The World Bank Report No: ISR10445 Implementation Status & Results Georgia EAST-WEST HIGHWAY IMPROVEMENT 3 (P112523) Public Disclosure Copy Operation Name: EAST-WEST HIGHWAY IMPROVEMENT 3 (P112523) Project Stage: Implementation Seq.No: 7 Status: ARCHIVED Archive Date: 26-Jun-2013 Country: Georgia Approval FY: 2010 Product Line: IBRD/IDA Region: EUROPE AND CENTRAL ASIA Lending Instrument: Specific Investment Loan Implementing Agency(ies): Key Dates Board Approval Date 10-Sep-2009 Original Closing Date 30-Jun-2013 Planned Mid Term Review Date Last Archived ISR Date 26-Dec-2012 Effectiveness Date 03-Nov-2009 Revised Closing Date 30-Jun-2015 Actual Mid Term Review Date Project Development Objectives Project Development Objective (from Project Appraisal Document) (i) to contribute to the gradual reduction of road transport costs and improve access, ease of transit, and road safety along the central part of the Borrowers East-West corridor; and (ii) strengthen the capacity of the Roads Department and relevant government entities to plan and manage the road network and to improve road safety. Has the Project Development Objective been changed since Board Approval of the Project? Yes No Component(s) Component Name Component Cost A. Sveneti-Ruisi Road Link 180.80 B. Institutional Strengthening 2.70 C. Project Implementation 0.20 Construction of the Ruisi Agara Section (funded by Additional Financing) 35.00 Overall Ratings Public Disclosure Copy Previous Rating Current Rating Progress towards achievement of PDO Satisfactory Satisfactory Overall Implementation Progress (IP) Moderately Satisfactory Moderately Satisfactory Overall Risk Rating Moderate Moderate Implementation Status Overview The civil works for the three lots financed under the initial financing of the project are nearing completion, as contractors are correcting minor construction defects and completing River Protection works on the Liakhvi River The Liakhvi Bridge will be completed and last defects corrected after an independent Category 3 Bridge Design Check in accordance with European Standards is completed. The tunnels West of Gori are nearing completion, with western portal almost complete and the eastern portal 55% complete. Testing of electromechanical and fire-fighting equipment Page 1 of 5 The World Bank Report No: ISR10445 is still outstanding. In regards to the progress of the Ruisi to Agara bypass financed under TEWHIP AF, works have started and there has been good implementation progress made since the last ISR. The RD has almost finalized expropriations and the contractor is authorized to work on 90% of the proposed layout. Public Disclosure Copy Assistance activities to the roads department in project management and safeguards are carried out satisfactorily. Locations Country First Administrative Division Location Planned Actual Georgia Not Entered Vaziani Georgia Not Entered Tiniskhidi Georgia Not Entered T'edotsminda Georgia Shida Kartli Svenet'i Georgia Not Entered Shindisi Georgia Not Entered Sakasheti Georgia Shida Kartli Ruisi Georgia Not Entered Pkhvenisi Georgia Not Entered Otarsheni Georgia Not Entered Kvemo-Okona Georgia Not Entered Kvemo-Khviti Georgia Shida Kartli Kareli Georgia Not Entered Karalet'i Georgia Shida Kartli Gori Public Disclosure Copy Georgia Not Entered Berbuki Georgia Not Entered Avnevi Georgia Not Entered Akhalsheni Georgia Not Entered Akhaldaba Not Entered Not Entered Not Entered Georgia Not Entered Tskhinvali Page 2 of 5 The World Bank Report No: ISR10445 Results Project Development Objective Indicators Public Disclosure Copy Indicator Name Core Unit of Measure Baseline Current End Target Transit time from Sveneti to Ruisi (minutes) Minutes Value 12.00 8.10 9.00 Date 09-Aug-2009 22-May-2013 30-Jun-2013 Comments Vehicle operating cost from Sveneti to Ruisi Text Value 0.20 0.17 0.18 (cars in US$/km) Date 09-Aug-2009 22-May-2013 30-Jun-2013 Comments Vehicle operating cost from Sveneti to Ruisi Text Value 0.76 0.71 0.72 (trucks in US$/km) Date 09-Aug-2009 22-May-2013 30-Jun-2013 Comments Percentage reduction in road fatality rate per Percentage Value 0.00 43.00 30.00 10,000 vehicles on E60 corridor from Senaki to Date 09-Aug-2009 22-May-2013 30-Jun-2013 Tbilisi. Comments AADT was 6219 and road fatality was 112 Improvement in road capacity from Ruisi to Number Value 2800.00 2800.00 8000.00 Agara Bypass in passenger car space Date 03-May-2012 22-May-2013 30-Jun-2015 equivalent per hour Comments Roads in good and fair condition as a share of Percentage Value 85.00 85.00 85.00 total classified roads Date 03-May-2012 24-Sep-2012 30-Jun-2015 Comments Size of the total classified network Kilometers Value 1644.00 1644.00 1644.00 Sub Type Supplemental Transit time from Sveneti to the Agara Bypass Minutes Value 27.00 23.20 20.00 Public Disclosure Copy Date 03-May-2012 22-May-2013 Comments Vehicle operating cost from Sveneti to Agara Amount(USD) Value 0.20 0.19 18.00 Bypass (cars, USD/km) Date 03-May-2012 22-May-2013 30-Jun-2015 Comments Vehicle operating cost from Sveneti to Agara Amount(USD) Value 0.76 0.72 0.72 Bypass (trucks, US$/km) Date 03-May-2012 22-May-2013 30-Jun-2015 Comments Page 3 of 5 The World Bank Report No: ISR10445 Direct project beneficiaries Number Value 17240.00 17240.00 17240.00 Date 03-May-2012 22-May-2013 30-Jun-2015 Comments # of people living in the area Public Disclosure Copy of influence of the Sveneti to Agara Bypass road Female beneficiaries Percentage Value 51.00 51.00 51.00 Sub Type Supplemental Intermediate Results Indicators Indicator Name Core Unit of Measure Baseline Current End Target Number of kilometers of road upgraded Kilometers Value 0.00 14.00 15.00 Sveneti-Ruisi Date 09-Aug-2009 05-Nov-2012 30-Jun-2013 Comments Endorsement by RD of Georgian road safety Text Value No Yes audit manuals for new and existing roads Date 09-Aug-2009 05-Nov-2012 30-Jun-2013 Comments No Percentage of E60 corridor Senaki to Tbilisi Percentage Value 0.00 0.00 50.00 subject to road safety audits Date 09-Aug-2009 05-Nov-2012 30-Jun-2013 Comments This result depends on the completion of the manuals All new IBRD financed road sections subject to Yes/No Value No Yes Yes formal road safety audit using Georgian Date 09-Aug-2009 22-May-2013 31-Dec-2012 manuals Comments Number of km upgraded Sveneti-Agara Bypass Kilometers Value 0.00 15.00 34.00 Date 03-May-2012 22-May-2013 30-Jun-2015 Comments Public Disclosure Copy Percentage of E60 Corridor Senaki to Tbilisi Percentage Value 0.00 90.00 100.00 with road safety engineering improvements Date 03-May-2009 22-May-2013 30-Jun-2013 completed Comments Data on Financial Performance (as of 28-May-2013) Financial Agreement(s) Key Dates Project Ln/Cr/Tf Status Approval Date Signing Date Effectiveness Date Original Closing Date Revised Closing Date P112523 IBRD-77410 Effective 10-Sep-2009 18-Sep-2009 03-Nov-2009 30-Jun-2013 30-Jun-2013 Page 4 of 5 The World Bank Report No: ISR10445 Project Ln/Cr/Tf Status Approval Date Signing Date Effectiveness Date Original Closing Date Revised Closing Date P112523 IDA-51080 Effective 26-Jun-2012 28-Jun-2012 27-Jul-2012 30-Jun-2015 30-Jun-2015 Disbursements (in Millions) Public Disclosure Copy Project Ln/Cr/Tf Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P112523 IBRD-77410 Effective USD 147.00 147.00 0.00 147.00 0.00 100.00 P112523 IDA-51080 Effective USD 43.00 43.00 0.00 14.31 27.34 33.00 Disbursement Graph Key Decisions Regarding Implementation None Public Disclosure Copy Restructuring History There has been no restructuring to date. Related Projects P128863-Third East West Highway Improvement Additional Financing Page 5 of 5