The World Bank
                             Transmission Investment Plan (PIT) Program to support Post-COVID-19 Economic Recovery in Peru (P174812)




                                   Appraisal Environmental and Social Review Summary
                                                                Appraisal Stage
                                                          (ESRS Appraisal Stage)
Public Disclosure




                                             Date Prepared/Updated: 06/21/2021 | Report No: ESRSA01549




                    Jun 22, 2021                                                                                             Page 1 of 17
                               The World Bank
                               Transmission Investment Plan (PIT) Program to support Post-COVID-19 Economic Recovery in Peru (P174812)



                     BASIC INFORMATION

                     A. Basic Project Data

                     Country                       Region                           Project ID                     Parent Project ID (if any)

                     Peru                          LATIN AMERICA AND                P174812
                                                   CARIBBEAN

                     Project Name                  Transmission Investment Plan (PIT) Program to support Post-COVID-19 Economic
                                                   Recovery in Peru

                     Practice Area (Lead)          Financing Instrument             Estimated Appraisal Date       Estimated Board Date

                     Energy & Extractives          Investment Project               6/14/2021                      11/30/2021
                                                   Financing

                     Borrower(s)                   Implementing Agency(ies)

                     Ministry of Economy and       Ministry of Energy and
                     Finance                       Mines
Public Disclosure




                     Proposed Development Objective
                     To increase the availability and reliability in selected areas of Peru and support the modernization of the power sector
                     regulatory framework.


                     Financing (in USD Million)                                                                                          Amount

                      Total Project Cost                                                                                                     87.50



                     B. Is the project being prepared in a Situation of Urgent Need of Assistance or Capacity Constraints, as per Bank IPF
                     Policy, para. 12?
                     No


                     C. Summary Description of Proposed Project [including overview of Country, Sectoral & Institutional Contexts and
                     Relationship to CPF]
                     The proposed activity focuses on investing in subtransmission infrastructure to help increase the availability and
                     reliability of electricity service and greening of electricity supply to accelerate COVID-19 recovery in Peru and to also
                     facilitate overcoming regulatory shortcomings to help modernize the power sector. Delayed investments by the public
                     electricity distribution companies hinder meeting existing and new electricity demand and are causing emergency
                     situations in various departments of Peru where polluting emergency diesel generation has to be used to overcome
                     the resulting electricity supply issues. This constrains economic activities at the regional level, increases electricity

                    Jun 22, 2021                                                                                                        Page 2 of 17
                              The World Bank
                              Transmission Investment Plan (PIT) Program to support Post-COVID-19 Economic Recovery in Peru (P174812)



                     supply costs, and causes local environmental pollution, which negatively impacts the populations in these regions
                     including the poorer and more vulnerable populations. The COVID-19 crisis has further delayed critical electricity
                     system investments, putting at risk the reliability of electricity provision for health facilities and for remote learning
                     and working. If not addressed, important secondary cities and peri-urban areas may soon face service disruptions,
                     new electricity customers be turned away and existing commercial and industrial customers unable to expand
                     production due to the electricity supply constraints resulting from the lack of PIT investments in these areas. This
                     situation also undermines the provision of electricity to power critical services and economic activities in these areas
                     and the prospects for inclusive and greener economic recovery. The Government also is seeking to modernize the
                     power sector’s institutional and regulatory framework to facilitate greater uptake of clean energy technologies,
                     increase private sector participation as market agents, and to enhance power system reliability and financial
                     sustainability. This would also include measures to facilitate improving electricity service delivery to enable
                     distribution companies to become more resilient for facing emergencies such as climate and disaster risks and the
                     current COVID pandemic.

                     The proposed project will finance critical electricity system investments needed to increase electricity service
                     availability, reliability, and greener provision of electricity supply for meeting existing and new electricity demand. The
                     project will include the following project components: (i) strengthening and expansion of substations and
                     transmission lines; (ii) technical assistance for regulatory strengthening; and (iii) project management and capacity
                     building. The Ministry of Energy and Mines (MINEM), through its General Directorate of Rural Electrification (DGER)
                     would be responsible for implementing the project in close coordination with the country's public electricity
                     distribution companies.
Public Disclosure




                     This investment and regulatory support is essential to furthering the Government's post-COVID economic recovery
                     efforts by increasing the availability, reliability, and sustainability of electricity service to sustain the economy and
                     enhance social welfare in selected areas of Peru following the COVID-19 crisis to ensure that these regions are not left
                     behind.



                     D. Environmental and Social Overview
                     D.1. Detailed project location(s) and salient physical characteristics relevant to the E&S assessment [geographic,
                     environmental, social]
                     D.1. Detailed project location(s) and salient physical characteristics relevant to the E&S assessment [geographic,
                     environmental, social]

                     Out of the 3 components to be financed by the project, social and/or environmental impacts are expected to arise
                     from the implementation of those interventions to be financed under Component 1, comprised by four types of
                     investments: (i) expansion and reinforcement of existing power transformation substations; (ii) repowering of existing
                     transmission lines within existing rights-of-way; (iii) new substations; and (iv) new transmission lines. The
                     interventions will be chosen from a list of priority investments identified by MINEM and the public distribution
                     companies. The long list of potential investments includes 52 investments located in 16 of the 24 regions (also called
                     Departments) of Peru covering urban, peri-urban, and rural areas and cover the coastal, highlands, and Amazon
                     regions.


                    Jun 22, 2021                                                                                                        Page 3 of 17
                              The World Bank
                              Transmission Investment Plan (PIT) Program to support Post-COVID-19 Economic Recovery in Peru (P174812)



                     Their regions and locations are:

                     San Martin: Moyobamba, Picota
                     Cajamarca: Jaén
                     Loreto: Yurimaguas
                     Amazonas: Bagua Grande
                     Ucayali: Manantay, Campoverde
                     Ayacucho: Ayacucho
                     Junin: Chanchamayo,
                     Puno: Puno, Juliaca, Azángaro, Ayaviri
                     Madre de Dios: Puerto Maldonado
                     Cusco: Cusco
                     Apurimac: Apurimac
                     Lambayeque: Chiclayo
                     Arequipa: Arequipa
                     Moquegua: Moquegua
                     Tacna: Tacna,
                     Piura: Sullana, Morropón

                     The Emergency Decree 048-2021 (05.24.21) that exceptionally authorizes the Ministry of Energy and Mines to
                     develop the “Transmission Investment Plan – PIT” Program of the electricity distribution companies under the scope
Public Disclosure




                     of the National Fund for Financing of the State's Business Activity – FONAFE, states in its considerations that projects
                     have been selected because in the areas where they will be developed there are hospitals and health centers, which
                     by not having a guaranteed power supply will put at risk the attention to emergencies such as the supply of oxygen,
                     operationalization of ICU beds, monitoring of patients infected with COVID-19 and all the infrastructure necessary to
                     address the pandemic.

                     Environmental context:
                     According to the National Environmental Information System (SINIA) of the Ministry of Environment (MINAM), these
                     16 regions cover five natural regions of the country (Tropical Forest, Yunga, Andean, Coastal, and Aquatic Ecosystems)
                     and different types of ecosystems according to the National Ecosystem Map, among which are: savannas, mountain
                     forest, dry puna, paramos, high altitude wetland, scrublands, and coastal desert. The country's forest coverage is
                     estimated at 56.8% (2018 data) according to the World Bank geoportal and 60% according to MINAM. In this context,
                     the potential environmental risks that could be generated in the planning and construction stages of the subprojects
                     to be financed will be related to the physical and biological characteristics of the area where each subproject will be
                     implemented. Additionally, the potential impacts of each subproject will depend on factors related mainly to the
                     proposed design, the precise location, the routes of the power lines, the extent of the works, and the
                     electromechanical equipment to be installed or replaced.

                     Social context:
                     The interventions that will be financed under Component 1 will be situated mainly in urban and peri-urban areas of
                     provincial cities, such as district capitals, and a few rural areas in the periphery of cities of yet unknown social
                     characteristics. The investments to be financed by the Project will be carried out exclusively by public distribution
                     companies’ infrastructure linked to the Interconnected National Electric System and subprojects that cause physical
                    Jun 22, 2021                                                                                                      Page 4 of 17
                              The World Bank
                              Transmission Investment Plan (PIT) Program to support Post-COVID-19 Economic Recovery in Peru (P174812)



                     displacement of formal and informal occupants would not be eligible. The proposed investments will benefit a variety
                     of stakeholders such as end users, both private and institutional (populations that receive the electricity services,
                     businesses, service providers such as health care facilities and education sector, government agencies, among others),
                     as well as third parties that seek and/or receive services from these end users of the electricity service, including
                     vulnerable and disadvantaged groups and individuals (such as people with disabilities and the poorest, city dwellers
                     from disadvantaged indigenous or ethnic groups, and afro descendants, among others). The project is designed to be
                     carried out in 16 regions located in the Andes and the Peruvian Amazon. Within these regions, the provinces where
                     the subprojects will be carried out are characterized by the low quality of basic social infrastructure in health,
                     education, sanitation, housing, transportation and communications, as well as the low presence of productive
                     economic infrastructure. In these scenarios of low presence of state institutions and formal markets, these projects
                     could generate positive effects on the social and economic life of the end beneficiaries. In these places, urban and
                     peri-urban contexts (mainly district capitals) are characterized by low population density, traditional lifestyles and
                     economies that combine services with agricultural activities. On the other hand, rural contexts are characterized by
                     dispersed settlement patterns, dedication mainly to agriculture and cattle raising, and the presence of vulnerable
                     peasant communities in the Andes and native communities in the Amazon. Aspects such as settlement patterns of the
                     population centers, land ownership, use of natural resources, economic activity, among others, will be considered in
                     the identification and evaluation of specific subprojects’ social risks.
                     D. 2. Borrower’s Institutional Capacity
                     The project will be implemented by the Ministry of Energy and Mines (Ministerio de Energía y Minas - MINEM)
                     through the Directorate General of Rural Electrification (Dirección General de Electrificación Rural - DGER) and within
                     this Directorate, the Directorate of Competitive Funds (Dirección de Fondos Concursables - DFC).
Public Disclosure




                     To date, the following institutional actors have been identified: i) DGER as the executing agency and Project overseer;
                     ii) DFC as the coordinating unit and PIU; iii) distribution companies which through contract administration will ensure
                     that national, local and the World Bank E&S requirements are put in place; iv) contractors which will be responsible
                     for implementing measures, actions and plans embodied in the E&S site-specific instruments; and v) supervisors of
                     civil works, which will supervise and monitor contractors’ compliance with the national and the World Bank E&S
                     requirements.

                     DGER/DFC currently lacks the institutional capacity to manage the E&S aspects of the Project. During preparation one-
                     time external consultants were hired to prepare the Borrower’s environmental and social risk management
                     instruments and DGER/DFC had no experienced E&S specialists available to supervise the work of the consultants or
                     to work with World Bank’s E&S specialists. For the implementation phase of the Project, DGER agreed to create an
                     E&S management unit as part of its PIU, which will comprise an E&S Coordinator, a full-time environmental specialist
                     and a full-time social specialist, who will ensure E&S management in accordance with the Project’s E&S instruments.
                     The PIU will be staffed following Project Effectiveness and these institutional capacity commitments will be clearly set
                     out in the ESCP.

                     In order to achieve adequate environmental and social management, all mapped actors will need to develop their
                     capacity to comply with the Project’s E&S standards; therefore, once the PIU, distribution companies, contractors and
                     supervision companies have been identified, a new assessment should be carried out to determine their capacity
                     development needs. Relevant actions from the assessment will be included in the Project’s Environmental and Social
                     Commitment Plan (ESCP), promoting the strengthening of the Borrower’s capacity.


                    Jun 22, 2021                                                                                                     Page 5 of 17
                              The World Bank
                              Transmission Investment Plan (PIT) Program to support Post-COVID-19 Economic Recovery in Peru (P174812)



                     II. SUMMARY OF ENVIRONMENTAL AND SOCIAL (ES) RISKS AND IMPACTS

                       A. Environmental and Social Risk Classification (ESRC)                                                          Moderate


                       Environmental Risk Rating                                                                                       Moderate
                       The environmental proposed risk classification for the Project is Moderate. Classification responds to the scale of the
                       activities, which relates to expansion and strengthening of existing power transformation substations, repowering of
                       existing transmission lines within existing rights of way, new substations and new transmission lines, which
                       correspond to routine and construction activities that have been previously carried out by the distribution
                       companies. Potential preliminary risks and impacts are: (i) not likely to be significant, comprising mostly of small
                       nuisances during construction and assembly works; (ii) not expected to be complex, with existing mitigation and
                       management mechanisms in place that have been proven to be effective; (iii) predictable and expected to occur
                       only during construction; (iv) site-specific, with Project activities taking place within fenced areas, and without the
                       likelihood of impacts beyond the Project footprint; (v) low probability of serious adverse effects to human health
                       and/or the environment, although hazardous materials containing Polychlorinated Biphenyls (PCBs) will be required
                       to be managed as hazardous waste during parts replacements following local regulations and international
                       agreements; (vi) routine safety precautions as related to civil works and assembly of electrical parts are sufficient to
                       prevent accidents, and; (vii) will be easily mitigated in a predictable manner. The most relevant potential
                       environmental risks preliminary identified to date are: • Those related to the generation of hazardous wastes which
                       will likely contain PCBs, and its inadequate transportation, storage, and/or disposal. The generation of these types of
Public Disclosure




                       waste will be assessed, and strict management measures put in place for adequate and safe handling,
                       transportation, and treatment or disposal. These measures will follow the WBG General EHS Guidelines, and local
                       regulations specific to these hazardous wastes. PCB management plan(s) will be prepared considering these
                       guidelines, to respond to the needs of each investment. • The increase in transportation activities will also pose risks
                       related to possible environmental pollution due to normal vehicle operations, possible incidents or accidents, as well
                       as possible impacts to the workforce, however, these risks are predictable and prevention and mitigation measures
                       are easy to implement. • Potential environmental impacts will be small nuisances such as noise, dust, and air
                       emissions. These are not to reach community members as substations are located at a safe distance from receptors.
                       Some clearance of vegetation may be required; however, this would involve work in areas that are already modified
                       and/or not legally protected. Components 2 and 3 of the Project are not considered to generate environmental
                       impacts, since they are focused on administrative activities related to technical assistance for regulatory
                       strengthening and Project management and capacity building. Should the Project be implemented during the
                       COVID-19 (C19) emergency, the ESMF will consider measures for surveilling workers' health and avoiding
                       transmission of C19 from project workers to local communities and vice versa. These measures will consider: (i)
                       workers screening before traveling to project sites, (ii) maintaining social distancing, (iii) providing adequate PPE, (iv)
                       setting up disinfection protocols, and (iv) contingency plans in the event someone showing symptoms or carrying
                       SARS-CoV-2, among others. If more information becomes available in the future or the Project is updated, the
                       environmental risk rating will need to be reviewed to ensure that it reflects the environmental risks and impacts
                       generated as subprojects are identified and assessments are done.
                       Social Risk Rating                                                                                              Moderate
                       The social proposed risk classification for the Project is Moderate. This classification responds to the scale and
                       magnitude of potential social impacts in the context of implementation of the four types of subprojects to be

                    Jun 22, 2021                                                                                                         Page 6 of 17
                              The World Bank
                              Transmission Investment Plan (PIT) Program to support Post-COVID-19 Economic Recovery in Peru (P174812)



                       financed (refer to section D). The subprojects are expected to produce a number of benefits. However, since they
                       involve new infrastructure, they could also potentially generate negative social impacts. Potential social impacts are:
                       (i) temporary access restrictions, (ii) inconvenience to locals due to air pollution from dust and noise from the works,
                       (iii) increased traffic, (iv) community health and safety risks (communicable diseases, increased incidents of road
                       accidents), and (v) land acquisition and/or temporary or permanent restrictions on land use, among others. Land
                       acquisition or land use restrictions could affect vulnerable people whose economic and social activities depend on
                       the land and its resources. The project is not expected to support any subprojects that would generate physical
                       displacement; however, it could finance subprojects that may cause economic displacements under certain
                       conditions as stipulated in the Resettlement Framework prepared for the Project. Also, the project will not finance
                       subprojects that could adversely affect indigenous communities and their lands. In the case of investments in new
                       substations and new transmission lines, especially those located in peri-urban and rural areas, the social impacts
                       would be highly positive, due to the infrastructure and services gap in general that hinders the development of
                       these areas and the wellbeing of its inhabitants, according to the National Rural Electricity Plan (MINEM, 2010). The
                       project will benefit electricity end users, including vulnerable groups in underserved areas, by strengthening existing
                       energy systems and providing more stable access and delivery of electricity service. These activities will, in turn,
                       provide local development opportunities and improve the social welfare and living conditions of end-users.
                       Dissemination of project information (design, proposed investments, job opportunities, opportunities for the
                       provision of local goods and services, environmental and social management, etc.) and access to grievance
                       mechanisms, aligned with the Stakeholder Engagement Plan (SEP) prepared under ESS10, will create a mechanism to
                       address beneficiary concerns, manage expectations and collect stakeholder suggestions. Regarding workers, the
                       Borrower will prepare labor management procedures (LMP) in line with ESS 2, and a project-level Environmental and
Public Disclosure




                       Social Management Framework (ESMF) will provide guidelines to identify and manage project risks, impacts, and
                       opportunities once investment selection is carried out and substations and transmission lines locations are known.
                       Although the level of risk related to sexual exploitation and abuse (SEA) and sexual harassment (SH) is considered
                       Low at the Appraisal stage, this risk will be further reassessed when specific information is available on the
                       subprojects to be financed, particularly their locations and social characteristics. Similarly, the social risk will be
                       continuously assessed and measures to increase social inclusiveness will be explored, through stakeholder
                       consultation at the subproject level. The World Bank will periodically review the risk rating assigned to the Project,
                       including during Project implementation, and modify the rating as necessary, in line with adaptive management, to
                       ensure that the risk and the E&S risk mitigation measures proposed remain adequate.


                     B. Environment and Social Standards (ESSs) that Apply to the Activities Being Considered

                     B.1. General Assessment

                     ESS1 Assessment and Management of Environmental and Social Risks and Impacts
                     Overview of the relevance of the Standard for the Project:
                     This standard is relevant.

                     The Ruling for the Environmental Protection in Electrical Activities (“Ruling”), approved by Supreme Decree (SD) 014-
                     2019-EM establishes that in the cases where the developer has a pre-existing “Environmental Study” or a
                     complementary “Environmental Management Instrument” for an electrical facility and wishes to carry out an
                     extension and/or modification of its original Project, it must apply for a modification of its Environmental License

                    Jun 22, 2021                                                                                                       Page 7 of 17
                              The World Bank
                              Transmission Investment Plan (PIT) Program to support Post-COVID-19 Economic Recovery in Peru (P174812)



                     through the submission of an “Environmental Management Instrument” specific for this change. The “Environmental
                     Management Instrument” to be used to request such change will depend upon the scope of the change asked and
                     the level of the original “Environmental Management Instrument” (per national law, that includes a detailed EIA,
                     semi-detailed EIA, or a Declaration of Environmental Impact, DIA, depending on potential adverse impacts and risk).
                     This would apply to the expansion of substations or replacement of transformers under Component 1, which are
                     expected to be operating under an existing Environmental Instrument. On the other hand, this Ruling also indicates
                     that rural electrical systems of generation of electricity up to 1500 kW should carry out a DIA. Notwithstanding the
                     foregoing, DGER/DFC will coordinate with the distribution companies to update or obtain new licenses for all the
                     investments to be implemented under component 1, in full compliance of national and local laws and regulations.
                     The Project ESMF – to be finalized at the latest within 30 days of Effectiveness, but available in advanced draft by
                     Project Appraisal for consultation – lays out the process by which gaps between national laws and the World Bank’s
                     ESF will be filled to allow a comprehensive set of instruments to attach to the bidding process for contractors.

                     Environmental impacts preliminarily identified:

                     - Noise, dust, and air emissions generation. Small nuisances to the surrounding communities are expected to occur
                     during the works. Dust generation is expected to be low in magnitude and not to reach nearby houses or sensitive
                     areas outside the fenced areas in a manner that affects them. Noise and air emissions generated from the use of
                     construction equipment are also unlikely to seriously affect surrounding communities. An assessment of the
                     potential measures to address these impacts will be carried out according to the environmental instruments
                     applicable for each investment.
Public Disclosure




                     - Clearance of vegetation consisting of small bushes and grasses or previously disturbed sites outside environmentally
                     protected areas. For safety purposes, it may be required to clear vegetation that may be present within the fenced
                     areas or ROWs. A site visit (or if not possible, photos) will provide information on this to assess its need before
                     construction or installation activities.

                     - Generation, transport, and disposal of hazardous wastes which will likely contain PCBs. Old transformers are likely
                     to have PCBs, so the replacement of these transformers and expansion of substations will generate this type of
                     hazardous waste. During Project preparation, DGER/DFC through the distribution companies will assess the possibility
                     of encountering these wastes and the adequate disposal and/or treatment methods available and compliant with
                     local regulations and international best practices, including those from the General EHS guidelines focusing on Waste
                     Management.

                     - Occupational health and safety risks are those common from works at substations and electricity facilities. They are
                     related to works with energized equipment, working at heights, transportation of equipment, and from the
                     manipulation of materials potentially contaminated with hazardous oils, including PCBs. Environmental and
                     occupational health and safety impacts and risks will be assessed, and guidelines for each specific impact and risk will
                     be developed. These guidelines will build from the General EHS Guidelines and Industry Specific Guidelines.

                     Social impacts preliminarily identified:




                    Jun 22, 2021                                                                                                     Page 8 of 17
                              The World Bank
                              Transmission Investment Plan (PIT) Program to support Post-COVID-19 Economic Recovery in Peru (P174812)



                     - Temporary access restrictions to businesses and houses. Due to construction activities, transportation of supplies
                     and materials, personnel, etc., required for all four types of investments.

                     - Inconvenience for local inhabitants due to air pollution from dust, vibrations and noise from the construction work.
                     Construction activities could generate environmental impacts affecting the local population, especially those located
                     near the work area.

                     - Increased traffic. The number of vehicles and frequency of transport will increase as construction activities develop,
                     which could generate traffic episodes and an increase in the presence of heavy machinery.

                     - Risks to community health and safety. Peru is currently in a state of health emergency and the presence of foreign
                     workers could lead to the possible spread of COVID-19 and other contagious diseases. Also, the increase in traffic
                     increases the risk of traffic accidents. Is important to consider the risk of environmental impacts that are not
                     adequately mitigated.

                     - Land acquisition and/or temporary or permanent restrictions on economic use. Particularly for subproject
                     investments corresponding to type 3 and 4 investments, i.e. new substations, and transmission lines, here new
                     infrastructure may require land acquisition or permanent rights of way.

                     Given the lack of knowledge regarding the specific locations where the proposed investments would be made, the
                     borrower has prepared an Environmental and Social Management Framework (ESMF) to help screen activities once
Public Disclosure




                     locations and scope of works are known. This ESMF provides guidelines on (i) subproject eligibility criteria, (ii)
                     procedures for screening subprojects for E&S risks and impacts, (iii) proposed methodologies for carrying out the
                     environmental and social risk assessment of the Project, and (iv) guidelines for developing a gap analysis between the
                     national environmental and social instrument of each subproject and the World Bank’s environmental and social
                     standards, among main issues addressed in the ESMF. The draft ESMF was disclosed for purposes of public
                     consultations on June 4 (for more details on stakeholder engagement see ESS10 below). Further to public
                     consultations, the ESMF will be revised and finalized (incorporating stakeholder opinions), adopted and disclosed by
                     the Borrower no later than 30 days after Effectiveness, as set out in the ESCP.

                     However, during Project preparation the Borrower, through DGER, already identified a group of seven specific
                     subprojects to be part of the first financed package under the Project once the Loan Agreement is signed. Thus, the
                     E&S assessment for subprojects under the Project is to be conducted under two scenarios:

                     •        For the seven specific investments identified during Project preparation, the DGER, as per World Bank’s ESSs,
                     submitted to the Bank the site-specific environmental and social instruments prepared to comply with the national
                     legislation. Since gaps with the ESF have been identified, supplemental studies to the existing E&S instruments will
                     have to be carried out prior to the bidding process to ensure that relevant E&S requirements identified through these
                     studies become binding commitments as part of the awarded contract(s). No site-specific investment (civil works) will
                     be carried out without prior preparation and implementation of E&S instruments to the satisfaction of the Bank, in
                     line with the ESSs. This will be clearly set out in the ESCP.




                    Jun 22, 2021                                                                                                     Page 9 of 17
                              The World Bank
                              Transmission Investment Plan (PIT) Program to support Post-COVID-19 Economic Recovery in Peru (P174812)



                     •       Any other subprojects to be identified and included for financing under the Project during its implementation
                     must meet the E&S eligibility criteria embodied in the Environmental and Social Management Framework and need
                     to be prepared in line with this and other applicable instruments (e.g., the Resettlement Framework). The ESMF
                     developed by DGER explains the methodology to be followed to ensure the eligibility of the subprojects in relation to
                     these three criteria and subsequent processes to ensure the adequate environmental and social management of the
                     selected subprojects to Bank’s satisfaction.

                     In order to adequately manage the risks preliminary identified during the environmental and social due diligence
                     (DD), an Environmental and Social Commitment Plan (ESCP) will be agreed between MINEM/DGER and the World
                     Bank, which reflects the responsibilities of the Project's institutional actors with respect to environmental and social
                     management and establishes the deadlines for the execution of each agreed action.



                     ESS10 Stakeholder Engagement and Information Disclosure
                     This standard is relevant.

                     Key stakeholders include institutions such as MINEM, DFC/DGER, and FONAFE, as well as relevant non-governmental
                     stakeholders, as well as the population that could be impacted by the investments and/or would benefit
                     (beneficiaries) from the improved electricity service where the Project investments will be made. Beneficiaries (end
                     users) encompass different subgroups such as local governments and agencies that provide services to citizens
Public Disclosure




                     including disadvantaged and vulnerable people and groups, economic agents (micro, small, medium and large
                     enterprises, business, industries, etc.), health care and education facilities, among others. DGER has prepared a draft
                     Stakeholder Engagement Plan (SEP), proportionate to the risk of the Project, that was disclosed on June 4
                     (http://dger.minem.gob.pe/Transparencia/PIT/PIT-DGER.pdf,), along with the ESMF, RF and LMP, and consulted on
                     June 10th, before Project appraisal, through a virtual workshop with 100 registered participants. These included
                     regional authorities from Apurímac, Arequipa, Junín, Piura, Puno, San Martín, Tacna, and Ucayali; representatives of
                     Distribution Electricity Companies that would benefit from the Project, and representatives from OSINERGMIN, MEF,
                     and consulting firms. The draft SEP includes the results of key stakeholders mapping for the Project and a Grievance
                     Redress Mechanism (GRM) that will be ready and publicly available to process any complaints resulting from Project
                     activities as soon the final SEP is published. Beneficiaries will be informed about the availability of this Mechanism as
                     soon as the draft SEP is published. The final SEP will be adopted and disclosed by the Borrower within 30 days of the
                     Project’s effectiveness date as set out in the ESCP. All technical information and ESF compliance requirements will be
                     disclosed in an ongoing manner and in a way that is satisfactory to the Bank. Also, once the location and scope of the
                     specific intervention are known, each intervention will be screened following ESMF guidelines (ESS 1) and this will
                     include a stakeholder mapping to engage local stakeholders, using culturally appropriate approaches and materials
                     whenever necessary, to address specific concerns and risks identified by these stakeholders, including risks to
                     vulnerable people, security and/or safety risks affecting the delivery of services, past social liabilities regarding access
                     and service or related to past electrification Projects, etc.

                     Due to the ongoing pandemic, the Borrower will carry out consultations and other participatory engagements
                     respecting WHO’s guidelines and existing national norms related to this issue such as the Legislative Decree N° 1500
                     (05.11. 2020) which establishes special measures to reactivate, improve and optimize the execution of public, private


                    Jun 22, 2021                                                                                                        Page 10 of 17
                              The World Bank
                              Transmission Investment Plan (PIT) Program to support Post-COVID-19 Economic Recovery in Peru (P174812)



                     and public-private investment projects in view of the impact of COVID-19, as well as the Technical Note on “Public
                     Consultations and Stakeholder Engagement in WB-supported operations when there are constraints on conducting
                     public meetings” (March 2020). Remote engagement strategies will be preferred whenever feasible. When in-person
                     engagement activities need to be carried out to ensure robust and inclusive engagement with key stakeholders, all
                     necessary precautions will be taken to protect Project personnel and the stakeholders involved in the activities.


                     B.2. Specific Risks and Impacts

                     A brief description of the potential environmental and social risks and impacts relevant to the Project.
                     ESS2 Labor and Working Conditions
                     This standard is relevant.

                     Project workforce will include direct workers (consultants working in the PIU), civil servants (staff working in the
                     Project of MINEM/DFC/DGER/FONAFE, the state holding corporation National Fund for Financing of State Companies
                     that manages the 11 public distribution companies), and contracted workers (contractors, and subcontractors). The
                     construction workforce is expected to be small and mainly locally sourced through third party hiring. Just the same,
                     the investments will be screened for sexual exploitation and abuse and sexual harassment (SEA/SH) risks.

                     The standard recognizes the importance of promoting sound worker-management relationships and enhancing
                     Project development benefits by treating workers fairly and providing safe and healthy working conditions. Given the
                     scope of the interventions to be financed the necessary workforces are not expected to be extensive, and no major
Public Disclosure




                     issues associated with labor influx are anticipated. The Project will not hire children under the age of 18. Workers’
                     rights are protected by government organizations such as the Ministry of Labor and Employment Promotion and the
                     National Superintendency of Labor Inspection (Superintendencia Nacional de Fiscalización Laboral - SUNAFIL), among
                     others. National work regulations recognize equal opportunities and non-discrimination.

                     The Borrower prepared a Labor Management Procedure (LMP) in line with ESS 2, which will set out how all types of
                     Project workers will be managed. The LMP (disclosed before Project Appraisal) describes the working conditions and
                     management of worker relationships, the terms and conditions of employment, provisions for non-discrimination and
                     equal opportunity, worker’s organizations and freedom of association, occupational health and safety for workers,
                     provisions to protect the workforce, including child labor and minimum wage, and the prevention of forced labor. The
                     LMP also provides general guidelines regarding the provision of housing or accommodation for workers to be
                     included in contractor’s bidding documents to ensure that working conditions are adequate if such facilities are
                     required.

                     The LMP will further ensure that the health and safety of workers are adequately addressed using World Bank Group
                     General Environmental, Health, and Safety (EHS) Guidelines as pertinent. Key industry occupational health and safety
                     risks for this Project would be those related to i) electric power transmission and distribution (EHS, such as electric
                     and magnetic fields, hazardous materials, live power lines, etc.); and ii) construction and decommissioning activities
                     (WB EHS Guidelines 4.2), such as overexertion, slips, and falls, works in heights, struck by objects, dust, moving
                     machinery, exposure to chemical, hazardous or flammable material, waste, etc. Also, key general H&S risks
                     considered under WB EHS Guidelines 2.0, such as workspace, physical hazards, chemical hazards, etc. will be


                    Jun 22, 2021                                                                                                   Page 11 of 17
                              The World Bank
                              Transmission Investment Plan (PIT) Program to support Post-COVID-19 Economic Recovery in Peru (P174812)



                     addressed. These risks will be confirmed during Project implementation once the exact nature and scope of the
                     works for each subproject are known.

                     Regarding work safety issues under the COVID-19 pandemic, all actors involved in the electricity sector have prepared
                     and submitted to the Supervisory Body of Investment in Energy and Mining (Organismo Supervisor de la Inversión en
                     Energía y Minería – OSINERGMIN) and MINEM their Contingency Plan (protocols and measures) to address health
                     and safety issues related to COVID-19, following WHO guidelines and national regulations. The Contingency Plan,
                     protocols and measures are also mandatory for contractors and subcontractors as well as for members of the general
                     public going to public distribution companies’ premises. This Contingency Plan is included in the LMP.

                     Likewise, a Workers Code of Conduct, which contains obligations of all workers involved in the Project, will be
                     prepared and included in the final LMP (to be finalized after extensive consultations immediately after Project
                     Effectiveness), and adherence to the Code of Conduct will be a condition of employment for all workers. The Code of
                     Conduct will explicitly address issues of sexual exploitation and abuse (SEA), sexual harassment (SH), and gender-
                     based violence (GBV).

                     The LMP includes the details of the grievance mechanism for workers and the roles and responsibilities for
                     monitoring such workers. SUNAFIL is the national mechanism for any labor complaints. Workers in the PIU and
                     elsewhere, independent of their level, will have access to this mechanism. How SUNAFIL functions regarding
                     grievances is described in the LMP. Moreover, a Project-specific worker’s grievance mechanism that additionally
                     covers the subprojects to be financed will also be established and implemented. This workers GRM is included in the
Public Disclosure




                     LMP and will be made available to all Project workers.

                     Final LMP will be adopted and disclosed before start of bidding process (estimated for September 2021) as set out in
                     the ESCP. During Project implementation, the LMP will be revisited and updated as required, as additional labor-
                     related risks or issues unfold.



                     ESS3 Resource Efficiency and Pollution Prevention and Management
                     This standard is relevant.

                     The following issues related to Resource Efficiency and Pollution Prevention are relevant and will be addressed during
                     Project preparation and implementation.

                     Generation of Hazardous Waste. Existing transformers identified as hazardous waste due to PCB content will pose
                     health and safety risks to humans and the environment if environmentally sound final disposal is not undertaken.
                     Waste management will follow World Bank Group EHS Guidelines on Solid Waste Management (storage,
                     transportation, and disposal) of hazardous waste, international best practice guidance, and local regulations. These
                     will be in line with both national legislation and applicable international conventions. These protocols will be
                     developed by the DGER/DFC through the distribution companies in charge of each investment.




                    Jun 22, 2021                                                                                                  Page 12 of 17
                              The World Bank
                              Transmission Investment Plan (PIT) Program to support Post-COVID-19 Economic Recovery in Peru (P174812)



                     Pollution. No significant pollution issues are preliminary expected to arise from civil works under Component 1
                     (expected to be small scale works). Nevertheless, the ESMF will include (i) provisions to consider ESS3 requirements
                     in the screening of all investments to exclude any with significant adverse impacts related to this standard; and (ii)
                     Guidelines for Pollution Prevention, to be developed as part of the site-specific ESMPs. These guidelines will include
                     measures to prevent and/or mitigate any pollution-related adverse impact due to Component 1 interventions in
                     compliance with national regulation, the applicable provisions of this ESS, and WBG General EHS Guidelines for the
                     potential handling of hazardous material.

                     Pesticide use. Works requiring clearing and later re-installation of vegetation may require the use of pesticides. The
                     ESMF will include guidelines for pest management approaches stating that the Project will not use any pesticide
                     products containing active ingredients that are restricted under applicable international conventions or their
                     protocols or that are listed in, or meeting, the criteria of their annexes.

                     In compliance with ESS3, during project execution, impacts related to environmental pollution will be prevented and
                     mitigated through the application of the provisions detailed in the specific instruments for each investment and the
                     complementary studies to be carried out. This management is described in the ESMF.

                     In addition, as part of the environmental and social assessment of the Project, the Borrower, with the Bank's
                     assistance, estimated the gross greenhouse gas (GHG) emissions resulting from the Project. By displacing diesel-fired
                     self-generation with cleaner grid-supplied power, the investments are expected to result in GHG reductions.
                     According to a preliminary assessment, the Project will result in a GHG reduction of about 2.82 million tons of CO2 or
Public Disclosure




                     0.17 million tons of CO2 on average per year.


                     ESS4 Community Health and Safety
                     This standard is relevant.

                     Key risks and impacts related to community security, health, and safety are linked to (i) construction, and assembly
                     works, (ii) traffic safety during transportation of equipment, and (iii) potential spills of hazardous materials.

                      (i) Construction, and assembly works: most works will be within specific and fenced areas, with access controlled by
                     the contractor’s personnel. Ambient noise and dust will be controlled in Projects according to the specific
                     environmental instruments of each investment, to ensure no unintended impacts are in place. Works to be
                     conducted outside substations fenced areas, such as existing or new transmission lines will require the
                     implementation of adequate measures to prevent accidents, such as security protocols, signaling of the work and
                     security areas, ample communication of works to be done, control of access to the work areas, among others.

                     (ii) Traffic safety during transportation of equipment: transport of equipment, such as transformers, will involve the
                     use of trucks along the road. Although no significant traffic impact is expected, it is important to put in place
                     measures to prevent accidents to communities from these activities.

                     (iii) Potential of spill(s) of hazardous materials: the Project will be discarding or managing parts potentially
                     contaminated with PCBs. The Project should have a contingency plan in place to ensure that remediation actions,


                    Jun 22, 2021                                                                                                    Page 13 of 17
                              The World Bank
                              Transmission Investment Plan (PIT) Program to support Post-COVID-19 Economic Recovery in Peru (P174812)



                     communication procedures, and cleaning of sites are undertaken in an adequate and timely manner if these events
                     were to occur.

                     The Project’s risk level related to sexual exploitation and abuse (SEA) and sexual harassment (SH) is Low, per the
                     evaluation conducted by the World Bank during Project preparation. Moreover, a worker's Code of Conduct to be
                     prepared by DGER, and complemented as needed by Contractors, will specifically address SEA/SH risks. Adherence to
                     the Code of Conduct will be a condition of employment and mandatory for the entire Project workforce (from
                     managers to workers).

                     It is not known at the moment if the Project will require the use of security personnel, but it is possible that some
                     substations may require these personnel during project construction or assembly (Component 1). This will be further
                     assessed during project implementation, and ESS1 and ESS4 requirements will be considered.

                     Relevance of this ESS will continue to be assessed as part of the Bank’s due diligence, as more information becomes
                     available about the scope and location of interventions to be financed.


                     ESS5 Land Acquisition, Restrictions on Land Use and Involuntary Resettlement
                     This standard is relevant.

                     DGER and World Bank have determined that new substations and transmission lines that could require land
Public Disclosure




                     acquisition for the construction of new infrastructure or establishment of rights-of-way might be needed by the
                     Project under certain conditions. In these cases, DGER expects that the impacts involved will stem from economic
                     displacement, and not physical displacement. In other words, if new land acquisition is required, project authorities
                     will seek to avoid affecting productive land or requiring the displacement of structures of any kind, on the principle
                     that the Project should generate the least possible impact. If the resettlement of any persons are involved, it will be
                     the result of a negotiated process, akin to a “willing buyer-willing seller” transaction, in which those persons 1) are
                     fully informed of the options available to them, as well as their right to reject all of them if they wish; and 2) indicate
                     their acceptance of the final agreement reached in writing. In other words, the resettlement will be fully voluntary, in
                     that the affected parties will have a right to say “no”, in which case the distribution company involved will have to
                     seek alternative alignments for the transmission line or modify the physical footprint of the substation, as the case
                     may be.

                     The ESMF for the Project includes guidelines for the selection of subprojects according to criteria that will allow it to
                     remain at a Moderate risk in terms of land acquisition. A draft Resettlement Framework (RF) has been prepared by
                     DGER to address specific ESS5 issues and serve as the basis for managing any economic displacement or voluntary
                     resettlement that may occur. The draft RF was disclosed on June 4th and consulted on June 10th. The final RF will be
                     disclosed no later than 30 days after the Project Effectiveness date. If gaps with ESS5 are identified, DGER-DFC will
                     develop resettlement/ compensation or other types of action plans that are consistent with the requirements of ESS5
                     and the guidelines set forth in the RF. Finally, as agreed between DGER and the Bank, subprojects that would be
                     implemented in land where indigenous communities, as defined under ESS7, are physically present will not be eligible
                     for Project financing.



                    Jun 22, 2021                                                                                                       Page 14 of 17
                              The World Bank
                              Transmission Investment Plan (PIT) Program to support Post-COVID-19 Economic Recovery in Peru (P174812)



                     ESS6 Biodiversity Conservation and Sustainable Management of Living Natural Resources
                     This standard is not relevant.

                     Interventions under Component 1 will be located in already-modified areas, and although these areas may be within
                     natural habitats, it is not preliminary expected that the activities will generate significant impacts in natural habitats
                     or on natural resources. This conclusion, taking note of the available information, is based on (i) works are expected
                     to be site-specific, of small scale, and limited scope; (ii) according to the second E&S eligibility criteria of the Project,
                     investments will not be eligible if they encroach environmentally sensitive areas, such as reserves, protected areas or
                     natural forest areas; and (iii) investments with environmental risks deemed substantial or high, and/or which pose
                     potential significant adverse impacts over natural habitats will be screened out through the ESMF.

                     Based on the available information, and to mitigate any potential low-scale impacts from the expected small scale
                     civil works, the ESMF and site-specific environmental instruments will include guidelines and measures to manage
                     impacts in natural habitats and on natural resources (e.g., area of native vegetation patches).

                     The relevance of ESS6 will be further reviewed during Project implementation when exact intervention sites are
                     identified and will be assessed through the ESMF.


                     ESS7 Indigenous Peoples/Sub-Saharan African Historically Underserved Traditional Local Communities
                     The information available indicates that most of the subprojects will be located in urban and peri-urban areas in
Public Disclosure




                     district capitals. Although the location of the majority of subprojects that will be financed by the Project (substations
                     and transmission lines) is currently unknown, it is possible that some subprojects in the extended prioritized list of 52
                     subprojects will be planned for areas where indigenous peoples are physically present, as defined under ESS7.
                     However, as agreed between the Bank and DGER, the Project will not support any subprojects that may negatively
                     affect indigenous populations and their lands, such as those that promote the involuntary resettlement of IPs or
                     encroachments on their communal territories, especially in the Andean and Amazon regions. Thus, this standard is
                     currently not relevant.


                     ESS8 Cultural Heritage
                     This standard is not relevant.

                     The Project activities are unlikely to generate risks or impacts on tangible or intangible cultural heritage as
                     subprojects are expected to be implemented in existing footprints or in previously modified areas.

                     Potential impacts on cultural heritage (if any) could be identified during the preparation of each subproject, and
                     mitigated during implementation. The ESMF includes guidelines in line with ESS8 to manage possible risks and
                     impacts on cultural heritage. In the event of an encounter with any physical cultural heritage, the chance finds
                     procedure included in the ESMF must be followed. Relevance of ESS8 will be further reviewed during Project
                     implementation.




                    Jun 22, 2021                                                                                                        Page 15 of 17
                              The World Bank
                              Transmission Investment Plan (PIT) Program to support Post-COVID-19 Economic Recovery in Peru (P174812)



                     ESS9 Financial Intermediaries
                     This standard is not relevant.



                     C. Legal Operational Policies that Apply

                     OP 7.50 Projects on International Waterways                                                                        No


                     OP 7.60 Projects in Disputed Areas                                                                                 No




                    B.3. Reliance on Borrower’s policy, legal and institutional framework, relevant to the Project risks and impacts

                     Is this project being prepared for use of Borrower Framework?                                                      No


                     Areas where “Use of Borrower Framework” is being considered:
                     None
Public Disclosure




                     IV. CONTACT POINTS

                     World Bank
                     Contact:             Janina Andrea Franco Salazar       Title:            Senior Energy Specialist

                     Telephone No:        +1-202-458-9860                    Email:            jfranco3@worldbank.org

                     Contact:             Laura Wendell Berman               Title:            Energy Specialist

                     Telephone No:        +1-202-473-8506                    Email:            lberman@worldbankgroup.org

                     Borrower/Client/Recipient
                     Borrower:             Ministry of Economy and Finance

                     Implementing Agency(ies)
                     Implementing Agency: Ministry of Energy and Mines



                     V. FOR MORE INFORMATION CONTACT




                    Jun 22, 2021                                                                                                  Page 16 of 17
                              The World Bank
                              Transmission Investment Plan (PIT) Program to support Post-COVID-19 Economic Recovery in Peru (P174812)



                     The World Bank
                     1818 H Street, NW
                     Washington, D.C. 20433
                     Telephone: (202) 473-1000
                     Web: http://www.worldbank.org/projects


                     VI. APPROVAL

                     Task Team Leader(s):               Janina Andrea Franco Salazar, Laura Wendell Berman

                     Practice Manager (ENR/Social)      Maria Gonzalez de Asis Cleared on 21-Jun-2021 at 15:24:20 GMT-04:00
Public Disclosure




                    Jun 22, 2021                                                                                              Page 17 of 17