The World Bank                                                                             Implementation Status & Results Report
           Second Bridges Improvement and Maintenance Program (P161929)



Second Bridges Improvement and Maintenance Program (P161929)

 SOUTH ASIA | Nepal | Transport Global Practice | Requesting Unit: SACNP | Responsible Unit: GTR06
 IBRD/IDA | Program-for-Results Financing | FY 2019 | Team Leader(s): Oceane Keou


 Seq No: 1 | ARCHIVED on 01-Mar-2019 | ISR35056 | Created by: Oceane Keou on 26-Nov-2018 | Modified by: Oceane Keou on 26-Feb-2019




 Program Development Objectives

  Program Development Objective (from Program Appraisal Document)
  To provide safe, resilient and cost effective bridges on Nepal's Strategic Road Network.



 Overall Ratings

 Name                                                                        Previous Rating                         Current Rating

 Progress towards achievement of PDO                                         --                                      Satisfactory
 Overall Implementation Progress (IP)                                        --                                      Moderately Satisfactory


 Implementation Status and Key Decisions
  The Project Development Objective (PDO) is to provide safe, resilient, and cost-effective bridges on Nepal’s Strategic Roads Network. To
  achieve this objective, year one of the operation focuses on the completion of (a) backlog bridges works (around 1,700 m) and (b) activities under
  the IPF component: addressing Department of Roads' (DOR) capacity gaps, preparation of new designs/standards, Occupational and Community
  Health and Safety (OCHS) guidelines, feasibility studies.
  As the project was just launched and became effective in December 2019, the mission assessed that the PDO is on track to be achieved. DOR
  initiated several project activities in a timely manner and good progress has been made in the construction of backlog bridges to be completed
  during the first year of implementation. Lastly, relevant consulting services are expected to be procured in time under the Investment Project
  Financing (IPF) component as required.


 Data on Financial Performance

 Disbursements (by loan)

 Project      Loan/Credit/TF      Status      Currency       Original   Revised      Cancelled      Disbursed     Undisbursed               % Disbursed

 P161929      IDA-63170           Effective   USD             133.00      133.00             0.00        0.00            130.99                        0%


 Key Dates (by loan)
 Project       Loan/Credit/TF     Status      Approval Date      Signing Date      Effectiveness Date      Orig. Closing Date     Rev. Closing Date

 P161929       IDA-63170          Effective   26-Sep-2018        14-Nov-2018       03-Dec-2018             15-Jul-2023            15-Jul-2023



 Program Action Plan


3/1/2019                                                                                                                     Page 1 of 13
           The World Bank                                                                         Implementation Status & Results Report
           Second Bridges Improvement and Maintenance Program (P161929)


                            All Program implementing units equipped with mobile tablets and BSMS made operational in all Program
  Action Description
                            implementing units including DROs, Bridge Sector Offices, and Bridge Branch Headquarters.

  Source                    DLI#                   Responsibility           Timing                  Timing Value               Status

                                                                                                    Initial accomplishment
                                                                                                    within 9 months of
  Technical                                        Bridge Branch            Other                   effective date and         In Progress
                                                                                                    subsequent use for
                                                                                                    duration of Program.

                            Initial milestone: At least 5 complete BSMS reports filed per DRO and Bridge Sector office.
  Completion
  Measurement
                            Measure of sustainable use: At least 2 reports per month per bridge site with active works contracts.

  Comments



                            The DOR to establish a DATC within Bridge Branch, satisfactory to the Association, for insourcing a fraction of
  Action Description        bridge-related engineering tasks and developing the capacity of junior engineers, with a particular focus on training
                            and developing femal

  Source                    DLI#                   Responsibility           Timing                  Timing Value               Status

                                                                                                    First cohort
                                                                                                    (approximately 5–10
                                                                                                    engineers or
                                                                                                    specialists) recruited
                                                                                                    within 18 months of
                                                   DOR’s office of the
  Technical                                                                 Other                   effective date.            In Progress
                                                   Director General
                                                                                                    Subsequent cohorts
                                                                                                    recruited annually with
                                                                                                    approximately 5–10
                                                                                                    engineers or specialists
                                                                                                    per cohort.

                            (a) Endorsement of DATC ToRs by Secretary of MoPIT through official letter to all DOR units;
  Completion
                            (b) Initial and subsequently annual recruitment of the DATC cohort completed; and
  Measurement
                            (c) Cohorts to target not less than one-third female participants.

  Comments



                            The DOR to update Bridge Policy and Strategy with additional focus on resilient systems approach and the principles
  Action Description
                            that will be applied to achieving resilience in subsidiary plans.

  Source                    DLI#                   Responsibility           Timing                  Timing Value               Status

                                                                                                    Within 24 months of
  Technical                                        Bridge Branch            Other                                              In Progress
                                                                                                    effective date

  Completion                Official promulgation of updated Bridge Policy and Strategy by MoPIT Secretary.
  Measurement



3/1/2019                                                                                                                  Page 2 of 13
           The World Bank                                                                       Implementation Status & Results Report
           Second Bridges Improvement and Maintenance Program (P161929)



  Comments



                            The DOR to update CMS and FMIS software and to relaunch the updated CMS and FMIS. The Program’s contracts
  Action Description
                            and financial transactions will use the CMS/FMIS.

  Source                    DLI#                  Responsibility           Timing                 Timing Value               Status

                                                                                                  Revised CMS/FMIS
                                                                                                  software launched
                                                                                                  within 18 months. All
                                                  DOR’s office of the                             contracts and
  Fiduciary Systems                                                        Other                                             In Progress
                                                  Director General                                transactions through
                                                                                                  the FMIS/CMS within
                                                                                                  24 months of effective
                                                                                                  date.

  Completion                Confirmation letter from MoPIT secretary regarding relaunch of the updated CMS and FMISs. All Program contracts
  Measurement               to be covered under the CMS/FMIS with all Program transactions made through the FMIS.

  Comments



                            BB to operationalize PAT for all Program contracts and include summaries of contracts in Trimester Reports.The PAT
  Action Description        will be used until CMS/BSMS are fully able to incorporate reporting on fiduciary,technical,environment/social
                            performance of contractor

  Source                    DLI#                  Responsibility           Timing                 Timing Value               Status

                                                                                                  Within 12 months of
  Fiduciary Systems                               Bridge Branch            Other                  effective date and         In Progress
                                                                                                  continuously thereafter

  Completion                PAT outputs included in Trimester Reports.
  Measurement

  Comments



                            DOR’s outstanding audit observations up to FY 2017/18 and each subsequent fiscal year are recorded annually and
  Action Description
                            addressed as part of continuously monitored plan to reduce audit observations.

  Source                    DLI#                  Responsibility           Timing                 Timing Value               Status

                                                                                                  Within 18 months of
  Fiduciary Systems                               DOR                      Other                  effective date and         In Progress
                                                                                                  annually thereafter

  Completion                FMIS to record audit observations, spreadsheet tool to track action against addressing audit observations.
  Measurement

  Comments




3/1/2019                                                                                                                Page 3 of 13
           The World Bank                                                                       Implementation Status & Results Report
           Second Bridges Improvement and Maintenance Program (P161929)


                             Contractor market assessment updated, and recommended procurement strategy developed for future DOR bridge
  Action Description
                             works (including those under potential major projects).

  Source                     DLI#                  Responsibility          Timing                 Timing Value               Status

                                                                                                  Within 18 months of
  Fiduciary Systems                                Bridge Branch           Other                                             In Progress
                                                                                                  effective date

  Completion                 Final report endorsed by the MoPIT and presented to the NPC and the MoF. Revised report approved by the NPC.
  Measurement

  Comments



  Action Description         Prepare and approve the business plan for GESU for the next three years.

  Source                     DLI#                  Responsibility          Timing                 Timing Value               Status

  Environmental and Social                                                                        Within 12 months of
                                                   GESU                    Other                                             In Progress
  Systems                                                                                         effective date

  Completion                 Business Plan approved by the DOR DG
  Measurement

  Comments



                             Revise bidding documents with distinct reflection of costs for OCHS, environmental and social management
  Action Description
                             mitigation cost in the BoQs, and inclusion of relevant provisions under the conditions of contract.

  Source                     DLI#                  Responsibility          Timing                 Timing Value               Status

  Environmental and Social                         DOR/Bridge
                                                                           Due Date               30-Sep-2018                Delayed
  Systems                                          Branch/GESU

  Completion                 Revised bidding documents in practice
  Measurement

                             GESU with support from BB are in the process of reviewing and finalizing the revised bid documents incorporating
  Comments
                             Environmental, Social, Health and Safety provisions by Feb 28, 2019.



                             The DOR’s ESMF updated (in whole or with addendum) to include enhanced provisions relating to OCHS, labor
  Action Description         camp management, CE protocol, provisions on the prevention of child labor, provisions on prevention of GBV and
                             SEA.

  Source                     DLI#                  Responsibility          Timing                 Timing Value               Status

  Environmental and Social                                                                        Within 24 months of
                                                   MoPIT/GESU              Other                                             In Progress
  Systems                                                                                         effective date

  Completion                 Official approval of updated ESMF (in whole or with addendum) by the MoPIT Secretary and public disclosure
  Measurement                thereafter.

  Comments



3/1/2019                                                                                                                Page 4 of 13
           The World Bank                                                                         Implementation Status & Results Report
           Second Bridges Improvement and Maintenance Program (P161929)




  Action Description         Effectiveness of GESU

  Source                     DLI#                   Responsibility          Timing                  Timing Value               Status

  Environmental and Social                                                                          Within 12 months of
                                                    GESU and BB             Other                                              In Progress
  Systems                                                                                           effective date

                             Confirmation from the DOR DG of: (a) Set up of functional team in GESU for OCHS and labor standards;
  Completion
  Measurement                (b) Approved organizational structure for GESU; (c) ToRs defined for specialists; and (d) Specialists in post and
                             performing daily functions.

  Comments



  Action Description         OCHS and labor management guidelines (bridge-specific elements) developed and deployed on Program contracts.

  Source                     DLI#                   Responsibility          Timing                  Timing Value               Status

                                                                                                    Interim guidelines
                                                                                                    endorsed by the DOR
                                                                                                    by end September
  Environmental and Social
                                                    GESU and BB             Other                   2018; Final guidelines     In Progress
  Systems
                                                                                                    endorsed by the MoPIT
                                                                                                    within 12 months of
                                                                                                    effective date

                             Deployment of specific provisions for worksites to be included in contracts, BoQ items,social/ environmental
  Completion
                             documents;Deployment of specific provisions to ensure control over subcontracted arrangements in the supply chain
  Measurement
                             of goods works and services

  Comments



                             The DOR OCHS and labor policy:Integrated OCHS and labor standards developed to align with national legislation
  Action Description         (incl Labor Act 2017) and matching updates to DOR’s ESMF (or addendum to ESMF) to reflect DOR policy and
                             OHCS and labor mgmt. guideline

  Source                     DLI#                   Responsibility          Timing                  Timing Value               Status

  Environmental and Social                                                                          Within 24 months of
                                                    GESU and BB             Other                                              In Progress
  Systems                                                                                           effective date

                             MoPIT endorsement/confirmation through letter of: (a) Final OCHS and labor management policy; (b) Completion of
  Completion                 stakeholder consultation on ESMF update; and (c) Public disclosure of final updated ESMF (or addendum
  Measurement                developed).



  Comments



  Action Description         OCHS management officers assigned to Program sites.



3/1/2019                                                                                                                  Page 5 of 13
           The World Bank                                                                        Implementation Status & Results Report
           Second Bridges Improvement and Maintenance Program (P161929)



  Source                     DLI#                  Responsibility          Timing                  Timing Value               Status

  Environmental and Social
                                                   BB and GESU             Due Date                30-Jul-2019                In Progress
  Systems

                             (a) DOR engineers assigned as OCHS management officers for all Program sites; (b) Consultants assigned to
  Completion
                             support officers with field monitoring and reporting; and (c) Assignment register developed, promulgated, and updated
  Measurement
                             in each Trimester Report.

  Comments



  Action Description         OCHS capacity-building program (training, awareness, and education)

  Source                     DLI#                  Responsibility          Timing                  Timing Value               Status

                                                   Road Sector Skill                               Within 12 months of
  Environmental and Social
                                                   Development             Other                   effective date and         In Progress
  Systems
                                                   Unit/BB                                         annually thereafter

                             Modules developed and delivered annually before beginning of each construction season covering
  Completion
  Measurement                (a) Training for DOR engineers and consultants; (b) Contractors compliance training; and (c) Demand-side
                             awareness raising training initiative for workers

  Comments



  Action Description         OCHS system monitoring

  Source                     DLI#                  Responsibility          Timing                  Timing Value               Status

                                                                                                   Within 12 months of
  Environmental and Social
                                                   GESU and BB             Other                   effective date and         In Progress
  Systems
                                                                                                   annually thereafter

                             Documentation in BSMS of (a) Regular and unannounced site visits by OCHS management officers, support
  Completion
                             consultants to worksites to ascertain actual performance at implementing OCHS standards;(b) Consultations with
  Measurement
                             communities near Program worksites

  Comments



  Action Description         OCHS system near miss and incident data collection.

  Source                     DLI#                  Responsibility          Timing                  Timing Value               Status

                                                                                                   Within 12 months of
  Environmental and Social
                                                   GESU/BB                 Other                   effective date and         In Progress
  Systems
                                                                                                   continuously thereafter

  Completion                 a) Accidents and near misses documented made public;
  Measurement                (b) Worker grievances to be directed to GRM system;




3/1/2019                                                                                                                 Page 6 of 13
           The World Bank                                                                        Implementation Status & Results Report
           Second Bridges Improvement and Maintenance Program (P161929)



                             (c) Documentation in the BSMS and public disclosure of incidents through DOR website; (d) Injured workers to be
                             engaged as trainers/speakers

  Comments



  Action Description         OHCS independent system validation and corrective actions.

  Source                     DLI#                  Responsibility           Timing                 Timing Value               Status

                                                                                                   Reports provided
                                                                                                   annually by end July of
  Environmental and Social                                                                         each fiscal year; Action
                                                   BB                       Other                                             In Progress
  Systems                                                                                          plans to be in place by
                                                                                                   September of each
                                                                                                   year

  Completion                 Independent assessments of in-practice function of OCHS and labor standards to include field validation and
  Measurement                community consultation.Executed by one or more external bodies.Annual action plans developed/agreed with IDA.

  Comments



                             Annual DOR staff surveys to be completed using questionnaire satisfactory to the Association. Annual staff survey
  Action Description
                             results reports to be independently compiled and publicly disclosed

  Source                     DLI#                  Responsibility           Timing                 Timing Value               Status

                                                                                                   Within 12 months of
                                                                                                   effective date and
                                                                                                   surveys administered
  Other                                            NPC                      Other                                             In Progress
                                                                                                   annually thereafter by
                                                                                                   December 31 of each
                                                                                                   calendar year

  Completion                 Public disclosure of results reports on the DOR website.
  Measurement

  Comments



                             Bridge development process defined with specific Gate Reviews and input stages from key technical, social, and
  Action Description
                             environmental work streams.

  Source                     DLI#                  Responsibility           Timing                 Timing Value               Status

                                                                                                   Within 9 months of
  Other                                            BB                       Other                  effective date and         In Progress
                                                                                                   continuously thereafter.

  Completion                 (a) Bridge development process endorsed by the MoPIT for initial use; and
  Measurement                (b) Documentation and signoffs for Gate Reviews completed for each Bridge Dossier.

  Comments


3/1/2019                                                                                                                Page 7 of 13
            The World Bank                                                                                Implementation Status & Results Report
            Second Bridges Improvement and Maintenance Program (P161929)




                                   Update of model bid documents technical, fiduciary, and environmental and social provisions used for contracting
  Action Description
                                   Program works

  Source                           DLI#                  Responsibility          Timing                    Timing Value             Status

  Other                                                  BB                      Due Date                  30-Sep-2018              Delayed

  Completion                       Model bid documents, satisfactory to the Association, adopted by Program for works contracts.
  Measurement

  Comments




  Risks

 Systematic Operations Risk-rating Tool

  Risk Category                                               Rating at Approval              Previous Rating             Current Rating

  Political and Governance                                    High                           --                          High
  Macroeconomic                                               Moderate                       --                          Moderate
  Sector Strategies and Policies                              High                           --                          High
  Technical Design of Project or Program                      Moderate                       --                          Moderate
  Institutional Capacity for Implementation and
  Sustainability                                              Moderate                       --                          Moderate
  Fiduciary                                                   Substantial                    --                          Substantial
  Environment and Social                                      Substantial                    --                          Substantial
  Stakeholders                                                Moderate                       --                          Moderate
  Other                                                       --                              --                          --
  Overall                                                     High                           --                          High


  Results

 PDO Indicators by Objectives / Outcomes

  Safe Bridges
   IN00664748
    ►Reduced     likelihood of road departure crashes on Program Bridges (Number, Custom)

                                          Baseline                  Actual (Previous)              Actual (Current)       End Target
    Value                               0.00                        --                             0.00                   18.00




3/1/2019                                                                                                                       Page 8 of 13
           The World Bank                                                                              Implementation Status & Results Report
           Second Bridges Improvement and Maintenance Program (P161929)



    Date                           03-May-2018                  --                             21-Dec-2018                15-Jul-2023
                                   Updates on the indicator will be provided in the next review. Final verification will be carried out by end of
    Comments                       the Program


  Resilient Bridges
   IN00664798
    ►Enhanced    DOR capabilites for developing resilient bridge designs (Number, Custom)

                                   Baseline                     Actual (Previous)              Actual (Current)           End Target
    Value                          0.00                         --                             0.00                       10.00

    Date                           03-May-2018                  --                             21-Dec-2018                15-Jul-2023
                                   Updates on the indicator will be provided in the next review. Final verification will be carried out by end of
    Comments                       the Program.


  Cost Effective Bridges
   IN00664740
    ►Estimated   road user cost savings achieved by Program interventions (Amount(USD), Custom)

                                   Baseline                     Actual (Previous)              Actual (Current)           End Target
    Value                          0.00                         --                             0.00                       26,049.97

    Date                           03-May-2018                  --                             21-Dec-2018                15-Jul-2023

                                   Final verification will be carried out by the end of the Program.
    Comments


  Beneficiary Feedback
   IN00664774
    ►Beneficiary   Feedback (Days, Custom)

                                   Baseline                     Actual (Previous)              Actual (Current)           End Target
    Value                          31.20                        --                             0.00                       10.00

    Date                           03-May-2018                  --                             21-Dec-2018                15-Jul-2023
                                   Updated result achieved will be assessed in next review and final verification will be carried out by the end
    Comments                       of the Program.



 Intermediate Results Indicators by Results Areas


  Safe Bridges
   IN00664821
    ►Road    Safety upgrades on Progam Bridges (Meter(m), Custom)

                                   Baseline                     Actual (Previous)              Actual (Current)           End Target
    Value                          0.00                         --                             0.00                       8,000.00




3/1/2019                                                                                                                     Page 9 of 13
           The World Bank                                                                              Implementation Status & Results Report
           Second Bridges Improvement and Maintenance Program (P161929)



    Date                            03-May-2018                  --                             21-Dec-2018                15-Jul-2023
                                    Updates on the indicator will be provided in the next review. Final verification will be carried out by end of
    Comments                        the Program.



  Resilient Bridges
   IN00664799
    ►Design   and Advanced Technology Cell created (Text, Custom)

                                    Baseline                     Actual (Previous)              Actual (Current)           End Target
                                                                                                The office space for
                                                                                                                           DATC
    Value                           N/A                          --                             DATC has been
                                                                                                                           staffed/mobilized
                                                                                                created.
    Date                            03-May-2018                  --                             21-Dec-2018                15-Jul-2020
                                    Updated result achieved will be assessed in the next review and final verification will be carried out by the
    Comments                        end of the Program.



  Resilient Bridges
   IN00664800
    ►Mobilization   of advanced design skills for improved resilience and inclusion (Number, Custom)

                                    Baseline                     Actual (Previous)              Actual (Current)           End Target
    Value                           0.00                         --                             0.00                       10.00

    Date                            03-May-2018                  --                             21-Dec-2018                15-Jul-2023
                                    Updates on the indicator will be provided in the next review. Final verification will be carried out by end of
    Comments                        the Program.



  Resilient Bridges
   IN00664826
    ►Female Engineers recruited in the Design and Advanced Technology Cell and given advanced skills training (Percentage,
    Custom)
                                    Baseline                     Actual (Previous)              Actual (Current)           End Target
    Value                           6.00                         --                             0.00                       33.00

    Date                            03-May-2018                  --                             21-Dec-2018                15-Jul-2023
                                    Updated result achieved (in %) will be assessed in each review and final verification will be carried out by
    Comments                        end of Year two and >33% in all years till end of Program.



  Cost Effective Bridges
   IN00664817
    ►Implementation    of high priority maintenance to extend asset lives (Meter(m), Custom)

                                    Baseline                     Actual (Previous)              Actual (Current)           End Target
    Value                           0.00                         --                             0.00                       4,500.00



3/1/2019                                                                                                                     Page 10 of 13
           The World Bank                                                                             Implementation Status & Results Report
           Second Bridges Improvement and Maintenance Program (P161929)



    Date                            03-May-2018                  --                            21-Dec-2018                15-Jul-2023
                                    Updated result achieved (in meter) will be assessed in next review and final verification will be carried out by
    Comments                        the end of the Program.



  Cost Effective Bridges
   IN00664822
    ►Completion    of Backlog bridges to reduce road user costs (Meter(m), Custom)

                                    Baseline                     Actual (Previous)             Actual (Current)           End Target
    Value                           0.00                         --                            0.00                       5,000.00

    Date                            03-May-2018                  --                            21-Dec-2018                15-Jul-2023
                                    Updated result achieved (in meter) will be assessed in next review and final verification will be carried out by
    Comments                        the end of the Program.



  Cost Effective Bridges
   IN00664823
    ►Construction   of New Bridges to reduce road user costs (Meter(m), Custom)

                                    Baseline                     Actual (Previous)             Actual (Current)           End Target
    Value                           0.00                         --                            0.00                       6,000.00

    Date                            03-May-2018                  --                            21-Dec-2018                15-Jul-2023
                                    Updated result achieved (in meter) will be assessed in next review and final verification will be carried out by
    Comments                        the end of the Program.



  Beneficiary Feedback
   IN00664825
    ►Responsiveness     of DOR's Grievance Redress Mechanism (Days, Custom)

                                    Baseline                     Actual (Previous)             Actual (Current)           End Target
    Value                           31.20                        --                            0.00                       10.00

    Date                            03-May-2018                  --                            21-Dec-2018                15-Jul-2023
                                    Updated result achieved will be assessed in next review and final verification will be carried out by the end
    Comments                        of the Program.



  Beneficiary
   IN00664827
    ►Anticipated   beneficiaries of inclusive design concepts (Number, Custom)

                                    Baseline                     Actual (Previous)             Actual (Current)           End Target
    Value                           0.00                         --                            0.00                       5,000.00




3/1/2019                                                                                                                    Page 11 of 13
           The World Bank                                                                               Implementation Status & Results Report
           Second Bridges Improvement and Maintenance Program (P161929)



    Date                               03-May-2018                    --                          21-Dec-2018               15-Jul-2023
                                       Updated result achieved will be assessed in next review and final verification will be carried out by the end
    Comments                           of the Program.



 Disbursement Linked Indicators
 DLI_IND_TABLE
    ►DLI    1 Major bridge maintenance (Output, 13,087,728.00, 0%)

                                Baseline                         Actual (Previous)             Actual (Current)               July 15, 2023

    Value                       0.00                             --                            0.00                           1,250.00

    Date                        --                               --                            21-Dec-2018                   --

    Comments



    ►DLI    2 Road safety upgrades on bridges (Output, 17,450,304.00, 0%)

                                Baseline                         Actual (Previous)             Actual (Current)               July 15, 2023

    Value                       0.00                             --                            0.00                           2,444.00

    Date                        --                               --                            21-Dec-2018                   --

    Comments



    ►DLI    3 New 2 lane bridge construction, rehab., and replacement of bridges (Output, 35,288,393.00, 0%)

                                Baseline                         Actual (Previous)             Actual (Current)               July 15, 2023

    Value                       0.00                             --                            0.00                           1,500.00

    Date                        --                               --                            21-Dec-2018                   --

    Comments



    ►DLI    4 New 4 lane bridge construction (Output, 25,205,995.00, 0%)

                                Baseline                         Actual (Previous)             Actual (Current)               July 15, 2023

    Value                       0.00                             --                            0.00                           743.00

    Date                        --                               --                            21-Dec-2018                   --

    Comments



    ►DLI    5 Completion of backlog bridges under construction (Output, 22,055,246.00, 0%)


3/1/2019                                                                                                                      Page 12 of 13
           The World Bank                                                                   Implementation Status & Results Report
           Second Bridges Improvement and Maintenance Program (P161929)



                                Baseline                    Actual (Previous)       Actual (Current)            July 15, 2023

    Value                       0.00                        --                      0.00                        0.00

    Date                        --                          --                      21-Dec-2018                 --

    Comments



    ►DLI    6 Improved fiduciary governance of design-build contracting (Intermediate Outcome, 2,000,000.00, 0%)

                                Baseline                    Actual (Previous)       Actual (Current)            July 15, 2023
                                                                                    BB, DOR is in the process
                                                                                    of hiring a consultant to
                                                                                    improve design-build
                                No guidelines or standard
    Value                                                   --                      contract documents          --
                                documents
                                                                                    incorporating stronger
                                                                                    fiduciary governance
                                                                                    measures
    Date                        --                          --                      21-Dec-2018                 --

    Comments



    ►DLI    7 BSMS (mobile monitoring system) use on Program worksites (Output, 3,750,750.00, 0%)

                                Baseline                    Actual (Previous)       Actual (Current)            July 15, 2023

    Value                       0.00                        --                      0.00                        576.00

    Date                        --                          --                      21-Dec-2018                 --

    Comments




3/1/2019                                                                                                         Page 13 of 13