The World Bank                                                                                                                                             Report No: ISR11842


                                                                                                   Implementation Status & Results
                                                                                                                   Haiti
                                                                                                     HT Electricity Project (P098531)
Public Disclosure Copy




                         Operation Name: HT Electricity Project (P098531)                                   Project Stage:   Implementation         Seq.No: 13     Status: ARCHIVED    Archive Date:    12-Sep-2013
                                                                              Country: Haiti                                         Approval FY:        2007
                         Product Line: IBRD/IDA                               Region: LATIN AMERICA AND CARIBBEAN                    Lending Instrument: Specific Investment Loan
                         Implementing Agency(ies):

                         Key Dates
                         Board Approval Date      03-Aug-2006         Original Closing Date 28-Feb-2010            Planned Mid Term Review Date 08-Jul-2011                Last Archived ISR Date 25-Mar-2013
                         Effectiveness Date       31-Jul-2007         Revised Closing Date 31-Aug-2013             Actual Mid Term Review Date       27-Sep-2011

                         Project Development Objectives
                         Project Development Objective (from Project Appraisal Document)

                         Contribute to the sustainable improvement in the quality of electricity services to customers and to the strengthening of the financial and operational performance of the
                         electricity public utility (EDH).
                         Has the Project Development Objective been changed since Board Approval of the Project?

                            Yes           No

                         Component(s)
                         Component Name                                                                                                          Component Cost
                         Installation of CMS/TSMS                                                                                                           4.60
                         Improvement in quality of service and increase in revenue collection of EDH for selected group of                                  1.90
                         customers
                         Participatory approach, project management, M&E                                                                                    1.50
                         Management support to EDH                                                                                                          2.80
Public Disclosure Copy




                         Overall Ratings
                                                                  Previous Rating                       Current Rating
                         Progress towards achievement of PDO      Moderately Satisfactory               Moderately Satisfactory
                         Overall Implementation Progress (IP)     Moderately Unsatisfactory             Moderately Unsatisfactory
                         Overall Risk Rating


                         Implementation Status Overview
                         Significant achievements have been implemented under the Project between April and August 2013. EDH remote metering system is operational and able to receive data from the
                         72 remote meters installed at priority industrial customers, EDH staff has been trained to install the remaining 350 meters purchased under the Project, recommendations from



                                                                                                                                                                                                          Page 1 of 6
                             The World Bank                                                                                                                                        Report No: ISR11842



                         experts were provided for the sustainability of EDH Information Systems purchased under the Project, and technical assistance to EDH Financial Division helped preparing and
                         supervising the financial audit of the utility.
                         Locations
Public Disclosure Copy




                         Country                                             First Administrative Division                    Location                                  Planned                 Actual
                         Haiti                                               Departement de l'Ouest                           Port-au-Prince

                         Haiti                                               Departement de l'Ouest                           Petit Goave

                         Haiti                                               Departement du Sud-Est                           Jacmel

                         Haiti                                               Not Entered                                      Republic of Haiti

                         Haiti                                               Departement de l'Artibonite                      Gonaives

                         Haiti                                               Departement du Sud                               Les Cayes

                         Haiti                                               Departement du Nord                              Cap-Haitien


                         Results
                         Project Development Objective Indicators
                         Indicator Name                                 Core Unit of Measure                       Baseline                       Current                          End Target
                         Cash Recovery Index                                   Percentage               Value      11.51                          26.70                            40.00
                                                                                                        Date       01-Mar-2011                    01-Jul-2013                      30-Nov-2013
                                                                                                        Comments   Value has been reset post      Commercial progress on           Value expected in April 2013,
                                                                                                                   earthquake. Average value      private clients could not        as an OIA (Tetra Tech)
                                                                                                                   over the last 12 months.       compensate the increase of       objective.
                                                                                                                                                  payment arrears from public
                                                                                                                                                  entities.
                         Percentage of customers served at least 6             Text                     Value      20%                            100%                             50%
                         hours per day on average in the zones served                                   Date       01-Mar-2011                    01-Jul-2013                      31-Aug-2013
                         by EDH
Public Disclosure Copy




                                                                                                        Comments   Value has been set post        Important variations, due to a
                                                                                                                   earthquake.                    fragile power system (Epower
                                                                                                                                                  plant down since June 2013).
                                                                                                                                                  Lowest value on one
                                                                                                                                                  distribution circuit was 8.3h/
                                                                                                                                                  day in June 2013.

                         Intermediate Results Indicators




                                                                                                                                                                                                         Page 2 of 6
                             The World Bank                                                                                                                                Report No: ISR11842



                         Indicator Name                                Core Unit of Measure              Baseline                        Current                           End Target
                         1.1.Number of customers in CMS database             Text             Value      0                               224,052                           185,315
                                                                                              Date       12-Dec-2005                     01-Jul-2013                       31-Aug-2013
Public Disclosure Copy




                                                                                              Comments                                   Major improvement, thanks to Value has to be reset post the
                                                                                                                                         the Commercial action plan   earthquake.
                                                                                                                                         implemented since October
                                                                                                                                         2012.
                         1.2. Number of customers in TSMS database           Text             Value      0                               224,052                           180,315
                                                                                              Date       12-Dec-2005                     01-Jul-2013                       31-Aug-2013
                                                                                              Comments                                   Clients of the provinces in     Value has to be reset post the
                                                                                                                                         TSMS database, but tool not earthquake.
                                                                                                                                         yet operational in these areas.
                         1.3. Number of EDH employees trained to use         Text             Value      0                               296                               435
                         CMS and TSMS (not cumulative)                                        Date       12-Dec-2005                     01-Jul-2013                       31-Aug-2013
                                                                                              Comments                                   Remaining staff to be trained
                                                                                                                                         are located in the provinces.
                                                                                                                                         As deployment of the CMS is
                                                                                                                                         considered by EDH
                                                                                                                                         management as a priority
                                                                                                                                         action (following the August
                                                                                                                                         2013 gap analysis conducted
                                                                                                                                         under the Project), training of
                                                                                                                                         staff will start in September
                                                                                                                                         2013.
                         1.4. Active Customers/employee ratio                Text             Value      80                              98                                100
                                                                                              Date       12-Dec-2005                     01-Jul-2013                       31-Aug-2013
                                                                                              Comments   184,000 customers for 2,300     As of July 2013, 224,502          Value to be adjusted with new
                                                                                                         employees, information          clients for 2302 employees.       commercial and financial
                                                                                                         available in the project PAD.                                     recovery plans.
                         5.2. Number of satisfied customers (large           Text             Value      TBD                             TBD                               1,270
Public Disclosure Copy




                         customers)                                                           Date       12-Dec-2005                     01-Jul-2013                       31-Aug-2013
                                                                                              Comments   No baseline.                    Survey to will be conducted in
                                                                                                                                         September2013, for the
                                                                                                                                         Government's ICR.
                         5.3. Employees satisfied with new system            Text             Value      0                               TBD                               625
                                                                                              Date       12-Dec-2005                     01-Jul-2013                       31-Aug-2013
                                                                                              Comments                                   Survey to will be conducted in
                                                                                                                                         September2013, for the
                                                                                                                                         Government's ICR.



                                                                                                                                                                                            Page 3 of 6
                             The World Bank                                                                                                               Report No: ISR11842



                         TA to EDH management                            Text   Value      Sub standard procedures        Gap analysis done,              Implementation of new
                                                                                                                          recommended new                 procedures for: - Financial
                                                                                                                          procedures for Commercial       Management - Internal
                                                                                                                          and IT.                         Control - Human Resources -
Public Disclosure Copy




                                                                                                                                                          Technical Management
                                                                                Date       18-Dec-2009                    01-Aug-2013                     31-Aug-2013
                                                                                Comments                                  TA supported design and
                                                                                                                          implementation of
                                                                                                                          Commercial action plan
                                                                                                                          2012-2013 and Financial
                                                                                                                          Audit 2013-2014.
                         Financial Management Plan                       Text   Value      No financial management        EDH Financial tool by           Implementation of (i) an
                                                                                           plan in place                  September 2013, Extensive       accounting system, (ii)
                                                                                                                          financial audit by Q1-2014.     definition of manual of
                                                                                                                                                          procedures, and (iii) inventory
                                                                                                                                                          of assets with support from
                                                                                                                                                          accounting assistance.
                                                                                Date       18-Dec-2009                    01-Aug-2013                     31-Aug-2013
                                                                                Comments                                  Accounting assistance
                                                                                                                          contract signed on May 13,
                                                                                                                          2013 with awarded firm.
                                                                                                                          Results expected by February
                                                                                                                          2014.
                                                                                                                          By end September 2013, a
                                                                                                                          parallel financial audit will
                                                                                                                          provide a tool to present
                                                                                                                          scenarios for the next 2-3
                                                                                                                          fiscal years..
                         Small customers served at least six hours a     Text   Value                                     100%                            50%
                         day on average                                         Date                                      01-Jul-2013                     31-Aug-2013
                                                                                Comments   Measurement started in 2011. 100% of industrial clients in
                                                                                                                        the industrial zones have
Public Disclosure Copy




                                                                                                                        more than 12h/day
                         Percentage of large customers served at least   Text   Value                                     75%                             60%
                         12 hours per day on average                            Date                                      01-Apr-2012                     28-Feb-2013
                                                                                Comments   This measurement started in    Not measured yet, remote
                                                                                           2011.                          meters will provide
                                                                                                                          information in May 2013
                         Cash Recovery Index - large customers           Text   Value                                                                     85%
                                                                                Date                                      01-Jul-2013                     31-Aug-2013




                                                                                                                                                                            Page 4 of 6
                             The World Bank                                                                                                                                             Report No: ISR11842



                                                                                                    Comments       CRI indicator not estimated by Audit of 310inactive industrial
                                                                                                                   customer type.                 customers showed 8% having
                                                                                                                                                  a fraudulent use of service.
Public Disclosure Copy




                         Number of large customers regularized                    Text              Value          0                                 1320                               1270
                                                                                                    Date           12-Dec-2005                       01-Jul-2013                        31-Aug-2013
                                                                                                    Comments                                         Since 2012, 50 new industrial Total number of industrial
                                                                                                                                                     clients in the Port-au-Prince customers may evolve.
                                                                                                                                                     area.
                         Number of EDH employees trained to attend                Text              Value          0                                 28                                 20
                         and follow up on large customers                                           Date           12-Jan-2010                       01-Jul-2013                        31-Aug-2013
                                                                                                    Comments       No specific recurrent training    A Large Clients Unit has been EDH willing to have a cell of
                                                                                                                   for this frange of custumers      created, for individualized   20 staff specialized in large
                                                                                                                                                     customer relationship .       priority customers.
                         Successful training of MTPTC staff to                    Text              Value          Not trained                       Energy Cell created in             Staff dedicated to sector
                         supervise performance indicators                                                                                            MTPTEC, coordinator of the         performance review trained
                                                                                                                                                     unit hired.
                                                                                                    Date           18-Dec-2009                       01-Aug-2013                        31-Aug-2013
                                                                                                    Comments       Baseline is set on the day of     Coordinator to recruit team.
                                                                                                                   effectiveness of the additional   Former Energy Unit staff who
                                                                                                                   financing, which finances the     did performance indicators
                                                                                                                   MTPTC staff                       monitoring could be recruited.
                         Number of EDH employees satisfied with the               Text              Value          0                                 TBD                                1938
                         project                                                                    Date           12-Dec-2005                       01-Dec-2012                        28-Feb-2013
                                                                                                    Comments                                         Surveys will be conducted in
                                                                                                                                                     September 2013.


                         Data on Financial Performance (as of 26-Jul-2013)
                         Financial Agreement(s) Key Dates
                         Project              Ln/Cr/Tf                Status             Approval Date                 Signing Date          Effectiveness Date        Original Closing Date     Revised Closing Date
Public Disclosure Copy




                         P098531              IDA-H2510               Effective          03-Aug-2006                   11-Sep-2006           31-Jul-2007               28-Feb-2010               31-Aug-2013
                         P098531              IDA-H5100               Effective          08-Sep-2009                   02-Nov-2009           15-Dec-2009               28-Feb-2012               31-Aug-2013

                         Disbursements (in Millions)
                         Project              Ln/Cr/Tf                Status             Currency           Original             Revised          Cancelled          Disbursed           Undisbursed          % Disbursed
                         P098531              IDA-H2510               Effective          XDR                              4.10             4.10               0.00               2.96                  1.14         72.00
                         P098531              IDA-H5100               Effective          XDR                              3.30             3.30               0.00               2.87                  0.43         87.00


                         Disbursement Graph

                                                                                                                                                                                                              Page 5 of 6
                             The World Bank                                                                                                                                        Report No: ISR11842
Public Disclosure Copy




                         Key Decisions Regarding Implementation
                         The Project is closing on August 31, 2013 with a final disbursement rate of 93% and all the major activities completed, with exception of the installation of remote meters.

                         Restructuring History
                         Level two Approved on 28-Feb-2013

                         Related Projects
                         P112164-HT (AF) Electricity Loss Reduction Project
Public Disclosure Copy




                                                                                                                                                                                                        Page 6 of 6