused on it and did not require project support. i) Streamlined procedures; Integrated tax and business registration process ii) Reduction in transaction costs for company registration with Corporate Affairs Indicator 5: Commission (including a reduction in the number of steps required to register a business from 9 to 6 and reduction in time required by 30%) Value i) No integration of i)Streamlined procedures; i) Initial report on integrating quantitative or tax and business Integrated tax and registration process was 5 Equipment Leasing Association of Nigeria. xi Qualitative) registration process. business registration prepared and disseminated, process workshop held, and hardware ii) 44 days and 10 ii) Reduction in delivered; however, procedures to transaction costs for integration process is still register a business in company registration work in progress. ii) Based on Nigeria according to with Corporate Affairs Nigeria Sub-national Doing Doing Business Commission (including a Business 2010 results partial 2004 report. reduction in the number reduction in transaction costs of steps required to observed both nationally and No sub-national register a business from 9 in target states as summarized data were available to 6 and reduction in time below, though this can only be at the time. required by 30%) partially attributed to Project (33 days and 9 procedures for Abia; 31 days and 9 procedures for Kaduna; and 31 days and 8 procedures for Lagos) Date achieved 15-Dec-2004 31-Dec-2011 The project supported the development of streamlined and common business registration procedures between the Corporate Affairs Commission (CAC) and Federal Inland Revenue Service (FIRS). These procedures were adopted by the relevant entities and the agreement was formalized in a memorandum of Understanding between the CAC, FIRS, and NIPC. The necessary hardware was also funded under the project. However, the physical link between the databases of CAC and FIRS was not finalized by the closing date and is expected to be Comments completed in the Summer of 2012. The process of business registration in Nigeria improved (incl. % since Doing Business 2004 Report, from 44 days and 10 procedures to 34 and 8 respectively achievement) according to DB 2012. Also, according to Nigeria sub-national Doing Business 2010 results, the same indicators for target states are: 33 days and 9 procedures for Abia; 31 days and 9 procedures for Kaduna; and 31 days and 8 procedures for Lagos. However, while momentum for improving procedures was created by the project, given that the intended streamlining of the business registration process has not been completed yet, these improvements may only be partially attributed to project activities. Public-Private Sector Partnership Development i) At least 3 MSME competitiveness conferences held (annual) and reports of proceedings produced and disseminated; Indicator 6: ii) Associated roundtable discussions held between Government and private sector to disseminate lessons , best practices, success stories from the project and establish dialogue to improve policies and programs targeted at MSMEs i) 1 MSME conference held i) at least 3 MSME Value ii) 18 various events conferences quantitative or N/A supporting public private ii) Roundtable Qualitative) dialogue held, including discussions roundtable discussions Date achieved 15-Dec-2004 31-Dec-2011 The purpose of this component was to develop public private dialogue as a precondition for the Comments successful execution of private public partnerships in policy formulation and in actual (incl. % development projects. The component supported preparation of one MSME Competitiveness achievement) Report as well as a national conference on competitiveness which was organized in September 2011. In addition, according to the PMU‟s Completion Report, the following 18 events xii supporting public private dialogue were held: three roundtables for MSME financial service providers, two stakeholder forums on private credit bureaus, one consultative forum on commercial bank downscaling, two roundtables on investment climate, two knowledge sharing alternative dispute resolution events, co-sponsoring of three annual Nigerian Economic Summits, three BDS fairs, and two stakeholder forums on rice and tourism sectors. i) Appropriate monitoring and evaluation system established to measure the project‟s Indicator 7: impact on participating States Value i) M&E system in place, i) Appropriate M&E quantitative or N/A though with some system in place Qualitative) shortcomings Date achieved 15-Dec-2004 The results framework included outcomes which extend beyond the immediate impact on project beneficiaries and not all intermediate indicators were closely related to the achievement of the PDO. However, the team addressed this by commissioning two impact assessments in 2008 and 2009 Comments to gauge the impact of the two largest components - Access to Finance and BDS – both of (incl. % which had a direct impact on PDO. The assessments were conducted at a time when a achievement) significant portion of the planned grant funding for these components had been disbursed. As explained, the actual total disbursements to these components turned out in the end to be smaller as a percentage of the total project cost. Consequently, the ICR provides a summary review below of the costs and benefits of the other components. Detailed implementation reports were regularly prepared. G. Ratings of Project Performance in ISRs No. Date ISR DO IP Actual Archived Disbursements (USD Millions) 1 4/30/2004 Satisfactory Satisfactory 0 2 7/13/2004 Satisfactory Satisfactory 0 3 12/14/2004 Satisfactory Satisfactory 0 4 12/15/2004 Satisfactory Satisfactory 0 5 6/24/2005 Moderately Unsatisfactory 1.12 Satisfactory 6 12/20/2005 Unsatisfactory Unsatisfactory 1.12 7 4/26/2006 Moderately Moderately 1.92 Satisfactory Unsatisfactory Moderately Moderately 8 6/29/2006 Satisfactory Satisfactory 2.83 9 12/20/2006 Moderately Moderately 3.7 Satisfactory Satisfactory xiii Moderately Moderately 10 6/27/2007 Satisfactory Satisfactory 5.46 11 12/28/2007 Moderately Moderately 7.18 Satisfactory Satisfactory 12 6/18/2008 Satisfactory Satisfactory 10.73 13 12/23/2008 Satisfactory Satisfactory 13.34 14 6/29/2009 Satisfactory Satisfactory 16.71 15 12/20/2009 Moderately Satisfactory 19.02 Satisfactory 16 5/31/2010 Satisfactory Satisfactory 21.08 17 6/28/2010 Satisfactory Satisfactory 21.32 Moderately Moderately 18 3/24/2011 Satisfactory Satisfactory 25.36 19 11/14/2011 Satisfactory Satisfactory 29.12 20 n/a n/a n/a 33.37 xiv H. Restructuring (if any) Project restructuring was done only to request project extensions and amend the Development Credit Agreement. However, there was no restructuring of project activities or objectives. Although the implementation performance dipped to less than satisfactory in 2005, it was not considered that formal restructuring was necessary because the original composition of assistance components remained valid and the main obstacles were in terms of implementation bottlenecks (including an FM review) rather than the content of the assistance program as such. I. Disbursement Profile Disbursement under the MSME project was unexpectedly slow. This was caused by a number of factors (see below) some of which were outside the control of the project. This situation led to the unsatisfactory rating of 2005. However during the period of project extension (2010 to 2012) the disbursement lag was reduced to zero and funds were finally 98% disbursed. xv 1. Project Context, Development Objectives and Design 1.1 Context at Appraisal 1. With a GDP of about US$40 billion at the time of project preparation, Nigeria was Africa‟s second largest economy, endowed with rich natural resources, most notably oil. According to the Project Appraisal Document (PAD), Nigeria‟s economy however displayed a significant dualism between oil and non-oil producing sectors, with the middle-income oil producing economy of about five million people having a per capita income of around US$2,200. At the same time, 70 percent of its population lived below the poverty line with an average per capita income of US$200. Further, based on the United Nation‟s Development Program‟s (UNDP) Human Development Index, Nigeria ranked low in the human development category – 151st out of 174 countries for which the UNDP had data, and 22nd out of 45 African countries. 2. In February 2002, the Joint Interim Strategy Update put private sector led growth at the core of the Bank program. The strategy had three pillars: (i) improving economic governance; (ii) creating the conditions for rapid private sector led poverty-reducing growth, particularly in the non-oil economy; and (iii) enabling local communities to take charge of their own development. Assistance to achieve the development objectives under the first and third pillars were to be provided through a combination of lending and non-lending services including those for economic management capacity building, sectoral programs on education, health, energy, water and transport, and community driven projects. 3. The MSME Project aimed at supporting growth potential of MSMEs. Project components included: access to finance, business development services, investment climate, public private sector partnership development, project management, monitoring and evaluation. The Project targeted three non-oil producing states (Lagos, Abia, and Kaduna), except for part of investment climate component which also supported nationwide reforms. The MSME project was complemented by the IDA Privatization Support Project, which was successfully implemented and closed in December 2009. 4. The MSME Project was part of the joint IDA-IFC MSME Development Pilot Program for Africa. The Program aimed at unlocking private sector growth in selected African countries by supporting MSMEs, which taken together account for the vast majority of private sector activities in most of the continent. Projects under this Pilot Program were meant to differ from previous private sector development projects in three ways: (i) they would address MSME constraints in a holistic manner, i.e., by tackling regulatory obstacles, as well as facilitating access to finance and the creation of a market for business development services; (ii) they would rely on a range of private sector partners for implementation, (iii) they would provide a framework for collaboration between the Bank and IFC. The initial pilot included the following seven countries: Ghana, Kenya, Madagascar, Mali, Nigeria, Tanzania and Uganda. The program was later extended outside the Africa region to Cambodia and Papua New Guinea. 1.2 Original Project Development Objectives (PDO) and Key Indicators 5. The PDO aimed to increase the performance and employment levels of MSMEs in selected non-oil industry sub-sectors and in three targeted states of the country. To achieve the PDOs the project supported three sets of interventions (i) development and strengthening of the capacity of local intermediaries to deliver financial and non-financial services to MSMEs; (ii) 1 reduction of selected investment climate barriers that constrain MSME performance; and (iii) mobilization of increased private investments in MSMEs and intermediaries via (i) and (ii). Key performance indicators included the following: PDO Indicator: i) Growth of MSMEs‟ value-added in participating States and sectors Intermediate Outcome Indicators: Component 1- Access to Finance: i) US$15 million new private sector investments in microfinance institutions; ii) At least two MFIs established; iii) Three commercial banks establish MSME downscaling programs; iv) Portfolio at risk (arrears over 60 days) not greater than five percent after the second year of operation for both MFIs and commercial banks; and v) Loan portfolio cumulative disbursed of US$75 million each for MFIs and commercial banks. Component 2 – Business Development Services (BDS): i) At least 1,000 MSMEs are supplied with BDS by participating BDS providers; ii) Up to 4,000 new (including indirect) jobs in 3-5 supply chains in selected industries; iii) Under both the BDS Fund and industry supply chain, at least 20 BDS providers assisted by the Fund; iv) At least 75 percent cost recovery reached by participating BDS providers within a specific time frame; and v) At least 20 products or services with sustained uptake improved or developed through support from the Fund. Component 3 – Investment Climate: i) Secured transactions regime introduced in each target State; ii) Regulatory framework updated for leasing industry; iii) Framework for credit bureau established; iv) Alternative dispute resolution mechanisms developed and implemented in up to three States; and v) Streamlined procedures; integrated tax and business registration process Reduction in transaction costs for company registration with Corporate Affairs Commission (including a reduction in the number of steps required to register a business from 9 to 6 and reduction in time required by 30%). Component 4 - Public-Private Sector Partnership Development: i) At least three MSME competitiveness conferences held (annual) and reports of proceedings produced and disseminated; and ii) Associated roundtable discussions held between Government and private sector to disseminate lessons, best practices, success stories from the project and establish dialogue to improve policies and programs targeted at MSMEs. Component 5 – Project Management, Monitoring and Evaluation - Project Impact Assessment: i) Appropriate monitoring and evaluation systems established to measure project‟s impact in participating States. 2 1.3 Revised PDO and Key Indicators, and reasons/justification 6. The PDO and key outcome indicators remained unchanged during the project as it was considered that they were appropriate, and that the targets were by and large feasible, if challenging in some cases. 1.4 Main Beneficiaries 7. The project supported MSMEs growth by: (i) facilitating increased access to finance; (ii) improving business development services; (iii) enhancing the investment climate; and (iv) supporting the dialogue between the public and private sector to facilitate MSME development. The main targeted beneficiaries of the project included: (i) BDS providers which received grants to improve and expand their services to MSMEs; (ii) financial institutions which received grants to establish microfinance operations and/or downscale; (iii) supported MSMEs with better access to finance, business development services, and improved investment climate; and (iv) the government with better regulatory framework in selected areas, improved capacity, and expected healthier fiscal position resulting from the growth of private sector. 1.5 Original Components 8. The project included five components: (i) access to finance; (ii) business development services; (iii) investment climate; (iv) public-private sector partnership development; and (v) project management, monitoring and evaluation. 9. Component 1: Access to Finance (IDA US$10 million, Other US$23 million). This component aimed to improve access to financial services available to MSMEs. This objective was to be achieved by using grants to support the creation or strengthening the capacity of microfinance institutions and banks to serve the MSME segment. The component envisaged support for the following activities: i) establishment of local commercially viable, regulated, micro-finance companies; ii) technical skills transfer programs that incorporate new systems and lending methodologies to support commercial banks to expand their loan portfolio to MSMEs; iii) support for the establishment of private credit bureaus over an initial set-up period until a bureau establishes a revenue flow from its services; and iv) specialized technical assistance to selected firms providing long-term leasing services. 10. Component 2: Business Development Services (IDA US$12 million, Other US$4 million). This component intended to develop the market for business development services (BDS) by supporting qualifying intermediaries via grants and technical assistance to respond to unmet MSME demand for BDS. The component focused in the three target States. Two types of TA and trainings were funded under this component: (i) TA and training on specific value chains; and (ii) TA and trainings on more general business functions (i.e, accounting, marketing, management etc). In addition, towards the very end of the project, support was provided for implementation of two special programs – the Grooming Enterprise Leadership Program (GEL) and the Youth Enterprise with Innovation in Nigeria (YouWiN). These two programs were not captured under impact assessment surveys, because they were included in the project only in 2011. 11. Component 3: Investment Climate (IDA US$5.1 million, Other US$0.7 million). This component was intended to support the Government of Nigeria in: (i) reforming the business registration process, including upgrading and decentralizing the information systems of the Corporate Affairs Commission (CAC); (ii) introducing and strengthening the alternative dispute 3 resolution (ADR) in three states; (iii) enhancing the existing leasing framework by providing technical assistance for developing the laws and regulations together with a training program to ensure full understanding by relevant stakeholders; (iv) supporting the required legal reforms for the establishment of credit bureaus; and (v) introducing a new secured transaction system including the laws and regulations, hardware, and software system that could be used for an integrated registration covering various forms of moveable collateral. 12. Component 4: Public-Private Sector Partnership Development (IDA US$1 million). Resources were allocated to fund learning events (study tours, trainings, conferences) and reports to facilitate dialogue between the public and private sector, and thus support reforms for MSME development. Key beneficiary institutions under this component were the Small and Medium Scale Enterprises Development Agency of Nigeria (SMEDAN) and the Nigerian Investment Promotion Commission (NIPC). SMEDAN would take the lead on a dialogue with business associations, private sector and government stakeholders with a view to preparing MSME competitiveness report on an annual basis utilizing the cost of doing business surveys and other evaluations generated by the project and research undertaken by SMEDAN itself. 13. Component 5: Project Management, Monitoring and Evaluation (IDA US$2.3 million) Due to limited government capacity to implement the project, a decision was made to select a private sector entity on a competitive basis, and entrust it with the management of the project, with the exception of disbursement and FM functions which were performed by the government run PIU. This component funded the operational cost of the PMU, as well as equipment and other financial, audit, training and consultant assignments for both the PMU and PIU. 1.6 Revised Components 14. The program components remained unchanged throughout the project. However, the scope of some activities was broadened to respond to client demand and country needs. For example, during implementation two new BDS programs were added: (i) Grooming Enterprise Leadership Program - GEL to provide training to SMEs in 24 locations across the country; and (ii) Youth Enterprise with Innovation in Nigeria - YouWiN to support business plan competition for young entrepreneurs. These programs were requested by the Ministry of Finance to support its jobs and growth agenda. 1.7 Other Significant Changes 15. The project was extended from the originally scheduled closing date of June 30, 2009 to December 31, 2011 due to implementation delays. The project was extended three times. An initial request was made to extend the closing date from June 30, 2009 to June 30, 2010 to ensure completion of planned activities which were behind schedule due to delayed effectiveness. The second extension moved the closing date to June 20, 2011 to enable the team to conclude several activities which were already in advanced stages (i.e., $900,000 worth of matching grants under the three value chains). A final six month extension request was made to complete the remaining project activities, including Grooming Enterprise Leadership (GEL) program, which was included in the project in 2011. The reasons for these delays are further set out below, section 2.2. 4 2. Key Factors Affecting Implementation and Outcomes 2.1 Project Preparation, Design, and Quality at Entry 16. The Nigeria MSME Project was one of seven joint IDA/IFC MSME pilot projects for Africa designed to support MSME growth in a comprehensive fashion. Specifically, the projects under this IDA-IFC program included: (i) access to financial services; (ii) business development services and entrepreneurship development, including strengthening inter-firm linkages (both domestic and foreign) and information access; and (iii) improvements in the business environment for MSMEs, including strengthening business associations. An additional objective of the pilot program was to leverage IDA and IFC resources to support project implementation. As a result, the project was designed based on the framework for pilot programs and tailored to respond to specific MSME needs in Nigeria. 17. The project objective was relevant to the country‟s goals and development priorities. This was reflected in the IDA‟s Interim Strategy Update from February 2002, highlighted in analytical work which preceded preparation, and confirmed in FY10-13 CPS and recent analytical work6. 18. The project design was based on considerable Economic and Sector Work 7 which revealed that the non-oil private sector in Nigeria faced major development challenges. The findings revealed that Nigerian private sector firms suffered from high costs and lack of competitiveness. Following a due diligence process, the Project team identified the following MSME issues in Nigeria: (i) poor access to finance; (ii) lack of access to business development services; (iii) constraint in the investment climate; and (iv) limitations to public-private sector dialogue. As a result, four corresponding project components were designed. 19. The project focused on three pilot states of Lagos, Abia, and Kaduna. The PAD did not provide detailed information about the selection process of targeted states. It is understood however, that the geographic focus areas were previously agreed between the Government of Nigeria and the World Bank. The three pilot states were selected to ensure geographic and socio- economic diversity, with Lagos being the commercial capital of the country, Abia an underdeveloped and poor, and Kaduna as an industrial center in northern Nigeria. 20. In addition, the business development services component focused on four target industries, based on a set of selection criteria identified in the PAD. The criteria included: high growth potential; size of the industry (contribution to GDP) and geographical distribution; number of MSMEs in the value chain and MSME employment; potential for local MSMEs to 6 Financing SMEs in Nigeria By Gunhild Berg, Michael Fuchs, Leonardo Iacovone, Thomas Jaeggi, Andrew Lovegrov, and Carolina Villegas Sanchez, 2012. 7 Bank Staff Assessments: 1) Results of the Nigeria Firm Survey, Regional Program on Enterprise Development (RPED Paper #118, April 2002), World Bank. 2) The Implementation Completion Report (ICR) on the World Bank Small and Medium Enterprise Development Project (Loan 2995-UNI), Report #16811, June 1997. 3) Africa Program Framework Paper for a Joint IDA/IFC Micro, Small and Medium Enterprise Development Pilot Program for Africa, World Bank JIFC (considered by the Board of Executive Directors, June 19,2003). 4) SME mapping exercise undertaken in parallel with a survey on Nigerian firms conducted under the WED of the World Bank, October 2001. 5) “Joining the Race for Non-Oil Foreign Investment, �? conducted by the Foreign Investment Advisory Services; 6) “Direct Support to Private Firms - Evidence of Effectiveness�?, G. Batra and S. Mahmood, 2001 and „YDA ‟s Partnership for Poverty Reduction (FY94-FY00): An Independent Evaluation �?, OED, 200 1 , pp 31-33. Other: 1) “Evaluation of the Mekong Project Development Facility �?, Nexus and Assocs., June, 2002 with important insights into the best design parameters for BDS provider capacity building. 2) Guiding Principles for Donor Intervention Business Development Services for Small Enterprises: Guiding Principles for Donor Intervention, Committee of Donor Agencies for Small Enterprise Development, February 2001. 5 capture more value added; the potential for technical assistance to help MSMEs achieve the above goal; and, commitment of key industry stakeholders. In this regard, catfish farming was identified in the PAD as the first target industry, while the selection of other industries was to be made during project implementation and based on assessment of their potential. Eventually, rice, palm oil, and tourism sectors were included in the project. 21. The project may have been too ambitious in terms of the number of planned activities and their scope, given its pilot nature and the challenging implementation environment. The project design, including both IDA and IFC inputs, was consciously attempting a comprehensive approach to MSME development in order to leverage the interrelationships of policy, institution building, finance and technical upgrading, rather than a piecemeal approach. The team wanted to ensure implementation of a reform agenda to address obstacles and nurture MSME development. However, this approach came up against the inevitable problem of a complex management structure, and it proved difficult in practice. Implementation rested on a variety of institutions and required a high level of coordination which was difficult to ensure in a complex implementing environment 2.2 Implementation 22. The commencement of implementation experienced significant delays and the project lagged behind the original schedule ever since. This project faced a difficult implementation environment which was to a significant extent outside the control of the project management. The delay factors which impacted implementation and outcomes, included the following: (i) delayed effectiveness; (ii) delays with the establishment of the Project Management Unit (PMU); (iii) limited capacity of the government Project Implementation Unit (PIU) in implementing World Bank financial management guidelines and related FM in-depth review; (iv) PMU‟s limited exposure to World Bank‟s procurement procedures; (v) low interest from vendors to bid for project funded activities; (vi) an amendment to the Development Credit Agreement due to lack of counterpart funding; (vii) delayed approval of regulatory framework for MFIs; and (viii) the security situation in Abia State. Below is a brief summary outlining each of the highlighted factors. 23. The Project was declared effective six months after the originally planned effectiveness target date of June 2004, which delayed commencement of project activities. Amongst other issues, the conditions of effectiveness included signing of management contract between NIPC and the firm appointed for project execution services, which required completion of procurement for the private PMU. Given that the procurement process took an extended period of time, due to low technical capacity, the effectiveness was delayed until December 2004. 24. The establishment of the privately managed Project Management Unit (PMU) took nearly two years to complete. The PMU became fully operational only in June of 2005. This was largely due to Nigerian Investment Promotion Commission‟s (NIPC) insufficient procurement capacity at the time. Following a lengthy international procurement process, the contract with the winning bidder - Nathan Associates – was signed in November 2004. However, the staffing of the PMU took another six months and was completed only in June 2005, when the PMU finally became fully operational. 25. Project implementation was temporarily delayed due to the PIU‟s lack of full compliance with World Bank‟s FM guidelines, which triggered an in-depth FM review. The World Bank‟s FM supervision mission in 2007 and 2008 flagged non-compliance with some of the FM guidelines, such as travel without proper recording of receipts, lack of purchase orders, and so 6 forth. As the project failed to comply with required financial management procedures by the time of expected extension in 2009, it was subject to the World Bank‟s FM review process. The FM review included several stages and involved a dynamic interaction between the PIU and the Bank‟s FM team. Specifically, as the PIU had to respond to FM team‟s inquiries with additional clarifications and/or documents in each of the stages of the review, the whole process took approximately four months to complete. According to the project team, during this period some contractors engaged to support rice and palm oil value chains stopped working temporarily given that their payments were not processed in a timely fashion. While the World Bank did not impose an explicit disbursement ban during this period, withdrawal applications could not be prepared promptly until the project financial records were sorted out internally. Following completion of FM review, the project received a clean bill of health and implementation was put back on track. 26. Initially, the PMU had limited familiarity with the Bank procurement guidelines. At the outset, the PMU staff responsible for procurement did not have adequate knowledge of World Bank procedures. This translated into slower than expected implementation. The Bank‟s procurement team reported that it took nearly two years until sufficient capacity was created with the assistance of World Bank procurement staff who delivered training to the PMU. 27. International vendors exhibited low initial interest to bid for project work. Initially the interest to bid for project work in Nigeria was low and a number of tenders received only limited response. In some cases this led to retendering, which caused implementation delays. This particularly affected the implementation of the rice and catfish value chains. This issue was not specifically related to this project as it also affected other projects being implemented in Nigeria over this period. 28. Project implementation was slowed down by lack of counterpart funding. This issue was eventually addressed with the amendment of the Development Credit Agreement (DCA). In 2005, the DCA had to be amended because the counterpart funding from the government was not made available regularly. Initially, the DCA envisaged a split of 80 percent IDA and 20 percent counterpart funding, but as the counterpart funds were not readily available the DCA was amended to include 100 percent IDA financing in order to facilitate implementation. 29. Slow approval of the regulatory framework for MFIs delayed implementation of the access to finance component. Component 1 – Access to Finance - could not commence until the regulatory framework for microfinance, which would allow for licensing of microfinance banks, was put in place. While the Project provided support to the development of regulatory framework for microfinance, the Central Bank of Nigeria issued its Microfinance Guidelines (a prerequisite for implementation), only in December 2005, and proceeded with implementation in 2006. Thus real activity in the MFI sector only started in 2006, and the first MFI – Accion - opened in July 2007, while the last one – Microcred - was established in early 2010. 30. The deterioration of the security situation in Abia State delayed the project implementation in the state. The challenging security situation in one of the project focus areas between 2008-2011, including high incidence of violent crime and kidnappings, negatively impacted project implementation. Project beneficiaries were affected by a risky environment, and the World Bank project team could not supervise implementation in the field due to security concerns. 31. The global financial crisis of 2008 severely affected the Nigerian financial sector. In addition to the exceptionally difficult implementation environment, the project had to contend with the global financial crisis at about mid-term which adversely impacted on the fulfillment of 7 some components and in particular access to finance. Nevertheless, four of the six MFIs supported by the project withstood the crisis. Starting from November 2009 the banks‟ balance sheets were severely affected by the drastic drop in oil prices (from $147 to $39 per barrel) and a considerable depreciation of the Naira (from N117 to N190 to the US$ before stabilizing at around N150)8. Further, the volume of non-performing loans (NPLs) started to rise following the crash of the Nigeria Stock Exchange (NSE) which, by 2008, was dominated by banks accounting for around 70 percent of market capitalization. Project implementation was thus unavoidably affected. Out of 6 MFIs established with the project support, two failed (IMFB and MIC). In addition, the one commercial bank – Oceanic Bank - which successfully downscaled as a result of project support, experienced difficulties during the crisis and was acquired by another commercial bank (Ecobank), which however maintained its MSME focus. 32. Some of the above cited implementation delays and issues may have warranted a project restructuring. Restructuring may have been an effective measure to address the challenges that the project experienced. This was considered at various times. However, it was decided to maintain the integrity of the project as it was first designed, because it was considered that the issues were associated with delay factors rather than inability to fulfill component objectives as such. The delays in fact affected all components, ranging from funding of BDS providers to promulgation of MFI regulations so restructuring was not indicated. However, in practice there was a reallocation of funds introduced at the closing phase to ensure fulfillment of targets. 2.3 Monitoring and Evaluation, M&E Design, Implementation and Utilization 33. The results framework was designed to measure outcomes which extend beyond the immediate impact on project beneficiaries. Not uncommon for projects designed 10 years ago, both the PDO and PDO indicator lacked specificity and would have benefitted from a more direct causal link with the supported activities. The PDO aimed to achieve the increase in the performance and employment levels of MSMEs in participating states and sectors . Given that the project focused on relatively limited number of beneficiaries, in line with the available resources, and that it was designed to reach to MSMEs via intermediaries (i.e., BDS providers, microfinance banks, etc.) the PDO was probably too ambitious. Similarly, the PDO indicator aimed to measure MSMEs value-added in participating states and sectors, which is not necessarily directly attributable to interventions funded under the project. In retrospect intermediate outcome targets could have been included for capacity building activities within the MFIs and within the BDS suppliers, as well as final outcome or impact targets in terms of performance improvement in the MSMEs themselves. 34. Two impact assessments were commissioned to gauge direct impact on project beneficiaries for the two largest planned components - access to finance and business development services. In keeping with the outcome objectives these assessments focused primarily on determining the impact that MFI finance and business development services had on beneficiary MSMEs‟ sales and employment levels. However, ultimately the original BDS component and the ATF component comprised a substantially lower proportion of project expenditure than originally planned. It is important to note that the grants under these components were performance based and were disbursed only upon meeting of certain targets. In 8 Making Finance Work for Nigeria, 2009 8 regards to ATF component, some of the initially approved grants could not be fully disbursed given that certain grantees could not meet the performance targets (i.e. IMFB and MIC lost their licenses to operate as microfinance banks). As far as BDS is concerned, the number of qualifying applicants was lower than expected, and moreover these grants were also based on meeting performance targets which in some cases could not be met. At the same time, the Investment Climate and Public Private Sector Partnership Development components ended up comprising a relatively larger share of project expenditures than originally planned. A review of achievements under these two components is provided below in section 3.5. 35. To assess progress towards the achievement of PDO, sales revenue of beneficiary MSMEs was used as a proxy to measure their performance. While the PDO indicator was originally designed to capture MSME value added as a means of measuring performance, in practice it was difficult to calculate. More specifically, value-added is defined as the difference between sales revenues and purchased inputs. Because the MSMEs surveyed did not use a standardized accounting approach for measuring these inputs, it was difficult to obtain reliable and comparable value added calculations which would have required a detailed survey of MSME operations. This data obstacle was addressed by tracking MSME sales as a more reliable indicator even though it is does not measure efficiency/profitability. This was reinforced by employment data for the beneficiary MSMEs to indicate progress towards the PDO. 36. The two impact assessments demonstrated an association between the funded interventions under the access to finance and BDS components and the increase in employment and sales of beneficiary MSMEs. Obtaining a loan from project supported MFIs was associated on average with a 44 percent increase of respondents‟ monthly sales compared to the pre- intervention time. In addition, the average monthly sales of MSMEs benefitting from BDS supported by the project increased by 84.4 percent, while their employment level increased by 41.7 percent. 37. While the impact assessments were prepared in 2008 and 2009, a significant portion of grants utilized to support access to finance and business development services was disbursed by the time of the reports‟ completion. Out of the total amount of US$7.8 million and US$3.1 million9 of grants actually paid to support establishment of MFIs/bank downscaling and matching grants for business development services respectively, 80 percent of grant resources under access to finance and 37 percent for BDS were utilized by the time each of the impact assessments were completed. It should also be noted that that matching grants for BDS were paid in tranches based on performance, and so the actual disbursements may underestimate the magnitude of BDS because the total grants were fully disbursed only after verification of agreed targets. 38. An additional source of evidence is the study Financing SMEs in Nigeria10 conducted by the World Bank in 2012 which showed sustained gains in access to finance, the crisis notwithstanding. Specifically, it indicated that 9.5 percent of surveyed firms (other than project beneficiaries) had access to loans or lines of credit in 2011 compared to 5.1 percent in 2007. Based on this information, it seems that, while still at the low overall level, access to finance for MSMEs continued to increase from 2007 despite the crisis which severely affected the financial sector. It is reasonable to conclude that part of this gain can be attributed to the effects of the project. 9 This excludes a final grant of $2.5 million which was approved and disbursed only in 2011 to support implementation of new initiatives (i.e., YouWin). This grant was for a special project which was not originally planned and which did not include a matching component. Also, this activity was not covered with impact assessments. 10 By Gunhild Berg, Michael Fuchs, Leonardo Iacovone, Thomas Jaeggi, Andrew Lovegrove, and Carolina Villegas Sanchez, 2012. 9 2.4 Safeguards and Fiduciary Compliance Safeguards 39. The project did not trigger any safeguards policies. Fiduciary Compliance The project broadly complied with FM and procurement requirements. The government PIU was tasked with FM functions, while the private contractor (PMU) was responsible for procurement, once it became operational. In turn, the firm managing the PMU was procured by the PIU. By the closing date, project implementation in both procurement and FM was rated moderately satisfactory. 40. Due to poor record keeping and high staff turnover, the project was subject to a FM review. In 2009 the FM rating in implementation supervision report (ISR) was downgraded to moderately unsatisfactory due to: poor filing system; high turnover of FM staff of the project; breakdown in the computerized accounting system; delays by project management to resolve issues identified in audited financial statements and FM supervision mission reports; absence of internal audit activities, and inadequate staffing for the FM function. 41. However, the FM review concluded that the PIU had addressed all the previously identified shortcomings and the project was upgraded. Following an in-depth FM supervision mission, project compliance improved; this was formally recorded in the ISR, and FM rating was upgraded to moderately satisfactory in May 2010. Accountability and internal controls were improved with the hiring of two additional FM staff in the accounts unit, redeployment of the project accountant who had been transferred to another assignment earlier, and addressing of internal control issues raised by the previous FM supervision mission. The project rating during the most recent FM supervision mission was moderately satisfactory. 42. While it took some time for the PMU to build internal procurement capacity, the project in general complied with World Bank requirements in this area. The initial issues identified by Bank‟s procurement review mission (e.g., procurement of equipment without formally approved procurement plan, delays in payments, short deadlines for submission of bids, and inadequate staffing of procurement function) were addressed as implementation progressed and internal capacity was built. To address these shortcomings, the World Bank procurement team delivered training for project procurement staff. The Bank's procurement team rated overall procurement compliance as moderately satisfactory. 2.5 Post Completion Operation Next Phase 43. Various government institutions will continue to oversee implementation of the reforms initiated under the project. 44. Business Registration. The project supported the development of streamlined and common business registration procedures linking the Corporate Affairs Commission (CAC) and Federal Inland Revenue Service (FIRS). These procedures were adopted by the relevant entities and the agreement was formalized in a memorandum of Understanding between the CAC, FIRS, and NIPC. Additionally, various workshops were organized to build client awareness and institutional capacity to implement these reforms. The necessary hardware was also funded under 10 the project. However, the physical link between the databases of CAC and FIRS was not finalized by the closing date. Final testing of the software and installed systems is underway and it is expected that the business registration streamlining will be completed by summer, 2012, when the new system is expected to go live. Once implemented, the time required to register a new company will significantly decrease. 45. Secured Transactions. The Project supported the drafting of the Law on Secured Transactions, but the Law has not been approved by Parliament. The Central Bank FSS 2020 Working Group11 has adopted the Project‟s supported draft Law and included it in the package of laws that the Central Bank will nominate for Parliamentary approval in 2012. 46. In addition, the World Bank will continue close policy dialogue with the authorities in the area of access to finance. Specifically, the upcoming Financial Sector Assessment Program will cover access to finance issues, which will provide an opportunity for further engagement in the policy area which has received project support. 47. Finally, the World Bank will also conduct a review of the joint IDA/IFC MSME pilot program for Africa. 3. Assessment of Outcomes 3.1 Relevance of Objectives, Design and Implementation Relevance of Objectives 48. The development objective of the project was to “increase the performance and employment levels of MSMEs in selected non-oil industry sub-sectors and in pilot areas of the country.�? The private sector is widely considered a key generator of economic growth and MSMEs account for the vast majority of private sector activities and employment in Nigeria. As such, the project rightly focused on supporting MSMEs to promote private sector led growth. The development objective was also consistent with the Joint Interim Strategy Update for the Federal Republic of Nigeria of February 2002, which identified private sector led growth of the non-oil economy as key to reduce poverty (second pillar of the Strategy Update). The Government‟s priorities in this sector were reflected in the above-mentioned strategic documents, and in its original request for this project which specifically focused on MSMEs development. 49. This objective continues to be relevant today; hence, the project is rated high in terms of relevance of objectives. The relevance of the project objective was confirmed in the FY 10-13 Country Partnership Strategy (CPS). Amongst others, the CPS recognized the importance of maintaining non-oil growth and called for targeted interventions to promote private sector involvement. In addition, the 2011 CPS progress report also stated that Nigeria requested donor support to increase MSME access to finance. Listed instruments include: partial credit risk guarantees, bank downscaling, entrepreneurial training and business development services, and credit lines to support MSMEs. Finally, according to recently completed World Bank Study Financing SMEs in Nigeria12, 96 percent of firms in the manufacturing sector are SMEs, and while they account for 70 percent of employment they contribute only 1 percent, of GDP which 11 FSS 2020 is an independent unit of the CBN tasked with the responsibility to support Nigeria‟s transformation into one of the twenty largest economies in the world by the year 2020. 12 By Gunhild Berg, Michael Fuchs, Leonardo Iacovone, Thomas Jaeggi, Andrew Lovegrove, and Carolina Villegas Sanchez, 2012. 11 reflects partly the country‟s dependency on extractive industries and the continuing relevance of the project‟s focus on MSMEs and non-oil industry subsectors. Relevance of Design and Implementation 50. The project was designed around four themes: (i) improving access to finance; (ii) enhancing business development services; (iii) improving the investment climate; and (iv) promoting public-private sector dialogue. These themes are essential for MSME development. Accessible financing enables entry of start-ups and expansion of existing firms by facilitating investments in inputs, equipment, technology, and/or labor which are all essential for growth. Business development services are important as they contribute to improvement of management practices which in turn have positive impact on productivity. Finally, an unfavorable investment climate can stifle MSME growth and public-private sector dialogue can help promote business environment reforms. 51. The importance of these themes for MSME growth was also identified in the IDA IFC framework paper of 2003. Projects under the IDA-IFC framework recognized the need to address obstacles for MSMEs growth in a holistic manner, specifically in three areas: i) access to finance; ii) business development services; and iii) investment climate. The framework was designed to respond to common issues affecting MSME performance across Africa and it envisaged relying on private sector partners to enhance implementation. The MSME project was designed as one of IDA-IFC pilots and as such it incorporated the recommended instruments aimed at nurturing MSME growth. As a result, this contributed to higher relevance of project design to identified MSME development agenda. 52. Recent analytical work confirmed the importance of investment climate and access to finance for Nigerian MSMEs. Therefore relevance of design is rated substantial. Access to finance remains the second largest obstacle for MSMEs according to 2011 Investment Climate Assessment, and the importance of investment climate reforms was highlighted in the CPS as means to support non-oil growth. Finally, the previously cited study Financing SMEs in Nigeria13 found that only 9.5 percent of surveyed SMEs had a loan or line of credit from a financial institution in 2010. While this was a significant increase compared to 2007 when this percentage was 5.1 percent, this nevertheless highlights the relevance of MSME access to finance agenda. 53. To implement the ambitious reform program, the project relied on implementation mechanisms which placed private sector at the center. First, recognizing the limitations of government capacity to implement complex projects, a decision was made to engage a private sector project management unit. Second, the access to finance component was designed to support the creation of a market leader (a new microfinance bank or bank that downscales) that would eventually serve as a demonstrator to other market participants and prove that lending to the MSME segment is a profitable venture. Third, the Bank and IFC partnered to support the creation of a commercial microfinance bank. Fourth, the project provided support to BDS providers (rather than MSMEs directly) to create a market for BDS providers. The innovative design for access to finance and BDS components was instrumental for achieving the PDO. 54. Rating: Based on high relevance of objectives and substantial relevance of design and implementation, overall relevance is rated substantial. More weight was placed on project design and implementation, as these two areas are instrumental for achieving the stated objectives. 13 Ibid. 12 3.2 Achievements of Project Development Objectives 55. The Project Development Objective was to increase the performance and employment levels of MSMEs in selected non-oil industry sub-sectors and in pilot areas of the country which was largely confirmed. As stated previously, while originally the PDO monitoring indicator was designed to capture MSME value-added, the project eventually monitored sales revenue as a more accessible indicator of impact on MSME performance. This approach was used because MSMEs do not use a standardized accounting approach to report on purchased inputs which is, in addition to sales revenue, used to determine value added. Consequently, the progress towards the PDO was measured by tracking beneficiary MSME sales and employment levels. 56. The two independent impact evaluation studies14 largely confirmed achievement of the PDO. The studies were based on the surveys of MSMEs benefitting from activities supported under Access to Finance and BDS Components. Both impact assessments found an association between accessing a loan and receiving business development services, on the one hand, and an increase in sales and employment levels of target MSMEs on the other, thus confirming the pilot approach and likely confirming the achievement of the PDO in a sample of surveyed enterprises by 2009. While the impact assessments were prepared in 2008 and 2009, as previously discussed in paragraph 37, a significant portion of total grants utilized to support access to finance and business development services were disbursed by the time impact assessments were completed. 57. The following review of achievement of PDO is divided in two parts, each focusing on one of the specific targets, namely: (i) increase in beneficiary MSME performance measured by increase in sales levels; and (ii) increase in beneficiary MSME employment levels. Increase in MSME performance 58. The beneficiary MSMEs which obtained a loan from microfinance institutions established with project support on average increased monthly sales by 44 percent compared to pre-intervention time. According to an independent impact assessment study prepared by IFC‟s Results Measurement Unit in 2009, based on the data collected by BDO OFO consulting covering a stratified random sample of 450 borrowers (out of 11,000) of three microfinance institutions supported by the project (Susu, Accion, and MIC), the Project recorded substantial impact in improving performance of participating MSMEs. The relevant results are as follows: (i) obtaining a loan seems to have had a substantial effect on borrowers‟ monthly sales; on average, the monthly sales increased by NGN 197,385 or 44 percent per respondent compared to pre- intervention time from NGN 455,388 in 2007 to NGN 652,773 in July 2008; further, more than 80 percent of respondents agreed that obtaining a loan affected their business sales and profitability in the past year; (ii) the project succeeded in increasing access to finance for 25 percent (88 out of 354 people) of respondents who had been unable to access the loans before; (iii) respondents reported positive change in business practices, as 94 percent agreed with a statement that obtaining a loan led to improvements in their businesses, such as changes in 14 i) Impact Evaluation of Borrowers from Accion , Susu, and MIC Microfinance Banks , by Luba Shara, IFC with data collection conducted by: BDO OFO CONSULTING LTD, 2009; and ii) Impact Survey of MSME Beneficiares, by BDO OFO CONSULTING LTD, 2008. 13 keeping business records and preparing end of the year accounts15. It should be noted that while the study of MFIs did not directly estimate a counterfactual through interviews with non-assisted MSMEs, the interview questions did elicit views on the probable „with-without‟ scenario, so that the stated sales increases were indicative of significant net effects. 59. The issue of attribution was addressed by directly asking respondents about the extent to which the changes in sales were caused by obtaining the loan, and the majority of project beneficiaries confirmed a positive link. Based on this approach, 25.5 percent of respondents attributed the change in sales completely or to a large extent to the loan, another 39 percent stated that accessing the loan had some effect on sales, while 36 percent claimed that the loan had no or little effect on sales. 60. MSMEs which benefited from project supported business development services reported an 84.2 percent increase in average monthly sales in the observed period. According to an independent impact survey of 183 MSMEs serviced under the project, conducted by BDO in conjunction with the IFC in 2008, the project also had a significant positive impact on sales of MSMEs which received project supported BDS. In this case the study used a matched control group of MSMEs to estimate net effects. Specifically, beneficiary MSMEs reported an increase of 84.2 percent on their average monthly sales (from about N243,840.58 to N449,270.4) in the observed period, compared to an increase of only 6.2 percent (from N401,713.5 to N426,466.2) for the control group of 72 MSMEs benefiting from other BDS providers in non-pilot states. Further, the corresponding quarterly sales figures of beneficiary MSMEs increased by 112 percent (from N1,023,884 to N2,172,799), while the control group recorded a decrease of 3.7 percent. According to the study, and based on statistical test of significance, the changes in beneficiary MSMEs monthly and quarterly sales were found to be statistically significant at 95 percent confidence level. At the same time, increase in monthly sales of the control group was not statistically significant while their decrease in quarterly sales was significant16. 61. To verify findings, the survey included two other matched control groups: 225 MSMEs without any BDS in pilot states and 295 MSMEs without any BDS assistance in non-pilot states. In both cases, the beneficiary MSMEs experienced higher impact on sales than control groups. Specifically, the MSMEs that operated in the same environment as beneficiary MSMEs but did not receive any BDS, experienced a slight increase in average monthly sales of 3.5 percent (from N263,667 to N273,008) and 11.2 percent increase in quarterly sales (from N723,000 to N812,462); however, these increases in monthly and quarterly sales were not statistically significant at 95 percent confidence level17. Finally, the MSMEs with no BDS in non-pilot states recorded an insignificant decrease in monthly and quarterly sales of 16 percent (from N1,229,584.6 to N1,022,741) and 3.6 percent (from N3,558,134 to N3,429,624) respectively18. Issues such as attributability and sampling method remain in question as always, but even though the trend in sales may be attributable to various factors, the finding that the increase in sales performance of beneficiary MSMEs was significantly higher than that of three other matched control groups suggest a robust result. 15 The number of respondents who keep business records increased by 23.4% as compared to the pre-loan time period (a rise from 66.0% to 89.4%), while the number of those who prepare end of the year accounts increased by 3.9% compared to pre-term time period (from 31.9% to 35.8%). 16 The computed t-statistics for target group‟s monthly and quarterly sales figures was 2.021 and 2.249 respectively, and for the control group it was 1.681 and 2.340 respectively. 17 Computed t-statistics for monthly and quarterly sales increase was 1.369 and 1.454, respectively. 18 Computed t-statistics for monthly and quarterly sales were 0.426 and 1.929, respectively. 14 Increase in MSME Employment Levels 62. According to the same independent impact survey focusing on BDS, the trend in employment before and after BDS showed that beneficiary MSMEs experienced an increase of about 41.7 percent in employee numbers (rising from a mean of 5.8 workers to 8.3 workers). The control group of MSMEs that received BDS in non-pilot states experienced an increase of 16 percent (from 10.9 to 12.7). Since the control group enterprises were on average larger than the assisted enterprises the results are not watertight. However, they are instructive since they show a net additional employment effect of some 25 percent and they also show an absolute positive net effect in increased number of workers (2.5 vs. 1.8). The other two control groups which did not receive BDS (in pilot and non-pilot states) did not provide additional data for the observed periods to enable a comparable calculation, though their average employment increased as well. Overall, based on the employment results from the survey, it could be concluded that as a result of project-supported BDS, beneficiary MSMEs recorded significantly greater increases in employment than the different control groups. Box 1: Access to Finance – Context and Achievements: According to the PAD, even prior to commencement of project activities the Nigerian financial system consisted of a diverse universe of banking and non-banking financial institutions. As of end 2001, it included 89 commercial and merchant banks, over 1,000 rural-oriented community banks, 7 development finance institutions, 229 licensed finance companies, about 195 primary mortgage institution, over 100 insurance companies, 5 discount houses, various pension schemes and over 100 exchange bureaus. At the same time, the financial sector was overwhelmingly dominated by commercial banks, which accounted for 93 percent of non-central bank assets. While several commercial banks began with micro- finance pilot projects in 2001 and approximately 17 major NGOs were providing microfinance services, there was no commercially viable and sustainable microfinance sector in Nigeria. In 2004, the Central Bank of Nigeria raised the minimum capital requirements for commercial banks from N 2 to 25 billion, and consolidated and strengthened the banking sector by reducing the number of banks from 89 to 25 by 2005. The global crisis of 2008 significantly impacted Nigeria with massive drop in oil prices, currency depreciation, crash of stock exchange, increasing NPLs, and overall pressure on the private sector. As an illustration, out of total of 25 banks, eight experienced severe capital deficiencies and liquidity problems, and three of those ended up being nationalized. Despite this challenging financial sector context, the Project managed to catalyze the emergence of a growing commercial microfinance industry in Nigeria on a sustainable basis The project supported the Central Bank of Nigeria in developing a regulatory framework for microfinance, which was a prerequisite for setting up commercial microfinance industry. Once the regulatory framework was in place, the Project administrated competitive performance grants scheme combined with first-mover approach which facilitated the establishment of 6 de novo microfinance institutions (Accion, AB, Susu, and Microcred, IMFB, and MIC) and supported downscaling of one commercial bank (Oceanic Bank). The following grant amounts were disbursed: i) AB - $ 1.5 mn; ii) Accion – $ 1.5 mn; iii) Susu – 1.196mn; iv) Microcred - $ 1.5 mn; v) Oceanic - $975 k; vi) MIC - $528 k; vii) IMFB - $ 650k. Due to the shocks caused by the global financial crisis two out of six established MFIs – IMFB and MIC – failed and lost their license. Susu and Accion microfinance banks underwent a process of consolidation to deal with portfolio quality problems, while AB and Microcred continue to expand. While Oceanic Bank also experienced difficulties following the crisis, it has been recently taken over by Ecobank and thus its microfinance portfolio has been sustained. 15 In conclusion, despite the massive financial crisis, four new MFIs ( Accion, AB, Susu, and Microcred) were established and remain in operation and this achievement was at least partly attributable to the project. This was achieved with a total $5,696,000 in grants which in turn mobilized over $30 million of private equity contribution and resulted in their current loan portfolio of nearly $50 million. A grant of $975k to Oceanic Bank supported its downscaling efforts and resulted development of microfinance portfolio of nearly $8 million. 63. Finally, the project achieved synergy with IFC which originally committed to investing $1.5 million and ended up committing US$10 million. The original IFC commitment was meant to support Accion‟s venture into microfinance sector. However, this contribution was significantly exceeded with a total IFC investment of around US$10 million. Details of IFC project related investments are presented in the table below: Activity Debt Equity Advisory AB Microfinance Bank N475mn ($3.2mn) N150m ($1.03mn) - Accion Microfinance Bank - $1.89mn - Microcred Microfinance Bank $2mn $1mn $700k CRC credit bureau Ltd. - - N34.5mn ($ 238k) Total IFC Investment $5.2 mn $3.92mn $938k 64. Overall, the studies from 2008 and 2009 have confirmed a link between the project supported activities and the impact on beneficiary MSMEs performance and employment levels. This conclusion is always subject to caveats in terms of attribution and counterfactuals but there is sufficient evidence to indicate that the project resulted in significant improvements in MFI and MSME operations and profitability. 65. Rating: The results framework of the project measured outcomes which extended beyond the immediate project beneficiaries. Nevertheless, the team measured the direct impact of the activities funded under the two largest components through two impact assessments. While the assessments were completed in 2008 and 2009 (three years prior to project closing), a significant portion of grants utilized to support these two components had been utilized by then. Intermediate outcome indicators for the other components are less closely linked to PDO achievement, hence only the outcome of the largest two components is used in the rating. Based on this, the achievement of PDO is rated moderately satisfactory. 3.3 Efficiency Efficiency of Project Implementation 66. As mentioned previously this project faced some unusually difficult implementation problems, both internal and external, which impacted on the ability of the project‟s management to oversee rapid implementation. 67. The project experienced numerous delays throughout its lifecycle. Following Board approval on December 16, 2003 the Project became effective only on December 13, 2004. Further, the closing date was extended by 2.5 years, from the originally scheduled June 30, 2009 to December 31, 2011. Finally, at completion out of the total available SDR 22.3 million, SDR 473,181.82, or about 2.1 percent, remained undisbursed. 68. The delays experienced extended the planned implementation schedule by 2.5 years, which in turn translated into significantly higher project implementation costs. Specifically, the 16 disbursements under Project Management, Monitoring and Evaluation component reached $8.6 million as of June 2012, up from originally planned US$2.3 million. Even without the delays and associated project extension which caused the increase in implementation costs, the original implementation budget seems to have been underestimated. The reasons for the increase in Management costs were because the original five year contract for the project managing firm was extended by three years and adjusted for inflation in seven contract amendments. In addition, provision under this component was made for provision of additional technical expertise in areas such as secured lending, in resolution of IT issues affecting the business registration databases, and providing communications facilities which had not been originally budgeted. To cover these additional requirements the actual cost of project management rose from the original contract value of US$3.07 million equivalent to US$6.45 million equivalent over the project period. The overall project budget was not however exceeded as a transfer was made from other components. 69. Some of the major delays affecting implementation were beyond the control of the project team. For example, initial delays were related to late project effectiveness which was the primary responsibility of the government. Further, CBN‟s slow implementation of microfinance framework resulted in delays with implementation of access to finance activities. In addition, the complex security situation in Abia state delayed implementation in this location. 70. The cost benefit analysis conducted at appraisal stage estimated a net present value of about US$35.6 million corresponding to an internal rate of return of 26.2 percent. The cost- benefit analysis as presented in the PAD included all project components as follows: (i) BDS, which factored in some elements of the micro finance and commercial bank downscaling sub- components; (ii) access to finance; and (iii) investment climate, which included public-private partnership and project management components, and unallocated resources. It was also assumed that the BDS component would create a multiplicative effect on MSME output of about five times the norm (which resulted in a greater IRR for the BDS component, i.e., 5 percentage points higher than the access to finance component) and produce a lasting effect for up to seven years after project completion. Separate IRRs were calculated based on relative size of each component: 24.3 percent for access to finance, 29 percent for BDS, and 19.5 percent for investment climate (and other activities as listed). In summary, the weighted average of the individual components‟ IRR of 26.2 percent was produced. 71. For the purpose of this report, and due to limited availability of data, a new cost benefit analysis model was developed based on actual data, and focusing on two main project components - access to finance and business development services. The new model focused on these two components as they offered quantitative data necessary for the ex-post calculation of the net present value and internal rate of return. It was not possible to determine direct economic output of the investment climate and public private partnership development activities even though the latter also had tangible impact as discussed in section 3.5. 72. Equal weights were used for both components as they ended up disbursing similar amounts. The new model does not calculate separate economic IRRs for each component as it is difficult to allocate the project management overhead costs by component. Finally, in determining the direct attributable benefit flows for these two components, based on the available data, the following variables were applied: (i) MFI equity investment inflows; (ii) the increase in sales of borrower MSMEs; (iii) the increase in sales of MSMEs benefitting from BDS; and (iv), the BDS providers‟ matching of received grants. 73. According to the new model and based on available data, the calculated net present value and internal rate of return for Access to Finance and BDS components were US$11.8 million and 17 28 percent respectively. While the net present value is below the original calculation, the combined IRR of 28 percent exceeds the overall project target of 26.2 percent. At the same time it is important to recall that the NPV and IRR in this model are based on the outcomes of two components only, whereas the original one focused on the entire project. Further, the new model was based on available actual data, while the original one relied on assumptions which could not take into account factors such as the global crisis. If data had been available to quantify the impact of the investment climate and public private partnership development components, it is likely that the NPV and IRR would have been higher. The details of this analysis are presented in Annex 3. It is important also to note that the original objectives of the project included generation of indirect output and employment resulting from the external effects on the MSME sector from BDS upgrading. If such effects were quantified they would most likely also increase the measured return to the project. 74. The two main components significantly exceeded the expected targets which were aimed to be achieved with the initial investment. In support of the strong economic IRR estimate it is worth reiterating that, while the access to finance component was aimed at supporting the establishment of two commercially viable MFIs, the actual achievement was double the target. Further, the BDS component reached around 3,400 MSMEs as opposed to 1,000 initially planned. 75. The project facilitated mobilization of IFC resources of around $10 million, thus far exceeding the initially planned IFC commitment of $1.5 million. This was achieved with the project support for the establishment of three MFIs (Accion, AB, and Microcred) which subsequently received IFC investment. To the extent that the IDA commitment mobilized the IFC investments this may be credited as a benefit to the project. 76. Rating: Overall, while the project experienced delays it also exceeded the originally planned targets regarding access to finance and business development services components, and planned IFC investments, and it achieved a substantial Economic IRR of 28 percent without exceeding the originally planned total project budget. On the basis of these factors, efficiency is rated substantial. 3.4 Justification of overall outcome rating 77. Despite the delays and other shortcomings, the project recorded significant achievements. Moreover, this was accomplished in the context of the project‟s pilot nature, ambitious development agenda, and a complex implementation environment, including a massive financial crisis and serious security challenges. Further, the project demonstrated flexibility and was able to quickly respond to government‟s request and broaden the scope with GEL and YouWiN initiatives. In conclusion, based on substantial relevance, moderately satisfactory achievement of PDO, and substantial efficiency, the overall outcome rating is moderately satisfactory. 3.5 Overarching Themes Other Outcomes and Impacts 78. The central theme of the project was focus on and engagement with the private sector, both in terms of final beneficiaries and service providers. Whereas some programs primarily focus on tackling institutional change as means to facilitate private sector development, the MSME project focused directly on extending support to the private sector itself, as well as supporting investment climate and other relevant policy reforms. As a result, the project facilitated the creation of a commercial microfinance industry in Nigeria and introduced a new supply model for business development services to MSMEs. Ultimately nearly 3,400 MSMEs benefitted from the Project and a further significant number would have benefited indirectly. It 18 should also be noted that implementation of activities which relied on the private sector were ultimately more successful than those that tried to facilitate institutional change within the government structures. 79. The project also used the opportunities to broaden the scope of engagement. In this regard, it supported the development of catfish value chain activities in Oyo state as well as tourism value chain activities in Cross River state, which were not initially envisaged. As previously mentioned, it also responded to government request to implement GEL and YouWin programs, the latter of which had a strong focus on youth entrepreneurship. While no clear quantifiable outcomes of this additional engagement are available at this time, the activities they supported seem to have been well received by the government and beneficiaries. 80. While the outcomes under the Investment Climate and Public Private Partnership Development Components could not be quantified to establish a direct link to PDO, they nevertheless provided a significant contribution to the sustainability of MSMEs in Nigeria and can be assessed qualitatively. The activities sponsored under these two components (as listed in Annex 10) in the form of various capacity building workshops, training events, and study tours directly reinforced the technical capacity of the institutions responsible for project implementation and MSME development (i.e. NIPC, SMEDAN). Below is a summary of the main achievements under these two components which could not be captured by the two impact assessment studies. 81. The principal outcomes of Investment Climate component include the establishment of Credit Bureaus (CB) and Alternative Dispute Resolution (ADR) mechanisms. By supporting the development of a regulatory framework for CBs, and thus facilitating creation of three new CBs in Nigeria, this component has helped to reinforce the foundations of a commercial microfinance industry established under the project‟s access to finance component. In addition, access to finance infrastructure in Nigeria will be further strengthened once the new Law on Secured Transactions, also prepared with the project support, is enacted. Further, the achievements under this component included introduction of novel dispute resolution mechanisms in Kaduna and Abia states by supporting the establishment of two multi-door ADR courthouses, and strengthening the existing one in Lagos, thus facilitating faster and cheaper dispute resolution process for MSMEs. 82. In addition, noticeable progress was made regarding comprehensive reform of the business registration process in Nigeria. As discussed in paragraph 44, the project supported the development of streamlined and common business registration procedures which were approved and adopted by relevant entities, organized stakeholder workshops, and provided the necessary hardware. The only remaining activity is the establishment of a physical link between the databases of CAC and FIRS which is expected to be completed by the summer of 2012. Once this is done, the business registration process will be significantly enhanced. It should also be reported that over the course of the project life, the process of business registration in Nigeria has improved. At the beginning of project implementation, and as recorded by Doing Business 2004 Report, it took 44 days and ten procedures start a business. Today, according to Doing Business 2012 Report, it takes 34 days and eight procedures. Also, according to Nigeria‟s sub-national Doing Business 2010 results, the same indicators for the project target states are as follows: 33 days and 9 procedures for Abia; 31 days and nine procedures for Kaduna; and 31 days and eight procedures for Lagos. While the intended streamlining of the business registration process has yet to be completed, these improvements may be partially attributed to the project as it has actively supported this agenda. 19 83. The activities sponsored under Public Private Partnership Development component supported capacity building of relevant authorities and facilitated dialogue with the private sector to advance development of MSMEs. Under this component, 247 courses and 38 study tours focusing on the reform topics targeted by the project, were organized for NIPC, SMEDAN, and other federal and state level authorities. An MSME competitiveness report was also prepared, and a national competitiveness conference was organized in September 2011. Further, an additional 18 events supporting public private dialogue were held. These included three roundtables for MSME financial service providers, two stakeholder forums on private credit bureaus, one consultative forum on commercial bank downscaling, two roundtables on investment climate, two knowledge sharing alternative dispute resolution events, co-sponsoring of three annual Nigerian Economic Summits, three BDS fairs, and two stakeholder forums on rice and tourism sectors. 4. Assessment of Risk to Development Outcome 84. While the MSME sector in general tends to be dynamic in terms of entry and exit, the project supported activities in the area of access to finance and business development services which seem to have had a largely sustainable impact. The gains from exposure to the project have already been accrued in target MSMEs, as recorded in the evaluation survey. In addition, the project supported the establishment of previously embryonic financial infrastructure in the form of a commercial microfinance industry, which shows evidence of sustainability, thus at least partially addressing the low access to finance which was identified as one of the principal constraints for development of enterprises in Nigeria19. In addition, it could be argued that four supported MFIs have already sustained the ultimate test caused by global financial crisis. 85. Further, the network of business development service providers which received project support, and ultimately supported some 3,400 MSMEs, is expected to continue to introduce better management practices which should in turn positively impact productivity. This causal relationship between improved management practices and productivity increases has been illustrated in an example from India. According to Improving Management in India20 case study21 a sample group of companies which received five months of intensive management consultancy showed that improvements in management practices led to large increases in performance. Specifically, their productivity levels rose by about 15% and profits by about 24 percent (an increase of US$474,000 per firm). Based on this, it could be assumed that a similar relationship would apply to Nigerian MSME sector as well. 86. Even in the case of exit of some MSMEs, an externality may persist in that the owners, managers, and employees who benefitted from business development services should still be equipped with skills to deal with business challenges and/or embark on new ventures. Nevertheless, the potential risks for continued MSME development in Nigeria exist. They could be broadly divided into exogenous and endogenous risks. 87. Exogenous Risks. These are the risks of a slow recovery from the global crisis and oil price volatility. Negative trends could weaken the Nigerian economy and pose significant 19 According to the most recent World Bank Investment Climate Assessment study from 2011, low access to finance was the second most important constraint for Nigerian SMEs, following the shortage of electricity. 20 Improving Management in India by Nick Bloom, Benn Eifert, Aprajit Mahajan, David McKenzie, and John Roberts. Finance & PSD Impact ; Issue no. 10. April 2010. “The Lessons from DECRG-FP Impact Evaluations". 20 pressures on MSME activities and overall sector sustainability. On the other hand a sustained reduction in the price of oil could improve the environment for MSMEs by allowing depreciation of the real exchange rate and improving competitiveness. 88. Endogenous Risks. These are risks of failure to achieve needed policy and institutional reforms. The extent of institutional and policy reforms in the area of business environment both at the federal and state levels, macroeconomic stability, quality of prudential supervision, and the access to infrastructure (such as electricity), as well as political and security situation could all pose potential risks to the MSME sector. 89. The prospects of gradual global recovery and government announced commitment to pursue comprehensive reforms serve as mitigating factors. Further, the recorded gains in MSMEs sector have already been achieved in a challenging environment and in light of materialization of practically all of the risks listed above to a certain extent. Finally, all of the mentioned challenges are ongoing country risks endemic to Nigeria. 90. Rating: Overall, the risk to sustainable development outcomes beyond the project life is rated as moderate. 5. Assessment of Bank and Borrower Performance 5.1 Bank Performance a) Bank Performance in Ensuring Quality at Entry 91. The project was designed to address the key obstacles to MSME development, as identified by considerable Economic and Sector Work 22 which preceded preparation. The representative analytical work underpinning project design included Results of the Nigeria Firm Survey and SME mapping exercise. These reports revealed that Nigerian private sector suffered from high costs and lacked competitiveness due to: (i) limited access to finance; (ii) lack of access to adequate business development services; and (iii) investment climate non conducive to MSME growth. The project was designed to tackle specifically these obstacles. Finally, the operation was in line with joint IDA/IFC pilot program for Africa, which aimed to develop MSMEs in Sub-Saharan Africa by addressing obstacles to MSME growth in a comprehensive manner. 92. The project objective was and still is highly relevant to the country‟s goals and development priorities. This was reflected in the IDA‟s Interim Strategy Update from February 2002, highlighted in analytical work which preceded preparation, and confirmed in FY10-13 CPS, and confirmed in recent analytical work (e.g., Making Finance work for Nigeria, 2009). 22 Bank Staff Assessments: 1) Results of the Nigeria Firm Survey, Regional Program on Enterprise Development (RPED Paper #118, April 2002), World Bank. 2) The Implementation Completion Report (ICR) on the World Bank Small and Medium Enterprise Development Project (Loan 2995-UNI), Report #16811, June 1997. 3) Africa Program Framework Paper for a Joint IDA/IFC Micro, Small and Medium Enterprise Development Pilot Program for Africa, World BankJIFC (considered by the Board o f Executive Directors, June 19,2003). 4) SME mapping exercise undertaken in parallel with a survey on Nigerian firms conducted under the WED of the World Bank, October 2001. 5) “Joining the Race for Non-Oil Foreign Investment, �? conducted by the Foreign Investment Advisory Services; 6) “Direct Support to Private Firms - Evidence of Effectiveness�?, G. Batra and S. Mahmood, 2001 and „YDA ‟s Partnership for Poverty Reduction (FY94-FY00): An Independent Evaluation �?, OED, 200 1 , pp 31-33. Other: 1) “Evaluation of the Mekong Project Development Facility �?, Nexus and Assocs., June, 2002 with important insights into the best design parameters for BDS provider capacity building. 2) Guiding Principles for Donor Intervention Business Development Services for Small Enterprises: Guiding Principles for Donor Intervention, Committee of Donor Agencies for Small Enterprise Development, February 2001. 21 93. The project design relied on then innovative design features, which have by present day become the mainstream approach for MSME projects. Specifically, this included providing direct assistance to BDS providers, as opposed to MSMEs, in order to expand their services and outreach, to support development of the market for business development services. Further, by supporting first-movers in the microfinance sector and commercial bank downscaling, the project probably created a demonstration effect. For example, following downscaling of Oceanic Bank, at least four more banks (Stanbic, First Bank, Diamond, and UBA) followed suit without direct project engagement. 94. The project tried to address identified problems in a very comprehensive way. This may have been too ambitious in the context of complex implementing environment. Such a comprehensive project required significant coordination across different government agencies, which in practice proved difficult to achieve. In this regard, limited government capacity to ensure implementation of a complex and comprehensive reform agenda may have been underestimated. At the same time some issues with project management from the side of the Bank, in particular the time required for a FM audit, and delay in procurement training, added to the complex nature of the Bank-Government dialogue. 95. The choice of specific investment loan (SIL) was appropriate for the access to finance and business development services components which were the main focus of the project. It was also appropriate for delivering technical assistance to the authorities to improve business environment (i.e. drafting laws, exposure to best practices, etc). However, a SIL may not have been the most appropriate instrument to support approval of some of the attendant legal reforms. A development policy loan (DPL) may have been more appropriate in this respect. However, at the time of project approval the government was not interested in a development policy loan. Further, a Federal level DPL supporting financial sector reforms, approved during the period of project implementation, was processed as an emergency operation and as such had a very specific and sharp focus. As a result, the option of including investment climate reforms could not be considered. In light of this, and given the focus of the project on access to finance and BDS, the choice of instrument was appropriate. Rating: Overall, the quality at entry is rated moderately satisfactory. b) Quality of Supervision 96. Implementation Supervision Reports (ISRs) were filed regularly and the ratings largely reflected the project performance. The project was rated unsatisfactory from June 2005 until April 2006 (when it was upgraded to moderately unsatisfactory) due to delays in meeting effectiveness conditions and approval of the necessary MFI framework and licensing of Accion, which prevented earlier commencement of access to finance activities. Additional reasons included PMU's slow implementation progress, including inadequate procurement staff, and the ability of NIPC to disburse resources due to a requirement to obtain its management approval on implementation matters, contrary to agreed project implementation manual. Also, following implementation support provided by the project team, and agreement on remedial actions with the government and implementing entities, overall implementation progress was rated moderately satisfactory in June 2006. At the time of FM review, due to temporary non-compliance with FM procedures, the FM rating was justifiably rated moderately unsatisfactory. 97. At the same time, it may have been appropriate to use a more conservative rating in the final ISR. Since the last ISR was not based on new, end-project impact assessment to reconfirm 22 previously recorded progress and given that some of the planned investment climate reforms were not completed by that time, a more proper rating for the final ISR may have been moderately satisfactory as opposed to the awarded satisfactory rating. 98. On account of the delays experienced, the costs under the Project Management, Monitoring and Evaluation component reached US$8.6 million as of the June 2012 FM report, up from the originally planned US$2.3 million. As explained in section 3.3, one of the principal reasons for the increase was the overall extension of project by 2.5 years and adjustment for inflation. The bulk of these costs (i.e. US$5.9 million) were project management associated costs accrued by the PMU to cover both the extensions and some additional technical assistance. An additional US$1.1 million was also incurred for general office expenses. The Bank supervision team approved the increase in operating costs resulting from the delays experienced in order to ensure the functioning of the PMU and continued implementation. Given the magnitude in the switch in funding, a formal restructuring proposal may have been appropriate. 99. Despite the views of the dedicated project supervision team, the shortcomings during implementation might have warranted project restructuring. The shortcomings included the FM deficiency which triggered an in-depth FM review, performance problems with the investment climate component, and, the substantial increase in costs for Project Management, Monitoring and Evaluation. Early restructuring might have reduced the scale of the planned activities to conform more to operational constraints and to allow for better monitoring of the project. Further, restructuring might also have helped to address the identified implementation issues and challenges, including: (i) streamlining of project components by removing underperforming activities and providing additional support for successful pilots; and (ii) revising the PDO and results framework to ensure that they measure direct impact of the supported activities. 100. Finally, implementation was hampered by the global crisis, which severely affected Nigeria, and by significant security challenges. The global crisis severely hit the Nigeria financial sector. As a result, two project supported MFIs failed and lost their license. Moreover, significant security threats in one of the pilot states (Abia) further complicated supervision activities as the project team could not provide on-site implementation support for extended period of time due to high incidence of crime and kidnappings. Nevertheless, supervision was thorough and involved adequate staffing and resources. The project team provided regular implementation support to address the identified technical challenges; further, special procurement training was designed and delivered to increase the capacity of implementing entities and facilitate implementation. In addition to formal missions, the task team leader was based in the field for about three years and was thus able to provide ongoing implementation support. The team displayed commendable adaptability to ever changing situation and responsiveness to the client. The support for GEL and YouWin projects is a testament of team‟s responsiveness. 101. Rating: Overall, based on the above, the quality of supervision is rated moderately satisfactory. c) Justification of Rating for Overall Bank Performance 102. Rating: Based on moderately satisfactory quality at entry and moderately satisfactory quality of supervision, overall Bank performance is rated moderately satisfactory. 5.2 Borrower Performance a) Government Performance 23 103. Due to lack of initial government pro-activity, project implementation was off to a late start. This is illustrated by the fact that Credit Effectiveness was achieved six months after the target date, or a year following Bank approval. In addition, the Government did not provide agreed co-financing which then required amendment to legal documents, causing additional delays. Also, some of the key investment climate reforms were not fully completed despite several project extensions, while implementation of access to finance activities was initially delayed due to slow implementation of microfinance framework. Overall, it seems that high- level institutional coordination and the government‟s strategic guidance for project implementation was missing. In practice, political commitment when the project was conceived did not adequately translate into strong implementation performance – partly the result of a fragmentation of agencies at the federal level. The lack of commitment tended to have general effects across the project as a whole. 104. The project addressed MSME obstacles in a very comprehensive manner. The implementation of such program required full commitment of a range of institutions, well beyond the implementing agency. While overall commitment may have been lacking, the Nigerian Investment Promotion Council (NIPC), where the government Project Implementation Unit was housed, itself showed strong commitment throughout project implementation. However, NIPC had to build its capacity upfront, and it did not have the institutional mandate and power to push through legislative reforms which depended on actions by other entities and/or the National Assembly. As a result, delays were recorded in implementation of the access to finance component due to CBN‟s slow implementation of microfinance framework and subsequently delayed licensing of Accion. Also, only partial reforms were implemented under the investment climate component, as some of the required regulatory reforms, such as the Law on Secured Transactions, were not enacted. Finally, streamlining of business registration process was not fully completed. 105. Rating: Based on the above, the government performance is rated moderately unsatisfactory. b) Implementing Agency Performance 106. Low initial capacity of PIU and PMU in implementing some of the World Bank procedures led to delays with project implementation, though most issues were resolved as implementation progressed. The project implementation rested on the government PIU and private sector PMU. The PIU was housed in the NIPC and was responsible for implementation of IDA credit, including overseeing PMU operations, and approving its annual work plan and budgets. Further, the PIU was responsible for financial management and disbursement. A private firm hired under the project managed the PMU which was tasked with overall project administration, including monitoring and evaluation, reporting, procurement, and outreach and communications activities. During the lengthy period of selection of PMU, PIU was fulfilling this role in the interim. The procurement process was in some cases lengthier than expected, largely due to lack of procurement capacity within PIU/PMU, but it was generally compliant with procedural requirements. In terms of financial management, as discussed, project implementation was substantially delayed as a result of temporary non-compliance with FM requirements. However, following the FM review, the project received clean bill of health, and implementation continued. 107. Once both entities were fully operational, and following training provided by the Bank team, project implementation was generally adequate. This was also achieved in the context of 24 objective shortcomings such as security threats in one of the targeted states. Implementation of the investment climate reforms experienced some difficulties. Although significant preliminary work was done, including drafting of regulations and studies, certain actions under this component were not implemented. It should however be highlighted that this was beyond control of the PIU, PMU, and Bank team. Finally, monitoring and progress reports were detailed and prepared on regular basis. 108. Rating: As a result, primarily due to temporary non-compliance in relation to required FM practices and delays in procurement, the implementing agency performance is rated moderately satisfactory. c) Justification of Rating for Overall Borrower Performance 109. Rating: Based on the moderately unsatisfactory government performance and moderately satisfactory implementing agency performance, overall Borrower performance is rated moderately satisfactory. Greater weight was placed on implementing agency performance as it had a greater impact on achieving the PDO. This is confirmed with the fact that significant measurable achievements were recorded in the context of challenging and complex implementation environment. 6. Lessons learned 110. Results framework should be designed to measure direct impact of the project. This includes ensuring that monitoring and impact indicators directly correspond to the project objective and are easily measurable. This is essential not only to assessing whether project objectives have been achieved, but also to ensuring that the targets are practically achievable and within the control of the project management. 111. In case of significant project delays (i.e., delay in effectiveness, implementation, etc.), which may affect implementation of original project design, a review of planned project activities should be conducted to confirm that they can be practically implemented. As a result of long delays, operational and political circumstances may change. This could inhibit implementation in line with the initial design. If these changes are substantial, project restructuring should be considered to ensure that the operation fits the new implementation environment. 112. Implementing entities should include key staff with required qualification and experience with World Bank procedures from the very start of the project. As there was no suitable entity within the government, and based on previous experience with government run projects in Nigeria, a private entity was tasked with project management. The PMU also employed national staff in some key positions thus building local capacity, while the PIU was staffed with civil servants. As a result, it is likely that the local staff capacity to implement complex projects was increased, and should provide a significant human resource for future projects. While the engagement of a private sector operator may have increased overall implementation capacity in a complex implementation environment, the private PMU has also experienced initial challenges with applying World Bank procurement guidelines. In this regard, to alleviate the initial capacity issues in the future, the Bank should ensure that implementing entities include key staff with required qualification and experience from the very beginning. In addition, all key staff should undergo additional task specific technical trainings – designed and delivered by the World Bank - during the first six months of project implementation. Finally, the World Bank project teams may 25 need to provide more intense implementation support during the first year of implementation, especially related to compliance with Bank‟s fiduciary standards. 113. All core project management functions should be within a single implementing entity. Implementation arrangements envisaged both the private PMU and government led PIU. While most of the project management functions were with the PMU, including procurement, the responsibility for financial management and disbursements and compliance with World Bank rules in these areas rested with the PIU. The split of the core functions proved to be ineffective, as overall project implementation depended on synchronized performance of both entities which could not always be ensured due to different capacity levels and/or procedural requirements. 114. Building commercially viable microfinance institutions under the project required funding and experienced technical knowhow. The latter had to be imported to Nigeria from reputable international companies. While the commercial banking sector was expanding and diverse in 2003, the microfinance market was embryonic and did not contain adequate local expertise. In the absence of local capacity a “first mover�? approach involving reputable international partners/investors (i.e., IFC, Accion, Microcred, etc.) was necessary and the use of performance grants was an effective approach to using such expertise to jumpstart the industry. 115. Piloted approach of targeting BDS providers, as opposed to MSMEs, can facilitate creation of market for BDS. While a demand driven approach has a sound rationale, targeting existing BDS providers has advantages in terms of avoiding intervention in market transactions and ensuring the accumulation of skills from outside rather than the recycling of existing skills. Following the latter approach the project built the capacity of BDS suppliers and expanded the services, thereby potentially attracting a broader customer base, and increasing cost-effectiveness and outreach to MSMEs. It would have been beneficial if the project also facilitated more interaction and networking between the BDS providers to allow for more knowledge exchange. 116. The Specific investment loan may not be the most suitable tool for facilitating comprehensive policy reforms. All envisaged project activities that depended on the PMU/PIU and private sector engagement were relatively successfully implemented (i.e., ATF, BDS, etc.). By contrast activities which required wider government actions or parliamentary approval, such as certain investment climate reforms, were delayed, or only partial progress was achieved. When wider policy reforms are necessary, investment loans may have to be coupled with budget support operations. Alternatively, dated legal covenants underpinning planned reforms could be considered as well. Finally, the government oversight (i.e., PIU) should ideally be housed with an institution with a clear mandate for the project supported activities (i.e., MSME development) and a high level of authority. While such institution did not exist in Nigeria at the time of design, identifying an influential champion institution remains a key to operations timely success. 117. Though it was a pilot project, which allowed for a more flexible design and testing of new approaches, the breadth of the operation may have been too ambitious. This is especially true with regard to numerous activities aimed at reforming the investment climate which required wide institutional support which could not be fully secured. With regard to support provided to value chains, it may have been beneficial if the project concentrated on one value chain intervention initially, and scaled up only following successful implementation. In addition, delays related to capacity issues and slow administrative procedures further complicated achievement of some of the planned activities which depended on many stakeholders, and which could not be achieved despite three extensions. Thus simplification of both the component and the management structure of the project could have been worthwhile. 26 118. While IFC investments in the microfinance sector were larger than estimated at design, it seems that this was achieved with very limited IDA-IFC coordination. No regular reporting and interaction mechanisms were established at the design stage, and no periodic operational meetings were organized during implementation. It is likely that in-depth collaboration with IFC may be difficult given the different approaches of the two organizations, but nevertheless a more structured form of coordination would be beneficial in joint projects. 7. Comments on Issues Raised by Borrower/Implementing Agencies/Partners 119. Overall, the borrower, implementing agencies, and beneficiaries all highly rated project activities and outputs. They felt that tackling MSME issues in Nigeria was highly relevant for addressing economic growth and employment issues. In regards to their experience with project implementation they all cited lengthy and often complex administrative procedures regarding implementation of World Bank funded projects. Further, it was suggested that any future operation should have a well developed publicity strategy to properly educate the stakeholders about the project and build consensus about the importance of reforms. To ensure proper involvement of all relevant government stakeholders, including those who may not be directly involved with the project but whose action may be critical at certain occasion, it was suggested that liaison officers are appointed by all relevant/participating agencies who could follow up on all pending issues. 120. Access to finance was identified as a key constraint for Nigerian MSMEs by all stakeholders. This is consistent with the findings of the most recent World Bank Investment Climate Assessment study from 2011 which identified low access to finance as the second most important constraint for Nigerian SMEs, following the shortage of electricity 121. Not surprisingly, all consulted stakeholders expressed strong interest in a follow up project focusing on access to finance and expanding to other areas of the country. Stakeholders also highlighted that access to finance is more restricted in rural areas. The following topics were identified as potentially relevant to future operations: (i) technical assistance for MFIs to improve their operations and better serve their clients; (ii) access to a MSME credit lines for qualifying MFIs and banks interested in downscaling; (iii) country wide consumer financial education/literacy program; and iv) support with improved regulation and supervision of growing MFI sector to ensure stability, transparency, and to prevent public‟s loss of confidence in financial system due to failure of some MFIs in recent years. . 27 Annex 1. Project Costs and Financing The following information is based on Financial Management report as of June 2012. Project Cost by Component (in US$ million equivalent) Components Appraisal Estimate Actual Latest Percentage of (US$ million) Estimate Appraisal (US$ million) Access to Finance 10 7.9 79% Business 12 7.4 Development Services 61.6% Investment Climate 5.1 6.6 129.4% Public/Private 1 2.3 Partnership Development 230% Project 2.3 8.6 Management, Monitoring Evaluation 373% Unallocated 1.6 TOTAL 32.0 32.8 28 Annex 2. Outputs by Component Below is a summary of the most significant project outputs: Component 1: Access to Finance The project supported the establishment of four MFIs (Accion, Susu, Microcredit, and AB) and thus facilitated subsequent mobilization of US$30.8 million of private equity investment Total number of borrowers and savers in 4 MFIs as of end September 2011 was 35,232 and 144,683 respectively Downscaling of one commercial bank (Oceanic Bank) Total disbursed loan portfolio for four MFIs and a commercial bank of around US$57.4 million Component 2: Business Development Services Support provided to 69 BDS providers (45 under general BDS Fund and 24 through 4 value chain interventions – catfish, rice, palm oil, and tourism) which in turn introduced 25 new products and services Approximately 3,360 MSMEs received BDS, and a total of 20,161 MSME attendants of which 17,358 were covered under the general BDS program and 2,803 in 4 supply chains New jobs in supported supply chains estimated at around 1,168 Component 3: Investment Climate Law on Secured Transactions drafted Legal and regulatory framework for credit bureaus was established Central Bank of Nigeria Staff trained in supervising credit bureaus Three new Credit Bureaus (CB) are operational Two new multi-door alternative dispute resolution (ADR) court houses established in Kaduna and Abia State, while the existing ADR centers in Lagos was strengthened Report on integrating registration process was prepared and disseminated, workshop held, and hardware delivered Component 4: Public/Private Partnership Development 159 23 public sector personnel from NIPC, SMEDAN, and federal and state level governments received advanced project related training through 285 training activities (247 courses and 38 study tours) Three roundtables for MSME financial services providers Two stakeholder forums on private credit bureaus One consultative forum on commercial bank downscaling Two PPD roundtables on IC Two knowledge sharing ADR events; 23 Some trainees benefited from more than one training/study tour. 29 Co-sponsored three annual NESG NES; Three BDS fairs; Two stakeholder forums on rice and tourism values chains One MSME Competitiveness report prepared One Competitiveness Conference organized Component 5: Project Management, Monitoring and Evaluations N/A - This component ensured implementation of the four program components above. 30 Annex 3. Economic and Financial Analysis 1. The primary focus of the Economic and Financial Analysis was on the two main project components: (i) access to finance; and (ii) business development services. The reason for this approach is that these were the only two components offering quantitative data necessary for calculating net present value and internal rate of return. 2. For the Investment Climate and Public Private Sector Partnership Development components a qualitative analysis of costs and benefits has been presented in the main text. Access to Finance 3. In determining the direct attributable cash flows for this component, two variables were applied: (i) equity investment; and (ii) increase in sales of beneficiary MSMEs. i) Equity Investment: These figures used as they represented direct investments facilitated by the MSME Project, and were derived from the four supported MFIs. For purposes of this analysis, it was assumed and reflected in the table below, that the equity investments were made at the time of establishment of each of the MFIs (i.e., Accion and AB were established in 2007, Susu in 2008, Microcred in 2010). Equity Investments for MFIs Equity (N) Equity ($) AB 1,500,000,000.00 10,344,827.59 Accion 1,206,000,000.00 8,317,241.38 Microcred 1,000,000,000.00 6,896,551.72 Susu 773,000,000.00 5,331,034.48 Total 4,479,000,000.00 30,889,655.17 ii) Increase in sales of beneficiary MSMEs: In 2009, an independent impact survey 24 was conducted to measure the impact of the access to finance component. The survey focused on three MFIs: Accion, Susu, and Mic. It is important to note that while MIC microfinance bank ultimately failed during the crisis and lost its license, the positive impact on beneficiary borrowers/MSMEs was confirmed by the cited survey. 4. One of the areas measured by the study was the effect that obtaining a loan had on sales of beneficiary MSMEs. The study found that on average, the monthly sales of beneficiary MSMEs increased by NGN 197,385 (from NGN 455,388 in 2007 to NGN 652,773 in July 2008), or 44% per respondent compared to pre-intervention time. Given that these results were obtained based on response of 56 percent of the surveyed MSMEs, it was assumed that the same impact was recorded for 56 percent of the borrowers of three observed MFIs (approx. 11,000 at the time). Further, as no control groups were used in this part of the study the evaluation team gauged the attribution effect by directly asking respondents about the extent to which the changes in sales were caused; as a result 25.2 percent attributed the change completely or to a large extent to the loan, 39 percent said that it had some effect, while 36 percent said that loan had no or little effect. Consequently, the change in sales was applied to 64.25 percent of respondents who confirmed this causation. This number was then multiplied by the average monthly sale increase 24 Impact Evaluation of Borrowers from Accion , Susu, and MIC Microfinance Banks, by Luba Shara, IFC with data collection conducted by: BDO OFO CONSULTING LTD, 2009 31 of NGN 197,385 converted to a US Dollar amount ($1,361.28). According to the study, the increase was observed from 2007 to mid-2008. As no data was available for subsequent years, the cash flows were assumed to equal to zero from 2009 to 2011. For purposes of this analysis, the same assumptions, related to impact of loan on MSME sales, were applied to borrowers MFIs which were not covered by the study and/or may not have been operational at the time of the study. Namely, this includes AB which was operational in 2008 but not covered by the study, Oceanic Bank‟s borrowers resulting from downscaling in 2009, and Microcred which was established in 2010. Attribution effect Respondents (64.25% of Avg. Total Avg. (56% of borrowers Monthly Monthly Number of borrowers surveyed) Sales Sales Microfinance Banks Borrowers surveyed) OK Increase ($) Increase ($) Susu, ACCION, and 11,000 6,160 3,958 1,361.28 5,387,657.61 MIC (in 2008) 326 183 117 1,361.28 159,670.58 AB (in 2008) 2,886 1,616 1,038 1,361.28 1,678,192.75 Microcred (in 2010) 1826 1022.42 657 1,361.28 671,632.66 Oceanic (2009) Business Development Services 5. In determining the direct attributable cash flows for this component, two variables were applied: i) increase in sales of beneficiary MSMEs; and ii) matching grants. (i) Increase in sales of beneficiary MSMEs: According to an independent impact survey25 focusing on BDS component, the average monthly sales of beneficiary MSMEs increased from about N243,840.58 in 2006 to N449,270.4 in early 2008, or by 84.2 percent. The conclusions were based on a sample of 183 MSMEs from a total population of approximately 3,000 project beneficiaries at the time. For purposes of this analysis, it was assumed that the measured benefits could be applied to total population of project beneficiaries (MSMEs) at the time. Accordingly, the measured increase in sales of N205,429.82 was converted to US Dollars and applied to entire population of 3,000 beneficiary MSMEs. In addition, it was conservatively assumed that beneficiary MSMEs continued to record a real annual sales growth of five percent following the initial increase of 84.2 percent (i.e., from 2009-2011). 25 Impact Survey of MSME Beneficiares, by BDO OFO CONSULTING LTD, 2008. 32 Avg. Monthly Sales Total Avg. Monthly Business Development Services No. of Beneficiaries Increase ($) Sales Increase ($) 2006-2008 3,000.00 1,416.76 4,250,272.14 2009 3,000.00 331.53 994,591.71 2010 3,000.00 588.7 1,766,097.43 2011 3,000.00 728.13 2,184,383.67 6. Matching Grants: By design, the BDS component required beneficiary BDS providers to match the received grants. For purposes of this analysis, it was assumed that the total of $3.1 million under the matching grant scheme resulted in mobilization of the equal amount by the beneficiary BDS providers. According to the information received from the PMU, the disbursement of BDS grants on annual basis was as follows: 2006 - US$491,150; 2007 - US$676,606; 2008 - US$758,665; 2009 - US$419,183; 2010 - US$551,255 and 2011 - US$257,781. Consequently, it was assumed and reflected in the table below, that the same amounts were matched in each of the project years. Overall Project Financial Analysis 7. The economic analysis of this MSME project made the following assumptions in order to produce net present value (NPV) and the internal rate of return (IRR) on project investment: The considered project life was seven years, beginning in 2005 and ending in 2011. This was a result of delayed effectiveness which materialized in December 2004, thus allowing disbursements to begin only in 2005. The observed increases in sales of beneficiary MSMEs for access to finance and BDS components were based on the respective impact assessment studies which focused on specific periods. For the periods not covered by the studies, the cash flows for access to finance were denoted as zero, while for BDS a real growth of 5% was assumed. The rationale for assuming continued increase in sales for BDS beneficiaries was that technical skills they obtained would continue to enhance their business. For access to finance components, the impact on sales of AB, Microcred, and Oceanic Bank‟s borrowers resulting from downscaling was assumed to be the same as determined by the cited studies. Oceanic Bank was exempted from the analysis of the private equity contribution variable as it was not possible to obtain data regarding the exact equity investment for the Oceanic Bank‟s portfolio which was a result of downscaling. The cash flows were also assumed to equal to zero in all instances/years where quantitative data was missing. Finally, all original figures in Nigerian Naira were converted US Dollars using an average exchange rate of N145/US$1 for the whole implementation period (N130/US$1 in 2007; N160/US$1 in 2011). Total planned IDA disbursements based on the most recent FM report as of June 2012 (US$23,963,103) for Access to Finance, BDS, and Project Management, and M&E components were considered to have been expensed in year 1. The Discount rate used was 12 percent, in line with the original Economic and Financial Analysis from the Project Appraisal Document. 33 Calculation of NPV and IRR: 2005 2006 2007 2008 2009 2010 2011 In US$ 0 1 2 3 4 5 6 Capital Outlay Investment -23,963,103 Access to Finance Component Equity Investment 0 0 18,662,068.97 5,331,034.48 0 6,896,551.72 0.00 Increase in sales revenue of Borrower MSMEs 0 0 0 5,547,328 671,632.66 0 1,678,192.75 BDS Component Increase in sales of BDS Beneficiaries 0 0 0 4,250,272.14 994,592 1,766,097 2,184,384 Matching grants 0 491,150.00 676,606.00 758,665.00 419,183.00 551,255.00 257,781.00 Net cashflow -23,963,103 491,150 19,338,675 15,887,300 2,085,407 9,213,904 4,120,357 Discount Factor 1.00 0.89 0.80 0.71 0.64 0.57 0.51 Discounted Cashflow -23,963,103.00 438,526.79 15,416,673.28 11,308,266.19 1,325,314.08 5,228,216.67 2,087,501.30 NPV 11,841,395.31 IRR 28% 34 Annex 4. Bank Lending and Implementation Support Supervision Processes (a) Task Team Members Names Title Unit Lending Ismail Radwan Country Program Coordinator ECCUS Peter J. Mousley Lead Private Sector Development Specialist AFTFW Chioma Kelechi Nwagboso Consultant AFTFW Irene F. Chacon Operations Analyst AFTFW Uma Subramanian Lead Private Sector Development Specialist CICTI Geeta Batra Chief Evaluation Officer CEXEG Bayo Awosemusi Lead Procurement Specialist AFTPC Jennifer Isern Manager CSAAP Peer Benno Walter Stein Senior Manager CAIDR Shireen El-Wahab Consultant EASFP Irene Arias Regional Manager CLACO Mehnaz S. Safavian Senior Economist SASFP Hisham A. Abdo Kahin Senior Counsel LEGES Mary Asanato-Adiwu Senior Procurement Specialist AFTPC Chaoying Liu Evaluation Officer CDIAS Luba Shara Senior Monitoring & Evaluation Specialist CAFAF Thomas Losse-Mueller Senior Financial Sector Specialist AFTFE Adenike Sherifat Oyeyiola Senior Financial Management Specialist AFTFM Akinrinmola Oyenuga Akinyele Senior Financial Management Specialist AFTFM Adewunmi Cosmas Ameer Adekoya Financial Management Specialist AFTFM Rona P. Cook Program Assistant AFTFE Yeshareg Dagne Program Assistant AFTFE Collins S. Umunnah Team Assistant AFCW2 Giula Pellegrini Junior Professional Associate AFTFE Marilyn Swann Manalo Consultant AFTFW Karen Alexandra Hudes Senior Counsel LEGST 35 (b) Staff Time and Cost Staff Time and Cost (Bank Budget Only) Stage of Project Cycle USD Thousands (including No. of staff weeks travel and consultant costs) Lending FY04 617,717.30 FY05 0.00 FY06 0.00 FY07 0.00 FY08 0.00 Total: 617,717.30 Supervision/ICR FY04 77,209.92 FY05 243,351.90 FY06 173,232.00 FY07 137,155.53 FY08 209,534.11 FY09 237,160.79 FY10 200,118.16 FY11 153,429.19 FY12 174,685.79 Total: 1,605,877.39 36 Annex 5. Beneficiary Survey Results 1. In order to measure progress with achieving the Project Development Objective, two impact surveys were commissioned focusing on the impact of Access to Finance and Business Development Services components respectively. Both surveys focused on determining the project‟s impact on sales and employment levels of beneficiary MSMEs. Access to Finance Survey was finalized in 2009 and it focused on impact evaluation of borrowers from Accion, Susu, and MIC microfinance banks, which were all established with project support. Business Development Survey was finalized in 2008 and focused on MSMEs which benefitted from business development services facilitated by the project. 2. The surveys confirmed a link between projects supported activities and increase in sales and employment levels of beneficiary MSMEs. The results are detailed below: Access to Finance Survey– Impact Evaluation of Borrowers from Accion, Susu, and MIC, Microfinance Banks26 3. The survey was conducted on a stratified random sample of 450 out of 11,000 borrowers of ACCION, SUSU, and MIC microfinance banks. The key objectives of the survey were to determine the project impact on: (i) increasing access to finance for previously undeserved MSMEs; (ii) positively affecting borrowers‟ business sales; and (iii) increasing the number of people borrowers employ. The results are summarized below: (i) Access to finance increased for previously underserved MSMEs, as the project succeeded in increasing access to finance for 25 percent (88 out of 354 people) of respondents who had been unable to access the loans before. The change in access to finance was calculated by aggregating respondents who did not apply for a loan before because of perceived difficulties with those respondents who applied but were denied, and then dividing this value by a total sample size. (ii) Obtaining a loan on average resulted in 44 percent increase of respondents‟ monthly sales as compared to pre-intervention time. Respondents reported monthly sales losses as low as NGN 2,400,000 and sales increases as large as NGN 6,543,333 with almost 20 percent of respondents reported no changes in sales at all. Yet, on average, the monthly sales increased by NGN 197,385 or 44 percent per respondent compared to pre- intervention time from NGN 455,388 in 2007 to NGN 652,773 in July 2008. The change in sales was calculated only for those 198 respondents (56 percent of a total sample) who provided numbers for both 2007 and 2008 years. 4. The attribution effect was addressed by directly asking respondents about the extent to which the changes in sales were caused by obtaining the loan, confirming that obtaining a loan had an effect on sales. Slightly more than a quarter of respondents (25.2 percent) attributed the change in sales completely or to a large extent to the loan. Another 39 percent claimed that accessing the loan had some effect on sales, whereas 36 percent stated that the loan had no or little effect on sales. 26 Prepared by: Luba Shara, International Finance Corporation (World Bank Group); Field Work (Primarily Data Collection) Conducted by: BDO OFO CONSULTING LTD. July 9, 2009. 37 5. In addition, in responding to a direct question, more than 80% of respondents agreed that obtaining a loan affected both their business sales and profitability in the past year. Results are provided in the tables below. (Sales can be attributed to obtaining a loan = “completely agree�? (10.8 percent) + “to a large extent�? (14.4 percent) + “to some extent (38.7 percent) + “to a little extent�? (20.1 percent) = 84 percent). Perceived Effect on sales Sales were affected by N of cases % Valid % Cumulative % obtaining a loan? Agree 153 77.3 82.7 82.7 Disagree 32 16.2 17.3 100.0 Total 185 93.4 100.0 Missing 13 6.6 Total 198 100.0 Perceived effect on profitability Profitability was affected N of cases % Valid % Cumulative % by obtaining a loan? Agree 162 81.8 85.7 85.7 Disagree 27 13.6 14.3 100.0 Total 189 95.5 100.0 Missing 9 4.5 Total 198 100.0 6. Obtaining a loan seems to have had only a minuscule effect on employment: only about one percent of respondents reported an increase in hiring completely or largely due to a loan obtained as a result of the project. The average number of employees hired by respondents has not changed over the period of 1.5 years (on average, two employees). Only 34 respondents (11.6 percent) stated that they hired new people after obtaining the loan. Of 11.6 percent who did hire more people, the number of new hires ranged from one to six, with two new employees on average. More than half of respondents (56.2 percent) hired only one new employee, and majority (90.6 percent) from one to two employees. However, when asked about attribution of hiring as a result of a loan, only three respondents attributed the increase in hiring completely or to a large extent to a loan (10 percent), while 50 percent stated that a loan had little or no effect on their decision to hire more people. And, 40 percent of those who answered this question attributed some effect in hiring of new people to a loan obtained from the bank. 7. In addition to confirming improved access to finance and increase in sales, the survey also confirmed positive change in business practices of beneficiary MSMEs. According to the survey, 94 percent of respondents agreed with a statement that obtaining a loan led to improvements in their businesses. Specific examples include changes in keeping business records and preparing end of the year accounts: the number of respondents who keep business records increased by 23.4 percent as compared to the pre-loan time period (a rise from 66.0 percent to 89.4 percent), while the number of those who prepare end of the year accounts increased by 3.9 percent compared to pre-term time period (from 31.9 percent to 35.8 percent). 38 BUSINESS DEVELOPMENT SERVICES – MSME BDS Impact Assessment Survey27 8. The objective of the assessment was to conduct a comprehensive survey of MSMEs which received assistance from the project‟s BDS component, as well as three control groups. The survey locations for the BDS Impact Survey comprised the pilot states of BDS interventions of Lagos, Kaduna and Abia and control (matching) states of Ogun, Oyo, Kano, Plateau and Anambra. Ogun and Oyo are the matching states for Lagos; Kano and Plateau for Kaduna and Anambra for Abia. The survey was administered on the four groups of enterprises as follows: Treatment Group (A) 183 MSMEs benefiting from BDS grant services in pilot states of Lagos, Kaduna and Abia Control Group (B) 225 MSMEs without any BDS assistance in pilot states. Control Group (C) 74 MSMEs benefiting from other BDS providers‟ (non-clients) services in non-pilot states of Ogun,Oyo, Kano, Plateau, Anambra, FCT and Bauchi Control Group (D) 295 MSMEs without any BDS assistance in non pilot states. 9. Based on the results on sales for all the groups and employment results for Groups A and C it can be inferred that BDS of the supported BDS providers made more positive impact on performance than the control groups. The measurable impact of BDS on sales and employment levels was gauged by the trend and changes in sales/employment figures of the MSMEs before and after they received BDS and whether the changes are statistically significant. 10. The survey confirmed that the average monthly sales of Group A increased by 84.2 percent (from about N243,840.58 in 2006 to N449,270.4) while that of Group C increased by mere 6.2 percent (from N401,713.5 in 2006 to N426,466.2367,771). The corresponding quarterly sales figures for group A increased from N1, 023,884 to N2, 172,799 representing 112 percent increase and for group C it was a decrease of 3.7 percent. 11. Based on statistical test of significance, BDS received by group A impacted positively on their sales more than that of control group C. When the sales figure before and after BDS were subjected to statistical tests of significance, the changes in group A‟s monthly and quarterly sales were found to be statistically significant at 95 percent confidence level. The computed t-statistics for A‟s monthly and quarterly sales figures are 2.021 and 2.249 respectively. For group C, the increase in monthly sales was not statistically significant while the quarterly sales decrease was significant. The computed t-statistics for C‟s monthly and quarterly sales figures are 1.681 and 2.340 respectively. Moreover, only 15(20 percent) of group C attributed changes in their sales figure to BDS while 86(47 percent) of Group A enterprises attributed their changes in sales to 27 BDO OFO CONSULTING LTD. February 21, 2008. 39 BDS. Group B that operated in the same environment as group A (pilot states) but did not enjoy any BDS experienced a slight increase of 3.5 percent in their average monthly sales (from N263,667 in 2006 to N273,008 in 2007) and 11.2 percent increase in quarterly sales(from N723,000 to N812,462). These increases in monthly and quarterly sales were not statistically significant at 95 percent confidence level with computed t – statistics been 1.396 and 1.454 respectively. 12. Based on the trend in employment before and after BDS, the survey confirmed that the target Group A experiencing a 41.7 percent increase in employment (from a mean of 5.8 to 8.3 employees) while Group C experienced an increase of about 16 percent (from 10.9 to 12.7). The statistical test of employment change in Group A gave a significant difference before and after BDS while Group C shows an insignificant difference. The computed t-statistics for A and C are 2.405 and 1.335 respectively. This shows that BDS had impacted positively on the employment performance for the clients of the supported BDS providers more than on the performance of the clients supported by other BDS providers. The control groups B and D only provided overall average employment figure for 2006 and 2007 and no separate figures for the periods to enable calculation of growth rates in their employment. The mean employment figures for B and D are 6.07 and 13.98 respectively. These employment figures are incomparable with that of group A for the purpose of impact assessment because the changes in employment of groups B and D cannot be gauged. 13. In addition to impact on sales and employment, the survey recorded additional benefits from project facilitated BDS. Specifically, based on the analysis of the respondents‟ satisfaction ratings it was concluded that the quality of BDS received by the treated Group A was higher than that of the Control Group C. Further, it was found that the BDS providers in the pilot states made more impacts on knowledge and skills acquisition than the services providers in the Control states. In terms of acquisition and improvement in skills and knowledge, about 63 percent respondents from Group A and about 38% from Group C strongly agreed that they obtained new knowledge by purchasing BDS. In regards to new skill acquisition 50 percent as of Group A respondents strongly agreed that they acquired new skills, while only 16 percent from Group C confirmed the same relationship. In regards to application of skills and knowledge in business/operations, 96% of BDS users in Group A have applied the knowledge and skill gained to their business practices, as well as 91% of Control group C. The follow up support for both training and advisory services were rated poor (38% for consultancy and 34 percent for training). 404040 BDS users in Group A have applied the knowledge and skill gained to their business practices, as well as 91 percent of Control group C. 40 Annex 6. Stakeholder Workshop Report and Results A final closeout event of the MSME Project was organized by the project‟s communication team in consultation with the PMU and NIPC. This was held on the 7th of December, 2011 with attendance from beneficiaries from the states targeted from the Project, government institutions like the Central Bank of Nigeria, SMEDAN, and the media. The event featured beneficiaries‟ testimonies as well as a preview of the documentary on the Project -- all highlighting the achievement and lessons learned from the implementation of the project. 41 Annex 7. Summary of Borrower’s ICR and / or comments on Draft ICR The World Bank has received the project completion report as prepared by the PMU. Below is the summary of main reported achievements and supported events. Targets from PIM – Access to Finance Achievements as of 31/09/2011 1.1 At least two new microfinance 1.1 Four new MFIs have been established (AB institutions are established. Microfinance Bank; ACCION Microfinance Bank, MicroCred Microfinance Bank, and Susu For each MFI: Microfinance Bank). 1.1.1 At least 30,000 active clients by end 1.1.1 Active borrowers and savers for each MFI are: AB of year 4. (15,061/38,199); ACCION (12,089/59,084); MicroCred (5,294/ 10,096) and Susu (2,778/37,304) as of 31/09/2011. Total borrowers were 35,232 and total savers were 144,683. 1.1.2 At least US$20 million outstanding 1.1.2 Total outstanding portfolio is US$33.9 million. portfolio by end of year 4. Outstanding portfolio for each MFI is: AB (US$18.6 m); ACCION (US$10 m), MicroCred (US$3.3 m); and Susu (US$2 m) as of 31/09/2011. 1.1.3 Financial self-sufficiency ratio at 1.1.3 Financial self-sufficiency is 89% (AB), 117% least 100% by end of year 4. (ACCION), 55.3% (Microcred) and 105% (Susu) as of 31/09/2011. 1.1.4 Loan loss rate below 5% by end of 1.1.4 Loan loss rate is 0% (Microred), 2% (AB) and 6% year 4. (ACCION) as of 31/09/2011 (the other grantee did not report). However, it was agreed that portfolio at risk (PAR) at 30 days was a better indicator: 0.65% (AB), 3.93% (ACCION), 0.78% (Microcred) and 4.99%* (Susu) as of 31/09/2011. 1.2 New private sector investment in MFIs 1.2 New private sector investment in MFIs was US$30 at least US$15 million million (N4.5 billion paid up capital) as of 30/06/2011. Note: This figure does not include paid up capital from the two microfinance banks that the MSME Project financed and are now closed. 1.3 At least one commercial bank 1.3 One commercial bank (Oceanic) established an establishes an MSME downscaling internal microfinance section as of 31/09/2011. programme. For each commercial bank: 1.3.1 At least 5,000 active clients by end 1.3.1 3,818 active borrowers and 1,073,429 active savers of year 4. as of 31/09/2011. 1.3.2 At least US$10 million outstanding 1.3.2 US$7 million (N 1.017 billion) outstanding portfolio portfolio at end of year 4. as of 31/09/2011. 1.3.3 Financial self-sufficiency ratio at 1.3.3 This figure is not available as the microfinance least 100% by end of year 4. department is a unit within the bank, but the ratio is at least 100%. 1.3.4 Loan loss rate below 5% at end of 1.3.4 There is no figure available for this indicator, but it year 4. was agreed that portfolio at risk (PAR) at 30 days 42 was a better indicator: this was 5.9% as of 31/09/2011. 1.4 Bankers are aware of downscaling 1.4 There have been successful meetings with Banker‟s programme and develop more positive Committee on downscaling and a number of perceptions of commercial viability of commercial banks (Afribank, First Bank, UBA, and downscaling. IBTC) have invested in subsidiary banks. Including the three banks that have invested in ACCION (NIB [Citibank], Ecobank, and Zenith Bank), seven out of Nigeria's 22 commercial banks have invested in one form or another in commercial microfinance. Targets from PIM – General BDS Fund Achievements as of 31/12/2011 2.1 Assistance provided to at least 20 BDS 2.1 Assistance provided to 46 Providers from General providers BDS Fund (excluding VC BDS Grants). 2.1.1 At least 20 products or services 2.1.1 63 products or services improved or developed. improved or developed through Project support 2.2 At least 1,000 MSMEs receive BDS from 2.2 17,358 MSMEs have received BDS from participating BDS providers participating BDS providers. 2.3 Each assisted BDS provider demonstrates sustained uptake of supported products and services: 2.3.1 by end of third year, at least 75% of 2.3.1 / 2.3.2 There are conceptual problems with the clients adopt new behaviors measuring criteria 2.3.1 and 2.3.2 but they have been probably met where appropriate. A certificate course (the 2.3.2 at least 25% of clients return for Kaduna Program) could obviously not have repeat additional services customers. A widely circulated casebook on family business succession has problems in defining each reader as a client. 2.3.3 Cost recovery for the specific activities considered 2.3.3 by end of third year, BDS provider has is around 58%. at least 75% cost recovery on supported projects 43 Targets from PIM – Value Chains Achievements as 31/12/2011 2.2 Assistance provided to at least 30 BDS providers 2.2 A total of 29 BDS providers have been assisted through the four value chain interventions – catfish (11), rice (5), palm oil (3) and tourism (10) 2.2.1 At least 20 products or services improved or developed through Project support 2.2.1 29 products/services have improved or developed by the BDS grantees. 2.3 At least 1,000 MSMEs receive BDS from 2.3 2,803 firms have received BDS from participating BDS providers participating BDS providers – catfish (1,300), rice (997), palm oil (206) and tourism (300). 2.4 Each assisted BDS provider demonstrates sustained uptake of supported products and services: 2.4.1 by end of third year, at least 75% of clients 2.4.1 Of those BDS providers who successfully adopt new behaviors completed their grants there is considerable sustained uptake. 2.4.2 at least 25% of clients return for additional 2.4.2 Not all the services provided require the services provision of repeat or additional services to be effective (e.g. training). Where repeat use is relevant, repeat or additional use is in 2.4.3 by end of third year, BDS provider has at least line with the target of 25%. 75% cost recovery on supported projects 2.4.3 The initiatives under tourism (destination promotion) and palm oil (training) did not call for cost recovery. In catfish and rice, where grants were used to provide BDS, cost recovery was close to 100%. 2.5 Trusted and reliable accreditation process for BDS 2.5 This referred to the Catfish Value Chain providers is created (1st year: stakeholders agree Programme in particular. FISONS, a grantee, on accreditation qualifications and criteria) was supported by the programme to develop an accreditation system and has now drafted law, which it is pushing through Parliament, to give its accreditation system the force of law. There were also certification elements in the tourism VC intervention. 2.6 Catfish association is established in response to 2.6 The catfish associations already existed and industry-led demand for joint action were helped to become key BDS providers. Targets in the PIM – Investment Climate Achievements as of 31/12/2011 3.1 Legal and regulatory framework for credit 3.1 The legal and regulatory framework for credit bureaus bureau established has been established. 3.2 Private sector credit bureau is created 3.2 Three private sector credit bureaus have been established and are functioning. 44 3.3 Bank officers‟ awareness and knowledge of 3.3 CBN staff have been trained in supervision of credit credit bureau increased bureau. The awareness of the services offered is spreading across the banking industry but there is a need for greater awareness and capacity building to increase usage of services. The industry association is undertaking this. 3.4 Alternative dispute resolution mechanisms 3.4 Two new ADR Multidoor Courthouses have been developed and implemented in up to three created in Abia and Kaduna, and the existing Multidoor States Courthouse and the Citizen‟s Mediation Center in Lagos have been strengthened. 3.5 The diagnostic, design and implementation have been 3.5 Diagnostic conducted, programme design completed, though not within a year. completed, and formal agreements reached by end of year 1 3.6 The Abia and Kaduna Multidoor Courthouses have 3.6 Time required to resolve commercial just been established so it is too early to measure impacts. dispute under alternative system at least XX% There is evidence of increased usage of mediation services less than prior/existing system (target level at the Citizen‟s Mediation Center in Lagos contingent on diagnostic) Targets in PIM – Public Private Partnership Achievements as of 31/12/2011 Development 4.1 26 public sector personnel from NIPC, 4.1 159 unique public sector personnel from NIPC, SMEDAN and state-level ministries (e.g., SMEDAN, CBN and federal and state-level commerce and industry) receive advanced ministries have received advanced project-related project-related training. training through 285 training activities (247 courses and 38 study tours). Note: Some personnel have benefited from more than one training course/study tour. 4.2 Training participants provide at least one in- 4.2 26 of the trainees have conducted post training house seminar upon return. seminars. 4.3 Training participants prepare training 4.3 66 training summary reports have been prepared summary report. (verbally or written). 4.4 Annual roundtable discussion, beginning 2nd 4.4 The project held three roundtables for MSME Qtr 2005, between government and private financial services providers; two stakeholder sector to establish dialogue on policies and forums on private credit bureaus; one consultative programs targeted at MSMEs and to forum on commercial bank downscaling; two PPD disseminate lessons learned, best practices, roundtables on IC; two knowledge sharing ADR and project success stories. events; co-sponsored three annual NESG NES; three BDS fairs; two stakeholder forums in rice and tourism. There were also several materials (brochures, documentaries) which were widely distributed. Note: This section was redesigned in the period following the completion of the PIM. 4.5 Project is represented on the programme of 4.5 The Project signed a memorandum of understanding Nigerian Economic Summit (NES) every with the NESG and supported the implementation of 45 year beginning 2005. the NES programme. In addition, the project co- sponsored the annual NES Summits and the work of the Non-oil & Agriculture Policy Commission, and supported representatives from the State Governments in the project states to participate in the NES and dialogue. 4.6 Three MSME Competitiveness Reports. 4.6 One MSME competitiveness report was prepared in conjunction with the NESG and other stakeholders. Note: This activity was done late in the project because the project had been previously directed to drop the element. 4.7 Three Competitiveness fora. 4.7 One Competitiveness forum was organized in conjunction with NESG and other stakeholders. Note: This activity was done late in the project because the project had been previously directed to drop the element. 46 Annex 8. Comments of Co-financiers and Other Partners/Stakeholders N/A 47 Annex 9. List of Supporting Documents 1. Project Concept Note (July 2003) 2. Project Appraisal Document (November 2003) 3. Project Implementation Manual (November 2004) 4. Aide Memoires and Implementation Status Reports 5. PMU‟s Project Progress Reports and Completion Report 6. Impact Evaluation of Borrowers from Accion , Susu, and MIC Microfinance Banks, by Luba Shara, IFC with data collection conducted by: BDO OFO CONSULTING LTD, 2009 7. Impact Survey of MSME Beneficiares, by BDO OFO CONSULTING LTD, 2008. 48 Annex 10. List of sponsored events under each component of the Project: Component 1: Access to Finance Date Location First roundtable on Technical Service Provision for 1 June 2006 Lagos, Nigeria MSME 2 Roundtable on ATF Component for MSME June 2006 Kaduna, Nigeria 3 Roundtable on ATF Component for MSME June 2006 Abia, Nigeria 4 NationaL Stakeholder Workshop on Credit Bureaus June 2006 Lagos, Nigeria Award Ceremony for Access to Finance Grants to Susu 5 February 2007 Lagos, Nigeria and MIC Microfinance Banks 6 ACCION Microfinance Bank Launching July 2007 Lagos, Nigeria 7 Workshop on External Audit for Microfinance March 2009 Lagos, Nigeria 8 Workshop on Portfolio Quality and Governance March 2009 Lagos, Nigeria 9 External Audit of Microfinance Banks in Nigeria April 2009 Lagos, Nigeria 10 Savings Mobilization for Commercial Microfinance August 2009 Lagos, Nigeria 11 Savings Mobilization for Commercial Microfinance September 2009 Kaduna, Nigeria 12 Workshop on MicroLeasing December 2010 Lagos, Nigeria 13 Workshop on Microinsurance December 2010 Abuja, Nigeria 49 Component 2: Business Development Services Date Location Training on Market Oriented Small Business 1 February 2007 Abuja, Nigeria Development Services for BDS Providers 2 Workshop for Catfish VC BDS Grantees June 2008 Lagos, Nigeria Training on Market Oriented Small Business 3 August 2008 Abuja, Nigeria Development Training for BDS Providers 4 Lagos BDS Fair May 2009 Lagos, Nigeria 5 Kaduna BDS Fair June 2009 Kaduna, Nigeria 6 Abia BDS Fair June 2009 Abia, Nigeria Value Chain Workshop, jointly organised by 7 October 2009 Abuja, Nigeria MSME Project & DFID Training on Market Driven BDS and Value Chain 8 November 2009 Abuja, Nigeria Development for BDS Providers 9 Workshop for Tourism VC BDS Grantees November 2009 Calabar, Nigeria 10 Workshop for Tourism VC BDS Grantees January 2010 Lagos, Nigeria Kaduna BDS Fair hosted within the 31st Annual 11 February 2010 Kaduna, Nigeria Kaduna International Trade Fair Tourism Value Chain Stakeholders‟ Final 12 June 2010 Calabar, Nigeria Seminar 13 Workshop for Rice VC BDS Grantees July 2010 Kaduna, Nigeria ILO/ITC Training of BDS Providers on Women's 14 November 2010 Abuja, Nigeria Entrepreneurship Development Rice Value Chain Development Stakeholders 15 December 2010 Kaduna, Nigeria Final Seminar ILO/ITC Training of BDS Providers on Women's 16 May 2011 Abuja, Nigeria Entrepreneurship Development 17 Stakeholder Workshop for Palm Oil November 2011 Umuahia, Nigeria 50 Component 3: Investment Climate Date Location CREDIT BUREAUS National Workshop on Credit Bureau 1 June 2006 Abuja, Nigeria Development in Nigeria Implant Training for Credit Bureau Operations 2 March 2009 Abeokuta in Nigeria (for CBN staff) Washington and Chicago, 3 Study Tour - Regulating Credit Bureaus September – October 2009 USA / Cairo, Egypt 4 Stakeholders Workshop on Credit Bureau December 2011 Lagos, Nigeria BUSINESS REGISTRATION Signing of MOU on Business Registration 1 September 2007 Abuja, Nigeria among NIPC, CAC and FIRS 2 Workshop on Credit Bureau for CBN Staff February- March 2009 Abuja, Nigeria Implant Training for Credit Bureau Operations 3 February 2009 Kaduna, Nigeria in Nigeria (organised solely for CBN staff) SECURED LENDING Secured Lending Inaugural Stakeholder‟s 1 May 2009 Abuja, Nigeria meeting National Workshop on Secured 2 November 2011 Abuja, Nigeria Lending/Securitization ADR Study Tour to Uganda on Commercial Court 1 February 2007 Uganda Practices (ADR) ADR Seminar “Commercial Alternative 2 November 2007 Abuja, Nigeria Dispute Resolution for Core Stakeholders�? 3 ADR Assessment Report Presentation Forum February 2009 Abuja, Nigeria ADR Stakeholder‟s Phase 2/Design Phase 4 June 2009 Abuja, Nigeria Conference Training - Alternative Dispute Resolution 5 October 2009 Washington, USA (ADR) 6 Signing of Protocol on ADR by Abia State June 2010 Aba, Nigeria Settlement Week of Lagos Multi-Door 7 July 2010 Lagos, Nigeria Courthouse Opening ceremony of Abia State Multidoor 8 December 2011 Umuahia, Nigeria Commission 51 Component 4: Private – Public Partnership Date Location 1 Intervention Design and Management in BDS – July 2004 Glasgow, UK NIPC and SMEDAN staff 2 Microfinance Training – NIPC Project August- Plokwane City, South Africa Coordinator September 2004 3 Seminar on Model Law on Leasing – Chartered October 2004 Rome, Italy Inst. Of Arbitrators 4 Goods and Equipment Procurement Course – November 2004 Durban, South Africa NIPC Staff 5 Services Procurement – NIPC Staff NA Lagos, Nigeria 6 Financial Management and Disbursement – November 2004 Malawi NIPC Staff 7 Accounting Software System Training - NIPC November – Lagos, Nigeria Staff December 2004 8 Financial Management & disbursement training September 2005 Malawi – NIPC Staff 9 Financial management & disbursement training November 2005 Malawi II 10 Workshop on Procurement & Consultancy November 2005 Lagos, Nigeria Service – NIPC staff 11 Capacity Building and Needs Assessment December 2005 Abuja, Nigeria Workshop – NIPC and SMEDAN Staff 12 Course on The General Manager January 2006 Harvard, US Program(TGMP) – NIPC Staff 13 Principles & Practice of MSME Promotion & June 2006 Abuja, Nigeria Development – NIPC and SMEDAN staff 14 Summit on Sustaining Reforms and Unlocking June 2006 Abuja, Nigeria Nigeria's Potential – NIPC and Minister of Commerce Kaduna/Lagos 15 Collateral Reform and Access to Finance – July 2006 London, UK NIPC, CBM and FMoJ staff 16 Creating an Enabling Environment for Small October 2006 Turin, Italy Enterprise Development – NIPC and SMEDAN staff 17 Prevention, Analysis & Detection of Corporate October 2006 Mombasa Kenya Fraud – NIPC staff 18 Local Government .Investment Climate Reform March 2007 Tanzania 19 Strengthening OSIC for Accelerated Public March 2007 Kaduna, Italy Sector Reform 20 NESG National Forum for Synergy in MSME June 2007 Abuja, Nigeria Development 21 Phase 1 Study Tour on IPA Strategy for IC July 2007 Botswana Reforms 22 Financial Management Training October 2007 Turin, Italy 52 23 NIPC Directors Study Tour to Egypt November 2007 Egypt 24 Training on Project Management – NIPC Staff July 2009 London, UK 25 Results-Based Management Implementation and September- Setym International Training, Performance Indicators October 2009 Canada, 26 Study Tour for NIPC October 2009 Bangladesh 27 Training -Crown Agents Certificate in November 2009 London, UK Procurement for Senior Executives – NIPC Staff 28 Sustainable Microfinance – NIPC Project November 2009 London, UK Coordinator 29 Training - Results-Based Management November - Setym International Training, Implementation and Performance Indicators, December 2009 Malaysia, 30 Creating an Enabling Environment for SMEs November- Turin, Italy Development December 2009 31 Project Budgeting and Cost Control – NIPC May 2010 Malaysia Project Accountant 32 Monitoring and Evaluation August 2010 London, UK 33 Project and Program Impact Assessment August- Montreal, Canada September 2010 34 Project Budgeting and Cost Control – NIPC Staff October 2010 Malaysia 35 Study Tour – NIPC Staff October 2010 Indonesia 36 Advance Audit Skills – NIPC Internal Audit October 2010 London, UK 37 Project & Programme Management Training – November 2010 London, UK NIPC Staff 38 Public Financial Management: Planning and November- London, UK Control – NIPC Staff December 2010 39 Creating and Enabling Environment for November – Turin, Italy Sustainable Small Enterprise Development – December 2010 NIPC Staff 40 Course on Regulating Financial Markets – NIPC March 2011 Washington DC Project Accountant 41 Training course on Monitoring and Evaluation – 2011 London, UK NIPC Department Project Coordinator 42 Course on Leading a Project Team – NIPC March 2011 Dubai, UAE Project Secretariat 43 Study Tour – NIPC Staff July 2011 Ahmedabad, India 44 Study Tour – NIPC Staff July 2011 Chennai, India 45 Leadership for Senior Managers – NIPC Mrs. November 2011 Dubai, UAE Okala 53 To Tahoua To Agadez To Nguigmi 10°E 15°E Illela NIGER NIGER SOKOTO e Lake Chad ob To Y Kandi Sokoto Katsina Yobe Oamasak Nguru ma Kaura Ri S Namoda K AT S I N A dej ia Gan a ok o Ha gu BORNO ot Birnin JIGAWA du i Kebbi aar ma Gusau YO B E Ko J am KEBBI Z A M FA R A Kano Dutse Pokiskum Damaturu Maiduguri To Nig er KANO CHAD Kandi Zaria n g ol a Go Bunga Kaduna BAUCHI GOMBE Biu BENIN Kainji Kontagora CAMEROON Reservoir dun a KADUNA Bauchi Gombe Ka 10°N NIGER 10°N A Wawa Jos To A W Bori Minna e nu P L AT E AU A M ABUJA Be Nige r Yola K WA R A FEDERAL Shendam A D Jalingo Baro CAPITAL Ilorin TERRITORY Lafia SA NAS A R AWA O Y O Ta ab Benue r a Bali NIGERIA Oshogbo EKITI Lokoja Wukari Ibadan Ado-Ekiti K O G I Makurdi TAR ABA O SU N OSUN Akure BENUE Abeokuta ONDO OGUN ENUGU To Lomé LAGOS EDO Enugu ANAM Benin Abakaliki Lagos City Asaba Awka EBONYI CROSS NIGERIA BRA Sapete RIVER MICRO, SMALL AND MEDIUM r Nige D E LTA IMO CAMEROON Warri Umuahia ENTERPRISE PROJECT Owerri ABIA Uyo MAIN CITIES AND TOWNS 5°N RIVERS Aba Calabar 5°N Yenogoa Port AKWA- STATE CAPITALS Gulf of Guinea BAYELSA Harcourt IBOM To Doula NATIONAL CAPITAL 0 50 100 150 200 Kilometers MAIN ROADS This map was produced by the Map Design Unit of The World Bank. RAILROADS The boundaries, colors, denominations and any other information 0 50 100 150 Miles IBRD 39221 MARCH 2012 STATE BOUNDARIES shown on this map do not imply, on the part of The World Bank Group, any judgment on the legal status of any territory, or any Bioko I. endorsement or acceptance of such boundaries. 5°E (EQ. GUINEA) 10°E INTERNATIONAL BOUNDARIES