Public Disclosure Copy The World Bank Implementation Status & Results Report Guizhou Tongren Rural Transport Project (P148071) Guizhou Tongren Rural Transport Project (P148071) EAST ASIA AND PACIFIC | China | Transport & Digital Development Global Practice | IBRD/IDA | Investment Project Financing | FY 2016 | Seq No: 6 | ARCHIVED on 22-May-2018 | ISR32541 | Implementing Agencies: People's Republic of China, Tongren World Bank Project Management Office, Tongren Transport Bureau Key Dates Key Project Dates Bank Approval Date:25-Sep-2015 Effectiveness Date:27-Jan-2016 Planned Mid Term Review Date:01-Sep-2018 Actual Mid-Term Review Date:-- Original Closing Date:30-Jun-2021 Revised Closing Date:30-Jun-2021 Project Development Objectives Project Development Objective (from Project Appraisal Document) The project development objective is to improve rural transport connectivity in Dejiang and Sinan counties. Has the Project Development Objective been changed since Board Approval of the Project Objective? No PHRPDODEL Components Name A. Dejiang Rural Transport:(Cost $150.02 M) B. Sinan Rural Transport:(Cost $80.77 M) C. Technical Assistance:(Cost $1.00 M) Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO  Satisfactory  Satisfactory Overall Implementation Progress (IP)  Moderately Satisfactory  Moderately Satisfactory Overall Risk Rating  Substantial  Moderate Implementation Status and Key Decisions 5/22/2018 Page 1 of 6 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Guizhou Tongren Rural Transport Project (P148071) Progress on road works in both counties continues to proceed ahead of schedule. With the project savings, Dejiang is expected to prepare a fourth batch of roads, while Sinan will take a decision about whether to utilize some, or all, of its savings to enhance the safety of rural roads. Both counties expressed a preference to combine the technical assistance activities on rural road network planning and rural road maintenance into a single activity. Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance  --  Low  Low Macroeconomic  --  Low  Low Sector Strategies and Policies  --  Moderate  Moderate Technical Design of Project or Program  --  Moderate  Moderate Institutional Capacity for Implementation and Sustainability  --  Substantial  Substantial Fiduciary  --  Moderate  Moderate Environment and Social  --  Substantial  Substantial Stakeholders  --  Moderate  Moderate Other  --  --  -- Overall  --  Substantial  Moderate 5/22/2018 Page 2 of 6 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Guizhou Tongren Rural Transport Project (P148071) Results Project Development Objective Indicators PHINDPDOTBL  Direct project beneficiaries (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 9,388.00 262,000.00 Date 01-Apr-2015 31-Oct-2017 13-Apr-2018 31-Dec-2020 PHINDPDOTBL  Female beneficiaries (Percentage, Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 35.00 48.00 PHINDPDOTBL  Travel Time Savings on Upgraded / Improved Roads (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 30.00 Date 01-Apr-2015 31-Oct-2017 13-Apr-2018 31-Dec-2020 Overall Comments Intermediate Results Indicators 5/22/2018 Page 3 of 6 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Guizhou Tongren Rural Transport Project (P148071) PHINDIRITBL  Roads rehabilitated, Rural (Kilometers, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 115.75 646.00 Date 01-Apr-2015 31-Oct-2017 13-Apr-2018 31-Dec-2020 PHINDIRITBL  Number of Bridges Improved / Constructed (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 5.00 30.00 Date 01-Apr-2015 31-Oct-2017 13-Apr-2018 31-Dec-2020 PHINDIRITBL  Number of Villages with New Road Safety Measures (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 32.00 147.00 Date 01-Apr-2015 31-Oct-2017 13-Apr-2018 31-Dec-2020 PHINDIRITBL  Number of Trainees who Attended Training and Study Tours (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 187.00 226.00 300.00 Date 01-Apr-2015 31-Oct-2017 13-Apr-2018 31-Dec-2020 5/22/2018 Page 4 of 6 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Guizhou Tongren Rural Transport Project (P148071) PHINDIRITBL  Technical Assistance: Studies and Plans Completed (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No No No Yes Date 01-Apr-2015 31-Oct-2017 13-Apr-2018 31-Dec-2020 PHINDIRITBL  Direct Project Consultations with Beneficiaries Undertaken (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target Value Yes Yes Yes Yes Date 01-Apr-2015 31-Oct-2017 13-Apr-2018 31-Dec-2020 Overall Comments Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed Disbursed P148071 IBRD-85340 Effective USD 150.00 150.00 0.00 68.63 81.37 46% Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P148071 IBRD-85340 Effective 25-Sep-2015 29-Oct-2015 27-Jan-2016 30-Jun-2021 30-Jun-2021 Cumulative Disbursements 5/22/2018 Page 5 of 6 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Guizhou Tongren Rural Transport Project (P148071) Restructuring History There has been no restructuring to date. Related Project(s) There are no related projects. 5/22/2018 Page 6 of 6 Public Disclosure Copy