The World Bank                                                                                 Implementation Status & Results Report
          Sindh Solar Energy Project (P159712)



Sindh Solar Energy Project (P159712)

 SOUTH ASIA | Pakistan | Energy & Extractives Global Practice |
 IBRD/IDA | Investment Project Financing | FY 2018 | Seq No: 4 | ARCHIVED on 11-Dec-2019 | ISR39800 |


 Implementing Agencies: Energy Department - Government of Sindh, Alternate Energy Development Board, Islamic Republic of Pakistan, Ministry of
 Energy



 Key Dates

  Key Project Dates

   Bank Approval Date: 14-Jun-2018                                               Effectiveness Date: 09-Jan-2019
   Planned Mid Term Review Date: 30-Nov-2021                                     Actual Mid-Term Review Date:
   Original Closing Date: 29-Sep-2023                                            Revised Closing Date: 29-Sep-2023
 pdoTable

 Project Development Objectives
  Project Development Objective (from Project Appraisal Document)
  The Development Objective is to increase solar power generation and access to electricity in Sindh Province.

  Has the Project Development Objective been changed since Board Approval of the Project Objective?
  No


 Components            Table




 Name
 Component 1: Utility-Scale Solar:(Cost $40.00 M)
 Component 2: Distributed Solar:(Cost $25.00 M)
 Component 3: Solar Home Systems:(Cost $30.00 M)
 Component 4: Capacity Building and Technical Assistance:(Cost $5.00 M)
 PMU Costs:(Cost $5.00 M)

 Overall Ratings

 Name                                                                          Previous Rating                           Current Rating

 Progress towards achievement of PDO                                           Satisfactory                             Satisfactory
 Overall Implementation Progress (IP)                                          Satisfactory                             Satisfactory
 Overall Risk Rating                                                           Moderate                                 Moderate


 Implementation Status and Key Decisions
  The project was approved by the World Bank (WB) Board on June 14, 2018, and became effective on January 9, 2019. The first disbursement was
  made in September 2019, signifying an important milestone.
  The WB team was pleased to note the contract signing in the presence of the Honorable Chief Minister for the Distributed Solar Building Survey and
  Household Energy Survey relating to Components 2 and 3 respectively, an important milestone for the project. The WB team also participated in
  kick-off meetings with both consultancy firms, a private sector consultation workshop opened by the Minister for Energy and the Secretary, visited
  the proposed site in Jamshoro District in relation to Component 1, carried out visits to three prospective sites for installation of distributed solar in
  Karachi in relation to Component 2, and held a number of other meetings. The team notes that despite substantial progress on many fronts, the full-

12/11/2019                                                                                                                        Page 1 of 6
                              The World Bank                                                                       Implementation Status & Results Report
                              Sindh Solar Energy Project (P159712)


  time Project Management Unit (PMU) is still not in place, but has received assurances that this process will be completed very soon. It is essential
  for the speedy implementation of the project for the eight selected PMU staff to be appointed, for the remaining four unfilled posts to be re-
  advertised, and for the move to dedicated office space to be completed.
  The Transaction Advisor relating to Component 1 is expected to be under contract in a matter of days, enabling work to start on the first 50 MW site.
  Sindh Energy Department is now considering options for the remaining 350 MW to be facilitated under the project, including development of a solar
  park.
  A number of other critical procurement activities are ongoing or about to start, not least the procurement of a firm for "design, supply, install and
  operation" of around 1 MW of distributed solar under Component 2. The intention is to run an accelerated procurement process for this initial 1 MW
  at a single site, with the target of having a functioning solar system installed on at least one building by May 2020. Procurement of the remaining 19
  MW of capacity would proceed in parallel.




  Risks

 Systematic Operations Risk-rating Tool

  Risk Category                                                           Rating at Approval           Previous Rating            Current Rating

  Political and Governance                                                Moderate                    Moderate                  Moderate
  Macroeconomic                                                           Moderate                    Moderate                  Moderate
  Sector Strategies and Policies                                          Moderate                    Moderate                  Moderate
  Technical Design of Project or Program                                  Moderate                    Moderate                  Moderate
  Institutional Capacity for Implementation and
  Sustainability                                                          Moderate                    Moderate                  Moderate
  Fiduciary                                                               Substantial                 Substantial               Substantial
  Environment and Social                                                  Moderate                    Moderate                  Moderate
  Stakeholders                                                            Moderate                    Moderate                  Moderate
  Other                                                                   --                           --                         --
  Overall                                                                 Moderate                    Moderate                  Moderate


  Results

 PDO Indicators by Objectives / Outcomes


   Increase solar power generation in Sindh Province
    IN00780277




    ►Generation                      capacity of energy constructed or rehabilitated (Megawatt, Corporate)

                                                      Baseline                 Actual (Previous)            Actual (Current)       End Target
    Value                                             0.00                     0.00                         0.00                   420.00

    Date                                              14-May-2018              28-Aug-2019                  04-Dec-2019           31-Dec-2024
                 IN00780279




                 Renewable energy generation capacity (other than hydropower) constructed under the project (Megawatt, Corporate
                 Breakdown)


12/11/2019                                                                                                                             Page 2 of 6
                              The World Bank                                                                     Implementation Status & Results Report
                              Sindh Solar Energy Project (P159712)



                                                     Baseline                 Actual (Previous)          Actual (Current)       End Target
                 Value                              0.00                      0.00                       0.00                   420.00

                 Date                               14-May-2018               28-Aug-2019                04-Dec-2019            31-Dec-2024
                 IN00780280




                 Utility-scale        solar power generation capacity constructed under the project (Megawatt, Custom Breakdown)

                                                     Baseline                 Actual (Previous)          Actual (Current)       End Target
                 Value                              0.00                      0.00                       0.00                   400.00

                 Date                               14-May-2018               28-Aug-2019                04-Dec-2019            31-Dec-2024
                 IN00780281




                 Distributed         solar power generation capacity constructed under the project (Megawatt, Custom Breakdown)

                                                     Baseline                 Actual (Previous)          Actual (Current)       End Target
                 Value                              0.00                      0.00                       0.00                   20.00

                 Date                               14-May-2018               28-Aug-2019                04-Dec-2019            31-Dec-2024



   Increase access to electricity in Sindh Province
    IN00780276




    ►People                      provided with new or improved electricity service (Number, Corporate)

                                                      Baseline                 Actual (Previous)          Actual (Current)       End Target
    Value                                             0.00                     0.00                       0.00                   1,200,000.00

    Date                                              14-May-2018              28-Aug-2019                04-Dec-2019           29-Dec-2023
                 IN00780278




                 People provided with access to electricity under the project by household connections (grid or off-grid). (Number, Corporate
                 Breakdown)

                                                     Baseline                 Actual (Previous)          Actual (Current)       End Target
                 Value                              0.00                      0.00                       0.00                   1,200,000.00

                 Date                               14-May-2018               28-Aug-2019                04-Dec-2019            29-Dec-2023



 Intermediate Results Indicators by Components


   Component 1: Utility-Scale Solar
    IN00780282




    ►Completion                      of competitive bidding process for awarding the first 50 MW sub-project (Yes/No, Custom)

                                                      Baseline                 Actual (Previous)          Actual (Current)       End Target
    Value                                             No                       No                         No                     Yes

    Date                                              14-May-2018              28-Aug-2019                04-Dec-2019           31-Dec-2019
    IN00780286




12/11/2019                                                                                                                             Page 3 of 6
                 The World Bank                                                                    Implementation Status & Results Report
                 Sindh Solar Energy Project (P159712)



    ►Private        capital mobilized (Amount(USD), Custom)

                                          Baseline                 Actual (Previous)        Actual (Current)       End Target
    Value                                0.00                     0.00                      0.00                   273,500,000.00

    Date                                 14-May-2018              28-Aug-2019               04-Dec-2019           29-Dec-2023



   Component 2: Distributed Solar
    IN00780283




    ►Identification       of at least 1 MW of distributed solar PV and competitive bidding completed (Yes/No, Custom)

                                          Baseline                 Actual (Previous)        Actual (Current)       End Target
    Value                                No                       No                        No                     Yes

    Date                                 14-May-2018              28-Aug-2019               04-Dec-2019           31-Dec-2019



   Component 3: Solar Home Systems
    IN00780284




    ►Female-headed           households provided with solar home systems (Number, Custom)

                                          Baseline                 Actual (Previous)        Actual (Current)       End Target
    Value                                0.00                     0.00                      0.00                   4,000.00

    Date                                 14-May-2018              28-Aug-2019               04-Dec-2019           29-Dec-2023
    IN00780287




    ►Social        Audit conducted at mid-term and results incorporated into project (Yes/No, Custom)

                                          Baseline                 Actual (Previous)        Actual (Current)       End Target
    Value                                No                       No                        No                     Yes

    Date                                 14-May-2018              28-Aug-2019               04-Dec-2019           31-Dec-2020



   Component 4: Capacity Building and Technical Assistance
    IN00780285




    ►Consumer          Advocate added to Project Steering Committee (Yes/No, Custom)

                                          Baseline                 Actual (Previous)        Actual (Current)       End Target
    Value                                No                       No                        No                     Yes

    Date                                 14-May-2018              28-Aug-2019               04-Dec-2019           31-Dec-2019
    IN00780288




    ►Female          and/or disabled staff within household energy survey contractor firm (Percentage, Custom)

                                          Baseline                 Actual (Previous)        Actual (Current)       End Target
    Value                                0.00                     0.00                      0.00                   15.00




12/11/2019                                                                                                               Page 4 of 6
                 The World Bank                                                                             Implementation Status & Results Report
                 Sindh Solar Energy Project (P159712)



    Date                                  14-May-2018                 28-Aug-2019                    04-Dec-2019              29-Dec-2023
    IN00780289




    ►Female          and/or disabled staff within the PMU (Percentage, Custom)

                                           Baseline                   Actual (Previous)              Actual (Current)         End Target
    Value                                 0.00                        17.00                          0.00                     15.00

    Date                                  14-May-2018                 28-Aug-2019                    04-Dec-2019              29-Dec-2023

                                           The Interim PMU has six staff appointed, of which one is female.
    Comments:
    IN00780290




    ►Training        event for women and/or disabled people held (Yes/No, Custom)

                                           Baseline                   Actual (Previous)              Actual (Current)         End Target
    Value                                 No                          No                             No                       Yes

    Date                                  14-May-2018                 28-Aug-2019                    04-Dec-2019              31-Dec-2020
    IN00780291




    ►Improved         data on energy access in Sindh Province (Yes/No, Custom)

                                           Baseline                   Actual (Previous)              Actual (Current)         End Target
    Value                                 No                          No                             No                       Yes

    Date                                  14-May-2018                 28-Aug-2019                    04-Dec-2019              29-Dec-2023




 Data on Financial Performance

 Disbursements (by loan)

 Project            Loan/Credit/TF    Status      Currency      Original    Revised     Cancelled         Disbursed     Undisbursed                % Disbursed

 P159712            IDA-62580         Effective   USD             100.00      100.00          0.00             0.99           94.07                        1%


 Key Dates (by loan)
 Project             Loan/Credit/TF   Status      Approval Date      Signing Date      Effectiveness Date       Orig. Closing Date      Rev. Closing Date

 P159712             IDA-62580        Effective   14-Jun-2018        09-Jan-2019       09-Jan-2019              29-Sep-2023             29-Sep-2023


Cumulative Disbursements




12/11/2019                                                                                                                           Page 5 of 6
          The World Bank                         Implementation Status & Results Report
          Sindh Solar Energy Project (P159712)




  Restructuring History

  There has been no restructuring to date.


  Related Project(s)

  There are no related projects.




12/11/2019                                                          Page 6 of 6