IMO STATE GOVERNMENT OF NIGERIA


      RURAL ACCESS AND MOBILITY PROJECT (RAMP2)

  Environmental and Social Management Plan (ESMP)
                         for
Reinstating/Constructing Damaged, Washed Away & Missing 23
 nos River Crossings on the Rural Road Network in Imo State




                        Final Report
                        November 2019


                              i
                                                                      Table of Contents
Table of Contents ........................................................................................................................................ ii
List of Tables ............................................................................................................................................. iv
List of Figures ............................................................................................................................................ iv
List of Plates................................................................................................................................................ v
List of Annexes ........................................................................................................................................... v
LIST OF ABBREVIATIONS AND ACRONYMS ................................................................................... vi
EXECUTIVE SUMMARY ......................................................................................................................... ii
CHAPTER ONE ......................................................................................................................................... 1
1.1        Project Background ...................................................................................................................... 1
1.2        Objective of the ESMP ................................................................................................................. 1
1.3        Approach and Methodology ......................................................................................................... 1
CHAPTER TWO ........................................................................................................................................ 3
2.1 State and National Environmental Legislation and Institutional Frameworks ................................... 3
2.2        International Conventions and Agreements .................................................................................. 5
2.3        World Bank Safeguard Policies Triggered by RAMP 2 ............................................................... 6
CHAPTER THREE..................................................................................................................................... 7
3.1        Priority River Crossings................................................................................................................ 7
CHAPTER FOUR ..................................................................................................................................... 11
4.1        Introduction................................................................................................................................. 11
4.2        Biophysical Environment ........................................................................................................... 11
4.2.1.1 Soil Physico-Chemical Properties and Quality ........................................................................... 11
4.2.1.2 Ambient Air Quality ................................................................................................................... 11
4.2.1.3 Physico-Chemical Analysis of the Surface Water Samples ....................................................... 11
4.3        Overview of the Description of the Prioritized River Crossings ................................................ 13
4.4        Socio-Economic Environment .................................................................................................... 31
CHAPTER FIVE .................................................................................................................................... 34
5.1        Introduction................................................................................................................................. 34
5.2        Potential Environmental and Social Impacts .............................................................................. 34
5.2.1 Positive Environmental and Social Impacts ............................................................................... 34
5.2.2 Potential Negative Environmental and Social Impacts ............................................................... 35
CHAPTER SIX ...................................................................................................................................... 36
6.1 Introduction ...................................................................................................................................... 36
6.2        GBV Risk Management Mechanisms ........................................................................................... 59
6.3        Institutional Arrangements ......................................................................................................... 60

                                                                                    ii
6.4        Capacity Assessment and Training Programme ......................................................................... 62
6.5       Monitoring and Reporting ............................................................................................................. 63
6.5.1 Monitoring Activities.................................................................................................................. 63
6.5.2 Reporting Procedures.................................................................................................................. 63
6.5.3 Record Keeping and Control ...................................................................................................... 63
6.6        Implementation Schedule ........................................................................................................... 64
6.8        ESMP Disclosure ........................................................................................................................ 65
6.9        Cost of Implementing the ESMP ................................................................................................ 65
CHAPTER SEVEN................................................................................................................................... 66
7.1        Introduction................................................................................................................................. 66
7.2 Grievance Redress Process............................................................................................................... 67
7.3 Structure of Grievance Redress for the RCs Rehabilitation Works ................................................. 67
7.4 Setting up a Grievance Redress Committee ..................................................................................... 68
7.4.1 First Level GRM: GRC at the Site/Community Level: .............................................................. 68
7.4.2 Second Level of GRM: GRC at the SPIU Level: ....................................................................... 69
7.4.3 Third Level of GRM: GRC at the State Technical Committee Level: ....................................... 70
7.4.4 Court Resolution of Grievance Matters ...................................................................................... 71
7.5 Awareness of GRM .......................................................................................................................... 71
7.6        Reporting: ................................................................................................................................... 72
7.7        GRM Jurisdiction: ...................................................................................................................... 72
7.8        Expectation When Grievances Arise .......................................................................................... 72
7.9 Management of Reported Grievances ................................................................................................. 73
7.10 Grievance Log and Response Time ............................................................................................... 73
CHAPTER EIGHT................................................................................................................................. 74
8.1        Introduction................................................................................................................................. 74
8.2        Objectives ................................................................................................................................... 74
8.3        Stakeholder Engagement Approach............................................................................................ 75
8.4        Stakeholder KIIs, FGDs, Community Meeting and Interpretation ............................................. 75
CHAPTER NINE ...................................................................................................................................... 81
9.1        Summary ..................................................................................................................................... 81
9.2        Recommendation ........................................................................................................................ 81
ANNEXURE ............................................................................................................................................. 83




                                                                                  iii
List of Tables

Table 2.1 State and National Environmental Guidelines and Institutional Frameworks                              3
Table 2.2: Safeguard Policies Triggered by RAMP-2                                                               6
Table 3.1: Imo RAMP 2 Priority River Crossing                                                                   7
Table 3.2: Imo State RAMP 2 River Crossing Project Activities                                                   8
Table 3.3: Details of Hydraulic Structures                                                                      8
Table 3.4: Pavement Layers and Surfacing Types                                                                  9
Table 3.5 Geometric and Pavement Data for Approach Roads                                                        9
Table 4.1 Sampling point for Biophysical Environment (soil, surface water and air)                             12
Table 4.2: Current Status of the Prioritized Imo RAMP-2 River Crossings (LOT 1)                                13
Table 4.3: Current Status of the Prioritized Imo RAMP-2 River Crossings (LOT 2)                                18
Table 4.4: Current Status of the Prioritized Imo RAMP-2 River Crossings (LOT 3)                                23
Table 4.5: Current Status of Prioritized Imo RAMP-2 River Crossings (LOT 4)                                    27
Table 4.6 Socio-economic Characteristics of the consulted persons in the Communities                           31
Table 5.1: Project implementation phases and associated activities                                             34
Table 6.1: Environmental and Social Mitigation and Monitoring Plan during the Pre-Construction Phase           37
Table 6.2: Environmental and Social Mitigation and Monitoring Plan during the Construction Phase               47
Table 6.3: Environmental and Social Mitigation and Monitoring Plan during the Post – Construction/Operation Phase
                                                                                                               55
Table 6.4: Institutional Arrangement for ESMP Implementation                                                   60
Table 6.5: Institutional Capacity Strengthening Plan                                                           62
Table 6.7: Internal and External Monitoring                                                                    63
Table 6.8: ESMP Implementation Schedule                                                                        64
Table 6.9: Contractual Measures                                                                                65
Table 6.10 Disclosure Procedure                                                                                65
Table 6.11 Cost of Implementing the ESMP                                                                       65
Table 7.1: Typical Reporting format for Grievance Redress                                                      73
Table 8.1 Summary of Issues Raised at KIIs                                                                     75
Table 8.2 Summary of Issues Raised at FGDs                                                                     76
Table 8.3 Summary of Issues Raised at Community Meeting                                                        76

List of Figures

Figure 4.1: Prioritized River Crossings in LOT 1 ........................................................... Error! Bookmark not defined.
Figure 4.2: Prioritized River Crossings in LOT 2 ........................................................... Error! Bookmark not defined.
Figure 4.3: Prioritized River Crossings in LOT 3 ........................................................... Error! Bookmark not defined.
Figure 4.4: Prioritized RAMP River Crossings in LOT 4............................................... Error! Bookmark not defined.
Figure 6.1 Imo RAMP 2 Grievance Redress Framework .......................................................................................... 67
Figure 6.2 Grievance Redress Flowchart ........................................................................ Error! Bookmark not defined.




                                                                       iv
List of Plates

Plate 4.1: River Crossings in LOT 1 ............................................................................................................. 17
Plate 4.2: River Crossing in LOT 2 ............................................................................................................... 21
Plate 4.3: Boa ................................................................................................................................................ 22
Plate 4.4: River Crossings in LOT 3 ............................................................................................................. 26
Plate 4.5 River Crossings in LOT 4 .............................................................................................................. 30

List of Annexes
ANNEX 1: TERMS OF REFERENCE ........................................................................................................................................ 83
ANNEX II: QUESTIONNAIRE .................................................................................................................................................... 92
ANNEX III: MINUTES OF THE STAKEHOLDERS MEETING ................................................................................................ 97
ANNEX IV: STAKEHOLDER MEETING ATTENDANCE ..................................................................................................... 106
ANNEX V: LIST OF THE PERSONS MET ............................................................................................................................... 107
ANNEX VI: STAKEHOLDER CONSULTATION .................................................................................................................... 108
ANNEX VII: CODE OF CONDUCT TO PREVENT GENDER BASED VIOLENCE DURING THIS PROJECT ................. 110
ANNEX VIII: GRIEVANCE REDRESS FRAMEWORK FOR IMO STATE RAMP .............................................................. 114
ANNEX IX: SUMMARY OF WORLD BANK ENVIRONMENTAL AND SOCIAL SAFEGUARD POLICIES APPLICABLE
   TO THE RAMP PROJECT ................................................................................................................................................. 115
ANNEX X: GENERAL ENVIRONMENTAL MANAGEMENT CONDITIONS FOR CONSTRUCTION CONTRACTS .... 116
ANNEX XI TRAFFIC MANAGEMENT PLAN ........................................................................................................................ 120
ANNEX XII: PHYSICAL CULTURAL RESOURCES - MANAGEMENT PLAN (PCR-MP). .............................................. 121
ANNEX XIV PROJECT OCCUPATIONAL HEALTH AND SAFETY (OHS) PLAN .......................................................... 127
ANNEX XV BORROW PIT REMEDIATION PLAN ................................................................................................................ 131
ANNEX XVI WORKERS’ SITE MANAGEMENT PLAN ..................................................................................................... 133
ANNEX XVII WASTE MANAGEMENT PLAN ..................................................................................................................... 134
ANNEX XVIII: ENVIRONMENTAL AND SOCIAL SCREENING FOR IMO STATE RAMP2 RIVER CROSSINGS ........ 135
ANNEX XIX RAP SCREENING REPORT FOR RIVER CROSSINGS ................................................................................... 137
ANNEX XX PICTURE OF BOA ............................................................................................................................................... 140
ANNEX XXI LOCATION OF PROPOSED STAGING AREA, BASE CAMP AND PCR ...................................................... 141
ANNEX XXII LABOUR INFLUX MANAGEMENT PLAN ..................................................................................................... 142




                                                                                      v
                           LIST OF ABBREVIATIONS AND ACRONYMS


ARAPs   Abbreviated Resettlement Action Plans                M&E      Monitoring & Evaluation

AFD     French Development Agency                            NESREA   National Environmental Standards and Regulatory
                                                                      Enforcement Agency
BOQ     Bill of Quantity
                                                             NGOs     Non- Governmental Organizations
CBOs    Community Based Organizations
                                                             NPE      National Policy on Environment
CSOs    Civil Society Organizations
                                                             NSME     Nigerian Society of Mining Engineers
CDA     Community Development Associations
                                                             OHS      Occupational Health and Safety
EA      Environmental Assessment
                                                             OHSMP    Occupational Health and Safety Management Plan
EMS     Environmental Management Systems
                                                             OP       Operational Policy
ESIA    Environmental and Social Impact Assessment
                                                             PAD      Project Appraisal Document
ESMP    Environmental and Social Management Plan
                                                             PAP      Project Affected Persons
EIA     Environmental Impact Assessment
                                                             PC       Project Coordinator
ESMF    Environmental and Social Management Framework
                                                             PCN      Project Concept Notes
ESO     Environmental Safeguard Officer
                                                             PDOs     Project Development Objectives
FGN     Federal Government of Nigeria
                                                             PIM      Project Implementation Manual
FGD     Focus Group Discussion
                                                             RAMP 2   Rural Access and Mobility Project 2
FMEnv   Federal Ministry of Environment
                                                             RC       River Crossing
GRC     Grievance Redress Committee
                                                             RPF      Resettlement Policy Framework
GRM     Grievance Redress Mechanism
                                                             SPIU     State Project Implementation Unit
ISEPA   Imo State Environmental Protection Agency
                                                             ToR      Terms of Reference
IPV     Intimate Partner Violence
                                                             WB       World Bank
KII     Key Informant Interview
                                                             WHO      World Health Organization
LGA     Local Government Authority

MDAs    Ministries Department and Agencies




                                                        vi
                                      EXECUTIVE SUMMARY

ES 1: Background

The Federal Government of Nigeria has received financing from the World Bank (WB) and French
Development Agency (AFD) for the implementation of Second Rural Access and Mobility Project
(RAMP2). The RAMP-2 is aimed at improving and enhancing accessibility and mobility in the rural areas
of Nigeria. As part of RAMP-2 Activities in Imo State, a total of 23 Nos critical river crossings across
several Local Government Areas (LGA) of the state have been prioritized for rehabilitation/construction.
The project will involve medium-sized civil engineering works which is envisaged to result in minor
negative Environmental and Social impacts thus, triggering the World Bank’s Safeguard Policies including
Environmental Assessment OP 4.01; Natural Habitats OP 4.04, Involuntary Resettlement OP 4.12 and
Physical and Cultural Resources OP 4.11. Consequently, the Imo State RAMP-2 Project Implementation
Unit (SPIU) has prepared this Environmental and Social Management Plan (ESMP) to mitigate the likely
Environmental and Social impacts that may result from project implementation.

ES 2: Policy, Legal and Administrative Framework

The proposed project will be guided by applicable Federal and State policies and regulatory framework,
and the World Bank operational safeguard policies. The ESMP has been prepared in accordance with the
procedures for conducting Environmental Assessments (EA) for development projects in line with the
Environmental Impact Assessment Act No. 86, 1992 (as amended by EIA Act CAP E12 LFN 2004), and
also the World Bank OP 4.01 (Environmental Assessment). Consequently, the project implementation will
be guided by the provisions of the National Policy on Environment (1989) and the applicable World Bank
operational policies. The legal and regulatory framework is provided in details in chapter 2.

ES 3: Project Description

The project activities include Site preparation, Construction of Box Culverts, Protection Works and
Ancillary Works; approach roads, retaining walls, side drains, etc. Table 3.1 lists the
rehabilitation/construction works of prioritized River Crossings.

ES 4: Environmental and Social Baseline Information of Project Locations

Some of the existing river crossings which will be rehabilitated, and areas marked for provision of new
river crossings are characterized by the presence of various aquatic plants and animals such as bamboo,
Plantain and Alligator lizard respectively. Other plants of economic importance located around these areas
include palm tree, oil bean and cashew among others. Due to the location of these economic trees, they are
likely to be impacted during implementation of civil works. The rivers or streams are the major source of
water for domestic use across the priority sites. They also serve other purposes like source of water for
fishing and recreation. These activities are likely to be affected during the civil work. There is a shrine in
Mgbidi community. The river (Obana) is a deity where fishing is prohibited. The killing of animals such as
Boa constrictor is also a prohibited and a taboo in Mgbidi community (see Annex XIII & XXI for more
details). The people across the project areas are mainly farmers who are into crop and cash crop cultivation.

ES 5: Potential Environmental and Social Impacts

The potential positive project impacts will include:
   • Enhanced access and mobility for the people and movement of agricultural products;
   • Creation of jobs for the people of Imo State including new jobs for youth and women;
   • Greater diversity in production and in farmers income;

                                                      ii
    •   Access to market-induced increase in production
    •   Reduction in cost of transportation; and
    •   Increase inter-communal socio-economic exchange
The envisaged adverse impacts that may result from the project are listed in the table below:
 Potential Adverse Impacts
 Social Impacts                                                                  Environmental Impacts
• Loss of sources of livelihood                                         • Soil erosion caused by the weight and activities of the
• Conflict arising potentially from loss of sources of livelihood and     heavy-duty machines
   access to assets                                                     • Air and water pollution from construction spoils
• Exacerbation of the risk of transmission of HIV/AIDS and other        • Noise disturbance from heavy duty machineries
   STIs due to increase in migrant population.                          • Disruption of access to movement due to excavations
• Damage to shrines and cultural sites (PCR)e.g in Mgbidi               • Dust emission due excavation and use of heavy
   community                                                              construction machineries
• Occupational health and Safety risks                                  • Waste generation from construction spoils
• Respiratory and eye related problems for workers due to               • Loss of vegetation due to site clearing
   exposure to fugitive dusts and gaseous emissions.                    • Potential siltation of surface water from eroded and
• Increased security risks due to storage of materials and                excavated soils
   equipment on site                                                    • Soil contamination from leakage/ spillage of fuel or oil
• Threat to community culture, safety and security due to                 from equipment and vehicles.
   presence of workers and business opportunists.                       • Generation of construction waste and debris
• Increase in vehicular movement may cause traffic congestion           • Material sourcing, borrow pit formation and
   and accidents                                                          management
• Risks of occupational and social accidents and injuries in using      • Staging area impacts
   the new river crossings                                              • Risk of flooding during civil work
• Risk to community health and safety                                   • Wastewater discharges
                                                                        • Increased demand on freshwater resources
• Traffic congestion and diversion during construction works
                                                                        • Increased use of/demand for natural resources
• Risk of drowning in river by workers
• Security issues that may lead to stealing of contractor equipment
   mobilized to site
• Threat to community culture due to labour influx
• Risk of social conflict and gender-based violence due to labour
   influx
• Increased risk of illicit behavior and crime
• Increased burden on and competition for public service provision
• Impacts on community dynamics
• Child labour and school dropout
• Local inflation of prices
• Increased pressure on accommodation and rent


ES 6: Implementation schedule
The project implementation phase is estimated to be completed in 7 months. The implementation
schedule is presented in chapter 6 (Table 6.8).

ES 7: Environmental and Social Management Plan
The ESMP establishes mitigation measures to address all potential adverse environmental and social
impacts identified for the proposed project, including responsibility and costs as detailed in Chapter 6, table
6.1. The mitigation costs will be embedded as part of the contractors BOQ. The plan also provides a
monitoring program including responsibilities and monitoring frequency to ensure compliance to mitigation
measures.
                                                         iii
ES 8: Capacity Building Plan
The SPIU has not previously been involved in implementing World Bank assisted projects. As such, their
capacity in implementing projects in line with the Bank’s policies was assessed to be limited. The capacity
building programme in Chapter 6, table 6.5 will therefore be implemented to strengthen institutional
capacity in ensuring environmental and social safeguard compliance in the project implementation.

ES 9: ESMP Disclosure
This ESMP shall be disclosed to the public at designated centers in Imo State and published in two national
newspapers accessible to the project stakeholders for review, in line with the guidelines of the Federal
Ministry of Environment and in the external website of the World Bank.

ES 10: Grievance Redress Mechanism
Similar with other RAMP 2 states, Grievance Redress Mechanism (GRM) shall be set up by the Imo State
RAMP SPIU to address complaints arising from the project implementation. The GRM will be established
at four tiers; the first tier will be at the community level, the second at the level of the state PIU, the third
with support from the Federal PIU and the fourth tier will include seeking court judicial process.
Stakeholders and affected persons will also be informed of the various tiers. This committee at the
community and in the state will comprise relevant officers of the Imo SPIU, representative of the Ministry
of Local Government and Rural Development, representatives of the 23 priority sites who are to be
nominated by the traditional heads and Community Development Association (CDA).

ES 11: Budget for Environmental and Social Management Plan Implementation
The implementation cost of the ESMP is Eleven Million, seven hundred and Sixty-five Thousand and six
hundred Naira (Twenty-five thousand, six hundred and seventy-two Dollars). The summary of the
implementation cost as explained in chapter 5 (table 5.11) is as follows:

Cost of Implementing the ESMP
Heading                                  Indicative Costing in Naira (N)    Cost Estimate in USD
Cost of Mitigation                       4,356,000.00                       12,100.00
Capacity Building and Training           1,100,000.00                       3,055.56
Monitoring Programme                     2,196,000.00                       6,100.00
Grievance Redress Mechanism              750,000.00                         2,083.33
Sub-total                                8,402,000.00                       23, 338.89
Contingency                              840,200.00                         2, 338.89
Total                                    9,242,200.00                       25, 672.78
(1 USD = 360.00)

ES 12: Stakeholders Consultation
The main issues expressed by the stakeholders during the public consultation with regards to the proposed
river crossing in their area include:
1.     Existence of cultural rites in some communities (Mgbidi). This issue was addressed by the community
       leaders who gave assurance that all the necessary consultations and rituals will be carried out. The
       associated costs will be captured in the stand-alone RAP been prepared which will be implemented
       prior to commencement of the project works. The consultant also notified the community members
       that physical and cultural resources are usually treated with sensitivity in World Bank funded projects.
2.     Request for other river crossings. This issue was resolved by explaining to the beneficiaries that the
       selected priority roads are the ones considered at this phase and others will be considered in
       subsequent phases.
                                                       iv
3.    Bad state of existing access roads. This was resolved by explaining to the beneficiaries that the
      approach roads to the river crossings will be rehabilitated.

The communities’ expectations during construction and operation phases are as follows:
1.   Employment of the locals during the construction and operation phases of the project should be
     prioritized;
2.   For safety and security of workers, machinery and equipment, the host communities are willing to be
     engaged for proper policing;
3.   Adequate compensation to people whose properties will be lost due to the intervention, especially
     along the channel of water distribution. This it was indicated will be captured in RAP report
4.   Creation of alternative routes. The beneficiaries were informed that alternative routes will be captured
     in the engineering designs for all the river crossings

It is expected that the issues raised by stakeholders will be taken into consideration during the
implementation of this project. It is expected that the results of the socio-economic impact assessment be
communicated to the community through a process of debriefing on results of the study. This will allow the
communities to make final input before full project implementation.




                                                     v
                                             CHAPTER ONE

                                            INTRODUCTION

1.1     Project Background
The Federal Government of Nigeria has received financing from the World Bank (WB) and French
Development Agency (AFD) for the implementation of Second Rural Access and Mobility Project (RAMP-
2). The RAMP-2 is aimed at improving and enhancing accessibility and mobility in the rural areas.
Accessibility and mobility are critical issues in the lives of the rural population, considering that majority
of them are agriculturalists. Movement of their agricultural inputs and outputs (produce) is hinged on
accessibility and mobility. The current dilapidated state of river crossings invariably diminishes their
economic empowerment and socio-cultural wellbeing.

As part of RAMP-2 activities in Imo State, a total of 23 Nos critical river crossings across several Local
Government Areas (LGA) of the state have been prioritized for rehabilitation/construction. The project will
involve medium-sized civil engineering works which are envisaged to result in some negative
Environmental and Social impacts thus, triggering the World Bank’s Safeguard Policies on Environmental
Assessment OP 4.01; Natural Habitats OP 4.04, Involuntary Resettlement OP 4.12 and Physical and
Cultural Resources OP 4.11. Consequently, the Imo State RAMP-2 Project Implementation Unit (SPIU)
has prepared this Environmental and Social Management Plan (ESMP) to identify measures to mitigate the
likely environmental and social impacts that may result from project implementation.

1.2     Objective of the ESMP
The major developmental objective of this ESMP is to facilitate an effective decision-making process and
to ensure that during project implementation, the activities are environmentally sound; that community
consultation and participation are encouraged; and that social wellbeing is enhanced in ways that are
generally sustainable. The specific objectives are to:
    • Identify and quantify potential negative and positive environmental and social impacts of the
        proposed works;
    • Recommend mitigating measures (in the form of an Environmental and Social Management Plan,
        ESMP) to be implemented to avoid these negative environmental and social impacts;
    • recommend an appropriate Institutional structure that will ensure sustainable safeguard measures;
        and
    • explore the possibilities for community-based safeguard approach and the Capacity Building needs
        of the relevant stakeholders.

1.3    Approach and Methodology
The preparation of the ESMP was guided by RAMP 2 Environmental and Social Management Framework
(ESMF) and Project Appraisal Document (PAD) alongside other relevant RAMP 2 documents.

Field studies were undertaken between December 12, 2018 – February 10, 2019 in the project location to
identify environmental and social sensitivities likely to be affected by the project (biophysical data
collection was carried out in December, 2018 while the socio-economic survey and stakeholder consultation
were carried out in January and February 2019 respectively).

                                                      1
Socio-economic survey was conducted through Focus Group Discussion (FGD), in-depth interviews and
administration of structured questionnaire using random sampling techniques. The FGD targeted the youth,
women, men and aged groups in the project area. The sampling of stakeholders for engagement and data
collection is based on the following criteria: adequate representation from the relevant social groups in the
study location; inclusion of groups and individuals with different population characteristics/socio-economic
status; participation of those with access to relevant information; evidence of different types of livelihood
activities; and inclusion of males and females where possible. In all, 430 questionnaires were administered
(10 questionnaires were administered in each proposed River crossing site to direct potential project
affected persons (PAPs) and26 FGDs, 17 in-depth interviews IDIs and 6 Public forum meetings were
organized in the communities (Photos, attendance and minutes can be found in Annex V, III and II
respectively).


Public forum meetings were held on the 7th of April, 2019 including direct discussions with key
stakeholders in the community and the PIU to determine their views of the proposed intervention project.
The outcomes of these were documented and these include how issues and problems raised would be
resolved.




                                                     2
                                                  CHAPTER TWO

 INSTITUTIONAL AND LEGAL FRAMEWORK FOR ENVIRONMENTAL MANAGEMENT

2.1 State and National Environmental Legislation and Institutional Frameworks
Several state and national environmental legislations and institutional frameworks are applicable to the
operations of the RAMP 2 intervention in Imo State. They are outlined in table 2.1.

Table 2.1 State and National Environmental Guidelines and Institutional Frameworks
 Relevant Imo State Legislations

 Legislation                                      Year       Mandate

 Imo Environmental Protection Agency Law          2008       This law is to ensure that every developmental project in the state adheres
                                                             to established environmental guidelines

 Imo Environmental Transformation Commission      2008       To ensure a “clean and green�? Imo State including regulating the activities
 (ENTRACO) Law No. 3                                         of refuse collectors and operation of an environmental sanitation and
                                                             traffic court in each Local Government Area of Imo State.

 Imo Environmental Sanitation Agency Law          2003       This law is to ensure proper disposal and clearing of wastes in the State
 2003

 Imo State Institutional Framework

 Imo State Ministry of Petroleum & Environment;              The mandate of the ministry includes:

                                                             • liaising with the Federal Ministry of Environment, FMEnv to achieve a
                                                                healthy or better management of the environment via development of
                                                                National Policy on Environment
                                                             • responsibility for monitoring waste management standards,
                                                             • responsibility for general environmental matters in the State, and
                                                             • monitoring the implementation of ESIA studies and other environmental
                                                                studies for all developmental projects in the State.
 Imo State Ministry of Agriculture & Natural                 This ministry is responsible for the promotion of agriculture and ensuring
 Resources,                                                  the sustainable exploitation of natural resources in the state

 Imo State Ministry of Works and Transport                   This ministry is responsible for the execution of public works of the
                                                             government and the management of transportation infrastructure across
                                                             the state

 Imo State Environmental Protection Agency                   This agency is charged with the responsibility to monitor, evaluate and
 (ISEPA)                                                     audit the implementation

                                                             of the ESMP to ensure that the rehabilitation works and project operations
                                                             meet “best

                                                             environmental practices

 Relevant National Policies and Legislation       Year       Provisions




                                                         3
The National Policy on Environment (NPE) of         (revised in   The mandates of the NPE include among others:
1989                                                1999 and
                                                    2016)         • Ensuring the quality of the environment is adequate for good health and
                                                                     well-being;
                                                                  • Promoting sustainable use of natural resources and the restoration and
                                                                     maintenance of the biological diversity of ecosystems;
                                                                  • Promoting an understanding of the essential linkages between the
                                                                     environment, social and economic development issues;
                                                                  • Encouraging individual and community participation in environmental
                                                                     improvement initiatives.
Environmental Impact Assessment (EIA) Act           2004          The Act makes EIA mandatory for all major development projects likely to
CAP. E12 L.F.N                                                    have adverse impacts on the environment and gives specific powers to
                                                                  FMEnv to facilitate environmental assessment of projects in Nigeria. The
                                                                  Act also stipulates the minimum requirements for environmental
                                                                  assessments which was adopted in preparing this ESMP.

Other relevant national policies and legislations

National Policy on Flood and Erosion Control        2006          This policy addresses the need to combat erosion in the country by utilizing
                                                                  the procedures outlined in the National Action Plan for Flood and Erosion
                                                                  Control and Technical Guidelines

National Gender Policy                              2006          The goal of the National Gender Policy is to build a just society devoid of
                                                                  discrimination, harness the full potentials of all social groups regardless of
                                                                  sex or circumstance, promote the enjoyment of fundamental human rights
                                                                  and protect the health, social, economic and political well-being of all
                                                                  citizens in order to achieve equitable rapid economic growth; evolve an
                                                                  evidence based planning and governance system where human, social,
                                                                  financial and technological resources are efficiently and effectively
                                                                  deployed for sustainable development.

Relevant Acts

National Environmental Standards and                2007          With the repealing of the Federal Environmental Protection Act of 1988,
Regulations Enforcement Agency Act                                the NESREA Act, 2007 became the major statutory regulation or
(NESREA Act)                                                      instrument guiding environmental matters in Nigeria. It specially makes
                                                                  provision for solid waste management and its administration and prescribes
                                                                  sanctions for offences or acts, which run contrary to proper and adequate
                                                                  waste disposal procedures and practices.

Land Use Act                                        1978          The Land Use Act of 1978 (modified in 1990) remains the primary legal
                                                                  means to acquire land in the country. The Act vests all land comprised in
                                                                  the territory of each state in the federation in the governor of the State and
                                                                  requires that such land shall be held in trust and administered for the use
                                                                  and common benefit of all Nigerians in accordance with the provisions of
                                                                  this Act.

Factories Act                                       2004          The Act is the primary legislation for the protection of the safety, health and
                                                                  welfare of workers. It has its broad objective to make elaborate provisions
                                                                  for the health, safety and welfare of the workers exposed to occupational
                                                                  hazards by taking measures to prevent accidents and injuries.

Child Rights Act                                    2003          The Act serves as a legal documentation and protection of Children rights
                                                                  and responsibilities in Nigeria. It also acts as a legislation against Human


                                                              4
                                                               trafficking since it forbids children from being "separated from parents
                                                               against their will, except where it is in the best interests of the child.

 Employee's Compensation Act                        2010       The Act make provisions for compensations for any death, injury, disease
                                                               or disability arising out of or in the course of employment; and for related
                                                               matters.

 Other Relevant Legislations at the Federal Level

 Criminal Code                                                 The Nigerian Criminal Code makes it an offence punishable with up to 6
                                                               months imprisonment for any person who:

                                                               • Violates the atmosphere in any place so as to make it noxious to the
                                                                 health of persons in general dwelling or carry on business in the
                                                                 neighborhood, or passing along a public way: or
                                                               • Does any act which is, and which he knows or has reason to believe to
                                                                 be likely to spread the infection of any disease dangerous to life,
                                                                 whether human or animal.
 National Institutional Framework

 The Federal Ministry of Environment (FMEnv)                   FMEnv is the apex body charged with the responsibility to administrate and
                                                               enforce environmental laws in Nigeria. The FMEnv prohibits public and
                                                               private sectors from embarking on major developmental projects or
                                                               activities without due consideration, at early stages, for environmental and
                                                               social impacts. In addition to the EIA Act, the Ministry has produced
                                                               sectorial including sectorial guidelines on infrastructure development
                                                               which will be duly considered in the implementation of this project

 The Imo State Project Implementation Unit (Imo                The Imo State Project Implementation Unit (Imo-SPIU) headed by the State
 SPIU) RAMP                                                    Coordinator and hosted by the Ministry of Local Government and Rural
                                                               Development is responsible for the coordination of RAMP projects in Imo
                                                               State. The coordinator is thus directly responsible for coordinating activities
                                                               of the Site intervention, including the implementation of this ESMP.

 Federal Ministry of Agriculture and Rural                     The Federal Ministry of Agriculture and Rural Development (FMARD)
 Development                                                   has the responsibility of optimizing agriculture and integrating rural
                                                               development for the transformation of the Nigerian economy, with a view
                                                               to attaining food security and positioning Nigeria as a net food exporter
                                                               for socio-economic development.



2.2     International Conventions and Agreements
Applicable international guidelines/conventions/treaties to which Nigeria is a signatory and will be duly
considered in implementation of this project are outlined below:
    • Vienna convention for the protection of the Ozone Layer and the Montreal protocol for Control of
      Substances that deplete the ozone layer;
    • Basel Convention on the prevention of trans-boundary movement of hazardous wastes and their
      disposal;
    • Convention on the prevention of the international trade in endangered species (CITES), 1973;
    • Convention on Biodiversity 1992;
    • Convention on climate change 1992; and

                                                           5
          • World Health Organization (WHO) Health and Safety Component of EIA, 1987.

      2.3      World Bank Safeguard Policies Triggered by RAMP 2
      The World Bank Environmental and Social Safeguard Policies are a cornerstone of its support to sustainable
      poverty reduction. The main objective of these policies is to prevent and mitigate undue harm to people and
      their respective environment in the developmental processes. Four of these policies have been triggered and
      are discussed briefly in Table 2.2.

      Table 2.2: Safeguard Policies Triggered by RAMP-2
S/N     Safeguard Policies                 Applicability to project due to                        How Project Address Policy Requirements
1       Environmental Assessment (OP/BP    Civil works under the project including                An ESMF has been prepared for RAMP 2 and site-
        4.01)                              excavation and construction of river crossings         specific mitigation measures developed in this
                                           (RCs) will have adverse effect on the                  ESMP
                                           environment
2       Physical Cultural Resources (OP/BP Civil works under the project, including               Implement the Chance find procedure within the
        4.11)                              excavations will most likely not be able to avoid      ESMP or as a standalone document
                                           all cultural heritage sites as well as presently
                                           unknown sites that can be expected to be found
                                           in this area rich of cultural and historical values.
3       Involuntary Resettlement (OP/BP    The activities under the project will require the    A resettlement policy framework (RPF) has been
        4.12)                              acquisition of land (some with economic trees        prepared for the RAMP2. Due to the potential
                                           and farms) surrounding the Rivers and streams        impacts to economic trees and farmland located
                                           for implementation of the civil works.               around the intervention sites, standalone RAP(s)
                                                                                                will be prepared, and measures implemented
                                                                                                before project implementation(See screening
                                                                                                checklist in annex XIX).
4       Natural Habitat (OP/BP 4.04)          The project activities may require the conversion An ESMF has been prepared for RAMP 2 and site-
                                              of significant areas of natural habitats. This is specific mitigation measures developed in this
                                              more so as the project is located in a sensitive ESMP
                                              ecosystem (wetland) thereby causing disturbance
                                              and or damage to these ecosystems.




                                                                     6
                                           CHAPTER THREE

                                       PROJECT DESCRIPTION

3.1     Priority River Crossings
Rehabilitation/Construction works of prioritized River Crossings are to be carried out in 23 selected River
crossing in some prioritized LGAs of Imo State as outlined in Table 3.1.

Table 3.1: Imo RAMP 2 Priority River Crossing
S/N       Name of Priority Site                       LGA                           X                  Y
                                                                                        Lot 1
1         Agbata-Umuigwe Na Uzoagba                   Ikeduru/Mbatoli                      5.5471351       7.1456688
2         Okwu-Umuonohor                              Ikeduru/Mbatoli                      5.5386931       7.1940632
3         Orie Mbieri-Umuomumumbieri                  Ikeduru/Mbatoli                      5.5833629       7.0635892
4         Ekwe-Okwuodor                               Njaba/Isu/Nkwere/Nwangele             5.725831       7.0270723
5         Umuduruemghara-Okpala Anara                 Isiala Mbano/Ehime Mbano             5.7103055       7.1796244
6         Umuihim Autonomous Community – Umukaku      Isiala Mbano/Ehime Mbano             5.6694058       7.2049614
7         Umulogho-Okwuohia                           Aniri/Agwu                           5.5855616       7.3612385
                                                                                        Lot 2
1         Uzurunamu-Okwudo Mgbidi                     Oru East/Oru West/Orsu               5.7258524       6.8820876
2         Akama-Nansa-Akwa Ihedi                      Orsu                                 5.8850147       7.0069225
3         Igbee-Amaruru                               Orsu                                 5.8895854       6.9687548
4         Ndiuche-Izuogu Uri                          Ideato North/South                   5.8230743       7.1782618
5         Obinugwu-Umueshi-Okwa                       Ideato North/South                   5.8355695       7.1244245
6         Dikenafai-Abba Nwagele                      Ideato North/South                   5.7543142       7.1481708
7         Dimagu-Nkwere                               Ideato North/South                   5.7847093       7.1120534
                                                                                        Lot 3
1         Umueziogwu-Uzoagba-Okitankwo-Umunahu        Owerri East/West                    5.5139843        7.1066507
2         Umuebee-Umuhu                               Owerri East/West                    5.5471296        7.1456688
3         Ugbele-Bsc                                  Ideato South                        5.8013891        7.0774081
4         Amugu-Umulebe                               Ideato South                        5.8603032        7.1424667
                                                                                        Lot 4
1         Ndikpa Umucheke-Okiu                        Onuimo                              5.7923226        7.1956882
2         Ukolu-Umucheke                              Onuimo                              5.7817906        7.1951538
3         Umunaa-Uhi Owerre-Okwe                      Onuimo                               5.797752        7.2101361
4         Umuokpara Ofeiyi-Umuoleche                  Okigwe                              5.8311087        7.3200808
5         Amano-Umukogwu                              Okigwe                              5.8538709        7.3192942

3.2         Proposed Intervention Works

The proposed intervention works according to the engineering designs are outlined as follows:

      •     Project activities (Table 3.2)
      •     Hydraulic Structure Size and Design Details (Table 3.3)
      •     Pavement Layers and Surfacing Types (Table 3.4)
      •     Geometric and Pavement Data for Approach Roads (Table 3.5)




                                                    7
Table 3.2: Imo State RAMP 2 River Crossing Project Activities
Phase            Activity                  Description of Activity                       Staffing        Support             Schedule
                                                                                                         Facilities    and
                                                                                                         services

Pre-              • Sensitization           • Sensitize and inform community members                     •Base camp           • 4 weeks or 1 month
Construction      • Mobilisation              on the time and duration of civil works.
                  • Marking                 • Mobilize trucks, vehicles and other Skilled Labor          •Borrow pit
                    Temporary access          equipment and install camp office and (5 nos)
                    culvert                   workshop.                                                  •Staging area
                  • Clearing Safety         • Mark the boundaries of the working areas Unskilled
                    measures                  around the site.                           labour (35)
                  • Staging area            • Construct a temporary pedestrian access
                  • Workers camp              culvert for community members and other
                  • Locating borrow           users;
                    pits                    • Clear vegetation covering stream banks
                                              and widen banks appropriately
                                            • Evacuate obstacles such as silt and solid
                                              waste along stream
                                            • Install lighting and relevant road signage
                                              and barriers at construction site
Construction      • Side Drains             • Site clearing and excavation               Skilled Labor   •Base camp           • 24 weeks        or   6
                  • Culvert works           • Excavation, and stabilization              (10 nos)                               months
                  • Utilizing borrow        • Construction of bed, and concrete                          •Borrow pit
                    pits                      screeding;                                 Unskilled
                                            • Construction of reinforced concrete wall labour (50)       •Staging area
                                              (Abutments);
                                            • Construction of deck concrete;                             Priority Work
                                            • Drainage structure and facilities;                         sites/ River
                                            • Retaining walls and earth – filling;                       crossing
                                            • Any other ancillary work                                   corridor
Post-             • Maintenance of          • Regular clearing of culverts, drains and Skilled Labor     •road               During operation
Construction        Culvert, Drains,          stream of silt and solid waste;            (3 nos)         maintenance
/Operational        Stream and access       • Regular checks and maintenance of road                     workshop
/Maintenance        Road                      surface;                                   Unskilled
                  • Borrow        pit       • Checks and exchange of wearing course labour (15)          • road corridor
                    reclamation               after number of years;
                                            • Exchange of binder course after a number                   River crossing
                                              of years;
                                                                                                         corridor
                                            • Routine inspections of foundations, joins
                                              etc;
                                            • Routine inspections of pavement
                  • Maintenance of          • Maintenance of road restraint systems;
                    other      ancillary      Maintenance of traffic control and
                    facilities                information systems;
                                            • Maintenance of fencing walls screens and
                                              environmental barriers; and
                                            • Maintenance of the road verge (including
                                              landscaping and rehabilitation).

Table 3.3: Details of Hydraulic Structures
S/N     Name of River crossing                               Slope       Manning        Velocity         Peak flow         Recommended structure
                                                                         Coefficient
                                                              Lot             1
1       Agbata-Umuigwe Na Uzoagba                            249.5       0.15           0.2              16.47             RC
2       Okwu-Umuonohor                                       220         0.15           0.1              3.40              RC
3       Orie Mbieri-Umuomumumbieri                           195         0.15           0.1              1.5               RC
4       Ekwe-Okwuodor                                        67          0.15           2.2              0.22              RC
                                                                  8
5      Umuduruemghara-Okpala Anara                      248        0.15             0.71      0.15            RC
6      Umuihim Autonomous Community – Umukaku           252.5      0.15             0.4       0.57            RC
7      Umulogho-Okwuohia                                214.5      0.15             0.23      2.32            RC
                                                         Lot              2
1      Uzurunamu-Okwudo Mgbidi                          211        0.15             19.0      0.06            RC
2      Akama-Nansa-Akwa Ihedi                           252.5      0.15             0.4       0.57            RC
3      Igbee-Amaruru                                    252.5      0.15             0.4       0.57            RC
4      Ndiuche-Izuogu Uri                               294.5      0.15             0.85      11.66           RC
5      Obinugwu-Umueshi-Okwa                            198        0.15             4.5       0.50            RC
6      Dikenafai-Abba Nwagele                           246        0.15             1.52      2.67            RC
7      Dimagu-Nkwere                                    252.5      0.15             0.4       0.57            RC
                                                         Lot              3
1      Umueziogwu-Uzoagba-Okitankwo-Umunahu             195        0.15             0.1       1.5             RC
2      Umuebee-Umuhu                                    249.5      0.15             0.2       16.47           20 meters Bridge
3      Ugbele-Bsc                                       308.5      0.15             0.53      41.07           RC
4      Amugu-Umulebe                                    168        0.15             5.5       6.5             RC
                                                         Lot              4
1      Ndikpa Umucheke-Okiu                             235.5      0.15             0.1       41.09           RC
2      Ukolu-Umucheke                                   245.5      0.15             0.8       11.18           RC
3      Umunaa-Uhi Owerre-Okwe                           223        0.15             4.74      0.01            RC
4      Umuokpara Ofeiyi-Umuoleche                       198        0.15             4.5       0.50            RC
5      Amano-Umukogwu                                   252.2      0.15             0.4       0.57            RC

Table 3.4: Pavement Layers and Surfacing Types
 S/N      Pavement Layer/Surfacing Type   Description
 1        Base Course                     Typically, 150mm thick natural granular lateritic base course or crushed-stone base
                                          material.

 2        Sub-base                        Typically, 150mm thick (or nil) natural granular lateritic sub- base course layer of equal
                                          subgrade strength.

 3        Dust-Suppressants               To suppress/control dust with chemical additives such as Wetting Agents, Salt/Chlorides,
                                          Natural Polymers, Wax Agents, etc.

 4        Surfaces                        Earth

 5        Other surfaces                  Otta seal and 2-Coat surface dressing




Table 3.5 Geometric and Pavement Data for Approach Roads
S/N    Name of Priority Site        Approach Width of           Pavement Structure (mm)       RC Side drains (mm2)         Length of
                                    Road       road                                                                        Side drain
                                    Length (m) (m)              Sub Base Base   Surface       Right side    Left side      (m)
                                                                Course   Course
                               Lot          1
1      Agbata-Umuigwe Na Uzoagba    100           7.3           150           150    Earth    750X750       750X750        200
2      Okwu-Umuonohor               100           7.3           150           150    Earth    750X750       750X750        200
3      Orie Mbieri-Umuomumumbieri   100           7.3           150           150    Earth    750X750       750X750        200
4      Ekwe-Okwuodor                100           7.3           150           150    Earth    750X750       750X750        200
5      Umuduruemghara-Okpala Anara 100            7.3           150           150    Earth    750X750       750X750        200
6      Umuihim Autonomous Community 100           7.3           150           150    Earth    750X750       750X750        200
       – Umukaku
7      Umulogho-Okwuohia            100           7.3           150           150    Earth    750X750       750X750        200

                                                            9
                              Lot         2                                                      750X750
1   Uzurunamu-Okwudo Mgbidi         100       7.3        150   150   Earth   750X750   750X750   200
2   Akama-Nansa-Akwa Ihedi          100       7.3        150   150   Earth   750X750   750X750   200
3   Igbee-Amaruru                   100       7.3        150   150   Earth   750X750   750X750   200
4   Ndiuche-Izuogu Uri              100       7.3        150   150   Earth   750X750   750X750   200
5   Obinugwu-Umueshi-Okwa           100       7.3        150   150   Earth   750X750   750X750   200
6   Dikenafai-Abba Nwagele          100       7.3        150   150   Earth   750X750   750X750   200
7   Dimagu-Nkwere                   100       7.3        150   150   Earth   750X750   750X750   200
                              Lot         3
1   Umueziogwu-Uzoagba-             100       7.3        150   150   Earth   750X750   750X750   200
    Okitankwo-Umunahu
2   Umuebee-Umuhu                   100       7.3        150   150   Earth   750X750   750X750   200
3   Ugbele-Bsc                      100       7.3        150   150   Earth   750X750   750X750   200
4   Amugu-Umulebe                   100       7.3        150   150   Earth   750X750   750X750   200
                             Lot          4
1   Ndikpa Umucheke-Okiu            100       7.3        150   150   Earth   750X750   750X750   200
2   Ukolu-Umucheke                  100       7.3        150   150   Earth   750X750   750X750   200
3   Umunaa-Uhi Owerre-Okwe          100       7.3        150   150   Earth   750X750   750X750   200
4   Umuokpara Ofeiyi-Umuoleche      100       7.3        150   150   Earth   750X750   750X750   200
5   Amano-Umukogwu                  100       7.3        150   150   Earth   750X750   750X750   200




                                                    10
                                          CHAPTER FOUR

                  BASELINE ENVIRONMENTAL AND SOCIAL CONDITIONS

4.1      Introduction
Imo State is one of the seven states created by the Federal Military Government on February 3, 1976. It
derives its name from Imo River, which takes its course from the Okigwe/Awka upland. The State lies
within latitudes 4°45'N and 7°15'N, and longitude 6°50'E and 7°25'E. It occupies the area between the lower
River Niger and the upper and middle Imo River. Imo State is bounded on the east by Abia State, on the
west by the River Niger and Delta State; and on the north by Anambra State, while Rivers State lies to the
south. The State covers an area of about 5,100sq km.

4.2      Biophysical Environment
This sub-section examines the existing biophysical environment/ conditions of the proposed intervention
project area. The baseline information pertinent to the proposed intervention project area are presented
here. These include:
•        Soil Quality;
•        Air Quality;
•        Water Quality

4.2.1 Analysis of Bio-Physical Environment
The primary data source for the project is a one-season field sampling carried out through an environmental
baseline survey conducted in December, 2018. The sample preservation techniques and chain of custody
is shown in the annex. Table 4.1 shows the sampling locations while the detailed result of analyses is
presented in Annex XIII. See Annex VI for pictures of sample collection.

4.2.1.1 Soil Physico-Chemical Properties and Quality
Soil samples were collected from each RC project area to represent the project site. Each of the samples
was randomly collected at one depth intervals (0 - 15cm of topsoil) using a stainless-steel auger. The soil
samples were then stored in plastic buckets and homogenized before sub-sampling. The samples were
subsequently stored in on ice (below 4 ºC) and transported.

4.2.1.2 Ambient Air Quality
A pre-calibrated air quality meter (GrayWolf AdanceSense TM) and Gray wolf particle counter were used
to measure the in-situ air quality parameters. The measured parameters include Carbon monoxide (CO),
Carbon dioxide (CO2), Air temperature, Humidity, Volatile Organic Carbon (VOC), Sulphur dioxide (SO2),
Nitrogen dioxide (NO2), Hydrogen sulphide (H2S) and Particulate Matter (PM 0.3-10).

4.2.1.3 Physico-Chemical Analysis of the Surface Water Samples
A pre-calibrated water quality meter (Extech DO 700 meter) was used to measure the in-situ water quality
parameters. The concentrations of the parameters were generally compared against the WHO/FMEnv
permissible limits for aquatic life and domestic use.




                                                    11
Table 4.1         Sampling point for Biophysical Environment (soil, surface water and air)
S/N     Name of Priority Site                                      X                      Y
                          Lot 1
1       Agbata-Umuigwe Na Uzoagba                                  5.5471351              7.1456688
2       Okwu-Umuonohor                                             5.5386931              7.1940632
3       Orie Mbieri-Umuomumumbieri                                 5.5833629              7.0635892
4       Ekwe-Okwuodor                                              5.725831               7.0270723
5       Umuduruemghara-Okpala Anara                                5.7103055              7.1796244
6       Umuihim Autonomous Community – Umukaku                     5.6694058              7.2049614
7       Umulogho-Okwuohia                                          5.5855616              7.3612385


1       Uzurunamu-Okwudo Mgbidi                                    5.7258524              6.8820876
2       Akama-Nansa-Akwa Ihedi                                     5.8850147              7.0069225
3       Igbee-Amaruru                                              5.8895854              6.9687548
4       Ndiuche-Izuogu Uri                                         5.8230743              7.1782618
5       Obinugwu-Umueshi-Okwa                                      5.8355695              7.1244245
6       Dikenafai-Abba Nwagele                                     5.7543142              7.1481708
7       Dimagu-Nkwere                                              5.7847093              7.1120534

1       Umueziogwu-Uzoagba-Okitankwo-Umunahu                       5.5139843              7.1066507
2       Umuebee-Umuhu                                              5.5471296              7.1456688
3       Ugbele-Bsc                                                 5.8013891              7.0774081
4       Amugu-Umulebe                                              5.8603032              7.1424667

1       Ndikpa Umucheke-Okiu                                       5.7923226              7.1956882
2       Ukolu-Umucheke                                             5.7817906              7.1951538
3       Umunaa-Uhi Owerre-Okwe                                     5.797752               7.2101361
4       Umuokpara Ofeiyi-Umuoleche                                 5.8311087              7.3200808
5       Amano-Umukogwu                                             5.8538709              7.3192942

4.2.2   Physico-Chemical Analysis of Soil, Water and Air

With regards to the soil, the pH ranges between 6.09 and 7.92 implying that the samples slightly acidic to
alkaline. The total nitrogen ranges between 13,412 and 16,750. Conductivity ranges between 1,112 and
1,890. In terms of the air samples, the analysis reveals that SO2 ranges between 0.00 and 0.01. NO2 ranges
between 0.00 and 0.02. For VOC, the values range between 0.101 and 0.154. The H2S were all below 0.01
and CO is between 0.0 and 0.2. The CO2 is between 0.0 and 0.1. Air temperature is between 28.6 and
32.7oC. The range of noise pollution across the project area is between 38.5 dB and 50.4 dB. With respect
to the analysis of water samples, the pH is between 6.57 and 7.87. For the conductivity in the water sample,
the values ranged between 401 and 689. The Dissolved Oxygen in the samples ranged between 2.53 and
6.92 while the resistivity values ranged between 3.28 and 5.76. All the water samples are clear, odourless
with temperature ranging between 30.3oC and 32.1 oC. All the samples were within the FMEnv limits. Detail
results of the physico-chemical analysis of the soil, water and air samples and the FMEnv limits are outlined
in annex XIII.




                                                     12
      4.3      Overview of the Description of the Prioritized River Crossings
      The current status of the priority sites in each lot are further illustrated in tables 4.2 – 4.5. The table also provides the description of the identified
      environmental and social issues in the priority sites. Figs. 4.1 – 4.4 shows the map of the priority sites in the four lots while plates 4.1 – 4.5 shows
      the pictures of the priority sites. The locations of the staging area, base camps and Physical Cultural Resources among others can be found in Annex
      XXI. It is noted that in all priority sites where economic trees and other sources of livelihood will be impacted, a RAP will be complemented to
      adequately address these impacts. The sub-project implementation will ensure that avoidance of impacts where feasible, is prioritized to reduce
      severity of impact in these communities.

      Table 4.2: Current Status of the Prioritized Imo RAMP-2 River Crossings (LOT 1)
S/N   Name of priority site/LGA Size of structure/ Name of Status             Environmental             Social Sensitivity                        Pictures
                                Length of RC       River                      Sensitivity
                                (m)

1     Agbata-Umuigwe Na        3 (3m X 3.5         Mba       No existing       The River overflows its The River at this section is a source of
      Uzoagba (Ikeduru/Mbatoli m)/10.3                       access bridge     banks and covers the road water for domestic use to two
      LGA)                                                   across the river. during the wet season     communities (Agbata and Umuigwe
                                                                               making it impassable.     Na Uzoagba). This may be affected
                                                                               The project site is       during the site clearing and
                                                                               surrounded by a wetland construction phase. The project site is
                                                                               with different aquatic    surrounded by economic trees which
                                                                               plants and animals. The may be cut down during site clearing.
                                                                               River is about 10m wide Impact to these assets will be captured
                                                                               and 0.8 m deep            in the standalone RAP that will be
                                                                                                         prepared. Fishing is the major
                                                                                                         economic activity carried out in the
                                                                                                         River. It is however carried out
                                                                                                         upstream and may not be affected by
                                                                                                         the project.

2     Okwu-Umuonohor             3(3m X 3.5 m)/7.3 Onuoma Dilapidated         The River overflows its   The River at this section provides
      (Ikeduru/Mbatoli LGA)                               bridge              banks and covers the      water supply for domestic use to two
                                                                              bridge during the wet     communities (Okwu and
                                                                              season making it          Umuonohor). This may be impacted
                                                                              impassable. The project   during the site clearing and
                                                                              site is surrounded by a   construction phase. Farms can be
                                                                              wetland with different    found along the river bank. They may
                                                                              aquatic plants and        be affected during site clearance.
                                                                                  13
                                                                      animals such as Bamboo, Fishing is the major economic activity
                                                                      Plantain and Alligator  carried out in the River.
                                                                      lizard respectively.

3   Orie Mbieri-             2(3m X 3.5 m)/6.0 Okatankp No existing   The project site is The River at this section provides
    Umuomumumbieri                             u        culvert       surrounded by a wetland water supply for domestic use to two
    (Ikeduru/Mbatoli LGA)                                             with different aquatic communities (Orie Mbieri and
                                                                      plants and animals such as Umuomumumbieri). This may be
                                                                      Bamboo, Plantain and affected during the site clearing and
                                                                      Alligator           lizard construction phase. Sand mining is
                                                                      respectively. The River also carried out in this River. This may
                                                                      overflows its banks and affect the sustainability of the RC. The
                                                                      covers the road during the project site is surrounded by economic
                                                                      wet season making it trees which may be cut down during
                                                                      impassable                 site clearing. Fishing is the major
                                                                                                 economic activity carried out in the
                                                                                                 River. This will be affected during
                                                                                                 construction

4   Ekwe-Okwuodor            (3m X 3.5 m)/2.8 Ikwe      No existing   The project site is        The River at this section is a source of
    (Njaba/Isu/Nkwere/Nwange                            culvert       surrounded by a wetland water for domestic use to two
    le)                                                               with different aquatic     communities (Ekwe and Okwuodor).
                                                                      plants and animals such This may be affected during the site
                                                                      as Bamboo, Plantain and clearing and construction phase. The
                                                                      Alligator lizard           project site is surrounded by economic
                                                                      respectively.. The River trees which may be cut down during
                                                                      overflows its banks and site clearing. Fishing is the major
                                                                      covers the road during the economic activity carried out in the
                                                                      wet season making it       River. It is however carried out
                                                                      impassable                 downstream and will be affected by
                                                                                                 the project.




                                                                          14
5   Umuduruemghara-Okpala (2m X 2 m)/0.6   N/A   • Existing       The project site is         The River at this section is a source of
    Anara (Isiala Mbano/Ehime                      dilapidated    surrounded by a wetland     water for domestic use to two
    Mbano LGA)                                     Culvert        with different aquatic      communities (Umuduruemghara and
                                                 • 1 X 1 single   plants and animals such     Okpala). This may be affected during
                                                   cell           as Bamboo, Plantain and     the site clearing and construction
                                                 • No drainage    Alligator lizard            phase. Farms can be found along the
                                                   before and     respectively. The River     river bank. They may be affected
                                                   after the      overflows its banks and     during site clearance. Fishing is the
                                                   culvert        covers the river crossing   major economic activity carried out in
                                                                  during the wet season.      the River. It is however carried out
                                                                                              upstream and may not be affected by
                                                                                              the project.

6   Umuihim Autonomous     3(3m X 3.5      N/A   • Undersize      The River overflows its The River at this section is a source of
    Community – Umukaku    m)/7.52                 existing       banks and covers the river water for domestic use to two
    (Isiala Mbano/Ehime                            culvert        crossing during the wet communities (Umuihim Autonomous
    Mbano LGA)                                   • 3 X 2m         season                     Community and Umukaku). This may
                                                   culvert                                   be affected during construction. The
                                                                                             project is surrounded by farmlands
                                                                                             which may be affected during site
                                                                                             clearing. Fishing is the major
                                                                                             economic activity carried out in the
                                                                                             River. It is however carried out
                                                                                             downstream.

7   Umulogho-Okwuohia      4(3m X 3.5      N/A   No existing      The project site is         The River at this section is a source of
    (Aniri/Agwu LGA)       m)/12.0               culvert          surrounded by a wetland     water for domestic use to two
                                                                  with different aquatic      communities (Umulogho and
                                                                  plants and animals such     Okwuohia). This may be affected
                                                                  as Bamboo, Plantain and     during construction. The project is
                                                                  Alligator lizard            also surrounded by farmlands which
                                                                  respectively. The River     may be affected during site clearing.
                                                                  overflows its banks and     The major economic activity carried
                                                                  covers the river crossing   out in the River is fishing. It is
                                                                  during the wet season       however carried out downstream and
                                                                  making it impassable        will be affected by the project




                                                                      15
Figure 4.1   Prioritized River Crossings in LOT 1
                                                    16
   Umulogho-Okwuohia                  Umuduruemghara-Okpala Anara




   Ekwe-Okwuodor                      Umuebee-Umuhu
Plate 4.1: River Crossings in LOT 1




                                           17
Table 4.3: Current Status of the Prioritized Imo RAMP-2 River Crossings (LOT 2)
S/N Name of priority Size of structure/ Name of    Status                  Environmental Sensitivity          Social Sensitivity                                  Pictures
    site             Length of RC (M) River

1   Uzurunamu-     4 (3m X 3.5 m)/12.3 Obana        • No existing access The river is shallow but wide. It is The Obana River at this section is a source of
    Okwudo Mgbidi                                                        surrounded by a wetland with         water for domestic use for Uzurunamu and
    (Oru East/Oru                                                        different aquatic plants and         Okwudo communities. The River is a deity and
    West/Orsu LGA)                                                       animals such as Bamboo, Plantain fishing in the river is a taboo. Boa constrictors
                                                                         and Alligator lizard respectively. (Plate 4.3 and Annex XX) are also worshipped
                                                                         The area is very swampy with         in this community so they must not be killed.
                                                                         palm trees and bamboo.               These cultural inhibitions may be affected
                                                                                                              during site clearance and construction phase.
                                                                                                              Lots of economic trees (Breadfruit, oil bean and
                                                                                                              oil palm) can be found along the river bank.
                                                                                                              These plants may be impacted during site
                                                                                                              clearance.

2   Akama-Nansa-     3(3m X 3.5 m)/10.0 Nwangele    • No existing access The river is very wide river (60 The River at this section is a source of water for
    Akwa Ihedi (Orsu                                                     meters). It is a wetland with      domestic use for the three communities (Akama,
    LGA)                                                                 different aquatic plants and       Nansa and Akwa Ihedi). This may be affected
                                                                         animals such as Bamboo, Plantain during the site clearance and construction phase.
                                                                         and Alligator lizard respectively. The project area is also surrounded by
                                                                         The area is very swampy.           farmlands. They may be affected during site
                                                                                                            clearance. Fishing is the major economic
                                                                                                            activity carried out in the River. It is however
                                                                                                            carried out upstream and may not be affected by
                                                                                                            the project.

3   Igbee-Amaruru    2(2.0m X 2.0      Ngwugwo      • Concrete slab        The project site is surrounded by The River at this section is a source of water for
    (Orsu LGA)       m)/3.56                          access               a wetland with different aquatic domestic use for the two communities (Igbee
                                                    • Boundary between     plants and animals such as         and Amaruru). This may be affected during the
                                                      Imo and Anambra      Bamboo, Plantain and Alligator site clearing and construction phase. There is
                                                      state                lizard respectively. The River     predominance of Bamboo in the project site. It
                                                                           overflows its banks and covers     is also surrounded by farmlands. They may be
                                                                           the bridge during the wet season affected during site clearance.
                                                                           making it impassable. The river is
                                                                           perennial and the area is swampy
                                                                           with the predominance of
                                                                           bamboo.




                                                                                    18
S/N Name of priority Size of structure/ Name of   Status                  Environmental Sensitivity           Social Sensitivity                                   Pictures
    site             Length of RC (M) River

4   Ndiuche-Izuogu 3(2.0m X 3.5 m)/4.5 Uri          • No existing access The project site is surrounded by The River at this section is a source of water for
    Uri (Ideato                                                          a wetland with different aquatic domestic use for two communities (Ndiuche and
    North/South LGA)                                                     plants and animals such as         Izuogu Uri). This may be affected during the
                                                                         Bamboo, Plantain and Alligator site clearing and construction phase. There is
                                                                         lizard respectively. The River     predominance of Bamboo and other economic
                                                                         overflows its banks and covers     trees like oil palm and oil bean. They are also
                                                                         the road during the wet season     surrounded by farmlands. They may be affected
                                                                         making it impassable. The river is during site clearance. Fishing is the major
                                                                         seasonal                           economic activity carried out in the River. It is
                                                                                                            however carried out upstream and may not be
                                                                                                            affected by the project.

5   Obinugwu-        3(3m X 3.5 m)/10   Okwa        • Undersized culvert The project site is surrounded by    The River at this section provides water for
    Umueshi-Okwa                                    • 2 X 2 cell         a wetland with different aquatic     domestic use to three communities (Obinugwu,
    (Ideato                                                              plants and animals such as           Umueshi and Okwa). This may be affected
    North/South LGA)                                                     Bamboo, Plantain and Alligator       during the site clearing and construction phase.
                                                                         lizard respectively. The River       The project site is also surrounded by farmlands.
                                                                         overflows its banks and covers       They may be affected during site clearance.
                                                                         the culvert during the wet season
                                                                         making it impassable


6   Dikenafai-Abba 3(3m X 3.5 m)/10.3 Nwamurum      • The existing access The project site is surrounded by   The River at this section provides water for
    Nwagele (Ideato                   uru             is a 900 m steel a wetland with different aquatic       domestic use to two communities (Dikenafai
    North/South LGA)                                  pipe.               plants and animals such as          and Abba Nwagele). It is bordered by a palm oil
                                                                          Bamboo, Plantain and Alligator      processing factory (about 200 meters). This may
                                                                          lizard respectively.                be affected during construction. There are also
                                                                                                              economic trees (oil palm and Bamboo) very
                                                                                                              close to the project site. They may also be
                                                                                                              affected during site clearance. There will be ne
                                                                                                              be the need for a resettlement action plan.

7   Dimagu-Nkwere 3(3m X 3.5 m )/8.2 Urashi         • Dilapidated         The river width is about 7 meters. The River at this section provides water supply
    (Ideato                                           existing bridge     It is surrounded by a wetland with for domestic use to two communities (Dimagu
    North/South LGA)                                • 4m X 6M             different aquatic plants and and Nkwere). This may be affected during the
                                                                          animals such as Bamboo, Plantain site clearance and construction phase. Presence
                                                                          and Alligator lizard respectively. of economic trees (oil palm and Bamboo) around
                                                                          The River overflows its banks and the project site. They may be affected during site
                                                                          covers the bridge during the wet clearance. Fishing is the major economic activity
                                                                          season making it impassable        carried out in the River. It is however carried out
                                                                                                             downstream and will be affected by the project.


                                                                                   19
Figure 4.2   Prioritized River Crossings in LOT 2
                                                    20
 Uzurunamu-Okwudo Mgbidi                  Ndiuche-Izuogu Uri




 Umuisu- Umunaga                           Igbee-Amaruru


Plate 4.2: River Crossing in LOT 2




                                     21
Plate 4.3: Boa
Source: Onyeakagbu (2019)




                            22
Table 4.4: Current Status of the Prioritized Imo RAMP-2 River Crossings (LOT 3)
S/N    Name of priority site   Size of         Name of     Status              Environmental Sensitivity         Social Sensitivity                 Pictures
                               structure       River

1      Umueziogwu-Uzoagba- 3(3m X 3.5 m)       Okitankwo    • Undersize        The project site is surrounded     The River at this section is a
       Okitankwo-Umunahu                                      bridge           by a wetland with different        source of water for domestic
       (Owerri East/West                                                       aquatic plants and animals         use to four communities
       LGA)                                                                    such as Bamboo, Plantain and       (Umueziogwu-Uzoagba-
                                                                               Alligator lizard respectively.     Okitankwo-Umunahu). This
                                                                               The River overflows its banks      may be affected during the
                                                                               and covers the road during the     site clearing and construction
                                                                               wet season making it               phase.
                                                                               impassable

2      Umuebee-Umuhu           6(3m X 3.5 m)   Urashi       • Existing         The project site is surrounded     The River at this section is a
       (Owerri East/West                                      wooden           by a wetland with different        source of water for domestic
       LGA)                                                   bridge is        aquatic plants and animals         use for two communities
                                                              damaged          such as Bamboo, Plantain and       (Umuebee and Umuhu). This
                                                            • River width is   Alligator lizard respectively.     may be affected during the
                                                              about 20 m       The River overflows its banks      site clearing and construction
                                                                               and covers the road during the     phase. Bamboo trees are
                                                                               wet season making it               predominant around the
                                                                               impassable. The project site is    project site. These may be
                                                                               surrounded by farmlands.           affected during site clearance.
                                                                               They may be affected during
                                                                               site clearance. The River
                                                                               overflows its banks and covers
                                                                               the river crossing during the
                                                                               wet season

3      Ugbele-BSC (Ideato      6(3m X 3.5 m)   Ikwe         • Dilapidated The project site is surrounded          The River at this section is a
       South LGA)                                             existing iron by a wetland with different           source of water for domestic
                                                              bridge        aquatic plants (bamboo and            use for two communities
                                                                            palm tree) and animals. The           (Ugbele and BSC). This may
                                                                            River overflows its banks and         be affected during the site
                                                                            covers the culvert during the         clearance and construction
                                                                            wet season making it                  phase. The project site is
                                                                            impassable.                           surrounded by farmlands
                                                                                                                  (with cassava, yam and maize

                                                                          23
                                                                                                as major farm produce). These
                                                                                                may be affected during site
                                                                                                clearance. Fishing is the
                                                                                                major economic activity
                                                                                                carried out in the River. It is
                                                                                                however carried out upstream
                                                                                                and may not be affected by
                                                                                                the project.

4   Amugu-Umulebe        3(3m X 3.5 m)   Ikwu   • Dilapidated   The River overflows its banks   The River at this section is a
    (Ideato South LGA)                            existing      and covers the culvert during   source of water for domestic
                                                  culvert       the wet season making it        use to two communities
                                                • 5m X 5m       impassable. Predominance of     (Amugu and Umulebe). This
                                                  culvert       bamboo around the project       may be affected during the
                                                • 2 X 2 cell    site. They may be affected      site clearing and construction
                                                                during site clearance.          phase. Fishing is the major
                                                                                                economic activity carried out
                                                                                                in the River. It is however
                                                                                                carried out downstream and
                                                                                                will be affected by the project.




                                                           24
Figure 4.3   Prioritized River Crossings in LOT 3
                                                    25
                                           Umueziogwu-Uzoagba-Okitankwo-
  Ugbele-BSC                               Umunahu




 Ikwe Ezelu-Owere Okwe                     Umuebee-Umuhu

Plate 4.4: River Crossings in LOT 3




                                      26
      Table 4.5: Current Status of Prioritized Imo RAMP-2 River Crossings (LOT 4)
S/N   Name of priority site/LGA Size of structure/ Length Name of River   Status                   Environmental               Social Sensitivity                     Picture
                                of RC (M)                                                          Sensitivity

1     Ndikpa Umucheke-Okiu      2(3m X 3.5m)/ 5.10      Ekwi Ogbo          • No existing culvert The river is seasonal.        The project area is surrounded by
      (Onuimo LGA)                                                                               The River crosses the         some economic trees, which may
                                                                                                 road during the wet           be affected during site clearance
                                                                                                 season making it              and construction. Fishing is the
                                                                                                 impassable.                   major economic activity carried
                                                                                                                               out in the River. It is however
                                                                                                   .                           carried out upstream and may not
                                                                                                                               be affected by the project.




2     Ukolu-Umucheke (Onuimo (3m X 3.5 m)/3.0           Ikwe Umunanama     • No existing culvert   The river is seasonal.      The River at this section is a
      LGA)                                                                                         The River crosses the       source of water supply for
                                                                                                   road during the wet         domestic use for two communities
                                                                                                   season making it            (Ukolu and Umucheke). This may
                                                                                                   impassable.                 be affected during the site clearing
                                                                                                                               and construction phase. The
                                                                                                                               project site is surrounded by
                                                                                                                               Farmlands (with major farm
                                                                                                                               produce such as cassava, yam and
                                                                                                                               maize). They may be affected
                                                                                                                               during site clearance and
                                                                                                                               construction.

3     Umunaa-Uhi Owerre-Okwe 3(3m X 3.5 m)/10           N/A                • Existing dilapidated It is a seasonal river but   The River at this section is a
      (Onuimo LGA)                                                           culvert              overflows in wet season.     source of water for domestic use
                                                                           • 2 X 1 single cell The project site is             for Umunna and Uhi Owerre-
                                                                             culvert              surrounded by a wetland      Okwe communites. This may be
                                                                                                  with different aquatic       affected during the site clearing
                                                                                                  plants and animals such      and construction phase. There are
                                                                                                  as Bamboo, Plantain and      economic trees such as Bamboo
                                                                                                  Alligator lizard             and palm tree in close proximity
                                                                                                  respectively. The River      to the project site which may be
                                                                                                  overflows its banks and      affected during site clearance.
                                                                                                  covers the culvert during
                                                                                                  the wet season making it
                                                                                                  impassable.




                                                                                           27
4   Umuokpara Ofeiyi-      4(3m X 3.5 m)/12.0   N/A   • Blocked culvert    The culvert is blocked      The project site is within the
    Umuoleche (Okigwe LGA)                                                 due to siltation and is     Umuopara Ofeiyi community.
                                                                           currently causing gully
                                                                           erosion in adjoining
                                                                           areas.




5   Amano-Umukogwu          2(3m X 3.5 m)/5.0   N/A   • Dilapidated bridge The project site is        The River at this section is a source
    (Okigwe LGA)                                      • 2m X 0.8m          surrounded by a wetland    of water for domestic use for
                                                                           with different aquatic     Amano         and       Umukogwu
                                                                           plants and animals such    communities. This may be affected
                                                                           as Bamboo, Plantain and    during the site clearing and
                                                                           Alligator lizard           construction phase. The project site
                                                                           respectively. The River    is surrounded by Farmlands (with
                                                                           overflows its banks and    major farm produce such as
                                                                           covers the bridge during   cassava, yam and maize which may
                                                                           the wet season making it   be affected during site clearance
                                                                           impassable. Not suitable   and construction.
                                                                           for motorized vehicle
                                                                           transport.




                                                                     28
Figure 4.4   Prioritized River Crossings in LOT 4
                                                    29
 Umuokpara Ofeiyi-Umuoleche               Ukolu-Umucheke




 Umunaa-Uhi Owerre-Okwe                   Amano-Umukogwu

Plate 4.5 River Crossings in LOT 4




                                     30
     4.4     Socio-Economic Environment
     The result from the socio-economic survey conducted based on the lots is shown in Table 4.6.

     Table 4.6 Socio-economic Characteristics of the consulted persons in the Communities
S/N Socio-          (LOTS)
    Economic
    Indicator      Lot 1                                                  Lot 2                                             Lot 3                                              Lot 4
                   Ikeduru/Mbatoli/Njaba/Isu/Nkwere/Nwangele/             Oru East/Oru West/Orsu/ Ideato North/Ideato South Owerri East/Owerri West/ Ideato South              Onuimo/ Okigwe
                   Isiala Mbano/Ehime Mbano/Aniri/Agwu
1   Gender         There were more males (52.0%) than females               There were more males (57.0%) than females There were more males (54.0%) than                        There were more males (51.0%) than females (49.0%)
                   (47.0%) respondents. This implies that the study         (43.0%) respondents. This implies that the study tried females (46.0%) respondents. This             respondents. This implies that the study tried to observe
                   tried to observe gender balance in the selection of      to observe gender balance in the selection of implies that the study tried to observe                gender balance in the selection of respondents, hence both
                   respondents, hence both gender voices were taken         respondents, hence both gender voices were taken gender balance in the selection of                  gender voices were taken into account.
                   into account.                                            into account.                                            respondents, hence both gender voices
                                                                                                                                     were taken into account.
2   Age            The highest proportion of the respondents (55.0%) Age groups between 18-45 years constitute the                   Age groups between 18-45 years              The highest proportion of the respondents (54.0%) falls
                   falls within the age range of 45–65 years. This is       highest proportion of the respondents with 56.0%. constitute the highest proportion of the           within the age range of 45–65 years. This is followed by
                   followed by 18–44 years (31.0%) and 65 and above 46–65 years age group constitutes 34.0% of the                   respondents with 66.0%. 46–65 years age 18–45 years (31.0%) and 65 and above (15.0%). This
                   (14.0%). This indicates a potential of availability of respondents while 66 years and above are about             group constitutes 24.0% of the              indicates a potential of available active work force (labour)
                   active work force (labour) in the project areas.         10.0%. This indicates a potential of available active respondents while 66 years and above are in the project areas.
                                                                            work force (labour) in the project areas.                about 10.0%. This indicates a potential of
                                                                                                                                     available active work force (labour) in the
                                                                                                                                     project areas.
3   Ethnic group The respondents in these areas belong mainly to the The respondents in these areas belong mainly to the The respondents in these areas belong                   The respondents in these areas belong mainly to the Igbo
                   Igbo ethnic group (100%). This points to ethnic          Igbo ethnic group (100%). This points to ethnic          mainly to the Igbo ethnic group (100%). ethnic group (100%). This points to ethnic homogeneity in
                   homogeneity in the project area and the possible         homogeneity in the project area and the possible         This points to ethnic homogeneity in the the project area and the possible ease of consultation for
                   ease of consultation for the project.                    ease of consultation for the project.                    project area and the possible ease of       the project.
                                                                                                                                     consultation for the project.
4   Literacy level About 58.5.0% of the respondents in this settlement Literacy level is high in this settlement with only           About 65.0% of the respondents in this      Literacy level is high in this settlement with only 76.0% of
    / Language(s) have a definite form of formal education, basically 72.0% of the respondents with formal education.                settlement have a definite form of formal the respondents with formal education. This contributes
    spoken         up to secondary school level, hence they can read This contributes similarly to the language spoken as education, basically up to secondary                   similarly to the language spoken as most can read and
                   and write in English and local Language. This can most can read and write in English and their mother school level, hence they can read and                   write in English and their mother language. This can be
                   be related to the potential ease of communication language. This can be related to the potential ease of write in English and local Language. This related to the potential ease of communication and
                   and reduction in conflict which may be caused by communication and reduction in conflict which may can be related to the potential ease of                    reduction in conflict which may be caused by poor
                   poor understanding of the project                        be caused by poor understanding of the project           communication and reduction in conflict understanding of the project
                                                                                                                                     which may be caused by poor
                                                                                                                                     understanding of the project
5   Marital Status Most of the respondents (69.0%) are married while Most of the respondents in this settlement are                  Most of the respondents are married 43.0% Most of the respondents are married 71.0% while 10.0%
                   16.0% are single. The widows/widowers (15.0%) married 70.5% while 22.5% are single. The                           while     36.0%      are      single.  The are single. The widows/widowers (19.0%) are mostly
                   are mostly within the aged age group. The                widows/widowers (7.0%) are mostly within the aged widows/widowers (21.0%) are mostly within the aged age group. The predominance of married
                   predominance of married individuals among the            age group. The predominance of married                   within the aged age group.             The individuals in the project area points to the possibility of
                   respondents in the project area points to the            individuals in the project area points to the            predominance of married individuals in the population increase. It is also a sign of maturity and
                   possibility of population increase. It is also a sign of possibility of population increase. It is also a sign of project area points to the possibility of responsibility implying that youth restiveness may not be a
                   maturity and responsibility implying that youth          maturity and responsibility implying that youth          population increase. It is also a sign of problem to the project.
                   restiveness may not be a problem to the project.         restiveness may not be a problem to the project.         maturity and responsibility implying that
                                                                                                                                     youth restiveness may not be a problem to
                                                                                                                                     the project.


                                                                                                              31
6   Occupation     Categories of occupation classifications recognizedThere are two basic occupational groups identified Categories of occupation classifications Categories of occupation classifications recognized within
                   within these communities include: 85.0% are        within this settlement. Most of the individuals are recognized within this community               this community include: 70.0% are farmers, Others (30%)
                   farmers. Others who are engaged in small scale     farmers (74.0%), while others are self-employed        include: 65.0% are farmers. Other           are engaged in small scale business and trading. This
                   business and trading, make up 15%. This indicates  individuals including traders (26.0%). This indicates respondents which are engaged in small indicates that the respondents are economically
                   that the respondents are economically empowered.   that the respondents are economically empowered. It scale business and trading make up 35%. empowered. It also shows that care must be taken to reduce
                   It also shows that care must be taken to reduce thealso shows that care must be taken to reduce the       This indicates that the respondents are     the impact of the project on farms as it is the main source
                   impact of the project on farms as it is the main   impact of the project on farms as it is the main       economically empowered. It also shows of livelihood to most of the respondents
                   source of livelihood to most of the respondents    source of livelihood to most of the respondents        that care must be taken to reduce the
                                                                                                                             impact of the project on farms as it is the
                                                                                                                             main source of livelihood to most of the
                                                                                                                             respondents
7 Size of      This ranged from 1-3 members (19.0%), 4-6              The household size ranged from 1-3 (11.0%), 4-6        The household size ranged from: 1-3         The family sizes in these communities can be classified
   Households members (31.0%), 7-10 members (38.0%) and               (55.0%), 7-10 (15.0%) and above 15 members             members (22.0%), 4-6 members (21.0%), into four groups. The first group has a minimum of 1-3
   of the      above 15 members (12.0%). The average family           (19.0%). Hence, the family size tends towards an       7-10 members (23.0%) and above 15           members (21.0%), the second group ranges from 4-6
   Respondents size is 8 in the communities. With the large family average of 8. With the large family sizes, care must members (34.0%). The average family              members (25.0%), the third group has a range of 7-10
               sizes, care must be taken to protect the family’s      be taken to protect the family’s sources of livelihood size is 8 in the communities. With the      members (38.0%) and the last group have 15 family
               sources of livelihood (farming) from the impact of (farming) from the impact of the project as the            large family sizes, care must be taken to members and above (15.0%). The average family size is 8
               the project, as the number of people that will be      number of people that will be affected are many.       protect the family’s sources of livelihood in the communities. With the large family sizes, care must
               affected are many.                                                                                            (farming) from the impact of the project be taken to protect the family’s sources of livelihood
                                                                                                                             as the number of people that will be        (farming) from the impact of the project as the number pf
                                                                                                                             affected are many.                          people that will be affected are many.
8 Income Level Total income structure of the respondents showed Total income structure of the respondents showed Total income structure of the respondents Total income structure of the respondents showed that 38%
   of the      that most (70.0%) earn less than N20,000 a month. that most (48.5%) earn less than N20,000 a month. showed that most (57.0%) earn less than earn less than N20,000 a month. 45.0% earn between
   respondents 18.0% earn between N20,000–N50,000 a month, 30.0% earn between N20,000 -N50,000 a month                       N20,000 a month. 38.0% earn between         N20,000 -N50,000 a month while those that earn greater
               while those that earn above N50,000 constitute         while those that earn greater than N50,000 constitute N20,000–N50,000 a month, while those than N50,000 constitute 22% of the population. This
               12.0% of the population. This indicates that most of 21.5% of the population. This indicates that most of that earn above N50,000 constitute 5.0% indicates that most of the respondents are vibrant
               the respondents are vibrant individuals who look for the respondents are vibrant individuals who look for of the population. This indicates that most individuals who look for every opportunity they get to
               every opportunity they get to generate income that every opportunity they get to generate income that of the respondents are vibrant individuals generate income that will help sustain their families among
               will help sustain their families among other           will help sustain their families among other           who look for every opportunity they get other endeavors. The proposed intervention will further
               endeavors. The proposed intervention will further endeavors. The proposed intervention will further to generate income that will help sustain increase the income level of the respondent especially
               increase the income level of the respondents           increase the income level of the respondents           their families among other endeavors.       through participation in the project, which will improve
               especially through participation in the project which especially through participation in the project which The proposed intervention will further        their mobility and marketing of their farm produce.
               improve their mobility and the marketing of their will improve their mobility and the marketing of            increase the income level of the
               farm produce.                                          their farm produce.                                    respondents especially through
                                                                                                                             participation in the project, which will
                                                                                                                             improve their mobility and the marketing
                                                                                                                             of their farm produce.
0 Waste        Most of the residents which accounts for 46.0%,        Most of the respondents in these communities           Most of the residents (59%) use the         Most of the residents in these communities (about 52%)
   Management dispose their waste through the use of community deposit their waste at the backyard of their houses community dumpsites. This is followed deposit their waste at the backyard of their houses. While
   Approaches dumpsites. This is followed by 26.0% residents          (60%), while about 20% burn their refuses and 20% by 26% residents who burn their waste            about 10% dump in the river or stream, 38% burn their
               who burn their waste and 28.0% of other that dump dump their refuse in the stream or river. The               while 5% usually dump the refuse in their refuses. The dumping of refuse in rivers and streams may
               their refuse in their backyard or in the stream/river. dumping of refuse in rivers and streams may have backyard and 10% in the stream/river.             have impact on the life span of the proposed RCs.
               The dumping of refuse in rivers and streams may impact on the life span of the proposed RCs.                  The dumping of refuse in rivers and
               have impact on the life span of the proposed RCs                                                              streams may have impact on the life span
               by blocking access to waterflow.                                                                              of the proposed RCs.
10 Sources of  Most respondents (95%) in the communities have Most respondents (97%) in the communities have Most respondents (97%) in the                               Most respondents (98%) in the communities have access to
   Water       access to the Rivers in this Lot and thus depend on access to the Rivers in this Lot and thus depend on it communities have access to the Rivers in the Rivers in this Lot and thus depend on it as main source
               it as main source of water for drinking, cooking and as main source of water for drinking, cooking and this Lot and thus depend on it as main             of water for drinking, cooking and bathing & washing.
               bathing & washing. Other sources include as            bathing & washing. Other sources include rainwater source of water for drinking, cooking and Other sources include rainwater harvesting mainly in the
               rainwater harvesting mainly in the rainy season        harvesting mainly in the rainy season (3%), wells      bathing & washing. Other sources include rainy season (2%), wells and boreholes are also prominent
                                                                                                          32
                (5%), wells and boreholes are also prominent in the and boreholes are also prominent in the community. rainwater harvesting mainly in the rainy in the community. Care must therefore be taken to protect
                community. Care must therefore be taken to protect Care must therefore be taken to protect the River   season (3%), wells and boreholes are also the River from pollution
                the River from pollution.                            from pollution                                    prominent in the community. Care must
                                                                                                                       therefore be taken to protect the River
                                                                                                                       from pollution
10 Ethno-       In terms of ethnic homogeneity, most of the          The communities are historically homogenous       In terms of ethnic homogeneity, most of About 90% of the respondents indicated that the
   cultural     respondents in the communities (80.0%) reckoned (87%). There are no records of ethnic clashes or       the respondents (80.0%) reckoned that the communities are historically homogenous. There are no
   Dynamics     that the settlement is historically homogenous.      crises in the communities, especially with Fulani communities are historically homogenous records of ethnic clashes or crises in the communities.
                There are few records of major or deadly ethnic      cattle herders.                                   but heterogeneous in terms of population.
                clashes or crises in the communities.                                                                  There are no records of major or deadly
                                                                                                                       ethnic clashes or crises in the
                                                                                                                       communities
11 Awareness of Most of the respondents (80%) claimed they have no Most of the respondents (85%) depict poor Most of the respondents (90%) claimed The respondents (80%) depict poor knowledge of the
   the Proposed prior-knowledge of the project. They are however in knowledge of the proposed project. They however they have no prior-knowledge of the proposed project. They however claimed to be satisfied with
   River        support of the scheme and willing to assist in claimed to be satisfied with the proposed project.                   This indicates that public the proposed intervention. This indicates that public
   crossing     ensuring the success of the project. This indicates intervention. This indicates that public awareness awareness needs to be carried out to awareness needs to be carried out to enlighten the
                that public awareness needs to be carried out to needs to be carried out to enlighten the communities enlighten the communities of the proposed communities of the proposed project to reduce potential
                enlighten the communities of the proposed project to of the proposed project to reduce potential project to reduce potential misconceptions misconceptions
                reduce potential misconceptions                      misconceptions




                                                                                                    33
                                  CHAPTER FIVE
                   POTENTIAL ENVIRONMENTAL AND SOCIAL IMPACTS

5.1      Introduction
This project is envisaged to make numerous positive contributions to the households, communities and
state, however, there are also potential negative impacts associated with project activities as discussed
in the subsequent sections. Table 5.1 provides an overview of project activities likely to generate
adverse impacts during project implementation and operation.

Table 5.1: Project implementation phases and associated activities
S/N       Project Phase         Activities

1         Pre-Construction        • Sensitization
                                  • Mobilisation
                                  • Site clearing
                                  • Clearing Safety measures
                                  • Material sourcing
                                  • Staging area
                                  • Workers camp
2         Construction             • Earthworks including excavation and grading
                                   • Provision of lateritic sub-base and base course (150mm)
                                   • Side Drains
                                   • Culvert works
                                   • Utilization of borrow pits
3         Post-Construction        • Road usage
          /Operational             • Maintenance and Repairs
          /Maintenance             • scheduled and unscheduled integrity checks for bridges and culverts
                                   • maintenance and replacement of wearing/faulty/damaged components
                                   • repairs of cracks and potholes
                                   • Cleaning of drains where and when necessary
                                   • Cleaning and vegetation control along the shoulders
                                   • Borrow pit reclamation


5.2     Potential Environmental and Social Impacts
5.2.1 Positive Environmental and Social Impacts
5.2.1.1 Positive Environmental Impacts

      •   Elimination of poor state of the river crossings;
      •   Rehabilitation of degraded river crossings and their conversion into productive use;
      •   Improved aesthetics of the environment

5.2.1.2 Positive Social Impacts

      •   Local sale of food and other items to workers on the site by the host community members;
      •   Opportunities for locals to supply construction materials;
      •   Employment of local labour for site clearance, construction and operations;
      •   Enhanced access and mobility for the people and movement of agricultural products;
      •   Increase in inter-communal socio-economic exchange;
      •   Reduction of disaster risks zones in the project area;
      •   Access to market-induced increase in production;
      •   Greater diversity in production and in farmers income;
                                                    34
   •   Reduction in cost of transportation

5.2.2 Potential Negative Environmental and Social Impacts
5.2.2.1 Potential Negative Environmental Impacts

   •   Ambient air pollution from release of dusts and gaseous emissions
   •   Loss of soil quality from de-vegetation and erosion
   •   Vegetation loss from preparation activities such as land clearing
   •   Generation of vegetal wastes and other cleared materials
   •   Fauna habitat alteration due to site clearing and construction activities
   •   Material sourcing, borrow pit formation and management
   •   Staging area impacts
   •   Impact on fish habitat
   •   Noise and vibration from the use of machineries and motorized equipment
   •   Generation of spoils and other construction wastes
   •   Slope instability arising from excavation to construct drainages
   •   Increased surface water run-off due to diversion during construction.
   •   Predisposition of soil erosion resulting from improper abandonment of borrow pit
   •   Underground water pollution from spillages & leakages from oil storage tanks.

5.2.2.2 Potential Negative Social Impacts

   •   Impact on shrines and cultural beliefs/areas
   •   Loss of farmland and economic trees
   •   Businesses could be impacted such as the palm oil processing factory that was observed in
       Dikenafai community
   •   Poor implementation of occupational health and safety measure which could lead to the risk of
       workers drowning in the river
   •   Security issues that may lead to stealing of contractor equipment mobilized to site
   •   Cultural conflicts due to fetching of water in Obana river on small Orie day
   •   Increase in vehicular movement may cause traffic congestion and accidents
   •   Risks of occupational and social accidents and injuries in using the new river crossings
   •   Risk to community health and safety and exacerbation of the risk of transmission of
       HIV/AIDS and other STIs due to increase population.
   •   Increase in crime rate (including prostitution, theft and substance abuse)
   •   Adverse impacts on community dynamics Threat to community culture due to labour influx
   •   Increased burden on public service Provision
   •   Labour influx issues such as: Gender-based violence, including sexual harassment, child
       abuse and exploitation
   •   Impact on the livelihood of fishing communities
   •   Local inflation of prices and crowding out of local consumer
   •   Increased pressure on accommodation and rents
   •   Impact on water supply to communities and increased demand on freshwater resources
   •   Camp related land use, access roads, noise and lights
   •   Increased use/demand on natural resources
   •   The impact of dumping of refuse in rivers and streams on the life span of the proposed RCs
       by blocking access to waterflow.

                                                35
                           CHAPTER SIX
    ENVIRONMENTAL AND SOCIAL IMPACT MANAGEMENT AND MONITORING
                           PROGRAMME
6.1 Introduction
As part of this ESMP, a project specific environmental and social management and monitoring plan has
been designed. This plan establishes environmental and social action plans with well-defined desired
outcomes and actions to address all potential impacts identified for the proposed project. The plan also
includes elements such as parameters to be measured, methods of measurement, location of
measurement, and with estimates of the resources and responsibilities for monitoring. The plan is
presented in Table 6.1.




                                                  36
Table 6.1: Environmental and Social Mitigation and Monitoring Plan during the Pre-Construction Phase
S/N Activity            Potential Impacts     Mitigation/Enhancement           Mitigation        Cost of Mitigation Indicators/Paramet Method of   Sampling     Frequency Monitoring      Cost of
                                              Measures                         Responsibility                       ers                Measurement Location     of         Responsibility Monitoring
                                                                               (Implementatio                                                                   Monitoring (Supervision) USD$ NGN
                                                                               n)
                                                                                                  USD$     NGN

Environmental Impacts

A1    • Sensitization Noise and vibration •            Maintain equipment and Contractor        320      115,000   • Noise   Levels • In-Situ   Construction Daily                          150   54,000
      • Mobilization from the use of                   machineries adequately to                                     (Not to exceed Measureme Site and                     Environmental
      • Site clearing motorized vehicles               reduce their noise levels                                     90dB(A)          nt        surrounding                Safeguards
      • Clearing Safety and equipment     •            Fit machineries and                                         • Records     of • Sighting  area                       Officer (ESO),
        measures                                       heavy-duty     equipment                                      Equipment      • Complaint                            SPIU
      • Material                                       with               exhaust                                    Maintenance      Register
        sourcing                                       mufflers/silencers       to                                                                                         SMEnv
      • Staging area                                   minimize             noise
      • Workers camp                                   generation
                                          •            Avoid unnecessary idling
                                                       of internal combustion
                                                       engines
A2                      Ambient air          •         Suppress dust emissions Contractor       320      115,000   • Suspended         • In-Situ   Construction Daily      ESO              100   36,000
                        pollution from                 by appropriate methods                                        Particulates        Measureme Site and
                        release of dusts and           such as spraying water on                                     (SPM),       SO2, nt          surrounding             SMEnv
                        gaseous emissions              soil                                                          NOx, CO, THC                  area
                                             •         Maintain vehicles in good                                   • Vehicle Exhaust
                                                       working condition.                                            Measurements
                                              •        Ensure exhaust fumes                                        • Records        of
                                                       from vehicles conform to                                      maintenance for
                                                       applicable       National                                     all machineries
                                                       standards              and                                    and equipment
                                                       specifications
A3                      Soil contamination        •   Ensure fuel storage tanks Contractor      320/     115,000   Soil        quality In situ/ and Project site Monthly   ESO              100   36,000
                        from accidental               are leak-proof,                                              parameters          Laboratory
                        leakage/spillage of       •   checked daily & installed                                    (especially         analysis                            SMEnv
                        fuel, oil and                 in a bunded area                                             hydrocarbon
                        lubricants                •   Establish procedures for                                     contaminants)       Visual
                                                      storage & handling of                                                            observation
                                                      hazardous materials.                                         Compliance with
                                                  •   Implement       emergency                                    fuel        storage
                                                      response plan as part of                                     procedures
                                                                                                37
S/N Activity   Potential Impacts   Mitigation/Enhancement             Mitigation        Cost of Mitigation Indicators/Paramet Method of   Sampling       Frequency Monitoring      Cost of
                                   Measures                           Responsibility                       ers                Measurement Location       of         Responsibility Monitoring
                                                                      (Implementatio                                                                     Monitoring (Supervision) USD$ NGN
                                                                      n)
                                                                                        USD$      NGN

                                        OHS Plan to deal with
                                        spillage in line with annex
                                        XIV

A4             Loss of soil quality •   Avoid       removal      of Contractor         300      108,000   • % of Vegetal • Visual         Construction   During site ESO         150    54,000
               from de-vegetation       vegetation and trees to the                                         Loss           estimate       Site and       clearing
               and erosion              extent possible                                                   • Revegetated                   surrounding    and         SMEnv
                                    •   Protect all vegetation not                                          areas                         area           constructio
                                        required to be removed                                                                                           n
                                        against damage
                                   •    Re-vegetate exposed soil
                                        quickly
A5             Impact on fish      •    Washing of Project plant Contractor            150      54,000    • Records of fish • Complaint   Construction   During site             50     18,000
               habitat and water        and       vehicles       in                                         catch             Register    Site and       clearing
               quality                  watercourses will not be                                          • Visual                        surrounding    and
                                        undertaken                                                          monitoring                    area           constructio
                • Reduced primary •     Avoid direct impacts (i.e.                                        • Probe                                        n
                  productivity in       habitat disturbance in the                                          monitoring
                  fisheries,            channel) or increases in
                • Potential impact      suspended sediments in
                  on fish spawning      the water in the rivers
                  and bank-nesting      especially      in      the
                • degradation of        spawning season
                  spawning habitat •    Watercourse        crossing
                • Habitat loss,         methods        will      be
                  fragmentation         developed with the aim of
                  and degradation       minimising              the
                  leading to            mobilisation of sediments
                  potential loss of •   Daily visual monitoring
                  specie                of turbidity will be
                • restriction of fish   undertaken      at    river
                  movement and          crossings while works are
                  reduced               being undertaken at that
                  reproductive          river
                  success
                                                                                       38
S/N Activity   Potential Impacts   Mitigation/Enhancement    Mitigation        Cost of Mitigation Indicators/Paramet Method of   Sampling      Frequency Monitoring      Cost of
                                   Measures                  Responsibility                       ers                Measurement Location      of         Responsibility Monitoring
                                                             (Implementatio                                                                    Monitoring (Supervision) USD$ NGN
                                                             n)
                                                                               USD$      NGN

                                   •   Only              essential
                                       construction vehicles (as
                                       approved       by       the
                                       Company)        will     be
                                       allowed to enter rivers or
                                       streams and only with
                                       prior examination of the
                                       vehicles for fuel/lubricant
                                       leaks
                                   •   Construction traffic will
                                       cross watercourses via a
                                       flume/culvert        (piped
                                       bridge), which will be
                                       sized so as not to restrict
                                       the    flow      in     the
                                       watercourse and allow
                                       fish and other aquatic
                                       organisms to pass through
                                   •   The     river      crossing
                                       contractor will prepare a
                                       plan to respond to an
                                       outbreak of pollution,
                                       including clean up and
                                       remediation for outbreak
                                       and      liaison       with
                                       downstream users
A6             Generation of      •    Comply with the Waste Contractor       200      72,000    • Contractors     • Visual        Construction Weekly   ESO           100    36,000
               vegetal wastes and      Management             Plan                                 Compliance to     observation   Site and
               other cleared           (WMP) in Annex XVII                                         WMP             • Waste         surrounding           SMEnv
               materials          •    Promote               waste                               • On-site Waste     Tracking      area
                                       avoidance;      reduction;                                  management        Report
                                       reuse and recycling as                                      techniques
                                       applicable
                                   •   Ensure proper handling,
                                       and disposal of wastes

                                                                              39
S/N Activity           Potential Impacts   Mitigation/Enhancement             Mitigation        Cost of Mitigation Indicators/Paramet Method of   Sampling         Frequency Monitoring      Cost of
                                           Measures                           Responsibility                       ers                Measurement Location         of         Responsibility Monitoring
                                                                              (Implementatio                                                                       Monitoring (Supervision) USD$ NGN
                                                                              n)
                                                                                                USD$      NGN

                                                (especially contaminated
                                                soil,    concrete,    oils,
                                                grease, lubricants, metals,
                                                etc.)
Social Mitigation and Monitoring Plan

      • Sensitization Loss of farmland as •     Implementation of              • Imo State To be provided by      • RAP/ARAP         • Assessment Impacted         All issues FPMU         Provided in the
      • Mobilization well as land-based         measures outlined in the         RAMP-       the RAP/ARAP           Prepared           by the SPIU communities     should be               RAP/ARAP
      • Site clearing livelihood including      RAP/ARAP which will              SPIU;                            • Implementation to determine                    settled     Imo State
      • Clearing Safety economic trees and      outline the mitigation         • Imo State                          s     of      the if         the               before the RAMP-SPIU;
        measures        crops                   measures and                     Ministry of                        requirements of objectives of                  start of
      • Material                                compensation where               Land and                           the resettlement the                           civil works Imo State
        sourcing                                eligible.                        Survey.                            instrument         resettlement                            Ministry of
                                                                                                                                       instrument                              Land and
      • Staging area
                                                                                                                                       have been                               Survey.
      • Workers camp
                                                                                                                                       achieved.
A7                     Grievances and       •   Continuous community           • Social    160          57,600    • Regular          • Evidence of Impacted        Throughou FPMU       50         18,000
                       conflict arising         engagement/consultation          Safeguard                          consultations      consultation, communities   t project
                       potentially from     •   Establishment of                 Officers,                          with               e.g., minute                implement Imo State
                       members of the           grievance redress                GRCs                               stakeholders       of meetings                 ations    RAMP-SPIU;
                       community asked to       mechanism (GRM) to                                                  and members of pictures
                       vacate areas             receive and address                                                 the              • Number of
                       allocated for the        concerns                                                            communities        complaints
                       project especially                                                                         • Implementation received and
                       the drainage channel                                                                         of GRM             resolved.

A8                     Security issues that • Engage competent            Contractor           160      57,600    • Regular       • Log book       Community/ Monthly        Supervision    50     18,000
                       may lead to stealing   security personnel                                                    meetings with                  project site              Consultant
                       of        contractor • Provide adequate training                                             community
                       equipment              of security personnel.                                                heads                                                    Imo State
                       mobilized to site    • Disclose site security                                                                                                         RAMP-SPIU;
                                              arrangements     to     the
                                              Police       and       host
                                              communities


                                                                                               40
S/N Activity           Potential Impacts   Mitigation/Enhancement      Mitigation        Cost of Mitigation Indicators/Paramet Method of   Sampling        Frequency Monitoring      Cost of
                                           Measures                    Responsibility                       ers                Measurement Location        of         Responsibility Monitoring
                                                                       (Implementatio                                                                      Monitoring (Supervision) USD$ NGN
                                                                       n)
                                                                                          USD$      NGN

A9    • Sensitization • Threat             to • Involve local community Contractor      350       126,000 • Implementation • Log book Community/           Monthly     Imo State  100      36,000
      • Mobilization     community culture and opinion leaders in            SPIU                           s      of      the • Assessment project site               RAMP-SPIU;
      • Site clearing    due    to    labour    planning  process                       To be    To be      requirements of by the SPIU                    All issues             Provid   Provided
      • Clearing Safety influx                • Develop an induction                    provided provided   the code of to determine                       regarding Supervision  ed in    in the
        measures       • Impact on site of program including a code                     by the   by the     conducts      and if           the             cultural    Consultant the      RAP/ARA
      • Material         cultural heritage of conduct for all workers.                  RAP/ARAP RAP/ARA    the       cultural objectives of               heritage               RAP/A    P
        sourcing         (Obana River)        • Provide cultural                                 P          sensitization        the                       should be              RAP
      • Staging area • Impact             on sensitization training to                                      programs             resettlement              settled
      • Workers camp intangible cultural improve awareness of and                                         • Regular              instrument                before the
                         heritage (fishing in sensitivity of workers to                                     meetings with have been                        start of
                         Obana River and local cultures, traditions                                         community            achieved.                 civil works
                         water-fetching on and lifestyles. (Implement                                       heads
                         small orie days the PCRMP annex XII)                                             • RAP/ARAP
                         (market day)         • Minimize the disruption as                                  Prepared
                                                a result of the relocation
                                                and removal of sacred sites
                                              • Where possible, design or
                                                re-design Project
                                                components to avoid or
                                                minimize impacts to known
                                                physical cultural heritage
                                                resources based on input
                                                from cultural heritage
                                                specialists.
                                              • Avoidance of shrines
                                                determined to be very
                                                important to the local
                                                community.
                                              • If shrines considered
                                                important to the local
                                                community cannot be
                                                avoided, consultation with
                                                the local community will
                                                occur to offer compensation
                                                for the loss of the cultural

                                                                                        41
S/N Activity   Potential Impacts   Mitigation/Enhancement              Mitigation       Cost of Mitigation Indicators/Paramet Method of   Sampling   Frequency Monitoring      Cost of
                                   Measures                            Responsibility                      ers                Measurement Location   of         Responsibility Monitoring
                                                                       (Implementatio                                                                Monitoring (Supervision) USD$ NGN
                                                                       n)
                                                                                         USD$     NGN

                                     resource or to inquire about
                                     the possibility of relocating
                                     the resource.
                                   • Sensitize all workers on the
                                     restriction of fetching water
                                     from Obana River on small
                                     Orie day
                                   • stakeholder engagement to
                                     identify the Boa’s habitat,
                                     migratory route and routine;
                                   • Gaps or buffer will be
                                     created to allow the Boa
                                     and other wildlife to cross
                                     the ROW
                                   • Site marking/protection
                                     with barriers to restrict the
                                     movement of the Boa into
                                     project area;
                                   • educational,       awareness-
                                     raising and information
                                     programmes, aimed at the
                                     general public, in particular
                                     construction workers from
                                     other communities
                                   • identify and define the
                                     various elements of this
                                     intangible cultural heritage
                                     (fetching water on small orie
                                     day and fishing) with the
                                     participation                of
                                     communities and relevant
                                     non-governmental
                                     organizations.

                                                                                        42
S/N Activity   Potential Impacts   Mitigation/Enhancement             Mitigation       Cost of Mitigation Indicators/Paramet Method of   Sampling   Frequency Monitoring      Cost of
                                   Measures                           Responsibility                      ers                Measurement Location   of         Responsibility Monitoring
                                                                      (Implementatio                                                                Monitoring (Supervision) USD$ NGN
                                                                      n)
                                                                                        USD$     NGN

                                   • consultation with chief
                                     priest and community elders
                                     on        the        required
                                     compensation if fish is
                                     mistakenly killed or water is
                                     fetched on small Orie day;
                                   • adopt a general policy of
                                     respect aimed at promoting
                                     the function of these
                                     intangible cultural heritages
                                     and at integrating the
                                     safeguarding      of     such
                                     heritage     into      project
                                     planning programmes;
                                   • Instructions in the chance
                                     find procedures on the line
                                     of action when the fish is
                                     mistakenly killed; and
                                   • designate or establish one or
                                     more competent bodies for
                                     the safeguarding of these
                                     intangible cultural heritages;
                                   • The community leaders
                                     gave assurance that all the
                                     necessary rituals will be
                                     carried out
                                   • This will be further
                                     examined      through      the
                                     ARAP study (See Annex
                                     XXI)

                                                                                       43
S/N Activity   Potential Impacts    Mitigation/Enhancement         Mitigation        Cost of Mitigation Indicators/Paramet Method of   Sampling       Frequency Monitoring      Cost of
                                    Measures                       Responsibility                       ers                Measurement Location       of         Responsibility Monitoring
                                                                   (Implementatio                                                                     Monitoring (Supervision) USD$ NGN
                                                                   n)
                                                                                     USD$      NGN

A10            Exposure of          • Implement site specific        Contractor     250      90,000    • Contractors      • Routine    Construction Weekly      ESO           120    43,200
               workers to             OHS Plan:                                                          Compliance to Inspection      Site/
               occupational         • Ensure that staging areas                                          Occupation       • HSE        Campsite/                SMEnv
               hazards                for contractor equipment                                           safety      and Reports       Staging
                                      are adequately delineated                                          Health                        areas/                   Supervision
                                      and cordoned off with                                              (OSH)/Health                  borrow pit               Consultant
                                      reflective tapes and                                               Safety      and               areas
                                      barriers                                                           Environment
                                    • Any uncovered work pits                                            (HSE) Plan
                                      should have appropriate                                          • Compliance to
                                      signage and protection                                             use of PPEs
                                      around them                                                      • HSE Statistics
                                    • Workers should get a daily                                         (FAC, LTI, etc.)
                                      induction/toolbox before                                         • No of workers
                                      going on the site and a                                            trained
                                      refresher of what happened
                                      on site a day before
                                    • Adequate safety signage on
                                      construction sites should be
                                      installed        to      alert
                                      community/drivers/pedestr
                                      ians      lighting    and/or
                                      reflective      tapes     and
                                      signages integrated in all
                                      worksites for safety at night
                                    • appropriate security
                                      measures in place to
                                      prevent harassment or
                                      kidnapping (see OHS plan
                                      annex XIV).
A11            Risk of diseases     • Develop a site specific Contractor            350      126,000   • Workers Using • Routine       Project site   Daily       ESO and SSO 150    54,000
               arising from             HSE plan                                                         PPE              Inspection                  during Pre-
               indiscriminate waste • Comply with the waste                                            • HSE Statistics • HSE                         Constructi SMEnv
               disposal                 management plan in                                               (FAC, LTI, etc.) Reports                     on
                                        Annex XIV
                                                                                    44
S/N Activity   Potential Impacts      Mitigation/Enhancement      Mitigation        Cost of Mitigation Indicators/Paramet Method of   Sampling   Frequency Monitoring      Cost of
                                      Measures                    Responsibility                       ers                Measurement Location   of         Responsibility Monitoring
                                                                  (Implementatio                                                                 Monitoring (Supervision) USD$ NGN
                                                                  n)
                                                                                    USD$      NGN

A12            Conflict arising       Employment of local labour Contractor        100      36,000    • No. of local • Log book      Construction Weekly      Imo State 100     36,000
               from the poor          should be maximized by                                            labor used                   Site         during Pre- RAMP-SPIU
               employment/engage      ensuring the submission of                                                                                  Constructi
               ment of local labour   statement of intent to employ                                                                               on
               for site clearing      local labour as a condition in
                                      the procurement document for
                                      the contractor.

A13            Impacts on water        • Ensure that construction Contractor       100      36,000    Water      quality • In-Situ   Community/ Weekly        Imo State 100     36,000
               supply to                 activities do not impact on                                  parameters           Measureme project site during Pre- RAMP-SPIU
               communities               communities’ water use                                                            nt                     Constructi
                                       • Arrange drainage around                                      Regular meetings • Sighting                 on
                                         the construction sites to                                    with community • Complaint
                                         prevent soil erosion and                                     heads                Register
                                         sedimentation into water
                                         collection points
                                       • Regularly check the River
                                         to ensure they are not
                                         blocked by construction
                                         spoil or waste and if they
                                         are affected, provide
                                         alternative           water
                                         collection points
                                       • Immediately rehabilitate
                                         water collection points if
                                         they are damaged by pre-
                                         construction              or
                                         construction activities
                                       • Provide          alternative
                                         domestic water source for
                                         the community if water
                                         supply to the community
                                         will      be     negatively
                                         impacted


                                                                                   45
S/N Activity   Potential Impacts   Mitigation/Enhancement      Mitigation        Cost of Mitigation Indicators/Paramet Method of   Sampling   Frequency Monitoring      Cost of
                                   Measures                    Responsibility                       ers                Measurement Location   of         Responsibility Monitoring
                                                               (Implementatio                                                                 Monitoring (Supervision) USD$ NGN
                                                               n)
                                                                                  USD$     NGN



A14            Impact on             • Ensure that construction Contractor      100      36,000      Regular meetings • Log book   Community/ Weekly        Imo State 50     18,000
               livelihood of fishing   activities do not impact on                                   with community                project site during Pre- RAMP-SPIU
               communities             fishermen use of the River                                    heads and heads of                         Constructi
                                       for their livelihood                                          fishermen                                  on
                                     • Informing the community
                                       and       especially     the
                                       fishermen        of      the
                                       construction schedule at
                                       least two weeks before the
                                       construction.
                                     • Train the fishermen on
                                       alternative         vocation
                                       during       preconstruction
                                       and construction
                                     • Continuous consultation
                                       with the local community
                                       to ensure that suitable
                                       solutions to problems are
                                       taken and communities’
                                       and fishermen concerns
                                       related to construction
                                       activities are addressed.

               TOTAL                                                            3,180    1,144,800                                                                    1,370 493,200




                                                                                46
     Table 6.2: Environmental and Social Mitigation and Monitoring Plan during the Construction Phase
S/N Activity              Potential Impacts        Mitigation/Enhance Responsibility Cost of Mitigation Indicators/Param Method of   Sampling         Frequency Responsibili Cost of Monitoring
                                                   ment Measures      (Implementati                     eters            Measurement Location         of         ty           (USD$/NGN)
                                                                      on)                                                                             Monitoring (Supervision
                                                                                     (USD$ NGN                                                                   )            (USD$) NGN
                                                                                     )

Environmental Mitigation and Monitoring Plan

B1      • Earthworks       Noise and vibration from See A1                See A1       320   115,200   See A1                See A1       See A1       See A1     See A1      160    57,600
          including        the use of motorized
          excavation and vehicles and equipment
          grading
B2      • Provision     of Channel/River      Bank • Heavy duty           Contractor   380   13,800    • Distance      of • Visual        Construction Every day, ESO          250   90,000
          lateritic   sub- Failure                    machinery and                                      heavy-duty         observation   Site         during the Engineer –
          base and base                               filling material                                   machines from                                 constructio SPIU
          course                                      should be about                                    the      channel                              n phase
          (150mm)                                     30m away from the                                  during      civil                                         State
        • Side Drains                                 channel;                                           works                                                     Ministry of
        • Culvert works                             • Vibration induced                                                                                            Works
        • Utilization of                              machines should be                               • Overhead
          borrow pits                                 avoided;                                           position      of
                                                    • Lower the overhand                                 excavator with
                                                      before using                                       boom of at least
                                                      excavator with a                                   25 meters.
                                                      boom of at least 25
                                                      meters.                                          • Vibration level
                                                                                                         of     machinery
                                                                                                         during      civil
                                                                                                         works.

B3                        Ambient air pollution     See A2                See A2       350   126,000   • Suspended         See A2         See A2       See A2     See A2      250    90,000
                          from release of dusts and                                                      Particulates
                          gaseous emissions                                                              (SPM),       SO2,
                          during construction                                                            NOx, CO, THC
                                                                                                       • Vehicle Exhaust
                                                                                                         Measurements
                                                                                                       • Records        of
                                                                                                         maintenance for
                                                                                                         all machineries
                                                                                                         and equipment

                                                                                             47
B4   Increased Siltation and • Desilting of stream Contractor      250/   90,000      Surface Water In-Situ          Discharge  During      ESO,           100   36,000
     runoff/flooding           channel                                                Quality    (pH, Measurements   point,     constructio Engineer,
                             • Enlighten          the                                 TDS, TSS, BOD,                 midstream n
                               populace on proper                                     COD, Turbidity)                and                    SMEnv
                               disposal of domestic                                                                  downstream
                               waste        Enhance
                               proper handling and
                               disposal of wastes
                               (especially
                               contaminated soil or
                               water,       concrete,
                               demolition
                               materials,       oils,
                               grease, lubricants,
                               metals, etc.)
                             • Construct temporary
                               drainage channels
                               with sedimentation
                               traps and/or screens
                             • Install sediment silt
                               fences or other
                               similar devices at
                               strategic locations to
                               prevent run-offs of
                               sediment/silt       to
                               surface water
B5   Topographic alterations • Construction           Contractor   500/   180,000   • Height of bank Routine                  • During
                                                                                                                     Construction             ESO          320   115,200
     and Slope instability       works should be                                      stabilization to Inspection    Site         constructio Engineer –
     arising from excavation     done according to                                    the local relief                            n           SPIU
     to construct drainages      local relief and
                                 hydrology;                                         • Depth and area                                         State
                             • Old          drainage                                  extent      of                                         Ministry of
                                 systems should be                                    excavation.                                            Works
                                 maintained      and
                                 new            ones                                • Number and area
                                 prioritized;                                         extent of cut and
                             • Ensure            that                                 fill
                                 engineering
                                 designs          are                               • Terraced    areas
                                 designed       with                                  (extent)


                                                                          48
                                                      respect to local
                                                      topography.
                                                   • Excavation        /
                                                      scooping should be
                                                      top down and no
                                                      down or base
                                                      cutting with huge
                                                      rock hanging
B6                        Loss of soil quality from See A3               See A3               350/   126,000   See A3          See A3          See A3       See A3     See A3       200   72,000
                          de-vegetation and
                          erosion

B7                        Generation of spoils and See A4                     See A4          320/   115,200   See A4           See A4          See A4       See A4    See A4       150   54,000
                          other construction
                          wastes

Social Mitigation and Monitoring Plan

B8     • Earthworks       Risk of diseases arising See A10                      See A10       350/   126,000    See A10            See A10     See A10      See A10   See A10      150    54,000
         including        from indiscriminate
         excavation and waste disposal
         grading
B9     • Provision     of GBV/SEA risks                • Commitment / policy Contractor,      Part of          • No of workers Routine         Priority Site During     Supervision 100   36,000
         lateritic   sub-                                to cooperate with law ESO, SSO,      construction       sensitized.      Inspection                 Constructi Consultant
         base and base • Intimate Partner                enforcement            GRC,          cost             • Code of conduct                             on
         course             Violence (IPV)               agencies               Procurement                      developed    for                                       Imo State
         (150mm)          • Public harassment            investigating          SPIU, GBV                        workers                                                RAMP-SPIU
       • Side Drains        including, verbal insults,   perpetrators        of Specialist                     • Code of conduct
       • Culvert works      physical abuse, rape,        gender-based                                            signed        by                                     ESO
       • Utilization of harmful widowhood                violence;                                               Contractor and
         borrow pits        practices . Child labour   • Ensure a copy of the                                    workers                                              Police
                                                         code of conduct is                                    • Level         of
                                                         presented to all                                        awareness     of
                                                         workers and signed                                      workers to local
                                                         by each worker [See                                     cultures
                                                         Annex VII].                                           • Awareness     of
                                                       • Ensure workers are                                      grievance
                                                         trained on the                                        • procedures.
                                                         content of the code                                   • No of local
                                                         of conduct in                                           workers


                                                                                                     49
  English and local              • Presence    of
  language                         security
• Provide cultural                 personnel
  sensitisation training
  to improve
  awareness of and
  sensitivity of
  workers to local
  cultures, traditions
  and lifestyles.
• Prohibit child and
  forced labour.
• Establish and
  implement the GBV-
  GRM .
• Engage competent
  security personnel
• Developing a clear
  RAMP           specific
  internal “Reporting
  and          Response
  Protocol" to guide
  relevant stakeholders
  in case of GBV/SEA
  incidents,
• Strengthening
  operational processes
  of RAMP states
  project   area     on
  GBV/SEA,
• Identifying
  development
  partners           and
  cultivating pragmatic
  partnership         on
  GBV/SEA
  prevention measures
  and referral services,
                            50
                                • Providing   financial
                                  support
                                  implementation of
                                  the       GBV/SEA
                                  actions    described
                                  herein,    including
                                  training          and
                                  awareness building
                                  for           various
                                  stakeholders,
                                • Establishing   inter-
                                 ministerial
                                 committee           to
                                 advance GBV/SEA
                                 actions     described
                                 above.
B10   Conflict arising from the See A11                 See A11      350   126,000    See A11                  See A11     See A11      See A11    Supervision 150      54,000
      poor                                                                                                                                         Consultant
      employment/engagement
      of local labour for                                                                                                                          See A11
      construction activities
B11   Traffic congestion and   Implement        site Contractor in   200   72,000    • Contractors        •   Routine      Priority Site During      ESO          100   36,000
      increased risk of road   specific   Transport conjunction                        Compliance             Inspection                 Constructio
      traffic accidents and    Management      Plan with FRSC                        • Workers Using                                     n           Federal Road
      injury                   (TMP) (Annex XI) and                                    Personal                                                      Safety
                               OHS Plan (Annex                                         Protective                                                    Commission
                               XIV)                                                    Equipment-
                                                                                       Health      Safety
                                                                                       and
                                                                                       Environment
                                                                                       (PPE-HSE)
                                                                                       Statistics/
                                                                                       Incident/acciden
                                                                                       t report
B12   Risks of diseases such as Develop a site specific Contractor   500   180,000   • Contractors        •   Routine     Construction During      Supervision 150      54,000
      HIV/AIDS, STDs            HSE plan                                               Compliance             Inspection  Site         Constructio Consultant
                                                                                     • Workers Using •        HSE Reports              n
                                                                                       PPE

                                                                           51
                                                                                  • HSE Statistics •      Record of                           Imo State
                                                                                    (First Aid Case       awareness                           RAMP-
                                                                                    (FAC),     Loss       and theme                           SPIU;
                                                                                    Time      Injury      carried out
                                                                                    (LTI),      etc)                                          Imo State
                                                                                    (Annex XIV)                                               Ministry of
                                                                                                                                              Environment
                                                                                                                                              and Mineral
                                                                                                                                              Resources

B13   Damage to shrines and     • Adopt chance find Contractor    300   108,000   • Record keeping • Log book        Construction During      Supervision 200    72,000
      cultural sites              procedures as stated                            • Expert           • Number of Site             Constructio Consultant,
                                  in Annex XII                                      verification       chances finds              n           ESO, SSO,
                                                                                    procedures,                                               Imo State
                                                                                  • Chain of custody                                          Ministry of
                                                                                    instructions                                              Arts and
                                                                                                                                              Culture

B14   Community Health &        Implement a site     Contractor   300   108,000   • Contractors     •      Routine    Construction During      Supervision 200   72,000
      Safety risks              specific HSE plan                                   Compliance             Inspection Site         Constructio Consultant
                                                                                  • Workers Using •         HSE                    n
                                                                                    PPE                     Reports                            Imo State
                                                                                  • HSE Statistics                                             RAMP-
                                                                                    (FAC, LTI, etc)                                            SPIU; Imo
                                                                                                                                               State
                                                                                                                                               Ministry of
                                                                                                                                               Environment
                                                                                                                                               and Mineral
                                                                                                                                               Resources

B15   Safety risks associated   • Develop        and Contractor   500   180,000   • Contractors       •    Routine    Borrow pit   During      ESO SMEnv 350     126,000
      with falls in poorly        Implement        a                                Compliance to          Inspection Site         Constructio
      managed borrow pits         borrow          pit                               borrow        pit •    HSE                     n
                                  management and                                    management             Reports
                                  reclamation plan.                                 plan
                                  See annex XV                                    • Workers Using
                                • Adequate      PPEs                                PPE
                                  must be provided                                • Report         of
                                  and    used     by                                unreclaim
                                  workers                                           borrow pits from
                                • All borrow pits                                   completion audit
                                  must be reclaimed                                 report
                                                                        52
                              • Any        uncovered
                                  work pits should
                                  have appropriate
                                  signage         and
                                  protection around
                                  them
B16   The potential risk of   • Adequate PPEs (life Contractor   300   108,000   • Workers Using •   Routine    River         During      Supervision 150   /54,000
      drowning                  jackets, buoyancy                                  PPE               Inspection Crossing site Constructio Consultant
                                aid and surf helmets)                                            •   HSE                      n
                                must be provided                                                     Reports                              ESO SMEnv
                                and used by workers
                              • All river should
                                have      appropriate
                                signage           and
                                protection around
                                them
                              • Design and erect
                                fences or barrier
                                structures     around
                                the walking paths
                              • Install warning signs
                                and install lighting
                                system around the
                                project sites.
                              • Enlighten the public
                                about this drowning
                                risk in the project
                                area
                              • Ensure that workers
                                who can swim are
                                engaged.

                              • Local members of
                                the community who
                                are able to swim can
                                also be engaged as
                                lifeguards     during
                                civil works.
                              • Develop      a    site
                                specific        HSE
                                drowning plan

                                                                       53
B17   Damage to and            • Employ utility        Contractor 200   72,000   Notify      Utility • Notification Construction During     ESO         100   36,000
      disruption of services of survey maps to                                   Service Providers     Register     area         excavation
      existing public utility    identify existing                                                   • Visual                               Engineer,
      cables and pipes           underground                                                           Observation                          SPIU
                                 facilities before
                                 excavation works to                                                                                        PC, SPIU
                                 prevent / minimize
                                 damages and
                                 disruption of
                                 services
                               • Shut down service if
                                 necessary, should be
                                 as temporal as
                                 possible
                               • Any disruption will
                                 be discussed with
                                 utility operators and
                                 the community
                                 beforehand.
                               .
B18   Uncontrolled sale of     • The HSE officer will Contractor  200   72,000   •    HSE        •     Routine    Construction During      Imo State   100    36,000
      food and other items to    ensure that only                                     Statistics       Inspection Site         Constructio RAMP-
      workers on the site        approved vendors                                     (FAC, LTI, •     HSE                     n           SPIU; Imo
                                 are allowed to sell                                  etc)             Reports                             State
                                 food.                                                                                                     Ministry of
                               • Access to the site                                                                                        Environment
                                 should be restricted                                                                                      and Mineral
                                 to avoid sale of                                                                                          Resources
                                 contraband on site                                                                                        Ministry of
                               • Implement a site                                                                                          Health
                                 specific HSE plan
                                 (section 12-Welfare)
B19   Interference from local • Engage members of SSO and ESO 200       72,000   • Regular       •     Log book    Community/ Monthly       Imo State   100   36,000
      community causing          communities in                                    meetings with                   project site             RAMP-
      disruptions to work        stakeholder           Contractor                  community                                                SPIU;
                                 consultation                                      heads
                                 throughout the
                                 Lifecyle of the
                                 project
                               • Involve local
                                 community and

                                                                        54
                                             opinion leaders in
                                             planning process
                                           • To minimize the
                                             number of foreign
                                             workers being
                                             brought to the site,
                                             the contractor will
                                             be required to hire
                                             skilled/unskilled
                                             labour from local
                                             people if they wish
                                             to be hired.
B20                Impacts on water supply • A12                  A12         100   36,000      •   A12         •   A12       A12         A12         A12         100     36,000
                   /water quality

B21                Impact on livelihood of • A13                A13           100   36,000      •   A13         •   A13       A13         A13         A13         50      18,000
                   fishing communities and
                   fish habitat

B22                Risk of flooding        • Desilting of stream Contractor   100   36,000      • Record keeping • Log book   Construction During      Supervision 50     18,000
                                             channel                                                                          Site         Constructio Consultant,
                                           • Enlighten the                                                                                 n           ESO, SSO,
                                             populace on proper                                                                                        Imo State
                                             disposal of domestic                                                                                      Ministry of
                                             waste                                                                                                     Arts and
                                           • Enhance proper                                                                                            Culture
                                             handling and
                                             disposal of wastes
                                             (especially
                                             contaminated soil or
                                             water, concrete,
                                             demolition
                                             materials, oils,
                                             grease, lubricants,
                                             metals, etc.)
      Total                                                                   6,170 2,221,200                                                                     3,480   1,252,800




  Table 6.3: Environmental and Social Mitigation and Monitoring Plan during the Post – Construction/Operation Phase

                                                                                    55
S/N      Activity                      Potential Impacts              Mitigation/Enhance Responsibility   Cost of Mitigation Indicators/ Method of        Sampling Frequency Responsibili Cost       of
                                                                      ment Measures      (Implementation)                    Parameters Measurement       Location of         ty          Monitoring
                                                                                                                                                                   Monitoring (Supervisio
                                                                                                               (USD$)   NGN                                                   n)          (USD NGN
                                                                                                                                                                                          $)

Environmental Impacts

C1         • Road usage               Increased air pollution level / See A2              See A2               300      108,000 See A2       See A2       See A2      See A2   See A2        150    54,000
           • Maintenance         and dust due to increased
             Repairs                  vehicular traffic after the
           • scheduled           and renovation of the RC
             unscheduled integrity
             checks for bridges and
             culverts
C2         • maintenance         and Soil contamination from See A3                       See A3               350      126,000 See A3       See A3       See A3      See A3   See A3        100/   36,000
             replacement           of accidental leakage/spillage of
             wearing/faulty/damaged fuel, oil and lubricants during
             components               River crossing maintenance
           • repairs of cracks and
             potholes
           • Cleaning of drains
             where     and     when
C3           necessary                Contamination of surface • Implement            the Contractor           400      144,000 Surface     • In-Situ    / Discharge Monthly   Imo State     200    72,000
           • Cleaning and vegetation  water  as  a  result of  waste    Waste                                                   Water         Laboratory point,                RAMP-
             control    along     the dumping in and around the Management Plan                                                 Quality (pH, Measurements midstream            SPIU;
             shoulders                stream/river during River (WMP)              annex                                        TDS, TSS,                  &
                                      crossing maintenance              XVII                                                    BOD, COD,                  downstream
           • Borrow pit reclamation
                                                                      • Promote     waste                                       Turbidity,
                                                                        avoidance;                                              THC, Heavy
                                                                        reduction; reuse                                        Metals)
                                                                        and recycling as
                                                                        applicable
Social Impacts

C4          • Road usage                Exacerbation of the risk of   • Conduct             Contractor         350      126,000 • Number Routine          Project area Daily   Supervision 200      72,000
            • Maintenance          and transmission of HIV/AIDS         sensitization and                                         of health inspection                         Consultant,
              Repairs                   and other STIs due to           awareness                                                 campaigns
            • scheduled            and potential labour influx          campaigns                                                 and                                          Ministry of
              unscheduled     integrity                               • Supply       health HSE officer                           toolbox                                      Health, Imo
                                                                        check equipment                                           meetings                                     State

                                                                                                          56
S/N   Activity                      Potential Impacts            Mitigation/Enhance Responsibility   Cost of Mitigation Indicators/ Method of         Sampling Frequency Responsibili Cost       of
                                                                 ment Measures      (Implementation)                    Parameters Measurement        Location of         ty          Monitoring
                                                                                                                                                               Monitoring (Supervisio
                                                                                                         (USD$)   NGN                                                     n)          (USD NGN
                                                                                                                                                                                      $)

            checks for bridges and                              • Ensure                                                   • Number                                         RAMP-
            culverts                                              compliance        to                                       of health                                      SPIU;
        •   maintenance         and                               workers’ Code of                                           checks
            replacement           of                              conduct as stated
            wearing/faulty/damaged
C5          components               Risks of occupational and • Implement the         Contractor        300/     108,000 HSE        Routine          Road and    Monthly   Supervision 150     54,000
        •   repairs of cracks and social accidents and injuries   site specific HSE                                       Statistics Inspection       drainage              Consultant,
            potholes                 in using the new river       plan                                                    (FAC, LTI,
        •   Cleaning of drains crossings                        • Build concrete or                                       etc.)                                             Ministry of
            where     and     when                                steel barriers at                                                                                         Work, Imo
            necessary                                             sides of bridge by                                                                                        State
        •   Cleaning and vegetation                               the river and                                                                                             RAMP-
            control    along     the                              immediate                                                                                                 SPIU;
            shoulders                                             approach to
        •   Borrow pit reclamation                                bridge


C6                                  Safety risks from abandoned See B14               See B14            200/     72,000   See B14       See B14      See B14     See B14   See B14       100   36,000
                                    borrow pits after
                                    construction

C7                                  Traffic congestion and         See B10            See B10            250/     90,000   See B10       See B10      See B10     See B10   See B10       100   36,000
                                    increased risk of road traffic
                                    accidents and injuries due to
                                    increase in traffic on the new
                                    RCs

C8                                  River crossing damage from Develop plan for    Contractor            350      126,000 Log book       Visual       Project area Daily    Imo State     100   36,000
                                    use                        regular maintenance                                                       inspection                         RAMP-
                                                               of river crossings                                                                                           SPIU;

C9                                  • Contamination of surface • Implement the    Contractor             250      90,000   Contractors Visual         Project area Weekly   Imo State     150   54,000
                                      water as a result of waste Waste Management                                          Compliance Observation                           RAMP-
                                      dumping in and around the Plan (WMP)                                                 to WMP                                           SPIU;
                                      stream/river

                                                                                                    57
S/N   Activity   Potential Impacts          Mitigation/Enhance Responsibility   Cost of Mitigation Indicators/ Method of       Sampling Frequency Responsibili Cost       of
                                            ment Measures      (Implementation)                    Parameters Measurement      Location of         ty          Monitoring
                                                                                                                                        Monitoring (Supervisio
                                                                              (USD$)   NGN                                                         n)          (USD NGN
                                                                                                                                                               $)

                 • Waste dumping impact on • Promote waste                                       Waste        Waste Tracking
                   the life span of the      avoidance,                                          Handling     Report
                   proposed RCs by blocking reduction; reuse                                     and Disposal
                   access to waterflow.
                                             and recycling as
                                             applicable
                                           • Ensure proper
                                             handling, and
                                             disposal of the
                                             various types of
                                             solid municipal and
                                             household wastes
                                           • Fence off
                                             river/stream banks
                                             around bridge

                 TOTAL                                                        2,750    990,000                                                                1,250 450,000




                                                                         58
6.2     GBV Risk Management Mechanisms

A GBV workshop to be conducted to sensitize the SPIU staff on the key principle and specific
requirements to address GBV/SEA have been included in the bidding documents (‘pre -qualification’
and ‘employers’ requirements’). As such specific measures to reduce and mitigate the risk of GBV/SEA
in the project. Such measures will include:

   •   GBV/SEA assessment of project;
   •   mandatory contractors’ code of conduct on sexual harassment;
   •   appointment of NGO to monitor GBV/SEA in RAMP-2;
   •   community and workers’ sensitization on GBV/SEA;
   •   provision of referral units for survivors of GBV/SEA;
   •   provisions in contracts for dedicated payments to contractors for GBV/SEA prevention activities
       against evidence of completion;
   •   contractor and SPIU requirement to ensure a minimum target of female employment with
       incremental rewards of the obtainment of this target.

The following actions are recommended for immediate implementation:
  • Hiring a dedicated GBV/SEA specialist or retraining Social Livelihood Officers (SLOs) for the
     project,
  • Including in the focal NGO’s ToR services for managing social risks associated with GBV/SEA
     in the project,
  • Building and improving FPMU/SPIUs, local communities and other relevant stakeholders’
     capacities to address risks of GBV/SEA by developing and providing guidance, training,
     awareness, and dissemination of relevant GBV/SEA materials to communities,
     1. Developing a clear RAMP specific internal “Reporting and Response Protocol" to guide
     relevant stakeholders in case of GBV/SEA incidents,
     2. Strengthening operational processes of RAMP states project area on GBV/SEA,
     3. Identifying development partners and cultivating pragmatic partnership on GBV/SEA
     prevention measures and referral services,
     4. Developing Codes of Conduct for civil works contractors with prohibitions against GBV/SEA,
  • Strengthening consultations and operationalizing GBV/SEA specific grievance redress
     mechanisms,
     1. Providing financial support implementation of the GBV/SEA actions described herein,
          including training and awareness building for various stakeholders,
     2. Establishing inter-ministerial committee to advance GBV/SEA actions described above.

Overall, GBV risks in the project target areas might include Intimate Partner Violence (IPV), public
harassment including harassment, verbal insults, physical abuse, rape, harmful widowhood practices
and women and child trafficking. Targeted support to women under the program could likely exacerbate
these risks. Development and implementation of specific GBV risk prevention and mitigation strategies,
tailored to local contexts, will be critical. Guidelines for situation analysis of GBV and safe reporting
guidelines in line with international best practices will be implemented. Further, all risks related to
labour influx will have to be mitigated by participation of project beneficiaries/communities, and
involvement of project contractors and contractors’ workers and consultant employees, in identifying
mitigation and implementing measures, including developing mitigation instruments such as “Lab or
Influx Management Plan�? (Annex XXII) and “Workers Camp Site Management Plan�? (Annex XVI).
                                                   59
       6.3     Institutional Arrangements
       The successful implementation of the mitigation and monitoring program will depend on the
       commitment and capacity of the Project Implementation Unit (PIU), environmental and social
       safeguard consultants and other third parties (institutions) to implement the program effectively. The
       roles and responsibilities of those that will be involved in the implementation and monitoring of this
       ESMP are discussed in table 6.4.

       Table 6.4: Institutional Arrangement for ESMP Implementation
S/N Category                    Roles & Responsibilities
1   Imo State Ministry of Local • Environmental monitoring and compliance overseer at the State level
    Government and Rural • Review of draft ESMP report (in liaison with Federal Ministry of Environment)
    Development                 • Site assessment and monitoring of ESMP implementation.
2   Federal    Ministry      of • Lead role in the provision of advice on screening, scoping, review of draft ESMP report (in liaison with State
    Environment/           EIA Ministry of Environment), receiving comments from stakeholders, public hearing of the project proposals
    Department and NESREA and social liability investigations, monitoring and evaluation of mitigation measures
3.  World Bank                  • Responsible for the final review, clearance and approval of the safeguard instruments – ESIA/ESMP/RAP
3   FPMU                        • Maintain an oversight role to ensure compliance with the safeguards policies
                                • Maintain an oversight role on the supervision of the ESMP/ARAP implementation, and may conduct spot
                                  checks or audits (if necessary)
                                • Provide overall guidance and recommend additional measures for strengthening the management framework
                                  and implementation performance.
                                • Conduct regular supervision missions throughout the project implementation, and monitor the progress of the
                                  construction project.
4   FPMU, Environmental• Review all ESIAs/ESMPs/ARAPs/RAPs documents prepared by environmental and social consultants and
    & Social Safeguard ensure adequacy under the World Bank Safeguard policies.
    Units                      • Ensure that the project design and specifications adequately reflect the recommendations of the ESIAs/
                                  ESMPs;
                               • Co-ordinate application, follow up processing and obtain requisite clearances required for the project, if
                                  required;
                               • Prepare compliance reports with statutory requirements;
                               • Develop, organize and deliver training program for the PIU staff, the contractors and others involved in the
                                  project implementation, in collaboration with the PIU;
                               • Review and approve the Contractor’s Implementation Plan for the environmental measures, as per the
                                  ESIAs/ESMPs and any other supplementary environmental and social studies that may need to be carried out
                                  by the PIU;
                               • Liaise with the Contractors and the SPIU / Ministry, Department and Agencies (MDAs) on implementation
                                  of the ESIAs/ESMPs;
                               • Liaise with various Central and State Government agencies on environmental, resettlement and other
                                  regulatory matters;
                               • Review the performance of the project through an assessment of the periodic environmental and social
                                  monitoring reports; provide a summary of the same to the Project Manager, and initiate necessary follow-up
                                  actions;
                               • Provide support and assistance to the State Government Agencies to supervise the implementation.
5   Safeguard Unit, RAMP 2 Environmental Safeguards
    (Environmental & Social) • Collate environmental baseline data on relevant environmental characteristics of the selected project sites;
                                • Ensure that project activities are implemented in accordance to best practices and guidelines set out in the
                                  ESMP;
                                • Identify and liaise with all stakeholders involved in environment related issues in the project; and be
                                  responsible for the overall monitoring of mitigation measures and the impacts of the project during
                                  implementation.
                                Social Safeguards
                                • Develop, coordinate and ensures the implementation of the social aspects of the ESMP
                                • Identify and liaise with all stakeholders involved in social related issues in the project;
                                • Conduct impact evaluation and beneficiary’s assessment; and
                                • Establish partnerships and liaise with organizations, Community Based Organizations (CBOs) and Civil
                                  Society Organizations (CSOs)
6   SPIU                        • Liaise closely with Imo State Ministry of Local Government and Rural Development in preparing a
                                  coordinated response on the environmental and social aspects of project development respectively.
                                • Safeguards due diligence.
                                • The PIU would form and supervise the GRC (Grievance Redress Committee) which would be responsible
                                  for addressing and management of grievances
                                                                     60
7    Contractor                 • Compliance to BOQ specification in procurement of material and construction
                                • Implement ESMP during project implementation
                                • Ensure all contractors and workers sign the Code of Conduct (CoC) and are routinely trained on the contents
                                  of the CoC
                                • Develop and implement contractor’s ESMP (C-ESMP)
                                • Ensure that there are sufficient resources (time, money and people) to manage the environmental issues of
                                  the works.
                                • Be responsible for ensuring that all site staff, including sub-contractors and sub-contracted activities will
                                  comply with the projects ESMP.
                                • Maintain records of environmental incidents as well as corrective and preventive actions taken.
                                • Ensure that any changes during the construction process that may have a significant environmental and
                                  social impact are communicated to the Supervising Engineer/ SPIU in time and manage them accordingly.
                                • Ensure that the Environmental Supervising Engineer is sufficiently informed on contractors monitoring
                                  results.
                                • Organizing weekly toolbox/work meetings
                                • Ensure that all construction personnel and subcontractors are trained on the content of the CESMP and are
                                   made aware of the required measures for environmental and social compliance and performance
                                • Prepare and implement Campsite, Staging Area management Plan for the pre-construction phase,
                                   construction and decommissioning phase
                                • Prepare OHS manual and abide by labor laws as set out in the agreement
                                • Provide adequate basic amenities and PPEs to workers, and ensure that the PPEs are worn by workers
                                   during work.
                                • Prepare and maintain records and all required reporting data as stipulated by the ESMP, for submission to
                                   the Supervising Consultant
8    Supervising Engineer       • Preparation of the engineering designs for the project.
                                • Provides an independent oversight ensuring contractor adhere strictly to the engineering specifications
                                • Prepare and implement Environmental Monitoring Plan during construction
                                • Update the ESMP to reflect changes to the project, area of influence or activities, with Borrower to re-
                                   disclose
                                • Inspect and approve contractor’s work.
                                • Supervise the contractor’s implementation of the works in accordance with the contract requirements and
                                   the ESMP
                                • Report any incidents or non-compliance with the C-ESMP to the ESSU-PIU
                                • Ensure adequate training and education of all staff involved in environmental and social safeguard
                                   supervision
                                • Prepare monthly safeguards report including recommendations to the RAMP regarding ESMP performance
                                   as part of an overall commitment to continuous improvement
9    Supervision Consultant     •     Prepare and implement Environmental and Social Monitoring Plan during construction
     (Environmental and Social •      Supervise contractor performance of implementation of the Construction Campsite/Staging area Camp
     Officers)                        Management Plan and C-ESMP
                                •     Report any incidents or non-compliance with the C-ESMP to the Environmental and Social Safeguard
                                      Unit of the SPIU
                                •     Ensure adequate training and education of all staff involved in environmental supervision
                                •     Prepare monthly safeguards report including recommendations to the RAMP regarding ESMP
                                      performance as part of an overall commitment to continuous improvement
10   State Government MDAs • Other MDAs come in as and when relevant areas or resources under their jurisdiction or management are
                                  likely to be affected by or implicated projects.
                                • They participate in the EA processes and in project decision-making that helps prevent or minimize impacts
                                  and to mitigate them. These institutions may also be required to issue a consent or approval for an aspect of
                                  a project; allow an area to be included in a project; or allow impact to a certain extent or impose restrictions
                                  or conditions, monitoring responsibility or supervisory oversight.
11   The        Imo       State • Inspection of project premises in order to ensure strict compliance with sanitation and waste management
     Environmental Protection standards in Imo State.
     Agency;                    • Collaboration with other MDAs at the State and Federal level, NGOs and Donor Agencies in environmental
     The Imo State Bureau for protection and management especially in areas of waste recycling etc.
     Sanitation & Transport;
12   LGAs                       • Provision of oversight function across project within its jurisdiction for ESMP compliance.
                                • Monitoring of activities related to public health, sanitation, waste management amongst others.
13   Affected Community         • Promote environmental awareness.
                                • Review environmental and social performance report made available by PIU.
                                • Provide comments, advice and/or complaints on issues of nonconformity.
                                • Attend public meetings organized by the PIU to disseminate information and receive feedback.


                                                                     61
14   Grievance         Redress • Provide support to project affected persons (PAPs) on problems arising from loss of private properties,
     Committees (GRCs)           business area or any other impact caused by the project
                               • Record the grievance of the PAPs, categorize and prioritize the grievances that need to be resolved by the
                                 committee;
                               • Report to the aggrieved parties about the developments regarding their grievances and the decision of the
                                 project authorities and
                               • Ensure that grievances are settled locally and in time as much as possible.
                               • Settling the complaints and grievances (if any) and suggest solutions for the outstanding issues to SPIU in
                                 improving project implementation.
15   Community Development • Ensure community participation by mobilizing, sensitizing community members;
     Association (CDA)         • Support with provision of necessary infrastructures and engage/ encourage carrying out comprehensive and
                                practical awareness campaign for the proposed projects, amongst the various relevant grass roots interest
                                groups.
16   NGOs/CSOs                 • Assisting in their respective ways to ensure effective response actions, conducting scientific researches
                                 alongside government groups to evolve and devise sustainable environmental strategies and techniques.
17   CBOs                      • Mobilizing rural communities with a view to maximizing the benefits of the project
                               • Facilitating the selection of the river crossing maintenance group
                               • Monitoring of the progress of the river crossing implementation work
                               • Sensitize community members for community actions
18   World Bank                • Overall supervision and provision of technical support and guidance.
                               • Recommend additional measures for strengthening the management framework and implementation
                                 performance;
                               • Supervising the application and recommendations of sub- project ESMPs.
19   Others/General Public     • Identify issues that could derail the project and support project impacts and mitigation measures, Awareness
                                 campaigns.

        6.4      Capacity Assessment and Training Programme
        The SPIU has not previously been involved in implementing World Bank assisted projects. As such,
        their capacity in implementing projects in line with the Bank’s policies was assessed to be limited. The
        capacity building programme in table 6.5 will therefore be implemented to strengthen institutional
        capacity in ensuring environmental and social safeguard compliance in the project implementation.

        Table 6.5: Institutional Capacity Strengthening Plan
Schedule     Capacity Need                   Target        Duration Facilitator  Project phase                       Cost in $ Cost in (N)
                                             Participants
Day 1        • World Bank safeguards PC, ESSU,             7 hours Environmental Pre-construction                    1,111.11 400,000.00
               policies and Nigerian Extant M&E, Project            Consultant
               laws     on    environmental Engineer,
               protection                    Procurement
             • ESMP         implementation, Officer,
               project    monitoring     and Relevant
               evaluation,    environmental MDAs
               management for construction
               contracts
Day 2        • Hazards in Construction       Contractors,  7 hours Engineering Pre-construction                      1,111.11 400,000.00
             • Incidents: Causation,         PAP’s PIU              Consultant
               Investigation & Reporting members,
             • Excavation Safety             relevant MDAs
             • River Safety
             • Construction Site Inspection
             • Personal Protective
               Equipment
             • The use of PPEs,
               management concerns,
               occupational safety and
               health


                                                                   62
Day 3         • Training on Code of       Contractors,   7 hours          Social        Pre-construction       833.33    300,000.00
                Conduct                   Contractor’s                    consultant
              • Community and stakeholder workers, PAP’s
                engagement roles in RAMP PIU members,
                project                   relevant MDAs
              • GBV/SEA and VAC
                awareness and prevention
              • GRM
              • Basic health awareness on
                communicable diseases and
                prevention
Total Capacity Building Budget                                                                                 3,055.55 1,100,000.00


        6.5      Monitoring and Reporting

        6.5.1 Monitoring Activities
        The monitoring plan (Internal and External Monitoring) for the ESMP is presented in Table 6.7.
        Monitoring results shall be documented with preventive/corrective actions to be implemented.

        Table 6.7: Internal and External Monitoring
         Monitoring     Action                              Responsibility             When                      Deliverables
         Internal       Regular site visit to ensure that   E&S          Safeguard     During                    Monitoring
         Monitoring     the mitigation measures and         Officers from SPIU.        Preconstruction,          Reports      and
                        actions specified in the                                       Construction     and      documentation
                        monitoring plan and as bound        FPMU Safeguards Unit       Operation Phases
                        by the contract is satisfactorily
                        implemented.
                        Site visit for monitoring and       Supervision                During   Construction     Observations and
                        inspection to ensure contractor     Consultants                Phase                     Monitoring
                        adhere      strictly    to    the                                                        Reports to be
                        engineering       designs    and                                                         compiled       and
                        specifications for the project                                                           presented to the
                                                                                                                 SPIU.
         External       Regular site visit to ensure        FMEnv, Imo State           During                    Inspect
         Monitoring     project is implemented in an        Ministry    of  Local      Preconstruction,          monitoring
                        environmentally & socially          Government and Rural       Construction     and      reports      from
                        sustainable manner using the        Development,               Operation Phases          Safeguard units
                        monitoring indicators specified     Representatives    of                                and       provide
                        in the monitoring plan and          affected communities,                                feedback        on
                        other national and international    and other relevant                                   observations.
                        environmental      &      social    MDAs.                                                Enforce
                        requirements                                                                             corrective
                                                                                                                 actions    where
                                                                                                                 necessary.

        6.5.2 Reporting Procedures
        The SPIU shall implement a system of continuous reporting between all parties involved in the ESMP
        implementation to ensure receipt of timely feedback and to take rapid corrective actions if there are
        issues of non-conformance.

        6.5.3 Record Keeping and Control
        The contractor is required to keep records providing evidence of ongoing mitigation activities. Such
        records may include site monitoring plan, HSE Policy, Site Specific HSE Plan, Waste Management
        Plan, Traffic Control Plan, Emergency response and preparedness procedures, site instructions, training

                                                               63
      records, complaints records, incident report, Inspection, maintenance and equipment calibration
      records. These documents should be made available to the Safeguard Unit upon request.

      The Safeguard Unit is also required to keep records to provide evidence of monitoring activities and
      effectiveness of the monitoring plan. The site monitoring Plan identified problems/corrective actions
      and monitoring Reports are to be kept by the Safeguard unit and be made available to relevant regulators
      upon request. In addition, all significant communications with FMEnv, Nigerian Society of Mining
      Engineers (NSME) and other relevant authorities should be documented and kept. These documents are
      required to track performance in order to achieve and demonstrate compliance with the monitoring plan
      and applicable regulatory requirements.

      6.6    Implementation Schedule
      The project implementation phase is estimated to be completed in 7 months. The implementation
      schedule is presented in Table 6.8 below.

      Table 6.8: ESMP Implementation Schedule
S/N     Activity Description           Responsible              Pre-construction   Construction               Operation
                                                                (Week)
                                                                                   (Month)

                                                                1   2    3     4   1    2    3    4   5   6

1       Clearance and Formal           Imo SPIU
        Disclosure of ESMP

2       Inclusion of Environmental &   Imo SPIU
        Social Requirements in Bid
        Docs

3       Allocating Budget for ESMP     Imo SPIU

4       Appointing Support Staff for   Imo SPIU
        ESMP

5       Review & Approval of           Imo SPIU
        Contractor’s ESMP, Waste &
        Safety Plan

6       Finalization of Engineering    Imo SPIU/Engineering
        Designs                        Design Consultant

7       Environmental and Social       Environmental and
        Training                       Social Consultant

8       Mobilization to site           Contractor

9       Construction Phase             Contractor

10      Implementation of Mitigation   Contractor

11      Supervising ESMP               Imo SPIU
        Implementation

12      Monitoring & Reporting on      Imo SPIU/Relevant
        ESMP Implementation            MDAs

13      Environmental and Social       Imo SPIU/Imo State
        Auditing                       Ministry of Local
                                       Government and Rural
                                       Development


                                                           64
6.7     Contractual Measures
Most of the mitigation measures are the obligation of the Contractor during all phases of the
project. Consequently, the potential contractor will have to prepare their proposals taking into
account the measures in Table 6.9 as well as the detailed general environmental management
conditions during civil works attached as Annex X.

Table 6.9: Contractual Measures
 Action                                                            Remarks
 The measures as described in this ESMP shall be included          The non-inclusion of these measures in the proposal will
 in the tender documents with appropriate flexibility to           lead to a disqualification of the proponent;
 adjust these measures to site circumstances, and that the         The contract with the successful bidder should contain these
 potential contractor will have to prepare their proposals         environmental and social management measures as firm
 taking into account these measures.                               conditions to be complied with.
 Specifically, the measures should be translated into a suite      This approach will ensure that the environmental and social
 of environmental specification that are written in the same       controls integrate seamlessly into the tender document and
 language style and format as the rest of the contract             are presented in a familiar form to the Contractor
 document
 Cost of mitigation measures be added to the cost of the           The contactor must take into account and put the cost for the
 contractual document                                              environmental and social requirements specified in the
                                                                   ESMP.

6.8     ESMP Disclosure
This ESMP has been prepared in consultation with the FPMU, Imo SPIU, relevant stakeholders
including communities along the project corridors. The Imo SPIU will disclose the ESMP, in line with
the guidelines of the Federal Ministry of Environment and in the external website of the World Bank.

Table 6.10: Disclosure Procedure
 S/N   Action                                    Remarks
 1     Disclosure on 2 national newspapers       The FPMU/SPIU will disclose the ESMP as required by the Nigeria EIA public notice
                                                 and review procedures. This entails advert in 2 newspapers; one national and one local
                                                 (state) newspaper
 2     Disclosure at the Imo State Ministry of   The SPIU will disclose the ESMP as required by the Nigeria EIA public notice and
       Local    Government       and    Rural    review procedures
       Development
 3     Disclosure at the RAMP-2 office           The SPIU will display the ESMP as required by the Nigeria EIA public notice and
                                                 review procedures
 4     Disclosure at respective LGA office &     The purpose will be to inform stakeholders about the project activities; environmental
       the host communities                      and social impacts anticipated and proposed environmental and social mitigation
                                                 measures.
 5     Disclosure at the World Bank Info Shop    The ESMP will be disclosed according to the World Bank Disclosure Policy- OP/BP
                                                 17.50


6.9    Cost of Implementing the ESMP
The cost of implementing this ESMP is a total of all the individual costs as provided in table 6.11.

Table 6.11    Cost of Implementing the ESMP
Heading                                      Indicative Costing in Naira (N)                     Cost Estimate in USD
Cost of Mitigation                           4,356,000.00                                        12,100.00
Capacity Building and Training               1,100,000.00                                        3,055.56
Monitoring Programme                         2,196,000.00                                        6,100.00
Grievance Redress Mechanism                  750,000.00                                          2,083.33
Sub-total                                    8,402,000.00                                        23,338.89
Contingency                                  840,200.00                                          2,338.89
Total                                        9,242,200.00                                        25,672.78
(1 USD = 360.00)
                                                          65
                                           CHAPTER SEVEN

                             GRIEVANCE REDRESS MECHANISM (GRM)

7.1      Introduction
A Grievance Redress Committee will be set up by the Imo State RAMP SPIU to address complaints arising
from the project implementation. This committee will comprise relevant officers of the Imo SPIU,
representative of the Ministry of Local Government and Rural Development, representatives of the 23
priority sites who are to be nominated by the traditional heads and Community Development Association.
The committee shall report to the Chairman, the RAMP Technical Committee who is also the Permanent
Secretary, Ministry of Local Government and Rural Development in Imo state. The Grievance Redress
Committee (GRC) shall work in synergy with the Site Committees and the Contractors’ Health and Safety
Officer.

The functions of the GRC are to:

    •   provide support to Project Affected Persons (PAPs) on problems arising from the pollution of
        environmental media – water, land and air, arising from the project implementation
    • record the grievance of the PAPs, categorize and prioritize the grievances that need to be resolved
        by the committee; and
    • report to the aggrieved parties about the developments regarding their grievances and the decision
        of the project authorities.
The main objective of this procedure will be to provide a mechanism to mediate conflict and cut down on
lengthy litigation, which often delays such developmental projects. It will also provide people who might
have objections or concerns about the impacts of the project, a public forum to raise their objections and
address these issues adequately.

The committee will provide many opportunities to redress complaints informally, in addition to the existing
formal administrative and legal procedures. However, the major grievances that might require mitigation
include:

   •       PAPs at risk of the project impacts;
   •       Pollution of water bodies in the area from project activities;
   •       Danger or loss of lives due to inadequate safety measures;
   •       Insecurity, cases of theft and sexual abuse;
   •       Conflict of interest between project and the community;
   •       Delay in response to the concerns of PAPs;
   •       Project activity impact on land and livelihood; etc.

Imo State RAMP 2 has put in place a Grievance Redress Framework following the World Bank’s approach
to GRM (Annex VIII). The framework has four levels of addressing grievances (Fig 7.1).



                                                     66
                                                                                        4.      Courts
                                                        Unresolved

                                Unresolved                3.        RAMP Steering and
                                                               Technical Committee


        Unresolved
                          2.       Project Management Unit – Grievance
                                  Redress Committee (PIU-GRC)




   1.       Grievance Redress Committee                         Resolved                     NO FURTHER
                                                                                               ACTION


Fig. 7.1 Imo RAMP 2 Grievance Redress Framework

As shown in the framework, Level 1; Grievance Redress Committee (GRC), Level 2; Project
Implementation Unit – Grievance Redress Committee (SPIU-GRC), Level 3; RAMP Steering and
Technical Committee and Level 4; is the Courts). Effort will be made to ensure that grievances are
addressed at the First Level. It will only move on to Second Level if the first level agreement was not
accepted by the party involved and then to third then to the fourth under similar situation. If a party is not
satisfied with the outcomes of Levels I, 2, and 3 then he/she can take the case to the Law Courts (the 4th
Level).

7.2 Grievance Redress Process
There is no ideal model or one-size-fits-all approach to grievance resolution. The best solutions to conflicts
are generally achieved through localized mechanisms that take account of the specific issues, cultural
context, local customs, and project conditions and scale.

In its simplest form, grievance mechanisms can be broken down into the following primary components:

    •        Receiving and registering a complaint.
    •        Screening and assessing the complaint.
    •        Formulating a response.
    •        Selecting a resolution approach.
    •        Implementing the approach.
    •        Announcing the result.
    •        Tracking and evaluating the results.
    •        Learning from the experience and communicate back to all parties involved.
    •        Preparing a timely report to management on the nature and resolution of grievances.

7.3 Structure of Grievance Redress for the RCs Rehabilitation Works
This grievance procedure is prepared in line with the provision of the RPF of the RAMP 2. The need to
provide a forum locally to receive, hear and resolve disputes is in the best interest of all parties to forestall
                                                         67
the lengthy process of litigation, which could affect the progress of project. Therefore, the setting of
Grievance Redress Committee (GRC) early during project implementation is desirable.

The RAMP 2 Grievance Redress Mechanism (GRM) shall receive and act upon complaints from
stakeholders or PAPs in relation to any occurrences for which the Project is directly responsible (or believed
to be responsible), and which are perceived by the aggrieved party to have involved corrupt, illegal, unjust,
or unfair activities, omissions, or behavior.

For the purposes of the RAMP 2, a complaint is a notification (in written, verbal or electronic form)
regarding project activities and/or conduct of staff, consultants, partners and/or sub- contractors, directly or
indirectly supporting the project or associated with its implementation, which the complainant believes is
wrong, either under the law or on the grounds of unacceptable behavior.

The complainant(s) need not be personally aggrieved or impacted, and may be acting merely in accordance
with a sense of civic duty in bringing an occurrence to the attention of project authorities.

In defining the levels of grievance redress, priority was given to aligning with the existing mechanism and
strengthening same as required, which was designed based on consultation and stakeholder inclusion during
the preparation of the ESMP. Defining the GRM process took into account the specific issues, cultural
context, local customs, industry standards and project conditions. The functioning of the GRM system, how
to register complaints (written, by phone, or in person), where to go and hours of service, all should be
clearly explained in local language during initial public consultations on the project.

7.4 Setting up a Grievance Redress Committee
The best solutions to conflicts are generally achieved through localized mechanisms that take account of
the specific issues, cultural context, local customs, and project conditions and scale. Three levels of
grievance redress channels have been identified:

7.4.1 First Level GRM: GRC at the Site/Community Level:
Complaints regarding project implementation and activities arising from the project area shall be channeled
to the Village head, who shall convene the GRC committee at that level to review and address the complaint.
The underlying merit is that the community has proven a notable channel for conflict resolution in the
project area. The Village head shall head this committee while membership of the committee will consist
of:

    •   The Village head -Chairman
    •   A representative of Council of Elders
    •   A representative of the Community Development Association
    •   A representative of Youth Organization
    •   Representative of the Women Group
    •   Social Safeguards Officer of the SPIU-Secretary
This committee will be expected to report to the SPIU. In addition, complaint box will be placed in the
Community leader’s palace, where complaints from PAPs can be dropped.

                                                      68
The complaints are received (in written, verbal or electronic form) at various points at Community Level.
These points may include one or more of the following;

        a) Complaint box
        b) Mobile application (WhatsApp, Telegram) Complaint line
        c) Toll-free/hot lines

The various points of receiving complaints at the provincial level would be as follows:

        a)   Respective LGAs;
        b)   Community Townhall
        c)   Designated spots along the RCs
        d)   Traditional Ruler’s Palace
        e)   Social safeguards/GBV Officers at SPIU

After registering the complaint in the Grievance Redressal Registration and Monitoring Sheet, the social
safeguards officer of SPCU would study the complaint made in detail and forward the complaint to the SPC
with specific dates for replying and redressing the same. The SPIU shall issue an acknowledgement letter
within five working days, including an outline of the complaint review and appeal process. A written
response shall be issued within two weeks. The SPIU can also coordinate a meeting with the aggrieved
party if required. To address such issues in an expedient manner, the SPIU shall nominate a sub-committee
to handle complaints. The sub-committee may adopt any of the traditional methods (community meetings,
elders-in- council, dialogue, council of chiefs, appeals and summons, elder’s assembly, religious leaders,
youth council, women groups) that is accessible and affordable in the settlement of complaints if required.
The deliberations of the meetings and decisions taken are recorded.

The resolution at the first tier will be normally be done within 14 working days and notified to the concerned
through a disclosure form. Should the Grievance not be solved within this period, this would be referred to
the next level of Grievance Redressal. However, if the social safeguard officer feels that adequate solutions
are worked out the problem and it would require a few more days for actions to be taken, he can decide on
retaining the issue at the first level by informing the complainant accordingly. However, if the complainant
requests for an immediate transfer of the issue to the next level, it would be accepted and the issue would
be taken to the next channel. But in any case, if the issue is not addressed within 21 days, it needs to be
taken to the next level.

7.4.2 Second Level of GRM: GRC at the SPIU Level:
The PIU shall receive, hear and address complaints arising from the project implementation. The Project
Coordinator (PC) shall head this committee while membership of the committee shall be as follows:

    •   Project Coordinator- Chairman
    •   Internal Auditor
    •   Monitoring and Evaluation officer
    •   Social Safeguard Officer- Secretary
    •   Environmental officer
                                                     69
    •   Communications Officer
    •   One representative of the non-state sector from within the State Project Monitoring Committees
If the complaint is not satisfied by the first level GRC response nor has a complaint regarding their decision-
making process, they can directly write to the SPIU. All complaints submitted to the SPIU shall be logged
with a unique ID code. Complainants shall receive an acknowledgement letter within 5 working days,
including an outline of the complaint review and appeal process. The complaint shall be filed according to
a tracking system, so that complaints are classified, and responded to consistently. Furthermore, the
complaint shall be discussed within the SPIU and responded to in writing within 2 weeks. The SPIU shall
also convene a meeting of the aggrieved parties if required. The SPIU shall undertake a six-monthly internal
review of the complaint handling mechanism, and make necessary corrections, if need be.
The SPIU-GRC will hold the necessary meetings with the complainant and the concerned officers and
attempt to find a solution acceptable at all levels. GRC would record the minutes of the meeting.
The decisions of the PIU-GRC are communicated to the complainant formally and if he accepts the
resolutions, the complainant’s acceptance is obtained on a disclosure form.
If the complainant does not accept the solution offered by the SPIU-GRC, then the complaint is passed on
to the next level / or the complainant can reach the next level. The Chairman of the SPIU-GRC would
require to forward the issue to the next level through the Secretary of the SPIU-GRC to facilitate in
exploring a solution to this at this level before transferring it to the Third level. In any case the case should
be forwarded to the next level if no solution is reached within 14 days of the case reaching the second level
and, in a case(s), nearing the required solution, it can be retained to an extent of 21 days.
7.4.3 Third Level of GRM: GRC at the State Technical Committee Level:
Any unresolved matter at the SPIU level will be channeled to the Project Technical Committee. The
committee at this level shall be headed by the Permanent Secretary ImoState Ministry of Water Resources
while the PC shall serve as the secretary of the committee.

Finally, if the complainant is not satisfied with the Community or SPIU response or has a complaint about
the overall RAMP II, or there is a time delay of more than a month in solving the issue, the complainant
can opt to consider taking it to overall Technical Committee GRC (TC-GRC) facilitated by the State
Ministry of Water Resources. This committee shall convene on a case-by case basis, arbitrate the issue
based on the guidelines established, and convene the necessary stakeholders if necessary. All the
stakeholders, including state and non-state actors shall be able to lodge a complaint with the TC-GRC.

The TC-GRC will be constituted as the Third Level of Redressal to look into the problems not solved in
the Second Level. Membership of the GRC at this level shall constitute as follows:

    •   The Permanent Secretary-Chairman;
    •   Director Ministry of Environment
    •   Director Bureau of Lands & Survey
    •   The Project Coordinator of RAMP 2
    •   A witnessing NGO
                                                       70
The Traditional/Community Leaders and the Commissioner of Local Government of the project
Community will be the invitees to the Committee meetings to enable the TC-GRC to understand the
deliberations of the Community Level GRC.

The Social Safeguard Officer of the SPIU will collect all the details of the Grievance including the
deliberations of First and Second level efforts and present it to the TC-GRC. The TC-GRC will deliberate
upon the issue and give suitable recommendations. The meetings are recorded. The decisions of the TC-
GRC are communicated to the complainant formally and if he accepts the resolutions, the complainant’s
acceptance is obtained on a disclosure form.

The decisions of the TC-GRC would be final from the Project side and the Complainant may decide to take
a legal or any other recourse if he /she is not satisfied with the resolutions due to the deliberations of the
Third Level GRC. The Complainant has also the option of approaching the Donor (World Bank), if they
find that the established GRM cannot resolve the issue.

7.4.4 Court Resolution of Grievance Matters
The possibility of seeking for grievance resolution in the court may be a last resort and should be expected,
especially, where the complainant felt dissatisfied with resolution of the GRC.

The provision of the RPF for RAMP 2 on this matter is that grievances concerning non-fulfilment of
contracts, levels of compensation, or seizure of assets without compensation shall be addressed to the state
local courts system of administration of justice. The court hierarchy would in ascending order therefore, be
land dispute tribunals/chiefs, followed by magistrate courts and then finally the high courts. The high court
of the state is being designated as the highest appellate court to settle grievances.

This, admittedly, is a costly and time-consuming procedure. Nevertheless, affected persons will be
exempted from administrative and legal fees incurred pursuant to this grievance redress procedure.

7.5 Awareness of GRM
GRM should be given a wide publicity among stakeholder groups such as affected parties, government
agencies, and civil society organizations. Effective awareness of GRM process makes people better
understanding about their options, depending on the types of complaints. However, measures should also
be taken to encourage stakeholders not to submit false claims. Criteria for eligibility need to be
communicated and also awareness campaigns should be launched to give publicity to the roles and functions
of the GRM.

Awareness should include the following components:

    •   Scope of the project, planned construction phases, etc.;
    •   Types of GRCs available; purposes for which the different GRMs can be accessed, e.g.,
        construction-related grievances, grievances related to physical and economic displacement,
    •   Types of grievances not acceptable to the GRC.
    •   Eligibility to access the GRM.

                                                     71
      •   How complaints can be reported to those GRC and to whom, e.g., phone, postal and email
          addresses, as well as information that should be included in a complaint;
      •   Procedures and time frames for initiating and concluding the grievance redress process; boundaries
          and limits of GRM in handling grievances; and roles of different agencies such as project
          implementer and funding agency.
      •   A variety of methods can be adopted for communicating information to the relevant stakeholders.
          These methods could include display of posters in public places such as in government offices,
          project offices, community centers, hospitals and health clinics of the area.

Similarly, an effective awareness program should be arranged to educate the PAPs on the following:

      •   Members of GRC and its location
      •   Method of complaining or reporting the grievance
      •   Taking part in the GRC meeting (is any companions of the complainant allowed)
      •   The steps of resolving process and timeline adopted in this mechanism.
      •   Needed documents and evidence to support of the complaint.

This information should be part of a simple brochure that explains the different grievance redress
possibilities for PAPs.

7.6       Reporting:
The Social Safeguard Officer of the SPIU would prepare the Quarterly Report on the Grievance Redressal
issues of the Project for addition into the quarterly report.

The TC-GRC will review the nature of grievances that have been represented and if similar grievances are
reported many times, suitable changes in implementation procedures / suitable policies would be worked
out and recommended to State Level Steering Committee for consideration and needful action.

7.7       GRM Jurisdiction:
This is a project specific GRM and applicable to solve the concerns of the stakeholders of the Project. This
is however not intended to bypass Governments own redress process; rather intended to address affected
people’s concerns and complaints promptly, making it readily accessible to all segments of the affected
people and is scaled to the risks and impacts of the Project. The Government Redress mechanism takes
priority over this one.

7.8       Expectation When Grievances Arise
When local people present a grievance, they expect to be heard and taken seriously. Therefore, the SPMU
and others such as the engineers involved in one aspect of the project or other must convince people that
they can voice grievances and work to resolve them without retaliation.

It should be understood that all or any of the following is or are expected from the project
management/channel of grievance resolution by the local people:

      •       acknowledgement of their problem,
                                                     72
    •       an honest response to questions/issues brought forward,
    •       an apology, adequate compensation,
    •       modification of the conduct that caused the grievance and some other fair remedies

7.9 Management of Reported Grievances
    a)      The procedure for managing grievances should be as follows:
    b)      The affected person files his/ her grievance, relating to any issue associated with the
            resettlement process or compensation, in writing or phone to the project Resettlement and
            Compensation committee (Phone numbers will be provided by the SPMU). Where it is written,
            the grievance note should be signed and dated by the aggrieved person. And where it is phone,
            the receiver should document every detail.
    c)      A selected member of the Site Committee will act as the Project Liaison Officer who will be
            the direct liaison with PAPs in collaboration with an independent agency/NGO person to ensure
            objectivity in the grievance process.
    d)      Where the affected person is unable to write, the local Project Liaison Officer will write the
            note on the aggrieved person’s behalf.
    e)      Any informal grievances will also be documented

7.10 Grievance Log and Response Time
The process of grievance redress will start with registration of the grievance(s) to be addressed, for reference
purposes and to enable progress updates of the cases. Thus, the person affected by the project will file a
Grievance Form with the Grievance Redress Committee. The Form (See table 21) should contain a record
of the person responsible for an individual complaint, and records dates for the date the complaint was
reported; date the Grievance Log was uploaded onto the project database; date information on proposed
corrective action sent to complainant (if appropriate), the date the complaint was closed out and the date
response was sent to complainant.

The Project Liaison Officer working with the local Government Desk Officer in recording all grievances
will ensure that each complaint has an individual reference number, and is appropriately tracked and
recorded actions are completed.

The response time will depend on the issue to be addressed but it should be addressed with efficiency. The
Grievance committee will act on it within 10 working days of receipt of grievances. If no amicable solution
is reached, or the affected person does not receive a response within 15 working days, the affected person
can appeal to the SLO in the SPMU, which should act on the grievance within 15 working days of its filing.

Table 7.1: Typical Reporting format for Grievance Redress
        Community                    Type of Grievance                             Grievance Resolution
         project &
          Name of
        Complainant




                                                      73
                                        CHAPTER EIGHT
                                  STAKEHOLDER CONSULTATION

8.1      Introduction
Public consultation for the proposed river crossings entails the process of informing stakeholders on the
need to carry out the ESMP of the project with respect to the project’s environment; the scope and the need
for the community to own and safeguard the project as beneficiaries. Public consultation should be a
continuous process and would be an ongoing activity throughout the project lifespan. Public participation
and consultation were carried out as necessary through meetings, requests for written proposals/comments,
filling of questionnaires, explanations of project to the locals, making public documents available at the
state and local levels at all stage of the project. At the local level, the stakeholder consultation was carried
out at the project sites and in the community town halls/open grounds. The consultation measures took into
account the low literacy levels prevailing in these rural communities by allowing an adequate amount of
time for responses and feedback. Nevertheless, details of public consultation are discussed.

8.2     Objectives
Stakeholders’ engagement is essential in achieving the major objectives of any project implementation and
sustainable development. Participatory approaches in project planning and implementation enhances
project policy, ownership and sustainability and also empower targeted beneficiaries. The objectives for
stakeholders’ engagement and sensitization include but not limited to the following;

i.      To create general public awareness and understanding of the project, and ensure its acceptance;
ii.     To develop and maintain avenues of communication between the project proponent, stakeholders
        and PAPs in order to ensure that their views and concerns are incorporated into the project design
        and implementation with the objectives of reducing, mitigating or offsetting negative impacts and
        enhancing benefits from the project;
iii.    To inform and discuss about the nature and scale of possible adverse impacts of the rehabilitation
        work and to identify and prioritize the mitigation measures for the impacts in a more transparent
        and direct manner;
iv.     To document the concerns raised by stakeholders and PAPs so that their views and proposals are
        mainstreamed to formulate mitigation and benefit enhancement measures;
v.      To sensitize other MDAs, local authorities, Non-governmental Organizations (NGOs) and
        Community Based Organizations (CBOs) about the project and solicit their views and discuss their
        share of responsibility for the smooth functioning of the overall project operations; and
vi.     To reduce potential conflict between stakeholders, project proponents PAPs.
vii.    To develop stakeholder’s capacity in the areas sustainable project management.

In summary, it goes to spell out the role of stakeholders in the project planning, implementation and
monitoring. Involving stakeholders in monitoring service delivery, revenues, budget execution,
procurement, contract awards, and reform policies can increase transparency, improve efficiency of service
delivery or budget execution, and reduce opportunities for corruption. Some mechanisms for stakeholders-
led monitoring include public expenditure tracking surveys, social audits, or stakeholder report cards.

                                                      74
  8.3       Stakeholder Engagement Approach
  8.3.1     Consultations in the Study Area

  For the ESMP, the consultant visited Imo state between 7th January and 13th April, 2019. Informal
  interactive sessions with the various stakeholders were carried out as necessary. The gathering provided
  insights into the state of the proposed river crossing, hierarchy of traditional rulers in the study area,
  community life style and dispute resolution system amongst others. Present at the interactive stakeholder
  consultation meetings were:
      •       Community Traditional rulers or President Generals at Umuoleche, Okpuala, Mgbidi, BSC,
              Umuomumu and Umuezedike
      •       Imo RAMP Environmental safeguard officer
      •       Imo RAMP Social safeguard officer,
      •       Community Women leaders
      •       Community Youth leaders
      •       General public (people living at the host communities).

  8.4      Stakeholder KIIs, FGDs, Community Meeting and Interpretation
  In all interactions, stakeholders present comprised of the State PIU’s environmental and social safeguard
  officers, representatives/leadership of the host communities, and Heads of community/ households.
  Information provided in this section is completely based on responses from stakeholders, documented
  reports in state and physical site observations.

  Key Informant Interview (KII) and Focus Group Discussions (FGDs) were carried out to obtain the
  stakeholders’ views on the project. The groups consulted include, The Elders, Women and youths in the
  Communities. other groups include Fishermen, farmers and hunters. The project engineer in Imo State
  RAMP and desk officer in Imo State Ministry of Local Government and Rural Development. Questions
  asked include efforts of the state/community to ensure accessibility, knowledge of the potential
  environmental and social impacts of the proposed sub-project activities, presence or absence of community
  conflict, community associations and cultural heritage that might be impinged upon by the project. This
  section attracts a large populace of the host communities as shown in Annex 3, 4 and 6. Summary of the
  IDIs and FGDs are provided in table 8.1 and 8.2, whereas site specific consultations are provided in table
  8.3.

  Table 8.1           Summary of Issues Raised at KIIs
Date of Consultation                13/04/2019
Name of Stakeholders                   All priority sites
Language                               Pidgin-English, English and Igbo
Questions                              Stakeholders comments and views                    Consultant’s Response
  • Description of the means of          • The main occupation of the residents of the Explanations were offered by the ESMP team:
    livelihood of the community            communities is farming                           • It was explained to them that another team of
  • How will the construction affect the • The impact of the intervention on the economy      consultant will prepare the Resettlement Action Plan
    economic activities of the people in   of the people will be mainly positive as it will   (RAP) to access and value structures that would be
    the community?                         improve their finances and social interaction      affected by the proposed intervention based on the
  • Suggested measures to mitigate the                                                        designed engineering drawing.
    negative environmental and socio-
                                                                 75
    economic impacts of the civil            • The members of the communities must be • It was also indicated that compensation would be paid
    works                                      efficiently consulted and carried along to      to people whose building/sources of livelihood would
                                               make them own the project                       be affected by the project implementation.
                                             • Sufficient compensation must be paid to those • The youth in the community were assured that they
                                               whose properties will be affected               would first be considered for employment before
                                             • Local workers must be employed especially       skilled and unskilled labour will be sought from other
                                               for non-skilled positions                       places.

   Table 8.2           Summary of Issues Raised at FGDs
Date of Consultation                 13/04/2019
Name of Stakeholders                    All Priority Sites
Language                                Pidgin-English, English and Igbo
Items                                   Stakeholders comments and views
  • Description of the means of          •     Most of the residents are farmers, depending solely on agriculture as their means of livelihood
    livelihood of the community          •     Members of the community were said to be of reasonably good health, with the common ailment such
  • Description of the health status of        as malaria and cough.
    members of the community             •     Youths make up the predominant portion of the community, followed by the middle aged and the
  • How the intervention will impact           elderly.
    on the health of the people of the •       Many youths in the community are artisans and can provide the workforce if needed.
    community                            •     Some residents listed headache, cough, catarrh, and fever as the common ailments that would likely
  • How will the construction affect the       surface during the period of construction because of the dust and fumes that will accompany the
    economic activities of the people in       construction.
    the community?                       •     Some residents said vulnerable members of the community would be assisted to cope with the
  • Effect of the construction on the          difficulties during the period of construction.
    accessibility to the community       •     The overwhelming majority said that women would be more affected because they do more work in
  • Effect of the construction on              caring for children and using the water from the River for domestic purposes. They are usually
    vulnerable groups                          responsible for purchase of food stuffs and other household goods, and are usually weaker than men.
  • How will the construction affect     •     A few respondents feel it would have the same effects since both sexes are plying the same route.
    men and women differently?           •     Traders would also face the difficulty of conveying their goods to their various points of businesses.
  • What will be the effect of the             Respondents recommended the provision of a pedestrian bridge during the construction that will be
    construction on those whose                strong, not too high and would also have rail guards to protect the elderly, school children and the
    livelihood are tied to the route?          handicapped.
  • Suggested measures to mitigate the •       The contractor was encouraged to wet the road with water during construction in the dry season to
    negative environmental and socio-          reduce dust.
    economic impacts of the civil        •     Some residents are scared that the river which is their main source of water may be affected during
    works                                      construction.


   Table 8.3 Summary of Issues Raised at Community Meeting
Date of Consultation                13/04/2019
Stakeholders in            Elders, Women and Youth, other members of the communities, Imo RAMP2 Social Safeguard Officer, ESMP
Attendance                 Consultant
Locations where            Umuoleche Community, Umuokpara Ofeiyi-Umuoleche (Okigwe LGA)
consultations took place
Language                   Pidgin-English, English and Igbo
Items                      Stakeholders comments and views                      Response to comments & views
Concerns/Complaints/Re • On culture and tradition, it was noted that there
                                                                           Explanations were offered by the ESMP team:
marks/Recommendations    is no archaeological site/ shrine located within
                         and around the project site;                       • With regards to making advances to women and underage girls,
                       • It was also mentioned that contractors/visitors        the community members were assured that their views and
                         are not allowed to make advances to married            concerns will be recorded and communicated to the contractors
                         women in the community.                                and other consultants that will be visiting
                       • Some of the stakeholders asked what their lots
                         would be should their farms and other properties
                         get affected by the proposed intervention.
                                                                    76
                           • The youth, especially the artisans among them      •   The youth in the community were assured that they would first be
                             enquired if they would be employed by the              considered for employment before skilled and unskilled labour
                             contractors                                            will be sought from other places.
                           • They asked for more River crossing projects for    •   It was explained to them that another team of consultants will
                             the community. Specifically, they feel Amagu-          prepare a Resettlement Action Plan (RAP) which will access and
                             Umulebe bridge and Okorobi-Umuju-Amaikpa               value structures that would be affected by the proposed
                             bridge are of higher priority than the selected        intervention based on the designed engineering drawing.
                             one.                                               •   It was also indicated that compensation would be paid to people
                           • They pleaded that as part of the project, RAMP         whose building/assets would be affected by the project
                             should help complete their health centre and           implementation.
                             improve their school                               •   It was also noted that the RAMP project is focused essentially on
                                                                                    rural accessibility (roads and River crossings). The community
                                                                                    members were therefore advised to visit the office of the World
                                                                                    Bank supported CSDP programme for assistance on project
                                                                                    related to health, school among others.

Date of Consultation                  13/04/2019
Stakeholders in            Elders, Women and Youth, other members of the communities, Imo RAMP2 Social Safeguard Officer, ESMP
Attendance                 Consultant
Locations where            Okpuala Community, Umuduru Emghara-Okpuala Anara (Isiala Mbano/Ehime Mbano)
consultations took place
Language                   Pidgin-English, English and Igbo
Items                      Stakeholders comments and views                     Response to comments & views
Concerns/Complaints/Re • There are no cultural issues in the community
                                                                              Explanations were offered by the ESMP team:
marks/Recommendations    that may hinder the implementation of the
                         project                                               • The ESMP consultant gave the dimension of the RC as 20 meters
                       • They expressed their happiness about the                 long and 8 meters wide. He also indicated that there will be an
                         intervention and look forward to seeing the              approach road which will be 7.3 meters wide with side drains
                                                                                  (750X750) on both sides of the road
                         contractors on site.
                                                                               • It was also indicated that compensation would be paid to people
                       • The nature of the intervention was also enquired.        whose building would be affected by the project implementation.
                         Is it a bridge or a culvert? What is its capacity?
                         Is it a single lane or dual carriage river crossing?

                            • Will the road be constructed too?
Date of Consultation                    12/04/2019
Stakeholders in            Elders, Women and Youth, other members of the communities, Imo RAMP2 Social Safeguard Officer, ESMP
Attendance                 Consultant
Locations where            Umuomumu Community, Orie Mbieri-Umuomumu Mbieri (Ikeduru/Mbatoli)
consultations took place
Language                   Pidgin-English, English and Igbo
Items                      STAKEHOLDERS COMMENTS AND VIEWS RESPONSE TO COMMENTS & VIEWS
Concerns/Complaints/Re • The ESMP team was welcomed by the             • Explanations were offered by the ESMP team:
marks/Recommendations    Community’s leader who expressed his joy         o The team assured the community of the genuineness of the
                         about the proposed River crossing across the       project.
                         Okitankwo stream.                                o They were also assured that their concern on the flow of the
                       • Several/past communal and individual efforts       River will be communicated to the Project Engineer
                         to improve accessibility were enumerated by      o It was explained to them that another team of consultant will
                         them;                                              prepare a Resettlement Action Plan (RAP) which will access
                       • Some of the locals expressed their skepticism      and value structures that would be affected by the proposed
                         about the seriousness of the proposed RAMP 2       intervention based on the designed engineering drawing.
                         intervention owing to their past experiences;    o The consultant explained that based on the World Bank
                         while some of the participants noted that the      procedure, representatives of the community will be part of the


                                                                 77
                          visit was their first time knowing about the       Project Implementation team. The fear of project hijack should
                          RAMP 2;                                            therefore not be entertained
                        • They requested that the flow of the stream       o With regards to making advances to women and underage
                          should be enhanced during the construction of      girls, the community members were assured that their views
                          the River crossing as it is currently silted.      and concerns will be recorded and communicated to the
                        • RAMP 2 to carry them along in the process of       contractors and other consultants that will be visiting
                          executing the project.
                        • They do not want the project to be hijacked by
                          politicians;
                        • In all, they expressed their happiness about the
                          intervention and look forward to seeing
                          contractors on site.
                        • It was also mentioned that contractors/visitors
                          are not allowed to make advances to married
                          women in the community.
Date of Consultation                13/04/2019
Location               Uzuruanamu community, Uzurunamu-Okwudo Mgbidi (Oru east/Oru west/Orsu)
Stakeholders in        Elders, Women and Youth, other members of the communities, Imo RAMP2 Social Safeguard Officer, ESMP
Attendance             Consultant
Language               Pidgin-English, English and Igbo
Items                  Stakeholders Comments and Views                     Response to Comments & Views
Concerns/Complaints/Re •   It was indicated that the community council
                                                                            Explanations were offered by the ESMP team:
marks/Recommendations      constructed a bridge over the River in the past.
                       •   Some of the stakeholders asked what their lots • On the issue of Obana River and the deified Boa constrictors,
                           would be should their farms and other                the community members were assured that their concerns will be
                           properties get affected by the proposed              documented and communicated to the contractor and other
                           intervention.                                        consultants
                       • On their culture and tradition, it was noted that • It was explained to them that another team of consultant will
                           there is a shrine located within and around the      prepare a Resettlement Action Plan (RAP) to access and value
                           project site. It is the Obana River; a deity         structures and all other cultural activities that would be affected
                           where no fishing is allowed.                         by the proposed intervention based on the designed engineering
                       • The Boa is also a deity. They are harmless and         drawing.
                           should not be killed                               • They were assured that cultural areas are special in all World
                       • Sexual relationship with underage or                   Bank supported projects and will be paid extra attention
                           unmarried girls especially teenagers is not       • With regards to making advances to women and underage girls,
                           allowed. Any girl who gets pregnant before            the community members were assured that their views and
                           the Fattening process would be ostracized for         concerns will be recorded and communicated to the contractors
                           life and her family shamed.                           and other consultants that will be visiting
                       • Nobody is expected to take the water from the • It was also indicated that compensation would be paid to people
                           Obana River home on small Orie days (market          whose building would be affected by the project implementation.
                           day).                                              • On the issue of water use, the consultant indicated that this will
                       • The community leaders gave assurance that all          be documented and conveyed to the contractor (See Sec 5.2.2.2
                           the necessary rituals will be carried out            and section A9 of the ESMP Matrix)
                           without major cost implication before the
                           commencement of the project.
Date of Consultation                13/04/2019
Location               Obinugwu Community, Ugbele-Bsc (Ideato South)
Stakeholders in        Elders, Women and Youth, other members of the communities, Imo RAMP2 Social Safeguard Officer, ESMP
Attendance             Consultant
Language               Pidgin-English, English and Igbo
Items                  Stakeholders comments and views                     Response to comments & views
Concerns/Complaints/Re
                       •   Some of the stakeholders asked what their lots Explanations were offered by the ESMP team:
marks/Recommendations
                           would be should their farms and other


                                                               78
                               properties get affected by the proposed • The ESMP consultant gave the dimension of the RC as a culvert.
                               intervention.                                      The dimension of the RC as 20 meters long and 8 meters wide. He
                                                                                  also indicated that there will be an approach road which will be
                          • The nature of the intervention was also enquired.     7.3 meters wide with side drains (750X750) on both sides of the
                            Is it a bridge or a culvert? What is its capacity? Is road He also indicated that there will be an approach road which
                            it a single lane or dual carriage river crossing?     based on the engineering design is an earth road. It is also a single
                                                                                  lane road.
                          • Will the road be constructed too?                     •          It was explained to them that another team of consultant
                                                                                             will prepare a Resettlement Action Plan (RAP) to access
                                                                                             and value structures that would be affected by the
                                                                                             proposed intervention based on the designed
                                                                                             engineering drawing.
                                                                                  •          It was also noted that the RAMP project is focused
                                                                                             essentially on rural accessibility (roads and River
                                                                                             crossings). The community members were therefore
                                                                                             advised to visit the office of the World Bank supported
                                                                                             CSDP programme for assistance on project related to
                                                                                             health, school among others
Date of Consultation                      13/04/2019
Location                 Umuezedike Community, Umuokpara Ofeiyi-Umuoleche (Okigwe)
Stakeholders in          Elders, Women and Youth, other members of the communities, Imo RAMP2 Social Safeguard Officer, ESMP
Attendance               Consultant
Language               Pidgin-English, English and Igbo
Items                  Stakeholders comments and views                     Response to comments & views
Concerns/Complaints/Re
                        • Some of the stakeholders asked what the lots Explanations were offered by the ESMP team:
marks/Recommendations
                          would be should their farms and other properties
                                                                            • It was explained to them that another team of consultant will
                          get affected by the proposed intervention.          prepare a Resettlement Action Plan (RAP) to access and value
                          • The youth, especially the artisans among them     structures that would be affected by the proposed intervention
                                                                              based on the designed engineering drawing.
                            enquired if they would be employed by the
                                                                            • The youth in the community were assured that they would first be
                            contractors                                       considered for employment before skilled and unskilled labour
                          • They asked for more River crossing projects for   will be sought from other places.
                                                                            • With regards to their request for more RCs, the community
                            the community.
                                                                              members were assured that their request will be communicated to
                          • They pleaded that as part of the project, RAMP    the SPIU. It was noted that the selected priority roads are the ones
                            should help complete their health centre and      considered at this phase and others will be considered in
                                                                              subsequent phases.
                            improve their school
                                                                            • It was also explained that the RAMP project is focused essentially
                                                                              on rural accessibility (roads and River crossings). The community
                                                                              members were therefore advised to visit the office of the World
                                                                              Bank supported CSDP programme for assistance on project
                                                                              related to health, school among others



   The main issues expressed by the stakeholders during the public consultation with regards to the proposed
   river crossing in their project locations include:

   1.     Existence of cultural rites in some communities (Mgbidi). This issue was addressed by the
          community leaders who gave assurance that all the necessary rituals, consultations, compensation
          will be carried out before the commencement of the project. The consultant further explained that the
          World Bank OP 4.11 addresses such issues of physical and cultural resources and a PCR plan is
          provided in Annex XII

                                                                  79
2.    Request for other river crossings. This issue was resolved by explaining to the beneficiaries that
      the selected priority roads are the ones considered at this phase and others will be considered in
      subsequent phases.
3.    Bad state of existing access roads. This was resolved by explaining to the beneficiaries that the
      approach roads to the river crossings will be rehabilitated/constructed
4.    Zero tolerance to sexual relations with underage and married women. The community members
      were assured that their concerns will be communicated to the contractor and other visitors
5.    Possible pollution of rivers during construction. This was resolved by explaining to the members
      of the communities that adequate mitigation measures will be put in pace to forestall the pollution

The communities’ expectations during construction and operation phases are as follows:
1.   Employment of the local during construction and operation phases of the project should be
     prioritized;
2.   For safety and security of workers, machinery and equipment, the host communities are willing to be
     engaged for proper policing;
3.   Adequate compensation to people whose properties will be lost due to the intervention, especially
     along the channel of water distribution. This will be captured in RAP report
4.   With regards to the creation of alternative routes, the beneficiaries were informed that alternative
     routes will be captured in the engineering designs for all the river crossings to ease their movement
     during construction.
5.   The potential impact of construction on the River was raised. The beneficiaries were informed that
     mitigation measures will be developed to reduce this impact. This also applies to other environmental
     impacts connected to the project

In general, the host communities are peace-loving people. Also, the communities assured the ESMP team
of total cooperation with the State’s coordinators, contractors and consultants. They promised adequate
security and protection of lives, properties and equipment during construction and operation phases. Plates
in Annex 6 show the consultation sessions/meetings with the communities.




                                                    80
                                             CHAPTER NINE

                               SUMMARY AND RECOMMENDATIONS

9.1      Summary
The study assessed the basic biophysical and social baseline information of the proposed intervention site,
identified susceptible environmental parameters, which may be positively and or negatively impacted upon
at the different phases of the project. It also presented the necessary mitigation measures for such identified
impacts. An assessment of the ground state of affairs illustrates that the nature and extent of accessibility is
poor within the project sites. The proposed intervention works will therefore positively impact on human
lives and improve their productivity. Similarly, the residents of the communities within the project sites
have also expressed their acceptance for the intervention. Hence, the proposed intervention project is a
welcome development to the affected communities.

9.2     Recommendation
The following recommendations are for the consideration of the Imo State RAMP SPIU. The
recommendations are geared towards ensuring the improvement of decisions and filling of gaps identified
by the ESMP study.

   •        There is the need for more public consultation and awareness to ensure the buy-in and ownership
            of the proposed projects by the host communities.
   •        There is a need to create more awareness on the anthropogenic causes of soil erosion and
            flooding with a bid to ensure project sustainability after the river crossing rehabilitation works.
   •        Waste management is also a serious issue in the area as residents tend to dump their refuse in
            the drainages. These should be discouraged and programme designed to enlighten them on best
            practice for refuse disposal.
   •        All managers must sign the ‘Manager’s Code of Conduct’ detailing their responsibilities for
            implementing the company’s commitments and enforcing the responsibilities in the ‘Individual
            Code of Conduct’.
   •        All employees must sign the project’s ‘Individual Code of Conduct’ confirming their agreement
            not to engage in activities resulting in GBV or VAC.
   •        Displaying the Company and Individual Codes of Conduct prominently and in clear view at
            workers’ camps, offices, and in in public areas of the work space. Examples o f areas include
            waiting, rest and lobby areas of sites, canteen areas, health clinics.
   •        Ensure that posted and distributed copies of the Company and Individual Codes of Conduct are
            translated into the appropriate language of use in the work site areas as well as for any
            international staff in their native language.
   •        An appropriate personnel trained on survival centered approach in handling GBV issues is
            nominated as the company’s ‘Focal Point’ for addressing GBV and VAC issues, including
            representing the company on the GBV and VAC Compliance Team (GCCT) which is comprised
            of representatives from the client, contractor(s), the supervision consultant, and local service
            provider(s).
   •        That the company effectively implements the Action Plan, providing feedback to the GCCT for
            improvements and updates as appropriate.



                                                      81
•   All employees attend an induction training course prior to commencing work on site to ensure
    they are familiar with the company’s commitments and the project’s GBV and VAC Codes of
    Conduct.
•   The construction site will be fenced off with temporary fencing to all surrounds. Site fencing
    will prevent any access from un-authorized entry to site. Construction site access is through site
    entry only.
•   The construction vehicle site entry will be via the Road and will make use of driveway access
    then flowing across a vacant allotment to an existing bitumen paved parking area. This makes
    use of the of the existing site conditions and reduces the impact to the adjoining facilities. All
    of the construction deliveries and access will be via this entry.
•   Clear signage will be erected outlining the construction entry. Construction pedestrian / workers
    access will be separated from vehicle access by way of separate pedestrian entry from adjoining
    footpath. Workers will have a direct footpath access to site amenities from pedestrian entry gate.
•   A delivery area will be located within the site compound - All material deliveries for the works
    will be made via the entry/entry via the Road. Vehicular movements around the building will
    be managed by trained traffic management operatives. All vehicles will enter and exit the
    construction site in forward facing direction.
•   Tower crane will generally be used to unload heavy material and equipment directly from the
    truck. They are to be lifted to the designated location or on to loading platform. Traffic control
    during loading and unloading inside the construction site will be carried out by contractor’s
    representative.
•   A man and materials hoist will be used to provide safe access on the floors and the movement
    of smaller materials. A safe pedestrian access will be provided to the hoist location.
•   The Contractor shall be required to provide appropriate information, training, instruction or
    supervision necessary to protect all persons from risks to their health and safety.
•   The Contractor must also ensure construction induction training is provided to workers who
    carry out construction work.
•   Use water suppression to prevent dust emission
•   Maintain vehicles and machineries to reduce emission
•   Maintain low speed to reduce dust and gaseous emission
•   Vegetal waste shall be supplied to farmers for use as compost.




                                             82
                                                    ANNEXURE

ANNEX 1: TERMS OF REFERENCE

DETAILED ASSESSMENT, PRIORITISATION, ENGINEERING DESIGN, AND ENVIRONMENTAL
AND SOCIAL MANAGEMENT PLAN FOR REINSTATING/CONSTRUCTING DAMAGED, WASHED
AWAY AND MISSING RIVER CROSSINGS ON THE RURAL ROAD NETWORK IN IMO STATE

1.0      Background
The Second Rural Access and Mobility Project (RAMP-2) is a World Bank (WB) and French Development Agency
(AFD) assisted project in support of the implementation of the National Rural Travel and Transport Policy (RTTP) in
Imo State. The project is being coordinated by the State Project Implementation Unit (SPIU) under the Imo State
Ministry of Local Government and Rural Development. The main objective of the project is to improve transport
conditions and bring sustained access to the rural population through constructing/rehabilitating and maintaining key
rural transport infrastructure in a sustainable manner.

Imo State Government intends to apply part of the RAMP-2 financing towards the detailed assessment, prioritization,
engineering design, and environmental and social management plan for reinstating/constructing damaged, washed
away and missing river crossings on the rural road network in Imo State. The SPIU on behalf of Imo Sate Government
proposes to commission the services of a qualified and experienced consultant firm (hereinafter called “the
Consultant�?) to undertake the assignment. (hereinafter called “the Services�?) herein described.

2.0      Objectives of Consultancy Service
The objectives of the Services are as follows:
•    To carry out an initial assessment of the condition, size and approximate construction/rehabilitation cost
     associated with each candidate on the long-list provided (attached as Annex I), together with the reported reasons
     for failure and for local prioritization, while also rating their apparent priority based on an agreed framework of
     broad socioeconomic criteria. And develop an initial short-list of approximately eighty (80) candidates for
     further prioritization.
•    To carry out a detailed assessment of the condition of the identified/short-listed river crossings, evaluate the
     relative economic and social importance and benefits of the river crossings, and carry out the prioritization and
     ranking of the river crossings, for approval.
•    To carry out the detailed engineering design and production of full bidding documents for about twenty-three
     (23) of the prioritized river crossings (generally including but not limited to culverts and small bridges with total
     spans not exceeding 15.0m) with all associated Works.
•    To prepare the Environmental and Social Impact Assessment (ESIA), the Environmental and Social Management
     Plan (ESMP), and, if necessary, the Abbreviated Resettlement Action Plans (ARAPs) for the proposed
     interventions.

3.0.     Project Description
The SPIU has compiled a long list of river crossings, which have been identified by the Local Government Authorities
as requiring such Works. The list of roads about eighty (80) river crossings have been identified is attached as Annex
I of the TOR. These river crossings are by no means exhaustive. Over and above these identified crossings the
Consultant shall allow for the inclusion of about twenty (20) additional river crossings. These will be identified by the
SPIU and the Consultant for consideration during the assessment phase and will consist of those river crossings that
are deemed to be critical for network coherence and the establishment of proper access for the affected rural
communities as well as alignment with the objectives of the Nigeria Agricultural Transformation Agenda (NATA).
                                                           83
The provision of the consultancy services will then entail:

    •    Initial Assessment: An initial on-the-ground assessment of the condition, size and approximate
         construction/rehabilitation cost associated with each candidate on the long-list provided (attached as Annex
         I), together with the reported reasons for failure and for local prioritization, while also rating their apparent
         priority based on an agreed framework of broad socioeconomic criteria. And develop an initial short-list of
         approximately 50 candidates for further prioritization.
    •    Prioritization: A more extensive visit to the identified/short-listed river crossings to further assess their
         condition and detailed rehabilitation/construction requirements, together with collection of socioeconomic
         data of the project areas so as to enable the prioritization and ranking of the river crossings in order of their
         socioeconomic importance and alignment with the goals of the Nigeria Agricultural Transformation Agenda.
    •    Engineering Design and Production of Bidding Documents: The detailed engineering design of all the
         Works associated with the construction/rehabilitation of the priority river crossings, together with Preparation
         of the associated Bidding Documents.
    •    Preparation of the Environmental and Social Impact Assessment (ESIA), the Environmental and Social
         Management Plan (ESMP), and, if necessary, the Abbreviated Resettlement Action Plans (ARAPs) for the
         proposed interventions.

4.0      Scope of Services

The scope of the consultancy services shall include the following;

A.       INITIAL ASSESSMENT.

4.1      Carry out an initial on-the-ground assessment of the condition, size and approximate
         rehabilitation/construction cost associated with each candidate on the long-list provided (attached as Annex
         I), together with the reported reasons for failure and for local prioritization, while also rating their apparent
         priority based on an agreed framework of broad socioeconomic criteria. And develop an initial short-list of
         approximately fifty (50) candidates for possible prioritization

B.       PRIORITIZATION

4.2      Data collection and desk study

The Consultants shall collect and review all relevant existing data as available in respect of the candidates short-listed
through the initial assessment, including but not limited to: maps and aerial photographs if available/necessary; any
as-built drawings for the candidate river crossings; traffic surveys; geology/stream morphology,
hydrological/hydraulic data (water levels & scouring); locations of any existing and proposed utilities, present
condition of the crossing, their banks, abutments, roads and river training works (character and shape including
existing soils forming the embankments) etc.

4.3      Detailed Condition Assessment

The Consultant shall then complete the existing data and collect the following information:

•       GPS reading for each of the identified sites/location
•       Traffic levels and composition


                                                           84
•     Show on a separate road map, based on the GPS readings, for each Local Government Area, the position of the
      identified river crossings and the respective road links and the class of road involved and its condition.
•     Basic measurements and arrangements of the structures (type, length, height, skew, spans, number and
      diameter/size of pipes/culverts and small bridges etc). Where structures are completely washed away, the
      Consultant shall note this accordingly.
      1. Condition of the structure, preliminary scope of works and key cause for required works.
      2. Comprehensive Digital Photographs.
      3. The nature and condition of the existing alignment and approaches.
      4. Prepare preliminary cost estimates for the proposed remedial works and/or hydraulic structures
      5. Recommend appropriate type and size of hydraulic structure for crossings without any existing structures.
      6. Classify the various structures in terms of size, type, associated additional necessary works; and costs.

4.4       Economic and Social Evaluation

The Consultant shall also:

      •      Collect and review data relating to the demography, agricultural activities, land use characteristics and
             social amenities in the proposed project corridors.
      •      Evaluate the data collected and assess the benefits that will accrue to the communities due to the
             proposed works.

4.5       Prioritization and Ranking

Based on the data collected from the above activities, the Consultant shall carry out a Multi Criteria Analysis (MCA)
based on the following criteria:

•     Social Criteria: These include estimated population of settlements located along each route, number of health
      facilities and schools to be served by each identified or selected river crossing.
•     Economic Criteria: These include the observed traffic and the previously recorded traffic, the number of
      markets and cottage industries, volume of agricultural output that are found along or connected by each link.
•     Accessibility Criteria: These include average cost of transportation per kilometer and road density within the
      local government area in which each link is located.
•     Cost Criteria: The estimated cost of the proposed works to be carried out at the identified locations; and the
      budgetary impact.
The Consultant shall propose weightings for the foregoing criteria and any additional criteria with justification.

The Consultant may also propose variations to the evaluation method with adequate justification for the Client’s
consideration for approval during the course of the assignment but well ahead of the prioritization.

The Consultant shall thereafter produce a list of the short-listed river crossings, showing the results of socioeconomic
evaluation and the costs of the proposed works, with details, arranged in the order of priority/ranking, w ith the
cumulative costs also shown. This shall then be presented for approval, prior to proceeding with the detailed design.




                                                          85
      C.       ENGINEERING DESIGN & PREPARATION OF BIDDING DOCUMENTS

      4.6      General

      This phase shall focus on the agreed prioritized of the structures (and their associated works) selected for immediate
      repair/rehabilitation and replacement. The Services shall include the engineering design, completion of drawings
      where required (Standards drawings should be used as far as possible), preparation of detailed cost estimates and
      bidding documents.

      •      All identified structures larger than small bridges (maximum span 15.0m) shall not be included in this phase.
      •      The services as detailed below are required for a total number of about 25 river crossings of varying sizes and
             spread out over the entire Imo State. Should the final agreed number differ substantially (by more than 30%),
             such difference would form the basis of an addendum.

      4.7    Engineering Assessment and Design

      i)     The first phase of assessment should be confirmed in terms of requirements to complete the required
             engineering design to reinstate the structures at the identified river crossings. It is expected that the need for
             additional inspections would be minimal and focused only on the larger structures (larger culverts and small
             bridges) included in this phase.
             Where the affected road crosses a low-lying area that is prone to seasonal flooding, the intention is to provide
             both the river crossing and approaches that will enable all-weather use of the road link.

      ii)    The Consultant shall assess the seasonal traffic volume prevalent at the time. For determining the annual and
             other seasonal traffic patterns standard procedures, of using existing data to project traffic patterns shall be
             applied.

      iii)   Execute topographic and geotechnical field work to establish the necessary data and basic drawings for the
             detailed design at appropriate scale to determine location, elevation, foundation levels and sizes of the new
             and, as needed, of the existing structures. Special attention shall be given to the required information for
             hydraulic dimensioning of the structures and the protective measures for the watercourses. If elevations cannot
             be referred to the official level system permanent benchmarks have to be placed and secured which will permit
             to re-establish the reference height at each structure. Access ramps and modified road sections shall be included
             to the extent, which permits proper adoption of the existing alignment to the new situation.

The scales of the design drawings shall be:

•            Site Plan including approach roads (scale: 1/1000)
•            Longitudinal (vertical) and transverse alignment (scale: 1/500)
•            River profiles (cross section; scale:1/100-1/250) of the present and potential crossing points marked with
             high water, flood water, and low water level
•            Standard cross section of approach roads (scale: 1/100)
•            General Plan/View and cross section of proposed bridges or culverts (scale:1/50 - 1/100)
•            Structural details of the bridge and culverts (scale: 1/10 - 1/50), etc.
iv)          Undertake detailed structural design and calculation using British Standards (BS) or any other internationally
             recognized code of practice. The loading must in any case be identical with those regularly applied for the
             respective types of roads in Nigeria.
                                                                86
v)            Detailed design of erosion and scouring protection and control for each structure.

vi)           The scales of the design drawings shall be 1/50 - 1/100. The detailed design drawings for the agreed structures
              shall include detailed drawings for erosion and scouring protection and protection measures.

vii)          Verify the hydraulic effectiveness of the proposed dimensions of all structures included in the programme.

viii)         Ensure compliance with the Environmental and Social Management Plan being developed in parallel with the
              design of the Works.

ix)           Prepare the detailed design drawings for the agreed structures and the agreed associated Works, where
              applicable to include the approach road sections at appropriate scales and in such a detail that contractors
              may confidently bid and execute all construction work without further design except for workshop drawings
              for formwork, scaffolding and other auxiliary installations. Particular attention shall be paid to the
              elaboration of essential standard details as transition joints, bearing, railings, etc., which shall be serviceable
              and easy to be maintained. Where applicable, the safety of all structural parts shall be verified by static and
              foundation engineering analysis (for computer-based calculations the type of computer and the programmes
              used shall be mentioned) using British Standards (BS) or any other internationally recognized code of
              practice. The loading must in any case be identical with those regularly applied for the respective types of
              roads in Nigeria.
x)            Prepare Bills of Quantities and actual cost estimates based on unit prices broken down in local currency. Tax
              and duty elements shall be presented separately. The estimate for the right-of-way acquisition, if any, shall be
              furnished by the SPIU for each land property used.

xi)           Draw up Bid Lots by grouping the structures according to geographical location, magnitude and nature of work
              etc.

xii)          Prepare a detailed Time schedule for the programme based on the proposed packaging and the individual
              construction time for each structure assuming a practical sequence of activities under given climatic conditions
              and taking into account the time needed for tendering, contract negotiations and award, mobilisation, etc. The
              expected Cash Flow shall also be indicated.

4.8           Preparation of Bidding Documents.

       The Consultant shall prepare bidding documents for the Civil Works contracts for each Lot, conforming to the World
       Bank’s “Standard Bidding Documents for Procurement of Works�?. A draft of the propos ed final documents shall be
       furnished to the SPIU as scheduled in section 4.9 below.

       Final complete bidding documents including instruction to bidders, detailed engineering plans and drawings, standard
       technical specifications, specifications of particular applications, model contract, special conditions of contract, and
       bills of quantities, shall also be furnished to the SPIU as scheduled in section 4.9 below. The ESMP shall be included
       as an annex to the bidding documents.

       D.       Environmental and Social Impact Assessment

       For the short-listed sites, the Consultant shall conduct an Environmental and Social Impact Assessment (ESIA) in line
       with World Bank Operational Policy OP4.01 to identify, quantify and to the extent possible monetize the likely
       negative and positive environmental and social impacts of the proposed works, and suggest the required mitigating

                                                                  87
measures (in the form of an Environmental and Social Management Plan, ESMP) to be implemented to avoid these
negative impacts. As needed, the ESIA and the ESMP will also include “chance find procedures�? as per the World
Bank Operational Policy for Physical Cultural Resources (OP/BP 4.11). The ESIA shall among others: (i) Recommend
an appropriate Institutional structure for safeguard in the rural roads that will guarantee sustainable safeguard measures
system; (ii) Explore the possibilities for community-based safeguard approach and the Capacity Building needs of the
relevant stakeholders; and (iii) Explore and recommend alternative safeguard measures/models.

The ESMP shall contain the following:
i)      Summary of Environmental Impact
iv)     Environmental and Social Impact Mitigation Measures (At Design, Construction and Operation phases)
v)      Environmental Monitoring Plan (At Construction and Operation phases)
vi)     Cost Estimates for Mitigation and Monitoring
vii)    Costs for implementation of monitoring
As needed, Resettlement Action Plan (RAP) or Abbreviated Resettlement Action Plan (ARAP) in line with World
Bank Operational Policy OP4.12, to ensure that the eventual Project Affected Persons (PAPs) are adequately
compensated or provided assistance. However, it is not anticipated that land acquisition or resettlement will be
undertaken as all project physical activities would be carried out at on the existing right of way (ROW).

In preparing the ESIA, and if necessary, the RAP/ARAP, the Consultant shall take cognizance of the issues highlighted
in the existing Environmental and Social Management Framework (ESMF) and the Resettlement Policy Framework
(RPF) for RAMP-2.

The ESIA and ESMP shall be comprehensive and cover all social risks, including: (a) Labor including care of
contractors’ workers, restriction of the use of child labor and prevention of child sex abuse that could be caused
by the influx of workers; (b) Safety at construction sites and safety of the local community; and (c) Health aspects,
including risks affecting sanitation and general health of the local community and prevention of HIV/AIDS. The
ESIAs shall assess and document the economic and social benefits of the project to the local community and
identify initiatives that will help resolve the challenges confronting the social and economic well - being of the
community, gender inequality, and ultimately reduce poverty and enhance shared gr owth. The safeguards
assessment and monitoring during implementation will include the possible impacts generated by the influx of
works (Labor influx) to be involved in the construction and mechanized maintenance.

4.9      Reporting Requirements
The following reports are required:
•      Inception Report providing details of the Consultant’s establishment and mobilization; the extent of provision
       of a suitable counterpart and all the data stipulated under section 5.0 herein; the Consultant’s initial findings ;
       the proposed methodology and implementation programme plus details needed or actions to be taken by SPIU
       to enable the assignment to be completed. The report shall be submitted in four (4) copies (two hard and two
       electronic) to SPIU within two (2) weeks of commencement of the assignment.
•      Initial Assessment and Short-Listing Report with necessary preliminary assessment and the initial
       prioritization/short-listing of candidates, maps and the initial major findings of the Initial Assessment phase of
       the study. The report shall be submitted to SPIU in four (4) copies (two hard and two electronic) for review
       and necessary approval prior to commencement of the Detailed Assessment and Prioritization Phase. This
       report shall be submitted within six (6) weeks of the start of the assignment, and shall be submitted to SPIU in
       four (4) copies (two hard and two electronic) for review, comment and approval to proceed.
•      Detailed Assessment and Prioritization Report including all the comments of the Client shall be furnished
       to the SPIU not later than ten (10) weeks after the start of the assignment. Ten sets of documents (Eight hard

                                                           88
        and two electronic copies) shall be prepared and submitted. The Consultant shall include with the Final
        Prioritization Report, in electronic format, inter alia, the socio-economic data, maps, and GPS data.
 •      Draft Design Report and Sample Bidding Document, the latter to include instruction to bidders,
        preliminary engineering plans and drawings, standard technical specifications, specifications of particular
        applications, model contract, special conditions of contract, and bills of quantities. The Draft Design Report
        and the Sample Bidding Document shall be furnished to the SPIU within twelve (12) weeks of the start of the
        assignment. Three hard and two electronic copies shall be prepared and submitted to SPIU for review and
        approval.
 •      ESIA: The Consultant shall also submit within twelve (12) weeks of the start of assignment four (4) hard
        copies and two electronic copies of the ESIA and if needed the RAP/ARAP to the SPIU for review and onward
        disclosure.
 •      Final Design Report and full Bidding Documents (for each Lot) shall be submitted to SPIU, including
        instruction to bidders, detailed engineering plans and drawings, standard technical specifications, specifications
        of particular applications, form of contract, special conditions of contract, bills of quantities. These shall be
        furnished to the SPIU no later than fifteen (15) weeks after the start of the assignment. Ten sets of documents
        (eight hard and two electronic) shall be prepared and submitted for each Lot. Together with 10 (ten) copies of
        the Final Design Report (eight hard and two electronic copies).

Report Schedule                                                          Due date (N=commencement of contract)
Inception Report                                                         N+2 weeks
Initial Assessment & Short-Listing Report                                N+6weeks
Allow for SPIU agreement/approval                                        N+6 weeks
Detailed Assessment & Prioritization Report                              N+10weeks
Allow for SPIU agreement/approval                                        N+11 weeks
Draft Design Report & Sample Bid Document                                N+12 weeks
ESMP                                                                     N+12 weeks
Allow for SPIU agreement/approval                                        N+13weeks
Final Design Report and Full Bid Documents                               N+15weeks


 5.0      Services to be provided by the Client
 5.1      At the commencement of the Services, the Client will provide the Consultant with the Long-List of candidate
 river crossings and any other structures to be considered. The Client will also make available details (if available) of
 each of the river crossings before they were damaged, the cause of damage, and copies of standard design drawings
 for small span bridges (up to 15m span), single and multiple reinforced concrete Box Culverts, single and multiple
 pipe culverts, river training works, and the different class of road structures. In addition, the Client will make available:
 The Agricultural Transformation Agenda (ATA); the existing Environmental and Social Management Framework
 (ESMF) for RAMP2; and Resettlement Policy Framework (RPF). And, for the duration of the initial assessment
 phase, the Client will make available a counterpart to serve as a guide to the Consultant to ensure the candidate river
 crossings are properly located and the local administrations are contacted for input.




                                                              89
All the information, data and reports obtained from the SPIU in the execution of the Services of the Consultant shall
be properly reviewed and analyzed by the Consultant. The responsibility for the correctness of using such data shall
rest with the Consultant. All such information, data and reports shall be treated as confidential.

The Consultant shall be responsible for arranging necessary office and living accommodations, transportation,
equipment, supplies, surveys, investigations, testing, secretarial services and all other input required for the purpose
of the works. The Consultant shall make his own arrangements for document reproduction, printing and reproduction
of all study reports during the course of the assignment.

5.2      Liaison with the SPIU.
Consultants shall be free to consult the SPIU for further explanation and clarification concerning these Terms of
Reference.

5.3      Conduct of the Consultancy

The Consultant shall be based in Owerri Imo State Capital and shall manage the Services from their Owerri offices.
The SPIU will oversee the consultancy services. The study will commence with a briefing from the SPIU. The
Consultant shall work closely with SPIU and road authorities.

5.4      Ownership of Data and Third-Party Usage

All the computer software, maps, data and information provided, developed and collected during this exercise shall
belong to the Client. No use shall be made of them outside of the project without the formal prior authorization
from the Client. At the end of the Services, the Consultant shall relinquish all data, maps, software and information
to the Client and shall make no use of them in any other study without prior authority from the Client.

5.5      Estimated Organizational Setup of the Assignment and Staffing.

The Consultant is solely responsible for proposing an organizational setup of the assignment which in his view is
appropriate for carrying out the assignment, fulfilling the Terms of Reference and producing the required outputs.
As a general guide, the organizational setup should reflect (i) the expectations of the Client, (ii) the knowledge of
the situation and desired outcomes, and (iii) the time frame for the delivery of outputs.

Time frame: It is expected that the Services shall be carried out within four (4) months. The estimated Consultant
input is about 24 person-months.

The table showing the estimated 24 person-month to be inserted here

The Consultants shall provide the following key staff to carry out the Services as described above:

*        Team Leader: a qualified engineer with BSc degree in civil engineering with a minimum of 15 years
project management experience with management of emergency assessments and experience in bridge works an
added advantage. The Team Leader may be one of the engineering experts listed below.

*        Structural Engineer: a qualified engineer with BSc degree in bridge/structural Engineering and a minimum
         of 15 years relevant experience in similar project, at least five must be in the region.

*        Geotechnical Engineer: a qualified engineer with BSc degree in foundation engineering and a minimum of
         10 years relevant experience.

*        Hydraulic Engineer: a qualified engineer with BSc degree in Civil engineering or equivalent with minimum
         of 10 years relevant experience in similar projects.

                                                          90
*   Transport Economist: a qualified transport economist with Bachelor of Arts in Economics degree or
    equivalent with minimum of 10 years relevant experience;

*   Environmental Specialist: a qualified environmental specialist with Bachelor of Science degree or
    equivalent, in an appropriate field and with 10-years relevant experience in similar assignments.

*   Social Safeguard Specialist: a qualified social scientist or social safeguard expert with Bachelor of Science
    degree or equivalent, in an appropriate field and with 10-years relevant experience in similar assignments.

*   Senior Land Surveyor: Bachelor of Science degree (BSc) in Land Surveying or relevant discipline.
    Minimum experience shall be Ten (10) years, with a minimum specific experience of five (5) years in road
    projects. The candidate shall also be computer literate and fluent in the written, spoken and reading use of
    the English language.

*   Quantity surveyor: Bachelor of Science degree (BSc) in Civil Engineering or relevant discipline, and
    professionally registered. Minimum experience shall be eight (8) years, with specific experience in
    Building and Infrastructure Projects/Facilities Quantities. The candidate shall also be computer literate and
    fluent in the written, spoken and reading use of the English language.




                                                    91
ANNEX II: QUESTIONNAIRE
                                  IMO RAMP 2 INTERVENTION PROJECT

Dear Respondent,
Thank you for taking the time to complete the following survey. The purpose of this survey is to gain valuable insight
on proposed IMO RAMP RIVER CROSSING INTERVENTION PROJECT. This provides you the opportunity to
contribute to the environmental and social components of the project implementation.
NOTE:
Please read each question carefully. Your answers are completely confidential and will be included only in summaries
where individual answers cannot be identified. Unless otherwise instructed, please tick appropriate answer category
that best describes your opinion. It will take approximately 20 minutes to complete this questionnaire.

Settlement/Community:…Lot.No…………………../L.G.A:…….………………Date:…………..……

SECTION A: Household data
1.      Gender of Respondent:                 (a) Male          (b) Female
2.      Age:      (a) Below 18 yrs            (b) 18-45 yrs     (c) 46-65 yrs               (d) Above 66 yrs
3.      Marital Status: (a) Single (b) Married (d) Divorced/Separated (e) Widowed
4.      Occupation: (a) Famer (b) Daily Labourer (c) Trading & Shop Keeping (d) Artisans (e) Employed (salary)
        (f) Self Employed (g) Social Support (h) unemployed (i) Others specify……………………
5.      Residential Status: (a) Permanent Resident (b) Back Home (Returnee) (c) Non-Resident, Visiting
6.      Ethnic Group: (a) Igbo (b)Yoruba (c) Hausa (d) Ijaw ( e) Itsekiri (h) Others, specify………
7.      Religion:          (a) Christianity (b) Islam           (c) Traditional
8.      Relationship to Household Head (HH): (a) Self (b) Spouse (c) Child          (d) Parent (e) Other, specify…...
9.      Size of the HH ……………………………
No. of Adults (Above 18)                               Men                            Women
No. of Children (below 18)                             Boys                           Girls
10.     How long have you been living in this area?       (a) 0-2 yrs (b) 3-5 yrs (c) 6-9 yrs (d) 10 yrs and Above
11.     If non-resident, please state your actual location: …………….               (Location/LGA/State)
12.     Education:         (a) No formal education (b) Primary School            (c) Secondary School
        (d) Tertiary (Excluding University)            (e) University Graduate (f) University Post Graduate

Education of young household member
12.1 Does anyone in your household currently A            Yes                               b     No
attend school (If no, skip to 2)
12.2 What level of education are they? (Place             School Category                         Number
name)                                         A           Primary                           b     Junior High
                                              C           Senior High/ Tech/ Voc            d     Post-Secondary
12.3. How long does it take to get to school? A           <5 mins                           b     5-15 mins
(Note response to each school accessed)       C           15-30 mins                       d     30-60 mins
                                                   E      60+ mins
12.4. What method of transport is used to get to A        Foot                             b     Bicycle
school? (Note response to each school accessed) C         Mini bus                         d     Taxi
                                                   E      Private Car                      f     Okada
                                                   G      Tri-cycle
13.      Are you in anyway affected by the poor state of the River crossing in this community
         (a) yes            (b) no
14.      If question 11 is yes, how (a) damage to Agric/farmland        (b) Damage to building/property
                                                         92
      (c) loss of landed / Building property (d) Damage to household utensils/personal belonging
      (e) economic loss due to inability to access or operate means of livelihoods (f) others specify………
15.   Does the state of the River crossing prevent children from going to school?
      (a) Yes (b) No
16.   If question 15 is yes, how regular is the occurrence? (a) Often (b) frequently (c) rarely
SECTION B: Health Status
1.    Is your present state of health affected in any way by the state of the River crossing?
      (a) Yes             (b) No
2.    If yes, in what way? (a) Skin diseases (b) Cough (c) Catarrh (d) Malaria (e) Water-borne diseases (f) Other,
      Specify……………………
3.    Does the prevalence / occurrence of the disease(s) become severe during flood periods (a) Yes (b) No
4.    How do you manage your health conditions when sick? (a) Attend hospital/clinic (b) Buys drugs from nearby
      chemist (c) Traditional medicine (d) None (e) Others Specify………………………….
5.    If you do attend hospital/clinic, when last did you visit one?    (a) last six months (b) last one year  (c)
      last five years (d) more than five years ago (e) Never visited one.
6.    Do you think your health condition will be affected by the proposed intervention by IMO RAMP? (a) Yes
      (b) No
7.    If yes, how? (a) Contamination of ground water (b) Contamination of surface water (c) Provide breading site
      for disease vectors (d) Noise/air pollution (e) Others, specify:……………………………………
8.    Please        suggest     how        this     can      be       averted       during      construction  and
      implementation……………………………………………………………………………………….

SECTION C. Standard of Living / Socio-Economic Activities
1.    Assets
1.1 Do you have any of the following items
Item                             Quantity               Item                                    Quantity
a.       radio / tape recorder                          k. beds
b.       television                                     l. furniture set
c.       DVD player                                     m. fan
d.       telephone (land line)                          n. computer
e.       mobile phone                                   o. generator
f.       stove                                          p. mosquito nets
g.       fridge                                         q. insect screens
h.       hunting trap                                   r. other (specify)

1.2 What sort of transport does your family own
Item                                   Quantity           Item                                Quantity
a.      bicycle                                           f. car
b.      motorcycle/okada                                  g. truck
c.      canoe                                             h. taxi
d.      boat                                              i. bus
e.      tri-cycle                                         j. other (specify)

1.3 What mode of transport do you frequently use
Item                                  Quantity              Item                               Quantity
a.      bicycle                                             f. car
b.      motorcycle/okada                                    g. truck
c.      canoe                                               h. taxi

                                                       93
d.        boat                                                      i. bus
e.        tri-cycle                                                 j. other (specify)

1.4 What sort of housing does your household live in?
a. Construction material - Walls                Plastered mud             c. Number of rooms                    1-2
                                                Cement blocks                                                   3-4
                                                Other (specify)                                                 Other (specify)
b. Construction material - roofing              Corrugated roofing        d. Other structures on plot           Animal Pen
                                                Aluminium                                                       Granary
                                                Asbestos                                                        Shops
                                                Tile                                                            Kiosks
                                                Other (specify)                                                 Other (specify)
e. Construction material - floor                Earthen
                                                Concretes
                                                Tiles
                                                Other (specify)
f. Toilet Facility                              Pit latrine
                                                Water closet
                                                Toilet facility outside dwelling
                                                Pier latrine
                                                Other (specify)
                                                None
g. Tenure of housing                            Owned
                                                Rented
                                                Occupied rent free
                                                Other
h. Tenure of land                               Owned
                                                Rented
                                                Occupied rent free
                                                Lease hold
                                                Others specify
2.       Indicate household refuse disposal for solid waste? (Multiple options) (a) Depositing refuse at backyard of
         the house (b) Dumping in water body (c) Dumping in community refuse/garbage pit/dumpsite
         (d) Burning after gathering together (e) Waste collector         (f) Other specify………
2.0      Household Services
2.1      Rank in order of availability and usability the source(s) of lighting for the household? (please use 1, 2,...in
         hierarchical order with 1 indicating the most available and used source)
         (a) PHCN (b) Generator (c) Lantern (d) Candle (e) Palm (f) Torchlight (g) Wood (h) Kerosene (i) Gas
                                                              Oil Lamp Battery

2.2      Using the method in 2.1, indicate major source of energy for cooking?
         (a)     Fire (b) Coal    (c) Kerosene (d) Electricity (e)    Animal (f) Gas                (g)           Crop Others
         Wood                                                  dropping                             Residue/saw dust

3.0       Sources of Water
                                                for drinking                for cooking                 for bathing and washing
         Well                                   Yes          No            Yes              No          Yes            No
         Borehole                               Yes          No            Yes              No          Yes            No
         Water pump                             Yes          No            Yes              No          Yes            No
                                                               94
        Community tap                      Yes        No         Yes            No         Yes             No
        Piped water outside dwelling       Yes        No         Yes            No         Yes             No
        River                              Yes        No         Yes            No         Yes             No
        h. Rain harvesting                 Yes        No         Yes            No         Yes             No
        i.   Water vendor                  Yes        No         Yes            No         Yes             No
        j.   Tanked water                  Yes        No         Yes            No         Yes             No
        Other (specify)                    Yes        No         Yes            No         Yes             No
4.0     Income
        State your main income per month                N
4.1     Remittances
        1. Does anyone in the family who lives elsewhere send money to you?                      1   Yes    2    No

      2. If yes, how much (per month)                N
5.0    Other Income
      1. Do you have other income streams                 Yes                            No
      2. If yes, please specify the amount?               N
6.    Total Income
      1 What is the total household monthly income (all activities)?                      N
7.    In your opinion, how has the standard of living of your household changed over the previous three years?
      (a) Same (b) Better (c) Worse
8.    Is the option in 7 propelled by the poor state of the River crossing       (a) Yes (b) No
9.    If 8 is yes, do you think the proposed intervention will improve the situation? (a) Yes     (b) No
10.    If 9 is yes specify how the project will improve the situation ………………………
11.   How do you ensure gender equity in the community? (a) Women are elected in public office (b) Females are
      given equal opportunity and access to education and employment (c) Quotas on genders are ensures in
      leadership of community-based organizations (d) Others specify…………………………………………...
SECTION D: Resources/ Cultural Property
1.    Please indicate the environmental problems which your settlement/community experiences and whose cause
      can be linked to the poor state of the River crossing? (a) Soil infertility (b) Poor drainage system (c) Bad
      road (d) Bad lands (e) environmental degradation (f) Degraded land (i) Destruction of infrastructures (j)
      Others (specify) …………………………..
2.    Please indicate the environmental problems which your settlement/community would likely experience and
      whose cause can be linked to the proposed intervention project during construction? (a) Soil infertility
      (b) Poor drainage system (c) Bad road (d) Low visibility (e) Erosion Problems (f) Flooding
      (g) Environmental degradation         (g) Destruction of infrastructures (h) encroachment of land properties
      (i) Pollution (air, surface water, ground water, noise) (j) Others (specify) ………………………….
3.    Please indicate the environmental problems which your settlement/community would likely experience and
      whose cause can be linked to the proposed intervention project during operation? (a) Soil infertility
      (b) Poor drainage system (c) Bad road (d) Low visibility (e) Erosion Problems (f) Flooding
      (g) Environmental degradation (h) Destruction of infrastructures (i) encroachment of land properties
      (j) Pollution (air, surface water, ground water, noise) (k) Others (specify) …………………………..
4.    Do you think the proposed intervention project will affect any valued resource/cultural/archaeological
      property in your area?       (a) Yes (b) No
5.    If yes mention the name(s) of the valued resource/cultural/archaeological property …………………………
6.    How will valued resource/cultural/archaeological property be affected? (a) Displacement of such valued
      cultural properties (b) Vandalisation of sacred items/locations (c) Possible theft of sacred/archaeological
      items (d) Others, specify: ……………………………
SECTION E: Intervention Project Activities Impact Evaluation
      Are you aware of the proposed intervention by IMO RAMP (a) Yes (b) No


                                                       95
        If yes, from which source (a) Community meetings (b) Media (TV, Radio, Newspaper, Internet)
        (c) Others specify…………………………….
        Do you think the project can cause restiveness in your community? (a) Yes (b) No
        If 3 is yes how will the proposed intervention result in restiveness? (a) Disrespect of norms and culture by
        contractors (b) loss of farmland / Property (c) Possible theft of sacred/archaeological items
        (d) local people not employed during construction       (e) Others, specify: ……………………………
5.      How will the proposed intervention project impact on your livelihood and environment?
        Positive impacts                                             Negative impacts
        (a)
        (b)
        (c)
        (d)
        (e)
        (f)
6.      Can you name some of the animals and other habitat at the River crossing site that may be affected by the
        proposed                                          intervention                                          project?
        …………………………………………………………………………………………
7.      What do you expect from the activities of IMO RAMP intervention? (a) employment of Locals during
        construction (b) compensation for those whose properties will be affected (c) capacity building for
        maintenance during implementation (d) community input into final engineering design (e)Others please
        specify……………………..
8.      Are there any other issue(s) of concern as regards the intervention project in your area, please state clearly?

Section F: Rural Mobility and Expectation from the Project
1.      Is there any existing River crossing that links this community to others? (a) Yes (b) No (c) I d on’t know
2.      Which mode of transport do you use to access river crossings? (a) Buses (b) Bicycle (c) Motorcycle(d)
        Pick-up Vans (e) Timber Logging Truck (f) others, specify...............................
3.      How efficient is the mobility on the road? (a) very good (b) Good (c) Fair (d) Poor (e) Very Poor
4.      What are the factors influencing the mobility efficiency? Write as many as applicable
5.      In what way would you benefit most if a River crossing is constructed via this community? (a) Enhanced
        mobility of people and farm produce (b) Improvement in commercial activities (c) Enhancement of Social
        activities (d) Others, specify............................................................
6.      Would you allow it if the River crossing construction affect your landed property or part thereof? (a) Yes
        (b) No
7.      How would you like to be compensated if your property is affected? (a) Cash (b) To be given another land
        (c) To be provided with another building (d) Cash plus another land/building (e) Others,
        specify...........................................................................................................
        8.            What other things do you want Government to do for your community?
        ........................................................................
9.      Who do you think should negotiate with Government on behalf of your community? (a) Traditional Chief (b)
        Community Chairman (c) Youth Leader (d) Religious Leader (E) Others
        specify..........................................................................




                                                           96
     ANNEX III: MINUTES OF THE STAKEHOLDERS MEETING

     LOT 1 - ORIE MBIERI-UMUOMUMU MBIERI (IKEDURU/MBATOLI)

Items                        Description
Name of Stakeholder:         General Stakeholder Consultation
Date:                        12/04/2019
Venue:                       Community Open Ground, Umuomumu Community
Language                  of Pidgin-English, English and Igbo
Communication:
In attendance                 •   The traditional leader, Umuomumu Community;
                              •   The Secretary Umuomumu Community;
                              •   The Youth President, Umuomumu community;
                              •   The Women Leader, Umuomumu Community;
                              •   Imo RAMP environmental safeguard officer;
                              •   Imo RAMP social safeguard officer
                              •   The ESMP consultant team;
                              •   Community Members.
                             Attendance (Annex III) Photo (Annex V)
Opening Remarks              The purpose of the meeting was clearly introduced by the environmental and social safeguard officers.
ESMP            Consultant’s The ESMP consultant explained in details the need for the ESMP in preparation for the project execution. He noted
Remarks                      that soil, water and air samples would be collected all around the community to assess the current state of the
                             environment. These, according to him, would also serve as the baseline data to assess the impact of the intervention
                             project on the environment in the future He also emphasized the need for public consultation which was designed to
                             elicit from the residents and their perception of the proposed project. He finally thanked the members of the
                             communities for their expected cooperation.
Issues Raised                     •    The ESMP team was welcomed by the Community’s leader who expressed his joy about the proposed
                                       River crossing across the Okatankwo stream.
                                  •    He noted that this will also facilitate the easy movement of agricultural product cultivated in the
                                       community to the neighbouring markets thereby improving the living standards of the people
                                  •    When asked about their (community’s) knowledge of the RAMP 2, greater percentage (including the
                                       traditional leader of the Umuomumu Residents Association) indicated that they were not aware of the
                                       existence of the RAMP 2 and its proposed intervention in their community.
                                  •    Several/past communal and individual efforts to improve accessibility were enumerated by them;
                                  •    Some of the locals expressed their skepticism about the seriousness of the proposed RAMP 2
                                       intervention owing to their past experiences; while some of the participants noted that the visit was their
                                       first time knowing about the RAMP 2;
                                  •    Mrs Rose Akudie from the women group expressed her joy over the proposed project as it is a sign that
                                       more development is coming to their community
                                  •    Chief C.G. Nwaonu from the Elders group requested that the flow of the stream should be enhanced
                                       during the construction of the River crossing as it is currently silted.
                                  •    Chief Oliver Eke from the Elders group asked for clarification on the part the members of the community
                                       are expected to play in the project
                                  •    The community leader particularly the Chairman wants the RAMP 2 to carry them along in the process
                                       of executing the project; They do not want the project to be hijacked by politicians;
                                  •    In all, they expressed their happiness about the intervention and look forward to seeing contractors on
                                       site.
                                       Cultural and Social Issues
                                  •    Inhabitants are mainly farmers who cultivate cassava and yam;
                                  •    They also engage in the cultivation of economic trees especially oil palm and cashew trees


                                                                     97
                                 •   On culture and tradition, it was noted that there is no archaeological site/ shrine located within and
                                     around the project site as the people are now majorly Christians;
                                 •   It was also mentioned that contractors/visitors are not allowed to make advances to married women in
                                     the community.
Question\Comment                 •   Some of the stakeholders asked what their lots would be should their farms and other properties get
                                     affected by the proposed intervention.
                                 •   The youth, especially the artisans among them enquired if they would be employed by the contractors
                                 •   Businessmen asked if they can supply construction material to the contractors
Response               •          Explanations were offered by the ESMP team:
                                • It was explained to them that another team of consultant known as Resettlement Action Plan (RAP) would
                                    be coming to access and value structures that would be affected by the proposed intervention based on the
                                    designed engineering drawing.
                                • It was also indicated that compensation would be paid to people whose assets and livelihoods would be
                                    affected by the project implementation.
                                • The youth in the community were assured that they would first be considered for employment before
                                    skilled and unskilled labour will be sought from other places

Community Needs                 • Training in engineering skill
                                • Public schools;
                                • Good Roads; and
                                • Comprehensive Health Facility.
Closing Remark              The people were eager to see contractors mobilized to site.
                            Community elders and Chairman expressed their joy and thanked the ESMP team while reaffirming their readiness
                            to support the proposed intervention to a logical conclusion.


     LOT 4: UMUOKPARA OFEIYI-UMUOLECHE (OKIGWE)

     Minutes of the Stakeholders Meeting Held at the Umuezedike Community Square
Items                         Description
Name of Stakeholder:          General Stakeholder Consultation
Date:                         12/04/2019
Venue:                        Community Open Ground, Umuezedike Community
Language                   of Pidgin-English, English and Igbo
Communication:
In attendance          •          The Community leader, Umuezedike Community;

                       •          The Secretary Umuezedike Community;
                                •        The Youth President, Umuezedike Community;
                                •        The Women Leader, Umuezedike Community;
                                •        Imo RAMP environmental safeguard officer;
                                •        Imo RAMP social safeguard officer
                                •        The ESMP consultant team;
                                •        Community Members.
                            Attendance (Annex III) Photo (Annex V)
Opening Remarks             The purpose of the meeting was clearly introduced by the environmental and social safeguard officers.

ESMP          Consultant’s The ESMP consultant explained in details the need for the ESMP in preparation for the project execution. He noted that
Remarks                    soil, water and air samples would be collected all around the community to assess the current state of the environment.
                           These, according to him, would also serve as the baseline data to assess the impact of the intervention project on the
                           environment in the future He also emphasized the need for public consultation which was designed to elicit from the

                                                                   98
                   residents and their perception of the proposed project. He finally thanked the members of the communities for their expected
                   cooperation.


Issues Raised         •   The ESMP team was welcomed by the Community’s leader (Chief Samuel Udoji) who expressed his joy about
                          the proposed River crossing.
                      • He noted that this will also facilitate the easy movement of agricultural product cultivated in the community to
                          the neighbouring markets thereby improving the living standards of the people
                      • When asked about their (community’s) knowledge of the RAMP 2, greater percentage (including the traditional
                          leader of the Umuezedike community) indicated that they were not aware of the existence of the RAMP 2 and its
                          proposed intervention in their community.
                      • Mr Sunday Ugochukwu from the Elders group noted that Umuezedike is a peaceful community. He promised
                          that the lives and machinery of the contractor are safe in the community.
                      • He also promised to provide accommodation to the contractors when they come
                      • The community leader particularly the Chairman wants the RAMP 2 to carry them along in the process of
                          executing the project; They do not want the project to be hijacked by politicians;
                      • In all, they expressed their happiness about the intervention and look forward to seeing contractors on site.
                      Cultural and Social Issues
                      • Inhabitants are mainly farmers who cultivate cassava and yam;
                      • They also engage in the cultivation of economic trees especially oil palm and cashew trees
                      • On culture and tradition, it was noted that there is no archaeological site/ shrine located within and around the
                          project site as the people are now majorly Christians;

Question\Comment      •    Some of the stakeholders asked what their lots would be should their farms and other properties get affected by
                           the proposed intervention.
                      • Mrs Theresa Owina from the women group enquired if the proposed intervention is a bridge or a culvert
                      • The youth, especially the artisans among them enquired if they would be employed by the contractors
                      • Mr Ncheghari Nnoham from the youth group asked for more River crossing projects for the community.
                      • Mrs Angela Umunna from the women group pleaded that as part of the project, RAMP should help complete
                           their health centre and improve their school
                      • It was also mentioned that contractors/visitors are not allowed to make advances to married women in the
                           community.
Response           Explanations were offered by the ESMP team:
                      • It was explained to them that another team of consultant known as Resettlement Action Plan (RAP) would be
                           coming to access and value structures that would be affected by the proposed intervention based on the designed
                           engineering drawing.
                      • It was also indicated that compensation would be paid to people whose building would be affected by the project
                           implementation.
                      • The ESMP consultant gave the dimension of the RC as 20 meters long and 8 meters wide. He also indicated that
                           there will be an approach road which will be 7.3 meters wide with side drains (750X750) on both sides of the
                           road
                      • The youth in the community were assured that they would first be considered for employment before skilled and
                           unskilled labour will be sought from other places
                      • The consultant also explained to the beneficiaries that the selected priority roads are the ones considered at this
                           phase and others will be considered in subsequent phases. Their request will however be communicated the SPIU
                      • It was also noted that the RAMP project is focused essentially on rural accessibility (roads and River crossings).
                           The community members were therefore advised to visit the office of the World Bank supported CSDP
                           programme for assistance on project related to health, school among others
                      • On the issue of making advances to married women and underage girls, the consultant assured the community
                           members that their concerns have been documented and will be communicated to the contractor and other visitors
Community Needs       • Amagu-Umulebe bridge;
                      • Okorobi-Umuju-Amaikpa bridge
                      • Good Roads;
                      • School; and
                      • Comprehensive Health Facility.

                                                           99
Closing Remark                   •   The people were eager to see contractors mobilized to site.
                                 •   Community elders and Chairman expressed their joy and thanked the ESMP team while reaffirming their readiness
                                     to support the proposed intervention to a logical conclusion.



     LOT 2: UZURUNAMU-OKWUDO MGBIDI (ORU EAST/ORU WEST/ORSU)

     Minutes of the Stakeholders Meeting Held at the Uzuruanamu Community Open Ground

Items                        Description
Name of Stakeholder:         General Stakeholder Consultation
Date:                        13/04/2019
Venue:                       Community Open Ground, Uzuruanamu Autonomous Community
Language                  of Pidgin-English, English and Igbo
Communication:
In attendance                   • The PG Uzuruanamu Autonomous Community;
                                • The Secretary Uzuruanamu Autonomous Community;
                                • The Youth President, Uzuruanamu Autonomous Community;
                                • The Women Leader, Uzuruanamu Autonomous Community;
                                • Imo RAMP environmental safeguard officer;
                                • Imo RAMP social safeguard officer
                                • The ESMP consultant team;
                                • Community Members.
                                Attendance (Annex III) Photo (Annex V)
Opening Remarks              The purpose of the meeting was clearly introduced by the environmental and social safeguard officers.

ESMP            Consultant’s The ESMP consultant explained in details the need for the ESMP in preparation for the project execution. He noted
Remarks                      that soil, water and air samples would be collected all around the community to assess the current state of the
                             environment. These, according to him, would also serve as the baseline data to assess the impact of the intervention
                             project on the environment in the future He also emphasized the need for public consultation which was designed to
                             elicit from the residents and their perception of the proposed project. He finally thanked the members of the
                             communities for their expected cooperation.
Issues Raised           •           The ESMP team was welcomed by the Community’s President General (Chief Sunday Umunnah) who
                                    expressed his joy about the proposed River crossing.
                                • He noted that the bridge will improve the commercial and socio-economic life of the people
                                • When asked about their (community’s) knowledge of the RAMP 2, greater percentage (including the
                                   traditional leader of the Uzuruanamu Residents Association) indicated that they were not aware of the
                                   existence of the RAMP 2 and its proposed intervention in their community.
                                • It was indicated that the community council constructed a bridge over the River in the past.
                                • In all, they expressed their happiness about the intervention and look forward to seeing the contractors on site.
                             Cultural and Social Issues
                                • Inhabitants are mainly farmers who cultivate cassava and yam;
                                • They also engage in the cultivation of economic trees especially oil palm and cashew trees
                                • On their culture and tradition, it was noted that there is a shrine located within and around the project
                                • The Obana River is a deity where no fishing is allowed.
                                • The Boa is also a deity. They are harmless and should not be killed (see picture in Plate 4.3 and Annex XX
                                   and text in Annex XX)
                                • Sexual relationship with underage or unmarried girls especially teenagers is not allowed. Any girl who gets
                                   pregnant before the Fattening process would be ostracised for life and her family shamed.
                                • Nobody is expected to take the water from the Obana River home on small Orie days




                                                                     100
Question\Comment       •            Some of the stakeholders asked what their lots would be should their farms and other properties get affected
                                    by the proposed intervention.
                       •            The nature of the intervention was also enquired. Is it a bridge or a culvert? What is its capacity? Is it a single
                                    lane or dual carriage river crossing?
                       •            Will the road be constructed too?
Response                        •           Explanations were offered by the ESMP team:
                                •           On the issue of Obana River and the Boa, the community members were assured that their concerns
                                            will be documented and communicated to the contractor and other consultants
                                •           It was explained to them that another team of consultant will prepare a Resettlement Action Plan
                                            (RAP) to access and value structures and all other cultural activities that would be affected by the
                                            proposed intervention based on the designed engineering drawing.
                                •           They were assured that cultural areas are special in all World Bank projects and will be given extra
                                            attention. The consultant further explained that the World Bank OP 4.11 addresses such issues of
                                            physical and cultural resources and a PCR plan is provided in Annex XII
                                •           With regards to making advances to women and underage girls, the community members were assured
                                            that their views and concerns will be recorded and communicated to the contractors and other
                                            consultants that will be visiting
                                •           On the issue of water use, the consultant indicated that this will be documented and conveyed to the
                                            contractor (Section 5.2.2.2 and section A9 of the ESMP Matrix)
                                •           The ESMP consultant gave the dimension of the RC as 20 meters long and 8 meters wide. He also
                                            indicated that there will be an approach road which will be 7.3 meters wide with side drains
                                            (750X750) on both sides of the road
Community Needs                 •           A good road to access the bridge
                                •           Engagement of youths of the community
                                •           Establishment of skill acquisition centres
Closing Remark                  •           The people were eager to see contractors mobilized to site.
                                •           Community elders and Chairman expressed their joy and thanked the ESMP team while reaffirming
                                            their readiness to support the proposed intervention to a logical conclusion.




     LOT 3: UGBELE-BSC (IDEATO SOUTH LGA)

     Minutes of the Stakeholders Meeting Held at the Obinugwu Town hall, Ugbelle

Items                         Description
Name of Stakeholder:          General Stakeholder Consultation
Date:                         13/04/2019
Venue:                        Community Town hall, Obinugwu
Language                   of Pidgin-English, English and Igbo
Communication:
In attendance                     •   The community leader, Obinugwu Community;
                                  •   the Secretary Obinugwu Community;
                                  •   The Youth President, Obinugwu Community,
                                  •   The Women Leader, Obinugwu Community,
                                  •   Imo RAMP environmental safeguard officer,
                                  •   Imo RAMP social safeguard officer,
                                  •   The ESMP consultant team,
                                  •   Community Members,
                             Attendance (Annex III) Photo (Annex V)


                                                                       101
Opening Remarks              The purpose of the meeting was clearly introduced by the environmental and social safeguard officers.
ESMP            Consultant’s The ESMP consultant explained in details the need for the ESMP in preparation for the project execution. He noted
Remarks                      that soil, water and air samples would be collected all around the community to assess the current state of the
                             environment. These, according to him, would also serve as the baseline data to assess the impact of the intervention
                             project on the environment in the future He also emphasized the need for public consultation which was designed to
                             elicit from the residents and their perception of the proposed project. He finally thanked the members of the
                             communities for their expected cooperation.
Issues Raised                 • The ESMP team was welcomed by the Obinugwu traditional leader (High Chief David Aliakor) who expressed
                                his joy about the proposed rehabilitation of the Urashi River crossing.

                              • He noted that this will also facilitate the easy movement of agricultural product cultivated in the community to
                                the neighbouring markets thereby improving the living standards of the people

                              • When asked about their (community’s) knowledge of the RAMP 2, greater percentage (including the traditional
                                leader of the Obinugwu community) indicated that they were not aware of the existence of the RAMP 2 and its
                                proposed intervention in their community.

                              • Mr Sunday Ugochukwu from the Elders group noted that Obinugwu is a peaceful community. He promised that
                                the lives and properties of the contractor are safe in the community.

                              • The community leader wants the RAMP 2 to carry them along in the process of executing the project; They do
                                not want the project to be hijacked by politicians;

                              • In all, they expressed their happiness about the intervention and look forward to seeing contractors on site.
                             Cultural and Social Issues
                                • Inhabitants are mainly farmers who cultivate cassava and yam;
                                • They also engage in the cultivation of economic trees especially oil palm and cashew trees
                                • On culture and tradition, it was noted that there is no archaeological site/ shrine located within and around
                                      the project site as the people are now majorly Christians;

Question\Comment         •           Some of the stakeholders asked what their lots would be should their farms and other properties get affected
                                     by the proposed intervention
                         •           It was also mentioned that contractors/visitors are not allowed to make advances to married women in the
                                     community.
Response                         •        Explanations were offered by the ESMP team:
                                 •        It was explained to them that another team of consultant known as Resettlement Action Plan (RAP)
                                          would be coming to access and value structures that would be affected by the proposed intervention
                                          based on the designed engineering drawing.
                                 •        It was also indicated that compensation would be paid to people whose building would be affected
                                          by the project implementation.
                                 •        With regards to making advances to women and underage girls, the community members were
                                          assured that their views and concerns will be recorded and communicated to the contractors and
                                          other consultants that will be visiting
Community Needs          •         Good road accessibility

                         •           Standard road crossing that will stand the test of time
Closing Remark           •           The people were eager to see contractors mobilized to site.

                         •           Community elders and youths expressed their joy and thanked the ESMP team while reaffirming their
                                     readiness to support the proposed intervention to a logical conclusion.




                                                                       102
      LOT 1: UMUDURU EMGHARA-OKPUALA ANARA (ISIALA MBANO/EHIME
      MBANO)

      Minutes of the Stakeholders Meeting Held at the Okpuala Community Open Ground

Items                        Description
Name of Stakeholder:         General Stakeholder Consultation
Date:                        13/04/2019
Venue:                       Community Open Ground, Okpuala Community
Language                  of Pidgin-English, English and Igbo
Communication:
In attendance                 •   The PG Okpuala Community;
                              •   The Secretary Okpuala Community;
                              •   The Youth President, Okpuala Community;
                              •   The Women Leader, Okpuala Community;
                              •   Imo RAMP environmental safeguard officer;
                              •   Imo RAMP social safeguard officer
                              •   The ESMP consultant team;
                              •   Community Members.
                           Attendance (Annex III) Photo (Annex V)
Opening Remarks            The purpose of the meeting was clearly introduced by the environmental and social safeguard officers.
ESMP          Consultant’s The ESMP consultant explained in details the need for the ESMP in preparation for the project execution. He noted
Remarks                    that soil, water and air samples would be collected all around the community to assess the current state of the
                           environment. These, according to him, would also serve as the baseline data to assess the impact of the intervention
                           project on the environment in the future He also emphasized the need for public consultation which was designed to
                           elicit from the residents and their perception of the proposed project. He finally thanked the members of the
                           communities for their expected cooperation. The issues raised for discussion are:
                               • The building of culverts on Okpuala road which has dilapidated over the years
                               • The co-operation of the community in seeing that the project is carried out without any hindrance or
                                   molestation by the community members.
                               • assurance that the community welcomes the initiative by RAMP for the benefit of the entire community.
                               • the project is only concerned with rehabilitation of the culverts and not construction of Okpuala road
Issues Raised                  • The ESMP team was welcomed by the Community’s President General who expressed his joy about the
                                   proposed River crossing.
                               • He noted that the bridge will improve the commercial and socio-economic life of the people
                               • When asked about their (community’s) knowledge of the RAMP 2, greater percentage (including the
                                   traditional leader of the Okpuala Residents Association) indicated that they were not aware of the existence
                                   of the RAMP 2 and its proposed intervention in their community.
                               • In all, they expressed their happiness about the intervention and look forward to seeing the contractors on site.

Question\Comment             • Some of the stakeholders asked what their lots would be should their farms and other properties get affected by
                               the proposed intervention.
                             • The nature of the intervention was also enquired. Is it a bridge or a culvert? What is its capacity? Is it a single
                               lane or dual carriage river crossing?
                             • Will the road be constructed too?
Response                          •        Explanations were offered by the ESMP team:
                                  •        It was explained to them that another team of consultant known as Resettlement Action Plan (RAP)
                                           would be coming to access and value structures that would be affected by the proposed intervention
                                           based on the designed engineering drawing.

                                                                     103
                                 •         It was also indicated that compensation would be paid to people whose building would be affected
                                           by the project implementation.
                                 •         It was also noted that the RAMP project is focused essentially on rural accessibility (roads and River
                                           crossings).
                                 •         The ESMP consultant gave the dimension of the RC as 20 meters long and 8 meters wide. He also
                                           indicated that there will be an approach road which will be 7.3 meters wide with side drains
                                           (750X750) on both sides of the road
Community Needs                  •         A good road to access the bridge
                                 •         Engagement of youths of the community
                                 •         Establishment of skill acquisition centres
Closing Remark               The people were eager to see contractors mobilized to site.
                             Community elders and Chairman expressed their joy and thanked the ESMP team while reaffirming their readiness
                             to support the proposed intervention to a logical conclusion.



        LOT 4: UMUOKPARA OFEIYI-UMUOLECHE (OKIGWE)

        Minutes of the Stakeholders Meeting Held at the Umuoleche Community Open Ground

Items                    Description
Name of Stakeholder:     General Stakeholder Consultation

Date:                    13/04/2019
Venue:                   Community Open Ground, Umuoleche Community
Language               of Pidgin-English, English and Igbo
Communication:
In attendance                •       The community leader, Umuoleche Community;
                             •       The Secretary Umuoleche Community;
                             •       The Youth President, Umuoleche Community;
                             •       The Women Leader, Umuoleche Community;
                             •       Imo RAMP environmental safeguard officer;
                             •       Imo RAMP social safeguard officer
                             •       The ESMP consultant team;
                             •       Community Members.
                             •       Attendance (Annex III) Photo (Annex V)
Opening Remarks        The purpose of the meeting was clearly introduced by the environmental and social safeguard officers.
ESMP      Consultant’s The ESMP consultant explained in details the need for the ESMP in preparation for the project execution. He noted that
Remarks                soil, water and air samples would be collected all around the community to assess the current state of the environment.
                       These, according to him, would also serve as the baseline data to assess the impact of the intervention project on the
                       environment in the future He also emphasized the need for public consultation which was designed to elicit from the
                       residents and their perception of the proposed project. He finally thanked the members of the communities for their
                       expected cooperation.
Issues Raised             • The people assured them that they do not kill human beings neither are they hostile to visitors.
                         • The village informed them that they do not desire to have any of them turn to thieves or armed robbers. The river is
                           known as EFE river; it has no taboo or evil effect on anyone.
                         • Efe river is one that does not harbour shrine or deity.
                         • The village UMUOLOCHE, therefore desire and ask for your assistance to give us a viable bridge.
                         • There are no armed robbers in this village.


                                                                    104
                    • They assured the ESMP team that there will be no obstruction in term of the construction bridges, roads and
                      electricity.
                    • The community will help to provide security for the builders and otherwise to ensure that the work progresses.
                    • It is a taboo for a man to force or rape a woman in the village.
Question\Comment    • Some of the stakeholders asked what their lots would be should their farms and other properties get affected by the
                      proposed intervention.
                    • The nature of the intervention was also enquired. Is it a bridge or a culvert? What is its capacity? Is it a single lane or
                      dual carriage river crossing?
                    • Will be road be constructed too?
Response            Explanations were offered by the ESMP team:

                    • It was explained to them that another team of consultant known as Resettlement Action Plan (RAP) would be
                      coming to access and value structures that would be affected by the proposed intervention based on the designed
                      engineering drawing.
                    • It was also indicated that compensation would be paid to people whose building would be affected by the project
                      implementation.
                    • The ESMP consultant gave the dimension of the RC as 20 meters long and 8 meters wide. He also indicated that
                      there will be an approach road which will be 7.3 meters wide with side drains (750X750) on both sides of the road.
Community Needs •        A good road to access the bridge
                •        Engagement of youths of the community
                •        Establishment of skill acquisition centres
Closing Remark
                •         Community elders and Chairman expressed their joy and thanked the ESMP team while reaffirming their readiness
                          to support the proposed intervention to a logical conclusion.




                                                                  105
ANNEX IV: STAKEHOLDER MEETING ATTENDANCE




                                           106
ANNEX V: LIST OF THE PERSONS MET

S/N   NAME                     POSITION                                    PHONE NO
1     Mr Okpara Patrick        P.G. Umucheke Autonomous Community          08033815692
2     Mr Ibeke Edwin           Sec General Umucheke Autonomous Community   07061690502
3     Mr Okpara James          Community member                            07031840848
4     Mr Melody Obi            Community member                            08068149685
5     Hon Boniface Ugochukwu   Umuobom community member                    08030799637
6     Mr Fredman Mbama         Okwudor community member                    08137419091
7     Mr Njoku Emmanuel        Umueze autonomous community member          08060080242
8     Mr Benson Okpara         Umueze autonomous community member          08038667669
9     Mr Chibike Okonkwo       Okwudor community member                    08107847953
10    Mr Micheal Amoku         Okwudor community member                    09038239905
11    Mr Christian Ukaga       Umueziogwu community member                 08067176544
12    Mr Samuel Akujobi        Uzagba community member                     08133906249
13    Mr Uzoma Akujobi         Uzagba community member                     08177242644
14    Mr Ndubuisi Akakuru      Uzagba community member                     N/A
15    Mr Uchenna Akujobi       Umueziogwu community member                 07031885563
16    Mr Ndubuisi Ama          Umueziogwu community member                 08136590269




                                            107
ANNEX VI: STAKEHOLDER CONSULTATION

QUESTIONNAIRE ADMINISTRATION, KII AND FGD
LOT 1 & 2                                            LOT 3 & 4




CROSS-SECTION OF THE CONSULTATION AT ORIE-MBIERI – UMUOMUMU MBIERI




CROSS-SECTION OF CONSULTATION AT UGBELE – BSC ROAD




CROSS-SECTION OF CONSULTATION AT AMAGU-UMUNEBE

                                   108
CROSS-SECTION OF CONSULTATION AT UZUNANMU COMMUNITY, MGBIDI




CROSS-SECTION OF CONSULTATION AT UMUOKPARA OFEIYI-UMUOLOCHE




CROSS-SECTION OF CONSULTATION AT UMUDURUEMAGHARA-OKPARA




                                  109
ANNEX VII: CODE OF CONDUCT TO PREVENT GENDER BASED VIOLENCE
DURING THIS PROJECT
         Company Code of Conduct on Preventing Gender Based Violence (GBV) and Violence Against Children (VAC)

The company……….. is committed to creating and maintaining an environment in which gender-based violence (GBV) and violence
against children (VAC) have no place, and where they will not be tolerated by any employee, associate, or representative of the company.
Therefore, in order to ensure that all those engaged in the project are aware of this commitment, and in order to prevent, be aware of, and
respond to any allegations of GBV and VAC, the company commits to the following core principles and minimum standards of behaviour
that will apply to all company employees, associates, and representatives including sub-contractors, without exception:

    •          The company—and therefore all employees, associates, and representatives—commit to treating women, children (persons
               under the age of 18), and men with respect regardless of race, colour, language, religion, political or other opinion, national,
               ethnic or social origin, property, disability, birth or other status. Acts of GBV and VAC are in violation of this commitment.
    •          Demeaning, threatening, harassing, abusive, culturally inappropriate, or sexually provocative language and behaviour are
               prohibited among all company employees, associates, and its representatives.
    •          Acts of GBV or VAC constitute gross misconduct and are therefore grounds for sanctions, which may include penalties
               and/or termination of employment. All forms of GBV and VAC, including grooming are unacceptable, regardless of whether
               they take place on the work site, the work site surroundings, at worker’s camps or at worker’s homes.
    •          In addition to company sanctions, legal prosecution of those who commit acts of GBV or VAC will be pursued if appropriate.
    •          Sexual contact or activity with children under 18—including through digital media—is prohibited. Mistaken belief regarding
               the age of a child is not a defence. Consent from the child is also not a defence or excuse.
    •          Sexual favours—for instance, making promises or favourable treatment dependent on sexual acts—or other forms of
               humiliating, degrading or exploitative behaviour are prohibited.
    •          Unless there is full consent1 by all parties involved in the sexual act, sexual interactions between the company’s employees
               (at any level) and members of the communities surrounding the work place are prohibited. This includes relationships
               involving the withholding/promise of actual provision of benefit (monetary or non-monetary) to community members in
               exchange for sex—such sexual activity is considered “non-consensual�? within the scope of this Code.
    •          All employees, including volunteers and sub-contractors are highly encouraged to report suspected or actual acts of GBV
               and/or VAC by a fellow worker, whether in the same company or not. Reports must be made in accordance with GBV and
               VAC Allegation Procedures.
    •          Managers are required to report suspected or actual acts of GBV and/or VAC as they have a responsibility to uphold
               company commitments and hold their direct reports responsible.
To ensure that the above principles are implemented effectively the company commits to ensuring that:

    •          All managers sign the ‘Manager’s Code of Conduct’ detailing their responsibilities for implementing the company’s
               commitments and enforcing the responsibilities in the ‘Individual Code of Conduct’.
    •          All employees sign the project’s ‘Individual Code of Conduct’ confirming their agreement not to engage in activities
               resulting in GBV or VAC.
    •          Displaying the Company and Individual Codes of Conduct prominently and in clear view at workers’ camps, offices, and
               in in public areas of the work space. Examples of areas include waiting, rest and lobby areas of sites, canteen areas, health
               clinics.
    •          Ensure that posted and distributed copies of the Company and Individual Codes of Conduct are translated into the
               appropriate language of use in the work site areas as well as for any international staff in their native language.
    •          An appropriate person is nominated as the company’s ‘Focal Point’ for addressing GBV and VAC issues, including
               representing the company on the GBV and VAC Compliance Team (GCCT) which is comprised of representatives from
               the client, contractor(s), the supervision consultant, and local service provider(s).
    •          Ensuring that an effective Action Plan is developed in consultation with the GCCT which includes as a minimum:
               1.          GBV and VAC Allegation Procedure to report GBV and VAC issues through the project Grievance Redress
                           Mechanism (GRM);
               2.          Accountability Measures to protect confidentiality of all involved; and,
               3.          Response Protocol applicable to GBV and VAC survivors and perpetrators.



1 Consent is defined as the informed choice underlying an individual’s free and voluntary intention, acceptance or agreement to do some thing.
No consent can be found when such acceptance or agreement is obtained through the use of threats, force or other forms of coercion, abduction,
fraud, deception, or misrepresentation. In accordance with the United Nations Convention on the Rights of the Child, the World Bank considers
that consent cannot be given by children under the age of 18, even in the event that national legislation of the country into which the Code of
Conduct is introduced has a lower age. Mistaken belief regarding the age of the child and consent from the child is not a defence.

                                                                      110
    •          That the company effectively implements the Action Plan, providing feedback to the GCCT for improvements and updates
               as appropriate.
     •         All employees attend an induction training course prior to commencing work on site to ensure they are familiar with the
               company’s commitments and the project’s GBV and VAC Codes of Conduct.
     •         All employees attend a mandatory training course once a month for the duration of the contract starting from the first
               induction training prior to commencement of work to reinforce the understanding of the project’s GBV and VAC Code of
               Conduct.
I do hereby acknowledge that I have read the foregoing Company Code of Conduct, and on behalf of the company agree to comply with
the standards contained therein. I understand my role and responsibilities to prevent and respond to GBV and VAC. I understand that any
action inconsistent with this Company Code of Conduct or failure to take action mandated by this Company Code of Conduct may result
in disciplinary action.

                    Company name:           _________________________
                    Signature:             _________________________
                    Printed Name:          _________________________
                    Title:                 _________________________
                    Date:                  _________________________


                Manager’s Code of Conduct on Preventing Gender Based Violence and Violence Against Children

Managers at all levels have particular responsibilities to uphold the company’s commitment to preventing and addressing GBV and VAC.
This means that managers have an acute responsibility to create and maintain an environment that prevents GBV and VAC. Managers need
to support and promote the implementation of the Company Code of Conduct. To that end, managers must adhere this Manager’s Code of
Conduct and also sign the Individual Code of Conduct. This commits them to supporting and developing systems that facilitate the
implementation of the Action Plan and maintain a GBV-free and VAC-free environment at the workplace and in the local community.
These responsibilities include but are not limited to:

Implementation

    •         To ensure maximum effectiveness of the Company and Individual Codes of Conduct:
              1.          Prominently displaying the Company and Individual Codes of Conduct in clear view at workers’ camps, offices,
                          and in in public areas of the work space. Examples of areas include waiting, rest and lobby areas of sites, canteen
                          areas, health clinics.
              2.          Ensuring all posted and distributed copies of the Company and Individual Codes of Conduct are translated into
                          the appropriate language of use in the work site areas as well as for any international staff in their native language.
    •         Verbally and in writing explain the Company and Individual Codes of Conduct to all staff.
    •         Ensure that:
              1.          All direct reports sign the ‘Individual Code of Conduct’, including acknowledgment that they have read and agree
                          with the Code of Conduct.
              2.          Staff lists and signed copies of the Individual Code of Conduct are provided to the GCCT and the client.
              3.          Participate in training and ensure that staff also participate as outlined below.
              4.          Staff are familiar with the Grievance Redress Mechanism (GRM) and that they can use it to anonymously report
                          concerns of GBV or VAC incidents.
              5.          Staff are encouraged to report suspected or actual GBV or VAC through the GRM by raising awareness about
                          GBV and VAC issues, emphasizing the staff’s responsibility to the Company and the country hosting their
                          employment, and emphasizing the respect for confidentiality.
    •         In compliance with applicable laws and to the best of your abilities, prevent perpetrators of sexual exploitation and abuse
              from being hired, re-hired or deployed. Use background and criminal reference checks for all employees.
    •         Ensure that when engaging in partnership, sub-contractor or similar agreements, these agreements:
              1.          Incorporate the GBV and VAC Codes of Conduct as an attachment.
              2.          Include the appropriate language requiring such contracting entities and individuals, and their employees and
                          volunteers, to comply with the Individual Codes of Conduct.
              3.          Expressly state that the failure of those entities or individuals, as appropriate, to take preventive measures against
                          GBV and VAC, to investigate allegations thereof, or to take corrective actions when GBV or VAC has occurred,
                          shall constitute grounds for sanctions and penalties in accordance with the Individual Codes of Conduct.
    •         Provide support and resources to the GCCT to create and disseminate internal sensitization initiatives through the awareness-
              raising strategy under the Action Plan.
   •          Ensure that any GBV or VAC issue warranting police action is reported to the client and the World Bank immediately.
Training

    •         All managers are required to attend an induction manager training course prior to commencing work on site to ensure that
              they are familiar with their roles and responsibilities in upholding the GBV and VAC Codes of Conduct. This training will
                                                                     111
               be separate from the induction training course required of all employees and will provide managers with the necessary
               understanding and technical support needed to begin to develop the Action Plan for addressing GBV and VAC issues.
    •          Ensure that time is provided during work hours and that staff attend the mandatory project facilitated induction training on
               GBV and VAC required of all employees prior to commencing work on site.
    •          Ensure that staff attend the monthly mandatory refresher training course required of all employees to combat increased risk
               of GBV and VAC during civil works.
    •          Managers are required to attend and assist with the project facilitated monthly training courses for all employees. Managers
               will be required to introduce the trainings and announce the self-evaluations.
   •           Collect satisfaction surveys to evaluate training experiences and provide advice on improving the effectiveness of training.
Response

    •         Managers will be required to provide input to the GBV and VAC Allegation Procedures and Response Protocol developed
              by the GCCT as part of the final cleared Action Plan.
    •         Once adopted by the Company, managers will uphold the Accountability Measures set forth in the Action Plan to maintain
              the confidentiality of all employees who report or (allegedly) perpetrate incidences of GBV and VAC (unless a breach of
              confidentiality is required to protect persons or property from serious harm or where required by law).
    •         If a manager develops concerns or suspicions regarding any form of GBV or VAC by one of his/her direct reports, or by an
              employee working for another contractor on the same work site, s/he is required to report the case using the GRM.
    •         Once a sanction has been determined, the relevant manager(s) is/are expected to be personally responsible for ensuring that
              the measure is effectively enforced, within a maximum timeframe of 14 days from the date on which the decision to sanction
              was made.
    •         Managers failing to report or comply with such provision can in turn be subject to disciplinary measures, to be determined
              and enacted by the company’s CEO, Managing Director or equivalen t highest-ranking manager. Those measures may
              include:
              1.        Informal warning.
              2.        Formal warning.
              3.        Additional Training.
              4.        Loss of up to one week's salary.
              5.        Suspension of employment (without payment of salary), for a minimum period of 1 month up to a maximum of
                        6 months.
              6.        Termination of employment.
    •         Ultimately, failure to effectively respond to GBV and VAC cases on the work site by the company’s managers or CEO may
              provide grounds for legal actions by authorities.
I do hereby acknowledge that I have read the foregoing Manager’s Code of Conduct, do agree to comply with the standards contained
therein and understand my roles and responsibilities to prevent and respond to GBV and VAC. I understand that any action inconsistent
with this Manager’s Code of Conduct or failure to take action mandated by this Manager’s Code of Conduct may result in disciplinary
action.

                     Signature:            _________________________
                     Printed Name:         _________________________
                     Title:                _________________________
                     Date:                 _________________________


Individual Code of Conduct on Preventing Gender Based Violence and Violence Against Children (VAC)

I, ______________________________, acknowledge that preventing gender-based violence (GBV) and violence against children (VAC)
is important. The company considers that GBV or VAC activities constitute acts of gross misconduct and are therefore grounds for
sanctions, penalties or potential termination of employment. All forms of GBV or VAC are unacceptable be it on the work site, the work
site surroundings, or at worker’s camps. Prosecution of those who commit GBV or VAC may be pursued if appropriate.

I agree that while working on the project I will:

    •          Consent to police background check.
    •          Treat women, children (persons under the age of 18), and men with respect regardless of race, color, language, religion,
               political or other opinion, national, ethnic or social origin, property, disability, birth or other status.
    •          Not use language or behavior towards women, children or men that is inappropriate, harassing, abusive, sexually
               provocative, demeaning or culturally inappropriate.
    •          Not participate in sexual contact or activity with children—including grooming, or contact through digital media. Mistaken
               belief regarding the age of a child is not a defense. Consent from the child is also not a defense or excuse.
    •          Not engage in sexual favors—for instance, making promises or favorable treatment dependent on sexual acts —or other
               forms of humiliating, degrading or exploitative behavior.

                                                                   112
    •         Unless there is the full consent2 by all parties involved, I will not have sexual interactions with members of the surrounding
              communities. This includes relationships involving the withholding or promise of actual provision of benefit (monetary or
              non-monetary) to community members in exchange for sex—such sexual activity is considered “non-consensual�? within
              the scope of this Code.
   •          Attend and actively partake in training courses related to HIV/AIDS, GBV and VAC as requested by my employer.
   •          Consider reporting through the GRM or to my manager any suspected or actual GBV or VAC by a fellow worker, whether
              employed by my company or not, or any breaches of this Code of Conduct.
With regard to children under the age of 18:

    •          Wherever possible, ensure that another adult is present when working in the proximity of children.
    •          Not invite unaccompanied children unrelated to my family into my home, unless they are at immediate risk of injury or in
               physical danger.
    •          Not sleep close to unsupervised children unless absolutely necessary, in which case I must obtain my supervisor's
               permission, and ensure that another adult is present if possible.
    •          Use any computers, mobile phones, or video and digital cameras appropriately, and never to exploit or harass children or to
               access child pornography through any medium (see also “Use of children's images for work related purposes�? below).
    •          Refrain from physical punishment or discipline of children.
    •          Refrain from hiring children for domestic or other labour which is inappropriate given their age or developmental stage,
               which interferes with their time available for education and recreational activities, or which places them at significant risk
               of injury.
    •          Comply with all relevant local legislation, including labour laws in relation to child labour.

Use of children's images for work related purposes
When photographing or filming a child for work related purposes, I must:

    •          Before photographing or filming a child, assess and endeavour to comply with local traditions or restrictions for reproducing
               personal images.
    •          Before photographing or filming a child, obtain informed consent from the child and a parent or guardian of the child. As
               part of this I must explain how the photograph or film will be used.
    •          Ensure photographs, films, videos and DVDs present children in a dignified and respectful manner and not in a vulnerable
               or submissive manner. Children should be adequately clothed and not in poses that could be seen as sexually suggestive.
    •          Ensure images are honest representations of the context and the facts.
    •          Ensure file labels do not reveal identifying information about a child when sending images electronically.
Sanctions
I understand that if I breach this Individual Code of Conduct, my employer will take disciplinary action which could include:

    •          Informal warning.
    •          Formal warning.
    •          Additional Training.
    •          Loss of up to one week’s salary.
    •          Suspension of employment (without payment of salary), for a minimum period of 1 month up to a maximum of 6 months.
    •          Termination of employment.
    •          Report to the police if warranted.
I understand that it is my responsibility to avoid actions or behaviours that could be construed as GBV or VAC or breach this Individual
Code of Conduct. I do hereby acknowledge that I have read the foregoing Individual Code of Conduct, do agree to comply with the
standards contained therein and understand my roles and responsibilities to prevent and respond to GBV and VAC. I understand that any
action inconsistent with this Individual Code of Conduct or failure to take action mandated by this Individual Code of Conduct may result
in disciplinary action and may affect my ongoing employment.

                      Signature:            _________________________
                      Printed Name:         _________________________
                      Title:                _________________________
                      Date:                 _________________________



2 Consent is defined as the informed choice underlying an individual’s free and voluntary intention, acceptance or agreement to do something.
No consent can be found when such acceptance or agreement is obtained through the use of threats, force or other forms of coercion, abduction,
fraud, deception, or misrepresentation. In accordance with the United Nations Convention on the Rights of the Child, the World Bank considers
that consent cannot be given by children under the age of 18, even in the event that national legislation of the country into which the Code of
Conduct is introduced has a lower age. Mistaken belief regarding the age of the child and consent from the child is not a defence.

                                                                      113
       ANNEX VIII: GRIEVANCE REDRESS FRAMEWORK FOR IMO STATE RAMP
       Grievances may arise from any of the following: 1) involuntary resettlement and compensation issues, 2) gender based
       violence/SEA issues, 3) exclusion from project benefits and non-compliance of the contractor to the agreement reached with RAMP
       or the community, 4) Poor construction waste handling, 5) lack of alternative route for movement during construction, etc.

       A Grievance Redress Mechanism (GRM) will be implemented to ensure that all complaints from local communities are dealt with
       appropriately, with corrective actions being implemented, and the complainant being informed of the outcome. It will be applied
       to all complaints from affected parties. The SPIU will maintain a Complaints Database, which will contain all the information on
       complaints or grievances received from the communities or other stakeholders. This would include: the type of complaint, location,
       time, actions to address these complaints, and final outcome.

       The SPIU, shall set-up a grievance redress committee that will address any complaints during project implementation. This will be
       treated in two folds; 1) GBV related GRM and 2) non GBV related GRM. A classified procedure for confidentiality is required in
       the cases of GBV and thus, a GBV risk management plan is prepared separate for this project. Grievance Redress Committees
       (GRCs) shall be constituted at various levels to implement the GRM for the project including community level, SPIU level, FPMU
       level, World Bank Grievance Redress System. It is noteworthy to state that a detailed GRM is been developed for RAMP, thus Imo
       RAMP will align its processes to the framework.

       The Grievance Redress Committee will be responsible for:
         •      Communicating with the Affected persons (AP’s) and evaluate if they are entitled to recompense;
         •      Making the list of affected persons public and the established grievance redress procedure.
         •      Recommending to the Social Safeguard Officer of the SPIU solutions to such grievances from affected persons;
       Communicating the decisions to the AP’s; to acknowledge appeals from persons, households or groups who rightfully will not be
       affected by the project, but claim to be, and to recommend to the SPIU whether such persons should be recognized as AP’s, and to
       communicate back the decisions to the Claimants.

       Expectation When Grievances Arise

       When people present a grievance, any of the followings is or are expected from the project management/channel of grievance
       resolution by the local people:
            •    acknowledgement of their problem;
            •    an honest response to questions/issues brought forward;
            •    an apology, adequate compensation; and
            •    Modification of the conduct that caused the grievance and some other fair remedies.

       Structure and Protocols for Reporting and Managing Grievances

       The SPC will set up a grievance redress committee to look into escalated grievances. This shall be established in various levels as
       follows:

First Level GRM: GRC at      Composed at the community level, easily accessible to community people, village head and representative of women shall
the Site/Community Level     be part of the committee among other identified persons. This committee will be expected to report to the SPIU. In addition,
                             complaint box will be placed in the Community leader’s palace and other locations such as markets, civic centers etc. that
                             will encourage aggrieved parties drop their complaints.

Second Level of GRM:         This committee shall comprise of PIU members including the Project Coordinator, Social Safeguard Officer among others,
GRC at the SPIU Level        and other state level representative from within the State Project Monitoring Committees. If the complainant does not
                             accept the solution offered by the SPIU-GRC, then the complaint is referred by the SPC to the SPMC.

Third Level of GRM: GRC      The Federal Project Management Unit (FPMU) will be required to intervene in grievances beyond the state level resolution.
at the FPMU Level

Court Redress of             While the purposes of GRM put in place by this Project is to resolve all issues caused by the project implementation out
Grievances                   of court and to save time which is usually involved in litigation matters, it is not out of place to anticipate a scenario where
                             aggrieved person is not satisfied with the process and judgment given by the grievance redress committee(s). Therefore,
                             SPIU shall inform aggrieved persons of their right to seek for redress in the court of law as the final resort.

                                                                       114
ANNEX IX: SUMMARY OF WORLD BANK ENVIRONMENTAL AND SOCIAL
SAFEGUARD POLICIES APPLICABLE TO THE RAMP PROJECT
Environmental Assessment (OP 4.01). Outlines Bank policy and procedure for the environmental assessment of Bank lending
operations. The Bank undertakes environmental screening of each proposed project to determine the appropriate extent and type of
EA process.

Natural Habitats (OP 4.04). The conservation of natural habitats, like other measures that protect and enhance the environment,
is essential for long-term sustainable development. The Bank does not support projects involving the significant conversion of
natural habitats unless there are no feasible alternatives for the project and its siting, and comprehensive analysis demonstrates that
overall benefits from the project substantially outweigh the environmental costs. If the environmental assessment indicates that a
project would significantly convert or degrade natural habitats, the project includes mitigation measures acceptable to the Bank.

Involuntary Resettlement (OP 4.12). This policy covers direct economic and social impacts that both result from Bank-assisted
investment projects, and are caused by (a) the involuntary taking of land resulting in (i) relocation or loss of shelter; (ii) loss of
assets or access to assets, or (iii) loss of income sources or means of livelihood, whether or not the affected persons must move to
another location; or (b) the involuntary restriction of access to legally designated parks and protected areas resulting in adverse
impacts on the livelihoods of the displaced persons. The ESMF and RPF reports discuss the applicability of this policy in detail.

Physical Cultural Resources OP. 4.11This policy addresses physical cultural resources,1 which are defined as movable or
immovable objects, sites, structures, groups of structures, and natural features and landscapes that have archaeological,
paleontological, historical, architectural, religious, aesthetic, or other cultural significance. Physical cultural resources may be
located in urban or rural settings, and may be above or below ground, or under water. Their cultural interest may be at the local,
provincial or national level, or within the international community.




                                                                 115
ANNEX X: GENERAL ENVIRONMENTAL MANAGEMENT CONDITIONS FOR
CONSTRUCTION CONTRACTS

General
1.        In addition to these general conditions, the Contractor shall comply with any specific Environmental and Social
          Management Plan (ESMP) for the works he is responsible for. The Contractor shall inform himself about such an EMP,
          and prepare his work strategy and plan to fully take into account relevant provisions of that EMP. If the Contractor fails
          to implement the approved EMP after written instruction by the Supervising Engineer (SE) to fulfil his obligation within
          the requested time, the Owner reserves the right to arrange through the SE for execution of the missing action by a third
          party on account of the Contractor.
2.        Notwithstanding the Contractor’s obligation under the above clause, the Contractor shall implement all measures
          necessary to avoid undesirable adverse environmental and social impacts wherever possible, restore work sites to
          acceptable standards, and abide by any environmental performance requirements specified in an EMP. In general, these
          measures shall include but not be limited to:
          (a)        Minimize the effect of dust on the surrounding environment resulting from earth mixing sites, asphalt mixing
          sites, dispersing coal ashes, vibrating equipment, temporary access roads, etc. to ensure safety, health and the protection
          of workers and communities living in the vicinity dust producing activities.
          (b)        Ensure that noise levels emanating from machinery, vehicles and noisy construction activities (e.g. excavation,
          blasting) are kept at a minimum for the safety, health and protection of workers within the vicinity of high noise levels
          and nearby communities.
          (c)        Ensure that existing water flow regimes in rivers, streams and other natural or irrigation channels is maintained
          and/or re-established where they are disrupted due to works being carried out.
          (d)        Prevent bitumen, oils, lubricants and waste water used or produced during the execution of works from entering
          into rivers, streams, irrigation channels and other natural water bodies/reservoirs, and also ensure that stagnant water in
          uncovered borrow pits is treated in the best way to avoid creating possible breeding grounds for mosquitoes.
          (e)        Prevent and minimize the impacts of quarrying, earth borrowing, piling and building of temporary construction
          camps and access roads on the biophysical environment including protected areas and arable lands; local communities
          and their settlements. In as much as possible restore/rehabilitate all sites to acceptable standards.
          (f)        Upon discovery of ancient heritage, relics or anything that might or believed to be of archaeological or historical
          importance during the execution of works, immediately report such findings to the SE so that the appropriate authorities
          may be expeditiously contacted for fulfilment of the measures aimed at protecting such historical or archaeological
          resources.
          (g)        Discourage construction workers from engaging in the exploitation of natural resources such as hunting,
          fishing, collection of forest products or any other activity that might have a negative impact on the social and economic
          welfare of the local communities.
          (h)        Implement soil erosion control measures in order to avoid surface run off and prevents siltation, etc.
          (i)        Ensure that garbage, sanitation and drinking water facilities are provided in construction workers camps.
          (j)        Ensure that, in as much as possible, local materials are used to avoid importation of foreign material and long-
          distance transportation.
          (k)        Ensure public safety, and meet traffic safety requirements for the operation of work to avoid accidents.
3.        The Contractor shall indicate the period within which he/she shall maintain status on site after completion of civil works
          to ensure that significant adverse impacts arising from such works have been appropriately addressed.
4.        The Contractor shall adhere to the proposed activity implementation schedule and the monitoring plan / strategy to ensure
          effective feedback of monitoring information to project management so that impact management can be implemented
          properly, and if necessary, adapt to changing and unforeseen conditions.
5.        Besides the regular inspection of the sites by the SE for adherence to the contract conditions and specifications, the Owner
          may appoint an Inspector to oversee the compliance with these environmental conditions and any proposed mitigation
          measures. State environmental authorities may carry out similar inspection duties. In all cases, as directed by the SE,
          the Contractor shall comply with directives from such inspectors to implement measures required to ensure the adequacy
          rehabilitation measures carried out on the bio-physical environment and compensation for socio-economic disruption
          resulting from implementation of any works.

Worksite/Campsite Waste Management
6.       All vessels (drums, containers, bags, etc.) containing oil/fuel/surfacing materials and other hazardous chemicals shall be
         bonded in order to contain spillage. All waste containers, litter and any other waste generated during the construction
         shall be collected and disposed at designated disposal sites in line with applicable government waste management
         regulations.
                                                                 116
7.        All drainage and effluent from storage areas, workshops and camp sites shall be captured and treated before being
          discharged into the drainage system in line with applicable government water pollution control regulations.
8.        Used oil from maintenance shall be collected and disposed of appropriately at designated sites or be reused or sold for
          re-use locally.
9.        Entry of runoff to the site shall be restricted by constructing diversion channels or holding structures such as banks,
          drains, dams, etc. to reduce the potential of soil erosion and water pollution.
10.       Construction waste shall not be left in stockpiles along the road, but removed and reused or disposed of on a daily basis.
11.       If disposal sites for clean spoil are necessary, they shall be located in areas, approved by the SE, of low land use value
          and where they will not result in material being easily washed into drainage channels. Whenever possible, spoil materials
          should be placed in low-lying areas and should be compacted and planted with species indigenous to the locality.
Material Excavation and Deposit
12.       The Contractor shall obtain appropriate licenses/permits from relevant authorities to operate quarries or borrow areas.
13.       The location of quarries and borrow areas shall be subject to approval by relevant local and national authorities, including
          traditional authorities if the land on which the quarry or borrow areas fall in traditional land.
14.       New extraction sites:
          a)         Shall not be located in the vicinity of settlement areas, cultural sites, wetlands or any other valued ecosystem
          component, or on high or steep ground or in areas of high scenic value, and shall not be located less than 1km from such
          areas.
          b)         Shall not be located adjacent to stream channels wherever possible to avoid siltation of river channels. Where
          they are located near water sources, borrow pits and perimeter drains shall surround quarry sites.
          c)         Shall not be located in archaeological areas. Excavations in the vicinity of such areas shall proceed with great
          care and shall be done in the presence of government authorities having a mandate for their protection.
          d)         Shall not be located in forest reserves. However, where there are no other alternatives, permission shall be
          obtained from the appropriate authorities and an environmental impact study shall be conducted.
          e)         Shall be easily rehabilitated. Areas with minimal vegetation cover such as flat and bare ground, or areas
          covered with grass only or covered with shrubs less than 1.5m in height, are preferred.
          f)         Shall have clearly demarcated and marked boundaries to minimize vegetation clearing. Vegetation clearing
          shall be restricted to the area required for safe operation of construction work. Vegetation clearing shall not be done more
          than two months in advance of operations.
15.       Stockpile areas shall be located in areas where trees can act as buffers to prevent dust pollution. Perimeter drains shall
          be built around stockpile areas. Sediment and other pollutant traps shall be located at drainage exits from workings.
16.       The Contractor shall deposit any excess material in accordance with the principles of the general conditions, and any
          applicable EMP, in areas approved by local authorities and/or the SE.
17.       Areas for depositing hazardous materials such as contaminated liquid and solid materials shall be approved by the SE
          and appropriate local and/or national authorities before the commencement of work. Use of existing, approved sites shall
          be preferred over the establishment of new sites.

Rehabilitation and Soil Erosion Prevention
18.       To the extent practicable, the Contractor shall rehabilitate the site progressively so that the rate of rehabilitation is similar
          to the rate of construction.
19.       Always remove and retain topsoil for subsequent rehabilitation. Soils shall not be stripped when they are wet as this can
          lead to soil compaction and loss of structure.
20.       Topsoil shall not be stored in large heaps. Low mounds of no more than 1 to 2m high are recommended.
21.       Re-vegetate stockpiles to protect the soil from erosion, discourage weeds and maintain an active population of beneficial
          soil microbes.
22.       Locate stockpiles where they will not be disturbed by future construction activities.
23.       To the extent practicable, reinstate natural drainage patterns where they have been altered or impaired.
24.       Remove toxic materials and dispose of them in designated sites. Backfill excavated areas with soils or overburden that
          is free of foreign material that could pollute groundwater and soil.
25.       Identify potentially toxic overburden and screen with suitable material to prevent mobilization of toxins.
26.       Ensure reshaped land is formed so as to be inherently stable, adequately drained and suitable for the desired long-term
          land and allow natural regeneration of vegetation.
27.       Minimize the long-term visual impact by creating landforms that are compatible with the adjacent landscape.
28.       Minimize erosion by wind and water both during and after the process of reinstatement.
29.       Compacted surfaces shall be deep ripped to relieve compaction unless subsurface conditions dictate otherwise.
30.       Re-vegetate with plant species that will control erosion, provide vegetative diversity and, through succession, contribute
          to a resilient ecosystem. The choice of plant species for rehabilitation shall be done in consultation with local research
          institutions, forest department and the local people.

                                                                   117
Water Resources Management
31.       The Contractor shall at all costs avoid conflicting with water demands of local communities.
32.       Abstraction of both surface and underground water shall only be done with the consultation of the local community and
          after obtaining a permit from the relevant Water Authority.
33.       Abstraction of water from wetlands shall be avoided. Where necessary, authority has to be obtained from relevant
          authorities.
34.       Temporary damming of streams and rivers shall be done in such a way avoids disrupting water supplies to communities
          downstream, and maintains the ecological balance of the river system.
35.       No construction water containing spoils or site effluent, especially cement and oil, shall be allowed to flow into natural
          water drainage courses.
36.       Wash water from washing out of equipment shall not be discharged into water courses or road drains.
37.       Site spoils and temporary stockpiles shall be located away from the drainage system, and surface run off shall be directed
          away from stockpiles to prevent erosion.
Traffic Management             *-
38.       Location of access roads/detours shall be done in consultation with the local community especially in important or
          sensitive environments. Access roads shall not traverse wetland areas.
39.       Upon the completion of civil works, all access roads shall be ripped and rehabilitated.
40.       Access roads shall be sprinkled with water at least five times a day in settled areas, and three times in unsettled areas, to
          suppress dust emissions.
Blasting
41.       Blasting activities shall not take place less than 2km from settlement areas, cultural sites, or wetlands without the
          permission of the SE.
42.       Blasting activities shall be done during working hours, and local communities shall be consulted on the proposed blasting
          times.
43.       Noise levels reaching the communities from blasting activities shall not exceed 90 decibels.
Disposal of Unusable Elements
44.       Unusable materials and construction elements such as electro-mechanical equipment, pipes, accessories and demolished
          structures will be disposed of in a manner approved by the SE. The Contractor has to agree with the SE which elements
          are to be surrendered to the Client’s premises, which will be recycled or reused, and which will be disposed of at approved
          landfill sites.
45.       As far as possible, abandoned pipelines shall remain in place. Where for any reason no alternative alignment for the new
          pipeline is possible, the old pipes shall be safely removed and stored at a safe place to be agreed upon with the SE and
          the local authorities concerned.
46.       AC-pipes as well as broken parts thereof have to be treated as hazardous material and disposed of as specified above.
47.       Unsuitable and demolished elements shall be dismantled to a size fitting on ordinary trucks for transport.
Health and Safety
48.       In advance of the construction work, the Contractor shall mount an awareness and hygiene campaign. Workers and local
          residents shall be sensitized on health risks particularly of Cholera, tetanus and Hepatitis.
49.       Adequate road signs to warn pedestrians and motorists of construction activities, diversions, etc. shall be provided at
          appropriate points.
50.       Construction vehicles shall not exceed maximum speed limit of 40km per hour.
Repair of Private Property
51.       Should the Contractor, deliberately or accidentally, damage private property, he shall repair the property to the owner’s
          satisfaction and at his own cost. For each repair, the Contractor shall obtain from the owner a certificate that the damage
          has been made good satisfactorily in order to indemnify the Client from subsequent claims.
52.       In cases where compensation for inconveniences, damage of crops etc. are claimed by the owner, the Client has to be
          informed by the Contractor through the SE. This compensation is in general settled under the responsibility of the Client
          before signing the Contract. In unforeseeable cases, the respective administrative entities of the Client will take care of
          compensation.
Contractor’s Environment, Health and Safety Management Plan (EHS-MP)
53.       Within 6 weeks of signing the Contract, the Contractor shall prepare an EHS-MP to ensure the adequate management of
          the health, safety, environmental and social aspects of the works, including implementation of the requirements of these
          general conditions and any specific requirements of an EMP for the works. The Contractor’s EHS -MP will serve two
          main purposes:
          •           For the Contractor, for internal purposes, to ensure that all measures are in place for adequate EHS
          management, and as an operational manual for his staff.



                                                                 118
        •         For the Client, supported where necessary by a SE, to ensure that the Contractor is fully prepared for the
        adequate management of the EHS aspects of the project, and as a basis for monitoring of the Contractor’s EHS
        performance.
54.     The Contractor’s EHS-MP shall provide at least:
        •         a description of procedures and methods for complying with these general environmental management
        conditions, and any specific conditions specified in an EMP;
        •         a description of specific mitigation measures that will be implemented in order to minimize adverse impacts;
        •         a description of all planned monitoring activities (e.g. sediment discharges from borrow areas) and the reporting
        thereof; and
        •         the internal organizational, management and reporting mechanisms put in place for such.
55. The Contractor’s EHS-MP will be reviewed and approved by the Client before start of the works. This review should
        demonstrate if the Contractor’s EHS-MP covers all of the identified impacts, and has defined appropriate measures to
        counteract any potential impacts.

EHS Reporting
56. The Contractor shall prepare bi-weekly progress reports to the SE on compliance with these general conditions, the project
         EMP if any, and his own EHS-MP. An example format for a Contractor EHS report is given below. It is expected that
         the Contractor’s reports will include information on:
         •         EHS management actions/measures taken, including approvals sought from local or national authorities;
         •         Problems encountered in relation to EHS aspects (incidents, including delays, cost consequences, etc. as a result
         thereof);
         •         Lack of compliance with contract requirements on the part of the Contractor;
         •         Changes of assumptions, conditions, measures, designs and actual works in relation to EHS aspects; and
         •         Observations, concerns raised and/or decisions taken with regard to EHS management during site meetings.

Training of Contractor’s Personnel
57.       The Contractor shall provide sufficient training to his own personnel to ensure that they are all aware of the relevant
          aspects of these general conditions, any project EMP, and his own EHS-MP, and are able to fulfil their expected roles
          and functions. Specific training should be provided to those employees that have particular responsibilities associated
          with the implementation of the EHS-MP. General topics should be:
          •         EHS in general (working procedures);
          •         Emergency procedures; and
          •         Social and cultural aspects (raise awareness on social issues).
Cost of Compliance
58.       It is expected that compliance with these conditions is already part of standard good workmanship and state of art as
          generally required under this Contract. The item “Compliance with Environmental Management Conditions�? in the Bill
          of Quantities covers this cost. No other payments will be made to the Contractor for compliance with any request to
          avoid and/or mitigate an avoidable EHS impact.




                                                               119
ANNEX XI TRAFFIC MANAGEMENT PLAN

A site-specific Traffic Management Plan for construction activities that will describe the deliveries traffic path,
pedestrian path, internal traffic path will be issued prior to commencing construction. The Traffic Management Plan
will include information on the following:
• Overview
• Traffic Management inside the Construction Site
• Traffic Management for construction delivery
• Traffic Management for pedestrian
• Any effect on existing neighbouring property traffic or access.

• Site fencing / Hoardings
The construction site will be fenced off with temporary fencing to all surrounds. Site fencing will prevent any access
from un-authorised entry to site. Construction site access is through site entry only.

• Construction site entry
The construction vehicle site entry must be indicated by the contractor and will make use of driveway access then
flowing across a vacant allotment to a paved parking area. This makes use of the existing site conditions and reduces
the impact to the adjoining facilities. All of the construction deliveries and access will be via this entry. Clear signage
will be erected outlining the construction entry. Construction pedestrian / workers access will be separated from
vehicle access by way of separate pedestrian entry from adjoining footpath. Workers will have a direct footpath access
to site amenities from pedestrian entry gate.

• Deliveries & Traffic Management
A delivery area will be located within the site compound - All material deliveries for the works will be made via the
entry/entry via the designated entry road. Vehicular movements around the building will be managed by trained traffic
management operatives. All vehicles will enter and exit the construction site in forward facing direction.

• Tower Crane
Tower crane will generally be used to unload heavy material and equipment directly from the truck. They are to be
lifted to the designated location or on to loading platform. Traffic control during loading and unloading inside the
construction site will be carried out by contractor’s representative.

• Man Materials hoist
A man and materials hoist will be used to provide safe access on the floors and the movement of smaller materials. A
safe pedestrian access will be provided to the hoist location.

The Contractor shall be required to provide appropriate information, training, instruction or supervision necessary to
protect all persons from risks to their health and safety. The Contractor must also ensure construction induction
training is provided to workers who carry out construction work.
• The Imo State RAMP will place speed limits and appropriate road signage along all Project roads;
• The Imo State RAMP will enforce speed limits for safety, air quality, and noise purposes both on the Project site
    and beyond;
• All drivers should be trained by a road safety specialist; and,
• All vehicles should be properly maintained and undergo periodic safety inspections.
• Observance of speed limits by contractor’s vehicles / drivers should be part of the contractual agreement




                                                           120
ANNEX XII: PHYSICAL CULTURAL RESOURCES - MANAGEMENT PLAN (PCR-
MP).

Purpose of the Physical Cultural Resources Management Plan (PCRMP)

The PCRMP is a project-specific procedure that outlines actions required to protect cultural areas and to serve as
guidelines if previously unknown heritage resources, particularly archaeological resources, are encountered during
project construction or operation.

Project Context
The proposed project will be located in Riverine areas. The ESMP mentioned that except in Mgbidi (Obana River)
the other project sites are not within archeologically or culturally significant areas.

Specifically, the potential impact of the project on Physical Cultural Resources include the following:
    • Relocation of the shrine
    • Killing of fish in Obana River
    • Restricting the movement of worshippers
    • Killing of the Boa
    • Fetching of water from the Obana River on small Orie days

However, before starting the construction works, ESMP recommends that the civil contractors should be taken on a
guided tour to the site to acquaint themselves on the physical and cultural resources. The contractors need to be made
aware of the chance find procedure enabling them on specific actions to in case deified animals (Boa), burials and
any other culturally significant objects could be observed.

Scope

In case during site clearing and construction, the contractor comes across or unearths materials/objects/animals that
are considered to be of significance in terms of the fact that;
     • they are culturally sensitive objects such as burials, trees or stones
     • the community in the area uphold and respect them (as is the case of the Boa in Mgbidi town)
     • they are of archeological importance;

Then the PCRMP should be followed:


General PCRMP

If any person discovers a physical cultural resource, such as (but not limited to) archaeological sites, deified animals,
historical sites, remains and objects, or a cemetery and/or individual graves during excavation or construction, the
following steps shall be taken:

1.   Stop all works in the vicinity of the find, until a solution is found for the preservation of these artefacts, or advice
     from the relevant authorities is obtained;
2.   Immediately notify a foreman. The foreman will then notify the Construction Manager and the Environment
     Officer (EO)/Environmental Manager (EM);
3.   The knowledge of local communities is particularly important for identifying cultural heritage that may be tied
     to the natural environment and not evident to outsiders. Therefore, in this case, the civil contractors should
     have the presence of mind to act upon any doubtful objects that will surfaced in the excavation work.
4.   Record details in Incident Report and take photos of the find;

                                                            121
5.   Delineate the discovered site or area; secure the site to prevent any damage or loss of removable objects. In cases
     of removable antiquities or sensitive remains, a night guard shall be arranged until the responsible local
     authorities take over;
6.   Preliminary evaluation of the findings by archaeologists. The archaeologist must make a rapid assessment of the
     site or find to determine its importance. Based on this assessment the appropriate strategy can be implemented.
     The significance and importance of the findings should be assessed according to the various criteria relevant to
     cultural heritage such as aesthetic, historic, scientific or research, social and economic values of the find;
7.   Sites of minor significance (such as isolated or unclear features, and isolated finds) should be recorded
     immediately by the archaeologist, thus causing a minimum disruption to the work schedule of the Contractor.
     The results of all archaeological work must be reported to the Ministry/Agency, once completed.
     8. In case of burials, the contractor should consult the Grievance Committee members and should be in touch
          with the relevant family members, before they are dealt with. In consultation with the family members the
          contractor should provide all necessary assistance to protect the burials in situ (by erecting a fence around
          the area) or to translocate same with consent of the family members after paying compensation if required.
     9. Areas to be protected on the advice of the stakeholders should be adhered to by the contractor and the project
          developer. Such areas should be demarcated and specific management practices should be adopted.
     10. In case of significant find the Agency/Ministry (Agency for Protection of National Heritage or
          Archaeological Research Centre, hereinafter referred to as Heritage team) should be informed immediately
          and in writing within 7 days from the find (ref. law on heritage protection).
     11. The onsite archaeologist provides the Heritage team with photos, other information as relevant for
          identification and assessment of the significance of heritage items.
     12. The Ministry must investigate the fact within 2 weeks from the date of notification and provide response in
          writing.
     13. Decisions on how to handle the finding shall be taken by the responsible authorities. This could include
          changes in the layout (such as when finding an irremovable remain of cultural or archaeological importance)
          conservation, preservation, restoration and salvage;
     14. Construction works could resume only after permission is granted from the responsible authorities.
     15. In case no response received within the 2 weeks period mentioned above, this is considered as authorization
          to proceed with suspended construction works.

One of the main requirements of the procedure is record keeping. All finds must be registered. Photolog, copies of
communication with decision making authorities, conclusions and recommendations/guidance, implementation
reports – kept.

Additional information management options for archaeological and cultural site
   • Site avoidance. If the boundaries of the site have been delineated attempt must be made to redesign the
        proposed development to avoid the site. (The fastest and most cost-effective management option)
   • Mitigation. If it is not feasible to avoid the site through redesign, it will be necessary to sample it using data
        collection program prior to its loss. This could include surface collection and/or excavation. (The most
        expensive and time-consuming management option.)
   • Site Protection. It may be possible to protect the site through the installation of barriers during the time of
        the development and/or possibly for a longer term. This could include the erection of high visibility fencing
        around the site or covering the site area with a geotextile and then capping it with fill. The exact prescription
        would be site- specific.

Specific PCRMP
Tangible Cultural Heritage (Replicable heritage)
Obana shrine


                                                          122
Obana shrine was regarded as a tangible cultural heritage that is replicable3. For this cultural heritage, the following
mitigation hierarchy will be applied:

    •    Educate the contractors and sub-contractors about the shrine or sacred site based on a previous specialist
         review;
    •    Engage with stakeholder and members of the community to determine the shrine’s level of importance;
    •    Avoid shrines determined to be very important to the local community.
    •    Where possible, design or re-design Project components to avoid or minimize impacts to known physical
         cultural heritage resources based on input from cultural heritage specialists.
    •    Consult with the local community if shrines considered important to the local community cannot be avoided
         and offer compensation for the loss of the cultural resource or to inquire about the possibility of relocating
         the resource;
    •    Integrate locational data from mapping survey and shrine importance information from stakeholder
         engagement data into the Project’s cultural heritage GIS database.
    •    Minimize impacts to traditional religious observances associated with removal/relocation of sacred sites
         through ongoing stakeholder engagement; and
    •    Solicit input from and provide information to local communities, traditional rulers, National Commission for
         Museum and Monuments (NCMM), and national and international scientific community on heritage issues,
         work, and concerns throughout construction and notify these groups of relevant Chance Finds as needed.

Non-replicable cultural heritage
The Boa

The Boa constrictor is regarded as a tangible non-replicable cultural heritage in Mgbidi town. For this cultural heritage,
the following mitigation hierarchy should be applied:

   • stakeholder engagement to identify the Boa’s habitat, migratory route and routine;
   • Gaps or buffer will be created to allow the Boa and other wildlife to cross the ROW
   • Site marking/protection with barriers to restrict the movement of the Boa into project area;
   • Reduced working strip to reduce the possibility of encroaching the Boa’s habitat.
   • construction scheduling based on the Boa’s route and routine to avoid contact;
   • consultation with chief priest and community elders on the required compensation if Boa is mistakenly killed;
   • Instructions in worker’s Code of Conduct on the line of action when the Boa is seen on site;
Nonreplicable cultural heritage4 must not be removed unless all of the following conditions are met:



            3Replicable cultural heritage is defined as tangible forms of cultural heritage that can themselves be
            moved to another location or that can be replaced by a similar structure or natural features to which
            the cultural values can be transferred by appropriate measures. Archaeological or historical sites
            may be considered replicable where the particular eras and cultural values they represent are well
            represented by other sites and/or structures.

4 Nonreplicable cultural heritage may relate to the social, economic, cultural, environmental, and climatic
conditions of past peoples, their evolving ecologies, adaptive strategies, and early forms of environmental
management, where the (i) cultural heritage is unique or relatively unique for the period it represents, or (ii)
cultural heritage is unique or relatively unique in linking several periods in the same site. Examples of non-
replicable cultural heritage may include an ancient city or temple, or a site unique in the period that it represents.
                                                        123
There are no technically or financially feasible alternatives to removal;
    • Any removal of cultural heritage must be conducted using the best available technique advised by relevant
        authority and supervised by a zoologist in this case of the Boa, with inputs from the chief priest and elders.

Human Remains Management Options

The handling of human remains believed to be archaeological in nature requires communication according to the same
procedure described above.

There are two possible courses of action:

    •   Avoid. The development project is redesigned to completely avoid the found remains. An assessment should
        be made as to whether the remains may be affected by residual or accumulative impacts associated with the
        development, and properly addressed by a comprehensive management plan.
    •   Exhume. Exhumation of the remains in a manner considered appropriate by decision makers. This will
        involve the predetermination of a site suitable for the reburial of the remains. Certain ceremonies or
        procedures may need to be followed before development activities can recommence in the area of the
        discovery.

Intangible Cultural heritage
Restriction on Fishing and fetching water from Obana River on Small Orie days
    • educational, awareness-raising and information programmes, aimed at the general public, in particular
         construction workers from other communities
    • identify and define the various elements of this intangible cultural heritage (fetching water on small orie day
         and fishing) with the participation of communities and relevant non-governmental organizations.
    • consultation with chief priest and community elders on the required compensation if fish is mistakenly killed
         or water is fetched on small Orie day;
    • adopt a general policy of respect aimed at promoting the function of these intangible cultural heritages and
         at integrating the safeguarding of such heritage into project planning programmes;
    • Instructions in worker’s Code of Conduct on the line of action when the fish is mistakenly killed; and
    • designate or establish one or more competent bodies for the safeguarding of these intangible cultural
         heritages;

EMERGENCY CONTACTS Ministry of Information and Culture




                                                        124
         ANNEX XIII: ANALYSIS OF THE BIO-PHYSICAL ENVIRONMENT
                         Soil                     Air                                                          Surface Water
S/N     Name of          LOT 1
        Priority Site            Total
                         Ph               Cond    SO2     NO2    VOC     H2S     CO    CO2    Air Temp Noise   pH     Cond     DO     Res    Colour Odour        Temp
                                 Nitrogen
        Agbata-
1       Umuigwe Na 6.54          15,253   1,612   <0.01   0.01   0.104   <0.01   0.2   0.01   32.7     43.2    7.15   554      6.92   5.76   Clear   Odourless   31.3
        Uzoagba
        Okwu-
2                       6.61     16,218   1,810   <0.01   0.02   0.145   <0.01   0.2   0.01   32.0     44.0    7.23   558      5.71   3.96   Clear   Odourless   30.4
        Umuonohor
        Orie Mbieri-
3       Umuomumumbi 6.09         16,863   1,720   <0.01   0.01   0.101   <0.01   0.1   0.01   30.5     39.4    6.75   541      2.53   4.37   Clear   Odourless   31.7
        eri
        Ekwe-
4                       7.65     16,331   2,220   <0.01   0.01   0.131   <0.01   0.1   0.01   31.1     50.4    6.82   476      3.39   4.21   Clear   Odourless   31.2
        Okwuodor
        Umuduruemgha
5                       7.77     16,265   1,865   <0.01   0.01   0.104   <0.01   0.0   0.01   30.5     38.5    7.51   589      5.42   3.54   Clear   Odourless   31.9
        ra-Okpala Anara
        Umuihim
        Autonomous
6                       7.67     16,183   1,432   <0.01   0.02   0.125   <0.01   0.0   0.01   30.7     45.2    6.93   490      4.47   5.78   Clear   Odourless   31.7
        Community –
        Umukaku
        Umulogho-
7                       7.89     15,341   1,211   <0.01   0.01   0.111   <0.01   0.1   0.01   30.9     47.8    7.22   471      5.76   4.72   Clear   Odourless   30.6
        Okwuohia
LOT 2
        Uzurunamu-
1                     7.91       15,421   1,198   <0.01   0.02   0.141   <0.01   0.0   0.01   31.3     43.2    7.23   540      5.22   4.37   Clear   Odourless   30.9
        Okwudo Mgbidi
        Akama-Nansa-
2                     6.09       15,239   1,211   <0.01   0.00   0.133   <0.01   0.0   0.01   31.2     43.5    7.43   556      5.43   4.80   Clear   Odourless   30.3
        Akwa Ihedi
3       Igbee-Amaruru 7.68       15,538   1,120   <0.01   0.00   0.123   <0.01   0.1   0.01   30.5     49.3    7.50   532      3.47   3.35   Clear   Odourless   30.6
        Ndiuche-Izuogu
4                        6.99    16,290   1,112   <0.01   0.02   0.125   <0.01   0.0   0.01   31.3     42.1    7.01   454      3.28   5.65   Clear   Odourless   31.1
        Uri
        Obinugwu-
5                        6.53    16,439   1,210   <0.01   0.01   0.154   <0.01   0.1   0.01   31.7     38.5    6.72   541      5.24   4.55   Clear   Odourless   31.3
        Umueshi-Okwa
        Dikenafai-Abba
6                        6.59    16,300   1,325   <0.01   0.01   0.130   <0.01   0.2   0.01   31.9     41.2    6.99   498      5.12   4.51   Clear   Odourless   30.4
        Nwagele
        Dimagu-
7                        6.94    16,750   1,614   <0.01   0.00   0.152   <0.01   0.2   0.01   30.8     47.8    6.57   401      5.76   4.21   Clear   Odourless   31.8
        Nkwere
LOT 3


                                                                                 125
        Umueziogwu-
        Uzoagba-
1                      6.59   15,950     1,512   <0.01   0.01    0.101   <0.01   0.0   0.01   30.1   38.5   6.65   534     6.65   4.52   Clear   Odourless   32.1
        Okitankwo-
        Umunahu
        Umuebee-
2                      7.92   16,301     1,810   <0.01   0.01    0.121   <0.01   0.0   0.01   30.5   41.2   7.11   403     5.90   4.67   Clear   Odourless   31.3
        Umuhu
3       Ugbele-Bsc     6.76   16,458     1,720   <0.01   0.01    0.114   <0.01   0.1   0.01   31.3   39.4   7.79   520     2.87   3.44   Clear   Odourless   31.6
        Amugu-
4                      7.61   16,109     1,720   <0.01   0.01    0.105   <0.01   0.0   0.01   30.7   40.4   6.67   450     4.66   4.87   Clear   Odourless   30.9
        Umulebe
LOT 4
        Ndikpa
1                     6.90    16,340     1,112   <0.01   0.01    0.121   <0.01   0.0   0.01   30.5   41.1   6.76   601     6.11   4.65   Clear   Odourless   30.9
        Umucheke-Okiu
        Ukolu-
2                     6.64    16,180     1,715   <0.01   0.02    0.138   <0.01   0.0   0.01   28.6   42.3   7.87   579     5.43   4.11   Clear   Odourless   31.7
        Umucheke
        Umunaa-Uhi
3                     7.79    16,341     1,890   <0.01   0.01    0.137   <0.01   0.1   0.01   31.2   38.7   7.45   523     4.76   4.94   Clear   Odourless   31.6
        Owerre-Okwe
        Umuokpara
4       Ofeiyi-       6.78    16,280     1,437   <0.01   0.01    0.112   <0.01   0.0   0.01   30.9   45.2   7.05   411     3.39   5.27   Clear   Odourless   30.6
        Umuoleche
        Amano-
5                     7.05    16,653     1,202   <0.01   0.02    0.123   <0.01   0.1   0.01   32.2   38.5   7.11   689     4.54   3.56   Clear   Odourless   31.2
        Umukogwu
                                                         0.04-
FMEnv Limits           N/S    N/S        N/S     0.1             N/S     N/S     10    N/S    N/S    90     6.5-8.5 1000   N/S    N/S    Clear   Odourless   >45
                                                         0.06
               Source: Fieldwork, 2019




                                                                                 126
ANNEX XIV PROJECT OCCUPATIONAL HEALTH AND SAFETY (OHS) PLAN
1.0 INTRODUCTION
Every project poses its HSE risks. This plan was necessitated to meet up with OHS standards and to achieve the objectives set for the
proposed project. The project team shall undertake to ensure high performance standards and conformity with contract requirements
by managing the works in a systematic and thorough manner.

2.0 PROJECT DESCRIPTION
2.1 Purpose The purpose of this document is to describe the Project Occupational Health and Safety (OHS) plan for the proposed
bridge reconstruction and the specific management controls, risk control systems and workplace precautions required to ensure
compliance with Occupational Health and Safety Laws and Standards.

2.2 HSE Objectives

The Objectives for this plan are to:

         • Adopt a positive Health & Safety Culture.
         • Adopt the principles of prevention to avoid risk.
         • Complete the project without incident (Zero fatalities, Zero Lost Time Injury (LTI) or occupational illness).
2.3 Scope of Work

The Project Occupational Health and Safety (OHS) plan covers the scope of works defined in the contract. This includes
Preconstruction, Construction, Operation & Maintenance and Decommissioning phases.

2.4 Policy Statement In addition to the existing HSE policy, other policies shall be developed which includes:

          • Substance Abuse Policy – Prohibiting the consumption or possession of narcotics, drugs, alcohol and other banned
          substances
          • Emergency Response Policy – Stating commitment to ensure adequate resources and arrangement are in place in the case
          an emergency.
          • Community Affairs Policy – Stating commitment to foster healthy relationships with communities through observance of
          the highest standard of conduct.
          • Road Safety Policy–Stating commitment to complying with Road Traffic regulations and continuously improving its road
          safety performance by implementing a Road Safety Management Plan (RSMP)

3.0 KEY RESPONSIBILITIES
Involvement of all in implementing, maintaining and continually improving OHS processes is the key to successful completion and
achievement of quality objectives set by the management. All project personnel shall therefore be required to be familiar with the
content of this OHS plan and shall participate in implementing, maintaining and improving the management system. It is the
responsibility of the project manager and all key personnel to ensure that the requirements for quality are fulfilled for works under
their responsibility. All new staff and staff who are given new responsibilities are to be inducted into the requirements set out in this
plan in general and into their function and responsibilities in particular.

3.1 Project Manager Responsibilities

          • Set good example in HSE issues.
          • Ensure the availability of resources essential to establish, implement, maintain and improve the OHS Management
          System.
          • Define, document and communicate roles, allocate responsibilities and accountabilities, delegating authorities, to
          facilitate effective OHS management.
          • Ensure that all of the activities undertaken in the Project conform to Nigerian legislation, client requirements or
          international standards when applicable.
          • Review objectives achievements throughout the year.
3.2 Project Supervisors Responsibilities

          • Enforcing all phases of the established HSE plan.
                                                                  127
        • Set good example in HSE issues.
        • Preparing Job Hazard Analysis when required.
        • Ensuring the safety of all workers associated with the site.
        • Conducting HSE inspections.
        • Ensuring workers are competent for their allocated tasks.
        • Attending and participating in HSE meetings.
        • Participating in accident investigations.
3.3 HSE Manager/Supervisor Responsibilities

        • Prepare relevant OHS documentation and procedures.
        • Monitor the efficient implementation of OHS requirements.
        • Participate and organize the OHS risk assessments.
        • Advise management of compliance and of conditions requiring attention.
        • Conduct regular HSE inspections.
        • Make thorough analysis of statistical data and inspections; delineates problem areas; and makes recommendation for
        solutions.
        • Take part in the review of all OHS incidents and assist in investigating incident.
        • Monitor the efficient implementation of the Project’s OHS requirements.
        • Organize the Project’s OHS risk assessment exercises.
        • Check on the use of all types of personal protective equipment specifies the use of appropriate PPE for the various work
        activities. Evaluates their effectiveness and suggests improvements where indicated .
3.4 HSE Advisor Responsibilities

        • Check on the use of all types of personal protective equipment specifies the use of appropriate PPE for the various work
          activities. Evaluates their effectiveness and suggests improvements.
        • Conduct independent inspections to observe conformance with established OHS Plan and determines the effectiveness of
          individual elements of the plan (pre-task briefing, weekly toolbox talk, etc)
        • Establish contact with Subcontractors with the objective of maintaining good relations and coordination of accident
          prevention activities and compliance with the established OHS plan. • Correct unsafe acts and unsafe conditions.
        • Deliver HSE induction/orientation course to all employees, including subcontractors. • Deliver HSE awareness course and
          toolbox talk. • Advise employees on OHS matters.
3.5 All employees Responsibilities

          • Take all reasonable and practical steps to care for their own health and safety and avoid affecting the health and safety of
            coworkers and the general public.
          • Follow all instructions and use the equipment properly
          • Not interfere with any safety arrangements.
          • Report any circumstances which may not comply with the project’s OHS management system.

4.0 Competency
All personnel required to operate or work with any equipment or machine must be competent, be tested for each equipment that
he/she shall be operating. All personnel who as part of their profession require licensing or certification must obtain the necessary
certification before he/she shall be allowed to work on the site.

5.0 Fitness
All personnel working on site shall be required to be certified medically fit to do so by an approved medical facility or Medical
Doctor (pre-employment medical examination)

6.0 HSE Training

6.1 Induction/Orientation

Every new or rehired employee and Subcontractors employees must undergo mandatory OHS orientation / induction. The purpose of
the Induction is to educate workers and make them aware of the major potential hazards he or she shall come into contact with while
working on the site; also, it is one more opportunity to stress the importance of HSE being the first priority in the operations. The
content of the HSE orientation / induction shall cover the following subjects:


                                                                  128
          • Site safety rules.
          • Personnel protective equipment requirements (PPE).
          • Environmental sensitivity and protection.
          • Preparation and planning of the job (Daily Pre-task talk).
          • Emergency plan and muster points.
6.2 Project Specific HSE Training

In addition to the HSE orientation /induction, there shall be specific site HSE trainings which shall cover the following topics:

          • Manual handling.
          • Electrical Safety
           • Emergency Prevention, Preparedness and Response
          • Work at height training • First Aid training (for site First Aiders)
          • Lifting and Rigging
          • Safe Driving techniques (for drivers)

7.0 Hazard identification & HSE risk assessment

7.1 Project HSE Risk Assessment

The project HSE risk assessment shall be developed and recorded. The P roject’s HSE risk assessment shall be conducted by a team
consisting of HSE Manager/ Supervisor and technical managers/supervisors. It must be approved by the Project manager.

7.2 Fire Risk Assessment

A fire risk assessment shall be developed and recorded. A fire safety plan shall be in place in the site.

7.3 Job Hazard Analysis

Job hazard analysis is required when the hazards and risks associated with a specific task is to be identified so as to implement
control measures. The HSE department together with the technical managers/supervisors shall develop a job hazard analysis when
applicable.

8.0 EMERGENCY PREPAREDNESS AND RESPONSE

Emergency procedures and evacuation plan shall be developed by the HSE Department and displayed on the notice board. These
procedures shall be communicated to all staff. Also, each section/department shall have at least a trained first aider at all times.

9.0 HSE IMPLEMENTATION AND PERFORMANCE MONITORING

9.1 HSE Meetings HSE management meetings shall be held once a month. The meeting is to help identify safety problems, develop
solutions, review incident reports, provide training and evaluate the effectiveness of our safety program. Some of the meetings shall
be:

    • Project/Site Management HSE Meeting for management and supervision (Monthly).
    • Tool box talk meetings for all workforce (Weekly).
    • Pre-task briefing for all workforces (Daily).
    • Special situation meeting (As required).


9.2 HSE Reporting

All incidents and illnesses must be reported to site supervisor after which investigation shall commence and recorded so that appropriate
corrective actions shall be implemented to prevent any re-occurrence and report findings shall be forwarded to management for review.
Reporting requirements shall include notification of incident, investigation report, and monthly report. Notification of Incident form
shall be developed which shall be filled and submitted to HSE department for investigation.

                                                                   129
9.3 HSE Inspection and Audits

For continual improvement of HSE management system, HSE inspection and audit shall be conducted. An inspection checklist shall
be developed. This is to ensure that the HSE management system is being adhered to. The inspection shall be conducted by the HSE
department together with site management.

9.4 Corrective and Preventive Actions and Non-Conformities

During the cause of inspections, concerns raised shall be addressed and closed out. It is expected that in a period of two weeks, a
close out inspection shall take place to verify that the corrective actions have been closed.

10.0 Project HSE Rules

The project HSE rules shall be developed and supervision shall develop specific rules and procedures when necessary. The following
site rules shall be implemented at all times. The Site Manager shall draw these rules to the attention of their own workmen or staff.
All sub-contractors must ensure that these rules are drawn to the attention of their workmen and staff. The Principal Contractor may
implement additional site rules during the contract programme. Any such additional rules shall be notified to all personnel engaged
on the project prior to their implementation. The HSE rules shall include but not limited to:

        1. Personal Protective Equipment must be worn at all times.
        2. All instructions issued by the Site Manager regarding the storage, handling or cleaning of materials, plant and equipment
            must be followed.
        3. All vehicles must be parked in the designated areas.
        4. Any workman suffering from a medical condition that might affect his work and/or that could require specific Medical
            treatment must inform the supervisor before commencing work.
        5. All site tools shall either be battery operated or 110 volts.
        6. No one shall be permitted on site if it is believed that they are under the influence of alcohol or drugs.
        7. Vehicles must not reverse without a banksman in attendance.
        8. All visitors to site must undergo a site-specific induction and operative Identity badges must be worn at all times.
        9. All excavations must be secured.
        10. Smoking and eating shall only be permitted in the designated area. This area shall be identified during induction.
        11. All food and drink vendors on site shall be registered.
        12. The variant of food and drink to be sold in the sites must be approved by the HSE officer
        13. No hot works operations are permitted without a hot work permit in place.
        14. There shall be no radios or other music playing devices on site.
        15. Good housekeeping practices to be adopted.
        16. Compliance with all Ethical Power Permit to Work systems
        17. The site keyed access procedure must be strictly adhered to.
        18. All Contractors must comply with Site Health & Safety Guidelines / Site Safety Method Statement
        19. No untrained worker shall be permitted to operate heavy machineries.

11.0 SAFE WORK PRACTICES

Implementing safe work practices is one of the keys to achieving our HSE objectives and some of these safe work practices include:

11.1 Personal Protective Equipment (PPE)

The basic PPE required for the project shall be Safety Glasses, Safety Boots, Hand Gloves, Hard Hat and Coverall. Any other PPE
shall be used as applicable. Management is responsible for the provision of PPE and usage shall be enforced at all time. PPE shall be
provided in circumstances where exposure to hazards cannot be avoided by other means or to supplement existing control measures
identified by a risk assessment. An assessment shall be made to ensure that the PPE is suitable for purpose and is appropriate to the
risk involved. Information, instruction & training shall be given to all employees on safe use, maintenance and storage of PPE.
Employees shall, in accordance with instructions given, make full use of all PPE provided and maintain it in a serviceable condition
and report its loss or defect immediately to the maintenance department where it shall be replaced. PPE shall be replaced when it is no
longer serviceable and returned on a new for old basis. Employees shall sign to state that they have received PPE when issued.




                                                                 130
      12.0 WELFARE FACILITIES

      The provision of welfare facilities on the site shall be communicated to all operatives at site induction. A cleaning regime shall be
      implemented and maintained for the duration of the construction phase to ensure the site welfare facilities remain in a clean and tidy
      condition.

             •     If mains drinking water becomes unavailable during the construction phase bottled water shall be brought to site for all
                   operatives for the necessary period.
             •     All food and drink vendors on site shall be registered.
             •     The HSE officer will ensure that only approved vendors are allowed to sell food.
             •     The variant of food and drink to be sold on the sites must be approved by the HSE officer
             •     Access to the site should be restricted to avoid sale of contraband on site
             •     Smoking and eating shall only be permitted in the designated area. This area shall be identified during induction.


      13.0 SIGNAGE

      Adequate provision for warning and directional signs shall be made.

      14.0 PROJECT HSE PROCEDURES OHS procedures shall be developed. Project activities shall generally be controlled in
      accordance with OHS Procedures. These procedures shall include:

                 • Lifting and Rigging Procedure
                 • HSE Reporting Procedure
                 • Working at Height Procedure.
                 • Emergency Procedure.



      ANNEX XV BORROW PIT REMEDIATION PLAN
      (A)        Siting
      Specific locations of borrow areas to be used will be identified by contractor based on the recommendations of the ESIA report. In
      case the contractor or the contractor wants to open any new borrow areas other than mentioned in this report, and then the selection
      and recommendations for borrow areas will be based on environmental as well as civil engineering considerations.
      Certain precautions have to be taken to restrict unauthorised borrowing by the contractor and the contractor. No borrow area shall be
      opened without permission of the Engineer.
                                           Table 1: Probable Borrow Area along the Project Corridor

                               Site identification                    Approximate Quantity (Cum)
       Name                           Offset                             Available Surrounding
Sample         Materia Nearest        from
       of                                                                Land     / Land       / Remarks
no.            l type Chainage Left / nearest Length Breadth Depth Total
       Village                 Right           (m)   (m)     (m)   (Cum) Terrain Terrain
                       (Km.)          Chainage
                                      (m)


      (B)        Criteria for Evaluation of Borrow Areas
      i.     Existing land use (Agricultural / Barren / Scrub / grazing / any other type)
      ii.    Vegetation / trees to be removed
      iii.   Erosion/degradation potential
      iv.    Distance and name of the nearest settlement
      v.     Distance from the nearest surface water body
      vi.    Drainage pattern of the area

                                                                          131
vii.    Distance of the nearest Reserve Forest (if any)
viii.   Distance of the nearest Sacred Tree (if any)
ix.     Distance from the nearest school / hospital / primary health centre
x.      Daily / Occasional use of borrow area by the community
xi.     Any schemes or avenues for generation of income for adjoining community
(C)       Documentation of Borrow Pit
The contractor must ensure that following data based must be documented for each identified borrow areas that provide the basis of
the redevelopment plan.
 •      Chainage along with offset distance
 •      Area (in Sq m)
 •      Type of Access/width from carriageway
 •      Soil Type
 •      Slope / Drainage Characteristics
 •      Water Table of the area or identify from nearest well etc/ask people
 •      Existing Land-use such as barren/agricultural/grazing land
 •      Location/Name/Population of Nearest Settlement/Community & distance from Borrow Area/Type and characteristics of
        settlement
 •      Daily / occasional use of the Borrow Area by the community, if any
 •      Identification of any other community facility in the vicinity of the borrow pit
(D)       Guidelines for Stripping, Stocking, Preservation of Top Soil
During the excavation of the borrowing material contractor must ensure that the topsoil from all areas of cutting and all areas to be
permanently covered shall be stripped to a specified depth of 150mm and stored in stockpiles. At least 10% of the temporarily
acquired area shall be earmarked for storing topsoil. The stockpile shall be designed such that the slope does not exceed 1:2 (vertical
to horizontal), and the height of the pile is restricted to 2m.
(E)       Guidelines for Enhancement
As far as possible borrow area selected for enhancement shall be on government / community land in the vicinity of settlement. The
contractor must ensure that any enhancement design proposed should be workable, maintenance free and preferably worked out in
consultation with the community and proposed enhancement materials should be locally available. The borrow area can be
developed either of the following:
Vegetative Cover:
 •      Vegetative cover must be established on all affected land.
 •      Topsoil must be placed, seeded, and mulched within 30 days of final grading if it is within a current growing season or within
        30 days of the start of the next growing season.
 •      Vegetative material used in reclamation must consist of grasses, legumes, herbaceous, or woody plants or a mixture thereof.
 •      Plant material must be planted during the first growing season following the reclamation phase.
 •      Selection and use of vegetative cover must take into account soil and site characteristics such as drainage, pH, nutrient
        availability, and climate to ensure permanent growth.
 •      The vegetative cover is acceptable if within one growing season of seeding:
 •      The planting of trees and shrubs results in a permanent stand, or regeneration and succession rate, sufficient to assure a 75%
        survival rate;
 •      The planting results in 90% ground coverage.
 •    The site shall be inspected when the planting is completed and again at one year to ensure compliance with the reclamation plan.
Certificate of Completion of Reclamation
 •      Contractors have to obtained certificate of satisfaction from the landowner and submit it to the Engineer before final payment is
        to done.

                                                                     132
(F)      Drawings to be Prepared

 •      The contractor has to prepared the drawings showing both cross-section as well as plan of the identified borrow areas
        incorporating following inputs:
 •      Contours if any, depth if any
 •      Location of trees, height, foliage spread and afternoon shaded area on ground
 •      Any other existing details at the road / property interface such as signage/railing/etc.
 •      Details of immediate surrounding for at least 5m on either side.
(G)      Photographs to be Include
The contractor must ensure that photographs are to be taken before and after the excavation of borrow materials and also after the
implementation of redevelopment plan, incorporating the following:
 •      Overall View from access side
 •      Any other community resource in the vicinity
 •      All spots to be detailed such as access to borrow pit /cluster of existing trees etc.
(H)      OUTPUTS
The contractor must ensure based on the above-mentioned guidelines following outcomes must be evolved:
 •      Working plan
 •      Cross Section
 •      Longitudinal Section/Elevation of Site
 •      Details of all proposed Enhancements including signage etc.
 •      BoQ


ANNEX XVI WORKERS’ SITE MANAGEMENT PLAN
(A)         SITING

The contractor based on the following guidelines shall identify the location of the construction site. The construction site shall be
located:

      ▪ The construction camps will be located at least 500 m away from habitations at identified sites. The living accommodation and
         ancillary facilities for labour shall be erected and maintained to standards and scales approved by the resident engineer.

      ▪ On non-agricultural lands, as far as possible
      ▪ Not within 1000m of either side of locations of Forest areas.
      ▪ All sites used for camps must be adequately drained. They must not be subject to periodic flooding, nor located within 300 feet
         of pools, sink holes or other surface collections of water unless such water surface can be subjected to mosquito control
         measures.
      ▪ The camps must be located such that the drainage from and through the camps will not endanger any domestic or public water
         supply.
      ▪ All sites must be graded, ditched and rendered free from depressions such that water may get stagnant and become a nuisance.
(B)         LAYOUT

A conceptual layout of a typical construction site has been presented in Figure A. The Contractor during the progress of work will
provide, erect and maintain necessary (temporary) living accommodation and ancillary facilities for labour to standards and scales
approved by the engineer. All temporary accommodation must be constructed and maintained in such a fashion that uncontaminated
water is available for drinking, cooking and washing. Safe drinking water should be provided to the dwellers of the construction camps.
Adequate washing and bathing places shall be provided, and kept in clean and drained condition. Construction camps are to be sited

                                                                     133
    away from vulnerable people and adequate health care is to be provided for the work force.

    Sanitation Facilities: Construction camps shall be provided sanitary latrines and urinals. Sewerage drains should be provided for the
    flow of used water outside the camp. Drains and ditches should be treated with bleaching powder on a regular basis. The sewage
    system for the camp must be properly designed, built and operated so that no health hazard occurs and no pollution to the air, ground
    or adjacent watercourses takes place. Compliance with the relevant legislation must be strictly adhered to. Garbage bins must be
    provided in the camp and regularly emptied and the garbage disposed off in a hygienic manner

    Shelter at Workplace: At every workplace, there shall be provided free of cost, four suitable shelters, two for meals and two others for
    rest, separately for use of men and women labourers. The height of shelter shall not be less than 3m from floor level to lowest part of
    the roof. Sheds shall be kept clean and the space provided shall be on the basis of at least 0.5m 2 per head.

    Canteen Facilities: A cooked food canteen on a moderate scale shall be provided for the benefit of workers wherever it is considered
    necessary. The contractor shall conform generally to sanitary requirements of local medical, health and municipal authorities and at
    all times adopt such precautions as may be necessary to prevent soil pollution of the site.

    First aid facilities: At every workplace, a readily available first-aid unit including an adequate supply of sterilized dressing materials
    and appliances will be provided as per the Factory Rules. Workplaces remote and far away from regular hospitals will have indoor
    health units with one bed for every 250 workers. Suitable transport will be provided to facilitate taking injured and ill persons to the
    nearest hospital. At every workplace an ambulance room containing the prescribed equipment and nursing staff will be provided.

    Health Care Facilities: Health problems of the workers should be taken care of by providing basic health care facilities through health
    centres temporarily set up for the construction camp. The health centre should have at least a doctor, nurses, duty staff, medicines and
    minimum medical facilities to tackle first-aid requirements or minor accidental cases, linkage with nearest higher order hospital to
    refer patients of major illnesses or critical cases.

    The health centre should have MCW (Mother and Child Welfare) units for treating mothers and children in the camp. Apart from this,
    the health centre should provide with regular vaccinations required for children.


    ANNEX XVII                       WASTE MANAGEMENT PLAN

S/N      Potential Source               Waste Type          Waste Streams                           Management
         A PRECONSTRUCTION
1        Movement of vehicles on        Emission            COx, SOx, NOx, CO, Dust                 Use water suppression to prevent dust emission Maintain
         unpaved surface and engine                                                                 vehicles and machineries to reduce emission Maintain low
         exhaust                                                                                    speed to reduce dust and gaseous emission Allow aerial
                                                                                                    dispersal over a large area.
2        Site Clearing and              Non-Hazardous          Vegetal Waste                        Vegetal waste shall be supplied to farmers for use as
         Installation of temporary                                                                  compost.
         workers camp and offices                                                                   Woody vegetal shall be supplied to host communities for
         and workshops                                                                              domestic uses including as fuel wood for cooking.
                                                                                                    Segregated and stored on site to be collected at least once a
                                                               Industrial Waste: Metal scraps,
                                                                packaging waste
                                                                                                    facilities.
3        Workers’ camp                  Domestic and          Food remnant, kitchen wastes.         To be transferred to locals for use as compost and animal
                                        Sanitary              Food packaging etc                    feed.
                                                                                                    Plastic and other packaging to be recycled through licensed
                                                                                                    recycling third parties.
                                                              Domestic Sewage                       Temporary stored and transferred to licensed carrier for
                                                                                                    disposal
B        CONSTRUCTION
1        Movement of vehicles on        Emission            COx, SOx, NOx, CO, Dust                 See A1
         unpaved surface and engine
         exhaust
2        Civil works                    Non-Hazardous         Spoils                                Reuse spoils as fill materials as much as possible
                                        /Industrial           Waste Packaging and Dunnage           Segregated and kept securely in closed containers on site. To
                                                              such as scrap wood, scrap             be transferred to approved recycling third parties for
                                                              metal, steel, glass, plastic, paper   reuse/recycling.
                                                              and cardboard empty metal             Non-recyclables to be removed by approved waste contractor
                                                              containers , excess concrete,         for onward disposal at approved sites.
                                                                       134
                                                              broken equipment, or
                                                              components                            To be transferred to locals for use as compost and animal
         Workers’ camp/offices                                Domestic-type waste:                  feed.
                                                              wastepaper and food scraps,
                                                              metal cans                            recycling third parties.
3        Civil Works                    Hazardous           Solid Wastes: used batteries,           Store on site in closed containers with secondary containment and
                                        Waste               chemical containers, concrete etc       transferred to a registered waste contractor with off-site permitted
                                                                                                    hazardous waste treatment storage, or disposal
                                                            Liquid Waste: spent lubricating         facilities
                                                            oils, hydraulic fluids, brake fluids,
                                                            battery electrolyte, and dielectric
1.    ANNEX XVIII: ENVIRONMENTAL AND SOCIAL SCREENING FOR IMO STATE RAMP2 RIVER CROSSINGS
B     General Information/Project Brief
                                                                                                                                     Agbata-Umuigwe Na Uzoagba /3(3m x
1.    Name of Project                                                                                                                3.5m)
2.    Location of Hydraulic Structures                                                                                               See Final Prioritization Report
3.    Dimensions of Hydraulic Structures                                                                                             3(3m x 3.5m)
B.    SCREENING QUESTIONS                                                                                                            Yes     No       N/A      Remarks
      Project Location
1.    What is the nearest habitation? Name type of premises                                                                                                    House
2.    Approximate distance to the nearest premises                                                                                                             300m
3.    Is the proposed road on a slope?                                                                                               X
4.    Adjacent to or within any Environmentally Sensitive Area
      4.1: Protected Area                                                                                                                      X
      4.2: Wetland/Floodplains                                                                                                       X
      4.3: Buffer Zone of Protected Area                                                                                                       X
      4.4: Special Area for Protecting Biodiversity                                                                                            X
      4.5: Bay/Lagoon                                                                                                                          X
      4.6: Rivers/Waterways/Canals                                                                                                   X
      4.7: Coastal Zone                                                                                                                        X
5.    Affect to Natural Biological Environment
      5.1: Wildlife Habitat                                                                                                                    X
      5.2: Ecology of Fisheries                                                                                                                X
      5.3: Threatened and Endangered Species                                                                                                   X
      5.4: Trees on Proposed Road RoW                                                                                                X
6.    Adjacent to or Within any Historic Culturally Important Site                                                                              X
7.    Any Health Centre in the Community?                                                                                                       X
      Name of Place       Location (Chainage) Existing conditions, problems and causes of problems:                                  Potential problem from road works:
      Villages along      Villages along the        Dust and noise from construction activities may affect health of community and   Dust and noise from construction activities may not
      the route           route                     health centre patients-                                                          affect health of community and health centre patients
8.    Any Displacement/Resettlement of Activities? Compensation Issues?                                                                        X
9.    Economics and Environment (List)                                                                                                         X
      9.1: Might the proposed activity cause elimination or relocation                                                                         X
      9.2: Might the activity cause generation of employment?                                                                            X
      9.3: Might the activity cause reduction in employment?                                                                                   X
      9.4: Might the proposed activity cause generation of social conflicts?                                                                   X
10.   General (Positive Impacts). Will the project create:
      10.1: Create job opportunities to support the enhancement of living standard of the community                                      X
                                                                                      135
      10.2: Contribute to poverty reduction in the project areas                                                                          X
      10.3: Contribute to sustainable development                                                                                         X
11.   Soil and Water Resources
      11.1: Surface Water Hydrology                                                                                                           X
      11.2: Surface Water Quality                                                                                                             X
      11.3: Ground Water Quality                                                                                                              X
      11.4: Soil Erosion                                                                                                                      X
      11.5: Geology                                                                                                                           X
      11.6: Climate                                                                                                                           X
12.   Environmental Hazard or Pollution Threat
      12.1: Might the activity cause an increase or probability of increase of Environmental hazard                                               X
      12.2: Might the activity be susceptible to environmental hazard due its location                                                            X
      12.3: Might the activity affect the quality of water resources within, adjacent to or near the project area                                 X
      12.4: Might the activity result in a deleterious effect on the quality of any water resources/watershed area                        X
13.   Resources Conservation and Use
      13.1: Might the activity affect commercial fisheries or aquaculture resources or production                                         X
      13.1: Might the activity affect cultural activities and/or resources                                                                        X
14.   Air Quality and Atmospheric Environment
      14.1: If the activity results in the generation of dust, will it affect the project area, immediate adjacent areas? Who readily?    X
      14.2: If the activity results in the generation of noise, will it affect the project area, immediate adjacent areas? Who readily?           X
15.   Community Facilities/Services/Open Spaces/Recreations
      15.1: Might the proposed activity result in change in community facilities, services or institutions?                                       X
      15.2: Might any impacts to existing community structures/business enterprises or housing?                                                   X
      15.3: Will the activity result in impact to lifestyle values system?                                                                        X
      15.4: Might any site/open space/use of access or recreation areas significance be affected?                                                 X
16.   Visual Resources/Aesthetics of the Site
      16.1: Might the activity cause a change in the visual character in or near the area through alteration?                                     X
      16.2: Might the activity affect views or access to views of natural or cultural landscape features?                                         X
      16.3: Might the activity introduce new materials, colours and forms to the immediate landscape?                                             X




                                                                                           136
ANNEX XIX                   RAP SCREENING REPORT FOR RIVER CROSSINGS

         a) Project Right of Way (ROW)
The FPMU and the SPIU gave the defined ROW as 8m width for the road approach which is 100 meters to the River
crossings on both sides. An additional 2m was provided to enable maneuverability of heavy plant and equipment,
during RCs construction/rehabilitation. Thus, ROW is 10m for the RCs and 8m for the approach roads.

        b) Identification of Project Affected Persons (PAPs)
The approach to be used identifying the PAPs, adopted the following outline:
    • Community sensitization to enlighten the public of the proposed project and the RAP exercise
    • On the field assessment with the community members to determine the project’s ROW and assets to be
        affected;
    • An inventory and categorization of the PAPs and assets to be affected

          c) Potential Impacts
This section outlines the potential negative impacts that are anticipated and will be associated with the construction
of River Crossings. The impacts will be related to activities carried out during construction, commissioning,
operations, maintenance and decommissioning phases. This is outlined in the Table below and discussed in subsequent
sections. Some photos of the priority sites can be found in the appendix.

RAP Screening Result
S/N Name of Priority Site               LGA                           RAP? Reason                         No of PAP
    Lot 1
1   Agbata-Umuigwe Na Uzoagba           Ikeduru/Mbatoli               No    Existing road                 N/A
2   Okwu-Umuonohor                      Ikeduru/Mbatoli               No    Existing road                 N/A
3   Orie Mbieri-Umuomumumbieri          Ikeduru/Mbatoli               No    Existing road                 N/A
4   Ekwe-Okwuodor                       Njaba/Isu/Nkwere/Nwangele No        Existing road                 N/A
5   Umuduruemghara-Okpala Anara         Isiala Mbano/Ehime Mbano No         Existing road                 N/A
6   Umuihim Autonomous                  Isiala Mbano/Ehime Mbano No         Existing road                 N/A
    Community – Umukaku
7   Umulogho-Okwuohia                   Aniri/Agwu                    Yes Economic trees and cultural 4
                                                                          area
    Lot 2
1   Uzurunamu-Okwudo Mgbidi             Oru East/Oru West/Orsu        Yes Economic trees and cultural 4
                                                                          area
2   Akama-Nansa-Akwa Ihedi              Orsu                          Yes Economic trees              1
3   Igbee-Amaruru                       Orsu                          Yes Economic trees                  2
4   Ndiuche-Izuogu Uri                  Ideato North/South            Yes Economic trees                  2
5   Obinugwu-Umueshi-Okwa               Ideato North/South            Yes Economic trees                  1
6   Dikenafai-Abba Nwagele              Ideato North/South            No Economic trees and oil           1
                                                                          processing plant
7   Dimagu-Nkwere                       Ideato North/South            Yes Economic trees and              1
                                                                          farmland
    Lot 3
1   Umueziogwu-Uzoagba-                 Owerri East/West              Yes Economic trees                  1
    Okitankwo-Umunahu
2   Umuebee-Umuhu                       Owerri East/West              Yes Economic trees                  3

                                                        137
3   Ugbele-Bsc                            Ideato South                  No Existing road                N/A
4   Amagu-Umulebe                         Ideato South                  Yes Economic trees and cultural 3
                                                                            area
    Lot 4
1   Ndikpa Umucheke-Okiu                  Onuimo                        No  Existing road                    N/A
2   Ukolu-Umucheke                        Onuimo                        No  Existing road                    N/A
3   Umunaa-Uhi Owerre-Okwe                Onuimo                        No  Existing road                    N/A
4   Umuokpara Ofeiyi-Umuoleche            Okigwe                        Yes Economic trees and               6
                                                                            farmland
5   Amano-Umukogwu                        Okigwe                        Yes Economic trees and               1
                                                                            farmland
Total                                                                                                        30

As shown in the table, resettlement will be required in 12 priority sites as the proposed project will lead to the removal
of economic trees and farmlands and impact on cultural areas in these sites. This project affects 30 people, thus, a
Resettlement Action Plan (RAP) is required.

        d) Impact on Shrine and Cultural Areas
Impact on shrines and cultural areas are envisaged in one priority site. This is a community where the River is
worshipped. The priority site and the River name is outlined in the table below

Impact on shrines and cultural areas
 S/N    Priority site                                       LGA                           Name of River           No of PAP
 1      Uzurunamu-Okwudo Mgbidi                             Oru East/Oru West/Orsu        Obana                   1
 Total                                                                                                            1

          e) Land take
The project will not involve significant land acquisition because the reconstruction of drainage, culvert and road
approaches will be carried out on the existing road in the project area of influence. However, minimal land acquisition
will be required in three priority sites without existing motorable roads

Land Take
 S/N   Priority site                                                   LGA                            No of PAP
 1     Umuokpara Ofeiyi-Umuoleche                                      Okigwe                         1
 2     Igbee-Amaruru                                                   Orsu                           1
 3     Umueziogwu-Uzoagba-Okitankwo-Umunahu                            Owerri East/West               1
 Total                                                                                                3

          f) Impact on Livelihood
The proposed project will lead to the removal of economic trees in the twelve (12) priority sites. The affected
economic trees include bamboo, oil palm among others. Farmlands and sand mining activities will also be affected
in three sites as shown in the table below

Impact on Livelihood
S/N Name of Priority Site                     LGA                             Farmland            Sand mining      Economic trees
    Lot 1
1   Umulogho-Okwuohia                         Aniri/Agwu                      -                   1
    Lot 2
2   Uzurunamu-Okwudo Mgbidi                   Oru East/Oru West/Orsu          1
3   Akama-Nansa-Akwa Ihedi                    Orsu                            -
                                                          138
4        Igbee-Amaruru                       Orsu                           1
5        Ndiuche-Izuogu Uri                  Ideato North/South             -
6        Obinugwu-Umueshi-Okwa               Ideato North/South             -
7        Dimagu-Nkwere                       Ideato North/South             -
         Lot 3
8        Umueziogwu-Uzoagba-Okitankwo-       Owerri East/West               -
         Umunahu
9        Umuebee-Umuhu                       Owerri East/West               -
10       Amagu-Umulebe                       Ideato South                   -
         Lot 4
11       Umuokpara Ofeiyi-Umuoleche          Okigwe                         1
12       Amano-Umukogwu                      Okigwe                         -
Total                                                                       3

         g) Recommendations
Based on the above screening results and with the identified potential negative impacts, efforts should be made in line
with the policy of the project RPF to reduce/avoid impacts as follows:

     •     Consultation with the community leaders and village priests on the customary rights to be performed before
           work can be carried out across the Rivers in question
     •     To alter alignments and technical designs to avoid displacement as much as possible within the ROW
     •     Application of appropriate technology to reduce impact on structures through vibrations
     •     Precise scheduling of construction to secure access to community members and transporters
     •     Pre-construction street meetings and adequate notification
     •     Hands on social monitoring and supervision
     •     Alternative diversionary routes/access bridge will be created during the construction phase.
     •     The public will receive prior notification of temporary disruptions to access and be agreed with the PIU &
           Contractor.
     •     Prior to commencing work, the Contractor will prepare a Traffic Management Plan which will detail how
           traffic delays, the occasional need for temporary road closure and the use of diversionary routes will be
           managed as much as possible through sensitization and awareness campaign of the communities residing
           along the corridor of roads under construction.




                                                         139
ANNEX XX PICTURE OF BOA




Boa constrictor (Boa constrictor)

In parts of Imo and Anambra States, Boas and Pythons (locally called Eke) are worshipped and
regarded as both the totem of the deity or the reincarnation of the ancestors. The Boas and Pythons
roam about even into people’s bedrooms, causing no harm to the people and being certain that no
harm would be done them. These snakes are non-venomous and harmless.




                                               140
              ANNEX XXI LOCATION OF PROPOSED STAGING AREA, BASE CAMP AND PCR
S/N Name of Priority Site   X       Y        X       Y       X       Y       X    Y     X       Y        X         Y       X       Y       X       Y
                              Intervention    Staging Area   Base Camps          PCR        Borrow pit       Env & Social Alternative route Public Utility
                                  sites                                                                      Sensitivities
                            Lot 1
1    Agbata-Umuigwe Na
                            5.5471 7.1456 5.543 7.145        5.582 7.066                5.578   7.137    5.547     7.149
     Uzoagba
2    Okwu-Umuonohor         5.5387 7.1941 5.538 7.196        5.545 7.151                5.631   7.363    5.573     7.029
3    Orie Mbieri-
                            5.5834 7.0635 5.5873 8.0636 5.5834 7.0633                   5.667   7.049    5.581     7.363
     Umuomumumbieri
4    Ekwe-Okwuodor          5.7258 7.0270 5.724 7.037        5.723 7.033                5.667   7.049    5.723     7.029   5.719   7.026
5    Umuduruemghara-
     Okpala Anara           5.7103 7.1796 5.706 7.181        5.705 7.178                5.701   7.204    5.71      7.179
6    Umuihim Autonomous
                                                                                        5.631   7.363
     Community – Umukaku    5.6694 7.2050 5.666 7.208        5.667 7.202                                 5.584     7.061
7    Umulogho-Okwuohia      5.5856 7.3613 5.585 7.364        5.583 7.36                 5.519   7.138    5.673     7.202
                             Lot 2
1    Uzurunamu-Okwudo
     Mgbidi                 5.7259 6.8821 5.715 6.893        5.714 6.892 5.717 6.89     5.703   6.972    5.718     6.892   5.896   6.959
2    Akama-Nansa-Akwa
     Ihedi                  5.8850 7.0069 5.880 7.002        5.884 7.006                5.859   7.116    5.834     7.121
3    Igbee-Amaruru          5.8896 6.9688 5.883 6.969        5.887 6.974                5.859   7.116    5.891     6.964
4    Ndiuche-Izuogu Uri     5.8231 7.1783 5.818 7.186        5.829 7.12                 5.843   6.982    5.818     7.186
5    Obinugwu-Umueshi-
     Okwa                   5.8356 7.1244 5.831 7.126        5.829 7.12                 5.763   7.223    5.829     7.121
6    Dikenafai-Abba
     Nwagele                5.7543 7.1482 5.75 7.146         5.781 7.105                5.629   7.363    5.75      7.146
7    Dimagu-Nkwere          5.7847 7.1121 5.781 7.105        5.818 7.186                5.629   7.363    5.781     7.105   5.716   6.905
                            Lot 3
1    Umueziogwu-Uzoagba-
     Okitankwo-Umunahu    5.5140    7.1067   5.857   7.089   5.515   7.089              5.858   7.117    5.516     7.098   5.509   7.104
2    Umuebee-Umuhu        5.5471    7.1457   5.794   7.146   5.543   7.146              5.799   7.065    5.547     7.149
3    Ugbele-Bsc           5.8014    7.0774   5.543   7.147   5.799   7.668              5.543   7.065    5.80      7.018
4    Amugu-Umulebe        5.8603    7.1425   5.857   7.146   5.858   7.146              5.515   7.089    5.862     7.139   5.86    7.132
                           Lot 4
1    Ndikpa Umucheke-Okiu 5.7923    7.1957 5.793 7.194       5.791 7.197                5.801   7.190    5.794     7.195   5.794   7.192
2    Ukolu-Umucheke       5.7818    7.1952 5.782 7.194       5.774 7.209                5.774   7.209    5.783     7.194
3    Umunaa-Uhi Owerre-
     Okwe                 5.7978    7.2101 5.799 7.208       5.797 7.212                5.820   7.233    5.799     7.210
4    Umuokpara Ofeiyi-
     Umuoleche            5.8311    7.3291 5.833 7.319       5.818 7.318                5.318   7.318    5.853     7.319
5    Amano-Umukogwu       5.8539    7.3193 5.855 7.318       5.844 7.310                5.844   7.310    5.853     7.318   5.851   7.323




                                                                                  141
      ANNEX XXII                              LABOUR INFLUX MANAGEMENT PLAN
      This plan identifies labour requirements and sets out the procedures for addressing labour conditions and risks associated with the proposed project,

SUB-CATEGORY             WORKER                           PROJECT                          MITIGATION MEASURES                             MONITORING         MONITORING         RESPONS-
                         IMPACTS\RISKS                    IMPACTS\RISKS                                                                                       FREQUENCY          IBILITY

Employment               Influx of many foreigners        Competition on livelihood        60% of unskilled labour shall be from the       Verify             Onset of Project   ESO; SSO
                         into project community           and job opportunity with         project community. Where possible                                  and bi-weekly
                                                          locals                           qualified skilled workers on contract shall
                                                                                           also be sourced within the community

Housekeeping.            The general appearance of        The overall camp experience      Ensure that camp grounds and common             Verify             Monthly            ESO; SSO
                         the camp deteriorates making     is compromised which in          areas are routinely cleaned and organised
                         camp life unpleasant.            turn leaves workers              with appropriate signage in place, and that
                                                          demoralized and                  grounds are maintained (e.g., grassed areas
                                                          unproductive.                    are regularly mown).

                                                                                           Establish easily accessible, designated
                                                                                           smoking areas which are clearly highlighted
                                                                                           and regularly cleaned.

Recreation.              Workers spend most of their      Tensions arise from the local    Provide appropriate recreational facilities     Assessment         Quarterly          ESO; SSO
                         time in the camps and could      communities as workers           and activities. These should be discussed
                         become disenchanted and          impact their activities in       with the camp residents committee.
                         bored. They may want to          search of recreation. An
                         leave the camps and go into      increase in alcohol
                         the local towns and villages     consumption and prostitution
                         in search of recreation.         could result due to the influx
                                                          of workers into local
                                                          communities.

Spiritual /Religion.     Workers will want access to      Tensions arise from the local    Provide appropriate places of worship           Assessment         Quarterly          ESO; SSO
                         places of worship for their      communities as workers           where residents express a need for this in
                         chosen religion. They may        impact their activities.         accordance with cultural sensitivities, and
                         leave the camps and go into                                       assess transport arrangements on a case-by-
                         the local towns and villages                                      case basis.
                         in search of an appropriate
                         place of worship.                                                 Ensure that equipment and facilities are kept
                                                                                           clean and well maintained.


                                                                                              142
SUB-CATEGORY           WORKER                            PROJECT                          MITIGATION MEASURES                            MONITORING   MONITORING   RESPONS-
                       IMPACTS\RISKS                     IMPACTS\RISKS                                                                                FREQUENCY    IBILITY

Security.              Inconsistent and aggressive       Insufficient training and        Ensure that camp security personnel meet at    Assessment   Quarterly    ESO; SSO
                       behaviour of security             control of security personnel    least the following requirements:
                       personnel towards workers         can lead to the inappropriate    • Have not been implicated in past abuses
                       can result in tensions and        use of force, while protecting   • Are trained in appropriate conduct towards
                       conflict in the workplace and     Project workers and assets,      workers and community members
                       a perception of human rights      or inappropriate behaviour       including:
                       abuses.                           towards local populations,       o Exercising constraint and caution and
                                                         resulting in human rights        understand how force may be used
                                                         claims.                          o Respecting human rights
                                                                                          o Behaving consistently
                                                                                          o Knowing and abiding by applicable laws
                                                                                          o Fostering good community relations
                                                                                          through their interaction and behaviour
                                                                                          towards the workforce and communities
Community relations.   Communities are negatively        Workers are stopped from         Implement control measures to avoid and        Assessment   Quarterly    ESO; SSO
                       impacted by camp activities:      going to work, which affects     minimise the impacts of camp and living
                       noise, waste, traffic, lighting   productivity.                    conditions on communities.
                       and so forth. This may result
                       in negative actions towards                                        Limit foreign worker interaction with
                       camp operations such as road                                       communities and provide cultural sensitivity
                       closures and the prevention                                        awareness training to facilitate appropriate
                       of workers or suppliers from                                       interaction with communities.
                       entering the worksite.




                                                                                            143