The World Bank                                                                                  Implementation Status & Results Report
           Zhejiang Rural Water Supply and Sanitation Project (P133018)



Zhejiang Rural Water Supply and Sanitation Project (P133018)


 EAST ASIA AND PACIFIC | China | Water Global Practice |
 IBRD/IDA | Investment Project Financing | FY 2015 | Seq No: 13 | ARCHIVED on 07-Sep-2020 | ISR43188 |


 Implementing Agencies: People's Republic of China, Zhejiang Provincial Economic Information Center



 Key Dates


  Key Project Dates

   Bank Approval Date: 25-Sep-2014                                           Effectiveness Date: 02-Feb-2015
   Planned Mid Term Review Date: 01-Dec-2017                                 Actual Mid-Term Review Date: 20-Nov-2017
   Original Closing Date: 31-Dec-2020                                        Revised Closing Date: 30-Jun-2021
 pdoTable

 Project Development Objectives

  Project Development Objective (from Project Appraisal Document)
  The proposed Project Development Objective (PDO) is to improve access to sustainable water supply and sanitation services in selected villages
  and towns in rural areas of Zhejiang Province.

  Has the Project Development Objective been changed since Board Approval of the Project Objective?
  No


 Components Table

 Name
 Improving Water Supply and Sanitation:(Cost $301.07 M)
 Training and Capacity Building:(Cost $1.00 M)
 Project Management and Supervision:(Cost $1.50 M)

 Overall Ratings

 Name                                                                      Previous Rating                         Current Rating

 Progress towards achievement of PDO                                       Satisfactory                           Satisfactory
 Overall Implementation Progress (IP)                                      Satisfactory                           Satisfactory
 Overall Risk Rating                                                       Moderate                               Moderate


 Implementation Status and Key Decisions

  The progress towards achieving the Project Development Objective (PDO) has been satisfactory. A project restructuring was approved by the Bank
  to (1) extend the project closing date from December 31, 2020 to June 30, 2021, and (2) add a new project implementation unit, namely Longquan
  Rural Water Affairs Co., ltd to look after master planning, construction management and operation of rural water supply and sanitation schemes in
  Longquan City. A total of 139 rural sewerage treatment schemes were built and put into operation. The project has already started to provide
  improved wastewater collection and treatment services to the residents of the participating small towns and villages.




9/7/2020                                                                                                                   Page 1 of 8
            The World Bank                                                                                      Implementation Status & Results Report
            Zhejiang Rural Water Supply and Sanitation Project (P133018)




  Risks


 Systematic Operations Risk-rating Tool


  Risk Category                                              Rating at Approval              Previous Rating                Current Rating

  Political and Governance                                   --                              Moderate                      Moderate
  Macroeconomic                                              --                              Moderate                      Moderate
  Sector Strategies and Policies                             --                              Low                           Low
  Technical Design of Project or Program                     --                              Low                           Low
  Institutional Capacity for Implementation and
                                                             --                              Moderate                      Low
  Sustainability
  Fiduciary                                                  --                              Moderate                      Moderate
  Environment and Social                                     --                              Low                           Low
  Stakeholders                                               --                              Moderate                      Low
  Other                                                      --                              --                             --
  Overall                                                    --                              Moderate                      Moderate



  Results


 PDO Indicators by Objectives / Outcomes



   To improve access to sustainable water supply and sanitation services in selected villages and towns

    IN00883935
    ►Number of people in rural areas provided with access to Improved Water Sources under the project (Number, Custom)

                                       Baseline                    Actual (Previous)              Actual (Current)          End Target

    Value                              0.00                        312,078.00                     377,057.00                450,000.00

    Date                               22-Aug-2014                 31-Dec-2019                    30-Jun-2020              30-Jun-2021

     IN00883936
     Female population (Number, Custom Breakdown)

                                      Baseline                    Actual (Previous)           Actual (Current)             End Target

     Value                           0.00                         156,039.00                  192,896.00                   225,000.00

     Date                            22-Aug-2014                  31-Dec-2019                 30-Jun-2020                  30-Jun-2021

    IN00883937
    ►People provided with access to ‘improved sanitation facilities” under the proj. (Number, Corporate)

                                       Baseline                    Actual (Previous)              Actual (Current)          End Target



9/7/2020                                                                                                                         Page 2 of 8
           The World Bank                                                                                      Implementation Status & Results Report
           Zhejiang Rural Water Supply and Sanitation Project (P133018)




    Value                             0.00                         611,160.00                    623,785.00                 630,000.00

    Date                              22-Aug-2014                  31-Dec-2019                   30-Jun-2020                30-Jun-2021

     IN00883938
     People provided with access to "improved sanitation facilities" - rural (Number, Custom Breakdown)

                                     Baseline                     Actual (Previous)             Actual (Current)            End Target

     Value                          0.00                          611,160.00                    623,785.00                  630,000.00

     Date                           22-Aug-2014                   31-Dec-2019                   30-Jun-2020                 30-Jun-2021

     IN00883939
     Female population (Number, Custom Breakdown)

                                     Baseline                     Actual (Previous)             Actual (Current)            End Target

     Value                          0.00                          305,580.00                    309,328.00                  315,000.00

     Date                           22-Aug-2014                   31-Dec-2019                   30-Jun-2020                 30-Jun-2021



 Intermediate Results Indicators by Components



   Improving Water Supply and Sanitation

    IN00883940
    ►Piped household water connections that are benefiting from rehabilitation works undertaken by the project (Number, Custom)

                                      Baseline                      Actual (Previous)             Actual (Current)          End Target

    Value                             0.00                         17,444.00                     96,699.00                  130,000.00

    Date                              22-Aug-2014                  31-Dec-2019                   30-Jun-2020                30-Jun-2021

    IN00883943
    ►New household sewer connections constructed under the project (Number, Custom)

                                      Baseline                      Actual (Previous)             Actual (Current)          End Target

    Value                             0.00                         87,794.00                     72,564.00                  85,000.00

    Date                              22-Aug-2014                  31-Dec-2019                   30-Jun-2020                30-Jun-2021
                                       The previous figure of "87,794" in the last ISR has some errors; the current figure of "72.564" in this ISR
   Comments:                           has corrected the last errors, as outlined in the restructuring paper.

    IN00883944
    ►Volume(mass) of BOD pollution load removed by treatment plant under the project (Tones/year, Custom)

                                      Baseline                      Actual (Previous)             Actual (Current)          End Target

    Value                             0.00                         2,937.00                      1,475.00                   2,796.00

    Date                              22-Aug-2014                  31-May-2019                   30-Jun-2020                30-Jun-2021



9/7/2020                                                                                                                        Page 3 of 8
           The World Bank                                                                                     Implementation Status & Results Report
           Zhejiang Rural Water Supply and Sanitation Project (P133018)



                                       The previous figure of "2,937" for total BOD load reduction and "2,675" for Fuyang WWTP in the last ISR
                                       have some errors. In this ISR, the current figure of "1,475" for total and "1362" for Fuyang WWTP in this
                                       ISR have corrected these errors, as outlined in the restructuring paper.
                                       In this ISR, total BOD load reduction as of June 30, 2020 is 1,475t. Target for 2020 (as of December 31,
                                       2020) is 2,777t. The breakdown of half-year result and target for 2020 are: Fuyang 1362 and 2500, Anren
                                       7 and 8, Meixi 106 and 250.
                                       The load reduction for Badu, Xiaomei, Chatian and Lanju WWTPs are still zero as of June 30, 2020. Their
                                       sewer networks are being completed and commissioning are planed for the second half of 2020. Their
   Comments:
                                       BOD load reduction targets are expected to be achieved in the next ISR and/or ICR.
                                       The BOD load reduction for Meixi WWTP in this ISR is lower than the last ISR. This is because Meixi
                                       WWTP receives industrial wastewater as well as domestic sewerage. The business of industries were
                                       affected by Covid-19 over the first half of 2020, but is expected to be resumed over the second half of the
                                       year so that the volume of influent BOD load is expected to be resumed and, consequently, the reduction
                                       of BOD load in the next ISR and/or ICR is expected to be increased.


     IN00883945
     Fuyang WWTP (Phase 4) (Tones/year, Custom Breakdown)

                                     Baseline                     Actual (Previous)            Actual (Current)            End Target

     Value                          0.00                         2,675.00                      1,362.00                    2,500.00

     Date                           22-Aug-2014                  31-Dec-2019                   30-Jun-2020                30-Jun-2021

     IN00883946
     Anren WWTP (Tones/year, Custom Breakdown)

                                     Baseline                     Actual (Previous)            Actual (Current)            End Target

     Value                          0.00                         6.90                          7.00                        15.00

     Date                           22-Aug-2014                  31-Dec-2019                   30-Jun-2020                30-Jun-2021

     IN00883947
     Badu WWTP (Tones/year, Custom Breakdown)

                                     Baseline                     Actual (Previous)            Actual (Current)            End Target

     Value                          0.00                         0.00                          0.00                        11.00

     Date                           22-Aug-2014                  31-Dec-2019                   30-Jun-2020                30-Jun-2021

     IN00883948
     Xiaomei WWTP (Tones/year, Custom Breakdown)

                                     Baseline                     Actual (Previous)            Actual (Current)            End Target

     Value                          0.00                         0.00                          0.00                        4.00

     Date                           22-Aug-2014                  31-Dec-2019                   30-Jun-2020                30-Jun-2021

     IN00883949
     Chatian WWTP (Tones/year, Custom Breakdown)

                                     Baseline                     Actual (Previous)            Actual (Current)            End Target

     Value                          0.00                         0.00                          0.00                        4.00

     Date                           22-Aug-2014                  31-May-2019                   30-Jun-2020                30-Jun-2021

     IN00883950


9/7/2020                                                                                                                      Page 4 of 8
           The World Bank                                                                                   Implementation Status & Results Report
           Zhejiang Rural Water Supply and Sanitation Project (P133018)




     Lanju WWTP (Tones/year, Custom Breakdown)

                                     Baseline                   Actual (Previous)            Actual (Current)           End Target

     Value                          0.00                        0.00                         0.00                       4.00

     Date                           22-Aug-2014                 31-Dec-2019                  30-Jun-2020               30-Jun-2021

     IN00883951
     Jinxi WWTP (Tones/year, Custom Breakdown)

                                     Baseline                   Actual (Previous)            Actual (Current)           End Target

     Value                          0.00                        0.00                         0.00                       3.00

     Date                           22-Aug-2014                 31-Dec-2019                  30-Jun-2020               30-Jun-2021

     IN00883952
     Meixi WWTP (Tones/year, Custom Breakdown)

                                     Baseline                   Actual (Previous)            Actual (Current)           End Target

     Value                          0.00                        255.00                       106.00                     255.00

     Date                           22-Aug-2014                 31-Dec-2019                  31-Dec-2019               30-Jun-2021

   IN00883953
   ►Ratio of production cost of water supply per cubic meter over the tariff charge per cubic meter (Anji Guoyuan Water Company) (Text,
   Custom)

                                      Baseline                    Actual (Previous)           Actual (Current)          End Target

    Value                             NA                         less than 1                  less than 1               less than 1

    Date                              22-Aug-2014                31-Dec-2019                  30-Jun-2020               30-Jun-2021

    IN00883954
    ►Ratio of production cost of water supply per cubic meter over the tariff charge per cubic meter (Fuyang Water Company) (Text, Custom)

                                      Baseline                    Actual (Previous)           Actual (Current)          End Target

    Value                             Less than 1                less than 1                  less than 1               Less than 1

    Date                              22-Aug-2014                31-Dec-2019                  30-Jun-2020               30-Jun-2021

    IN00883955
    ►Ratio of production cost of water supply per cubic meter over the tariff charge per cubic meter (Tiantai Water Company) (Text, Custom)

                                      Baseline                    Actual (Previous)           Actual (Current)          End Target

    Value                             less than 1                less than 1                  less than 1               less than 1

    Date                              22-Aug-2014                31-Dec-2019                  30-Jun-2020               30-Jun-2021

    IN00883956
    ►Ratio of production cost of water supply per cubic meter over the tariff charge per cubic meter (Longquan Water Company) (Text, Custom)

                                      Baseline                    Actual (Previous)           Actual (Current)          End Target

    Value                             less than 1                less than 1                  less than 1               less than 1


9/7/2020                                                                                                                   Page 5 of 8
           The World Bank                                                                                    Implementation Status & Results Report
           Zhejiang Rural Water Supply and Sanitation Project (P133018)




    Date                              22-Aug-2014                 31-Dec-2019                  30-Jun-2020               30-Jun-2021

   IN00883957
   ►Ratio of production cost of water supply per cubic meter over the tariff charge per cubic meter (Longquan Rural Water Supply Station)
   (Text, Custom)

                                      Baseline                    Actual (Previous)            Actual (Current)          End Target

    Value                             less than 1                 less than 1                  less than 1               less than 1

    Date                              22-Aug-2014                 31-Dec-2019                  30-Jun-2020               30-Jun-2021

   IN00883958
   ►Ratio of production cost of water supply per cubic meter over the tariff charge per cubic meter (Longquan Rural Water Affairs Co., ltd))
   (Text, Custom)

                                      Baseline                    Actual (Previous)            Actual (Current)          End Target

    Value                             NA                          NA                           NA                        less than 1

    Date                              17-Jun-2020                 17-Jun-2020                  17-Jun-2020               30-Jun-2021



   Training and Capacity Building

    IN00883941
    ►Number of staff training days in project financed training and TA activities (Number, Custom)

                                      Baseline                    Actual (Previous)            Actual (Current)          End Target

    Value                             0.00                        2,814.00                     2,865.00                  2,800.00

    Date                              22-Aug-2014                 31-Dec-2019                  30-Jun-2020               30-Jun-2021



   Project Management and Supervision

    IN00883942
    ►Number of O&M management plans prepared and implemented (Number, Custom)

                                      Baseline                    Actual (Previous)            Actual (Current)          End Target

    Value                             0.00                        5.00                         5.00                      6.00

    Date                              22-Aug-2014                 31-Dec-2019                  30-Jun-2020               30-Jun-2021
                                       The new PIU approved by the Bank in July 2020 is expected to submit its O&M plan to the Bank before
   Comments:                           end October 2020.



 Performance-Based Conditions



 Data on Financial Performance


 Disbursements (by loan)



9/7/2020                                                                                                                     Page 6 of 8
           The World Bank                                                                                     Implementation Status & Results Report
           Zhejiang Rural Water Supply and Sanitation Project (P133018)




 Project       Loan/Credit/TF     Status      Currency        Original    Revised     Cancelled     Disbursed       Undisbursed                % Disbursed


 P133018       IBRD-84240         Effective   USD             200.00       200.00           0.00         170.54           29.46                       85%


 Key Dates (by loan)

 Project        Loan/Credit/TF    Status      Approval Date       Signing Date      Effectiveness Date      Orig. Closing Date      Rev. Closing Date

 P133018        IBRD-84240        Effective   25-Sep-2014         25-Nov-2014       02-Feb-2015             31-Dec-2020             30-Jun-2021


Cumulative Disbursements




 PBC Disbursement

                                                                                         Achievement       Disbursed amount in         Disbursement %
 PBC ID                    PBC Type     Description            Coc        PBC Amount
                                                                                         Status            Coc                         for PBC




  Restructuring History


  Level 2 Approved on 24-Jul-2020


  Related Project(s)




9/7/2020                                                                                                                         Page 7 of 8
           The World Bank                                                 Implementation Status & Results Report
           Zhejiang Rural Water Supply and Sanitation Project (P133018)




  There are no related projects.




9/7/2020                                                                                 Page 8 of 8