Sample Procurement Plan (Text in italic font is meant for instruction to staff and should be deleted in the final version of the PP) (This is only a sample with the minimum content that is required to be included in the PAD. The detailed procurement plan is still mandatory for disclosure on the Bank’s website in accordance with the guidelines. The initial procurement plan will cover the first 18 months of the project and then updated annually or earlier as necessary). I. General 1. Bank’s approval Date of the procurement Plan [Original: December 2007]: Revision 15 of Updated Procurement Plan, June 2010] 2. Date of General Procurement Notice: Dec 24, 2006 3. Period covered by this procurement plan: The procurement period of project covered from year June 2010 to December 2012 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: [Thresholds for applicable procurement methods (not limited to the list below) will be determined by the Procurement Specialist /Procurement Accredited Staff based on the assessment of the implementing agency’s capacity.] Procurement Method Prior Review Threshold Comments US$ 1. ICB and LIB (Goods) Above US$ 500,000 All 2. NCB (Goods) Above US$ 100,000 First contract 3. ICB (Works) Above US$ 15 million All 4. NCB (Works) Above US$ 5 million All 5. (Non-Consultant Services) Below US$ 100,000 First contract [Add other methods if necessary] 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: [Refer to the relevant CDD project implementation document approved by the Bank or delete if not applicable] 4. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan Project XYZ 04/01/2010 issued by <mention name of PIU> July 9, 2010 5. Any Other Special Procurement Arrangements: [including advance procurement and retroactive financing, if applicable] 5 ICB works packages will be financed under retroactive financing 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness ( including those that are subject to retroactive financing and advanced procurement) [List the Packages which require Bank’s prior review first and then the other packages] 1 2 3 4 5 6 7 Ref. Description Estimated Packages Domest Review Comments No. Cost ic by Bank US$ Prefere (Prior / Post) million nce (yes/no) Summary of 82 5 No Prior the ICB (Works) Summary of 43.77 15 No Prior the ICB (Goods) Summary of 64.53 18 No Post 1st the NCB contract (Works) for Prior Review Summary of 1.86 4 No Post 1st the NCB contract (Goods) for Prior Review Summary of 0.45 1 No Prior the ICB (Non- Consultant Services) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Threshold Comments 1. Competitive Methods (Firms) Above US$ 100,000 2. Single Source (Firms) All 3. Individual Above US$ 50,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise July 9, 2010 entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: [including advance procurement and retroactive financing, if applicable or delete if not applicable] 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description of Estimated Packages Review Comments Assignment Cost by Bank US$ (Prior / million Post) Summary of 4.17 7 Prior number of contracts that will be let under QCBS Summary of 0.83 1 Prior CQS number of contracts that will be let under other methods July 9, 2010 PROCUREMENT Kazakhstan : SME Competitiveness Project PLAN General Information Country: Kazakhstan Banks Approval Date of the Original Procurement Plan: 2017-11-06 Revised Plan Date(s): (comma delineated, leave blank if none) 2018-07-18 Project ID: P147705 GPN Date: Project Name: SME Competitiveness Project Loan / Credit No: IBRD / 84770 Executing Agency(ies): Ministry of National Economy WORKS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GOODS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KZ/SMEC/NCB-01 / IT & Office 1. SME Capacity Building Request for Single Stage - One Pending IBRD / 84770 Post Open - National 300,000.00 0.00 2018-10-06 2018-12-12 2019-12-12 equipment for Component 1 Program Quotations Envelope Implementation KZ/SMEC/CII/SH-01 / Office 2. SME Linkages in Competitive Request for Single Stage - One Pending IBRD / 84770 Post Open - National 100,000.00 0.00 2018-09-07 2018-11-13 2019-11-13 computer equipment Sectors Quotations Envelope Implementation KZ/SMEC/CII/SH-02 / Office 2. SME Linkages in Competitive Request for Single Stage - One Pending IBRD / 84770 Post Open - National 100,000.00 0.00 2018-09-07 2018-11-13 2019-11-13 furniture Sectors Quotations Envelope Implementation KZ/SMEC/CII/SH-03 / office 2. SME Linkages in Competitive Request for Single Stage - One Pending IBRD / 84770 Post Open - National 68.00 0.00 2018-09-07 2018-11-13 2019-11-13 stationary Sectors Quotations Envelope Implementation KZ/SMEC/ICB-01 / Software and 2. SME Linkages in Competitive Request for Single Stage - One Pending IBRD / 84770 Prior Open - International 1,000,000.00 0.00 2018-10-01 2018-10-06 2018-11-17 2018-11-27 2018-12-17 2019-12-17 equipment for factoring platform Sectors Proposals Envelope Implementation NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Technical Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 1. SME Capacity Building KZ/SMEC/QCBS-01 / Program KZ/SMEC/QCBS-01 - 4. Project Management Elaboration of State Nonfinancial Quality And Cost- Under IBRD / 84770 3. Impact Evaluations & Prior Open - International N 0.00 960,000.00 2017-08-31 Support Development Strategy Based Selection Implementation Monitoring and Improving Stakeholder 2. SME Linkages in Competitive Competences Sectors 1. SME Capacity Building KZ/SMEC/QCBS-06 / Program KZ/SMEC/QCBS-06-TA to KZ 4. Project Management Quality And Cost- Industry Development Institute on IBRD / 84770 3. Impact Evaluations & Prior Open - International N 0.00 2,652,042.90 Signed 2016-12-12 2016-12-14 Based Selection Implementing Cluster Policy in Monitoring the Regions of KZ 2. SME Linkages in Competitive Sectors 1. SME Capacity Building KZ/SMEC/QCBS-05 / Program KZ/SMEC/QCBS-05-Capacity 4. Project Management Quality And Cost- Building of Kazakhstan Industry IBRD / 84770 3. Impact Evaluations & Prior Open - International N 500,000.00 348,445.00 Signed 2016-12-07 2016-12-08 Based Selection Development Institute on Cluster Monitoring Policy Deployment 2. SME Linkages in Competitive Sectors KZ/SMEC/QCBS-07 / Development of feasibility study for the creation of a factoring 2. SME Linkages in Competitive Quality And Cost- Under platform in the Republic of IBRD / 84770 Prior Open - International 1,000,000.00 0.00 2017-11-14 2017-11-17 2017-11-27 2017-11-24 2018-01-25 2018-02-04 2018-02-24 2018-03-14 2018-03-26 2018-04-25 2018-04-30 2018-05-11 2018-06-04 2019-12-04 Sectors Based Selection Implementation Kazakhstan and enhancing the competence of relevant stakeholders KZ/SMEC/QCBS-09 / Conducting an impact evaluation of programs on support of small 3. Impact Evaluations & Quality And Cost- IBRD / 84770 Prior Open - International 1,500,000.00 949,938.00 Signed 2017-11-14 2017-11-17 2017-11-27 2017-11-17 2018-01-25 2018-01-22 2018-02-24 2018-02-28 2018-03-26 2018-04-23 2018-04-30 2018-05-16 2018-06-04 2018-06-25 2019-12-04 and medium sized enterprises Monitoring Based Selection and providing training for capacity building of key stakeholders KZ/SMEC/QCBS-04 / Services for the establishment of the Supplier Development Service, its 2. SME Linkages in Competitive Quality And Cost- Under IBRD / 84770 Prior Open - International 7,700,000.00 0.00 2017-11-23 2018-01-15 2017-11-30 2018-01-18 2018-01-13 2018-03-30 2018-02-10 2018-05-29 2018-03-12 2018-04-16 2018-05-21 2019-11-20 capacity building and Sectors Based Selection Implementation implementation of supplier development pilot projects KZ/SMEC/QCBS-10 / Services on conducting the national baseline survey of the state of small and medium sized 3. Impact Evaluations & Quality And Cost- Under IBRD / 84770 Prior Open - International 1,500,000.00 0.00 2018-01-25 2018-02-14 2018-01-31 2018-02-15 2018-03-03 2018-04-13 2018-04-02 2018-06-04 2018-05-02 2018-05-26 2018-06-19 2019-08-18 enterprises sector in Kazakhstan Monitoring Based Selection Implementation and development of the Concept of small and medium sized enterprises development Page 1 KZ/SMEC/QCBS-11 / Services on conducting an assessment of the transparancy of policies and the legislative framework in the 3. Impact Evaluations & Quality And Cost- sphere of microfinance support of IBRD / 84770 Prior Open - International 1,500,000.00 0.00 Under Review 2018-01-29 2018-01-31 2018-03-14 2018-04-13 2018-04-28 2018-05-29 2018-06-29 2019-04-25 Monitoring Based Selection SMEs in Kazakhstan and recomend a feasibility model of funding microfinance organizations KZ/SMEC/CQS-02-2 / Services on developing and conducting of Consultant 1. SME Capacity Building Pending information campaign on IBRD / 84770 Post Qualification Open - National 200,000.00 0.00 2018-05-01 2018-05-06 2018-06-19 2018-07-19 2018-08-23 2019-06-19 Program Implementation implementation of SME Selection Competitiveness Project KZ/SMEC/CQS-02 / Provision of services for conducting an Consultant Outreach Campaign for 1. SME Capacity Building Under IBRD / 84770 Post Qualification Open - National 300,000.00 0.00 2018-02-07 2018-02-05 2018-02-12 2018-03-28 2018-04-10 2018-04-27 2018-07-11 2018-06-01 2019-03-28 implementation of the project Program Implementation Selection "Small and Medium-Sized Enterprises Competitiveness" KZ/SMEC/QCBS-02 / Services for the creation of a system for preparation of business 1. SME Capacity Building Quality And Cost- Pending IBRD / 84770 Prior Open - International 1,900,000.00 0.00 2018-07-15 2018-07-29 2018-09-07 2018-10-07 2018-10-27 2018-11-20 2018-12-14 2020-04-07 consultants and conducting Program Based Selection Implementation training for business consultants and SMEs INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Contract Type Estimated Actual Amount Draft Negotiated Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 2