The World Bank                                                                                  Implementation Status & Results Report
            Montenegro Second Energy Efficiency Project (P165509)



Montenegro Second Energy Efficiency Project (P165509)


 EUROPE AND CENTRAL ASIA | Montenegro | Energy & Extractives Global Practice |
 IBRD/IDA | Investment Project Financing | FY 2018 | Seq No: 6 | ARCHIVED on 28-Jun-2021 | ISR47492 |


 Implementing Agencies: Ministry of Health, Ministry of Capital Investments, Montenegro



 Key Dates


  Key Project Dates

   Bank Approval Date: 04-Jun-2018                                           Effectiveness Date: 30-Aug-2018
   Planned Mid Term Review Date: 15-Dec-2021                                 Actual Mid-Term Review Date:
   Original Closing Date: 31-Dec-2023                                        Revised Closing Date: 31-Dec-2023
 pdoTable

 Project Development Objectives

  Project Development Objective (from Project Appraisal Document)
  The project development objective is to improve energy efficiency in health sector buildings, and to develop and demonstrate a sustainable
  financing model.

  Has the Project Development Objective been changed since Board Approval of the Project Objective?
  No


 Components Table

 Name
 Component 1 – EE investments in public sector buildings:(Cost $7959015.00 M)
 Component 2 – Technical assistance:(Cost $406890.00 M)
 Component 3 – Project implementation support:(Cost $616500.00 M)

 Overall Ratings

 Name                                                                       Previous Rating                         Current Rating

 Progress towards achievement of PDO                                        Satisfactory                           Satisfactory
 Overall Implementation Progress (IP)                                       Moderately Satisfactory                Moderately Satisfactory
 Overall Risk Rating                                                        Low                                    Low


 Implementation Status and Key Decisions

  Project implementation is progressing with some minor delays related to the COVID-19 pandemic. The government has taken corrective actions to
  avoid further delays in procurement under the project.




6/28/2021                                                                                                                   Page 1 of 6
            The World Bank                                                                                     Implementation Status & Results Report
            Montenegro Second Energy Efficiency Project (P165509)




  Risks


 Systematic Operations Risk-rating Tool


  Risk Category                                              Rating at Approval              Previous Rating               Current Rating

  Political and Governance                                   Moderate                       Low                          Low
  Macroeconomic                                              Moderate                       Low                          Low
  Sector Strategies and Policies                             Moderate                       Low                          Low
  Technical Design of Project or Program                     Moderate                       Moderate                     Moderate
  Institutional Capacity for Implementation and
                                                             Substantial                    Moderate                     Moderate
  Sustainability
  Fiduciary                                                  Moderate                       Low                          Low
  Environment and Social                                     Moderate                       Moderate                     Moderate
  Stakeholders                                               Moderate                       Low                          Low
  Other                                                      --                              Moderate                     Moderate
  Overall                                                    Moderate                       Low                          Low



  Results


 PDO Indicators by Objectives / Outcomes



   Improved energy efficiency in health sector public buildings

    IN01015332
    ►Projected energy or fuel savings (Mega Joules (MJ), Corporate)

                                      Baseline                      Actual (Previous)           Actual (Current)           End Target

    Value                             0.00                         43,000,000.00                141,780,000.00             215,000,000.00

    Date                              04-Jun-2018                  17-Dec-2020                  25-Jun-2021               31-Dec-2023
                                       Construction works on 5 buildings are complete, and the technical monitoring and verification for the
   Comments:                           three buildings completed.

     IN01015333
     Projected lifetime fuel savings (Mega Joules (MJ), Corporate Breakdown)

                                     Baseline                     Actual (Previous)            Actual (Current)           End Target

     Value                           0.00                         35,000,000.00                123,000,000.00             192,000,000.00

     Date                            04-Jun-2018                  17-Dec-2020                  25-Jun-2021                31-Dec-2023

     IN01015334
     Projected electricity generation savings (Mega Joules (MJ), Corporate Breakdown)

                                     Baseline                     Actual (Previous)            Actual (Current)           End Target



6/28/2021                                                                                                                     Page 2 of 6
            The World Bank                                                                                      Implementation Status & Results Report
            Montenegro Second Energy Efficiency Project (P165509)




     Value                           0.00                         8,000,000.00                  18,780,000.00              23,000,000.00

     Date                            04-Jun-2018                  17-Dec-2020                   25-Jun-2021                31-Dec-2023


   Developed and demonstrated sustainable energy efficiency financing model

    IN01015331
    ►Develop and demonstrate a sustainable financing model (Text, Custom)

                                       Baseline                     Actual (Previous)            Actual (Current)           End Target
                                                                                                 TA in progress but the
                                                                                                 (a) Energy savings        (a) Energy savings
                                                                                                 capture model is being    capture model
                                                                                                 implemented; (b)          implemented; (b)
                                                                                                 arrangements for          arrangements for
                                       No sustainable financing                                  MEEP2 energy              MEEP2 energy
    Value                                                          TA in progress
                                       model                                                     savings have been         savings adopted; (c)
                                                                                                 adopted; (c) proposal     proposal for long-term
                                                                                                 for long-term EE          EE investment
                                                                                                 investment framework      framework submitted
                                                                                                 submitted to              to Government
                                                                                                 Government.
    Date                               04-Jun-2018                 17-Dec-2020                   01-Jun-2021               31-Dec-2023
                                       Development of the sustainable financing model is complete. Consultant was hired to
                                       support implementation of the model. Energy cost savings of 97,395 Euro have been allocated to the
   Comments:
                                       Ministry of Economy for EE investments in 2021.


 Overall Comments PDO

  The project is generally on track with both investment and technical assistance indicators.




 Intermediate Results Indicators by Components



   Component 1: Energy efficiency investments in public sector buildings

    IN01015335
    ►Net greenhouse gas emissions (Tones/year, Corporate)

                                       Baseline                     Actual (Previous)            Actual (Current)           End Target

    Value                              0.00                        242.00                        2,420.13                   -3,211.27

    Date                               04-Jun-2018                 17-Dec-2020                   25-Jun-2021               31-Dec-2023

    IN01015337
    ►Number of buildings retrofitted (Number, Custom)

                                       Baseline                     Actual (Previous)            Actual (Current)           End Target

    Value                              0.00                        5.00                          8.00                       18.00



6/28/2021                                                                                                                      Page 3 of 6
            The World Bank                                                                                     Implementation Status & Results Report
            Montenegro Second Energy Efficiency Project (P165509)




    Date                              04-Jun-2018                  17-Dec-2020                   25-Jun-2021               31-Dec-2023
                                       Construction works on 3 buildings finished implementation in 2019, on 2 buildings in 2020, and on another
   Comments:                           3 buildings in 2021. The implementation is on track.

    IN01015339
    ►Percentage of project beneficiaries reporting an improvement in building comfort level, disaggregated by gender (Percentage, Custom)

                                      Baseline                      Actual (Previous)            Actual (Current)          End Target

    Value                             0.00                         0.00                          0.00                      30.00

    Date                              04-Jun-2018                  17-Dec-2020                   25-Jun-2021               31-Dec-2023
                                       Social monitoring and evaluation is carried out for this indicator. The following five healthcare facilities
                                       were chosen to take part in the social monitoring and evaluation: GH Bar, GH Nikšić, HC Ulcinj, HC Tivat
   Comments:                           and HC Podgorica-Golubovci. Social monitoring prior to the investment was completed, and will be carried
                                       out after the works are completed.

     IN01015340
     Percentage of male project beneficiaries reporting an improvement in building comfort level (Percentage, Custom Breakdown)

                                     Baseline                     Actual (Previous)            Actual (Current)            End Target

     Value                           0.00                         0.00                         0.00                        30.00

     Date                            04-Jun-2018                  17-Dec-2020                  25-Jun-2021                 31-Dec-2023

     IN01015341
     Percentage of female project beneficiaries reporting an improvement in building comfort level (Percentage, Custom Supplement)

                                     Baseline                     Actual (Previous)            Actual (Current)            End Target

     Value                           0.00                         0.00                         0.00                        30.00


   Component 2: Technical Assistance

    IN01015336
    ►Increase in women’s awareness of EE (Percentage, Custom)

                                      Baseline                      Actual (Previous)            Actual (Current)          End Target

    Value                             0.00                         0.00                          0.00                      10.00

    Date                              04-Jun-2018                  17-Dec-2020                   25-Jun-2021               31-Dec-2023

    IN01015338
    ►Captured energy cost savings (Amount(USD), Custom)

                                      Baseline                      Actual (Previous)            Actual (Current)          End Target

    Value                             0.00                         110,348.00                    97,395.00                 1,200,000.00

    Date                              04-Jun-2018                  17-Dec-2020                   25-Jun-2021               31-Dec-2023


 Overall Comments IR



6/28/2021                                                                                                                      Page 4 of 6
            The World Bank                                                                                  Implementation Status & Results Report
            Montenegro Second Energy Efficiency Project (P165509)



  Despite delays in project implementation due to COVID and a change in the government, construction at selected facilities is now
  complete. The post-construction survey of beneficiaries (users, patients, carers, as well as health staff) has been included in the
  project implementation plan for the upcoming 2021-2022 winter season. During FY21, the design of the post-construction survey
  was discussed and finalized, and is now ready for deployment to obtain feedback on the levels of improved comfort by building
  users. In addition, the PIU staff routinely visits the target facilities, to gather informal feedback from staff and patients. In the
  context of COVID, however, there has been restricted access to patients and other users. For this reason it has been agreed that the
  post-construction survey will include additional questions to patients. The regular patient and user (non-staff) feedback and
  monitoring practice by PIU staff is expected to restart in FY22 when the COVID restrictions are lifted.




 Performance-Based Conditions



 Data on Financial Performance


 Disbursements (by loan)

 Project        Loan/Credit/TF    Status       Currency        Original   Revised     Cancelled     Disbursed     Undisbursed                % Disbursed


 P165509        IBRD-88700        Effective    USD                7.39       7.39           0.00         4.51             2.54                      64%


 Key Dates (by loan)

 Project         Loan/Credit/TF    Status      Approval Date       Signing Date     Effectiveness Date    Orig. Closing Date      Rev. Closing Date

 P165509         IBRD-88700        Effective   04-Jun-2018         02-Jul-2018      30-Aug-2018           31-Dec-2023             31-Dec-2023


Cumulative Disbursements




6/28/2021                                                                                                                      Page 5 of 6
            The World Bank                                                                        Implementation Status & Results Report
            Montenegro Second Energy Efficiency Project (P165509)




 PBC Disbursement

                                                                                 Achievement   Disbursed amount in     Disbursement %
 PBC ID                     PBC Type    Description          Coc    PBC Amount
                                                                                 Status        Coc                     for PBC




  Restructuring History


  There has been no restructuring to date.


  Related Project(s)


 There are no related projects.




6/28/2021                                                                                                        Page 6 of 6