Sample Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan: agreed upon at appraisal 2. Date of General Procurement Notice: 3. Period covered by this procurement plan: first 18 months II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement Procurement Method Prior Review Comments Threshold US$ 1. ICB and LIB (Goods) Above US$ 1000,000 First three packages 2. NCB (Goods) Above US$ 100,000 First contract 5. (Non-Consultant Services) Below US$ 1000,000 First three packages [Add other methods if necessary] 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 4. Reference to (if any) Project Operational/Procurement Manual: 5. Summary of the Procurement Packages planned during the first 18 months after project effectiveness 1 2 3 4 5 6 7 Ref. Descripti Estimat Packages Dome Review Comme No. on ed stic by Bank nts Cost Prefe (Prior / US$ rence Post) million (yes/ no) G.Sev Several IT 1.35 No Prior (Goods) eral equipment million packages for establishin g Consumer Departmen t and Microfinan ce Unit III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comments Threshold 1. Competitive Methods (Firms) Above US$ 100,000 2. Single Source (Firms) All 3. Individual Above US$ 0.2 Million 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description Estimat Package Review Comment of ed s by Bank s Assignmen Cost (Prior / t US$ Post) million C.IND.Seve Several 0.25 1 Post ral Contracts million supporting developmen t of the institutional framework for microfinance C.QCBS.2 Enhance 0.35 1 Prior consumer million protection mechanism PROCUREMENT Egypt, Arab Republic of : Inclusive Regulations for Microfinance PLAN General Information Country: Egypt, Arab Republic of Bank’s Approval Date of the Original Procurement Plan: 2017-06-20 2021-05-18 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P149677 GPN Date: Project Name: Inclusive Regulations for Microfinance Loan / Credit No: TF / 17864 Egyptian Financial Supervisory Authority Executing Agency(ies): WORKS Procureme Activity Reference No. / Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH nt Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) Justification for Award Type Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual FRA-18 / Update of the Personnel and Payroll Program TF / 17864 Post Direct Selection Direct 3,821.66 Completed 2018-09-30 2018-10-01 2018-11-13 2018-11-13 2018-12-02 2018-12-30 2021-12-01 2019-01-01 (HITS DNA) FRA-19 / Update the electronic archive program TF / 17864 Post Direct Selection Direct 1,751.59 Completed 2018-09-30 2018-10-01 2018-11-12 2018-11-13 2018-12-02 2018-12-30 2021-12-01 2019-03-03 (JUPITER) FRA-GO-SH-1 / Tech. facilities & Supplies ( Request for Single Stage - One TF / 17864 Post Limited 30,249.30 Completed 2019-05-01 2019-06-09 2019-06-05 2019-07-25 2019-12-02 2019-07-29 Conference System) for the Quotations Envelope new training center FRA-GO-SH-3 / Tech. facilities & Supplies ( Sound Request for Single Stage - One TF / 17864 Post Limited 12,377.93 Completed 2019-04-28 2019-06-09 2019-06-02 2019-07-28 2019-11-29 2019-07-31 Systems) for the new training Quotations Envelope center FRA-GO-SH-4 / Tech. facilities & Supplies ( Projector Request for Single Stage - One TF / 17864 Post Limited 30,543.42 Completed 2019-05-01 2019-06-09 2019-06-12 2019-06-26 2019-12-09 2019-07-11 System) for the new training Quotations Envelope center FRA-GO-SH-2 / MIS Software, Design and Single Stage - Two Implementation of EFSA TF / 17864 Post Request for Bids Limited 6,138.11 Completed 2016-03-01 2016-04-21 2016-10-24 2016-10-24 2016-12-21 2016-12-21 2017-05-23 2017-05-23 2017-06-22 2017-06-22 2019-09-30 2018-01-18 Envelope Microfinance Information and Reporting System FRA-GO-SH-5 / Furnitures Request for Single Stage - One TF / 17864 Post Limited 0.00 Canceled 2019-04-23 2019-05-30 2019-11-26 for the new training center Quotations Envelope EG-FRA-119037-GO-RFQ / Financial Inclusion Training Request for Single Stage - One Center Main Display Screen TF / 17864 Post Limited 80,000.00 Completed 2019-06-16 2019-06-16 2019-07-04 2019-07-07 2019-07-07 2019-07-11 Quotations Envelope with Video signal cabling & installation accessories FRA- GO-45 / FRA BACKUP INFRASTRUCTURE SOLUTIONS TF / 17864 Post Direct Selection Direct 0.00 Canceled 2020-04-13 2020-04-07 2020-04-15 2020-04-09 2020-04-19 2020-07-03 SYSTEM (Verits) FRA- GO-46 / RAM FOR Request for Single Stage - One TF / 17864 Post Limited 2,678.93 Completed 2020-05-25 2020-06-25 2020-06-30 2020-07-09 2020-12-27 2020-07-21 UPGRADING DELL SERVERS Quotations Envelope FRA-GO-49 / FRA BACKUP Single Stage - One INFRASTRUCTURE SOLUTIONS TF / 17864 Post Request for Bids Open - National 0.00 Canceled 2020-08-25 2020-08-30 2020-10-11 2020-11-10 2020-12-15 2021-06-13 Envelope SYSTEM NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LEASE-001 / Rent premises TF / 17864 Prior Direct Selection Direct 78,085.99 Signed 2015-04-01 CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Consultant IC/EFSA/2015 / procurement TF / 17864 Prior Qualification Open - International 10,000.00 Terminated 2015-08-06 2015-08-10 consultant Selection INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Contract Type Process Status Teams of Reference Identified/Selected Signed Contract Contract Completion No. (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual FRA-CS-INDV-25 / Mohamed Individual Mohamed Taha, FRA's TF / 17864 Post Consultant Limited 6,140.00 Signed 2018-12-02 2018-12-25 2018-12-16 2019-08-01 2018-12-23 2018-12-23 2019-01-01 2019-01-01 2020-06-30 Inspections & Compliance Selection Specialist Page 1 FRA-CS-INDV-26 / Hossam Individual Fathy Gamal El Din, FRA's TF / 17864 Post Consultant Limited 6,140.00 Signed 2018-12-02 2018-12-02 2018-12-23 2018-12-06 2018-12-23 2018-12-16 2019-01-01 2018-12-30 2020-06-30 Junior Inspections & Selection Compliance Specialist FRA-CS-INDV-27 / Reem Individual Issam Mohammed, FRA's TF / 17864 Post Consultant Limited 6,140.00 Signed 2018-12-02 2018-12-02 2018-12-07 2018-12-06 2018-12-16 2018-12-16 2019-01-01 2018-12-30 2020-06-30 Inspections & Compliance Selection Specialist FRA-CS-INDV-28 / Sarah Individual Mohamed Morsy, FRA's TF / 17864 Post Consultant Limited 6,140.00 Signed 2018-12-02 2018-12-02 2018-12-16 2018-12-06 2018-12-23 2018-12-23 2019-01-01 2018-12-31 2020-06-30 Inspections & Compliance Selection Specialist FRA-CS-INDV-29 / Hoda Individual Abdel-Hamid Hermach, FRA's TF / 17864 Post Consultant Limited 6,140.00 Signed 2018-12-02 2018-12-02 2018-12-07 2018-12-16 2018-12-16 2018-12-24 2019-01-01 2019-01-01 2020-06-30 Inspections & Compliance Selection Specialist FRA-CS-INDV-30 / Individual Mohammed Ramadan Abdul TF / 17864 Post Consultant Limited 6,140.00 Signed 2018-12-02 2018-12-02 2018-12-07 2018-12-06 2018-12-16 2018-12-16 2019-01-01 2018-12-30 2020-06-30 Aziz, FRA's Inspections & Selection Compliance Specialist FRA-CS-INDV-31 / Mostafa Individual Said Ibrahim, FRA's TF / 17864 Post Consultant Limited 6,140.00 Signed 2018-12-02 2018-12-02 2018-12-16 2019-10-06 2018-12-23 2018-12-23 2019-01-01 2018-12-31 2020-06-30 Inspections & Compliance Selection Specialist FRA-CS-INDV-32 / Amira Individual Karam Sabbak, FRA's TF / 17864 Post Consultant Limited 6,140.00 Signed 2018-12-02 2018-12-02 2018-12-16 2018-12-06 2018-12-23 2018-12-16 2018-12-30 2018-12-31 2020-06-30 Inspections & Compliance Selection Specialist FRA-CS-INDV-33 / Individual Mohammed Reza Mohammed, TF / 17864 Post Consultant Limited 6,140.00 Signed 2018-12-02 2018-12-02 2018-12-07 2018-12-06 2018-12-16 2018-12-16 2019-01-01 2019-01-01 2020-06-30 FRA's Inspections & Selection Compliance Specialist Individual FRA-CS-INDV-34 / Mirna TF / 17864 Post Consultant Limited 6,140.00 Signed 2018-12-02 2018-12-02 2018-12-16 2018-12-16 2018-12-23 2018-12-23 2019-01-01 2019-01-01 2020-06-30 Ashraf Fathi Selection FRA-CS-INDV-35 / Fatima Individual Mohammed Jaber, FRA's TF / 17864 Post Consultant Limited 6,140.00 Signed 2018-12-02 2018-12-16 2018-12-16 2018-12-16 2018-12-23 2018-12-23 2019-01-01 2019-01-01 2020-06-30 Inspections & Compliance Selection Specialist FRA-CS-INDV-36 / Amira Individual Fawzi Mohamed, FRA's TF / 17864 Post Consultant Limited 6,140.00 Signed 2018-12-02 2018-12-02 2018-12-16 2018-12-16 2018-12-23 2018-12-23 2019-01-01 2019-01-01 2020-06-30 Inspections & Compliance Selection Specialist FRA-CS-INDV-37 / Alaa Individual Nasser Sayed, FRA's TF / 17864 Post Consultant Limited 6,140.00 Signed 2018-12-02 2018-12-02 2018-12-16 2018-12-06 2018-12-23 2018-12-19 2019-01-01 2018-12-31 2020-06-30 Inspections & Compliance Selection Specialist FRA-CS-INDV-38 / Bassam Individual Hussam El - Din Abdel - TF / 17864 Post Consultant Limited 6,140.00 Signed 2018-12-02 2018-12-02 2018-12-07 2018-12-06 2018-12-16 2018-12-16 2019-01-01 2018-12-31 2020-06-30 Hamd, FRA's Inspections & Selection Compliance Specialist FRA-CS-INDV-39 / Samar Individual Ibrahim Hefnawi, Junior TF / 17864 Post Consultant Limited 6,140.00 Signed 2018-12-02 2018-12-02 2018-12-07 2018-12-06 2018-12-20 2018-12-20 2019-01-01 2019-01-01 2020-06-30 Inspections & Compliance Selection Specialist FRA-CS-INDV-40 / Israa Individual Abdel Azim Ahmed, Junior TF / 17864 Post Consultant Limited 6,140.00 Signed 2018-12-02 2018-12-02 2018-12-07 2018-12-06 2018-12-16 2018-12-16 2019-01-01 2018-12-31 2020-06-30 Inspections & Compliance Selection Specialist FRA-CS-INDV-41 / Fatima Al- Individual Zahra Abd Al-Badea, Junior TF / 17864 Post Consultant Limited 6,140.00 Completed 2018-12-02 2018-12-02 2018-12-07 2018-12-06 2018-12-12 2018-12-16 2019-01-01 2018-12-30 2020-06-30 2021-03-01 Inspections & Compliance Selection Specialist FRA-CS-INDV-42 / Shadwa Individual Alaa Eddin Mahmoud, Junior TF / 17864 Post Consultant Limited 6,140.00 Signed 2018-12-02 2018-12-02 2018-12-07 2018-12-06 2018-12-16 2018-12-16 2019-01-01 2019-01-01 2020-06-30 Inspections & Compliance Selection Specialist FRA-CS-INDV-43 / Aya Ali Individual Mohamed, Junior Inspections TF / 17864 Post Consultant Limited 6,140.00 Signed 2018-12-02 2018-12-02 2018-12-07 2018-12-06 2018-12-16 2018-12-16 2019-01-01 2019-01-01 2020-06-30 & Compliance Specialist Selection FRA-CS-INDV-44 / Sarah Individual Kamal Riad, Junior Inspections TF / 17864 Post Consultant Limited 6,140.00 Signed 2018-12-02 2018-12-02 2018-12-07 2018-12-06 2018-12-16 2018-12-07 2019-01-01 2018-12-31 2020-06-30 & Compliance Specialist Selection FRA-CS-INDV-1 / MF Project Individual deputy Manager (Ahmed TF / 17864 Post Consultant Limited 4,758.26 Signed 2016-08-01 2016-08-01 2016-08-06 2016-08-06 2016-08-21 2016-08-21 2016-09-01 2016-09-01 2020-06-30 Hussein Abdelgawad) Selection FRA-CS-INDV-4 / Specialist Individual of Analysis and Control TF / 17864 Post Consultant Limited 2,647.72 Signed 2015-06-01 2015-06-01 2015-06-06 2015-06-06 2015-06-16 2015-06-16 2015-07-12 2015-07-12 2020-06-30 (Ahmed Mohamed Ahmed Selection Abdel Aati) FRA-CS-INDV-5 / Individual Compliance & Inspection TF / 17864 Post Consultant Limited 2,283.61 Completed 2015-09-22 2015-09-22 2015-09-27 2015-09-27 2015-10-18 2015-10-18 2015-11-11 2015-11-11 2020-06-30 2019-10-31 Specialist (Hassan Mohamed Selection Abdel Latif Hassan) FRA-CS-INDV-6 / Individual Compliance & Inspection TF / 17864 Post Consultant Limited 1,734.26 Signed 2016-07-03 2016-07-03 2016-07-08 2016-07-08 2016-07-29 2016-07-29 2016-09-01 2016-09-01 2017-02-28 Specialist (Anas Sobhy Ahmed Selection El-Erian) Page 2 FRA-CS-INDV-7 / Individual Compliance & Inspection TF / 17864 Post Consultant Limited 1,737.53 Signed 2016-07-03 2016-07-03 2016-07-08 2016-07-08 2016-07-29 2016-07-29 2016-09-01 2016-09-01 2020-06-30 Specialist (Hisham Abdel- Selection Maleem Abdel-Kareem) FRA-CS-INDV-8 / Individual Compliance & Inspection TF / 17864 Post Consultant Limited 776.72 Signed 2018-10-01 2018-10-01 2018-10-06 2018-10-06 2018-10-16 2018-10-16 2018-11-01 2018-11-01 2020-06-30 Specialist (Mina Reda Nassif) Selection FRA-CS-INDV-9 / Individual Compliance & Inspection TF / 17864 Post Consultant Limited 1,040.39 Completed 2017-11-07 2017-11-07 2017-11-12 2017-11-12 2017-12-03 2017-12-03 2018-01-15 2018-01-15 2020-06-30 2019-12-31 Specialist (Assem Eid Selection Mahmoud) FRA-CS-INDV-10 / training Individual and awareness Specialist TF / 17864 Post Consultant Limited 962.94 Signed 2017-12-11 2017-12-11 2017-12-16 2017-12-07 2018-01-06 2018-01-06 2018-02-01 2018-02-01 2020-06-30 (Safaa Mohamed Abdoun Selection Hussein) FRA-CS-INDV-11 / Individual Compliance & Inspection TF / 17864 Post Consultant Limited 815.05 Signed 2018-05-27 2018-05-27 2018-06-01 2018-05-30 2018-06-17 2018-06-17 2018-07-01 2018-07-01 2020-06-30 Specialist (Abbas Abdel Selection Moneim Abbas Al - Saidi) FRA-CS-INDV-12 / Individual Compliance & Inspection TF / 17864 Post Consultant Limited 985.18 Signed 2018-02-01 2018-02-01 2018-02-06 2018-02-06 2018-02-19 2018-02-19 2018-03-01 2018-03-01 2020-06-30 Specialist (Mohammed Ayman Selection Kamal Al - Kurdi) FRA-CS-INDV-13 / Individual Procurment & Adm Specialist TF / 17864 Post Consultant Limited 7,000.00 Signed 2019-01-01 2019-01-01 2019-01-06 2019-01-08 2019-01-15 2019-01-15 2019-02-01 2019-02-01 2020-06-30 (Mohamed Nabil Zaki) Selection FRA-CS-INDV-14 / Individual Administrative Affairs Clerck TF / 17864 Post Consultant Limited 1,070.08 Signed 2015-02-26 2015-02-26 2015-03-03 2015-03-03 2015-03-24 2015-03-24 2015-04-26 2015-04-26 2020-06-30 (Hashem Ahmed Hashim) Selection FRA-CS-INDV-15 / Support Individual Services Assitant (Abdullah TF / 17864 Post Consultant Limited 540.00 Signed 2016-08-01 2016-08-01 2016-08-06 2016-08-07 2016-08-16 2016-08-16 2016-09-19 2016-10-19 2020-06-30 Abdulrahman Mohammed Al - Selection Sadawi) FRA-CS-INDV-16 / Support Individual Services Assitant (Alaa TF / 17864 Post Consultant Limited 640.00 Signed 2016-08-01 2016-08-01 2016-08-06 2016-08-07 2016-08-27 2016-09-11 2016-09-19 2016-09-19 2020-06-30 mahmood mahmood) Selection FRA-CS-INDV-17 / Support Individual Services Assitant (Mohammed TF / 17864 Post Consultant Limited 540.00 Signed 2016-08-01 2016-08-01 2016-08-06 2016-08-07 2016-08-27 2016-08-27 2016-09-19 2016-10-19 2020-04-30 Jnaidi Jad Amira) Selection FRA-CS-INDV-18 / M&E Individual Specialist (Ms. Sara TF / 17864 Post Consultant Limited 3,433.77 Signed 2017-10-01 2017-10-01 2017-10-06 2017-10-06 2017-10-16 2017-10-16 2017-11-01 2017-11-01 2020-06-30 Eldegheidi) Selection FRA-CS-CDS-1 / Senior Advisor Microfinance TF / 17864 Post Direct Selection Direct 2,158.73 Signed 2014-11-15 2014-11-15 2014-11-25 2014-11-25 2015-01-01 2015-01-01 2015-12-31 Regulatory Framework (Mr. Abdel Hamid Ibrahim) FRA-CS-CDS-11 / Insurance Advisor (Mr. Hesham Ibrahim) TA under our MF Project to cover specifically the insurance sector. EFSA TF / 17864 Post Direct Selection Direct 2,178.27 Completed 2017-10-01 2017-10-01 2017-10-11 2017-10-14 2017-10-27 2017-10-26 2017-12-31 2021-01-21 currently needs to work on the following: • Drafting a new insurance law taking into consideration all the recent developments FRA-CS-CDS-2 / FRA's Advisor for legislation and TF / 17864 Post Direct Selection Direct 191.69 Signed 2017-10-01 2017-10-01 2017-10-15 2017-10-15 2017-11-01 2017-11-01 2018-12-31 drafting of lawsJudge (Mr. Mohamed Abed Elkerim) FRA-CS-CDS-3 / Consumer Protection Advisor (Dr. Shahira Fawzy) Local consulatnt under MF project for the Consumer Protection to guidance FRA TF / 17864 Post Direct Selection Direct 767.75 Signed 2018-04-01 2018-04-01 2018-04-11 2018-04-07 2018-05-01 2018-05-02 2018-12-31 team and design the needed framwork to support FRA efforts which aim to develop non banking financial markets In Egypt FRA-CS-CDS-4 / MFI Financial Reporting quality TF / 17864 Post Direct Selection Direct 9,000.00 Signed 2018-05-16 2018-05-16 2018-05-28 2018-05-28 2018-07-01 2019-07-01 2018-12-31 assurance consultant (Dr. Mohamed Yehia) FRA-CS-CDS-5 / Information Technology Advisor Eng. TF / 17864 Post Direct Selection Direct 1,406.65 Signed 2018-01-21 2018-01-21 2018-01-31 2018-01-31 2018-03-01 2018-03-01 2018-12-31 Tarek Fathy FRA-CS-CDS-6 / Information Technology Advisor MIS TF / 17864 Post Direct Selection Direct 1,904.76 Signed 2018-12-02 2018-12-02 2018-12-16 2018-12-16 2019-01-01 2019-01-01 2019-12-31 Sysytem Eng. Nael Abdelwahab FRA-CS-INDV-2 / Finance Individual Planning & General Support TF / 17864 Post Consultant Limited 1,533.55 Signed 2015-02-01 2015-02-01 2015-02-11 2015-02-11 2015-02-25 2015-02-25 2015-04-01 2015-04-01 2015-12-31 Services Manager (Hossam Selection Bashir) FRA-CS-INDV-3 / Head of Individual Micro Finance (Mr. Gamal TF / 17864 Post Consultant Direct 3,192.08 Signed 2015-01-01 2015-01-01 2015-01-11 2015-01-11 2015-02-01 2018-02-01 2015-03-01 2015-03-01 2015-12-31 Khalifa) Selection Page 3 FRA-CS-CDS-7 / Digital Transformation Advisor (Mrs. TF / 17864 Post Direct Selection Direct 952.38 Signed 2018-12-02 2018-12-02 2018-12-12 2018-12-12 2019-01-01 2019-01-01 2019-12-31 Asmaa Mahmoud Hosny) EG-EFSA-201452-CS-CDS / a consultant for drafting the TF / 17864 Post Direct Selection Direct 0.00 Under Review 2020-10-25 2020-09-15 2020-10-27 2020-11-01 2021-04-30 law of Futures Contracts Exchange (Samah adel) Page 4 PROCUREMENT PLAN (Textual Part) Project information: Ethiopia, One WASH- Consolidated WASH Account (CWA) Project “Phase II”, P167794 Project Implementation agency: Water Development Commission (WDC) of the Ministry of Water, Irrigation and Energy (MoWIE) Date of the Procurement Plan: August 28, 2019 Period covered by this Procurement Plan: September 2019 to August 2020. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016 revised August 2018) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Section 33(1)(a) from 35-48 of the Proclamation Number 649/2009 of the Ethiopian Federal Government Procurement and Property Administration Proclamation, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. • Open Advertising of the procurement opportunity at the national level; • The procurement is open to eligible firms from any country; • The request for bids/Proposal documents shall require that bidders/proposers submitting Bids/Proposal present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of and compliance with the Bank’s Anti-Corruption Guidelines, including without limitation the bank’s right to sanction and the Bank’s inspection and audit right; • Contracts with an appropriate allocation of responsibilities, risks and liabilities; • Application of Standstill period and Publication of contract award information; • Maintenance of records of the procurement process; and • The Bank has the right to review procurement documentation and activities. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second-Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: Is applicable for those contracts identified in the Procurement Plan; Works: Is applicable for those contracts identified in the Procurement Plan. Other Relevant Procurement Information. None PROCUREMENT Ethiopia : One WASH—Consolidated Water Supply, Sanitation, and Hygiene Account Project (One WASH—CWA) PLAN General Information Country: Ethiopia Bank’s Approval Date of the Original Procurement Plan: 2020-03-11 2021-05-17 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P167794 GPN Date: 2019-12-06 Project Name: One WASH—Consolidated Water Supply, Sanitation, and Hygiene Account Project (One WASH—CWA) Loan / Credit No: IDA / 64450 T Executing Agency(ies): IGRAY WRDB WORKS Procureme Activity Reference No. / Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH nt Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) Justification for Award Type Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-TIGRAY WRDB-151604- CW-RFB / Civil work construction with supply and installation of Pipes ,Fittings Urban Water Supply, Under Single Stage - One 2021-04- and electro-mechanical IDA / 64450 Sanitation, and Hygiene Post Request for Bids Open - National 0.00 Implementat 2020-03-04 2020-04-01 2020-03-19 2020-04-18 2020-05-04 2020-05-18 2020-09-08 2020-06-28 Envelope 24 equipment's) forAdi Daero (Urban WASH) ion Town. Implementing Agency-Tigray Water Resource Bureau ET-TIGRAY WRDB-155372- CW-RFB / Drilling and pumping test of one Deep Urban Water Supply, Single Stage - One 2020-07- borehole for Adi Nebried IDA / 64450 Sanitation, and Hygiene Post Request for Bids Open - National 30,670.14 Signed 2020-02-05 2020-04-13 2020-02-20 2020-03-21 2020-05-13 2020-04-20 2020-07-08 2020-05-25 2020-08-17 Envelope 24 Town. (Urban WASH) Implementing Agency-Tigray Water Resource Bureau ET-TIGRAY WRDB-151608- CW-RFB / Expansion of water Urban Water Supply, Under supply system at Nebelet Single Stage - One 2020-09- IDA / 64450 Sanitation, and Hygiene Post Request for Bids Open - National 0.00 Implementat 2020-02-12 2020-04-16 2020-02-27 2020-03-28 2020-05-15 2020-04-27 2020-07-21 2020-06-01 town. Envelope 29 (Urban WASH) ion Implimenting Agency-Tigray Water Resource Bureau ET-TIGRAY WRDB-151627- CW-RFB / Construction of RPS (Civil work construction , supply and installation of Pipes and Fittings and Rural Water Supply, Under Single Stage - One 2021-04- electromechanical equipment) IDA / 64450 Sanitation, and Hygiene Post Request for Bids Open - National 0.00 Implementat 2020-02-24 2020-05-19 2020-03-10 2020-04-21 2020-06-23 2020-05-21 2020-10-10 2020-07-01 Envelope 07 at Kilite Awlealo Woreda (Rural WASH) ion (Dinwale Village) Implementing Agency-Tigray Water Resource Bureau ET-TIGRAY WRDB-151638- CW-RFB / Drilling and pumping test of Five Deep borehole for (Laelay Maychew Rural Water Supply, Under Single Stage - One 2020-09- #1, Laelay Adiyabo #1 , IDA / 64450 Sanitation, and Hygiene Post Request for Bids Open - National 153,863.83 Implementat 2020-02-14 2020-04-10 2020-02-29 2020-04-11 2020-05-20 2020-05-11 2020-07-08 2020-06-21 Envelope 19 hintalo wojerat (Gonka) (Rural WASH) ion #1,Tsegede #1 and Welkait#1) Implementing Agency-Tigray Water Resource Bureau ET-TIGRAY WRDB-155368- CW-RFB / Drilling of shallow wells and supply and installation of Afredeve hand pump at lot-1 Atsbi Wonberta and ofla Rural Water Supply, Under Single Stage - One 2020-11- woredas #10Shallow wells IDA / 64450 Sanitation, and Hygiene Post Request for Bids Open - National 156,058.70 Implementat 2020-03-28 2020-04-08 2020-04-12 2020-05-12 2020-05-08 2020-06-11 2020-07-07 2020-07-16 Envelope 13 lot-2Welkayit woreda #10 (Rural WASH) ion shallow wells lot-3Tsegede Woreda#10SW Implementing Agency- Tigray Water Resource Bureau ET-TIGRAY WRDB-151601- CW-RFB / Civil work construction with supply and installation of Pipes ,Fittings Urban Water Supply, Under Single Stage - One 2021-06- and electromechanical IDA / 64450 Sanitation, and Hygiene Post Request for Bids Open - National 0.00 Implementat 2020-02-07 2020-04-01 2020-02-25 2020-03-26 2020-05-07 2020-05-05 2020-09-22 2020-06-15 Envelope 15 equipments) for Wukro Maray (Urban WASH) ion Town. Implementing Agency- Tigray Water Resource Bureau ET-TIGRAY WRDB-232288- National CW-DIR / Construction of Procurement Rural Water Supply, Pending RPSs including supply and Document - 1 2022-01- IDA / 64450 Sanitation, and Hygiene Post Direct Selection Direct 0.00 Implementat 2021-04-30 2021-05-05 2021-05-22 Installation of Pipes and Envelope 27 (Rural WASH) ion Fittings and EME for Dinwale process (Non village by Tigray WRB Bank-SPD) ET-TIGRAY WRDB-232291- National CW-DIR / Construction of WSS Procurement Urban Water Supply, Pending including supply and Document - 1 2021-12- IDA / 64450 Sanitation, and Hygiene Post Direct Selection Direct 0.00 Implementat 2021-04-30 2021-05-05 2021-05-22 Installation of Pipes and Envelope 08 (Urban WASH) ion Fittings and EME for Adi Daero process (Non Town by Tigray WRB Bank-SPD) ET-TIGRAY WRDB-232292- National CW-DIR / Construction of WSS Procurement Urban Water Supply, Pending including supply and Document - 1 2022-05- IDA / 64450 Sanitation, and Hygiene Post Direct Selection Direct 0.00 Implementat 2021-04-30 2021-05-05 2021-05-22 Installation of Pipes and Envelope 22 (Urban WASH) ion Fittings and EME for Wukro process (Non Maray Town by Tigray WRB Bank-SPD) ET-TIGRAY WRDB-232293- National CW-DIR / Construction of WSS Procurement Urban Water Supply, Pending including supply and Document - 1 2022-02- IDA / 64450 Sanitation, and Hygiene Post Direct Selection Direct 0.00 Implementat 2021-04-30 2021-05-05 2021-05-22 installation of pipes and Envelope 16 (Urban WASH) ion fittings and EME for Chercher process (Non Town by Tigray WRDB Bank-SPD) Page 1 National ET-TIGRAY WRDB-232299- Procurement CW-DIR / Drilling of 30 Rural Water Supply, Pending Document - 1 2021-09- shallow wells including supply IDA / 64450 Sanitation, and Hygiene Post Direct Selection Direct 0.00 Implementat 2021-04-30 2021-05-05 2021-05-22 Envelope 19 & installation of hand pump in (Rural WASH) ion process (Non 4 lots by Tigray RWB Bank-SPD) GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-TIGRAY WRDB-232298- GO-DIR / Procurement of 7 Urban Water Supply, Pending generator and 6 pumps and 3 IDA / 64450 Sanitation, and Hygiene Post Direct Selection Direct 0.00 Implementati 2021-04-30 2021-05-05 2021-06-09 2021-09-07 switch boards by Tigray Water (Urban WASH) on Resources Bureau NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Contract Type Process Status Teams of Reference Identified/Selected Signed Contract Contract Completion No. (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-TIGRAY WRDB-155393- CS-INDV / Selection and Individual Employment of Regional Institutional Strengthening Under IDA / 64450 Post Consultant Open 0.00 2020-02-20 2020-04-09 2020-04-30 2020-06-04 2021-06-04 WASH Assistant coordinator and Project Management Implementation Selection by Tigray Water Resource Bureau. ET-TIGRAY WRDB-155455- CS-INDV / Recruitment of Individual Institutional Strengthening Under Monitoring and Evaluation IDA / 64450 Post Consultant Open 0.00 2020-02-20 2020-04-09 2020-04-30 2020-06-04 2021-06-04 and Project Management Implementation Specialist by Tigray Water Selection Resource Bureau. ET-TIGRAY WRDB-155465- CS-INDV / Recuitement of Individual Institutional Strengthening Under Electromechanical Specialist IDA / 64450 Post Consultant Open 0.00 2020-02-20 2020-04-09 2020-04-30 2020-06-04 2021-06-04 and Project Management Implementation by Tigray Water Resource Selection Bureau ET-TIGRAY WRDB-155475- CS-INDV / Recruitment of Individual Institutional Strengthening Technical Specialist (Engineer) IDA / 64450 Post Consultant Open 0.00 Canceled 2020-02-20 2020-04-09 2020-04-30 2020-06-04 2021-06-04 and Project Management by Tigray Water Resource Selection Bureau ET-TIGRAY WRDB-155461- Individual CS-INDV / Recruitment of Institutional Strengthening IDA / 64450 Prior Consultant Open 0.00 Canceled 2020-04-20 2020-06-08 2020-06-29 2020-08-03 2023-08-03 Procurement specialist by and Project Management Selection Tigray Water Resource Bureau. ET-TIGRAY WRDB-191553- Individual CS-INDV / Recuitment of Institutional Strengthening Under IDA / 64450 Prior Consultant Open 0.00 2020-09-12 2020-10-31 2020-11-21 2020-12-26 2023-12-26 procurement specialist by and Project Management Implementation Selection Tigray Water Resource Bureau ET-TIGRAY WRDB-191557- CS-INDV / Recuitemnet of Individual Institutional Strengthening Under technical specialist (Engineer) IDA / 64450 Post Consultant Open 0.00 2020-09-12 2020-10-31 2020-11-21 2020-12-26 2021-12-26 and Project Management Implementation by Tigray Water Resource Selection Bureau ET-TIGRAY WRDB-232308- Individual CS-INDV / Recruitment of Institutional Strengthening Pending IDA / 64450 Post Consultant Limited 0.00 2021-05-05 2021-05-10 2021-05-25 2021-06-25 2022-06-25 Technical Specialist (Engineer) and Project Management Implementation Selection by Tigray WRB ET-TIGRAY WRDB-232310- Individual Institutional Strengthening Pending CS-INDV / Recruitment of IDA / 64450 Post Consultant Limited 0.00 2021-05-05 2021-05-10 2021-05-31 2021-07-05 2022-07-05 and Project Management Implementation Social Safeguard by Tigray Selection WRB ET-TIGRAY WRDB-232311- Individual CS-INDV / Recruitment of Institutional Strengthening Pending IDA / 64450 Post Consultant Limited 0.00 2021-05-05 2021-05-10 2021-05-31 2021-07-05 2022-07-05 Procurement specialist by and Project Management Implementation Selection Tigray WRB Page 2 Nigeria For APPEALSP PROCUREMENT PLAN (Textual Part) Project information: [Nigeria] [Agro-Processing, Productivity Enhancement and Livelihood Improvement Support Project] (P53390) Project Implementation agency: [Federal Ministry of Agriculture and Rural Development] Date of the Procurement Plan: [October 25, 2018] Period covered by this Procurement Plan: [October 25, 2018 to December 2018] Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable. Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables. Not Applicable. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works).Not Applicable. Goods: is not applicable Works: is not applicable Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Not Applicable Other Relevant Procurement Information. The project will use the CDD procurement under this project. CDD manual will be produced by the project. PROCUREMENT Nigeria : Agro-Processing, Productivity Enhancement and Livelihood Improvement Support Project PLAN General Information Country: Nigeria Bank’s Approval Date of the Original Procurement Plan: 2019-04-26 2021-05-21 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P148616 GPN Date: Project Name: Agro-Processing, Productivity Enhancement and Livelihood Improvement Support Project Loan / Credit No: IDA / 59930 LAGOS APPEALS Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned APPEALSP-LGSCO-CW-01 / Under Renovation of Office, Project Management and Request for Single Stage - One 2020-01- IDA / 59930 Post Limited 27,470.00 27,514.10 Implementat 2019-05-11 2019-05-07 2019-07-06 2019-06-13 Conference Room & Training Coordination Quotations Envelope 02 ion Hall NG-LAGOS APPEALS-158867- CW-RFB / Construction/rehabilitation of Infrastructure Support to Single Stage - Two 2021-07- IDA / 59930 Post Request for Bids Open - National 877,780.00 0.00 Canceled 2020-08-10 2020-08-15 2020-09-26 2020-12-09 2021-01-13 7.9 km Farm Access Roads Agribusiness Clusters Envelope 12 (3.8Km at Igbodu, Epe; 4.1 Km at Erikorodo -Phase 1) NG-LAGOS APPEALS-235890- Request for Bids - Pending CW-RFB / Infrastructure Support to Single Stage - One Small Works SPD 2022-03- IDA / 59930 Post Request for Bids Open - National 3,966,280.00 0.00 Implementat 2021-05-27 2021-06-01 2021-07-13 2021-08-12 2021-09-16 Construction/Rehabilitation of Agribusiness Clusters Envelope (1 envelope 15 ion Farm Access Road process) NG-LAGOS APPEALS-235891- Request for Bids - Pending CW-RFB / Infrastructure Support to Single Stage - One Small Works SPD 2022-03- IDA / 59930 Post Request for Bids Open - National 458,333.00 0.00 Implementat 2021-06-08 2021-06-13 2021-07-25 2021-08-24 2021-09-28 Construction/Rehabilitation of Agribusiness Clusters Envelope (1 envelope 27 ion 3 No.s of Aggregation Centers process) NG-LAGOS APPEALS-235893- Primary processing, Value Request for Bids - Pending CW-RFB / Establishment of 12 Addition, Post-Harvest Single Stage - One Small Works SPD 2022-03- IDA / 59930 Post Request for Bids Open - National 1,833,333.00 0.00 Implementat 2021-06-08 2021-06-13 2021-07-25 2021-08-24 2021-09-28 No.s Cottage Processing Management and Women & Envelope (1 envelope 27 ion Centers Youth Empowerment process) GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual APPEALSP-LGSCO-GO-01 / Production of Information, Education &Communication Project Management and Request for Single Stage - One materials / Knowledge IDA / 59930 Post Limited 8,240.00 14,793.04 Signed 2019-05-12 2019-08-05 2019-07-07 2019-08-26 2020-01-03 2020-03-25 Coordination Quotations Envelope sharing materials (Fact sheets, Newsletters, leaflets, handbills, manuals, briefs etc APPEALSP-LGSCO-GO-02 / Procurement of Communication equipment; (1)High Megapixel photo Technical Assistance, Request for Single Stage - One camera, (2)HD Professional IDA / 59930 Knowledge Management and Post Limited 4,330.00 174,430.32 Signed 2019-05-11 2019-05-24 2019-07-06 2019-06-20 2020-01-02 2019-08-27 Quotations Envelope Camera, (3) Medium PAS Communication (1);(4) Big Movable PAS(1),(5) Projector and Screen, (6) Media Mobile device APPEALSP-LGSCO-GO-03 / Technical Assistance, Request for Single Stage - One Production of Promotional IDA / 59930 Knowledge Management and Post Limited 10,990.00 10,877.06 Signed 2019-05-12 2019-05-05 2019-07-07 2019-07-02 2020-01-03 2019-09-06 Quotations Envelope items & Bill Boards/Sign posts Communication APPEALSP-LGSCO-GO-04 / Procurement of Office Furniture: 20 Executive Chairs Project Management and Request for Single Stage - One IDA / 59930 Post Limited 13,740.00 13,713.66 Signed 2019-04-27 2019-05-03 2019-06-22 2019-06-11 2019-12-19 2019-07-19 and Tables; Office fittings (e.g Coordination Quotations Envelope curtains,window blind,railings etc) APPEALSP-LGSCO-GO-05 / Procurement of Electrical Equipment and Appliances, 6 Infrastructure Support to Request for Single Stage - One units of 2HP Airconditioners IDA / 59930 Post Limited 18,930.00 5,099.93 Completed 2019-04-29 2019-04-30 2019-06-24 2019-05-31 2019-12-21 2019-09-06 Agribusiness Clusters Quotations Envelope for the training Hall, 30 units of fanS, calculators and Casting machine. APPEALSP-LGSCO-GO-06 / Provision of Alternative Source Infrastructure Support to Request for Single Stage - One of Energy for SCO (Inverter IDA / 59930 Post Limited 27,470.00 50,374.63 Signed 2019-05-14 2019-05-10 2019-07-09 2019-07-02 2020-01-05 2020-05-08 Agribusiness Clusters Quotations Envelope System/ Battery Banks and accessories etc) APPEALSP-LGSCO-GO-07 / Procurement of computers and accessories: 20 Nos Computer Laptops with carrier bags for projects officers, Project Management and Request for Single Stage - One IDA / 59930 Post Limited 28,830.00 56,284.84 Signed 2019-04-30 2019-05-02 2019-06-25 2019-07-01 2019-12-22 2019-07-31 External hard drive(EHD) and Coordination Quotations Envelope Flash drives, 20 units of Modem, Printers and Scanners, Global Positioning System (GPS) APPEALSP-LGSCO-GO-08 / Procurement of the following soft wares: 10 units of Database tracking soft ware, Project Management and Request for Single Stage - One IDA / 59930 Post Limited 21,560.00 15,595.85 Completed 2019-04-30 2019-07-15 2019-06-25 2019-07-16 2019-12-22 2019-08-06 5 users Smart draw for Coordination Quotations Envelope excelent chart and reporting; Computer aided design CAD Soft wares Page 1 APPEALSP-LGSCO-GO-09 / Under Project Management and Request for Single Stage - One Procurement of 1 unit of IDA / 59930 Post Limited 71,430.00 0.00 Implementati 2019-05-20 2019-05-30 2019-07-15 2020-01-11 Coordination Quotations Envelope project Utility vehicle on NG-LAGOS APPEALS-158835- Primary processing, Value GO-RFQ / Procurement of Addition, Post-Harvest Request for Single Stage - One IDA / 59930 Post Limited 83,330.00 229,662.72 Signed 2020-04-28 2020-04-23 2020-06-23 2020-05-06 2020-12-20 2020-06-02 facilities for the Establishment Management and Women & Quotations Envelope of Farmers Markets Youth Empowerment NG-LAGOS APPEALS-158940- Project Management and Request for Single Stage - One GO-RFQ / Procurement of 2 IDA / 59930 Post Limited 154,000.00 138,069.27 Signed 2020-03-28 2020-03-30 2020-05-23 2020-04-24 2020-11-19 2020-04-28 Coordination Quotations Envelope Utility vehicles NG-LAGOS APPEALS-158738- Primary processing, Value GO-RFQ / Procurement of Addition, Post-Harvest Request for Single Stage - One IDA / 59930 Post Limited 27,780.00 0.00 Canceled 2020-09-26 2020-11-21 2021-05-20 facilities for the Establishment Management and Women & Quotations Envelope of One-Stop-Shop Youth Empowerment APPEALSP-LGSCO-GO-9C / Technical Assistance, Pending Procurement of (Furniture, Request for Single Stage - One IDA / 59930 Knowledge Management and Post Limited 27,778.00 0.00 Implementati 2021-08-08 2021-10-03 2022-04-01 Workstation etc)for the Quotations Envelope Communication on Establishment of Library APPEALSP-LGSCO-GO-08C / Technical Assistance, Pending Procurement of knowleged Request for Single Stage - One IDA / 59930 Knowledge Management and Post Limited 27,778.00 0.00 Implementati 2021-08-04 2021-09-29 2022-03-28 material repository for Quotations Envelope Communication on Development of e-library NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-LAGOS APPEALS-156950- Consultant CS-CQS / Feasibility study on Production and Productivity IDA / 59930 Post Qualification Open - National 40,280.00 0.00 Under Review 2020-04-30 2020-06-04 2020-05-21 2020-09-14 2020-07-04 2020-07-20 2020-08-03 2020-09-07 2021-03-06 the establishment of bird Enhancement Selection hatchery in the State NG-LAGOS APPEALS-162010- CS-CQS / Engagement of a Primary processing, Value Consultants for the facilitation Consultant Addition, Post-Harvest of all activities for the PWDs IDA / 59930 Post Qualification Open - National 33,330.00 0.00 Under Review 2020-03-09 2020-03-20 2020-03-30 2020-05-13 2020-06-12 2020-07-17 2021-01-13 Management and Women & (Training, Mentoring, Selection Youth Empowerment Monitoring etc) support under the WYEP NG-LAGOS APPEALS-162013- Primary processing, Value CS-CQS / Engagement of Consultant Addition, Post-Harvest Under Consultancy to facilitate IDA / 59930 Post Qualification Open - National 27,780.00 0.00 2020-05-25 2019-06-20 2020-06-15 2020-07-29 2020-08-28 2020-10-02 2021-03-31 Management and Women & Implementation International Market Selection Youth Empowerment Expectation for Aquaculture NG-LAGOS APPEALS-161811- Primary processing, Value Consultant CS-CQS / Feasibility Study on Addition, Post-Harvest Under IDA / 59930 Post Qualification Open - National 27,780.00 0.00 2020-04-20 2020-05-28 2020-05-11 2020-06-24 2020-07-24 2020-08-28 2021-02-24 production of Egg Powder Management and Women & Implementation Selection technology in the State. Youth Empowerment NG-LAGOS APPEALS-161999- CS-CQS / Technical Consultant Assistance for the conduct of Production and Productivity IDA / 59930 Post Qualification Open - National 27,780.00 0.00 Canceled 2020-03-31 2020-04-21 2020-06-04 2020-07-04 2020-08-08 2021-02-04 Need Assessment for the Enhancement Selection selected value chains of Poultry, Aquaculture and Rice. NG-LAGOS APPEALS-162000- CS-CQS / Consultancy to Consultant source for climate smart, Production and Productivity IDA / 59930 Post Qualification Open - National 27,780.00 0.00 Canceled 2020-05-18 2020-06-08 2020-07-22 2020-08-21 2020-09-25 2021-03-24 nutrition sensitive and Enhancement Selection improved technologies to enhance Farmers productivity NG-LAGOS APPEALS-162005- Technical Assistance, Consultant CS-CQS / Consultancy on IDA / 59930 Knowledge Management and Post Qualification Open - National 27,880.00 0.00 Canceled 2020-06-09 2020-06-30 2020-08-13 2020-09-12 2020-10-17 2021-04-15 Production of Project Communication Selection Documentary NG-LAGOS APPEALS-162001- Consultant CS-CQS / Technical Support Project Management and IDA / 59930 Post Qualification Open - National 27,780.00 0.00 Canceled 2020-04-28 2020-05-19 2020-07-02 2020-08-01 2020-09-05 2021-03-04 to strengthen the fiduciary Coordination Selection system of the Project NG-LAGOS APPEALS-162006- CS-CQS / Technical Technical Assistance, Consultant Assistance on Production of IDA / 59930 Knowledge Management and Post Qualification Open - National 41,670.00 0.00 Canceled 2020-04-29 2020-05-20 2020-07-03 2020-08-02 2020-09-06 2021-03-05 Knowledge and learning Communication Selection products NG-LAGOS APPEALS-162008- CS-CQS / Consultancy Consultant services for the Enviromental Project Management and IDA / 59930 Post Qualification Open - National 33,330.00 0.00 Canceled 2020-03-23 2020-04-13 2020-05-27 2020-06-26 2020-07-31 2021-01-27 and Social Impact Assesmemt Coordination Selection (including ESMP) for Rural Infrastructural support NG-LAGOS APPEALS-158859- Consultant CS-CQS / Engagement of Infrastructure Support to IDA / 59930 Post Qualification Open - National 36,105.55 0.00 Canceled 2020-04-15 2020-05-06 2020-06-19 2020-07-19 2020-08-23 2021-02-19 Consultant for the Design of Agribusiness Clusters Selection 14.66 Km Farm Access Road. Page 2 NG-LAGOS APPEALS-162012- CS-CQS / Consultancy on Primary processing, Value Market Sensitivity Analysis Consultant Addition, Post-Harvest and Determination of IDA / 59930 Post Qualification Open - National 27,780.00 0.00 Canceled 2020-04-30 2020-05-21 2020-07-04 2020-08-03 2020-09-07 2021-03-06 Management and Women & Consumer Preference for Selection Youth Empowerment Poultry, Aquaculture and Rice value chains INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual APPEALSP-LGSCO-CS-01 / Consultancy on the conduct of Primary processing, Value Individual Technical Feasibility Studies Addition, Post-Harvest IDA / 59930 Post Consultant Limited 13,740.00 13,793.10 Completed 2019-04-18 2019-06-26 2019-04-23 2019-05-03 2019-05-14 2019-07-04 2019-06-18 2019-08-23 2019-12-15 2019-12-06 on Market Information / Management and Women & Selection Opprtunities for the selected Youth Empowerment value chains in the State. APPEALSP-LGSCO-CS-02 / Consultancy for the Technical Assistance, Individual engagement of Technical IDA / 59930 Knowledge Management and Post Consultant Limited 13,740.00 0.00 Canceled 2019-05-19 2019-06-26 2019-05-24 2019-06-14 2019-07-19 2020-01-15 assistant to strengthen the Communication Selection financial management of the Project. APPEALSP-LGSCO-CS-03 / Technical Assistance, Individual Conduct of Survey on effective IDA / 59930 Knowledge Management and Post Consultant Limited 13,740.00 0.00 Canceled 2019-05-21 2019-06-26 2019-05-26 2019-07-30 2019-06-16 2019-07-21 2020-01-17 communication channels in Communication Selection Lagos State APPEALSP-LGSCO-CS-04 / Individual Engagement of consultant for Project Management and IDA / 59930 Post Consultant Limited 8,240.00 13,226.06 Under Review 2019-09-26 2019-06-26 2019-10-01 2019-08-01 2019-10-22 2019-09-26 2019-11-26 2019-09-13 2020-05-24 2020-01-22 the development of greivance Coordination Selection redress mechanism(GRM) APPEALSP-LGSCO-CS-05 / Technical Assistance, Individual Production & Airing of Jingles IDA / 59930 Knowledge Management and Post Consultant Limited 13,740.00 13,679.90 Under Review 2019-04-29 2019-06-26 2019-05-04 2019-06-27 2019-05-25 2019-07-26 2019-06-29 2019-08-05 2019-12-26 2020-03-02 (Yoruba, English, Pidgin on Communication Selection Radio NG-LAGOS APPEALS-162004- CS-INDV / Consultancy on Technical Assistance, Individual News feature of project IDA / 59930 Knowledge Management and Post Consultant Limited 19,440.00 0.00 Under Review 2020-03-31 2019-07-03 2020-04-05 2020-04-26 2020-05-31 2020-11-27 activities in print and Communication Selection electronic media NG-LAGOS APPEALS-158943- Technical Assistance, Individual CS-INDV / Conduct of Survey IDA / 59930 Knowledge Management and Post Consultant Limited 27,780.00 0.00 Under Review 2020-04-20 2020-07-07 2020-04-25 2020-05-16 2020-06-20 2020-12-17 on effective communication Communication Selection channels in Lagos State NG-LAGOS APPEALS-158856- Individual Project Management and CS-INDV / Consultancy for IDA / 59930 Post Consultant Limited 8,330.00 0.00 Canceled 2020-06-10 2020-06-15 2020-07-06 2020-08-10 2021-02-06 Coordination GBV mapping in the State Selection NG-LAGOS APPEALS-158845- CS-INDV / Engagement of Individual Infrastructure Support to Consultant for preparation of IDA / 59930 Post Consultant Limited 13,890.00 0.00 Canceled 2020-09-23 2020-09-28 2020-10-19 2020-11-23 2021-05-22 Agribusiness Clusters ESMP for 3NO Cottage Selection Industries NG-LAGOS APPEALS-158903- Individual CS-INDV / Consultancy on the Infrastructure Support to IDA / 59930 Post Consultant Limited 16,670.00 0.00 Canceled 2020-04-15 2020-04-20 2020-05-11 2020-06-15 2020-12-12 Design and Supervision of Agribusiness Clusters Selection Energy Interventions NG-LAGOS APPEALS-158889- CS-INDV / Engagement of Individual Infrastructure Support to consultant for the Design of 2 IDA / 59930 Post Consultant Limited 25,000.00 0.00 Canceled 2020-04-24 2020-04-29 2020-05-20 2020-06-24 2020-12-21 Agribusiness Clusters Nos of Jetties (Badagry; Selection Agbowa) NG-LAGOS APPEALS-158916- Individual CS-INDV / Engagement of Project Management and IDA / 59930 Post Consultant Limited 27,780.00 0.00 Canceled 2020-10-19 2020-10-24 2020-11-14 2020-12-19 2021-06-17 Technical Assistant on Coordination Selection Agricultural Production Survey Individual APPEALSP-LGSCO-CS-03C / Infrastructure Support to Pending IDA / 59930 Post Consultant Limited 19,444.00 0.00 2021-06-22 2021-06-27 2021-07-18 2021-08-22 2022-02-18 Design of Energy for Clusters Agribusiness Clusters Implementation Selection APPEALSP-LGSCO-CS-02C / Individual Infrastructure Support to Pending Engagement of consultant for IDA / 59930 Post Consultant Limited 20,834.00 0.00 2021-05-29 2021-06-03 2021-06-24 2021-07-29 2022-01-25 Agribusiness Clusters Implementation the design of Jetties Selection Individual NG-LAGOS APPEALS-158941- Project Management and IDA / 59930 Post Consultant Limited 13,890.00 0.00 Canceled 2020-04-02 2020-04-07 2020-04-28 2020-06-02 2020-11-29 CS-INDV / Market Price Survey Coordination Selection Page 3 Procurement Plan Community Development Program Support Project – Phase III (Programme National de Développement Participatif – Phase III) I. General 1. Bank’s approval Date of the procurement Plan [Original: February 2016]: Revision of Updated Procurement Plan, May 05, 2017 2. Date of General Procurement Notice: February 15, 2016 3. Period covered by this procurement plan: The procurement period of project covered from year January to December 2017 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Comments Threshold US$ 1. ICB and LIB (Goods) Above US$ 1,500,000 All 2. NCB (Goods) None 3. ICB (Works) Above US$ 5 million All 4. NCB (Works) Above US$ 5 million 5. DC (Non-Consultant Services) none 2. Prequalification. Not applicable. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: Procurement (works, goods and services) for subprojects of communes, such as small infrastructure, social infrastructure, classrooms, health centers, community halls, , minor works or rehabilitation, will be procured on the basis of community participation in accordance with the clause 3.19 of the World Bank Procurement Guidelines (Community Participation in Procurement), and the Guidelines for Simplified Procurement and Disbursement for Community-Based Investments (March 3, 1998) detailed in the specific manual or guidelines to communes approved by the bank. 4. Reference to (if any) Project Operational/Procurement Manual: Guide des Acteurs intervenant dans le processus de passation et de l’exécution des marchés communaux financés par le PNDP – Juin 2010, révisé en Janvier 2016 May 05, 2017 5. Any Other Special Procurement Arrangements: 5 ICB works packages will be financed under - retroactive financing 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness (including those that are subject to retroactive financing and advanced procurement) 1 2 3 4 5 6 7 Ref. Descriptio Estimate Packag Domesti Review Comments No. n d es c by Bank Cost Prefere (Prior / US$ nce Post) million (yes/no) Summary of 2.328 2 No Prior the ICB (Goods) Summary of 0.700 1 No Post 1st contract the NCB for Prior (Goods) Review III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comments Threshold 1. Competitive Methods (Firms) Above US$ 500,000 2. Single Source (Firms) Above US$ 500,000 Justification prior reviewed by bank 3. Individual Above US$ 200,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: not applicable 4. Consultancy Assignments with Selection Methods and Time Schedule May 05, 2017 1 2 3 4 5 6 7 Ref Description of Estimate Selection Review Expecte Comment . Assignment d cost method by the d s/ No (US$ Bank proposal completio equivale (prior/po s n date nt) st) submissi on date For the Support for the 1 Post first year preparation of 20,000 IC 21/08/15 24/09/15 Statutory Instruments (30 days) 2 Study on the definition 40,000 Post 22/04/16 of a planning CQS 25/01/16 (03 methodology at months) regional level 3 Study on the planning 40,000 CQS Post 25/01/16 22/04/16 process in the (03 communes and urban months) communities 4 Study for the 20,000 IC Post 19/02/16 24/03/16 establishment of local (30 days) public service in communes 5 Study on the 40,000 CQS Post 11/04/16 18/07/16 sustainability of the (03 PNDP months) 6 Evaluation of the 40,000 CQS Post 13/07/16 18/10/16 decentralization (03 process in months) Cameroon/supports to the finalization of the national strategy for decentralization 7 Selection of a 20,000 IC Post 20/11/15 30/12/15 consultant to develop (30 days) the practitioner's manual for the 31 communes 8 Municipal staff training 100,000 SSS Prior NA Service provided by the CEFAM (Conventio n) 9 Training of 100,000 SSS Prior NA Service procurement provided commissions by ARMP (Conventio n) 10 Financial Audits of the 150,000 LCS Post 10/03/15 Contract project for the first 2 for 2 years years 11 legal advice 10,000 IC Post 28/12/15 Annual contract May 05, 2017 1 2 3 4 5 6 7 Ref Description of Estimate Selection Review Expecte Comment . Assignment d cost method by the d s/ No (US$ Bank proposal completio equivale (prior/po s n date nt) st) submissi on date 12 Design and 90,000 CQS Post 12/02/16 22/08/16 development of an (06 internet portal on the months) PNDP and communes 13 Translation of 90,000 CQS Post 11/05/16 20/08/16 documents (03 months) 14 Technical audit 80,000 QCBS Post 16/02/16 31/08/16 (06 months) 15 Beneficiary assessment 50,000 QCBS Post 15/11/16 22/05/17 (06 months) 16 Environmental and 70,000 QCBS Post 13/12/16 26/06/17 Social Assessment (06 months) 17 Service Follow-up of training SSS Prior NA provided deployment and by AIMF 70,000 technical assistance to expert Sim_ba software in (Conventio communes n) 18 IC Post 27/05/15 Annual contract (the 10,000 current contract ends June Insurance advice 30, 2015) 19 QCBS Post 01/12/16 16/04/16 Preparation of CDPs for 80,000 (06 the 31 communes months) May 05, 2017 PROCUREMENT Cameroon : Community Development Program Support Project-Phase III PLAN General Information Country: Cameroon Bank’s Approval Date of the Original Procurement Plan: 2017-05- 30 2021-06- Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P144637 GPN Date: 01 2016-09- Project Name: Community Development Program Support Project-Phase III 06 Loan / Credit No: IDA / 57180, IDA / D2990, IDA / 62240 CELLULE REGIONALE DE COORDONATION - EXTREME NORD Executing Agency(ies): WORKS Activity Reference No. Procurement Estimate Actual Draft Pre- Draft Bidding Specific Proposal Bid Evaluation Loan / Credit Market Procurement Prequalificati High SEA/SH Process Prequalification Bidding Documents Contract / Description Component Review Type Method Document d Amount qualification Document / Procurement Notice Submission / Report and Signed Contract No. Approach Process on (Y/N) Risk Status Evaluation Report as Issued Completion Type Amount (US$) Documents Justification / Invitation Opening / Minutes Recommendation (US$) Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned for Award Actual Planned Actual Planne d CM-CRC EXTREME NORD- 8012-CW-RFQ / Petits Component C: travaux d'aménagement des Coordination, management, Request for Single Stage - One Complete 2017-03- 2017-05- 2017-05- 2017-07- 2017- bureaux (cloisonnement des IDA / 57180 Post Limited 5,600.00 4,722.91 monitoring and evaluation Quotations Envelope d 10 26 05 22 06-04 bureaux, équipement and communication étagères pour classement, etc...) à la CRC EN CM-CRC EXTREME NORD- 8013-CW-RFQ / Construct et équipt d'01 bloc de 02 de sc et d'un bloc de Lt à trois comparts à l'EP de Dogba, Component A: Local Request for Single Stage - One 154,638.0 139,405. 2017-03- 2017-06- 2017-05- 2017-10- 2017- au lycée de Gayack et IDA / 57180 Post Limited Signed development support Quotations Envelope 0 62 25 12 20 30 09-17 Construction de 01 bloc de hangar de 52 pces et d'un bloc de Lt à trois comparts au marché de Papata,Commune de Mra II CM-CRC EXTREME NORD- 8016-CW-RFQ / Constructde 6 forages équipés de PMH à Tchékéhi, Component A: Local Request for Single Stage - One 68,485.3 2017-03- 2017-05- 2017-05- 2017-09- 2017- IDA / 57180 Post Limited 96,000.00 Signed Mbokouré, Magaldao development support Quotations Envelope 0 25 30 20 12 08-18 Toupéo, Soukkoungo Galdima, Bourango et Bandalaré, commune de Pétté CM-CRC EXTREME NORD- 8035-CW-RFQ / Construct d'un magasin de stockage à Kéné-Kéné, Construct d'un Component A: Local Request for Single Stage - One 68,573.2 2017-03- 2017-05- 2017-05- 2017-09- 2017- IDA / 57180 Post Limited 82,609.00 Signed bloc de 02 sc équipées à development support Quotations Envelope 6 25 30 20 12 08-18 l'EP de Djafgué, et Construct d'un bloc de Lt à l'EP de Djafgué commune de Pétté CM-CRC EXTREME NORD- 8036-CW-RFQ / Constr d'un forage pastoral à énergie solaire équipé de 02 abreuvoirs à Balaza Lawane Component A: Local Request for Single Stage - One 76,928.1 Complete 2017-03- 2017-05- 2017-05- 2017-09- 2017- IDA / 57180 Post Limited 82,196.00 (Tchalloudi mango) et development support Quotations Envelope 6 d 25 15 20 12 08-18 Constr d'un forage pastoral à énergie solaire équipé de 02 abreuvoirs à Kongola Saïd, Cne Maroua 3 CM-CRC EXTREME NORD- 8037-CW-RFQ / Construct d'un bloc de 02 sc équipées et d'un bloc de Lt à trois Component A: Local Request for Single Stage - One 136,106.0 2017-03- 2017-05- 2017- IDA / 57180 Post Limited 0.00 Canceled comparts à l'EP de Mayel development support Quotations Envelope 0 25 20 08-18 Béi, à l'EP de Bao Hosséré II et à l'EP de Palaoudi, commune Maroua 1 CM-CRC EXTREME NORD- 8040-CW-RFQ / construction d'un bloc Component A: Local Request for Single Stage - One 46,402.6 2017-03- 2017-05- 2017-05- 2017-08- 2017- maternel à l'école Maternelle IDA / 57180 Post Limited 57,421.00 Signed development support Quotations Envelope 2 25 15 20 17 08-18 de Zokok-Laddo et branchement au réseau d'alimentation en eau potable, commune de Maroua 1 CM-CRC EXTREME NORD- 8042-CW-RFQ / Construction de trois Component A: Local Request for Single Stage - One 39,964.5 2017-03- 2017-05- 2017-05- 2017-09- 2017- forages équipés de pompe à IDA / 57180 Post Limited 46,689.00 Signed development support Quotations Envelope 9 25 25 20 12 08-18 motricité humaine à Ouro Dow, Goni Bello et Yoldéo Guiziga, Commune Maroua 1 CM-CRC EXTREME NORD- 8043-CW-RFQ / Construction de d'un bloc de 02 salles de classe Component A: Local Request for Single Stage - One 77,069.0 2017-03- 2017-04- 2017-05- 2017-07- 2017- IDA / 57180 Post Limited 92,247.00 Signed équipées et d'un bloc de development support Quotations Envelope 7 25 25 20 07 08-18 latrines à trois compartiments à l'EP Masfaï et au CES de Boula, commune de Mokolo CM-CRC EXTREME NORD- 8045-CW-RFQ / Construction de 2 forages Component A: Local Request for Single Stage - One 30,426.6 2017-03- 2017-04- 2017-05- 2017-07- 2017- IDA / 57180 Post Limited 33,787.00 Signed équipés de PMH un à Ouro development support Quotations Envelope 4 25 05 20 07 08-18 Kessoum et à Mounam, commune de Mokolo CM-CRC EXTREME NORD- 8047-CW-RFQ / Construction d'un ouvrage Component A: Local Request for Single Stage - One 81,284.7 Complete 2017-03- 2017-03- 2017-05- 2017-10- 2017- de franchissement et IDA / 57180 Post Limited 87,751.00 development support Quotations Envelope 8 d 25 31 20 31 08-18 assainissement(radier-dalot) sur le Mayo Kwayaga, dans la commune de Mogodé CM-CRC EXTREME NORD- 8050-CW-RFQ / Construction d'un bloc de 02 salles de classe équipées Component A: Local Request for Single Stage - One 85,878.4 Complete 2017-03- 2017-04- 2017-05- 2017-06- 2017- IDA / 57180 Post Limited 90,443.00 et d'un bloc de latrines à development support Quotations Envelope 9 d 25 06 20 21 08-18 trois compartiments à l'EP de Saoudjo et au CES de Madaka, commune de Bogo CM-CRC EXTREME NORD- 8053-CW-RFQ / Component A: Local Request for Single Stage - One 28,863.6 2017-03- 2017-04- 2017-05- 2017-07- 2017- Construction d'un forage IDA / 57180 Post Limited 32,294.00 Signed development support Quotations Envelope 3 25 06 20 05 08-18 équipé de PMH à Dambaye et à Bagalaf commune de Bogo CM-CRC EXTREME NORD- 8054-CW-RFQ / construction d'un bloc de deux (02) salles de classe equipees et un (01) bloc Component A: Local Request for Single Stage - One 178,787.0 163,753. Complete 2017-03- 2017-07- 2017-05- 2017-10- 2017- IDA / 57180 Post Limited latrine a trois (03) development support Quotations Envelope 0 46 d 25 07 20 27 09-17 compartiments a l'EP de honkol, a l'EP de darsala, a l'EP de dabanga et l'equipement en meubles a l'ecole maternelle de logone birni CM-CRC EXTREME NORD- 8056-CW-RFQ / construction de trois forages équipés de pompe à Component A: Local Request for Single Stage - One 44,814.2 Complete 2017-03- 2017-04- 2017-05- 2017-06- 2017- IDA / 57180 Post Limited 50,245.00 motricité humaines: un à development support Quotations Envelope 4 d 25 20 20 30 08-18 l'EP de Dabanga, un à l'EP de Honkol et un à l'EP de Darsala dans la Commune de Logone Birni CM-CRC EXTREME NORD- 8057-CW-RFQ / construction d'un forage Component A: Local Request for Single Stage - One 41,388.9 Complete 2017-03- 2017-04- 2017-05- 2017-06- 2017- pastoral équipé de pompe IDA / 57180 Post Limited 45,860.00 development support Quotations Envelope 5 d 25 20 20 30 08-18 immergée à énergie photovoltaique à Sahaba 1 dans la Commune de Logone Birni CM-CRC EXTREME NORD- 8068-CW-RFQ / réhabilitation de la mare artificielle et la construction Component A: Local Request for Single Stage - One 114,601.0 91,831.5 Complete 2017-03- 2017-07- 2017-05- 2017-11- 2017- IDA / 57180 Post Limited d'un forage pastoral à development support Quotations Envelope 0 8 d 25 07 20 27 09-17 energie photovoltaique à Mogong dans la commune de Moutourwa CM-CRC EXTREME NORD- 8072-CW-RFQ / construction de 2 blocs de deux salles de classe Component A: Local Request for Single Stage - One 115,353.0 102,090. 2017-03- 2017-03- 2017-05- 2017-06- 2017- IDA / 57180 Post Limited Signed équipées et de 2 blocs de development support Quotations Envelope 0 02 25 23 20 12 08-18 latrines à trois compartiments EP NGré et EP Afadé dans la commune de Makary CM-CRC EXTREME NORD- 38352-CW-RFB / Travaux de construction d'un forage PMH à Kaliao, Goulmoyo, Mbozo Mofou, Balewa et Component A: Local Single Stage - One 260,774.0 200,809. 2017-11- 2017-11- 2017-12- 2018-01- 2018-01- 2018-02- 2018-01- 2018-03- 2018-04- 2018- Manguirdla (Lot 1), IDA / 57180 Post Request for Bids Open - National Signed development support Envelope 0 46 27 01 02 13 15 12 19 19 04 06-17 Gadjawai, Guivel, Quartier Méri centre, Nguissar et Kilwo-Valta (Lot 2), Moundour Foulbé, Dogba Maliki, Magawa, Houloum et Tchaki djébé (Lot 3) C-MERI CM-CRC EXTREME NORD- 38353-CW-RFQ / Travaux de Construction d'un bloc Component A: Local Request for Single Stage - One 36,949.0 2017-12- 2017-12- 2018-01- 2018-07- 2018- de deux salles de classe IDA / 57180 Post Limited 51,198.00 Signed development support Quotations Envelope 6 02 23 27 12 04-27 équipées et un bloc de latrines au C.E.S de Manguirdla dans la commune de Meri CM-CRC EXTREME NORD- 38354-CW-RFQ / Travaux de construction d'un bloc de Component A: Local Request for Single Stage - One 67,277.8 2017-12- 2017-12- 2018-01- 2018-04- 2018- deux salles de classe IDA / 57180 Post Limited 95,682.00 Signed development support Quotations Envelope 1 02 28 27 04 04-27 équipées avec latrines à l'EP de Domo Doukou et à l'EP de Riganda COMMUNE DE YAGOUA CM-CRC EXTREME NORD- 38355-CW-RFQ / Travaux de construction d'un bloc de deux salles de classe Component A: Local Request for Single Stage - One 82,938.9 2017-12- 2017-12- 2018-01- 2018-03- 2018- IDA / 57180 Post Limited 99,316.00 Signed équipées et un bloc de development support Quotations Envelope 4 02 22 27 27 04-27 latrines à l'EP de Pitoa- Kolara et à l'EP de Badadji COMMUNE DE MOULVOUDAYE CM-CRC EXTREME NORD- 38356-CW-RFQ / Travaux de construction d'un bloc de Component A: Local Request for Single Stage - One 79,132.8 Complete 2017-12- 2017-12- 2018-01- 2018-04- 2018- deux salles équipées et un IDA / 57180 Post Limited 91,386.00 development support Quotations Envelope 6 d 02 22 27 09 04-27 bloc de latrines à l'EP de Djagalaye et au CES de Hardé COMMUNE DE MAROUA Ier CM-CRC EXTREME NORD- 38357-CW-RFQ / Travaux de construction d'un bloc de deux salles équipées et un Component A: Local Request for Single Stage - One 82,420.0 Complete 2017-12- 2017-12- 2018-01- 2018-04- 2018- bloc de latrines CES de IDA / 57180 Post Limited 89,342.00 development support Quotations Envelope 0 d 02 22 27 04 04-27 Balda et Construction d'un bloc de deux salles de classe équipées à l'EP de Sedek Ouro-Gabdo COMMUNE DE BOGO CM-CRC EXTREME NORD- 38358-CW-RFQ / Travaux de Construction de 01 forage PMH A EM de Ldamtsai, Mandaka Component A: Local Request for Single Stage - One 133,467.0 117,088. 2017-12- 2017-12- 2018-01- 2018-04- 2018- Mpoldok, Camp mission de IDA / 57180 Post Limited Signed development support Quotations Envelope 0 54 02 26 27 08 04-27 Tourou, Koudougour II Loctcha, Katamsa Sikia, Gouldoum Moufou, Houdango Dandi et Ouro Bocki(2lots) dans la commune de Mokolo CM-CRC EXTREME NORD- 38359-CW-RFQ / Travaux Component A: Local Request for Single Stage - One 14,057.2 2017-12- 2018-01- 2018-01- 2018-04- 2018- de construction d' un forage IDA / 57180 Post Limited 15,816.00 Signed development support Quotations Envelope 0 02 31 27 05 03-28 équipé de PMH à l'EP de Riganda commune YAGOUA CM-CRC EXTREME NORD- 38360-CW-RFQ / Travaux de construction d'un forage équipé de PMH à l'EP de Component A: Local Request for Single Stage - One 61,321.8 2017-12- 2017-12- 2018-01- 2018-03- 2018- IDA / 57180 Post Limited 72,362.00 Signed Badadji, à l'EP de Pitoa- development support Quotations Envelope 8 02 22 27 26 04-27 Kolara, au lycée de Kolara et à Gadjia Padjonré COMMUNE DE MOULVOUDAYE CM-CRC EXTREME NORD- 38361-CW-RFQ / Travaux de construction d'un forage Component A: Local Request for Single Stage - One 35,012.7 2017-12- 2017-12- 2018-01- 2018-04- 2018- équipé de PMH à l'EP de IDA / 57180 Post Limited 48,640.00 Signed development support Quotations Envelope 5 02 22 27 09 04-27 Yamdjidjing, à l'EP de Djagalaye et à Zébé COMMUNE DE MAROUA Ier CM-CRC EXTREME NORD- 38362-CW-RFQ / Travaux de Construction d'un forage équipé de pompe à motricité humaine à l'EP de Component A: Local Request for Single Stage - One 67,323.3 2017-12- 2017-12- 2018-01- 2018-04- 2018- IDA / 57180 Post Limited 94,648.00 Signed Sedek Ouro Gabdo à Ardo development support Quotations Envelope 9 02 22 27 04 04-27 Foulbé Tankirou à Gagnéri Kourdaya à Guinlaye Guizigaré et Guinlaye Moufouré dans la commune BOGO CM-CRC EXTREME NORD- 38386-CW-RFQ / Travaux de construction d'un bloc de deux salles de classe équipées avec latrines à l'EP Component A: Local Single Stage - One 237,076.0 213,978. 2017-11- 2017-12- 2017-12- 2018-01- 2018-01- 2018-02- 2018-02- 2018-03- 2018-04- 2018- de Mouftoum et à l'Ecole IDA / 57180 Post Request for Bids Open - National Signed development support Envelope 0 48 27 19 02 13 25 12 01 19 09 06-17 Bilingue de Rhoumzou (Lot 1), au lycée de SIR et à l'EPB de Kwashimalda (Lot 2) , au CES de Goura (Lot 3) dans la commune de Mogode CM-CRC EXTREME NORD- 38387-CW-RFB / Travaux de construction d'un bloc de deux salles équipées et un bloc de latrines à l'EP de Component A: Local Single Stage - One 233,628.0 193,465. 2017-11- 2017-11- 2017-12- 2018-01- 2018-02- 2018-02- 2018-02- 2018-03- 2018-04- 2018- IDA / 57180 Post Request for Bids Open - National Signed Ldamang et à l'EP de Ndrock development support Envelope 0 09 27 01 02 13 13 12 14 19 06 06-17 Tourou (Lot 1), l'EP de Moufou-sud et à l'EP de Zili Yolel (Lot 2),au CES de Mandaka (Lot 3) dans la commune de MokolO CM-CRC EXTREME NORD- 38388-CW-RFB / Travaux de construction d'un radier Component A: Local Single Stage - One 27,858.8 2017-11- 2017-12- 2017-12- 2018-01- 2018-02- 2018-02- 2018-02- 2018-03- 2018-04- 2018- IDA / 57180 Post Request for Bids Open - National 34,548.00 Signed de 12 ml sur le mayo Teki development support Envelope 7 27 11 02 13 19 12 19 19 04 06-17 dans la localité de Teki, dans la commune de Mogode CM-CRC EXTREME NORD- 58606-CW-RFQ / Travaux de Construct d'un bloc de Component A: Local Request for Single Stage - One 73,189.1 2017-10- 2017-12- 2017-12- 2018- 02 sc équipées et d'un bloc IDA / 57180 Post Open - National 86,221.00 Signed development support Quotations Envelope 1 08 03 04 03-03 de Lt à trois comparts à l'EP de Mayel Béi, et à l'EP de Palaoudi l cmne Maroua 1 CM-CRC EXTREME NORD- 58541-CW-RFQ / Travaux de construction d'un forage Component A: Local Request for Single Stage - One 42,885.4 2018-05- 2018-05- 2018-07- 2018-09- 2018- productif équipé de pompe IDA / 57180 Post Limited 63,894.00 Signed development support Quotations Envelope 1 06 17 08 11 10-06 manuelle à EP Louguéré à EP Ouro Nangué à Fakalao à Hodango CM-CRC EXTREME NORD- 58600-CW-RFQ / Travaux de construction d'un bloc de 02 salles de classe équipées Component A: Local Request for Single Stage - One 67,400.3 2018-05- 2018-05- 2018-07- 2018-09- 2018- IDA / 57180 Post Limited 93,735.00 Signed et construction d'un bloc de development support Quotations Envelope 4 06 17 01 11 09-29 latrines à trois compartiment à EP de WOUYANG et à l'EP de GONOZO CM-CRC EXTREME NORD- 58693-CW-RFQ / Travaux de Construction d'un atelier de maçonnerie au CETIC de Component A: Local Request for Single Stage - One 43,242.0 Complete 2018-05- 2018-05- 2018-07- 2018-09- 2018- IDA / 57180 Post Limited 68,198.00 Loulou et'un bloc de latrines development support Quotations Envelope 6 d 06 17 08 11 11-05 à trois compartiments au CETIC de Loulou COMMUNE DE NDOUKOULA CM-CRC EXTREME NORD- 58296-CW-RFQ / Travaux de construction d'un bloc de 02 salles de classe équipées et d'un bloc de latrines à Component A: Local Request for Single Stage - One 142,608.0 118,724. Complete 2018-05- 2018-05- 2018-07- 2018-09- 2018- IDA / 57180 Post Limited trois compartiments à l'EP development support Quotations Envelope 0 87 d 06 10 08 10 10-06 de GUIRIOU CENTRE, (lot 01) au Lycée de DOM PYA, à la SAR/SM de Gobo(lot02) dans la cmne de GOBO Page 1 CM-CRC EXTREME NORD- 58490-CW-RFQ / Travaux de construction d'un bloc de Component A: Local Request for Single Stage - One 18,969.0 2018-05- 2018-09- 2018-07- 2018-12- 2018- latrines a quatre (04) IDA / 57180 Post Limited 22,188.00 Signed development support Quotations Envelope 7 06 05 08 26 10-06 compartiments au marché de GOBO et de NOULDAINA dans la cmne de GOBO CM-CRC EXTREME NORD- 58375-CW-RFQ / Travaux Component A: Local Request for Single Stage - One 13,046.6 Complete 2018-05- 2018-05- 2018-07- 2018-09- 2018- de construction d'un forage IDA / 57180 Post Limited 15,668.00 development support Quotations Envelope 9 d 06 10 08 17 08-07 équipé de PMH à l'EP de GUIRIOU CENTRE CM-CRC EXTREME NORD- 58689-CW-RFQ / Travaux de construction d'un bloc de Component A: Local Request for Single Stage - One 35,806.9 Complete 2018-05- 2018-06- 2018-07- 2018-10- 2018- 02 salles de classe équipées IDA / 57180 Post Limited 47,536.00 development support Quotations Envelope 5 d 06 07 08 10 10-06 et d'un bloc de latrines à trois compartiments au CES de Doukroye CM-CRC EXTREME NORD- 58628-CW-RFQ / Travaux de construction d'un forage Component A: Local Request for Single Stage - One 10,491.3 2018-05- 2018-06- 2018-07- 2018-10- 2018- IDA / 57180 Post Limited 15,272.00 Signed équipé de PMH à l'EP de development support Quotations Envelope 3 06 13 08 15 10-06 Daloa (Doukroye) dans la cmne de KAIKAI CM-CRC EXTREME NORD- 58637-CW-RFQ / Travaux d'achevement de la Construction des ouvrages Component A: Local Request for Single Stage - One 15,519.7 Complete 2018-05- 2018-07- 2018-10- 2018- annexes d'embarquement IDA / 57180 Post Limited 33,961.00 development support Quotations Envelope 4 d 06 08 10 09-06 (quaie dembarquement et hangar d'abris)des pirogues à LOUGOUANG MASSOUANG dans la cmne de Kaikai CM-CRC EXTREME NORD- 58605-CW-RFQ / Travaux de construction d'un bloc de 02 salles de classe équipées Component A: Local Request for Single Stage - One 73,407.1 2018-05- 2018-05- 2018-07- 2018-10- 2018- IDA / 57180 Post Limited 95,312.00 Signed et d'un bloc de latrines à development support Quotations Envelope 8 06 29 08 10 10-06 trois compartiments à EP de Balane au CES de Sirlawé dans la cmne de KAR-HAY CM-CRC EXTREME NORD- 58552-CW-RFQ / Travaux de construction d'un forage équipé de PMH à l'EP de Component A: Local Request for Single Stage - One 65,668.0 2018-05- 2018-05- 2018-07- 2018-10- 2018- IDA / 57180 Post Limited 91,324.00 Signed Damdama à l'EP de development support Quotations Envelope 7 06 29 08 15 10-06 Gouloulou à l'EP Balane à l'EP de REY-FOULAYE à l'EP de Sadielle au CES de Sirlawe CM-CRC EXTREME NORD- 58690-CW-RFQ / Travaux de construction d'un bloc de 02 salles de classe équipées Component A: Local Request for Single Stage - One 73,038.9 2018-05- 2018-05- 2018-07- 2018-10- 2018- IDA / 57180 Post Limited 99,800.00 Signed et d'un bloc de latrines à development support Quotations Envelope 7 06 15 08 17 10-06 trois compartiments à l'EP de Bihoré à l'EP de Troké dans la, commue de Tchatibali. CM-CRC EXTREME NORD- 58610-CW-RFQ / Travaux de construction d'un forage Component A: Local Request for Single Stage - One 33,727.6 2018-05- 2018-05- 2018-07- 2018-10- 2018- équipé de PMH à l'EP IDA / 57180 Post Limited 47,159.00 Signed development support Quotations Envelope 8 06 15 08 16 10-06 Saouringwa, à Kada 'a et Glonheme dans la cmne de Tchatibali CM-CRC EXTREME NORD- 58611-CW-RFQ / Travaux de construction d'un forage Component A: Local Request for Single Stage - One 35,580.8 2018-05- 2018-05- 2018-07- 2018-09- 2018- IDA / 57180 Post Limited 48,115.00 Signed équipé de PMH à Bibalé - development support Quotations Envelope 0 06 08 08 11 10-06 Gambour à Goubara à Kassilé dans la commue de Kaele CM-CRC EXTREME NORD- 58489-CW-RFQ / Travaux de réhabilitation de la mare de Garey Kaélé, Component A: Local Request for Single Stage - One 47,962.2 2018-05- 2018-05- 2018-07- 2018-09- 2018- Construction d'un forage IDA / 57180 Post Limited 55,100.00 Signed development support Quotations Envelope 8 06 08 08 11 10-06 pastoral à énergie solaire Garey Kaélé et construction d'un forage équipé de PMH à Kassilé dans la commue de Kaele CM-CRC EXTREME NORD- 58682-CW-RFQ / Travaux de Construction d'un bloc de 02 salles de classe équipées et d'un bloc Component A: Local Request for Single Stage - One 188,121.0 154,981. Complete 2018-05- 2018-05- 2018-07- 2018-09- 2018- IDA / 57180 Post Limited latrines a trois development support Quotations Envelope 0 86 d 06 08 08 27 10-06 compartiments à l'EP de Badjafe, à l'EP de Zouana, (lot 01 )à l'EP de Tchabeyel et EP de Goudjouing (lot 02) cmne de Kaele. CM-CRC EXTREME NORD- 58614-CW-RFQ / Travaux de construction d'un bloc de 02 salles de classe équipées Component A: Local Request for Single Stage - One 72,592.8 2018-05- 2018-10- 2018-07- 2018-11- 2018- d'un bloc de latrines à EP IDA / 57180 Post Limited 87,556.00 Signed development support Quotations Envelope 6 06 01 08 29 10-06 Mayel -Guinadj et un bloc de 02 salles de classe équipées à l'EP de KALAF cmne de Moutourwa. CM-CRC EXTREME NORD- 58527-CW-RFQ / Travaux de construction de 01 Component A: Local Request for Single Stage - One 54,374.2 2018-05- 2018-10- 2018-07- 2018-11- 2018- forage équipé de PMH à IDA / 57180 Post Limited 64,020.00 Signed development support Quotations Envelope 8 06 10 08 16 10-06 Ganaha, à EP de Dourloum à EP de KALAF et EP de Mayel- guinadji dans la cmne de moutourwa CM-CRC EXTREME NORD- 58849-CW-RFQ / Component A: Local Request for Single Stage - One 30,049.0 2018-05- 2018-05- 2018-07- 2018-09- 2018- construction d'un forage IDA / 57180 Post Limited 37,902.00 Signed development support Quotations Envelope 9 06 08 08 24 10-06 équipé de PMH à EM Moskota et à l'EP GOKORO CM-CRC EXTREME NORD- 58676-CW-RFQ / Travaux de Construction d'un bloc de deux salles de classe équipées et d'un bloc Component A: Local Request for Single Stage - One 150,000.0 124,030. 2018-05- 2018-06- 2018-07- 2018-08- 2018- IDA / 57180 Post Limited Signed latrines a trois development support Quotations Envelope 0 36 06 04 08 30 10-06 compartiments au CES de Mazaya à EP ZELE (Soulédé) (lot01) à EP de Doumbéré(lot02) cmne de ROUA CM-CRC EXTREME NORD- 58267-CW-RFQ / Travaux Component A: Local Request for Single Stage - One 23,886.6 2018-05- 2018-08- 2018-07- 2018-10- 2018- de construction d'un forage IDA / 57180 Post Limited 39,124.00 Signed development support Quotations Envelope 6 06 02 08 15 10-06 équipé de PMH à Koulang à Mangavé cmne de MORA CM-CRC EXTREME NORD- 58524-CW-RFQ / Travaux de construction de 01 Component A: Local Request for Single Stage - One 2018-05- 2018-08- 2018-07- 2018-10- 2018- magasin de stockage à IDA / 57180 Post Limited 69,155.00 2,421.57 Signed development support Quotations Envelope 06 02 08 22 11-05 cereale à Sera -Idoumda et un magasin de conservation d'oignon à Kourgui cmne de MORA CM-CRC EXTREME NORD- 58623-CW-RFQ / Travaux de Construction d'un forage équipé de PMH à l'EP GANCE Component A: Local Request for Single Stage - One 63,149.4 2018-05- 2018-05- 2018-07- 2018-09- 2018- IDA / 57180 Post Limited 79,756.00 Signed au CES Toltomari et development support Quotations Envelope 1 06 11 08 03 10-06 Réalisation d’un forage solaire avec borne fontaine à Kolofata cmne de Kolofata CM-CRC EXTREME NORD- 58445-CW-RFQ / Travaux de Construction d'un bloc Component A: Local Request for Single Stage - One 131,092.0 110,625. 2018-05- 2018-05- 2018-07- 2018-09- 2018- de 02 salles de classe IDA / 57180 Post Limited Signed development support Quotations Envelope 0 81 06 07 08 24 11-05 équipées s à EP Chéoulew, au CES de Makalingaï (lot01)à EP Tazang (lot02) cmne de Tokombere CM-CRC EXTREME NORD- 58679-CW-RFQ / Travaux de Construction de 01 Component A: Local Request for Single Stage - One 35,355.2 Complete 2018-05- 2018-05- 2018-07- 2018-10- 2018- IDA / 57180 Post Limited 29,122.00 forage équipé de PMH à development support Quotations Envelope 6 d 06 07 08 01 09-06 Baka-Fourwa et à Djaltar dans la cmne de Tokombere CM-CRC EXTREME NORD- 59466-CW-RFQ / TRAVAUX DE REHABILILATION DU Component A: Local Request for Single Stage - One 81,782.2 2018-05- 2018-09- 2018-07- 2018-10- 2019- IDA / 57180 Post Limited 93,480.00 Signed TRONCON HOTEL LE SAHEL- development support Quotations Envelope 2 06 14 08 15 01-04 MAYO-KALIAO (0,7 KM) cmne DE MAROUA Ier CM-CRC EXTREME NORD- 58513-CW-RFQ / TRAVAUX Component A: Local Request for Single Stage - One 74,376.6 2018-05- 2018-05- 2018-07- 2018-08- 2018- DE REHABILILATION DE LA IDA / 57180 Post Limited 90,301.00 Signed development support Quotations Envelope 7 06 14 01 24 12-28 PISTE SOUKOUDJO- BAGRISSE-FARARE (28 KM) CM-CRC EXTREME NORD- 58707-CW-RFQ / TRAVAUX DE CONSTRUCTION D'UN BLOC DE DEUX SALLES DE Component A: Local Request for Single Stage - One 45,015.4 Complete 2018-05- 2018-10- 2018-07- 2018-12- 2018- CLASSE EQUIPE ET D'UN IDA / 57180 Post Limited 52,286.00 development support Quotations Envelope 5 d 06 01 08 20 10-06 BLOC DE LATRINES A TROIS COMPARTIMENTS A L’EP KOUTOULA DANS LA CMNE DE BLANGOUA CM-CRC EXTREME NORD- 58839-CW-RFQ / TRAVAUX D’AMENAGEMENT D’UNE GARE ROUTIERE PAR LA CONSTRUCTION DE 04 Component A: Local Request for Single Stage - One 68,084.6 2018-05- 2018-10- 2018-07- 2018-12- 2018- IDA / 57180 Post Limited 84,030.00 Signed GUICHETS, 04 MAGASINS, development support Quotations Envelope 6 06 01 08 20 11-05 D’UN HANGAR D’ATTENTE ET D’UN BLOC LATRINE AVEC UN MUR D’ENCEINTE DE 130 m A BLANGOUA CM-CRC EXTREME NORD- 58514-CW-RFQ / TRAVAUX DE CONSTRUCTION D'UN Component A: Local Request for Single Stage - One 21,590.5 2018-05- 2018-05- 2018-07- 2018-10- 2018- FORAGE EQUIPE DE PMH A la IDA / 57180 Post Limited 35,201.00 Signed development support Quotations Envelope 5 06 31 08 04 09-06 gare routiere de BLANGOUA ET A L'EP DE KOUTOULA DANS LA CMNE DE BLANGOUA CM-CRC EXTREME NORD- 58434-CW-RFQ / TRAVAUX DE CONSTRUCTION TRAVAUX DE CONSTRUCTION D’UNE MINI Component A: Local Request for Single Stage - One 36,812.8 Complete 2018-05- 2018-10- 2018-07- 2018-12- 2018- IDA / 57180 Post Limited 47,598.00 AEP PASTORAL EQUIPE DE development support Quotations Envelope 0 d 06 02 08 20 10-06 DEUX ABREUVOIRS, D’UNE POMPE IMMERGEE A ENERGIE PHOTOVOLTAÏQUE A MAGALAKABIR, DANS LA CMNE DE DARAK CM-CRC EXTREME NORD- 58286-CW-RFQ / TRAVAUX DE CONSTRUCTION D'UN Component A: Local Request for Single Stage - One 75,327.5 Complete 2018-05- 2018-06- 2018-07- 2018-10- 2018- FORAGE PASTORAL A IDA / 57180 Post Limited 96,354.00 development support Quotations Envelope 8 d 06 01 08 04 10-06 ENERGIE SOLAIRE A KARENA ET A NAGA DANS LA CMNE DE DARAK CM-CRC EXTREME NORD- 58688-CW-RFQ / TRAVAUX DE CONSTRUCTION D'UN BLOC DE DEUX SALLES DE CLASSE EQUIPE ET D'UN BLOC DE LATRINES A TROIS Component A: Local Request for Single Stage - One 76,025.4 2018-05- 2018-05- 2018-07- 2018-10- 2018- IDA / 57180 Post Limited 89,200.00 Signed COMPARTIMENTS A L’EP development support Quotations Envelope 7 06 14 08 01 10-06 HILELLE (LOT01) ET CONSTRUCTION D'UN HANGAR AU MARCHE DE GOULFEY GANA (LOT02) cmne DE GOULFEY CM-CRC EXTREME NORD- 58840-CW-RFQ / TRAVAUX D’AMENAGEMENT D’UNE GARE ROUTIERE PAR LA CONSTRUCTION DE 04 Component A: Local Request for Single Stage - One 69,011.4 2018-05- 2018-09- 2018-07- 2018-12- 2018- GUICHETS, 04 MAGASINS, IDA / 57180 Post Limited 86,829.00 Signed development support Quotations Envelope 4 06 24 08 20 11-05 D’UN HANGAR D’ATTENTE, 02 BOUTIQUES ET D’UN BLOC LATRINE AVEC UN MUR D’ENCEINTE DE 90 m A GOULFEY cmne DE GOULFEY CM-CRC EXTREME NORD- 58451-CW-RFQ / TRAVAUX DE CONSTRUCTION D'UN FORAGE EQUIPES DE POMPE Component A: Local Request for Single Stage - One 40,595.7 Complete 2018-05- 2018-05- 2018-07- 2018-10- 2018- A MOTRICITE HUMAINE A IDA / 57180 Post Limited 66,094.00 development support Quotations Envelope 8 d 06 14 08 01 10-06 MOUGALAM, A TAWOULWEBE, A GARE ROUTIERE ET A L'EP HILELE COMMUNE DE GOULFEY CM-CRC EXTREME NORD- 58554-CW-RFQ / TRAVAUX DE CONSTRUCTION D'UN BLOC DE DEUX SALLES DE Component A: Local Request for Single Stage - One 46,481.6 2018-05- 2018-10- 2018-07- 2018-12- 2018- IDA / 57180 Post Limited 52,286.00 Signed CLASSE EQUIPE ET D'UN development support Quotations Envelope 5 06 28 01 20 09-29 BLOC DE LATRINES A TROIS COMPARTIMENTS A L’EP GONONI CM-CRC EXTREME NORD- 58671-CW-RFQ / TRAVAUX DE CONSTRUCTION D'UN FORAGE EQUIPE DE POMPE A Component A: Local Request for Single Stage - One 21,590.5 Complete 2018-05- 2018-05- 2018-07- 2018-10- 2018- IDA / 57180 Post Limited 51,376.00 MOTRICITE HUMAINE A development support Quotations Envelope 5 d 06 31 08 04 10-06 MAFOULSO III, A FAMARE ET A L'EP DE GONONI commune DE HILE ALIFA CM-CRC EXTREME NORD- 58631-CW-RFQ / TRAVAUX DE CONSTRUCTION TRAVAUX DE CONSTRUCTION D’UNE MINI Component A: Local Request for Single Stage - One 21,447.8 Complete 2018-05- 2018-05- 2018-07- 2018-10- 2018- IDA / 57180 Post Limited 96,018.00 AEP PASTORAL EQUIPE DE development support Quotations Envelope 3 d 06 31 08 04 10-06 DEUX ABREUVOIRS, D’UNE POMPE IMMERGEE A ENERGIE PHOTOVOLTAÏQUE A ABASSOUNI, A DOLE BADA cmne DE HILE ALIFA CM-CRC EXTREME NORD- 58426-CW-RFQ / TRAVAUX DE CONSTRUCTION D'UN BLOC DE DEUX SALLES DE Component A: Local Request for Single Stage - One 43,152.3 2018-05- 2018-05- 2018-07- 2018-09- 2018- IDA / 57180 Post Limited 52,286.00 Signed CLASSE EQUIPE ET D'UN development support Quotations Envelope 1 06 11 08 24 10-06 BLOC DE LATRINES A TROIS COMPARTIMENTS AU CES D'ADJAÏNE cmne DE KOUSSERI CM-CRC EXTREME NORD- 58417-CW-RFQ / CONSTRUCTION D'UN FORAGE EQUIPE DE POMPE A MOTRICITE HUMAINE AU CES D'ADJAINE ET D'UNE Component A: Local Request for Single Stage - One 104,068.0 82,972.8 2018-05- 2018-05- 2018-07- 2018-09- 2018- IDA / 57180 Post Limited Signed MINI AEP PASTORAL EQUIPE development support Quotations Envelope 0 2 06 11 08 24 10-06 DE DEUX ABREUVOIRS, D'UNE POMPE IMMERGEE A ENERGIE PHOTOVOLTAÏQUE A LACTA 1, ET A MASSAKI COMMUNE DE KOUSSERI CM-CRC EXTREME NORD- 58510-CW-RFQ / TRAVAUX DE CONSTRUCTION D'UN FORAGES EQUIPES DE POMPE Component A: Local Request for Single Stage - One 40,954.4 2018-05- 2018-05- 2018-07- 2018-10- 2018- IDA / 57180 Post Limited 49,640.00 Signed A MOTRICITE HUMAINE A development support Quotations Envelope 3 06 15 08 15 10-06 MASSIO-GOURGOURA, A NAGA NDIGUINI, A EP MALTAM. cmne DE MAKARI CM-CRC EXTREME NORD- 58677-CW-RFQ / TRAVAUX DE CONSTRUCTION D'UN Component A: Local Request for Single Stage - One 40,757.6 2018-05- 2018-07- 2018-09- 2018- IDA / 57180 Post Open - National 46,901.00 Signed HANGAR AVEC BLOC development support Quotations Envelope 9 06 01 10 09-29 LATRINE AU MARCHE DE BIAMO, cmne DE MAKARI CM-CRC EXTREME NORD- 58398-CW-RFQ / TRAVAUX DE CONSTRUCTION D'UN BLOC DE DEUX SALLES DE Component A: Local Request for Single Stage - One 43,675.8 2018-05- 2018-05- 2018-07- 2018-09- 2018- IDA / 57180 Post Limited 52,286.00 Signed CLASSE EQUIPE ET D'UN development support Quotations Envelope 4 06 15 08 10 10-06 BLOC DE LATRINES A TROIS COMPARTIMENTS A L'EP DE MALTAM cmne DE MAKARI CM-CRC EXTREME NORD- 58564-CW-RFQ / Travaux des MP D'INSTALLATION D'ECLAIRAGE PUBLIC (10 Component A: Local Request for Single Stage - One 2018-05- 2018-07- 2018- IDA / 57180 Post Limited 47,904.00 0.00 Canceled KITS)AVEC ENERGIE SOLAIRE development support Quotations Envelope 06 08 09-06 DE L'AXE MAIRIE DE HILE ALIFA-BRIGADE DE GENDARMERIE DE HILE Page 2 CM-CRC EXTREME NORD- 58697-CW-RFB / TRAVAUX DE CONSTRUCTION DE DEUX SALLES DE CLASSES EQUIPEES ET DE LATRINES AU CETIC DE OUZAL (LOT Component A: Local Single Stage - Two 230,463.0 2018-05- 2018-05- 2018-05- 2018-06- 2018-08- 2018-10- 2019- IDA / 57180 Post Request for Bids Open - National 0.00 Canceled N°1), CONSTRUCTION DE development support Envelope 0 01 08 06 17 30 04 02-01 DEUX SALLES DE CLASSES EQUIPEES A L'EP DE KORSAMBA ET L'EP DE KARAZAWA (LOT N°2), CONSTRUCTION D'UN BLOC MATERNEL L'EM DE MOZOGO CM-CRC EXTREME NORD- 58498-CW-RFQ / Travaux de Construction d'un bloc de 02 salles de classe Component A: Local Request for Single Stage - One 2018-05- 2018-07- 2018- IDA / 57180 Post Limited 57,225.00 0.00 Canceled équipées à EP de Gance et development support Quotations Envelope 06 08 10-06 d'un bloc de latrines à trois compartiments à L'EP TOLKOMARI cmne de Kolofata CM-CRC EXTREME NORD- 58260-CW-RFQ / TRAVAUX DE CONSTRUCTION D'UN BLOC DE DEUX (02) SALLES DE CLASSE EQUIPEES A EP Component A: Local Request for Single Stage - One 151,984.0 120,021. 2018-05- 2018-09- 2018-07- 2018-11- 2018- DE GANCE ET D'UN BLOC IDA / 57180 Post Limited Signed development support Quotations Envelope 0 73 06 24 08 29 10-06 DE LATRINES A L'EP TOLKOMARI ( LOT 01) CONSTRUCTION DE DEUX BLOC DE DEUX (02) SALLES DE CLASSE EQUIPEES CES TOLkomari CM-CRC EXTREME NORD- 111329-CW-RFQ / Travaux de Construction d'un bloc Component A: Local Request for Single Stage - One 40,309.2 2019-04- 2019-06- 2019-10- 2019- de 02 salles de classe IDA / 57180 Post Open - National 49,652.00 Signed development support Quotations Envelope 3 06 01 08 08-30 équipé et d'un bloc de latrines au CETIC de Tchévi dans la commune de Bourha CM-CRC EXTREME NORD- 111255-CW-RFQ / Travaux de Travaux de Construction Component A: Local Request for Single Stage - One 54,869.3 2019-04- 2019-06- 2019-11- 2019- d'un forage PMH au CETIC IDA / 57180 Post Open - National 65,429.00 Signed development support Quotations Envelope 8 06 01 04 08-30 de Tchévi, à Zouvou- yolde à DOUVA et à ZEU dans la commune de Bourha CM-CRC EXTREME NORD- 111381-CW-RFQ / Travaux de Construction des caniveaux en BA à Bourha Component A: Local Request for Single Stage - One 52,560.1 2019-04- 2019-06- 2019-10- 2019- IDA / 57180 Post Open - National 69,336.00 Signed (axe Hamadou -ZRA-Bello development support Quotations Envelope 0 06 01 03 08-30 Hayatou) (lot 01) et à Boukoula face commissariat (lot 02) dans la Commune de Bourha CM-CRC EXTREME NORD- 111363-CW-RFB / Travaux de Construction de deux (02) blocs de dix (10) boutiques au marché de Component A: Local Single Stage - One 258,957.0 17,073,0 2019-04- 2019-04- 2019-04- 2019-05- 2019-05- 2019-06- 2019-05- 2019-07- 2019-12- 2019- HINA cote A lot (01) et IDA / 57180 Post Request for Bids Open - National Signed development support Envelope 0 76.62 01 24 06 18 21 17 24 22 19 11-19 Travaux de Construction de deux (02) blocs de dix (10) boutique et un bloc latrines vip au marché de HINA cote B lot (02), commune de HINA. CM-CRC EXTREME NORD- 111379-CW-RFQ / Travaux d'extension du reseau Component A: Local Single Stage - One 205,088.0 171,312. 2019-04- 2019-05- 2019-04- 2019-05- 2019-07- 2019-06- 2019-07- 2019-07- 2019-10- 2019- electrique de Dargala centre- IDA / 57180 Post Request for Bids Open - National Signed development support Envelope 0 93 01 14 06 18 01 17 02 22 17 11-19 Roufirde, Roufirde- Gassayel, Gassayel- Guertogalwo dans la commune de Dargala CM-CRC EXTREME NORD- 111324-CW-RFQ / Travaux de Construction de 01 Under forage à PMH à Yoldé- Component A: Local Request for Single Stage - One 100,326.0 2019-04- 2019-06- 2019- IDA / 57180 Post Open - National 0.00 Implemen Naggué, à Tchakamadjé, development support Quotations Envelope 0 06 01 09-29 tation Yaga djibiwo, à Bakourebi (Abba wollo) Toukou mayel(Ouro-Bedem) et à MAYA ,commune de Pétté CM-CRC EXTREME NORD- 111354-CW-RFQ / Travaux de Construction d'un mini Under Component A: Local Request for Single Stage - One 2019-04- 2019-06- 2019- adduction d'eau à energie IDA / 57180 Post Open - National 52,340.00 0.00 Implemen development support Quotations Envelope 06 01 08-30 photovoltaique pour usage tation agricole a fadare dans la commune de pette CM-CRC EXTREME NORD- 111372-CW-RFQ / Travaux de Construction de 01 Component A: Local Request for Single Stage - One 22,465.4 Complete 2019-04- 2019-06- 2019-11- 2019- IDA / 57180 Post Open - National 32,707.00 forage à PMH à EP lobokri et development support Quotations Envelope 8 d 06 01 04 08-30 à dahounga gholonguini, dans la Commune de Dziguilao CM-CRC EXTREME NORD- 111360-CW-RFB / Travaux de Construction d'un bloc de deux salles de classe Component A: Local Single Stage - One 207,364.0 160,942. 2019-04- 2019-04- 2019-04- 2019-05- 2019-05- 2019-06- 2019-05- 2019-07- 2019-09- 2019- équipées et d'un bloc de IDA / 57180 Post Request for Bids Open - National Signed development support Envelope 0 65 01 09 06 18 10 17 11 22 30 11-19 latrines à trois compartiments à EP REBEDE EP LOBOKRI, (lot1) EP MBITOU et CES SOUEYE (lot2) dans la Commune de Dziguilao CM-CRC EXTREME NORD- 111319-CW-RFQ / Travaux de Construction d'un bloc Component A: Local Request for Single Stage - One 41,717.1 Complete 2019-04- 2019-06- 2019-08- 2019- de deux salles de classe IDA / 57180 Post Open - National 47,483.00 development support Quotations Envelope 8 d 06 01 27 08-30 équipées et d'un bloc latrine à trois compartiments à l'EP de Ligazang, commune de Mindif CM-CRC EXTREME NORD- 111254-CW-RFQ / Travaux de Construction et équipement d'un centre de Component A: Local Request for Single Stage - One 132,500.0 102,729. 2019-04- 2019-06- 2019-08- 2019- IDA / 57180 Post Open - National Signed santé intégré avec development support Quotations Envelope 0 06 06 01 27 09-29 incinerateur et un bloc de latrines à trois compartiments à MATFAI, dans la commune de Mindif CM-CRC EXTREME NORD- 111382-CW-RFQ / Travaux de Construction d'un forage Component A: Local Request for Single Stage - One 32,342.7 2019-04- 2019-06- 2019-12- 2019- IDA / 57180 Post Open - National 38,095.00 Signed pastoral a energie development support Quotations Envelope 0 06 01 07 08-30 photovoltaique au marché à bétail à Moulvoudaye CM-CRC EXTREME NORD- 111373-CW-RFB / Travaux d'aménagement du marché à bétail en contruisant un Component A: Local Request for Single Stage - One 42,683.0 2019-04- 2019-06- 2019-12- 2019- parc à betail une cloture un IDA / 57180 Post Open - National 56,123.00 Signed development support Quotations Envelope 7 06 01 08 09-29 quai d'embarquement et un bloc latrine a trois compartiments dans la Commune de Moulvoudaye. CM-CRC EXTREME NORD- 111380-CW-RFB / Travaux de Construction de 02 sdc et 3 latriness à EP Component A: Local Single Stage - One 234,082.0 186,401. 2019-04- 2019-05- 2019-04- 2019-05- 2019-05- 2019-06- 2019-06- 2019-07- 2019-10- 2019- KAOSSERE, à l'EP Ticheeo IDA / 57180 Post Request for Bids Open - National Signed development support Envelope 0 14 01 02 06 18 31 17 01 22 11 10-20 Kolandi, à l'EP Tchoura-Bizili L1 et de 02 SDC EPB Touloum L2 et DE 2 SDC avec BUREAUX A L’EPP SAOTSAI L3 Cune de Touloum CM-CRC EXTREME NORD- 111358-CW-RFQ / Travaux de Construction d'un forage Component A: Local Request for Single Stage - One 13,255.7 2019-04- 2019-06- 2019-12- 2019- IDA / 57180 Post Open - National 15,380.00 Signed équipé de PMH à lycee development support Quotations Envelope 0 06 01 26 07-31 bilingue dans la commue de Kaele CM-CRC EXTREME NORD- 111384-CW-RFQ / Travaux de Construction de 01 Component A: Local Request for Single Stage - One 31,562.3 2019-04- 2019-06- 2019-12- 2019- IDA / 57180 Post Open - National 50,833.00 Signed forage à PMH à Gai gai, à EP development support Quotations Envelope 7 06 01 10 08-30 Golonpoui et à EP Kankwa, dans la commune de Datcheka CM-CRC EXTREME NORD- 111395-CW-RFQ / Travaux de Construction d'un bloc de 02 salles de classe Component A: Local Request for Single Stage - One 149,671.0 121,571. 2019-04- 2019-06- 2019-12- 2019- IDA / 57180 Post Open - National Signed équipées et avec un bloc de development support Quotations Envelope 0 86 06 01 09 08-30 latrines à trois compartiments à EP Golonpoui , EP Kankrwa et EP Guidima , dans la commune de Datcheka CM-CRC EXTREME NORD- 111378-CW-RFQ / Travaux de Construction d'un bloc de deux salles de classe Component A: Local Request for Single Stage - One 175,994.0 67,097.9 2019-04- 2019-06- 2019-10- 2019- IDA / 57180 Post Open - National Signed équipées au CETIC de Vélé, development support Quotations Envelope 0 6 06 01 28 08-30 au CES de Widigue , au CES de Dabaye et au CES d'Agolla, dans la commune de Guémé CM-CRC EXTREME NORD- 111369-CW-RFQ / Travaux de Construction d'un hangar 52 places au marché de Component A: Local Request for Single Stage - One 57,109.6 2019-04- 2019-06- 2019-08- 2019- IDA / 57180 Post Open - National 67,637.00 Signed Gabaraye et Travaux de development support Quotations Envelope 1 06 01 27 08-30 Construction d'un bloc de latrines au marché de Gabaraye, commune de Guémé CM-CRC EXTREME NORD- 111362-CW-RFQ / Travaux de Construction d'un centre Component A: Local Request for Single Stage - One 127,436.0 106,966. 2019-04- 2019-06- 2019-10- 2019- IDA / 57180 Post Open - National Signed de santé intégré équipé et development support Quotations Envelope 0 95 06 01 08 09-29 un bloc de latrines au CSI à Nguéring, commune de Gueré CM-CRC EXTREME NORD- 111396-CW-RFQ / Component A: Local Request for Single Stage - One 27,215.6 2019-04- 2019-06- 2019-10- 2019- Construction d'un bloc de IDA / 57180 Post Open - National 32,708.00 Signed development support Quotations Envelope 4 06 01 09 08-30 05 boutiques au marché d'Ardaf Commune de Guere CM-CRC EXTREME NORD- 111388-CW-RFQ / Travaux de Construction d'un forage Component A: Local Request for Single Stage - One 12,359.6 2019-04- 2019-06- 2020-01- 2019- IDA / 57180 Post Open - National 15,311.00 Signed équipé de PMH à l'EP de development support Quotations Envelope 6 06 01 23 07-31 DAMA Djougong, commune de Kai kai CM-CRC EXTREME NORD- 111390-CW-RFQ / CONSTRUCTION DEUX Component A: Local Request for Single Stage - One 40,484.4 Complete 2019-04- 2019-06- 2019-08- 2019- IDA / 57180 Post Open - National 69,678.00 BLOCS DE CINQ (05) development support Quotations Envelope 0 d 06 01 22 08-30 BOUTIQUES AU MARCHÉ DE KALFOU, DANS LA COMMUNE DE KALFOU CM-CRC EXTREME NORD- 111371-CW-RFQ / Travaux de Construction d'un forage équipé de pompe à Component A: Local Request for Single Stage - One 57,350.2 2019-04- 2019-06- 2019-11- 2019- motricité humaine à Gandou IDA / 57180 Post Open - National 67,386.00 Signed development support Quotations Envelope 9 06 01 22 08-30 Golopo, au CES de Zaria, à Djada, réhabilitation d'un forage PMH à Delta Guibéré et Mandara, dans la commune de Kalfou CM-CRC EXTREME NORD- 111398-CW-RFQ / Under Component A: Local Request for Single Stage - One 2019-04- 2019-06- 2019- Équipement en matériel IDA / 57180 Post Open - National 16,804.00 0.00 Implemen development support Quotations Envelope 06 01 07-31 médicaux au CSI de Takreo tation yoldeo Commune Kar Hay CM-CRC EXTREME NORD- 111260-CW-RFQ / Electrification du nouveau Component A: Local Request for Single Stage - One 152,907.0 134,395. 2019-04- 2019-06- 2019-12- 2019- marché de Guirvidig (lot 01) IDA / 57180 Post Open - National Signed development support Quotations Envelope 0 99 06 01 06 09-29 et de la localité de Yangah (lot 02) , dans la commune de Maga CM-CRC EXTREME NORD- 111368-CW-RFQ / Travaux de Construction d'un forage Component A: Local Request for Single Stage - One 13,773.4 2019-04- 2019-06- 2019-12- 2019- IDA / 57180 Post Open - National 15,759.00 Signed équipé de pompe à development support Quotations Envelope 0 06 01 06 07-31 motricité humaine à Bindiriel Danghou, commue de Tchatibali CM-CRC EXTREME NORD- 111259-CW-RFB / Travaux de Construction d'un bloc de 02 salles de classe équipées et d'un bloc de Component A: Local Single Stage - One 244,743.0 78,116.8 2019-04- 2019-05- 2019-04- 2019-05- 2019-06- 2019-06- 2019-06- 2019-07- 2019-10- 2019- latrines à IDA / 57180 Post Request for Bids Open - National Signed development support Envelope 0 5 01 02 06 18 13 17 14 22 23 11-19 troiscompartiments au CES Kamargui, à EP Goulourgou (lot 02), EP Bigi, EP de Djenreng (lot 02)et EP Waimou (lot 03) COMMUNE DE WINA CM-CRC EXTREME NORD- 111383-CW-RFQ / Travaux de Construction D’UN BLOC DE DEUX SALLES DE CLASSE Component A: Local Request for Single Stage - One 32,203.2 2019-04- 2019-06- 2019-12- 2019- IDA / 57180 Post Open - National 96,762.00 Signed AVEC BUREAUX EQUIPES au development support Quotations Envelope 2 06 01 03 09-29 CES de DJOGOIDI et au lycee de Vounaloum Commune de yagoua CM-CRC EXTREME NORD- 111365-CW-RFQ / Travaux de Construction d'un hangar Component A: Local Request for Single Stage - One 56,945.7 2019-04- 2019-06- 2019-10- 2019- IDA / 57180 Post Open - National 76,074.00 Signed de 28 places et d'une development support Quotations Envelope 2 06 01 08 09-29 boucherie au marché de Velé, dans la commune de Guémé CM-CRC EXTREME NORD- 111374-CW-RFQ / Travaux Under de Construction de 01 Component A: Local Request for Single Stage - One 2019-04- 2019-06- 2019- IDA / 57180 Post Open - National 38,095.00 0.00 Implemen forage à énergie solaire à development support Quotations Envelope 06 01 08-30 tation CSI de Bosgoye, dans la commune de Wina CM-CRC EXTREME NORD- 111389-CW-RFQ / Travaux de Construction de 2 salles de classe et de latrines à l'EP de BIJE ( lot 01) , Component A: Local Request for Single Stage - One 80,535.3 2019-04- 2019-06- 2019-05- 2019- Construction de 2 salles de IDA / 57180 Post Open - National 96,542.00 Signed development support Quotations Envelope 6 06 01 27 08-30 classes à EPPB de TOKOMBERE et equipement en table bancs et bureaux au CES de makilingai (lot 02) dans la commune de Tokombere CM-CRC EXTREME NORD- 111392-CW-RFQ / Travaux de Construction d'un bloc Component A: Local Request for Single Stage - One 55,757.8 Complete 2019-04- 2019-06- 2019-05- 2019- de deux salle de classe IDA / 57180 Post Open - National 67,299.00 development support Quotations Envelope 5 d 06 01 25 08-30 équipés et d'un bloc latrines à Magala Djamene dans la commune de Darak CM-CRC EXTREME NORD- 111385-CW-RFQ / Travaux Component A: Local Request for Single Stage - One 10,462.3 Complete 2019-04- 2019-06- 2019-05- 2019- de Construction de 01 IDA / 57180 Post Open - National 19,048.00 development support Quotations Envelope 9 d 06 01 25 08-30 forage PMH à Magala Djamene, dans la commune de Darak CM-CRC EXTREME NORD- 111325-CW-RFB / Travaux de Construction d'un bloc de deux salles de classe Component A: Local Single Stage - One 226,885.0 94,907.5 2019-04- 2019-03- 2019-04- 2019-05- 2019-04- 2019-06- 2019-04- 2019-07- 2019-07- 2019- équipées et d'un bloc de IDA / 57180 Post Request for Bids Open - National Signed development support Envelope 0 3 01 28 06 18 24 17 25 22 10 11-19 latrines à trois compartiments à EP GADAFAI, au Lycée de Fotokol à EP Magadji et à EP de GUEGUERI, commune de Fotokol CM-CRC EXTREME NORD- 111261-CW-RFQ / Travaux Component A: Local Request for Single Stage - One 31,367.2 Complete 2019-04- 2019-06- 2019-07- 2019- IDA / 57180 Post Open - National 34,286.00 de Construction d'un development support Quotations Envelope 5 d 06 01 02 08-30 magasin de stockage à Goulfey CM-CRC EXTREME NORD- 111367-CW-RFQ / Travaux Component A: Local Request for Single Stage - One 30,637.2 2019-04- 2019-06- 2019-05- 2019- de Construction d'une mini IDA / 57180 Post Open - National 48,024.00 Signed development support Quotations Envelope 0 06 01 25 08-30 AEP pastorale à énergie solaire à fadja commune de Hilé Alifa CM-CRC EXTREME NORD- 111320-CW-RFQ / Travaux de Construction de 01 Component A: Local Request for Single Stage - One 36,050.5 Complete 2019-04- 2019-06- 2019-05- 2019- forage PMH à Michiska IDA / 57180 Post Open - National 49,510.00 development support Quotations Envelope 8 d 06 01 25 08-30 Mousgoum, OUNANGARE et NGADA 1, dans la commune de Logone Birni CM-CRC EXTREME NORD- 111327-CW-RFB / Travaux Component A: Local Request for Single Stage - One 40,199.6 2019-04- 2019-06- 2019-09- 2019- de Construction d'un IDA / 57180 Post Open - National 48,020.00 Signed development support Quotations Envelope 3 06 01 11 08-30 magasin de stockage à zigague, dans la commune de Waza CM-CRC EXTREME NORD- 111322-CW-RFQ / Travaux Component A: Local Request for Single Stage - One 38,848.3 Complete 2019-04- 2019-06- 2019-07- 2019- de Construction d'un forage IDA / 57180 Post Open - National 50,855.00 development support Quotations Envelope 8 d 06 01 15 08-30 PMH à malia, NDIGUINA et MADA dans la commune de Waza Page 3 CM-CRC EXTREME NORD- 111377-CW-RFQ / Travaux d’extension du réseau électrique en moyenne Component A: Local Request for Single Stage - One 120,000.0 108,328. 2020-10- 2020-12- 2021-01- 2021- tension (MT) et basse IDA / 57180 Post Open - National Signed development support Quotations Envelope 0 90 05 16 08 12-31 tension (BT) triphasé et un transformateur H61 160 KVA dans les quartiers de Wourndé II et III, commune de Maroua 2 CM-CRC EXTREME NORD- 111376-CW-RFQ / Travaux d’electrification en moyenne Component A: Local Request for Single Stage - One 130,938.0 116,385. 2019-04- 2019-06- 2019-09- 2019- tension (MT) et basse IDA / 57180 Post Open - National Signed development support Quotations Envelope 0 17 06 01 02 09-29 tension (BT) monophasé de l'axe Barzao- barza foulbe- Barza-Guiziga, commune de Gazawa CM-CRC EXTREME NORD- 111355-CW-RFQ / Fourniture et installation de 07 lampadaires solaires Component A: Local Request for Single Stage - One 15,778.3 2019-04- 2019-06- 2019-08- 2019- composés de panneaux IDA / 57180 Post Open - National 19,048.00 Signed development support Quotations Envelope 5 06 01 27 07-31 solaires monocristallins et de batteries de type gel dans le centre urbain de vele commune DE GUEME CM-CRC EXTREME NORD- 111331-CW-RFQ / Travaux de Construction d'un forage Component A: Local Request for Single Stage - One 2019-04- 2019-06- 2019- IDA / 57180 Post Open - National 15,238.00 0.00 Canceled équipé de pompe à development support Quotations Envelope 06 01 07-31 motricité humaine a Djafgadjie, commue de yagoua CM-CRC EXTREME NORD- 111386-CW-RFQ / Travaux de Construction d'un CSI Component A: Local Request for Single Stage - One 152,381.0 2019-04- 2019-06- 2019- équipé avec case d'astreinte, IDA / 57180 Post Open - National 0.00 Canceled development support Quotations Envelope 0 06 01 09-29 un incinérateur et un bloc de latrines au CSI Djiddeo Garre, dans la commune de Maroua 3 CM-CRC EXTREME NORD- 111433-CW-RFQ / Component A: Local Request for Single Stage - One 2019-09- 2019-11- 2020- IDA / 57180 Post Open - National 10,000.00 0.00 Canceled réalisation d'un parc à bétail development support Quotations Envelope 07 02 04-30 dans la commune de Wina (GP) CM-CRC EXTREME NORD- 111394-CW-RFQ / Travaux de Construction d’un forage Component A: Local Request for Single Stage - One 2019-04- 2019-06- 2019- IDA / 57180 Post Open - National 29,376.00 0.00 Canceled à énergie solaire avec development support Quotations Envelope 06 01 08-30 château au centre de santé de Djiddéo, dans la commune de Maroua 3 CM-CRC EXTREME NORD- 111387-CW-RFQ / Travaux Component A: Local Request for Single Stage - One 2019-04- 2019-06- 2019- de construction d'un forage IDA / 57180 Post Open - National 15,238.00 0.00 Canceled development support Quotations Envelope 06 01 07-31 pmh à l'EP Dolgaye Commune Kar Hay CM-CRC EXTREME NORD- 196682-CW-RFQ / Travaux de Construction d'un CSI Component A: Local Request for Single Stage - One 120,952.0 97,049.8 2020-11- 2021-01- 2021-01- 2021- équipé avec un incinérateur IDA / 57180 Post Open - National Signed development support Quotations Envelope 0 5 04 15 26 05-15 et un bloc de latrines au CSI Djiddeo Garre, dans la commune de Maroua 3 CM-CRC EXTREME NORD- 196726-CW-RFQ / Travaux de Construction et Component A: Local Request for Single Stage - One 36,267.8 2020-11- 2021-01- 2021-01- 2021- équipement des blocs des IDA / 57180 Post Open - National 45,714.00 Signed development support Quotations Envelope 2 04 15 26 04-15 salles de classes et d'un bloc de latrines au CES de GUINADJI Commune de Maroua III CM-CRC EXTREME NORD- 196667-CW-RFQ / Travaux Under Component A: Local Request for Single Stage - One 10,958.0 2020-11- 2021-01- 2021-01- 2021- de Construction d’un forage IDA / 57180 Post Open - National 15,238.00 Implemen development support Quotations Envelope 5 04 15 26 03-16 PMH au centre de santé de tation Djiddéo Commune de Maroua III CM-CRC EXTREME NORD- 196678-CW-RFQ / REALISATION D’UN FORAGE EQUIPE DE POMPE A MOTRICITE HUMAINE A Under Component A: Local Request for Single Stage - One 2020-11- 2021-01- 2021- GUIVEL, QUARTIER MERI IDA / 57180 Post Open - National 57,244.00 0.00 Implemen development support Quotations Envelope 04 15 04-15 CENTRE ET KILWO-VALTA tation ET L’ACHEVEMENT DE LA CONSTRUCTION DES FORAGES DE GADJAWAI ET NGUISSAR DANS LA COMMUNE DE MERI CM-CRC EXTREME NORD- 196722-CW-RFQ / Travaux de CONSTRUCTION D’UN Pending FORAGE PASTORAL A Component A: Local Request for Single Stage - One 2020-11- 2021-01- 2021- IDA / 57180 Post Open - National 41,546.00 0.00 Implemen ENERGIE SOLAIRE EQUIPE development support Quotations Envelope 04 15 04-15 tation D’UN château ET DE (02) ABREUVOIRS DANS LA LOCALITE DE DJONGDONG, COMMUNE DE WINA CM-CRC EXTREME NORD- 196718-CW-RFQ / Travaux Pending de Construction de 01 Component A: Local Request for Single Stage - One 2020-10- 2020-12- 2021- IDA / 57180 Post Open - National 38,095.00 0.00 Implemen forage à énergie solaire à development support Quotations Envelope 05 16 03-16 tation CSI de Bosgoye, dans la commune de Wina CM-CRC EXTREME NORD- 196724-CW-RFQ / Travaux de CONSTRUCTION D’UN FORAGE PASTORAL A Component A: Local Request for Single Stage - One 36,344.1 2020-11- 2021-01- 2021-01- 2021- IDA / 57180 Post Open - National 40,000.00 Signed ENERGIE SOLAIRE EQUIPE development support Quotations Envelope 7 04 15 26 04-15 D’UN château ET DE (02) ABREUVOIRS DANS LA LOCALITE DE MIZILING WAILA MAYO, COMMUNE DE GAZAWA CM-CRC EXTREME NORD- 196687-CW-RFQ / Travaux Component A: Local Request for Single Stage - One 14,150.1 2020-11- 2021-01- 2021-01- 2021- de Construction d'un forage IDA / 57180 Post Open - National 15,631.00 Signed development support Quotations Envelope 2 04 15 08 03-16 équipé de PMH de Yonkolel Commune de Dargala. CM-CRC EXTREME NORD- 196720-CW-RFQ / Travaux de Construction d'un forage Under équipé de PMH à lalepaki et Component A: Local Request for Single Stage - One 2020-11- 2021-01- 2021- IDA / 57180 Post Open - National 17,143.00 0.00 Implemen Acquisition d’une caisse à development support Quotations Envelope 04 15 03-16 tation outils pour l’entretien des forages dans la commune de Commune de Touloum CM-CRC EXTREME NORD- 196723-CW-RFQ / TRAVAUX DE CONSTRUCT D’UN BLOC DE 2 SALLES DE CLASSE EQUIPEES ET D’UN Under Component A: Local Request for Single Stage - One 2020-11- 2021-03- 2021- BLOC DE LATRINES À L'EP IDA / 57180 Post Open - National 87,964.00 0.00 Implemen development support Quotations Envelope 04 16 06-14 TCHOURA-BIZILI ET tation CONSTRUCTION D'UN BLOC DE 02 SALLES DE CLASSE ÉQUIPÉES À EP BILINGUE DE TOULOUM COMMUNE DE TOULOUM CM-CRC EXTREME NORD- 196721-CW-RFQ / TRAVAUX DE CONSTRUCTION D’UN BLOC Pending Component A: Local Request for Single Stage - One 2020-11- 2021-01- 2021- DE DEUX SALLES DE CLASSE IDA / 57180 Post Open - National 45,113.00 0.00 Implemen development support Quotations Envelope 04 15 04-15 EQUIPEES ET D’UN BLOC DE tation LATRINES À TROIS COMPARTIMENTS à l'EP de ZANYAO Commune de YAGOUA CM-CRC EXTREME NORD- 196681-CW-RFQ / Travaux de Construction d’un forage équipé de pompe à Component A: Local Request for Single Stage - One 71,202.8 2020-11- 2021-01- 2021-01- 2021- IDA / 57180 Post Open - National 80,952.00 Signed motricité humaine à Dinao, development support Quotations Envelope 6 04 15 08 04-15 Louggol palé, Kodadjiho, Hamadalao et Golombeswé Commune KALFOU CM-CRC EXTREME NORD- 196688-CW-RFQ / Travaux Pending de Construction d'un forage Component A: Local Request for Single Stage - One 2020-11- 2021-01- 2021- IDA / 57180 Post Open - National 32,381.00 0.00 Implemen équipé de PMH à douang et development support Quotations Envelope 04 15 03-16 tation dingue-Gabaraye Commune de Gueme CM-CRC EXTREME NORD- 196677-CW-RFQ / Réalisation d’un (01) forage Component A: Local Request for Single Stage - One 41,275.2 2020-11- 2021-01- 2021-01- 2021- pastoral photovoltaïque et IDA / 57180 Post Open - National 47,200.00 Signed development support Quotations Envelope 8 04 15 08 04-15 de deux abreuvoirs au lieu- dit KOLOFATA GUIDI dans la commune de KOLOFATA CM-CRC EXTREME NORD- 196719-CW-RFQ / Travaux Under Component A: Local Request for Single Stage - One 2020-11- 2021-01- 2021- de construction d'un forage IDA / 57180 Post Open - National 13,742.00 0.00 Implemen development support Quotations Envelope 04 15 04-15 équipé de PMH à Koulang tation Commune de MORA CM-CRC EXTREME NORD- 196685-CW-RFQ / Travaux de Construction d'un forage Component A: Local Request for Single Stage - One 14,195.0 2020-10- 2020-12- 2021-01- 2021- IDA / 57180 Post Open - National 16,190.00 Signed équipé de pompe à development support Quotations Envelope 1 05 16 08 02-14 motricité humaine à Guermé Kalfou Commune de Kalfou CM-CRC EXTREME NORD- 196671-CW-RFQ / Travaux de Construction d'un bloc de deux salle de classe Under équipées à l'EPB DE MADA Component A: Local Request for Single Stage - One 2020-11- 2021-01- 2021- IDA / 57180 Post Open - National 95,238.00 0.00 Implemen KOLKOCH ET A LEP development support Quotations Envelope 04 15 05-15 tation MAMBEZA et Construction d'un bloc de latrines à l'EPB DE MADA KOLKOCH ET Commune de Tokombere CM-CRC EXTREME NORD- 196727-CW-RFQ / TRAVAUX D’AMENAGEMENT D’UNE GARE ROUTIERE PAR Pending LA CONSTRUCTION DE 04 Component A: Local Request for Single Stage - One 2020-11- 2021-01- 2021- IDA / 57180 Post Open - National 95,238.00 0.00 Implemen GUICHETS, 04 MAGASINS, development support Quotations Envelope 04 15 05-15 tation D’UN HANGAR D’ATTENTE ET D’UN BLOC LATRINE AVEC UN MUR D’ENCEINTE COMMUNE DE YAGOUA CM-CRC EXTREME NORD- 204463-CW-RFQ / travaux de construction d’un bloc Component A: Local Request for Single Stage - One 48,124.0 2020-12- 2021-02- 2021-01- 2021- de deux salles de classe IDA / 62240 Post Open - National 57,142.86 Signed development support Quotations Envelope 6 01 02 15 06-02 équipées avec bloc latrines à à l’EP d’Afadé Groupe 2 Commune Makary CM-CRC EXTREME NORD- Component C: 196964-CW-RFQ / Coordination, management, Request for Single Stage - One 2020-11- 2020-12- 2021- Aménagement d'un parking IDA / 62240 Post Limited 5,000.00 0.00 Canceled monitoring and evaluation Quotations Envelope 04 30 01-29 additionnel et des bureaux and communication de la crc-EN à maroua CM-CRC EXTREME NORD- 196679-CW-RFQ / Travaux de Construction d'un dalot mixte (BA et Beton Component A: Local Request for Single Stage - One 2020-11- 2021-01- 2021- IDA / 57180 Post Open - National 62,857.00 0.00 Canceled cyclopeen) de 2x2,5x6 m de development support Quotations Envelope 04 15 05-15 franchissement de 5 ml et 22 m de portée sur le mayo- Guili Commune de Bourha. CM-CRC EXTREME NORD- 196672-CW-RFQ / REALISATION D’UN FORAGE Component A: Local Request for Single Stage - One 2020-11- 2021-01- 2021- IDA / 57180 Post Open - National 15,238.00 0.00 Canceled EQUIPE DE POMPE A development support Quotations Envelope 04 15 03-16 MOTRICITE HUMAINE A Dolgaye Commune Kar Hay CM-CRC EXTREME NORD- 196725-CW-RFQ / Travaux de Construction d'un bloc Component A: Local Request for Single Stage - One 2020-11- 2021-01- 2021- IDA / 57180 Post Open - National 43,810.00 0.00 Canceled de deux salles de classe development support Quotations Envelope 04 15 04-15 équipées au lycee de Goundaye Commune de Dziguilao. CM-CRC EXTREME NORD- 196686-CW-RFQ / Travaux de Construction d'un bloc Component A: Local Request for Single Stage - One 2020-11- 2021-01- 2021- de 02 salles de classe IDA / 57180 Post Open - National 48,949.00 0.00 Canceled development support Quotations Envelope 04 15 04-15 équipées et d'un bloc de latrines à trois compartiments a EP Waimou COMMUNE DE WINA CM-CRC EXTREME NORD- 222521-CW-RFQ / travaux de construct et équipement Pending Component A: Local Request for Single Stage - One 152,380.0 2021-04- 2021-06- 2021- d’une salle d’hospitalisation IDA / 62240 Post Open - National 0.00 Implemen development support Quotations Envelope 0 13 08 10-06 et d'un bloc opératoire au tation CMA de Logone birni Commune de Logone birni CM-CRC EXTREME NORD- 222525-CW-RFQ / travaux de construct d’1 bloc maternel et latrines à EM Pending Component A: Local Request for Single Stage - One 148,470.0 2021-04- 2021-06- 2021- Logone birni (lot 01) et IDA / 62240 Post Open - National 0.00 Implemen development support Quotations Envelope 0 13 08 10-06 Réhabilitation de 6 salles de tation classe avec bureau attenant et équipement a EP Logone birni GPE 1 A (lot 02) Commune de Logone birni CM-CRC EXTREME NORD- 222842-CW-RFQ / Travaux de construct et équipement Pending Component A: Local Request for Single Stage - One 152,380.0 2021-04- 2021-06- 2021- d’une salle d’hospitalisation IDA / 62240 Post Open - National 0.00 Implemen development support Quotations Envelope 0 13 08 10-06 et d'un bloc opératoire au tation CMA de Fotokol Commune de Fotokol (A2011B1) CM-CRC EXTREME NORD- 222748-CW-RFQ / Travaux de construct d’un forage équipé de pompe à Pending Component A: Local Request for Single Stage - One 2021-04- 2021-06- 2021- motricité humaine à Mada IDA / 62240 Post Open - National 73,180.00 0.00 Implemen development support Quotations Envelope 13 08 10-06 (Ngroh), à Goura 2 tation (Mosquée), à Labado, à Chou et réhabilitation d’un forage à Mada 1 (quartier Sara) Commune de Makary CM-CRC EXTREME NORD- 222522-CW-RFQ / Travaux Pending Component A: Local Request for Single Stage - One 2021-04- 2021-06- 2021- de construct d’une mini AEP IDA / 62240 Post Open - National 38,020.00 0.00 Implemen development support Quotations Envelope 13 08 10-06 au camp des réfugiés tation d’Afadé Commune de Makary CM-CRC EXTREME NORD- 222828-CW-RFQ / Travaux Pending Component A: Local Request for Single Stage - One 2021-04- 2021-06- 2021- de construct d’un forage IDA / 62240 Post Open - National 21,915.00 0.00 Implemen development support Quotations Envelope 13 08 09-06 équipé de PMH à Tagawa tation Commune de Waza CM-CRC EXTREME NORD- 222782-CW-RFQ / Travaux de réalisation d’un forage productif équipé de pompe à motricité humaine dans Pending Component A: Local Request for Single Stage - One 2021-04- 2021-06- 2021- les localités de : YEME, IDA / 62240 Post Open - National 96,820.00 0.00 Implemen development support Quotations Envelope 13 08 10-06 DANDAYA, KOLDIMA, tation MADJINA et MEHE EMMA (Camp refugié) dans la Commune de Mora, Département du Mayo Sava. CM-CRC EXTREME NORD- 222778-CW-RFQ / Travaux de construct d’1 logement d'astreint et d'un mur de Pending cloture à l’EP IGAWA MEME Component A: Local Request for Single Stage - One 198,220.0 2021-04- 2021-06- 2021- IDA / 62240 Post Open - National 0.00 Implemen (lot1) et de construct de 4 development support Quotations Envelope 0 13 08 10-06 tation salles de classe équipées avec 1 bureau attenant et de latrines à l’EP de KOTCHEREHE (lot 02) Commune de Mora CM-CRC EXTREME NORD- 222959-CW-RFQ / TRAVAUX DE construct D’UN BLOC DE DEUX SALLES DE CLASSE EQUIPEES AVEC Pending BUREAU ET D’UN BLOC Component A: Local Request for Single Stage - One 189,335.0 2021-04- 2021-06- 2021- IDA / 62240 Post Open - National 0.00 Implemen LATRINE A TROIS development support Quotations Envelope 0 13 08 06-20 tation COMPARTIMENTS A L’EPB DE KOSSEHONE, L'EP WANDAI (lot 01) ET L'EP NDROCK (lot 02) DANS LA COMMUNE DE MOKOLO, DEPARTEMENT DU MAYO-TSANAGA. CM-CRC EXTREME NORD- 222785-CW-RFQ / Travaux de construct de 01 forage à Pending Component A: Local Request for Single Stage - One 2021-04- 2021-06- 2021- Zamai, à Ldagodja-Tourou, IDA / 62240 Post Open - National 67,115.00 0.00 Implemen development support Quotations Envelope 13 08 10-06 à Ngolkodjala-Kosséhone et tation à Wandaï-djamboutou Commune de Mokolo Page 4 CM-CRC EXTREME NORD- 222977-CW-RFQ / TRAVAUX DE construct ET Pending EQUIPEMENT DU CENTRE DE Component A: Local Request for Single Stage - One 152,380.0 2021-04- 2021-06- 2021- IDA / 62240 Post Open - National 0.00 Implemen SANTE INTEGRE A development support Quotations Envelope 0 13 08 06-20 tation KOSSEHONE DANS LA COMMUNE DE MOKOLO, DEPARTEMENT DU MAYO- TSANAGA.(A2011B1) CM-CRC EXTREME NORD- 222983-CW-RFQ / Travaux Pending de Construction de 01 Component A: Local Request for Single Stage - One 2021-04- 2021-06- 2021- IDA / 57180 Post Open - National 34,286.00 0.00 Implemen forage à énergie solaire au development support Quotations Envelope 13 08 09-06 tation CSI de hile haoussa, dans la commune de kousseri (A2031C1) CM-CRC EXTREME NORD- 228212-CW-RFQ / travaux de construction d'un bloc Pending Component A: Local Request for Single Stage - One 2021-05- 2021-07- 2021- latrines a troix IDA / 57180 Post Open - National 9,000.00 0.00 Implemen development support Quotations Envelope 10 05 09-03 compartiement et tation construction d'un incinerateur au CSI de hile haoussa dans la Commune de kousseri CM-CRC EXTREME NORD- 237615-CW-RFQ / construct de 6 SDC équipées avec bureau et Request for Pending latrines à EP de BIAMO (lot Component A: Local Request for Single Stage - One 285,350.0 2021-06- 2021-08- 2022- IDA / 62240 Post Open - National Quotations (Non 0.00 Implemen 01) construct de 2 SDC avec development support Quotations Envelope 0 06 01 01-28 Bank-SPD) tation bureau a EP GRP 2 de BODO (lot 02) construct de 2 SDC avec bureau et latrines a EP de DJAMOUS (lot 03) Commune de Makary CM-CRC EXTREME NORD- 237617-CW-RFQ / travaux de construct de 4 salles de classe équipées avec 2 Request for Pending Component A: Local Request for Single Stage - One 253,980.0 2021-06- 2021-08- 2022- bureau à EP Fotokol (lot 01) IDA / 62240 Post Open - National Quotations (Non 0.00 Implemen development support Quotations Envelope 0 06 01 01-28 et construct de 4 salles de Bank-SPD) tation classe équipées avec 2 bureau et de 3 blocs de latrines à EP Fotokol (lot 02) Commune de Fotokol GOODS Activity Reference No. Estimated Actual Draft Pre- Draft Bidding Specific Proposal Bid Evaluation Loan / Credit Market Procurement Prequalificati Process Prequalification Bidding Documents Contract / Description Component Review Type Method Amount Amount qualification Document / Procurement Notice Submission / Report and Signed Contract No. Approach Process on (Y/N) Status Evaluation Report as Issued Completion (US$) (US$) Documents Justification / Invitation Opening / Minutes Recommendation Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned for Award Actual Planned Actual Planned Actual CM-CRC EXTREME NORD- 7991-GO-RFQ / Acquisition Component C: des fournitures de bureaux Coordination, management, Request for Single Stage - One 2017-03- 2017-05- 2017-05- 2017-06- 2017-05- IDA / 57180 Post Limited 10,000.00 8,556.39 Signed du matériels d'entretien et monitoring and evaluation Quotations Envelope 10 26 05 22 19 des fournitures diverses à la and communication CRC, Région de l'Extrême- Nord CM-CRC EXTREME NORD- 8000-GO-RFQ / Acquisition des consomables Component C: Informatiques (Encres, clés Coordination, management, Request for Single Stage - One 2017-03- 2017-05- 2017-05- 2017-07- 2017-05- IDA / 57180 Post Limited 10,000.00 5,074.65 Signed internet, CD, 2 disques durs monitoring and evaluation Quotations Envelope 10 26 05 22 19 externes Tera, 9 clés USB, and communication antivirus) à la CRC, Région de l'Extrême-Nord CM-CRC EXTREME NORD- 8001-GO-RFQ / Acquisition des fournitures pour Component C: véhicules ((5pneusX3véh), 3 Coordination, management, Request for Single Stage - One 2017-03- 2017-05- 2017-05- boîtes à pharmacie, 3 IDA / 57180 Post Limited 10,000.00 0.00 Canceled monitoring and evaluation Quotations Envelope 10 05 19 extincteurs,3 pelles, 6 and communication paires de gants, 3machettes, 3manteaux...) à la CRC, Région de l'Extrême- Nord CM-CRC EXTREME NORD- Component C: 8003-GO-RFQ / acquisition, Coordination, management, Request for Single Stage - One 2017-03- 2017-12- 2017-05- 2017-12- 2017-07- 2018-01- IDA / 57180 Post Limited 9,000.00 4,880.26 Completed aménagement et monitoring and evaluation Quotations Envelope 10 04 05 29 04 19 équipement de 2 conteneurs and communication de 40 pieds Component C: CM-CRC EXTREME NORD- Coordination, management, Request for Single Stage - One 2017-03- 2017-10- 2017-05- 2017-12- 2017-06- 2018-01- 8006-GO-RFQ / aquisition IDA / 57180 Post Limited 6,000.00 5,492.69 Completed monitoring and evaluation Quotations Envelope 10 03 05 22 04 15 et installation de 10 splits and communication CM-CRC EXTREME NORD- 8008-GO-RFQ / acquisition Component C: du kit à outils du Coordination, management, Request for Single Stage - One 2017-03- 2017-05- 2017-06- CCI(scléromètre, lazermètre, IDA / 57180 Post Limited 1,500.00 0.00 Canceled monitoring and evaluation Quotations Envelope 10 05 04 odomètre, pi à coulisse and communication électronique, EPI, Gilets de sauvetage CM-CRC EXTREME NORD- 8009-GO-RFQ / fourniture des services de maintenance Component C: électrique, climatiseurs, Coordination, management, Request for Single Stage - One 2017-03- 2017-05- 2017-05- 2017-07- 2018-05- IDA / 57180 Post Limited 4,800.00 2,176.75 Signed groupe électrogène, monitoring and evaluation Quotations Envelope 10 26 05 24 05 plolmberie et menuiserie à and communication la CRC, Région de l'Extrême- Nord CM-CRC EXTREME NORD- 38389-GO-RFQ / Equipement en table bancs, tables et chaise pour Component A: Local Request for Single Stage - One 2017-12- 2017-12- 2018-01- 2018-04- 2018-04- Enseignants et armoires au IDA / 57180 Post Limited 16,265.00 12,882.93 Signed development support Quotations Envelope 02 19 27 09 27 CETIC de Mogodé, à l'EP de SIR, à l'EPB de Rhoumsiki et à l'EP de Tchanawa dans la commune de Mogode CM-CRC EXTREME NORD- 58709-GO-RFQ / Acquisition des consomables Informatiques Component A: Local Request for Single Stage - One 2017-10- 2017-10- 2017-12- 2017-12- 2017-12- IDA / 57180 Post Limited 2,600.00 1,816.76 Signed (Encres, clés internet, CD, 2 development support Quotations Envelope 08 03 03 07 17 disques durs externes Tera, 9 clés USB, antivirus) à la CRC, Région de l'Extrême- Nord VAGUE 2 CM-CRC EXTREME NORD- 58529-GO-RFP / Fourniture d' une pirogue à moteur 30CV type E40GMHL (avec coque en fibre de verre) et Component A: Local Request for Single Stage - One 2018-05- 2018-06- 2018-07- 2018-10- 2018-08- 2018-12- IDA / 57180 Post Limited 26,974.00 25,881.80 Completed des équipements annexes: development support Quotations Envelope 06 13 01 23 30 21 portes tout tricycle tractable, pagaies, gilets de sauvetage, panneaux de labelisation) dans la cmne de KAIKAI CM-CRC EXTREME NORD- 111400-GO-RFQ / Fourniture en mobilier et Component A: Local Request for Single Stage - One 2019-04- 2019-06- 2019-08- 2019-07- petit materiel sanitaire de IDA / 57180 Post Open - National 49,494.00 38,928.38 Signed development support Quotations Envelope 06 01 27 31 CSI de Mindif, de Modjombodi, de Maoudine et de Mogom dans la commune de Mindif. CM-CRC EXTREME NORD- 196822-GO-RFQ / Fourniture et installation de Component A: Local Request for Single Stage - One 2020-11- 2021-01- 2021-01- 2021-04- 39 lampadaires a énergie IDA / 57180 Post Open - National 89,143.00 68,717.03 Signed development support Quotations Envelope 04 15 08 15 solaire dont 10 à Ndoukoula,14 à Dagaï Kola et de 15 à Loulou Commune de Ndoukoula CM-CRC EXTREME NORD- 196840-GO-RFQ / Fourniture et l'installation Component A: Local Request for Single Stage - One 2020-11- 2021-01- 2021-01- 2021-07- IDA / 57180 Post Open - National 16,571.00 12,009.59 Signed de 3 poteaux solaires à development support Quotations Envelope 04 15 08 14 Ouro Bone et 03 à Modjombodi Commune de Mindif. CM-CRC EXTREME NORD- 196835-GO-RFQ / Fourniture et installation de Component A: Local Request for Single Stage - One 2020-11- 2020-12- 2021-01- 2021-03- IDA / 57180 Post Open - National 31,429.00 27,298.43 Signed 12 poteaux solaires de l’axe development support Quotations Envelope 04 30 08 30 Sous-préfecture- Ngaoundéréo Commune de Kalfou CM-CRC EXTREME NORD- 196829-GO-RFQ / Pending Fourniture et installation Component A: Local Request for Single Stage - One 2020-11- 2020-12- 2021-02- IDA / 57180 Post Limited 9,905.00 0.00 Implement d’un kit solaire pour development support Quotations Envelope 04 30 28 ation l’alimentation en energie électrique du lycée de gabaraye. Commune Gueme. CM-CRC EXTREME NORD- Component C: Under 196917-GO-RFQ / Coordination, management, Request for Single Stage - One 2020-11- 2020-12- 2021-01- IDA / 62240 Post Limited 9,000.00 0.00 Implement Fourniture et installation monitoring and evaluation Quotations Envelope 04 30 29 ation des stores et moquettes à la and communication CRC EN CM-CRC EXTREME NORD- 196937-GO-RFQ / Fourniture et installation du Component C: matériel informatique (5 Under Coordination, management, Request for Single Stage - One 2020-11- 2020-11- 2020-12- 2021-01- ordinateurs portables pour IDA / 62240 Post Limited 18,000.00 0.00 Implement monitoring and evaluation Quotations Envelope 04 09 30 29 CR, RRSE, CPTR, CCI2 et ation and communication ARPM) et de reprographie (deux photocopieurs professionnels) à la CRC de l’Extrême-nord CM-CRC EXTREME NORD- 196954-GO-RFQ / Achat de Component C: matériels, équipements et Pending Coordination, management, Request for Single Stage - One 2020-11- 2020-12- 2021-01- mobilier de bureaux(chaises IDA / 62240 Post Limited 8,400.00 0.00 Implement monitoring and evaluation Quotations Envelope 04 30 29 réception(20), fauteuil ation and communication directeur(10), 2bureaux) à la CRC Région de l'Extrême- Nord CM-CRC EXTREME NORD- 196957-GO-RFQ / Component C: Acquisition des fournitures Coordination, management, Request for Single Stage - One 2020-11- 2020-11- 2020-12- 2020-12- 2021-01- IDA / 62240 Post Limited 8,000.00 7,316.27 Signed de bureaux et divers pour le monitoring and evaluation Quotations Envelope 04 26 30 14 29 compte de la CRC, Région and communication de l'Extrême-Nord CM-CRC EXTREME NORD- Component C: 196959-GO-RFQ / Coordination, management, Request for Single Stage - One 2020-11- 2020-10- 2020-12- 2020-12- 2021-06- Fourniture des services de IDA / 62240 Post Limited 4,937.00 8,659.75 Signed monitoring and evaluation Quotations Envelope 04 26 30 31 28 gardiennage à la CRC, and communication Région de l'Extrême-Nord CM-CRC EXTREME NORD- 196961-GO-RFQ / Fournture de service de Maintenance informatique Component C: (photocopieur, scanner, Coordination, management, Request for Single Stage - One 2020-11- 2020-10- 2020-12- 2020-12- 2021-12- IDA / 62240 Post Limited 4,800.00 4,428.86 Signed ordinateur portable , monitoring and evaluation Quotations Envelope 04 26 30 31 25 desktop et copieur à la CRC- and communication EN lot 01 et maintenance électricité, climatisseur, groupe électrogène et plomberie lot 02 à la CRC- EN CM-CRC EXTREME NORD- 196962-GO-RFQ / Acquisition de 6 Kits solaires pour les communes Component B: Support to Pending Request for Single Stage - One 2020-11- 2021-02- 2021-07- de Mora, Fotokol, Makary, IDA / 62240 the decentralization Post Open - National 69,600.00 0.00 Implement Quotations Envelope 21 01 31 Logone Birni, mokolo et process ation Waza pour le fonctionnement de SIMBA dans la Region de l'Extreme- nord CM-CRC EXTREME NORD- 204462-GO-RFQ / Pending Component A: Local Request for Single Stage - One 2020-12- 2021-02- 2021-04- fourniture en equipements IDA / 62240 Post Open - National 60,000.00 0.00 Implement development support Quotations Envelope 01 02 03 et medicaments aux CSI de ation Zizagué et CSI de Waza CM-CRC EXTREME NORD- 204459-GO-RFQ / fourniture en equipements Under Component A: Local Request for Single Stage - One 2020-12- 2021-02- 2021-04- et medicaments aux CSI de IDA / 62240 Post Open - National 60,000.00 0.00 Implement development support Quotations Envelope 01 02 03 Kossa et au CSI de Méhé ation Emma dans la commune de Commune de Mora CM-CRC EXTREME NORD- 196810-GO-RFQ / Fourniture en Equipement en 60 tables bancs et un Component A: Local Request for Single Stage - One 2020-11- 2020-12- 2021-02- IDA / 57180 Post Limited 9,905.00 0.00 Canceled bureau à l'EP Guinlaye et development support Quotations Envelope 04 30 28 111 tables bancs et un bureau à l'EP BOGO SIRATARE I Commune de BOGO CM-CRC EXTREME NORD- 196816-GO-RFQ / Fourniture en équipement Component A: Local Request for Single Stage - One 2020-10- 2020-12- 2021-02- en 200 tables bancs, 4 IDA / 57180 Post Open - National 12,952.00 0.00 Canceled development support Quotations Envelope 05 16 14 bureaux, 4 chaises rembourrées et 4 armoires à l'EP MAGA IIB Commune de Maga. CM-CRC EXTREME NORD- 196797-GO-RFQ / Component A: Local Request for Single Stage - One 2020-11- 2021-01- 2021-03- Fourniture en Équipement IDA / 57180 Post Open - National 12,801.00 0.00 Canceled development support Quotations Envelope 04 15 16 en matériel médicaux au CSI de Takreo yoldeo Commune Kar Hay CM-CRC EXTREME NORD- Component C: 222789-GO-RFQ / Pending Coordination, management, Request for Single Stage - One 2021-04- 2021-06- 2021-12- Fourniture de Achat de 3 IDA / 62240 Post Limited 6,000.00 0.00 Implement monitoring and evaluation Quotations Envelope 13 08 05 scanners professionnels à la ation and communication CRC de l’Extrême-nord ( C101203) CM-CRC EXTREME NORD- 222792-GO-RFQ / Component C: Pending Acquisition de Coordination, management, Request for Single Stage - One 2021-04- 2021-06- 2021-07- IDA / 62240 Post Limited 15,000.00 0.00 Implement consommables monitoring and evaluation Quotations Envelope 13 08 08 ation informatiques et autres and communication fournitures dela CRC, Région de l'EN ( C101303) CM-CRC EXTREME NORD- 222730-GO-RFQ / Component C: Pending Acquisition des fournitures Coordination, management, Request for Single Stage - One 2021-04- 2021-06- 2021-07- IDA / 62240 Post Limited 9,000.00 0.00 Implement de bureaux et divers pour le monitoring and evaluation Quotations Envelope 13 08 08 ation compte de la CRC, Région and communication de l'Extrême-Nord (C101301) CM-CRC EXTREME NORD- 222841-GO-RFQ / Component C: Pending Acquisition des fournitures Coordination, management, Request for Single Stage - One 2021-04- 2021-06- 2021-12- IDA / 62240 Post Limited 4,935.00 0.00 Implement pour véhicules à la CRC, monitoring and evaluation Quotations Envelope 13 08 05 ation Région de l'Extrême-Nord and communication (C101304) CM-CRC EXTREME NORD- 222795-GO-RFQ / Component C: Pending Acquisition d'un vehicule Coordination, management, Request for Single Stage - One 2021-04- 2021-06- 2021-08- IDA / 62240 Post Open - National 50,000.00 0.00 Implement pick up pour le compte de monitoring and evaluation Quotations Envelope 13 08 07 ation la CRC, Région de l'Extrême- and communication Nord (C101205) CM-CRC EXTREME NORD- 222798-GO-RFQ / FOURNITURE ET INSTALLATION D’UNE MINI Pending CENTRALE SOLAIRE AU CSI Component A: Local Request for 2021-04- 2021-06- 2021-09- IDA / 62240 Post 56,935.00 0.00 Implement DE KOSSA, DANS LA development support Quotations 13 08 06 ation COMMUNE DE MORA, DEPARTEMENT DU MAYO- SAVA, REGION DE L’EXTREME – NORD. (A2011B1) NON CONSULTING SERVICES Activity Reference No. Estimated Actual Draft Pre- Draft Bidding Specific Proposal Bid Evaluation Loan / Credit Market Procurement Prequalificati Process Prequalification Bidding Documents Contract / Description Component Review Type Method Amount Amount qualification Document / Procurement Notice Submission / Report and Signed Contract No. Approach Process on (Y/N) Status Evaluation Report as Issued Completion (US$) (US$) Documents Justification / Invitation Opening / Minutes Recommendation Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned for Award Actual Planned Actual Planned Actual CM-CRC EXTREME NORD- 111430-NC-RFQ / Selection d'une agence d'edition pour la production d'un bulletin Component A: Local Request for Single Stage - One 2019-06- 2019-08- 2019-11- 2020-08- IDA / 57180 Post Open - National 47,000.00 31,781.53 Signed trimestriel d'informations development support Quotations Envelope 09 04 15 03 communales(47 communes) dans la region de l'Extreme- nord CONSULTING FIRMS Activity Reference No. Actual Short List and Draft Opening of Combined Loan / Credit Market Contract Type Estimated Process Expression of Request for Evaluation of Contract / Description Component Review Type Method Amount Terms of Reference Request for Technical Proposals Evaluation Report Signed Contract No. Approach Amount (US$) Status Interest Notice Proposals as Issued Technical Proposal Completion (US$) Proposals / Minutes and Draft Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Negotiated Contract Actual Planned Actual Planned Actual CM-CRC EXTREME NORD- 8076-CS-CQS / Sélection Component B: Support to Consultant d'un consultant pour 2017-03- 2017-05- 2017-03- 2017-05- 2017-06- 2017-06- 2018-03- 2017-07- 2018-07- 2018-05- 2020-08- IDA / 57180 the decentralization Post Qualification Open - National 63,060.00 20,007.04 Completed l'actualisation du PCD de la 10 04 31 14 10 13 22 18 06 14 05 process Selection commune de Guéré, Région de l'Extrême-Nord CM-CRC EXTREME NORD- 8082-CS-CQS / Sélection Component B: Support to Consultant d'un consultant pour 2017-03- 2017-05- 2017-03- 2017-05- 2017-06- 2017-06- 2018-03- 2017-07- 2018-07- 2018-05- IDA / 57180 the decentralization Post Qualification Open - National 26,970.00 22,183.49 Signed l'actualisation du PCD de la 10 04 31 14 10 13 22 18 11 14 process Selection commune de Kalfou, Région de l'Extrême-Nord Page 5 CM-CRC EXTREME NORD- 8088-CS-CQS / Sélection Component B: Support to Consultant d'un consultant pour 2017-03- 2017-05- 2017-03- 2017-05- 2017-06- 2017-06- 2018-03- 2017-07- 2018-07- 2018-05- IDA / 57180 the decentralization Post Qualification Open - National 63,060.00 18,355.82 Signed l'actualisation du PCD de la 10 04 31 14 09 13 22 18 06 14 process Selection commune de Mindif, Région de l'Extrême-Nord CM-CRC EXTREME NORD- 8094-CS-CQS / Sélection Component B: Support to Consultant d'un consultant pour 2017-03- 2017-05- 2017-03- 2017-05- 2017-06- 2017-06- 2018-03- 2017-07- 2018-07- 2018-05- IDA / 57180 the decentralization Post Qualification Open - National 53,760.00 30,571.90 Signed l'actualisation du PCD de la 10 04 31 14 10 13 27 18 06 14 process Selection commune de Gazawa., Région de l'Extrême-Nord CM-CRC EXTREME NORD- 8093-CS-CQS / Sélection Component B: Support to Consultant d'un consultant pour 2017-03- 2017-05- 2017-03- 2017-05- 2017-06- 2017-06- 2018-03- 2017-07- 2018-06- 2018-05- IDA / 57180 the decentralization Post Qualification Open - National 15,570.00 29,601.16 Signed l'actualisation du PCD de la 10 04 31 14 09 13 22 18 27 14 process Selection commune de Guidiguis, Région de l'Extrême-Nord CM-CRC EXTREME NORD- 8097-CS-CQS / Sélection Component B: Support to Consultant d'un consultant pour 2017-03- 2017-05- 2017-03- 2017-05- 2017-06- 2017-06- 2018-03- 2017-07- 2018-07- 2018-05- IDA / 57180 the decentralization Post Qualification Open - National 57,600.00 18,445.45 Signed l'actualisation du PCD de la 10 04 31 14 10 13 27 18 06 14 process Selection commune de Dargala, Région de l'Extrême-Nord CM-CRC EXTREME NORD- 29268-CS-CQS / Sélection Component B: Support to Consultant d'un consultant pour 2017-09- 2017-05- 2017-10- 2017-11- 2017-06- 2017-12- 2018-03- 2018-01- 2018-07- 2018-11- 2020-08- IDA / 57180 the decentralization Post Qualification Open - National 63,060.00 8,628.26 Completed l'actualisation du PCD de la 20 04 11 24 10 24 22 28 06 24 05 process Selection commune de WINA, Région de l'Extrême-Nord CM-CRC EXTREME NORD- 29270-CS-CQS / Sélection Component B: Support to Consultant d'un consultant pour 2017-09- 2017-05- 2017-10- 2017-11- 2017-06- 2017-12- 2018-03- 2018-01- 2018-07- 2018-11- IDA / 57180 the decentralization Post Qualification Open - National 26,460.00 29,798.62 Signed l'actualisation du PCD de la 20 23 11 24 09 24 27 28 16 24 process Selection commune de BOURHA, Région de l'Extrême-Nord CM-CRC EXTREME NORD- 29272-CS-CQS / Sélection Component B: Support to Consultant d'un consultant pour 2017-09- 2017-05- 2017-10- 2017-11- 2017-06- 2017-12- 2018-03- 2018-01- 2018-07- 2018-11- IDA / 57180 the decentralization Post Qualification Open - National 63,060.00 23,663.61 Signed l'actualisation du PCD de la 20 04 11 24 10 24 27 28 06 24 process Selection commune de Hina, Région de l'Extrême-Nord CM-CRC EXTREME NORD- 29273-CS-CQS / Sélection Component B: Support to Consultant d'un consultant pour 2017-09- 2017-05- 2017-10- 2017-11- 2017-06- 2017-12- 2018-03- 2018-01- 2018-06- 2018-11- IDA / 57180 the decentralization Post Qualification Open - National 15,570.00 9,919.43 Signed l'actualisation du PCD de la 20 04 11 24 10 24 27 28 25 24 process Selection commune de Koza, Région de l'Extrême-Nord CM-CRC EXTREME NORD- 29274-CS-CQS / Sélection Component B: Support to Consultant d'un consultant pour 2017-09- 2017-05- 2017-10- 2017-11- 2017-06- 2017-12- 2018-03- 2018-01- 2018-07- 2018-11- IDA / 57180 the decentralization Post Qualification Open - National 53,760.00 37,441.16 Signed l'actualisation du PCD de la 20 04 11 24 10 24 27 28 06 24 process Selection commune de Mozogo., Région de l'Extrême-Nord CM-CRC EXTREME NORD- 29276-CS-CQS / Sélection Component B: Support to Consultant d'un consultant pour 2017-09- 2017-10- 2017-11- 2017-12- 2018-01- 2018-11- IDA / 57180 the decentralization Post Qualification Open - National 57,600.00 0.00 Canceled l'actualisation du PCD de la 20 11 24 24 28 24 process Selection commune de Kolofata, Région de l'Extrême-Nord CM-CRC EXTREME NORD- 29277-CS-CQS / Sélection Component B: Support to Consultant d'un consultant pour 2017-09- 2017-05- 2017-10- 2017-11- 2017-06- 2017-12- 2018-01- 2018-11- IDA / 57180 the decentralization Post Qualification Open - National 57,600.00 0.00 Canceled l'actualisation du PCD de la 20 04 11 24 10 24 28 24 process Selection commune de Kolofata, Région de l'Extrême-Nord CM-CRC EXTREME NORD- 29280-CS-CQS / Sélection Component B: Support to Consultant d'un consultant pour 2017-09- 2017-10- 2017-11- 2017-12- 2018-01- 2018-11- IDA / 57180 the decentralization Post Qualification Open - National 26,970.00 0.00 Canceled l'actualisation du PCD de la 20 11 24 24 28 24 process Selection commune de Goulfey, Région de l'Extrême-Nord CM-CRC EXTREME NORD- 29281-CS-CQS / Sélection Component B: Support to Consultant d'un consultant pour 2017-09- 2017-05- 2017-10- 2017-11- 2017-06- 2017-12- 2018-03- 2018-01- 2018-10- 2018-11- IDA / 57180 the decentralization Post Qualification Open - National 26,460.00 17,141.65 Signed l'actualisation du PCD de la 20 04 11 24 14 24 22 28 06 24 process Selection commune de FOTOKOL, Région de l'Extrême-Nord CM-CRC EXTREME NORD- 29282-CS-CQS / Sélection Component B: Support to Consultant d'un consultant pour 2017-09- 2017-05- 2017-10- 2017-11- 2017-06- 2017-12- 2018-03- 2018-01- 2018-07- 2018-11- 2020-08- IDA / 57180 the decentralization Post Qualification Open - National 63,060.00 -2,518.29 Completed l'actualisation du PCD de la 20 04 11 24 15 24 20 28 06 24 05 process Selection commune de Blangoua, Région de l'Extrême-Nord CM-CRC EXTREME NORD- 29284-CS-CQS / Sélection Component B: Support to Consultant d'un consultant pour 2017-09- 2017-05- 2017-10- 2017-11- 2017-06- 2017-12- 2018-03- 2018-01- 2018-07- 2018-11- IDA / 57180 the decentralization Post Qualification Open - National 15,570.00 31,593.26 Signed l'actualisation du PCD de la 20 04 11 24 15 24 22 28 11 24 process Selection commune de Darak, Région de l'Extrême-Nord CM-CRC EXTREME NORD- 8089-CS-CQS / sélection Component B: Support to Consultant d'un consultant pour 2018-06- 2018-09- 2018-07- 2018-08- 2018-11- 2018-09- 2018-12- 2018-10- 2019-03- 2019-08- IDA / 57180 the decentralization Post Qualification Open - National 26,460.00 19,922.77 Signed l'actualisation du PCD de la 15 28 06 19 07 18 21 23 01 19 process Selection commune de Datcheka, Région de l'Extrême-Nord CM-CRC EXTREME NORD- 29269-CS-CQS / Sélection Component B: Support to Consultant d'un consultant pour 2018-06- 2018-09- 2018-07- 2018-08- 2018-11- 2018-09- 2018-12- 2018-10- 2019-03- 2019-08- IDA / 57180 the decentralization Post Qualification Open - National 26,970.00 18,485.99 Signed l'actualisation du PCD de la 15 28 06 19 07 18 21 23 01 19 process Selection commune de TCHATIBALI, Région de l'Extrême-Nord CM-CRC EXTREME NORD- 29278-CS-CQS / Sélection Component B: Support to Consultant d'un consultant pour 2018-06- 2018-09- 2018-07- 2018-08- 2018-11- 2018-09- 2018-12- 2018-10- 2019-03- 2019-08- 2020-08- IDA / 57180 the decentralization Post Qualification Open - National 63,060.00 -1,222.01 Completed l'actualisation du PCD de la 15 28 06 19 10 18 21 23 01 19 05 process Selection commune de Waza, Région de l'Extrême-Nord CM-CRC EXTREME NORD- 29285-CS-CQS / Sélection Component B: Support to Consultant d'un consultant pour 2018-06- 2018-09- 2018-07- 2018-08- 2018-11- 2018-09- 2018-12- 2018-10- 2019-03- 2019-08- IDA / 57180 the decentralization Post Qualification Open - National 53,760.00 1,279.72 Signed l'actualisation du PCD de la 15 28 06 19 10 18 21 23 01 19 process Selection commune deHILE-ALIFA., Région de l'Extrême-Nord CM-CRC EXTREME NORD- 58613-CS-CQS / Sélection Component B: Support to Consultant d'un consultant pour 2018-06- 2018-09- 2018-07- 2018-08- 2018-11- 2018-09- 2018-12- 2018-10- 2019-03- 2019-08- 2020-08- IDA / 57180 the decentralization Post Qualification Open - National 26,070.00 24,573.33 Completed l'actualisation du PCD de la 15 28 06 19 10 18 21 23 01 19 05 process Selection cmne de Goulfey, Région de l'Extrême-Nord CM-CRC EXTREME NORD- 58629-CS-CQS / Sélection Component B: Support to Consultant d'un consultant pour 2018-06- 2018-10- 2018-07- 2018-08- 2018-11- 2018-09- 2018-12- 2018-10- 2019-03- 2019-08- 2020-08- IDA / 57180 the decentralization Post Qualification Open - National 57,600.00 -2,073.39 Completed l'actualisation du PCD de la 15 02 06 19 06 18 21 23 01 19 05 process Selection cmne de Kolofata, Région de l'Extrême-Nord CM-CRC EXTREME NORD- 58563-CS-CQS / Sélection de deux consultants (OAL) Consultant Component A: Local 2017-04- 2017-03- 2017-04- 2017-06- 2017-04- 2017-07- 2017-05- 2017-08- 2017-09- 2017-11- pour la collecte et la saisie IDA / 57180 Post Qualification Open - National 85,727.00 546,754.14 Signed development support 05 30 26 09 19 09 27 13 27 11 des données du score cadre Selection deans 21 cmnes , Région de l'Extrême-Nord CM-CRC EXTREME NORD- 111119-CS-CQS / Sélection Component B: Support to Consultant 2019-06- 2020-09- 2019-06- 2019-08- 2019-09- 2019-10- 2020-08- d'un OAL pour IDA / D2990 the decentralization Post Qualification Open - National 13,000.00 0.00 Canceled 01 14 22 05 04 09 04 l'actualisation légère du PCD process Selection de la commune de KAI KAI CM-CRC EXTREME NORD- 111118-CS-CQS / Sélection Component B: Support to Consultant 2019-06- 2019-07- 2019-06- 2019-08- 2019-08- 2019-09- 2020-09- 2019-10- 2021-05- d'un OAL pour IDA / 57180 the decentralization Post Qualification Open - National 13,000.00 0.00 Canceled 01 25 22 05 29 04 14 09 31 l'actualisation légère du PCD process Selection de la commune de YAGOUA CM-CRC EXTREME NORD- 111218-CS-CQS / Sélection Component B: Support to Consultant 2019-06- 2019-07- 2019-06- 2019-08- 2019-12- 2019-09- 2020-09- 2019-10- 2020-08- d'un OAL pour IDA / 57180 the decentralization Post Qualification Open - National 13,000.00 0.00 Canceled 01 25 22 05 29 04 14 09 04 l'actualisation légère du PCD process Selection de la commune de TOKOMBERE CM-CRC EXTREME NORD- 111121-CS-CQS / Sélection Component B: Support to Consultant 2019-06- 2019-07- 2019-06- 2019-08- 2019-08- 2019-09- 2020-09- 2019-10- 2020-08- d'un OAL pour IDA / 57180 the decentralization Post Qualification Open - National 13,000.00 0.00 Canceled 01 25 22 05 29 04 14 09 04 l'actualisation légère du PCD process Selection de la commune de NDOUKOULA CM-CRC EXTREME NORD- 111120-CS-CQS / Sélection Component B: Support to Consultant 2019-06- 2019-07- 2019-06- 2019-08- 2019-08- 2019-09- 2020-09- 2019-10- 2020-08- d'un OAL pour IDA / 57180 the decentralization Post Qualification Open - National 13,000.00 0.00 Canceled 01 25 22 05 29 04 14 09 04 l'actualisation légère du PCD process Selection de la commune de MOUTOURWA CM-CRC EXTREME NORD- 111122-CS-CQS / Sélection Component B: Support to Consultant 2019-06- 2019-07- 2019-06- 2019-08- 2019-08- 2019-09- 2020-09- 2019-10- 2020-08- d'un OAL pour IDA / 57180 the decentralization Post Qualification Open - National 13,000.00 0.00 Canceled 01 25 22 05 29 04 14 09 04 l'actualisation légère du PCD process Selection de la commune de MOGODE CM-CRC EXTREME NORD- 111231-CS-CQS / Sélection Component B: Support to Consultant 2019-06- 2019-07- 2019-06- 2019-08- 2019-08- 2019-09- 2020-09- 2019-10- 2020-08- d'un OAL pour IDA / 57180 the decentralization Post Qualification Open - National 13,000.00 0.00 Canceled 01 25 22 05 29 04 14 09 04 l'actualisation légère du PCD process Selection de la commune de MAKARY CM-CRC EXTREME NORD- 111232-CS-CQS / Sélection Component B: Support to Consultant 2019-06- 2019-07- 2019-06- 2019-08- 2019-08- 2019-09- 2020-09- 2019-10- 2019-11- d'un OAL pour IDA / 57180 the decentralization Post Qualification Open - National 13,000.00 0.00 Canceled 01 25 22 05 29 04 14 09 08 l'actualisation légère du PCD process Selection de la commune de LOGONE BIRNI CM-CRC EXTREME NORD- 111123-CS-CQS / Sélection Component B: Support to Consultant 2019-06- 2019-07- 2019-06- 2019-08- 2020-07- 2019-09- 2020-05- 2019-10- 2020-08- d'un OAL pour IDA / 57180 the decentralization Post Qualification Open - National 13,000.00 0.00 Canceled 01 25 22 05 14 04 26 09 04 l'actualisation légère du PCD process Selection de la commune de KAELE CM-CRC EXTREME NORD- 111124-CS-CQS / Sélection Component B: Support to Consultant 2019-06- 2019-07- 2019-06- 2019-08- 2020-07- 2019-09- 2020-05- 2019-10- 2020-08- d'un OAL pour IDA / 57180 the decentralization Post Qualification Open - National 13,000.00 0.00 Canceled 01 25 22 05 15 04 26 09 04 l'actualisation légère du PCD process Selection de la commune de BOGO CM-CRC EXTREME NORD- 111230-CS-CQS / Sélection Component B: Support to Consultant 2019-06- 2020-09- 2019-06- 2019-08- 2019-09- 2019-10- 2020-08- d'un OAL pour IDA / 57180 the decentralization Post Qualification Open - National 13,000.00 0.00 Canceled 01 14 22 05 04 09 04 l'actualisation légère du PCD process Selection de la commune de MOKOLO CM-CRC EXTREME NORD- 222975-CS-CQS / Sélection d'un consultant (OSC) pour la collecte et la saisie des Component B: Support to Consultant Pending 2021-04- 2021-04- 2021-06- 2021-07- 2021-08- 2022-02- données du score cadre IDA / 62240 the decentralization Post Qualification Open - National 36,400.00 0.00 Implementation 08 29 12 12 16 12 dans 7 communes (darak process Selection hile alifa, blangoua, Fotokol, kousseri zina et waza) , Région de l'Extrême-Nord ( B201103) CM-CRC EXTREME NORD- 222973-CS-CQS / Sélection d'un consultant (OSC) pour la collecte et la saisie des Component B: Support to Consultant Pending 2021-04- 2021-04- 2021-06- 2021-07- 2021-08- 2022-02- données du score cadre IDA / 62240 the decentralization Post Qualification Open - National 36,400.00 0.00 Implementation 08 29 12 12 16 12 deans 7 communes (mora, process Selection kolofata, meri, maroua 1, Bourha, Koza et mokolo) , Région de l'Extrême-Nord ( B201103) CM-CRC EXTREME NORD- 222960-CS-CQS / Sélection d'un consultant (OSC) pour la collecte et la saisie des Component B: Support to Consultant Pending 2021-04- 2021-04- 2021-06- 2021-07- 2021-08- 2022-02- données du score cadre IDA / 62240 the decentralization Post Qualification Open - National 31,200.00 0.00 Implementation 08 29 12 12 16 12 deans 6 communes (bogo, process Selection pette, maroua 3, TOULOUM,Mindif , GUIDIGUIS°, Région de l'Extrême-Nord ( B201103) CM-CRC EXTREME NORD- 222968-CS-CQS / Sélection d'un consultant (OSC) pour la collecte et la saisie des Component B: Support to Consultant Pending 2021-04- 2021-04- 2021-06- 2021-07- 2021-08- 2022-02- données du score cadre IDA / 62240 the decentralization Post Qualification Open - National 31,200.00 0.00 Implementation 08 29 12 12 16 12 deans 6 communes (Krhay, process Selection Kalfou, guere, wina datcheka et kaikai), Région de l'Extrême-Nord ( B201103) INDIVIDUAL CONSULTANTS Activity Reference No. Actual Invitation to Loan / Credit Market Contract Type Estimated Process Draft Negotiated Contract / Description Component Review Type Method Amount Terms of Reference Identified/Selected Signed Contract No. Approach Amount (US$) Status Contract Completion (US$) Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CM-CRC EXTREME NORD- 8103-CS-INDV / Sélection d'un consultant pour l'élaboration des Etudes de Individual faisabilité techniques et Component A: Local 2017-03- 2017-05- 2017-03- 2017-06- 2017-04- 2017-06- 2017-05- 2017-12- 2017-06- IDA / 57180 Post Consultant Limited 3,000.00 3,805.88 Signed environnementales de development support 06 08 11 12 01 16 06 28 20 Selection Construction d'un bloc saitaire et d'un bloc de latrines au CSI de Djiddeo garre, commune de Maroua III CM-CRC EXTREME NORD- 8107-CS-INDV / Sélection d'un consultant pour l'élaboration des Etudes de faisabilité techniques et Individual Component A: Local 2017-03- 2017-05- 2017-03- 2017-06- 2017-04- 2017-06- 2017-05- 2017-06- 2017-06- 2018-01- environnementales de IDA / 57180 Post Consultant Limited 2,600.00 1,522.35 Completed development support 06 08 11 13 01 16 06 19 20 25 Construction de 2 forages Selection équipés de PMH, un à Dolddosewo et un Ngouroré et la construction d'un bief à Kossewa, commune Maroua II CM-CRC EXTREME NORD- 8110-CS-INDV / Sélection d'un consultant pour l'élaboration des Etudes de faisabilité techniques et Individual Component A: Local 2017-03- 2017-03- 2017-04- 2017-05- 2017-06- environnementales de IDA / 57180 Post Consultant Limited 3,000.00 0.00 Canceled development support 06 11 01 06 20 Construction d'un bloc Selection sanitaire et d'un bloc de latrines au centre de santé de Rhumzou, dans la commune de Mogodé CM-CRC EXTREME NORD- 8112-CS-INDV / Sélection d'un consultant pour l'élaboration des Etudes de faisabilité techniques et Individual environnementales des MP Component A: Local 2017-03- 2017-05- 2017-03- 2017-09- 2017-04- 2017-09- 2017-05- 2017-10- 2017-06- 2017-10- IDA / 57180 Post Consultant Limited 2,400.00 2,093.23 Completed de Construction d'un bloc development support 06 08 11 05 01 12 06 20 20 23 Selection de deux salles de classe équipées d'un bloc latrines a trois compartiements à l'EP de Sedek Ourogabdo et au CES de BOGO CM-CRC EXTREME NORD- 8114-CS-INDV / Sélection d'un consultant pour l'élaboration des Etudes de faisabilité MP de Individual Component A: Local 2017-03- 2017-05- 2017-03- 2017-09- 2017-04- 2017-09- 2017-05- 2017-09- 2017-06- 2017-10- Construction d 6 forage IDA / 57180 Post Consultant Limited 5,600.00 3,615.59 Completed development support 06 08 11 05 01 12 06 20 20 23 équipé de pompe à Selection motricité humaine et e deux (02) forages équipé de pompe à motricité humaine et rehabilitation de deux forages exista commune de BOGO CM-CRC EXTREME NORD- 8118-CS-INDV / Sélection d'un Consultant pour le Suivi/contrôle des Travaux de Construction et Individual équipement d'01 bloc de 02 Component A: Local 2017-03- 2017-04- 2017-03- 2017-04- 2017-04- 2017-10- 2017-05- 2017-11- 2017-08- IDA / 57180 Post Consultant Limited 6,186.00 3,107.61 Signed salles de classe et d'un bloc development support 06 03 11 07 01 11 06 01 04 Selection de latrines à trois compartiments à l'EP Dogba, Gayack dans Construction d1 hangar et d'un bloc de latrines A PAPATA CM-CRC EXTREME NORD- 8122-CS-INDV / Sélection d'un Consultant pour le Suivi/contrôle des Travaux de Construction d'un Individual Component A: Local 2017-03- 2017-04- 2017-03- 2017-05- 2017-04- 2017-10- 2017-05- 2017-10- 2017-08- magasin de stockage à Kéné- IDA / 57180 Post Consultant Limited 3,304.00 2,572.86 Signed development support 06 10 11 08 01 26 06 30 04 Kéné, Construction d'un Selection bloc de 02 salles de classe équipées à l'EP de Djafgué, et Construction d'un bloc de latrines à l'EP de Djafgué cne Page 6 CM-CRC EXTREME NORD- 8126-CS-INDV / sélection d'un consultant pour le sui/contrôle des travaux de Individual réalisation de 6 forages Component A: Local 2017-03- 2017-03- 2017-04- 2017-05- 2017-08- IDA / 57180 Post Consultant Limited 3,840.00 0.00 Canceled équipés de PMH à Tchékéhi, development support 06 11 01 06 04 Selection Mbokouré, Magaldao Toupéo, Soukkoungo Galdima, Bourango et Bandalaré dans la commune de Pétté CM-CRC EXTREME NORD- 8130-CS-INDV / sélection d'un consultant pour le suivi/controle des travaux Individual de Construction d'un forage Component A: Local 2017-03- 2017-04- 2017-03- 2017-05- 2017-04- 2017-11- 2017-05- 2017-11- 2017-08- IDA / 57180 Post Consultant Limited 3,200.00 3,047.82 Signed pastoral à énergie solaire development support 06 10 11 08 01 08 06 20 04 Selection Balaza Lawane (Tchalloudi mango) 1 forage pastoral à énergie solaire à Kongola Saïd, commune de Maroua 3 CM-CRC EXTREME NORD- 8154-CS-INDV / sélection d'un consultant pour le suivi/controle des travaux de Construction d'un bloc Individual Component A: Local 2017-03- 2017-03- 2017-04- 2017-05- 2017-08- de 02 salles de classe IDA / 57180 Post Consultant Limited 5,544.00 0.00 Canceled development support 06 11 01 06 04 équipées et d'un bloc de Selection latrines à trois compartiments à l'EP de Mayel Béi, à l'EP de Bao Hosséré II et à l'EP de Palaoudi, commune Maroua 1 CM-CRC EXTREME NORD- 8157-CS-INDV / sélection d'un consultant pour le suivi/contrôle des travaux Individual de construction d'un bloc Component A: Local 2017-03- 2017-03- 2017-04- 2017-05- 2017-08- IDA / 57180 Post Consultant Limited 2,292.00 0.00 Canceled maternel à l'école Maternelle development support 06 11 01 06 04 Selection de Zokok-Laddo et branchement au réseau d'alimentation en eau potable, commune de Maroua 1 CM-CRC EXTREME NORD- 8159-CS-INDV / sélection d'un consultant pour le suivi/contrôle des travaux Individual Component A: Local 2017-03- 2017-04- 2017-03- 2017-06- 2017-04- 2017-06- 2017-05- 2017-06- 2017-08- 2018-02- de Construction de trois IDA / 57180 Post Consultant Limited 1,840.00 1,591.10 Completed development support 06 10 11 13 01 30 06 30 04 20 forages équipés de pompe à Selection motricité humaine à Ouro Dow, Goni Bello et Yoldéo Guiziga, Commune Maroua 1 CM-CRC EXTREME NORD- 8161-CS-INDV / sélection d'un consultant pour le suivi/contrôle des travaux Individual de Construction d'un bloc Component A: Local 2017-03- 2017-04- 2017-03- 2017-05- 2017-04- 2017-06- 2017-05- 2017-06- 2017-08- IDA / 57180 Post Consultant Limited 3,690.00 3,041.89 Signed de 02 salles de classe development support 06 10 11 08 01 30 06 30 04 Selection équipées et d'un bloc de latrines à trois compartiments à l'EP Masfaï et au CES de Boula, commune de Mokolo CM-CRC EXTREME NORD- 8163-CS-INDV / sélection d'un consultant pour le Individual suivi/contrôle des travaux Component A: Local 2017-03- 2017-04- 2017-03- 2017-05- 2017-04- 2017-06- 2017-05- 2017-09- 2017-08- IDA / 57180 Post Consultant Limited 1,350.00 1,113.47 Signed de Construction de 2 development support 06 10 11 08 01 06 06 14 04 Selection forages équipés de PMH un à Ouro Kessoum et à Mounam, commune de Mokolo CM-CRC EXTREME NORD- 8165-CS-INDV / sélection d'un consultant pour le suivi/contrôle des travaux Individual Component A: Local 2017-03- 2017-04- 2017-03- 2017-05- 2017-04- 2017-12- 2017-05- 2018-01- 2017-08- 2018-04- de construction d'un IDA / 57180 Post Consultant Limited 3,510.00 3,246.38 Completed development support 06 10 11 08 01 28 06 31 04 24 ouvrage de franchissement Selection et d'assainissement sur le mayo-kwayaga, dans la commune de Mogodé CM-CRC EXTREME NORD- 8166-CS-INDV / sélection d'un consultant pour le suivi/contrôle des travaux Individual de Construction d'un bloc Component A: Local 2017-03- 2017-03- 2017-03- 2017-04- 2017-04- 2017-06- 2017-05- 2017-06- 2017-08- 2017-09- IDA / 57180 Post Consultant Limited 3,618.00 2,776.20 Completed de 02 salles de classe development support 06 31 11 07 01 14 06 21 04 27 Selection équipées et d'un bloc de latrines à trois compartiments à l'EP de Saoudjo et au CES de Madaka, commune de Bogo CM-CRC EXTREME NORD- 8246-CS-INDV / sélection d'un consultant pour le suivi/contrôle des travaux de Construction d'un forage Individual Component A: Local 2017-03- 2017-03- 2017-03- 2017-04- 2017-04- 2017-06- 2017-05- 2017-06- 2017-08- 2017-08- équipé de PMH à Dambaye IDA / 57180 Post Consultant Limited 4,913.00 1,125.49 Completed development support 06 31 11 07 01 14 06 21 04 16 et à Bagalaf etAménagement Selection d'un bas-fond avec un forage à énergie solaire à Ouro Mésséré pour les cultures maraichères, commune de Bogo CM-CRC EXTREME NORD- 8247-CS-INDV / sélection d'un consultant pour le suivi/contrôle des travaux deconstruction d'un bloc de Individual deux (02) salles de classe Component A: Local 2017-03- 2017-04- 2017-03- 2017-05- 2017-04- 2017-11- 2017-05- 2017-11- 2017-09- IDA / 57180 Post Consultant Limited 7,152.00 6,461.92 Signed equipees et un (01) bloc development support 06 10 11 08 01 10 06 15 03 Selection latrine a trois (03) compartiments a l'EP de honkol, a l'EP de darsala, a l'EP de dabanga et l'equipement en me CM-CRC EXTREME NORD- 8248-CS-INDV / sélection d'un consultant pour le suivi/contrôle des travaux deconstruction d'un forage Individual Component A: Local 2017-03- 2017-04- 2017-03- 2017-05- 2017-04- 2017-06- 2017-05- 2017-06- 2017-09- 2017-09- équipé d'une pompe à IDA / 57180 Post Consultant Limited 3,280.00 3,398.97 Completed development support 06 10 11 08 01 02 06 10 03 29 motricité humaine à l' EP de Selection Darsala, l' EP de Dabanga, et un forage pastoral solaire au village Sahaba 1, l'EP groupe de Logone birni et à EP Ho CM-CRC EXTREME NORD- 8249-CS-INDV / sélection d'un consultant pour le Individual Component A: Local 2017-03- 2017-04- 2017-03- 2017-05- 2017-04- 2017-11- 2017-05- 2018-01- 2017-09- 2018-06- suivi/contrôle des travaux IDA / 57180 Post Consultant Limited 4,584.00 3,598.46 Completed development support 06 10 11 08 01 24 06 20 03 13 de réalisation d'une mare Selection artificielle à Mogon dans la commune de Moutourwa CM-CRC EXTREME NORD- 8250-CS-INDV / sélection d'un consultant pour le suivi/contrôle des travaux Individual Component A: Local 2017-03- 2017-04- 2017-03- 2017-07- 2017-04- 2017-07- 2017-05- 2017-07- 2017-08- de construction d'un bloc de IDA / 57180 Post Consultant Limited 4,614.00 4,102.81 Signed development support 06 10 11 17 01 24 06 24 04 deux salles de classe et de Selection deux blocs de latrines à l'EP de Afadé et à l'EP de NGré dans la commune de Makary CM-CRC EXTREME NORD- 8251-CS-INDV / Sélection d'un Consultant pour le Suivi/contrôle des Travaux Individual de Construction de 6 Component A: Local 2017-03- 2017-04- 2017-03- 2017-09- 2017-04- 2017-09- 2017-05- 2018-01- 2017-08- IDA / 57180 Post Consultant Limited 3,840.00 3,192.11 Signed forages équipés de PMH à development support 06 10 11 18 01 25 06 11 04 Selection Tchékéhi, Mbokouré, Magaldao Toupéo, Soukkoungo Galdima, Bourango et Bandalaré dans la commune de Pétté CM-CRC EXTREME NORD- 8252-CS-INDV / Sélection de 3 consultants pour Individual l'appui du CCI dans la Component A: Local 2017-03- 2017-03- 2017-04- 2017-05- 2018-05- IDA / 57180 Post Consultant Limited 27,632.00 0.00 Canceled passation des marchés, le development support 06 11 01 06 06 Selection suivi et l'exécution des projets à la CRC, Région de l'Extrême-Nord CM-CRC EXTREME NORD- 29287-CS-INDV / Sélection d'un consultant pour l'élaboration des Etudes de faisabilité techniques et Individual environnementales des MP Component A: Local 2017-09- 2017-05- 2017-09- 2017-06- 2017-10- 2017-06- 2017-11- 2017-07- 2018-01- 2017-09- IDA / 57180 Post Consultant Limited 8,500.00 5,328.23 Completed de Construction d'un forage development support 20 08 25 09 16 16 20 10 04 22 Selection PMH à Guivel Méri centre, à Houloum, à Tchaki Djébé, à Kilwo, à Mbozo Mofou, à Balewa, à Nguissar, au quartier Hot CM-CRC EXTREME NORD- 29288-CS-INDV / Sélection d'un consultant pour l'élaboration des Etudes de faisabilité techniques et Individual Component A: Local 2017-09- 2017-05- 2017-09- 2017-06- 2017-10- 2017-06- 2017-11- 2017-07- 2018-01- 2017-09- environnementales des MP IDA / 57180 Post Consultant Limited 2,400.00 3,425.29 Completed development support 20 08 25 12 16 16 20 10 04 22 de Construction d'un bloc Selection de deux salles de classe équipées avec un bloc latrines au CES de Manguirdla et Construction d'un magasin de stockage à CM-CRC EXTREME NORD- 29289-CS-INDV / Sélection d'un consultant pour l'élaboration des Etudes de faisabilité techniques et Individual Component A: Local 2017-09- 2017-05- 2017-09- 2017-06- 2017-10- 2017-11- 2017-08- 2018-01- 2017-10- environnementales des MP IDA / 57180 Post Consultant Limited 2,000.00 2,367.54 Completed development support 20 08 25 19 16 20 01 04 04 de Construction 01 bloc de Selection deux salles de classe équipées avec un bloc latrines à l'EP de Djagalaï et au CES de Hardé dans la commune de MRA IER CM-CRC EXTREME NORD- 29291-CS-INDV / Sélection d'un consultant pour l'élaboration des Etudes de faisabilité techniques et Individual Component A: Local 2017-09- 2017-05- 2017-09- 2017-06- 2017-10- 2017-06- 2017-11- 2017-06- 2018-01- 2017-10- environnementales des MP IDA / 57180 Post Consultant Limited 1,600.00 1,694.12 Completed development support 20 08 25 13 16 16 20 19 04 04 de Construction d'un forage Selection équipé de pompe à motricité humaine à Nyamdjidim et à Zébé dans la commune de Maroua I (2 FORAGES PMH) CM-CRC EXTREME NORD- 29292-CS-INDV / Sélection d'un consultant pour les Etudes des des MP de Construction d'un bloc de Individual Component A: Local 2017-09- 2017-05- 2017-11- 2017-06- 2017-11- 2017-06- 2018-01- 2017-07- 2018-02- 2017-09- 02 salles de classe équipées IDA / 57180 Post Consultant Open 3,750.00 4,231.37 Completed development support 21 08 09 12 30 16 04 04 18 21 avec 01 bloc de latrines à Selection l'EP de Ndrock Tourou, à EP Zili Yolel, à EP Moufou Sud, EP de Ldamang et au CES Mandaka commune mokolo CM-CRC EXTREME NORD- 29293-CS-INDV / Sélection d'1 consultant pour Individual Component A: Local 2017-09- 2017-05- 2017-11- 2017-06- 2017-11- 2017-09- 2018-01- 2017-09- 2018-02- 2017-09- l'élaboration des Etudes des IDA / 57180 Post Consultant Open 5,000.00 3,001.30 Completed development support 21 08 09 12 30 08 04 14 18 21 MP de Construction de 08 Selection forage PMH dans la commune de mokolo CM-CRC EXTREME NORD- 29295-CS-INDV / Sélection d'un consultant pour l'élaboration des Etudes de faisabilité techniques et Individual Component A: Local 2017-09- 2017-05- 2017-09- 2017-06- 2017-10- 2017-06- 2017-11- 2017-12- 2018-01- 2018-01- environnementales MP IDA / 57180 Post Consultant Limited 1,600.00 2,664.12 Completed development support 20 08 25 12 16 16 20 20 04 10 Construction d'1 bloc de Selection deux salles de classe équipées et 1 bloc de latrine à l'EP de Pitoa Kolara et à l'EP de Badadji dans la cne de moulvoudaye CM-CRC EXTREME NORD- 29297-CS-INDV / Sélection d'un consultant pour Etudes de faisabilité des MP de Construction d'un forage Individual Component A: Local 2017-09- 2017-05- 2017-09- 2017-05- 2017-10- 2017-06- 2017-11- 2017-08- 2018-01- 2017-09- PMH à Hourgoum, IDA / 57180 Post Consultant Limited 3,000.00 2,568.97 Completed development support 20 08 25 13 16 18 20 28 04 28 Goumlaye, Kadaye Selection Djamboutou, à Gadja Padjonré et au Lycée de Kolara , EP piotao kaloara et Ep bardadji dans la commune de Moulvoudaye CM-CRC EXTREME NORD- 29299-CS-INDV / Sélection d'un consultant pour Etudes d des MP de Construction d'1 bloc de Individual Component A: Local 2017-09- 2017-05- 2017-09- 2017-06- 2017-10- 2017-06- 2017-11- 2017-07- 2018-01- 2017-09- deux salles de classe et d'1 IDA / 57180 Post Consultant Limited 4,000.00 5,113.88 Completed development support 20 08 25 12 16 16 20 10 04 22 bloc de latrine à l'EP Selection MOUFTOUM , au CES GOURIA, Lycée de SIR, à l'EPB de RHUMZOU , à l'EPB de KWASHIMANDA et équipement tables banc cne de MOZOGO CM-CRC EXTREME NORD- 29300-CS-INDV / Sélection d'un consultant pour l'élaboration des Etudes de faisabilité techniques et Individual Component A: Local 2017-09- 2017-05- 2017-09- 2017-06- 2017-10- 2017-06- 2017-11- 2017-09- 2018-01- 2017-09- environnementales des MP IDA / 57180 Post Consultant Limited 2,000.00 2,534.91 Completed development support 20 08 25 12 16 16 20 07 04 22 de Construction d'un Selection ouvrage d'assainissement et de franchissement sur le Mayo Teki à TEKI commune de MOGODE CM-CRC EXTREME NORD- 29301-CS-INDV / Sélection d'un consultant pour l'élaboration des Etudes de Sélection d'un consultant Individual Component A: Local 2017-09- 2017-05- 2017-09- 2017-06- 2017-10- 2017-06- 2017-11- 2017-07- 2018-01- 2017-09- pour l'élaboration des IDA / 57180 Post Consultant Limited 4,950.00 3,805.88 Completed development support 20 08 25 06 16 16 20 10 04 22 Etudes de faisabilité Selection techniques et environnementales des MP de Construction d'un forage équipé à PMH (8 Forages) da commune de MOGODE CM-CRC EXTREME NORD- 29302-CS-INDV / Sélection d'un consultant pour Elaboration étude des MP de Construction d'1 bloc de Individual Component A: Local 2017-09- 2017-05- 2017-09- 2017-06- 2017-10- 2017-06- 2017-11- 2017-06- 2018-01- 2017-09- deux salles de classe IDA / 57180 Post Consultant Limited 4,000.00 4,894.14 Completed development support 20 08 25 12 16 16 20 16 04 22 équipées et d'1 bloc de Selection latrines à l'EP Souaye Dana, à l'EP Domo Doukou, à l'EP de Riganda, à l'EP Kao-Galak et à l'EP Bilingue Vounsia CNE YAGOUA CM-CRC EXTREME NORD- 29303-CS-INDV / Sélection d'un consultant pourétude des MP de Construction d'un Individual forage equipe de PMH à l'EP Component A: Local 2017-09- 2017-05- 2017-09- 2017-06- 2017-10- 2017-06- 2017-11- 2017-06- 2018-01- 2017-09- IDA / 57180 Post Consultant Limited 3,000.00 4,869.96 Completed Souaye Dana, à l'EP Domo development support 20 08 25 12 16 16 20 18 04 22 Selection Doukou, à l'EP de Riganda, à l'EP Kao-Galak et à l'EP Bi Vounsia dans la commune de Yagoua CM-CRC EXTREME NORD- 38284-CS-INDV / ÉTUDES DE FAISABILITÉ DES MP DE CONSTRUCTION D'UN BLOC DE DEUX SALLES DE CLASSE Individual ÉQUIPÉES À L'EP KOZA I, À Component A: Local 2017-11- 2017-09- 2017-12- 2017-10- 2017-12- 2017-10- 2018-01- 2017-10- 2018-03- 2017-12- IDA / 57180 Post Consultant Limited 6,600.00 2,458.96 Completed L'EP KOZA II, À L'EP development support 26 11 01 02 22 06 26 16 12 04 Selection DAKOTCHERE, À L'EP DE KILDA ET À L'EP DE GABOUA, CONSTRUCTION D'UN BLOC LATRINES A L'EP DE GABOUA, DANS LA COMMUNE DE KOZA CM-CRC EXTREME NORD- 38285-CS-INDV / ETUDES de faisabilité des MP de Individual Construction d'un forage Component A: Local 2017-11- 2017-09- 2017-12- 2017-10- 2017-12- 2017-10- 2018-01- 2017-10- 2018-03- 2017-12- IDA / 57180 Post Consultant Limited 1,000.00 1,134.91 Completed équipé de pompe à development support 27 11 02 02 23 06 27 16 13 04 Selection motricité humaine a l'EP de KILDA dans la commune de KOZA dans la commune de KOZA CM-CRC EXTREME NORD- 38286-CS-INDV / ETUDES de faisabilité des MP d'équipement en tables Individual Component A: Local 2017-11- 2017-09- 2017-12- 2017-10- 2017-12- 2017-10- 2018-01- 2017-10- 2018-03- 2017-12- banc et bureaux ( 60 tables IDA / 57180 Post Consultant Limited 1,800.00 756.60 Completed development support 27 11 02 02 23 06 27 16 13 04 banc + 02 bureaux et 02 Selection Chaises) a l'EP de KOZA I , l'EP de KOZA II, a l'EP de GABOUA, dans la commune de KOZA CM-CRC EXTREME NORD- 38287-CS-INDV / ETUDES de faisabilité des MP de Construction d'un bloc de deux salles de classe Individual équipées et d'un bloc de Component A: Local 2017-11- 2017-09- 2017-12- 2017-10- 2017-12- 2017-10- 2018-01- 2017-10- 2018-03- 2018-03- IDA / 57180 Post Consultant Limited 6,000.00 2,601.01 Completed latrines à trois development support 27 11 02 02 23 06 27 16 13 06 Selection compartiments au CES MAZAYA, à l'EPB de MIDRE, l'EP ZELE SOULEDE, l'EP BAO DALBAI et l'EP DOUMDERE dans la commune de ROUA dans la Page 7 CM-CRC EXTREME NORD- 38288-CS-INDV / ETUDES de faisabilité des MP de Construction d'un forage Individual Component A: Local 2017-11- 2017-09- 2017-12- 2017-10- 2017-12- 2017-10- 2018-01- 2017-12- 2018-03- 2018-03- équipé de pompe à IDA / 57180 Post Consultant Limited 4,000.00 2,811.29 Completed development support 26 11 01 02 22 06 26 20 12 06 motricité humaine à l'EP Selection ZELE SOULEDE, à l'EP BAO DALBAI, au CES MAZAYA et à l'EP DOUMDERE dans la commune de ROUA CM-CRC EXTREME NORD- 38289-CS-INDV / ETUDES de faisabilité des MP de Construction d'un forage Individual Component A: Local 2017-11- 2017-09- 2017-12- 2017-09- 2017-12- 2017-10- 2018-01- 2017-10- 2018-03- équipé de pompe à IDA / 57180 Post Consultant Limited 3,000.00 2,054.80 Signed development support 27 14 02 14 23 06 27 06 13 motricité humaine au CETIC Selection D'OUZAL, l'EP GOKORO et l'EM de MOSKOTA dans la commune MOZOGO CM-CRC EXTREME NORD- 38290-CS-INDV / ETUDES des MP de Construction de deux salles de classe équipées et d'1 bloc latrines Individual Component A: Local 2017-11- 2017-09- 2017-12- 2017-09- 2017-12- 2017-10- 2018-01- 2018-10- 2018-03- au CETIC D'OUZAL, l'EP IDA / 57180 Post Consultant Limited 9,600.00 10,413.78 Signed development support 27 14 02 14 23 06 27 09 13 NGUETCHEWE ,de deux Selection salles de classe équipées à l'EPB MOZOGO, L'EP KORASAMBA, l'EP KARAZAWA l'EP GOKORO et d1 atelier à la SAR/SM et CETIC MOZOGO CM-CRC EXTREME NORD- 38291-CS-INDV / ETUDES de faisabilité des MP de Individual Component A: Local 2017-11- 2017-09- 2017-12- 2017-09- 2017-12- 2017-10- 2018-01- 2017-10- 2018-03- Construction d'un hangar de IDA / 57180 Post Consultant Limited 2,400.00 2,680.17 Signed development support 27 14 02 14 23 06 27 09 13 marché au marché de Selection MAWA MOZOGO et au marche de MOSKOTA CM-CRC EXTREME NORD- 38292-CS-INDV / ETUDES de faisabilité des MP de Individual Component A: Local 2017-11- 2017-09- 2017-12- 2017-09- 2017-12- 2017-10- 2018-01- 2017-10- 2018-03- Construction d'un bloc IDA / 57180 Post Consultant Limited 2,400.00 2,405.98 Signed development support 27 14 02 14 23 06 27 09 13 maternelle équipée à L'EM Selection DE MOSKOTA et d'une cloture a l'EM de MOZOGO CM-CRC EXTREME NORD- 38293-CS-INDV / ETUDES de faisabilité des MP de Construction d'un forage Individual Component A: Local 2017-11- 2017-09- 2017-12- 2017-10- 2017-12- 2017-10- 2018-01- 2017-10- 2018-03- 2018-12- équipé de pompe à IDA / 57180 Post Consultant Limited 4,000.00 1,903.46 Completed development support 27 11 02 02 23 06 27 16 13 20 motricité humaine à Ildin- Selection toungouloun, Wouro Wandou Moufou, Narewa Et Makoumba dans la commune de GAZAWA CM-CRC EXTREME NORD- 38294-CS-INDV / ETUDES de faisabilité des MP de Construction de deux salles de classe équipées et d'un Individual Component A: Local 2017-11- 2017-09- 2017-12- 2017-10- 2017-12- 2017-10- 2018-01- 2017-10- 2018-03- 2017-12- bloc de latrines à l'EP de IDA / 57180 Post Consultant Limited 3,600.00 2,577.87 Completed development support 27 11 02 02 23 06 27 16 13 23 wouyang, à l'EP de GONOZO Selection et construction d'un atelier de maçonnerie et d'un bloc latrine au CETIC de Loulou A NDOUKOULA CM-CRC EXTREME NORD- 38295-CS-INDV / ETUDES de faisabilité des MP de Construction d'un forage Individual équipé de pompe PMH à Component A: Local 2017-11- 2017-09- 2017-12- 2017-10- 2017-12- 2017-10- 2018-01- 2017-10- 2018-03- 2017-12- IDA / 57180 Post Consultant Limited 5,600.00 2,575.26 Completed l'EP de Ouro-Nangué, à l'EP development support 27 11 02 02 23 06 27 16 13 23 Selection MOUDVAR, à l'EP de Gonozo, à Fakalao, à EP Louguéré, à Talandé et à Hodango CMNE NDOUKOULA CM-CRC EXTREME NORD- 38296-CS-INDV / ETUDES de faisabilité des MP d' Individual Component A: Local 2017-11- 2017-09- 2017-12- 2017-10- 2017-12- 2017-10- 2018-01- 2017-10- 2018-03- 2018-11- Extension du réseau IDA / 57180 Post Consultant Limited 6,000.00 4,722.68 Completed development support 27 11 02 02 23 06 27 16 13 17 électrique Loulou- Selection Ndoukoula-Dagaï (22km) COMMUNE NDOUKOULA CM-CRC EXTREME NORD- 38297-CS-INDV / ETUDES de faisabilité des MP de Construction de deux salles de classe équipées et Individual Component A: Local 2017-11- 2017-09- 2017-12- 2017-10- 2017-12- 2017-10- 2018-01- 2017-10- 2018-03- 2017-12- d'un bloc de latrines à l'EP IDA / 57180 Post Consultant Limited 5,400.00 2,161.74 Completed development support 27 11 02 02 23 06 27 16 13 13 de Bihoré, à l'EP de Troké, à Selection l'EP de Goua et à l'EP de Youaye Mbogue et équipement des salles de classe au lycée de TCHATIBALI CM-CRC EXTREME NORD- 38298-CS-INDV / ETUDES de faisabilité des MP de Construction d'un forage Individual équipé de pompe à Component A: Local 2017-11- 2017-09- 2017-12- 2017-10- 2017-12- 2017-10- 2018-01- 2017-10- 2018-03- 2017-12- IDA / 57180 Post Consultant Limited 4,500.00 2,368.41 Completed motricité Humaine à Gané development support 27 11 02 02 23 06 27 16 13 13 Selection (quartier bili), à L'EP de Saouringwa, à Danglao(quartier Bidomo), Kada'a Glonhene, Bindiriel Danghou commune Tchatibali CM-CRC EXTREME NORD- 38299-CS-INDV / ETUDES de faisabilité des MP de Construction d'un bloc de deux salles de classe Individual Component A: Local 2017-11- 2017-09- 2017-12- 2017-10- 2017-12- 2017-10- 2018-01- 2017-10- 2018-03- 2017-12- équipées et d'un bloc de IDA / 57180 Post Consultant Limited 6,000.00 2,593.97 Completed development support 27 11 02 02 23 06 27 11 13 06 latrines à trois Selection compartiments l'EP de Balané, au CES de Sirlawé, l'EP de Rey-foulaye, l'EP de Datchéka-takréo,l'EP de Sadielle COMMUNE DE KARHAY. CM-CRC EXTREME NORD- 38300-CS-INDV / ETUDES de faisabilité des MP de Construction d'un forage équipé de pompe à Individual Component A: Local 2017-11- 2017-09- 2017-12- 2017-10- 2017-12- 2017-10- 2018-01- 2017-10- 2018-03- 2017-12- motricité Humaine à l'EP de IDA / 57180 Post Consultant Limited 5,600.00 2,577.87 Completed development support 27 11 02 02 23 06 27 16 13 06 Balané, à l'école des parents Selection de Gouloulou, à l'EP de Rey- foulaye, à l'EP de Sadielle, à l'EP de Damdama, au CES de Sirlawé, au CSI de Doukoula 1 CM-CRC EXTREME NORD- 38301-CS-INDV / ETUDES de faisabilité des MP de Construction d'un Centre de Individual Component A: Local 2017-11- 2017-09- 2017-12- 2017-09- 2017-12- 2017-10- 2018-01- 2017-10- 2018-03- 2017-12- Santé intégré équipé, un IDA / 57180 Post Consultant Limited 2,800.00 2,828.45 Completed development support 27 11 02 28 23 06 27 16 13 06 incinérateur, et un bloc de Selection latrines au Centre de Santé Intégré de Doukoula 1 commune KARHAY CM-CRC EXTREME NORD- 38302-CS-INDV / ETUDES de faisabilité des MP de Construction de deux salles de classe équipées et d'un  Individual Component A: Local 2017-11- 2017-09- 2017-12- 2017-10- 2017-12- 2017-10- 2018-01- 2017-10- 2018-03- bloc latrines au Lycée tech IDA / 57180 Post Consultant Limited 6,000.00 3,045.09 Signed development support 27 11 02 02 23 06 27 09 13 de Gobo, l' EP GUIRIOU Selection CENTRE, Lycée de DOM PYA, la SAR/ SM Gobo, et la construction d'un bloc latrines au marché de GOBO et de NOULD CM-CRC EXTREME NORD- 38303-CS-INDV / ETUDES de faisabilité des MP de construction d'un forage pastoral équipé de pompe à Individual énergie photovoltaïque à Component A: Local 2017-11- 2017-09- 2017-12- 2017-10- 2017-12- 2017-10- 2018-01- 2017-10- 2018-03- IDA / 57180 Post Consultant Limited 4,000.00 3,026.19 Signed GALAM BASSA et la development support 27 11 02 02 23 06 27 09 13 Selection construction d'un forage équipé de PMH au CES de POLGUE, à l'EP GUIRIOU CENTRE et à la SAR/ SM de Gobo CM-CRC EXTREME NORD- 38304-CS-INDV / ETUDES de faisabilité des MP de Construction d'un  bloc de deux salles de classe Individual équipées et construction Component A: Local 2017-11- 2017-09- 2017-12- 2017-10- 2017-12- 2017-10- 2018-01- 2017-10- 2018-03- 2017-12- IDA / 57180 Post Consultant Limited 4,800.00 2,819.53 Completed d'un  bloc latrine à trois development support 27 11 02 02 23 06 27 09 13 14 Selection compartiment au CES de Doukroye, au CETIC de Doreissou, à l'EP de Dama - Djougong et à l'EP de DJOWELNANDJI communeKAIKAI CM-CRC EXTREME NORD- 38305-CS-INDV / ETUDES de faisabilité des MP de Construction d'un forage équipé de PMH au CETIC de Individual Component A: Local 2017-11- 2017-09- 2017-12- 2017-10- 2017-12- 2017-10- 2018-01- 2017-10- 2018-03- 2017-12- Doressou, a l'EP de Daram - IDA / 57180 Post Consultant Limited 5,400.00 2,819.53 Completed development support 27 11 02 02 23 06 27 09 13 14 Djougong, à l' EP de Daloa Selection (Doukroye), au Lycée de Bégué Palam, au Lycée de Daram-Doreissou centre, à l'EP de Memié COMMUNE DE KAI-KAI CM-CRC EXTREME NORD- 38306-CS-INDV / ETUDES de faisabilité des MP de Construction d'un  bloc de deux salles de classe Individual équipées et de construction Component A: Local 2017-11- 2017-09- 2017-12- 2017-10- 2017-12- 2017-10- 2018-01- 2017-10- 2018-03- 2017-11- IDA / 57180 Post Consultant Limited 8,000.00 4,728.78 Completed d'un  bloc de latrines à trois development support 27 11 02 02 23 06 27 16 13 30 Selection compartiments à l'EP de Doumrou, à l'EP Mizao, à l'EP de Bipaing, a l' EP de Goudjouing, au lycée de Mindjil, à E CM-CRC EXTREME NORD- 38307-CS-INDV / ETUDES de faisabilité des MP de Construction d'un forage équipé de PMH à Bibalé - Individual Gambour, à Goubara, à Component A: Local 2017-11- 2017-09- 2017-12- 2017-10- 2017-12- 2017-10- 2018-01- 2017-10- 2018-03- 2017-11- IDA / 57180 Post Consultant Limited 5,400.00 4,699.43 Completed Kourong, à Kassilé. Et development support 27 11 02 02 23 06 27 16 13 30 Selection l'actualisationdes microprojets de réhabilitation de la mare de Garey Kaélé et la construction d'un forage pastoral à énergie so CM-CRC EXTREME NORD- 38308-CS-INDV / ETUDES de faisabilité des MP de Construction d'un  bloc de deux salles de classe Individual Component A: Local 2017-11- 2017-09- 2017-12- 2017-10- 2017-12- 2017-10- 2018-01- 2017-10- 2018-03- 2017-12- équipées à EP Dourdoum, IDA / 57180 Post Consultant Limited 3,000.00 2,689.95 Completed development support 27 11 02 02 23 06 27 18 13 15 à EP Kalaf, à EP Mayel - Selection Guinadji et Construction d'un  bloc latrine à trois compartiment à EP Mayel - Guinadji COMMUNE DE Moutourwa CM-CRC EXTREME NORD- 38309-CS-INDV / ETUDES de faisabilité du MP de Individual Construction d'un forage Component A: Local 2017-11- 2017-09- 2017-12- 2017-10- 2017-12- 2017-10- 2018-01- 2017-10- 2018-03- 2017-12- IDA / 57180 Post Consultant Limited 1,000.00 2,086.45 Completed équipé de PMH À development support 27 11 02 02 23 06 27 17 13 15 Selection GANAHA,EP DOURDOUM, À EP KALAF, À EP MAYEL - GUINADJI COMMUNE DE Moutourwa CM-CRC EXTREME NORD- 38310-CS-INDV / ETUDES de faisabilité du MP Individual Component A: Local 2017-11- 2017-09- 2017-12- 2017-10- 2017-12- 2017-10- 2018-01- 2017-10- 2018-03- d'électrification en énergie IDA / 57180 Post Consultant Limited 3,600.00 1,879.77 Signed development support 27 11 02 02 23 06 27 16 13 solaire de la localité de Selection Magada carrefour COMMUNE DE Moutourwa CM-CRC EXTREME NORD- 38311-CS-INDV / ETUDES de faisabilité des MP de Construction d'un bloc de deux salles de classe Individual Component A: Local 2017-11- 2017-09- 2017-12- 2017-09- 2017-12- 2017-10- 2018-01- 2017-12- 2018-03- 2017-12- équipées à l'EP de IDA / 57180 Post Consultant Limited 6,000.00 4,905.06 Completed development support 27 14 02 14 23 25 27 05 13 09 Gouvaka, à l'EP de Majé, à Selection l'EP de Malika et construction de 01 magasin de stockage à Oignon à Sera -Idoumda et à Kourgui COMMUNE DE MORA CM-CRC EXTREME NORD- 38312-CS-INDV / ETUDES de faisabilité des MP de Individual Component A: Local 2017-11- 2017-09- 2017-12- 2017-09- 2017-12- 2017-12- 2018-01- 2017-12- 2018-03- 2017-12- Construction d'un forage IDA / 57180 Post Consultant Limited 2,000.00 2,633.18 Completed development support 27 14 02 14 23 05 27 05 13 09 équipé de pompe à Selection motricité Humaine à Koulang, à Mangavé COMMUNE DE MORA CM-CRC EXTREME NORD- 38313-CS-INDV / ETUDES de faisabilité des MP de Construction d'un forage Individual Component A: Local 2017-11- 2017-09- 2017-12- 2017-09- 2017-12- 2017-10- 2018-01- 2017-10- 2018-03- 2017-12- équipé de pompe à IDA / 57180 Post Consultant Limited 3,000.00 1,962.54 Completed development support 27 14 02 28 23 06 27 16 13 19 motricité humaine dans les Selection localités de WOLORDE- TCABAWOL, BAKA FOURWA ET DJALTAR dans la commune de TOKOMBERE CM-CRC EXTREME NORD- 38314-CS-INDV / ETUDES de faisabilité des MP de Construction d'un bloc de Individual Component A: Local 2017-11- 2017-09- 2017-12- 2017-10- 2017-12- 2017-10- 2018-01- 2017-10- 2018-03- 2017-12- deux salles de classe IDA / 57180 Post Consultant Limited 3,200.00 2,689.95 Completed development support 27 11 02 02 23 06 27 06 13 19 équipées à l'EP DE Selection TSABATSABA,L'EP CHEOULEW, l'EP TAZANG ET AU CES DE MAKALINGAI dans la commune de TOKOMBERE CM-CRC EXTREME NORD- 38315-CS-INDV / ETUDES de faisabilité des MP de Construction d'un bloc de deux salles de classe Individual Component A: Local 2017-11- 2017-09- 2017-12- 2017-09- 2017-12- 2017-10- 2018-01- 2017-10- 2018-03- 2017-12- équipées à l'EP DE GANCE, IDA / 57180 Post Consultant Limited 3,000.00 3,961.78 Completed development support 27 14 02 14 23 25 27 25 13 14 AU CES DE TOLKOMARI et Selection Construction d'un bloc de latrines a trois compartiments au CES de TOLKOMARI, commune de KOLOFATA CM-CRC EXTREME NORD- 38316-CS-INDV / ETUDES de faisabilité du MP de Construction d'un forage pastoral équipé de pompe à Individual énergie solaire avec Component A: Local 2017-11- 2017-09- 2017-12- 2017-09- 2017-12- 2017-10- 2018-01- 2017-10- 2018-03- 2017-12- IDA / 57180 Post Consultant Limited 2,800.00 3,961.78 Completed réservoir et abreuvoirs à development support 27 14 02 14 23 25 27 25 13 14 Selection Kolofata-Guidi et Construction d'un forage équipé de pompe à motricité humaine au CES de TOLKOMARI dans la commune de KOLO CM-CRC EXTREME NORD- 38317-CS-INDV / ETUDES DE FAISABILITE DU MP CONSTRUCTION D'UN BLOC Individual DE DEUX SALLES DE CLASSE Component A: Local 2017-11- 2017-11- 2017-12- 2017-11- 2017-12- 2017-11- 2018-01- 2017-11- 2018-03- 2018-03- IDA / 57180 Post Consultant Limited 1,650.00 1,505.22 Completed EQUIPE ET D'UN BLOC DE development support 27 06 02 06 23 17 27 20 13 22 Selection LATRINES A TROIS COMPARTIMENTS A L'EP KOUTOULA COMMUNE DE BLANGOUA CM-CRC EXTREME NORD- 38318-CS-INDV / ETUDES Individual DE FAISABILITE DU MP Component A: Local 2017-11- 2017-11- 2017-12- 2017-11- 2017-12- 2017-11- 2018-01- 2017-11- 2018-03- 2018-03- IDA / 57180 Post Consultant Limited 2,700.00 2,409.68 Completed CONSTRUCTION D'UNE development support 27 06 02 06 23 17 27 20 13 22 Selection GARE ROUTIERE AVEC BLOC LATRINES A BLANGOUA CM-CRC EXTREME NORD- 38319-CS-INDV / ELABORATION DES ETUDES Individual DE FAISABILITE DU MP DE Component A: Local 2017-11- 2017-11- 2017-12- 2017-11- 2017-12- 2017-11- 2018-01- 2017-11- 2018-03- 2018-03- IDA / 57180 Post Consultant Limited 2,000.00 1,880.84 Completed CONSTRUCTION D'UN development support 27 06 02 06 23 17 27 17 13 25 Selection FORAGE EQUIPE DE PMH A ABINKRO ET A KOUTALA DANS LA COMMUNE DE BLANGOUA CM-CRC EXTREME NORD- 38320-CS-INDV / ETUDES DE FAISABILITE DU MP D Individual CONSTRUCTION D'UN Component A: Local 2017-11- 2017-11- 2017-12- 2017-11- 2017-12- 2017-11- 2018-01- 2017-11- 2018-03- 2018-03- IDA / 57180 Post Consultant Limited 2,700.00 2,539.13 Completed FORAGE PASTORAL A development support 27 06 02 06 23 17 27 17 13 21 Selection ENERGIE SOLAIRE A MAGALAKABIR, A KARENA ET A NAGA COMMUNE DE DARAK CM-CRC EXTREME NORD- 38321-CS-INDV / ETUDES DE FAISABILITE DU MP DE CONSTRUCTION D'UN BLOC Individual DE DEUX SALLES DE CLASSE Component A: Local 2017-11- 2017-11- 2017-12- 2017-11- 2017-12- 2017-11- 2018-01- 2017-11- 2018-03- 2018-03- IDA / 57180 Post Consultant Limited 1,650.00 1,472.58 Completed EQUIPE ET D'UN BLOC DE development support 27 06 02 06 23 17 27 20 13 23 Selection LATRINES A TROIS COMPARTIMENTS A L'EP HILELLE COMMUNE DE GOULFEY Page 8 CM-CRC EXTREME NORD- 38322-CS-INDV / ETUDES DE FAISABILITE DU MP DE Individual Component A: Local 2017-11- 2017-11- 2017-12- 2017-11- 2017-12- 2017-11- 2018-01- 2017-11- 2018-03- 2018-03- CONSTRUCTION D'UN IDA / 57180 Post Consultant Limited 1,170.00 1,099.00 Completed development support 27 06 02 06 23 17 27 20 13 23 HANGAR AU MARCHE DE Selection GOULFEY GANA COMMUNE DE GOULFEY CM-CRC EXTREME NORD- 38323-CS-INDV / ETUDES DE FAISABILITE DU MP DE Individual Component A: Local 2017-11- 2017-11- 2017-12- 2017-11- 2017-12- 2017-11- 2018-01- 2017-11- 2018-03- 2018-03- CONSTRUCTION D'UN IDA / 57180 Post Consultant Limited 1,140.00 1,017.42 Completed development support 27 06 02 06 23 17 27 20 13 23 MAGASIN DE STOCKAGE A Selection GOULFEY COMMUNE DE GOULFEY CM-CRC EXTREME NORD- 38324-CS-INDV / ETUDES DE FAISABILITE DU MP DE Individual Component A: Local 2017-11- 2017-11- 2017-12- 2017-11- 2017-12- 2017-11- 2018-01- 2017-11- 2018-03- 2018-03- CONSTRUCTION D'UNE IDA / 57180 Post Consultant Limited 2,700.00 2,409.68 Completed development support 27 06 02 14 23 17 27 20 13 23 GARE ROUTIERE AVEC BLOC Selection LATRINES A GOULFEY COMMUNE DE GOULFEY CM-CRC EXTREME NORD- 38325-CS-INDV / ETUDES DE FAISABILITE DU MP DE CONSTRUCTION D'UN FORAGE PASTORAL A Individual ENERGIE SOLAIRE A Component A: Local 2017-11- 2017-11- 2017-12- 2017-11- 2017-12- 2017-11- 2018-01- 2017-11- 2018-03- 2018-03- IDA / 57180 Post Consultant Limited 4,000.00 3,761.68 Completed DJAGALAT, A AKMASSIRAK development support 27 06 02 06 23 17 27 17 13 23 Selection ET DE LA CONSTRUCTION D'UN FORAGE EQUIPES DEPMH A MOUGALAM, A LA GARE ROUTIERE DE GOULFEY, A TAWOULWEBE ET A L'EP HILELE COMMUNE DE GOULFEY CM-CRC EXTREME NORD- 38326-CS-INDV / ETUDES DE FAISABILITE DU MP DE CONSTRUCTION D'UN CENTRE DE SANTE INTEGRE Individual Component A: Local 2017-11- 2017-11- 2017-12- 2017-11- 2017-12- 2017-11- 2018-01- 2017-11- 2018-03- 2018-03- EQUIPE, AVEC BLOC DE IDA / 57180 Post Consultant Limited 4,500.00 4,016.14 Completed development support 27 06 02 14 23 17 27 20 13 23 LATRINES ET UN Selection INCINERATEUR A HILE HAOUSSA COMMUNE DE HILE ALIFA " CM-CRC EXTREME NORD- 38327-CS-INDV / ETUDES DE FAISABILITE DU MP DE CONSTRUCTION D'UN BLOC Individual DE DEUX SALLES DE CLASSE Component A: Local 2017-11- 2017-11- 2017-12- 2017-11- 2017-12- 2017-11- 2018-01- 2017-11- 2018-03- 2018-03- IDA / 57180 Post Consultant Limited 1,650.00 1,472.58 Completed EQUIPE ET D'UN BLOC DE development support 27 06 02 14 23 17 27 20 13 23 Selection LATRINES A TROIS COMPARTIMENTS AU CES D'ADJAÏNE COMMUNE DE HILE ALIFA CM-CRC EXTREME NORD- 38328-CS-INDV / TUDE DES MICROPROJETS DE CONSTRUCTION D'UN FORAGE PASTORAL A Individual ENERGIE SOLAIRE A LACTA Component A: Local 2017-11- 2017-11- 2017-12- 2017-11- 2017-12- 2017-11- 2018-01- 2017-11- 2018-03- 2018-03- IDA / 57180 Post Consultant Limited 2,800.00 2,633.18 Completed 1, MASSAKI ET development support 27 06 02 06 23 17 27 17 13 23 Selection CONSTRUCTION D'UN FORGAE EQUIPE DE POMPE A MOTRICITE HUMAINE AU CES D'ADJAINE ET AU CSI DE HILE HAOUSSA COMMUNE DE HILE ALIFA CM-CRC EXTREME NORD- 38329-CS-INDV / ETUDES DE FAISABILITE DU MP DE CONSTRUCTION DE QUATRE FORAGES EQUIPES DE POMPE Individual Component A: Local 2017-11- 2017-11- 2017-12- 2017-11- 2017-12- 2017-11- 2018-01- 2017-11- 2018-03- 2018-03- A MOTRICITE HUMAINE AU IDA / 57180 Post Consultant Limited 2,800.00 2,554.31 Completed development support 27 06 02 06 23 17 27 17 13 22 MARCHE A BETAIL DE Selection MADA, A MASSIO- GOURGOURA, A NAGA NDIGUINI, A EP MALTAM COMMMUNE DE MAKARY CM-CRC EXTREME NORD- 38330-CS-INDV / ETUDES DE FAISABILITE DU MP DE Individual CONSTRUCTION D'UNE Component A: Local 2017-11- 2017-11- 2017-12- 2017-11- 2017-12- 2017-11- 2018-01- 2017-11- 2018-03- 2018-03- IDA / 57180 Post Consultant Limited 1,500.00 1,338.71 Completed CLOTURE ET D'UN BLOC DE development support 27 06 02 14 23 17 27 20 13 22 Selection LATRINES AU MARCHE A BETAIL DE MADA COMMMUNE DE MAKARY CM-CRC EXTREME NORD- 38331-CS-INDV / ETUDES DE FAISABILITE DU MP DE Individual Component A: Local 2017-11- 2017-11- 2017-12- 2017-11- 2017-12- 2017-11- 2018-01- 2017-11- 2018-03- 2018-03- CONSTRUCTION D'UN IDA / 57180 Post Consultant Limited 1,170.00 1,044.20 Completed development support 27 06 02 06 23 17 27 20 13 22 HANGAR AVEC BLOC Selection LATRINE AU MARCHE DE BIAMO, COMMMUNE DE MAKARY CM-CRC EXTREME NORD- 38332-CS-INDV / ETUDES DE FAISABILITE DU MP DE CONSTRUCTION D'UN BLOC Individual DE DEUX SALLES DE CLASSE Component A: Local 2017-11- 2017-11- 2017-12- 2017-11- 2017-12- 2017-11- 2018-01- 2017-11- 2018-03- 2018-03- IDA / 57180 Post Consultant Limited 1,650.00 1,505.22 Completed EQUIPE ET D'UN BLOC DE development support 27 06 02 06 23 17 27 20 13 23 Selection LATRINES A TROIS COMPARTIMENTS A L'EP DE MALTAM COMMMUNE DE MAKARY CM-CRC EXTREME NORD- 38333-CS-INDV / ETUDES DE FAISABILITE DU MP DE CONSTRUCTION D'UN BLOC Individual DE DEUX SALLES DE CLASSE Component A: Local 2017-11- 2017-11- 2017-12- 2017-11- 2017-12- 2017-11- 2018-01- 2017-11- 2018-03- 2018-03- IDA / 57180 Post Consultant Limited 1,650.00 1,472.58 Completed EQUIPE ET D'UN BLOC DE development support 27 06 02 14 23 17 27 20 13 25 Selection LATRINES A TROIS COMPARTIMENTS A L'EP GONONI COMMUNE DE HILE ALIFA CM-CRC EXTREME NORD- 38334-CS-INDV / ETUDES DE FAISABILITE DU MP DE CONSTRUCTION D'UN FORAGE PASTORAL A Individual ENERGIE SOLAIRE A Component A: Local 2017-11- 2017-11- 2017-12- 2017-11- 2017-12- 2017-11- 2018-01- 2017-11- 2018-03- 2018-03- IDA / 57180 Post Consultant Limited 5,700.00 5,360.39 Completed ABASSOUNI, A HILE ALIFA 1, development support 27 06 02 06 23 17 27 17 13 25 Selection A FADJA, A DOLE BADA ET CONSTRUCTION D'UN FORAGE EQUIPE DE PMH A MAFOULSO III, A FAMARE ET A L'EP DE GONONI COMMUNE DE HILE ALIFA CM-CRC EXTREME NORD- 38335-CS-INDV / ETUDES DE FAISABILITE DES MP D'INSTALLATION Individual D'ECLAIRAGE PUBLIC (10 Component A: Local 2017-11- 2017-11- 2017-12- 2017-11- 2017-12- 2017-11- 2018-01- 2017-11- 2018-03- 2018-03- IDA / 57180 Post Consultant Limited 1,600.00 1,504.67 Completed KITS)AVEC ENERGIE SOLAIRE development support 27 06 02 06 23 17 27 17 13 25 Selection DE L'AXE MAIRIE DE HILE ALIFA-BRIGADE DE GENDARMERIE DE HILE COMMUNE DE HILE ALIFA CM-CRC EXTREME NORD- 38336-CS-INDV / Suivi/contrôle de la Construction de deux salles de classe équipées avec Individual latrines à l'EP Mouftoum et Component A: Local 2017-11- 2018-02- 2017-12- 2018-02- 2017-12- 2018-03- 2018-01- 2018-04- 2018-05- IDA / 57180 Post Consultant Limited 9,483.00 7,714.59 Signed à l'EPB Rhoumzou, au lycée development support 27 05 02 28 23 06 27 10 27 Selection SIR et à l'EPB Kwashimalda, Et CES Goura et Equipment au CETIC Mogodé, à l'EP SIR, à l'EPB Rhoumsiki et à l'EP Tchanawa CM-CRC EXTREME NORD- 38337-CS-INDV / Suivi/contrôle des Travaux Individual Component A: Local 2017-11- 2018-02- 2017-12- 2018-02- 2017-12- 2018-04- 2018-01- 2018-04- 2018-04- construction d'un radier de IDA / 57180 Post Consultant Limited 13,819.00 1,115.61 Signed development support 27 05 02 28 23 06 27 10 27 12 ml sur le mayo Teki Selection dans la localité de Teki, Commune de Mogode CM-CRC EXTREME NORD- 38338-CS-INDV / Suivi/contrôle des Travaux de construction d'un bloc de deux salles équipées et un Individual Component A: Local 2017-11- 2018-02- 2017-12- 2018-03- 2017-12- 2018-04- 2018-01- 2018-04- 2018-04- bloc de latrines à l'EP de IDA / 57180 Post Consultant Limited 9,345.00 6,782.81 Signed development support 27 05 02 07 23 06 27 10 27 Ldamang et à l'EP de Ndrock Selection Tourou, à l'EP de Moufou- sud et à l'EP de Zili Yolel et au CES de Mandaka COMMUNE DE MOKOLO CM-CRC EXTREME NORD- 38339-CS-INDV / Suivi/contrôle des Travaux Construction de 01 forage équipé dePMH à EM de Individual Ldamtsai, Mandaka Component A: Local 2017-11- 2018-02- 2017-12- 2018-02- 2017-12- 2018-04- 2018-01- 2018-04- 2018-05- IDA / 57180 Post Consultant Limited 5,339.00 2,320.44 Signed Mpoldok, Camp mission de development support 27 05 02 28 23 06 27 10 27 Selection Tourou, Koudougour II Loctcha, Katamsa Sikia, Gouldoum Moufou, Houdango Dandi et Ouro Bocki(2lots) COMMUNE DE MOKOLO CM-CRC EXTREME NORD- 38341-CS-INDV / Suivi/contrôle des Travaux de construction d'un forage Individual Component A: Local 2017-11- 2018-02- 2017-12- 2018-03- 2017-12- 2018-04- 2018-01- 2018-04- 2018-04- équipé de PMH dans les IDA / 57180 Post Consultant Limited 3,477.00 2,737.83 Signed development support 27 05 02 02 23 04 27 06 27 localités de Gadjawai, Selection Guivel, Quartier Méri centre, Nguissar et Kilwo-Valta (Lot 2) COMMUNE DE MERI CM-CRC EXTREME NORD- 38343-CS-INDV / Suivi/contrôle des Travaux Individual Construction d'un bloc de Component A: Local 2017-11- 2018-02- 2017-12- 2018-03- 2017-12- 2018-04- 2018-01- 2018-04- 2018-04- IDA / 57180 Post Consultant Limited 2,047.00 1,429.35 Signed deux salles de classe development support 27 05 02 07 23 04 27 06 27 Selection équipées et un bloc de latrines au C.E.S de Manguirdla commune de MERI CM-CRC EXTREME NORD- 38344-CS-INDV / Suivi/contrôle des Travaux Individual de construction d'un bloc de Component A: Local 2017-11- 2018-02- 2017-12- 2018-03- 2017-12- 2018-04- 2018-01- 2018-04- 2018-04- IDA / 57180 Post Consultant Limited 3,827.00 2,945.17 Signed deux salles de classe development support 27 05 02 07 23 05 27 10 27 Selection équipées avec latrines à l'EP de Domo Doukou et à l'EP de Riganda commune de yagoua CM-CRC EXTREME NORD- 38345-CS-INDV / Individual Suivi/contrôle des Travaux Component A: Local 2017-11- 2018-02- 2017-12- 2018-03- 2017-12- 2018-04- 2018-01- 2018-04- 2018-03- IDA / 57180 Post Consultant Limited 623.00 526.56 Signed de construction d' un forage development support 27 05 02 07 23 05 27 10 28 Selection équipé de PMH à l'EP de Riganda de yagoua CM-CRC EXTREME NORD- 38346-CS-INDV / Suivi/contrôle des Travaux construction d'un forage Individual Component A: Local 2017-11- 2018-02- 2017-12- 2018-02- 2017-12- 2018-04- 2018-01- 2018-04- 2018-04- équipé de PMH à l'EP de IDA / 57180 Post Consultant Limited 2,895.00 2,945.17 Signed development support 27 05 02 08 23 05 27 10 27 Badadji, à l'EP de Pitoa- Selection Kolara, au lycée de Kolara et à Gadjia Padjonré commune de moulvoudaye CM-CRC EXTREME NORD- 38347-CS-INDV / Suivi/contrôle des Travaux Individual construction d'un bloc de Component A: Local 2017-11- 2018-02- 2017-12- 2018-02- 2017-12- 2018-04- 2018-01- 2018-04- 2018-04- IDA / 57180 Post Consultant Limited 3,973.00 2,945.17 Signed deux salles de classe development support 27 05 02 28 23 05 27 10 27 Selection équipées et un bloc de latrines à l'EP de Pitoa- Kolara et à l'EP de Badadji CM-CRC EXTREME NORD- 38348-CS-INDV / Suivi/contrôle des Travaux Individual de construction d'un bloc de Component A: Local 2017-11- 2018-02- 2017-12- 2018-02- 2017-12- 2018-04- 2018-01- 2018-04- 2018-04- IDA / 57180 Post Consultant Limited 3,655.00 3,010.44 Signed deux salles équipées et un development support 27 05 02 28 23 04 27 06 27 Selection bloc de latrines à l'EP de Djagalaye et au CES de Hardé commune de Maroua I CM-CRC EXTREME NORD- 38349-CS-INDV / Suivi/contrôle des Travaux Individual construction d'un forage Component A: Local 2017-11- 2018-02- 2017-12- 2018-02- 2017-12- 2018-04- 2018-01- 2018-04- 2018-04- IDA / 57180 Post Consultant Limited 1,946.00 1,350.14 Signed équipé de PMH à l'EP de development support 27 05 02 28 23 04 27 06 27 Selection Yamdjidjing, à l'EP de Djagalaye et à Zébé commune de MAROUA I CM-CRC EXTREME NORD- 38350-CS-INDV / Suivi/contrôle de Travaux de construction d'un bloc de Individual deux salles équipées et un Component A: Local 2017-11- 2018-03- 2017-12- 2018-03- 2017-12- 2018-04- 2018-01- 2018-04- 2018-04- 2019-08- IDA / 57180 Post Consultant Limited 3,574.00 2,976.37 Completed bloc de latrines CES de development support 27 14 02 21 23 04 27 06 27 08 Selection Balda et Construction d'un bloc de deux salles de classe équipées à l'EP de Sedek Ouro-Gabdo commune de BOGO CM-CRC EXTREME NORD- 38351-CS-INDV / Suivi/contrôle de Travaux de Construction d'un forage équipé de pompe à Individual Component A: Local 2017-11- 2018-02- 2017-12- 2018-02- 2017-12- 2018-04- 2018-01- 2018-04- 2018-05- motricité humaine à l'EP de IDA / 57180 Post Consultant Limited 3,786.00 2,477.61 Signed development support 27 05 02 28 23 04 27 12 27 Sedek Ouro Gabdo à Ardo Selection Foulbé Tankirou à Gagnéri Kourdaya à Guinlaye Guizigaré et Guinlaye Moufouré dans la commune BOGO CM-CRC EXTREME NORD- 58686-CS-INDV / Sélection d'un consultant pour etudes de faisabilité DU Individual Component A: Local 2017-11- 2017-11- 2018-01- 2017-12- 2018-02- 2018-12- 2018-03- 2018-02- 2018-04- MICROPROJET DES TRAVAUX IDA / 57180 Post Consultant Open 3,000.00 2,587.10 Signed development support 27 27 15 14 05 21 12 21 26 DE REHABILILATION DU Selection TRONCON HOTEL LE SAHEL- MAYO-KALIAO (0,7 KM) cmne DE MAROUA Ier CM-CRC EXTREME NORD- 58621-CS-INDV / Sélection d'un consultant pour etudes Individual de faisabilité des MP de Component A: Local 2017-11- 2017-11- 2018-01- 2018-01- 2018-02- 2018-02- 2018-03- 2018-11- 2018-04- IDA / 57180 Post Consultant Open 3,000.00 2,648.73 Signed REHABILILATION DE LA development support 27 28 15 25 05 01 12 19 26 Selection PISTE SOUKOUDJO- BAGRISSE-FARARE (28 KM) dans la cmne de Pette. CM-CRC EXTREME NORD- 58856-CS-INDV / Sélection d'un consultant pour lEtudes de faisabilité des MP de Individual Construction de 01 Component A: Local 2018-05- 2018-05- 2018-07- 2018-06- 2018-08- 2018-07- 2018-09- 2018-07- 2018-10- 2018-12- IDA / 57180 Post Consultant Open 2,200.00 1,902.66 Completed batiment abritant le bloc development support 27 08 15 22 05 02 09 16 24 20 Selection opératoire, la salle d'échographie au CMA avec clôture et un bloc de latrine au CMA de Gazawa dans la cmne de Gazawa. CM-CRC EXTREME NORD- 58511-CS-INDV / Sélection d'un consultant pour etudes de faisabilité des MP de Individual Component A: Local 2018-05- 2018-05- 2018-07- 2018-06- 2018-08- 2018-07- 2018-09- 2018-07- 2018-10- 2018-07- construction de 01 forage à IDA / 57180 Post Consultant Open 3,000.00 2,596.59 Completed development support 27 08 15 22 05 02 09 06 24 20 PMH à Yoldé-Naggué à Selection Hodema à Tchakamadjé à Yaga -Djibiwo à Bakourehi cmne de Pette. CM-CRC EXTREME NORD- 58487-CS-INDV / Sélection d'un consultant pour etudes de faisabilité des MP de Individual Component A: Local 2018-05- 2018-05- 2018-07- 2018-06- 2018-08- 2018-07- 2018-09- 2018-07- 2018-10- construction de 01 forage à IDA / 57180 Post Consultant Open 2,400.00 2,089.44 Signed development support 27 08 15 22 05 02 09 09 24 PMH au CES de Guinadji à Selection DJARELOL ALIOUM et un forage solaire au CSI de Djiddéo cmne de MAROUA III. CM-CRC EXTREME NORD- 58620-CS-INDV / Sélection d'un consultant pour etudes Individual Component A: Local 2018-05- 2018-05- 2018-07- 2018-06- 2018-08- 2018-07- 2018-09- 2018-07- 2018-10- de faisabilité des MP de IDA / 57180 Post Consultant Open 1,000.00 3,935.36 Signed development support 27 08 15 15 05 02 09 06 24 Contruction d'un bloc de 2 Selection salles de classe au CES GOBIO dans la cmne de Kalfou. CM-CRC EXTREME NORD- 58492-CS-INDV / Sélection d'un consultant pour etudes de faisabilité des MP de construct d'un forage à PMH Individual Component A: Local 2018-05- 2018-05- 2018-07- 2018-08- 2018-07- 2018-09- 2018-07- 2018-10- 2018-12- à Meskina Tifouli à Djabéwal IDA / 57180 Post Consultant Open 4,600.00 3,940.34 Completed development support 27 08 15 05 02 09 06 24 27 à Gandou Guinane au CES Selection de Zaria à Delta Guibéré et Rehabilitation d'un forage à Djada à Mandara dans la cmne de Kalfou. Page 9 CM-CRC EXTREME NORD- 58568-CS-INDV / Sélection d'un consultant pour etudes de faisabilité des MP de Individual Component A: Local 2018-05- 2018-05- 2018-07- 2018-06- 2018-08- 2018-07- 2018-09- 2018-07- 2018-10- 2018-11- Construction de 01 forage IDA / 57180 Post Consultant Open 2,400.00 2,439.92 Completed development support 27 02 15 22 05 02 09 06 24 30 equipé de PMH au CETIC de Selection Tchévi à ZEU à ZOUVOU - YOLDE à DOUVA cmne DE BOURHA(04 MP) CM-CRC EXTREME NORD- 58678-CS-INDV / Sélection d'un consultant pour etudes de faisabilité des MP de Rehabilitation de la route Individual Component A: Local 2018-05- 2018-05- 2018-07- 2018-06- 2018-08- 2018-07- 2018-09- 2018-07- 2018-10- 2018-11- Guili-ZEU, construction des IDA / 57180 Post Consultant Open 4,000.00 3,148.29 Completed development support 27 08 15 15 05 02 09 06 24 30 caniveaux à Bourha (axe Selection Hamadou -ZRA-Bello Hayatou) et Construction des caniveaux à Boukoula face commissariat cmne de Bourha. CM-CRC EXTREME NORD- 58538-CS-INDV / Sélection d'un consultant pour etudes de faisabilité des MP de Individual Component A: Local 2018-05- 2018-05- 2018-07- 2018-05- 2018-08- 2018-07- 2018-09- 2018-07- 2018-10- 2018-11- construction d'un bloc de 02 IDA / 57180 Post Consultant Open 1,300.00 1,136.88 Completed development support 27 02 15 24 05 02 09 06 24 30 salles de classe équipées et Selection d'un bloc de latrines à trois compartiments au CETIC de Tchevi cmne de Bourha. CM-CRC EXTREME NORD- 58385-CS-INDV / Sélection d'un consultant pour etudes de faisabilité des MP de Individual construct bloc de 02 SC Component A: Local 2018-05- 2018-05- 2018-07- 2018-06- 2018-08- 2018-07- 2018-09- 2018-07- 2018-10- 2018-11- IDA / 57180 Post Consultant Open 4,750.00 3,128.80 Completed equipés et d'un bloc de development support 27 08 15 15 05 02 09 04 24 09 Selection latrines à EP KAOSSERE à EP LIOUDE à L'EP B de TOULOUM à L'EP TCHOURA BIZILI à EP SAOTSAI cmne de TOULOUM CM-CRC EXTREME NORD- 58328-CS-INDV / Sélection d'un consultant pour etudes Individual Component A: Local 2018-05- 2018-05- 2018-07- 2018-06- 2018-08- 2018-07- 2018-09- 2018-07- 2018-10- 2018-11- de faisabilité des MP de IDA / 57180 Post Consultant Open 1,000.00 1,394.24 Completed development support 27 08 15 15 05 02 09 04 24 09 Construction de 01 forage à Selection PMH à L'EP TCHOURA BIZILI cmne de Touloum CM-CRC EXTREME NORD- 58649-CS-INDV / Sélection d'un consultant pour etudes Individual de faisabilité des MP de Component A: Local 2018-05- 2018-05- 2018-07- 2018-06- 2018-08- 2018-07- 2018-09- 2018-07- 2018-10- 2018-11- IDA / 57180 Post Consultant Open 1,600.00 1,401.01 Completed construction d'un bloc de 03 development support 27 08 15 22 05 02 09 04 24 09 Selection boutiques au marché centrale de Touloum et 02 boutiques au marché de SAOTSAI 1 CM-CRC EXTREME NORD- 58694-CS-INDV / Sélection d'un consultant pour etudes de faisabilité des MP de Individual Component A: Local 2018-05- 2018-05- 2018-07- 2018-05- 2018-08- 2018-07- 2018-09- 2018-07- 2018-10- 2018-12- Construction d'un CSI d'un IDA / 57180 Post Consultant Open 5,600.00 4,897.34 Completed development support 27 08 15 24 05 02 09 06 24 08 logement d'astreinte et d'un Selection incinerateur et d'un bloc latrine à Danigué et à Nguéring (06 MP) CM-CRC EXTREME NORD- 58325-CS-INDV / sélection d1 consultant pour le suivi/controle des travaux de Construction d'un bloc Individual Component A: Local 2017-09- 2017-09- 2017-09- 2017-09- 2017-10- 2017-11- 2017-11- 2017-11- 2018-02- de 02 salles de classe et de IDA / 57180 Post Consultant Limited 6,200.00 5,558.23 Signed development support 12 12 17 12 08 04 12 06 10 latrines à l'EP de Mayel Béi Selection et l'EP de Palaoudi et travaux de construction d'un bloc maternel à EM de Zokok-Laddeo cmne de Maroua 1 CM-CRC EXTREME NORD- 58591-CS-INDV / Sélection d'un Consultant pour le Individual Suivi/contrôle des Component A: Local 2018-05- 2018-06- 2018-06- 2018-07- 2018-07- 2018-07- 2018-08- 2018-08- 2019-02- IDA / 57180 Post Consultant Open 3,936.00 3,082.22 Signed TRAVAUX DE development support 02 01 20 16 11 27 15 18 11 Selection REHABILILATION DU TRONCON HOTEL LE SAHEL- MAYO-KALIAO (0,7 KM) cmne DE MAROUA Ier CM-CRC EXTREME NORD- 58842-CS-INDV / Sélection d'un Consultant pour le Individual Component A: Local 2018-05- 2018-08- 2018-06- 2018-10- 2018-07- 2018-10- 2018-08- 2018-11- 2019-02- Suivi/contrôle des TRAVAUX IDA / 57180 Post Consultant Open 3,802.00 3,274.86 Signed development support 02 03 20 08 11 16 15 29 11 DE REHABILILATION DE LA Selection PISTE SOUKOUDJO- BAGRISSE-FARARE (28 KM) CM-CRC EXTREME NORD- 58553-CS-INDV / Sélection d'un Consultant pour le Suivi/contrôle des Travaux Individual Component A: Local 2018-05- 2018-06- 2018-06- 2018-07- 2018-07- 2018-07- 2018-08- 2018-09- 2018-11- de construction d'un forage IDA / 57180 Post Consultant Open 2,690.00 2,075.63 Signed development support 02 01 20 16 11 27 15 27 13 productif équipé de pompe Selection manuelle à EP Louguéré à EP Ouro Nangué à Fakalao à Hodango CM-CRC EXTREME NORD- 58315-CS-INDV / Sélection d'un Consultant pour le Suivi/contrôle des Travaux Individual de construction d'un bloc de Component A: Local 2018-05- 2018-06- 2018-06- 2018-07- 2018-07- 2018-07- 2018-08- 2018-10- 2018-11- IDA / 57180 Post Consultant Open 3,947.00 2,940.47 Signed 02 salles de classe équipées development support 02 01 20 16 11 27 15 25 13 Selection et construction d'un bloc de latrines à trois compartiment à EP de WOUYANG et à l'EP de GONOZO CM-CRC EXTREME NORD- 58549-CS-INDV / Sélection d'un Consultant pour le Suivi/contrôle des Travaux Individual Component A: Local 2018-05- 2018-06- 2018-06- 2018-07- 2018-07- 2018-07- 2018-08- 2018-10- 2018-11- de Construction d'un atelier IDA / 57180 Post Consultant Open 2,871.00 1,729.69 Signed development support 02 01 20 16 11 27 15 25 13 de maçonnerie au CETIC de Selection Loulou et'un bloc de latrines à trois compartiments au CETIC de Loulou CM-CRC EXTREME NORD- 58669-CS-INDV / Sélection d'un Consultant pour le Suivi/contrôle des Travaux Individual de construction de 02 salles Component A: Local 2018-05- 2018-06- 2018-06- 2018-07- 2018-07- 2018-07- 2018-08- 2018-11- 2018-11- 2019-06- IDA / 57180 Post Consultant Open 8,006.00 4,880.90 Completed de classe et d'un bloc de development support 02 01 20 16 11 27 15 01 13 18 Selection latrines au Lycée Tech de Gobo, à l'EP de GUIRIOU CENTR, au Lycée de DOM PYA, à la SAR/SM de Gobo dans la cmne de GOBO CM-CRC EXTREME NORD- 58684-CS-INDV / Sélection d'un Consultant pour le Suivi/contrôle des Travaux Individual Component A: Local 2018-05- 2018-06- 2018-06- 2018-07- 2018-07- 2018-07- 2018-08- 2018-11- 2018-10- 2019-05- de construction d'un bloc de IDA / 57180 Post Consultant Open 934.00 748.35 Completed development support 02 01 20 16 11 27 15 01 14 22 latrines a quatre (04) Selection compartiments au marché de GOBO et de NOULDAINA dans la cmne de GOBO CM-CRC EXTREME NORD- 58850-CS-INDV / Sélection d'un Consultant pour le Individual Component A: Local 2018-05- 2018-06- 2018-06- 2018-07- 2018-07- 2018-07- 2018-08- 2018-11- 2018-09- 2019-03- Suivi/contrôle des Travaux IDA / 57180 Post Consultant Open 660.00 574.90 Completed development support 02 01 20 16 11 27 15 15 29 01 de construction d'un forage Selection équipé de PMH à l'EP de GUIRIOU CENTRE CM-CRC EXTREME NORD- 58558-CS-INDV / Sélection d'un Consultant pour le Suivi/contrôle des Travaux Individual Component A: Local 2018-05- 2018-08- 2018-06- 2018-10- 2018-07- 2018-11- 2018-08- 2018-12- 2018-11- de construction d'un bloc de IDA / 57180 Post Consultant Open 2,002.00 1,433.49 Signed development support 02 03 20 23 11 03 15 27 13 02 salles de classe équipées Selection et d'un bloc de latrines à trois compartiments au CES de Doukroye CM-CRC EXTREME NORD- 58560-CS-INDV / Sélection d'un Consultant pour le Individual Suivi/contrôle des Travaux Component A: Local 2018-05- 2018-08- 2018-06- 2018-10- 2018-07- 2018-11- 2018-08- 2018-12- 2018-09- IDA / 57180 Post Consultant Open 643.00 517.42 Signed de construction d'un forage development support 02 03 20 27 11 03 15 18 14 Selection équipé de PMH à l'EP de Daloa (Doukroye) dans la cmne de KAIKAI CM-CRC EXTREME NORD- 58636-CS-INDV / Sélection d'un Consultant pour le Suivi/contrôle des Travaux Individual de construction d'un bloc de Component A: Local 2018-05- 2018-06- 2018-06- 2018-07- 2018-07- 2018-07- 2018-08- 2018-11- 2018-11- 2019-05- IDA / 57180 Post Consultant Open 4,013.00 2,853.99 Completed 02 salles de classe équipées development support 02 01 20 16 11 27 15 01 13 30 Selection et d'un bloc de latrines à trois compartiments à EP de Balane au CES de Sirlawé dans la cmne de KAR-HAY CM-CRC EXTREME NORD- 58634-CS-INDV / Sélection d'un Consultant pour le Suivi/contrôle des Travaux de construction d'un forage Individual Component A: Local 2018-05- 2018-06- 2018-06- 2018-07- 2018-07- 2018-07- 2018-08- 2018-11- 2018-11- équipé de PMH à l'EP de IDA / 57180 Post Consultant Open 3,845.00 2,594.54 Signed development support 02 01 20 16 11 27 15 01 13 Damdama à l'école des Selection parents de Gouloulou à l'EP Balane à l'EP de REY- FOULAYE à l'EP de Sadielle au CES de Sirlawe CM-CRC EXTREME NORD- 58701-CS-INDV / Sélection d'un Consultant pour le Suivi/contrôle des Travaux Individual de construction d'un bloc de Component A: Local 2018-05- 2018-06- 2018-06- 2018-07- 2018-07- 2018-07- 2018-08- 2018-09- 2018-11- IDA / 57180 Post Consultant Open 4,332.00 2,789.46 Signed 02 salles de classe équipées development support 02 01 20 16 11 27 15 17 13 Selection et d'un bloc de latrines à trois compartiments à l'EP de Bihoré à l'EP de Troké dans la, commue de Tchatibali. CM-CRC EXTREME NORD- 58848-CS-INDV / Sélection d'un Consultant pour le Suivi/contrôle des Travaux Individual Component A: Local 2018-05- 2018-06- 2018-06- 2018-07- 2018-07- 2018-07- 2018-08- 2018-11- 2018-11- de construction d'un forage IDA / 57180 Post Consultant Open 1,986.00 1,394.73 Signed development support 02 01 20 16 11 27 15 05 13 équipé de PMH à l'EP Selection Saouringwa, à Kada et 'a Glonheme dans la cmne de Tchatibali CM-CRC EXTREME NORD- 58615-CS-INDV / Sélection d'un Consultant pour le Individual Component A: Local 2018-05- 2018-06- 2018-06- 2018-07- 2018-07- 2018-07- 2018-08- 2018-09- 2018-10- Suivi/contrôle des Travaux IDA / 57180 Post Consultant Open 2,026.00 1,917.50 Signed development support 02 01 20 16 11 27 15 03 14 de construction d'un forage Selection équipé de PMH à Bibalé - Gambour à Goubara à Kassilé CM-CRC EXTREME NORD- 58667-CS-INDV / Sélection d'un Consultant pour le Suivi/contrôle des Travaux de réhabilitation de la mare Individual Component A: Local 2018-05- 2018-06- 2018-06- 2018-07- 2018-07- 2018-07- 2018-08- 2018-09- 2018-11- de Garey Kaélé, IDA / 57180 Post Consultant Open 2,320.00 1,917.50 Signed development support 02 01 20 23 11 30 15 18 13 Construction d'un forage Selection pastoral à énergie solaire Garey Kaélé et construction d'un forage équipé de PMH à Kassilé dans la commue de Kaele CM-CRC EXTREME NORD- 58555-CS-INDV / Sélection d'un Consultant pour le Suivi/contrôle des Travaux Individual de construct de 02 salles Component A: Local 2018-05- 2018-06- 2018-06- 2018-07- 2018-07- 2018-07- 2018-08- 2018-10- 2018-11- IDA / 57180 Post Consultant Open 7,921.00 5,839.65 Signed de classe équipées et bloc development support 02 01 20 16 11 27 15 15 13 Selection latrines à l'EP de Badjafe, à l'EP de Zouana à l'EP de Tchabeyel et EP de Goudjouing cmne de Kaele. CM-CRC EXTREME NORD- 58641-CS-INDV / Sélection d'un Consultant pour le Suivi/contrôle des travaux Individual Component A: Local 2018-05- 2018-08- 2018-06- 2018-10- 2018-07- 2018-11- 2018-08- 2018-11- 2018-11- de construction de 02 salles IDA / 57180 Post Consultant Open 3,687.00 2,782.38 Signed development support 02 03 20 26 11 03 15 07 13 de classe et d'un bloc de Selection latrines à EP Mayel -Guinadj et 02 salles de classe à l'EP de KALAF cmne de Moutourwa. CM-CRC EXTREME NORD- 58703-CS-INDV / Sélection d'un Consultant pour le Suivi/contrôle des travaux Individual Component A: Local 2018-05- 2018-08- 2018-06- 2018-10- 2018-07- 2018-11- 2018-08- 2018-11- 2018-11- de construction de 01 IDA / 57180 Post Consultant Open 2,696.00 2,086.79 Signed development support 02 03 20 26 11 03 15 19 13 forage équipé de PMH à Selection Ganaha, à EP de Dourloum à EP de KALAF et EP de Mayel- guinadji dans la cmne de moutourwa CM-CRC EXTREME NORD- 58306-CS-INDV / Sélection d'un Consultant pour le Suivi/contrôletravaux de construction de 02 salles de Individual Component A: Local 2018-05- 2018-06- 2018-06- 2018-07- 2018-07- 2018-07- 2018-08- 2018-10- 2018-11- 2019-01- classe et d'un bloc de IDA / 57180 Post Consultant Open 2,339.00 1,656.24 Completed development support 02 01 20 23 11 30 15 25 13 03 latrines à l'EP de GABOUA et Selection Equipements en tables- bancs et bureauxà l'EP de KOZA 1, Koza 2 et Gaboua dans la cmne de KOZA CM-CRC EXTREME NORD- 58522-CS-INDV / Sélection d'un Consultant pour le Individual Component A: Local 2018-05- 2018-06- 2018-06- 2018-07- 2018-07- 2018-07- 2018-08- 2018-10- 2018-10- Suivi/contrôle des Travaux IDA / 57180 Post Consultant Open 1,596.00 1,391.14 Signed development support 02 01 20 16 11 30 15 15 14 de construction d'un forage Selection équipé de PMH à EM Moskota et à l'EP GOKORO CM-CRC EXTREME NORD- 58708-CS-INDV / Sélection d'un Consultant pour le Suivi/contrôle des Travaux Individual de travaux de construction Component A: Local 2018-05- 2018-06- 2018-06- 2018-06- 2018-07- 2018-06- 2018-08- 2018-11- 2018-11- IDA / 57180 Post Consultant Open 3,809.00 3,138.14 Signed de 02 salles de classe et development support 02 01 20 23 11 30 15 07 13 Selection d'un bloc de latrines au CETIC D'OUZAL et Construction d'un bloc de deux salles de classe équipées à l'EP KARAZAWA CM-CRC EXTREME NORD- 58298-CS-INDV / Sélection d'un Consultant pour le Suivi/contrôle des Travaux Individual Component A: Local 2018-05- 2018-06- 2018-06- 2018-06- 2018-07- 2018-06- 2018-08- 2018-11- 2018-09- de construction d'un bloc IDA / 57180 Post Consultant Open 4,136.00 3,312.48 Signed development support 02 01 20 23 11 30 15 07 29 maternelle à EM de Selection MOSKOTA et Construction d'un bloc de salle de classe équipé à l'EP KORSAMBA CM-CRC EXTREME NORD- 58692-CS-INDV / Sélection d'un Consultant pour le Suivi/contrôle des Travaux de Construction d'un bloc Individual de deux salles de classe Component A: Local 2018-05- 2018-06- 2018-06- 2018-07- 2018-07- 2018-07- 2018-08- 2018-10- 2018-11- IDA / 57180 Post Consultant Open 6,000.00 3,504.25 Signed équipées et d'un bloc development support 02 01 20 23 11 30 15 25 13 Selection latrines a trois compartiments au CES de Mazaya à EP ZELE (Soulédé) (lot01) à EP de Doumbéré(lot02) cmne de ROUA CM-CRC EXTREME NORD- 58291-CS-INDV / Sélection d'un Consultant pour le Suivi/contrôle des construct de 02 SC equipées Gouvaka Individual Component A: Local 2018-05- 2018-08- 2018-06- 2018-09- 2018-07- 2018-10- 2018-08- 2018-10- 2018-09- Chefferie et équipement IDA / 57180 Post Consultant Open 5,825.00 4,178.33 Signed development support 02 03 20 03 11 16 15 22 29 bureau et construct de 02 Selection SC equipées à L'EP de Majéconstruct de 02 SC equipées et équipement SC existantes à L'EP de Malika CM-CRC EXTREME NORD- 58612-CS-INDV / Sélection d'un Consultant pour le Individual Component A: Local 2018-05- 2018-08- 2018-06- 2018-10- 2018-07- 2018-10- 2018-08- 2018-11- 2018-10- Suivi/contrôle des Travaux IDA / 57180 Post Consultant Open 1,647.00 1,220.39 Signed development support 02 03 20 06 11 16 15 06 14 de construction d'un forage Selection équipé de PMH à Koulang à Mangavé cmne de MORA CM-CRC EXTREME NORD- 58556-CS-INDV / Sélection d'un Consultant pour le Suivi/contrôle des Travaux Individual Component A: Local 2018-05- 2018-08- 2018-06- 2018-10- 2018-07- 2018-10- 2018-08- 2018-10- 2018-11- de construction de 01 IDA / 57180 Post Consultant Open 2,912.00 2,440.77 Signed development support 02 03 20 08 11 16 15 22 13 magasin de stockage de Selection cereale à Sera -Idoumda et de conservation d'oignon àà Kourgui cmne de MORA Page 10 CM-CRC EXTREME NORD- 58593-CS-INDV / Sélection d'un Consultant pour le Suivi/contrôle de Travaux Individual de Construction d'un bloc Component A: Local 2018-05- 2018-06- 2018-06- 2018-07- 2018-07- 2018-07- 2018-08- 2018-10- 2018-11- IDA / 57180 Post Consultant Open 2,409.00 2,085.86 Signed de 02 salles de classe development support 02 01 20 01 11 27 15 14 13 Selection équipées à EP de Gance et d'un bloc de latrines à trois compartiments à L'EP TOLKOMARI cmne de Kolofata CM-CRC EXTREME NORD- 58609-CS-INDV / Selction d un consultant pour le Individual suivi/controle Travaux de Component A: Local 2018-05- 2018-06- 2018-06- 2018-07- 2018-07- 2018-07- 2018-08- 2018-10- 2018-11- 2019-08- IDA / 57180 Post Consultant Open 3,990.00 2,789.46 Completed Construction de deux bloc development support 02 01 20 16 11 27 15 24 13 02 Selection de 02 salles de classe équipées aux CES TOLKOMARI I cmne de Kolofata. CM-CRC EXTREME NORD- 58666-CS-INDV / Sélection d'un Consultant pour le Suivi/contrôle de Travaux Individual de Construction d'un forage Component A: Local 2018-05- 2018-06- 2018-06- 2018-07- 2018-07- 2018-07- 2018-08- 2018-08- 2018-11- IDA / 57180 Post Consultant Open 3,358.00 2,615.12 Signed équipé de PMH à l'EP GANCE development support 02 01 20 16 11 27 15 16 13 Selection au CES Toltomari et Réalisation d’un forage solaire avec borne fontaine à Kolofata cmne de Kolofata CM-CRC EXTREME NORD- 58646-CS-INDV / Sélection d'un Consultant pour le Suivi/contrôle des Travaux Individual Component A: Local 2018-05- 2018-08- 2018-06- 2018-10- 2018-07- 2018-10- 2018-08- 2018-10- 2018-11- 2019-03- de Construction d'un bloc IDA / 57180 Post Consultant Open 5,520.00 3,897.16 Completed development support 02 03 20 05 11 08 15 12 13 12 de 02 salles de classe Selection équipées s à EP Chéoulew au CES de Makalingaï (lot01)à EP Tazang (lot02) cmne de Tokombere CM-CRC EXTREME NORD- 58545-CS-INDV / Sélection d'un Consultant pour le Individual Suivi/contrôle des Travaux Component A: Local 2018-05- 2018-06- 2018-06- 2018-07- 2018-07- 2018-07- 2018-08- 2018-10- 2018-10- 2018-12- IDA / 57180 Post Consultant Open 1,226.00 1,420.87 Completed de Construction de 01 development support 02 01 20 01 11 27 15 22 14 18 Selection forage équipé de PMH à Baka-Fourwa et à Djaltar dans la cmne de Tokombere CM-CRC EXTREME NORD- 58642-CS-INDV / SELECTION CONSULTANT SUIVI/CONTROLE TRAVAUX DE CONSTRUCTION D'UN Individual Component A: Local 2018-05- 2018-05- 2018-06- 2018-07- 2018-07- 2018-07- 2018-08- 2018-12- 2018-11- BLOC DE DEUX SALLES DE IDA / 57180 Post Consultant Open 2,201.00 1,817.81 Signed development support 02 23 20 13 11 20 15 13 13 CLASSE EQUIPE ET D'UN Selection BLOC DE LATRINES A TROIS COMPARTIMENTS A L’EP KOUTOULA DANS LA CMNE DE BLANGOUA CM-CRC EXTREME NORD- 58705-CS-INDV / SUIVI CONTROLE DES TRAVAUX D'AMENAGEMENT D'UNE GARE ROUTIERE PAR LA Individual Component A: Local 2018-05- 2018-05- 2018-06- 2018-07- 2018-07- 2018-07- 2018-08- 2018-07- 2018-12- 2019-09- CONSTRUCTION DE 04 IDA / 57180 Post Consultant Open 3,600.00 2,707.83 Completed development support 02 23 20 13 11 20 15 23 13 08 GUICHETS, 04 MAGASINS, Selection D'UN HANGAR D'ATTENTE ET D'UN BLOC LATRINE AVEC UN MUR D'ENCEINTE DE 130 m A BLANGOUA CM-CRC EXTREME NORD- 58559-CS-INDV / SELECTION CONSULTANT SUIVI/CONTROLE TRAVAUX Individual Component A: Local 2018-05- 2018-05- 2018-06- 2018-06- 2018-07- 2018-07- 2018-08- 2018-07- 2018-11- DE CONSTRUCTION D'UN IDA / 57180 Post Consultant Open 1,482.00 856.87 Signed development support 02 23 20 19 11 20 15 27 13 FORAGE EQUIPE DE PMH A la Selection gare routiere de BLANGOUA ET A L'EP DE KOUTOULA DANS LA CMNE DE BLANGOUA CM-CRC EXTREME NORD- 58681-CS-INDV / SELECTION CONSULTANT SUIVI/CONTROLE TRAVAUX Individual Component A: Local 2018-05- 2018-05- 2018-06- 2018-07- 2018-07- 2018-07- 2018-08- 2018-07- 2018-11- 2019-02- DE CONSTRUCTION D'UN IDA / 57180 Post Consultant Open 4,057.00 4,474.93 Completed development support 02 23 20 13 11 20 15 24 13 02 FORAGE PASTORAL A Selection ENERGIE SOLAIRE A KARENA ET A NAGA DANS LA CMNE DE DARAK CM-CRC EXTREME NORD- 58838-CS-INDV / SELECTION CONSULTANT SUIVI/CONTROLE TRAVAUX DE CONSTRUCTION D'UN BLOC DE DEUX SALLES DE Individual Component A: Local 2018-05- 2018-05- 2018-06- 2018-07- 2018-07- 2018-07- 2018-08- 2018-12- 2018-11- 2019-07- CLASSE EQUIPE ET D'UN IDA / 57180 Post Consultant Open 3,756.00 3,047.10 Completed development support 02 23 20 16 11 20 15 03 13 05 BLOC DE LATRINES A TROIS Selection COMPARTIMENTS A L’EP HILELLE ) ET CONSTRUCTION D'UN HANGAR AU MARCHE DE GOULFEY GANA cmne DE GOULFEY CM-CRC EXTREME NORD- 58567-CS-INDV / SELECTION CONSULTANT SUIVI/CONTROLE TRAVAUX D’AMENAGEMENT D’UNE GARE ROUTIERE PAR LA Individual Component A: Local 2018-05- 2018-05- 2018-06- 2018-07- 2018-07- 2018-07- 2018-08- 2018-12- 2018-11- 2019-10- CONSTRUCTION DE 04 IDA / 57180 Post Consultant Open 3,656.00 2,698.86 Completed development support 02 23 20 16 11 20 15 17 13 11 GUICHETS, 04 MAGASINS, Selection D’UN HANGAR D’ATTENTE, 02 BOUTIQUES ET D’UN BLOC LATRINE AVEC UN MUR D’ENCEINTE DE 90 m A GOULFEY cmne DE GOULFEY CM-CRC EXTREME NORD- 58594-CS-INDV / SELECTION CONSULTANT SUIVI/CONTROLE TRAVAUX Individual DE CONSTRUCTION D'UN Component A: Local 2018-05- 2018-05- 2018-06- 2018-07- 2018-07- 2018-07- 2018-08- 2018-07- 2018-11- IDA / 57180 Post Consultant Open 2,087.00 853.74 Signed FORAGE EQUIPES DE POMPE development support 02 23 20 13 11 20 15 27 13 Selection A MOTRICITE HUMAINE A MOUGALAM,A TAWOULWEBE ET A L'EP HILELE cmne DE HILE ALIFA CM-CRC EXTREME NORD- 58565-CS-INDV / SELECTION CONSULTANT SUIVI/CONTROLE TRAVAUX Individual DE CONSTRUCTION D'UN Component A: Local 2018-05- 2018-05- 2018-06- 2018-07- 2018-07- 2018-08- 2018-07- 2018-11- IDA / 57180 Post Consultant Open 2,477.00 1,859.26 Signed BLOC DE DEUX SALLES DE development support 02 23 20 11 20 15 22 13 Selection CLASSE EQUIPE ET D'UN BLOC DE LATRINES A TROIS COMPARTIMENTS A L’EP GONONI CM-CRC EXTREME NORD- 58519-CS-INDV / SELECTION CONSULTANT SUIVI/CONTROLE TRAVAUX Individual DE CONSTRUCTION D'UN Component A: Local 2018-05- 2018-05- 2018-06- 2018-07- 2018-07- 2018-07- 2018-08- 2018-07- 2018-11- IDA / 57180 Post Consultant Open 2,163.00 853.74 Signed FORAGE EQUIPE DE POMPE A development support 02 23 20 13 11 20 15 27 13 Selection MOTRICITE HUMAINE A MAFOULSO III, A FAMARE ET A L'EP DE GONONI cmne DE HILE ALIFA CM-CRC EXTREME NORD- 58608-CS-INDV / SELECTION CONSULTANT SUIVI/CONTROLE TRAVAUX DE CONSTRUCTIOND’UNE Individual Component A: Local 2018-05- 2018-05- 2018-06- 2018-07- 2018-07- 2018-07- 2018-08- 2018-07- 2018-11- MINI AEP PASTORAL EQUIPE IDA / 57180 Post Consultant Open 4,043.00 3,065.26 Signed development support 02 23 20 13 11 20 15 27 13 DE DEUX ABREUVOIRS, Selection D’UNE POMPE IMMERGEE A ENERGIE PHOTOVOLTAÏQUE A ABASSOUNI, A DOLE BADA cmne DE HILE ALIFA CM-CRC EXTREME NORD- 58557-CS-INDV / SELECTION CONSULTANT SUIVI/CONTROLE TRAVAUX DE CONSTRUCTION D'UN Individual Component A: Local 2018-05- 2018-05- 2018-06- 2018-07- 2018-07- 2018-07- 2018-08- 2018-07- 2018-11- BLOC DE DEUX SALLES DE IDA / 57180 Post Consultant Open 2,350.00 1,735.98 Signed development support 02 23 20 16 11 20 15 24 13 CLASSE EQUIPE ET D'UN Selection BLOC DE LATRINES A TROIS COMPARTIMENTS AU CES D'ADJAÏNE A HILE HAOUSSA cmne DE KOUSSERI CM-CRC EXTREME NORD- 58569-CS-INDV / SELECTION CONSULTANT Individual SUIVI/CONTROLE TRAVAUX Component A: Local 2018-05- 2018-05- 2018-06- 2018-07- 2018-07- 2018-07- 2018-08- 2018-12- 2018-11- IDA / 57180 Post Consultant Open 1,975.00 1,629.76 Signed DE CONSTRUCTION D'UN development support 02 23 20 16 11 20 15 03 13 Selection HANGAR AVEC BLOC LATRINE AU MARCHE DE BIAMO, cmne DE MAKARI CM-CRC EXTREME NORD- 58691-CS-INDV / SELECTION CONSULTANT SUIVI/CONTROLE TRAVAUX Individual DE CONSTRUCTION D'UN Component A: Local 2018-05- 2018-05- 2018-06- 2018-07- 2018-07- 2018-07- 2018-08- 2018-07- 2018-11- 2019-07- IDA / 57180 Post Consultant Open 2,201.00 1,629.76 Completed BLOC DE DEUX SALLES DE development support 02 23 20 16 11 20 15 24 13 20 Selection CLASSE EQUIPE ET D'UN BLOC DE LATRINES A TROIS COMPARTIMENTS A L'EP DE MALTAM cmne DE MAKARI CM-CRC EXTREME NORD- 58495-CS-INDV / SELECTION CONSULTANT SUIVI/CONTROLE TRAVAUX Individual DEs MP D'INSTALLATION Component A: Local 2018-05- 2018-06- 2018-07- 2018-08- 2018-10- IDA / 57180 Post Consultant Open 2,017.00 0.00 Canceled D'ECLAIRAGE PUBLIC (10 development support 02 20 11 15 14 Selection KITS)AVEC ENERGIE SOLAIRE DE L'AXE MAIRIE DE HILE ALIFA-BRIGADE DE GENDARMERIE DE HILE CM-CRC EXTREME NORD- 38340-CS-INDV / Suivi/contrôle des Travaux construction d'un forage Individual Component A: Local 2017-11- 2018-02- 2017-12- 2017-12- 2018-01- 2018-04- équipé de PMH dans les IDA / 57180 Post Consultant Limited 3,477.00 0.00 Canceled development support 27 05 02 23 27 27 localités de Kaliao, Selection Goulmoyo, Mbozo Mofou, Balewa et Manguirdla (Lot1) COMMUNE DE MERI CM-CRC EXTREME NORD- 38342-CS-INDV / Suivi/contrôle technique et environnemental des travaux de construction Individual d'un forage équipé de PMH Component A: Local 2017-11- 2018-02- 2017-12- 2018-03- 2017-12- 2018-04- 2018-01- 2018-04- 2018-04- IDA / 57180 Post Consultant Limited 6,954.00 5,699.52 Signed dans les localités de Kaliao, development support 27 05 02 28 23 04 27 06 27 Selection Goulmoyo, Mbozo Mofou, Balewa et Manguirdla, Moundour Foulbé, Dogba Maliki, Magawa, Houloum et Tchaki djébé Commune de MERI CM-CRC EXTREME NORD- 83169-CS-INDV / Sélection d'un consultant pour l'élaboration des Etudes de Individual faisabilité techniques et Component A: Local 2018-06- 2018-10- 2018-08- 2018-10- 2018-08- 2018-10- 2018-09- 2018-10- 2018-11- 2019-12- IDA / 57180 Post Consultant Open 4,500.00 3,858.02 Completed environnementales des MP development support 15 08 03 26 24 27 28 27 12 19 Selection d'électrification de la localité de Dargala centre- Lycée de Dargala et Dargala- Hodande Commune de Dargala. CM-CRC EXTREME NORD- 83165-CS-INDV / Sélection d'un consultant pour l'élaboration des Etudes de faisabilité des MP de Individual Component A: Local 2018-06- 2018-10- 2018-08- 2018-10- 2018-08- 2018-10- 2018-09- 2018-10- 2018-11- 2018-12- construction d'un (01) IDA / 57180 Post Consultant Open 3,500.00 3,542.39 Completed development support 15 08 03 25 24 27 28 27 12 19 forage à PMH à Dargala- Selection Centre à Hardéo-Golo à Yonkolel à Toupouré- Sirataré à Wirdiwo à Ouro- Domayo à Ouro-Hitgo Commune de Dargala. CM-CRC EXTREME NORD- 83171-CS-INDV / Sélection d'un consultant pour l'élaboration des Etudes de Individual faisabilité techniques et Component A: Local 2018-10- 2018-10- 2018-12- 2018-10- 2018-12- 2018-10- 2019-01- 2018-10- 2019-03- 2019-01- IDA / 57180 Post Consultant Open 4,000.00 4,048.44 Completed environnementales des MP development support 15 08 03 25 24 27 28 29 14 03 Selection de Rehabilitation des routes dans les quartiers de Wourndé II, III, VI long d'environ 3 km Commune de Maroua II. CM-CRC EXTREME NORD- 83155-CS-INDV / Sélection d'un consultant pour l'élaboration des Etudes de Individual faisabilité techniques et Component A: Local 2018-10- 2018-10- 2018-12- 2018-10- 2018-12- 2018-10- 2019-01- 2018-12- 2019-03- 2019-01- IDA / 57180 Post Consultant Open 4,000.00 4,223.60 Completed environnementales des MP development support 15 08 03 25 24 27 28 06 14 03 Selection d'extension du réseau électrique dans les quartiers de Wourndé II, III, VI Commune de Maroua II. CM-CRC EXTREME NORD- 83158-CS-INDV / Sélection d'un consultant pour l'élaboration des Etudes de Individual faisabilité techniques et Component A: Local 2018-10- 2018-10- 2018-12- 2018-10- 2018-12- 2018-10- 2019-01- 2018-10- 2019-03- 2018-12- IDA / 57180 Post Consultant Open 1,600.00 1,709.83 Completed environnementales des MP development support 15 10 03 26 24 27 28 29 14 22 Selection de Construction d’une aire d’abattage d’un bloc latrines et d’un forage à Doursoungo Commune de Maroua III. CM-CRC EXTREME NORD- 83143-CS-INDV / Sélection d'un consultant pour l'élaboration des Etudes de faisabilité techniques et Individual environnementales des MP Component A: Local 2018-10- 2018-10- 2018-12- 2018-10- 2018-12- 2018-10- 2019-01- 2018-10- 2019-02- 2018-11- IDA / 57180 Post Consultant Open 3,000.00 3,570.54 Completed d'éclairage public à energie development support 15 08 03 24 24 27 28 29 27 08 Selection solaire dans les localités de Mindif, Ouro Bouné, Modjombodi, Djodjong et Djouta Wade Commune de Mindif CM-CRC EXTREME NORD- 83159-CS-INDV / Sélection d'un consultant pour l'élaboration des Etudes de faisabilitédes MP de Individual Component A: Local 2018-10- 2018-10- 2018-12- 2018-10- 2018-12- 2018-10- 2019-01- 2018-10- 2019-03- 2018-11- construction et équipement IDA / 57180 Post Consultant Open 5,000.00 5,149.62 Completed development support 15 08 03 26 24 27 28 29 14 08 d'un CSI à Hoppo et Selection fourniture en équipement dans les CSI de Mindif de Modjombodi de Maoundine et de Mogom Commune de Mindif. CM-CRC EXTREME NORD- 83145-CS-INDV / Sélection d'1 consultant pour EF des MP de Construction d'1 bloc de 02 salles classe et Individual Component A: Local 2018-10- 2018-10- 2018-12- 2018-10- 2018-12- 2018-10- 2019-01- 2018-10- 2019-03- 2018-11- d'1 bloc de latrines à EP IDA / 57180 Post Consultant Open 5,400.00 5,984.42 Completed development support 15 10 03 25 24 27 28 27 14 23 Rebede au CES de Selection Dongrosse au CES de Soueye,à EP Mbiteu à EP Lobokri à EP SAIGA et équipements à l'EP Danhou Commune de Dziguilao. CM-CRC EXTREME NORD- 83147-CS-INDV / Sélection d'un consultant pour l'élaboration des Etudes de Individual faisabilité techniques et Component A: Local 2018-10- 2018-10- 2018-12- 2018-10- 2018-12- 2018-10- 2019-01- 2018-10- 2019-03- 2018-11- IDA / 57180 Post Consultant Open 1,200.00 2,665.22 Completed environnementales des MP development support 15 08 03 23 24 27 28 23 14 23 Selection de construction d'un (01) forage à PMH à l’EP de SAIGA et de Lobokri dans la Commune de Dziguilao. . CM-CRC EXTREME NORD- 83160-CS-INDV / Sélection d'un consultant pour l'élaboration des Etudes de Individual faisabilité de Construction Component A: Local 2018-10- 2018-10- 2018-12- 2018-10- 2018-12- 2018-10- 2019-01- 2018-10- 2019-03- IDA / 57180 Post Consultant Open 3,369.00 3,040.99 Signed d'un bloc de 02 salles de development support 15 08 03 26 24 27 28 28 14 Selection classe équipées et d'un bloc de latrines à EP Guidima, à EP Kankrwa, à EP Golonpoui dans la Commune de Datcheka. CM-CRC EXTREME NORD- 83188-CS-INDV / Sélection d'un consultant pour l'élaboration des Etudes de faisabilité des MP de Individual Component A: Local 2018-10- 2018-10- 2018-12- 2018-10- 2018-12- 2018-10- 2019-01- 2018-10- 2019-03- 2018-12- construction d'1 forage à IDA / 57180 Post Consultant Open 3,500.00 3,625.14 Completed development support 15 08 03 27 24 27 28 27 14 27 PMH à EP Kankrwa, à EP Selection Golonpoui, à l'abattoir du marché de Zouaye, à Gaï Gaï, à Tining, à Tibali et à Lara dans la Commune de Datcheka. CM-CRC EXTREME NORD- 83167-CS-INDV / Sélection d'un consultant pour l'élaboration des Etudes de Individual Component A: Local 2018-10- 2018-10- 2018-12- 2018-10- 2018-12- 2018-10- 2019-01- 2018-10- 2019-03- 2018-12- faisabilité techniques et IDA / 57180 Post Consultant Open 1,130.00 1,519.93 Completed development support 15 08 03 26 24 27 28 29 14 27 environnementales des MP Selection de construction d'un abattoir au marché de Zouaye Commune de Datcheka. Page 11 CM-CRC EXTREME NORD- 83151-CS-INDV / Sélection d'un consultant pour l'élaboration des Etudes de faisabilité des MP de Individual Component A: Local 2018-10- 2018-10- 2018-12- 2018-10- 2018-12- 2018-10- 2019-01- 2018-10- 2019-03- 2019-12- Construction d'un bloc de IDA / 57180 Post Consultant Open 4,500.00 4,385.81 Completed development support 15 10 03 26 24 27 28 27 14 12 deux salles de classe Selection équipées au CES d'Agolla, au CES de Dabaye, au CES de Widigue, au CETIC de Vele et au Lycée de Kartoua Commune de Gueme. CM-CRC EXTREME NORD- 83168-CS-INDV / Sélection d'un consultant pour l'élaboration des Etudes de Individual faisabilité techniques et Component A: Local 2018-10- 2018-10- 2018-12- 2018-10- 2018-12- 2018-10- 2019-01- 2018-10- 2019-03- 2018-12- IDA / 57180 Post Consultant Open 1,900.00 1,910.99 Completed environnementales des MP development support 15 10 03 26 24 27 28 29 14 12 Selection de Construction d'un hangar au marché de Dabaye et d'un bloc de latrines VIP au marché de Gabaraye commune de Gueme. CM-CRC EXTREME NORD- 83191-CS-INDV / Sélection d'un consultant pour l'élaboration des Etudes de Individual Component A: Local 2018-10- 2018-10- 2018-12- 2018-10- 2018-12- 2018-10- 2019-01- 2018-10- 2019-03- 2018-12- faisabilité techniques et IDA / 57180 Post Consultant Open 1,900.00 1,909.51 Completed development support 15 08 03 26 24 27 28 29 14 12 environnementales des MP Selection de Construction d'une boucherie et d'un hangar au marché de Vele commune de Gueme. CM-CRC EXTREME NORD- 83148-CS-INDV / Sélection d'un consultant pour l'élaboration des Etudes de faisabilité des MP Individual Component A: Local 2018-10- 2018-10- 2018-12- 2018-10- 2018-12- 2018-10- 2019-01- 2018-12- 2019-03- 2018-12- d'extention de l'électricité IDA / 57180 Post Consultant Open 6,000.00 5,903.98 Completed development support 15 08 03 26 24 27 28 06 14 14 dans la localité de Maga et Selection electrification du marché de Guirvidig des quartiers environnant et de la localité de Yanga Commune de Maga. CM-CRC EXTREME NORD- 83187-CS-INDV / Sélection d'1 consultant élaboration des EF des MP Construction d'1 bloc de 02 salles de Individual Component A: Local 2018-10- 2018-10- 2018-12- 2018-10- 2018-12- 2018-10- 2019-01- 2018-10- 2019-03- 2018-11- classe équipées et 01 bloc IDA / 57180 Post Consultant Open 5,600.00 4,723.18 Completed development support 15 08 03 25 24 27 28 29 14 15 latrines à EP Djenreng à EP Selection Djarwar à EP Vaidou à EP Waimou à EP Bigdi à EP Guidoua à EP Goulourgou au CES de Kamargui Commune Wina. CM-CRC EXTREME NORD- 83153-CS-INDV / Sélection d'un consultant pour l'élaboration des Etudes de faisabilité des MP de Individual Component A: Local 2018-10- 2018-10- 2018-12- 2018-10- 2018-12- 2018-10- 2019-01- 2018-10- 2019-03- 2018-11- construction de 01 forage à IDA / 57180 Post Consultant Open 2,400.00 3,469.96 Completed development support 15 08 03 25 24 27 28 29 14 15 énergie solaire au CSI de Selection Bosgoye d’01 forage pastoral à énergie solaire à Djongdong et d’un forage à PMH à EP Vaidou Comune de Wina CM-CRC EXTREME NORD- 83156-CS-INDV / Sélection d'un consultant pour l'élaboration des Etudes de Individual Component A: Local 2018-05- 2018-05- 2018-07- 2018-06- 2018-08- 2018-07- 2018-09- 2018-07- 2018-10- faisabilité techniques et IDA / 57180 Post Consultant Open 2,400.00 4,853.80 Signed development support 27 08 15 26 05 02 09 06 24 environnementales des MP Selection de contruction d’un mini AEP aux CSI de Danigué et Nguéring Commune de Guere. CM-CRC EXTREME NORD- 83184-CS-INDV / Sélection d'un consultant pour l'élaboration des Etudes de Individual faisabilité techniques et Component A: Local 2018-10- 2018-10- 2018-12- 2018-10- 2018-12- 2018-10- 2019-01- 2018-10- 2019-03- 2018-12- IDA / 57180 Post Consultant Open 3,000.00 3,037.47 Completed environnementales des MP development support 15 08 03 26 24 27 28 29 14 07 Selection de construction de 04 blocs de 10 boutique et Construction de latrines VIP au marché de HINA CM-CRC EXTREME NORD- 83185-CS-INDV / Sélection d'un consultant pour l'élaboration des Etudes de faisabilité techniques et Individual Component A: Local 2018-10- 2018-10- 2018-10- 2018-10- 2018-11- 2018-10- 2018-12- 2018-11- 2019-02- environnementales des MP IDA / 57180 Post Consultant Direct 1,600.00 1,633.42 Signed development support 15 11 25 13 15 18 20 06 03 de Construction d'un bloc Selection de deux salles de classe équipées et un bloc latrines a trois compartiments à Magala-Djamene Commune Darak. CM-CRC EXTREME NORD- 83146-CS-INDV / Sélection d'un consultant pour l'élaboration des Etudes de Individual Component A: Local 2018-10- 2018-10- 2018-10- 2018-10- 2018-11- 2018-10- 2018-12- 2018-10- 2019-02- faisabilité techniques et IDA / 57180 Post Consultant Direct 3,700.00 3,357.24 Signed development support 15 11 25 18 15 25 20 25 03 environnementales des MP Selection d'electrification en énergie solaire de l'auberge municipal et hôtel de ville de Darak CM-CRC EXTREME NORD- 83164-CS-INDV / Sélection d'un consultant pour l'élaboration des Etudes de faisabilité des MP de Individual Component A: Local 2018-10- 2018-10- 2018-10- 2018-10- 2018-11- 2018-10- 2018-12- 2018-11- 2019-02- 2018-12- Construction d'1 bloc de IDA / 57180 Post Consultant Direct 5,000.00 6,462.69 Completed development support 15 11 25 17 15 18 20 05 03 14 deux salles de classe Selection équipées et un bloc latrines à EP DEGA, à EP GADAFAI, à EP NIGUE et à EP WAROU I Commune Fotokol. CM-CRC EXTREME NORD- 83190-CS-INDV / Sélection d'un consultant pour l'élaboration des Etudes de Individual faisabilité des MP de Component A: Local 2018-10- 2018-10- 2018-10- 2018-10- 2018-11- 2018-10- 2018-12- 2018-10- 2019-02- IDA / 57180 Post Consultant Direct 3,000.00 2,685.79 Signed Construction d’un (01) development support 15 11 25 25 15 25 20 25 03 Selection forage PMH dans les lotalités de Amssadeck, de Barkari II, de Djabrari, de Haigayo II Commune Fotokol. CM-CRC EXTREME NORD- 83142-CS-INDV / Sélection d'un consultant pour l'élaboration des Etudes de faisabilité des MP de Individual Component A: Local 2018-10- 2018-10- 2018-10- 2018-10- 2018-11- 2018-10- 2018-12- 2018-11- 2019-02- 2018-12- Construction d'un bloc de IDA / 57180 Post Consultant Direct 2,500.00 3,277.70 Completed development support 15 01 25 11 15 18 20 05 03 14 deux salles de classe Selection équipées et un bloc latrines a trois compartiments à EP WAROU II et à EP OH HAMADIE Commune Fotokol. CM-CRC EXTREME NORD- 83149-CS-INDV / Sélection d'un consultant pour l'élaboration des Etudes de Individual faisabilité des MP de Component A: Local 2018-10- 2018-10- 2018-10- 2018-10- 2018-11- 2018-10- 2018-12- 2018-10- 2019-02- IDA / 57180 Post Consultant Direct 3,000.00 2,685.79 Signed Construction d’un (01) development support 15 11 25 11 15 18 20 23 03 Selection forage PMH dans les lotalités de Kabetoua, de OH Isseini, de Warou II et de Worokaime Commune Fotokol. CM-CRC EXTREME NORD- 83152-CS-INDV / Sélection d'1 consultant pour l'élaboration des EF des MP de Construction d'1 bloc de Individual Component A: Local 2018-10- 2018-10- 2018-10- 2018-10- 2018-11- 2018-10- 2018-12- 2018-11- 2019-02- deux salles de classe IDA / 57180 Post Consultant Direct 3,800.00 5,427.12 Signed development support 15 11 25 11 15 18 20 05 03 équipées et 01 bloc latrines Selection à EP DAVA à EP Kabéla et à EP Beré et fourniture en equipement pour les EP Commune Logone-Birni. CM-CRC EXTREME NORD- 83141-CS-INDV / Sélection d'un consultant pour l'élaboration des Etudes de faisabilité techniques des Individual Component A: Local 2018-10- 2018-10- 2018-10- 2018-10- 2018-11- 2019-10- 2018-12- 2018-11- 2019-02- MP de Construction d’un IDA / 57180 Post Consultant Direct 4,200.00 5,091.18 Signed development support 15 11 25 11 15 18 20 06 03 (01) forage PMH dans les Selection lotalités de Ounangaré de Ngada I de Ngada II de Michiska Mousgoum de Marafine I de SHI commune de Logone-Birni CM-CRC EXTREME NORD- 83162-CS-INDV / Sélection d'un consultant pour l'élaboration des Etudes de Individual Component A: Local 2018-10- 2018-10- 2018-10- 2018-10- 2018-11- 2018-10- 2018-12- 2018-11- 2019-02- faisabilité techniques et IDA / 57180 Post Consultant Direct 1,600.00 1,678.62 Signed development support 15 11 25 17 15 18 20 06 03 environnementales des MP Selection de Construction d'un magasin de stockage de cereale à Zigagué Commune de Waza CM-CRC EXTREME NORD- 83150-CS-INDV / Sélection d'un consultant pour l'élaboration des Etudes de Individual faisabilité techniques et Component A: Local 2018-10- 2018-10- 2018-10- 2018-10- 2018-11- 2018-10- 2018-12- 2018-10- 2019-02- IDA / 57180 Post Consultant Direct 2,400.00 2,280.74 Signed environnementales des MP development support 15 11 25 11 15 18 20 31 03 Selection de Construction d’un (01) forage PMH dans les lotalités de Ndiguina, de Malia et de Mada 1 Commune de Waza CM-CRC EXTREME NORD- 83140-CS-INDV / Sélection d'un consultant pour l'élaboration des Etudes de Individual faisabilité techniques et Component A: Local 2018-10- 2018-10- 2018-10- 2018-10- 2018-11- 2018-11- 2018-12- 2018-11- 2019-02- IDA / 57180 Post Consultant Direct 4,000.00 5,913.04 Signed environnementales des MP development support 15 11 25 11 15 13 20 16 03 Selection de construction d’une mini approvisionement en eau potable à Zigagué Commune de Waza CM-CRC EXTREME NORD- 83154-CS-INDV / Sélection d'un consultant pour l'élaboration des Etudes de faisabilité techniques et Individual Component A: Local 2018-10- 2018-10- 2018-10- 2018-10- 2018-11- 2018-10- 2018-12- 2018-11- 2019-02- environnementales des MP IDA / 57180 Post Consultant Direct 2,000.00 2,044.34 Signed development support 15 11 25 11 15 18 20 06 03 de Construction d'un bloc Selection de deux salles de classe équipées et un bloc latrines a trois compartiments à EP de Davagang Commune Zina. CM-CRC EXTREME NORD- 83161-CS-INDV / Sélection d'un consultant pour l'élaboration des Etudes de Individual faisabilité techniques et Component A: Local 2018-10- 2018-10- 2018-10- 2018-10- 2018-11- 2018-10- 2018-12- 2018-10- 2019-02- IDA / 57180 Post Consultant Direct 2,400.00 2,182.21 Signed environnementales des MP development support 15 11 25 25 15 25 20 25 03 Selection de Construction d’un (01) forage PMH dans les lotalités de ZAMA et de Gadabou Commune de ZINA CM-CRC EXTREME NORD- 58303-CS-INDV / Sélection Individual d'un Consultant pour le Component A: Local 2018-05- 2018-06- 2018-07- 2018-08- 2018-09- IDA / 57180 Post Consultant Open 1,735.00 0.00 Canceled Suivi/contrôle des Travaux development support 02 20 11 15 29 Selection Construction d'une clôture à EM de MOZOGO CM-CRC EXTREME NORD- 58550-CS-INDV / SELECTION CONSULTANT SUIVI/CONTROLE CONSTRUCTION D’UNE MINI Individual Component A: Local 2018-05- 2018-06- 2018-07- 2018-08- 2018-10- AEP PASTORAL EQUIPE DE IDA / 57180 Post Consultant Open 2,004.00 0.00 Canceled development support 02 20 11 15 14 DEUX ABREUVOIRS, D’UNE Selection POMPE IMMERGEE A ENERGIE PHOTOVOLTAÏQUE A MAGALAKABIR, DANS LA CMNE DE DARAK CM-CRC EXTREME NORD- 58544-CS-INDV / SUIVI/CONTROLE CONSTRUCTION D'UN FORAGE EQUIPE DE POMPE A Individual MOTRICITE HUMAINE AU Component A: Local 2018-05- 2018-05- 2018-06- 2018-07- 2018-08- 2018-11- IDA / 57180 Post Consultant Open 4,382.00 0.00 Canceled CES D'ADJAINE ET D'UNE development support 02 23 20 11 15 13 Selection MINI AEP PASTORAL EQUIPE DE DEUX ABREUVOIRS, D'UNE POMPE IMMERGEE A ENERGIE PHOTOVOLTAÏQUE A LACTA 1, MASSAKI CM-CRC EXTREME NORD- 58518-CS-INDV / SELECTION CONSULTANT SUIVI/CONTROLE TRAVAUX Individual DE CONSTRUCTION D'UN Component A: Local 2018-05- 2018-05- 2018-06- 2018-07- 2018-08- 2018-11- IDA / 57180 Post Consultant Open 2,090.00 0.00 Canceled FORAGES EQUIPES DE POMPE development support 02 23 20 11 15 13 Selection A MOTRICITE HUMAINE A MASSIO-GOURGOURA, A NAGA NDIGUINI, A EP MALTAM. cmne DE MAKARI CM-CRC EXTREME NORD- 111116-CS-INDV / suivi controle des travaux de Individual construction d'un bloc de 02 Component A: Local 2019-06- 2019-06- 2019-07- 2019-07- 2019-08- 2019-08- 2019-09- 2019-10- 2019-12- IDA / 57180 Post Consultant Open 1,986.00 2,044.34 Signed salles de classe équipé et development support 03 17 22 11 12 05 16 09 15 Selection d'un bloc de latrines au CETIC de Tchévi dans la commune de Bourha CM-CRC EXTREME NORD- 111253-CS-INDV / suivi controle des travaux de Individual Component A: Local 2019-06- 2019-06- 2019-07- 2019-07- 2019-08- 2019-10- 2019-09- 2020-03- 2019-12- construction d'un forage IDA / 57180 Post Consultant Open 2,617.00 2,253.55 Signed development support 03 17 22 24 12 05 16 02 15 PMH au CETIC de Tchévi, à Selection Zouvou- yolde à DOUVA et à ZEU dans la commune de Bourha CM-CRC EXTREME NORD- 111266-CS-INDV / suivi controle des travaux de Individual construction des caniveaux Component A: Local 2019-06- 2019-06- 2019-07- 2019-07- 2019-08- 2019-08- 2019-09- 2019-10- 2019-12- IDA / 57180 Post Consultant Open 2,774.00 2,545.59 Signed en BA à Bourha (axe development support 03 17 22 24 12 05 16 09 15 Selection Hamadou -ZRA-Bello Hayatou) et à Boukoula face commissariat ( dans la Commune de Bourha CM-CRC EXTREME NORD- 111262-CS-INDV / suivi controle des travaux de construction de 2 blocs de Individual 10 boutiques au marché de Component A: Local 2019-06- 2019-06- 2019-07- 2019-07- 2019-08- 2019-11- 2019-09- 2019-11- 2020-01- IDA / 57180 Post Consultant Open 10,360.00 13,312.67 Signed HINA cote A l1 et development support 03 17 22 24 12 01 16 15 14 Selection construction de 2 blocs de 10 boutiques au marché de HINA et latrines vip au marché de HINA cote B lot (02), commune de HINA. CM-CRC EXTREME NORD- 111341-CS-INDV / suivi controle des travaux de construction de 01 forage à Individual Component A: Local Under 2019-06- 2021-01- 2019-07- 2019-08- 2019-09- 2019-12- PMH à Yoldé-Naggué, à IDA / 57180 Post Consultant Open 4,014.00 0.00 development support Implementation 03 06 22 12 16 15 Tchakamadjé, Yaga djibiwo, Selection à Bakourebi (Abba wollo) Toukou mayel(Ouro-Bedem) et à MAYA ,commune de Pétté CM-CRC EXTREME NORD- 111359-CS-INDV / suivi controle des travaux de Individual construction d'un mini Component A: Local Under 2019-06- 2021-01- 2019-07- 2019-08- 2019-09- 2019-12- IDA / 57180 Post Consultant Open 2,094.00 0.00 adduction d'eau à energie development support Implementation 03 06 22 12 16 15 Selection photovoltaique pour usage agricole a fadare dans la commune de pette CM-CRC EXTREME NORD- 111337-CS-INDV / suivi controle des travaux de construction d'un bloc de Individual deux salles de classe Component A: Local 2019-06- 2019-06- 2019-07- 2019-07- 2019-08- 2019-10- 2019-09- 2019-11- 2020-01- IDA / 57180 Post Consultant Open 8,296.00 8,954.03 Signed équipées et d'un bloc de development support 03 17 22 24 12 25 16 15 14 Selection latrines à trois compartiments à EP SAIGA, EP LOBOKRI, EP MBITEU et CES SOUEYE dans la Commune de Dziguilao CM-CRC EXTREME NORD- 111334-CS-INDV / suivi controle des travaux de Individual construction d'un bloc de Component A: Local 2019-06- 2019-06- 2019-07- 2019-07- 2019-08- 2019-10- 2019-09- 2019-12- 2019-12- IDA / 57180 Post Consultant Open 1,900.00 1,678.62 Signed deux salles de classe development support 03 17 22 24 12 28 16 06 15 Selection équipées et d'un bloc latrine à trois compartiments à l'EP de Ligazang, commune de Mindif CM-CRC EXTREME NORD- 111352-CS-INDV / suivi controle des travaux de construction et équipement d'un csi avec incinerateur et Individual Component A: Local 2019-06- 2019-06- 2019-07- 2019-07- 2019-08- 2019-11- 2019-09- 2019-12- 2020-01- latrines à MATFAI, et IDA / 57180 Post Consultant Open 7,281.00 5,108.10 Signed development support 03 17 22 24 12 05 16 06 14 Fourniture en mobilier et Selection petit materiel sanitaire de CSI de Mindif, de Modjombodi, de Maoudine et de Mogom dans la commune de Mindif Page 12 CM-CRC EXTREME NORD- 111263-CS-INDV / suivi controle des travaux de Individual Component A: Local 2019-06- 2019-11- 2019-07- 2019-07- 2019-08- 2019-11- 2019-09- 2019-12- 2019-12- construction d'un forage IDA / 57180 Post Consultant Open 1,524.00 1,702.70 Signed development support 03 25 22 24 12 22 16 06 15 pastoral a energie Selection photovoltaique au marché à bétail à Moulvoudaye CM-CRC EXTREME NORD- 111348-CS-INDV / suivi controle des travaux d'aménagement du marché Individual à bétail en contruisant un Component A: Local 2019-06- 2019-06- 2019-07- 2019-07- 2019-08- 2019-11- 2019-09- 2019-12- 2020-01- IDA / 57180 Post Consultant Open 2,245.00 2,000.67 Signed parc à betail une cloture un development support 03 17 22 24 12 22 16 06 14 Selection quai d'embarquement et un bloc latrine a trois compartiments dans la Commune de Moulvoudaye. CM-CRC EXTREME NORD- 111264-CS-INDV / suivi controle des travaux de construction de 02 SDC et de latrines à EP KAOSSERE, à Individual Component A: Local 2019-06- 2019-06- 2019-07- 2019-07- 2019-08- 2019-10- 2019-09- 2019-11- 2020-01- l'EP Ticheeo Kolandi à l'EP IDA / 57180 Post Consultant Open 9,364.00 4,784.86 Signed development support 03 17 22 24 12 28 16 25 14 Tchoura-Bizili et de SDC à Selection EPB Touloum et de 2 SDC AVEC BUREAUX A L’EPP SAOTSAI.Commune de Touloum CM-CRC EXTREME NORD- 111272-CS-INDV / suivi controle des travaux de Individual Component A: Local 2019-06- 2019-06- 2019-07- 2019-07- 2019-08- 2019-10- 2019-09- 2019-12- 2019-12- construction de 01 forage à IDA / 57180 Post Consultant Open 2,034.00 1,699.43 Signed development support 03 17 22 24 12 05 16 06 15 PMH à Gai gai, à EP Selection Golonpoui et à EP Kankwa, dans la commune de Datcheka CM-CRC EXTREME NORD- 111265-CS-INDV / suivi controle des travaux de construction d'un bloc de 02 Individual Component A: Local 2019-06- 2019-06- 2019-07- 2019-07- 2019-08- 2019-10- 2019-09- 2019-12- 2019-12- salles de classe équipées et IDA / 57180 Post Consultant Open 5,988.00 4,866.93 Signed development support 03 17 22 24 12 06 16 06 15 avec un bloc de latrines à Selection trois compartiments à EP Golonpoui , EP Kankrwa et EP Guidima , dans la commune de Datcheka CM-CRC EXTREME NORD- 111236-CS-INDV / suivi controle des travaux de construction d'un bloc de Individual deux salles de classe Component A: Local 2019-06- 2019-06- 2019-07- 2019-07- 2019-08- 2019-10- 2019-09- 2019-11- 2019-12- IDA / 57180 Post Consultant Open 7,041.00 10,911.03 Signed équipées au CETIC de Vélé, development support 03 17 22 24 12 24 16 18 15 Selection au CES de Widigue (lot01), au CES de Dabaye et au CES d'Agolla, (lot02) dans la commune de Guémé CM-CRC EXTREME NORD- 111273-CS-INDV / suivi controle des travaux de construction d'un hangar 52 Individual Component A: Local 2019-06- 2019-06- 2019-07- 2019-07- 2019-08- 2019-10- 2019-09- 2019-11- 2019-12- places au marché de IDA / 57180 Post Consultant Open 2,706.00 3,058.97 Signed development support 03 17 22 24 12 23 16 05 15 Gabaraye et suivi controle Selection des travaux de construction d'un bloc de latrines au marché de Gabaraye, commune de Guémé CM-CRC EXTREME NORD- 111252-CS-INDV / suivi controle des travaux de Individual Component A: Local 2019-06- 2019-07- 2019-07- 2019-10- 2019-08- 2019-11- 2019-09- 2020-01- 2020-01- construction d'un centre de IDA / 57180 Post Consultant Open 5,098.00 3,615.78 Signed development support 03 24 22 29 12 05 16 06 14 santé intégré équipé et un Selection bloc de latrines au CSI à Nguéring, commune de Gueré CM-CRC EXTREME NORD- 111335-CS-INDV / suivi Individual controle des travaux de Component A: Local 2019-06- 2019-06- 2019-07- 2019-07- 2019-08- 2019-10- 2019-09- 2019-11- 2019-12- IDA / 57180 Post Consultant Open 1,308.00 1,678.62 Signed construction d'un bloc de 05 development support 03 17 22 24 12 23 16 05 15 Selection boutiques au marché d'Ardaf Commune de Guere CM-CRC EXTREME NORD- 111277-CS-INDV / suivi controle des travaux de Individual Component A: Local 2019-06- 2019-06- 2019-07- 2019-07- 2019-08- 2019-10- 2019-09- 2019-11- 2019-12- 2020-01- CONSTRUCTION DEUX IDA / 57180 Post Consultant Open 2,787.00 2,182.21 Completed development support 03 17 22 24 12 28 16 09 15 22 BLOCS DE CINQ (05) Selection BOUTIQUES AU MARCHÉ DE KALFOU, DANS LA COMMUNE DE KALFOU CM-CRC EXTREME NORD- 111340-CS-INDV / suivi controle des travaux de construction d'un forage Individual équipé de pompe à Component A: Local 2019-06- 2019-06- 2019-07- 2019-07- 2019-08- 2019-11- 2019-09- 2019-12- 2019-12- IDA / 57180 Post Consultant Open 2,696.00 2,375.46 Signed motricité humaine à Gandou development support 03 17 22 24 12 05 16 06 15 Selection Golopo, au CES de Zaria, à Djada, réhabilitation d'un forage PMH à Delta Guibéré et Mandara, dans la commune de Kalfou CM-CRC EXTREME NORD- 111338-CS-INDV / suivi controle des travaux de construction d'un bloc de 02 Individual salles de classe équipées et Component A: Local 2019-06- 2019-06- 2019-07- 2019-07- 2019-08- 2019-11- 2019-09- 2019-11- 2020-01- IDA / 57180 Post Consultant Open 9,791.00 82,526.23 Signed d'un bloc de latrines à development support 03 17 22 24 12 08 16 06 14 Selection troiscompartiments au CES Kamargui, à EP Goulourgou , EP Bigi, EP de Djenreng et EP Waimou commune de wina CM-CRC EXTREME NORD- 111256-CS-INDV / suivi controle des travaux de Individual Component A: Local 2019-04- 2019-06- 2019-05- 2019-07- 2019-06- 2019-10- 2019-07- 2019-11- 2019-11- construction d'un hangar de IDA / 57180 Post Consultant Open 3,051.00 3,357.24 Signed development support 01 17 20 24 10 23 15 05 12 28 places et d'une Selection boucherie au marché de Veleé, dans la commune de Guémé CM-CRC EXTREME NORD- 111346-CS-INDV / suivi controle des travaux Individual Component A: Local 2019-04- 2019-06- 2019-05- 2019-07- 2019-06- 2019-12- 2019-07- 2019-12- 2019-10- d'éclairage public à energie IDA / 57180 Post Consultant Open 762.00 923.86 Signed development support 01 17 20 24 10 05 15 06 13 solaire de 07 poteaux Selection solaires dans le centre urbain de vele Commune GUEME CM-CRC EXTREME NORD- 111351-CS-INDV / suivi controle des travaux de Individual Component A: Local Under 2019-04- 2021-01- 2019-05- 2019-06- 2019-07- 2019-10- construction de 01 forage à IDA / 57180 Post Consultant Open 1,524.00 0.00 development support Implementation 01 07 20 10 15 13 énergie solaire à CSI de Selection Bosgoye, dans la commune de Wina CM-CRC EXTREME NORD- 111361-CS-INDV / suivi controle des travaux de construction 02 salles de Individual classe et de latrines à l'EP Component A: Local 2019-04- 2019-06- 2019-05- 2019-07- 2019-06- 2019-07- 2019-07- 2019-08- 2019-10- IDA / 57180 Post Consultant Open 3,862.00 3,886.40 Signed BIJE construction de 2 development support 01 17 20 24 10 30 15 02 13 Selection salles de classeà EPPB de TOKOMBERE et equipement CES de makilingaidans la commune de Tokombere CM-CRC EXTREME NORD- 111326-CS-INDV / suivi controle des travaux de Individual construction d'un bloc de Component A: Local 2019-04- 2019-04- 2019-05- 2019-05- 2019-06- 2019-05- 2019-07- 2019-05- 2019-10- 2019-07- IDA / 57180 Post Consultant Open 2,692.00 2,517.93 Completed deux salle de classe équipés development support 01 08 20 06 10 16 15 25 13 25 Selection et d'un bloc latrines à Magala Djamene dans la commune de Darak CM-CRC EXTREME NORD- 111332-CS-INDV / suivi Individual controle des travaux de Component A: Local 2019-04- 2019-04- 2019-05- 2019-05- 2019-06- 2019-05- 2019-07- 2019-05- 2019-10- 2019-07- IDA / 57180 Post Consultant Open 762.00 839.08 Completed construction de 01 forage development support 01 08 20 07 10 16 15 21 13 17 Selection PMH à Magala Djamene, dans la commune de Darak CM-CRC EXTREME NORD- 111257-CS-INDV / suivi controle des travaux de construction d'un bloc de Individual deux salles de classe Component A: Local 2019-04- 2019-04- 2019-05- 2019-05- 2019-06- 2019-05- 2019-07- 2019-09- 2019-11- IDA / 57180 Post Consultant Open 9,077.00 10,679.58 Signed équipées et d'un bloc de development support 01 08 20 07 10 16 15 10 12 Selection latrines à trois compartiments à EP GADAFAI, au Lycée de Fotokol à EP Magadji et à EP de GUEGUERI, commune de Fotokol CM-CRC EXTREME NORD- 111345-CS-INDV / suivi Individual Component A: Local 2019-04- 2019-04- 2019-05- 2019-05- 2019-06- 2019-05- 2019-07- 2019-07- 2019-10- 2019-07- controle des travaux de IDA / 57180 Post Consultant Open 1,372.00 1,184.55 Completed development support 01 08 20 08 10 16 15 02 13 02 construction d'un magasin Selection de stockage à Goulfey CM-CRC EXTREME NORD- 111330-CS-INDV / suivi Individual controle des travaux de Component A: Local 2019-04- 2019-04- 2019-05- 2019-05- 2019-06- 2019-05- 2019-07- 2019-05- 2019-10- IDA / 57180 Post Consultant Open 1,921.00 1,687.46 Signed construction d'une mini AEP development support 01 08 20 07 10 16 15 25 13 Selection pastorale à énergie solaire à fadja commune de Hilé Alifa CM-CRC EXTREME NORD- 111342-CS-INDV / suivi controle des travaux de Individual Component A: Local 2019-04- 2019-04- 2019-05- 2019-05- 2019-06- 2019-05- 2019-07- 2019-05- 2019-10- 2019-07- construction de 01 forage IDA / 57180 Post Consultant Open 1,981.00 2,531.19 Completed development support 01 08 20 08 10 16 15 27 13 05 PMH à Michiska Mousgoum, Selection OUNANGARE et NGADA, dans la commune de Logone Birni CM-CRC EXTREME NORD- 111258-CS-INDV / suivi Individual controle des travaux de Component A: Local 2019-04- 2019-04- 2019-05- 2019-05- 2019-06- 2019-05- 2019-07- 2019-09- 2019-10- IDA / 57180 Post Consultant Open 1,921.00 2,531.19 Signed construction d'un magasin development support 01 08 20 07 10 16 15 21 13 Selection de stockage à zigague, dans la commune de Waza CM-CRC EXTREME NORD- 111356-CS-INDV / suivi Individual controle des travaux de Component A: Local 2019-04- 2019-04- 2019-05- 2019-05- 2019-06- 2019-05- 2019-07- 2019-07- 2019-10- IDA / 57180 Post Consultant Open 2,034.00 2,328.61 Signed construction d'un forage development support 01 08 20 07 10 16 15 19 13 Selection PMH à malia, NDIGUINA et MADA dans la commune de Waza CM-CRC EXTREME NORD- 83186-CS-INDV / Sélection d'un consultant pour l'élaboration des Etudes de Individual Component A: Local 2018-10- 2018-12- 2018-12- 2019-01- 2019-03- faisabilité techniques et IDA / 57180 Post Consultant Open 1,400.00 0.00 Canceled development support 15 03 24 28 14 environnementales des MP Selection de Construction d'un centre multimédia à Dziguilao dans la Commune de Dziguilao CM-CRC EXTREME NORD- 111318-CS-INDV / suivi controle des travaux de Individual Component A: Local 2019-06- 2019-11- 2019-07- 2019-08- 2019-09- 2019-11- construction d'un forage IDA / 57180 Post Consultant Open 610.00 0.00 Canceled development support 03 25 22 12 16 15 équipé de pompe à Selection motricité humaine a Djafgadjie, commue de yagoua CM-CRC EXTREME NORD- 111349-CS-INDV / suivi controle des travaux de construction D’UN BLOC DE Individual Component A: Local 2019-06- 2019-11- 2019-07- 2019-08- 2019-09- 2020-01- DEUX SALLES DE CLASSE IDA / 57180 Post Consultant Open 3,871.00 0.00 Canceled development support 03 25 22 12 16 14 AVEC BUREAUX EQUIPES au Selection CES de DJOGOIDI et au lycee de Vounaloum Commune de yagoua CM-CRC EXTREME NORD- 111370-CS-INDV / Sélection d'un consultant pour l'élaboration des Individual Component A: Local 2018-10- 2019-11- 2018-12- 2018-12- 2019-01- 2019-02- Etudes de faisabilité IDA / 57180 Post Consultant Open 2,200.00 0.00 Canceled development support 15 25 03 24 28 27 techniques et Selection environnementales de CONSTRUCTION D'UN BLOC DE MATERNITÉ ÉQUIPÉ AU CMA DE GAZAWA CM-CRC EXTREME NORD- 111234-CS-INDV / Sélection d'un consultant pour l'élaboration des Individual Component A: Local 2019-01- 2020-01- 2019-02- 2019-03- 2019-04- 2019-05- Etudes de faisabilité IDA / 57180 Post Consultant Open 1,000.00 0.00 Canceled development support 02 06 20 13 17 17 techniques et Selection environnementales d'un microprojet de construction d'un parc à bétail dans la commune de WINA CM-CRC EXTREME NORD- 111353-CS-INDV / suivi controle des travaux de Individual construction d'un CSI équipé Component A: Local 2019-06- 2020-03- 2019-07- 2019-08- 2019-09- 2020-01- IDA / 57180 Post Consultant Open 6,096.00 0.00 Canceled avec case d'astreinte, un development support 03 04 22 12 16 14 Selection incinérateur et un bloc de latrines au CSI Djiddeo Garre, dans la commune de Maroua 3 CM-CRC EXTREME NORD- 111235-CS-INDV / Sélection d'un consultant pour l'élaboration des Etudes de faisabilité Individual Component A: Local 2019-04- 2020-03- 2019-05- 2019-06- 2019-07- 2019-08- techniques et IDA / 57180 Post Consultant Open 2,400.00 0.00 Canceled development support 01 04 20 10 15 29 environnementales de Selection construction d'un forage agricole à énergie solaire à Doumer et d'un construction d'un forage à énergie solaire à Djaodé CM-CRC EXTREME NORD- 111344-CS-INDV / suivi controle des travaux de Individual Component A: Local 2019-06- 2020-03- 2019-07- 2019-08- 2019-09- 2019-11- construction d'un forage IDA / 57180 Post Consultant Open 615.00 0.00 Canceled development support 03 04 22 12 16 15 équipé de PMH à lycee Selection bilingue dans la commue de Kaele CM-CRC EXTREME NORD- 111350-CS-INDV / suivi controle des travaux de Individual Component A: Local 2019-06- 2021-01- 2019-07- 2019-08- 2019-09- 2019-12- construction d’un forage à IDA / 57180 Post Consultant Open 1,178.00 0.00 Canceled development support 03 06 22 12 16 15 énergie solaire avec château Selection au centre de santé de Djiddéo, dans la commune de Maroua 3 CM-CRC EXTREME NORD- 111357-CS-INDV / suivi Individual Component A: Local 2019-04- 2020-03- 2019-05- 2019-06- 2019-07- 2019-10- controle des travaux de IDA / 57180 Post Consultant Open 1,000.00 0.00 Canceled development support 01 04 20 10 15 13 réalisation d'un parc à bétail Selection dans la commune de Wina (GP) CM-CRC EXTREME NORD- 111347-CS-INDV / suivi controle des travaux de Individual Component A: Local 2019-06- 2020-03- 2019-07- 2019-08- 2019-09- 2019-11- construction d'un forage IDA / 57180 Post Consultant Open 630.00 0.00 Canceled development support 03 04 22 12 16 15 équipé de pompe à Selection motricité humaine à Bindiriel Danghou, commue de Tchatibali CM-CRC EXTREME NORD- 196621-CS-INDV / Suivi controle des travaux de Individual Construction d'un CSI Component A: Local Under 2020-10- 2021-01- 2020-12- 2021-01- 2021-02- 2021-06- IDA / 57180 Post Consultant Open 4,838.00 0.00 équipé avec un incinérateur development support Implementation 30 06 27 17 21 21 Selection et un bloc de latrines au CSI Djiddeo Garre, dans la commune de Maroua 3 CM-CRC EXTREME NORD- 196857-CS-INDV / Suivi controle des travaux de Individual Construction et équipement Component A: Local Under 2020-10- 2020-11- 2020-11- 2020-12- 2021-01- 2021-04- IDA / 57180 Post Consultant Direct 1,829.00 0.00 des blocs des salles de development support Implementation 30 26 18 09 13 13 Selection classes et d'un bloc de latrines au CES de GUINADJI Commune de Maroua III CM-CRC EXTREME NORD- 196547-CS-INDV / Suivi controle des travaux de Construction D’UN FORAGE Individual Component A: Local Under 2020-10- 2021-01- 2020-12- 2021-01- 2021-02- 2021-05- PASTORAL A ENERGIE IDA / 57180 Post Consultant Open 1,662.00 0.00 development support Implementation 30 06 27 17 21 22 SOLAIRE EQUIPE D’UN Selection FORAGE ET DE (02) ABREUVOIRS DANS LA LOCALITE DE DJONGDONG, COMMUNE DE WINA, CM-CRC EXTREME NORD- 196622-CS-INDV / Suivi controle des travaux de CONSTRUCTION D’UN Individual Component A: Local Under 2020-10- 2021-01- 2020-12- 2021-01- 2021-02- 2021-05- FORAGE PASTORAL A IDA / 57180 Post Consultant Open 1,600.00 0.00 development support Implementation 30 06 27 17 21 22 ENERGIE SOLAIRE EQUIPE Selection D’UN château ET DE (02) ABREUVOIRS DANS LA LOCALITE DEMIZILING WAILA MAYO, COMMUNE DE GAZAWA CM-CRC EXTREME NORD- 196544-CS-INDV / Suivi controle des travaux deTravaux d'Eclairage public Individual Component A: Local Under 2020-10- 2021-01- 2020-12- 2021-01- 2021-02- 2021-05- en énergie solaire de 10 IDA / 57180 Post Consultant Open 3,566.00 0.00 development support Implementation 30 06 27 17 21 22 poteaux à Ndoukoula de 14 Selection poteaux à Dagaï Kola et de 15 poteaux à Loulou Commune de Ndoukoula Page 13 CM-CRC EXTREME NORD- 196628-CS-INDV / Suivi controle des travaux de Individual Component A: Local 2020-10- 2020-11- 2020-12- 2021-01- 2021-02- 2021-05- Construction d'un bloc de IDA / 57180 Post Consultant Open 1,752.00 0.00 Canceled development support 30 26 18 08 12 13 deux salles de classe Selection équipées au lycee de Goundaye Commune de Dziguilao. CM-CRC EXTREME NORD- 196564-CS-INDV / Suivi controle des travaux de Individual Component A: Local Under 2020-10- 2021-01- 2020-12- 2021-01- 2021-02- 2021-05- Construction d'un bloc de IDA / 57180 Post Consultant Open 1,805.00 0.00 development support Implementation 30 06 27 17 21 22 deux salles de classe Selection équipées à l'EP de ZANYAO Commune de YAGOUA CM-CRC EXTREME NORD- 196526-CS-INDV / Suivi controle des travaux de construction d’un forage Individual Component A: Local Under 2020-10- 2021-01- 2020-12- 2021-01- 2021-02- 2021-05- équipé de pompe à IDA / 57180 Post Consultant Open 3,238.00 0.00 development support Implementation 30 06 27 17 21 22 motricité humaine à Dinao, Selection Louggol palé, Kodadjiho, Hamadalao et Golombeswé Commune KALFOU CM-CRC EXTREME NORD- 196638-CS-INDV / Suivi controle des travaux de Individual Component A: Local Under 2020-10- 2021-01- 2020-12- 2021-01- 2021-02- 2021-05- Construction d'un forage IDA / 57180 Post Consultant Open 1,295.00 0.00 development support Implementation 30 06 27 17 21 22 équipé de PMH à douang et Selection dingue-Gabaraye Commune de Gueme CM-CRC EXTREME NORD- 196889-CS-INDV / Suivi controle des travaux d'eclairage public par la Individual Component A: Local Under 2020-10- 2021-01- 2020-12- 2021-01- 2021-02- 2021-02- fourniture et l'installation de IDA / 57180 Post Consultant Open 1,295.00 0.00 development support Implementation 30 06 18 08 12 21 12 poteaux solaires de l’axe Selection Sous-préfecture- Ngaoundéréo Commune de Kalfou CM-CRC EXTREME NORD- 196540-CS-INDV / Suivi controle des travaux de Construction d'un bloc de deux salle de classe Individual Component A: Local Under 2020-10- 2021-01- 2020-12- 2021-01- 2021-02- 2021-05- équipées à l'EPB DE MADA IDA / 57180 Post Consultant Open 3,810.00 0.00 development support Implementation 30 06 27 17 21 22 KOLKOCH ET A LEP Selection MAMBEZA et Construction d'un bloc de latrines à l'EPB DE MADA KOLKOCH ET Commune de Tokombere CM-CRC EXTREME NORD- 196623-CS-INDV / Suivi controle des TRAVAUX D’AMENAGEMENT D’UNE GARE ROUTIERE PAR LA Individual Component A: Local Under 2020-10- 2021-01- 2020-12- 2021-01- 2021-02- 2021-05- CONSTRUCTION DE 04 IDA / 57180 Post Consultant Open 3,810.00 0.00 development support Implementation 30 06 27 17 21 22 GUICHETS, 04 MAGASINS, Selection D’UN HANGAR D’ATTENTE ET D’UN BLOC LATRINE AVEC UN MUR D’ENCEINTE COMMUNE DE YAGOUA CM-CRC EXTREME NORD- 196853-CS-INDV / Suivi contrôle de la fourniture en Individual en equipement en 200 Component A: Local 2020-10- 2020-11- 2020-11- 2020-12- 2021-01- 2021-04- IDA / 57180 Post Consultant Direct 445.00 0.00 Canceled tables bancs, 4 bureaux, 4 development support 30 30 18 09 13 13 Selection chaises rembourées et 4 armoires à l'EP MAGA IIB Commune de Maga. CM-CRC EXTREME NORD- 196553-CS-INDV / Suivi controle des travaux Individual d'Eclairage public par la Component A: Local Under 2020-10- 2021-01- 2020-12- 2021-01- 2021-02- 2021-05- IDA / 57180 Post Consultant Open 1,000.00 0.00 fourniture et l'installation de development support Implementation 30 06 27 17 21 22 Selection 3 poteaux solaires à Ouro Bone et 03 à Modjombodi Commune de Mindif CM-CRC EXTREME NORD- 196619-CS-INDV / Suivi Individual controle des travaux de Component A: Local Under 2020-10- 2021-01- 2020-12- 2021-01- 2021-02- 2021-04- IDA / 57180 Post Consultant Open 1,000.00 0.00 Construction d’un forage development support Implementation 30 06 27 17 21 22 Selection PMH au centre de santé de Djiddéo Commune de Maroua III CM-CRC EXTREME NORD- 196626-CS-INDV / Suivi Individual controle des travaux de Component A: Local Under 2020-10- 2021-01- 2020-12- 2021-01- 2021-02- 2021-04- IDA / 57180 Post Consultant Open 1,000.00 0.00 Construction d'un forage development support Implementation 30 06 27 17 21 22 Selection équipé de PMH de Yonkolel Commune de Dargala. CM-CRC EXTREME NORD- 196535-CS-INDV / Suivi controle des travaux de Construction d'un forage Individual Component A: Local Under 2020-10- 2021-01- 2020-12- 2021-01- 2021-02- 2021-04- équipé de PMH à lalepaki et IDA / 57180 Post Consultant Open 1,000.00 0.00 development support Implementation 30 06 27 17 21 22 Acquisition d’une caisse à Selection outils pour l’entretien des forages dans la commune de Commune de Touloum CM-CRC EXTREME NORD- 196576-CS-INDV / Suivi controle des travaux de Individual fourniture et installation Component A: Local Under 2020-10- 2020-11- 2020-12- 2021-01- 2021-02- 2021-02- IDA / 57180 Post Consultant Open 1,000.00 0.00 d’un kit solaire pour development support Implementation 30 25 27 17 21 27 Selection l’alimentation en energie électrique du lycée de gabaraye. Commune Gueme. CM-CRC EXTREME NORD- 196627-CS-INDV / Suivi controle des travaux de Individual Component A: Local Under 2020-10- 2021-01- 2020-12- 2021-01- 2021-02- 2021-04- Construction d'un forage IDA / 57180 Post Consultant Open 1,000.00 0.00 development support Implementation 30 06 27 17 21 22 équipé de pompe à Selection motricité humaine à Guermé Kalfou Commune de Kalfou CM-CRC EXTREME NORD- 196845-CS-INDV / Suivi contrôle de la fourniture en Equipement en 60 tables Individual Component A: Local 2020-10- 2020-11- 2020-11- 2020-12- 2021-01- 2021-04- bancs et un bureau à l'EP IDA / 57180 Post Consultant Direct 1,000.00 0.00 Canceled development support 30 26 18 09 13 13 Guinlaye et 111 tables Selection bancs et un bureau à l'EP BOGO SIRATARE I Commune de BOGO CM-CRC EXTREME NORD- 204438-CS-INDV / Elaboration des Etudes de faisabilité techniques et Individual environnementales des MP Component A: Local Pending 2020-11- 2020-11- 2020-12- 2021-01- 2021-03- IDA / 62240 Post Consultant Limited 3,800.00 0.00 de Construction de salles de development support Implementation 16 21 12 16 02 Selection classe équipées dans le complexe d'écoles publiques Grpe 1, 2, 3 et 4 de Fotokol, commune fotokol. CM-CRC EXTREME NORD- 204457-CS-INDV / Elaboration des Etudes de faisabilité techniques et Individual Component A: Local 2020-11- 2020-11- 2020-11- 2020-12- 2021-01- 2021-03- environnementales des MP IDA / 62240 Post Consultant Limited 4,200.00 0.00 Under Review development support 16 13 21 12 16 02 de travaux Rénovation et Selection équipement du CMA de Fotokol Commune de FOTOKOL CM-CRC EXTREME NORD- 204439-CS-INDV / Elaboration des Etudes de faisabilité des MP de Individual Construction d’un forage Component A: Local Pending 2020-11- 2020-11- 2020-12- 2021-01- 2021-03- IDA / 62240 Post Consultant Limited 3,400.00 0.00 équipé de pompe à development support Implementation 16 21 12 16 02 Selection motricité humaine à Mada (Ngroh), à Goura 2, à Labado, à Chou et réhabilitation d’un forage à Mada 1 Commune de Makary CM-CRC EXTREME NORD- 204435-CS-INDV / Elaboration des Etudes de Individual faisabilité techniques et Component A: Local Pending 2020-11- 2020-11- 2020-12- 2021-01- 2021-01- IDA / 62240 Post Consultant Limited 2,200.00 0.00 environnementales des MP development support Implementation 16 21 12 16 19 Selection de Construction d’une mini AEP au camp des réfugiés d’Afadé Commune de Makary CM-CRC EXTREME NORD- 204447-CS-INDV / Elaboration des Etudes de faisabilité techniques et environnementales des MP Individual Component A: Local Pending 2020-11- 2020-11- 2020-12- 2021-01- 2021-03- de Construction d’un bloc IDA / 62240 Post Consultant Limited 2,400.00 0.00 development support Implementation 16 21 12 16 02 de deux salles de classe Selection équipées avec bloc latrines à l’EP de Djamous à l’EP BODO (1 ET 2) et à l'EP BIAMO Commune de Makary CM-CRC EXTREME NORD- 204456-CS-INDV / Elaboration des Etudes de faisabilité des MP de Construction d’un bloc de Individual Component A: Local Pending 2020-11- 2020-11- 2020-12- 2021-01- 2021-03- deux salles de classe IDA / 62240 Post Consultant Limited 3,000.00 0.00 development support Implementation 16 21 12 16 02 équipées dans les EP gpe Selection 1A, 1B et Construction d’un bloc maternel à l’école maternelle de Logone Birni Commune de Logone Birni CM-CRC EXTREME NORD- 204441-CS-INDV / Elaboration des Etudes de faisabilité techniques et Individual environnementales des MP Component A: Local Pending 2020-11- 2020-11- 2020-12- 2021-01- 2021-03- IDA / 62240 Post Consultant Limited 3,000.00 0.00 de Construction et development support Implementation 16 21 12 16 02 Selection équipement d’une salle d’hospitalisation et bloc opératoire au CMA de Logone birni Commune de Logone Birni CM-CRC EXTREME NORD- 204443-CS-INDV / Elaboration des Etudes de faisabilité techniques et Individual Component A: Local Pending 2020-11- 2020-11- 2020-12- 2021-01- 2021-03- environnementales des MP IDA / 62240 Post Consultant Direct 1,600.00 0.00 development support Implementation 16 26 17 21 07 d'Equipement et fourniture Selection de médicaments aux CSI de Zizagué et CSI de Waza Commune de waza CM-CRC EXTREME NORD- 204436-CS-INDV / Elaboration des Etudes de faisabilité techniques et Individual Component A: Local Pending 2020-11- 2020-11- 2020-12- 2021-01- 2021-03- environnementales des MP IDA / 62240 Post Consultant Limited 1,600.00 0.00 development support Implementation 16 21 12 16 02 de Construction d’un forage Selection équipé de PMH à Tagawa Y/C etude complementaire Commune de Waza CM-CRC EXTREME NORD- 204381-CS-INDV / Elaboration des Etudes de Individual faisabilité techniques et Component A: Local Pending 2020-11- 2020-11- 2020-12- 2021-01- 2021-03- IDA / 62240 Post Consultant Limited 1,600.00 0.00 environnementales des MP development support Implementation 16 21 12 25 11 Selection d'Alimentation en énergie solaire du CSI de Kossa Commune de Mora CM-CRC EXTREME NORD- 204454-CS-INDV / Elaboration des Etudes de faisabilité techniques et Individual Component A: Local Pending 2020-11- 2020-11- 2020-12- 2021-01- 2021-03- environnementales des MP IDA / 62240 Post Consultant Direct 1,300.00 0.00 development support Implementation 16 26 17 21 07 de Equipement et fourniture Selection de médicaments au CSI de Kossa et au CSI de Méhé Emma Commune de Mora CM-CRC EXTREME NORD- 204455-CS-INDV / Elaboration des Etudes de faisabilité techniques et Individual environnementales des MP Component A: Local Pending 2020-11- 2020-11- 2020-12- 2021-01- 2021-03- IDA / 62240 Post Consultant Limited 2,900.00 0.00 de Construction d’un forage development support Implementation 16 21 12 16 02 Selection équipé de PMH à Yémé, Dandaya, à Koldima, Madina et au Camp des réfugiés de Méhé Emma Commune de Mora CM-CRC EXTREME NORD- 204445-CS-INDV / Elaboration des Etudes de faisabilité techniques et Individual Component A: Local Pending 2020-11- 2020-11- 2020-12- 2021-01- 2021-03- environnementales des MP IDA / 62240 Post Consultant Limited 2,200.00 0.00 development support Implementation 16 21 12 16 02 de Construction d’un bloc Selection de deux salles équipées à l’EP d’Igawa et kotcherehe Commune de Mora CM-CRC EXTREME NORD- 204444-CS-INDV / Elaboration des Etudes de faisabilité techniques et Individual environnementales des MP Component A: Local Pending 2020-11- 2020-11- 2020-12- 2021-01- 2021-03- IDA / 62240 Post Consultant Limited 3,600.00 0.00 Construction d’un bloc de development support Implementation 16 21 12 16 02 Selection 02 salles de classe à EPB Kosséhone, à EP NDROCK Tourou, EP de Wandaï Commune de Mokolo CM-CRC EXTREME NORD- 204458-CS-INDV / suivi- contrôle des travaux de Individual construction d’un bloc de Component A: Local Under 2020-11- 2021-01- 2020-12- 2020-12- 2021-01- 2021-05- IDA / 62240 Post Consultant Limited 2,285.71 0.00 deux salles de classe development support Implementation 26 06 01 22 26 26 Selection équipées avec bloc latrines à à l’EP d’Afadé Groupe 2 Commune Makary CM-CRC EXTREME NORD- 204386-CS-INDV / Elaboration des Etudes de Individual faisabilité techniques et Component A: Local Pending 2020-11- 2020-11- 2020-12- 2021-01- 2021-02- IDA / 62240 Post Consultant Limited 1,800.00 0.00 environnementales des MP development support Implementation 16 21 05 09 23 Selection de Construction d'un bloc de CSI au CSI de kossehone Commune de Mokolo CM-CRC EXTREME NORD- 204453-CS-INDV / Elaboration des Etudes de faisabilité techniques et Individual Component A: Local Pending 2020-11- 2020-11- 2020-12- 2021-01- 2021-03- environnementales des MP IDA / 62240 Post Consultant Limited 2,600.00 0.00 development support Implementation 16 21 12 16 02 deConstruction de 01 Selection forage à Zamai, à EP FERDE, à Kosséhone et à Ldendeng Commune de Mokolo CM-CRC EXTREME NORD- 196625-CS-INDV / Suivi Individual contrôle de la fourniture en Component A: Local 2020-10- 2020-11- 2020-12- 2021-01- 2021-02- 2021-04- IDA / 57180 Post Consultant Open 1,000.00 0.00 Canceled en Équipement en matériel development support 30 25 27 17 21 22 Selection médicaux au CSI de Takreo yoldeo Commune Kar Hay CM-CRC EXTREME NORD- 196620-CS-INDV / Suivi controle des travaux de Individual Component A: Local 2020-10- 2020-11- 2020-12- 2021-01- 2021-02- 2021-04- REALISATION D’UN FORAGE IDA / 57180 Post Consultant Open 1,000.00 0.00 Canceled development support 30 25 27 17 21 22 EQUIPE DE POMPE A Selection MOTRICITE HUMAINE A Dolgaye Commune Kar Hay CM-CRC EXTREME NORD- 222830-CS-INDV / Sélection d'un consultant pour l'élaboration des Individual Etudes de faisabilité Component A: Local Pending 2021-04- 2021-05- 2021-06- 2021-07- 2021-09- IDA / 62240 Post Consultant Open 3,600.00 0.00 techniques et development support Implementation 08 27 17 22 05 Selection environnementales des MP d'Alimentation en énergie solaire au CMA de de Fotokol Commune de Fotokol (A101201) CM-CRC EXTREME NORD- 222746-CS-INDV / Sélection d'un consultant pour l'élaboration des Individual Etudes de faisabilité Component A: Local Pending 2021-04- 2021-05- 2021-06- 2021-07- 2021-09- IDA / 62240 Post Consultant Open 3,600.00 0.00 techniques et development support Implementation 08 27 17 22 05 Selection environnementales des MP de construct d’une mini AEP au cma de Logone birni Commune de Logone birni (A101201) CM-CRC EXTREME NORD- 222774-CS-INDV / Sélection d'un consultant pour l'élaboration des Individual Etudes de faisabilité Component A: Local Pending 2021-04- 2021-05- 2021-06- 2021-07- 2021-09- IDA / 62240 Post Consultant Open 3,000.00 0.00 techniques et development support Implementation 08 27 17 22 05 Selection environnementales des MP d'Alimentation en énergie solaire au cma de Logone birni Commune de Logone birni (A101201) Page 14 CM-CRC EXTREME NORD- 222796-CS-INDV / Sélection d'un consultant pour l'élaboration des Individual Etudes de faisabilité Component A: Local Pending 2021-04- 2021-05- 2021-06- 2021-07- 2021-09- IDA / 62240 Post Consultant Open 1,300.00 0.00 techniques et development support Implementation 08 27 17 22 05 Selection environnementales des MP construct d’un bloc de 02 salles de classe à EP mokola djavdjaya Commune de Mokolo (A101201) CM-CRC EXTREME NORD- 222805-CS-INDV / Sélection d'un consultant pour l'élaboration des Individual Etudes de faisabilité Component A: Local Pending 2021-04- 2021-05- 2021-06- 2021-07- 2021-09- IDA / 62240 Post Consultant Open 1,800.00 0.00 techniques et development support Implementation 08 27 17 22 05 Selection environnementales des MP deconstruct de 01 forage À Zamai, à ferdé et Ldendeng Commune de Mokolo (A101201) CM-CRC EXTREME NORD- 222751-CS-INDV / suivi controle des travaux de Individual Component A: Local Pending 2021-04- 2021-05- 2021-06- 2021-07- 2021-11- construct et équipement IDA / 62240 Post Consultant Open 6,095.00 0.00 development support Implementation 08 27 17 22 19 d’une salle d’hospitalisation Selection et d'un bloc opératoire au CMA de Logone birni CM-CRC EXTREME NORD- 222781-CS-INDV / suivi controle des travaux de construct d’1 bloc maternel Individual et latrines à EM Logone Component A: Local Pending 2021-04- 2021-05- 2021-06- 2021-07- 2021-11- IDA / 62240 Post Consultant Open 5,940.00 0.00 birni et Réhabilitation de 6 development support Implementation 08 27 17 22 19 Selection salles de classe avec bureau attenant et équipement a EP Logone birni GPE 1 A Commune de Logone birni CM-CRC EXTREME NORD- 222801-CS-INDV / suivi controle des travaux de Individual Component A: Local Pending 2021-04- 2021-05- 2021-06- 2021-07- 2022-01- construct et équipement IDA / 62240 Post Consultant Open 6,095.00 0.00 development support Implementation 08 27 17 22 18 d’une salle d’hospitalisation Selection et d'un bloc opératoire au CMA de Fotokol CM-CRC EXTREME NORD- 222786-CS-INDV / suivi controle des travaux de construct de 4 salles de Individual classe équipées avec 2 Component A: Local Pending 2021-04- 2021-05- 2021-06- 2021-07- 2021-11- IDA / 62240 Post Consultant Open 9,145.00 0.00 bureau à EP Fotokol et development support Implementation 08 27 17 22 19 Selection construct de 4 salles de classe équipées avec 2 bureau et de 3 blocs de latrines à EP Fotokol Commune de Fotokol CM-CRC EXTREME NORD- 222787-CS-INDV / suivi controle des travaux de construct de deux blocs de deux salles de classe Individual Component A: Local Pending 2021-04- 2021-05- 2021-06- 2021-07- 2021-11- équipées, d'un bloc de deux IDA / 62240 Post Consultant Open 6,505.00 0.00 development support Implementation 08 27 17 22 19 salles de classe équipées Selection avec bureau pour enseignants et d'un bloc latrines a trois compartiments à EP de BIAMO Commune de Makary CM-CRC EXTREME NORD- 222777-CS-INDV / suivi controle des construct de 6 SDC équipées avec bureau et latrines à EP de BIAMO Individual Component A: Local Pending 2021-04- 2021-05- 2021-06- 2021-07- 2021-11- construct de 2 SDC avec IDA / 62240 Post Consultant Open 4,910.00 0.00 development support Implementation 08 27 17 22 19 bureau a EP GRP 2 de BODO, Selection construct de 2 SDC avec bureau et latrines a EP de DJAMOUS Commune de Makary CM-CRC EXTREME NORD- 222823-CS-INDV / suivi controle des travaux de construct d’un forage Individual équipé de pompe à Component A: Local Pending 2021-04- 2021-05- 2021-06- 2021-07- 2021-08- IDA / 62240 Post Consultant Open 2,925.00 0.00 motricité humaine à Mada development support Implementation 08 27 17 22 03 Selection (Ngroh), à Goura 2 (Mosquée), à Labado, à Chou et réhabilitation d’un forage à Mada 1 (quartier Sara) Commune de Makary CM-CRC EXTREME NORD- 222826-CS-INDV / suivi Individual controle des travaux de Component A: Local Pending 2021-04- 2021-05- 2021-06- 2021-07- 2021-11- IDA / 62240 Post Consultant Open 1,520.00 0.00 construct d’une mini AEP au development support Implementation 08 27 17 22 19 Selection camp des réfugiés d’Afadé Commune de Makary CM-CRC EXTREME NORD- 222762-CS-INDV / suivi Individual controle des travaux de Component A: Local Pending 2021-04- 2021-05- 2021-06- 2021-07- 2021-10- IDA / 62240 Post Consultant Open 1,000.00 0.00 construct d’un forage development support Implementation 08 27 17 22 20 Selection équipé de PMH à Tagawa Commune de Waza CM-CRC EXTREME NORD- 222808-CS-INDV / suivi controle des travaux de réalisation d’un forage productif équipé de pompe Individual à motricité humaine dans Component A: Local Pending 2021-04- 2021-05- 2021-06- 2021-07- 2021-11- IDA / 62240 Post Consultant Open 3,875.00 0.00 les localités de : YEME, development support Implementation 08 27 17 22 19 Selection DANDAYA, KOLDIMA, MADJINA et MEHE EMMA (Camp refugié) dans la Commune de Mora, Département du Mayo Sava. CM-CRC EXTREME NORD- 222824-CS-INDV / suivi controle des de construct d’1 logement d'astreint et Individual d'un mur de cloture à l’EP Component A: Local Pending 2021-04- 2021-05- 2021-06- 2021-07- 2021-11- IDA / 62240 Post Consultant Open 7,930.00 0.00 IGAWA MEME,et de development support Implementation 08 27 17 22 19 Selection construct de 4 salles de classe équipées avec 1 bureau attenant et de latrines à l’EP de KOTCHEREHE Commune de Mora CM-CRC EXTREME NORD- 222799-CS-INDV / SUIVI CONTROLE DES TRAVAUX DE construct D’UN BLOC DE DEUX SALLES DE CLASSE EQUIPEES AVEC BUREAU ET Individual Component A: Local Pending 2021-04- 2021-05- 2021-06- 2021-07- 2021-11- D’UN BLOC LATRINE A IDA / 62240 Post Consultant Open 7,575.00 0.00 development support Implementation 08 27 17 22 19 TROIS COMPARTIMENTS A Selection L’EPB DE KOSSEHONE, L'EP WANDAI ET L'EP NDROCK DANS LA COMMUNE DE MOKOLO, DEPARTEMENT DU MAYO-TSANAGA. CM-CRC EXTREME NORD- 222768-CS-INDV / Suivi contrôle des travaux de Individual construct de 01 forage à Component A: Local Pending 2021-04- 2021-05- 2021-06- 2021-07- 2021-11- IDA / 62240 Post Consultant Open 2,685.00 0.00 Zamai, à Ldagodja-Tourou, development support Implementation 08 27 17 22 19 Selection à Ngolkodjala-Kosséhone et à Wandaï-djamboutou Commune de Mokolo CM-CRC EXTREME NORD- 222737-CS-INDV / SUIVI CONTROLE DES TRAVAUX DE construct ET Individual Component A: Local Pending 2021-04- 2021-05- 2021-06- 2021-07- 2021-11- EQUIPEMENT DU CENTRE DE IDA / 62240 Post Consultant Open 6,095.00 0.00 development support Implementation 08 27 17 22 19 SANTE INTEGRE A Selection KOSSEHONE DANS LA COMMUNE DE MOKOLO, DEPARTEMENT DU MAYO- TSANAGA. CM-CRC EXTREME NORD- 222987-CS-INDV / Suivi contrôle des Travaux de Individual Component A: Local Pending 2021-05- 2021-06- 2021-07- 2021-08- 2021-10- Construction de 01 forage IDA / 57180 Post Consultant Open 1,371.00 0.00 development support Implementation 05 23 14 18 17 à énergie solaire au CSI de Selection hile haoussa, dans la commune de kousseri (A2031C1) CM-CRC EXTREME NORD- 228207-CS-INDV / Suivi contrôle des travaux de Individual construction d'un bloc Component A: Local Pending 2021-05- 2021-06- 2021-07- 2021-08- 2021-10- IDA / 62240 Post Consultant Open 1,000.00 0.00 latrines a troix development support Implementation 05 23 14 18 17 Selection compartiement et construction d'un incinerateur au CSI de hile haoussa dans la Commune de kousseri CM-CRC EXTREME NORD- 222755-CS-INDV / suivi controle des travaux de FOURNITURE ET Individual INSTALLATION D’UNE MINI Component A: Local Pending 2021-06- 2021-07- 2021-08- 2021-09- 2022-01- IDA / 62240 Post Consultant Open 2,275.00 0.00 CENTRALE SOLAIRE AU CSI development support Implementation 01 20 10 14 12 Selection DE KOSSA, DANS LA COMMUNE DE MORA, DEPARTEMENT DU MAYO- SAVA, REGION DE L’EXTREME – NORD. Page 15 PROCUREMENT PLAN (Textual Part) Project information: [Sudan] [Sudan Family Support Program] (SFSP) (P173521) Project Implementation agency: [Ministry of Finance & Economic Planning/ PIU] Date of the Procurement Plan: [31/08/2020] Period covered by this Procurement Plan: [18 Month] Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in [Sudan procurement contracting and disposal of assets law 2010], such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. [Applicable as provide in section 5 paragraph 5.3 to 5.6 of procurement REGULATION for IPF Borrowers] When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: [is not applicable is for those contracts identified in the Procurement Plan tables]; Works: [is not applicable for those contracts identified in the Procurement Plan tables] Other Relevant Procurement Information. [N/A] PROCUREMENT Sudan : Sudan Family Support Project PLAN General Information Country: Sudan Bank’s Approval Date of the Original Procurement Plan: 2020-11-22 2021-05-17 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P173521 GPN Date: Project Name: Sudan Family Support Project Loan / Credit No: IDA / D7350 Ministry of Finance and Economic Planning Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SD-MOWSS-202443-GO-RFQ Component 2: Establish Pending Request for Single Stage - One / ICT Hardware / USSD IDA / D7350 Delivery Systems and Build Post Limited 190,000.00 0.00 Implementati 2020-11-06 2021-01-01 2021-06-30 Quotations Envelope Gateway Institutional Capacity on SD-MOWSS-202446-GO-RFQ Component 2: Establish Pending Request for Single Stage - One / Laptops for physical IDA / D7350 Delivery Systems and Build Post Limited 125,000.00 0.00 Implementati 2020-11-06 2021-01-01 2021-06-30 Quotations Envelope Registration Institutional Capacity on SD-MOWSS-202448-GO-RFQ Component 2: Establish Pending Request for Single Stage - One / Tablets for physical IDA / D7350 Delivery Systems and Build Post Limited 60,000.00 0.00 Implementati 2020-11-06 2021-01-01 2021-06-30 Quotations Envelope registration Institutional Capacity on SD-MOWSS-202449-GO-RFQ Component 2: Establish Pending Request for Single Stage - One / Rent bandwidth for USSD IDA / D7350 Delivery Systems and Build Post Limited 3,000.00 0.00 Implementati 2020-11-06 2021-01-01 2021-06-30 Quotations Envelope (three Telcos) Institutional Capacity on Component 2: Establish Pending SD-MOWSS-202639-GO-RFQ Request for Single Stage - One IDA / D7350 Delivery Systems and Build Post Limited 10,000.00 0.00 Implementati 2020-11-09 2021-01-04 2021-07-03 / CRM Software Quotations Envelope Institutional Capacity on SD-MOWSS-202640-GO-RFQ Component 2: Establish Pending Request for Single Stage - One / Vehicle for Mobile IDA / D7350 Delivery Systems and Build Post Limited 1,375,000.00 0.00 Implementati 2020-11-09 2021-01-04 2021-07-03 Quotations Envelope registration Institutional Capacity on SD-MOWSS-202642-GO-RFQ Component 2: Establish Pending Request for Single Stage - One / Satellite Communication for IDA / D7350 Delivery Systems and Build Post Open - International 125,000.00 0.00 Implementati 2020-11-09 2021-01-04 2021-07-03 Quotations Envelope registration vehicles Institutional Capacity on Component 2: Establish Under SD-MOFEP-235901-GO-RFB Single Stage - One IDA / D7350 Delivery Systems and Build Post Request for Bids Open - National 750,000.00 0.00 Implementati 2021-05-24 2021-05-30 2021-05-30 2021-07-15 2021-07-21 2021-07-29 2021-08-15 / Supply of Tablets Envelope Institutional Capacity on Component 2: Establish Pending SD-MOFEP-236095-GO-RFQ Request for Single Stage - One IDA / D7350 Delivery Systems and Build Post Limited 100,000.00 0.00 Implementati 2021-07-05 2021-08-30 2022-02-26 / Supply of tablets Quotations Envelope Institutional Capacity on NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 3: Project Pending SD-MOWSS-202694-NC-RFQ Request for Single Stage - One IDA / D7350 Management, Monitoring and Post Limited 11,000.00 0.00 Implementati 2020-11-09 2021-01-04 2021-07-03 / Office furniture Quotations Envelope Evaluation, and Learning on Component 3: Project Pending SD-MOWSS-202703-NC-RFQ Request for Single Stage - One IDA / D7350 Management, Monitoring and Post Limited 5,000.00 0.00 Implementati 2020-11-09 2021-01-04 2021-07-03 / Software Packages Quotations Envelope Evaluation, and Learning on Component 2: Establish Pending SD-MOWSS-202704-NC-RFQ Request for Single Stage - One IDA / D7350 Delivery Systems and Build Post Limited 10,000.00 0.00 Implementati 2020-11-09 2021-01-04 2021-07-03 / Cell Phone Quotations Envelope Institutional Capacity on Component 2: Establish Pending SD-MOWSS-202705-NC-RFQ Request for Single Stage - One IDA / D7350 Delivery Systems and Build Post Limited 3,000.00 0.00 Implementati 2020-11-09 2021-01-04 2021-07-03 / Stationery Quotations Envelope Institutional Capacity on Component 2: Establish Pending SD-MOWSS-202707-NC-RFQ Request for Single Stage - One IDA / D7350 Delivery Systems and Build Post Limited 14,000.00 0.00 Implementati 2020-11-09 2021-01-04 2021-07-03 / monitors/docking stations Quotations Envelope Institutional Capacity on Component 2: Establish Pending SD-MOWSS-202708-NC-RFQ Request for Single Stage - One IDA / D7350 Delivery Systems and Build Post Limited 20,000.00 0.00 Implementati 2020-11-09 2021-01-04 2021-07-03 / Vehicle rent for Sr staff Quotations Envelope Institutional Capacity on SD-MOFEP-207302-NC-RFQ Component 2: Establish Pending Request for Single Stage - One / Data Protection Authority / IDA / D7350 Delivery Systems and Build Post Limited 300,000.00 0.00 Implementati 2020-12-06 2021-01-31 2021-07-30 Quotations Envelope Institutional arrangments Institutional Capacity on CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 1 Component 2: Establish SD-MOWSS-202671-CS- Quality And Cost- Pending IDA / D7350 Delivery Systems and Build Post Open - International 250,000.00 0.00 2020-11-04 2020-11-25 2021-01-08 2021-02-05 2021-03-07 2021-04-11 2021-05-16 2022-05-16 QCBS / Reconciliation Audit Based Selection Implementation Institutional Capacity SD-MOWSS-202673-CS- Component 2: Establish QCBS / Payment Services Quality And Cost- Pending IDA / D7350 Delivery Systems and Build Post Open - International 150,000.00 0.00 2020-11-04 2020-11-25 2021-01-08 2021-02-05 2021-03-07 2021-04-11 2021-05-16 2022-05-16 Providers (MNOs, Banks, Based Selection Implementation Institutional Capacity Other) SD-MOWSS-202679-CS- Component 2: Establish Quality And Cost- Pending QCBS / MIS Development IDA / D7350 Delivery Systems and Build Post Open - International 200,000.00 0.00 2020-11-04 2020-11-25 2021-01-08 2021-02-05 2021-03-07 2021-04-11 2021-05-16 2022-05-16 Based Selection Implementation (Firm) Institutional Capacity Component 2: Establish SD-MOWSS-202680-CS- Quality And Cost- Pending IDA / D7350 Delivery Systems and Build Post Open - International 15,000.00 0.00 2020-11-04 2020-11-25 2021-01-08 2021-02-05 2021-03-07 2021-04-11 2021-05-16 2022-05-16 QCBS / MEL Framework (Firm) Based Selection Implementation Institutional Capacity SD-MOWSS-202681-CS- Component 2: Establish Quality And Cost- Pending QCBS / Media Content IDA / D7350 Delivery Systems and Build Post Open - National 15,000.00 0.00 2020-11-04 2020-11-25 2021-01-08 2021-02-05 2021-03-07 2021-04-11 2021-05-16 2022-05-16 Based Selection Implementation Creation Institutional Capacity Component 2: Establish SD-MOWSS-202682-CS- Quality And Cost- Pending IDA / D7350 Delivery Systems and Build Post Open - National 15,000.00 0.00 2020-11-04 2020-11-25 2021-01-08 2021-02-05 2021-03-07 2021-04-11 2021-05-16 2022-05-16 QCBS / Media Punchers Based Selection Implementation Institutional Capacity INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SD-MOWSS-201613-CS-CQS Component 3: Project Individual Under / ENROLLMENT MA / IDA / D7350 Management, Monitoring and Post Consultant Open 12,000.00 0.00 2020-11-02 2021-02-22 2020-12-21 2021-01-11 2021-02-15 2021-08-14 Implementation Enrolment Manager Evaluation, and Learning Selection Component 3: Project Individual SD-MOWSS-202658-CS- Under IDA / D7350 Management, Monitoring and Post Consultant Open 12,000.00 0.00 2020-11-02 2021-02-22 2020-12-21 2021-01-11 2021-02-15 2021-08-14 INDV / Payment Manager Implementation Evaluation, and Learning Selection Component 3: Project Individual SD-MOWSS-202659-CS- Under IDA / D7350 Management, Monitoring and Post Consultant Open 12,000.00 0.00 2020-11-02 2021-02-22 2020-12-21 2021-01-11 2021-02-15 2021-08-14 INDV / Information Security Implementation Evaluation, and Learning Selection SD-MOWSS-202657-CS- Component 3: Project Individual INDV / Communication IDA / D7350 Management, Monitoring and Prior Consultant Open 12,000.00 0.00 Under Review 2020-11-02 2020-12-21 2021-01-11 2021-02-15 2021-08-14 Manager Evaluation, and Learning Selection Component 3: Project Individual SD-MOWSS-202663-CS- Under IDA / D7350 Management, Monitoring and Post Consultant Limited 40,000.00 0.00 2020-11-04 2021-02-22 2020-11-09 2020-11-30 2021-01-04 2021-07-03 INDV / Program Manager Implementation Evaluation, and Learning Selection Component 3: Project Individual SD-MOWSS-202660-CS- Pending IDA / D7350 Management, Monitoring and Post Consultant Open 12,000.00 0.00 2020-11-02 2020-12-21 2021-01-11 2021-02-15 2021-08-14 INDV / MIS Manager Implementation Evaluation, and Learning Selection Component 3: Project Individual SD-MOWSS-202661-CS- Under IDA / D7350 Management, Monitoring and Post Consultant Open 12,000.00 0.00 2020-11-02 2021-02-22 2020-12-21 2021-01-11 2021-02-15 2021-08-14 INDV / MEL Manager Implementation Evaluation, and Learning Selection SD-MOWSS-202664-CS- Component 3: Project Individual Pending INDV / Database IDA / D7350 Management, Monitoring and Post Consultant Limited 18,000.00 0.00 2020-11-04 2020-11-09 2020-11-30 2021-01-04 2021-07-03 Implementation Administrator Evaluation, and Learning Selection SD-MOWSS-202666-CS- Component 3: Project Individual Pending INDV / Network IDA / D7350 Management, Monitoring and Post Consultant Limited 18,000.00 0.00 2020-11-04 2020-11-09 2020-11-30 2021-01-04 2021-07-03 Implementation Administration Evaluation, and Learning Selection SD-MOWSS-202667-CS- Component 3: Project Individual Pending INDV / Family Enrolment Lead IDA / D7350 Management, Monitoring and Post Consultant Limited 18,000.00 0.00 2020-11-04 2020-11-09 2020-11-30 2021-01-04 2021-07-03 Implementation Officer Evaluation, and Learning Selection SD-MOWSS-202668-CS- Component 3: Project Individual Pending INDV / Registration Focal IDA / D7350 Management, Monitoring and Post Consultant Limited 18,000.00 0.00 2020-11-04 2020-11-09 2020-11-30 2021-01-04 2021-07-03 Implementation Points per State Evaluation, and Learning Selection Component 3: Project Individual SD-MOWSS-202649-CS- Pending IDA / D7350 Management, Monitoring and Post Consultant Limited 18,000.00 0.00 2020-11-04 2020-11-09 2020-11-30 2021-01-04 2021-07-03 INDV / Payments Officer Implementation Evaluation, and Learning Selection SD-MOWSS-202651-CS- Component 3: Project Individual Pending INDV / Grievance Redress IDA / D7350 Management, Monitoring and Post Consultant Limited 12,000.00 0.00 2020-11-04 2020-11-09 2020-11-30 2021-01-04 2021-07-03 Implementation Officer Evaluation, and Learning Selection SD-MOWSS-202652-CS- Component 3: Project Individual Pending INDV / Privacy and Digital IDA / D7350 Management, Monitoring and Post Consultant Limited 21,000.00 0.00 2020-11-04 2020-11-09 2020-11-30 2021-01-04 2021-07-03 Implementation Ethics Officer Evaluation, and Learning Selection SD-MOWSS-202653-CS- Component 3: Project Individual Pending INDV / Civil Society and IDA / D7350 Management, Monitoring and Post Consultant Limited 21,000.00 0.00 2020-11-04 2020-11-09 2020-11-30 2021-01-04 2021-07-03 Implementation Community Outreach Officer Evaluation, and Learning Selection SD-MOWSS-202655-CS- Component 3: Project Individual Pending INDV / State-level IDA / D7350 Management, Monitoring and Post Consultant Limited 12,000.00 0.00 2020-11-04 2020-11-09 2020-11-30 2021-01-04 2021-07-03 Implementation Communication Coordinator Evaluation, and Learning Selection SD-MOWSS-202656-CS- Component 3: Project Individual Pending INDV / Gender / Social Impact IDA / D7350 Management, Monitoring and Post Consultant Limited 12,000.00 0.00 2020-11-04 2020-11-09 2020-11-30 2021-01-04 2021-07-03 Implementation Specialist Evaluation, and Learning Selection SD-MOWSS-202670-CS- Component 3: Project Individual Under INDV / Project Procurement IDA / D7350 Management, Monitoring and Prior Consultant Limited 21,000.00 0.00 2020-11-04 2021-02-22 2020-11-09 2020-11-30 2021-01-04 2021-07-03 Implementation Specialist Evaluation, and Learning Selection Page 2 Component 3: Project SD-MOFEP-236088-CS-CDS Pending IDA / D7350 Management, Monitoring and Post Direct Selection Direct 42,000.00 0.00 2021-06-15 2021-06-25 2021-08-29 2022-02-25 / Hiring of Legal advisor Implementation Evaluation, and Learning SD-MOFEP-236097-CS-INDV Component 3: Project Individual Pending / Digital Channel Enrollment IDA / D7350 Management, Monitoring and Post Consultant Limited 30,000.00 0.00 2021-06-30 2021-07-05 2021-07-26 2021-08-30 2022-02-26 Implementation Officer Evaluation, and Learning Selection SD-MOFEP-236104-CS-INDV Component 3: Project Individual Pending / Family Enrollment Team IDA / D7350 Management, Monitoring and Post Consultant Limited 30,000.00 0.00 2021-06-30 2021-07-05 2021-07-26 2021-08-30 2022-02-26 Implementation leader Evaluation, and Learning Selection Component 3: Project Individual SD-MOFEP-236106-CS-INDV Pending IDA / D7350 Management, Monitoring and Post Consultant Limited 30,000.00 0.00 2021-06-30 2021-07-05 2021-07-26 2021-08-30 2022-02-26 / Business Analyst Implementation Evaluation, and Learning Selection Component 3: Project Individual SD-MOFEP-236111-CS-INDV Pending IDA / D7350 Management, Monitoring and Post Consultant Limited 30,000.00 0.00 2021-06-30 2021-07-05 2021-07-26 2021-08-30 2022-02-26 / hiring of Payment Officer Implementation Evaluation, and Learning Selection SD-MOFEP-236113-CS-INDV Component 3: Project Individual Pending / hiring of Social Media IDA / D7350 Management, Monitoring and Post Consultant Limited 30,000.00 0.00 2021-06-30 2021-07-05 2021-07-26 2021-08-30 2022-02-26 Implementation Associate Evaluation, and Learning Selection Page 3 PROCUREMENT PLAN (Textual Part) Project information: SUDAN EDUCATION COVID-19 RESPONSE Sudan, (SECEP) P174220 Project Implementation agency: Federal Ministry of Education Date of the Procurement Plan: May 2020 Period covered by this Procurement Plan: [May 2020 –Feb 2021] Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in [ Not applicable], such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. List only the applicable conditions required to ensure consistency with paragraph 5.4 of the Procurement Regulations. If no conditions apply, delete the phrase “and the following conditions”. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Not applicable Goods: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables]; Works: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables] Other Relevant Procurement Information. any other relevant procurement information such as procedures for CDD components, Procurement in Situations of Urgent Need of Assistance or Capacity Constraints etc. The project will implement procurement of goods that will contribute to project’s objective, through the Alternative Procurement Arrangements (APA) where the recipient is a 3rd party e.g. a UN Agency. To expedite, prioritize 3rd parties with whom the Bank already has APA arrangements to minimize time required for the APA assessments. Agencies with existing APA arrangements include WHO, UNICEF, FAO, UNOPS, WFP, UNDP and ICRC. PROCUREMENT Sudan : Sudan Education COVID-19 Response PLAN General Information Country: Sudan Bank’s Approval Date of the Original Procurement Plan: 2021-05-30 2021-05-30 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P174220 GPN Date: Project Name: Sudan Education COVID-19 Response Loan / Credit No: TF / B3339 Ministry of Education Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SD-MOE-210604-GO-RFQ / Supporting safe transition Pending Printing and distribution of Request for Single Stage - One TF / B3339 back to school during Post Open - National 1,300,000.00 0.00 Implementati 2021-01-20 2021-02-03 2021-02-28 assignments for Basic School Quotations Envelope recovery on Students SD-MOE-210623-GO-DIR / Pending Program coordination and Procurement Ready Made TF / B3339 Post Direct Selection Direct 50,000.00 0.00 Implementati 2020-12-25 2020-12-30 2021-02-03 2021-08-02 management Accounting Software for PCU on SD-MOE-210624-GO-RFQ / Pending Program coordination and Request for Single Stage - One Procurement of laptops for TF / B3339 Post Open - National 30,000.00 0.00 Implementati 2020-12-30 2021-02-24 2021-08-23 management Quotations Envelope PCU on SD-MOE-210625-GO-RFQ / Pending Procurement of photocopier Program coordination and Request for Single Stage - One TF / B3339 Post Open - National 32,000.00 0.00 Implementati 2021-01-04 2021-03-01 2021-08-28 for PCU management Quotations Envelope on Office Equipment SD-MOE-210626-GO-UN / Pending Procurement of Vehicles for Program coordination and UN Agencies TF / B3339 Post Direct 120,000.00 0.00 Implementati 2020-12-30 2021-01-04 2021-02-08 2021-08-07 states (four Pick-Up double management (Direct) on cabin) SD-MOE-210627-GO-RFQ / Pending Program coordination and Request for Single Stage - One Procurement of Audiovisuals TF / B3339 Post Open - National 50,000.00 0.00 Implementati 2021-01-20 2021-03-17 2021-09-13 management Quotations Envelope tools for distant learning on Supporting learning SD-MOE-210609-GO-UN / continuity at the basic Pending Procurement of (100,000) Single Stage - Two TF / B3339 education level during the Prior Request for Bids Open - National 2,000,000.00 0.00 Implementati 2021-06-15 2021-06-20 2021-07-04 2021-07-20 2021-09-30 Solar FM/AM/SW portable Envelope COVID-19 pandemic and on radios school system shutdown SD-MOE-210605-GO-RFQ / Supporting safe transition Pending Request for Single Stage - One Provision of 1,760 storage TF / B3339 back to school during Post Open - National 880,000.00 0.00 Implementati 2021-06-06 2021-07-13 2021-08-09 Quotations Envelope Water tanks to schools recovery on NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Supporting learning SD-MOE-210599-NC-RFP / continuity at the basic Pending Request for Single Stage - Two General broadcasting (COVID- TF / B3339 education level during the Post Limited 400,000.00 0.00 Implementati 2020-12-20 2021-01-12 2021-01-19 2021-01-26 2021-03-17 2022-09-08 Proposals Envelope 19 awareness, WASH) COVID-19 pandemic and on school system shutdown Supporting learning SD-MOE-210603-NC-RFP / continuity at the basic Pending Request for Improving of education TF / B3339 education level during the Post Limited 700,000.00 0.00 Implementati 2021-01-05 2021-02-21 2021-02-21 2021-02-28 2021-04-06 2022-05-05 Proposals quality in Math and reading COVID-19 pandemic and on school system shutdown CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SD-MOE-210611-CS-CQS / Consultant Program coordination and Pending Hiring of PCU Financial TF / B3339 Post Qualification Open - National 24,000.00 0.00 2020-12-25 2021-01-15 2021-02-28 2021-03-30 2021-05-04 2021-10-31 management Implementation Management Officer Selection Consultant SD-MOE-210618-CS-CQS / Program coordination and Pending TF / B3339 Post Qualification Open - National 36,000.00 0.00 2020-12-25 2021-01-15 2021-02-28 2021-03-30 2021-05-04 2021-10-31 Hiring of PCU M&E Specialist management Implementation Selection Consultant SD-MOE-210619-CS-CQS / Program coordination and Pending TF / B3339 Post Qualification Open - National 36,000.00 0.00 2020-12-25 2021-01-15 2021-02-28 2021-03-30 2021-05-04 2021-10-31 Hiring of PCU Data Specialist management Implementation Selection SD-MOE-210620-CS-CQS / Consultant Program coordination and Pending Hiring of PCU Assistant Data TF / B3339 Post Qualification Open - National 24,000.00 0.00 2020-12-25 2021-01-15 2021-02-28 2021-03-30 2021-05-04 2021-10-31 management Implementation Specialist Selection Consultant SD-MOE-210621-CS-CQS / Program coordination and Pending TF / B3339 Post Qualification Open - National 24,000.00 0.00 2020-12-25 2021-01-15 2021-02-28 2021-03-30 2021-05-04 2021-10-31 Hiring of PCU ICT Officer management Implementation Selection Page 1 SD-MOE-210622-CS-CQS / Consultant Program coordination and Pending Hiring of PCU communication TF / B3339 Post Qualification Open - National 24,000.00 0.00 2020-12-25 2021-01-15 2021-02-28 2021-03-30 2021-05-04 2021-10-31 management Implementation officer Selection INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 2 PROCUREMENT PLAN (Textual Part) Project information: DRC - Regional Great Lakes Integrated Development Project (P-143307) Project Implementation agency: Ministry of Agriculture Date of the Procurement Plan: April 18, 2017 Period covered by this Procurement Plan: July2014 – July 31, 2017 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Specify for each Goods: Request for quotations; Works: Not Applicable Other Relevant Procurement Information. PROCUREMENT Eastern Africa : AFR RI-Regional Great Lakes Integrated Agriculture Development Project PLAN General Information Country: Eastern Africa Bank’s Approval Date of the Original Procurement Plan: 2017-04-18 2021-05-25 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P143307 GPN Date: 2018-11-02 Project Name: AFR RI-Regional Great Lakes Integrated Agriculture Development Project Loan / Credit No: IDA / Q9260, IDA / 58520, IDA / Q9610 Ministry of Agriculture Executing Agency(ies): WORKS Activity Reference No. / Procurement Estimated Actual Draft Pre- Draft Bidding Bid Evaluation Report Loan / Credit Market Procurement Prequalification High SEA/SH Process Prequalification Specific Procurement Bidding Documents Proposal Submission Contract Description Component Review Type Method Document Amount Amount qualification Document / and Recommendation Signed Contract No. Approach Process (Y/N) Risk Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Completion Type (US$) (US$) Documents Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned ZR-MINAGRI-79144-CW- RFB / Travaux de Support Services and Project Single Stage - One 2018-10- 2019-01- 2018-10- 2019-07- 2018-11- 2019-02- 2018-12- 2019-03- 2019-01- 2019-08- 2019-07- IDA / 58520 Prior Request for Bids Open - National 500,000.00 656,215.93 Signed réhabilitation des bâtiments Management Envelope 03 11 08 13 19 22 19 29 23 09 22 des inspestions provinciales de Sud Kivu ZR-MINAGRI-78946-CW- RFB / Travaux de Support Services and Project Single Stage - One 2018-10- 2019-01- 2018-10- 2018-11- 2019-02- 2018-12- 2019-03- 2019-01- 2019-06- 2019-07- IDA / 58520 Post Request for Bids Open - National 500,000.00 486,607.72 Signed réhabilitation des bâtiments Management Envelope 03 11 08 19 22 19 21 23 24 22 des inspestions provinciales de Tanganyika ZR-MINAGRI-79093-CW- RFQ / Travaux de réhabilitation des bâtiments devant servir des bureaux du Support Services and Project Request for Single Stage - One 2018-10- 2019-02- 2018-12- 2019-05- 2019-06- IDA / 58520 Post Limited 80,000.00 79,437.21 Signed Ministre Provincial de Management Quotations Envelope 08 02 03 16 01 l'Agriculture,Pêche et Elevage et du Développement Rural du Tanganyika ZR-MINAGRI-105397-CW- RFQ / Travaux de Réhabilitation des bâtiments Support Services and Project Request for Single Stage - One 2019-05- 2019-10- 2019-07- 2019-12- 2020-01- abritant le Bureau_ du IDA / 58520 Post Limited 30,000.00 24,227.50 Signed Management Quotations Envelope 15 09 10 09 06 Ministère provincial de l’Agriculture, pèche et élevage du Sud-Kivu ZR-MINAGRI-133733-CW- RFQ / Travaux de Pending réhabilitation du bâtiment Support Services and Project Request for Single Stage - One 2019-10- 2019-12- 2020-06- IDA / 58520 Post Limited 40,000.00 0.00 Implementa devant servir des bureaux Management Quotations Envelope 20 15 12 tion provisoires de l'IPAPEL Sud Kivu ZR-MINAGRI-169983-CW- RFQ / Travaux d'aménagement du bâtiment Pending Support Services and Project Request for Single Stage - One 2020-08- 2020-09- 2021-03- abritant les bureaux des IDA / 58520 Post Limited 80,000.00 0.00 Implementa Management Quotations Envelope 04 29 28 services du Secrétariat tion Général à la Pêche et Elevage sur l'avenue de la libération (SQUAV) ZR-MINAGRI-169808-CW- DIR / Contractualisation avec SAGEC KAT pour les travaux de construction des bureaux Support for the development Pending 2020-07- 2020-08- 2020-09- 2021-03- complémentaires des des IDA / 58520 of the private agro- Post Direct Selection Direct 145,000.00 0.00 Implementa 30 04 08 07 inspections de l'Agriculture industrial sector tion et du Développement Rural de la province de Tanganyika et aménagement extérieur ZR-MINAGRI-169820-CW- RFQ / Travaux de Pending Support Services and Project Request for Single Stage - One 2020-05- 2020-07- 2021-01- construction de deux (2) IDA / 58520 Post Limited 200,000.00 0.00 Implementa Management Quotations Envelope 20 15 11 laboratoires du SENASEM et tion de l'INERA Tanganyika ZR-MINAGRI-169811-CW- DIR / Contractualisation avec KIMA CONSTRUCTION pour Under la réalisation des travaux de Support Services and Project 2020-06- 2020-10- 2020-06- 2020-10- 2020-08- 2021-01- IDA / 58520 Post Direct Selection Direct 25,000.00 25,377.38 Implementa la clôture et d'aménagement Management 22 07 27 12 01 28 tion extérieur des bureaux du Ministre Provincial de l'Agriculture Sud Kivu ZR-MINAGRI-188529-CW- RFQ / Travaux de construction de six (06) Pending Agriculture Value Chain Request for Single Stage - One 2020-10- 2020-12- 2021-05- Centres Communautaires de IDA / 58520 Post Limited 200,000.00 0.00 Implementa Development Quotations Envelope 07 02 31 Transformation de Riz tion (CCTRIZ) dans la Province de Tanganyika ZR-MINAGRI-188543-CW- RFQ / Travaux de construction de Entrepôts Pending Agriculture Value Chain Request for Single Stage - One 2020-11- 2020-12- 2021-06- dépôts de stockage à IDA / 58520 Post Limited 200,000.00 0.00 Implementa Development Quotations Envelope 05 31 29 Rugumba, Rugo, Lwaminwa, tion Katibili, Muhala et Kabimba dans la Province du Tanganyika ZR-MINAGRI-188540-CW- RFQ / Travaux de construction de 6 dépôts de Pending Agriculture Value Chain Request for Single Stage - One 2020-09- 2020-11- 2021-04- stockage à Rugumba, Rugo, IDA / 58520 Post Limited 150,000.00 0.00 Implementa Development Quotations Envelope 06 01 30 Lwaminwa, Katibili, Muhala tion et Kabimba dans la Province du Tanganyika ZR-MINAGRI-188521-CW- RFQ / Travaux de construction de deux (02) dépôts vétérinaires dans la Pending Agriculture Value Chain Request for Single Stage - One 2020-10- 2020-12- 2021-06- ville de Kalemie et deux (02) IDA / Q9610 Post Limited 150,000.00 0.00 Implementa Development Quotations Envelope 27 22 20 cliniques vétérinaires dans tion les bassins de production de la Rugumba et Lwamina, territoire de Kalemie/Tanganyika ZR-MINAGRI-188479-CW- DIR / Contractualisation avec l'Entreprise SAGEC KAT SARL pour les travaux complémentaires de Support Services and Project 2020-09- 2020-10- 2020-09- 2020-10- 2020-10- 2020-11- 2021-04- Réhabilitation du bâtiment IDA / 58520 Post Direct Selection Direct 150,000.00 149,428.76 Signed Management 16 07 21 12 26 23 24 devant servir des bureaux des Inspections Provinciales de l’Agriculture et du Développement Rural du Sud Kivu ZR-MINAGRI-188497-CW- RFQ / Travaux de construction du laboratoire Pending Agriculture Value Chain Request for Single Stage - One 2020-10- 2020-12- 2021-06- de la Coordination IDA / 58520 Post Limited 170,000.00 0.00 Implementa Development Quotations Envelope 23 18 16 Provinciale de Service tion National de Semences (SENASEM)/Tanganyika ZR-MINAGRI-188489-CW- RFQ / Travaux de Pending Agriculture Value Chain Request for Single Stage - One 2020-10- 2020-12- 2021-06- construction des Unités de IDA / 58520 Post Limited 200,000.00 0.00 Implementa Development Quotations Envelope 26 21 19 transformation du lait dans tion territoire de Kalemie/Tanganyika ZR-MINAGRI-188545-CW- RFQ / Travaux de constuction de dix Centres (Bâtiments) Communautaires Agriculture Value Chain Request for Single Stage - One 2020-10- 2020-12- 2021-05- de Transformation de Maïs IDA / 58520 Post Limited 230,000.00 0.00 Canceled Development Quotations Envelope 06 01 30 dont 2 à Kabimba, 2 à Rugo, 2 à Rugumba, 2 à Katibili et 2 à Lwamminwa dans la Province de Tanganyika ZR-MINAGRI-210011-GO- RFQ / Travaux de Pending construction de deux (2) mini Agriculture Value Chain Request for Single Stage - One 2021-02- 2021-04- 2021-10- IDA / 58520 Post Limited 20,000.00 0.00 Implementa chambres froides dont 1 à Development Quotations Envelope 13 10 07 tion Luberezi et 1 Mutarule, dans le cadre du PICAGL, UPEP Sud- Kivu ZR-MINAGRI-210021-CW- RFQ / Construction de deux (2) mini laboratoires de Service National de Semences (SENASEM) dont 1 à Bwegera Pending Support Services and Project Request for Single Stage - One 2021-01- 2021-03- 2021-09- et 1 Fizi centre, d’un (1) mur IDA / 58520 Post Limited 123,000.00 0.00 Implementa Management Quotations Envelope 30 27 23 de clôture et aménagement tion des paillasses dans la salle de labo physique et phytopathologie aux bureaux de SENASEM Bukavu ZR-MINAGRI-210108-CW- RFQ / Travaux de construction de deux (02) Pending Agriculture Value Chain Request for Single Stage - One 2021-01- 2021-03- 2021-09- provenderies dans les IDA / 58520 Post Limited 65,000.00 0.00 Implementa Development Quotations Envelope 20 17 13 Bassins de production de tion Rugumba et Lwaminwa dans la Province de Tanganyika ZR-MINAGRI-210111-CW- RFQ / Travaux de construction de quatre (04) Pending boutiques d'intrants Agriculture Value Chain Request for Single Stage - One 2021-01- 2021-03- 2021-09- IDA / 58520 Post Limited 128,000.00 0.00 Implementa agricoles dans les Bassins de Development Quotations Envelope 25 22 18 tion production de Rugumba, Kabimba, Kalemie et Kamango dans la Province de Tanganyika Page 1 ZR-MINAGRI-210125-CW- RFQ / Travaux de construction de quatre (4) Centres de Collecte et Pending Agriculture Value Chain Request for Single Stage - One 2021-02- 2021-03- 2021-09- Transformation de Manioc IDA / 58520 Post Limited 153,000.00 0.00 Implementa Development Quotations Envelope 01 29 25 dont 2 à Bitale, 1 à Bulmbika tion et 1 à Mulonge, dans le territoire de Kalehe, dans le cadre du PICAGL, UPEP Sud- Kivu ZR-MINAGRI-210132-CW- RFQ / Travaux de construction de quatre (4) Centres de Collecte et Pending Agriculture Value Chain Request for Single Stage - One 2021-02- 2021-03- 2021-09- Transformation de Manioc IDA / 58520 Post Limited 153,000.00 0.00 Implementa Development Quotations Envelope 01 29 25 dont 1 à Mubuku, 1 à Karasi, tion 1 à Kitchanga et 1 à Maibano, dans le territoire de Kalehe, dans le cadre du PICAGL, UPEP Sud-Kivu ZR-MINAGRI-210126-CW- RFQ / Travaux de construction de deux (2) Pending Centres de Collecte et Agriculture Value Chain Request for Single Stage - One 2021-02- 2021-03- 2021-09- IDA / 58520 Post Limited 77,000.00 0.00 Implementa Transformation de Manioc Development Quotations Envelope 01 29 25 tion dont 1 à Katanga et 1 à Malinde, dans le territoire de Fizi, dans le cadre du PICAGL, UPEP Sud-Kivu ZR-MINAGRI-210127-CW- RFQ / Travaux de construction de cinq (5) Pending Centres de Collecte et Agriculture Value Chain Request for Single Stage - One 2021-02- 2021-03- 2021-09- IDA / 58520 Post Limited 192,000.00 0.00 Implementa Transformation de Manioc Development Quotations Envelope 01 29 25 tion dont 3 à Katana, 1 à Kavumu et 1 à Luhihi, dans le territoire de Kabare, dans le cadre du PICAGL, UPEP Sud- Kivu ZR-MINAGRI-210129-CW- RFQ / Travaux de construction de trois (3) Centres de Collecte et Pending Agriculture Value Chain Request for Single Stage - One 2021-02- 2021-03- 2021-09- Transformation de Manioc IDA / 58520 Post Limited 115,000.00 0.00 Implementa Development Quotations Envelope 01 29 25 dont 1 à Sange, 1 à Kiliba et tion 1 à Runingu, dans le territoire d’Uvira, dans le cadre du PICAGL, UPEP Sud- Kivu ZR-MINAGRI-210130-CW- RFQ / Travaux de construction de quatre (4) Centres de Collecte et Pending Agriculture Value Chain Request for Single Stage - One 2021-02- 2021-03- 2021-09- Transformation de Manioc IDA / 58520 Post Limited 153,000.00 0.00 Implementa Development Quotations Envelope 01 29 25 dont 2 à Kamanyola, 1 à tion Luvungi et 1 à Lubarika, dans la plaine de Ruzizi, dans le cadre du PICAGL, UPEP Sud- Kivu ZR-MINAGRI-195187-CW- Pending RFQ / Travaux de Agriculture Value Chain Request for Single Stage - One 2021-01- 2021-03- 2021-08- IDA / 58520 Post Limited 160,000.00 0.00 Implementa construction du laboratoire Development Quotations Envelope 04 01 28 tion de l'INERA dans le territoire de Kalemie ZR-MINAGRI-210336-CW- RFQ / Construction des aires de sechage semi ouverts Pending dans le groupement de Agriculture Value Chain Request for Single Stage - One 2021-02- 2021-04- 2021-10- IDA / 58520 Post Limited 41,000.00 0.00 Implementa Bushumba dans le territoire Development Quotations Envelope 08 05 02 tion de Kabare et le groupement d'Itara dans le territoire d'Uvira, dans le cadre du PICAGL, UPEP Sud-Kivu ZR-MINAGRI-210338-CW- RFQ / Construction des aires Pending de sechage non couverts à Agriculture Value Chain Request for Single Stage - One 2021-02- 2021-04- 2021-10- IDA / 58520 Post Limited 18,000.00 0.00 Implementa Sebele dans le territoire de Development Quotations Envelope 08 05 02 tion Fizi et à Uvira, dans le cadre du PICAGL, UPEP Sud-Kivu ZR-MINAGRI-210648-CW- RFQ / Travaux de construction de sept (7) abris dont six (6) pour mini- Pending Agriculture Value Chain Request for Single Stage - One 2021-02- 2021-03- 2021-09- minoterie et un (1) pour mini- IDA / 58520 Post Limited 84,000.00 0.00 Implementa Development Quotations Envelope 03 31 27 laiterie de type 2, et d’une tion (1) provenderie, dans le territoire de Kabare, dans le cadre du PICAGL, UPEP Sud- Kivu ZR-MINAGRI-210650-CW- RFQ / Travaux de construction de quatre (4) Pending abris dont un (1) pour mini- Agriculture Value Chain Request for Single Stage - One 2021-02- 2021-03- 2021-09- IDA / Q9260 Post Limited 42,000.00 0.00 Implementa minoterie et trois (3) pour Development Quotations Envelope 03 31 27 tion mini-laiterie de type 2, dans le territoire de Kalehe, dans le cadre du PICAGL, UPEP Sud- Kivu ZR-MINAGRI-210651-CW- RFQ / Travaux de construction de dix (10) abris dont huit (8) pour mini- Pending minoterie, un (1) pour rizerie Agriculture Value Chain Request for Single Stage - One 2021-02- 2021-03- 2021-09- IDA / 58520 Post Limited 110,000.00 0.00 Implementa de type 2 (SB-50 ou Development Quotations Envelope 03 31 27 tion équivalent) et un (1) pour mini-laiterie de type 2, dans le territoire de Fizi, dans le cadre du PICAGL, UPEP Sud- Kivu ZR-MINAGRI-210653-CW- RFQ / Travaux de construction de deux (2) Pending Agriculture Value Chain Request for Single Stage - One 2021-02- 2021-03- 2021-09- abris pour mini-laiterie de IDA / 58520 Post Limited 34,000.00 0.00 Implementa Development Quotations Envelope 03 31 27 type 2 et une (1) tion provenderie, à Bukavu, dans le cadre du PICAGL, UPEP Sud- Kivu ZR-MINAGRI-210654-CW- RFQ / Travaux de construction de seize (16) abris dont douze (12) pour Pending mini minoterie, trois (3) pour Agriculture Value Chain Request for Single Stage - One 2021-02- 2021-03- 2021-09- IDA / 58520 Post Limited 174,000.00 0.00 Implementa rizerie type 2 (SB-50 ou Development Quotations Envelope 03 31 27 tion équivalent), un (1) pour mini- laiterie de type 2 et d’une (1) provenderie dans la plaine de Ruzizi (Territoires d’Uvira et Walungu) ZR-MINAGRI-210656-CW- RFQ / Travaux de construction de quatorze (14) abris dont cinq (5) pour Pending Agriculture Value Chain Request for Single Stage - One 2021-02- 2021-03- 2021-09- mini-minoterie, deux (2) IDA / 58520 Post Limited 141,000.00 0.00 Implementa Development Quotations Envelope 03 31 27 pour rizerie de type 2, un (1) tion pour entrepot des intrants agricoles et six (6) pour mini- laiterie de type 2, dans le territoire d’Uvira ZR-MINAGRI-210894-CW- RFQ / Travaux de construction de trois (3) entrepôts des produits Pending Agriculture Value Chain Request for Single Stage - One 2021-02- 2021-04- 2021-10- agricoles avec bureaux des IDA / 58520 Post Limited 171,000.00 0.00 Implementa Development Quotations Envelope 10 07 04 préposés et latrines et d’un tion (1) entrepôt semencier à Katanga, dans le cadre du PICAGL, UPEP Sud-Kivu ZR-MINAGRI-210893-CW- RFQ / Travaux de construction de trois (3) entrepôts des produits Pending Agriculture Value Chain Request for Single Stage - One 2021-02- 2021-04- 2021-10- agricoles avec bureaux des IDA / 58520 Post Limited 171,000.00 0.00 Implementa Development Quotations Envelope 10 07 04 préposés et latrines à Baraka tion et d’un (1) entrepôt semencier à Nemba, dans le cadre du PICAGL, UPEP Sud- Kivu ZR-MINAGRI-210891-CW- RFQ / Travaux de construction de trois (3) entrepôts des produits Pending agricoles avec bureaux des Agriculture Value Chain Request for Single Stage - One 2021-02- 2021-04- 2021-10- IDA / 58520 Post Limited 171,000.00 0.00 Implementa préposés et latrines dont 1 à Development Quotations Envelope 10 07 04 tion Sebele, 1 à Kabondonzi et 1 à Malinde et d’un (1) entrepôt semencier à Sebele, dans le cadre du PICAGL, UPEP Sud-Kivu ZR-MINAGRI-210886-CW- RFQ / Travaux de construction de quatre (4) entrepôts des produits Pending Agriculture Value Chain Request for Single Stage - One 2021-02- 2021-04- 2021-10- agricoles avec bureaux des IDA / 58520 Post Limited 187,000.00 0.00 Implementa Development Quotations Envelope 10 07 04 préposés et latrines dont tion deux (2) à Fizi centre et deux (2) à Mulongwe, dans le cadre du PICAGL, UPEP Sud- Kivu ZR-MINAGRI-210885-CW- RFQ / Travaux de construction de trois (3) entrepôts des produits Pending Agriculture Value Chain Request for Single Stage - One 2021-02- 2021-04- 2021-10- agricoles avec bureaux des IDA / 58520 Post Limited 200,000.00 0.00 Implementa Development Quotations Envelope 10 07 04 préposés et latrines et de tion deux (2) entrepôts semenciers à Sange, dans le cadre du PICAGL, UPEP Sud- Kivu ZR-MINAGRI-210892-CW- RFQ / Travaux de construction de trois (3) entrepôts des produits Pending agricoles avec bureaux des Agriculture Value Chain Request for Single Stage - One 2021-02- 2021-04- 2021-10- IDA / 58520 Post Limited 171,000.00 0.00 Implementa préposés et latrines dont un Development Quotations Envelope 10 07 04 tion (1) à Kiliba et deux (2) à Runingu, et d’un (1) entrepôt semencier à Kiliba, dans le cadre du PICAGL, UPEP Sud- Kivu Page 2 ZR-MINAGRI-210890-CW- RFQ / Travaux de construction de quatre (4) entrepôts des produits Pending Agriculture Value Chain Request for Single Stage - One 2021-02- 2021-04- 2021-10- agricoles avec bureaux des IDA / 58520 Post Limited 187,000.00 0.00 Implementa Development Quotations Envelope 10 07 04 préposés et latrines dont tion trois (3) à Luvungi et un (1) à Lubarika, dans le cadre du PICAGL, UPEP Sud-Kivu ZR-MINAGRI-210887-CW- RFQ / Travaux de construction de quatre (4) entrepôts des produits Pending agricoles avec bureaux des Agriculture Value Chain Request for Single Stage - One 2021-02- 2021-04- 2021-10- IDA / 58520 Post Limited 187,000.00 0.00 Implementa préposés et latrines dont un Development Quotations Envelope 10 07 04 tion (1) à Kagando, un (1) à Kahwizi, un (1) à Kigongo et un (1) à Murunga, dans le cadre du PICAGL, UPEP Sud- Kivu ZR-MINAGRI-210884-CW- RFQ / Travaux de construction de deux (2) entrepôts des produits Pending Agriculture Value Chain Request for Single Stage - One 2021-02- 2021-04- 2021-10- agricoles avec bureaux des IDA / 58520 Post Limited 124,000.00 0.00 Implementa Development Quotations Envelope 10 07 04 préposés et latrines et d’un tion (1) entrepôt semencier à Nyangezi, dans le cadre du PICAGL, UPEP Sud-Kivu ZR-MINAGRI-210888-CW- RFQ / Travaux de construction de trois (3) Pending entrepôts des produits Agriculture Value Chain Request for Single Stage - One 2021-02- 2021-04- 2021-10- IDA / 58520 Post Limited 140,000.00 0.00 Implementa agricoles avec bureaux des Development Quotations Envelope 10 07 04 tion préposés et latrines à Kamanyola, dans le cadre du PICAGL, UPEP Sud-Kivu ZR-MINAGRI-210889-CW- RFQ / Travaux de construction de deux (2) entrepôts des produits Pending Agriculture Value Chain Request for Single Stage - One 2021-02- 2021-04- 2021-10- agricoles avec bureaux des IDA / 58520 Post Limited 95,000.00 0.00 Implementa Development Quotations Envelope 10 07 04 préposés et latrines dont un tion (1) à Mudaka et un (1) à Bunyakiri/Bitale, dans le cadre du PICAGL, UPEP Sud- Kivu ZR-MINAGRI-210974-CW- RFQ / Travaux de Pending construction d’une (1) laiterie Agriculture Value Chain Request for Single Stage - One 2021-02- 2021-04- 2021-09- IDA / 58520 Post Limited 32,000.00 0.00 Implementa de type 3 à Cirunga, dans le Development Quotations Envelope 06 03 30 tion territoire de Kabare, dans le cadre du PICAGL, UPEP Sud- Kivu ZR-MINAGRI-210975-CW- RFQ / Travaux de construction de trois (3) Pending laiteries de type 3 dont deux Agriculture Value Chain Request for Single Stage - One 2021-02- 2021-04- 2021-09- IDA / 58520 Post Limited 96,000.00 0.00 Implementa (2) à Luvungi et une (1) à Development Quotations Envelope 06 03 30 tion Bwegera, dans le territoire d’Uvira, dans le cadre du PICAGL, UPEP Sud-Kivu ZR-MINAGRI-210973-CW- RFQ / Travaux de construction de quatre (4) Pending laiteries de type 3 dont 1 à Agriculture Value Chain Request for Single Stage - One 2021-02- 2021-04- 2021-09- IDA / 58520 Post Limited 130,000.00 0.00 Implementa Sange, 1 à Kavimvira et 2 à Development Quotations Envelope 06 03 30 tion Uvira, dans le territoire d’Uvira, dans le cadre du PICAGL, UPEP Sud-Kivu ZR-MINAGRI-188474-CW- RFQ / Travaux de constuction de sept Centres (Bâtiments) Communautaires Pending de Transformation de Manioc Agriculture Value Chain Request for Single Stage - One 2020-11- 2020-12- 2021-06- IDA / 58520 Post Limited 200,000.00 0.00 Implementa ( CCTMA) dont 1 à Kabimba, Development Quotations Envelope 05 31 29 tion 1 à Rugo, 1 à Rugumba, 2 à Katibili, 1 à Tabacongo et 1 à Lwamminwa dans la Province de Tanganyika GOODS Activity Reference No. / Draft Pre- Draft Bidding Bid Evaluation Report Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Prequalification Specific Procurement Bidding Documents Proposal Submission Description Component Review Type Method qualification Document / and Recommendation Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Documents Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-PARSSA-6375-GO-RFQ / Pending Acquisition matériels Support Services and Project Request for Single Stage - One 2016-06- 2016-08- 2017-02- IDA / Q9260 Post Limited 16,000.00 0.00 Implementat informatiques en faveur du Management Quotations Envelope 17 12 08 ion personnel PICAGL ZR-PARSSA-5170-GO-RFQ / Under Acquisition de 3 véhicules en Support Services and Project Request for Single Stage - One 2015-10- 2015-12- 2016-06- IDA / Q9260 Post Limited 120,000.00 0.00 Implementat faveur des coordinations Management Quotations Envelope 15 10 07 ion provinciales ZR-PARSSA-5154-GO-DIR / Acquisition du logiciel de Support Services and Project 2015-09- 2015-09- 2015-11- 2015-10- 2016-05- IDA / Q9260 Post Direct Selection Direct 37,000.00 50,591.91 Signed gestion financière et Management 24 29 03 22 01 comptable Tom² pro MOF-REF-5 / Acquisition Agriculture Value Chain Request for Single Stage - One 2018-11- 2019-01- 2019-07- IDA / 58520 Post Limited 160,000.00 0.00 Canceled des camions Development Quotations Envelope 27 22 21 MOF-REF-6 / Acquisition des matériels pour la Support Services and Project Request for Single Stage - One 2018-11- 2019-01- 2019-07- vaccination contre la peste IDA / 58520 Post Limited 80,000.00 0.00 Canceled Management Quotations Envelope 28 23 22 bovine et la PPR dans les provinces de Sud Kivu et de Tanganyika MOF-REF-7 / Fourniture et mise en service des matériels informatiques et de Support Services and Project Single Stage - One 2018-10- 2018-10- 2018-12- 2019-01- 2019-02- 2019-08- IDA / 58520 Post Request for Bids Open - National 250,000.00 0.00 Canceled reprographie en faveur du Management Envelope 18 23 04 03 07 06 Projet et des services impliqués ZR-MINAGRI-78950-GO- RFQ / Acquisition de fournitures de bureau et Support Services and Project Request for Single Stage - One 2018-10- 2018-12- 2019-06- consommables informatiques IDA / 58520 Post Limited 60,000.00 0.00 Canceled Management Quotations Envelope 24 19 17 en faveur de l'Unité Nationale de Projet et les services impliqués du MINAGRI, PEL et DR ZR-MINAGRI-78990-GO- RFB / Acquisition des Support Services and Project Single Stage - One 2018-11- 2018-11- 2018-12- 2019-01- 2019-02- 2019-08- IDA / 58520 Post Request for Bids Open - National 150,000.00 0.00 Canceled matériels de sensibilisation Management Envelope 01 06 18 17 21 20 et visibilité en faveur de l'UNCP ZR-MINAGRI-78881-GO- RFQ / Fourniture et installation des équipements Support Services and Project Request for Single Stage - One 2018-10- 2018-10- 2018-12- 2018-12- 2019-05- IDA / 58520 Post Limited 24,000.00 18,547.00 Signed pour la connexion internet et Management Quotations Envelope 06 16 01 03 30 abonnement annuel du bureau de l'UPEP PICAGL Sud- Kivu ZR-MINAGRI-79034-GO- RFQ / Fourniture et Support Services and Project Request for Single Stage - One 2018-10- 2018-08- 2018-12- 2018-10- 2019-06- 2019-04- installation des mobiliers de IDA / 58520 Post Limited 30,000.00 31,481.80 Completed Management Quotations Envelope 20 20 15 03 13 30 bureau pour l'Unité Provinciale d’Exécution du PICAGL Sud-Kivu ZR-MINAGRI-79167-GO- Pending RFQ / Fournitures et mise Support Services and Project Request for Single Stage - One 2018-11- 2019-01- 2019-07- IDA / 58520 Post Limited 15,000.00 0.00 Implementat service des kits solaires Management Quotations Envelope 11 06 05 ion pour l'UPEP PICAGL Sud-Kivu ZR-MINAGRI-78817-GO- Pending RFQ / Acquisition de Support Services and Project Request for Single Stage - One 2018-10- 2018-12- 2019-06- IDA / 58520 Post Limited 15,000.00 0.00 Implementat carburant et lufrifiant pour Management Quotations Envelope 20 15 13 ion les véhicules de l'UPEP PICAGL Sud-Kivu ZR-MINAGRI-79039-GO- RFQ / Fourniture et mise en service des matériels Support Services and Project Request for Single Stage - One 2018-10- 2018-10- 2018-12- 2018-12- 2019-06- 2019-01- IDA / 58520 Post Limited 40,000.00 40,515.00 Completed informatiques et de Management Quotations Envelope 20 16 15 03 13 15 reprographie pour l’Unité Provinciale d’Exécution du PICAGL Sud-Kivu. ZR-MINAGRI-78971-GO- RFQ / Acquisition des Support Services and Project Request for Single Stage - One 2019-01- 2018-11- 2019-02- 2019-02- 2019-08- 2019-04- IDA / 58520 Post Limited 15,000.00 7,475.00 Completed matériels de sensibilisation Management Quotations Envelope 02 30 27 18 26 22 et visibilité en faveur de l'UPEP Sud Kivu ZR-MINAGRI-79095-GO- RFQ / Fourniture et installation des équipements Support Services and Project Request for Single Stage - One 2018-10- 2018-10- 2018-12- 2018-11- 2019-05- IDA / 58520 Post Limited 24,000.00 27,280.00 Signed pour la connexion internet et Management Quotations Envelope 06 26 01 22 30 abonnement annuel du bureau de l'UPEP PICAGL Tanganyika ZR-MINAGRI-79160-GO- RFQ / Fourniture et Support Services and Project Request for Single Stage - One 2018-10- 2018-10- 2018-12- 2018-12- 2019-06- 2019-04- installation des mobiliers de IDA / 58520 Post Limited 30,000.00 27,400.00 Completed Management Quotations Envelope 20 23 15 03 13 08 bureau pour l'Unité Provinciale d’Exécution du PICAGL Tanganyika ZR-MINAGRI-79165-GO- Pending RFQ / Fournitures et Support Services and Project Request for Single Stage - One 2018-11- 2019-01- 2019-07- IDA / 58520 Post Limited 15,000.00 0.00 Implementat installation des équipements Management Quotations Envelope 11 06 05 ion solaires pour l'UPEP PICAGL Tanganyika Page 3 ZR-MINAGRI-78973-GO- RFQ / Acquisition de Support Services and Project Request for Single Stage - One 2018-10- 2019-01- 2018-12- 2019-05- 2019-06- IDA / 58520 Post Limited 15,000.00 15,000.00 Signed carburant et lufrifiant pour Management Quotations Envelope 20 18 15 13 13 les véhicules de l'UPEP PICAGL Tanganyika ZR-MINAGRI-79163-GO- RFQ / Fourniture et mise en service des matériels Support Services and Project Request for Single Stage - One 2018-10- 2018-10- 2018-12- 2018-11- 2019-06- IDA / 58520 Post Limited 40,000.00 36,358.51 Signed informatiques et de Management Quotations Envelope 20 26 15 23 13 reprographie pour l’Unité Provinciale d’Exécution du PICAGL Tanganyika ZR-MINAGRI-79102-GO- RFQ / Acquisition des Support Services and Project Request for Single Stage - One 2019-01- 2018-10- 2019-02- 2018-12- 2019-08- IDA / 58520 Post Limited 15,000.00 11,565.00 Signed matériels de sensibilisation Management Quotations Envelope 02 26 27 03 26 et visibilité en faveur de l'UPEP Tanganyika ZR-MINAGRI-78926-GO- Support Services and Project 2018-09- 2018-10- 2018-09- 2018-10- 2018-11- 2019-04- DIR / Acquisition des IDA / 58520 Post Direct Selection Direct 700,000.00 461,362.00 Signed Management 15 22 20 25 30 23 véhicules 4X4 TT auprès de l'UNOPS ZR-MINAGRI-78949-GO- Pending Support Services and Project 2018-09- 2018-09- 2018-10- 2019-04- DIR / Acquisition des motos IDA / 58520 Post Direct Selection Direct 110,000.00 0.00 Implementat Management 15 20 25 23 DT 125 auprès de l'UNOPS ion ZR-MINAGRI-105380-GO- RFQ / Fourniture et montage des mobiliers pour le Pending personnel complémentaire Support Services and Project Request for Single Stage - One 2019-04- 2019-06- 2019-12- IDA / 58520 Post Limited 65,200.00 0.00 Implementat du PICAGL, la salle de Management Quotations Envelope 23 18 15 ion réunions du SG Agriculture et pour les services de l'Agriculture(SNSA, DPPV et DMPCC) ZR-MINAGRI-105371-GO- RFQ / Fourniture et Pending installation de matériels de Support Services and Project Request for Single Stage - One 2019-04- 2019-06- 2020-06- IDA / 58520 Post Limited 80,000.00 0.00 Implementat connexion internet pour le Management Quotations Envelope 23 18 17 ion bureau complémentaire de l'UNCP PICAGL ZR-MINAGRI-105378-GO- RFQ / Acquisition de fournitures de bureau et Pending consommables informatiques Support Services and Project Request for Single Stage - One 2019-05- 2019-06- 2019-12- IDA / 58520 Post Limited 60,000.00 0.00 Implementat en faveur de l'Unité Nationale Management Quotations Envelope 01 26 23 ion de Projet et les services impliqués du MINAGRI, PEL et DR ZR-MINAGRI-105314-GO- RFQ / Fourniture et mise en Pending service des matériels de Support Services and Project Request for Single Stage - One 2018-10- 2018-12- 2019-03- IDA / 58520 Post Limited 5,000.00 0.00 Implementat laboratoire du Service Management Quotations Envelope 24 19 19 ion National des Fertilisants et Intrants Connexes(SENAFIC) ZR-MINAGRI-105370-GO- RFQ / Acquisition des matériels de sensibilisation Support Services and Project Request for Single Stage - One 2019-06- 2019-05- 2019-07- 2019-06- 2020-01- IDA / 58520 Post Limited 15,000.00 14,523.75 Signed et visibilité en faveur de Management Quotations Envelope 02 30 28 25 24 l'UPEP Tanganyika pour l'exercice 2019 ZR-MINAGRI-105372-GO- RFQ / Fourniture et montage des mobiliers pour les Support Services and Project Request for Single Stage - One 2019-10- 2018-10- 2019-11- 2018-12- 2020-05- 2019-04- IDA / 58520 Post Limited 15,000.00 27,400.00 Completed inspections provinciales de Management Quotations Envelope 03 28 28 03 26 08 l'Agriculture et Dévelopement Rural de Tanganyka ZR-MINAGRI-105353-GO- RFQ / Fourniture et installation des matériels informatiques et de Support Services and Project Request for Single Stage - One 2019-10- 2019-05- 2019-11- 2019-06- 2020-05- reprographie pour les IDA / 58520 Post Limited 13,000.00 12,895.00 Signed Management Quotations Envelope 03 28 28 21 26 services du Ministère provincial de l'Agriculture, Pêche et Elevage et du Développement Rural du Tanganyka ZR-MINAGRI-105392-GO- RFQ / Acquisition de fournitures de bureau et consommables informatiques Support Services and Project Request for Single Stage - One 2019-05- 2019-05- 2019-06- 2019-06- 2019-12- IDA / 58520 Post Limited 18,000.00 17,971.65 Signed pour l'UPEP, les Inspections Management Quotations Envelope 03 30 28 21 25 Provinciales de l'Agriculture et du Développement Rural de Tanganyika ZR-MINAGRI-105400-GO- RFQ / Fourniture et installation du groupe electrogène de 60 kva pour Support Services and Project Request for Single Stage - One 2019-10- 2019-05- 2019-11- 2019-06- 2020-05- 2019-08- IDA / 58520 Post Limited 30,000.00 29,958.50 Completed le bâtiment l'inspection Management Quotations Envelope 03 24 28 12 26 23 provinciale de l'Agriculture et du Développement Rural Tanganyika ZR-MINAGRI-105329-GO- RFQ / Fourniture et installation de 20 splits de 12.000 BTU (dont 2 pour les Pending Support Services and Project Request for Single Stage - One 2019-10- 2019-11- 2020-05- locaux serveurs et 18 pour IDA / 58520 Post Limited 16,000.00 0.00 Implementat Management Quotations Envelope 03 28 26 les bureaux des inspections ion de l'Agriculrure et du Développement Rural) en faveur de l'UPEP Tanganyika ZR-MINAGRI-105323-GO- RFQ / Acquisition des Support Services and Project Request for Single Stage - One 2019-04- 2019-10- 2019-06- 2019-11- 2019-12- 2020-01- mobiliers des bureaux pour IDA / 58520 Post Limited 15,000.00 12,331.00 Completed Management Quotations Envelope 15 09 10 12 07 22 l'inspection provinciale de l'agriculture au Sud KIVU ZR-MINAGRI-105359-GO- RFQ / Acquisition des matériels informatiques pour Support Services and Project Request for Single Stage - One 2019-09- 2019-08- 2019-11- 2019-09- 2020-05- 2019-10- IDA / 58520 Post Limited 13,000.00 12,200.00 Completed les services du Ministère Management Quotations Envelope 21 16 16 17 14 02 Provincial de l’agriculture et UPEP Sud Kivu ZR-MINAGRI-105402-GO- RFQ / Acquisition de Support Services and Project Request for Single Stage - One 2019-04- 2019-06- 2019-06- 2019-08- 2019-12- carburant et lubrifiant pour IDA / 58520 Post Limited 15,000.00 9,996.80 Signed Management Quotations Envelope 12 26 07 28 04 les véhicules de l'UPEP PICAGL Sud Kivu Pending ZR-MINAGRI-105278-GO- Support Services and Project Request for Single Stage - One 2019-04- 2019-05- 2020-05- IDA / 58520 Post Limited 10,000.00 0.00 Implementat RFQ / travaux Management Quotations Envelope 01 27 26 ion ZR-MINAGRI-117750-GO- RFQ / Fourniture et Support Services and Project Request for Single Stage - One 2019-07- 2019-06- 2019-09- 2019-08- 2019-11- 2019-10- installation de groupe IDA / 58520 Post Limited 25,000.00 20,760.50 Completed Management Quotations Envelope 30 26 24 28 08 02 électrogène de 60 Kva pour le bureau de l'UPEP/Sud-Kivu ZR-MINAGRI-117751-GO- RFQ / Acquisition de fournitures de bureau et Support Services and Project Request for Single Stage - One 2019-07- 2019-10- 2019-09- 2019-11- 2019-11- consommables informatiques IDA / 58520 Post Limited 25,000.00 17,802.50 Signed Management Quotations Envelope 30 09 24 12 08 pour l'UPEP/Sud-Kivu, les Inspections de l'Agriculture et du Développement Rural ZR-MINAGRI-133012-GO- DIR / Acquisition et livraison de 2 véhicules Pending complémentaires pour le Support Services and Project 2019-10- 2019-10- 2019-12- 2019-12- IDA / 58520 Post Direct Selection Direct 110,000.00 0.00 Implementat Laboratoire Vétérinaire de Management 25 30 04 13 ion Kinshasa(LABOVET) et le Secrétariat Général au Développement Rural ZR-MINAGRI-170574-GO- RFQ / Acquisition mobiliers Pending Support Services and Project Request for Single Stage - One 2020-06- 2020-08- 2021-02- de bureaux complémentaires IDA / 58520 Post Limited 10,500.00 0.00 Implementat Management Quotations Envelope 20 15 11 pour le personnel l'UPEP ion Tanganyika ZR-MINAGRI-169843-GO- RFQ / Acquisition matériels de visibilité et sensibilisation Pending Support Services and Project Request for Single Stage - One 2020-05- 2020-07- 2021-01- du mécanisme de Gestion IDA / 58520 Post Limited 15,000.00 0.00 Implementat Management Quotations Envelope 20 15 11 des Plaintes (MGP) en faveur ion de l'UPEP Tanganyika exercice 2020 Tanganyika ZR-MINAGRI-169881-GO- RFQ / Fourniture et installation de splits de Pending 12000 BTU pour les bureaux Support Services and Project Request for Single Stage - One 2020-06- 2020-08- 2021-02- IDA / 58520 Post Limited 28,000.00 0.00 Implementat des inspections de Management Quotations Envelope 20 15 11 ion l'Agriculture et du Développement Rural de la province de Tanganyika ZR-MINAGRI-169913-GO- RFQ / Recrutement d'un prestataire pour l'entretien et Pending la réparation des splits des Support Services and Project Request for Single Stage - One 2020-06- 2020-08- 2021-02- IDA / 58520 Post Limited 15,000.00 0.00 Implementat bureaux des Inspections de Management Quotations Envelope 25 20 16 ion l'Agriculture et du Développement Rural de la Province de Tanganyika ZR-MINAGRI-169918-GO- CDD / Acquisitions de 52 Community Pending taureaux (géniteurs) en Agriculture Value Chain 2020-05- 2020-06- 2020-07- 2021-01- IDA / 58520 Post Driven Direct 120,000.00 0.00 Implementat faveur de l'Inspection Development 30 04 09 05 Development ion Provinciale de l'Agriculture, Pêche et Elevage du Sud Kivu Page 4 ZR-MINAGRI-169991-GO- RFQ / Acquisition des fournitures de bureau et consommables informatiques Pending pour les services des Support Services and Project Request for Single Stage - One 2020-01- 2020-03- 2020-09- IDA / 58520 Post Limited 25,000.00 0.00 Implementat Ministères provinciaux de Management Quotations Envelope 20 16 12 ion l'Agriculture, Pêche et Elevage et du Développement Rural et l'UPEP Tanganyika (Exercice 2020) ZR-MINAGRI-169902-GO- RFQ / Fourniture et Pending installation des kits solaires Support Services and Project Request for Single Stage - One 2020-06- 2020-08- 2021-02- IDA / 58520 Post Limited 20,000.00 0.00 Implementat pour le bâtiment de Management Quotations Envelope 20 15 11 ion l'inspection provinciale de l'Agriculture de Tanganyika ZR-MINAGRI-169993-GO- RFQ / Installation des équipements de la connexion internet ainsi que Pending l’abonnement annuel pour Support Services and Project Request for Single Stage - One 2020-06- 2020-08- 2021-02- IDA / 58520 Post Limited 30,000.00 0.00 Implementat les Bureaux de UPEP et des Management Quotations Envelope 20 15 11 ion Inspections Provinciales de l’Agriculture, Pêche, Elevage et du Développement Rural de Tanganyika ZR-MINAGRI-170560-GO- RFQ / Acquisition et installation de mobiliers de Support Services and Project Request for Single Stage - One 2020-08- 2020-03- 2020-10- 2020-05- 2021-04- bureau du Ministère IDA / 58520 Post Limited 15,000.00 11,020.00 Signed Management Quotations Envelope 20 19 15 05 13 Provincial de l"Agriculture, Pêche et Elevage, et Développement Rural du Sud- Kivu ZR-MINAGRI-170565-GO- RFQ / Fourniture et installation des kits solaires Support Services and Project Request for Single Stage - One 2020-08- 2020-11- 2020-10- 2021-01- 2021-04- IDA / 58520 Post Limited 20,000.00 31,318.90 Signed pour le bâtiment de Management Quotations Envelope 20 18 15 15 13 l'inspection provinciale de l'Agriculture de Sud Kivu ZR-MINAGRI-170575-GO- RFQ / Acquisition, installation et fourniture internet pour le nouveau Support Services and Project Request for Single Stage - One 2020-07- 2020-09- 2020-09- 2020-11- 2021-03- bâtiment des Inspections IDA / 58520 Post Limited 26,000.00 7,051.50 Signed Management Quotations Envelope 15 15 09 09 08 Provinciales de l'Agriculture, Pêche et Elevage, et du Développement Rural du Sud- Kivu et du Ministère Provincial ZR-MINAGRI-169976-GO- RFQ / Acquisition et montage des équipements informatiques et bureaux pour la coordination Support Services and Project Request for Single Stage - One 2020-05- 2020-02- 2020-07- 2020-03- 2021-01- 2020-09- provinciale du Sud-Kivu (4 IDA / 58520 Post Limited 32,000.00 21,715.00 Completed Management Quotations Envelope 20 17 15 24 11 04 onduleurs, 4 imprimentes, 4 stabilisateurs pour les 4 spécialistes, photocopiie en couleur) et pour le Ministre Provincial Agric du Sud Kivu ZR-MINAGRI-169898-GO- RFQ / Acquisition matériels de visibilité pour l'UPEP Sud Support Services and Project Request for Single Stage - One 2020-05- 2020-02- 2020-07- 2020-03- 2021-01- 2020-08- Kivu ( Roll up, T-shirt, IDA / 58520 Post Limited 30,000.00 28,270.00 Completed Management Quotations Envelope 21 17 16 24 12 21 Calendrier, Gilets, Képis, Agendas, Dépliants) pour l'exercice 2020 ZR-MINAGRI-169728-GO- RFQ / Acquisition des matériels et d'équipements Support Services and Project Request for Single Stage - One 2020-05- 2020-04- 2020-07- 2020-06- 2021-01- 2020-07- IDA / 58520 Post Limited 5,000.00 2,485.00 Completed de terrain (imperméables, Management Quotations Envelope 22 27 17 10 13 15 bottes, parapluies) en faveur de l'UPEP Sud Kivu ZR-MINAGRI-169813-GO- RFQ / Reproduction de guide Pending Support Services and Project Request for Single Stage - One 2020-05- 2020-07- 2021-01- des bonnes pratiques pour la IDA / 58520 Post Limited 7,500.00 0.00 Implementat Management Quotations Envelope 23 18 14 production végétales et ion animales au Sud Kivu ZR-MINAGRI-187940-GO- Pending RFQ / Acquisition des Support Services and Project Request for Single Stage - One 2020-10- 2020-11- 2021-05- IDA / 58520 Post Limited 150,000.00 0.00 Implementat matériels de visibilité et de Management Quotations Envelope 05 30 29 ion sensibilisation pour l'UNCP ZR-MINAGRI-188537-GO- RFQ / Acquisition mobiliers Pending Support Services and Project Request for Single Stage - One 2020-04- 2020-06- 2020-12- de bureaux complémentaires IDA / 58520 Post Limited 20,000.00 0.00 Implementat Management Quotations Envelope 20 15 12 pour le personnel de l 'UPEP ion Tanganyika ZR-MINAGRI-188508-GO- RFQ / Acquisition des équipements de transformation du manioc en Pending Agriculture Value Chain Request for Single Stage - One 2020-11- 2020-12- 2021-06- faveur de dix (10) Centres IDA / 58520 Post Limited 150,000.00 0.00 Implementat Development Quotations Envelope 04 30 28 Communautaires de ion Transformation de manioc dans la Province du Tanganyika ZR-MINAGRI-188515-GO- RFQ / Acquisition des équipements de Pending transformation du manioc en Agriculture Value Chain Request for Single Stage - One 2020-11- 2020-12- 2021-06- IDA / 58520 Post Limited 100,000.00 0.00 Implementat faveur de dix (10) Centres Development Quotations Envelope 05 31 29 ion Communautaires de Transformation de Maïs dans la Province du Tanganyika ZR-MINAGRI-188533-GO- RFQ / Acquisition d'1 drone et d' 1 appareil photo Pending professionnel et camera Support Services and Project Request for Single Stage - One 2020-11- 2021-01- 2021-06- IDA / 58520 Post Limited 6,000.00 0.00 Implementat hybride pour la couverture Management Quotations Envelope 06 01 30 ion communicationnelle des activités du Projet dans la Province du Tanganyika ZR-MINAGRI-188499-GO- RFQ / Acquisition de 5 motos en faveur de Délégués à Pied Pending d'Ouevre en charge de la Agriculture Value Chain Request for Single Stage - One 2020-11- 2021-01- 2021-07- IDA / 58520 Post Limited 24,000.00 0.00 Implementat surveillance des travaux de Development Quotations Envelope 07 02 01 ion construction des Centres Communautaires dans la Province du Tanganyika ZR-MINAGRI-188507-GO- RFQ / Acquisition de Pending matériels et équipements de Agriculture Value Chain Request for Single Stage - One 2020-10- 2020-12- 2021-06- IDA / 58520 Post Limited 60,000.00 0.00 Implementat provenderie pour les Development Quotations Envelope 25 20 18 ion éleveurs et les OP dans la ville de Kalemie/Tanganyika ZR-MINAGRI-188504-GO- RFQ / Acquisition et installation de 6 Pending Décortiqueuse à riz des Agriculture Value Chain Request for Single Stage - One 2020-11- 2020-12- 2021-06- IDA / 58520 Post Limited 120,000.00 0.00 Implementat coopératives rizicoles dans Development Quotations Envelope 03 29 27 ion les six bassins de production, territoire de Kalemie dans la province de Tanganyika MOF-REF-26 / Acquisition de 10 Tricycles pour la collecte de paddy des Pending Agriculture Value Chain Request for Single Stage - One 2020-11- 2020-12- 2021-06- coopératives rizicoles dans IDA / Q9610 Post Limited 50,000.00 0.00 Implementat Development Quotations Envelope 04 30 28 les six bassins de ion production, territoire de Kalemie dans la province de Tanganyika ZR-MINAGRI-188542-GO- RFQ / Acquisition de dix (10) Cages flottantes complètes Pending Agriculture Value Chain Request for Single Stage - One 2020-11- 2020-12- 2021-06- avec accessoires et IDA / 58520 Post Limited 40,000.00 0.00 Implementat Development Quotations Envelope 05 31 29 installation dans le territoire ion de Kalemie dans la province de Tanganyika ZR-MINAGRI-188505-GO- RFQ / Aiquisition et installation de 4 unités de pêche complete pour l'approvisionnement regulier Pending Agriculture Value Chain Request for Single Stage - One 2020-11- 2021-01- 2021-06- en poisson des unités de IDA / 58520 Post Limited 120,000.00 0.00 Implementat Development Quotations Envelope 06 01 30 transformation de plateforme ion et conservation du poisson à Kasambondo, Kabuga, Kalemie et Kabimba dans la Province du Tanganyika ZR-MINAGRI-188526-GO- RFQ / Fourniture, installation des matériels pour Pending Support Services and Project Request for Single Stage - One 2020-08- 2020-10- 2021-04- connexion internet ainsi que IDA / 58520 Post Limited 13,000.00 0.00 Implementat Management Quotations Envelope 20 15 13 l'abonnement annuel en ion faveur du bureau du Ministre de l'agriculture de Tanganyika ZR-MINAGRI-188544-GO- RFQ / Acquisition et installation de 10 splits muraux en faveur du Support Services and Project Request for Single Stage - One 2020-09- 2020-08- 2020-11- 2020-11- 2021-05- bâtiment devant servir des IDA / 58520 Post Limited 8,500.00 8,100.00 Signed Management Quotations Envelope 20 24 15 09 14 bureaux pour l'UPEP et Inspections Provinciales de de l'Agriculture et Pêche de la Prvonce du Sud Kivu Page 5 ZR-MINAGRI-188511-GO- RFB / Acquisition d'un lot de 120 génisses pour les Pending Agriculture Value Chain Single Stage - One 2020-10- 2020-10- 2020-12- 2021-01- 2021-02- 2021-08- coopératives, les éleveurs IDA / 58520 Post Request for Bids Open - National 100,000.00 0.00 Implementat Development Envelope 16 21 02 01 05 04 particuliers et les OP dans le ion territoire de Kalemie/Tanganyika ZR-MINAGRI-188502-GO- RFQ / Acquisition des équipements de Pending transformation du manioc en Agriculture Value Chain Request for Single Stage - One 2020-11- 2021-01- 2021-06- IDA / 58520 Post Limited 90,000.00 0.00 Implementat faveur de Centres Development Quotations Envelope 06 01 30 ion Communautaires de Transformation du Riz dans la Province du Tanganyika ZR-MINAGRI-187936-GO- RFQ / Fourniture et mise en service des matériels Pending informatiques, de Support Services and Project Request for Single Stage - One 2020-11- 2020-12- 2021-02- IDA / 58520 Post Limited 250,000.00 0.00 Implementat reproduction et de Management Quotations Envelope 03 29 27 ion vidéoconférence pour le personnel du projet ainsi que les services impliqués ZR-MINAGRI-209975-GO- RFQ / Acquisition de fournitures de bureau et consommables informatiques Pending Support Services and Project Request for Single Stage - One 2020-12- 2021-02- 2021-08- pour l’UPEP PICAGL Sud-Kivu IDA / 58520 Post Limited 30,000.00 0.00 Implementat Management Quotations Envelope 25 19 18 et les Inspections ion provinciales de l'Agriculture, Pêche et Elevage, et du Développement Rural du Sud- Kivu ZR-MINAGRI-210054-GO- RFQ / Acquisition des moulins à manioc en faveur Pending Agriculture Value Chain Request for Single Stage - One 2021-02- 2021-04- 2021-10- de vingt-deux (22) Centres IDA / 58520 Post Limited 66,000.00 0.00 Implementat Development Quotations Envelope 15 12 09 de Collecte et de ion Transformation de Manioc, dans le cadre du PICAGL, UPEP Sud-Kivu ZR-MINAGRI-210048-GO- RFQ / Acquisition des presses à vérins hydrauliques Pending motorisées en faveur de Agriculture Value Chain Request for Single Stage - One 2021-02- 2021-04- 2021-10- IDA / 58520 Post Limited 98,000.00 0.00 Implementat vingt-deux (22) Centres de Development Quotations Envelope 15 12 09 ion Collecte et de Transformation de Manioc, dans le cadre du PICAGL, UPEP Sud-Kivu ZR-MINAGRI-210053-GO- RFQ / Acquisition des râpeuses avec châssis en Pending faveur de vingt-deux (22) Agriculture Value Chain Request for Single Stage - One 2021-02- 2021-04- 2021-10- IDA / 58520 Post Limited 60,000.00 0.00 Implementat Centres de Collecte et de Development Quotations Envelope 15 12 09 ion Transformation de Manioc, dans le cadre du PICAGL, UPEP Sud-Kivu ZR-MINAGRI-210046-GO- RFQ / Acquisition des séchoirs solaires en faveur Pending Agriculture Value Chain Request for Single Stage - One 2021-02- 2021-04- 2021-10- de vingt-deux (22) Centres IDA / 58520 Post Limited 66,000.00 0.00 Implementat Development Quotations Envelope 15 12 09 de Collecte et de ion Transformation de Manioc, dans le cadre du PICAGL, UPEP Sud-Kivu ZR-MINAGRI-210051-GO- RFQ / Acquisition des kits d'insémination artificielle en Pending Agriculture Value Chain Request for Single Stage - One 2021-02- 2021-04- 2021-10- faveur de trois (3) IDA / 58520 Post Limited 25,000.00 0.00 Implementat Development Quotations Envelope 22 19 16 institutions et cabinets ion spécialisés, dans le cadre du PICAGL, UPEP Sud-Kivu ZR-MINAGRI-210058-GO- RFQ / Acquisition des Pending équipements en faveur de Agriculture Value Chain Request for Single Stage - One 2021-02- 2021-04- 2021-10- IDA / 58520 Post Limited 45,000.00 0.00 Implementat deux (2) micro-minoteries Development Quotations Envelope 22 19 16 ion du riz, dans le cadre du PICAGL, UPEP Sud-Kivu ZR-MINAGRI-210056-GO- RFQ / Acquisition des Pending équipements en faveur d'un Agriculture Value Chain Request for Single Stage - One 2021-03- 2021-04- 2021-10- IDA / 58520 Post Limited 35,000.00 0.00 Implementat (1) Centre de Collecte du Development Quotations Envelope 01 26 23 ion Lait, dans le cadre du PICAGL, UPEP Sud-Kivu ZR-MINAGRI-210059-GO- RFQ / Fourniture et Pending installation des kits solaires Agriculture Value Chain Request for Single Stage - One 2021-03- 2021-04- 2021-10- IDA / 58520 Post Limited 35,000.00 0.00 Implementat en faveur d'un (1) Centre de Development Quotations Envelope 01 26 23 ion Collecte du Lait, dans le cadre du PICAGL, UPEP Sud- Kivu ZR-MINAGRI-210055-GO- RFQ / Acquisition des équipements en faveur de Pending Agriculture Value Chain Request for Single Stage - One 2021-02- 2021-04- 2021-10- trois (3) Provenderies à IDA / 58520 Post Limited 28,000.00 0.00 Implementat Development Quotations Envelope 22 19 16 Luvungi, Kabare et Bukavu, ion dans le cadre du PICAGL, UPEP Sud-Kivu ZR-MINAGRI-210082-GO- RFQ / Acquisition de vingt (20) tricycles motorisés en faveur de coopératives, associations et autres, pour Pending Agriculture Value Chain Request for Single Stage - One 2021-02- 2021-04- 2021-10- la collecte et le transport de IDA / 58520 Post Limited 80,000.00 0.00 Implementat Development Quotations Envelope 24 21 18 paddy, manioc, boutures, ion lait,..., dans le bassin d'Uvira, Province du Sud-Kivu,dans le cadre du PICAGL, UPEP Sud- Kivu ZR-MINAGRI-210084-GO- RFQ / Acquisition de dix (10) tricycles motorisés en faveur de coopératives, associations Pending et autres, pour la collecte et Agriculture Value Chain Request for Single Stage - One 2021-02- 2021-04- 2021-10- IDA / 58520 Post Limited 40,000.00 0.00 Implementat le transport de paddy, Development Quotations Envelope 24 21 18 ion manioc, boutures, lait, ... dans le bassin de Fizi, Province du Sud-Kivu, dans le cadre du PICAGL, UPEP Sud- Kivu ZR-MINAGRI-210081-GO- RFQ / Acquisition de dix- sept (17) tricycles motorisés en faveur de coopératives, Pending associations et autres, pour Agriculture Value Chain Request for Single Stage - One 2021-02- 2021-04- 2021-10- IDA / 58520 Post Limited 68,000.00 0.00 Implementat la collecte et le transport de Development Quotations Envelope 24 21 18 ion paddy, manioc, boutures, lait,..., dans les bassins de Kalehe, Kabare et Walungu, Province du Sud-Kivu ZR-MINAGRI-210090-GO- RFQ / Acquisition des Pending Agriculture Value Chain Request for Single Stage - One 2021-02- 2021-04- 2021-10- produits vétérinaires, dans le IDA / 58520 Post Limited 95,000.00 0.00 Implementat Development Quotations Envelope 22 19 16 cadre du PICAGL, UPEP Sud- ion Kivu ZR-MINAGRI-210086-GO- RFQ / Acquisition des découpeuses avec châssis en Pending faveur de vingt-deux (22) Agriculture Value Chain Request for Single Stage - One 2021-02- 2021-04- 2021-10- IDA / 58520 Post Limited 55,000.00 0.00 Implementat Centres de Collecte et de Development Quotations Envelope 15 12 09 ion Transformation de Manioc,dans le cadre du PICAGL, UPEP Sud-Kivu ZR-MINAGRI-210089-GO- RFQ / Acquisition des machines pour coudre les sacs en faveur de vingt-deux Pending Agriculture Value Chain Request for Single Stage - One 2021-02- 2021-04- 2021-10- (22) Centres de Collecte et IDA / 58520 Post Limited 25,000.00 0.00 Implementat Development Quotations Envelope 15 12 09 de Transformation de Manioc ion et trois (3) provenderies, dans le cadre du PICAGL, UPEP Sud-Kivu ZR-MINAGRI-210446-GO- RFQ / Acquisition des matériels et équipements pour le conditionnement et la conservation du lait en Pending Agriculture Value Chain Request for Single Stage - One 2021-02- 2021-04- 2021-10- faveur de huit (8) mini- IDA / 58520 Post Limited 50,000.00 0.00 Implementat Development Quotations Envelope 17 14 11 laiteries de type 3, quatorze ion (14) mini-laiteries de type 2 et deux (2) mini-laiteries de type 1, dans le cadre du PICAGL, UPEP Sud-Kivu ZR-MINAGRI-210445-GO- RFQ / Acquisition des matériels pour la pasteurisation du lait en Pending Agriculture Value Chain Request for Single Stage - One 2021-02- 2021-04- 2021-10- faveur de huit (8) mini- IDA / 58520 Post Limited 45,000.00 0.00 Implementat Development Quotations Envelope 17 14 11 laiteries de type 3 et ion quatorze (14) mini-laiteries de type 2, dans le cadre du PICAGL, UPEP Sud-Kivu ZR-MINAGRI-210448-GO- RFQ / Acquisition des réchauds à gaz en faveur de Pending huit (8) mini-laiteries de type Agriculture Value Chain Request for Single Stage - One 2021-02- 2021-04- 2021-10- IDA / 58520 Post Limited 12,000.00 0.00 Implementat 3 et quatorze (14) mini- Development Quotations Envelope 17 14 11 ion laiteries de type 2, dans le cadre du PICAGL, UPEP Sud- Kivu Page 6 ZR-MINAGRI-210449-GO- RFQ / Acquisition des kits solaires en faveur de huit (8) mini-laiteries de type 3, Pending Agriculture Value Chain Request for Single Stage - One 2021-02- 2021-04- 2021-10- quatorze (14) mini-laiteries IDA / 58520 Post Limited 36,000.00 0.00 Implementat Development Quotations Envelope 17 14 11 de type 2 et deux (2) mini- ion laiteries de type 1, dans le cadre du PICAGL, UPEP Sud- Kivu ZR-MINAGRI-210642-GO- RFQ / Acquisition des matériels d’entreposage en faveur de 33 mini-minoteries Pending de manioc, 19 rizeries de Agriculture Value Chain Request for Single Stage - One 2021-02- 2021-04- 2021-10- IDA / 58520 Post Limited 50,000.00 0.00 Implementat type 1 (Zaccaria ou Development Quotations Envelope 20 17 14 ion équivalent), 6 rizeries de type 2 (SB-50 ou équivalent) et 3 provenderies, dans le cadre du Projet PICAGL, UPEP Sud-Kivu ZR-MINAGRI-210644-GO- RFQ / Acquisition des sacs d’emballage en faveur de 33 mini-minoteries de manioc, Pending 19 rizeries de type 1 Agriculture Value Chain Request for Single Stage - One 2021-02- 2021-04- 2021-10- IDA / 58520 Post Limited 40,000.00 0.00 Implementat (Zaccaria ou équivalent), 6 Development Quotations Envelope 16 13 10 ion rizeries de type 2 (SB-50 ou équivalent) et 3 provenderies, dans le cadre du Projet PICAGL, UPEP Sud- Kivu ZR-MINAGRI-210645-GO- RFQ / Acquisition des équipements en faveur de Pending Agriculture Value Chain Request for Single Stage - One 2021-02- 2021-04- 2021-10- trente-trois (33) mini IDA / 58520 Post Limited 99,000.00 0.00 Implementat Development Quotations Envelope 20 17 14 minoteries de manioc, dans ion le cadre du Projet PICAGL, UPEP Sud-Kivu ZR-MINAGRI-210646-GO- RFQ / Acquisition des décortiqueuses en faveur de Pending Agriculture Value Chain Request for Single Stage - One 2021-02- 2021-04- 2021-10- six (6) rizeries de type 2 (SB- IDA / 58520 Post Limited 90,000.00 0.00 Implementat Development Quotations Envelope 20 17 14 50 ou équivalent), dans le ion cadre du Projet PICAGL, UPEP Sud-Kivu ZR-MINAGRI-210647-GO- RFQ / Acquisition des générateurs d'énergie en faveur de 33 mini-minoteries Pending Agriculture Value Chain Request for Single Stage - One 2021-02- 2021-04- 2021-10- de manioc, 19 rizeries de IDA / 58520 Post Limited 72,000.00 0.00 Implementat Development Quotations Envelope 20 17 14 type 1 (Zaccaria ou ion équivalent) et 6 rizeries de type 2 (SB-50 ou équivalent), dans le cadre du PICAGL, UPEP Sud-Kivu ZR-MINAGRI-211078-GO- RFQ / Acquisition, installation et fourniture de la connexion internet aux Pending Support Services and Project Request for Single Stage - One 2021-01- 2021-03- 2021-09- bureaux de l'UPEP Sud-Kivu IDA / 58520 Post Limited 20,000.00 0.00 Implementat Management Quotations Envelope 30 27 23 et du Ministre Provincial de ion l'Agriculture, Pêche et Elevage, et Développement Rural du Sud-Kivu ZR-MINAGRI-211393-GO- RFQ / Acquisition des taureaux géniteurs de race Pending Agriculture Value Chain Request for Single Stage - One 2021-02- 2021-04- 2021-10- améliorée à livrer dans le IDA / 58520 Post Limited 25,000.00 0.00 Implementat Development Quotations Envelope 27 24 21 bassin de Fizi-Mutambala, ion dans le cadre du PICAGL, UPEP Sud-Kivu ZR-MINAGRI-211394-GO- RFQ / Acquisition des taureaux géniteurs de race Pending Agriculture Value Chain Request for Single Stage - One 2021-02- 2021-04- 2021-10- améliorée à livrer dans la IDA / 58520 Post Limited 70,000.00 0.00 Implementat Development Quotations Envelope 27 24 21 plaine de Ruzizi et moyens ion plateaux, dans le cadre du PICAGL, UPEP Sud-Kivu ZR-MINAGRI-211397-GO- RFQ / Acquisition des Pending taureaux géniteurs de race Agriculture Value Chain Request for Single Stage - One 2021-02- 2021-04- 2021-10- IDA / 58520 Post Limited 50,000.00 0.00 Implementat améliorée à livrer à Kalehe, Development Quotations Envelope 27 24 21 ion dans le cadre du PICAGL, UPEP Sud-Kivu ZR-MINAGRI-211395-GO- RFQ / Acquisition des Pending taureaux géniteurs de race Agriculture Value Chain Request for Single Stage - One 2021-02- 2021-04- 2021-10- IDA / 58520 Post Limited 25,000.00 0.00 Implementat améliorée à livrer à Walungu, Development Quotations Envelope 27 24 21 ion dans le cadre du PICAGL, UPEP Sud-Kivu ZR-MINAGRI-211396-GO- RFQ / Acquisition des Pending taureaux géniteurs de race Agriculture Value Chain Request for Single Stage - One 2021-02- 2021-04- 2021-10- IDA / 58520 Post Limited 55,000.00 0.00 Implementat améliorée à livrer à Kabare, Development Quotations Envelope 27 24 21 ion dans le cadre du PICAGL, UPEP Sud-Kivu ZR-MINAGRI-214234-GO- RFB / Acquisition des décortiqueuses en faveur de Pending Agriculture Value Chain Single Stage - One 2021-02- 2021-03- 2021-04- 2021-05- 2021-06- 2021-12- dix-neuf (19) rizeries de type IDA / 58520 Post Request for Bids Open - National 500,000.00 0.00 Implementat Development Envelope 26 03 14 14 18 15 1 (Zaccaria Modèle ZX-6 ou ion équivalent), dans le cadre du Projet PICAGL, UPEP Sud-Kivu NON CONSULTING SERVICES Activity Reference No. / Draft Pre- Draft Bidding Bid Evaluation Report Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Prequalification Specific Procurement Bidding Documents Proposal Submission Description Component Review Type Method qualification Document / and Recommendation Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Documents Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-MINAGRI-79168-NC- RFQ / Location des bureaux Pending Support Services and Project Request for Single Stage - One 2018-10- 2018-12- 2019-06- devant abriter le personnel IDA / 58520 Post Limited 60,000.00 0.00 Implementat Management Quotations Envelope 18 13 11 complémentaire de l'UNCP ion PICAGL ZR-MINAGRI-78968-NC- RFQ / Location des bureaux Support Services and Project Request for Single Stage - One 2018-08- 2018-06- 2018-10- 2018-10- 2019-04- devant abriter l’Unité IDA / 58520 Post Limited 30,000.00 30,000.00 Signed Management Quotations Envelope 18 25 13 02 11 Provinciale d’Exécution du PICAGL Sud-Kivu ZR-MINAGRI-79170-NC- RFQ / Fourniture des services Support Services and Project Request for Single Stage - One 2018-09- 2018-07- 2018-11- 2018-10- 2019-05- de gardiennage à l’Unité IDA / 58520 Post Limited 14,000.00 8,940.00 Signed Management Quotations Envelope 08 09 03 04 02 Provinciale d’Exécution du PICAGL Sud-Kivu ZR-MINAGRI-79128-NC- RFQ / Services d’entretien Support Services and Project Request for Single Stage - One 2018-09- 2018-08- 2018-11- 2018-10- 2019-05- des bureaux de l’Unité IDA / 58520 Post Limited 9,600.00 7,200.00 Signed Management Quotations Envelope 08 20 03 04 02 Provinciale d’Exécution du PICAGL Sud-Kivu ZR-MINAGRI-79094-NC-DIR / Location des bureaux Support Services and Project 2018-08- 2018-09- 2018-08- 2018-09- 2018-09- 2018-09- 2019-03- 2019-09- devant abriter l’Unité IDA / 58520 Post Direct Selection Direct 36,000.00 36,000.00 Completed Management 13 13 18 15 22 15 21 15 Provinciale d’Exécution du PICAGL Tanganyika ZR-MINAGRI-79148-NC- RFQ / Fourniture des services Support Services and Project Request for Single Stage - One 2018-09- 2018-10- 2018-11- 2018-12- 2019-05- de gardiennage à l’Unité IDA / 58520 Post Limited 14,000.00 11,720.00 Signed Management Quotations Envelope 08 23 03 04 02 Provinciale d’Exécution du PICAGL Tanganyika ZR-MINAGRI-78928-NC- RFQ / Services d’entretien Support Services and Project Request for Single Stage - One 2018-09- 2018-10- 2018-11- 2018-12- 2019-05- des bureaux de l’Unité IDA / 58520 Post Limited 9,600.00 7,200.00 Signed Management Quotations Envelope 08 24 03 06 02 Provinciale d’Exécution du PICAGL Tanganyika ZR-MINAGRI-105102-NC- RFQ / Prestataire de service Pending pour le gardiennage des Support Services and Project Request for Single Stage - One 2019-04- 2019-06- 2020-06- IDA / 58520 Post Limited 17,000.00 0.00 Implementat bureaux du personnel Management Quotations Envelope 06 01 01 ion complémentaire de l'UNCP PICAGL ZR-MINAGRI-105298-NC- RFQ / Prestataire de service Pending Support Services and Project Request for Single Stage - One 2018-10- 2018-12- 2019-12- pour le nettoyage des IDA / 58520 Post Limited 15,000.00 0.00 Implementat Management Quotations Envelope 18 13 12 bureaux du personnel ion complémentaire de l'UNCP PICAGL ZR-MINAGRI-105101-NC- RFQ / Affretement d'un avion Pending Support Services and Project Request for Single Stage - One 2019-03- 2019-05- 2019-11- pour les missions conjointes IDA / 58520 Post Limited 100,000.00 0.00 Implementat Management Quotations Envelope 18 13 09 de supervision ion (Gouvernement Banque mondiale) ZR-MINAGRI-105389-NC- RFQ / Sélection d'un prestataire pour l'entretien et Pending Support Services and Project Request for Single Stage - One 2019-04- 2019-05- 2020-05- réparation des véhicules, IDA / 58520 Post Limited 14,000.00 0.00 Implementat Management Quotations Envelope 02 28 05 motos motos et groupe ion électrogène(IRD) pour l'UPEP Tanganyika ZR-MINAGRI-105388-NC- RFQ / Sélection d'un Pending Support Services and Project Request for Single Stage - One 2019-11- 2019-12- 2020-06- prestataire pour l'entretien et IDA / 58520 Post Limited 14,000.00 0.00 Implementat Management Quotations Envelope 02 28 25 réparation des splits muraux ion pour l'UPEP Tanganyika Page 7 ZR-MINAGRI-105296-NC- RFQ / Recrutement d'un prestataire pour l'entretien et Support Services and Project Request for Single Stage - One 2019-05- 2019-05- 2019-06- 2019-06- 2020-06- réparation des matériels IDA / 58520 Post Limited 8,000.00 7,800.00 Signed Management Quotations Envelope 03 28 28 24 26 informatiques et de reprographie pour l'UPEP Tanganyika MOF-REF-125 / Sélection d'un prestataire pour Pending l'entretien et réparation des Support Services and Project Request for Single Stage - One 2019-04- 2019-06- 2020-06- IDA / 58520 Post Limited 20,000.00 0.00 Implementat véhicules, motos et groupe Management Quotations Envelope 14 09 08 ion électrogène(IRD) pour l'UPEP Sud Kivu ZR-MINAGRI-170554-NC- Pending DIR / Mise à jour et Support Services and Project 2020-07- 2020-07- 2020-09- 2021-03- IDA / 58520 Post Direct Selection Direct 37,500.00 0.00 Implementat utilisation de la version Management 25 30 03 02 ion TOMPRO WEB du logiciel PICAGL ZR-MINAGRI-169816-NC- DIR / Renouvellement du Contrat avec Union pour l'Emancipation de la Femme Support Services and Project 2020-01- 2019-12- 2020-01- 2019-12- 2020-02- 2019-12- 2020-08- IDA / 58520 Post Direct Selection Direct 7,200.00 7,200.00 Signed Autochtone (UEFA ) pour Management 02 01 07 02 11 10 09 l'entretien des bureaux de l’Unité Provinciale d’Exécution de Projet (UPEP) Tanganyika ZR-MINAGRI-169814-NC- DIR / Renouvellement du Contrat avec le prestataire HUMAN DIGNITY IN THE Support Services and Project 2020-01- 2019-12- 2020-01- 2020-02- 2020-02- 2020-02- 2020-08- IDA / 58520 Post Direct Selection Direct 10,920.00 10,920.00 Signed WORLD (HDW) pour le Management 03 02 08 05 12 06 10 gardiennage des bureaux de l’Unité Provinciale d’Exécution de Projet Tanganyika ZR-MINAGRI-169988-NC- RFQ / Selection d'un Under prestataire pour l'entretien et Support Services and Project Request for Single Stage - One 2020-05- 2020-02- 2020-07- 2021-01- IDA / 58520 Post Limited 20,000.00 19,754.20 Implementat réparation des véhicules, Management Quotations Envelope 26 17 21 17 ion motos et groupe electrogène pour l'UPEP Sud-Kivu ZR-MINAGRI-188482-NC- DIR / Contractualisation avec les radios, télévisions communautaires et Associations locales pour la Pending communication sociale de Support Services and Project 2020-08- 2020-08- 2020-09- 2021-03- IDA / 58520 Post Direct Selection Direct 35,000.00 0.00 Implementat proximité dans la Province Management 16 21 25 24 ion du Tanganyika ( RTNC, RTGT, TELE 6, AFYA FM, RADIO KAOZE, COJELTA, CJDT et BAKOYOKA SON naTanganyika) ZR-MINAGRI-170570-NC- RFQ / Contractualisation avec huit radios communautaires au Sud Kivu pour la sensibilisation des Pending Support Services and Project 2020-08- 2020-08- 2020-09- 2021-03- activités du Projet ( Radio IDA / 58520 Post Direct Selection Direct 35,000.00 0.00 Implementat Management 15 20 24 23 Maéndeleo, Radio Umoja, ion Radio Baraka, Radio Messager du Peuple, Radio notre Dame de Tanganyika, Radio Flash FM, Radio AMKA, Radio RTBO) ZR-MINAGRI-196114-NC- RFQ / Recrutement d'un prestataire des services de Support Services and Project Request for Single Stage - One 2020-10- 2020-10- 2020-12- 2020-11- 2021-06- gardiennage des bureaux de IDA / 58520 Post Limited 14,000.00 9,600.00 Signed Management Quotations Envelope 20 02 15 09 13 l’Unité Provinciale d’Exécution du Projet PICAGL (UPEP) / Sud-Kivu ZR-MINAGRI-196116-NC- RFQ / Recrutement d'un prestataire des services d’entretien des bureaux et Support Services and Project Request for Single Stage - One 2020-10- 2020-10- 2020-12- 2020-11- 2021-06- IDA / 58520 Post Limited 14,000.00 10,800.00 Signed d'aménagement de la Cour Management Quotations Envelope 20 02 15 09 13 de l’Unité Provinciale d’Exécution du Projet PICAGL (UPEP) / Sud-Kivu ZR-MINAGRI-210104-NC- RFQ / Recrutement d'un prestataire des services de Pending Support Services and Project Request for Single Stage - One 2021-01- 2021-03- 2021-09- gardiennage des bureaux de IDA / 58520 Post Limited 14,000.00 0.00 Implementat Management Quotations Envelope 10 07 03 l’Unité Provinciale ion d’Exécution du Projet PICAGL (UPEP) / Tanganyika ZR-MINAGRI-210105-NC- RFQ / Recrutement d'un prestataire des services Pending d’entretien des bureaux et Support Services and Project Request for Single Stage - One 2021-01- 2021-03- 2021-09- IDA / 58520 Post Limited 15,000.00 0.00 Implementat d'aménagement de la Cour Management Quotations Envelope 10 07 03 ion de l’Unité Provinciale d’Exécution du Projet PICAGL (UPEP) / Tanganyika CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-PARSSA-4343-CS-CQS / Consultant Recrutement d'un Cabinet Support Services and Project 2016-12- 2017-02- 2017-03- 2016-09- 2017-04- 2016-09- 2017-10- IDA / Q9260 Post Qualification Open - National 90,000.00 81,902.00 Signed 2016-12-08 pour la Sélection du Management 29 11 13 13 17 21 14 Selection Personnel Essentiel du PICAGL ZR-PARSSA-5160-CS-QBS / Elaboration schéma directeur Agriculture Value Chain Quality Based Open - Pending 2015-11- 2016-01- 2016-01- 2016-02- 2016-03- 2016-05- 2017-05- IDA / Q9260 Post 500,000.00 0.00 2015-10-29 sur le corridor Bukavu-Uvira- Development Selection International Implementation 19 02 30 29 30 04 04 Kalemie ZR-MINAGRI-78952-CS- QCBS / Recrutement d'un Support for the development consultant firme pour la Quality And Cost- Pending 2018-10- 2018-12- 2019-01- 2019-02- 2019-03- 2019-04- 2020-04- IDA / 58520 of the private agro- Post Open - National 500,000.00 0.00 2018-10-02 réalisation des études Based Selection Implementation 23 06 03 02 09 13 12 industrial sector sectorielles pour la mise en place de parc agroindustriel ZR-MINAGRI-78955-CS- QCBS / Recrutement d'un Support for the development consultant firme pour la Quality And Cost- Open - Pending 2018-10- 2018-12- 2019-01- 2019-02- 2019-03- 2019-04- 2020-04- IDA / 58520 of the private agro- Post 500,000.00 0.00 2018-10-02 réalisation de l'étude du Based Selection International Implementation 23 06 03 02 09 13 12 industrial sector marché pour le parc agroindustriel ZR-MINAGRI-78984-CS- QCBS / Recrutement d'un Support for the development Quality And Cost- Open - Pending 2018-10- 2018-12- 2019-01- 2019-02- 2019-03- 2019-04- 2020-04- consultant firme pour le IDA / 58520 of the private agro- Post 500,000.00 0.00 2018-10-02 Based Selection International Implementation 23 06 03 02 09 13 12 renforcement des capacités industrial sector des institutions financières ZR-MINAGRI-79138-CS-QBS / Recrutement d'une ONG Agriculture Value Chain Quality Based Under 2020-09- 2018-12- 2019-02- 2019-03- 2019-04- 2019-05- 2019-06- 2020-06- spécialisée dans les IDA / 58520 Post Open - National 150,000.00 0.00 2018-12-01 Development Selection Implementation 11 22 04 04 03 03 07 06 questions des violences basées sur le genre VSBG ZR-MINAGRI-78906-CS- QCBS / Recrutement d'un consultant firme pour la Support Services and Project Quality And Cost- 2018-12- 2019-01- 2019-02- 2019-03- 2019-04- 2019-05- 2020-05- réalisation des études IDA / 58520 Prior Open - National 500,000.00 0.00 Canceled 2018-11-10 Management Based Selection 01 14 11 13 17 22 21 d'orientation pour l'appui aux services fonciers dans l'aire d'intervention du PICAGL ZR-MINAGRI-78816-CS- QCBS / Consultant chargé Agriculture Value Chain Quality And Cost- Pending 2019-01- 2019-02- 2019-03- 2019-04- 2019-05- 2019-06- 2020-06- d'évaluation de la sécurité IDA / 58520 Post Open - National 100,000.00 0.00 2018-12-17 Development Based Selection Implementation 07 20 20 19 24 28 27 alimentaire dans les zones du projet ZR-MINAGRI-79114-CS- QCBS / Recrutement d''un auditeur externe pour la Support Services and Project Quality And Cost- Open - Under 2019-01- 2018-10- 2018-12- 2019-01- 2019-02- 2019-03- 2019-04- 2020-04- certification des états IDA / 58520 Post 170,000.00 0.00 2018-10-02 Management Based Selection International Implementation 19 23 06 03 02 09 13 12 financiers des exercices comptables 2018, 2019 et 2020 ZR-MINAGRI-105374-CS- QCBS / Recrutement d'un consultant firme pour la Support Services and Project Quality And Cost- Open - 2019-07- 2019-08- 2019-09- 2019-10- 2019-11- 2019-12- 2020-12- réalisation des études IDA / 58520 Prior 500,000.00 0.00 Canceled 2019-06-17 Management Based Selection International 08 21 18 18 22 27 26 d'orientation pour l'appui aux services fonciers dans l'aire d'intervention du PICAGL ZR-MINAGRI-78821-CS-QBS / Recrutement d'un Support Services and Project Quality Based Open - 2019-05- 2018-12- 2019-02- 2019-03- 2019-04- 2019-05- 2019-06- 2020-06- consultant firme pour la IDA / 58520 Prior 500,000.00 0.00 Canceled 2018-12-10 Management Selection International 28 31 13 13 12 12 16 15 réalisation de l' étude de référence du projet ZR-MINAGRI-140241-CS- CQS / Bureau d’Etude pour l'élaboration de la Notice d’Impact Environnemental et Consultant Support Services and Project 2019-11- 2020-01- 2020-01- 2020-03- 2021-03- Social de la construction de IDA / 58520 Post Qualification Open - National 70,000.00 0.00 Canceled 2019-10-28 Management 18 01 31 06 06 la microcentrale Selection hydroélectrique de MUTSUVA dans le territoire de KABARE, Province du SUD- KIVU. Page 8 ZR-MINAGRI-140242-CS- CQS / Bureau d’Etude pour la réalisation des études techniques des travaux de Consultant 2019-11- 2020-01- 2020-02- 2020-03- 2020-05- construction de la IDA / 58520 Regional integration Post Qualification Open - National 120,000.00 0.00 Canceled 2019-11-08 29 12 11 17 16 microcentrale Selection hydroélectrique de MUTSUVA dans le territoire de KABARE, Province du SUD- KIVU. ZR-MINAGRI-169986-CS- CQS / Recrutement d'un bureau d'études pour la réalisation des études Consultant techniques et Support Services and Project Under 2020-09- 2020-08- 2020-09- 2020-10- 2020-12- 2021-06- IDA / 58520 Post Qualification Open - National 50,000.00 0.00 2020-07-26 environnementales des Management Implementation 11 16 29 29 03 01 Selection travaux d'aménagement des bureaux DMPCC, ancien bureaux du Secrétaire Général et PARRSA ZR-MINAGRI-169823-CS- CQS / Recrutement d'un consultant (bureau d'étude) Consultant pour la rélisation des études Support Services and Project Pending 2020-08- 2020-10- 2020-11- 2020-12- 2021-06- IDA / 58520 Post Qualification Open - National 250,000.00 0.00 2020-07-29 faisabilités techniques et Management Implementation 19 02 01 06 04 Selection soci-environnementales de trois plates formes multiservices dans la Province du Sud-Kivu MOF-REF-45 / Recrutement d'une ONG spécialisée en Support Services and Project Quality And Cost- Open - 2018-12- 2019-01- 2019-02- 2019-03- 2019-04- 2019-05- 2020-05- IDA / 58520 Prior 500,000.00 0.00 Canceled 2018-11-15 gestion de conflits dans l'aire Management Based Selection International 06 19 16 18 22 27 26 d'intervention de PICAGL ZR-MINAGRI-105368-CS- CQS / Recrutement d'une Consultant ONG pour la mise en œuvre Support Services and Project Pending 2020-11- 2020-12- 2021-01- 2021-02- 2021-08- IDA / 58520 Post Qualification Open - National 350,000.00 0.00 2020-10-14 du Plan d'Actions en Faveur Management Implementation 04 18 17 21 20 Selection des Populations Autoctones de l'aire d'intervention du PICAGL ZR-MINAGRI-140242-CS- CQS-2 / Bureau d’Etude pour la réalisation des études d'impacts environnemental et Consultant social des travaux de Pending 2020-11- 2021-01- 2021-02- 2021-03- 2021-05- IDA / 58520 Regional integration Post Qualification Open - National 70,000.00 0.00 2020-10-31 construction de la Implementation 21 04 03 10 09 Selection microcentrale hydroélectrique de MUTSUVA dans le territoire de KABARE, Province du SUD-KIVU. INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-PARSSA-4340-CS-CDS / Consultant individuel devant actualiser le manuel des procédures administratives, Support Services and Project 2016-12- 2017-02- 2016-09- 2017-08- IDA / Q9260 Prior Direct Selection Direct 25,000.00 41,591.00 Signed 2016-12-08 financières, comptables et Management 18 21 05 20 passation des marchés de l'UNCP PARRSA en prenant compte l'exécution de PICAGL ZR-PARSSA-6313-CS-CDS / Recrutement consultant Support Services and Project 2015-12- 2016-02- 2015-12- 2016-08- élaboration des documents IDA / Q9260 Prior Direct Selection Direct 200,000.00 190,630.00 Signed 2015-12-10 Management 20 23 03 21 cadres de gestion environnementale ZR-PARSSA-6325-CS-CDS / Consultant individuel en Support Services and Project 2015-08- 2015-10- 2015-07- 2016-04- IDA / Q9260 Prior Direct Selection Direct 25,000.00 24,104.00 Signed 2015-07-25 charge de l' élaboration Management 04 08 03 05 termes de référence ZR-PARSSA-6314-CS-INDV / Recrutement de deux Individual Support Services and Project 2016-06- 2016-06- 2015-11- 2016-08- 2016-01- 2017-01- Consultants individuels en IDA / Q9260 Post Consultant Limited 32,000.00 36,000.00 Signed 2016-06-02 Management 07 28 27 02 18 29 appui aux comités Selection préparatoires ZR-PARSSA-6321-CS-CDS / Recrutement d'un Consultant Support Services and Project 2016-09- 2016-11- 2016-09- 2017-05- individuel pour la mise à jour IDA / Q9260 Prior Direct Selection Direct 25,000.00 41,591.00 Signed 2016-09-16 Management 26 30 15 29 du PARRSA pour tenir compte de PICAGL ZR-PARSSA-5149-CS-CDS / Recrutement du Consortium Agriculture Value Chain 2016-06- 2016-08- 2016-11- 2017-02- UCB-UEA- SENASEM pour la IDA / Q9260 Prior Direct Selection Direct 120,000.00 1,044,956.00 Signed 2016-06-13 Development 23 27 21 23 sélection participative des variétés de riz ZR-PARSSA-5150-CS-INDV / Recrutement de trois Individual Support Services and Project Pending 2016-11- 2016-12- 2017-01- 2017-07- chauffeurs en faveur des IDA / Q9260 Post Consultant Open 12,000.00 0.00 2016-09-30 Management Implementation 18 09 13 12 coordinations provinciales Selection PICAGL ZR-MINAGRI-78820-CS- CDS / Contractualusation Agriculture Value Chain 2018-11- 2019-02- 2019-01- 2019-08- avec RIKOLTO pour l'appui à IDA / 58520 Prior Direct Selection Direct 3,000,000.00 5,500,000.00 Under Review 2018-11-20 Development 30 03 14 02 la mise en œuvre de la chaine de valeur riz ZR-MINAGRI-78874-CS- CDS / Contractualusation avec IITA pour l'appui à la Agriculture Value Chain 2019-01- 2019-03- 2019-01- 2019-09- IDA / 58520 Prior Direct Selection Direct 10,950,000.00 10,209,591.00 Signed 2018-12-27 mise en œuvre de la chaine Development 06 12 10 08 de valeur manioc et création de l'emploi des jeunes ZR-MINAGRI-78980-CS- CDS / Contractualusation avec les instituts de CGIAR pour l'appui à la mise en 2019-01- 2019-03- 2019-03- 2019-09- IDA / 58520 Regional integration Prior Direct Selection Direct 7,780,000.00 8,834,538.00 Signed 2018-12-27 oeuvre de l’intégration 06 12 25 08 régionale des centres de recherche et aux services d’appui et gestion du projet ZR-MINAGRI-78983-CS- CDS / Contractualusation Agriculture Value Chain 2019-01- 2019-03- 2019-01- 2019-09- avec VSF pour l'appui à la IDA / 58520 Prior Direct Selection Direct 3,000,000.00 3,437,132.00 Under Review 2018-12-28 Development 07 13 29 09 mise en œuvre de la chaine de valeur élevage laitier ZR-MINAGRI-78877-CS- CDS / Assistance technique Agriculture Value Chain 2019-01- 2019-03- 2019-07- 2019-09- IDA / 58520 Prior Direct Selection Direct 2,000,000.00 2,000,000.00 Signed 2018-12-29 de la FAO pour la chaîne de Development 08 14 01 10 valeur peche et aquaculture ZR-MINAGRI-78658-CS- Individual INDV / Recrutement d'un Support Services and Project Under 2019-07- 2019-02- 2019-03- 2019-04- 2019-10- IDA / 58520 Post Consultant Open 120,000.00 0.00 2018-12-30 spécialiste national en Management Implementation 25 17 10 14 11 Selection nutrition ZR-MINAGRI-78876-CS- Individual INDV / Recrutement d'un Support Services and Project Under 2019-07- 2019-02- 2019-03- 2019-04- 2019-10- IDA / 58520 Post Consultant Open 120,000.00 0.00 2018-12-31 spécialiste en gestion des Management Implementation 25 18 11 15 12 Selection savoirs ZR-MINAGRI-79098-CS- CDS / Maitrise d'Ouvrage Délégué avec UNOPS pour le Agriculture Value Chain 2018-10- 2018-12- 2018-10- 2019-06- Développement IDA / 58520 Prior Direct Selection Direct 38,000,000.00 38,000,000.00 Signed 2018-10-02 Development 12 16 18 14 d'infrastructures proritaires en appui aux chaines de valeur sélectionnées  MOF-REF-21 / Recrutement Individual Support Services and Project 2018-09- 2018-10- 2018-11- 2019-05- d'un spécialiste en suivi et IDA / 58520 Prior Consultant Limited 240,000.00 0.00 Canceled 2018-09-23 Management 28 19 23 22 évaluation en faveur de Selection l'UNCP Individual MOF-REF-22 / Recrutement Support Services and Project 2018-11- 2018-12- 2019-01- 2019-07- IDA / 58520 Prior Consultant Open - National 240,000.00 0.00 Canceled 2018-09-23 d'un auditeur interne Management 11 02 06 05 Selection ZR-MINAGRI-78879-CS- Individual INDV / Recrutement d'un Support Services and Project Pending 2018-08- 2018-08- 2018-09- 2019-03- IDA / 58520 Prior Consultant Open 210,000.00 0.00 2018-06-14 Chargé de Passation des Management Implementation 02 23 27 26 Selection Marchés en faveur de l'UNCP ZR-MINAGRI-79003-CS- INDV / Recrutement de deux Individual Support Services and Project Pending 2016-09- 2016-10- 2016-11- 2017-05- coordonnateurs provinciaux IDA / 58520 Prior Consultant Open 500,000.00 0.00 2016-08-09 Management Implementation 27 18 22 21 pour les UPEP Sud Kivu et Selection Tanganyika ZR-MINAGRI-79009-CS- INDV / Recrutement Individual Support Services and Project Pending 2016-09- 2016-10- 2016-11- 2017-05- spécialistes provinciaux en IDA / 58520 Post Consultant Open 400,000.00 0.00 2016-08-09 Management Implementation 27 18 22 21 suivi et évaluation pour les Selection UPEP Sud Kivu et Tanganyika ZR-MINAGRI-79142-CS- INDV / Recrutement de deux Individual Support Services and Project Under 2019-07- 2018-11- 2018-11- 2019-01- 2019-07- experts en charge de IDA / 58520 Prior Consultant Open 400,000.00 0.00 2018-09-20 Management Implementation 25 08 29 03 02 l'agronomie et de la Selection recherche appliquée ZR-MINAGRI-78660-CS- Individual INDV / Recrutement de deux Support Services and Project Under 2019-07- 2018-11- 2018-11- 2019-01- 2019-07- IDA / 58520 Prior Consultant Open 400,000.00 0.00 2018-09-21 experts en travaux de génie Management Implementation 25 09 30 04 03 Selection civil Page 9 ZR-MINAGRI-78666-CS- Individual INDV / Recrutement de deux Support Services and Project 2018-12- 2018-12- 2019-02- 2019-08- IDA / 58520 Prior Consultant Open 400,000.00 0.00 Canceled 2018-10-22 spécialistes en Management 10 31 04 03 Selection développement du secteur privé ZR-MINAGRI-78965-CS- Individual INDV / Recrutement de deux Support Services and Project Pending 2016-09- 2016-10- 2016-11- 2017-05- IDA / 58520 Post Consultant Open 400,000.00 0.00 2016-08-09 spécialistes provinciaux en Management Implementation 27 18 22 21 Selection passation des marchés ZR-MINAGRI-78889-CS- Individual Support Services and Project Pending 2016-08- 2016-09- 2016-10- 2017-04- INDV / Recrutement de deux IDA / 58520 Post Consultant Limited 360,000.00 0.00 2016-08-09 Management Implementation 14 04 09 07 comptables provinciaux Selection ZR-MINAGRI-78812-CS- INDV / Recrutement de deux Individual Support Services and Project Pending 2016-09- 2016-10- 2016-11- 2017-05- spécialistes provinciaux en IDA / 58520 Post Consultant Open 360,000.00 0.00 2016-08-09 Management Implementation 27 18 22 21 sauvegarde Selection environnementale et sociale ZR-MINAGRI-78813-CS- Individual INDV / Recrutement d'un Support Services and Project Under 2019-07- 2018-11- 2018-12- 2019-01- 2019-07- IDA / 58520 Prior Consultant Open 210,000.00 0.00 2018-09-26 spécialiste national en Management Implementation 25 14 05 09 08 Selection sauvegarde environnementale ZR-MINAGRI-79116-CS- Individual INDV / Recrutement d'un Support Services and Project Pending 2018-11- 2018-12- 2019-01- 2019-07- IDA / 58520 Post Consultant Open 210,000.00 0.00 2018-09-27 spécialiste national en Management Implementation 15 06 10 09 Selection sauvegarde sociale ZR-MINAGRI-78891-CS- Individual INDV / Recrutement de deux Support Services and Project Pending 2018-11- 2018-12- 2019-01- 2019-07- IDA / 58520 Post Consultant Open 210,000.00 0.00 2018-09-28 assistants provinciaux en Management Implementation 16 07 11 10 Selection communication ZR-MINAGRI-79172-CS- Individual INDV / Recrutement d'un Support Services and Project Under 2019-07- 2018-11- 2018-11- 2019-01- 2019-07- IDA / 58520 Prior Consultant Open 210,000.00 0.00 2018-09-19 expert en gestion de Projet Management Implementation 25 07 28 02 01 Selection en faveur de l'UNCP ZR-MINAGRI-79012-CS- CDS / Recrutement d'un Support Services and Project Pending 2018-10- 2018-12- 2019-06- IDA / 58520 Post Direct Selection Direct 60,000.00 0.00 2018-10-02 consultant individuel pour la Management Implementation 12 16 14 mise en place du tableau de bord ZR-MINAGRI-79018-CS- INDV / Recrutement d'un consultant individuel pour Individual Agriculture Value Chain Under 2019-07- 2018-12- 2018-12- 2019-02- 2019-08- l'élaboration du plan d'action IDA / 58520 Post Consultant Limited 40,000.00 0.00 2018-12-05 Development Implementation 13 10 31 04 03 en faveur des populations Selection autochtones dans l'aire d'intervention du PICAGL ZR-MINAGRI-79166-CS- CDS / Protocole d'accord Support for the development avec ANAPI pour Pending 2019-01- 2019-03- 2019-09- IDA / 58520 of the private agro- Post Direct Selection Direct 100,000.00 0.00 2018-12-26 l'amélioration du climat d' Implementation 05 11 07 industrial sector affaires dans l'aire d'intervention du PICAGL au Sud Kivu et Tanganyika ZR-MINAGRI-78814-CS- CDS / Protocole d'accord Agriculture Value Chain Pending 2018-10- 2018-12- 2019-06- avec SENASEM pour IDA / 58520 Post Direct Selection Direct 350,000.00 0.00 2018-09-28 Development Implementation 08 12 10 l'inspection, contrôle et certification des semences dans l'aire du Projet ZR-MINAGRI-79117-CS- Individual INDV / Recrutement d'un Support Services and Project 2018-10- 2018-12- 2018-11- 2019-01- 2018-11- 2019-02- 2018-12- 2019-08- IDA / 58520 Post Consultant Open 12,000.00 12,000.00 Signed 2018-10-31 Caissier pour l'UPEP PICAGL Management 11 19 20 09 28 13 07 12 Selection Sud-Kivu ZR-MINAGRI-78908-CS- Individual INDV / Recrutement d'un Support Services and Project Pending 2018-12- 2019-01- 2019-02- 2019-08- IDA / 58520 Post Consultant Open 12,000.00 0.00 2018-10-31 Assistant en communition Management Implementation 19 09 13 12 Selection pour l'UPEP PICAGL Sud-Kivu ZR-MINAGRI-79120-CS- Individual INDV / Recrutement d'un Support Services and Project 2018-12- 2019-01- 2018-11- 2019-02- 2018-12- 2019-08- IDA / 58520 Post Consultant Open 12,000.00 12,000.00 Signed 2018-10-31 Secrétaire l'UPEP PICAGL Sud- Management 19 09 30 13 07 12 Selection Kivu ZR-MINAGRI-78991-CS- Individual INDV / Recrutement d'un Support Services and Project 2018-10- 2018-12- 2019-01- 2018-11- 2019-02- 2018-12- 2019-08- IDA / 58520 Post Consultant Open 12,000.00 12,000.00 Signed 2018-10-31 Assistant de logistique pour Management 11 19 09 28 13 07 12 Selection l'UPEP PICAGL Sud-Kivu ZR-MINAGRI-78910-CS- Individual INDV / Recrutement d'un Support Services and Project Under 2019-02- 2018-12- 2019-01- 2019-02- 2019-08- IDA / 58520 Post Consultant Open 9,000.00 0.00 2018-10-31 Chauffeur complémentaire Management Implementation 07 19 09 13 12 Selection pour l'UPEP PICAGL Sud-Kivu ZR-MINAGRI-79132-CS- Individual INDV / Recrutement d'un Support Services and Project 2018-12- 2019-01- 2019-01- 2019-02- 2019-01- 2019-08- IDA / 58520 Post Consultant Open 12,000.00 12,000.00 Signed 2018-10-31 caissier pour l'UPEP PICAGL Management 19 09 07 13 07 12 Selection Tanganyika ZR-MINAGRI-78976-CS- INDV / Recrutement d'un Individual Support Services and Project Pending 2018-11- 2018-11- 2018-12- 2019-06- assistant en communition IDA / 58520 Post Consultant Limited 12,000.00 0.00 2018-10-31 Management Implementation 05 26 31 29 pour l'UPEP PICAGL Selection Tanganyika ZR-MINAGRI-78995-CS- Individual INDV / Recrutement d'un Support Services and Project 2018-10- 2018-11- 2018-12- 2018-11- 2019-01- 2018-12- 2019-01- 2019-06- IDA / 58520 Post Consultant Limited 12,000.00 12,000.00 Signed 2018-10-31 secrétaire l'UPEP PICAGL Management 11 05 26 26 07 31 07 29 Selection Tanganyika ZR-MINAGRI-79136-CS- Individual INDV / Recrutement d'un Support Services and Project 2018-12- 2019-01- 2018-12- 2019-02- 2019-01- 2019-08- IDA / 58520 Post Consultant Open 12,000.00 12,000.00 Signed 2018-10-31 assistant de logistique pour Management 19 09 28 13 07 12 Selection l'UPEP PICAGL Tanganika ZR-MINAGRI-78882-CS- INDV / Recrutement d'un Individual Support Services and Project Under 2019-02- 2018-12- 2019-01- 2019-02- 2019-08- chauffeur complémentaire IDA / 58520 Post Consultant Open 9,000.00 0.00 2018-10-31 Management Implementation 07 19 09 13 12 pour l'UPEP PICAGL Selection Tanganyika ZR-MINAGRI-79000-CS- INDV / Recrutement d'un Délégué à pied d'œuvre pour Individual Support Services and Project 2019-03- 2019-01- 2019-05- 2019-01- 2019-06- 2019-02- 2019-06- 2019-08- le contrôle et surveillance IDA / 58520 Post Consultant Open 10,000.00 6,000.00 Signed 2018-11-15 Management 15 03 16 24 06 28 06 27 des travaux de réhabilitation Selection du bureau du Ministre Provincial de l'Agriculture du Tanganyika ZR-MINAGRI-79096-CS- Individual Support Services and Project Pending 2018-08- 2018-08- 2018-09- 2019-03- INDV / Recrutement d'un IDA / 58520 Post Consultant Open 180,000.00 0.00 2018-06-14 Management Implementation 02 23 27 26 comptable national Selection ZR-MINAGRI-78986-CS- CDS / Contractualisation avec STUDI INTERNATIONAL Agriculture Value Chain Under 2019-10- 2018-10- 2018-12- 2019-06- pour la mise à jour des IDA / 58520 Post Direct Selection Direct 120,000.00 0.00 2018-09-30 Development Implementation 18 10 14 12 documents de sauvegarde environnementale et social du PICAGL ZR-MINAGRI-79173-CS- CDS / Contractualisation avec le consortium UCB, Agriculture Value Chain Pending 2018-10- 2018-12- 2019-06- UEA, INERA et SENASEM pour IDA / 58520 Post Direct Selection Direct 170,000.00 0.00 2018-09-23 Development Implementation 03 07 05 la sélection participative des variétés de riz dans la province de Tanganyika ZR-MINAGRI-79014-CS- CDS / Contractualisation Support Services and Project 2018-10- 2018-12- 2019-01- 2019-06- avec SAPHIR IDA / 58520 Post Direct Selection Direct 120,000.00 96,786.00 Signed 2018-10-04 Management 14 18 15 16 DEVELOPPEMENT pour le recrutement du personnel complémentaire de PICAGL ZR-MINAGRI-78988-CS- CDS / Protocole d'accord avec l'INERA pour la Agriculture Value Chain Pending 2018-10- 2018-12- 2019-06- IDA / 58520 Post Direct Selection Direct 350,000.00 0.00 2018-09-27 production des semences Development Implementation 07 11 09 des variétés améliorées dans l'aire du Projet ZR-MINAGRI-105382-CS- CDS / Recrutement de deux délégués à pied d'œuvre pour la surveillance des Support Services and Project 2019-07- 2019-05- 2019-09- 2019-07- 2019-11- 2020-01- IDA / 58520 Post Direct Selection Direct 50,000.00 49,695.00 Signed 2019-05-03 travaux de réhabilitation des Management 08 13 10 17 15 13 bâtiments des inspections provinciales de l'Agriculture du Sud Kivu et Tanganyika ZR-MINAGRI-105304-CS- CDS / Contractualisation avec SAPHIR Support Services and Project 2019-07- 2018-10- 2019-09- 2018-12- 2020-01- 2019-02- IDA / 58520 Post Direct Selection Direct 80,000.00 9,456,960.00 Signed 2018-10-04 DEVELOPPEMENT pour le Management 21 14 13 18 31 01 développement des compétences des ressources humaines du Projet PICAGL ZR-MINAGRI-105356-CS- Individual INDV / Recrutement d'un Support Services and Project Under 2019-07- 2019-03- 2019-04- 2019-05- 2020-05- IDA / 58520 Post Consultant Open 40,000.00 0.00 2019-01-21 logisticien pour l'UNCP Management Implementation 25 11 01 06 05 Selection PICAGL ZR-MINAGRI-105386-CS- INDV / Recrutement d'un Individual Consultant individuel pour Support Services and Project Pending 2019-06- 2019-07- 2019-08- 2020-02- IDA / 58520 Post Consultant Open 35,000.00 0.00 2019-05-06 l'élaboration du guide Management Implementation 24 15 19 15 Selection environnemental du volet végétal de PICAGL Page 10 ZR-MINAGRI-105396-CS- INDV / Recrutement d'un Individual Support Services and Project Pending 2019-04- 2019-05- 2019-06- 2019-12- Consultant individuel pour la IDA / 58520 Post Consultant Limited 35,000.00 0.00 2019-04-06 Management Implementation 11 02 06 03 sensibilisation aux enjeux Selection environnementaux MOF-REF-120 / Individual Recrutement d'un chauffeur Support Services and Project Pending 2019-03- 2019-03- 2019-04- 2020-04- IDA / 58520 Post Consultant Limited 9,000.00 0.00 2019-02-25 complémentaire pour l'UPEP Management Implementation 02 23 27 26 Selection PICAGL Sud-Kivu ZR-MINAGRI-105399-CS- INDV / Recrutement d"un consultant chargé des Individual études techniques et Support Services and Project Under 2019-10- 2019-07- 2019-07- 2019-09- 2020-02- IDA / 58520 Post Consultant Open 25,000.00 0.00 2019-05-20 surveillance des travaux de Management Implementation 08 08 29 02 29 Selection réhabilitation du Ministère et le bâtiments devant abriter provisoirement l’IPAPEL Sud Kivu ZR-MINAGRI-117752-CS- INDV / Recrutement d'un Individual Agriculture Value Chain Under 2019-07- 2019-09- 2019-09- 2019-10- 2021-12- Spécialiste en Agribusiness IDA / 58520 Post Consultant Open 96,000.00 0.00 2019-07-15 Development Implementation 08 02 23 28 31 et développement de chaînes Selection de valeur ZR-MINAGRI-117753-CS- Individual INDV / Recrutement d'un Agriculture Value Chain Under 2019-07- 2019-09- 2019-10- 2019-11- 2021-12- IDA / 58520 Post Consultant Open 96,000.00 0.00 2019-07-24 Spécialiste en Finance Rurale Development Implementation 08 11 02 06 31 Selection pour le secteur agricole ZR-MINAGRI-105103-CS- INDV / Recrutement d'un consultant individuel pour Individual Support Services and Project 2019-06- 2019-06- 2019-07- 2020-01- l'élaboration du plan d'action IDA / 58520 Post Consultant Open 40,000.00 0.00 Canceled 2019-04-17 Management 05 26 31 27 en faveur des populations Selection autochtones dans l'aire d'intervention du PICAGL ZR-MINAGRI-78904-CS- INDV / Recrutement d'un Individual Support Services and Project 2018-11- 2018-12- 2019-01- 2019-07- consultant individuel pour IDA / 58520 Post Consultant Open 40,000.00 0.00 Canceled 2018-10-06 Management 24 15 19 18 l'élaboration du manuel Selection d'accès au crédit ZR-MINAGRI-122621-CS- CDS / Recrutement de Support for the development Under 2019-07- 2019-08- 2019-10- 2020-04- Monsieur Ibrahim Dione IDA / 58520 of the private agro- Post Direct Selection Direct 40,000.00 0.00 2019-07-31 Implementation 25 10 14 11 pour l'élaboration du manuel industrial sector d'accès au crédit ZR-MINAGRI-122617-CS- CDS / Recrutement de l'IFPRI Agriculture Value Chain 2019-08- 2019-08- 2019-11- 2019-10- 2020-12- 2020-04- IDA / 58520 Prior Direct Selection Direct 500,000.00 452,114.90 Signed 2019-07-31 pour la réalisation de l' étude Development 28 10 05 14 15 11 de référence du PICAGL ZR-MINAGRI-140233-CS- CDS / Etude de faisabilité d'un plan d'opération de d'un Support for the development plan d'aménagement d'un Under 2019-11- 2019-11- 2020-03- 2020-01- 2020-07- IDA / 58520 of the private agro- Prior Direct Selection Direct 1,200,000.00 0.00 2019-10-30 parc agroindustriel dans la Implementation 30 09 20 13 11 industrial sector plaine de Rugumba dans le territoire de Kaliémie dans la Province de Tanganyika avec ONUDI ZR-MINAGRI-140238-CS- CDS / Réalisation de la Agriculture Value Chain Under 2019-12- 2019-11- 2020-01- 2020-07- cartographie des sols sur le IDA / 58520 Post Direct Selection Direct 120,000.00 0.00 2019-10-30 Development Implementation 15 09 13 11 corridor Bukavu -Kalemie avec IITA ZR-MINAGRI-148116-CS- CDS / Réalisation des études techniques, d'impacts environnemental et social Agriculture Value Chain Under 2019-12- 2019-12- 2020-03- 2020-08- des travaux de construction IDA / 58520 Post Direct Selection Direct 150,000.00 0.00 2019-12-20 Development Implementation 14 30 04 31 de la microcentrale hydroélectrique de MUTSUVA dans le territoire de KABARE, Province du SUD-KIVU avec STUCKY SA ZR-MINAGRI-148122-CS- INDV / Recrutement d'un Individual Responsable Provincial de Support Services and Project 2019-12- 2020-01- 2020-08- 2020-02- 2020-08- 2020-03- 2020-10- 2020-09- IDA / 58520 Post Consultant Limited 90,000.00 42,000.00 Signed 2020-01-15 Suivi et Évaluation pour Management 14 20 26 10 28 16 28 12 Selection l'Unité Provinciale d'Exécution de Tanganyika ZR-MINAGRI-148125-CS- INDV / Recrutement d'un Individual chargé de Passation des Support Services and Project Under 2019-12- 2020-01- 2020-02- 2020-03- 2020-09- IDA / 58520 Post Consultant Limited 90,000.00 0.00 2020-01-15 Marchés pour l'Unité Management Implementation 14 20 10 16 12 Selection Provinciale d'Exécution du Projet Sud Kivu ZR-MINAGRI-157206-CS- CDS / Recrutement de M. ISSA DRAME pour le renforcement des capacités des acteurs impliqués dans Support Services and Project Under 2020-02- 2020-03- 2020-05- 2020-11- la mise en œuvre du projet IDA / 58520 Post Direct Selection Direct 35,000.00 0.00 2020-02-20 Management Implementation 07 01 05 01 en suivi-évaluation et rapportage et l’appui à l’élaboration du rapport de la mission conjointe de supervision du PICAGL ZR-MINAGRI-170568-CS- INDV / Recrutement d'un consultant individuel pour la Individual réalisation des études Support Services and Project Pending 2020-08- 2020-09- 2020-10- 2021-04- IDA / 58520 Post Consultant Limited 8,000.00 0.00 2020-08-15 techniques des travaux de Management Implementation 20 10 15 13 Selection construction du laboratoire du SENASEM et INERA Tanganyika ZR-MINAGRI-169817-CS- INDV / Recrutement d'un Délégué à Pied d'Oeuvre pour Individual le contrôle et la surveillance Support Services and Project Pending 2020-08- 2020-09- 2020-10- 2021-04- IDA / 58520 Post Consultant Limited 12,000.00 0.00 2020-08-15 des travaux de construction Management Implementation 20 10 15 13 Selection de deux (2) laboratoires du SENASEM et de l'INERA Tanganyika ZR-MINAGRI-169895-CS- INDV / Recrutement consultant pour la traduction Individual Support Services and Project Pending 2020-08- 2020-09- 2020-10- 2021-04- du guide de bonnes IDA / 58520 Post Consultant Limited 3,000.00 0.00 2020-08-10 Management Implementation 15 05 10 08 pratiques environnementales Selection et sociales du PICAGL en swahili en faveur de l'UPEP Tanganyika ZR-MINAGRI-169847-CS- INDV / Recrutement Individual Support Services and Project Pending 2020-07- 2020-07- 2020-07- 2020-07- consultant pour infographie IDA / 58520 Post Consultant 8,000.00 0.00 2020-07-10 Management Implementation 10 10 10 10 du Guide Selection environnemental/Tanganyika ZR-MINAGRI-169821-CS- INDV / Recrutement d'un délégué à pied d'œuvre (DPO) pour le contrôle et Individual surveillance des travaux de Support Services and Project Pending 2020-05- 2020-06- 2020-07- 2021-01- IDA / 58520 Post Consultant Limited 8,000.00 0.00 2020-05-20 réhabiitation du bâtiment Management Implementation 25 15 20 16 Selection complémentaire de l'Inspection Provinciale de l'Agriculture, Pêche et Elevage de la province du Sud Kivu ZR-MINAGRI-185889-CS- CDS / Recrutement du bureau d'études INTAIRPLAN Support Services and Project Under 2020-10- 2020-08- 2020-11- 2020-12- Gmb H pour la revue des IDA / 58520 Post Direct Selection Direct 60,000.00 0.00 2020-08-20 Management Implementation 13 30 03 18 études techniques de travaux de réhabilitation de routes de desserte agricole ZR-MINAGRI-188541-CS- INDV / Recrutement d'un Délégué à Pied d'Œuvre (DPO) pour la surveillance et le contrôle des travaux de Individual Agriculture Value Chain Under 2020-09- 2020-11- 2020-12- 2021-01- 2021-07- construction de 6 dépôts de IDA / 58520 Post Consultant Open 12,000.00 0.00 2020-10-01 Development Implementation 30 19 10 14 13 stockage dont deux (02) à Selection Rugumba, deux (02) à Lwaminwa et deux (02) à Katibili dans la Province de Tanganyika ZR-MINAGRI-188506-CS- INDV / Recrutement d'un Délégué à Pied d'Oeuvre pour la surveillance et le contrôle Individual Agriculture Value Chain Under 2020-09- 2020-11- 2020-12- 2021-01- 2021-07- des travaux de construction IDA / 58520 Post Consultant Open 12,000.00 0.00 2020-10-02 Development Implementation 29 20 11 15 14 de 10 Bâtiments devant Selection abriter les unités de transformation de manioc dans la Province de Tanganyika ZR-MINAGRI-188518-CS- INDV / Recrutement d'un Délégué à Pied d'Oeuvre pour la surveillance et le contrôle des travaux de construction Individual Agriculture Value Chain 2021-01- 2020-11- 2020-12- 2021-01- 2021-07- de 6 Bâtiments devant abriter IDA / 58520 Post Consultant Open 12,000.00 0.00 Under Review 2020-10-03 Development 28 21 12 16 15 les équipements de Selection transformation de Riz dans les six Bassins de production dans la Province de Tanganyika Page 11 ZR-MINAGRI-188546-CS- INDV / Recrutement d'un Délégué à Pied d'Oeuvre pour la surveillance et le contrôle Individual Agriculture Value Chain Pending 2020-11- 2020-12- 2021-01- 2021-07- des travaux de construction IDA / 58520 Post Consultant Open 12,000.00 0.00 2020-10-04 Development Implementation 22 13 17 16 de 10 bâtiments devant Selection abriter les unités de transformation de maïs dans la Province de Tanganyika ZR-MINAGRI-188527-CS- INDV / Recrutement d'un Délégué à Pied d'Ouevre pour le contrôle et la surveillance Individual Agriculture Value Chain Pending 2020-12- 2021-01- 2021-02- 2021-08- travaux de construction de 2 IDA / 58520 Post Consultant Open 12,000.00 0.00 2020-10-25 Development Implementation 13 03 07 06 dépôts vétérinaires et 2 Selection cliniques vétérinaires dans les bassins de la Rugumba et Lwamina, territoire de Kalemie ZR-MINAGRI-188525-CS- INDV / Recrutement d'un Délégué à Pied d'Ouevre (DPO) pour le contrôle et la Individual Agriculture Value Chain Under 2020-09- 2020-12- 2021-01- 2021-02- 2021-08- surveillance des travaux de IDA / 58520 Post Consultant Open 12,000.00 0.00 2020-10-26 Development Implementation 30 14 04 08 07 construction de huit (08) Selection mini laiteries dans les six bassins de production, territoire de Kalemie ZR-MINAGRI-188484-CS- INDV / Recrutement d'un Délégué à Pied d'Oeuvre (DPO) pour le contrôle et la surveillance des travaux de Individual Agriculture Value Chain Under 2020-09- 2020-12- 2021-01- 2021-02- 2021-08- construction de deux (02) IDA / 58520 Post Consultant Open 6,000.00 0.00 2020-10-27 Development Implementation 30 15 05 09 08 cliniques vétérinaires dans Selection les bassins de production de la Rugumba et Lwamina, territoire de Kalemie/Tanganyika ZR-MINAGRI-188538-CS- INDV / Recrutement d'un Délégué à Pied d'Œuvre Individual (DPO) pour le contrôle et la Agriculture Value Chain Pending 2020-12- 2021-01- 2021-02- 2021-08- IDA / 58520 Post Consultant Open 6,000.00 0.00 2020-10-28 surveillance des travaux de Development Implementation 16 06 10 09 Selection construction de deux (02) dépôts vétérinaires dans la ville de Kalemie/Tanganyika ZR-MINAGRI-188524-CS- INDV / Recrutement Individual consultant pour la traduction Support Services and Project Pending 2020-08- 2020-09- 2020-10- 2021-04- IDA / 58520 Post Consultant Limited 3,000.00 0.00 2020-08-21 du guide de bonnes Management Implementation 26 16 21 19 Selection pratiques environnementales et sociales du PICAGL en swahili/Sud Kivu ZR-MINAGRI-188869-CS- CDS / Contractualisation avec Monsieur Freddy KAPIAMBA WA KAPIAMBA pour le contrôle des travaux Support Services and Project Under 2020-12- 2020-09- 2020-11- 2021-05- complémentaires de IDA / 58520 Post Direct Selection Direct 14,000.00 0.00 2020-09-15 Management Implementation 11 25 29 28 Réhabilitation du bâtiment devant servir des bureaux des Inspections Provinciales de l’Agriculture et du Développement Rural de Tanganyika ZR-MINAGRI-188911-CS- CDS / Contractualisation avec Monsieur Mabel LUBEMBE NZUNGA pour le contrôle et la surveillance Support Services and Project Pending 2020-09- 2020-12- 2021-05- des Travaux IDA / 58520 Post Direct Selection Direct 14,000.00 0.00 2020-09-17 Management Implementation 27 01 30 complémentaires de réhabilitation du bâtiment des bureaux des Inspections Provinciales de l’Agriculture, Pêche, Elevage et Développent Rural du Sud Kivu ZR-MINAGRI-188912-CS- CDS / Contractualisation avec Monsieur MASEMBE WASIKATENDA Samy pour le contrôle et la surveillance Support Services and Project Pending 2020-09- 2020-12- 2021-05- des travaux de réhabilitation IDA / 58520 Post Direct Selection Direct 14,000.00 0.00 2020-09-17 Management Implementation 27 01 30 des bureaux du Ministère Provincial de l’Agriculture, Pêche, Elevage et Développement Rural du Sud- Kivu ZR-MINAGRI-189089-CS- CDS / Contractualisation Support Services and Project Under 2020-11- 2020-09- 2020-11- 2021-05- avec Monsieur IBRAHIMA IDA / 58520 Post Direct Selection Direct 16,000.00 0.00 2020-09-15 Management Implementation 08 25 29 28 DIONE pour la mise à jour du tableau de bord du Projet PICAGL ZR-MINAGRI-188459-CS- CDS / Contractualisation avec la firme Zuid Oost Azië Support Services and Project 2020-11- 2021-01- 2021-07- IDA / 58520 Prior Direct Selection Direct 500,000.00 0.00 Under Review 2020-10-29 (ZOA) pour la gestion des Management 08 12 11 conflits et questions foncières dans la zone d'intervention du PICAGL ZR-MINAGRI-196112-CS- INDV / Recrutement d'un Délégué à Pied d'Œuvre pour Individual Agriculture Value Chain 2020-10- 2020-12- 2020-12- 2021-01- 2021-07- la surveillance et le contrôle IDA / 58520 Post Consultant Open 12,000.00 0.00 Under Review 2020-10-15 Development 28 03 24 28 27 des travaux de construction Selection du Laboratoire du SENASEM du Tanganyika ZR-MINAGRI-196113-CS- INDV / Recrutement d'un Délégué à Pied d'Œuvre pour Individual Agriculture Value Chain 2020-10- 2020-12- 2020-12- 2021-01- 2021-07- la surveillance et le contrôle IDA / 58520 Post Consultant Open 12,000.00 0.00 Under Review 2020-10-15 Development 28 03 24 28 27 des travaux de construction Selection du Laboratoire de l'INERA du Tanganyika ZR-MINAGRI-199487-CS- CDS / Mission d' appui à l’UNCP dans la mise en œuvre des activités du Support Services and Project 2020-10- 2020-10- 2020-10- 2020-12- 2020-10- 2021-06- PICAGL(Appui à l'élaboration IDA / 58520 Post Direct Selection Direct 75,000.00 74,450.00 Signed 2020-10-16 Management 19 26 20 30 21 28 du rapport à mi-parcours et d'activités) et l' élaboration du rapport d’achèvement du PARRSA -FA avec Monsieur ISSA DRAME ZR-MINAGRI-203023-CS- INDV / Recrutement d'un Individual Support Services and Project Under 2021-01- 2020-12- 2020-12- 2021-01- 2021-07- Responsable Provincial en IDA / 58520 Post Consultant Limited 42,000.00 0.00 2020-11-30 Management Implementation 09 05 26 30 29 sauvegarde Selection environnementale et sociale de l'UPEP Sud Kivu ZR-MINAGRI-203024-CS- INDV / Recrutement d'un Délégué à pied d'oeuvre pour Individual la surveillance et contrôle Agriculture Value Chain Pending 2020-12- 2021-01- 2021-02- 2021-08- IDA / 58520 Post Consultant Limited 12,000.00 0.00 2020-12-09 des travaux de réhabilitation Development Implementation 14 04 08 07 Selection des travaux du bâtiment du Secrétariat Général de Pêche et Elevage à Kinshasa ZR-MINAGRI-209981-CS- CDS / Contractualisation avec Monsieur MASEMBE WASIKATENDA Samy, Délégué à Pied d’Œuvre pour Support Services and Project Pending 2020-12- 2021-03- 2021-09- le contrôle et la surveillance IDA / 58520 Post Direct Selection Direct 6,000.00 0.00 2020-12-20 Management Implementation 30 05 01 des travaux de la clôture et aménagement extérieur des Bureaux du Ministère Provincial de l’Agriculture, Elevage, Pêche du Sud-Kivu ZR-MINAGRI-210123-CS- INDV / Recrutement d'un Délégué à Pied d'Œuvre pour la surveillance et le contrôle des Travaux de construction Individual Agriculture Value Chain 2021-06- 2021-03- 2021-03- 2021-04- 2021-10- de quatre (04) boutiques IDA / 58520 Post Consultant Open 12,000.00 0.00 Under Review 2021-01-15 Development 16 05 26 30 27 d'intrants agricoles dans les Selection Bassins de production de Rugumba, Lwaminwa, Kabimba et Kalemie dans la Province de Tanganyika ZR-MINAGRI-210124-CS- INDV / Recrutement d'un Délégué à Pied d'Œuvre (DPO) pour la surveillance et Individual le contrôle des Travaux de Agriculture Value Chain Pending 2021-03- 2021-04- 2021-05- 2021-11- IDA / 58520 Post Consultant Open 8,000.00 0.00 2021-01-22 construction de deux (02) Development Implementation 12 02 07 03 Selection provenderies dans les Bassins de production de Rugumba et Lwaminwa dans la Province de Tanganyika ZR-MINAGRI-210137-CS- INDV / Recrutement d'un (1) délégué à pied d'oeuvre pour la mission de controle et Individual surveillance des Travaux de Agriculture Value Chain 2021-05- 2021-02- 2021-02- 2021-03- 2021-09- IDA / 58520 Post Consultant Limited 8,000.00 0.00 Under Review 2021-01-27 construction de quatre (4) Development 26 01 22 29 25 Selection Centres de Collecte et Transformation de Manioc à Bitale, Bulmbika et Mulonge, dans le territoire de Kalehe Page 12 ZR-MINAGRI-210139-CS- INDV / Recrutement d'un (1) délégué à pied d'oeuvre pour la mission de controle et surveillance des Travaux de Individual Agriculture Value Chain 2021-05- 2021-02- 2021-02- 2021-03- 2021-09- construction de quatre (4) IDA / 58520 Post Consultant Limited 8,000.00 0.00 Under Review 2021-01-27 Development 26 01 22 29 25 Centres de Collecte et Selection Transformation de Manioc à Mubuku, Karasi, Kitchanga et Maibano, dans le territoire de Kalehe ZR-MINAGRI-210134-CS- INDV / Recrutement d'un (1) délégué à pied d'oeuvre pour la mission de controle et Individual surveillance des Travaux de Agriculture Value Chain 2021-05- 2021-02- 2021-02- 2021-03- 2021-09- IDA / 58520 Post Consultant Limited 8,000.00 0.00 Under Review 2021-01-27 construction de deux (2) Development 26 01 22 29 25 Selection Centres de Collecte et Transformation de Manioc à Katanga et Malinde, dans le territoire de Fizi ZR-MINAGRI-210133-CS- INDV / Recrutement d'un (1) délégué à pied d'oeuvre pour la mission de controle et Individual surveillance des Travaux de Agriculture Value Chain 2021-05- 2021-02- 2021-02- 2021-03- 2021-09- IDA / 58520 Post Consultant Limited 8,000.00 0.00 Under Review 2021-01-27 construction de cinq (5) Development 26 01 22 29 25 Selection Centres de Collecte et Transformation de Manioc à Katana, Kavumu et Luhihi, dans le territoire de Kabare ZR-MINAGRI-210135-CS- INDV / Recrutement d'un (1) délégué à pied d'oeuvre pour la mission de controle et Individual surveillance des Travaux de Agriculture Value Chain 2021-05- 2021-02- 2021-02- 2021-03- 2021-09- IDA / 58520 Post Consultant Limited 8,000.00 0.00 Under Review 2021-01-27 construction de trois (3) Development 26 01 22 29 25 Selection Centres de Collecte et Transformation de Manioc à Sange, Kiliba et Runingu, dans le territoire d’Uvira ZR-MINAGRI-210138-CS- INDV / Recrutement d'un (1) délégué à pied d'oeuvre pour la mission de controle et surveillance des Travaux de Individual Agriculture Value Chain 2021-05- 2021-02- 2021-02- 2021-03- 2021-09- construction de quatre (4) IDA / 58520 Post Consultant Limited 6,000.00 0.00 Under Review 2021-01-27 Development 26 01 22 29 25 Centres de Collecte et Selection Transformation de Manioc à Kamanyola, Luvungi et Lubarika, dans la plaine de Ruzizi ZR-MINAGRI-210214-CS- INDV / Recrutement d'un délégué à pied d'oeuvre pour la surveillance des Travaux de construction de 2 mini Individual Support Services and Project Pending 2021-01- 2021-02- 2021-03- 2021-09- laboratoires de SENASEM à IDA / 58520 Post Consultant Limited 8,000.00 0.00 2021-01-25 Management Implementation 30 20 27 23 Bwegera et Fizi, d’1 mur de Selection clôture et aménagement paillasses salle de labo physique et phytopathologie au SENASEM Bukavu ZR-MINAGRI-210331-CS- INDV / Recrutement d'un délégué à pied d'oeuvre pour la mission de contrôle et surveillance des Travaux de Individual Agriculture Value Chain Pending 2021-02- 2021-03- 2021-04- 2021-10- construction des aires de IDA / 58520 Post Consultant Limited 8,000.00 0.00 2021-02-03 Development Implementation 08 01 05 02 sechage semi ouverts dans le Selection groupement de Bushumba (territoire de Kabare) et le groupement d'Itara (territoire d'Uvira) ZR-MINAGRI-210333-CS- INDV / Recrutement d'un délégué à pied d'oeuvre pour la mission de contrôle et Individual Agriculture Value Chain Pending 2021-02- 2021-03- 2021-04- 2021-10- surveillance des Travaux de IDA / 58520 Post Consultant Limited 8,000.00 0.00 2021-02-03 Development Implementation 08 01 05 02 construction des aires de Selection sechage non couverts à Sebele dans le territoire de Fizi et à Uvira ZR-MINAGRI-210661-CS- INDV / Recrutement d'un délégué à pied d'oeuvre pour la surveillance des Travaux Individual Agriculture Value Chain 2021-05- 2021-02- 2021-02- 2021-03- 2021-09- de construction de 7 abris IDA / 58520 Post Consultant Limited 8,000.00 0.00 Under Review 2021-01-29 Development 26 03 24 31 27 dont 6 pour mini-minoterie Selection et 1 pour mini-laiterie de type 2, et d'une provenderie, dans le territoire de Kabare ZR-MINAGRI-210658-CS- INDV / Recrutement d'un délégué à pied d'oeuvre pour la surveillance des Travaux Individual de construction de 16 abris Agriculture Value Chain 2021-05- 2021-02- 2021-02- 2021-03- 2021-09- IDA / 58520 Post Consultant Limited 8,000.00 0.00 Under Review 2021-01-29 dont 12 pour mini- Development 26 03 24 31 27 Selection minoterie, 3 pour rizerie type 2 et 1 pour mini- laiterie de type 2, et d'une provenderie, dans la plaine de Ruzizi ZR-MINAGRI-210662-CS- INDV / Recrutement d'un délégué à pied d'oeuvre pour Individual la surveillance des Travaux Agriculture Value Chain 2021-05- 2021-02- 2021-02- 2021-03- 2021-09- IDA / 58520 Post Consultant Limited 8,000.00 0.00 Under Review 2021-01-29 de construction de 4 abris Development 26 03 24 31 27 Selection dont 1 pour mini-minoterie et 3 pour mini-laiterie de type 2, dans le territoire de Kalehe ZR-MINAGRI-210659-CS- INDV / Recrutement d'un délégué à pied d'oeuvre pour la surveillance des Travaux Individual de construction de 10 abris Agriculture Value Chain 2021-05- 2021-02- 2021-02- 2021-03- 2021-09- IDA / 58520 Post Consultant Limited 8,000.00 0.00 Under Review 2021-01-29 dont 8 pour mini-minoterie, Development 26 03 24 31 27 Selection 1 pour rizerie de type 2 (SB- 50 ou équivalent) et 1 pour mini-laiterie de type 2, dans le territoire de Fizi ZR-MINAGRI-210660-CS- INDV / Recrutement d'un délégué à pied d'oeuvre pour Individual le contrôle et la surveillance Agriculture Value Chain 2021-05- 2021-02- 2021-02- 2021-03- 2021-09- IDA / 58520 Post Consultant Limited 8,000.00 0.00 Under Review 2021-01-29 des Travaux de construction Development 26 03 24 31 27 Selection de 2 abris pour mini-laiterie de type 2 et d'une provenderie, à Bukavu ZR-MINAGRI-210657-CS- INDV / Recrutement d'un délégué à pied d'oeuvre pour la surveillance des Travaux Individual de construction de 14 abris Agriculture Value Chain 2021-05- 2021-02- 2021-02- 2021-03- 2021-09- IDA / 58520 Post Consultant Limited 8,000.00 0.00 Under Review 2021-01-29 dont 5 mini-minoteries, 2 Development 26 03 24 31 27 Selection rizerie de type 2, 1 entrepôt des intrants agricoles et 6 mini-laiteries de type 2, dans le territoire d’Uvira ZR-MINAGRI-210877-CS- INDV / Recrutement d'un délégué à pied d'oeuvre pour la surveillance des travaux de Construction de 3 entrepôts Individual Agriculture Value Chain Pending 2021-02- 2021-03- 2021-04- 2021-10- des produits agricoles avec IDA / 58520 Post Consultant Limited 8,000.00 0.00 2021-02-05 Development Implementation 10 03 07 04 bureaux des préposés et Selection latrines et d’1 entrepôt semencier à Katanga, dans le cadre du PICAGL, UPEP Sud- Kivu ZR-MINAGRI-210874-CS- INDV / Recrutement d'un délégué à pied d'oeuvre pour la surveillance des travaux de Construction de 3 entrepôts Individual Agriculture Value Chain Pending 2021-02- 2021-03- 2021-04- 2021-10- des produits agricoles avec IDA / 58520 Post Consultant Limited 8,000.00 0.00 2021-02-05 Development Implementation 10 03 07 04 bureaux des préposés et Selection latrines à Baraka et d’1 entrepôt semencier à Nemba, dans le cadre du PICAGL, UPEP Sud-Kivu ZR-MINAGRI-210876-CS- INDV / Recrutement d'un délégué à pied d'oeuvre pour la surveillance des travaux de Construction de 3 entrepôts Individual Agriculture Value Chain Pending 2021-02- 2021-03- 2021-04- 2021-10- des produits agricoles avec IDA / 58520 Post Consultant Limited 8,000.00 0.00 2021-02-05 Development Implementation 10 03 07 04 bureaux des préposés et Selection latrines à Sebele,Kabondonzi et Malinde et d’1 entrepôt semencier à Sebele,UPEP Sud- Kivu ZR-MINAGRI-210880-CS- INDV / Recrutement d'un délégué à pied d'oeuvre pour la surveillance des travaux de Individual Construction de 4 entrepôts Agriculture Value Chain Pending 2021-02- 2021-03- 2021-04- 2021-10- IDA / 58520 Post Consultant Limited 8,000.00 0.00 2021-02-05 des produits agricoles avec Development Implementation 10 03 07 04 Selection bureaux des préposés et latrines dont 2 à Fizi centre et 2 à Mulongwe, dans le cadre du PICAGL, UPEP Sud- Kivu Page 13 ZR-MINAGRI-210883-CS- INDV / Recrutement d'un délégué à pied d'oeuvre pour la surveillance des travaux de Construction de 3 entrepôts Individual Agriculture Value Chain Pending 2021-02- 2021-03- 2021-04- 2021-10- des produits agricoles avec IDA / 58520 Post Consultant Limited 8,000.00 0.00 2021-02-05 Development Implementation 10 03 07 04 bureaux des préposés et Selection latrines et de 2 entrepôts semenciers à Sange, dans le cadre du PICAGL, UPEP Sud- Kivu ZR-MINAGRI-210873-CS- INDV / Recrutement d'un délégué à pied d'oeuvre pour la surveillance des travaux de Individual Construction de 3 entrepôts Agriculture Value Chain Pending 2021-02- 2021-03- 2021-04- 2021-10- IDA / 58520 Post Consultant Limited 8,000.00 0.00 2021-02-05 des produits agricoles avec Development Implementation 10 03 07 04 Selection bureaux des préposés et latrines à Kiliba et Runingu, et d’1 entrepôt semencier à Kiliba, UPEP Sud-Kivu ZR-MINAGRI-210879-CS- INDV / Recrutement d'un délégué à pied d'oeuvre pour la surveillance des travaux de Individual Construction de 4 entrepôts Agriculture Value Chain Pending 2021-02- 2021-03- 2021-04- 2021-10- IDA / 58520 Post Consultant Limited 8,000.00 0.00 2021-02-05 des produits agricoles avec Development Implementation 10 03 07 04 Selection bureaux des préposés et latrines dont 3 à Luvungi et 1 à Lubarika, dans le cadre du PICAGL, UPEP Sud-Kivu ZR-MINAGRI-210881-CS- INDV / Recrutement d'un délégué à pied d'oeuvre pour la surveillance des travaux de Construction de 4 entrepôts Individual Agriculture Value Chain Pending 2021-02- 2021-03- 2021-04- 2021-10- des produits agricoles avec IDA / 58520 Post Consultant Limited 8,000.00 0.00 2021-02-05 Development Implementation 10 03 07 04 bureaux des préposés et Selection latrines à Kagando, Kahwizi, Kigongo et Murunga, dans le cadre du PICAGL, UPEP Sud- Kivu ZR-MINAGRI-210878-CS- INDV / Recrutement d'un délégué à pied d'oeuvre pour la surveillance des travaux de Construction de 2 entrepôts Individual Agriculture Value Chain Pending 2021-02- 2021-03- 2021-04- 2021-10- des produits agricoles avec IDA / 58520 Post Consultant Limited 8,000.00 0.00 2021-02-05 Development Implementation 10 03 07 04 bureaux des préposés et Selection latrines et d’1 entrepôt semencier à Nyangezi, dans le cadre du PICAGL, UPEP Sud- Kivu ZR-MINAGRI-210882-CS- INDV / Recrutement d'un délégué à pied d'oeuvre pour la surveillance des travaux de Individual Construction de 3 entrepôts Agriculture Value Chain Pending 2021-02- 2021-03- 2021-04- 2021-10- IDA / 58520 Post Consultant Limited 8,000.00 0.00 2021-02-05 des produits agricoles avec Development Implementation 10 03 07 04 Selection bureaux des préposés et latrines à Kamanyola, dans le cadre du PICAGL, UPEP Sud- Kivu ZR-MINAGRI-210875-CS- INDV / Recrutement d'un délégué à pied d'oeuvre pour la surveillance des travaux de Construction de 2 entrepôts Individual Agriculture Value Chain Pending 2021-02- 2021-03- 2021-04- 2021-10- des produits agricoles avec IDA / 58520 Post Consultant Limited 8,000.00 0.00 2021-02-05 Development Implementation 10 03 07 04 bureaux des préposés et Selection latrines dont 1 à Mudaka et 1 à Bunyakiri/Bitale, dans le cadre du PICAGL, UPEP Sud- Kivu ZR-MINAGRI-210976-CS- INDV / Recrutement d’un (1) délégué à pied d’œuvre pour Individual le contrôle et la surveillance Agriculture Value Chain 2021-05- 2021-02- 2021-02- 2021-04- 2021-09- IDA / 58520 Post Consultant Limited 8,000.00 0.00 Under Review 2021-02-01 des Travaux de construction Development 26 06 27 03 30 Selection d’une (1) laiterie de type 3 à Cirunga, dans le territoire de Kabare ZR-MINAGRI-210978-CS- INDV / Recrutement d’un (1) délégué à pied d’œuvre pour le contrôle et la surveillance Individual Agriculture Value Chain 2021-05- 2021-02- 2021-02- 2021-04- 2021-09- des Travaux de construction IDA / 58520 Post Consultant Limited 8,000.00 0.00 Under Review 2021-02-01 Development 26 06 27 03 30 de trois (3) laiteries de type 3 Selection dont deux (2) à Luvungi et une (1) à Bwegera, dans le territoire d’Uvira ZR-MINAGRI-210977-CS- INDV / Recrutement d’un (1) délégué à pied d’œuvre pour le contrôle et la surveillance Individual Agriculture Value Chain 2021-05- 2021-02- 2021-02- 2021-04- 2021-09- des Travaux de construction IDA / 58520 Post Consultant Limited 8,000.00 0.00 Under Review 2021-02-01 Development 26 06 27 03 30 de quatre (4) laiteries de type Selection 3 dont 1 à Sange, 1 à Kavimvira et 2 à Uvira, dans le territoire d’Uvira ZR-MINAGRI-213742-CS- INDV / Recrutement d'un délégué à pied d'oeuvre pour la mission de contrôle et Individual surveillance des Travaux de Agriculture Value Chain Pending 2021-02- 2021-03- 2021-04- 2021-10- IDA / 58520 Post Consultant Limited 8,000.00 0.00 2021-02-08 construction de deux (2) mini Development Implementation 13 06 10 07 Selection chambres froides dont 1 à Luberezi et 1 Mutarule, dans le cadre du PICAGL, UPEP Sud- Kivu Page 14 PLAN DE PASSATION DES MARCHES AVEC INDICATION DES SEUILS DE REVUE ET DE PASSATION DES MARCHES Information sur le Projet : Togo –Projet de Filets Sociaux et de Services de Base (P157038) Agence d’exécution du Projet : Agence Nationale d’Appui au Développement à la Base (ANADEB) Date du plan de passation des marchés: 11 Septembre, 2017 Période couverte par ce plan de passation des marchés: Septembre, 2017 – 31 août, 2018 I. GENERAL 1. Informations sur le Projet : P-RAMS • Evaluation de risque par P-RAMS (Procurement Risk Assessment and Management System): Elevé II. TRAVAUX, FOURNITURES ET SERVICES AUTRES QUE LES SERVICES DE CONSULTANTS 1. Dispositions relatives aux seuils de revue préalable : Seuils requis pour les décisions de marchés soumis à la revue préalable de la Banque, tel que prévu dans l’annexe 1 des "Directives de Passation des Marchés de fournitures, de travaux et de services (autres que les services de consultants) par les Emprunteurs de la Banque mondiale dans le cadre des prêts de la BIRD et des crédits de l’AID. Catégories de Seuils de revue a Observations marchés/Méthode de priori passation des marchés Montants estimatifs des contrats en millions de dollars américains Travaux, Contrats clé en main et Contrats de >= 5 Fourniture et Montage d’Installations Fournitures, Système d’information, et Services >= 1.5 autres que les services de consultants Travaux, Les justifications de Contrats Contrats clé en l’entente directe à passer main et devront être jointes par Contrats de >= 5 et approuvées avec entente Fourniture et PPM directe Montage d’Installations Fournitures, Système d’information, et Services >= 1.5 autres que les services de consultants 2. Pré qualification : Aucune n’a été pour l’instant identifiée. Toutefois, en cas de pré-qualification, les soumissionnaires seront pré qualifiées en accord avec les dispositions des paragraphes 2.9 et 2.10 des directives. 3. Seuils pour les méthodes de passation des marchés : Les seuils de passation des marchés se présentent comme suit au vu des conditions du marché : FOURNITURES ET SERVICES AUTRE QUE LES SERVICES DE CONSULTANTS (US$ TRAVAUX (US$ équivalent) équivalent) AOI AON CF AOI AON CF < < 100.000 ≥5.000.000 <5.000.000 ≥ 500.000 < 500.000 200.000 4. Dispositions spéciales sur les marchés : Concernant les acquisitions de véhicules et de carburant, en fonction des circonstances et des besoins spécifiques du pays, le seuil pour la consultation de fournisseurs pourrait être porté à la contre-valeur d’USD 500,000 (en prenant soin de consulter tous les principaux concessionnaires de marque ou distributeurs de produits pétroliers). II. Sélection des Consultants 1. Dispositions relatives aux seuils de revue préalable des marchés : Décisions de sélection sujet à la revue préalable de la Banquet comme indiqué dans l’annexe 1 du Guide de Sélection et d’Emploi des Consultants par les Emprunteurs de la Banque Mondiale dans le cadre des Prêts de la BIRD et des Crédits et Dons de l’AID Méthode de Seuils de revue a Observations sélection/Catégories de priori marchés Montants estimatifs des contrats en millions de dollars américains Méthode >= 0.5 compétitive/Firmes de consultants Entente directe/firmes Les justifications pour >= 0.5 de consultants l’entente directe Entente devront être jointes et directe/Consultants >= 0.2 approuvées avec le individuel PPM Méthode Compétitive >= 0.2 (Comparaison de CVs)/ Consultants individuels 2. Liste restreinte composée entièrement de firmes nationales: La liste restreinte de consultants pour les prestations d’études d’ingénierie, de contrôle et de surveillance estimées à moins de 300,000 US$ par contrat, et pour tout autre type de prestations, estimées à moins de 100 000 US$ par contrat, peut comporter entièrement de consultants nationaux selon les dispositions du paragraphe 2.7 des Directives de Sélection et d’Emploi des Consultants, et l’Emprunteur ne procède pas à une publication dans UNDB. 3. Autre arrangement spécial de Sélection de consultants : Le seuil pour l’utilisation de la méthode de sélection de consultant fondée sur les qualifications des consultants est déterminé au cas par cas en tenant compte de la nature et de la complexité de la mission; cependant, ce seuil ne devrait pas dépasser la contre-valeur de USD 300,000 sauf dans des cas exceptionnels prévus au paragraphe 3.7 des directives pour la sélection et l’emploi des consultants par les emprunteurs de la Banque Mondiale dans le cadre des Prêts de la BIRD et des Crédits et Dons de l’AID PROCUREMENT Togo : Safety Nets and Basic Services Project PLAN General Information Country: Togo Bank’s Approval Date of the Original Procurement Plan: 2017-09-11 2021-06-01 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P157038 GPN Date: 2017-07-31 Project Name: Safety Nets and Basic Services Project Loan / Credit No: IDA / V0650, IDA / D1740 N Executing Agency(ies): ational Agency for Development Support at the Base WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned 03FT-PFS / Travaux Component 3:Capacity Request for Single Stage - One 2017-11- d'aménagement des Antennes IDA / V0650 building and project Post Limited 24,167.00 38,573.20 Signed 2017-07-20 2017-09-08 2017-09-14 2018-02-02 Quotations Envelope 13 Régionales ANADEB management GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 3:Capacity 01FT-PFS / Acquisition de UN Agencies IDA / V0650 building and project Post Direct 300,000.00 223,857.36 Completed 2017-04-14 2017-06-01 2017-04-21 2017-06-01 2017-06-09 2017-09-25 2017-11-06 2018-01-15 matériel roulant (Direct) management 06FT-PFS / Reproduction des Component 2: Social safety Request for Single Stage - One carnets de reçus pour IDA / D1740 Post Limited 17,000.00 4,690.48 Completed 2017-08-22 2017-09-08 2017-10-17 2017-10-09 2017-11-16 2017-10-30 nets Quotations Envelope l'opération cantine scolaire Component 3:Capacity 02FT-PFS / Acquisition de Single Stage - One IDA / V0650 building and project Post Request for Bids Open - National 129,000.00 217,653.64 Signed 2017-04-14 2018-01-20 2017-04-21 2017-05-21 2017-07-19 2017-06-20 2017-09-20 2018-02-07 2017-12-27 2018-04-08 matériels informatiques Envelope management TG-ANADEB-44865-GO-RFB Component 3:Capacity Single Stage - One / Acquisition de six (6) IDA / V0650 building and project Post Request for Bids Open - National 70,000.00 75,869.41 Signed 2017-07-11 2017-07-18 2017-08-17 2017-09-04 2017-09-16 2017-10-20 2017-10-28 2018-07-20 2017-12-27 Envelope groupes électrogènes management TG-ANADEB-46559-GO-RFQ / Tablettes: Acquisition de 50 Component 3:Capacity tablettes pour les enquêtes Request for Single Stage - One IDA / D1740 building and project Post Limited 23,334.00 24,278.90 Completed 2018-02-06 2018-09-05 2018-04-03 2018-11-14 2018-06-02 2018-11-20 (PMT, géolocalisation, Quotations Envelope management enregistrement de données de terrain) TG-ANADEB-46571-GO-RFQ Component 3:Capacity / Fournitures de Bureau: Request for Single Stage - One IDA / D1740 building and project Post Limited 16,667.00 0.00 Canceled 2018-04-04 2018-05-30 2018-11-26 Acquisition de fournitures de Quotations Envelope management bureau TG-ANADEB-101617-GO- RFQ / Consommables cartes TM: Acquisition des Component 3:Capacity Request for Single Stage - One consommables pour la IDA / D1740 building and project Post Limited 17,000.00 29,589.54 Completed 2019-03-09 2019-03-11 2019-05-04 2019-05-02 2019-07-03 2019-05-27 Quotations Envelope production des cartes des management bénéficiaires des transferts monétaires TG-ANADEB-101632-GO- RFQ / Consommables de Component 3:Capacity Request for Single Stage - One bureau: Acquisition de IDA / D1740 building and project Post Limited 25,000.00 0.00 Canceled 2019-03-05 2019-04-30 2020-02-24 Quotations Envelope consommables informatiques management et bureautiques TG-ANADEB-46558-GO-RFQ / Communication institutionnelle: Production Component 3:Capacity de supports imprimés de Request for Single Stage - One IDA / D1740 building and project Post Limited 24,167.00 0.00 Canceled 2018-02-25 2018-04-22 2018-10-19 communication Quotations Envelope management institutionnelle autour du projet (dépliants, gadgets, étrennes, kakemono etc,) TG-ANADEB-46574-GO-RFQ Component 3:Capacity Request for Single Stage - One / Fourniture de IDA / D1740 building and project Post Limited 16,667.00 0.00 Canceled 2019-09-21 2019-11-16 2019-12-16 Quotations Envelope consommables informatiques management TG-ANADEB-123497-GO- DIR / Moteurs véhicules: Component 3:Capacity Acquisition, montage et IDA / D1740 building and project Post Direct Selection Direct 75,000.00 81,236.08 Signed 2019-09-11 2019-07-01 2019-09-26 2019-07-16 2019-10-27 2019-10-31 2020-01-25 services connexes de six (6) management moteurs pour les véhicules rétrocédés du projet PDCplus TG-ANADEB-164855-GO- RFQ / Tablette pour le Component 3:Capacity personnel: Acquisition de dix Request for Single Stage - One IDA / D1740 building and project Post Limited 15,000.00 28,486.57 Completed 2020-04-04 2020-11-20 2020-05-30 2020-12-31 2020-06-29 2021-02-15 (10) tablettes pour le Quotations Envelope management personnel de l'unité de gestion du projet TG-ANADEB-180540-GO- RFQ / ACQUISITION EPI: Acquisition des équipements Component 3:Capacity de protection individuels (EPI) Request for Single Stage - One IDA / D1740 building and project Post Limited 15,000.00 24,303.99 Completed 2020-07-01 2020-07-02 2020-08-26 2020-09-15 2020-09-15 2020-10-19 pour le personnel de Quotations Envelope management l'ANADEB dans le cadre de suivi et supervision de mise en œuvre des microprojets sur le terrain Page 1 TG-ANADEB-212323-GO- RFQ / Acquisition 3 Lap top: Acquisition de trois (03) Component 3:Capacity Pending ordinateurs performants pour Request for Single Stage - One IDA / D1740 building and project Post Limited 8,000.00 0.00 Implementati 2021-01-20 2021-03-17 2021-04-16 la gestion des bases de Quotations Envelope management on données du projet Filets sociaux et services de base (FSB) NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 07FT-PFS / Location de Component 3:Capacity bureau dans les antennes IDA / V0650 building and project Post Direct Selection Direct 12,000.00 0.00 Canceled 2017-09-14 2017-09-19 2017-10-24 2018-10-24 régionales ANADEB management TG-ANADEB-46584-NC-RFQ Component 3:Capacity / Assurance du personnel: Request for Single Stage - One IDA / D1740 building and project Post Limited 16,667.00 12,806.53 Signed 2018-02-05 2018-07-09 2018-04-02 2018-06-19 2019-03-28 Souscription de police Quotations Envelope management d'assurance pour le personnel TG-ANADEB-48433-NC-RFQ / Extension réseau internet: Fourniture de services Component 3:Capacity Request for Single Stage - One d'extension du réseau intranet IDA / D1740 building and project Post Limited 20,000.00 0.00 Canceled 2018-02-22 2018-04-19 2018-06-18 Quotations Envelope et internet (câblage et management connections internet ADSL) dans les bureaux de l'ANADEB TG-ANADEB-48480-NC-RFQ / Supports audio-visuels: Component 3:Capacity Production des manuels et Request for Single Stage - One IDA / D1740 building and project Post Limited 33,334.00 0.00 Canceled 2018-03-08 2018-05-03 2018-07-02 des guides illustrés du projet Quotations Envelope management sous forme de supports audio- visuels TG-ANADEB-48435-NC-RFB / Impression et multiplication Component 3:Capacity des manuels, des brochures, Single Stage - One IDA / D1740 building and project Post Request for Bids Open - National 75,000.00 0.00 Canceled 2018-03-01 2018-03-08 2018-04-19 2018-05-19 2018-06-23 2018-08-22 des guides illustrés et des Envelope management supports pédagogiques sur les activités du projet TG-ANADEB-48434-NC-RFQ Component 3:Capacity / Magasine: Production d'un Request for Single Stage - One IDA / D1740 building and project Post Limited 16,667.00 0.00 Canceled 2018-03-11 2018-05-06 2018-07-05 magasine d'information Quotations Envelope management semestriel TG-ANADEB-49332-NC-RFQ / Paiement des TM: Fourniture des services de transfert Component 2: Social safety Request for Single Stage - One IDA / D1740 Post Limited 100,000.00 79,045.10 Signed 2018-03-06 2018-10-12 2018-05-08 2018-12-24 2019-05-03 monétaires aux bénéficiaires nets Quotations Envelope de la sous composante des Transferts monétaires 05FT-PFS / Acquisition de modules complémentaires de Component 3:Capacity TOM2PRO et de IDA / V0650 building and project Post Direct Selection Direct 70,000.00 0.00 Canceled 2017-04-21 2017-04-28 2017-06-16 2017-08-15 TOMMONITORING et des clé management de connexion et fourniture de services connexes TG-ANADEB-69430-NC-DIR / LOGICIEL TOM2PRO: Acquisition de modules Component 3:Capacity complémentaires de IDA / D1740 building and project Post Direct Selection Direct 105,000.00 108,947.26 Signed 2018-07-12 2018-07-27 2018-07-17 2018-08-03 2018-08-21 2018-10-12 2018-09-20 TOM2PRO et de management TOMMONITORING et des clé de connexion et fourniture de services connexes TG-ANADEB-99919-NC-RFQ / Reproduction guides FGB: Component 3:Capacity Reproduction des guides Request for Single Stage - One IDA / D1740 building and project Post Limited 55,000.00 39,058.24 Signed 2019-03-20 2019-05-29 2019-05-22 2019-09-11 2019-11-18 illustrés de formation de Quotations Envelope management gestion à la base (FGB) du projet TG-ANADEB-101629-NC- RFQ / Carnet TM: Component 3:Capacity Request for Single Stage - One Reproduction des cartes de IDA / D1740 building and project Post Limited 30,000.00 10,191.40 Signed 2019-03-05 2019-03-14 2019-04-30 2019-05-21 2019-05-30 Quotations Envelope bénéficiaires des transferts management monétaires TG-ANADEB-101958-NC- RFQ / Extension câblage internet: Fourniture de services d'extension du Component 3:Capacity Request for Single Stage - One réseau intranet et internet IDA / D1740 building and project Post Limited 20,000.00 0.00 Canceled 2019-03-06 2019-05-01 2019-05-31 Quotations Envelope (câblage et connections management internet ADSL) dans les bureaux des Antennes régionales de l'ANADEB TG-ANADEB-197272-NC- RFQ / PLANCHES PHOTO CAUSERIES TM: Reproduction Component 3:Capacity Pending Request for Single Stage - One de planches-photo pour les IDA / D1740 building and project Post Limited 50,000.00 0.00 Implementati 2020-11-04 2021-01-06 2021-02-05 Quotations Envelope causeries socio-éducatives management on sur les transferts monétaire (TM) CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 2 01PI-PFS / Sélection d'un Component 3:Capacity Consultant cabinet pour le recrutement IDA / V0650 building and project Post Qualification Open - National 40,000.00 16,801.42 Signed 2017-04-10 2017-05-02 2017-05-01 2017-06-14 2017-07-04 2017-07-14 2017-07-28 2017-08-18 2017-08-17 2017-10-17 du personnel du projet management Selection 06PI-PFS / Recrutement des Consultant ONG pour la mise en œuvre Component 2: Social safety IDA / D1740 Post Qualification Open - National 195,000.00 130,248.82 Signed 2017-07-05 2017-10-20 2017-07-26 2017-09-08 2017-11-14 2017-10-08 2017-12-15 2017-11-12 2017-12-26 2018-08-09 des cantines scolaires dans nets Selection les écoles bénéficiaires 02PI-PFS / Recrutement d'un Component 3:Capacity cabinet pour l'audit des Least Cost IDA / V0650 building and project Post Open - National 15,000.00 0.00 Canceled 2017-07-15 2017-08-05 2017-09-18 2017-10-16 2017-11-15 2017-12-20 2018-01-24 2018-02-23 comptes du fonds de Selection management préparation du projet TG-ANADEB-46579-CS-LCS / Audit Financier Comptable: Sélection d'un cabinet pour Component 3:Capacity Least Cost l'audit financier et comptable IDA / D1740 building and project Post Open - National 40,000.00 57,412.34 Signed 2018-05-31 2018-09-26 2018-06-21 2018-08-04 2018-12-12 2018-09-01 2018-12-31 2018-10-01 2019-01-16 2018-11-05 2019-02-05 2018-12-10 2019-04-02 2019-10-06 Selection du Projet, Exercices 2018 management (Juillet 2017 à Décembre 2018), 2019 et 2020 TG-ANADEB-101956-CS- CQS / Évaluation processus Component 3:Capacity Consultant TM: Recrutement d'un IDA / D1740 building and project Post Qualification Open - National 50,000.00 60,845.87 Completed 2019-04-15 2020-02-26 2019-04-29 2019-06-28 2020-06-19 2019-07-19 2020-08-07 2019-08-23 2020-08-26 2019-10-22 2021-02-12 consultant pour l'évaluation management Selection du processus du programme des transferts monétaires TG-ANADEB-46577-CS-CQS / Conception SIG: Sélection Consultant d'un consultant pour la Component 2: Social safety IDA / V0650 Post Qualification Open - National 58,334.00 0.00 Canceled 2018-01-31 2018-02-21 2018-04-06 2018-05-06 2018-06-10 2018-09-08 conception et l'installation du nets Selection système d'information et de gestion (SIG) des projets TG-ANADEB-143908-CS- CQS / Agence de communication: sélection Component 3:Capacity Consultant d'une agence de IDA / D1740 building and project Post Qualification Limited 25,000.00 0.00 Canceled 2019-11-20 2019-12-04 2020-01-03 2020-02-07 2020-12-03 communication pour la management Selection capitalisation des réalisations du projet FSB TG-ANADEB-101955-CS- CQS / Mise en place du RSU: Component 3:Capacity Consultant Sélection d'une firme pour la IDA / D1740 building and project Post Qualification Open - National 92,000.00 0.00 Canceled 2020-04-30 2020-05-14 2020-07-13 2020-08-03 2020-09-07 2020-12-06 mise en place du système du management Selection registre social unifié (RSU) TG-ANADEB-197245-CS- CQS / Formation en sauvegarde du personnel: Recrutement d'un cabinet Component 3:Capacity Consultant pour la formation du IDA / D1740 building and project Post Qualification Open - National 50,000.00 0.00 Canceled 2020-10-30 2020-12-07 2020-11-13 2020-12-27 2021-01-11 2021-02-15 2021-03-17 personnel de l'ANADEB sur les management Selection directives en sauvegardes environnementales et sociales des bailleurs notamment la Banque mondiale TG-ANADEB-204771-CS- CQS / Étude Financement Component 3:Capacity Consultant Cantines: Sélection d'un IDA / D1740 building and project Post Qualification Open - National 42,000.00 0.00 Canceled 2020-12-31 2021-01-21 2021-03-06 2021-04-05 2021-05-10 2021-07-09 cabinet pour l'étude sur les management Selection financements innovants des cantines scolaires TG-ANADEB-228821-CS- CQS / AUDIT TM DIGITAUX: SÉLECTION D'UN BUREAU/CABINET POUR Component 3:Capacity Consultant Pending L'AUDIT DES PAIEMENTS IDA / D1740 building and project Post Qualification Open - National 65,000.00 0.00 2021-04-20 2021-05-04 2021-06-08 2021-06-29 2021-08-03 2021-09-02 Implementation DIGITAUX DES TRANSFERTS management Selection MONÉTAIRES (TM) DU PROJET DE FILETS SOCIAUX ET SERVICES DE BASE (FSB) INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 05PI-PFS / Recrutement d'un consultant national en appui Component 3:Capacity Individual au système de planification et IDA / V0650 building and project Post Consultant Open 17,000.00 0.00 Canceled 2017-10-02 2017-11-20 2017-12-11 2018-01-15 2018-07-14 du suivi évaluation de management Selection l'ANADEB TG-ANADEB-36702-CS-INDV / Coordonnateur: Component 3:Capacity Individual Recrutement d'Un IDA / D1740 building and project Post Consultant Open 30,000.00 33,512.32 Signed 2017-06-01 2017-06-09 2017-07-20 2017-11-23 2017-08-10 2017-11-24 2017-09-14 2018-03-01 2018-09-09 Coordonnateur pour le management Selection compte de l'Unité de gestion du projet TG-ANADEB-46332-CS-INDV / Consultant FGB : Component 3:Capacity Individual Recrutement d'un (01) IDA / D1740 building and project Post Consultant Open 33,350.00 33,387.89 Signed 2018-01-28 2018-03-18 2018-04-05 2018-04-08 2018-06-11 2018-05-13 2018-08-10 2018-11-09 Consultant pour l'actualisation management Selection des outils de formation en gestion à la base (FGB) TG-ANADEB-46353-CS-INDV Component 3:Capacity Individual / Assistant SSE: Recrutement IDA / D1740 building and project Post Consultant Open 15,000.00 15,703.71 Signed 2018-01-31 2018-01-31 2018-03-21 2018-09-20 2018-04-11 2018-09-26 2018-05-16 2018-10-01 2019-05-11 d'un (01) Assistant suivi- management Selection évaluation Page 3 TG-ANADEB-46355-CS-INDV / Gestionnaire SIG: Component 3:Capacity Individual Recrutement d'un (01) IDA / D1740 building and project Post Consultant Open 20,000.00 15,461.44 Signed 2018-01-31 2018-05-17 2018-03-21 2019-01-09 2018-04-11 2019-01-11 2018-05-16 2019-01-14 2019-05-11 Spécialiste en système management Selection d'information et de gestion (SIG) TG-ANADEB-46359-CS-INDV / Assistant administratif: Component 3:Capacity Individual Recrutement d'un (01) IDA / D1740 building and project Post Consultant Open 10,000.00 6,260.62 Signed 2018-01-31 2018-01-31 2018-03-21 2018-09-21 2018-04-11 2018-09-26 2018-05-16 2018-10-01 2019-05-11 Assistant administratif pour le management Selection projet TG-ANADEB-46799-CS-INDV / Sauvegarde sociale: Component 3:Capacity Individual Recrutement d'un Spécialiste IDA / D1740 building and project Post Consultant Open 20,000.00 26,587.73 Signed 2017-10-15 2017-10-20 2017-12-03 2017-12-26 2017-12-24 2018-04-09 2018-01-28 2018-04-10 2019-01-23 en sauvegarde sociale pour le management Selection compte du projet TG-ANADEB-44863-CS-INDV / SGF: Recrutement d'Un Component 3:Capacity Individual Spécialiste en gestion IDA / D1740 building and project Post Consultant Open 10,000.00 22,551.84 Signed 2017-06-01 2017-06-09 2017-07-20 2017-11-24 2017-08-10 2017-12-06 2017-09-14 2018-03-01 2018-03-13 financière (SGF) pour le management Selection compte de l'Unité de gestion du projet TG-ANADEB-44864-CS-INDV / SPM: Recrutement d'un Component 3:Capacity Individual Spécialiste en passation de IDA / D1740 building and project Post Consultant Open 10,000.00 25,026.30 Signed 2017-06-01 2017-06-09 2017-07-20 2017-12-11 2017-08-10 2017-12-13 2017-09-14 2018-03-01 2018-03-13 marchés (SPM) pour le compte management Selection de l'Unité de gestion du projet TG-ANADEB-46352-CS-INDV / Filets Sociaux RM: Recrutement d'un(e) Assistant Component 3:Capacity Individual régional en transfert IDA / D1740 building and project Post Consultant Open 14,000.00 15,703.71 Signed 2018-01-31 2018-01-31 2018-03-21 2018-09-20 2018-04-11 2018-09-26 2018-05-16 2018-10-01 2019-05-11 monétaire/ cantines scolaires management Selection pour le compte du projet au profit de l'antenne régionale Maritime de l'ANADEB TG-ANADEB-46357-CS-INDV / FGB Région Maritime: Recrutement d'un(e) Component 3:Capacity Individual Formateur en gestion à la IDA / D1740 building and project Post Consultant Open 14,000.00 15,654.14 Signed 2018-01-31 2018-01-31 2018-03-21 2018-09-28 2018-04-11 2018-10-04 2018-05-16 2018-11-12 2019-05-11 base (FGB) pour le compte du management Selection projet au profit de l'antenne régionale Maritime de l'ANADEB TG-ANADEB-46365-CS-INDV / Graphiste: Recrutement d'un illustrateur (Graphiste) pour Component 3:Capacity Individual l'actualisation/adaptation des IDA / D1740 building and project Post Consultant Open 15,000.00 0.00 Canceled 2018-02-05 2018-03-26 2018-04-16 2018-05-21 2018-09-18 boîtes à images des modules management Selection de formation en gestion à la base (FGB) TG-ANADEB-48453-CS-INDV / FGB Région Plateaux: Recrutement d'un(e) Component 3:Capacity Individual Formateur en gestion à la IDA / D1740 building and project Post Consultant Open 14,000.00 15,703.71 Signed 2018-01-31 2018-01-31 2018-03-21 2018-09-28 2018-04-11 2018-10-01 2018-05-16 2018-10-04 2019-05-11 base (FGB) pour le compte du management Selection projet au profit de l'antenne régionale Plateaux de l'ANADEB TG-ANADEB-48454-CS-INDV / FGB Région Centrale: Recrutement d'un(e) Component 3:Capacity Individual Formateur en gestion à la IDA / D1740 building and project Post Consultant Open 14,000.00 15,703.71 Signed 2018-01-31 2018-01-31 2018-03-21 2018-09-28 2018-04-11 2018-10-04 2018-05-16 2018-10-08 2019-05-11 base (FGB) pour le compte du management Selection projet au profit de l'antenne régionale Centrale de l'ANADEB TG-ANADEB-48455-CS-INDV / FGB Région Kara: Recrutement d'un(e) Component 3:Capacity Individual Formateur en gestion à la IDA / D1740 building and project Post Consultant Open 14,000.00 15,703.71 Signed 2018-01-31 2018-01-31 2018-03-21 2018-09-28 2018-04-11 2018-10-01 2018-05-16 2018-10-03 2019-05-11 base (FGB) pour le compte du management Selection projet au profit de l'antenne régionale Kara de l'ANADEB TG-ANADEB-48457-CS-INDV / FGB Région Savanes: Recrutement d'un(e) Component 3:Capacity Individual Formateur en gestion à la IDA / D1740 building and project Post Consultant Open 14,000.00 15,703.71 Signed 2018-01-31 2018-01-31 2018-03-21 2018-09-28 2018-04-11 2018-10-04 2018-05-16 2018-10-04 2019-05-11 base (FGB) pour le compte du management Selection projet au profit de l'antenne régionale Savanes de l'ANADEB TG-ANADEB-48459-CS-INDV / Filets Sociaux RP: Recrutement d'un(e) Assistant Component 3:Capacity Individual régional en transfert IDA / D1740 building and project Post Consultant Open 14,000.00 15,703.71 Signed 2018-01-31 2018-01-31 2018-04-04 2018-09-26 2018-04-25 2018-09-28 2018-05-30 2018-10-01 2019-05-25 monétaire/ cantines scolaires management Selection pour le compte du projet au profit de l'antenne régionale Plateaux de l'ANADEB TG-ANADEB-48460-CS-INDV / Filets Sociaux RC: Recrutement d'un(e) Assistant Component 3:Capacity Individual régional en transfert IDA / D1740 building and project Post Consultant Open 14,000.00 15,703.71 Signed 2018-01-31 2018-01-31 2018-03-21 2018-09-13 2018-04-11 2018-10-26 2018-05-16 2018-10-01 2019-05-11 monétaire/ cantines scolaires management Selection pour le compte du projet au profit de l'antenne régionale Centrale de l'ANADEB TG-ANADEB-48463-CS-INDV / Filets Sociaux RK: Recrutement d'un(e) Assistant Component 3:Capacity Individual régional en transfert IDA / D1740 building and project Post Consultant Open 14,000.00 15,703.71 Signed 2018-01-31 2018-01-31 2018-03-21 2018-09-20 2018-04-11 2018-09-26 2018-05-16 2018-10-01 2019-05-11 monétaire/ cantines scolaires management Selection pour le compte du projet au profit de l'antenne régionale Kara de l'ANADEB Page 4 TG-ANADEB-48464-CS-INDV / Filets Sociaux RS: Recrutement d'un(e) Assistant Component 3:Capacity Individual régional en transfert IDA / D1740 building and project Post Consultant Open 14,000.00 15,703.71 Signed 2018-01-31 2018-01-31 2018-03-21 2018-09-20 2018-04-11 2018-09-26 2018-05-16 2018-10-01 2019-05-11 monétaire/ cantines scolaires management Selection pour le compte du projet au profit de l'antenne régionale Savanes de l'ANADEB TG-ANADEB-46341-CS-CDS / Ciblage de bénéficiaires: Component 2: Social safety Sélection d'une firme pour le IDA / V0650 Post Direct Selection Direct 116,667.00 97,705.78 Signed 2018-01-28 2018-03-29 2018-02-09 2018-05-11 2018-04-15 2018-07-20 2018-08-13 nets ciblage des bénéficiaires du projet TG-ANADEB-48466-CS-INDV / Assistant Infra RP: Recrutement d'un Assistant régional en Infrastructures, Component 3:Capacity Individual Chargé de la passation des IDA / D1740 building and project Post Consultant Open 16,000.00 15,390.55 Signed 2018-01-31 2018-01-31 2018-03-21 2018-10-09 2018-04-11 2018-12-31 2018-05-16 2019-01-07 2019-05-11 marchés pour le compte du management Selection projet au profit de l'antenne régionale Plateaux de l'ANADEB TG-ANADEB-46802-CS-INDV / Comptable-gestionnaire: Component 3:Capacity Individual Recrutement d'un Comptable- IDA / D1740 building and project Post Consultant Direct 10,000.00 0.00 Canceled 2017-12-01 2017-12-11 2017-12-18 2018-01-01 2018-06-30 gestionnaire au niveau management Selection national pour le compte du projet TG-ANADEB-46351-CS-INDV / Assistant Infra RM: Recrutement d'un Assistant régional en Infrastructures, Component 3:Capacity Individual Chargé de la passation des IDA / D1740 building and project Post Consultant Open 16,000.00 15,703.71 Signed 2018-01-31 2018-01-31 2018-03-21 2018-09-21 2018-04-11 2018-09-26 2018-05-16 2018-10-01 2019-05-11 marchés pour le compte du management Selection projet au profit de l'antenne régionale Maritime de l'ANADEB TG-ANADEB-46358-CS-INDV / Comptable-Gestionnaire RM: Recrutement d'un Component 3:Capacity Individual comptable-gestionnaire IDA / D1740 building and project Post Consultant Open 14,000.00 14,688.17 Signed 2018-01-31 2018-01-31 2018-03-21 2018-09-13 2018-04-11 2018-09-26 2018-05-16 2018-10-01 2019-05-11 régional pour le compte du management Selection projet au profit de l'antenne régionale Maritime de l'ANADEB TG-ANADEB-46363-CS-INDV / Secrétaire-Caissier RM: Recrutement d'un(e) secrétaire Component 3:Capacity Individual caissier pour le compte du IDA / D1740 building and project Post Consultant Open 6,000.00 5,217.18 Signed 2018-01-31 2018-01-31 2018-03-21 2018-09-21 2018-04-11 2018-09-26 2018-05-16 2018-10-08 2019-05-11 projet au profit de l'antenne management Selection régionale Maritime de l'ANADEB TG-ANADEB-48450-CS-INDV / Secrétaire-Caissier RP: Recrutement d'un(e) secrétaire Component 3:Capacity Individual Under caissier pour le compte du IDA / D1740 building and project Post Consultant Open 6,000.00 0.00 2018-01-31 2018-01-31 2018-03-21 2018-04-11 2018-05-16 2019-05-11 Implementation projet au profit de l'antenne management Selection régionale Plateaux de l'ANADEB TG-ANADEB-48451-CS-INDV / Secrétaire-Caissier RC: Recrutement d'un(e) secrétaire Component 3:Capacity Individual caissier pour le compte du IDA / D1740 building and project Post Consultant Open 6,000.00 5,217.18 Signed 2018-01-31 2018-01-31 2018-03-21 2018-09-21 2018-04-11 2018-09-26 2018-05-16 2018-10-01 2019-05-11 projet au profit de l'antenne management Selection régionale Centrale de l'ANADEB TG-ANADEB-48468-CS-INDV / Assistant Infra RC: Recrutement d'un Assistant régional en Infrastructures, Component 3:Capacity Individual Chargé de la passation des IDA / D1740 building and project Post Consultant Open 16,000.00 15,703.71 Signed 2018-01-31 2018-01-31 2018-03-21 2018-09-21 2018-04-11 2018-09-26 2018-05-16 2018-10-01 2019-05-11 marchés pour le compte du management Selection projet au profit de l'antenne régionale Centrale de l'ANADEB TG-ANADEB-48469-CS-INDV / Assistant Infra RK: Recrutement d'un Assistant Component 3:Capacity Individual régional en Infrastructures, IDA / D1740 building and project Post Consultant Open 16,000.00 15,703.71 Signed 2018-01-31 2018-01-31 2018-03-21 2018-09-21 2018-04-11 2018-09-26 2018-05-16 2018-10-01 2019-05-11 Chargé de la passation des management Selection marchés pour le compte du projet au profit de l'antenne régionale Kara de l'ANADEB TG-ANADEB-48470-CS-INDV / Assistant Infra RS: Recrutement d'un Assistant régional en Infrastructures, Component 3:Capacity Individual Chargé de la passation des IDA / D1740 building and project Post Consultant Open 16,000.00 15,187.47 Signed 2018-01-31 2018-01-31 2018-03-21 2018-10-30 2018-04-11 2019-10-30 2018-05-16 2018-11-12 2019-05-11 marchés pour le compte du management Selection projet au profit de l'antenne régionale Savanes de l'ANADEB TG-ANADEB-48473-CS-INDV / Comptable-Gestionnaire RP: Recrutement d'un comptable- Component 3:Capacity Individual gestionnaire régional pour le IDA / D1740 building and project Post Consultant Open 14,000.00 14,688.17 Signed 2018-01-31 2018-01-31 2018-03-21 2018-04-11 2018-09-26 2018-05-16 2018-10-01 2019-05-11 compte du projet au profit de management Selection l'antenne régionale Plateaux de l'ANADEB Page 5 TG-ANADEB-48474-CS-INDV / Comptable-Gestionnaire RC: Recrutement d'un comptable- Component 3:Capacity Individual gestionnaire régional pour le IDA / D1740 building and project Post Consultant Open 14,000.00 14,688.17 Signed 2018-01-31 2018-01-31 2018-03-21 2018-09-13 2018-04-11 2018-09-26 2018-05-16 2018-10-01 2019-05-11 compte du projet au profit de management Selection l'antenne régionale Centrale de l'ANADEB TG-ANADEB-48477-CS-INDV / Comptable-Gestionnaire RS: Recrutement d'un comptable- Component 3:Capacity Individual gestionnaire régional pour le IDA / D1740 building and project Post Consultant Open 14,000.00 14,688.17 Signed 2018-01-31 2018-06-22 2018-03-21 2018-09-13 2018-04-11 2018-09-26 2018-05-16 2018-10-15 2019-05-11 compte du projet au profit de management Selection l'antenne régionale Savanes de l'ANADEB TG-ANADEB-48476-CS-INDV / Comptable-Gestionnaire RK: Recrutement d'un comptable- Component 3:Capacity Individual gestionnaire régional pour le IDA / D1740 building and project Post Consultant Open 14,000.00 14,688.17 Signed 2018-01-31 2018-01-31 2018-03-21 2018-09-13 2018-04-11 2018-09-26 2018-05-16 2018-10-01 2019-05-11 compte du projet au profit de management Selection l'antenne régionale Kara de l'ANADEB TG-ANADEB-46364-CS-INDV / Chauffeur-Coursier FSB: Recrutement d'un (01) Component 3:Capacity Individual Chauffeur-Coursier pour le IDA / D1740 building and project Post Consultant Open 4,000.00 3,131.68 Signed 2018-01-31 2018-01-31 2018-03-21 2018-09-24 2018-04-11 2018-09-26 2018-05-16 2018-10-01 2019-05-11 compte du projet au profit de management Selection la direction générale de l'ANADEB TG-ANADEB-51929-CS-INDV / Chauffeur-Coursier RM: Recrutement d'un (01) Component 3:Capacity Individual Chauffeur-Coursier pour le IDA / D1740 building and project Post Consultant Open 4,000.00 2,712.93 Signed 2018-01-31 2018-01-31 2018-03-21 2018-09-14 2018-04-11 2018-09-26 2018-05-16 2018-10-01 2019-05-11 compte du projet au profit de management Selection l'Antenne régionale de l'ANADEB Maritime TG-ANADEB-51930-CS-INDV / Chauffeur-Coursier RP: Recrutement d'un (01) Component 3:Capacity Individual Under Chauffeur-Coursier pour le IDA / D1740 building and project Post Consultant Open 4,000.00 0.00 2018-01-31 2018-01-31 2018-03-21 2018-09-26 2018-04-11 2018-05-16 2019-05-11 Implementation compte du projet au profit de management Selection l'Antenne régionale de l'ANADEB Plateaux TG-ANADEB-51931-CS-INDV / Chauffeur-Coursier RC: Recrutement d'un (01) Component 3:Capacity Individual Chauffeur-Coursier pour le IDA / D1740 building and project Post Consultant Open 4,000.00 2,714.12 Signed 2018-01-31 2018-01-31 2018-03-21 2018-09-14 2018-04-11 2018-09-26 2018-05-16 2018-10-01 2019-05-11 compte du projet au profit de management Selection l'Antenne régionale de l'ANADEB Centrale TG-ANADEB-62826-CS-INDV / Formation en Passation des Component 3:Capacity Individual Marchés: Recrutement d'un IDA / D1740 building and project Post Consultant Limited 25,000.00 0.00 Canceled 2018-05-31 2018-06-05 2018-06-26 2018-07-31 2018-09-29 consultant pour la formation management Selection des acteurs sur la passation des marchés communautaires TG-ANADEB-46347-CS-INDV / FGB proximité RM: Recrutement de cinq (5) Component 3:Capacity Individual prestataires individuels IDA / D1740 building and project Post Consultant Open 5,835.00 0.00 Canceled 2018-07-31 2018-07-08 2018-09-18 2018-10-09 2018-11-13 2019-09-09 chargés de l'animation management Selection communautaire en Formation en Gestion à la Base (FGB) dans la région Maritime TG-ANADEB-74839-CS-INDV / FGB proximité RP: Recrutement de huit (8) Component 3:Capacity Individual prestataires individuels IDA / D1740 building and project Post Consultant Open 9,336.00 0.00 Canceled 2018-07-31 2018-09-18 2018-10-09 2018-11-13 2019-09-09 chargés de l'animation management Selection communautaire en Formation en Gestion à la Base (FGB) dans la région des Plateaux TG-ANADEB-74842-CS-INDV / FGB proximité RC: Recrutement de sept (7) Component 3:Capacity Individual prestataires individuels IDA / D1740 building and project Post Consultant Open 8,170.00 0.00 Canceled 2018-07-31 2018-09-18 2018-10-09 2018-11-13 2019-09-09 chargés de l'animation management Selection communautaire en Formation en Gestion à la Base (FGB) dans la région Centrale TG-ANADEB-74845-CS-INDV / FGB proximité RK: Recrutement de neuf (9) Component 3:Capacity Individual prestataires individuels IDA / D1740 building and project Post Consultant Open 10,500.00 0.00 Canceled 2018-07-31 2018-09-18 2018-10-09 2018-11-13 2019-09-09 chargés de l'animation management Selection communautaire en Formation en Gestion à la Base (FGB) dans la région de la Kara TG-ANADEB-74847-CS-INDV / FGB proximité RS: Recrutement de onze (11) Component 3:Capacity Individual prestataires individuels IDA / D1740 building and project Post Consultant Open 12,840.00 0.00 Canceled 2018-07-31 2018-01-31 2018-09-18 2018-10-09 2018-11-13 2019-09-09 chargés de l'animation management Selection communautaire en Formation en Gestion à la Base (FGB) dans la région des savanes TG-ANADEB-101639-CS- INDV / Géoréférencement: Recrutement d'un consultant Component 3:Capacity Individual pour l'appui à l'ANADEB dans IDA / D1740 building and project Post Consultant Open 25,000.00 0.00 Canceled 2019-04-30 2019-07-13 2019-08-03 2019-09-07 2019-11-06 le géoréférencement des management Selection microprojets sociocommunautaires Page 6 TG-ANADEB-101950-CS- INDV / Formation en Passation des Marchés: Component 3:Capacity Individual Recrutement d'un consultant IDA / D1740 building and project Post Consultant Open 17,000.00 20,277.86 Signed 2019-02-25 2019-03-28 2019-03-31 2019-05-20 2019-04-21 2019-07-08 2019-05-26 2019-07-15 2019-07-25 pour la formation des acteurs management Selection sur la passation des marchés communautaires TG-ANADEB-101952-CS- INDV / Evaluation sociale: Component 3:Capacity Individual Recrutement d'un (01) IDA / D1740 building and project Post Consultant Open 25,000.00 0.00 Under Review 2019-05-02 2019-07-15 2019-08-05 2019-09-09 2019-11-08 Consultant pour l'évaluation management Selection en genre et développement social sur les microprojets TG-ANADEB-101954-CS- INDV / Évaluation mi- Component 3:Capacity Individual parcours: Recrutement d'un IDA / D1740 building and project Post Consultant Open 25,000.00 24,428.28 Completed 2019-02-28 2019-02-08 2019-05-13 2019-04-11 2019-06-03 2019-04-26 2019-07-08 2019-05-07 2019-09-06 2019-06-07 (01) Consultant pour management Selection l'évaluation à mi-parcours du projet TG-ANADEB-107032-CS- INDV / Consultant screening Component 3:Capacity Individual social: Recrutement d'un Under IDA / D1740 building and project Post Consultant Limited 4,500.00 5,495.83 2019-02-15 2019-02-02 2019-03-02 2019-03-02 2019-03-09 2019-03-22 2019-03-21 2019-07-19 consultant en sauvegarde Implementation management Selection sociale pour appui au screening des microprojets TG-ANADEB-107033-CS- INDV / Consultant screening Component 3:Capacity Individual social: Recrutement d'un IDA / D1740 building and project Post Consultant Limited 4,500.00 5,406.68 Signed 2019-02-15 2019-02-02 2019-03-02 2019-03-02 2019-03-09 2019-03-22 2019-03-21 2019-03-25 2019-07-19 consultant en sauvegarde management Selection sociale pour appui au screening des microprojets TG-ANADEB-107034-CS- INDV / Consultant screening Component 3:Capacity Individual environnemental: IDA / D1740 building and project Post Consultant Limited 4,500.00 5,406.68 Signed 2019-02-15 2019-02-02 2019-03-02 2019-03-02 2019-03-09 2019-03-22 2019-03-21 2019-03-25 2019-07-19 Recrutement d'un consultant management Selection en sauvegarde environnemantale pour appui au screening des microprojets TG-ANADEB-107035-CS- INDV / Spécialiste Sauvegarde Component 3:Capacity Individual Sociale: Recrutement d'un IDA / D1740 building and project Post Consultant Open 20,000.00 25,851.36 Signed 2019-03-28 2019-03-27 2019-05-01 2019-09-17 2019-05-15 2019-09-18 2019-06-12 2019-10-03 2020-06-06 Spécialiste en sauvegarde management Selection sociale pour le compte de l'unité de gestion du projet TG-ANADEB-127084-CS- INDV / Filets Sociaux RS: Recrutement d'un(e) Assistant Component 3:Capacity Individual régional en transfert IDA / D1740 building and project Post Consultant Open 14,000.00 1,392.45 Signed 2019-08-20 2019-09-25 2019-09-15 2020-02-11 2019-09-22 2020-02-14 2019-10-02 2020-03-02 2020-09-26 monétaire/ cantines scolaires management Selection pour le compte du projet au profit de l'antenne régionale Maritime de l'ANADEB TG-ANADEB-132921-CS- INDV / Comptable RM: Recrutement d'un Comptable Component 3:Capacity Individual gestionnaire pour le compte IDA / D1740 building and project Post Consultant Open 16,000.00 15,469.15 Signed 2019-09-16 2019-10-01 2019-10-20 2020-02-10 2019-10-27 2020-02-14 2019-11-10 2020-03-02 2020-11-04 du projet au profit de management Selection l'antenne régionale Maritime de l'ANADEB TG-ANADEB-132923-CS- INDV / Audit institutionnel Component 3:Capacity Individual ANADEB: Recrutement d'un IDA / D1740 building and project Post Consultant Open 25,000.00 0.00 Canceled 2019-09-30 2019-11-03 2019-11-24 2019-12-29 2020-02-27 consultant individuel pour management Selection l’audit organisationnel et institutionnel de l’ANADEB TG-ANADEB-123267-CS- CDS / Mission de recours INSEED: Contractualisation avec l'INSEED pour la gestion Component 3:Capacity des recours liés aux listes des IDA / D1740 building and project Post Direct Selection Direct 171,500.00 0.00 Canceled 2019-07-17 2019-07-27 2019-09-30 2020-03-28 ménages bénéficiaires des management transferts monétaires et la sélection de nouveaux ménages bénéficiaires TG-ANADEB-143903-CS- INDV / Consultant social RM: Recrutement d'un consultant social junior pour le suivi de mise en œuvre des mesures Component 3:Capacity Individual de sauvegardes IDA / D1740 building and project Post Consultant Open 10,000.00 6,134.83 Signed 2019-11-15 2020-01-08 2019-12-25 2020-07-21 2020-01-15 2020-07-24 2020-02-19 2020-08-14 2021-02-13 environnementale et sociale management Selection dans le cadre des sous- projets communautaires des projets FSB et EJV dans la région maritime TG-ANADEB-143904-CS- INDV / Consultant social RP: Recrutement d'un consultant social junior pour le suivi de mise en œuvre des mesures Component 3:Capacity Individual de sauvegardes IDA / D1740 building and project Post Consultant Open 10,000.00 6,166.28 Signed 2019-11-15 2020-01-08 2019-12-25 2020-07-21 2020-01-15 2020-07-24 2020-02-19 2020-08-14 2021-02-13 environnementale et sociale management Selection dans le cadre des sous- projets communautaires des projets FSB et EJV dans la région des Plateaux TG-ANADEB-143905-CS- INDV / Consultant social RC: Recrutement d'un consultant social junior pour le suivi de mise en œuvre des mesures Component 3:Capacity Individual de sauvegardes IDA / D1740 building and project Post Consultant Open 10,000.00 6,163.01 Signed 2019-11-15 2020-01-08 2019-12-25 2020-07-21 2020-01-15 2020-07-24 2020-02-19 2020-08-14 2021-02-13 environnementale et sociale management Selection dans le cadre des sous- projets communautaires des projets FSB et EJV dans la région Centrale Page 7 TG-ANADEB-143906-CS- INDV / Consultant social RK: Recrutement d'un consultant social junior pour le suivi de mise en œuvre des mesures Component 3:Capacity Individual de sauvegardes IDA / D1740 building and project Post Consultant Open 10,000.00 6,163.01 Signed 2019-11-15 2020-01-08 2019-12-25 2020-07-21 2020-01-15 2020-07-24 2020-02-19 2020-08-14 2021-02-13 environnementale et sociale management Selection dans le cadre des sous- projets communautaires des projets FSB et EJV dans la région Kara TG-ANADEB-143907-CS- INDV / Consultant social RS: Recrutement d'un consultant social junior pour le suivi de mise en œuvre des mesures Component 3:Capacity Individual de sauvegardes IDA / D1740 building and project Post Consultant Open 10,000.00 6,163.01 Signed 2019-11-15 2020-01-08 2019-12-25 2020-07-21 2020-01-15 2020-08-07 2020-02-19 2020-08-14 2021-02-13 environnementale et sociale management Selection dans le cadre des sous- projets communautaires des projets FSB et EJV dans la région des Savanes TG-ANADEB-150059-CS- INDV / Audit institutionnel ANADEB: Recrutement d'un consultant individuel pour l'audit institutionnel t Component 3:Capacity Individual organisationnel de l'Agence IDA / D1740 building and project Post Consultant Limited 40,000.00 74,345.00 Signed 2020-01-03 2019-12-17 2020-01-18 2020-01-09 2020-02-08 2020-06-09 2020-03-07 2020-08-26 2020-05-06 nationale d'appui au management Selection développement à la base (ANADEB) en charge de la mise en œuvre des projets FSB et EJV TG-ANADEB-101636-CS- INDV / Audit marchés Component 3:Capacity Individual communautaires: IDA / D1740 building and project Post Consultant Open 35,000.00 22,778.29 Signed 2020-04-30 2020-06-23 2020-07-13 2020-11-24 2020-08-03 2021-01-25 2020-09-07 2021-03-11 2020-11-06 Recrutement d'un consultant management Selection pour l'audit des marchés communautaires TG-ANADEB-165419-CS- Component 3:Capacity Individual INDV / Gestionnaire RSU: IDA / D1740 building and project Post Consultant Open 20,000.00 0.00 Canceled 2020-04-30 2020-04-30 2020-06-18 2020-07-02 2020-08-06 2021-08-01 Recrutement d'un management Selection gestionnaire du Registre Social Unifié (RSU) TG-ANADEB-194529-CS- INDV / Collaboration élus locaux ANADEB: Recrutement Component 3:Capacity Individual d'un (01) Consultant pour IDA / D1740 building and project Post Consultant Limited 10,000.00 26,594.34 Signed 2020-09-25 2020-09-30 2020-09-30 2020-10-02 2020-10-15 2020-12-01 2020-11-19 2020-12-18 2020-12-19 l'élaboration de la stratégie de management Selection collaboration entre l'ANADEB et les élus locaux TG-ANADEB-165416-CS- INDV / Audit environnemental et social : Recrutement d'un consultant pour l'Audit Component 3:Capacity Individual Under environnemental et social des IDA / D1740 building and project Post Consultant Open 35,000.00 0.00 2020-11-30 2020-11-24 2021-01-18 2021-02-08 2021-03-15 2021-05-14 Implementation infrastructures management Selection sociocommunautaires réalisées dans le cadre du projet TG-ANADEB-165404-CS- INDV / Audit technique des INFRA: Recrutement d'un Component 3:Capacity Individual consultant pour l'audit Under IDA / D1740 building and project Post Consultant Open 35,000.00 0.00 2020-12-15 2020-10-07 2021-02-02 2021-03-24 2021-02-23 2021-03-30 2021-05-29 technique des ouvrages Implementation management Selection sociocommunauataires réalisés dans le cadre du projet TG-ANADEB-209693-CS- INDV / Financements Component 3:Capacity Individual innovants Cantines: Sélection Under IDA / D1740 building and project Post Consultant Open 42,000.00 0.00 2020-12-31 2020-12-21 2021-02-18 2021-03-11 2021-04-15 2021-07-14 d'un cabinet pour l'étude sur Implementation management Selection les financements innovants des cantines scolaires TG-ANADEB-211871-CS- INDV / PROTECTION SOCIALE: Recrutement d’un consultant Component 3:Capacity Individual Under international pour le IDA / D1740 building and project Post Consultant Limited 60,000.00 0.00 2021-01-15 2021-01-06 2021-01-22 2021-02-03 2021-02-12 2021-03-19 2021-09-15 Implementation développement du management Selection programme de protection sociale du gouvernement TG-ANADEB-224313-CS- INDV / CGES _projet Cohésion sociale :recrutement d'un consultant pour l'élaboration Component 3:Capacity Individual du Cadre de Gestion Under IDA / D1740 building and project Post Consultant Limited 35,000.00 0.00 2021-03-25 2021-06-02 2021-04-01 2021-04-22 2021-05-27 2021-06-26 Environnementale et Sociale Implementation management Selection (CGES) intégrant le Plan de Gestion des Pestes et Pesticides (PGPP) du Projet de cohésion sociale (P175043) TG-ANADEB-224318-CS- INDV / CPR_projet Cohésion sociale: Recrutement d'un consultant pour l'élaboration Component 3:Capacity Individual Under du Cadre de Politique de IDA / D1740 building and project Post Consultant Limited 25,000.00 0.00 2021-03-30 2021-06-02 2021-04-06 2021-04-27 2021-06-01 2021-06-26 Implementation Réinstallation (CPR) du Projet management Selection de cohésion sociale pour les régions défavorisées du Golfe de Guinée (P175043) TG-ANADEB-224319-CS- INDV / PGMO_projet Cohésion sociale: Recrutement d'un consultant pour l'élaboration Component 3:Capacity Individual Under du Plan de Gestion de la Main IDA / D1740 building and project Post Consultant Limited 20,000.00 0.00 2021-03-30 2021-06-02 2021-04-06 2021-04-27 2021-06-01 2021-06-26 Implementation d’œuvre (PGMO) du Projet de management Selection cohésion sociale pour les régions défavorisées du Golfe de Guinée (P175043) Page 8 ANDHRA PRADESH INTEGRATED IRRIGATION AND AGRICULTURE TRANSFORMATION PROJECT Procurement Methods Procurement Approaches and Thresholds (US$ Equivalent) Methods Open international (goods, IT, and non- >3 million consulting services) Open national (goods, IT, and non- >100,000 and up to 3 million consulting services) National request for quotation Up to 100,000 (goods/works) Open international (works) >40 million Open national (works) >100,000 and up to 40 million Direct selection No threshold; For goods/works/non-consulting services: According to paragraphs 6.8–6.10 of the Regulations; For consultants: According to paragraphs 7.13–7.15 of the Regulations Framework Agreements For goods, works, and non-consulting services: According to paragraphs 6.57–6.59 of the Regulations Shortlist of national consultants Up to 800,000 1. Procurement prior-review thresholds based on the Moderate rating. The World Bank requires its prior review of the following types of contract: (a) Works: All contracts more than US$15 million equivalent (b) Goods and IT: All contracts more than US$4 million equivalent (c) Non-consulting services: All contracts more than US$4 million equivalent (d) Consultants: All contracts more than US$2 million equivalent for firms and US$400,000 equivalent for individuals (e) Direct selection: Justification of DS for all contracts more than US$100,000 equivalent 2. National procurement procedure conditions. National competition for the procurement of goods, works, and non-consulting services will be within the thresholds and will comply with the Procurement Provisions of paragraphs 5.3–5.6 of Section V of the Regulations and the following additional provisions: (a) Only the model bidding documents agreed with the World Bank (as amended from time to time) will be used for bidding. (b) At least 30 days before the deadline for submission of bids, invitations to bid will be advertised in at least one widely circulated national daily newspaper, or on a widely-used website or electronic portal with free national and international access inan abridged version of the advertisement published in a widely circulated national daily, giving details of the electronic portal where the full invitation to bid can be downloaded. (c) No preference will be accorded to any bidder for price or for other terms when competing with foreign bidders, state-owned enterprises, small- scale enterprises, or enterprises from a given state. (d) Extension of bid validity will not be allowed for contracts subject to World Bank prior review without prior World Bank concurrence (i) for the first request for an extension longer than four weeks and (ii) for all subsequent requests for extension whatever the length; concurrence will be considered only in cases of force majeure and other circumstances beyond the control of the purchaser employer. (e) There will be no re-bidding of contracts subject to World Bank prior review without prior World Bank concurrence. In this project, bids will not be rejected for being outside a predetermined range of prices. (f) To improve the efficiency and transparency of small-value purchases in WB-financed projects, the Bank has agreed to allow the following uses of Government e-Marketplace (GeM): (i) in lieu of shopping, up to US$30,000 in catalog mode; (ii) in lieu of shopping, up to US$100,000 if there are at least three suppliers for the item on GeM and the purchaser uses the GeM Request for Quotation feature (mini-competition) to discover the final price; (iii) in both cases, borrowers will record their assessment that the price is reasonable, and (iv) GeM is not to be used in lieu of National Competitive Bidding. (g) No negotiations are to be conducted even with the lowest evaluated responsive bidders. Domestic preference. Domestic preference will be applied in evaluating bids in accordance with Annex VI of the Regulations. PROCUREMENT India : AP Integrated Irrigation & Agriculture Transformation Project PLAN General Information Country: India Bank’s Approval Date of the Original Procurement Plan: 2020-09-23 2021-05-25 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P160463 GPN Date: Project Name: AP Integrated Irrigation & Agriculture Transformation Project Loan / Credit No: IBRD / 89100 Irrigation Circle, Ananthapuramu Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned IN-ICANTPAPIIATP-194144- CW-RFB / Rehabilitation of Component A: Improving Under Sreedhargatta MI tank Single Stage - One 2021-07- IBRD / 89100 Irrigated Agriculture Post Request for Bids Open - National 97,853.00 0.00 Implementat 2020-10-12 2020-10-12 2020-10-17 2020-10-20 2020-11-28 2020-11-19 2020-12-28 2021-03-15 2021-02-01 (Independent) in Envelope 31 Efficiency ion Sreedhargatta (V) in Bommanahal (M) in Ananthapuramu District IN-ICANTPAPIIATP-194155- CW-RFB / Rehabilitation of Component A: Improving Apparas Cheruvu Single Stage - One 2021-07- IBRD / 89100 Irrigated Agriculture Post Request for Bids Open - National 304,448.00 0.00 Canceled 2020-10-12 2020-10-12 2020-10-17 2020-11-28 2020-12-28 2021-02-01 (Independent) in Apparas Envelope 31 Efficiency Cheruvu (V) in Bathalapalli (M) in Ananthapuramu District IN-ICANTPAPIIATP-194162- CW-RFB / Rehabilitation of Component A: Improving Under Hariyani cheruvu Single Stage - One 2021-07- IBRD / 89100 Irrigated Agriculture Post Request for Bids Open - National 148,466.00 0.00 Implementat 2020-10-12 2020-10-12 2020-10-17 2020-11-28 2020-11-19 2020-12-28 2021-03-15 2021-02-01 (Independent) in Hariyani Envelope 31 Efficiency ion cheruvu (V) in C.K.Palli (M) in Ananthapuramu District IN-ICANTPAPIIATP-194231- CW-RFB / Rehabilitation of Component A: Improving Under Madigubba MI tank Single Stage - One 2021-07- IBRD / 89100 Irrigated Agriculture Post Request for Bids Open - National 146,166.00 0.00 Implementat 2020-10-12 2020-10-12 2020-10-17 2020-11-28 2020-11-19 2020-12-28 2021-03-15 2021-02-01 (Independent) in Madigubba Envelope 31 Efficiency ion (V) in Atmakur (M) in Ananthapuramu District IN-ICANTPAPIIATP-194267- CW-RFB / Rehabilitation of Component A: Improving Under Gunipalli tank (Independent) Single Stage - One 2021-07- IBRD / 89100 Irrigated Agriculture Post Request for Bids Open - National 128,374.00 0.00 Implementat 2020-10-12 2020-10-12 2020-10-17 2020-11-28 2020-11-19 2020-12-28 2021-03-15 2021-02-01 in Gunipalli (V) in Envelope 31 Efficiency ion Bukkapatnam (M) in Ananthapuramu District IN-ICANTPAPIIATP-194273- CW-RFB / Rehabilitation of Component A: Improving Under Jambuladinne tank Single Stage - One 2021-07- IBRD / 89100 Irrigated Agriculture Post Request for Bids Open - National 192,178.00 0.00 Implementat 2020-10-12 2020-10-12 2020-10-17 2020-11-28 2020-11-19 2020-12-28 2021-03-15 2021-02-01 (Independent) in Envelope 31 Efficiency ion Jambuladinne (V) in Garladinne (M) in Ananthapuramu District IN-ICANTPAPIIATP-194276- CW-RFB / Rehabilitation of Component A: Improving Under Kandukuru chowti tank Single Stage - One 2021-07- IBRD / 89100 Irrigated Agriculture Post Request for Bids Open - National 168,252.00 0.00 Implementat 2020-10-12 2020-10-12 2020-10-17 2020-11-28 2020-11-19 2020-12-28 2021-03-15 2021-02-01 (Independent) in Kandukuru Envelope 31 Efficiency ion (V) in Ananthapuramu(M) & District IN-ICANTPAPIIATP-194277- CW-RFB / Rehabilitation of Component A: Improving Under Single Stage - One 2021-07- Budili MI tank (Independent) IBRD / 89100 Irrigated Agriculture Post Request for Bids Open - National 88,037.00 0.00 Implementat 2020-10-12 2020-10-12 2020-10-17 2020-11-28 2020-11-19 2020-12-28 2021-03-15 2021-02-01 Envelope 31 in Budili (V) in Gorantla (M) Efficiency ion in Ananthapuramu District IN-ICANTPAPIIATP-194280- CW-RFB / Rehabilitation of Component A: Improving Under Single Stage - One 2021-07- Pulakunta tank (Independent) IBRD / 89100 Irrigated Agriculture Post Request for Bids Open - National 89,877.00 0.00 Implementat 2020-10-12 2020-10-12 2020-10-17 2020-11-28 2020-11-19 2020-12-28 2021-03-15 2021-02-01 Envelope 31 in Pulakunta (V) in Hindupur Efficiency ion (M) in Ananthapuramu District IN-ICANTPAPIIATP-194282- CW-RFB / Rehabilitation of Component A: Improving Under Kasaba MI tank( Kodur MI Single Stage - One 2021-07- IBRD / 89100 Irrigated Agriculture Post Request for Bids Open - National 160,276.00 0.00 Implementat 2020-10-12 2020-10-12 2020-10-17 2020-11-28 2020-11-19 2020-12-28 2021-03-15 2021-02-01 tank) (Independent) in Kodur Envelope 31 Efficiency ion (V) in Chilamathur (M) in Ananthapuramu District IN-ICANTPAPIIATP-194287- CW-RFB / Rehabilitation of Budidhagaddapalli tank Component A: Improving Under Single Stage - One 2021-07- (Independent) in IBRD / 89100 Irrigated Agriculture Post Request for Bids Open - National 127,301.00 0.00 Implementat 2020-10-12 2020-10-12 2020-10-17 2020-11-28 2020-11-19 2020-12-28 2021-03-15 2021-02-01 Envelope 31 Budidhagaddapalli (V) in Efficiency ion Gorantla (M) in Ananthapuramu District IN-ICANTPAPIIATP-194290- CW-RFB / Rehabilitation of Component A: Improving Under Gorantla Big tank Single Stage - One 2021-07- IBRD / 89100 Irrigated Agriculture Post Request for Bids Open - National 180,368.00 0.00 Implementat 2020-10-12 2020-10-12 2020-10-17 2020-11-28 2020-11-19 2020-12-28 2021-03-15 2021-02-01 (Independent) in Gorantla (V) Envelope 31 Efficiency ion in Gorantla (M) in Ananthapuramu District IN-ICANTPAPIIATP-194293- CW-RFB / Rehabilitation of Component A: Improving Under Grandham vani cheruvu Single Stage - One 2021-07- IBRD / 89100 Irrigated Agriculture Post Request for Bids Open - National 66,258.00 0.00 Implementat 2020-10-12 2020-10-12 2020-10-17 2020-11-28 2020-11-19 2020-12-28 2021-03-15 2021-02-01 Cascade No.12 in Envelope 31 Efficiency ion Bandameeda palli(V) in Gandlapenta (M) in Ananthapuramu District IN-ICANTPAPIIATP-194335- CW-RFB / Rehabilitation of Component A: Improving Under Nyamaddala MI tank Single Stage - One 2021-07- IBRD / 89100 Irrigated Agriculture Post Request for Bids Open - National 217,638.00 0.00 Implementat 2020-10-12 2020-10-12 2020-10-17 2020-11-28 2020-11-19 2020-12-28 2021-03-15 2021-02-01 (Independent) in Nyamaddala Envelope 31 Efficiency ion (V) in C.K.Palli (M) in Ananthapuramu District Page 1 IN-ICANTPAPIIATP-194345- CW-RFB / Rehabilitation of Component A: Improving Under Single Stage - One 2021-07- Yerra cheruvu (Independent) IBRD / 89100 Irrigated Agriculture Post Request for Bids Open - National 123,160.00 0.00 Implementat 2020-10-12 2020-10-12 2020-10-17 2020-11-28 2020-11-19 2020-12-28 2021-03-15 2021-02-01 Envelope 31 in Kanumukkala (V) in Efficiency ion C.K.Palli (M) in Ananthapuramu District IN-ICANTPAPIIATP-194352- CW-RFB / Rehabilitation of Ammagari Cheruvu Component A: Improving Under Single Stage - One 2021-07- (Independent) in IBRD / 89100 Irrigated Agriculture Post Request for Bids Open - National 112,883.00 0.00 Implementat 2020-10-12 2020-10-12 2020-10-17 2020-11-28 2020-11-19 2020-12-28 2021-03-15 2021-02-01 Envelope 31 Santhekondapuram (V) in Efficiency ion Bramhasamudram (M) in Ananthapuramu District IN-ICANTPAPIIATP-225829- CW-RFB / Rehabilitation of Santhekondapuram MI tank Component A: Improving Pending Single Stage - One 2022-01- Cascade No-32 in IBRD / 89100 Irrigated Agriculture Post Request for Bids Open - National 313,804.00 0.00 Implementat 2021-04-12 2021-04-17 2021-05-29 2021-06-28 2021-08-02 Envelope 29 Santhekondapuram (V) in Efficiency ion Brahmasamudram (M) in Ananthapuramu (dist) IN-ICANTPAPIIATP-225974- CW-RFB / Rehabilitation of Component A: Improving Pending Bachupalli MI tank Cascade Single Stage - One 2022-01- IBRD / 89100 Irrigated Agriculture Post Request for Bids Open - National 328,221.00 0.00 Implementat 2021-04-12 2021-04-17 2021-05-29 2021-06-28 2021-08-02 No-29 in Bachupalli (V) in Envelope 29 Efficiency ion Gooty (M) in Ananthapuramu (dist) IN-ICANTPAPIIATP-225978- CW-RFB / Rehabilitation of Component A: Improving Pending Single Stage - One 2022-01- B.Yaleru MI tank IBRD / 89100 Irrigated Agriculture Post Request for Bids Open - National 618,712.00 0.00 Implementat 2021-04-12 2021-04-17 2021-05-29 2021-06-28 2021-08-02 Envelope 29 (Independent) in B.Yaleru (V) Efficiency ion in Atmakur (M) in Ananthapuramu District IN-ICANTPAPIIATP-225987- CW-RFB / Rehabilitation of Component A: Improving Pending Nidragatta MI tank Single Stage - One 2022-01- IBRD / 89100 Irrigated Agriculture Post Request for Bids Open - National 410,276.00 0.00 Implementat 2021-04-12 2021-04-17 2021-05-29 2021-06-28 2021-08-02 (Independent) in Nidragatta Envelope 29 Efficiency ion (V) in Amarapuram (M) in Ananthapuramu District IN-ICANTPAPIIATP-236484- National CW-RFB / Rehabilitation of Component A: Improving Procurement Pending Apparas Cheruvu Single Stage - One 2022-09- IBRD / 89100 Irrigated Agriculture Post Request for Bids Open - National Document - 1 304,448.00 0.00 Implementat 2021-06-07 2021-06-12 2021-07-24 2021-08-23 2021-09-27 (Independent) in Apparas Envelope 26 Efficiency Envelope process ion Cheruvu (V) in Bathalapalli (Non Bank-SPD) (M) in Ananthapuramu District GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 2 RÉPUBLIQUE GABONAISE (Union-Travail-Justice) MINISTÈRE DE L’ÉCONOMIE ET DES FINANCES COMMISSION NATIONALE DES TIPPEE SECRETARIAT PERMANENT PROJET DE PREPARATION STRATEGIQUE ET DE RIPOSTE AU COVID-19 Financement : BIRD | ID : P173927 PLAN DE PASSATION DE MARCHÉS (Texte) Information sur le Projet : P173927 - Projet de Préparation et de riposte Stratégiques au COVID-19 (PPRS) du Gabon Agence d’exécution du Projet : Commission Nationale des Travaux d’Intérêt Public pour la Promotion de l’Entreprenariat et l’Emploi (CNTIPPEE) Date du plan de passation des marchés : 07 mai 2020 Période couverte par ce plan de passation des marchés : mai 2020 à avril 2021 Préambule Conformément au paragraphe 5.9 du “Règlement de Passation des Marchés pour les Emprunteurs sollicitant le Financement de Projets d’Investissement (FPI)” (Juillet 2016) révisé en Novembre 2017 puis en Août 2018 (“Règlement de Passation des Marchés”) le Système électronique de la Banque de suivi systématique des transactions de marchés publics (STEP) sera utilisé pour préparer, valider et actualiser les plans de passation des marchés et effectuer toutes les transactions liées à la passation des marchés du projet. Ce texte ainsi que les tableaux du plan de passation des marchés présents dans STEP constituent le plan de passation des marchés du projet. Les conditions suivantes s'appliquent à toutes les activités de passation de marchés du plan de passation de marchés. Les autres éléments du plan de passation des marchés tels que requis au paragraphe 4.4 du Règlement de passation des marchés sont énoncés dans STEP. Les Dossiers types de passation des marchés publics de la Banque devront être utilisés pour tous les contrats soumis à la concurrence internationale, ainsi que pour tous les autres contrats soumis à cette obligation telle que spécifiée dans les tableaux du plan de passation des marchés de STEP. Procédures nationales de passation des marchés : En accord avec le paragraphe 5.3 du Règlement de passation des marchés, dans le cas où la procédure de passation des marché se fera au niveau national (telle que spécifiée dans les tableaux du plan de passation des marchés inclus de STEP), les procédures nationales de passation des marchés du pays considéré pourront être utilisées. Si l’Emprunteur utilise ses propres procédures d’appel d’offres national ouvert telles qu’énoncées dans le Code des Marchés Publics, Décret n°00027/PR/MEPPDD du 17 janvier 2018, ces arrangements sont soumis aux dispositions du paragraphe 5.4 du Règlement de passation des marchés et aux conditions suivantes : a. publication de l'appel d’offres/à propositions au niveau national ; b. les entreprises éligibles de tout pays peuvent concourir ; c. le dossier d'appel d'offres/à propositions oblige le Soumissionnaire/Proposant présentant une Offre/Proposition à déposer un agrément signé qui sera joint à tout contrat éventuel, pour confirmer qu'il applique et respecte les Directives de la Banque pour la lutte contre la corruption y compris sans limitation. Le droit de la Banque de sanctionner et les droits de la Banque pour l'inspection et l'audit ; d. les marchés doivent comporter une répartition appropriée des attributions, risques et responsabilités ; e. la publication des informations relatives à l'attribution du marché ; f.les droits de la Banque d’examiner le dossier et les activités de passation des marchés ; g. l'existence d'un mécanisme efficace d'examen des plaintes ; et h. la gestion et l'archivage des dossiers relatifs au Processus de la Passation des Marchés. Lorsque l’Emprunteur utilise d’autres procédures que l’appel d’offres national ouvert, ces procédures devront être en accord avec les dispositions du paragraphe 5.5 du Règlement de passation des marchés. Crédit-bail tel que spécifié au paragraphe 5.10 du Règlement de Passation des marchés : Le crédit-bail peut être utilisé pour les contrats indiqués comme tel dans le Plan de passation des marchés. Sans objet. Achat de biens d’occasion tel que spécifié au paragraphe 5.11 du Règlement de Passation des Marchés est autorisé pour les contrats indiqués comme tel dans le Plan de passation des marchés. Sans objet. Préférence nationale telle que spécifiée au paragraphe 5.51 du Règlement de Passation des Marchés (Fournitures et Travaux). Fournitures : ne s’applique pas/s’applique pour les contrats indiqués dans les tableaux du Plan de passation des marchés. Travaux ne s’applique pas/s’applique pour les contrats indiqués dans les tableaux du Plan de passation des marchés. L’Assistance directe à la mise en œuvre (sigle HEIS en anglais) tel que précisée aux paragraphes 3.10 et 3.11 du Règlement de Passation des marchés s’applique : 3.10La Banque peut accepter d'apporter une assistance directe à la mise œuvre des activités de passation des marchés lorsqu'elle juge que ('Emprunteur/le bénéficiaire ou, le cas échéant, le pays membre : a. est dans un besoin urgent d'assistance en raison d'une catastrophe d'origine naturelle ou humaine, ou d'un conflit ; ou b. se heurte à des problèmes de capacités du fait de sa fragilité ou de vulnérabilités particulières (petits Etats, par exemple). 3.11La Banque détermine, au cas par cas, le champ et la nature de cet appui. Celui-ci ne l'amène pas à exécuter les opérations de passation des marchés en lieu et place de l'Emprunteur, qui reste responsable de l'exécution du projet. Autres informations pertinentes sur la passation des marchés : Sans objet. Approche du Montant % Date de Catégorie marché/ estimé financ démarrage Numéro Compétition Méthode de Type de prévue de é par Description de passation de (Dollars revue passation la Référence marché US) (jj/mm/aaaa) de marché Banqu e Fournitures GA-CN TIPPEE-169285-GO-UN / Acquisition équipement de protection, test/équipement de laboratoire, Go-Ref 1 GO Direct UN 6 300 000,00 100 Post 2020/05/25 ambulances médicalisées, formation personnel de santé – réponse au COVID19 GA-CN TIPPEE-172487-GO-DIR / Fourniture d’internet et téléphonie Go-Ref 2 GO Direct DIR 10 000,00 100 Post 2020/06/20 mobile Services de consultants GA-CN TIPPEE-172488-CS-QCBS / Open - Auditeur comptable et financier CS-Ref 1 CS QCBS 60 000,00 100 Post 2020/12/23 International 2020,2021 et clôture GA-CN TIPPEE-172490-CS-CDS / Audit CS-Ref 2 CS Direct CDS 130 000,00 100 Post 2020/07/20 global réponse au COVID19 CS-Ref 3 CS Non-consulting Services GA-CN TIPPEE-172653-NC-RFQ / NC-Ref 3 NC CF RFQ 50 000,00 Post 2020/06/27 Logistique, transporteur et dispatching PROCUREMENT Gabon : GABON COVID-19 Strategic Preparedness and Response Project (SPRP) PLAN General Information Country: Gabon Bank’s Approval Date of the Original Procurement Plan: 2020-05-07 2021-06-03 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P173927 GPN Date: Project Name: GABON COVID-19 Strategic Preparedness and Response Project (SPRP) Loan / Credit No: IBRD / 91240 COMMISSION NATIONALE DES TIPPEE Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GA-CN TIPPEE-169285-GO- UN / Acquisition équipement de protection, test/équipement de Component 1: Emergency UN Agencies IBRD / 91240 Post Direct 6,300,000.00 6,240,052.49 Signed 2020-05-08 2020-05-17 2020-05-13 2020-05-22 2020-05-25 2020-05-25 2020-11-21 laboratoire, ambulances COVID-19 Response (Direct) médicalisées, formation personnel de santé – réponse au COVID19 GA-CN TIPPEE-172487-GO- Component 3: Project Under DIR / Fourniture d’internet et IBRD / 91240 Implementation and Post Direct Selection Direct 10,000.00 0.00 Implementati 2020-11-02 2020-11-03 2020-11-07 2020-12-12 2021-06-10 téléphonie mobile Monitoring on GA-CN TIPPEE-195897-GO- Component 2: Supporting Request for Single Stage - One RFQ / Acquisition de IBRD / 91240 National and Sub-national, Post Limited 410,000.00 355,982.96 Signed 2020-09-25 2020-09-25 2020-10-09 2020-10-15 2021-04-07 Quotations Envelope consommables médicaux Prevention and Preparedness GA-CN TIPPEE-195892-GO- Component 2: Supporting RFQ / Acquisition de Request for Single Stage - One IBRD / 91240 National and Sub-national, Post Limited 1,000,000.00 1,430,295.74 Signed 2020-09-26 2020-09-25 2020-10-17 2020-10-15 2021-04-15 médicaments et autres Quotations Envelope Prevention and Preparedness produits de santé GA-CN TIPPEE-195903-GO- Component 3: Project RFQ / Acquisition Matériel Request for Single Stage - One IBRD / 91240 Implementation and Post Limited 17,000.00 47,112.35 Signed 2020-09-30 2020-11-02 2020-10-12 2020-11-11 2020-12-11 Informatique pour la Cellule Quotations Envelope Monitoring FINEX GA-CN TIPPEE-195905-GO- RFQ / Acquisition de quatre Component 3: Project Request for Single Stage - One (4) Véhicules pour les activités IBRD / 91240 Implementation and Post Limited 150,000.00 0.00 Canceled 2020-09-25 2020-10-15 2020-12-14 Quotations Envelope de la Cellule de Suivi Monitoring Evaluation du COPIL GA-CN TIPPEE-195902-GO- Component 3: Project RFQ / Acquisition Matériel Request for Single Stage - One IBRD / 91240 Implementation and Post Limited 26,000.00 118,965.89 Signed 2020-11-08 2020-12-09 2020-11-28 2021-03-25 2021-01-27 Informatique pour la Cellule Quotations Envelope Monitoring de Suivi Evaluation du COPIL GA-CN TIPPEE-201737-GO- Component 3: Project Under DIR / Fourniture de carburant IBRD / 91240 Implementation and Post Direct Selection Direct 11,000.00 0.00 Implementati 2020-11-02 2020-11-03 2020-11-04 2020-11-12 2021-05-11 à l'UCP Monitoring on GA-CN TIPPEE-201726-GO- DIR / Acquisition de six (6) Component 3: Project Véhicules pour les activités de IBRD / 91240 Implementation and Post Direct Selection Direct 166,000.00 269,845.50 Completed 2020-11-05 2020-11-03 2020-11-07 2020-11-09 2020-11-10 2020-11-11 2021-01-09 2021-01-08 la Cellule de Suivi Evaluation Monitoring du COPIL et la Cellule FINEX GA-CN TIPPEE-238804-GO- Component 3: Project Pending DIR / Fourniture du carburant IBRD / 91240 Implementation and Post Direct Selection Direct 5,600.00 0.00 Implementati 2021-06-08 2021-06-09 2021-06-11 2021-12-08 à la Cellule Finex Monitoring on GA-CN TIPPEE-238917-GO- Component 3: Project Pending RFQ / Fourniture des outils de Request for Single Stage - One IBRD / 91240 Implementation and Post Limited 10,000.00 0.00 Implementati 2021-06-23 2021-07-14 2021-07-23 communication pour le PPRS Quotations Envelope Monitoring on COVID-19 NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GA-CN TIPPEE-172653-NC- Pending Component 1: Emergency Request for Single Stage - One RFQ / Logistique, transporteur IBRD / 91240 Post Limited 50,000.00 0.00 Implementati 2020-12-03 2021-01-03 2021-07-02 COVID-19 Response Quotations Envelope et dispatching on CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GA-CN TIPPEE-172488-CS- Component 3: Project Quality And Cost- Under QCBS / Auditeur comptable et IBRD / 91240 Implementation and Post Open - National 60,000.00 0.00 2020-11-10 2021-04-10 2020-11-17 2020-12-08 2021-01-07 2021-01-14 2021-01-28 2021-02-09 2022-02-09 Based Selection Implementation financier 2020,2021 et clôture Monitoring GA-CN TIPPEE-183997-CS- Component 3: Project Quality And Cost- Pending QCBS / Audit global réponse IBRD / 91240 Implementation and Post Open - National 130,000.00 0.00 2021-08-02 2021-08-09 2021-09-22 2021-10-22 2021-10-29 2021-11-12 2021-11-24 2022-03-24 Based Selection Implementation au COVID19 Monitoring Page 1 INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GA-CN TIPPEE-183699-CS- INDV / Recrutement d’un Component 3: Project Individual Consultant Individuel pour IBRD / 91240 Implementation and Post Consultant Limited 85,000.00 48,528.74 Signed 2020-07-15 2020-07-13 2020-07-18 2020-07-15 2020-07-22 2020-08-19 2020-07-26 2020-08-20 2020-09-24 l’élaboration d’un Cadre de Monitoring Selection Gestion environnementale et Sociale GA-CN TIPPEE-195898-CS- Component 3: Project Individual INDV / Recrutement d’un IBRD / 91240 Implementation and Post Consultant Open 32,000.00 0.00 Canceled 2020-11-21 2020-12-17 2020-12-19 2020-12-22 2021-12-17 Comptable pour le projet Monitoring Selection COVID-19 GA-CN TIPPEE-195900-CS- INDV / Recrutemnt d’un Component 3: Project Individual Expert pour le suivi IBRD / 91240 Implementation and Post Consultant Limited 26,000.00 22,257.24 Signed 2020-11-24 2021-01-14 2020-12-01 2021-02-04 2020-12-06 2021-05-10 2020-12-09 2021-05-10 2021-06-07 épidémiologique pour la Monitoring Selection Risposte au COVID-19 GA-CN TIPPEE-222184-CS- Component 3: Project CDS / Recrutement d’une Pending IBRD / 91240 Implementation and Post Direct Selection Direct 30,000.00 0.00 2021-12-01 2021-12-04 2021-12-07 2022-06-05 Assistante de Direction pour Implementation Monitoring le projet COVID-19 GA-CN TIPPEE-238900-CS- Component 3: Project Individual INDV / Recrutement d’un Pending IBRD / 91240 Implementation and Post Consultant Limited 35,000.00 0.00 2021-06-09 2021-06-10 2021-06-11 2021-06-13 2021-08-12 Auditeur Environnemental et Implementation Monitoring Selection Social GA-CN TIPPEE-238904-CS- Component 3: Project Individual INDV / Recrutement d’un Pending IBRD / 91240 Implementation and Post Consultant Limited 30,000.00 0.00 2021-06-10 2021-06-12 2021-06-14 2021-06-18 2021-12-15 spécialiste environnemental Implementation Monitoring Selection pour le projet GA-CN TIPPEE-238906-CS- INDV / Recrutement d’un consultant Spécialiste en Component 3: Project Individual Élaboration de la Stratégie de Pending IBRD / 91240 Implementation and Post Consultant Direct 25,000.00 0.00 2021-06-09 2021-06-11 2021-06-12 2021-06-14 2021-09-12 Passation de Marchés pour Implementation Monitoring Selection promouvoir le Développement (PPSD) pour le projet PPRS - P173927 GA-CN TIPPEE-238915-CS- Component 3: Project Individual INDV / Recrutement d’un Pending IBRD / 91240 Implementation and Post Consultant Open 65,000.00 0.00 2021-06-10 2021-06-17 2021-06-19 2021-06-21 2022-05-27 Auditeur Interne pour les Implementation Monitoring Selection projets de la CN-TIPPEE Page 2 Lao PDR: Agriculture Competitiveness Project Procurement Plan (as of December 21, 2017) 1. Project information: Country: Lao PDR Borrower/Recipient: Lao PDR Project Name: Agriculture Competitiveness Project Project ID No: P161473 Project Implementing Agency: Ministry of Agriculture and Forestry (MAF) 2. Bank’s approval date of the Procurement Plan • Original Plan: December 21, 2017 • First Revision: 3. Date of General Procurement Notice: 4. Period covered by this procurement plan: at least 18 months I. Works and Goods and Non-Consultant Services 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Annex II of the Procurement Regulations: Procurement Method Prior Review Thresholds Thresholds Applicable Category Applicable thresholds Remarks thresholds Remarks (in US$ (in US$) equivalent) Works RFB through ≥ 2.0 million – Above US$ 10 This has not been Open million foreseen at the International project preparation market approach stage. RFB through ≥ 200,000 < – None - Open National 2.0 million market approach Request for < 200,000 – None – Quotation Direct Selection None No threshold; Same as for This has not been meet competitive foreseen at the requirements of selection project preparation regulations 7.13- stage. 7.15 Goods and Non-Consulting Services RFB through ≥ 0.6 million – Above US$ 2 This has not been Open million foreseen at the International project preparation market approach stage. RFB through ≥ 100,000 < - None Risk-based approach Open National 0.6 million market approach Request for < 100,000 None Quotation 1 Direct Selection None No threshold; Same as for This has not been meet competitive foreseen at the requirements of selection project preparation regulations 7.13- stage. 7.15 2. Prequalification. Not expected for the works/goods packages. 3. Any Other Special Procurement Arrangements: National procurement procedures as specified under paragraph 5.4 of the Procurement Regulations and the conditions specified in Annex 1 to this Procurement Plan 4. Leased assets as specified under paragraph 5.10 of the Procurement Regulations: Not applicable. 5. Procurement of second hand Goods as specified under paragraph 5.11 of the Procurement Regulations: Not applicable. 6. Hands-on Expanded Implementation Support (HEIS) as specified under paragraph 3.10 and 3.11 of the Procurement Regulations: Not applicable. 7. Procurement packages for Goods (prior and post reviews) with method and Time Schedule Revi Expect Contract Procurement ew ed Estima Bids by Ref. (Description) ted Method Openi Commen Bank No. Cost ng ts (US$) (Prio r/ Date Post) Khammouane Upgrade of infrastructure KM/W- Request for Execute for KM PAFO for seed, GAP 30,000 Post Sep-18 RFQ 01 Quotation by PAFO and general extension Upgrade of infrastructure KM/W- Request for Sep Execute for KM DAFOs for seed 30,000 Post RFQ 02 Quotation 20118 by PAFO and GAP Upgrade of critical RFB (National) / KM/W- Execute productive infrastructure 900,000 Request for Post Jun-19 RFB 01 by PAFO in KM (multiple contracts) Quotation Equipment for KM Execute KM/G- Request for PAFO/DAFO for seed and 21,000 Post Dec-18 by RFQ 01 Quotation GAP PAFO/MAF Bolikhamxay Upgrade of infrastructure BLK/W- Request for Sep Execute for BLK for seed, GAP and 30,000 Post RFQ 01 Quotation 20117 by PAFO general extension Upgrade of infrastructure BLK/W- Request for Execute for BLK DAFOs for seed 30,000 Post Sep-18 RFQ 02 Quotation by PAFO and GAP Upgrade of critical RFB (National) / BLK/W- productive infrastructure Sep Execute 900,000 Request for Post RFB 01 in BLK (multiple 20118 by PAFO Quotation contracts) Equipment for BLK Execute BLK/G- Request for PAFO/DAFO for seed and 21,000 Post Dec-18 by RFQ 01 Quotation GAP PAFO/MAF 2 Revi Expect Contract Procurement ew ed Vientiane Capital Estima Ref. ted Commen Upgrade of infrastructure VC/W- No. Cost Request for Execute ts for VC for seed, GAP and 30,000 Post Sep-18 RFQ 01 (US$) Quotation by PAFO general extension Upgrade of infrastructure VC/W- Request for Sep Execute for VC DAFOs for seed 40,000 Post RFQ 02 Quotation 20118 by PAFO and GAP Upgrade of critical RFB (National) / VC/W- Execute productive infrastructure 900,000 Request for Post Sep-18 RFB 01 by PAFO in VC (multiple contracts) Quotation Equipment for VC Execute VC/G- Request for PAFO/DAFO for seed and 23,000 Post Dec-18 by RFQ 01 Quotation GAP PAFO/MAF Vientiane Province Upgrade of infrastructure VP/W- Request for Execute for VP PAFO for seed, GAP 30,000 Post Sep-18 RFQ 01 Quotation by PAFO and general extension Upgrade of infrastructure VP/W- Request for Execute for VP DAFOs for seed and 20,000 Post Sep-18 RFQ 02 Quotation by PAFO GAP Upgrade of critical RFB (National) / VP/W- 1,000,0 Execute productive infrastructure Request for Post Sep-18 RFB 01 00 by PAFO in VP (multiple contracts) Quotation Equipment for VP Execute VP/G- Request for PAFO/DAFO for seed and 21,000 Post Dec-18 by RFQ 01 Quotation GAP PAFO/MAF Xayabouly Upgrade of infrastructure XYL/W- for XYL PAFO for seed, Request for Execute 30,000 Post Sep-18 RFQ 01 GAP and general Quotation by PAFO extension Upgrade of infrastructure XYL/W- Request for Sep Execute for XYL DAFOs for seed 40,000 Post RFQ 02 Quotation 20118 by PAFO and GAP Upgrade of critical RFB (National) / XYL/W- Execute productive infrastructure 900,000 Request for Post Sep-18 RFB 01 by PAFO in VP (multiple contracts) Quotation Equipment for XYL Execute XYL/G- Request for PAFO/DAFO for seed and 23,000 Post Dec-18 by RFQ 01 Quotation GAP PAFO/MAF MAF Execute MAF/W Request for by -RFQ Seed storage at NAFRI 70,000 Post Sep-18 Quotation NAFRI/MA 01 F Execute MAF/G- Machine and equipment Request for by 20,000 Post Sep-18 RFQ 01 for NAFRI-ARC Quotation NAFRI/MA F MAF/G- Machine and equipment Request for Execute 25,000 Post Sep-18 RFQ 02 for NAFRI- HRC Quotation by MAF MAF/G- Request for Execute Lab equipment for DOA 20,000 Post Dec-18 RFQ 03 Quotation by MAF MAF/G- Equipment for DOA Clean Request for Execute 20,000 Post Dec-18 RFQ 04 Agriculture Dev. Center Quotation by MAF MAF/G- Extension materials for Request for Execute 10,000 Post Sep-18 RFQ 05 DOA Quotation by MAF 3 Revi Expect Contract Procurement ew ed MAF/G- Extension materials for Estima Request for Execute 50,000 Post Sep-18 Ref. RFQ 06 DAEC ted Quotation Commen by MAF No. Rapid test kits and Cost ts MAF/G- (US$) Request for Execute chemicals and reagents 9,000 Post Sep-18 RFQ 07 Quotation by MAF for DOA Office equipment for MAF, MAF/G- Request for Execute MOIC, 5 provinces and 133,200 Post Sep-18 RFQ 08 Quotation by MAF districts MAF/G- Motorbikes for Provinces, Request for Execute 84,000 Post Sep-18 RFQ 09 MAF and MOIC (42 units) Quotation by MAF MAF/G- Pick-up for 5 provinces, Execute 630,000 RFB (National) Post Sep-18 RFB 01 MAF and MOIC (14 units) by MAF 6,090, Total Works and Goods 200 4 III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Annex II of the Procurement Regulations: Procurement Method Prior Review Thresholds Thresholds Applicable Applicable Category thresholds thresholds Remarks Remarks (in US$ (in US$, equivalent) millions) QCBS, QBS, FBS, ≥ 300,000 Shortlist of only ≥ 1.0 million Risk-based LCS (Using the National Consultants approach most appropriate (Firms) for contract market agreed in the PP approach) CQS (Open or < 300,000 QCBS, QBS, FBS, None limited LCS) can be applied competition for contracts with through national value under or international $300,000 market approach, specified in the PP and agreed with the Bank. Direct Selection None No threshold; meet Same as for This has not been of firms requirements of competitive foreseen at the regulations 7.13- selection project preparation 7.15 stage. Individual N/A depending Essential individual ≥ 300,000 and Risk-based Consultants on nature of assignments will be for the positions approach services defined in the as specified in Procurement Plan the PP agreed agreed with the with the Bank Bank and in line with regulations 7.34- 7.39 using the most appropriate market approach 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than US$ 200,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 7.1, Section VII of the Procurement Regulations. 5 3. Consultancy Assignments with Selection Methods and Time Schedule Estimat Selecti Revi Expecte ed on ew d Proposa Metho by ls Description of Cost Ref. No. d Bank Submiss Comments Assignment ion (Prio US$ r/ Date Post) Khammouane Technical consultant for Execute by KM/IC-01 KM PAFO in extension 120,000 IC Post Jun-18 MAF services Technical assistance for Execute by KM/IC-02 FOs on Productive 50,000 IC Post Jul-18 MAF partnerships (PPs) in KM Technical assistance to Execute by KM/IC-03 120,000 IC Post Jul-18 KM PICO MAF Project accountant for KM Execute by KM/IC-04 66,000 IC Post Mar-18 PAFO MAF Bolikhamxay Technical consultant for Execute by BLK/IC-01 BLK PAFO in extension 120,000 IC Post Jun-18 MAF services Technical assistance for Execute by BLK/IC-02 FOs on Productive 50,000 IC Post Jul-18 MAF partnerships (PPs) in BLK Technical assistance to Execute by BLK/IC-03 120,000 IC Post Jul-18 BLK PICO MAF Project accountant for BLK Execute by BLK/IC-04 66,000 IC Post Mar-18 PAFO MAF Vientiane Capital Technical consultant for Execute by VC/IC 01 VC PAFO in extension 120,000 IC Post Jun-18 MAF services Technical assistance for Execute by VC/IC-02 FOs on Productive 50,000 IC Post Jul-18 MAF partnerships (PPs) in VC Technical assistance to VC Execute by VC/IC-03 120,000 IC Post Jul-18 PICO MAF Project accountant for VC Execute by VC/IC-04 66,000 IC Post Mar-18 PAFO MAF Vientiane Province Technical consultant for Execute by VP/IC-01 VP PAFO in extension 120,000 IC Post Jun-18 MAF services Technical assistance for Execute by VP/IC-02 FOs on Productive 50,000 IC Post Jul-18 MAF partnerships (PPs) in VP Technical assistance to VP Execute by VP/IC-03 120,000 IC Post Jul-18 PICO MAF Project accountant for VP Execute by VP/IC-04 66,000 IC Post Mar-18 PAFO MAF Xayabouly 6 Estimat Selecti Revi Expecte ed on ew d Technical consultant for XYL /IC- Execute by XBL PAFO in extension 120,000 IC Post Jun-18 01 Description of MAF Ref. No. services Comments Assignment Technical assistance for Execute by XYL/IC-02 FOs on Productive 50,000 IC Post Jul-18 MAF partnerships (PPs) in XYL Technical assistance to Execute by XYL/IC-03 120,000 IC Post Jul-18 XYL PICO MAF Project accountant for XYL Execute by XYL/IC-04 66,000 IC Post Mar-18 PAFO MAF MAF SSS/QB S TA for AB Matching Grants (Qualit MAF/QBS- Management and Execute by 600,000 y Post Sep-18 01 Capacity Building for rice MAF Based mills Selecti on) SSS MAF/SSS- Technical assistance to Execute by 770,000 (with Post Sep-18 01 support implementation (1) MAF FAO) Completed MAF/SSS- Environment safeguard (Keoduangc 84,000 SSS Post Aug-17 hay 02 specialist (DoPF) Keokhamph ui) Completed MAF/SSS- Social safeguard specialist 84,000 SSS Post Aug-17 (Bounhome 03 (DoPF) Phothimath) MAF/SSS- Monitoring and evaluation Execute by 132,000 SSS Post Jul-18 04 specialist (DoPF) MAF Completed MAF/SSS- Finance management 132,000 SSS Post Aug-17 (Khayta 05 specialist* (DoPF) Sithivong) Completed MAF/SSS- Procurement specialist (Keophouth 120,000 SSS Post Aug-17 06 (DoPF) one Inthivong) Local Consultant on MAF/IC- Execute by Survey-Design of 144,000 IC Post Jun-18 01 MAF irrigation system (DOI) Local Consultant on MAF/IC- Execute by strengthening of WUA and 180,000 IC Post Jun-18 02 MAF O&M (DOI) Study on integrated MAF/IC- farming Execute by 30,000 IC Post Jul-18 03 systems/diversification for MAF nutrition MAF/IC- National Project Advisor Execute by 198,000 IC post Mar-18 04 (DoPF) MAF International Project MAF/IC- Execute by Advisor (Project 225,000 IC post Mar-18 05 MAF management DoPF) MAF/IC- Execute by Accountant – chief 132,000 IC Post Mar-18 06 MAF MAF/IC- Execute by Accountant- assistant 66,000 IC Post Mar-18 07 MAF 7 Estimat Selecti Revi Expecte ed on ew d MAF/IC- Execute by Accountant- assistant 66,000 IC Post Mar-18 08 MAF Description of Ref. No. MAF/IC- Comments Execute by Assignment Cashier – assistant 66,000 IC Post Mar-18 09 MAF MAF/IC- Administrative staff – Execute by 66,000 IC Post Mar-18 10 assistant MAF MAF/IC- Execute by Procurement assistant 66,000 IC Post Mar-18 11 MAF MAF/IC- Project Advisor (part time) Execute by 72,000 IC Post Jul-18 12 for MOIC DOPC MAF MAF/IC- Administrative staff for Execute by 46,000 IC Post Jul-18 13 MOIC DOPC MAF Nutrition social behavior MAF/CQS- Execute by change communication 400,000 CQS Prior Jul-18 01 MAF (SBBC) MAF/CQS- Panel of Expert – Dam Execute by 100,000 CQS Post Jul-18 02 Safety MAF MAF/CQS- TA firm for baseline, mid- Execute by 180,000 CQS Post Mar-18 03 term and final assessment MAF MAF/CQS- Execute by DOPF - Project Audits* 180,000 CQS Post Dec-18 04 MAF 5,919,0 Total consulting services 00 Total Works, Goods and 12,009, Consulting Services 200 1 Consultants under FAO SSS package: Estimated Position Cost (USD) FAO-Int 01 Int. Policy on seed management (MAF DoPF) 15,000 FAO-Int 02 Int. Nutrition Specialist (MAF DoPF) 45,000 FAO-Int 03 Int. Crop/GAP Specialist (MAF DoPF) 45,000 FAO-Int 04 Int. Institutional Specialist (MAF DoPF) 45,000 FAO-Int 05 Int. consultant to develop MIS system (MoIC) 60,000 FAO-Int 06 Int. consultant on rice mill standard promotion policy (MoIC) 45,000 Int. consultant to review and develop rice export strategy FAO-Int 07 45,000 (MoIC) FAO-Int 08 Int. TA for Preparing for GMP and HACCP certification (MoIC) 15,000 FAO-Int 09 Int. consultant to develop guidelines on Quality Mark (MoIC) 45,000 Subtotal International Consultants 360,000 FAO-Nat DOA - Technical Consultant for certification of organic 108,000 01 production and GAP (MAF) FAO-Nat DAEC - Technical Consultant on seed certification for R3 (MAF) 108,000 02 FAO-Nat DALAM -Technical Consultant on organic fertilization (MAF) 108,000 03 FAO-Nat Develop a system for M&E and reporting on SPS (MAF) 10,000 04 FAO-Nat Improve the system of plant quarantine inspection (MAF) 12,000 05 FAO-Nat DIMEX- National consultant on Rice import and export 24,000 06 legislations (MOIC) FAO-Nat DOSMEP - National consultant on GMP, HACCP (MOIC) 30,000 07 8 FAO-Nat DOTP - Promotion of Quality Mark (MOIC) 10,000 08 Subtotal National Consultants 410,000 GRAND TOTAL 770,000 * Although these packages are subject to procurement Post Review, the World Bank will do prior technical review or the EOI evaluation reports and draft negotiated contracts. 9 Annex 1 - Additional National Procurement Provisions. Procurement under National Procurement Procedures will be carried out in accordance with national regulations including the Procurement Decree #03, dated January 9, 2004 and Implementation Rule and Regulations (IRR) #0063 issued by MOF on March 12, 2004 and #0861/MOF, dated May 5, 2009 (amended version); Procurement Manual dated May 2009 and harmonized bidding documents for national competitive bidding and request for quotations agreed between Government of Lao PDR, World Bank and Asia Development Bank. In addition to the provisions stipulated in the above documents, Government and Implementing agencies for Bank financed projects shall implement the following additional provisions: i. The request for bids/request for proposals document shall require that bidders/proposers submitting bids/proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, Bank Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights; ii. Information related to award of contract including reasons for rejection of unsuccessful bidders shall be published on the implementing agency websites and/or newspaper of wide circulation. iii. All complaints on procurement related matters including complaints arising from procurement under Bank financed Projects whilst using National Procurement Procedures shall be dealt with in accordance with Article 33 of the Procurement Decree. Borrower shall put in place an effective complaints review mechanism for dealing with procurement related complaints, and shall disclose the details in all the bidding documents. All complaints shall be recorded by the Borrower in the appropriate tracking and monitoring system, as agreed between the Bank and the Borrower. 10 PROCUREMENT Lao People's Democratic Republic : Agriculture Competitiveness Project PLAN General Information Country: Lao People's Democratic Republic Bank’s Approval Date of the Original Procurement Plan: 2017-07-20 2021-05-21 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P161473 GPN Date: 2018-10-17 Project Name: Agriculture Competitiveness Project Loan / Credit No: IDA / V0940, IDA / 62050 D Executing Agency(ies): epartment of Planning and Cooperation, Ministry of Agriculture and Forestry WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned MAF/W-RFQ02 / Office Request for Single Stage - One 2019-03- Renovation and Extension of IDA / 62050 C. Project Management Post Limited 22,000.00 21,484.34 Signed 2018-08-04 2018-07-30 2018-09-29 2018-09-24 Quotations Envelope 28 CPMO KM/W- RFQ 01 / Upgrade of infrastructure for KM PAFO for A. Improved Agricultural Request for Single Stage - One 2019-08- IDA / 62050 Post Limited 30,000.00 29,862.49 Signed 2018-12-08 2018-11-13 2019-02-02 2018-12-11 seed, GAP and general Efficiency and Sustainability Quotations Envelope 01 extension KM/W-RFQ 02 / Upgrade of A. Improved Agricultural Request for Single Stage - One 2019-08- infrastructure for KM DAFOs IDA / 62050 Post Limited 30,000.00 29,944.02 Signed 2018-12-08 2018-12-04 2019-02-02 2019-01-04 Efficiency and Sustainability Quotations Envelope 01 for seed and GAP BLK/W-RFQ 01 / Upgrade of A. Improved Agricultural Request for Single Stage - One 2019-08- infrastructure for BLK for IDA / 62050 Post Limited 30,000.00 29,821.38 Signed 2018-12-08 2018-12-11 2019-02-02 2019-01-04 Efficiency and Sustainability Quotations Envelope 01 seed, GAP and general extension BLK/W-RFQ 02 / Upgrade of A. Improved Agricultural Request for Single Stage - One 2019-08- infrastructure for BLK DAFOs IDA / 62050 Post Limited 30,000.00 9,889.69 Signed 2018-12-08 2018-12-05 2019-02-02 2019-01-04 Efficiency and Sustainability Quotations Envelope 01 for seed and GAP VC/W- RFQ 01 / Upgrade of A. Improved Agricultural Request for Single Stage - One 2019-08- infrastructure for VC for seed, IDA / 62050 Post Limited 30,000.00 29,644.13 Signed 2018-12-08 2018-11-20 2019-02-02 2018-12-14 Efficiency and Sustainability Quotations Envelope 01 GAP and general extension VC/W- RFQ 02 / Upgrade of A. Improved Agricultural Request for Single Stage - One 2019-08- infrastructure for VC DAFOs IDA / 62050 Post Limited 40,000.00 28,541.17 Signed 2018-12-08 2019-01-30 2019-02-02 2019-03-01 Efficiency and Sustainability Quotations Envelope 01 for seed and GAP VP/W- RFQ 01 / Upgrade of infrastructure for VP PAFO for A. Improved Agricultural Request for Single Stage - One 2019-08- IDA / 62050 Post Limited 30,000.00 50,450.60 Signed 2018-12-08 2018-12-24 2019-02-02 2019-01-16 seed, GAP and general Efficiency and Sustainability Quotations Envelope 01 extension VP/W- RFQ 02 / Upgrade of A. Improved Agricultural Request for Single Stage - One 2019-08- infrastructure for VP DAFOs IDA / 62050 Post Limited 20,000.00 50,450.60 Signed 2018-12-08 2018-12-24 2019-02-02 2019-01-16 Efficiency and Sustainability Quotations Envelope 01 for seed and GAP XYL/W- RFQ 01 / Upgrade of infrastructure for XYL PAFO A. Improved Agricultural Request for Single Stage - One 2019-08- IDA / 62050 Post Limited 30,000.00 30,697.50 Signed 2018-12-08 2018-12-10 2019-02-02 2019-01-14 for seed, GAP and general Efficiency and Sustainability Quotations Envelope 01 extension XYL/W- RFQ 02 / Upgrade of A. Improved Agricultural Request for Single Stage - One 2019-08- infrastructure for XYL DAFOs IDA / 62050 Post Limited 40,000.00 42,698.20 Signed 2018-12-08 2019-02-04 2019-02-02 2019-02-22 Efficiency and Sustainability Quotations Envelope 01 for seed and GAP XYL/W- RFQ 01.1 / Upgrade of critical productive A. Improved Agricultural Request for Single Stage - One 2021-05- IDA / 62050 Post Open - National 121,387.08 50,556.62 Signed 2020-10-06 2020-12-01 2020-12-03 infrastructure (Nam Ngeum 2) Efficiency and Sustainability Quotations Envelope 30 in Xienghone District XYL/W- RFQ 01.4 / Upgrade of critical productive A. Improved Agricultural Request for Single Stage - One 2021-05- IDA / 62050 Post Open - National 55,110.45 111,926.29 Signed 2020-10-06 2020-12-01 2020-12-03 infrastructure (Na Ngao) in Efficiency and Sustainability Quotations Envelope 30 Xayabuly District XYL/W- RFQ 01.5 / Upgrade Pending of critical productive A. Improved Agricultural Request for Single Stage - One 2021-12- IDA / 62050 Post Open - National 36,664.21 0.00 Implementat 2021-05-06 2021-07-01 infrastructure (Na La) in Efficiency and Sustainability Quotations Envelope 28 ion Xayabuly District XYL/W- RFQ 01.7 / Upgrade Pending of critical productive A. Improved Agricultural Request for Single Stage - One 2021-12- IDA / 62050 Post Open - National 196,899.10 0.00 Implementat 2021-05-06 2021-07-01 infrastructure (Nam Tan) in Efficiency and Sustainability Quotations Envelope 28 ion Phieng District KM/W-RFQ 01.5 / Upgrade of Pending critical productive A. Improved Agricultural Request for Single Stage - One 2021-12- IDA / 62050 Post Open - National 51,200.27 0.00 Implementat 2021-05-06 2021-07-01 infrastructure in (Ban Mahaxay Efficiency and Sustainability Quotations Envelope 28 ion Neua) Mahaxay District BLK/W-RFQ 01.1 / Upgrade of critical productive A. Improved Agricultural Request for Single Stage - One 2021-11- IDA / 62050 Post Open - National 168,880.99 157,685.59 Signed 2021-04-06 2021-06-01 2021-04-20 infrastructure in (Ban Pak Efficiency and Sustainability Quotations Envelope 28 Peung 1-3) Paksan District GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MAF/G-RFQ 08 / Office Single Stage - One equipment for MAF, MOIC, 5 IDA / 62050 C. Project Management Post Request for Bids Open - National 133,200.00 75,416.00 Signed 2018-09-01 2019-01-08 2018-09-06 2018-10-18 2019-01-30 2018-11-17 2019-01-30 2018-12-22 2019-02-14 2019-06-20 Envelope provinces and districts Page 1 MAF/G- RFQ 09 / Motorbikes Single Stage - One for Provinces, MAF and MOIC IDA / 62050 C. Project Management Post Request for Bids Open - National 84,000.00 57,680.00 Signed 2018-12-01 2019-03-26 2018-12-06 2019-01-17 2019-04-25 2019-02-16 2019-04-29 2019-03-23 2019-05-31 2019-09-19 Envelope (42 units) MAF/G- RFB 01 / Pick-up for A. Improved Agricultural Single Stage - One 5 provinces, MAF and MOIC IDA / 62050 Post Request for Bids Limited 630,000.00 628,400.00 Signed 2018-12-03 2019-01-11 2018-12-08 2019-01-11 2019-01-19 2019-02-08 2019-02-18 2019-02-08 2019-03-25 2019-03-11 2019-09-21 Efficiency and Sustainability Envelope (14 units) C3/G001 / Accounting software for the project Request for Single Stage - One IDA / 62050 C. Project Management Post Limited 25,000.00 24,200.00 Signed 2017-07-29 2017-12-18 2017-09-23 2018-01-31 2018-03-22 preparation and project Quotations Envelope implementation periods. C3/G002 / Computers for each project implementation Request for Single Stage - One unit involve in the PPA and IDA / V0940 C. Project Management Post Limited 30,000.00 27,168.00 Signed 2017-07-29 2017-11-01 2017-09-23 2017-12-06 2018-03-22 Quotations Envelope project implementation stages. MAF/G-RFQ 02 / Machine A. Improved Agricultural Request for Single Stage - One and equipment for NAFRI- IDA / 62050 Post Limited 25,000.00 41,327.00 Signed 2018-12-08 2019-11-26 2019-02-02 2020-01-22 2019-08-01 Efficiency and Sustainability Quotations Envelope HRC MAF/G-RFQ 10 / Lab A. Improved Agricultural Request for Single Stage - One Equipment and Tractor for IDA / 62050 Post Limited 70,000.00 55,597.00 Signed 2019-02-09 2019-04-29 2019-04-05 2019-06-25 2019-10-02 Efficiency and Sustainability Quotations Envelope NAFRI MAF/G- RFQ11 / Notebooks of 20 sets and Cellphone with Request for Single Stage - One IDA / 62050 C. Project Management Post Open - National 32,000.00 32,000.00 Signed 2019-07-06 2019-08-31 2020-08-03 2020-02-27 4-5G of 20sets Quotations Envelope (NPMO,PPMO,Districts) MAF/G- RFQ 12 / Additional Request for Single Stage - One IDA / 62050 C. Project Management Post Open - National 35,000.00 28,853.00 Signed 2019-07-06 2019-08-31 2020-09-14 2020-02-27 Equipment for DALAM Quotations Envelope MAF/G-RFQ 01 / Machine A. Improved Agricultural Request for Single Stage - One IDA / 62050 Post Limited 26,000.00 41,327.00 Signed 2019-11-20 2019-11-26 2020-01-15 2020-01-22 2020-07-13 and equipment for NAFRI-ARC Efficiency and Sustainability Quotations Envelope MAF/G-RFQ-13 / Office Request for Single Stage - One IDA / 62050 C. Project Management Post Limited 7,000.00 4,607.12 Signed 2019-12-06 2019-11-21 2020-01-31 2020-01-21 2020-07-29 Extension/Renovation Quotations Envelope MAF/G-RFQ-14 / Lab Request for Single Stage - One Equipment for PAFO & DAFO IDA / 62050 C. Project Management Post Limited 92,000.00 101,388.16 Signed 2020-01-06 2020-05-11 2020-03-02 2020-07-10 2020-08-29 Quotations Envelope of 5 Provinces MAF/G-RFQ 15 / Office Request for Single Stage - One Equipment for PAFO, DAFO, IDA / 62050 C. Project Management Post Open - National 94,100.00 68,260.50 Signed 2020-07-06 2020-08-31 2020-08-03 2021-02-27 Quotations Envelope PICO & DICO NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MAF/QBS-01 / TA for AB Matching Grants Management B. Enhanced Agricultural Quality Based IDA / 62050 Post Open - National 600,000.00 654,548.22 Signed 2018-12-15 2018-10-02 2019-01-05 2019-02-18 2019-03-13 2019-03-18 2019-04-30 2019-04-17 2019-05-23 2019-05-17 2019-08-30 2019-06-21 2019-10-25 2020-06-20 and Capacity Building for rice Commercialization Selection mills Consultant MAF/CQS-04 / Project Audits IDA / 62050 C. Project Management Post Qualification Limited 180,000.00 177,100.00 Signed 2018-12-03 2018-09-26 2018-12-17 2018-11-23 2019-01-16 2019-03-25 2019-02-20 2019-05-06 2019-08-19 for NPMO Selection Consultant MAF/CQS-02 / Panel of IDA / 62050 C. Project Management Post Qualification Limited 100,000.00 0.00 Canceled 2019-02-01 2019-09-05 2019-02-15 2019-03-17 2019-04-21 2019-10-18 Expert – Dam Safety Selection MAF/CQS-03 / TA firm for Consultant baseline, mid-term and final IDA / 62050 C. Project Management Post Qualification Limited 180,000.00 97,262.00 Signed 2019-02-01 2019-02-08 2019-02-15 2019-03-25 2019-03-17 2020-06-10 2019-04-21 2020-06-16 2019-10-18 assessment Selection Consultant MAF/CQS-05 / M&E Software IDA / 62050 C. Project Management Post Qualification Open - National 32,000.00 0.00 Canceled 2020-07-01 2020-07-17 2020-07-22 2020-09-04 2020-10-04 2020-11-08 2021-05-07 Selection MAF/LCS-01 / Mid Term Least Cost IDA / 62050 C. Project Management Post Open - National 100,000.00 0.00 Canceled 2021-08-01 2021-08-22 2021-10-05 2021-11-02 2021-12-02 2022-01-06 2022-02-10 2022-08-09 Review Selection INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual C1/C001 / Senior Technical Individual Advisor (International) IDA / V0940 C. Project Management Post Consultant Open 25,000.00 39,930.00 Signed 2017-07-19 2017-07-24 2017-09-06 2017-07-24 2017-09-27 2017-11-13 2017-11-01 2017-11-13 2018-04-30 working with DPC in Lao PDR. Selection Individual C3/C001 / Procurement staff IDA / V0940 C. Project Management Post Consultant Open 8,000.00 32,400.00 Signed 2017-07-19 2017-07-24 2017-09-06 2017-08-29 2017-09-27 2017-08-29 2017-11-01 2017-10-01 2018-04-30 working in DPC Selection C3/C003 / Environmental Individual Safeguard Specialist working IDA / V0940 C. Project Management Post Consultant Open 12,000.00 14,250.00 Signed 2017-07-19 2017-08-07 2017-09-06 2017-08-29 2017-09-27 2017-10-05 2017-11-01 2017-10-09 2018-04-30 with DPC. Selection Page 2 Individual C3/C004 / Social Safeguard IDA / V0940 C. Project Management Post Consultant Open 12,000.00 8,360.00 Signed 2017-07-19 2017-08-01 2017-09-06 2017-08-29 2017-09-27 2017-10-05 2017-11-01 2017-10-09 2018-04-30 Specialist working with DPC Selection XYL /IC-01 / Technical Individual A. Improved Agricultural consultant for XBL PAFO in IDA / 62050 Post Consultant Open 120,000.00 31,200.00 Signed 2018-08-01 2018-07-02 2018-09-19 2018-07-02 2018-10-10 2018-09-19 2018-11-14 2018-09-26 2019-05-13 Efficiency and Sustainability extension services Selection Individual KM/IC-04 / Project A. Improved Agricultural IDA / 62050 Post Consultant Open 66,000.00 15,000.00 Signed 2018-08-01 2017-12-18 2018-09-19 2017-12-18 2018-10-10 2018-08-23 2018-11-14 2018-09-24 2019-05-13 accountant for KM PAFO Efficiency and Sustainability Selection Individual BLK/IC-04 / Project A. Improved Agricultural IDA / 62050 Post Consultant Open 66,000.00 10,800.00 Signed 2018-08-01 2017-12-18 2018-09-19 2017-12-18 2018-10-10 2018-08-21 2018-11-14 2018-09-24 2019-05-13 accountant for BLK PAFO Efficiency and Sustainability Selection Individual VC/IC-04 / Project A. Improved Agricultural IDA / 62050 Post Consultant Open 66,000.00 20,400.00 Signed 2018-08-01 2017-12-18 2018-09-19 2017-12-18 2018-10-10 2018-09-05 2018-11-14 2018-09-24 2019-05-13 accountant for VC PAFO Efficiency and Sustainability Selection Individual VP/IC-04 / Project A. Improved Agricultural IDA / 62050 Post Consultant Open 66,000.00 18,000.00 Signed 2018-08-01 2017-12-18 2018-09-19 2017-12-18 2018-10-10 2018-09-04 2018-11-14 2018-09-24 2019-05-13 accountant for VP PAFO Efficiency and Sustainability Selection Individual XYL/IC-04 / Project A. Improved Agricultural IDA / 62050 Post Consultant Open 66,000.00 13,200.00 Signed 2018-08-01 2017-12-18 2018-09-19 2017-12-18 2018-10-10 2018-08-23 2018-11-14 2018-09-24 2019-05-13 accountant for XYL PAFO Efficiency and Sustainability Selection Individual MAF/IC-14 / Monitoring and IDA / 62050 C. Project Management Post Consultant Open 132,000.00 35,000.00 Signed 2018-08-01 2018-05-31 2018-09-19 2018-05-31 2018-10-10 2018-09-17 2018-11-14 2018-10-09 2019-05-13 evaluation specialist (DoPF) Selection Individual MAF/IC-08 / Accountant- IDA / 62050 C. Project Management Post Consultant Open 66,000.00 18,000.00 Signed 2018-08-01 2018-01-05 2018-09-19 2018-01-04 2018-10-10 2018-06-12 2018-11-14 2018-06-29 2019-05-13 assistant Selection Individual MAF/IC-11 / Procurement IDA / 62050 C. Project Management Post Consultant Open 66,000.00 18,000.00 Signed 2018-08-01 2018-05-31 2018-09-19 2018-06-04 2018-10-10 2018-09-03 2018-11-14 2018-09-03 2019-05-13 assistant Selection KM/IC-01 / Technical Individual A. Improved Agricultural consultant for KM PAFO in IDA / 62050 Post Consultant Open 120,000.00 33,600.00 Signed 2018-08-01 2018-07-02 2018-09-19 2018-07-02 2018-10-10 2018-09-10 2018-11-14 2018-09-26 2019-05-13 Efficiency and Sustainability extension services Selection VP/IC-01 / Technical Individual A. Improved Agricultural consultant for VP PAFO in IDA / 62050 Post Consultant Open 120,000.00 31,200.00 Signed 2018-08-01 2018-07-02 2018-09-19 2018-07-02 2018-10-10 2018-09-14 2018-11-14 2018-09-26 2019-05-13 Efficiency and Sustainability extension services Selection VC/IC 01 / Technical Individual A. Improved Agricultural consultant for VC PAFO in IDA / 62050 Post Consultant Open 120,000.00 33,600.00 Signed 2018-08-01 2018-07-02 2018-09-19 2018-07-02 2018-10-10 2018-09-14 2018-11-14 2018-09-26 2019-05-13 Efficiency and Sustainability extension services Selection BLK/IC-01 / Technical Individual A. Improved Agricultural consultant for BLK PAFO in IDA / 62050 Post Consultant Open 120,000.00 33,600.00 Signed 2018-08-01 2018-07-02 2018-09-19 2018-07-02 2018-10-10 2018-09-11 2018-11-14 2018-09-26 2019-05-13 Efficiency and Sustainability extension services Selection C1/C002 / Technical Advisor Individual (Lao National) working with IDA / V0940 Post Consultant Open 8,000.00 0.00 Canceled 2017-07-19 2017-09-06 2017-09-27 2017-11-01 2018-04-30 DPC. Selection MAF/IC-1 / Local Consultant Individual on Survey-Design of irrigation IDA / 62050 C. Project Management Post Consultant Open 144,000.00 44,800.00 Signed 2018-08-01 2018-05-31 2018-09-19 2018-05-31 2018-10-10 2018-10-04 2018-11-14 2018-10-10 2019-05-13 system (DOI) Selection Individual MAF/IC-4 / National Project IDA / 62050 C. Project Management Post Consultant Open 198,000.00 42,000.00 Signed 2018-09-03 2018-05-31 2018-10-22 2018-06-13 2018-11-12 2018-09-25 2018-12-17 2018-10-15 2019-06-15 Advisor (DoPF) Selection Individual MAF/IC-07 / Accountant- IDA / 62050 C. Project Management Post Consultant Open 66,000.00 18,000.00 Signed 2018-09-03 2018-01-04 2018-10-22 2018-06-28 2018-11-12 2018-06-28 2018-12-17 2018-07-13 2019-06-15 assistant Selection Individual MAF/IC-09 / Cashier – IDA / 62050 C. Project Management Post Consultant Limited 66,000.00 9,600.00 Signed 2018-09-01 2018-04-05 2018-09-06 2018-04-06 2018-09-27 2018-04-23 2018-11-01 2018-04-26 2019-04-30 assistant Selection MAF/SSS-06 / Procurement IDA / 62050 C. Project Management Post Direct Selection Direct 120,000.00 38,400.00 Signed 2018-10-01 2018-08-13 2018-10-11 2018-08-14 2018-12-15 2018-09-03 2019-06-13 specialist (DoPF) MAF/SSS-05 / Finance management specialist* IDA / 62050 C. Project Management Post Direct Selection Direct 132,000.00 26,195.00 Signed 2018-12-03 2018-10-24 2018-12-13 2018-10-29 2019-02-16 2018-11-19 2019-08-15 (DoPF) MAF/SSS-03 / Social IDA / 62050 C. Project Management Post Direct Selection Direct 84,000.00 19,000.00 Signed 2018-09-01 2018-08-14 2018-09-11 2018-08-15 2018-11-15 2018-08-27 2019-05-14 safeguard specialist (DoPF) MAF/IC-05 / International Individual Project Advisor (Project IDA / 62050 C. Project Management Post Consultant Limited 225,000.00 0.00 Canceled 2018-10-01 2018-10-06 2018-10-27 2018-12-01 2019-05-30 management DoPF) Selection MAF/SSS-07 / International IDA / 62050 C. Project Management Post Direct Selection Direct 225,000.00 62,000.00 Signed 2018-11-01 2018-10-12 2018-11-11 2018-11-22 2019-01-15 2019-01-17 2019-07-14 Project Advisor for NPMO Individual MAF/IC-010 / Administrative IDA / 62050 C. Project Management Post Consultant Limited 90,000.00 19,500.00 Signed 2018-11-01 2018-10-12 2018-11-06 2018-10-29 2018-11-27 2018-11-30 2019-01-01 2018-11-30 2019-06-30 & Public Relations Officer Selection MAF/IC-15 / 2nd Individual Procurement Assistant for IDA / 62050 C. Project Management Post Consultant Limited 36,000.00 0.00 Canceled 2018-11-01 2018-10-12 2018-11-06 2018-10-29 2018-11-27 2018-11-30 2019-01-01 2019-06-30 NPMO Selection Individual MAF/IC-012 / Project Advisor IDA / 62050 C. Project Management Post Consultant Limited 72,000.00 12,727.20 Signed 2018-11-01 2018-10-12 2018-11-06 2018-10-29 2018-11-27 2018-11-30 2019-01-01 2018-12-05 2019-06-30 (part time) for MOIC DOPC Selection Page 3 Individual MAF/IC-13 / Administrative IDA / 62050 C. Project Management Post Consultant Limited 46,000.00 7,200.00 Signed 2018-11-01 2018-10-12 2018-11-06 2018-10-29 2018-11-27 2018-12-26 2019-01-01 2018-12-24 2019-06-30 staff for MOIC DOPC Selection Individual KM/IC-03 / Technical IDA / 62050 C. Project Management Post Consultant Limited 120,000.00 24,000.00 Signed 2019-03-04 2019-05-17 2019-03-09 2019-05-28 2019-03-30 2019-11-29 2019-05-04 2019-12-27 2019-10-31 assistance to KM PICO Selection Individual BLK/IC-03 / Technical IDA / 62050 C. Project Management Post Consultant Limited 120,000.00 21,600.00 Signed 2019-03-04 2019-05-17 2019-03-09 2019-05-28 2019-03-30 2019-11-29 2019-05-04 2019-12-27 2019-10-31 assistance to BLK PICO Selection Individual VC/IC-03 / Technical IDA / 62050 C. Project Management Post Consultant Limited 120,000.00 24,000.00 Signed 2019-03-04 2019-05-17 2019-03-09 2019-05-28 2019-03-30 2019-11-29 2019-05-04 2019-12-27 2019-10-31 assistance to VC PICO Selection Individual VP/IC-03 / Technical IDA / 62050 C. Project Management Post Consultant Limited 120,000.00 21,000.00 Signed 2019-03-04 2019-05-17 2019-03-09 2019-05-28 2019-03-30 2019-11-29 2019-05-04 2019-12-27 2019-10-31 assistance to VP PICO Selection Individual XYL/IC-03 / Technical IDA / 62050 C. Project Management Post Consultant Limited 120,000.00 25,200.00 Signed 2019-03-04 2019-05-17 2019-03-09 2019-05-28 2019-03-30 2019-11-29 2019-05-04 2019-12-27 2019-10-31 assistance to XYL PICO Selection MAF/IC-02 / Local Individual Consultant on strengthening IDA / 62050 C. Project Management Post Consultant Limited 180,000.00 31,900.00 Signed 2019-01-07 2018-10-12 2019-01-12 2018-10-29 2019-02-02 2018-12-03 2019-03-09 2019-01-28 2019-09-05 of WUA and O&M (DOI) Selection Individual MAF/IC-16 / National Project IDA / 62050 C. Project Management Post Consultant Limited 198,000.00 36,000.00 Signed 2019-02-04 2019-02-05 2019-02-09 2019-02-11 2019-03-02 2019-07-02 2019-04-06 2019-07-02 2019-10-03 Advisor (NPMO) Selection MAF/SSS-08 / International Individual Procurement Advisor for IDA / 62050 C. Project Management Post Consultant Direct 51,000.00 29,480.00 Signed 2019-02-04 2019-02-11 2019-02-14 2019-02-11 2019-03-07 2019-02-11 2019-04-11 2019-02-28 2019-10-08 NPMO Selection MAF/IC-18 / National Individual Consultant on Institutional IDA / 62050 C. Project Management Post Consultant Open 130,500.00 31,200.00 Signed 2019-06-01 2019-06-05 2019-07-20 2019-08-06 2019-08-10 2019-08-12 2019-09-14 2019-08-12 2020-03-12 and Gender for MAF Selection MAF/IC-19 / National Individual Consultant on Seed, GAP and IDA / 62050 C. Project Management Post Consultant Open 130,500.00 36,000.00 Signed 2019-06-01 2019-06-05 2019-07-20 2019-06-10 2019-08-10 2019-08-14 2019-09-14 2019-08-14 2020-03-12 Organic Production and Selection Certification for MAF MAF/IC-20 / National Individual Consultant on Rice Import- IDA / 62050 C. Project Management Post Consultant Open 24,000.00 21,120.00 Signed 2019-06-01 2019-07-02 2019-07-20 2019-09-03 2019-08-10 2019-11-06 2019-09-14 2019-11-26 2020-03-12 Export Legislation and Selection Strategy to DIMAX for MoIC MAF/SSS-001 / Technical assistance to support IDA / 62050 C. Project Management Post Direct Selection Direct 485,000.00 695,955.00 Signed 2019-06-01 2019-05-22 2019-06-11 2019-06-03 2019-08-15 2020-01-08 2020-02-11 implementation (1) MAF/SSS-01 / Technical assistance to support IDA / 62050 C. Project Management Post Direct Selection Direct 770,000.00 0.00 Canceled 2018-12-03 2018-09-13 2018-12-13 2018-10-10 2019-02-16 2019-08-15 implementation (1) MAF/IC-22 / National Individual Consultant on Seed, GAP and IDA / 62050 C. Project Management Post Consultant Open 121,500.00 18,000.00 Signed 2020-01-01 2019-06-05 2020-02-19 2019-12-09 2020-03-11 2020-02-17 2020-04-15 2020-02-21 2020-10-12 Organic Production and Selection Certification for MAF Individual MAF/IC-23 / International IDA / 62050 C. Project Management Post Consultant Open 163,000.00 94,840.00 Signed 2020-01-01 2019-11-01 2020-02-19 2019-11-05 2020-03-11 2019-12-25 2020-04-15 2020-02-10 2020-10-12 Project Advisor for NPMO Selection MAF/IC-24 / National Individual Consultant on Business IDA / 62050 C. Project Management Post Consultant Limited 26,400.00 41,184.00 Signed 2020-03-01 2019-12-05 2020-03-06 2020-01-27 2020-03-27 2020-02-17 2020-05-01 2020-02-21 2020-10-28 Planning Advisor Selection MAF/IC-25 / National Consultant on Strengthening Individual of Water User Association IDA / 62050 C. Project Management Post Consultant Limited 151,000.00 19,800.00 Signed 2020-03-01 2019-12-13 2020-03-06 2020-01-15 2020-03-27 2020-01-21 2020-05-01 2020-02-21 2020-10-28 (WUAs) and Operation and Selection Maintenance (O&M) Individual KM/IC-05 / Junior IDA / 62050 C. Project Management Post Consultant Open 12,000.00 3,971.16 Signed 2020-04-01 2019-11-19 2020-05-20 2020-03-06 2020-06-10 2020-06-19 2020-07-15 2020-06-23 2021-01-11 Agronomist for KM PAFO Selection Individual BLK/IC-05 / Junior IDA / 62050 C. Project Management Post Consultant Open 12,000.00 3,968.64 Signed 2020-04-01 2019-11-19 2020-05-20 2020-03-06 2020-06-10 2020-06-19 2020-07-15 2020-06-22 2021-01-11 Agronomist for BLK PAFO Selection Individual VP/IC-05 / Junior IDA / 62050 C. Project Management Post Consultant Open 12,000.00 17,858.88 Signed 2020-04-01 2019-11-19 2020-05-20 2020-03-06 2020-06-10 2020-06-19 2020-07-15 2020-06-22 2021-01-11 Agronomist for VP PAFO Selection Individual XYL/IC-05 / Junior IDA / 62050 C. Project Management Post Consultant Open 12,000.00 15,477.70 Signed 2020-04-01 2019-11-19 2020-05-20 2020-03-06 2020-06-10 2020-06-19 2020-07-15 2020-06-22 2021-01-11 Agronomist for XYL PAFO Selection Individual VC/IC-05 / Junior IDA / 62050 C. Project Management Post Consultant Open 12,000.00 11,913.48 Signed 2020-04-01 2019-11-19 2020-05-20 2020-03-06 2020-06-10 2020-06-19 2020-07-15 2020-06-27 2021-01-11 Agronomist for VC PAFO Selection VC/IC-06 / Local service Individual providers – Farmer Group A. Improved Agricultural IDA / 62050 Post Consultant Open 63,000.00 0.00 Canceled 2020-04-01 2020-05-20 2020-06-10 2020-07-15 2021-01-11 Investment Plan Development Efficiency and Sustainability Selection for VC PAFO KM/IC-06 / Local service Individual providers – Farmer Group A. Improved Agricultural IDA / 62050 Post Consultant Open 59,000.00 0.00 Canceled 2020-04-01 2020-05-20 2020-06-10 2020-07-15 2021-01-11 Investment Plan Development Efficiency and Sustainability Selection for KM PAFO Page 4 MAF/IC-21 / National Individual Consultant to develop Market IDA / 62050 C. Project Management Post Consultant Limited 45,000.00 0.00 Canceled 2019-08-01 2019-12-19 2019-08-06 2020-01-08 2019-08-27 2019-10-01 2020-03-29 Information System (MIS) for Selection DIMEX, MoIC KM/IC-06.01 / Local service Individual providers – Farmer Group A. Improved Agricultural IDA / 62050 Post Consultant Open 29,500.00 29,500.00 Signed 2020-08-01 2020-03-03 2020-09-19 2020-04-06 2020-10-10 2020-06-22 2020-11-14 2020-06-30 2021-05-13 Investment Plan Development Efficiency and Sustainability Selection for KM PAFO KM/IC-06.02 / Local service Individual providers – Farmer Group A. Improved Agricultural IDA / 62050 Post Consultant Open 29,500.00 29,500.00 Signed 2020-08-01 2020-03-03 2020-09-19 2020-08-10 2020-10-10 2020-09-25 2020-11-14 2020-09-30 2021-05-13 Investment Plan Development Efficiency and Sustainability Selection for KM PAFO BLK/IC-06.01 / Local service Individual providers – Farmer Group A. Improved Agricultural IDA / 62050 Post Consultant Open 25,500.00 25,500.00 Signed 2020-08-01 2020-03-03 2020-09-19 2020-04-06 2020-10-10 2020-06-22 2020-11-14 2020-06-30 2021-05-13 Investment Plan Development Efficiency and Sustainability Selection for BLK PAFO BLK/IC-06.02 / Local service Individual providers – Farmer Group A. Improved Agricultural IDA / 62050 Post Consultant Open 25,500.00 25,500.00 Signed 2020-08-01 2020-03-03 2020-09-19 2020-08-10 2020-10-10 2020-09-25 2020-11-14 2020-09-30 2021-05-13 Investment Plan Development Efficiency and Sustainability Selection for BLK PAFO VC/IC-06.01 / Local service Individual providers – Farmer Group A. Improved Agricultural IDA / 62050 Post Consultant Open 31,500.00 31,500.00 Signed 2020-08-01 2020-03-03 2020-09-19 2020-04-06 2020-10-10 2020-06-22 2020-11-14 2020-06-30 2021-05-13 Investment Plan Development Efficiency and Sustainability Selection for VC PAFO VC/IC-06.02 / Local service Individual providers – Farmer Group A. Improved Agricultural IDA / 62050 Post Consultant Open 31,500.00 31,500.00 Signed 2020-08-01 2020-03-03 2020-09-19 2020-08-10 2020-10-10 2020-09-25 2020-11-14 2020-09-30 2021-05-13 Investment Plan Development Efficiency and Sustainability Selection for VC PAFO VP/IC-06.01 / Local service Individual providers – Farmer Group A. Improved Agricultural IDA / 62050 Post Consultant Open 25,000.00 25,000.00 Signed 2020-08-01 2020-03-03 2020-09-19 2020-07-13 2020-10-10 2020-06-22 2020-11-14 2020-06-30 2021-05-13 Investment Plan Development Efficiency and Sustainability Selection for VP PAFO VP/IC-06.02 / Local service Individual providers – Farmer Group A. Improved Agricultural IDA / 62050 Post Consultant Open 25,000.00 25,000.00 Signed 2020-08-01 2020-03-03 2020-09-19 2020-08-10 2020-10-10 2020-09-25 2020-11-14 2020-09-30 2021-05-13 Investment Plan Development Efficiency and Sustainability Selection for VP PAFO XYL/IC-06.01 / Local service Individual providers – Farmer Group A. Improved Agricultural IDA / 62050 Post Consultant Open 92,500.00 0.00 Canceled 2020-08-01 2020-09-19 2020-10-10 2020-11-14 2021-05-13 Investment Plan Development Efficiency and Sustainability Selection for XYL PAFO XYL/IC-06.02 / Local service Individual providers – Farmer Group A. Improved Agricultural IDA / 62050 Post Consultant Open 92,500.00 0.00 Canceled 2020-08-01 2020-09-19 2020-10-10 2020-11-14 2021-05-13 Investment Plan Development Efficiency and Sustainability Selection for XYL PAFO KM/IC-07.01 / Local Service Individual Providers to assist ABs in B. Enhanced Agricultural IDA / 62050 Post Consultant Open 12,000.00 10,500.00 Signed 2020-08-01 2020-05-28 2020-09-19 2020-07-13 2020-10-10 2021-03-25 2020-11-14 2021-03-31 2021-05-13 Developing Business Plans for Commercialization Selection KM PAFO KM/IC-07.02 / Local Service Individual Providers to assist ABs in B. Enhanced Agricultural IDA / 62050 Post Consultant Open 9,000.00 10,500.00 Signed 2020-08-01 2020-05-28 2020-09-19 2020-07-13 2020-10-10 2021-03-25 2020-11-14 2021-03-31 2021-05-13 Developing Business Plans for Commercialization Selection KM PAFO BLK/IC-07.01 / Local Service Individual Providers to assist ABs in B. Enhanced Agricultural IDA / 62050 Post Consultant Open 6,000.00 4,500.00 Signed 2020-08-01 2020-05-28 2020-09-19 2020-07-13 2020-10-10 2021-03-25 2020-11-14 2021-03-31 2021-05-13 Developing Business Plans for Commercialization Selection BLK PAFO BLK/IC-07.02 / Local Service Individual Providers to assist ABs in B. Enhanced Agricultural IDA / 62050 Post Consultant Open 3,000.00 4,500.00 Signed 2020-08-01 2020-05-28 2020-09-19 2020-07-13 2020-10-10 2021-03-25 2020-11-14 2021-03-31 2021-05-13 Developing Business Plans for Commercialization Selection BLK PAFO VC/IC-07.01 / Local Service Individual Providers to assist ABs in B. Enhanced Agricultural IDA / 62050 Post Consultant Open 12,000.00 12,000.00 Signed 2020-08-01 2020-05-28 2020-09-19 2020-07-13 2020-10-10 2021-03-25 2020-11-14 2021-03-31 2021-05-13 Developing Business Plans for Commercialization Selection VC PAFO VC/IC-07.02 / Local Service Individual Providers to assist ABs in B. Enhanced Agricultural IDA / 62050 Post Consultant Open 12,000.00 12,000.00 Signed 2020-08-01 2020-05-28 2020-09-19 2020-07-13 2020-10-10 2021-03-25 2020-11-14 2021-03-31 2021-05-13 Developing Business Plans for Commercialization Selection VC PAFO VP/IC-07.01 / Local Service Individual Providers to assist ABs in B. Enhanced Agricultural IDA / 62050 Post Consultant Open 12,000.00 10,500.00 Signed 2020-08-01 2020-05-28 2020-09-19 2020-07-13 2020-10-10 2021-03-25 2020-11-14 2021-03-31 2021-05-13 Developing Business Plans for Commercialization Selection VP PAFO VP/IC-07.02 / Local Service Individual Providers to assist ABs in B. Enhanced Agricultural IDA / 62050 Post Consultant Open 9,000.00 10,500.00 Signed 2020-08-01 2020-05-28 2020-09-19 2020-07-13 2020-10-10 2021-03-25 2020-11-14 2021-03-31 2021-05-13 Developing Business Plans for Commercialization Selection VP PAFO XYL/IC-07.01 / Local Service Individual Providers to assist ABs in B. Enhanced Agricultural IDA / 62050 Post Consultant Open 6,000.00 6,000.00 Signed 2020-08-01 2020-05-28 2020-09-19 2020-07-13 2020-10-10 2021-03-25 2020-11-14 2021-03-31 2021-05-13 Developing Business Plans for Commercialization Selection XYL PAFO XYL/IC-07.02 / Local Service Individual Providers to assist ABs in B. Enhanced Agricultural IDA / 62050 Post Consultant Open 6,000.00 6,000.00 Signed 2020-08-01 2020-05-28 2020-09-19 2020-07-13 2020-10-10 2021-03-25 2020-11-14 2021-03-31 2021-05-13 Developing Business Plans for Commercialization Selection XYL PAFO KM/IC-08.01 / Local Service Individual A. Improved Agricultural Provider for Farmer Group IDA / 62050 Post Consultant Open 4,800.00 3,843.36 Signed 2020-08-01 2020-08-05 2020-09-19 2020-10-05 2020-10-10 2021-01-20 2020-11-14 2021-01-20 2021-05-13 Efficiency and Sustainability Facilitator for KM PAFO Selection Page 5 KM/IC-08.02 / Local Service Individual A. Improved Agricultural Provider for Farmer Group IDA / 62050 Post Consultant Open 4,800.00 3,843.36 Signed 2020-08-01 2020-08-05 2020-09-19 2020-10-05 2020-10-10 2021-01-20 2020-11-14 2021-01-20 2021-05-13 Efficiency and Sustainability Facilitator for KM PAFO Selection KM/IC-08.03 / Local Service Individual A. Improved Agricultural Provider for Farmer Group IDA / 62050 Post Consultant Open 4,800.00 3,843.36 Signed 2020-08-01 2020-08-05 2020-09-19 2020-10-05 2020-10-10 2021-01-20 2020-11-14 2021-01-20 2021-05-13 Efficiency and Sustainability Facilitator for KM PAFO Selection BLK/IC-08.01 / Local Service Individual A. Improved Agricultural Provider for Farmer Group IDA / 62050 Post Consultant Open 4,800.00 3,843.36 Signed 2020-08-01 2020-08-05 2020-09-19 2020-10-05 2020-10-10 2021-01-15 2020-11-14 2021-01-18 2021-05-13 Efficiency and Sustainability Facilitator for BLK PAFO Selection BLK/IC-08.02 / Local Service Individual A. Improved Agricultural Provider for Farmer Group IDA / 62050 Post Consultant Open 4,800.00 3,843.36 Signed 2020-08-01 2020-08-05 2020-09-19 2020-10-05 2020-10-10 2021-01-15 2020-11-14 2021-01-18 2021-05-13 Efficiency and Sustainability Facilitator for BLK PAFO Selection BLK/IC-08.03 / Local Service Individual A. Improved Agricultural Provider for Farmer Group IDA / 62050 Post Consultant Open 4,800.00 3,843.36 Signed 2020-08-01 2020-08-05 2020-09-19 2020-10-05 2020-10-10 2021-01-15 2020-11-14 2021-01-18 2021-05-13 Efficiency and Sustainability Facilitator for BLK PAFO Selection VC/IC-08.01 / Local Service Individual A. Improved Agricultural Provider for Farmer Group IDA / 62050 Post Consultant Open 4,800.00 3,843.36 Signed 2020-08-01 2020-08-05 2020-09-19 2020-10-05 2020-10-10 2021-01-20 2020-11-14 2021-01-21 2021-05-13 Efficiency and Sustainability Facilitator for VC PAFO Selection VC/IC-08.02 / Local Service Individual A. Improved Agricultural Provider for Farmer Group IDA / 62050 Post Consultant Open 4,800.00 3,841.92 Signed 2020-08-01 2020-08-05 2020-09-19 2020-10-05 2020-10-10 2021-01-20 2020-11-14 2021-02-12 2021-05-13 Efficiency and Sustainability Facilitator for VC PAFO Selection VC/IC-08.03 / Local Service Individual A. Improved Agricultural Provider for Farmer Group IDA / 62050 Post Consultant Open 4,800.00 3,843.36 Signed 2020-08-01 2020-08-05 2020-09-19 2020-10-05 2020-10-10 2021-01-20 2020-11-14 2021-01-21 2021-05-13 Efficiency and Sustainability Facilitator for VC PAFO Selection VP/IC-08.01 / Local Service Individual A. Improved Agricultural Provider for Farmer Group IDA / 62050 Post Consultant Open 4,800.00 3,843.36 Signed 2020-08-01 2020-08-05 2020-09-19 2020-10-05 2020-10-10 2021-01-15 2020-11-14 2021-01-18 2021-05-13 Efficiency and Sustainability Facilitator for VP PAFO Selection VP/IC-08.02 / Local Service Individual A. Improved Agricultural Provider for Farmer Group IDA / 62050 Post Consultant Open 4,800.00 3,843.36 Signed 2020-08-01 2020-08-05 2020-09-19 2020-10-05 2020-10-10 2021-01-15 2020-11-14 2021-01-18 2021-05-13 Efficiency and Sustainability Facilitator for VP PAFO Selection VP/IC-08.03 / Local Service Individual A. Improved Agricultural Provider for Farmer Group IDA / 62050 Post Consultant Open 4,800.00 3,843.36 Signed 2020-08-01 2020-08-05 2020-09-19 2020-10-05 2020-10-10 2021-01-15 2020-11-14 2021-01-18 2021-05-13 Efficiency and Sustainability Facilitator for VP PAFO Selection XYL/IC-08.01 / Local Service Individual A. Improved Agricultural Provider for Farmer Group IDA / 62050 Post Consultant Open 4,800.00 3,840.48 Signed 2020-08-01 2020-08-05 2020-09-19 2020-10-05 2020-10-10 2021-01-20 2020-11-14 2021-01-25 2021-05-13 Efficiency and Sustainability Facilitator for XYL PAFO Selection XYL/IC-08.02 / Local Service Individual A. Improved Agricultural Provider for Farmer Group IDA / 62050 Post Consultant Open 4,800.00 3,840.48 Signed 2020-08-01 2020-08-05 2020-09-19 2020-10-05 2020-10-10 2021-01-20 2020-11-14 2021-01-25 2021-05-13 Efficiency and Sustainability Facilitator for XYL PAFO Selection XYL/IC-08.03 / Local Service Individual A. Improved Agricultural Provider for Farmer Group IDA / 62050 Post Consultant Open 4,800.00 3,840.48 Signed 2020-08-01 2020-08-05 2020-09-19 2020-10-05 2020-10-10 2021-01-20 2020-11-14 2021-01-25 2021-05-13 Efficiency and Sustainability Facilitator for XYL PAFO Selection XYL/IC-08.04 / Local Service Individual A. Improved Agricultural Provider for Farmer Group IDA / 62050 Post Consultant Open 4,800.00 3,840.48 Signed 2020-08-01 2020-08-05 2020-09-19 2020-10-05 2020-10-10 2021-01-20 2020-11-14 2021-01-25 2021-05-13 Efficiency and Sustainability Facilitator for XYL PAFO Selection XYL/IC-08.05 / Local Service Individual A. Improved Agricultural Provider for Farmer Group IDA / 62050 Post Consultant Open 4,800.00 3,840.48 Signed 2020-08-01 2020-08-05 2020-09-19 2020-10-05 2020-10-10 2021-01-20 2020-11-14 2021-01-25 2021-05-13 Efficiency and Sustainability Facilitator for XYL PAFO Selection XYL/IC-08.06 / Local Service Individual A. Improved Agricultural Provider for Farmer Group IDA / 62050 Post Consultant Open 4,800.00 3,840.48 Signed 2020-08-01 2020-08-05 2020-09-19 2020-10-05 2020-10-10 2021-01-20 2020-11-14 2021-01-25 2021-05-13 Efficiency and Sustainability Facilitator for XYL PAFO Selection XYL/IC-08.07 / Local Service Individual A. Improved Agricultural Provider for Farmer Group IDA / 62050 Post Consultant Open 4,800.00 3,840.48 Signed 2020-08-01 2020-08-05 2020-09-19 2020-10-05 2020-10-10 2021-01-20 2020-11-14 2021-01-25 2021-05-13 Efficiency and Sustainability Facilitator for XYL PAFO Selection XYL/IC-08.08 / Local Service Individual A. Improved Agricultural Provider for Farmer Group IDA / 62050 Post Consultant Open 4,800.00 0.00 Canceled 2020-08-01 2020-08-05 2020-09-19 2020-10-10 2020-11-14 2021-05-13 Efficiency and Sustainability Facilitator for XYL PAFO Selection XYL/IC-08.09 / Local Service Individual A. Improved Agricultural Provider for Farmer Group IDA / 62050 Post Consultant Open 4,800.00 0.00 Canceled 2020-08-01 2020-08-05 2020-09-19 2020-10-10 2020-11-14 2021-05-13 Efficiency and Sustainability Facilitator for XYL PAFO Selection XYL/IC-08.10 / Local Service Individual A. Improved Agricultural Provider for Farmer Group IDA / 62050 Post Consultant Open 4,800.00 0.00 Canceled 2020-08-01 2020-08-05 2020-09-19 2020-10-10 2020-11-14 2021-05-13 Efficiency and Sustainability Facilitator for XYL PAFO Selection MAF/IC-021 / International Individual Consultant on develop Market IDA / 62050 C. Project Management Post Consultant Open 60,000.00 54,692.00 Signed 2020-07-01 2019-12-19 2020-08-19 2020-01-08 2020-09-09 2020-05-26 2020-10-14 2020-06-05 2021-04-12 Information System (MIS) for Selection DIMEX MoIC Individual MAF/IC-28 / National Project IDA / 62050 C. Project Management Post Consultant Open 153,000.00 17,824.80 Signed 2020-08-01 2019-01-11 2020-09-19 2021-01-26 2020-10-10 2021-03-10 2020-11-14 2021-03-29 2021-05-13 Advisor (NPMO) Selection MAF/IC-27 / National Individual Consultant on Seed, GAP and IDA / 62050 C. Project Management Post Consultant Open 114,000.00 20,538.84 Signed 2020-08-01 2020-05-13 2020-09-19 2020-07-21 2020-10-10 2020-09-25 2020-11-14 2020-09-30 2021-05-13 Organic Production and Selection Certification for MAF Individual MAF/IC-29 / Local Irrigation A. Improved Agricultural IDA / 62050 Post Consultant Open 78,000.00 0.00 Canceled 2020-10-01 2020-08-14 2020-11-19 2020-12-10 2021-01-14 2021-07-13 Design Engineer Efficiency and Sustainability Selection MAF/IC-30 / International Individual A. Improved Agricultural Consultant of Irrigation IDA / 62050 Post Consultant Open 42,900.00 0.00 Canceled 2020-10-01 2020-08-14 2020-11-19 2020-12-10 2021-01-14 2021-07-13 Efficiency and Sustainability Design Selection Page 6 XYL/IC- 06.1 / Local service Individual providers – Farmer Group A. Improved Agricultural IDA / 62050 Post Consultant Open 37,000.00 37,000.00 Signed 2020-11-01 2020-03-03 2020-12-20 2020-04-06 2021-01-10 2020-09-25 2021-02-14 2020-10-30 2021-08-13 Investment Plan Development Efficiency and Sustainability Selection for XYL PAFO XYL/IC- 06.2 / Local service Individual providers – Farmer Group A. Improved Agricultural IDA / 62050 Post Consultant Open 37,000.00 37,000.00 Signed 2020-11-01 2020-03-03 2020-12-20 2020-04-06 2021-01-10 2020-09-25 2021-02-14 2020-10-30 2021-08-13 Investment Plan Development Efficiency and Sustainability Selection for XYL PAFO XYL/IC- 06.3 / Local service Individual providers – Farmer Group A. Improved Agricultural IDA / 62050 Post Consultant Open 37,000.00 37,000.00 Signed 2020-11-01 2020-03-03 2020-12-20 2020-10-10 2021-01-10 2020-11-25 2021-02-14 2020-11-26 2021-08-13 Investment Plan Development Efficiency and Sustainability Selection for XYL PAFO XYL/IC- 06.4 / Local service Individual providers – Farmer Group A. Improved Agricultural IDA / 62050 Post Consultant Open 37,000.00 37,000.00 Signed 2020-11-01 2020-03-03 2020-12-20 2020-10-10 2021-01-10 2020-11-26 2021-02-14 2020-11-26 2021-08-13 Investment Plan Development Efficiency and Sustainability Selection for XYL PAFO XYL/IC- 06.5 / Local service Individual providers – Farmer Group A. Improved Agricultural Pending IDA / 62050 Post Consultant Open 37,000.00 0.00 2020-11-01 2020-12-20 2021-01-10 2021-02-14 2021-08-13 Investment Plan Development Efficiency and Sustainability Implementation Selection for XYL PAFO KM/IC-9 / Technical Individual consultant for KM PAFO in IDA / 62050 C. Project Management Post Consultant Open 52,800.00 20,664.96 Signed 2020-11-01 2018-07-22 2020-12-20 2020-10-05 2021-01-10 2020-12-01 2021-02-14 2020-11-30 2021-08-13 extension services Selection VC/IC-9 / Technical Individual consultant for VC PAFO in IDA / 62050 C. Project Management Post Consultant Open 57,600.00 30,000.00 Signed 2020-11-01 2018-07-22 2020-12-20 2020-10-05 2021-01-10 2020-11-23 2021-02-14 2020-11-30 2021-08-13 extension services Selection Individual KM/IC- 10 / Local Irrigation A. Improved Agricultural IDA / 62050 Post Consultant Open 72,000.00 0.00 Canceled 2020-11-01 2020-12-20 2021-01-10 2021-02-14 2021-08-13 Design Engineer for KM PAFO Efficiency and Sustainability Selection Individual BLK/IC- 09 / Local Irrigation A. Improved Agricultural IDA / 62050 Post Consultant Open 72,000.00 0.00 Canceled 2020-11-01 2020-12-20 2021-01-10 2021-02-14 2021-08-13 Design Engineer for BLK PAFO Efficiency and Sustainability Selection Individual VC/IC- 10 / Local Irrigation A. Improved Agricultural IDA / 62050 Post Consultant Open 72,000.00 0.00 Canceled 2020-11-01 2020-12-20 2021-01-10 2021-02-14 2021-08-13 Design Engineer for VC PAFO Efficiency and Sustainability Selection Individual VP/IC- 09 / Local Irrigation A. Improved Agricultural IDA / 62050 Post Consultant Open 72,000.00 0.00 Canceled 2020-11-01 2020-12-20 2021-01-10 2021-02-14 2021-08-13 Design Engineer for VP PAFO Efficiency and Sustainability Selection Individual XYL/IC- 09 / Local Irrigation A. Improved Agricultural IDA / 62050 Post Consultant Open 72,000.00 0.00 Canceled 2020-11-01 2020-12-20 2021-01-10 2021-02-14 2021-08-13 Design Engineer for XYL PAFO Efficiency and Sustainability Selection Individual MAF/IC-31 / Monitoring and IDA / 62050 C. Project Management Post Consultant Open 67,000.00 15,317.28 Signed 2021-04-01 2021-01-01 2021-05-20 2020-11-24 2021-06-10 2021-02-25 2021-07-15 2021-03-09 2022-01-11 Evaluation Specialist Selection Individual VP/IC-10 / Technical Under IDA / 62050 C. Project Management Post Consultant Open 99,000.00 0.00 2021-05-01 2021-05-28 2021-06-19 2021-07-10 2021-08-14 2022-02-10 assistance to VP PICO Implementation Selection Individual VC/IC-11 / Technical Under IDA / 62050 C. Project Management Post Consultant Open 96,000.00 0.00 2021-05-01 2021-05-28 2021-06-19 2021-07-10 2021-08-14 2022-02-10 assistance to VC PICO Implementation Selection Individual MAF/IC-32 / Monitoring and Under IDA / 62050 C. Project Management Post Consultant Open 67,000.00 0.00 2021-06-01 2021-06-10 2021-07-20 2021-08-10 2021-09-14 2022-03-13 Evaluation specialist Implementation Selection MAF/DS-01 / Monitoring IDA / 62050 C. Project Management Post Direct Selection Direct 25,000.00 0.00 Under Review 2021-07-01 2021-06-10 2021-07-11 2021-09-14 2022-03-13 Geotagging Website MAF/IC-33 / Provincial Individual A. Improved Agricultural Irrigation Survey and Design IDA / 62050 Post Consultant Open 72,000.00 0.00 Under Review 2021-07-01 2021-06-10 2021-08-19 2021-09-09 2021-10-14 2022-04-12 Efficiency and Sustainability Engineer for VC & VP Selection MAF/IC-34 / Provincial Individual A. Improved Agricultural Irrigation Survey and Design IDA / 62050 Post Consultant Open 36,000.00 0.00 Under Review 2021-07-01 2021-06-10 2021-08-19 2021-09-09 2021-10-14 2022-04-12 Efficiency and Sustainability Engineer for XYL Province Selection MAF/IC-35 / Provincial Individual A. Improved Agricultural Irrigation Survey and Design IDA / 62050 Post Consultant Open 42,000.00 0.00 Under Review 2021-07-01 2021-06-10 2021-08-19 2021-09-09 2021-10-14 2022-04-12 Efficiency and Sustainability Engineer for BOL Province Selection MAF/IC-36 / Provincial Individual A. Improved Agricultural Irrigation Survey and Design IDA / 62050 Post Consultant Open 48,000.00 0.00 Under Review 2021-07-01 2021-06-10 2021-08-19 2021-09-09 2021-10-14 2022-04-12 Efficiency and Sustainability Engineer for KHM Province Selection Individual MAF/IC-37 / Environment & IDA / 62050 C. Project Management Post Consultant Open 32,000.00 0.00 Under Review 2021-07-01 2021-06-10 2021-08-19 2021-09-09 2021-10-14 2022-04-12 Social Safeguard Specialist Selection Individual MAF/IC-38 / Regional A. Improved Agricultural IDA / 62050 Post Consultant Open 92,400.00 0.00 Under Review 2021-07-01 2021-06-10 2021-08-19 2021-09-09 2021-10-14 2022-04-12 Irrigation Expert Efficiency and Sustainability Selection Page 7 PROCUREMENT PLAN (Textual Part) Project information: Ethiopia, Capacity Development Support to the AUC and Other AU Regional Organs, P126848 Project Implementation agency: The African Union Commission Date of the Procurement Plan: March 14, 2018 Period covered by this Procurement Plan: March 14, 2019 to March 14, 2020 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in [insert appropriate references to the national procurement legislation], such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. Not Applicable Not Applicable When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Not Applicable Goods: Not Applicable Works: Not Applicable PROCUREMENT Eastern Africa : Support for Capacity Dev't of the AUC and other African Union Organs PLAN General Information Country: Eastern Africa Bank’s Approval Date of the Original Procurement Plan: 2019-03-14 2021-06-03 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P126848 GPN Date: Project Name: Support for Capacity Dev't of the AUC and other African Union Organs Loan / Credit No: IDA / H9390, IDA / D3550 Africa Union Commission Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-AUC-81935-GO-RFB / Pending i. Strengthening Single Stage - One Supply and Installation IDA / H9390 Post Request for Bids Open - International 250,000.00 0.00 Implementati 2018-09-05 2018-09-10 2018-10-22 2018-11-21 2018-12-26 2019-06-24 Institutional Capacity Envelope Networking Equipment in AU on ET-AUC-115819-GO-RFB / Upgrading of the AUC and Reginal Office (RO) network Pending for high availability i. Strengthening Single Stage - One IDA / D3550 Post Request for Bids Open - International 300,000.00 0.00 Implementati 2019-05-31 2019-06-05 2019-07-17 2019-08-16 2019-09-20 2020-03-18 infrastructure by deployment Institutional Capacity Envelope on of Identity service Engine (ISE), Steal watch and network extension ET-AUC-175163-GO-RFB / Pending Purchase of AUCC access i. Strengthening Single Stage - One IDA / D3550 Post Request for Bids Open - International 250,000.00 0.00 Implementati 2020-07-19 2020-07-24 2020-08-21 2020-09-11 2020-10-09 2021-01-07 switches + Regional offices Institutional Capacity Envelope on Firewall ET-AUC-175168-GO-RFB / Pending Purchase and installation of i. Strengthening Single Stage - One IDA / D3550 Post Request for Bids Open - International 350,000.00 0.00 Implementati 2020-07-09 2020-07-14 2020-08-11 2020-09-01 2020-09-22 2020-12-21 equipment and IT telephony & Institutional Capacity Envelope on telecom systems ET-AUC-109689-GO-RFB / Selection of System Integrator for Design, Development, i. Strengthening Single Stage - One IDA / D3550 Post Request for Bids Open - International 1,500,000.00 0.00 Canceled 2019-07-24 2019-07-29 2019-09-09 2019-10-09 2019-11-13 2021-12-12 Implementation and Institutional Capacity Envelope Maintenance of e-Sourcing Software for the African Union ET-AUC-175170-GO-RFB / Implementation of e- i. Strengthening Single Stage - One IDA / D3550 Post Request for Bids Open - International 400,000.00 0.00 Canceled 2020-09-06 2020-09-11 2020-10-11 2020-11-10 2020-12-08 2021-05-17 Procurement system using Institutional Capacity Envelope SAAS model ET-AUC-175216-GO-RFB / Procurement of data infrastructure systems for the ii. Facilitating Economic Pending digitization of civil records Single Stage - One IDA / D3550 Development Results with Post Request for Bids Open - International 120,000.00 0.00 Implementati 2020-09-20 2020-09-25 2020-09-28 2020-10-19 2020-11-10 2021-02-08 and registries and Envelope Stakeholders on Maintenance Services at national and sub-national levels. ET-AUC-179315-GO-RFB / Pending i. Strengthening Single Stage - One Supply and delivery of IT IDA / D3550 Post Request for Bids Open - International 760,000.00 0.00 Implementati 2020-07-09 2020-07-14 2020-08-25 2020-09-24 2020-10-29 2021-04-27 Institutional Capacity Envelope Equipment on ET-AUC-179363-GO-DIR / Pending Renewal of the EMAIL and i. Strengthening IDA / D3550 Post Direct Selection Direct 340,000.00 0.00 Implementati 2020-07-16 2020-07-21 2020-08-25 2020-09-24 CLOUD services - Microsoft Institutional Capacity on Licenses ET-AUC-179500-GO-RFQ / Pending Purchase of e-Learning i. Strengthening Request for Single Stage - One IDA / D3550 Post Limited 12,000.00 0.00 Implementati 2020-08-07 2020-10-02 2021-03-31 Animation Software Institutional Capacity Quotations Envelope on (Subscription) ET-AUC-175194-NC-RFQ / Procurement of software and Pending i. Strengthening Request for Single Stage - One templates for the re- IDA / D3550 Post Limited 50,000.00 0.00 Implementati 2021-01-18 2021-03-15 2021-04-14 Institutional Capacity Quotations Envelope engineering process of e- on NEPAD Platform ET-AUC-181481-GO-RFB / Pending Purchase of data center i. Strengthening Single Stage - One IDA / D3550 Post Request for Bids Open - International 300,000.00 0.00 Implementati 2020-07-20 2020-07-25 2020-09-05 2020-10-05 2020-11-09 2021-02-07 storage and compute Institutional Capacity Envelope on equipment ET-AUC-181487-GO-RFB / Pending Purchase of Datacenter i. Strengthening Single Stage - One IDA / D3550 Post Request for Bids Open - International 200,000.00 0.00 Implementati 2020-08-04 2020-08-09 2020-09-20 2020-10-20 2020-11-24 2021-02-22 firewall and monitoring Institutional Capacity Envelope on licenses NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-AUC-175150-NC-RFQ / Under i. Strengthening Request for Single Stage - One Printing services of magazine IDA / D3550 Post Limited 15,000.00 0.00 Implementati 2020-06-19 2020-07-24 2020-07-24 2020-08-08 Institutional Capacity Quotations Envelope and brochures on Page 1 ET-AUC-175152-NC-RFQ / Pending Purchasing of Printing i. Strengthening Request for Single Stage - One IDA / D3550 Post Open - National 35,000.00 0.00 Implementati 2020-10-13 2020-12-08 2021-06-06 services of magazines and Institutional Capacity Quotations Envelope on Brochures for AU CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-AUC-78696-CS-QCBS / Update AU Digital Platforms - i. Strengthening Quality And Cost- IDA / H9390 Post Open - International 82,000.00 0.00 Canceled 2018-11-22 2018-12-13 2019-01-26 2019-02-23 2019-03-25 2019-04-29 2019-06-03 2020-06-02 Website Rebranding & Content Institutional Capacity Based Selection Update ET-AUC-81942-CS-QCBS / Consultancy services for RECs i. Strengthening Quality And Cost- IDA / H9390 Post Open - International 100,000.00 0.00 Canceled 2018-11-14 2018-12-05 2019-01-18 2019-02-15 2019-03-17 2019-04-21 2019-05-26 2020-05-25 operational model Institutional Capacity Based Selection assessment. ET-AUC-81953-CS-QCBS / Expanded Study on the ii. Facilitating Economic benefits of the Single African Quality And Cost- Under IDA / H9390 Development Results with Post Open - International 450,000.00 0.00 2018-11-09 2019-10-15 2018-11-30 2019-01-13 2019-02-10 2019-03-12 2019-04-16 2019-05-21 2020-05-20 Air Transport Market and Based Selection Implementation Stakeholders Communication Strategy for SAATM advocacy ET-AUC-118984-CS-CQS / Selection of Training Consultant i. Strengthening Pending providing firm for AU IDA / D3550 Post Qualification Open - International 25,000.00 0.00 2019-06-14 2019-07-05 2019-08-18 2019-09-17 2019-10-22 2020-04-19 Institutional Capacity Implementation Emerging Leaders training for Selection AU staff. ET-AUC-118994-CS-CQS / Selection of training providing Consultant i. Strengthening Pending firm in Women in Leadership IDA / D3550 Post Qualification Open - International 25,000.00 0.00 2019-06-14 2019-07-05 2019-08-18 2019-09-17 2019-10-22 2020-04-19 Institutional Capacity Implementation training program for the AU Selection staff. ET-AUC-118995-CS-CQS / Selection of training providing Consultant firm so as to provide Report i. Strengthening Pending IDA / D3550 Post Qualification Open - International 25,000.00 0.00 2019-06-14 2019-07-05 2019-08-18 2019-09-17 2019-10-22 2020-04-19 Writing and Presentation Skills Institutional Capacity Implementation Selection training program for the AU staff. ET-AUC-118997-CS-CQS / Selection of training providing Consultant i. Strengthening Pending firm so as to provide Effective IDA / D3550 Post Qualification Open - International 25,000.00 0.00 2019-06-14 2019-07-05 2019-08-18 2019-09-17 2019-10-22 2020-04-19 Institutional Capacity Implementation Communication Skills training Selection program for the AU staff ET-AUC-118998-CS-CQS / Selection of training providing Consultant firm so as to provide Strategic i. Strengthening Pending IDA / D3550 Post Qualification Open - International 25,000.00 0.00 2019-06-14 2019-07-05 2019-08-18 2019-09-17 2019-10-22 2020-04-19 Management for Agenda 2063 Institutional Capacity Implementation Selection training program for the AU staff ET-AUC-118999-CS-CQS / Selection of training providing Consultant i. Strengthening Pending firm so as to provide IDA / D3550 Post Qualification Open - International 25,000.00 0.00 2019-06-14 2019-07-05 2019-08-18 2019-09-17 2019-10-22 2020-04-19 Institutional Capacity Implementation Diplomatic Etiquette training Selection program for the AU staff. ET-AUC-119000-CS-CQS / Selection of training providing Consultant i. Strengthening Pending firm so as to provide Policy IDA / D3550 Post Qualification Open - International 25,000.00 0.00 2019-06-14 2019-07-05 2019-08-18 2019-09-17 2019-10-22 2020-04-19 Institutional Capacity Implementation Research & Analysis training Selection program for the AU staff. ET-AUC-119003-CS-CQS / Selection of training providing Consultant firm so as to provide i. Strengthening Pending IDA / D3550 Post Qualification Open - International 25,000.00 0.00 2019-06-14 2019-07-05 2019-08-18 2019-09-17 2019-10-22 2020-04-19 Delivering Service Excellence Institutional Capacity Implementation Selection training program for the AU staff. ET-AUC-119004-CS-CQS / Selection of training providing Consultant firm so as to provide ICT i. Strengthening Pending IDA / D3550 Post Qualification Open - International 25,000.00 0.00 2019-06-14 2019-07-05 2019-08-18 2019-09-17 2019-10-22 2020-04-19 Productivity- Microsoft Office Institutional Capacity Implementation Selection Proficiency training program for the AU staff. ET-AUC-78675-CS-QCBS / SAP Grant Management i. Strengthening Quality And Cost- IDA / D3550 Post Open - International 700,000.00 0.00 Canceled 2018-09-19 2018-10-12 2018-11-25 2018-12-23 2019-01-22 2019-02-26 2019-04-02 2019-09-29 Implementation Support for Institutional Capacity Based Selection the AU ET-AUC-175132-CS-QCBS / i. Strengthening Quality And Cost- Pending Development of the AU IDA / D3550 Post Open - International 300,000.00 0.00 2020-07-30 2020-08-05 2020-09-03 2020-10-01 2020-10-16 2020-10-30 2020-11-27 2021-02-23 Institutional Capacity Based Selection Implementation transition plan ET-AUC-175177-CS-QCBS / Consultancy service and acquisition of AUC HR records i. Strengthening Quality And Cost- Pending IDA / D3550 Post Open - International 100,000.00 0.00 2020-08-10 2020-08-25 2020-09-16 2020-10-14 2020-10-29 2020-12-03 2021-01-07 2021-04-05 and archives management Institutional Capacity Based Selection Implementation system to digitize employees’ records. ET-AUC-175197-CS-QCBS / Consultancy service for support of process review and i. Strengthening Quality And Cost- Under re-engineering, solution IDA / D3550 Post Open - International 200,000.00 0.00 2020-09-13 2020-06-23 2020-09-28 2020-10-27 2020-11-24 2020-12-09 2021-01-07 2021-01-28 2021-05-28 Institutional Capacity Based Selection Implementation proposal and change management in view of e- NEPAD formation. Page 2 ET-AUC-175201-CS-QCBS / Consultancy service for deployment and training of i. Strengthening Quality And Cost- Pending IDA / D3550 Post Open - International 400,000.00 0.00 2020-08-09 2020-08-16 2020-09-14 2020-10-12 2020-11-02 2020-11-23 2020-12-15 2021-05-14 opted solution(s) for Institutional Capacity Based Selection Implementation automation and digital workplace. ET-AUC-175214-CS-QCBS / Consultancy Services to undertake development, ii. Facilitating Economic Quality And Cost- Under deployment and maintenance IDA / D3550 Development Results with Post Open - International 200,000.00 0.00 2020-08-23 2020-08-24 2020-09-07 2020-09-29 2020-10-27 2020-11-17 2020-12-12 2021-01-03 2021-06-02 Based Selection Implementation of data tools and technologies Stakeholders for the AU Innovation Data Hub. ET-AUC-175203-CS-QCBS / Consultancy service on reconfiguration and i. Strengthening Quality And Cost- Pending IDA / D3550 Post Open - International 100,000.00 0.00 2020-08-16 2020-08-17 2020-09-15 2020-10-13 2020-10-28 2020-11-25 2020-12-17 2021-05-16 consolidation of AUDA-NEPAD Institutional Capacity Based Selection Implementation SAP ERP System to align with e- NEPAD ET-AUC-178370-CS-QCBS / Consultancy Services to ii. Facilitating Economic develop Africa’s Partnership Quality And Cost- Under IDA / D3550 Development Results with Post Open - International 132,980.00 0.00 2020-08-16 2020-08-24 2020-09-06 2020-10-20 2020-11-17 2020-12-17 2021-01-21 2021-02-25 2021-05-26 Strategy, Map, develop Based Selection Implementation Stakeholders baseline and external partners report ET-AUC-178374-CS-QCBS / Consultancy Services on ii. Facilitating Economic Innovation of Data Hab for Quality And Cost- Under IDA / D3550 Development Results with Post Open - International 90,000.00 0.00 2020-08-28 2020-08-24 2020-09-18 2020-11-01 2020-11-29 2020-12-29 2021-02-02 2021-03-09 2021-06-07 datasets and information Based Selection Implementation Stakeholders required for generating policy insights from the hub. ET-AUC-175142-CS-QCBS / Consultancy Services for the i. Strengthening Quality And Cost- Pending IDA / D3550 Post Open - International 200,000.00 0.00 2020-07-12 2020-07-19 2020-08-17 2020-09-14 2020-09-29 2020-10-13 2020-10-27 2021-01-23 production of documentaries Institutional Capacity Based Selection Implementation for AU flagship projects ET-AUC-175164-CS-QCBS / Consultancy Services for SAP i. Strengthening Quality And Cost- Under IDA / D3550 Post Open - International 182,000.00 0.00 2020-07-05 2020-08-05 2020-07-20 2020-08-17 2020-09-14 2020-09-29 2020-10-13 2020-10-27 2021-04-05 Business Process Re- Institutional Capacity Based Selection Implementation engineering in AUS ET-AUC-184878-CS-QCBS / Implementation of e- i. Strengthening Quality And Cost- IDA / D3550 Post Open - International 400,000.00 0.00 Under Review 2020-07-31 2020-08-10 2020-08-14 2020-09-12 2020-10-10 2020-10-25 2020-11-29 2021-01-03 2021-06-02 Procurement System in AU Institutional Capacity Based Selection using SaaS model ET-AUC-188089-CS-QCBS / Establishment of expert databases, repositories, Communities of Practice and ii. Facilitating Economic Quality And Cost- Under guidelines for data collection, IDA / D3550 Development Results with Post Open - International 60,000.00 0.00 2020-08-30 2020-08-24 2020-09-20 2020-11-03 2020-12-01 2020-12-31 2021-02-04 2021-03-11 2021-05-10 Based Selection Implementation analysis, validation, reporting, Stakeholders and for mutual accountability - reinforcing the continental dashboard ET-AUC-188090-CS-QCBS / Development of a continental dashboard with an interactive map that enables tracking and ii. Facilitating Economic Quality And Cost- Under reporting on AU Member IDA / D3550 Development Results with Post Open - International 95,000.00 0.00 2020-08-30 2020-08-19 2020-09-20 2020-11-03 2020-12-01 2020-12-31 2021-02-04 2021-03-11 2021-05-10 Based Selection Implementation States' implementation Stakeholders progress and performance on Agenda 2063 and SDGs goals and targets ET-AUC-188093-CS-QCBS / Consultancy Services to acquire, customize and operationalize continental e- learning System on Software ii. Facilitating Economic Quality And Cost- Under as a Services (SaaS) model to IDA / D3550 Development Results with Post Open - International 350,000.00 0.00 2020-08-30 2020-10-02 2020-09-20 2020-11-03 2020-12-01 2020-12-31 2021-02-04 2021-03-11 2021-06-29 Based Selection Implementation disseminate Business Stakeholders Development and Management Solutions for MSMEs leaders in 55 African Member States. ET-AUC-188094-CS-QCBS / Consultancy Services to acquire, customize and operationalize e-Market Place ii. Facilitating Economic Quality And Cost- Pending module Repository of IDA / D3550 Development Results with Post Open - International 450,000.00 0.00 2020-08-30 2020-09-20 2020-11-03 2020-12-01 2020-12-31 2021-02-04 2021-03-11 2021-06-29 Based Selection Implementation marketplaces (e-commerce, Stakeholders etc.) on Software as a Services (SaaS) model for MSMEs in 55 countries in Africa ET-AUC-188098-CS-QCBS / Consultancy Services to acquire, customize and operationalize Simplified e- ii. Facilitating Economic Procurement module on Quality And Cost- Pending IDA / D3550 Development Results with Post Open - International 150,000.00 0.00 2020-08-30 2020-09-20 2020-11-03 2020-12-01 2020-12-31 2021-02-04 2021-03-11 2021-06-29 Software as a Services (SaaS) Based Selection Implementation Stakeholders model to avail public procurement opportunities to MSMEs in 55 countries in Africa ET-AUC-188100-CS-QCBS / Consultancy Service to support the designing and ii. Facilitating Economic implementation of e-learning Quality And Cost- Pending IDA / D3550 Development Results with Post Open - International 300,000.00 0.00 2020-08-23 2020-09-13 2020-10-27 2020-11-24 2020-12-24 2021-01-28 2021-03-04 2021-06-22 system, e-Market place Based Selection Implementation Stakeholders system and simplified e- Procurement platform for AUDA-NEPAD ET-AUC-227208-CS-LCS / i. Strengthening Least Cost Pending IDA / H9390 Post Open - National 10,000.00 0.00 2021-03-31 2021-04-01 2021-04-03 2021-05-01 2021-05-06 2021-05-16 2021-05-28 2021-06-27 Annual Project Financial Audit Institutional Capacity Selection Implementation Page 3 INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-AUC-78689-CS-INDV / Individual Development of Finance i. Strengthening IDA / H9390 Post Consultant Open 50,000.00 0.00 Canceled 2018-11-14 2019-01-02 2019-01-23 2019-02-27 2019-08-26 Intranet (Regulatory, IPSAS Institutional Capacity Selection NEWS, forum,....) ET-AUC-78693-CS-INDV / Individual i. Strengthening Pending development of strategic IDA / H9390 Post Consultant Open 150,000.00 0.00 2018-11-29 2019-01-17 2019-02-07 2019-03-14 2019-09-10 Institutional Capacity Implementation plans of 2 AU organs Selection ET-AUC-81933-CS-INDV / Individual i. Strengthening Consultancy & development of IDA / H9390 Post Consultant Open 50,000.00 0.00 Canceled 2018-11-27 2019-01-15 2019-02-05 2019-03-12 2019-09-08 Institutional Capacity a Financial Control Framework Selection Individual ET-AUC-78679-CS-INDV / i. Strengthening IDA / D3550 Post Consultant Limited 12,000.00 0.00 Canceled 2019-05-15 2019-05-20 2019-06-10 2019-07-15 2020-01-11 Communication Consultant Institutional Capacity Selection ET-AUC-106359-CS-CDS / i. Strengthening Pending 2018 Year End Project IDA / H9390 Post Direct Selection Direct 2,400.00 0.00 2019-05-14 2019-05-24 2019-07-28 2020-01-24 Institutional Capacity Implementation Financial Audit ET-AUC-115842-CS-QCBS / Individual Selection of an individual i. Strengthening Pending IDA / D3550 Post Consultant Open 50,000.00 0.00 2019-05-21 2019-07-09 2019-07-30 2019-09-03 2020-03-01 consultant for Revamping of Institutional Capacity Implementation Selection the AUC Internet Portal Individual ET-AUC-78697-CS-INDV / i. Strengthening IDA / H9390 Post Consultant Limited 12,000.00 0.00 Canceled 2018-04-11 2018-04-16 2018-05-07 2018-06-11 2018-12-08 Media Consultant Institutional Capacity Selection ET-AUC-166560-CS-CDS / i. Strengthening Pending IDA / D3550 Post Direct Selection Direct 2,129.00 0.00 2020-03-27 2020-04-06 2020-06-10 2020-12-07 Annual Project Audit Institutional Capacity Implementation ET-AUC-175184-CS-INDV / ii. Facilitating Economic Individual Senior consultant in Trade in Under IDA / D3550 Development Results with Post Consultant Open 100,000.00 0.00 2020-09-13 2020-06-24 2020-10-20 2020-10-27 2020-11-17 2021-02-15 goods – data Implementation Stakeholders Selection analytics/economist ET-AUC-175188-CS-INDV / Development of a continental dashboard with an interactive map that enables tracking and ii. Facilitating Economic Individual reporting on AU Member IDA / D3550 Development Results with Post Consultant Open 95,000.00 0.00 Canceled 2020-08-11 2020-06-25 2020-09-29 2020-10-20 2020-11-24 2021-05-23 States' implementation Stakeholders Selection progress and performance on Agenda 2063 and SDGs goals and targets ET-AUC-175191-CS-INDV / Establishment of expert databases, repositories, Communities of Practice and ii. Facilitating Economic Individual Under guidelines for data collection, IDA / D3550 Development Results with Post Consultant Open 60,000.00 0.00 2020-09-13 2020-06-25 2020-11-01 2020-11-22 2020-12-27 2021-06-25 Implementation analysis, validation, reporting, Stakeholders Selection and for mutual accountability - reinforcing the continental dashboard. ET-AUC-175204-CS-INDV / Individual Engagement of consultant for i. Strengthening Under IDA / D3550 Post Consultant Open 65,000.00 0.00 2020-09-13 2020-06-23 2020-10-17 2020-11-01 2020-11-29 2021-04-28 project coordination and Institutional Capacity Implementation Selection assistance ET-AUC-175212-CS-INDV / Senior expert to develop ii. Facilitating Economic Individual Partnerships M & E Under IDA / D3550 Development Results with Post Consultant Open 48,020.00 0.00 2020-09-07 2020-08-24 2020-09-28 2020-10-05 2020-10-27 2020-12-26 Framework, Tracking & Implementation Stakeholders Selection Reporting Tool, Digital database ET-AUC-175213-CS-INDV / ii. Facilitating Economic Individual Under Junior Short-term Consultant IDA / D3550 Development Results with Post Consultant Open 80,000.00 0.00 2020-10-11 2020-08-24 2020-11-19 2020-12-04 2020-12-12 2021-05-11 Implementation to support TCP on project Stakeholders Selection ET-AUC-175220-CS-INDV / Consultancy Services to develop an AU-wide Citizen ii. Facilitating Economic Individual Under Engagement Strategy in line IDA / D3550 Development Results with Post Consultant Open 70,000.00 0.00 2020-09-22 2020-08-24 2020-11-10 2020-12-01 2021-01-05 2021-04-05 Implementation with standardized tools, Stakeholders Selection instruments and indicators for Agenda 2063 implementation. ET-AUC-175186-CS-INDV / Consultancy service for ii. Facilitating Economic Individual competition policy for the IDA / D3550 Development Results with Post Consultant Open 50,000.00 0.00 Under Review 2020-09-08 2020-09-23 2020-10-27 2020-11-17 2020-12-22 2021-06-20 AfCFTA support unit and Stakeholders Selection Interim secretariat. ET-AUC-175222-CS-INDV / Consultancy Services to develop a set of advisory services guidelines and ii. Facilitating Economic Individual Under knowledge products based on IDA / D3550 Development Results with Post Consultant Open 70,000.00 0.00 2020-09-13 2020-08-24 2020-11-01 2020-11-22 2020-12-27 2021-04-26 Implementation the AU-wide Citizen Stakeholders Selection Engagement Strategy (tools, capacity building and training materials) ET-AUC-175225-CS-INDV / Consultancy Services to Undertake a context analysis and stakeholder mapping of ii. Facilitating Economic Individual Under existing data use and citizens IDA / D3550 Development Results with Post Consultant Open 52,000.00 0.00 2020-09-20 2020-08-24 2020-11-08 2020-11-29 2021-01-03 2021-04-03 Implementation engagement mechanisms Stakeholders Selection across AU Organs, CSOs, private sector, communities, faith-based organizations Page 4 ET-AUC-175209-CS-INDV / Consultancy Services to Individual i. Strengthening Pending supervise and monitor the IDA / D3550 Post Consultant Open 65,000.00 0.00 2020-08-16 2020-09-24 2020-10-01 2020-10-23 2021-06-24 Institutional Capacity Implementation development of e-NEPAD Selection solutions. ET-AUC-175215-CS-INDV / Deployment of data interfacing modules and tools ii. Facilitating Economic Individual Pending in selected Member States for IDA / D3550 Development Results with Post Consultant Open 48,000.00 0.00 2020-09-20 2020-11-08 2020-11-29 2021-01-03 2021-05-03 Implementation linkage and transmission of Stakeholders Selection data to and from the AU Innovation Data hub ET-AUC-175145-CS-INDV / Consultancy Services for Individual Multimedia content i. Strengthening Under IDA / D3550 Post Consultant Open 30,000.00 0.00 2020-07-06 2020-07-10 2020-08-09 2020-08-23 2020-09-20 2021-02-17 development and video Institutional Capacity Implementation Selection documentaries on flagships projects ET-AUC-175147-CS-INDV / Individual Consultancy Services for the i. Strengthening Under IDA / D3550 Post Consultant Open 40,000.00 0.00 2020-07-12 2020-07-10 2020-08-01 2020-08-15 2020-09-05 2021-02-02 development of AU Open Institutional Capacity Implementation Selection Space Content ET-AUC-175139-CS-INDV / Develop and design L&D Strategy, processes and Individual i. Strengthening Pending policies to improve e- IDA / D3550 Post Consultant Open 70,000.00 0.00 2020-06-21 2020-08-09 2020-08-14 2020-08-28 2020-10-27 Institutional Capacity Implementation learning, web-based, and VC Selection based training modules and knowledge impact assessment ET-AUC-175146-CS-INDV / Individual Consultancy Services for i. Strengthening Under IDA / D3550 Post Consultant Open 30,000.00 0.00 2020-07-03 2020-07-10 2020-08-05 2020-08-19 2020-09-16 2021-02-13 development of contents for Institutional Capacity Implementation Selection six publications ET-AUC-175187-CS-INDV / Consultancy service to provide capacity development support ii. Facilitating Economic Individual Under to the team responsible for IDA / D3550 Development Results with Post Consultant Open 75,000.00 0.00 2020-08-02 2020-10-22 2020-08-22 2020-09-05 2020-09-26 2021-03-25 Implementation statistical strategy Stakeholders Selection implementation (Harmonization of Statistics) ET-AUC-184110-CS-CDS / SAP S4 Training by SAP Africa) i. Strengthening Under to AU Senior Management, IDA / D3550 Post Direct Selection Direct 290,000.00 0.00 2020-10-02 2020-08-05 2020-10-12 2020-12-16 2021-03-16 Institutional Capacity Implementation Business Users (FICO, HCM, MM) and SAP Technical Team ET-AUC-200078-CS-INDV / the consultancy service is used to assist the African Union in developing a partnership strategy and Individual i. Strengthening Under policy, providing guidelines to IDA / D3550 Post Consultant Open 60,000.00 0.00 2020-10-16 2020-10-16 2020-12-04 2020-12-25 2021-01-29 2021-07-28 Institutional Capacity Implementation strengthen its capacity in Selection partnership initiation, development, coordination and management, with a view of agenda 2063. ET-AUC-200085-CS-INDV / The Consultant will support the Head of PMCD and his team in developing the Individual i. Strengthening Under partnership strategy and IDA / H9390 Post Consultant Open 30,000.00 0.00 2020-10-16 2020-10-16 2020-12-04 2020-12-25 2021-01-29 2021-07-28 Institutional Capacity Implementation policy and Support the Selection development of working methods with ACBF and AUDA- NEPAD. ET-AUC-200088-CS-INDV / Consultancy service for the development of the partnerships management Individual i. Strengthening Under information system (PMIS) is IDA / D3550 Post Consultant Open 30,000.00 0.00 2020-10-16 2020-10-16 2020-12-04 2020-12-25 2021-01-29 2021-07-28 Institutional Capacity Implementation used to provide support to Selection the Partnerships Management and Coordination Division in the development of the PMIS ET-AUC-201013-CS-INDV / Consultancy service to provide capacity development support ii. Facilitating Economic Individual Pending to the team responsible for IDA / D3550 Development Results with Post Consultant Open 75,000.00 0.00 2020-10-22 2020-12-10 2020-12-31 2021-02-04 2021-08-03 Implementation statistical strategy Stakeholders Selection implementation (Harmonization of Statistics) ET-AUC-238211-CS-INDV / Selection of Communication officer to support AUC- STATAFRIC on the Individual i. Strengthening Pending management and IDA / H9390 Post Consultant Open 60,000.00 0.00 2021-06-04 2021-07-23 2021-08-13 2021-09-17 2022-03-16 Institutional Capacity Implementation implementation of the series Selection of webinars on the impact of the COVID 19 pandemic on statistical production in Africa ET-AUC-238214-CS-INDV / Selection of IT/Statistician to support AUC-STATAFRIC on Individual the management and i. Strengthening Pending IDA / H9390 Post Consultant Open 60,000.00 0.00 2021-06-04 2021-07-23 2021-08-13 2021-09-17 2022-03-16 implementation of the series Institutional Capacity Implementation Selection of webinars on the impact of the COVID 19 pandemic on statistical production in Africa Page 5 PROCUREMENT PLAN Project information: Sint Maarten Hospital Resiliency Project (P167532) Project Implementation agency: SMMC Date of the Procurement Plan: 09/14/2018 Period covered by this Procurement Plan: September 2018 to March 2020 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: [is applicable for those contracts identified in the Procurement Plan tables]; Works: [is applicable for those contracts identified in the Procurement Plan tables] Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations not Applicable. PROCUREMENT St Maarten : Sint Maarten Hospital Resiliency & Preparedness Project PLAN General Information Country: St Maarten Bank’s Approval Date of the Original Procurement Plan: 2018-10-02 2021-05-24 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P167532 GPN Date: Project Name: Sint Maarten Hospital Resiliency & Preparedness Project Loan / Credit No: TF / A8176, / SMMC Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned AN-SMMC-77512-CW-RFQ / Transition and Contingency Fire detection system, Request for Single Stage - One 2019-06- TF / A8176 Plan for Sint Maarten Medical Prior Open - International 150,000.00 115,357.00 Signed 2018-11-28 2019-02-01 2019-02-21 purchases and installation of Quotations Envelope 14 Center system Transition and Contingency AN-SMMC-78173-CW-DIR / 2018-11- TF / A8176 Plan for Sint Maarten Medical Prior Direct Selection Direct 300,000.00 265,807.00 Signed 2018-09-13 2018-09-13 2018-09-13 2018-07-24 Roof reinforcement 07 Center ESSENTIAL UPGRADES DOC Transition and Contingency 2019-06- CHAPTER 10 / Fiber Optic TF / A8176 Plan for Sint Maarten Medical Prior Direct Selection Direct 500,000.00 0.00 Canceled 2019-01-08 2019-01-13 2019-03-22 21 connection to SMMC Center AN-SMMC-99835-CW-DIR / Component 1: World Bank Building and launching of the 17,000,000.0 133,309,86 2023-04- TF / A8176 Prior Direct Selection Direct Signed 2019-02-08 2019-02-08 2019-02-08 2016-09-19 Contribution to INSO contract new hospital 0 5.00 03 with SMMC ESSENTIAL UPGRADES DOC Transition and Contingency Request for Single Stage - One 2020-06- CHAPTER SIX / expansion of TF / A8176 Plan for Sint Maarten Medical Post Open - National 60,000.00 0.00 Canceled 2020-01-18 2020-03-10 Quotations Envelope 13 Dialysis department Center AN-SMMC-77679-CW-RFB / Transition and Contingency Pending Request for Single Stage - One 2020-04- Upgrading OR Complex Phase TF / A8176 Plan for Sint Maarten Medical Post Open - National 125,000.00 0.00 Implementat 2019-11-05 2020-01-11 Quotations Envelope 18 1 - Expansion Center ion AN-SMMC-77501-CW-RFQ / Transition and Contingency Request for Single Stage - One 2020-05- Medical gas distribution sytem TF / A8176 Plan for Sint Maarten Medical Post Open - International 35,000.00 492,680.00 Signed 2019-10-30 2020-01-03 2020-10-13 Quotations Envelope 15 upgrading Center ESSENTIAL UPGRADES DOC Transition and Contingency CHAPTER 5 / Construction of 2019-11- TF / A8176 Plan for Sint Maarten Medical Post Direct Selection Direct 256,500.00 0.00 Canceled 2019-06-03 2019-06-20 2019-08-29 Additional Patient rooms 28 Center MedSurg AN-SMMC-78161-CW-RFB / Transition and Contingency Construction of 5 x Double Single Stage - One 2019-05- TF / A8176 Plan for Sint Maarten Medical Post Request for Bids Open - National 731,500.00 0.00 Canceled 2018-11-09 2018-11-19 2018-12-19 2019-01-18 2019-02-15 Patient Rooms and Support Envelope 16 Center Services Building AN-SMMC-78164-CW-RFQ / Transition and Contingency Pending Request for Single Stage - One 2019-05- Upgrade OR Complex Phase 3 TF / A8176 Plan for Sint Maarten Medical Post Open - International 125,000.00 0.00 Implementat 2018-11-30 2019-02-18 Quotations Envelope 03 - Floor, ceiling, etc. Center ion AN-SMMC-135079-CW-RFQ Transition and Contingency / Construction of 5 x Double Request for Single Stage - One 1,582,304.5 2020-07- TF / A8176 Plan for Sint Maarten Medical Post Open - International 731,500.00 Signed 2019-11-10 2020-01-19 2021-01-11 Patient Rooms & Support Quotations Envelope 8 02 Center Service Building AN-SMMC-177444-CW-RFP Transition and Contingency Request for Single Stage - Two 2020-10- / Hurricane facility for Covid- TF / A8176 Plan for Sint Maarten Medical Post Limited 600,000.00 559,500.00 Signed 2020-06-02 2020-05-25 2020-06-03 2020-05-25 2020-06-04 2020-06-04 2020-06-19 2020-06-11 2020-07-04 2020-06-23 Proposals Envelope 02 19 Care Center AN-SMMC-204963-CW-RFQ Transition and Contingency Request for Single Stage - One 2021-07- / Construction for Dialysis an TF / A8176 Plan for Sint Maarten Medical Post Open - National 527,500.00 783,000.00 Signed 2020-11-23 2021-01-22 2021-02-01 Quotations Envelope 21 Oncology expansion. Center AN-SMMC-78169-CW-RFB / Transition and Contingency Single Stage - One 2020-10- Construction of Care Complex TF / A8176 Plan for Sint Maarten Medical Post Request for Bids Open - International 810,000.00 0.00 Canceled 2020-01-17 2020-01-27 2020-03-02 2020-03-19 2020-04-23 Envelope 19 Expansion Center Transition and Contingency AN-SMMC-78172-CW-RFQ / Request for Single Stage - One 2020-09- TF / A8176 Plan for Sint Maarten Medical Post Open - International 40,000.00 0.00 Canceled 2020-05-25 2020-07-27 Execution Water Control Plan Quotations Envelope 25 Center AN-SMMC-78162-CW-RFQ / Transition and Contingency Request for Single Stage - One 2020-03- Improve General Facilities - TF / A8176 Plan for Sint Maarten Medical Post Open - National 130,000.00 0.00 Canceled 2019-11-23 2020-01-27 Quotations Envelope 29 Cashier / Main Patio Upgrade Center AN-SMMC-77689-CW-RFQ / Upgrading OR Complex phase Transition and Contingency 2. Installation of HVAC Single Stage - One 2020-05- TF / A8176 Plan for Sint Maarten Medical Post Request for Bids Open - International 375,000.00 0.00 Canceled 2019-11-11 2019-11-18 2019-12-18 2020-01-01 2020-02-05 system, upgrading of the Envelope 10 Center electrical installation OR, upgrading of medical gas OR. AN-SMMC-208157-CW-DIR / Transition and Contingency Hospital MEP installation 2021-07- TF / A8176 Plan for Sint Maarten Medical Post Direct Selection Direct 800,000.00 815,000.00 Signed 2020-12-04 2020-10-30 2020-12-09 2020-11-18 2021-01-13 2021-01-11 works for double patient 12 Center rooms and new OR complex. GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 1 AN-SMMC-98713-GO-RFQ / Supply and installation of a Transition and Contingency Request for Single Stage - One new autoclave grinder system TF / A8176 Plan for Sint Maarten Medical Post Open - International 250,000.00 0.00 Canceled 2019-03-07 2019-05-25 2019-08-03 Quotations Envelope for the treatment of our Center medical waste. AN-SMMC-78174-GO-RFQ / ICT upgrades - pro forma Transition and Contingency upload of activity - all sub Request for Single Stage - One TF / A8176 Plan for Sint Maarten Medical Post Open - International 350,000.00 299,836.00 Signed 2019-02-23 2019-04-20 2019-06-06 2020-03-23 activities will be uploaded Quotations Envelope Center separately in consultation with our ICT manager AN-SMMC-77520-GO-RFQ / Transition and Contingency Request for Single Stage - One Upgrading Access Control TF / A8176 Plan for Sint Maarten Medical Post Open - International 75,000.00 92,069.75 Signed 2019-02-17 2019-04-23 2019-04-26 2019-09-03 Quotations Envelope System Center Transition and Contingency AN-SMMC-78168-GO-RFQ / Request for Single Stage - One TF / A8176 Plan for Sint Maarten Medical Post Open - International 35,000.00 0.00 Canceled 2018-11-07 2019-01-18 2019-03-29 Generator Care Complex Quotations Envelope Center AN-SMMC-78167-GO-RFQ / Transition and Contingency Request for Single Stage - One Two Generators for SMMC - TF / A8176 Plan for Sint Maarten Medical Post Open - International 200,000.00 180,768.56 Signed 2018-11-07 2019-01-18 2019-07-19 2019-03-29 Quotations Envelope Main Building & Care Complex Center AN-SMMC-114142-GO-RFQ Transition and Contingency / Purchase of Furniture & Request for Single Stage - One TF / A8176 Plan for Sint Maarten Medical Post Open - International 250,000.00 0.00 Canceled 2019-11-20 2020-01-22 2020-04-21 Equipment for approved Quotations Envelope Center existing WB projects ESSENTIAL UPGRADES DOC Transition and Contingency Pending CHAPTER 6 / Purchase of TF / A8176 Plan for Sint Maarten Medical Post Direct Selection Direct 15,000.00 0.00 Implementati 2020-05-30 2020-06-13 2020-08-01 2020-11-04 Dialysis Equipment and Water Center on Loop AN-SMMC-114144-GO-DIR / Transition and Contingency Purchase of DELL Work TF / A8176 Plan for Sint Maarten Medical Post Direct Selection Direct 275,000.00 0.00 Canceled 2019-05-08 2019-09-23 2019-11-02 2019-11-22 Stations & Back-up Servers Center AN-SMMC-227327-GO-DIR / Justification for direct contracting for goods is based on: - Critical and urgent need Transition and Contingency Pending for medical supplies, TF / A8176 Plan for Sint Maarten Medical Post Direct Selection Direct 1,632,300.00 0.00 Implementati 2021-03-30 2021-04-04 2021-05-09 2021-11-05 equipment, and furniture, in Center on emergency response to the rapid increase of patients on island during Covid -19 Pandemic; NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual AN-SMMC-114141-CS-CQS / Preparation of bidding and Transition and Contingency Consultant permit documentation for 5 TF / A8176 Plan for Sint Maarten Medical Post Qualification Open - International 37,500.00 31,395.00 Signed 2019-05-08 2019-03-27 2019-05-09 2019-05-11 2019-04-25 2019-05-27 2019-06-09 2019-06-17 2019-06-02 2019-07-17 double patient rooms in Med- Center Selection Surg ward AN-SMMC-78171-CS-CQS / Transition and Contingency Consultant Consultancy Services to TF / A8176 Plan for Sint Maarten Medical Post Qualification Open - National 10,000.00 0.00 Canceled 2019-09-16 2019-10-07 2019-11-20 2019-12-09 2019-12-30 2020-02-07 realize Water Control Plan Center Selection INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual AN-SMMC-77526-CS-INDV / Individual Hiring Project Coordinator and Under / Project Management Prior Consultant Open 300,000.00 0.00 2018-09-01 2018-10-19 2018-10-26 2018-11-09 2019-12-31 Project Assistant as Implementation Selection employees. AN-SMMC-114139-CS-CDS / Consultancy services hired for Transition and Contingency PDO # 2,5,10 - Emergency TF / A8176 Plan for Sint Maarten Medical Post Direct Selection Direct 25,000.00 22,200.00 Signed 2019-05-08 2019-02-17 2019-05-10 2019-04-07 2019-05-13 2019-04-25 2019-08-11 Disaster & Preparedness Plan Center and Contingency Plan. AN-SMMC-78166-CS-QCBS / Design firm for Additional Patient rooms and care complex expansion - preferred to do by same Transition and Contingency engineer as new hospital TF / A8176 Plan for Sint Maarten Medical Post Direct Selection Direct 118,500.00 0.00 Canceled 2018-11-30 2018-12-07 2019-01-30 2019-04-30 project for realizing mock-up Center rooms and additional space in Care Complex that can be used well in combination with new hospital. AN-SMMC-208166-CS-CDS / Transition and Contingency COVID- 19 Pandemic support Under TF / A8176 Plan for Sint Maarten Medical Post Direct Selection Direct 250,000.00 0.00 2020-12-04 2021-01-12 2020-12-04 2020-11-27 2020-12-07 2021-06-05 staff, Medical, Administrative Implementation Center and Store Room Staff Page 2 PROCUREMENT PLAN (Textual Part) Project information: Cote d’Ivoire Electricity Transmission and Access Project(P157055) Project Implementation agency: CI-ENERGIES Date of the Procurement Plan: September 7, 2017 Period covered by this Procurement Plan: September 2017- December 2018 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements , such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing is not applicable. Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is not applicable. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable Works: is not applicable PROCUREMENT Cote d'Ivoire : Cote d'Ivoire - Electricity Transmission and Access Project PLAN General Information Country: Cote d'Ivoire Bank’s Approval Date of the Original Procurement Plan: 2017-09-25 2021-05-20 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P157055 GPN Date: 2017-08-23 Project Name: Cote d'Ivoire - Electricity Transmission and Access Project Loan / Credit No: IDA / 59990 C Executing Agency(ies): I-ENERGIES WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned CI-CI-ENERGIES-27208-CW- RFB / Construction du poste source 225/90/33/15 kV de Gagnoa Rehabilitation, lot 1: Travaux de création du Reinforcement, and Extension Single Stage - One 13,900,000.0 15,774,796. 2019-06- poste source IDA / 59990 of Distribution Systems in Prior Request for Bids Open - International Signed 2017-09-05 2017-09-19 2017-10-06 2017-10-31 2018-01-04 2017-11-30 2018-01-19 2018-01-04 2018-02-26 Envelope 0 66 28 lot 2: Travaux de création de Abidjan and 10 Regional l'entrée en coupure des ligne Capital cities 225 et 90 kV lot 3 : Télétransmission du poste source CI-CI-ENERGIES-27217-CW- RFB / Construction des postes sources 225/90kV de Yopougon 1, Treichville et Bia Rehabilitation, Sud Reinforcement, and Extension lot 1: Poste 225kV incluant 1 Single Stage - One 43,000,000.0 35,966,613. Under 2019-08- IDA / 59990 of Distribution Systems in Prior Request for Bids Open - International 2017-09-12 2017-11-08 2017-09-21 2018-02-11 2017-11-02 2018-04-17 2017-12-03 2019-01-24 2018-01-08 2019-01-21 transfo 225/90kV 100MVA Envelope 0 45 Review 05 Abidjan and 10 Regional lot 2: Poste 225kV incluant 2 Capital cities transfo 225/90kV 100MVA lot 3: Poste 225kV incluant 2 travées transfo 225/90kV 100MVA CI-CI-ENERGIES-30306-CW- RFB / Extension et Reinforcement of Single Stage - One 41,900,000.0 27,326,220. 2019-10- renforcement des réseaux de IDA / 59990 Prior Request for Bids Open - International Signed 2018-01-16 2018-02-20 2018-02-13 2018-02-21 2018-03-27 2018-04-18 2018-04-26 2019-01-24 2018-05-22 2019-01-23 Transmission Systems Envelope 0 21 16 distribution dans 10 chefs lieux de régions- 3 lots CI-CI-ENERGIES-30308-CW- RFB / Passage en souterrain de réseaux HTA aériens Reinforcement of Single Stage - One 40,000,000.0 Under 2020-03- d'Abidjan et remplacement IDA / 59990 Prior Request for Bids Open - International 0.00 2018-03-13 2018-12-19 2018-04-10 2019-01-10 2018-05-22 2018-06-21 2018-07-17 Transmission Systems Envelope 0 Review 25 des câbles HTA de type CPI en câble HTA de type CIS dans les DRAS et DRYOP - 3 lots CI-CI-ENERGIES-30313-CW- Rural Electrification and RFB / Travaux d'électrification Single Stage - One 15,700,000.0 2019-11- IDA / 59990 Support to Electricity for All Prior Request for Bids Open - International 0.00 Canceled 2018-03-13 2018-04-10 2018-05-22 2018-06-21 2018-07-17 de localités dans la région du Envelope 0 28 Program Gbôklè - 5 lots CI-CI-ENERGIES-30315-CW- Rural Electrification and RFB / Travaux d'électrification Single Stage - One 19,100,000.0 2019-11- IDA / 59990 Support to Electricity for All Prior Request for Bids Open - International 0.00 Canceled 2018-03-13 2018-04-10 2018-05-22 2018-06-21 2018-07-17 de localités dans la région du Envelope 0 26 Program Haut Sassandra - 5 lots CI-CI-ENERGIES-30316-CW- Rural Electrification and RFB / Travaux d'électrification Single Stage - One 15,000,000.0 2019-11- IDA / 59990 Support to Electricity for All Prior Request for Bids Open - International 0.00 Canceled 2018-03-13 2018-04-10 2018-05-22 2018-06-21 2018-07-17 de localités dans la région de Envelope 0 26 Program la Nawa - 5 lots CI-CI-ENERGIES-30317-CW- Rural Electrification and RFB / Travaux d'électrification Single Stage - One 18,600,000.0 2019-11- IDA / 59990 Support to Electricity for All Prior Request for Bids Open - International 0.00 Canceled 2018-03-13 2018-04-10 2018-05-22 2018-06-21 2018-07-17 de localités dans la région de Envelope 0 26 Program San Pédro - 5 lots CI-CI-ENERGIES-30548-CW- RFB / Fourniture et Installation de Rehabilitation, transformateurs à Kossou, Reinforcement, and Extension Ferké, Man, Abobo, Taabo et Single Stage - One 55,500,000.0 44,940,082. 2019-11- IDA / 59990 of Distribution Systems in Prior Request for Bids Open - International Signed 2018-01-16 2018-03-09 2018-02-12 2018-03-20 2018-03-26 2018-05-29 2018-04-25 2018-07-23 2018-05-22 2018-09-27 Renforcement et Sécurisation Envelope 0 83 26 Abidjan and 10 Regional des postes de Agboville, Capital cities Attakro, Ayamé, Bongo, Bouaké 1, Abengourou, Dabou, Daloa, Danané et Dimbokro Gagnoa - 4 lots CI-CI-ENERGIES-95225-CW- Rural Electrification and RFB / Travaux d'électrification Single Stage - One 15,700,000.0 2020-11- IDA / 59990 Support to Electricity for All Prior Request for Bids Open - International 0.00 Canceled 2019-04-24 2019-05-21 2019-07-10 2019-07-26 2019-08-23 rurale des localités dans la Envelope 0 15 Program région du Gboklê - 5 Lots CI-CI-ENERGIES-95232-CW- Rural Electrification and RFB / Travaux d'électrification Single Stage - One 18,600,000.0 2020-10- IDA / 59990 Support to Electricity for All Prior Request for Bids Open - International 0.00 Canceled 2019-03-26 2019-04-23 2019-06-12 2019-06-28 2019-07-26 des localités dans la région de Envelope 0 18 Program San Pédro- 5 lots CI-CI-ENERGIES-95234-CW- Rural Electrification and RFB / Travaux d'électrification Single Stage - One 19,100,000.0 13,630,277. 2020-10- IDA / 59990 Support to Electricity for All Prior Request for Bids Open - International Signed 2019-03-26 2019-03-31 2019-04-23 2019-04-04 2019-06-12 2019-05-21 2019-06-28 2019-11-12 2019-07-26 2020-01-09 des localités dans la région du Envelope 0 91 18 Program Haut- Sassandra- 5 lots CI-CI-ENERGIES-95236-CW- Rural Electrification and RFB / Travaux d'électrification Single Stage - One 15,000,000.0 11,691,486. 2020-08- IDA / 59990 Support to Electricity for All Prior Request for Bids Open - International Signed 2019-01-23 2019-01-29 2019-02-19 2019-02-04 2019-04-10 2019-03-26 2019-04-26 2019-06-06 2019-05-24 2019-08-27 des localités dans la région de Envelope 0 30 16 Program la Nawa- 5 lots Page 1 CI-CI-ENERGIES-168080-CW- RFQ / Electrification des localités de Bolorouko, Diomandé carrefour, Leledou, Louloudou, Zuzuoko, Rural Electrification and Request for Single Stage - One 2021-09- Zakareko et Yakassé, IDA / 59990 Support to Electricity for All Post Limited 3,900,000.00 0.00 Canceled 2020-04-15 2020-04-17 2020-06-10 Quotations Envelope 03 Dassioko et Kpata Abidou, Program Gbabililié/Kroukrou(Yoberi), Grogbaledou, Mahamankro, Wawakro, Wawapéko,Zakpberi et Zériberi CI-CI-ENERGIES-168081-CW- RFQ / Electrification des localités de Gnago I et Gnago Rural Electrification and Request for Single Stage - One 2021-07- II, Tripoko, Gnégrouboué, IDA / 59990 Support to Electricity for All Post Limited 3,600,000.00 0.00 Canceled 2020-04-15 2020-04-17 2020-06-10 Quotations Envelope 05 Gobroko, Bolo V1, Bolo V2, Program Bolo V3, Boutoubré I et Zégréboué CI-CI-ENERGIES-168083-CW- RFQ / Construction des lignes MT/BT Gaoulou-Grihiri et Rural Electrification and Request for Single Stage - One 2021-09- Beyo-PK 31 et électrification IDA / 59990 Support to Electricity for All Post Limited 4,100,000.00 0.00 Canceled 2020-04-15 2020-06-10 Quotations Envelope 03 des localités de Grihiri, Program Godekro, Tiazalé, Vodieko, Lohiri (Godiè) et Madinatché CI-CI-ENERGIES-168085-CW- RFQ / Electrification des Rural Electrification and Request for Single Stage - One 2021-06- localités de Balokouya, IDA / 59990 Support to Electricity for All Post Limited 2,100,000.00 0.00 Canceled 2020-04-15 2020-04-17 2020-06-10 Quotations Envelope 05 Gréguibré I, Lobakuya, Medon Program et Zaebré CI-CI-ENERGIES-168086-CW- RFQ / Electrification des Rural Electrification and Request for Single Stage - One 2021-09- localités de Labakuya, Lossan IDA / 59990 Support to Electricity for All Post Limited 2,000,000.00 0.00 Canceled 2020-04-15 2020-04-17 2020-06-10 Quotations Envelope 03 Kouamekro, Pauly brousse, Program Sahoua et Sialloukro CI-CI-ENERGIES-168087-CW- RFQ / Electrification des localité de Djimimbo, Gliké- Rural Electrification and Est, Iratéké, Trahé, Mani Request for Single Stage - One 2021-06- IDA / 59990 Support to Electricity for All Post Limited 3,700,000.00 0.00 Canceled 2020-05-06 2020-07-01 Béréby, Iboké, Grélé, Néro- Quotations Envelope 26 Program Brousse, ouro, Pataké, Grélelon et Roc douGbalél/Roc Oulidié/ SUF CI-CI-ENERGIES-168088-CW- RFQ / Electrification des Rural Electrification and localités de Baba, Dimoulé, Request for Single Stage - One 2021-06- IDA / 59990 Support to Electricity for All Post Limited 4,700,000.00 0.00 Canceled 2020-05-06 2020-07-01 Taboké, Waté, Dagadji, Quotations Envelope 26 Program Djapadji, Gagny, Gnepasso, Dahoro, Gligbeuadji et Goh CI-CI-ENERGIES-168089-CW- RFQ / Electrification des localités de Blahou, Kpoté, Rural Electrification and petit Pedro, Kounouko, Ligne Request for Single Stage - One 2021-09- IDA / 59990 Support to Electricity for All Post Limited 3,700,000.00 0.00 Canceled 2020-05-06 2020-07-01 Gabiadji-san Pédro, Quotations Envelope 24 Program Monogaga, Bloho, Gnity cailloux, Gnaké, Touih et Touré Dougou/SUF CI-CI-ENERGIES-168090-CW- RFQ / Electrification des localités de Soumahorodougou, Rural Electrification and Request for Single Stage - One 2021-06- Cantondougou, Pont Bascule, IDA / 59990 Support to Electricity for All Post Limited 4,300,000.00 0.00 Canceled 2020-05-06 2020-07-01 Quotations Envelope 26 Béoué, Karie, Nekawuinho Program (Neka village), Petit Grabo, Poutou, Youkou, Néro village, petit Guiglo, Podoué et Soto CI-CI-ENERGIES-168091-CW- RFQ / Electrification des localités de Blidouba, Dapo Rural Electrification and Request for Single Stage - One 2021-06- Iboké, Dégné, Déhé, Georges- IDA / 59990 Support to Electricity for All Post Limited 2,200,000.00 0.00 Canceled 2020-05-06 2020-07-01 Quotations Envelope 26 Town, Gnénaholoké, Néro V1 Program et Nero V2, Niplou et tépo Iboké/ SUF CI-CI-ENERGIES-178152-CW- RFB / Electrification des localités de Bolorouko, Diomandé carrefour, Leledou, Louloudou, Zuzuoko, Rural Electrification and Single Stage - One 2,910,065.8 2021-10- Zakareko et Yakassé, IDA / 59990 Support to Electricity for All Post Request for Bids Open - National 3,900,000.00 Signed 2020-06-16 2020-06-16 2020-06-23 2020-06-24 2020-07-23 2020-07-17 2020-08-13 2020-08-27 2020-08-27 2020-11-03 Envelope 6 21 Dassioko et Kpata Abidou, Program Gbabililié/Kroukrou(Yoberi), Grogbaledou, Mahamankro, Wawakro, Wawapéko,Zakpberi et Zériberi CI-CI-ENERGIES-178153-CW- RFB / Electrification des localités de Gnago I et Gnago Rural Electrification and Single Stage - One 2,743,732.9 2021-08- II, Tripoko, Gnégrouboué, IDA / 59990 Support to Electricity for All Post Request for Bids Open - National 3,600,000.00 Signed 2020-06-16 2020-06-16 2020-06-23 2020-06-24 2020-07-23 2020-07-17 2020-08-13 2020-08-27 2020-08-27 2020-11-03 Envelope 1 22 Gobroko, Bolo V1, Bolo V2, Program Bolo V3, Boutoubré I et Zégréboué CI-CI-ENERGIES-178156-CW- RFB / Construction des lignes MT/BT Gaoulou-Grihiri et Rural Electrification and Single Stage - One 2,915,531.2 2021-10- Beyo-PK 31 et électrification IDA / 59990 Support to Electricity for All Post Request for Bids Open - National 4,100,000.00 Signed 2020-06-16 2020-06-16 2020-06-23 2020-06-24 2020-07-23 2020-07-17 2020-08-13 2020-08-27 2020-08-27 2020-11-03 Envelope 9 21 des localités de Grihiri, Program Godekro, Tiazalé, Vodieko, Lohiri (Godiè) et Madinatché CI-CI-ENERGIES-178157-CW- RFB / Electrification des Rural Electrification and Single Stage - One 1,466,529.3 2021-08- localités de Balokouya, IDA / 59990 Support to Electricity for All Post Request for Bids Open - National 2,100,000.00 Terminated 2020-06-16 2020-06-16 2020-06-23 2020-06-24 2020-07-23 2020-07-17 2020-08-13 2020-08-27 2020-08-27 2020-11-03 Envelope 4 22 Gréguibré I, Lobakuya, Medon Program et Zaebré Page 2 CI-CI-ENERGIES-178159-CW- RFB / Electrification des Rural Electrification and Single Stage - One 1,532,244.1 2021-08- localités de Labakuya, Lossan IDA / 59990 Support to Electricity for All Post Request for Bids Open - National 2,000,000.00 Terminated 2020-06-16 2020-06-16 2020-06-23 2020-06-24 2020-07-23 2020-08-27 2020-08-13 2020-08-27 2020-08-27 2020-11-03 Envelope 6 22 Kouamekro, Pauly brousse, Program Sahoua et Sialloukro CI-CI-ENERGIES-178161-CW- RFB / Electrification des localité de Djimimbo, Gliké- Rural Electrification and Est, Iratéké, Trahé, Mani Single Stage - One 257,870,66 2021-10- IDA / 59990 Support to Electricity for All Post Request for Bids Open - National 3,700,000.00 Terminated 2020-06-23 2020-06-30 2020-06-30 2020-07-09 2020-07-30 2020-08-18 2020-08-20 2020-12-03 2020-09-03 2021-03-04 Béréby, Iboké, Grélé, Néro- Envelope 3.61 28 Program Brousse, ouro, Pataké, Grélelon et Roc douGbalél/Roc Oulidié/ SUF CI-CI-ENERGIES-178164-CW- RFB / Electrification des Rural Electrification and localités de Baba, Dimoulé, Single Stage - One 2,930,439.7 2021-08- IDA / 59990 Support to Electricity for All Post Request for Bids Open - National 4,700,000.00 Signed 2020-06-23 2020-06-30 2020-06-30 2020-07-09 2020-07-30 2020-08-18 2020-08-20 2020-12-03 2020-09-03 2021-03-16 Taboké, Waté, Dagadji, Envelope 0 29 Program Djapadji, Gagny, Gnepasso, Dahoro, Gligbeuadji et Goh CI-CI-ENERGIES-178165-CW- RFB / Electrification des localités de Blahou, Kpoté, Rural Electrification and petit Pedro, Kounouko, Ligne Single Stage - One 2,417,694.6 2021-10- IDA / 59990 Support to Electricity for All Post Request for Bids Open - National 3,700,000.00 Signed 2020-06-23 2020-06-30 2020-06-30 2020-07-09 2020-07-30 2020-08-18 2020-08-20 2020-12-03 2020-09-03 2021-03-09 Gabiadji-san Pédro, Envelope 9 28 Program Monogaga, Bloho, Gnity cailloux, Gnaké, Touih et Touré Dougou/SUF CI-CI-ENERGIES-178166-CW- RFB / Electrification des localités de Soumahorodougou, Rural Electrification and Single Stage - One 1,626,547.9 2021-08- Cantondougou, Pont Bascule, IDA / 59990 Support to Electricity for All Post Request for Bids Open - National 4,300,000.00 Signed 2020-06-23 2020-06-30 2020-06-30 2020-07-09 2020-07-30 2020-08-18 2020-08-20 2020-12-14 2020-09-03 2021-03-16 Envelope 5 29 Béoué, Karie, Nekawuinho Program (Neka village), Petit Grabo, Poutou, Youkou, Néro village, petit Guiglo, Podoué et Soto CI-CI-ENERGIES-178168-CW- RFB / Electrification des localités de Blidouba, Dapo Rural Electrification and Single Stage - One 1,251,188.0 2021-08- Iboké, Dégné, Déhé, Georges- IDA / 59990 Support to Electricity for All Post Request for Bids Open - National 2,200,000.00 Signed 2020-06-23 2020-06-30 2020-06-30 2020-07-09 2020-07-30 2020-08-18 2020-08-20 2020-12-14 2020-09-03 2021-02-26 Envelope 0 29 Town, Gnénaholoké, Néro V1 Program et Nero V2, Niplou et tépo Iboké/ SUF CI-CI-ENERGIES-189370-CW- DIR / Passage en 225 kV du Rural Electrification and 1,720,403.5 2021-07- poste de Bia Sud: Collecte et IDA / 59990 Support to Electricity for All Prior Direct Selection Direct 1,700,000.00 Signed 2020-08-24 2020-09-09 2020-08-31 2020-09-25 2020-09-26 2020-10-21 5 23 transfert des terres et eaux Program polluées aux micropolluants GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Strengthening Institutional CI-CI-ENERGIES-30322-GO- Capacity of the Electricity Request for Single Stage - One RFQ / Acquisition et entretien IDA / 59990 Post Limited 862,000.00 724,363.68 Completed 2017-09-27 2017-09-25 2017-11-03 2017-10-30 2017-12-20 2017-12-23 Sector and Project Quotations Envelope de véhicules Management CI-CI-ENERGIES-30325-GO- Strengthening Institutional RFQ / Acquisition de Camion Capacity of the Electricity Request for Single Stage - One IDA / 59990 Post Limited 400,000.00 0.00 Canceled 2018-01-10 2018-02-22 2018-04-10 Labo y compris formation et Sector and Project Quotations Envelope pièces de réchanges Management CI-CI-ENERGIES-95231-GO- RFB / Passage en souterrain de réseaux HTA aériens et Reinforcement of Single Stage - One IDA / 59990 Prior Request for Bids Open - International 40,000,000.00 44,302,794.00 Signed 2019-01-17 2019-01-17 2019-02-26 2019-02-26 2019-03-14 2019-03-19 2019-04-18 2019-04-19 2020-12-08 remplacement des câbles HTA Transmission Systems Envelope de type CPI en CIS dans la ville d'Abidjan - 3 lots CI-CI-ENERGIES-95240-GO- Strengthening Institutional RFQ / Acquisition du camion Capacity of the Electricity Request for Single Stage - One IDA / 59990 Post Limited 400,000.00 0.00 Canceled 2019-01-29 2019-02-11 2019-03-13 2019-07-11 labo y compris formation et Sector and Project Quotations Envelope pièce de réchange Management CI-CI-ENERGIES-95242-GO- Strengthening Institutional RFQ / Acquisition Capacity of the Electricity Request for Single Stage - One IDA / 59990 Post Limited 300.00 0.00 Canceled 2019-01-28 2019-03-07 2019-04-22 d'instruments de mesures et Sector and Project Quotations Envelope de controle- 2 Lots Management CI-CI-ENERGIES-95244-GO- Strengthening Institutional RFQ / Acquisition de materiel Capacity of the Electricity Request for Single Stage - One IDA / 59990 Post Limited 8,500.00 0.00 Canceled 2019-01-22 2019-02-14 2019-03-01 informatique, de bureau et Sector and Project Quotations Envelope consommables informatiques Management Strengthening Institutional CI-CI-ENERGIES-146023-GO- Capacity of the Electricity DIR / FOURNITURES DE DEUX IDA / 59990 Post Direct Selection Direct 601,000.00 585,667.64 Signed 2019-11-25 2019-06-24 2019-11-30 2019-06-24 2020-01-04 2019-12-04 2020-08-31 2020-08-13 Sector and Project CAMIONS LABORATOIRE Management Rehabilitation, CI-CI-ENERGIES-239558-GO- Reinforcement, and Extension Single Stage - One RFB / Acquisition de trente- IDA / 59990 of Distribution Systems in Prior Request for Bids Open - International 26,135,000.00 0.00 Under Review 2021-06-17 2021-06-27 2021-08-10 2021-08-31 2021-10-05 2022-08-01 Envelope trois (33) transformateurs Abidjan and 10 Regional Capital cities NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 3 CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CI-CI-ENERGIES-22356-CS- QCBS / Ingénieurs-Conseils pour le contrôle et la Strengthening Institutional surveillance des travaux de Capacity of the Electricity Quality And Cost- IDA / 59990 Prior Open - International 8,300,000.00 0.00 Canceled 2017-09-05 2017-09-12 2017-09-28 2017-10-09 2018-02-11 2017-11-21 2018-02-27 2017-12-12 2018-03-19 2017-12-21 2018-01-25 2019-08-31 transport, distribution et Sector and Project Based Selection électrification rurale - Lot 1: Management Transport- Distribution et Lot 2: Électrification rurale CI-CI-ENERGIES-222501-CS- QCBS / Ingenieurs-Conseils pour le contrôle et la Strengthening Institutional surveillance des travaux de Capacity of the Electricity Quality And Cost- IDA / 59990 Prior Open - International 4,700,000.00 0.00 Under Review 2021-03-03 2021-03-08 2021-03-17 2021-03-09 2021-04-30 2021-05-28 2021-06-27 2021-08-01 2021-09-05 2023-02-27 transport, distribution et Sector and Project Based Selection électrification rurale: Contrôle Management et surveillance des travaux de Transport et de Distribution CI-CI-ENERGIES-220229-CS- QCBS / Ingenieurs-Conseils pour le contrôle et la Strengthening Institutional surveillance des travaux de Capacity of the Electricity Quality And Cost- IDA / 59990 Prior Open - International 4,700,000.00 0.00 Canceled 2021-02-17 2021-02-24 2021-03-03 2021-04-16 2021-05-14 2021-06-13 2021-07-18 2021-08-22 2023-04-14 transport, distribution et Sector and Project Based Selection électrification rurale: Management Contrôle et surveillance des travaux de Transport et de Distribution CI-CI-ENERGIES-220225-CS- QCBS / Ingenieurs-Conseils pour le contrôle et la Strengthening Institutional surveillance des travaux de Capacity of the Electricity Quality And Cost- IDA / 59990 Prior Open - International 3,600,000.00 0.00 Canceled 2021-02-17 2021-02-24 2021-03-03 2021-04-16 2021-05-14 2021-06-13 2021-07-18 2021-08-22 2022-08-22 transport, distribution et Sector and Project Based Selection électrification rurale- Contrôle Management te surveillance des travaux d'Electrification Rurale CI-CI-ENERGIES-226512-CS- QCBS / Ingenieurs-Conseils pour le contrôle et la Strengthening Institutional surveillance des travaux de Capacity of the Electricity Quality And Cost- IDA / 59990 Prior Open - International 4,700,000.00 9,207,945.13 Signed 2017-09-05 2021-03-31 2017-09-26 2017-11-09 2017-12-07 2018-03-27 2018-01-06 2021-03-31 2018-02-10 2021-03-31 2018-03-17 2018-08-23 2019-03-17 transport, distribution et Sector and Project Based Selection électrification rurale- Contrôle Management et surveillance des travaux de Transport et de Distribution CI-CI-ENERGIES-226514-CS- QCBS / Ingenieurs-Conseils pour le contrôle et la Strengthening Institutional surveillance des travaux de Capacity of the Electricity Quality And Cost- IDA / 59990 Post Open - International 3,600,000.00 3,003,233.06 Signed 2017-09-05 2017-08-21 2017-09-26 2017-11-09 2018-01-23 2017-12-07 2018-02-27 2018-01-06 2018-03-12 2018-02-10 2018-06-18 2018-03-17 2018-07-31 2019-03-17 transport, distribution et Sector and Project Based Selection électrification rurale- Contrôle Management te surveillance des travaux d'Electrification Rurale CI-CI-ENERGIES-222502-CS- QCBS / Ingenieurs-Conseils pour le contrôle et la Strengthening Institutional surveillance des travaux de Capacity of the Electricity Quality And Cost- IDA / 59990 Post Open - International 3,600,000.00 0.00 Canceled 2021-03-03 2021-03-08 2021-03-17 2021-04-30 2021-05-28 2021-06-27 2021-08-01 2021-09-05 2023-04-28 transport, distribution et Sector and Project Based Selection électrification rurale: Contrôle Management te surveillance des travaux d'Electrification Rurale INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Strengthening Institutional CI-CI-ENERGIES-95249-CS- Capacity of the Electricity CDS / Audit comptable et IDA / 59990 Prior Direct Selection Direct 93,000.00 99,106.06 Signed 2019-01-23 2019-01-28 2018-10-08 2019-02-11 2019-05-13 2019-03-01 Sector and Project financier du projet Management CI-CI-ENERGIES-95251-CS- Strengthening Institutional INDV / Consultant individuel Individual Capacity of the Electricity court-terme en appui au IDA / 59990 Post Consultant Limited 10,500.00 10,144.86 Signed 2019-01-21 2019-02-05 2019-01-26 2019-02-08 2019-02-06 2019-04-03 2019-02-15 2019-04-03 2019-02-15 Sector and Project spécialiste genre et Selection Management développement social. CI-CI-ENERGIES-146017-CS- Strengthening Institutional INDV / Recrutement d'un Individual Capacity of the Electricity Consultant International en IDA / 59990 Post Consultant Limited 75,000.00 112,900.00 Completed 2019-11-20 2019-11-28 2019-11-25 2019-11-29 2019-12-16 2020-01-09 2020-01-20 2020-01-30 2021-01-19 2020-09-30 Sector and Project Appui à la Mise en Œuvre des Selection Management Sauvegardes CI-CI-ENERGIES-157500-CS- Strengthening Institutional Individual INDV / Recrutement d'un Capacity of the Electricity IDA / 59990 Post Consultant Limited 50,000.00 1,520.45 Signed 2020-02-06 2020-01-28 2020-02-20 2020-03-19 2020-02-27 2020-04-29 2020-03-08 2020-05-14 2020-07-06 assistant en passation de Sector and Project Selection marchés Management CI-CI-ENERGIES-174199-CS- CDS / Recrutement d'une firme (Hydrogen) en vue de la Strengthening Institutional réalisation du CIES du Projet Capacity of the Electricity de fourniture, d’installation, IDA / 59990 Post Direct Selection Direct 55,000.00 48,057.22 Completed 2020-05-22 2020-06-16 2020-06-01 2020-06-16 2020-06-15 2020-07-06 2020-07-15 2020-12-06 Sector and Project de systèmes de stockage Management d'énergie par batteries 300 MWh & des équipements de synchronisation Page 4 CI-CI-ENERGIES-207215-CS- INDV / Consultant International en appui technique à la mise en œuvre Strengthening Institutional Individual des sauvegardes Capacity of the Electricity IDA / 59990 Post Consultant Direct 108,950.00 108,950.00 Signed 2020-11-30 2020-11-17 2020-12-04 2020-11-17 2020-12-09 2020-11-30 2020-12-19 2020-12-17 2021-12-14 environnementales et Sector and Project Selection sociales, santé et sécurité au Management travail, gestion des plaintes et aspects genre et vulnérabilité dans le cadre du projet CI-CI-ENERGIES-207228-CS- INDV / Recrutement d'un(e) Strengthening Institutional consultant(e) pour Individual Capacity of the Electricity Pending l'élaboration du CIES du projet IDA / 59990 Post Consultant Direct 52,000.00 0.00 2020-12-02 2020-12-14 2020-12-28 2021-01-11 2021-02-10 Sector and Project Implementation de construction et de Selection Management restructuration du réseau HTA de Gagnoa CI-CI-ENERGIES-207241-CS- Strengthening Institutional Individual INDV / Recrutement d'un(e) Capacity of the Electricity IDA / 59990 Post Consultant Limited 86,200.00 3,605.88 Signed 2020-11-30 2020-06-12 2020-12-05 2020-06-18 2020-12-26 2020-11-18 2021-01-30 2020-11-26 2022-12-31 spécialiste en Développement Sector and Project Selection Social et Genre Management CI-CI-ENERGIES-207252-CS- Strengthening Institutional Individual INDV / Recrutement d'un(e) Capacity of the Electricity IDA / 59990 Post Consultant Limited 86,200.00 3,577.22 Signed 2020-11-30 2020-07-03 2020-12-05 2020-06-18 2020-12-26 2020-12-08 2021-01-30 2020-12-08 2022-12-31 spécialiste en sauvegarde Sector and Project Selection environnemental Management CI-CI-ENERGIES-215321-CS- CDS / Contrat avec EDF CI pour le contrôle, la supervision , la surveillance Reinforcement of IDA / 59990 Prior Direct Selection Direct 3,300,000.00 0.00 Canceled 2021-01-25 2021-01-29 2021-03-01 2022-06-24 et le suivi environnemental et Transmission Systems social des ouvrages de Transport et Distribution du PTDAE CI-CI-ENERGIES-207236-CS- INDV / Recrutement d'un(e) Strengthening Institutional consultant(e) pour Individual Capacity of the Electricity l'actualisation du PAR de la IDA / 59990 Post Consultant Direct 34,500.00 0.00 Canceled 2020-12-03 2020-12-15 2021-01-05 2021-01-19 2021-02-18 Sector and Project DRAS dans le cadre du Selection Management passage en souterrain de câbles CI-CI-ENERGIES-207232-CS- INDV / Recrutement d'un(e) Strengthening Institutional consultant(e) pour Individual Capacity of the Electricity l'élaboration du PAR du projet IDA / 59990 Post Consultant Direct 43,000.00 0.00 Canceled 2020-12-03 2020-12-15 2021-01-05 2021-01-19 2021-02-18 Sector and Project de construction et de Selection Management restructuration du réseau HTA de Gagnoa CI-CI-ENERGIES-207238-CS- INDV / Recrutement d'un(e) Strengthening Institutional consultant(e) pour Individual Capacity of the Electricity l'actualisation du CIES de la IDA / 59990 Post Consultant Direct 43,000.00 0.00 Canceled 2020-12-03 2020-12-15 2021-01-05 2021-01-19 2021-02-18 Sector and Project DRAS dans le cadre du Selection Management passage en souterrain de câbles CI-CI-ENERGIES-157499-CS- INDV / RECRUTEMENT D’UN(E) CONSULTANT(E) INDIVIDUEL(LE) CHARGE(E) DE L’ELABORATION DU PLAN Strengthening Institutional Individual D’ACTION DE Capacity of the Electricity IDA / 59990 Post Consultant Limited 44,000.00 0.00 Canceled 2020-02-06 2020-01-02 2020-02-11 2020-03-03 2020-04-07 2021-04-07 REINSTALLATION (PAR) Sector and Project Selection PERSONNES AFFECTEES PAR Management LES TRAVAUX DE CONNEXION DU NOUVEAU POSTE DE GAGNOA AU CHEF-LIEU DE REGION DU GOH Page 5 World Bank Assisted National Agricultural Higher Education Project Education Division Indian Council of Agricultural Research Government of India Procurement Plan (Ist Phase – 18 months ) From : May 2017 to Sept.,2018 1 2 I. General 1. Project information Country : India Borrower : Government of India Project Name : NATIONAL AGRICULTURAL HIGHER EDUCATION PROJECT (NAHEP) Project Identification No (ID) : P151072 : -- Project Implementing Agency (PIA): ICAR and all participating Agriculture Universities 2. Bank’s approval Date of the Initial Procurement Plan: 4. Date of General Procurement Notice: 16th December 2016 Period covered by this procurement plan: First 18 months of the project i.e April, 2017 to Sept., 2018 5. Applicable Bank Guideline: a) For Goods ,Works and Non-consulting Services :"Guidelines: Procurement of Goods, Works and Non-Consulting Services under IBRD Loans and IDA Credits & Grants by World Bank Borrowers" dated January 2011 (Procurement Guidelines) and revised July 2014; and b) For Consultancy Services :"Guidelines: Selection and Employment of Consultants under IBRD Loans and IDA Credits & Grants by World Bank Borrowers" dated January 2011 (Consultant Guidelines) and revised July 2014; 3 II. Goods, Works and Non-Consulting Services Category Method of Threshold (US$ Prior review Procurement Equivalent) threshold Goods and International Contracts more than All contracts Non- competitive the equivalent of equal to consulting Bidding (ICB) US$ 3 million per or greater than US$2 services(ex contract million equivalent; cluding TI Limited As per para 3.2 of the contracts) International Guideline , all Bidding Contracts more than the equivalent of US $ 100,000 per contract National Contracts more than competitive the equivalent of US$ Bidding (NCB) 100,000 but less than the equivalent of US$ 3 million per contract (with NCB conditions) Shopping ** Up to $100,000 Direct As per para 3.7 of Contracting(DC) Guidelines Community# As per para 3.19 of Participation the guideline Force Account As per para 3.9 of Guidelines Framework As per para 3.6 of Agreements(FA) Guidelines Works ICB Civil works more or All contracts equal to or equivalent of greater than US$10 US$40,000,000 per million equivalent contract NCB Civil works more than 100,000 and upto $40,000,000 (with NCB conditions) Shopping Civil works up to $100,000 DC As per para 3.7 of Guidelines Community As per para 3.19 of participation# the guideline Force Account As per para 3.9 of Guidelines 4 Category Method of Threshold (US$ Prior review Procurement Equivalent) threshold Consultant CQS/LCS Contracts Up to All contracts equal to or s’ Services $300,000 or less per greater than US$1 contract Million equivalent for Single source As per para 3.9-3.11 firms; and equal to or selection (SSS) of Guidelines greater than Individual As per Section V of US$300,000 equivalent contracts Guidelines for individuals QCBS/QBS/FBS for all other cases (i) International >$800,000 shortlist (ii) Shortlist may Up to $800,000 comprise national consultants only * If a transaction comprises several contracts, lots or slices, the aggregate estimated value of all contracts, lots or slices will determine the applicable threshold amount. **State Rate Contracts cannot be used at par with Shopping. If state rate contract exists for an item, the same can be considered as one of the 3 quotations to be sought under shopping procedures. However DGS&D rate contracts are acceptable under any procurement under the Shopping procedure # Community Procurement would be applicable to activities under learning/training pilots It would be based on World Bank “Guidance Note For Management of Procurement Responsibilities In Community-Driven Development Projects dated December 2009 and as included in the Procurement manual. 2. Pre-qualification: Not Applicable 3. Reference to Project Procurement Manual: A Procurement Manual based on World Bank Guidelines “Procurement of Goods, Works, and Non-Consulting Services under IBRD Loans and IDA Credits & Grants by World Bank Borrowers, January 2011,Revised July 2014”and “Selection and Employment of Consultants under IBRD Loans and IDA Credits and Grants by World Bank Borrowers” has been prepared. All procurements in the project will be governed by the procedures described in the Manual. In case of any inconsistency between the Procurement Manual and the World Bank Guidelines 2011, Revised July 2014, the provisions of the Guidelines shall prevail. 4. Any Other Special Procurement Arrangements (Goods & Works) : A. Contracts procured in advance will be financed under retroactive financing within the specified limits, as agreed to in the Credit Agreement provided 5 they are procured in accordance with agreed processes and procedures for the project and have been cleared as part of procurement plan. B. National Competitive Bidding (NCB) method for procurement of goods, works and non-consulting services as per the above value thresholds will be conducted in accordance with paragraph 3.3 and 3.4 of the World Bank Procurement Guidelines and the following provisions: (i) Only the model bidding documents for NCB agreed with the GOI Task Force (and as amended for time to time), shall be used for bidding; (ii) Invitations to bid shall be advertised in at least one widely circulated national daily newspaper (or on a widely used website or electronic portal with free national and international access ) along with an abridged version of the said advertisement published in a widely circulated national daily inter-alia giving the website/electronic portal details from which the details of the invitation to bid can be downloaded), at least 30 days prior to the deadline for the submission of bids; (iii) No special preference will be accorded to any bidder either for price or for other terms and conditions when competing with foreign bidders, state-owned enterprises, small-scale enterprises or enterprises from any given State. (iv) Except with the prior concurrence of the Bank, there shall be no negotiation of price with the bidders, even with the lowest evaluated bidder; (v) Extension of bid validity shall not be allowed with reference to contracts subject to prior review without the prior concurrence of the World Bank (i) for the first request for extension if it is longer than four weeks; and (ii) for prior approved packages, all subsequent requests for extension irrespective of the period. (Such concurrence will be considered by the Bank only in cases of Force Majeure and circumstances beyond the control of the Purchaser/Employer); (vi) Re-bidding shall not be carried out with reference to Contracts subject to Bank prior review without the prior concurrence of the Bank. (vii) The system of rejecting bids outside a pre-determined margin or "bracket" of prices shall not be used in the project. (viii) Rate contracts entered into by Directorate General of Supplies and Disposals will not be acceptable as a substitute for NCB procedures unless agreed with the Bank on case to case basis. Such contracts will be acceptable however for any procurement under the Shopping procedures. (ix) Two or three envelop system will not be used (except when using e- Procurement system assessed and agreed by the Bank). 6 (x) As per 1.1(e) of World Bank Procurement Guidelines, the Association’s right to inspect accounts and records of the bidders, suppliers and contractors will be included in the bidding document. 7 Selection of Consultants 1. Methods and Value thresholds for Consultancy Services Consulting Methods Value Review Arrangements Services Threshold* Consulting i) Quality and Cost Services Based Selection (Firms) (QCBS) ii) Quality Based Selection (QBS) iii) Selection based on a Fixed Budget (FBS) iv) Selection Based on Least Cost First QCBS Contract Basis (LCS) irrespective of value and v) (Selection based Contracts all subsequent on Consultant’s estimated to cost consultancy contracts Qualification equivalent of valued above US$ 1 (CQS) US$ 200,000 or Million will be subject to less per contract. Prior Review by the World Bank. All other contracts vi) Single Source As per the provisions of will be subject to post Selection (SSS)# paragraph 3.8 to review. 3.11 of Consultant Guidelines Individual i) Competitive As per the Consultants Selection provisions of paragraph 5.1 to 5.6 of Consultant Guidelines ii) Single Source As per the Selection (SSS) provisions of paragraph 5.1 and 5.3 to 5.6 of Consultant Guidelines * If a transaction comprises several packages, lots or slices, the aggregate estimated value of contracts will determine the applicable threshold amount. # Irrespective of contract value any hiring of Government or Research Institutes of unique and exceptional nature requires prior no objection of the World Bank on case to case basis. 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than US $800,000 equivalent per 8 contract, may comprise entirely of national consultants in accordance with the provisions of Para 2.7 the World Bank Consultant Guidelines. 3. Any Other Special Selection Arrangements (Consulting Services) : (a) Contracts procured in advance will be financed under retroactive financing within the specified limits, as agreed to in the Credit Agreement provided procurement is in accordance with agreed processes and procedures for the project. (b) Requests for Expression of Interest (REOI) for assignments expected to cost more than US$ 300,000 shall be advertised in UNDB online in accordance with Para 2.5 of the Consultant Guidelines. With respect to each contract for the employment of individual consultants estimated to cost the equivalent of US $ 30,000 or more, the qualifications, experience, terms of reference and terms of employment of the consultants shall be furnished to the World Bank for its prior review and No Objection iv) Implementing Agency Capacity Building Activities with Time Schedule S. Expected outcome / Start Date Comments No. Activity Description 1 Training in World Bank To familiarise the online STEP system procurement official in Immediate regard to electronic submissions to the Bank. 2 Trainings in Bank To make procurement Within 3 Procurement at ASCI Officials from participating months of AU’s familiar with WB the procurement procedures negotiations 3 Customized training for Based on the learning from all selected official at PIU the project and hands on Within 3 and selected AU’s. experience a customized months of training to be conducted for effectiveness. strengthening the specific understanding for all IA. 9 PROCUREMENT India : National Agricultural Higher Education Project PLAN General Information Country: India Bank’s Approval Date of the Original Procurement Plan: 2019-12-30 2021-05-25 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P151072 GPN Date: 2016-12-16 Project Name: National Agricultural Higher Education Project Loan / Credit No: IBRD / 87760 A Executing Agency(ies): AU, Anand WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned IN-AAU - ANAND-142118- Support to Agricultural Request for Single Stage - One 2020-09- CW-RFQ / Higher capacity IBRD / 87760 Post Limited 23,300.00 17,919.93 Completed 2020-02-06 2020-02-29 2020-04-02 2020-03-20 Universities Quotations Envelope 29 Split AC for -14 Nos. IN-AAU - ANAND-142133- CW-RFQ / Fresh room cum Support to Agricultural Request for Single Stage - One 2020-09- IBRD / 87760 Post Limited 29,500.00 25,235.63 Completed 2020-02-06 2021-03-15 2020-04-02 2021-03-30 washroom, Furniture and Universities Quotations Envelope 29 electrification IN-AAU - ANAND-142124- CW-RFQ / Training room , Support to Agricultural Request for Single Stage - One 2020-09- Meeting room, PI & Co-PI IBRD / 87760 Post Limited 47,000.00 50,026.23 Completed 2020-02-06 2020-02-11 2020-04-02 2020-03-21 Universities Quotations Envelope 29 room, Technical & research staff Seating Room etc IN-AAU - ANAND-164463- CW-RFQ / Renovation of Office, Server room, Computer Laboratory, Store room, Aluminium Door, window and Support to Agricultural Request for Single Stage - One 2020-12- IBRD / 87760 Post Limited 37,300.00 32,985.82 Completed 2020-04-15 2020-02-11 2020-06-10 2021-01-11 partitions, window grill, Universities Quotations Envelope 07 painting, electrification, fall ceiling, OTS facility creation and other necessary furnishing GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-AAU - ANAND-142156- Under GO-RFQ / AI data & image Support to Agricultural IBRD / 87760 Post Direct Selection Direct 77,500.00 0.00 Implementati 2020-02-01 2021-03-31 2020-02-06 2020-03-12 2020-09-08 extraction subscription to Universities on ISRO, Ahmedabad. IN-AAU - ANAND-142155- Support to Agricultural Request for Single Stage - One GO-RFQ / GPS devices-10 IBRD / 87760 Post Limited 15,000.00 6,918.80 Completed 2020-02-06 2020-01-17 2020-04-02 2020-03-04 2020-09-29 2020-03-09 Universities Quotations Envelope nos. IN-AAU - ANAND-142384- GO-RFQ / External Hard Support to Agricultural Request for Single Stage - One IBRD / 87760 Post Limited 2,800.00 2,465.34 Completed 2020-02-06 2020-02-27 2020-04-02 2020-03-02 2020-09-29 2020-03-02 drives and storage devices - Universities Quotations Envelope 60 Nos. IN-AAU - ANAND-142495- GO-RFQ / Statistical and Support to Agricultural Request for Single Stage - One IBRD / 87760 Post Limited 23,000.00 20,440.65 Completed 2020-02-06 2020-02-26 2020-04-02 2020-03-11 2020-09-29 2020-03-17 analytical software (data Universities Quotations Envelope mining) IN-AAU - ANAND-142497- GO-RFQ / Networking, CCTV Support to Agricultural Request for Single Stage - One IBRD / 87760 Post Limited 15,000.00 11,489.03 Completed 2020-02-06 2020-02-29 2020-04-02 2020-03-18 2020-09-29 2020-03-31 Camera, Intercom & its Universities Quotations Envelope accessories IN-AAU - ANAND-149649- GO-RFQ / Photocopier Support to Agricultural Request for Single Stage - One Machine - 1 Nos. IBRD / 87760 Post Limited 6,150.00 6,732.68 Completed 2020-02-06 2020-02-14 2020-04-02 2020-02-21 2020-09-29 2020-02-21 Universities Quotations Envelope Duplex printer cum scanner - 2 nos. IN-AAU - ANAND-149654- GO-RFQ / Bulk soft copy writer - 1 Nos. Work station - 10 Nos  Support to Agricultural Request for Single Stage - One High end Personal computer IBRD / 87760 Post Limited 92,400.00 88,007.09 Completed 2020-02-06 2020-03-03 2020-04-02 2020-03-13 2020-09-29 2020-03-13 Universities Quotations Envelope and Laptops with peripherals - 36 Nos Computer server - 3 Nos. Tablets - 20 Nos IN-AAU - ANAND-149651- GO-RFQ / Interactive Projector & Screen - 1 Nos. Video Camera with accessories - 1 Nos. Support to Agricultural Request for Single Stage - One Smart LED display TV - IBRD / 87760 Post Limited 28,153.00 18,698.12 Completed 2020-02-06 2020-02-14 2020-04-02 2020-03-23 2020-09-29 2020-03-23 Universities Quotations Envelope Meeting room -4 nos  Public Address System (sets) & its accessories - 1 Nos. DSLR camera with lens and other accessories -1 Nos IN-AAU - ANAND-142486- GO-RFQ / Software for Support to Agricultural Request for Single Stage - One IBRD / 87760 Post Limited 23,000.00 20,939.72 Completed 2020-02-06 2020-10-29 2020-04-02 2020-12-04 2020-09-29 2020-12-15 Artificial Intelligence & Universities Quotations Envelope Applications (Apps) Page 1 IN-AAU - ANAND-149653- GO-RFQ / ADMN. Office Tables - 2 Nos Computer Tables with drawer and necessary accessories - 50 Nos Fixed/ Revolving chair - 20 Support to Agricultural Request for Single Stage - One IBRD / 87760 Post Limited 40,095.00 36,026.89 Completed 2020-02-06 2020-03-06 2020-04-02 2020-03-13 2020-09-29 2020-03-13 Nos Universities Quotations Envelope Revolving chair for laboratory & others staff - 50 Nos  High back revolving chair - 8 Nos PI & Co -PI office tables - 4 Nos IN-AAU - ANAND-149652- GO-RFQ / 10 KVA Online UPS Support to Agricultural Request for Single Stage - One - 3 nos IBRD / 87760 Post Limited 35,300.00 17,684.58 Completed 2020-02-06 2020-03-20 2020-04-02 2020-03-21 2020-09-29 2020-03-31 Universities Quotations Envelope Online Stabilizer- 75 KVA - 1 nos. IN-AAU - ANAND-149646- GO-RFQ / File compactors - 1 Support to Agricultural Request for Single Stage - One IBRD / 87760 Post Limited 18,600.00 10,110.57 Completed 2020-02-06 2020-03-02 2020-04-02 2020-03-09 2020-09-29 2020-03-31 Nos. Universities Quotations Envelope Cabinet for storage - 20 Nos. IN-AAU - ANAND-153049- GO-RFQ / Handheld Spectroradiometer - 1No. Canopy Analyzer (for LAI) - 1 Support to Agricultural Request for Single Stage - One IBRD / 87760 Post Limited 39,200.00 26,301.93 Completed 2020-02-20 2020-01-17 2020-04-16 2020-03-17 2020-10-13 2020-03-23 No. Universities Quotations Envelope Infrared Thermometer - 1 No. SPAD Chlorophyll Meter - 1 No. IN-AAU - ANAND-153097- GO-RFQ / Peripheral & Support to Agricultural Request for Single Stage - One Computer IBRD / 87760 Post Limited 21,500.00 19,055.95 Completed 2020-02-20 2020-02-24 2020-04-16 2020-03-06 2020-10-13 2020-03-31 Universities Quotations Envelope High End Personal Laptop with peripherals - 17 Nos. IN-AAU - ANAND-153100- GO-RFQ / Furniture and Fixture for Training Room, Support to Agricultural Request for Single Stage - One IBRD / 87760 Post Limited 30,100.00 27,193.59 Completed 2020-02-20 2021-01-27 2020-04-16 2021-03-25 2020-10-13 2021-03-31 Meeting cum Conference Universities Quotations Envelope Room and Modular Furniture and Baby Toddler IN-AAU - ANAND-147413- Support to Agricultural IBRD / 87760 Post Direct Selection Direct 15,500.00 2,634.76 Completed 2020-04-13 2020-02-17 2020-04-18 2020-02-17 2020-05-23 2020-03-07 2020-11-19 2020-03-31 GO-DIR / Books and Journals Universities IN-AAU - ANAND-226233- Support to Agricultural GO-DIR / BOOKS AND IBRD / 87760 Post Direct Selection Direct 12,450.00 10,778.21 Completed 2021-04-10 2020-10-23 2021-04-15 2020-10-23 2021-05-20 2021-02-06 2021-11-16 2021-02-22 Universities JOURNALS DIRECT SELECTION IN-AAU - ANAND-226235- Pending Support to Agricultural GO-DIR / BOOKS AND IBRD / 87760 Post Direct Selection Direct 9,310.00 0.00 Implementati 2021-05-01 2021-05-06 2021-06-10 2021-12-07 Universities JOURNALS DIRECT SELECTION on NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-AAU - ANAND-196022- CS-CDS / Title: Demand and Supply projections of three components namely Food grains, Fisheries and Milk & Individual Support to Agricultural Milk Products IBRD / 87760 Post Consultant Limited 56,600.00 112,783.22 Signed 2020-11-09 2020-08-07 2020-11-14 2020-08-07 2020-12-05 2020-08-25 2021-01-09 2020-11-18 2021-07-08 Universities Objectives: Demand and Selection Supply projections of 1. Food grains. 2. Fisheries. 3. Milk and Milk products IN-AAU - ANAND-196023- CS-CDS / Title: Growth and Export Opportunities of major value added food products. Objectives: Study on Market Individual Support to Agricultural Competitiveness of Dairy IBRD / 87760 Post Consultant Limited 5,600.00 11,550.09 Signed 2020-11-09 2020-08-26 2020-11-14 2020-08-26 2020-12-05 2020-09-04 2021-01-09 2020-11-18 2021-07-08 Universities Commodities Selection Growth and Export Opportunities of : Major Value-added processed food products manufactured from Vegetables and Fr Page 2 IN-AAU - ANAND-196035- CS-CDS / Title: A study on performance of Farmer Producer Organization (FPOs) in Gujarat Individual Objectives: To study the Support to Agricultural IBRD / 87760 Post Consultant Limited 8,250.00 10,870.67 Signed 2020-11-09 2020-08-26 2020-11-14 2020-08-26 2020-12-05 2020-09-25 2021-01-09 2020-11-16 2021-07-08 structure, conduct and Universities Selection performance of FPOs. To identify the factors influencing performance FPOs. To analyze the impact of FPOs on Farmers economy IN-AAU - ANAND-220402- CS-INDV / Market Potential and Trade Competitiveness of selected Agro-commodities in India To analyse the trend and Individual Support to Agricultural instability,India’s volume and IBRD / 87760 Post Consultant Direct 9,400.00 10,910.18 Signed 2021-04-12 2021-02-09 2021-04-22 2021-02-09 2021-05-13 2021-02-15 2021-06-17 2021-05-25 2021-12-14 Universities direction of trade ,market Selection potential and trade competitiveness and challenges in trade of selected agri commodities. IN-AAU - ANAND-164472- CS-CDS / Enhancing Agricultural Market Intelligence using Digital Knowledge Agribusiness Ecosystem platform for Support to Agricultural Under generating primary digital IBRD / 87760 Post Direct Selection Direct 46,550.00 0.00 2021-04-14 2020-08-25 2021-04-24 2021-06-28 2021-12-25 Universities Implementation continuous data streams. Deploy the Digital Agribusiness Ecosystems, agrifood value chains, generating market intelligence IN-AAU - ANAND-163715- CS-CDS / IRMA - Anand Support to Agricultural Purpose: Collaborative work IBRD / 87760 Post Direct Selection Direct 7,755.00 0.00 Canceled 2020-04-10 2020-04-20 2020-06-24 2020-12-21 Universities on capacity building programme and FPO. IN-AAU - ANAND-164469- CS-CDS / Agri Digital Media Support to Agricultural IBRD / 87760 Post Direct Selection Direct 3,100.00 0.00 Canceled 2020-04-10 2020-04-20 2020-06-24 2020-12-21 Purpose: Dissemination of Universities information through ICT tools. IN-AAU - ANAND-164471- CS-CDS / Papua New Guinea Uni. of Technology Support to Agricultural Purpose: Will provide IBRD / 87760 Post Direct Selection Direct 4,700.00 0.00 Canceled 2020-04-10 2020-04-20 2020-06-24 2020-12-21 Universities methodology for global market intelligence in major crop. IN-AAU - ANAND-164468- CS-CDS / National Cooperative Dairy Federation of India Limited Support to Agricultural Purpose: Will contribute to the IBRD / 87760 Post Direct Selection Direct 4,700.00 0.00 Canceled 2020-04-10 2020-04-20 2020-06-24 2020-12-21 Universities fulfillment of methodology part of price forecast for the Dairy and Animal Husbandry Products. IN-AAU - ANAND-164467- CS-CDS / Title: Price Support to Agricultural IBRD / 87760 Post Direct Selection Direct 4,700.00 0.00 Canceled 2020-11-10 2020-11-20 2021-01-24 2021-07-23 forecasting of Oil Seed crop Universities for short and long term IN-AAU - ANAND-207926- CS-INDV / Price Volatility, Price Discovery and Relationship between Spot and Futures Prices in Individual Support to Agricultural Under Agricultural Commodity IBRD / 87760 Post Consultant Limited 7,400.00 8,918.10 2021-04-25 2020-08-31 2021-04-30 2020-08-31 2021-05-21 2020-11-28 2021-06-25 2021-12-22 Universities Implementation Markets in India. To measure Selection the degree of price instability of selected agricultural commodities in major domestic markets of India Page 3 PROCUREMENT PLAN (Textual Part) Project information: Maldives, Maldives Urban Development & Resilience (P163957) Project Implementation agency: Ministry of National Planning and Infrastructure Date of the Procurement Plan: September 12, 2019 Period covered by this Procurement Plan: September 12, 2019– March 12, 2020 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Chapter on Public Procurement for Maldives’ Public Finance Regulations 2017, Chapter 10 – State Procurement System, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. 1) Only bidding documents acceptable to the Bank shall be used for all national open competitive procurement. 2) The eligibility of bidders shall be as defined under Section III of the Procurement Regulations. Accordingly, no bidder or potential bidder shall be declared ineligible for contracts financed by the Bank for reasons other than those provided in Section III of the Procurement Regulations. 3) The request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance (in the form attached) at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. 4) Procurement Documents include provisions, as agreed with the Bank, intended to adequately mitigate against environmental, social (including sexual exploitation and abuse and gender-based violence), health and safety (“ESHS”) risks and impacts 5) In case of Open Tendering, the receipt of less than three bids shall not be considered grounds for cancellation and re-invitation of bids. 6) Bid shall not be rejected merely on the basis of a comparison with an official estimate. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Specify for each Goods: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables]; Not Applicable Works: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables] Not Applicable Table 5.1. Procurement Methods to Be Used in the Project Applicable for ‘High’ risk Expenditur Contract Value Procurement Contracts/ e Category (threshold) Method Processes Subject to Prior Review ≥US$100,000 Open International All contracts over Goods • D ¡ f € / ¨ â ¡ Monitoring and Evaluation Selection Consultant CN-GXFCPRPMC-69880-CS- Project Management, IBRD / 86700 Post Qualification Open - National 73,800.00 71,447.71 Completed 2018-07-24 2018-07-27 2018-08-14 2018-12-25 2018-09-27 2018-09-03 2018-10-27 2018-09-28 2018-12-01 2018-11-01 2019-05-30 2019-10-31 CQS / \ > ù - Œ ý › ú ¾ Monitoring and Evaluation Selection GXSJ-ZX-05 / Project Management- provide project management consulting Project Management, Quality And Cost- services for project IBRD / 86700 Post Open - International 984,600.00 723,554.08 Signed 2019-01-23 2019-01-25 2019-02-13 2019-03-12 2019-03-29 2019-04-30 2019-04-26 2019-06-17 2019-05-26 2019-06-17 2019-06-30 2019-07-04 2019-08-04 2019-08-30 2020-08-03 Monitoring and Evaluation Based Selection manangement offices in autonomous regions, cities and counties GXSJ-ZX-06 / Monitoring assessment from the thrid Consultant party-provide external Project Management, IBRD / 86700 Post Qualification Open - National 298,500.00 271,863.65 Signed 2019-01-25 2019-01-25 2019-02-15 2019-03-31 2019-03-25 2019-04-30 2019-07-27 2019-06-04 2019-08-30 2019-12-01 monitoring and evaluation for Monitoring and Evaluation Selection the project from the thrid party GXSJ-ZX-07 / Project financial guidance and inspection -To provide Consultant Project Management, financial guidance, inspection IBRD / 86700 Post Qualification Open - National 276,900.00 249,371.34 Signed 2019-03-31 2019-04-22 2019-04-21 2019-06-04 2019-05-09 2019-07-04 2019-05-28 2019-08-08 2019-06-14 2020-02-04 Monitoring and Evaluation and consulting services for Selection PMOs in autonomous regions, cities and counties GXSJ-ZX-08 / Purchase of consulting service for Consultant Business Incubation Center Enhancing Investments in IBRD / 86700 Post Qualification Open - National 184,615.38 165,728.49 Signed 2020-05-07 2020-05-11 2020-05-21 2020-06-11 2020-06-08 2020-07-11 2020-07-14 2020-08-15 2020-07-08 2021-02-11 information platform (APP) Poor Areas Selection development, operation and maintenance INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GXPG-ZX-2021-01 / Pingguo Individual Improvement of Pro-Poor Under BIC purchases legal IBRD / 86700 Post Consultant Open 10,000.00 0.00 2021-03-01 2021-01-05 2021-04-19 2021-05-10 2021-06-14 2022-05-11 Value Chains Implementation consultancy service. Selection GXSJ-ZX-09 / Publicity Public Infrastructure and Pending service of Guangxi Poverty IBRD / 86700 Post Direct Selection Direct 46,153.85 0.00 2021-05-20 2021-05-30 2021-08-03 2022-01-30 Services Implementation Alleviation Pilot Project Page 2 PROCUREMENT PLAN FOR PROJECT PREPARATION ADVANCE (PPA) Project information: Nigeria Identification for Development (ID4D) Project - (P167183) Project Implementation agency: Youth Employment and Social Support (YESSO) is implementing the PPA on behalf of the National Identity Management Commission Date of the Procurement Plan: August 17, 2018 Period covered by this Procurement Plan: August 2018 to November 2019 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Nigeria Public Procurement Act 2007, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables. Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: [15% is applicable for those contracts identified in the Procurement Plan tables]; Works: [ 7.5% is applicable for those contracts identified in the Procurement Plan tables] I. Threshold for Prior Review, Procurement Approaches and Methods – Good, Works and Non- Consulting Services Procurement Approaches and Methods (US$ millions) Prior Review Category Open Open Request for (US$ millions) International National Quotation (RfQ) Works ≥5 ≥ 20 < 20 ≤ 0.2 Goods, IT, and non-consulting ≥ 1.5 ≥5 <5 ≤ 0.1 services Post Review: All contracts not subject to prior review shall be subject to post review. Summary of the procurement packages for Goods Sr Contract Estima Revie Market Selectio Evaluation Options Prequ Domesti Expecte Expecte Expected . Description ted w by Approac n (Most al- c d date d date of completi N Cost Bank h (Open- Method Advantageous Bid, ificatio Preferen of bid/ Contract on date o (US$) (Prior/ National/ (RFP, BAFO, Rated n ce proposal Signatur Post) Limited RFB, Criteria etc.) (Yes/ (Yes/No) opening e etc.) RFQ, DS No) etc.) 1 Procurement of 200,00 Post Open/ RFB Most Advantag- No No 03/12/18 10/01/20 01/03/19 Office Furniture 0 National eous Bid 19 and supplies for project coordination 2 Supply of 100,00 Post Limited RFQ Most Advantag- No No 22/10/18 30/10/20 30/11/201 computers and 0 eous Bid 18 8 software for M&E 3 Supply of 300,00 Post Open/ RFB Most Advantag- No No 15/12/20 14/01/20 28/02/201 biometric 0 National eous Bid 18 19 9 equipment including computers and software 4 Financial 10,000 Post Direct DIR Direct No No 17/10/20 31/10/20 30/11/201 management 18 18 8 software Total Goods 610,000 II. Thresholds for Prior Review, Selection Approaches and Methods – Consulting Services Category Prior Review Short List of National Consultants (US$ millions) Consulting Engineering and Construction Supervision Services Consultants (Firms) ≥ 0.5 ≤ 0.3 ≤ 0.5 Individual Consultants ≥ 0.2 Note: Consultancy services estimated to cost equivalent to US $ 300,000 and above per contract shall be advertised in the United Nations Development Business (UNDB) online in addition to advertising in national newspaper(s) of wide circulation and/or national newspaper. III. Summary of the procurement packages for Consulting Services Sr. Contract Estimate Revie Market Selection Expected Expected Expected No Description d Cost w by Approach Method date of bid/ date of date of (US$) Bank (Open - (QCBS, FBS, proposal Contract Completion (Prior/ International/ LCBS, QBS, opening Signature date Post) National/ CQS, DS etc.) etc.) 1 Social Assessment Limited / for Nigeria National 295,000 POST CQS Identification for Development Project 15/08/2018 31/08/2018 21/12/2018 2 Project Coordinator, Open / National National Identity 60,000 POST INDV Management Commission NA 01/10/2018 01/10/2019 3 Operations Open / National Specialist, National 40,000 POST INDV Identity Management Commission NA 02/11/2018 01/11/2019 4 Senior M&E Open / National Specialist, National 40,000 POST INDV Identity Management Commission NA 02/11/2018 02/11/2019 5 M&E Specialist, Open / National National Identity 30,000 POST INDV Management Commission NA 05/11/2018 05/11/2019 6 Financial Open / National Management Specialist, National 30,000 PRIOR INDV Identity Management Commission NA 06/11/2018 06/11/2019 7 Procurement Open / National Specialist, National 30,000 PRIOR INDV Identity Management Commission NA 07/11/2018 07/11/2019 8 Project Assistant, , Open / National National Identity 20,000 POST INDV Management Commission NA 08/11/2018 08/11/2019 9 Coordinator, Office of Open / National 60,000 POST INDV the Vice President NA 09/11/2018 09/11/2019 10 Technical expert, eID Open / National and Systems 40,000 POST INDV Integration, Office of the Vice President NA 12/11/2018 12/11/2019 11 M&E Specialist, Open / National Office of the Vice 40,000 POST INDV President NA 13/11/2018 13/11/2019 12 Communication and Open / National Awareness Specialist, 40,000 POST INDV Office of the Vice President NA 14/11/2018 14/11/2019 13 Social Development Open / National Specialist, Office of 40,000 POST INDV the Vice President NA 15/11/2018 15/11/2019 14 Financial Open / National Management 30,000 PRIOR INDV Specialist, Office of the Vice President NA 16/11/2018 16/11/2019 15 Procurement Open / National Specialist, Office of 30,000 PRIOR INDV the Vice President NA 19/11/2018 19/11/2019 16 Consultant to draft Limited / detailed Project National 50,000 POST INDV Implementation Manual NA 20/11/2018 20/01/2019 17 Consultant to draft Limited / Manual of Procedures National 10,000 POST INDV for Financial Mangement NA 21/11/2018 21/01/2019 18 Consultant to design Limited / a monitoring and 50,000 POST National INDV evaluation plan NA 22/11/2018 21/01/2019 19 Consultant to draft Limited / Environmental and National 17,000 POST INDV Social Management Framework NA 03/09/2018 17/10/2018 20 Consultant to draft Limited / Resettlement Policy 17,000 POST National INDV Framework NA 03/09/2018 17/10/2018 21 Consultant (short Limited / term) to assist in National procurement of 15,000 POST INDV project preparation activities NA 01/08/2018 31/12/2018 22 Consultant to design Limited / the project Grievance 42,000 POST National INDV Redress Mechanism NA 23/11/2018 29/01/2019 23 Consultant to Limited / develop a National 50,000 POST INDV communications strategy NA 26/11/2018 25/01/2019 24 Firm to develop and Open / National carry out public communications and 230,000 POST CQS awareness campaigns 10/12/2018 25/01/2019 15/06/2019 25 Technical support for Limited / drafting any National necessary new 299,000 PRIOR CQS legislation and amendments to existing legislation 10/12/2018 15/01/2019 15/04/2019 26 Institutional analysis Limited / and capacity National 100,000 POST CQS assessment of institutions 02/10/2018 29/10/2018 15/01/2019 implicated in the implementation of the ID4D project 27 Study on HR Limited / capacity-building National 100,000 POST INDV strategy for NIMC for ID4D implementation NA 27/11/2018 22/01/2019 28 Risks assessment of Limited / ID4D project National implementation, including risks of 50,000 POST INDV data protection and privacy (but not including social and environmental risks) NA 28/11/2018 23/01/2019 29 Cybersecurity and Open / data protection International assessment for 200,000 POST CQS identification ecosystem and Action Plan 15/08/2018 28/09/2018 28/02/2019 30 Drafting technical Limited / system specifications National for selected enrollment partners 100,000 POST INDV and functional users of the National ID registry NA 29/11/2018 28/02/2019 31 Firm to carry out Limited / consultations with National beneficiaries and 250,000 POST CQS stakeholders during project preparation 15/08/2018 28/09/2018 21/12/2018 Total Consultancy 2,405,00 Services 0 PROCUREMENT Nigeria : Nigeria Digital Identification for Development Project PLAN General Information Country: Nigeria Bank’s Approval Date of the Original Procurement Plan: 2019-07-09 2021-05-20 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P167183 GPN Date: Project Name: Nigeria Digital Identification for Development Project Loan / Credit No: IDA / V2290 National Identity Management Commission Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NIMC-PPA-13 / NIMC PIU: Procurement of Office Component 4: Project Request for Single Stage - One Furniture and supplies for IDA / V2290 Management and Stakeholder Post Limited 100,000.00 76,516.84 Signed 2019-07-27 2020-02-03 2019-09-07 2020-06-23 2019-10-07 Quotations Envelope project coordination (Tables Engagement and Chairs) NIMC-PPA-14 / NIMC PIU: Procurement of Office Component 4: Project Request for Single Stage - One Furniture and supplies for IDA / V2290 Management and Stakeholder Post Limited 90,000.00 72,297.86 Signed 2019-07-27 2020-02-03 2019-09-21 2020-06-23 2019-10-21 Quotations Envelope project coordination (Electrical Engagement Appliances) Component 4: Project Pending NIMC-PPA-18 / Financial IDA / V2290 Management and Stakeholder Post Direct Selection Direct 10,000.00 0.00 Implementati 2019-08-04 2019-08-09 2019-09-13 2019-11-15 Management Software Engagement on NG-NIMC-169497-GO-RFQ / Procurement of Equipment to Component 4: Project Request for Single Stage - One support Virtual Office IDA / V2290 Management and Stakeholder Post Limited 30,000.00 26,366.33 Signed 2020-04-29 2020-04-28 2020-06-24 2020-05-13 2020-08-23 Quotations Envelope requirements during COVID- Engagement 19 Lockdown NG-NIMC-PPA-57-1 / Procurement of items to support Reopening NIMC Component 2: Establishing a Under enrolment services and offices Single Stage - One IDA / V2290 Robust and Inclusive Post Request for Bids Limited 365,000.00 0.00 Implementati 2020-07-20 2020-08-17 2020-07-25 2020-08-17 2020-08-08 2020-09-03 2020-08-22 2020-09-03 2020-09-12 2020-10-12 across the nation under the Envelope Foundational ID System on COVID-19 Lockdown (Pharmaceutical and General Supplies) NG-NIMC-PPA-57-2 / Procurement of items to support Reopening NIMC Component 2: Establishing a Under Request for Single Stage - One enrolment services and offices IDA / V2290 Robust and Inclusive Post Limited 75,000.00 0.00 Implementati 2020-07-25 2020-08-17 2020-09-19 2020-10-19 Quotations Envelope across the nation under the Foundational ID System on COVID-19 Lockdown (Printing/Banners/Posters) NG-NIMC-PPA-68 / Procurement of Furniture and Office Equipment for Component 4: Project Pending Request for Single Stage - One Allocated Office Space for the IDA / V2290 Management and Stakeholder Post Limited 100,000.00 0.00 Implementati 2020-11-28 2021-01-23 2021-02-22 Quotations Envelope ECSU in Office of the Secretary Engagement on to the Government of the Federation NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NIMC-PPA-25 / Firm to carry Component 4: Project Consultant out consultations with Under IDA / V2290 Management and Stakeholder Post Qualification Limited 250,000.00 0.00 2019-07-22 2019-08-26 2019-08-05 2019-09-04 2019-09-18 2020-03-19 beneficiaries and stakeholders Implementation Engagement Selection during project preparation NIMC-PPA-28 / Firm to Component 4: Project Consultant develop and carry out public Under IDA / V2290 Management and Stakeholder Post Qualification Open - National 225,000.00 0.00 2019-07-22 2019-08-26 2019-08-12 2019-09-25 2019-10-25 2019-11-08 2020-03-10 communications and Implementation Engagement Selection awareness campaigns NIMC-PPA-29 / Technical support for drafting any Component 1: Strengthening Consultant Pending necessary new legislation and IDA / V2290 the Legal and Institutional Post Qualification Open - National 299,000.00 0.00 2019-07-22 2019-08-12 2019-09-01 2019-10-01 2019-10-15 2020-04-15 Implementation amendments to existing Framework Selection legislation NIMC-PPA-33 / Cybersecurity and data Component 1: Strengthening Consultant protection assessment for IDA / V2290 the Legal and Institutional Post Qualification Limited 200,000.00 158,897.20 Completed 2018-09-03 2018-08-01 2018-09-17 2018-11-02 2018-10-17 2019-04-01 2018-11-21 2019-04-08 2019-05-23 2020-02-20 identification ecosystem and Framework Selection Action Plan Page 1 Component 4: Project Consultant NIMC-PPA-37 / Firm to carry IDA / V2290 Management and Stakeholder Post Qualification Limited 295,000.00 216,823.02 Signed 2018-07-23 2018-09-04 2018-08-06 2018-09-04 2018-09-05 2018-10-23 2018-10-10 2018-10-24 2019-04-08 out Social Assessment (SA) Engagement Selection NIMC-PPA-30 / Institutional analysis and capacity Component 1: Strengthening Consultant assessment of institutions IDA / V2290 the Legal and Institutional Post Qualification Limited 100,000.00 0.00 Canceled 2019-07-22 2019-08-26 2019-08-05 2019-09-04 2019-09-18 2020-01-19 implicated in the Framework Selection implementation of the ID4D project NG-NIMC-PPA-67 / Consultancy for Furniture Component 4: Project Consultant Needs Assessment and Design IDA / V2290 Management and Stakeholder Post Qualification Limited 30,000.00 0.00 Under Review 2020-10-20 2020-11-27 2020-10-27 2020-11-03 2020-11-17 2020-12-17 for Allocated Office Space for Engagement Selection the ECSU NG-NIMC-PPA-63 / Consultancy Services for the Component 4: Project Consultant Development of Grievance IDA / V2290 Management and Stakeholder Post Qualification Open - National 250,000.00 0.00 Canceled 2020-12-14 2020-12-10 2020-12-28 2021-01-25 2021-02-08 2021-03-08 2021-09-04 Redress Mechanism for ID4D Engagement Selection Ecosystem NG-NIMC-PPA-66 / Component 4: Project Consultant Consultancy Services for IDA / V2290 Management and Stakeholder Post Qualification Open - National 250,000.00 0.00 Canceled 2020-12-14 2020-12-28 2021-01-25 2021-02-08 2021-03-08 2021-09-04 Project Management Support Engagement Selection to ID4D Ecosystem NG-NIMC-PPA-64 / Consultancy Services for the Component 4: Project Consultant Development of a IDA / V2290 Management and Stakeholder Post Qualification Open - National 250,000.00 0.00 Canceled 2020-12-14 2020-12-10 2020-12-28 2021-04-21 2021-01-25 2021-02-08 2021-03-08 2021-09-04 Communication Strategy for Engagement Selection the ID4D Ecosystem NG-NIMC-PPA-69 / Consultancy Services for the Component 4: Project Consultant Under Development of Grievance IDA / V2290 Management and Stakeholder Post Qualification Open - National 300,000.00 0.00 2021-01-04 2021-01-08 2021-01-18 2021-04-21 2021-03-03 2021-03-17 2021-04-14 2021-10-11 Implementation Redress Mechanism for ID4D Engagement Selection Ecosystem NG-NIMC-PPA-70 / Consultancy Services for the Component 4: Project Quality And Cost- Under Development of a IDA / V2290 Management and Stakeholder Post Open - National 450,000.00 0.00 2021-01-04 2021-01-08 2021-01-18 2021-04-21 2021-03-03 2021-03-17 2021-03-31 2021-04-28 2021-05-26 2021-11-22 Based Selection Implementation Communication Strategy for Engagement the ID4D Ecosystem NG-NIMC-PPA-71 / Component 4: Project Consultancy Services for Quality And Cost- Under IDA / V2290 Management and Stakeholder Post Open - International 600,000.00 0.00 2021-01-04 2021-01-08 2021-01-18 2021-04-21 2021-02-15 2021-03-01 2021-03-15 2021-04-05 2021-05-10 2022-05-10 Project Management Support Based Selection Implementation Engagement to ID4D Ecosystem NG-NIMC-PPA-65 / Consultancy Services for Definition of Architecture and Implementation Arrangements Component 4: Project Consultant for the ID4D Ecosystem, Under IDA / V2290 Management and Stakeholder Prior Qualification Limited 1,600,000.00 0.00 2021-01-04 2021-02-10 2021-01-18 2021-02-01 2021-03-01 2021-08-28 including Implementation Implementation Engagement Selection Strategy, Requirements Catalogue, Business Model, and Licensing and Assurance Framework NG-NIMC-PPA-72 / Component 4: Project Consultant Appointment of Firm for the Under IDA / V2290 Management and Stakeholder Post Qualification Limited 20,000.00 0.00 2021-05-19 2021-05-21 2021-05-23 2021-05-27 2021-06-04 2021-06-25 External Audit of the Nigeria Implementation Engagement Selection ID4D Project INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 4: Project Individual NIMC-PPA-01 / NIMC PIU: IDA / V2290 Management and Stakeholder Post Consultant Direct 100,000.00 0.00 Canceled 2019-07-22 2019-08-01 2019-08-08 2019-08-22 2020-02-21 Project Coordinator Engagement Selection Component 4: Project Individual NIMC-PPA-04 / NIMC PIU: IDA / V2290 Management and Stakeholder Post Consultant Limited 30,000.00 0.00 Under Review 2019-07-22 2019-08-28 2019-07-27 2019-08-03 2019-08-17 2020-02-16 Grievance Redress Manager Engagement Selection Component 1: Strengthening Individual NIMC-PPA-09 / NIMC PIU: IDA / V2290 the Legal and Institutional Post Consultant Limited 50,000.00 0.00 Under Review 2019-07-22 2019-07-24 2019-08-07 2019-08-14 2019-08-28 2020-02-27 Cybersecurity Specialist Framework Selection Component 1: Strengthening Individual NIMC-PPA-10 / OVP SCU: IDA / V2290 the Legal and Institutional Post Consultant Limited 40,000.00 0.00 Under Review 2019-07-22 2019-08-28 2019-07-27 2019-08-03 2019-08-17 2020-02-16 Senior Program Officer Framework Selection NIMC-PPA-16 / Consultant Component 4: Project Individual for the draft of a detailed IDA / V2290 Management and Stakeholder Post Consultant Limited 50,000.00 20,233.43 Signed 2019-07-22 2019-10-15 2019-07-27 2020-03-18 2019-08-17 2020-04-20 2019-08-31 2020-05-06 2020-03-01 Project Implementation Engagement Selection Manual (overall project) NIMC-PPA-17 / Consultant to Component 4: Project Individual draft Manual of Procedures for IDA / V2290 Management and Stakeholder Post Consultant Limited 10,000.00 8,537.50 Signed 2019-07-22 2019-10-14 2019-07-27 2020-03-18 2019-08-03 2020-04-20 2019-08-17 2020-05-06 2019-10-19 Financial Management Engagement Selection NIMC-PPA-19 / Consultant Component 4: Project Individual for the design for Monitoring IDA / V2290 Management and Stakeholder Post Consultant Limited 50,000.00 0.00 Under Review 2019-07-22 2019-08-28 2019-07-27 2019-08-17 2019-08-31 2019-12-02 and Evaluation Plan Engagement Selection NIMC-PPA-20 / Consultant Component 4: Project Individual (short term) to assist in IDA / V2290 Management and Stakeholder Prior Consultant Limited 15,000.00 0.00 Canceled 2019-01-14 2019-01-19 2019-02-09 2019-03-16 2019-06-16 procurement of Project Engagement Selection Preparation activities Page 2 NIMC-PPA-23 / Consultant to Component 4: Project Individual draft Environmental and Social IDA / V2290 Management and Stakeholder Post Consultant Limited 17,000.00 12,000.00 Signed 2018-09-03 2018-09-11 2018-09-08 2018-09-11 2018-09-29 2018-10-08 2018-10-13 2018-10-10 2019-04-14 Management Framework Engagement Selection NIMC-PPA-24 / Consultant to Component 4: Project Individual draft Resettlement Policy IDA / V2290 Management and Stakeholder Post Consultant Limited 17,000.00 12,216.49 Signed 2018-09-03 2018-09-11 2018-09-08 2018-09-11 2018-09-29 2018-10-08 2018-11-03 2018-10-10 2019-05-05 Framework Engagement Selection NIMC-PPA-31 / Study on HR capacity-building for NIMC for Component 1: Strengthening Individual ID4D implementation Under IDA / V2290 the Legal and Institutional Post Consultant Limited 100,000.00 0.00 2019-09-10 2019-08-26 2019-09-15 2019-10-06 2019-10-20 2020-01-21 including revised Implementation Framework Selection organizational arrangements and staffing plan Component 4: Project Individual NIMC-PPA-05 / NIMC PIU: IDA / V2290 Management and Stakeholder Post Consultant Limited 30,000.00 0.00 Under Review 2019-07-31 2019-08-28 2019-08-14 2019-08-28 2019-09-11 2020-03-12 Safeguards Officer Engagement Selection Component 4: Project Individual NIMC-PPA-36 / NIMC PIU: IDA / V2290 Management and Stakeholder Post Consultant Limited 100,000.00 79,502.98 Signed 2018-09-15 2018-10-17 2018-09-20 2018-12-14 2018-10-11 2019-01-18 2018-11-15 2019-01-31 2019-05-14 Team Lead Engagement Selection NIMC-PPA-12 / Consultant Component 4: Project Individual (short term) to assist in Under IDA / V2290 Management and Stakeholder Post Consultant Limited 15,000.00 0.00 2018-10-12 2018-10-17 2018-11-07 2018-12-12 2019-06-10 procurement of Project Implementation Engagement Selection Preparation activities NG-NIMC-130237-CS-CDS / Consultant (short term) to Component 4: Project Under assist in procurement of IDA / V2290 Management and Stakeholder Post Direct Selection Direct 10,000.00 0.00 2019-09-06 2019-09-18 2019-09-16 2019-09-27 2019-10-01 2019-12-30 Implementation Project Preparation activities Engagement (Extension) NIMC-PPA-34 / Drafting technical system Component 1: Strengthening Individual specifications for selected IDA / V2290 the Legal and Institutional Post Consultant Limited 100,000.00 0.00 Canceled 2019-07-22 2019-08-26 2019-07-27 2019-08-17 2019-08-31 2019-12-02 enrollment partners and Framework Selection functional users of the National ID registry NIMC-PPA-32 / Risks assessment of ID4D project implementation, including Component 1: Strengthening Individual risks of data protection and IDA / V2290 the Legal and Institutional Post Consultant Limited 50,000.00 0.00 Canceled 2019-07-22 2019-08-26 2019-07-27 2019-08-17 2019-08-31 2020-01-01 privacy (but not including Framework Selection social and environmental risks) NG-NIMC-169507-CS-CDS / Component 4: Project Individual NIMC PIU: Procurement Officer IDA / V2290 Management and Stakeholder Prior Consultant Direct 60,000.00 27,783.51 Signed 2020-05-04 2020-05-04 2020-05-14 2020-05-20 2020-05-28 2020-06-02 2020-06-25 2020-06-03 2020-12-22 (New) Engagement Selection Component 4: Project Individual NG-NIMC-PPA-41 / PIU: Under IDA / V2290 Management and Stakeholder Post Consultant Open 40,000.00 0.00 2020-05-27 2020-07-13 2020-07-01 2020-07-08 2020-07-22 2020-12-31 Coordinator Implementation Engagement Selection NG-NIMC-PPA-42 / PIU: Component 4: Project Individual Under Environmental Safeguard IDA / V2290 Management and Stakeholder Post Consultant Open 30,000.00 0.00 2020-05-27 2020-07-13 2020-07-01 2020-07-08 2020-07-22 2020-12-31 Implementation Officer Engagement Selection Component 4: Project Individual NG-NIMC-PPA-44 / PIU: Under IDA / V2290 Management and Stakeholder Post Consultant Open 30,000.00 0.00 2020-05-27 2020-07-09 2020-07-01 2020-07-08 2020-07-22 2020-12-31 Biometric Architect Implementation Engagement Selection NG-NIMC-PPA-45 / PIU: Component 4: Project Individual Under Business Analyst/Process IDA / V2290 Management and Stakeholder Post Consultant Open 30,000.00 0.00 2020-05-27 2020-06-18 2020-07-01 2020-07-08 2020-07-22 2020-12-31 Implementation Architect Engagement Selection NG-NIMC-PPA-46 / ECSU: Component 4: Project Individual Under External Communications IDA / V2290 Management and Stakeholder Post Consultant Open 30,000.00 0.00 2020-05-27 2020-07-13 2020-07-01 2020-07-08 2020-07-22 2020-12-31 Implementation Manager Engagement Selection Component 4: Project Individual NG-NIMC-PPA-47 / ECSU: Under IDA / V2290 Management and Stakeholder Post Consultant Open 30,000.00 0.00 2020-05-27 2020-07-13 2020-07-01 2020-07-08 2020-07-22 2020-12-31 M&E Specialist Implementation Engagement Selection Component 4: Project Individual NG-NIMC-PPA-48 / ECSU: Under IDA / V2290 Management and Stakeholder Post Consultant Open 20,000.00 0.00 2020-05-27 2020-06-20 2020-07-01 2020-07-08 2020-07-22 2020-12-31 Communications Assistant Implementation Engagement Selection Component 1: Strengthening Individual NIMC-PPA-11 / OVP SCU: IDA / V2290 the Legal and Institutional Post Consultant Limited 40,000.00 0.00 Canceled 2019-07-22 2019-08-28 2019-07-27 2019-08-03 2019-08-17 2020-02-16 Communications Specialist Framework Selection Component 4: Project Individual NG-NIMC-PPA-50 / ECSU: Under IDA / V2290 Management and Stakeholder Post Consultant Open 30,000.00 0.00 2020-06-30 2020-07-13 2020-08-04 2020-08-11 2020-08-25 2020-12-31 Social Accountability Officer Implementation Engagement Selection Component 4: Project Individual NG-NIMC-PPA-52 / PIU: Under IDA / V2290 Management and Stakeholder Post Consultant Open 30,000.00 0.00 2020-06-30 2020-07-09 2020-08-04 2020-08-11 2020-08-25 2020-12-31 Social Safeguard Officer Implementation Engagement Selection NG-NIMC-PPA-53 / PIU: Component 4: Project Individual Under Database and Integration IDA / V2290 Management and Stakeholder Post Consultant Open 30,000.00 0.00 2020-06-30 2020-07-09 2020-08-04 2020-08-11 2020-08-25 2020-12-31 Implementation Architect Engagement Selection Component 4: Project Individual NG-NIMC-PPA-54 / PIU: Under IDA / V2290 Management and Stakeholder Post Consultant Open 30,000.00 0.00 2020-06-30 2020-07-10 2020-08-04 2020-08-11 2020-08-25 2020-12-31 Security Architect Implementation Engagement Selection Component 4: Project Individual NG-NIMC-PPA-55 / PIU: Test Under IDA / V2290 Management and Stakeholder Post Consultant Open 30,000.00 0.00 2020-06-30 2020-07-09 2020-08-04 2020-08-11 2020-08-25 2020-12-31 and Assurance Architect Implementation Engagement Selection Component 4: Project Individual NG-NIMC-PPA-56 / PIU: Under IDA / V2290 Management and Stakeholder Post Consultant Open 30,000.00 0.00 2020-06-30 2020-07-22 2020-08-04 2020-08-11 2020-08-25 2020-12-31 Software Engineer Implementation Engagement Selection Page 3 NG-NIMC-PPA-43 / PIU: Component 4: Project Individual Under Operations Architect/Change IDA / V2290 Management and Stakeholder Post Consultant Open 30,000.00 0.00 2020-07-13 2020-07-21 2020-08-17 2020-08-24 2020-09-07 2020-12-31 Implementation Manager Engagement Selection Component 4: Project Individual NIMC-PPA-06 / NIMC PIU: IDA / V2290 Management and Stakeholder Prior Consultant Limited 30,000.00 0.00 Canceled 2019-07-22 2019-07-17 2019-07-27 2019-08-16 2019-08-03 2019-08-24 2020-02-23 Procurement Officer Engagement Selection Component 4: Project Individual NG-NIMC-PPA-58 / PIU: M & Under IDA / V2290 Management and Stakeholder Post Consultant Open 30,000.00 0.00 2020-07-20 2020-07-21 2020-08-17 2020-08-24 2020-09-21 2021-09-21 E Specialist (Statistician) Implementation Engagement Selection Component 4: Project Individual NIMC-PPA-02 / NIMC PIU: IDA / V2290 Management and Stakeholder Post Consultant Limited 40,000.00 0.00 Canceled 2019-07-22 2020-07-09 2019-07-27 2019-08-03 2019-08-17 2020-02-16 Technical Lead Engagement Selection Component 4: Project Individual NIMC-PPA-03 / NIMC PIU: IDA / V2290 Management and Stakeholder Post Consultant Limited 40,000.00 0.00 Canceled 2019-07-22 2019-08-28 2019-07-27 2019-08-03 2019-08-17 2020-02-16 Senior M&E Specialist Engagement Selection NIMC-PPA-08 / NIMC PIU: Component 4: Project Individual Internal Communications IDA / V2290 Management and Stakeholder Post Consultant Limited 30,000.00 0.00 Canceled 2019-07-22 2020-07-09 2019-08-17 2019-08-24 2019-09-07 2020-03-08 Officer Engagement Selection Component 4: Project Individual NG-NIMC-PPA-59 / PIU: Under IDA / V2290 Management and Stakeholder Post Consultant Open 40,000.00 0.00 2020-07-20 2020-07-21 2020-08-17 2020-08-24 2020-09-21 2021-09-21 Technical Lead Implementation Engagement Selection NG-NIMC-PPA-60 / PIU: Component 4: Project Individual Under Internal Communication IDA / V2290 Management and Stakeholder Post Consultant Open 30,000.00 0.00 2020-07-20 2020-07-21 2020-08-17 2020-08-24 2020-09-21 2021-09-21 Implementation Officer Engagement Selection Component 4: Project Individual NG-NIMC-PPA-61 / PIU: Under IDA / V2290 Management and Stakeholder Post Consultant Open 30,000.00 0.00 2020-07-20 2020-07-21 2020-08-17 2020-08-24 2020-09-21 2021-09-21 Grievance Redress Manager Implementation Engagement Selection NG-NIMC-PPA-49 / Review Component 4: Project Individual and Business Analysis of Under IDA / V2290 Management and Stakeholder Post Consultant Limited 25,000.00 0.00 2020-07-20 2020-08-07 2020-07-25 2020-09-24 2020-08-08 2020-09-05 2020-12-04 Concept of Self-Enrolment in Implementation Engagement Selection the midst of COVID19 NG-NIMC-PIU-62 / Component 4: Project Individual Coordinator for the Ecosystem Under IDA / V2290 Management and Stakeholder Post Consultant Open 40,000.00 0.00 2020-07-24 2020-07-21 2020-08-21 2020-08-28 2020-09-18 2021-09-18 Coordinating Strategic Unit Implementation Engagement Selection (ESCU) NIMC-PPA-26 / Consultant to Component 4: Project Individual design the project Grievance IDA / V2290 Management and Stakeholder Post Consultant Limited 42,000.00 0.00 Canceled 2019-07-22 2019-08-28 2019-07-27 2019-08-17 2019-08-31 2019-12-02 Redress Mechanism Engagement Selection NIMC-PPA-27 / Consultant to Component 4: Project Individual develop a communications IDA / V2290 Management and Stakeholder Post Consultant Limited 50,000.00 0.00 Canceled 2019-07-22 2019-08-28 2019-07-27 2019-08-03 2019-08-17 2019-11-18 strategy Engagement Selection Component 4: Project Individual NG-NIMC-PPA-51 / ECSU: IDA / V2290 Management and Stakeholder Post Consultant Open 30,000.00 0.00 Canceled 2020-06-30 2020-08-04 2020-08-11 2020-08-25 2020-12-31 Procurement Specialist Engagement Selection Page 4 PROCUREMENT PLAN Version 1.7 – Date: June 17, 2021 INSTITUTIONAL STRENGTHENING FOR IMPROVED VILLAGE SERVICE DELIVERY PROJECT A. Project information: Country: Indonesia Borrower: Republic of Indonesia Project ID: P165543 Financing Agreement IBRD Loan 8941-ID Number: Project Implementation Agency(ies): CPMU: Ministry of Home Affairs (MOHA), Directorate General of Village Government Affairs CPIU: Ministry of Home Affairs (MOHA), Directorate General of Village Government Affairs Ministry of Villages, Directorate General of Village Development and Community Empowerment (PPMD) Ministry of National Development Planning/BAPPENAS, Deputy for Regional Development Directorate for the Development of Disadvantaged Regions, Transmigration and Rural Areas B. Key Dates: 1. Procurement Plan: a. Version 1.0 (for Feb 28, 2019 negotiation) Bank’s Approval to this Mar 12, 2019 version: Period covered by this Apr 1, 2019 – December 31, version: 2020 b. Version 1.6 (previous May 18, 2021 version) Bank’s Approval to this May 28, 2021 version: Period covered by this Apr 1, 2019 – December 31, version: 2023 c. Version 1.7 (this version) June 17, 2021 Bank’s Approval to this June 21, 2021 version: Period covered by this Apr 1, 2019 – December 31, version: 2023 d. [next version, if any] [to be updated] 2. General Procurement Mar 26, 2020 Notice: C. Preamble All Procurement under the Project shall be carried out in accordance with the World Bank’s Procurement Regulations for IPF Borrowers of July 2016, revised November 2017 and August 2018, and the provisions of the Procurement Plan and Project Operations Manual and shall take precedence over any national procurement regulations. In accordance with paragraph 5.9 of the Procurement Regulations, the Bank’s online procurement planning and tracking tools i.e. Systematic Tracking and Exchanges in Procurement (STEP) will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. D. Key Provisions The following conditions apply to all procurement activities in this Procurement Plan. The Bank’s procurement prior review thresholds: The identified procurement risk under this Project is ‘Substantial’. Accordingly, all contracts listed in the Procurement Plan that are at or above the thresholds set out below are subject to the Bank’s prior review. All other contracts are subject to the Bank’s ex-post review. Table 1. Applied Prior Review Threshold Type of procurement Procurement Prior Review Thresholds (US$ millions) Works (including turnkey, supply & installation of 10 plant and equipment, and PPP) Goods, Information Technology and Non- 2 consulting Services Consultants: Firms 1 Consultants: Individuals 0.3 The Bank’s approved selection methods thresholds: The following selection method thresholds shall apply for procurement of goods & information technology, non-consulting services and consulting services of each identified activity. Table 2. Applied Approved Selection Method Threshold Type of procurement and Approved Selection Method Thresholds Approved Selection (US$ millions) Method National International Works (including turnkey, supply & installation of plant and equipment, and PPP) (i) Request for Request for at or above $0.2 and at or above $25 Bids (RFB) less than $25 (ii) Request for Quotations less than $0.2 N/A (RFQ) (iii) Direct Selection On exceptional basis On exceptional basis if justified as per if justified as per paragraph 6.8, 6.9 paragraph 6.8, 6.9 and 6.10 of the and 6.10 of the Procurement Procurement Regulations Regulations Goods, Information Technology and Non-consulting services a. For Goods and Information Technology: (i) Request for Request for at or above $0.1 and at or above $2 Bids (RFB) less than $2 Type of procurement and Approved Selection Method Thresholds Approved Selection (US$ millions) Method National International (ii) Request for Quotations less than $0.1 N/A (RFQ) (iii) Direct Selection On exceptional basis On exceptional basis if justified as per if justified as per paragraph 6.8, 6.9 paragraph 6.8, 6.9 and 6.10 of the and 6.10 of the Procurement Procurement Regulations Regulations b. For Non-consulting Services: (i) Request for Request for at or above $0.1 and at or above $10 Bids (RFB) less than $10 (ii) Request for Quotations less than $0.1 N/A (RFQ) (iii) Direct Selection On exceptional basis On exceptional basis if justified as per if justified as per paragraph 6.8, 6.9 paragraph 6.8, 6.9 and 6.10 of the and 6.10 of the Procurement Procurement Regulations Regulations Consultants: firms a. For Selection of Consulting Firms (i) Quality Cost Based Shortlist of firms for at or above $0.4 Selection (QCBS), Fixed contracts below $0.4 Budget Based Selection may comprise (FBS), Least Cost Based entirely national Selection (LCS) and firms Quality Based Selection (QBS) (ii) Consultant’s less than $0.3 N/A Qualifications Based Selection (CQS) (iii) Direct Selection On exceptional basis On exceptional basis if justified as per if justified as per paragraph 7.13, 7.14 paragraph 7.13, 7.14 and 7.15 of the and 7.15 of the Procurement Procurement Regulations Regulations b. For Selection of Individual Consultants Type of procurement and Approved Selection Method Thresholds Approved Selection (US$ millions) Method National International (i) Open Competitive All, no monetary All, no monetary Selection of Individual threshold threshold Consultants and Limited Competitive Selection of Individual Consultants (ii) Direct Selection of On exceptional basis On exceptional basis Individual Consultants if justified as per if justified as per paragraph 7.39 of paragraph 7.39 of the Procurement the Procurement Regulations Regulations Standard Procurement Documents (SPD): The Bank’s SPD shall be used when approaching the international market (specifically for international competitive procurement and those contracts shall be as specified in the Procurement Plan tables in STEP. Use of National Procurement Procedures: In accordance with paragraphs 5.3 of the Procurement Regulations, when approaching the national market all contracts to be procured through open national competitive procurement will follow the GoI’s procurement regulation. The procedures applicable to the procurement of goods and non-consulting services awarded on the basis of open national competitive procurement shall be those of the Tender method as set forth in the Peraturan Presiden No. 16/2018 and its subsequent amendment Peraturan Presiden No. 12/2021) provided that such arrangements continue to meet requirements set forth under paragraph 5.4 of these Regulations and the following conditions: 1. The procurement is open to eligible firms from any country. There shall not any restriction to the bidders’ participation including mandatory requirement to form in joint venture; 2. Any gaps between National Procurement Procedures and the Procurement Regulations will be addressed and incorporated in the harmonized bidding documents acceptable by the Bank. Use of National e-Procurement System (SPSE): Unless informed otherwise by the Bank in writing, SPSE e-procurement system may be used only for procurement of works, goods and non-consulting services under Request for Bids (RFB) method through national open competitive procurement method, applying the harmonized model bidding documents for national open competitive procurement agreed by the Bank. For selection of consulting services through QCBS method, only the modified SPSE (termed by LKPP as SPSE-“ICB”) may be used applying the Bank’s Standard Request for Proposal (RFP) document. The Bank has further accepted GOI’s proposal for use of SPSE-ICB for selection of consulting services through CQS method applying a modified Bank’s Standard RFP. Two consulting services activities (contracts) under other Bank-financed project are being performed as pilot use of SPSE-ICB for CQS method to ensure that the system is working as intended. Since at the present time LKPP has not yet developed the modified SPSE for procurement of goods, works and non-consulting services under international open Competitive method, nor for selection of consulting services under QBS, LCS, FBS, and individual consultant selection methods, therefore procurement of all contract packages under these methods shall be carried out through non- electronic process with manual issuance of specific procurement notice (request for expression of interest or invitation for bids/proposals and receipt of bids/proposals), until such time that the modified SPSE has been completed by LKPP and assessed by the Bank to be acceptable. If the Bank determines the modified SPSE to be acceptable for use under the above- mentioned remaining procurement methods, the Bank will confirm through the Bank’s written no objection to LKPP and will also notify in writing to CMPU/CPIUs. Use of National e-Catalogue System. Based on the Bank’s assessment of the national e-catalogue system, the Bank allows the Project Implementing Units (PIUs) under World Bank financed projects to use the national e- catalogue for procurement of small value of goods in lieu of the Request for Quotations (RFQ) method specified in these Regulations within the parameters as below: a) For Goods (other than medicines) with estimated cost not more than USD 15,000 equivalent per contract. PIUs may use the national e-catalogue for procuring such items of goods within the above-specified threshold, if such goods are required under the project and specified in the Procurement Plan approved by the Bank. b) Goods (other than medicines) with estimated cost greater than USD 15,000 but less than USD 100,000 equivalent per contract. PIUs may use the national e-catalogue for procuring such items of goods if such goods are required under the project subject to fulfilling the following additional procedural requirement as below: PIU shall carry out a secondary procurement process through mini competition, by comparing the prices of similar goods offered by at least three different suppliers which available in the national e-catalogue and then selecting the Supplier with the lowest evaluated price on the basis of “as delivered" price at final destination (i.e., including inland transportation, insurance, applicable taxes and any other incidental charges for the delivery of the required quantity of goods at final destination). E. Other Relevant Procurement Information • Project Operations Manual (POM) shall set out the operating procedures for procurement and contract implementation matters under the Project written in Bahasa, which shall be consistent with the procedures and rules specified under the Bank’s Procurement Regulations. In case of any difference of interpretation between the POM and the Bank’s Procurement Regulations, the later shall prevail; • CPMU and CPIUs may use its own forms of contract for goods/non- consulting services procured under Request for Quotations (RFQ) method when approaching to national market, acceptable to the Bank; • Advance procurement may be applied under the project and shall be valid by signing of the Loan Agreement. CPMU and CPIUs may commence the procurement process prior to issuance of the DIPA for any anticipated activity to be procured under the Project, while signing of the contract shall be subject to issuance of the DIPA of the respective activity. All contracts shall not be designed as single-year contract, and therefore procurement process shall continue throughout multiple calendar years without limitation of contract period up to end of the GoI’s fiscal year; • Regardless of the Bank’s review requirement (prior or post), the Bank may review technical aspects of procurement documents and other non- procurement matters (terms of reference, statement of works, technical specifications, environmental documents, cost estimate, etc.) related to the procurement activity in question, if needed; • The Bank will continue to provide guidance and support to the CPMUs, and CPIUs for procurement processing through the STEP. • Project Implementation Support Personnel as defined in the PPSD shall not be included in this Procurement Plan. Their selection and hiring procedures shall continue to apply the GoI’s selection and hiring procedures as further defined in the POM. The Procurement Plan is a living document and can be revised if there are any changes during the implementation of the project. PROCUREMENT Indonesia : Institutional Strengthening for Improved Village Service Delivery PLAN General Information Country: Indonesia Bank’s Approval Date of the Original Procurement Plan: 2020-05-07 2021-05-28 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P165543 GPN Date: 2020-03-26 Project Name: Institutional Strengthening for Improved Village Service Delivery Loan / Credit No: IBRD / 89410 D Executing Agency(ies): G PPMD, KEMENDES WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ID-PPMD-190471-GO-RFB / Pengadaan Server Storage dan Virtualisasi, Firewall, Link Promoting Participatory Single Stage - One IBRD / 89410 Post Request for Bids Open - National 1,033,000.00 973,400.83 Completed 2020-09-01 2020-09-21 2020-09-04 2020-09-25 2020-10-13 2020-10-02 2020-10-16 2020-10-14 2020-11-06 2020-12-28 2020-12-23 Controller, DNS Server serta Village Development Envelope Revitalisasi Jaringan Campus LAN Gedung Utama ID-PPMD-190499-GO-RFQ / Pengadaan Infrastruktur Promoting Participatory Request for Single Stage - One IBRD / 89410 Post Limited 97,500.00 98,051.77 Completed 2020-09-06 2020-09-29 2020-10-12 2020-11-03 2020-11-11 2020-12-15 Ruang Kendali dan Media Village Development Quotations Envelope Center ID-PPMD-203501-NC-RFQ / Printing and Distribution of P3PD Support Guidelines Pending Promoting Participatory Request for Single Stage - One Subcomponent 2B: IBRD / 89410 Post Limited 14,145.00 0.00 Implementati 2020-11-13 2020-11-20 2020-12-20 Village Development Quotations Envelope Community Capacity Building on and Social Accountability Systems NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ID-PPMD-169353-NC-RFB / Administrative Services Firm (ASF) for Managing Contracts Promoting Participatory Single Stage - One IBRD / 89410 Prior Request for Bids Open - National 4,000,000.00 3,535,875.79 Signed 2020-05-11 2020-05-18 2020-05-16 2020-06-06 2020-08-19 2020-07-06 2021-01-20 2020-08-10 2021-02-24 2024-12-17 of Technical Assistance Village Development Envelope Supports for MOV under Component 2 ID-PPMD-203511-NC-RFQ / Preparation of Policy Promoting Participatory Request for Single Stage - One Documents and Socialization IBRD / 89410 Post Limited 73,741.00 72,865.12 Completed 2020-11-12 2020-11-05 2020-11-19 2020-11-20 2020-12-31 2020-12-21 Village Development Quotations Envelope Materials of P3PD Subcomponent 2B ID-PPMD-203859-NC-RFQ / Workshop for Regulation Promoting Participatory Request for Single Stage - One IBRD / 89410 Post Limited 30,000.00 27,158.30 Signed 2020-11-12 2020-11-19 2020-11-19 2020-12-08 2020-12-31 Harmonization of Sub- Village Development Quotations Envelope Component 2A-P3PD PIU PMD ID-PPMD-234734-NC-RFB / Strengthening Capacity of Pending Promoting Participatory Single Stage - One Tenaga Pendamping IBRD / 89410 Prior Request for Bids Open - National 2,750,000.00 0.00 Implementati 2021-05-17 2021-05-24 2021-06-07 2021-06-21 2021-07-08 2021-11-05 Village Development Envelope Profesional (TPP) P3PD Project on Fiscal Year 2021 ID-PPMD-234735-NC-RFB / Preparation of P3PD Learning Under Promoting Participatory Single Stage - One Materials Subcomponent 2b IBRD / 89410 Post Request for Bids Open - National 365,000.00 0.00 Implementati 2021-05-17 2021-05-31 2021-05-24 2021-06-03 2021-06-10 2021-06-21 2021-10-19 Village Development Envelope and Women's Leadership on Workshop ID-PPMD-234757-NC-RFB / Technical Guidance for Pending Inclusive Village P3PD and Promoting Participatory Single Stage - One IBRD / 89410 Post Request for Bids Open - National 850,000.00 0.00 Implementati 2021-05-17 2021-05-24 2021-06-03 2021-06-11 2021-06-21 2021-11-28 Tryout of Social Accountability Village Development Envelope on Implementation in P3PD Village CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ID-PPMD-187415-CS-QCBS / Consultant services for NGO Promoting Participatory Quality And Cost- IBRD / 89410 Prior Open - International 3,882,000.00 0.00 Canceled 2020-08-12 2020-10-19 2020-09-02 2020-09-23 2020-10-21 2020-11-04 2020-12-09 2021-01-04 2024-12-24 Village Community Capacity Village Development Based Selection Development Region I ID-PPMD-187419-CS-QCBS / Consultant services for NGO Promoting Participatory Quality And Cost- IBRD / 89410 Prior Open - International 4,327,000.00 0.00 Canceled 2020-08-12 2020-10-19 2020-09-02 2020-09-23 2020-10-21 2020-11-04 2020-12-09 2021-01-04 2024-12-24 Village Community Capacity Village Development Based Selection Development Region II Page 1 ID-PPMD-187423-CS-QCBS / Consultant services for NGO Promoting Participatory Quality And Cost- IBRD / 89410 Prior Open - International 4,436,000.00 0.00 Canceled 2020-08-12 2020-10-19 2020-09-02 2020-09-23 2020-10-21 2020-11-04 2020-12-09 2021-01-04 2024-12-24 Village Community Capacity Village Development Based Selection Development Region III ID-PPMD-240060-CS-QCBS / Community Capacity Development And Social Promoting Participatory Quality And Cost- Accountability Systems IBRD / 89410 Prior Open - International 2,067,500.00 0.00 Under Review 2021-06-21 2021-07-12 2021-08-10 2021-09-07 2021-10-07 2021-11-25 2021-12-27 2024-12-10 Village Development Based Selection Through Digital Platforms (Non-Government Organization) Western Region ID-PPMD-240069-CS-QCBS / Community Capacity Development And Social Promoting Participatory Quality And Cost- Accountability Systems IBRD / 89410 Prior Open - International 2,275,500.00 0.00 Under Review 2021-06-21 2021-07-12 2021-08-10 2021-09-07 2021-10-07 2021-11-25 2021-12-27 2024-12-10 Village Development Based Selection Through Digital Platforms (Non-Government Organization) middle Region ID-PPMD-240074-CS-QCBS / Community Capacity Development And Social Promoting Participatory Quality And Cost- Accountability Systems IBRD / 89410 Prior Open - International 2,340,500.00 0.00 Under Review 2021-06-21 2021-07-12 2021-08-10 2021-09-07 2021-10-07 2021-11-25 2021-12-27 2024-12-10 Village Development Based Selection Through Digital Platforms (Non-Government Organization) Eastern Region INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ID-PPMD-203715-CS-INDV / Procurement of Individual Individual Consultant for Participatory Promoting Participatory Pending IBRD / 89410 Post Consultant Limited 2,840.00 0.00 2020-11-09 2020-11-11 2020-11-13 2020-11-17 2021-01-16 Planning, Inclusion and Social Village Development Implementation Selection Accountability for the P3PD Program, Subcomponent 2B Page 2 PROCUREMENT PLAN (Textual Part) Project information: Support to Enterprise Development and Competitiveness Project (P161590) Project Implementation agency: PADEC Date of the Procurement Plan: Août 2018 Period covered by this Procurement Plan: PPA Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016, revised November 2017 and August 2018) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables. “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is applicable for those contracts identified in the Procurement Plan tables; Other Relevant Procurement Information. “Not Applicable” PROCUREMENT Congo, Republic of : Support to Enterprise Development and Competitiveness Project PLAN General Information Country: Congo, Republic of Bank’s Approval Date of the Original Procurement Plan: 2018-11-07 2021-05-30 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P161590 GPN Date: 2019-08-22 Project Name: Support to Enterprise Development and Competitiveness Project Loan / Credit No: IBRD / P4920, IBRD / 88710 C Executing Agency(ies): G-Support to Economic Diversification WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CG-PADEC-014-F-DPX-18- MOBILIERS DE BUREA / Project implementation and Request for Single Stage - One IBRD / P4920 Post Open - National 60,000.00 49,602.94 Completed 2018-09-21 2018-11-16 2019-04-09 2019-05-15 2019-04-25 Acquisition de mobilier de coordination Quotations Envelope bureau pour l'UGP du PADEC CG-PADEC-015-F-DPX-18- ORDINATEURS UGP / Project implementation and Request for Single Stage - One Acquisition matériels IBRD / P4920 Post Open - National 70,000.00 58,873.14 Completed 2018-09-11 2018-11-06 2018-12-17 2019-05-05 2019-01-16 coordination Quotations Envelope informatiques et de reprographie pour l'UGP CG-PADEC-016-F-DPX-18- ACQUISITION VEHICU / Project implementation and Request for Single Stage - One IBRD / P4920 Post Open - National 280,000.00 259,904.73 Completed 2018-09-08 2018-11-03 2018-12-17 2019-05-02 2019-01-16 Acquisition des véhicules pour coordination Quotations Envelope le Projet CG-PADEC-017-F-SED-18- TOM2PRO / Acquisition et Project implementation and IBRD / P4920 Post Direct Selection Direct 41,000.00 33,334.13 Completed 2018-10-05 2018-11-21 2018-10-10 2018-11-21 2018-11-14 2018-12-17 2019-05-13 2019-01-16 installation du logiciel coordination TOM²PRO CG-PADEC-035-F- FOURNITURES-19 / VEHICULES UNITES OP- Acquisition de 03 véhicules Regulatory and institutional POUR LES Unites support to strenghten the Request for Single Stage - One IBRD / P4920 Post Open - National 228,000.00 148,247.24 Completed 2019-03-12 2019-05-07 2019-05-06 2019-11-03 2019-05-21 operationnelles du PADEC enabling environment for Quotations Envelope (FADPME CPA et COMITE DE private sector development CONCERTATION ENTRE LES ADMINISTRATIONS ET LE SECTEUR PRIVE) CG-PADEC-036-F- FOURNITURES-19 / EQUIP- UNIT- OP- Acquisition Regulatory and institutional matériel et équipement support to strenghten the Request for Single Stage - One informatique pour le FADPME IBRD / P4920 Post Open - National 70,000.00 53,119.37 Completed 2019-04-03 2019-05-29 2019-11-29 2019-11-25 2019-12-21 enabling environment for Quotations Envelope CPA et COMITE DE private sector development CONCERTATION entre les administrations et le secteur prive CG-PADEC-037-F FOURNITURES-19 / MOB UNIT- OP- Acquisition de mobilier Regulatory and institutional de bureau pour les UNites support to strenghten the Request for Single Stage - One operationnelles du PADEC IBRD / P4920 Post Open - National 60,000.00 28,139.28 Completed 2019-03-26 2019-05-21 2019-12-10 2019-11-17 2020-01-24 enabling environment for Quotations Envelope (FADPME, CPA, COMITE DE private sector development CONCERTATION ENTRE LES ADMINISTRATIONS ET LE SECTEUR PRIVE) CG-PADEC-035-F- FOURNITURES-19 / LOGICIEL SUIV EVAL- Acquisition du Project implementation and IBRD / P4920 Post Direct Selection Direct 40,000.00 0.00 Canceled 2019-10-30 2021-05-12 2019-11-04 2019-12-09 2020-06-06 Logiciel de traitement de coordination l'information de suivi- évaluation TOM²PRO CG-PADEC-075-SAC-AC-20 / AC-FOURNITURE DE BUREAU- SELECTION D'UN PRESTATAIRE EN VUE D'UN ACCORD CADRE Under Project implementation and Request for Single Stage - One POUR LA FOURNITURE DES IBRD / P4920 Post Open - National 33,000.00 0.00 Implementati 2020-03-21 2020-05-16 2020-11-12 coordination Quotations Envelope CONSOMMABLES on INFORMATIQUES ET FOURNITURES DE BUREAU DU PADEC CG-PADEC-079-F- FOURNITURES-20 / VEHICULE DE L'ADPME- ACQUISITION Direct support to MSMEs to D'UN VEHICULE DE TYPE 4X4 enhance the development Request for Single Stage - One IBRD / 88710 Post Open - National 90,000.00 72,274.81 Signed 2020-11-04 2020-12-30 2021-03-23 2021-06-28 POUR L'AGENCE DE and competitiveness of Quotations Envelope DEVELOPPEMENT DES PETITES selected value chains ET MOYENNES ENTREPRISES (ADPME) CG-PADEC-078-F- FOURNITURES-20 / EQUIP- ADPME- Acquisition et livraison du matériel et Direct support to MSMEs to équipement informatique enhance the development Request for Single Stage - One IBRD / 88710 Post Limited 59,973.00 75,884.19 Signed 2020-12-02 2021-02-05 2021-01-27 2021-03-23 2021-07-26 pour la Direction générale et and competitiveness of Quotations Envelope les directions selected value chains départementales du Kouilou, du Niari, de la Cuvette et de la Sangha de l'ADPME Page 1 CG-PADEC-081-F- FOURNITURES-20 / Mobilier de bureau- ADPME- Acquisition, installation et Direct support to MSMEs to livraison de mobilier de enhance the development Request for Single Stage - One IBRD / 88710 Post Limited 77,905.00 53,628.75 Signed 2020-12-15 2021-02-05 2021-02-09 2021-03-23 2021-08-08 bureau pour la Direction and competitiveness of Quotations Envelope générale et les directions selected value chains départementales du Kouilou, du Niari, de la Cuvette et de la Sangha de l'ADPME CG-PADEC-084-F-DC-21 / ACQUISITION DE TABLETTES POUR ODK- Acquisition de 55 Under Project implementation and Request for Single Stage - One tablettes pour la collecte IBRD / 88710 Post Limited 36,000.00 0.00 Implementati 2021-04-27 2021-06-22 2021-12-19 coordination Quotations Envelope digitale des données à on distance via l'application ODK Collect CG-PADEC-087- FOURNITURES-RFQ-21 / VEHICULE DE L'APPDZES- ACQUISITION D'UN VEHICULE Regulatory and institutional Pending DE TYPE 4X4 POUR L'AGENCE support to strenghten the Request for Single Stage - One IBRD / 88710 Post Limited 74,000.00 0.00 Implementati 2021-07-05 2021-08-30 2022-02-26 DE PLANIFICATION DE enabling environment for Quotations Envelope on PROMOTION ET DE private sector development DEVELOPPEMENT DES ZONES ECONOMIQUES SPECIALES (APPDZES) CG-PADEC-088- FOURNITURES-RFQ-21 / EQUIP INFORM APPDZES- ACQUISITION DU MATÉRIEL ET Regulatory and institutional EQUIPEMENT INFORMATIQUE Under support to strenghten the Request for Single Stage - One POUR L'AGENCE DE IBRD / 88710 Post Limited 33,250.00 0.00 Implementati 2021-06-22 2021-08-17 2022-02-13 enabling environment for Quotations Envelope PLANIFICATION, DE on private sector development PROMOTION ET DE DÉVELOPPEMENT DES ZONES ECONOMIQUES SPÉCIALES (APPDZES) CG-PADEC-089- FOURNITURES-RFQ-21 / MOBILIER APPDZES- ACQUISITION DU MOBILIER DE Regulatory and institutional Pending BUREAU POUR L'AGENCE DE support to strenghten the Request for Single Stage - One IBRD / 88710 Post Limited 30,000.00 0.00 Implementati 2021-06-30 2021-08-25 2022-02-21 PLANIFICATION, DE enabling environment for Quotations Envelope on PROMOTION ET DE private sector development DÉVELOPPEMENT DES ZONES ECONOMIQUES SPÉCIALES (APPDZES) NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CG-PADEC-051-SAC-19 / GARDIENNAGE CONCERTATION-Recrutement Regulatory and institutional Under dune societe chargee des support to strenghten the Request for Single Stage - One IBRD / P4920 Post Limited 4,080.00 0.00 Implementati 2019-07-02 2019-08-27 2020-02-23 services de gardiennage au enabling environment for Quotations Envelope on Comite de Concertation entre private sector development les administrations publiques et le secteur prive CG-PADEC-053-SAC-19 / NETTOYAGE CONCERTATION- Recrutement dune societe Regulatory and institutional Under chargee de lentretien des support to strenghten the Request for Single Stage - One IBRD / P4920 Post Limited 4,800.00 0.00 Implementati 2019-07-17 2019-09-11 2020-03-09 locaux du Comite de enabling environment for Quotations Envelope on Concertation entre les private sector development administrations publiques et le secteur prive CG-PADEC-055-SAC-19 / ENTR INFORM- Recrutement d'un prestataire chargé de Project implementation and Request for Single Stage - One IBRD / P4920 Post Limited 15,000.00 12,677.42 Signed 2019-07-05 2019-07-25 2019-08-30 2019-09-23 2020-02-26 l'entretien du matériel coordination Quotations Envelope informatique du Projet (y compris frais de maintenance) CG-PADEC-073-SAC-AC-20 / AC-SUPPORT HORS MEDIA- SELECTION D'UN PRESTATAIRE EN VUE D'UN ACCORD CADRE Project implementation and Request for Single Stage - One POUR LA CONCEPTION ET LA IBRD / P4920 Post Open - National 64,000.00 62,214.60 Signed 2020-03-01 2020-09-28 2020-04-26 2020-02-25 2020-10-23 coordination Quotations Envelope FOURNITURE DES SUPPORTS DE COMMUNICATION HORS MEDIA (FADPME & CPA Y COMPRIS) CG-PADEC-074-SAC-AC-20 / AC-SUPPORT AUDIO VISUEL- SELECTION D'UN PRESTATAIRE EN VUE D'UN ACCORD CADRE Project implementation and Request for Single Stage - One POUR LA CONCEPTION ET LA IBRD / P4920 Post Open - National 16,000.00 14,889.72 Signed 2020-03-01 2020-09-28 2020-04-26 2020-02-25 2020-10-23 coordination Quotations Envelope FOURNITURE DE SUPPORTS DE COMMUNICATION AUDIVISUELLE DU PADEC (FADPME & CPA Y COMPRIS) CG-PADEC-080-SAC-20 / ENTR SPLITS- Recrutement d'un prestataire chargé de Under l'entretien et la maintenance Project implementation and Request for Single Stage - One IBRD / 88710 Post Limited 22,800.00 0.00 Implementati 2020-11-16 2021-01-11 2021-07-10 des splits et groupes coordination Quotations Envelope on électrogènes des sites 1 & 2 du Projet (y compris frais de maintenance) Page 2 CG-PADEC-082-SAC-AC-20 / AC-SUPPORT OUTILS DE VISIBILITE-SELECTION D'UN PRESTATAIRE EN VUE D'UN Project implementation and Request for Single Stage - One ACCORD CADRE POUR LA IBRD / 88710 Post Open - National 24,000.00 22,086.24 Signed 2020-11-05 2020-12-31 2020-08-12 2021-06-29 coordination Quotations Envelope CONCEPTION ET LA FOURNITURE DES OUTILS DE VISIBILITE DU PADEC (FADPME & CPA Y COMPRIS) CG-PADEC-083-SAC-AC-20 / AC-SUPPORT OUTILS DE PRODUCTION AUDIO VISUELLE- SELECTION D'UN PRESTATAIRE EN VUE D'UN ACCORD CADRE Project implementation and Request for Single Stage - One IBRD / 88710 Post Limited 18,000.00 16,564.68 Signed 2020-11-07 2020-07-14 2021-01-02 2020-08-12 2021-07-01 POUR LA CONCEPTION ET LA coordination Quotations Envelope FOURNITURE D'OUTILS DE PRODUCTION AUDIO VISUELLE DU PADEC (FADPME & CPA Y COMPRIS) CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CG-PADEC-001-C-SFQ- 18OBSERV DE TRANSPORT / Recrutement d'une firme pour Regulatory and institutional l'étude de faisabilité de support to strenghten the Quality Based IBRD / P4920 Post Open - National 240,000.00 193,845.94 Completed 2018-09-21 2018-11-23 2018-10-12 2018-11-25 2018-11-23 2018-12-23 2019-10-17 2019-01-22 2019-10-17 2019-02-21 2019-10-17 2019-03-28 2019-05-20 2020-03-27 2020-10-14 l'observatoire de transport enabling environment for Selection multimodal pour le Conseil private sector development Congolais des Chargeurs (CCC) CG-PADEC-002-C-SFQC-18 AUDIT PABPS / Recrutement Regulatory and institutional d'une firme chargée de la support to strenghten the Quality And Cost- réalisation d'un audit des IBRD / P4920 Post Open - National 260,000.00 66,503.45 Completed 2018-09-20 2018-11-23 2018-10-11 2018-11-24 2018-11-23 2018-12-22 2019-10-11 2019-01-21 2019-10-11 2019-02-25 2019-10-15 2019-04-01 2019-05-06 2020-03-31 2019-11-26 enabling environment for Based Selection ressources humaines du Port private sector development Autonome de Brazzaville et Ports secondaires (PABPS) CG-PADEC-003-C-SFQ-18- ETUDE MARCHE ZES / Regulatory and institutional Recrutement d'une firme support to strenghten the Quality Based IBRD / P4920 Post Open - International 220,000.00 200,506.30 Completed 2018-11-08 2019-10-22 2018-11-29 2019-04-24 2019-01-12 2019-09-19 2019-02-09 2019-09-19 2019-03-11 2019-09-19 2019-04-10 2019-10-11 2019-05-15 2019-10-25 2020-05-14 2020-06-26 chargée de l'actualisation de enabling environment for Selection l'étude de faisabilité de la ZES private sector development de Pointe Noire CG-PADEC-005-C-SFQ-18- Regulatory and institutional DIAGNOSTIC GUYOT / support to strenghten the Quality Based Recrutement d'un cabinet de IBRD / P4920 Post Open - International 200,000.00 215,087.40 Completed 2018-09-21 2018-11-23 2018-10-12 2018-11-25 2018-11-23 2018-12-23 2019-10-16 2019-01-22 2019-10-16 2019-02-21 2019-10-16 2019-03-28 2019-06-24 2020-03-27 2020-10-19 enabling environment for Selection consultants pour réaliser private sector development l'étude diagnostique du GUOT CG-PADEC-007-C-SFQ-18- ORGANISATION CPA / Direct support to MSMEs to Recrutement d'une assistance Consultant enhance the development technique pour l'organisation IBRD / P4920 Post Qualification Open - International 320,000.00 284,180.49 Signed 2018-10-15 2019-08-05 2018-11-05 2018-12-19 2019-09-18 2019-01-18 2019-09-18 2019-02-22 2019-07-15 2019-08-21 and competitiveness of et l'opérationnaliser du Selection selected value chains Concours de Plan d'Affaires (CPA) CG-PADEC-008-C-SFQ-18 OPERATIONAL FADPME / Recrutement d'une assistance Direct support to MSMEs to Consultant technique pour la gestion et enhance the development IBRD / P4920 Post Qualification Open - International 360,000.00 418,394.45 Signed 2018-10-09 2019-09-04 2018-10-30 2018-12-13 2019-10-02 2019-01-12 2019-10-18 2019-02-16 2019-09-13 2019-08-15 l'opérationnalisation du and competitiveness of Selection Fonds d'Appui au selected value chains Développement des PME (FADPME) CG-CG-PADEC-011-C-SFQC- 18- PLAN DEMERGEN / Recrutement d'une firme chargé de l'élaboration d'une Direct support to MSMEs to stratégie d'émergence et de enhance the development Quality And Cost- IBRD / P4920 Post Open - International 300,000.00 0.00 Canceled 2018-09-20 2020-01-29 2018-10-11 2018-11-24 2018-12-22 2019-01-21 2019-02-25 2019-04-01 2020-03-31 consolidation des TPE/ PME and competitiveness of Based Selection dans les secteurs du selected value chains Tourisme, du Bois, des Transports Logistiques et de l'agro-industrie CG-PADEC-018-C-SFQC-18- AUDIT DES COMPTES / Recrutement d'un cabinet Project implementation and Quality And Cost- IBRD / P4920 Post Open - National 90,000.00 49,562.03 Signed 2018-11-15 2018-11-13 2018-12-06 2019-01-19 2019-01-29 2019-02-16 2019-09-23 2019-03-18 2019-10-11 2019-04-22 2019-10-14 2019-05-27 2019-05-06 2020-05-26 chargé de réaliser l'audit coordination Based Selection administratif, financier et comptable du PPA-PADEC CG-PADEC-032-C-QC-19 / COMM TEXTES REFORMES- Regulatory and institutional Consultant Recrutement d une firme support to strenghten the Under IBRD / P4920 Post Qualification Open - National 30,000.00 0.00 2019-08-22 2021-06-07 2019-09-12 2019-10-26 2019-11-25 2019-12-30 2020-06-27 chargee de l appui a la enabling environment for Implementation Selection sensibilisation des textes de private sector development reformes CG-PADEC-066-C-SQC-19 / STRATEGIE COMM- Consultant Recrutement d'un cabinet de Project implementation and IBRD / 88710 Post Qualification Open - International 300,000.00 252,919.21 Signed 2019-12-05 2020-10-22 2019-12-26 2020-09-15 2020-02-08 2020-11-20 2020-03-09 2020-12-22 2020-04-13 2021-01-28 2020-10-10 consultant pour l'élaboration coordination Selection de la stratégie de communication du PADEC CG-PADEC-067-C-SQC-19 / APPD-ZES-Recrutement d'un cabinet de consultant chargé d'assister le Ministère des Regulatory and institutional Zones Economiques Spéciales Consultant support to strenghten the dans l'opérationnalisation de IBRD / 88710 Post Qualification Open - International 300,000.00 295,303.46 Signed 2020-02-14 2021-03-16 2020-03-06 2020-10-27 2020-04-19 2021-01-11 2020-05-19 2021-02-24 2020-06-23 2021-03-23 2020-12-20 enabling environment for l'Agence de Planification, de Selection private sector development Promotion et de Développement des Zones Economiques Spéciales (APPD- ZES) Page 3 CG-PADEC-076-C-SFQC-20 / ORGANE DE COORDINATION DES CORRIDORS- Regulatory and institutional RECRUTEMENT D'UN CABINET support to strenghten the Quality And Cost- Under DE CONSULTANTS CHARGE DE IBRD / P4920 Post Open - International 318,000.00 0.00 2020-03-06 2021-06-07 2020-03-27 2020-10-07 2020-05-10 2020-06-07 2020-07-07 2020-08-11 2020-09-15 2021-09-15 enabling environment for Based Selection Implementation METTRE EN PLACE L'ORGANE private sector development DE COORDINATION ET DE RÉGULATION DES CORRIDORS ET DES TRANSPORTS CG-PADEC-077-SAC-AC-20 / ÉVÉNEMENTIELLE- RECRUTEMENT D'UN CABINET DE CONSULTANT CHARGEE DE Regulatory and institutional Consultant L'ORGANISATION DES support to strenghten the IBRD / P4920 Post Qualification Open - International 300,000.00 0.00 Under Review 2020-03-13 2020-11-05 2020-04-03 2020-05-17 2020-06-16 2020-07-21 2021-01-17 JOURNEES DE REFLEXION SUR enabling environment for Selection L'ECOSYSTEME DES STARTUPS private sector development ÉVOLUANT DANS LE NUMÉRIQUE A BRAZZAVILLE ET POINTE NOIRE. CG-PADEC-085-C-SQC-21 / CYBERLEGISLATION- Recrutement d'un cabinet de consultants chargé Regulatory and institutional d'organiser les ateliers de Consultant support to strenghten the sensibilisation et de IBRD / 88710 Post Qualification Open - National 150,000.00 0.00 Under Review 2021-04-19 2021-05-03 2021-05-10 2021-06-23 2021-07-23 2021-08-27 2022-02-23 enabling environment for vulgarisation de la cyber Selection private sector development législation congolaise dans les villes de Brazzaville, Pointe Noire, Dolisie, Owando et Ouesso CG-PADEC-086-C-CQS-21 / FORUM SUR LES ZES- Recrutement d'un cabinet de Regulatory and institutional Consultant consultants chargé de support to strenghten the Pending IBRD / 88710 Post Qualification Open - National 100,000.00 0.00 2021-06-30 2021-07-21 2021-09-03 2021-10-03 2021-11-07 2022-05-06 l'organisation sur 03 jours du enabling environment for Implementation Selection Forum sur la Zones private sector development Economique Spéciale (ZES) de Pointe Noire INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CG-PADEC-004C-ED OMT- 18 VISA TOURISTIQUE / Regulatory and institutional Entente directe avec l'OMT support to strenghten the pour appuyer le Ministère du IBRD / P4920 Post Direct Selection Direct 90,000.00 0.00 Canceled 2018-10-17 2019-03-20 2018-10-27 2018-12-31 2019-06-29 enabling environment for Tourisme et de private sector development l'Environnement dans la création du visa touristique CG-PADEC-006-COMP 03CV- 18-SITES WEB DGI / Appui à la Regulatory and institutional Individual mise en place de 02 sites Web support to strenghten the IBRD / P4920 Post Consultant Limited 6,000.00 0.00 Canceled 2018-10-10 2019-01-14 2018-10-15 2019-01-22 2018-11-05 2019-01-22 2018-12-10 2019-06-08 pour la Direction Générale des enabling environment for Selection Impôt & Direction Générale de private sector development la Construction CG-PADEC-009-C-CI-18- MANUEL DU FADPME / Recrutement d'un Consultant Direct support to MSMEs to Individual individuel pour l'élaboration enhance the development IBRD / P4920 Post Consultant Open 60,000.00 53,721.43 Completed 2018-09-24 2018-11-19 2018-11-12 2018-11-19 2018-12-03 2018-11-19 2019-01-07 2018-11-22 2019-07-06 2018-12-18 du manuel de procédures et and competitiveness of Selection des opérations du Fonds selected value chains d'Appui au Développement des PME (FADPME) CG-PADEC-010-C-CI-18- Direct support to MSMEs to MANUELS CPA / Recrutement Individual enhance the development d'un Consultant individuel IBRD / P4920 Post Consultant Open 60,000.00 51,329.92 Completed 2018-09-17 2018-11-22 2018-11-05 2018-11-22 2018-11-26 2018-12-17 2018-12-31 2018-12-17 2019-06-29 2019-01-16 and competitiveness of pour l'élaboration du manuel Selection selected value chains d'opération du CPA CG-PADEC-012-CI-18- SAUVEGARDE ENVIRONNEM / Individual Project implementation and Recrutement d'un spécialiste IBRD / P4920 Post Consultant Open 51,600.00 46,584.30 Signed 2018-09-06 2018-11-22 2018-10-25 2018-11-15 2018-11-22 2018-12-20 2018-11-22 2019-06-18 coordination en sauvegarde Selection environnementale. CG-PADEC-013-CI-18 SAUVEGARDE SOCIALE / Individual Project implementation and Recrutement un consultant IBRD / P4920 Post Consultant Open 51,600.00 46,584.30 Signed 2018-09-10 2018-11-22 2018-10-29 2018-11-19 2018-11-22 2018-12-24 2018-11-22 2019-06-22 coordination national/ spécialiste en Selection sauvegarde sociale CG-PADEC-019-CI-18- MANUEL DE PROC PADEC / Recrutement d'un Consultant Individual personne physique pour Project implementation and IBRD / P4920 Post Consultant Open 40,000.00 32,157.07 Completed 2018-09-19 2018-11-21 2018-11-07 2018-10-01 2018-11-28 2018-11-21 2019-01-02 2018-11-22 2019-07-01 2018-11-30 l'actualisation du manuel des coordination Selection procédures administratives, financières et comptables du PADEC CG-PADEC-020-CI-18- Individual COMPTABLE PADEC / Project implementation and IBRD / P4920 Post Consultant Open 38,400.00 38,240.84 Signed 2018-09-12 2018-11-22 2018-10-31 2018-11-21 2018-11-22 2018-12-26 2018-11-22 2019-06-24 RECRUTEMENT DU coordination Selection COMPTABLE DU PADEC CG-PADEC-021-CI-19 / Individual SPECIALISTE COMM- Project implementation and IBRD / 88710 Post Consultant Open 51,600.00 45,041.96 Signed 2019-02-15 2019-08-19 2019-04-05 2019-08-19 2019-04-26 2019-08-19 2019-05-31 2019-05-06 2019-11-27 Recrutement du Spécialiste en coordination Selection communication du PADEC CG-PADEC-022-CI-19 / SECRETAIRE PERMANENT- Regulatory and institutional Recrutement du Secrétaire Individual support to strenghten the permanent du Comite de IBRD / P4920 Post Consultant Limited 52,800.00 51,921.73 Signed 2019-03-27 2020-07-09 2019-04-01 2020-02-03 2019-04-22 2020-02-28 2019-05-27 2020-02-28 2019-11-23 enabling environment for Concertation entre les Selection private sector development administrations et le secteur prive Page 4 CG-PADEC-023-CI-19 / SP ADJOINT DU DPP-Recrutement Regulatory and institutional du Secretaire permanent Individual support to strenghten the adjoint du Comite de IBRD / P4920 Post Consultant Limited 48,000.00 47,740.12 Signed 2019-03-29 2020-07-09 2019-04-03 2020-01-22 2019-04-24 2020-01-28 2019-05-29 2020-02-28 2019-11-25 enabling environment for Concertation entre les Selection private sector development administrations et le secteur prive CG-PADEC-026-C-CI-19 / COMPT-CONCERTATION- Regulatory and institutional Recrutement d un Comptable Individual support to strenghten the Under pour le Comite de IBRD / P4920 Post Consultant Open 33,600.00 0.00 2019-03-20 2021-06-09 2019-05-08 2019-05-29 2019-07-03 2019-12-30 enabling environment for Implementation Concertation entre les Selection private sector development administrations et le secteur prive CG-PADEC-027-C- COMPARAISON DE 03 CV-19 / SECRETAIRE CONCERTATION- Regulatory and institutional Individual Recrutement dune secretaire support to strenghten the Under IBRD / P4920 Post Consultant Limited 13,200.00 0.00 2019-04-18 2021-06-21 2019-04-23 2019-05-14 2019-06-18 2019-12-15 pour le Comite de enabling environment for Implementation Selection Concertation entre les private sector development administrations et le secteur prive CG-PADEC-028-CI- COMPRAISON DE 03 CV-19 / PLANTON CONCERTATION- Regulatory and institutional Individual Recrutement d un Planton support to strenghten the Under IBRD / P4920 Post Consultant Limited 4,800.00 0.00 2019-03-27 2021-06-21 2019-04-01 2019-04-22 2019-05-27 2019-11-23 pour le Comite de enabling environment for Implementation Selection Concertation entre les private sector development administrations et le secteur prive CG-PADEC-029-CI- COMPARAISON DE 03 CV-19 / CHAUFFEUR CONCERTATION- Regulatory and institutional Individual recrutement d un Chauffeur support to strenghten the IBRD / P4920 Post Consultant Limited 8,400.00 8,720.87 Signed 2019-03-22 2020-01-27 2019-03-27 2019-11-18 2019-04-17 2019-12-13 2019-05-22 2019-12-26 2019-11-18 pour le Comite de enabling environment for Selection Concertation entre les private sector development administrations et le secteur prive CG-PADEC-030-CI- COMPARAISON-03-CV-19 / NETTOYAGE CONCERTATION- Regulatory and institutional Individual Recrutement d'un individu support to strenghten the IBRD / P4920 Post Consultant Limited 4,800.00 0.00 Canceled 2019-04-17 2019-04-22 2019-05-13 2019-06-17 2019-12-14 pour l entretien des bureaux enabling environment for Selection du Comite de Concertation private sector development entre les administrations et le secteur prive CG-PADEC-031-CI- COMPARAISON-CV-19 / GARDIENNAGE Regulatory and institutional CONCERTATION--Selection d Individual support to strenghten the un premier individu pour IBRD / P4920 Post Consultant Limited 4,080.00 0.00 Canceled 2019-04-17 2019-04-22 2019-05-13 2019-06-17 2019-12-14 enabling environment for assurer la securite du siege du Selection private sector development Comite de Concertation entre les administrations et le secteur prive CG-PADEC-033-C-CI-19 / ETUDE DE REFERENCE- Individual Project implementation and Recrutement d un consultant IBRD / P4920 Post Consultant Open 60,000.00 104,441.81 Completed 2019-04-08 2019-09-17 2019-05-27 2019-10-17 2019-06-17 2019-10-17 2019-07-22 2019-08-05 2020-01-18 2020-03-25 coordination individuel charge de realiser l Selection etude de reference du PADEC CG-PADEC-034-C-CI-19 / MANUEL SUIVI EVAL- Individual Recrutement d un consultant Project implementation and IBRD / P4920 Post Consultant Open 60,000.00 48,812.40 Completed 2019-04-15 2019-10-29 2019-06-03 2019-10-30 2019-06-24 2019-10-30 2019-07-29 2019-09-26 2020-01-25 2019-12-31 individuel charge de realiser la coordination Selection manuel de suivi evaluation du Projet PADEC CG-PADEC-038-C-CI-19 / Individual ASSIST PM- Recrutement d'un Project implementation and IBRD / P4920 Post Consultant Open 33,600.00 25,882.32 Signed 2019-04-30 2019-09-17 2019-06-18 2019-09-18 2019-07-09 2019-09-18 2019-08-13 2019-08-01 2020-02-09 Assistant en passation de coordination Selection marchés pour le PADEC CG-PADEC-039-CI- COMPARAISON-03 CV-19 / SECURITE CONCERTATION-- Regulatory and institutional Selection d un deuxieme Individual support to strenghten the individu pour assurer la IBRD / P4920 Post Consultant Limited 4,080.00 0.00 Canceled 2019-04-17 2019-04-22 2019-05-13 2019-06-17 2019-12-14 enabling environment for securite du siege du Comite Selection private sector development de Concertation entre les administrations et le secteur prive CG-PADEC-041-CI- COMPARAISON 03CV-19 / CONSUL INT PLANIFICATION /recrutement d'un consultant Individual Project implementation and en planification stratégique IBRD / P4920 Post Consultant Limited 40,000.00 0.00 Canceled 2019-04-01 2019-05-27 2019-04-06 2019-04-27 2019-06-01 2019-11-28 coordination pour la mission Selection d'opérationnalisation des programmes de diversification par le secteur privé CG-PADEC-042-CI- COMPARAISON 03CV-19 / CONS INT INFORM- Recrutement du consultant en charge de la Individual Project implementation and programmation informatique IBRD / P4920 Post Consultant Limited 32,000.00 0.00 Canceled 2019-04-04 2019-05-27 2019-04-09 2019-04-30 2019-06-04 2019-12-01 coordination en vue de la production du PIV Selection pour la mission d'opérationnalisation des programmes de diversification par le secteur privé Page 5 CG-PADEC-043-CI- COMPARAISON 03CV-19 / CONS INT FINAN-Recrutement Individual d'un consultant en charge du Project implementation and IBRD / P4920 Post Consultant Limited 32,000.00 0.00 Canceled 2019-04-09 2019-05-27 2019-04-14 2019-05-05 2019-06-09 2019-12-06 financement du secteur privé coordination Selection pour la mission d'opérationnalisation du PND par le secteur privé CG-PADEC-044-CI- COMPARAISON 03CV-19 / CONS NAT INDUS- Recrutement d'un consultant Individual Project implementation and en charge du secteur IBRD / P4920 Post Consultant Limited 24,000.00 0.00 Canceled 2019-04-15 2019-05-27 2019-04-20 2019-05-11 2019-06-15 2019-12-12 coordination industriel pour la mission Selection d'opérationnalisation des programmes de diversification par le secteur privé CG-PADEC-045-CI- COMPARAISON 03CV-19 / CONS NAT TOURISME- Recrutement d'un consultant Individual Project implementation and en charge du secteur IBRD / P4920 Post Consultant Limited 24,000.00 0.00 Canceled 2019-04-17 2019-05-27 2019-04-22 2019-05-13 2019-06-17 2019-12-14 coordination touristique pour la mission Selection d'opérationnalisation des programmes de diversification par le secteur privé CG-PADEC-046-CI- COMPARAISON 03 CV-19 / CONS NAT AGRI-Recrutement d'un consultant en charge du Individual Project implementation and secteur agricole pour la IBRD / P4920 Post Consultant Limited 24,000.00 0.00 Canceled 2019-04-18 2019-05-27 2019-04-23 2019-05-14 2019-06-18 2019-12-15 coordination mission d'opérationnalisation Selection des programmes de diversification par le secteur privé CG-PADEC-047-CI- COMPARAISON 03CV-19 / CONS NAT PROGR- Recrutement d'un consultant Individual national en programmation Project implementation and IBRD / P4920 Post Consultant Limited 24,000.00 0.00 Canceled 2019-04-22 2019-05-27 2019-04-27 2019-05-18 2019-06-22 2019-12-19 des investissements privés coordination Selection (PIV) pour la mission d'opérationnalisation des programmes de diversification par le secteur privé CG-PADEC-048-CI- COMPARAISON 03CV-19 / CONS NAT COMM- Recrutement d'un consultant Individual national chargé d'élaborer et Project implementation and IBRD / P4920 Post Consultant Limited 12,000,000.00 0.00 Canceled 2019-04-24 2019-03-04 2019-04-29 2019-05-20 2019-06-24 2019-12-21 de mettre en œuvre la coordination Selection stratégie et le plan de communication des programmes de diversification par le secteur privé CG-PADEC-049-CI- COMPRAISON 03CV-19 / DescriptionCONS NAT COMM- Recrutement d'un consultant Individual national chargé d'élaborer et Project implementation and IBRD / P4920 Post Consultant Limited 24,000.00 0.00 Canceled 2019-03-28 2019-05-27 2019-04-02 2019-04-23 2019-05-28 2019-11-24 de mettre en œuvre la coordination Selection stratégie et le plan de communication des programmes de diversification par le secteur privé CG-PADEC-025-CI-SED-19 / ASS TECH PRIVE-Entente directe avec Monsieur Felix Regulatory and institutional MOUKO pour apporter une support to strenghten the Under assistance technique au IBRD / P4920 Post Direct Selection Direct 100,000.00 0.00 2019-08-14 2021-06-21 2019-08-24 2019-10-28 2020-04-25 enabling environment for Implementation Comite de Concertation entre private sector development les administrations et le secteur prive-Volet secteur prive CG-PADEC-024-CI-SED-19 / ASSIS TECH PUBLIC-Entente directe avec Monsieur Tertius Regulatory and institutional ZONGO pour apporter une support to strenghten the Under assistance technique au IBRD / P4920 Post Direct Selection Direct 120,000.00 0.00 2019-08-14 2021-06-21 2019-08-24 2019-10-28 2020-04-25 enabling environment for Implementation Comite de Concertation entre private sector development les administrations et le secteur prive-Volet secteur public CG-PADEC-052-CI-COMP CV- 19 / VISA TOURIS- Recrutement dun consultant Regulatory and institutional Individual individuel pour appuyer le support to strenghten the IBRD / P4920 Post Consultant Limited 90,000.00 65,617.93 Completed 2019-06-19 2019-08-19 2019-06-24 2019-08-26 2019-07-15 2019-09-18 2019-08-19 2019-07-09 2020-02-15 2019-12-09 Ministere du Tourisme et de enabling environment for Selection lenvironnement dans la mise private sector development en place dun visa touristique en Republique du Congo CG-PADEC-054-CI-COMP CV- 19 / 05 SITES WEB- Recrutement dun consultant charge de realiser les sites Regulatory and institutional web de la Direction generale Individual support to strenghten the de la construction la direction IBRD / P4920 Post Consultant Limited 44,000.00 33,299.40 Signed 2019-06-30 2019-10-01 2019-07-05 2019-10-01 2019-07-26 2019-10-01 2019-08-30 2019-01-18 2020-02-26 enabling environment for generale des impots de la Selection private sector development Mairie du Port Autonome de Pointe Noire et de ll'Agence pour la création des entreprises (Ex CFE) CG-PADEC-056-CI-SED-19 / CONS INT FINAN-Selection directe de Jean STRAGIER en Individual qualite de consultant en Project implementation and IBRD / 88710 Post Consultant Direct 85,000.00 78,846.00 Completed 2019-07-26 2019-09-23 2019-08-05 2019-09-25 2019-08-26 2019-09-25 2019-09-30 2019-06-28 2020-03-28 2020-07-30 charge du financement du coordination Selection secteur privé pour la mission d'opérationnalisation du PND par le secteur privé Page 6 CG-PADEC-57-CI-SED-19 / CONS INT PLANIFICATION- Selection directe de NCHO Individual OGUIE en qualite de Project implementation and IBRD / 88710 Post Consultant Direct 125,000.00 116,994.00 Completed 2019-07-28 2019-09-23 2019-08-07 2019-09-25 2019-08-28 2019-09-25 2019-10-02 2019-06-28 2020-03-30 2020-07-30 consultant en planification coordination Selection strategique pour la mission d'opérationnalisation du PND par le secteur privé CG-PADEC-058-CI-SED-19 / CONS INT PROGR INFOR- Sélection directe de LOKNA DJAOBELE en qualite de Individual consultant en charge de la Project implementation and IBRD / 88710 Post Consultant Direct 86,000.00 78,438.00 Completed 2019-07-29 2019-09-17 2019-08-08 2019-09-19 2019-08-29 2019-09-19 2019-10-03 2019-06-28 2020-03-31 2020-07-30 programmation informatique coordination Selection en vue de la production du PIV pour la mission d'opérationnalisation du PND par le secteur privé CG-PADEC-059-CI-SED-19 / CONS NAT PROGR INVEST- Selection directe de LlYOD ONDZEKI en qualite de Individual consultant en charge de la Project implementation and IBRD / 88710 Post Consultant Direct 30,000.00 20,548.96 Completed 2019-07-29 2019-09-23 2019-08-08 2019-09-23 2019-08-29 2019-09-24 2019-10-03 2019-07-18 2020-03-31 2020-07-30 programmation des coordination Selection investissements Privés (PIV) pour la mission d'opérationnalisation du PND par le secteur privé CG-PADEC-060-CI-SED-19 / CONS NAT AGRICULTURE- Selection directe de Jacques Individual BOUITY en qualite de Project implementation and IBRD / 88710 Post Consultant Direct 40,000.00 26,120.44 Completed 2019-07-30 2019-09-23 2019-08-09 2019-09-25 2019-08-30 2019-09-25 2019-10-04 2019-06-28 2020-04-01 2020-07-30 consultant en charge du coordination Selection secteur agricole pour la mission d'opérationnalisation du PND par le secteur privé CG-PADEC-061-CI-SED-19 / CONS NAT PLAN COM- Selection directe de Jean Pierre GOMA en qualite de Individual consultant chargé d'élaborer Project implementation and IBRD / 88710 Post Consultant Direct 32,000.00 21,710.50 Completed 2019-07-31 2019-09-23 2019-08-10 2019-09-23 2019-08-31 2019-09-24 2019-10-05 2019-07-18 2020-04-02 2020-07-30 et de mettre en oeuvre la coordination Selection strategie de communication et le plan pour la mission d'opérationnalisation du PND par le secteur privé CG-PADEC-062-CI-SED-19 / CONS NAT SECTEUR INDUST- Selection directe de Sylvestre Individual OSSIALA en qualite de Project implementation and IBRD / 88710 Post Consultant Direct 40,000.00 27,730.78 Completed 2019-07-31 2019-09-17 2019-08-10 2019-09-25 2019-08-31 2019-09-25 2019-10-05 2019-06-28 2020-04-02 2020-07-30 consultant en charge du coordination Selection secteur industriel pour la mission d'opérationnalisation du PND par le secteur privé CG-PADEC-063-CI-SED-19 / CONS NAT SECTEUR TOURIS- Selection directe de Jerome Individual MIKOUIZA en qualite de Project implementation and IBRD / 88710 Post Consultant Direct 35,000.00 27,723.16 Completed 2019-07-26 2019-09-17 2019-08-05 2019-09-23 2019-08-26 2019-09-24 2019-09-30 2019-07-18 2020-03-28 2020-07-30 consultant en charge du coordination Selection secteur touristique pour la mission d'opérationnalisation du PND par le secteur privé CG-PADEC-064-CI- COMPARAISON 03 CV-19 / CHAUFFEUR CPA- Direct support to MSMEs to RECRUTEMENT DUN Individual enhance the development CHAUFFEUR POUR LA FIRME IBRD / 88710 Post Consultant Limited 8,730.00 9,369.31 Signed 2019-10-15 2020-08-31 2019-10-20 2020-09-08 2019-11-10 2020-09-08 2019-12-15 2020-09-08 2020-06-12 and competitiveness of CHARGEE DE Selection selected value chains LOPERATIONNALISATION DU CONCOURS DE PLAN DAFFAIRES (CPA) CG-PADEC-065-CI- COMPARAISON 03 CV-19 / CHAUFFEUR FADPME- RECRUTEMENT DUN Direct support to MSMEs to CHAUFFEUR POUR LE Individual enhance the development PRESTATAIRE CHARGE IBRD / 88710 Post Consultant Limited 8,730.00 9,369.31 Signed 2019-10-15 2020-08-31 2019-10-20 2020-09-04 2019-11-10 2020-09-08 2019-12-15 2020-02-17 2020-06-12 and competitiveness of DOPERATIONNALISER LE Selection selected value chains FONDS DAPPUI AU DEVELOPPEMENT DES PETITES ET MOYENNES ENTREPRISES (FADPME) CG-PADEC-070-CI-19 / RECRUTEMENT D'UN Direct support to MSMEs to ASSISTANT EN SUIVI Individual enhance the development EVALUATION POUR LE IBRD / 88710 Post Consultant Open 19,630.00 0.00 Canceled 2019-12-27 2020-07-09 2020-02-14 2020-03-06 2020-04-10 2020-10-07 and competitiveness of PRESTATAIRE CHARGE Selection selected value chains D'ANIMER LE CONCOURS DE PLAN D'AFFAIRES (CPA) CG-PADEC-069-CI-19 / COMPTABLE CPA- Direct support to MSMEs to RECRUTEMENT D'UN Individual enhance the development COMPTABLE POUR LE IBRD / 88710 Post Consultant Open 17,450.00 0.00 Canceled 2019-12-24 2020-07-09 2020-02-11 2020-03-03 2020-04-07 2020-10-04 and competitiveness of PRESTATAIRE CHARGE Selection selected value chains D'ANIMER LE CONCOURS DE PLAN D'AFFAIRES (CPA) CG-PADEC-071-CI-19 / SITE PADEC-RECRUTEMENT D'UN Individual CONSULTANT INDIVIDUEL Project implementation and Under IBRD / 88710 Post Consultant Open 7,000.00 0.00 2020-02-10 2021-06-21 2020-03-30 2020-10-19 2020-04-20 2020-05-25 2020-11-21 CHARGE DE CONCEVOIR LE coordination Implementation Selection SITE INTERNET DU PADEC ET LA PLATEFORME DU CPA Page 7 CG-PADEC-068-C-SED- ERSUMA-19 / ERSUMA- SÉLECTION DIRECTE DE ERSUMA POUR LA FORMATION Regulatory and institutional DES ACTEURS DU support to strenghten the Under DÉVELOPPEMENT DES IBRD / 88710 Post Direct Selection Direct 250,000.00 0.00 2020-02-11 2021-05-31 2020-02-21 2020-09-29 2020-04-26 2020-10-23 enabling environment for Implementation ENTREPRISES ET DE LA private sector development COMPÉTITIVITÉ EN RÉPUBLIQUE DU CONGO SUR LES ACTES UNIFORMES DE L'OHADA CG-PADEC-072-CI-20 / AUDIT ENVIRONNEMENTAL- Recrutement d’un consultant en vue de l’élaboration d’un Individual Guide d’audit Project implementation and IBRD / P4920 Post Consultant Open 54,000.00 66,332.08 Completed 2020-02-14 2020-07-09 2020-04-03 2020-04-17 2020-04-24 2020-04-23 2020-05-29 2020-04-24 2020-11-25 2020-12-30 environnemental et social des coordination Selection MPME et du renforcement des capacités des spécialistes en sauvegardes dans le cadre de la mise en œuvre du PADEC CG-PADEC-032-C-CI-19 / STRATEGIE API-Recrutement d Regulatory and institutional un consultant individuel pour Individual support to strenghten the l elaboration de l etude IBRD / P4920 Post Consultant Open 100,000.00 0.00 Canceled 2019-08-22 2021-01-06 2019-10-10 2019-10-31 2019-12-05 2020-06-02 enabling environment for strategique de promotion des Selection private sector development investissements assortie d un plan daction CG-PADEC-090-C-CI-21 / REVUE A MI PARCOURS- Individual RECRUTEMENT DU Project implementation and Under IBRD / 88710 Post Consultant Open 70,000.00 0.00 2021-06-15 2021-06-01 2021-08-03 2021-08-24 2021-09-28 2022-03-27 CONSULTANT CHARGE DE coordination Implementation Selection REALISER LA REVUE A MI PARCOUSR DU PADEC. Page 8 Procurement Plan General 1. Project Information Country: KENYA 2. Project Name: Kenya Informal Settlements Improvement Project 2 3. Project ID: P167814 4. Project Implementation Agency: Ministry of Transport and Infrastructure 5. Date of the Procurement Plan: Jan 26,2021 6. Period Covered by this procurement plan: 18 months I. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. II. Bank’s Standard Procurement Documents: The Bank’s Standard Procurement Documents shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. III. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in The Public Procurement and Assets Disposal Act, 2015 such arrangements shall be subject to paragraph 5.3 and 5.4 of the Procurement Regulations : When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. IV. Prequalification: Not Applicable 1 V. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable VI. Procurement of Second-Hand Goods as specified under paragraph 5.11 of the Procurement Regulations: Not Applicable VII. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Not Applicable VIII. Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. Not Applicable IX. Other Relevant Procurement Information Not Applicable 2 X. Threshold for Prior Review, Procurement Approaches and Methods – Good, Works and Non- Consulting Services Procurement Approaches and Methods (US$ millions) Prior Review Category Open Open National Request for (US$ millions) International Quotation (RfQ) Works Goods, IT, and non-consulting services Post Review: All contracts not subject to prior review shall be subject to post review. Summary of the procurement packages for Good, Works and Non-Consulting Services Sr. Contract Estima Revie Market Selection Evaluati Procurem Prequali Domesti Expect Expect No Description ted w by Approac Method on ent fication c ed date ed date Cost Bank h (Open- (RFP, Options Process (Yes/ Prefere of bid/ of (US$) (Prio National/ RFB, (Most (Single No) nce propos Contra r/ Limited RFQ, DS Advanta stage- (Yes/No al ct Post) etc.) etc.) geous single ) openin Signat Bid, envelope g ure BAFO, etc.) Rated Criteria etc.) GOODS 1. 2. 3. 4. Total Goods 613,00 0 WORKS Total works 3 NON-CONSULTING SERVICES Total Non- Consulting Services XI. Thresholds for Prior Review, Selection Approaches and Methods – Consulting Services Category Prior Review Short List of National Consultants (US$ millions) Consulting Engineering and Construction Supervision Services Consultants (Firms) Individual Consultants Note: Consultancy services estimated to cost equivalent to US $ 300,000 and above per contract shall be advertised in the United Nations Development Business (UNDB) online in addition to advertising in national newspaper(s) of wide circulation and/or regional newspaper. XII. Summary of the procurement packages for Consulting Services Sr. Contract Description Estimat Review Market Selection Shortlisti Expected Expected No ed Cost by Approach Method ng date of bid/ date of (US$) Bank (Open - (QCBS, (Yes/ No) proposal Contract (Prior/ International FBBS, LCBS, opening Signature Post) / National/ QBS, CQS, etc.) DS etc.) 1. 2. 3. 4. 5. 6. 4 7. 8. 9. 10. Total Consulting Services 5 Appendix 1 Letter of Acceptance of the World Bank’s Anti-Corruption Guidelines and Sanctions Framework Date: Invitation of Bids/Proposals No.__________ To: ___________________________________________________________________________ We, along with our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not) consultants and personnel, acknowledge and agree to abide by the World Bank’s policy regarding Fraud and Corruption (corrupt, fraudulent, collusive, coercive, and obstructive practices), as set out and defined in the World Bank’s Anti-Corruption Guidelines1 in connection with the procurement and execution of the contract (in case of award), including any amendments thereto. We declare and warrant that we, along our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not), consultants and personnel, , are not subject to, and are not controlled by any entity or individual that is subject to, a temporary suspension, early temporary suspension, or debarment imposed by a member of the World Bank Group, including, inter alia, a cross-debarment imposed by the World Bank Group as agreed with other international financial institutions (including multilateral development banks), or through the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement. Further, we are not ineligible under the laws or official regulations of [Insert name of Employer as per bidding document] or pursuant to a decision of the United Nations Security Council. We confirm our understanding of the consequences of not complying with the World Bank’s Anti-Corruption Guidelines, which may include the following: a. rejection of our Proposal/Bid for award of contract; b. in the case of award, termination of the contract, without prejudice to any other remedy for breach of contract; and c. sanctions, pursuant to the Bank’s Anti-Corruption Guidelines and in accordance with its prevailing sanctions policies and procedures as set forth in the Bank’s Sanctions Framework. This may include a public declaration of ineligibility, either indefinitely or for a stated period of time, (i) to be awarded or otherwise benefit from a Bank- financed contract, financially or in any other manner;2 (ii) to be a nominated3 sub- 1Guidelines on Preventing and Combating Fraud and Corruption in Projects Financed by International Bank for Reconstruction and Development Loans and the International Development Agency Credits and Grants, dated October 15, 2006, and revised in January 2011 and July 2016, as they may be revised from time to time. 2 For the avoidance of doubt, a sanctioned party’s ineligibility to be awarded a contract shall include, without limitation, (i) applying for pre-qualification, expressing interest in a consultancy, and bidding, either directly or as a nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider, in respect of such contract, and (ii) entering into an addendum or amendment introducing a material modification to any existing contract. 6 contractor, consultant, manufacturer or supplier, or service provider of an otherwise eligible firm being awarded a Bank-financed contract; and (iii) to receive the proceeds of any loan made by the Bank or otherwise to participate further in the preparation or implementation of any Bank-financed project. We understand that we may be declared ineligible as set out above upon: a. completion of World Bank Group sanctions proceedings according to its prevailing sanctions procedures; b. cross-debarment as agreed with other international financial institutions (including multilateral development banks); c. the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement; or d. temporary suspension or early temporary suspension in connection with an ongoing World Bank Group sanctions proceeding. For avoidance of doubt, the foregoing effects of ineligibility do not extend to a sanctioned firm’s or individual’s execution of its ongoing Bank-financed contracts (or its ongoing sub-agreements under such contracts) that are not the subject of a material modification, as determined by the Bank. We shall permit, and shall cause our sub-contractors, sub-consultants, agents (whether declared or not), personnel, consultants, service providers or suppliers, to permit the Bank to inspect4 all accounts, records, and other documents relating to the procurement process and/or contract execution (in the case of award), and to have them audited by auditors appointed by the Bank. We agree to preserve all accounts, records, and other documents (whether in hard copy or electronic format) related to the procurement and execution of the contract. Name of the Bidder/Consultant: Name of the person duly authorized to sign the Bid/Proposal on behalf of the Bidder/Consultant: 3 A nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider (different names are used depending on the particular bidding document) is one which has been: (i) included by the bidder in its pre-qualification application or bid because it brings specific and critical experience and know-how that allow the bidder to meet the qualification requirements for the particular bid; or (ii) appointed by the Borrower. 4 Inspections in this context are usually investigative (i.e., forensic) in nature: they involve fact-finding activities undertaken by the Bank or persons appointed by the Bank to address specific matters related to investigations/audits, such as evaluating the veracity of an allegation of possible Fraud and Corruption, through the appropriate mechanisms. Such activity includes but is not limited to accessing and examining a firm's or individual's financial records and information, and making copies thereof as relevant; accessing and examining any other documents, data, and information (whether in hard copy or electronic format) deemed relevant for the investigation/audit, and making copies thereof as relevant; interviewing staff and other relevant individuals; performing physical inspections and site visits; and obtaining third-party verification of information. 7 Title of the person signing the Letter: 8 PROCUREMENT Kenya : Second Kenya Informal Settlements Improvement Project PLAN General Information Country: Kenya Bank’s Approval Date of the Original Procurement Plan: 2021-01-29 2021-06-02 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P167814 GPN Date: 2021-01-08 Project Name: Second Kenya Informal Settlements Improvement Project Loan / Credit No: IDA / 67590 M Executing Agency(ies): inistry of Transport and Infrastructure WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KE-MOTI-214040-CS-QCBS / Consultancy Service for Institutional capacity Quality And Cost- Mapping and Preparation of IDA / 67590 development for slum Post Open - National 1,600,000.00 0.00 Canceled 2021-02-10 2021-03-03 2021-04-16 2021-05-14 2021-06-13 2021-07-18 2021-08-22 2022-08-22 Based Selection National Geodatabase for upgrading Slums/ Informal settlements KE-MOTI-214043-CS-QCBS / Consultancy Service for Institutional capacity Capacity Assessment and Quality And Cost- Pending IDA / 67590 development for slum Post Open - International 300,000.00 0.00 2021-02-14 2021-03-07 2021-04-20 2021-05-18 2021-06-17 2021-07-22 2021-08-26 2022-08-26 Implementation Plan for Based Selection Implementation upgrading Counties and KISIP for Slum Upgrading. KE-MOTI-215295-CS-QCBS / Consultancy Services to undertake Physical Planning, Cadastral Survey and detailed Integrated settlement Quality And Cost- Topographical Survey of 10 IDA / 67590 Post Open - International 1,300,000.00 0.00 Canceled 2021-02-08 2021-05-12 2021-03-01 2021-04-14 2021-05-12 2021-06-11 2021-07-16 2021-08-20 2022-08-20 upgrading Based Selection selected Informal Settlements in Kilifi, Kitui, Makuenei and Taita Taveta Counties Lot V- Cluster 1 KE-MOTI-215297-CS-QCBS / Consultancy Services to undertake Physical Planning, Cadastral survey and detailed Integrated settlement Quality And Cost- IDA / 67590 Post Open - International 1,400,000.00 0.00 Canceled 2021-02-08 2021-05-12 2021-03-01 2021-04-14 2021-05-12 2021-06-11 2021-07-16 2021-08-20 2022-08-20 Topographical Survey of 11 upgrading Based Selection selected informal settlements in Tana River county. Lot V - Cluster 4 KE-MOTI-215299-CS-QCBS / Consultancy Services to undertake Physical Planning, Cadastral Survey and detailed Integrated settlement Quality And Cost- Topographical Survey of 8 IDA / 67590 Post Open - International 1,300,000.00 0.00 Canceled 2021-02-08 2021-05-12 2021-03-01 2021-04-14 2021-05-12 2021-06-11 2021-07-16 2021-08-20 2022-08-20 upgrading Based Selection selected Informal Settlements in Siaya, Homabay, Bungoma, Transzoia and West Pokot Counties Lot V- Cluster 3 KE-MOTI-215300-CS-QCBS / Consultancy Services to undertake Physical Planning, Cadastral Survey and detailed Integrated settlement Quality And Cost- Topographical Survey of 11 IDA / 67590 Post Open - International 1,300,000.00 0.00 Canceled 2021-02-08 2021-05-12 2021-03-01 2021-04-14 2021-05-12 2021-06-11 2021-07-16 2021-08-20 2022-08-20 upgrading Based Selection selected informal settlements in Kiambu, Tharaka Nithi and Machakos Counties. Lot V - Cluster 2 KE-MOTI-214044-CS-QCBS / Consultancy Services for Program management and Quality And Cost- IDA / 67590 Post Open - International 500,000.00 0.00 Under Review 2021-02-17 2021-06-10 2021-03-10 2021-04-23 2021-05-21 2021-06-20 2021-07-25 2021-08-29 2022-08-29 Technical Assistance on an coordination Based Selection Independent Fiduciary Agency KE-MOTI-216645-CS-QCBS / Consultancy Services for Program management and Quality And Cost- IDA / 67590 Post Open - International 1,800,000.00 0.00 Canceled 2021-02-15 2021-03-08 2021-04-21 2021-05-19 2021-06-18 2021-07-23 2021-08-27 2022-08-27 Independent Performance coordination Based Selection Assessment KE-MOTI-214041-CS-QCBS / Consultancy Service for Institutional capacity Quality And Cost- Pending Review and Development of IDA / 67590 development for slum Post Open - International 600,000.00 0.00 2021-02-14 2021-03-07 2021-04-20 2021-05-18 2021-06-17 2021-07-22 2021-08-26 2022-08-26 Based Selection Implementation the National Slum Upgrading upgrading and Prevention Strategies Page 1 KE-MOTI-218292-CS-QCBS / Consultancy Services to Develop Socio-Economic Inclusion Plans, Toolkit for Crime and Violence Prevention Through Environmental Socio-economic inclusion Quality And Cost- Pending IDA / 67590 Prior Open - International 4,000,000.00 0.00 2021-02-21 2021-03-14 2021-04-27 2021-05-25 2021-06-24 2021-07-29 2021-09-02 2022-09-02 Design (CPTED) planning Based Selection Implementation Investments,Strategy and Guidelines of Utilization, Preparation of Mechanism and Guidelines of Community Level KE-MOTI-214793-CS-QCBS / Consultancy Services for Review and repackaging of existing Engineering designs, Procurement Integrated settlement Quality And Cost- Under Documents,Updating RAP & IDA / 67590 Prior Open - International 700,000.00 0.00 2021-02-15 2021-04-22 2021-03-08 2021-04-21 2021-05-19 2021-06-18 2021-07-23 2021-08-27 2022-08-27 upgrading Based Selection Implementation ESIA Reports,and supervision of construction works in informal settlements in Kisumu and Kakamega counties KE-MOTI-214833-CS-QCBS / Consultancy Services for Review and Repackaging of Existing Engieering Integrated settlement Quality And Cost- Under Designs,Procurement IDA / 67590 Prior Open - International 700,000.00 0.00 2021-02-15 2021-04-22 2021-03-08 2021-04-21 2021-05-19 2021-06-18 2021-07-23 2021-08-27 2022-08-27 upgrading Based Selection Implementation Documents,Updating RAPs & ESIA Reports and Supervision of Construction works in the counties of Nairobi & Nakuru KE-MOTI-214831-CS-QCBS / Consultancy Services for Review and Repackaging of existing Engineering Designs, procurement Integrated settlement Quality And Cost- Under IDA / 67590 Prior Open - International 500,000.00 0.00 2021-02-15 2021-04-22 2021-03-08 2021-04-21 2021-05-19 2021-06-18 2021-07-23 2021-08-27 2022-08-27 documents,Updating RAPs & upgrading Based Selection Implementation ESIA Reports and Supervision of Construction works in the counties of Kilifi and Mombasa. KE-MOTI-235017-CS-QCBS / Consultancy Services to undertake Physical Planning, Cadastral survey and detailed Integrated settlement Quality And Cost- IDA / 67590 Prior Open - International 1,400,000.00 0.00 Under Review 2021-05-21 2021-06-11 2021-07-25 2021-08-22 2021-09-21 2021-10-26 2021-11-30 2023-05-24 Topographical Survey of 11 upgrading Based Selection selected informal settlements in Tana River county. Lot V - Cluster 4 KE-MOTI-235021-CS-QCBS / Consultancy Services to undertake Physical Planning, Cadastral Survey and detailed Integrated settlement Quality And Cost- Topographical Survey of 8 IDA / 67590 Prior Open - International 1,300,000.00 0.00 Under Review 2021-05-21 2021-06-11 2021-07-25 2021-08-22 2021-09-21 2021-10-26 2021-11-30 2023-05-24 upgrading Based Selection selected Informal Settlements in Siaya, Homabay, Bungoma, Transzoia and West Pokot Counties Lot V- Cluster 3 KE-MOTI-235022-CS-QCBS / Consultancy Services to undertake Physical Planning, Cadastral Survey and detailed Integrated settlement Quality And Cost- Topographical Survey of 11 IDA / 67590 Prior Open - International 1,300,000.00 0.00 Under Review 2021-05-21 2021-06-11 2021-07-25 2021-08-22 2021-09-21 2021-10-26 2021-11-30 2023-05-24 upgrading Based Selection selected informal settlements in Kiambu, Tharaka Nithi and Machakos Counties. Lot V - Cluster 2 KE-MOTI-235024-CS-QCBS / Consultancy Services to undertake Physical Planning, Cadastral Survey and detailed Integrated settlement Quality And Cost- Topographical Survey of 10 IDA / 67590 Prior Open - International 1,300,000.00 0.00 Under Review 2021-05-21 2021-06-11 2021-07-25 2021-08-22 2021-09-21 2021-10-26 2021-11-30 2023-05-24 upgrading Based Selection selected Informal Settlements in Kilifi, Kitui, Makuenei and Taita Taveta Counties Lot V- Cluster 1 KE-MOTI-238013-CS-QCBS / Consultancy Services for Program management and Quality And Cost- Pending IDA / 67590 Prior Open - International 1,800,000.00 0.00 2021-06-11 2021-07-02 2021-08-15 2021-09-12 2021-10-12 2021-11-16 2021-12-21 2023-12-11 Independent Performance coordination Based Selection Implementation assessment KE-MOTI-238027-CS-QCBS / Consultancy Service for Institutional capacity Quality And Cost- Pending Mapping and Preparation of IDA / 67590 development for slum Prior Open - International 1,600,000.00 0.00 2021-06-11 2021-07-02 2021-08-15 2021-09-12 2021-10-12 2021-11-16 2021-12-21 2022-04-20 Based Selection Implementation National Geodatabase for upgrading Slums/ Informal settlements INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KE-MOTI-214054-CS-INDV / Individual Consultancy Services for Program management and Under IDA / 67590 Post Consultant Open 180,000.00 0.00 2021-02-14 2021-03-16 2021-04-04 2021-04-25 2021-05-30 2021-11-26 Individual Program Assistant coordination Implementation Selection Consultant (1No) KE-MOTI-214061-CS-INDV / Individual Consultancy Services for Program management and Under IDA / 67590 Post Consultant Open 160,000.00 0.00 2021-02-17 2021-03-16 2021-04-07 2021-04-28 2021-06-02 2021-11-29 Individual Environmental coordination Implementation Selection Safeguard Consultant (1No) KE-MOTI-215303-CS-INDV / Individual Consultancy Services for a Integrated settlement Under IDA / 67590 Post Consultant Open 155,000.00 0.00 2021-02-08 2021-03-22 2021-03-29 2021-04-19 2021-05-24 2021-11-20 Land Surveyor Consultant ( 1 upgrading Implementation Selection No) Page 2 KE-MOTI-215304-CS-INDV / Individual Consultancy Services for a Integrated settlement Under IDA / 67590 Post Consultant Open 155,000.00 0.00 2021-02-08 2021-03-22 2021-03-29 2021-04-19 2021-05-24 2021-11-20 Land Administration upgrading Implementation Selection Consultant ( 1 No) KE-MOTI-216647-CS-INDV / Individual Consultancy Services for Integrated settlement Under IDA / 67590 Post Consultant Open 149,000.00 0.00 2021-02-07 2021-03-25 2021-03-28 2021-04-18 2021-05-23 2021-11-19 Individual Physical Planning upgrading Implementation Selection Consultants KE-MOTI-215103-CS-INDV / Individual Consultancy Services for Civil Integrated settlement Under IDA / 67590 Prior Consultant Open 306,000.00 0.00 2021-02-08 2021-03-31 2021-03-29 2021-04-19 2021-05-24 2021-11-20 Engineer ( Individual upgrading Implementation Selection Consultant) KE-MOTI-216970-CS-INDV / Individual Consultancy Services for Program management and Under IDA / 67590 Post Consultant Open 170,000.00 0.00 2021-02-08 2021-03-16 2021-03-29 2021-04-19 2021-05-24 2021-11-20 Individual Social Safeguard coordination Implementation Selection Consultant KE-MOTI-213869-CS-INDV / Individual Program management and Under Consultancy Services for IDA / 67590 Prior Consultant Open 160,000.00 0.00 2021-02-08 2021-03-18 2021-03-29 2021-04-19 2021-05-24 2023-05-14 coordination Implementation Procurement Consultant Selection KE-MOTI-214048-CS-INDV / Individual Consultancy Services for Program management and Under IDA / 67590 Prior Consultant Open 200,000.00 0.00 2021-02-18 2021-03-23 2021-04-08 2021-04-29 2021-06-03 2021-11-30 Individual Communication coordination Implementation Selection Consultant KE-MOTI-216641-CS-INDV / Individual Integrated settlement Under Consultancy Services for Civil IDA / 67590 Prior Consultant Open 306,000.00 0.00 2021-02-08 2021-04-12 2021-03-29 2021-04-19 2021-05-24 2021-11-20 upgrading Implementation Engineer (Individual) Selection KE-MOTI-216642-CS-INDV / Individual Integrated settlement Under Consultancy Services for Civil IDA / 67590 Prior Consultant Open 306,000.00 0.00 2021-02-08 2021-03-31 2021-03-29 2021-04-19 2021-05-24 2021-11-20 upgrading Implementation Engineer (Individual) Selection KE-MOTI-216648-CS-INDV / Individual Consultancy Services for Integrated settlement Under IDA / 67590 Post Consultant Open 149,000.00 0.00 2021-02-07 2021-03-25 2021-03-28 2021-04-18 2021-05-23 2021-11-19 Individual Physical Planning upgrading Implementation Selection Consultant KE-MOTI-216656-CS-INDV / Individual Consultancy Services for Integrated settlement Under IDA / 67590 Post Consultant Open 170,000.00 0.00 2021-02-08 2021-03-16 2021-03-29 2021-04-19 2021-05-24 2021-11-20 Individual Social Safeguards upgrading Implementation Selection Expert (Individual) KE-MOTI-216657-CS-INDV / Individual Consultancy Services for Integrated settlement Under IDA / 67590 Post Consultant Open 170,000.00 0.00 2021-02-08 2021-03-16 2021-03-29 2021-04-19 2021-05-24 2021-11-20 Individaul Social Safeguards upgrading Implementation Selection Expert KE-MOTI-223918-CS-INDV / Consultancy Services for Individual Integrated settlement Under Individual Geographical IDA / 67590 Post Consultant Open 170,000.00 0.00 2021-03-15 2021-03-22 2021-05-03 2021-05-24 2021-06-28 2021-12-25 upgrading Implementation Information System (GIS) Selection Consultant KE-MOTI-223919-CS-INDV / Individual Consultancy Services for Program management and Under IDA / 67590 Post Consultant Open 150,000.00 0.00 2021-03-15 2021-04-29 2021-05-03 2021-05-24 2021-06-28 2021-12-25 Individual Urban Planning coordination Implementation Selection Consultant to assist the CoG KE-MOTI-223920-CS-INDV / Individual Consultancy Services for Program management and Under IDA / 67590 Post Consultant Open 150,000.00 0.00 2021-03-23 2021-04-29 2021-05-11 2021-06-01 2021-07-06 2023-06-26 Individual Procurement coordination Implementation Selection Consultant to assist the CoG Page 3 Sample Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan [This is the first procurement plan) 2. Date of General Procurement Notice: April 25, 2017 3. Period covered by this procurement plan: September 2016 to June 2017 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: [Thresholds for applicable procurement methods (not limited to the list below) will be determined by the Procurement Specialist /Procurement Accredited Staff based on the assessment of the implementing agency’s capacity.] Procurement Method Prior Review Comments Threshold US$ 1. ICB and LIB (Goods) Above US$ 1,500,000 All 2. NCB (Goods) NA 3. ICB (Works) Above US$ 7 million All 4. NCB (Works) NA 5. ICB and LIB (Non-Consultant Above US$ 1,500,000 All Services) 6 NCB (Non-Consultant Services) NA [Add other methods if necessary] 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: [CDD project implementation Manual to be issued by DRDIP PIU, MoANR for Bank approval) 4. Reference to (if any) Project Operational/Procurement Manual: DRDIP Procurement Manual to be issued by DRDIP PIU. 5. Any Other Special Procurement Arrangements: NA 6. Summary of the Procurement Packages planned during the first 18 July 9, 2010 months after project effectiveness ( including those that are subject to retroactive financing and advanced procurement) [List the Packages which require Bank’s prior review first and then the other packages] 1 2 3 4 5 6 7 Ref. Descripti Estimat Packages Dome Review Comme No. on ed stic by Bank nts Cost Prefe (Prior / US$ rence Post) million (yes/ no) Summary NA NA NA NA of the ICB (Works) Summary 6.69 4 No Prior of the ICB (Goods) Summary 3.8 9 No Post All of the NCB (Works) Summary 14.70 14 No Post All of the NCB (Goods) Summary NA NA NA NA of the ICB (Non- Consultant Services) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Commentes Threshold 1. Competitive Methods (Firms) Above US$ 500,000 2. Single Source (Firms) All 3. Individual Above US$ 200,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: NA July 9, 2010 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description Estimat Package Review Comment of ed s by Bank s Assignmen Cost (Prior / t US$ Post) million Summary 0.35 2 Prior of number of contracts that will be let under QCBS Summary 1.4 38 Post LCS/ IC of number of contracts that will be let under other methods July 9, 2010 PROCUREMENT Eastern Africa : Development Response to Displacement Impacts Project in the HoA PLAN General Information Country: Eastern Africa Bank’s Approval Date of the Original Procurement Plan: 2017-08-10 2021-05-19 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P152822 GPN Date: Project Name: Development Response to Displacement Impacts Project in the HoA Loan / Credit No: IDA / 58210 Office of the Prime Minister Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned UG-OPM-22288-CW-RFQ / Project Management, and Single Stage - One 2018-09- Partitioning of offices at IDA / 58210 Post Request for Bids Limited 32,877.00 0.00 Canceled 2017-11-30 2017-12-05 2018-01-16 2018-02-15 2018-03-22 Monitoring and Evaluation Envelope 18 Kampala GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual UG-OPM-22297-GO-RFQ / Project Management, and Request for Single Stage - One Installation of Air conditioners IDA / 58210 Post Limited 19,178.00 12,369.46 Completed 2017-10-28 2018-02-02 2017-12-23 2018-04-06 2018-06-21 2018-04-28 Monitoring and Evaluation Quotations Envelope at the DRDIP Kampala office UG-OPM-22304-GO-RFQ / Project Management, and Request for Single Stage - One Installation of Window Blinds IDA / 58210 Post Limited 2,740.00 2,567.46 Completed 2017-10-28 2018-02-02 2017-12-23 2018-03-09 2018-06-21 2018-05-21 Monitoring and Evaluation Quotations Envelope at the Kampala offices UG-OPM-22310-GO-RFQ / Procurement of Assorted Office Furniture (1.No. Conference Table plus 26 Visitors Chairs, 13 No.Office Project Management, and Request for Single Stage - One Desks, 13 No. Office Chairs, IDA / 58210 Post Limited 73,973.00 33,021.06 Completed 2017-10-25 2017-11-21 2017-12-20 2018-02-28 2018-06-18 2018-05-21 Monitoring and Evaluation Quotations Envelope 26 No. Visitors chairs, 2No Sofa Sets, 2No. Coffee set, 1No. Round Table, 1No. Reception/ Front Desk Unit, 1No. Paper trim UG-OPM-29346-GO-RFB / Procurement of Motorvehicles (Lot 1: 1 No Station Wagon Type A (Not exceeding Project Management, and Single Stage - One IDA / 58210 Prior Request for Bids Open - National 1,064,600.00 0.00 Canceled 2017-11-24 2017-11-29 2018-01-10 2018-02-09 2018-03-16 2018-09-12 3000cc), Station Wagon Type Monitoring and Evaluation Envelope B (Not exceeding 2800cc), Lot 2: 15 No Double Cabin Pickups, Lot 3: 17 No Motorcycles) UG-OPM-39369-GO-RFB / Procurement of Assorted Motor vehicles - 6 Double Project Management, and Single Stage - One IDA / 58210 Post Request for Bids Open - National 1,008,705.00 390,961.72 Completed 2018-02-02 2018-03-01 2018-02-07 2018-03-21 2018-03-29 2018-04-20 2018-04-19 2018-05-25 2019-04-30 2018-07-09 2019-06-06 cabins, 1 station wagon and Monitoring and Evaluation Envelope 23 motorcycles for field operations UG-OPM-22084-GO-RFB / Procurement of ICT Hardware/ Equipment (31 Laptops, 3 Desktop Computers, 17 Small Project Management, and Single Stage - One and Medium Duty IDA / 58210 Post Request for Bids Open - National 170,693.00 161,492.06 Completed 2018-02-05 2018-02-12 2018-02-10 2018-07-12 2018-03-24 2018-03-12 2018-04-23 2018-03-23 2018-05-28 2018-06-13 2018-11-24 2019-01-21 Monitoring and Evaluation Envelope Photocopiers, 2 Printers, 15 Scanners, 1 Projector, 17 Internet Modems, 29 computer Tablets) UG-OPM-81114-GO-RFB / Project Management, and Single Stage - One purchase of 8 Double Cabin IDA / 58210 Post Request for Bids Open - National 328,205.10 380,179.59 Completed 2019-01-14 2019-04-11 2019-01-19 2019-03-02 2019-05-15 2019-04-01 2019-05-29 2019-05-06 2019-09-05 2019-11-02 2019-09-30 Monitoring and Evaluation Envelope Pickups UG-OPM-110980-GO-DIR / Project Management, and Single Stage - One Purchase of 23 Motor Cycles IDA / 58210 Post Request for Bids Open - National 84,736.84 96,899.98 Completed 2019-05-06 2019-05-09 2019-05-11 2019-06-22 2019-06-10 2019-07-22 2019-06-27 2019-08-26 2019-10-17 2020-02-22 2019-11-01 Monitoring and Evaluation Envelope for Project Operations UG-OPM-120099-GO-RFQ / Purchase of 13 Multipurpose Project Management, and Request for Single Stage - One IDA / 58210 Post Limited 3,448.00 4,119.41 Completed 2019-07-05 2019-07-08 2019-08-30 2019-09-04 2020-02-26 2019-09-20 Power Stabilizers for District Monitoring and Evaluation Quotations Envelope Photocopier Machines UG-OPM-124188-GO-RFQ / Project Management, and Request for Single Stage - One Purchase of Assorted ICT IDA / 58210 Post Limited 92,308.00 81,046.54 Completed 2019-08-30 2020-01-16 2019-10-25 2020-06-26 2020-04-22 2020-10-20 Monitoring and Evaluation Quotations Envelope Equipment UG-OPM-124418-GO-RFQ / Project Management, and Request for Single Stage - One Purchase of construction IDA / 58210 Post Limited 2,718.00 2,846.34 Completed 2019-08-10 2019-08-16 2019-10-05 2019-10-15 2020-04-02 2019-11-12 Monitoring and Evaluation Quotations Envelope Safety Gear UG-OPM-125409-GO-RFQ / Project Management, and Request for Single Stage - One Purchase of 4 Motorcycles for IDA / 58210 Post Limited 15,384.00 16,777.59 Completed 2019-08-30 2019-11-29 2019-10-25 2020-02-11 2020-04-22 2020-03-05 Monitoring and Evaluation Quotations Envelope District Operations UG-OPM-125414-GO-RFB / Project Management, and Single Stage - One Purchase of 3 Double Cabin IDA / 58210 Post Request for Bids Open - National 163,461.00 159,093.71 Completed 2019-08-30 2020-05-11 2019-09-04 2019-10-16 2020-06-29 2019-11-15 2020-06-29 2019-12-20 2020-11-24 2020-06-17 2021-03-31 Monitoring and Evaluation Envelope Pickups UG-OPM-125415-GO-RFQ / Regional Support for Request for Single Stage - One purchase of Furniture for IDA / 58210 Coordination, Capacity and Post Limited 25,641.00 21,981.41 Completed 2019-09-07 2020-05-21 2019-11-02 2020-07-17 2020-04-30 2020-09-09 Quotations Envelope Districts Operations Knowledge Page 1 UG-OPM-124420-GO-RFQ / Purchase of Material Testing Project Management, and Request for Single Stage - One IDA / 58210 Post Limited 10,102.00 0.00 Canceled 2019-08-24 2019-10-19 2020-04-16 Equipment for Project Monitoring and Evaluation Quotations Envelope Operations UG-OPM-125412-GO-RFB / Project Management, and Single Stage - One Purchase of 4 station wagon IDA / 58210 Post Request for Bids Open - National 272,547.00 0.00 Canceled 2019-08-26 2019-08-31 2019-10-12 2019-11-11 2019-12-16 2020-06-13 Monitoring and Evaluation Envelope Vehicles UG-OPM-22312-GO-DIR / Project Management, and Request for Single Stage - One Assorted office stationery and IDA / 58210 Post Limited 19,178.00 0.00 Canceled 2017-11-05 2017-12-31 2018-06-29 Monitoring and Evaluation Quotations Envelope other office consumables UG-OPM-187073-GO-RFQ / Project Management, and Single Stage - One Purchase of 145 Biometric IDA / 58210 Post Request for Bids Open - National 117,567.00 134,856.46 Completed 2020-08-16 2020-08-06 2020-08-21 2020-10-02 2020-10-22 2020-11-01 2020-11-09 2020-12-06 2021-02-12 2021-06-04 2021-03-26 Monitoring and Evaluation Envelope Tablets FY-20-21 UG-OPM-187075-GO-RFQ / Pending Purchase of an Environmental Project Management, and Request for Single Stage - One IDA / 58210 Post Limited 23,783.00 0.00 Implementati 2020-08-29 2020-10-24 2021-04-22 and Monitoring Drone FY 20- Monitoring and Evaluation Quotations Envelope on 21 UG-OPM-187174-GO-RFB / Under Project Management, and Single Stage - One Purchase of Assorted ICT IDA / 58210 Post Request for Bids Open - National 260,270.00 194,057.87 Implementati 2020-08-23 2020-11-16 2020-08-28 2020-10-09 2021-01-04 2020-11-08 2021-01-19 2020-12-13 2021-06-11 Monitoring and Evaluation Envelope Equipment FY 2020-2021 on UG-OPM-187178-GO-RFQ / Purchase of Material and Project Management, and Request for Single Stage - One IDA / 58210 Post Limited 18,919.00 17,053.12 Signed 2020-09-05 2020-10-20 2020-10-31 2021-01-08 2021-04-29 Safety Testing Equipment - FY Monitoring and Evaluation Quotations Envelope 20-21 UG-OPM-187188-GO-RFQ / Project Management, and Request for Single Stage - One Purchase of Assorted IDA / 58210 Post Limited 27,027.00 25,723.15 Completed 2020-08-29 2020-12-14 2020-10-24 2021-03-12 2021-04-22 2021-03-22 Monitoring and Evaluation Quotations Envelope Furniture FY 2020-2021 UG-OPM-187189-GO-RFQ / Purchase of Standby Project Management, and Request for Single Stage - One IDA / 58210 Post Limited 18,919.00 18,881.22 Completed 2020-09-05 2020-12-14 2020-10-31 2021-03-12 2021-04-29 2021-03-22 Generator for Ruth Towers - Monitoring and Evaluation Quotations Envelope FY 2020-2021 UG-OPM-187274-GO-RFQ / Video Camera, Still photo Pending camera, voice recorder, SD Project Management, and Request for Single Stage - One IDA / 58210 Post Limited 8,108.00 0.00 Implementati 2020-08-29 2020-10-24 2021-04-22 cards, tripod stand, video Monitoring and Evaluation Quotations Envelope on editing desk top and software - FY 2020-2021 UG-OPM-187275-GO-RFQ / camera's, radios flash cards Pending Project Management, and Request for Single Stage - One for center and districts (for 88 IDA / 58210 Post Limited 20,270.00 0.00 Implementati 2020-09-19 2020-11-14 2021-05-13 Monitoring and Evaluation Quotations Envelope watersheds and for on settlements) - FY 2020-2021 UG-OPM-72397-GO-RFQ / Project Management, and Request for Single Stage - One Purchase of 30 Electronic IDA / 58210 Post Limited 13,077.00 0.00 Canceled 2018-08-25 2018-10-20 2019-04-18 Monitoring and Evaluation Quotations Envelope Tablets UG-OPM-125420-GO-DIR / Purchase of Biometric Based Project Management, and Tablets for the Management IDA / 58210 Post Direct Selection Direct 51,282.00 0.00 Canceled 2019-08-26 2019-08-31 2019-10-05 2020-04-02 Monitoring and Evaluation Information System and Data Collection UG-OPM-190124-GO-RFQ / Project Management, and Request for Single Stage - One purchase 3 motorcycles fy IDA / 58210 Post Limited 13,461.00 13,290.95 Signed 2020-09-05 2021-01-19 2020-10-31 2021-04-01 2021-04-29 Monitoring and Evaluation Quotations Envelope 2020-2021 UG-OPM-187191-GO-RFB / Pending Purchase of 7 Double cabin Project Management, and Single Stage - One IDA / 58210 Post Request for Bids Open - National 487,807.00 0.00 Implementati 2020-09-07 2020-09-12 2020-10-24 2020-11-23 2020-12-28 2021-06-26 Pickups and 1 Station Wagon Monitoring and Evaluation Envelope on - FY 2020-2021 UG-OPM-222266-GO-RFQ / Pending Purchase of 7 Laptops, 2 Project Management, and Request for Single Stage - One IDA / 58210 Post Limited 18,736.00 0.00 Implementati 2021-03-13 2021-05-08 2021-11-04 Mobile Printers and Network Monitoring and Evaluation Quotations Envelope on Storage - FY 2020-2021 NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual UG-OPM-22095-NC-DIR / Project Management, and LAN set up/ extension to the IDA / 58210 Prior Direct Selection Direct 10,959.00 11,824.67 Signed 2017-08-21 2018-02-13 2017-08-26 2018-02-23 2017-09-30 2018-05-18 2018-03-29 Monitoring and Evaluation DRDIP Offices UG-OPM-22307-NC-DIR / Procurement of Additional Project Management, and Office Space for DRDIP TST at IDA / 58210 Prior Direct Selection Direct 68,493.00 69,120.00 Completed 2017-08-14 2017-08-19 2017-10-30 2017-09-23 2018-01-23 2018-03-22 2018-02-27 Monitoring and Evaluation Ruth Towers (One years Contract) UG-OPM-22306-NC-RFQ / Project Management, and Request for Single Stage - One Office Branding for the IDA / 58210 Post Limited 548.00 1,316.80 Completed 2017-10-28 2018-10-01 2017-12-23 2019-02-05 2018-06-21 2019-03-11 Monitoring and Evaluation Quotations Envelope Kampala Offices UG-OPM-22287-NC-DIR / Development of a Project Project Management, and IDA / 58210 Prior Direct Selection Direct 300,905.00 287,226.00 Signed 2017-12-08 2017-12-13 2018-02-06 2018-01-17 2018-04-20 2018-07-16 Management Information Monitoring and Evaluation System (MIS) UG-OPM-45668-NC-DIR / Purchase and Installation of Project Management, and IDA / 58210 Prior Direct Selection Direct 9,642.00 8,090.36 Completed 2018-02-05 2018-03-04 2018-02-10 2018-03-09 2018-03-17 2018-05-30 2018-09-13 2018-06-27 Wireless internet for DRDIP Monitoring and Evaluation Offices Page 2 UG-OPM-73171-NC-RFQ / Project Management, and Request for Single Stage - One Development of a Website for IDA / 58210 Post Limited 15,385.00 0.00 Canceled 2018-09-01 2018-10-27 2019-04-25 Monitoring and Evaluation Quotations Envelope DRDIP UG-OPM-73186-NC-RFQ / Project Management, and Request for Single Stage - One Office Branding for Kampala IDA / 58210 Post Limited 1,282.00 3,323.96 Completed 2018-08-31 2019-11-29 2018-10-26 2020-08-03 2019-04-24 2020-08-04 Monitoring and Evaluation Quotations Envelope Offices UG-OPM-91818-NC-RFQ / Project Management, and Request for Single Stage - One Purchase of Printed Materials ( IDA / 58210 Post Limited 12,279.00 12,501.94 Completed 2018-12-29 2019-02-08 2019-02-23 2019-05-20 2019-08-22 2019-08-19 Monitoring and Evaluation Quotations Envelope Assorted ) UG-OPM-91819-NC-RFQ / Project Management, and Request for Single Stage - One Purchase of T- Shirts and IDA / 58210 Post Limited 4,423.00 4,054.73 Completed 2018-12-29 2019-01-29 2019-02-23 2019-02-22 2019-08-22 2019-04-17 Monitoring and Evaluation Quotations Envelope Caps UG-OPM-22104-NC-RFQ / Project Management, and Request for Single Stage - One PABX Upgrade/ extension to IDA / 58210 Post Limited 13,699.00 0.00 Canceled 2017-10-28 2017-12-23 2018-06-21 Monitoring and Evaluation Quotations Envelope the refugees office UG-OPM-126639-NC-RFQ / Pending Project Management, and Request for Single Stage - One Wireless Internet for DRDIP IDA / 58210 Post Limited 9,642.00 0.00 Implementati 2019-08-30 2019-10-25 2020-04-22 Monitoring and Evaluation Quotations Envelope Offices (one Year Contract) on UG-OPM-143186-NC-RFQ / Project Management, and Request for Single Stage - One Video Production services for IDA / 58210 Post Limited 2,261.00 2,332.74 Completed 2019-11-09 2019-11-29 2020-01-04 2020-01-29 2020-07-02 2020-06-12 Monitoring and Evaluation Quotations Envelope DRDIP Commissioning UG-OPM-143324-NC-RFQ / Project Management, and Request for Single Stage - One Purchase of Car Tracking IDA / 58210 Post Limited 2,564.00 3,853.08 Completed 2019-11-09 2019-11-29 2020-01-04 2019-12-17 2020-07-02 2020-01-15 Monitoring and Evaluation Quotations Envelope devices for Project Vehicles UG-OPM-147676-NC-RFQ / Project Management, and Request for Single Stage - One Airing of News Features and IDA / 58210 Post Limited 25,692.00 18,184.47 Signed 2019-12-07 2020-01-16 2020-02-01 2020-03-26 2020-07-30 2020-06-20 Monitoring and Evaluation Quotations Envelope Documentaries UG-OPM-125419-NC-RFQ / Purchase and Installation of a Project Management, and Request for Single Stage - One IDA / 58210 Post Limited 10,256.00 0.00 Canceled 2019-08-31 2019-10-26 2020-04-23 CCTV Camera System at Ruth Monitoring and Evaluation Quotations Envelope Towers UG-OPM-124185-NC-RFQ / Project Management, and Request for Single Stage - One Development of DRDIP/OPM IDA / 58210 Post Limited 15,385.00 0.00 Canceled 2019-08-30 2019-10-25 2020-04-22 Monitoring and Evaluation Quotations Envelope Website UG-OPM-125416-NC-RFQ / Project Management, and Request for Single Stage - One upgrade of the Existing Local IDA / 58210 Post Limited 3,846.00 0.00 Canceled 2019-09-01 2019-10-27 2020-04-24 Monitoring and Evaluation Quotations Envelope Area Network at Ruth Towers UG-OPM-187177-NC-RFQ / Purchase of installation of Project Management, and Request for Single Stage - One IDA / 58210 Post Limited 13,514.00 13,139.79 Completed 2020-08-21 2020-09-29 2020-10-16 2020-11-26 2021-04-14 2020-12-30 CCTV Cameras at Ruth Towers Monitoring and Evaluation Quotations Envelope -FY 20-21 UG-OPM-187273-NC-DIR / Supply, Installation, Configuration and Support of Project Management, and IDA / 58210 Post Direct Selection Direct 12,454.00 14,670.23 Completed 2020-08-17 2020-07-20 2020-08-22 2020-09-29 2020-09-26 2020-11-11 2021-03-25 2020-11-25 SSL Certificate for DRDIP Monitoring and Evaluation Management Information System - FY 2020-2021 UG-OPM-193664-NC-DIR / Purchase of Mobile Internet Project Management, and IDA / 58210 Post Direct Selection Direct 2,562.00 5,573.65 Signed 2020-09-21 2020-08-27 2020-09-26 2020-10-12 2020-10-31 2020-11-24 2021-04-29 2021-01-11 for M&E Tablets and Modems Monitoring and Evaluation - FY 2020-2021 UG-OPM-233696-NC-RFQ / Pending Development and Deployment Project Management, and Request for Single Stage - One IDA / 58210 Post Limited 16,216.00 0.00 Implementati 2021-05-29 2021-07-24 2022-01-20 of DRDIP Website Information Monitoring and Evaluation Quotations Envelope on Portal UG-OPM-233921-NC-DIR / Pending Service Support Contract for Project Management, and IDA / 58210 Post Direct Selection Direct 95,654.00 0.00 Implementati 2021-05-24 2021-05-29 2021-07-03 2021-12-30 DRDIP Management Monitoring and Evaluation on Information System CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual UG-OPM-173625-CS-LCS / Project Management, and Least Cost Under Independent Procurement IDA / 58210 Post Open - National 64,102.00 0.00 2020-07-20 2020-07-14 2020-08-10 2020-09-23 2020-12-10 2020-10-21 2021-01-18 2020-11-20 2021-02-03 2020-12-25 2021-03-03 2021-01-29 2021-07-28 Monitoring and Evaluation Selection Implementation Audit UG-OPM-225769-CS-CQS / Consultancy Services for Consultant Project Management, and Under Assessment of performance of IDA / 58210 Post Qualification Open - National 40,540.00 0.00 2021-03-29 2021-04-01 2021-04-19 2021-06-02 2021-07-02 2021-08-06 2022-02-02 Monitoring and Evaluation Implementation Livelihoods model & Selection interventions FY 20-21 INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Individual UG-OPM-22326-CS-INDV / Project Management, and IDA / 58210 Post Consultant Open 76,010.88 93,857.95 Signed 2017-08-18 2018-01-30 2017-10-06 2018-08-03 2017-10-27 2018-08-17 2017-12-01 2018-12-19 2018-05-30 M & E Officer Monitoring and Evaluation Selection Individual UG-OPM-22332-CS-INDV / Project Management, and Pending IDA / 58210 Post Consultant Open 98,367.12 0.00 2017-08-18 2017-10-06 2017-10-27 2017-12-01 2018-05-30 Project Engineer Monitoring and Evaluation Implementation Selection Page 3 Individual UG-OPM-22344-CS-INDV / Project Management, and Under IDA / 58210 Post Consultant Open 76,010.88 0.00 2017-08-18 2018-01-30 2017-10-06 2017-10-27 2017-12-01 2018-05-30 Livelihood Officer Monitoring and Evaluation Implementation Selection Individual UG-OPM-22345-CS-INDV / Project Management, and IDA / 58210 Post Consultant Open 76,010.88 93,857.95 Signed 2017-08-18 2018-01-30 2017-10-06 2018-08-03 2017-10-27 2018-08-03 2017-12-01 2018-12-21 2018-05-30 Environment Officer Monitoring and Evaluation Selection Individual UG-OPM-22347-CS-INDV / Project Management, and IDA / 58210 Post Consultant Open 76,010.88 93,857.95 Signed 2017-08-18 2018-01-30 2017-10-06 2018-08-03 2017-10-27 2018-08-17 2017-12-01 2018-12-19 2018-05-30 Social Safeguards Officer Monitoring and Evaluation Selection Individual UG-OPM-22349-CS-INDV / Project Management, and IDA / 58210 Post Consultant Open 43,651.20 0.00 Canceled 2017-08-18 2017-10-06 2017-10-27 2017-12-01 2018-05-30 Communication Assistant Monitoring and Evaluation Selection Individual UG-OPM-22352-CS-INDV / Project Management, and Under IDA / 58210 Post Consultant Open 43,651.20 0.00 2017-08-18 2018-01-31 2017-10-06 2017-10-27 2017-12-01 2018-05-30 Administrative Assistant Monitoring and Evaluation Implementation Selection UG-OPM-22355-CS-INDV / Individual Project Management, and Engineering Assistant 1 IDA / 58210 Post Consultant Open 43,651.20 53,958.09 Signed 2017-08-18 2018-01-30 2017-10-06 2018-12-12 2017-10-27 2018-12-12 2017-12-01 2018-12-19 2018-05-30 Monitoring and Evaluation (Kampala Office) Selection UG-OPM-22357-CS-INDV / Individual Project Management, and Engineering Assistant 2 IDA / 58210 Post Consultant Open 43,651.20 53,900.33 Signed 2017-08-18 2018-01-30 2017-10-06 2018-12-12 2017-10-27 2018-12-12 2017-12-01 2018-12-19 2018-05-30 Monitoring and Evaluation (Kampala Office) Selection Individual UG-OPM-22360-CS-INDV / Project Management, and IDA / 58210 Post Consultant Open 43,651.20 0.00 Canceled 2017-08-18 2017-10-06 2017-10-27 2017-12-01 2018-05-30 Social Safeguards Assistant 1 Monitoring and Evaluation Selection Individual UG-OPM-22361-CS-INDV / Project Management, and IDA / 58210 Post Consultant Open 43,651.20 0.00 Canceled 2017-08-18 2017-10-06 2017-10-27 2017-12-01 2018-05-30 Social Safeguards Assistant 2 Monitoring and Evaluation Selection Individual UG-OPM-22362-CS-INDV / Project Management, and IDA / 58210 Post Consultant Open 43,651.20 53,900.33 Signed 2017-08-18 2018-01-30 2017-10-06 2018-08-03 2017-10-27 2018-08-17 2017-12-01 2018-12-19 2018-05-30 Accounts Assistant Monitoring and Evaluation Selection Individual UG-OPM-22363-CS-INDV / Project Management, and IDA / 58210 Post Consultant Open 43,651.20 0.00 Canceled 2017-08-18 2017-10-06 2017-10-27 2017-12-01 2018-05-30 Executive Assistant Monitoring and Evaluation Selection UG-OPM-22367-CS-INDV / Individual Project Management, and District Engineering Assistant IDA / 58210 Post Consultant Open 13,150.56 16,238.40 Signed 2017-08-18 2018-01-30 2017-10-06 2018-08-03 2017-10-27 2018-08-17 2017-12-01 2018-12-19 2018-05-30 Monitoring and Evaluation 1 Selection UG-OPM-22368-CS-INDV / Individual Project Management, and District Engineering Assistant IDA / 58210 Post Consultant Open 13,150.56 16,238.40 Signed 2017-08-18 2018-01-30 2017-10-06 2018-08-03 2017-10-27 2018-08-17 2017-12-01 2018-12-19 2018-05-30 Monitoring and Evaluation 2 Selection UG-OPM-22369-CS-INDV / Individual Project Management, and District Engineering Assistant IDA / 58210 Post Consultant Open 13,150.56 16,238.40 Signed 2017-08-18 2018-01-30 2017-10-06 2018-08-03 2017-10-27 2018-08-17 2017-12-01 2018-12-19 2018-05-30 Monitoring and Evaluation 3 Selection UG-OPM-22372-CS-INDV / Individual Project Management, and District Engineering Assistant IDA / 58210 Post Consultant Open 13,150.56 16,238.40 Signed 2017-08-18 2018-01-30 2017-10-06 2018-08-03 2017-10-27 2018-08-17 2017-12-01 2018-12-19 2018-05-30 Monitoring and Evaluation 4 Selection UG-OPM-22373-CS-INDV / Individual Project Management, and District Engineering Assistant IDA / 58210 Post Consultant Open 13,150.56 16,238.40 Signed 2017-08-18 2018-01-30 2017-10-06 2018-08-03 2017-10-27 2018-08-17 2017-12-01 2018-12-21 2018-05-30 Monitoring and Evaluation 5 Selection UG-OPM-22374-CS-INDV / Individual Project Management, and District Engineering Assistant IDA / 58210 Post Consultant Open 13,150.56 16,238.40 Signed 2017-08-18 2018-01-30 2017-10-06 2019-03-04 2017-10-27 2018-08-17 2017-12-01 2019-03-19 2018-05-30 Monitoring and Evaluation 6 Selection UG-OPM-22377-CS-INDV / Individual Project Management, and District Engineering Assistant IDA / 58210 Post Consultant Open 13,150.56 16,238.40 Signed 2017-08-18 2018-01-30 2017-10-06 2019-04-25 2017-10-27 2019-04-25 2017-12-01 2019-04-25 2018-05-30 Monitoring and Evaluation 7 Selection UG-OPM-22379-CS-INDV / Individual Project Management, and District Engineering Assistant IDA / 58210 Post Consultant Open 13,150.56 16,238.40 Signed 2017-08-18 2018-01-30 2017-10-06 2019-03-04 2017-10-27 2019-03-19 2017-12-01 2019-03-19 2018-05-30 Monitoring and Evaluation 8 Selection UG-OPM-22382-CS-INDV / Individual Project Management, and District Engineering Assistant IDA / 58210 Post Consultant Open 13,150.56 16,238.40 Signed 2017-08-18 2018-01-30 2017-10-06 2019-04-18 2017-10-27 2019-04-11 2017-12-01 2019-04-11 2018-05-30 Monitoring and Evaluation 9 Selection UG-OPM-22384-CS-INDV / Individual Project Management, and District Engineering Assistant IDA / 58210 Post Consultant Open 13,150.56 16,238.40 Signed 2017-08-18 2018-01-30 2017-10-06 2018-12-12 2017-10-27 2018-08-17 2017-12-01 2018-12-19 2018-05-30 Monitoring and Evaluation 10 Selection UG-OPM-22387-CS-INDV / Individual Project Management, and District Engineering Assistant IDA / 58210 Post Consultant Open 13,150.56 16,357.80 Signed 2017-08-18 2018-01-30 2017-10-06 2018-08-17 2017-10-27 2018-08-17 2017-12-01 2018-12-12 2018-05-30 Monitoring and Evaluation 11 Selection Individual UG-OPM-22505-CS-INDV / Project Management, and Pending IDA / 58210 Post Consultant Open 11,835.60 0.00 2017-08-18 2017-10-06 2017-10-27 2017-12-01 2018-05-30 Office Attendant 1 Monitoring and Evaluation Implementation Selection Individual UG-OPM-22509-CS-INDV / Project Management, and Pending IDA / 58210 Post Consultant Open 11,835.60 0.00 2017-08-18 2017-10-06 2017-10-27 2017-12-01 2018-05-30 Office Attendant 2 Monitoring and Evaluation Implementation Selection Individual UG-OPM-22515-CS-INDV / Project Management, and Pending IDA / 58210 Post Consultant Open 9,863.01 0.00 2017-08-18 2017-10-06 2017-10-27 2017-12-01 2018-05-30 Driver 1 Monitoring and Evaluation Implementation Selection Individual UG-OPM-22517-CS-INDV / Project Management, and Pending IDA / 58210 Post Consultant Open 9,863.01 0.00 2017-08-18 2017-10-06 2017-10-27 2017-12-01 2018-05-30 Driver 2 Monitoring and Evaluation Implementation Selection Page 4 Individual UG-OPM-22519-CS-INDV / Project Management, and Pending IDA / 58210 Post Consultant Open 9,863.01 0.00 2017-08-18 2017-10-06 2017-10-27 2017-12-01 2018-05-30 Driver 3 Monitoring and Evaluation Implementation Selection Individual UG-OPM-22524-CS-INDV / Project Management, and Pending IDA / 58210 Post Consultant Open 9,863.01 0.00 2017-08-18 2017-10-06 2017-10-27 2017-12-01 2018-05-30 Driver 4 Monitoring and Evaluation Implementation Selection Individual UG-OPM-22527-CS-INDV / Project Management, and Pending IDA / 58210 Post Consultant Open 9,863.01 0.00 2017-08-18 2017-10-06 2017-10-27 2017-12-01 2018-05-30 Driver 5 Monitoring and Evaluation Implementation Selection UG-OPM-22316-CS-CDS / Project Management, and Under IDA / 58210 Prior Direct Selection Direct 120,723.12 0.00 2017-10-02 2017-10-12 2017-12-16 2018-06-14 Project Manager - DRDIP Monitoring and Evaluation Implementation UG-OPM-30462-CS-CDS / Procurement of Consulting services for Updating of the Environmental and Social Project Management, and Under Management Framework and IDA / 58210 Prior Direct Selection Direct 41,551.00 0.00 2017-10-05 2017-10-17 2017-10-09 2017-10-19 2017-10-27 2017-11-24 Monitoring and Evaluation Implementation Resettlement Policy Framework for the Development Response to Displacement Impact Project. UG-OPM-22353-CS-CDS / Project Management, and IDA / 58210 Prior Direct Selection Direct 43,651.20 0.00 Canceled 2017-08-18 2017-08-28 2017-11-01 2018-04-30 Procurement Assistant Officer Monitoring and Evaluation Individual UG-OPM-22343-CS-CDS / Project Management, and Pending IDA / 58210 Post Consultant Limited 76,010.88 0.00 2017-10-20 2017-10-25 2017-11-15 2017-12-20 2018-06-18 Project Accountant Monitoring and Evaluation Implementation Selection Individual UG-OPM-22350-CS-CDS / Project Management, and IDA / 58210 Post Consultant Limited 43,651.20 0.00 Canceled 2017-10-27 2017-11-01 2017-11-22 2017-12-27 2018-06-25 ICT Assistant Officer Monitoring and Evaluation Selection UG-OPM-52236-CS-INDV / Individual Project Management, and Consulting Services for IDA / 58210 Post Consultant Open 76,010.00 0.00 Canceled 2018-03-05 2019-10-17 2018-04-23 2018-05-14 2018-06-18 2018-12-15 Monitoring and Evaluation Communications Officer Selection UG-OPM-52238-CS-INDV / Individual Project Management, and Consultant services for ICT IDA / 58210 Post Consultant Open 76,010.00 93,857.95 Signed 2018-03-05 2018-01-30 2018-04-23 2018-12-12 2018-05-14 2018-12-12 2018-06-18 2018-12-19 2018-12-15 Monitoring and Evaluation Officer Selection UG-OPM-61708-CS-INDV / Individual Project Management, and Consulting Services for a IDA / 58210 Post Consultant Limited 76,010.00 93,982.80 Signed 2018-05-22 2017-10-02 2018-05-27 2017-11-13 2018-06-17 2017-11-30 2018-07-22 2017-11-30 2019-01-18 Monitoring and Evaluation Procurement Officer Selection UG-OPM-22319-CS-CDS / Project Management, and IDA / 58210 Prior Direct Selection Direct 164,383.56 0.00 Canceled 2017-08-18 2017-08-28 2017-11-01 2018-04-30 Baseline survey Monitoring and Evaluation UG-OPM-22349-CS-INDV-2 Individual / Individual consulting Project Management, and IDA / 58210 Post Consultant Open 43,651.20 0.00 Canceled 2019-08-26 2019-08-16 2019-10-14 2019-11-04 2019-12-09 2020-06-06 services for a communication Monitoring and Evaluation Selection Assistant Individual UG-OPM-143192-CS-INDV / Project Management, and Pending IDA / 58210 Post Consultant Limited 76,010.00 0.00 2019-11-04 2019-11-09 2019-11-30 2020-01-04 2020-07-02 Communications officer Monitoring and Evaluation Implementation Selection Individual UG-OPM-143193-CS-INDV / Project Management, and Pending IDA / 58210 Post Consultant Limited 43,651.20 0.00 2019-11-04 2019-11-09 2019-11-30 2020-01-04 2020-07-02 Communications Assistant Monitoring and Evaluation Implementation Selection UG-OPM-173329-CS-CDS / Project Management, and Environmental and Social IDA / 58210 Post Direct Selection Direct 64,102.00 79,134.94 Completed 2020-06-01 2020-03-03 2020-06-11 2020-05-21 2020-08-15 2020-10-01 2021-02-11 2021-01-21 Monitoring and Evaluation Audit for DRDIP UG-OPM-187276-CS-INDV / Individual Project Management, and Pending Natural Resources Officer - FY IDA / 58210 Post Consultant Limited 74,983.00 0.00 2020-09-21 2020-09-26 2020-10-17 2020-11-21 2021-05-20 Monitoring and Evaluation Implementation 2020-2021 Selection UG-OPM-187277-CS-INDV / Individual Project Management, and Pending GBV and VAC Officer - FY IDA / 58210 Post Consultant Limited 74,983.00 0.00 2020-09-14 2020-09-19 2020-10-10 2020-11-14 2021-05-13 Monitoring and Evaluation Implementation 2020-2021 Selection UG-OPM-187278-CS-INDV / Individual District Engineering Assistant Project Management, and Pending IDA / 58210 Post Consultant Open 13,150.56 0.00 2020-09-21 2020-11-09 2020-11-30 2021-01-04 2021-07-03 - Terego District - FY 2020- Monitoring and Evaluation Implementation Selection 2021 UG-OPM-187279-CS-INDV / Individual District Engineering Assistant Project Management, and Pending IDA / 58210 Post Consultant Open 13,150.56 0.00 2020-09-14 2020-11-02 2020-11-23 2020-12-28 2021-06-26 - Obongi District - FY 2020- Monitoring and Evaluation Implementation Selection 2021 UG-OPM-187280-CS-INDV / Individual District Engineering Assistant Project Management, and Pending IDA / 58210 Post Consultant Open 13,150.56 0.00 2020-09-21 2020-11-09 2020-11-30 2021-01-04 2021-07-03 - Kikuube District - FY 2020- Monitoring and Evaluation Implementation Selection 2021 UG-OPM-187281-CS-INDV / Individual District Engineering Assistant Project Management, and Pending IDA / 58210 Post Consultant Open 13,150.56 0.00 2020-09-28 2020-11-16 2020-12-07 2021-01-11 2021-07-10 - Madi Okollo District - FY Monitoring and Evaluation Implementation Selection 2020-2021 UG-OPM-225948-CS-CDS / Assessment of Natural Project Management, and Resources & Ecosystems to IDA / 58210 Prior Direct Selection Direct 32,432.00 0.00 Canceled 2021-03-29 2021-04-08 2021-06-12 2021-12-09 Monitoring and Evaluation support sustainable livelihoods UG-OPM-225951-CS-CDS / Project Management, and Under Energy value chain and IDA / 58210 Post Direct Selection Direct 27,027.00 0.00 2021-03-29 2021-04-01 2021-04-08 2021-06-12 2021-12-09 Monitoring and Evaluation Implementation market assessments Page 5 UG-OPM-229923-CS-CDS / Assessment of Natural Project Management, and IDA / 58210 Post Direct Selection Direct 31,578.00 0.00 Under Review 2021-04-26 2021-05-10 2021-05-06 2021-07-10 2022-01-06 Resources and ecosystems Monitoring and Evaluation capacity - FY 20-21 Page 6 PROCUREMENT PLAN (Textual Part) Country: Kyrgyz Republic Full Project Name: Enhancing Resilience in the Kyrgyz Republic Project (ERIK) Project Number: P162635 Project Implementation Project Implementation Unit of the Project agency under MoES Date of the Procurement December 26, 2017 Plan: Period covered by this December 26, 2017 - December 26, 2018 Procurement Plan: Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. PROCUREMENT Kyrgyz Republic : Enhancing Resilience in Kyrgyzstan Project PLAN General Information Country: Kyrgyz Republic Bank’s Approval Date of the Original Procurement Plan: 2017-12-27 2021-05-18 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P162635 GPN Date: 2020-11-09 Project Name: Enhancing Resilience in Kyrgyzstan Project Loan / Credit No: IDA / V1060, / , IDA / 62380, IDA / 66870, IDA / D6550 M Executing Agency(ies): inistry of Emergency Situations WORKS Procureme Activity Reference No. / Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH nt Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) Justification for Award Type Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KG-CW/RFB-10 / Improving Safety and Single Stage - One 2023-04- Procurement of civil works for IDA / 62380 Functionality of School Prior Request for Bids Open - International 0.00 Canceled 2021-11-30 2021-12-17 2022-02-15 2022-03-17 2022-04-28 Envelope 28 schools Infrastructure KG-CW/RFB-09 / Improving Safety and Pending Single Stage - One 2022-01- Procurement of civil works for IDA / 62380 Functionality of School Post Request for Bids Open - International 0.00 Implementat 2020-08-25 2020-09-11 2020-11-10 2020-12-10 2021-01-21 Envelope 21 schools Infrastructure ion KG-CW/RFB-01/AF / Improving Safety and Pending Single Stage - One 2023-04- Procurement of civil works for IDA / 66870 Functionality of School Prior Request for Bids Open - International 0.00 Implementat 2021-10-01 2021-10-29 2021-12-13 2022-03-04 2022-04-15 Envelope 15 10 schools Infrastructure ion KG-CW/RFB-02/AF / Improving Safety and Pending Single Stage - One 2024-04- Procurement of civil works for IDA / 66870 Functionality of School Prior Request for Bids Open - International 0.00 Implementat 2022-10-01 2022-10-29 2022-12-13 2023-03-04 2023-04-15 Envelope 14 10 schools Infrastructure ion KG-CW/RFB-03/AF / Improving Safety and Pending Single Stage - One 2025-04- Procurement of civil works for IDA / 66870 Functionality of School Prior Request for Bids Open - International 0.00 Implementat 2023-10-01 2023-10-29 2023-12-13 2024-03-03 2024-04-14 Envelope 14 20 schools Infrastructure ion Pending KG-CW/RFQ-01/AF / Major Project Management and Request for Single Stage - One 2022-01- IDA / 66870 Post Open - National 0.00 Implementat 2021-06-12 2021-11-27 repairs of the PIU office Monitoring & Evaluation Quotations Envelope 26 ion GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KG-G/RFB-02 / Equipment Single Stage - One / Post Request for Bids Open - International 0.00 Canceled 2018-04-25 2018-05-23 2018-07-07 2018-08-04 2018-09-01 2019-02-28 for '112' Call Center Envelope KG-G/RFB-02B / Equipment Contingent Emergency Single Stage - One IDA / V1060 Post Request for Bids Open - International 229,590.14 Completed 2018-05-28 2018-07-20 2018-06-08 2018-07-20 2018-07-20 2018-09-04 2018-08-19 2018-09-13 2018-09-23 2018-10-02 2019-03-22 2019-02-26 for '112' Call Center Response Envelope KG-G/RFQ-02/1 / Software Project Management and (1C accounting system for PIU IDA / V1060 Post Direct Selection Direct 7,900.00 Completed 2018-05-29 2018-06-18 2018-06-01 2018-06-18 2018-06-14 2018-06-19 2018-07-14 2018-07-19 Monitoring & Evaluation under the MOES) KG-G/RFQ-01 / Equipment Project Management and Request for Single Stage - One IDA / V1060 Post Open - National 0.00 Canceled 2018-04-27 2018-05-18 2018-06-07 2018-07-17 for PIU Monitoring & Evaluation Quotations Envelope KG-G/RFQ-02 / Software (1C Project Management and Request for Single Stage - One IDA / V1060 Post Open - National 0.00 Canceled 2018-05-05 2018-06-15 2018-08-14 accounting system for MoES) Monitoring & Evaluation Quotations Envelope KG-G/RFB-01 / Equipment Contingent Emergency Single Stage - One IDA / V1060 Post Request for Bids Open - International 0.00 Canceled 2018-05-15 2018-05-29 2018-07-13 2018-08-10 2018-09-07 2019-03-06 for rescue team Response Envelope KG-G/RFB-01A / Equipment for rescue team: Lot #1- Procurement of Contingent Emergency Single Stage - One IDA / V1060 Post Request for Bids Open - National 98,060.00 Completed 2018-06-22 2018-06-28 2018-06-29 2018-06-29 2018-08-03 2018-07-27 2018-09-02 2018-08-06 2018-10-07 2018-10-01 2018-11-21 2018-10-30 rescue tools Response Envelope Lot #2- Procurement of equipment for rescue service KG-G/RFQ-01B / Furniture Project Management and Request for Single Stage - One IDA / V1060 Post Open - National 3,719.77 Completed 2018-06-29 2018-07-20 2018-08-17 2018-09-06 2018-09-16 2018-10-05 for PIU Monitoring & Evaluation Quotations Envelope KG-G/RFQ-01A / Computer Project Management and Request for Single Stage - One IDA / V1060 Post Open - National 19,146.94 Completed 2018-06-29 2018-06-29 2018-08-10 2018-07-12 2018-09-09 2018-08-24 equipment for PIU Monitoring & Evaluation Quotations Envelope KG-G/RFB-02A / Software for Contingent Emergency IDA / V1060 Post Direct Selection Direct 508,250.80 Completed 2018-07-09 2018-08-06 2018-07-14 2018-08-07 2018-08-30 2018-08-28 2019-01-17 2019-01-14 '112' call center Response KG-G/RFB-01B / Equipment for rescue team: Lot#1 - Contingent Emergency Single Stage - One Rescue equipment, Lot#2 - IDA / V1060 Post Request for Bids Open - National 18,141.96 Completed 2018-08-15 2018-08-17 2018-08-17 2018-08-17 2018-09-14 2018-09-07 2018-10-14 2018-09-20 2018-11-11 2018-10-17 2018-12-26 2018-11-23 Response Envelope Fire equipment, Lot #3 - Diving equipment. KG-G/RFB-01C / Equipment for rescue team: Lot#1 - Contingent Emergency Single Stage - One Rescue equipment, Lot#2 - IDA / V1060 Post Request for Bids Open - National 45,416.74 Completed 2018-10-04 2018-10-05 2018-10-05 2018-10-05 2018-10-26 2018-10-26 2018-11-15 2018-11-13 2018-12-10 2018-12-17 2019-01-24 2019-04-12 Response Envelope Fire equipment Re-advertisement KG-G/RFQ-04 / Procurement Enhancing Financial Request for Single Stage - One of office equipment for IDA / 62380 Post Open - National 0.00 Canceled 2019-04-11 2019-05-23 2019-07-22 Protection Quotations Envelope regional offices SIO KG-G/RFQ-05 / Procurement Enhancing Financial Request for Single Stage - One of furniture for regional IDA / 62380 Post Open - National 0.00 Canceled 2019-04-11 2019-05-30 2019-07-29 Protection Quotations Envelope offices SIO Page 1 KG-G/RFQ-07 / Procurement Enhancing Financial Request for Single Stage - One IDA / 62380 Post Open - National 0.00 Canceled 2019-07-14 2019-09-13 2019-12-12 of mobile devices for SIO Protection Quotations Envelope KG-G/RFB-05 / Establishing Strengthening Disaster Single Stage - One the Platform to Exchange the IDA / 62380 Preparedness and Response Post Request for Bids Open - International 0.00 Canceled 2019-03-28 2019-04-04 2019-05-19 2019-06-16 2019-07-14 2020-07-13 Envelope Data Systems KG-G/RFQ-10 / Procurement Strengthening Disaster of Software for development Request for Single Stage - One IDA / 62380 Preparedness and Response Post Open - International 55,000.00 Completed 2019-04-05 2019-04-05 2019-05-20 2019-07-09 2019-09-17 2019-09-04 of the Unified Duty- Quotations Envelope Systems Dispatching Service 112 KG-G/RFB-03 / Development of the Country-Wide Strengthening Disaster Single Stage - One Integrated Public Notification IDA / 62380 Preparedness and Response Prior Request for Bids Open - International 1,241,130.00 Signed 2019-04-04 2019-06-26 2019-04-19 2019-08-21 2019-06-03 2019-08-22 2019-07-01 2019-10-30 2019-08-12 2019-11-14 2020-02-08 Envelope and Warning System - OKSION Systems System KG-G/RFB-04 / Development of Routine Management Body - Crisis Management Center: Strengthening Disaster Lot #1 purchase of controller Single Stage - One IDA / 62380 Preparedness and Response Post Request for Bids Open - International 103,167.69 Completed 2019-03-25 2019-04-05 2019-03-29 2019-04-05 2019-05-13 2019-05-20 2019-06-10 2019-06-19 2019-07-08 2019-07-10 2019-12-15 2019-12-10 for video wall. Lot# 2 Envelope Systems purchase of satellite equipment. Lot #3 purchase of radio station equipment. KG-G/RFB-09 / Disaster Strengthening Disaster Under Learning Platform for Single Stage - One IDA / 62380 Preparedness and Response Post Request for Bids Open - International 0.00 Implementati 2020-06-22 2021-05-28 2020-06-26 2021-05-28 2020-08-07 2020-09-04 2020-10-16 2021-02-13 Professional Training Center Envelope Systems on MES KG-G/RFB-10 / Procurement Enhancing Financial Request for Single Stage - One of furniture for regional IDA / 62380 Post Open - National 47,782.91 Completed 2019-04-18 2019-05-13 2019-06-17 2019-07-19 2019-08-16 2019-10-22 Protection Quotations Envelope offices SIO KG-G/RFB-12 / Procurement Enhancing Financial Request for Single Stage - One of office equipment for IDA / 62380 Post Open - National 67,943.35 Completed 2019-04-18 2019-05-13 2019-06-17 2019-07-19 2019-08-16 2019-09-17 Protection Quotations Envelope regional offices SIO KG-G/RFQ-11 / Computer Project Management and IDA / V1060 Post Direct Selection Direct 3,924.70 Completed 2019-05-07 2019-05-17 2019-05-12 2019-05-21 2019-06-16 2019-05-22 2019-07-31 2019-06-05 equipment for PIU Monitoring & Evaluation KG-G/RFQ-12 / Additional Project Management and IDA / V1060 Post Direct Selection Direct 909.09 Completed 2019-05-07 2019-05-17 2019-05-12 2019-05-21 2019-05-24 2019-05-22 2019-06-23 2019-05-29 furniture for PIU Monitoring & Evaluation KG-G/RFQ-09 / Procurement of office equipment for Contingent Emergency Request for Single Stage - One IDA / 62380 Post Open - National 0.00 Canceled 2019-03-22 2019-05-08 2019-06-24 Unified Duty- Dispatching Response Quotations Envelope Service 112 KG-G/RFQ-09A / Strengthening Disaster Request for Single Stage - One Procurement of computer IDA / 62380 Preparedness and Response Post Open - National 0.00 Canceled 2019-06-14 2019-07-11 2019-07-24 2019-09-12 Quotations Envelope equipment for 112 system Systems KG-G/RFB-11 / Procurement Enhancing Financial Single Stage - One IDA / 62380 Post Request for Bids Open - International 163,420.25 Completed 2019-06-24 2019-07-22 2019-06-28 2019-07-22 2019-08-09 2019-09-02 2019-08-23 2019-10-01 2019-09-20 2019-10-18 2019-11-19 2020-02-28 of server equipment for SIO Protection Envelope KG-G/RFB-08 / Strengthening the capacity of the newly created 15 cluster interdistrict points (points) of Strengthening Disaster Single Stage - One monitoring of hazardous IDA / 62380 Preparedness and Response Post Request for Bids Open - International 0.00 Canceled 2019-06-17 2019-06-21 2019-08-02 2019-08-16 2019-09-13 2019-12-12 Envelope natural processes within the Systems framework of the creation of mobile monitoring points of the ESCMP Strengthening Disaster KG-G/RFQ-13 / Procurement Request for Single Stage - One IDA / V1060 Preparedness and Response Post Open - National 0.00 Canceled 2019-06-16 2019-08-23 2019-07-31 2019-09-29 of compressed air apparatus Quotations Envelope Systems KG-G/RFB-13 / Procurement of hardware for Web portal and newly created 15 cluster interdistrict points (points) of Strengthening Disaster Single Stage - One monitoring of hazardous IDA / 62380 Preparedness and Response Post Request for Bids Open - International 0.00 Canceled 2019-08-07 2019-08-16 2019-08-09 2019-08-16 2019-09-20 2019-11-12 2019-10-21 2019-12-04 2019-11-25 2020-02-24 Envelope natural processes within the Systems framework of the creation of mobile monitoring points of the ESCMP. KG-G/RFB-14 / Production of Pending Enhancing Financial Single Stage - One Branded and Promotional IDA / 62380 Post Request for Bids Open - National 0.00 Implementati 2019-08-12 2019-08-15 2019-09-26 2019-10-26 2019-11-26 2020-02-24 Protection Envelope Products for SIO on KG-G/RFB-04A / Development of Routine Strengthening Disaster Single Stage - One Management Body - Crisis IDA / 62380 Preparedness and Response Post Request for Bids Open - International 0.00 Canceled 2019-08-02 2019-08-13 2019-08-05 2019-08-13 2019-09-19 2019-09-25 2019-10-17 2019-12-05 2019-11-14 2020-02-12 Envelope Management Center: Purchase Systems of satellite equipment KG-G/RFB-15 / Procurement Enhancing Financial Single Stage - One IDA / 62380 Post Request for Bids Open - International 0.00 Terminated 2019-08-07 2019-08-16 2019-08-09 2019-08-16 2019-09-23 2019-09-27 2019-10-23 2019-11-18 2019-11-25 2019-12-25 2020-01-24 of mobile devices for SIO Protection Envelope KG-G/RFB-06A / Goods for operational survey of landslides: Lot #1 - Strengthening Disaster Equipment and car. Lot # 2 - Single Stage - One IDA / 62380 Preparedness and Response Post Request for Bids Open - International 0.00 Canceled 2019-06-03 2019-06-07 2019-06-06 2019-06-06 2019-07-18 2019-07-19 2019-08-01 2019-08-12 2019-08-29 2019-12-17 Mobile meteorological station Envelope Systems and measuring equipment. Lot #3 - UAV and land surveying equipment KG-G/RFB-06C / Strengthening Disaster Single Stage - One Procurement of Off-road IDA / 62380 Preparedness and Response Post Request for Bids Open - National 0.00 Canceled 2019-09-27 2019-09-16 2019-09-30 2019-09-17 2019-11-11 2019-12-26 2020-01-23 2020-05-22 Envelope Vehicle Systems KG-G/RFB-06D / Strengthening Disaster Single Stage - One Procurement of UAV and land IDA / 62380 Preparedness and Response Post Request for Bids Open - National 47,819.01 Completed 2019-10-03 2019-09-16 2019-10-07 2019-09-17 2019-11-18 2019-10-08 2020-01-02 2019-10-31 2020-01-30 2019-11-12 2020-05-29 2020-03-18 Envelope survey equipment Systems Page 2 KG-G/RFB-06Е / Strengthening Disaster Single Stage - One Procurement of Measuring IDA / 62380 Preparedness and Response Post Request for Bids Open - National 0.00 Canceled 2019-09-27 2019-09-16 2019-09-30 2019-09-17 2019-11-11 2019-10-09 2019-12-26 2020-01-23 2020-05-22 Envelope Equipment Systems KG-G/RFB-06F / Strengthening Disaster Single Stage - One Procurement of Mobile IDA / 62380 Preparedness and Response Post Request for Bids Open - International 0.00 Canceled 2019-09-27 2019-10-17 2019-09-30 2019-10-18 2019-11-14 2019-12-03 2019-12-30 2019-12-19 2020-02-03 2020-06-02 Envelope Weather Station and Forecast Systems Equipment KG-G/RFQ-13A / Strengthening Disaster Request for Single Stage - One Procurement of compressed IDA / V1060 Preparedness and Response Post Open - National 19,574.61 Completed 2019-10-02 2019-09-24 2019-12-30 2019-12-06 2020-02-28 2020-02-06 Quotations Envelope air apparatus Systems KG-G/DC-01 / Procurement of Software for newly created 15 cluster interdistrict points Strengthening Disaster (points) of monitoring of IDA / 62380 Preparedness and Response Post Direct Selection Direct 176,305.00 Completed 2019-09-30 2019-09-20 2019-10-11 2019-09-26 2019-11-08 2019-10-18 2020-03-07 2019-12-03 hazardous natural processes Systems within the framework of the creation of mobile monitoring points of the ESCMP KG-G/RFQ-09A-2 / Strengthening Disaster Procurement of office Request for Single Stage - One IDA / 62380 Preparedness and Response Post Open - National 9,694.14 Completed 2019-10-05 2019-09-27 2019-11-19 2019-11-14 2020-01-08 2019-12-26 equipment for Unified Duty- Quotations Envelope Systems Dispatching Service 112 KG-G/RFB-06C-2 / Strengthening Disaster Single Stage - One Procurement of Special IDA / 62380 Preparedness and Response Post Request for Bids Open - International 55,798.40 Completed 2020-02-06 2020-01-24 2020-02-12 2020-01-23 2020-04-02 2020-03-16 2020-05-12 2020-05-18 2020-06-16 2020-06-05 2020-10-14 2020-10-01 Envelope Vehicles Systems KG-G/RFB-13-2 / Procurement of hardware for newly created 15 cluster interdistrict points (points) of Strengthening Disaster Single Stage - One monitoring of hazardous IDA / 62380 Preparedness and Response Post Request for Bids Open - National 0.00 Canceled 2020-02-13 2020-03-11 2020-02-18 2020-03-11 2020-03-16 2020-04-01 2020-04-30 2020-06-04 2020-09-02 Envelope natural processes within the Systems framework of the creation of mobile monitoring points of the ESCMP KG-G/RFB-04A-2 / Development of Routine Strengthening Disaster Single Stage - One Management Body - Crisis IDA / 62380 Preparedness and Response Post Request for Bids Open - International 0.00 Canceled 2020-02-18 2020-02-07 2020-02-21 2020-02-07 2020-04-06 2020-05-11 2020-06-08 2020-10-06 Envelope Management Center: Purchase Systems of satellite equipment KG-G/RFB-06Е-2 / Strengthening Disaster Single Stage - One Procurement of measuring IDA / 62380 Preparedness and Response Post Request for Bids Open - International 0.00 Canceled 2020-03-10 2020-03-13 2020-03-13 2020-03-13 2020-04-30 2020-06-30 2020-06-19 2020-07-17 2020-11-14 Envelope equipment Systems KG-G/RFB-06F-2 / Strengthening Disaster Procurement of a mobile Single Stage - One IDA / 62380 Preparedness and Response Post Request for Bids Open - International 57,208.80 Completed 2020-03-23 2020-06-04 2020-03-25 2020-06-05 2020-05-14 2020-07-27 2020-07-03 2020-08-27 2020-07-31 2020-09-14 2020-11-28 2021-01-12 weather station and forecast Envelope Systems equipment KG/ERIK-CERC/G/RFQ/2020- 01 / Personal Protective Equipment for RRTs, 24 Contingent Emergency Request for Single Stage - One IDA / 62380 Post Open - International 0.00 Canceled 2020-04-07 2020-04-06 2020-04-19 2020-05-19 designated quarantine Response Quotations Envelope hospitals, PHC, ICUs and designated hospitals KG/ERIK-CERC/G/RFQ/2020- 02 / Disinfectants for RRTs, Contingent Emergency Request for Single Stage - One 24 designated quarantine IDA / 62380 Post Open - International 0.00 Canceled 2020-04-07 2020-04-06 2020-04-19 2020-05-19 Response Quotations Envelope hospitals, PHC, ICUs and designated hospitals KG/ERIK-CERC/G/RFQ/2020- 03 / Laboratory reagents needed for diagnosis for Contingent Emergency Request for Single Stage - One IDA / 62380 Post Open - International 71,415.39 Signed 2020-04-07 2020-04-06 2020-05-19 2020-04-29 2020-11-15 2020-05-22 RRTs, 24 designated Response Quotations Envelope quarantine hospitals, PHC, ICUs and designated hospitals KG/ERIK-CERC/G/RFQ/2020- 04 / Lifesaving essential drugs for diagnosis for RRTs, Contingent Emergency Request for Single Stage - One IDA / 62380 Post Open - International 749,828.10 Completed 2020-04-07 2020-04-06 2020-05-19 2020-04-23 2020-11-15 2020-07-06 24 designated quarantine Response Quotations Envelope hospitals, PHC, ICUs and designated hospitals KG/ERIK-CERC/G/RFQ/2020- 05 / Medical devices for diagnosis for RRTs, 24 Contingent Emergency Request for Single Stage - One IDA / 62380 Post Open - International 2,510.00 Completed 2020-04-07 2020-04-06 2020-04-19 2020-04-23 2020-05-19 2020-06-29 designated quarantine Response Quotations Envelope hospitals, PHC, ICUs and designated hospitals KG/ERIK-CERC/G/RFQ/2020- 09 / Procurement of 13 fully Contingent Emergency Request for Single Stage - One equipped ambulances - IDA / 62380 Post Open - International 764,900.00 Completed 2020-04-07 2020-04-06 2020-04-19 2020-04-22 2020-06-18 2020-09-01 Response Quotations Envelope Advanced Life Support (ALS) vehicles KG/ERIK-CERC/G/RFQ/2020- 06 / Medical equipment for diagnosis for RRTs, 24 Contingent Emergency Request for Single Stage - One IDA / 62380 Post Open - International 571,333.53 Completed 2020-04-07 2020-04-06 2020-04-19 2020-04-28 2020-06-18 2020-10-14 designated quarantine Response Quotations Envelope hospitals, PHC, ICUs and designated hospitals KG/ERIK-CERC/G/RFQ/2020- 08 / Other products (paper Contingent Emergency Request for Single Stage - One IDA / 62380 Post Open - International 0.00 Canceled 2020-04-07 2020-04-06 2020-04-19 2020-05-19 towels, shipping containers, Response Quotations Envelope etc.) KG/ERIK-CERC/G/RFQ/2020- Contingent Emergency Request for Single Stage - One 07 / Respiratory Support IDA / 62380 Post Open - International 1,431,298.56 Completed 2020-04-07 2020-04-06 2020-04-19 2020-05-07 2020-06-18 2020-10-21 Response Quotations Envelope Equipment Page 3 KG/ERIK-CERC/G/RFQ/2020- 01B / PPEs for RRTs, 24 Contingent Emergency Request for Single Stage - One designated quarantine IDA / 62380 Post Open - International 330,763.38 Completed 2020-04-17 2020-04-17 2020-04-29 2020-05-08 2020-05-29 2020-08-03 Response Quotations Envelope hospitals, PHC, ICUs and designated hospitals - 2 lots KG/ERIK-CERC/G/RFQ/2020- 02B / Disinfectants for RRTs, Contingent Emergency Request for Single Stage - One 24 designated quarantine IDA / 62380 Post Open - International 33,803.70 Completed 2020-04-17 2020-04-17 2020-04-29 2020-04-30 2020-05-29 2020-05-18 Response Quotations Envelope hospitals, PHC, ICUs and designated hospitals KG/ERIK-CERC/G/RFQ/2020- 08B / Other products (paper Contingent Emergency Request for Single Stage - One IDA / 62380 Post Open - International 6,157.70 Signed 2020-04-17 2020-04-17 2020-04-29 2020-05-08 2020-05-29 2020-07-19 towels, liquid soap, shipping Response Quotations Envelope containers, etc.) G/ERIK-CERC/G/RFQ/2020- 05B / Medical devices for diagnosis for RRTs, 24 designated quarantine Contingent Emergency Request for Single Stage - One IDA / 62380 Post Open - International 21,614.87 Completed 2020-04-20 2020-04-20 2020-05-02 2020-05-04 2020-06-01 2020-06-01 hospitals, PHC, ICUs and Response Quotations Envelope designated hospitals - Lot No 2 - Consumables for medicament injection KG/ERIK-CERC/G/RFQ/2020- 04B / Procurement of lifesaving essential drugs for Contingent Emergency Request for Single Stage - One diagnosis for RRTs, 24 IDA / 62380 Post Open - International 152,657.78 Completed 2020-04-23 2020-04-23 2020-05-05 2020-05-04 2020-06-04 2020-06-04 Response Quotations Envelope designated quarantine hospitals, PHC, ICUs and designated hospitals KG/ERIK-CERC/G/RFQ/2020- 03B / Laboratory reagents needed for diagnosis for Contingent Emergency Request for Single Stage - One RRTs, 24 designated IDA / 62380 Post Open - International 0.00 Canceled 2020-05-11 2020-05-11 2020-06-24 2020-07-24 Response Quotations Envelope quarantine hospitals, PHC, ICUs and designated hospitals -Lot No 1 KG-G/DC-02 / Procurement Enhancing Financial of database of residential IDA / 62380 Post Direct Selection Direct 0.00 Canceled 2020-05-10 2020-05-27 2020-05-15 2020-05-28 2020-05-25 2020-07-24 Protection properties for SIO KG/ERIK-CERC/G/RFQ/2020- 06B / Medical equipment for diagnosis for RRTs, 24 Contingent Emergency Request for IDA / 62380 Post 63,213.67 Completed 2020-05-18 2020-05-19 2020-06-09 2020-08-11 2020-08-08 2020-12-17 designated quarantine Response Quotations hospitals, PHC, ICUs and designated hospitals. KG/ERIK-CERC/G/RFQ/2020- 10 / Procurement of Contingent Emergency Request for Single Stage - One equipment for disinfection IDA / 62380 Post Open - International 196,854.00 Completed 2020-05-26 2020-05-28 2020-06-22 2020-07-07 2020-08-21 2020-11-13 Response Quotations Envelope and reduction of medical waste KG-G/RFB-13-2B / Procurement of hardware for newly created 15 cluster interdistrict points (points) of Strengthening Disaster Single Stage - One monitoring of hazardous IDA / 62380 Preparedness and Response Post Request for Bids Open - National 0.00 Canceled 2020-06-22 2020-06-22 2020-06-25 2020-06-22 2020-07-25 2020-07-15 2020-08-29 2020-08-28 2020-09-08 2020-12-07 Envelope natural processes within the Systems framework of the creation of mobile monitoring points of the ESCMP KG/ERIK- CERC/G/UNA/2020/1 / Contingent Emergency UN Agencies Procurement of Personel IDA / 62380 Post Direct 460,978.76 Completed 2020-07-01 2020-06-25 2020-07-03 2020-06-24 2020-07-10 2020-06-25 2020-08-29 2020-10-26 Response (Direct) Protective Equipment and medical drugs KG/ERIK-CERC/G/DC/2020- 02 / Procurement of lifesaving Contingent Emergency IDA / 62380 Post Direct Selection Direct 70,575.11 Completed 2020-07-01 2020-06-30 2020-07-01 2020-07-01 2020-07-04 2020-07-04 2020-07-29 2020-08-21 essential drugs for RRTs of Response health care organizations KG/ERIK-CERC/G/DC/2020- 03 / Procurement of lifesaving Contingent Emergency IDA / 62380 Post Direct Selection Direct 843,411.22 Completed 2020-07-01 2020-06-30 2020-07-01 2020-07-01 2020-07-04 2020-07-04 2020-07-29 2020-07-18 essential drugs for RRTs of Response health care organizations KG/ERIK-CERC/G/DC/2020- 04 / Procurement of lifesaving Contingent Emergency IDA / 62380 Post Direct Selection 52,596.49 Completed 2020-07-01 2020-06-30 2020-07-01 2020-07-01 2020-07-04 2020-07-04 2020-07-06 2020-07-21 essential drugs for RRTs of Response health care organizations KG/ERIK-CERC/G/DC/2020- 05 / Procurement of lifesaving Contingent Emergency IDA / 62380 Post Direct Selection Direct 9,465.82 Completed 2020-07-01 2020-06-30 2020-07-01 2020-07-04 2020-07-04 2020-07-04 2020-07-29 2020-07-07 essential drugs for RRTs of Response health care organizations KG/ERIK-CERC/G/RFQ/2020- 03B-2 / Purchase of Contingent Emergency Request for Single Stage - One IDA / 62380 Post Open - International 181,860.95 Completed 2020-07-13 2020-07-08 2020-08-08 2020-08-11 2020-09-07 2020-09-21 consumables for polymerase Response Quotations Envelope chain reaction (PCR) analysis KG/ERIK-CERC/G/RFQ/2020- 10-2 / Procurement of Contingent Emergency Request for Single Stage - One IDA / 62380 Post Open - International 632,322.65 Completed 2020-07-15 2020-07-09 2020-08-15 2020-08-21 2020-11-13 2020-12-14 Microwave equipment for Response Quotations Envelope disinfection of medical waste KG/ERIK-CERC/G/DC/2020- 01 / Procurement of lifesaving Contingent Emergency essential drugs for diagnosis IDA / 62380 Post Direct Selection Direct 4,056.78 Completed 2020-07-08 2020-06-30 2020-07-08 2020-07-01 2020-07-09 2020-07-09 2020-08-03 2020-07-15 Response for RRTs of health care organization KG-G/RFQ-14 / Procurement Enhancing Financial Request for Single Stage - One of mobile devices for OJSC IDA / 62380 Post Open - International 90,477.34 Completed 2020-08-20 2020-08-27 2020-10-14 2020-10-21 2020-12-13 2021-01-15 Protection Quotations Envelope State Insurance Organization Page 4 KG/ERIK-CERC- COVID19/G/RFB/2020-01 / Contingent Emergency Single Stage - One IDA / 62380 Prior Request for Bids Open - International 0.00 Canceled 2020-08-21 2020-08-23 2020-08-28 2020-08-25 2020-09-14 2020-09-09 2020-10-29 2020-11-24 2021-03-24 Procurement of computer Response Envelope tomographs KG-G/DC-02-2 / Procurement of database of Enhancing Financial residential properties for IDA / 62380 Post Direct Selection Direct 28,740.25 Signed 2020-09-10 2020-09-04 2020-09-15 2020-09-04 2020-10-13 2020-09-16 2020-12-12 Protection OJSC "State Insurance Organization" Strengthening Disaster KG-G/DC-03 / Procurement IDA / 62380 Preparedness and Response Post Direct Selection Direct 37,734.28 Completed 2020-09-10 2020-09-08 2020-09-24 2020-09-08 2020-10-29 2020-10-21 2021-01-27 2021-03-16 of measuring equipment Systems KG-G/RFQ-06/AF / Project Management and Request for Single Stage - One Procurement of Office IDA / 66870 Post Open - National 3,314.50 Completed 2020-12-15 2020-11-27 2021-04-01 2021-01-12 2021-06-10 2021-02-03 Monitoring & Evaluation Quotations Envelope Furniture for PIU KG-G/RFQ-07/AF / Office Project Management and Request for Single Stage - One IDA / 66870 Post Open - National 0.00 Canceled 2020-12-01 2020-11-27 2021-03-18 2021-05-27 Equipment for PIU Monitoring & Evaluation Quotations Envelope KG-G/RFB-06/AF / Project Management and Single Stage - One IDA / 66870 Post Request for Bids Open - National 0.00 Canceled 2020-11-26 2020-12-01 2021-01-15 2021-02-14 2021-03-28 2021-07-26 Procurement cars for PIU Monitoring & Evaluation Envelope KG-G/RFB-02/AF / Strengthening Disaster Pending Procurement of necessary fire Single Stage - One IDA / 66870 Preparedness and Response Post Request for Bids Open - International 0.00 Implementati 2022-07-15 2022-08-12 2022-09-26 2022-11-25 2023-01-27 2023-04-27 extinguishing means and Envelope Systems on other equipment KG-G/RFB-04/AF / Improving Safety and Pending Single Stage - One Procurement of Furniture for IDA / 66870 Functionality of School Post Request for Bids Open - International 0.00 Implementati 2023-03-01 2023-03-29 2023-05-13 2023-08-02 2023-09-13 2024-04-10 Envelope 10 schools Infrastructure on KG-G/RFB-05/AF / Improving Safety and Pending Single Stage - One Procurement of Furniture for IDA / 66870 Functionality of School Prior Request for Bids Open - International 0.00 Implementati 2024-03-01 2024-03-29 2024-05-13 2024-08-02 2024-09-13 2025-04-11 Envelope 20 schools Infrastructure on KG-G/RFB-03/AF / Improving Safety and Pending Single Stage - One Improving IT infrastructure of IDA / 66870 Functionality of School Post Request for Bids Open - International 0.00 Implementati 2021-09-01 2021-09-29 2021-11-13 2022-02-02 2022-03-16 2022-09-12 Envelope the MOeS Infrastructure on KG-G/RFB-13-2C / Procurement of hardware for newly created 15 cluster interdistrict points (points) of Strengthening Disaster Single Stage - One monitoring of hazardous IDA / 62380 Preparedness and Response Post Request for Bids Open - National 65,562.40 Signed 2020-10-22 2020-11-25 2020-10-27 2020-11-25 2020-11-17 2020-12-15 2020-12-27 2020-12-22 2021-01-06 2021-01-21 2021-04-06 Envelope natural processes within the Systems framework of the creation of mobile monitoring points of the ESCMP KG-G/RFB-01/AF / Procurement of vehicles Lot Strengthening Disaster Single Stage - One No 1 - Firefighting vehicle; IDA / 66870 Preparedness and Response Prior Request for Bids Open - International 0.00 Canceled 2021-07-15 2021-08-12 2021-09-26 2021-12-16 2022-01-27 2023-01-27 Envelope Lot No 2- Feet maintaining Systems vehicles KG-G/RFB-13A / Strengthening Disaster Single Stage - One Procurement of hardware for IDA / 62380 Preparedness and Response Post Request for Bids Open - International 176,861.06 Signed 2020-11-20 2020-12-03 2020-11-25 2020-12-03 2021-01-11 2021-01-20 2021-02-25 2021-03-23 2021-03-25 2021-04-16 2021-07-23 Envelope Web portal of the USCEMF Systems KG-G/RFQ-07/AF-2 / Project Management and Request for Single Stage - One Procurement of office IDA / 66870 Post Open - National 11,839.09 Completed 2020-12-25 2021-06-07 2021-02-16 2021-08-16 2021-03-27 Monitoring & Evaluation Quotations Envelope equipment for PIU KG-G/RFB-06/AF-2 / Project Management and Single Stage - Two IDA / 66870 Post Request for Bids Open - National 0.00 Canceled 2020-10-15 2020-12-11 2020-10-20 2020-12-10 2020-11-24 2021-01-05 2021-02-08 2021-02-25 2021-06-25 Procurement of cars for PIU Monitoring & Evaluation Envelope KG-G/RFB-06/AF-4 / Pending Project Management and Single Stage - One Procurement of vehicles for IDA / 66870 Post Request for Bids Open - National 0.00 Implementati 2021-10-01 2021-10-01 2021-11-15 2021-12-15 2022-01-05 2022-04-05 Monitoring & Evaluation Envelope PIU on KG-G/RFB-06/AF-3 / Project Management and Single Stage - One IDA / 66870 Post Request for Bids Open - National 29,413.01 Completed 2021-01-25 2021-01-22 2021-01-30 2021-01-22 2021-02-17 2021-02-09 2021-03-03 2021-03-11 2021-03-20 2021-03-17 2021-06-18 2021-04-04 Procurement of vehicle for PIU Monitoring & Evaluation Envelope Strengthening Disaster Under KG-G/RFB-01/AF-2 / Single Stage - Two IDA / 66870 Preparedness and Response Prior Request for Bids Open - International 0.00 Implementati 2021-02-19 2021-04-09 2021-03-19 2021-04-14 2021-05-10 2021-08-20 2021-09-17 2022-09-17 Procurement of vehicles Envelope Systems on KG-G/RFB-16/ERIK / Development of Routine Strengthening Disaster Under Single Stage - One Management Body (CMC): IDA / 62380 Preparedness and Response Post Request for Bids Open - National 0.00 Implementati 2021-03-23 2021-03-30 2021-03-26 2021-03-30 2021-04-16 2021-04-19 2021-05-31 2021-05-07 2021-06-17 2021-10-15 Envelope Procurement of radio Systems on equipment KG-G/RFB-17/ERIK / Strengthening Disaster Under Procurement of land surveying Single Stage - One IDA / 62380 Preparedness and Response Post Request for Bids Open - National 0.00 Implementati 2021-05-28 2021-05-20 2021-05-31 2021-05-20 2021-06-21 2021-08-05 2021-08-22 2021-12-20 equipment for USCEMF Envelope Systems on (software and UAV) KG-G/RFB-18/ERIK / Strengthening Disaster Under Single Stage - One Procurement of land surveying IDA / 62380 Preparedness and Response Post Request for Bids Open - National 0.00 Implementati 2021-05-03 2021-05-20 2021-05-06 2021-05-20 2021-05-27 2021-07-11 2021-07-28 2021-11-25 Envelope equipment for USCEMF (GNSS) Systems on KG-G/RFB-19/ERIK / Strengthening Disaster Under Single Stage - One Procurement of measuring IDA / 62380 Preparedness and Response Post Request for Bids Open - National 0.00 Implementati 2021-06-01 2021-05-20 2021-06-04 2021-05-20 2021-06-25 2021-08-09 2021-08-26 2021-12-24 Envelope equipment for USCEMF Systems on KG-G/RFB-20/ERIK / Capacity building of the Emergency Monitoring and Strengthening Disaster Pending Single Stage - One Forecasting Center: IDA / 62380 Preparedness and Response Post Request for Bids Open - National 0.00 Implementati 2021-06-01 2021-06-04 2021-06-25 2021-08-09 2021-08-26 2021-12-24 Envelope Procurement of office Systems on equipment and engineering infrastructure (furniture) Page 5 KG-G/RFQ-15/ERIK / Procurement of hardware for Strengthening Disaster Pending Request for Single Stage - One newly created 15 cluster IDA / 62380 Preparedness and Response Post Open - National 0.00 Implementati 2021-05-20 2021-07-16 2021-08-30 Quotations Envelope interdistrict points of ES Systems on monitoring KG-G/RFB-21/ERIK / Strengthening Disaster Under Procurement of special vehicle Single Stage - One IDA / 62380 Preparedness and Response Post Request for Bids Open - National 0.00 Implementati 2021-05-18 2021-05-20 2021-05-21 2021-05-20 2021-06-11 2021-07-26 2021-08-12 2022-01-09 (operational research Envelope Systems on laboratory of MoES) KG/ERIK-CERC- Under COVID19/G/RFB/2021-02 / Contingent Emergency Single Stage - Two IDA / 62380 Prior Request for Bids Open - International 0.00 Implementati 2021-06-01 2021-06-22 2021-06-22 2021-06-24 2021-08-06 2021-10-19 2021-11-16 2022-03-16 Procurement of computed Response Envelope on tomography Strengthening Disaster Pending KG-G/RFB-07 / Scaling-up of Single Stage - One IDA / 62380 Preparedness and Response Post Request for Bids Open - International 0.00 Implementati 2021-01-25 2021-02-01 2021-03-18 2021-04-15 2021-05-13 2021-11-09 the operational monitoring Envelope Systems on KG-G/RFB-22/ERIK / Strengthening Disaster Pending Procurement of Single Stage - One IDA / 62380 Preparedness and Response Post Request for Bids Open - International 0.00 Implementati 2021-06-15 2021-06-18 2021-08-02 2021-10-01 2021-11-05 2022-02-03 communication devices for Envelope Systems on development of UIMS Under KG-G/RFB-06/AF-1 / Project Management and Request for Single Stage - One IDA / D6550 Post Open - National 0.00 Implementati 2021-06-12 2021-06-02 2021-08-07 2022-02-03 Procurement for car for PIU Monitoring & Evaluation Quotations Envelope on NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KG-G/RFB-06B / Strengthening Disaster Single Stage - One Procurement of Digital terrain IDA / 62380 Preparedness and Response Post Request for Bids Open - International 0.00 Canceled 2019-04-05 2019-04-12 2019-05-24 2019-06-21 2019-08-02 2019-12-20 Envelope model (DTM) and Systems orthophotographs CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KG-CS/QCBS-02 / Business process review for Enhancing Financial Quality And Cost- IDA / V1060 Prior Open - International 1,333,333.33 Signed 2018-03-15 2018-03-25 2018-04-14 2018-05-11 2018-05-12 2018-06-25 2018-06-09 2018-07-25 2018-06-29 2018-09-12 2018-08-03 2018-11-26 2018-09-18 2018-12-26 2020-09-17 catastrophe insurance and Protection Based Selection supporting IT customization services KG-CS/LCS-01 / Financial Least Cost audit (annual) of project for / Post Open - International 0.00 Canceled 2018-02-25 2018-03-03 2018-03-27 2018-04-24 2018-05-22 2018-06-11 2018-07-09 2018-07-23 2019-12-31 Selection 2018-2020 KG-CS/QCBS-01 / Preparation of Feasibility Studies and Designs for Quality And Cost- Improved Seismic Safety and / Prior Open - International 0.00 Canceled 2018-04-25 2018-05-25 2018-06-22 2018-07-20 2018-08-09 2018-09-13 2018-10-29 2020-10-28 Based Selection Energy Efficiency of Schools and Technical Supervision of construction. KG-CS/QCBS-01/2 / Preparation of Feasibility Studies and Designs for Improving Safety and Quality And Cost- Improved Seismic Safety and IDA / V1060 Functionality of School Post Open - International 0.00 Canceled 2020-03-02 2020-03-23 2020-04-27 2020-06-08 2020-06-28 2020-08-02 2020-09-11 2021-04-09 Based Selection Energy Efficiency of Schools Infrastructure and Technical Supervision of construction. KG-CS/LCS-01/A / Financial Project Management and Least Cost IDA / 62380 Post Open - International 76,832.00 Signed 2019-01-18 2019-02-05 2019-02-03 2019-02-08 2019-02-24 2019-03-06 2019-03-24 2019-04-03 2019-04-07 2019-04-10 2019-04-22 2019-04-19 2019-05-13 2019-05-17 2024-01-31 audit of project (annual) Monitoring & Evaluation Selection KG-CS/QCBS-01/1 / Preparation of Feasibility Improving Safety and Studies and Designs for Quality And Cost- IDA / V1060 Functionality of School Prior Open - International 596,999.33 Signed 2019-06-28 2020-01-16 2019-07-12 2020-02-03 2019-08-12 2020-08-11 2019-09-11 2020-09-28 2019-10-09 2021-01-15 2019-11-13 2021-04-23 2019-12-18 2021-05-24 2020-12-17 Improved Seismic Safety and Based Selection Infrastructure Energy Efficiency of Schools and Author supervision KG-CS/QCBS-01/3 / Preparation of Feasibility Improving Safety and Studies and Designs for Quality And Cost- IDA / V1060 Functionality of School Prior Open - International 0.00 Canceled 2020-07-28 2020-08-27 2020-09-27 2020-10-27 2020-11-24 2020-12-29 2021-02-02 2022-10-25 Improved Seismic Safety and Based Selection Infrastructure Energy Efficiency of Schools and Author supervision Improving Safety and Consultant KG-CS/CQS-02 / Supervision IDA / V1060 Functionality of School Post Qualification Open - National 0.00 Canceled 2021-04-01 2021-04-15 2021-05-13 2021-05-27 2021-07-03 2022-06-28 and monitoring Infrastructure Selection Improving Safety and KG-CS/QCBS-05 / Quality And Cost- Pending IDA / V1060 Functionality of School Prior Open - International 0.00 2021-02-02 2021-02-23 2021-04-08 2021-05-06 2021-06-05 2021-07-10 2021-08-14 2022-12-27 Supervision and monitoring Based Selection Implementation Infrastructure KG-CS/CQS-03 / Strengthening Disaster Consultant Establishing a Platform to IDA / 62380 Preparedness and Response Post Qualification Open - International 131,370.00 Signed 2019-08-05 2019-08-27 2019-08-26 2019-09-06 2019-10-09 2019-12-02 2019-10-16 2020-02-25 2019-11-13 2020-03-17 2020-02-11 Exchange the Data Systems Selection KG-CS/QCBS-03 / Enhancing Financial Quality And Cost- Pending Optimisation of SIO core IDA / 62380 Prior Open - International 0.00 2020-10-01 2020-10-15 2020-12-10 2021-01-07 2021-02-06 2021-03-03 2021-04-18 2022-04-18 Protection Based Selection Implementation business processes KG-CS/CQS-04 / Risk Consultant Enhancing Financial Pending management and regulatory IDA / 62380 Post Qualification Open - International 0.00 2020-10-15 2020-10-29 2020-12-14 2021-01-25 2021-03-01 2021-03-13 Protection Implementation compliance Selection Page 6 KG-CS/QCBS-01/AF / Preparation of Feasibility Studies and Designs for Improving Safety and Quality And Cost- Pending Improved Seismic Safety and IDA / 66870 Functionality of School Prior Open - International 0.00 2020-12-25 2021-01-01 2021-02-27 2021-04-13 2021-05-04 2021-06-15 2021-08-10 2022-08-10 Based Selection Implementation Energy Efficiency of Schools Infrastructure and Author supervision for 10 schools KG-CS/QCBS-03/AF / Preparation of Feasibility Studies and Designs for Improving Safety and Quality And Cost- Pending Improved Seismic Safety and IDA / 66870 Functionality of School Prior Open - International 0.00 2021-12-25 2022-01-01 2022-03-01 2022-04-15 2022-05-06 2022-06-17 2022-08-12 2023-08-12 Based Selection Implementation Energy Efficiency of Schools Infrastructure and Author supervision for 20 schools KG-CS/LCS-01/AF / Financial Project Management and Least Cost Pending IDA / 66870 Post Open - International 0.00 2021-04-16 2021-05-01 2021-06-28 2021-07-26 2021-08-15 2021-09-05 2021-10-09 2025-09-28 audit (annual) - 2021-2027 Monitoring & Evaluation Selection Implementation KG-CS/QCBS-02/AF / Improving Safety and Quality And Cost- Pending Technical supervision for 10 IDA / 66870 Functionality of School Prior Open - International 0.00 2022-08-18 2022-09-15 2022-10-28 2022-12-12 2023-01-02 2023-02-13 2023-04-10 2024-04-09 Based Selection Implementation schools Infrastructure KG-CS/QCBS-04/AF / Improving Safety and Quality And Cost- Pending Technical supervision for 20 IDA / 66870 Functionality of School Prior Open - International 0.00 2023-09-01 2023-09-15 2023-10-26 2023-12-10 2023-12-31 2024-02-04 2024-04-07 2025-04-07 Based Selection Implementation schools Infrastructure KG-CS/CQS-01/AF / Strengthening Disaster Consultant Pending Development of Fire Service IDA / 66870 Preparedness and Response Post Qualification Open - International 0.00 2021-11-01 2021-11-22 2022-01-05 2022-01-21 2022-02-25 2022-08-24 Implementation Program Systems Selection KG-CS/CQS-02/AF / Improving Safety and Consultant Development of special Pending IDA / 66870 Functionality of School Post Qualification Open - National 0.00 2021-01-01 2021-01-22 2021-02-21 2021-03-14 2021-04-27 2021-10-24 technical conditions for 30 Implementation Infrastructure Selection schools KG-CS/CQS-03/AF / Improving Safety and Consultant Pending Development of IDA / 66870 Functionality of School Post Qualification Open - National 0.00 2021-01-01 2021-01-22 2021-03-07 2021-04-06 2021-04-27 2025-08-31 Implementation communication strategy Infrastructure Selection KG-CS/CQS-05 / Expansion of the activities of the web Strengthening Disaster Consultant portal of the USCEMF: Pending IDA / 62380 Preparedness and Response Post Qualification Open - International 0.00 2021-06-17 2021-07-01 2021-07-29 2021-08-26 2021-09-09 2021-12-08 Development of software to Implementation Systems Selection expand the activities of the USCEMF web portal INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Contract Type Process Status Teams of Reference Identified/Selected Signed Contract Contract Completion No. (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KG-IOC/IC-07 / Local Individual Project Management and Coordinator for the IDA / V1060 Post Consultant Open 12,731.86 Completed 2018-02-15 2018-02-15 2018-03-29 2018-04-02 2018-03-30 2018-04-02 2018-04-17 2018-04-16 2020-04-06 2019-04-30 Monitoring & Evaluation Component 1 Selection KG-IOC/IC-08 / Local Individual Project Management and Coordinator for the IDA / V1060 Post Consultant Open 11,086.74 Completed 2018-02-15 2018-02-19 2018-03-29 2018-04-25 2018-03-30 2018-04-28 2018-04-17 2018-05-14 2020-04-06 2019-04-30 Monitoring & Evaluation Component 2 Selection KG-IOC/IC-09 / Local Individual Project Management and Coordinator for the IDA / V1060 Post Consultant Open 13,404.13 Completed 2018-02-15 2018-02-15 2018-03-29 2018-04-04 2018-03-30 2018-04-06 2018-04-17 2018-04-23 2020-04-06 2019-04-30 Monitoring & Evaluation Component 3 Selection Individual KG-IOC/IC-03 / Local Project Management and IDA / V1060 Prior Consultant Direct 20,923.36 Completed 2018-02-15 2018-03-02 2018-03-08 2018-03-19 2018-03-22 2018-04-04 2018-03-29 2018-04-01 2019-11-19 2019-04-30 Financial Manager Monitoring & Evaluation Selection Individual KG-IOC/IC-04 / Local Project Management and IDA / V1060 Post Consultant Open 11,986.87 Completed 2018-02-15 2018-02-19 2018-03-20 2018-04-03 2018-03-22 2018-04-03 2018-04-08 2018-04-18 2019-04-03 2019-04-30 Disbursment Specialist Monitoring & Evaluation Selection KG-IOC/IC-05 / Local Individual Project Management and assistant of Procurement IDA / V1060 Post Consultant Open 4,791.60 Terminated 2018-02-15 2018-02-19 2018-03-29 2018-04-03 2018-03-30 2018-04-05 2018-04-19 2018-04-16 2019-04-14 Monitoring & Evaluation Specialist Selection Individual KG-IOC/IC-06 / Local Project Management and IDA / V1060 Post Consultant Open 8,286.74 Terminated 2018-02-15 2018-02-19 2018-03-29 2018-04-02 2018-03-30 2018-04-02 2018-04-19 2018-04-16 2019-04-14 Translator-office-manager Monitoring & Evaluation Selection Individual KG-CS/IC-02 / Selection of Project Management and / Post Consultant Limited 3,235.30 Terminated 2017-12-29 2018-01-09 2017-12-30 2018-01-17 2018-01-05 2018-01-23 2018-01-17 2018-02-28 Local Social Consultant Monitoring & Evaluation Selection KG-CS/IC-01 / Selection of Individual Local Environmental / Post Consultant Limited 3,970.59 Completed 2017-12-29 2018-01-30 2017-12-31 2018-01-17 2018-01-05 2018-01-22 2018-01-17 2018-02-04 2018-02-28 2018-04-06 Consultant Selection Individual KG-IOC/IC-02 / Local Senior Project Management and IDA / V1060 Prior Consultant Direct 13,575.10 Terminated 2018-02-22 2018-03-02 2018-02-22 2018-03-19 2018-02-22 2018-04-04 2018-04-01 2018-04-01 2019-11-22 Procurement Specialist Monitoring & Evaluation Selection Individual KG-MES-54500-CS-INDV / Project Management and IDA / V1060 Prior Consultant Limited 14,390.21 Completed 2018-03-19 2018-03-22 2018-03-19 2018-04-06 2018-04-02 2018-04-24 2018-04-26 2018-05-16 2019-04-21 2019-04-30 Local Director PIU Monitoring & Evaluation Selection Individual KG-IOC/IC-01 / Local / Prior Consultant Open 0.00 Canceled 2018-02-15 2018-02-19 2018-03-29 2018-04-12 2018-05-17 2020-05-06 Director PIU Selection KG-CS/IC-03 / Selection of Local Consultant for Individual preparation of bidding / Post Consultant Open 0.00 Canceled 2018-04-15 2018-05-27 2018-06-10 2018-06-24 2019-06-19 documents for goods for Selection MoES Page 7 KG-CS/IC-03-2 / Local IT Consultant for preparation of Individual Project Management and bidding documents for IDA / V1060 Post Consultant Limited 0.00 Canceled 2018-05-10 2018-05-15 2018-06-05 2018-07-03 2019-07-03 Monitoring & Evaluation Component #1 and Selection Component #3 KG-CS/IC-03/1 / Local Individual Consultant for Business Project Management and IDA / V1060 Post Consultant Open 12,778.57 Completed 2018-06-21 2018-06-21 2018-07-30 2018-08-06 2018-08-02 2018-08-06 2018-08-21 2018-08-22 2019-08-21 2019-08-21 Processes and Information Monitoring & Evaluation Selection Technologies Improving Safety and Individual KG-CS/IC-04 / International IDA / V1060 Functionality of School Post Consultant Open 0.00 Canceled 2018-10-26 2018-12-05 2018-12-21 2019-01-09 2020-12-29 Сivil engineer Infrastructure Selection Improving Safety and Individual KG-CS/IC-04/A / Local civil IDA / 62380 Functionality of School Post Consultant Open 26,288.61 Terminated 2019-02-17 2019-03-01 2019-03-14 2019-04-10 2019-03-21 2019-04-24 2019-04-11 2019-04-25 2020-04-10 engineer Infrastructure Selection Improving Safety and Individual KG-CS/IC-05 / Local Social & IDA / 62380 Functionality of School Post Consultant Open 0.00 Canceled 2019-02-27 2019-02-25 2019-04-04 2019-04-10 2019-04-11 2019-05-02 2020-05-01 Environment Consultant Infrastructure Selection Strengthening Disaster Individual KG-CS/IC-07 / Local IT IDA / V1060 Preparedness and Response Post Consultant Open 5,213.26 Terminated 2019-03-25 2019-04-10 2019-04-19 2019-06-04 2019-04-22 2019-05-31 2019-05-10 2019-06-19 2020-05-09 Consultant for MES KR Systems Selection KG-CS/IC-09 / Local Improving Safety and Individual Translator Consultant for IDA / 62380 Functionality of School Post Consultant Open 0.00 Canceled 2019-03-25 2019-04-02 2019-04-11 2019-06-28 2019-04-12 2019-04-29 2020-04-28 Component #2 Infrastructure Selection KG-CS/IC-10 / Local Individual Enhancing Financial Translator Consultant for IDA / 62380 Post Consultant Open 0.00 Canceled 2019-03-25 2019-04-02 2019-04-11 2019-07-02 2019-04-12 2019-04-29 2020-04-28 Protection Component #3 Selection Improving Safety and Individual KG-CS/IC-05-2 / Local IDA / 62380 Functionality of School Post Consultant Limited 18,631.04 Terminated 2019-05-03 2019-05-15 2019-05-10 2019-05-21 2019-05-24 2019-05-31 2019-06-14 2019-07-04 2020-06-13 Social&Enviroment Consultant Infrastructure Selection KG-CS/IC-08 / Local Strengthening Disaster Individual Translator Consultant for IDA / 62380 Preparedness and Response Post Consultant Open 0.00 Canceled 2019-03-25 2019-04-02 2019-04-11 2019-07-17 2019-04-12 2019-04-29 2020-04-28 Component #1 Systems Selection KG-CS/IC-03/2 / Local Individual Consultant for Business Enhancing Financial IDA / 62380 Post Consultant Direct 12,808.23 Completed 2019-08-21 2019-09-06 2019-08-21 2019-08-20 2019-08-21 2019-08-20 2019-08-22 2019-08-20 2020-08-31 2020-08-31 Processes and Information Protection Selection Technologies KG/CS/SSS-01/SDC / Improving Safety and Development of special IDA / 62380 Functionality of School Post Direct Selection Direct 48,252.84 Signed 2020-07-01 2020-06-24 2020-07-15 2020-07-23 2020-09-09 2020-09-25 2020-11-08 design criteria Infrastructure Strengthening Disaster Individual KG-CS/IC-07/B / Local IT IDA / 62380 Preparedness and Response Post Consultant Open 10,085.87 Signed 2020-05-22 2020-06-12 2020-06-20 2020-08-24 2020-07-04 2020-08-24 2020-07-07 2020-09-09 2021-07-07 Consultant for MES Systems Selection KG-CS/IC-03/3 / Local Individual Consultant for Business Enhancing Financial IDA / 62380 Post Consultant Direct 25,809.03 Signed 2020-08-28 2020-08-24 2020-08-31 2020-08-25 2020-08-31 2020-08-25 2020-09-01 2020-09-01 2021-03-31 Processes and Information Protection Selection Technologies KG-CS/IC-01/AF / Improving Safety and Individual Communications Strategy IDA / 66870 Functionality of School Post Consultant Open 10,522.20 Signed 2020-10-26 2020-10-13 2020-12-02 2021-01-11 2020-12-09 2021-01-11 2020-12-30 2021-01-25 2025-08-31 Specialist Infrastructure Selection Strengthening Disaster Individual KG-CS/IC-02/AF / Fire Safety IDA / 66870 Preparedness and Response Post Consultant Open 0.00 Canceled 2020-10-27 2020-12-10 2020-12-17 2020-12-31 2021-12-31 Specialist Systems Selection KG-CS/IC-11 / Local Improving Safety and Individual Сonsultant Engineer on IDA / 62380 Functionality of School Post Consultant Open 8,992.22 Signed 2021-02-03 2021-02-03 2021-03-17 2021-03-12 2021-03-24 2021-03-12 2021-03-27 2021-04-01 2021-07-25 energy efficiency Infrastructure Selection KG-CS/IC-12 / Local Improving Safety and Individual Сonsultant Engineer on IDA / 62380 Functionality of School Post Consultant Open 8,992.22 Signed 2021-02-03 2021-02-03 2021-03-17 2021-03-12 2021-03-24 2021-03-12 2021-03-27 2021-04-01 2021-07-25 energy efficiency Infrastructure Selection KG-CS/IC-13 / Local Improving Safety and Individual Consultant on water supply IDA / 62380 Functionality of School Post Consultant Open 0.00 Canceled 2021-02-03 2021-02-03 2021-03-17 2021-03-12 2021-03-24 2021-03-27 2021-07-25 and sanitation Infrastructure Selection KG-CS/IC-13-2 / Local Improving Safety and Individual Consultant on water supply IDA / 62380 Functionality of School Post Consultant Limited 8,994.63 Signed 2021-03-30 2021-03-30 2021-04-13 2021-04-05 2021-04-27 2021-04-15 2021-05-11 2021-04-30 2021-09-08 and sanitation Infrastructure Selection Improving Safety and Individual KG-CS/IC-03/AF / IT Under IDA / 66870 Functionality of School Post Consultant Open 0.00 2021-04-01 2021-03-30 2021-05-06 2021-05-13 2021-05-27 2023-05-27 Consultant for Component 2 Implementation Infrastructure Selection Page 8 SUMMARY O F PROCUREMENT PLAN Project Preparation Advancement (PPA) Project information: Harmonizing and Improving Statistics in West Africa Project -P169265 Project Implementation agency: Liberia Institute of Statistics and Geo- Information Services (LISGIS) Date of the Procurement Plan: February 3, 2020 Period covered by this Procurement Plan: 3rd February to 31st July 2020 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 1, 2016), revised in November 2017, and August 2018 (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Public Procurement and Concessions Act, 2010 of the Republic of Liberia, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. In accordance with paragraph 5.3 of the Procurement Regulations, the request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. The form of the Letter of Acceptance is attached in Appendix 1. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables. Not Applicable. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: Not Applicable for those contracts identified in the Procurement Plan tables; Works: Not Applicable for those contracts identified in the Procurement Plan tables. Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations: Not Applicable. Other Relevant Procurement Information: - (a). Prior Procurement Arrangements: The Procurement Arrangements as indicated in the below table and within the thresholds indicated in the below tables will be used. The thresholds for the Bank’s prior review requirements are also provided in the table below: Table: Thresholds*, Procurement Arrangements, and Prior Review (The table below depicts the Thresholds and Procurement Methods to be used under the Regional Project for Statistics Thresholds*, Procurement Methods, and Prior Review Contract (C) Value Expenditure Procurement Contracts Subject to No Threshold* [eq. Category Method Prior Review /[eq. US$] USD] All contracts at or above USD Open Competition 5,000,000 are subject to International Market 1 Works C ≥ 5,000,000 Approach and Direct international advertising and the use of the Bank’s SPDs (or other Contracting documents agreed with the Contract (C) Value Expenditure Procurement Contracts Subject to No Threshold* [eq. Category Method Prior Review /[eq. US$] USD] Bank). Open Competition National Market 200,000 < C < 5,000,000 None Approach C ≤ 200,000 RfQ None All contracts at or above USD Open Competition 500,000 are subject to International Market international advertising and the C ≥ 500,000 Approach and Direct use of the Bank’s SPDs (or other Goods, IT and Contracting documents agreed with the 2 non-consulting Bank). services Open Competition 100,000 < C < 500,000 National Market None Approach C ≤ 100,000 RfQ None All contracts at or above USD 100,000 are subject to for international advertising and the C < 100,000 Consulting Services use of the Bank’s SPDs (or other National documents agreed with the shortlist for Bank). 3 selection of All contracts at or above USD consultant firms for 200,000 are subject to Engineering and international advertising and the C ≤ 200,000 Construction use of the Bank’s SPDs (or other Supervision documents agreed with the Bank). Selection of All values ≥ 100,000 4 Individual All Approaches consultants Training, This line activity is not subject to Workshops, Based on approved Procurement Review However, 5 Study Tours All Values Annual Work Plan & each of the activities will be Budgets (AWPB) by TTL cleared with the TTL prior to its implementation. (Special procurement arrangements like direct contracting, use of SOEs, UN Agencies, third party monitors, local NGOs, Force Account, servants needs, results based arrangements. It is not expected that there will be need for prequalification in the procurement arrangements under this Regional Project *These thresholds are for the purposes of the initial procurement plan for the PPA and for first 18 months. The thresholds will be revised periodically based on re- assessment of risks. All contracts not subject to prior review will be post-reviewed. Prequalification. Not expected for the packages of works/goods packages in the procurement plan. Proposed Procedures for CDD Components: Not Applicable Reference to (if any) Project Operational/Procurement Manual: The LISGIS Project Management Team will prepare Procurement manuals. The Procurement Plan will also form part of the Project Implementation Manual. Any Other Special Procurement Arrangements: None Procurement Packages/PLAN with Procurement Arrangements and Time Schedule: as per the Table below: b) PROCUREMENT PLAN Works There are no works under the Project Preparation Advance Goods and Non-Consulting Services 1 2 3 4 5 6 7 8 9 Ref. Contract Estimated Procurement Prequ Nation Revie Expecte Expecte Comment No. (Description) Cost Method alifica al w d bid d s US$ tion Prefer by opening Contrac (yes/n ence Bank date t o) (yes/n (Prior Signatu o) / Post) re Date 1 Procurement of 4 12,100 laptops, 3 No. all- in-1 printers, Limited, RFQ No No Post 28 Feb 4 Mar office desks, a 20 20 projector, metal filing cabinet, and stationery and supplies for project management Consultancy Services 1 2 3 4 5 6 7 8 9 Ref. Description of Estimate Selection Review Expecte Expected Expected Comments No. Assignment d Method/ by Bank d date Contract Completi Cost in Arrangem (Prior / of Signatur on US$ ent Post) proposal e Date submissi Date on 1. Recruitment of a Consultant to draft and validate 10,000 INDV Post 16 Mar 10 Apr 23 Apr ToR to be curricula of the 20 20 20 submitted to IDA Statistics degree & for Review and No CEST Program at Objection. the UL 2. Recruitment of a ToR, performance Financial evaluation, draft Management contract and Officer for Project DS Prior 10 Feb 21 Feb 31 Aug minutes of Management 20 20 20 contract negotiation to be submitted to IDA for Review and No 15,600 Objection. 3. ToR, performance evaluation, draft Recruitment of a contract and Procurement DS Prior 10 Feb 21 Feb 31 Aug minutes of Specialist for 20 20 20 contract Project 18,000 negotiation to be Management submitted to IDA for Review and No Objection. Training and Workshop (Training & Workshop activities are subject to TTL clearance). Estimat Estimated Expected Ref. Training, workshop and ed Cost Duration Training/workshop No. study tours in (Days) Date (US$) Conduct of validation 54,000 workshop and TOT for the GP Feb. 20 to March 1. on the design of 13 2020 questionnaires and enumeration training manual Workshop for cartographic 150,000 Feb. 24 to March 2. field staff training 16 2020 Workshop for enumeration 113,900 3. mapping training April 15, 2020 Study Tours to regional 32,000 countries for first-hand experience on regional March to April 4. harmonization of data 2020 collection, management and communication Workshops on current 50,000 administrative data across 5. April to July 2020 MACs and LISGIS regional offices Workshop to strengthen and 35,000 6. develop institutional capacity April to July 2020 of NSO Workshops for steering 40,000 7. committee on Administrative April to July 2020 Data Workshop for Project 10,000 Steering/Technical 8. Committees for annual work February 2020 plan preparation, review and validation GENERAL NOTES 1. Training and capacity building: Training workshops (including training material and support), conference attendance and study tours, will be carried out based on approved annual training and allied activities plan by the TTL. The beneficiaries, after the training, will be requested to submit a brief report indicating what skills have been acquired and how these skills will contribute to enhance their performance and contribute to the attainment of the Project’s development objective. 2. Operational Costs: These are expenditures incurred by the Recipient to finance: (i) communication technology (including, without limitation, internet and telephone; (ii) per diem and travel expenses of the operational staff performing their responsibilities under the Project; (iii) fuel and vehicle maintenance; (iv) maintenance of equipment; (v) photocopies and publications; (viii) bank commissions; and (ix) utilities and office supplies as defined in the FA. Appendix 1 Letter of Acceptance of the World Bank’s Anti-Corruption Guidelines and Sanctions Framework Date: Invitation of Bids/Proposals No.__________ To: ___________________________________________________________________________ We, along with our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not) consultants and personnel, acknowledge and agree to abide by the World Bank’s policy regarding Fraud and Corruption (corrupt, fraudulent, collusive, coercive, and obstructive practices), as set out and defined in the World Bank’s Anti-Corruption Guidelines1 in connection with the procurement and execution of the contract (in case of award), including any amendments thereto. We declare and warrant that we, along our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not), consultants and personnel, , are not subject to, and are not controlled by any entity or individual that is subject to, a temporary suspension, early temporary suspension, or debarment imposed by a member of the World Bank Group, including, inter alia, a cross-debarment imposed by the World Bank Group as agreed with other international financial institutions (including multilateral development banks), or through the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement. Further, we are not ineligible under the laws or official regulations of [Insert name of Employer as per bidding document] or pursuant to a decision of the United Nations Security Council. We confirm our understanding of the consequences of not complying with the World Bank’s Anti-Corruption Guidelines, which may include the following: a. rejection of our Proposal/Bid for award of contract; 1Guidelines on Preventing and Combating Fraud and Corruption in Projects Financed by International Bank for Reconstruction and Development Loans and the International Development Agency Credits and Grants, dated October 15, 2006, and revised in January 2011 and July 2016, as they may be revised from time to time. b. in the case of award, termination of the contract, without prejudice to any other remedy for breach of contract; and c. sanctions, pursuant to the Bank’s Anti-corruption Guidelines and in accordance with its prevailing sanctions policies and procedures as set forth in the Bank’s Sanctions Framework. This may include a public declaration of ineligibility, either indefinitely or for a stated period of time, (i) to be awarded or otherwise benefit from a Bank-financed contract, financially or in any other manner;2 (ii) to be a nominated3 sub-contractor, consultant, manufacturer or supplier, or service provider of an otherwise eligible firm being awarded a Bank-financed contract; and (iii) to receive the proceeds of any loan made by the Bank or otherwise to participate further in the preparation or implementation of any Bank-financed project. We understand that we may be declared ineligible as set out above upon: a. completion of World Bank Group sanctions proceedings according to its prevailing sanctions procedures; b. cross-debarment as agreed with other international financial institutions (including multilateral development banks); c. the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement; or d. temporary suspension or early temporary suspension in connection with an ongoing World Bank Group sanctions proceeding. For avoidance of doubt, the foregoing effects of ineligibility do not extend to a sanctioned firm’s or individual’s execution of its ongoing Bank-financed contracts (or its ongoing sub-agreements under such contracts) that are not the subject of a material modification, as determined by the Bank. We shall permit, and shall cause our sub-contractors, sub-consultants, agents (whether declared or not), personnel, consultants, service providers or suppliers, to 2 For the avoidance of doubt, a sanctioned party’s ineligibility to be awarded a contract shall include, without limitation, (i) applying for pre-qualification, expressing interest in a consultancy, and bidding, either directly or as a nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider, in respect of such contract, and (ii) entering into an addendum or amendment introducing a material modification to any existing contract. 3 A nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider (different names are used depending on the particular bidding document) is one which has been: (i) included by the bidder in its pre-qualification application or bid because it brings specific and critical experience and know-how that allow the bidder to meet the qualification requirements for the particular bid; or (ii) appointed by the Borrower. permit the Bank to inspect4 all accounts, records, and other documents relating to the procurement process and/or contract execution (in the case of award), and to have them audited by auditors appointed by the Bank. We agree to preserve all accounts, records, and other documents (whether in hard copy or electronic format) related to the procurement and execution of the contract. Name of the Bidder/Consultant: Name of the person duly authorized to sign the Bid/Proposal on behalf of the Bidder/Consultant: Title of the person signing the Letter: 4 Inspections in this context are usually investigative (i.e., forensic) in nature: they involve fact-finding activities undertaken by the Bank or persons appointed by the Bank to address specific matters related to investigations/audits, such as evaluating the veracity of an allegation of possible Fraud and Corruption, through the appropriate mechanisms. Such activity includes but is not limited to accessing and examining a firm's or individual's financial records and information, and making copies thereof as relevant; accessing and examining any other documents, data, and information (whether in hard copy or electronic format) deemed relevant for the investigation/audit, and making copies thereof as relevant; interviewing staff and other relevant individuals; performing physical inspections and site visits; and obtaining third-party verification of information. PROCUREMENT Western Africa : Harmonizing and Improving Statistics in West Africa PLAN General Information Country: Western Africa Bank’s Approval Date of the Original Procurement Plan: 2020-03-30 2021-05-18 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P169265 GPN Date: 2021-05-19 Project Name: Harmonizing and Improving Statistics in West Africa Loan / Credit No: IDA / 65730, IDA / D5840 M Executing Agency(ies): inistry of Finance and Economic Development WORKS Procureme Activity Reference No. / Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH nt Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) Justification for Award Type Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SL-MOFED-163632-CW-RFB Country-Specific Component: / Rehabilitation of Statistics Improving and modernizing Single Stage - One 2021-01- IDA / 65730 Post Request for Bids Open - National 0.00 Canceled 2020-03-26 2020-03-31 2020-05-12 2020-06-11 2020-07-16 Sierra Leone Physical physical and statistical Envelope 12 Infrastructure infrastructure GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Regional component: Harmonization, Data SL-MOFED-168263-GO-RFQ Collection, Quality Request for / Procurement of station IDA / D5840 Post 0.00 Canceled 2020-04-27 2020-04-27 2020-04-27 Improvement, Dissemination Quotations wagon and Use of Core Social and Economic Statistics Regional component: SL-MOFED-168262-GO-RFQ Harmonization, Data / Procurement of ICT Pending Collection, Quality Request for Single Stage - One equipment including IDA / D5840 Post Limited 0.00 Implementati 2020-04-29 2020-06-24 2020-12-21 Improvement, Dissemination Quotations Envelope laptops,photocopier and on and Use of Core Social and external drives Economic Statistics SL-MOFED-205719-GO-RFQ Pending Project Management and Request for Single Stage - One / Procurement of one vehicle IDA / D5840 Post Open - National 0.00 Implementati 2020-11-28 2021-01-23 2021-07-22 Monitoring and Evaluation Quotations Envelope for Project Coordination on SL-MOFED-205750-GO-RFB / procurement of servers Under Hardware (High Availability) Project Management and Single Stage - One IDA / D5840 Post Request for Bids Open - National 0.00 Implementati 2020-12-16 2020-12-17 2020-12-21 2021-02-01 2021-03-03 2021-04-07 2021-10-04 Windows Servers OS Monitoring and Evaluation Envelope on Microsoft, Client Antivirus and Software SL-MOFED-205730-GO-RFB / Procurement of laptop Country-Specific Component: Under computers for census Improving and modernizing Single Stage - One IDA / D5840 Post Request for Bids Open - International 0.00 Implementati 2020-11-30 2020-12-10 2020-12-05 2021-01-16 2021-02-15 2021-03-22 2021-09-18 including printers with physical and statistical Envelope on scanners for PCU Data infrastructure Science Team SL-MOFED-205734-GO-RFQ / Procurement of plotters, printers, machine for printing Country-Specific Component: of IEC materials, book binder& Under Improving and modernizing Request for Single Stage - One embroidery machines with IDA / D5840 Post Open - National 0.00 Implementati 2020-12-20 2021-02-14 2021-08-13 physical and statistical Quotations Envelope different sizes of flex on infrastructure banners& specific details to be provided before the procurement SL-MOFED-205740-GO-RFB / Procurement of Network Country-Specific Component: Under Infrastructural core Improving and modernizing Single Stage - One IDA / D5840 Post Request for Bids Open - National 0.00 Implementati 2020-11-25 2021-01-12 2020-11-30 2021-01-11 2021-02-10 2021-03-17 2021-09-13 equipment(Network hierarchy physical and statistical Envelope on design and HQ Structure infrastructure Cabling Country-Specific Component: SL-MOFED-205747-GO-RFB Pending Improving and modernizing / Procurement of cartographic IDA / D5840 Post Request for Bids 0.00 Implementati 2020-12-08 2020-12-13 2021-01-24 2021-02-23 2021-03-30 2021-09-26 physical and statistical imagery nation wide on infrastructure SL-MOFED-205736-GO-RFQ Country-Specific Component: / Procurement of Data Pending Improving and modernizing Request for Single Stage - One Collection Application IDA / D5840 Post Open - National 0.00 Implementati 2020-12-23 2021-02-17 2021-08-16 physical and statistical Quotations Envelope (Enumeration pad) with on infrastructure wireless network SL-MOFED-205748-GO-RFB Country-Specific Component: Under / Procurement of Android Improving and modernizing Single Stage - One IDA / D5840 Post Request for Bids Open - International 0.00 Implementati 2020-12-02 2020-12-10 2020-12-07 2021-01-18 2021-02-17 2021-03-24 2021-09-20 Tablets for Cartographic physical and statistical Envelope on mapping for Census operation infrastructure SL-MOFED-235343-GO-RFB / Procurement of Laptop Regional component: Computers, Docking Harmonization, Data Computers, Printers, Copiers, Pending Collection, Quality Single Stage - One Projectors, Recorders, IDA / D5840 Post Request for Bids Open - National 0.00 Implementati 2021-05-24 2021-05-29 2021-07-10 2021-08-09 2021-09-13 2022-03-12 Improvement, Dissemination Envelope Cameras, Digital Radios Sets, on and Use of Core Social and Scanners, UPS, Memory Sticks, Economic Statistics External Drives for PCU and Economic Statistics Regional component: SL-MOFED-235347-GO-RFQ Harmonization, Data Pending / Procurement of Office Collection, Quality Request for Single Stage - One IDA / D5840 Post Open - National 0.00 Implementati 2021-05-29 2021-07-24 2022-01-20 Furniture for three (3) field Improvement, Dissemination Quotations Envelope on Offices and Use of Core Social and Economic Statistics Page 1 Regional component: Harmonization, Data SL-MOFED-235349-GO-RFQ Pending Collection, Quality Request for Single Stage - One / Procurement of 50 Salter IDA / D5840 Post Open - National 0.00 Implementati 2021-05-29 2021-07-24 2022-01-20 Improvement, Dissemination Quotations Envelope Digital Scales on and Use of Core Social and Economic Statistics Regional component: Harmonization, Data SL-MOFED-235351-GO-RFQ Pending Collection, Quality Request for Single Stage - One / Procurement of Mobile IDA / D5840 Post Open - National 0.00 Implementati 2021-05-29 2021-07-24 2022-01-20 Improvement, Dissemination Quotations Envelope Network Infrastructure on and Use of Core Social and Economic Statistics SL-MOFED-235357-GO-RFB Regional component: / Procurement of Seventeen Harmonization, Data (17) Station Wagons, three Pending Collection, Quality Single Stage - One Out board Engines and IDA / D5840 Post Request for Bids Open - National 0.00 Implementati 2021-05-25 2021-05-30 2021-07-11 2021-08-10 2021-09-14 2022-03-13 Improvement, Dissemination Envelope Eighteen (18) Motor Bikes, on and Use of Core Social and Automatic for Stats-Sl for Economic Statistics Census and other Operations NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SL-MOFED-205746-NC-RFB / Procurement of mobile Country-Specific Component: network and Internet Services Pending Improving and modernizing Single Stage - One to support Mid-Term Census IDA / D5840 Post Request for Bids Open - National 0.00 Implementati 2020-12-07 2020-12-12 2021-01-23 2021-02-22 2021-03-29 2021-09-25 physical and statistical Envelope and Installation of high speed on infrastructure Internet Services for six months SL-MOFED-216498-NC-DIR Country-Specific Component: Under / Procurement of Satellite Improving and modernizing IDA / D5840 Post Direct Selection Direct 0.00 Implementati 2021-02-01 2021-02-04 2021-02-06 2021-03-13 2021-09-09 Imagery for Cartographic physical and statistical on Mappings Nation wide infrastructure CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SL-MOFED-205744-CS-CQS Country-Specific Component: / Recruitment of a consultant Consultant Improving and modernizing Pending to support CAP1, Tablets, IDA / D5840 Post Qualification Open - National 0.00 2020-12-14 2021-01-04 2021-02-17 2021-03-19 2021-04-23 2021-10-20 physical and statistical Implementation Provisioning and Data Selection infrastructure Analysis SL-MOFED-226614-CS-LCS / Audit of Financial Statements Project Management and Least Cost Under IDA / D5840 Post Open - National 0.00 2021-03-26 2021-04-12 2021-04-16 2021-05-30 2021-06-27 2021-07-27 2021-08-31 2021-10-05 2022-04-03 for HISWA- Project (November- Monitoring and Evaluation Selection Implementation 2020- December,2021) SL-MOFED-235355-CS-CQS Regional component: / Hire a firm to conduct Harmonization, Data Consultant preparatory works for Stats SL Collection, Quality Pending IDA / D5840 Post Qualification Open - National 0.00 2021-05-25 2021-06-15 2021-07-29 2021-08-28 2021-10-02 2022-03-31 HQ rehabilitation of physical Improvement, Dissemination Implementation Selection infrastructure (Pre- and Use of Core Social and Construction activities) Economic Statistics INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Contract Type Process Status Teams of Reference Identified/Selected Signed Contract Contract Completion No. (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SL-MOFED-167863-CS-INDV Individual / Hiring a consultant to Project Management and Under IDA / D5840 Post Consultant Limited 0.00 2020-04-09 2020-04-14 2020-04-14 2020-05-05 2020-06-09 2020-12-06 develop the Project Monitoring and Evaluation Implementation Selection Implementation Manual Regional component: SL-MOFED-235339-CS-INDV Harmonization, Data Individual / Recruitment of an Individual Collection, Quality Pending IDA / D5840 Post Consultant Open 0.00 2021-05-19 2021-07-07 2021-07-28 2021-09-01 2022-02-28 Consultant as CAPI Consultant Improvement, Dissemination Implementation Selection for tablet provisioning and Use of Core Social and Economic Statistics Regional component: SL-MOFED-235340-CS-INDV Harmonization, Data Individual / Recruitment of an Individual Collection, Quality Pending IDA / D5840 Post Consultant Open 0.00 2021-05-19 2021-07-07 2021-07-28 2021-09-01 2022-02-28 Consultant for processing of Improvement, Dissemination Implementation Selection Data Analysis and Use of Core Social and Economic Statistics Regional component: SL-MOFED-235082-CS-INDV Harmonization, Data / Recruitment of an Individual Individual Collection, Quality Consultant for CAPI IDA / D5840 Post Consultant Open 0.00 Canceled 2021-05-18 2021-07-06 2021-07-27 2021-08-31 2022-02-27 Improvement, Dissemination Development for Data Selection and Use of Core Social and Management Economic Statistics Regional component: SL-MOFED-235337-CS-CDS Harmonization, Data / Recruitment of CSPro Collection, Quality Under IDA / D5840 Post Direct Selection Direct 0.00 2021-05-19 2021-05-24 2021-05-29 2021-08-02 2022-01-29 Consultant for digitizing the Improvement, Dissemination Implementation mid Term Census and Use of Core Social and Economic Statistics Page 2 PROCUREMENT PLAN (Textual Part) Project information: [Mozambique] [Sustainable Rural Economy Program] [P-174002] Project Implementation agency: [Ministério da Agricultura e Desenvolvimento Rural] Date of the Procurement Plan: [2021, 01 April] Period covered by this Procurement Plan: [18 months] Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (November 2020) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in “Regulamento de Contratação de Empreitada de Obras Públicas, Fornecimento de Bens e Prestação de Serviços ao Estado” of the Republic of Mozambique of March 8, 2016 (“the Regulation”), as per Decree No. 5/2016, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). NA Goods: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables]; To be identified Works: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables]: To be identified Other Relevant Procurement Information. NA PROCUREMENT Mozambique : Sustainable Rural Economy Program PLAN General Information Country: Mozambique Bank’s Approval Date of the Original Procurement Plan: 2021-05-07 2021-05-19 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P174002 GPN Date: Project Name: Sustainable Rural Economy Program Loan / Credit No: / Foundation for the Conservation of Biodiversity Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 10/ANAC/SREP/G/21 / Under Enhancing natural resources Acquisition of 5 motorbike for / Post Direct Selection Direct 5,000.00 0.00 Implementati 2021-06-15 2021-06-03 2021-06-20 2021-07-25 2022-01-21 management Tchuma Tchato on NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 08/ANAC/SREP/CQS/21 / Consultant Development of the Enhancing natural resources / Post Qualification Open - National 23,200.00 0.00 Under Review 2021-05-31 2021-06-03 2021-06-21 2021-08-04 2021-09-03 2021-10-08 2022-04-06 Management Plan for the management Selection Mágoe National Park 09/ANAC/SREP/CQS/21 / Development of an Integrated Consultant Enhancing natural resources Development Plan for the / Post Qualification Open - National 80,000.00 0.00 Under Review 2021-05-31 2021-06-03 2021-06-21 2021-08-04 2021-09-03 2021-10-08 2022-04-06 management Tchuma Tchato Community Selection Program INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 01/BIOFUND/SREP/IC/21 / Individual Strengthening institutions Under Procurement Officer for / Prior Consultant Open 72,000.00 0.00 2021-05-31 2021-06-09 2021-07-19 2021-08-09 2021-09-13 2022-03-12 and policies Implementation BIOFUND Selection Individual 02/BIOFUND/SREP/IC/21 / Strengthening institutions Under / Post Consultant Open 60,000.00 0.00 2021-05-31 2021-06-03 2021-07-19 2021-08-09 2021-09-13 2022-03-12 Accountant for BIOFUND and policies Implementation Selection 07/ANAC/SREP/IC/21 / Individual Finance and Human Resources Enhancing natural resources Under / Post Consultant Open 60,000.00 0.00 2021-05-31 2021-06-03 2021-07-19 2021-08-09 2021-09-13 2022-03-12 Officer for Mágoe National management Implementation Selection Park 06/ANAC/SREP/IC/21 / Community Development and Individual Enhancing natural resources Under Environmental Education / Post Consultant Open 60,000.00 0.00 2021-05-31 2021-06-03 2021-07-19 2021-08-09 2021-09-13 2022-03-12 management Implementation Officer for the Mágoe National Selection Park 04/ANAC/SREP/IC/21 / Individual Enhancing natural resources Under Operations Manager for / Post Consultant Open 103,200.00 0.00 2021-05-31 2021-06-10 2021-07-19 2021-08-09 2021-09-13 2022-03-12 management Implementation Tchuma Tchato Selection 05/ANAC/SREP/IC/21 / Community Development and Individual Enhancing natural resources Under Environmental Education / Post Consultant Open 60,000.00 0.00 2021-05-31 2021-06-03 2021-07-19 2021-08-09 2021-09-13 2022-03-12 management Implementation Officer for the Tchuma Tchato Selection Community Program 03/ANAC/SREP/IC/21 / Individual Enhancing natural resources Under Operations Manager for / Post Consultant Open 103,200.00 0.00 2021-05-31 2021-06-03 2021-07-19 2021-08-09 2021-09-13 2022-03-12 management Implementation Mágoe National Park Selection Page 1 PROCUREMENT PLAN Project information: COVID-19 EMERGENCY Response and Health Systems Preparedness Project Project Implementation agency: Ministry Of Health, Nutrition and Indigenous Medicine, Sri Lanka Date of the Procurement Plan: 24 MARCH 2020 Period covered by this Procurement Plan: 01 April 2020 to 30 June 2020 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016, Revised November 2017 and August 2018) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Procedures In accordance with the Procurement Regulations for IPF Borrowers (July 2016, revised November 2017) (“Procurement Regulations”), when approaching the national market, as agreed in the Procurement Plan tables in STEP, the country’s own procurement procedures may be used. When the Borrower, for the procurement of goods, works and non-consulting services, uses its own national open competitive procurement arrangements as set forth in Sri Lanka’s Procurement Guidelines 2006, such arrangements shall be subject to paragraph 5.4 of the Bank’s Procurement Regulations and the following conditions: 1. Only bidding documents acceptable to the Bank shall be used for all national open competitive procurement. 2. The request for bids/request for proposals document shall require that bidders/proposers submitting bids/proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. 3. The eligibility of bidders shall be as defined under Section III of the World Bank Procurement Regulations for IPF Borrowers (Procurement Regulations): accordingly, no bidder or potential bidder shall be declared ineligible for contracts financed by the Bank for reasons other than those provided in Section III of the Procurement Regulations. 4. In case of Open Tendering, the receipt of less than three bids shall not be considered grounds for cancellation and re-invitation of bids 5. Procurement Documents include provisions, as agreed with the Bank, intended to adequately mitigate against environmental, social (including sexual exploitation and abuse and gender-based violence), health and safety (“ESHS”) risks and impacts Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second-Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables]; Works: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables] Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. HEIS is recommended for this project. Other Relevant Procurement Information. Since this is an emergency response project there will be no prior review for all procurement during the relief phase. Procurement of items for emergency requirements will follow methods of Direct Contracting, Procurement from UN Agencies, Limited bidding, etc. This project will also have higher value threshold for shopping and National procurement, as applicable in emergency projects. PROCUREMENT Sri Lanka : Sri Lanka COVID-19 Emergency Response and Health Systems Preparedness Project PLAN General Information Country: Sri Lanka Bank’s Approval Date of the Original Procurement Plan: 2020-05- 07 2021-05- Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P173867 GPN Date: 24 2020-04- Project Name: Sri Lanka COVID-19 Emergency Response and Health Systems Preparedness Project 30 Loan / Credit No: IBRD / 90850, IDA / 65950, TF / B3017 Ministry of Health Services and Indigenous Medicine Executing Agency(ies): WORKS Activity Reference No. Procurement Estimate Actual Draft Pre- Draft Bidding Specific Proposal Bid Evaluation Loan / Credit Market Procurement Prequalificati High SEA/SH Process Prequalification Bidding Documents Contract / Description Component Review Type Method Document d Amount qualification Document / Procurement Notice Submission / Report and Signed Contract No. Approach Process on (Y/N) Risk Status Evaluation Report as Issued Completion Type Amount (US$) Documents Justification / Invitation Opening / Minutes Recommendation (US$) Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned for Award Actual Planned Actual Planne d LK-MOH-171565-CW-RFQ / Modifications and Pending refurbishment to provide Component 1: Emergency Request for Single Stage - One 2020-05- 2020-07- 2021- IBRD / 90850 Post Limited 60,000.00 0.00 Implemen isolation facilities for Covid COVID-19 Response Quotations Envelope 25 20 01-16 tation 19 patients with ICUs in National Hospital Kandy LK-MOH-173948-CW-RFQ / Partitioning Eighth Floor Pending for Isolating Rooms at Eight Component 1: Emergency Request for Single Stage - One 2020-06- 2020-07- 2020- IDA / 65950 Post Limited 17,300.00 0.00 Implemen Storied Building – COVID-19 Response Quotations Envelope 08 27 08-26 tation District General Hospital Negombo LK-MOH-173947-CW-RFQ / Water Proofing work at Component 1: Emergency Request for Single Stage - One 2020-06- 2020-07- 2020- IDA / 65950 Post Limited 12,420.00 0.00 Canceled Gampaha District General COVID-19 Response Quotations Envelope 05 24 08-23 Hospital new ICU unit LK-MOH-181751-CW-RFQ Pending / Conversion the WD 24 as Component 1: Emergency Request for Single Stage - One 2020-06- 2020-08- 2020- IDA / 65950 Post Limited 32,343.00 0.00 Implemen Covid 19 Ward at Badulla COVID-19 Response Quotations Envelope 30 11 09-01 tation Provincial General Hospital LK-MOH-181753-CW-RFQ / Convert Existing OPD C Pending Component 1: Emergency Request for Single Stage - One 2020-06- 2020-08- 2020- room for checking Corona IDA / 65950 Post Limited 6,694.00 0.00 Implemen COVID-19 Response Quotations Envelope 30 18 09-08 Patients at Gampaha tation Provincial General Hospital LK-MOH-189400-CW-RFQ / Extension of Piped Medical Pending gas System for ward No.22 Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020- IDA / 65950 Post Limited 3,980.00 0.00 Implemen and ward No. 03 obtained COVID-19 Response Quotations Envelope 24 19 11-09 tation by Badulla General Hospital during Covid period. LK-MOH-189741-CW-RFQ / Supplying and fixing Recast Concrete Soak-age Pending pit for mortuary Area and Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020- IDA / 65950 Post Limited 2,363.00 0.00 Implemen Fixing of Door for A & e COVID-19 Response Quotations Envelope 26 21 11-11 tation Theater area and orthopedic Clinic area at Baticalo General Hospital during Covid Period. LK-MOH-189742-CW-RFQ Pending / Improvement of covid 19 Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020- IDA / 65950 Post Limited 1,916.00 0.00 Implemen unit with aluminium COVID-19 Response Quotations Envelope 26 21 11-11 tation partition at Baticalo General Hospital LK-MOH-189743-CW-RFQ / Supply and fixing of Pending Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020- patient waiting shed at IDA / 65950 Post Limited 6,484.00 0.00 Implemen COVID-19 Response Quotations Envelope 26 21 11-11 Baticalo General Hospital tation during Covid period. LK-MOH-189747-CW-RFB Pending / Renovation Of Ward 36 at Component 1: Emergency Single Stage - One 2020-08- 2020-08- 2020-09- 2020-09- 2020-10- 2020- IDA / 65950 Post Request for Bids Limited 18,336.00 0.00 Implemen Kandy General Hospital COVID-19 Response Envelope 21 26 09 23 21 11-11 tation during Covid period LK-MOH-189749-CW-RFB / Construction Of New Component 1: Emergency Single Stage - One 2020-08- 2020-09- 2020-08- 2020-09- 2020-09- 2020-09- 2020-09- 2020-09- 2020-10- 2020-09- 2020- Nurses Room At Ward No:10 IDA / 65950 Post Request for Bids Limited 4,969.00 6,405.41 Signed COVID-19 Response Envelope 21 01 26 01 09 10 23 11 21 11 11-11 at Kandy General Hospital during Covid period LK-MOH-189750-CW-RFB / Renovation of SBU For Component 1: Emergency Single Stage - One 2020-08- 2020-09- 2020-08- 2020-09- 2020-09- 2020-09- 2020-09- 2020-09- 2020-10- 2020-09- 2020- IDA / 65950 Post Request for Bids Limited 5,411.00 8,195.12 Signed Covid-19 Epidemic at Kandy COVID-19 Response Envelope 21 01 26 01 09 06 23 09 21 11 11-11 General Hospital during Covid period LK-MOH-189751-CW-RFB / Renovation of ETU, MICU, CT Scan Room, Bleeding Component 1: Emergency Single Stage - One 2020-08- 2020-09- 2020-08- 2020-09- 2020-09- 2020-09- 2020-09- 2020-09- 2020-10- 2020-09- 2020- Room and OPD Entrance IDA / 65950 Post Request for Bids Limited 6,682.00 7,844.49 Signed COVID-19 Response Envelope 21 01 26 01 09 10 23 11 21 14 11-11 Area For Covid -19 Epidemic at Kandy General Hospital during Covid period. LK-MOH-189752-CW-RFB / Construction of New Admission Rooms And Component 1: Emergency Single Stage - One 15,772.9 2020-08- 2020-09- 2020-08- 2020-09- 2020-09- 2020-09- 2020-09- 2020-09- 2020-10- 2020-09- 2020- Renovation of Wards For IDA / 65950 Post Request for Bids Limited 15,600.00 Signed COVID-19 Response Envelope 9 21 01 26 01 09 10 23 11 21 11 11-11 Corona Epidemic at Kandy General Hospital during Covid period. LK-MOH-189754-CW-RFB / Construction of New Admission Rooms And Pending Component 1: Emergency Single Stage - One 132,914.0 2020-08- 2020-08- 2020-09- 2020-09- 2020-10- 2020- Renovation of Wards For IDA / 65950 Post Request for Bids Limited 0.00 Implemen COVID-19 Response Envelope 0 21 26 09 23 21 11-11 Corona Epidemic at Kandy tation General Hospital during Covid period LK-MOH-189755-CW-RFB / Installation of Utility Pending Component 1: Emergency Single Stage - One 2020-08- 2020-08- 2020-09- 2020-09- 2020-10- 2020- Supply For New Fourth Cath IDA / 65950 Post Request for Bids Limited 4,032.00 0.00 Implemen COVID-19 Response Envelope 21 26 09 23 21 11-11 Lab at Kandy General tation Hospital during Covid period. LK-MOH-189756-CW-RFB / Renovation of Cath Lab at Component 1: Emergency Single Stage - One 11,005.4 2020-08- 2020-09- 2020-08- 2020-09- 2020-09- 2020-09- 2020-09- 2020-09- 2020-10- 2020-09- 2020- IDA / 65950 Post Request for Bids Limited 7,801.00 Signed Kandy General Hospital COVID-19 Response Envelope 1 21 01 26 01 09 10 23 11 21 11 11-11 during Covid period. LK-MOH-189757-CW-RFB / Rearrangement Component 1: Emergency Single Stage - One 18,860.9 2020-08- 2020-09- 2020-08- 2020-09- 2020-09- 2020-09- 2020-09- 2020-09- 2020-10- 2020-09- 2020- Intermediate ICU For Covid IDA / 65950 Post Request for Bids Limited 15,963.00 Signed COVID-19 Response Envelope 3 21 01 26 01 09 10 23 13 21 14 11-11 -19 Epidemic at Kandy General Hospital during Covid period. LK-MOH-189758-CW-RFB / Demolishing of Old Director Quarters,Toilet Pending Component 1: Emergency Single Stage - One 2020-08- 2020-08- 2020-09- 2020-09- 2020-10- 2020- block and Temporary IDA / 65950 Post Request for Bids Limited 4,136.00 0.00 Implemen COVID-19 Response Envelope 21 26 09 23 21 11-11 Waiting Wall for Proposed tation Isolation Ward Complex at Kandy General Hospital during Covid period. LK-MOH-189759-CW-RFB / Renovation of Ward -5 and 6 For Covid -19 Component 1: Emergency Single Stage - One 11,772.9 2020-08- 2020-09- 2020-08- 2020-09- 2020-09- 2020-09- 2020-09- 2020-09- 2020-10- 2020-09- 2020- IDA / 65950 Post Request for Bids Limited 10,283.00 Signed Epidemic at Base Hospital- COVID-19 Response Envelope 8 21 01 26 01 09 10 23 11 21 11 11-11 Theldeniya at andy General Hospital during Covid period. LK-MOH-190363-CW-RFQ / Supply of necessary electrical supplies for air Pending conditioners in the section Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020- IDA / 65950 Post Limited 263.00 0.00 Implemen dedicated to Covid-19 COVID-19 Response Quotations Envelope 31 12 11-02 tation suspected patients in old medical intensive care unit at Ragama Teaching Hospital during Covid period. LK-MOH-190404-CW-RFQ / Partition work for Isolation Pending Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020- Room, Supply & fixing of IDA / 65950 Post Limited 809.00 0.00 Implemen COVID-19 Response Quotations Envelope 31 12 11-02 sink and Electrical work in tation ward No.18 at NCTH Ragama. LK-MOH-190405-CW-RFQ Pending / Construction of Fence or Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020- IDA / 65950 Post Limited 1,502.00 0.00 Implemen wall between OPD Building COVID-19 Response Quotations Envelope 31 12 11-02 tation & Clinic Building at NCTH Ragama LK-MOH-190447-CW-DIR / Construction of Bathroom Pending Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020- for Isolation room at IDA / 65950 Post Direct Selection Direct 1,497.00 0.00 Implemen COVID-19 Response 26 31 14 09-28 Rathnapura General Hospital tation during Covid period LK-MOH-190449-CW-DIR / Construction of Exhaust Pending line with HEPA Filters for Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020- IDA / 65950 Post Direct Selection Direct 2,033.00 0.00 Implemen Ward No.28 &Isolation room COVID-19 Response 26 31 14 09-28 tation at Rathnapura General Hospital during Covid period . LK-MOH-190450-CW-DIR / Construction of Exhaust Pending Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020- line with HEPA Filters for A IDA / 65950 Post Direct Selection Direct 2,033.00 0.00 Implemen COVID-19 Response 26 31 14 09-28 & E ICU at Rathnapura tation General Hospital during Covid period . LK-MOH-190925-CW-RFQ / Renovation of emergency Treatment unit, Ward 02 and Intensive care unit of Pending Component 1: Emergency Request for Single Stage - One 2020-09- 2020-10- 2020- Base Hospital (Teaching) IDA / 65950 Post Limited 13,973.00 0.00 Implemen COVID-19 Response Quotations Envelope 02 28 11-27 Gampola to treat patients tation suspected of having COVID 19 at Gampola Base Hospital during Covid period LK-MOH-190926-CW-RFQ / Development of triage Pending area and patient Component 1: Emergency Request for Single Stage - One 2020-09- 2020-10- 2020- IDA / 65950 Post Limited 16,175.00 0.00 Implemen examination room for COVID-19 Response Quotations Envelope 02 28 11-27 tation patients suspected of having COVID 19 at Base Hospital (Teaching) Gampola LK-MOH-190927-CW-RFQ / Development of triage area at Medical Clinic, Pediatrics clinic, Obstetrics Pending Component 1: Emergency Request for Single Stage - One 2020-09- 2020-10- 2020- clinic and Gynecological IDA / 65950 Post Limited 12,671.00 0.00 Implemen COVID-19 Response Quotations Envelope 02 28 11-27 clinic of Base Hospital tation (Teaching) Gampola and construction of patient waiting area at clinic to ensure physical LK-MOH-191041-CW-DIR Pending / Aluminium Works at Component 1: Emergency 2020-08- 2020-09- 2020-10- 2021- IDA / 65950 Post Direct Selection Direct 211.00 0.00 Implemen Ragama Teaching Hospital COVID-19 Response 28 02 07 04-05 tation during Covid period LK-MOH-192338-CW-RFQ Pending / Refurbishment of technical Component 1: Emergency Request for Single Stage - One 2020-09- 2020-11- 2020- TF / B3017 Post Limited 31,579.00 0.00 Implemen units of Health Promotion COVID-19 Response Quotations Envelope 28 09 12-09 tation Bureau under Covid Grant LK-MOH-192339-CW-RFQ / Renovation of Dining Room , Partitioning of Pending Component 1: Emergency Request for Single Stage - One 2020-10- 2020-11- 2020- Planning unit ,Renovation of TF / B3017 Post Limited 14,022.00 0.00 Implemen COVID-19 Response Quotations Envelope 11 22 12-22 Mithuru Piyasa & Women tation Health Unit at Family Health Bureau under Covid Grant LK-MOH-192353-CW-RFQ / Renovation and Pending Component 1: Emergency Request for Single Stage - One 2020-09- 2020-11- 2020- refurbishment of psychiatry TF / B3017 Post Limited 26,316.00 0.00 Implemen COVID-19 Response Quotations Envelope 28 09 12-09 unit at NHSL: Ward 59 under tation Covid Grant by College of psychiatry. LK-MOH-192360-CW-RFQ / Renovation of psychiatry Pending Component 1: Emergency Request for Single Stage - One 2020-09- 2020-11- 2020- clinic at Base Hospital TF / B3017 Post Limited 526.00 0.00 Implemen COVID-19 Response Quotations Envelope 28 09 12-09 Horana under Covid Grant tation by College of psychiatry. LK-MOH-192365-CW-RFQ / Renovation of seclusion room at District General Pending Component 1: Emergency Request for Single Stage - One 2020-09- 2020-11- 2020- Hospital Vavunia to be used TF / B3017 Post Limited 1,842.00 0.00 Implemen COVID-19 Response Quotations Envelope 28 09 12-09 as an isolation room or a tation seclusion room under Covid Grant by College of Psychiatry. LK-MOH-192367-CW-RFQ / Renovating psychiatry Pending Component 1: Emergency Request for Single Stage - One 2020-09- 2020-11- 2020- clinic at Base Hospital TF / B3017 Post Limited 10,209.00 0.00 Implemen COVID-19 Response Quotations Envelope 28 09 12-09 Nikaweratiya under Covid tation Grant by College of psychiatry. LK-MOH-192369-CW-RFQ / Renovating and Pending refurbishing psychiatry Component 1: Emergency Request for Single Stage - One 2020-09- 2020-11- 2020- TF / B3017 Post Limited 526.00 0.00 Implemen clinic at Base Hospital COVID-19 Response Quotations Envelope 28 09 12-09 tation Panadura under Covid Grant by College of psychiatry LK-MOH-192376-CW-RFQ Pending / Renovating mother baby Component 1: Emergency Request for Single Stage - One 2020-09- 2020-11- 2020- TF / B3017 Post Limited 1,316.00 0.00 Implemen unit at Base Hospital COVID-19 Response Quotations Envelope 28 09 12-09 tation Trincomalee by College of Psychiatry LK-MOH-192378-CW-RFQ Pending / Renovating and Component 1: Emergency Request for Single Stage - One 2020-09- 2020-11- 2020- TF / B3017 Post Limited 8,342.00 0.00 Implemen refurbishment of psychiatry COVID-19 Response Quotations Envelope 28 09 12-09 tation unit at Teaching Hospital Batticoloa LK-MOH-192382-CW-RFQ / Renovating psychiatry Pending Component 1: Emergency Request for Single Stage - One 2020-09- 2020-11- 2020- ward and clinic at General TF / B3017 Post Limited 5,794.00 0.00 Implemen COVID-19 Response Quotations Envelope 28 09 12-09 Hospital Rathnapura under tation Covid Grant by College of Psychiatry. LK-MOH-192383-CW-RFQ Pending / Renovating Psychiatry Component 1: Emergency Request for Single Stage - One 2020-09- 2020-11- 2020- TF / B3017 Post Limited 4,845.00 0.00 Implemen ward Nuwaraeliya to include COVID-19 Response Quotations Envelope 28 09 12-09 tation mother baby unit LK-MOH-192387-CW-RFQ / Renovating and Pending refurbishing child and Component 1: Emergency Request for Single Stage - One 2020-09- 2020-11- 2020- TF / B3017 Post Limited 21,053.00 0.00 Implemen adolescent psychiatry unit COVID-19 Response Quotations Envelope 28 09 12-09 tation Teaching Hospital Jaffna under Covid Grant by College of Psychiatry LK-MOH-192388-CW-RFQ / Renovating and Pending Component 1: Emergency Request for Single Stage - One 2020-09- 2020-11- 2020- refurbishing psychiatry TF / B3017 Post Limited 15,790.00 0.00 Implemen COVID-19 Response Quotations Envelope 28 09 12-09 clinic Base Hospital tation Telippalai under Covid Grant by College of Psychiatry. LK-MOH-192389-CW-RFQ / Renovating the Pending Component 1: Emergency Request for Single Stage - One 2020-09- 2020-11- 2020- occupational therapy unit TF / B3017 Post Limited 23,684.00 0.00 Implemen COVID-19 Response Quotations Envelope 28 09 12-09 Base Hospital Tellippalai tation under Covid Grant by College of Psychiatry LK-MOH-192391-CW-RFQ / Renovation of psychiatry Pending Component 1: Emergency Request for Single Stage - One 2020-09- 2020-11- 2020- clinic Teaching Hospital TF / B3017 Post Limited 2,632.00 0.00 Implemen COVID-19 Response Quotations Envelope 28 09 12-09 Kuliyapitiya under Covid tation Grant by College of Psychistry LK-MOH-192392-CW-RFQ / Development of Pending Component 1: Emergency Request for Single Stage - One 2020-09- 2020-11- 2020- occupational therapy unit at TF / B3017 Post Limited 526.00 0.00 Implemen COVID-19 Response Quotations Envelope 28 09 12-09 Base Hospital Mannar under tation Covid Grant by College of Psychiatry LK-MOH-192393-CW-RFQ / Renovating occupational therapy area and fencing Pending Component 1: Emergency Request for Single Stage - One 2020-09- 2020-11- 2020- the horticulture area at TF / B3017 Post Limited 677.00 0.00 Implemen COVID-19 Response Quotations Envelope 28 09 12-09 District General Hospital tation Kaluthara under Covid Grant by College of Psychiatry LK-MOH-192400-CW-RFQ / Renovating and Pending Component 1: Emergency Request for Single Stage - One 2020-09- 2020-11- 2020- refurbishing rehabilitation TF / B3017 Post Limited 6,316.00 0.00 Implemen COVID-19 Response Quotations Envelope 28 09 12-09 unit at General Hospital tation Delthota under Covid Grant by College og Psychiatry LK-MOH-192401-CW-RFQ Pending / Renovate existing ward as Component 1: Emergency Request for Single Stage - One 2020-09- 2020-11- 2020- TF / B3017 Post Limited 26,316.00 0.00 Implemen alcohol rehabilitation unit at COVID-19 Response Quotations Envelope 28 09 12-09 tation District Hospital Hikkaduwa LK-MOH-192666-CW-RFQ Pending / Renovation and Component 1: Emergency Request for Single Stage - One 135,962.0 2020-10- 2020-11- 2020- TF / B3017 Post Limited 0.00 Implemen refurbishment of COVID-19 Response Quotations Envelope 0 12 23 12-23 tation Epidemiology Unit under Covid Grant LK-MOH-193045-CW-RFQ / Pending Component 1: Emergency Request for Single Stage - One 2020-10- 2020-11- 2020- Construction/Refurbishment TF / B3017 Post Limited 632.00 0.00 Implemen COVID-19 Response Quotations Envelope 05 16 12-16 of child mental health unit tation at DH Thalangama under Covid Grant Page 1 LK-MOH-193046-CW-RFQ / Pending Component 1: Emergency Request for Single Stage - One 2020-10- 2020-11- 2020- Construction/Refurbishment TF / B3017 Post Limited 1,782.00 0.00 Implemen COVID-19 Response Quotations Envelope 05 16 12-16 of child mental health unit tation in General Hospital Katugasthota under Covid Grant LK-MOH-193047-CW-RFQ / Pending Component 1: Emergency Request for Single Stage - One 2020-10- 2020-11- 2020- Construction/Refurbishment TF / B3017 Post Limited 20,563.00 0.00 Implemen COVID-19 Response Quotations Envelope 05 16 12-16 of child mental health unit tation in District Hospital Monaragala under Covid Grant LK-MOH-193472-CW-RFB / Renovation of Ward 34 For Pending Component 1: Emergency Single Stage - One 2020-09- 2020-09- 2020-10- 2020-10- 2020-11- 2020- Covid -19 Epidemic at IDA / 65950 Post Request for Bids Limited 13,214.00 0.00 Implemen COVID-19 Response Envelope 11 16 07 21 11 12-11 Kandy Teaching Hospital tation during Covid period (Advance) LK-MOH-193592-CW-RFQ / Relocation, Modification & Pending Expansion of National Component 1: Emergency Request for Single Stage - One 107,605.0 2020-10- 2020-12- 2021- TF / B3017 Post Limited 0.00 Implemen Institute of Mental Health COVID-19 Response Quotations Envelope 0 23 04 01-03 tation rehabilitation centers under Covid Grant LK-MOH-198635-CW-RFQ / Renovating and Pending Conversion of existing ward Component 1: Emergency Request for Single Stage - One 2020-11- 2020-12- 2021- TF / B3017 Post Limited 82,489.00 0.00 Implemen building Floor to Covid 19 COVID-19 Response Quotations Envelope 02 14 01-13 tation treatment ward at Warakapola hospital, Kagalla District. LK-MOH-201654-CW-RFQ / Renovation of Male Ward (4) ,Male Ward (5) ,Female Ward (1) ,Female Ward (2), Pending Component 1: Emergency Request for Single Stage - One 188,440.0 2020-11- 2020-12- 2021- Female Ward (3), Female IDA / 65950 Post Limited 0.00 Implemen COVID-19 Response Quotations Envelope 0 10 15 01-14 Ward (5), Admin Block (1), tation Admin Block (2) and ETU (1) of infectious Disease Hospital at Kilinochchi, Northern Province LK-MOH-201656-CW-RFQ / Renovation of ETU (2) ,Patient Dinning area ,PCR collecting points, Driver quarters, Nurses quarters, Pending Component 1: Emergency Request for Single Stage - One 121,886.0 2020-11- 2020-12- 2021- Doctor quarters, security IDA / 65950 Post Limited 0.00 Implemen COVID-19 Response Quotations Envelope 0 04 09 01-08 quarters, MOIC quarters, tation Consultant quarters, staff dining area, Security hut (Nos-4), Ambulance park and Water Supply System LK-MOH-201657-CW-RFQ / External electricity arrangement ,Construction of waste water collection pit to ward Pending Component 1: Emergency Request for Single Stage - One 2020-11- 2020-12- 2021- no.01,02,03,04,05,06,07 IDA / 65950 Post Limited 90,259.00 0.00 Implemen COVID-19 Response Quotations Envelope 04 09 01-08 and 08, Renovation of tation Directors office, Material Supply Cost - Fencing work and Improvement of IDH internal Road at kirushnapuram (880m) LK-MOH-203649-CW-RFQ / Construction of Steel Roof Pending Cover for Container for Component 1: Emergency Request for Single Stage - One 2020-11- 2021-01- 2021- IDA / 65950 Post Limited 14,258.00 0.00 Implemen Covid Lab required by COVID-19 Response Quotations Envelope 13 08 07-07 tation General Hospital, Badulla during Covid period wave 1.(Advance) LK-MOH-203650-CW-RFQ / Improvement to Part of Pending the Ward no.03 for Covid Component 1: Emergency Request for Single Stage - One 2020-11- 2021-01- 2021- IDA / 65950 Post Limited 18,093.00 0.00 Implemen Patients required by General COVID-19 Response Quotations Envelope 13 08 07-07 tation Hospital, Badulla during Covid period wave 1.(Advance) LK-MOH-203651-CW-RFQ / Improvement of Ward Pending No.22 & 23 for covid Patient Component 1: Emergency Request for Single Stage - One 2020-11- 2021-01- 2021- IDA / 65950 Post Limited 11,073.00 0.00 Implemen treatment required by COVID-19 Response Quotations Envelope 13 08 07-07 tation General Hospital, Badulla during Covid period wave 1.(Advance) LK-MOH-203652-CW-RFQ / Extension of Piped Medical Pending gas System for ward No.22 Component 1: Emergency Request for Single Stage - One 2020-11- 2021-01- 2021- IDA / 65950 Post Limited 1,937.00 0.00 Implemen required by General COVID-19 Response Quotations Envelope 13 08 07-07 tation Hospital, Badulla during Covid period wave 1.(Advance) LK-MOH-203653-CW-RFQ / Extension of Piped Medical Pending gas System for ward No.03 Component 1: Emergency Request for Single Stage - One 2020-11- 2021-01- 2021- IDA / 65950 Post Limited 2,150.00 0.00 Implemen required by General COVID-19 Response Quotations Envelope 13 08 07-07 tation Hospital, Badulla during Covid period wave 1.(Advance) LK-MOH-203789-CW-RFQ / Renovation and Pending Component 1: Emergency Request for Single Stage - One 2020-12- 2021-01- 2021- modification to wards for IDA / 65950 Post Limited 31,351.00 0.00 Implemen COVID-19 Response Quotations Envelope 05 30 07-29 accommodating covid + tation patients at Badulla DH- Bogahakumbura LK-MOH-203793-CW-RFQ / Renovation and Pending Component 1: Emergency Request for Single Stage - One 2020-12- 2021-01- 2021- modification to wards for IDA / 65950 Post Limited 31,351.00 0.00 Implemen COVID-19 Response Quotations Envelope 05 30 07-29 accommodating covid + tation patients at Badulla DH- Bandarawela LK-MOH-203798-CW-RFQ / Renovation and Pending Component 1: Emergency Request for Single Stage - One 2020-12- 2021-01- 2021- modification to wards for IDA / 65950 Post Limited 31,351.00 0.00 Implemen COVID-19 Response Quotations Envelope 05 30 07-29 accommodating covid + tation patients at Badulla DH- Uraniya LK-MOH-203806-CW-RFQ Pending / Essential modification to Component 1: Emergency Request for Single Stage - One 2020-12- 2021-01- 2021- IDA / 65950 Post Limited 32,432.00 0.00 Implemen the hospital building at COVID-19 Response Quotations Envelope 05 30 07-29 tation Galle DH- Arachchikanda LK-MOH-203829-CW-RFQ / Completion of the civil Pending Component 1: Emergency Request for Single Stage - One 2020-12- 2021-01- 2021- works to the partially build IDA / 65950 Post Limited 15,135.00 0.00 Implemen COVID-19 Response Quotations Envelope 05 30 07-29 hospital building at tation Hikkaduwa Galle-DH LK-MOH-203832-CW-RFQ Pending / Civil work for modification Component 1: Emergency Request for Single Stage - One 2020-12- 2021-01- 2021- IDA / 65950 Post Limited 63,514.00 0.00 Implemen of Hospital Building at COVID-19 Response Quotations Envelope 05 30 07-29 tation Vidaththalthive Mannar DH LK-MOH-203841-CW-RFQ / Renovation and modification to wards for Pending Component 1: Emergency Request for Single Stage - One 2020-12- 2021-01- 2021- accommodating covid + IDA / 65950 Post Limited 21,082.00 0.00 Implemen COVID-19 Response Quotations Envelope 05 30 07-29 patients and Modifications tation Required for Ambulance washing bay at Kandy DH Pussallawa LK-MOH-203933-CW-RFQ / Renovation and Pending modification to wards for Component 1: Emergency Request for Single Stage - One 2020-12- 2021-01- 2021- IDA / 65950 Post Limited 61,081.00 0.00 Implemen accommodating covid + COVID-19 Response Quotations Envelope 05 30 07-29 tation patients at DH Padiyathalawa Ampara- _Eastern Province LK-MOH-203934-CW-RFQ / Renovation and Pending Component 1: Emergency Request for Single Stage - One 2020-12- 2021-01- 2021- modification to wards for IDA / 65950 Post Limited 60,162.00 0.00 Implemen COVID-19 Response Quotations Envelope 05 30 07-29 accommodating covid + tation patients at DH Kalmunai- _Eastern Province LK-MOH-203935-CW-RFQ / Renovation and Pending modification to wards for Component 1: Emergency Request for Single Stage - One 2020-12- 2021-01- 2021- IDA / 65950 Post Limited 10,654.00 0.00 Implemen accommodating covid + COVID-19 Response Quotations Envelope 05 30 07-29 tation patients at DH Karadiyanaru, Batticolo- _Eastern Province LK-MOH-203936-CW-RFQ / Renovation and Pending modification to wards for Component 1: Emergency Request for Single Stage - One 2020-12- 2021-01- 2021- IDA / 65950 Post Limited 72,270.00 0.00 Implemen accommodating covid + COVID-19 Response Quotations Envelope 05 30 07-29 tation patients at DH Echilammpaththu-Trinco- _Eastern Province LK-MOH-203945-CW-RFQ / Renovation and Pending modification to wards for Component 1: Emergency Request for Single Stage - One 2020-12- 2021-01- 2021- IDA / 65950 Post Limited 27,027.00 0.00 Implemen accommodating covid + COVID-19 Response Quotations Envelope 05 30 07-29 tation patients at DH Ambanpola, North Western Province LK-MOH-203947-CW-RFQ / Renovation and Pending modification to wards for Component 1: Emergency Request for Single Stage - One 2020-12- 2021-01- 2021- IDA / 65950 Post Limited 27,027.00 0.00 Implemen accommodating covid + COVID-19 Response Quotations Envelope 05 30 07-29 tation patients at DH Narammala, North Western Province LK-MOH-203948-CW-RFQ / Renovation and Pending modification to wards for Component 1: Emergency Request for Single Stage - One 2020-12- 2021-01- 2021- IDA / 65950 Post Limited 45,946.00 0.00 Implemen accommodating covid + COVID-19 Response Quotations Envelope 05 30 07-29 tation patients at DH Dankotuwa, North Western Province LK-MOH-203951-CW-RFQ / Partitioning and Pending Component 1: Emergency Request for Single Stage - One 2020-12- 2021-01- 2021- modification to wards for IDA / 65950 Post Limited 16,216.00 0.00 Implemen COVID-19 Response Quotations Envelope 05 30 07-29 accommodating covid + tation patients at Udugoda- aluminum works LK-MOH-203953-CW-RFQ / Renovation and Pending Component 1: Emergency Request for Single Stage - One 2020-12- 2021-01- 2021- modification to wards for IDA / 65950 Post Limited 32,432.00 0.00 Implemen COVID-19 Response Quotations Envelope 05 30 07-29 accommodating covid + tation patients at Rakwana DH LK-MOH-203954-CW-RFQ / Renovation and Pending Component 1: Emergency Request for Single Stage - One 2020-12- 2021-01- 2021- modification to wards for IDA / 65950 Post Limited 4,865.00 0.00 Implemen COVID-19 Response Quotations Envelope 05 30 07-29 accommodating covid + tation patients at Laggala DH , Matale LK-MOH-203955-CW-RFQ / Renovation and Pending Component 1: Emergency Request for Single Stage - One 2020-12- 2021-01- 2021- modification to wards for IDA / 65950 Post Limited 37,838.00 0.00 Implemen COVID-19 Response Quotations Envelope 05 30 07-29 accommodating covid + tation patients at Mankulam DH LK-MOH-203957-CW-RFQ / Renovation and Pending Component 1: Emergency Request for Single Stage - One 151,325.0 2020-12- 2021-01- 2021- modification to IDA / 65950 Post Limited 0.00 Implemen COVID-19 Response Quotations Envelope 0 05 30 07-29 Rehabilitation Center for tation covid + patients at Ampara DGH LK-MOH-203961-CW-RFQ Pending / Modification to ward Component 1: Emergency Request for Single Stage - One 2020-12- 2021-01- 2021- IDA / 65950 Post Limited 37,838.00 0.00 Implemen building to accommodate COVID-19 Response Quotations Envelope 05 30 07-29 tation for Covid patients of Walapane Hospital LK-MOH-203962-CW-RFQ Pending / Modification to ward Component 1: Emergency Request for Single Stage - One 2020-12- 2021-01- 2021- IDA / 65950 Post Limited 21,622.00 0.00 Implemen building to accommodate COVID-19 Response Quotations Envelope 05 30 07-29 tation Covid patients of Dikoya Hospital LK-MOH-203964-CW-RFQ / Constructions of Pending Component 1: Emergency Request for Single Stage - One 2020-12- 2021-01- 2021- ambulance washing bay at IDA / 65950 Post Limited 5,405.00 0.00 Implemen COVID-19 Response Quotations Envelope 05 30 07-29 Polonaruwa Pulathisipura tation National College of education LK-MOH-203965-CW-RFQ / Renovations and necessary Pending Component 1: Emergency Request for Single Stage - One 100,000.0 2020-12- 2021-01- 2021- improvements for covid 19 IDA / 65950 Post Limited 0.00 Implemen COVID-19 Response Quotations Envelope 0 05 30 07-29 suspected patients ward at tation DH Atabage LK-MOH-203966-CW-RFQ / Renovation and Pending Component 1: Emergency Request for Single Stage - One 2020-12- 2021-01- 2021- modification to wards for IDA / 65950 Post Limited 91,892.00 0.00 Implemen COVID-19 Response Quotations Envelope 05 30 07-29 accommodating covid + tation patients-Kithulgala Hospital LK-MOH-203968-CW-RFQ Pending / Improvement of existing Component 1: Emergency Request for Single Stage - One 2020-12- 2021-01- 2021- IDA / 65950 Post Limited 37,838.00 0.00 Implemen building at DH C Beligala COVID-19 Response Quotations Envelope 05 30 07-29 tation for Covid patient treatment LK-MOH-203969-CW-RFQ / Renovation and Pending Component 1: Emergency Request for Single Stage - One 122,703.0 2020-12- 2021-01- 2021- modification to wards and IDA / 65950 Post Limited 0.00 Implemen COVID-19 Response Quotations Envelope 0 05 30 07-29 other construction works for tation covid + patients at Ampara DGH LK-MOH-203976-CW-RFQ / To initiate ICU and HDU facilities to facilitate the Pending Component 1: Emergency Request for Single Stage - One 116,216.0 2020-12- 2021-01- 2021- management of COVID 19 IDA / 65950 Post Limited 0.00 Implemen COVID-19 Response Quotations Envelope 0 05 30 07-29 patients at Physical and tation Mental Rehabilitation Centre at Ampara DGH LK-MOH-203985-CW-RFQ / Modifications required to convert ward 25 to accommodate covid positive Pending Component 1: Emergency Request for Single Stage - One 2020-12- 2021-01- 2021- psychiatric male patients IDA / 65950 Post Limited 16,210.00 0.00 Implemen COVID-19 Response Quotations Envelope 05 30 07-29 and rehabilitation unit to tation accommodate the psychiatric covid positive female patients at NIMH LK-MOH-205317-CW-RFQ Pending / Refurbishment of ward no Component 1: Emergency Request for Single Stage - One 2020-12- 2021-01- 2021- IDA / 65950 Post Limited 9,189.00 0.00 Implemen 07 as covid intermediate COVID-19 Response Quotations Envelope 05 30 07-29 tation ward at Mahamodara TH LK-MOH-205318-CW-RFQ / Refurbishment of health Pending Component 1: Emergency Request for Single Stage - One 2020-12- 2021-01- 2021- education unit in to covid IDA / 65950 Post Limited 21,081.00 0.00 Implemen COVID-19 Response Quotations Envelope 05 30 07-29 isolation ward at TH tation Mahamodara LK-MOH-205321-CW-RFQ Pending / Establishing medical Component 1: Emergency Request for Single Stage - One 2020-12- 2021-01- 2021- IDA / 65950 Post Limited 16,216.00 0.00 Implemen cubicles with Air conditions COVID-19 Response Quotations Envelope 05 30 07-29 tation and communication system LK-MOH-205323-CW-RFQ Pending / Modifications Required for Component 1: Emergency Request for Single Stage - One 2020-12- 2021-01- 2021- IDA / 65950 Post Limited 5,405.00 0.00 Implemen Ambulance washing bay at COVID-19 Response Quotations Envelope 05 30 07-29 tation Akurana DH LK-MOH-205325-CW-RFQ / Renovation and Pending Component 1: Emergency Request for Single Stage - One 2020-12- 2021-01- 2021- modification of wards for IDA / 65950 Post Limited 16,216.00 0.00 Implemen COVID-19 Response Quotations Envelope 05 30 07-29 accommodating covid tation positive patients at Akurana DH LK-MOH-205326-CW-RFQ Pending / Telecommunication facility Component 1: Emergency Request for Single Stage - One 2020-12- 2021-01- 2021- IDA / 65950 Post Limited 7,868.00 0.00 Implemen and surveillance system for COVID-19 Response Quotations Envelope 05 30 07-29 tation Pussalawa and Akurana DH LK-MOH-205328-CW-RFQ / Renovation and Pending Component 1: Emergency Request for Single Stage - One 2020-12- 2021-01- 2021- modification of wards for IDA / 65950 Post Limited 32,432.00 0.00 Implemen COVID-19 Response Quotations Envelope 05 30 07-29 accommodating covid tation positive patients at DH, Buttala LK-MOH-205332-CW-RFQ / Renovation and Pending Component 1: Emergency Request for Single Stage - One 2020-12- 2021-01- 2021- modification to wards for IDA / 65950 Post Limited 62,864.00 0.00 Implemen COVID-19 Response Quotations Envelope 05 30 07-29 accommodating covid + tation patients at Palamunai DH LK-MOH-205333-CW-RFQ / Renovation and Pending Component 1: Emergency Request for Single Stage - One 2020-12- 2021-01- 2021- modification to wards for IDA / 65950 Post Limited 62,865.00 0.00 Implemen COVID-19 Response Quotations Envelope 05 30 07-29 accommodating covid + tation patients at Echchilampaththu DH LK-MOH-205336-CW-RFQ / Modification to ward 21 Pending Component 1: Emergency Request for Single Stage - One 2020-12- 2021-01- 2021- converting to isolation ward IDA / 65950 Post Limited 11,351.00 0.00 Implemen COVID-19 Response Quotations Envelope 05 30 07-29 at Apeksha Hospital tation Maharagama LK-MOH-205478-CW-RFQ / Renovation and Pending Component 1: Emergency Request for Single Stage - One 2020-12- 2021-01- 2021- modification to wards for IDA / 65950 Post Limited 75,675.00 0.00 Implemen COVID-19 Response Quotations Envelope 05 30 07-29 accommodating covid + tation patients at Gampola Base Hospital LK-MOH-205479-CW-RFQ / Conversion of DH Pending Component 1: Emergency Request for Single Stage - One 102,703.0 2020-12- 2021-01- 2021- Unawatuna to quarantine IDA / 65950 Post Limited 0.00 Implemen COVID-19 Response Quotations Envelope 0 05 30 07-29 and management of covid tation 19 psychiatrics patients Page 2 LK-MOH-205632-CW-RFQ Pending Component 1: Emergency Request for Single Stage - One 194,594.0 2020-12- 2021-02- 2021- / Renovation and IDA / 65950 Post Limited 0.00 Implemen COVID-19 Response Quotations Envelope 0 12 06 08-05 modification to ICU in TH tation Anuradhapuara LK-MOH-192346-CW-RFQ / Renovation and Pending refurbishment of psychiatry Component 1: Emergency Request for Single Stage - One 2020-12- 2021-01- 2021- TF / B3017 Post Limited 94,366.00 0.00 Implemen unit at Teaching Hospital COVID-19 Response Quotations Envelope 05 16 02-15 tation Ragama under Covid Project by College of psychiatry. LK-MOH-207181-CW-RFQ / Renovation and Pending modification to ICU and Component 1: Emergency Request for Single Stage - One 2020-12- 2021-01- 2021- IDA / 65950 Post Limited 48,649.00 0.00 Implemen HDU facilities for COVID-19 Response Quotations Envelope 19 30 03-01 tation accommodating covid positive patients at Marawila BH-aluminum works LK-MOH-207186-CW-RFQ / Essential renovations to Pending Component 1: Emergency Request for Single Stage - One 2020-12- 2021-01- 2021- provide staff quarantine and IDA / 65950 Post Limited 43,243.00 0.00 Implemen COVID-19 Response Quotations Envelope 19 30 03-01 accommodation facilities at tation COVID19 treatment center LK-MOH-207192-CW-RFQ / Establishment of 6 bedded Pending Component 1: Emergency Request for Single Stage - One 2020-12- 2021-01- 2021- HDU facilities for IDA / 65950 Post Limited 16,216.00 0.00 Implemen COVID-19 Response Quotations Envelope 19 30 03-01 complicated COVID 19 tation patients for DH Pinbura LK-MOH-207200-CW-RFQ / Modifications required for Pending ward no.3, 10, 05, 01 and Component 1: Emergency Request for Single Stage - One 2020-12- 2021-01- 2021- IDA / 65950 Post Limited 16,216.00 0.00 Implemen psychiatric ward at BH COVID-19 Response Quotations Envelope 19 30 03-01 tation homagama to provide multi disciplinary care for Covid 19 LK-MOH-207201-CW-RFQ / Modifications required for Pending ward no.8 and 5 to Component 1: Emergency Request for Single Stage - One 2020-12- 2021-01- 2021- IDA / 65950 Post Limited 54,054.00 0.00 Implemen accommodate covid+ COVID-19 Response Quotations Envelope 19 30 03-01 tation maternal and child patients at Kandana BH LK-MOH-207205-CW-RFQ Pending / Renovations of wards 02 Component 1: Emergency Request for Single Stage - One 2020-12- 2021-01- 2021- IDA / 65950 Post Limited 21,622.00 0.00 Implemen and 03 as COVID Unit at COVID-19 Response Quotations Envelope 19 30 03-01 tation Maldeniya BH LK-MOH-207206-CW-RFQ / Extension of ward 17 to Pending accommodate ICU and HDU Component 1: Emergency Request for Single Stage - One 2020-12- 2021-01- 2021- IDA / 65950 Post Limited 43,243.00 0.00 Implemen facilities for Covid 19 COVID-19 Response Quotations Envelope 19 30 03-01 tation patients at Peradeniya Teaching Hospital in Kandy District LK-MOH-207207-CW-RFQ / Renovation and Pending Component 1: Emergency Request for Single Stage - One 2020-12- 2021-01- 2021- modification of wards for IDA / 65950 Post Limited 16,216.00 0.00 Implemen COVID-19 Response Quotations Envelope 19 30 03-01 accommodating covid tation positive patients at DH Gangodagama LK-MOH-207208-CW-RFQ / Setting up a removable Pending Component 1: Emergency Request for Single Stage - One 2020-12- 2021-01- 2021- safety fence at intermediate IDA / 65950 Post Limited 10,811.00 0.00 Implemen COVID-19 Response Quotations Envelope 19 30 03-01 COVID care center at Nilwala tation college of education LK-MOH-207428-CW-RFQ Pending / Modifications at DH Component 1: Emergency Request for Single Stage - One 2020-12- 2021-02- 2021- IDA / 65950 Post Limited 10,811.00 0.00 Implemen Athurugiriya to provide COVID-19 Response Quotations Envelope 26 06 03-08 tation elderly patient care LK-MOH-207618-CW-RFQ Pending / Civil works for further Component 1: Emergency Request for Single Stage - One 2020-12- 2021-01- 2021- IDA / 65950 Post Limited 29,730.00 0.00 Implemen essential improvement at COVID-19 Response Quotations Envelope 27 31 03-02 tation IDH Kilinochchi LK-MOH-207633-CW-RFQ Pending / Improvement work to Component 1: Emergency Request for Single Stage - One 2020-12- 2021-01- 2021- IDA / 65950 Post Limited 10,270.00 0.00 Implemen External Water Supply and COVID-19 Response Quotations Envelope 27 31 03-02 tation Director Office at IDH Kilinochchi LK-MOH-203960-CW-RFQ Pending / Modification to ward Component 1: Emergency Request for 189,189.0 2020-12- 2021-02- 2021- IDA / 65950 Post 0.00 Implemen building to accommodate COVID-19 Response Quotations 0 23 17 08-16 tation Covid patient of Maskeliya Hospital LK-MOH-210690-CW-RFB Pending Component 1: Emergency Single Stage - One 340,541.0 2021-01- 2021-01- 2021-03- 2021-04- 2021-05- 2021- / Construction of 8 bedded IDA / 65950 Post Request for Bids Open - National 0.00 Implemen COVID-19 Response Envelope 0 20 25 08 07 12 11-08 ICU unit at BH Balangoda tation LK-MOH-210698-CW-RFQ / Establishment of 4 bedded Pending Component 1: Emergency Request for Single Stage - One 2021-01- 2021-03- 2021- HDU facilities for IDA / 65950 Post Limited 75,646.00 0.00 Implemen COVID-19 Response Quotations Envelope 04 01 08-28 complicated covid 19 tation patients treatment unit at BH Eheliyagoda LK-MOH-210704-CW-RFQ / Modifying a ward for quarantining in isolation of Pending disabled patients who are Component 1: Emergency Request for Single Stage - One 2021-01- 2021-03- 2021- IDA / 65950 Post Limited 27,027.00 0.00 Implemen arriving from abroad at COVID-19 Response Quotations Envelope 09 06 09-02 tation Rheumatology and Rehabilitation Hospital Ragama LK-MOH-210708-CW-RFQ / Converting ward 05 for covid + psychiatric patients Pending Component 1: Emergency Request for Single Stage - One 2021-01- 2021-03- 2021- and Converting kitchen IDA / 65950 Post Limited 41,625.00 0.00 Implemen COVID-19 Response Quotations Envelope 09 06 09-02 building to nurse station & tation construction of 3 unit toilet bocks at BH Pimbura LK-MOH-210712-CW-RFQ Pending / Establishment COVID-19 Component 1: Emergency Request for Single Stage - One 2021-01- 2021-03- 2021- IDA / 65950 Post Limited 32,432.00 0.00 Implemen treatment center at DH COVID-19 Response Quotations Envelope 09 06 09-02 tation Damana LK-MOH-210715-CW-RFQ Pending / Establishing level 2 Component 1: Emergency Request for Single Stage - One 2021-01- 2021-03- 2021- IDA / 65950 Post Limited 97,297.00 0.00 Implemen COVID19 treatment center COVID-19 Response Quotations Envelope 11 08 09-04 tation at DH Kuchchaveli LK-MOH-210716-CW-RFQ / Renovation and Pending Component 1: Emergency Request for Single Stage - One 108,108.0 2021-01- 2021-03- 2021- modification of wards for IDA / 65950 Post Limited 0.00 Implemen COVID-19 Response Quotations Envelope 0 11 08 09-04 accommodating COVID-19 tation positive patients DK Kallar LK-MOH-210718-CW-RFQ Pending Component 1: Emergency Request for Single Stage - One 2021-01- 2021-03- 2021- / Construction of waiting IDA / 65950 Post Limited 2,703.00 0.00 Implemen COVID-19 Response Quotations Envelope 12 09 09-05 area DH Padiyathalawa tation LK-MOH-210719-CW-RFQ Pending / Establishing Covid-19 Component 1: Emergency Request for Single Stage - One 2021-01- 2021-03- 2021- IDA / 65950 Post Limited 59,459.00 0.00 Implemen treatment center at DH COVID-19 Response Quotations Envelope 11 08 09-04 tation Murathamunai LK-MOH-193602-CW-RFQ / Renovation and Re- Pending Component 1: Emergency Request for Single Stage - One 178,378.0 2020-10- 2020-11- 2020- furbishment of Nursing TF / B3017 Post Limited 0.00 Implemen COVID-19 Response Quotations Envelope 0 13 24 12-24 Training School at tation Mulleriyawa under Covid Grant LK-MOH-212455-CW-RFQ / Renovation, modification and additions to existing Pending Mortuary to establish 15 Component 1: Emergency Request for Single Stage - One 2021-01- 2021-03- 2021- IDA / 65950 Post Limited 81,081.00 0.00 Implemen Unit Dialysis Center COVID-19 Response Quotations Envelope 25 22 09-18 tation including installation of RO plant and convertainer for storage purpose at DH Kandana. LK-MOH-212465-CW-DIR Pending / Increase the Height of the Component 1: Emergency 2021-01- 2021-01- 2021-03- 2021- IDA / 65950 Post Direct Selection Direct 10,811.00 0.00 Implemen incinerator Chimney at DGH COVID-19 Response 20 25 01 08-28 tation Negombo. LK-MOH-212471-CW-RFQ Pending Component 1: Emergency Request for Single Stage - One 2021-01- 2021-03- 2021- / Modification to Ward 4 to IDA / 65950 Post Limited 75,675.00 0.00 Implemen COVID-19 Response Quotations Envelope 24 21 09-17 establish a 4 bedded ICU tation LK-MOH-212617-CW-RFQ / Improvements on Pending Component 1: Emergency Request for Single Stage - One 2021-01- 2021-03- 2021- Respiratory ward and other IDA / 65950 Post Limited 18,000.00 0.00 Implemen COVID-19 Response Quotations Envelope 25 22 09-18 additional units and Safety tation Improvement on Radiology Department LK-MOH-212618-CW-RFQ Pending / Improving the ventilation Component 1: Emergency Request for Single Stage - One 2021-01- 2021-03- 2021- IDA / 65950 Post Limited 7,417.00 0.00 Implemen facility in the PCU theater COVID-19 Response Quotations Envelope 25 22 09-18 tation and ICU ventilation system LK-MOH-212628-CW-RFQ / Supply, Intallation and Pending Component 1: Emergency Request for Single Stage - One 2021-01- 2021-03- 2021- Commissioning of Air IDA / 65950 Post Limited 27,027.00 0.00 Implemen COVID-19 Response Quotations Envelope 25 22 09-18 Conditioning System at Base tation Hospital Kamburugamuwa LK-MOH-215727-CW-RFB Pending / Improviement of exsisting Component 1: Emergency Single Stage - One 162,162.0 2021-01- 2021-02- 2021-03- 2021-04- 2021-05- 2021- IDA / 65950 Post Request for Bids Open - National 0.00 Implemen operation teater to covid COVID-19 Response Envelope 0 31 05 19 18 23 11-19 tation treatment Center LK-MOH-215748-CW-RFQ / Constuction of Water Pending Reservoir at the Natural Component 1: Emergency Request for Single Stage - One 2021-02- 2021-04- 2021- IDA / 65950 Post Limited 27,030.00 0.00 Implemen Water Source, laying pipes COVID-19 Response Quotations Envelope 05 02 09-29 tation and construction of Overhead tank at Endana Divisional hospital. LK-MOH-212445-CW-RFQ / Installation of Negative pressure system, Hepa Pending Filters and UV lights with Component 1: Emergency Request for Single Stage - One 135,135.0 2021-04- 2021-06- 2021- IDA / 65950 Post Limited 0.00 Implemen necessary improvements COVID-19 Response Quotations Envelope 0 10 05 12-02 tation and modifications to the infra structure to the existing Ward No 28 LK-MOH-224044-CW-RFB / Establishment of 10 Pending Component 1: Emergency Single Stage - One 237,000.0 2021-04- 2021-04- 2021-06- 2021-07- 2021-08- 2022- bedded ICU in COVID 19 IDA / 65950 Post Request for Bids Open - National 0.00 Implemen COVID-19 Response Envelope 0 20 25 06 06 10 02-06 level 2 treatment center at tation BH Warakapola LK-MOH-224240-CW-RFQ Pending / Urgent modifications Component 1: Emergency Request for Single Stage - One 2021-04- 2021-06- 2021- IDA / 65950 Post Limited 5,300.00 0.00 Implemen required at medical ward to COVID-19 Response Quotations Envelope 13 08 12-05 tation accomodate 3 HDU beds LK-MOH-224243-CW-RFQ / Modification required for Pending Component 1: Emergency Request for Single Stage - One 2021-04- 2021-06- 2021- partitioning of ward 13& 15 IDA / 65950 Post Limited 26,400.00 0.00 Implemen COVID-19 Response Quotations Envelope 25 20 12-17 to accommodate psychiatry tation patients in siolation LK-MOH-224248-CW-RFQ Pending / conversion of general ICU Component 1: Emergency Request for Single Stage - One 2021-04- 2021-06- 2021- IDA / 65950 Post Limited 26,400.00 0.00 Implemen in to a 8 bedded covid COVID-19 Response Quotations Envelope 26 21 12-18 tation treatment ICU LK-MOH-224660-CW-RFB / Renovation and modifications to the Pending Component 1: Emergency Single Stage - One 1,160,000. 2021-04- 2021-04- 2021-06- 2021-07- 2021-08- 2022- existing buildings of District IDA / 65950 Post Request for Bids Open - National 0.00 Implemen COVID-19 Response Envelope 00 15 20 01 01 05 02-01 General Hospital tation Hambanthota to convert into an infectious disease hospital including a laboratory. LK-MOH-224253-CW-RFQ / Essential modifications to Pending Component 1: Emergency Request for Single Stage - One 131,600.0 2021-05- 2021-06- 2021- convert exsisting motuary IDA / 65950 Post Limited 0.00 Implemen COVID-19 Response Quotations Envelope 0 02 27 12-24 into dialasys center for tation covid + patients LK-MOH-224239-CW-RFQ / Establishemnt of HDU for Component 1: Emergency Request for Single Stage - One 2021-04- 2021-06- 2021- moderate sysptoms & ICU IDA / 65950 Post Limited 15,800.00 0.00 Canceled COVID-19 Response Quotations Envelope 13 08 12-05 step down patients - methsiri sewana Request for LK-MOH-231792-CW-RFQ Quotations - Pending / Renovation of Audeo Component 1: Emergency Request for Single Stage - One Small Works 2021-05- 2021-07- 2022- IDA / 65950 Post Limited 12,100.00 0.00 Implemen Visual Stoodeo and COVID-19 Response Quotations Envelope (Emergency) 25 20 01-16 tation Edidditing Room at Health SPD - Promotion Bureau Competitive LK-MOH-232321-CW-RFQ Request for / Construction of a patient Quotations - wash room to Ward No 21 Pending Component 1: Emergency Request for Single Stage - One Small Works 2021-05- 2021-07- 2022- of Apeksha Hospital IDA / 65950 Post Limited 9,000.00 0.00 Implemen COVID-19 Response Quotations Envelope (Emergency) 17 12 01-08 (Cancer) to manage Covid tation SPD - positive Cancer patients and Competitive Covid doubt full Cancer patients LK-MOH-212447-CW-RFB Request for Bids Pending / Extension to medical Ward Component 1: Emergency Single Stage - One - Small Works 1,270,000. 2021-03- 2021-03- 2021-04- 2021-05- 2021-06- 2021- IDA / 65950 Post Request for Bids Open - National 0.00 Implemen for establishment of ten COVID-19 Response Envelope SPD (1 envelope 00 02 07 18 18 22 12-19 tation Bedded ICU at TH process) Rathnapura. Request for LK-MOH-236971-CW-RFQ Quotations - Pending Component 1: Emergency Request for Single Stage - One 2021-07- 2021-08- 2022- / Renovation of Office Room IDA / 65950 Post Limited Small Works 4,150.00 0.00 Implemen COVID-19 Response Quotations Envelope 03 28 02-24 and Toilet (Emergency) tation SPD - Competitive GOODS Activity Reference No. Estimated Actual Draft Pre- Draft Bidding Specific Proposal Bid Evaluation Loan / Credit Market Procurement Prequalificati Process Prequalification Bidding Documents Contract / Description Component Review Type Method Amount Amount qualification Document / Procurement Notice Submission / Report and Signed Contract No. Approach Process on (Y/N) Status Evaluation Report as Issued Completion (US$) (US$) Documents Justification / Invitation Opening / Minutes Recommendation Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned for Award Actual Planned Actual Planned Actual LK-MOH-171730-GO-RFQ Pending Component 1: Emergency Request for Single Stage - One 2020-05- 2020-07- 2020-07- / Supplying of Hardware IBRD / 90850 Post Limited 11,033.00 0.00 Implement COVID-19 Response Quotations Envelope 13 01 15 Items ation LK-MOH-171737-GO-RFQ Pending Component 1: Emergency Request for Single Stage - One 2020-06- 2020-07- 2020-08- / Supplying and Installation IBRD / 90850 Post Limited 11,579.00 0.00 Implement COVID-19 Response Quotations Envelope 02 28 11 of Air Conditioning ation Machines LK-MOH-171735-GO-DIR Pending / Supplying of Aluminum Component 1: Emergency Request for Single Stage - One 2020-05- 2020-07- 2020-07- IDA / 65950 Post Limited 8,158.00 0.00 Implement Items for Refurbishment of COVID-19 Response Quotations Envelope 25 13 27 ation an ICU at Gampaha DGH LK-MOH-171734-GO-DIR / Supplying of Tiles and Pending Component 1: Emergency Request for Single Stage - One 2020-05- 2020-07- 2020-07- Sanitary Fittings or Required IDA / 65950 Post Limited 12,105.00 0.00 Implement COVID-19 Response Quotations Envelope 26 14 28 for Refurbishment of an ICU ation at Gampaha DGH LK-MOH-172529-GO-DIR / SUPPLY REAGENT FOR BS Pending Component 1: Emergency 2020-05- 2020-05- 2020-06- 2020-06- 800 BIOCHEMISTRY IDA / 65950 Post Direct Selection Direct 52,632.00 0.00 Implement COVID-19 Response 07 12 02 17 ANALYZER for Kandy ation Teaching Hospital during Covid 19 period LK-MOH-172535-GO-DIR Pending / SUPPLY of PCR KIT Component 1: Emergency 2020-05- 2020-05- 2020-06- 2020-06- IDA / 65950 Post Direct Selection Direct 52,632.00 0.00 Implement required for Kandy Teaching COVID-19 Response 07 12 02 17 ation Hospital during Covid 19 period LK-MOH-172539-GO-RFQ Pending / 6500 Nos Goggles Component 1: Emergency Request for Single Stage - One 2020-05- 2020-06- 2020-07- IDA / 65950 Post Limited 34,655.00 0.00 Implement procured by MSD during COVID-19 Response Quotations Envelope 12 30 14 ation Covid 19 period LK-MOH-172541-GO-RFQ Pending / 9975 Nos N95 mask Component 1: Emergency Request for Single Stage - One 2020-05- 2020-06- 2020-07- IDA / 65950 Post Limited 21,053.00 0.00 Implement procured by MSD during COVID-19 Response Quotations Envelope 12 30 14 ation Covid 19 period LK-MOH-172542-GO-RFQ Pending / 10275 Nos Coverall Kits Component 1: Emergency Request for Single Stage - One 2020-05- 2020-06- 2020-07- IDA / 65950 Post Limited 63,503.00 0.00 Implement procured by MSD during COVID-19 Response Quotations Envelope 12 30 14 ation Covid 19 period LK-MOH-172543-GO-RFQ Pending Component 1: Emergency Request for Single Stage - One 2020-05- 2020-06- 2020-07- / 405 Nos Boots procured IDA / 65950 Post Limited 7,895.00 0.00 Implement COVID-19 Response Quotations Envelope 12 30 14 by MSD during Covid Period ation LK-MOH-172545-GO-DIR / 2500 Nos PERSONAL Pending Component 1: Emergency 2020-05- 2020-05- 2020-06- 2020-06- PROTECTIVE EQUIPMENT IDA / 65950 Post Direct Selection Direct 123,684.00 0.00 Implement COVID-19 Response 07 12 09 23 (PPE)SET procured by SPC ation during Covid 19 period LK-MOH-172546-GO-DIR / 5000 Nos PERSONAL Pending Component 1: Emergency 2020-05- 2020-05- 2020-06- 2020-06- PROTECTIVE EQUIPMENT IDA / 65950 Post Direct Selection Direct 244,737.00 0.00 Implement COVID-19 Response 07 12 09 23 (PPE)SET procured by SPC ation during Covid 19 period LK-MOH-172548-GO-DIR Pending Component 1: Emergency 2020-05- 2020-05- 2020-06- 2020-06- / 16 Nos. Diathermy IDA / 65950 Post Direct Selection Direct 100,979.00 0.00 Implement COVID-19 Response 07 12 02 17 procured by BME during ation Covid 19 period Page 3 LK-MOH-172549-GO-RFB Pending / 10 Nos. Multi Monitor Component 1: Emergency Single Stage - One 2020-05- 2020-05- 2020-05- 2020-05- 2020-06- 2020-07- IDA / 65950 Post Request for Bids Limited 8,000.00 0.00 Implement procured by BME during COVID-19 Response Envelope 07 12 14 28 25 09 ation Covid 19 period LK-MOH-172552-GO-RFB Pending / 50 Nos. Micro Component 1: Emergency Single Stage - One 2020-05- 2020-05- 2020-07- 2020-08- 2020-09- 2021-03- IDA / 65950 Post Request for Bids Open - National 20,941.00 0.00 Implement Microhaematocrit procured COVID-19 Response Envelope 26 31 12 11 15 14 ation by BME during Covid 19 period LK-MOH-172554-GO-RFQ / Mattress 50, Plastic Table 30, Plastic chair with arm Pending Component 1: Emergency Request for Single Stage - One 2020-05- 2020-06- 2020-07- 60, Plastic chair with out IDA / 65950 Post Limited 2,632.00 0.00 Implement COVID-19 Response Quotations Envelope 12 30 14 arm -60 procured by MoH ation Procurement Department during Covid 19 period LK-MOH-172556-GO-RFQ Pending / Hospital Beds 50 procured Component 1: Emergency Request for Single Stage - One 2020-05- 2020-06- 2020-07- IDA / 65950 Post Limited 7,895.00 0.00 Implement by MoH Procurement COVID-19 Response Quotations Envelope 12 30 14 ation Department during Covid 19 period LK-MOH-172557-GO-RFQ Pending / Bed Side Lockers 140 Component 1: Emergency Request for Single Stage - One 2020-05- 2020-06- 2020-07- IDA / 65950 Post Limited 12,632.00 0.00 Implement procured by MoH Supplies COVID-19 Response Quotations Envelope 12 30 14 ation Division during Covid period LK-MOH-172560-GO-RFQ / Mattress 50, Plastic Table 45, Plastic chair with arm Pending 60, Plastic chair with out Component 1: Emergency Request for Single Stage - One 2020-05- 2020-06- 2020-07- IDA / 65950 Post Limited 6,316.00 0.00 Implement arm -110 Water Dispenser COVID-19 Response Quotations Envelope 12 30 14 ation 30 procured by MoH Procurement Department during Covid 19 period LK-MOH-172564-GO-RFQ Pending / Mattress 50 procured by Component 1: Emergency Request for Single Stage - One 2020-05- 2020-06- 2020-07- IDA / 65950 Post Limited 1,053.00 0.00 Implement MoH Procurement COVID-19 Response Quotations Envelope 12 30 14 ation Department during Covid 19 period LK-MOH-172565-GO-RFQ Pending / Hospital Beds 25 procured Component 1: Emergency Request for Single Stage - One 2020-05- 2020-06- 2020-07- IDA / 65950 Post Limited 3,947.00 0.00 Implement by MoH Procurement COVID-19 Response Quotations Envelope 12 30 14 ation Department during Covid 19 period LK-MOH-172566-GO-RFQ / Porcelain Plates Porcelain Pending Component 1: Emergency Request for Single Stage - One 2020-05- 2020-06- 2020-07- Cup & Sauces procured by IDA / 65950 Post Limited 300.00 0.00 Implement COVID-19 Response Quotations Envelope 12 30 14 MoH Procurement ation Department during Covid 19 period LK-MOH-172680-GO-RFQ / Mosquito Nets 6' x Pending Component 1: Emergency Request for Single Stage - One 2020-05- 2020-06- 2020-07- 4'(Round) procured by MoH IDA / 65950 Post Limited 138.00 0.00 Implement COVID-19 Response Quotations Envelope 12 30 14 Procurement Department ation during Covid 19 period LK-MOH-172681-GO-RFQ / Bed Sheets ,Pillows,Pillow Pending Component 1: Emergency Request for Single Stage - One 2020-05- 2020-06- 2020-07- Cases procured by MoH IDA / 65950 Post Limited 1,022.00 0.00 Implement COVID-19 Response Quotations Envelope 12 30 14 Procurement Department ation during Covid 19 period LK-MOH-172682-GO-RFQ / Porcelain Plates Porcelain Pending Component 1: Emergency Request for Single Stage - One 2020-05- 2020-07- 2020-07- Cup & Sauces procured by IDA / 65950 Post Limited 480.00 0.00 Implement COVID-19 Response Quotations Envelope 13 01 15 MoH Procurement ation Department during Covid 19 period LK-MOH-172683-GO-RFQ / Mosquito Nets 6' x Pending Component 1: Emergency Request for Single Stage - One 2020-05- 2020-07- 2020-07- 4'(Round) procured by MoH IDA / 65950 Post Limited 276.00 0.00 Implement COVID-19 Response Quotations Envelope 13 01 15 Procurement Department ation during Covid 19 period LK-MOH-172684-GO-RFQ / Bed Sheets , Pending Component 1: Emergency Request for Single Stage - One 2020-05- 2020-07- 2020-07- Pillows,Pillows Cases IDA / 65950 Post Limited 1,566.00 0.00 Implement COVID-19 Response Quotations Envelope 13 01 15 procured by MoH ation Procurement Department during Covid 19 period LK-MOH-172686-GO-RFQ / Purchasing polythene for Pending Component 1: Emergency Request for Single Stage - One 2020-05- 2020-06- 2020-07- the PPE kits procured by IDA / 65950 Post Limited 5,263.00 0.00 Implement COVID-19 Response Quotations Envelope 13 24 01 MoH Development unit ation during Covid 19 period LK-MOH-172688-GO-RFQ / Iron Bed – (Double bunker Bed) 10 Unit (Preparation of Pending Component 1: Emergency Request for Single Stage - One 2020-05- 2020-07- 2020-07- Doctors quarters to face IDA / 65950 Post Limited 574.00 0.00 Implement COVID-19 Response Quotations Envelope 13 01 15 COVID 19 Pandemic) ation procured by Kalubowila Hospital during Covid 19 period LK-MOH-172689-GO-RFQ / Double Layer form mattress 20 unit Pending Component 1: Emergency Request for Single Stage - One 2020-05- 2020-07- 2020-07- (Preparation of Doctors IDA / 65950 Post Limited 621.00 0.00 Implement COVID-19 Response Quotations Envelope 13 01 15 quarters to face COVID 19 ation Pandemic) procured by Kalubowila Hospital during Covid 19 period LK-MOH-172690-GO-RFQ / Double Layer form mattress 20 unit Pending Component 1: Emergency Request for Single Stage - One 2020-05- 2020-07- 2020-07- (Preparation of Doctors IDA / 65950 Post Limited 621.00 0.00 Implement COVID-19 Response Quotations Envelope 13 01 15 quarters to face COVID 19 ation Pandemic) procured by Kalubowila Hospital during Covid 19 period LK-MOH-172691-GO-RFQ / Wooden Table 3’ x 2’ Teak 8 unit (Preparation of Pending Component 1: Emergency Request for Single Stage - One 2020-05- 2020-07- 2020-07- Doctors quarters to face IDA / 65950 Post Limited 905.00 0.00 Implement COVID-19 Response Quotations Envelope 13 01 15 COVID 19 Pandemic) ation procured by Kalubowila Hospital during Covid 19 period LK-MOH-172692-GO-RFQ / MDF Wooden Table 4’ x 2’ Unit 2 (Preparation of Pending Component 1: Emergency Request for Single Stage - One 2020-05- 2020-07- 2020-07- Doctors quarters to face IDA / 65950 Post Limited 157.00 0.00 Implement COVID-19 Response Quotations Envelope 13 01 15 COVID 19 Pandemic) ation procured by Kalubowila Hospital during Covid 19 period LK-MOH-172693-GO-RFQ / Computer Chairs with arm Unit 10 (Preparation of Pending Component 1: Emergency Request for Single Stage - One 2020-05- 2020-07- 2020-07- Doctors quarters to face IDA / 65950 Post Limited 458.00 0.00 Implement COVID-19 Response Quotations Envelope 13 01 15 COVID 19 Pandemic) ation procured by Kalubowila Hospital during Covid 19 period LK-MOH-172694-GO-RFQ / Plastic Chairs (without arm) Unit 100 (Preparation Pending Component 1: Emergency Request for Single Stage - One 2020-05- 2020-07- 2020-07- of Doctors quarters to face IDA / 65950 Post Limited 464.00 0.00 Implement COVID-19 Response Quotations Envelope 13 01 15 COVID 19 Pandemic) ation procured by Kalubowila Hospital during Covid 19 period LK-MOH-172695-GO-RFQ / Plastic Paddle bin 18 L - Unit 10 (Preparation of Pending Component 1: Emergency Request for Single Stage - One 2020-05- 2020-07- 2020-07- Doctors quarters to face IDA / 65950 Post Limited 145.00 0.00 Implement COVID-19 Response Quotations Envelope 13 01 15 COVID 19 Pandemic) ation procured by Kalubowila Hospital during Covid 19 period LK-MOH-172696-GO-RFQ / Plastic Paddle Bin with wheel – 70L -2 unit Pending Component 1: Emergency Request for Single Stage - One 2020-05- 2020-07- 2020-07- (Preparation of Doctors IDA / 65950 Post Limited 73.00 0.00 Implement COVID-19 Response Quotations Envelope 13 01 15 quarters to face COVID 19 ation Pandemic) procured by Kalubowila Hospital during Covid 19 period LK-MOH-172697-GO-RFQ / Plastic Bucket – 45L - Unit 10 (Preparation of Doctors Pending Component 1: Emergency Request for Single Stage - One 2020-05- 2020-07- 2020-07- quarters to face COVID 19 IDA / 65950 Post Limited 103.00 0.00 Implement COVID-19 Response Quotations Envelope 13 01 15 Pandemic) procured by ation Kalubowila Hospital during Covid 19 period LK-MOH-172699-GO-RFQ / Basin – (Plastic) – 25 L - unit 10 (Preparation of Pending Component 1: Emergency Request for Single Stage - One 2020-05- 2020-07- 2020-07- Doctors quarters to face IDA / 65950 Post Limited 23.00 0.00 Implement COVID-19 Response Quotations Envelope 13 01 15 COVID 19 Pandemic) ation procured by Kalubowila Hospital during Covid 19 period LK-MOH-172700-GO-RFQ / Paddle bin – 40L - 3 Unit (Preparation of Doctors Pending Component 1: Emergency Request for Single Stage - One 2020-05- 2020-07- 2020-07- quarters to face COVID 19 IDA / 65950 Post Limited 69.00 0.00 Implement COVID-19 Response Quotations Envelope 13 01 15 Pandemic) procured by ation Kalubowila Hospital during Covid 19 period LK-MOH-172701-GO-RFQ / Paddle bin – 10L 10 unit (Preparation of Doctors Pending Component 1: Emergency Request for Single Stage - One 2020-05- 2020-07- 2020-07- quarters to face COVID 19 IDA / 65950 Post Limited 63.00 0.00 Implement COVID-19 Response Quotations Envelope 13 01 15 Pandemic) procured by ation Kalubowila Hospital during Covid 19 period LK-MOH-172702-GO-RFQ / Googles – Normal 300 Unit (Opening Up New Pending Component 1: Emergency Request for Single Stage - One 2020-05- 2020-07- 2020-07- Isolation Unit For COVID 19 IDA / 65950 Post Limited 624.00 0.00 Implement COVID-19 Response Quotations Envelope 13 01 15 Suspected patients procured ation by Kalubowila Hospital during Covid 19 period LK-MOH-172703-GO-RFQ / Googles – No ; 01 100 Unit (Opening Up New Pending Component 1: Emergency Request for Single Stage - One 2020-05- 2020-07- 2020-07- Isolation Unit For COVID 19 IDA / 65950 Post Limited 471.00 0.00 Implement COVID-19 Response Quotations Envelope 13 01 15 Suspected patients) ation procured by Kalubowila Hospital during Covid 19 period LK-MOH-172705-GO-RFQ / Washing Machine – 100% Drier – 8Kg 01 Unit Pending (Opening Up New Isolation Component 1: Emergency Request for Single Stage - One 2020-05- 2020-07- 2020-07- IDA / 65950 Post Limited 753.00 0.00 Implement Unit For COVID 19 COVID-19 Response Quotations Envelope 13 01 15 ation Suspected patients) procured by Kalubowila Hospital during Covid 19 period LK-MOH-172706-GO-RFQ / Wall Fan - 3 unit (Opening Up New Isolation Pending Component 1: Emergency Request for Single Stage - One 2020-05- 2020-07- 2020-07- Unit For COVID 19 IDA / 65950 Post Limited 261.00 0.00 Implement COVID-19 Response Quotations Envelope 13 01 15 Suspected patients) ation procured by Kalubowila Hospital during Covid 19 period LK-MOH-172707-GO-RFQ / Wall Fan 3 Unit (Opening Up New Isolation Unit For Pending Component 1: Emergency Request for Single Stage - One 2020-05- 2020-07- 2020-07- COVID 19 Suspected IDA / 65950 Post Limited 221.00 0.00 Implement COVID-19 Response Quotations Envelope 13 01 15 patients) procured by ation Kalubowila Hospital during Covid 19 period LK-MOH-172708-GO-RFQ / Ex house Fan (12x12) 1 unit (Opening Up New Pending Component 1: Emergency Request for Single Stage - One 2020-05- 2020-07- 2020-07- Isolation Unit For COVID 19 IDA / 65950 Post Limited 50.00 0.00 Implement COVID-19 Response Quotations Envelope 13 01 15 Suspected patients) ation procured by Kalubowila Hospital during Covid 19 period LK-MOH-172709-GO-RFQ / Washing machine – (8Kg) 2 Unit (Opening Up New Pending Component 1: Emergency Request for Single Stage - One 2020-05- 2020-07- 2020-07- Isolation Unit For COVID 19 IDA / 65950 Post Limited 832.00 0.00 Implement COVID-19 Response Quotations Envelope 13 01 15 Suspected patients) ation procured by Kalubowila Hospital during Covid 19 period LK-MOH-172710-GO-RFQ / Fabric – Tapata materials – 60” 1000m (Accessories Pending Component 1: Emergency Request for Single Stage - One 2020-05- 2020-07- 2020-07- for Personal Protection Kit) IDA / 65950 Post Limited 763.00 0.00 Implement COVID-19 Response Quotations Envelope 13 01 15 procured by Kalubowila ation Hospital during Covid 19 period LK-MOH-172711-GO-RFQ / Fabric – Mask Materials – 60” 76 m (Accessories for Pending Component 1: Emergency Request for Single Stage - One 2020-05- 2020-07- 2020-07- Personal Protection Kit) IDA / 65950 Post Limited 36.00 0.00 Implement COVID-19 Response Quotations Envelope 13 01 15 procured by Kalubowila ation Hospital during Covid 19 period LK-MOH-172712-GO-RFQ / Elastic – ¾” (100m) Roll 9 Pending (Accessories for Personal Component 1: Emergency Request for Single Stage - One 2020-05- 2020-07- 2020-07- IDA / 65950 Post Limited 92.00 0.00 Implement Protection Kit) procured by COVID-19 Response Quotations Envelope 13 01 15 ation Kalubowila Hospital during Covid 19 period LK-MOH-172713-GO-RFQ / Personal Protecting Pending overall 200 Unit ( for Component 1: Emergency Request for Single Stage - One 2020-05- 2020-07- 2020-07- IDA / 65950 Post Limited 621.00 0.00 Implement Isolation Unit) procured by COVID-19 Response Quotations Envelope 13 01 15 ation Kalubowila Hospital during Covid 19 period LK-MOH-172714-GO-RFQ / Bed Sheet 90"x54" 500 Pending Numbers ( for Isolation Unit) Component 1: Emergency Request for Single Stage - One 2020-05- 2020-07- 2020-07- IDA / 65950 Post Limited 1,303.00 0.00 Implement procured by Kalubowila COVID-19 Response Quotations Envelope 13 01 15 ation Hospital during Covid 19 period LK-MOH-172715-GO-RFQ / Sanitary gel – 250 ml 25 bottle (For COVID 19 Pending Component 1: Emergency Request for Single Stage - One 2020-05- 2020-07- 2020-07- Suspected Patient's Isolation IDA / 65950 Post Limited 86.00 0.00 Implement COVID-19 Response Quotations Envelope 13 01 15 Unit) procured by ation Kalubowila Hospital during Covid 19 period LK-MOH-172716-GO-RFQ / Plastic Cup 500 unit (For Pending COVID 19 Suspected Component 1: Emergency Request for Single Stage - One 2020-05- 2020-07- 2020-07- IDA / 65950 Post Limited 13.00 0.00 Implement Patient's Isolation Unit) COVID-19 Response Quotations Envelope 13 01 15 ation procured by Kalubowila Hospital during Covid 19 period LK-MOH-172717-GO-RFQ / Plastic Spoon 500 unit (For Pending COVID 19 Suspected Component 1: Emergency Request for Single Stage - One 2020-05- 2020-07- 2020-07- IDA / 65950 Post Limited 16.00 0.00 Implement Patient's Isolation Unit) COVID-19 Response Quotations Envelope 13 01 15 ation procured by Kalubowila Hospital during Covid 19 period LK-MOH-172718-GO-RFQ / Paper Serviette 50 pkt (For Pending COVID 19 Suspected Component 1: Emergency Request for Single Stage - One 2020-05- 2020-07- 2020-07- IBRD / 90850 Post Limited 31.00 0.00 Implement Patient's Isolation Unit) COVID-19 Response Quotations Envelope 13 01 15 ation procured by Kalubowila Hospital during Covid 19 period LK-MOH-172719-GO-RFQ / Hand Wash 5L Can 100 nos (For COVID 19 Pending Component 1: Emergency Request for Single Stage - One 2020-05- 2020-07- 2020-07- Suspected Patient's Isolation IDA / 65950 Post Limited 3,289.00 0.00 Implement COVID-19 Response Quotations Envelope 13 01 15 Unit) procured by ation Kalubowila Hospital during Covid 19 period LK-MOH-172720-GO-RFQ / 3 Feet Polythene 163.35 m (For COVID 19 Suspected Pending Component 1: Emergency Request for Single Stage - One 2020-05- 2020-06- 2020-07- Patient's Isolation Unit) IDA / 65950 Post Limited 758.00 0.00 Implement COVID-19 Response Quotations Envelope 13 24 01 procured by Kalubowila ation Hospital during Covid 19 period LK-MOH-172721-GO-RFQ / Washing Powder – Surf excel 50Kg (For COVID 19 Pending Component 1: Emergency Request for Single Stage - One 2020-05- 2020-06- 2020-07- Suspected Patient's Isolation IDA / 65950 Post Limited 87.00 0.00 Implement COVID-19 Response Quotations Envelope 13 24 01 Unit) procured by ation Kalubowila Hospital during Covid 19 period LK-MOH-172722-GO-RFQ / Hand wash 5 L can (For Pending COVID 19 Suspected Component 1: Emergency Request for Single Stage - One 2020-05- 2020-07- 2020-07- IDA / 65950 Post Limited 579.00 0.00 Implement Patient's Isolation Unit) COVID-19 Response Quotations Envelope 13 01 15 ation procured by Kalubowila Hospital during Covid 19 period LK-MOH-172723-GO-RFQ / Washing Powder 100 Kg Pending (For COVID 19 Suspected Component 1: Emergency Request for Single Stage - One 2020-05- 2020-06- 2020-07- IDA / 65950 Post Limited 116.00 0.00 Implement Patient's Isolation Unit) COVID-19 Response Quotations Envelope 13 24 01 ation procured by Kalubowila Hospital during Covid 19 period Page 4 LK-MOH-172724-GO-RFQ / Grocery Bag (10x7) 15000 nos (For COVID 19 Pending Component 1: Emergency Request for Single Stage - One 2020-05- 2020-06- 2020-07- Suspected Patient's Isolation IDA / 65950 Post Limited 62.00 0.00 Implement COVID-19 Response Quotations Envelope 13 24 01 Unit) procured by ation Kalubowila Hospital during Covid 19 period LK-MOH-172725-GO-RFQ / Shopping bag (18 x 4x14) 15000 nos (For COVID 19 Pending Component 1: Emergency Request for Single Stage - One 2020-05- 2020-06- 2020-07- Suspected Patient's Isolation IDA / 65950 Post Limited 99.00 0.00 Implement COVID-19 Response Quotations Envelope 13 24 01 Unit) procured by ation Kalubowila Hospital during Covid 19 period LK-MOH-172726-GO-RFQ / Lunch Sheet 2500 nos (For Pending COVID 19 Suspected Component 1: Emergency Request for Single Stage - One 2020-05- 2020-06- 2020-07- IDA / 65950 Post Limited 34.00 0.00 Implement Patient's Isolation Unit) COVID-19 Response Quotations Envelope 13 24 01 ation procured by Kalubowila Hospital during Covid 19 period LK-MOH-172727-GO-RFQ / Card board lunch box 500nos (For COVID 19 Pending Component 1: Emergency Request for Single Stage - One 2020-05- 2020-06- 2020-07- Suspected Patient's Isolation IDA / 65950 Post Limited 45.00 0.00 Implement COVID-19 Response Quotations Envelope 13 24 01 Unit) procured by ation Kalubowila Hospital during Covid 19 period LK-MOH-172728-GO-RFQ / AA Battery 5000 nos (For Pending COVID 19 Suspected Component 1: Emergency Request for Single Stage - One 2020-05- 2020-06- 2020-07- IDA / 65950 Post Limited 1,193.00 0.00 Implement Patient's Isolation Unit) COVID-19 Response Quotations Envelope 13 24 01 ation procured by Kalubowila Hospital during Covid 19 period LK-MOH-172729-GO-RFQ / Adult Diapers XL 10’s 50 nos (For COVID 19 Pending Component 1: Emergency Request for Single Stage - One 2020-05- 2020-06- 2020-07- Suspected Patient's Isolation IDA / 65950 Post Limited 46.00 0.00 Implement COVID-19 Response Quotations Envelope 13 24 01 Unit) procured by ation Kalubowila Hospital during Covid 19 period LK-MOH-172730-GO-RFQ / Plastic Bin Heavy Duty 120L 3 nos (For COVID 19 Pending Component 1: Emergency Request for Single Stage - One 2020-05- 2020-07- 2020-07- Suspected Patient's Isolation IDA / 65950 Post Limited 78.00 0.00 Implement COVID-19 Response Quotations Envelope 13 01 15 Unit) procured by ation Kalubowila Hospital during Covid 19 period LK-MOH-174708-GO-UN / Procurement of COVID-19 Component 1: Emergency UN Agencies 2020-05- 2020-03- 2020-05- 2020-04- 2020-06- 2020-05- 2020-12- related Surgical/Medical IDA / 65950 Post Direct 35,240,003.58 35,240,003.58 Signed COVID-19 Response (Direct) 21 30 26 03 30 26 27 Consumables and PPE through UNICEF LK-MOH-176190-GO-RFB Component 1: Emergency Single Stage - One 2020-06- 2020-06- 2020-06- 2020-06- 2020-06- 2020-07- 2020-07- 2020-07- 2020-08- 2020-08- / Supply and Delivery of 25 IDA / 65950 Post Request for Bids Open - National 1,500,000.00 1,217,431.77 Signed COVID-19 Response Envelope 02 01 03 17 17 01 15 29 26 28 Nos Brand New Double Cabs LK-MOH-171620-GO-RFB Component 1: Emergency Single Stage - One 2020-05- 2020-05- 2020-06- 2020-07- 2020-08- 2021-02- / Supply and Delivery of 25 IBRD / 90850 Post Request for Bids Limited 1,500,000.00 0.00 Canceled COVID-19 Response Envelope 14 19 18 18 22 18 Nos Brand New Double Cabs LK-MOH-176195-GO-RFB Component 1: Emergency Single Stage - One 2020-06- 2020-06- 2020-06- 2020-06- 2020-07- 2020-07- 2020-07- 2020-08- 2020-08- 2020-08- / Supply And Delivery of IDA / 65950 Post Request for Bids Open - National 1,300,000.00 1,286,529.24 Signed COVID-19 Response Envelope 08 26 09 23 14 08 23 05 26 20 805 Nos Brand New Motor Bicycles LK-MOH-171742-GO-RFB Component 1: Emergency Single Stage - One 2020-05- 2020-06- 2020-07- 2020-07- 2020-09- 2021-03- / Supply And Delivery of IBRD / 90850 Post Request for Bids Limited 1,300,000.00 0.00 Canceled COVID-19 Response Envelope 27 01 01 31 04 03 805 Nos Brand New Motor Bicycles LK-MOH-176198-GO-RFB Under Component 1: Emergency Open - Single Stage - One 2020-06- 2021-02- 2020-06- 2021-04- 2020-08- 2020-09- 2020-10- 2020-11- / Supply and Delivery of IDA / 65950 Post Request for Bids 2,800,000.00 0.00 Implement COVID-19 Response International Envelope 24 12 29 05 10 09 14 28 2087 Nos Brand New ation Scooters LK-MOH-171743-GO-RFB Component 1: Emergency Single Stage - One 2020-06- 2020-06- 2020-07- 2020-08- 2020-09- 2021-03- / Supply and Delivery of IBRD / 90850 Post Request for Bids Limited 2,800,000.00 0.00 Canceled COVID-19 Response Envelope 10 15 15 14 18 17 2087 Nos Brand New Scooters LK-MOH-181002-GO-RFQ Pending / Disposable Face Marks Component 1: Emergency Request for Single Stage - One 2020-06- 2020-07- 2020-08- IDA / 65950 Post Limited 4,000.00 0.00 Implement procured by Badulla PGH G COVID-19 Response Quotations Envelope 25 23 06 ation during Covid 19 period LK-MOH-181003-GO-RFQ Pending / 05 No of Steel Beds Component 1: Emergency Request for Single Stage - One 2020-06- 2020-07- 2020-08- IDA / 65950 Post Limited 711.00 0.00 Implement procured by Badulla PGH G COVID-19 Response Quotations Envelope 25 23 06 ation during Covid 19 period LK-MOH-181004-GO-RFQ Pending / 04 Nos Washing Machines Component 1: Emergency Request for Single Stage - One 2020-06- 2020-07- 2020-08- IDA / 65950 Post Limited 885.00 0.00 Implement procured by Badulla PGH G COVID-19 Response Quotations Envelope 25 23 06 ation during Covid 19 period LK-MOH-181005-GO-RFQ Pending / 02 Nos Refrigerators Component 1: Emergency Request for Single Stage - One 2020-06- 2020-07- 2020-08- IDA / 65950 Post Limited 541.00 0.00 Implement procured by Badulla PGH G COVID-19 Response Quotations Envelope 25 23 06 ation during Covid 19 period LK-MOH-181068-GO-RFQ Pending / 10 Nos Mobile Phones Component 1: Emergency Request for Single Stage - One 2020-06- 2020-07- 2020-08- IDA / 65950 Post Limited 85.00 0.00 Implement procured by Badulla PGH G COVID-19 Response Quotations Envelope 26 24 07 ation during Covid 19 period LK-MOH-181069-GO-RFQ Pending / 250 Mtr Poplin Material Component 1: Emergency Request for Single Stage - One 2020-06- 2020-07- 2020-08- IDA / 65950 Post Limited 152.00 0.00 Implement procured by Badulla PGH G COVID-19 Response Quotations Envelope 26 24 07 ation during Covid 19 period LK-MOH-181071-GO-RFB / Supply, Installation and Pending Component 1: Emergency Single Stage - One 2020-06- 2020-06- 2020-08- 2020-09- 2020-10- 2020-11- Commissioning of 05 Units IDA / 65950 Post Request for Bids Open - National 51,710.00 0.00 Implement COVID-19 Response Envelope 21 26 07 06 11 25 Ventilators procured Badulla ation PGH G during Covid 19 period LK-MOH-181072-GO-RFB Pending / 08 Nos Autoclave table Component 1: Emergency Single Stage - One 2020-06- 2020-06- 2020-08- 2020-09- 2020-10- 2020-11- IDA / 65950 Post Request for Bids Open - National 20,421.00 0.00 Implement tops procured by Badulla COVID-19 Response Envelope 21 26 07 06 11 25 ation PGH G during Covid 19 period LK-MOH-181073-GO-RFB Pending / Bio-safety Cabinet for Mini Component 1: Emergency Single Stage - One 2020-06- 2020-06- 2020-08- 2020-09- 2020-10- 2020-11- IDA / 65950 Post Request for Bids Open - National 9,500.00 0.00 Implement Lab procured by Badulla COVID-19 Response Envelope 21 26 07 06 11 25 ation PGH G during Covid 19 period LK-MOH-181074-GO-RFB / Medical Laboratory Pending Component 1: Emergency Single Stage - One 2020-06- 2020-06- 2020-08- 2020-09- 2020-10- 2020-11- Centrifuge for Mini Lab IDA / 65950 Post Request for Bids Open - National 5,120.00 0.00 Implement COVID-19 Response Envelope 21 26 07 06 11 25 procured by Badulla PGH G ation during Covid 19 period LK-MOH-181075-GO-RFB Pending Component 1: Emergency Single Stage - One 2020-06- 2020-06- 2020-08- 2020-09- 2020-10- 2020-11- / Bench Top Fully IDA / 65950 Post Request for Bids Open - National 15,785.00 0.00 Implement COVID-19 Response Envelope 21 26 07 06 11 25 Automated Biochemistry ation Analyzer LK-MOH-181155-GO-DIR / Fully Automated Pending Component 1: Emergency 2020-06- 2020-06- 2020-07- 2020-07- Biochemistry Analyzer for IDA / 65950 Post Direct Selection 1,960.00 0.00 Implement COVID-19 Response 22 27 11 25 Mini Lab (Reagents) ation procured by Badulla PGH G during Covid 19 period LK-MOH-181157-GO-DIR Pending / 05 Nos Stethoscope Component 1: Emergency 2020-06- 2020-06- 2020-07- 2020-07- IDA / 65950 Post Direct Selection Direct 58.00 0.00 Implement procured by Badulla PGH G COVID-19 Response 22 27 11 25 ation during Covid 19 period LK-MOH-181196-GO-DIR Pending / 05 Nos BP Meters Component 1: Emergency 2020-06- 2020-06- 2020-07- 2020-07- IDA / 65950 Post Direct Selection Direct 101.00 0.00 Implement procured by Badulla PGH G COVID-19 Response 22 27 11 25 ation during Covid 19 period LK-MOH-181197-GO-RFQ Pending / 200 Nos N 95 Masks Component 1: Emergency Request for Single Stage - One 2020-06- 2020-07- 2020-08- IDA / 65950 Post Limited 342.00 0.00 Implement procured by Badulla PGH G COVID-19 Response Quotations Envelope 27 21 04 ation during Covid 19 period LK-MOH-181198-GO-DIR Pending / 10 Nos Stethoscopes Component 1: Emergency 2020-06- 2020-06- 2020-07- 2020-07- IDA / 65950 Post Direct Selection Direct 116.00 0.00 Implement procured by Badulla PGH G COVID-19 Response 22 27 11 25 ation during Covid 19 period LK-MOH-181200-GO-DIR Pending / 04 Nos BP Meter procured Component 1: Emergency 2020-06- 2020-06- 2020-07- 2020-07- IDA / 65950 Post Direct Selection Direct 272.00 0.00 Implement by Badulla PGH G during COVID-19 Response 22 27 11 25 ation Covid 19 period LK-MOH-181201-GO-DIR / 07 Nos Digital clinical Pending Component 1: Emergency 2020-06- 2020-06- 2020-07- 2020-07- Thermometer procured by IDA / 65950 Post Direct Selection Direct 33.00 0.00 Implement COVID-19 Response 22 27 11 25 Badulla PGH G during Covid ation 19 period LK-MOH-182740-GO-RFQ Pending Component 1: Emergency Request for Single Stage - One 2020-07- 2020-08- 2020-08- / Dust Bin 120L procured by IDA / 65950 Post Limited 270.00 0.00 Implement COVID-19 Response Quotations Envelope 11 15 29 MOH supplies division ation LK-MOH-182741-GO-RFQ / Plastic chair with out arm Pending Component 1: Emergency Request for Single Stage - One 2020-07- 2020-08- 2020-08- -50 Nos & Water Dispenser IDA / 65950 Post Limited 1,622.00 0.00 Implement COVID-19 Response Quotations Envelope 11 15 29 - 14 Nos procured by MOH ation Procurement Division LK-MOH-182742-GO-RFQ Pending / 131 Nos Bed side Lockers Component 1: Emergency Request for Single Stage - One 2020-07- 2020-08- 2020-08- IDA / 65950 Post Limited 10,810.00 0.00 Implement procured by MOH Supplies COVID-19 Response Quotations Envelope 11 15 29 ation Division LK-MOH-182743-GO-RFQ / Wheel chairs 03 Nos , Pending Component 1: Emergency Request for Single Stage - One 2020-07- 2020-08- 2020-08- Oxygen cart - 05 Nos & IBRD / 90850 Post Limited 2,703.00 0.00 Implement COVID-19 Response Quotations Envelope 11 15 29 Saline Stand - 36 Nos ation procured by MOH supplies division LK-MOH-182746-GO-RFQ Pending / Over Bed Table - 36 Nos Component 1: Emergency Request for Single Stage - One 2020-07- 2020-08- 2020-08- IDA / 65950 Post Limited 2,703.00 0.00 Implement procured by MOH supplies COVID-19 Response Quotations Envelope 11 15 29 ation division during Covid period LK-MOH-182747-GO-RFQ / Patient Trolley - 05 Nos & Pending Component 1: Emergency Request for Single Stage - One 2020-07- 2020-08- 2020-08- Drug Trolley 09 Nos IDA / 65950 Post Limited 1,622.00 0.00 Implement COVID-19 Response Quotations Envelope 11 15 29 procured by MOH supplies ation division during Covid period LK-MOH-182748-GO-RFQ Pending / Hospital Beds - 151 Component 1: Emergency Request for Single Stage - One 2020-07- 2020-08- 2020-08- IDA / 65950 Post Limited 19,919.00 0.00 Implement procured by MOH supplies COVID-19 Response Quotations Envelope 11 15 29 ation division during Covid period LK-MOH-182751-GO-RFQ Pending / Bedside Lockers - 176 Nos Component 1: Emergency Request for Single Stage - One 2020-07- 2020-08- 2020-08- IDA / 65950 Post Limited 13,514.00 0.00 Implement procured by MOH supplies COVID-19 Response Quotations Envelope 11 15 29 ation division during Covid period LK-MOH-182754-GO-RFQ Pending / Mattress - 150 Nos Component 1: Emergency Request for Single Stage - One 2020-07- 2020-08- 2020-08- IDA / 65950 Post Limited 3,243.00 0.00 Implement procured by MOH supplies COVID-19 Response Quotations Envelope 11 15 29 ation division during Covid period LK-MOH-182756-GO-RFQ Pending / Infrared thermometers - Component 1: Emergency Request for Single Stage - One 2020-07- 2020-08- 2020-08- IDA / 65950 Post Limited 430.00 0.00 Implement 05 Nos procured by NHSL COVID-19 Response Quotations Envelope 11 15 29 ation during Covid period LK-MOH-182762-GO-RFQ Pending / Ventilator Circuits - 300 Component 1: Emergency Request for Single Stage - One 2020-07- 2020-08- 2020-08- IDA / 65950 Post Limited 2,270.00 0.00 Implement Nos are procured by NHSL COVID-19 Response Quotations Envelope 11 15 29 ation during Covid period. LK-MOH-182763-GO-RFQ / Flexible Breathing System Pending Component 1: Emergency Request for Single Stage - One 2020-07- 2020-08- 2020-08- with Water Traps - 250 Nos IDA / 65950 Post Limited 3,378.00 0.00 Implement COVID-19 Response Quotations Envelope 11 15 29 procured by NHSL during ation Covid period. LK-MOH-182764-GO-RFQ Pending / Oxygen Marks - 1,000 nos Component 1: Emergency Request for Single Stage - One 2020-07- 2020-08- 2020-08- IDA / 65950 Post Limited 4,054.00 0.00 Implement procured by NHSL during COVID-19 Response Quotations Envelope 11 15 29 ation Covid period. LK-MOH-182765-GO-RFQ Pending Component 1: Emergency Request for Single Stage - One 2020-07- 2020-08- 2020-08- / Eco Masks 80 Nos IDA / 65950 Post Limited 541.00 0.00 Implement COVID-19 Response Quotations Envelope 11 15 29 procured by NHSL during ation Covid period. LK-MOH-182766-GO-RFQ / Goggles for emergency Pending Component 1: Emergency Request for Single Stage - One 2020-07- 2020-08- 2020-08- infectious condition - 1000 IDA / 65950 Post Limited 4,108.00 0.00 Implement COVID-19 Response Quotations Envelope 11 15 29 Nos procured by NHSL ation during Covid period. LK-MOH-182769-GO-RFQ / Personnel Protective Pending Component 1: Emergency Request for Single Stage - One 2020-07- 2020-08- 2020-08- Equipment - 250 Sets IDA / 65950 Post Limited 10,584.00 0.00 Implement COVID-19 Response Quotations Envelope 11 15 29 procured by NHSL during ation Covid period. LK-MOH-182770-GO-RFQ / Bacterial Filter without Pending Component 1: Emergency Request for Single Stage - One 2020-07- 2020-08- 2020-08- heat moisture - 3,000 Nos IDA / 65950 Post Limited 3,514.00 0.00 Implement COVID-19 Response Quotations Envelope 11 15 29 procured by NHSL during ation Covid period. LK-MOH-182771-GO-RFQ Pending / Shoe Covers - 1,000 Nos Component 1: Emergency Request for Single Stage - One 2020-07- 2020-08- 2020-08- IDA / 65950 Post Limited 243.00 0.00 Implement procured by NHSL during COVID-19 Response Quotations Envelope 11 15 29 ation Covid period. LK-MOH-182772-GO-RFQ Pending / Polythene Bags - 161,150 Component 1: Emergency Request for Single Stage - One 2020-07- 2020-08- 2020-08- IDA / 65950 Post Limited 26,649.00 0.00 Implement Kgs procured by NHSL COVID-19 Response Quotations Envelope 11 15 29 ation during Covid period. LK-MOH-182778-GO-RFQ Pending / N 95 Face Masks - 1,000 Component 1: Emergency Request for Single Stage - One 2020-07- 2020-08- 2020-08- IDA / 65950 Post Limited 4,865.00 0.00 Implement Nos procured by NHSL COVID-19 Response Quotations Envelope 11 15 29 ation during Covid period. LK-MOH-182780-GO-RFQ Pending / Infrared Thermometer - Component 1: Emergency Request for Single Stage - One 2020-07- 2020-08- 2020-08- IDA / 65950 Post Limited 3,438.00 0.00 Implement 40 Nos procured by NHSL COVID-19 Response Quotations Envelope 11 15 29 ation during Covid period. LK-MOH-182781-GO-RFQ Pending / Disposable Coveralls and Component 1: Emergency Request for Single Stage - One 2020-07- 2020-08- 2020-08- IDA / 65950 Post Limited 27,568.00 0.00 Implement Items - 4,500 Nos procured COVID-19 Response Quotations Envelope 11 15 29 ation by NHSL during Covid period. LK-MOH-182782-GO-RFB Pending / Pulse Oximeter - 57 Nos Component 1: Emergency Single Stage - One 2020-07- 2020-07- 2020-08- 2020-08- 2020-09- 2020-09- IDA / 65950 Post Request for Bids Limited 31,735.00 0.00 Implement procured by BME Division COVID-19 Response Envelope 06 11 01 16 06 20 ation during Covid period. LK-MOH-182783-GO-RFB Pending / Infusion Pumps - 108 Nos Component 1: Emergency Single Stage - One 2020-07- 2020-07- 2020-08- 2020-08- 2020-09- 2020-09- IDA / 65950 Post Request for Bids Limited 32,692.00 0.00 Implement procured by BME Division COVID-19 Response Envelope 06 11 01 15 05 19 ation during Covid period LK-MOH-182785-GO-RFB Pending / Syringe Pumps - 38 Nos Component 1: Emergency Single Stage - One 2020-07- 2020-07- 2020-08- 2020-08- 2020-09- 2020-09- IDA / 65950 Post Request for Bids Limited 16,895.00 0.00 Implement procured by BME Division COVID-19 Response Envelope 06 11 01 15 05 19 ation during Covid period LK-MOH-182786-GO-RFQ / Suction Apparatus - 57 Component 1: Emergency Single Stage - One 2020-07- 2020-09- 2020-07- 2020-09- 2020-08- 2020-09- 2020-08- 2020-09- 2020-09- 2020-09- 2020-09- IDA / 65950 Post Request for Bids Limited 60,389.00 60,307.68 Signed Nos procured by BME COVID-19 Response Envelope 06 01 11 01 01 10 08 11 05 15 20 Division during Covid period LK-MOH-182787-GO-RFB / Defibrillators - 11 Nos Component 1: Emergency Single Stage - One 2020-07- 2020-09- 2020-07- 2020-09- 2020-08- 2020-09- 2020-08- 2020-09- 2020-09- 2020-09- 2020-09- IDA / 65950 Post Request for Bids Limited 52,859.00 52,780.98 Signed procured by BME Division COVID-19 Response Envelope 06 01 11 01 01 07 15 08 05 10 20 during Covid period LK-MOH-182788-GO-RFB / High Floor Oxygen Meters Component 1: Emergency Single Stage - One 2020-07- 2020-09- 2020-07- 2020-09- 2020-08- 2020-09- 2020-08- 2020-09- 2020-09- 2020-09- 2020-09- IDA / 65950 Post Request for Bids Limited 251,622.00 251,248.04 Signed - 38 Nos procured by BME COVID-19 Response Envelope 06 01 11 08 01 09 15 11 05 14 20 Division during Covid period LK-MOH-182789-GO-RFB / Bronchoscopy Machine 25 Component 1: Emergency Single Stage - One 2020-07- 2020-09- 2020-07- 2020-09- 2020-08- 2020-09- 2020-08- 2020-09- 2020-08- 2020-09- 2020-09- IDA / 65950 Post Request for Bids Limited 214,865.00 214,574.87 Signed Nos procured by BME COVID-19 Response Envelope 06 01 11 01 01 10 08 11 29 14 12 Division during Covid period LK-MOH-182790-GO-RFB / Blood Gas Machines - Component 1: Emergency Single Stage - One 2020-07- 2020-09- 2020-07- 2020-09- 2020-08- 2020-09- 2020-08- 2020-09- 2020-09- 2020-09- 2020-09- IDA / 65950 Post Request for Bids Limited 177,295.00 177,056.01 Signed 10Nos procured by BME COVID-19 Response Envelope 06 01 11 01 01 10 15 11 05 14 19 Division during Covid period LK-MOH-182791-GO-RFB Pending / Two Concentrates - 25 Component 1: Emergency Single Stage - One 2020-07- 2020-07- 2020-08- 2020-08- 2020-09- 2020-09- IDA / 65950 Post Request for Bids Limited 22,297.00 0.00 Implement Nos procured by BME COVID-19 Response Envelope 06 11 01 15 05 26 ation Division during Covid period Page 5 LK-MOH-182792-GO-RFB / CRRT Machine 02 Nos Component 1: Emergency Single Stage - One 2020-07- 2020-09- 2020-07- 2020-09- 2020-08- 2020-09- 2020-08- 2020-09- 2020-09- 2020-09- 2020-10- IDA / 65950 Post Request for Bids Limited 69,189.00 73,404.37 Signed procured by BME Division COVID-19 Response Envelope 06 01 11 01 01 11 16 11 13 14 04 during Covid period LK-MOH-182794-GO-RFB / CRRT Machine - 03 Nos Component 1: Emergency Single Stage - One 2020-07- 2020-09- 2020-07- 2020-09- 2020-08- 2020-09- 2020-08- 2020-09- 2020-09- 2020-09- 2020-10- IDA / 65950 Post Request for Bids Limited 97,297.00 100,391.27 Signed procured by BME Division COVID-19 Response Envelope 06 01 11 01 01 10 15 11 12 11 03 during Covid period LK-MOH-182795-GO-RFB Pending / Suction Apparatus - 32 Component 1: Emergency Single Stage - One 2020-07- 2020-07- 2020-08- 2020-08- 2020-09- 2021-03- IDA / 65950 Post Request for Bids Limited 33,297.00 0.00 Implement Nos procured by BME COVID-19 Response Envelope 06 11 01 15 19 18 ation Division during Covid period LK-MOH-182796-GO-RFB Pending / Blood Pressure Apparatus Component 1: Emergency Single Stage - One 2020-07- 2020-07- 2020-08- 2020-08- 2020-09- 2020-09- IDA / 65950 Post Request for Bids Limited 1,903.00 0.00 Implement - 32 Nos procured by BME COVID-19 Response Envelope 06 11 01 15 05 06 ation Division during Covid period LK-MOH-182865-GO-RFQ / Printing and Delivery of Pending 250,000 Posters on Component 1: Emergency Request for Single Stage - One 2020-07- 2020-08- 2020-09- IDA / 65950 Post Limited 32,436.00 0.00 Implement Adapting to Normal day-to- COVID-19 Response Quotations Envelope 14 17 01 ation day life without being infected by Covid-19 LK-MOH-183669-GO-DIR / Provision of meals and Pending refreshments for the staff Component 1: Emergency 2020-07- 2020-07- 2020-08- 2022-04- IDA / 65950 Post Direct Selection Direct 8,349.00 0.00 Implement involved in the PCR testing COVID-19 Response 14 19 09 01 ation at BIA Katunayake for the period of two months LK-MOH-185535-GO-RFQ Pending / Purchase of Paint Items Component 1: Emergency Request for Single Stage - One 2020-08- 2020-09- 2020-11- IDA / 65950 Post Limited 74,730.00 0.00 Implement required for Quarantine COVID-19 Response Quotations Envelope 02 20 04 ation centers LK-MOH-185536-GO-RFQ Pending Component 1: Emergency Request for Single Stage - One 2020-08- 2020-09- 2021-03- / Purchase of Septic Tanks IDA / 65950 Post Limited 3,566.00 0.00 Implement COVID-19 Response Quotations Envelope 02 13 12 for Quarantine centers ation LK-MOH-185537-GO-RFQ Pending Component 1: Emergency Request for Single Stage - One 2020-08- 2020-09- 2020-11- / Purchase of Tools for IDA / 65950 Post Limited 12,570.00 0.00 Implement COVID-19 Response Quotations Envelope 02 20 04 Quarantine centers ation LK-MOH-185539-GO-RFQ Pending Component 1: Emergency Request for Single Stage - One 2020-08- 2020-09- 2021-03- / Purchase of Plywood Sheet IDA / 65950 Post Limited 2,744.00 0.00 Implement COVID-19 Response Quotations Envelope 02 13 12 for Quarantine centers ation LK-MOH-185540-GO-RFQ Pending / Purchase of 2,702 Nos Component 1: Emergency Request for Single Stage - One 2020-08- 2020-09- 2020-10- IDA / 65950 Post Limited 14,221.00 0.00 Implement Cement Bags for Quarantine COVID-19 Response Quotations Envelope 02 13 13 ation centers LK-MOH-185542-GO-RFQ Pending Component 1: Emergency Request for Single Stage - One 2020-08- 2020-08- 2020-10- / Purchase of Tile for IDA / 65950 Post Limited 8,050.00 0.00 Implement COVID-19 Response Quotations Envelope 02 30 14 Quarantine centers ation LK-MOH-185543-GO-RFQ Pending Component 1: Emergency Request for Single Stage - One 2020-08- 2020-08- 2020-10- / Purchase of Sanitary IDA / 65950 Post Limited 94,668.00 0.00 Implement COVID-19 Response Quotations Envelope 02 30 14 Fittings for Quarantine ation centers LK-MOH-185546-GO-RFQ Pending Component 1: Emergency Request for Single Stage - One 2020-08- 2020-08- 2020-10- / Purchase of Timber for IDA / 65950 Post Limited 40,000.00 0.00 Implement COVID-19 Response Quotations Envelope 02 30 14 Quarantine centers ation LK-MOH-185547-GO-RFQ Pending Component 1: Emergency Request for Single Stage - One 2020-08- 2020-08- 2020-10- / Purchase of Zn/Aluminium IDA / 65950 Post Limited 37,280.00 0.00 Implement COVID-19 Response Quotations Envelope 02 30 14 Sheet for Quarantine centers ation LK-MOH-185553-GO-RFQ / Purchase of Yard Items Pending (River Component 1: Emergency Request for Single Stage - One 2020-08- 2020-09- 2020-10- IDA / 65950 Post Limited 32,315.00 0.00 Implement Sand/Metal/Rubble/Cement COVID-19 Response Quotations Envelope 02 13 13 ation Blocks/Engineering Bricks/Precast Concrete Grill) for Quarantine centers LK-MOH-185556-GO-RFQ Pending Component 1: Emergency Request for Single Stage - One 2020-08- 2020-09- 2020-10- / Purchase of Electrical IDA / 65950 Post Limited 22,616.00 0.00 Implement COVID-19 Response Quotations Envelope 02 13 13 Cables for Quarantine ation centers LK-MOH-185559-GO-RFQ Pending Component 1: Emergency Request for Single Stage - One 2020-08- 2020-09- 2020-10- / Purchase of Ceiling/wall IDA / 65950 Post Limited 96,480.00 0.00 Implement COVID-19 Response Quotations Envelope 02 13 13 Fan for Quarantine centers ation LK-MOH-185561-GO-RFQ Pending Component 1: Emergency Request for Single Stage - One 2020-08- 2020-09- 2020-10- / Purchase of Electrical IDA / 65950 Post Limited 46,621.00 0.00 Implement COVID-19 Response Quotations Envelope 02 13 13 Fittings for Quarantine ation centers LK-MOH-185562-GO-RFQ Pending Component 1: Emergency Request for Single Stage - One 2020-08- 2020-09- 2020-10- / Purchase of Hardware IDA / 65950 Post Limited 121,628.00 0.00 Implement COVID-19 Response Quotations Envelope 02 13 13 Items for Quarantine centers ation LK-MOH-185567-GO-RFQ Pending Component 1: Emergency Request for Single Stage - One 2020-08- 2020-09- 2020-10- / Purchase of Steel for IDA / 65950 Post Limited 38,437.00 0.00 Implement COVID-19 Response Quotations Envelope 02 13 13 Quarantine centers ation LK-MOH-185569-GO-RFQ Pending Component 1: Emergency Request for Single Stage - One 2020-08- 2020-09- 2020-10- / Purchase of Aluminium IDA / 65950 Post Limited 16,731.00 0.00 Implement COVID-19 Response Quotations Envelope 02 13 13 Item for Quarantine centers ation LK-MOH-185577-GO-RFQ Pending Component 1: Emergency Request for Single Stage - One 2020-08- 2020-09- 2020-10- / Purchase of P.V.C. Items IDA / 65950 Post Limited 50,941.00 0.00 Implement COVID-19 Response Quotations Envelope 02 13 13 for Quarantine centers ation LK-MOH-185580-GO-RFQ Pending Component 1: Emergency Request for Single Stage - One 2020-08- 2020-09- 2020-10- / Purchase of Water Tank IDA / 65950 Post Limited 6,043.00 0.00 Implement COVID-19 Response Quotations Envelope 02 13 13 for Quarantine centers ation LK-MOH-185582-GO-RFQ Pending Component 1: Emergency Request for Single Stage - One 2020-08- 2020-09- 2020-10- / Purchase of Concrete IDA / 65950 Post Limited 1,272.00 0.00 Implement COVID-19 Response Quotations Envelope 02 13 13 Mixture for Quarantine ation centers LK-MOH-185584-GO-RFQ Pending Component 1: Emergency Request for Single Stage - One 2020-08- 2020-09- 2020-10- / Purchase of GAS Items for IDA / 65950 Post Limited 442.00 0.00 Implement COVID-19 Response Quotations Envelope 02 13 13 Quarantine centers ation LK-MOH-186237-GO-RFB / 200,000 Nos Covid 19 Under Real Time PCR Kits, 200,000 Component 1: Emergency Open - Single Stage - One 2020-08- 2020-09- 2020-08- 2020-09- 2020-08- 2020-09- 2020-10- 2020-12- IDA / 65950 Post Request for Bids 4,273,232.00 0.00 Implement Nos Extraction Kits and COVID-19 Response International Envelope 13 10 17 10 31 07 05 04 ation other consumable items required for PCR Tests LK-MOH-188260-GO-RFQ / 20 Mos Steel Towel Racks Pending Component 1: Emergency Request for Single Stage - One 2020-08- 2020-09- 2021-03- for Kalubowila Hospital IDA / 65950 Post Limited 237.00 0.00 Implement COVID-19 Response Quotations Envelope 16 20 19 Doctors quarters to face ation Covid 19 Pandemic LK-MOH-188396-GO-RFQ / Supply of PCR reagent N28 Realstr R SARS Cov-2 Pending Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-11- RT –PCR Kit RUo,96 IDA / 65950 Post Limited 21,891.00 0.00 Implement COVID-19 Response Quotations Envelope 17 05 19 Reactions and necessary ation consumables procured by Ragama Teaching Hospital during Covid period LK-MOH-188398-GO-RFQ / Supply of PCR reagent Pending N28Realstr R SARS Cov-2 Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-11- IDA / 65950 Post Limited 4,842.00 0.00 Implement RT –PCR Kit RUo,96 COVID-19 Response Quotations Envelope 17 05 19 ation Reactions procured by Ragama Teaching Hospital during Covid period LK-MOH-188399-GO-RFQ / Supply of PCR reagent Commercial vial RAN Pending Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-11- extraction kit to extract viral IDA / 65950 Post Limited 3,354.00 0.00 Implement COVID-19 Response Quotations Envelope 17 05 19 RAN procured by Ragama ation Teaching Hospital during Covid period LK-MOH-188400-GO-RFQ / Supply of PCR reagent Commercial vial RAN Pending Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-11- extraction kit to extract viral IDA / 65950 Post Limited 22,226.00 0.00 Implement COVID-19 Response Quotations Envelope 17 05 19 RAN procured by Ragama ation Teaching Hospital during Covid period LK-MOH-188402-GO-RFQ / Supply of Ethanol Absolute Pending Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-10- 99.9% procured by Ragama IDA / 65950 Post Limited 1,474.00 0.00 Implement COVID-19 Response Quotations Envelope 17 05 06 Teaching Hospital during ation Covid period LK-MOH-188413-GO-DIR / 01 Nos Infrared Pending Component 1: Emergency 2020-08- 2020-08- 2020-08- 2020-09- Thermometers, procured by IDA / 65950 Post Direct Selection Direct 158.00 0.00 Implement COVID-19 Response 12 17 31 07 Ragama Teaching Hospital ation during Covid period. LK-MOH-188414-GO-DIR Pending / 06 Nos Infrared Component 1: Emergency 2020-08- 2020-08- 2020-08- 2020-09- IDA / 65950 Post Direct Selection Direct 726.00 0.00 Implement Thermometers procured by COVID-19 Response 12 17 31 07 ation Ragama Teaching Hospital during Covid period LK-MOH-188415-GO-DIR Pending / 04 Nos Infrared Component 1: Emergency 2020-08- 2020-08- 2020-08- 2020-09- IDA / 65950 Post Direct Selection Direct 484.00 0.00 Implement Thermometers procured by COVID-19 Response 12 17 31 07 ation Ragama Teaching Hospital during Covid period LK-MOH-188416-GO-DIR Pending / 250 Nos N95 Mask Component 1: Emergency 2020-08- 2020-08- 2020-08- 2020-09- IDA / 65950 Post Direct Selection Direct 1,645.00 0.00 Implement Original procured by COVID-19 Response 12 17 31 07 ation Ragama Teaching Hospital during Covid period LK-MOH-188417-GO-DIR Pending / 05 Nos Sanitizer 5L (Hand Component 1: Emergency 2020-08- 2020-08- 2020-08- 2020-09- IDA / 65950 Post Direct Selection Direct 289.00 0.00 Implement ) procured by Ragama COVID-19 Response 12 17 31 07 ation Teaching Hospital during Covid period LK-MOH-188418-GO-DIR / 30 Nos Scissor & Stapler Pending Component 1: Emergency 2020-08- 2020-08- 2020-08- 2020-09- Machine procured by IDA / 65950 Post Direct Selection Direct 52.00 0.00 Implement COVID-19 Response 12 17 31 07 Ragama Teaching Hospital ation during Covid period LK-MOH-188434-GO-DIR Pending / 250 Nos N95 Mask Component 1: Emergency 2020-08- 2020-08- 2020-08- 2020-09- IDA / 65950 Post Direct Selection Direct 1,645.00 0.00 Implement (Original) procured by COVID-19 Response 12 17 31 07 ation Ragama Teaching Hospital during Covid period LK-MOH-188435-GO-DIR / procured by Ragama Teaching Hospital during Covid period Pending Component 1: Emergency 2020-08- 2020-08- 2020-08- 2020-09- IDA / 65950 Post Direct Selection Direct 237.00 0.00 Implement COVID-19 Response 12 17 31 07 ation 2500 Nos Disposable Gloves (powder Free) procured by Ragama Teaching Hospital during Covid period LK-MOH-188437-GO-DIR / 06 Nos Lacy S Zip Bag Pending Component 1: Emergency 2020-08- 2020-08- 2020-08- 2020-09- Gallon (COVID Lab) IDA / 65950 Post Direct Selection Direct 23.00 0.00 Implement COVID-19 Response 12 17 31 07 procured by Ragama ation Teaching Hospital during Covid period. LK-MOH-188443-GO-DIR / 25 Nos Rubberized Coir Pending Component 1: Emergency 2020-08- 2020-08- 2020-08- 2020-09- Mattress procured by IDA / 65950 Post Direct Selection Direct 651.00 0.00 Implement COVID-19 Response 12 17 31 07 Ragama Teaching Hospital ation during Covid period. LK-MOH-188447-GO-DIR Pending / Hand Wash item for ward Component 1: Emergency 2020-08- 2020-08- 2020-08- 2020-09- IDA / 65950 Post Direct Selection Direct 1,416.00 0.00 Implement procured by Ragama COVID-19 Response 12 17 31 07 ation Teaching Hospital during Covid period. LK-MOH-188449-GO-DIR Pending / 05 Nos Civilizing Fans Component 1: Emergency 2020-08- 2020-08- 2020-08- 2020-09- IDA / 65950 Post Direct Selection Direct 232.00 0.00 Implement procured by Ragama COVID-19 Response 12 17 31 07 ation Teaching Hospital during Covid period LK-MOH-188451-GO-DIR Pending / 03 Nos Air Purifier Component 1: Emergency 2020-08- 2020-08- 2020-08- 2020-09- IDA / 65950 Post Direct Selection Direct 174.00 0.00 Implement procured by Ragama COVID-19 Response 12 17 31 07 ation Teaching Hospital during Covid period. LK-MOH-188452-GO-DIR Pending / Lasy Zip bag for covid lab Component 1: Emergency 2020-08- 2020-08- 2020-08- 2020-09- IDA / 65950 Post Direct Selection Direct 19.00 0.00 Implement procured by Ragama COVID-19 Response 12 17 31 07 ation Teaching Hospital during Covid period. LK-MOH-188453-GO-DIR Pending / Vehicle Battery procured Component 1: Emergency 2020-08- 2020-08- 2020-08- 2020-09- IDA / 65950 Post Direct Selection Direct 118.00 0.00 Implement by Ragama Teaching COVID-19 Response 12 17 31 07 ation Hospital during Covid period. LK-MOH-188454-GO-DIR / Garbage Bins (covid Lab & Pending Component 1: Emergency 2020-08- 2020-08- 2020-08- 2020-09- ward) procured by Ragama IDA / 65950 Post Direct Selection Direct 683.00 0.00 Implement COVID-19 Response 12 17 31 07 Teaching Hospital during ation Covid period. LK-MOH-188455-GO-DIR / 06 Nos Wall Fan for Covid Pending Component 1: Emergency 2020-08- 2020-08- 2020-08- 2020-09- ward procured by Ragama IDA / 65950 Post Direct Selection Direct 152.00 0.00 Implement COVID-19 Response 12 17 31 07 Teaching Hospital during ation Covid period. LK-MOH-188457-GO-DIR / Electrical Accessories Pending Component 1: Emergency 2020-08- 2020-08- 2020-08- 2020-09- (Repair of MICU) procured IDA / 65950 Post Direct Selection Direct 578.00 0.00 Implement COVID-19 Response 12 17 31 07 by Ragama Teaching ation Hospital during Covid period. LK-MOH-188458-GO-DIR Pending / 3 KVA UPS for Covid Lab Component 1: Emergency 2020-08- 2020-08- 2020-08- 2020-09- IDA / 65950 Post Direct Selection Direct 342.00 0.00 Implement procured by Ragama COVID-19 Response 12 17 31 07 ation Teaching Hospital during Covid period. LK-MOH-188460-GO-DIR Pending / 03 Nos Toner Cartridge Component 1: Emergency 2020-08- 2020-08- 2020-08- 2020-09- IDA / 65950 Post Direct Selection Direct 257.00 0.00 Implement procured by Ragama COVID-19 Response 12 17 31 07 ation Teaching Hospital during Covid period. LK-MOH-188461-GO-DIR / 150 Nos Disposable Long Pending Sleeve Surgeon Gown Full Component 1: Emergency 2020-08- 2020-08- 2020-08- 2020-09- IDA / 65950 Post Direct Selection Direct 513.00 0.00 Implement Body Kit procured by COVID-19 Response 12 17 31 07 ation Ragama Teaching Hospital during Covid period. LK-MOH-188464-GO-DIR Pending / 250 Nos N 95 Mask Component 1: Emergency 2020-08- 2020-08- 2020-08- 2020-09- IDA / 65950 Post Direct Selection Direct 1,648.00 0.00 Implement Original procured by COVID-19 Response 12 17 31 07 ation Ragama Teaching Hospital during Covid period. LK-MOH-188466-GO-DIR Pending / 03 Nos Infrared Component 1: Emergency 2020-08- 2020-08- 2020-08- 2020-09- IDA / 65950 Post Direct Selection Direct 521.00 0.00 Implement Thermometers procured by COVID-19 Response 12 17 31 07 ation Ragama Teaching Hospital during Covid period. LK-MOH-188468-GO-DIR / 01 No Air Ventilation Pending Component 1: Emergency 2020-08- 2020-08- 2020-08- 2020-09- System for covid ward IDA / 65950 Post Direct Selection Direct 4,499.00 0.00 Implement COVID-19 Response 12 17 31 07 procured by Ragama ation Teaching Hospital during Covid period. LK-MOH-188485-GO-DIR / 10,000 Nos Supply of Pending Component 1: Emergency 2020-08- 2020-08- 2020-08- 2020-09- Surgical Caps ( Lab & Other IDA / 65950 Post Direct Selection Direct 1,053.00 0.00 Implement COVID-19 Response 12 17 31 07 Unit) procured by Ragama ation Teaching Hospital during Covid period. LK-MOH-188486-GO-DIR / 150 Nos Supply of Pending Component 1: Emergency 2020-08- 2020-08- 2020-08- 2020-09- Goggles ( Lab & ward) IDA / 65950 Post Direct Selection Direct 324.00 0.00 Implement COVID-19 Response 12 17 31 07 procured by Ragama ation Teaching Hospital during Covid period. LK-MOH-188488-GO-DIR Pending / 200 Nos Swab (PCR Lab) Component 1: Emergency 2020-08- 2020-08- 2020-08- 2020-09- IDA / 65950 Post Direct Selection Direct 47.00 0.00 Implement procured by Ragama COVID-19 Response 12 17 31 07 ation Teaching Hospital during Covid period. LK-MOH-188491-GO-DIR Pending / 50 Nos Safety Goggles( Component 1: Emergency 2020-08- 2020-08- 2020-08- 2020-09- IDA / 65950 Post Direct Selection Direct 329.00 0.00 Implement ward) procured by Ragama COVID-19 Response 12 17 31 07 ation Teaching Hospital during Covid period. Page 6 LK-MOH-188494-GO-DIR / 2019 Nos Safety Goggles ( Pending Component 1: Emergency 2020-08- 2020-08- 2020-08- 2020-09- Ward & Unit) procured by IDA / 65950 Post Direct Selection Direct 438.00 0.00 Implement COVID-19 Response 12 17 31 07 Ragama Teaching Hospital ation during Covid period. LK-MOH-188495-GO-DIR Pending / 18 Nos N95 Masks Component 1: Emergency 2020-08- 2020-08- 2020-08- 2020-09- IDA / 65950 Post Direct Selection Direct 171.00 0.00 Implement procured by Ragama COVID-19 Response 12 17 31 07 ation Teaching Hospital during Covid period. LK-MOH-188496-GO-DIR Pending / 300 Nos Oxypura Masks Component 1: Emergency 2020-08- 2020-08- 2020-08- 2020-09- IDA / 65950 Post Direct Selection Direct 268.00 0.00 Implement procured by Ragama COVID-19 Response 12 17 31 07 ation Teaching Hospital during Covid period. LK-MOH-188498-GO-RFQ / 410 Nos N95 Mask Pending Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2021-04- (Wards & PCR Lab) procured IDA / 65950 Post Limited 2,697.00 0.00 Implement COVID-19 Response Quotations Envelope 17 12 10 by Ragama Teaching ation Hospital during Covid period. LK-MOH-188576-GO-DIR / 150 Nos Safety Goggles ( Pending Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- Ward & Unit ) procured by IDA / 65950 Post Direct Selection Direct 300.00 0.00 Implement COVID-19 Response 13 18 01 08 Ragama Teaching Hospital ation during Covid period LK-MOH-188577-GO-DIR Pending / 20 Nos 3 M N95 Masks Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- IDA / 65950 Post Direct Selection Direct 208.00 0.00 Implement procured by Ragama COVID-19 Response 13 18 01 08 ation Teaching Hospital during Covid period. LK-MOH-188578-GO-DIR Pending / 200 Nos Oxypura Mask Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- IDA / 65950 Post Direct Selection Direct 179.00 0.00 Implement (Staff ) procured by Ragama COVID-19 Response 13 18 01 08 ation Teaching Hospital during Covid period. LK-MOH-188579-GO-DIR / 342 Mtr Sheeting Material Pending Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- ( Made PPT Item ) procured IDA / 65950 Post Direct Selection Direct 405.00 0.00 Implement COVID-19 Response 13 18 01 08 by Ragama Teaching ation Hospital during Covid period. LK-MOH-188582-GO-DIR / 700 Mtrs Fabric formal Pending Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- ware Tafata white coat IDA / 65950 Post Direct Selection Direct 332.00 0.00 Implement COVID-19 Response 13 18 01 08 procured by Ragama ation Teaching Hospital during Covid period. LK-MOH-188583-GO-DIR / 05 Nos Sewing Machine Pending Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- motor & Motor belt (PPE IDA / 65950 Post Direct Selection Direct 55.00 0.00 Implement COVID-19 Response 13 18 01 08 Item) procured by Ragama ation Teaching Hospital during Covid period. LK-MOH-188584-GO-DIR / 250 Nos Coconut Shell Pending Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- spoons ( Covid Lab) IDA / 65950 Post Direct Selection Direct 26.00 0.00 Implement COVID-19 Response 13 18 01 08 procured by Ragama ation Teaching Hospital during Covid period. LK-MOH-188585-GO-DIR / 311.8 Kg Polythene (for Pending Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- PPE Item) procured by IDA / 65950 Post Direct Selection Direct 558.00 0.00 Implement COVID-19 Response 13 18 01 08 Ragama Teaching Hospital ation during Covid period. LK-MOH-188587-GO-DIR / 10 Nos Zip Lock Bag ( Pending Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- coved Lab) procured by IDA / 65950 Post Direct Selection Direct 7.70 0.00 Implement COVID-19 Response 13 18 01 08 Ragama Teaching Hospital ation during Covid period. LK-MOH-188592-GO-DIR / 05 Nos Lacotogen milk Pending Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- covid ward procured by IDA / 65950 Post Direct Selection Direct 16.00 0.00 Implement COVID-19 Response 13 18 01 08 Ragama Teaching Hospital ation during Covid period. LK-MOH-188594-GO-DIR Pending / 05 Nos Cartridge ( PCR Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- IDA / 65950 Post Direct Selection Direct 50.00 0.00 Implement Lab) procured by Ragama COVID-19 Response 13 18 01 08 ation Teaching Hospital during Covid period. LK-MOH-188596-GO-DIR / 08 Nos Zip Lock Bag ( PCR Pending Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- Lab) procured by Ragama IDA / 65950 Post Direct Selection Direct 7.60 0.00 Implement COVID-19 Response 13 18 01 08 Teaching Hospital during ation Covid period. LK-MOH-188597-GO-DIR Pending / 01 No Toner ( Lab ) Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- IDA / 65950 Post Direct Selection Direct 24.00 0.00 Implement procured by Ragama COVID-19 Response 13 18 01 08 ation Teaching Hospital during Covid period. LK-MOH-188598-GO-DIR Pending / 42 Kg Polythene ( PPT Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- IDA / 65950 Post Direct Selection Direct 75.00 0.00 Implement Item ) procured by Ragama COVID-19 Response 13 18 01 08 ation Teaching Hospital during Covid period. LK-MOH-188621-GO-DIR Pending / 01 No UPS ( PCR Lab ) Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- IDA / 65950 Post Direct Selection Direct 342.00 0.00 Implement procured by Ragama COVID-19 Response 13 18 01 08 ation Teaching Hospital during Covid period. LK-MOH-188622-GO-DIR / 01 No Junkie Machine ( Pending Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- Made for PPE Item ) IDA / 65950 Post Direct Selection Direct 249.00 0.00 Implement COVID-19 Response 13 18 01 08 procured by Ragama ation Teaching Hospital during Covid period. LK-MOH-188624-GO-DIR Pending / 01 No Refrigerator ( PCR Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- IDA / 65950 Post Direct Selection Direct 185.00 0.00 Implement Lab ) procured by Ragama COVID-19 Response 13 18 01 08 ation Teaching Hospital during Covid period. LK-MOH-188625-GO-DIR / 10 Nos Transparent Sheet Pending Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- ( ward ) procured by IDA / 65950 Post Direct Selection Direct 47.00 0.00 Implement COVID-19 Response 13 18 01 08 Ragama Teaching Hospital ation during Covid period. LK-MOH-188626-GO-DIR / 480 Nos Mineral water Pending Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- Bottles ( ward ) procured by IDA / 65950 Post Direct Selection Direct 63.00 0.00 Implement COVID-19 Response 13 18 01 08 Ragama Teaching Hospital ation during Covid period. LK-MOH-188630-GO-DIR Pending / Electrical Accessories ( Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- IDA / 65950 Post Direct Selection Direct 161.00 0.00 Implement MICU ) procured by Ragama COVID-19 Response 13 18 01 08 ation Teaching Hospital during Covid period. LK-MOH-188633-GO-DIR / 450 Nos Water Bottle ( Pending Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- coved Ward ) procured by IDA / 65950 Post Direct Selection Direct 83.00 0.00 Implement COVID-19 Response 13 18 01 08 Ragama Teaching Hospital ation during Covid period. LK-MOH-188638-GO-DIR Pending / 10 Nos Toners ( PCR Lab Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- IDA / 65950 Post Direct Selection Direct 47.00 0.00 Implement ) procured by Ragama COVID-19 Response 13 18 01 08 ation Teaching Hospital during Covid period. LK-MOH-188639-GO-DIR / 100 Nos Polythene Apron Pending Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- for Ward & Unit procured IDA / 65950 Post Direct Selection Direct 145.00 0.00 Implement COVID-19 Response 13 18 01 08 by Ragama Teaching ation Hospital during Covid period. LK-MOH-188640-GO-DIR Pending / Aluminum Bars (MICU ) Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- IDA / 65950 Post Direct Selection Direct 390.00 0.00 Implement procured by Ragama COVID-19 Response 13 18 01 08 ation Teaching Hospital during Covid period. LK-MOH-188642-GO-DIR Pending / 300 Kg Polythene ( PPT Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- IDA / 65950 Post Direct Selection Direct 643.00 0.00 Implement Item ) procured by Ragama COVID-19 Response 13 18 01 08 ation Teaching Hospital during Covid period. LK-MOH-188645-GO-DIR / 200 Nos Polythene Gown Pending Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- Hospital Staff procured by IDA / 65950 Post Direct Selection Direct 263.00 0.00 Implement COVID-19 Response 13 18 01 08 Ragama Teaching Hospital ation during Covid period. LK-MOH-188664-GO-DIR / 01 No Toner Cartridge for Pending Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- COVID Lab procured by IDA / 65950 Post Direct Selection Direct 42.00 0.00 Implement COVID-19 Response 13 18 01 08 Ragama Teaching Hospital ation during Covid period. LK-MOH-188667-GO-DIR Pending / Cotton Pillows -for ward Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- IDA / 65950 Post Direct Selection Direct 155.00 0.00 Implement procured by Ragama COVID-19 Response 13 18 01 08 ation Teaching Hospital during Covid period. LK-MOH-188669-GO-DIR Pending / 130 Kg Polythene Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- IDA / 65950 Post Direct Selection Direct 95.20 0.00 Implement procured by Ragama COVID-19 Response 13 18 01 08 ation Teaching Hospital during Covid period. LK-MOH-188670-GO-DIR Pending / 01 No AMP with USB Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- IDA / 65950 Post Direct Selection Direct 184.00 0.00 Implement procured by Ragama COVID-19 Response 13 18 01 08 ation Teaching Hospital during Covid period. LK-MOH-188794-GO-DIR Pending / Wax Ribbon & Art Paper Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- IDA / 65950 Post Direct Selection Direct 120.00 0.00 Implement procured by Ragama COVID-19 Response 14 19 02 09 ation Teaching Hospital during Covid period. LK-MOH-188795-GO-DIR Pending / Pijama Kit ( Hospital Staff Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- IDA / 65950 Post Direct Selection Direct 52.00 0.00 Implement ) procured by Ragama COVID-19 Response 14 19 02 09 ation Teaching Hospital during Covid period. LK-MOH-188796-GO-DIR Pending / Hardware item for Micu Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- IDA / 65950 Post Direct Selection Direct 13.00 0.00 Implement procured by Ragama COVID-19 Response 14 19 02 09 ation Teaching Hospital during Covid period. LK-MOH-188797-GO-DIR Pending / Masking tape ( covid Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- IDA / 65950 Post Direct Selection Direct 45.00 0.00 Implement ward ) procured by Ragama COVID-19 Response 14 19 02 09 ation Teaching Hospital during Covid period. LK-MOH-188799-GO-DIR / 130 Mtrs Black polythene Pending Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- for wards procured by IDA / 65950 Post Direct Selection Direct 57.00 0.00 Implement COVID-19 Response 14 19 02 09 Ragama Teaching Hospital ation during Covid period. LK-MOH-188800-GO-DIR / 625 Mtrs Polythene made Pending Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- by PPE Item procured by IDA / 65950 Post Direct Selection Direct 1,154.00 0.00 Implement COVID-19 Response 14 19 02 09 Ragama Teaching Hospital ation during Covid period. LK-MOH-188801-GO-DIR Pending / 32 Nos Transparent Sheet Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- IDA / 65950 Post Direct Selection Direct 147.00 0.00 Implement A4 procured by Ragama COVID-19 Response 14 19 02 09 ation Teaching Hospital during Covid period. LK-MOH-188803-GO-DIR Pending / Electrical Item (MICU ) Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- IDA / 65950 Post Direct Selection Direct 41.00 0.00 Implement procured by Ragama COVID-19 Response 14 19 02 09 ation Teaching Hospital during Covid period. LK-MOH-188804-GO-DIR Pending / 30 Kg. Polythene procured Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- IDA / 65950 Post Direct Selection Direct 27.00 0.00 Implement by Ragama Teaching COVID-19 Response 14 19 02 09 ation Hospital during Covid period. LK-MOH-188805-GO-DIR Pending / 1 No NPU Toner for MICU Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- IDA / 65950 Post Direct Selection Direct 108.00 0.00 Implement procured by Ragama COVID-19 Response 14 19 02 09 ation Teaching Hospital during Covid period. LK-MOH-188806-GO-DIR Pending / Hardware Item ( MICU ) Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- IDA / 65950 Post Direct Selection Direct 455.00 0.00 Implement procured by Ragama COVID-19 Response 14 19 02 09 ation Teaching Hospital during Covid period. LK-MOH-188811-GO-DIR Pending / 35 Nos Sponge Sheet Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- IDA / 65950 Post Direct Selection Direct 455.00 0.00 Implement MICU procured by Ragama COVID-19 Response 14 19 02 09 ation Teaching Hospital during Covid period. LK-MOH-188813-GO-DIR Pending / Aluminium Bars (MICU ) Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- IDA / 65950 Post Direct Selection Direct 175.00 0.00 Implement procured by Ragama COVID-19 Response 14 19 02 09 ation Teaching Hospital during Covid period. LK-MOH-188814-GO-DIR / 36 Nos Mosquito Nets Pending Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- (Coved ward ) procured by IDA / 65950 Post Direct Selection Direct 90.00 0.00 Implement COVID-19 Response 14 19 02 09 Ragama Teaching Hospital ation during Covid period. LK-MOH-188815-GO-DIR / 03 Nos Exhaust fans for Pending Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- MICU procured by Ragama IDA / 65950 Post Direct Selection Direct 79.00 0.00 Implement COVID-19 Response 14 19 02 09 Teaching Hospital during ation Covid period. LK-MOH-188816-GO-DIR / 175 Nos Polythene made Pending Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- Gown procured by Ragama IDA / 65950 Post Direct Selection Direct 46.00 0.00 Implement COVID-19 Response 14 19 02 09 Teaching Hospital during ation Covid period. LK-MOH-188818-GO-DIR / 1125 nOs Polythene made Pending Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- Gowns procured by Ragama IDA / 65950 Post Direct Selection Direct 196.00 0.00 Implement COVID-19 Response 14 19 02 09 Teaching Hospital during ation Covid period. LK-MOH-188820-GO-DIR Pending / Hardware Item (MICU) Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- IDA / 65950 Post Direct Selection Direct 226.00 0.00 Implement procured by Ragama COVID-19 Response 14 19 02 09 ation Teaching Hospital during Covid period. LK-MOH-188821-GO-DIR Pending / Zip lock bag procured by Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- IDA / 65950 Post Direct Selection Direct 11.00 0.00 Implement Ragama Teaching Hospital COVID-19 Response 14 19 02 09 ation during Covid period. LK-MOH-188824-GO-DIR / Taffeta & Elastic roll Made Pending Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- PPE item procured by IDA / 65950 Post Direct Selection Direct 42.00 0.00 Implement COVID-19 Response 14 19 02 09 Ragama Teaching Hospital ation during Covid period. LK-MOH-188825-GO-DIR Pending / 4000 Nos Transparent Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- IDA / 65950 Post Direct Selection Direct 189.00 0.00 Implement Sheets procured by Ragama COVID-19 Response 14 19 02 09 ation Teaching Hospital during Covid period. LK-MOH-188827-GO-DIR / 300 Nos Polythene made Pending Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- Gowns procured by Ragama IDA / 65950 Post Direct Selection Direct 79.00 0.00 Implement COVID-19 Response 14 19 02 09 Teaching Hospital during ation Covid period. LK-MOH-188828-GO-DIR / 1210 Nos Polythene made Pending Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- Gowns procured by Ragama IDA / 65950 Post Direct Selection Direct 318.00 0.00 Implement COVID-19 Response 14 19 02 09 Teaching Hospital during ation Covid period. LK-MOH-188829-GO-DIR / Hardware Item & Electrical Pending Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- Item ( MICU ) procured by IDA / 65950 Post Direct Selection Direct 78.00 0.00 Implement COVID-19 Response 14 19 02 09 Ragama Teaching Hospital ation during Covid period. LK-MOH-188831-GO-DIR / 264 Kg Polythene made Pending Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- by PPE item procured by IDA / 65950 Post Direct Selection Direct 653.00 0.00 Implement COVID-19 Response 14 19 02 09 Ragama Teaching Hospital ation during Covid period. LK-MOH-188833-GO-DIR / 200 Mtrs Rexine material Pending Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- foe PPE item made procured IDA / 65950 Post Direct Selection Direct 477.00 0.00 Implement COVID-19 Response 14 19 02 09 by Ragama Teaching ation Hospital during Covid period. LK-MOH-188839-GO-DIR / Hardware items for Pending Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- quarantine center procured IDA / 65950 Post Direct Selection Direct 213.00 0.00 Implement COVID-19 Response 14 19 02 09 by Ragama Teaching ation Hospital during Covid period. LK-MOH-188841-GO-DIR Pending / 450 Nos Water Bottles Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- IDA / 65950 Post Direct Selection Direct 83.00 0.00 Implement procured by Ragama COVID-19 Response 14 19 02 09 ation Teaching Hospital during Covid period. Page 7 LK-MOH-188842-GO-DIR Pending / 02 Nos Toner Cartridges Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- IDA / 65950 Post Direct Selection Direct 47.00 0.00 Implement procured by Ragama COVID-19 Response 14 19 02 09 ation Teaching Hospital during Covid period. LK-MOH-188844-GO-DIR Pending / 547 Nos Polythene Aprons Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- IDA / 65950 Post Direct Selection Direct 144.00 0.00 Implement procured by Ragama COVID-19 Response 14 19 02 09 ation Teaching Hospital during Covid period. LK-MOH-188845-GO-DIR / Aluminium Bars Pending Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- construction of a quarantine IDA / 65950 Post Direct Selection Direct 190.00 0.00 Implement COVID-19 Response 14 19 02 09 center procured by Ragama ation Teaching Hospital during Covid period. LK-MOH-188847-GO-DIR Pending / Polythene for covid ward Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- IDA / 65950 Post Direct Selection Direct 643.00 0.00 Implement procured by Ragama COVID-19 Response 14 19 02 09 ation Teaching Hospital during Covid period. LK-MOH-188849-GO-DIR / 1000 Nos Polythene apron Pending Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- for corona ward procured by IDA / 65950 Post Direct Selection Direct 263.00 0.00 Implement COVID-19 Response 14 19 02 09 Ragama Teaching Hospital ation during Covid period. LK-MOH-188859-GO-DIR / 01 No Toner Cartridge for Pending Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- wards procured by Ragama IDA / 65950 Post Direct Selection Direct 42.00 0.00 Implement COVID-19 Response 14 19 02 09 Teaching Hospital during ation Covid period. LK-MOH-188860-GO-DIR Pending / 150 Nos Cotton Pillows Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- IDA / 65950 Post Direct Selection Direct 155.00 0.00 Implement procured by Ragama COVID-19 Response 14 19 02 09 ation Teaching Hospital during Covid period. LK-MOH-188863-GO-DIR / 53 Kg Polythene for PPE Pending Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- Item make procured by IDA / 65950 Post Direct Selection Direct 95.00 0.00 Implement COVID-19 Response 14 19 02 09 Ragama Teaching Hospital ation during Covid period LK-MOH-188864-GO-DIR / Hi-tone Boss AMP with Pending Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- USB and microphone IDA / 65950 Post Direct Selection Direct 184.00 0.00 Implement COVID-19 Response 14 19 02 09 procured by Ragama ation Teaching Hospital during Covid period. LK-MOH-188866-GO-DIR / Wax Ribbon & Art Paper Pending Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- Above items are procured IDA / 65950 Post Direct Selection Direct 120.00 0.00 Implement COVID-19 Response 14 19 02 09 by Ragama Teaching ation Hospital during Covid period. LK-MOH-188867-GO-DIR Pending / Pijama Kit for Office Staff Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- IDA / 65950 Post Direct Selection Direct 52.00 0.00 Implement procured by Ragama COVID-19 Response 14 19 02 09 ation Teaching Hospital during Covid period. LK-MOH-188868-GO-DIR / Surf Exel & Sunlight Pending Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- Powder (For SSSD & Covid- IDA / 65950 Post Direct Selection Direct 364.00 0.00 Implement COVID-19 Response 14 19 02 09 19 ward) procured by ation Ragama Teaching Hospital during Covid period. LK-MOH-188870-GO-DIR Pending / 04 Nos Tyre for Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- IDA / 65950 Post Direct Selection Direct 509.00 0.00 Implement Ambulance procured by COVID-19 Response 14 19 02 09 ation Ragama Teaching Hospital during Covid period. LK-MOH-188871-GO-DIR / Access Electronic Door Pending Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- Lock ( For Covid lab) IDA / 65950 Post Direct Selection Direct 575.00 0.00 Implement COVID-19 Response 14 19 02 09 procured by Ragama ation Teaching Hospital during Covid period. LK-MOH-188873-GO-DIR Pending / Air Purifier (For Covid Lab) Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- IDA / 65950 Post Direct Selection Direct 443.00 0.00 Implement procured by Ragama COVID-19 Response 14 19 02 09 ation Teaching Hospital during Covid period LK-MOH-188875-GO-DIR / 30 Kg Polythene for Apron Pending Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- make for ward & unit IDA / 65950 Post Direct Selection Direct 90.00 0.00 Implement COVID-19 Response 14 19 02 09 procured by Ragama ation Teaching Hospital during Covid period. LK-MOH-188876-GO-DIR / 30 Nos LED panel lights Pending Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- for ward procured by IDA / 65950 Post Direct Selection Direct 76.00 0.00 Implement COVID-19 Response 14 19 02 09 Ragama Teaching Hospital ation during Covid period. LK-MOH-188879-GO-DIR Pending / 06 Nos Plywood sheets Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- IDA / 65950 Post Direct Selection Direct 114.00 0.00 Implement procured by Ragama COVID-19 Response 14 19 02 09 ation Teaching Hospital during Covid period. LK-MOH-188882-GO-DIR Pending / 24 Nos chock (Philips) Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- IDA / 65950 Post Direct Selection Direct 88.00 0.00 Implement procured by Ragama COVID-19 Response 14 19 02 09 ation Teaching Hospital during Covid period LK-MOH-188883-GO-DIR Pending / 130 Ltrs Acid procured by Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- IDA / 65950 Post Direct Selection Direct 10.00 0.00 Implement Ragama Teaching Hospital COVID-19 Response 14 19 02 09 ation during Covid period. LK-MOH-188885-GO-DIR Pending / 01 No Lactogen Milk Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- IDA / 65950 Post Direct Selection Direct 3.00 0.00 Implement Powder procured by Ragama COVID-19 Response 14 19 02 09 ation Teaching Hospital during Covid period. LK-MOH-188887-GO-DIR Pending / Electrical Accessories for Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- IDA / 65950 Post Direct Selection Direct 45.00 0.00 Implement Lab procured by Ragama COVID-19 Response 14 19 02 09 ation Teaching Hospital during Covid period. LK-MOH-188888-GO-DIR Pending / Zip lock Bags PCR Lab Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- IDA / 65950 Post Direct Selection Direct 20.00 0.00 Implement procured by Ragama COVID-19 Response 14 19 02 09 ation Teaching Hospital during Covid period. LK-MOH-188890-GO-DIR Pending / 06 Nos LED Bulbs -MICU Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- IDA / 65950 Post Direct Selection Direct 45.00 0.00 Implement procured by Ragama COVID-19 Response 14 19 02 09 ation Teaching Hospital during Covid period. LK-MOH-188895-GO-DIR Pending / 10 Nos LED Driver -Lab Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- IDA / 65950 Post Direct Selection Direct 21.00 0.00 Implement procured by Ragama COVID-19 Response 14 18 01 08 ation Teaching Hospital during Covid period. LK-MOH-188966-GO-DIR Pending / 04 Nos Mobile Phones Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- IDA / 65950 Post Direct Selection Direct 21.00 0.00 Implement procured by Ragama COVID-19 Response 16 21 04 11 ation Teaching Hospital during Covid period. LK-MOH-188973-GO-DIR / 01 Nob Pre Nan Milk Pending Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- Powder Tin procured by IDA / 65950 Post Direct Selection Direct 6.00 0.00 Implement COVID-19 Response 16 21 04 11 Ragama Teaching Hospital ation during Covid period. LK-MOH-188974-GO-DIR / 01 No Electrical Pending Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- Accessories for Lab IDA / 65950 Post Direct Selection Direct 14.00 0.00 Implement COVID-19 Response 16 21 04 11 procured by Ragama ation Teaching Hospital during Covid period. LK-MOH-188976-GO-DIR / 05 Nos Lactogen Pending Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- powdered milk for covid IDA / 65950 Post Direct Selection Direct 16.00 0.00 Implement COVID-19 Response 16 21 04 11 wards procured by Ragama ation Teaching Hospital during Covid period. LK-MOH-188977-GO-DIR Pending / 02 Nos 40 Amp MCB Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- IDA / 65950 Post Direct Selection Direct 29.00 0.00 Implement procured by Ragama COVID-19 Response 16 21 04 11 ation Teaching Hospital during Covid period. LK-MOH-188981-GO-DIR Pending / 735 Nos Polythene Aprons Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- IDA / 65950 Post Direct Selection Direct 193.00 0.00 Implement procured by Ragama COVID-19 Response 16 21 04 11 ation Teaching Hospital during Covid period. LK-MOH-188982-GO-DIR / 102 Nos Nos Polythene Pending Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- Aprons procured by Ragama IDA / 65950 Post Direct Selection Direct 27.00 0.00 Implement COVID-19 Response 16 21 04 11 Teaching Hospital during ation Covid period. LK-MOH-188984-GO-DIR Pending / Mortine - Coved Lab Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- IDA / 65950 Post Direct Selection Direct 23.00 0.00 Implement procured by Ragama COVID-19 Response 16 21 04 11 ation Teaching Hospital during Covid period. LK-MOH-188986-GO-DIR / 99.65 Kg Polythene to Pending Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- make PPE items procured by IDA / 65950 Post Direct Selection Direct 192.00 0.00 Implement COVID-19 Response 16 21 04 11 Ragama Teaching Hospital ation during Covid period. LK-MOH-188989-GO-DIR Pending / Sponge Sheets procured Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- IDA / 65950 Post Direct Selection Direct 108.00 0.00 Implement by Ragama Teaching COVID-19 Response 16 21 04 11 ation Hospital during Covid period. LK-MOH-188991-GO-DIR / 197.3 Kg Polythene to Pending Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- make PPE Items procured by IDA / 65950 Post Direct Selection Direct 353.00 0.00 Implement COVID-19 Response 16 21 04 11 Ragama Teaching Hospital ation during Covid period. LK-MOH-189017-GO-DIR Pending / Electrical Accessories Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- IDA / 65950 Post Direct Selection Direct 34.00 0.00 Implement procured by Ragama COVID-19 Response 16 21 04 11 ation Teaching Hospital during Covid period. LK-MOH-189021-GO-DIR Pending / Network Accessories Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- IDA / 65950 Post Direct Selection Direct 23.00 0.00 Implement procured by Ragama COVID-19 Response 16 21 04 11 ation Teaching Hospital during Covid period. LK-MOH-189022-GO-DIR Pending / 167 Nos Polythene Aprons Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- IDA / 65950 Post Direct Selection Direct 44.00 0.00 Implement procured by Ragama COVID-19 Response 16 21 04 11 ation Teaching Hospital during Covid period LK-MOH-189023-GO-DIR Pending / Stapler Machine procured Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- IDA / 65950 Post Direct Selection Direct 13.00 0.00 Implement by Ragama Teaching COVID-19 Response 16 21 04 11 ation Hospital during Covid period LK-MOH-189024-GO-DIR Pending / Pijama Kit For hospital Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- IDA / 65950 Post Direct Selection Direct 489.00 0.00 Implement Staff procured by Ragama COVID-19 Response 16 21 04 11 ation Teaching Hospital during Covid period. LK-MOH-189025-GO-DIR Pending / Pijama Kit For hospital Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- IDA / 65950 Post Direct Selection Direct 739.00 0.00 Implement Staff procured by Ragama COVID-19 Response 16 21 04 11 ation Teaching Hospital during Covid period. LK-MOH-189026-GO-DIR Pending / Air Conditioner For Covid Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- IDA / 65950 Post Direct Selection Direct 655.00 0.00 Implement Lab procured by Ragama COVID-19 Response 16 21 04 11 ation Teaching Hospital during Covid period. LK-MOH-189027-GO-DIR / Ceiling fans for staff rest Pending Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- rooms procured by Ragama IDA / 65950 Post Direct Selection Direct 232.00 0.00 Implement COVID-19 Response 16 21 04 11 Teaching Hospital during ation Covid period. LK-MOH-189028-GO-DIR Pending / Server rack for Pathology Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- IDA / 65950 Post Direct Selection Direct 522.00 0.00 Implement lab procured by Ragama COVID-19 Response 16 21 04 11 ation Teaching Hospital during Covid period. LK-MOH-189029-GO-DIR / 01 No Refrigerator for Pending Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- covid ward procured by IDA / 65950 Post Direct Selection Direct 192.00 0.00 Implement COVID-19 Response 16 21 04 11 Ragama Teaching Hospital ation during Covid period. LK-MOH-189030-GO-DIR / Hardware Items for Pending Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- Maintenance unit procured IDA / 65950 Post Direct Selection Direct 404.00 0.00 Implement COVID-19 Response 16 21 04 11 by Ragama Teaching ation Hospital during Covid period. LK-MOH-189035-GO-RFQ / 500 Nos Extraction kits (Spinster Viral nucleic acid), 10000 Nos Novel corona PCR kit (Real-star SARS Pending Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-11- –COV-2 RT PCR Kit ,Altona), IDA / 65950 Post Limited 250,125.00 0.00 Implement COVID-19 Response Quotations Envelope 22 17 16 10000 Nos Novel corona ation positive control (ITD)(CDC Protocol) and other consumables procured by Anuradhapura Teaching Hospital LK-MOH-189036-GO-RFQ / 20000 Nos PCR tubes 0.2ml, 10000 Nos PCR strip Pending tubes and caps 0.1 ml Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-11- IDA / 65950 Post Limited 23,447.00 0.00 Implement Qiagen, and 5000 Nos Viral COVID-19 Response Quotations Envelope 22 17 16 ation transport procured by Anuradhapura Teaching Hospital during Corona period LK-MOH-189037-GO-RFQ / 300 Nos Sample collection Pending Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-11- tube e NAT procured by IDA / 65950 Post Limited 938.00 0.00 Implement COVID-19 Response Quotations Envelope 22 17 16 Anuradhapura Teaching ation Hospital during Corona period LK-MOH-189278-GO-DIR Pending Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- / Surgical Gloves procured IDA / 65950 Post Direct Selection Direct 419,240.00 0.00 Implement COVID-19 Response 18 23 13 27 by MSD during Covid period ation LK-MOH-189281-GO-DIR / Examination Gloves Pending Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- procured by MSD during IDA / 65950 Post Direct Selection Direct 196,830.00 0.00 Implement COVID-19 Response 18 23 13 27 Covid period from Sisili ation Projects Consortium (PVT) Ltd LK-MOH-189286-GO-DIR / Alcohol Based Hand Rub Pending Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- procured by MSD during IDA / 65950 Post Direct Selection Direct 74,503.00 0.00 Implement COVID-19 Response 18 23 13 27 Covid period from Suraksha ation Pharma (Pvt) Ltd LK-MOH-189294-GO-DIR Pending / Alcohol Based Hand Rub Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- IDA / 65950 Post Direct Selection Direct 91,917.00 0.00 Implement procured by MSD during COVID-19 Response 18 23 13 27 ation Covid period from Medicom (Pvt) Ltd LK-MOH-189396-GO-RFQ Pending / 05 Nos Micro Pippets Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-10- IDA / 65950 Post Limited 5,053.00 0.00 Implement procured by Badulla General COVID-19 Response Quotations Envelope 24 12 26 ation Hospital during Covid period. LK-MOH-189397-GO-RFQ Pending / 01 No Heat Block procured Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-10- IDA / 65950 Post Limited 426.00 0.00 Implement by Badulla General Hospital COVID-19 Response Quotations Envelope 24 12 26 ation during Covid period. LK-MOH-189398-GO-RFQ Pending / 783 Nos Overall Kits Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-10- IDA / 65950 Post Limited 5,257.00 0.00 Implement procured by Badulla General COVID-19 Response Quotations Envelope 24 12 26 ation Hospital during Covid period. LK-MOH-189399-GO-RFQ Pending / 10 Nos Infrared Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-10- IDA / 65950 Post Limited 974.00 0.00 Implement Thermometers procured by COVID-19 Response Quotations Envelope 24 12 26 ation Badulla General Hospital during Covid period. LK-MOH-189738-GO-DIR Pending Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- / Sisili Surgical Gloves IDA / 65950 Post Direct Selection Direct 196,830.00 0.00 Implement COVID-19 Response 21 26 16 30 procured by MSD during ation Covid period LK-MOH-189739-GO-DIR Pending / Medicon Alcohol Based Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- IDA / 65950 Post Direct Selection Direct 91,917.00 0.00 Implement Hand Rub procured by MSD COVID-19 Response 21 26 16 30 ation during Covid period LK-MOH-189740-GO-DIR Pending / Suraksha Alcohol Based Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- IDA / 65950 Post Direct Selection Direct 74,503.00 0.00 Implement Hand Rub procured by MSD COVID-19 Response 21 26 16 30 ation during Covid period from Suraksha LK-MOH-189744-GO-RFQ Pending / 2500 Nos Garbage Bags Component 1: Emergency Request for Single Stage - One 2020-08- 2020-09- 2020-09- IDA / 65950 Post Limited 183.00 0.00 Implement procured by IDH during COVID-19 Response Quotations Envelope 26 23 30 ation Covid period Page 8 LK-MOH-189745-GO-RFQ Pending / 100000 Nos Grocery Bags Component 1: Emergency Request for Single Stage - One 2020-08- 2020-09- 2020-09- IDA / 65950 Post Limited 274.00 0.00 Implement procured by IDH during COVID-19 Response Quotations Envelope 26 23 30 ation Covid period. LK-MOH-189746-GO-DIR Pending Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- / 01 No PCT Kit procured by IDA / 65950 Post Direct Selection Direct 1,886.00 0.00 Implement COVID-19 Response 21 26 09 16 IDH during Covid period. ation LK-MOH-189760-GO-DIR / Sisili Surgical Gloves Component 1: Emergency 2020-08- 2020-09- 2020-08- 2020-09- 2020-09- 2020-09- 2020-09- IDA / 65950 Post Direct Selection Direct 1,646,981.00 1,898,463.31 Signed procured by MSD during COVID-19 Response 21 01 26 07 16 14 30 Covid period from Sisili LK-MOH-189762-GO-DIR / Sisili Examination Gloves Component 1: Emergency 2020-08- 2020-09- 2020-08- 2020-09- 2020-09- 2020-09- 2020-09- IDA / 65950 Post Direct Selection Direct 451,105.00 618,281.56 Signed procured by MSD during COVID-19 Response 21 01 26 01 16 08 30 Covid period from Sisili LK-MOH-189767-GO-RFQ / 300 Numbers Pillow Case Pending 26"x18" (Quarantine Ward Component 1: Emergency Request for Single Stage - One 2020-08- 2020-09- 2020-10- IDA / 65950 Post Limited 261.00 0.00 Implement No 5) procured by COVID-19 Response Quotations Envelope 26 23 07 ation Kalubowila Teaching Hospital during Covid period. LK-MOH-189768-GO-RFQ / 02 Nos Air Water Cooler Pending Model Smart 30+ Brand - Component 1: Emergency Request for Single Stage - One 2020-08- 2020-09- 2020-10- IDA / 65950 Post Limited 442.00 0.00 Implement Cello (For Isolation Unit) COVID-19 Response Quotations Envelope 26 23 07 ation procured by Kalubowila Teaching Hospital during Covid period. LK-MOH-189769-GO-RFQ / 01 No Phillips Hair Dryer Pending Machine (2 years Warranty) Component 1: Emergency Request for Single Stage - One 2020-08- 2020-09- 2020-10- IDA / 65950 Post Limited 42.00 0.00 Implement (For Isolation Unit) procured COVID-19 Response Quotations Envelope 26 23 07 ation by Kalubowila Teaching Hospital during Covid period. LK-MOH-189771-GO-RFQ / 01 No Washing Machine- Capacity 8kg Drying 6kg Pending Component 1: Emergency Request for Single Stage - One 2020-08- 2020-09- 2020-10- 100% dryer. (For Isolation IDA / 65950 Post Limited 1,026.00 0.00 Implement COVID-19 Response Quotations Envelope 26 23 07 Unit) procured by ation Kalubowila Teaching Hospital during Covid period. LK-MOH-189772-GO-RFQ / 02 Nos 30m Magic Hose With Multiple Spray Gun and Pending Component 1: Emergency Request for Single Stage - One 2020-08- 2020-09- 2020-10- tap Socket (For Isolation IDA / 65950 Post Limited 105.00 0.00 Implement COVID-19 Response Quotations Envelope 26 23 07 Unit) procured by ation Kalubowila Teaching Hospital during Covid period. LK-MOH-189773-GO-RFQ / 02 nos Folding tent 10x10 with power coated iron rod Pending and with a waterproof Component 1: Emergency Request for Single Stage - One 2020-08- 2020-09- 2020-10- IDA / 65950 Post Limited 284.00 0.00 Implement canvas cover (OPD triage COVID-19 Response Quotations Envelope 26 23 07 ation area) procured by Kalubowila Teaching Hospital during Covid period. LK-MOH-189775-GO-DIR / 50 Nos KDK Ceiling Fan Pending N56RG (For OPD triage area Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- IDA / 65950 Post Direct Selection Direct 203.00 0.00 Implement and Isolation Unit) procured COVID-19 Response 21 26 09 23 ation by Kalubowila Teaching Hospital during Covid period. LK-MOH-189776-GO-RFQ / 300 Mtrs 100% Cotton Sheeting Fabric- Blue Colour Pending Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-10- ( Prepare doctors Overall to IDA / 65950 Post Limited 6,237.00 0.00 Implement COVID-19 Response Quotations Envelope 26 07 21 personal protection) ation procured by Kalubowila Teaching Hospital during Covid period. LK-MOH-189780-GO-RFQ / 50 Nos Inferred Pending thermometer (For Hospital Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-10- IDA / 65950 Post Limited 4,211.00 0.00 Implement words and clinics) procured COVID-19 Response Quotations Envelope 26 07 21 ation by Kalubowila Teaching Hospital during Covid period. LK-MOH-189786-GO-RFQ Pending / 12 Nos Banner Stand Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-10- IDA / 65950 Post Limited 123.00 0.00 Implement procured by Polonnaruwa COVID-19 Response Quotations Envelope 26 07 21 ation Hospital during Covid period. LK-MOH-189809-GO-RFQ / Hardware items for Pending Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-10- Aluminium Partitioning work IDA / 65950 Post Limited 2,560.00 0.00 Implement COVID-19 Response Quotations Envelope 26 07 21 at Polonnaruwa Hospital ation during Covid period. LK-MOH-189811-GO-RFQ Pending / Hardware items for Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-10- IDA / 65950 Post Limited 102.00 0.00 Implement Plumbing at Polonnaruwa COVID-19 Response Quotations Envelope 26 07 21 ation Hospital during Covid period LK-MOH-189812-GO-RFQ Pending / 100 Nos PURIFIER Sanitizer Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-10- IDA / 65950 Post Limited 4,474.00 0.00 Implement procured by Polonnaruwa COVID-19 Response Quotations Envelope 26 07 21 ation Hospital during Covid period LK-MOH-189814-GO-RFQ Pending / Electrical consumables Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-10- IDA / 65950 Post Limited 227.00 0.00 Implement procured by Polonnaruwa COVID-19 Response Quotations Envelope 26 07 21 ation Hospital during Covid period LK-MOH-189816-GO-RFQ / 02 Nos Water heater Jug Pending Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-10- and 04 Nos Emergency Led IDA / 65950 Post Limited 37.00 0.00 Implement COVID-19 Response Quotations Envelope 26 07 21 light procured by ation Polonnaruwa Hospital during Covid period LK-MOH-189819-GO-RFQ Pending / Tools & Accessories Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-10- IDA / 65950 Post Limited 1,997.00 0.00 Implement procured by Polonnaruwa COVID-19 Response Quotations Envelope 26 07 21 ation Hospital during Covid period LK-MOH-189821-GO-RFQ Pending / 400 Pkts Photocopy Paper Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-10- IDA / 65950 Post Limited 1,455.00 0.00 Implement A 4 size procured by COVID-19 Response Quotations Envelope 26 07 21 ation Polonnaruwa Hospital during Covid period LK-MOH-189824-GO-RFQ / Shopping Bags, Plastic Pending Broom, Washing Powder and Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-10- IDA / 65950 Post Limited 3,984.00 0.00 Implement Hand Wash procured by COVID-19 Response Quotations Envelope 26 07 21 ation Polonnaruwa Hospital during Covid period LK-MOH-189827-GO-RFQ / 2000 Lts General Purpose (Teepole), 300 Ltrs Pending Disinfectant Cleaner (Lysol) Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-10- IDA / 65950 Post Limited 5,446.00 0.00 Implement and Toilet Bowl Cleaner COVID-19 Response Quotations Envelope 26 07 21 ation (Harpic) procured by Polonnaruwa Hospital during Covid period. LK-MOH-189831-GO-RFQ Pending / 120 Ltrs Clorex procured Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-10- IDA / 65950 Post Limited 993.00 0.00 Implement by Polonnaruwa Hospital COVID-19 Response Quotations Envelope 26 07 21 ation during Covid period. LK-MOH-189834-GO-RFQ / Electrical wiring consumables (Baton Holder/ Pending Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-10- Screw Nails/ Floater IDA / 65950 Post Limited 35.00 0.00 Implement COVID-19 Response Quotations Envelope 26 07 21 switch/Conduit joint ation Sockets) procured by Polonnaruwa Hospital during Covid period. LK-MOH-189837-GO-RFQ / Electrical Consumables (CFL Pin Type Bulbs/ Round Pending Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-10- Block/ Emergency Lamp/ IDA / 65950 Post Limited 146.00 0.00 Implement COVID-19 Response Quotations Envelope 26 07 21 Conduit bend & clips) ation procured by Polonnaruwa Hospital during Covid period. LK-MOH-189841-GO-RFQ / Cleaning Items (Mob Pending Bucket/Toilet Soap/ Ekal Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-10- IDA / 65950 Post Limited 1,287.00 0.00 Implement Broom/ Tile Brush) procured COVID-19 Response Quotations Envelope 26 07 21 ation by Polonnaruwa Hospital during Covid period. LK-MOH-189845-GO-RFQ / 30000 Nos Shopping Bags Pending Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-10- & 50000 Grocery Bags IDA / 65950 Post Limited 574.00 0.00 Implement COVID-19 Response Quotations Envelope 26 07 21 procured by Polonnaruwa ation Hospital during Covid period. LK-MOH-189847-GO-RFQ / 80000 Nos Garbage Bags Pending Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-10- -Black procured by IDA / 65950 Post Limited 3,952.00 0.00 Implement COVID-19 Response Quotations Envelope 26 07 21 Polonnaruwa Hospital ation during Covid period. LK-MOH-189849-GO-RFQ / 12 Nos Saucepans, 100 Nos Plastic bowl , 30 Ns Shoe Racks, 30 nos Plastic Pending Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-10- Basin, 20Kg Polythene, 3000 IDA / 65950 Post Limited 965.00 0.00 Implement COVID-19 Response Quotations Envelope 26 07 21 Nos Plastic Brooms & 5000 ation Nos Blade procured by Polonnaruwa Hospital during Covid period. LK-MOH-189852-GO-RFQ / 400 Nos Pijama Kits, 500 Nos Surgeon Overall Kits & Pending Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-10- 500 Nos Surgeon Overall Kit IDA / 65950 Post Limited 10,989.00 0.00 Implement COVID-19 Response Quotations Envelope 26 07 21 - Wraparound procured by ation Polonnaruwa Hospital during Covid period. LK-MOH-189857-GO-RFQ / 750 Check Cloth - Cotton Pending & 750 White Bed Sheet - Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-10- IDA / 65950 Post Limited 4,926.00 0.00 Implement Sheeting procured by COVID-19 Response Quotations Envelope 26 07 21 ation Polonnaruwa Hospital during Covid period LK-MOH-189861-GO-RFQ / Hardware Items procured Pending Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-10- by Polonnaruwa Hospital IDA / 65950 Post Limited 8,826.00 0.00 Implement COVID-19 Response Quotations Envelope 26 07 21 during Covid period from ation Almet Enterprises LK-MOH-189863-GO-RFQ / Hardware items procured Pending Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-10- by Polonnaruwa Hospital IDA / 65950 Post Limited 731.00 0.00 Implement COVID-19 Response Quotations Envelope 26 07 21 during Covid period from ation Isuru Hardware LK-MOH-189983-GO-RFQ / Paint ans painting Pending Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-10- consumables procured by IDA / 65950 Post Limited 394.00 0.00 Implement COVID-19 Response Quotations Envelope 29 10 24 Polonnaruwa Hospital ation during Covid period. LK-MOH-189987-GO-RFQ Pending / Steel Hardware items Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-10- IDA / 65950 Post Limited 296.00 0.00 Implement procured by Polonnaruwa COVID-19 Response Quotations Envelope 29 10 24 ation Hospital during Covid period. LK-MOH-189989-GO-RFQ Pending / Silicon gum procured by Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-10- IDA / 65950 Post Limited 33.00 0.00 Implement Polonnaruwa Hospital COVID-19 Response Quotations Envelope 29 10 24 ation during Covid period. LK-MOH-189990-GO-RFQ / Hardware items for Pending Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-10- Aluminium partitioning IDA / 65950 Post Limited 2,314.00 0.00 Implement COVID-19 Response Quotations Envelope 29 10 24 work procured by ation Polonnaruwa Hospital during Covid period. LK-MOH-189993-GO-RFQ Pending / Electrical consumables Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-10- IDA / 65950 Post Limited 132.00 0.00 Implement procured by Polonnaruwa COVID-19 Response Quotations Envelope 29 10 24 ation Hospital during Covid period. LK-MOH-189994-GO-RFQ / 01 No Rice Cooker and Pending Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-10- 100 Nos Multi plug Base IDA / 65950 Post Limited 328.00 0.00 Implement COVID-19 Response Quotations Envelope 29 10 24 procured by Polonnaruwa ation Hospital during Covid period. LK-MOH-189996-GO-RFQ / 01 No. Gas Cooker, 01 No Pending Hot Plate, 02 Nos Television Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-10- IDA / 65950 Post Limited 1,830.00 0.00 Implement and 02 Nos Coping Machine COVID-19 Response Quotations Envelope 29 10 24 ation procured by Polonnaruwa Hospital during Covid period. LK-MOH-190000-GO-RFQ Pending / 01 No. Photocopy Machine Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-10- IDA / 65950 Post Limited 608.00 0.00 Implement procured by Polonnaruwa COVID-19 Response Quotations Envelope 29 10 24 ation Hospital during Covid period. LK-MOH-190002-GO-RFQ / 100 Nos Basket, 50 Nos Pending Pillows, 50 Nos Mosquito Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-10- IDA / 65950 Post Limited 487.00 0.00 Implement Nets and 250 Mtrs White COVID-19 Response Quotations Envelope 29 10 24 ation Polythene procured by Polonnaruwa Hospital during Covid period. LK-MOH-190114-GO-RFQ Pending / 100 nos Multi Plug Base Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-10- IDA / 65950 Post Limited 305.00 0.00 Implement procured by Polonnaruwa COVID-19 Response Quotations Envelope 30 11 25 ation Hospital during Covid period. LK-MOH-190115-GO-RFQ / 30Nos Wall Clocks & 30 Pending Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-10- Nos Re-chargeable Torches IDA / 65950 Post Limited 251.00 0.00 Implement COVID-19 Response Quotations Envelope 30 11 25 procured by Polonnaruwa ation Hospital during Covid period. LK-MOH-190116-GO-RFQ Pending / 29 Nos Air Conditioning Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-10- IDA / 65950 Post Limited 20,475.00 0.00 Implement Units procured by COVID-19 Response Quotations Envelope 30 11 25 ation Polonnaruwa Hospital during Covid period. LK-MOH-190117-GO-RFQ / 70 Nos Led Bulbs, 25 Nos Pending Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-10- Bulb Holders & 50 Mtrs T T IDA / 65950 Post Limited 98.00 0.00 Implement COVID-19 Response Quotations Envelope 30 11 25 Cables procured by ation Polonnaruwa Hospital during Covid period. LK-MOH-190118-GO-RFQ Pending / 50 Nos 3/4" Conduit Pipe Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-10- IDA / 65950 Post Limited 21.00 0.00 Implement procured by Polonnaruwa COVID-19 Response Quotations Envelope 30 11 25 ation Hospital during Covid period. LK-MOH-190119-GO-RFQ / 06 Nos Working Pending Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-10- Cupboards & 05 Nos Towel IDA / 65950 Post Limited 1,395.00 0.00 Implement COVID-19 Response Quotations Envelope 30 11 25 Racks (Large) procured by ation Polonnaruwa Hospital during Covid period. LK-MOH-190120-GO-RFQ / 30 Nos MDF/Melamine Tables, 30 Nos Pending MDF/Melamine Altamira, 20 Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-10- IDA / 65950 Post Limited 4,889.00 0.00 Implement Nos Book Racks, 20 Shoe COVID-19 Response Quotations Envelope 30 11 25 ation Racks & 3 Nos Mirrors procured by Polonnaruwa Hospital during Covid period. LK-MOH-190121-GO-RFQ / 60 Ltrs Emulsion Paints, Pending 60 Ltrs Weather Guard Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-10- IDA / 65950 Post Limited 554.00 0.00 Implement Paints & 100 Nos Sand COVID-19 Response Quotations Envelope 30 11 25 ation Papers procured by Polonnaruwa Hospital during Covid period. LK-MOH-190122-GO-RFQ Pending / 04 Ltrs Floor Paints Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-10- IDA / 65950 Post Limited 15.00 0.00 Implement procured by Polonnaruwa COVID-19 Response Quotations Envelope 30 11 25 ation Hospital during Covid period. LK-MOH-190123-GO-RFQ / 20 Nos Stand Fans and 30 Pending Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-10- Nos Ceiling Fans procured IDA / 65950 Post Limited 1,842.00 0.00 Implement COVID-19 Response Quotations Envelope 30 11 25 by Polonnaruwa Hospital ation during Covid period. LK-MOH-190126-GO-RFQ / 02 Nos Polythene Sealer, Pending 50 Nos Sink Brush & 25 Nos Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-10- IDA / 65950 Post Limited 2,731.00 0.00 Implement Shopping Trolley procured COVID-19 Response Quotations Envelope 30 11 25 ation by Polonnaruwa Hospital during Covid period. LK-MOH-190128-GO-RFQ / 200 Nos Pillow Case, 60 Pending Nos Half Shoes & 04 Nos Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-10- IDA / 65950 Post Limited 102.00 0.00 Implement Carrot Beater procured by COVID-19 Response Quotations Envelope 30 11 25 ation Polonnaruwa Hospital during Covid period. Page 9 LK-MOH-190130-GO-RFQ / 50 Nos Racer & 300 Nos Pending Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-10- Toilet Bowl Cleaner IDA / 65950 Post Limited 212.00 0.00 Implement COVID-19 Response Quotations Envelope 30 11 25 procured by Polonnaruwa ation Hospital during Covid period. LK-MOH-190135-GO-RFQ Pending / 200 Nos Plastic Brooms Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-10- IDA / 65950 Post Limited 189.00 0.00 Implement procured by Polonnaruwa COVID-19 Response Quotations Envelope 30 11 25 ation Hospital during Covid period. LK-MOH-190136-GO-RFQ Pending / 150 Nos Commode Brush Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-10- IDA / 65950 Post Limited 103.00 0.00 Implement procured by Polonnaruwa COVID-19 Response Quotations Envelope 30 11 25 ation Hospital during Covid period. LK-MOH-190137-GO-RFQ / 40 Nos 18 W Panel Light Pending (Surface) and electrical Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-10- IDA / 65950 Post Limited 1,742.00 0.00 Implement Consumables procured by COVID-19 Response Quotations Envelope 30 11 25 ation Polonnaruwa Hospital during Covid period. LK-MOH-190140-GO-RFQ / 100 Nos Multi Plug Base 13Amp, 100 Nos 18 W Pending Blasters, 400 Mtrs 1.044 Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-10- IDA / 65950 Post Limited 720.00 0.00 Implement Electric Cables & 200 nos 18 COVID-19 Response Quotations Envelope 30 11 25 ation W Pin Type CFL Bulbs procured by Polonnaruwa Hospital during Covid period. LK-MOH-190145-GO-RFQ / 25 Nos Ceiling Rose, 15 Pending Nos Wall Clocks & 05 Nos Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-10- IDA / 65950 Post Limited 199.00 0.00 Implement Multi function AC Remote COVID-19 Response Quotations Envelope 30 11 25 ation procured by Polonnaruwa Hospital during Covid period. LK-MOH-190153-GO-RFQ / 100 Nos One Way Sunk Pending Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-10- Box & 100 Nos Two Way IDA / 65950 Post Limited 65.00 0.00 Implement COVID-19 Response Quotations Envelope 30 11 25 Sunk Boxes procured by ation Polonnaruwa Hospital during Covid period. LK-MOH-190156-GO-RFQ Pending / Steel Hardware items Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-10- IDA / 65950 Post Limited 22,014.00 0.00 Implement procured by Polonnaruwa COVID-19 Response Quotations Envelope 30 11 25 ation Hospital during Covid period. LK-MOH-190158-GO-RFQ Pending / Electrical Consumables Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-10- IDA / 65950 Post Limited 421.00 0.00 Implement procured by Polonnaruwa COVID-19 Response Quotations Envelope 30 11 25 ation Hospital during Covid period. LK-MOH-190161-GO-RFQ Pending / Hardware items procured Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-10- IDA / 65950 Post Limited 411.00 0.00 Implement by Polonnaruwa Hospital COVID-19 Response Quotations Envelope 30 11 25 ation during Covid period. LK-MOH-190162-GO-RFQ Pending / 10 Nos Desk top Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-10- IDA / 65950 Post Limited 6,211.00 0.00 Implement Computers procured by COVID-19 Response Quotations Envelope 30 11 25 ation Polonnaruwa Hospital during Covid period. LK-MOH-190163-GO-RFQ Pending / 20000 Nos Lunch Sheets Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-10- IDA / 65950 Post Limited 158.00 0.00 Implement procured by Polonnaruwa COVID-19 Response Quotations Envelope 30 11 25 ation Hospital during Covid period. LK-MOH-190165-GO-RFQ / 04 Nos Reception Tables & Pending Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-10- 12 Nos Bunker Beds with IDA / 65950 Post Limited 8,748.00 0.00 Implement COVID-19 Response Quotations Envelope 30 11 25 Ladders procured by ation Polonnaruwa Hospital during Covid period. LK-MOH-190168-GO-RFQ / 20 Nos Toner for Toshiba Pending Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-10- E Studio Photocopier IDA / 65950 Post Limited 1,228.00 0.00 Implement COVID-19 Response Quotations Envelope 30 11 25 procured by Polonnaruwa ation Hospital during Covid period. LK-MOH-190172-GO-RFQ / 15 Nos Keyocera TASKalfa Pending Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-10- 1800 Toner procured by IDA / 65950 Post Limited 1,006.00 0.00 Implement COVID-19 Response Quotations Envelope 30 11 25 Polonnaruwa Hospital ation during Covid period. LK-MOH-190173-GO-RFQ Pending / Electrical Consumables Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-10- IDA / 65950 Post Limited 868.00 0.00 Implement procured by Polonnaruwa COVID-19 Response Quotations Envelope 30 11 25 ation Hospital during Covid period. LK-MOH-190176-GO-RFQ / 08 Nos 1"Conduit Pipes Pending Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-10- and 01 No Two Pole IDA / 65950 Post Limited 6.00 0.00 Implement COVID-19 Response Quotations Envelope 30 11 25 Connector Box procured by ation Polonnaruwa Hospital during Covid period. LK-MOH-190177-GO-RFQ Pending / Electrical Consumables Component 1: Emergency Request for Single Stage - One 2020-09- 2020-10- 2020-10- IDA / 65950 Post Limited 121.00 0.00 Implement procured by Polonnaruwa COVID-19 Response Quotations Envelope 05 17 31 ation Hospital during Covid period. LK-MOH-190178-GO-RFQ Pending / Electrical Consumables Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-10- IDA / 65950 Post Limited 498.00 0.00 Implement procured by Polonnaruwa COVID-19 Response Quotations Envelope 30 11 25 ation Hospital during Covid period. LK-MOH-190179-GO-RFQ Pending / 10000 Lunch Sheets Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-10- IDA / 65950 Post Limited 79.00 0.00 Implement procured by Polonnaruwa COVID-19 Response Quotations Envelope 30 11 25 ation Hospital during Covid period. LK-MOH-190180-GO-RFQ Pending / Hardware Items procured Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-10- IDA / 65950 Post Limited 284.00 0.00 Implement by Polonnaruwa Hospital COVID-19 Response Quotations Envelope 30 11 25 ation during Covid period. LK-MOH-190183-GO-RFQ Pending / Paints & Painting Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-10- IDA / 65950 Post Limited 219.00 0.00 Implement consumables procured by COVID-19 Response Quotations Envelope 30 11 25 ation Polonnaruwa Hospital during Covid period. LK-MOH-190184-GO-RFQ Pending / Electrical consumables Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-10- IDA / 65950 Post Limited 1,449.00 0.00 Implement procured by Polonnaruwa COVID-19 Response Quotations Envelope 30 11 25 ation Hospital during Covid period. LK-MOH-190185-GO-RFQ Pending / 03 Nos Transport Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-10- IDA / 65950 Post Limited 30,711.00 0.00 Implement Ventilators procured by COVID-19 Response Quotations Envelope 30 11 25 ation Polonnaruwa Hospital during Covid period. LK-MOH-190186-GO-RFQ Pending / 20 Nos Digital BP Meters Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-10- IDA / 65950 Post Limited 635.00 0.00 Implement procured by Polonnaruwa COVID-19 Response Quotations Envelope 30 11 25 ation Hospital during Covid period. LK-MOH-190189-GO-RFQ / 10 Nos Calibration Cartridges, 10 Nos Rinsing Solutions MATA, 10 Nos Pending Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-10- Rinsing Solutions BAG ISE IDA / 65950 Post Limited 11,751.00 0.00 Implement COVID-19 Response Quotations Envelope 30 11 25 and Consumables Rinsing ation Solutions procured by Polonnaruwa Hospital during Covid period. LK-MOH-190299-GO-RFQ Pending / 03 Units of ICU Ventilators Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-10- IDA / 65950 Post Limited 47,368.00 0.00 Implement procured by Polonnaruwa COVID-19 Response Quotations Envelope 31 12 26 ation Hospital during Covid period. LK-MOH-190300-GO-RFQ / 01 Unit Bio Safety Cabinet (Double Use), 01 Unit Sealed Pending Bucket Safety Cabinet Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-10- IDA / 65950 Post Limited 29,921.00 0.00 Implement Centrifuge and 05 Part COVID-19 Response Quotations Envelope 31 12 26 ation Hematology Analyser procured by Polonnaruwa Hospital during Covid period. LK-MOH-190301-GO-RFQ / 01 Unit Portable Digital X- Pending Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-10- ray Machine procured by IDA / 65950 Post Limited 52,368.00 0.00 Implement COVID-19 Response Quotations Envelope 31 12 26 Polonnaruwa Hospital ation during Covid period. LK-MOH-190302-GO-RFQ Pending / 03 Unit Transport Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-10- IDA / 65950 Post Limited 30,711.00 0.00 Implement Ventilator procured by COVID-19 Response Quotations Envelope 31 12 26 ation Polonnaruwa Hospital during Covid period. LK-MOH-190303-GO-RFQ Pending / 02 Units ECG Machines Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-10- IDA / 65950 Post Limited 4,305.00 0.00 Implement procured by Polonnaruwa COVID-19 Response Quotations Envelope 31 12 26 ation Hospital during Covid period. LK-MOH-190304-GO-RFQ Pending / 04 Nos Video Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-10- IDA / 65950 Post Limited 12,526.00 0.00 Implement Leryngeoscope procured by COVID-19 Response Quotations Envelope 31 12 26 ation Polonnaruwa Hospital during Covid period. LK-MOH-190306-GO-RFQ Pending / 06 Nos Defibrillators Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-10- IDA / 65950 Post Limited 31,136.00 0.00 Implement procured by Polonnaruwa COVID-19 Response Quotations Envelope 31 12 26 ation Hospital during Covid period. LK-MOH-190307-GO-RFQ / 50 Nos Stethoscope & 100 Pending Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-10- Nos BP Operators procured IDA / 65950 Post Limited 7,066.00 0.00 Implement COVID-19 Response Quotations Envelope 31 12 26 by Polonnaruwa Hospital ation during Covid period. LK-MOH-190308-GO-RFQ Pending / 10 Nos Infrared Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-10- IDA / 65950 Post Limited 934.00 0.00 Implement Thermometers procured by COVID-19 Response Quotations Envelope 31 12 26 ation Polonnaruwa Hospital during Covid period. LK-MOH-190310-GO-RFQ / 10 Nos Suction Apparatus Pending Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-10- - Double Jar procured by IDA / 65950 Post Limited 15,711.00 0.00 Implement COVID-19 Response Quotations Envelope 31 12 26 Polonnaruwa Hospital ation during Covid period. LK-MOH-190312-GO-RFQ Pending / 01 No Portable RO Plant Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-10- IDA / 65950 Post Limited 2,368.00 0.00 Implement procured by Polonnaruwa COVID-19 Response Quotations Envelope 31 12 26 ation Hospital during Covid period. LK-MOH-190314-GO-RFQ Pending / 08 Nos Bi PAP procured by Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-10- IDA / 65950 Post Limited 49,705.00 0.00 Implement Polonnaruwa Hospital COVID-19 Response Quotations Envelope 31 12 26 ation during Covid period. LK-MOH-190329-GO-RFQ Pending / 05 Nos ICU Beds procured Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-10- IDA / 65950 Post Limited 13,118.00 0.00 Implement by Polonnaruwa Hospital COVID-19 Response Quotations Envelope 31 12 26 ation during Covid period. LK-MOH-190332-GO-RFQ / Supply & Installation of 1 Pending Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-10- Unit AC And Ventilation IDA / 65950 Post Limited 39,960.00 0.00 Implement COVID-19 Response Quotations Envelope 31 12 26 System procured by ation Polonnaruwa Hospital during Covid period. LK-MOH-190339-GO-RFQ Pending / 01 No Centrifuge procured Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-10- IDA / 65950 Post Limited 5,263.00 0.00 Implement by Ragama Teaching COVID-19 Response Quotations Envelope 31 12 26 ation Hospital during Covid period. LK-MOH-190340-GO-RFQ / 03 Nos Screen Laryngeal Pending Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-10- set for five blades procured IDA / 65950 Post Limited 3,553.00 0.00 Implement COVID-19 Response Quotations Envelope 31 12 26 by Ragama Teaching ation Hospital during Covid period. LK-MOH-190341-GO-RFQ Pending / 01 no H2O2 Vapor Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-10- IDA / 65950 Post Direct Selection Direct 4,711.00 0.00 Implement system procured by Ragama COVID-19 Response 26 31 21 05 ation Teaching Hospital during Covid period LK-MOH-190342-GO-RFQ / 01 No Point of care testing Pending Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-10- (POCT) Immunol Analyzer IDA / 65950 Post Limited 2,895.00 0.00 Implement COVID-19 Response Quotations Envelope 31 12 26 procured by Ragama ation Teaching Hospital during Covid period. LK-MOH-190345-GO-RFQ Pending / 01 No Server Rack for Lab Component 1: Emergency 2020-08- 2020-08- 2020-10- 2021-04- IDA / 65950 Post Direct Selection Direct 522.00 0.00 Implement procured by Ragama COVID-19 Response 26 31 05 03 ation Teaching Hospital during Covid period. LK-MOH-190346-GO-RFQ Pending / 01 No Electric Door Lock Component 1: Emergency 2020-08- 2020-08- 2020-10- 2021-04- IDA / 65950 Post Direct Selection Direct 575.00 0.00 Implement procured by Ragama COVID-19 Response 26 31 05 03 ation Teaching Hospital during Covid period. LK-MOH-190348-GO-RFQ / Furniture for Patient Pending Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-10- Waiting Area procured by IDA / 65950 Post Limited 1,032.00 0.00 Implement COVID-19 Response Quotations Envelope 31 12 26 Ragama Teaching Hospital ation during Covid period. LK-MOH-190350-GO-RFQ / Furniture for Patient Pending Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-10- Waiting Area procured by IDA / 65950 Post Limited 462.00 0.00 Implement COVID-19 Response Quotations Envelope 31 12 26 Ragama Teaching Hospital ation during Covid period. LK-MOH-190352-GO-RFQ / Furniture for Patient Pending Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-10- waiting area procured by IDA / 65950 Post Limited 807.00 0.00 Implement COVID-19 Response Quotations Envelope 31 12 26 Ragama Teaching Hospital ation during Covid period. LK-MOH-190355-GO-DIR Pending / 04 Nos Ambulance Tyre Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-10- IDA / 65950 Post Direct Selection Direct 509.00 0.00 Implement procured by Ragama COVID-19 Response 26 31 21 05 ation Teaching Hospital during Covid period. LK-MOH-190357-GO-RFQ Pending / 50 nos Mattresses Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-10- IDA / 65950 Post Limited 1,039.00 0.00 Implement procured by Ragama COVID-19 Response Quotations Envelope 31 12 26 ation Teaching Hospital during Covid period. LK-MOH-190358-GO-RFQ Pending / 01 Unit Centrifuge Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-10- IDA / 65950 Post Limited 5,201.00 0.00 Implement procured by Ragama COVID-19 Response Quotations Envelope 31 12 26 ation Teaching Hospital during Covid period. LK-MOH-190360-GO-DIR / 5000 Nos A4 Size Pending Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-10- Transparent Sheets IDA / 65950 Post Direct Selection Direct 237.00 0.00 Implement COVID-19 Response 26 31 21 05 procured by Ragama ation Teaching Hospital during Covid period. LK-MOH-190413-GO-RFQ Pending / Bathroom Fittings Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2021-04- IDA / 65950 Post Limited 264.00 0.00 Implement procured by Rathnapura COVID-19 Response Quotations Envelope 31 05 03 ation General Hospital during Covid period. LK-MOH-190422-GO-DIR / Electrical Consumables Pending Component 1: Emergency 2020-08- 2020-08- 2020-10- 2021-04- procured by Rathnapura IDA / 65950 Post Direct Selection Direct 247.00 0.00 Implement COVID-19 Response 26 31 05 03 General Hospital during ation Covid period. LK-MOH-190424-GO-RFQ / Polythene, Gum Tape and Pending Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-10- Formica stick Glue procured IDA / 65950 Post Limited 346.00 0.00 Implement COVID-19 Response Quotations Envelope 31 05 12 by Rathnapura General ation Hospital during Covid period. LK-MOH-190432-GO-RFQ / Instruments & Consumables to commence Pending Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-10- COVID-19 RT-PCR Test IDA / 65950 Post Limited 1,462.00 0.00 Implement COVID-19 Response Quotations Envelope 31 05 12 procured by Rathnapura ation General Hospital during Covid period. (Advance) LK-MOH-190437-GO-RFQ / Instruments & Consumables to commence Pending Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-10- COVID-19 RT-PCR Test IDA / 65950 Post Limited 1,277.00 0.00 Implement COVID-19 Response Quotations Envelope 31 05 12 procured by Rathnapura ation General Hospital during Covid period. (Retroactive) LK-MOH-190441-GO-RFQ / Consumables to Pending commence COVID-19 RT- Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-10- IDA / 65950 Post Limited 233.00 0.00 Implement PCR Test procured by COVID-19 Response Quotations Envelope 31 05 12 ation Rathnapura General Hospital during Covid period. Page 10 LK-MOH-190442-GO-RFQ / Consumables & Pending instruments related to nCoV Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-10- IDA / 65950 Post Limited 1,269.00 0.00 Implement RT-PCR test procured by COVID-19 Response Quotations Envelope 31 05 12 ation Rathnapura General Hospital during Covid period. LK-MOH-190445-GO-RFQ / PCR Tubes for 7500 Pending Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-10- FASTO PCR Machine IDA / 65950 Post Limited 3,204.00 0.00 Implement COVID-19 Response Quotations Envelope 31 05 12 procured by Rathnapura ation General Hospital during Covid period. LK-MOH-190631-GO-RFQ / 90 Nos Dust Bin 50 Ltr & Pending Component 1: Emergency Request for Single Stage - One 2020-09- 2020-09- 2020-10- 24 Nos Dust Bin 120 Ltr IDA / 65950 Post Limited 1,554.00 0.00 Implement COVID-19 Response Quotations Envelope 01 29 13 procured by Supply Division ation G during Covid period (Advance) LK-MOH-190632-GO-RFQ / 50 Nos Mattresses Pending Component 1: Emergency Request for Single Stage - One 2020-09- 2020-09- 2020-10- 72"x30"x4" & 30 Nos Water IDA / 65950 Post Limited 4,099.00 0.00 Implement COVID-19 Response Quotations Envelope 01 29 13 Dispensers procured by ation Supply Division G during Covid period LK-MOH-190633-GO-RFQ / 1000 Yard Polythene for Pending Component 1: Emergency Request for Single Stage - One 2020-09- 2020-09- 2020-10- Aprons procured by IDA / 65950 Post Limited 421.00 0.00 Implement COVID-19 Response Quotations Envelope 01 29 13 Kaluthara DGH G During ation Covid period (Advance) LK-MOH-190634-GO-RFQ / 10000 Nos Soap for Hand Washing , 10000 Nos Soap Pending Component 1: Emergency Request for Single Stage - One 2020-09- 2020-09- 2020-10- for Cloth washing & 1000 IDA / 65950 Post Limited 5,144.00 0.00 Implement COVID-19 Response Quotations Envelope 01 29 13 Kg Washing Powder ation procured by Kaluthara DGHG during Covid period (advance) LK-MOH-190635-GO-RFQ Pending / 210 Nos Surgeon Gowns Component 1: Emergency Request for Single Stage - One 2020-09- 2020-09- 2020-10- IDA / 65950 Post Limited 1,382.00 0.00 Implement procured by Kaluthara COVID-19 Response Quotations Envelope 01 29 13 ation DGHG during Covid period LK-MOH-190636-GO-RFQ Pending / 05 Nos normal Beds Component 1: Emergency Request for Single Stage - One 2020-09- 2020-09- 2020-10- IDA / 65950 Post Limited 554.00 0.00 Implement procured by Kaluthara COVID-19 Response Quotations Envelope 01 29 13 ation DGHG during Covid period LK-MOH-190638-GO-RFQ / 05 Nos Mattresses & 05 Pending Component 1: Emergency Request for Single Stage - One 2020-09- 2020-09- 2020-10- Nos Plastic Chairs procured IDA / 65950 Post Limited 737.00 0.00 Implement COVID-19 Response Quotations Envelope 01 29 13 by Kaluthara DGHG during ation Covid period LK-MOH-190639-GO-RFQ / 01 Nos 12000 BTU AC Machine, 03 Nos 18000 BTU Pending Component 1: Emergency Request for Single Stage - One 2020-09- 2020-09- 2020-10- AC Machines & 04 Nos IDA / 65950 Post Limited 5,468.00 0.00 Implement COVID-19 Response Quotations Envelope 01 29 13 24000 BTU AC Machines ation procured by Chilaw DGHG during Covid period LK-MOH-190642-GO-RFQ Pending / 01 No Centrifuge procured Component 1: Emergency Request for Single Stage - One 2020-09- 2020-10- 2020-10- IDA / 65950 Post Limited 5,263.00 0.00 Implement by Ragama Teaching COVID-19 Response Quotations Envelope 01 13 27 ation Hospital G during Covid period. LK-MOH-190644-GO-RFB / 01 Unit Point of Care Pending Testing BIOCHEMISTRY Component 1: Emergency Single Stage - One 2020-08- 2020-09- 2020-10- 2020-11- 2020-12- 2021-06- IDA / 65950 Post Request for Bids Open - National 6,579.00 0.00 Implement ANALYZER procured by COVID-19 Response Envelope 27 01 13 12 17 15 ation Ragama Teaching Hospital G during Covid period. LK-MOH-190647-GO-RFB / 01 Unit Bio Safety Cabinet Pending Component 1: Emergency Single Stage - One 2020-08- 2020-09- 2020-10- 2020-11- 2020-12- 2021-06- procured by Ragama IDA / 65950 Post Request for Bids Open - National 9,379.00 0.00 Implement COVID-19 Response Envelope 27 01 13 12 17 15 Teaching Hospital G during ation Covid period.(Advance) LK-MOH-190648-GO-RFQ / 07 Nos PCR reagent and Pending Consumables (Qlamp viral Component 1: Emergency Request for Single Stage - One 2020-09- 2020-10- 2020-10- IDA / 65950 Post Limited 9,470.00 0.00 Implement RNA Mini kit) procured by COVID-19 Response Quotations Envelope 01 06 13 ation Ragama Teaching Hospital during Covid period.(Advance) LK-MOH-190650-GO-RFQ / 06 Nos PCR reagent and Consumables (Artus e NAT Pending Component 1: Emergency Request for Single Stage - One 2020-09- 2020-10- 2020-10- collection kit 300) procured IDA / 65950 Post Limited 5,968.00 0.00 Implement COVID-19 Response Quotations Envelope 01 06 13 by Ragama Teaching ation Hospital G during Covid period (Advance) LK-MOH-190652-GO-RFQ / 100 Nos Face Shields, 100 Nos Long Sleeved impervious Gown, 200 Nos Pending Component 1: Emergency Request for Single Stage - One 2020-09- 2020-10- 2020-10- Face Shields & 200 Nos IDA / 65950 Post Limited 2,842.00 0.00 Implement COVID-19 Response Quotations Envelope 01 06 13 Long Sleeved impervious ation Gown procured by Ragama Teaching Hospital G during Covid period. (Advance) LK-MOH-190653-GO-RFQ / Hardware item for Repair Beds of Koran-tine center Pending Component 1: Emergency Request for Single Stage - One 2020-09- 2020-10- 2020-10- plywood sheet,wring nails IDA / 65950 Post Limited 815.00 0.00 Implement COVID-19 Response Quotations Envelope 01 06 13 Hand saw etc procured by ation Ragama Teaching Hospital G during Covid period.(Advance) LK-MOH-190654-GO-RFQ Pending / 200 Nos N 95 Masks Component 1: Emergency Request for Single Stage - One 2020-09- 2020-10- 2020-10- IDA / 65950 Post Limited 344.00 0.00 Implement procured by Karapitiya TGH COVID-19 Response Quotations Envelope 01 06 13 ation G during Covid period. LK-MOH-190655-GO-RFQ / 50 Nos Spin Star Viral Pending Component 1: Emergency Request for Single Stage - One 2020-09- 2020-10- 2020-10- nucleic Acid Extraction kit IDA / 65950 Post Limited 21,316.00 0.00 Implement COVID-19 Response Quotations Envelope 01 06 13 Karapitiya Teaching Hospital ation G during Covid period. (Advance) LK-MOH-190656-GO-RFQ / 1000 Nos Naso Pending pharyngeal Swab Nobs Component 1: Emergency Request for Single Stage - One 2020-09- 2020-10- 2020-10- IDA / 65950 Post Limited 2,368.00 0.00 Implement procured by Karapitiya COVID-19 Response Quotations Envelope 01 06 13 ation Teaching Hospital G during Covid period. (Advance) LK-MOH-190657-GO-RFQ / 01 No Point of Care Pending Component 1: Emergency Request for Single Stage - One 2020-09- 2020-10- 2020-10- Testing Devise procured by IDA / 65950 Post Limited 6,579.00 0.00 Implement COVID-19 Response Quotations Envelope 01 06 13 Karapitiya Teaching Hospital ation G during Covid period. LK-MOH-190658-GO-RFQ / Hardware items procured Component 1: Emergency Request for Single Stage - One 2020-09- 2020-09- 2020-10- 2020-09- 2020-10- by Polonnaruwa Hospital G IDA / 65950 Post Limited 14.00 14.04 Signed COVID-19 Response Quotations Envelope 01 01 13 10 27 during Covid period. (Advance) LK-MOH-190678-GO-DIR / Hardware Items procured Under Component 1: Emergency 2020-08- 2020-09- 2020-09- 2020-09- 2020-09- 2020-10- by Polonnaruwa General IDA / 65950 Post Direct Selection Direct 30.00 0.00 Implement COVID-19 Response 27 01 01 01 22 06 Hospital G during Covid ation period. (Advance) LK-MOH-190679-GO-RFQ Pending / Hardware Items procured Component 1: Emergency Request for Single Stage - One 2020-09- 2020-10- 2020-10- IDA / 65950 Post Limited 342.00 0.00 Implement by Polonnaruwa Hospital G COVID-19 Response Quotations Envelope 01 13 27 ation during Covid period. LK-MOH-190681-GO-RFQ / Electrical Consumables Component 1: Emergency Request for Single Stage - One 2020-09- 2020-09- 2020-10- 2020-09- 2020-10- procured by Polonnaruwa IDA / 65950 Post Limited 4,970.00 5,120.78 Signed COVID-19 Response Quotations Envelope 01 01 13 10 27 Hospital G during Covid period. (Advance) LK-MOH-190692-GO-RFQ / Electrical Consumables Component 1: Emergency Request for Single Stage - One 2020-09- 2020-09- 2020-10- 2020-09- 2020-10- procured by Polonnaruwa IDA / 65950 Post Limited 1,111.00 1,140.73 Signed COVID-19 Response Quotations Envelope 01 01 13 10 27 Hospital G during Covid period. LK-MOH-190696-GO-RFQ / Hardware Items procured Component 1: Emergency Request for Single Stage - One 2020-09- 2020-09- 2020-10- 2020-09- 2020-10- IDA / 65950 Post Limited 195.00 201.22 Signed by Polonnaruwa Hospital G COVID-19 Response Quotations Envelope 01 01 13 10 27 during Covid period. LK-MOH-190700-GO-RFQ / 150 Nos 20 W CFL Bulbs Component 1: Emergency Request for Single Stage - One 2020-09- 2020-09- 2020-10- 2020-09- 2020-10- procured by Polonnaruwa IDA / 65950 Post Limited 355.00 366.05 Signed COVID-19 Response Quotations Envelope 01 01 13 10 27 Hospital G during Covid period. LK-MOH-190705-GO-RFQ / Hardware Items procured Component 1: Emergency Request for Single Stage - One 2020-09- 2020-09- 2020-10- 2020-09- 2020-10- IDA / 65950 Post Limited 451.00 464.32 Signed by Polonnaruwa Hospital G COVID-19 Response Quotations Envelope 01 01 13 11 27 during Covid period.(Advance) LK-MOH-190707-GO-RFQ / 115 Nos Roofing Sheets Pending Component 1: Emergency Request for Single Stage - One 2020-09- 2020-10- 2020-10- procured by Polonnaruwa IDA / 65950 Post Limited 266.00 0.00 Implement COVID-19 Response Quotations Envelope 01 13 27 Hospital G during Covid ation period. (Advance) LK-MOH-190708-GO-RFQ / Hardware Items procured Component 1: Emergency Request for Single Stage - One 2020-09- 2020-09- 2020-10- 2020-09- 2020-10- IDA / 65950 Post Limited 1,148.00 1,178.95 Signed by Polonnaruwa Hospital G COVID-19 Response Quotations Envelope 01 01 13 10 27 during Covid period. LK-MOH-190710-GO-RFQ / Hardware Items procured Component 1: Emergency Request for Single Stage - One 2020-09- 2020-09- 2020-10- 2020-09- 2020-10- IDA / 65950 Post Limited 8.00 7.92 Signed by Polonnaruwa Hospital G COVID-19 Response Quotations Envelope 01 01 13 10 27 during Covid period. LK-MOH-190714-GO-RFQ / Hardware Items procured Component 1: Emergency Request for Single Stage - One 2020-09- 2020-09- 2020-10- 2020-09- 2020-10- IDA / 65950 Post Limited 30.00 31.14 Signed by Polonnaruwa Hospital G COVID-19 Response Quotations Envelope 01 01 13 10 27 during Covid period. LK-MOH-190720-GO-RFQ / Hardware items procured Pending Component 1: Emergency Request for Single Stage - One 2020-09- 2020-10- 2020-10- by Polonnaruwa Hospital G IDA / 65950 Post Limited 411.00 0.00 Implement COVID-19 Response Quotations Envelope 01 13 27 during Covid period. ation (Advance) LK-MOH-190744-GO-RFQ / Hardware Items procured Component 1: Emergency Request for Single Stage - One 2020-09- 2020-09- 2020-10- 2020-09- 2020-10- by Polonnaruwa Hospital G IDA / 65950 Post Limited 125.00 30.82 Signed COVID-19 Response Quotations Envelope 01 01 13 10 27 during Covid period. (Advance) LK-MOH-190746-GO-RFQ / Hardware Items procured Pending Component 1: Emergency Request for Single Stage - One 2020-09- 2020-10- 2020-10- by Polonnaruwa Hospital G IDA / 65950 Post Limited 383.00 0.00 Implement COVID-19 Response Quotations Envelope 01 13 27 during Covid period. ation (Advance) LK-MOH-190747-GO-RFQ / Electrical Consumables Under Component 1: Emergency Request for Single Stage - One 2020-09- 2020-09- 2020-10- 2020-10- procured by Polonnaruwa IDA / 65950 Post Limited 27.00 28.01 Implement COVID-19 Response Quotations Envelope 01 01 13 27 Hospital G during Covid ation period. (Advance) LK-MOH-190749-GO-RFQ / 02 Nos Haylese Power Sprayers procured by Component 1: Emergency Request for Single Stage - One 2020-09- 2020-09- 2020-10- 2020-09- 2020-10- IDA / 65950 Post Limited 197.00 202.16 Signed Polonnaruwa Hospital G COVID-19 Response Quotations Envelope 01 01 13 10 27 during Covid period. (Advance) LK-MOH-190750-GO-RFQ / 04 Nos 1"x1" Box Bars & 04 Nos 1x1/2 Reducing Component 1: Emergency Request for Single Stage - One 2020-09- 2020-09- 2020-10- 2020-09- 2020-10- IDA / 65950 Post Limited 34.00 34.72 Signed Tee procured by COVID-19 Response Quotations Envelope 01 01 13 10 27 Polonnaruwa Hospital G during Covid period. (Advance) LK-MOH-190752-GO-RFQ / 01 No Septic Tank with Pending Component 1: Emergency Request for Single Stage - One 2020-09- 2020-10- 2020-10- Transport procured by IDA / 65950 Post Limited 203.00 0.00 Implement COVID-19 Response Quotations Envelope 01 13 27 Polonnaruwa Hospital G ation during Covid period. LK-MOH-190753-GO-RFQ / Hardware Items procured Component 1: Emergency Request for Single Stage - One 2020-09- 2020-09- 2020-10- 2020-09- 2020-10- by Polonnaruwa Hospital G IDA / 65950 Post Limited 580.00 594.07 Signed COVID-19 Response Quotations Envelope 01 01 13 10 27 during Covid period. (Advance) LK-MOH-190755-GO-RFQ / Household Items procured Component 1: Emergency Request for Single Stage - One 2020-09- 2020-09- 2020-10- 2020-09- 2020-10- by Polonnaruwa Hospital G IDA / 65950 Post Limited 2,414.00 2,951.50 Signed COVID-19 Response Quotations Envelope 01 01 13 10 27 during Covid period. (Advance) LK-MOH-190758-GO-RFQ Pending / Hardware Items procured Component 1: Emergency Request for Single Stage - One 2020-09- 2020-10- 2020-10- IDA / 65950 Post Limited 588.00 0.00 Implement by Polonnaruwa Hospital G COVID-19 Response Quotations Envelope 01 13 27 ation during Covid period. LK-MOH-190765-GO-RFQ / Household Items procured Pending Component 1: Emergency Request for Single Stage - One 2020-09- 2020-10- 2020-10- by Polonnaruwa Hospital G IDA / 65950 Post Limited 2,362.00 0.00 Implement COVID-19 Response Quotations Envelope 01 13 27 during Covid period. ation (Advance) LK-MOH-190770-GO-RFQ / Stationery Items procured Component 1: Emergency Request for Single Stage - One 2020-09- 2020-09- 2020-10- 2020-09- 2020-10- by Polonnaruwa Hospital G IDA / 65950 Post Limited 51.00 52.23 Signed COVID-19 Response Quotations Envelope 01 01 13 10 27 during Covid period. (Advance) LK-MOH-190775-GO-RFQ / 08 Items of Doctor Component 1: Emergency Request for Single Stage - One 2020-09- 2020-09- 2020-10- 2020-09- 2020-10- Overalls, Pijamas & Towels IDA / 65950 Post Limited 9,416.00 9,672.89 Signed COVID-19 Response Quotations Envelope 01 01 13 10 27 procured by Polonnaruwa Hospital G during Covid period. LK-MOH-190776-GO-RFQ / 01 No. Coffin procured by Pending Component 1: Emergency Request for Single Stage - One 2020-09- 2020-10- 2020-10- Polonnaruwa Hospital G IDA / 65950 Post Limited 263.00 0.00 Implement COVID-19 Response Quotations Envelope 01 13 27 during Covid period. ation (Advance) LK-MOH-190778-GO-RFQ / Hardware Items procured Component 1: Emergency Request for Single Stage - One 2020-09- 2020-09- 2020-10- 2020-09- 2020-10- by Polonnaruwa Hospital G IDA / 65950 Post Limited 7,540.00 7,743.68 Signed COVID-19 Response Quotations Envelope 01 01 13 10 27 during Covid period. (Advance) LK-MOH-190781-GO-RFQ / Household and Pending Miscellaneous items Component 1: Emergency Request for Single Stage - One 2020-09- 2020-10- 2020-10- IDA / 65950 Post Limited 476.00 0.00 Implement procured by Polonnaruwa COVID-19 Response Quotations Envelope 01 13 27 ation Hospital G during Covid period. (Advance) LK-MOH-190930-GO-RFQ / 02 Nos Washing Machines, Pending 01 No. Jukkie Machine & 01 Component 1: Emergency Request for Single Stage - One 2020-09- 2020-10- 2020-10- IDA / 65950 Post Limited 1,395.00 0.00 Implement No Refrigerator procured by COVID-19 Response Quotations Envelope 02 14 28 ation Anuradhapura TH during Covid period. LK-MOH-190931-GO-RFQ / 10 Nos Cupboards & 02 Pending Nos Mirror Cupboards Component 1: Emergency Request for Single Stage - One 2020-09- 2020-10- 2020-10- IDA / 65950 Post Limited 1,516.00 0.00 Implement procured by Anuradhapura COVID-19 Response Quotations Envelope 02 14 28 ation Teaching Hospital G during Covid period. LK-MOH-190932-GO-RFQ / 12 Nos Water Bottles & 20 Pending Nos Plastic Containers 70 Component 1: Emergency Request for Single Stage - One 2020-09- 2020-10- 2020-10- IDA / 65950 Post Limited 702.00 0.00 Implement Ltrs procured by COVID-19 Response Quotations Envelope 02 14 28 ation Anuradhapura Teaching Hospital G during Covid period. LK-MOH-190933-GO-RFQ / 16 Nos Hand Sprayers (16 Pending Component 1: Emergency Request for Single Stage - One 2020-09- 2020-10- 2020-10- L) procured by IDA / 65950 Post Limited 26.00 0.00 Implement COVID-19 Response Quotations Envelope 02 14 28 Anuradhapura Teaching ation Hospital G during Covid period. LK-MOH-190934-GO-RFQ / 01 No Plate Cutting Scissors, 150 Nos Gum Pending Component 1: Emergency Request for Single Stage - One 2020-09- 2020-10- 2020-10- Boots & 25 Nos Mattresses IDA / 65950 Post Limited 2,053.00 0.00 Implement COVID-19 Response Quotations Envelope 02 14 28 6'x3' procured by ation Anuradhapura Teaching Hospital G during Covid period. LK-MOH-190935-GO-RFQ / Household Items procured Pending Component 1: Emergency Request for Single Stage - One 2020-09- 2020-10- 2020-10- by Anuradhapura Teaching IDA / 65950 Post Limited 1,491.00 0.00 Implement COVID-19 Response Quotations Envelope 02 14 28 Hospital G during Covid ation period. Page 11 LK-MOH-190937-GO-RFQ / 65 Nos Dust Bins with Pending Component 1: Emergency Request for Single Stage - One 2020-09- 2020-10- 2020-10- paddle procured by IDA / 65950 Post Limited 428.00 0.00 Implement COVID-19 Response Quotations Envelope 02 14 28 Anuradhapura Teaching ation Hospital G during Covid period. LK-MOH-190938-GO-RFQ / 01 No Gas Stoves Single Pending Component 1: Emergency Request for Single Stage - One 2020-09- 2020-10- 2020-10- procured by Anuradhapura IDA / 65950 Post Limited 39.00 0.00 Implement COVID-19 Response Quotations Envelope 02 14 28 Teaching Hospital G during ation Covid period. LK-MOH-190939-GO-RFQ / 15 Nos Plastic Chairs Pending Component 1: Emergency Request for Single Stage - One 2020-09- 2020-10- 2020-10- procured by Anuradhapura IDA / 65950 Post Limited 87.00 0.00 Implement COVID-19 Response Quotations Envelope 02 14 28 Teaching Hospital G during ation Covid period. LK-MOH-190940-GO-RFQ / 03 Nos Electric Heater Pending Jugs & 16 Nos Hot Water Component 1: Emergency Request for Single Stage - One 2020-09- 2020-10- 2020-10- IDA / 65950 Post Limited 87.00 0.00 Implement Flasks procured by COVID-19 Response Quotations Envelope 02 14 28 ation Anuradhapura Teaching Hospital G during Covid period. LK-MOH-190941-GO-RFQ / 10 Nos Beds (Wooden) Pending Component 1: Emergency Request for Single Stage - One 2020-09- 2020-10- 2020-10- 6'x3' procured by IDA / 65950 Post Limited 711.00 0.00 Implement COVID-19 Response Quotations Envelope 02 14 28 Anuradhapura Teaching ation Hospital G during Covid period. LK-MOH-190942-GO-RFQ / 5000 Nos Soap for washing Hands, 1000 Nos Pending Component 1: Emergency Request for Single Stage - One 2020-09- 2020-10- 2020-10- Hand Wash & 5000 Pkts IDA / 65950 Post Limited 5,053.00 0.00 Implement COVID-19 Response Quotations Envelope 02 14 28 Paper Serviette procured by ation Anuradhapura Teaching Hospital G during Covid period. LK-MOH-190943-GO-RFQ / 250 Kg Polythene Roll 6" & Pending 250 Kg Polythene Roll 8" Component 1: Emergency Request for Single Stage - One 2020-09- 2020-10- 2020-10- IDA / 65950 Post Limited 1,221.00 0.00 Implement procured by Anuradhapura COVID-19 Response Quotations Envelope 02 14 28 ation Teaching Hospital G during Covid period. LK-MOH-190944-GO-RFQ / 400 Mtrs Poplin Cloth, 500 Nos Baby Pampas & 25 Pending Component 1: Emergency Request for Single Stage - One 2020-09- 2020-10- 2020-10- Nos Mob Buckets procured IDA / 65950 Post Limited 1,072.00 0.00 Implement COVID-19 Response Quotations Envelope 02 14 28 by Anuradhapura Teaching ation Hospital G during Covid period. LK-MOH-190946-GO-RFQ / 160 Mtrs Polythene Pending Component 1: Emergency Request for Single Stage - One 2020-09- 2020-10- 2020-10- procured by Anuradhapura IDA / 65950 Post Limited 17.00 0.00 Implement COVID-19 Response Quotations Envelope 02 14 28 Teaching Hospital G during ation Covid period. LK-MOH-190947-GO-RFQ / 100 Nos Regiform Bottles, 5100 Lunch Sheets & 25 Kg Pending Component 1: Emergency Request for Single Stage - One 2020-09- 2020-10- 2020-10- Wrapping Papers procured IDA / 65950 Post Limited 146.00 0.00 Implement COVID-19 Response Quotations Envelope 02 14 28 by Anuradhapura Teaching ation Hospital G during Covid period. LK-MOH-190948-GO-RFQ / 20 Nos 1"Cello Tape Roll, 500 Nos Yellow Garbage Pending Component 1: Emergency Request for Single Stage - One 2020-09- 2020-10- 2020-10- Bags (Large) & 200 Mtrs IDA / 65950 Post Limited 87.00 0.00 Implement COVID-19 Response Quotations Envelope 02 14 28 Wire procured by ation Anuradhapura Teaching Hospital G during Covid period. LK-MOH-190950-GO-RFQ / 180 Mtrs MACINTOSH Pending Component 1: Emergency Request for Single Stage - One 2020-09- 2020-10- 2020-10- (BLACK) procured by IDA / 65950 Post Limited 100.00 0.00 Implement COVID-19 Response Quotations Envelope 02 14 28 Anuradhapura Teaching ation Hospital G during Covid period. LK-MOH-190951-GO-RFQ Pending Component 1: Emergency Request for Single Stage - One 2020-09- 2020-10- 2020-10- / 100 Mtrs Poplin Cloth & IDA / 65950 Post Limited 921.00 0.00 Implement COVID-19 Response Quotations Envelope 02 14 28 500 Ns Baby Pampas ation LK-MOH-190952-GO-RFQ / 01 No Fan & 01 No Earth Pending Component 1: Emergency Request for Single Stage - One 2020-09- 2020-10- 2020-10- Rod procured by IDA / 65950 Post Limited 17.00 0.00 Implement COVID-19 Response Quotations Envelope 02 14 28 Anuradhapura Teaching ation Hospital G during Covid period. LK-MOH-190953-GO-RFQ / Electrical Consumables Pending Component 1: Emergency Request for Single Stage - One 2020-09- 2020-10- 2020-10- procured by Anuradhapura IDA / 65950 Post Limited 64.00 0.00 Implement COVID-19 Response Quotations Envelope 02 14 28 Teaching Hospital G during ation Covid period. LK-MOH-190954-GO-RFQ / 02 Units ICU Ventilator For Adult and peadiactric Component 1: Emergency Request for Single Stage - One 2020-09- 2020-09- 2020-10- 2020-09- 2020-10- IDA / 65950 Post Limited 47,526.00 55,387.45 Signed machine procured by COVID-19 Response Quotations Envelope 02 01 14 14 28 Anuradhapura Teaching Hospital G during Covid period. LK-MOH-190958-GO-RFQ / Leflunomide tab.20 mg Component 1: Emergency Request for Single Stage - One 2020-09- 2020-09- 2020-10- 2020-09- 2021-04- IDA / 65950 Post Limited 69,236.00 71,011.32 Signed procured by MSD during COVID-19 Response Quotations Envelope 02 06 28 08 26 Covid period (Advance) LK-MOH-190962-GO-RFQ Pending / Morphine Sulfate CR tab Component 1: Emergency Request for Single Stage - One 2020-09- 2020-10- 2021-04- IDA / 65950 Post Limited 69,236.00 0.00 Implement 10mg procured by by MSD COVID-19 Response Quotations Envelope 02 28 26 ation during Covid period. (Advance) LK-MOH-190963-GO-RFQ Pending / Sodium bicarbonate for IV Component 1: Emergency Request for Single Stage - One 2020-09- 2020-10- 2021-04- IDA / 65950 Post Limited 119,368.00 0.00 Implement use 8.4% ,50 ml procured by COVID-19 Response Quotations Envelope 02 28 26 ation by MSD during Covid period LK-MOH-190965-GO-RFQ Pending Component 1: Emergency Request for Single Stage - One 2020-09- 2020-10- 2021-04- / Clotrimazole IDA / 65950 Post Limited 3,563.00 0.00 Implement COVID-19 Response Quotations Envelope 02 28 26 1%+Lignocaine 2%Ear drops ation 10ml vial LK-MOH-190968-GO-RFQ Pending / Beta methasone Lotion Component 1: Emergency Request for Single Stage - One 2020-09- 2020-10- 2021-04- IDA / 65950 Post Limited 36,947.00 0.00 Implement 0.05%, 50ml bot procured COVID-19 Response Quotations Envelope 02 28 26 ation by by MSD during Covid period LK-MOH-190971-GO-RFQ Pending / Doxycycline hydrochloride Component 1: Emergency Request for Single Stage - One 2020-09- 2020-10- 2021-04- IDA / 65950 Post Limited 52,895.00 0.00 Implement Cap. 100mg procured by by COVID-19 Response Quotations Envelope 02 28 26 ation MSD during Covid period LK-MOH-190973-GO-RFQ / Doxycycline hydrochloride Pending Component 1: Emergency Request for Single Stage - One 2020-09- 2020-10- 2021-04- Cap. 100 mg procured by by IDA / 65950 Post Limited 55,263.00 0.00 Implement COVID-19 Response Quotations Envelope 02 28 26 MSD during Covid period ation (Advance) LK-MOH-190974-GO-RFQ / Ipratropium Br. Pending Component 1: Emergency Request for Single Stage - One 2020-09- 2020-10- 2021-04- Resp.sol0.25mg/1ml,15ml IDA / 65950 Post Limited 47,869.00 0.00 Implement COVID-19 Response Quotations Envelope 02 28 26 procured by by MSD during ation Covid period. (Advance) LK-MOH-190975-GO-RFQ / Dobutamine Inj. Component 1: Emergency Request for Single Stage - One 2020-09- 2020-09- 2020-10- 2020-09- 2021-04- IDA / 65950 Post Limited 84,884.00 87,048.94 Signed 250mg/20ml procured by COVID-19 Response Quotations Envelope 02 01 28 09 26 by MSD during Covid period. (Advance) LK-MOH-190976-GO-RFQ Pending / Duloxetine (hydrochloride) Component 1: Emergency Request for Single Stage - One 2020-09- 2020-10- 2021-04- IDA / 65950 Post Limited 3,769.00 0.00 Implement 20 mg Capsules procured COVID-19 Response Quotations Envelope 02 28 26 ation by by MSD during Covid period LK-MOH-190977-GO-RFQ Pending / Iron Drops 50mg/ml, in Component 1: Emergency Request for Single Stage - One 2020-09- 2020-10- 2021-04- IDA / 65950 Post Limited 29,800.00 0.00 Implement 15ml dropper procured by COVID-19 Response Quotations Envelope 02 28 26 ation by MSD during Covid period (Advance) LK-MOH-190980-GO-RFQ Pending / Amiodarone injection Component 1: Emergency Request for Single Stage - One 2020-09- 2020-10- 2021-04- IDA / 65950 Post Limited 44,737.00 0.00 Implement 150mg/3ml procured by by COVID-19 Response Quotations Envelope 02 28 26 ation MSD during Covid period LK-MOH-190982-GO-RFQ Pending / Adenosine inj. 6 mg/2 ml Component 1: Emergency Request for Single Stage - One 2020-09- 2020-10- 2021-04- IDA / 65950 Post Limited 125,678.00 0.00 Implement procured by by MSD during COVID-19 Response Quotations Envelope 02 28 26 ation Covid period. (Advance) LK-MOH-190984-GO-RFQ / Ketamine HCl Inj. 500 mg/ Pending Component 1: Emergency Request for Single Stage - One 2020-09- 2020-10- 2021-04- 10ml procured by by MSD IDA / 65950 Post Limited 10,516.00 0.00 Implement COVID-19 Response Quotations Envelope 02 28 26 during Covid period. ation (Advance) LK-MOH-190987-GO-RFQ / Clomipramine HCI tab Pending Component 1: Emergency Request for Single Stage - One 2020-09- 2020-10- 2021-04- 25mg Vial procured by by IDA / 65950 Post Limited 14,093.00 0.00 Implement COVID-19 Response Quotations Envelope 02 28 26 MSD during Covid period. ation (Advance) LK-MOH-190991-GO-RFQ Pending / Methyl predinisolone IV inj Component 1: Emergency Request for Single Stage - One 2020-09- 2020-10- 2021-04- IDA / 65950 Post Limited 47,629.00 0.00 Implement 1g Vial procured by by MSD COVID-19 Response Quotations Envelope 02 28 26 ation during Covid period LK-MOH-190993-GO-RFQ Pending Component 1: Emergency Request for Single Stage - One 2020-09- 2020-10- 2021-04- / 0.2% Chlorohexidine IDA / 65950 Post Limited 26,526.00 0.00 Implement COVID-19 Response Quotations Envelope 02 28 26 Mouth Wash 100 ml bottle ation LK-MOH-190994-GO-RFQ Pending Component 1: Emergency Request for Single Stage - One 2020-09- 2020-10- 2021-04- / Pethidine hydrochloride IDA / 65950 Post Limited 41,874.00 0.00 Implement COVID-19 Response Quotations Envelope 02 28 26 Inj. 50 mg ation LK-MOH-190995-GO-RFQ Pending / Clobazam tablet 5mg Component 1: Emergency Request for Single Stage - One 2020-09- 2020-10- 2021-04- IDA / 65950 Post Limited 8,736.00 0.00 Implement procured by by MSD during COVID-19 Response Quotations Envelope 02 28 26 ation Covid period LK-MOH-190999-GO-RFQ Pending / Prednisolone Tablet 20mg Component 1: Emergency Request for Single Stage - One 2020-09- 2020-10- 2021-04- IDA / 65950 Post Limited 18,724.00 0.00 Implement procured by by MSD during COVID-19 Response Quotations Envelope 02 28 26 ation Covid period LK-MOH-191001-GO-RFQ Pending / Levofloxacin Tab. 500mg Component 1: Emergency Request for Single Stage - One 2020-09- 2020-10- 2021-04- IDA / 65950 Post Limited 4,013.00 0.00 Implement procured by by MSD during COVID-19 Response Quotations Envelope 02 28 26 ation Covid period LK-MOH-191002-GO-RFQ Pending / Fluconazole Cap. 50mg Component 1: Emergency Request for Single Stage - One 2020-09- 2020-10- 2021-04- IDA / 65950 Post Limited 2,021.00 0.00 Implement procured by by MSD during COVID-19 Response Quotations Envelope 02 28 26 ation Covid period LK-MOH-191005-GO-RFQ Pending / Oseltami vir cap.45mg Component 1: Emergency Request for Single Stage - One 2020-09- 2020-10- 2021-04- IDA / 65950 Post Limited 67,308.00 0.00 Implement procured by by MSD during COVID-19 Response Quotations Envelope 02 28 26 ation Covid period LK-MOH-191006-GO-RFQ Pending / Moxifloxacin ophthalmic Component 1: Emergency Request for Single Stage - One 2020-09- 2020-10- 2021-04- IDA / 65950 Post Limited 9,955.00 0.00 Implement solutn. 0.5%,5ml procured COVID-19 Response Quotations Envelope 02 28 26 ation by by MSD during Covid period LK-MOH-191008-GO-RFQ Pending Component 1: Emergency Request for Single Stage - One 2020-09- 2020-10- 2021-04- / Di clofenac sodium supp. IDA / 65950 Post Limited 3,752.00 0.00 Implement COVID-19 Response Quotations Envelope 02 28 26 25 mg ation LK-MOH-191010-GO-RFQ Pending / Suxamethonium chloride Component 1: Emergency Request for Single Stage - One 2020-09- 2020-10- 2021-04- IDA / 65950 Post Limited 40,895.00 0.00 Implement inj.100mg/2ml procured by COVID-19 Response Quotations Envelope 02 28 26 ation by MSD during Covid period LK-MOH-191013-GO-RFQ Pending / Clotrimazole pessaries Component 1: Emergency Request for Single Stage - One 2020-09- 2020-10- 2021-04- IDA / 65950 Post Limited 3,754.00 0.00 Implement 100 mg procured by by COVID-19 Response Quotations Envelope 02 28 26 ation MSD during Covid period LK-MOH-191014-GO-RFQ Pending / Pancuronium bromide inj. Component 1: Emergency Request for Single Stage - One 2020-09- 2020-10- 2021-04- IDA / 65950 Post Limited 75,000.00 0.00 Implement 4mg/2ml procured by by COVID-19 Response Quotations Envelope 02 28 26 ation MSD during Covid period LK-MOH-191015-GO-RFQ Pending / Prednisolone Syr.5mg / Component 1: Emergency Request for Single Stage - One 2020-09- 2020-10- 2021-04- IDA / 65950 Post Limited 8,499.00 0.00 Implement 5ml ,60ml procured by by COVID-19 Response Quotations Envelope 02 28 26 ation MSD during Covid period LK-MOH-191016-GO-RFQ / Fluticasone + Component 1: Emergency Request for Single Stage - One 2020-09- 2020-09- 2020-10- 2020-09- 2021-04- Salmeterolinha 50mcg IDA / 65950 Post Limited 1,292.00 17,778.14 Signed COVID-19 Response Quotations Envelope 02 01 28 10 26 /25mcg md,120d procured by by MSD during Covid period LK-MOH-191018-GO-RFQ / Total Pareneteral Nutrition Pending Component 1: Emergency Request for Single Stage - One 2020-09- 2020-10- 2021-04- in 1000ml -2500ml IDA / 65950 Post Limited 66,274.00 0.00 Implement COVID-19 Response Quotations Envelope 02 28 26 collapsible bag procured by ation by MSD during Covid period LK-MOH-191019-GO-RFQ Pending / Spacer device for infants Component 1: Emergency Request for Single Stage - One 2020-09- 2020-10- 2021-04- IDA / 65950 Post Limited 5,921.00 0.00 Implement procured by by MSD during COVID-19 Response Quotations Envelope 02 28 26 ation Covid period LK-MOH-191020-GO-RFQ Pending / Potassium cit-rate Component 1: Emergency Request for Single Stage - One 2020-09- 2020-10- 2021-04- IDA / 65950 Post Limited 6,908.00 0.00 Implement procured by by MSD during COVID-19 Response Quotations Envelope 02 28 26 ation Covid period LK-MOH-191022-GO-RFQ / Protein hydrolysate Inj. Component 1: Emergency Request for Single Stage - One 2020-09- 2020-09- 2020-10- 2020-09- 2021-04- IDA / 65950 Post Limited 1,695.00 1,738.19 Signed 100ml procured by by MSD COVID-19 Response Quotations Envelope 02 01 28 10 26 during Covid period LK-MOH-191665-GO-RFQ / 01 Unit Refrigerator (450 Component 1: Emergency Request for Single Stage - One 2020-09- 2020-09- 2020-10- 2020-09- 2020-11- IDA / 65950 Post Limited 2,631.00 870.27 Signed -500 Ltr Capacity) for COVID-19 Response Quotations Envelope 08 02 27 28 10 Airport Health Office Katunayake LK-MOH-191666-GO-RFQ / 12 Nos Laptops, 05 Nos Pending Component 1: Emergency Request for Single Stage - One 2020-09- 2020-11- 2020-12- Desk Tops, 01 No IDA / 65950 Post Limited 15,789.00 0.00 Implement COVID-19 Response Quotations Envelope 15 10 01 Photocopier and 01 No ation Facsimile Machine for Project Monitoring Unit LK-MOH-191667-GO-RFQ / Installation of Air Pending Component 1: Emergency Request for Single Stage - One 2020-09- 2020-10- 2020-10- Condition unit at MICU by IDA / 65950 Post Limited 29.00 0.00 Implement COVID-19 Response Quotations Envelope 08 13 27 Ragama Teaching Hospital ation during Covid period. LK-MOH-192417-GO-RFQ / 02 Nos Desktop Computers, 02 Nos Laptop Computers, 01 No. Laser Pending Colour Printer, 01 No. Component 1: Emergency Request for Single Stage - One 2020-09- 2020-11- 2020-12- TF / B3017 Post Limited 7,053.00 0.00 Implement Multimedia Projector, 01 No COVID-19 Response Quotations Envelope 29 17 08 ation Photocopy Machine, 01 No: Facsimile Machine, 01 No: Web Cam with Head set and 01 No: Android Box require for FHB under Covid Grant LK-MOH-192425-GO-RFQ / 01 No. Executive Table, 03 Nos High Back Executive Chairs, 02 Nos Tables, 11 Pending Component 1: Emergency Request for Single Stage - One 2020-09- 2020-11- 2020-12- nos Law Back Chairs, 01 No TF / B3017 Post Limited 4,112.00 0.00 Implement COVID-19 Response Quotations Envelope 29 17 08 Sofa Set, 01 No Folder Rack, ation 05 Nos Office Cupboards and 02 Nos Filing Cabinets required for FHB under Covid Grant LK-MOH-192655-GO-RFQ / 03 Nos Air Condition Pending Component 1: Emergency Request for Single Stage - One 2020-09- 2020-11- 2020-12- Plants for refurbishment of TF / B3017 Post Limited 2,368.00 0.00 Implement COVID-19 Response Quotations Envelope 29 17 08 Family Health Bureau under ation Covid Grant LK-MOH-192656-GO-RFQ Pending / 02 Nos UHD TV 42" Component 1: Emergency Request for Single Stage - One 2020-09- 2020-11- 2020-12- TF / B3017 Post Limited 1,263.00 0.00 Implement required for Family Health COVID-19 Response Quotations Envelope 29 17 08 ation Bureau under Covid Grant LK-MOH-193053-GO-DIR Pending / 07 Nos hand Sprayer Component 1: Emergency 2020-09- 2020-09- 2020-09- 2021-03- IDA / 65950 Post Direct Selection Direct 79.00 0.00 Implement procured by District COVID-19 Response 10 15 29 28 ation Hospital Baticalao during Covid Period (Advance) LK-MOH-193055-GO-DIR / 05 Nos Garbage Bins Pending Component 1: Emergency 2020-09- 2020-09- 2020-09- 2020-09- procured by Baticaloa IDA / 65950 Post Direct Selection Direct 132.00 0.00 Implement COVID-19 Response 10 15 29 30 District Hospital during ation Covid period. (Advance) LK-MOH-193058-GO-DIR / 41 Nos Hand Wash Pending Component 1: Emergency 2020-09- 2020-09- 2020-09- 2020-10- Dispensers procured by IDA / 65950 Post Direct Selection Direct 270.00 0.00 Implement COVID-19 Response 10 15 29 13 Baticaloa District Hospital ation during Covid period. (Advance) Page 12 LK-MOH-193051-GO-RFQ / PCR testing and Pending Component 1: Emergency Request for Single Stage - One 2020-09- 2020-10- 2020-11- consumables procured by IDA / 65950 Post Limited 768.00 0.00 Implement COVID-19 Response Quotations Envelope 15 27 10 Baticaloa District Hospital ation during Covid period. (advance) LK-MOH-193052-GO-RFQ Pending / 08 Nos Desk top Component 1: Emergency Request for Single Stage - One 2020-09- 2020-10- 2020-11- IDA / 65950 Post Limited 4,842.00 0.00 Implement Computers procured by COVID-19 Response Quotations Envelope 15 27 10 ation Baticaloa District Hospital during Covid period. LK-MOH-193062-GO-RFQ / 02 Nos Air Conditioner 36000 BTU & 02 Nos Air Pending Component 1: Emergency Request for Single Stage - One 2020-09- 2020-10- 2020-11- Conditioner 24000 BTU IDA / 65950 Post Limited 4,524.00 0.00 Implement COVID-19 Response Quotations Envelope 15 27 10 procured by Baticaloa ation District Hospital during Covid period. (Advance) LK-MOH-193065-GO-RFQ / 300 nos. Nilkamal Plastic Pending Chairs with Arm procured Component 1: Emergency Request for Single Stage - One 2020-09- 2020-10- 2020-11- IDA / 65950 Post Limited 1,658.00 0.00 Implement by Baticaloa District Hospital COVID-19 Response Quotations Envelope 15 27 10 ation during Covid period. (Advance) LK-MOH-193071-GO-RFQ / 10 Nos Half Shoes Pending Component 1: Emergency Request for Single Stage - One 2020-09- 2020-10- 2020-11- procured by Baticaloa IDA / 65950 Post Limited 64.00 0.00 Implement COVID-19 Response Quotations Envelope 15 27 10 District Hospital during ation Covid period. (Advance) LK-MOH-193076-GO-RFQ Pending / 35 Nos Nescafe procured Component 1: Emergency Request for Single Stage - One 2020-09- 2020-10- 2020-11- IDA / 65950 Post Limited 159.00 0.00 Implement by Baticaloa District Hospital COVID-19 Response Quotations Envelope 15 27 10 ation during Covid period.(Advance) LK-MOH-193078-GO-RFQ / 33 Nos Drinking Water Pending Component 1: Emergency Request for Single Stage - One 2020-09- 2020-10- 2020-11- Bottles-19Ltr procured by IDA / 65950 Post Limited 63.00 0.00 Implement COVID-19 Response Quotations Envelope 15 27 10 Baticaloa District Hospital ation during Covid period. (Advance) LK-MOH-193801-GO-DIR / Novel Coronavirus (Covid- Pending Component 1: Emergency 2020-09- 2020-09- 2020-10- 2020-10- 19) Real Time PCR kit (100 IDA / 65950 Post Direct Selection Direct 384,211.00 0.00 Implement COVID-19 Response 15 20 11 25 Reactions per kit) for ation 40,000 reactions LK-MOH-193802-GO-DIR Pending / QIAmp Viral RNA Mini Kit Component 1: Emergency 2020-09- 2020-09- 2020-10- 2020-10- IDA / 65950 Post Direct Selection Direct 147,368.00 0.00 Implement extraction kit (100 COVID-19 Response 15 20 11 25 ation Reactions per kit) for 40,000 reactions LK-MOH-193803-GO-DIR Pending Component 1: Emergency 2020-09- 2020-09- 2020-10- 2020-10- / 48,000 Nos Viral transport IDA / 65950 Post Direct Selection Direct 25,305.00 0.00 Implement COVID-19 Response 15 21 12 26 media with swabs ation LK-MOH-193804-GO-DIR / 80,000 Nos Micro Pending Component 1: Emergency 2020-09- 2020-09- 2020-10- 2020-10- centrifuge tubes, Virgin IDA / 65950 Post Direct Selection Direct 1,835.00 0.00 Implement COVID-19 Response 15 20 11 25 polypropylene, safe lock, ation PCR grade, sterile, colourless, Vol. 1.5ml LK-MOH-193805-GO-DIR / 80 Nos Cryo vial, vial Pending stands without holder, Component 1: Emergency 2020-09- 2020-09- 2020-10- 2020-10- IDA / 65950 Post Direct Selection Direct 9,175.00 0.00 Implement screw capped, autoclavable, COVID-19 Response 15 20 11 25 ation can be frozen at -80 C, bulk packed, volume 1.8ml LK-MOH-193808-GO-DIR / 44 Packs of Micro Pending Component 1: Emergency 2020-09- 2020-09- 2020-10- 2020-10- centrifuge tubes: 0.2 ml PCR IDA / 65950 Post Direct Selection Direct 2,083.00 0.00 Implement COVID-19 Response 15 20 11 25 grade, clear tubes in strips ation (8 tubes) 120 strips per pack LK-MOH-193809-GO-DIR / 8,000 Nos Micro Pending Component 1: Emergency 2020-09- 2020-09- 2020-10- 2020-10- centrifuge tubes: 0.1 ml PCR IDA / 65950 Post Direct Selection Direct 1,474.00 0.00 Implement COVID-19 Response 15 20 11 25 grade, clear tubes in strips ation (4 tubes) with cap LK-MOH-193810-GO-DIR / 24,000 Nos Micro Pending Component 1: Emergency 2020-09- 2020-09- 2020-10- 2020-10- centrifuge tubes for IDA / 65950 Post Direct Selection Direct 998.00 0.00 Implement COVID-19 Response 15 20 11 25 amplification; Flat-shaped ation lids, size 0.2 ml (PCR grade) LK-MOH-193812-GO-DIR Pending / 80,000 Nos Micro pipette Component 1: Emergency 2020-09- 2020-09- 2020-10- 2020-10- IDA / 65950 Post Direct Selection Direct 6,316.00 0.00 Implement tips with filter, PCR grade COVID-19 Response 15 20 11 25 ation volume 10-20 mic.l LK-MOH-193814-GO-DIR Pending / 100,000 Nos Micro pipette Component 1: Emergency 2020-09- 2020-09- 2020-10- 2020-10- IDA / 65950 Post Direct Selection Direct 6,710.00 0.00 Implement tips PCR grade volume 0.5- COVID-19 Response 15 20 11 25 ation 10 mic.l LK-MOH-193818-GO-DIR Pending Component 1: Emergency 2020-09- 2020-09- 2020-10- 2020-10- / 17,280 Nos Micro pipette IDA / 65950 Post Direct Selection Direct 1,672.00 0.00 Implement COVID-19 Response 15 20 11 25 tips PCR grade, volume ation 1000 mic.l LK-MOH-193819-GO-DIR Pending / 160,000 Nos Micro pipette Component 1: Emergency 2020-09- 2020-09- 2020-10- 2020-10- IDA / 65950 Post Direct Selection Direct 9,728.00 0.00 Implement tips PCR grade, volume 20- COVID-19 Response 15 20 11 25 ation 200 mic.l LK-MOH-193820-GO-DIR Pending Component 1: Emergency 2020-09- 2020-09- 2020-10- 2020-10- / 40,000 Nos Disposable IDA / 65950 Post Direct Selection Direct 3,084.00 0.00 Implement COVID-19 Response 15 20 11 25 plastic Pasteur pipette, 3ml ation with bulb LK-MOH-195372-GO-RFQ / 05 Nos Photocopy Pending Component 1: Emergency Request for Single Stage - One 2020-10- 2020-12- 2021-01- Machines required for Sri TF / B3017 Post Limited 2,200.00 0.00 Implement COVID-19 Response Quotations Envelope 13 08 07 Lanka College of Psychiatry ation under Covid Grant LK-MOH-195378-GO-RFQ / 06 Nos Exercise Machines Pending Component 1: Emergency Request for Single Stage - One 2020-10- 2020-12- 2021-01- required for Sri Lanka TF / B3017 Post Limited 4,737.00 0.00 Implement COVID-19 Response Quotations Envelope 13 08 07 Collage of Psychiatry under ation Covid Grant LK-MOH-195413-GO-DIR / 10 Nos Wall Fans for Covid Pending Component 1: Emergency 2020-09- 2020-09- 2020-10- 2020-10- wards at Ragama Teaching IDA / 65950 Post Direct Selection Direct 438.00 0.00 Implement COVID-19 Response 21 26 10 17 Hospital during Covid ation period (Retroactive) LK-MOH-195414-GO-DIR / Hardware item for Micu Pending Component 1: Emergency 2020-09- 2020-09- 2020-10- 2020-10- procured by Ragama IDA / 65950 Post Direct Selection Direct 75.00 0.00 Implement COVID-19 Response 21 26 10 17 Teaching Hospital during ation Covid period (Retroactive) LK-MOH-195419-GO-DIR / Sisili Examination & Pending Component 1: Emergency 2020-09- 2020-09- 2020-10- 2020-10- Surgical Gloves IDA / 65950 Post Direct Selection Direct 5,098,545.00 0.00 Implement COVID-19 Response 21 26 17 31 (25,064,000.00) procured ation by MSD during Covid period (Retroactive) LK-MOH-189311-GO-RFB Pending / 18 Nos. Blood Fluid Component 1: Emergency Single Stage - One 2020-08- 2020-08- 2020-10- 2020-11- 2020-12- 2021-06- IDA / 65950 Post Request for Bids Open - National 23,021.00 0.00 Implement Warmer procured by BME COVID-19 Response Envelope 18 23 04 03 08 06 ation during Covid period LK-MOH-195396-GO-RFQ Pending / 10 Nos Electric Ovens Component 1: Emergency Request for Single Stage - One 2020-10- 2020-12- 2021-01- TF / B3017 Post Limited 947.00 0.00 Implement required for College of COVID-19 Response Quotations Envelope 27 22 21 ation Psychiatry under Covid Grant LK-MOH-195369-GO-RFQ / 02 Unit Electro Convulsive Pending Therapy machines (ECT) Component 1: Emergency Request for Single Stage - One 2020-10- 2020-12- 2021-06- TF / B3017 Post Limited 52,631.00 0.00 Implement required for Sri Lanka COVID-19 Response Quotations Envelope 13 08 06 ation College of Psychiatry under Covid Grant LK-MOH-198065-GO-RFQ / 02 Nos Sphygmomanometer, 02 Nos Glucometer, 02 Nos Pending Component 1: Emergency Request for Single Stage - One 2020-10- 2020-12- 2021-01- Thermometer, 02 Nos TF / B3017 Post Limited 1,379.00 0.00 Implement COVID-19 Response Quotations Envelope 25 20 19 Stethoscope, 02 Nos ation Nebulizer and 20 Nos Walkers for National Institute of Mental Health Day enters under Covid Grant LK-MOH-198066-GO-RFQ / 18 Items of Household Pending and Office equipment items Component 1: Emergency Request for Single Stage - One 2020-10- 2020-12- 2021-01- TF / B3017 Post Limited 20,632.00 0.00 Implement required for Day Center for COVID-19 Response Quotations Envelope 26 21 20 ation Elderly, National Institute of Mental Health, Sri Lanka LK-MOH-198113-GO-RFQ Pending Component 1: Emergency Request for Single Stage - One 2020-10- 2020-12- 2021-01- / Purchase of Mattress Items IDA / 65950 Post Limited 50,565.00 0.00 Implement COVID-19 Response Quotations Envelope 19 14 13 for Quarantine Centers ation LK-MOH-198116-GO-RFQ / Sanitary Items for Quarantine centers There was an urgent need arisen for expanding the Pending Component 1: Emergency Request for Single Stage - One 2020-10- 2020-11- 2020-11- capacity of Quarantine IDA / 65950 Post Limited 17,298.00 0.00 Implement COVID-19 Response Quotations Envelope 19 08 22 Centers and the Covid ation patient management hospitals due to the unexpected community spread of Covid-19 discovered in the Gampaha district, which LK-MOH-198117-GO-RFQ / Furniture for Quarantine centers There was an urgent need arisen for expanding the Pending Component 1: Emergency Request for Single Stage - One 2020-10- 2020-11- 2020-11- capacity of Quarantine IDA / 65950 Post Limited 115,991.00 0.00 Implement COVID-19 Response Quotations Envelope 19 09 23 Centers and the Covid ation patient management hospitals due to the unexpected community spread of Covid-19 discovered in the Gampaha district, which has LK-MOH-198153-GO-RFQ Pending Component 1: Emergency Request for Single Stage - One 2020-10- 2020-11- 2020-11- / Glass and Porcelain IDA / 65950 Post Limited 45,777.00 0.00 Implement COVID-19 Response Quotations Envelope 19 11 18 Tableware Items for ation Quarantine centers LK-MOH-198203-GO-RFQ Pending Component 1: Emergency Request for Single Stage - One 2020-10- 2020-11- 2020-11- / Kitchen Items for IDA / 65950 Post Limited 11,438.00 0.00 Implement COVID-19 Response Quotations Envelope 19 09 16 Quarantine centers ation LK-MOH-198212-GO-RFQ Pending Component 1: Emergency Request for Single Stage - One 2020-10- 2020-11- 2020-11- / Cutlery Sets for IDA / 65950 Post Limited 6,226.00 0.00 Implement COVID-19 Response Quotations Envelope 19 09 16 Quarantine centers ation LK-MOH-198220-GO-RFQ Pending Component 1: Emergency Request for Single Stage - One 2020-10- 2020-11- 2020-11- / Bedding Items for IDA / 65950 Post Limited 97,775.00 0.00 Implement COVID-19 Response Quotations Envelope 19 09 16 Quarantine centers ation LK-MOH-198234-GO-RFQ Pending Component 1: Emergency Request for Single Stage - One 2020-10- 2020-11- 2020-11- / Bed Frames with Bases for IDA / 65950 Post Limited 70,212.00 0.00 Implement COVID-19 Response Quotations Envelope 19 09 16 Quarantine centers ation LK-MOH-198567-GO-RFQ Pending / 300 Nos Patient Beds for Component 1: Emergency Request for Single Stage - One 2020-10- 2020-11- 2020-11- IDA / 65950 Post Limited 33,158.00 0.00 Implement new Covid treatment center COVID-19 Response Quotations Envelope 17 07 14 ation at Neviel Fernando Hospital LK-MOH-198572-GO-RFQ Pending / Kitchen and Washing Component 1: Emergency Request for Single Stage - One 2020-10- 2020-11- 2020-11- IDA / 65950 Post Limited 80,215.00 0.00 Implement Equipment for Quarantine COVID-19 Response Quotations Envelope 19 09 16 ation centers LK-MOH-198575-GO-RFQ Pending Component 1: Emergency Request for Single Stage - One 2020-10- 2020-11- 2020-11- / Office Furniture for IDA / 65950 Post Limited 5,615.00 0.00 Implement COVID-19 Response Quotations Envelope 19 09 16 Quarantine centers ation LK-MOH-198577-GO-RFQ Pending Component 1: Emergency Request for Single Stage - One 2020-10- 2020-11- 2020-11- / Stationary Items for IDA / 65950 Post Limited 2,126.00 0.00 Implement COVID-19 Response Quotations Envelope 19 09 16 Quarantine centers ation LK-MOH-198636-GO-RFB / Equipment for health information management Pending center at disaster Component 1: Emergency Single Stage - One 2020-11- 2020-11- 2020-12- 2021-01- 2021-02- 2021-08- IDA / 65950 Post Request for Bids Open - National 263,158.00 0.00 Implement preparedness and response COVID-19 Response Envelope 05 10 22 21 25 24 ation division and Epidemiological unit for strengthening surveillance. LK-MOH-198646-GO-RFQ Pending / 300 Nos Mattresses for Component 1: Emergency Request for Single Stage - One 2020-10- 2020-11- 2020-11- IDA / 65950 Post Limited 9,474.00 0.00 Implement New Covid19 Patientcare COVID-19 Response Quotations Envelope 19 09 16 ation center at Neviel Fernando Hospital LK-MOH-198648-GO-RFQ / 300 Nos Bed Sheets, Pending Component 1: Emergency Request for Single Stage - One 2020-10- 2020-11- 2020-11- Pillows and Pillow cases for IDA / 65950 Post Limited 1,700.00 0.00 Implement COVID-19 Response Quotations Envelope 19 09 16 New Covid19 Patientcare ation center at Neviel Fernando Hospital LK-MOH-198574-GO-RFQ Pending / Boilers, Scales & Other Component 1: Emergency Request for Single Stage - One 2020-10- 2020-11- 2020-11- IDA / 65950 Post Limited 36,937.00 0.00 Implement Equipment for Quarantine COVID-19 Response Quotations Envelope 19 09 16 ation centers LK-MOH-198239-GO-RFQ Pending Component 1: Emergency Request for Single Stage - One 2020-10- 2020-11- 2020-11- / Computers and a IDA / 65950 Post Limited 10,288.00 0.00 Implement COVID-19 Response Quotations Envelope 19 09 16 Photocopier for Quarantine ation centers LK-MOH-198244-GO-RFQ Pending Component 1: Emergency Request for Single Stage - One 2020-10- 2020-11- 2020-11- / Garden Items for IDA / 65950 Post Limited 36,340.00 0.00 Implement COVID-19 Response Quotations Envelope 19 09 16 Quarantine centers ation LK-MOH-198569-GO-RFQ Pending Component 1: Emergency Request for Single Stage - One 2020-10- 2020-11- 2020-11- / Televisions for Quarantine IDA / 65950 Post Limited 48,653.00 0.00 Implement COVID-19 Response Quotations Envelope 19 09 16 centers ation LK-MOH-198252-GO-RFQ Pending Component 1: Emergency Request for Single Stage - One 2020-10- 2020-11- 2020-11- / Electrical Items for IDA / 65950 Post Limited 26,934.00 0.00 Implement COVID-19 Response Quotations Envelope 19 09 16 Quarantine centers ation LK-MOH-198067-GO-RFQ Pending Component 1: Emergency Request for Single Stage - One 2020-11- 2020-12- 2021-01- / 24 Items of Office TF / B3017 Post Limited 7,525.00 0.00 Implement COVID-19 Response Quotations Envelope 01 27 26 furniture and Hospital ation furniture LK-MOH-199094-GO-RFQ Pending / 07 Nos Multi-para Component 1: Emergency Request for Single Stage - One 2020-10- 2020-11- 2020-12- IDA / 65950 Post Limited 9,211.00 0.00 Implement monitors to manage the COVID-19 Response Quotations Envelope 19 23 08 ation COVID-19 patients LK-MOH-199382-GO-RFQ / Furniture and other office items to improve the Pending Component 1: Emergency Request for Single Stage - One 2020-10- 2020-11- 2020-11- surveillance system at TF / B3017 Post Limited 10,526.00 0.00 Implement COVID-19 Response Quotations Envelope 26 16 23 Epidemiology Unit on ation disaster management e- surveillance system. LK-MOH-199384-GO-RFQ / Supply & instillation of 04 Pending Component 1: Emergency Request for Single Stage - One 2020-11- 2020-11- 2020-12- Nos of Air Conditioners to TF / B3017 Post Limited 2,632.00 0.00 Implement COVID-19 Response Quotations Envelope 04 25 02 Epidemiology Unit e- ation surveillance system. LK-MOH-199400-GO-RFQ / Supply, Installation, Testing and Commissioning Pending Component 1: Emergency Request for Single Stage - One 2020-11- 2020-12- 2020-12- of Cameras for Health TF / B3017 Post Limited 22,368.00 0.00 Implement COVID-19 Response Quotations Envelope 10 01 08 Promotion Bureau to ation upgrade the public awareness and healthy behaviors. LK-MOH-199543-GO-RFQ / Laptop for Social Medea Pending Component 1: Emergency Request for Single Stage - One 2020-11- 2020-11- 2020-12- Platform at Health TF / B3017 Post Limited 7,105.00 0.00 Implement COVID-19 Response Quotations Envelope 04 25 02 Promotion Bureau to ation improve social media platform.. LK-MOH-199725-GO-RFQ / Procurement of Pending Component 1: Emergency Request for Single Stage - One 2020-11- 2020-11- 2020-12- referencing test books for TF / B3017 Post Limited 5,263.00 0.00 Implement COVID-19 Response Quotations Envelope 04 25 02 Epidemiology unit for close ation monitoring of e-surveillance system. LK-MOH-199728-GO-RFQ Pending / Public Address System for Component 1: Emergency Request for Single Stage - One 2020-11- 2020-11- 2020-12- TF / B3017 Post Limited 526.00 0.00 Implement Nurses Training School, COVID-19 Response Quotations Envelope 04 25 02 ation Mulleriyawa LK-MOH-199729-GO-RFQ Pending / 13 items of Furniture Component 1: Emergency Request for Single Stage - One 2020-11- 2020-11- 2020-11- TF / B3017 Post Limited 13,636.00 0.00 Implement required for Nursing COVID-19 Response Quotations Envelope 02 23 30 ation Training School Mulleriyawa Page 13 LK-MOH-199738-GO-RFQ Pending / 05 Items of Household Component 1: Emergency Request for Single Stage - One 2020-11- 2020-11- 2020-12- TF / B3017 Post Limited 2,525.00 0.00 Implement items required for Nurses COVID-19 Response Quotations Envelope 04 25 02 ation Training School LK-MOH-199745-GO-RFQ / Supply and Installation of Pending Component 1: Emergency Request for Single Stage - One 2020-11- 2020-12- 2020-12- 03 Units Air Condition TF / B3017 Post Limited 2,368.00 0.00 Implement COVID-19 Response Quotations Envelope 10 01 08 Machines at Nurses Training ation School, Mulleriyawa LK-MOH-199774-GO-RFQ / 01 No Multimedia Pending Projector, 01 No Large Component 1: Emergency Request for Single Stage - One 2020-11- 2020-12- 2020-12- TF / B3017 Post Limited 4,605.00 0.00 Implement Digital Screen and 01 No COVID-19 Response Quotations Envelope 10 01 08 ation Riso Duplo Machine for Nursing Training School Mulleriyawa LK-MOH-199781-GO-RFQ / 01 No Bio Chemistry Pending Component 1: Emergency Request for Single Stage - One 2020-10- 2020-12- 2020-12- Analyzer for Covid IDA / 65950 Post Limited 6,316.00 0.00 Implement COVID-19 Response Quotations Envelope 20 08 22 management at Kandy ation Teaching Hospital (Advance procurement) LK-MOH-199786-GO-RFQ / 01 No Bio Safety Cabinet Pending Component 1: Emergency Request for Single Stage - One 2020-10- 2020-12- 2020-12- for Covid management at IDA / 65950 Post Limited 9,379.00 0.00 Implement COVID-19 Response Quotations Envelope 20 08 22 Kandy Teaching Hospital ation during Covid period (Advance) LK-MOH-199789-GO-RFQ / 5-Part Hematology Pending Analyzer With CRP capability- Component 1: Emergency Request for Single Stage - One 2020-10- 2020-12- 2020-12- IDA / 65950 Post Limited 20,526.00 0.00 Implement covid-19 patient COVID-19 Response Quotations Envelope 20 08 22 ation management at Kandy Teaching Hospital (Advance Procurement) LK-MOH-199791-GO-RFQ / 03 Nos Hydrogen Peroxide Pending Component 1: Emergency Request for Single Stage - One 2020-10- 2020-12- 2020-12- Fogging Machine-covid-19 IDA / 65950 Post Limited 12,553.00 0.00 Implement COVID-19 Response Quotations Envelope 20 08 22 patient management at ation Kandy Teaching Hospital. (Advance) LK-MOH-199792-GO-RFQ Pending / 20000 Envelopes required Component 1: Emergency Request for Single Stage - One 2020-10- 2020-12- 2020-12- IDA / 65950 Post Limited 3,947.00 0.00 Implement for Kandy Teaching hospital COVID-19 Response Quotations Envelope 20 08 22 ation during Covid period (Advance) LK-MOH-199795-GO-RFQ / 39 Items of building Pending maintenance equipment for Component 1: Emergency Request for Single Stage - One 2020-10- 2020-12- 2020-12- IDA / 65950 Post Limited 9,292.00 0.00 Implement Covid patient Management COVID-19 Response Quotations Envelope 20 08 22 ation at Kandy Teaching Hospital (Advance procurement) LK-MOH-199835-GO-RFQ / 12 Nos Stand Fans Pending required for Covid patient Component 1: Emergency Request for Single Stage - One 2020-10- 2020-12- 2020-12- IDA / 65950 Post Limited 502.00 0.00 Implement management at COVID-19 Response Quotations Envelope 20 08 22 ation Anuradhapura Teaching Hospital (Advance procurement) LK-MOH-199845-GO-RFQ / 02 Nos Cupboards with Pending Mirrors required for Covid Component 1: Emergency Request for Single Stage - One 2020-10- 2020-12- 2020-12- IDA / 65950 Post Limited 209.00 0.00 Implement patient management at COVID-19 Response Quotations Envelope 20 08 22 ation Anuradhapura Teaching Hospital (Advance) LK-MOH-199849-GO-RFQ / 50 Nos Dust Bins (Paddle) Pending and 100 Nos Gum Boots Component 1: Emergency Request for Single Stage - One 2020-10- 2020-12- 2020-12- IDA / 65950 Post Limited 1,271.00 0.00 Implement required for Covid patient COVID-19 Response Quotations Envelope 20 08 22 ation management at Anuradhapura Teaching Hospital LK-MOH-199857-GO-RFQ / 01 No Freezer Double Pending Door 250Ltr required for Component 1: Emergency Request for Single Stage - One 2020-10- 2020-12- 2020-12- IDA / 65950 Post Limited 491.00 0.00 Implement Covid patient management COVID-19 Response Quotations Envelope 20 08 22 ation at Anuradhapura Teaching Hospital LK-MOH-200025-GO-RFQ / 02 Nos Washing Machines Pending required for Covid patient Component 1: Emergency Request for Single Stage - One 2020-10- 2020-12- 2020-12- IDA / 65950 Post Limited 581.00 0.00 Implement management at COVID-19 Response Quotations Envelope 21 09 23 ation Anuradhapura Teaching Hospital during Covid period (Advance) LK-MOH-200026-GO-RFQ / 02 Nos Office Cupboards, 01 No Office Cupboard with Glass, 25 Nos Electrical Pending Kettles and 25 Nos Water Component 1: Emergency Request for Single Stage - One 2020-10- 2020-12- 2020-12- IDA / 65950 Post Limited 1,432.00 0.00 Implement Heaters required for Covid COVID-19 Response Quotations Envelope 21 09 23 ation patient management Anuradhapura Teaching Hospital during Covid period (Advance) LK-MOH-200029-GO-RFQ / 25 Nos Paddle Bins Pending required for Covid patient Component 1: Emergency Request for Single Stage - One 2020-10- 2020-12- 2020-12- IDA / 65950 Post Limited 243.00 0.00 Implement management at COVID-19 Response Quotations Envelope 21 09 23 ation Anuradhapura Teaching Hospital during Covid period. (Advance) LK-MOH-200030-GO-RFQ / 25 Nos Electric Jugs, 25 Nos Double Layer Pending Mattresses 6'x3' and Steel Component 1: Emergency Request for Single Stage - One 2020-10- 2020-12- 2020-12- IDA / 65950 Post Limited 1,257.00 0.00 Implement Beds 6'x3' required for COVID-19 Response Quotations Envelope 21 09 23 ation Covid patient management Anuradhapura Teaching Hospital during Covid period. (Advance procurement ) LK-MOH-200031-GO-RFQ / 500 Nos Surgical Gown Pending required for Covid patient Component 1: Emergency Request for Single Stage - One 2020-10- 2020-12- 2020-12- IDA / 65950 Post Limited 4,105.00 0.00 Implement management Anuradhapura COVID-19 Response Quotations Envelope 21 09 23 ation Teaching Hospital during Covid period. (Advance) LK-MOH-200043-GO-RFQ / 08 Nos Polythene Sealers Pending required for Covid patient Component 1: Emergency Request for Single Stage - One 2020-10- 2020-12- 2020-12- IDA / 65950 Post Limited 240.00 0.00 Implement management at COVID-19 Response Quotations Envelope 21 09 23 ation Anuradhapura Teaching Hospital during Covid period. (Advance LK-MOH-200047-GO-RFQ / 25 Nos Gum Boots Pending Component 1: Emergency Request for Single Stage - One 2020-10- 2020-12- 2020-12- required for Anuradhapura IDA / 65950 Post Limited 201.00 0.00 Implement COVID-19 Response Quotations Envelope 21 09 23 Teaching Hospital during ation Covid period. (Advance procurement) LK-MOH-200048-GO-RFQ / 500 Nos Surgical Gown Pending required for Covid patient Component 1: Emergency Request for Single Stage - One 2020-10- 2020-12- 2020-12- IDA / 65950 Post Limited 4,105.00 0.00 Implement management at COVID-19 Response Quotations Envelope 21 09 23 ation Anuradhapura Teaching Hospital during Covid period. (Advance) LK-MOH-200050-GO-RFQ / 01 No Laser Printer Pending required for Covid patient Component 1: Emergency Request for Single Stage - One 2020-10- 2020-12- 2020-12- IDA / 65950 Post Limited 86.00 0.00 Implement management at COVID-19 Response Quotations Envelope 21 09 23 ation Anuradhapura Teaching Hospital during Covid period. (Advance procurement) LK-MOH-200053-GO-RFQ / 8000 Mtrs Baby Elastics and 125 Nos White Thone Pending Component 1: Emergency Request for Single Stage - One 2020-10- 2020-12- 2020-12- Cone (2500) required for IDA / 65950 Post Limited 253.00 0.00 Implement COVID-19 Response Quotations Envelope 21 09 23 Anuradhapura Teaching ation Hospital during Covid period. (Advance procurement) LK-MOH-200055-GO-RFQ / 150 Mtrs Apron Wax Cloth and 200 Nos Plastic Brooms Pending Component 1: Emergency Request for Single Stage - One 2020-10- 2020-12- 2020-12- required for Anuradhapura IDA / 65950 Post Limited 792.00 0.00 Implement COVID-19 Response Quotations Envelope 21 09 23 Teaching Hospital during ation Covid period. (Advance procurement) LK-MOH-200061-GO-RFQ / 1000 Nos White Bed Pending Sheets required for Component 1: Emergency Request for Single Stage - One 2020-10- 2020-12- 2020-12- IDA / 65950 Post Limited 3,658.00 0.00 Implement Anuradhapura Teaching COVID-19 Response Quotations Envelope 21 09 23 ation Hospital during Covid period. (Advance procurement) LK-MOH-200063-GO-RFQ / 08 Items of Office Pending Furniture required for Component 1: Emergency Request for Single Stage - One 2020-10- 2020-12- 2020-12- IDA / 65950 Post Limited 1,284.00 0.00 Implement Anuradhapura Teaching COVID-19 Response Quotations Envelope 21 09 23 ation Hospital during Covid period. (Advance procurement) LK-MOH-200064-GO-RFQ / 500 Mtrs White Raw Cloth Pending required for Anuradhapura Component 1: Emergency Request for Single Stage - One 2020-10- 2020-12- 2020-12- IDA / 65950 Post Limited 776.00 0.00 Implement Teaching Hospital during COVID-19 Response Quotations Envelope 21 09 23 ation Covid period. (Advance procurement) LK-MOH-200067-GO-RFQ / 02 Nos Industrial Stand Pending Fans equired for Component 1: Emergency Request for Single Stage - One 2020-10- 2020-12- 2020-12- IDA / 65950 Post Limited 241.00 0.00 Implement Anuradhapura Teaching COVID-19 Response Quotations Envelope 21 09 23 ation Hospital during Covid period. (Advance procurement) LK-MOH-200068-GO-RFQ / 01 No Air Conditioner, 01 No Steel Table, 11 Nos Refrigerators, 01 No Fully Pending Automatic Washing Machine Component 1: Emergency Request for Single Stage - One 2020-10- 2020-12- 2020-12- IDA / 65950 Post Limited 1,583.00 0.00 Implement and 01 No Cold & Hot Water COVID-19 Response Quotations Envelope 21 09 23 ation Dispenser required for Anuradhapura Teaching Hospital during Covid period. (Advance procurement) LK-MOH-200069-GO-RFQ / 100 Nos Doctor Overalls Pending required for Anuradhapura Component 1: Emergency Request for Single Stage - One 2020-10- 2020-12- 2020-12- IDA / 65950 Post Limited 821.00 0.00 Implement Teaching Hospital during COVID-19 Response Quotations Envelope 21 09 23 ation Covid period. (Advance procurement) LK-MOH-200070-GO-RFQ / 500 Nos hospital attires Pending required for Anuradhapura Component 1: Emergency Request for Single Stage - One 2020-10- 2020-12- 2020-12- IDA / 65950 Post Limited 3,579.00 0.00 Implement Teaching Hospital during COVID-19 Response Quotations Envelope 21 09 23 ation Covid period. (Advance procurement) LK-MOH-200071-GO-RFQ / 300 Nos Hospital Attires Pending (Small) required for Component 1: Emergency Request for Single Stage - One 2020-10- 2020-12- 2020-12- IDA / 65950 Post Limited 2,147.00 0.00 Implement Anuradhapura Teaching COVID-19 Response Quotations Envelope 21 09 23 ation Hospital during Covid period. (Advance procurement) LK-MOH-200075-GO-RFQ / 740 Nos Half Shoes Pending Component 1: Emergency Request for Single Stage - One 2020-10- 2020-12- 2020-12- required for Anuradhapura IDA / 65950 Post Limited 5,238.00 0.00 Implement COVID-19 Response Quotations Envelope 21 09 23 Teaching Hospital during ation Covid period. (Advance procurement) LK-MOH-200076-GO-RFQ / 02 Nos Desk Tops, 01 No Laser jet Printer, 01 No Mini Pending Sub Woofer and 01 No UPS Component 1: Emergency Request for Single Stage - One 2020-10- 2020-12- 2020-12- IDA / 65950 Post Limited 1,753.00 0.00 Implement required for Anuradhapura COVID-19 Response Quotations Envelope 21 09 23 ation Teaching Hospital during Covid period. (Advance rocurement) LK-MOH-200080-GO-RFQ / 300 Nos hospital attires Pending required for Anuradhapura Component 1: Emergency Request for Single Stage - One 2020-10- 2020-12- 2020-12- IDA / 65950 Post Limited 615.00 0.00 Implement Teaching Hospital during COVID-19 Response Quotations Envelope 21 09 23 ation Covid period. (Advance procurement) LK-MOH-200082-GO-RFQ / 03 Nos Stand Fans, 03 Nos Exhaust Fans, 03 Nos Wall Pending Fans and 10 nos Wall Component 1: Emergency Request for Single Stage - One 2020-10- 2020-12- 2020-12- IDA / 65950 Post Limited 387.00 0.00 Implement Hangers required for COVID-19 Response Quotations Envelope 21 09 23 ation Anuradhapura Teaching Hospital during Covid period. (Advance procurement) LK-MOH-200095-GO-RFQ / 100 Nos Bath Towels and Pending 300 Nos Pijamas required Component 1: Emergency Request for Single Stage - One 2020-10- 2020-12- 2020-12- IDA / 65950 Post Limited 2,616.00 0.00 Implement for Anuradhapura Teaching COVID-19 Response Quotations Envelope 21 09 23 ation Hospital during Covid period. (Advance procurement) LK-MOH-200097-GO-RFQ / 07 Items of Hardware and Pending house Hold items required Component 1: Emergency Request for Single Stage - One 2020-10- 2020-12- 2020-12- IDA / 65950 Post Limited 246.00 0.00 Implement for Anuradhapura Teaching COVID-19 Response Quotations Envelope 21 09 23 ation Hospital during Covid period. (Advance procurement) LK-MOH-200112-GO-RFQ / 09 Items of Building Pending Component 1: Emergency Request for Single Stage - One 2020-10- 2020-12- 2020-12- Materials required for IDA / 65950 Post Limited 1,686.00 0.00 Implement COVID-19 Response Quotations Envelope 21 09 23 Anuradhapura Teaching ation Hospital during Covid period. (Advance) LK-MOH-200113-GO-RFQ / 5000 Nos Soap, 1000 Nos Hand Wash, 25 Nos Dust Pending Bins and 5000 Pkts Paper Component 1: Emergency Request for Single Stage - One 2020-10- 2020-12- 2020-12- IDA / 65950 Post Limited 5,094.00 0.00 Implement Serviette required for COVID-19 Response Quotations Envelope 21 09 23 ation Anuradhapura Teaching Hospital during Covid period. (Advance Procurement) LK-MOH-200121-GO-RFQ / IT and Office Equipment for health information Component 2: management center at Strengthening National and Pending Request for Single Stage - One 2020-11- 2020-12- 2021-01- disaster preparedness and IDA / 65950 Sub-national Institutions Post Limited 132,631.00 0.00 Implement Quotations Envelope 03 22 05 response division and for Prevention and ation Epidemiological unit for Preparedness strengthening surveillance island wide. LK-MOH-200128-GO-RFQ / 19 Nos DSLR Cameras and 01 No Document Camera Component 2: for health information Strengthening National and Pending management center at Request for Single Stage - One 2020-11- 2020-12- 2021-01- IDA / 65950 Sub-national Institutions Post Limited 10,526.00 0.00 Implement disaster preparedness and Quotations Envelope 04 23 06 for Prevention and ation response division and Preparedness Epidemiological unit for strengthening surveillance island wide. LK-MOH-200132-GO-RFQ / 06 items of Audio and Video Equipment and accessories (Items list under Component 2: comments) required for Strengthening National and Pending Request for Single Stage - One 2020-10- 2020-12- 2020-12- health information IDA / 65950 Sub-national Institutions Post Limited 1,432.00 0.00 Implement Quotations Envelope 22 10 24 management center at for Prevention and ation disaster preparedness and Preparedness response division and Epidemiological unit for strengthening surveillance. LK-MOH-201167-GO-DIR / 25,000 Nos. Magnetic Pending Component 1: Emergency 2020-10- 2020-10- 2020-11- 2020-11- Bead RNA and RT-qPCR Test IDA / 65950 Post Direct Selection Direct 750,000.00 0.00 Implement COVID-19 Response 26 31 14 28 Kits (with Master Mix) ation (Penta Base - TM Test Kits) LK-MOH-201169-GO-RFQ Pending / 50,000 Nos Goggles for Component 1: Emergency Request for Single Stage - One 2020-11- 2020-12- 2020-12- IDA / 65950 Post Limited 96,154.00 0.00 Implement Emergency Infectious COVID-19 Response Quotations Envelope 09 14 28 ation Condition LK-MOH-201170-GO-RFQ Pending Component 1: Emergency Request for Single Stage - One 2020-11- 2020-12- 2020-12- / 5,000 Nos Personal IDA / 65950 Post Limited 178,571.00 0.00 Implement COVID-19 Response Quotations Envelope 03 08 22 Protective Equipment (PPE) ation Set LK-MOH-201171-GO-RFQ Pending / 60,000 Nos Isolation gown Component 1: Emergency Request for Single Stage - One 2020-11- 2020-12- 2020-12- IDA / 65950 Post Limited 148,352.00 0.00 Implement for Emergency Infectious COVID-19 Response Quotations Envelope 03 08 22 ation Condition LK-MOH-201172-GO-RFQ Pending / 50,000 Nos Protective Component 1: Emergency Request for Single Stage - One 2020-11- 2020-12- 2020-12- IDA / 65950 Post Limited 153,846.00 0.00 Implement coverall for Emergency COVID-19 Response Quotations Envelope 03 08 22 ation Infectious Condition LK-MOH-201174-GO-RFQ Pending / 250000 Nos Shoe covers / Component 1: Emergency Request for Single Stage - One 2020-11- 2020-12- 2020-12- IDA / 65950 Post Limited 178,571.00 0.00 Implement Boot covers for Emergency COVID-19 Response Quotations Envelope 03 08 22 ation Infectious Condition Page 14 LK-MOH-201175-GO-RFQ Pending Component 1: Emergency Request for Single Stage - One 2020-11- 2020-12- 2020-12- / 2,500,000 Nos Surgical IDA / 65950 Post Limited 151,098.00 0.00 Implement COVID-19 Response Quotations Envelope 03 08 22 Face Masks ation LK-MOH-201420-GO-RFB Pending / 190,000 Isolation gown Component 1: Emergency Single Stage - One 2020-11- 2020-11- 2020-12- 2021-01- 2021-01- 2021-03- IDA / 65950 Post Request for Bids Open - National 467,033.00 0.00 Implement for Emergency Infectious COVID-19 Response Envelope 10 15 27 10 31 17 ation Condition LK-MOH-201421-GO-RFB Pending / 200,000 Nos Protective Component 1: Emergency Single Stage - One 2020-11- 2020-11- 2020-12- 2021-01- 2021-01- 2021-02- IDA / 65950 Post Request for Bids Open - National 769,231.00 0.00 Implement coverall for Emergency COVID-19 Response Envelope 10 15 27 03 24 23 ation Infectious Condition LK-MOH-201422-GO-RFB Pending Component 1: Emergency Single Stage - One 2020-11- 2020-11- 2020-12- 2021-01- 2021-01- 2021-02- / 2,500,000 Nos Surgical IDA / 65950 Post Request for Bids Open - National 151,099.00 0.00 Implement COVID-19 Response Envelope 10 15 27 03 24 23 Face Mask ation LK-MOH-201426-GO-RFB Pending / 250,000 Nos Particulate Component 1: Emergency Single Stage - One 2020-11- 2020-11- 2020-12- 2021-01- 2021-01- 2021-02- IDA / 65950 Post Request for Bids Open - National 412,088.00 0.00 Implement Respirator for Emergency COVID-19 Response Envelope 10 15 27 03 24 23 ation Infectious Condition LK-MOH-201428-GO-RFQ Pending / 100,000 Nos Particulate Component 1: Emergency Request for Single Stage - One 2020-10- 2020-12- 2020-12- IDA / 65950 Post Limited 164,835.00 0.00 Implement Respirator for Emergency COVID-19 Response Quotations Envelope 31 05 19 ation Infectious Condition LK-MOH-201544-GO-RFQ / 04 Items of House Hold Pending equipment (6 Refrigerator Component 1: Emergency Request for Single Stage - One 2020-11- 2020-12- 2020-12- IDA / 65950 Post Limited 5,769.00 0.00 Implement Single door) ( 3 Refrigerator COVID-19 Response Quotations Envelope 09 12 26 ation Double door , 2 Washing machine, 12 TV(32") LK-MOH-201644-GO-RFQ Pending / Furniture required for new Component 1: Emergency Request for Single Stage - One 2020-11- 2020-12- 2020-12- IDA / 65950 Post Limited 50,893.00 0.00 Implement infection disease building in COVID-19 Response Quotations Envelope 10 13 27 ation Kilinochchi LK-MOH-201645-GO-RFQ Pending / 01 No Generator set for Component 1: Emergency Request for Single Stage - One 2020-11- 2020-12- 2020-12- IDA / 65950 Post Limited 21,978.00 0.00 Implement new infections disease COVID-19 Response Quotations Envelope 10 13 27 ation hospital in Kilinochchi LK-MOH-201646-GO-RFQ / 03 Units of Reverse Pending Component 1: Emergency Request for Single Stage - One 2020-11- 2020-12- 2020-12- Osmosis systems plants for IDA / 65950 Post Limited 6,593.00 0.00 Implement COVID-19 Response Quotations Envelope 10 13 27 new infections disease ation hospital in Kilinochchi LK-MOH-201647-GO-RFQ Pending / 100 Nos Street Lamps Component 1: Emergency Request for Single Stage - One 2020-11- 2020-12- 2020-12- IDA / 65950 Post Limited 2,198.00 0.00 Implement required for new infections COVID-19 Response Quotations Envelope 10 13 27 ation disease hospital in Kilinochchi LK-MOH-201648-GO-RFQ Pending / 02 Nos Dryers required for Component 1: Emergency Request for Single Stage - One 2020-11- 2020-12- 2020-12- IDA / 65950 Post Limited 3,297.00 0.00 Implement new infections disease COVID-19 Response Quotations Envelope 10 13 27 ation hospital in Kilinochchi LK-MOH-201649-GO-RFQ Pending / Sound System required for Component 1: Emergency Request for Single Stage - One 2020-11- 2020-12- 2020-12- IDA / 65950 Post Limited 2,742.00 0.00 Implement new infections disease COVID-19 Response Quotations Envelope 10 13 27 ation hospital in Kilinochchi LK-MOH-201650-GO-RFQ / 06 Nos Air Conditioners (24,000 BTU) and 04 Nos Air Pending Component 1: Emergency Request for Single Stage - One 2020-11- 2020-12- 2020-12- Conditioner Units (18,000 IDA / 65950 Post Limited 9,341.00 0.00 Implement COVID-19 Response Quotations Envelope 10 13 27 Btu) required for ation Consultants quarters at the new infections disease hospital in Kilinochchi LK-MOH-201651-GO-RFQ / Supply and Installation of suitable Pending tele/visual/audio/online Component 1: Emergency Request for Single Stage - One 2020-11- 2020-12- 2021-01- IDA / 65950 Post Limited 16,484.00 0.00 Implement communication facilities COVID-19 Response Quotations Envelope 23 26 09 ation with CCTV cameras at the new infections disease hospital in Kilinochchi. LK-MOH-201653-GO-RFQ Pending / 12 Nos Led Monitors for Component 1: Emergency Request for Single Stage - One 2020-11- 2020-12- 2021-01- IDA / 65950 Post Limited 1,429.00 0.00 Implement the new infections disease COVID-19 Response Quotations Envelope 17 20 03 ation hospital in Kilinochchi LK-MOH-201853-GO-RFQ / Banner Stand for Pending Component 1: Emergency Request for Single Stage - One 2020-11- 2020-11- 2020-12- Valikanda Covid patient IDA / 65950 Post Limited 129.00 0.00 Implement COVID-19 Response Quotations Envelope 02 28 05 Center- Polonnaruwa DGH ation (Advance Procurement) LK-MOH-201854-GO-RFQ / 16 items of Assorted items for partitioning of Pending Component 1: Emergency Request for Single Stage - One 2020-11- 2020-11- 2020-12- Covid patient isolation IDA / 65950 Post Limited 2,673.00 0.00 Implement COVID-19 Response Quotations Envelope 02 28 05 center at Welikanda Hospital ation during Covid period (Advance Proc.) (List as per annex) LK-MOH-201855-GO-RFQ / 35 Assorted items for fixing doors partitioning for Pending Component 1: Emergency Request for Single Stage - One 2020-11- 2020-11- 2020-12- isolation at Welikanda IDA / 65950 Post Limited 1,068.00 0.00 Implement COVID-19 Response Quotations Envelope 02 28 05 Hospital during Covid ation period (Advance Proc.) (List as per annex) LK-MOH-201856-GO-RFQ / 100 Nos Prifiler Sanitizer Pending Component 1: Emergency Request for Single Stage - One 2020-11- 2020-11- 2020-12- required by Walikanda IDA / 65950 Post Limited 4,670.00 0.00 Implement COVID-19 Response Quotations Envelope 02 28 05 Hospital during Covid ation period (Advance Proc.) LK-MOH-201857-GO-RFQ / 11 associated items for Electrical wiring for Pending Component 1: Emergency Request for Single Stage - One 2020-11- 2020-11- 2020-12- Walikander Covid patient IDA / 65950 Post Limited 237.00 0.00 Implement COVID-19 Response Quotations Envelope 02 28 05 center during Covid ation period.(Advance Proc.) (List attached) LK-MOH-201858-GO-RFQ / 07 hardware items Pending Component 1: Emergency Request for Single Stage - One 2020-11- 2020-11- 2020-12- required by Walikanda Covid IDA / 65950 Post Limited 2,084.00 0.00 Implement COVID-19 Response Quotations Envelope 02 28 05 patient Hospital during ation Covid period.( List attached) (Advance proc.) LK-MOH-201859-GO-RFQ / 05 items of cleaning Pending materials required by Component 1: Emergency Request for Single Stage - One 2020-11- 2020-11- 2020-12- IDA / 65950 Post Limited 1,852.00 0.00 Implement Walikanda Covid patient COVID-19 Response Quotations Envelope 02 28 05 ation center during Covid period (List attached) (Advance Proc.) LK-MOH-201861-GO-RFQ / 03 items of disinfectants Pending Component 1: Emergency Request for Single Stage - One 2020-11- 2020-11- 2020-12- required by Walikanda Covid IDA / 65950 Post Limited 1,966.00 0.00 Implement COVID-19 Response Quotations Envelope 02 28 05 patient center List as per ation annex) (Advance proc.) LK-MOH-201862-GO-RFQ / 07 Electrical consumables Pending required by Walikanda Covid Component 1: Emergency Request for Single Stage - One 2020-11- 2020-11- 2020-12- IDA / 65950 Post Limited 152.00 0.00 Implement patient center during Covid COVID-19 Response Quotations Envelope 02 28 05 ation period. (List attached) Advance proc.) LK-MOH-201864-GO-RFQ / 05 cleaning items required Pending Component 1: Emergency Request for Single Stage - One 2020-11- 2020-11- 2020-12- by Walikanda Covid patient IDA / 65950 Post Limited 1,343.00 0.00 Implement COVID-19 Response Quotations Envelope 02 28 05 center during Covid period ation (List attached) (Advance proc.) LK-MOH-201865-GO-RFQ / 30,000 Nos Shopping Pending bags & 50,000 Nos Grocery Component 1: Emergency Request for Single Stage - One 2020-11- 2020-11- 2020-12- IDA / 65950 Post Limited 599.00 0.00 Implement Bags required by Walikanda COVID-19 Response Quotations Envelope 02 28 05 ation Covid patient center during Covid period LK-MOH-201866-GO-RFQ / 80,000 Nos Garbage bags Pending Component 1: Emergency Request for Single Stage - One 2020-11- 2020-11- 2020-12- required by Walikanda Covid IDA / 65950 Post Limited 4,125.00 0.00 Implement COVID-19 Response Quotations Envelope 02 28 05 patient center during Covid ation period (Advance proc.) LK-MOH-201867-GO-RFQ / 09 Household Items Pending Component 1: Emergency Request for Single Stage - One 2020-11- 2020-11- 2020-12- required by Walikanda Covid IDA / 65950 Post Limited 1,035.00 0.00 Implement COVID-19 Response Quotations Envelope 02 28 05 patient center during Covid ation period (liast attached (Advance proc.) LK-MOH-201869-GO-RFQ / 06 items of Hospital Attires for Hospital staff Pending Component 1: Emergency Request for Single Stage - One 2020-11- 2020-11- 2020-12- required by Welikanda Covid IDA / 65950 Post Limited 3,901.00 0.00 Implement COVID-19 Response Quotations Envelope 02 28 05 patient center during Covid ation period(List attached) (Advance Proc.) LK-MOH-202150-GO-RFQ / 750 Check Bed Sheet Pending Cloths & 750 White Bed Component 1: Emergency Request for Single Stage - One 2020-11- 2020-11- 2020-12- IDA / 65950 Post Limited 5,139.00 0.00 Implement Sheet Cloth required COVID-19 Response Quotations Envelope 04 30 07 ation Polonnaruwa DH during Covid period, Advance proc.) LK-MOH-202151-GO-RFQ / 55 Associated materials Pending Component 1: Emergency Request for Single Stage - One 2020-11- 2020-11- 2020-12- for partitioning at IDA / 65950 Post Limited 9,225.00 0.00 Implement COVID-19 Response Quotations Envelope 04 30 07 Polonnaruwa DH during ation Covid period (List attached) (Advance proc.) LK-MOH-202152-GO-RFQ / 61 Plumbing and Pending associated items required Component 1: Emergency Request for Single Stage - One 2020-11- 2020-11- 2020-12- IDA / 65950 Post Limited 763.00 0.00 Implement for Polonnaruwa DH during COVID-19 Response Quotations Envelope 04 30 07 ation Covid period. (List attached) (Advance proc) LK-MOH-202153-GO-RFQ / 33 Items of Paint, Pending Plumbing and associated Component 1: Emergency Request for Single Stage - One 2020-11- 2020-11- 2020-12- IDA / 65950 Post Limited 411.00 0.00 Implement materials required for COVID-19 Response Quotations Envelope 04 30 07 ation Polonnaruwa DH during Covid period. list attached) (Advance proc.) LK-MOH-202154-GO-RFQ / 37 Items of Hardware Pending materials required by Component 1: Emergency Request for Single Stage - One 2020-11- 2020-11- 2020-12- IDA / 65950 Post Limited 309.00 0.00 Implement Polonnaruwa DH during COVID-19 Response Quotations Envelope 04 30 07 ation Covid period. (List attached) (Advance proc) LK-MOH-202155-GO-RFQ / 36 Items of Aluminum petitioning materials and Pending Component 1: Emergency Request for Single Stage - One 2020-11- 2020-11- 2020-12- other associated materials IDA / 65950 Post Limited 2,416.00 0.00 Implement COVID-19 Response Quotations Envelope 04 30 07 required by Polonnaruwa DH ation during Covid period. (List attached) (Advance proc) LK-MOH-202156-GO-RFQ / 40 mtrs 16mm Aluminum Pending Wire, 01 no 70 Amp MCBC Component 1: Emergency Request for Single Stage - One 2020-11- 2020-11- 2020-12- IDA / 65950 Post Limited 138.00 0.00 Implement and 10 Nos 16x8 Lugs COVID-19 Response Quotations Envelope 04 30 07 ation required by Polonnaruwa DH during Covid period. (Advance proc) LK-MOH-202157-GO-RFQ / 02 Nos Photocopy Pending Component 1: Emergency Request for Single Stage - One 2020-11- 2020-11- 2020-12- Machines required by IDA / 65950 Post Limited 1,937.00 0.00 Implement COVID-19 Response Quotations Envelope 04 30 07 Polonnaruwa DH during ation Covid period. (Advance proc) LK-MOH-202159-GO-RFQ / 100 Nos Baskets, 50 Nos Pillows, 50 Mosquito Nets Pending Component 1: Emergency Request for Single Stage - One 2020-11- 2020-11- 2020-12- and 250 Mtrs white IDA / 65950 Post Limited 207.00 0.00 Implement COVID-19 Response Quotations Envelope 04 30 07 Polythene required by ation Polonnaruwa DH during Covid period. (Advance Proc.) LK-MOH-202160-GO-RFQ / 100 Nos Multi Plug Base Pending Component 1: Emergency Request for Single Stage - One 2020-11- 2020-11- 2020-12- required by Polonnaruwa DH IDA / 65950 Post Limited 319.00 0.00 Implement COVID-19 Response Quotations Envelope 04 30 07 during Covid period. ation (Advance Proc.) LK-MOH-202161-GO-RFQ / Supply and installation of 03 Nos 12,000 BTU Air Conditioners, 11 Nos 18,000 BTU Air Pending Component 1: Emergency Request for Single Stage - One 2020-11- 2020-11- 2020-12- Conditioners, 08 Nos IDA / 65950 Post Limited 21,374.00 0.00 Implement COVID-19 Response Quotations Envelope 04 30 07 24,000 BTU Air ation Conditioners and 7 Nos 36,000 BTU air Conditioners required by Walikanda treatment Polonnaruwa DH during Covid period. (Advance Proc.) LK-MOH-202363-GO-RFQ / 06 nos Working Pending Cupboards and 05 Nos Component 1: Emergency Request for Single Stage - One 2020-11- 2020-12- 2020-12- IDA / 65950 Post Limited 1,457.00 0.00 Implement Towel Racks required by COVID-19 Response Quotations Envelope 05 01 08 ation Polonnaruwa DH during Covid period (Advance proc.) LK-MOH-202364-GO-RFQ / 30 nos Tables, 30 Nos Almirahs, 20 Nos Bok Racks, Pending Component 1: Emergency Request for Single Stage - One 2020-11- 2020-12- 2020-12- 10 Nos Shoe Racks and 03 IDA / 65950 Post Limited 5,005.00 0.00 Implement COVID-19 Response Quotations Envelope 05 01 08 Nos Mirrors required by ation Polonnaruwa DH during Covid period (Advance proc.) LK-MOH-202365-GO-RFQ / 60 Ltrs Emulsion paints, 60Ltrs Weather Guard Paints Pending Component 1: Emergency Request for Single Stage - One 2020-11- 2020-12- 2020-12- and 100 nos Sand Papers IDA / 65950 Post Limited 578.00 0.00 Implement COVID-19 Response Quotations Envelope 05 01 08 required by Polonnaruwa DH ation during Covid period (Advance proc.) LK-MOH-202366-GO-RFQ / 20 Nos Stand Fans and 30 Pending Component 1: Emergency Request for Single Stage - One 2020-11- 2020-12- 2020-12- Nos Civiling Fans required IDA / 65950 Post Limited 1,923.00 0.00 Implement COVID-19 Response Quotations Envelope 05 01 08 by Polonnaruwa DH during ation Covid period (Advance proc.) LK-MOH-202367-GO-RFQ / 25 Nos Shopping Trolleys Pending Component 1: Emergency Request for Single Stage - One 2020-11- 2020-12- 2020-12- required by Polonnaruwa DH IDA / 65950 Post Limited 2,740.00 0.00 Implement COVID-19 Response Quotations Envelope 05 01 08 during Covid period ation (Advance proc.) LK-MOH-202368-GO-RFQ / 200 Nos Pillow Cases, 60 Pending Pairs Half Shoes and 03 Nos Component 1: Emergency Request for Single Stage - One 2020-11- 2020-12- 2020-12- IDA / 65950 Post Limited 709.00 0.00 Implement Carrot Beaters required by COVID-19 Response Quotations Envelope 05 01 08 ation Polonnaruwa DH during Covid period (Advance proc.) LK-MOH-202369-GO-RFQ / 50Nos Shavers and 300 Pending Component 1: Emergency Request for Single Stage - One 2020-11- 2020-12- 2020-12- Nos Toilet Bowl Cleaners IDA / 65950 Post Limited 221.00 0.00 Implement COVID-19 Response Quotations Envelope 05 01 08 required by Polonnaruwa DH ation during Covid period (Advance proc.) LK-MOH-202370-GO-RFQ / 10Nos Industrial Fans Pending Component 1: Emergency Request for Single Stage - One 2020-11- 2020-12- 2020-12- required by Polonnaruwa DH IDA / 65950 Post Limited 841.00 0.00 Implement COVID-19 Response Quotations Envelope 05 01 08 during Covid period ation (Advance proc.) LK-MOH-202371-GO-RFQ / 06 Items of Electrical Pending Component 1: Emergency Request for Single Stage - One 2020-11- 2020-12- 2020-12- consumables required by IDA / 65950 Post Limited 978.00 0.00 Implement COVID-19 Response Quotations Envelope 05 01 08 Polonnaruwa DH during ation Covid period (Advance proc.) LK-MOH-202372-GO-RFQ / 04 items of electrical Pending Component 1: Emergency Request for Single Stage - One 2020-11- 2020-12- 2020-12- consumables required by IDA / 65950 Post Limited 751.00 0.00 Implement COVID-19 Response Quotations Envelope 05 01 08 Polonnaruwa DH during ation Covid period. (Advance proc,) LK-MOH-202373-GO-RFQ / 60 Items of Hardware materials required for Pending Component 1: Emergency Request for Single Stage - One 2020-11- 2020-12- 2020-12- patient treatment centers IDA / 65950 Post Limited 12,381.00 0.00 Implement COVID-19 Response Quotations Envelope 05 01 08 required by Polonnaruwa DH ation during Covid period.(List attached) (Advance proc,) LK-MOH-202374-GO-RFQ / 42 items of Hardware materials required for Pending Component 1: Emergency Request for Single Stage - One 2020-11- 2020-12- 2020-12- patient treatment centers IDA / 65950 Post Limited 10,531.00 0.00 Implement COVID-19 Response Quotations Envelope 05 01 08 required by Polonnaruwa DH ation during Covid period.(As per attached list) (Advance proc,) Page 15 LK-MOH-202375-GO-RFQ / 9 items of Electrical consumables for patient Pending Component 1: Emergency Request for Single Stage - One 2020-11- 2020-12- 2020-12- treatment centers required IDA / 65950 Post Limited 440.00 0.00 Implement COVID-19 Response Quotations Envelope 05 01 08 by Polonnaruwa DH during ation Covid period.(As per attached list) (Advance proc,) LK-MOH-202376-GO-RFQ / 24 items of Hardware materials for patient Pending Component 1: Emergency Request for Single Stage - One 2020-11- 2020-12- 2020-12- treatment centers required IDA / 65950 Post Limited 429.00 0.00 Implement COVID-19 Response Quotations Envelope 05 01 08 by Polonnaruwa DH during ation Covid period.(As per attached list) (Advance proc,) LK-MOH-202377-GO-RFQ / 10Nos Desktop Pending Computers for patient Component 1: Emergency Request for Single Stage - One 2020-11- 2020-12- 2020-12- IDA / 65950 Post Limited 6,484.00 0.00 Implement treatment centers required COVID-19 Response Quotations Envelope 05 01 08 ation by Polonnaruwa DH during Covid period.(As per attached list) (Advance proc,) LK-MOH-202379-GO-RFQ / 05 items of Electrical Pending consumables required by Component 1: Emergency Request for Single Stage - One 2020-11- 2020-12- 2020-12- IDA / 65950 Post Limited 907.00 0.00 Implement Polonnaruwa DH during COVID-19 Response Quotations Envelope 05 01 08 ation Covid period (List attached). (Advance proc,) LK-MOH-202380-GO-RFQ / 12 items of Electrical Pending consumables required by Component 1: Emergency Request for Single Stage - One 2020-11- 2020-12- 2020-12- IDA / 65950 Post Limited 520.00 0.00 Implement Polonnaruwa DH during COVID-19 Response Quotations Envelope 05 01 08 ation Covid period. (List attached) (Advance Proc.) LK-MOH-202381-GO-RFQ / 13 items of plumbing Pending consumables required by Component 1: Emergency Request for Single Stage - One 2020-11- 2020-12- 2020-12- IDA / 65950 Post Limited 297.00 0.00 Implement Polonnaruwa DH during COVID-19 Response Quotations Envelope 05 01 08 ation Covid period. (List attached) (Advance Proc.) LK-MOH-202382-GO-RFQ / 12 Items of Pain and Pending Painting materials required Component 1: Emergency Request for Single Stage - One 2020-11- 2020-12- 2020-12- IDA / 65950 Post Limited 228.00 0.00 Implement by Polonnaruwa DH during COVID-19 Response Quotations Envelope 05 01 08 ation Covid period. (List attached) (Advance Proc.) LK-MOH-202383-GO-RFQ / 11 items of Electrical Pending consumables required by Component 1: Emergency Request for Single Stage - One 2020-11- 2020-12- 2020-12- IDA / 65950 Post Limited 1,513.00 0.00 Implement Polonnaruwa DH during COVID-19 Response Quotations Envelope 05 01 08 ation Covid period. (Last attached) (Advance proc.) LK-MOH-202384-GO-RFQ / 03 Nos Transport Pending Component 1: Emergency Request for Single Stage - One 2020-11- 2020-12- 2020-12- Ventilators required by IDA / 65950 Post Limited 32,060.00 0.00 Implement COVID-19 Response Quotations Envelope 05 01 08 Polonnaruwa DH during ation Covid period. (Advance proc.) LK-MOH-202385-GO-RFQ / 20 Nos Digital Blood Pending Component 1: Emergency Request for Single Stage - One 2020-11- 2020-12- 2020-12- Pressure Meters required by IDA / 65950 Post Limited 663.00 0.00 Implement COVID-19 Response Quotations Envelope 05 01 08 Polonnaruwa DH during ation Covid period. (Advance proc.) LK-MOH-202386-GO-RFQ / 12 items of PCR testing Pending Consumables (List attached) Component 1: Emergency Request for Single Stage - One 2020-11- 2020-12- 2020-12- IDA / 65950 Post Limited 12,268.00 0.00 Implement required by Polonnaruwa DH COVID-19 Response Quotations Envelope 05 01 08 ation during Covid period. (Advance proc.) LK-MOH-202387-GO-RFQ / 03 Nos ICU Ventilators Pending Component 1: Emergency Request for Single Stage - One 2020-11- 2020-12- 2020-12- required by Polonnaruwa DH IDA / 65950 Post Limited 49,450.00 0.00 Implement COVID-19 Response Quotations Envelope 05 01 08 during Covid period ation (Advance Proc.) LK-MOH-202388-GO-RFQ / 01 No Bio Safety Cabinet Pending Component 1: Emergency Request for Single Stage - One 2020-11- 2020-12- 2020-12- (Double use) required by IDA / 65950 Post Limited 9,791.00 0.00 Implement COVID-19 Response Quotations Envelope 05 01 08 Polonnaruwa DH during ation Covid period (Advance Proc.) LK-MOH-202389-GO-RFQ / 01 no Sealed Bucket Safety Pending Component 1: Emergency Request for Single Stage - One 2020-11- 2020-12- 2020-12- Cabinet Centrifuge required IDA / 65950 Post Limited 3,862.00 0.00 Implement COVID-19 Response Quotations Envelope 05 01 08 by Polonnaruwa DH during ation Covid period. (advance proc.) LK-MOH-202390-GO-RFQ / 05 Parts of Hematology Pending Component 1: Emergency Request for Single Stage - One 2020-11- 2020-12- 2020-12- Analyzer required by IDA / 65950 Post Limited 17,582.00 0.00 Implement COVID-19 Response Quotations Envelope 05 01 08 Polonnaruwa DH during ation Covid period. (Advance Proc.) LK-MOH-202391-GO-RFQ / 01 No Portable Digital X- Pending Component 1: Emergency Request for Single Stage - One 2020-11- 2020-12- 2020-12- Ray Machine required by IDA / 65950 Post Limited 54,670.00 0.00 Implement COVID-19 Response Quotations Envelope 05 01 08 Polonnaruwa DH during ation Covid period. (Advance Proc.) LK-MOH-202392-GO-RFQ / 03 Nos transport Pending Component 1: Emergency Request for Single Stage - One 2020-11- 2020-12- 2020-12- Ventilators required by IDA / 65950 Post Limited 32,504.00 0.00 Implement COVID-19 Response Quotations Envelope 05 01 08 Polonnaruwa DH during ation Covid period. (Advance Proc.) LK-MOH-202393-GO-RFQ / 02 Nos ECG machines Pending Component 1: Emergency Request for Single Stage - One 2020-11- 2020-12- 2020-12- required by Polonnaruwa DH IDA / 65950 Post Limited 4,495.00 0.00 Implement COVID-19 Response Quotations Envelope 05 01 08 during Covid period. ation (Advance procurement) LK-MOH-202414-GO-RFQ Pending / 06 Nos Defibrillators Component 1: Emergency Request for Single Stage - One 2020-11- 2020-12- 2020-12- IDA / 65950 Post Limited 32,504.00 0.00 Implement required by Plonnaruwa DH COVID-19 Response Quotations Envelope 05 01 08 ation during Covid period. (Advance Proc.) LK-MOH-202415-GO-RFQ / 50 Nos Stethoscopes Pending Component 1: Emergency Request for Single Stage - One 2020-11- 2020-12- 2020-12- required during Covid IDA / 65950 Post Limited 1,332.00 0.00 Implement COVID-19 Response Quotations Envelope 05 01 08 period by Polonnaruwa ation DGH. (Advance proc.) LK-MOH-202417-GO-RFQ / 100 Nos Blood Pressure Pending Component 1: Emergency Request for Single Stage - One 2020-11- 2020-12- 2020-12- Apparatus required during IDA / 65950 Post Limited 6,044.00 0.00 Implement COVID-19 Response Quotations Envelope 05 01 08 Covid period by ation Polonnaruwa DGH. (Advance proc.) LK-MOH-202419-GO-RFQ / 10Nos Infrared Pending Component 1: Emergency Request for Single Stage - One 2020-11- 2020-12- 2020-12- Thermometers required by IDA / 65950 Post Limited 975.00 0.00 Implement COVID-19 Response Quotations Envelope 05 01 08 Polonnaruwa DH during ation Covid period. (Advance proc.) LK-MOH-202420-GO-RFQ / 10 Nos Suction Apparatus Pending Component 1: Emergency Request for Single Stage - One 2020-11- 2020-12- 2020-12- - double Jar required by IDA / 65950 Post Limited 16,401.00 0.00 Implement COVID-19 Response Quotations Envelope 05 01 08 Polonnaruwa DH during ation Covid period. (Advance proc.) LK-MOH-202421-GO-RFQ / 01 No Portable RO Plant Pending Component 1: Emergency Request for Single Stage - One 2020-11- 2020-12- 2020-12- required by Polonnaruwa DH IDA / 65950 Post Limited 2,473.00 0.00 Implement COVID-19 Response Quotations Envelope 05 01 08 during Covid period. ation (Advance proc.) LK-MOH-202422-GO-RFQ / 08 Nos Bi-PAP required Pending Component 1: Emergency Request for Single Stage - One 2020-11- 2020-12- 2020-12- during Covid period by IDA / 65950 Post Limited 51,868.00 0.00 Implement COVID-19 Response Quotations Envelope 05 01 08 Polonnaruwa DGH (Advance ation proc.) LK-MOH-202423-GO-RFQ / 05 Nos ICU Beds required Pending Component 1: Emergency Request for Single Stage - One 2020-11- 2020-12- 2020-12- during Covid period by IDA / 65950 Post Limited 13,695.00 0.00 Implement COVID-19 Response Quotations Envelope 05 01 08 Polonnaruwa DGH (Advance ation proc.) LK-MOH-202424-GO-RFQ / Supply and Installation of Pending AC Plant and Ventilator unit Component 1: Emergency Request for Single Stage - One 2020-11- 2020-12- 2020-12- IDA / 65950 Post Limited 41,717.00 0.00 Implement during Covid period by COVID-19 Response Quotations Envelope 05 01 08 ation Polonnaruwa DGH. (Advance proc.) LK-MOH-202425-GO-RFQ / 100 Nos Overhead Tables Pending Component 1: Emergency Request for Single Stage - One 2020-11- 2020-12- 2020-12- required during Covid IDA / 65950 Post Limited 8,011.00 0.00 Implement COVID-19 Response Quotations Envelope 05 01 08 period by Polonnaruwa ation DGH. (Advance proc.) LK-MOH-202427-GO-RFQ / 04 Nos Video Pending Component 1: Emergency Request for Single Stage - One 2020-11- 2020-12- 2020-12- Laryngoscope required IDA / 65950 Post Limited 13,077.00 0.00 Implement COVID-19 Response Quotations Envelope 05 01 08 during Covid period by ation Polonnaruwa DGH. (Advance proc.) LK-MOH-202429-GO-RFQ / 14 Items of materials Pending Component 1: Emergency Request for Single Stage - One 2020-11- 2020-12- 2020-12- required for Fencing work at IDA / 65950 Post Limited 25,259.00 0.00 Implement COVID-19 Response Quotations Envelope 10 13 27 Covid 19 Patient Treatment ation Center. (List Attached) LK-MOH-203382-GO-DIR / 20 Nos Medical Air 47 Ltr Pending Component 1: Emergency Request for Single Stage - One 2020-11- 2020-12- 2021-01- Standard Cylinders and 02 IDA / 65950 Post Limited 3,133.00 0.00 Implement COVID-19 Response Quotations Envelope 17 20 03 Nos Nitrous 47Ltrs Standard ation Cylinders LK-MOH-203405-GO-RFQ / 10 Nos Chairs, 14 Nos Pending Office Cupboard (with racks Component 1: Emergency Request for Single Stage - One 2020-11- 2020-12- 2021-01- TF / B3017 Post Limited 3,679.00 0.00 Implement & Glass doors)and 01 No COVID-19 Response Quotations Envelope 24 29 28 ation Cupboard with locker for Mental Health Directorate. (Grant) LK-MOH-203411-GO-RFQ Pending / 10Items of IT and Office Component 1: Emergency Request for Single Stage - One 2020-11- 2020-12- 2021-01- TF / B3017 Post Limited 33,191.00 0.00 Implement equipment for Mental Heath COVID-19 Response Quotations Envelope 24 29 28 ation Directorate. (Grant) LK-MOH-203439-GO-RFB / Desktop Computers with UPS 1363 Nos, Low end Multi function Photocopier 1353 Nos, Laptop 34 Nos Pending Component 1: Emergency Single Stage - One 2020-11- 2020-11- 2020-12- 2020-12- 2021-01- 2021-03- Multimedia Projector 13 Nos IDA / 65950 Post Request for Bids Open - National 1,886,423.00 0.00 Implement COVID-19 Response Envelope 12 17 08 22 19 20 and Portable Hard Disc 2 TB ation 05 Nos for Epidemiology unit , NIHS , 982 hospitals in all districts for disaster management LK-MOH-203455-GO-RFQ / Supply, Installation, Pending Testing and commissioning Component 1: Emergency Request for Single Stage - One 2020-11- 2021-01- 2021-07- TF / B3017 Post Limited 38,162.00 0.00 Implement of 12 Items of Audio Visual COVID-19 Response Quotations Envelope 24 19 18 ation Equipment for Health Promotion Bureau. (Grant) LK-MOH-199380-GO-RFQ / IT and Office equipment to Component 1: Emergency Request for Single Stage - One 2020-11- 2020-11- 2020-11- TF / B3017 Post Limited 264,806.00 0.00 Canceled improve the surveillance COVID-19 Response Quotations Envelope 01 22 29 system LK-MOH-203576-GO-RFB / Supply and Installation of Pending 10 Nos Multi Para Monitors Component 1: Emergency Single Stage - One 2020-11- 2020-11- 2020-12- 2021-01- 2021-02- 2021-08- IDA / 65950 Post Request for Bids Open - National 11,622.00 0.00 Implement (Basic) at General Hospital, COVID-19 Response Envelope 07 12 24 23 27 26 ation Badulla during Covid period wave 1(Advance) LK-MOH-203577-GO-RFB / Supply and installation of Pending 03 Nos Multipara Monitors Component 1: Emergency Single Stage - One 2020-11- 2020-11- 2020-12- 2021-01- 2021-02- 2021-08- IDA / 65950 Post Request for Bids Open - National 53,514.00 0.00 Implement (ICU) for General Hospital, COVID-19 Response Envelope 07 12 24 23 27 26 ation Badulla during Covid period wave 1. (Advance) LK-MOH-203578-GO-RFB / Supply and Installation of Pending 01 No Ultra sound Scanner Component 1: Emergency Single Stage - One 2020-11- 2020-11- 2020-12- 2021-01- 2021-02- 2021-08- IDA / 65950 Post Request for Bids Open - National 53,243.00 0.00 Implement required by General COVID-19 Response Envelope 07 12 24 23 27 26 ation Hospital, Badulla during Covid period wave 1 (Advance) LK-MOH-203579-GO-RFB / Supply and Installation of Pending 02 Nos Patient Warmers are Component 1: Emergency Single Stage - One 2020-11- 2020-11- 2020-12- 2021-01- 2021-02- 2021-08- IDA / 65950 Post Request for Bids Open - National 3,351.00 0.00 Implement required by General COVID-19 Response Envelope 07 12 24 23 27 26 ation Hospital, Badulla during Covid period wave 1 (Advance) LK-MOH-203580-GO-RFB / 10 Nos portable Suckers Pending Component 1: Emergency Single Stage - One 2020-11- 2020-11- 2020-12- 2021-01- 2021-02- 2021-08- are required by General IDA / 65950 Post Request for Bids Open - National 9,719.00 0.00 Implement COVID-19 Response Envelope 07 12 24 23 27 26 Hospital, Badulla during ation Covid period wave 1. (Advance) LK-MOH-203582-GO-RFB / 02 Nos Defibrillators Pending Component 1: Emergency Single Stage - One 2020-11- 2020-11- 2020-12- 2021-01- 2021-02- 2021-08- required by General IDA / 65950 Post Request for Bids Open - National 9,568.00 0.00 Implement COVID-19 Response Envelope 07 12 24 23 27 26 Hospital, Badulla during ation Covid period wave 1. (Advance) LK-MOH-203583-GO-RFB / 02 Nos ECG machines Pending Component 1: Emergency Single Stage - One 2020-11- 2020-11- 2020-12- 2021-01- 2021-02- 2021-08- required by General IDA / 65950 Post Request for Bids Open - National 1,297.00 0.00 Implement COVID-19 Response Envelope 07 12 24 23 27 26 Hospital, Badulla during ation Covid period wave 1. (Advance) LK-MOH-203584-GO-RFB / 01 Unit X-Ray mobile Pending Component 1: Emergency Single Stage - One 2020-11- 2020-11- 2020-12- 2021-01- 2021-02- 2021-08- Machine required by General IDA / 65950 Post Request for Bids Open - National 24,541.00 0.00 Implement COVID-19 Response Envelope 07 12 24 23 27 26 Hospital, Badulla during ation Covid period wave 1. (Advance) LK-MOH-203585-GO-RFB / Supply & installation of central Monitoring system Pending Component 1: Emergency Single Stage - One 2020-11- 2020-11- 2020-12- 2021-01- 2021-02- 2021-08- with 03 Nos of ICU IDA / 65950 Post Request for Bids Open - National 53,514.00 0.00 Implement COVID-19 Response Envelope 07 12 24 23 27 26 Multipara Monitors required ation by General Hospital, Badulla during Covid period wave 1 (Advance) LK-MOH-203587-GO-RFB / Supply & Installation of 0 Pending No Ultra Sound scanner Gyn Component 1: Emergency Single Stage - One 2020-11- 2020-11- 2020-12- 2021-01- 2021-02- 2021-08- IDA / 65950 Post Request for Bids Open - National 37,838.00 0.00 Implement & Obs. required by General COVID-19 Response Envelope 07 12 24 23 27 26 ation Hospital, Badulla during Covid period wave 1 (Advance) LK-MOH-203588-GO-RFB / Supply and Installation of Pending 02 Nos Bio Safety Cabinet - Component 1: Emergency Single Stage - One 2020-11- 2020-11- 2020-12- 2021-01- 2021-02- 2021-08- IDA / 65950 Post Request for Bids Open - National 15,178.00 0.00 Implement Class ii A required by COVID-19 Response Envelope 07 12 24 23 27 26 ation General Hospital, Badulla during Covid period wave 1 (Advance) LK-MOH-203589-GO-RFB / Supply and Installation of Pending 01 No Real Time PCR Component 1: Emergency Single Stage - One 2020-11- 2020-11- 2020-12- 2021-01- 2021-02- 2021-08- IDA / 65950 Post Request for Bids Open - National 21,622.00 0.00 Implement Machine required by General COVID-19 Response Envelope 07 12 24 23 27 26 ation Hospital, Badulla during Covid period wave 1 (Advance) LK-MOH-203590-GO-RFB / Supply and Installation of Pending 01 No PCR Hood required Component 1: Emergency Single Stage - One 2020-11- 2020-11- 2020-12- 2021-01- 2021-02- 2021-08- IDA / 65950 Post Request for Bids Open - National 4,222.00 0.00 Implement by General Hospital, Badulla COVID-19 Response Envelope 07 12 24 23 27 26 ation during Covid period wave 1 (Advance) LK-MOH-203643-GO-RFQ / 05 Nos Micro Pipets Pending Component 1: Emergency Request for Single Stage - One 2020-11- 2021-01- 2021-07- required by General IDA / 65950 Post Limited 5,189.00 0.00 Implement COVID-19 Response Quotations Envelope 13 08 07 Hospital, Badulla during ation Covid period wave 1 (Advance) LK-MOH-203642-GO-RFQ / PCR Reagent required by Pending Component 1: Emergency Request for Single Stage - One 2020-11- 2021-01- 2021-07- General Hospital, Badulla IDA / 65950 Post Limited 10,946.00 0.00 Implement COVID-19 Response Quotations Envelope 13 08 07 during Covid period wave 1. ation (Advance) LK-MOH-203644-GO-RFQ / PCR Reagents required by Pending Component 1: Emergency Request for Single Stage - One 2020-11- 2021-01- 2021-07- General Hospital, Badulla IDA / 65950 Post Limited 21,862.00 0.00 Implement COVID-19 Response Quotations Envelope 13 08 07 during Covid period wave 1. ation (Advance) LK-MOH-203645-GO-RFQ / Supply and Installation of Pending Micro Centrifuge required Component 1: Emergency Request for Single Stage - One 2020-11- 2021-01- 2021-07- IDA / 65950 Post Limited 3,649.00 0.00 Implement by General Hospital, Badulla COVID-19 Response Quotations Envelope 13 08 07 ation during Covid period wave 1. (Advance) Page 16 LK-MOH-203646-GO-RFQ / 01 No. Heat Block Pending Component 1: Emergency Request for Single Stage - One 2020-11- 2021-01- 2021-07- required by General IDA / 65950 Post Limited 438.00 0.00 Implement COVID-19 Response Quotations Envelope 13 08 07 Hospital, Badulla during ation Covid period wave 1. (Advance) LK-MOH-203647-GO-RFQ / 783 Nos Overall Kits Pending Component 1: Emergency Request for Single Stage - One 2020-11- 2021-01- 2021-07- required by General IDA / 65950 Post Limited 5,399.00 0.00 Implement COVID-19 Response Quotations Envelope 13 08 07 Hospital, Badulla during ation Covid period wave 1. (Advance) LK-MOH-203648-GO-RFQ / 10 Nos Infrared Pending Component 1: Emergency Request for Single Stage - One 2020-11- 2021-01- 2021-07- Thermometers required by IDA / 65950 Post Limited 1,000.00 0.00 Implement COVID-19 Response Quotations Envelope 13 08 07 General Hospital, Badulla ation during Covid period wave 1. (Advance) LK-MOH-203654-GO-RFQ / 40 Nos Sink (Large), 35 Kg 12mm Wire, 30 Nos Welding Pending Cross, 100 Nos Stop Vane Component 1: Emergency Request for Single Stage - One 2020-11- 2021-01- 2021-01- IDA / 65950 Post Limited 1,951.00 0.00 Implement and 25 Nos Swan Nec Taps COVID-19 Response Quotations Envelope 13 01 15 ation required for Anuradhapura Teaching Hospital during Covid period. (Advance) LK-MOH-203655-GO-RFQ / 12 Items of Plumbing Pending materials required for Component 1: Emergency Request for Single Stage - One 2020-11- 2021-01- 2021-01- IDA / 65950 Post Limited 1,331.00 0.00 Implement Anuradhapura Teaching COVID-19 Response Quotations Envelope 13 01 15 ation Hospital during Covid period. (Advance) LK-MOH-203656-GO-RFQ / 06 Items of Plumbing Pending materials required for Component 1: Emergency Request for Single Stage - One 2020-11- 2021-01- 2021-01- IDA / 65950 Post Limited 446.00 0.00 Implement Anuradhapura Teaching COVID-19 Response Quotations Envelope 13 01 15 ation Hospital during Covid period. (Advance) LK-MOH-203657-GO-RFQ / 500 Nos 7 x 10 Garbage Bags and 6,000 Packets of Pending Component 1: Emergency Request for Single Stage - One 2020-11- 2021-01- 2021-01- Paper Serviette required for IDA / 65950 Post Limited 2,065.00 0.00 Implement COVID-19 Response Quotations Envelope 13 01 15 Anuradhapura Teaching ation Hospital during Covid period.(Advance) LK-MOH-203658-GO-RFQ / 14 Items of Aluminum Bars and accessories Pending Component 1: Emergency Request for Single Stage - One 2020-11- 2021-01- 2021-01- required for partitioning IDA / 65950 Post Limited 740.00 0.00 Implement COVID-19 Response Quotations Envelope 13 01 15 works for Anuradhapura ation Teaching Hospital during Covid period.(Advance) LK-MOH-203660-GO-RFQ / 32 Items of Aluminium Bars & Accessories Pending Required for Partitioning & Component 1: Emergency Request for Single Stage - One 2020-11- 2021-01- 2021-01- IDA / 65950 Post Limited 2,653.00 0.00 Implement Assorted items for wiring COVID-19 Response Quotations Envelope 13 01 15 ation required for Anuradhapura Teaching Hospital during Covid period.(Advance) LK-MOH-203661-GO-RFQ / 16 Associated items for Pending wiring (List attached) Component 1: Emergency Request for Single Stage - One 2020-11- 2021-01- 2021-01- IDA / 65950 Post Limited 1,699.00 0.00 Implement required for Anuradhapura COVID-19 Response Quotations Envelope 13 01 15 ation Teaching Hospital during Covid period.(Advance) LK-MOH-203662-GO-RFQ / 12 Items of Aluminium associated items for Pending Component 1: Emergency Request for Single Stage - One 2020-11- 2021-01- 2021-01- partitioning work required IDA / 65950 Post Limited 598.00 0.00 Implement COVID-19 Response Quotations Envelope 13 01 15 for Anuradhapura Teaching ation Hospital during Covid period.(Advance) LK-MOH-203664-GO-RFQ / 35 Items of Aluminium Bars and Accessories for Pending Component 1: Emergency Request for Single Stage - One 2020-11- 2021-01- 2021-01- partitioning required for IDA / 65950 Post Limited 1,148.00 0.00 Implement COVID-19 Response Quotations Envelope 13 01 15 Anuradhapura Teaching ation Hospital during Covid period.(Advance) LK-MOH-203665-GO-RFQ / 400 Mtrs Poplin cloth, 500 Nos Baby Pampas, 200 Nos 1/2 aplastic pins, 25 Nos Mop Buckets, 30 Nos Plastic Pending Component 1: Emergency Request for Single Stage - One 2020-11- 2021-01- 2021-01- wash basin (Medium), 200 IDA / 65950 Post Limited 1,832.00 0.00 Implement COVID-19 Response Quotations Envelope 13 01 15 Nos 2'' binding tape, 1000 ation Nos Transparent sheet ,300 Mtrs 1/2 Elastic, 25 Nos Plastic dual pane required for Anuradhapura LK-MOH-203666-GO-RFQ / 14 Items of Aluminium Bars and accessories for Pending Component 1: Emergency Request for Single Stage - One 2020-11- 2021-01- 2021-01- Partitioning (List Attached) IDA / 65950 Post Limited 2,239.00 0.00 Implement COVID-19 Response Quotations Envelope 13 01 15 required for Anuradhapura ation Teaching Hospital during Covid period. (Advance) LK-MOH-203667-GO-RFQ / 65 Nos Elbow Taps and 05 Pending Nos Large Sinks required for Component 1: Emergency Request for Single Stage - One 2020-11- 2021-01- 2021-01- IDA / 65950 Post Limited 1,132.00 0.00 Implement Anuradhapura Teaching COVID-19 Response Quotations Envelope 13 01 15 ation Hospital during Covid period. (Advance) LK-MOH-203668-GO-RFQ / 18 Items of Aluminium fittings and accessories (List Pending Component 1: Emergency Request for Single Stage - One 2020-11- 2021-01- 2021-01- Attached) required for IDA / 65950 Post Limited 893.00 0.00 Implement COVID-19 Response Quotations Envelope 13 01 15 Anuradhapura Teaching ation Hospital during Covid period. (Advance) LK-MOH-203669-GO-RFQ / 23 associated Items of Pending Electrical wiring (List Component 1: Emergency Request for Single Stage - One 2020-11- 2021-01- 2021-01- IDA / 65950 Post Limited 440.00 0.00 Implement attached) required for COVID-19 Response Quotations Envelope 13 01 15 ation Anuradhapura Teaching Hospital during Covid period.(Advance) LK-MOH-203670-GO-RFQ / 32 Items of Aluminium fittings and accessories (List Pending Component 1: Emergency Request for Single Stage - One 2020-11- 2021-01- 2021-01- attached) required for IDA / 65950 Post Limited 3,326.00 0.00 Implement COVID-19 Response Quotations Envelope 13 01 15 Anuradhapura Teaching ation Hospital during Covid period.(Advance) LK-MOH-203671-GO-RFQ / 11 Items of Hardware Pending items & fittings (List Component 1: Emergency Request for Single Stage - One 2020-11- 2021-01- 2021-01- IDA / 65950 Post Limited 208.00 0.00 Implement attached) required for COVID-19 Response Quotations Envelope 13 01 15 ation Anuradhapura Teaching Hospital during Covid period. (Advance) LK-MOH-203672-GO-RFQ / 16 Items of Hardware Pending items & fittings (List Component 1: Emergency Request for Single Stage - One 2020-11- 2021-01- 2021-01- IDA / 65950 Post Limited 1,691.00 0.00 Implement attached) required for COVID-19 Response Quotations Envelope 13 01 15 ation Anuradhapura Teaching Hospital during Covid period. (Advance) LK-MOH-203673-GO-RFQ / 52 Items of Hardware Pending items & fittings (List Component 1: Emergency Request for Single Stage - One 2020-11- 2021-01- 2021-01- IDA / 65950 Post Limited 2,992.00 0.00 Implement attached) required for COVID-19 Response Quotations Envelope 13 01 15 ation Anuradhapura Teaching Hospital during Covid period. (Advance) LK-MOH-203674-GO-RFQ / 09 Items of Hardware Pending items & fittings (List Component 1: Emergency Request for Single Stage - One 2020-11- 2021-01- 2021-01- IDA / 65950 Post Limited 593.00 0.00 Implement attached) required for COVID-19 Response Quotations Envelope 13 01 15 ation Anuradhapura Teaching Hospital during Covid period. (Advance) LK-MOH-203675-GO-RFQ / 1000 Nos Bar Soap, 1,000 Nos Hand Wash, 150 Nos Pending Surfexel (1 Kg) and 200 Component 1: Emergency Request for Single Stage - One 2020-11- 2021-01- 2021-01- IDA / 65950 Post Limited 3,105.00 0.00 Implement Nos Washing Powder (1Kg) COVID-19 Response Quotations Envelope 13 01 15 ation required for Anuradhapura Teaching Hospital during Covid period.(Advance) LK-MOH-203693-GO-RFQ / 09 Items of Hardware materials (List Pending Component 1: Emergency Request for Single Stage - One 2020-11- 2021-01- 2021-01- attached)required for IDA / 65950 Post Limited 242.00 0.00 Implement COVID-19 Response Quotations Envelope 13 01 15 Anuradhapura Teaching ation Hospital during Covid period.(Advance) LK-MOH-203694-GO-RFQ / 09 items of Stationery and Pending other items (List attached) Component 1: Emergency Request for Single Stage - One 2020-11- 2021-01- 2021-01- IDA / 65950 Post Limited 216.00 0.00 Implement required for Anuradhapura COVID-19 Response Quotations Envelope 13 01 15 ation Teaching Hospital during Covid period. (Advance) LK-MOH-203696-GO-RFQ / 08 Lengths 4" PVC Pipe,15 Lengths 2"PVC Pipe, 08 Nos Pending Plan Sockets 2", 01 no 4" T- Component 1: Emergency Request for Single Stage - One 2020-11- 2021-01- 2021-01- IDA / 65950 Post Limited 473.00 0.00 Implement Sockets and 500ml Slone COVID-19 Response Quotations Envelope 13 01 15 ation Glue required for Anuradhapura Teaching Hospital during Covid period. (Advance) LK-MOH-203720-GO-RFQ / 5X3 Stand Board 15 Nos,12x8 Board 02 Nos, Pending Component 1: Emergency Request for Single Stage - One 2020-11- 2021-01- 2021-01- 6x4 Board 3 Nos, and 1.5x2 IDA / 65950 Post Limited 1,547.00 0.00 Implement COVID-19 Response Quotations Envelope 14 02 16 Banner 14 Nos required for ation Anuradhapura Teaching Hospital during Covid period. (Advance) LK-MOH-203722-GO-RFQ / 41 Items of partitioning Pending related items (List attached) Component 1: Emergency Request for Single Stage - One 2020-11- 2021-01- 2021-01- IDA / 65950 Post Limited 2,339.00 0.00 Implement required for Anuradhapura COVID-19 Response Quotations Envelope 14 02 16 ation Teaching Hospital during Covid period. (Advance) LK-MOH-203723-GO-RFQ / 10 Items of Partitioning Pending related items (List attached) Component 1: Emergency Request for Single Stage - One 2020-11- 2021-01- 2021-01- IDA / 65950 Post Limited 323.00 0.00 Implement required for Anuradhapura COVID-19 Response Quotations Envelope 14 02 16 ation Teaching Hospital during Covid period. (Advance) LK-MOH-203724-GO-RFQ / 33 Items of Partitioning related materials (List Pending Component 1: Emergency Request for Single Stage - One 2020-11- 2021-01- 2021-01- attached) required for IDA / 65950 Post Limited 2,908.00 0.00 Implement COVID-19 Response Quotations Envelope 14 02 16 Anuradhapura Teaching ation Hospital during Covid period. (Advance) Pending LK-MOH-203741-GO-RFQ Component 1: Emergency Request for Single Stage - One 2020-12- 2020-12- 2021-01- IDA / 65950 Post Limited 162,162.00 0.00 Implement / 1,500 Nos Patient Beds COVID-19 Response Quotations Envelope 01 27 03 ation Pending LK-MOH-203748-GO-RFQ Component 1: Emergency Request for Single Stage - One 2020-11- 2020-12- 2021-01- IDA / 65950 Post Limited 32,432.00 0.00 Implement / 1,500 Nos Mattresses COVID-19 Response Quotations Envelope 30 26 02 ation LK-MOH-203750-GO-RFQ Pending / 1,500 Nos Pillows, 4,500 Component 1: Emergency Request for Single Stage - One 2020-11- 2020-12- 2021-01- IDA / 65950 Post Limited 40,951.00 0.00 Implement Nos Pillow Cases and 4,500 COVID-19 Response Quotations Envelope 30 26 02 ation Nos Bed Sheets LK-MOH-203805-GO-RFQ / Supply and installation of Pending 3 Nos CCTV systems for Component 1: Emergency Request for Single Stage - One 2020-12- 2021-01- 2021-07- IDA / 65950 Post Limited 9,730.00 0.00 Implement Bandarawela COVID-19 Response Quotations Envelope 05 30 29 ation ,Bogahakumbura & Uraniya Hospitals Badulla DH LK-MOH-203810-GO-RFQ / Supply of essential Pending Component 1: Emergency Request for Single Stage - One 2020-12- 2021-01- 2021-07- building materials for IDA / 65950 Post Limited 1,322.00 0.00 Implement COVID-19 Response Quotations Envelope 05 30 29 renovation and modification ation of the hospital at Ambalangoda DH-Galle LK-MOH-203823-GO-RFQ / Supply of essential Pending Component 1: Emergency Request for Single Stage - One 2020-12- 2021-01- 2021-07- building materials for IDA / 65950 Post Limited 22,703.00 0.00 Implement COVID-19 Response Quotations Envelope 05 30 29 renovation and modification ation of the hospital at Karandeniya DH Galle LK-MOH-203835-GO-RFQ Pending / Supply and Installation of Component 1: Emergency Request for Single Stage - One 2020-12- 2021-01- 2021-07- IDA / 65950 Post Limited 8,108.00 0.00 Implement CCTV system at COVID-19 Response Quotations Envelope 05 30 29 ation Vidaththalthivu Mannar DH LK-MOH-203937-GO-RFQ / Supply & Installation of 4 Nos CCTV systems for Pending Component 1: Emergency Request for Single Stage - One 2020-12- 2021-01- 2021-07- Padhiyathalawa , Palamunai IDA / 65950 Post Limited 15,135.00 0.00 Implement COVID-19 Response Quotations Envelope 05 30 29 , Karadiyanaru , ation Eachchilampattu, Eastern Province LK-MOH-203938-GO-RFQ / Supply & Installation of 4 Nos PABX systems for Pending Component 1: Emergency Request for Single Stage - One 2020-12- 2021-01- 2021-07- Padhiyathalawa , Palamunai IDA / 65950 Post Limited 19,459.00 0.00 Implement COVID-19 Response Quotations Envelope 05 30 29 , Karadiyanaru , ation Eachchilampattu, Eastern Province LK-MOH-203939-GO-RFQ / Supply of material for Pending Essential modification to Component 1: Emergency Request for Single Stage - One 2020-12- 2021-01- 2021-07- IDA / 65950 Post Limited 29,189.00 0.00 Implement establish Covid-19 ward at COVID-19 Response Quotations Envelope 05 30 29 ation DH Weligama, Sothern Province LK-MOH-203940-GO-RFQ / Essential items required Pending Component 1: Emergency Request for Single Stage - One 2020-12- 2021-01- 2021-07- for renovations of MS IDA / 65950 Post Limited 10,811.00 0.00 Implement COVID-19 Response Quotations Envelope 05 30 29 quarters for covid + ation patients at Kamburuoitiya BH LK-MOH-203941-GO-RFQ / Supply of material for Pending Component 1: Emergency Request for Single Stage - One 2020-12- 2021-01- 2021-07- Essential modification to IDA / 65950 Post Limited 21,634.00 0.00 Implement COVID-19 Response Quotations Envelope 05 30 29 establish Covid-19 ward at ation DH Dickwella LK-MOH-203943-GO-RFQ / Supply of material for Pending Component 1: Emergency Request for Single Stage - One 2020-12- 2021-01- 2021-07- Essential modification to IDA / 65950 Post Limited 6,486.00 0.00 Implement COVID-19 Response Quotations Envelope 05 30 29 establish Covid-19 ward at ation DH Ambalantota LK-MOH-203950-GO-RFQ Pending Component 1: Emergency Request for Single Stage - One 2020-12- 2021-01- 2021-07- / Supply of Hospital Attia IDA / 65950 Post Limited 10,812.00 0.00 Implement COVID-19 Response Quotations Envelope 05 30 29 for Kegalla DH ation LK-MOH-203967-GO-RFQ Pending / installation of CCTV Component 1: Emergency Request for Single Stage - One 2020-12- 2021-01- 2021-07- IDA / 65950 Post Limited 10,811.00 0.00 Implement system at special Isolation COVID-19 Response Quotations Envelope 05 30 29 ation unit DH A Kithulgala and Beligala LK-MOH-203970-GO-RFQ Pending Component 1: Emergency Request for Single Stage - One 2020-12- 2021-01- 2021-01- / Supply and installation of IDA / 65950 Post Limited 2,703.00 0.00 Implement COVID-19 Response Quotations Envelope 05 07 21 sound system at DGH ation Ampara LK-MOH-203972-GO-RFQ Pending / Supply and Installation of Component 1: Emergency Request for Single Stage - One 2020-12- 2021-01- 2021-01- IDA / 65950 Post Limited 32,432.00 0.00 Implement Industrial Washing Machine COVID-19 Response Quotations Envelope 05 07 21 ation at Ampara DGH LK-MOH-203974-GO-RFQ Pending Component 1: Emergency Request for Single Stage - One 2020-12- 2021-01- 2021-07- / Supply and Installation of IDA / 65950 Post Limited 16,216.00 0.00 Implement COVID-19 Response Quotations Envelope 05 30 29 CCTV system at Ampara ation DGH LK-MOH-203994-GO-DIR / The TONI-IV, The Wechsler Adult Intelligence Scale fourth edition, The Pending Repeatable Battery for Component 1: Emergency 2020-11- 2020-12- 2021-01- 2021-07- TF / B3017 Post Direct Selection Direct 3,233.73 0.00 Implement Neuropsychological COVID-19 Response 30 05 09 08 ation Assessment and The LOTCA and LOTCA-G tools are required by Collage of Psychiatric LK-MOH-203998-GO-DIR / The Neuropsychiatry unit Pending Component 1: Emergency 2020-11- 2020-12- 2021-01- 2021-07- Cognitive Assessment tool TF / B3017 Post Direct Selection Direct 164.95 0.00 Implement COVID-19 Response 30 05 09 08 required by Collage of ation Psychiatric Page 17 LK-MOH-204011-GO-RFQ / Development, Pending Establishment and Component 1: Emergency Request for Single Stage - One 2020-12- 2021-01- 2021-07- TF / B3017 Post Limited 28,541.00 0.00 Implement Maintenance of of 60 Nos COVID-19 Response Quotations Envelope 05 30 29 ation of Bill Boards in island wide required by Family Health Bureau. LK-MOH-205320-GO-RFQ / supply of building material Pending for improving Component 1: Emergency Request for Single Stage - One 2020-12- 2021-01- 2021-07- IDA / 65950 Post Limited 9,730.00 0.00 Implement Agunukolapalessa COVID-19 Response Quotations Envelope 05 30 29 ation agriculture school to be converted as intermediate care center LK-MOH-205331-GO-RFQ Pending / Supply and Installation of Component 1: Emergency Request for Single Stage - One 2020-12- 2021-01- 2021-07- IDA / 65950 Post Limited 8,108.00 0.00 Implement of Communication and COVID-19 Response Quotations Envelope 05 30 29 ation CCTV System at Buttala DH LK-MOH-205339-GO-DIR / Reagents for fully automated nucleic acid Pending extractors reagents for fully Component 1: Emergency 2020-11- 2020-12- 2021-01- 2021-07- IDA / 65950 Post Direct Selection Direct 1,297,297.00 0.00 Implement automated nucleic acid COVID-19 Response 30 05 09 08 ation extractors. Maxwell RSC x 2000 kits (228,000 Reactions) BGI x 150,000 reactions LK-MOH-205340-GO-DIR / BGI extraction kits ( the Pending requirement is 108 Boxes Component 1: Emergency 2020-11- 2020-12- 2021-01- 2021-07- IDA / 65950 Post Direct Selection Direct 594,595.00 0.00 Implement (180,000 reactions) for the COVID-19 Response 30 05 09 08 ation machine at CEBH- Mulleriyawa): LK-MOH-205341-GO-DIR Pending / Roche magNa pure 96 Component 1: Emergency 2020-11- 2020-12- 2021-01- 2021-07- IDA / 65950 Post Direct Selection Direct 583,784.00 0.00 Implement system extraction kit for BIA COVID-19 Response 30 05 09 08 ation three months requirement LK-MOH-205520-GO-RFQ / Urgently required medical equipment -digital BP Pending apparatus ,pulse oximeter , Component 1: Emergency Request for Single Stage - One 2020-12- 2021-01- 2021-07- IDA / 65950 Post Limited 140,541.00 0.00 Implement nebulizer ,ECG,IR COVID-19 Response Quotations Envelope 05 30 29 ation thermometer, CTG, Hand Held doppler for treatment center (annex 1) LK-MOH-205727-GO-RFB Pending / Urgently required medical Component 1: Emergency Single Stage - One 2020-11- 2020-12- 2021-01- 2021-02- 2021-03- 2021-09- IDA / 65950 Post Request for Bids Open - National 243,243.00 0.00 Implement equipment - ICU bed and COVID-19 Response Envelope 30 05 16 15 22 18 ation HDU bed (annex 1) LK-MOH-205544-GO-RFQ Pending / 30 Nos Sawing machines Component 1: Emergency Request for Single Stage - One 2020-12- 2021-02- 2021-08- TF / B3017 Post Limited 4,865.00 0.00 Implement for Mental Health COVID-19 Response Quotations Envelope 08 02 01 ation Rehabilitation units island wide LK-MOH-205546-GO-RFQ / 02 Nos Exercise and Pending Component 1: Emergency Request for Single Stage - One 2020-12- 2021-02- 2021-08- fitness machine for Mental TF / B3017 Post Limited 1,081.00 0.00 Implement COVID-19 Response Quotations Envelope 08 02 01 Health Rehabilitation units ation island wide LK-MOH-205633-GO-RFQ Pending / Procurement of Paint Component 1: Emergency Request for Single Stage - One 2020-12- 2021-01- 2021-01- IDA / 65950 Post Limited 105,028.00 0.00 Implement Items for quarantine and COVID-19 Response Quotations Envelope 13 08 15 ation patient management centers. LK-MOH-205634-GO-RFQ Pending / Procurement of Septic Component 1: Emergency Request for Single Stage - One 2020-12- 2021-01- 2021-01- IDA / 65950 Post Limited 25,722.00 0.00 Implement Tanks for quarantine and COVID-19 Response Quotations Envelope 13 08 15 ation patient management centers LK-MOH-205635-GO-RFQ Pending / Procurement of Tools for Component 1: Emergency Request for Single Stage - One 2020-12- 2021-01- 2021-01- IDA / 65950 Post Limited 21,719.00 0.00 Implement quarantine and patient COVID-19 Response Quotations Envelope 13 08 15 ation management centers LK-MOH-205636-GO-RFQ Pending / Procurement of Plywood Component 1: Emergency Request for Single Stage - One 2020-12- 2021-01- 2021-01- IDA / 65950 Post Limited 123,611.00 0.00 Implement Sheets for quarantine and COVID-19 Response Quotations Envelope 20 15 22 ation patient management centers LK-MOH-205637-GO-RFQ Pending / Procurement of Yard Items Component 1: Emergency Request for Single Stage - One 2020-12- 2021-01- 2021-01- IDA / 65950 Post Limited 137,396.00 0.00 Implement for quarantine and patient COVID-19 Response Quotations Envelope 20 15 22 ation management centers LK-MOH-205638-GO-RFQ Pending / Procurement of Cement Component 1: Emergency Request for Single Stage - One 2020-12- 2021-01- 2021-01- IDA / 65950 Post Limited 97,233.00 0.00 Implement for quarantine and patient COVID-19 Response Quotations Envelope 20 15 22 ation management centers LK-MOH-205640-GO-RFQ Pending / Procurement of Tile Items Component 1: Emergency Request for Single Stage - One 2020-12- 2021-01- 2021-01- IDA / 65950 Post Limited 190,236.00 0.00 Implement for quarantine and patient COVID-19 Response Quotations Envelope 20 15 22 ation management centers LK-MOH-205642-GO-RFQ Pending / Procurement of Sanitary Component 1: Emergency Request for Single Stage - One 2020-12- 2021-01- 2021-01- IDA / 65950 Post Limited 87,095.00 0.00 Implement Fittings for quarantine and COVID-19 Response Quotations Envelope 20 15 22 ation patient management centers LK-MOH-205643-GO-RFQ Pending / Procurement of Timber for Component 1: Emergency Request for Single Stage - One 2020-12- 2021-01- 2021-01- IDA / 65950 Post Limited 134,311.00 0.00 Implement quarantine and patient COVID-19 Response Quotations Envelope 20 15 22 ation management centers LK-MOH-205644-GO-RFQ / Procurement of Sandwich Pending Panel Items (Zn/Al Sheets) Component 1: Emergency Request for Single Stage - One 2020-12- 2021-01- 2021-01- IDA / 65950 Post Limited 186,059.00 0.00 Implement and GI Corrugated Sheets COVID-19 Response Quotations Envelope 20 15 22 ation for quarantine and patient management centers LK-MOH-205645-GO-RFQ Pending / Procurement of Electrical Component 1: Emergency Request for Single Stage - One 2020-12- 2021-01- 2021-01- IDA / 65950 Post Limited 198,879.00 0.00 Implement Wires for quarantine and COVID-19 Response Quotations Envelope 20 15 22 ation patient management centers LK-MOH-205646-GO-RFQ / Procurement of Fans & Pending Component 1: Emergency Request for Single Stage - One 2020-12- 2021-01- 2021-01- Lighting Items for IDA / 65950 Post Limited 89,894.00 0.00 Implement COVID-19 Response Quotations Envelope 20 15 22 quarantine and patient ation management centers LK-MOH-205648-GO-RFQ Pending / Procurement of Electrical Component 1: Emergency Request for Single Stage - One 2020-12- 2021-01- 2021-01- IDA / 65950 Post Limited 141,277.00 0.00 Implement Items for quarantine and COVID-19 Response Quotations Envelope 20 15 22 ation patient management centers LK-MOH-205649-GO-RFQ Pending / Procurement of Hardware Component 1: Emergency Request for Single Stage - One 2020-12- 2021-01- 2021-01- IDA / 65950 Post Limited 19,063.00 0.00 Implement Items for quarantine and COVID-19 Response Quotations Envelope 20 15 22 ation patient management centers LK-MOH-205651-GO-RFQ Pending / Procurement of Concrete Component 1: Emergency Request for Single Stage - One 2020-12- 2021-01- 2021-01- IDA / 65950 Post Limited 49,426.00 0.00 Implement Nails for quarantine and COVID-19 Response Quotations Envelope 20 15 22 ation patient management centers LK-MOH-205652-GO-RFQ Pending / Procurement of Steel items Component 1: Emergency Request for Single Stage - One 2020-12- 2021-01- 2021-01- IDA / 65950 Post Limited 142,635.00 0.00 Implement for quarantine and patient COVID-19 Response Quotations Envelope 20 15 22 ation management centers LK-MOH-205654-GO-RFQ Pending / Procurement of Aluminium Component 1: Emergency Request for Single Stage - One 2020-12- 2021-01- 2021-01- IDA / 65950 Post Limited 199,437.00 0.00 Implement Items for quarantine and COVID-19 Response Quotations Envelope 20 15 22 ation patient management centers LK-MOH-205656-GO-RFQ Pending / Procurement of P.V.C. Component 1: Emergency Request for Single Stage - One 2020-12- 2021-01- 2021-01- IDA / 65950 Post Limited 181,045.00 0.00 Implement Pipes for quarantine and COVID-19 Response Quotations Envelope 20 15 22 ation patient management centers LK-MOH-205657-GO-RFQ Pending / Procurement of Plumbing Component 1: Emergency Request for Single Stage - One 2020-12- 2021-01- 2021-01- IDA / 65950 Post Limited 44,065.00 0.00 Implement Items for quarantine and COVID-19 Response Quotations Envelope 20 15 22 ation patient management centers LK-MOH-205658-GO-RFQ Pending / Procurement of Water Component 1: Emergency Request for Single Stage - One 2020-12- 2021-01- 2021-01- IDA / 65950 Post Limited 32,066.00 0.00 Implement Tanks for quarantine and COVID-19 Response Quotations Envelope 20 15 22 ation patient management centers LK-MOH-205659-GO-RFQ Pending / Procurement of Mattress Component 1: Emergency Request for Single Stage - One 2020-12- 2021-01- 2021-01- IDA / 65950 Post Limited 107,099.00 0.00 Implement for quarantine and patient COVID-19 Response Quotations Envelope 20 15 22 ation management centers LK-MOH-205660-GO-RFQ Pending / Procurement of Sanitary Component 1: Emergency Request for Single Stage - One 2020-12- 2021-01- 2021-01- IDA / 65950 Post Limited 128,785.00 0.00 Implement Items for quarantine and COVID-19 Response Quotations Envelope 20 15 22 ation patient management centers LK-MOH-205663-GO-RFQ Pending / Procurement of Furniture Component 1: Emergency Request for Single Stage - One 2020-12- 2021-01- 2021-01- IDA / 65950 Post Limited 114,476.00 0.00 Implement for quarantine and patient COVID-19 Response Quotations Envelope 20 15 22 ation management centers LK-MOH-205666-GO-RFQ / Procurement of Glass and Pending Component 1: Emergency Request for Single Stage - One 2020-12- 2021-01- 2021-01- Porcelain Items for IDA / 65950 Post Limited 87,168.00 0.00 Implement COVID-19 Response Quotations Envelope 20 15 22 quarantine and patient ation management centers LK-MOH-205667-GO-RFQ Pending / Procurement of Cutlery Component 1: Emergency Request for Single Stage - One 2020-12- 2021-01- 2021-01- IDA / 65950 Post Limited 20,404.00 0.00 Implement Sets for quarantine and COVID-19 Response Quotations Envelope 20 15 22 ation patient management centers LK-MOH-205672-GO-RFQ Pending / Procurement of Bedding Component 1: Emergency Request for Single Stage - One 2020-12- 2021-01- 2021-01- IDA / 65950 Post Limited 172,571.00 0.00 Implement Items for quarantine and COVID-19 Response Quotations Envelope 20 15 22 ation patient management centers LK-MOH-205674-GO-RFQ Pending / Procurement of Mosquito Component 1: Emergency Request for Single Stage - One 2020-12- 2021-01- 2021-01- IDA / 65950 Post Limited 44,306.00 0.00 Implement Nets for quarantine and COVID-19 Response Quotations Envelope 20 15 22 ation patient management centers LK-MOH-205675-GO-RFQ / Procurement of Bed Iron Pending Component 1: Emergency Request for Single Stage - One 2020-12- 2021-01- 2021-01- Single (Frames with Bases) IDA / 65950 Post Limited 162,446.00 0.00 Implement COVID-19 Response Quotations Envelope 20 15 22 for quarantine and patient ation management centers LK-MOH-205676-GO-RFQ Pending / Procurement of Spray Component 1: Emergency Request for Single Stage - One 2020-12- 2021-01- 2021-01- IDA / 65950 Post Limited 69,958.00 0.00 Implement Machines for quarantine and COVID-19 Response Quotations Envelope 20 15 22 ation patient management centers LK-MOH-205677-GO-RFQ / Washing Machines, Rice Steamers, LED TV, Water Pending Boilers & Pumps, Coconut Component 1: Emergency Request for Single Stage - One 2020-12- 2021-01- 2021-01- IDA / 65950 Post Limited 159,854.00 0.00 Implement Scrappers, Weighing Scales COVID-19 Response Quotations Envelope 20 15 22 ation & other household Items) for quarantine and patient management centers LK-MOH-205678-GO-RFQ / Procurement of Pending Component 1: Emergency Request for Single Stage - One 2020-12- 2021-01- 2021-01- Communication items for IDA / 65950 Post Limited 44,240.00 0.00 Implement COVID-19 Response Quotations Envelope 20 15 22 quarantine and patient ation management centers LK-MOH-205679-GO-RFQ Pending / Procurement of Kitchen Component 1: Emergency Request for Single Stage - One 2020-12- 2021-01- 2021-01- IDA / 65950 Post Limited 71,706.00 0.00 Implement items for quarantine and COVID-19 Response Quotations Envelope 20 15 22 ation patient management centers LK-MOH-205680-GO-RFQ Pending / Procurement of Stationary Component 1: Emergency Request for Single Stage - One 2020-12- 2021-01- 2021-01- IDA / 65950 Post Limited 19,829.00 0.00 Implement Items for quarantine and COVID-19 Response Quotations Envelope 20 15 22 ation patient management centers LK-MOH-205681-GO-RFQ Pending / Procurement of Portable Component 1: Emergency Request for Single Stage - One 2020-12- 2021-01- 2021-01- IDA / 65950 Post Limited 40,000.00 0.00 Implement Washrooms for quarantine COVID-19 Response Quotations Envelope 20 15 22 ation and patient management centers LK-MOH-205682-GO-RFQ Pending / Procurement of Component 1: Emergency Request for Single Stage - One 2020-12- 2021-01- 2021-01- IDA / 65950 Post Limited 127,176.00 0.00 Implement Generators for quarantine COVID-19 Response Quotations Envelope 20 15 22 ation and patient management centers LK-MOH-205683-GO-RFQ / Procurement of Plastic Pending Tables, Chairs and other Component 1: Emergency Request for Single Stage - One 2020-12- 2021-01- 2021-01- IDA / 65950 Post Limited 97,513.00 0.00 Implement Items (Dust Bins, Buckets, COVID-19 Response Quotations Envelope 20 15 22 ation Cans, etc) for use of quarantine and patient management centers LK-MOH-205686-GO-RFQ / Procurement of Fire Pending Component 1: Emergency Request for Single Stage - One 2020-12- 2021-01- 2021-01- Extinguishers for quarantine IDA / 65950 Post Limited 7,833.00 0.00 Implement COVID-19 Response Quotations Envelope 20 15 22 and patient management ation centers LK-MOH-205690-GO-RFQ Pending / Supply of materials for Component 1: Emergency Request for Single Stage - One 2020-12- 2021-01- 2021-01- IDA / 65950 Post Limited 2,703.00 0.00 Implement covered way at Kahagolla COVID-19 Response Quotations Envelope 20 15 22 ation Intermediate Center LK-MOH-205694-GO-RFQ / IT and Office equipment required for strengthening Pending Component 1: Emergency Request for Single Stage - One 2020-12- 2021-01- 2021-02- COVI 19 related risk IDA / 65950 Post Limited 119,611.00 0.00 Implement COVID-19 Response Quotations Envelope 27 22 21 communication through ation HPB, District counter parts and hospitals (Annex 2) LK-MOH-205696-GO-RFQ / Furniture required for Pending strengthening COVI 19 Component 1: Emergency Request for Single Stage - One 2020-12- 2021-01- 2021-02- IDA / 65950 Post Limited 3,924.00 0.00 Implement related risk communication COVID-19 Response Quotations Envelope 27 22 21 ation through HPB, District counter parts and hospitals Annex 2 LK-MOH-205697-GO-RFQ / Stationery items required Pending for strengthening COVI 19 Component 1: Emergency Request for Single Stage - One 2020-12- 2021-01- 2021-02- IDA / 65950 Post Limited 1,870.00 0.00 Implement related risk communication COVID-19 Response Quotations Envelope 27 22 21 ation through HPB, District counter parts and hospitals Annex 2 LK-MOH-205733-GO-RFQ / Supply ,Installation and Pending Component 1: Emergency Request for Single Stage - One 2020-12- 2021-02- 2021-08- Commissioning of CCTV IDA / 65950 Post Limited 11,273.00 0.00 Implement COVID-19 Response Quotations Envelope 14 08 07 system for patient ation surveillance in NIID LK-MOH-203403-GO-RFQ Pending / 08 Items of Kitchen Component 1: Emergency Request for Single Stage - One 2020-11- 2020-12- 2021-01- TF / B3017 Post Limited 7,622.00 0.00 Implement Equipment for Mental Heath COVID-19 Response Quotations Envelope 24 29 28 ation directorate (Grant) LK-MOH-203392-GO-RFQ / 05 Nos Guitars, 05 Nos Keyboards, 20 Nos Pending Component 1: Emergency Request for Single Stage - One 2020-11- 2020-12- 2021-01- Tambourine, 20Nos Congo TF / B3017 Post Limited 2,108.00 0.00 Implement COVID-19 Response Quotations Envelope 24 29 28 and 20Nos Maraca Pairs for ation Directorate of Mental Health .(Grant) LK-MOH-203389-GO-RFQ Pending / 06 Type of Sports items Component 1: Emergency Request for Single Stage - One 2020-11- 2020-12- 2021-01- TF / B3017 Post Limited 6,535.00 0.00 Implement for Directorate of Mental COVID-19 Response Quotations Envelope 24 29 28 ation Health (Grant) LK-MOH-205501-GO-UN / Supply of Bio Medical Equipment, 14 Nos Automated RNA Extractors, Pending Component 1: Emergency UN Agencies 2020-12- 2021-01- 2021-02- 2021-08- Equipment for 5 Molecular IDA / 65950 Prior Direct 6,613,385.00 0.00 Implement COVID-19 Response (Direct) 28 02 06 05 Laboratories and Installation ation of Laboratory Information Management System (LIMS) through UNOP procurement LK-MOH-207175-GO-RFQ / Supply and Installation of Pending Component 1: Emergency Request for Single Stage - One 2020-12- 2021-01- 2021-03- central air-conditioner IDA / 65950 Post Limited 48,649.00 0.00 Implement COVID-19 Response Quotations Envelope 19 30 01 system with Hepa filters for ation COVID ICU and HDU at BH Marawila LK-MOH-207182-GO-RFQ Pending Component 1: Emergency Request for Single Stage - One 2020-12- 2021-01- 2021-03- / Supplying medical gas and IDA / 65950 Post Limited 16,217.00 0.00 Implement COVID-19 Response Quotations Envelope 19 30 01 fire extinguishes for ation Marawila BH LK-MOH-207185-GO-RFQ Pending Component 1: Emergency Request for Single Stage - One 2020-12- 2021-01- 2021-03- / Supply and Installation of IDA / 65950 Post Limited 21,622.00 0.00 Implement COVID-19 Response Quotations Envelope 19 30 01 Generator set for Marawila ation BH Page 18 LK-MOH-207211-GO-RFQ / 50 Nos Hand held public Pending Component 1: Emergency Request for Single Stage - One 2020-12- 2021-02- 2021-02- address systems for risk IDA / 65950 Post Limited 13,514.00 0.00 Implement COVID-19 Response Quotations Envelope 26 07 21 communication at estate ation and urban areas Pending LK-MOH-207213-GO-RFQ Component 1: Emergency Request for Single Stage - One 2020-12- 2021-02- 2021-02- IDA / 65950 Post Limited 70,270.00 0.00 Implement / 65 Nos Suction apparatus COVID-19 Response Quotations Envelope 27 08 22 ation LK-MOH-207585-GO-RFQ / Purchasing Two mobile toilets, one fiber glass Pending mobile shower unit and 10 Component 1: Emergency Request for Single Stage - One 2020-12- 2021-02- 2021-02- IDA / 65950 Post Limited 2,162.00 0.00 Implement paddle sink ,3 shower COVID-19 Response Quotations Envelope 27 08 22 ation heater with pressure pump for Warallawatta Yakkakala intermediate Covid Center LK-MOH-207586-GO-RFQ / 336 Nos Stand fan , 119 Nos Double door Pending Component 1: Emergency Request for Single Stage - One 2020-12- 2021-02- 2021-02- refrigerator, 136 Nos IDA / 65950 Post Limited 183,784.00 0.00 Implement COVID-19 Response Quotations Envelope 27 08 22 Washing ation machine 10 kg , 247 Nos Electric kettles and 159 Nos Television 42" LK-MOH-207594-GO-RFQ / Procurement of telephone Pending and network cables and Component 1: Emergency Request for Single Stage - One 2020-12- 2021-02- 2021-02- TF / B3017 Post Limited 4,322.00 0.00 Implement accessories for COVID-19 Response Quotations Envelope 27 08 22 ation improvement and extension of 1926 Help Line LK-MOH-207596-GO-RFQ / Conference Table 01, Pending Component 1: Emergency Request for Single Stage - One 2020-12- 2021-02- 2021-02- Metal Chairs 04, Office TF / B3017 Post Limited 541.00 0.00 Implement COVID-19 Response Quotations Envelope 27 08 22 cupboard 01, Filing Rack ation 01, Book Shelf  01 LK-MOH-207613-GO-RFQ / Supply , installation and Pending Component 1: Emergency Request for Single Stage - One 2020-12- 2021-02- 2021-03- commissioning 01 Unit of IDA / 65950 Post Limited 135,135.00 0.00 Implement COVID-19 Response Quotations Envelope 27 21 23 500 KVA Diesel Generator ation for Base Hospital Marawila LK-MOH-207656-GO-RFQ / Procurement of License Pending package of  Adobe Creative Component 1: Emergency Request for Single Stage - One 2020-12- 2021-02- 2021-08- TF / B3017 Post Limited 1,622.00 0.00 Implement Suite for 03 computers for COVID-19 Response Quotations Envelope 27 21 20 ation two years for Health Promotion Bureau. LK-MOH-208776-GO-DIR Pending Component 1: Emergency 2020-12- 2020-12- 2021-01- 2021-01- / 100,000 Nos of KN 95 IDA / 65950 Post Direct Selection Direct 51,892.00 0.00 Implement COVID-19 Response 15 20 10 25 Face Masks ation LK-MOH-208778-GO-RFQ Pending Component 1: Emergency Request for Single Stage - One 2020-12- 2021-02- 2021-02- / 400,000 Nos KN 95 Face IDA / 65950 Post Limited 189,190.00 0.00 Implement COVID-19 Response Quotations Envelope 20 07 22 Masks ation LK-MOH-210720-GO-RFQ / Supply of material for Pending Component 1: Emergency Request for Single Stage - One 2021-01- 2021-03- 2021-09- Essential modification to IDA / 65950 Post Limited 6,486.00 0.00 Implement COVID-19 Response Quotations Envelope 11 08 04 establish Covid-19 ward at ation Nilwala education center LK-MOH-210723-GO-RFQ Pending Component 1: Emergency Request for Single Stage - One 2021-01- 2021-03- 2021-03- / 05 Nos Laptops for MoH IDA / 65950 Post Limited 10,801.00 0.00 Implement COVID-19 Response Quotations Envelope 19 10 25 Procurement division ation LK-MOH-210725-GO-RFQ Pending / 01 No Smart Interactive Component 1: Emergency Request for Single Stage - One 2021-01- 2021-03- 2021-03- IDA / 65950 Post Limited 5,405.00 0.00 Implement Digital Display including COVID-19 Response Quotations Envelope 19 10 25 ation Web Camera with TV Mount LK-MOH-210727-GO-RFQ Pending Component 1: Emergency Request for Single Stage - One 2021-01- 2021-03- 2021-03- / Supply and Installation of IDA / 65950 Post Limited 2,703.00 0.00 Implement COVID-19 Response Quotations Envelope 19 10 25 Wireless Conference System ation LK-MOH-203388-GO-RFQ / 72 items of Occupational Pending Therapy Instrument (List Component 1: Emergency Request for Single Stage - One 2020-11- 2020-12- 2021-01- TF / B3017 Post Limited 10,280.00 0.00 Implement attached) for Mental health COVID-19 Response Quotations Envelope 17 22 21 ation District General Hospital ,Monaragala. (Grant) LK-MOH-203385-GO-RFQ / 31 Items of Occupational Pending Therapy Instruments for Component 1: Emergency Request for Single Stage - One 2020-11- 2020-12- 2021-01- TF / B3017 Post Limited 8,108.00 0.00 Implement Mental Health - General COVID-19 Response Quotations Envelope 17 22 21 ation Hospital Katugasthota. (Grant). LK-MOH-212321-GO-RFQ / 06 Unit of Electro Convulsive Therapy Pending Component 1: Emergency Request for Single Stage - One 2021-01- 2021-03- 2021-03- machines (ECT) required for TF / B3017 Post Limited 162,162.00 0.00 Implement COVID-19 Response Quotations Envelope 17 07 22 06 Hospitals (GH Vavuniya, ation TH Anuradhapura, TH Kandy, TH Peradeniya, DGH Kegalle, GH Nuwara Eliya) LK-MOH-212322-GO-DIR Pending / 02 Nos of Freezer plants Component 1: Emergency 2021-01- 2021-01- 2021-02- 2021-02- TF / B3017 Post Direct Selection Direct 108,108.00 0.00 Implement for the Central Vaccine store COVID-19 Response 11 16 13 28 ation at the Epidemiology Unit. LK-MOH-212431-GO-RFQ / 08 Nos Executive Tables, 18 Nos 2 Seater Work Pending Stations, 20 Nos Stainless Component 1: Emergency Request for Single Stage - One 2021-01- 2021-02- 2021-02- TF / B3017 Post Limited 5,405.00 0.00 Implement Steel Dining Chairs and 02 COVID-19 Response Quotations Envelope 17 14 21 ation Nos Dining Tables required for Epidemiology Unit to strength Covid-19 Surveillance LK-MOH-212432-GO-RFQ / Supply and Installation of 07 Nos 12000 BTU Air Pending Conditioner Unit and 01 No Component 1: Emergency Request for Single Stage - One 2021-01- 2021-02- 2021-02- TF / B3017 Post Limited 4,500.00 0.00 Implement 24,000 BTU Air Conditioner COVID-19 Response Quotations Envelope 17 14 21 ation Unit for Epidemiology Unit to strength Covid-19 Surveillance. LK-MOH-212433-GO-RFQ / Supply and delivery of 14 Pending Items of Office Furniture for Component 1: Emergency Request for Single Stage - One 2021-01- 2021-02- 2021-02- TF / B3017 Post Limited 10,811.00 0.00 Implement Newly Build Infection COVID-19 Response Quotations Envelope 16 13 20 ation Prevention and Control Unit (NIMH) LK-MOH-215133-GO-RFQ / CCTV Survaillence and Pending Component 1: Emergency Request for Single Stage - One 2021-01- 2021-03- 2021-09- Audio Visual TF / B3017 Post Limited 10,810.00 0.00 Implement COVID-19 Response Quotations Envelope 29 26 22 Communication System for ation Mental Health Unit at NIMH LK-MOH-215136-GO-RFQ / Vidio Coference Pending Component 1: Emergency Request for Single Stage - One 2021-01- 2021-03- 2021-09- Equipment and Accessaris TF / B3017 Post Limited 10,810.00 0.00 Implement COVID-19 Response Quotations Envelope 30 27 23 for newly build Infection and ation Control Unit at NIMH LK-MOH-215715-GO-RFQ / Harware items for the Pending Component 1: Emergency Request for Single Stage - One 2021-02- 2021-04- 2021-09- Renovation works of IDA / 65950 Post Limited 24,324.00 0.00 Implement COVID-19 Response Quotations Envelope 05 02 29 hospital building ation Norechcholai Covid Treatment Center LK-MOH-215714-GO-RFQ Pending / Electrical items required Component 1: Emergency Request for Single Stage - One 2021-02- 2021-04- 2021-09- IDA / 65950 Post Limited 8,108.00 0.00 Implement for the renovation work at COVID-19 Response Quotations Envelope 05 02 29 ation Norichcholai Treatment Center LK-MOH-215719-GO-RFQ / Supply, Installation and commissioning of Pending Component 1: Emergency Request for Single Stage - One 2021-02- 2021-04- 2021-09- Telecommunication and IDA / 65950 Post Limited 8,108.00 0.00 Implement COVID-19 Response Quotations Envelope 05 02 29 Video Survailiance facilities ation at Udagama, Atabage Covid treatment Center LK-MOH-215723-GO-RFQ / Hardware items required Pending Component 1: Emergency Request for Single Stage - One 2021-02- 2021-03- 2021-03- for construction of IDA / 65950 Post Limited 48,650.00 0.00 Implement COVID-19 Response Quotations Envelope 05 03 10 temporary wards for Covid ation treatment at Colombo East Base Hospital LK-MOH-215728-GO-RFQ / Procurement of Aluminium fittings and Accessaries Pending Component 1: Emergency Request for Single Stage - One 2021-02- 2021-03- 2021-03- required for construction of IDA / 65950 Post Limited 27,030.00 0.00 Implement COVID-19 Response Quotations Envelope 05 03 10 temporary wards for Covid ation treatment at Colombo East Base Hospital LK-MOH-215732-GO-RFQ / Procurement of Yard Items Pending required for construction of Component 1: Emergency Request for Single Stage - One 2021-02- 2021-03- 2021-03- IDA / 65950 Post Limited 32,432.00 0.00 Implement temporary wards for Covid COVID-19 Response Quotations Envelope 05 03 10 ation treatment at Colombo East Base Hospital LK-MOH-215737-GO-RFQ / Procurement of PVC and Pending Wiring Accessaries required Component 1: Emergency Request for Single Stage - One 2021-02- 2021-03- 2021-03- IDA / 65950 Post Limited 27,030.00 0.00 Implement for construction of COVID-19 Response Quotations Envelope 05 03 10 ation temporary wards for Covid treatment at Colombo East Base Hospital LK-MOH-215766-GO-RFB / Supply ,Installation and commissioning of 03 Nos Pending Component 1: Emergency Single Stage - One 2021-02- 2021-02- 2021-03- 2021-04- 2021-05- 2021-11- walk in cold storage IDA / 65950 Post Request for Bids Open - National 32,450.00 0.00 Implement COVID-19 Response Envelope 08 13 27 26 31 27 facilities at centarl ation vaccination store , Badulla RMSD & , Rathnapura RMSD LK-MOH-219224-GO-RFB Under Component 1: Emergency Open - Single Stage - One 2021-02- 2021-02- 2021-02- 2021-04- 2021-03- 2021-04- 2021-06- 2021-12- / 60 Nos Unused IDA / 65950 Post Request for Bids 4,736,842.00 0.00 Implement COVID-19 Response International Envelope 12 12 17 05 31 30 04 01 Ambulances ation LK-MOH-201484-GO-RFB Component 1: Emergency Open - Single Stage - One 2020-12- 2020-12- 2021-02- 2021-03- 2021-04- 2021-10- IDA / 65950 Prior Request for Bids 3,846,154.00 0.00 Canceled / 60 Units of Ambulances COVID-19 Response International Envelope 22 27 07 09 13 10 LK-MOH-212440-GO-RFQ / Supply and delivery of essential Building Materials Pending to convert Ward 01 to a Component 1: Emergency Request for Single Stage - One 2021-01- 2021-03- 2021-05- IDA / 65950 Post Limited 54,054.00 0.00 Implement Step Down Covid Treatment COVID-19 Response Quotations Envelope 25 15 14 ation Center and modification to high dependency unit of TH Rathnapura. LK-MOH-224018-GO-RFQ Pending Component 1: Emergency Request for Single Stage - One 2021-04- 2021-05- 2021-11- / IT equipment for covid IDA / 65950 Post Limited 4,250.00 0.00 Implement COVID-19 Response Quotations Envelope 04 30 26 PCR lab at NIHS ation LK-MOH-224030-GO-RFQ Pending Component 1: Emergency Request for Single Stage - One 2021-04- 2021-05- 2021-11- / Furniture for covid PCR IDA / 65950 Post Limited 6,350.00 0.00 Implement COVID-19 Response Quotations Envelope 04 30 26 lab at NIHS ation LK-MOH-224033-GO-RFQ / Supply & Installation of AC Pending Component 1: Emergency Request for Single Stage - One 2021-04- 2021-05- 2021-11- system for the new ICU IDA / 65950 Post Limited 42,150.00 0.00 Implement COVID-19 Response Quotations Envelope 05 31 27 being built near ward 17 (LK- ation MOH-207206-CW-RFQ) LK-MOH-224034-GO-RFQ / supply , installation and Pending Component 1: Emergency Request for Single Stage - One 2021-04- 2021-05- 2021-11- commissioning of RO plant IDA / 65950 Post Limited 19,000.00 0.00 Implement COVID-19 Response Quotations Envelope 05 31 27 in the dialisys unit at ation Minuwangoda Base Hospital LK-MOH-224037-GO-RFQ / supply and installation of Pending Component 1: Emergency Request for Single Stage - One 2021-04- 2021-05- 2021-11- hospital furniture, bedding IDA / 65950 Post Limited 68,500.00 0.00 Implement COVID-19 Response Quotations Envelope 05 31 27 itemsand non medical ation equipment to ICU LK-MOH-224045-GO-RFQ Pending Component 1: Emergency Request for Single Stage - One 2021-04- 2021-06- 2021-12- / Medical equipment for 10 IDA / 65950 Post Limited 52,650.00 0.00 Implement COVID-19 Response Quotations Envelope 13 08 05 bedded ICU ation LK-MOH-224242-GO-RFQ / Supply installation and Pending Component 1: Emergency Request for Single Stage - One 2021-04- 2021-06- 2021-12- commissioning of essential IDA / 65950 Post Limited 26,400.00 0.00 Implement COVID-19 Response Quotations Envelope 14 09 06 medical equipment for 3 ation beded HDU LK-MOH-224245-GO-RFQ Pending / supply , installation and Component 1: Emergency Request for Single Stage - One 2021-04- 2021-06- 2021-12- IDA / 65950 Post Limited 18,500.00 0.00 Implement commissioning of mortuary COVID-19 Response Quotations Envelope 13 08 05 ation cooler with 4 chambers LK-MOH-224247-GO-RFQ / Extention of Central AC Pending Component 1: Emergency Request for Single Stage - One 2021-04- 2021-06- 2021-12- system to vnewly built IDA / 65950 Post Limited 37,000.00 0.00 Implement COVID-19 Response Quotations Envelope 14 09 06 medical intensive care unit ation located in different floor LK-MOH-224249-GO-RFQ / supply installation and commissing of washer Pending extractor , dryer tumbler Component 1: Emergency Request for Single Stage - One 2021-04- 2021-06- 2021-12- IDA / 65950 Post Limited 168,500.00 0.00 Implement and disinfection machine. COVID-19 Response Quotations Envelope 25 20 17 ation And double door high pressure sterilizer in level 3 covid treatment center Pending LK-MOH-224250-GO-DIR Component 1: Emergency 2021-03- 2021-04- 2021-05- 2021-11- IDA / 65950 Post Direct Selection Direct 2,560.00 0.00 Implement / Supply of Dosimeter COVID-19 Response 29 03 08 04 ation LK-MOH-224252-GO-RFQ / Supply ,Installation and Pending Component 1: Emergency Request for Single Stage - One 2021-04- 2021-06- 2021-12- commissioning of Liquied IDA / 65950 Post Limited 23,700.00 0.00 Implement COVID-19 Response Quotations Envelope 24 19 16 Oxygen plant at TH ation Theldeniya LK-MOH-207216-GO-RFQ / Supply of consumables , lab equipment and lab test facilities-Vitamin D deficiency in adults: Component 1: Emergency Request for Single Stage - One 2020-12- 2021-02- 2021-02- IDA / 65950 Post Limited 32,432.00 0.00 Canceled Prevalence, risk factors and COVID-19 Response Quotations Envelope 26 07 21 its association with COVID- 19 among residents in the district of Colombo- annex 3 budget and annex 4 proposal LK-MOH-224676-GO-RFQ / Supply, Installation and commissioning of Air Pending Component 1: Emergency Request for Single Stage - One 2021-04- 2021-06- 2021-12- Conditioning Plants (18000 IDA / 65950 Post Limited 8,000.00 0.00 Implement COVID-19 Response Quotations Envelope 12 07 04 BTU -03 Nos & 12000 BTU - ation 07 Nos) for Health Promotion Bureau. LK-MOH-227595-GO-DIR Pending / Suplly Installation and Component 1: Emergency 2021-04- 2021-05- 2021-06- 2021-12- IDA / 65950 Post Direct Selection Direct 6,500.00 0.00 Implement Commissioning of medical COVID-19 Response 26 01 05 02 ation gas / oxygen to HDU LK-MOH-227607-GO-RFQ / Purchase of material required for partioning the Pending Component 1: Emergency Request for Single Stage - One 2021-05- 2021-06- 2021-12- cuibicale to be convereted IDA / 65950 Post Limited 15,800.00 0.00 Implement COVID-19 Response Quotations Envelope 01 26 23 in to a safe 6 bedded HDU ation with direct monitoring , anteroom and doffing room LK-MOH-231325-GO-RFQ / Supply, installation, Testing and commissioning Pending Component 1: Emergency Request for Single Stage - One 2021-05- 2021-07- 2022-01- of piped medical gas IDA / 65950 Post Limited 8,300.00 0.00 Implement COVID-19 Response Quotations Envelope 10 05 01 distribution system to the ation ward no 6A, 7A and 7B of National Infectious Disease Hospital LK-MOH-199415-GO-RFQ / Supply and Installation of Tables and Adjustable Component 1: Emergency Request for Single Stage - One 2020-10- 2020-11- 2020-11- TF / B3017 Post Limited 4,211.00 0.00 Canceled chairs for Audio Visual COVID-19 Response Quotations Envelope 26 16 23 Recording Studio at Health Promotion Bureau. LK-MOH-231681-GO-RFB Pending / Procurement of Viral Component 1: Emergency 2021-05- 2021-05- 2021-06- 2021-12- IDA / 65950 Post Direct Selection Direct 276,000.00 0.00 Implement Transport Media and SWABS COVID-19 Response 05 10 14 11 ation - 300,000 Nos LK-MOH-232303-GO-RFQ Pending / 8,000 Nos Pillows, 16,000 Component 1: Emergency Request for Single Stage - One 2021-05- 2021-06- 2021-06- IDA / 65950 Post Limited 181,000.00 0.00 Implement Pillow Cases - White and COVID-19 Response Quotations Envelope 11 06 13 ation 16,000 Bed Sheets - White Pending LK-MOH-232305-GO-RFQ Component 1: Emergency Request for Single Stage - One 2021-05- 2021-06- 2021-06- IDA / 65950 Post Limited 180,000.00 0.00 Implement / 8,000 Nos Mattresses COVID-19 Response Quotations Envelope 11 06 13 ation LK-MOH-232307-GO-RFQ Pending Component 1: Emergency Request for Single Stage - One 2021-05- 2021-06- 2021-06- / 8,000 Nos Mosquito Nets IDA / 65950 Post Limited 27,350.00 0.00 Implement COVID-19 Response Quotations Envelope 11 06 13 (Single) ation Page 19 Pending LK-MOH-232309-GO-RFQ Component 1: Emergency Request for Single Stage - One 2021-05- 2021-06- 2021-06- IDA / 65950 Post Limited 130,000.00 0.00 Implement / 8,000 Nos Plywood Sheets COVID-19 Response Quotations Envelope 11 06 13 ation LK-MOH-233638-GO-RFQ / Extention of piped Medical Pending Gas distribution system to Component 1: Emergency Request for Single Stage - One 2021-05- 2021-07- 2022-01- IDA / 65950 Post Limited 21,000.00 0.00 Implement Ward 7, 8, and 9 of COVID-19 Response Quotations Envelope 25 20 16 ation Colombo nEast Base Hospital, Mulleriyawa LK-MOH-233616-GO-RFQ / 1,000Units of Automated Digital Blood Presure Pending Measurement Device and Component 1: Emergency Request for Single Stage - One 2021-06- 2021-07- 2022-01- IDA / 65950 Post Limited 40,000.00 0.00 Implement 200 Units of Glucometers COVID-19 Response Quotations Envelope 01 27 23 ation with 200,000 Test Strips to improve self-testing facilities at Hospitals LK-MOH-234317-GO-DIR Pending / 27,000 Roach Magna pure Component 1: Emergency 2021-05- 2021-05- 2021-06- 2021-12- IDA / 65950 Post Direct Selection Direct 254,000.00 0.00 Implement 96 system automated COVID-19 Response 20 25 29 26 ation extraction kits with consumabels LK-MOH-234316-GO-DIR / 58500 numbers of Pending Component 1: Emergency 2021-05- 2021-05- 2021-07- 2022-01- Pentabase magnetic bead IDA / 65950 Post Direct Selection Direct 1,500,000.00 0.00 Implement COVID-19 Response 26 31 05 01 RNA extraction kit for ation basepurified with consumabales LK-MOH-234319-GO-DIR / 121500 numbers of Pending Component 1: Emergency 2021-05- 2021-05- 2021-07- 2022-01- Nucleic acid extraction kits IDA / 65950 Post Direct Selection Direct 840,000.00 0.00 Implement COVID-19 Response 26 31 05 01 for Maxwell RSC Automated ation with consumables LK-MOH-234321-GO-DIR / 54000 number of Pending Component 1: Emergency 2021-05- 2021-05- 2021-07- 2022-01- QIASymphony extraction IDA / 65950 Post Direct Selection Direct 600,000.00 0.00 Implement COVID-19 Response 26 31 05 01 mini kits QIASymphony SP ation with consumables LK-MOH-234330-GO-RFQ / 135000 numbers of Pending Component 1: Emergency Request for Single Stage - One 2021-05- 2021-07- 2022-01- Eppendorf Automated IDA / 65950 Post Limited 700,000.00 0.00 Implement COVID-19 Response Quotations Envelope 31 26 22 extraction kits for ation ependrofautomated machine with consumabels LK-MOH-234343-GO-RFB Pending / 300000 numbers of SARS Component 1: Emergency Open - Single Stage - One 2021-05- 2021-05- 2021-07- 2021-08- 2021-09- 2022-03- IDA / 65950 Post Request for Bids 1,800,000.00 0.00 Implement Cov-2 rapid Ag assay (ICT COVID-19 Response International Envelope 26 31 12 11 15 14 ation /Lateral flow method) LK-MOH-234344-GO-RFB Pending Component 1: Emergency Open - Single Stage - One 2021-05- 2021-05- 2021-07- 2021-08- 2021-09- 2022-03- / 750000 numbers of IDA / 65950 Prior Request for Bids 7,700,000.00 0.00 Implement COVID-19 Response International Envelope 26 31 12 11 15 14 COVID -19 PCR test kit ation LK-MOH-234348-GO-RFQ Pending Component 1: Emergency Request for Single Stage - One 2021-05- 2021-07- 2022-01- / 1000 Nos of Jumbo IDA / 65950 Post Limited 198,000.00 0.00 Implement COVID-19 Response Quotations Envelope 31 26 22 Cylinders empty for Oxygen ation (6800Lts) Pending LK-MOH-234349-GO-RFQ Component 1: Emergency Request for Single Stage - One 2021-05- 2021-07- 2022-01- IDA / 65950 Post Limited 154,000.00 0.00 Implement / 15,000 nos of PPE Kits COVID-19 Response Quotations Envelope 29 24 20 ation LK-MOH-234352-GO-RFQ Pending Component 1: Emergency Request for Single Stage - One 2021-05- 2021-07- 2022-01- / 50,000 nos of Goggles for IDA / 65950 Post Limited 178,000.00 0.00 Implement COVID-19 Response Quotations Envelope 29 24 20 health staff ation LK-MOH-234353-GO-RFQ Pending / 3,000,000 nos of Surgical Component 1: Emergency Request for Single Stage - One 2021-05- 2021-07- 2022-01- IDA / 65950 Post Limited 174,000.00 0.00 Implement Face Mask ( non streile ear COVID-19 Response Quotations Envelope 29 24 20 ation loop type) LK-MOH-234356-GO-RFQ Pending Component 1: Emergency Request for Single Stage - One 2021-05- 2021-07- 2022-01- / 50,000 nos of Face Sheild IDA / 65950 Post Limited 50,000.00 0.00 Implement COVID-19 Response Quotations Envelope 29 24 20 for health staff ation LK-MOH-234357-GO-RFQ Pending Component 1: Emergency Request for Single Stage - One 2021-05- 2021-07- 2022-01- / 16,000,000 nos of IDA / 65950 Post Limited 173,000.00 0.00 Implement COVID-19 Response Quotations Envelope 29 24 20 Surgical Hair Cap ation LK-MOH-234358-GO-RFQ Pending Component 1: Emergency Request for Single Stage - One 2021-05- 2021-07- 2022-01- / 75000 nos of Isolation IDA / 65950 Post Limited 170,000.00 0.00 Implement COVID-19 Response Quotations Envelope 29 24 20 Gown ation LK-MOH-234360-GO-RFQ Pending Component 1: Emergency Request for Single Stage - One 2021-05- 2021-07- 2022-01- / 100,000 nos of Particular IDA / 65950 Post Limited 176,000.00 0.00 Implement COVID-19 Response Quotations Envelope 29 24 20 Respirator ation LK-MOH-234362-GO-RFQ Pending / 3,000,000 nos of Surgical Component 1: Emergency Request for Single Stage - One 2021-05- 2021-07- 2022-01- IDA / 65950 Post Limited 150,000.00 0.00 Implement Face Mask , Tie , on type , 3 COVID-19 Response Quotations Envelope 29 24 20 ation ply LK-MOH-234363-GO-RFQ Pending Component 1: Emergency Request for Single Stage - One 2021-05- 2021-07- 2022-01- / 70,000 nos of Protective IDA / 65950 Post Limited 163,000.00 0.00 Implement COVID-19 Response Quotations Envelope 29 24 20 Coverall ation LK-MOH-234364-GO-RFQ Pending Component 1: Emergency Request for Single Stage - One 2021-05- 2021-07- 2022-01- / 150,000 nos of Boot IDA / 65950 Post Limited 103,000.00 0.00 Implement COVID-19 Response Quotations Envelope 29 24 20 covers ation Pending LK-MOH-234366-GO-RFQ Component 1: Emergency Request for Single Stage - One 2021-05- 2021-07- 2022-01- IDA / 65950 Post Limited 108,000.00 0.00 Implement / 5000 Nos of Body Bags COVID-19 Response Quotations Envelope 29 24 20 ation LK-MOH-234827-GO-RFQ Pending Component 1: Emergency Request for Single Stage - One 2021-06- 2021-07- 2022-01- / 6,000,000.00 Nos of IDA / 65950 Post Limited 104,000.00 0.00 Implement COVID-19 Response Quotations Envelope 05 31 27 Surgical Hair Caps ation LK-MOH-234830-GO-RFB Pending Component 1: Emergency Single Stage - One 2021-05- 2021-06- 2021-07- 2021-08- 2021-09- 2022-03- / 375,000 Nos of Isolation IDA / 65950 Post Request for Bids Open - National 840,000.00 0.00 Implement COVID-19 Response Envelope 31 05 17 16 20 19 Gowns ation LK-MOH-234833-GO-RFB Pending Component 1: Emergency Single Stage - One 2021-05- 2021-06- 2021-07- 2021-08- 2021-09- 2022-03- / 100,000 Nos of Particular IDA / 65950 Post Request for Bids Open - National 616,000.00 0.00 Implement COVID-19 Response Envelope 31 05 17 16 20 19 Respirators (KN 95) ation LK-MOH-234835-GO-RFB Pending Component 1: Emergency Single Stage - One 2021-05- 2021-06- 2021-07- 2021-08- 2021-09- 2022-03- / 19,000,000 Nos of IDA / 65950 Post Request for Bids Open - National 926,000.00 0.00 Implement COVID-19 Response Envelope 31 05 17 16 20 19 Surgical Face Masks, Tie on ation type 3 ply LK-MOH-234836-GO-RFB Pending Component 1: Emergency Single Stage - One 2021-05- 2021-06- 2021-07- 2021-08- 2021-09- 2022-03- / 200,000 Nos of Protective IDA / 65950 Post Request for Bids Open - National 464,000.00 0.00 Implement COVID-19 Response Envelope 31 05 17 16 20 19 Coveralls ation LK-MOH-234838-GO-RFB Pending Component 1: Emergency Single Stage - One 2021-05- 2021-06- 2021-07- 2021-08- 2021-09- 2022-03- / 5,000 Nos of Jumbo IDA / 65950 Post Request for Bids Open - National 987,000.00 0.00 Implement COVID-19 Response Envelope 31 05 17 16 20 19 Cylinder 6,800 Ltrs New ation (Empty) for O2 LK-MOH-234839-GO-RFQ Pending Component 1: Emergency Request for Single Stage - One 2021-06- 2021-07- 2022-01- / 2,700,000 Nos of Micro IDA / 65950 Post Limited 60,000.00 0.00 Implement COVID-19 Response Quotations Envelope 05 31 27 Centrifuge Tubes 1.5ml ation LK-MOH-234843-GO-RFQ Pending Component 1: Emergency Request for Single Stage - One 2021-06- 2021-07- 2022-01- / 1,350 Nos of PCR Tubes IDA / 65950 Post Limited 64,000.00 0.00 Implement COVID-19 Response Quotations Envelope 05 31 27 Optical grade 0.2ml ation LK-MOH-234844-GO-RFQ Pending Component 1: Emergency Request for Single Stage - One 2021-06- 2021-07- 2022-01- / 900,000 Nos of 20 MIC 1 IDA / 65950 Post Limited 48,000.00 0.00 Implement COVID-19 Response Quotations Envelope 05 31 27 Filter Tips for PCR testing ation LK-MOH-234845-GO-RFQ Pending Component 1: Emergency Request for Single Stage - One 2021-06- 2021-07- 2022-01- / 900,000 Nos of 10 MIC 1 IDA / 65950 Post Limited 48,000.00 0.00 Implement COVID-19 Response Quotations Envelope 05 31 27 Filter Tips ation LK-MOH-234946-GO-RFQ / Procurement of 5 nos Wheel chair ,4 Nos Patient Trolley- Stainless steel , 4 Pending NosPatient Trolley- Powder Component 1: Emergency Request for Single Stage - One 2021-06- 2021-07- 2022-01- IDA / 65950 Post Limited 19,000.00 0.00 Implement coated , 10 Nos Saline COVID-19 Response Quotations Envelope 05 31 27 ation Stand , 4 Nos Drugs Trolley & 160 Nos Bed Side Lockers to special Covid Treatment Center @ CEBH Mulleriyawa LK-MOH-235147-GO-DIR Pending / 14 Varieties of Reagents Component 1: Emergency 2021-05- 2021-06- 2021-07- 2022-01- IDA / 65950 Post Direct Selection Direct 240,000.00 0.00 Implement required for Genetic COVID-19 Response 31 05 10 06 ation sequencing. LK-MOH-235149-GO-DIR Pending Component 1: Emergency 2021-05- 2021-06- 2021-07- 2022-01- / 04 Nos of Qiagen RNA IDA / 65950 Post Direct Selection Direct 5,130.00 0.00 Implement COVID-19 Response 31 05 10 06 extraction kits250 reactions ation LK-MOH-235150-GO-DIR / Taqpath PCR kits (1000 reactions) 1, MicroAmp™ Pending Optical 96-Well Reaction Component 1: Emergency 2021-05- 2021-06- 2021-07- 2022-01- IDA / 65950 Post Direct Selection Direct 21,300.00 0.00 Implement Plate,10 plates/pack 10, COVID-19 Response 31 05 10 06 ation MicroAmp™ Optical Adhesive Film, 25 Covers/pack 10, ELISA sealers (100/pack) 2 LK-MOH-236932-GO-RFQ Pending / 02 Nos of Rice Steamer Component 1: Emergency Request for Single Stage - One 2021-06- 2021-08- 2022-02- IDA / 65950 Post Limited 7,900.00 0.00 Implement 50Kg and 50 Nos of Water COVID-19 Response Quotations Envelope 21 16 12 ation Boiler 20Ltr Automatic LK-MOH-236934-GO-RFQ / 250 Nos of Bed Side Lockers, 150 Nos of Over Pending Component 1: Emergency Request for Single Stage - One 2021-06- 2021-08- 2022-02- Head Table ,25 Nos of IDA / 65950 Post Limited 35,800.00 0.00 Implement COVID-19 Response Quotations Envelope 20 15 11 Mdf Table 4*3, 25 Nos of ation MDF Almairah 6*3, 10 Nos of Portable Sound Systems LK-MOH-236936-GO-RFQ Pending / 40 Nos of Oxygen Stand Component 1: Emergency Request for Single Stage - One 2021-06- 2021-08- 2022-02- IDA / 65950 Post Limited 13,700.00 0.00 Implement Jumbo and 50 Nos of COVID-19 Response Quotations Envelope 20 15 11 ation Oxygen Stand Normal LK-MOH-236937-GO-RFQ / 15,000 Nos of Bed sheet Pending Component 1: Emergency Request for Single Stage - One 2021-06- 2021-08- 2022-02- 6*4, 3,000 Nos of Pillow IDA / 65950 Post Limited 57,700.00 0.00 Implement COVID-19 Response Quotations Envelope 20 15 11 cases and 100 Nos of ation Double layer Mattress 6*3 LK-MOH-236981-GO-DIR / 20 mic 1 Filter Tips,10 mic 1 Filter Tips, 200 mic 1 Filter Tips, 1000 mic 1 Filter Pending Component 1: Emergency 2021-06- 2021-06- 2021-07- 2022-01- Tips, PCR Tubes Optical IDA / 65950 Post Direct Selection Direct 1,250,000.00 0.00 Implement COVID-19 Response 16 21 26 22 Grade 0.1 ml, Individual PCR ation Tubes Optical Grade, Flat shaped lids , 0.2 ml and Disposable plastic Pasteur pippete , 3ml LK-MOH-236962-GO-RFQ / 04 Nos of Desk Top Computers, 01 No of Laptop Computer, 01 No of Pending Component 1: Emergency Request for Single Stage - One 2021-06- 2021-08- 2022-02- Photocopy Machine, 02 Nos IDA / 65950 Post Limited 7,600.00 0.00 Implement COVID-19 Response Quotations Envelope 27 22 18 Flat bed Scaners, 02 Nos of ation Laser Jet Printers (Black & White) and01 No of Laser Jet Colour Printer. LK-MOH-236966-GO-RFQ / 01 No of High Back Executive Chair-High Back, Pending 1 No of Executive Office Component 1: Emergency Request for Single Stage - One 2021-06- 2021-08- 2022-02- IDA / 65950 Post Limited 4,310.00 0.00 Implement Table, 04 Nos of Typist COVID-19 Response Quotations Envelope 28 23 19 ation Chair with Arms, 12 Nos Visiters Chair with Arms, 05 Nos of Work Stations and 02 Nos of Office Wall Racks LK-MOH-236968-GO-RFQ Pending Component 1: Emergency Request for Single Stage - One 2021-06- 2021-08- 2022-02- / 01 Unit Air Conditioner IDA / 65950 Post Limited 1,025.00 0.00 Implement COVID-19 Response Quotations Envelope 28 23 19 Unit - 18,000 BTU ation LK-MOH-236978-GO-RFQ Pending Component 1: Emergency Request for Single Stage - One 2021-06- 2021-08- 2021-08- / 50 Nos of Industrial IDA / 65950 Post Limited 26,000.00 0.00 Implement COVID-19 Response Quotations Envelope 29 17 31 Washing Machines ation LK-MOH-236982-GO-DIR Pending / 150,000 Nos of Nuclic- Component 1: Emergency 2021-06- 2021-06- 2021-07- 2022-01- IDA / 65950 Post Direct Selection Direct 990,000.00 0.00 Implement Acid Extraction Kits (Viral COVID-19 Response 15 20 25 21 ation DNA/RNA Isolation Kits) LK-MOH-234339-GO-RFB Component 1: Emergency Single Stage - One 2021-05- 2021-05- 2021-07- 2021-08- 2021-09- 2022-03- / 150000 numbers of IDA / 65950 Post Request for Bids Open - National 990,000.00 0.00 Canceled COVID-19 Response Envelope 26 31 12 11 15 14 Nucleic Acid Extraction Kits (Mannual) Pending LK-MOH-237143-GO-RFB Component 1: Emergency Single Stage - One 2021-06- 2021-06- 2021-08- 2021-09- 2021-10- 2022-04- IDA / 65950 Prior Request for Bids Open - National 4,600,000.00 0.00 Implement / 450,000 Nos of PPE Kits COVID-19 Response Envelope 24 29 10 09 14 12 ation NON CONSULTING SERVICES Activity Reference No. Estimated Actual Draft Pre- Draft Bidding Specific Proposal Bid Evaluation Loan / Credit Market Procurement Prequalificati Process Prequalification Bidding Documents Contract / Description Component Review Type Method Amount Amount qualification Document / Procurement Notice Submission / Report and Signed Contract No. Approach Process on (Y/N) Status Evaluation Report as Issued Completion (US$) (US$) Documents Justification / Invitation Opening / Minutes Recommendation Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned for Award Actual Planned Actual Planned Actual LK-MOH-171564-NC-RFB / Produce mass media Pending Component 1: Emergency Single Stage - One 2020-05- 2020-05- 2020-06- 2020-06- 2020-07- 2021-01- commercials and media IBRD / 90850 Post Request for Bids Open - National 1,200,000.00 0.00 Implement COVID-19 Response Envelope 13 18 01 08 13 09 time purchase in selected ation media channels in Sri-Lanka LK-MOH-171868-NC-RFQ Pending Component 1: Emergency Request for Single Stage - One 2020-06- 2020-07- 2020-08- / Supplying and Installation IBRD / 90850 Post Limited 2,595.00 0.00 Implement COVID-19 Response Quotations Envelope 02 21 04 of Electrical Panels ation LK-MOH-171740-NC-DIR / Pending Component 1: Emergency 2020-05- 2020-06- 2020-06- 2020-07- Supplying and Installation of IBRD / 90850 Post Direct Selection Direct 27,632.00 0.00 Implement COVID-19 Response 28 02 30 14 Oxygen System ation LK-MOH-171741-NC-RFQ Pending Component 1: Emergency Request for Single Stage - One 2020-05- 2020-07- 2020-07- / Hire of Tools IBRD / 90850 Post Limited 5,263.00 0.00 Implement COVID-19 Response Quotations Envelope 25 13 27 refurbishment work ation LK-MOH-172685-GO-RFQ / Prepared Changing Rooms,wash rooms and Pending Component 1: Emergency Request for Single Stage - One 2020-05- 2020-07- 2020-07- store rooms using IDA / 65950 Post Limited 15,105.00 0.00 Implement COVID-19 Response Quotations Envelope 13 01 22 containers at IDH procured ation by MoH Development unit during Covid 19 period. Pending LK-MOH-171736-NC-DIR / Component 1: Emergency Request for Single Stage - One 2020-06- 2020-07- 2020-08- IBRD / 90850 Post Limited 12,421.00 0.00 Implement Waterproofing work COVID-19 Response Quotations Envelope 02 21 04 ation LK-MOH-188661-NC-DIR / Pending Sewing of 135 Nos Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- IDA / 65950 Post Direct Selection Direct 197.00 0.00 Implement Polythene Aprons at COVID-19 Response 13 18 01 15 ation Ragama Teaching Hospital during Covid period LK-MOH-188850-NC-DIR / Pending Sawing 325 Nos Corona Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- IDA / 65950 Post Direct Selection Direct 197.00 0.00 Implement Apron required for Ragama COVID-19 Response 14 19 02 16 ation Teaching Hospital during Covid period LK-MOH-188865-NC-DIR / Pending Hire of Labour obtained by Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- IDA / 65950 Post Direct Selection Direct 211.00 0.00 Implement Ragama Teaching Hospital COVID-19 Response 14 19 02 16 ation during Covid period LK-MOH-188881-NC-DIR / Pending Sewing of 540 Nos corona Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- IDA / 65950 Post Direct Selection Direct 142.00 0.00 Implement apron for Ragama Teaching COVID-19 Response 14 19 02 16 ation Hospital during Covid period LK-MOH-188967-NC-DIR / Installation of power outlet Pending Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- service obtained by Ragama IDA / 65950 Post Direct Selection Direct 16.00 0.00 Implement COVID-19 Response 16 21 04 18 Teaching Hospital during ation Covid period LK-MOH-188968-NC-DIR / Sewing of 390 Nos Corona Pending Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- Aprons obtained by Ragama IDA / 65950 Post Direct Selection Direct 103.00 0.00 Implement COVID-19 Response 16 21 04 18 Teaching Hospital during ation Covid period LK-MOH-188979-NC-DIR / Pending Sewing of 800 Nos Coron Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- IDA / 65950 Post Direct Selection Direct 211.00 0.00 Implement Aprons for Ragama COVID-19 Response 16 21 04 18 ation Teaching Hospital during Covid period LK-MOH-188980-NC-DIR / Pending Sewing of 450 Nos Coron Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- IDA / 65950 Post Direct Selection Direct 118.00 0.00 Implement Aprons for Ragama COVID-19 Response 16 21 04 18 ation Teaching Hospital during Covid period LK-MOH-188988-NC-DIR / Pending Sewing of 730 Nos Corona Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- IDA / 65950 Post Direct Selection Direct 192.00 0.00 Implement Aprons for Ragama COVID-19 Response 16 21 04 18 ation Teaching Hospital during Covid period. Page 20 LK-MOH-188993-NC-DIR / Pending Repair of sewing Machine at Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- IDA / 65950 Post Direct Selection Direct 24.00 0.00 Implement Ragama Teaching Hospital COVID-19 Response 16 21 04 18 ation during Covid period LK-MOH-189018-NC-DIR / For sawing 1000 Nos Pending Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- Polythene Apron for Ragama IDA / 65950 Post Direct Selection Direct 263.00 0.00 Implement COVID-19 Response 16 21 04 18 Teaching Hospital during ation Covid period. LK-MOH-189019-NC-DIR / Pending Sawing 897 Nos Polythine Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- IDA / 65950 Post Direct Selection Direct 174.00 0.00 Implement Apron for Ragama Teaching COVID-19 Response 16 21 04 18 ation Hospital during Covid period. LK-MOH-189020-NC-DIR / Pending Repair of sewing machine at Component 1: Emergency 2020-08- 2020-08- 2020-09- 2020-09- IDA / 65950 Post Direct Selection Direct 13.00 0.00 Implement Ragama Teaching Hospital COVID-19 Response 16 21 04 18 ation during Covid period LK-MOH-190365-CW-RFQ / Installation of a Pedal Sink Pending Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-10- in front of Ward 33 (Lama IDA / 65950 Post Limited 263.00 0.00 Implement COVID-19 Response Quotations Envelope 31 12 13 Piyasa) at Ragama Teaching ation Hospital during Covid period. LK-MOH-190395-NC-RFQ / Installing a new door to Pending Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-10- the toilet at Ward 06 at IDA / 65950 Post Limited 263.00 0.00 Implement COVID-19 Response Quotations Envelope 31 12 26 Ragama Teaching Hospital ation during Covid period. LK-MOH-190397-NC-RFQ / Installation of a new sink Pending Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-10- for the ward 23 clinic at IDA / 65950 Post Limited 263.00 0.00 Implement COVID-19 Response Quotations Envelope 31 12 26 Ragama Teaching Hospital ation during Covid period. LK-MOH-190398-NC-RFQ / Installation of a new sink Pending Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-10- for the ward 23 clinic at IDA / 65950 Post Limited 263.00 0.00 Implement COVID-19 Response Quotations Envelope 31 12 26 Ragama Teaching Hospital ation during Covid period. LK-MOH-190399-NC-RFQ / Fixing Rubber beading tape for the doors at the Pending Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-10- entrance of the medical IDA / 65950 Post Limited 263.00 0.00 Implement COVID-19 Response Quotations Envelope 31 12 26 intensive care unit Anti- ation room and Anti-room area at Ragama Teaching Hospital during Covid period. LK-MOH-190401-NC-RFQ / Fixing Rubber beading tape for the doors at the Pending Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-10- entrance of the medical IDA / 65950 Post Limited 263.00 0.00 Implement COVID-19 Response Quotations Envelope 31 12 26 intensive care unit Anti- ation room and Anti-room area at Ragama Teaching Hospital during Covid period. LK-MOH-190402-NC-RFQ / Fixing Rubber beading tape for the doors at the Pending Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-10- entrance of the medical IDA / 65950 Post Limited 263.00 0.00 Implement COVID-19 Response Quotations Envelope 31 12 26 intensive care unit Anti- ation room and Anti-room area at Ragama Teaching Hospital during Covid period. LK-MOH-190403-NC-RFQ / Installation of new sink & Pending Component 1: Emergency Request for Single Stage - One 2020-08- 2020-10- 2020-10- tap for Ward 26 at Ragama IDA / 65950 Post Limited 263.00 0.00 Implement COVID-19 Response Quotations Envelope 31 12 26 Teaching Hospital during ation Covid period. LK-MOH-190955-NC-DIR / Central AC – Repair and Fix Pending Component 1: Emergency 2020-08- 2020-09- 2020-09- 2020-10- at Anuradhapura Teaching IDA / 65950 Post Direct Selection Direct 30,224.00 0.00 Implement COVID-19 Response 28 02 16 16 Hospital G during Covid ation period. LK-MOH-192657-NC-RFQ / Production of Feature film of 20-30 minutes, to Pending improve the community Component 1: Emergency Request for Single Stage - One 2020-10- 2020-11- 2020-12- TF / B3017 Post Limited 13,158.00 0.00 Implement awareness on importance of COVID-19 Response Quotations Envelope 05 23 23 ation healthy relationships for a happy family for Family Health Bureau under Covid Grant LK-MOH-192658-NC-RFQ / Production of Sinhala and Tamil versions of an electronic media message of 30 seconds duration, to Pending Component 1: Emergency Request for Single Stage - One 2020-10- 2020-11- 2020-12- improve the community TF / B3017 Post Limited 5,263.00 0.00 Implement COVID-19 Response Quotations Envelope 05 23 23 awareness on available ation health sector services for the survivors of Gender –based Violence for Family Health Bureau under Covid Grant. LK-MOH-192659-NC-RFQ / Production of Sinhala and Tamil versions of an electronic media message of 30 seconds duration, to Pending Component 1: Emergency Request for Single Stage - One 2020-10- 2020-11- 2020-12- improve the community TF / B3017 Post Limited 5,263.00 0.00 Implement COVID-19 Response Quotations Envelope 05 23 23 awareness on Preconception ation care programme as a mode of primordial prevention of Gender-Base Violence For Family Health Bureau under Co LK-MOH-192660-NC-RFQ / Telecasting of produced Pending Component 1: Emergency Request for Single Stage - One 2020-10- 2020-11- 2020-12- feature film in television TF / B3017 Post Limited 5,263.00 0.00 Implement COVID-19 Response Quotations Envelope 05 23 23 networks for Family Health ation Bureau under Covid Grant LK-MOH-192662-NC-RFQ / Publicizing produced Pending electronic media messages Component 1: Emergency Request for Single Stage - One 2020-10- 2020-11- 2020-12- TF / B3017 Post Limited 148,267.00 0.00 Implement in television networks for COVID-19 Response Quotations Envelope 05 23 23 ation Family Health Bureau under Covid Grant LK-MOH-201168-NC-RFQ / To carry out soil Pending Component 1: Emergency Request for Single Stage - One 2020-11- 2020-12- 2021-01- investigation of the IDA / 65950 Post Limited 11,358.00 0.00 Implement COVID-19 Response Quotations Envelope 09 21 04 construction site for ation proposed Isolation Centre at IDH. LK-MOH-201652-NC-RFQ Pending / Intercom System and Data Component 1: Emergency Request for Single Stage - One 2020-11- 2020-12- 2021-01- IDA / 65950 Post Limited 3,846.00 0.00 Implement cabling at the new COVID-19 Response Quotations Envelope 17 20 19 ation infections disease hospital in Kilinochchi LK-MOH-203419-NC-RFQ / Production of 05 Items of Information, Educational Pending and Communication Component 1: Emergency Request for Single Stage - One 2020-11- 2021-01- 2021-07- TF / B3017 Post Limited 40,778.00 0.00 Implement Materials (Light Boxes, COVID-19 Response Quotations Envelope 24 19 18 ation Pennants, Wall Charts, Stickers and Video Clips ) for Mental Health Directorate. (Grant) LK-MOH-203426-NC-DIR / Mental Health promotion Pending among under privileged Component 1: Emergency 2020-11- 2020-11- 2020-12- 2021-01- TF / B3017 Post Direct Selection Direct 3,555.00 0.00 Implement children in Three Districts COVID-19 Response 19 24 08 07 ation through the active utilization of Drama Therapy. (Grant) LK-MOH-203444-NC-RFQ / Display Time on LED Pending Component 1: Emergency Request for Single Stage - One 2020-11- 2021-01- 2021-01- Screens to display videos on TF / B3017 Post Limited 32,432.00 0.00 Implement COVID-19 Response Quotations Envelope 24 05 19 current health issues and ation public health emergencies. (Grant) LK-MOH-203469-NC-RFQ Pending / Development of six Component 1: Emergency Request for Single Stage - One 2020-11- 2021-01- 2021-01- TF / B3017 Post Limited 13,514.00 0.00 Implement graphic animation video for COVID-19 Response Quotations Envelope 24 05 19 ation Health Promotion Bureau. (Grant) LK-MOH-203725-NC-DIR / Face Book and Instagram Pending social media platform Component 1: Emergency 2020-11- 2020-12- 2021-01- 2022-12- TF / B3017 Post Direct Selection Direct 48,649.00 0.00 Implement service for the period of two COVID-19 Response 26 01 05 26 ation years required by Health Promotion Bureau (Grant) LK-MOH-205700-NC-DIR / Pending Airing video communication Component 1: Emergency 2020-12- 2020-12- 2021-01- 2021-02- IDA / 65950 Post Direct Selection Direct 54,055.00 0.00 Implement to mitigate stigma attached COVID-19 Response 02 07 11 10 ation to COVID LK-MOH-205701-NC-RFQ / Airing video Pending Component 1: Emergency Request for Single Stage - One 2020-12- 2021-02- 2021-03- communication to mitigate IDA / 65950 Post Limited 195,000.00 0.00 Implement COVID-19 Response Quotations Envelope 07 01 03 stigma attached to COVID ation through television media LK-MOH-205849-NC-RFQ / Airing video Pending Component 1: Emergency Request for Single Stage - One 2020-12- 2021-02- 2021-03- communication to mitigate IDA / 65950 Post Limited 54,054.00 0.00 Implement COVID-19 Response Quotations Envelope 07 01 03 stigma attached to COVID ation through television media LK-MOH-207673-NC-DIR / Pending Extension of Central Air Component 1: Emergency 2020-12- 2020-12- 2021-01- 2021-07- IDA / 65950 Post Direct Selection Direct 81,081.00 0.00 Implement Conditioning system at DGH COVID-19 Response 22 27 31 30 ation Gampaha. LK-MOH-207669-NC-RFQ / Design & Development of Pending Component 1: Emergency Request for Single Stage - One 2020-12- 2021-02- 2021-02- 5 Video Clips ( 3-5 min) to TF / B3017 Post Limited 13,514.00 0.00 Implement COVID-19 Response Quotations Envelope 27 07 21 promote mental health ation across lifespan and settings LK-MOH-215774-NC-DIR / Establishment of Regular Vaccine Cold Chain Pending Monitoring Network System Component 1: Emergency 2021-02- 2021-02- 2021-03- 2021-09- IDA / 65950 Post Direct Selection Direct 108,108.00 0.00 Implement for Central and Regional COVID-19 Response 08 13 20 16 ation Medical supply devisions (Central Monitoring System Smart View) LK-MOH-224251-NC-RFQ Pending Component 1: Emergency Request for Single Stage - One 2021-04- 2021-05- 2021-11- / Labortary investigation for IDA / 65950 Post Limited 26,400.00 0.00 Implement COVID-19 Response Quotations Envelope 04 30 26 vitamin D serum ation C/creatining LK-MOH-224238-NC-RFQ / supply installation and Component 1: Emergency Request for Single Stage - One 2021-04- 2021-06- 2021-12- IDA / 65950 Post Limited 6,320.00 0.00 Canceled commissioning of medical COVID-19 Response Quotations Envelope 13 08 05 gas / oxygen to HDU LK-MOH-231677-NC-DIR / Provision of server space, connectivity and required Component 2: modifications to establish a Strengthening National and Pending Laboratory Information 2021-05- 2021-05- 2021-07- 2021-12- IDA / 65950 Sub-national Institutions Post Direct Selection Direct 185,000.00 0.00 Implement System for connecting 33 25 30 04 31 for Prevention and ation PCR labs with public Health Preparedness Field units involved with sampling, diagnosis and contact tracing (LIMS) CONSULTING FIRMS Activity Reference No. Actual Short List and Draft Opening of Combined Loan / Credit Market Contract Type Estimated Process Expression of Request for Evaluation of Contract / Description Component Review Type Method Amount Terms of Reference Request for Technical Proposals Evaluation Report Signed Contract No. Approach Amount (US$) Status Interest Notice Proposals as Issued Technical Proposal Completion (US$) Proposals / Minutes and Draft Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Negotiated Contract Actual Planned Actual Planned Actual LK-MOH-195368-CS-CQS / Redesign Sri Lanka College of Psychiatry website to Consultant Component 1: Emergency Pending 2020-10- 2020-10- 2020-12- 2021-01- 2021-02- 2021-08- provide public information TF / B3017 Post Qualification Open - National 42,105.00 0.00 COVID-19 Response Implementation 06 27 10 09 13 12 regarding island wide Selection services and online therapy under Covid Grant INDIVIDUAL CONSULTANTS Activity Reference No. Actual Invitation to Loan / Credit Market Contract Type Estimated Process Draft Negotiated Contract / Description Component Review Type Method Amount Terms of Reference Identified/Selected Signed Contract No. Approach Amount (US$) Status Contract Completion (US$) Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LK-MOH-207591-CS-CDS / Consultancy Services to Strengthening Community Component 1: Emergency Pending 2020-12- 2021-01- 2021-03- 2021-09- TF / B3017 Post Direct Selection Direct 75,805.00 0.00 Engagement Activities in the COVID-19 Response Implementation 22 01 07 03 COVID 19 situation in the country. Page 21 Procurement Plan for Punjab RWSS (P150520) I. General 1. Bank’s approval Date of the procurement Plan 2012 2. Date of General Procurement Notice: [October 01, 2014 ] 3. Period covered by this procurement plan: January 2020 onwards II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as per the Procurement Risk Rating of the Project: 2. Procurement Method Prior Review Threshold US$ 1. ICB and LIB (Goods) Above US$ 2M 2. NCB (Goods) Above US$ 1M 3. ICB (Works) Above US$ 40 million 4. NCB (Works) Above US$ 10 million 5. (Non-Consultant Services) Above US$ 1M 2. Prequalification for Bidders _Not applicable_ 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: NA 4. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan Project P150520 5. Any Other Special Procurement Arrangements: In addition, the justification for all contracts to be issued on the basis of LIB, single-source or direct contracting (except for contracts less than US$50,000 in value) will be subject to prior review. III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Threshold 1. Competitive Methods (Firms) Above US$ 1M 2. Single Source (Firms) Above US$ 500,000 3. Individual Above US$ 300,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. PROCUREMENT India : Punjab Rural Water and Sanitation Sector Improvement Project PLAN General Information Country: India Bank’s Approval Date of the Original Procurement Plan: 2018-09-05 2021-05-31 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P150520 GPN Date: Project Name: Punjab Rural Water and Sanitation Sector Improvement Project Loan / Credit No: IBRD / 84870 HR Manager Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PRWSS-C-SPMC-5543-1 / Hiring of consultant to act as Strengthening Institutions IBRD / 84870 Post Direct Selection Direct 20,000.00 15,235.43 Signed 2018-08-31 2018-08-31 2018-09-01 2018-09-24 2018-09-01 2018-09-24 2019-09-01 Director Water Quality from and Project Management 01-09-2018 to 31-08-2019 PRWSS-C-SPMC-5646-1 / Hiring Sr. Environment Strengthening Institutions IBRD / 84870 Post Direct Selection Direct 27,700.00 1,800.97 Signed 2018-10-22 2018-04-27 2018-10-25 2018-10-22 2018-10-31 2018-10-22 2019-10-31 Specialist under PRWSSIP and Project Management Project. PRWSS-C-SPMC-5907-1 / Hiring of Advisor (Litigation) Strengthening Institutions IBRD / 84870 Post Direct Selection Direct 16,700.00 14,053.33 Signed 2018-12-18 2018-12-18 2018-12-26 2019-01-14 2018-12-28 2019-01-14 2019-12-28 in Department of Water and Project Management Supply and Sanitation, Punjab. PRWSS-C-SPMC-5365-2 / Hiring Liason Officer in Water Strengthening Institutions IBRD / 84870 Post Direct Selection Direct 18,000.00 14,449.69 Signed 2019-05-07 2018-05-03 2019-05-17 2019-05-09 2019-07-21 2019-05-09 2020-05-06 Supply and Sanitation and Project Management Department. PRWSS-C-SPMC-8190-1 / Strengthening Institutions Hiring Liason officer in WSS IBRD / 84870 Post Direct Selection Direct 17,000.00 0.00 Under Review 2020-04-26 2020-05-07 2020-05-04 2020-05-07 2021-05-07 and Project Management (continuation in Services) PRWSSIP-C-SPMC-6987-1 / Hiring of consultant to act as Strengthening Institutions IBRD / 84870 Post Direct Selection Direct 17,500.00 0.00 Canceled 2019-09-09 2019-08-31 2019-09-10 2019-09-10 2020-09-09 Director Water Quality from and Project Management 01-09-2019 to 31-08-2020 PRWSS-C-SPMC-7806-1 / Hiring of Advisor (Litigation) Strengthening Institutions IBRD / 84870 Post Direct Selection Direct 16,000.00 0.00 Canceled 2020-01-10 2020-01-12 2020-01-14 2021-01-13 in Department of Water and Project Management Supply and Sanitation, Punjab. PRWSS-C-SPMC-6666-1 / Strengthening Institutions Hiring of Consultant to act as IBRD / 84870 Post Direct Selection Direct 36,000.00 0.00 Canceled 2019-09-01 2019-09-16 2019-11-25 2021-11-24 and Project Management Building Construction Expert PRWSS-C-SPMC-9573-1 / Strengthening Institutions Hiring Liason officer in WSS IBRD / 84870 Post Direct Selection Direct 2,286.00 2,195.70 Signed 2021-05-11 2021-05-07 2021-05-13 2021-06-10 2021-05-16 2021-06-11 2021-06-30 and Project Management (continuation in Services) Page 1 Jhelum & Tawi Flood Recovery Project (Project ID: P154990) Procurement Summary I. General 1. Project Information: Project Name: Jhelum & Tawi Flood Recovery Project Country: India Project Code: P154990 2. Bank’s approval Date of the procurement Plan: Draft Procurement Plan dated April 24, 2015 Revision 0: Agreed by the Bank on April 25, 2015 Revision 1: March 30, 217 Revision 2: Feb 15 2019 3. Date of General Procurement Notice: September 01 2015 4. Period covered by this procurement plan: next 18 months II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Methods and Threshold Category Method of Threshold (US$ Equivalent) Procurement Goods and Non- ICB >3,000,000 consultant LIB Wherever agreed by the services Bank NCB Up to 3,000,000 (with NCB conditions) Shopping Up to 500,000 DC As per Para 3.7 of the Bank Guidelines, wherever agreed and with prior agreement with the Bank Force Account As per Para 3.9 of Guidelines Framework As per Para 3.6 of Agreements Guidelines Works and Supply ICB >40,000,000 and Installation NCB Up to 40,000,000 (with NCB conditions) Shopping Up to 1,000,000 carried out through a qualified local contractor selected through shopping (after inviting a minimum of three quotations in response to a written invitation with a minimum of 15 days’ notice period) Force Account As per Para 3.9 of Guidelines DC As per Para 3.7 of Guidelines,  Prior Review by the Bank. The Bank will prior review the following contracts: • Works: All contracts more than US$ 10.0 million equivalent; • Goods: All contracts more than US$ 2.0 million equivalent; • Information Technology: All contracts more than US$ 2.0 million equivalent; and • Non-Consulting Services: All contracts more than US$ 2.0 million equivalent  The PMU shall prior review the first contract issued by each implementing agency, if the estimate of those contracts are below the prior review threshold value. The Bank will conduct prior review for only those contract whose estimate falls in prior review threshold value. In addition, the justifications for all contracts to be issued on LIB, single-source (>US$ 30,000) or direct contracting (>US$ 30,000) basis will be subject to Banks prior review. These thresholds are for the initial 18 months period and are based on the procurement performance of the project, these thresholds will be modified. In addition, the Bank will carry out an annual ex post procurement review of the procurement falling below the prior review threshold mentioned above.  All contracts below the specified prior review threshold value shall be subject to Post Procurement Review (PPR). The IA shall prepare a list of contract and submit it to the Bank for conducting PPR. The PPR will be conducted on annual basis. 2. Pre-qualification. Not applicable 3. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan Project issued by Project Management Unit JTFRP, J&K, India All the contracts issued under the project will follow the World Bank’s Guidelines: Bank’s “Guidelines: Procurement under IBRD Loans and IDA Credits” dated January 2011and revised in July 2014and “Guidelines: Selection and Employment of Consultants by World Bank Borrowers” dated January 2011 and revised in July 2014, In case of any inconsistency between the Procurement Manual or Government Procurement Procedures and the Bank Guidelines, the latter shall prevail. 4. Any Other Special Procurement Arrangements: The bid evaluation will be carried out as per agreed timeline in the Procurement Manual.  National Competitive Bidding (NCB): Any contract exceeding shopping threshold shall be procured using NCB method. The model bidding documents for NCB as agreed with the GoI Task Force (and as amended from time to time), shall be used for bidding. The following NCB provisions shall apply: i. Only the model bidding documents for NCB as agreed with the GoI Task Force (and as amended from time to time), shall be used for bidding. ii. Invitation to bid shall be advertised in at least one widely circulated national daily newspaper (or on a widely used website or electronic portal with free national and international access along with an abridged version of the said advertisement published in a widely circulated national daily inter-alia giving the website/electronic portal details from which the details of the invitation to bid can be downloaded), at least 30 days prior to the deadline for the submission of bids. For smaller packages (lesser than US$1 million for Works and US$ 500,000 for Goods), advertisement in state newspapers will be accepted with at least 15 days given for submission of bids; iii. No special preference will be accorded to any bidder either for price or for other terms and conditions when competing with foreign bidders, state-owned enterprises, small-scale enterprises or enterprise from any given State; iv. Except with the prior concurrence of the Bank, there shall be no negotiation of price with the bidders, even with the lowest evaluated bidder; v. At the Borrower's request, the Bank may agree to the Borrower's use, in whole or in part, of its electronic procurement system, provided that the Bank is satisfied with the adequacy of such system. vi. For prior review contracts, extension of bid validity shall not be allowed with reference to Contracts subject to Bank prior review without the prior concurrence of the Bank (i) for the first request for extension if it is longer than four weeks; and (ii) for all subsequent requests for extension irrespective of the period (such concurrence will be considered by Bank only in cases of Force Majeure and circumstance beyond the control of the Purchaser/Employer); vii. For prior review contracts , re-bidding shall not be carried out with reference to Contracts subject to Bank prior review without the prior concurrence of the Bank; viii. The system of rejecting bids outside a pre-determined margin or “bracket” of prices shall not be used in the project; ix. Government e-Marketplace (GeM)1 set-up by Ministry of Commerce, Government of India will be acceptable for procurement under Request for Quotations (RFQ) method. x. The Borrower shall use an effective complaints mechanism for handling procurement related complaints in a timely manner. xi. Two or three envelop system will not be used (expect when suing e-procurement system assessed and agreed by the Bank. xii. Procurement Documents will include provisions, as agreed with the Bank, intended to adequately mitigate against environmental, social (including sexual exploitation and abuse and gender-based violence), health and safety ("ESHS") risks and impacts.  Force Account: When contractors/suppliers are unlikely to bid at reasonable prices because of the location and risk associated with the project or a certain government agency has exclusive rights in certain type of works/supply, borrowers may use their own government departments’ personnel and equipment or government owned construction unit may be the only practical method, provided that the borrower has sufficient managerial capacity and possesses the required technical and financial controls to report to the Bank on expenditure as per paragraph 3.9 of the Procurement Guidelines.  Framework Agreements: State level rate contracts will be examined by the Bank and if agreed, may also be used as framework agreements. Implementing agencies also have option to set-up new framework agreements as per paragraph 3.6 of Guidelines.  Use of government Institutions and Enterprise: Government owned enterprise or institutions in India may be hired for its unique and exceptional nature if their participation is considered critical to the project implementation. In such cases, the conditions given in clauses 1.13 of Consultant Guidelines shall be satisfied and each case will be subject to prior review by the Bank. The works contracts up to cumulative amount of 37.5 million USD, would be directly executed by the J&K Projects Construction 1 Use of GeM will be allowed in lieu of RFQ as per following details: • up to INR 50,000 in catalogue mode (viz. any available item could be selected by IA without further competition), provided selected Item/Supplier meeting the requisite quality, specification and delivery period. • up to INR 3 Million from the Supplier having lowest price amongst at least three Suppliers meeting the requisite quality, specification and delivery period. The tools for online bidding and online reverse auction available on GeM may be used by the Purchaser. • up to INR equivalent of US$ 500,000 from the Supplier having lowest price and meeting the requisite quality, specification and delivery period after mandatorily obtaining bids from at least three Suppliers, using online bidding or reverse auction tool provided on GeM. Corporation Ltd., which a Public Sector Undertaking. J&K Projects Construction Corporation Ltd. is executing projects of State as well as Central Government departments. 5. Summary of the Procurement Packages planned during the first 18 months and thereafter: Available on STEP III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Category Method of Procurement Threshold (US$ Equivalent) Consultants’ CQS Up to 500,000 Services SSS Up to 200,000 As per para 3.9-3.11 of Guidelines Individuals As per Section V of Guidelines QCBS/QBS/FBS/LCS for all other cases (i) International >800,000 shortlist (ii) Shortlist may Up to 800,000 comprise national consultants only  Prior Review by the Bank. The Bank will prior review the following contracts: o Consulting Services: All contracts more than US$ 1.0 million equivalent for firm; and o Consulting Services: All contracts more than US$ 300,000 equivalent for Individuals. 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $ 800,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Consultancy Assignments with Selection Methods and Time Schedule: Available on STEP Use of e-procurement portal Procurement of goods works and non-consultancy services shall be conducted using the e-procurement portal www.jktenders.gov.in. All IAs shall use this e-procurement portal for procurement of goods works and non-consulting services. PROCUREMENT India : Jhelum and Tawi Flood Recovery Project PLAN General Information Country: India Bank’s Approval Date of the Original Procurement Plan: 2016-12-22 2021-05-19 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P154990 GPN Date: 2016-11-18 Project Name: Jhelum and Tawi Flood Recovery Project Loan / Credit No: IDA / 56950 I Executing Agency(ies): ndustry & Commerce Department (I&CD), J&K WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned JTFRP/JK/IC/JKI/B/W001/16 / Construction/Repairs of factory Building at Bemina Woolen Mills Sgr. under Restoration and Single Stage - Two 2018-11- Project JTRF for restoration IDA / 56950 Post Request for Bids Open - National 732,230.00 218,451.40 Signed 2017-01-30 2017-08-18 2017-02-06 2017-03-08 2017-10-25 2017-04-14 2018-02-16 2017-05-19 2018-03-01 strengthening of livelihoods Envelope 18 and strengthening of livelihood for Composite Market Centre for Whole Chain of Wool Activity . JTFRP/JK/IC/JKI/R/W002/16 / Construction of factory building under JTFR Project for Restoration and Restoration and Single Stage - Two 1,735,510.0 2018-12- Strengthening of Livelihood IDA / 56950 Post Request for Bids Open - National 2,937,100.00 Signed 2017-01-30 2017-08-01 2017-02-06 2017-08-11 2017-03-08 2017-12-13 2017-04-14 2018-02-16 2017-05-22 2018-03-01 strengthening of livelihoods Envelope 0 21 for Composite Market Centre for Whole chain of Silk Activity at Silk Factory Rajbagh Srinagar. JTFRRP/JK/IC/CDI/CSPEP/W00 1/16 / Construction of PG Restoration and Single Stage - Two 2018-12- building at Craft Development IDA / 56950 Post Request for Bids Open - National 400,000.00 0.00 Canceled 2017-01-30 2017-02-04 2017-03-06 2017-04-20 2017-06-01 strengthening of livelihoods Envelope 01 Institute Srinagar under JTFRP . JTFRP/JK/IC/BWM/W003/19 / Interior works for showroom Restoration and Single Stage - Two 2019-12- cum interpretation centre for IDA / 56950 Post Request for Bids Open - National 338,500.00 312,919.37 Signed 2019-01-25 2019-04-13 2019-01-30 2019-04-29 2019-03-13 2019-06-21 2019-05-26 2019-10-07 2019-06-30 2019-11-29 strengthening of livelihoods Envelope 27 Government Woollen Mills Bemina Srinagar J&K GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual JTFRP/JK/IC/CDI/CSPEP/G001 /16 / Procurement of Digital and IT Equipment's , net working soft ware for upcoming post Graduate Restoration and Single Stage - One program in craft Design and IDA / 56950 Post Request for Bids Open - National 100,000.00 0.00 Canceled 2018-03-13 2018-03-18 2018-04-17 2018-06-01 2018-07-06 2018-10-04 strengthening of livelihoods Envelope sustainable development in creative industries being launched by CDI.Sgr under JTFRP for restoration strengthening of livelihoods. JTFRP/JK/IC/CDI/CSPEP/G003 /16 / Procurement for Printing of Brochures and other publicity materials for upcoming post graduate Restoration and Single Stage - One IDA / 56950 Post Request for Bids Open - National 8,000.00 0.00 Canceled 2018-01-09 2018-01-14 2018-02-13 2018-03-06 2018-04-13 2018-06-12 Programs in craft design and strengthening of livelihoods Envelope sustainable development in creative industries to be launched by CDI Sgr. under JTFRP . JTFRP/JK/IC/JKI/R/G001/16 / Procurement of machines under Jhelum and Tawi flood recovery project for restoration and Restoration and Single Stage - Two IDA / 56950 Post Request for Bids Open - National 651,098.00 0.00 Canceled 2018-02-25 2018-03-07 2018-04-10 2018-05-18 2018-06-05 2018-12-05 strengthening of livelihood strengthening of livelihoods Envelope composite market centre for whole chain of silk activity in Govt. Silk Factory Rajbagh Srinagar. JTFRP/JK/IC/JKI/B/G002/16 / Procurement of machines under Jehlum and Tawi Flood recovery project for restoration and strengthening Restoration and Single Stage - Two IDA / 56950 Post Request for Bids Open - National 1,074,124.00 0.00 Canceled 2018-02-26 2018-03-10 2018-04-14 2018-05-20 2018-06-10 2018-12-15 of livelihoods composite strengthening of livelihoods Envelope market centre for whole chain of wool activity in Govt. Wool Mills at Bemina Srinagar. JTFRP/JK/IC/BWM/G001/18 / Supply installation testing and Restoration and Single Stage - Two commissioning of various IDA / 56950 Post Request for Bids Open - National 338,460.00 0.00 Canceled 2018-09-28 2018-10-05 2018-10-03 2018-10-16 2018-11-14 2018-11-24 2019-01-27 2019-03-03 2019-08-30 strengthening of livelihoods Envelope textile machinery for Govt. Woolen mills Bemina JTFRP/JK/IC/BWM/G002/18 / Supply installation testing and Restoration and Single Stage - Two commissioning of cone IDA / 56950 Post Request for Bids Open - National 55,385.00 0.00 Canceled 2018-09-28 2018-10-06 2018-10-03 2018-10-16 2018-11-14 2018-11-24 2019-01-27 2019-03-03 2019-08-30 strengthening of livelihoods Envelope winders for Govt Woollen Mills Bemina Page 1 JTFRP/JK/IC/BWM/G003/18 / Supply Installation Testing Restoration and Single Stage - Two and Commissioning of Pirn IDA / 56950 Post Request for Bids Open - National 16,155.00 0.00 Canceled 2018-09-28 2018-10-09 2018-10-03 2018-10-16 2018-11-14 2018-11-26 2019-01-27 2019-03-03 2019-08-30 strengthening of livelihoods Envelope winder for Govt Woollen Mills Bemina JTFRP/JK/IC/BWM/G004/18 / Supply Installation Testing Restoration and Single Stage - Two and Commissioning of Rapier IDA / 56950 Post Request for Bids Open - National 246,150.00 0.00 Canceled 2018-10-02 2018-10-09 2018-10-07 2018-10-16 2018-11-18 2018-11-26 2019-01-31 2019-03-07 2019-09-03 strengthening of livelihoods Envelope Looms for Government Woollen Mills Bemina JTFRP/JK/IC/BWM/G005/18 / Supply Installation Testing and Commissioning of roller Restoration and Single Stage - Two IDA / 56950 Post Request for Bids Open - National 30,770.00 0.00 Canceled 2018-10-03 2018-10-09 2018-10-08 2018-10-16 2018-11-19 2018-11-27 2019-02-01 2019-03-08 2019-09-04 calendaring machine for strengthening of livelihoods Envelope Government Woollen Mills Bemina. JTFRP/JK/IC/BWM/G006/18 / Supply Installation Testing and Commissioning of dyeing Restoration and Single Stage - Two IDA / 56950 Post Request for Bids Open - National 170,000.00 0.00 Canceled 2018-10-08 2018-10-09 2018-10-13 2018-10-16 2018-11-24 2018-11-27 2019-02-06 2019-03-13 2019-09-09 and related machinery for strengthening of livelihoods Envelope Government Woollen Mills Bemina JTFRP/JK/IC/BWM/G007/18 / Supply Installation Testing Restoration and Single Stage - Two and Commissioning of Boilers IDA / 56950 Post Request for Bids Open - National 138,460.00 0.00 Canceled 2018-10-08 2018-10-09 2018-10-13 2018-10-16 2018-11-24 2018-11-28 2019-02-06 2019-03-13 2019-09-09 strengthening of livelihoods Envelope for Government Woollen Mills Bemina JTFRP/JK/IC/BWM/G008/18 / Supply Installation Testing and Commissioning of Fabric Restoration and Single Stage - Two IDA / 56950 Post Request for Bids Open - National 23,000.00 0.00 Canceled 2018-10-08 2018-10-09 2018-10-13 2018-10-16 2018-11-24 2018-11-29 2019-02-06 2019-03-13 2019-09-09 Inspection machines at strengthening of livelihoods Envelope Government Woollen Mills Bemina JTFRP/JK/IC/BMW/G009/18 / Supply Installation Testing Restoration and Single Stage - Two and Commissioning of Twist IDA / 56950 Post Request for Bids Open - National 15,385.00 0.00 Canceled 2018-10-05 2018-10-09 2018-10-10 2018-10-16 2018-11-21 2018-11-29 2019-02-03 2019-03-10 2019-09-06 strengthening of livelihoods Envelope Setting Chamber Government Woollen Mills Bemina JTFRP/JK/IC/RSF/G001/18 / Supply Installation Testing Restoration and Single Stage - Two and Commissioning of rapier IDA / 56950 Post Request for Bids Open - National 653,900.00 0.00 Canceled 2018-10-24 2018-10-20 2018-10-29 2018-10-29 2018-12-10 2018-12-12 2019-02-22 2019-03-29 2019-09-25 strengthening of livelihoods Envelope Looms for Govt Silk Factory Rajbagh Srinagar J&K JTFRP/JK/IC/BWM/G014/19 / Supply Installation, Testing and Commissioning of Rapier Restoration and Single Stage - Two IDA / 56950 Post Request for Bids Open - National 133,000.00 347,936.00 Signed 2019-01-21 2019-01-18 2019-01-26 2019-01-23 2019-03-09 2019-03-12 2019-05-22 2019-11-11 2019-06-26 2020-02-10 2019-09-24 looms for Government strengthening of livelihoods Envelope Woollen Mills Bemina Srinagar J&K JTFRP/JK/IC/RSF/G011/19 / Supply Installation Testing & Under Restoration and Single Stage - Two commissioning of Rapier IDA / 56950 Post Request for Bids Open - National 625,000.00 0.00 Implementati 2019-01-21 2019-01-17 2019-01-26 2019-01-22 2019-03-09 2019-05-22 2019-06-26 2019-09-24 strengthening of livelihoods Envelope Looms for Government Silk on Factory Rajbagh, Srinagar J&K JTFRP/JK/IC/RSF/G002/19 / Supply Installation Testing and Commissioning of Two Restoration and Single Stage - Two IDA / 56950 Post Request for Bids Open - National 1,086,000.00 0.00 Canceled 2019-05-27 2019-05-27 2019-06-01 2019-06-11 2019-07-13 2019-09-25 2019-10-30 2020-04-27 for One Twisters for strengthening of livelihoods Envelope Government Silk Factory Rajbagh Srinagar, J&K JTFRP/JK/IC/RSF/G003/19 / Supply Installation Testing and Commissioning of Restoration and Single Stage - Two preparatory machinery for IDA / 56950 Post Request for Bids Open - National 121,500.00 0.00 Canceled 2019-06-14 2019-06-24 2019-06-19 2019-07-09 2019-07-31 2019-10-13 2019-11-17 2020-05-15 strengthening of livelihoods Envelope government silk factory rajbagh Srinagar Jammu and Kashmir JTFRP/JK/IC/RSF/G022/19 / Supply Installation Testing and Commissioning of Two Restoration and Single Stage - Two IDA / 56950 Post Request for Bids Open - National 634,500.00 622,940.85 Signed 2019-07-21 2019-09-09 2019-07-26 2020-02-29 2019-09-06 2019-11-09 2019-11-19 2019-12-24 2019-12-24 2020-02-14 2020-06-21 for One Twisters for strengthening of livelihoods Envelope Government Silk Factory Rajbagh Srinagar J&K JTFRP/JK/IC/BWM/G017/19 / Supply Installation Testing & Restoration and Single Stage - Two Commissioning of boilers for IDA / 56950 Post Request for Bids Open - National 133,000.00 0.00 Canceled 2019-01-21 2019-01-18 2019-01-26 2019-03-09 2019-05-22 2019-06-26 2019-09-24 strengthening of livelihoods Envelope Government Woollen Mills Bemina Srinagar J&k JTFRP/JK/IC/BWM/G011/19 / Supply Installation & Testing Restoration and Single Stage - Two of various textile machinery IDA / 56950 Post Request for Bids Open - National 338,460.00 0.00 Canceled 2019-01-21 2019-01-18 2019-01-26 2019-01-23 2019-03-09 2019-05-22 2019-06-26 2019-09-24 strengthening of livelihoods Envelope for Government Woollen Mills, Bemina, Srinagar J&K JTFRP/JK/IC/BWM/G016/19 / Supply Installation Testing & Commissioning of dyeing & Restoration and Single Stage - Two IDA / 56950 Post Request for Bids Open - National 162,500.00 0.00 Canceled 2019-01-21 2019-01-18 2019-01-26 2019-01-23 2019-03-09 2019-05-22 2019-06-26 2019-09-24 related machinery for strengthening of livelihoods Envelope Government Woollen Mills Bemina Srinagar J&K JTFRP/JK/IC/BWM/G017/19- 2 / Supply Installation Testing and Commisioning of Boilers Restoration and Single Stage - Two IDA / 56950 Post Request for Bids Open - National 193,000.00 0.00 Canceled 2020-03-10 2020-04-05 2020-03-15 2020-05-12 2020-04-26 2020-07-09 2020-08-13 2020-11-11 for Government Woolen Mills strengthening of livelihoods Envelope Bemina and Government Silk Factory Rajbagh Srinagar J&K Page 2 JTFRP/JK/IC/BWM/G016/19- 2 / Supply Installation Testing Under and Commissioning of dyeing Restoration and Single Stage - Two IDA / 56950 Post Request for Bids Open - National 162,500.00 0.00 Implementati 2020-03-10 2020-05-11 2020-03-15 2020-05-20 2020-04-26 2020-07-09 2020-08-13 2020-11-11 & related machinery for strengthening of livelihoods Envelope on Government Woollen Mills Bemina Srinagar J&K JTFRP/JK/IC/BWM/G011/19- 2 / Supply Installation Testing Under and Commissioning for Restoration and Single Stage - Two IDA / 56950 Post Request for Bids Open - National 338,460.00 0.00 Implementati 2020-03-10 2020-08-10 2020-03-15 2020-09-12 2020-04-26 2020-07-09 2020-08-13 2020-11-11 various textile machinery for strengthening of livelihoods Envelope on Government Woollen Mills Bemina Srinagar J&K JTFRP/JK/IC/RSF/G003/19-2 / Supply, Installation, Testing and Commissioning of Restoration and Single Stage - Two IDA / 56950 Post Request for Bids Open - National 104,300.00 61,849.02 Signed 2020-05-19 2020-05-22 2020-05-24 2020-05-26 2020-07-05 2020-06-26 2020-09-17 2020-07-25 2020-10-22 2020-08-10 2021-04-20 Preparatory Machinery for strengthening of livelihoods Envelope Government Silk Factory, Rajbagh, Srinagar, J&K. JTFRP/JK/IC/RSF/G021/20 / Supply Installation Testing Under Restoration and Single Stage - Two and Commissioning of rapier IDA / 56950 Post Request for Bids Open - National 385,700.00 0.00 Implementati 2020-07-21 2020-08-02 2020-07-26 2020-08-10 2020-09-06 2020-11-19 2020-12-24 2021-06-22 strengthening of livelihoods Envelope Looms for Govt Silk Factory on Rajbagh Srinagar J&K JTFRP/JK/IC/RSF/G043/20 / Supply Installation Testing Under and Commissioning of Restoration and Single Stage - Two IDA / 56950 Post Request for Bids Open - National 185,700.00 0.00 Implementati 2020-07-22 2020-08-02 2020-07-27 2020-08-10 2020-09-07 2020-11-20 2020-12-25 2021-06-23 Weaving and Finishing strengthening of livelihoods Envelope on Machinery for Government Silk Factory Rajbagh Srinagar J&K JTFRP/JK/IC/BWM/G001/20 / Supply of bought out items Under Restoration and for Interiors of new showroom IDA / 56950 Post Direct Selection Direct 35,700.00 0.00 Implementati 2020-10-16 2020-10-05 2020-10-21 2020-11-25 2021-05-24 strengthening of livelihoods cum interpretation centre at on Govt Woollen Mills Bemina JTFRP/JK/IC/BWM/G017/19- 2-2 / Supply Installation Testing and Commisioning of Restoration and IDA / 56950 Post Request for Bids 193,000.00 0.00 Canceled 2020-10-07 2020-12-24 2020-10-12 2021-01-05 2020-11-23 2021-02-05 2021-02-05 2021-03-12 2021-06-10 Boilers for Government strengthening of livelihoods Woollens Mills Bemina and Government Silk Factory Rajbagh JTFRP/JK/IC/BWM/G001/21 / Supply, Installation, Testing & Commissioning of Boilers for Under Restoration and Single Stage - Two Government Silk Factory, IDA / 56950 Post Request for Bids Open - National 235,700.00 0.00 Implementati 2021-05-12 2021-05-19 2021-05-17 2021-05-25 2021-06-06 2021-07-30 2021-09-03 2021-12-02 strengthening of livelihoods Envelope Rajbagh and Government on Woollen Mills, Bemina, Srinagar, J&K NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual JTFRP/JK/IC/CDI/CSPEP/C003 /16 / Providing of consultancy services towards design of publicity and promotion material for Restoration and Least Cost IDA / 56950 Post Open - National 3,071.00 0.00 Canceled 2017-06-28 2017-07-12 2017-08-11 2017-09-10 2017-09-25 2017-10-17 2017-11-21 2017-12-21 launching of Post Graduate strengthening of livelihoods Selection Program in Craft Design and sustainable development in creative industriesby CDI Sgr under JTFRP . JTRF/JK/IC/HD/C002/16 / Consultancy for census of Restoration and Quality And Cost- Craft practitioners in J&K and IDA / 56950 Post Open - National 307,700.00 368,747.71 Signed 2017-01-25 2017-01-22 2017-02-08 2017-04-05 2017-03-10 2017-08-20 2017-04-16 2018-08-20 2017-05-01 2018-10-20 2017-05-23 2019-03-14 2017-06-27 2019-05-30 2018-06-27 strengthening of livelihoods Based Selection to develop a complete Artisans database. JTFRP/JK/IC/HD/C001/16 / Consultancy for feasibility of Reconstruction of roads and Quality And Cost- IDA / 56950 Post Open - National 15,400.00 0.00 Canceled 2017-01-28 2017-01-19 2017-02-12 2017-04-05 2017-03-19 2017-04-18 2017-05-03 2017-05-25 2017-06-29 2017-08-28 site & working Model for bridges Based Selection Kashmir Haat. JTFRP/JK/IC/HD/C003/17 / Develop E Commerce Strategy and Actionable Business Plan, Restoration and Quality And Cost- Design Build And Maintain E IDA / 56950 Post Open - National 230,800.00 0.00 Canceled 2017-03-15 2017-03-13 2017-04-05 2017-04-05 2017-05-19 2017-06-16 2017-07-01 2017-08-05 2017-09-09 2021-03-12 strengthening of livelihoods Based Selection Commerce Portal and Manage E Commerce Operations under JTFRP. JTFRP/JK/IC/HD/C006/17 / Develop E Commerce Strategy and Actionable Business Plan, Restoration and Quality And Cost- Design Build And Maintain E IDA / 56950 Post Open - National 230,800.00 0.00 Canceled 2017-08-10 2017-09-26 2017-08-31 2017-10-20 2017-10-14 2017-11-11 2017-12-11 2018-01-15 2018-02-19 2020-06-01 strengthening of livelihoods Based Selection Commerce Portal and Manage E Commerce Operations under JTFRP JTFRP/JK/IC/HD/R/C001/18 / Consultancy for feasibility of site and working model for Restoration and Quality And Cost- IDA / 56950 Post Open - National 80,000.00 0.00 Canceled 2018-03-25 2018-04-19 2018-04-15 2018-05-29 2018-06-26 2018-07-26 2018-08-30 2018-10-04 2019-01-02 Kashmir Haat and strengthening of livelihoods Based Selection International Trade Centre at Pampore Page 3 JTFRP/JK/IC/HD/ECOM/C002/ 18 / Develop e-Commerce Strategy and Actionable Restoration and Quality And Cost- Business PlanDesign, Build, IDA / 56950 Post Open - National 230,800.00 0.00 Canceled 2018-04-27 2018-08-06 2018-05-07 2018-06-13 2018-07-11 2018-07-26 2018-08-30 2018-10-04 2022-04-06 strengthening of livelihoods Based Selection Maintain and Manage e- Commerce Operations under JTFRP JTFRP/JK/IC/JKI/UCCN/C002/ 18 / Consultancy Services For preparation of dossier for Restoration and Quality And Cost- IDA / 56950 Post Open - National 115,400.00 64,016.52 Signed 2018-08-05 2018-08-06 2018-08-26 2018-10-09 2018-10-01 2018-11-06 2018-12-11 2018-12-06 2019-03-20 2019-01-10 2019-04-10 2019-02-14 2019-04-23 2020-02-14 inclusion of Srinagar city On strengthening of livelihoods Based Selection UNESCO Creative Cities Network JTFRP/JK/IC/HD/WW/C005/18 / Consultancy services to carry out end to end cluster Restoration and Quality And Cost- IDA / 56950 Post Open - National 384,615.00 0.00 Canceled 2018-09-28 2018-10-15 2018-10-03 2018-11-10 2018-11-16 2018-12-14 2019-01-13 2019-02-17 2019-03-24 2020-03-23 development activities in strengthening of livelihoods Based Selection willow wicker cluster at Ganderbal JTFRP/JK/IC/HDD/WB/C007/1 8 / Consultancy services to undertake Cluster Restoration and Quality And Cost- IDA / 56950 Post Open - National 384,615.00 0.00 Canceled 2018-10-18 2018-10-20 2018-11-08 2018-11-10 2018-12-22 2019-01-19 2019-02-18 2019-03-25 2019-04-29 2022-04-04 Development activities in strengthening of livelihoods Based Selection Wool Cluster of Bandipora, Jammu and Kashmir JTFRP/JK/IC/HDD/WP/C008/1 8 / Consultancy services to undertake Cluster Restoration and Quality And Cost- IDA / 56950 Post Open - National 384,615.00 0.00 Canceled 2018-10-19 2018-10-25 2018-11-09 2018-11-10 2018-12-23 2019-01-20 2019-02-19 2019-03-26 2019-04-30 2022-04-04 Development activities in strengthening of livelihoods Based Selection Wool Cluster of Pulwama, Jammu and Kashmir JTFRP/JK/IC/BBC/C010/18 / Consultancy services to develop and launch branding Restoration and Quality And Cost- IDA / 56950 Post Open - National 153,850.00 0.00 Canceled 2018-10-29 2018-12-03 2018-11-19 2018-12-17 2019-01-02 2019-01-30 2019-03-01 2019-04-05 2019-05-10 2020-05-09 and communications strengthening of livelihoods Based Selection campaign for products of J&K state JTFRP/JK/IC/IML/C011/18 / Consultancy to undertake training of artisans in product development cycle for Restoration and Quality And Cost- IDA / 56950 Post Open - National 307,700.00 0.00 Canceled 2018-10-29 2018-12-03 2018-11-19 2018-12-17 2019-01-02 2019-01-30 2019-03-01 2019-04-05 2019-05-10 2021-05-09 International Market Linkages strengthening of livelihoods Based Selection in Willow Wicker, Papier Machie, Embroidery and Wool in Jammu and Kashmir JTFRP/JK/IC/HD/WW/C015/18 / Consultancy services to undertake end to end cluster Restoration and Quality And Cost- IDA / 56950 Post Open - National 384,615.00 0.00 Canceled 2018-11-30 2018-12-03 2018-12-21 2018-12-17 2019-02-03 2019-03-03 2019-04-02 2019-05-07 2019-06-11 2021-06-10 development actvities in strengthening of livelihoods Based Selection Willow Wicker Cluster in Ganderbal JTFRP/JK/IC/HDD/WP/C018/1 8 / Consultancy services for carrying out end to end Restoration and Quality And Cost- IDA / 56950 Post Open - National 384,615.00 0.00 Canceled 2018-11-30 2018-12-03 2018-12-21 2018-12-17 2019-02-03 2019-03-03 2019-04-02 2019-05-07 2019-06-11 2021-06-10 cluster development strengthening of livelihoods Based Selection activitiesin wool cluster at Pulwama JTFRP/JK/IC/HDD/WB/C017/1 8 / Consultancy services for Restoration and Quality And Cost- carrying out end to end IDA / 56950 Post Open - National 384,615.00 0.00 Canceled 2018-11-30 2018-12-03 2018-12-21 2018-12-17 2019-02-03 2019-03-03 2019-04-02 2019-05-07 2019-06-11 2021-06-10 strengthening of livelihoods Based Selection cluster development activities in wool cluster at Bandipora. JTFRP/JK/IC/HD/ECOM/C012/ 19 / Consultancy services to develop e-Commerce Strategy Consultant Restoration and and Actionable Business Plan IDA / 56950 Post Qualification Open - National 230,800.00 0.00 Canceled 2019-01-20 2019-02-10 2019-03-26 2019-04-25 2019-05-30 2022-11-30 strengthening of livelihoods Design, Build, Maintain and Selection Manage e-Commerce Operations JTFRP/JK/IC/IML/C021/19 / to undertake Training of Artisans in Product Development Cycle for Restoration and Quality And Cost- Under IDA / 56950 Post Open - National 307,700.00 0.00 2019-02-18 2019-02-15 2019-03-11 2019-02-28 2019-04-24 2019-05-22 2019-06-21 2019-07-26 2019-08-30 2021-08-29 International Market Linkages strengthening of livelihoods Based Selection Implementation in Willow Wicker, Paper Mache, Crewel stitch embroidery and Wool in Jammu and Kashmir JTFRP/JK/IC/HDD/WB/C027/1 9 / Consultancy services to undertake Cluster Restoration and Quality And Cost- IDA / 56950 Post Open - National 384,615.00 256,006.78 Signed 2019-02-18 2019-03-12 2019-03-11 2019-03-21 2019-04-24 2019-06-25 2019-05-22 2019-08-29 2019-06-21 2019-12-10 2019-07-26 2019-12-16 2019-08-30 2020-02-10 2021-08-29 Development activities in strengthening of livelihoods Based Selection Wool Cluster of Bandipora, Jammu and Kashmir JTFRP/JK/IC/HDD/WP/C020/1 9 / Consultancy services to undertake Cluster Restoration and Quality And Cost- IDA / 56950 Post Open - National 384,615.00 0.00 Canceled 2019-02-18 2019-03-18 2019-03-11 2019-03-21 2019-04-24 2019-05-22 2019-06-21 2019-07-26 2019-08-30 2021-08-29 Development activities in strengthening of livelihoods Based Selection Wool Cluster of Pulwama, Jammu and Kashmir JTFRP/JK/IC/BBC/C020/19 / Consultancy services to Restoration and Quality And Cost- develop and launch branding IDA / 56950 Post Open - National 153,850.00 296,862.77 Signed 2019-02-18 2019-02-20 2019-03-11 2019-02-28 2019-04-24 2019-12-07 2019-05-22 2020-02-27 2019-06-21 2020-03-16 2019-07-26 2020-06-01 2019-08-30 2020-07-26 2020-08-29 strengthening of livelihoods Based Selection and communications Campaign for J&K products JTFRP/JK/HD/WW/C025/19 / Consultancy services to carry out end to end cluster Restoration and Quality And Cost- IDA / 56950 Post Open - National 384,615.00 0.00 Canceled 2019-03-25 2019-03-15 2019-04-15 2019-03-21 2019-05-29 2019-06-26 2019-07-26 2019-08-30 2019-10-04 2021-10-03 development activities in strengthening of livelihoods Based Selection Willow Wicker craft at Ganderbal J&K Page 4 JTFRP/JK/IC/JKI/R/C005/19 / Consultancy services for Restoration and Quality And Cost- conservation/restoration and IDA / 56950 Post Open - National 114,300.00 116,526.88 Signed 2019-04-10 2019-04-10 2019-05-01 2019-04-14 2019-06-14 2019-12-04 2019-07-12 2020-02-12 2019-08-11 2020-02-18 2019-09-15 2020-04-24 2019-10-20 2020-06-30 2021-04-12 strengthening of livelihoods Based Selection adaptive reuse of Govt Silk Factory Rajbagh, Srinagar J&K JTFRP/JK/IC/HD/ECOM/022/1 9 / Consultancy services to develop e-Commerce Strategy Restoration and Quality And Cost- and Actionable Business Plan IDA / 56950 Post Open - National 657,100.00 0.00 Canceled 2019-04-12 2019-05-24 2019-05-03 2019-06-05 2019-06-16 2019-07-14 2019-08-13 2019-09-17 2019-10-22 2023-04-24 strengthening of livelihoods Based Selection Design, Build, Maintain and Manage e-Commerce Operations JTFRP/JK/HD/WW/C035/19 / Consultancy services to carry out end to end cluster Restoration and Quality And Cost- IDA / 56950 Post Open - National 384,615.00 0.00 Canceled 2019-07-21 2019-09-01 2019-08-11 2019-09-29 2019-09-24 2019-10-22 2019-11-21 2019-12-26 2020-01-30 2022-01-29 development activities in strengthening of livelihoods Based Selection Willow Wicker craft at Ganderbal J&K JTFRP/JK/IC/HDD/WP/C030/1 9 / Consultancy services to Restoration and Quality And Cost- undertake cluster IDA / 56950 Post Open - National 384,615.00 0.00 Canceled 2019-07-21 2019-09-08 2019-08-11 2019-09-29 2019-09-24 2019-10-22 2019-11-21 2019-12-26 2020-01-30 2022-01-29 strengthening of livelihoods Based Selection development activities in Wool cluster of Pulwama J&K JTFRP/JK/HD/WW/C035/19-2 / Consultancy services to carry out end to end cluster Restoration and Quality And Cost- IDA / 56950 Post Open - National 384,615.00 154,542.70 Signed 2019-11-06 2019-10-20 2019-11-27 2019-11-19 2020-01-10 2020-05-23 2020-02-07 2020-05-29 2020-03-08 2020-06-06 2020-04-12 2020-06-18 2020-05-17 2020-08-14 2022-05-17 development activities in strengthening of livelihoods Based Selection willow wicker cluster at ganderbal JTFRP/JK/IC/HDD/WP/C030/1 9-2 / Consultancy services to Restoration and Quality And Cost- undertake end to end cluster IDA / 56950 Post Open - National 384,615.00 0.00 Canceled 2019-11-06 2019-11-04 2019-11-27 2019-11-19 2020-01-10 2020-02-07 2020-03-08 2020-04-12 2020-05-17 2022-05-17 strengthening of livelihoods Based Selection development activities in wool cluster at Pulwama INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual JTFRP/JK/IC/JKI/R/C001/16 / Consultancy to provide technical assistance for Restoration and assessing tangible and IDA / 56950 Post Direct Selection Direct 15,400.00 41,127.33 Completed 2017-01-18 2017-01-19 2017-02-01 2017-02-18 2017-03-29 2017-04-07 2017-05-13 2017-06-10 strengthening of livelihoods intangible heritage value of Building at Silk Factory Rajbagh Srinagar. JTFRP/JK/IC/CDI/CSPEP/C002 /16 / Individual Consultant for curriculum, course material development and It equipment for CDIs PG Individual Restoration and programs in Craft Design and IDA / 56950 Post Consultant Limited 23,000.00 0.00 Canceled 2017-01-05 2017-01-05 2017-01-10 2017-01-15 2017-01-31 2017-03-07 2017-09-03 strengthening of livelihoods sustainable development in Selection creative industries Under JTFRP for restoration and Strengthening of Livelihoods at CDI Sgr. JTFRP/JK/IC/RB/C002/17 / Consultancy for Technical Individual assistance in sourcing Restoration and IDA / 56950 Post Consultant Limited 15,400.00 4,706.07 Signed 2017-03-06 2017-04-06 2017-03-13 2017-05-05 2017-04-03 2017-06-06 2017-05-08 2017-06-20 2017-06-12 machines and Equipments for strengthening of livelihoods Selection Silk Factory Rajbagh and Bemina Woolen Mills Srinagar. JTFRP/JK/IC/JKI/BD/C003 / Consultancy for providing Restoration and retail Design of show rooms IDA / 56950 Post Direct Selection Direct 23,000.00 69,319.56 Signed 2017-04-06 2017-03-01 2017-04-16 2017-04-14 2017-06-20 2017-06-20 2018-12-20 strengthening of livelihoods at Bemina Woolen Mills and Dehli Show room under JTFRP . JTFRP/JK/IC/JKI/R/B/C002/17 / Consultancy for Technical Assistance in sourcing Individual Restoration and machines and equipments for IDA / 56950 Post Consultant Open 15,400.00 0.00 Canceled 2017-02-20 2017-04-01 2017-04-12 2017-05-03 2017-06-07 strengthening of livelihoods Silk factory RajBagh and Selection Bemina Woolen Mills Srinagar. JTFRP/JK/IC/HD/C004/17 / Consultancy services of Domain Expert towards the Restoration and IDA / 56950 Post Direct Selection Direct 461,500.00 340,042.11 Signed 2018-02-05 2018-02-05 2018-02-15 2018-02-08 2018-04-21 2018-07-25 2020-11-09 development of Crewel strengthening of livelihoods Chainstitch Cluster at Noor Bagh. JTFRP/JK/IC/HD/CD-PM- C004-18 / Consultancy Restoration and services for development of IDA / 56950 Post Direct Selection Direct 461,500.00 309,975.39 Signed 2018-04-18 2018-04-18 2018-04-28 2018-04-23 2018-05-21 2018-07-25 2020-05-31 strengthening of livelihoods Papier Machie Cluster at Zadibal Srinagar JTFRP/JK/IC/JKI/CRB001/18 / Consultancy for Technical Assistance and Project Supervision for Various Restoration and IDA / 56950 Post Direct Selection Direct 33,900.00 24,213.75 Signed 2018-07-31 2017-12-11 2018-08-06 2018-04-10 2018-10-10 2018-07-31 2019-04-08 Building Works Identified strengthening of livelihoods Under The Livelihood Component of Jehlum Tawi Floor Recovery Project JTFRP/JK/IC/HD/ITC/C006/18 / Consultancy services for feasibility study of site and Restoration and IDA / 56950 Post Direct Selection Direct 77,000.00 0.00 Canceled 2018-10-17 2018-10-27 2018-12-31 2019-06-29 working model for Kashmir strengthening of livelihoods Haat and International Trade Centre Pampore JK Page 5 JTFRP/JK/IC/SOL/C001/19 / Consultancy services for Restoration and Under adaptive reuse of Solina IDA / 56950 Prior Direct Selection Direct 357,000.00 0.00 2019-12-16 2020-10-10 2019-12-26 2020-01-10 2020-02-29 2020-08-27 strengthening of livelihoods Implementation Filatures as Arts, Culture and Crafts Centre JTFRP/JK/IC/DS/S/C001/20 / Consultancy services for undertaking a comprehensive study to determine the requirements and Restoration and Under specifications of machinery, IDA / 56950 Post Direct Selection Direct 15,750.00 0.00 2020-07-21 2020-08-18 2020-07-31 2020-10-04 2021-04-02 strengthening of livelihoods Implementation allied equipment and facilities for the existing Common Facility Centre(CFC) and formulate Quality Control and Testing benchmarks for JTFRP/JK/IC/DS/S/C002/20 / Consultancy services for Survey, Collection and Multiplication of superior Cricket Bat Willow (Salix Alba Restoration and Under IDA / 56950 Post Direct Selection Direct 128,500.00 0.00 2020-07-21 2020-08-18 2020-07-31 2020-10-04 2021-04-02 var. Caerulea) germplasm for strengthening of livelihoods Implementation livelihood security of farmers and economic sustainability of Cricket Bat Industry of Kashmir Page 6 FEDERAL REPUBLIC OF NIGERIA 18-Months Procurement Plan General: Project Information: Nigeria; REDISSE; P159040. Project Implementation Agency: Nigeria Centre for Disease Control (NCDC) Date of the Procurement Plan: April 2018 Period covered by this Procurement Plan: April 2018 - November, 2019 I. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers”, July 2016 (Revised November 2017) (“Procurement Regulations”), the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. II. Bank’s Standard Procurement Documents: The Bank’s Standard Procurement Documents shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. III. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Nigeria Public Procurement Act 2007 and the Regulations, 2016, such arrangements shall be subject to paragraph 5.3 and 5.4 of the Procurement Regulations and the following conditions: o There should be no mandatory requirements for inclusion of local experts and firms for the consulting assignments; o There should be no exclusive preference based on threshold prescribed in PPA and credit and its Regulations; o Negotiations with the lowest evaluated bidder to reduce price in the case of goods, works and non-consulting services where competitive methods have been used shall not be allowed; 1 o The fixed budget method shall not be used for goods, works and non- consulting services; o Established and approved procurement standards by the government may be used, provided that they are not restrictive When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. In accordance with paragraph 5.4(c) and 5.5 of the Procurement Regulations, the request for bids/request for proposals/request for quotations document shall require that Bidders/Proposers submitting Bids/Proposals/quotations present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. The form of the Letter of Acceptance is attached in Appendix 1. IV. Prequalification: Applicable (May be applicable at the Federal for high value Consultant Assignments V. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable VI. Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations: Not Applicable VII. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Not Applicable Domestic preference is not applicable for National Open Competitive Procurement VIII. Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is: Not Applicable IX. Other Relevant Procurement Information: Not Applicable 2 3 X. Threshold for Prior Review, Procurement Approaches and Methods – Goods, Works and Non- Consulting Services Procurement Approaches and Methods (US$ millions) Category Open Open National Request for Quotation International (RfQ) Works, Turnkey, and ≥5 <5 ≤ 0.2 S&I of Plant and Equipment Goods, IT, and non- ≥5 <0.5 ≤ 0.1 consulting services Post Review: All contracts not subject to prior review shall be subject to post review. XI. Summary of the procurement packages for Goods, Works and Non-Consulting Services: Sr. Contract Implem Estima Revie Market Selecti Evaluati Procurem Prequ Domesti Expect Expect No Description enting ted w by Approa on on ent alifica c ed ed date Agency Cost Bank ch Metho Options Process tion Prefere date of (US$) (Prior (Open- d (Most (Single (Yes/ nce of bid/ Contra / Nationa (RFP, Advanta stage- No) (Yes/No propo ct Post) l/ RFB, geous single ) sal Signat Limited RFQ, Bid, envelope openin ure etc.) DS BAFO, etc.) g etc.) Rated Criteria etc.) GOODS 1 Procureme NCDC 3,579,1 Post Open, RFB Most Single No No 08-10- 22-10-18 nt of (AH & 39 National Advanta stage- 18 Vehicles HH) geous single (12 Nos. Bid envelope 4WD DC; 6Nos. 4WD Veterinary Ambulatory vehicle; 4 Nos. 4WD 4 SUVs; 1No. 20Tonnes Truck; 75 Motorcycle and 175 Tricycle 2 Procureme NCDC 198,162 Post Open, RFB Most Single No No 20-03- 10-04-19 nt of Office (AH) National Advanta stage- 19 Equipment geous single & Furniture Bid envelope for 37 state Vet. Public Health /Epidemiolo gy Offices 3 Procureme NCDC 97,377 Post Limited RfQ Rated Single No No 17-09- 01-10-18 nt of (AH) Criteria envelope 18 Laptops and Internet Modem for Surveillanc e activities & Non- Android Phones for animal disease informants 4 Procureme NCDC 926,423 Post Open, RFB Most Single No No 08-10- 22-10-18 nt of Lab. (HH) National Advanta envelope 18 Equipt. , geous Reagents & Bid Consumabl es and Biosecurity Materials (4Lots) 5 Procureme NCDC 295,082 Prior DIR DIR Direct Single No No Nov. Nov. nt of (AH) Selection envelope 2018 2021 5 50000/Vial of ARV Vaccine 6 Procureme NCDC 1,067,8 Post Open, RFB Most Single No No 08-10- 22-10-18 nt of (AH 68 National Advanta envelope 18 Veterinary &HH) geous Stockpiles Bid for preventabl e Zoonotic diseases (AH ) & Consumabl e for HEPR Stockpiling (HH) -2 Lots 7 Procureme NCDC 45,015 Post Limited RfQ Rated Single No No 17-09- 01-10-18 nt of Office (AH) Criteria envelope 18 Furniture/E quipment for Crises Manageme nt Centre (AH) 8 Supply of NCDC 75,374 Post Limited RfQ Rated Single No No 17-09- 01-10-18 Office (AH) Criteria envelope 18 Furniture and Equipment for REDISSE Animal Health Component Office (AH) 9 Printing of NCDC 146,787 Post Limited RfQ Rated Single No No 31-10- 14-11-18 IDSR (HH) Criteria envelope 18 Guideline 10 Printing of NCDC 200,164 Post Limited RfQ Rated Single No No 31-10- 14-11-18 IDSR Tools (HH) Criteria envelope 18 6 (Forms 001,002, 003) 11 Printing of NCDC 36,393 Post Limited RfQ Rated Single No No 31-10- 14-11-18 IDSR Policy (HH) Criteria envelope 18 12 Procureme NCDC 819,672 Post Open, RFB Most Single No No 08-10- 22-10-18 nt of (HH) National Advanta envelope 18 Emergency geous Laboratory Bid reagents and consumable s for NRL/CPHL 13 Procureme NCDC 606,557 Post Open, RFB Most Single No No 08-10- 22-10-18 nt of (HH) National Advanta envelope 18 Consumabl geous e and IPC Bid Materials (HH) 14 Supply of NCDC 68,508 Post Limited RfQ Most Single No No 17-09- 01-10-18 Office (HH) Advanta envelope 18 Furniture geous and Bid Equipment for REDISSE PCU Office - (HH) 15 Procureme NCDC 57,172 Post Limited RfQ Rated Single No No 31-10- 14-11-18 nt of Tabs (HH) Criteria envelope 18 (80), Laptops (35) and 2GB/Month USB Internet Service for step-down training for IDSR for HH 7 16 Supply and NCDC 98,361 Post Limited RfQ Rated Single No No 17-09- 01-10-18 Installation (HH) Criteria envelope 18 of 250 KVA Gen. Set and 20 KVAs Solar Panels and Inverters for REDISSE PCU's Office Total Goods 8,318, 954 WORKS 17 Rehabilitati NCDC 110,16 Post Limited RfQ Rated Single No No 21-01- 04-02-19 on of 7 Nos (AH) 4 Criteria envelope 19 State Veterinary Public Health/Epid emiology offices - NW ZONE ( Kaduna, Katsina, Kano, Jigawa,Keb bi, Zamfara & Sokoto) 18 Rehabilitati NCDC 94,426 Post Limited RfQ Rated Single No No 21-01- 04-02-19 on of 6 Nos. (AH) Criteria envelope 19 State Veterinary Public Health/Epid emiology offices- NE ZONE (Bauchi, Borno, 8 Yobe, Adamawa, Gombe & Taraba) 19 Rehabilitati NCDC 110,16 Post Limited RfQ Rated Single No No 21-01- 04-02-19 on of 7 Nos (AH) 4 Criteria envelope 19 State Veterinary Public Health/Epid emiology offices - NC ZONE ( Plateau, Nasarawa, Benue, Niger, Kogi, Kwara & FCT) 20 Rehabilitati NCDC 94,426 Limited Limited RfQ Rated Single No No 21-01- 04-02-19 on of 6 Nos. (AH) Criteria envelope 19 State Veterinary Public Health/Epid emiology offices - SW ZONE (Osun, Oyo, Ogun, Ondo, Lagos & Ekiti) 21 Rehabilitati NCDC 94,426 Limited Limited RfQ Rated Single No No 21-01- 04-02-19 on of 6 Nos. (AH) Criteria envelope 19 State Veterinary Public Health/Epid emiology 9 offices - SS ZONE ( Edo, Delta, Bayelsa, Rivers, Cross- Rivers & Akwa-Ibom) 22 Rehabilitati NCDC 78,688 Post Limited RfQ Rated Single No No 21-01- 04-02-19 on of 5 Nos. (AH) Criteria envelope 19 State Veterinary Public Health/Epid emiology offices - SE ZONE ( Enugu, Ebonyi, Imo, Anambra & Abia) 23 Refurbishm NCDC 75,374 Post Limited RfQ Rated Single No No 21-01- 04-02-19 ent of (HH) Criteria envelope 19 REDISSE Animal Health component office at Headquarte r 24 Renovation NCDC 114,75 Post Limited RfQ Rated Single No No 21-01- 04-02-19 and (HH) 4 Criteria envelope 19 upgrade of 7 Nos. Isolation Centers in NW ZONE ( Kaduna, Katsina, 10 Kano, Jigawa, Kebbi, Zamfara & Sokoto) 25 Renovation NCDC 98,360 Post Limited RfQ Rated Single No No 21-01- 04-02-19 and (HH) Criteria envelope 19 upgrade of 6 Nos. Isolation Centers in NE ZONE (Bauchi, Borno, Yobe, Adamawa, Gombe & Taraba) 26 Renovation NCDC 114,75 Post Limited RfQ Rated Single No No 21-01- 04-02-19 and (HH) 4 Criteria envelope 19 upgrade of 7 Nos. Isolation Centers in NC ZONE ( Plateau, Nasarawa, Benue, Niger, Kogi, Kwara & FCT) 27 Renovation NCDC 98,360 Post Limited RfQ Rated Single No No 21-01- 04-02-19 and (HH) Criteria envelope 19 upgrade of 6 Nos. Isolation Centers in SW ZONE (Osun, Oyo, Ogun, 11 Ondo, Lagos & Ekiti) 28 Renovation NCDC 98,360 Post Limited RfQ Rated Single No No 21-01- 04-02-19 and (HH) Criteria envelope 19 upgrade of 6 Nos. Isolation Centers in SS ZONE ( Edo, Delta, Bayelsa, Rivers, Cross- Rivers & Akwa-Ibom) 29 Renovation NCDC 81,967 Post Limited RfQ Rated Single No No 21-01- 04-02-19 and (HH) Criteria envelope 19 upgrade of 5 Nos. Isolation Centres in SE ZONE ( Enugu, Ebonyi, Imo, Anambra & Abia) 30 Supply and NCDC 606,55 Post Open, RFB Most Single No No 04-03- 25-03-19 Installation (HH) 7 National Advanta envelope 19 of 1No. geous Incinerator Bid in a selected facilty in each of the six geopolitical zones Total works 1,870, 780 12 NON-CONSULTING SERVICES 31 Registration NCDC (AH) 20,492 Post Limited RfQ Rated Single No No 18-12- 02-10-19 of Criteria envelope 18 motorcycles (75 Nos. ) and tricycle (175 Nos.) for AH 32 Registration NCDC (AH) 266,437 Post Limited RfQ Rated Single No No 18-12- 02-10-19 and Insurance Criteria envelope 18 for 9 Nos. 4WD DC vehicles; 2 Nos. 15- Seater Bus; 6 Nos. 4WD Vet. Ambulatory vehicle; 2 Nos. SUVs; and 1No. 20Tonne Truck for AH 33 Registration NCDC 93,098 Post Limited RfQ Rated Single No No 18-12- 02-10-19 and Insurance (HH) Criteria envelope 18 for 3 Nos. 4WD DC vehicles; 2 Nos. SUVs for HH 34 Installation of NCDC 4,049 Post Limited RfQ Rated Single No No 18-12- 02-10-19 tracking (AH) Criteria envelope 18 systems in 9 Nos. 4WD DC vehicles; 2 Nos. 15- Seater Bus; 6 Nos. 4WD Vet. Ambulatory vehicle; 2 Nos. SUV for AH 35 Installation of NCDC 1,066 Post Limited RfQ Rated Single No No 18-12- 02-10-19 tracking (HH) Criteria envelope 18 systems in 3 Nos. 4WD DC vehicles; 2 Nos. SUV for HH 36 Support for NCDC 16,393 Post Limited RfQ Rated Single No No 18-12- 02-10-19 Distribution of (AH) 18 13 Office logistic Criteria envelope and Lab. Materials to 37 state, NVRI and 10 VTHs 37 Procurement NCDC 142,043 Post Limited RfQ Rated Single No No 18-12- 02-10-19 of courier (HH) Criteria envelope 18 service logistics for specimen transportation and pre- positioning of supplies 38 Recruitment NCDC 45,246 Post Limited RfQ Rated Single No No 17-09- 01-10-18 of 17 (AH) Criteria envelope 18 contract/ad hoc staff (AH) Total Non- 588,82 Consulting 5 Services Note: Based on Liberia’s specific needs and circumstances, shopping threshold for the purchase of vehicles and fuel may be increased up to US$500,000. Thresholds for Prior Review, Selection Approaches and Methods – Consulting Services Category Prior Review Short List of National Consultants (US$ millions) Consulting Engineering and Construction Supervision Services Consultants (Firms) ≥ 0.5 ≤ 0.1 ≤ 0.2 Individual Consultants ≥ 0.2 n.a. n.a. Note: Consultancy services estimated to cost equivalent to US$ 300,000 and above per contract shall be advertised in the United Nations Development Business (UNDB) online in addition to advertising in national newspaper(s) of wide circulation and/or regional newspaper. XI. Summary of the procurement packages for Consulting Services -Planned for the first 18 months after project effectiveness): 14 Sr. Contract Implem Estimat Revie Market Selection Shortlist Expected Expected No Description enting ed Cost w by Approach Method ing date of date of Agency (US$) Bank (Open - (QCBS, (Yes/ No) bid/ Contract (Prior/ Internation FBS, LCBS, proposal Signature Post) al/ QBS, CQS, opening National/ DS etc.) etc.) 39 Engagement of NCDC 7,026 Post Limited INDV No 15-10-18 29-10-18 Individual Consultants from relevant Sectors to develop a National Strategy for ONE Health and Workforce strategy 40 Recruitment of NCDC 201,836 Prior Open, INDV No 01-10-18 15-10-18 3 Consultants National to support for 12 months to facilitate NCDC-FETP training and lead redesign of the FETP programme 41 Engagement of NCDC 243,934 Prior Open, INDV No 01-10-18 22-10-18 5 Consultants/ National Specialists in relevant Thematic Areas to support Project Implementatio n 42 Consultancy NCDC 197,871 Post Open, CQS No 15-10-18 29-10-18 for Branding National and corporate 15 communication including development of risk communication strategies for the REDISSE project 43 Consultancy to NCDC 66,953 Post Open, CQS No 15-10-18 29-10-18 develop project National website and project intranet including overhaul and upgrade of NCDC website and development of REDISSE webpages 44 Consultancy NCDC 177,540 Post Open, CQS No 18-03-19 01-04-19 for National Establishing, developing, training, and licensing enterprise management of software for Procurement, Audit and Financial management 45 Engagement of NCDC 11,689 Post Limited INDV No 15-10-18 29-10-18 a Consultant to provide Safeguard, Waste Management 16 and Grievance Support 46 Engagement of NCDC 9,797 Post Limited INDV No 20-02-19 06-03-19 2 Individual Consultants to conduct situational analysis and develop a road map for development of laboratory standards 47 Consultancy to NCDC 80,343 Post Open, CQS No 20-02-19 06-03-19 conduct Needs National assessment and consensus building for human and animal health information systems to develop a plan and road map for an interconnected real-time system for human and animal health including a development of a technical plan data systems integration 48 Consultancy NCDC 106,749 Post Open, CQS No 17-04-19 02-05-19 for a National National Public Health Laboratory 17 Needs Assessment 49 Consultancy to NCDC 7,065 post Limited INDV No 20-02-19 06-03-19 develop strategy and training modules on shipment of samples for diagnosis of) zoonotic and epidemic prone diseases 50 Consultancy NCDC 180,343 Post Open, CQS No 17-04-19 02-05-19 for the National assessment of isolation units in all the state capitals in the country to identify gaps compared to global best practice and develop minimum standards for isolation practice 51 Consultancy NCDC 78,220 Post Open, CQS No 17-04-19 02-05-19 for Situational National Analysis and Development of a Multi- hazard Plans 52 Consultancy to NCDC 71,555 Post Open, CQS No 17-04-19 02-05-19 conduct gap National analysis of the existing surveillance 18 system for Transboundary Animal Diseases and zoonotic diseases 53 Consultancy to NCDC 48,355 Post Limited INDV No 15-11-18 29-11-18 conduct the prioritization of TADs and zoonotic diseases. Review and update priority animal diseases TADs 54 Consultancy to NCDC 64,575 Post Open, CQS No 17-04-19 02-05-19 harmonize and National develop guidelines, protocols and tools for animal disease surveillance and disease reporting processes 55 Consultancy to NCDC 14,942 Post Limited INDV No 17-04-19 02-05-19 develop training manual for Surveillance Agents (AH) 56 Consultancy to NCDC 24,104 Post Limited INDV No 17-04-19 02-05-19 identify and develop the GIS Mapping of Hot-spots in human, Wild and Domestic 19 animals interface(AH) 57 Engagement of NCDC 196,721 Post Open, INDV No 15-10-18 29-10-18 25 National Veterinarians as ad hoc staff (AH) 58 Engagement of NCDC 61,967 Post Open, INDV No 15-10-18 29-10-18 10 ad-hoc National Laboratory Scientists at NRL (HH) 59 Consultancy NCDC 56,429 Post Open, CQS No 14-11-18 28-11-18 for re- National assessment of 37 Veterinary Public Health/ Epidemiology offices, preparation of BOQs and Supervision of Rehabilitation 60 Consultancy NCDC 60,656 Post Open, CQS No 14-11-18 28-11-18 for re- National assessment of 37 Isolation Centers, preparation of BOQs and Supervision of renovation Total Consultancy 1,968,6 Services 70 20 Appendix 1 Letter of Acceptance of the World Bank’s Anti-Corruption Guidelines and Sanctions Framework Date: Invitation of Bids/Proposals No.__________ To: ___________________________________________________________________________ We, along with our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not) consultants and personnel, acknowledge and agree to abide by the World Bank’s policy regarding Fraud and Corruption (corrupt, fraudulent, collusive, coercive, and obstructive practices), as set out and defined in the World Bank’s Anti-Corruption Guidelines1 in connection with the procurement and execution of the contract (in case of award), including any amendments thereto. We declare and warrant that we, along our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not), consultants and personnel, , are not subject to, and are not controlled by any entity or individual that is subject to, a temporary suspension, early temporary suspension, or debarment imposed by a member of the World Bank Group, including, inter alia, a cross-debarment imposed by the World Bank Group as agreed with other international financial institutions (including multilateral development banks), or through the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement. Further, we are not ineligible under the laws or official regulations of [Insert name of Employer as per bidding document] or pursuant to a decision of the United Nations Security Council. We confirm our understanding of the consequences of not complying with the World Bank’s Anti-Corruption Guidelines, which may include the following: a. rejection of our Proposal/Bid for award of contract; b. in the case of award, termination of the contract, without prejudice to any other remedy for breach of contract; and c. sanctions, pursuant to the Bank’s Anti-corruption Guidelines and in accordance with its prevailing sanctions policies and procedures as set forth in the Bank’s Sanctions Framework. This may include a public declaration of ineligibility, either indefinitely or for a stated period of time, (i) to be awarded or otherwise benefit from a Bank- financed contract, financially or in any other manner;2 (ii) to be a nominated3 sub- 1Guidelines on Preventing and Combating Fraud and Corruption in Projects Financed by International Bank for Reconstruction and Development Loans and the International Development Agency Credits and Grants, dated October 15, 2006, and revised in January 2011 and July 2016, as they may be revised from time to time. 2 For the avoidance of doubt, a sanctioned party’s ineligibility to be awarded a contract shall include, without limitation, (i) applying for pre-qualification, expressing interest in a consultancy, and bidding, either directly or as a nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider, in respect of such contract, and (ii) entering into an addendum or amendment introducing a material modification to any existing contract. 21 contractor, consultant, manufacturer or supplier, or service provider of an otherwise eligible firm being awarded a Bank-financed contract; and (iii) to receive the proceeds of any loan made by the Bank or otherwise to participate further in the preparation or implementation of any Bank-financed project. We understand that we may be declared ineligible as set out above upon: a. completion of World Bank Group sanctions proceedings according to its prevailing sanctions procedures; b. cross-debarment as agreed with other international financial institutions (including multilateral development banks); c. the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement; or d. temporary suspension or early temporary suspension in connection with an ongoing World Bank Group sanctions proceeding. For avoidance of doubt, the foregoing effects of ineligibility do not extend to a sanctioned firm’s or individual’s execution of its ongoing Bank-financed contracts (or its ongoing sub-agreements under such contracts) that are not the subject of a material modification, as determined by the Bank. We shall permit, and shall cause our sub-contractors, sub-consultants, agents (whether declared or not), personnel, consultants, service providers or suppliers, to permit the Bank to inspect4 all accounts, records, and other documents relating to the procurement process and/or contract execution (in the case of award), and to have them audited by auditors appointed by the Bank. We agree to preserve all accounts, records, and other documents (whether in hard copy or electronic format) related to the procurement and execution of the contract. Name of the Bidder/Consultant: Name of the person duly authorized to sign the Bid/Proposal on behalf of the Bidder/Consultant: 3 A nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider (different names are used depending on the particular bidding document) is one which has been: (i) included by the bidder in its pre-qualification application or bid because it brings specific and critical experience and know-how that allow the bidder to meet the qualification requirements for the particular bid; or (ii) appointed by the Borrower. 4 Inspections in this context are usually investigative (i.e., forensic) in nature: they involve fact-finding activities undertaken by the Bank or persons appointed by the Bank to address specific matters related to investigations/audits, such as evaluating the veracity of an allegation of possible Fraud and Corruption, through the appropriate mechanisms. Such activity includes but is not limited to accessing and examining a firm's or individual's financial records and information, and making copies thereof as relevant; accessing and examining any other documents, data, and information (whether in hard copy or electronic format) deemed relevant for the investigation/audit, and making copies thereof as relevant; interviewing staff and other relevant individuals; performing physical inspections and site visits; and obtaining third-party verification of information. 22 Title of the person signing the Letter: 23 PROCUREMENT Western Africa : Regional Disease Surveillance Systems Enhancement (REDISSE) Phase II PLAN General Information Country: Western Africa Bank’s Approval Date of the Original Procurement Plan: 2018-11-20 2021-05-18 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P159040 GPN Date: Project Name: Regional Disease Surveillance Systems Enhancement (REDISSE) Phase II Loan / Credit No: IDA / 59700 Nigeria Centre for Disease Control Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned REDISSE-CW-RFQ-01 / Rehabilitation of 7 Nos State Veterinary Public Component 1: Surveillance Request for Single Stage - One 2019-08- Health/Epidemiology offices - IDA / 59700 Post Limited 110,164.00 0.00 Canceled 2018-12-25 2019-02-19 and Information Systems Quotations Envelope 18 NW ZONE ( Kaduna, Katsina, Kano, Jigawa,Kebbi, Zamfara & Sokoto) REDISSE-CW-RFQ-02 / Rehabilitation of 6 Nos. State Veterinary Public Component 1: Surveillance Request for Single Stage - One 2019-08- IDA / 59700 Post Limited 94,426.00 0.00 Canceled 2018-12-25 2019-02-19 Health/Epidemiology offices- and Information Systems Quotations Envelope 18 NE ZONE (Bauchi, Borno, Yobe, Adamawa, Gombe & Taraba) REDISSE-CW-RFQ-03 / Rehabilitation of 7 Nos State Veterinary Public Component 1: Surveillance Request for Single Stage - One 2019-08- Health/Epidemiology offices - IDA / 59700 Post Limited 110,164.00 0.00 Canceled 2018-12-25 2019-02-19 and Information Systems Quotations Envelope 18 NC ZONE ( Plateau, Nasarawa, Benue, Niger, Kogi, Kwara & FCT) REDISSE-CW-RFQ-04 / Rehabilitation of 6 Nos. State Veterinary Public Component 1: Surveillance Request for Single Stage - One 2019-08- IDA / 59700 Post Limited 94,426.00 0.00 Canceled 2018-12-25 2019-02-19 Health/Epidemiology offices - and Information Systems Quotations Envelope 18 SW ZONE (Osun, Oyo, Ogun, Ondo, Lagos & Ekiti) REDISSE-CW-RFQ-05 / Rehabilitation of 6 Nos. State Veterinary Public Component 1: Surveillance Request for Single Stage - One 2019-08- Health/Epidemiology offices - IDA / 59700 Post Open - National 94,426.00 0.00 Canceled 2018-12-25 2019-02-19 and Information Systems Quotations Envelope 18 SS ZONE ( Edo, Delta, Bayelsa, Rivers, Cross-Rivers & Akwa- Ibom) REDISSE-CW-RFQ-06 / Rehabilitation of 5 Nos. State Veterinary Public Component 1: Surveillance Request for Single Stage - One 2019-08- IDA / 59700 Post Limited 78,689.00 0.00 Canceled 2018-12-25 2019-02-19 Health/Epidemiology offices - and Information Systems Quotations Envelope 18 SE ZONE ( Enugu, Ebonyi, Imo, Anambra & Abia) REDISSE-CW-RFQ-07F / Component 5: Institutional Pending Refurbishment of REDISSE Capacity Building, Project Request for Single Stage - One 2019-08- IDA / 59700 Post Limited 24,742.00 0.00 Implementat 2018-12-25 2019-02-19 Animal Health component Management, Coordination Quotations Envelope 18 ion office at Headquarter and Advocacy REDISSE-CW-RFQ-08 / Renovation and upgrade of 7 Nos. Isolation Centres in NW Component 3: Preparedness Request for Single Stage - One 2019-08- IDA / 59700 Post Limited 126,230.00 0.00 Canceled 2018-12-25 2019-02-19 ZONE ( Kaduna, Katsina, Kano, and Emergency Response Quotations Envelope 18 Jigawa,Kebbi, Zamfara & Sokoto) REDISSE-CW-RFQ-09 / Renovation and upgrade of 6 Component 3: Preparedness Request for Single Stage - One 2019-08- Nos. Isolation Centres in NE IDA / 59700 Post Limited 108,197.00 0.00 Canceled 2018-12-25 2019-02-19 and Emergency Response Quotations Envelope 18 ZONE (Bauchi, Borno, Yobe, Adamawa, Gombe & Taraba) REDISSE-CW-RFQ-10 / Renovation and upgrade of 7 Nos. Isolation Centres in NC Component 3: Preparedness Request for Single Stage - One 2019-08- IDA / 59700 Post Limited 126,230.00 0.00 Canceled 2018-12-25 2019-02-19 ZONE ( Plateau, Nasarawa, and Emergency Response Quotations Envelope 18 Benue, Niger, Kogi, Kwara & FCT) REDISSE-CW-RFQ-11 / Renovation and upgrade of 6 Component 3: Preparedness Request for Single Stage - One 2019-08- Nos. Isolation Centres in SW IDA / 59700 Post Limited 108,197.00 0.00 Canceled 2018-12-25 2019-02-19 and Emergency Response Quotations Envelope 18 ZONE (Osun, Oyo, Ogun, Ondo, Lagos & Ekiti) REDISSE-CW-RFQ-12 / Renovation and upgrade of 6 Nos. Isolation Centres in SS Component 3: Preparedness Request for Single Stage - One 2019-08- IDA / 59700 Post Open - National 108,197.00 0.00 Canceled 2018-12-25 2019-02-19 ZONE ( Edo, Delta, Bayelsa, and Emergency Response Quotations Envelope 18 Rivers, Cross-Rivers & Akwa- Ibom) REDISSE-CW-RFQ-13 / Renovation and upgrade of 6 Nos. Isolation Centres in SS Component 3: Preparedness Request for Single Stage - One 2019-08- IDA / 59700 Post Limited 108,197.00 0.00 Canceled 2018-12-25 2019-02-19 ZONE ( Edo, Delta, Bayelsa, and Emergency Response Quotations Envelope 18 Rivers, Cross Rivers and Akwa Ibom) - HH REDISE-CW-RFQ-14 / Component 5: Institutional Pending Refurbishment of Redisse Capacity Building, Project Request for Single Stage - One 2019-07- IDA / 59700 Post Limited 24,742.00 0.00 Implementat 2018-12-03 2019-01-28 Animal Health Component Management, Coordination Quotations Envelope 27 ion Oficce at Headquarter and Advocacy Page 1 Component 5: Institutional REDISSE-CW-RFQ-15 / Office Capacity Building, Project Request for Single Stage - One 2019-11- partitioning REDISSE PCU IDA / 59700 Post Limited 10,557.38 9,320.47 Completed 2019-03-11 2019-02-25 2019-05-06 2019-03-04 Management, Coordination Quotations Envelope 02 Office and Advocacy REDISSE-CW-RFQ-01-2020 / Component 5: Institutional Pending Rehabilitate 36 State office Capacity Building, Project Request for Single Stage - One 2021-07- IDA / 59700 Post Limited 1,496,843.00 0.00 Implementat 2020-11-23 2021-01-18 accommodation and FCT (6 Management, Coordination Quotations Envelope 17 ion LOTS) and Advocacy GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual REDISSE-GDS-RFB-02 / Procurement of Office Component 1: Surveillance Single Stage - One Equipment & Furniture for 37 IDA / 59700 Post Request for Bids Open - National 146,787.00 0.00 Canceled 2018-10-16 2018-10-21 2018-12-02 2019-01-01 2019-02-05 2019-08-04 and Information Systems Envelope state Vet. Public Health /Epidimeology Offices REDISSE-GDS-RFQ-01 / Procurement of Laptops and Internet Modem etc for Component 1: Surveillance Request for Single Stage - One IDA / 59700 Post Limited 110,738.00 0.00 Canceled 2018-08-04 2018-09-29 2019-03-28 Surveillance activities & Non- and Information Systems Quotations Envelope Android Phones for animal disease informants REDISSE-GDS-RFB-04 / Procurement of Vetinary Stockpiles for preventable Component 3: Preparedness Single Stage - One IDA / 59700 Post Request for Bids Open - National 994,099.00 508,823.27 Signed 2018-10-16 2019-10-18 2018-10-21 2018-12-02 2019-11-18 2019-01-01 2020-01-03 2019-02-05 2020-01-27 2019-08-04 2020-07-01 Zoonotic diseases (AH ) & and Emergency Response Envelope Consumable for HEPR Stockpiling (HH) -2 Lots REDISSE-GDS-RFQ-3 / Procurement of Office Pending Component 3: Preparedness Request for Single Stage - One Furniture/Equipment for IDA / 59700 Post Limited 41,896.00 0.00 Implementati 2018-10-14 2018-12-09 2019-06-07 and Emergency Response Quotations Envelope Crises Management Centre on (AH) REDISSE-GDS-RFQ-04 / Component 5: Institutional Pending Supply of Office Furniture and Capacity Building, Project Request for Single Stage - One IDA / 59700 Post Limited 33,144.00 0.00 Implementati 2018-10-14 2018-12-09 2019-06-07 Equipment for REDISSE Animal Management, Coordination Quotations Envelope on Health Component Office and Advocacy REDISSE-GDS-RFQ-05 / Component 1: Surveillance Request for Single Stage - One IDA / 59700 Post Limited 146,787.00 0.00 Canceled 2018-11-20 2019-01-15 2019-07-14 Printing of IDSR Guideline and Information Systems Quotations Envelope REDISSE-GDS-RFQ-06 / Component 1: Surveillance Request for Single Stage - One Printing of IDSR Tools (Forms IDA / 59700 Post Limited 200,164.00 0.00 Canceled 2018-11-20 2019-01-15 2019-07-14 and Information Systems Quotations Envelope 001,002, 003) REDISSE-GDS-RFQ-07 / Component 1: Surveillance Request for Single Stage - One IDA / 59700 Post Limited 36,393.00 0.00 Canceled 2018-11-20 2019-01-15 2019-07-14 Printing of IDSR Policy and Information Systems Quotations Envelope REDISSE-GDS-RFB-05 / Pending Procurement of Emergency Component 2: Strengthening Single Stage - One IDA / 59700 Post Request for Bids Open - National 819,672.00 0.00 Implementati 2018-10-16 2018-10-21 2018-12-02 2019-01-01 2019-02-05 2019-08-04 Laboratory reagents and of Laboratory Capacity Envelope on consummables for NRL/CPHL REDISSE-GDS-RFB-06 / Supply and Installation of 6 Component 3: Preparedness Single Stage - One IDA / 59700 Post Request for Bids Open - National 590,164.00 0.00 Canceled 2018-11-07 2018-11-12 2018-12-24 2019-01-23 2019-02-27 2019-08-26 Incinerators in one facility of and Emergency Response Envelope each of the geopolical zone REDISSE-GDS-RFB-07 / Pending Component 3: Preparedness Single Stage - One Procurement of Consummable IDA / 59700 Post Request for Bids Open - National 608,197.00 0.00 Implementati 2018-11-07 2018-11-12 2018-12-24 2019-01-23 2019-02-27 2019-08-26 and Emergency Response Envelope and IPC Materials (HH) on REDISSE-GDS-RFQ-09 / Procurement of Tabs (80), Component 1: Surveillance Request for Single Stage - One Laptops (35) and 2GB/Month IDA / 59700 Post Limited 57,172.00 0.00 Canceled 2018-10-14 2018-12-09 2019-06-07 and Information Systems Quotations Envelope USB Internet Service for step- down training for IDSR for HH REDISSE-GDS-RFQ-10 / Component 5: Institutional Supply and Installation od 250 Pending Capacity Building, Project Single Stage - One KVA Gen. Set and 20 KVAs IDA / 59700 Post Request for Bids Open - National 147,541.00 0.00 Implementati 2018-10-09 2018-10-14 2018-11-25 2018-12-25 2019-01-29 2019-07-28 Management, Coordination Envelope Solar Panels and Inverters for on and Advocacy REDISSE PCU's Office REDISSE-GDS-RFQ-16 / Component 5: Institutional Pending Support for fueling of vehicles Capacity Building, Project Request for Single Stage - One IDA / 59700 Post Limited 7,790.00 0.00 Implementati 2018-12-05 2019-01-30 2019-07-29 and generators (6600ltrs AGO Management, Coordination Quotations Envelope on & 6600 PMS) -AH and Advocacy Component 4: Human REDISSE-GDS-RFQ-17 / Pending Resource Management for Request for Single Stage - One Support for alternative source IDA / 59700 Post Limited 72,131.00 0.00 Implementati 2018-12-05 2019-01-30 2019-07-29 Effective Disease Surveillance Quotations Envelope of power -AH on and Epidemic Preparedness Component 5: Institutional REDISSE-GDS-RFQ-18 / Pending Capacity Building, Project Request for Single Stage - One Support for Office Supplies- IDA / 59700 Post Limited 26,097.00 0.00 Implementati 2018-12-05 2019-01-30 2019-07-29 Management, Coordination Quotations Envelope AH on and Advocacy REDISSE-GDS-RFB-01 / Procurement of Vehicles-12 Nos. 4WD DC, 6Nos. 4WD Pending Component 1: Surveillance Single Stage - One Ambulance, 4 Nos. 4WD IDA / 59700 Post Request for Bids Open - National 3,261,517.00 0.00 Implementati 2018-10-16 2018-10-21 2018-12-02 2019-01-01 2019-02-05 2019-08-04 and Information Systems Envelope SUVs, 75 Motorcycles and 175 on Tricycles and 2Nos. 15- seater bus - AH &HH REDISSE-GDS-DIR-1 / Pending Procurement of 200,000 Component 2: Strengthening IDA / 59700 Post Direct Selection Direct 295,082.00 0.00 Implementati 2019-01-16 2019-01-21 2019-02-25 2019-08-24 doses/vials of anti-rabies of Laboratory Capacity on vaccines (ARV) Page 2 REDISSE-GDS-RFQ-13 / Procurement of Equipment for Component 2: Strengthening Request for Single Stage - One IDA / 59700 Post Limited 139,036.99 119,502.36 Completed 2019-02-09 2019-03-08 2019-04-06 2019-06-17 2019-10-03 2019-09-17 Molecular Diagnostic of Laboratory Capacity Quotations Envelope Laboratory REDISSE-GDS-RFQ-14 / Procurement of Laboratory Component 2: Strengthening Request for Single Stage - One IDA / 59700 Post Limited 183,900.62 166,291.48 Completed 2019-02-09 2019-03-11 2019-04-06 2019-06-17 2019-10-03 2019-09-10 Reagents for LF Emergency of Laboratory Capacity Quotations Envelope Response REDISSE-GDS-RFQ-15 / Procurement of consumables Component 2: Strengthening Request for Single Stage - One IDA / 59700 Post Limited 92,694.42 59,391.08 Completed 2019-02-09 2019-03-12 2019-04-06 2019-06-17 2019-10-03 2019-10-10 for Rapid Diagnosis of Lassa of Laboratory Capacity Quotations Envelope Fever Emmergency Response NG-NCDC-98247-GO-RFQ / Printing of National Guidelines Component 3: Preparedness Request for Single Stage - One on Case Management of LF IDA / 59700 Post Limited 37,615.50 27,999.97 Completed 2019-02-09 2019-11-01 2019-04-06 2020-02-11 2019-10-03 2020-02-27 and Emergency Response Quotations Envelope and IPC for VHFs for the Lassa Fever Emergency Response NG-NCDC-98248-GO-RFQ / Procurement of Injectable Component 2: Strengthening Ribavirin for Lassa Fever IDA / 59700 Post Direct Selection Direct 459,177.05 386,075.88 Completed 2019-02-04 2019-01-21 2019-02-09 2019-01-21 2019-03-16 2019-01-31 2019-09-12 2019-02-04 of Laboratory Capacity Emergency Response (200mg/2ml) NG-NCDC-98250-GO-RFQ / Pending Procurement of Ribavirin Component 2: Strengthening Request for Single Stage - One IDA / 59700 Post Limited 24,786.88 0.00 Implementati 2019-02-09 2019-04-06 2019-10-03 Tablets for LF Emergency of Laboratory Capacity Quotations Envelope on Response Component 5: Institutional REDISSE-GDS-RFQ-08 / Capacity Building, Project Request for Single Stage - One Supply of Office Furniture for IDA / 59700 Post Limited 113,732.00 73,847.60 Completed 2019-03-16 2019-02-21 2019-05-11 2019-03-15 2019-11-07 2019-04-25 Management, Coordination Quotations Envelope REDISSE PCU Office-(HH) and Advocacy NG-NCDC-104619-GO-RFQ Component 5: Institutional / Office Equipment and IT Capacity Building, Project Request for Single Stage - One IDA / 59700 Post Limited 83,253.75 49,708.76 Signed 2019-03-16 2019-02-25 2019-05-11 2019-03-20 2019-11-07 2019-04-30 Equipment - REDISSE PCU Management, Coordination Quotations Envelope Office and Advocacy NG-NCDC-105950-GO-RFQ Component 5: Institutional Pending / Set up Project intranet Capacity Building, Project Request for Single Stage - One IDA / 59700 Post Limited 56,882.00 0.00 Implementati 2019-04-03 2019-05-29 2019-11-25 including overhaul and Management, Coordination Quotations Envelope on upgrade of NCDC website and Advocacy NG-NCDC-111659-GO-RFQ / Emergency Procurement - Procure 2000 ltrs Pending Component 2: Strengthening Request for Single Stage - One disinfectants CID and 1000 IDA / 59700 Post Limited 276,229.50 0.00 Implementati 2019-05-16 2019-07-11 2020-01-07 of Laboratory Capacity Quotations Envelope ltrs 20 percent alcohol, 185 on motorized sprayers, 500 bio- security kits NG-NCDC-111690-GO-RFQ Pending / Emergency procurement of Component 2: Strengthening Request for Single Stage - One IDA / 59700 Post Limited 188,776.00 0.00 Implementati 2019-05-12 2019-07-07 2020-01-03 Animal Health laboratory of Laboratory Capacity Quotations Envelope on consumables and equipment NG-NCDC-142564-GO-RFQ / Procurement of Laboratory Pending Component 2: Strengthening Request for Single Stage - One Equipments, Reagents and IDA / 59700 Post Limited 129,808.94 0.00 Implementati 2019-11-02 2019-12-28 2020-06-25 of Laboratory Capacity Quotations Envelope Consumables for NVRI Lab. on VOM NG-NCDC-142566-GO-RFQ Pending Component 3: Preparedness Request for Single Stage - One / Procurement of Vaccination IDA / 59700 Post Limited 27,505.36 0.00 Implementati 2019-11-01 2019-12-27 2020-06-24 and Emergency Response Quotations Envelope campaign materials on NG-NCDC-142568-GO-RFQ / Procurement of Dog Pending Component 3: Preparedness Request for Single Stage - One Collar/Medals/Card and flyers IDA / 59700 Post Limited 56,909.84 0.00 Implementati 2019-11-02 2019-12-28 2020-06-25 and Emergency Response Quotations Envelope for Anti-Rabies outbreak on campaign in four (4) states NG-NCDC-142570-GO-RFQ / Registration of 12 nos of 4 x 4 Toyota Hilux pick-ups, 2 nos. 2 x 2 Toyota High roof Component 5: Institutional Pending buses, 4 nos. 4 x 4 Toyota Capacity Building, Project Request for Single Stage - One IDA / 59700 Post Limited 24,262.00 0.00 Implementati 2019-11-03 2019-12-29 2020-06-26 Fortuner, 5 nos. 4 x 4 Management, Coordination Quotations Envelope on Veterinary Ambulatory Toyota and Advocacy vehicles, 175 nos. Tricycles and 75 nos. Royal Motorcycles. NG-NCDC-142573-GO-RFQ Component 5: Institutional / Insurance of project vehicles Capacity Building, Project Request for Single Stage - One IDA / 59700 Post Limited 236,027.09 45,989.81 Completed 2019-10-29 2019-11-01 2019-12-24 2019-12-13 2020-06-21 2019-12-17 - 23 Motor vehicles, 175 Management, Coordination Quotations Envelope Tricycles and 75 Motor Cycles. and Advocacy NG-NCDC-142577-GO-RFQ Component 5: Institutional / Vehicular Movement Capacity Building, Project Request for Single Stage - One IDA / 59700 Post Limited 7,540.98 2,518.49 Completed 2019-10-29 2019-11-04 2019-12-24 2019-12-13 2020-06-21 2019-12-16 Tracking Devices for Project Management, Coordination Quotations Envelope Vehicles and Advocacy NG-NCDC-147224-GO-RFQ / Procurement of Under Commercially Available Yellow Component 2: Strengthening Request for Single Stage - One IDA / 59700 Post Limited 166,854.43 105,105.89 Implementati 2019-12-02 2019-12-05 2020-01-27 2020-07-25 Fever Reagents and of Laboratory Capacity Quotations Envelope on Commodities for Yellow Fever Laboratory Network. NG-NCDC-147233-GO-RFQ Component 4: Human Under / Procurement of 48 Laptop Resource Management for Request for Single Stage - One IDA / 59700 Post Limited 40,885.25 34,848.87 Implementati 2019-12-03 2019-12-10 2020-01-28 2020-07-26 Computers for NFELTP and Effective Disease Surveillance Quotations Envelope on SORMAS training and Epidemic Preparedness Page 3 NG-NCDC-142569-GO-DIR / Procurement of Anti-Rabies Pending Component 3: Preparedness Vaccines for outbreak IDA / 59700 Post Direct Selection Direct 206,655.74 0.00 Implementati 2019-11-27 2019-12-02 2020-01-06 2020-07-04 and Emergency Response campaign in Bauchi, Bayelsa, on Ekiti and Plateau States REDISSE-GDS-RFQ -02-2020 / Emergency Procurement of Pending Component 3: Preparedness Request for Investigation and Case IDA / 59700 Post 249,838.00 0.00 Implementati 2020-03-05 2020-03-05 2020-03-05 and Emergency Response Quotations Management Consumable - 2 on Lots REDISSE-GDS-RFQ -03-2020 / Emergency Procurement of COVID-19 Sample Pippetting , Pending Component 3: Preparedness Request for Sample Collection, Waste IDA / 59700 Post 140,416.00 0.00 Implementati 2020-03-06 2020-03-06 2020-03-06 and Emergency Response Quotations Management and PCR Test on Laboratory Consumables - 4 Lots REDISSE-GDS-RFQ -04-2020 / Emergency Procurement of Pending COVID-19 Laboratory Component 3: Preparedness Request for IDA / 59700 Post 263,711.00 0.00 Implementati 2020-03-13 2020-03-13 2020-03-13 Reagents for: PCR Diagnosis; and Emergency Response Quotations on Sequencing; and Multiplex Diagnosis. REDISSE-GDS-RFQ -05-2020 Under / Emergency Procurement of Component 3: Preparedness Request for IDA / 59700 Post 222,364.00 174,500.24 Implementati 2020-03-13 2020-03-13 2020-03-13 COVID-19 Laboratory and Emergency Response Quotations on Equipment: A)PCR Equipment REDISSE-GDS-RFQ -06-2020 / Emergency Procurement of Component 3: Preparedness Request for COVID-19 Laboratory IDA / 59700 Post 446,166.00 344,999.66 Completed 2020-03-13 2020-03-13 2020-03-24 2020-03-13 2020-06-04 and Emergency Response Quotations Equipment: A) Multiplex Equipment REDISSE-GDS-RFQ -07-2020 / Emergency Additional Procurement of COVID-19 Pending Component 3: Preparedness Request for and Lassa Fever Laboratory IDA / 59700 Post 124,162.00 0.00 Implementati 2020-03-23 2020-03-23 2020-03-23 and Emergency Response Quotations Reagents for: PCR Diagnosis; on Sequencing; and Multiplex Diagnosis. REDISSE-GDS-RFQ -08-2020 / Emergency Additional Pending Component 3: Preparedness Request for Procurement of COVID-19 IDA / 59700 Post 236,111.00 0.00 Implementati 2020-03-23 2020-03-23 2020-03-23 and Emergency Response Quotations and Lassa Fever Laboratory on PCR and Multiplex Equipment REDISSE-GDS-RFQ -09-2020 / Supply and Installation of Gen. set and Inverter in 10 Component 5: Institutional Emergency Operation Centres Capacity Building, Project Request for IDA / 59700 Post 555,555.00 122,967.55 Signed 2020-03-23 2020-03-23 2020-04-23 2020-03-23 (EOCs) at states level to Management, Coordination Quotations ugment Power supply from and Advocacy National Electricity Grid - 2 Lots REDISSE-GDS-RFQ -10-2020 / Supply and Installation of Component 1: Surveillance Request for ICT in 10 Emergency IDA / 59700 Post 416,666.00 414,798.24 Signed 2020-03-23 2020-03-23 2021-03-05 2020-03-23 and Information Systems Quotations Operation Centres (EOCs) at states level REDISSE-GDS-RFQ -11-2020 / Procurement of 20 no. of 4x4 DC Pick-ups for EOCs rapid response and Component 3: Preparedness Request for monitoring across states and IDA / 59700 Post 1,050,000.00 1,121,934.56 Completed 2020-03-23 2020-03-23 2020-04-03 2020-03-23 2020-04-09 and Emergency Response Quotations 1 no. additional 4x4 Pick-up for M&E at the REDISSE PCU (to be procured through acredited/frontline dealers). REDISSE-GDS-RFQ -12-2020 / Construction of new 5 nos. Component 5: Institutional Under of 40-bed carrying space Capacity Building, Project Request for IDA / 59700 Post 1,944,444.00 0.00 Implementati 2020-04-02 2020-04-02 2020-04-02 Isolation /Treatment Centres Management, Coordination Quotations on at Kano, Kwara, Rivers, Lagos and Advocacy and Enugu states - 5 Lots REDISSE-CW-RFQ -01-2020 / Renovation of 2 nos. of Component 5: Institutional Pending existing Isolation/Treatment Capacity Building, Project Request for IDA / 59700 Post 277,777.00 0.00 Implementati 2020-03-23 2020-03-23 2020-03-23 Centres at Iberekodo General Management, Coordination Quotations on Hospital (Ogun state) & one and Advocacy other site - 2 Lots REDISSE-GDS-RFQ -13-2020 / Procurement of Equipment Pending for 2 nos. of renovated Component 3: Preparedness Request for IDA / 59700 Post 555,555.00 0.00 Implementati 2020-03-23 2020-03-23 2020-03-23 Isolation/Treatment Centres and Emergency Response Quotations on at Iberekodo General Hospital (Ogun state) and one other REDISSE-GDS-RFQ -14-2020 / Procurement of 15 nos. fully equipped Ambulances Pending Component 3: Preparedness Request for for Isolation/treatment IDA / 59700 Post 1,041,667.00 0.00 Implementati 2020-03-23 2020-03-23 2020-03-23 and Emergency Response Quotations centres (7nos); International on airpts(5nos); FMoH (1no.); and Ogun state (2nos). REDISSE-GDS-RFQ -15-2020 / Procurement & installation Component 5: Institutional of one Dialysis Machine each Capacity Building, Project Request for for Lassa Fever treatment IDA / 59700 Post 208,333.00 198,311.49 Signed 2020-03-23 2020-03-23 2020-07-29 2020-03-23 Management, Coordination Quotations Centre at Irrua, Owo and and Advocacy Abakaliki (3 nos. of Dialysis Machines). Page 4 REDISSE-GDS-RFQ -16-2020 / Procurement of Equipment Pending for 5 nos. newly constructed Component 3: Preparedness Request for IDA / 59700 Post 1,388,889.00 0.00 Implementati 2020-04-02 2020-04-02 2020-04-02 Isolation/Treatment Centres and Emergency Response Quotations on at Kano, Kwara, Rivers, Lagos and Enugu states - 5 Lots REDISSE-GDS-DIR -01-2020 / Procurement of 20 computers, 20 Head-phones and 20 Electric Extension Wire Component 1: Surveillance for Surveillance - Call Centre; IDA / 59700 Post Direct Selection Direct 60,168.00 52,578.51 Completed 2020-03-23 2020-02-23 2020-03-28 2020-02-28 2020-05-02 2020-03-19 2020-10-29 2020-04-06 and Information Systems plus 20 Laptops for NRL Laboratory Adhoc Staff + Data manager; 2 Printers; 5 Toner catridges; and 5InK REDISSE-GDS-DIR -03-2020 Pending Component 2: Strengthening / Procurement of additional IDA / 59700 Post Direct Selection Direct 357,894.00 0.00 Implementati 2020-04-02 2020-04-07 2020-05-12 2020-11-08 of Laboratory Capacity 20,000 PPEs Coverals - 1 Lot on REDISSE-GDS-RFQ -17- 2020 Pending / Procurement of additional Component 2: Strengthening Request for IDA / 59700 Post 271,934.00 0.00 Implementati 2020-04-02 2020-04-02 2020-04-02 Infection, Prevention Controls of Laboratory Capacity Quotations on Accessories - 1 Lot REDISSE-GDS-DIR -04-2020 / Provision Internet Under Infrastructure and Networking Component 1: Surveillance IDA / 59700 Post Direct Selection Direct 77,354.00 80,133.51 Implementati 2020-04-02 2020-03-26 2020-04-07 2020-03-20 2020-05-12 2020-11-08 of NCDC Annex Building and Information Systems on (Housing the REDISSE Project) -1 Lot REDISSE-GDS-RFQ -18- 2020 / Procurement of Disinfectants and veterinary stockpiles for the Component 3: Preparedness Request for containtment of outbreak of IDA / 59700 Post 532,508.00 502,892.77 Signed 2020-04-02 2020-04-02 2020-04-27 2020-04-02 and Emergency Response Quotations African Swine Fever (ASF) - 3 Lots: Lot A: Disinfectants; Lot B: PPEs; Lot C: Motorized Sprayers REDISSE-GDS-RFQ -01-2020 / Emergency Procurement of Component 3: Preparedness Request for Personal Protective Equipment IDA / 59700 Post 203,922.00 165,605.23 Completed 2020-03-05 2020-03-05 2020-03-12 2020-03-05 2020-03-18 and Emergency Response Quotations (PPEs) - 12,000 pcs of Coveralls - 1 Lot REDISSE-GDS-DIR-05-2020 / Procurement of Insurance Component 5: Institutional Policies for 20 Nos New Pending Capacity Building, Project Vehicles for EOC's at state IDA / 59700 Post Direct Selection Direct 44,930.00 0.00 Implementati 2020-05-27 2020-06-01 2020-07-06 2021-01-02 Management, Coordination level and 1 nos new vehicle on and Advocacy for monitoring and evaluation at the PCU. REDISSE-GDS-RFQ-19-2020 / Procurement of 44,000 pieces of Coverall (white Component 3: Preparedness Request for Single Stage - One Tyvek, with elastic wrists, IDA / 59700 Post Limited 863,333.00 812,637.17 Completed 2020-07-04 2020-07-09 2020-08-29 2020-07-28 2021-02-25 2020-10-30 and Emergency Response Quotations Envelope ankles and hood, Hidden zipper, Disposable) for 36 states plus FCT REDISSE-GDS-RFQ-20-2020 / Procurement of 88,800 units of Protective gowns full sleeve Component 3: Preparedness Request for Single Stage - One IDA / 59700 Post Limited 1,089,444.00 1,028,414.89 Completed 2020-07-04 2020-07-09 2020-08-29 2020-07-28 2021-02-25 2020-09-14 (Water resistant & pack of 10) and Emergency Response Quotations Envelope and 37,000 units of Hood for 36 states plus FCT REDISSE-GDS-RFQ-21-2020 / Procurement of 48,100 units of Protective goggles (grey Component 3: Preparedness Request for Single Stage - One plastic frame with clear lens, IDA / 59700 Post Limited 521,083.00 466,121.30 Completed 2020-07-04 2020-07-09 2020-08-29 2020-07-28 2021-02-25 2020-08-27 and Emergency Response Quotations Envelope With adjustable head band, disposable) for 36 states plus FCT REDISSE-GDS-RFQ-22-2020 / Procurement of 48,100 units Component 3: Preparedness Request for Single Stage - One IDA / 59700 Post Limited 374,111.00 351,426.95 Completed 2020-07-04 2020-07-09 2020-08-29 2020-07-28 2021-02-25 2020-09-10 of Face shield (disposable) for and Emergency Response Quotations Envelope 36 states plus FCT REDISSE-GDS-RFQ-23-2020 / Procurement of 16,428 units of Examination gloves without powder size small, ambidextrous, Nitrile non- Component 3: Preparedness Request for Single Stage - One IDA / 59700 Post Limited 213,367.00 187,748.22 Completed 2020-07-04 2020-07-10 2020-08-29 2020-07-28 2021-02-25 2020-10-19 sterile, disposable. (box of and Emergency Response Quotations Envelope 100) , 14,800 pairs of Gloves surgical, (size 8.5) and 3700 pairs of Heavy duty rubber gloves for 36 states plus FCT REDISSE-GDS-RFQ-24-2020 / Procurement of 18,500 units of Heavy duty non-woven apron, 5,180 pieces of Scrubs (Tunic XL, L), 5180 Pieces of Component 3: Preparedness Request for Single Stage - One IDA / 59700 Post Limited 210,489.00 192,047.97 Completed 2020-07-04 2020-07-09 2020-08-29 2020-07-28 2021-02-25 2020-09-30 Scrubs (Trousers XL, L) and and Emergency Response Quotations Envelope 193,140 pairs of Boot cover, high model (45cm, white, 50gm/m2 SMS, disposable) for the 36 states plus FCT REDISSE-GDS-RFQ-25-2020 / Procurement of 237,140 Component 3: Preparedness Request for Single Stage - One units of Face mask, particulate IDA / 59700 Post Limited 1,319,667.00 1,218,196.32 Completed 2020-07-04 2020-07-09 2020-08-29 2020-07-28 2021-02-25 2020-08-27 and Emergency Response Quotations Envelope respirator (grade N95) for 36 states plus FCT Page 5 REDISSE-GDS-RFQ-26-2020 / Procurement of 592 Boxes of Sharps container boxes, 1,480 pieces of Body bag, Component 3: Preparedness Request for Single Stage - One IDA / 59700 Post Limited 151,289.00 142,809.22 Completed 2020-07-04 2020-07-16 2020-08-29 2020-07-29 2021-02-25 2020-08-19 2,220 pairs of Rubber BOOTS and Emergency Response Quotations Envelope and 148,000 pieces of Biohazard bag (100 l) for the 36 States plus FCT REDISSE-GDS-RFQ-27-2020 / Procurement of 7,400 pieces of Digital THERMO SCANS with batteries, 740 Pieces of Infrared digital Thermometer, Component 3: Preparedness Request for Single Stage - One IDA / 59700 Post Limited 164,856.00 155,893.92 Completed 2020-07-04 2020-07-14 2020-08-29 2020-07-29 2021-02-25 2020-08-24 74,000 pieces of Hand and Emergency Response Quotations Envelope sanitizer gel, 1665 KG of Chlorine, and 1,850 units of Sodium Hypochlorite for the 36 states plus FCT REDISSE-GDS-RFQ-28-2020 / Procurement of 370 pieces of Bucket with tap, 222 pieces of Mopping bucket with sticks, 2,220 pieces of 1Kg Component 3: Preparedness Request for Single Stage - One IDA / 59700 Post Limited 72,458.00 75,277.76 Completed 2020-07-04 2020-07-10 2020-08-29 2020-07-28 2021-02-25 2020-08-18 Detergent, 14,800 Containers and Emergency Response Quotations Envelope of Liquid soap, 222 pieces of Backpack sprayer, and 370 pieces of Waste bin colour for the 36 States plus FCT REDISSE-GDS-RFQ-29-2020 Component 2: Strengthening Request for Single Stage - One / Emergency Procurement of IDA / 59700 Prior Limited 860,213.00 0.00 Canceled 2020-08-10 2020-10-05 2021-04-03 of Laboratory Capacity Quotations Envelope PCR RNA Extraction Kit REDISSE-GDS-RFQ-30-2020 / Procurement of Laptop Component 1: Surveillance Request for Single Stage - One IDA / 59700 Post Limited 350,000.00 327,522.11 Signed 2020-08-15 2020-07-24 2020-10-10 2020-08-07 2021-04-08 Computers and Tablets for and Information Systems Quotations Envelope SORMAS Training - 2 lots REDISSE-GDS-DIR-06-2020 / Under Component 2: Strengthening Emergency Procurement of IDA / 59700 Prior Direct Selection Direct 860,213.00 0.00 Implementati 2020-08-24 2020-08-29 2020-10-03 2021-04-01 of Laboratory Capacity PCR RNA Extraction Kit. on REDISSE-GDS-RFQ-32-2020 Component 3: Preparedness Request for Single Stage - One / Supply and Installation of IDA / 59700 Post Limited 7,527.00 7,431.57 Completed 2020-10-10 2020-07-20 2020-12-05 2020-07-29 2021-06-03 2020-08-14 and Emergency Response Quotations Envelope Fire Extinguisher REDISSE-GDS-RFQ-33-2020 / Supply, Delivery and Component 3: Preparedness Request for Single Stage - One Installation of additional 27 IDA / 59700 Post Limited 405,405.00 310,945.42 Completed 2020-10-10 2020-08-25 2020-12-05 2020-10-19 2021-06-03 2020-12-03 and Emergency Response Quotations Envelope Generating sets for States - emergency procurement REDISSE-GDS-RFQ-38-2020 / Procure mobile phones, Component 5: Institutional Under recharge cards, and internet Capacity Building, Project Request for Single Stage - One IDA / 59700 Post Limited 29,224.00 42,875.97 Implementati 2020-10-10 2020-12-09 2020-12-05 2021-06-03 for Project staff, Heads of Management, Coordination Quotations Envelope on Divisions in DVPCS _ FMARD and Advocacy project ad -hoc staff REDISSE-GDS-RFQ-42-2020 Pending / Procure 11 KVA Solar Component 2: Strengthening Request for Single Stage - One IDA / 59700 Post Limited 130,264.00 0.00 Implementati 2020-10-24 2020-12-19 2021-06-17 system for 11 Nos NVRI of Laboratory Capacity Quotations Envelope on laboratory outstations REDISSE-GDS-DIR-08-2020 / Procure 2000500 doses anti Under rabies vaccines using single Component 3: Preparedness IDA / 59700 Prior Direct Selection Direct 2,105,790.00 0.00 Implementati 2020-10-26 2020-10-31 2020-12-05 2021-06-03 source method, to suppport and Emergency Response on high risk states in the control of rabies outbreaks Component 5: Institutional REDISSE-GDS-RFQ-53-2020 Pending Capacity Building, Project Request for Single Stage - One / Logistics and utilities IDA / 59700 Post Limited 24,474.00 0.00 Implementati 2020-11-14 2021-01-09 2021-07-08 Management, Coordination Quotations Envelope support to DVPCS on and Advocacy REDISSE-GDS-RFQ-45-2020 / Production of Pending Component 3: Preparedness Request for Single Stage - One radio/television jiggles for IDA / 59700 Post Limited 13,158.00 0.00 Implementati 2020-10-31 2020-12-26 2021-06-24 and Emergency Response Quotations Envelope anti-rabies vaccination on campaign REDISSE-GDS-RFQ-47-2020 Component 5: Institutional Pending / Installation of tracking Capacity Building, Project Request for Single Stage - One IDA / 59700 Post Limited 3,553.00 0.00 Implementati 2020-11-07 2021-01-02 2021-07-01 device on vehicles purchased Management, Coordination Quotations Envelope on by AHS and Advocacy Component 5: Institutional REDISSE-GDS-RFQ-51-2020 Pending Capacity Building, Project Request for Single Stage - One / Provide Internet Services for IDA / 59700 Post Limited 2,527.00 0.00 Implementati 2020-11-07 2021-01-02 2021-07-01 Management, Coordination Quotations Envelope the Animal Health Sector on and Advocacy REDISSE-GDS-RFQ-31-2020 / Supply and Installation of Component 1: Surveillance Request for Single Stage - One IDA / 59700 Post Limited 39,474.00 36,709.06 Completed 2020-11-23 2020-08-07 2021-01-18 2020-08-12 2021-07-17 2020-08-31 Video Conferencing and Information Systems Quotations Envelope Equipment for REDISSE Project REDISSE-GDS-RFQ-35-2020 Component 5: Institutional / Procurement of mobile Capacity Building, Project Request for Single Stage - One IDA / 59700 Post Limited 25,810.00 17,944.05 Completed 2020-11-23 2020-05-28 2021-01-18 2020-06-01 2021-07-17 2020-06-08 phones and Accessories for Management, Coordination Quotations Envelope HHS Project Staff and Advocacy REDISSE-GDS-RFQ-41-2020 / Procurement of 91 Laptops, Component 5: Institutional 49 Tablets & Accessories, 6 Capacity Building, Project Request for Single Stage - One nos 3 in 1 Photocopier and IDA / 59700 Post Limited 294,451.00 0.00 Canceled 2020-11-23 2021-01-18 2021-07-17 Management, Coordination Quotations Envelope Office Logistics/Maintenance and Advocacy for Human Health Sector - 3 Lots Page 6 REDISSE-GDS-RFQ-36-2020 Pending / Procurement of Laboratory Component 2: Strengthening Request for Single Stage - One IDA / 59700 Post Limited 565,240.00 0.00 Implementati 2020-11-23 2021-01-18 2021-07-17 Reagents, Consumables and of Laboratory Capacity Quotations Envelope on Equipments - 3 Lots REDISSE-GDS-RFQ-37-2020 / Procure basic passive Pending disease surveillance materials Component 1: Surveillance Request for Single Stage - One IDA / 59700 Post Limited 230,193.00 0.00 Implementati 2020-11-23 2021-01-18 2021-07-17 for 36 States and the FCT in and Information Systems Quotations Envelope on line with PVS recommendations. REDISSE-GDS-RFQ-46-2020 Component 5: Institutional / Procurement of office tables, Pending Capacity Building, Project Request for Single Stage - One chairs, projector, all-in-one IDA / 59700 Post Limited 152,577.00 0.00 Implementati 2020-11-23 2021-01-18 2021-07-17 Management, Coordination Quotations Envelope printer and generator for on and Advocacy States REDISSE-GDS-RFQ-52-2020 Component 5: Institutional Pending / Procure office refreshment Capacity Building, Project Request for Single Stage - One IDA / 59700 Post Limited 18,208.00 0.00 Implementati 2020-11-23 2021-01-18 2021-07-17 consumables and utensils for Management, Coordination Quotations Envelope on AHS and Advocacy REDISSE-GDS-RFB-01-2020 / Procurement of 78 Project Vehicles; 52 nos. 4x4 double Pending cabin,15 nos. 2x2 Hospital Component 1: Surveillance Single Stage - One IDA / 59700 Post Request for Bids Open - National 5,404,826.00 0.00 Implementati 2020-10-19 2020-10-24 2020-12-05 2021-01-04 2021-02-08 2021-08-07 Ambulances, 7 nos. 4x4 and Information Systems Envelope on Veterinary Ambulatory vehicles, 3 nos. 2x2WD Bus, 1 nos 4X4 SUV REDISSE-GDS-RFQ-55-2020 Component 5: Institutional / Procurement of 110 Laptops Pending Capacity Building, Project Request for Single Stage - One and Accessories; 25nos. 3in1 IDA / 59700 Post Limited 203,271.00 0.00 Implementati 2020-12-12 2021-02-06 2021-08-05 Management, Coordination Quotations Envelope Photocopier and 35 nos. on and Advocacy Toners - 2 Lots REDISSE-GDS-RFQ-40-2020 Pending / Procurement of laboratory Component 2: Strengthening Request for Single Stage - One IDA / 59700 Post Limited 237,844.00 0.00 Implementati 2020-10-24 2020-12-19 2021-06-17 reagents for NVRI and VTH of Laboratory Capacity Quotations Envelope on labs REDISSE-GDS-RFQ-43-2020 Pending / Procurement of Anti-Rabies Component 3: Preparedness Request for Single Stage - One IDA / 59700 Post Limited 301,104.00 0.00 Implementati 2020-10-31 2020-12-26 2021-06-24 vaccination campaign and Emergency Response Quotations Envelope on materials - 2 Lots REDISSE-GDS-RFQ-44-2020 / Procurement of Dog Pending Component 3: Preparedness Request for Single Stage - One collar/medals/card and flyers IDA / 59700 Post Limited 614,037.00 0.00 Implementati 2020-10-31 2020-12-26 2021-06-24 and Emergency Response Quotations Envelope for anti-rabies vaccination on campaign materials - 2 Lots REDISSE-GDS-RFQ-56-2020 / Procurement of 6 Nos. Laptops, 69 Nos. Small Screen Component 5: Institutional Mobile Devices & Accessories, Pending Capacity Building, Project Request for Single Stage - One MDM & Kiosk App including IDA / 59700 Post Limited 192,320.00 0.00 Implementati 2020-12-26 2021-02-20 2021-08-19 Management, Coordination Quotations Envelope insurance for SORMAS and on and Advocacy Office Logistics/Maintenance for 12 Months for HHS - 2 Lots REDISSE-GDS-RFQ-01-2021 Pending / Procurement of Laptops and Component 1: Surveillance Request for Single Stage - One IDA / 59700 Post Limited 12,106.00 0.00 Implementati 2021-01-27 2021-03-24 2021-09-20 Modems to support FCT Data and Information Systems Quotations Envelope on Clerks REDISSE-GDS-RFB-01-2021 / Procurement of Lassa Fever Stockpiles including Ribavirin Under Injections, Ribavirin Tablets, Component 2: Strengthening Single Stage - One IDA / 59700 Post Request for Bids Open - National 1,102,618.00 0.00 Implementati 2021-01-22 2021-01-27 2021-01-27 2021-05-10 2021-03-10 2021-04-09 2021-05-14 2021-11-10 Personal Protective of Laboratory Capacity Envelope on Wears(PPEs) and Critical Consumables for Outbreak Response - 4 Lots REDISSE-GDS-DIR-01-2021 / Procurement of Reagents for Component 2: Strengthening IDA / 59700 Post Direct Selection Direct 569,680.00 521,249.45 Signed 2021-02-10 2021-02-09 2021-02-15 2021-02-24 2021-03-22 2021-03-11 2021-09-18 Molecular Diagnosis of Lassa of Laboratory Capacity fever and Yellow fever. REDISSE-GDS-RFQ-03-2021- Pending HH / Printing of 3000 copies Component 1: Surveillance Request for Single Stage - One IDA / 59700 Post Limited 19,737.00 0.00 Implementati 2021-05-29 2021-07-24 2022-01-20 of technical guidelines for all and Information Systems Quotations Envelope on States & other stakeholders. REDISSE-GDS-RFQ-04-2021- Pending HH / Printing of 35,000 Component 1: Surveillance Request for Single Stage - One IDA / 59700 Post Limited 138,158.00 0.00 Implementati 2021-05-29 2021-07-24 2022-01-20 copies of SOPs for all health and Information Systems Quotations Envelope on facilities in Nigeria REDISSE-GDS-RFQ-02-2021- HH / Printing of IDSR Pending Component 1: Surveillance Request for Single Stage - One reporting forms, Rumor Log, IDA / 59700 Post Limited 337,145.00 0.00 Implementati 2021-05-29 2021-07-24 2022-01-20 and Information Systems Quotations Envelope Case investigation form and on Contract tracing forms. NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual REDISSE-NC-RFQ-01 / Pending Distribution of Office logistics Component 1: Surveillance Request for Single Stage - One IDA / 59700 Post Limited 16,393.00 0.00 Implementati 2018-12-05 2019-01-30 2019-07-29 and Lab. Materials to 37 and Information Systems Quotations Envelope on states, NVRI and 10 VTHs Page 7 REDISSE-NC-RFB-02 / Procurement of courier service Component 2: Strengthening Single Stage - One logistics for specimen IDA / 59700 Post Request for Bids Open - National 32,754.00 0.00 Canceled 2018-11-30 2018-12-05 2019-01-16 2019-02-15 2019-03-22 2019-09-18 of Laboratory Capacity Envelope transportation and pre- positioning of supplies Component 5: Institutional REDISSE-NC-RFQ-03 / Pending Capacity Building, Project Request for Single Stage - One Support for utility fees for IDA / 59700 Post Limited 9,836.00 0.00 Implementati 2018-12-05 2019-01-30 2019-07-29 Management, Coordination Quotations Envelope electricity for 12 months - AH on and Advocacy Component 5: Institutional REDISSE-NC-RFQ-04 / Pending Capacity Building, Project Request for Single Stage - One Provision for vehicle IDA / 59700 Post Limited 14,164.00 0.00 Implementati 2018-12-05 2019-01-30 2019-07-29 Management, Coordination Quotations Envelope maintenence- AH on and Advocacy Component 5: Institutional REDISSE-NC-RFQ-05 / Pending Capacity Building, Project Request for Single Stage - One Provision for maintenance IDA / 59700 Post Limited 3,934.00 0.00 Implementati 2018-12-05 2019-01-30 2019-07-29 Management, Coordination Quotations Envelope services -AH on and Advocacy Component 5: Institutional REDISSE-NC-RFQ-06 / Pending Capacity Building, Project Request for Single Stage - One Provision for utility fees IDA / 59700 Post Limited 1,967.00 0.00 Implementati 2018-12-05 2019-01-30 2019-07-29 Management, Coordination Quotations Envelope (water) for 12 months - AH on and Advocacy Component 5: Institutional REDISSE-NC-RFQ-07 / Pending Capacity Building, Project Request for Single Stage - One Provision for waste IDA / 59700 Post Limited 1,639.00 0.00 Implementati 2018-12-05 2019-01-30 2019-07-29 Management, Coordination Quotations Envelope management disposal -AH on and Advocacy REDISSE-NCS-RFQ -01-2020 / Maintenance for Quant Pending Component 2: Strengthening Request for Studio 12 flex; Quant Studio 5 IDA / 59700 Post 41,667.00 0.00 Implementati 2020-03-23 2020-03-23 2020-03-23 of Laboratory Capacity Quotations flex; and, Maintenance for on MagPix REDISSE-NCS-RFQ -02-2020 Pending Component 2: Strengthening Request for / Maintenance for Master IDA / 59700 Post 13,889.00 0.00 Implementati 2020-03-23 2020-03-23 2020-03-23 of Laboratory Capacity Quotations cycler X50 on REDISSE-NCS-RFQ-03-2020 / Procurement of Insurance Pending Component 3: Preparedness Request for Single Stage - One Policies for 40 nos project IDA / 59700 Post Limited 79,051.00 0.00 Implementati 2020-10-17 2020-12-12 2021-06-10 and Emergency Response Quotations Envelope Vehicles for EOC's rapid on response REDISSE-NCS-DIR-02-2020 / Provide monthly airtime for Component 4: Human the CVO's office, project staff Pending Resource Management for , Federal and State Epid. IDA / 59700 Post Direct Selection Direct 9,859.00 0.00 Implementati 2020-11-02 2020-11-07 2020-12-12 2021-06-10 Effective Disease Surveillance Officers for disease on and Epidemic Preparedness reporting , phone calls and bulk SMS on feedback REDISSE-NCS-RFQ-06-2020 / Procurement of Pending Transportation Services of Component 3: Preparedness Request for Single Stage - One IDA / 59700 Post Limited 34,862.00 0.00 Implementati 2020-11-23 2021-01-18 2021-07-17 materials for disease and Emergency Response Quotations Envelope on containment and surveillance to states, VTHs, NVRI, LBMs REDISSE-NCS-RFQ-07-2020 Pending / Support for anti rabies Component 3: Preparedness Request for Single Stage - One IDA / 59700 Post Limited 273,606.00 0.00 Implementati 2020-11-28 2021-01-23 2021-07-22 vaccination campaign logistics and Emergency Response Quotations Envelope on in high risk states REDISSE-NCS-RFQ-05-2020 Component 5: Institutional Pending / Insurance of vehicles, Capacity Building, Project Request for Single Stage - One IDA / 59700 Post Limited 326,544.00 0.00 Implementati 2020-11-07 2021-01-02 2021-07-01 motorcycles and tricycles for Management, Coordination Quotations Envelope on AHS and Advocacy Component 5: Institutional REDISSE-NCS-RFQ-08-2020 Pending Capacity Building, Project Request for Single Stage - One / Comprehensive insurance of IDA / 59700 Post Limited 70,587.00 0.00 Implementati 2021-01-03 2021-02-28 2021-08-27 Management, Coordination Quotations Envelope vehicles/Renewal on and Advocacy CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual REDISSE-CS-CQS-01 / Consultancy for Branding and Component 5: Institutional Consultant corporate communication Capacity Building, Project IDA / 59700 Post Qualification Open - National 42,081.00 0.00 Canceled 2018-08-15 2018-09-05 2018-10-19 2018-11-18 2018-12-23 2019-06-21 including development of risk Management, Coordination Selection communication strategies for and Advocacy the REDISSE project REDISSE-CS-CQS-03 / Consultancy for Establising, Component 5: Institutional developing, training, and Consultant Capacity Building, Project Pending licensing enterprise IDA / 59700 Post Qualification Open - National 162,295.00 0.00 2018-10-30 2018-11-20 2019-01-03 2019-02-02 2019-03-09 2019-09-05 Management, Coordination Implementation management of software for Selection and Advocacy Procurement, Audit and Financial management. REDISSE-CS-INDV -06 / Needs assessment and consensus building for human Consultant and animal health information Component 1: Surveillance IDA / 59700 Post Qualification Open - National 69,512.00 0.00 Canceled 2018-10-30 2018-11-20 2019-01-03 2019-02-02 2019-03-09 2019-09-05 systems to develop a plan and and Information Systems Selection road map for an interconnected real-time system. REDISSE-CS-CQS-04 / Consultant Consultancy for a National Component 2: Strengthening IDA / 59700 Post Qualification Open - National 105,478.00 0.00 Canceled 2018-10-30 2018-11-20 2019-01-03 2019-02-02 2019-03-09 2019-09-05 Public Health Laboratory of Laboratory Capacity Selection Needs Assessment Page 8 REDISSE-CS-CQS-06 / Consultancy for re- assessment of 37 Veterinary Consultant Component 1: Surveillance Public Health/ Epidemiology IDA / 59700 Post Qualification Open - National 58,230.00 0.00 Canceled 2018-10-22 2018-11-12 2018-12-26 2019-01-25 2019-03-01 2019-08-28 and Information Systems offices, preparation of BOQs Selection and Supervision of Rehabilitation REDISSE-CS-CQS-07 / Consultancy for assessment of Isolation Units in State Consultant Capitals in the country to Component 3: Preparedness IDA / 59700 Post Qualification Open - National 61,341.00 0.00 Canceled 2018-10-22 2018-11-12 2018-12-26 2019-01-25 2019-03-01 2019-08-28 identify gaps compared to and Emergency Response Selection global best practice and develop minimum standards for isolation practice. Component 5: Institutional REDISSE-CS-CQS-01-2020 / Consultant Capacity Building, Project Pending Engagement of External IDA / 59700 Post Qualification Limited 13,889.00 0.00 2020-04-27 2020-05-11 2020-06-10 2020-07-15 2021-01-11 Management, Coordination Implementation Auditor for REDISSE II Project. Selection and Advocacy REDISSE-CS-CQS-02-2020 / Consultant Consultancy for Supervision of Component 3: Preparedness Under IDA / 59700 Post Qualification Limited 198,144.00 0.00 2020-06-29 2020-09-17 2020-07-13 2020-08-12 2020-09-16 2021-03-15 Construction of 5Nos. and Emergency Response Implementation Selection Isolation/Treatment Centre REDISSE-CS-CQS-03-2020 / Engage Consultants to Consultant Component 1: Surveillance Under Upgrade the National Animal IDA / 59700 Post Qualification Limited 26,586.00 0.00 2020-11-18 2020-11-09 2020-12-02 2021-01-01 2021-02-05 2021-08-04 and Information Systems Implementation Disease Information System Selection (NADIS) database INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual REDISSE-CS-INDV -01 / Engagement of Individual Component 4: Human Individual Consultants from relevant Resource Management for IDA / 59700 Post Consultant Direct 7,026.00 0.00 Canceled 2018-11-15 2018-11-25 2018-12-16 2019-01-20 2019-07-19 Sectors to develop a National Effective Disease Surveillance Selection Strategy for ONE Health and and Epidemic Preparedness Workforce startegy REDDISSE-CS-INDV -02 / Recruitment of 3 Consultants Component 4: Human Individual to support for 12 months to Resource Management for IDA / 59700 Post Consultant Open 89,705.00 0.00 Canceled 2018-10-20 2018-12-08 2018-12-29 2019-02-02 2019-08-01 facilitate NCDC-FETP training Effective Disease Surveillance Selection and lead redesign of the FETP and Epidemic Preparedness programme REDISSE-CS-INDV -04 / Component 5: Institutional Engagement of a Consultant Individual Capacity Building, Project to provide Safeguard,Waste IDA / 59700 Post Consultant Limited 13,633.00 0.00 Canceled 2018-10-30 2018-11-04 2018-11-25 2018-12-30 2019-06-28 Management, Coordination Management and Grievance Selection and Advocacy Support REDISSE-CS-INDV -08 / Individual Consultancy for Situational Component 3: Preparedness IDA / 59700 Post Consultant Open 15,422.00 0.00 Canceled 2018-10-30 2018-12-18 2019-01-08 2019-02-12 2019-08-11 Analysis and Development of and Emergency Response Selection a Multi-hazard Plans REDISSE-CS-INDV -09 / Consultancy for to conduct gap analysis of the existing Individual Component 1: Surveillance Under surveillance system for IDA / 59700 Post Consultant Open 14,491.00 0.00 2018-10-30 2018-12-18 2019-01-08 2019-02-12 2019-08-11 and Information Systems Implementation Transboundary Animal Selection Diseases and zoonotic diseases REDISSE-CS-INDV -10 / Consultancy to conduct the Individual prioritazation of TADs and Component 1: Surveillance Pending IDA / 59700 Post Consultant Open 7,383.00 0.00 2018-10-30 2018-12-18 2019-01-08 2019-02-12 2019-08-11 zoonotic diseases. Review and Information Systems Implementation Selection and update priority animal diseases TADs and REDISSE-CS-INDV -11 / Consultancy to harmonize and Individual develop guidelines, protocols Component 1: Surveillance IDA / 59700 Post Consultant Open 5,350.00 0.00 Canceled 2018-11-15 2019-01-03 2019-01-24 2019-02-28 2019-08-27 and tools for animal disease and Information Systems Selection surveillance and disease reporting processes REDISSE-CS-INDV-X / Map the hot-spots in human, wild Individual Component 1: Surveillance Under and domestic animal species IDA / 59700 Post Consultant Limited 24,105.00 0.00 2019-01-16 2019-01-21 2019-02-11 2019-03-18 2019-09-14 and Information Systems Implementation interfaces for zoonotic Selection diseases and TAD REDISSE-CS-INDV-XXX / Component 4: Human Support ad hoc animal health Individual Resource Management for Pending officers in state with IDA / 59700 Post Consultant Limited 196,722.00 0.00 2018-11-28 2018-12-03 2018-12-24 2019-01-28 2019-07-27 Effective Disease Surveillance Implementation inadequate human resources Selection and Epidemic Preparedness - Hire 20 ad hoc Veterinarians . REDISSE-CS-INDV-XXXX / Consultancy to scale up and Individual Component 1: Surveillance training of animal diseases IDA / 59700 Post Consultant Limited 14,943.00 0.00 Canceled 2019-01-15 2019-01-20 2019-02-10 2019-03-17 2019-09-13 and Information Systems surveillance agents from 591 Selection -1000 Component 4: Human REDISEE-CS-INDV-XXXXX / Individual Resource Management for Under Hiring of 10 adhoc Laboratory IDA / 59700 Post Consultant Limited 61,968.00 0.00 2018-11-28 2019-04-19 2018-12-03 2018-12-24 2019-01-28 2019-07-27 Effective Disease Surveillance Implementation staff at NRL Selection and Epidemic Preparedness Page 9 REDISSE-CS-INDV-XXXXXX / Consultancy to complete the Individual Component 3: Preparedness Pending development of the Medical IDA / 59700 Post Consultant Limited 11,031.00 0.00 2018-11-28 2018-12-03 2018-12-24 2019-01-28 2019-07-27 and Emergency Response Implementation Counter-measures Logistics Selection Plan Component 5: Institutional REDISSE-CS-INDV-XXXXXXX / Individual Capacity Building, Project Engagement of 1No. IDA / 59700 Post Consultant Limited 45,246.00 46,188.64 Completed 2018-11-15 2018-12-10 2018-11-20 2018-04-17 2018-12-11 2018-04-25 2019-01-15 2018-04-30 2019-07-14 2019-04-30 Management, Coordination Procurement Consultant Selection and Advocacy REDISSE-CS-INDV -03 / Engagement of 5 Component 5: Institutional Individual Consultants/Specialists in Capacity Building, Project IDA / 59700 Post Consultant Open 253,377.00 0.00 Canceled 2018-10-20 2018-12-08 2018-12-29 2019-02-02 2019-08-01 relevant Thematic Areas to Management, Coordination Selection support Project and Advocacy Implementation REDISSE-CS-INDV -07 / Consultancy to develop Individual strategy and training modules Component 2: Strengthening IDA / 59700 Post Consultant Direct 6,628.00 0.00 Canceled 2018-10-30 2018-11-09 2018-11-30 2019-01-04 2019-07-03 on shipment of samples for of Laboratory Capacity Selection diagnosis of zoonotic and epidemic prone diseases NG-NCDC-102557-CS-INDV / Terms of Reference for the Deployment of Surge Staff for Individual Component 3: Preparedness Pending Lassa Fever Case Management IDA / 59700 Post Consultant Limited 28,032.79 0.00 2019-02-25 2019-03-02 2019-03-23 2019-04-27 2019-10-24 and Emergency Response Implementation to the Infection Control Selection Centre, Federal Medical Centre, Owo, Ondo State. NG-NCDC-102596-CS-INDV / Terms of Reference for the deployment of surge staff for Individual Component 3: Preparedness Pending Lassa Fever Case Management IDA / 59700 Post Consultant Limited 28,032.79 0.00 2019-03-04 2019-03-09 2019-03-30 2019-05-04 2019-10-31 and Emergency Response Implementation to the Lassa Fever Research Selection Institute, Irrua Specialist Teaching Hospital, Edo State. REDISSE-CS-CQS-02 / Component 5: Institutional Consultancy to develop Individual Capacity Building, Project Pending project website and IDA / 59700 Post Consultant Limited 4,348.00 0.00 2019-03-29 2019-04-03 2019-04-24 2019-05-29 2019-11-25 Management, Coordination Implementation development of REDISSE Selection and Advocacy webpages NG-NCDC-98251-CS-INDV / Component 5: Institutional Individual Hire 3 consultants to support Capacity Building, Project Pending IDA / 59700 Post Consultant Limited 38,360.65 0.00 2019-02-07 2019-02-12 2019-03-05 2019-04-09 2019-10-06 IPC data management and risk Management, Coordination Implementation Selection communication. and Advocacy NG-NCDC-108831-CS-INDV Component 5: Institutional / Hiring of Social Safeguard Individual Capacity Building, Project Consultant for initial 90 days IDA / 59700 Post Consultant Limited 24,799.00 14,173.80 Completed 2019-04-04 2019-04-11 2019-04-09 2019-10-17 2019-04-30 2019-11-14 2019-06-04 2020-02-03 2019-12-01 2020-09-25 Management, Coordination and renewable for maximum Selection and Advocacy of 120 days. NG-NCDC-108837-CS-INDV Component 5: Institutional / Hiring of Environmental Individual Capacity Building, Project Safeguards Consultant for IDA / 59700 Post Consultant Limited 24,799.00 8,864.46 Completed 2019-04-04 2019-04-11 2019-04-09 2019-10-17 2019-04-30 2019-11-18 2019-06-04 2020-01-21 2019-12-01 2020-11-20 Management, Coordination initial 90 days and renewable Selection and Advocacy for maximum of 120 days. Component 5: Institutional NG-NCDC-111680-CS-INDV Individual Capacity Building, Project Pending / Hiring of Junior and Mid- IDA / 59700 Post Consultant Limited 51,541.00 0.00 2019-05-15 2019-05-20 2019-06-10 2019-07-15 2020-01-11 Management, Coordination Implementation level Adhoc Support staff Selection and Advocacy NG-NCDC-111694-CS-INDV Component 5: Institutional Individual / Hiring of an Administrative Capacity Building, Project IDA / 59700 Post Consultant Limited 13,800.00 1,354.76 Signed 2019-04-24 2020-03-01 2019-04-29 2020-03-17 2019-05-20 2020-03-20 2019-06-24 2020-04-01 2019-12-21 officer to support the Project Management, Coordination Selection Coordinator and Advocacy NG-NCDC-121477-CS-CDS / Engagement of a Consultant Component 2: Strengthening Under for Biomedical Engineering IDA / 59700 Post Direct Selection Direct 9,285.25 0.00 2019-06-28 2019-03-24 2019-07-08 2019-09-11 2020-03-09 of Laboratory Capacity Implementation Support to ensure equipment functionality NG-NCDC-127508-CS-INDV Component 5: Institutional / Extension/Renewal of the Individual Capacity Building, Project Procurement Consultant's IDA / 59700 Post Consultant Direct 60,309.00 47,591.16 Completed 2019-08-16 2019-04-25 2019-08-26 2019-04-25 2019-09-16 2019-04-27 2019-10-21 2019-04-30 2020-04-18 2020-07-02 Management, Coordination Contract for 264 days in 12 Selection and Advocacy Calendar months NG-NCDC-147259-CS-INDV / Engagement of SORMAS Individual Component 1: Surveillance Pending Implementation Support IDA / 59700 Post Consultant Limited 23,606.56 0.00 2019-12-02 2019-12-07 2019-12-28 2020-02-01 2020-07-30 and Information Systems Implementation Officer one each in Taraba Selection State and Delta State. REDISSE-CS-INDV -01-2020 Component 4: Human Individual / Hiring of Data Management , Resource Management for Under IDA / 59700 Post Consultant 7,353.00 0.00 2020-03-23 2020-03-02 2020-03-23 2020-03-23 2020-03-23 2020-03-23 Entry and Processing Officer Effective Disease Surveillance Implementation Selection (Procurement) and Epidemic Preparedness REDISSE-CS-INDV -02-2020 / Hiring of 28 personnel connect centre response team Component 4: Human Individual (4 Supervisors, 20 call agents, Resource Management for Under IDA / 59700 Post Consultant 80,556.00 0.00 2020-03-23 2020-04-03 2020-03-23 2020-03-23 2020-03-23 2020-03-23 2 IT support and 2 Laboratory Effective Disease Surveillance Implementation Selection Data and Epidemic Preparedness Management/Communication officer) REDISSE-CS-INDV -03-2020 / Engagement of Consultant Component 4: Human for Architectural designs and Individual Resource Management for Under BOQ's for Construction of 5 IDA / 59700 Post Consultant 41,667.00 0.00 2020-04-08 2020-04-07 2020-04-08 2020-04-08 2020-04-08 2020-04-08 Effective Disease Surveillance Implementation nos. New Treatment Centre Selection and Epidemic Preparedness with 40 beds patient carrying capacity Page 10 REDISSE-CS-INDV-05-2020 / Engagement of 50 additional ad-hoc Veterinarians/animal Component 4: Human Individual health worker for state with Resource Management for Under IDA / 59700 Post Consultant Open 583,334.00 0.00 2020-08-03 2020-11-30 2020-09-21 2020-10-12 2020-11-16 2021-05-15 inadequate Veterinary human Effective Disease Surveillance Implementation Selection resources for the Animal and Epidemic Preparedness Health Sector of the REDISSE Project. Component 5: Institutional REDISSE-CS-INDV-06-2020 / Individual Capacity Building, Project Pending Engagement of 2 ad-hoc IDA / 59700 Post Consultant Open 13,334.00 0.00 2020-08-10 2020-09-28 2020-10-19 2020-11-23 2021-05-22 Management, Coordination Implementation Procurement Officers for AHS Selection and Advocacy REDISSE-CS-INDV-10-2020 / Component 5: Institutional Procurement Consultant: Individual Capacity Building, Project Extension of consultancy to IDA / 59700 Post Consultant Direct 49,361.00 0.00 Under Review 2020-08-24 2020-05-06 2020-09-03 2020-09-24 2020-10-29 2021-04-27 Management, Coordination support activities of REDISSE Selection and Advocacy for 1 year REDISSE-CS-INDV-11-2020 / Individual Engagement of Two Component 3: Preparedness Under IDA / 59700 Prior Consultant Open 53,685.00 0.00 2020-10-05 2020-11-30 2020-11-23 2020-12-14 2021-01-18 2021-07-17 Procurement Consultants for and Emergency Response Implementation Selection 1 Year REDISSE-CS-INDV-14-2020 / Engage a consultant to carry Individual Component 2: Strengthening Under out need assessment of NVRI IDA / 59700 Post Consultant Open 27,528.00 0.00 2020-10-19 2020-09-28 2020-12-07 2020-12-28 2021-02-01 2021-07-31 of Laboratory Capacity Implementation outstations and VTH Selection Laboratories REDISSE-CS-INDV-16-2020 / Engage a consultant to Individual develop a National Integrated Component 3: Preparedness IDA / 59700 Post Consultant Limited 14,104.00 0.00 Canceled 2020-10-26 2020-03-25 2020-10-31 2020-11-21 2020-12-26 2021-06-24 Preparedness Plans (EPP) for and Emergency Response Selection TADs and emerging and remerging animal diseases Component 5: Institutional REDISSE-CS-INDV-04-2020 / Individual Capacity Building, Project Engagement of 2 ad-hoc IDA / 59700 Post Consultant Open 5,334.00 0.00 Canceled 2020-08-10 2020-09-28 2020-10-19 2020-11-23 2021-05-22 Management, Coordination Drivers for AHS Selection and Advocacy Component 5: Institutional REDISSE-CS-INDV-08-2020 / Individual Capacity Building, Project Engagement of an ad-hoc IDA / 59700 Post Consultant Open 6,667.00 0.00 Canceled 2020-08-10 2020-09-28 2020-10-19 2020-11-23 2021-05-22 Management, Coordination M&E Officer for AHS Selection and Advocacy Component 5: Institutional REDISSE-CS-INDV-07-2020 / Individual Capacity Building, Project Engagement of 2 ad-hoc IDA / 59700 Prior Consultant Open 13,334.00 0.00 Canceled 2020-08-10 2020-09-28 2020-10-19 2020-11-23 2021-05-22 Management, Coordination Store Officers for AHS Selection and Advocacy REDISSE-CS-INDV-13-2020 / Component 5: Institutional Individual Engagement of 1 Team Capacity Building, Project IDA / 59700 Post Consultant Limited 7,895.00 7,285.98 Signed 2020-11-09 2020-11-20 2020-11-14 2021-01-13 2020-12-05 2021-02-19 2021-01-09 2021-02-24 2021-07-08 Assistant to Support the Management, Coordination Selection Project Coordinator and Advocacy Component 5: Institutional REDISSE-CS-INDV-20-2020 / Individual Capacity Building, Project Under Engagement of an ad-hoc IDA / 59700 Post Consultant Limited 7,895.00 0.00 2020-11-09 2020-02-04 2020-11-14 2020-12-05 2021-01-09 2021-07-08 Management, Coordination Implementation M&E Officer for AHS Selection and Advocacy Component 5: Institutional REDISSE-CS-INDV-21-2020 / Individual Capacity Building, Project Engagement of 2 ad-hoc IDA / 59700 Post Consultant Limited 5,334.00 0.00 Under Review 2020-11-11 2020-02-04 2020-11-16 2020-12-07 2021-01-11 2021-07-10 Management, Coordination Drivers for AHS Selection and Advocacy REDISSE-CS-INDV-12-2020 / Engagement of 2 Monitoring Individual and Evaluation Assistants to Component 3: Preparedness IDA / 59700 Post Consultant Open 15,790.00 0.00 Canceled 2020-10-12 2020-11-30 2020-12-21 2021-01-25 2021-07-24 support REDISSE II and and Emergency Response Selection COPREP implementation Process at the PCU REDISSE-CS-INDV-22-2020 / Engagement of 2 Monitoring Component 5: Institutional Individual and Evaluation Assistants to Capacity Building, Project IDA / 59700 Post Consultant Limited 15,790.00 14,571.96 Signed 2020-11-12 2020-11-25 2020-11-17 2020-12-23 2020-12-08 2021-02-23 2021-01-12 2021-03-01 2021-07-11 support REDISSE II and Management, Coordination Selection COPREP implementation and Advocacy Process at the PCU Component 5: Institutional REDISSE-CS-INDV-18-2020 / Individual Capacity Building, Project Under Engagement of 2 ad-hoc IDA / 59700 Post Consultant Limited 13,334.00 0.00 2020-11-09 2020-02-04 2020-11-14 2020-12-05 2021-01-09 2021-07-08 Management, Coordination Implementation Store Officers for AHS Selection and Advocacy Component 5: Institutional REDISSE-CS-INDV-19-2020 / Individual Capacity Building, Project Under Engagement of 2 ad-hoc IDA / 59700 Post Consultant Limited 13,334.00 0.00 2020-11-09 2020-02-04 2020-11-14 2020-12-05 2021-01-09 2021-07-08 Management, Coordination Implementation Procurement Officers for AHS Selection and Advocacy REDISSE-CS-INDV-17-2020 / Engagement of Logistics Component 4: Human Individual Management Information Resource Management for IDA / 59700 Post Consultant Limited 7,895.00 7,285.98 Signed 2020-11-18 2020-10-13 2020-11-23 2021-01-13 2020-12-14 2021-02-12 2021-01-18 2021-02-24 2021-07-17 System Officer for the NCDC Effective Disease Surveillance Selection Supply Chain for a period of and Epidemic Preparedness 12 months REDISSE-CS-CDS-01-2020 / Engage a Vulnerability Risk Component 3: Preparedness Under IDA / 59700 Post Direct Selection Direct 4,556.00 0.00 2020-11-18 2020-11-27 2020-11-28 2021-01-13 2021-02-01 2021-07-31 Assessment Mapping (VRAM) and Emergency Response Implementation Data Analyst REDISSE-CS-INDV-09-2020 / Engagement of 4 nos. Component 4: Human Individual Technical Resource Management for Under IDA / 59700 Post Consultant Limited 94,667.00 0.00 2020-11-25 2020-02-18 2020-11-30 2020-12-21 2021-01-25 2021-07-24 Assistants/Consultants for Effective Disease Surveillance Implementation Selection operational management of and Epidemic Preparedness NFELTP Page 11 REDISSE-CS-CDS-03-2020 / Support to 2 Research teams for Nigeria COVID-19 Component 2: Strengthening Under IDA / 59700 Post Direct Selection Direct 52,632.00 0.00 2020-11-25 2021-01-07 2020-12-05 2021-02-08 2021-08-07 Consortium of Rapid of Laboratory Capacity Implementation Diagnostic Test (RDTs) Kits for COVID-19 in Nigeria. REDISSE-CS-INDV-26-2020 / Component 4: Human Engagement of a National Individual Resource Management for Under Consultant to Develop IDA / 59700 Post Consultant Limited 15,210.00 0.00 2020-12-07 2020-12-01 2020-12-12 2021-01-02 2021-02-06 2021-08-05 Effective Disease Surveillance Implementation National Public Health Selection and Epidemic Preparedness Workforce Strategy REDISSE-CS-CDS-04-2020 / Component 5: Institutional Engagement of advocacy and Capacity Building, Project IDA / 59700 Post Direct Selection Direct 22,516.00 21,857.94 Signed 2020-12-07 2020-12-01 2020-12-17 2021-01-18 2021-02-20 2021-03-01 2021-08-19 communications consultant Management, Coordination for 12 Months and Advocacy REDISSE-CS-INDV-23-2020 / Engagement of a consultant Individual to develop National Integrated Component 3: Preparedness Under IDA / 59700 Post Consultant Limited 14,104.00 0.00 2020-12-07 2020-03-25 2020-12-12 2021-01-02 2021-02-06 2021-08-05 Preparedness Plans (EPP) for and Emergency Response Implementation Selection TADs and emerging and remerging animal diseases REDISSE-CS-INDV-25-2020 / Component 4: Human Engagement of a consultant Individual Resource Management for Under for 2 months to develop IDA / 59700 Post Consultant Limited 14,484.00 0.00 2020-12-07 2020-11-14 2020-12-12 2021-01-02 2021-02-06 2021-08-05 Effective Disease Surveillance Implementation database of all veterinarians Selection and Epidemic Preparedness and para-veterinarians REDISSE-CS-INDV-24-2020 / Engagement of a consultant to conduct gap analysis for Individual Component 1: Surveillance Pending the existing animal diseases IDA / 59700 Post Consultant Limited 14,953.00 0.00 2020-12-07 2020-12-12 2021-01-02 2021-02-06 2021-08-05 and Information Systems Implementation surveillance system for Selection zoonotic and non-zoonotic diseases REDISSE-CS-INDV-15-2020 / conduct 2 problem oriented Individual research and studies on Component 2: Strengthening Pending IDA / 59700 Post Consultant Open 132,369.00 0.00 2020-10-26 2020-12-14 2021-01-04 2021-02-08 2021-08-07 TADS , major zoonotic of Laboratory Capacity Implementation Selection disease outbreaks towards scientific publications. REDISSE-CS-CDS-01-2021 / Data Management, Entry and Component 5: Institutional Processing Officer Capacity Building, Project Under IDA / 59700 Post Direct Selection Direct 7,895.00 0.00 2021-01-25 2021-01-22 2021-02-04 2021-04-10 2021-10-07 (Procurement): Extension of Management, Coordination Implementation consultancy to support and Advocacy activities of REDISSE for 1 year Component 5: Institutional REDISSE-CDS-19-02 / Capacity Building, Project Procurement of Flexible IDA / 59700 Post Direct Selection Direct 26,316.00 29,837.59 Signed 2021-01-25 2019-12-05 2021-02-04 2020-02-05 2021-04-10 2021-02-01 2021-10-07 Management, Coordination Accounting Software and Advocacy REDISSE-CS-CDS-02-2021 / Engagement of a consultant for the Preparation of an Environmental and Social Management Plan (ESMP) for Component 3: Preparedness IDA / 59700 Post Direct Selection Direct 13,050.00 12,131.48 Signed 2021-02-10 2021-02-10 2021-02-20 2021-01-27 2021-04-26 2021-02-16 2021-10-23 the Construction of Infectious and Emergency Response Disease (COVID-19) Treatment Centre at the Aminu Kano Teaching Hospital, Kano REDISSE-CS-CDS-03-2021 / Engagement of a consultant for the Preparation of Environmental and Social Management Plans (ESMPs) for Component 3: Preparedness Under IDA / 59700 Post Direct Selection Direct 12,787.00 0.00 2021-02-11 2021-02-10 2021-02-21 2021-01-27 2021-04-27 2021-10-24 the Construction of Infectious and Emergency Response Implementation Disease (COVID-19) Treatment Centre at the University of Port Harcourt Teaching Hospital, (UPTH) REDISSE-CS-CDS-04-2021 / Engagement of a consultant for the Preparation of Environmental and Social Management Plans (ESMPs) for Component 3: Preparedness Under IDA / 59700 Post Direct Selection Direct 12,787.00 0.00 2021-02-12 2021-02-10 2021-02-22 2021-04-28 2021-10-25 the Construction of Infectious and Emergency Response Implementation Disease (COVID-19) Treatment Centre at the Lagos University Teaching Hospital, (LUTH) REDISSE-CS-CDS-05-2021 / Engagement of a consultant for the Preparation of an Environmental and Social Management Plan (ESMP) for Component 3: Preparedness IDA / 59700 Post Direct Selection Direct 12,787.00 11,886.83 Signed 2021-02-13 2021-02-10 2021-02-23 2021-01-27 2021-04-29 2021-02-12 2021-10-26 the Construction of Infectious and Emergency Response Disease (COVID-19) Treatment Centre at the University of Nigeria Teaching Hospital (UNTH), Enugu REDISSE-CS-CDS-06-2021 / Engagement of a consultant for the Preparation of an Environmental and Social Management Plan (ESMP) for Component 3: Preparedness Under IDA / 59700 Post Direct Selection Direct 12,787.00 0.00 2021-02-14 2021-02-10 2021-02-24 2021-04-30 2021-10-27 the Construction of Infectious and Emergency Response Implementation Disease (COVID-19) Treatment Centre at the University of Ilorin Teaching Hospital, Kwara State REDISSE-CS-INDV-01-2021- Individual HH / SORMAS Surveillance Component 1: Surveillance IDA / 59700 Post Consultant Direct 360,000.00 324,187.42 Signed 2021-04-27 2021-04-23 2021-05-07 2021-04-26 2021-05-28 2021-04-30 2021-07-02 2021-04-30 2021-12-29 Support Officer's Re- and Information Systems Selection Engagement Page 12 REDISSE-CS-INDV-02-2021- Individual Component 1: Surveillance HH / SORMAS Data Officers IDA / 59700 Post Consultant Direct 150,000.00 123,570.16 Signed 2021-04-27 2021-04-23 2021-05-07 2021-04-26 2021-05-28 2021-04-30 2021-07-02 2021-04-30 2021-12-29 and Information Systems and Clerks Re-Engagement Selection REDISSE-CS-INDV-03-2021- HH / SORMAS IT Experts, Individual Component 1: Surveillance Operations manager and IDA / 59700 Post Consultant Direct 100,000.00 68,971.93 Signed 2021-04-27 2021-04-23 2021-05-07 2021-04-26 2021-05-28 2021-04-30 2021-07-02 2021-04-30 2021-12-29 and Information Systems Admin Support Re- Selection Engagement REDISSE-CS-INDV-04-2021- HH / ENGAGEMENT OF 8NOS. Individual LABORATORY STAFF TO Component 2: Strengthening IDA / 59700 Post Consultant Limited 65,158.00 0.00 Under Review 2021-05-17 2021-05-04 2021-05-22 2021-06-12 2021-07-17 2022-01-13 SUPPORT DISEASE DIAGNOSIS of Laboratory Capacity Selection AT THE NATIONAL REFERENCE LABORATORY (NRL), GADUWA. REDISSE-CS-INDV-05-2021- HH / Engagement of a Consultant to conduct Individual assessment of the current Component 1: Surveillance Under IDA / 59700 Post Consultant Limited 7,487.00 0.00 2021-05-24 2021-06-07 2021-05-29 2021-06-19 2021-07-24 2022-01-20 situation of community-based and Information Systems Implementation Selection surveillance in Nigeria & develop National CBS Strategic Plan. Page 13 PROCUREMENT PLAN (Textual Part) Project information: Angola, Electricity Sector Improvement Project (P166805) Project Implementation agency: Ministry of Energy and Water - GEPE Date of the Procurement Plan: 24 July 2019 Period covered by this Procurement Plan: July 2019 to 30 June 2020 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016, revised August 2018) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used, once and if approved by the World Bank. When the Borrower uses its own national open competitive procurement arrangements as set forth in Law No. 9/16 dated 16 June (Lei dos Contratos Públicos), such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and additional conditions acceptable to and agreed with the World Bank. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable for those contracts identified in the Procurement Plan tables; Works: is not applicable for those contracts identified in the Procurement Plan tables. PROCUREMENT Angola : Angola - Electricity Sector Improvement and Access Project PLAN General Information Country: Angola Bank’s Approval Date of the Original Procurement Plan: 2019-07-25 2021-05-17 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P166805 GPN Date: 2021-06-22 Project Name: Angola - Electricity Sector Improvement and Access Project Loan / Credit No: IBRD / P4990 M Executing Agency(ies): inistry of Energy and Water - GEPE WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned AO-MINEA - GEPE-210427- Pending CW-RFB / Rehabilitation and Electricity service Single Stage - One 33,250,000.0 2024-01- IBRD / P4990 Prior Request for Bids Open - International 0.00 Implementat 2022-04-03 2022-04-08 2022-05-20 2022-07-04 2022-08-08 upgrade of Quileva and Cuito improvement Envelope 0 30 ion substations AO-MINEA - GEPE-210432- CW-RFB / Construction of National Control Centre (primary and backup), Market Operator and supporting Pending Electricity service Single Stage - One 40,500,000.0 2024-08- offices, installation of SCADA IBRD / P4990 Prior Request for Bids Open - International 0.00 Implementat 2022-04-08 2022-04-13 2022-05-25 2022-07-09 2022-08-13 improvement Envelope 0 12 System and upgrade of local ion substation automation systems and supply and installation of meters at border points AO-MINEA - GEPE-210439- CW-RFB / Construction of Primary and Backup Pending Datacentres (Disaster Electricity service Single Stage - One 2024-08- IBRD / P4990 Post Request for Bids Open - International 2,750,000.00 0.00 Implementat 2022-04-17 2022-04-22 2022-06-03 2022-07-18 2022-08-22 Recovery Backup Data Centre improvement Envelope 21 ion and upgrade of existing Data Centre infrastructure and Systems) AO-MINEA - GEPE-210434- Pending CW-RFB / Expansion and Electricity service Single Stage - One 24,700,000.0 2024-10- IBRD / P4990 Prior Request for Bids Open - International 0.00 Implementat 2022-06-01 2022-06-06 2022-07-18 2022-09-01 2022-10-06 upgrade of the improvement Envelope 0 05 ion telecommunication network GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual AO-MINEA - GEPE-210044- GO-RFB / Supply and Electricity access expansion Pending Installation of meters and Single Stage - One IBRD / P4990 and improvement of revenue Prior Request for Bids Open - International 7,000,000.00 0.00 Implementati 2021-09-20 2021-10-05 2021-11-24 2021-12-24 2022-01-28 2023-04-28 meter control center for the Envelope collection on RRP (Revenue Protection Program) AO-MINEA - GEPE-210374- Improvement of PRODEL’s GO-RFB / Supply and Pending capacity and strengthening Single Stage - One installation of dam safety IBRD / P4990 Post Request for Bids Open - International 2,000,000.00 0.00 Implementati 2022-06-23 2022-06-28 2022-08-09 2022-09-08 2022-10-13 2023-04-11 sustainable management of Envelope monitoring equipment, on generation plants software and training AO-MINEA - GEPE-210380- Improvement of PRODEL’s GO-RFB / Supply and Pending capacity and strengthening Single Stage - One installation of hydro- IBRD / P4990 Post Request for Bids Open - International 1,000,000.00 0.00 Implementati 2022-06-30 2022-07-05 2022-08-16 2022-09-15 2022-10-20 2023-04-18 sustainable management of Envelope meteorological monitoring on generation plants equipment and training Improvement of PRODEL’s AO-MINEA - GEPE-210382- Pending capacity and strengthening Single Stage - One GO-RFB / Supply of special IBRD / P4990 Post Request for Bids Open - International 500,000.00 0.00 Implementati 2022-06-15 2022-06-20 2022-08-01 2022-08-31 2022-10-05 2023-04-03 sustainable management of Envelope tools for maintenance (O&M) on generation plants AO-MINEA - GEPE-210385- Improvement of PRODEL’s GO-RFB / Supply and Pending capacity and strengthening Single Stage - One installation of equipment to IBRD / P4990 Post Request for Bids Open - International 1,000,000.00 0.00 Implementati 2022-06-13 2022-06-18 2022-07-30 2022-08-29 2022-10-03 2023-04-01 sustainable management of Envelope upgrade training facilities in on generation plants Lauca AO-MINEA - GEPE-210440- GO-RFB / Supply and training of Engineering and project management software, Pending Electricity service Single Stage - One software for power system IBRD / P4990 Post Request for Bids Open - International 1,250,000.00 0.00 Implementati 2021-06-01 2021-06-06 2021-07-18 2021-09-01 2021-10-06 2022-07-03 improvement Envelope planning, software for on operational studies, software for managing and controlling hydrothermal generation AO-MINEA - GEPE-210377- GO-RFB / Supply and Improvement of PRODEL’s Pending installation of generation capacity and strengthening Single Stage - One IBRD / P4990 Prior Request for Bids Open - International 7,000,000.00 0.00 Implementati 2021-06-15 2021-06-20 2021-08-01 2021-08-31 2021-10-05 2022-04-03 monitoring centre and data sustainable management of Envelope on platform (data centre and generation plants equipment) AO-MINEA - GEPE-210441- Pending GO-RFB / Supply and Electricity service Single Stage - One IBRD / P4990 Post Request for Bids Open - International 2,000,000.00 0.00 Implementati 2021-09-01 2021-09-06 2021-10-18 2021-12-02 2022-01-06 2023-04-01 installation of Primary and improvement Envelope on Backup Datacentres software AO-MINEA - GEPE-210443- GO-RFB / Upgrade of the Pending Electricity service Single Stage - One actual Management Support IBRD / P4990 Post Request for Bids Open - International 1,490,000.00 0.00 Implementati 2021-09-06 2021-09-11 2021-10-23 2021-12-07 2022-01-11 2023-04-06 improvement Envelope Systems to RNT-EP's Business on Processes and training Page 1 AO-MINEA - GEPE-210386- Improvement of PRODEL’s Pending GO-RFB / Supply of O&M capacity and strengthening Single Stage - One IBRD / P4990 Post Request for Bids Open - International 1,500,000.00 0.00 Implementati 2022-06-06 2022-06-11 2022-07-23 2022-08-22 2022-09-26 2023-03-25 software for Lauca and sustainable management of Envelope on Luachimo dams generation plants AO-MINEA - GEPE-210442- GO-RFB / Upgrade, Licensing Pending and Support of the Electricity service Single Stage - One IBRD / P4990 Post Request for Bids Open - International 2,710,000.00 0.00 Implementati 2021-09-08 2021-09-13 2021-10-25 2021-12-09 2022-01-13 2023-04-08 Information and improvement Envelope on communication technology Systems AO-MINEA - GEPE-210444- Pending GO-RFB / Maintenance Electricity service Single Stage - One IBRD / P4990 Post Request for Bids Open - International 250,000.00 0.00 Implementati 2021-06-02 2021-06-07 2021-07-19 2021-09-02 2021-10-07 2022-07-04 Management Tool (Portal RNT improvement Envelope on + Sharepoint AO-MINEA - GEPE-210373- GO-RFB / Purchase of Improvement of PRODEL’s Pending hardware computers, capacity and strengthening Single Stage - One IBRD / P4990 Prior Request for Bids Open - International 5,000,000.00 0.00 Implementati 2022-06-23 2022-06-28 2022-08-09 2022-09-08 2022-10-13 2023-04-11 customization, software sustainable management of Envelope on licensing and training for the generation plants upgrade of the ERP MINIMAL NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual AO-MINEA - GEPE-210094- CS-QCBS / Consulting firm (Owner's Engineer) to support PRODEL in preparation of Improvement of PRODEL’s technical specifications, capacity and strengthening Quality And Cost- Pending bidding documents, bid IBRD / P4990 Prior Open - International 4,000,000.00 0.00 2022-01-09 2022-02-08 2022-04-14 2022-05-14 2022-06-28 2022-08-17 2022-09-21 2023-09-21 sustainable management of Based Selection Implementation evaluation reports and generation plants supervision of implementation of generation monitoring centre, dam safety equipment and O&M software AO-MINEA - GEPE-210364- CS-QCBS / Consulting firm to provide PRODEL with Improvement of PRODEL’s corporate advisory services capacity and strengthening Quality And Cost- Pending IBRD / P4990 Post 2,000,000.00 0.00 2021-09-10 2021-10-10 2021-12-14 2022-01-13 2022-02-27 2022-04-18 2022-05-23 2022-11-19 and supervision of sustainable management of Based Selection Implementation implementation of ERP generation plants (Upgrade of MINIMAL) installation AO-MINEA - GEPE-210372- Improvement of PRODEL’s CS-QCBS / Corporate and capacity and strengthening Quality And Cost- Pending IBRD / P4990 Post Open - International 2,000,000.00 0.00 2021-09-15 2021-10-15 2021-12-29 2022-01-28 2022-03-14 2022-05-03 2022-06-07 2023-06-07 technical training (HR, sustainable management of Based Selection Implementation Finance, Procurement, etc) generation plants AO-MINEA - GEPE-210406- CS-QCBS / Owner's Engineer firm to design, prepare bidding documents to contract the EPC and supervise the Construction of Electricity service Quality And Cost- Pending IBRD / P4990 Post Open - International 2,250,000.00 0.00 2021-05-24 2021-06-23 2021-08-27 2021-09-26 2021-11-10 2021-12-30 2022-02-03 2024-05-03 the National Control Centre improvement Based Selection Implementation (main and backup), Market Operator and supporting offices, installation of SCADA System and Upgrade of local sub AO-MINEA - GEPE-210416- CS-QCBS / Consultant firm prepare the RNT's IT Strategic plan and support the client Electricity service Quality And Cost- Pending during the upgrade and IBRD / P4990 Post Open - International 450,000.00 0.00 2021-06-01 2021-07-01 2021-09-04 2021-10-04 2021-11-18 2022-01-22 2022-02-26 2023-08-20 improvement Based Selection Implementation customization of the Modules of the "MINIMAL" ERP and installation of Primary and Backup Datacentres software AO-MINEA - GEPE-210422- CS-QCBS / Consulting firm to carry out feasibility study for Electricity service Quality And Cost- Pending IBRD / P4990 Post Open - International 3,500,000.00 0.00 2021-06-10 2021-07-10 2021-09-13 2021-10-13 2021-11-27 2022-01-07 2022-02-11 2023-08-05 the expansion of the Network improvement Based Selection Implementation (Eastern connection to Northern) AO-MINEA - GEPE-210424- CS-QCBS / Consulting firm to Electricity service Quality And Cost- Pending carry out feasibility studies for IBRD / P4990 Post Open - International 1,500,000.00 0.00 2021-06-10 2021-07-10 2021-09-13 2021-10-13 2021-11-27 2022-01-31 2022-03-07 2023-08-29 improvement Based Selection Implementation the expansion of the Cabinda Network AO-MINEA - GEPE-210392- CS-QCBS / Owner's Engineer firm to supervise the works Electricity service Quality And Cost- Pending IBRD / P4990 Post Open - International 1,750,000.00 0.00 2021-05-17 2021-06-16 2021-08-20 2021-09-19 2021-11-03 2021-12-23 2022-01-27 2024-04-26 for rehabilitation and upgrade improvement Based Selection Implementation of Cuito and Quileva substations AO-MINEA - GEPE-210420- CS-QCBS / Consulting firm to Electricity service Quality And Cost- Pending prepare and implement the IBRD / P4990 Post Open - International 1,500,000.00 0.00 2021-06-08 2021-07-08 2021-09-11 2021-10-11 2021-11-25 2022-01-29 2022-03-05 2023-08-27 improvement Based Selection Implementation capacity building plan for RNT staff Page 2 AO-MINEA - GEPE-210411- CS-QCBS / Owner's Engineer firm to design, prepare bidding documents to Electricity service Quality And Cost- Pending IBRD / P4990 Post Open - International 1,300,000.00 0.00 2021-06-27 2021-07-27 2021-09-30 2021-10-30 2021-12-14 2022-02-17 2022-03-24 2024-06-21 contract the EPC and improvement Based Selection Implementation supervise Expansion and upgrade of the telecommunication network AO-MINEA - GEPE-210063- CS-QCBS / Owner's Engineer for revision of preliminary Electricity access expansion Quality And Cost- Pending design and supervision of IBRD / P4990 and improvement of revenue Prior Open - International 2,430,000.00 0.00 2021-04-15 2021-05-15 2021-07-19 2021-08-18 2021-10-02 2021-11-21 2021-12-26 2024-03-25 Based Selection Implementation works for distribution collection networks rehabilitation and expansion - Package B AO-MINEA - GEPE-210079- CS-QCBS / Owner's Engineer for revision of preliminary Electricity access expansion Quality And Cost- Pending design and supervision of IBRD / P4990 and improvement of revenue Prior Open - International 2,430,000.00 0.00 2021-04-15 2021-05-15 2021-07-19 2021-08-18 2021-10-02 2021-11-21 2021-12-26 2024-03-25 Based Selection Implementation works for distribution collection networks rehabilitation and expansion - Package C AO-MINEA - GEPE-210060- CS-QCBS / Owner's Engineer for revision of preliminary Electricity access expansion Quality And Cost- Pending design and supervision of IBRD / P4990 and improvement of revenue Prior Open - International 2,430,000.00 0.00 2021-04-15 2021-05-15 2021-07-19 2021-08-18 2021-10-02 2021-11-21 2021-12-26 2024-03-25 Based Selection Implementation works for distribution collection networks rehabilitation and expansion - Package A INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual AO-MINEA - GEPE-123486- CS-INDV / Short-term Individual Environmental Consultant (for IBRD / P4990 Project management support Post Consultant Limited 70,000.00 110,837.99 Signed 2019-07-28 2019-07-25 2019-08-02 2019-08-01 2019-08-22 2019-08-25 2019-08-30 2019-10-28 2019-10-29 preparation of Environmental Selection and Social Management Framework - ESMF) AO-MINEA - GEPE-144993- Improvement of PRODEL’s Individual CS-INDV / Project Coordinator capacity and strengthening IBRD / P4990 Prior Consultant Open 240,000.00 297,336.90 Signed 2019-11-18 2019-11-14 2020-01-18 2020-02-21 2020-02-08 2020-07-21 2020-03-14 2020-08-07 2021-06-07 (Lead Staff, Project sustainable management of Selection Coordination Unit - PCU) generation plants Improvement of PRODEL’s AO-MINEA - GEPE-145487- Individual capacity and strengthening CS-INDV / Procurement IBRD / P4990 Prior Consultant Open 230,000.00 298,636.90 Signed 2019-11-18 2019-11-14 2020-01-18 2020-02-21 2020-02-08 2020-07-07 2020-03-14 2020-07-27 2021-06-07 sustainable management of Specialist Selection generation plants Improvement of PRODEL’s AO-MINEA - GEPE-145488- Individual capacity and strengthening CS-INDV / Financial IBRD / P4990 Prior Consultant Open 155,000.00 281,500.00 Signed 2019-11-18 2019-11-13 2020-01-18 2020-02-21 2020-02-08 2020-07-21 2020-03-14 2020-08-07 2021-06-07 sustainable management of Management Specialist Selection generation plants Improvement of PRODEL’s AO-MINEA - GEPE-191630- Individual capacity and strengthening Under CS-INDV / Social Safeguard IBRD / P4990 Post Consultant Open 175,000.00 0.00 2020-09-21 2020-09-24 2020-12-05 2020-12-26 2021-01-29 2022-01-29 sustainable management of Implementation Specialist Selection generation plants Improvement of PRODEL’s AO-MINEA - GEPE-191639- Individual capacity and strengthening Under CS-INDV / Environmental IBRD / P4990 Post Consultant Open 175,000.00 0.00 2020-09-21 2020-09-16 2020-12-05 2020-12-26 2021-01-30 2022-04-25 sustainable management of Implementation Specialist Selection generation plants Improvement of PRODEL’s AO-MINEA - GEPE-191619- Individual capacity and strengthening CS-INDV / Junior Procurement IBRD / P4990 Prior Consultant Limited 120,000.00 0.00 Canceled 2020-09-10 2020-11-03 2020-11-17 2021-01-07 2022-01-07 sustainable management of Specialist Selection generation plants AO-MINEA - GEPE-210042- CS-INDV / Individual consultant to assist in Individual Pending preparation of bidding IBRD / P4990 Project management support Post Consultant Open 50,000.00 0.00 2021-02-08 2021-04-24 2021-05-15 2021-06-19 2021-09-17 Implementation documents and bid evaluation Selection reports for the RPP (Revenue Protection Program) AO-MINEA - GEPE-210045- CS-INDV / Individual consultant to assist in Individual preparation of bidding Pending IBRD / P4990 Project management support Post Consultant Open 50,000.00 0.00 2021-01-11 2021-03-27 2021-04-17 2021-05-22 2021-11-18 documents and bid evaluation Implementation Selection reports for the distribution networks rehabilitation and expansion projects AO-MINEA - GEPE-210085- Improvement of PRODEL’s CS-INDV / Individual Individual capacity and strengthening consultant to prepare terms of IBRD / P4990 Post Consultant Open 50,000.00 0.00 Under Review 2021-04-05 2021-06-23 2021-06-19 2021-07-10 2021-08-14 2021-11-12 sustainable management of reference for the Owner's Selection generation plants Engineer AO-MINEA - GEPE-210361- CS-INDV / Individual Individual Pending consultant to prepare terms of IBRD / P4990 Project management support Post Consultant Open 50,000.00 0.00 2021-01-25 2021-04-10 2021-05-01 2021-06-05 2021-09-03 Implementation reference for the corporate Selection advisory services Individual AO-MINEA - GEPE-216418- Under IBRD / P4990 Project management support Post Consultant 120,000.00 0.00 2021-01-29 2021-03-24 2021-04-14 2021-05-19 2022-05-19 CS-INDV / Project Accountant Implementation Selection Page 3 AO-MINEA - GEPE-198004- CS-CDS / Technical training to IRSEA by MRC Consultants so that it will be able to fulfil Improvement of PRODEL’s its enhanced role in the capacity and strengthening implementation of the IBRD / P4990 Prior Direct Selection Direct 60,000.00 0.00 Canceled 2020-10-09 2020-10-19 2020-12-23 2021-06-21 sustainable management of Presidential Decree No generation plants 178/20 of 25 June 2020, for establishing, and periodically adjusting, revenue requirements. Improvement of PRODEL’s AO-MINEA - GEPE-204622- Individual capacity and strengthening CS-INDV / Procurement IBRD / P4990 Prior Consultant Limited 120,000.00 0.00 Canceled 2020-11-12 2021-01-21 2021-01-05 2021-01-19 2021-02-07 2021-08-06 sustainable management of Specialist Selection generation plants AO-MINEA - GEPE-226461- Individual CS-INDV / Technical Under IBRD / P4990 Project management support Post Consultant Open 200,000.00 0.00 2021-03-30 2021-05-07 2021-06-30 2021-07-21 2021-08-25 2022-08-25 Specialist/Distribution Implementation Selection Engineer (PCU staff) AO-MINEA - GEPE-226466- Individual CS-INDV / Technical Under IBRD / P4990 Project management support Post Consultant Open 200,000.00 0.00 2021-03-31 2021-06-23 2021-07-07 2021-07-28 2021-09-01 2022-09-01 Specialist/Transmission Implementation Selection Engineer (PCU Staff) AO-MINEA - GEPE-224718- Individual CS-INDV / Procurement IBRD / P4990 Project management support Prior Consultant Open 120,000.00 0.00 Canceled 2021-05-17 2021-08-21 2021-09-11 2021-10-16 2022-10-16 Specialist Selection AO-MINEA - GEPE-226474- CS-CDS / Technical Training to IRSEA for the IBRD / P4990 Project management support Post Direct Selection Direct 60,000.00 0.00 Under Review 2021-06-20 2021-06-24 2021-07-11 2021-09-14 2022-01-12 implementation of the Presidential Decree No. 178/20. AO-MINEA - GEPE-224718- Individual Under CS-INDV-2 / SENIOR IBRD / P4990 Project management support Prior Consultant Open 230,000.00 0.00 2021-06-13 2021-06-10 2021-09-17 2021-10-08 2021-11-12 2022-11-12 Implementation PROCUREMENT SPECIALIST Selection Page 4 PROCUREMENT PLAN (Textual Part) Project information: [Mali] [Reinsertion of Ex-Combatants Project] [P157233] Project Implementation agency: [Project Implementation Unit (PIU) of the National Disarmament, Demobilization, and Reinsertion Commission (NDDRC)] Date of the Procurement Plan: [01/28/2018] Period covered by this Procurement Plan: [02/15/2018 to 07/28/2019] Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the [Decree No. 2015-3721 /MEF-SG dated October 22, 2015], such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: [is not applicable]; Works: [is not applicable] Other Relevant Procurement Information. PROCUREMENT Mali : Mali Reinsertion of Ex-combatants Project PLAN General Information Country: Mali Bank’s Approval Date of the Original Procurement Plan: 2018-01-30 2021-05-24 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P157233 GPN Date: Project Name: Mali Reinsertion of Ex-combatants Project Loan / Credit No: IDA / D1680 ML Reinsertion of Ex-combatants Project Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned CW-KID-03 / Tv. réalisation et équip. de 2 forages avec Request for Single Stage - One 2020-03- IDA / D1680 Community Rehabilitation Post Limited 68,970.00 68,226.31 Signed 2019-11-27 2020-03-11 2020-01-16 2020-06-16 système solaire à Tintiska et à Quotations Envelope 01 Tinta ghène région de Kidal CW-KID-14 / Travaux de surcreusement de puits Request for Single Stage - One 2020-12- pastoral à IDA / D1680 Community Rehabilitation Post Limited 43,103.00 44,118.22 Signed 2020-07-18 2020-10-15 2020-09-06 2020-12-24 Quotations Envelope 05 Anoumalène/aguelhoc dans la région de Kidal CW-TOM-07 / Tv réhabilitation du château du CSREF de Tombouctou ; Tv de Request for Single Stage - One 2020-03- IDA / D1680 Community Rehabilitation Post Limited 71,154.00 55,631.38 Signed 2019-12-04 2020-05-26 2020-01-23 2020-07-22 réalisation d’une ADS à Quotations Envelope 08 Alkama bangou à Nboura région de Tombouctou CW-KID-07 / Tv. réalisation et équip 1 puit à Request for Single Stage - One 2020-05- IDA / D1680 Community Rehabilitation Post Limited 20,688.00 22,193.82 Signed 2020-02-22 2020-05-11 2020-03-26 2020-07-02 Anhar/Tinzawatène commune Quotations Envelope 10 de Abeibara région de Kidal CW-KID-06 / Tv. réhab. du Request for Single Stage - One 2019-12- radier de amassine dans la IDA / D1680 Community Rehabilitation Post Limited 31,923.00 32,022.95 Signed 2019-10-23 2020-05-13 2019-11-25 2020-07-02 Quotations Envelope 25 région de Kidal CW-MEN-05 / Travaux de réhabilitation trois adductions d'eau sommaire (AES) à Inzougaz, Assew et Request for Single Stage - One 2020-12- IDA / D1680 Community Rehabilitation Post Limited 85,801.00 98,592.49 Signed 2020-07-29 2021-02-25 2020-09-17 2021-05-05 Tinazabène et de réalisation Quotations Envelope 16 d’une adduction d’eau à Wortakna dans la région de Ménaka CW-TOM-12 / Travaux de construction d'un forage Request for Single Stage - One 2020-12- équipé d'un château et pompe IDA / D1680 Community Rehabilitation Post Limited 41,500.00 46,633.87 Signed 2020-08-08 2020-11-02 2020-09-27 2021-01-05 Quotations Envelope 26 solaire à Faytawane dans la région de Tombouctou CW-TOM-13 / Travaux de réhabilitation du canal principale et équipement d'un Request for Single Stage - One 2020-11- IDA / D1680 Community Rehabilitation Post Limited 13,534.00 15,215.91 Signed 2020-08-08 2021-03-17 2020-09-27 2021-04-24 périmètre pour la culture du Quotations Envelope 26 riz à Mamadoukoyra dans la région de Tombouctou CW-GAO-14 / Travaux de surcreusement de 2 marres à Moudett et Intillit Nord à Moudett et Intillit, de construction d'une digue avec Request for Single Stage - One 2020-12- IDA / D1680 Community Rehabilitation Post Limited 37,931.00 40,092.36 Signed 2020-08-26 2021-02-08 2020-10-15 2021-03-25 ouvrage à submersion Quotations Envelope 29 controlée à Abba Koyra et de construction d'un parc de vaccination à Haoussa dans la région de Gao CW-MEN-03 / Travaux de réalisation et équipement Pending Request for Single Stage - One 2020-01- d’un forage à Adalwag IDA / D1680 Community Rehabilitation Post Limited 35,512.00 0.00 Implementat 2019-10-26 2019-11-28 Quotations Envelope 12 commune de Tidermène dans ion la région de Ménaka CW-KID-01 / Tv. Const. 3 salles de classe équipées 3 Request for Single Stage - One 2019-12- IDA / D1680 Community Rehabilitation Post Limited 46,552.00 48,580.83 Signed 2019-10-23 2020-04-01 2019-11-25 2020-05-21 latrines et bureau mag. à Quotations Envelope 25 Efereur région de Kidal CW-GAO-10 / Travaux de réalisation et équipement de 3 forages en pompe solaire à Request for Single Stage - One 2020-01- IDA / D1680 Community Rehabilitation Post Limited 171,914.00 168,511.94 Signed 2019-11-05 2020-03-09 2019-12-08 2020-04-24 Tabankorte à Almoustarat et Quotations Envelope 07 Nbeykoul lajoulla région de Gao CW-KID-10 / Travaux de construction d'une digue de Request for Single Stage - One 2020-12- IDA / D1680 Community Rehabilitation Post Limited 75,862.00 83,304.91 Signed 2020-07-21 2020-12-07 2020-09-09 2021-02-03 protection à Kidal aviation, Quotations Envelope 08 région de Kidal CW-TOM-14 / Travaux de construction de 2 salles de Request for Single Stage - One 2020-12- IDA / D1680 Community Rehabilitation Post Limited 39,326.00 40,628.28 Signed 2020-08-08 2020-10-09 2020-09-27 2021-01-15 classe à Milala dans la région Quotations Envelope 11 de Tombouctou CW-GAO-13 / Travaux de réalisation d’un périmètre maraicher pour la coopérative des femmes à Taboye et d’un Request for Single Stage - One 2021-01- IDA / D1680 Community Rehabilitation Post Limited 19,224.00 22,192.41 Signed 2020-08-22 2021-02-08 2020-10-11 2021-03-25 périmètre 3 hectares pour Quotations Envelope 09 l’association des groupements ruraux villageois à Gounga dans la région de Gao Page 1 CW-GAO-03 / Tv const. 2 magasins dans le marché Taboye Commune Taboye cercle Bourem , Tv Const. 6 Request for Single Stage - One 2020-01- IDA / D1680 Community Rehabilitation Post Limited 31,035.00 31,988.62 Signed 2019-11-02 2020-04-07 2019-12-05 2020-05-21 hangars dans le marché Quotations Envelope 04 TEMERA Commune de Temera cercle Bourem dans la région de Gao CW-GAO-04 / Travaux d’aménagement de la plaine Request for Single Stage - One 2020-01- de Moudakhane Commune de IDA / D1680 Community Rehabilitation Post Limited 77,204.00 75,723.89 Signed 2019-11-02 2020-04-30 2019-12-05 2020-06-24 Quotations Envelope 04 Taboye cercle Bourem dans la région de Gao CW-GAO-01 / Construction de 3 salles de classes, Bureau Request for Single Stage - One 2019-12- magasin et de 2 blocs de 3 IDA / D1680 Community Rehabilitation Post Limited 73,686.00 71,853.22 Signed 2019-11-03 2020-03-30 2019-12-06 2020-05-11 Quotations Envelope 12 latrines à Tindjirindjitane Tessit dans la région de Gao CW-GAO-11 / Travaux de réalisation et équipement Request for Single Stage - One 2020-07- d’un forage en PMH à IDA / D1680 Community Rehabilitation Post Limited 43,103.00 43,521.01 Signed 2020-03-29 2020-05-20 2020-05-18 2020-06-26 Quotations Envelope 17 Tinassamede cercle de Bourem dans la région de Gao CW-TOM-11 / Travaux de réhabilitation d'une dune Request for Single Stage - One 2020-01- ecole Oguenatt Ag ALWEYNA IDA / D1680 Community Rehabilitation Post Limited 25,862.00 26,781.47 Signed 2019-11-02 2020-04-06 2019-12-05 2020-05-22 Quotations Envelope 04 Ebanguimalane à GOSSI Gourma rharous CW-TOM-15 / Travaux d’équipement d'un forage en Request for Single Stage - One 2020-12- mini adduction d'eau à IDA / D1680 Community Rehabilitation Post Limited 39,326.00 41,422.17 Signed 2020-08-08 2020-11-02 2020-09-27 2020-12-24 Quotations Envelope 26 Amachachare à Imbodiki dans la région de Tombouctou CW-KID-02 / Tv. réalisation et équip. 2 forage avec Request for Single Stage - One 2020-03- IDA / D1680 Community Rehabilitation Post Limited 85,960.00 86,067.14 Signed 2019-11-27 2020-04-17 2020-01-16 2020-06-22 système solaire à Djanchassé Quotations Envelope 01 et à Takalout région de Kidal CW-TOM-04 / Travaux de fonçage d’un puit pastoral à Request for Single Stage - One 2020-03- IDA / D1680 Community Rehabilitation Post Limited 27,557.00 15,184.40 Signed 2019-11-27 2020-06-03 2020-01-16 2020-07-22 Sakarouratan à BER dans la Quotations Envelope 01 région de Tombouctou CW-TAO-03 / Travaux de Request for Single Stage - One 2020-01- construction d'un poste de IDA / D1680 Community Rehabilitation Post Limited 60,259.00 52,761.89 Signed 2019-10-30 2020-04-23 2019-12-02 2020-07-27 Quotations Envelope 31 santé avancé Taoudénit CW-MOP-06 / Travaux de réalisation de trois périmètres maraichers à simérou, à Mopti Pending Request for Single Stage - One 2020-11- pour les femmes et à Dia pour IDA / D1680 Community Rehabilitation Post Limited 158,814.00 0.00 Implementat 2020-07-06 2020-08-25 Quotations Envelope 23 l’association des femmes de ion Dia BENKOLA dans la région de Mopti CW-TAO-02 / Tv const. 3 salles classes bureau magasin et un bloc 3 latrines Foum Elba cercle de Foum Elba et Tv Request for Single Stage - One 2020-01- IDA / D1680 Community Rehabilitation Post Limited 139,102.00 152,039.31 Signed 2019-10-30 2020-04-01 2019-12-02 2020-07-22 const. 3 salles classes bureau Quotations Envelope 16 magasin et un bloc 3 latrines Al ourch cercle de Al ourch région de Taoudénit CW-MOP-04 / Tv 1 radier 50m kanibonzo: Const. clôture école diandiori Request for Single Stage - One 2019-12- Sokoura; Const. 1mag stoc. IDA / D1680 Community Rehabilitation Post Limited 103,917.00 111,420.67 Signed 2019-10-19 2020-06-04 2019-11-21 2020-07-28 Quotations Envelope 21 Ass. karanga Guiné;Const. salle d’obs. mag. au CSR de Bankass CW-KID-08 / Travaux de réalisation de deux (02) Pending Request for Single Stage - One 2020-11- forages équipés à Djalguit et IDA / D1680 Community Rehabilitation Post Limited 81,896.00 0.00 Implementat 2020-07-20 2020-08-25 Quotations Envelope 23 Tagorast dans la région de ion Kidal CW-KID-09 / Travaux de réalisation de trois (3) forages équipés de Système Solaire Request for Single Stage - One 2020-09- IDA / D1680 Community Rehabilitation Post Limited 129,300.00 136,059.86 Signed 2020-07-21 2020-11-02 2020-09-09 2020-12-24 àTidjazal, Intilit et Quotations Envelope 18 Abatolnmanit dans la région de Kidal CW-KID-11 / Travaux de réalisation et d’équipement de trois (3) puits citernes, de Request for Single Stage - One 2020-12- IDA / D1680 Community Rehabilitation Post Limited 85,344.00 87,581.96 Signed 2020-07-21 2020-12-07 2020-09-09 2021-02-01 château et système solaire à Quotations Envelope 08 Abuyou, Agazer et Ibadid dans la région de Kidal CW-KID-12 / Travaux de réalisation de deux forages Request for Single Stage - One 2020-09- équipés de Système Solaire à IDA / D1680 Community Rehabilitation Post Limited 86,206.00 91,106.07 Signed 2020-07-21 2020-11-16 2020-09-09 2021-01-07 Quotations Envelope 18 Tacharaght et Imasrakaden dans la région de Kidal CW-KID-15 / Travaux de Pending construction de la digue de Request for Single Stage - One 2020-12- IDA / D1680 Community Rehabilitation Post Limited 86,207.00 0.00 Implementat 2020-07-18 2020-09-06 protection d'Aguelhock dans Quotations Envelope 05 ion la région de Kidal Page 2 CW-MEN-06 / Travaux d’équipement en systéme d'adduction d'eau sommaire à Afaisawa, de forage à Inafere Request for Single Stage - One 2020-12- IDA / D1680 Community Rehabilitation Post Limited 79,870.00 80,382.27 Signed 2020-07-29 2020-10-08 2020-09-17 2020-12-22 et Tabakort, de réhabilitation Quotations Envelope 16 d’une adduction d'eau sommaire (AES) à Elangue dans la région de Ménaka CW-MEN-07 / Construction d'un parc de vaccination à Request for Single Stage - One 2020-12- IDA / D1680 Community Rehabilitation Post Limited 29,310.00 21,780.91 Signed 2020-07-29 2020-10-09 2020-09-17 2020-12-21 Andéraboukane dans la région Quotations Envelope 16 de Ménaka CW-MOP-07 / Travaux de Request for Single Stage - One 2020-11- réalisation d'un puits moderne IDA / D1680 Community Rehabilitation Post Limited 45,534.00 49,770.26 Signed 2020-07-11 2020-10-15 2020-08-30 2021-01-07 Quotations Envelope 28 dans la région de Mopti CW-TAO-04 / Travaux de Réalisation de deux (2) forges équipés de pompe solaire avec mini d'adduction d’eau Request for Single Stage - One 2021-09- IDA / D1680 Community Rehabilitation Post Limited 121,264.00 99,770.07 Signed 2019-10-30 2020-04-23 2019-12-02 2020-08-27 sommaire de 3 bornes Quotations Envelope 07 fontaines à Tinaghalhaj et à M’Back Semna dans le Cercle d’Araoune reion Taoudenit CW-MOP-05 / Tv. réalisat. d’un jardin d’arbres fruitiers à Request for Single Stage - One 2019-11- IDA / D1680 Community Rehabilitation Post Limited 35,873.00 40,955.29 Signed 2019-10-20 2020-06-09 2019-11-22 2020-08-18 Kanibonzo dans la région de Quotations Envelope 25 Mopti CW-GAO-12 / Travaux de réalisation d'un forage équipé de PMH à Tinassamede, d’un Request for Single Stage - One 2021-01- puits d'un à grand diamètre à IDA / D1680 Community Rehabilitation Post Limited 55,173.00 58,753.16 Signed 2020-08-22 2021-01-07 2020-10-11 2021-02-18 Quotations Envelope 09 Inamakka et d'un mini forage californien équipé motopompe dans la région de Gao CW-TOM-06 / Tv construction d’un mur de Request for Single Stage - One 2020-03- clôture du second cycle « IDA / D1680 Community Rehabilitation Post Limited 35,432.00 20,193.87 Signed 2019-12-04 2020-03-03 2020-01-23 2020-04-29 Quotations Envelope 08 yehia alkaya de Tombouctou » région de Tombouctou CW-MEN-02 / Travaux de construction et équipement de 3 salles de classes Request for Single Stage - One 2020-01- IDA / D1680 Community Rehabilitation Post Limited 50,695.00 53,513.15 Signed 2019-11-20 2020-04-06 2020-01-09 2020-06-04 équipées à Echaghane Quotations Envelope 13 commune de Tidèrmène dans la région de Ménaka CW-TOM-08 / Tv réalisation et équipement 1 forage en pompe solaire à Tabaye- Request for Single Stage - One 2020-02- IDA / D1680 Community Rehabilitation Post Limited 60,734.00 42,662.98 Signed 2019-11-19 2020-06-15 2020-01-08 2020-10-01 barite commune de Tilemsi Quotations Envelope 22 cercle Goundam région de Tombouctou CW-TOM-03 / Tv. de réhabilitation d'une AES par soufflage Tindaydaye GOSSI et Request for Single Stage - One 2020-01- IDA / D1680 Community Rehabilitation Post Limited 45,348.00 53,810.60 Signed 2019-11-02 2020-04-30 2019-12-05 2020-08-24 Tv. réalisation AES à Quotations Envelope 19 Tintahaten Gossi dans la région de Tombouctou CW-MOP-01 / Tv. d'Aménag. périmètre maraîcher avec mini adduction d’eau pour Request for Single Stage - One 2019-12- IDA / D1680 Community Rehabilitation Post Limited 51,080.00 53,745.67 Signed 2019-10-20 2021-03-05 2019-11-22 2020-04-03 l'association djiguiya de Quotations Envelope 22 Saoula à Djenne région de Mopti CW-TOM-10 / Travaux de réalisation et équipement d’un forage moderne en Request for Single Stage - One 2020-07- château d’eau et panneaux IDA / D1680 Community Rehabilitation Post Limited 42,362.00 38,587.68 Signed 2020-03-11 2020-04-14 2020-04-30 2020-07-17 Quotations Envelope 29 solaires à Djiri berra goungou cercle de Gourma-Rharous dans la région de Tombouctou CW-GAO-09 / Travaux de réalisation d'éclairage public à Request for Single Stage - One 2020-01- IDA / D1680 Community Rehabilitation Post Limited 67,839.00 68,430.32 Signed 2019-11-05 2020-03-19 2019-12-25 2020-05-20 Borno dans le cercle de Quotations Envelope 24 Bourem region de gao CW-MEN-01 / Tv. Const.salle de formation et de bureaux pour les femmes d'Anderaboukane Request for Single Stage - One 2020-02- IDA / D1680 Community Rehabilitation Post Limited 51,724.00 51,133.22 Signed 2019-11-20 2020-04-30 2020-01-09 2020-06-02 Tv const.maison et centre de Quotations Envelope 08 formation les jeunes d'Anderaboukane dans la région de Ménaka CW-GAO-15 / Travaux de réalisation deux forages Under Request for Single Stage - One 2021-01- équipés de pompe solaire à IDA / D1680 Community Rehabilitation Post Limited 79,151.00 0.00 Implementat 2020-08-26 2021-05-05 2020-10-15 Quotations Envelope 13 Taffassilite et à Injaguel dans ion la région de Gao CW-MEN-04 / Travaux de réalisation de deux forages dont un de 180mn à Agadèye Request for Single Stage - One 2020-12- et à Inaghade et d’un château IDA / D1680 Community Rehabilitation Post Limited 87,063.00 100,729.15 Signed 2020-07-29 2021-02-25 2020-09-17 2021-05-03 Quotations Envelope 16 d’eau sur puits existant à Tamtak dans la région de Ménaka CW-MOP-03 / TTravaux de Réalisation d’un forage avec Request for Single Stage - One 2020-01- adduction d’eau sommaire de IDA / D1680 Community Rehabilitation Post Limited 67,845.00 70,334.21 Signed 2019-10-20 2020-04-10 2019-11-22 2020-06-30 Quotations Envelope 06 Kende à Bondy région de Mopti Page 3 CW-TOM-09 / Travaux de réhabilitation d’un CSCOM, d’une école et d’un puit à Request for Single Stage - One 2020-03- IDA / D1680 Community Rehabilitation Post Limited 86,170.00 90,190.92 Signed 2019-12-04 2020-03-19 2020-01-23 2020-05-13 Teberent, Cercle de Gourma- Quotations Envelope 08 Rharous dans la région de Tombouctou CW-TOM-05 / Tv de réalisation et équipement d’un forage en pompe solaire Request for Single Stage - One 2020-01- à Tin Afferene à Gargando et IDA / D1680 Community Rehabilitation Post Limited 103,443.00 96,671.88 Signed 2019-11-02 2020-04-14 2019-12-05 2020-05-21 Quotations Envelope 19 Tv de réalisation d’une AES à Gargando dans la région de Tombouctou CW-TAO-01 / Tv. F/P Request for Single Stage - One 2020-01- Poteaux élect. Compt. Bouge IDA / D1680 Community Rehabilitation Post Limited 69,551.00 61,294.42 Signed 2019-10-30 2020-04-23 2019-12-02 2020-07-27 Quotations Envelope 01 Beha Taoudénit CW-GAO-06 / Travaux de réalisation et équipement d'un Request for Single Stage - One 2020-01- forage équipé d’une pompe IDA / D1680 Community Rehabilitation Post Limited 39,655.00 42,664.95 Signed 2019-11-05 2020-04-14 2019-12-08 2020-07-01 Quotations Envelope 22 solaire à Intilit commune de Tilemsi dans la région de Gao CW-KID-04 / Tv. réalisation et équip. 2 forages avec système solaire à Guljiat Request for Single Stage - One 2020-03- IDA / D1680 Community Rehabilitation Post Limited 90,258.00 90,327.27 Signed 2019-11-27 2020-04-27 2020-01-16 2020-07-03 Tinessako et Tagoraste Quotations Envelope 01 Achibogho dans la région de Kidal CW-GAO-02 / Tv const. 03 magasins de stockage de 4 m X 4 m chacun à Bara, Tabangaw et Tanal dans la Commune de BARA cercle Request for Single Stage - One 2020-01- IDA / D1680 Community Rehabilitation Post Limited 41,379.00 21,239.00 Signed 2019-11-02 2020-03-30 2019-12-05 2020-05-21 Ansongo , Tv const. d'un Quotations Envelope 04 magasin de stockage de 4 m X 4 m à Talataye dans la Commune de Talataye cercle Ansongo région de Gao CW-KID-13 / Travaux de réalisation d'un puit avec Request for Single Stage - One 2020-12- IDA / D1680 Community Rehabilitation Post Limited 26,002.00 27,568.46 Signed 2020-07-18 2020-10-15 2020-09-06 2020-12-24 équipement solaire à Tassick Quotations Envelope 05 dans la région de Kidal CW-TOM-16 / Travaux de construction d'un parc de Request for Single Stage - One 2020-12- IDA / D1680 Community Rehabilitation Post Limited 20,700.00 22,211.76 Signed 2020-08-08 2020-10-09 2020-09-27 2020-12-21 vaccination à Habougara dans Quotations Envelope 11 la région de Tombouctou CW-GAO-16 / Travaux de réalisation et équipement d'un Request for Single Stage - One 2021-02- forage sur le site de Zanzan à IDA / D1680 Community Rehabilitation Post Limited 15,716.00 53,861.22 Signed 2020-11-07 2021-02-25 2020-12-12 2021-04-09 Quotations Envelope 10 Bamba, cercle de Bourem dans la région de Gao CW-KID-16 / Travaux de réalisation de trois (3) forages Request for Single Stage - One 2021-02- de système solaire à Etambar, IDA / D1680 Community Rehabilitation Post Limited 154,201.00 156,709.85 Signed 2020-11-14 2021-02-22 2020-12-19 2021-04-26 Quotations Envelope 17 Inktikwa, Tamtack dans la commune urbaine de Kidal CW-GAO-17 / Construction de 4 Hangars, 02 blocs de 3 latrines et une adduction Pending d’eau sommaire (AES) au Request for Single Stage - One 2021-02- IDA / D1680 Community Rehabilitation Post Limited 92,491.00 0.00 Implementat 2020-11-07 2020-12-12 marché à bétail de Forgho, Quotations Envelope 10 ion Commune Rurale de SONI ALI BER, cercle de Gao, Région de Gao CW-GAO-18 / Construction de deux (2) forages équipés au profit des populations Request for Single Stage - One 2021-02- déplacées de retour des IDA / D1680 Community Rehabilitation Post Limited 90,576.00 97,837.06 Signed 2020-11-07 2021-02-05 2020-12-12 2021-04-08 Quotations Envelope 10 quartiers de Gadèye et Farandjirèye dans la commune urbaine de Gao CW-GAO-20 / Travaux de réalisation d'un forage équipé Pending de système solaire avec Request for Single Stage - One 2021-02- IDA / D1680 Community Rehabilitation Post Limited 46,478.00 0.00 Implementat 2020-11-07 2020-12-22 château d'eau à Quotations Envelope 20 ion Timbargotane, Commune d'Anchawadj, dans la région de Gao CW-GAO-21 / Travaux de réhabilitation du PIV de TONDOTHIRO (canal et OSC) Request for Single Stage - One 2021-03- IDA / D1680 Community Rehabilitation Post Limited 32,266.00 27,377.19 Signed 2020-11-14 2021-02-23 2020-12-19 2021-04-15 dans la commune de Quotations Envelope 19 Gounzourèye dans le cercle de Gao, Région de Gao CW-GAO-22 / Travaux de réhabilitation du Centre de santé communautaire des villages de Zindiga-Berrah Request for Single Stage - One 2021-03- IDA / D1680 Community Rehabilitation Post Limited 190,986.00 180,939.59 Signed 2020-11-14 2021-03-08 2020-12-19 2021-04-08 dans la commune Sony Ali Ber Quotations Envelope 19 et de réalisation d'une AES à Azalala Gindo - cercle de Gao, Région de Gao. CW-TOM-17 / Réalisation de deux forages de système de pompage avec mini réseau d’adduction d’eau pour le Request for Single Stage - One 2021-03- IDA / D1680 Community Rehabilitation Post Limited 141,037.00 146,528.82 Signed 2020-12-05 2021-03-08 2021-01-09 2021-04-16 village de Sondage et Quotations Envelope 10 Tejakanite, commune de Léré, cercle de Niafunké dans la région de Tombouctou. Page 4 CW-TOM-19 / Travaux de réhabilitation d’une école et de construction d’un poste de Request for Single Stage - One 2021-04- santé à Nya Fraction Kel IDA / D1680 Community Rehabilitation Post Limited 56,265.00 65,068.03 Signed 2020-12-05 2019-10-14 2021-01-09 2021-04-20 Quotations Envelope 09 Tinakawwatt dans la commune rurale de Léré dans la région de Tombouctou. CW-GAO-23 / Construction de trois (3) salles de classe bureau, magasin et 2 blocs de Under Request for Single Stage - One 2021-04- latrine au profit des IDA / D1680 Community Rehabilitation Post Limited 72,121.00 0.00 Implementat 2020-12-02 2021-01-06 Quotations Envelope 06 populations déplacées dans la ion Commune de Inchawadji Région de Gao CW-KID-18 / Travaux de réalisation d'une mini adduction d'eau à Teknewene Request for Single Stage - One 2021-07- IDA / D1680 Community Rehabilitation Post Limited 90,000.00 90,798.97 Signed 2020-11-07 2021-03-30 2021-01-02 2021-06-01 dans la commune rurale Quotations Envelope 01 d'Anafis dans la région de Kidal CW-TAO-38 / Travaux de réalisation de deux (02) foragés équipés de systèmes solaires à Boukarcha Request for Single Stage - One 2021-04- IDA / D1680 Community Rehabilitation Post Limited 127,273.00 127,753.04 Signed 2020-11-10 2021-02-09 2021-01-05 2021-03-31 (commune de Liraka) et Quotations Envelope 05 Alfakrouna (commune de Alfakrouna) dans la région de Taoudéni CW-TAO-39 / Travaux d'electrification du CSCOM d'Arouane, d'éclairage de la rue principale du village Request for Single Stage - One 2021-07- d'Arouane et Réalisation d'une IDA / D1680 Community Rehabilitation Post Limited 69,090.00 70,289.74 Signed 2020-11-18 2021-02-25 2021-01-13 2021-03-31 Quotations Envelope 12 AES en forage équipé à Hassi Ouldad Sleymane (cercle de Arouane) dans la région de Taoudénit CW-TAO-23 / Travaux de réalisation de dix (10) adductions d'eau sommaire Under respectivement dans les Single Stage - One 2021-09- IDA / D1680 Community Rehabilitation Post Request for Bids Open - National 447,212.00 0.00 Implementat 2020-11-20 2021-02-01 2020-11-25 2021-06-02 2021-01-06 2021-03-19 2021-02-05 2021-03-23 2021-03-12 cercles de Al Ourch, Foum Envelope 08 ion Elba, Achourate, Bouge Béha et Taoudénit dans la région de Taoudénit CW-TOM-32 / Travaux de réhabilitation d'un périmètre Pending rizicole de 15 HA au profit de Request for Single Stage - One 2021-07- IDA / D1680 Community Rehabilitation Post Limited 40,964.00 0.00 Implementat 2020-11-21 2021-01-16 l'association paysanne Quotations Envelope 15 ion "CONDEYE" de Toya dans la Région de Tombouctou CW-MOP-02 / Travaux d'Aménag. de la marre de Request for Single Stage - One 2019-12- IDA / D1680 Community Rehabilitation Post Limited 78,144.00 80,065.36 Signed 2019-10-20 2020-03-09 2019-11-22 2020-04-17 Bergue Kounari à Manaco Quotations Envelope 22 région de Mopti CW-GAO-35 / Travaux de réalisation d'un forage équipé de système solaire avec château d'eau à Pending Timbargotane, Commune Request for Single Stage - One 2021-07- IDA / D1680 Community Rehabilitation Post Limited 88,175.00 0.00 Implementat 2020-11-15 2021-01-10 d'Anchawadj, et d'une Quotations Envelope 09 ion d'adduction d'eau potable par le pompage solaire à Tilemsi , Commune rurale de Telemsi, cercle de Gao,région de GaO CW-KID-40 / Travaux de réalisation de deux forages équipés de système solaire à Request for Single Stage - One 2021-07- IDA / D1680 Community Rehabilitation Post Limited 138,182.00 139,228.38 Signed 2020-11-11 2021-02-22 2021-01-06 2021-04-06 TAZARGHAFT et INFEFELE Quotations Envelope 05 dans la commune de Kidal, région de Kidal CW-TOM-23 / Travaux de réalisation d'un forage équipé de système solaire pour la Pending coopérative des producteurs Request for Single Stage - One 2021-07- IDA / D1680 Community Rehabilitation Post Limited 27,849.00 0.00 Implementat 2020-11-14 2021-01-09 de gomme arabique sur 10H à Quotations Envelope 08 ion Rharous/Sidi Oumar Adiawiakoye - Région de Tombouctou CW-MEN-45 / Aménagement de la marre de la ville de Request for Single Stage - One 2021-07- MENAKA contre les IDA / D1680 Community Rehabilitation Post Limited 81,818.00 89,189.22 Signed 2020-11-21 2021-04-16 2021-01-16 2021-06-01 Quotations Envelope 15 inondations - Région de Ménaka CW-MEN-37 / Travaux de réalisation de deux (02) forages équipés de système Request for Single Stage - One 2021-07- IDA / D1680 Community Rehabilitation Post Limited 127,273.00 131,526.44 Signed 2020-11-10 2021-02-25 2021-01-05 2021-05-10 solaire à Charbaley et Ibaram Quotations Envelope 04 Dabakar dans la commune de Ménaka - Région de Ménaka CW-GAO-44 / Travaux de réalisation d'éclairage public à Request for Single Stage - One 2021-07- IDA / D1680 Community Rehabilitation Post Limited 71,455.00 69,932.20 Signed 2020-11-25 2021-02-23 2021-01-20 2021-04-13 Bara - commune rurale de Quotations Envelope 19 Bara - Région de Gao CW-TOM-48 / Travaux de construction de magasin de stockage à Kadago Commune Request for Single Stage - One 2021-03- IDA / D1680 Community Rehabilitation Post Limited 14,532.00 14,328.34 Signed 2020-11-07 2021-02-22 2021-01-02 2021-03-31 rurale de de Ouinerden - Quotations Envelope 03 cercle de Gourma Rharous - Région de Tombouctou Page 5 CW-TAO-37 / Travaux de réalisation et équipement d'une unité pour la valorisation de la gomme Request for Single Stage - One 2021-04- IDA / D1680 Community Rehabilitation Post Limited 51,455.00 50,759.96 Signed 2020-11-07 2021-02-08 2021-01-02 2021-03-31 arabique au profit de Quotations Envelope 02 l'association des femmes de Nibkit - cercle de Al Ourche dans la région de Taoudénit CW-GAO-19 / Travaux de réalisation d'un (1) forage Request for Single Stage - One 2021-02- équipé à Taziguizit Commune IDA / D1680 Community Rehabilitation Post Limited 49,140.00 48,959.02 Signed 2020-11-07 2021-02-24 2020-12-12 2021-03-30 Quotations Envelope 10 de Talataye, cercle d'Ansongo dans la région de Gao. CW-KID-17 / Travaux de réalisation de deux (2) forages équipés d'un système solaire Request for Single Stage - One 2021-03- sur le site de Weilalam dans la IDA / D1680 Community Rehabilitation Post Limited 96,019.00 95,707.24 Signed 2020-11-14 2021-02-22 2020-12-19 2021-03-10 Quotations Envelope 19 commune d'Aguelhoc, cercle de Tessalit dans la région de Kidal CW-TOM-18 / Réalisation d’un forage équipé au Pending Request for 2021-03- bénéfice de la fraction Dag IDA / D1680 Community Rehabilitation Post 57,028.00 0.00 Implementat 2020-12-05 2021-01-09 Quotations 10 Baya sis à Goundam dans la ion région de Tombouctou. CW-TOM-20 / Travaux de réalisation de deux forages équipés au profit des réfugiés installés à Gossi et là 'école Request for Single Stage - One 2021-03- IDA / D1680 Community Rehabilitation Post Limited 88,461.00 88,467.80 Signed 2020-12-05 2021-02-09 2021-01-19 2021-03-25 fondamentale publique de Quotations Envelope 20 Gourzouguèye, cercle de Gourma Rharous dans la région de Tombouctou CW-TOM-49 / Travaux de réalisation de deux forages Request for équipés de pompe solaire à Quotations - Small Pending Request for Single Stage - One 2021-09- Tadarasse /Acharane et IDA / D1680 Community Rehabilitation Post Limited Works 90,637.00 0.00 Implementat 2021-05-29 2021-07-17 Quotations Envelope 15 Louteid, commune rurale (Emergency) SPD - ion d'Essakane dans la région de Competitive Tombouctou CW-GAO-31 / Réalisation Request for d'un périmètre maraicher à Quotations - Small Request for Single Stage - One 2021-03- Tin Joulgame dans la IDA / D1680 Community Rehabilitation Post Limited Works 89,839.00 91,972.44 Signed 2020-10-11 2021-02-24 2020-12-06 2021-04-19 Quotations Envelope 06 commune rurale de Tilemsi - (Emergency) SPD - Région de Gao Competitive CW-GAO-45 / Travaux de Request for réalisation d'un forage équipé Quotations - Small Pending Request for Single Stage - One 2021-08- à Inkourou dans la commune IDA / D1680 Community Rehabilitation Post Limited Works 39,478.00 0.00 Implementat 2021-05-29 2021-07-10 Quotations Envelope 24 rurale de Anchawadji dans la (Emergency) SPD - ion région de Gao Competitive CW-TOM-41 / Construction d'un centre de formation et Request for d'encadrement des jeunes à Quotations - Small Pending Zendjina Koyra et de la clôture Request for Single Stage - One 2021-09- IDA / D1680 Community Rehabilitation Post Limited Works 56,364.00 0.00 Implementat 2021-05-31 2021-07-26 du second cycle Abdoulaye Quotations Envelope 24 (Emergency) SPD - ion Soumaguel de Gourma Competitive Rharous - Région de Tombouctou GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GO-REF-7 / Achat de matériels informatiques pour Project Management Support Pending Request for Single Stage - One l’UEP et de matériels de IDA / D1680 to Project Implementation Post Limited 47,681.00 0.00 Implementati 2018-03-09 2018-05-04 2018-05-19 Quotations Envelope communication et de Unit on sensibilisation GO-REF-4 / Acquisition de 2 Project Management Support Pending Request for Single Stage - One Véhicules station wagon pour IDA / D1680 to Project Implementation Post Limited 144,928.00 0.00 Implementati 2018-04-09 2018-06-04 2018-07-04 Quotations Envelope les missions de l'UEP Unit on GO-REF-5 / Acquisition de Project Management Support Pending Request for Single Stage - One groupe électrogène de 50 KVA IDA / D1680 to Project Implementation Post Limited 24,155.00 0.00 Implementati 2018-03-25 2018-05-20 2018-06-04 Quotations Envelope pour l’UEP Unit on GO-REF-6 / Aquisition de 3 Project Management Support Pending Request for Single Stage - One motos pour chauffeurs et IDA / D1680 to Project Implementation Post Limited 2,899.00 0.00 Implementati 2018-05-29 2018-07-24 2018-08-08 Quotations Envelope coursier Unit on ML-PREC-51762-GO-RFB / Acquisition, transport, Stockage, distribution de Kits Pending Reinsertion Support to Single Stage - One de demarrage pour la IDA / D1680 Post Request for Bids Open - International 1,920,000.00 0.00 Implementati 2018-06-15 2018-06-20 2018-08-01 2018-08-11 2018-09-08 2018-12-07 Demobilized Ex-combatants Envelope réinsertion des Ex on combattants dans les 6 régions GO-REF-11 / Confection Project Management Support Pending Agenda, Calendrier, cartes de Request for Single Stage - One IDA / D1680 to Project Implementation Post Limited 10,000.00 0.00 Implementati 2018-12-14 2019-01-02 2019-01-17 visites et gadgets de Quotations Envelope Unit on communication GO-TAO-01 / Acq 20 Pending Request for Single Stage - One décortiqueuses Almatla région IDA / D1680 Community Rehabilitation Post Limited 44,414.00 0.00 Implementati 2019-10-30 2019-12-02 2020-05-30 Quotations Envelope de Taoudénit on Page 6 GO-TOM-01 / Acq Grpes Moto pompes à Gourzouguèye et Tourchawane; à 10 groupement maraichers Request for Single Stage - One IDA / D1680 Community Rehabilitation Post Limited 129,656.00 113,998.90 Terminated 2019-12-18 2020-02-10 2020-02-06 2020-04-10 2020-03-07 féminins Banikane Niafunké; Quotations Envelope pour les ass.« Aniya de thiaye et diékabara de sandy » de Koumayra ; à 10 groupements féminins de Ngorkou région de Tombouctou GO-TOM-02 / Acquisition de 3 moulins et de 7 décortiqueuses aux Request for Single Stage - One IDA / D1680 Community Rehabilitation Post Limited 25,483.00 21,592.32 Signed 2019-11-02 2020-02-10 2019-12-05 2020-03-24 2020-01-04 associations de femmes de Quotations Envelope Diré dans la région de Tombouctou GO-TOM-06 / Acquisition d'animaux pour la reconstitution de cheptel au profit des jeunes à risques de Request for Single Stage - One 4 fractions d’éleveurs à Lafia IDA / D1680 Community Rehabilitation Post Limited 42,414.00 39,880.09 Signed 2019-11-02 2020-07-30 2019-12-05 2020-10-12 2019-12-08 Quotations Envelope et au profit des communautés d’éleveurs de Gossi cercle de Gourma-Rharous dans la région de Tombouctou GO-MEN-04 / Acquisition d’animaux pour la reconstitution de cheptel à Request for Single Stage - One Tiderméne au profit de 107 IDA / D1680 Community Rehabilitation Post Limited 34,229.00 20,606.59 Signed 2020-07-25 2020-12-07 2020-09-13 2021-04-15 2020-10-13 Quotations Envelope familles et des communautés de Tinabaw dans la région de Ménaka GO-REF-2 / Acquisition Pending équipement du Système Reinsertion Support to Request for Single Stage - One IDA / D1680 Post Limited 64,412.00 0.00 Implementati 2018-04-07 2018-05-17 2018-07-01 d’Information et de Gestion Demobilized Ex-combatants Quotations Envelope on (SIG) GO-MOP-04 / Acq. Mob. Scolaires des écoles Request for Single Stage - One IDA / D1680 Community Rehabilitation Post Limited 12,036.00 12,819.83 Signed 2019-10-20 2020-06-04 2019-11-22 2020-07-08 2019-12-22 Commune Soubala cercle de Quotations Envelope bankass région de Mopti GO-MEN-03 / Acq Equip CSCOM de Emiss-Emiss Request for Single Stage - One IDA / D1680 Community Rehabilitation Post Limited 34,479.00 33,093.19 Signed 2019-10-27 2020-06-03 2019-11-29 2020-08-20 2019-12-29 commune de Inékar région de Quotations Envelope Ménaka Project Management Support Pending GO-REF-10 / Fourniture de Request for Single Stage - One IDA / D1680 to Project Implementation Post Limited 11,667.00 0.00 Implementati 2018-12-12 2018-12-29 2019-01-13 Comsommables de Bureau Quotations Envelope Unit on GO-GAO-01 / Acquisition d’animaux au bénéfice de Under Request for Single Stage - One trois groupements d’éleveurs IDA / D1680 Community Rehabilitation Post Limited 11,379.00 13,262.98 Implementati 2020-08-26 2021-01-04 2020-10-15 2020-11-14 Quotations Envelope de Tinahamma dans la région on de Gao GO-MOP-05 / Acquisition d’animaux pour la société coopérative à Guidjo Sare, Pending Single Stage - One l'association alliance à IDA / D1680 Community Rehabilitation Post Request for Bids Open - National 151,456.00 0.00 Implementati 2020-05-31 2020-06-07 2020-07-19 2020-08-18 2020-09-22 2021-03-21 Envelope Teninkou et l’association on Yiriwere mayo Togoro à Sossobe de la région de Mopti GO-MEN-01 / Acq.petits ruminants reconst.cheptel , 540 personnes victimes à Izgarate ; 40 personnes victimes à Tabankort ; 30 Request for Single Stage - One IDA / D1680 Community Rehabilitation Post Limited 86,007.00 88,326.20 Signed 2019-10-12 2020-02-12 2019-11-14 2020-04-13 2019-12-14 personnes victimes à Quotations Envelope Infoukaretane ; 317 personnes victimes à Wassaifi et 107 familles à Tidermène dans la région de Menaka GO-MOP-01 / Acq. animaux Comm.villag Diankabou Kombomé; comm.villag Gathilomou; femmes Diondiori ; coop Teninkou; Single Stage - One coop multif Hairé Boni ; grpmt IDA / D1680 Community Rehabilitation Post Request for Bids Open - National 296,931.00 318,540.32 Signed 2019-10-31 2020-06-10 2019-11-05 2021-06-06 2019-12-05 2020-07-30 2019-12-20 2020-08-10 2020-01-10 2020-12-01 2020-02-24 Envelope village mondoro ; éleveurs Hairé Boni ; ass. « yankouna haw ga goy Hombori; jeunes éleveurs de fatoma région Mopti GO-REF-1 / Acquisition des matériels, équipments et Reinsertion Support to Single Stage - One moyens de formation des Ex- IDA / D1680 Post Request for Bids Open - National 240,000.00 187,657.46 Signed 2018-04-15 2020-07-06 2018-04-20 2021-06-06 2018-05-20 2020-08-24 2018-05-27 2020-09-04 2018-06-24 2021-01-06 2018-07-24 Demobilized Ex-combatants Envelope Combattants dans les 6 régions GO-TAO-02 / Acquisition de petits ruminants pour les Request for Single Stage - One femmes de Taoudéni et les IDA / D1680 Community Rehabilitation Post Limited 82,844.00 84,913.59 Signed 2020-08-01 2020-10-09 2020-09-20 2020-12-21 2020-10-20 Quotations Envelope jeunes à Al Ourch dans la région de Taoudénit GO-REF-8 / Equipement de Project Management Support Pending Request for Single Stage - One la salle de conférence de l’UEP IDA / D1680 to Project Implementation Post Limited 8,293.00 0.00 Implementati 2018-03-25 2018-05-20 2018-06-09 Quotations Envelope et petits equipements Unit on ML-PREC-175183-GO-DIR / Project Management Support Pending Equipement de la salle de IDA / D1680 to Project Implementation Post Direct Selection Direct 20,000.00 0.00 Implementati 2020-05-28 2020-06-02 2020-06-17 2020-06-24 conférence de l'UEP PREC en Unit on solution de vidéoconférence Page 7 GO-MOP-06 / Acquisition d’animaux pour la reconstitution du cheptel au profit de Ass de femmes et jeunes des villages de Single Stage - One Darawal,Wamy et Koubel; Ass IDA / D1680 Community Rehabilitation Post Request for Bids Open - National 192,636.00 196,010.10 Signed 2020-10-05 2021-06-02 2020-10-10 2021-06-04 2020-11-21 2021-01-22 2020-12-21 2021-01-27 2021-01-25 2021-02-19 2021-07-24 Envelope des femmes et jeunes du village de Boni ; groupement de femmes des villages de Douna et de Niagassadiou Cercle Douenza GO-MOP-08 / Acquisition d’animaux pour la reconstitution de cheptel au profit des groupements Request for Single Stage - One /associations des femmes et IDA / D1680 Community Rehabilitation Post Limited 106,355.00 104,070.65 Signed 2020-11-07 2020-11-02 2021-01-01 2020-12-24 2021-03-02 Quotations Envelope jeunes des villages d’Aldouma, Tonou et de Toungourou, cercle de Koro dans la région de Mopti GO-GAO-02 / Acquisition d'une ambulance médicalisée Under Request for Single Stage - One de type 4x4 pour l'hopital IDA / D1680 Community Rehabilitation Post Limited 60,041.00 0.00 Implementati 2020-11-07 2020-12-12 2021-02-10 Quotations Envelope Hangadoumba Moulaye on TOURE de Gao GO-GAO-22 / Fourniture de : matériels de maraichage et agricole aux femmes de l'Ass du Sahel - Bourem; matériel de séchage et Pending Request for Single Stage - One commercialisation de poisson IDA / D1680 Community Rehabilitation Post Limited 85,285.00 0.00 Implementati 2020-11-17 2021-01-12 2021-07-11 Quotations Envelope à la coopérative des on vendeuses de poissons de Gao; de matériels agro sylvo pastoral pour jeunes de bamba GO-MEN-25 / équipements et Réinsertion de 20 Request for Single Stage - One IDA / D1680 Community Rehabilitation Post Limited 50,591.00 50,734.57 Signed 2020-11-07 2021-05-05 2021-01-02 2021-06-07 2021-07-01 associations de femmes en Quotations Envelope coupe couture à Alfakrou GO-GAO-44 / Acquisition d'équipement médical pour le Request for Single Stage - One IDA / D1680 Community Rehabilitation Post Limited 89,091.00 89,163.08 Signed 2020-11-22 2021-02-22 2021-01-17 2021-04-09 2021-07-16 Centre de référence du cercle Quotations Envelope de Gao GO-MEN-44 / Acquisition d'animaux pour la reconstitution du cheptel respectivement pour 40 Pending familles dans le village de Single Stage - One IDA / D1680 Community Rehabilitation Post Request for Bids Open - National 220,909.00 0.00 Implementati 2020-10-12 2020-10-27 2020-11-26 2020-12-16 2021-01-06 2021-03-07 Inwelane, 20 familles du Envelope on village d'Inticha, 20 familles du villages de Tabankorte,, 20 familles du village du village de Imisdounane - Ménaka GO-MEN-05 / Acquisition d’équipements pour les unités de savonnerie et de tannerie, des moulins au profit des Request for Single Stage - One IDA / D1680 Community Rehabilitation Post Limited 72,115.00 74,032.66 Signed 2020-09-06 2021-04-06 2020-10-18 2021-05-28 2020-12-17 groupements de femmes des Quotations Envelope communes de Ménaka, Andéranboukane et Intadeyné dans la région de Ménaka GO-GA0-28 / Equipement Pending Request for Single Stage - One d'une unité laitière à Ansongo IDA / D1680 Community Rehabilitation Post Limited 19,135.00 0.00 Implementati 2021-05-31 2021-07-12 2021-08-11 Quotations Envelope dans la région de Gao on NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GO-REF-9 / Acquisition et Project Management Support Pending installation d'un logiciel de Request for Single Stage - One IDA / D1680 to Project Implementation Post Open - National 59,581.00 0.00 Implementati 2018-04-14 2018-05-26 2021-05-25 comptabilité pour le projet et Quotations Envelope Unit on formation des utilisateurs NC-TAO-01 / Formation en Request for Single Stage - One chantier école de 120 jeunes IDA / D1680 Community Rehabilitation Post Limited 48,906.00 95,816.28 Signed 2020-11-22 2021-02-16 2021-01-17 2021-04-15 2021-05-17 Quotations Envelope dans la région de Taoudénit CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CS-REF-2 / P.E pour l'Encadrement, l'Appui conseil, l'Orientation et dispense de Reinsertion Support to Quality And Cost- IDA / D1680 Prior Open - International 1,000,000.00 0.00 Canceled 2018-02-06 2018-02-11 2018-03-12 2018-04-21 2018-04-28 2018-05-15 2018-06-19 2019-06-19 Kit de formation aux ex- Demobilized Ex-combatants Based Selection combattants démobilisés dans la région de Mopti. CS-REF-3 / P.E pour l'Encadrement, l'Appui conseil, l'Orientation et dispense de Reinsertion Support to Quality And Cost- IDA / D1680 Prior Open - International 1,000,000.00 0.00 Canceled 2018-02-06 2018-02-11 2018-03-12 2018-04-21 2018-04-28 2018-05-15 2018-06-19 2019-06-19 Kit de formation aux ex- Demobilized Ex-combatants Based Selection combattants démobilisés dans la région de Gao Page 8 CS-REF-5 / P.E pour l'Encadrement, l'Appui conseil, l'Orientation et dispense de Reinsertion Support to Quality And Cost- IDA / D1680 Prior Open - International 1,000,000.00 0.00 Canceled 2018-02-06 2018-02-11 2018-03-12 2018-04-21 2018-04-28 2018-05-15 2018-06-19 2019-06-19 Kit de formation aux ex- Demobilized Ex-combatants Based Selection combattants démobilisés dans la région de Kidal. CS-REF-7 / P.E pour l'Encadrement, l'Appui conseil, l'Orientation et dispense de Reinsertion Support to Quality And Cost- IDA / D1680 Prior Open - International 1,000,000.00 0.00 Canceled 2018-02-06 2018-02-11 2018-03-12 2018-04-21 2018-04-28 2018-05-15 2018-06-19 2019-06-19 Kit de formation aux ex- Demobilized Ex-combatants Based Selection combattants démobilisés dans la région de Taoudenit. CS-REF-9 / Recrutement des Prestataires d'appui au Reinsertion Support to Quality And Cost- Pending démarrage des associations IDA / D1680 Post Open - International 300,000.00 0.00 2018-07-18 2018-07-23 2018-08-20 2018-09-17 2018-09-22 2018-10-11 2018-11-15 2018-12-30 Demobilized Ex-combatants Based Selection Implementation économiques et des coopératives CS-REF-10 / Recrutement des Prestataires pour Reinsertion Support to Quality And Cost- Pending IDA / D1680 Post Open - International 600,000.00 0.00 2018-03-30 2018-04-04 2018-05-02 2018-05-30 2018-06-06 2018-06-23 2018-07-28 2019-07-28 Dispense des activités d'appui Demobilized Ex-combatants Based Selection Implementation à la réinsertion sociale CS-REF-11 / Contrat de Consultant Reinsertion Support to Pending l'évaluation annuelle IDA / D1680 Post Qualification Open - National 60,000.00 0.00 2018-06-19 2018-07-10 2018-08-23 2018-09-22 2018-10-27 2019-04-25 Demobilized Ex-combatants Implementation Indépendante (Audit externe) Selection CS-REF-8 / Recrutement d'un consultant pour l'appui psycho social en faveur des ex Consultant Reinsertion Support to Pending combattants démobilisés IDA / D1680 Post Qualification Open - International 45,480.00 0.00 2018-04-22 2018-05-06 2018-05-27 2018-06-03 2018-07-04 2019-07-04 Demobilized Ex-combatants Implementation souffrant de maladies psycho Selection sociales et de troubles mentaux CS-REF-25 / P.E N°02 pour l'Encadrement, l'Appui conseil, Consultant l'Orientation et dispense de Reinsertion Support to Pending IDA / D1680 Post Qualification Open - National 120,000.00 0.00 2019-10-15 2019-10-30 2019-11-24 2019-12-09 2019-12-30 2020-12-29 Kit de formation aux ex- Demobilized Ex-combatants Implementation Selection combattants démobilisés dans la région de Taoudenit. CS-REF-22 / P.E N°02 pour l'Encadrement, l'Appui conseil, Consultant l'Orientation et dispense de Reinsertion Support to IDA / D1680 Post Qualification Open - National 120,000.00 0.00 Under Review 2019-10-15 2019-02-27 2019-10-30 2019-11-24 2019-12-09 2019-12-30 2020-12-29 Kit de formation aux ex- Demobilized Ex-combatants Selection combattants démobilisés dans la région de Tombouctou. CS-REF-23 / P.E N°02 pour l'Encadrement, l'Appui conseil, Consultant l'Orientation et dispense de Reinsertion Support to IDA / D1680 Post Qualification Open - National 120,000.00 0.00 Under Review 2019-10-15 2019-02-27 2019-10-30 2019-11-24 2019-12-09 2019-12-30 2020-12-29 Kit de formation aux ex- Demobilized Ex-combatants Selection combattants démobilisés dans la région de Kidal. CS-REF-18 / P.E pour l'Encadrement, l'Appui conseil, Consultant l'Orientation et dispense de Reinsertion Support to IDA / D1680 Post Qualification Open - National 120,000.00 0.00 Under Review 2019-10-06 2019-02-27 2019-10-21 2019-11-15 2019-11-30 2019-12-21 2020-12-20 Kit de formation aux ex- Demobilized Ex-combatants Selection combattants démobilisés dans la région de Taoudenit. CS-REF-17 / P.E N°01 pour l'Encadrement, l'Appui conseil, Consultant l'Orientation et dispense de Reinsertion Support to IDA / D1680 Post Qualification Open - National 120,000.00 0.00 Under Review 2019-10-16 2019-02-27 2019-10-31 2019-11-25 2019-12-10 2019-12-31 2020-12-30 Kit de formation aux ex- Demobilized Ex-combatants Selection combattants démobilisés dans la région de Kidal. CS-REF-24 / P.E N°02 pour l'Encadrement, l'Appui conseil, Consultant l'Orientation et dispense de Reinsertion Support to IDA / D1680 Post Qualification Open - National 120,000.00 0.00 Under Review 2019-10-15 2019-02-27 2019-10-30 2019-11-24 2019-12-09 2019-12-30 2020-12-29 Kit de formation aux ex- Demobilized Ex-combatants Selection combattants démobilisés dans la région de Menaka. CS-REF-20 / P.E N°02 pour l'Encadrement, l'Appui conseil, Consultant l'Orientation et dispense de Reinsertion Support to IDA / D1680 Post Qualification Open - National 120,000.00 0.00 Under Review 2019-10-15 2019-02-27 2019-10-30 2019-11-24 2019-12-09 2019-12-30 2020-12-29 Kit de formation aux ex- Demobilized Ex-combatants Selection combattants démobilisés dans la région de Mopti. CS-REF-21 / P.E N°02 pour l'Encadrement, l'Appui conseil, Consultant l'Orientation et dispense de Reinsertion Support to IDA / D1680 Post Qualification Open - National 120,000.00 0.00 Under Review 2019-10-16 2019-02-27 2019-10-31 2019-11-25 2019-12-10 2019-12-31 2020-12-30 Kit de formation aux ex- Demobilized Ex-combatants Selection combattants démobilisés dans la région de Gao. CS-REF-14 / P.E N°01 pour l'Encadrement, l'Appui conseil, Consultant l'Orientation et dispense de Reinsertion Support to Under IDA / D1680 Post Qualification Open - National 120,000.00 0.00 2019-10-15 2019-02-27 2019-10-30 2019-11-24 2019-12-09 2019-12-30 2020-12-29 Kit de formation aux ex- Demobilized Ex-combatants Implementation Selection combattants démobilisés dans la région de Mopti. CS-REF-15 / PE N°01 pour l'Encadrement l'Appui conseil Consultant l'Orientation et dispense de Reinsertion Support to IDA / D1680 Post Qualification Open - National 120,000.00 0.00 Under Review 2019-10-15 2019-02-27 2019-10-30 2019-11-24 2019-12-09 2019-12-30 2020-12-29 Kit de formation aux ex- Demobilized Ex-combatants Selection combattants démobilisés dans la région de Gao CS-REF-31 / Recrutement d'un Consultant dans la Consultant région de Mopti pour IDA / D1680 Community Rehabilitation Post Qualification Open - National 45,208.00 38,337.14 Signed 2019-10-14 2019-10-16 2019-10-29 2021-05-10 2019-11-20 2020-02-20 2019-12-05 2020-03-12 2019-12-26 2021-05-06 2020-06-23 Etudes/Suivi et Contrôle dans Selection le cadre de l'execution des sous projets de la composante 3 Page 9 CS-REF-32 / Recrutement d'un Consultant dans la Consultant région de Gao pour IDA / D1680 Community Rehabilitation Post Qualification Open - National 30,731.00 0.00 Under Review 2019-10-04 2019-10-16 2019-10-19 2019-11-13 2019-11-28 2019-12-19 2020-06-16 Etudes/Suivi et Contrôle dans Selection le cadre de l'execution des sous projets de la composante 3 CS-REF-33 / Recrutement d'un Consultant dans la Consultant région de Kidal pour IDA / D1680 Community Rehabilitation Post Qualification Open - National 27,166.00 0.00 Under Review 2019-10-04 2019-10-21 2019-10-19 2019-11-13 2019-11-28 2019-12-19 2020-06-16 Etudes/Suivi et Contrôle dans Selection le cadre de l'execution des sous projets de la composante 3 CS-REF-34 / Recrutement d'un Consultant dans la région de Tombouctou pour Consultant Etudes/Suivi et Contrôle dans IDA / D1680 Community Rehabilitation Post Qualification Open - National 45,283.00 49,961.52 Signed 2019-10-04 2019-10-21 2019-10-19 2020-11-03 2019-11-13 2020-02-12 2019-11-28 2020-04-28 2019-12-19 2020-06-30 2020-06-16 le cadre de l'execution des Selection sous projets de la composante 3 CS-REF-35 / Recrutement d'un Consultant dans la Consultant région de Menaka pour IDA / D1680 Community Rehabilitation Post Qualification Open - National 18,089.00 0.00 Under Review 2019-10-04 2019-10-21 2019-10-19 2019-11-13 2019-11-28 2019-12-19 2020-06-16 Etudes/Suivi et Contrôle dans Selection le cadre de l'execution des sous projets de la composante 3 CS-REF-36 / Recrutement d'un Consultant dans la Consultant région de Toudenit pour IDA / D1680 Community Rehabilitation Post Qualification Open - National 18,119.00 27,838.27 Signed 2019-10-04 2019-10-21 2019-10-19 2020-11-18 2019-11-13 2020-02-10 2019-11-28 2020-03-16 2019-12-19 2020-05-18 2020-06-16 Etudes/Suivi et Contrôle dans Selection le cadre de l'execution des sous projets de la composante 3 CS-REF-4 / P.E pour l'Encadrement, l'Appui conseil, l'Orientation et dispense de Reinsertion Support to Quality And Cost- IDA / D1680 Prior Open - International 1,000,000.00 0.00 Canceled 2018-02-06 2018-10-01 2018-02-11 2018-03-12 2018-04-21 2018-04-28 2018-05-15 2018-06-19 2019-06-19 Kit de formation aux ex- Demobilized Ex-combatants Based Selection combattants démobilisés dans la région de Tombouctou CS-REF-6 / P.E pour l'Encadrement, l'Appui conseil, l'Orientation et dispense de Reinsertion Support to Quality And Cost- IDA / D1680 Prior Open - International 1,000,000.00 0.00 Canceled 2018-02-06 2018-09-17 2018-02-11 2018-03-12 2018-04-21 2018-04-28 2018-05-15 2018-06-19 2019-06-19 Kit de formation aux ex- Demobilized Ex-combatants Based Selection combattants démobilisés dans la région de Menaka CS-REF-50 / P.E N°01 pour l'Encadrement, l'Appui conseil, Consultant l'Orientation et dispense de Reinsertion Support to IDA / D1680 Post Qualification Open - International 120,000.00 0.00 Under Review 2019-10-25 2019-02-27 2019-10-26 2019-12-02 2019-12-17 2020-01-21 2021-01-20 Kit de formation aux ex- Demobilized Ex-combatants Selection combattants démobilisés dans la région de Tombouctou CS-REF-51 / P.E N°01 pour l'Encadrement, l'Appui conseil, Consultant l'Orientation et dispense de Reinsertion Support to IDA / D1680 Post Qualification Open - International 120,000.00 0.00 Under Review 2019-10-25 2019-02-27 2019-11-09 2019-12-09 2019-12-24 2020-01-28 2021-01-27 Kit de formation aux ex- Demobilized Ex-combatants Selection combattants démobilisés dans la région de Menaka CS-REF-56 / Recrutement d’un Consultant pour l’étude Project Management Support Consultant Under situation de référence pour IDA / D1680 to Project Implementation Post Qualification Open - National 17,241.00 0.00 2020-03-16 2020-04-17 2020-03-31 2020-05-10 2020-05-25 2020-06-14 2020-08-13 Implementation l’évaluation des Unit Selection effets/impacts du PREC INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CS-REF-1 / Recrutement d'un consultant pour l'étude récapitulative socio- économique sur les filières Project Management Support Individual Pending porteuses et les Kits de IDA / D1680 to Project Implementation Post Consultant Open 24,155.00 0.00 2018-02-15 2018-03-23 2018-03-30 2018-04-27 2018-05-27 Implementation Réinsertion dans toutes les Unit Selection régions sur la base d’anciennes études réalisées au Mali CS-REF-13 / Consultant pour Project Management Support Individual Pending l'élaboration de la stratégie de IDA / D1680 to Project Implementation Post Consultant Open 22,544.00 0.00 2018-02-26 2018-04-03 2018-04-10 2018-05-08 2018-06-07 Implementation communication Unit Selection CS-REF-19 / Contrat Project Management Support Individual Pending recrutement de Secrétaire IDA / D1680 to Project Implementation Post Consultant Open 16,000.00 0.00 2019-01-06 2019-02-11 2019-02-16 2019-02-24 2021-03-15 Implementation Administratif Financier (SAF) Unit Selection CS-REF-26 / Recrutement Project Management Support Pending d'un Consultant pour l'Etude IDA / D1680 to Project Implementation Post Direct Selection Direct 20,000.00 0.00 2019-01-08 2019-01-18 2019-02-03 2019-03-05 Implementation du CGES du PREC Unit CS-REF-27 / Recrutement Project Management Support Pending d'un Consultant pour l'Etude IDA / D1680 to Project Implementation Post Direct Selection Direct 20,000.00 0.00 2019-01-08 2019-01-18 2019-02-03 2019-03-05 Implementation du CPRP du PREC Unit CS-REF-28 / Consultant pour l'élaboration du manuel Project Management Support Pending technique de la composante 2 IDA / D1680 to Project Implementation Post Direct Selection Direct 10,000.00 0.00 2019-04-30 2019-05-05 2019-05-20 2019-06-09 Implementation des projets à la demande du Unit PREC CS-REF-43 / Recrutement Project Management Support Individual Pending Spécialiste en Développement IDA / D1680 to Project Implementation Post Consultant Open 32,148.00 0.00 2019-08-07 2019-09-16 2019-10-07 2019-11-07 2021-10-31 Implementation Social (SDS) de l'UEP du PREC Unit Selection Page 10 CS-REF-44 / Recrutement Project Management Support Individual Spécialiste en Sauvegarde Pending IDA / D1680 to Project Implementation Post Consultant Open 32,148.00 0.00 2019-08-07 2019-09-16 2019-10-07 2019-11-07 2021-10-31 Environnemental (SSEv) de Implementation Unit Selection l'UEP du PREC Project Management Support Individual CS-REF-12 / Contrat du Pending IDA / D1680 to Project Implementation Post Consultant Open 32,148.00 0.00 2018-04-16 2018-05-17 2018-05-24 2018-06-03 2019-06-03 spécialiste en suivi évaluation Implementation Unit Selection CS-REF-52 / Recrutement Project Management Support Individual d’un consultant national pour Pending IDA / D1680 to Project Implementation Post Consultant Limited 5,172.00 0.00 2019-11-06 2019-11-11 2019-11-26 2019-12-25 2020-02-23 appui à la passation des Implementation Unit Selection marchés à L’UEP/PREC CS-REF-53 / Recrutement Project Management Support Individual Specialiste en Passation de Under IDA / D1680 to Project Implementation Post Consultant Limited 41,400.00 0.00 2019-12-23 2020-01-14 2019-12-28 2020-01-04 2020-01-15 2021-01-14 marches pour le compte de Implementation Unit Selection l’UEP du PREC CS-REF-54 / Recrutement Project Management Support Individual Specialiste en Gestion Under IDA / D1680 to Project Implementation Post Consultant Limited 41,400.00 0.00 2019-12-23 2020-01-14 2019-12-28 2020-01-04 2020-01-15 2021-01-14 Financiere pour le compte de Implementation Unit Selection l’UEP du PREC CS-REF-55 / Recrutement Individual Ingénieur en Infrastructures Under IDA / D1680 Community Rehabilitation Post Consultant Limited 20,700.00 0.00 2019-12-23 2020-01-14 2019-12-28 2020-01-04 2020-01-15 2020-07-13 communautaires pour le Implementation Selection compte de l’UEP du PREC CS-REF-39 / Recrutement Individual assistant en suivi et IDA / D1680 Community Rehabilitation Post Consultant Open 23,077.00 1,176.62 Signed 2020-04-01 2020-04-17 2020-04-28 2020-07-15 2020-05-13 2020-09-07 2020-06-10 2020-11-16 2021-06-10 évaluation dans la région Selection Tombouctou CS-REF-57 / Recrutement Individual d’un Spécialiste en Violences Pending IDA / D1680 Community Rehabilitation Post Consultant Open 41,400.00 0.00 2020-02-28 2020-04-02 2020-04-09 2020-04-21 2021-04-21 basées sur le Genre (VBG) Implementation Selection pour le PREC CS-REF-42 / Recrutement Individual assistant en suivi et IDA / D1680 Community Rehabilitation Post Consultant Open 23,077.00 1,176.62 Signed 2019-10-27 2020-04-17 2019-11-23 2020-07-15 2019-12-08 2020-09-07 2020-01-05 2020-11-16 2021-01-04 évaluation dans la région Selection Taoudenit CS-REF-37 / Recrutement Individual assistant en suivi et IDA / D1680 Community Rehabilitation Post Consultant Open 23,077.00 1,176.62 Signed 2019-10-27 2020-04-17 2019-11-23 2020-07-16 2019-12-08 2020-09-07 2020-01-05 2020-11-16 2021-01-04 évaluation dans la région Selection Mopti CS-REF-38 / Recrutement Individual assistant en suivi et IDA / D1680 Community Rehabilitation Post Consultant Open 23,077.00 1,176.62 Signed 2019-10-27 2020-04-17 2019-11-23 2020-07-17 2019-12-08 2020-09-07 2020-01-05 2020-11-16 2021-01-04 évaluation dans la région de Selection Gao CS-REF-40 / Recrutement Individual assistant en suivi et IDA / D1680 Community Rehabilitation Post Consultant Open 23,077.00 1,176.62 Signed 2019-10-27 2020-04-17 2019-11-23 2020-07-15 2019-12-08 2020-09-07 2020-01-05 2020-11-16 2021-01-04 évaluation dans la région Selection Kidal CS-REF-41 / Recrutement Individual assistant en suivi et IDA / D1680 Community Rehabilitation Post Consultant Open 23,077.00 1,176.62 Signed 2020-04-01 2020-04-17 2020-04-28 2020-07-15 2020-05-13 2020-09-07 2020-05-28 2020-11-16 2021-05-28 évaluation dans la région Selection Menaka Page 11 PROCUREMENT PLAN (Textual Part) Project information: Sierra Leone: Financial Inclusion (P166601) Project Implementation agency: Ministry of Finance/Bank of Sierra Leone Date of the Procurement Plan: February 4, 2019 Period covered by this Procurement Plan: 18 months Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in The Public Procurement Act 2016, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable; Works: is not applicable Other Relevant Procurement Information. None PROCUREMENT Sierra Leone : Sierra Leone Financial Inclusion Project PLAN General Information Country: Sierra Leone Bank’s Approval Date of the Original Procurement Plan: 2019-02-08 2021-05-18 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P166601 GPN Date: Project Name: Sierra Leone Financial Inclusion Project Loan / Credit No: / , IDA / 63670 Ministry of Finance and Economic Development Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SL-MOFED-97393-GO-RFB / Ensuring the Viability of the Procure hardware and Single Stage - One IDA / 63670 Payments System through Post Request for Bids Open - National 300,000.00 0.00 Canceled 2019-06-10 2019-06-15 2019-07-27 2019-08-26 2019-09-30 2020-03-28 software equipment required Envelope Increasing Usage for upgrading of cybersecurity SL-MOFED-97090-GO-RFB / Procure hardware and Ensuring the Viability of the Single Stage - One software and services to IDA / 63670 Payments System through Post Request for Bids Open - International 400,000.00 0.00 Canceled 2019-05-27 2019-06-01 2019-07-13 2019-08-12 2019-09-16 2020-03-14 Envelope facilitate govt payment via Increasing Usage electronic methods SL-MOFED-96910-GO-RFB / Ensuring the Viability of the Supply and install POS Single Stage - One IDA / 63670 Payments System through Prior Request for Bids Open - International 450,000.00 0.00 Canceled 2020-07-06 2020-07-11 2020-08-22 2020-09-21 2020-10-26 2021-04-24 terminals and provide Envelope Increasing Usage maintenance/servicing SL-MOFED-97381-GO-RFB / Local firm to provide needed Ensuring the Viability of the hardware/software to Single Stage - One IDA / 63670 Payments System through Post Request for Bids Open - International 850,000.00 0.00 Canceled 2020-10-12 2020-10-17 2020-11-28 2020-12-28 2021-02-01 2021-07-31 facilitate rural connectivity to Envelope Increasing Usage the payments system for rural financial service providers SL-MOFED-96344-GO-RFP / Enhancing Interoperability of Single Stage - One Procurement of the National IDA / 63670 Prior Request for Bids Open - International 5,500,000.00 3,900,000.00 Signed 2019-04-29 2020-02-05 2019-05-04 2020-04-08 2019-06-15 2020-04-30 2019-07-15 2020-09-25 2019-08-19 2021-02-05 2022-02-28 Digital Payments Envelope Switch System of Sierra Leone SL-MOFED-173341-GO-RFQ / Supply of Office Project Implementation Request for Single Stage - One IDA / 63670 Post Limited 44,138.00 37,252.90 Completed 2020-05-15 2020-06-11 2020-06-04 2020-08-05 2020-06-18 2020-08-19 Equipments, furnitures & Support Quotations Envelope Stationery SL-MOFED-201699-GO-RFQ Project Implementation Request for Single Stage - One / Procurement of (one) 4*4 IDA / 63670 Post Limited 60,000.00 57,778.76 Completed 2020-11-10 2020-12-03 2021-01-05 2020-12-22 2021-07-04 2021-03-26 Support Quotations Envelope station wagon for SLFIP PIU. SL-MOFED-232920-GO-RFQ Pending Project Implementation Request for Single Stage - One / Procurement of Light IDA / 63670 Post Limited 6,000.00 0.00 Implementati 2021-06-21 2021-08-16 2022-02-12 Support Quotations Envelope Equipment for Switch unit on NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SL-MOFED-96373-CS-CQS / Hiring an international firm to Consultant Enhancing Interoperability of conduct system testing for / Post Qualification Open - International 200,000.00 0.00 Canceled 2019-06-10 2019-07-01 2019-08-14 2019-09-13 2019-10-18 2020-04-15 Digital Payments user acceptance and Selection supporting tools and systems SL-MOFED-96383-CS-CQS / Consultant Hire a firm to conduct security Enhancing Interoperability of / Post Qualification Open - National 200,000.00 0.00 Canceled 2019-06-17 2019-07-08 2019-08-21 2019-09-20 2019-10-25 2020-04-22 audit and network penetration Digital Payments Selection tests SL-MOFED-97067-CS-QCBS / Hire a firm to develop national stanfdards for mobile wallets and provide business advisory services to drive Ensuring the Viability of the Quality And Cost- access point innovation / Payments System through Prior Open - International 500,000.00 0.00 Canceled 2019-03-25 2019-04-15 2019-05-29 2019-06-26 2019-07-26 2019-08-30 2019-10-04 2020-10-03 Based Selection including developing a Increasing Usage national standard for mobile wallets and to provide implementation training and technical support SL-MOFED-97390-CS-CQS / Hire a firm to conduct Ensuring the Viability of the Consultant cybersecurity testing and IDA / 63670 Payments System through Post Qualification Open - International 200,000.00 0.00 Canceled 2019-05-27 2019-06-17 2019-07-31 2019-08-30 2019-10-04 2020-04-01 implementation plan for BSL Increasing Usage Selection and training for private banks Page 1 SL-MOFED-97376-CS-CQS / Local firm to conduct needs Ensuring the Viability of the Consultant assessment of identifying IDA / 63670 Payments System through Post Qualification Open - National 100,000.00 0.00 Canceled 2019-04-22 2019-05-13 2019-06-26 2019-07-26 2019-08-30 2020-02-26 opportunities for rural Increasing Usage Selection connectivity of the retail payment system SL-MOFED-97383-CS-CQS / Hire a firm to support implementation of improvements necessary to Ensuring the Viability of the Quality And Cost- connect the payments system IDA / 63670 Payments System through Post Open - International 400,000.00 0.00 Canceled 2020-11-02 2020-11-23 2021-01-06 2021-02-03 2021-03-05 2021-04-09 2021-05-14 2022-05-14 Based Selection for rural financial service Increasing Usage providers, including training on core banking applications and support on data migration SL-MOFED-97379-CS-CQS / Local firm to conduct assessment of opportunities Ensuring the Viability of the Consultant to facilitate the connectivity IDA / 63670 Payments System through Post Qualification Open - National 100,000.00 0.00 Canceled 2019-05-27 2019-06-17 2019-07-31 2019-08-30 2019-10-04 2020-04-01 for Apex Banks and member Increasing Usage Selection community banks and FSAs to the payment system SL-MOFED-161815-CS-CQS Ensuring the Viability of the Consultant / Firm to conduct rural IDA / 63670 Payments System through Post Qualification Open - International 100,000.00 97,500.00 Signed 2020-02-28 2020-02-28 2020-03-20 2020-03-12 2020-05-03 2020-05-22 2020-06-02 2020-06-11 2020-07-07 2020-08-25 2021-01-03 connectivity assessment of Increasing Usage Selection the Retail Payment System SL-MOFED-233045-CS-LCS / Project Implementation Least Cost Pending Hire an audit firm to conduct IDA / 63670 Post Open - National 8,000.00 0.00 2021-07-08 2021-07-29 2021-09-11 2021-10-09 2021-11-08 2021-12-13 2022-01-17 2022-07-16 Support Selection Implementation Financial Audit SL-MOFED-233425-CS-QCBS / Hire an International firm to Enhancing Interoperability of Quality And Cost- Pending conduct system testing for IDA / 63670 Post Open - International 200,000.00 0.00 2021-06-09 2021-06-30 2021-08-13 2021-09-10 2021-10-10 2021-11-14 2021-12-19 2022-12-19 Digital Payments Based Selection Implementation user acceptance and supporting tools and systems SL-MOFED-233427-CS-QCBS / Hire a firm to conduct Ensuring the Viability of the Quality And Cost- Under Cybersecurity assessment, IDA / 63670 Payments System through Post Open - International 200,000.00 0.00 2021-05-10 2021-05-11 2021-05-31 2021-05-21 2021-07-14 2021-08-11 2021-09-10 2021-10-15 2021-11-19 2022-11-19 Based Selection Implementation testing, implementation plan, Increasing Usage and capacity building for BSL. SL-MOFED-234182-CS-CQS Ensuring the Viability of the Consultant Under / Hire a firm to Develop a IDA / 63670 Payments System through Post Qualification Open - International 70,000.00 0.00 2021-05-14 2021-05-19 2021-06-04 2021-05-21 2021-07-18 2021-08-17 2021-09-21 2022-03-20 Implementation USSD Regulatory Policy Work Increasing Usage Selection INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SL-MOFED-96357-CS-INDV / Hiring a consultant to support Individual sustainable business model Enhancing Interoperability of / Post Consultant Open 100,000.00 0.00 Canceled 2019-04-22 2019-06-10 2019-07-01 2019-08-05 2020-02-01 for the national switch and Digital Payments Selection develop national switch operating procedures SL-MOFED-96368-CS-INDV / Individual Hire a consultant to support Enhancing Interoperability of / Post Consultant Open 150,000.00 0.00 Canceled 2019-04-22 2019-06-10 2019-07-01 2019-08-05 2020-02-01 implementation of the Digital Payments Selection national switch SL-MOFED-97397-CS-INDV / Hire an international Ensuring the Viability of the Individual consultant to support the Pending IDA / 63670 Payments System through Post Consultant Open 100,000.00 0.00 2019-04-22 2019-06-10 2019-07-01 2019-08-05 2020-02-01 development and Implementation Increasing Usage Selection implementation of financial awareness efforts SL-MOFED-97396-CS-INDV / Hire an international Ensuring the Viability of the Individual consultant to conduct legal IDA / 63670 Payments System through Post Consultant Limited 85,000.00 0.00 Canceled 2019-04-15 2019-04-20 2019-05-11 2019-06-15 2019-12-12 review of the payments Increasing Usage Selection legislation and to update the regulatory framework SL-MOFED-97401-CS-INDV / Individual Hire a consultant to develop Project Implementation Under IDA / 63670 Post Consultant Limited 20,000.00 0.00 2019-02-18 2019-02-21 2019-02-23 2019-02-21 2019-03-16 2019-04-03 2019-04-20 2019-10-17 the Project Implementation Support Implementation Selection Manual SL-MOFED-98272-CS-INDV / Hire a local consultant to facilitate implementation of Individual Project Implementation component 2b (rural IDA / 63670 Post Consultant Open 200,000.00 0.00 Canceled 2019-03-11 2019-04-29 2019-05-20 2019-06-24 2019-12-21 Support connectivity) of the project Selection and work with Apex Bank and the private sector committee SL-MOFED-96347-CS-INDV / Hire an international Individual Enhancing Interoperability of consultant to support the IDA / 63670 Post Consultant Open 75,000.00 0.00 Canceled 2019-02-22 2019-03-19 2019-04-12 2019-05-03 2019-06-07 2019-12-04 Digital Payments procurement of the national Selection switch SL-MOFED-97405-CS-INDV / Hire an international Individual consultant to support the Project Implementation IDA / 63670 Post Consultant Open 100,000.00 0.00 Canceled 2019-05-27 2019-07-15 2019-08-05 2019-09-09 2020-03-07 private sector committee Support Selection including its design and capacity building SL-MOFED-102104-CS-INDV Individual / Hire a consultant to support Enhancing Interoperability of IDA / 63670 Post Consultant Open 75,000.00 0.00 Canceled 2019-02-22 2019-03-19 2019-04-12 2019-05-03 2019-06-07 2019-12-04 the procurement of the Digital Payments Selection national switch Page 2 SL-MOFED-96363-CS-INDV / Individual Enhancing Interoperability of Hire a Switch Technical IDA / 63670 Prior Consultant Open 200,000.00 0.00 Canceled 2019-03-04 2019-04-22 2019-05-13 2019-06-17 2020-06-17 Digital Payments Advisor Selection SL-MOFED-97531-CS-INDV / Recruitment of a local consultant (Project Individual Coordinator) to facilitate Project Implementation IDA / 63670 Prior Consultant Open 300,000.00 0.00 Canceled 2019-02-14 2019-02-20 2019-04-04 2019-04-25 2019-05-30 2022-12-30 implementation pf the Support Selection project(SLFIP) for component 1 and the private sector committee SL-MOFED-103855-CS-INDV Individual Project Implementation / Recruitment of a Project IDA / 63670 Post Consultant Open 100,000.00 0.00 Canceled 2019-03-04 2019-03-04 2019-04-22 2019-05-13 2019-06-17 2020-06-17 Support Coordinator Selection SL-MOFED-104783-CS-INDV / Hire a local consultant to facilitate implementation of Ensuring the Viability of the Individual component 2b (rural IDA / 63670 Payments System through Post Consultant Open 100,000.00 0.00 Canceled 2019-03-11 2019-03-07 2019-04-29 2019-05-20 2019-06-24 2020-06-24 connectivity) of the project Increasing Usage Selection and work with Apex Bank and the Private Sector Committees SL-MOFED-97395-CS-INDV / Hire an international Ensuring the Viability of the Individual consultant to develop the IDA / 63670 Payments System through Post Consultant Limited 15,000.00 0.00 Canceled 2019-03-20 2019-03-25 2019-04-15 2019-05-15 2019-11-11 USSD (Unstructued Increasing Usage Selection Supplementary Service Data) regulations SL-MOFED-141688-CS-CDS / Hire a consultant to support Project Implementation IDA / 63670 Post Direct Selection Direct 80,000.00 100,588.66 Signed 2019-10-21 2019-10-21 2019-10-22 2019-10-23 2019-11-04 2019-11-13 2020-11-03 the procurement of the Support national switch SL-MOFED-141700-CS-CDS / Hire an international consultant to conduct legal Enhancing Interoperability of IDA / 63670 Post Direct Selection Direct 85,000.00 64,000.00 Signed 2019-10-22 2019-10-21 2019-11-01 2019-10-23 2019-12-14 2019-11-14 2021-07-14 review of the payments Digital Payments legislation and to update the regulatory framework SL-MOFED-142565-CS-INDV Individual / Recruitment of Local Project Implementation IDA / 63670 Post Consultant Open 75,000.00 72,000.00 Signed 2019-10-25 2019-10-25 2019-11-28 2020-02-25 2019-11-30 2020-03-23 2019-12-14 2020-05-07 2020-12-13 Consultant as a Project Support Selection Coordinator SL-MOFED-154612-CS-INDV Individual Enhancing Interoperability of / Payment Switch IDA / 63670 Post Consultant Open 175,000.00 174,302.04 Signed 2020-01-24 2020-01-21 2020-02-26 2020-03-13 2020-03-02 2020-04-09 2020-03-23 2020-08-04 2021-03-23 Digital Payments Implementation Manager Selection SL-MOFED-166452-CS-INDV / Hire a Payment Systems Ensuring the Viability of the Individual consultant (PSC) to help IDA / 63670 Payments System through Post Consultant Open 75,000.00 123,000.00 Signed 2020-03-27 2020-03-29 2020-05-15 2020-07-29 2020-06-05 2020-11-02 2020-07-10 2020-11-06 2021-01-06 operationalize the Sierra Increasing Usage Selection Leone National switch. SL-MOFED-186420-CS-INDV / A MAPPING OF Ensuring the Viability of the Individual GOVERNMENT PAYMENTS IDA / 63670 Payments System through Post Consultant Open 30,000.00 29,000.00 Signed 2020-07-31 2020-08-07 2020-09-18 2020-10-01 2020-10-09 2020-10-19 2020-11-13 2020-12-14 2021-05-12 FOR THE FINANCIAL Increasing Usage Selection INCLUSION PROJECT SL-MOFED-201696-CS-INDV Ensuring the Viability of the Individual / Hire a consultant to conduct IDA / 63670 Payments System through Post Consultant Open 30,000.00 0.00 Canceled 2020-10-28 2020-10-30 2020-11-24 2020-12-04 2020-12-18 2021-03-18 an assessment of the digital Increasing Usage Selection payment access point. SL-MOFED-164068-CS-INDV Ensuring the Viability of the Individual / Develop the USSD Policy and IDA / 63670 Payments System through Post Consultant Limited 25,000.00 0.00 Canceled 2020-03-13 2020-03-13 2020-03-20 2020-04-24 2020-10-21 Regulatory Work Increasing Usage Selection SL-MOFED-225242-CS-INDV Ensuring the Viability of the Individual / Develop the USSD policy and IDA / 63670 Payments System through Post Consultant Open 36,000.00 0.00 Canceled 2021-03-12 2021-03-24 2021-04-30 2021-05-21 2021-06-25 2021-12-22 Regulatory Work Increasing Usage Selection SL-MOFED-233046-CS-INDV / Hire the services of a Individual communications consultant to Enhancing Interoperability of Pending IDA / 63670 Post Consultant Open 20,000.00 0.00 2021-08-19 2021-10-07 2021-10-28 2021-12-02 2022-05-31 develop a concise Digital Payments Implementation Selection communication plan for switch roll out SL-MOFED-233047-CS-INDV Individual / Hire Technical Adviser to Project Implementation Pending IDA / 63670 Post Consultant Open 50,000.00 0.00 2021-06-30 2021-08-18 2021-09-08 2021-10-13 2022-04-11 support activities from Rural Support Implementation Selection Connectivity Page 3 WATER AND SANITATION DEVELOPMENT PROJECT (WSDP) SUMMARY PROCUREMENT PLAN (first eighteen months) I. General The following procurement plan has been developed for project implementation during the first eighteen months and provides the basis for the procurement methods and bank prior/post review thresholds. It covers the three categories, namely, Works; Consultancies; and Goods. The plan will be updated when need arises to reflect the actual project implementation needs. 1. Project information: Country / Borrower: Republic of Kenya Project: Water and Sanitation Development Project (WSDP) IDA Credit No. 6029 & 6030 Project Implementing Agencies: (a) Ministry of Water and Irrigation, (b) WaSREB, (c) Water Service Providers: Kilifi-Mariakani Water and Sewerage Company (Kimawasco),; Taita-Voi Water and Sewerage Company (Tavevo); Mombasa Water Supply and Sanitation Company (Mowassco); Kwale Water and Sewerage Company (Kwawasco); Garissa Water and Sewerage Company (Gawasco); Wajir Water and Sewerage Company (Wajwasco); and Malindi Water and Sewerage Company; and (d) Counties: Kilifi; Taita Taveta; Mombasa; Kwale; Garissa; and Wajir 2. Bank’s approval Date of the First Eighteen Months’ Procurement Plan: June 15, 2017 3. Date of General Procurement Notice: June 14, 2017 4. Period covered by this procurement plan: June 2017 to December 2018 II: Works, Goods and Consultancy Services: Thresholds for Procurement Methods and Bank’s Prior Review The Table below provides the details of Thresholds for Procurement Methods and Bank’s Prior Review for Works, Goods and Consultancy Services Page 1 of 2 Contract Value (Threshold) Procurement Expenditure Contract Subject to Category (US$ 000) Method Prior Review 1. Works 15,000 or more ICB Contracts above $5 million Below 15,000 NCB First contract per entity and Contracts above $5 million Below or equal Shopping None unless contract 200 specified in the PP No threshold Direct As specified in PP Contracting 2. Goods 1,000 or more ICB First contract per entity and Contracts above $1.5 million Below 1,000 NCB First contract per entity Below or equal Shopping None unless contract to 100 specified in the PP No threshold Direct As specified in PP Contracting 3. Consultancy Firms* QCBS,LCS,FBS, First contract per Services QBS entity and Contracts above $0.5 million Firms* CQS First contract per (Estimated cost entity less than $300,000) Individual IC (at least 3 All contract of CVs) estimated cost above $200,000 and more No threshold Single Source All *Assignments whose estimated cost is less $300,000 could be Open-National (Shortlist could comprise of all national firms) NB: All terms of reference for consulting services will be subject to IDA’s prior review. Page 2 of 2 PROCUREMENT Kenya : Water and Sanitation Development Project PLAN General Information Country: Kenya Bank’s Approval Date of the Original Procurement Plan: 2019-10-08 2021-05-23 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P156634 GPN Date: 2017-06-13 Project Name: Water and Sanitation Development Project Loan / Credit No: IDA / 60300, IDA / 60290 W Executing Agency(ies): ater Sector Trust Fund WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KE-WSTF-234306-GO-RFB / Component 3: National Purchase of Three Units Under performance-based financing Single Stage - One Special Duty, Utility Passenger IDA / 60300 Post Request for Bids Open - National 240,000.00 0.00 Implementati 2021-05-21 2021-05-31 2021-05-26 2021-06-25 2021-07-09 2021-08-06 2021-11-04 (PBF) (US$40.7 of which IDA- Envelope Caravan Vehicle, 4x4, L.W.B, on SUF US$37 million). 2900-4200cc, Diesel NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KE- WASREB-134249-CS- QCBS / Consultancy Services for Initial Assessment of Component 3: National Suitability and Design of performance-based financing Quality And Cost- Under Performance Based Contracts IDA / 60300 Post Open - International 496,800.00 487,400.00 2019-09-25 2019-10-08 2019-10-16 2020-02-17 2019-11-29 2021-03-10 2019-12-27 2021-03-26 2020-01-26 2021-04-12 2020-03-01 2021-05-18 2020-04-05 2021-08-03 (PBF) (US$40.7 of which IDA- Based Selection Implementation (PBCs) for Non Revenue Water SUF US$37 million). (NRW) Reduction for a Cluster of Six (6) Water Service Providers (WSPs) INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 3: National KE-WSTF-207294-CS-INDV / Individual performance-based financing Consultancy Services for IDA / 60300 Post Consultant Limited 150,000.00 90,487.22 Signed 2020-12-06 2021-03-17 2020-12-27 2021-05-12 2021-01-03 2021-05-31 2021-01-24 2021-06-07 2022-10-31 (PBF) (US$40.7 of which IDA- Financial expert. Selection SUF US$37 million). KE-WSTF-207303-CS-INDV / Component 3: National Consultancy Services for Individual performance-based financing Environmental and Social IDA / 60300 Post Consultant Limited 150,000.00 90,487.22 Signed 2020-12-06 2021-03-31 2020-12-27 2021-05-12 2021-01-03 2021-05-31 2021-01-24 2021-06-07 2022-10-31 (PBF) (US$40.7 of which IDA- Impact Assessment (ESIA) Selection SUF US$37 million). expert. KE-WSTF-207239-CS-CDS / Component 3: National Individual Consultancy performance-based financing Services - Program Manager IDA / 60290 Post Direct Selection Direct 212,250.00 191,182.29 Signed 2020-11-30 2021-04-15 2020-12-10 2021-05-31 2020-12-19 2021-01-01 2022-10-31 (PBF) (US$40.7 of which IDA- for implementation of the SUF US$37 million). NPBF program. Page 1 PROCUREMENT PLAN (Textual Part) Project information: [Nigeria] [Innovation Development and Effectiveness in the Acquisition of Skills (IDEAS) Project] [P-166239] Project Implementation Agency: [Federal Ministry of Education] Date of the Procurement Plan: [2109/10/24] Period covered by this Procurement Plan: [October 24, 2019 – April 23, 2020] Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016, Revised November 2017, August 2018 (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. - “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables - “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Not Applicable. Goods: Not Applicable Works: Not Applicable Consultancy: Not Applicable Hands-on Expanded Implementation Support (HEIS): Not Applicable PROCUREMENT Nigeria : Innovation Development and Effectiveness in the Acquisition of Skills (IDEAS) Project PLAN General Information Country: Nigeria Bank’s Approval Date of the Original Procurement Plan: 2021-05-20 2021-05-20 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P166239 GPN Date: Project Name: Innovation Development and Effectiveness in the Acquisition of Skills (IDEAS) Project Loan / Credit No: IDA / 65140 Benue IDEAS Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Incentivizing partnerships NG-BENUE IDEAS-231697- with industry for enhanced Pending Request for Single Stage - One GO-RFQ / Vehicle: 1 no. 2.7 IDA / 65140 quality and labour-market Post Limited 65,000.00 0.00 Implementati 2021-05-15 2021-07-10 2022-01-06 Quotations Envelope Hilux van orientation of public on Technical Colleges Incentivizing partnerships with industry for enhanced Pending NG-BENUE IDEAS-231821- Request for Single Stage - One IDA / 65140 quality and labour-market Post Limited 7,500.00 0.00 Implementati 2021-05-21 2021-07-16 2022-01-12 GO-RFQ / Office Furniture Quotations Envelope orientation of public on Technical Colleges Incentivizing partnerships with industry for enhanced Pending NG-BENUE IDEAS-231851- Request for Single Stage - One IDA / 65140 quality and labour-market Post Limited 25,625.00 0.00 Implementati 2021-06-04 2021-07-30 2022-01-26 GO-RFQ / Office equipment Quotations Envelope orientation of public on Technical Colleges Incentivizing partnerships NG-BENUE IDEAS-231877- with industry for enhanced Pending Request for Single Stage - One GO-RFQ / upgrades of IDA / 65140 quality and labour-market Post Limited 1,875.00 0.00 Implementati 2021-06-12 2021-08-07 2022-02-03 Quotations Envelope facilities orientation of public on Technical Colleges NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Incentivizing partnerships NG-BENUE IDEAS-231888-CS- with industry for enhanced Individual INDV / Consultancy support Pending IDA / 65140 quality and labour-market Post Consultant Limited 16,500.00 0.00 2021-05-31 2021-06-05 2021-06-26 2021-07-31 2021-09-29 needed to design Implementation orientation of public Selection communication strategy Technical Colleges NG-BENUE IDEAS-231890-CS- INDV / Consultancy to Incentivizing partnerships maintain curriculum relevance with industry for enhanced Individual Pending and providing targeted IDA / 65140 quality and labour-market Post Consultant Limited 16,000.00 0.00 2021-06-07 2021-06-12 2021-07-03 2021-08-07 2021-09-06 Implementation benefits to graduate in order orientation of public Selection to enhance the marketability Technical Colleges of IDEAS Project NG-BENUE IDEAS-237568-CS- INDV / Consultancy for Development of modern Individual Improving skills formation in Pending technology in the acquisition IDA / 65140 Post Consultant Limited 18,000.00 0.00 2021-06-13 2021-06-18 2021-07-09 2021-08-13 2021-09-12 the informal sector Implementation of skills for development is Selection necessary if the IDEAS project will achieve its PDO. Page 1 PROCUREMENT PLAN (Textual Part) Project information: [Nigeria] [Innovation Development and Effectiveness in the Acquisition of Skills (IDEAS) Project] [P-166239] Project Implementation Agency: [Federal Ministry of Education] Date of the Procurement Plan: [2109/10/24] Period covered by this Procurement Plan: [October 24, 2019 – April 23, 2020] Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016, Revised November 2017, August 2018 (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. - “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables - “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Not Applicable. Goods: Not Applicable Works: Not Applicable Consultancy: Not Applicable Hands-on Expanded Implementation Support (HEIS): Not Applicable PROCUREMENT Nigeria : Innovation Development and Effectiveness in the Acquisition of Skills (IDEAS) Project PLAN General Information Country: Nigeria Bank’s Approval Date of the Original Procurement Plan: 2021-05-21 2021-05-21 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P166239 GPN Date: Project Name: Innovation Development and Effectiveness in the Acquisition of Skills (IDEAS) Project Loan / Credit No: IDA / 65140 National Board for Technical Education Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Strengthening the regulatory PMU/IDEAS/CW/02/21 / environment and public Request for Pending Upgrade Facilities and Request for Single Stage - One 2022-02- IDA / 65140 management capacities for Post Limited Quotations (Non 200,000.00 0.00 Implementat 2021-07-03 2021-08-28 Systems in Skills Development Quotations Envelope 24 market-oriented skills Bank-SPD) ion Agencies development Strengthening the regulatory PMU/IDEAS/CW/01/21 / environment and public Request for Pending Request for Single Stage - One 2022-02- Renovation/Rehabilitation of IDA / 65140 management capacities for Post Limited Quotations (Non 200,000.00 0.00 Implementat 2021-07-03 2021-08-28 Quotations Envelope 24 Project Office in Kaduna market-oriented skills Bank-SPD) ion development GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PMU/IDEAS/GO/05/21 / Strengthening the regulatory Procurement of Project environment and public Pending Request for Single Stage - One Vehicles for Project Office in IDA / 65140 management capacities for Post Limited 127,000.00 0.00 Implementati 2021-07-19 2021-09-13 2022-03-12 Quotations Envelope Kaduna (Multiple Contracts) - market-oriented skills on 2 Lots development Strengthening the regulatory PMU/IDEAS/GO/03/21 / environment and public Pending Establishment of Management Single Stage - One IDA / 65140 management capacities for Post Request for Bids Limited 300,000.00 0.00 Implementati 2021-07-12 2021-07-17 2021-08-28 2021-09-27 2021-11-01 2022-04-30 Information (MIS) for Kaduna Envelope market-oriented skills on Office development Strengthening the regulatory PMU/IDEAS/GO/04/21 / environment and public Pending Procurement of Office Single Stage - One IDA / 65140 management capacities for Post Request for Bids Limited 200,000.00 0.00 Implementati 2021-07-27 2021-08-01 2021-09-12 2021-10-12 2021-11-16 2022-05-15 Furniture and ICT Equipment Envelope market-oriented skills on for Project Office in Kaduna development PMU/IDEAS/GO/01/21 / Strengthening the regulatory Procurement of Database environment and public Pending Single Stage - One Hardware for the National IDA / 65140 management capacities for Post Request for Bids Open - National 200,000.00 0.00 Implementati 2021-06-30 2021-09-15 2021-09-15 2021-07-05 2021-11-24 2021-12-24 2022-01-28 2023-07-22 Envelope Skills Qualification Framework market-oriented skills on (NSQF) Roll-out development NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Strengthening the regulatory PMU/IDEAS/GO/02/21 / environment and public Pending Production of Materials for Request for Single Stage - One IDA / 65140 management capacities for Post Limited 100,000.00 0.00 Implementati 2021-07-05 2021-08-30 2022-02-26 National Skills Qualification Quotations Envelope market-oriented skills on Framework (NSQF) development CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Incentivizing partnerships PMU/IDEAS/CS/01/21 / with industry for enhanced Consultant Prepare and conduct Pending IDA / 65140 quality and labour-market Post Qualification Limited 150,000.00 0.00 2021-06-08 2021-06-22 2021-07-22 2021-08-26 2022-02-22 foundational skills Implementation orientation of public Selection assessment and follow-up Technical Colleges Incentivizing partnerships PMU/IDEAS/CS/02/21 / with industry for enhanced Consultant Pending Support for IDP Development IDA / 65140 quality and labour-market Post Qualification Limited 252,000.00 0.00 2021-06-15 2021-06-29 2021-07-29 2021-09-02 2022-03-01 Implementation STCs orientation of public Selection Technical Colleges Incentivizing partnerships PMU/IDEAS/CS/03/21 / with industry for enhanced Consultant Pending Review and Development of IDA / 65140 quality and labour-market Post Qualification Limited 125,000.00 0.00 2021-06-22 2021-07-06 2021-08-05 2021-09-09 2022-03-08 Implementation Curricula for TCs orientation of public Selection Technical Colleges PMU/IDEAS/CS/14/21 / Consultant Digital /ICT Consultant to Improving skills formation in Pending IDA / 65140 Post Qualification Limited 200,000.00 0.00 2021-07-19 2021-08-02 2021-09-01 2021-10-06 2022-04-04 support the integration of ICT the informal sector Implementation Selection in Apprenticeship PMU/IDEAS/CS/16/21 / TA to facilitate implementation of Consultant Improving skills formation in Pending apprenticeship system & IDA / 65140 Post Qualification Limited 300,000.00 0.00 2021-06-25 2021-07-09 2021-08-08 2021-09-12 2022-03-11 the informal sector Implementation provide support to Selection apprentices Page 1 PMU/IDEAS/CS/17/21 / Consultant Develop training plans, Improving skills formation in Pending IDA / 65140 Post Qualification Limited 280,000.00 0.00 2021-06-28 2021-07-12 2021-08-11 2021-09-15 2022-03-14 manuals, curricula and the informal sector Implementation Selection assessment instruments Strengthening the regulatory PMU/IDEAS/CS/26/21 / environment and public Consultant Pending Baseline Study for Informal IDA / 65140 management capacities for Post Qualification Open - National 200,000.00 0.00 2021-08-17 2021-09-07 2021-10-21 2021-11-20 2021-12-25 2022-06-23 Implementation Sector market-oriented skills Selection development PMU/IDEAS/CS/27/21 / Strengthening the regulatory Development of Software for environment and public Consultant Pending the National Skills IDA / 65140 management capacities for Post Qualification Limited 300,000.00 0.00 2021-06-30 2021-07-14 2021-08-13 2021-09-17 2022-03-16 Implementation Qualification Framework market-oriented skills Selection (NSQF) Roll-out development PMU/IDEAS/CS/30/21 / Strengthening the regulatory Support to the Development environment and public Consultant of Sector Skills Councils (SSCs) Pending IDA / 65140 management capacities for Post Qualification Limited 250,000.00 0.00 2021-08-23 2021-09-06 2021-10-06 2021-11-10 2022-05-09 and National Council on Skills Implementation market-oriented skills Selection (NCS) - Coordinating development Consultant PMU/IDEAS/CS/39/21 / Strengthening the regulatory Engagement of External environment and public Consultant Pending Consultants for Monitoring IDA / 65140 management capacities for Post Qualification Limited 250,000.00 0.00 2021-08-30 2021-09-13 2021-10-13 2021-11-17 2022-05-16 Implementation and Evaluation of Project market-oriented skills Selection activities development Incentivizing partnerships PMU/IDEAS/CS/04/21 / with industry for enhanced Consultant Review and Development of Pending IDA / 65140 quality and labour-market Post Qualification Limited 125,000.00 0.00 2021-06-20 2021-07-04 2021-08-03 2021-09-07 2022-03-06 Curricula for TCs on Building Implementation orientation of public Selection and Carpentry trades Technical Colleges Incentivizing partnerships PMU/IDEAS/CS/06/21 / with industry for enhanced Consultant Review and Development of Pending IDA / 65140 quality and labour-market Post Qualification Limited 125,000.00 0.00 2021-07-19 2021-08-02 2021-09-01 2021-10-06 2022-04-04 Curricula for TCs on Electrical Implementation orientation of public Selection and Electronics Technology Technical Colleges Incentivizing partnerships PMU/IDEAS/CS/05/21 / with industry for enhanced Consultant Review and Development of Pending IDA / 65140 quality and labour-market Post Qualification 125,000.00 0.00 2021-07-12 2021-07-26 2021-08-25 2021-09-29 2022-03-28 Curricula for TCs on Auto Implementation orientation of public Selection Mechanics Technical Colleges PMU/IDEAS/CS/28/21 / Institutionalisation of National Strengthening the regulatory Skills Qualification Framework environment and public Consultant NSQF- Technical Assistants to Pending IDA / 65140 management capacities for Post Qualification Limited 300,000.00 0.00 2021-08-09 2021-08-23 2021-09-22 2021-10-27 2022-04-25 support NBTE in the Implementation market-oriented skills Selection Institutionalisation of of NSQF development and Recognition of Prior Learning System (RPL) PMU/IDEAS/CS/33/21 / Strengthening the regulatory Review/Development of environment and public Consultant Existing/New National Pending IDA / 65140 management capacities for Post Qualification Limited 300,000.00 0.00 2021-07-05 2021-07-19 2021-08-18 2021-09-22 2022-03-21 Occupational Standards (NOS) Implementation market-oriented skills Selection for at least 10 NOS (In development different Sectors)- Phase 1 PMU/IDEAS/CS/31/21 / Support to the Development Consultant of Sector Skills Councils (SSCs)- Improving skills formation in Pending IDA / 65140 Post Qualification Limited 250,000.00 0.00 2021-08-23 2021-09-06 2021-10-06 2021-11-10 2022-05-09 To support the Development the informal sector Implementation Selection of Sector Skills Council in Nigeria Strengthening the regulatory PMU/IDEAS/CS/34/21 / environment and public Consultant Content Development for Pending IDA / 65140 management capacities for Post Qualification Limited 200,000.00 0.00 2021-09-06 2021-09-20 2021-10-20 2021-11-24 2022-05-23 Skills Training (and internal Implementation market-oriented skills Selection capacity) - Phase 1 development PMU/IDEAS/CS/32/21 / Strengthening the regulatory Support to the National environment and public Consultant Pending Council on Skills (NCS)- IDA / 65140 management capacities for Post Qualification Limited 250,000.00 0.00 2021-08-23 2021-09-06 2021-10-06 2021-11-10 2022-05-09 Implementation National Council on Skills in market-oriented skills Selection Nigeria development Strengthening the regulatory PMU/IDEAS/CS/35/21 / environment and public Consultant Pending Development of Recognition IDA / 65140 management capacities for Post Qualification Limited 300,000.00 0.00 2021-08-31 2021-09-14 2021-10-14 2021-11-18 2022-05-17 Implementation of Prior Learning (RPL) System market-oriented skills Selection development INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PMU/IDEAS/CS/07/21 / Conduct skills gap (technical, Individual Improving skills formation in Pending digital and foundational) IDA / 65140 Post Consultant Limited 50,000.00 0.00 2021-07-26 2021-07-31 2021-08-21 2021-09-25 2022-03-24 the informal sector Implementation analysis for Apprentices Selection (Coordinating Consultant) PMU/IDEAS/CS/08/21 / Conduct skills gap (technical, Individual Improving skills formation in Pending digital and foundational) IDA / 65140 Post Consultant Limited 50,000.00 0.00 2021-06-30 2021-07-05 2021-07-26 2021-08-30 2022-02-26 the informal sector Implementation analysis for Apprentices - Selection Kano State PMU/IDEAS/CS/09/21 / Conduct skills gap (technical, Individual Improving skills formation in Pending digital and foundational) IDA / 65140 Post Consultant Limited 50,000.00 0.00 2021-07-30 2021-08-04 2021-08-25 2021-09-29 2022-03-28 the informal sector Implementation analysis for Apprentices - Selection Gombe State Page 2 PMU/IDEAS/CS/10/21 / Conduct skills gap (technical, Individual Improving skills formation in Pending digital and foundational) IDA / 65140 Post Consultant Limited 50,000.00 0.00 2021-03-08 2021-03-13 2021-04-03 2021-05-08 2021-11-04 the informal sector Implementation analysis for Apprentices - Selection Benue State PMU/IDEAS/CS/11/21 / Conduct skills gap (technical, Individual Improving skills formation in Pending digital and foundational) IDA / 65140 Post Consultant Limited 50,000.00 0.00 2021-07-30 2021-08-04 2021-08-25 2021-09-29 2022-03-28 the informal sector Implementation analysis for Apprentices - Selection Ekiti State PMU/IDEAS/CS/12/21 / Conduct skills gap (technical, Individual Improving skills formation in Pending digital and foundational) IDA / 65140 Post Consultant Limited 50,000.00 0.00 2021-03-08 2021-03-13 2021-04-03 2021-05-08 2021-11-04 the informal sector Implementation analysis for Apprentices - Edo Selection State PMU/IDEAS/CS/13/21 / Conduct skills gap (technical, Individual Improving skills formation in Pending digital and foundational) IDA / 65140 Post Consultant Open 50,000.00 0.00 2021-03-08 2021-04-26 2021-05-17 2021-06-21 2021-12-18 the informal sector Implementation analysis for Apprentices - Selection Abia State PMU/IDEAS/CS/15/21 / Technical Assisstant to plan, develop and upgrade Individual Improving skills formation in Pending apprenticeship system in IDA / 65140 Post Consultant Limited 150,000.00 0.00 2021-08-30 2021-09-04 2021-09-25 2021-10-30 2022-04-28 the informal sector Implementation Nigeria (Long Term Selection International Individual Consultant) Incentivizing partnerships PMU/IDEAS/CS/19/21 / with industry for enhanced Individual Engagement of Project Pending IDA / 65140 quality and labour-market Post Consultant Limited 50,000.00 0.00 2021-07-12 2021-07-17 2021-08-07 2021-09-11 2022-03-10 Technical Assistants (TA) - Implementation orientation of public Selection Financial Mgmt Technical Colleges Incentivizing partnerships PMU/IDEAS/CS/20/21 / with industry for enhanced Individual Engagement of Project Pending IDA / 65140 quality and labour-market Post Consultant Limited 50,000.00 0.00 2021-06-28 2021-07-03 2021-07-24 2021-08-28 2022-02-24 Technical Assistants (TA) - M Implementation orientation of public Selection &E Technical Colleges Incentivizing partnerships PMU/IDEAS/CS/21/21 / with industry for enhanced Individual Engagement of Project Pending IDA / 65140 quality and labour-market Post Consultant Limited 50,000.00 0.00 2021-06-14 2021-06-19 2021-07-10 2021-08-14 2022-02-10 Technical Assistants (TA) - Implementation orientation of public Selection ICT Technical Colleges Incentivizing partnerships PMU/IDEAS/CS/23/21 / with industry for enhanced Individual Pending Engagement of Project IDA / 65140 quality and labour-market Post Consultant Limited 50,000.00 0.00 2021-06-14 2021-06-19 2021-07-10 2021-08-14 2022-02-10 Implementation Technical Assistants (TA) - HR orientation of public Selection Technical Colleges Incentivizing partnerships PMU/IDEAS/CS/24/21 / with industry for enhanced Individual Engagement of Project Pending IDA / 65140 quality and labour-market Post Consultant Limited 50,000.00 0.00 2021-06-14 2021-06-19 2021-07-10 2021-08-14 2022-02-10 Technical Assistants (TA) - Implementation orientation of public Selection Technical to PMU Technical Colleges Incentivizing partnerships PMU/IDEAS/CS/25/21 / with industry for enhanced Individual Engagement of Project Pending IDA / 65140 quality and labour-market Post Consultant Limited 50,000.00 0.00 2021-06-21 2021-06-26 2021-07-17 2021-08-21 2022-02-17 Technical Assistants (TA) - Implementation orientation of public Selection Informal Sector Technical Colleges Strengthening the regulatory PMU/IDEAS/CS/38/21 / TA environment and public Individual Pending on Innovation (Innovation IDA / 65140 management capacities for Post Consultant Direct 100,000.00 0.00 2021-08-30 2021-09-09 2021-09-30 2021-11-04 2022-05-03 Implementation Grant Manager) market-oriented skills Selection development Incentivizing partnerships PMU/IDEAS/CS/22/21 / with industry for enhanced Individual Engagement of Project Pending IDA / 65140 quality and labour-market Post Consultant Limited 50,000.00 0.00 2021-06-21 2021-06-26 2021-07-17 2021-08-21 2022-02-17 Technical Assistants (TA) - Implementation orientation of public Selection Safeguard Technical Colleges Incentivizing partnerships PMU/IDEAS/CS/18/21 / with industry for enhanced Individual Engagement of Project Pending IDA / 65140 quality and labour-market Post Consultant Limited 50,000.00 0.00 2021-12-05 2021-12-10 2021-12-31 2022-02-04 2022-08-03 Technical Assistants (TA) - Implementation orientation of public Selection Procurement Technical Colleges Page 3 PROCUREMENT PLAN (Textual Part) Project information: Sao Tome and Principe - WACA Resilience Investment Project - P162337 Project Implementation agency: Ministry of Public Works and Natural Resources, Directorate General of Environment Date of the Procurement Plan: July 2017 Period covered by this Procurement Plan: July 1st 2017 to June 30th, 2018 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Regulamento de Licitação e Contratações Publicas such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables: Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables: Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable for those contracts identified in the Procurement Plan tables; Works: is not applicable for those contracts identified in the Procurement Plan tables Other Relevant Procurement Information.: Not Applicable PROCUREMENT Western Africa : West Africa Coastal Areas Resilience Investment Project PLAN General Information Country: Western Africa Bank’s Approval Date of the Original Procurement Plan: 2018-10-04 2021-05-19 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P162337 GPN Date: 2017-12-29 Project Name: West Africa Coastal Areas Resilience Investment Project Loan / Credit No: IDA / D2880, IDA / 62150, IDA / D2860 M Executing Agency(ies): inistry of Environment and Sustainable Development WORKS Procureme Activity Reference No. / Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH nt Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) Justification for Award Type Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MR-MEDD-74186-CW-RFQ / Component 3: Strengthening Mise en place d'une clôture Request for Single Stage - One 2019-07- 2019- IDA / D2880 National Physical and Social Post Limited 36,168.67 Completed 2018-11-10 2019-11-08 2019-01-05 2019-11-13 grillagée autour de la marre à Quotations Envelope 04 11-30 Investments Spartines MR-MEDD-74202-CW-RFQ / Component 3: Strengthening Travaux d'entretien des Request for Single Stage - One 2019-08- IDA / D2880 National Physical and Social Post Limited 0.00 Canceled 2018-12-30 2019-02-24 couloirs de pare-feux du Quotations Envelope 23 Investments Typha au niveau de Diawling MR-MEDD-74205-CW-RFB / Component 4: National Single Stage - Two 2019-08- Construction des sièges de IDA / D2880 Post Request for Bids Open - National 0.00 Canceled 2018-09-03 2018-09-08 2018-10-20 2019-01-02 2019-02-06 Coordination Envelope 05 l'Observatoire et de l'UGP MR-MEDD-75955-CW-RFB / Component 3: Strengthening Single Stage - One 2019-08- Colmatage des brèches du IDA / D2880 National Physical and Social Post Request for Bids Open - National 0.00 Canceled 2018-11-05 2018-11-10 2018-12-22 2019-01-21 2019-02-25 Envelope 24 littoral de NKTT Investments MR-MEDD-75986-CW-RFQ / Component 3: Strengthening Pending Request for Single Stage - One 2019-05- Travaux pour la fixation des IDA / D2880 National Physical and Social Post Limited 0.00 Implementat 2018-10-06 2018-12-01 Quotations Envelope 30 dunes au niveau de Chami Investments ion MR-MEDD-76006-CW-RFQ / Component 3: Strengthening Pending Restauration des éco- Request for Single Stage - One 2019-07- IDA / D2880 National Physical and Social Post Limited 0.00 Implementat 2018-11-20 2019-01-15 systèmes du Parc National Quotations Envelope 14 Investments ion d'Awleigatt (PNA) MR-MEDD-75980-CW-RFQ / Component 3: Strengthening Pending Travaux de fixation de dunes Request for Single Stage - One 2019-06- IDA / D2880 National Physical and Social Post Limited 0.00 Implementat 2018-10-20 2018-12-15 du littoral de NKTT sur un Quotations Envelope 13 Investments ion premier site pilote MR-MEDD-115356-CW-RFQ / Réalisation de clôture Component 3: Strengthening grillagée autour du périmètre Request for Single Stage - One 2019-07- 2019- IDA / D2880 National Physical and Social Post Limited 36,467.31 Completed 2019-05-25 2019-06-13 2019-06-10 2019-06-21 de 15 ha de fixation Quotations Envelope 20 07-22 Investments mécanique et biologique du cordon dunaire de Nouakchott MR-MEDD-115655-CW-RFQ Component 3: Strengthening Request for Single Stage - One 2019-08- 2019- / Fixation de 15 ha de dunes IDA / D2880 National Physical and Social Post Limited 36,984.27 Completed 2019-06-01 2019-06-12 2019-06-11 2019-06-28 Quotations Envelope 10 09-16 du littoral de Nouakchott Investments MR-MEDD-115657-CW-RFQ / Travaux d'entretien de Component 3: Strengthening Under Request for Single Stage - One 2019-07- couloirs de pare-feus pour la IDA / D2880 National Physical and Social Post Limited 0.00 Implementat 2019-05-30 2021-05-19 2019-06-12 Quotations Envelope 12 restauration des mangroves Investments ion au niveau de Diawling MR-MEDD-115659-CW-RFQ Component 3: Strengthening Request for Single Stage - One 2019-07- 2019- / Réalisation de pépinières de IDA / D2880 National Physical and Social Post Limited 34,921.07 Completed 2019-06-08 2019-07-19 2019-06-21 2019-08-01 Quotations Envelope 21 08-29 mangroves au Diawling Investments MR-MEDD-124501-CW-RFQ Component 3: Strengthening / mise en place d'une cloture Request for Single Stage - One 2020-04- 2019- IDA / D2880 National Physical and Social Post Limited 8,464.35 Completed 2019-08-26 2019-07-25 2019-10-21 2019-08-02 de protectionsur les 2 ha de Quotations Envelope 18 08-29 Investments dunes fixées au PND MR-MEDD-124500-GO-RFQ Component 3: Strengthening Pending / mise en place de clotures Request for Single Stage - One 2020-04- IDA / D2880 National Physical and Social Post Limited 0.00 Implementat 2019-09-07 2019-10-19 pour abriter les pépinières de Quotations Envelope 16 Investments ion mangroves au PND MR-MEDD-129309-CW-RFQ / Clôture grillagée pour la Component 3: Strengthening Request for Single Stage - One 2020-04- 2019- protection d'une fixation de IDA / D2880 National Physical and Social Post Limited 36,983.98 Completed 2019-09-07 2019-09-13 2019-11-02 2019-09-17 Quotations Envelope 30 10-23 dunes de 15 ha du littoral de Investments Nouakchott MR-MEDD-137084-CW-RFQ / Mise en place de couloirs de Component 1: Strengthening Request for Single Stage - One 2019-11- 2020- IDA / D2880 Post Limited 28,650.24 Completed 2019-10-06 2020-03-13 2019-10-16 2020-03-06 pare-feux de Typha au niveau Regional Integration Quotations Envelope 15 05-13 du Diawling MR-MEDD-137891-CW-DIR / Renforcement de la Component 3: Strengthening 2020-01- résilience des communautés IDA / D2880 National Physical and Social Post Direct Selection Direct 0.00 Canceled 2019-10-02 2019-10-04 2019-10-04 02 et des écosystèmes de Investments Ndiago. MR-MEDD-156359-CW-RFQ / Mise en place d'une clôture Component 3: Strengthening Pending Request for Single Stage - One 2020-04- grillagée autour de la marre à IDA / D2880 National Physical and Social Post Limited 0.00 Implementat 2020-02-10 2020-03-05 Quotations Envelope 19 Spartine à la Baie de l'Etoile Investments ion de Nouadhibou (phase II) MR-MEDD-170442-CW-RFQ Component 3: Strengthening Pending Request for Single Stage - One 2020-11- / Construction de Loges des IDA / D2880 National Physical and Social Post Limited 0.00 Implementat 2020-05-13 2020-07-08 Quotations Envelope 05 agents de surveillance Investments ion Page 1 MR-MEDD-170443-CW-RFQ Component 3: Strengthening Pending Request for Single Stage - One 2020-11- / Travaux de fixation des IDA / D2880 National Physical and Social Post Limited 0.00 Implementat 2020-06-13 2020-08-08 Quotations Envelope 06 dunes au diawling Investments ion MR-MEDD-170445-CW-RFQ Component 3: Strengthening Pending Request for Single Stage - One 2020-10- / Clôture grillagée fixation IDA / D2880 National Physical and Social Post Limited 0.00 Implementat 2020-05-14 2020-07-09 Quotations Envelope 17 dunes au Diawling Investments ion MR-MEDD-170447-CW-RFQ Component 3: Strengthening Request for Single Stage - One 2021-02- 2020- / Travaux de coupe de typha IDA / D2880 National Physical and Social Post Limited 33,708.59 Completed 2020-06-24 2020-03-05 2020-08-19 2020-03-23 Quotations Envelope 15 04-24 au Parc National du Diawling Investments MR-MEDD-170449-CW-RFQ Component 3: Strengthening Request for Single Stage - One 2020-10- 2020- / Mise en place de pépinière IDA / D2880 National Physical and Social Post Limited 29,996.09 Completed 2020-06-24 2020-03-10 2020-08-19 2020-03-25 Quotations Envelope 03 06-08 de mangroves au Diawling Investments MR-MEDD-170453-CW-RFQ Component 3: Strengthening / clôture pour protéger les Request for Single Stage - One 2020-11- 2020- IDA / D2880 National Physical and Social Post Limited 24,131.97 Completed 2020-06-13 2020-06-05 2020-08-08 2020-06-23 plantations de mangroves au Quotations Envelope 16 07-20 Investments Diawling Component 3: Strengthening MR-MEDD-170456-CW-RFQ Request for Single Stage - One 2020-11- 2020- IDA / D2880 National Physical and Social Post Limited 14,446.54 Completed 2020-07-16 2020-07-10 2020-09-10 2020-07-24 / Plantation de mangroves Quotations Envelope 09 08-10 Investments MR-MEDD-170457-CW-RFQ Component 3: Strengthening Pending / Travaux d’entretien des Request for Single Stage - One 2020-10- IDA / D2880 National Physical and Social Post Limited 0.00 Implementat 2020-05-15 2020-07-10 couloirs et de coupe de Typha Quotations Envelope 08 Investments ion déjà réalisés MR-MEDD-170572-CW-RFB / Travaux de réhabilitation et Component 3: Strengthening Pending 2021-05- extension de la digue Nord du IDA / D2880 National Physical and Social Post Request for Bids Open - National 0.00 Implementat 2020-08-10 2020-09-09 2020-10-09 2020-10-29 2020-11-28 27 Parc National du Diawling Investments ion (PND) MR-MEDD-170567-CW-RFB Component 2: Strengthening Pending Single Stage - One 2022-05- / Travaux de fixation de IDA / D2880 the Policy and Institutional Post Request for Bids Open - International 0.00 Implementat 2021-01-04 2021-01-19 2021-03-02 2021-04-01 2021-05-06 Envelope 03 dunes du littoral Framework ion MR-MEDD-178901-CW-RFQ Component 3: Strengthening / Entretien des claies et du Request for Single Stage - One 2020-07- 2020- IDA / D2880 National Physical and Social Post Limited 16,815.78 Completed 2020-06-15 2020-06-23 2020-06-28 2020-07-10 reboisement (au niveau du Quotations Envelope 28 07-23 Investments PND) MR-MEDD-200677-CW-RFQ Component 3: Strengthening Request for Single Stage - One 2021-02- / Construction d’un poste de IDA / D2880 National Physical and Social Post Limited 34,654.84 Signed 2020-11-15 2020-10-26 2021-01-10 2020-12-07 Quotations Envelope 24 surveillance au PND Investments MR-MEDD-200725-CW-RFQ Component 3: Strengthening Request for Single Stage - One 2021-04- 2020- / Mise en place d’une IDA / D2880 National Physical and Social Post Limited 16,021.62 Completed 2020-11-22 2020-10-26 2021-01-17 2020-11-11 Quotations Envelope 17 12-07 pépinière d’Acacias Investments MR-MEDD-200729-CW-RFQ Component 3: Strengthening Pending Request for Single Stage - One 2021-05- / Entretien des travaux et IDA / D2880 National Physical and Social Post Limited 0.00 Implementat 2020-12-21 2021-02-15 Quotations Envelope 16 couloirs déjà réalisés Investments ion MR-MEDD-200730-CW-RFQ Component 3: Strengthening Request for Single Stage - One 2021-04- 2020- / Entretien de 15 ha coupés IDA / D2880 National Physical and Social Post Limited 18,441.49 Completed 2020-11-25 2020-10-23 2021-01-20 2020-11-11 Quotations Envelope 20 12-17 en 2020 Investments MR-MEDD-200733-CW-RFQ Component 3: Strengthening Pending Request for Single Stage - One 2021-05- / Coupe de 50 ha de Typha IDA / D2880 National Physical and Social Post Limited 0.00 Implementat 2020-12-26 2021-02-20 Quotations Envelope 21 dans le bassin de BELL Investments ion MR-MEDD-225606-CW-RFQ Component 3: Strengthening Pending Request for Single Stage - One 2021-06- / Entretien des sites de IDA / D2880 National Physical and Social Post Limited 0.00 Implementat 2021-03-27 2021-05-16 Quotations Envelope 30 pépinières mangroves Investments ion MR-MEDD-225608-CW-RFQ Component 3: Strengthening Request for Single Stage - One 2021-06- 2021- / Clôture de plantations de IDA / D2880 National Physical and Social Post Limited 57,763.54 Completed 2021-04-03 2021-03-26 2021-05-09 2021-04-01 Quotations Envelope 08 04-13 mangroves Investments MR-MEDD-225609-CW-RFQ Component 3: Strengthening Request for Single Stage - One 2021-06- 2020- / Reboisement des zones de IDA / D2880 National Physical and Social Post Limited 15,365.45 Completed 2021-04-10 2021-06-10 2021-05-30 2020-07-24 Quotations Envelope 02 08-10 mangroves Investments MR-MEDD-170569-CW-RFB Component 3: Strengthening Single Stage - One 2022-01- / Travaux pour le colmatage IDA / D2880 National Physical and Social Post Request for Bids Open - International 0.00 Canceled 2020-10-12 2020-10-17 2020-11-28 2020-12-28 2021-02-01 Envelope 29 des brèches Investments MR-MEDD-170571-CW-RFB / Travaux pour la réalisation Component 3: Strengthening de passages de Single Stage - One 2021-09- IDA / D2880 National Physical and Social Post Request for Bids Open - National 0.00 Canceled 2020-11-16 2020-11-21 2021-01-02 2021-02-01 2021-03-08 franchissement du cordon Envelope 04 Investments dunaire et équipement des passages piétons MR-MEDD-75953-CW-RFQ / Component 3: Strengthening Mise en place de de bacs à Request for Single Stage - One 2019-08- IDA / D2880 National Physical and Social Post Limited 0.00 Canceled 2018-12-17 2019-02-11 fleurs pour la sécurisation du Quotations Envelope 10 Investments littoral MR-MEDD-74188-CW-RFQ / Component 3: Strengthening Request for Single Stage - One 2019-07- Aménagement du site de l'éco- IDA / D2880 National Physical and Social Post Limited 0.00 Canceled 2018-11-20 2019-01-15 Quotations Envelope 14 loge Investments MR-MEDD-75993-CW-RFQ / Travaux de restauration des Component 3: Strengthening paysages des carrières de Request for Single Stage - One 2019-07- IDA / D2880 National Physical and Social Post Limited 0.00 Canceled 2018-12-05 2019-01-30 coquillages en frange Quotations Envelope 29 Investments continentale du cordon dunaire du littoral MR-MEDD-74189-CW-RFQ / Component 3: Strengthening Request for Single Stage - One 2019-10- Travaux de construction de IDA / D2880 National Physical and Social Post Limited 0.00 Canceled 2019-02-09 2019-04-06 Quotations Envelope 03 l'éco-loge Investments Page 2 MR-MEDD-82725-CW-RFQ / Component 2: Strengthening mise en place d'une pépinière Request for Single Stage - One 2019-06- IDA / D2880 the Policy and Institutional Post Limited 0.00 Canceled 2018-10-27 2018-12-22 pour les besoins de la fixation Quotations Envelope 20 Framework des dunes du littoral MR-MEDD-200772-CW-RFB Component 3: Strengthening / Travaux de construction du Single Stage - One 2022-04- IDA / D2880 National Physical and Social Post Request for Bids Open - National 0.00 Canceled 2020-12-30 2021-01-04 2021-02-15 2021-03-17 2021-04-21 siège de l'Observatoire Envelope 21 Investments National du Littoral MR-MEDD-170440-CW-RFQ Component 3: Strengthening / Confection et mise en place Request for Single Stage - One 2020-09- IDA / D2880 National Physical and Social Post Limited 0.00 Canceled 2020-05-26 2020-07-21 de bacs pour la sécurisation Quotations Envelope 19 Investments du littoral MR-MEDD-75951-CW-RFQ / Component 3: Strengthening Travaux pour passages de Request for Single Stage - One 2019-09- IDA / D2880 National Physical and Social Post Limited 0.00 Canceled 2019-01-15 2019-03-12 piétons sur le cordon dunaire Quotations Envelope 08 Investments de NKTT MR-MEDD-232482-CW-RFQ Request for Component 3: Strengthening Pending / Entretenir les claies de Request for Single Stage - One Quotations 2021-12- IDA / D2880 National Physical and Social Post Limited 0.00 Implementat 2021-07-17 2021-09-11 fixations des dunes et les Quotations Envelope (Non Bank- 10 Investments ion bacs de protection SPD) Request for MR-MEDD-232485-CW-RFQ Component 3: Strengthening Pending Request for Single Stage - One Quotations 2021-11- / Réaliser les travaux de IDA / D2880 National Physical and Social Post Limited 0.00 Implementat 2021-06-27 2021-08-16 Quotations Envelope (Non Bank- 14 fixation des dunes Investments ion SPD) MR-MEDD-232486-CW-RFQ Request for Component 3: Strengthening Pending / Faire une clôture grillagée Request for Single Stage - One Quotations 2021-12- IDA / D2880 National Physical and Social Post Limited 0.00 Implementat 2021-07-10 2021-09-04 autour des sites fixés (fixation Quotations Envelope (Non Bank- 03 Investments ion biologique) du cordon dunaire SPD) MR-MEDD-232488-CW-RFQ Request for Component 3: Strengthening Pending / Reboisement de 10000 Request for Single Stage - One Quotations 2021-10- IDA / D2880 National Physical and Social Post Limited 0.00 Implementat 2021-06-27 2021-08-22 plants d’Acacia tortilles au Quotations Envelope (Non Bank- 21 Investments ion PND SPD) Request for MR-MEDD-232508-CW-RFB Component 3: Strengthening Bids - Works Pending / Réaliser les travaux de Single Stage - One 2023-03- IDA / D2880 National Physical and Social Post Request for Bids Open - National (without 0.00 Implementat 2021-11-15 2021-11-20 2022-01-01 2022-01-31 2022-03-07 colmatage des 3 brèches (9, Envelope 07 Investments prequalificati ion 13 et 16) on) SPD MR-MEDD-232510-CW-RFB Request for / Réaliser les travaux pour le Component 3: Strengthening Bids - Small Pending Single Stage - One 2023-03- passage de franchissement du IDA / D2880 National Physical and Social Post Request for Bids Open - National Works SPD (1 0.00 Implementat 2021-11-15 2021-11-20 2022-01-01 2022-01-31 2022-03-07 Envelope 07 cordon dunaire et équipement Investments envelope ion pour le passage piéton process) MR-MEDD-232489-CW-RFQ Request for / Entretenir les travaux, les Component 3: Strengthening Pending Request for Single Stage - One Quotations 2021-12- couloirs de pare-feu, les IDA / D2880 National Physical and Social Post Limited 0.00 Implementat 2021-07-19 2021-09-13 Quotations Envelope (Non Bank- 12 claies et le reboisement Investments ion SPD) réalisés en 2020 au PND National Procurement MR-MEDD-232506-CW-RFB Component 2: Strengthening Pending Single Stage - One Document - 1 2023-02- / Construire le siège de IDA / D2880 the Policy and Institutional Post Request for Bids Open - National 0.00 Implementat 2021-10-15 2021-10-20 2021-12-01 2021-12-31 2022-02-04 Envelope Envelope 01 l'observatoire du littoral Framework ion process (Non Bank-SPD) National MR-MEDD-232511-CW-RFB Procurement / Réhabiliter les bacs Component 3: Strengthening Pending Single Stage - One Document - 1 2023-01- existants et faire l'extension IDA / D2880 National Physical and Social Post Request for Bids Open - National 0.00 Implementat 2021-09-16 2021-09-21 2021-11-02 2021-12-02 2022-01-06 Envelope Envelope 03 pour la sécurisation du Investments ion process (Non cordon dunaire du littoral Bank-SPD) GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MR-MEDD-74169-GO-RFQ / Component 2: Strengthening Acquisition d'équipements de Request for Single Stage - One IDA / D2880 the Policy and Institutional Post Limited 1,680.00 Completed 2018-10-06 2019-07-22 2018-12-01 2019-07-25 2019-05-30 2019-08-30 bureaux au profit de l'Autorité Quotations Envelope Framework de la Zone franche de NDB MR-MEDD-74201-GO-RFQ / Acquisition de matériel pour Component 3: Strengthening Request for Single Stage - One la surveillance des IDA / D2880 National Physical and Social Post Limited 0.00 Canceled 2018-12-01 2019-01-26 2019-07-25 Quotations Envelope investissements physiques Investments pour Diawling MR-MEDD-74203-GO-RFQ / Acquisition d'équipement Component 3: Strengthening Pending Request for Single Stage - One pour l'observatoire IDA / D2880 National Physical and Social Post Limited 0.00 Implementati 2018-10-06 2018-12-01 2019-05-30 Quotations Envelope ornithologique au niveau de Investments on Diawling MR-MEDD-74204-GO-RFB / Component 4: National Single Stage - One IDA / D2880 Post Request for Bids Open - National 91,573.20 Signed 2018-08-30 2018-12-27 2018-09-04 2018-10-16 2019-02-07 2018-11-15 2019-02-20 2018-12-20 2020-06-20 2019-06-18 Achat de véhicule Coordination Envelope MR-MEDD-75977-GO-RFQ / Acquisition d'équipements de Component 2: Strengthening Request for Single Stage - One surveillance et de secourisme IDA / D2880 the Policy and Institutional Post Limited 0.00 Canceled 2018-10-30 2018-12-25 2019-06-23 Quotations Envelope au profit de la Direction de la Framework Protection Civile MR-MEDD-75990-GO-RFQ / Component 3: Strengthening Request for Single Stage - One Mise en place de pépinières IDA / D2880 National Physical and Social Post Limited 0.00 Canceled 2018-11-10 2019-01-05 2019-07-04 Quotations Envelope de mangroves à Nouamghar Investments MR-MEDD-75995-GO-RFQ / Acquisition d'équipements Component 2: Strengthening Pending Request for Single Stage - One pour le réseau des IDA / D2880 the Policy and Institutional Post Limited 0.00 Implementati 2018-12-10 2019-02-04 2019-08-03 Quotations Envelope Parlementaires et élus locaux Framework on de l'environnement Page 3 MR-MEDD-75997-GO-RFQ / Component 2: Strengthening Pending Acquisition de matériel pour Request for Single Stage - One IDA / D2880 the Policy and Institutional Post Limited 0.00 Implementati 2018-12-04 2019-01-29 2019-07-28 la coordination du Master Quotations Envelope Framework on Gaed MR-MEDD-75998-GO-RFQ / Component 2: Strengthening Pending Acquisition d'équipements Request for Single Stage - One IDA / D2880 the Policy and Institutional Post Limited 0.00 Implementati 2018-11-04 2018-12-30 2019-06-28 pour l'opérationnalisation de Quotations Envelope Framework on la base de données du MEED MR-MEDD-76001-GO-RFQ / Acquisition d'équipements Component 2: Strengthening Request for Single Stage - One pour le laboratoire des études IDA / D2880 the Policy and Institutional Post Limited 26,828.15 Completed 2018-11-04 2020-08-17 2018-12-30 2020-10-01 2019-06-28 2021-01-13 Quotations Envelope environnementales et de Framework géographie (LEERG) MR-MEDD-76866-GO-RFQ / Component 3: Strengthening Pending Request for Single Stage - One Acquisition de matériel pour IDA / D2880 National Physical and Social Post Open - National 0.00 Implementati 2018-10-15 2018-12-10 2019-06-08 Quotations Envelope les AGR Investments on MR-MEDD-124789-GO-RFQ / impression de cartes de Component 3: Strengthening distributions des formations Request for Single Stage - One IDA / D2880 National Physical and Social Post Limited 16,666.67 Completed 2019-08-26 2019-12-09 2019-10-21 2019-12-17 2020-04-18 2020-01-13 de mangroves du BAS DELTA Quotations Envelope Investments DU FLEUVE SENEGAL rive droite. MR-MEDD-170370-GO-RFQ Component 2: Strengthening Pending / Équipements au profit des Request for Single Stage - One IDA / D2880 the Policy and Institutional Post Limited 0.00 Implementati 2020-05-15 2020-07-10 2020-08-09 Délégations Régionales de Quotations Envelope Framework on l'Environnement (littoral) MR-MEDD-170397-GO-RFQ Component 2: Strengthening Pending / Acquisition d'équipement de Request for Single Stage - One IDA / D2880 the Policy and Institutional Post Limited 0.00 Implementati 2020-08-25 2020-10-20 2020-12-04 bureau au profit de l'autorité Quotations Envelope Framework on de la zone franche MR-MEDD-170462-GO-RFQ Component 2: Strengthening Request for Single Stage - One / Acquisition d'équipements IDA / D2880 the Policy and Institutional Post Limited 34,879.93 Completed 2020-08-23 2020-08-24 2020-10-18 2020-09-08 2021-04-16 2020-09-14 Quotations Envelope au profit de la DAPL/MEDD Framework MR-MEDD-172830-GO-DIR / Pending Component 4: National logiciel gestion suivi- IDA / D2880 Post Direct Selection Direct 0.00 Implementati 2020-08-10 2020-08-15 2020-09-19 2020-09-28 Coordination évaluation (RUCH) on MR-MEDD-200669-GO-RFQ / Acquisition d’équipements Component 2: Strengthening Pending au profit de la Délégation Request for Single Stage - One IDA / D2880 the Policy and Institutional Post Limited 0.00 Implementati 2020-11-10 2021-01-05 2021-02-19 Générale de la Sécurité Civile Quotations Envelope Framework on et de la Gestion des Crises au MIDEC MR-MEDD-200671-GO-RFQ Component 2: Strengthening Pending Request for Single Stage - One / Acquisition d’équipements IDA / D2880 the Policy and Institutional Post Limited 0.00 Implementati 2020-11-10 2021-01-05 2021-02-19 Quotations Envelope au profit de l’ONM Framework on MR-MEDD-200683-GO-RFQ Component 2: Strengthening / Acquisition de matériel Request for Single Stage - One IDA / D2880 the Policy and Institutional Post Limited 35,730.93 Completed 2020-11-28 2020-10-26 2021-01-23 2020-11-11 2021-03-09 2020-12-15 optique pour l’Observatoire Quotations Envelope Framework du PND MR-MEDD-200687-GO-RFQ Component 2: Strengthening Pending Request for Single Stage - One / Acquisition d’un Drone IDA / D2880 the Policy and Institutional Post Limited 0.00 Implementati 2020-11-28 2021-01-23 2026-01-01 Quotations Envelope équipé au profit du PND Framework on MR-MEDD-221606-GO-RFQ / Acquisition de deux zodiacs Component 3: Strengthening équipés de tous ses Request for Single Stage - One IDA / D2880 National Physical and Social Post Limited 9,675.19 Signed 2021-02-28 2021-03-04 2021-03-21 2021-03-08 2021-04-20 2021-03-16 accessoires, gonflables, avec Quotations Envelope Investments moteur à bord capable de transporter 5 personnes MR-MEDD-221613-GO-RFQ Component 3: Strengthening Request for Single Stage - One / Acquisition de deux drones IDA / D2880 National Physical and Social Post Limited 8,016.59 Completed 2021-02-28 2021-03-04 2021-03-21 2021-03-08 2021-04-11 2021-03-16 Quotations Envelope équipés au profit du PND Investments MR-MEDD-225619-GO-RFQ Component 2: Strengthening Pending Request for Single Stage - One / Equipement de la salle de IDA / D2880 the Policy and Institutional Post Limited 0.00 Implementati 2021-04-04 2021-05-24 2021-07-08 Quotations Envelope réunion du MEDD Framework on MR-MEDD-172827-GO-RFB / Acquisition d'équipements Component 2: Strengthening Single Stage - One de surveillance et de IDA / D2880 the Policy and Institutional Post Request for Bids Open - International 0.00 Canceled 2020-08-18 2020-08-23 2020-10-04 2020-11-03 2020-12-08 2021-06-06 Envelope secourisme au profit de la Framework Direction de la Protection Civile MR-MEDD-200771-GO-RFB / Acquisition d'une ambulance Component 2: Strengthening équipée au Profit de la Single Stage - One IDA / 62150 the Policy and Institutional Post Request for Bids Open - National 0.00 Canceled 2020-11-30 2020-12-05 2021-01-16 2021-02-15 2021-03-22 2021-03-26 Délégation Générale de la Envelope Framework sécurité Civile et de la Gestion des crises au MIDEC MR-MEDD-200663-GO-RFQ Component 2: Strengthening / Acquisition d’équipements Request for Single Stage - One IDA / D2880 the Policy and Institutional Post Limited 0.00 Canceled 2020-11-04 2020-12-30 2021-02-13 au profit de la Police Quotations Envelope Framework Environnementale MR-MEDD-75959-GO-RFQ / Component 2: Strengthening Acquisition d'équipements Request for Single Stage - One IDA / D2880 the Policy and Institutional Post Limited 0.00 Canceled 2018-12-10 2019-02-04 2019-08-03 pour l'observatoire national Quotations Envelope Framework du littoral mauritanien MR-MEDD-170405-GO-RFQ Component 2: Strengthening / Acquisition de matériel pour Request for Single Stage - One IDA / D2880 the Policy and Institutional Post Limited 0.00 Canceled 2020-06-16 2020-08-11 2020-09-25 la coordination du Master Quotations Envelope Framework GAED MR-MEDD-75978-GO-RFQ / Component 2: Strengthening Request for Single Stage - One Acquisition d'équipements au IDA / D2880 the Policy and Institutional Post Limited 0.00 Canceled 2018-10-20 2018-12-15 2019-06-13 Quotations Envelope profit de l'ONM Framework Page 4 MR-MEDD-75988-GO-RFQ / Component 3: Strengthening Acquisition d'équipements Request for Single Stage - One IDA / D2880 National Physical and Social Post Limited 0.00 Canceled 2018-11-20 2019-01-15 2019-07-14 pour la fixation des dunes au Quotations Envelope Investments niveau de Chami MR-MEDD-74196-GO-RFQ / Component 3: Strengthening Achat de plants pour la Request for Single Stage - One IDA / D2880 National Physical and Social Post Limited 0.00 Canceled 2018-11-25 2019-01-20 2019-07-19 fixation biologique du cordon Quotations Envelope Investments dunaire de Diawling MR-MEDD-200674-GO-RFQ / Acquisition d’équipements Component 2: Strengthening Request for Single Stage - One au profit du Port Autonome de IDA / D2880 the Policy and Institutional Post Limited 0.00 Canceled 2020-11-15 2021-01-10 2021-07-09 Quotations Envelope Nouakchott, dit Port de Framework l’Amitié (PAN – PA) MR-MEDD-74193-GO-RFQ / Component 3: Strengthening Acquisition d'équipements et Request for Single Stage - One IDA / D2880 National Physical and Social Post Limited 0.00 Canceled 2018-10-13 2018-12-08 2019-06-06 de matériels de protection du Quotations Envelope Investments cordon dunaire de Diawling MR-MEDD-75979-GO-RFQ / Component 2: Strengthening Acquisition d'équipements Request for Single Stage - One IDA / D2880 the Policy and Institutional Post Limited 0.00 Canceled 2018-11-20 2019-01-15 2019-07-14 pour l'opérationnalisation du Quotations Envelope Framework plan POLMAR MR-MEDD-75952-GO-RFQ / Component 3: Strengthening Equipements pour passages Request for Single Stage - One IDA / D2880 National Physical and Social Post Limited 0.00 Canceled 2019-01-20 2019-03-17 2019-09-13 de franchissement du cordon Quotations Envelope Investments dunaire de NKTT MR-MEDD-200694-GO-RFQ / Acquisition de stations de Component 2: Strengthening Request for Single Stage - One mesures topographiques et de IDA / D2880 the Policy and Institutional Post Limited 0.00 Canceled 2020-11-28 2021-01-23 2021-03-09 Quotations Envelope GPS différentiels au profit de Framework la DPREM MR-MEDD-170352-GO-RFQ Component 2: Strengthening / Équipement du centre de Request for Single Stage - One IDA / D2880 the Policy and Institutional Post Limited 0.00 Canceled 2020-07-01 2020-08-26 2020-10-10 documentation électronique Quotations Envelope Framework de la CNOEZA MR-MEDD-232476-GO-RFQ / Acquisition des équipements pour les Component 2: Strengthening Pending Request for Single Stage - One Délégations Régionales de IDA / D2880 the Policy and Institutional Post Limited 0.00 Implementati 2021-06-20 2021-08-09 2021-08-12 Quotations Envelope l'Environnement (NDB, Framework on INCHIRI, NKTT NORD ET TRARZA) MR-MEDD-232502-GO-RFB / Acquisition de 7 véhicules au profit des Délégations Component 2: Strengthening Pending Single Stage - One Régionales de l'environnement IDA / D2880 the Policy and Institutional Post Request for Bids Open - National 0.00 Implementati 2021-07-20 2021-07-25 2021-09-05 2021-10-05 2021-11-09 2022-03-09 Envelope : NDB, INCHIRI, NKTT ET Framework on TRARZA, et du Cabinet du MEDD NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MR-MEDD-74195-NC-RFQ / Collecte et transport sur sites Component 3: Strengthening Request for Single Stage - One de matériaux de fixation IDA / D2880 National Physical and Social Post Limited 0.00 Canceled 2018-11-13 2019-04-02 2019-01-08 2019-07-07 Quotations Envelope mécanique de dunes au Investments niveau de Diawling MR-MEDD-170490-NC-RFQ Component 4: National Request for Single Stage - One / Maintenance et suivi IDA / D2880 Post Limited 18,116.74 Signed 2020-05-15 2020-03-05 2020-07-10 2020-03-11 2021-07-07 Coordination Quotations Envelope informatique MR-MEDD-170472-NC-DIR / Component 3: Strengthening Pending Opérationnalisation du IDA / D2880 National Physical and Social Post Direct Selection Direct 0.00 Implementati 2020-06-23 2020-07-08 2020-08-12 2021-02-08 mécanisme de gestion de Investments on plaintes (MGP) MR-MEDD-200678-NC-RFQ Component 2: Strengthening Request for Single Stage - One / Nettoyage de 35 villages au IDA / D2880 the Policy and Institutional Post Limited 0.00 Canceled 2020-11-28 2021-01-23 2021-03-09 Quotations Envelope PND Framework MR-MEDD-232496-NC-RFQ Component 3: Strengthening Pending Request for Single Stage - One / Recruter une ONG IDA / D2880 National Physical and Social Post Open - National 0.00 Implementati 2021-07-28 2021-10-22 2022-10-19 Quotations Envelope facilitatrice du MGP Investments on CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MR-MEDD-74182-CS-QCBS / Component 2: Strengthening Consultant Elaboration de la directive IDA / D2880 the Policy and Institutional Post Qualification Open - National 0.00 Canceled 2018-09-25 2018-10-16 2018-11-29 2018-12-29 2019-02-02 2019-08-01 d'aménagement du littoral de Framework Selection NDB MR-MEDD-74184-CS-QCBS / Component 2: Strengthening Consultant Pending Etude sur le classement de la IDA / D2880 the Policy and Institutional Post Qualification Open - National 0.00 2018-09-20 2018-10-11 2018-11-24 2018-12-24 2019-01-28 2019-07-27 Implementation Baie de l'Etoile de NDB Framework Selection MR-MEDD-74207-CS-QCBS / Analyse du rapport EIE du Component 2: Strengthening Consultant projet Ahmeyin/Guembeul IDA / D2880 the Policy and Institutional Post Qualification Open - National 0.00 Canceled 2018-09-05 2018-09-26 2018-11-09 2018-12-09 2019-01-13 2019-07-12 pour la production de gaz Framework Selection offshore en Mauritanie et au Sénégal Page 5 MR-MEDD-74256-CS-CQS / Component 3: Strengthening Consultant Pending Etude pour le franchissement IDA / D2880 National Physical and Social Post Qualification Limited 0.00 2018-10-08 2018-10-22 2018-11-21 2018-12-26 2019-06-24 Implementation du cordon dunaire de NKTT Investments Selection MR-MEDD-75957-CS-QCBS / Component 2: Strengthening Consultant Evaluation des risques liés IDA / D2880 the Policy and Institutional Post Qualification Open - National 0.00 Canceled 2018-09-20 2018-10-11 2018-11-24 2018-12-24 2019-01-28 2019-07-27 aux inondations de la ville de Framework Selection NKTT MR-MEDD-75958-CS-QCBS / Component 2: Strengthening Consultant Elaboration de la directive IDA / D2880 the Policy and Institutional Post Qualification Open - National 0.00 Canceled 2018-09-28 2018-10-19 2018-12-02 2019-01-01 2019-02-05 2019-08-04 d'aménagement du littoral de Framework Selection NKTT MR-MEDD-75960-CS-QCBS / Component 2: Strengthening Consultant Elaboration d'une stratégie de IDA / D2880 the Policy and Institutional Post Qualification Open - National 0.00 Canceled 2018-09-21 2018-10-12 2018-11-25 2018-12-25 2019-01-29 2019-07-28 gestion intégrée du littoral Framework Selection mauritanien MR-MEDD-75970-CS-QCBS / Component 2: Strengthening Consultant Evaluation du capital IDA / D2880 the Policy and Institutional Post Qualification Open - National 0.00 Canceled 2018-09-20 2018-10-11 2018-11-24 2018-12-24 2019-01-28 2019-07-27 sédimentologique de la ville Framework Selection de NKTT MR-MEDD-115364-CS-CQS / Etude de faisabilité pour la Component 3: Strengthening Consultant réhabilitation et l'extension de IDA / D2880 National Physical and Social Post Qualification Limited 0.00 Canceled 2019-05-27 2020-04-27 2019-06-03 2019-06-07 2019-06-14 2019-07-24 la digue de protection au Investments Selection niveau du Diawling MR-MEDD-115676-CS-CQS Component 3: Strengthening Consultant / Etude technique pour le Pending IDA / D2880 National Physical and Social Post Qualification Limited 0.00 2018-06-15 2018-06-29 2018-07-13 2018-08-10 2018-09-24 colmatage des brèches du Implementation Investments Selection littoral de Nouakchott MR-MEDD-117326-CS-QCBS / recrutement d'un cabinet Component 4: National Quality And Cost- Pending d'audit pour audit extezrne du IDA / D2880 Post Open - National 0.00 2019-05-29 2019-05-31 2019-06-08 2019-06-11 2019-06-14 2019-06-20 2019-06-23 2019-07-13 Coordination Based Selection Implementation projet pour les années 2018 2019 2020 et 2021. MR-MEDD-124791-CS-INDV / etude sur la mise en place du système Waves pour le littoral et l'espace maritime : Component 2: Strengthening Quality And Cost- evaluation des ecosystèmes IDA / D2880 the Policy and Institutional Post Open - International 0.00 Canceled 2019-09-12 2019-10-03 2019-11-16 2019-12-14 2020-01-13 2020-02-17 2020-03-23 2021-03-23 Based Selection physiqueset monetaire pour la Framework selection des comptes du capital naturel côtier . MR-MEDD-135519-CS-QCBS / Etude environnementale Component 2: Strengthening Quality And Cost- stratégique pour l'exploitation IDA / D2880 the Policy and Institutional Post Open - International 0.00 Canceled 2019-10-04 2019-10-06 2019-10-09 2019-10-14 2019-10-29 2019-11-03 2019-11-13 2019-12-13 Based Selection du sable noir sur le littoral Framework mauritanien MR-MEDD-157694-CS-CQS / Etude environnementale Component 2: Strengthening Consultant Under stratégique pour l'exploitation IDA / D2880 the Policy and Institutional Post Qualification Open - International 0.00 2020-02-11 2020-02-06 2020-02-26 2020-04-10 2020-05-10 2020-06-14 2020-12-11 Implementation du sable noir sur le littoral Framework Selection mauritanien MR-MEDD-170561-CS-CQS Component 2: Strengthening Consultant / Élaboration des directives Under IDA / D2880 the Policy and Institutional Post Qualification Open - International 0.00 2020-05-11 2020-10-19 2020-06-01 2021-02-03 2020-07-15 2020-08-14 2020-09-18 2020-12-17 d’aménagement du littoral de Implementation Framework Selection Nouakchott de Nouadhibou MR-MEDD-170480-CS-INDV / Action pilote de recherche Component 3: Strengthening Consultant (introduction de plantes Pending IDA / D2880 National Physical and Social Post Qualification Open - National 0.00 2020-07-15 2020-08-05 2020-09-18 2020-10-18 2020-11-22 2021-01-21 aquatiques, atténuation du PH Implementation Investments Selection de l’eau,…) de la mare de Riyad MR-MEDD-170427-CS-CQS Component 2: Strengthening Consultant / Etude impact IDA / D2880 the Policy and Institutional Post Qualification Open - International 0.00 Canceled 2020-10-12 2020-08-03 2020-10-27 2020-12-10 2021-01-09 2021-02-13 2021-05-04 environnemental et social ( Framework Selection colmatage de brèches ) MR-MEDD-182813-CS-CQS / Réalisation de l'étude sur la Component 3: Strengthening Consultant caractérisation des déchets Pending IDA / D2880 National Physical and Social Post Qualification Open - International 0.00 2020-09-23 2020-10-14 2020-11-27 2020-12-27 2021-01-31 2021-03-17 urbains à Nouadhibou et Implementation Investments Selection proposition d'un système de gestion approprié MR-MEDD-200765-CS-CQS / accompagnement de l'UGP et des structures beneficiaires Consultant dans la mise en oeuvre des Component 4: National Under IDA / D2880 Post Qualification Limited 0.00 2020-05-04 2021-05-24 2020-05-18 2020-06-17 2020-07-22 2021-01-18 activitesd Coordination Implementation Selection investissement(identification des sites screening environnemental reporting...) MR-MEDD-182699-CS-CQS / accompagnement de l'UGP et des structures beneficiaires Component 2: Strengthening Consultant dans la mise en oeuvre des IDA / D2880 the Policy and Institutional Post Qualification Limited 0.00 Canceled 2020-07-01 2020-07-15 2020-08-14 2020-09-18 2020-12-17 activitesd Framework Selection investissement(identification des sites screening environnemental reporting...) MR-MEDD-200679-CS-INDV / Recrutement d'un formateur Component 2: Strengthening Consultant Pending pour la formation des IDA / D2880 the Policy and Institutional Post Qualification Open - National 0.00 2020-12-17 2021-01-07 2021-02-20 2021-03-22 2021-04-26 2021-05-26 Implementation instituteurs en éducation Framework Selection environnementale au PND Page 6 MR-MEDD-211477-CS-CQS Component 3: Strengthening Consultant / Recrutement d'un cabinet Pending IDA / D2880 National Physical and Social Post Qualification Open - National 0.00 2021-02-05 2021-02-26 2021-04-11 2021-05-11 2021-06-15 2021-08-14 pour le Suivi des travaux de la Implementation Investments Selection Digue Nord MR-MEDD-228916-CS-CQS / Recrutement d'un cabinet Component 3: Strengthening Consultant pour le choix d’un site Under IDA / D2880 National Physical and Social Post Qualification Limited 0.00 2021-04-06 2021-06-17 2021-04-20 2021-05-20 2021-06-24 2021-12-21 d’Enfouissement Technique et Implementation Investments Selection de traitement des ordures ménagères à Nouakchott MR-MEDD-170566-CS-CQS / Étude pour la détermination du trait de côte du littoral Component 2: Strengthening Consultant mauritanien par images IDA / D2880 the Policy and Institutional Post Qualification Open - National 0.00 Canceled 2020-06-15 2020-07-06 2020-08-19 2020-09-18 2020-10-23 2021-04-21 satellitaires avec quelques Framework Selection relevés du terrain par GNSS de N’Diago au Cap blanc MR-MEDD-170564-CS-CQS Component 2: Strengthening Consultant / Etude pour l’évaluation des IDA / D2880 the Policy and Institutional Post Qualification Open - International 0.00 Canceled 2020-06-15 2020-07-06 2020-08-19 2020-09-18 2020-10-23 2021-10-20 risques liés aux inondations Framework Selection de Nouakchott et Nouadhibou MR-MEDD-192591-CS-CQS Component 2: Strengthening Consultant / Etude de la bathymétrie et IDA / D2880 the Policy and Institutional Post Qualification Open - International 0.00 Canceled 2020-09-15 2020-09-30 2020-10-15 2020-10-30 2020-12-04 2021-06-02 de l'hydrométrie au PNBA Framework Selection MR-MEDD-76863-CS-QBS / élaboration de plans de Component 2: Strengthening Quality Based développement communaux IDA / D2880 the Policy and Institutional Post Open - National 0.00 Canceled 2018-09-26 2018-10-17 2018-11-30 2018-12-28 2019-01-27 2019-02-26 2019-04-02 2020-04-01 Selection pour Tevragh Zeine ,sebkha et Framework Elmina MR-MEDD-76873-CS-QCBS / Component 2: Strengthening Etude sur les pressions et Quality And Cost- IDA / D2880 the Policy and Institutional Post Open - International 0.00 Canceled 2018-10-08 2018-10-29 2018-12-12 2019-01-09 2019-02-08 2019-03-15 2019-04-19 2020-04-18 enjeux exercés sur l'espace Based Selection Framework vital du PNBA MR-MEDD-170392-CS-INDV Component 2: Strengthening Consultant / Etude de faisabilité sur la IDA / D2880 the Policy and Institutional Post Qualification Open - International 0.00 Canceled 2020-05-20 2020-05-20 2020-06-10 2020-07-24 2020-08-23 2020-09-27 2020-12-26 délocalisation du site Framework Selection d'orpaillage de Chami MR-MEDD-170573-CS-CQS Component 3: Strengthening Consultant / Activités de renforcement de IDA / D2880 National Physical and Social Post Qualification Open - International 0.00 Canceled 2020-05-11 2020-07-06 2020-06-01 2020-07-15 2020-08-14 2020-09-18 2021-09-15 la résilience des populations Investments Selection de N’Diago MR-MEDD-232480-CS-CQS / Recrutement d’un Cabinet Component 2: Strengthening Consultant pour réaliser un état des Pending IDA / D2880 the Policy and Institutional Post Qualification Limited 0.00 2021-06-14 2021-06-28 2021-07-13 2021-08-17 2021-11-15 connaissances et des données Implementation Framework Selection disponibles sur le système côtier (situation de référence MR-MEDD-232491-CS-CQS Component 3: Strengthening Consultant / Recruter un bureau pour Pending IDA / D2880 National Physical and Social Post Qualification Open - National 0.00 2021-07-13 2021-08-03 2021-09-16 2021-10-16 2021-11-14 2022-02-12 assurer le contrôle et le suivi Implementation Investments Selection des travaux de la digue MR-MEDD-232494-CS-CQS / Élaborer une enquête statistique sur le nombre de ménages situés sur le littoral Consultant Component 4: National Pending ayant accès à des activités de IDA / D2880 Post Qualification Open - National 0.00 2021-08-10 2021-08-31 2021-10-14 2021-11-13 2021-12-12 2022-03-12 Coordination Implementation substances améliorées et sur Selection le score du niveau de satisfaction des populations du littoral MR-MEDD-232505-CS-CQS / Recrutement d’un Cabinet pour Faire une modélisation de la dynamique du littoral au Component 2: Strengthening Consultant Pending niveau du Port de N'Diago IDA / D2880 the Policy and Institutional Post Qualification Open - International 0.00 2021-10-14 2021-11-04 2021-12-18 2022-01-17 2022-02-21 2022-08-20 Implementation pour mieux comprendre la Framework Selection problématique actuelle de l’érosion constatée et les mesures à prendre MR-MEDD-232513-CS-CQS / Recrutement d’un bureau pour Elaborer une EIES pour la Component 2: Strengthening Consultant Pending construction d'un Centre IDA / D2880 the Policy and Institutional Post Qualification Open - National 0.00 2021-09-15 2021-10-06 2021-11-19 2021-12-19 2022-01-23 2022-07-22 Implementation d'Enfouissement Technique Framework Selection des déchets de la ville de Nouakchott MR-MEDD-232504-CS-CQS / Recrutement d’un cabinet Component 2: Strengthening Consultant pour réaliser un audit IDA / D2880 the Policy and Institutional Post Qualification Open - International 0.00 Under Review 2021-09-15 2021-06-10 2021-10-06 2021-11-19 2021-12-19 2022-01-23 2022-07-22 environnemental des usines Framework Selection de farine de poisson le long du littoral MR-MEDD-232481-CS-CQS / Recrutement d’un bureau de Component 3: Strengthening Consultant contrôle et de suivi des IDA / D2880 National Physical and Social Post Qualification Open - National 0.00 Under Review 2021-06-21 2021-06-21 2021-07-12 2021-08-25 2021-09-24 2021-10-29 2022-04-27 travaux de colmatage des 3 Investments Selection brèches (9, 13 et 16) MR-MEDD-234410-CS-CQS / Recrutement d’une ONG Component 3: Strengthening Consultant Pending pour le suivi de Projets IDA / D2880 National Physical and Social Post Qualification Limited 0.00 2021-06-15 2021-06-29 2021-07-29 2021-09-02 2021-11-01 Implementation Sociaux et AGR dans la Investments Selection Communes de Tevragh Zeina MR-MEDD-234411-CS-CQS / Recrutement d’une ONG Component 3: Strengthening Consultant Pending pour le suivi de Projets IDA / D2880 National Physical and Social Post Qualification Limited 0.00 2021-07-15 2021-07-29 2021-08-28 2021-10-02 2021-12-01 Implementation Sociaux et AGR dans la Investments Selection Communes de Sebkha Page 7 MR-MEDD-234406-CS-CQS / Recrutement d’une ONG Component 3: Strengthening Consultant Pending pour le suivi de Projets IDA / D2880 National Physical and Social Post Qualification Limited 0.00 2021-07-15 2021-07-29 2021-08-28 2021-10-02 2021-12-31 Implementation Sociaux et AGR dans la Investments Selection Communes d’El Mina MR-MEDD-232512-CS-CQS / Élaborer une étude de faisabilité (technique et Component 2: Strengthening Consultant financière) pour la Pending IDA / D2880 the Policy and Institutional Post Qualification Open - International 0.00 2021-07-20 2021-08-10 2021-09-23 2021-10-23 2021-11-27 2022-05-26 construction d'un Centre Implementation Framework Selection d'Enfouissement Technique des déchets solides urbains de Nouakchott MR-MEDD-232514-CS-CQS / Recrutement d’un bureau pour Mener les études prioritaires nécessaires pour (i) suivre l’impact du Component 2: Strengthening Consultant Pending changement climatique sur le IDA / D2880 the Policy and Institutional Post Qualification Open - International 0.00 2021-06-15 2021-07-06 2021-08-19 2021-09-18 2021-10-23 2022-01-21 Implementation littoral, (ii) faire une analyse Framework Selection historique de l’évolution du trait de côte et (iii) fournir les données essentielles aux évalu INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Contract Type Process Status Teams of Reference Identified/Selected Signed Contract Contract Completion No. (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MR-MEDD-74127-CS-INDV / Diagnostic et évaluation de la Component 2: Strengthening Individual capacité de tous les Under IDA / D2880 the Policy and Institutional Post Consultant Limited 0.00 2018-08-17 2019-03-28 2018-08-22 2018-09-12 2018-10-17 2019-04-15 organismes concernés avec Implementation Framework Selection l'OLM (inclus consultations, séminaires, ateliers) MR-MEDD-74130-CS-INDV / Component 2: Strengthening Individual Pending Elaboration des plans de IDA / D2880 the Policy and Institutional Post Consultant Limited 0.00 2018-08-20 2018-08-25 2018-09-15 2018-10-20 2019-04-18 Implementation résilience de N'Diago Framework Selection MR-MEDD-74133-CS-INDV / Identification des actions Component 2: Strengthening Individual prioritaires de l'antenne Pending IDA / D2880 the Policy and Institutional Post Consultant Limited 0.00 2018-10-10 2018-10-15 2018-11-05 2018-12-10 2019-06-08 nationale de la MOLOA (inclus Implementation Framework Selection consultations, ateliers, séminaires) MR-MEDD-74135-CS-INDV / Component 3: Strengthening Individual Elaboration de textes IDA / D2880 National Physical and Social Post Consultant Limited 14,000.00 Completed 2018-11-02 2019-02-05 2018-11-07 2019-02-02 2018-11-28 2019-01-02 2019-02-25 2019-07-01 2020-02-10 juridiques relatifs aux Investments Selection principes pollueur-payeurs MR-MEDD-74137-CS-INDV / Conception et mise en place d'une plateforme de gestion Component 2: Strengthening Individual environnementale relative à IDA / D2880 the Policy and Institutional Post Consultant Limited 0.00 Canceled 2018-09-03 2018-09-08 2018-09-29 2018-11-03 2019-05-02 l'évaluation des activités et le Framework Selection suivi de leurs impacts environnementaux sur le littoral mauritanien MR-MEDD-74141-CS-INDV / Analyse du cadre foncier Component 2: Strengthening Individual Under relatif au littoral (inclus IDA / D2880 the Policy and Institutional Post Consultant Limited 0.00 2018-10-15 2020-12-16 2018-10-20 2018-11-10 2018-12-15 2019-06-13 Implementation consultations, séminaires, Framework Selection ateliers) MR-MEDD-74152-CS-INDV / Component 2: Strengthening Individual Elaboration de guide des Pending IDA / D2880 the Policy and Institutional Post Consultant Limited 0.00 2018-11-01 2018-11-06 2018-11-27 2019-01-01 2019-06-30 acteurs et des métiers du Implementation Framework Selection littoral mauritanien MR-MEDD-74153-CS-INDV / Revue et amendement du Component 2: Strengthening Individual système des études d'impact IDA / D2880 the Policy and Institutional Post Consultant Limited 36,000.00 Signed 2018-10-01 2020-02-11 2018-10-06 2020-05-30 2018-10-27 2020-06-02 2018-12-01 2020-06-30 2019-05-30 environnemental en Framework Selection Mauritanie MR-MEDD-74164-CS-INDV / Recrutement d'un assistant Component 2: Strengthening Individual Pending technique au profit de IDA / D2880 the Policy and Institutional Post Consultant Open 0.00 2018-09-13 2018-11-01 2018-11-22 2018-12-27 2019-06-25 Implementation l'Autorité de la Zone franche Framework Selection de NDB MR-MEDD-74175-CS-INDV / Component 2: Strengthening Individual Etat des lieux de Under IDA / D2880 the Policy and Institutional Post Consultant Limited 0.00 2018-11-01 2018-12-20 2018-11-06 2018-11-27 2019-01-01 2019-06-30 l'environnement au niveau de Implementation Framework Selection la Zone franche de NDB MR-MEDD-74194-CS-INDV / Component 3: Strengthening Individual Etudes de faisabilité des Under IDA / D2880 National Physical and Social Post Consultant Limited 0.00 2018-10-01 2018-11-24 2018-10-06 2018-10-27 2018-12-01 2019-05-30 travaux de fixation du cordon Implementation Investments Selection dunaire de Diawling MR-MEDD-74199-CS-INDV / Recrutement d'un consultant Component 3: Strengthening Individual pour le suivi et le contrôle des IDA / D2880 National Physical and Social Post Consultant Limited 9,240.00 Completed 2018-11-05 2019-03-28 2018-11-10 2019-03-28 2018-12-01 2019-01-05 2019-03-28 2019-07-04 2019-04-02 travaux du cordon dunaire de Investments Selection Diawling MR-MEDD-74200-CS-INDV / Component 3: Strengthening Individual Elaboration d'une carte IDA / D2880 National Physical and Social Post Consultant Limited 17,280.00 Completed 2018-11-15 2019-03-28 2018-11-20 2019-03-28 2018-12-11 2019-01-15 2019-03-28 2019-07-14 2019-05-15 d'occupation des éco- Investments Selection systèmes de mangroves MR-MEDD-75945-CS-INDV / Component 3: Strengthening Individual Under Etude pour le franchissement IDA / D2880 National Physical and Social Post Consultant Limited 0.00 2018-10-01 2019-02-12 2018-10-06 2018-10-27 2018-12-01 2019-05-30 Implementation du cordon dunaire de NKTT Investments Selection Page 8 MR-MEDD-75972-CS-INDV / Component 2: Strengthening Individual Pending Conception et mise en place IDA / D2880 the Policy and Institutional Post Consultant Limited 0.00 2018-11-05 2018-11-10 2018-12-01 2019-01-05 2019-07-04 Implementation d'un site web pour l'OLM Framework Selection MR-MEDD-76164-CS-INDV / Component 2: Strengthening Individual Pending Recrutement d'un Comptable IDA / D2880 the Policy and Institutional Post Consultant Open 0.00 2018-08-31 2018-10-19 2018-11-09 2018-12-14 2019-06-12 Implementation pour le Projet Framework Selection MR-MEDD-76422-CS-INDV / Individual Component 4: National Under Recrutement d'un auditeur IDA / D2880 Post Consultant Limited 0.00 2018-09-12 2018-09-17 2018-10-08 2018-11-12 2019-05-11 Coordination Implementation interne Selection MR-MEDD-76867-CS-INDV / Component 3: Strengthening Individual Mise à jour du SIG de la IDA / D2880 National Physical and Social Post Consultant Open 0.00 Canceled 2018-12-04 2019-01-22 2019-02-12 2019-03-19 2019-09-15 Région de Nouakchott Investments Selection MR-MEDD-76868-CS-INDV / Component 3: Strengthening Individual Adaptation du fonds IDA / D2880 National Physical and Social Post Consultant Open 0.00 Canceled 2018-12-04 2019-01-22 2019-02-12 2019-03-19 2019-09-15 d'Investissement communal Investments Selection (région de NKTT) MR-MEDD-82701-CS-INDV / recrutement d'un consultant Component 2: Strengthening Individual national pour l'appui à l'étude Pending IDA / D2880 the Policy and Institutional Post Consultant Limited 0.00 2018-10-29 2018-11-03 2018-11-24 2018-12-29 2019-06-27 de faisabilité du projet WACA- Implementation Framework Selection CCA en Mauritanie MR-MEDD-82704-CS-INDV / Component 2: Strengthening Individual Pending réalisation d'un documentaire IDA / D2880 the Policy and Institutional Post Consultant Limited 0.00 2018-10-19 2018-10-24 2018-11-14 2018-12-19 2019-06-17 Implementation sur la baie de l'étoile Framework Selection MR-MEDD-82731-CS-INDV / Individual Component 4: National Pending Maintenance et suivi IDA / D2880 Post Consultant Limited 0.00 2018-11-19 2018-11-24 2018-12-15 2019-01-03 2019-07-02 Coordination Implementation informatique Selection MR-MEDD-82737-CS-INDV / accompagnement de l'UGP et des structures beneficiaires Component 3: Strengthening Individual dans la mise en oeuvre des IDA / D2880 National Physical and Social Post Consultant Limited 0.00 Canceled 2018-11-15 2018-11-20 2018-12-11 2019-01-15 2019-07-14 activitesd Investments Selection investissement(identification des sites screening environnemental reporting...) MR-MEDD-76859-CS-NPO / Component 3: Strengthening Individual Pending Mise en place d'un système de IDA / D2880 National Physical and Social Post Consultant Limited 0.00 2018-11-01 2018-11-06 2018-11-27 2019-01-01 2019-06-30 Implementation Gestion de plaintes Investments Selection MR-MEDD-76166-CS-INDV / Component 2: Strengthening Individual Recrutement d'un IDA / D2880 the Policy and Institutional Post Consultant Limited 9,600.00 Signed 2018-09-05 2019-03-18 2018-09-10 2018-07-26 2018-10-01 2018-11-05 2019-07-31 2019-05-04 Responsable de Suivi- Framework Selection Evaluation MR-MEDD-76167-CS-INDV / Component 2: Strengthening Individual Pending Recrutement d'un Spécialiste IDA / D2880 the Policy and Institutional Post Consultant Open 0.00 2018-09-05 2018-10-24 2018-11-14 2018-12-19 2019-06-17 Implementation en communication Framework Selection MR-MEDD-76173-CS-INDV / Component 2: Strengthening Individual Recrutement en IDA / D2880 the Policy and Institutional Post Consultant Open 9,600.00 Signed 2018-09-05 2019-07-25 2018-10-24 2019-07-25 2018-11-14 2018-12-19 2019-08-01 2019-06-17 Développement Institutionnel Framework Selection MR-MEDD-76168-CS-INDV / Component 2: Strengthening Individual Recrutement d'un Spécialiste Pending IDA / D2880 the Policy and Institutional Post Consultant Open 0.00 2018-09-03 2018-10-22 2018-11-12 2018-12-17 2019-06-15 en Développement Social, Implementation Framework Selection sauvegarde sociale et genre MR-MEDD-76158-CS-INDV / Component 2: Strengthening Individual Recrutement Coordinateur du IDA / D2880 the Policy and Institutional Post Consultant Limited 4,320.00 Signed 2018-08-29 2017-09-28 2018-09-03 2017-09-28 2018-09-24 2017-09-28 2018-10-29 2020-01-02 2019-04-27 Projet WACA Framework Selection MR-MEDD-76160-CS-INDV / Component 2: Strengthening Individual Recrutement d'un IDA / D2880 the Policy and Institutional Post Consultant Limited 3,520.00 Signed 2018-08-29 2018-02-01 2018-09-03 2018-02-01 2018-09-24 2018-10-29 2018-05-02 2019-04-27 Coordinateur-Adjoint juriste Framework Selection pour le Projet WACA MR-MEDD-76162-CS-INDV / Component 2: Strengthening Individual Recrutement d'un IDA / D2880 the Policy and Institutional Post Consultant Limited 1,600.00 Signed 2018-08-29 2018-06-28 2018-09-03 2018-06-28 2018-09-24 2018-10-29 2018-08-02 2019-04-27 Responsable de Passation des Framework Selection Marchés MR-MEDD-115334-CS-INDV / Elaboration des TDR de Component 2: Strengthening Individual l'étude de détermination du Under IDA / D2880 the Policy and Institutional Post Consultant Open 0.00 2019-05-30 2019-10-01 2019-06-12 2019-06-14 2019-06-18 2019-07-08 trait de côte du Littoral Implementation Framework Selection mauritanien par GNSS de N'Diago au Cap blanc MR-MEDD-115272-CS-INDV Component 2: Strengthening Individual / Etude pour l'élaboration IDA / D2880 the Policy and Institutional Post Consultant Open 23,826.67 Completed 2019-05-30 2019-06-07 2019-06-13 2019-06-13 2019-06-15 2019-06-18 2019-06-21 2019-06-27 2019-08-05 2019-09-05 d'une stratégie et d'un plan de Framework Selection communication pour le Projet MR-MEDD-115327-CS-INDV / L'élaboration d'une étude Component 3: Strengthening Individual d'identification de sous- IDA / D2880 National Physical and Social Post Consultant Open 21,493.34 Completed 2019-05-30 2019-06-12 2019-06-11 2019-06-13 2019-06-13 2019-06-17 2019-06-27 2019-07-27 2019-09-05 projets dans les communes Investments Selection littorales MR-MEDD-115350-CS-INDV / Elaboration de cahier de Component 3: Strengthening Individual prescriptions techniques pour IDA / D2880 National Physical and Social Post Consultant Open 7,466.67 Signed 2019-05-30 2019-10-02 2019-06-12 2019-06-13 2019-06-17 2019-06-18 2019-06-20 2019-06-27 2019-07-16 le colmatage des brèches du Investments Selection cordon dunaire de Nouakchott MR-MEDD-115371-CS-CDS / Component 2: Strengthening Individual Etat des lieux du foncier du IDA / D2880 the Policy and Institutional Post Consultant Open 24,773.34 Completed 2019-05-30 2019-10-01 2019-06-11 2019-09-05 2019-06-13 2019-09-05 2019-06-17 2019-09-09 2019-08-16 2019-11-21 littoral de N'Diago et de la Framework Selection Zone Franche de Nouadhibou Page 9 MR-MEDD-124792-CS-INDV / Inventaire des textes Component 2: Strengthening Individual juridiques relatifs à la gestion IDA / D2880 the Policy and Institutional Post Consultant Limited 0.00 Canceled 2019-08-21 2019-08-26 2019-09-16 2019-10-21 2020-04-18 des zones côtières et marines Framework Selection et ratifications des protocoles de la convention d'Abidjan. MR-MEDD-129310-CS-CQS / Opérationalisation et Mise Component 3: Strengthening Under en place d'un système de IDA / D2880 National Physical and Social Post Direct Selection Direct 0.00 2019-09-24 2019-10-01 2019-09-27 2019-10-02 2020-03-30 Implementation gestion de plaintes pour le Investments Projet WACA MR-MEDD-74150-CS-INDV / Analyse et révision de Component 2: Strengthening Individual l'ordonnance relative au IDA / D2880 the Policy and Institutional Post Consultant Open 0.00 Canceled 2019-10-22 2019-11-15 2019-11-20 2019-11-30 2020-01-09 littoral et élaboration des Framework Selection textes d'application MR-MEDD-149021-CS-INDV / Recrutement d'un consultant pour une mission d'assistance Individual pour la saisie, sur le STEP, de Component 1: Strengthening Pending IDA / D2880 Post Consultant Limited 0.00 2019-12-09 2019-12-11 2019-12-13 2019-12-17 2020-01-01 l’ensemble des marchés Regional Integration Implementation Selection passés par les Projets PGDP et WACA/Mauritanie au cours de l’exercice 2019. MR-MEDD-170446-CS-INDV Component 3: Strengthening Individual Under / suivi des travaux de fixation IDA / D2880 National Physical and Social Post Consultant Limited 0.00 2020-05-29 2020-06-24 2020-06-13 2020-07-04 2020-08-08 2020-09-22 Implementation des dunes au Diawling Investments Selection MR-MEDD-170469-CS-INDV / Elaboration de l’étude d’impact environnemental ou Component 3: Strengthening Individual Under de notice d’impact IDA / D2880 National Physical and Social Post Consultant Open 0.00 2020-07-06 2020-11-11 2020-08-24 2021-05-26 2020-09-14 2021-05-26 2020-10-19 2021-04-17 Implementation environnemental pour Investments Selection l’extension de la digue Nord du PND MR-MEDD-170484-CS-INDV Component 3: Strengthening Individual Under / Expert Côtier (gestion IDA / D2880 National Physical and Social Post Consultant Open 0.00 2020-05-15 2020-07-09 2020-07-03 2020-07-24 2020-08-28 2021-08-25 Implementation intégrée des zones costières ) Investments Selection MR-MEDD-170486-CS-INDV / Expert en système de Component 3: Strengthening Individual gestion de l'information Under IDA / D2880 National Physical and Social Post Consultant Open 0.00 2020-06-15 2020-08-18 2020-08-04 2020-08-25 2020-09-29 2020-12-28 environnementale pour le Implementation Investments Selection littoral (Système de données et d'information) MR-MEDD-170488-CS-INDV Individual Component 4: National Under / Spécialiste en sauvegarde IDA / D2880 Post Consultant Open 0.00 2020-06-22 2020-05-20 2020-08-10 2020-08-31 2020-10-05 2021-01-03 Coordination Implementation environnementalement Selection MR-MEDD-170410-CS-INDV Component 2: Strengthening Individual Pending / Révision de l'ordonnance du IDA / D2880 the Policy and Institutional Post Consultant Open 0.00 2020-08-17 2020-10-05 2020-10-26 2020-11-30 2021-01-29 Implementation littoral Framework Selection MR-MEDD-170431-CS-INDV / Élaboration APS, APD et DAO Component 3: Strengthening Individual Under pour passage de IDA / D2880 National Physical and Social Post Consultant Open 0.00 2020-10-13 2020-09-10 2020-12-01 2021-06-01 2020-12-22 2021-06-02 2021-01-26 2021-04-26 Implementation franchissement du cordon Investments Selection dunaire MR-MEDD-170466-CS-INDV Component 3: Strengthening Individual / Elaboration des études (APS, IDA / D2880 National Physical and Social Post Consultant Open 26,669.01 Signed 2020-07-20 2020-05-08 2020-09-07 2020-06-02 2020-09-28 2020-06-02 2020-11-02 2020-06-24 2021-05-01 APD, DAO) de l’extension de Investments Selection la digue Nord du PND MR-MEDD-170420-CS-INDV Component 2: Strengthening Individual Pending / Révision du décret portant IDA / D2880 the Policy and Institutional Post Consultant Open 0.00 2020-06-08 2020-07-27 2020-08-17 2020-09-21 2020-11-05 Implementation création du FIE Framework Selection MR-MEDD-170408-CS-INDV Component 2: Strengthening Individual / Analyse de l'ordonnance du IDA / D2880 the Policy and Institutional Post Consultant Open 31,898.11 Signed 2020-05-11 2020-06-23 2020-06-29 2020-08-24 2020-07-20 2020-09-02 2020-08-24 2020-09-17 2020-10-08 littoral Framework Selection MR-MEDD-170478-CS-INDV Component 3: Strengthening Individual / Elaboration du Plan de Under IDA / D2880 National Physical and Social Post Consultant Open 0.00 2020-08-17 2021-05-24 2020-10-05 2021-05-17 2020-10-26 2021-05-24 2020-11-30 2021-05-29 gestion et d’exploitation de la Implementation Investments Selection mare de Riyad MR-MEDD-170430-CS-INDV Component 3: Strengthening Individual / Etude pour la préparation du Pending IDA / D2880 National Physical and Social Post Consultant Open 0.00 2020-06-22 2020-08-10 2020-08-31 2020-10-05 2021-01-03 dossier technique pour la Implementation Investments Selection fixation des dunes MR-MEDD-170476-CS-INDV / Réalisation de l’étude sur la Component 3: Strengthening Individual caractérisation des déchets IDA / D2880 National Physical and Social Post Consultant Open 0.00 Canceled 2020-08-10 2020-06-03 2020-09-28 2020-10-19 2020-11-23 2021-01-22 urbains à NDB et proposition Investments Selection d’un système de gestion approprié MR-MEDD-183319-CS-CDS / Complément à l'étude relative Component 3: Strengthening Pending à l'identification de sous- IDA / D2880 National Physical and Social Post Direct Selection Direct 0.00 2020-07-08 2020-07-18 2020-07-28 2020-08-04 Implementation projets sociaux dans les Investments communes littorales MR-MEDD-192575-CS-INDV Component 3: Strengthening Individual / Etude impact Pending IDA / D2880 National Physical and Social Post Consultant Limited 0.00 2020-09-21 2020-09-26 2020-10-11 2020-11-15 2020-12-30 environnemental et social Implementation Investments Selection (colmatage de brèches) MR-MEDD-170422-CS-INDV Component 2: Strengthening Individual / Etude de la bathymétrie et IDA / D2880 the Policy and Institutional Post Consultant Open 0.00 Canceled 2020-08-18 2020-09-05 2020-10-06 2020-10-27 2020-12-01 2021-03-01 de l'hydrométrie au PNBA Framework Selection Page 10 MR-MEDD-200718-CS-INDV / Recrutement d’un Component 3: Strengthening Individual Under Consultant pour l’élaboration IDA / D2880 National Physical and Social Post Consultant Limited 0.00 2020-11-30 2021-06-10 2020-12-05 2020-12-26 2021-01-30 2021-03-31 Implementation du dossier technique pour la Investments Selection fixation des dunes du Littoral MR-MEDD-200735-CS-INDV / Recrutement d’un Expert Component 2: Strengthening Individual Pending d’appui pour la restauration et IDA / D2880 the Policy and Institutional Post Consultant Limited 0.00 2020-12-25 2020-12-30 2021-01-20 2021-02-24 2021-04-10 Implementation la valorisation des Mangroves Framework Selection et du Sporobolus MR-MEDD-200747-CS-INDV / Recrutement d'un Expert Component 2: Strengthening Individual Under International en gestion du IDA / D2880 the Policy and Institutional Post Consultant Open 0.00 2020-12-15 2020-11-24 2021-02-02 2021-02-23 2021-03-30 2021-07-28 Implementation Littoral pour un appui à la Framework Selection DPREM MR-MEDD-200770-CS-CDS / Recrutement d’un Consultant Component 4: National Pending IDA / D2880 Post Direct Selection Direct 0.00 2020-09-15 2020-09-25 2020-10-20 2020-12-04 pour la formation sur STEP Coordination Implementation avec une assistance pour STEP MR-MEDD-203246-CS-INDV Individual Component 4: National Under / Recrutement d’un IDA / D2880 Post Consultant Limited 0.00 2020-09-10 2020-04-23 2020-09-15 2020-10-06 2020-11-10 2021-05-09 Coordination Implementation Coordinateur Adjoint Selection MR-MEDD-207334-CS-INDV / Etude de faisabilité de la Component 3: Strengthening Individual Under restauration et de la IDA / D2880 National Physical and Social Post Consultant Limited 0.00 2020-12-04 2020-12-14 2020-12-09 2020-12-19 2021-01-14 2021-02-13 Implementation valorisation de mangroves au Investments Selection PND MR-MEDD-209747-CS-INDV / Recrutement de consultant (e) individuel (le) pour la réalisation d’une Notice Component 2: Strengthening Individual Under d’Impact Environnemental et IDA / D2880 the Policy and Institutional Post Consultant Limited 0.00 2020-12-22 2020-12-23 2020-12-27 2020-01-20 2021-01-17 2021-01-29 2021-02-21 2021-04-22 Implementation Social (NIES) pour la Framework Selection construction du bâtiment devant abriter l’Observatoire du Littoral mauritanien (OLM). MR-MEDD-211476-CS-INDV Individual / Recrutement d'un Chef Component 4: National IDA / D2880 Post Consultant Open 0.00 Canceled 2021-01-15 2021-03-05 2021-03-26 2021-04-30 2022-04-27 comptable pour le Projet Coordination Selection WACA -Mauritanie Component 3: Strengthening Individual MR-MEDD-217842-CS-INDV Under IDA / D2880 National Physical and Social Post Consultant Direct 0.00 2021-02-09 2021-02-15 2021-02-11 2021-02-16 2021-02-20 2021-05-21 / Comptable du PGDP Implementation Investments Selection MR-MEDD-217844-CS-INDV Component 3: Strengthening Individual Under / Conseiller technique du IDA / D2880 National Physical and Social Post Consultant Direct 0.00 2021-02-09 2021-02-15 2021-02-11 2021-02-13 2021-02-16 2021-05-17 Implementation Coordinateur du PGDP Investments Selection Component 3: Strengthening Individual MR-MEDD-217850-CS-INDV Under IDA / D2880 National Physical and Social Post Consultant Direct 0.00 2021-02-09 2021-02-15 2021-02-11 2021-02-14 2021-02-19 2021-05-20 / Expert SIG du PGDP Implementation Investments Selection MR-MEDD-218369-CS-INDV Individual Component 4: National Under / Recrutement de l'Expert en IDA / D2880 Post Consultant Direct 0.00 2021-02-15 2021-05-23 2021-02-17 2021-02-20 2021-02-24 2022-02-24 Coordination Implementation suivi/évaluation Selection MR-MEDD-218371-CS-INDV Individual Component 4: National Under / Recrutement de l'Auditeur IDA / D2880 Post Consultant Direct 0.00 2021-02-15 2021-05-23 2021-02-17 2021-02-19 2021-02-23 2022-02-23 Coordination Implementation Interne Selection MR-MEDD-218374-CS-INDV Individual Component 4: National / Recrutement du Spécialiste IDA / D2880 Post Consultant Direct 0.00 Canceled 2021-02-15 2021-05-24 2021-02-17 2021-02-19 2021-02-23 2022-02-23 Coordination de Passation des Marchés Selection MR-MEDD-218375-CS-INDV Individual Component 4: National Under / Recrutement de l'assistant IDA / D2880 Post Consultant Direct 0.00 2021-02-15 2021-02-15 2021-02-17 2021-02-19 2021-02-23 2022-02-23 Coordination Implementation en passation de marchés Selection MR-MEDD-218377-CS-INDV Individual / Recrutement du spécialiste Component 4: National Under IDA / D2880 Post Consultant Direct 0.00 2021-02-15 2021-02-15 2021-02-17 2021-02-19 2021-02-23 2022-02-23 en Sauvegarde Sociale, Société Coordination Implementation Selection Civile et Genre MR-MEDD-218381-CS-INDV Individual Component 4: National Under / Recrutement d'un Spécialiste IDA / D2880 Post Consultant Direct 0.00 2021-02-15 2021-05-24 2021-02-17 2021-02-19 2021-02-23 2022-02-23 Coordination Implementation en Communication Selection MR-MEDD-218382-CS-INDV Individual Component 4: National Under / Recrutement de IDA / D2880 Post Consultant Direct 0.00 2021-02-15 2021-02-15 2021-02-17 2021-02-19 2021-02-23 2022-02-23 Coordination Implementation Coordinateur (ce) du Projet Selection MR-MEDD-219143-CS-INDV Individual Component 4: National Under / Recrutement d'un comptable IDA / D2880 Post Consultant Limited 20,016.68 2021-02-11 2021-03-19 2021-02-16 2021-02-25 2021-03-09 2021-02-01 2021-04-13 2021-10-10 Coordination Implementation en chef pour l'UGP Selection MR-MEDD-225611-CS-INDV / Recrutement d'un Consultant Individuel pour le Individual Component 4: National Under déroulement sur STEP des IDA / D2880 Post Consultant Direct 0.00 2021-03-22 2021-03-23 2021-04-01 2021-04-22 2021-05-21 2021-06-20 Coordination Implementation activités du Projet PGDP pour Selection les exercices 2019,2018 et 2017. MR-MEDD-200742-CS-INDV Component 2: Strengthening Individual / Recrutement d’un IDA / D2880 the Policy and Institutional Post Consultant Limited 0.00 Canceled 2020-12-25 2020-12-30 2021-01-20 2021-02-24 2021-04-25 consultant pour compléter Framework Selection l’étude sur la Baie de l’Etoile MR-MEDD-74185-CS-INDV / Component 2: Strengthening Individual Actualisation du plan IDA / D2880 the Policy and Institutional Post Consultant Open 0.00 Canceled 2018-09-20 2018-11-08 2018-11-29 2019-01-03 2019-07-02 d'aménagement et de gestion Framework Selection de la Baie de l'Etoile de NDB Page 11 MR-MEDD-200710-CS-INDV / Recrutement d’un Component 2: Strengthening Individual Consultant pour compléter le IDA / D2880 the Policy and Institutional Post Consultant Limited 0.00 Canceled 2020-11-23 2020-11-28 2020-12-19 2021-01-23 2021-03-24 guide des acteurs et métiers Framework Selection du littoral MR-MEDD-170414-CS-INDV / Élaboration du décret Component 2: Strengthening Individual portant modalités du IDA / D2880 the Policy and Institutional Post Consultant Limited 0.00 Canceled 2020-05-11 2020-05-16 2020-06-06 2020-07-11 2020-10-09 fonctionnement de Framework Selection l'observatoire du littoral MR-MEDD-170415-CS-INDV Component 2: Strengthening Individual / Révision du décret portant IDA / D2880 the Policy and Institutional Post Consultant Limited 0.00 Canceled 2020-05-18 2020-05-23 2020-06-13 2020-07-18 2020-09-01 création du conseil consultatif Framework Selection du littoral MR-MEDD-74187-CS-INDV / Component 3: Strengthening Individual Etude relative à la mise en IDA / D2880 National Physical and Social Post Consultant Open 0.00 Canceled 2018-09-18 2018-11-06 2018-11-27 2019-01-01 2019-06-30 place de l'éco-loge Investments Selection MR-MEDD-170403-CS-INDV / Élaboration du Plan de Component 2: Strengthening Individual Gestion Environnementale et IDA / D2860 the Policy and Institutional Post Consultant Open 0.00 Canceled 2020-05-25 2020-07-13 2020-08-03 2020-09-07 2020-11-06 Sociale de la Zone Franche de Framework Selection Nouadhibou MR-MEDD-74191-CS-INDV / Component 2: Strengthening Individual Elaboration d'une carte de IDA / D2880 the Policy and Institutional Post Consultant Limited 0.00 Canceled 2018-11-13 2018-11-18 2018-12-09 2019-01-13 2019-07-12 potentialités de la Zone Framework Selection franche de NDB MR-MEDD-170401-CS-INDV Component 2: Strengthening Individual / Élaboration d'une carte de IDA / D2880 the Policy and Institutional Post Consultant Open 0.00 Canceled 2020-08-25 2020-10-13 2020-11-03 2020-12-08 2021-06-06 potentialités pour la zone Framework Selection Franche de NDB MR-MEDD-170174-CS-INDV / Recrutement d'une assistance technique pour Component 2: Strengthening Individual l'intégration de la dimension IDA / D2880 the Policy and Institutional Post Consultant Open 0.00 Canceled 2020-07-15 2020-09-02 2020-09-23 2020-10-28 2020-12-27 résilience climatique dans Framework Selection l'ensemble des stratégies du littoral MR-MEDD-74190-CS-INDV / Component 3: Strengthening Individual Elaboration d'un plan de IDA / D2880 National Physical and Social Post Consultant Open 0.00 Canceled 2018-09-19 2018-11-07 2018-11-28 2019-01-02 2019-07-01 gestion environnementale et Investments Selection sociale du site de l'éco-loge MR-MEDD-170425-CS-INDV / Etude sur l'état des lieux et Component 2: Strengthening Individual le mapping des bases de IDA / D2880 the Policy and Institutional Post Consultant Open 0.00 Canceled 2020-07-20 2020-09-07 2020-09-28 2020-11-02 2021-05-01 données et systèmes Framework Selection géographiques des zones côtières de la Mauritanie MR-MEDD-74174-CS-INDV / Component 2: Strengthening Individual Actualisation du schéma IDA / D2880 the Policy and Institutional Post Consultant Limited 0.00 Canceled 2018-12-03 2018-12-08 2018-12-29 2019-02-02 2019-08-01 opérationnel de la Zone Framework Selection franche de NDB MR-MEDD-200714-CS-INDV / Recrutement d’un Consultant pour l’élaboration du décret portant modalités Component 3: Strengthening Individual du fonctionnement de IDA / D2880 National Physical and Social Post Consultant Limited 0.00 Canceled 2020-11-30 2020-12-05 2020-12-26 2021-01-30 2021-02-05 l’Observatoire du Littoral et la Investments Selection révision du décret portant création du Conseil Consultatif du Littoral MR-MEDD-124785-CS-INDV / etude sur l'état des lieux et Component 2: Strengthening Individual le mapping des bases de IDA / D2880 the Policy and Institutional Post Consultant Limited 0.00 Canceled 2019-08-05 2019-08-10 2019-08-15 2019-09-12 2019-10-12 donnees et SIG des zones Framework Selection côtières et arides de la mauritanie. MR-MEDD-74154-CS-INDV / Rédaction des termes de Component 2: Strengthening Individual référence de l'étude relative IDA / D2880 the Policy and Institutional Post Consultant Limited 0.00 Canceled 2018-10-03 2018-10-08 2018-10-29 2018-12-03 2019-06-01 aux plans de résilience de Framework Selection N'Diago (inclus consultations, ateliers, séminaires) MR-MEDD-137101-CS-INDV / sélection d'un consultant Component 3: Strengthening Individual pour préparer le dossier IDA / D2880 National Physical and Social Post Consultant Limited 0.00 Canceled 2019-10-08 2019-10-13 2019-10-20 2019-10-23 2019-12-22 relatif aux fixations des dunes Investments Selection du littoral MR-MEDD-200737-CS-INDV / Recrutement d’un Component 2: Strengthening Individual consultant pour adapter le IDA / D2880 the Policy and Institutional Post Consultant Limited 0.00 Canceled 2020-12-24 2020-12-29 2021-01-19 2021-02-23 2021-04-24 guide de bonnes pratiques Framework Selection /pestes et pesticides MR-MEDD-74192-CS-INDV / Component 3: Strengthening Individual Evaluation des risques IDA / D2880 National Physical and Social Post Consultant Limited 0.00 Canceled 2018-12-17 2018-12-22 2019-01-12 2019-02-16 2019-08-15 d'inondations pour la ville de Investments Selection NBD MR-MEDD-170396-CS-INDV Component 2: Strengthening Individual / Etat de lieu de la pollution IDA / D2880 the Policy and Institutional Post Consultant Open 0.00 Canceled 2020-09-15 2020-11-03 2020-11-24 2020-12-29 2021-06-27 métallique dans le milieu Framework Selection littoral de la baie du Lévrier MR-MEDD-158682-CS-INDV Component 2: Strengthening Individual / étude de faisabilité de la IDA / D2880 the Policy and Institutional Post Consultant Open 0.00 Canceled 2020-02-13 2020-04-02 2020-04-23 2020-05-28 2020-11-24 délocalisation du Centre de Framework Selection traitement de l'or de Chami Page 12 MR-MEDD-74172-CS-INDV / Component 2: Strengthening Individual Analyse du schéma IDA / D2880 the Policy and Institutional Post Consultant Open 0.00 Canceled 2020-01-29 2020-02-10 2020-03-18 2020-04-08 2020-05-13 2020-07-12 opérationnel de la Zone Framework Selection franche de NDB MR-MEDD-82696-CS-INDV / Component 2: Strengthening Individual recrutement d'un consultant IDA / D2880 the Policy and Institutional Post Consultant Limited 0.00 Canceled 2018-10-31 2018-11-20 2018-11-05 2018-11-26 2018-12-31 2019-06-29 pour appuyer la cellule Framework Selection Changement Climatique MR-MEDD-170400-CS-INDV / Etude pour réaliser un état des lieux des capacités des Component 2: Strengthening Individual usines de production de farine IDA / D2880 the Policy and Institutional Post Consultant Open 0.00 Canceled 2020-07-15 2020-08-18 2020-09-02 2020-09-23 2020-10-28 2021-01-26 de poisson d'Elbountiya en Framework Selection matière de gestion environnementale MR-MEDD-157985-CS-INDV Component 2: Strengthening Individual / Etude de faisabilité de la IDA / D2880 the Policy and Institutional Post Consultant Limited 0.00 Canceled 2020-02-10 2020-02-19 2020-02-15 2020-02-26 2020-03-11 2020-04-10 délocalisation du centre de Framework Selection traitement de l'or à Chami MR-MEDD-232477-CS-INDV Individual / Recrutement d’un Component 4: National Pending IDA / D2880 Post Consultant Open 0.00 2021-05-25 2021-07-13 2021-08-03 2021-09-07 2022-09-04 spécialiste en développement Coordination Implementation Selection institutionnel MR-MEDD-232478-CS-INDV Component 2: Strengthening Individual Pending / Recrutement d’un juriste en IDA / D2880 the Policy and Institutional Post Consultant Limited 0.00 2021-06-15 2021-06-20 2021-07-11 2021-08-15 2022-02-11 Implementation appui au MEDD Framework Selection MR-MEDD-232483-CS-INDV / Recrutement d’un Component 3: Strengthening Individual consultant Individuel pour Pending IDA / D2880 National Physical and Social Post Consultant Limited 0.00 2021-07-14 2021-07-19 2021-08-09 2021-09-13 2021-12-12 Faire le contrôle et le suivi des Implementation Investments Selection travaux de fixation des dunes du littoral MR-MEDD-232484-CS-INDV / Un Consultant Individuel Component 3: Strengthening Individual Pending pour assurer le suivi des IDA / D2880 National Physical and Social Post Consultant Limited 0.00 2021-06-28 2021-07-03 2021-07-24 2021-08-28 2022-02-24 Implementation travaux de franchissement et Investments Selection de construction de bacs MR-MEDD-232492-CS-INDV Component 3: Strengthening Individual Pending / Élaborer un plan genre pour IDA / D2880 National Physical and Social Post Consultant Open 0.00 2021-07-20 2021-09-07 2021-09-28 2021-10-27 2022-01-25 Implementation le projet Investments Selection MR-MEDD-232493-CS-INDV Component 3: Strengthening Individual / faire une évaluation Pending IDA / D2880 National Physical and Social Post Consultant Open 0.00 2021-07-19 2021-09-06 2021-09-27 2021-11-01 2022-01-30 environnementale et sociale Implementation Investments Selection des sous projets sociaux MR-MEDD-232495-CS-INDV Individual / Recrutement d’un Component 4: National Under IDA / D2880 Post Consultant Open 0.00 2021-08-10 2021-06-21 2021-09-28 2021-10-19 2021-11-17 2022-02-15 Consultant pour l’évaluation à Coordination Implementation Selection mi-parcours MR-MEDD-232497-CS-INDV / Evaluer les besoins (études, Component 3: Strengthening Individual données à acquérir) et définir Pending IDA / D2880 National Physical and Social Post Consultant Limited 0.00 2021-09-14 2021-09-19 2021-10-10 2021-11-14 2022-01-13 les indicateurs de suivi pour Implementation Investments Selection une meilleure compréhension de l’évolution du littoral MR-MEDD-232498-CS-INDV / Un Consultant Individuel Component 2: Strengthening Individual Pending pour Définir les objectifs, le IDA / D2880 the Policy and Institutional Post Consultant Open 0.00 2021-07-20 2021-09-07 2021-09-28 2021-11-02 2022-01-31 Implementation cadre et le contenu de Framework Selection l’Observatoire du Littoral MR-MEDD-236658-CS-INDV Individual / Recrutement du Spécialiste Component 4: National Under IDA / D2880 Post Consultant Open 0.00 2021-06-04 2021-06-02 2021-07-23 2021-08-13 2021-09-17 2022-09-14 de Passation des Marchés du Coordination Implementation Selection Projet WACA-Mauritanie Page 13 MALAWI WATERSHED SERVICES IMPROVEMENT PROJECT 18 MONTHS PROCUREMENT PLAN Project information: Malawi Watershed Services Improvement Project (MWASIP) - P167860 Project Implementation Agency: Ministry of Agriculture, Irrigation and Water Development, Malawi Date of the Procurement Plan: February 25, 2020 Period covered by this Procurement Plan: February 2020 to August 2021 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016 Revised November 2017 and August 2018) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Public Procurement and Disposal of Public Assets Act, 2017 of the Republic of Malawi, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. In accordance with paragraph 5.4 of the Procurement Regulations, the request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting 1 contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. The form of the Letter of Acceptance is attached in Appendix 1. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable Procurement of Second-Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables. Not Applicable. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: Not Applicable for those contracts identified in the Procurement Plan tables; Works: Not Applicable for those contracts identified in the Procurement Plan tables. Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations: Not Applicable. Other Relevant Procurement Information: - (a) Procurement Approach and Prior Review Thresholds: The Procurement Arrangements as indicated in the below table will be used. The thresholds for the Bank’s prior review requirements are also provided in the table: Prior-review Thresholds for Procurement Methods Thresholds Procurem Substanti Works Goods, IT & Non-Consulting Shortlist of National ent al Services Consultants Type Risk ($`000) Works 10,000 Open Request Request Internatio for Engineerin Open Open for nal or Quotatio Open g& Nation Nationa Quotatio Consulting ICB n or internatio Constructio al or l or n or Services ($'000 National nal or ICB n NCB NCB National ($'000) Shoppin ($'000) Supervision ($'000) ($'000) Shopping g ($'000) ($'000) ($'000) Goods, IT 2,000 & Non- Consulting ≧ < ≦ ≧ < ≦ < ≦ Services Consultan 1,000 ts (Firms) Individual 300 7,000 7,000 200 1,000 1,000 100 200 300 Consultan ts 2 *These prior review thresholds are for the purposes of the initial procurement plan for the first 18 months. The thresholds will be revised periodically based on re-assessment of risks. All contracts not subject to prior review will be post-reviewed. Prequalification. Not expected for the works/goods packages in the procurement plan. Proposed Procedures for CDD Components: Not Applicable Reference to (if any) Project Operational/Procurement Manual: The Ministry of Agriculture Irrigation and Water Development team will prepare Procurement manuals. The Procurement Plan will also form part of the Project Implementation Manual. Any Other Special Procurement Arrangements: None Procurement Packages/Plan with Procurement Arrangements and Time Schedule: as per the table below: b) PROCUREMENT PLAN Works 1 2 3 4 5 6 7 8 9 Ref Contract Estimate Procurem Prequalifica Nationa Revie Expecte Expecte . (Description) d ent tion l w d bid d No. Cost Method/ (yes/no) Prefere by openin Contrac US$ Arrangem nce Bank g date t million ent (yes/no) (Prior Signatu / re Date Post) 1. Construction of 10 11,000,00 Open Post No Prior 30-Nov- 30-Mar- irrigation schemes in 0 Internation 20 21 Zomba, Machinga, al, RFB Ncheu and Neno Districts 2. Construction of 10 Small 10,050,00 Open Post No Prior 30-Nov- 24-Apr- Dams and medium size 0 Internation 20 21 multipurpose dams al, RFB 3. Construction of 8 high 7,000,000 Open Post No Post 15 Jan 15 Jun yielding boreholes and Internation 21 21 associated irrigation al, RFB facilities 4. Construction of 20 rain 5,000,000 Open Post No Post 10 Feb 10 Jun water harvesting National, 21 21 structures RFB Goods and Non-Consulting Services 1 2 3 4 5 6 7 8 9 Ref. Contract Estimate Procurem Prequalifica Nationa Revie Expecte Expecte No. (Description) d ent tion l w d bid d Cost Method/ (yes/no) Prefere by openin Contrac US$ Arrangem nce Bank g date t million ent (yes/no) (Prior Signatu / re Date Post) 3 1. Procurement of 12 840,000 Open Post No Post 23-Apr- 15-Jun- motor vehicles National, 20 20 RFB 2. Procurement of 10 80,000 Limited, Post No Post 24-Mar- 28-Apr- motor cycles RFQ 20 20 3. Procurement of office 204,300 Open Post No Post 9-Apr-20 7-May- furniture (Desks, Chairs, National, 20 Filling Cabinets, RFB conference furniture, book shelves 4. Procurement of ICT 100,150 Open Post No Post 10-May- 8 Juy-20 equipment (20 Laptops, National, 20 and 5 supporting tools) RFB 5. Procurement of 20 15,600 Limited, Post No Post 26-Sep- 15-Dec- Tablets RFQ 20 20 6. Supply and of 1 Weather 2,000,00 Open, Post No Prior 6 Jun-20 29-Aug- radar and Associated 0 Internation 20 Accessories al, RFB 7. Procurement of 100,000 Open Post No Post 8-Mar-20 1-Jul-20 Financial Accounting National, Software maintenance RFB and Technical Support and user training Consultancy Services 1 2 3 4 5 6 7 Ref. Description of Assignment Estimat Selection Revie Expected Expected No. ed Method/ w date of Contract Cost Arrangeme by proposal Signature US$ nt Bank submissi Date (Prior / on Post) 1. Consulting Services to carry out 100,000 Open Post 12-Apr-20 10-Aug-20 Project Baseline Studies. National, CQS 2. Consulting Services for design, 1,000,00 Open Prior 12-Apr-20 10-Aug-20 design review, Construction 0 Internationa Supervision of 10 irrigation l, QCBS schemes and Water User Association (WUA) establishment 3. Consulting Services to update 500,000 Open Post 12-Apr- 11-Sep-20 ESIA and ESMP’s, and RAP Internationa 2020 preparation for 10 Irrigation l, QCBS Schemes 4. Consultancy Services to conduct 1,000,00 Open Prior 5-Apr-20 25-Jul-20 feasibility study and detailed 0 Internationa designs of 10 small and medium l, QCBS size multipurpose dams, including establishment of 4 1 2 3 4 5 6 7 Ref. Description of Assignment Estimat Selection Revie Expected Expected No. ed Method/ w date of Contract Cost Arrangeme by proposal Signature US$ nt Bank submissi Date (Prior / on community-based O&M Post) institutional arrangements 5. Consulting services for 500,000 Open Post 12-Apr- 11-Sep-20 Preparation of the ESIA and RAP Internationa 2020 for the Small and medium l QCBS Dams 6. Consulting services for detailed 400,000 Open Post 12-Apr- 11-Sep-20 design and supervision of 8 Internationa 2020 high yielding boreholes and l QCBS associated conveyance infrastructure 7. Consultancy Services for 400,000 Open Post 5-Apr-20 10-Aug-20 detailed design and Internationa Construction supervision of l, QCBS water harvesting structures 8. Consulting services for 200,000 Open Post 15-Aug-20 10-Dez-20 preparation of ESMPs and RAPs Internationa for high yielding boreholes and l QCBS water harvesting structures 9. Consulting services for (i) 1,000,00 Open Prior 15-Apr- 30-Sep-20 preparation and update 0 Internationa 2020 (including digitization) of l QCBS catchment management plans and micro-catchment plans (VLAPs) in the middle Shire River basin (SRBMP catchments in Blantyre, Neno, Ntcheu, Machinga, Zomba districts and (ii) delineation of priority hotspot catchments in the upper Shire (Balaka, Machinga, Zomba and Mangochi) and preparation catchment management plans and micro- catchment plans (VLAPs) 10. Consulting services for 1,000,00 Open Prior 15-Apr- 30-Sep- delineation of priority hotspot 00 Internationa 2020 2020 catchments in Linthipe, Bua, l QCBS and Dwangwa river basins, and preparation catchment management plans and micro- catchment plans (VLAPs) 11. Consulting services for social 1,000,00 Open Prior 15-Jul- 30-Nov- marketing 0 Internationa 2020 2020 l QCBS 12. Consulting services for design 800,000 Open Prior 15-Sep- 30-Jan-2020 of the PWS pilot for sediment Internationa 2020 reduction l QCBS 5 1 2 3 4 5 6 7 Ref. Description of Assignment Estimat Selection Revie Expected Expected No. ed Method/ w date of Contract Cost Arrangeme by proposal Signature US$ nt Bank submissi Date (Prior / on 13. PPP transaction advisory 800,000 Open Post) Prior 15-Apr- 30-Sep- services for development of Internationa 2020 2020 hydrological and climate l QCBS products and services (including market assessment) 14. Consulting services for 2,500,00 Open Prior 15-Sep- 30-Jan-2020 development and 0 Internationa 2020 operationalization of a l QCBS biophysical and ecological monitoring system (including capacity building) 15. Consulting services for update 1,000,00 Open Prior 15-Apr- 30-Sep- of agro-ecological zones, 0 Internationa 2020 2020 updated national forest cover l QCBS maps, land use and land cover maps (including map production) 16. Consulting services for 300,000 Open Post 15-Apr- 30-Sep- preparation of institutional Internationa 2020 2020 development plans for key l QCBS watershed institutions 17. Consulting services for 400,000 Open Prior 15-Apr- 30-Sep- independent verification of Internationa 2020 2020 performance of key watershed l QCBS institutions 18. Hiring of Financial Management 392,000 Open Prior 18-April- 8-Nov-20 Specialist National, 20 INDV 19. Hiring of Assistant Financial 157,000 Open Post 18-April- 8-Nov-20 Management Specialist National, 20 INDV 20. Hiring of Procurement 392,000 Open Prior 18-April- 8-Nov-20 Specialist National, 20 INDV 21. Hiring of Project Management 392,000 Open Prior 18-April- 8-Nov-20 Specialist National, 20 INDV 22. Hiring of Environmental 392,000 Open Prior 18-April- 8-Nov-20 Safeguards Specialist National, 20 INDV 23. Hiring of Social Safeguards 392,000. Open Prior 18-April- 8-Nov-20 Specialist 00 National, 20 INDV 24. Hiring of Monitoring and 392,000 Open Prior 18-April- 8-Nov-20 Evaluation Specialist National, 20 INDV 6 1 2 3 4 5 6 7 Ref. Description of Assignment Estimat Selection Revie Expected Expected No. ed Method/ w date of Contract Cost Arrangeme by proposal Signature US$ nt Bank submissi Date (Prior / on 25. Hire Technical Assistant in Land 216,400 Open Post) Post 18-Aug-20 10-Mar-21 Administration National, INDV RFB – Request for Bids; RFQ – Request for Quotations; CQS - Consultant’s Qualification Based Selection; QCBS - Quality and Cost Based Selection and; INDV - Individual Consultant Selection. 7 Appendix 1 Letter of Acceptance of the World Bank’s Anti-Corruption Guidelines and Sanctions Framework Date: Invitation of Bids/Proposals No.__________ To: ___________________________________________________________________________ We, along with our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not) consultants and personnel, acknowledge and agree to abide by the World Bank’s policy regarding Fraud and Corruption (corrupt, fraudulent, collusive, coercive, and obstructive practices), as set out and defined in the World Bank’s Anti-Corruption Guidelines1 in connection with the procurement and execution of the contract (in case of award), including any amendments thereto. We declare and warrant that we, along our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not), consultants and personnel, , are not subject to, and are not controlled by any entity or individual that is subject to, a temporary suspension, early temporary suspension, or debarment imposed by a member of the World Bank Group, including, inter alia, a cross-debarment imposed by the World Bank Group as agreed with other international financial institutions (including multilateral development banks), or through the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement. Further, we are not ineligible under the laws or official regulations of [Insert name of Employer as per bidding document] or pursuant to a decision of the United Nations Security Council. We confirm our understanding of the consequences of not complying with the World Bank’s Anti-Corruption Guidelines, which may include the following: a. rejection of our Proposal/Bid for award of contract; b. in the case of award, termination of the contract, without prejudice to any other remedy for breach of contract; and c. sanctions, pursuant to the Bank’s Anti-Corruption Guidelines and in accordance with its prevailing sanctions policies and procedures as set forth in the Bank’s Sanctions Framework. This may include a public declaration of ineligibility, either indefinitely or for a stated period of time, (i) to be awarded or otherwise benefit from a Bank-financed contract, financially or 1Guidelineson Preventing and Combating Fraud and Corruption in Projects Financed by International Bank for Reconstruction and Development Loans and the International Development Agency Credits and Grants, dated October 15, 2006, and revised in January 2011 and July 2016, as they may be revised from time to time. 8 in any other manner;2 (ii) to be a nominated3 sub-contractor, consultant, manufacturer or supplier, or service provider of an otherwise eligible firm being awarded a Bank-financed contract; and (iii) to receive the proceeds of any loan made by the Bank or otherwise to participate further in the preparation or implementation of any Bank-financed project. We understand that we may be declared ineligible as set out above upon: a. completion of World Bank Group sanctions proceedings according to its prevailing sanctions procedures; b. cross-debarment as agreed with other international financial institutions (including multilateral development banks); c. the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement; or d. temporary suspension or early temporary suspension in connection with an ongoing World Bank Group sanctions proceeding. For avoidance of doubt, the foregoing effects of ineligibility do not extend to a sanctioned firm’s or individual’s execution of its ongoing Bank-financed contracts (or its ongoing sub-agreements under such contracts) that are not the subject of a material modification, as determined by the Bank. We shall permit, and shall cause our sub-contractors, sub-consultants, agents (whether declared or not), personnel, consultants, service providers or suppliers, to permit the Bank to inspect4 all accounts, records, and other documents relating to the procurement process and/or contract execution (in the case of award), and to have them audited by auditors appointed by the Bank. We agree to preserve all accounts, records, and other documents (whether in hard copy or electronic format) related to the procurement and execution of the contract. 2 For the avoidance of doubt, a sanctioned party’s ineligibility to be awarded a contract shall include, without limitation, (i) applying for pre-qualification, expressing interest in a consultancy, and bidding, either directly or as a nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider, in respect of such contract, and (ii) entering into an addendum or amendment introducing a material modification to any existing contract. 3 A nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider (different names are used depending on the particular bidding document) is one which has been: (i) included by the bidder in its pre-qualification application or bid because it brings specific and critical experience and know-how that allow the bidder to meet the qualification requirements for the particular bid; or (ii) appointed by the Borrower. 4 Inspections in this context are usually investigative (i.e., forensic) in nature: they involve fact-finding activities undertaken by the Bank or persons appointed by the Bank to address specific matters related to investigations/audits, such as evaluating the veracity of an allegation of possible Fraud and Corruption, through the appropriate mechanisms. Such activity includes but is not limited to accessing and examining a firm's or individual's financial records and information, and making copies thereof as relevant; accessing and examining any other documents, data, and information (whether in hard copy or electronic format) deemed relevant for the investigation/audit, and making copies thereof as relevant; interviewing staff and other relevant individuals; performing physical inspections and site visits; and obtaining third-party verification of information. 9 Name of the Bidder/Consultant: Name of the person duly authorized to sign the Bid/Proposal on behalf of the Bidder/Consultant: Title of the person signing the Letter: 10 PROCUREMENT Malawi : Malawi Watershed Services Improvement Project PLAN General Information Country: Malawi Bank’s Approval Date of the Original Procurement Plan: 2020-08-28 2021-05-26 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P167860 GPN Date: 2020-08-28 Project Name: Malawi Watershed Services Improvement Project Loan / Credit No: IDA / D5860, IDA / 65790 M Executing Agency(ies): inistry of Agriculture, Irrigation and Water Development WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned MW-MOAIWD-197898-CW- RFQ / Rehabilitation of Malawi Technical and Project Request for Single Stage - One 2021-07- IDA / 65790 Post Limited 200,000.00 350,823.54 Signed 2020-11-21 2020-12-14 2021-01-05 2021-04-01 Watershed Services Management Support Quotations Envelope 04 Improvement Project (MWASIP) GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MW-MOAIWD-192192-GO- Technical and Project Single Stage - One RFB / Procurement of 12x 4x4 IDA / 65790 Post Request for Bids Open - National 840,000.00 722,254.69 Signed 2020-09-30 2020-10-02 2020-10-05 2020-10-06 2020-11-04 2020-11-04 2020-11-24 2020-11-11 2020-12-23 2021-04-01 2021-02-21 Management Support Envelope Double Cable Vehicles MW-MOAIWD-193096-GO- RFB / Supply and Delivery of Under Office Furniture including Technical and Project Single Stage - One IDA / 65790 Post Request for Bids Open - National 204,300.00 0.00 Implementati 2020-09-30 2020-10-14 2020-10-10 2020-12-11 2020-11-09 2020-11-24 2020-11-24 2020-12-22 2021-02-20 Desks, Executive Chairs, Management Support Envelope on Filling Cabinets, Conference Furniture and Book shelves MW-MOAIWD-196695-GO- Under Technical and Project Single Stage - One RFB / Procurement of ICT IDA / 65790 Post Request for Bids Open - National 100,150.00 0.00 Implementati 2020-10-08 2020-10-07 2020-10-13 2020-10-16 2020-11-12 2020-11-20 2020-12-12 2021-02-12 2020-12-31 2021-01-30 Management Support Envelope Equipment on MW-MOAIWD-231879-GO- Pending Technical and Project Request for Single Stage - One RFQ / Supply and Delivery of IDA / 65790 Post Limited 80,000.00 0.00 Implementati 2021-05-29 2021-07-06 2021-08-17 Management Support Quotations Envelope 10 Motorcycles on MW-MOAIWD-231887-GO- Pending Scaling up Landscape Request for Single Stage - One RFQ / Supply and Delivery of IDA / 65790 Post Limited 39,200.00 0.00 Implementati 2021-05-27 2021-07-04 2021-08-03 Restoration Quotations Envelope 50 Tablets on MW-MOAIWD-237722-GO- RFQ / Supply and Delivery of ICT Equipment (1 Heavy Duty Pending Technical and Project Request for Single Stage - One Photocopier, 3 Desktops and IDA / 65790 Post Limited 53,000.00 0.00 Implementati 2021-06-12 2021-07-16 2021-08-15 Management Support Quotations Envelope 3 UPS, 3 Printers, 25 External on Hard drives, and 56 Anti- virus. NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MW-MOAIWD-190073-CS- QCBS / Consulting services for design review, Quality And Cost- Under construction supervision of IDA / D5860 Improving Watershed Services Prior Open - International 1,000,000.00 0.00 2020-08-28 2020-09-30 2020-09-11 2020-12-03 2020-10-30 2020-12-11 2020-12-25 2021-02-05 2021-03-19 2024-01-03 Based Selection Implementation irrigation schemes and establishment of Water User's Association MW-MOAIWD-190038-CS- QCBS / Consulting services for preparation of catchment management plans and micro- catchment plans (VLAPs) in Scaling up Landscape Quality And Cost- Under IDA / D5860 Prior Open - International 1,000,000.00 0.00 2020-08-31 2020-09-30 2020-09-14 2021-02-24 2020-10-26 2020-12-07 2020-12-21 2021-01-29 2021-03-05 2023-02-23 the upper and middle Shire Restoration Based Selection Implementation River basin, including delineation of priority hotspot catchments in the upper Shire River Basin MW-MOAIWD-190055-CS- QCBS / Consulting services for development and Technical and Project Quality And Cost- Under operationalization of a IDA / D5860 Prior Open - International 2,500,000.00 0.00 2020-08-28 2020-09-29 2020-09-11 2021-02-24 2020-10-30 2020-12-11 2020-12-25 2021-02-05 2021-03-12 2025-03-11 Management Support Based Selection Implementation biophysical and ecological monitoring system (including capacity building) MW-MOAIWD-190067-CS- QCBS / Consulting services for detailed design and Quality And Cost- Under IDA / D5860 Improving Watershed Services Post Open - International 400,000.00 0.00 2020-09-04 2020-09-01 2020-09-18 2020-12-10 2020-11-06 2021-03-14 2020-12-18 2021-01-01 2021-02-12 2021-03-26 2023-03-16 supervision of 8 high yielding Based Selection Implementation boreholes and associated conveyance infractructure Page 1 MW-MOAIWD-189997-CS- QCBS / Consulting services for feasibility study, detailed design and construction supervision of small and Quality And Cost- Under IDA / D5860 Improving Watershed Services Prior Open - International 1,000,000.00 0.00 2020-09-04 2020-09-30 2020-09-18 2020-12-02 2020-11-06 2020-12-18 2021-01-01 2021-02-12 2021-03-26 2024-01-10 medium sized multipurpose Based Selection Implementation dams including establishment of community based operational and maintenance institutional arrangements MW-MOAIWD-190044-CS- QCBS / Consulting services Scaling up Landscape Quality And Cost- Under for independent verification IDA / D5860 Post Open - International 400,000.00 0.00 2020-10-12 2020-11-02 2020-10-26 2021-02-03 2020-12-14 2021-03-30 2021-01-25 2021-02-08 2021-03-03 2021-04-07 2025-04-06 Restoration Based Selection Implementation services for all performance- based grants under the project MW-MOAIWD-226189-CS- QCBS / Consultancy for Development of Intergrated Technical and Project Quality And Cost- Under IDA / 65790 Post Open - National 200,000.00 0.00 2021-04-26 2021-04-14 2021-05-17 2021-06-07 2021-06-16 2021-07-16 2021-07-31 2021-08-25 2021-09-18 2022-03-17 MRDRMP and MWASIP Management Support Based Selection Implementation Management Iformation System MW-MOAIWD-237719-CS- Consultant CQS / Consultancy Services Technical and Project Pending IDA / 65790 Post Qualification Limited 20,000.00 0.00 2021-06-21 2021-07-05 2021-07-19 2021-08-03 2021-09-02 for Development of Website Management Support Implementation Selection for MWASIP INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MW-MOAIWD-217448-CS- CDS / Procurement of computerized Financial Technical and Project IDA / D5860 Post Direct Selection Direct 100,000.00 91,080.00 Signed 2021-02-05 2021-01-18 2021-02-15 2021-03-19 2021-04-05 2021-03-19 2021-10-02 Management and Accounting, Management Support Procurement and Monitoring and Evaluation System MW-MOAIWD-226185-CS- INDV / Individual Consulting Individual Services” for Development of Scaling up Landscape IDA / 65790 Post Consultant Open 25,000.00 0.00 Canceled 2021-04-12 2021-03-29 2021-05-28 2021-06-11 2021-07-05 2021-11-02 Manuals for Matching Grants Restoration Selection for Enhancing Agricultural Based Livelihoods MW-MOAIWD-226631-CS- CDS / Consultancy Services Technical and Project Under IDA / 65790 Post Direct Selection Direct 300,000.00 0.00 2021-04-12 2021-03-30 2021-04-26 2021-06-03 2021-11-30 to undertake Baseline Study Management Support Implementation for MRDRMP and MWASIP MW-MOAIWD-226182-CS- INDV / Individual Consulting Individual Services for Development of Scaling up Landscape Under IDA / 65790 Post Consultant Limited 20,000.00 0.00 2021-04-12 2021-03-31 2021-04-26 2021-05-06 2021-05-30 2021-09-27 Performance Based Grants Restoration Implementation Selection Manuals for Establishment of Productive Forest MW-MOAIWD-226179-CS- Individual INDV / Consultancy Services IDA / 65790 Improving Watershed Services Post Consultant 25,000.00 0.00 Under Review 2021-04-19 2021-04-23 2021-05-03 2021-05-08 2021-06-01 2021-10-29 for Development of Climate Selection Change and Meteological Bill MW-MOAIWD-227202-CS- Individual Under INDV / Consultancy for Social IDA / 65790 Improving Watershed Services Post Consultant Open 172,500.00 0.00 2021-04-06 2021-04-20 2021-05-22 2021-06-01 2021-06-25 2022-06-25 Implementation Marketing Campaign Selection MW-MOAIWD-227965-CS- INDV / Individual Consulting Individual Services” for Development of Under IDA / 65790 Improving Watershed Services Post Consultant Limited 25,000.00 0.00 2021-04-06 2021-04-06 2021-04-11 2021-04-26 2021-05-04 2021-10-01 Manuals for Matching Grants Implementation Selection for Enhancing Agricultural Based Livelihoods MW-MOAIWD-231892-CS- Individual INDV / Individual Consulting Scaling up Landscape IDA / 65790 Post Consultant Open 22,000.00 0.00 Under Review 2021-05-31 2021-05-27 2021-07-19 2021-08-09 2021-09-13 2022-03-12 Services for Land Restoration Selection Administration Specialist MW-MOAIWD-231894-CS- INDV / Recruitment of Individual Individual Consultants as Technical and Project IDA / 65790 Post Consultant Open 151,000.00 0.00 Under Review 2021-05-26 2021-05-27 2021-07-14 2021-08-04 2021-09-08 2022-03-07 District Project Accountant (7 Management Support Selection Project Accountants for 7 Districts) MW-MOAIWD-237724-CS- INDV / Recruitment of Individual Technical and Project Under Individual Consultant as IDA / 65790 Prior Consultant Open 110,000.00 0.00 2021-06-15 2021-06-17 2021-07-27 2021-08-03 2021-08-23 2022-08-23 Management Support Implementation Assistant Procurement Selection Specialist MW-MOAIWD-237729-CS- Individual INDV / Recruitment of Technical and Project Under IDA / 65790 Prior Consultant Open 150,500.00 0.00 2021-06-15 2021-06-17 2021-07-27 2021-08-03 2021-08-23 2022-08-23 Individual Consultant as Management Support Implementation Selection Procurement Specialist Page 2 Sample Procurement Plan July 9, 2010 PROCUREMENT Nepal : Nepal-India Regional Trade And Transport Project PLAN General Information Country: Nepal Bank’s Approval Date of the Original Procurement Plan: 2017-05-17 2021-05-24 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P144335 GPN Date: Project Name: Nepal-India Regional Trade And Transport Project Loan / Credit No: IDA / 52730, / , IDA / H8630 Department of Roads, Ministry of Commerce Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned NIRTTP/PCO/NITDB/W/ICB-7 / Construction and Modernize transport and Pending 2018-03- development of existing / transit arrangements between Post Request for Bids Open - International 1,100,000.00 0.00 Implementat 2016-05-20 2016-06-22 2016-07-23 2016-08-24 2016-09-17 16 railway tracks into ballastless Nepal and India ion tracks NIRTTP/PCO/PPD/W/NCB-9 / Construction of Sanitary and Strengthen Trade-Related Under 2018-07- Phyto-santary SPS/Plant IDA / H8630 Institutional Capacity in Post Request for Bids Open - National 800,000.00 0.00 Implementat 2017-02-26 2017-12-26 2017-02-27 2017-12-27 2017-03-29 2017-03-30 2017-04-15 15 Quarantine and Regional Plant Nepal ion ProtectionLaboratory NIRTTP/PCO/NITDB/W/NCB- 3 / Construction of flexible Improve Select Trade-Related 1,014,567.5 2015-10- and rigid pavements with IDA / 52730 Prior Request for Bids Open - National 1,580,459.77 Signed 2013-10-07 2013-11-29 2014-01-14 2014-02-20 2014-03-12 2014-03-25 2014-04-22 Infrastructure 2 21 drains for pavement restoration at Bhairahawa ICD NIRTTP/PCO/DOTM/W/NCB- Modernize transport and Pending 6 / Consturction of 2017-03- / transit arrangements between Post Request for Bids Open - National 500,000.00 0.00 Implementat 2016-01-07 2016-01-24 2016-02-23 2016-03-10 2016-03-25 Weighbridges for Axle Load 24 Nepal and India ion Control -2 Nos NIRTTP/PCO/NITDB/W/ICB-1 Improve Select Trade-Related Single Stage - One 2019-01- / Extension of Storage Shed at IDA / 52730 Post Request for Bids Open - International 237,000.00 0.00 Canceled 2017-09-12 2017-09-17 2017-10-29 2017-11-28 2018-01-02 Infrastructure Envelope 02 Birgunj ICD NIRTTP/PCO/NITDB/W/ICB-1 Pending Improve Select Trade-Related Single Stage - One 2018-10- / Extension of Storage Shed at IDA / 52730 Post Request for Bids Open - International 237,000.00 0.00 Implementat 2018-01-10 2018-01-15 2018-02-26 2018-03-28 2018-05-02 Infrastructure Envelope 29 Birgunj ICD ion NIRTTP/PCO/NITDB/W/ICB-4 / Construction of Kathmandu Improve Select Trade-Related 18,700,000.0 13,288,546. 2019-05- IDA / 52730 Prior Request for Bids Open - International Signed 2018-01-15 2018-03-09 2018-01-15 2018-03-13 2018-03-06 2018-05-10 2018-05-05 2018-06-19 2018-06-29 2018-07-05 ICD/CFS (Part-A: Main Block Infrastructure 0 55 30 (Phase 1) NIRTTP/PCO/NITDB/W/NCB- 62 / Construction of Improve Select Trade-Related Single Stage - One 27,000,000.0 2,038,137.6 2019-12- IDA / 52730 Post Request for Bids Open - National Signed 2018-01-31 2018-01-19 2018-02-05 2018-03-20 2018-03-19 2018-04-18 2018-04-18 2018-06-18 2018-05-23 2018-07-11 Kathmandu ICD/CFS (Part-B: Infrastructure Envelope 0 0 24 Office and Quarters (Phase 1)) NIRTTP/PCO/DOC/W/RFQ-24 Strengthen Trade-Related Pending Request for Single Stage - One 2021-05- / Data Center maintenance in IDA / H8630 Institutional Capacity in Post Limited 12,500.00 0.00 Implementat 2021-02-03 2021-03-17 Quotations Envelope 16 Department of Customs Nepal ion GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NIRTTP/PCO/DOTM/G/SHP- Modernize transport and Pending Request for 23 / Procurement of Office / transit arrangements between Post Limited - National 2,200.00 0.00 Implementati 2015-10-05 2015-10-14 2015-11-05 Quotations Furniture for DoTM Nepal and India on NIRTTP/PCO/TEPC/G/NCB- 25 / Procurement of Deasktop Strengthen Trade-Related Under and Laptop Computers, and IDA / 52730 Institutional Capacity in Post Request for Bids Open - National 70,000.00 0.00 Implementati 2016-06-21 2018-05-06 2016-06-22 2018-05-07 2016-07-22 2018-06-06 2016-07-23 2016-07-31 2016-08-31 necessary equipments for Nepal on TEPC NIRTTP/PCO/DOTM/G/DC- Modernize transport and Pending 28 / Procurement of LED / transit arrangements between Post Direct Selection 42,000.00 0.00 Implementati 2016-09-21 2016-10-20 Television Screen and Memory Nepal and India on Sticks NIRTTP/PCO/PPD/G/SHP-29 / Procurement of Laptop Modernize transport and Pending Request for Computers, SLR Camera etc. / transit arrangements between Post Limited - National 5,600.00 0.00 Implementati 2016-11-22 2016-11-30 2016-12-31 Quotations for Plant Protection Nepal and India on Directorate NIRTTP/PCO/DOTM/G/NCB- 30 / Procurement of Server, Modernize transport and Under Smart Phone/Tabs, Laptop IDA / 52730 transit arrangements between Post Request for Bids Open - National 148,000.00 0.00 Implementati 2017-02-27 2017-03-05 2017-04-04 2017-04-10 2017-04-27 2017-06-26 Computers and necessary Nepal and India on equipment for RAIMS NIRTTP/PCO/DOTM/G/NCB- Modernize transport and Pending 31 / Printing of various Road / transit arrangements between Post Request for Bids Open - National 28,000.00 0.00 Implementati 2017-02-27 2017-03-05 2017-04-04 2017-04-10 2017-04-27 2017-06-26 Safety Regulations and Nepal and India on Materials NIRTTP/PCO/DOTM/G/SHP- 34 / Procurement of Modernize transport and Pending Request for Computers, Printers, GIS / transit arrangements between Post Limited - National 7,200.00 0.00 Implementati 2016-12-02 2016-12-21 2017-07-11 Quotations Software and furnitures for Nepal and India on DOTM Page 1 NIRTTP/PCO/G/SHP-35 / Modernize transport and Pending Supply and Installation of Request for / transit arrangements between Post Limited - National 11,000.00 0.00 Implementati 2017-01-06 2017-01-22 2017-02-21 Solar System with Batteries Quotations Nepal and India on and Power Inverter NIRTTP-MOCS-155-CP-B- NIRTTP/PCO/DOTM/G/S / Modernize transport and Pending Request for Single Stage - One Procurement of Computers, IDA / H8630 transit arrangements between Post Open - National 7,200.00 0.00 Implementati 2017-09-01 2017-10-27 2018-04-25 Quotations Envelope Printers, GIS Software and Nepal and India on furnitures for DOTM NIRTTP/PCO/G/SHP-39 / Strengthen Trade-Related Pending Request for Single Stage - One Procurement of Computer, IDA / H8630 Institutional Capacity in Post Limited 15,000.00 0.00 Implementati 2018-03-06 2018-05-01 2018-06-30 Quotations Envelope Laptop, Printer Nepal on NIRTTP/PCO/G/SHP- / Modernize transport and Supply and Installation of Request for / transit arrangements between Post Limited - National 11,000.00 0.00 Canceled 2013-12-02 2013-12-25 2014-07-15 Solar System with Batteries Quotations Nepal and India and Power-Inverter for PCO NIRTTP/PCO/DOC/G/NCB-32 / Procurement of Equipments Strengthen Trade-Related Single Stage - One for Custom Laboratory for IDA / H8630 Institutional Capacity in Post Request for Bids Open - National 160,000.00 0.00 Canceled 2018-02-28 2018-04-04 2018-03-05 2018-04-04 2018-04-16 2018-05-07 2018-05-16 2018-07-05 2018-06-20 2018-12-17 Envelope kathmandu ( DoC ) & birgunj Nepal Customs Laboratory NIRTTP/PCO/DOC/G/NCB-63 Strengthen Trade-Related / Procurement of Lab Single Stage - One IDA / H8630 Institutional Capacity in Post Request for Bids Open - National 60,000.00 44,871.93 Signed 2018-03-15 2018-04-04 2018-03-20 2018-04-04 2018-05-01 2018-05-07 2018-05-31 2018-06-20 2018-07-05 2018-07-19 2019-01-01 Equipment for Department of Envelope Nepal Customs NIRTTP/PCO/TEPC/G/SHOPPI Strengthen Trade-Related Under NG-64 / Solar Backup System Request for Single Stage - One IDA / H8630 Institutional Capacity in Post Open - National 16,000.00 0.00 Implementati 2018-05-20 2018-06-12 2018-07-15 2018-09-13 for Nepal Trade Information Quotations Envelope Nepal on Portal NIRTTP/PCO/G/SHP-33 / Modernize transport and Procurement of Office Request for / transit arrangements between Post Limited - National 9,200.00 0.00 Canceled 2016-11-26 2016-12-23 2017-07-15 Furniture, Fixtures and Quotations Nepal and India Furnishing for PCO NIRTTP/PCO/G/SHP-20 / Modernize transport and Request for Procurement of Stationery and / transit arrangements between Post Limited - National 8,800.00 0.00 Canceled 2015-10-11 2015-10-20 2015-10-20 Quotations Sundries for PCO Nepal and India NIRTTP/PCO/TEPC/G/SHP-26 Modernize transport and / Procurement of Office Request for / transit arrangements between Post Limited - National 5,000.00 0.00 Canceled 2016-07-16 2016-07-25 2016-08-25 Furniture and furnishing for Quotations Nepal and India TEPC NIRTTP/PCO/DOC/G/NCB-66 / Equipment for Custom Strengthen Trade-Related Single Stage - One Laboratory for kathmandu ( IDA / H8630 Institutional Capacity in Post Request for Bids Open - National 160,000.00 149,478.74 Signed 2018-09-02 2019-01-01 2018-09-12 2019-01-10 2018-10-12 2019-01-28 2018-12-11 2019-03-31 2019-01-15 2019-04-22 2019-07-14 Envelope DoC ) & birgunj Customs Nepal Laboratory NIRTTP/PCO/PPD/G/NCB-69 Strengthen Trade-Related Pending Single Stage - One / Lab equipments and IDA / H8630 Institutional Capacity in Post Request for Bids Open - National 50,000.00 0.00 Implementati 2019-01-01 2019-01-06 2019-02-17 2019-03-19 2019-04-23 2019-08-21 Envelope accessories for SPS Lab Nepal on NIRTTP/PCO/DOTM/G/NCB- Modernize transport and 79 / Hardware for Road Single Stage - One IDA / H8630 transit arrangements between Post Request for Bids Open - National 35,000.00 0.00 Canceled 2019-05-31 2019-06-05 2019-07-17 2019-08-16 2019-09-20 2020-01-18 Accident Information Envelope Nepal and India Management System( RAIMS) NIRTTP/PCO/TEPC/G/NCB- Strengthen Trade-Related Under 82 / Procurement of Desktop Single Stage - One IDA / H8630 Institutional Capacity in Post Request for Bids Open - National 78,000.00 0.00 Implementati 2019-08-01 2019-08-06 2019-09-17 2019-10-17 2019-11-21 2020-05-19 and Laptop Computers, and Envelope Nepal on necessary equipment for TEPC NIRTTP/PCO/TEPC/G/NCB- Strengthen Trade-Related Under Single Stage - One 83 / SOlar Backup system for IDA / H8630 Institutional Capacity in Post Request for Bids Open - National 42,000.00 0.00 Implementati 2019-08-01 2019-08-06 2019-09-17 2019-10-17 2019-11-21 2020-03-20 Envelope NTIP ( TEPC) Nepal on NIRTTP/PCO/DOC/G/NCB-86 Strengthen Trade-Related / Installation of Scanning Single Stage - One IDA / H8630 Institutional Capacity in Post Request for Bids Open - National 270,000.00 0.00 Canceled 2019-08-01 2019-08-06 2019-09-17 2019-10-17 2019-11-21 2020-05-19 Electron microscope (SEM) Envelope Nepal with EDX Detector NIRTTP/PCO/DOC/G/NCB-87 / Installation of High Strengthen Trade-Related Pending Single Stage - One Performance Liquid IDA / H8630 Institutional Capacity in Post Request for Bids Open - National 50,000.00 0.00 Implementati 2019-08-01 2019-08-06 2019-09-05 2019-10-05 2019-11-09 2020-03-08 Envelope Chromatography ( HPCL) for Nepal on DoC NIRTTP/PCO/DOC/G/NCB-89 Strengthen Trade-Related Pending Single Stage - One / Sport Utility Vehicles for IDA / H8630 Institutional Capacity in Post Request for Bids Open - National 80,000.00 0.00 Implementati 2019-08-15 2019-08-20 2019-09-19 2019-10-19 2019-11-23 2020-03-22 Envelope NNSW PIU Office Nepal on NIRTTP/PCO/DOC/G/SHP-90 Strengthen Trade-Related Pending Request for Single Stage - One / Procurement of Business IDA / H8630 Institutional Capacity in Post Limited 9,000.00 0.00 Implementati 2019-08-09 2019-10-04 2019-11-03 Quotations Envelope Series Laptop (package-1) Nepal on NIRTTP/PCO/DOC/G/SHP-91 Strengthen Trade-Related Pending Request for Single Stage - One / Procurement of Branded IDA / H8630 Institutional Capacity in Post Limited 8,000.00 0.00 Implementati 2019-08-09 2019-09-06 2019-10-06 Quotations Envelope High End Laptop (package-2) Nepal on NIRTTP/PCO/DOC/G/SHP-92 Strengthen Trade-Related Pending / Procurement of It Equipment Request for Single Stage - One IDA / H8630 Institutional Capacity in Post Limited 3,300.00 0.00 Implementati 2019-08-09 2019-09-06 2019-10-06 ( Printer,I-Pad & USB Hard Quotations Envelope Nepal on disk) (Package-3) NIRTTP/PCO/DOC/G/SHP-93 Strengthen Trade-Related Pending / Procurement of It Equipment Request for Single Stage - One IDA / H8630 Institutional Capacity in Post Limited 4,700.00 0.00 Implementati 2019-08-09 2019-09-06 2019-10-06 ( Photocopy,Color Quotations Envelope Nepal on Printer,Scanner) Package-4 Page 2 NIRTTP-PCO-DOC-G-SHP-81 / IT Equipment & Accessories Strengthen Trade-Related Pending for NNSW PIU Office ( Request for Single Stage - One IDA / H8630 Institutional Capacity in Post Open - National 20,000.00 0.00 Implementati 2019-10-06 2019-11-24 2019-12-24 Laptop,Desk Top, Quotations Envelope Nepal on Scanner,Printer,Photocopy, Vacuum Cleaner) -package-5 NIRTTP/PCO/DOC/G/SHP-84 Strengthen Trade-Related Pending Request for Single Stage - One / Procurement of Motorcycle IDA / H8630 Institutional Capacity in Post Limited 10,000.00 0.00 Implementati 2019-09-04 2019-10-16 2020-04-13 Quotations Envelope & Scooter for DoC Nepal on NIRTTP/PCO/G/SHP-87 / IT Strengthen Trade-Related Pending Request for Single Stage - One Equipment and other IDA / H8630 Institutional Capacity in Post Limited 9,000.00 0.00 Implementati 2019-09-04 2019-10-30 2020-04-27 Quotations Envelope Accessories for PCO Nepal on NIRTTP-PCO-DOTM-G-SHP- Modernize transport and Request for Single Stage - One 79 / Procurment of additional IDA / H8630 transit arrangements between Post Open - National 20,000.00 0.00 Canceled 2019-06-14 2019-08-02 2019-09-01 Quotations Envelope hardware for RAMIS Nepal and India NIRTTP/PCO/CAL/G/NCB- 104 / Supply & Installation of Strengthen Trade-Related Pending Lab Equipment for SPS /Plant Single Stage - One IDA / H8630 Institutional Capacity in Post Request for Bids Open - National 200,000.00 0.00 Implementati 2019-09-01 2019-09-06 2019-10-18 2019-11-17 2019-12-22 2020-04-20 Quarantine and Regional Plant Envelope Nepal on Protection Laboratory , Hariharbhawan, Lalitpur NP-MOC-133997-GO-DIR / Modernize transport and Pending Procurement of Smart phone IDA / H8630 transit arrangements between Post Direct Selection Direct 19,000.00 0.00 Implementati 2019-09-16 2019-09-30 2019-10-21 2019-11-05 for accident data collection Nepal and India on NIRTTP/PCO/DOC/G/SHP- 112 / Office equipment for Strengthen Trade-Related Pending NNSW, PIU Office (Office Request for Single Stage - One IDA / H8630 Institutional Capacity in Post Limited 14,000.00 0.00 Implementati 2019-12-05 2020-01-10 2020-02-09 Table, Computer Table, Sofa Quotations Envelope Nepal on Set, Chairs, Cupboard, Carpets) NIRTTP/PCO/DOC/G/NCB- Strengthen Trade-Related Pending 113 / Supply and Deliver of Single Stage - One IDA / H8630 Institutional Capacity in Post Request for Bids Open - National 220,000.00 0.00 Implementati 2020-01-25 2020-01-30 2020-02-29 2020-03-30 2020-04-27 2020-10-24 Portable RAMAN Spectroscopy Envelope Nepal on (Hand held) equipments NIRTTP/PCO/DOC/G/NCB- Strengthen Trade-Related Pending 114 / Supply and delivery of Single Stage - One IDA / H8630 Institutional Capacity in Post Request for Bids Open - National 85,000.00 0.00 Implementati 2020-01-24 2020-01-29 2020-03-11 2020-04-10 2020-05-15 2020-11-11 Portable XRF (Hand hel) Envelope Nepal on equipments NIRTTP/PCO/DOTM/G/NCB- 117 / Procurement of Modernize transport and Pending Single Stage - One Hardware for GPS-Vehicle IDA / H8630 transit arrangements between Post Request for Bids Open - National 420,000.00 0.00 Implementati 2020-03-25 2020-04-01 2020-05-01 2020-05-16 2020-05-30 2020-07-14 Envelope Tracking System for Public Nepal and India on Buses NIRTTP/PCO/G/SHP-119 / Strengthen Trade-Related Request for Single Stage - One Supply and delivery of the IDA / H8630 Institutional Capacity in Post Limited 20,000.00 13,843.10 Completed 2020-02-24 2020-05-29 2020-03-15 2020-06-21 2020-03-30 2020-07-07 Quotations Envelope office furniture Nepal NIRTTP/PCO/G/SHP-118 / Supply and deliver of Strengthen Trade-Related Pending Request for Single Stage - One Machinery Equipment IDA / H8630 Institutional Capacity in Post Limited 24,000.00 0.00 Implementati 2020-03-09 2020-04-21 2020-05-21 Quotations Envelope (Desktop, Laptops, Printers Nepal on etc) NIRTTP/PCO/G/DIR- 84 / Strengthen Trade-Related Supply and delivery of four IDA / H8630 Institutional Capacity in Post Direct Selection Direct 52,000.00 0.00 Canceled 2020-11-27 2020-12-04 2021-01-09 2021-02-08 wheel Jeep with five doors for Nepal PCO NIRTTP/PCO/G/DIR-85 / Strengthen Trade-Related Supply and delivery of double IDA / H8630 Institutional Capacity in Post Direct Selection Direct 37,000.00 0.00 Canceled 2020-11-27 2020-12-04 2021-01-01 2021-03-02 cab pickup for SPS laboratory Nepal NIRTTP/PCO/G/DIR-86 / Strengthen Trade-Related Supply and delivery of two IDA / H8630 Institutional Capacity in Post Direct Selection Direct 69,000.00 0.00 Canceled 2020-11-27 2020-12-04 2021-01-08 2021-02-07 Cars for PCO Nepal NIRTTP/PCO/G/DIR-87 / Strengthen Trade-Related Supply and delivery of Two IDA / H8630 Institutional Capacity in Post Direct Selection Direct 7,000.00 0.00 Canceled 2020-11-27 2020-12-04 2021-01-08 2021-02-07 motorbike for PCO Nepal NIRTTP/PCO/G/DIR-88 / Strengthen Trade-Related Supply and deliver of Two IDA / H8630 Institutional Capacity in Post Direct Selection Direct 5,000.00 0.00 Canceled 2020-11-27 2020-12-04 2021-01-09 2021-02-08 Scooters for PCO Nepal NIRTTP/PCO/MOALD/G/RFQ- 89 / Supply and delivery of Strengthen Trade-Related Pending Desktop computer, High-End Request for Single Stage - One IDA / H8630 Institutional Capacity in Post Limited 22,000.00 0.00 Implementati 2020-12-06 2021-01-25 2021-03-26 series labtop and Heavy duty Quotations Envelope Nepal on photocopy machine for SPS Laboratory. NIRTTP/PCO/G/RFQ-90 / Strengthen Trade-Related Pending Request for Single Stage - One Supply and delivery of IDA / H8630 Institutional Capacity in Post Limited 4,000.00 0.00 Implementati 2020-12-06 2021-01-25 2021-03-26 Quotations Envelope Desktop Computer for PCO. Nepal on NIRTTP/PCO/G/RFQ-91 / Strengthen Trade-Related Pending Request for Single Stage - One Supply and delivery of laptop IDA / H8630 Institutional Capacity in Post Limited 4,000.00 0.00 Implementati 2020-12-06 2021-01-24 2021-03-25 Quotations Envelope for PCO Nepal on NIRTTP/PCO/G/RFQ-92 / Strengthen Trade-Related Pending Supply and delivery of Printer, Request for Single Stage - One IDA / H8630 Institutional Capacity in Post Limited 4,000.00 0.00 Implementati 2020-12-07 2021-01-25 2021-02-24 scanner Or Other office Quotations Envelope Nepal on equipment for PCO NIRTTP/PCO/DOC/G/NCB- 121 / Supply, installation and Strengthen Trade-Related commissioning of Single Stage - One IDA / H8630 Institutional Capacity in Post Request for Bids Open - National 34,500.00 0.00 Canceled 2021-01-26 2021-01-26 2021-02-25 2021-03-27 2021-04-18 2021-05-18 Accessories Equipment for Envelope Nepal upgrading of Data Center In Department of Customs Page 3 NIRTTP/PCO/MOALD/G/NCB- 122 / Supply, delivery and Strengthen Trade-Related installation all lab. furniture IDA / H8630 Institutional Capacity in Post Request for Bids 137,000.00 0.00 Canceled 2021-02-02 2021-03-05 2021-02-02 2021-03-04 2021-04-04 2021-04-03 2021-05-31 2021-04-25 2021-10-22 and office furniture for SPS Nepal laboratory NIRTTP/PCO/DOTM/G-123 / Supply and delivery Server, Strengthen Trade-Related Pending Single Stage - One Computers GPS devices and IDA / H8630 Institutional Capacity in Post Request for Bids Open - National 320,000.00 0.00 Implementati 2021-02-24 2021-02-24 2021-03-26 2021-04-25 2021-05-24 2021-07-08 Envelope accessories for GPS Vehicle Nepal on tracking System NIRTTP/PCO/G/NCB-124 / Strengthen Trade-Related Under Supply and delivery of four Single Stage - One IDA / H8630 Institutional Capacity in Post Request for Bids Open - National 52,000.00 0.00 Implementati 2021-03-14 2021-03-26 2021-03-14 2021-04-13 2021-05-13 2021-06-04 2021-07-04 wheel Jeep with five doors for Envelope Nepal on PCO NIRTTP/PCO/G/NCB-125 / Strengthen Trade-Related Under Single Stage - One Supply and delivery of double IDA / H8630 Institutional Capacity in Post Request for Bids Open - National 37,000.00 0.00 Implementati 2021-03-14 2021-03-26 2021-03-14 2021-04-13 2021-05-13 2021-06-11 2021-07-06 Envelope cab pickup for SPS laboratory Nepal on NIRTTP/PCO/G/NCB-127 / Strengthen Trade-Related Under Supply and delivery of two Single Stage - One IDA / H8630 Institutional Capacity in Post Request for Bids Open - National 12,000.00 0.00 Implementati 2021-03-14 2021-03-26 2021-03-14 2021-04-13 2021-05-13 2021-06-04 2021-07-04 Bikes and two Scooters for Envelope Nepal on PCO NIRTTP/PCO/DOC/G/RFQ- 133 / Supply and delivery of Strengthen Trade-Related Pending Request for Single Stage - One IT Equipment and accessories IDA / H8630 Institutional Capacity in Post Limited 6,000.00 0.00 Implementati 2021-04-30 2021-05-24 2021-06-08 Quotations Envelope (Air conditioner , Camera etc) Nepal on for NNSW PIU Office NIRTTP/PCO/DOC/G/RFQ- 134 / Supply and Delivery of Strengthen Trade-Related Pending Request for Single Stage - One IT Equipment and IDA / H8630 Institutional Capacity in Post Limited 3,000.00 0.00 Implementati 2021-04-29 2021-05-23 2021-06-22 Quotations Envelope accessories(Projector, Tablet, Nepal on Fan ) for NNSW PIU Office NIRTTP/PCO/DOC/G/RFQ / Supply,delivery and Strengthen Trade-Related Pending commissioning of accessories Request for Single Stage - One IDA / H8630 Institutional Capacity in Post Limited 25,000.00 0.00 Implementati 2021-05-16 2021-06-16 2021-07-01 equipment for upgrading Data Quotations Envelope Nepal on Centre in Department of Customs. NIRTTP/PCO/G/NCB-126 / Strengthen Trade-Related Single Stage - One Supply and delivery of two IDA / H8630 Institutional Capacity in Post Request for Bids Open - National 69,000.00 0.00 Canceled 2021-03-14 2021-03-26 2021-03-14 2021-04-13 2021-04-26 2021-05-13 2021-04-26 2021-06-04 2021-07-04 Envelope Cars for PCO Nepal NIRTTP/PCO/G/DIR-126 / Strengthen Trade-Related Pending Supply and delivery of two IDA / H8630 Institutional Capacity in Post Direct Selection Direct 69,000.00 0.00 Implementati 2021-05-24 2021-05-29 2021-06-11 2021-06-26 cars for PCO Nepal on NIRTTP/PCO/MOALD/G/NCB- 122-2 / Supply, delivery and Strengthen Trade-Related Pending Single Stage - One installation of all lab. furniture IDA / H8630 Institutional Capacity in Post Request for Bids Open - National 137,000.00 0.00 Implementati 2021-06-03 2021-06-03 2021-07-03 2021-08-02 2021-08-31 2021-11-29 Envelope and office furniture for SPS Nepal on Laboratory. NIRTTP/PCO/MOALD/G /NCB- Strengthen Trade-Related 128 / Supply and delivery of Single Stage - One IDA / H8630 Institutional Capacity in Post Request for Bids Open - National 210,000.00 0.00 Canceled 2021-04-18 2021-04-21 2021-05-21 2021-06-20 2021-07-18 2021-10-16 Laboratory Equipment of Envelope Nepal Package A for SPS Laboratory NIRTTP/PCO/MOALD/G/NCB- Strengthen Trade-Related 129 / Supply and delivery of Single Stage - One IDA / H8630 Institutional Capacity in Post Request for Bids Open - National 107,000.00 0.00 Canceled 2021-04-18 2021-04-21 2021-05-21 2021-06-20 2021-07-18 2021-10-16 Laboratory Equipment of Envelope Nepal Package B for SPS Laboratory NIRTTP/PCO/MOALD/G/NCB- Strengthen Trade-Related 130 / Supply and delivery of Single Stage - One IDA / H8630 Institutional Capacity in Post Request for Bids Open - National 260,000.00 0.00 Canceled 2021-04-18 2021-04-21 2021-05-21 2021-06-20 2021-07-18 2021-10-16 Laboratory Equipment of Envelope Nepal Package C for SPS Laboratory NIRTTP/PCO/MOALD/G/NCB- Strengthen Trade-Related 131 / Supply and delivery of Single Stage - One IDA / H8630 Institutional Capacity in Post Request for Bids Open - National 164,000.00 0.00 Canceled 2021-04-18 2021-04-21 2021-05-21 2021-06-20 2021-07-18 2021-10-16 Laboratory Equipment of Envelope Nepal Package D for SPS-Laboratory NIRTTP/PCO/MOALD/G/NCB- Strengthen Trade-Related Under (132.1TO-132.10) / Supply Single Stage - One IDA / 52730 Institutional Capacity in Post Request for Bids Open - National 667,500.00 0.00 Implementati 2021-06-13 2021-06-15 2021-06-13 2021-07-13 2021-08-12 2021-09-10 2021-11-24 and delivery of Laboratory Envelope Nepal on Equipment for SPS- Laboratory NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NIRTTP/PCO/NS/SHP-26 / Computer software design, Modernize transport and Pending Request for installation helpful in / transit arrangements between Post Limited - National 5,700.00 0.00 Implementati 2016-11-10 2016-11-19 2017-07-05 Quotations improvement of operation and Nepal and India on management of the Project NIRTTP/PCO/DOTM/NS/SHP- Modernize transport and Pending 33 / Selection & Recruitment / transit arrangements between Post Request for Bids Open - National 24,000.00 0.00 Implementati 1901-01-01 2015-05-15 1901-01-01 1901-01-01 2015-06-28 2019-06-30 of Office Secretay Nepal and India on NIRTTP/PCO/DOTM/NS/NCB- 35 / Developing web based Road Accident Management Modernize transport and Pending Information System (RAMIS) / transit arrangements between Post Direct Selection National 40,000.00 0.00 Implementati 2016-01-20 2016-07-15 and piloting in Kathmandu Nepal and India on valley and along the Birgunj- Kathmandu corridor Page 4 NIRTTP/PCO/NS/NCB-29 / Kolkata-Kathmandu Corridor Modernize transport and Monitoring and Evaluation / transit arrangements between Post Request for Bids Open - National 278,000.00 0.00 Canceled 2016-01-07 2016-01-11 2016-02-10 2016-02-21 2016-03-04 2016-12-30 Data Management System Nepal and India (CMEDMS) NIRTTP/PCO/TEPC/NS/SHP- Strengthen Trade-Related Pending 34 / Selection & Recruitment Request for Single Stage - One IDA / H8630 Institutional Capacity in Post Open - National 24,000.00 0.00 Implementati 2017-09-17 2017-11-12 2019-12-31 of Office Secretay for TEPC, Quotations Envelope Nepal on Number -1 NIRTTP/PCO/NITDB/NS/SHP- 37 / Procurement of firm for Determination of Border crossing and transportation Pending Improve Select Trade-Related Request for Single Stage - One time of Cargo.(Originating at IDA / 52730 Post Open - National 10,000.00 0.00 Implementati 2017-09-22 2017-11-17 2018-05-16 Infrastructure Quotations Envelope Kolkata to reach Kathmandu on and vice versa for the both Road and Railway mode of transportation) NP-MOC-23661-NC-RFB / Procurement of Design, Supply and Build National Single Window IT system in Strengthen Trade-Related Single Stage - Two Nepal ( Previous ID as per IDA / H8630 Institutional Capacity in Prior Request for Bids Open - International 12,780,000.00 7,608,077.56 Signed 2017-08-03 2017-10-19 2017-10-19 2018-01-17 2017-08-08 2017-12-28 2018-03-21 2018-03-12 2019-03-21 2018-04-16 2019-06-25 2019-10-08 Envelope approved PP 2017-01 is Nepal NIRTTP-MOCS-87-LPI-S- NIRTTP/PCO/DOC/NS/ICB- 1(Two stage bidding) NIRTTP/PCO/NITDB/SHP-65 / Border Crossing & Under Improve Select Trade-Related Request for Single Stage - One Transportation time of cargo IDA / 52730 Post Open - National 22,000.00 0.00 Implementati 2018-06-06 2018-06-13 2018-08-01 2018-09-30 Infrastructure Quotations Envelope (Raxaul-Birgunj-Kathmandu- on Birgunj) NIRTTP/PCO/DOTM/NS/DIR- 57 / Technical support for Modernize transport and maintenance of Vehicle IDA / 52730 transit arrangements between Post Direct Selection Direct 50,000.00 0.00 Canceled 2018-03-01 2017-12-17 2018-03-06 2018-04-10 2018-10-07 Fitness Testing Center(VFTC) Nepal and India and capacity Buildings of staffs NIRTTP/PCO/NS/SHP-31 / Modernize transport and Selection and Recruitment of / transit arrangements between Post Request for Bids Open - National 196,800.00 0.00 Canceled 1901-01-01 2015-10-02 1901-01-01 1901-01-01 2015-10-31 2019-12-31 Assistants for PCO Nepal and India NIRTTP/PCO/PPD/NS/SHP-38 Modernize transport and / Developmentof National Request for / transit arrangements between Post Limited - National 18,500.00 0.00 Canceled 2016-11-05 2016-11-14 2016-11-14 Pest Surveillance Management Quotations Nepal and India Information System NIRTTP/PCO/DOC/NS/SHP- Modernize transport and 32 / Selection & Recruitment / transit arrangements between Post Request for Bids Open - National 24,000.00 0.00 Canceled 1901-01-01 2015-05-15 1901-01-01 1901-01-01 2015-06-28 2019-06-30 of Office Secretay Nepal and India NIRTTP/PCO/DOC/NS/SHP- Strengthen Trade-Related Pending Request for Single Stage - One 94 / Internet Service for NNSW IDA / H8630 Institutional Capacity in Post Limited 1,200.00 0.00 Implementati 2019-08-16 2019-09-13 2020-09-12 Quotations Envelope PIU Office Nepal on NIRTTP/PCO/DOC/NS/SHP- Strengthen Trade-Related Pending Request for Single Stage - One 100 / Recruitment of IDA / H8630 Institutional Capacity in Post Open - National 7,200.00 0.00 Implementati 2019-08-25 2019-10-20 2021-09-19 Quotations Envelope Computer Operator for NNSW Nepal on NIRTTP/PCO/DOC/NS/SHP- Strengthen Trade-Related Pending Request for Single Stage - One 101 / Recruitment of Project IDA / H8630 Institutional Capacity in Post Open - National 7,200.00 0.00 Implementati 2019-08-25 2019-10-20 2021-09-19 Quotations Envelope Assistant for NNSW Nepal on NIRTTP/PCO/DOC/NS/SHP- Strengthen Trade-Related Pending Request for Single Stage - One 102 / Recruitment of Office IDA / H8630 Institutional Capacity in Post Open - National 6,000.00 0.00 Implementati 2019-08-25 2019-10-20 2021-09-19 Quotations Envelope Assistance for NNSW Nepal on NIRTTP/PCO/DOC/NS/SHP- Strengthen Trade-Related Pending Request for Single Stage - One 103 / Recruitment of Driver IDA / H8630 Institutional Capacity in Post Open - National 6,000.00 0.00 Implementati 2019-08-25 2019-10-20 2021-09-19 Quotations Envelope for NNSW Nepal on NP-MOC-134402-NC-RFQ / Modernize transport and Pending Request for Single Stage - One Internet Connection for RAIMS IDA / H8630 transit arrangements between Post Open - National 11,000.00 0.00 Implementati 2019-09-30 2019-12-03 2019-12-18 Quotations Envelope Stations Nepal and India on NP-MOC-134403-NC-RFQ / Modernize transport and Pending Request for Single Stage - One License for Core Router IDA / H8630 transit arrangements between Post Open - National 6,000.00 0.00 Implementati 2019-10-02 2019-11-21 2019-11-28 Quotations Envelope Firewall for RAIMS Nepal and India on NP-MOC-134404-NC-RFQ / Modernize transport and Pending Request for Single Stage - One License for Web Application IDA / H8630 transit arrangements between Post Open - National 20,000.00 0.00 Implementati 2019-09-30 2019-11-19 2019-11-26 Quotations Envelope Firewall Nepal and India on NP-MOC-134405-NC-RFQ / Modernize transport and Pending Request for Single Stage - One Secure Sockets Layer IDA / H8630 transit arrangements between Post Open - National 1,000.00 0.00 Implementati 2019-10-02 2019-11-21 2019-11-28 Quotations Envelope Certificate for RAIMS Nepal and India on NP-MOC-134407-NC-RFQ / Modernize transport and Pending Request for Single Stage - One Windows Server 2019 IDA / H8630 transit arrangements between Post Open - National 5,000.00 0.00 Implementati 2019-10-02 2019-11-21 2019-11-28 Quotations Envelope Standard License Nepal and India on NIRTTP/PCO/DOTM/NC/RFQ- Modernize transport and Pending 44 / Procurement of internet Request for Single Stage - One IDA / H8630 transit arrangements between Post Limited 10,500.00 0.00 Implementati 2021-01-27 2021-02-20 2021-03-07 connection for RA-IMS Quotations Envelope Nepal and India on operation NIRTTP/PCO/DOC/NS/RFQ- 121 / Provide and Connect Strengthen Trade-Related Pending Request for Single Stage - One fast Internet and Zoom service IDA / H8630 Institutional Capacity in Post Limited 2,100.00 0.00 Implementati 2021-06-24 2021-07-26 2021-11-23 Quotations Envelope in PIU for Virtual Training Nepal on Program. CONSULTING FIRMS Page 5 Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NIRTTP-DOR-S-QCBS-1 / Consulting services for Modernize transport and Quality And Cost- Feasibility study, Detailed IDA / 52730 transit arrangements between Prior Open - International 0.00 3,181,587.36 Signed 2015-06-25 2015-07-05 Based Selection design & Constr. supervision Nepal and India of various Roads NIRTTP/PCO/NITDB/S/QCBS- 23 / Design and Construction Improve Select Trade-Related Quality And Cost- Under IDA / H8630 Post Open - National 191,700.00 0.00 2015-10-12 2015-12-24 2016-01-15 2016-02-05 2017-02-05 Supervision of Railway Tracks Infrastructure Based Selection Implementation Modification at BirgunjICD NIRTTP/PCO/NITDB/S/QCBS- 46 / Detailed Design Review Improve Select Trade-Related Quality And Cost- Under and Supervision Consultant IDA / H8630 Post Open - International 350,000.00 0.00 2016-11-16 2017-01-31 2017-02-14 2018-06-01 2017-02-21 2019-06-30 Infrastructure Based Selection Implementation for Construction of ICD, Kathmandu NIRTTP/PCO/DOTM/S/LCS- 47 / Consulting Servieces to Modernize transport and support DOTM for bus routes, Least Cost Under IDA / 52730 transit arrangements between Post Open - National 75,000.00 0.00 2016-11-25 2017-03-01 2017-03-10 2017-03-31 2017-06-30 vehicle standard survey and Selection Implementation Nepal and India for preparing standard criteria for route permits NIRTTP/PCO/DOTM/S/CQS- Modernize transport and Quality And Cost- Under 48 / Survey and Detailed IDA / 52730 transit arrangements between Post Open - National 40,000.00 0.00 2018-08-30 2017-03-17 2017-05-25 2017-05-30 2017-06-02 2017-12-01 Based Selection Implementation Design Weigh Bridge Stations Nepal and India NIRTTP/PCO/S/CQS-52 / Modernize transport and Consultant Feasibility Study for FTA with Pending / transit arrangements between Post Qualification Open - National 18,500.00 0.00 2016-11-17 2017-01-02 2017-07-01 a Country considering long Implementation Nepal and India Selection term trade benefit to Nepal NIRTTP/PCO/DOC/S/QCBS-9 / Selection of Firm for Nepal National Single Window and Trade Portal Strengthen Trade-Related Quality And Cost- Implementation"Quality IDA / 52730 Institutional Capacity in Prior Open - International 1,930,000.00 1,636,533.58 Signed 2014-06-25 2014-10-20 2014-11-02 2015-06-09 2014-11-30 2015-06-18 2017-11-30 Based Selection Assurance and Advisory Nepal Services(including Bid document prepartion)(International) NIRTTP/PCO/NITB/S/QCBS- 17 / Selection of Project Modernize transport and Implementation/Supervision Quality And Cost- IDA / 52730 transit arrangements between Prior Open - National 228,735.63 240,862.34 Signed 2013-11-29 2014-05-15 2014-06-21 2014-07-07 2014-07-14 2014-07-07 2016-01-07 Consultant for NITDB (Birgunj Based Selection Nepal and India and Bhairahawa ICD Improvement works) NP-MOC-23665-CS-CQS-40 / Selection of firm for preparing Master Plan and Strengthen Trade-Related Consultant Detailed Design/Drawing of Pending IDA / H8630 Institutional Capacity in Post Qualification Open - National 65,000.00 0.00 2017-08-03 2017-08-24 2017-10-07 2017-11-06 2017-12-11 2018-06-09 Referral/SPS and Regional Implementation Nepal Selection Plant Protection Laboratory including Supervision of Constriction Works NITDB/PCO/PPD/S/QCBS-45 / Consulting Services for Pest Modernize transport and Quality And Cost- Surveillance in six major crops / transit arrangements between Post Open - National 124,000.00 0.00 Canceled 2016-11-11 2017-01-10 2017-01-10 2017-02-12 2017-07-12 Based Selection and Pest Detection Survey in Nepal and India three major medicinal Herbs NIRTTP/PCO/TEPC/S/QCBS- 39 / Selection of Firm for Strengthen Trade-Related Quality And Cost- Pending Development and IDA / H8630 Institutional Capacity in Post Open - International 570,000.00 0.00 2017-08-03 2017-08-24 2017-10-07 2017-11-04 2017-12-04 2018-01-08 2018-02-12 2019-02-12 Based Selection Implementation Implementation of the Nepal Nepal Trade Information Portal NIRTTP/PCO/DOTM/S/LCS- 26 / Consulting Servieces to Modernize transport and support DOTM for bus routes, Least Cost Under IDA / H8630 transit arrangements between Post Open - National 35,000.00 0.00 2017-09-12 2016-05-05 2017-10-03 2017-11-16 2017-12-14 2018-01-13 2018-02-17 2018-03-24 2018-09-20 vehicle standard survey and Selection Implementation Nepal and India for preparing standard criteria for route permits NIRTTP/PCO/NITDB/S/QCBS- 24 / Survey Environmental Improve Select Trade-Related Quality And Cost- Pending IDA / 52730 Post Open - National 240,000.00 0.00 2017-09-11 2017-10-02 2017-11-15 2017-12-13 2018-01-12 2018-02-16 2018-03-23 2019-03-23 Study and Detailed Design for Infrastructure Based Selection Implementation Kathmandu CFS/ICD NIRTTP/PCO/S/CQS-56 / Consultant's services for a comprehensive study of Nepal's existing transit Strengthen Trade-Related Consultant Pending agreements with India, IDA / H8630 Institutional Capacity in Post Qualification Open - National 30,000.00 0.00 2017-09-17 2017-10-08 2017-11-21 2017-12-21 2018-01-25 2018-07-24 Implementation Bangladesh and China and Nepal Selection receive recommendations for amendments and improvements NIRTTP/PCO/S/CQS-57 / Consultant's services for a comprehensive study on the Strengthen Trade-Related Consultant Pending potentiality of trade-in- IDA / H8630 Institutional Capacity in Post Qualification Open - National 30,000.00 0.00 2018-02-01 2018-02-22 2018-04-07 2018-05-07 2018-06-11 2018-12-08 Implementation services with SAARC countries Nepal Selection to develop Nepal's service trade NIRTTP/PCO/NITDB/S/CQS- Consultant 21 / Data Capture Framework Improve Select Trade-Related Pending IDA / 52730 Post Qualification Open - National 22,000.00 0.00 2017-09-17 2017-10-08 2017-11-21 2017-12-21 2018-01-25 2018-07-24 For Kolkata-Kathmandu Infrastructure Implementation Selection Corridor Monitoring NIRTTP/PCO/S/CQS-53 / Preparation of Mid-term and Modernize transport and Consultant Long-term Strategy Plan for / transit arrangements between Post Qualification Open - National 37,000.00 0.00 Canceled 2016-11-17 2017-01-02 2017-07-01 Trade sector including Nepal and India Selection infrastructure Page 6 NIRTTP/PCO/S/CQS-73 / Strengthen Trade-Related Consultant Study on Possibilities of Pending IDA / H8630 Institutional Capacity in Post Qualification Open - National 40,000.00 0.00 2018-12-01 2018-12-22 2019-02-04 2019-03-06 2019-04-10 2019-10-07 Transit Trade Facility through Implementation Nepal Selection Inland Water Wages NP-MOC-23681-CS-CQS-45- PPD / Consulting Services for Strengthen Trade-Related Consultant Pest Surveillance in six major IDA / H8630 Institutional Capacity in Post Qualification Open - National 124,000.00 0.00 Canceled 2017-08-04 2017-08-25 2017-10-08 2017-11-07 2017-12-12 2018-06-10 crops and Pest Detection Nepal Selection Survey in three major medicinal Herbs NIRTTP/PCO/NITDB/S/QCBS -55 / Design, Development and Operation of Corridor Improve Select Trade-Related Quality And Cost- Pending IDA / H8630 Post Open - National 278,000.00 0.00 2017-08-27 2017-09-17 2017-10-31 2017-11-28 2017-12-28 2018-02-01 2018-03-08 2020-03-07 Monitoring and Evaluation Infrastructure Based Selection Implementation Data Management System (CMEDMS) NIRTTP/PCO/DOTM/S/LCS- Modernize transport and 78 / Consulting service for Least Cost Pending IDA / H8630 transit arrangements between Post Open - National 40,000.00 0.00 2018-10-15 2018-11-05 2018-12-19 2019-01-16 2019-02-15 2019-03-22 2019-04-26 2019-10-23 "Construction Supervision of Selection Implementation Nepal and India weighbridge station " NIRTTP/PCO/DOTM/S/QCBS- 115 / Procurement of System Modernize transport and Quality And Cost- Under Development consultant for IDA / H8630 transit arrangements between Post Open - National 150,000.00 0.00 2020-01-20 2020-01-29 2020-02-04 2020-02-16 2020-02-21 2020-03-20 2020-04-04 2020-04-18 2020-05-02 2021-05-02 Based Selection Implementation GPS-Vehicle tracking system Nepal and India for Public buses NIRTTP/PCO/DOTM/S /CQS- 127 / Procurement of Strengthen Trade-Related Consultant Under Consultant for speed limit IDA / H8630 Institutional Capacity in Post Qualification Open - National 13,000.00 0.00 2020-11-23 2020-11-23 2020-11-30 2020-12-21 2020-12-28 2021-01-18 2021-07-17 Implementation study for pilot routes for GPS- Nepal Selection Vehicle Tracking System NIRTTP/PCO/NITDB/S/CQS- 112 / Pre-feasibility study Strengthen Trade-Related Consultant potential ICD/CFS at IDA / H8630 Institutional Capacity in Post Qualification Open - National 90,000.00 0.00 Under Review 2021-06-23 2021-06-24 2021-06-23 2021-07-14 2021-08-13 2021-09-04 2021-11-18 Hilsa/Yari, Olangchung Gola, Nepal Selection Kimanthanka and in Gandaki Province INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Modernize transport and Individual NIRTTP/PCO/S/IND-28 / IDA / 52730 transit arrangements between Prior Consultant Open 0.00 119,603.22 Canceled 2015-09-01 Technical Adviser to NITDB Nepal and India Selection NIRTTP/PCO/S/IND-19 / Modernize transport and Individual Selection of Expert for Study IDA / 52730 transit arrangements between Prior Consultant Limited 30,000.00 30,000.00 Signed 2014-07-10 2014-03-31 2014-07-04 2015-01-03 on Transshipment Nepal and India Selection NIRTTP/PCO/S/IND-27 / Modernize transport and Individual Selection of full time IDA / 52730 transit arrangements between Prior Consultant Limited 100,000.00 57,532.13 Signed 2015-09-16 2015-06-05 2015-09-17 2019-06-30 Procurement Nepal and India Selection Specialist/Consultant NIRTTP/PCO/S/IND-28 / Strengthen Trade-Related Individual Selection of Technical Adviser IDA / 52730 Institutional Capacity in Prior Consultant Limited 110,000.00 83,757.40 Signed 2015-11-26 2015-11-05 2015-12-09 2019-12-31 for NITDB Nepal Selection NIRTTP/PCO/DOTM/S/IND- Modernize transport and Individual 29 / Selection of Technical IDA / 52730 transit arrangements between Prior Consultant Limited 100,000.00 45,313.41 Signed 2015-12-28 2015-11-05 2015-12-31 2019-12-31 Adviser for DoTM (National) Nepal and India Selection NIRTTP/PCO/S/IND-30 / Modernize transport and Individual Selection of Trade Facilitation IDA / 52730 transit arrangements between Prior Consultant Limited 100,000.00 97,117.14 Signed 2015-09-23 2015-06-30 2015-09-23 2019-12-31 Adviser (National) Nepal and India Selection NIRTTP/PCO/S/IND-31 / Modernize transport and Individual Selection of Trade IDA / 52730 transit arrangements between Prior Consultant Limited 100,000.00 101,175.24 Signed 2015-09-01 2015-06-30 2015-09-14 2019-12-31 Development Adviser for PCO Nepal and India Selection NIRTTP/PCO/PPD/S/IND-44 / Strengthen Trade-Related Individual Selection of Expert for Under IDA / H8630 Institutional Capacity in Post Consultant Limited 23,500.00 17,800.00 2016-12-12 2016-12-12 updating National Phyto- Implementation Nepal Selection Sanitary System of Nepal NIRTTP/PCO/PPD/S/IND-43 / Selection of Expert for Plant Modernize transport and Individual Pending Health Management study / transit arrangements between Post Consultant Limited 9,500.00 0.00 2016-12-12 2016-12-12 Implementation based on Traditional Nepal and India Selection Transborder Trade NIRTTP/PCO/S/IND-49 / Modernize transport and Individual Selection of Non Tariff Pending / transit arrangements between Post Consultant Limited 70,000.00 0.00 2016-12-15 2019-06-30 Measures (NTM) Tracking Implementation Nepal and India Selection System Analyst NIRTTP/PCO/S/IND-50 / Modernize transport and Individual Selection of Consultant for Pending / transit arrangements between Post Consultant Limited 18,500.00 0.00 2016-12-04 2016-12-04 study on Improvement of Implementation Nepal and India Selection Nepal-India Trading Regime NIRTTP/PCO/DOC/S/IND-50 / Selection of an International Strengthen Trade-Related Individual Procurement IDA / 52730 Institutional Capacity in Prior Consultant Limited 50,000.00 0.00 Canceled 2017-01-16 2017-07-15 Specialist/Consultant Nepal Selection (Intermittent) NIRTTP/PCO/DOC/S/IND-51 Strengthen Trade-Related Individual / Selection of an International IDA / 52730 Institutional Capacity in Post Consultant Limited 50,000.00 0.00 Canceled 2017-01-16 2017-07-15 IT Specialist/Consultant Nepal Selection (Intermittent) Page 7 NIRTTP/PCO/S/IND-52 / Strengthen Trade-Related Individual Selection of full time Under IDA / H8630 Institutional Capacity in Prior Consultant Limited 87,000.00 0.00 2017-01-18 2019-12-31 Procurement Implementation Nepal Selection Adviser/Consultant NIRTTP/PCO/S/IND-11 / Modernize transport and Individual Selection of full time IDA / 52730 transit arrangements between Prior Consultant Limited 18,045.98 21,496.57 Signed 2014-03-14 1901-01-01 2014-02-18 2014-07-15 Procurement Nepal and India Selection Specialist/Consultant NIRTTP/PCO/NITDB/S/IND- Strengthen Trade-Related Individual Under 18 / Selection of Engineering IDA / 52730 Institutional Capacity in Post Consultant Limited 17,241.38 0.00 2015-12-04 2019-12-31 Implementation Support to NITDB Nepal Selection NIRTTP/PCO/S/IND-13 / Strengthen Trade-Related Individual Selection of Environmental Pending IDA / H8630 Institutional Capacity in Post Consultant Open 40,000.00 0.00 2017-09-12 2017-10-31 2017-11-21 2017-12-26 2019-12-31 Safeguards Specialist Implementation Nepal Selection (Intermittent) NIRTTP/PCO/S/IND-14 / Strengthen Trade-Related Individual Pending Selection of Social Safeguards IDA / H8630 Institutional Capacity in Post Consultant Open 35,000.00 0.00 2017-09-12 2017-10-31 2017-11-21 2017-12-26 2018-06-24 Implementation Specialist (Intermittent) Nepal Selection NIRTTP/PCO/S/IND-58 / Consultanting service for the Strengthen Trade-Related Individual development of a system on Pending IDA / H8630 Institutional Capacity in Post Consultant Open 40,000.00 0.00 2018-03-01 2018-04-19 2018-05-10 2018-06-14 2018-12-11 Non-Tariff Measures of major Implementation Nepal Selection export markets for export promotion measures in Nepal NIRTTP/PCO/DOTM/IND-4 / Modernize transport and Individual Pending Selection of Project Assistant IDA / H8630 transit arrangements between Post Consultant Open 50,000.00 0.00 2017-09-17 2017-11-05 2017-11-26 2017-12-31 2019-12-31 Implementation for DOTM (National) Nepal and India Selection NIRTTP/PCO/NITDB/S/SSS- Improve Select Trade-Related Under 42 / Selection of Corridor IDA / 52730 Post Direct Selection Direct 3,000.00 2,698.86 2017-09-17 2017-09-27 2017-12-01 2018-05-30 Infrastructure Implementation Monitoring Consultant NIRTTP/PCO/PPD/S/IND-59 / Strengthen Trade-Related Individual Consultant for preparation of Pending IDA / H8630 Institutional Capacity in Post Consultant Open 20,000.00 0.00 2018-02-28 2018-04-18 2018-05-09 2018-06-13 2018-09-11 pest surveillance of 100 pests Implementation Nepal Selection of 10 major crops NITTP/PCO/PPD/S/IND-60 / Strengthen Trade-Related Individual Preparation of Internal Pending IDA / H8630 Institutional Capacity in Post Consultant Open 15,000.00 0.00 2018-01-01 2018-02-19 2018-03-12 2018-04-16 2018-07-15 Quarantine Procedure and Implementation Nepal Selection Guideline NIRTTP/PCO/S/IND-54 / Preparation of Mid-term and Strengthen Trade-Related Individual Pending long-term strategy plan for IDA / H8630 Institutional Capacity in Post Consultant Open 50,000.00 0.00 2017-11-01 2017-12-20 2018-01-10 2018-02-14 2018-08-13 Implementation trade sector including Nepal Selection infrastructure NIRTTP/PCO/DOTM/S/IND- Strengthen Trade-Related Individual 56 / Selection of Technical IDA / 52730 Institutional Capacity in Prior Consultant Open 50,000.00 56,815.29 Signed 2018-01-01 2018-02-19 2017-12-31 2018-03-12 2018-01-04 2018-04-16 2018-01-05 2019-12-31 Adviser for DoTM (National) Nepal Selection NIRTTP/PCO/PPD/IND-61 / Civil Engineer( Intermittent) Strengthen Trade-Related Individual Pending For supervision of IDA / H8630 Institutional Capacity in Post Consultant Open 16,000.00 0.00 2018-05-01 2018-06-19 2018-07-10 2018-08-14 2019-02-10 Implementation Construction work under Nepal Selection NIRTTP project NIRTTP/PCO/DOTM/S/IND- 54 / Selection of an Modernize transport and Individual International Consultant to Under IDA / H8630 transit arrangements between Post Consultant Limited 25,000.00 0.00 2018-08-08 2018-08-12 2018-10-15 2018-10-30 2019-04-30 2019-09-30 Support Establishment and Implementation Nepal and India Selection Operation of Vehicle Fitness Testing Center in Nepal NIRTTP/PCO/S/IND-74 / Strengthen Trade-Related Individual Pending Study on Possibility of Service IDA / H8630 Institutional Capacity in Post Consultant Open 30,000.00 0.00 2018-09-02 2018-10-21 2018-11-11 2018-12-16 2019-06-14 Implementation trade with SAARC countires Nepal Selection NIRTTP/PCO/S/IND-34 / Modernize transport and Individual Selection of MoCS Capacity / transit arrangements between Post Consultant Limited 110,000.00 0.00 Canceled 2015-10-30 2019-12-31 Enhancement Specialist Nepal and India Selection (National) NIRTTP/PCO/S/IND-15 / Modernize transport and Individual Selection of Finance / transit arrangements between Post Consultant Limited 18,045.98 0.00 Canceled 2015-11-15 2019-12-31 Specialist/Consultant Nepal and India Selection NIRTTP/PCO/DOC/S/IND-26 / Selection of Legal Adviser Modernize transport and Individual for Dept. of Customs for / transit arrangements between Prior Consultant Limited 1,700.00 0.00 Canceled 2015-11-30 2019-06-30 advice on the proposed Single Nepal and India Selection Window System NIRTTP/PCO/S/IND-53 / Selection of Senior Modernize transport and Individual Procurement / transit arrangements between Prior Consultant Limited 22,500.00 0.00 Canceled 2017-01-31 2019-06-30 Specialist/Consultant Nepal and India Selection (Intermittent) NIRTTP/PCO/S/IND-51 / Selection of Consultant for Modernize transport and Individual study on Requirements of / transit arrangements between Post Consultant Limited 18,500.00 0.00 Canceled 2016-12-04 2016-12-04 Additional Facility in Birgunj Nepal and India Selection Integrated Check Point (ICP) NIRTTP/PCO/NITDB/S/IND- Strengthen Trade-Related Individual Under 67 / Social Safeguard IDA / H8630 Institutional Capacity in Post Consultant Open 15,000.00 0.00 2018-12-01 2019-01-22 2019-01-19 2019-02-09 2019-03-16 2020-01-30 Implementation Mobiliser Nepal Selection Page 8 NIRTTP/PCO/S/IND-68 / Study on reorganizing the Nepal Transit and Strengthen Trade-Related Individual Under Waterhousing Company IDA / H8630 Institutional Capacity in Post Consultant Open 7,000.00 0.00 2018-12-31 2019-02-18 2019-03-11 2019-04-15 2019-06-14 Implementation Limited (NTWCL) and the Nepal Selection Nepal Inter-modal transport Development Board(NITDB) NIRTTP/PCO/TEPC/S/IND-69 / Project Management Advisor Strengthen Trade-Related Individual for Quality Assurance and Under IDA / H8630 Institutional Capacity in Post Consultant Open 24,000.00 0.00 2018-12-31 2018-12-10 2019-02-18 2019-03-11 2019-04-15 2019-06-14 Advisory Services in Support Implementation Nepal Selection of Nepal Trade Information Portal Extension NIRTTP/PCO/TEPC/S/IND-70 / National IT Specialist for Strengthen Trade-Related Individual Quality Assurance and Under IDA / H8630 Institutional Capacity in Post Consultant Open 5,000.00 0.00 2018-12-31 2018-12-10 2019-02-18 2019-03-11 2019-04-15 2019-06-14 Advisory Services in Support Implementation Nepal Selection of Nepal Trade Information Portal Extension NIRTTP/PCO/PPD/S/IND-67 / Study to find out modality to Strengthen Trade-Related Individual Under provide efficient plant IDA / H8630 Institutional Capacity in Post Consultant Open 10,000.00 0.00 2019-03-01 2019-01-28 2019-04-19 2019-05-10 2019-06-14 2019-08-13 Implementation protection services in Federal Nepal Selection and Provinces NIRTTP/PCO/NITDB/S/IND- Strengthen Trade-Related Individual Under 71 / Social Safeguard Expert IDA / H8630 Institutional Capacity in Post Consultant Open 26,000.00 0.00 2019-01-22 2019-01-24 2019-03-12 2019-04-02 2019-05-07 2019-11-23 Implementation for Kathmandu ICD Nepal Selection NIRTTP/PCO/S/IND-72 / Strengthen Trade-Related Individual Preparation of Strategies for Under IDA / H8630 Institutional Capacity in Post Consultant Open 6,000.00 0.00 2019-04-15 2019-04-19 2019-06-03 2019-06-24 2019-07-29 2019-09-27 Export Promotion to the Implementation Nepal Selection European Union (EU) NIRTTP/PCO/S/IND-73 / Strengthen Trade-Related Individual Under Preparation of Strategies for IDA / H8630 Institutional Capacity in Post Consultant Open 7,000.00 0.00 2019-04-15 2019-04-19 2019-06-03 2019-06-24 2019-07-29 2019-09-27 Implementation Export Promotion to India Nepal Selection NIRTTP/PCO/IND-75 / Strengthen Trade-Related Individual Preparation of Strategies for Under IDA / H8630 Institutional Capacity in Post Consultant Open 5,000.00 0.00 2019-04-15 2019-04-19 2019-06-03 2019-06-24 2019-07-29 2019-09-27 Export Promotion to the Implementation Nepal Selection United Arab Emirates (UAE) NIRTTP/PCO/DOTM/S/IND- 77 / "System Design and Modernize transport and Individual Under software/hardware IDA / H8630 transit arrangements between Post Consultant Open 5,000.00 0.00 2019-04-30 2019-05-15 2019-05-26 2019-06-02 2019-06-24 2019-08-23 Implementation requirement for GPS vehicle Nepal and India Selection tracking system" NIRTTP/PCO/S/IND-80 / Strengthen Trade-Related Individual Under Environmental Specialist IDA / H8630 Institutional Capacity in Post Consultant Open 19,000.00 0.00 2019-05-05 2019-05-21 2019-05-31 2019-06-07 2019-06-29 2019-12-31 Implementation Consultant (National) Nepal Selection NIRTTP/PCO/DOC/S/SSS-87 / Quality Assurance and Advisory Services for Strengthen Trade-Related Implementation of Nepal IDA / H8630 Institutional Capacity in Post Direct Selection Direct 970,000.00 817,285.64 Signed 2019-08-01 2019-11-10 2019-08-11 2019-12-31 2019-10-15 2020-08-19 2021-10-14 National Single Window Nepal System & NTIP Extension work (TEPC) NIRTTP/PCO/DOC/S/IND-88 Strengthen Trade-Related Individual / Nepal National Single Pending IDA / H8630 Institutional Capacity in Post Consultant Open 60,000.00 0.00 2019-10-01 2019-11-19 2019-12-10 2020-01-14 2021-12-24 Window Project management Implementation Nepal Selection Consultant NIRTTP/PCO/S/IND-105 / Strengthen Trade-Related Individual Pending Preparation of Strategies for IDA / H8630 Institutional Capacity in Post Consultant Open 7,000.00 0.00 2019-08-30 2019-10-18 2019-11-08 2019-11-22 2020-01-01 Implementation Export Promotion to UK Nepal Selection NIRTTP/PCO/S/IND-106 / Strengthen Trade-Related Individual Pending Preparation of Strategies for IDA / H8630 Institutional Capacity in Post Consultant Open 7,000.00 0.00 2019-08-30 2019-10-18 2019-11-08 2019-11-22 2020-01-01 Implementation Export Promotion to EU Nepal Selection NIRTTP/PCO/S/IND-107 / Strengthen Trade-Related Individual Pending Preparation of Strategies for IDA / H8630 Institutional Capacity in Post Consultant Open 7,000.00 0.00 2019-08-30 2019-10-18 2019-11-08 2019-11-22 2020-01-01 Implementation Export Promotion to Japan Nepal Selection NIRTTP/PCO/S/IND-108 / Strengthen Trade-Related Individual Pending Preparation of Strategies for IDA / H8630 Institutional Capacity in Post Consultant Open 7,000.00 0.00 2019-08-30 2019-10-18 2019-11-08 2019-11-22 2020-01-01 Implementation Export Promotion to Canada Nepal Selection NIRTTP/PCO/S/IND-109 / Strengthen Trade-Related Individual Preparation of Strategies for Pending IDA / H8630 Institutional Capacity in Post Consultant Open 7,000.00 0.00 2019-08-30 2019-10-18 2019-11-08 2019-11-22 2020-01-01 Export Promotion to Implementation Nepal Selection Bangladesh Strengthen Trade-Related Individual NIRTTP/PCO/S/IND-99 / Under IDA / H8630 Institutional Capacity in Prior Consultant Open 56,000.00 0.00 2019-08-18 2019-11-28 2019-10-06 2019-10-27 2019-12-01 2021-12-31 Procurement Specialist Implementation Nepal Selection NIRTTP/PCO/S/IND-110 / A Strengthen Trade-Related Individual Under study on export prospects of IDA / H8630 Institutional Capacity in Post Consultant Open 10,000.00 0.00 2019-11-11 2019-11-25 2019-12-10 2019-12-17 2019-12-31 2020-03-30 Implementation drinking water in Nepal Nepal Selection NIRTTP/PCO/S/IND-111 / Preparation of strategic plan Modernize transport and Individual Under of commerce sector of Nepal IDA / H8630 transit arrangements between Post Consultant Open 27,500.00 0.00 2019-11-27 2020-01-06 2019-12-26 2020-01-02 2020-01-16 2020-04-25 Implementation with separate medium term Nepal and India Selection and long term plan of actions. NIRTTP/PCO/DOTM/S/IND- Modernize transport and Individual 116 / Procurement of System Under IDA / H8630 transit arrangements between Post Consultant Limited 30,000.00 0.00 2020-01-20 2020-01-29 2020-02-04 2020-02-11 2020-03-03 2021-07-16 Supervision Consultant for Implementation Nepal and India Selection GPS-Vehicle Tracking System Page 9 NIRTTP/PCO/NITDB/S/IND- Strengthen Trade-Related Individual Under 100 / Procurement of Social IDA / H8630 Institutional Capacity in Post Consultant Direct 7,000.00 0.00 2020-07-30 2020-08-04 2020-08-04 2020-08-04 2021-01-31 Implementation Safeguard mobilizer Nepal Selection NIRTTP/PCO/DOTM//IND- Strengthen Trade-Related Individual Under 101 / Hiring of Technical IDA / H8630 Institutional Capacity in Post Consultant Direct 12,000.00 0.00 2020-07-31 2020-09-11 2020-08-01 2020-08-01 2020-08-01 2021-01-28 Implementation Advisor for DoTM (National) Nepal Selection NIRTTP/PCO/S/IND-102 / Strengthen Trade-Related Individual Under Hiring of Environmental IDA / H8630 Institutional Capacity in Post Consultant Direct 9,000.00 0.00 2020-07-31 2020-08-01 2020-08-01 2020-08-01 2021-01-28 Implementation Safeguard Specialist (National) Nepal Selection NIRTTP/PCO/S/IND-103 / Strengthen Trade-Related Individual Under Hiring of Social Safeguard IDA / H8630 Institutional Capacity in Post Consultant Direct 8,000.00 0.00 2020-07-31 2020-08-01 2020-08-01 2020-08-01 2021-01-28 Implementation Specialist Nepal Selection NIRTTP/PCO/S/IND-104 / Strengthen Trade-Related Individual Hiring of Trade Development IDA / H8630 Institutional Capacity in Post Consultant Direct 14,000.00 0.00 Canceled 2020-07-31 2020-08-01 2020-08-01 2020-08-01 2021-01-28 Adviser Nepal Selection NIRTTP/PCO/S/IND-122 / Strengthen Trade-Related Individual Under Hiring of Senior Infrastructure IDA / H8630 Institutional Capacity in Post Consultant Direct 8,000.00 0.00 2020-07-31 2020-08-01 2020-08-01 2020-08-01 2021-01-28 Implementation Engineer Nepal Selection NIRTTP/PCO/S/IND-123 / Strengthen Trade-Related Individual Under Hiring of Trade Facilitator IDA / H8630 Institutional Capacity in Post Consultant Direct 12,000.00 0.00 2020-07-31 2020-07-31 2020-08-01 2020-08-01 2020-08-01 2021-01-28 Implementation Adviser Nepal Selection NIRTTP/PCO/S/IND-124 / Strengthen Trade-Related Individual Hiring of Procurement and Under IDA / H8630 Institutional Capacity in Prior Consultant Open 28,000.00 0.00 2020-08-07 2020-09-09 2020-10-05 2020-10-26 2020-11-30 2021-11-30 Contract Management Implementation Nepal Selection Specialist NIRTTP/PCO/S/IND-104-2 / Strengthen Trade-Related Individual Under Hiring of Trade Development IDA / H8630 Institutional Capacity in Post Consultant Open 26,000.00 0.00 2020-08-23 2020-08-28 2020-10-05 2020-10-19 2020-11-16 2021-11-16 Implementation Adviser Nepal Selection NIRTTP/PCO/MOALD/S/IND- 125 / Hiring of Individual Strengthen Trade-Related Individual Consultant for Sanitary and Under IDA / H8630 Institutional Capacity in Post Consultant Limited 6,500.00 0.00 2020-09-13 2020-09-14 2020-09-16 2020-09-30 2020-10-14 2021-04-12 Phytosanitary (SPS) /Plant Implementation Nepal Selection Quarantine and Regional Plant Protection Laboratory NIRTTP/PCO/MOALD/S/IND- 126 / Hiring of Individual Strengthen Trade-Related Individual Consultant for preparing Under IDA / H8630 Institutional Capacity in Post Consultant Direct 1,000.00 0.00 2020-11-06 2020-11-16 2020-11-23 2020-12-14 2021-06-12 furniture specifications and Implementation Nepal Selection related documents for SPS laboratory. NIRTTP/PCO/S/IND-128 / Procurement of Individual Strengthen Trade-Related Individual Consultant for feasibility Under IDA / H8630 Institutional Capacity in Post Consultant Limited 8,600.00 0.00 2020-12-24 2020-12-20 2020-12-31 2021-01-14 2021-02-12 2021-05-13 study of service trade of Nepal Implementation Nepal Selection with India and SAARC countries. NIRTTP/PCO/NITDB/S/IND- Strengthen Trade-Related Individual Under 129 / Hiring of Environmental IDA / H8630 Institutional Capacity in Post Consultant Open 12,000.00 0.00 2021-01-10 2021-01-13 2021-02-14 2021-02-21 2021-03-14 2021-11-29 Implementation Safeguard for NITDB ,ICD Nepal Selection NIRTTP/PCO/NITDB/S/IND- Strengthen Trade-Related Individual Under 130 / Hiring of Social IDA / H8630 Institutional Capacity in Post Consultant Open 12,000.00 0.00 2021-01-10 2021-01-13 2021-02-14 2021-02-28 2021-03-14 2021-11-29 Implementation Safeguard for NITDB, ICD Nepal Selection NIRTTP/PCO/NITDB/S/IND- Strengthen Trade-Related Individual Under 131 / Hiring of Social IDA / H8630 Institutional Capacity in Post Consultant Open 4,200.00 0.00 2021-01-10 2021-02-14 2021-02-21 2021-03-14 2021-11-29 Implementation mobiliser for ICD Nepal Selection NIRTTP/PCO/NITDB/S/IND- Strengthen Trade-Related Individual 132 / Hiring of Senior Under IDA / H8630 Institutional Capacity in Post Consultant Open 12,000.00 0.00 2021-01-10 2021-01-19 2021-02-14 2021-02-21 2021-03-14 2021-11-29 infrastructure Engineer for Implementation Nepal Selection NITDB NIRRTP/PCO/NITDB/S/IND- 133 / Hiring of Strengthen Trade-Related Individual Under Communications and IDA / H8630 Institutional Capacity in Post Consultant Open 12,000.00 0.00 2021-01-10 2021-02-14 2021-02-21 2021-03-14 2021-11-29 Implementation Stakeholder Engagement Nepal Selection Specialist for NITDB NIRTTP/PCO/NITDB/S/IND- Strengthen Trade-Related Individual 134 / Hiring of Occupational Under IDA / H8630 Institutional Capacity in Post Consultant Open 12,000.00 0.00 2021-01-10 2021-02-14 2021-02-28 2021-03-14 2021-11-29 Health and Safety Safeguard Implementation Nepal Selection for NITDB NIRTTP/PCO/DOTM/S/IND- Strengthen Trade-Related Individual Under 135 / Hiring of Technical IDA / H8630 Institutional Capacity in Post Consultant Open 20,000.00 0.00 2021-01-10 2021-01-18 2021-02-14 2021-02-21 2021-03-14 2021-11-29 Implementation Adviser for DoTM Nepal Selection Page 10 PROCUREMENT PLAN (Textual Part) Project information: West Bengal Electricity Distribution Grid Modernization Project (P170590) Project Implementation agency: West Bengal State Electricity Distribution Company Limited (WBSEDCL) Date of the Procurement Plan: 22 June 2020 Period covered by this Procurement Plan: June 2020 - until publication of next revision Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016, revised August 2018) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. Most of the procurements will follow NPP procedure using Bank’s National Procurement Document. National Procurement Arrangements: National competition for the procurement of goods, works and non-consulting services according to the established thresholds will be conducted in accordance with paragraphs 5.3 – 5.6 of Section V of the Regulations and the following provisions: a. Only the model bidding documents for National Competitive Procurement agreed with the GOI Task Force (and as amended for time to time), shall be used for bidding. b. Invitations to bid shall be advertised on a widely used website or electronic portal with free open access at least 30 days prior to the deadline for the submission of bids, unless otherwise agreed in the approved procurement plan. c. No special preference will be accorded to any bidder either for price or for other terms and conditions when competing with foreign bidders, state- owned enterprises, small-scale enterprises or enterprises from any given State. d. Except with the prior concurrence of the Bank, there shall be no negotiation of price with the bidders, even with the lowest evaluated bidder. e. GeM set-up by Ministry of Commerce, Government of India will be acceptable for procurement under Request for Quotations1 method. f. At the Borrower’s request, the Bank may agree to the Borrower’s use, in whole or in part, of its electronic procurement system, provided that the Bank is satisfied with the adequacy of such system. g. Procurement will be open to eligible firms from any country. This eligibility shall be as defined under Section III of the Procurement Regulations. Accordingly, no bidder or potential bidder shall be declared ineligible for contracts financed by the Bank for reasons other than those provided in Section III of the Procurement Regulations. h. The Request for Bids/Request for Proposals document shall require that Bidders/Proposers submitting Bids/Proposals include a signed acceptance in the bid, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. i. The Borrower shall use an effective complaints mechanism for handling procurement related complaints in a timely manner. j. Procurement Documents will include provisions, as agreed with the Bank, intended to adequately mitigate against environmental, social (including sexual exploitation and abuse and gender-based violence), health and safety risks and impacts. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: will be applicable for those contracts identified in the Procurement Plan table; Works: Not applicable Other Relevant Procurement Information. Procurement Plan: The Implementing Agencies shall prepare a procurement plan and will submit to the Bank through STEP portal for all activities barring which special exemption given by the Bank for not using 1 To the extent possible, competitive bidding/e-RA options will be used while using GeM STEP. The approved procurement plan shall be automatically disclosed to the public through STEP portal. Project Procurement Strategy for Development (PPSD): PPSD has been prepared by the Borrower with Bank’s support and outcome of PPSD is updated in the procurement plan. Procurement Methods/Threshold Procurement Approaches and Thresholds (US$ equivalent) Methods Open international (Works) Any value Open national (Works) Up to 40 million Open international (goods, IT Any value system, and non-consulting services) Open national (goods, IT system, Up to 10 million and non-consulting services) National request for quotation Up to 100,000 (works, goods , IT & NCS) Direct selection No threshold; For goods/non-consulting services: According to paragraphs 6.8–6.10 of the Regulations; For consultants: According to paragraphs 7.13–7.15 of the Regulations Shortlist of national consultants Up to 800,000 Procurement prior-review thresholds. The World Bank will prior review the following contracts: (a) Works: All contracts more than US$10 million equivalent (b)Goods and IT system: All contracts more than US$2 million equivalent (c) Non-consulting services: All contracts more than US$2 million equivalent (d)Consultants (Firms): All contracts >US$1 million equivalent and (e) Consultants (Individual): All contracts >US$300,000 equivalent (f) Irrespective of the contract value, the following procurement activities are subject to the Bank’s procurement prior review: • procurement processes involving contract negotiations, as described in Section VI, paragraphs 6.34-36, of the Procurement Regulation for Borrowers • competitive dialogue; • sustainable procurement; • selection of probity assurance providers, as described in Section III, paragraph 3.3 of the Procurement Regulations for Borrowers; and • best and final offer. Post Review: All contracts not subject to prior review by the World Bank will be subject to post review during the project’s Implementation Support Missions (ISM) and/or special post review missions including missions by consultants hired by the Bank. The World Bank may conduct, at any time, independent procurement reviews of all the contracts financed under the loan. Also, if there are internal audits carried out for sample procurements, the Borrower may consult with the World Bank to include the Bank’s requirements under the TOR for such audits, in which case the Bank will only review the internal audit reports. Tentative Procurement plan (First 03 months) S.N Activity Name of Est. Meth Bank Oversight Expected Expected . No Activity Cost od/A date of date of (US$ ppro publication signing of Million ach of IFB/ RFP contract ) 1 HVDS-1 HVDS in 11.87 NCB Prior review Aug-20 Nov-20 Alipurduar (S & District I) HVDS-2 HVDS in 11.87 NCB Prior review Aug-20 Nov-20 Coochbehar (S & District I) 2 HVDS-3 HVDS in 11.87 NCB Prior review Aug-20 Nov-20 Jalpaiguri District (S & I) HVDS-4 HVDS in 11.87 NCB Prior review Aug-20 Nov-20 Darjeeling (S & District I) 3 HVDS-5 HVDS in Uttar 11.87 NCB Prior review Aug-20 Nov-20 Dinajpur District S.N Activity Name of Est. Meth Bank Oversight Expected Expected . No Activity Cost od/A date of date of (US$ ppro publication signing of Million ach of IFB/ RFP contract ) (S & I) HVDS-6 HVDS in Dakshin 11.87 NCB Prior review Aug-20 Nov-20 Dinajpur District (S & I) 4 HVDS-7 HVDS in Malda 11.87 NCB Prior review Aug-20 Nov-20 District (S & I) HVDS-8 HVDS in Nadia 11.87 NCB Prior review Aug-20 Nov-20 District (S & I) 5 HVDS-9 HVDS in Howrah 11.87 NCB Prior review Aug-20 Nov-20 District (S & I) HVDS-10 HVDS in Purba 11.87 NCB Prior review Aug-20 Nov-20 Midnapur District (S & I) 6 HVDS-11 HVDS in Bankura 11.87 NCB Prior review Aug-20 Dec-20 District (S & I) HVDS-12 HVDS in Purulia 11.87 NCB Prior review Aug-20 Dec-20 District (S & I) 7 HVDS-13 HVDS in 11.87 NCB Prior review Aug-20 Dec-20 Murshidabad (S & District I) PROCUREMENT India : West Bengal Electricity Distribution Grid Modernization Project PLAN General Information Country: India Bank’s Approval Date of the Original Procurement Plan: 2020-06-22 2021-05-19 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P170590 GPN Date: 2020-03-03 Project Name: West Bengal Electricity Distribution Grid Modernization Project Loan / Credit No: / W Executing Agency(ies): est Bengal State Electricity Distribution Company Limited WORKS Procureme Activity Reference No. / Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH nt Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) Justification for Award Type Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-WBSEDCL-183966-CW- RFB / Implementation of High Under Distribution System Single Stage - Two 6,316,742.9 2022-12- Voltage Distribution System / Prior Request for Bids Open - National Implementat 2020-07-20 2020-07-27 2020-08-05 2020-08-07 2020-09-04 2020-09-22 2020-11-10 2020-12-14 2020-12-23 Strengthening Envelope 6 22 (HVDS) in Howrah district of ion West Bengal IN-WBSEDCL-183989-CW- RFB / Implementation of High Under Distribution System Single Stage - Two 6,856,037.0 2022-12- Voltage Distribution System / Prior Request for Bids Open - National Implementat 2020-07-20 2020-07-27 2020-08-05 2020-08-07 2020-09-04 2020-09-22 2020-11-10 2020-12-13 2020-12-23 Strengthening Envelope 1 22 (HVDS) in Purba Midnapur ion district of West Bengal IN-WBSEDCL-187644-CW- RFB / Conversion of overhead Under Distribution System Single Stage - Two 2023-01- network to underground / Prior Request for Bids Open - National 0.00 Implementat 2020-08-14 2020-08-24 2020-08-25 2020-08-26 2020-09-29 2020-09-29 2020-11-10 2020-12-29 2021-01-31 Strengthening Envelope 30 cabling system for Baruipur ion Town IN-WBSEDCL-189633-CW- RFB / Implementation of High Under Voltage Distribution System Distribution System Single Stage - Two 11,345,475. 2023-01- / Prior Request for Bids Open - National Implementat 2020-08-25 2020-08-31 2020-09-04 2020-09-04 2020-10-09 2020-11-03 2020-12-04 2021-02-12 2021-01-31 (HVDS) in Alipurduar and Strengthening Envelope 85 30 ion Coochbehar districts of West Bengal IN-WBSEDCL-189638-CW- RFB / Implementation of High Under Voltage Distribution System Distribution System Single Stage - Two 18,959,985. 2023-01- / Prior Request for Bids Open - National Implementat 2020-08-25 2020-09-01 2020-09-04 2020-09-04 2020-10-09 2020-11-03 2020-12-04 2021-02-10 2021-01-31 (HVDS) in Uttar Dinajpur, Strengthening Envelope 75 30 ion Dakshin Dinajpur and Malda districts of West Bengal IN-WBSEDCL-189639-CW- RFB / Implementation of High Under Distribution System Single Stage - Two 11,274,497. 2023-01- Voltage Distribution System / Prior Request for Bids Open - National Implementat 2020-08-25 2020-08-31 2020-09-04 2020-09-04 2020-10-09 2020-11-03 2020-12-04 2021-02-02 2021-01-31 Strengthening Envelope 14 30 (HVDS) in Bankura and Purulia ion districts of West Bengal IN-WBSEDCL-189972-CW- RFB / Supply and Installations of 02 nos. New 33/11 KV Sub- Under Distribution System Single Stage - Two 2022-07- Stations and associated 33 KV / Post Request for Bids Open - National 0.00 Implementat 2020-08-25 2020-08-26 2020-08-26 2020-08-26 2020-09-29 2020-09-29 2020-11-10 2020-12-03 2021-01-31 Strengthening Envelope 30 & 11 KV lines in Alipurduar ion Region of WBSEDCL in West Bengal. IN-WBSEDCL-211042-CW- RFB / Conversion of Overhead Network into Underground Under Distribution System Single Stage - Two 2023-04- cable system at Rajarhat Town / Prior Request for Bids Open - National 0.00 Implementat 2020-12-24 2021-01-11 2021-01-05 2021-01-13 2021-02-08 2021-03-25 2021-03-03 2021-06-06 2021-04-30 Strengthening Envelope 29 under North 24 Parganas ion district within the state of West Bengal IN-WBSEDCL-211050-CW- RFB / Conversion of Overhead Network into Underground Under Distribution System Single Stage - Two 2023-04- cable system at Baguiati and / Prior Request for Bids Open - National 0.00 Implementat 2020-12-24 2021-01-11 2021-01-05 2021-01-13 2021-02-08 2021-02-08 2021-03-03 2021-06-08 2021-04-30 Strengthening Envelope 29 Keshtopur Towns under North ion 24 Parganas district within the state of West Bengal IN-WBSEDCL-211428-CW- RFB / Implementation of High Under Voltage Distribution System Distribution System Single Stage - Two 2023-05- / Prior Request for Bids Open - National 0.00 Implementat 2020-12-30 2021-01-04 2021-01-05 2021-01-05 2021-02-05 2021-02-10 2021-03-09 2021-05-24 2021-05-06 (HVDS) in Nadia and Strengthening Envelope 05 ion Murshidabad districts of West Bengal (2 packages) IN-WBSEDCL-234470-CW- RFB / Supply and Installation of High Voltage Distribution Other (with Under Distribution System Single Stage - Two 2023-09- System (HVDS) in semi-urban / Prior Request for Bids Open - National field for 0.00 Implementat 2021-05-18 2021-05-20 2021-06-10 2021-07-14 2021-08-31 2021-10-28 Strengthening Envelope 29 and rural areas in Jalpaiguri & explanation) ion Darjeeling (Plain area) Districts in West Bengal IN-WBSEDCL-233597-CW- RFB / Conversion of Overhead Network into Underground cable system at KhargapurTown under North Other (with Under Distribution System Single Stage - Two 2023-09- 24 Parganas Paschim / Prior Request for Bids Open - National field for 0.00 Implementat 2021-05-13 2021-05-26 2021-05-21 2021-06-04 2021-06-24 2021-09-06 2021-10-26 Strengthening Envelope 20 Midnapore district within the explanation) ion state of West Bengal' under West Bengal Electricity Distribution Grid Modernisation Project Page 1 IN-WBSEDCL-233611-CW- RFB / Conversion of Overhead Network into Underground cable system at Asansol Town(Part 1) under Paschim Other (with Under Distribution System Single Stage - Two 2023-09- Burdwan district within the / Prior Request for Bids Open - National field for 0.00 Implementat 2021-05-13 2021-05-23 2021-05-21 2021-06-01 2021-06-24 2021-09-06 2021-10-26 Strengthening Envelope 20 state of West Bengal' under explanation) ion West Bengal Electricity Distribution Grid Modernisation Project (P-170590) IN-WBSEDCL-233612-CW- RFB / Conversion of Overhead Network into Underground cable system at Asansol Town(Part 2) under Paschim Other (with Under Distribution System Single Stage - Two 2023-09- Burdwan district within the / Prior Request for Bids Open - National field for 0.00 Implementat 2021-05-13 2021-05-23 2021-05-21 2021-06-01 2021-06-24 2021-09-06 2021-10-26 Strengthening Envelope 20 state of West Bengal' under explanation) ion West Bengal Electricity Distribution Grid Modernisation Project (P-170590) GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-WBSEDCL-213824-CS- CQS / Invitation of EOI & RFP under International Procurement for Engagement Distribution System Quality And Cost- of PMA i.r.o HVDS projects for / Prior Open - International 0.00 Canceled 2021-01-25 2021-02-04 2021-02-02 2021-02-09 2021-03-18 2021-04-17 2021-05-17 2021-06-21 2021-07-26 2023-07-25 Strengthening Based Selection West Bengal Electricity Distribution Grid Modernization Project under World Bank loan financing IN-WBSEDCL-217209-CS- QCBS / Invitation of EOI & RFP under International Procurement for Engagement of PMA for conversion of OH Distribution System Quality And Cost- Under network into UG cable system / Prior Open - International 0.00 2021-02-03 2021-02-03 2021-02-09 2021-02-05 2021-04-16 2021-05-07 2021-05-27 2021-07-05 2021-08-12 2023-08-11 Strengthening Based Selection Implementation at 5 towns(6 Pkgs) for West Bengal Electricity Distribution Grid Modernisation Project under World Bank loan financing IN-WBSEDCL-229919-CS- QCBS / Invitation of EOI & RFP under International Procurement for Engagement Distribution System Quality And Cost- Under of PMA i.r.o HVDS projects for / Prior Open - International 0.00 2021-04-19 2021-05-06 2021-04-21 2021-05-06 2021-05-07 2021-06-02 2021-06-16 2021-07-05 2021-08-12 2023-08-11 Strengthening Based Selection Implementation West Bengal Electricity Distribution Grid Modernization Project under World Bank loan financing IN-WBSEDCL-239229-CS- QCBS / Direct RFP - Consultancy Services for Smart Grid Development in Quality And Cost- Pending / Post Open - National 0.00 2021-06-30 2021-06-30 2021-07-07 2021-08-04 2021-09-03 2021-10-08 2021-11-17 2023-11-17 Project Management of Urban Areas Based Selection Implementation deployment of SCADA/DMS/OMS in WBSEDCL INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Contract Type Process Status Teams of Reference Identified/Selected Signed Contract Contract Completion No. (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-WBSEDCL-171642-CS- CDS / Hiring a consultant for preparation of ESMF and ESIA documents for Distribution System Under / Post Direct Selection Direct 0.00 2020-07-01 2019-06-12 2020-07-15 2019-07-13 2020-08-19 2021-02-15 implementation of HVDS & Strengthening Implementation construction of GIS in 13 districts and UG cabling in 6 Towns of West Bengal IN-WBSEDCL-171990-CS- CDS / Hiring a consultant for preparation of DPR and PPSD for implementation of HVDS & Distribution System Under / Post Direct Selection Direct 0.00 2020-07-01 2019-06-12 2020-07-15 2019-07-29 2020-08-19 2021-02-15 construction of GIS in 13(+1) Strengthening Implementation districts and UG cabling in 6 Towns in WBSEDCL area of West Bengal Page 2 IN-WBSEDCL-181570-CS- CDS / Preparation of DPR for implementation of AMI project Smart Grid Development in Under / Post Direct Selection Direct 0.00 2020-07-01 2020-07-08 2020-07-11 2020-07-16 2020-09-14 2021-03-13 at different towns of West Urban Areas Implementation Bengal under World Bank assistance IN-WBSEDCL-181585-CS- CDS / Preparation of DPR for implementation of SCADA/ Smart Grid Development in Under / Post Direct Selection Direct 0.00 2020-07-01 2020-07-10 2020-07-11 2020-07-17 2020-09-14 2021-03-13 DMS project at different towns Urban Areas Implementation of West Bengal under World Bank assistance Page 3 Procurement Plan for ASPIRe Project I. General 1. Project information: Country : India Borrower : Republic of India Project Name : Assam State Public Finance Institutional Reforms (ASPIRe) Project Loan / Credit No. : Project Implementing : Assam Society for Comprehensive Agency (PIA), etc. Financial Management System 2. Bank’s approval Date of the procurement Plan [Original : ………; Revision 1:……..…] 3. Date of General Procurement Notice: 13th December 2016 4. Period covered by this procurement plan: First 18 months II. Goods and Works and non-consulting services 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement. World Bank review of procurement: The World Bank will prior review (thresholds are based on “Substantial” rating, will be modified if risk rating is changed after assessment by Bank during the project implementation) the following contracts: a) Works including turnkey Supply & Installation of Plant and Equipment and PPP: All contracts more than US$ 10 million equivalent b) Goods, Information Technology and Non-consulting Services: All contracts more than US$ 2 million equivalent First contract issued by implementing agency [IA] will be subject to prior review irrespective of their value. In addition, the justifications for all contracts to be issued on the basis of LIB, single-source or direct contracting will be subject to prior review. The above thresholds are for the initial 18 months implementation period; based on the procurement performance of the project these thresholds may be subsequently modified by Bank. In case of Post Review contracts, the inputs of Bank on Technical Specifications will be obtained by project. The procurement plan will be subsequently updated annually (or at any other time if required) and will reflect any change in prior review thresholds. The World Bank will carry out an annual ex-post procurement review of the procurement falling below the prior review thresholds provided above. To avoid any doubts, the Bank may conduct at any time Independent Procurement Reviews (IPRs) of all the contracts financed under the loan. Domestic preference is allowed only for Procurement of Goods and Information Technology and not for procurement of Works. Categor Method Threshold Method of Procurement y (US$ Equivalent) Works International Competitive Bidding > 40,000,000 (ICB) National Competitive Bidding Up to 40,000,000 (with (NCB) NCB conditions) Shopping Up to 100,000 As per paragraph 3.7 of Direct Contracting (DC) Guidelines Public-Private Partnership (PPP) As per paragraph 3.14 of for Works Guidelines As per paragraph 3.9 of Force Account Guidelines As per paragraph 3.6 of Framework Agreement (FA) Guidelines Goods International Competitive Bidding > 3,000,000 and non- (ICB) consultan Limited International Bidding (LIB) wherever agreed by Bank t services National Competitive Bidding Up to 3,000,000 (with NCB (NCS) (NCB) conditions) Shopping Up to 100,000 Direct Contracting (DC) As per paragraph 3.7 of Guidelines Public-Private Partnership (PPP) As per paragraph 3.14 of Services Guidelines Force Account (only for NCS) As per paragraph 3.9 of Guidelines Framework Agreement (FA)1 As per paragraph 3.6 of Guidelines Procurement from United Nations As per paragraph 3.10 of (UN) Agencies Guidelines 1/ DGS&D rate contracts may be used as framework agreement (FA) subject to the conditiona mentioned uner NCB conditions 2. Prequalification. Pre-qualification is not envisaged for any package under the Project. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: Not Applicable 4. Reference to (if any) Project Implementation Plan: Project Implementation Plan dated ___________. (to be updated) 5. Retroactive Financing : The GoA will be seeking retroactive financing, not exceeding US$ 1 million for technical and US$ 3 million for the EEP, in respect of payments for project-related work made by GoA during project preparation, on or after April 01, 2016. This includes payments to consultants for various preparatory studies, which inform the design of the information solutions and institutional strengthening, training and exposure visits (under technical assistance part) and EEP incurred prior to loan signing. 6. NCB Condition: National competition for the procurement of goods and works according to the established thresholds will be conducted in accordance with paragraphs 3.3 & 3.4 of Section III of the Guidelines and the following provisions: a) Only the model bidding documents for NCB agreed with the GoI Task Force (and as amended from time to time), shall be used for bidding; b) Invitations to bid shall be advertised in at least one widely circulated national daily newspaper (or on a widely used website or electronic portal with free national and international access along with an abridged version of the said advertisement published in a widely circulated national daily inter-alia giving the website/electronic portal details from which the details of the invitation to bid can be downloaded), at least 30 days prior to the deadline for the submission of bids; c) No special preference will be accorded to any bidder either for price or for other terms and conditions when competing with foreign bidders, state-owned enterprises, small-scale enterprises or enterprises from any given State; d) Except with the prior concurrence of the Bank, there shall be no negotiation of price with the bidders, even with the lowest evaluated bidder; e) Extension of bid validity shall not be allowed with reference to Contracts subject to Bank prior review without the prior concurrence of the Bank (i) for the first request for extension if it is longer than four weeks; and (ii) for all subsequent requests for extension irrespective of the period (such concurrence will be considered by Bank only in cases of Force Majeure and circumstances beyond the control of the Purchaser/Employer); f) Re-bidding shall not be carried out with reference to contracts subject to Bank prior review without the prior concurrence of the Bank. The system of rejecting bids outside a pre-determined margin or "bracket" of prices shall not be used in the project; g) Rate contracts entered into by Directorate General of Supplies and Disposals (DGS&D) will not be acceptable as a substitute for NCB procedures unless agreed with the Bank on case to case basis. Such contracts will be acceptable however for any procurement under the Shopping procedures; h) Use of DGS&D rate contracts as Framework Agreement must be reflected in the procurement plan agreed by the Bank for particular goods. Before issuing the purchasing order, the Bank will have to advise the government on carrying out a price analysis on the specific good that is intended to be purchased. If after this due diligence the borrower concludes [and Bank agrees] that the DGS&D rate contract is not suitable, then the borrower will have to proceed using NCB or shopping depending on the value. To meet the Bank's requirements for right to audit and F&C, these clauses may be included in the Purchase Orders [in case the purchasers are directly placing the purchase orders to DGS&D rate contract holders]. On the other hand, if indent is placed through DGS&D, the Purchaser has the option to sign a separate undertaking with DGS&D rate contract holder, where Bank’s right to audit and F&C clauses could be mentioned. Two or three envelope system will not be used (except when using e- procurement system assessed and agreed by the Bank). 7. Procurement Packages with Methods and Time Schedule as per Table A [attached] III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: a) Consultancy Services for selection of firms : All contracts more than US$ 1.0 million equivalent; b) Consultancy services for selection of individuals: All contracts above US$ 0.3 million. c) First contract issued by implementing agency [IA] will be subject to prior review irrespective of their value. In addition, the justifications for all contracts to be issued on the basis of single-source or direct contracting will be subject to prior review. The above thresholds are for the initial 18- month implementation period; based on the procurement performance of the project these thresholds may be subsequently modified by Bank. In case of Post Review contracts, the inputs of Bank on TORs will be obtained by project. The procurement plan will be subsequently updated annually (or at any other time if required) and will reflect any change in prior review thresholds. The World Bank will carry out an annual ex-post procurement review of the procurement falling below the prior review thresholds provided above. To avoid any doubts, the Bank may conduct at any time Independent Procurement Reviews (IPRs) of all the contracts financed under the loan. Selection Method Method Threshold (USD) Consultants’ Selection Based on Consultants’ Up to 300,000 Services Qualifications (CQS)/Least-Cost Selection (LCS) Single-Source Selection (SSS) As per paragraphs 3.9-3.11 of Guidelines Individuals As per Section V of Guidelines Particular Types of Consultants As per paragraphs 3.15-3.21 of Guidelines Quality- and Cost-Based Selection (QCBS)/ for all other cases Quality-Based Selection (QBS)/ Selection under a Fixed Budget (FBS) (i) International shortlist > 800,000 (ii) Shortlist may comprise national Up to 800,000 consultants only 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than US $ 800,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: First consultancy selection shall be prior reviewed irrespective of threshold. Refer to sl. No. 4 under Section-II of the procurement plan 4. Consultancy Assignments with Selection Methods and Time Schedule as per Table A [attached] Table A Assam State Public Finance Institutional Reforms Project : 18 month Procurement Plan Prior Bid / Delivery Estimate Estimat Procure / Bid/REO Proposa Contract Ref. Contract / d Cost ed Cost ment post I l Signing Remarks No. Description Complet (INR) (USD) Method Revi Advert Opening Date ion Date ew Date CONSULTANT SERVICES Technical Assistance Sub- Component 1.1: Strengthening Cash & Debt Management Contract Awarded Advisor – Debt May be CS-1 and Cash 27,75,000 41,500 SSS post - - Jan 2017 Jan 2018 extended by Management another 3 years annually. Data Analytics Sep CS-2 67,00,000 100,000 IC post Oct 2017 Dec 2017 Dec 2021 For 4 years Consultants (2) 2017 Strengthening Public Procurement Framework, Procurement Capacity and Scaling Up E-Procurement Consultant for developing Contract CS-3 15,00,000 23,000 IC post NA NA May 2017 March 18 Procurement Awarded Rules (4 Nos.) Consultants for developing Feb CS-4 Standard Bidding 54,00,000 80,000 IC’s post NA NA Jun 2017 1 year 2018 Documents (SBDs)- 7 Nos Prior Bid / Delivery Estimate Estimat Procure / Bid/REO Proposa Contract Ref. Contract / d Cost ed Cost ment post I l Signing Remarks No. Description Complet (INR) (USD) Method Revi Advert Opening Date ion Date ew Date Consultants for 3-4 individual State 100,00,00 CS-5 149,000 IC’s post NA NA Nov 2017 Oct 2021 consultants for Procurement 0 4 years Facilitation Cell Consultant for study of the implementation & Mar CS-6 10,00,000 15,000 IC post NA NA Nov 2016 scale up of e- 2017 procurement in Assam Consultancy on Procurement Justification to Training Needs July June be prior CS-7 Analysis, Training 75,00,000 112,000 CQS/SSS post Aug2017 Sept 2017 2017 2018 reviewed by Strategy & Bank Curriculum Development Consultancy for June Aug CS-8 MOOC 50,00,000 75,000 QCBS post Nov 2018 Apr 2019 2018 2018 Development Senior E- Procurement July Aug CS-9 90,00,000 135,000 IC post Sept 2017 Jun 2020 For 3 years Project Mgt 2017 2017 Consultant E-Procurement May Contract CS-10 Facility Mgt Cell 72,60,000 108,000 IC post Apr2017 Jun 2017 Jun 2021 2017 awarded and Training Prior Bid / Delivery Estimate Estimat Procure / Bid/REO Proposa Contract Ref. Contract / d Cost ed Cost ment post I l Signing Remarks No. Description Complet (INR) (USD) Method Revi Advert Opening Date ion Date ew Date Strengthening PPP Framework Consultancy for Policy and CS – Institutional Dec Sep Contract 60,00,000 90,000 QCBS post Jul 2016 Feb 2017 11 Reform for 2016 2017 Awarded Strengthening PPP Framework Consultancy- CS – Project Mgmt and 2,00,00,00 Oct Dec Mar 298,000 QCBS post Feb 2018 12 Support Unit for 0 2017 2017 2022 PPP Institutional Strengthing of Finance Dept Consultancy for Review of Org’n Structure and file July Aug Aug CS-13 work flow process 56,00,000 83,000 IC post Sept 2017 1 year 2017 2017 2018 in Finance Dept and selected Line Dept Consultancy to review the Aug Sep CS-14 20,00,000 30,000 IC post Sep 2017 Jan 2018 5 months Budget & FRBM 2017 2017 Disclosures Training and Capacity Building in Finance Consultancy on Training Needs 100,00,00 July Sep CS-15 150,000 LCS post Dec 2017 Jun 2018 Analysis for 0 2017 2017 offcials in Finance and Line dept, Training Strategy & Curriculum Development Prior Bid / Delivery Estimate Estimat Procure / Bid/REO Proposa Contract Ref. Contract / d Cost ed Cost ment post I l Signing Remarks No. Description Complet (INR) (USD) Method Revi Advert Opening Date ion Date ew Date Consultancy for MOOC Development for 100,00,00 Mar CS-16 150,000 QCBS post Jun 2018 Aug 2018 Mar 2019 Finance Cadres in 0 2018 Finance and Line Dept Strengthening Expenditure & Revenue Information Systems Design of Financial Management Information Systems Consultants for Designing of Financial Management Information 1,60,00,00 Feb Contract CS-17 System for the 238,000 QCBS post Jul 2016 Jan 2017 Feb 2018 0 2016 Awarded Government of Assam and support in selection of the System Integrator Project Management Consultancy to 5,00,00,00 Dec Mar 4 years CS-18 745,000 QCBS post Jun 2018 Sep 2022 oversee 0 2017 2018 contract implementation of FMIS Security Audit of Periodic Audit FMIS E- 1,00,00,00 Aug Nov of various CS-19 149,000 LCS post Jan 2019 Dec 2021 Governance 0 2018 2018 modules -3 Solution years Designing Information Systems and Institutional Strengthening of Commercial Tax Dept Consultancy Study for preparation of RFP and selection Contract CS-20 72,00,000 107,000 SSS Nov 15 Apr 2016 Jun 2017 of Systems prior Awarded Integrator for new IT application for CTD Prior Bid / Delivery Estimate Estimat Procure / Bid/REO Proposa Contract Ref. Contract / d Cost ed Cost ment post I l Signing Remarks No. Description Complet (INR) (USD) Method Revi Advert Opening Date ion Date ew Date Consultancy services for Institutional and GST readiness Contract CS-21 70,00,000 105,000 QCBS post Jan 2016 Jul 2016 Jan 2017 Feb 2018 assessment in the Awarded Commissionerate of Taxes, Govt. of Assam Project Management Consultancy to 1,62,00,00 June Aug 3 years CS-22 oversee 241,000 QCBS post Sep 2017 Sep 2020 0 2017 2017 contract implementation of E-Governance Solution in CTD Security Audit of CTD E- Apr CS-23 70,00,000 104,000 LCS post Jun 2017 Aug 2018 Sep 2019 Governance 2018 Solution Service Tax Sep CS-24 54,00,000 80,000 IC post Oct 2017 Nov 2017 Dec 2017 For 3 years Advisor (I/C) 2017 Design Development & Implementation of E-Governance Solution in Excise Dept Consultancy services for designing an e- Governance CS– 1,00,00,00 Feb Contract system for the 150,000 QCBS post Jul 2016 Jan 2017 Feb 2018 25 0 2016 Awarded Department of Excise, Government of Assam, India. Project Management Consultancy to CS– 3,00,00,00 Nov Mar 4 years oversee 447,000 QCBS post Jun 2018 Sep 2022 26 0 2017 2018 contract implementation of E-Governance Solution in Excise Prior Bid / Delivery Estimate Estimat Procure / Bid/REO Proposa Contract Ref. Contract / d Cost ed Cost ment post I l Signing Remarks No. Description Complet (INR) (USD) Method Revi Advert Opening Date ion Date ew Date Security Audit of Periodic Audit Excise E- Aug Nov of various CS-27 70,00,000 104,000 LCS post Jan 2019 Dec 2020 Governance 2018 2018 modules -2 Solution years Website Upgrade Aug Nov CS-28 for Excise 20,00,000 30,000 LCS post Dec 2017 Mar 2018 2017 2017 Department Project Management & Coordination Sep Dec Contract CS-29 CA for AS-CFMS 15,00,000 23,000 QCBS post Feb 2017 Apr 2018 2016 2016 Awarded Senior Mar Contract CS-30 Procurement 28,00,000 42,500 SSS post N/A N/A Aug 2016 2018 Awarded Consultant Justification to Procurement Mar be prior CS-31 30,00,000 45,500 SSS post N/A N/A June 2017 Support Specialist 2019 reviewed For 2 years IT Project 1,20,00,00 July Aug Sept CS-32 180,000 IC post Sept2017 For 5 years Manager 0 2017 2017 2022 Change Aug Sept CS-33 Management 85,00,000 126,000 IC post July2017 Sept 2017 For 5 years 2017 2022 Specialist Communication July Aug Sept CS-34 81,00,000 120,000 IC post Sept 2017 For 5 years Specialist 2017 2017 2022 Part B: Eligible Expenditure under the Project DoAT Short term Feb Apr Contract CS-35 Programmers/ 43,40,000 65,000 IC post May 2017 Apr 2019 2017 2017 Awarded DBA (2 years) Programmers for development of 1,00,00,00 Aug CS-36 150,000 IC post Jun 2017 Sep 2017 Aug 2019 E-Colln Portal and 0 2017 its roll out Prior Bid / Delivery Estimate Estimat Procure / Bid/REO Proposa Contract Ref. Contract / d Cost ed Cost ment post I l Signing Remarks No. Description Complet (INR) (USD) Method Revi Advert Opening Date ion Date ew Date CTD Short term July Aug CS-37 Programmers/ 43,40,000 65,000 IC post Sept 2017 Apr 2019 2017 2017 DBA (2 years) 33,21,15,0 4,956,50 SUB TOTAL - A 00 0 NON-CONSULTANT SERVICES Strengthening network NCS- connectivity for 10,00,00,0 1,492,00 July Sept Sept 5 years NCB post Nov 2017 1 CTD offices - 00 0 2017 2017 2022 contract Secondary Service Provider Strengthening network NCS- connectivity for 7,00,00,00 1,044,00 Dec Mar Sept 5 years NCB post Jun 2018 2 DoAT offices - 0 0 2017 2018 2022 contract Secondary Service Provider Procurement NCS- Mar May Sept MOOC Hosting 25,00,000 37,000 NCB post Jul 2019 3 2019 2019 2022 and Maintenance Upgrade and NCS- July Sept Sept Maintenance of 20,00,000 30,000 NCB post Oct 2017 4 2017 2017 2022 CS-DRMS 17,45,00,0 2,603,00 SUB TOTAL - B 00 0 Procu Prior Bid / Delivery Estimated reme / Bid/REO Proposa Contract Ref. Contract Estimated / Cost nt post I l Signing Remarks No. Description Cost (INR) Complet (USD) Meth Revi Advert Opening Date ion Date od ew Date GOODS Field Level Hardware 10,00,00,00 Apr GD -1 1,492,000 NCB post Jun 2018 Aug 2018 Feb 2019 Procurement 0 2018 (Treasury) Hardware 13,65,00,00 Nov Feb Sept Contract GD-2 (Peripherals) for 2,037,000 NCB prior June 2017 0 2016 2017 2017 Awarded CTD Hardware 15,00,00,00 Apr GD-3 (Peripherals) for 2,238,000 NCB post Jun 2018 Aug 2018 Feb 2019 0 2018 Excise SI for FMIS Procurement Solution will be initiated Development of only after the 44,00,00,00 Oct Sept GD-4 FMIS solution, O 6,565,000 LIB prior Jan 2017 Mar 2018 recommendati 0 2017 2022 & M, including ons from the cost of Core agency hired Server Hardware under CS - 17 SI for Procurement implementation will be initiated for Excise: New e- only after the governance 35,00,00,00 Oct Sept GD-5 5,223,000 ICB prior Jan 2017 Mar 2018 recommendati system 0 2017 2022 ons from the System agency hired Development, O under CS - 25 &M SI for CTD - 35,00,00,00 May Sept GD-6 5,223,000 LIB prior Jan 2017 July 2017 development 0 2017 2022 cost, O&M and hardware cost (servers/ license fee) Procu Prior Bid / Delivery Estimated reme / Bid/REO Proposa Contract Ref. Contract Estimated / Cost nt post I l Signing Remarks No. Description Cost (INR) Complet (USD) Meth Revi Advert Opening Date ion Date od ew Date Procurement of Aug GD-7 Equipment for 3,00,00,000 447,000 NCB post Jun 2019 Nov 2019 Jun 2020 2019 Test labs 155,65,00,0 SUB TOTAL - C 23,225,000 00 MINOR WORKS Refurbishment of Aug 450,00,000 670,000 NCB Jan 2017 Apr 2017 June 2017 Server Room post 2017 Refurbishment of Dec Mar DoAT incl Training 100,00,000 150,000 NCB post Jun 2019 Mar 2020 2018 2019 Room Refurbishment of Dec Mar Finance Dept 150,00,000 150,000 NCB post Jun 2018 Mar 2019 2017 2018 Divisions Refursbishment Aug 40,00,000 60,000 NCB post Oct 2017 Nov 2017 Mar 2018 of AS-CFMS Office 2017 SUB TOTAL - D 690,00,000 1,030,000 Totals Estimated 213,21,15, 31,814,50 Costs: 000 00 (A + B + C) PROCUREMENT India : Assam State Public Finance Institutional Reforms (ASPIRe) Project PLAN General Information Country: India Bank’s Approval Date of the Original Procurement Plan: 2016-12-12 2021-05-24 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P157198 GPN Date: 2016-12-12 Project Name: Assam State Public Finance Institutional Reforms (ASPIRe) Project Loan / Credit No: / , IBRD / 87650 A Executing Agency(ies): ssam Society for Comprehensive Financial Management System WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Strengthening Expenditure IN-AS-CFMS-5984-CW-RFP / Request for Single Stage - Two 2017-09- / and Revenue Information Post Open - National 670,000.00 0.00 Canceled 2017-02-10 2017-02-15 2017-03-17 2017-04-16 2017-05-12 Refurbishment of Server Room Proposals Envelope 09 Systems IN-AS-CFMS-72908-CW-RFB Project Management, / Interior finishing and Single Stage - Two 2022-01- IBRD / 87650 Monitoring & Evaluation and Post Request for Bids Open - National 220,000.00 0.00 Canceled 2018-08-30 2018-09-04 2018-10-02 2018-12-15 2019-01-19 furnishing of AS-CFMS Office Envelope 18 Coordination Space IN-AS-CFMS-79710-CW-RFQ / Furnishing and Finishing Project Management, Works at the AS-CFMS Office Request for Single Stage - One 2019-03- IBRD / 87650 Monitoring & Evaluation and Post Open - National 64,000.00 55,149.52 Signed 2018-10-10 2018-12-05 2018-12-21 Space: Civil, Floor Finishes, Quotations Envelope 15 Coordination Carpentry, Stone Works & Plumbing IN-AS-CFMS-79723-CW-RFQ / Furnishing and Finishing Project Management, Request for Single Stage - One 2019-03- Works at the AS-CFMS Office IBRD / 87650 Monitoring & Evaluation and Post Open - National 65,000.00 56,249.26 Signed 2018-10-10 2018-12-05 2018-12-21 Quotations Envelope 15 Space: Electrical, Fire Fighting Coordination & Ceiling Works IN-AS-CFMS-79733-CW-RFQ / Furnishing and Finishing Project Management, Pending Works at the AS-CFMS Office Request for Single Stage - One 2019-03- IBRD / 87650 Monitoring & Evaluation and Post Open - National 64,000.00 0.00 Implementat 2018-10-10 2018-12-05 Space: Furniture, Storage, Quotations Envelope 15 Coordination ion Paint Polishes & Miscellaneous Works Strengthening Expenditure Pending IN-AS-CFMS-5984-CW-RFB / Single Stage - Two 2019-11- IBRD / 87650 and Revenue Information Post Request for Bids Open - National 670,000.00 0.00 Implementat 2019-02-11 2019-02-16 2019-03-30 2019-06-12 2019-07-17 Refurbishment of Server Room Envelope 14 Systems ion IN-AS-CFMS-129209-CW- RFQ / SUPPLY & INSTALLATION OF NETWORK HARDWARE AND AIR Strengthening Expenditure CONDITIONERS INCLUDING Request for Single Stage - One 2024-10- IBRD / 87650 and Revenue Information Post Open - National 40,000.00 39,775.52 Signed 2019-08-29 2021-02-18 2019-10-10 2019-11-19 ELECTRICAL AND NETWORK Quotations Envelope 08 Systems CABLING WORK AT COMMISSIONERATE OF EXCISE AND DIRECTORATE OF ACCOUNTS AND TREASURIES IN-AS-CFMS-92284-CW-RFQ Strengthening Expenditure / Excise Electrical and Request for Single Stage - One 2019-05- IBRD / 87650 and Revenue Information Post Open - National 21,500.00 0.00 Canceled 2019-01-02 2019-02-27 Network Cabling Works Quotations Envelope 28 Systems including network devices IN-AS-CFMS-160371-CW- RFB / Refurbishment of 12 Pending Strengthening Public Finance Single Stage - Two 2021-02- Divisions (3 Floors) of Finance IBRD / 87650 Post Request for Bids Open - National 1,300,000.00 0.00 Implementat 2020-03-15 2020-03-20 2020-05-01 2020-07-14 2020-08-18 Institutional Capacity Envelope 14 Department including ion Centralised Air Conditioning IN-AS-CFMS-173069-CW- Strengthening Expenditure Request for Single Stage - One 2021-01- RFQ / Electrification Works at IBRD / 87650 and Revenue Information Post Limited 20,000.00 0.00 Canceled 2020-05-29 2020-07-24 Quotations Envelope 20 Kar Bhawan Data Centre Systems IN-AS-CFMS-186514-CW- Strengthening Expenditure Pending 2025-09- DIR / Electrification Works at IBRD / 87650 and Revenue Information Post Direct Selection Direct 20,000.00 0.00 Implementat 2020-07-31 2020-08-05 2020-09-09 08 Kar Bhawan Data Centre Systems ion IN-AS-CFMS-218781-CW- Strengthening Expenditure Pending RFQ / Refurbishment of office Request for Single Stage - One 2021-10- IBRD / 87650 and Revenue Information Post Open - National 46,000.00 0.00 Implementat 2021-02-24 2021-04-21 space for IFMIS Helpdesk at F Quotations Envelope 18 Systems ion Block, Janata Bhawan GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-AS-CFMS-6159-GO-RFB / Strengthening Expenditure SI for CTD - development Single Stage - Two IBRD / 87650 and Revenue Information Prior Request for Bids Limited 5,223,000.00 5,291,185.90 Signed 2017-02-03 2017-02-08 2017-02-06 2017-03-23 2017-06-06 2017-06-20 2018-04-05 2017-07-25 2019-05-30 2022-07-24 cost, O&M and hardware cost Envelope Systems (servers/ license fee) IN-AS-CFMS-4577-GO-RFP / Strengthening Expenditure Single Stage - Two Hardware (Peripherals) for / and Revenue Information Prior Request for Bids Open - National 2,037,000.00 0.00 Canceled 2017-01-30 2017-06-30 2017-01-30 2017-06-30 2017-01-30 2016-12-30 2017-01-30 2017-02-19 2017-08-18 Envelope CTD Systems IN-AS-CFMS-4577-GO-RFB / Strengthening Expenditure Single Stage - One Hardware (Peripherals) for IBRD / 87650 and Revenue Information Prior Request for Bids Open - National 2,037,000.00 2,841,038.80 Signed 2017-07-27 2017-08-01 2017-08-10 2017-08-06 2016-12-30 2017-08-11 2017-08-16 2017-08-16 2017-07-19 2022-08-15 Envelope CTD Systems Page 1 IN-AS-CFMS-27940-GO-RFB / National Competitive Bidding for Supply of Server, Strengthening Public Finance Single Stage - Two IBRD / 87650 Post Request for Bids Open - National 1,230,770.00 0.00 Canceled 2017-09-14 2017-09-20 2017-09-15 2017-09-21 2017-10-26 2018-01-08 2018-02-12 2023-02-11 Software and Network Institutional Capacity Envelope Hardware at the Directorate of Accounts and Treasuries IN-AS-CFMS-45495-GO-RFB / National Competitive Bidding for Supply of Server Under Strengthening Public Finance Single Stage - Two and its Peripherals, Software IBRD / 87650 Post Request for Bids Open - National 616,000.00 0.00 Implementati 2018-02-09 2018-02-16 2018-02-14 2018-03-28 2018-06-10 2018-07-15 2023-07-14 Institutional Capacity Envelope including Migration Activity at on the Directorate of Accounts and Treasuries. IN-AS-CFMS-64741-GO-RFB Under Strengthening Public Finance Single Stage - Two / System Integrator for Excise IBRD / 87650 Prior Request for Bids Open - National 2,815,000.00 0.00 Implementati 2018-06-08 2018-06-29 2018-06-13 2018-10-31 2018-08-10 2019-02-25 2018-10-23 2019-09-05 2018-11-27 2023-11-26 Institutional Capacity Envelope e-Governance Solution on IN-AS-CFMS-57404-GO-RFB / CoE: NCB for Supply of Computers, Network Hardware and Peripherals, Strengthening Public Finance Single Stage - Two IBRD / 87650 Post Request for Bids Open - National 550,000.00 0.00 Canceled 2018-04-30 2018-05-25 2018-05-05 2018-07-11 2018-06-16 2018-08-29 2018-10-03 2024-04-04 Including the Work of Power Institutional Capacity Envelope Supply, LAN, and Network Cabling at the Commissionerate of Excise, Assam IN-AS-CFMS-74725-GO-APA Strengthening Expenditure Request for Single Stage - One / CoE: Purchase of Laptops on IBRD / 87650 and Revenue Information Post Open - National 99,000.00 100,103.73 Signed 2018-08-29 2018-10-24 2018-11-22 2018-12-23 Quotations Envelope GeM Systems IN-AS-CFMS-74744-GO-RFQ Strengthening Expenditure Pending Request for Single Stage - One / CoE: Purchase of Desktops, IBRD / 87650 and Revenue Information Post Open - National 54,000.00 0.00 Implementati 2018-09-01 2018-10-27 2018-12-26 Quotations Envelope UPS and Printers on GeM Systems on IN-AS-CFMS-93284-GO-RFQ Project Management, Pending / Heating, ventilation and Air Request for Single Stage - One IBRD / 87650 Monitoring & Evaluation and Post Limited 45,000.00 0.00 Implementati 2019-02-16 2019-04-13 2019-06-12 Conditioning at new Office Quotations Envelope Coordination on Space Of ASPIRe IN-AS-CFMS-108496-GO- Strengthening Expenditure Under DIR / System Integrator for IBRD / 87650 and Revenue Information Prior Direct Selection Direct 3,000,000.00 0.00 Implementati 2019-04-11 2019-09-05 2019-04-16 2019-09-12 2019-05-21 2024-05-19 FMIS Solution Development Systems on IN-AS-CFMS-52090-GO-RFB / National Competitive Strengthening Expenditure Single Stage - Two Bidding for Supply of Network IBRD / 87650 and Revenue Information Post Request for Bids Open - National 500,000.00 0.00 Canceled 2018-03-19 2018-03-24 2018-05-05 2018-07-18 2018-08-22 2023-08-21 Envelope Hardware at the Directorate of Systems Accounts and Treasuries IN-AS-CFMS-124299-GO- Strengthening Expenditure Pending Request for Single Stage - One RFQ / Procurement of 13 IBRD / 87650 and Revenue Information Post Open - National 34,200.00 0.00 Implementati 2019-08-18 2019-10-13 2024-10-11 Quotations Envelope Remote Routers for Treasuries Systems on IN-AS-CFMS-124696-GO- Pending Strengthening Public Finance DIR / Development of State IBRD / 87650 Post Direct Selection Direct 700,000.00 0.00 Implementati 2019-08-25 2019-08-30 2019-10-04 2022-10-03 Institutional Capacity Public Procurement Portal on IN-AS-CFMS-125202-GO- Strengthening Expenditure Pending RFQ / Procurement of SSL Request for Single Stage - One IBRD / 87650 and Revenue Information Post Open - National 11,000.00 0.00 Implementati 2019-08-09 2019-10-04 2019-11-03 Certificates for Mission Quotations Envelope Systems on Critical Applications IN-AS-CFMS-125211-GO- Strengthening Expenditure Pending RFQ / 61 Layer 2 Managed Request for Single Stage - One IBRD / 87650 and Revenue Information Post Open - National 100,000.00 0.00 Implementati 2019-08-05 2019-09-30 2019-12-29 Switches (48 ports) for Quotations Envelope Systems on Treasuries IN-AS-CFMS-126763-GO- Strengthening Expenditure Pending Single Stage - Two RFB / Network equipment of IBRD / 87650 and Revenue Information Post Request for Bids Open - National 660,000.00 0.00 Implementati 2019-08-26 2019-08-31 2019-10-12 2019-12-25 2020-01-29 2025-01-27 Envelope DoAT Data Center Systems on IN-AS-CFMS-133239-GO- Project Management, Pending Request for Single Stage - One RFQ / Procurement of IT items IBRD / 87650 Monitoring & Evaluation and Post Open - National 36,000.00 0.00 Implementati 2019-09-16 2019-11-11 2020-05-09 Quotations Envelope for office space of ASPIRe Coordination on IN-AS-CFMS-133246-GO- Strengthening Expenditure Pending RFB / Procurement of 100 Request for Single Stage - One IBRD / 87650 and Revenue Information Post Limited 70,000.00 0.00 Implementati 2019-11-07 2020-01-02 2020-06-30 desktop computers for 16 Quotations Envelope Systems on new Treasuries, DoAT IN-AS-CFMS-141680-GO- Pending RFQ / Procurement of 30 Strengthening Public Finance Request for Single Stage - One IBRD / 87650 Post Limited 26,000.00 0.00 Implementati 2019-11-20 2020-01-15 2020-07-13 Laptops for the Training Institutional Capacity Quotations Envelope on Room at ASPIRe Office. IN-AS-CFMS-144431-GO- RFQ / Procurement of 35 nos. Strengthening Expenditure Pending Request for Single Stage - One of printer and 35 nos. of IBRD / 87650 and Revenue Information Post Limited 87,000.00 0.00 Implementati 2019-11-25 2020-01-20 2020-07-18 Quotations Envelope Scanner for Directorate of Systems on Audit (Local Fund) IN-AS-CFMS-144442-GO- RFQ / Procurement of 35 Strengthening Expenditure Pending Request for Single Stage - One Desktops and 100 UPS, for IBRD / 87650 and Revenue Information Post Limited 39,000.00 0.00 Implementati 2019-11-25 2020-01-20 2020-07-18 Quotations Envelope Directorate of Audit (Local Systems on Fund) IN-AS-CFMS-144453-GO- Strengthening Expenditure Pending RFQ / Procurement of 179 Single Stage - One IBRD / 87650 and Revenue Information Post Request for Bids Open - National 166,000.00 0.00 Implementati 2019-11-29 2019-12-04 2020-01-15 2020-02-14 2020-03-20 2020-09-16 Laptops for Directorate of Envelope Systems on Audit (Local Fund) IN-AS-CFMS-159875-GO- RFQ / Procurement of 30 Strengthening Public Finance Request for Single Stage - One Laptop and 10 Desktop for IBRD / 87650 Post Open - National 37,000.00 35,429.96 Signed 2020-02-25 2020-04-21 2020-05-04 2020-10-18 Institutional Capacity Quotations Envelope Finance Department Officials through GeM Page 2 IN-AS-CFMS-160355-GO- RFB / Procurement of 200 Strengthening Expenditure Pending Desktops, 200 Tablets, 60 Single Stage - Two IBRD / 87650 and Revenue Information Post Request for Bids Open - National 252,000.00 0.00 Implementati 2020-02-21 2020-02-26 2020-04-08 2020-06-21 2020-07-26 2021-01-22 Laser Printers and 200 Envelope Systems on Antivirus units for Directorate of Economics & Statistics IN-AS-CFMS-160374-GO- Strengthening Expenditure Pending RFQ / Procurement of 40 nos. Request for Single Stage - One IBRD / 87650 and Revenue Information Post Limited 9,700.00 0.00 Implementati 2020-02-29 2020-04-25 2020-10-22 of tablets, 500 pendrives and Quotations Envelope Systems on 150 Budget Bags for e-budget IN-AS-CFMS-171726-GO- RFB / RFP for SUPPLY OF COMPUTER, NETWORK Strengthening Expenditure Pending HARDWARE AND ITS Single Stage - Two IBRD / 87650 and Revenue Information Post Request for Bids Open - National 1,700,000.00 0.00 Implementati 2020-06-21 2020-06-26 2020-08-07 2020-10-20 2020-11-24 2025-11-23 PERIPHERALS, INCLUDING THE Envelope Systems on WORK OF POWER SUPPLY, UPS AND NETWORK CABLING AT VARIOUS TREASURY OFFICES IN-AS-CFMS-184736-GO- RFQ / Procurement of 50 All- Strengthening Expenditure Pending in-One Desktops, 30 Network Request for Single Stage - One IBRD / 87650 and Revenue Information Post Limited 86,000.00 0.00 Implementati 2020-08-04 2020-09-29 2021-03-28 Printers, and 50 UPS for Quotations Envelope Systems on Kamrup Rural district for implementation of FMIS IN-AS-CFMS-196774-GO- Strengthening Expenditure Under Single Stage - Two RFB / Procurement of IBRD / 87650 and Revenue Information Post Request for Bids Open - National 515,000.00 0.00 Implementati 2020-10-20 2020-10-25 2020-12-06 2021-02-18 2021-03-25 2023-03-25 Envelope Hardware for GST Prime Systems on IN-AS-CFMS-200079-GO- RFQ / Procurement of 50 Laptops, 5 Multi Function Pending Printers, 10 Desktops , 5 Strengthening Public Finance Request for Single Stage - One IBRD / 87650 Post Open - National 100,000.00 0.00 Implementati 2020-11-04 2020-12-30 2021-06-28 Photocopier Machines and Institutional Capacity Quotations Envelope on Cartridges and Toners for Finance Department for one Financial Year IN-AS-CFMS-200724-GO- Strengthening Expenditure Pending Request for Single Stage - One RFQ / Procurement of IT IBRD / 87650 and Revenue Information Post Open - National 50,000.00 0.00 Implementati 2020-11-01 2020-12-27 2021-06-25 Quotations Envelope Hardware for FMIS Helpdesk Systems on IN-AS-CFMS-200726-GO- Strengthening Expenditure Pending RFQ / Procurement of Chairs Request for Single Stage - One IBRD / 87650 and Revenue Information Post Open - National 7,200.00 0.00 Implementati 2020-11-01 2020-12-27 2021-06-25 and Conference table for FMIS Quotations Envelope Systems on Team IN-AS-CFMS-200732-GO- Strengthening Expenditure Pending RFQ / Procurement of IT Request for Single Stage - One IBRD / 87650 and Revenue Information Post Open - National 15,000.00 0.00 Implementati 2020-11-02 2020-12-28 2021-06-26 Hardware for Chief Secretary Quotations Envelope Systems on Monitoring Cell IN-AS-CFMS-200739-GO- Pending Strengthening Public Finance Single Stage - Two APA / Procurement of AC for IBRD / 87650 Post Request for Bids Open - National 103,000.00 0.00 Implementati 2020-11-02 2020-11-07 2020-12-19 2021-03-03 2021-04-07 2021-10-04 Institutional Capacity Envelope Finance Department on IN-AS-CFMS-200172-GO- DIR / DSC Public Key Strengthening Expenditure Pending Infrastructure and Document IBRD / 87650 and Revenue Information Post Direct Selection Direct 68,000.00 0.00 Implementati 2020-11-30 2020-12-14 2021-01-18 2022-01-18 Signer Certificate for Tax Systems on Officers IN-AS-CFMS-206383-GO- Strengthening Expenditure Pending DIR / Oracle Perpetual IBRD / 87650 and Revenue Information Post Direct Selection Direct 358,500.00 0.00 Implementati 2020-12-04 2020-12-09 2021-01-13 2022-01-13 Licenses for Excise e- Systems on Governance Solution IN-AS-CFMS-208626-GO- RFQ / Procurement of 60 Pending Desktops and One Online UPS Strengthening Public Finance Request for Single Stage - One IBRD / 87650 Post Open - National 65,000.00 0.00 Implementati 2021-02-16 2021-04-13 2021-10-10 for Computer Training Institutional Capacity Quotations Envelope on Laboratory at Kamrup DC Office IN-AS-CFMS-221734-GO- Strengthening Expenditure Pending DIR / Procurement of Oracle IBRD / 87650 and Revenue Information Post Direct Selection Direct 7,700.00 0.00 Implementati 2021-02-25 2021-03-02 2021-04-06 2021-10-03 Linux Virtualisation Manager Systems on IN-AS-CFMS-225784-GO- RFB / Procurement of 204 all- in-one desktops, 8 laptops, Strengthening Expenditure Pending 86 Laserjet Printers, 4 nos. Single Stage - Two IBRD / 87650 and Revenue Information Post Request for Bids Open - National 270,000.00 0.00 Implementati 2021-04-01 2021-04-06 2021-05-18 2021-07-31 2021-09-04 2022-09-04 line printer, 2 nos. 2 nos. of 3 Envelope Systems on KVA UPS and one IM Server for the Office of the Accountant General IN-AS-CFMS-226384-GO- RFQ / Procurement of 40 Pending Strengthening Public Finance Request for Single Stage - One Desktops & 2 10 KV UPS for IBRD / 87650 Post Open - National 42,000.00 0.00 Implementati 2021-04-23 2021-06-18 2021-12-15 Institutional Capacity Quotations Envelope IFMIS Training Room of on Finance Department NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Strengthening Expenditure IN-AS-CFMS-41198-NC-DIR IBRD / 87650 and Revenue Information Post Direct Selection Direct 5,000.00 0.00 Canceled 2017-12-29 2018-01-03 2018-02-07 2018-05-08 / Security Audit for eGRAS Systems IN-AS-CFMS-108300-NC- Pending Strengthening Public Finance Request for Single Stage - One RFQ / AMC of IT equipment of IBRD / 87650 Post Open - National 29,000.00 0.00 Implementati 2019-06-15 2019-08-10 2020-08-09 Institutional Capacity Quotations Envelope Finance Department on Page 3 IN-AS-CFMS-112298-NC- Project Management, Pending RFQ / Facility Management Request for Single Stage - One IBRD / 87650 Monitoring & Evaluation and Post Open - National 40,000.00 0.00 Implementati 2019-06-15 2019-08-10 2020-08-09 Services for New Office Space Quotations Envelope Coordination on (Kamakhya Tower) IN-AS-CFMS-118791-NC- Project Management, Request for Single Stage - One RFQ / Hiring 2 pool cars for IBRD / 87650 Monitoring & Evaluation and Post Open - National 29,000.00 18,632.67 Signed 2019-07-03 2019-08-28 2020-02-17 2020-08-27 Quotations Envelope AS-CFMS Coordination IN-AS-CFMS-120389-NC- Strengthening Expenditure Single Stage - Two RFB / Engagement of a Cloud IBRD / 87650 and Revenue Information Post Request for Bids Open - National 575,000.00 536,317.50 Signed 2019-08-01 2019-11-11 2019-08-06 2019-09-17 2020-01-24 2019-11-30 2020-04-28 2020-01-04 2020-08-03 2022-01-03 Envelope Services Provider for AS-CFMS Systems IN-AS-CFMS-150672-NC- RFB / Alternate Network Strengthening Expenditure Single Stage - One Connectivity at the Treasuries IBRD / 87650 and Revenue Information Prior Request for Bids Open - National 2,140,300.00 0.00 Canceled 2020-01-20 2020-04-02 2020-01-25 2020-06-09 2020-03-07 2020-06-22 2020-04-06 2020-05-11 2025-05-10 Envelope and Taxation Offices across Systems Assam IN-AS-CFMS-157415-NC- DIR / Design & Development Strengthening Expenditure of an Open-Source IBRD / 87650 and Revenue Information Post Direct Selection Direct 150,000.00 0.00 Canceled 2020-02-04 2020-02-09 2020-03-15 2021-01-09 Technology Platform Systems Providing Scheme Registry and Citizen Access Services IN-AS-CFMS-196355-NC- RFQ / Annual Maintenance Project Management, Pending Contract (AMC) and Facility Request for Single Stage - One IBRD / 87650 Monitoring & Evaluation and Post Open - National 73,000.00 0.00 Implementati 2020-10-05 2020-11-30 2022-11-30 Management Services (FMS) in Quotations Envelope Coordination on Finance Department and ASPIRe office IN-AS-CFMS-196778-NC- RFB / Procurement of Strengthening Expenditure Under Single Stage - Two Alternate Connectivity IBRD / 87650 and Revenue Information Post Request for Bids Open - National 700,000.00 0.00 Implementati 2020-10-09 2021-04-09 2020-10-14 2021-04-12 2020-11-03 2021-01-16 2021-02-20 2026-02-19 Envelope Services for Treasury and Systems on Taxation offices across Assam IN-AS-CFMS-203114-NC- Project Management, Pending RFQ / Facility Management Request for Single Stage - One IBRD / 87650 Monitoring & Evaluation and Post Open - National 30,000.00 0.00 Implementati 2020-11-13 2021-01-08 2023-01-08 Services for New Office space( Quotations Envelope Coordination on Kamakhya Tower) IN-AS-CFMS-225815-NC- RFQ / Hiring of Service Pending Strengthening Public Finance Request for Single Stage - One Provider for Regional IBRD / 87650 Post Open - National 6,500.00 0.00 Implementati 2021-03-27 2021-05-22 2021-11-18 Institutional Capacity Quotations Envelope Language Translation on Services. IN-AS-CFMS-225813-NC- RFQ / Hiring of Service Pending Strengthening Public Finance Request for Single Stage - One Provider for Providing IBRD / 87650 Post Open - National 17,200.00 0.00 Implementati 2021-03-27 2021-05-22 2023-05-22 Institutional Capacity Quotations Envelope Videography and related on services. CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-AS-CFMS-4524-CS-QCBS / Selection of Consultants for consultancy services for Strengthening Expenditure Quality And Cost- Under designing an e-Governance / and Revenue Information Post Open - National 148,236.00 0.00 2016-12-13 2016-02-03 2016-12-13 2016-12-13 2016-06-15 2016-12-13 2016-12-13 2016-12-13 2016-12-21 2017-01-17 2018-01-17 Based Selection Implementation system for the Department of Systems Excise, Government of Assam, India. IN-AS-CFMS-4525-CS-QCBS / Selection of Consultants for consultancy services for Strengthening Expenditure Quality And Cost- Under Institutional and GST / and Revenue Information Post Open - National 96,353.39 0.00 2016-12-13 2016-01-29 2016-12-13 2016-12-13 2016-06-15 2016-12-13 2016-07-22 2016-12-13 2016-10-04 2016-12-13 2016-12-02 2017-01-17 2018-01-17 Based Selection Implementation readiness assessment in the Systems Commissionerate of Taxes, Govt. of Assam IN-AS-CFMS-4528-CS-QCBS / Consultancy for Policy and Institutional Reform for Strengthening Public Finance Quality And Cost- Under / Post Open - National 88,941.00 302,641.56 2016-12-14 2016-07-22 2016-12-14 2016-12-14 2016-11-22 2016-12-30 2016-12-30 2017-01-14 2017-02-02 2017-02-18 2017-02-20 2017-03-25 2018-03-25 Strengthening PPP Framework Institutional Capacity Based Selection Implementation and enabling Environment for the Government of Assam IN-AS-CFMS-4483-CS-QCBS / Selection of Consultants for Designing of Financial Strengthening Expenditure Management Information Quality And Cost- Under / and Revenue Information Post Open - National 252,223.90 0.00 2016-12-13 2016-06-01 2016-12-13 2016-12-13 2016-12-13 2016-12-13 2016-12-13 2017-01-03 2018-01-03 System for the Government of Based Selection Implementation Systems Assam and support in selection of the System Integrator IN-AS-CFMS-4579-CS-LCS / Project Management, Least Cost Engaging Chartered / Monitoring & Evaluation and Post Open - National 22,235.40 4,846.94 Signed 2016-12-15 2016-09-29 2016-12-15 2016-12-15 2016-11-22 2016-12-30 2016-12-30 2017-01-29 2017-01-28 2017-02-05 2017-02-17 2017-02-12 2017-02-21 2018-02-12 Selection Accountant for AS-CFMS Coordination IN-AS-CFMS-19057-CS- Project Management, Quality And Cost- QCBS / Communications IBRD / 87650 Monitoring & Evaluation and Post Open - National 50,000.00 49,068.93 Signed 2017-07-14 2017-08-18 2017-08-04 2017-08-21 2017-09-17 2017-11-06 2017-10-15 2017-12-05 2017-11-14 2017-12-20 2017-12-19 2018-01-19 2018-01-23 2018-02-06 2019-01-23 Based Selection Consultant Coordination IN-AS-CFMS-19056-CS-CDS / Solution Provider for BI & Consultant Strengthening Public Finance Analytics Dashboard for the IBRD / 87650 Post Qualification Open - National 90,000.00 75,033.28 Signed 2017-07-28 2017-08-03 2017-08-11 2017-08-30 2017-11-07 2017-09-29 2018-01-10 2017-11-03 2018-04-17 2019-03-08 Institutional Capacity Department of Finance, Selection Government of Assam Page 4 IN-AS-CFMS-20784-CS- QCBS / Consultancy for Policy and Institutional Reform for Strengthening Public Finance Quality And Cost- IBRD / 87650 Post Open - National 100,000.00 61,565.39 Signed 2017-07-28 2016-07-22 2017-07-28 2017-07-28 2016-11-21 2017-07-28 2016-12-30 2017-07-28 2017-02-02 2017-07-28 2017-02-17 2017-07-28 2017-03-29 2017-12-05 Strengthening PPP Framework Institutional Capacity Based Selection & Enabling Environment for the Government of Assam IN-AS-CFMS-68604-CS-CQS Project Management, Consultant Under / Social Media Consultant for IBRD / 87650 Monitoring & Evaluation and Post Qualification Open - National 37,000.00 0.00 2018-08-08 2018-08-29 2018-10-12 2019-01-22 2018-11-11 2018-12-16 2019-12-16 Implementation AS-CFMS Coordination Selection IN-AS-CFMS-68680-CS-CQS Project Management, Consultant / Independent Verification IBRD / 87650 Monitoring & Evaluation and Post Qualification Open - National 120,000.00 181,893.87 Signed 2018-07-18 2018-08-29 2018-08-08 2018-09-21 2018-11-08 2018-10-21 2018-11-29 2018-11-25 2018-11-29 2023-11-24 Agency Coordination Selection IN-AS-CFMS-75908-CS-CQS Project Management, Consultant / Hiring a Statutory Auditor IBRD / 87650 Monitoring & Evaluation and Post Qualification Open - National 1,000.00 2,451.98 Signed 2018-08-30 2018-09-06 2018-09-20 2018-11-03 2018-11-14 2018-12-03 2018-12-10 2019-01-07 2018-12-10 2019-07-06 for AS-CFMS Coordination Selection IN-AS-CFMS-92282-CS- Strengthening Public Finance Quality And Cost- QCBS / Data Analytics Centre IBRD / 87650 Post Open - International 430,000.00 165,677.72 Signed 2019-01-18 2019-03-08 2019-02-08 2019-03-14 2019-03-24 2019-06-12 2019-04-21 2019-07-25 2019-05-21 2019-09-17 2019-06-25 2019-10-15 2019-07-30 2019-11-25 2022-07-29 Institutional Capacity Based Selection under AS-CFMS IN-AS-CFMS-107714-CS- QCBS / PMC for the e- Strengthening Expenditure Governance Project at Quality And Cost- IBRD / 87650 and Revenue Information Post Open - National 386,000.00 0.00 Canceled 2019-04-25 2019-05-16 2019-06-29 2019-07-27 2019-08-26 2019-09-30 2019-11-04 2021-05-05 Commissionerate of Excise, Based Selection Systems Assam, under ASPIRe Project, Government of Assam IN-AS-CFMS-108501-CS-UN / Consultancy Support for Strengthening Public Finance UN Agencies IBRD / 87650 Post Direct 700,000.00 0.00 Canceled 2019-06-04 2021-06-03 State Procurement Facilitation Institutional Capacity (Direct) Cell IN-AS-CFMS-109761-CS-UN / Consultancy Support to Strengthening Public Finance UN Agencies Pending IBRD / 87650 Post Direct 900,000.00 0.00 2019-08-19 2021-08-18 State Procurement Facilitation Institutional Capacity (Direct) Implementation Cell IN-AS-CFMS-92279-CS- Strengthening Expenditure QCBS / Project Management Quality And Cost- IBRD / 87650 and Revenue Information Post Open - National 286,000.00 0.00 Canceled 2019-01-18 2019-02-08 2019-03-24 2019-04-21 2019-05-21 2019-06-25 2019-07-30 2021-07-29 Consultancy for Infrastructure Based Selection Systems Upgradation in the Treasuries IN-AS-CFMS-125213-CS- QCBS / Consultancy for Strengthening Public Finance Quality And Cost- Pending Designing Work-flow Based IBRD / 87650 Post Open - National 120,000.00 0.00 2019-08-04 2019-08-25 2019-10-08 2019-11-05 2019-12-05 2020-01-09 2020-02-13 2021-02-12 Institutional Capacity Based Selection Implementation Ergonomic Interiors for Treasuries IN-AS-CFMS-134637-CS- QCBS / PMC for FMIS Strengthening Expenditure Quality And Cost- Pending Implementation for Finance IBRD / 87650 and Revenue Information Post Open - National 430,000.00 0.00 2019-09-27 2019-10-18 2019-12-01 2019-12-29 2020-01-28 2020-03-03 2020-04-07 2023-04-07 Based Selection Implementation Department, Government of Systems Assam IN-AS-CFMS-135145-CS- QCBS / Consultant Firm for Project Management, Quality And Cost- Revenue Augmentation in the IBRD / 87650 Monitoring & Evaluation and Post Open - National 610,000.00 177,893.83 Signed 2019-09-29 2019-11-20 2019-10-20 2021-03-22 2019-12-03 2020-02-04 2019-12-31 2020-05-04 2020-01-30 2020-10-05 2020-03-05 2020-12-08 2020-04-09 2021-01-27 2022-04-09 Based Selection State of Assam across four Coordination departments IN-AS-CFMS-139821-CS- Strengthening Expenditure QCBS / Selection of a Systems Quality And Cost- IBRD / 87650 and Revenue Information Prior Open - International 3,000,000.00 1,371,247.88 Signed 2019-10-17 2019-10-21 2019-11-07 2019-11-29 2019-12-21 2020-03-19 2020-01-18 2020-06-08 2020-02-17 2020-07-17 2020-03-23 2020-09-21 2020-04-27 2020-12-03 2021-04-27 Integrator for DBT Digital Based Selection Systems Infrastructure IN-AS-CFMS-141006-CS- QCBS / Excise Consultancy for Strengthening Expenditure Training Content Quality And Cost- Under IBRD / 87650 and Revenue Information Post Open - National 500,000.00 0.00 2019-10-24 2019-11-08 2019-11-14 2019-12-28 2020-01-13 2020-01-25 2020-02-25 2020-02-24 2020-03-11 2020-03-30 2020-05-04 2022-05-04 Development, Project Based Selection Implementation Systems Management and other services. IN-AS-CFMS-160353-CS- QCBS / Selection of a Firm for Strengthening Public Finance Quality And Cost- IBRD / 87650 Post Open - National 60,000.00 0.00 Canceled 2020-02-20 2020-03-12 2020-04-25 2020-05-23 2020-06-22 2020-07-27 2020-08-31 2021-03-29 Developing Assamese Institutional Capacity Based Selection Language Translation Tool IN-AS-CFMS-166046-CS- Consultant QCBS / Selection of a Firm for Strengthening Public Finance Pending IBRD / 87650 Post Qualification Open - National 60,000.00 0.00 2020-03-27 2020-04-17 2020-05-31 2020-06-30 2020-08-04 2021-01-31 Developing Assamese Institutional Capacity Implementation Selection Language Translation Tool IN-AS-CFMS-171552-CS-FBS Project Management, / CA firm for Internal Financial Fixed Budget Under IBRD / 87650 Monitoring & Evaluation and Post Open - National 15,000.00 0.00 2020-05-17 2020-05-29 2020-06-07 2020-07-21 2020-08-18 2020-09-17 2020-10-22 2020-11-26 2022-11-26 Management and Reporting of Selection Implementation Coordination AS-CFMS IN-AS-CFMS-171727-CS-FBS Project Management, Fixed Budget Under / Statutory Auditor for AS- IBRD / 87650 Monitoring & Evaluation and Post Open - National 12,000.00 0.00 2020-05-24 2020-05-20 2020-06-14 2020-07-28 2020-08-25 2020-09-24 2020-10-29 2020-12-03 2023-12-03 Selection Implementation CFMS Coordination IN-AS-CFMS-193877-CS- Strengthening Expenditure Consultant Pending CQS / PMC for Oversight of IBRD / 87650 and Revenue Information Post Qualification Open - National 285,000.00 0.00 2020-09-20 2020-10-05 2020-11-18 2020-12-18 2021-01-22 2023-01-22 Implementation DBT Solution Development Systems Selection IN-AS-CFMS-196354-CS- Strengthening Expenditure QCBS / HIRING OF A Quality And Cost- Pending IBRD / 87650 and Revenue Information Post Open - National 140,000.00 0.00 2020-09-28 2020-10-19 2020-10-30 2020-11-27 2020-12-04 2020-12-15 2021-01-12 2023-01-12 COMMUNICATION AGENCY Based Selection Implementation Systems FOR AS-CFMS IN-AS-CFMS-203115-CS- CQS / Design and Consultant Strengthening Public Finance Development of MOOC Portal IBRD / 87650 Post Qualification Open - National 300,000.00 203,781.05 Signed 2020-11-06 2020-11-17 2020-11-27 2021-01-10 2020-12-29 2021-02-09 2021-02-25 2021-03-16 2021-03-19 2021-05-05 Institutional Capacity for Procurement Capacity Selection Building Page 5 IN-AS-CFMS-217271-CS- Strengthening Expenditure Consultant Under CQS / Security Auditor for IBRD / 87650 and Revenue Information Post Qualification Open - National 280,000.00 0.00 2021-02-16 2021-03-07 2021-03-09 2021-04-08 2021-04-22 2021-05-22 2021-06-26 2024-06-25 Implementation FMIS and DIDS Systems Systems Selection INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-AS-CFMS-4567-CS-INDV Individual / Consultant for study of the Strengthening Public Finance Under / Post Consultant Direct 14,823.60 0.00 2016-12-14 2015-06-25 2016-12-14 2016-10-05 2016-12-14 2016-10-05 2016-12-14 2017-01-31 implementation & scale up of Institutional Capacity Implementation Selection e-procurement in Assam IN-AS-CFMS-4568-CS-INDV Project Management, Individual Under / Hiring of a short term Senior / Monitoring & Evaluation and Post Consultant Direct 10,376.51 0.00 2016-12-14 2016-08-10 2016-12-14 2016-12-14 2016-12-14 2017-03-31 Implementation Procurement Consultant Coordination Selection IN-AS-CFMS-5689-CS-INDV Individual Strengthening Public Finance Pending / ADVISOR - DEBT AND CASH / Post Consultant Direct 41,500.00 0.00 2017-01-30 2017-01-30 2017-01-30 2017-02-09 2018-02-09 Institutional Capacity Implementation MANAGEMENT Selection IN-AS-CFMS-5710-CS-INDV Strengthening Expenditure Individual Pending / DoAT Short term / and Revenue Information Post Consultant Open 65,000.00 0.00 2017-02-15 2017-04-15 2017-05-06 2017-05-28 2019-05-27 Implementation Programmers/ DBA (2 years) Systems Selection IN-AS-CFMS-5711-CS-INDV Strengthening Expenditure Individual Pending / CTD Short term / and Revenue Information Post Consultant Open 65,000.00 0.00 2017-01-17 2017-03-07 2017-03-28 2017-05-02 2019-05-02 Implementation Programmers/ DBA (2 years) Systems Selection IN-AS-CFMS-15352-CS- Project Management, Individual INDV / Procurement Support / Monitoring & Evaluation and Post Consultant Direct 24,000.00 44,897.59 Signed 2017-05-17 2017-05-22 2017-05-22 2017-05-25 2017-05-22 2017-05-31 2017-05-31 2017-06-01 2018-04-29 Staff for AS-CFMS Coordination Selection Project Management, Individual IN-AS-CFMS-28106-CS- IBRD / 87650 Monitoring & Evaluation and Post Consultant Open 74,000.00 59,093.72 Signed 2017-09-15 2017-09-26 2017-11-14 2018-05-29 2017-12-05 2018-05-29 2018-01-09 2019-08-01 2020-01-09 INDV / IT Project Manager Coordination Selection IN-AS-CFMS-30917-CS- Strengthening Expenditure Individual Pending INDV / Programmer (NIC IBRD / 87650 and Revenue Information Post Consultant Open 11,600.00 0.00 2017-10-07 2017-11-25 2017-12-16 2018-01-20 2020-01-20 Implementation Pune) for e-GRAS Systems Selection Customization Strengthening Expenditure IN-AS-CFMS-40757-CS-CDS IBRD / 87650 and Revenue Information Post Direct Selection Direct 5,000.00 0.00 Canceled 2017-12-30 2018-01-09 2018-03-15 2018-06-13 / Security Audit of e-GRAS Systems IN-AS-CFMS-40769-CS- Project Management, Individual Under INDV / eProcurement Project IBRD / 87650 Monitoring & Evaluation and Post Consultant Direct 11,000.00 0.00 2017-12-26 2018-01-05 2018-01-26 2018-03-02 2019-03-02 Implementation Manager Coordination Selection Individual IN-AS-CFMS-41230-CS- Strengthening Public Finance Under IBRD / 87650 Post Consultant Direct 11,000.00 0.00 2017-12-27 2018-01-06 2018-01-27 2018-03-03 2020-03-02 INDV / GeM Support Staff Institutional Capacity Implementation Selection IN-AS-CFMS-47697-CS- Individual Strengthening Public Finance Pending INDV / Procurement IBRD / 87650 Post Consultant Open 92,400.00 0.00 2018-02-25 2018-04-15 2018-05-06 2018-06-10 2019-06-10 Institutional Capacity Implementation Consultants (3) for CEPPA Selection IN-AS-CFMS-47698-CS- Individual Strengthening Public Finance Pending INDV / Legal Consultant for IBRD / 87650 Post Consultant Open 37,000.00 0.00 2018-02-25 2018-04-15 2018-05-06 2018-06-10 2019-06-10 Institutional Capacity Implementation CEPPA Selection IN-AS-CFMS-47702-CS- Individual INDV / Financial and Contract Strengthening Public Finance Pending IBRD / 87650 Post Consultant Open 37,000.00 0.00 2018-02-25 2018-04-15 2018-05-06 2018-06-10 2019-06-10 Management Consultant for Institutional Capacity Implementation Selection CEPPA IN-AS-CFMS-47703-CS- Individual Strengthening Public Finance Pending INDV / Data Analytics IBRD / 87650 Post Consultant Open 37,000.00 0.00 2018-02-25 2018-04-15 2018-05-06 2018-06-10 2019-06-10 Institutional Capacity Implementation Consultant for CEPPA Selection IN-AS-CFMS-47704-CS- Individual Strengthening Public Finance Under INDV / Junior Procurement IBRD / 87650 Post Consultant Open 65,000.00 0.00 2018-02-25 2018-03-23 2018-04-15 2019-01-30 2018-05-06 2018-06-10 2019-06-10 Institutional Capacity Implementation Consultants (5) for CEPPA Selection IN-AS-CFMS-51610-CS- Individual Strengthening Public Finance Under INDV / e-Procurement IBRD / 87650 Post Consultant Direct 30,000.00 0.00 2018-03-07 2018-03-07 2017-12-16 2018-03-07 2018-03-07 2019-03-07 Institutional Capacity Implementation Support Cell (5 members) Selection IN-AS-CFMS-56872-CS- Strengthening Expenditure Individual Pending INDV / Tester for Assam e- IBRD / 87650 and Revenue Information Post Consultant Limited 5,600.00 0.00 2018-04-10 2018-04-15 2018-05-06 2018-06-10 2019-06-10 Implementation GRAS Systems Selection IN-AS-CFMS-62671-CS- Strengthening Expenditure Individual Pending INDV / Senior Developer for IBRD / 87650 and Revenue Information Post Consultant Open 9,000.00 0.00 2018-05-18 2018-07-06 2018-07-27 2018-08-31 2019-08-31 Implementation DoAT Systems Selection IN-AS-CFMS-64922-CS- Project Management, Individual INDV / Architect cum Interior Under IBRD / 87650 Monitoring & Evaluation and Post Consultant Open 13,000.00 0.00 2018-06-15 2018-08-03 2018-08-24 2018-09-28 2019-06-25 Designer for Furnishing Office Implementation Coordination Selection Space for ASPIRe Project IN-AS-CFMS-68598-CS- Individual Strengthening Public Finance Pending INDV / GeM Support Staff (2 IBRD / 87650 Post Consultant Open 45,000.00 0.00 2018-07-30 2018-09-17 2018-10-08 2018-11-12 2021-11-11 Institutional Capacity Implementation persons) Selection IN-AS-CFMS-65782-CS- Individual Strengthening Public Finance INDV / Cash and Debt IBRD / 87650 Post Consultant Direct 9,200.00 5,870.43 Signed 2018-07-25 2018-08-04 2018-08-25 2018-09-29 2018-09-01 2019-09-29 Institutional Capacity Management Assistant Selection IN-AS-CFMS-72647-CS- Project Management, Individual Under INDV / Human Resources IBRD / 87650 Monitoring & Evaluation and Post Consultant Open 50,000.00 0.00 2018-08-17 2018-10-05 2018-10-26 2018-11-30 2023-11-29 Implementation Manager for AS-CFMS Coordination Selection Page 6 IN-AS-CFMS-74776-CS- Individual INDV / Director (Training), Strengthening Public Finance Pending IBRD / 87650 Post Consultant Open 37,000.00 0.00 2018-08-29 2018-10-31 2018-11-21 2018-12-26 2019-12-26 State Institute of Public Institutional Capacity Implementation Selection Finance, Assam Individual IN-AS-CFMS-83273-CS- Strengthening Public Finance Under IBRD / 87650 Post Consultant Open 11,000.00 0.00 2018-11-16 2019-01-04 2019-01-25 2019-03-01 2020-02-29 INDV / Business Analyst Institutional Capacity Implementation Selection IN-AS-CFMS-83274-CS- Individual Strengthening Public Finance Under INDV / Senior Business IBRD / 87650 Post Consultant Open 15,500.00 0.00 2018-11-16 2019-01-04 2019-01-25 2019-03-01 2020-02-29 Institutional Capacity Implementation Analyst Selection IN-AS-CFMS-85396-CS- Strengthening Expenditure Individual INDV / Technical Support Pending IBRD / 87650 and Revenue Information Post Consultant Direct 17,500.00 0.00 2018-11-16 2018-11-26 2018-12-17 2019-01-21 2019-07-20 Personnel for CTMIS (3 Implementation Systems Selection persons) IN-AS-CFMS-92274-CS- Strengthening Expenditure Individual Pending INDV / IT Expert for technical IBRD / 87650 and Revenue Information Post Consultant Direct 3,650.00 0.00 2018-12-28 2019-01-07 2019-01-28 2019-03-04 2019-06-02 Implementation evaluation of FinAssam Systems Selection Project Management, Individual IN-AS-CFMS-93309-CS- Pending IBRD / 87650 Monitoring & Evaluation and Post Consultant Open 12,000.00 0.00 2019-01-25 2019-03-15 2019-04-05 2019-05-10 2020-05-09 INDV / Content Writer Implementation Coordination Selection IN-AS-CFMS-96331-CS- Strengthening Expenditure Individual INDV / Domain Expert - Pending IBRD / 87650 and Revenue Information Post Consultant Direct 2,200.00 0.00 2019-01-31 2019-02-10 2019-03-03 2019-04-07 2019-07-06 Financial Rules & Regulations Implementation Systems Selection (Treasury) IN-AS-CFMS-96332-CS- Strengthening Expenditure Individual INDV / Domain Expert - Pending IBRD / 87650 and Revenue Information Post Consultant Direct 2,200.00 0.00 2019-01-31 2019-02-10 2019-03-03 2019-04-07 2019-07-06 Financial Rules & Regulations Implementation Systems Selection (Pension) IN-AS-CFMS-96334-CS- Strengthening Expenditure Individual INDV / Domain Expert - Pending IBRD / 87650 and Revenue Information Post Consultant Direct 2,200.00 0.00 2019-01-31 2019-02-10 2019-03-03 2019-04-07 2019-07-06 Financial Rules & Regulations Implementation Systems Selection (Audit L/F) IN-AS-CFMS-96335-CS- Project Management, Individual Pending INDV / Visual Design IBRD / 87650 Monitoring & Evaluation and Post Consultant Open 11,000.00 0.00 2019-01-31 2019-03-21 2019-04-11 2019-05-16 2019-11-12 Implementation Specialist Coordination Selection IN-AS-CFMS-101120-CS- Individual Strengthening Public Finance Pending INDV / Advisor - Financial IBRD / 87650 Post Consultant Open 26,000.00 0.00 2019-02-28 2019-04-18 2019-05-09 2019-06-13 2020-06-12 Institutional Capacity Implementation Inclusion and DBT Selection IN-AS-CFMS-28107-CS- Strengthening Expenditure Individual INDV / ICT Infrastructure IBRD / 87650 and Revenue Information Post Consultant Open 27,700.00 0.00 Canceled 2017-09-15 2017-11-14 2017-12-05 2018-01-09 2019-01-09 Specialist Systems Selection IN-AS-CFMS-118046-CS- CDS / PMC for the e- Strengthening Expenditure Governance Project at IBRD / 87650 and Revenue Information Post Direct Selection Direct 200,000.00 214,723.19 Signed 2019-06-28 2019-10-24 2019-07-08 2019-10-24 2019-09-11 2020-01-27 2020-03-09 Commissionerate of Taxes, Systems Assam, under ASPIRe Project, Government of Assam IN-AS-CFMS-110931-CS- Individual INDV / Architect for Strengthening Public Finance Pending IBRD / 87650 Post Consultant Open 36,000.00 0.00 2019-06-28 2019-08-16 2019-09-06 2019-10-11 2020-10-10 refurbishment of Finance Institutional Capacity Implementation Selection Department units IN-AS-CFMS-120383-CS- Strengthening Expenditure Pending CDS / Oracle Annual Technical IBRD / 87650 and Revenue Information Post Direct Selection Direct 121,225.00 0.00 2019-06-28 2019-06-28 2019-07-19 2020-03-31 Implementation Support (2019-20) Systems IN-AS-CFMS-120405-CS- Individual Strengthening Public Finance Pending INDV / Junior Cash & Debt IBRD / 87650 Post Consultant Open 12,900.00 0.00 2019-07-19 2019-09-20 2019-10-11 2019-11-15 2020-11-14 Institutional Capacity Implementation Management Consultant Selection IN-AS-CFMS-120410-CS- CDS / Consultancy for Study Strengthening Public Finance Pending IBRD / 87650 Post Direct Selection Direct 75,000.00 0.00 2019-07-26 2019-08-05 2019-10-09 2020-10-08 of State Channelizing Institutional Capacity Implementation Agencies IN-AS-CFMS-123357-CS- Individual Strengthening Public Finance Pending INDV / Consultant for service IBRD / 87650 Post Consultant Limited 7,800.00 0.00 2019-07-21 2019-07-26 2019-08-16 2019-09-20 2020-03-18 Institutional Capacity Implementation sector training under GST Selection IN-AS-CFMS-124291-GO- RFQ / Development of Strengthening Expenditure Under ePPO,eGPO and eCPO in AG IBRD / 87650 and Revenue Information Post Direct Selection Direct 5,000.00 0.00 2019-08-13 2019-08-23 2019-08-23 2019-10-27 2020-10-26 Implementation System for Integration with Systems FinAssam IN-AS-CFMS-129211-CS- CDS / Consultancy for Strengthening Public Finance Under IBRD / 87650 Post Direct Selection Direct 72,000.00 0.00 2019-09-03 2019-11-29 2019-09-13 2019-11-17 2020-11-16 Modernization of the Excise Institutional Capacity Implementation Chemical Lab IN-AS-CFMS-134804-CS- Individual INDV / Director, Training for Strengthening Public Finance Pending IBRD / 87650 Post Consultant Direct 26,000.00 0.00 2019-10-09 2019-10-19 2019-11-09 2019-12-14 2020-12-13 Public Finance Management Institutional Capacity Implementation Selection Institute IN-AS-CFMS-140239-CS- CDS / Consultancy for Bid Project Management, Process Management for IBRD / 87650 Monitoring & Evaluation and Post Direct Selection Direct 57,500.00 68,081.01 Signed 2019-10-25 2019-12-19 2019-11-04 2020-01-14 2020-01-08 2020-02-17 2021-01-07 Digital Infrastructure for DBT Coordination Schemes (DIDS) - SI procurement IN-AS-CFMS-141002-CS- Individual INDV / Banking Sector Strengthening Public Finance Pending IBRD / 87650 Post Consultant Open 20,000.00 0.00 2019-10-21 2019-12-09 2019-12-30 2020-02-03 2021-02-02 Consultant for DBT / Financial Institutional Capacity Implementation Selection Inclusion Page 7 IN-AS-CFMS-145116-CS- Strengthening Expenditure Individual Pending INDV / Hiring of Domain IBRD / 87650 and Revenue Information Post Consultant Direct 11,000.00 0.00 2019-11-15 2019-11-25 2019-12-16 2020-01-20 2020-12-20 Implementation Expert - Audit Systems Selection IN-AS-CFMS-147130-CS- Strengthening Expenditure Individual Pending INDV / Hiring of a Data IBRD / 87650 and Revenue Information Post Consultant Open 90,000.00 0.00 2019-11-30 2020-01-18 2020-02-08 2020-03-14 2023-03-14 Implementation Engineer (Data Analytics) Systems Selection IN-AS-CFMS-157409-CS- Strengthening Expenditure Individual Pending INDV / Hiring of a Technical IBRD / 87650 and Revenue Information Post Consultant Open 144,480.00 0.00 2020-02-05 2020-03-25 2020-04-15 2020-05-20 2023-05-20 Implementation Architect to support the PMU Systems Selection IN-AS-CFMS-157410-CS- Strengthening Expenditure Individual Pending INDV / Hiring of a Technical IBRD / 87650 and Revenue Information Post Consultant Open 108,000.00 0.00 2020-02-05 2020-03-25 2020-04-15 2020-05-20 2023-05-20 Implementation Lead to support the PMU Systems Selection IN-AS-CFMS-166042-CS- CDS / Design & Development of an Open-Source Strengthening Public Finance Pending IBRD / 87650 Post Direct Selection Direct 150,000.00 0.00 2020-03-27 2020-04-06 2020-06-10 2020-12-07 Technology Platform Institutional Capacity Implementation Providing Scheme Registry and Citizen Access Services Strengthening Expenditure Individual IN-AS-CFMS-171862-CS- Pending IBRD / 87650 and Revenue Information Post Consultant Open 15,500.00 0.00 2020-05-17 2020-07-05 2020-07-26 2020-08-30 2021-08-30 INDV / UI / UX Designer Implementation Systems Selection IN-AS-CFMS-171553-CS- Strengthening Public Finance CDS / Engagement of CSI and IBRD / 87650 Post Direct Selection Direct 100,000.00 0.00 Canceled 2020-05-24 2020-06-03 2020-08-07 2022-08-07 Institutional Capacity a Training Partner IN-AS-CFMS-200396-CS- CDS / Engagement of CSI as Strengthening Public Finance IBRD / 87650 Post Direct Selection Direct 106,500.00 79,094.63 Signed 2020-10-22 2020-10-22 2020-11-01 2020-11-13 2020-12-15 2021-03-22 2022-12-15 an IT Skill Enhancement for Institutional Capacity Finance Department IN-AS-CFMS-218512-CS- INDV / Architect cum Civil Strengthening Expenditure Individual Pending Engineer for technical support IBRD / 87650 and Revenue Information Post Consultant Open 20,000.00 0.00 2021-02-17 2021-04-07 2021-04-28 2021-06-02 2021-11-29 Implementation in the refurbishment of the Systems Selection Excise Chemical Laboratory IN-AS-CFMS-232778-CS- CDS / Engagement of Kerala Institute of Local Strengthening Public Finance Under Administration (KILA) for IBRD / 87650 Post Direct Selection Direct 72,000.00 0.00 2021-05-25 2021-05-25 2021-06-04 2021-08-08 2022-08-08 Institutional Capacity Implementation Capacity Building of Directorate of Audit (Local Fund), Assam (DALF) Page 8 PROCUREMENT PLAN (Textual Part)P163742 Project information: [country] [Project name] [P-number]Sri Lanka – Climate Smart Irrigated Agriculture Project – P163742 Project Implementation agency: [insert legal name]Ministry of Agriculture Date of the Procurement Plan: 24 January, 2019[insert date] Period covered by this Procurement Plan: [insert from – to period]24 January - 31 December 2019 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: : In accordance with the Procurement Regulations for IPF Borrowers (July 2016, revised November 2017) (“Procurement Regulations”), when approaching the national market, as agreed in the Procurement Plan tables in STEP, the country’s own procurement procedures may be used. When the Borrower, for the procurement of goods, works and non-consulting services, uses its own national open competitive procurement arrangements as set forth in Sri Lanka’s Procurement Guidelines 2006, such arrangements shall be subject to paragraph 5.4 of the Bank’s Procurement Regulations and the following conditions: 1. Only bidding documents acceptable to the Bank shall be used for all national open competitive procurement. 2. The request for bids/request for proposals document shall require that bidders/proposers submitting bids/proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. 3. The eligibility of bidders shall be as defined under Section III of the World Bank Procurement Regulations for IPF Borrowers (Procurement Regulations): accordingly, no bidder or potential bidder shall be declared ineligible for contracts financed by the Bank for reasons other than those provided in Section III of the Procurement Regulations. In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in [insert appropriate references to the national procurement legislation], such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. List only the applicable conditions required to ensure consistency with paragraph 5.4 of the Procurement Regulations. If no conditions apply, delete the phrase “and the following conditions”. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Otherwise state “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables Otherwise state “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Specify for each Goods: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables]; Works: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables] Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. [Include this sentence only if the Bank has formally agreed to provide the Borrower with HEIS. Otherwise delete] Other Relevant Procurement Information. Provide any other relevant procurement information such as procedures for CDD components, Procurement in Situations of Urgent Need of Assistance or Capacity Constraints etc. PROCUREMENT Sri Lanka : Climate Smart Irrigated Agriculture Project PLAN General Information Country: Sri Lanka Bank’s Approval Date of the Original Procurement Plan: 2021-05-19 2021-05-19 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P163742 GPN Date: 2020-07-29 Project Name: Climate Smart Irrigated Agriculture Project Loan / Credit No: IDA / 63460 D Executing Agency(ies): isaster Management Centre WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LK-DMC-235213-GO-RFQ / Under Procurement of beds and Contingent Emergency Request for Single Stage - One IDA / 63460 Post Limited 48,000.00 0.00 Implementati 2021-05-24 2021-07-19 2021-07-22 mattress (single bed 72"x30" Response Quotations Envelope on with mattress) NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 1 PROCUREMENT PLAN (Textual Part) Project information: Bosnia and Herzegovina – Real Estate Registration Project (Additional Financing) – P128950 Project Implementation agency: Federal Administration for Geodetic and Real Property Affairs and Republic of Srpska Administration for Geodetic and Property Affairs Date of the Procurement Plan: December 22, 2020 Period covered by this Procurement Plan: January – December 2021 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Specify for each Goods: Not applicable Works: Not applicable PROCUREMENT Bosnia and Herzegovina : REAL ESTATE REGISTRATION PROJECT PLAN General Information Country: Bosnia and Herzegovina Bank’s Approval Date of the Original Procurement Plan: 2020-12-22 2021-05-20 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P128950 GPN Date: 2020-12-29 Project Name: REAL ESTATE REGISTRATION PROJECT Loan / Credit No: IBRD / 90480 F Executing Agency(ies): ederal Administration for Geodetic and Real Property Affairs WORKS Procureme Activity Reference No. / Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH nt Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) Justification for Award Type Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BA-FGA-212516-GO-RFQ- Component B - Real Estate B.2.2.1.3 / Replaceable HW Request for Single Stage - One IBRD / 90480 Registration Infrastructure Post Limited 0.00 Canceled 2021-02-01 2021-05-02 2021-07-01 components required for HW Quotations Envelope Development maintenance - Phase 1 BA-FGA-227681-GO-RFQ- Component B - Real Estate B.2.2.1.3 / Replaceable HW Request for Single Stage - One IBRD / 90480 Registration Infrastructure Post Limited 43,505.18 Signed 2021-04-06 2021-04-16 2021-05-15 2021-05-27 2022-07-31 components required for HW Quotations Envelope Development maintenance BA-FGA-239590-GO-RFQ- Component C - Policy and Under Request for Single Stage - One C.3.2.2.2 / Office supply - IBRD / 90480 institutional development, Post Limited 0.00 Implementati 2021-06-21 2021-06-18 2021-07-09 2022-08-09 Quotations Envelope Phase 1, CY 2021 - C.3.2.2.2 and project management on NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BA-FGA-212390-NC-RFQ- A.1.3.1 / Printing of promo Component A - Real Estate Request for Single Stage - One material (brochures, flyers, IBRD / 90480 Registration Data Post Limited 2,644.89 Signed 2021-01-15 2021-01-29 2021-03-31 2021-03-01 2022-07-31 Quotations Envelope posters, and other promo Development mat.) - Phase 1 BA-FGA-212394-NC-RFB- Component A - Real Estate A.2.1.1.1 / Harmonization Single Stage - One IBRD / 90480 Registration Data Post Request for Bids Open - National 778,018.22 Signed 2021-01-07 2021-02-05 2021-01-12 2021-02-05 2021-02-26 2021-03-22 2021-03-10 2021-04-02 2021-04-12 2021-04-21 2021-10-09 data on cadastre and land Envelope Development book - Phase 1 BA-FGA-212457-NC-RFB- A.3.1 / Vectorization and Component A - Real Estate Single Stage - One cadastral database creation IBRD / 90480 Registration Data Post Request for Bids Open - National 123,541.91 Signed 2021-01-07 2021-02-01 2021-01-12 2021-02-02 2021-02-26 2021-03-19 2021-03-05 2021-04-02 2021-04-12 2021-04-21 2021-08-25 Envelope (preparation for REC) - Phase Development 1 BA-FGA-212461-NC-RFB- Component B - Real Estate B.3.2.1 / Cadastral scanning Single Stage - One IBRD / 90480 Registration Infrastructure Post Request for Bids Open - National 41,083.88 Signed 2021-01-07 2021-02-05 2021-01-12 2021-02-05 2021-02-26 2021-03-22 2021-03-05 2021-04-02 2021-04-12 2021-04-29 2021-08-10 and indexing for digital Envelope Development archives - Phase 1 BA-FGA-212703-NC-DIR - A.2.2.2.3.1 / Publishing costs Component A - Real Estate - Official Gazette of B&H, IBRD / 90480 Registration Data Post Direct Selection Direct 2,168.36 Signed 2021-01-07 2021-01-01 2021-01-07 2021-01-04 2021-01-12 2021-01-12 2021-12-31 Official Gazette of Federation Development B&H BA-FGA-212704-NC-DIR- Component A - Real Estate A.2.2.2.3.2 / Publishing costs IBRD / 90480 Registration Data Post Direct Selection Direct 2,168.36 Signed 2021-01-07 2021-01-01 2021-01-07 2021-01-04 2021-01-12 2021-01-12 2021-12-31 - daily newspaper Avaz -roto Development press d.o.o. Sarajevo BA-FGA-212705-NC-DIR- Component A - Real Estate A.2.2.2.3.3 / Publishing costs IBRD / 90480 Registration Data Post Direct Selection Direct 2,168.36 Signed 2021-01-07 2021-01-01 2021-01-07 2021-01-04 2021-01-12 2021-01-12 2021-12-31 - daily newspaper Večernji Development List BA-FGA-213262-NC-DIR- A.2.2.2.5.1 / Delivery cost of Component A - Real Estate Decisions on registrations IBRD / 90480 Registration Data Post Direct Selection Direct 6,040.44 Signed 2021-01-11 2021-01-01 2021-01-12 2020-12-23 2021-02-01 2021-02-01 2022-12-31 (Two posts) - JP BH POŠTA Development d.o.o. Sarajevo BA-FGA-213268-NC-DIR- A.2.2.2.5.2 / Delivery cost of Component A - Real Estate Decisions on registrations IBRD / 90480 Registration Data Post Direct Selection Direct 6,040.44 Signed 2021-01-11 2021-01-01 2021-01-12 2020-12-29 2021-02-01 2021-02-01 2022-12-31 (Two posts) - Hrvatska pošta Development d.o.o. Mostar BA-FGA-236325-NC-RFQ- Component B - Real Estate Pending B.3.3.1 / Indexing of land Request for Single Stage - One IBRD / 90480 Registration Infrastructure Post Limited 0.00 Implementati 2021-06-01 2021-08-10 2022-01-31 registry data for digital Quotations Envelope Development on archives - Phase 1 CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 1 BA-FGA-227687-CS-CQS- B.1.1.2A / Design for Component B - Real Estate Consultant Under renovation od CO's/LRO's IBRD / 90480 Registration Infrastructure Post Qualification Open - National 0.00 2021-04-01 2021-04-06 2021-04-22 2021-06-07 2021-05-24 2021-05-26 2021-07-07 2022-07-15 Implementation and Supervision of renovation Development Selection works of CO's/LRO's BA-FGA-236340-CS-CQS- C.2.2.1-A.1.2.1 / Project Component A - Real Estate Consultant Public Awareness Campaigne Under IBRD / 90480 Registration Data Post Qualification Open - National 0.00 2021-05-25 2021-05-27 2021-06-09 2021-06-08 2021-07-12 2021-07-26 2021-08-16 2022-07-31 (C.2.2.1) and Media Services Implementation Development Selection (Local Radio and TV) - Phase 1 (A.1.2.1) INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Contract Type Process Status Teams of Reference Identified/Selected Signed Contract Contract Completion No. (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BA-FGA-210575-CS-CDS - Component C - Policy and C.3.2.1A.1 / Monitoring and IBRD / 90480 institutional development, Post Direct Selection Direct 9,726.38 Signed 2020-12-17 2020-12-23 2020-12-21 2020-12-22 2021-01-01 2021-01-01 2021-03-31 Evaluation Specialist and project management BA-FGA-210580-CS-CDS - Component C - Policy and C.3.2.1A.2 / Procurement IBRD / 90480 institutional development, Post Direct Selection Direct 35,632.05 Signed 2020-12-17 2020-12-23 2020-12-21 2020-12-22 2021-01-01 2021-01-01 2021-03-31 specialist and project management BA-FGA-210581-CS-CDS - Component C - Policy and C.3.2.1A.3 / Administrative IBRD / 90480 institutional development, Post Direct Selection Direct 26,297.43 Signed 2020-12-17 2020-12-23 2020-12-21 2020-12-22 2021-01-01 2021-01-01 2021-03-31 assistant and project management BA-FGA-210582-CS-CDS - Component C - Policy and C.3.2.1A.4 / Finance IBRD / 90480 institutional development, Post Direct Selection Direct 5,522.07 Signed 2020-12-17 2020-12-23 2020-12-21 2020-12-22 2021-01-01 2021-01-01 2021-03-31 consultant and project management BA-FGA-210585-CS-CDS - Component C - Policy and C.3.2.1A.5 / Land IBRD / 90480 institutional development, Post Direct Selection Direct 35,632.05 Signed 2020-12-17 2020-12-23 2020-12-21 2020-12-22 2021-01-01 2021-01-01 2021-03-31 Administration specialist and project management BA-FGA-210592-CS-CDS - Component C - Policy and C.3.2.1A.6 / Cadastre IBRD / 90480 institutional development, Post Direct Selection Direct 35,632.05 Signed 2020-12-17 2020-12-23 2020-12-21 2020-12-22 2021-01-01 2021-01-01 2021-03-31 specialist and project management Component B - Real Estate BA-FGA-210598-CS-CDS - IBRD / 90480 Registration Infrastructure Post Direct Selection Direct 34,918.01 Signed 2020-12-17 2020-12-23 2020-12-21 2020-12-22 2021-01-01 2021-01-01 2021-03-31 B.2.1.1A.1 / IT Consultant Development Component A - Real Estate BA-FGA-210600-CS-CDS - IBRD / 90480 Registration Data Post Direct Selection Direct 4,455.31 Signed 2020-12-17 2020-12-23 2020-12-21 2020-12-22 2021-01-01 2021-01-01 2021-03-31 A.1.1.1A.1 / Social Specialist Development BA-FGA-210601-CS-CDS - Component A - Real Estate A.2.2.2.4A.1 / Individual IBRD / 90480 Registration Data Post Direct Selection Direct 6,275.09 Signed 2020-12-17 2020-12-23 2020-12-21 2020-12-22 2021-01-01 2021-01-01 2021-12-31 consultant for delivery of Development decisions on registration BA-FGA-210744-CS-CDS - Component A - Real Estate A.2.2.2.4A.2 / Individual IBRD / 90480 Registration Data Post Direct Selection Direct 8,785.12 Signed 2020-12-18 2020-12-23 2020-12-23 2020-12-22 2021-01-01 2021-01-01 2021-12-31 consultant for delivery of Development decisions on registration BA-FGA-210745-CS-CDS - Component A - Real Estate A.2.2.2.4A.3 / Individual IBRD / 90480 Registration Data Post Direct Selection Direct 9,412.63 Signed 2020-12-18 2020-12-23 2020-12-22 2020-12-22 2021-01-01 2021-01-01 2021-12-31 consultant for delivery of Development decisions on registration BA-FGA-210746-CS-CDS - Component A - Real Estate A.2.2.2.4A.4 / Individual IBRD / 90480 Registration Data Post Direct Selection Direct 7,530.10 Signed 2020-12-18 2020-12-23 2020-12-22 2020-12-22 2021-01-01 2021-01-01 2021-12-31 consultant for delivery of Development decisions on registration BA-FGA-210748-CS-CDS - Component A - Real Estate A.2.2.2.4A.5 / Individual IBRD / 90480 Registration Data Post Direct Selection Direct 8,785.12 Signed 2020-12-18 2020-12-23 2020-12-22 2020-12-22 2021-01-01 2021-01-01 2021-12-31 consultant for delivery of Development decisions on registration BA-FGA-210751-CS-CDS - Component A - Real Estate A.2.2.2.4A.6 / Individual IBRD / 90480 Registration Data Post Direct Selection Direct 6,275.09 Signed 2020-12-18 2020-12-23 2020-12-22 2020-12-22 2021-01-01 2021-01-01 2021-12-31 consultant for delivery of Development decisions on registration BA-FGA-210754-CS-CDS - Component A - Real Estate A.2.2.2.4A.7 / Individual IBRD / 90480 Registration Data Post Direct Selection Direct 8,785.12 Terminated 2020-12-18 2020-12-23 2020-12-22 2020-12-22 2021-01-01 2021-01-01 2021-12-31 consultant for delivery of Development decisions on registration Component C - Policy and BA-FGA-210755-CS-CDS - IBRD / 90480 institutional development, Post Direct Selection Direct 940.18 Signed 2020-12-18 2020-12-23 2020-12-24 2020-12-22 2021-01-01 2021-01-01 2021-03-31 C.3.2.3.1A.1 / Interpreter and project management BA-FGA-210756-CS-CDS - Component A - Real Estate A.2.2.1A.1 / Temporary Land IBRD / 90480 Registration Data Post Direct Selection Direct 7,515.38 Signed 2020-12-18 2020-12-23 2020-12-22 2020-12-22 2021-01-01 2021-01-01 2021-12-31 Registry Assistant Development BA-FGA-210758-CS-CDS - Component A - Real Estate A.2.2.1A.2 / Temporary Land IBRD / 90480 Registration Data Post Direct Selection Direct 7,515.38 Signed 2020-12-18 2020-12-23 2020-12-22 2020-12-22 2021-01-01 2021-01-01 2021-12-31 Registry Assistant Development BA-FGA-210759-CS-CDS - Component A - Real Estate A.2.2.1A.3 / Temporary Land IBRD / 90480 Registration Data Post Direct Selection Direct 7,515.38 Signed 2020-12-18 2020-12-23 2020-12-22 2020-12-22 2021-01-01 2021-01-01 2021-12-31 Registry Assistant Development BA-FGA-210761-CS-CDS - Component A - Real Estate A.2.2.1A.4 / Temporary Land IBRD / 90480 Registration Data Post Direct Selection Direct 9,394.22 Terminated 2020-12-18 2020-12-23 2020-12-22 2020-12-22 2021-01-01 2021-01-01 2021-12-31 Registry Assistant Development Page 2 BA-FGA-210762-CS-CDS - Component A - Real Estate A.2.2.1A.5 / Temporary Land IBRD / 90480 Registration Data Post Direct Selection Direct 9,394.22 Signed 2020-12-18 2020-12-23 2020-12-22 2020-12-22 2021-01-01 2021-01-01 2021-12-31 Registry Assistant Development BA-FGA-210763-CS-CDS - Component A - Real Estate A.2.2.1A.6 / Temporary Land IBRD / 90480 Registration Data Post Direct Selection Direct 7,515.38 Signed 2020-12-18 2020-12-23 2020-12-22 2020-12-22 2021-01-01 2021-01-01 2021-12-31 Registry Assistant Development BA-FGA-210764-CS-CDS- Component A - Real Estate A.2.2.1A.7 / Temporary Land IBRD / 90480 Registration Data Post Direct Selection Direct 9,394.22 Terminated 2020-12-18 2020-12-23 2020-12-22 2020-12-22 2021-01-01 2021-01-01 2021-12-31 Registry Assistant Development BA-FGA-210765-CS-CDS - Component A - Real Estate A.2.2.1A.8 / Temporary Land IBRD / 90480 Registration Data Post Direct Selection Direct 7,521.24 Signed 2020-12-18 2020-12-23 2020-12-22 2020-12-22 2021-01-01 2021-01-01 2021-12-31 Registry Assistant Development BA-FGA-210766-CS-CDS - Component A - Real Estate A.2.2.1A.9 / Temporary Land IBRD / 90480 Registration Data Post Direct Selection Direct 11,273.07 Signed 2020-12-18 2020-12-23 2020-12-22 2020-12-22 2021-01-01 2021-01-01 2021-12-31 Registry Assistant Development BA-FGA-210767-CS-CDS- Component A - Real Estate A.2.2.1A.10 / Temporary IBRD / 90480 Registration Data Post Direct Selection Direct 11,273.07 Signed 2020-12-18 2020-12-23 2020-12-22 2020-12-22 2021-01-01 2021-01-01 2021-12-31 Land Registry Assistant Development BA-FGA-210769-CS-CDS- Component A - Real Estate A.2.2.1A.11 / Temporary IBRD / 90480 Registration Data Post Direct Selection Direct 9,394.22 Signed 2020-12-18 2020-12-23 2020-12-22 2020-12-22 2021-01-01 2021-01-01 2021-12-31 Land Registry Assistant Development BA-FGA-210771-CS-CDS- Component A - Real Estate A.2.2.1A.12 / Temporary IBRD / 90480 Registration Data Post Direct Selection Direct 9,394.22 Signed 2020-12-18 2020-12-23 2020-12-22 2020-12-22 2021-01-01 2021-01-01 2021-12-31 Land Registry Assistant Development BA-FGA-210774-CS-CDS- Component A - Real Estate A.2.2.1A.13 / Temporary IBRD / 90480 Registration Data Post Direct Selection Direct 9,412.63 Signed 2020-12-18 2020-12-23 2020-12-22 2020-12-22 2021-01-01 2021-01-01 2021-12-31 Land Registry Assistant Development BA-FGA-210775-CS-CDS- Component A - Real Estate A.2.2.1A.14 / Temporary IBRD / 90480 Registration Data Post Direct Selection Direct 9,412.63 Signed 2020-12-21 2020-12-23 2020-12-23 2020-12-22 2021-01-01 2021-01-01 2021-12-31 Land Registry Assistant Development BA-FGA-210778-CS-CDS- Component A - Real Estate A.2.2.1A.15 / Temporary IBRD / 90480 Registration Data Post Direct Selection Direct 12,525.63 Signed 2020-12-18 2020-12-23 2020-12-22 2020-12-22 2021-01-01 2021-01-01 2021-12-31 Land Registry Assistant Development BA-FGA-210780-CS-CDS- Component A - Real Estate A.2.2.1A.16 / Temporary IBRD / 90480 Registration Data Post Direct Selection Direct 12,525.63 Signed 2020-12-18 2020-12-23 2020-12-22 2020-12-22 2021-01-01 2021-01-01 2021-12-31 Land Registry Assistant Development BA-FGA-210785-CS-CDS- Component A - Real Estate A.2.2.1A.18 / Temporary IBRD / 90480 Registration Data Post Direct Selection Direct 3,131.41 Signed 2020-12-18 2020-12-23 2020-12-22 2020-12-22 2021-01-01 2021-01-01 2021-07-31 Land Registry Assistant Development BA-FGA-210787-CS-CDS - Component A - Real Estate A.2.2.1A.19 / Temporary IBRD / 90480 Registration Data Post Direct Selection Direct 3,137.54 Signed 2020-12-18 2020-12-23 2020-12-22 2020-12-22 2021-01-01 2021-01-01 2021-07-31 Land Registry Assistant Development BA-FGA-210790-CS-CDS - Component A - Real Estate A.2.2.1A.21 / Temporary IBRD / 90480 Registration Data Post Direct Selection Direct 3,131.41 Signed 2020-12-18 2020-12-23 2020-12-22 2020-12-22 2021-01-01 2021-01-01 2021-07-31 Land Registry Assistant Development BA-FGA-210791-CS-CDS- Component A - Real Estate A.2.2.1A.22 / Temporary IBRD / 90480 Registration Data Post Direct Selection Direct 3,137.54 Signed 2020-12-18 2020-12-23 2020-12-22 2020-12-22 2021-01-01 2021-01-01 2021-07-31 Land Registry Assistant Development BA-FGA-210792-CS-CDS - Component A - Real Estate A.2.2.1A.23 / Temporary IBRD / 90480 Registration Data Post Direct Selection Direct 3,137.54 Terminated 2020-12-18 2020-12-23 2020-12-22 2020-12-22 2021-01-01 2021-01-01 2021-07-31 Land Registry Assistant Development BA-FGA-210793-CS-CDS- Component A - Real Estate A.2.2.1A.24 / Temporary IBRD / 90480 Registration Data Post Direct Selection Direct 3,137.54 Signed 2020-12-18 2020-12-23 2020-12-22 2020-12-22 2021-01-01 2021-01-01 2021-07-31 Land Registry Assistant Development BA-FGA-210795-CS-CDS - Component A - Real Estate A.2.2.1A.25 / Temporary IBRD / 90480 Registration Data Post Direct Selection Direct 7,515.38 Signed 2020-12-18 2020-12-23 2020-12-22 2020-12-22 2021-01-01 2021-01-01 2021-12-31 Land Registry Assistant Development BA-FGA-210796-CS-CDS- Component A - Real Estate A.2.2.1A.26 / Temporary IBRD / 90480 Registration Data Post Direct Selection Direct 7,515.38 Signed 2020-12-18 2020-12-23 2020-12-22 2020-12-22 2021-01-01 2021-01-01 2021-12-31 Land Registry Assistant Development BA-FGA-210798-CS-CDS- Component A - Real Estate A.2.2.1A.27 / Temporary IBRD / 90480 Registration Data Post Direct Selection Direct 9,394.22 Terminated 2020-12-18 2020-12-23 2020-12-22 2020-12-22 2021-01-01 2021-01-01 2021-12-31 Land Registry Assistant Development BA-FGA-210800-CS-CDS - Component A - Real Estate A.2.2.1A.28 / Temporary IBRD / 90480 Registration Data Post Direct Selection Direct 9,394.22 Signed 2020-12-18 2020-12-23 2020-12-22 2020-12-22 2021-01-01 2021-01-01 2021-12-31 Land Registry Assistant Development BA-FGA-210801-CS-CDS- Component A - Real Estate A.2.2.1A.29 / Temporary IBRD / 90480 Registration Data Post Direct Selection Direct 9,394.22 Signed 2020-12-18 2020-12-23 2020-12-22 2020-12-22 2021-01-01 2021-01-01 2021-12-31 Land Registry Assistant Development BA-FGA-210803-CS-CDS- Component A - Real Estate A.2.2.1A.30 / Temporary IBRD / 90480 Registration Data Post Direct Selection Direct 8,157.61 Signed 2020-12-18 2020-12-23 2020-12-22 2020-12-22 2021-01-01 2021-01-01 2021-12-31 Land Registry Assistant Development BA-FGA-210805-CS-CDS - Component A - Real Estate A.2.2.1A.31 / Temporary IBRD / 90480 Registration Data Post Direct Selection Direct 8,157.61 Signed 2020-12-18 2020-12-23 2020-12-22 2020-12-22 2021-01-01 2021-01-01 2021-12-31 Land Registry Assistant Development BA-FGA-210807-CS-CDS - Component A - Real Estate A.2.2.1A.32 / Temporary IBRD / 90480 Registration Data Post Direct Selection Direct 9,412.63 Signed 2020-12-18 2020-12-23 2020-12-22 2020-12-22 2021-01-01 2021-01-01 2021-12-31 Land Registry Assistant Development Page 3 BA-FGA-210808-CS-CDS - Component A - Real Estate A.2.2.1A.33 / Temporary IBRD / 90480 Registration Data Post Direct Selection Direct 9,412.63 Signed 2020-12-18 2020-12-23 2020-12-22 2020-12-22 2021-01-01 2021-01-01 2021-12-31 Land Registry Assistant Development BA-FGA-210810-CS-CDS - Component A - Real Estate A.2.2.1A.34 / Temporary IBRD / 90480 Registration Data Post Direct Selection Direct 9,412.63 Signed 2020-12-18 2020-12-23 2020-12-22 2020-12-22 2021-01-01 2021-01-01 2021-12-31 Land Registry Assistant Development BA-FGA-210811-CS-CDS - Component A - Real Estate A.2.2.1A.35 / Temporary IBRD / 90480 Registration Data Post Direct Selection Direct 9,412.63 Signed 2020-12-18 2020-12-23 2020-12-22 2020-12-22 2021-01-01 2021-01-01 2021-12-31 Land Registry Assistant Development BA-FGA-211121-CS-CDS - Component A - Real Estate A.2.2.1A.36 / Temporary IBRD / 90480 Registration Data Post Direct Selection Direct 11,295.15 Signed 2020-12-21 2020-12-23 2020-12-23 2020-12-22 2021-01-01 2021-01-01 2021-12-31 Land Registry Assistant Development BA-FGA-211122-CS-CDS - Component A - Real Estate A.2.2.1A.37 / Temporary IBRD / 90480 Registration Data Post Direct Selection Direct 11,295.15 Signed 2020-12-21 2020-12-23 2020-12-23 2020-12-22 2021-01-01 2021-01-01 2021-12-31 Land Registry Assistant Development BA-FGA-211124-CS-CDS - Component A - Real Estate A.2.2.1A.38 / Temporary IBRD / 90480 Registration Data Post Direct Selection Direct 11,295.15 Signed 2020-12-21 2020-12-23 2020-12-23 2020-12-22 2021-01-01 2021-01-01 2021-12-31 Land Registry Assistant Development BA-FGA-211126-CS-CDS - Component A - Real Estate A.2.2.1A.39 / Temporary IBRD / 90480 Registration Data Post Direct Selection Direct 12,525.63 Signed 2020-12-21 2020-12-23 2020-12-23 2020-12-22 2021-01-01 2021-01-01 2021-12-31 Land Registry Assistant Development BA-FGA-211127-CS-CDS- Component A - Real Estate A.2.2.1A.40 / Temporary IBRD / 90480 Registration Data Post Direct Selection Direct 5,010.25 Signed 2020-12-21 2020-12-23 2020-12-23 2020-12-22 2021-01-01 2021-01-01 2021-12-31 Land Registry Assistant Development BA-FGA-211132-CS-CDS - Component A - Real Estate A.2.2.1A.42 / Temporary IBRD / 90480 Registration Data Post Direct Selection Direct 9,412.63 Signed 2020-12-21 2020-12-23 2020-12-23 2020-12-22 2021-01-01 2021-01-01 2021-12-31 Land Registry Assistant Development BA-FGA-211133-CS-CDS - Component A - Real Estate A.2.2.1A.43 / Temporary IBRD / 90480 Registration Data Post Direct Selection Direct 9,394.22 Signed 2020-12-21 2020-12-23 2020-12-23 2020-12-22 2021-01-01 2021-01-01 2021-12-31 Land Registry Assistant Development BA-FGA-211135-CS-CDS- Component A - Real Estate A.2.2.1A.44 / Temporary IBRD / 90480 Registration Data Post Direct Selection Direct 9,394.22 Signed 2020-12-21 2020-12-23 2020-12-23 2020-12-22 2021-01-01 2021-01-01 2021-12-31 Land Registry Assistant Development BA-FGA-211137-CS-CDS - Component A - Real Estate A.2.2.1A.45 / Temporary IBRD / 90480 Registration Data Post Direct Selection Direct 9,394.22 Signed 2020-12-21 2020-12-23 2020-12-23 2020-12-22 2021-01-01 2021-01-01 2021-12-31 Land Registry Assistant Development BA-FGA-211139-CS-CDS - Component A - Real Estate A.2.2.1A.46 / Temporary IBRD / 90480 Registration Data Post Direct Selection Direct 9,394.22 Terminated 2020-12-21 2020-12-23 2020-12-23 2020-12-22 2021-01-01 2021-01-01 2021-12-31 Land Registry Assistant Development BA-FGA-211140-CS-CDS - Component A - Real Estate A.2.2.1A.47 / Temporary IBRD / 90480 Registration Data Post Direct Selection Direct 9,394.22 Signed 2020-12-21 2020-12-23 2020-12-23 2020-12-22 2021-01-01 2021-01-01 2021-12-31 Land Registry Assistant Development BA-FGA-211141-CS-CDS - Component A - Real Estate A.2.2.1A.48 / Temporary IBRD / 90480 Registration Data Post Direct Selection Direct 9,394.22 Signed 2020-12-21 2020-12-23 2020-12-23 2020-12-22 2021-01-01 2021-01-01 2021-12-31 Land Registry Assistant Development BA-FGA-211143-CS-CDS - Component A - Real Estate A.2.2.1A.49 / Temporary IBRD / 90480 Registration Data Post Direct Selection Direct 7,515.38 Signed 2020-12-21 2020-12-23 2020-12-23 2020-12-22 2021-01-01 2021-01-01 2021-12-31 Land Registry Assistant Development BA-FGA-211144-CS-CDS - Component A - Real Estate A.2.2.1A.50 / Temporary IBRD / 90480 Registration Data Post Direct Selection Direct 6,262.81 Signed 2020-12-21 2020-12-23 2020-12-23 2020-12-22 2021-01-01 2021-01-01 2021-07-31 Land Registry Assistant Development BA-FGA-211149-CS-CDS- Component A - Real Estate A.2.2.1A.51 / Temporary IBRD / 90480 Registration Data Post Direct Selection Direct 6,262.81 Signed 2020-12-21 2020-12-23 2020-12-23 2020-12-22 2021-01-01 2021-01-01 2021-07-31 Land Registry Assistant Development BA-FGA-211150-CS-CDS - Component A - Real Estate A.2.2.1A.52 / Temporary IBRD / 90480 Registration Data Post Direct Selection Direct 9,394.22 Signed 2020-12-21 2020-12-23 2020-12-23 2020-12-22 2021-01-01 2021-01-01 2021-12-31 Land Registry Assistant Development BA-FGA-211153-CS-CDS - Component A - Real Estate A.2.2.1A.53 / Temporary IBRD / 90480 Registration Data Post Direct Selection Direct 9,394.22 Signed 2020-12-21 2020-12-23 2020-12-23 2020-12-22 2021-01-01 2021-01-01 2021-12-31 Land Registry Assistant Development BA-FGA-211154-CS-CDS - Component A - Real Estate A.2.2.1A.54 / Temporary IBRD / 90480 Registration Data Post Direct Selection Direct 6,262.81 Signed 2020-12-21 2020-12-23 2020-12-23 2020-12-22 2021-01-01 2021-01-01 2021-12-31 Land Registry Assistant Development BA-FGA-211155-CS-CDS - Component A - Real Estate A.2.2.1A.55 / Temporary IBRD / 90480 Registration Data Post Direct Selection Direct 6,262.81 Signed 2020-12-21 2020-12-23 2020-12-23 2020-12-22 2021-01-01 2021-01-01 2021-12-31 Land Registry Assistant Development BA-FGA-211157-CS-CDS- Component A - Real Estate A.2.2.1A.56 / Temporary IBRD / 90480 Registration Data Post Direct Selection Direct 12,525.63 Signed 2020-12-21 2020-12-23 2020-12-23 2020-12-22 2021-01-01 2021-01-01 2021-12-31 Land Registry Assistant Development BA-FGA-211159-CS-CDS- Component A - Real Estate A.2.2.1A.57 / Temporary IBRD / 90480 Registration Data Post Direct Selection Direct 3,131.41 Signed 2020-12-21 2020-12-23 2020-12-23 2020-12-22 2021-01-01 2021-01-01 2021-07-31 Land Registry Assistant Development BA-FGA-211161-CS-CDS- Component A - Real Estate A.2.2.1A.58 / Temporary IBRD / 90480 Registration Data Post Direct Selection Direct 3,131.41 Signed 2020-12-21 2020-12-23 2020-12-23 2020-12-22 2021-01-01 2021-01-01 2021-07-31 Land Registry Assistant Development BA-FGA-211162-CS-CDS - Component A - Real Estate A.2.2.1A.59 / Temporary IBRD / 90480 Registration Data Post Direct Selection Direct 3,131.41 Signed 2020-12-21 2020-12-23 2020-12-23 2020-12-22 2021-01-01 2021-01-01 2021-07-31 Land Registry Assistant Development Page 4 BA-FGA-211163-CS-CDS- Component A - Real Estate A.2.2.1A.60 / Temporary IBRD / 90480 Registration Data Post Direct Selection Direct 3,131.41 Signed 2020-12-21 2020-12-23 2020-12-23 2020-12-22 2021-01-01 2021-01-01 2021-07-31 Land Registry Assistant Development BA-FGA-211168-CS-CDS- Component A - Real Estate A.2.2.1A.61 / Temporary IBRD / 90480 Registration Data Post Direct Selection Direct 12,525.63 Terminated 2020-12-21 2020-12-23 2020-12-23 2020-12-22 2021-01-01 2021-01-01 2021-12-31 Land Registry Assistant Development BA-FGA-211169-CS-CDS- Component A - Real Estate A.2.2.1A.62 / Temporary IBRD / 90480 Registration Data Post Direct Selection Direct 12,469.90 Signed 2020-12-21 2020-12-23 2020-12-23 2020-12-22 2021-01-01 2021-01-01 2021-12-31 Land Registry Assistant Development BA-FGA-211170-CS-CDS- Component A - Real Estate A.2.2.1A.63 / Temporary IBRD / 90480 Registration Data Post Direct Selection Direct 4,987.96 Signed 2020-12-21 2020-12-23 2020-12-23 2020-12-22 2021-01-01 2021-01-01 2021-07-31 Land Registry Assistant Development BA-FGA-211171-CS-CDS - Component A - Real Estate A.2.2.1A.64 / Temporary IBRD / 90480 Registration Data Post Direct Selection Direct 5,010.25 Signed 2020-12-21 2020-12-23 2020-12-23 2020-12-22 2021-01-01 2021-01-01 2021-07-31 Land Registry Assistant Development BA-FGA-211172-CS-CDS- Component A - Real Estate A.2.2.1A.65 / Temporary IBRD / 90480 Registration Data Post Direct Selection Direct 3,131.41 Signed 2020-12-21 2020-12-23 2020-12-23 2020-12-22 2021-01-01 2021-01-01 2021-07-31 Land Registry Assistant Development BA-FGA-211174-CS-CDS- Component A - Real Estate A.2.2.1A.66 / Temporary IBRD / 90480 Registration Data Post Direct Selection Direct 6,262.81 Signed 2020-12-21 2020-12-23 2020-12-23 2020-12-22 2021-01-01 2021-01-01 2021-12-31 Land Registry Assistant Development BA-FGA-211176-CS-CDS- Component A - Real Estate A.2.2.1A.67 / Temporary IBRD / 90480 Registration Data Post Direct Selection Direct 6,262.81 Signed 2020-12-21 2020-12-23 2020-12-23 2020-12-22 2021-01-01 2021-01-01 2021-12-31 Land Registry Assistant Development BA-FGA-211178-CS-CDS- Component A - Real Estate A.2.2.1A.68 / Temporary IBRD / 90480 Registration Data Post Direct Selection Direct 6,262.81 Signed 2020-12-21 2020-12-23 2020-12-23 2020-12-22 2021-01-01 2021-01-01 2021-12-31 Land Registry Assistant Development BA-FGA-211180-CS-CDS- Component A - Real Estate A.2.2.1A.69 / Temporary IBRD / 90480 Registration Data Post Direct Selection Direct 6,262.81 Signed 2020-12-21 2020-12-23 2020-12-23 2020-12-22 2021-01-01 2021-01-01 2021-12-31 Land Registry Assistant Development BA-FGA-211181-CS-CDS- Component A - Real Estate A.2.2.1A.70 / Temporary IBRD / 90480 Registration Data Post Direct Selection Direct 6,262.81 Terminated 2020-12-21 2020-12-23 2020-12-23 2020-12-22 2021-01-01 2021-01-01 2021-12-31 Land Registry Assistant Development BA-FGA-211559-CS-CDS- Component A - Real Estate A.2.2.2.4A.8 / Individual IBRD / 90480 Registration Data Post Direct Selection Direct 6,275.09 Signed 2020-12-24 2020-12-29 2020-12-28 2020-12-22 2021-01-01 2021-01-01 2021-07-31 consultant for delivery of Development decisions on registration BA-FGA-211560-CS-CDS- Component A - Real Estate A.2.2.2.4A.9 / Individual IBRD / 90480 Registration Data Post Direct Selection Direct 6,275.09 Signed 2020-12-24 2020-12-29 2020-12-28 2020-12-22 2021-01-01 2021-01-01 2021-07-31 consultant for delivery of Development decisions on registration BA-FGA-211875-CS-CDS- Component A - Real Estate A.2.2.2.4A.10 / Individual IBRD / 90480 Registration Data Post Direct Selection Direct 9,412.63 Signed 2020-12-29 2020-12-29 2020-12-30 2020-12-22 2021-01-01 2021-01-01 2021-12-31 consultant for delivery of Development decisions on registrations BA-FGA-212460-CS-INDV- Component B - Real Estate Individual B.1.1.1 / Architect required IBRD / 90480 Registration Infrastructure Post Consultant Limited 21,721.21 Signed 2021-01-06 2021-01-01 2021-01-18 2021-01-28 2021-02-01 2021-02-15 2021-02-18 2021-03-01 2022-07-31 for civil works Development Selection Component A - Real Estate Individual BA-FGA-212495-CS-INDV- IBRD / 90480 Registration Data Post Consultant Limited 27,403.84 Signed 2021-01-06 2021-02-08 2021-01-28 2021-02-25 2021-02-12 2021-03-19 2021-04-01 2021-04-01 2022-07-31 A.1.1.1B / Social Specialist Development Selection BA-FGA-212518-CS-INDV- B.2.2.4 / Feasibility study of Component B - Real Estate Individual new system and software IBRD / 90480 Registration Infrastructure Post Consultant Limited 0.00 Canceled 2021-01-06 2021-02-01 2021-02-21 2021-04-01 2021-09-28 architectures with tehnical Development Selection specifications in accordance with the ICT Strategy BA-FGA-212519-CS-INDV- Component B - Real Estate Individual B.2.2.7 / Cyber security policy IBRD / 90480 Registration Infrastructure Post Consultant Limited 0.00 Canceled 2021-01-07 2021-03-04 2021-03-24 2021-05-03 2021-08-01 and action plan Development Selection BA-FGA-212520-CS-INDV- Component C - Policy and Individual C.3.2.3.1B / Interpreter - IBRD / 90480 institutional development, Post Consultant Limited 6,344.84 Signed 2021-01-07 2021-01-01 2021-01-28 2021-02-25 2021-02-12 2021-03-30 2021-04-01 2021-04-01 2022-07-31 Phase 1 and project management Selection BA-FGA-211131-CS-CDS - Component A - Real Estate A.2.2.1A.41 / Temporary IBRD / 90480 Registration Data Post Direct Selection Direct 0.00 Canceled 2020-12-21 2020-12-23 2020-12-23 2020-12-30 2021-01-01 2021-12-31 Land Registry Assistant Development BA-FGA-210788-CS-CDS - Component A - Real Estate A.2.2.1A.20 / Temporary IBRD / 90480 Registration Data Post Direct Selection Direct 0.00 Canceled 2020-12-18 2020-12-23 2020-12-22 2020-12-30 2021-01-01 2021-07-31 Land Registry Assistant Development BA-FGA-210782-CS-CDS- Component A - Real Estate A.2.2.1A.17 / Temporary IBRD / 90480 Registration Data Post Direct Selection Direct 0.00 Canceled 2020-12-18 2020-12-23 2020-12-22 2020-12-30 2021-01-01 2021-12-31 Land Registry Assistant Development BA-FGA-218523-CS-INDV- A.4.1.1 / Project managers for Component A - Real Estate Individual Harmonization data on IBRD / 90480 Registration Data Post Consultant Open 70,846.41 Signed 2021-02-11 2021-02-24 2021-03-14 2021-04-12 2021-03-17 2021-04-21 2021-04-21 2021-04-21 2021-11-17 cadastre and land book - Development Selection Phase 1 BA-FGA-212498-CS-INDV- A.4.1.1 / Project managers for Component A - Real Estate Individual Harmonization data on IBRD / 90480 Registration Data Post Consultant Limited 0.00 Canceled 2021-01-06 2021-01-05 2021-02-05 2021-02-20 2021-03-28 2021-10-24 cadastre and land book - Development Selection Phase 1 Page 5 BA-FGA-218764-CS-INDV- A.2.2.1B / Updating Component A - Real Estate Individual (establishment and/or IBRD / 90480 Registration Data Post Consultant Open 82,921.40 Signed 2021-02-12 2021-04-22 2021-03-15 2021-04-15 2021-03-18 2021-04-22 2021-04-01 2021-05-20 2021-12-31 renewal) of land register data Development Selection - Temp LR Assistants BA-FGA-219067-CS-INDV- Component B - Real Estate Individual B.2.1.2 / Technical Assistance IBRD / 90480 Registration Infrastructure Post Consultant Limited 22,570.02 Signed 2021-02-11 2021-02-24 2021-02-17 2021-02-25 2021-03-04 2021-03-30 2021-04-01 2021-04-01 2022-07-31 for QA/QC, ICT Strategy Development Selection update, others BA-FGA-219075-CS-INDV- Component B - Real Estate Individual B.3.1 / Scanning, data entry IBRD / 90480 Registration Infrastructure Post Consultant Limited 52,431.54 Signed 2021-02-11 2021-04-22 2021-02-24 2021-03-24 2021-03-15 2021-05-14 2021-05-01 2021-05-20 2021-12-31 and indexing of LB arhives Development Selection documentation BA-FGA-219077-CS-INDV- Component A - Real Estate Individual A.4.2 / Quality Control - IBRD / 90480 Registration Data Post Consultant Limited 22,570.02 Signed 2021-02-11 2021-02-19 2021-02-19 2021-02-25 2021-03-06 2021-03-30 2021-04-01 2021-04-01 2022-07-31 RECDB Development Selection BA-FGA-219088-CS-INDV- Component C - Policy and Individual Under C.3.2.1B.2 / Monitoring and IBRD / 90480 institutional development, Post Consultant Limited 0.00 2021-02-11 2021-03-09 2021-03-01 2021-03-16 2021-04-01 2022-07-31 Implementation Evaluation Specialist and project management Selection BA-FGA-219100-CS-INDV- Component C - Policy and Individual Pending C.3.2.1B.5 / Finance IBRD / 90480 institutional development, Post Consultant Limited 0.00 2021-02-11 2021-02-28 2021-03-15 2021-04-01 2022-07-31 Implementation consultant and project management Selection BA-FGA-219308-CS-INDV- Component A - Real Estate Individual A.2.2.2.4B / Delivery cost of IBRD / 90480 Registration Data Post Consultant Limited 14,737.47 Signed 2021-02-12 2021-03-09 2021-02-19 2021-03-10 2021-03-06 2021-04-12 2021-04-01 2021-04-15 2021-12-31 Decisions on registrations Development Selection Component C - Policy and Individual BA-FGA-219315-CS-INDV- IBRD / 90480 institutional development, Post Consultant Limited 50,989.22 Signed 2021-02-15 2021-03-09 2021-02-28 2021-03-11 2021-03-15 2021-03-30 2021-04-01 2021-04-01 2022-07-31 C.3.2.1B.1 / Team Leader and project management Selection BA-FGA-212511-CS-INDV- Component B - Real Estate Individual B.2.1.1B / Technical ICT IBRD / 90480 Registration Infrastructure Post Consultant Limited 0.00 Canceled 2021-01-06 2021-01-01 2021-01-28 2021-02-12 2021-04-01 2022-07-31 Assistance for project Development Selection activities BA-FGA-224273-CS-INDV- Component B - Real Estate Individual Under B.2.2.7 / Cyber security policy IBRD / 90480 Registration Infrastructure Post Consultant Open 0.00 2021-03-11 2021-04-05 2021-04-02 2021-04-06 2021-05-03 2021-08-01 Implementation and action plan Development Selection BA-FGA-224275-CS-INDV- B.2.2.4 / Feasibility study of Component B - Real Estate Individual new system and software Under IBRD / 90480 Registration Infrastructure Post Consultant Open 0.00 2021-03-11 2021-04-05 2021-03-28 2021-05-26 2021-03-28 2021-04-01 2021-09-28 architectures with tehnical Implementation Development Selection specifications in accordance with the ICT Strategy BA-FGA-227676-CS-INDV- Component C - Policy and Individual C.3.2.2.5 / Project Controls IBRD / 90480 institutional development, Post Consultant Limited 25,877.56 Signed 2021-04-01 2021-04-06 2021-04-01 2021-04-09 2021-04-16 2021-04-12 2021-04-17 2021-04-19 2022-07-31 and QAQC and project management Selection BA-FGA-233043-CS-INDV- Component A - Real Estate Individual A.2.2.2.4B.VIS1 / Delivery cost IBRD / 90480 Registration Data Post Consultant Limited 3,718.42 Signed 2021-05-04 2021-05-05 2021-05-11 2021-04-30 2021-05-13 2021-05-17 2021-05-20 2021-06-01 2021-12-31 of Decisions on registrations Development Selection - A.2.2.2.4B.VIS1 BA-FGA-235303-CS-INDV- A.2.2.1B / Updating Component A - Real Estate Individual Under (establishment and/or IBRD / 90480 Registration Data Post Consultant Open 0.00 2021-05-20 2021-05-21 2021-07-13 2021-07-15 2021-08-01 2022-07-31 Implementation renewal) of land register data Development Selection - Temp LR Assistants Component A - Real Estate Individual BA-FGA-236315-CS-INDV- IBRD / 90480 Registration Data Post Consultant Limited 24,265.45 Signed 2021-05-25 2021-05-27 2021-05-28 2021-06-01 2021-06-11 2021-06-10 2021-06-15 2021-06-14 2022-07-31 A.1.1.1C / Social Specialist Development Selection Page 6 Jhelum & Tawi Flood Recovery Project (Project ID: P154990) Procurement Summary I. General 1. Project Information: Project Name: Jhelum & Tawi Flood Recovery Project Country: India Project Code: P154990 2. Bank’s approval Date of the procurement Plan: Draft Procurement Plan dated April 24, 2015 Revision 0: Agreed by the Bank on April 25, 2015 Revision 1: March 30, 217 Revision 2: Feb 15 2019 3. Date of General Procurement Notice: September 01 2015 4. Period covered by this procurement plan: next 18 months II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Methods and Threshold Category Method of Threshold (US$ Equivalent) Procurement Goods and Non- ICB >3,000,000 consultant LIB Wherever agreed by the services Bank NCB Up to 3,000,000 (with NCB conditions) Shopping Up to 500,000 DC As per Para 3.7 of the Bank Guidelines, wherever agreed and with prior agreement with the Bank Force Account As per Para 3.9 of Guidelines Framework As per Para 3.6 of Agreements Guidelines Works and Supply ICB >40,000,000 and Installation NCB Up to 40,000,000 (with NCB conditions) Shopping Up to 1,000,000 carried out through a qualified local contractor selected through shopping (after inviting a minimum of three quotations in response to a written invitation with a minimum of 15 days’ notice period) Force Account As per Para 3.9 of Guidelines DC As per Para 3.7 of Guidelines,  Prior Review by the Bank. The Bank will prior review the following contracts: • Works: All contracts more than US$ 10.0 million equivalent; • Goods: All contracts more than US$ 2.0 million equivalent; • Information Technology: All contracts more than US$ 2.0 million equivalent; and • Non-Consulting Services: All contracts more than US$ 2.0 million equivalent  The PMU shall prior review the first contract issued by each implementing agency, if the estimate of those contracts are below the prior review threshold value. The Bank will conduct prior review for only those contract whose estimate falls in prior review threshold value. In addition, the justifications for all contracts to be issued on LIB, single-source (>US$ 30,000) or direct contracting (>US$ 30,000) basis will be subject to Banks prior review. These thresholds are for the initial 18 months period and are based on the procurement performance of the project, these thresholds will be modified. In addition, the Bank will carry out an annual ex post procurement review of the procurement falling below the prior review threshold mentioned above.  All contracts below the specified prior review threshold value shall be subject to Post Procurement Review (PPR). The IA shall prepare a list of contract and submit it to the Bank for conducting PPR. The PPR will be conducted on annual basis. 2. Pre-qualification. Not applicable 3. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan Project issued by Project Management Unit JTFRP, J&K, India All the contracts issued under the project will follow the World Bank’s Guidelines: Bank’s “Guidelines: Procurement under IBRD Loans and IDA Credits” dated January 2011and revised in July 2014and “Guidelines: Selection and Employment of Consultants by World Bank Borrowers” dated January 2011 and revised in July 2014, In case of any inconsistency between the Procurement Manual or Government Procurement Procedures and the Bank Guidelines, the latter shall prevail. 4. Any Other Special Procurement Arrangements: The bid evaluation will be carried out as per agreed timeline in the Procurement Manual.  National Competitive Bidding (NCB): Any contract exceeding shopping threshold shall be procured using NCB method. The model bidding documents for NCB as agreed with the GoI Task Force (and as amended from time to time), shall be used for bidding. The following NCB provisions shall apply: i. Only the model bidding documents for NCB as agreed with the GoI Task Force (and as amended from time to time), shall be used for bidding. ii. Invitation to bid shall be advertised in at least one widely circulated national daily newspaper (or on a widely used website or electronic portal with free national and international access along with an abridged version of the said advertisement published in a widely circulated national daily inter-alia giving the website/electronic portal details from which the details of the invitation to bid can be downloaded), at least 30 days prior to the deadline for the submission of bids. For smaller packages (lesser than US$1 million for Works and US$ 500,000 for Goods), advertisement in state newspapers will be accepted with at least 15 days given for submission of bids; iii. No special preference will be accorded to any bidder either for price or for other terms and conditions when competing with foreign bidders, state-owned enterprises, small-scale enterprises or enterprise from any given State; iv. Except with the prior concurrence of the Bank, there shall be no negotiation of price with the bidders, even with the lowest evaluated bidder; v. At the Borrower's request, the Bank may agree to the Borrower's use, in whole or in part, of its electronic procurement system, provided that the Bank is satisfied with the adequacy of such system. vi. For prior review contracts, extension of bid validity shall not be allowed with reference to Contracts subject to Bank prior review without the prior concurrence of the Bank (i) for the first request for extension if it is longer than four weeks; and (ii) for all subsequent requests for extension irrespective of the period (such concurrence will be considered by Bank only in cases of Force Majeure and circumstance beyond the control of the Purchaser/Employer); vii. For prior review contracts , re-bidding shall not be carried out with reference to Contracts subject to Bank prior review without the prior concurrence of the Bank; viii. The system of rejecting bids outside a pre-determined margin or “bracket” of prices shall not be used in the project; ix. Government e-Marketplace (GeM)1 set-up by Ministry of Commerce, Government of India will be acceptable for procurement under Request for Quotations (RFQ) method. x. The Borrower shall use an effective complaints mechanism for handling procurement related complaints in a timely manner. xi. Two or three envelop system will not be used (expect when suing e-procurement system assessed and agreed by the Bank. xii. Procurement Documents will include provisions, as agreed with the Bank, intended to adequately mitigate against environmental, social (including sexual exploitation and abuse and gender-based violence), health and safety ("ESHS") risks and impacts.  Force Account: When contractors/suppliers are unlikely to bid at reasonable prices because of the location and risk associated with the project or a certain government agency has exclusive rights in certain type of works/supply, borrowers may use their own government departments’ personnel and equipment or government owned construction unit may be the only practical method, provided that the borrower has sufficient managerial capacity and possesses the required technical and financial controls to report to the Bank on expenditure as per paragraph 3.9 of the Procurement Guidelines.  Framework Agreements: State level rate contracts will be examined by the Bank and if agreed, may also be used as framework agreements. Implementing agencies also have option to set-up new framework agreements as per paragraph 3.6 of Guidelines.  Use of government Institutions and Enterprise: Government owned enterprise or institutions in India may be hired for its unique and exceptional nature if their participation is considered critical to the project implementation. In such cases, the conditions given in clauses 1.13 of Consultant Guidelines shall be satisfied and each case will be subject to prior review by the Bank. The works contracts up to cumulative amount of 37.5 million USD, would be directly executed by the J&K Projects Construction 1 Use of GeM will be allowed in lieu of RFQ as per following details: • up to INR 50,000 in catalogue mode (viz. any available item could be selected by IA without further competition), provided selected Item/Supplier meeting the requisite quality, specification and delivery period. • up to INR 3 Million from the Supplier having lowest price amongst at least three Suppliers meeting the requisite quality, specification and delivery period. The tools for online bidding and online reverse auction available on GeM may be used by the Purchaser. • up to INR equivalent of US$ 500,000 from the Supplier having lowest price and meeting the requisite quality, specification and delivery period after mandatorily obtaining bids from at least three Suppliers, using online bidding or reverse auction tool provided on GeM. Corporation Ltd., which a Public Sector Undertaking. J&K Projects Construction Corporation Ltd. is executing projects of State as well as Central Government departments. 5. Summary of the Procurement Packages planned during the first 18 months and thereafter: Available on STEP III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Category Method of Procurement Threshold (US$ Equivalent) Consultants’ CQS Up to 500,000 Services SSS Up to 200,000 As per para 3.9-3.11 of Guidelines Individuals As per Section V of Guidelines QCBS/QBS/FBS/LCS for all other cases (i) International >800,000 shortlist (ii) Shortlist may Up to 800,000 comprise national consultants only  Prior Review by the Bank. The Bank will prior review the following contracts: o Consulting Services: All contracts more than US$ 1.0 million equivalent for firm; and o Consulting Services: All contracts more than US$ 300,000 equivalent for Individuals. 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $ 800,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Consultancy Assignments with Selection Methods and Time Schedule: Available on STEP Use of e-procurement portal Procurement of goods works and non-consultancy services shall be conducted using the e-procurement portal www.jktenders.gov.in. All IAs shall use this e-procurement portal for procurement of goods works and non-consulting services. PROCUREMENT India : Jhelum and Tawi Flood Recovery Project PLAN General Information Country: India Bank’s Approval Date of the Original Procurement Plan: 2016-12-22 2021-05-24 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P154990 GPN Date: 2016-11-18 Project Name: Jhelum and Tawi Flood Recovery Project Loan / Credit No: IDA / 56950 I Executing Agency(ies): ndustry & Commerce Department (I&CD), J&K WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned JTFRP/JK/IC/JKI/B/W001/16 / Construction/Repairs of factory Building at Bemina Woolen Mills Sgr. under Restoration and Single Stage - Two 2018-11- Project JTRF for restoration IDA / 56950 Post Request for Bids Open - National 732,230.00 218,451.40 Signed 2017-01-30 2017-08-18 2017-02-06 2017-03-08 2017-10-25 2017-04-14 2018-02-16 2017-05-19 2018-03-01 strengthening of livelihoods Envelope 18 and strengthening of livelihood for Composite Market Centre for Whole Chain of Wool Activity . JTFRP/JK/IC/JKI/R/W002/16 / Construction of factory building under JTFR Project for Restoration and Restoration and Single Stage - Two 1,735,510.0 2018-12- Strengthening of Livelihood IDA / 56950 Post Request for Bids Open - National 2,937,100.00 Signed 2017-01-30 2017-08-01 2017-02-06 2017-08-11 2017-03-08 2017-12-13 2017-04-14 2018-02-16 2017-05-22 2018-03-01 strengthening of livelihoods Envelope 0 21 for Composite Market Centre for Whole chain of Silk Activity at Silk Factory Rajbagh Srinagar. JTFRRP/JK/IC/CDI/CSPEP/W00 1/16 / Construction of PG Restoration and Single Stage - Two 2018-12- building at Craft Development IDA / 56950 Post Request for Bids Open - National 400,000.00 0.00 Canceled 2017-01-30 2017-02-04 2017-03-06 2017-04-20 2017-06-01 strengthening of livelihoods Envelope 01 Institute Srinagar under JTFRP . JTFRP/JK/IC/BWM/W003/19 / Interior works for showroom Restoration and Single Stage - Two 2019-12- cum interpretation centre for IDA / 56950 Post Request for Bids Open - National 338,500.00 312,919.37 Signed 2019-01-25 2019-04-13 2019-01-30 2019-04-29 2019-03-13 2019-06-21 2019-05-26 2019-10-07 2019-06-30 2019-11-29 strengthening of livelihoods Envelope 27 Government Woollen Mills Bemina Srinagar J&K GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual JTFRP/JK/IC/CDI/CSPEP/G001 /16 / Procurement of Digital and IT Equipment's , net working soft ware for upcoming post Graduate Restoration and Single Stage - One program in craft Design and IDA / 56950 Post Request for Bids Open - National 100,000.00 0.00 Canceled 2018-03-13 2018-03-18 2018-04-17 2018-06-01 2018-07-06 2018-10-04 strengthening of livelihoods Envelope sustainable development in creative industries being launched by CDI.Sgr under JTFRP for restoration strengthening of livelihoods. JTFRP/JK/IC/CDI/CSPEP/G003 /16 / Procurement for Printing of Brochures and other publicity materials for upcoming post graduate Restoration and Single Stage - One IDA / 56950 Post Request for Bids Open - National 8,000.00 0.00 Canceled 2018-01-09 2018-01-14 2018-02-13 2018-03-06 2018-04-13 2018-06-12 Programs in craft design and strengthening of livelihoods Envelope sustainable development in creative industries to be launched by CDI Sgr. under JTFRP . JTFRP/JK/IC/JKI/R/G001/16 / Procurement of machines under Jhelum and Tawi flood recovery project for restoration and Restoration and Single Stage - Two IDA / 56950 Post Request for Bids Open - National 651,098.00 0.00 Canceled 2018-02-25 2018-03-07 2018-04-10 2018-05-18 2018-06-05 2018-12-05 strengthening of livelihood strengthening of livelihoods Envelope composite market centre for whole chain of silk activity in Govt. Silk Factory Rajbagh Srinagar. JTFRP/JK/IC/JKI/B/G002/16 / Procurement of machines under Jehlum and Tawi Flood recovery project for restoration and strengthening Restoration and Single Stage - Two IDA / 56950 Post Request for Bids Open - National 1,074,124.00 0.00 Canceled 2018-02-26 2018-03-10 2018-04-14 2018-05-20 2018-06-10 2018-12-15 of livelihoods composite strengthening of livelihoods Envelope market centre for whole chain of wool activity in Govt. Wool Mills at Bemina Srinagar. JTFRP/JK/IC/BWM/G001/18 / Supply installation testing and Restoration and Single Stage - Two commissioning of various IDA / 56950 Post Request for Bids Open - National 338,460.00 0.00 Canceled 2018-09-28 2018-10-05 2018-10-03 2018-10-16 2018-11-14 2018-11-24 2019-01-27 2019-03-03 2019-08-30 strengthening of livelihoods Envelope textile machinery for Govt. Woolen mills Bemina JTFRP/JK/IC/BWM/G002/18 / Supply installation testing and Restoration and Single Stage - Two commissioning of cone IDA / 56950 Post Request for Bids Open - National 55,385.00 0.00 Canceled 2018-09-28 2018-10-06 2018-10-03 2018-10-16 2018-11-14 2018-11-24 2019-01-27 2019-03-03 2019-08-30 strengthening of livelihoods Envelope winders for Govt Woollen Mills Bemina Page 1 JTFRP/JK/IC/BWM/G003/18 / Supply Installation Testing Restoration and Single Stage - Two and Commissioning of Pirn IDA / 56950 Post Request for Bids Open - National 16,155.00 0.00 Canceled 2018-09-28 2018-10-09 2018-10-03 2018-10-16 2018-11-14 2018-11-26 2019-01-27 2019-03-03 2019-08-30 strengthening of livelihoods Envelope winder for Govt Woollen Mills Bemina JTFRP/JK/IC/BWM/G004/18 / Supply Installation Testing Restoration and Single Stage - Two and Commissioning of Rapier IDA / 56950 Post Request for Bids Open - National 246,150.00 0.00 Canceled 2018-10-02 2018-10-09 2018-10-07 2018-10-16 2018-11-18 2018-11-26 2019-01-31 2019-03-07 2019-09-03 strengthening of livelihoods Envelope Looms for Government Woollen Mills Bemina JTFRP/JK/IC/BWM/G005/18 / Supply Installation Testing and Commissioning of roller Restoration and Single Stage - Two IDA / 56950 Post Request for Bids Open - National 30,770.00 0.00 Canceled 2018-10-03 2018-10-09 2018-10-08 2018-10-16 2018-11-19 2018-11-27 2019-02-01 2019-03-08 2019-09-04 calendaring machine for strengthening of livelihoods Envelope Government Woollen Mills Bemina. JTFRP/JK/IC/BWM/G006/18 / Supply Installation Testing and Commissioning of dyeing Restoration and Single Stage - Two IDA / 56950 Post Request for Bids Open - National 170,000.00 0.00 Canceled 2018-10-08 2018-10-09 2018-10-13 2018-10-16 2018-11-24 2018-11-27 2019-02-06 2019-03-13 2019-09-09 and related machinery for strengthening of livelihoods Envelope Government Woollen Mills Bemina JTFRP/JK/IC/BWM/G007/18 / Supply Installation Testing Restoration and Single Stage - Two and Commissioning of Boilers IDA / 56950 Post Request for Bids Open - National 138,460.00 0.00 Canceled 2018-10-08 2018-10-09 2018-10-13 2018-10-16 2018-11-24 2018-11-28 2019-02-06 2019-03-13 2019-09-09 strengthening of livelihoods Envelope for Government Woollen Mills Bemina JTFRP/JK/IC/BWM/G008/18 / Supply Installation Testing and Commissioning of Fabric Restoration and Single Stage - Two IDA / 56950 Post Request for Bids Open - National 23,000.00 0.00 Canceled 2018-10-08 2018-10-09 2018-10-13 2018-10-16 2018-11-24 2018-11-29 2019-02-06 2019-03-13 2019-09-09 Inspection machines at strengthening of livelihoods Envelope Government Woollen Mills Bemina JTFRP/JK/IC/BMW/G009/18 / Supply Installation Testing Restoration and Single Stage - Two and Commissioning of Twist IDA / 56950 Post Request for Bids Open - National 15,385.00 0.00 Canceled 2018-10-05 2018-10-09 2018-10-10 2018-10-16 2018-11-21 2018-11-29 2019-02-03 2019-03-10 2019-09-06 strengthening of livelihoods Envelope Setting Chamber Government Woollen Mills Bemina JTFRP/JK/IC/RSF/G001/18 / Supply Installation Testing Restoration and Single Stage - Two and Commissioning of rapier IDA / 56950 Post Request for Bids Open - National 653,900.00 0.00 Canceled 2018-10-24 2018-10-20 2018-10-29 2018-10-29 2018-12-10 2018-12-12 2019-02-22 2019-03-29 2019-09-25 strengthening of livelihoods Envelope Looms for Govt Silk Factory Rajbagh Srinagar J&K JTFRP/JK/IC/BWM/G014/19 / Supply Installation, Testing and Commissioning of Rapier Restoration and Single Stage - Two IDA / 56950 Post Request for Bids Open - National 133,000.00 347,936.00 Signed 2019-01-21 2019-01-18 2019-01-26 2019-01-23 2019-03-09 2019-03-12 2019-05-22 2019-11-11 2019-06-26 2020-02-10 2019-09-24 looms for Government strengthening of livelihoods Envelope Woollen Mills Bemina Srinagar J&K JTFRP/JK/IC/RSF/G011/19 / Supply Installation Testing & Under Restoration and Single Stage - Two commissioning of Rapier IDA / 56950 Post Request for Bids Open - National 625,000.00 0.00 Implementati 2019-01-21 2019-01-17 2019-01-26 2019-01-22 2019-03-09 2019-05-22 2019-06-26 2019-09-24 strengthening of livelihoods Envelope Looms for Government Silk on Factory Rajbagh, Srinagar J&K JTFRP/JK/IC/RSF/G002/19 / Supply Installation Testing and Commissioning of Two Restoration and Single Stage - Two IDA / 56950 Post Request for Bids Open - National 1,086,000.00 0.00 Canceled 2019-05-27 2019-05-27 2019-06-01 2019-06-11 2019-07-13 2019-09-25 2019-10-30 2020-04-27 for One Twisters for strengthening of livelihoods Envelope Government Silk Factory Rajbagh Srinagar, J&K JTFRP/JK/IC/RSF/G003/19 / Supply Installation Testing and Commissioning of Restoration and Single Stage - Two preparatory machinery for IDA / 56950 Post Request for Bids Open - National 121,500.00 0.00 Canceled 2019-06-14 2019-06-24 2019-06-19 2019-07-09 2019-07-31 2019-10-13 2019-11-17 2020-05-15 strengthening of livelihoods Envelope government silk factory rajbagh Srinagar Jammu and Kashmir JTFRP/JK/IC/RSF/G022/19 / Supply Installation Testing and Commissioning of Two Restoration and Single Stage - Two IDA / 56950 Post Request for Bids Open - National 634,500.00 622,940.85 Signed 2019-07-21 2019-09-09 2019-07-26 2020-02-29 2019-09-06 2019-11-09 2019-11-19 2019-12-24 2019-12-24 2020-02-14 2020-06-21 for One Twisters for strengthening of livelihoods Envelope Government Silk Factory Rajbagh Srinagar J&K JTFRP/JK/IC/BWM/G017/19 / Supply Installation Testing & Restoration and Single Stage - Two Commissioning of boilers for IDA / 56950 Post Request for Bids Open - National 133,000.00 0.00 Canceled 2019-01-21 2019-01-18 2019-01-26 2019-03-09 2019-05-22 2019-06-26 2019-09-24 strengthening of livelihoods Envelope Government Woollen Mills Bemina Srinagar J&k JTFRP/JK/IC/BWM/G011/19 / Supply Installation & Testing Restoration and Single Stage - Two of various textile machinery IDA / 56950 Post Request for Bids Open - National 338,460.00 0.00 Canceled 2019-01-21 2019-01-18 2019-01-26 2019-01-23 2019-03-09 2019-05-22 2019-06-26 2019-09-24 strengthening of livelihoods Envelope for Government Woollen Mills, Bemina, Srinagar J&K JTFRP/JK/IC/BWM/G016/19 / Supply Installation Testing & Commissioning of dyeing & Restoration and Single Stage - Two IDA / 56950 Post Request for Bids Open - National 162,500.00 0.00 Canceled 2019-01-21 2019-01-18 2019-01-26 2019-01-23 2019-03-09 2019-05-22 2019-06-26 2019-09-24 related machinery for strengthening of livelihoods Envelope Government Woollen Mills Bemina Srinagar J&K JTFRP/JK/IC/BWM/G017/19- 2 / Supply Installation Testing and Commisioning of Boilers Restoration and Single Stage - Two IDA / 56950 Post Request for Bids Open - National 193,000.00 0.00 Canceled 2020-03-10 2020-04-05 2020-03-15 2020-05-12 2020-04-26 2020-07-09 2020-08-13 2020-11-11 for Government Woolen Mills strengthening of livelihoods Envelope Bemina and Government Silk Factory Rajbagh Srinagar J&K Page 2 JTFRP/JK/IC/BWM/G016/19- 2 / Supply Installation Testing Under and Commissioning of dyeing Restoration and Single Stage - Two IDA / 56950 Post Request for Bids Open - National 162,500.00 0.00 Implementati 2020-03-10 2020-05-11 2020-03-15 2020-05-20 2020-04-26 2020-07-09 2020-08-13 2020-11-11 & related machinery for strengthening of livelihoods Envelope on Government Woollen Mills Bemina Srinagar J&K JTFRP/JK/IC/BWM/G011/19- 2 / Supply Installation Testing Under and Commissioning for Restoration and Single Stage - Two IDA / 56950 Post Request for Bids Open - National 338,460.00 0.00 Implementati 2020-03-10 2020-08-10 2020-03-15 2020-09-12 2020-04-26 2020-07-09 2020-08-13 2020-11-11 various textile machinery for strengthening of livelihoods Envelope on Government Woollen Mills Bemina Srinagar J&K JTFRP/JK/IC/RSF/G003/19-2 / Supply, Installation, Testing and Commissioning of Restoration and Single Stage - Two IDA / 56950 Post Request for Bids Open - National 104,300.00 61,849.02 Signed 2020-05-19 2020-05-22 2020-05-24 2020-05-26 2020-07-05 2020-06-26 2020-09-17 2020-07-25 2020-10-22 2020-08-10 2021-04-20 Preparatory Machinery for strengthening of livelihoods Envelope Government Silk Factory, Rajbagh, Srinagar, J&K. JTFRP/JK/IC/RSF/G021/20 / Supply Installation Testing Under Restoration and Single Stage - Two and Commissioning of rapier IDA / 56950 Post Request for Bids Open - National 385,700.00 0.00 Implementati 2020-07-21 2020-08-02 2020-07-26 2020-08-10 2020-09-06 2020-11-19 2020-12-24 2021-06-22 strengthening of livelihoods Envelope Looms for Govt Silk Factory on Rajbagh Srinagar J&K JTFRP/JK/IC/RSF/G043/20 / Supply Installation Testing Under and Commissioning of Restoration and Single Stage - Two IDA / 56950 Post Request for Bids Open - National 185,700.00 0.00 Implementati 2020-07-22 2020-08-02 2020-07-27 2020-08-10 2020-09-07 2020-11-20 2020-12-25 2021-06-23 Weaving and Finishing strengthening of livelihoods Envelope on Machinery for Government Silk Factory Rajbagh Srinagar J&K JTFRP/JK/IC/BWM/G001/20 / Supply of bought out items Under Restoration and for Interiors of new showroom IDA / 56950 Post Direct Selection Direct 35,700.00 0.00 Implementati 2020-10-16 2020-10-05 2020-10-21 2020-11-25 2021-05-24 strengthening of livelihoods cum interpretation centre at on Govt Woollen Mills Bemina JTFRP/JK/IC/BWM/G017/19- 2-2 / Supply Installation Testing and Commisioning of Restoration and IDA / 56950 Post Request for Bids 193,000.00 0.00 Canceled 2020-10-07 2020-12-24 2020-10-12 2021-01-05 2020-11-23 2021-02-05 2021-02-05 2021-03-12 2021-06-10 Boilers for Government strengthening of livelihoods Woollens Mills Bemina and Government Silk Factory Rajbagh JTFRP/JK/IC/BWM/G001/21 / Supply, Installation, Testing & Commissioning of Boilers for Under Restoration and Single Stage - Two Government Silk Factory, IDA / 56950 Post Request for Bids Open - National 235,700.00 0.00 Implementati 2021-05-12 2021-05-19 2021-05-17 2021-05-25 2021-06-06 2021-07-30 2021-09-03 2021-12-02 strengthening of livelihoods Envelope Rajbagh and Government on Woollen Mills, Bemina, Srinagar, J&K NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual JTFRP/JK/IC/CDI/CSPEP/C003 /16 / Providing of consultancy services towards design of publicity and promotion material for Restoration and Least Cost IDA / 56950 Post Open - National 3,071.00 0.00 Canceled 2017-06-28 2017-07-12 2017-08-11 2017-09-10 2017-09-25 2017-10-17 2017-11-21 2017-12-21 launching of Post Graduate strengthening of livelihoods Selection Program in Craft Design and sustainable development in creative industriesby CDI Sgr under JTFRP . JTRF/JK/IC/HD/C002/16 / Consultancy for census of Restoration and Quality And Cost- Craft practitioners in J&K and IDA / 56950 Post Open - National 307,700.00 368,747.71 Signed 2017-01-25 2017-01-22 2017-02-08 2017-04-05 2017-03-10 2017-08-20 2017-04-16 2018-08-20 2017-05-01 2018-10-20 2017-05-23 2019-03-14 2017-06-27 2019-05-30 2018-06-27 strengthening of livelihoods Based Selection to develop a complete Artisans database. JTFRP/JK/IC/HD/C001/16 / Consultancy for feasibility of Reconstruction of roads and Quality And Cost- IDA / 56950 Post Open - National 15,400.00 0.00 Canceled 2017-01-28 2017-01-19 2017-02-12 2017-04-05 2017-03-19 2017-04-18 2017-05-03 2017-05-25 2017-06-29 2017-08-28 site & working Model for bridges Based Selection Kashmir Haat. JTFRP/JK/IC/HD/C003/17 / Develop E Commerce Strategy and Actionable Business Plan, Restoration and Quality And Cost- Design Build And Maintain E IDA / 56950 Post Open - National 230,800.00 0.00 Canceled 2017-03-15 2017-03-13 2017-04-05 2017-04-05 2017-05-19 2017-06-16 2017-07-01 2017-08-05 2017-09-09 2021-03-12 strengthening of livelihoods Based Selection Commerce Portal and Manage E Commerce Operations under JTFRP. JTFRP/JK/IC/HD/C006/17 / Develop E Commerce Strategy and Actionable Business Plan, Restoration and Quality And Cost- Design Build And Maintain E IDA / 56950 Post Open - National 230,800.00 0.00 Canceled 2017-08-10 2017-09-26 2017-08-31 2017-10-20 2017-10-14 2017-11-11 2017-12-11 2018-01-15 2018-02-19 2020-06-01 strengthening of livelihoods Based Selection Commerce Portal and Manage E Commerce Operations under JTFRP JTFRP/JK/IC/HD/R/C001/18 / Consultancy for feasibility of site and working model for Restoration and Quality And Cost- IDA / 56950 Post Open - National 80,000.00 0.00 Canceled 2018-03-25 2018-04-19 2018-04-15 2018-05-29 2018-06-26 2018-07-26 2018-08-30 2018-10-04 2019-01-02 Kashmir Haat and strengthening of livelihoods Based Selection International Trade Centre at Pampore Page 3 JTFRP/JK/IC/HD/ECOM/C002/ 18 / Develop e-Commerce Strategy and Actionable Restoration and Quality And Cost- Business PlanDesign, Build, IDA / 56950 Post Open - National 230,800.00 0.00 Canceled 2018-04-27 2018-08-06 2018-05-07 2018-06-13 2018-07-11 2018-07-26 2018-08-30 2018-10-04 2022-04-06 strengthening of livelihoods Based Selection Maintain and Manage e- Commerce Operations under JTFRP JTFRP/JK/IC/JKI/UCCN/C002/ 18 / Consultancy Services For preparation of dossier for Restoration and Quality And Cost- IDA / 56950 Post Open - National 115,400.00 64,016.52 Signed 2018-08-05 2018-08-06 2018-08-26 2018-10-09 2018-10-01 2018-11-06 2018-12-11 2018-12-06 2019-03-20 2019-01-10 2019-04-10 2019-02-14 2019-04-23 2020-02-14 inclusion of Srinagar city On strengthening of livelihoods Based Selection UNESCO Creative Cities Network JTFRP/JK/IC/HD/WW/C005/18 / Consultancy services to carry out end to end cluster Restoration and Quality And Cost- IDA / 56950 Post Open - National 384,615.00 0.00 Canceled 2018-09-28 2018-10-15 2018-10-03 2018-11-10 2018-11-16 2018-12-14 2019-01-13 2019-02-17 2019-03-24 2020-03-23 development activities in strengthening of livelihoods Based Selection willow wicker cluster at Ganderbal JTFRP/JK/IC/HDD/WB/C007/1 8 / Consultancy services to undertake Cluster Restoration and Quality And Cost- IDA / 56950 Post Open - National 384,615.00 0.00 Canceled 2018-10-18 2018-10-20 2018-11-08 2018-11-10 2018-12-22 2019-01-19 2019-02-18 2019-03-25 2019-04-29 2022-04-04 Development activities in strengthening of livelihoods Based Selection Wool Cluster of Bandipora, Jammu and Kashmir JTFRP/JK/IC/HDD/WP/C008/1 8 / Consultancy services to undertake Cluster Restoration and Quality And Cost- IDA / 56950 Post Open - National 384,615.00 0.00 Canceled 2018-10-19 2018-10-25 2018-11-09 2018-11-10 2018-12-23 2019-01-20 2019-02-19 2019-03-26 2019-04-30 2022-04-04 Development activities in strengthening of livelihoods Based Selection Wool Cluster of Pulwama, Jammu and Kashmir JTFRP/JK/IC/BBC/C010/18 / Consultancy services to develop and launch branding Restoration and Quality And Cost- IDA / 56950 Post Open - National 153,850.00 0.00 Canceled 2018-10-29 2018-12-03 2018-11-19 2018-12-17 2019-01-02 2019-01-30 2019-03-01 2019-04-05 2019-05-10 2020-05-09 and communications strengthening of livelihoods Based Selection campaign for products of J&K state JTFRP/JK/IC/IML/C011/18 / Consultancy to undertake training of artisans in product development cycle for Restoration and Quality And Cost- IDA / 56950 Post Open - National 307,700.00 0.00 Canceled 2018-10-29 2018-12-03 2018-11-19 2018-12-17 2019-01-02 2019-01-30 2019-03-01 2019-04-05 2019-05-10 2021-05-09 International Market Linkages strengthening of livelihoods Based Selection in Willow Wicker, Papier Machie, Embroidery and Wool in Jammu and Kashmir JTFRP/JK/IC/HD/WW/C015/18 / Consultancy services to undertake end to end cluster Restoration and Quality And Cost- IDA / 56950 Post Open - National 384,615.00 0.00 Canceled 2018-11-30 2018-12-03 2018-12-21 2018-12-17 2019-02-03 2019-03-03 2019-04-02 2019-05-07 2019-06-11 2021-06-10 development actvities in strengthening of livelihoods Based Selection Willow Wicker Cluster in Ganderbal JTFRP/JK/IC/HDD/WP/C018/1 8 / Consultancy services for carrying out end to end Restoration and Quality And Cost- IDA / 56950 Post Open - National 384,615.00 0.00 Canceled 2018-11-30 2018-12-03 2018-12-21 2018-12-17 2019-02-03 2019-03-03 2019-04-02 2019-05-07 2019-06-11 2021-06-10 cluster development strengthening of livelihoods Based Selection activitiesin wool cluster at Pulwama JTFRP/JK/IC/HDD/WB/C017/1 8 / Consultancy services for Restoration and Quality And Cost- carrying out end to end IDA / 56950 Post Open - National 384,615.00 0.00 Canceled 2018-11-30 2018-12-03 2018-12-21 2018-12-17 2019-02-03 2019-03-03 2019-04-02 2019-05-07 2019-06-11 2021-06-10 strengthening of livelihoods Based Selection cluster development activities in wool cluster at Bandipora. JTFRP/JK/IC/HD/ECOM/C012/ 19 / Consultancy services to develop e-Commerce Strategy Consultant Restoration and and Actionable Business Plan IDA / 56950 Post Qualification Open - National 230,800.00 0.00 Canceled 2019-01-20 2019-02-10 2019-03-26 2019-04-25 2019-05-30 2022-11-30 strengthening of livelihoods Design, Build, Maintain and Selection Manage e-Commerce Operations JTFRP/JK/IC/IML/C021/19 / to undertake Training of Artisans in Product Development Cycle for Restoration and Quality And Cost- Under IDA / 56950 Post Open - National 307,700.00 0.00 2019-02-18 2019-02-15 2019-03-11 2019-02-28 2019-04-24 2019-05-22 2019-06-21 2019-07-26 2019-08-30 2021-08-29 International Market Linkages strengthening of livelihoods Based Selection Implementation in Willow Wicker, Paper Mache, Crewel stitch embroidery and Wool in Jammu and Kashmir JTFRP/JK/IC/HDD/WB/C027/1 9 / Consultancy services to undertake Cluster Restoration and Quality And Cost- IDA / 56950 Post Open - National 384,615.00 256,006.78 Signed 2019-02-18 2019-03-12 2019-03-11 2019-03-21 2019-04-24 2019-06-25 2019-05-22 2019-08-29 2019-06-21 2019-12-10 2019-07-26 2019-12-16 2019-08-30 2020-02-10 2021-08-29 Development activities in strengthening of livelihoods Based Selection Wool Cluster of Bandipora, Jammu and Kashmir JTFRP/JK/IC/HDD/WP/C020/1 9 / Consultancy services to undertake Cluster Restoration and Quality And Cost- IDA / 56950 Post Open - National 384,615.00 0.00 Canceled 2019-02-18 2019-03-18 2019-03-11 2019-03-21 2019-04-24 2019-05-22 2019-06-21 2019-07-26 2019-08-30 2021-08-29 Development activities in strengthening of livelihoods Based Selection Wool Cluster of Pulwama, Jammu and Kashmir JTFRP/JK/IC/BBC/C020/19 / Consultancy services to Restoration and Quality And Cost- develop and launch branding IDA / 56950 Post Open - National 153,850.00 296,862.77 Signed 2019-02-18 2019-02-20 2019-03-11 2019-02-28 2019-04-24 2019-12-07 2019-05-22 2020-02-27 2019-06-21 2020-03-16 2019-07-26 2020-06-01 2019-08-30 2020-07-26 2020-08-29 strengthening of livelihoods Based Selection and communications Campaign for J&K products JTFRP/JK/HD/WW/C025/19 / Consultancy services to carry out end to end cluster Restoration and Quality And Cost- IDA / 56950 Post Open - National 384,615.00 0.00 Canceled 2019-03-25 2019-03-15 2019-04-15 2019-03-21 2019-05-29 2019-06-26 2019-07-26 2019-08-30 2019-10-04 2021-10-03 development activities in strengthening of livelihoods Based Selection Willow Wicker craft at Ganderbal J&K Page 4 JTFRP/JK/IC/JKI/R/C005/19 / Consultancy services for Restoration and Quality And Cost- conservation/restoration and IDA / 56950 Post Open - National 114,300.00 116,526.88 Signed 2019-04-10 2019-04-10 2019-05-01 2019-04-14 2019-06-14 2019-12-04 2019-07-12 2020-02-12 2019-08-11 2020-02-18 2019-09-15 2020-04-24 2019-10-20 2020-06-30 2021-04-12 strengthening of livelihoods Based Selection adaptive reuse of Govt Silk Factory Rajbagh, Srinagar J&K JTFRP/JK/IC/HD/ECOM/022/1 9 / Consultancy services to develop e-Commerce Strategy Restoration and Quality And Cost- and Actionable Business Plan IDA / 56950 Post Open - National 657,100.00 0.00 Canceled 2019-04-12 2019-05-24 2019-05-03 2019-06-05 2019-06-16 2019-07-14 2019-08-13 2019-09-17 2019-10-22 2023-04-24 strengthening of livelihoods Based Selection Design, Build, Maintain and Manage e-Commerce Operations JTFRP/JK/HD/WW/C035/19 / Consultancy services to carry out end to end cluster Restoration and Quality And Cost- IDA / 56950 Post Open - National 384,615.00 0.00 Canceled 2019-07-21 2019-09-01 2019-08-11 2019-09-29 2019-09-24 2019-10-22 2019-11-21 2019-12-26 2020-01-30 2022-01-29 development activities in strengthening of livelihoods Based Selection Willow Wicker craft at Ganderbal J&K JTFRP/JK/IC/HDD/WP/C030/1 9 / Consultancy services to Restoration and Quality And Cost- undertake cluster IDA / 56950 Post Open - National 384,615.00 0.00 Canceled 2019-07-21 2019-09-08 2019-08-11 2019-09-29 2019-09-24 2019-10-22 2019-11-21 2019-12-26 2020-01-30 2022-01-29 strengthening of livelihoods Based Selection development activities in Wool cluster of Pulwama J&K JTFRP/JK/HD/WW/C035/19-2 / Consultancy services to carry out end to end cluster Restoration and Quality And Cost- IDA / 56950 Post Open - National 384,615.00 154,542.70 Signed 2019-11-06 2019-10-20 2019-11-27 2019-11-19 2020-01-10 2020-05-23 2020-02-07 2020-05-29 2020-03-08 2020-06-06 2020-04-12 2020-06-18 2020-05-17 2020-08-14 2022-05-17 development activities in strengthening of livelihoods Based Selection willow wicker cluster at ganderbal JTFRP/JK/IC/HDD/WP/C030/1 9-2 / Consultancy services to Restoration and Quality And Cost- undertake end to end cluster IDA / 56950 Post Open - National 384,615.00 0.00 Canceled 2019-11-06 2019-11-04 2019-11-27 2019-11-19 2020-01-10 2020-02-07 2020-03-08 2020-04-12 2020-05-17 2022-05-17 strengthening of livelihoods Based Selection development activities in wool cluster at Pulwama INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual JTFRP/JK/IC/JKI/R/C001/16 / Consultancy to provide technical assistance for Restoration and assessing tangible and IDA / 56950 Post Direct Selection Direct 15,400.00 41,127.33 Completed 2017-01-18 2017-01-19 2017-02-01 2017-02-18 2017-03-29 2017-04-07 2017-05-13 2017-06-10 strengthening of livelihoods intangible heritage value of Building at Silk Factory Rajbagh Srinagar. JTFRP/JK/IC/CDI/CSPEP/C002 /16 / Individual Consultant for curriculum, course material development and It equipment for CDIs PG Individual Restoration and programs in Craft Design and IDA / 56950 Post Consultant Limited 23,000.00 0.00 Canceled 2017-01-05 2017-01-05 2017-01-10 2017-01-15 2017-01-31 2017-03-07 2017-09-03 strengthening of livelihoods sustainable development in Selection creative industries Under JTFRP for restoration and Strengthening of Livelihoods at CDI Sgr. JTFRP/JK/IC/RB/C002/17 / Consultancy for Technical Individual assistance in sourcing Restoration and IDA / 56950 Post Consultant Limited 15,400.00 4,706.07 Signed 2017-03-06 2017-04-06 2017-03-13 2017-05-05 2017-04-03 2017-06-06 2017-05-08 2017-06-20 2017-06-12 machines and Equipments for strengthening of livelihoods Selection Silk Factory Rajbagh and Bemina Woolen Mills Srinagar. JTFRP/JK/IC/JKI/BD/C003 / Consultancy for providing Restoration and retail Design of show rooms IDA / 56950 Post Direct Selection Direct 23,000.00 69,319.56 Signed 2017-04-06 2017-03-01 2017-04-16 2017-04-14 2017-06-20 2017-06-20 2018-12-20 strengthening of livelihoods at Bemina Woolen Mills and Dehli Show room under JTFRP . JTFRP/JK/IC/JKI/R/B/C002/17 / Consultancy for Technical Assistance in sourcing Individual Restoration and machines and equipments for IDA / 56950 Post Consultant Open 15,400.00 0.00 Canceled 2017-02-20 2017-04-01 2017-04-12 2017-05-03 2017-06-07 strengthening of livelihoods Silk factory RajBagh and Selection Bemina Woolen Mills Srinagar. JTFRP/JK/IC/HD/C004/17 / Consultancy services of Domain Expert towards the Restoration and IDA / 56950 Post Direct Selection Direct 461,500.00 340,042.11 Signed 2018-02-05 2018-02-05 2018-02-15 2018-02-08 2018-04-21 2018-07-25 2020-11-09 development of Crewel strengthening of livelihoods Chainstitch Cluster at Noor Bagh. JTFRP/JK/IC/HD/CD-PM- C004-18 / Consultancy Restoration and services for development of IDA / 56950 Post Direct Selection Direct 461,500.00 309,975.39 Signed 2018-04-18 2018-04-18 2018-04-28 2018-04-23 2018-05-21 2018-07-25 2020-05-31 strengthening of livelihoods Papier Machie Cluster at Zadibal Srinagar JTFRP/JK/IC/JKI/CRB001/18 / Consultancy for Technical Assistance and Project Supervision for Various Restoration and IDA / 56950 Post Direct Selection Direct 33,900.00 24,213.75 Signed 2018-07-31 2017-12-11 2018-08-06 2018-04-10 2018-10-10 2018-07-31 2019-04-08 Building Works Identified strengthening of livelihoods Under The Livelihood Component of Jehlum Tawi Floor Recovery Project JTFRP/JK/IC/HD/ITC/C006/18 / Consultancy services for feasibility study of site and Restoration and IDA / 56950 Post Direct Selection Direct 77,000.00 0.00 Canceled 2018-10-17 2018-10-27 2018-12-31 2019-06-29 working model for Kashmir strengthening of livelihoods Haat and International Trade Centre Pampore JK Page 5 JTFRP/JK/IC/SOL/C001/19 / Consultancy services for Restoration and Under adaptive reuse of Solina IDA / 56950 Prior Direct Selection Direct 357,000.00 0.00 2019-12-16 2020-10-10 2019-12-26 2020-01-10 2020-02-29 2020-08-27 strengthening of livelihoods Implementation Filatures as Arts, Culture and Crafts Centre JTFRP/JK/IC/DS/S/C001/20 / Consultancy services for undertaking a comprehensive study to determine the requirements and Restoration and Under specifications of machinery, IDA / 56950 Post Direct Selection Direct 15,750.00 0.00 2020-07-21 2020-08-18 2020-07-31 2020-10-04 2021-04-02 strengthening of livelihoods Implementation allied equipment and facilities for the existing Common Facility Centre(CFC) and formulate Quality Control and Testing benchmarks for JTFRP/JK/IC/DS/S/C002/20 / Consultancy services for Survey, Collection and Multiplication of superior Cricket Bat Willow (Salix Alba Restoration and Under IDA / 56950 Post Direct Selection Direct 128,500.00 0.00 2020-07-21 2020-08-18 2020-07-31 2020-10-04 2021-04-02 var. Caerulea) germplasm for strengthening of livelihoods Implementation livelihood security of farmers and economic sustainability of Cricket Bat Industry of Kashmir Page 6 PROCUREMENT PLAN Project information: Colombia Sustainable Low Carbon Development In Orinoquía Region Project P160680 Project Implementation agency: Ministerio de Agricultura y Desarrollo Rural -MADR- Date of the Procurement Plan: 02/06/2019 Period covered by this Procurement Plan: 02/06/2019 – 12/31/2021 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the documents previously approved with the Bank will be used. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: Is not applicable; Works: Is not applicable PROCUREMENT Colombia : Sustainable Low-Carbon Development in Orinoquia region Project PLAN General Information Country: Colombia Bank’s Approval Date of the Original Procurement Plan: 2019-02-13 2021-05-21 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P160680 GPN Date: 2019-02-13 Project Name: Sustainable Low-Carbon Development in Orinoquia region Project Loan / Credit No: TF / A6377, TF / A6376 Ministerio de Agricultura y Desarrollo Rural Executing Agency(ies): WORKS Activity Reference No. / Procurement Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Market Procurement Prequalification High SEA/SH Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Document Amount Amount Document / and Recommendation Signed Contract No. Approach Process (Y/N) Risk Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion Type (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Document / and Recommendation Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CO-MADR-149145-GO-RFQ / Adquirir Equipos de computo, cámara, software Project Coordination, licenciado , ayudas Request for Single Stage - One TF / A6377 Management, Monitoring and Post Open - National 25,000.00 20,492.96 Completed 2020-02-23 2020-04-19 2020-02-18 2020-06-03 2020-05-25 tecnologicas audiovisulaes y Quotations Envelope Evaluation de telecomunicacion para apoyar la gestión del Proyecto Fondo biocarbono . CO-MADR-177410-GO-RFQ / Adquirir Equipos de Definition of Emission cómputo, software licenciado Reduction Program and Request for Single Stage - One TF / A6377 Post Open - National 61,200.00 0.00 Canceled 2020-06-20 2020-08-15 2020-10-14 y accesorios para apoyar la Monitoring, Reporting and Quotations Envelope gestión del Proyecto Fondo Verification biocarbono CO-MADR-205824-GO-RFB / Adquirir Equipos de cómputo, Definition of Emission software licenciado y Reduction Program and Single Stage - One TF / A6376 Post Request for Bids Open - National 231,158.77 148,408.08 Signed 2020-11-27 2020-12-29 2020-12-02 2021-02-08 2021-01-13 2021-02-18 2021-02-12 2021-04-09 2021-03-19 2021-06-18 2021-09-15 accesorios para apoyar la Monitoring, Reporting and Envelope gestión del Proyecto Fondo Verification biocarbono CO-MADR-222435-GO-RFQ / Adquisición de equipos Project Coordination, Under accesorios para la operación Request for Single Stage - One TF / A6376 Management, Monitoring and Post Open - National 36,084.00 0.00 Implementati 2021-03-20 2021-05-15 2021-11-11 del Proyecto Biocarbono Quotations Envelope Evaluation on Orinoquia y la Dirección de Innovación NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Document / and Recommendation Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CO-MADR-125771-NC-RFQ / SUMINISTRO DE TIQUETES AÉREOS AL PROYECTO: DESARROLLO SOSTENIBLE Project Coordination, BAJO EN CARBONO EN LA Request for Single Stage - One TF / A6377 Management, Monitoring and Post Open - National 20,000.00 17,788.20 Signed 2019-09-05 2019-10-09 2019-10-15 2020-10-08 REGIÓN DE LA ORINOQUIA, ASÍ Quotations Envelope Evaluation COMO LA PRESTACIÓN DE SERVICIOS DE AGENCIA DE VIAJES -AÑO 1 -COMPONENTE 4 CO-MADR-132942-NC-RFQ Project Coordination, / Taller de socializacion y Request for Single Stage - One TF / A6377 Management, Monitoring and Post Open - National 4,000.00 0.00 Canceled 2019-09-05 2019-09-20 2019-09-30 arranque Fondo Biocarbono Quotations Envelope Evaluation Septiembre 2019 CO-MADR-163819-NC-RFQ / Prestar los servicios logísticos (alimentación, salón y ayudas audiovisuales) para los asistentes a la primera Project Coordination, Request for Single Stage - One Mesa Técnica TF / A6377 Management, Monitoring and Post Open 8,000.00 0.00 Canceled 2020-03-09 2020-03-21 2020-04-20 Quotations Envelope Intercomponentes para el Evaluation proyecto, “DESARROLLO SOSTENIBLE BAJO EN CARBONO EN LA REGIÓN DE LA ORINOQUIA” CO-MADR-197658-NC-RFB / Implementar la actualización catastral con enfoque Integrated Land- Use multipropósito para el Planning and Improved municipio de Arauquita, en el TF / A6377 Post Direct Selection Direct 1,500,000.00 1,180,395.29 Signed 2020-11-06 2020-11-20 2020-11-11 2020-11-20 2020-12-08 2021-01-28 2021-12-08 Governance for Deforestation departamento de Arauca, en el Control marco del Proyecto Desarrollo Sostenible Bajo en Carbono para la Orinoquia. CO-MADR-201158-NC-RFB / Inventario Forestal de la Definition of Emission región de la Orinoquía, dentro Reduction Program and Single Stage - One del Componente 3: TF / A6376 Post Request for Bids Open - National 941,000.00 0.00 Canceled 2020-11-17 2020-11-19 2020-11-22 2020-11-21 2021-01-03 2021-02-02 2021-03-09 2021-09-05 Monitoring, Reporting and Envelope Preparación del Programa de Verification Reducción de Emisiones y del MRV CO-MADR-211404-NC-RFB / Elaborar el inventario forestal de la región Orinoquia siguiendo los parámetros Definition of Emission establecidos en el Documento Under Reduction Program and Single Stage - One Marco Rector, el marco TF / A6376 Post Request for Bids Open - National 941,000.00 0.00 Implementati 2020-12-28 2020-12-28 2021-01-02 2021-01-04 2021-01-19 2021-02-03 2021-03-10 2021-09-06 Monitoring, Reporting and Envelope estadístico y geoestadístico, on Verification los procedimientos, metodologías y protocolos técnicos definidos por el IDEAM para la impleme Page 1 CO-MADR-218245-NC-RFB / Establecer factores de emisión Definition of Emission Pending para los usos del suelo Reduction Program and Single Stage - One TF / A6376 Post Request for Bids Open - National 772,850.00 0.00 Implementati 2021-03-15 2021-03-20 2021-05-01 2021-05-31 2021-07-05 2022-01-01 distintos a bosque y los Monitoring, Reporting and Envelope on cambios de uso del suelo de la Verification Orinoquia CO-MADR-218458-NC-RFB / Prestar servicios como Integrated Land- Use Operador logístico para la Under Planning and Improved Single Stage - One puesta en marcha de las TF / A6376 Post Request for Bids Open - National 194,750.00 0.00 Implementati 2021-04-22 2021-04-14 2021-04-27 2021-06-08 2021-05-18 2021-07-08 2021-06-03 2021-08-12 2022-02-08 Governance for Deforestation Envelope diferentes actividades y on Control estrategias del proyecto BIOCARBONO CO-MADR-224155-NC-RFQ / Prestar sus servicios profesionales con autonomía técnica y administrativa, para Project Coordination, Pending la grabación, edición, Request for Single Stage - One TF / A6376 Management, Monitoring and Post Open - National 18,187.00 0.00 Implementati 2021-05-08 2021-07-03 2021-12-30 animación y entrega de videos Quotations Envelope Evaluation on y fotografías para el Proyecto Desarrollo Sostenible bajo en carbono en la región de la Orinoquia CO-MADR-218263-NC-RFB / Formular un plan de Integrated Land- Use ordenamiento social de la Planning and Improved Single Stage - One propiedad rural en un TF / A6376 Post Request for Bids Open - National 300,000.00 0.00 Canceled 2021-02-22 2021-02-27 2021-04-10 2021-05-10 2021-06-14 2021-12-11 Governance for Deforestation Envelope municipio priorizado por el Control Proyecto, con base en los lineamientos de la ANT CO-MADR-218264-NC-RFB / Integrated Land- Use Formular dos (2) planes de Planning and Improved Single Stage - One ordenación forestal, con base TF / A6376 Post Request for Bids Open - National 300,000.00 0.00 Canceled 2021-02-22 2021-02-27 2021-04-10 2021-05-10 2021-06-14 2021-12-11 Governance for Deforestation Envelope en los lineamientos de las Control Corporaciones y MADS CO-MADR-231937-NC-DIR / Suministro de tiquetes aéreos Integrated Land- Use Pending de pasajeros en rutas Planning and Improved TF / A6376 Post Direct Selection Direct 45,714.00 0.00 Implementati 2021-04-30 2021-05-05 2021-06-09 2021-12-06 nacionales o internacionales Governance for Deforestation on para el desarrollo del Proyecto Control BIOCARBONO - ORINOQUIA CO-MADR-222433-NC-RFQ / Prestar el servicio de diseño e impresión de afiches, folletos, cartillas, u otras publicaciones a demanda, Project Coordination, Request for Single Stage - One impresas o digitales, hacer las TF / A6376 Management, Monitoring and Post Open - National 30,312.00 0.00 Canceled 2021-03-20 2021-05-15 2021-11-11 Quotations Envelope respectivas gestiones para la Evaluation adquisición del ISBN para las publicaciones que lo requieran, realizar la producción CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CO-MADR-172824-CS-QCBS / “Elaborar los lineamientos y criterios técnicos establecidos en la Ley 1776 "por la cual se Integrated Land- Use crean y se desarrollan las Planning and Improved Quality And Cost- TF / A6377 Post Open - National 72,750.00 69,472.22 Signed 2020-05-08 2020-06-08 2020-05-22 2020-07-05 2020-10-09 2020-07-19 2020-11-27 2020-07-24 2021-01-25 2020-08-13 2021-01-15 2020-09-10 2021-04-27 2021-01-08 zonas de interés de desarrollo Governance for Deforestation Based Selection rural, económico y social, Control ZIDRES"; definiendo las condiciones de presentación, evaluación elegibilidad, CO-MADR-182002-CS-QBS / “Consultoría para la gestión de agroecosistemas ganaderos Sustainable Land- Use Quality Based Under TF / A6377 Prior Open - International 1,000,000.00 0.00 2020-06-30 2020-07-30 2020-07-21 2020-08-12 2020-08-19 2020-12-23 2020-09-03 2021-02-09 2020-09-13 2021-03-23 2020-09-23 2020-10-21 2021-12-15 sostenibles bajos en carbono Management Selection Implementation en paisajes priorizados de la Orinoquia” CO-MADR-183810-CS-QCBS / “Apoyar la estructuración de Sustainable Land- Use Quality And Cost- programas y proyectos de TF / A6377 Post Open - National 181,667.00 163,459.11 Signed 2020-07-13 2020-07-16 2020-07-28 2020-09-26 2020-10-05 2020-10-11 2020-11-20 2020-10-21 2020-12-23 2020-11-15 2020-12-23 2020-12-20 2021-03-23 2021-09-16 Management Based Selection Pagos por Servicios Ambientales CO-MADR-196095-CS-QBS / Consultoría para identificar, validar y socializar modelos productivos sostenibles bajos Sustainable Land- Use Quality Based en carbono para el cultivo de TF / A6377 Post Open - International 600,000.00 368,742.33 Signed 2020-09-30 2020-10-09 2020-10-21 2020-10-30 2020-11-19 2020-12-10 2021-01-03 2021-01-12 2021-01-18 2021-01-29 2021-02-02 2021-01-29 2021-03-02 2021-04-29 2022-03-02 Management Selection arroz en Arauca (Arauca), Paz de Ariporo (Casanare), Villavicencio, Puerto López y Puerto Gaitán (Meta). CO-MADR-197663-CS-CQS / Identificar, documentar, analizar y validar los factores de emisión para plantaciones Definition of Emission forestales de Colombia y en Consultant Reduction Program and Under particular de la región TF / A6377 Post Qualification Open - National 74,538.00 0.00 2020-10-09 2020-10-09 2020-10-13 2020-12-16 2020-12-27 2021-01-01 2021-01-25 2021-07-24 Monitoring, Reporting and Implementation Orinoquia, como insumo del Selection Verification sistema nacional de MRV para AFOLU y a través de un ejercicio concertado entre las entidad CO-MADR-178416-CS-QCBS / Actualizar el inventario de Definition of Emission Gases Efecto Invernadero (GEI) Reduction Program and Quality And Cost- TF / A6377 Post Open - National 85,000.00 0.00 Canceled 2020-06-12 2020-06-10 2020-06-26 2020-08-09 2020-08-23 2020-08-28 2020-09-17 2020-10-15 2020-12-14 de la región de la Orinoquía Monitoring, Reporting and Based Selection con variables representativas Verification (proxy) a escala municipal. CO-MADR-194714-CS-QCBS / Inventario Forestal de la Definition of Emission región de la Orinoquía, dentro Reduction Program and Quality And Cost- del Componente 3: TF / A6377 Post Open - International 941,000.00 0.00 Canceled 2020-09-24 2020-09-23 2020-10-14 2020-09-25 2020-12-13 2020-12-27 2021-01-01 2021-02-05 2021-03-06 2022-03-06 Monitoring, Reporting and Based Selection Preparación del Programa de Verification Reducción de Emisiones y del MRV Page 2 CO-MADR-201847-CS-QCBS / Caracterizar, validar y socializar sistemas agroforestales (SAF) bajos en carbono para el cultivo de Sustainable Land- Use Quality And Cost- Under TF / A6376 Post Open - National 383,000.00 0.00 2020-11-09 2021-06-11 2020-11-30 2021-01-13 2021-02-10 2021-03-12 2021-04-16 2021-05-21 2022-05-21 cacao en las subregiones del Management Based Selection Implementation Sarare (Arauca) y la cuenca alta y media del río Ariari (Meta), en la Orinoquia colombiana CO-MADR-204779-CS-LCS / Realizar la auditoria externa al proyecto Desarrollo Sostenible Project Coordination, Bajo en Carbono para la Least Cost Under TF / A6376 Management, Monitoring and Post Open - National 37,651.00 0.00 2020-11-27 2021-01-28 2020-12-18 2021-01-31 2021-02-04 2021-02-28 2021-03-04 2021-03-30 2021-05-04 2021-06-08 2021-12-05 Orinoquia , para el periodo Selection Implementation Evaluation comprendido entre el 1 de junio del 2019 y hasta el 31 de diciembre de 2020 CO-MADR-218246-CS-QCBS Definition of Emission / Generar factores de emisión Reduction Program and Quality And Cost- Under Tir2 para arroz de secano y TF / A6376 Post Open - National 353,000.00 0.00 2021-02-26 2021-04-27 2021-03-19 2021-05-02 2021-05-30 2021-06-29 2021-08-03 2021-09-07 2022-09-07 Monitoring, Reporting and Based Selection Implementation ganadería de cría en la región Verification de la Orinoquía CO-MADR-218250-CS-LCS / Definition of Emission Diseñar el Plan de financiación Reduction Program and Least Cost para la implementación de las TF / A6376 Post Open - National 80,000.00 0.00 Canceled 2021-02-19 2021-03-12 2021-04-25 2021-05-23 2021-06-22 2021-07-27 2021-08-31 2022-02-27 Monitoring, Reporting and Selection acciones e intervenciones Verification previstas del ERPD CO-MADR-218252-CS-LCS / Implementar las salvaguardas establecidas a nivel nacional, Definition of Emission con las comunidades de la Reduction Program and Least Cost región, y desarrollar los TF / A6376 Post Open - National 75,000.00 0.00 Canceled 2021-03-26 2021-04-16 2021-05-30 2021-06-27 2021-07-27 2021-08-31 2021-10-05 2022-04-03 Monitoring, Reporting and Selection reportes de dichas actividades Verification de acuerdo con los lineamientos nacionales (MGAS, PPI, MP) CO-MADR-201848-CS-QCBS / Caracterizar, validar y socializar modelos de producción - conservación Sustainable Land- Use Quality And Cost- Pending TF / A6376 Post Open - National 250,000.00 0.00 2021-03-01 2021-03-22 2021-05-05 2021-06-02 2021-07-02 2021-08-06 2021-09-10 2022-09-10 para el cultivo de marañón Management Based Selection Implementation bajo en carbono a escala de paisaje en la altillanura colombiana CO-MADR-218269-CS-QCBS / Desarrollo de un modelo de negocios para la consolidación de la producción de aceite de palma sostenible en paisajes Sustainable Land- Use Quality And Cost- Pending TF / A6376 Post Open - National 300,000.00 0.00 2021-03-15 2021-04-05 2021-05-19 2021-06-16 2021-07-16 2021-08-20 2021-09-24 2022-09-24 palmeros priorizados a partir Management Based Selection Implementation de la realización de análisis costo - beneficio de mejores prácticas bajas en carbono y el diseño de herrami CO-MADR-218270-CS-CQS / Identificar especies vegetales, desarrollar protocolos y Consultant Sustainable Land- Use Pending fortalecer capacidades para TF / A6376 Post Qualification Open - National 150,000.00 0.00 2021-04-30 2021-05-21 2021-07-04 2021-08-03 2021-09-07 2022-03-06 Management Implementation procesos de reconversión, Selection restauración y fomento de SAF en paisajes priorizados CO-MADR-218271-CS-QCBS / Definir e implementar mesas Sustainable Land- Use Quality And Cost- Under TF / A6376 Post Open - National 300,000.00 0.00 2021-03-01 2021-04-05 2021-03-22 2021-05-05 2021-06-02 2021-07-02 2021-08-06 2021-09-10 2022-09-10 técnicas agroclimáticas en la Management Based Selection Implementation Orinoquia CO-MADR-218275-CS-QCBS / Ajustar los instrumentos de financiamiento e incentivos Sustainable Land- Use Quality And Cost- Pending forestales y de bosques de TF / A6376 Post Open - National 225,000.00 0.00 2021-03-31 2021-04-21 2021-06-04 2021-07-02 2021-08-01 2021-09-05 2021-10-10 2022-10-10 Management Based Selection Implementation conservación y evaluar y/o diseñar instrumentos regulatorios CO-MADR-199060-CS-QCBS / Diseñar, apoyar y hacer recomendaciones a la implementación de acciones Integrated Land- Use dirigidas a la reducción de la Planning and Improved Quality And Cost- TF / A6376 Post Open - International 550,000.00 0.00 Canceled 2020-10-20 2020-11-12 2020-11-03 2020-12-20 2020-12-28 2021-01-05 2021-01-21 2021-02-14 2022-02-14 deforestación, la promoción Governance for Deforestation Based Selection de la legalidad de la cadena Control forestal y la conservación de los bosques en la región de la Orinoquia CO-MADR-222430-CS-LCS / Diseñar un Protocolo con guías de actuación en situaciones de riesgo, crisis comunicativa y reputacional, Project Coordination, Least Cost Pending socializarlo y capacitar a los TF / A6376 Management, Monitoring and Post Open - National 18,826.00 0.00 2021-03-12 2021-04-02 2021-05-16 2021-06-13 2021-07-13 2021-08-17 2021-09-21 2022-03-20 Selection Implementation voceros del Proyecto Evaluation Desarrollo Sostenible bajo en carbono en la región de la Orinoquia, en acuerdo con lo establecid CO-MADR-222431-CS-CQS / Prestar servicios de monitoreo de medios de comunicación nacionales, regionales y Project Coordination, Consultant Pending municipales (prensa escrita, TF / A6376 Management, Monitoring and Post Qualification Limited 10,609.00 0.00 2021-03-15 2021-03-29 2021-04-28 2021-06-02 2021-11-29 Implementation radio, televisión, internet y Evaluation Selection redes sociales) en temas de interés del proyecto Biocarbono Orinoquia Page 3 CO-MADR-222428-CS-QCBS / Prestar sus servicios como central de medios o agencia de medios para el diseño, ejecución y seguimiento de un Project Coordination, Least Cost Pending plan de medios que acompañe TF / A6376 Management, Monitoring and Post Open - National 87,853.00 0.00 2021-04-23 2021-05-14 2021-06-27 2021-07-25 2021-08-24 2021-09-28 2021-11-02 2022-05-01 Selection Implementation la estrategia de Evaluation comunicaciones y participación del Proyecto Desarrollo Sostenible bajo en carbono en la región de l CO-MADR-218256-CS-QCBS Integrated Land- Use / Actualizar y socializar el Planning and Improved Quality And Cost- TF / A6376 Post Open - National 200,000.00 0.00 Canceled 2021-05-31 2021-06-21 2021-08-04 2021-09-01 2021-10-01 2021-11-05 2021-12-10 2022-12-10 MOTRO con el gobierno Governance for Deforestation Based Selection regional actual Control CO-MADR-233553-CS-QCBS / Preparar un plan de financiación y un plan de Definition of Emission distribución de beneficios para Reduction Program and Quality And Cost- Under el Programa de Reducción de TF / A6376 Post Open - National 160,000.00 0.00 2021-05-10 2021-05-27 2021-05-31 2021-07-14 2021-08-11 2021-09-10 2021-10-15 2021-11-19 2022-03-19 Monitoring, Reporting and Based Selection Implementation Emisiones de la región de la Verification Orinoquia en Colombia, a partir de una evaluación de costos y beneficios CO-MADR-218457-CS-QCBS / Diseñar e implementar un programa de formación de formadores en planificación Integrated Land- Use territorial enfocado a bajo Planning and Improved Quality And Cost- Pending carbono, hacedores de TF / A6376 Post Open - National 392,440.00 0.00 2021-08-02 2021-08-23 2021-10-06 2021-11-03 2021-12-03 2022-01-07 2022-02-11 2022-11-08 Governance for Deforestation Based Selection Implementation política, organizaciones, Control EPSEAS y demás temas relacionados con los componentes 1 y 2 del Proyecto BIOCARBONO CO-MADR-218257-CS-CQS / Realizar acompañamiento técnico y jurídico para la Integrated Land- Use Consultant adopción de las determinantes Planning and Improved TF / A6376 Post Qualification Open - National 120,000.00 0.00 Canceled 2021-05-31 2021-06-21 2021-08-04 2021-09-03 2021-10-08 2022-04-06 ambientales regionales en las Governance for Deforestation Selection corporaciones Control (CORPORINOQUIA y CORMACARENA) CO-MADR-218259-CS-CQS / Implementar en los POT de los Integrated Land- Use Consultant municipios priorizados del Planning and Improved TF / A6376 Post Qualification Open - National 150,000.00 0.00 Canceled 2021-05-31 2021-06-21 2021-08-04 2021-09-03 2021-10-08 2022-04-06 Vichada, acciones de gestión Governance for Deforestation Selection de cambio climático basado en Control EEP CO-MADR-240660-CS-QCBS / Incorporar la gestión del cambio climático en las Integrated Land- Use determinantes ambientales Planning and Improved Quality And Cost- Pending (CORPORINOQUIA - TF / A6376 Post Open - National 270,000.00 0.00 2021-07-12 2021-08-02 2021-09-15 2021-10-13 2021-11-12 2021-12-17 2022-01-21 2023-01-21 Governance for Deforestation Based Selection Implementation CORMACARENA) y desarrollar Control un piloto a escala local a través del modelo de estructura ecológica principal CO-MADR-218266-CS-QCBS / Construir el plan de acción para la implementación de la estrategia integral de control Integrated Land- Use de la deforestación y Planning and Improved Quality And Cost- Pending TF / A6376 Post Open - National 300,000.00 0.00 2021-08-05 2021-08-26 2021-10-09 2021-11-06 2021-12-06 2022-01-10 2022-02-14 2023-02-14 propuesta de fortalecimiento Governance for Deforestation Based Selection Implementation de capacidades e Control involucramiento de actores, con énfasis en las autoridades ambientales y municipales CO-MADR-218273-CS-QCBS / Diseñar la estrategia de gestión del conocimiento para Sustainable Land- Use Quality And Cost- el desarrollo regional bajo en TF / A6376 Post Open - National 80,000.00 0.00 Canceled 2021-04-30 2021-05-21 2021-07-04 2021-08-01 2021-08-31 2021-10-05 2021-11-09 2022-11-09 Management Based Selection carbono de la Orinoquia y la consolidación de circuitos cortos bajos en carbono CO-MADR-218251-CS-LCS / Definition of Emission Construir propuestas de Reduction Program and Least Cost TF / A6376 Post Open - National 60,000.00 0.00 Canceled 2021-03-26 2021-04-16 2021-05-30 2021-06-27 2021-07-27 2021-08-31 2021-10-05 2022-04-03 articulación en áreas de Monitoring, Reporting and Selection traslape Verification CO-MADR-218253-CS-LCS / Definition of Emission Diseñar el Plan de distribución Reduction Program and Least Cost de beneficios del Programa de TF / A6376 Post Open - National 80,000.00 0.00 Canceled 2021-03-26 2021-04-16 2021-05-30 2021-06-27 2021-07-27 2021-08-31 2021-10-05 2022-04-03 Monitoring, Reporting and Selection Reducción de Emisiones de la Verification Orinoquia CO-MADR-218254-CS-CQS / Realizar el proceso de Definition of Emission Consultant mejoramiento de información Reduction Program and TF / A6376 Post Qualification Open - National 60,000.00 0.00 Canceled 2021-02-26 2021-03-19 2021-05-02 2021-06-01 2021-07-06 2022-01-02 y de los sistemas de Monitoring, Reporting and Selection información relacionados con Verification tierras forestales (SNIF) INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CO-MADR-99638-CS-INDV / Project Coordination, Individual Profesional de adquisiciones TF / A6377 Management, Monitoring and Post Consultant Open 24,500.00 55,379.34 Completed 2019-02-11 2019-02-26 2019-02-21 2019-04-10 2019-02-22 2019-04-19 2019-03-01 2019-06-04 2020-03-01 2020-02-20 para la UIP del proyecto Evaluation Selection CO-MADR-99663-CS-INDV / Project Coordination, Individual Profesional financiero para el TF / A6377 Management, Monitoring and Post Consultant Open 24,500.00 54,491.02 Signed 2019-02-11 2019-02-26 2019-02-19 2019-04-10 2019-02-20 2019-04-19 2019-03-01 2019-06-04 2019-08-28 apoyo en la UIP Evaluation Selection CO-MADR-99665-CS-INDV / Project Coordination, Individual Coordinador general para la TF / A6377 Management, Monitoring and Post Consultant Open 45,000.00 79,276.45 Completed 2019-02-11 2019-02-13 2019-02-19 2019-04-10 2019-02-22 2019-04-19 2019-03-01 2019-06-04 2019-08-28 2020-04-07 UPI Evaluation Selection Page 4 CO-MADR-99654-CS-INDV / Asistente administrativo y Project Coordination, Individual operativo para apoyar al TF / A6377 Management, Monitoring and Post Consultant Open 48,000.00 0.00 Canceled 2019-02-25 2019-04-15 2019-05-06 2019-06-10 2019-12-07 IDEAM en la coordinación de Evaluation Selection las acciones de gestión del programa CO-MADR-99650-CS-INDV / Seis consultores que obtengan los insumos para la Project Coordination, Individual elaboración del ER-Programa TF / A6377 Management, Monitoring and Post Consultant Open 210,000.00 0.00 Canceled 2019-02-18 2019-04-08 2019-04-29 2019-06-03 2019-11-30 desde las instituciones Evaluation Selection gubernamentales (MADS, MADR, UPRA, DNP, FINAGRO, PRICCO) CO-MADR-107364-CS-INDV Project Coordination, Individual / Apoyo Administrativo a la TF / A6377 Management, Monitoring and Post Consultant Open 17,000.00 31,945.63 Signed 2019-04-05 2019-06-25 2019-04-19 2019-08-06 2019-04-23 2019-09-02 2019-05-01 2019-09-12 2019-12-31 Unidad de Implementación del Evaluation Selection proyecto CO-MADR-107357-CS-INDV / Líder Especialista en Project Coordination, Individual Planificación y Políticas TF / A6377 Management, Monitoring and Post Consultant Open 23,900.00 35,046.00 Signed 2019-04-05 2019-06-18 2019-04-22 2019-08-13 2019-04-25 2019-09-13 2019-05-01 2019-10-25 2019-12-31 Públicas en la Unidad de Evaluation Selection Implementación del Proyecto CO-MADR-107358-CS-INDV / Líder Especialista en Project Coordination, Individual Monitoreo de la Unidad de TF / A6377 Management, Monitoring and Post Consultant Open 28,120.00 41,839.39 Signed 2019-04-05 2019-06-18 2019-04-22 2019-08-02 2019-04-25 2019-08-28 2019-05-01 2019-10-25 2019-12-31 Implementación del Proyecto Evaluation Selection MADR CO-MADR-107362-CS-INDV / Asesor de Comunicaciones y Project Coordination, Individual Participación de la Unidad de TF / A6377 Management, Monitoring and Post Consultant Open 23,900.00 45,256.30 Completed 2019-04-05 2019-06-25 2019-04-22 2019-08-09 2019-04-25 2019-08-02 2019-05-01 2019-09-12 2019-12-31 2020-04-07 Implementación del Proyecto Evaluation Selection MADR CO-MADR-107363-CS-INDV / Líder Especialista en Project Coordination, Individual Desarrollo Rural de Bajas TF / A6377 Management, Monitoring and Post Consultant Open 28,000.00 41,230.59 Signed 2019-04-05 2019-06-18 2019-04-22 2019-08-02 2019-04-25 2019-08-28 2019-05-01 2019-10-25 2019-12-31 Emisiones de la Unidad de Evaluation Selection Implementación del proyecto MADR CO-MADR-132927-CS-INDV Project Coordination, Individual / Apoyo Departamental TF / A6377 Management, Monitoring and Post Consultant Open 10,833.00 48,997.23 Signed 2019-09-05 2019-08-01 2019-09-05 2019-09-05 2019-09-05 2019-10-18 2019-09-12 2019-11-15 2019-12-31 Arauca - Primer (1)año Evaluation Selection CO-MADR-132931-CS-INDV Project Coordination, Individual / Apoyo Departamental TF / A6377 Management, Monitoring and Post Consultant Open 10,833.00 48,320.94 Signed 2019-09-05 2019-08-01 2019-09-05 2019-10-18 2019-09-05 2019-10-17 2019-09-12 2019-11-25 2019-12-31 Casanare (1) primer año Evaluation Selection CO-MADR-132935-CS-INDV Project Coordination, Individual / Apoyo Departamental Meta TF / A6377 Management, Monitoring and Post Consultant Open 10,833.00 48,997.23 Signed 2019-09-05 2019-08-01 2019-09-05 2019-10-08 2019-09-05 2019-10-18 2019-09-12 2019-11-15 2019-12-31 - Primer (1)año Evaluation Selection CO-MADR-132937-CS-INDV Project Coordination, Individual / Apoyo Departamental TF / A6377 Management, Monitoring and Post Consultant Open 10,833.00 25,176.86 Signed 2019-09-05 2019-08-01 2019-09-05 2019-09-05 2019-09-05 2019-09-05 2019-09-12 2019-12-02 2019-12-31 Vichada - Primer (1) año Evaluation Selection CO-MADR-153426-CS-CDS / Prestar sus servicios profesionales con autonomía técnica apoyando a la Definition of Emission Subdirección de Estudios Individual Reduction Program and Ambientales del el Instituto de TF / A6377 Post Consultant Direct 34,320.00 25,510.40 Signed 2020-02-06 2020-02-11 2020-02-27 2020-02-13 2020-03-03 2020-02-13 2020-03-13 2020-03-10 2021-03-13 Monitoring, Reporting and Hidrología, Meteorología y Selection Verification Estudios Ambientales IDEAM, como profesional experto en los análisis espaciales y estructuración de CO-MADR-143405-CS-INDV Project Coordination, Individual / Especialista en comunicación TF / A6377 Management, Monitoring and Post Consultant Open 28,000.00 13,851.04 Signed 2019-10-29 2019-10-30 2019-11-06 2020-01-28 2019-11-27 2020-02-04 2020-02-18 2020-03-03 2020-08-16 Digital Evaluation Selection CO-MADR-143406-CS-INDV Project Coordination, Individual / Profesional en medios e TF / A6377 Management, Monitoring and Post Consultant Open 2,000.00 1,484.04 Signed 2019-10-29 2019-10-30 2019-11-06 2020-01-31 2019-11-26 2020-02-07 2020-02-24 2020-03-03 2020-05-08 Identidad Grafica Evaluation Selection CO-MADR-148038-CS-INDV / Gestor Técnico, para la implementación y seguimiento técnico del componente 1 del Integrated Land- Use Proyecto: Desarrollo Individual Planning and Improved Sostenible bajo en carbono en TF / A6377 Post Consultant Open 34,000.00 25,368.42 Completed 2020-02-24 2020-03-12 2020-03-21 2020-05-29 2020-03-26 2020-04-23 2020-04-09 2020-05-01 2021-04-09 2020-05-01 Governance for Deforestation la región de la Orinoquia, Selection Control específicamente apoyando el desarrollo de la arquitecturafuncional y de componentes del sistema CO-MADR-153424-CS-CDS / Prestar sus servicios profesionales con autonomía técnica, apoyando a la Subdirección de Estudios Definition of Emission Individual Ambientales del el Instituto de Reduction Program and TF / A6377 Post Consultant Direct 34,320.00 25,358.02 Signed 2020-02-06 2020-02-11 2020-02-27 2020-02-13 2020-03-03 2020-02-13 2020-03-13 2020-03-06 2021-03-13 Hidrología, Meteorología y Monitoring, Reporting and Selection Estudios Ambientales IDEAM, Verification como profesional agropecuario para la caracterización y seguimiento de CO-MADR-132919-CS-INDV Project Coordination, Individual / Especialista Sector privado TF / A6377 Management, Monitoring and Post Consultant Open 12,500.00 58,528.16 Signed 2019-09-05 2019-08-01 2019-09-05 2019-09-30 2019-09-05 2019-09-30 2019-09-12 2019-11-26 2020-07-26 - año 1 Evaluation Selection CO-MADR-153423-CS-CDS / Prestar sus servicios profesionales con autonomía técnica, apoyando a la Definition of Emission Subdirección de Estudios Individual Reduction Program and Ambientales del el Instituto de TF / A6377 Post Consultant Direct 34,320.00 25,510.40 Signed 2020-02-06 2020-02-11 2020-02-27 2020-04-13 2020-03-03 2020-02-13 2020-03-13 2020-03-06 2021-03-13 Monitoring, Reporting and Hidrología, Meteorología y Selection Verification Estudios Ambientales IDEAM, como profesional experto en análisis espaciales para la recopilación, Page 5 CO-MADR-153429-CS-CDS / Prestar sus servicios profesionales con autonomía técnica apoyando a la Definition of Emission Subdirección de Estudios Individual Reduction Program and Ambientales del el Instituto de TF / A6377 Post Consultant Direct 31,680.00 25,189.40 Signed 2020-02-06 2020-02-11 2020-02-27 2020-06-08 2020-03-03 2020-06-08 2020-03-13 2020-07-15 2021-03-13 Monitoring, Reporting and Hidrología, Meteorología y Selection Verification Estudios Ambientales IDEAM, liderando la articulación de los procesos de Monitoreo Comunitario Par CO-MADR-132940-CS-INDV Project Coordination, Individual / Coordinador Regional - TF / A6377 Management, Monitoring and Post Consultant Open 38,000.00 28,352.94 Signed 2020-09-06 2020-01-08 2020-09-06 2020-02-07 2020-09-06 2020-03-03 2020-09-13 2020-03-06 2021-01-01 Primer (1) año Evaluation Selection CO-MADR-153428-CS-CDS / Prestar sus servicios profesionales con autonomía técnica apoyando a la Definition of Emission Subdirección de Estudios Individual Reduction Program and Ambientales del el Instituto de TF / A6377 Post Consultant Direct 37,180.00 27,636.27 Signed 2020-02-06 2020-02-11 2020-02-27 2020-02-13 2020-03-03 2020-02-13 2020-03-13 2020-03-06 2021-03-13 Monitoring, Reporting and Hidrología, Meteorología y Selection Verification Estudios Ambientales IDEAM, asesorando estadísticamente los procesos necesarios para el levantamien Integrated Land- Use Individual CO-MADR-142886-CS-INDV Planning and Improved TF / A6377 Post Consultant Open 34,000.00 25,649.94 Signed 2020-02-20 2019-12-05 2020-03-16 2020-02-18 2020-03-21 2020-03-16 2020-04-06 2020-03-17 2021-04-06 / GESTOR TECNICO DNP Governance for Deforestation Selection Control Integrated Land- Use Individual CO-MADR-146069-CS-INDV Planning and Improved TF / A6377 Post Consultant Open 6,000.00 4,476.78 Signed 2020-02-20 2019-12-05 2020-03-06 2020-02-27 2020-03-14 2020-02-27 2020-03-27 2020-03-26 2020-07-25 / PROFESIONAL ZIDRES 4 Governance for Deforestation Selection Control Integrated Land- Use Individual CO-MADR-146065-CS-INDV Planning and Improved TF / A6377 Post Consultant Open 6,000.00 4,526.46 Signed 2020-02-27 2019-12-05 2020-02-28 2020-02-27 2020-02-28 2020-02-27 2020-03-09 2020-03-25 2020-07-07 / PROFESIONAL ZIDRES 1 Governance for Deforestation Selection Control Integrated Land- Use Individual CO-MADR-146066-CS-INDV Planning and Improved TF / A6377 Post Consultant Open 6,000.00 4,476.78 Signed 2020-02-20 2019-12-05 2020-03-06 2020-02-27 2020-03-14 2020-02-27 2020-03-23 2020-03-26 2020-07-21 / PROFESIONAL ZIDRES 2 Governance for Deforestation Selection Control Integrated Land- Use Individual CO-MADR-146068-CS-INDV Planning and Improved TF / A6377 Post Consultant Open 6,000.00 4,476.78 Signed 2020-02-20 2019-12-05 2020-03-06 2020-02-27 2020-03-14 2020-02-27 2020-03-27 2020-03-26 2020-07-25 / PROFESIONAL ZIDRES 3 Governance for Deforestation Selection Control CO-MADR-159519-CS-INDV / Prestar sus servicios profesionales como consultor SOCIAL de salvaguardas con Definition of Emission autonomía técnica y Individual Reduction Program and administrativa, apoyando a la TF / A6377 Post Consultant Open 34,000.00 25,121.58 Completed 2020-02-20 2020-02-13 2020-03-25 2020-03-09 2020-03-30 2020-04-11 2020-04-10 2020-04-02 2021-04-10 2020-07-28 Monitoring, Reporting and Unidad Implementadora del Selection Verification Proyecto, UIP, al Ministerio de Agricultura y Desarrollo Rural, bajo la orientación del Ministerio de CO-MADR-159520-CS-INDV / Prestar sus servicios profesionales como consultor AMBIENTAL de salvaguardas Definition of Emission con autonomía técnica y Individual Reduction Program and administrativa, apoyando a la TF / A6377 Post Consultant Open 34,000.00 25,121.58 Signed 2020-02-20 2020-02-13 2020-03-25 2020-03-09 2020-03-30 2020-03-11 2020-04-15 2020-04-02 2021-04-15 Monitoring, Reporting and Unidad Implementadora del Selection Verification Proyecto UIP: Desarrollo sostenible bajo en carbono en la región de la Orinoquia, al Ministerio de CO-MADR-159522-CS-INDV / Prestar sus servicios profesionales, con autonomía técnica y administrativa, apoyando a la Dirección de Project Coordination, Individual Under Innovación, Desarrollo TF / A6377 Management, Monitoring and Post Consultant Open 34,000.00 31,046.40 2020-02-20 2020-03-04 2020-03-25 2020-06-23 2020-03-30 2020-06-23 2020-04-14 2021-04-14 Implementation Tecnológico y Protección Evaluation Selection Sanitaria del Ministerio de Agricultura y Desarrollo Rural, en la realización de los procesos de adqui Definition of Emission CO-MADR-151449-CS-INDV Individual Reduction Program and / Profesional Programador TF / A6377 Post Consultant Open 26,667.00 0.00 Canceled 2020-01-13 2020-01-13 2020-01-13 2020-02-17 2021-02-17 Monitoring, Reporting and senior Selection Verification CO-MADR-99651-CS-INDV / Un consultor para implementar una plataforma Project Coordination, Individual de gestión del conocimiento y TF / A6377 Management, Monitoring and Post Consultant Open 35,000.00 0.00 Canceled 2019-02-25 2019-04-15 2019-05-06 2019-06-10 2019-12-07 experiencias en el diseño e Evaluation Selection implementación de ER- Program CO-MADR-99659-CS-INDV / Líder técnico especialista en uso y cambios de uso del Project Coordination, Individual suelo de apoyo al IDEAM en la TF / A6377 Management, Monitoring and Post Consultant Open 72,000.00 0.00 Canceled 2019-02-25 2019-04-15 2019-05-06 2019-06-10 2019-12-07 estimación y el reporte de Evaluation Selection emisiones y remociones de GEI para el sector AFOLU Definition of Emission CO-MADR-151447-CS-INDV Individual Reduction Program and / Profesional Interprete 1 TF / A6377 Post Consultant Open 20,000.00 0.00 Canceled 2020-01-17 2020-01-17 2020-01-17 2020-02-21 2020-11-04 Monitoring, Reporting and (junior) Selection Verification CO-MADR-151444-CS-INDV / Profesional experto tematico para fortalecer capacidades del ideam en analisis de Definition of Emission Individual cambio de uso del suelo , en Reduction Program and TF / A6377 Post Consultant Direct 26,667.00 0.00 Canceled 2020-01-10 2020-01-20 2020-02-10 2020-03-16 2021-03-16 las cateforias claves a ser Monitoring, Reporting and Selection incluidas en la estimacion de Verification liena base , escenario de referencia y los reportes del PRE Page 6 CO-MADR-99656-CS-INDV / Dos analistas de datos que fortalezcan las capacidades Project Coordination, Individual del IDEAM de estimación y TF / A6377 Management, Monitoring and Post Consultant Open 96,000.00 0.00 Canceled 2019-02-25 2019-04-15 2019-05-06 2019-06-10 2019-12-07 reporte de emisiones y Evaluation Selection remociones de GEI para el sector AFOLU CO-MADR-99653-CS-INDV / Consultor senior para la Project Coordination, Individual consolidación coordinada del TF / A6377 Management, Monitoring and Post Consultant Open 100,000.00 0.00 Canceled 2019-02-25 2019-04-15 2019-05-06 2019-06-10 2019-12-07 ER-Program a partir de Evaluation Selection insumos técnicos específicos generados. CO-MADR-99657-CS-INDV / Líder técnico especialista en Actividades agrícolas que Project Coordination, Individual fortalezca las capacidades del TF / A6377 Management, Monitoring and Post Consultant Open 72,000.00 0.00 Canceled 2019-02-25 2019-04-15 2019-05-06 2019-06-10 2019-12-07 IDEAM de estimación y Evaluation Selection reporte, de emisiones y remociones de GEI para el sector AFOLU CO-MADR-157971-CS-INDV / Prestar sus servicios profesionales con autonomía técnica y administrativa, apoyando a la Dirección de Individual Sustainable Land- Use Innovación, Desarrollo TF / A6377 Post Consultant Open 50,000.00 0.00 Canceled 2020-02-06 2020-03-11 2020-03-18 2020-04-01 2020-11-02 Management Tecnológico y Protección Selection Sanitaria del Ministerio de Agricultura y Desarrollo Rural como profesional de apoyo para la formulación Individual CO-MADR-162169-CS-INDV Sustainable Land- Use TF / A6377 Post Consultant Open 19,500.00 14,494.55 Signed 2020-02-28 2020-02-19 2020-03-23 2020-04-16 2020-03-23 2020-04-21 2020-04-10 2020-06-02 2020-08-08 / Profesional Pdeas meta Management Selection Individual CO-MADR-158772-CS-INDV Sustainable Land- Use TF / A6377 Post Consultant Open 19,500.00 14,494.55 Signed 2020-02-28 2020-02-29 2020-03-23 2020-04-16 2020-03-23 2020-04-16 2020-04-10 2020-06-02 2020-08-08 / Profesional P DEAs vichada Management Selection Individual CO-MADR-162170-CS-INDV Sustainable Land- Use TF / A6377 Post Consultant Open 19,500.00 14,549.54 Signed 2020-02-28 2020-03-19 2020-03-23 2020-04-17 2020-03-23 2020-04-23 2020-04-10 2020-06-02 2020-08-08 / Profesional P DEAs Casanare Management Selection Individual CO-MADR-162171-CS-INDV Sustainable Land- Use TF / A6377 Post Consultant Open 19,500.00 14,494.55 Signed 2020-02-28 2020-02-19 2020-03-23 2020-04-21 2020-03-23 2020-04-21 2020-04-10 2020-06-02 2020-08-08 / Profesional P DEAS ARAUCA Management Selection Definition of Emission CO-MADR-143404-CS-INDV Individual Reduction Program and / Apoyo Administrativo - TF / A6377 Post Consultant Open 11,000.00 14,818.43 Signed 2019-10-29 2019-11-29 2019-11-05 2020-04-25 2020-02-14 2020-01-31 2020-02-19 2020-02-17 2020-08-17 Monitoring, Reporting and IDEAM - Primer año Selection Verification Definition of Emission CO-MADR-156564-CS-INDV Individual Reduction Program and / profesional ambiental- TF / A6377 Post Consultant Open 34,000.00 0.00 Canceled 2020-02-20 2020-03-30 2020-04-20 2020-04-30 2021-04-30 Monitoring, Reporting and salvaguardas Selection Verification Definition of Emission CO-MADR-156563-CS-INDV Individual Reduction Program and / profesional social - TF / A6377 Post Consultant Open 34,000.00 0.00 Canceled 2020-02-20 2020-03-30 2020-04-20 2020-04-30 2021-04-30 Monitoring, Reporting and salvaguardas Selection Verification CO-MADR-163818-CS-INDV / Prestar sus servicios profesionales como coordinador del proceso del Definition of Emission estimación y reporte de Reduction Program and emisiones y remociones de GI TF / A6377 Post Direct Selection Direct 46,000.00 27,353.81 Signed 2020-04-14 2020-04-16 2020-04-24 2020-04-20 2020-05-16 2020-06-03 2021-05-16 Monitoring, Reporting and para AFOLU en la Orinoquía, Verification en las categorías relacionadas con actividades agrícolas y su inclusión en el MRV del proyecto CO-MADR-163817-CS-INDV / Prestar sus servicios profesionales, como coordinador del proceso de Definition of Emission estimación y reporte de Reduction Program and emisiones y remociones de GEI TF / A6377 Post Direct Selection Direct 46,000.00 27,353.81 Signed 2020-04-14 2020-04-16 2020-04-24 2020-04-20 2020-05-16 2020-06-03 2021-05-16 Monitoring, Reporting and para el sector AFOLU de la Verification región de la Orinoquía, en las categorías relacionadas con uso y cambios de uso de la tierra CO-MADR-168115-CS-INDV Project Coordination, Individual / Coordinador General del TF / A6377 Management, Monitoring and Post Consultant Open 70,000.00 44,839.76 Signed 2020-04-15 2020-04-21 2020-05-06 2020-05-13 2020-05-11 2020-05-13 2020-05-21 2020-06-12 2020-12-31 Proyecto Evaluation Selection CO-MADR-149179-CS-INDV Project Coordination, Individual / Profesional de Comunicación TF / A6377 Management, Monitoring and Post Consultant Open 18,750.00 0.00 Canceled 2020-02-11 2020-03-31 2020-03-31 2020-05-05 2020-12-25 e intercambio de información Evaluation Selection de los resultados del proyecto Definition of Emission CO-MADR-172096-CS-INDV Individual Reduction Program and / Consultor modelamiento del TF / A6377 Post Consultant Open 21,243.00 19,476.72 Signed 2020-05-04 2020-05-06 2020-05-28 2020-07-10 2020-06-02 2020-07-17 2020-06-17 2020-08-20 2021-06-17 Monitoring, Reporting and riesgo SMByC Selection Verification CO-MADR-172097-CS-INDV Definition of Emission Individual / Experto encargado de la Reduction Program and TF / A6377 Post Consultant Open 22,449.00 32,232.00 Signed 2020-05-04 2020-10-07 2020-05-28 2020-10-28 2020-06-02 2020-10-30 2020-06-17 2021-01-04 2021-06-17 coordinación para elaboración Monitoring, Reporting and Selection del ERPD para la Orinoquia Verification CO-MADR-172098-CS-INDV Definition of Emission Individual / Intérpretes de imágenes Reduction Program and TF / A6377 Post Consultant Open 48,000.00 19,476.72 Signed 2020-05-04 2020-05-06 2020-05-28 2020-07-16 2020-06-02 2020-07-17 2020-06-17 2020-08-20 2021-06-17 satelitales para el Cubo de Monitoring, Reporting and Selection datos de IDEAM (x2) Verification Page 7 CO-MADR-172808-CS-CDS / Consultor junior en suelos gestionados : Prestar sus servicios profesionales apoyando a la Subdirección Definition of Emission Individual del IDEAM, en el proceso de Reduction Program and TF / A6377 Post Consultant Direct 26,000.00 20,673.12 Signed 2020-06-02 2020-06-02 2020-06-12 2020-06-03 2020-06-17 2020-06-03 2020-07-11 2020-07-15 2021-07-11 incorporación de las Monitoring, Reporting and Selection metodologías paraa Verification estimación de las emisiones asociadas a los suelos gestionados en el sector AFOLU Definition of Emission CO-MADR-172107-CS-CDS / Individual Reduction Program and Líder temático del Cubo de TF / A6377 Post Consultant Direct 35,200.00 25,443.84 Signed 2020-06-02 2020-06-02 2020-06-12 2020-06-03 2020-06-17 2020-06-03 2020-07-11 2020-07-15 2021-07-11 Monitoring, Reporting and datos de IDEAM Selection Verification CO-MADR-172800-CS-CDS / Consultor junior para el sector de uso y cambio de uso de la tierra: Hidrología, Definition of Emission Meteorología y Estudios Individual Reduction Program and Ambientales IDEAM, en el TF / A6377 Post Consultant Direct 26,000.00 22,263.36 Signed 2020-06-02 2020-06-02 2020-06-12 2020-06-03 2020-06-17 2020-06-03 2020-07-11 2020-07-15 2021-07-11 Monitoring, Reporting and proceso de estimación y Selection Verification reporte de emisiones y remociones de GEI para el sector AFOLU de la región de la Orinoquía, en las c CO-MADR-172806-CS-CDS / Consultor temático en ganadería: Prestar sus servicios profesionales apoyando a la Subdirección de Definition of Emission Individual Estudios Ambientales del Reduction Program and TF / A6377 Post Consultant Direct 26,000.00 20,673.12 Signed 2020-06-02 2020-06-02 2020-06-12 2020-06-03 2020-06-17 2020-06-03 2020-07-11 2020-07-15 2021-07-11 Instituto de Hidrología, Monitoring, Reporting and Selection Meteorología y Estudios Verification Ambientales IDEAM, en el proceso de ajuste de las metodologías para la estimación CO-MADR-172796-CS-CDS / Consultor junior en actividades agrícolas: Prestar sus servicios profesionales Definition of Emission apoyando a la Subdirección de Individual Reduction Program and Estudios Ambientales del TF / A6377 Post Consultant Direct 26,000.00 22,263.36 Signed 2020-06-02 2020-06-02 2020-06-12 2020-06-03 2020-06-17 2020-06-03 2020-07-11 2020-07-15 2021-07-11 Monitoring, Reporting and Instituto de Hidrología, Selection Verification Meteorología y Estudios Ambientales IDEAM, en el proceso de estimación y reporte de emisiones y Integrated Land- Use CO-MADR-178996-CS-INDV Individual Planning and Improved / Apoyo Administrativo Cartas TF / A6377 Post Consultant Open 4,970.00 3,853.34 Signed 2020-06-10 2020-06-12 2020-07-04 2020-10-09 2020-07-09 2020-10-13 2020-08-06 2020-11-11 2021-01-03 Governance for Deforestation del paisaje UIP-UPRA Selection Control CO-MADR-178997-CS-INDV Integrated Land- Use Individual / Profesional en análisis de Planning and Improved TF / A6377 Post Consultant Open 10,833.00 8,802.95 Signed 2020-06-10 2020-06-12 2020-07-04 2020-07-29 2020-07-09 2020-08-19 2020-08-06 2020-09-17 2021-01-03 sistemas productivos agrícolas Governance for Deforestation Selection del paisaje agropecuario Control CO-MADR-178999-CS-INDV Integrated Land- Use Individual / Profesional en análisis Planning and Improved TF / A6377 Post Consultant Open 12,008.00 9,418.38 Signed 2020-06-10 2020-06-12 2020-07-04 2020-08-05 2020-07-09 2020-08-06 2020-07-24 2020-09-28 2020-12-21 ambiental y Ecológico del Governance for Deforestation Selection paisaje agropecuario Control CO-MADR-179001-CS-INDV Integrated Land- Use Individual / Profesional en comunicación Planning and Improved TF / A6377 Post Consultant Open 10,833.00 8,399.30 Signed 2020-06-10 2020-06-12 2020-07-04 2020-07-29 2020-07-09 2020-08-05 2020-08-06 2020-11-03 2021-01-03 social para el desarrollo del Governance for Deforestation Selection paisaje agropecuario Control CO-MADR-179002-CS-INDV Integrated Land- Use Individual / Profesional en análisis Planning and Improved TF / A6377 Post Consultant Open 12,008.00 9,418.38 Signed 2020-06-10 2020-06-12 2020-07-04 2020-08-03 2020-07-09 2020-08-19 2020-08-06 2020-09-17 2021-01-03 económico del paisaje Governance for Deforestation Selection agropecuario Control Integrated Land- Use CO-MADR-179003-CS-INDV Individual Planning and Improved / Profesional en Ordenamiento TF / A6377 Post Consultant Open 14,355.00 11,258.91 Signed 2020-06-10 2020-06-12 2020-07-04 2020-07-27 2020-07-09 2020-07-28 2020-08-06 2020-09-17 2021-01-03 Governance for Deforestation territorial y prospectiva Selection Control CO-MADR-179004-CS-INDV Integrated Land- Use / Profesional en análisis de Individual Planning and Improved sistemas productivos TF / A6377 Post Consultant Open 10,833.00 8,496.80 Signed 2020-06-10 2020-06-12 2020-07-04 2020-07-29 2020-07-09 2020-07-29 2020-08-06 2020-09-28 2021-01-03 Governance for Deforestation pecuarios del paisaje Selection Control agropecuario CO-MADR-181730-CS-INDV / Gestor Técnico gestión de la Integrated Land- Use información apoyando al Individual Planning and Improved Departamento Nacional de TF / A6377 Post Consultant Direct 34,000.00 0.00 Canceled 2020-06-24 2020-06-29 2020-07-04 2020-07-19 2021-07-19 Governance for Deforestation Planeación, DNP para la Selection Control implementación y seguimiento técnico del componente 1 Definition of Emission CO-MADR-181986-CS-INDV Individual Reduction Program and / Consultor técnico de cambio TF / A6377 Post Consultant Open 32,728.00 28,674.00 Signed 2020-06-25 2020-06-26 2020-07-24 2020-08-26 2020-07-29 2020-08-26 2020-08-20 2020-09-29 2021-08-20 Monitoring, Reporting and climático para el MADS Selection Verification Definition of Emission Individual CO-MADR-181989-CS-INDV Reduction Program and TF / A6377 Post Consultant Open 32,728.00 28,235.52 Signed 2020-06-25 2020-06-26 2020-07-24 2020-08-26 2020-07-29 2020-09-02 2020-08-20 2020-09-28 2021-08-20 / Asesor jurídico y legal Monitoring, Reporting and Selection Verification CO-MADR-182723-CS-INDV / Gestor Técnico gestión de la Integrated Land- Use información apoyando al Individual Planning and Improved Departamento Nacional de TF / A6377 Post Consultant Direct 34,000.00 28,031.64 Signed 2020-06-30 2020-03-12 2020-07-10 2020-05-29 2020-07-15 2020-05-29 2020-08-04 2020-07-15 2021-08-04 Governance for Deforestation Planeación, DNP para la Selection Control implementación y seguimiento técnico del componente 1 CO-MADR-182724-CS-INDV Integrated Land- Use Individual / Profesional experto en Planning and Improved TF / A6377 Post Consultant Open 13,388.00 11,046.58 Signed 2020-07-03 2020-07-16 2020-08-01 2020-09-21 2020-08-06 2020-09-24 2020-08-30 2020-12-17 2021-01-27 desarrollo sostenible bajo en Governance for Deforestation Selection carbono Control Page 8 CO-MADR-184009-CS-INDV Integrated Land- Use Individual / Profesional ecología del Planning and Improved TF / A6377 Post Consultant Direct 13,388.33 31,187.32 Signed 2020-07-15 2020-07-16 2020-07-25 2020-08-14 2020-07-30 2020-08-19 2020-08-23 2020-09-03 2021-01-20 paisaje y sensoramiento Governance for Deforestation Selection remoto Control CO-MADR-190104-CS-CDS / Actualización de los inventarios de GEI con proxys Definition of Emission para los 59 municipios de la Reduction Program and región de la Orinoquía, dentro TF / A6377 Post Direct Selection Direct 85,000.00 84,982.67 Signed 2020-08-24 2020-08-25 2020-09-24 2020-09-28 2020-10-28 2021-02-01 2020-12-27 Monitoring, Reporting and del Componente 3: Verification Preparación del Programa de Reducción de Emisiones y del MRV CO-MADR-190915-CS-INDV / Prestar sus servicios profesionales como consultor SOCIAL de salvaguardas con Definition of Emission autonomía técnica apoyando a Individual Reduction Program and la Unidad Implementadora del TF / A6377 Post Consultant Direct 34,000.00 27,592.02 Signed 2020-08-27 2020-08-31 2020-08-29 2020-08-27 2020-09-03 2020-08-27 2020-10-01 2020-09-28 2021-10-01 Monitoring, Reporting and Proyecto, UIP, al Ministerio de Selection Verification Agricultura y Desarrollo Rural, bajo la orientación del Ministerio de Ambiente y Desarr CO-MADR-194082-CS-INDV / Prestar sus servicios profesionales en la realización de los procesos de adquisiciones y contrataciones Project Coordination, Individual que se requieran, de acuerdo TF / A6377 Management, Monitoring and Post Consultant Direct 47,287.00 40,784.64 Signed 2020-09-17 2020-09-18 2020-09-21 2020-09-16 2020-09-23 2020-09-16 2020-10-12 2020-10-16 2021-10-12 con lo establecido en el Evaluation Selection Acuerdo Legal, el Manual Operativo del Proyecto, el Plan de Adquisiciones y las Regulaciones de CO-MADR-197661-CS-INDV / Prestar sus servicios profesionales con autonomía técnica, apoyando a la Definition of Emission Subdirección de Estudios Individual Reduction Program and Under Ambientales del IDEAM como TF / A6377 Post Consultant Open 21,825.00 0.00 2020-10-21 2020-11-17 2020-11-20 2020-11-20 2020-12-09 2021-12-09 Monitoring, Reporting and Implementation profesional experto para Selection Verification realizar la descarga y procesamiento de imágenes, interpretación digital, validación, reporte y ajustes n CO-MADR-199053-CS-INDV / Prestar sus servicios profesionales apoyando a la Secretaria técnica del Nodo Integrated Land- Use Regional de Cambio Climático Individual Planning and Improved de la Orinoquia – NORECCO TF / A6376 Post Consultant Open 28,991.00 27,892.92 Signed 2020-10-14 2020-12-29 2020-11-14 2021-01-19 2020-11-16 2021-04-10 2020-12-05 2021-05-04 2021-12-05 Governance for Deforestation (CORMACARENA), como Selection Control consultor de apoyo para orientar, implementar y hacer seguimiento a la estrategia de Fortalecimiento d CO-MADR-199054-CS-INDV / consultor de apoyo técnico para la implementación y Integrated Land- Use seguimiento de medidas de Individual Planning and Improved cambio climático territoriales, TF / A6376 Post Consultant Open 100,905.00 85,326.92 Signed 2020-10-14 2021-01-18 2020-11-14 2021-01-21 2020-11-16 2021-04-12 2020-12-05 2021-05-07 2021-12-05 Governance for Deforestation con un enfoque al Selection Control ordenamiento territorial y el fomento de un desarrollo sostenible bajo en carbono (4) CO-MADR-199055-CS-INDV / facilitador para preparar el diseño metodológico, realizar Integrated Land- Use Individual la moderación, desarrollar, Planning and Improved TF / A6376 Post Consultant Open 25,226.00 21,480.47 Signed 2020-10-14 2020-12-29 2020-11-14 2021-02-08 2020-11-16 2021-04-06 2020-12-05 2021-05-07 2021-12-05 analizar, documentar y Governance for Deforestation Selection sistematizar los espacios de Control participación y para la socio construcción del conocimiento CO-MADR-199058-CS-INDV / consultor de apoyo técnico para la implementación y seguimiento de medidas de Integrated Land- Use Individual cambio climático en el Planning and Improved TF / A6376 Post Consultant Open 25,226.00 21,480.47 Signed 2020-10-14 2020-12-29 2020-11-14 2021-02-08 2020-11-16 2021-04-08 2020-12-05 2021-05-07 2021-12-05 ordenamiento territorial, en el Governance for Deforestation Selection cumplimiento de los PIGCCT y Control como enlace de NORECCO en jurisdicción de CORPORINOQUIA, CO-MADR-199069-CS-INDV / Prestar sus servicios como el Profesional en análisis socio- Integrated Land- Use cultural del paisaje Individual Planning and Improved agropecuario, para desarrollar TF / A6376 Post Consultant Direct 10,197.00 8,508.83 Signed 2020-10-09 2020-10-16 2020-10-17 2020-10-13 2020-10-20 2020-10-19 2020-11-08 2020-11-11 2021-04-07 Governance for Deforestation el componente socio-cultural Selection Control de la formulación de las Cartas del paisaje agropecuario. CO-MADR-197659-CS-INDV / Consultor Temático forestal quien prestara sus servicios profesionales en el análisis de Definition of Emission Individual bases de datos de actividad Reduction Program and TF / A6377 Post Consultant Open 25,462.00 0.00 Canceled 2020-10-09 2020-10-16 2020-11-12 2020-11-12 2020-12-01 2021-12-01 alfanuméricos y geográficos Monitoring, Reporting and Selection requeridos para la estimación Verification y el reporte de emisiones y remociones de GEI del sector AFOLU CO-MADR-201159-CS-INDV / Prestar sus servicios profesionales con autonomía técnica y administrativa, apoyando a la UIP y a la Project Coordination, Individual Dirección de Innovación, TF / A6376 Management, Monitoring and Post Consultant Direct 34,781.00 30,823.64 Signed 2020-10-22 2020-11-03 2020-11-01 2020-10-22 2020-11-22 2020-11-25 2020-12-27 2020-11-25 2021-06-25 Desarrollo Tecnológico y Evaluation Selection Protección Sanitaria del MADR como Asesor (a) de Comunicaciones y Participacion Page 9 CO-MADR-200275-CS-INDV / Prestar sus servicios profesionales con autonomía técnica, como ingeniero de Definition of Emission sistemas generando los Individual Reduction Program and desarrollos tecnológicos TF / A6376 Post Consultant Direct 30,121.00 27,234.24 Signed 2020-11-03 2020-11-03 2020-11-09 2020-11-04 2020-11-12 2020-11-04 2020-12-01 2020-12-01 2021-12-01 Monitoring, Reporting and necesarios para la captura, Selection Verification almacenamiento, procesamiento, análisis y divulgación de la información del IFN CO-MADR-200277-CS-INDV / Profesional de Calidad Operación estadística Inventario Forestal Nacional, para la implementación de las Definition of Emission Individual operaciones estadísticas de Reduction Program and TF / A6376 Post Consultant Direct 30,121.00 26,402.88 Signed 2020-11-03 2020-11-03 2020-11-09 2020-11-03 2020-11-12 2020-11-03 2020-12-01 2020-12-01 2021-12-01 USO DE LOS RECURSOS Monitoring, Reporting and Selection FORESTALES- URFN, y de Verification INVENTARIO FORESTAL NACIONAL-IFN, y de los procesos para la interoperabilidad CO-MADR-179000-CS-INDV Integrated Land- Use Individual / Profesional en análisis socio- Planning and Improved TF / A6377 Post Consultant Open 10,833.00 0.00 Canceled 2020-06-10 2020-08-20 2020-07-04 2020-07-09 2020-08-06 2021-01-03 cultural del paisaje Governance for Deforestation Selection agropecuario Control CO-MADR-99660-CS-INDV / Líder técnico de apoyo para la Project Coordination, Individual estimación y el reporte de TF / A6377 Management, Monitoring and Post Consultant Open 78,000.00 0.00 Canceled 2019-04-25 2019-05-14 2019-05-21 2019-06-02 2019-11-29 emisiones y remociones de GEI Evaluation Selection para el sector AFOLU CO-MADR-200276-CS-INDV / Prestar sus servicios profesionales como consultor experto coordinando la Definition of Emission Individual caracterización de las causas y Reduction Program and TF / A6376 Post Consultant Direct 37,021.00 33,143.39 Signed 2020-11-19 2020-11-20 2020-11-25 2020-11-03 2020-11-28 2020-12-17 2020-12-17 2020-12-17 2021-12-17 agentes de la transformación Monitoring, Reporting and Selection del bosque y sus emisiones Verification asociadas, los procesos de modelación y el monitoreo comunitario participativo CO-MADR-201844-CS-INDV / Prestar sus servicios profesionales apoyando a la Subdirección de Estudios Definition of Emission Ambientales del Instituto de Individual Reduction Program and Hidrología, Meteorología y TF / A6376 Post Consultant Direct 25,462.00 23,102.52 Signed 2020-11-19 2020-11-20 2020-11-29 2020-11-20 2020-12-20 2020-11-20 2021-01-24 2020-12-16 2021-07-23 Monitoring, Reporting and Estudios Ambientales IDEAM, Selection Verification en el proceso de incorporación y generación de propuesta metodológica y seguimiento de acciones CO-MADR-178998-CS-INDV Integrated Land- Use Individual / Profesional en análisis socio- Planning and Improved TF / A6377 Post Consultant Open 10,833.00 0.00 Canceled 2020-06-10 2020-08-20 2020-07-04 2020-07-09 2020-08-06 2021-01-03 cultural del paisaje Governance for Deforestation Selection agropecuario Control CO-MADR-205823-CS-CDS / Prestar sus servicios como el Profesional en análisis Integrated Land- Use sociocultural del paisaje Individual Planning and Improved agropecuario, para desarrollar TF / A6376 Post Consultant Direct 10,833.00 8,938.48 Signed 2020-11-27 2020-11-23 2020-12-07 2020-11-23 2020-12-28 2020-11-23 2021-02-01 2021-01-15 2021-07-31 Governance for Deforestation el componente sociocultural Selection Control de la formulación de las Cartas del paisaje agropecuario CO-MADR-208056-CS-INDV / Prestar sus servicios profesionales apoyando a la Subdirección de Estudios Definition of Emission Ambientales del Instituto de Individual Reduction Program and Hidrología, Meteorología y TF / A6376 Post Consultant Limited 25,462.00 23,599.80 Signed 2020-12-10 2020-12-07 2020-12-15 2020-12-15 2021-01-05 2021-01-21 2021-02-09 2021-02-19 2021-08-08 Monitoring, Reporting and Estudios Ambientales IDEAM, Selection Verification en el análisis de bases de datos de actividad alfanuméricos y geográficos requeridos para la est CO-MADR-209804-CS-INDV / Prestar sus servicios como el Profesional en Ordenamiento territorial y prospectiva del Integrated Land- Use paisaje agropecuario, para Individual Planning and Improved apoyar la coordinación de la TF / A6377 Post Consultant Direct 26,107.00 24,198.22 Signed 2020-12-22 2020-12-16 2021-01-01 2020-12-16 2021-01-22 2020-12-17 2021-02-26 2021-01-15 2022-02-26 Governance for Deforestation formulación de la Carta del Selection Control paisaje agropecuario, brindado el enfoque de ordenamiento territorial en todo el pr CO-MADR-197660-CS-INDV / Prestar servicios Definition of Emission Individual profesionales para el el Reduction Program and TF / A6377 Post Consultant Open 164,000.00 0.00 Canceled 2020-10-12 2020-11-20 2020-11-11 2020-11-11 2020-11-30 2021-11-30 control de calidad de datos de Monitoring, Reporting and Selection campo del inventario forestal Verification de la Orinoquia (x5) CO-MADR-211405-CS-INDV / Apoyar al especialista de adquisiciones en la realización de los procesos de adquisiciones y contrataciones Project Coordination, Individual que se requieran, de acuerdo TF / A6376 Management, Monitoring and Post Consultant Direct 23,576.00 21,110.86 Signed 2021-02-08 2021-02-05 2021-02-18 2021-02-05 2021-03-11 2021-02-09 2021-04-15 2021-02-15 2021-10-12 con lo establecido en el Evaluation Selection Acuerdo Legal, el Manual Operativo del Proyecto, el Plan de Adquisiciones y las Regulaciones CO-MADR-215613-CS-INDV / Apoyar al especialista financiero del Proyecto BIOCARBONO en la gestión Project Coordination, Individual financiera del proyecto, de TF / A6376 Management, Monitoring and Post Consultant Direct 23,576.00 21,110.86 Signed 2021-02-08 2021-02-05 2021-02-18 2021-02-05 2021-03-11 2021-02-05 2021-04-15 2021-02-15 2021-10-12 acuerdo con lo establecido en Evaluation Selection el Acuerdo Legal, el Manual Operativo del Proyecto y el Plan de Adquisiciones Page 10 CO-MADR-217660-CS-INDV / Prestar sus servicios personales apoyando a la Unidad de Implementación del Proyecto (UIP) en la Definition of Emission Individual implementación de los Reduction Program and Under TF / A6376 Post Consultant Limited 2,000.00 1,665.34 2021-02-15 2021-02-03 2021-02-20 2021-03-01 2021-03-13 2021-03-08 2021-04-17 2021-10-14 procesos de gestión de Monitoring, Reporting and Implementation Selection conocimiento a partir de la Verification información sobre las prácticas bajas en carbono para las cadenas priorizadas y las p CO-MADR-217665-CS-INDV / Apoyar a la Subdirección de Ecosistemas e Información Ambiental del Instituto de Definition of Emission Hidrología, Meteorología y Individual Reduction Program and Under Estudios Ambientales IDEAM, TF / A6376 Post Consultant Open 50,832.00 0.00 2021-02-22 2021-02-16 2021-04-12 2021-05-03 2021-06-07 2021-12-04 Monitoring, Reporting and Implementation en la verificación de las Selection Verification actividades que adelanten las brigadas en campo para el levantamiento de los conglomerados, d CO-MADR-217669-CS-INDV / Realizar el análisis de información a través de SIG para el soporte al marco Definition of Emission Individual geoestadístico como apoyo a Reduction Program and Under TF / A6376 Post Consultant Limited 54,000.00 0.00 2021-02-22 2021-02-16 2021-02-27 2021-03-20 2021-04-24 2021-10-21 la operación en campo y la Monitoring, Reporting and Implementation Selection generación de cartografía Verification relacionada con la implementación del IFN en la región de la Orinoquia CO-MADR-217672-CS-INDV / Apoyar los procesos de capacitación en los procedimientos metodológicos Definition of Emission del IFN, el análisis de la Individual Reduction Program and Under información, el seguimiento a TF / A6376 Post Consultant Open 24,161.00 0.00 2021-02-22 2021-02-16 2021-04-12 2021-05-03 2021-06-07 2021-12-04 Monitoring, Reporting and Implementation las actividades de campo y al Selection Verification aseguramiento, control de calidad y crítica de los procesos de supervisión propios del IFN CO-MADR-217673-CS-INDV / Consultor desarrollador para Definition of Emission consolidar la nueva plataforma Individual Reduction Program and Under informática que permite la TF / A6376 Post Consultant Open 18,826.00 0.00 2021-02-22 2021-03-15 2021-04-12 2021-05-03 2021-06-07 2021-12-04 Monitoring, Reporting and Implementation captura y administración de Selection Verification datos del Inventario Forestal Nacional - IFN CO-MADR-218247-CS-INDV / Fortalecer las capacidades de la Dirección de Cambio Definition of Emission Climático y Gestión del Riesgo Individual Reduction Program and (DCCGR) del MADS para la TF / A6376 Post Consultant Limited 36,000.00 0.00 Canceled 2021-03-12 2021-03-17 2021-04-07 2021-05-12 2021-11-08 Monitoring, Reporting and formulación, cuantificación, Selection Verification reporte y registro de iniciativas de mitigación de GEI CO-MADR-218248-CS-INDV / Realizar el diseño, validación Definition of Emission metodológica e Individual Reduction Program and Under implementación del sistema TF / A6376 Post Consultant Limited 35,000.00 0.00 2021-02-15 2021-04-05 2021-02-20 2021-03-13 2021-04-17 2021-10-14 Monitoring, Reporting and Implementation de monitoreo, reporte y Selection Verification verificación del sector AFOLU e n la Orinoquia CO-MADR-218249-CS-INDV Definition of Emission Individual / Realizar la identificación de Reduction Program and Under TF / A6376 Post Consultant Limited 35,000.00 15,957.00 2021-02-15 2021-04-05 2021-02-20 2021-04-22 2021-03-13 2021-06-17 2021-04-17 2021-10-14 Beneficios No carbono del Monitoring, Reporting and Implementation Selection ERPD Verification CO-MADR-218255-CS-INDV / Prestar sus servicios profesionales con autonomía técnica, apoyando a la Definition of Emission Subdirección de Estudios Individual Reduction Program and Ambientales del Instituto de TF / A6376 Post Consultant Limited 30,191.00 0.00 Canceled 2021-02-19 2021-02-24 2021-03-17 2021-04-21 2021-10-18 Monitoring, Reporting and Hidrología, Meteorología y Selection Verification Estudios Ambientales IDEAM, en el diseño y validación metodológica del sistema de monitoreo, reporte CO-MADR-199085-CS-INDV / Diseñar la estrategia de interoperabilidad para Integrated Land- Use recopilar y procesar Individual Planning and Improved información espacial y TF / A6376 Post Consultant Open 33,886.00 0.00 Canceled 2021-02-22 2021-03-25 2021-03-27 2021-04-15 2022-04-15 Governance for Deforestation geográfica del área de Selection Control intervención del Proyecto Biocarbono y entidades beneficiarias CO-MADR-218260-CS-INDV / Apoyar la recopilación y Integrated Land- Use Individual procesamiento de información Planning and Improved TF / A6376 Post Consultant Open 23,340.00 0.00 Canceled 2021-02-25 2021-04-15 2021-05-06 2021-06-10 2021-12-07 espacial y geográfica del área Governance for Deforestation Selection de intervención del Proyecto Control Biocarbono, y Minagricultura CO-MADR-201950-CS-INDV / Apoyar la formulación, implementación y seguimiento de estrategias asociadas al Individual Sustainable Land- Use fortalecimiento institucional TF / A6376 Post Consultant Open 36,000.00 0.00 Canceled 2021-02-22 2021-03-23 2021-04-02 2021-05-07 2022-05-07 Management de las mesas de ganadería Selection sostenible de la Orinoquia y su desarrollo sostenible bajo en carbono CO-MADR-201953-CS-INDV / Apoyar el fortalecimiento de las mesas de ganadería Individual sostenible departamentales de Sustainable Land- Use Under TF / A6376 Post Consultant Open 94,000.00 0.00 2021-02-22 2021-03-25 2021-03-23 2021-03-29 2021-04-02 2021-06-18 2021-05-07 2022-05-07 la Orinoquia (Meta, Casanare, Management Implementation Selection Arauca y Vichada) y el desarrollo regional sostenible bajo en carbono Page 11 CO-MADR-218459-CS-INDV / Fortalecer la institucionalidad regional del SNIA (Sistemas Territoriales Individual Innovación, mesas Sustainable Land- Use Under TF / A6376 Post Consultant Limited 25,000.00 0.00 2021-03-01 2021-02-24 2021-03-06 2021-03-27 2021-05-01 2021-10-28 departamentales de C&T, Management Implementation Selection innovación, actualización PECTIA, C&T regalías, supervisión apoyos profesionales PDEA) CO-MADR-218460-CS-INDV / Apoyo para la puesta en Individual Sustainable Land- Use Pending marcha y el seguimiento del TF / A6376 Post Consultant Limited 25,000.00 0.00 2021-03-01 2021-03-06 2021-03-27 2021-05-01 2021-10-28 Management Implementation PIGCC sector agropecuario / Selection NDC 2020 por parte del MADR CO-MADR-218461-CS-INDV / Apoyo seguimiento y Individual Sustainable Land- Use supervisión del proyecto TF / A6376 Post Consultant Limited 25,000.00 22,709.45 Signed 2021-03-01 2021-02-24 2021-03-06 2021-03-02 2021-03-27 2021-04-13 2021-05-01 2021-04-21 2021-10-28 Management BIOCARBONO ORINOQUIA por Selection parte de la DIDTPS CO-MADR-222427-CS-INDV Project Coordination, Individual / Prestar servicios Under TF / A6376 Management, Monitoring and Post Consultant Limited 6,903.00 0.00 2021-03-29 2021-05-26 2021-04-03 2021-04-24 2021-05-29 2021-11-25 profesionales como apoyo Implementation Evaluation Selection administrativo regional CO-MADR-223832-CS-INDV / Prestar sus servicios profesionales con autonomía técnica y administrativa, apoyando a la Dirección de Project Coordination, Individual Innovación, Desarrollo TF / A6376 Management, Monitoring and Post Consultant Limited 21,964.00 0.00 Canceled 2021-03-15 2021-03-17 2021-03-20 2021-04-12 2021-04-10 2021-05-15 2021-11-11 Tecnológico y Protección Evaluation Selection Sanitaria del Ministerio de Agricultura y Desarrollo Rural, como apoyo departamental del Proyecto Biocar CO-MADR-223836-CS-INDV / Prestar sus servicios profesionales con autonomía técnica y administrativa, apoyando a la Dirección de Individual Sustainable Land- Use Under Innovación, Desarrollo TF / A6376 Post Consultant Limited 20,803.00 0.00 2021-03-15 2021-03-10 2021-03-20 2021-03-12 2021-04-10 2021-05-15 2021-11-11 Management Implementation Tecnológico y Protección Selection Sanitaria del Ministerio de Agricultura y Desarrollo Rural como profesional de apoyo para la formulación CO-MADR-222434-CS-INDV / Realizar el análisis del cambio de uso del suelo en las categorías clave a ser incluidas Definition of Emission Individual en la estimación de línea base, Reduction Program and TF / A6376 Post Consultant Direct 3,187.00 0.00 Canceled 2021-03-15 2021-03-09 2021-03-25 2021-04-15 2021-05-20 2021-11-16 escenario de referencia y los Monitoring, Reporting and Selection reportes del programa de Verification reducción de emisiones considerando usos forestales, agrícolas y otros tipos de CO-MADR-224148-CS-INDV / Realizar el análisis del cambio de uso del suelo en las categorías clave a ser incluidas Definition of Emission Individual en la estimación de línea base, Reduction Program and Under TF / A6376 Post Consultant Direct 13,179.00 0.00 2021-03-15 2021-03-10 2021-03-25 2021-03-12 2021-04-15 2021-05-20 2021-11-16 escenario de referencia y los Monitoring, Reporting and Implementation Selection reportes del programa de Verification reducción de emisiones considerando usos forestales, agrícolas y otros tipos de CO-MADR-228016-CS-INDV / Análisis del cambio de uso del suelo en las categorías clave a ser incluidas en la Definition of Emission estimación de línea base, Individual Reduction Program and Under escenario de referencia y los TF / A6376 Post Consultant Direct 19,906.00 0.00 2021-04-12 2021-04-15 2021-04-22 2021-04-27 2021-06-01 2021-11-28 Monitoring, Reporting and Implementation reportes del programa de Selection Verification reducción de emisiones considerando usos forestales, agrícolas y otros tipos de cobertura v CO-MADR-230636-CS-INDV / Prestar sus servicios profesionales con autonomía técnica y administrativa para apoyar a la Unidad Individual Sustainable Land- Use Under Implementadora del Proyecto TF / A6376 Post Consultant Direct 36,000.00 0.00 2021-04-23 2021-04-26 2021-05-03 2021-05-24 2021-06-28 2021-12-25 Management Implementation Biocarbono UIP en la Selection formulación y seguimiento de iniciativas relacionadas con la validación de modelos productivos sostenibles CO-MADR-218262-CS-INDV Integrated Land- Use / Apoyar la recopilación y Individual Planning and Improved procesamiento de información TF / A6376 Post Consultant Open 23,340.00 0.00 Canceled 2021-02-25 2021-04-15 2021-05-06 2021-06-10 2021-12-07 Governance for Deforestation espacial y geográfica del área Selection Control de intervención para la región CO-MADR-218267-CS-INDV Integrated Land- Use Individual / Asesorar la implementación Planning and Improved TF / A6376 Post Consultant Open 31,000.00 0.00 Canceled 2021-03-15 2021-05-03 2021-05-24 2021-06-28 2021-12-25 de estrategia de gobernanza y Governance for Deforestation Selection control de la deforestación Control CO-MADR-218268-CS-INDV Integrated Land- Use / Apoyar la Implementación de Individual Planning and Improved la estrategia de control a la TF / A6376 Post Consultant Open 24,371.00 0.00 Canceled 2021-04-15 2021-06-03 2021-06-24 2021-07-29 2022-01-25 Governance for Deforestation deforestación (uno por foco de Selection Control deforestación) CO-MADR-231537-CS-INDV / Prestar sus servicios profesionales con autonomía técnica y administrativa Integrated Land- Use apoyando al Ministerio de Individual Planning and Improved Under Agricultura y Desarrollo Rural TF / A6376 Post Consultant Limited 33,886.00 0.00 2021-04-30 2021-05-04 2021-05-05 2021-06-02 2021-05-26 2021-06-30 2021-12-27 Governance for Deforestation Implementation (Min agricultura) y a la Unidad Selection Control Implementadora del Proyecto Biocarbono en la gestión y procesamiento de la información espa Page 12 CO-MADR-231548-CS-INDV / Prestar sus servicios profesionales con autonomía técnica y administrativa Integrated Land- Use apoyando al Ministerio de Individual Planning and Improved Under Agricultura y Desarrollo Rural TF / A6376 Post Consultant Limited 23,340.00 0.00 2021-04-30 2021-05-04 2021-05-05 2021-06-02 2021-05-26 2021-06-30 2021-12-27 Governance for Deforestation Implementation (Minagricultura) y la Unidad Selection Control Implementadora del Proyecto Biocarbono UIP como gestor para el desarrollo la estrategia de fo CO-MADR-230654-CS-INDV / Prestar sus servicios profesionales con autonomía técnica y administrativa apoyando al Ministerio de Integrated Land- Use Individual Agricultura y Desarrollo Rural Planning and Improved Under TF / A6376 Post Consultant Limited 42,000.00 0.00 2021-04-26 2021-05-04 2021-05-01 2021-06-02 2021-05-22 2021-06-26 2021-12-23 (Min agricultura) desde Governance for Deforestation Implementation Selection CORPORINOQUIA y o Control CORMACARENA como apoyo técnico para la implementación del Sistema de Información CO-MADR-230658-CS-INDV / Prestar sus servicios como Gestor técnico de gobernanza y control a la deforestación, Integrated Land- Use desde la Dirección de Individual Planning and Improved Under Bosques, Biodiversidad y TF / A6376 Post Consultant Limited 31,000.00 0.00 2021-04-30 2021-05-04 2021-05-05 2021-06-09 2021-05-26 2021-06-30 2021-12-27 Governance for Deforestation Implementation Servicios Ecosistémicos del Selection Control Ministerio de Ambiente y Desarrollo Sostenible, para la formulación, seguimiento y cumplimient CO-MADR-230661-CS-INDV / Apoyar a la Dirección de Bosques, Biodiversidad y Servicios Ecosistémicos del Integrated Land- Use Ministerio de Ambiente y Individual Planning and Improved Under Desarrollo Sostenible, a la TF / A6376 Post Consultant Limited 37,371.00 0.00 2021-04-30 2021-05-04 2021-05-05 2021-05-26 2021-06-30 2021-12-27 Governance for Deforestation Implementation Unidad implementadora del Selection Control Proyecto, y a los respectivos Departamentos en la planeación, programación, ejecución, monitoreo CO-MADR-231771-CS-INDV / Prestar sus servicios profesionales con autonomía técnica y administrativa a la Dirección de Innovación, Individual Sustainable Land- Use Desarrollo Tecnológico y TF / A6376 Post Consultant Limited 10,971.00 10,212.48 Signed 2021-04-30 2021-05-05 2021-05-05 2021-05-07 2021-05-26 2021-06-02 2021-06-30 2021-06-08 2021-12-27 Management Protección Sanitaria del Selection Ministerio de Agricultura y Desarrollo Rural como apoyo operativo para el seguimiento del Proyecto B CO-MADR-232603-CS-INDV / Prestar sus servicios profesionales apoyando a la Unidad Implementadora del Definition of Emission Proyecto UIP, para la Individual Reduction Program and Under construcción del Marco de TF / A6376 Post Consultant Open 22,857.00 0.00 2021-05-07 2021-05-04 2021-06-25 2021-07-16 2021-08-20 2022-02-16 Monitoring, Reporting and Implementation Gestión Ambiental y Social del Selection Verification Programa de Reducción de Emisiones para la Orinoquia, de acuerdo con los lineamientos de la Iniciati CO-MADR-232604-CS-INDV / Prestar sus servicios profesionales con autonomía técnica, apoyando a la Definition of Emission Dirección de Cambio Climático Individual Reduction Program and y Gestión del Riesgo del TF / A6376 Post Consultant Open 22,286.00 0.00 Canceled 2021-05-07 2021-05-31 2021-06-25 2021-07-16 2021-08-20 2022-02-16 Monitoring, Reporting and Ministerio de Ambiente y Selection Verification Desarrollo Sostenible (MADS), en el seguimiento de las acciones y políticas de reducción a la deforest CO-MADR-232605-CS-INDV / Prestar sus servicios profesionales con autonomía técnica y administrativa para apoyar al MADR – Dirección de Individual Sustainable Land- Use Under Innovación, Desarrollo TF / A6376 Post Consultant Limited 24,286.00 0.00 2021-05-07 2021-06-10 2021-05-12 2021-06-02 2021-07-07 2022-01-03 Management Implementation Tecnológico y Protección Selection Sanitaria en el desarrollo de agroecosistemas ganaderos sostenibles bajos en carbono en la Orinoq CO-MADR-234657-CS-INDV / Prestar sus servicios profesionales como Gestor Integrated Land- Use Individual Senior para el seguimiento y Planning and Improved TF / A6376 Post Consultant Direct 24,000.00 22,991.64 Signed 2021-05-19 2021-05-22 2021-05-22 2021-05-26 2021-05-25 2021-05-26 2021-06-04 2021-06-01 2021-12-31 monitoreo del proyecto Governance for Deforestation Selection Desarrollo Sostenible Bajo en Control Carbono en la Región de la Orinoquia CO-MADR-235332-CS-INDV / Prestar sus servicios profesionales con autonomía técnica y administrativa Integrated Land- Use apoyando al Ministerio de Individual Planning and Improved Under Agricultura y Desarrollo Rural TF / A6376 Post Consultant Limited 10,293.00 0.00 2021-05-24 2021-05-28 2021-05-29 2021-06-19 2021-07-24 2022-01-20 Governance for Deforestation Implementation (Min agricultura) y Selection Control específicamente a la Unidad de Planificación Rural Agropecuaria (UPRA) y a la Unidad Implementadora del CO-MADR-234498-CS-INDV / Prestar sus servicios como el Profesional en Ordenamiento territorial y prospectiva del Integrated Land- Use paisaje agropecuario, para Individual Planning and Improved apoyar la coordinación de la TF / A6376 Post Consultant Direct 13,535.00 12,568.61 Signed 2021-05-21 2021-05-22 2021-05-31 2021-05-12 2021-06-21 2021-06-03 2021-07-26 2021-06-21 2022-01-22 Governance for Deforestation formulación de la Carta del Selection Control paisaje agropecuario, brindado el enfoque de ordenamiento territorial en todo el pr Page 13 CO-MADR-237680-CS-INDV Definition of Emission Individual / Profesional análisis Reduction Program and TF / A6376 Post Consultant Limited 12,641.00 0.00 Under Review 2021-06-04 2021-06-22 2021-06-09 2021-06-30 2021-08-04 2022-01-31 distribución de la propiedad Monitoring, Reporting and Selection en la Orinoquia Verification CO-MADR-237682-CS-INDV Definition of Emission / Prestar servicios como Individual Reduction Program and Profesional para el diagnóstico TF / A6376 Post Consultant Limited 12,641.00 0.00 Under Review 2021-06-04 2021-06-22 2021-06-09 2021-06-30 2021-08-04 2022-01-31 Monitoring, Reporting and de la tenencia de la tierra en la Selection Verification Orinoquía CO-MADR-237683-CS-INDV / Prestar sus servicios profesionales con autonomía técnica y administrativa, apoyando a la Dirección de Project Coordination, Individual Under Innovación, Desarrollo TF / A6376 Management, Monitoring and Post Consultant Limited 20,000.00 0.00 2021-06-04 2021-06-11 2021-06-09 2021-06-30 2021-08-04 2022-01-31 Implementation Tecnológico y Protección Evaluation Selection Sanitaria del Ministerio de Agricultura y Desarrollo Rural, como apoyo departamental del Proyecto Biocar CO-MADR-240007-CS-INDV / Prestar sus servicios profesionales con autonomía técnica, apoyando a la Definition of Emission Dirección de Cambio Climático Individual Reduction Program and Under y Gestión del Riesgo del TF / A6376 Post Consultant Limited 24,474.00 0.00 2021-06-18 2021-06-16 2021-06-23 2021-07-14 2021-08-18 2022-08-18 Monitoring, Reporting and Implementation Ministerio de Ambiente y Selection Verification Desarrollo Sostenible (MADS), en el seguimiento de las acciones y políticas de reducción a la deforest Integrated Land- Use CO-MADR-240822-CS-INDV Individual Planning and Improved Pending / Coordinador infraestructura TF / A6376 Post Consultant Limited 39,663.00 0.00 2021-06-28 2021-07-03 2021-07-24 2021-08-28 2022-08-28 Governance for Deforestation Implementation de datos MADR-UPRA Selection Control Definition of Emission Individual CO-MADR-240877-CS-INDV Reduction Program and Under TF / A6376 Post Consultant Direct 13,714.00 0.00 2021-06-22 2021-06-23 2021-07-02 2021-07-23 2021-08-27 2022-02-23 / Consultor mapas biomasa Monitoring, Reporting and Implementation Selection Verification CO-MADR-218462-CS-INDV / Apoyo encadenamientos Individual Sustainable Land- Use productivos y circuitos cortos TF / A6376 Post Consultant Limited 25,000.00 0.00 Canceled 2021-03-01 2021-03-06 2021-03-27 2021-05-01 2021-10-28 Management bajos en carbono & negocios Selection verdes CO-MADR-218276-CS-INDV / Evaluar y consolidar Individual Sustainable Land- Use propuesta de turismo TF / A6376 Post Consultant Open 55,000.00 0.00 Canceled 2021-04-30 2021-06-18 2021-07-09 2021-08-13 2022-02-09 Management sostenible asociado al sector Selection AFOLU CO-MADR-218241-CS-INDV / Prestar sus servicios profesionales como intérprete Definition of Emission Individual junior 1 para análisis de Reduction Program and TF / A6376 Post Consultant Limited 11,000.00 0.00 Canceled 2021-02-15 2021-02-20 2021-03-13 2021-04-17 2021-10-14 cambio de uso del suelo en el Monitoring, Reporting and Selection cubo de datos del Sistema de Verification Monitoreo de Bosques y Carbono (SMByC) del IDEAM CO-MADR-218242-CS-INDV / Consultor individual par el análisis de incertidumbre de Definition of Emission Individual datos de actividad en el grupo Reduction Program and TF / A6376 Post Consultant Limited 25,000.00 0.00 Canceled 2021-02-26 2021-03-03 2021-03-24 2021-04-28 2021-10-25 de Procesamiento Digital de Monitoring, Reporting and Selection Imágenes del Sistema de Verification Monitoreo de Bosques y Carbono (SMByC) del IDEAM CO-MADR-218243-CS-INDV / Consultor desarrollador para análisis de cambio de uso del Definition of Emission Individual suelo en el grupo de Reduction Program and TF / A6376 Post Consultant Limited 28,000.00 0.00 Canceled 2021-02-26 2021-03-03 2021-03-24 2021-04-28 2021-10-25 Procesamiento Digital de Monitoring, Reporting and Selection Imágenes del Sistema de Verification Monitoreo de Bosques y Carbono (SMByC) del IDEAM Page 14 SUMMARY O F PROCUREMENT PLAN Project Preparation Advancement (PPA) Project information: Harmonizing and Improving Statistics in West Africa Project -P169265 Project Implementation agency: Liberia Institute of Statistics and Geo- Information Services (LISGIS) Date of the Procurement Plan: February 3, 2020 Period covered by this Procurement Plan: 3rd February to 31st July 2020 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 1, 2016), revised in November 2017, and August 2018 (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Public Procurement and Concessions Act, 2010 of the Republic of Liberia, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. In accordance with paragraph 5.3 of the Procurement Regulations, the request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. The form of the Letter of Acceptance is attached in Appendix 1. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables. Not Applicable. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: Not Applicable for those contracts identified in the Procurement Plan tables; Works: Not Applicable for those contracts identified in the Procurement Plan tables. Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations: Not Applicable. Other Relevant Procurement Information: - (a). Prior Procurement Arrangements: The Procurement Arrangements as indicated in the below table and within the thresholds indicated in the below tables will be used. The thresholds for the Bank’s prior review requirements are also provided in the table below: Table: Thresholds*, Procurement Arrangements, and Prior Review (The table below depicts the Thresholds and Procurement Methods to be used under the Regional Project for Statistics Thresholds*, Procurement Methods, and Prior Review Contract (C) Value Expenditure Procurement Contracts Subject to No Threshold* [eq. Category Method Prior Review /[eq. US$] USD] All contracts at or above USD Open Competition 5,000,000 are subject to International Market 1 Works C ≥ 5,000,000 Approach and Direct international advertising and the use of the Bank’s SPDs (or other Contracting documents agreed with the Contract (C) Value Expenditure Procurement Contracts Subject to No Threshold* [eq. Category Method Prior Review /[eq. US$] USD] Bank). Open Competition National Market 200,000 < C < 5,000,000 None Approach C ≤ 200,000 RfQ None All contracts at or above USD Open Competition 500,000 are subject to International Market international advertising and the C ≥ 500,000 Approach and Direct use of the Bank’s SPDs (or other Goods, IT and Contracting documents agreed with the 2 non-consulting Bank). services Open Competition 100,000 < C < 500,000 National Market None Approach C ≤ 100,000 RfQ None All contracts at or above USD 100,000 are subject to for international advertising and the C < 100,000 Consulting Services use of the Bank’s SPDs (or other National documents agreed with the shortlist for Bank). 3 selection of All contracts at or above USD consultant firms for 200,000 are subject to Engineering and international advertising and the C ≤ 200,000 Construction use of the Bank’s SPDs (or other Supervision documents agreed with the Bank). Selection of All values ≥ 100,000 4 Individual All Approaches consultants Training, This line activity is not subject to Workshops, Based on approved Procurement Review However, 5 Study Tours All Values Annual Work Plan & each of the activities will be Budgets (AWPB) by TTL cleared with the TTL prior to its implementation. (Special procurement arrangements like direct contracting, use of SOEs, UN Agencies, third party monitors, local NGOs, Force Account, servants needs, results based arrangements. It is not expected that there will be need for prequalification in the procurement arrangements under this Regional Project *These thresholds are for the purposes of the initial procurement plan for the PPA and for first 18 months. The thresholds will be revised periodically based on re- assessment of risks. All contracts not subject to prior review will be post-reviewed. Prequalification. Not expected for the packages of works/goods packages in the procurement plan. Proposed Procedures for CDD Components: Not Applicable Reference to (if any) Project Operational/Procurement Manual: The LISGIS Project Management Team will prepare Procurement manuals. The Procurement Plan will also form part of the Project Implementation Manual. Any Other Special Procurement Arrangements: None Procurement Packages/PLAN with Procurement Arrangements and Time Schedule: as per the Table below: b) PROCUREMENT PLAN Works There are no works under the Project Preparation Advance Goods and Non-Consulting Services 1 2 3 4 5 6 7 8 9 Ref. Contract Estimated Procurement Prequ Nation Revie Expecte Expecte Comment No. (Description) Cost Method alifica al w d bid d s US$ tion Prefer by opening Contrac (yes/n ence Bank date t o) (yes/n (Prior Signatu o) / Post) re Date 1 Procurement of 4 12,100 laptops, 3 No. all- in-1 printers, Limited, RFQ No No Post 28 Feb 4 Mar office desks, a 20 20 projector, metal filing cabinet, and stationery and supplies for project management Consultancy Services 1 2 3 4 5 6 7 8 9 Ref. Description of Estimate Selection Review Expecte Expected Expected Comments No. Assignment d Method/ by Bank d date Contract Completi Cost in Arrangem (Prior / of Signatur on US$ ent Post) proposal e Date submissi Date on 1. Recruitment of a Consultant to draft and validate 10,000 INDV Post 16 Mar 10 Apr 23 Apr ToR to be curricula of the 20 20 20 submitted to IDA Statistics degree & for Review and No CEST Program at Objection. the UL 2. Recruitment of a ToR, performance Financial evaluation, draft Management contract and Officer for Project DS Prior 10 Feb 21 Feb 31 Aug minutes of Management 20 20 20 contract negotiation to be submitted to IDA for Review and No 15,600 Objection. 3. ToR, performance evaluation, draft Recruitment of a contract and Procurement DS Prior 10 Feb 21 Feb 31 Aug minutes of Specialist for 20 20 20 contract Project 18,000 negotiation to be Management submitted to IDA for Review and No Objection. Training and Workshop (Training & Workshop activities are subject to TTL clearance). Estimat Estimated Expected Ref. Training, workshop and ed Cost Duration Training/workshop No. study tours in (Days) Date (US$) Conduct of validation 54,000 workshop and TOT for the GP Feb. 20 to March 1. on the design of 13 2020 questionnaires and enumeration training manual Workshop for cartographic 150,000 Feb. 24 to March 2. field staff training 16 2020 Workshop for enumeration 113,900 3. mapping training April 15, 2020 Study Tours to regional 32,000 countries for first-hand experience on regional March to April 4. harmonization of data 2020 collection, management and communication Workshops on current 50,000 administrative data across 5. April to July 2020 MACs and LISGIS regional offices Workshop to strengthen and 35,000 6. develop institutional capacity April to July 2020 of NSO Workshops for steering 40,000 7. committee on Administrative April to July 2020 Data Workshop for Project 10,000 Steering/Technical 8. Committees for annual work February 2020 plan preparation, review and validation GENERAL NOTES 1. Training and capacity building: Training workshops (including training material and support), conference attendance and study tours, will be carried out based on approved annual training and allied activities plan by the TTL. The beneficiaries, after the training, will be requested to submit a brief report indicating what skills have been acquired and how these skills will contribute to enhance their performance and contribute to the attainment of the Project’s development objective. 2. Operational Costs: These are expenditures incurred by the Recipient to finance: (i) communication technology (including, without limitation, internet and telephone; (ii) per diem and travel expenses of the operational staff performing their responsibilities under the Project; (iii) fuel and vehicle maintenance; (iv) maintenance of equipment; (v) photocopies and publications; (viii) bank commissions; and (ix) utilities and office supplies as defined in the FA. Appendix 1 Letter of Acceptance of the World Bank’s Anti-Corruption Guidelines and Sanctions Framework Date: Invitation of Bids/Proposals No.__________ To: ___________________________________________________________________________ We, along with our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not) consultants and personnel, acknowledge and agree to abide by the World Bank’s policy regarding Fraud and Corruption (corrupt, fraudulent, collusive, coercive, and obstructive practices), as set out and defined in the World Bank’s Anti-Corruption Guidelines1 in connection with the procurement and execution of the contract (in case of award), including any amendments thereto. We declare and warrant that we, along our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not), consultants and personnel, , are not subject to, and are not controlled by any entity or individual that is subject to, a temporary suspension, early temporary suspension, or debarment imposed by a member of the World Bank Group, including, inter alia, a cross-debarment imposed by the World Bank Group as agreed with other international financial institutions (including multilateral development banks), or through the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement. Further, we are not ineligible under the laws or official regulations of [Insert name of Employer as per bidding document] or pursuant to a decision of the United Nations Security Council. We confirm our understanding of the consequences of not complying with the World Bank’s Anti-Corruption Guidelines, which may include the following: a. rejection of our Proposal/Bid for award of contract; 1Guidelines on Preventing and Combating Fraud and Corruption in Projects Financed by International Bank for Reconstruction and Development Loans and the International Development Agency Credits and Grants, dated October 15, 2006, and revised in January 2011 and July 2016, as they may be revised from time to time. b. in the case of award, termination of the contract, without prejudice to any other remedy for breach of contract; and c. sanctions, pursuant to the Bank’s Anti-corruption Guidelines and in accordance with its prevailing sanctions policies and procedures as set forth in the Bank’s Sanctions Framework. This may include a public declaration of ineligibility, either indefinitely or for a stated period of time, (i) to be awarded or otherwise benefit from a Bank-financed contract, financially or in any other manner;2 (ii) to be a nominated3 sub-contractor, consultant, manufacturer or supplier, or service provider of an otherwise eligible firm being awarded a Bank-financed contract; and (iii) to receive the proceeds of any loan made by the Bank or otherwise to participate further in the preparation or implementation of any Bank-financed project. We understand that we may be declared ineligible as set out above upon: a. completion of World Bank Group sanctions proceedings according to its prevailing sanctions procedures; b. cross-debarment as agreed with other international financial institutions (including multilateral development banks); c. the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement; or d. temporary suspension or early temporary suspension in connection with an ongoing World Bank Group sanctions proceeding. For avoidance of doubt, the foregoing effects of ineligibility do not extend to a sanctioned firm’s or individual’s execution of its ongoing Bank-financed contracts (or its ongoing sub-agreements under such contracts) that are not the subject of a material modification, as determined by the Bank. We shall permit, and shall cause our sub-contractors, sub-consultants, agents (whether declared or not), personnel, consultants, service providers or suppliers, to 2 For the avoidance of doubt, a sanctioned party’s ineligibility to be awarded a contract shall include, without limitation, (i) applying for pre-qualification, expressing interest in a consultancy, and bidding, either directly or as a nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider, in respect of such contract, and (ii) entering into an addendum or amendment introducing a material modification to any existing contract. 3 A nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider (different names are used depending on the particular bidding document) is one which has been: (i) included by the bidder in its pre-qualification application or bid because it brings specific and critical experience and know-how that allow the bidder to meet the qualification requirements for the particular bid; or (ii) appointed by the Borrower. permit the Bank to inspect4 all accounts, records, and other documents relating to the procurement process and/or contract execution (in the case of award), and to have them audited by auditors appointed by the Bank. We agree to preserve all accounts, records, and other documents (whether in hard copy or electronic format) related to the procurement and execution of the contract. Name of the Bidder/Consultant: Name of the person duly authorized to sign the Bid/Proposal on behalf of the Bidder/Consultant: Title of the person signing the Letter: 4 Inspections in this context are usually investigative (i.e., forensic) in nature: they involve fact-finding activities undertaken by the Bank or persons appointed by the Bank to address specific matters related to investigations/audits, such as evaluating the veracity of an allegation of possible Fraud and Corruption, through the appropriate mechanisms. Such activity includes but is not limited to accessing and examining a firm's or individual's financial records and information, and making copies thereof as relevant; accessing and examining any other documents, data, and information (whether in hard copy or electronic format) deemed relevant for the investigation/audit, and making copies thereof as relevant; interviewing staff and other relevant individuals; performing physical inspections and site visits; and obtaining third-party verification of information. PROCUREMENT Western Africa : Harmonizing and Improving Statistics in West Africa PLAN General Information Country: Western Africa Bank’s Approval Date of the Original Procurement Plan: 2020-03-22 2021-05-20 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P169265 GPN Date: 2021-05-19 Project Name: Harmonizing and Improving Statistics in West Africa Loan / Credit No: IDA / 65730, IDA / 65760 H Executing Agency(ies): armonizing and Improving Statistics in West Africa - Ghana WORKS Procureme Activity Reference No. / Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH nt Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) Justification for Award Type Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Regional component: Harmonization, Data GP/GSS/HISWAP/PPA/TPFB/05 Collection, Quality Request for Single Stage - One /20 / Supply of Field bags for IDA / 65730 Post Open - National 0.00 Canceled 2020-02-14 2020-03-15 2020-04-14 Improvement, Dissemination Quotations Envelope trial census PES - 70 pcs and Use of Core Social and Economic Statistics Regional component: Harmonization, Data GP/GSS/HISWAP/PPA/TPRC/0 Collection, Quality Request for Single Stage - One 4/20 / Supply of Rain coats IDA / 65730 Post Open - National 0.00 Canceled 2020-02-16 2020-03-22 2020-05-21 Improvement, Dissemination Quotations Envelope for trial census PES - 70 and Use of Core Social and Economic Statistics Regional component: GP/GSS/HISWAP/PPA/TPRJ/07 Harmonization, Data /20 / Supply of Reflective Collection, Quality Request for Single Stage - One IDA / 65730 Post Open - National 0.00 Canceled 2020-02-14 2020-03-04 2020-04-03 Jackets for trial census PES - Improvement, Dissemination Quotations Envelope 70 pcs and Use of Core Social and Economic Statistics Regional component: Harmonization, Data GP/GSS/HISWAP/PPA/TPBC/08 Collection, Quality Request for Single Stage - One /20 / Supply of Branded Caps IDA / 65730 Post Open - National 0.00 Canceled 2020-02-16 2020-03-29 2020-06-27 Improvement, Dissemination Quotations Envelope for trial census PES - 70 pcs and Use of Core Social and Economic Statistics GP/GSS/HISWAP/PPA/TPTM/0 Regional component: 9/20 / Training Materials for Harmonization, Data Trial Census PES (Manuals - Collection, Quality Request for Single Stage - One 70, Flip Charts -5, Markers- IDA / 65730 Post Open - National 0.00 Canceled 2020-02-14 2020-03-09 2020-03-18 Improvement, Dissemination Quotations Envelope 5, Chalks-5pkt, Pens - and Use of Core Social and 5pkt,Notepads-70, Folders- Economic Statistics 70, ID Accessories -70, etc) Regional component: GP/GSS/HISWAP/PPA/MCBC/1 Harmonization, Data 0/20 / Supply of Branded Collection, Quality Single Stage - One Caps for Training field IDA / 65730 Post Request for Bids Open - National 66,898.35 Completed 2020-01-30 2020-01-17 2020-02-04 2020-03-05 2020-02-07 2020-03-26 2020-03-10 2020-04-30 2020-05-07 2020-08-28 2020-10-02 Improvement, Dissemination Envelope Practice and field work - and Use of Core Social and 70,000 pcs Economic Statistics Regional component: GP/GSS/HISWAP/PPA/MCNP/1 Harmonization, Data 1/20 / Supply of Notepad for Collection, Quality Request for Single Stage - One IDA / 65730 Post Open - National 48,611.11 Completed 2020-02-04 2020-03-24 2020-05-07 2020-06-22 2020-09-23 Training of Census Improvement, Dissemination Quotations Envelope Enumerators - 70,000 and Use of Core Social and Economic Statistics Regional component: GP/GSS/HISWAP/PPA/MCRC/1 Harmonization, Data 4/20 / Procurement of Collection, Quality Single Stage - One Raincoats for Training Field IDA / 65730 Post Request for Bids Open - National 315,030.42 Completed 2020-01-31 2020-01-16 2020-02-05 2020-03-06 2020-02-11 2020-03-27 2020-05-18 2020-05-01 2020-07-20 2020-07-30 2021-01-22 Improvement, Dissemination Envelope Practice and field work - and Use of Core Social and 70,000 Economic Statistics Regional component: GP/GSS/HISWAP/PPA/MCTB/1 Harmonization, Data 5/20 / Procurement of Collection, Quality Tablets for Census training, IDA / 65730 Prior Direct Selection Direct 0.00 Canceled 2020-01-30 2020-02-04 2020-03-03 2020-07-01 Improvement, Dissemination field practice and field work - and Use of Core Social and 20,000 pcs Economic Statistics Regional component: GP/GSS/HISWAP/PPA/MCRJ/1 Harmonization, Data 6/20 / Supply of Reflective Collection, Quality Single Stage - One Jackets for Census Training IDA / 65730 Post Request for Bids Open - National 164,205.04 Completed 2020-01-31 2020-02-17 2020-02-05 2020-03-06 2020-02-07 2020-03-27 2020-03-10 2020-05-01 2020-05-12 2020-08-29 2020-10-02 Improvement, Dissemination Envelope Field Practice and Field work - and Use of Core Social and 70,000 Economic Statistics GP/GSS/HISWAP/PPA/STN/17/ Project Management and Request for Single Stage - One 20 / Stationery for IDA / 65730 Post Open - National 0.00 Canceled 2020-04-04 2020-05-30 2020-06-29 Monitoring and Evaluation Quotations Envelope preparatory meetings Regional component: Harmonization, Data GP/HISWAP/GSS/MC/TAB/001 Collection, Quality /20 / Procurement of 35,000 IDA / 65730 Prior Direct Selection Direct 5,600,000.00 Signed 2020-02-07 2020-08-31 2020-02-10 2020-09-07 2020-03-05 2020-09-09 2020-04-24 Improvement, Dissemination Tablets and Power Banks and Use of Core Social and Economic Statistics Regional component: GP/HISWAP/GSS/MC/TAB/002 Harmonization, Data /20 / Procurement of 35,000 Collection, Quality IDA / 65730 Prior Direct Selection Direct 3,159,800.00 Completed 2020-02-07 2020-08-31 2020-02-11 2020-09-09 2020-03-08 2020-09-11 2020-04-27 2020-10-13 Tablets and Power Banks Improvement, Dissemination under direct contracting and Use of Core Social and Economic Statistics Page 1 GP/HISWAP/GSS/DM/LP/003/ Country-Specific Component: 20 / Procurement of 800 Improving and modernizing Single Stage - One Laptops for training and IDA / 65730 Post Request for Bids Open - National 723,801.33 Completed 2020-02-07 2020-01-20 2020-02-12 2020-03-13 2020-02-10 2020-04-03 2020-03-17 2020-05-08 2020-06-15 2020-08-06 2020-12-22 physical and statistical Envelope Census Data Monitoring (High infrastructure End Xtra ) Regional component: GP/HISWAP/GSS/MC/FB/004/ Harmonization, Data 20 / Procurement of Fieldbags Collection, Quality Single Stage - One IDA / 65730 Post Request for Bids Open - National 273,391.54 Completed 2020-02-20 2020-03-04 2020-02-25 2020-03-26 2020-03-27 2020-04-16 2020-05-14 2020-05-14 2020-07-17 2020-08-12 2021-01-21 for Main Census field work - Improvement, Dissemination Envelope 62,000 and Use of Core Social and Economic Statistics Regional component: GP/HISWAP/GSS/PES/FB/034/ Harmonization, Data 20 / Procurement of Fieldbags Collection, Quality Request for Single Stage - One IDA / 65730 Post Open - National 0.00 Canceled 2020-10-17 2020-11-28 2021-02-26 for PES CAPI and Manual - Improvement, Dissemination Quotations Envelope 300 and Use of Core Social and Economic Statistics Regional component: GH/GSS/HISWAP/GP/UN/TB/0 Harmonization, Data 1/20 / Procurement of Collection, Quality UN Agencies Tablets for Census training, IDA / 65760 Prior Direct 3,295,091.18 Completed 2020-09-21 2020-10-01 2020-09-26 2020-10-27 2020-10-29 2020-11-06 2021-02-26 2021-03-31 Improvement, Dissemination (Direct) field practice and field work - and Use of Core Social and 20,000 pcs Economic Statistics Country-Specific Component: GP/GSDP2/GSS/VEH/015/20 Improving and modernizing Single Stage - One / Procurement of Vehicles (For IDA / 65730 Prior Request for Bids Open - National 1,321,334.03 Signed 2020-11-30 2020-11-26 2020-12-05 2020-12-09 2021-01-04 2021-01-22 2021-01-25 2021-02-09 2021-03-01 2021-03-26 2021-05-30 physical and statistical Envelope GLSS -25, Pick ups - 6) infrastructure Regional component: CS/PHC/HISWAP/PHC/CC/004 Harmonization, Data /20 / Design, Supply and Collection, Quality Request for Single Stage - One IDA / 65760 Post Open - National 0.00 Canceled 2020-11-15 2020-12-14 2021-02-12 Installation of Call Center Improvement, Dissemination Quotations Envelope equipment and Use of Core Social and Economic Statistics GD/PHC/HISWAP/WLC/001/2 Regional component: 0 / Supply of Wireless LAN Harmonization, Data Controller and other Collection, Quality Request for Single Stage - One IDA / 65760 Post Open - National 17,709.00 Completed 2020-10-21 2020-11-25 2020-10-16 2020-12-16 2020-12-18 equipment for the Improvement, Dissemination Quotations Envelope provisioning of 2020PHC and Use of Core Social and Tablets Economic Statistics Regional component: GP/GSS/HISWAP/PPA/MCID/0 Harmonization, Data 6/20 / Procurement of 70,000 Collection, Quality Single Stage - One ID Cards for Census IDA / 65730 Post Request for Bids Open - National 0.00 Canceled 2020-02-28 2020-03-04 2020-04-03 2020-04-17 2020-05-22 2020-08-20 Improvement, Dissemination Envelope Enumerators Training and and Use of Core Social and field work Economic Statistics Regional component: GP/HISWAP/MOTCA/TQ/031/ Harmonization, Data Pending 20 / Printing of Collection, Quality Request for Single Stage - One IDA / 65730 Post Open - National 0.00 Implementati 2022-02-05 2022-05-22 2022-08-20 Questionnaires for Tourism Improvement, Dissemination Quotations Envelope on Arrival Receipt - 2,000 and Use of Core Social and Economic Statistics Regional component: GD/GSS/HISWAP/CP/WS/072/ Harmonization, Data 20 / Supply of additional Collection, Quality IDA / 65760 Prior Direct Selection Direct 0.00 Canceled 2021-05-31 2021-06-05 2021-07-10 2022-01-06 Digital Weighing Scales, and Improvement, Dissemination Spare Parts and Use of Core Social and Economic Statistics Regional component: GP/HISWAP/GSS/CPI/WS/024/ Harmonization, Data 20 / Procurement of Digital Collection, Quality Request for Single Stage - One IDA / 65730 Post Open - National 33,994.74 Completed 2021-09-05 2021-11-07 2021-04-08 2022-02-05 2021-05-27 Weighing Scale and Improvement, Dissemination Quotations Envelope Accessories for CPI and Use of Core Social and Economic Statistics Regional component: GP/HISWAP/GSS/PPI/FL/022/2 Harmonization, Data 0 / Supply Logistics for Collection, Quality Request for Single Stage - One Fieldwork for Rebasing of PPI IDA / 65730 Post Open - National 0.00 Canceled 2021-10-05 2021-12-07 2021-12-13 Improvement, Dissemination Quotations Envelope (e.g. satchels, pencils, and Use of Core Social and clipboards, etc.) Economic Statistics Regional component: GP/HISWAP/GSS/NA/AOC/011 Harmonization, Data Pending /20 / Procurement of One-in- Collection, Quality Request for Single Stage - One IDA / 65730 Post Open - National 0.00 Implementati 2021-09-05 2021-10-31 2021-12-30 all desktop computers for Improvement, Dissemination Quotations Envelope on National Accounts - 10 pcs and Use of Core Social and Economic Statistics GP/HISWAP/GSS/RE/019/20 / Country-Specific Component: Pending Recording Equipment (Digital Improving and modernizing Request for Single Stage - One IDA / 65730 Post Open - National 0.00 Implementati 2022-03-05 2022-05-07 2022-07-06 Camera - 2, Video Camera - physical and statistical Quotations Envelope on 2, Voice Recorder - 3) infrastructure GP/HISWAP/GSS/MC/VEH/005 Country-Specific Component: /20 / Procurement of vehicles Improving and modernizing Single Stage - One IDA / 65730 Post Request for Bids Open - National 0.00 Canceled 2022-03-31 2022-04-05 2022-05-05 2022-05-26 2022-06-30 2022-09-28 for 2020PHC (Robust 4X4-16, physical and statistical Envelope Saloon-5) infrastructure GP/HISWAP/GSS/GLSS8/DS/03 Country-Specific Component: 8/20 / Procurement of Market Improving and modernizing Request for Single Stage - One IDA / 65730 Post Open - National 0.00 Canceled 2022-09-05 2022-10-24 2023-01-22 Digital Scales for GLSS8 - 130 physical and statistical Quotations Envelope pcs infrastructure Country-Specific Component: GP/HISWAP/GSS/SWC/021/20 Pending Improving and modernizing Request for Single Stage - One / Supply and Fixing of Swivel IDA / 65730 Post Open - National 0.00 Implementati 2021-12-05 2022-02-06 2022-04-07 physical and statistical Quotations Envelope Chairs - 70 pieces on infrastructure Country-Specific Component: GP/HISWAP/GSS/CT/018/20 Pending Improving and modernizing Request for Single Stage - One / Procurement of Car Tyres IDA / 65730 Post Open - National 0.00 Implementati 2021-10-30 2022-01-01 2022-03-02 physical and statistical Quotations Envelope for HISWAP - 30 pieces on infrastructure Page 2 Country-Specific Component: GP/HISWAP/GSS/DDE/020/20 Improving and modernizing Single Stage - One / Procurement of Document IDA / 65730 Post Request for Bids Open - National 0.00 Canceled 2021-11-30 2021-12-05 2022-01-04 2022-01-25 2022-03-01 2022-05-30 physical and statistical Envelope Digitization Equipment infrastructure Country-Specific Component: GP/HISWAP/GSS/GLSS8/FDC/ Improving and modernizing Request for Single Stage - One 04020 / Furnishing of Data IDA / 65730 Post Open - National 0.00 Canceled 2022-03-05 2022-04-16 2022-07-15 physical and statistical Quotations Envelope Processing Centre infrastructure Regional component: GP/GSS/HISWAP/PPA/PB/BC/2 Harmonization, Data 0/20 / Supply of Branded Collection, Quality Request for Single Stage - One Caps for Census Official for IDA / 65730 Post Open - National 0.00 Canceled 2021-01-06 2021-03-03 2021-06-01 Improvement, Dissemination Quotations Envelope publicity and launching - and Use of Core Social and 3,900 pcs Economic Statistics Regional component: Harmonization, Data GP/HISWAP/MOE/BPD/028/20 Pending Collection, Quality Request for Single Stage - One / Procurement of Branded Pen IDA / 65730 Post Open - National 0.00 Implementati 2022-03-05 2022-04-30 2022-05-09 Improvement, Dissemination Quotations Envelope Drives - 300 on and Use of Core Social and Economic Statistics GP/HISWAP/GSS/GLSS8/CT/0 Project Management and Request for Single Stage - One 45/20 / Procurement of Car IDA / 65730 Post Open - National 0.00 Canceled 2022-05-04 2022-07-06 2022-09-04 Monitoring and Evaluation Quotations Envelope Tyre for GLSS8 - 570 pcs Regional component: GP/GSS/HISWAP/PPA/MCF/12 Harmonization, Data /20 / Supply of Folders for Collection, Quality Single Stage - One IDA / 65730 Post Request for Bids Open - National 0.00 Canceled 2021-01-11 2021-01-16 2021-02-15 2021-03-08 2021-04-12 2021-07-11 Training of Census Improvement, Dissemination Envelope Enumerators - 70,000 and Use of Core Social and Economic Statistics Regional component: GP/HISWAP/GSS/IBES/LF/042/ Harmonization, Data 20 / Procurement of Field Collection, Quality Request for Single Stage - One Logistics for IBES Fieldwork IDA / 65730 Post Open - National 0.00 Canceled 2022-04-05 2022-05-31 2022-08-29 Improvement, Dissemination Quotations Envelope (e.g. satchels, pencils, and Use of Core Social and clipboards, etc.) Economic Statistics Regional component: Harmonization, Data GP/HISWAP/GSS/IBES/IR/046/ Collection, Quality Request for Single Stage - One 20 / Printing of IBES Reports IDA / 65730 Post Open - National 0.00 Canceled 2021-12-20 2022-02-07 2022-02-16 Improvement, Dissemination Quotations Envelope (employment, job creation etc) and Use of Core Social and Economic Statistics GP/HISWAP/GSS/GLSS8/L&S/0 Regional component: 36/20 / Procurement of Harmonization, Data Logistics and Stationery for Collection, Quality Request for Single Stage - One GLSS8 fieldwork and mapping IDA / 65730 Post Open - National 0.00 Canceled 2021-10-05 2021-11-23 2022-02-21 Improvement, Dissemination Quotations Envelope activities (Raincoats, and Use of Core Social and fieldbags, solar lamp, field Economic Statistics boots etc) Regional component: Harmonization, Data GP/HISWAP/MOH/HSR/029/2 Pending Collection, Quality Request for Single Stage - One 0 / Printing of Health Survey IDA / 65730 Post Open - National 0.00 Implementati 2022-03-05 2022-04-30 2022-07-29 Improvement, Dissemination Quotations Envelope Report -200 on and Use of Core Social and Economic Statistics Regional component: Harmonization, Data GP/HISWAP/MOTCA/TRP/032 Collection, Quality Request for Single Stage - One /20 / Printing of Tourism IDA / 65730 Post Open - National 0.00 Canceled 2022-07-05 2022-08-23 2022-11-21 Improvement, Dissemination Quotations Envelope Report - 200 and Use of Core Social and Economic Statistics Regional component: GP/HISWAP/GSS/IBES/QM/043 Harmonization, Data /20 / Printing of Collection, Quality Request for Single Stage - One IDA / 65730 Post Open - National 0.00 Canceled 2022-03-05 2022-04-30 2022-05-01 Questionnaires and Manuals Improvement, Dissemination Quotations Envelope for IBES - 8,000 for IBES and Use of Core Social and Economic Statistics Regional component: GP/HISWAP/GSS/IBES/LE/044/ Harmonization, Data 20 / Procurement of Logistics Collection, Quality Request for Single Stage - One and Equipment for or IBES ( IDA / 65730 Post Open - National 0.00 Canceled 2022-03-05 2022-04-23 2022-07-22 Improvement, Dissemination Quotations Envelope Toners 10, External Drives - and Use of Core Social and 4, A4 Ppapers - 300 bx Economic Statistics Regional component: Harmonization, Data GP/HISWAP/GSS/MC/PR/035/ Pending Collection, Quality Request for Single Stage - One 20 / Printing of Census IDA / 65730 Post Open - National 0.00 Implementati 2022-01-05 2022-02-16 2022-05-17 Improvement, Dissemination Quotations Envelope Reports on and Use of Core Social and Economic Statistics Regional component: GP/HISWAP/BDR/RF/026/20 Harmonization, Data Pending / Printing and delivery of Birth Collection, Quality Request for Single Stage - One IDA / 65730 Post Open - National 0.00 Implementati 2022-04-04 2022-05-23 2022-08-21 and Death Registeration Improvement, Dissemination Quotations Envelope on Forms - 103,000 and Use of Core Social and Economic Statistics Regional component: GP/HISWAP/GSS/IBES/PF/041/ Harmonization, Data 20 / Printing of Posters - Collection, Quality Request for Single Stage - One IDA / 65730 Post Open - National 0.00 Canceled 2022-06-05 2022-07-31 2022-10-29 5000, and Flyers - 10,000 for Improvement, Dissemination Quotations Envelope IBES and Use of Core Social and Economic Statistics Regional component: GP/HISWAP/BDR/HS/033/20 Harmonization, Data Pending / Printing of Hologram Collection, Quality Request for Single Stage - One IDA / 65730 Post Open - National 0.00 Implementati 2022-07-05 2022-08-23 2022-11-21 Stickers for Birth and Death - Improvement, Dissemination Quotations Envelope on 100,000 and Use of Core Social and Economic Statistics Page 3 GP/HISWAP/GIS/FSU/030/20 Country-Specific Component: / Furnishing of Statistics Units Pending Improving and modernizing Request for Single Stage - One of Ghana Immigration IDA / 65730 Post Open - National 0.00 Implementati 2022-07-05 2022-08-16 2022-11-14 physical and statistical Quotations Envelope statistical offices across the on infrastructure country GP/HISWAP/GSS/GLSS8/IE/03 Regional component: 9/20 / Procurement of IT Harmonization, Data Equipment for or GLSS8 Collection, Quality Request for Single Stage - One (Notebook Computers - 30, IDA / 65730 Post Open - National 0.00 Canceled 2022-07-05 2022-08-23 2022-11-21 Improvement, Dissemination Quotations Envelope Power Banks - 160, CDR-500, and Use of Core Social and External Drives - 30, Flash Economic Statistics Drives - 500) Regional component: Harmonization, Data GP/GSS/HISWAP/PPA/SM/19/ Collection, Quality Request for Single Stage - One 20 / Printing of Supervisors IDA / 65730 Post Open - National 0.00 Canceled 2021-01-23 2021-02-20 2021-03-22 Improvement, Dissemination Quotations Envelope Manuals - 18,400 and Use of Core Social and Economic Statistics Country-Specific Component: GP/HISWAP/GSS/AC/016/20 Pending Improving and modernizing Request for Single Stage - One / Supply and Fixing of 80 Air- IDA / 65730 Post Open - National 0.00 Implementati 2021-09-05 2021-11-07 2022-02-05 physical and statistical Quotations Envelope conditioners on infrastructure GP/GSS/HISWAP/PPA/LP/03/2 Country-Specific Component: 0 / Procurement of 124 Improving and modernizing Laptops for training and use IDA / 65730 Post Request for Bids 0.00 Canceled 2021-03-15 2021-03-20 2021-04-19 2021-05-03 2021-05-31 2021-08-29 physical and statistical by 552 Census Data Monitors infrastructure (High End Xtra ) Regional component: GSS/HISWAP/GP/CTQ/RFQ/00 Harmonization, Data 2/21 / Printing of Collection, Quality Request for Single Stage - One IDA / 65760 Post Open - National 0.00 Canceled 2021-06-05 2021-07-10 2021-08-09 questionnaires for 20121PHC Improvement, Dissemination Quotations Envelope main training and Use of Core Social and Economic Statistics Regional component: Harmonization, Data GP/GSS/HISWAP/PPA/PM/18/ Collection, Quality Single Stage - One 20 / Printing of Field Officers IDA / 65730 Post Request for Bids Open - National 0.00 Canceled 2021-05-31 2021-06-05 2021-07-05 2021-07-26 2021-08-30 2021-10-19 Improvement, Dissemination Envelope Manuals - 80,000 and Use of Core Social and Economic Statistics Regional component: Harmonization, Data GP/GIS/HISWAP/DMS/39/21 Pending Collection, Quality Single Stage - One / Procurement of Digital IDA / 65760 Post Request for Bids Open - National 0.00 Implementati 2021-06-30 2021-07-05 2021-08-16 2021-09-15 2021-10-20 2021-10-29 Improvement, Dissemination Envelope Mobile Shelve on and Use of Core Social and Economic Statistics GP/HISWAP/GSS/MDA/VEH/04 Country-Specific Component: Under 0/21 / Procurement of Improving and modernizing Single Stage - One IDA / 65760 Post Request for Bids Open - National 0.00 Implementati 2021-07-30 2021-05-11 2021-08-04 2021-05-12 2021-09-15 2021-10-15 2021-11-19 2022-05-18 vehicles for HISWAP (Pickups- physical and statistical Envelope on 7, Mobile Registration Van-8) infrastructure Regional component: GP/HISWAP/GSS/CPI/LP/016/ Harmonization, Data Pending 21 / Procurement of Laptop Collection, Quality Request for Single Stage - One IDA / 65760 Post Open - National 0.00 Implementati 2021-07-05 2021-08-30 2022-02-26 computers with high speed Improvement, Dissemination Quotations Envelope on processor - 3 and Use of Core Social and Economic Statistics Regional component: GP/HISWAP/GSS/MC/FST/007 Harmonization, Data /20 / Printing of Stickers for Collection, Quality Single Stage - One IDA / 65730 Post Request for Bids Open - National 0.00 Canceled 2021-05-31 2021-06-05 2021-07-05 2021-07-26 2021-08-30 2021-09-08 Main Census field work - Improvement, Dissemination Envelope 5,000,000 and Use of Core Social and Economic Statistics Regional component: GP/HISWAP/MOE/ASCQ/027/ Harmonization, Data 20 / Printing and delivery Collection, Quality Request for Single Stage - One IDA / 65730 Post Open - National 41,582.13 Signed 2021-04-20 2021-06-22 2021-05-04 2021-12-19 questionnaires for Annual Improvement, Dissemination Quotations Envelope School Census - 53688 and Use of Core Social and Economic Statistics GP/HISWAP/GSS/SOL/012/20 / Procurement of Stationery and office logistics for HISWAP Project Management and Request for Single Stage - One IDA / 65760 Post Open - National 0.00 Canceled 2021-05-04 2021-05-24 2021-06-23 activities ( A4 Sheets, Pens, Monitoring and Evaluation Quotations Envelope Toners, Note pads, Arc Files etc) GP/GSS/HISWAP/PPA/CA/01/ 20 / Computers and Accessories to set up Census Country-Specific Component: offices (Desktop computers- Improving and modernizing Request for Single Stage - One IDA / 65730 Post Open - National 0.00 Canceled 2021-06-05 2021-07-24 2021-10-22 18, Workstation-4 UPS-18 physical and statistical Quotations Envelope printers-8, Toners-100, infrastructure External Drive-90, Copier Toners - 20, Flash Drives-70) GP/HISWAP/GSS/PHC/LDC/01 Country-Specific Component: Under 8/21 / Procurement of Improving and modernizing Single Stage - One IDA / 65760 Post Request for Bids Open - National 0.00 Implementati 2021-06-30 2021-05-10 2021-07-11 2021-05-12 2021-08-10 2021-09-09 2021-10-14 2021-12-13 Laptops - 312 units for 2021 physical and statistical Envelope on PHC infrastructure Regional component: GP/GSS/HISWAP/PPA/PB/BPS/ Harmonization, Data 20/20 / Supply of Branded Under Collection, Quality Request for Polo Shirts and Polo Caps for IDA / 65730 Post 0.00 Implementati 2021-06-12 2021-07-24 2021-10-22 Improvement, Dissemination Quotations Census Official for publicity on and Use of Core Social and and launching - 5,000 pcs Economic Statistics Regional component: GD/GSS/HISWAP/PHCL/CK/00 Harmonization, Data 1/21 / Procurement of Chalks Collection, Quality Request for Single Stage - One IDA / 65760 Post Open - National 92,040.66 Signed 2021-05-08 2021-06-10 2021-05-27 2021-06-13 for 2021PHC Listing Activities Improvement, Dissemination Quotations Envelope - 2,600 boxes and Use of Core Social and Economic Statistics Page 4 GP/HISWAP/GSS/ITE/014/20 / Procurement IT Equipment Country-Specific Component: for GSDP (Computers and UPS Pending Improving and modernizing Single Stage - One -203, Laptops -130, Servers - IDA / 65730 Post Request for Bids Open - National 0.00 Implementati 2021-08-20 2021-08-25 2021-09-24 2021-10-15 2021-11-19 2022-03-19 physical and statistical Envelope 21, Printers - 78, Scanners - on infrastructure 50, Photocopiers - 47, EHD - 102, Projectors - 40 ) Regional component: GP/HISWAP/GSS/DP/DKC/013 Harmonization, Data Under /20 / Procurement of High Collection, Quality Request for Single Stage - One IDA / 65730 Post Open - National 0.00 Implementati 2021-06-05 2021-07-31 2021-09-29 End Laptop Computers for Improvement, Dissemination Quotations Envelope on PHC Data Processing - 10 pcs and Use of Core Social and Economic Statistics GP/GSS/HISWAP/PHC/PTM/00 Regional component: 2/21 / Printing of Training Harmonization, Data materials for 2021PHC Collection, Quality Request for Single Stage - One Regional training IDA / 65760 Post Open - National 81,590.21 Signed 2021-05-07 2021-06-09 2021-05-27 2021-06-23 Improvement, Dissemination Quotations Envelope (Questionnaires - 9,500, and Use of Core Social and Trainers Guide - 8,000, Economic Statistics Manuals - 9,500). Regional component: GP/HISWAP/GSS/CPI/WS/023/ Harmonization, Data Pending 20 / Procurement of CPI work Collection, Quality Request for Single Stage - One IDA / 65730 Post Open - National 0.00 Implementati 2021-10-05 2021-12-07 2022-03-07 station with video conference Improvement, Dissemination Quotations Envelope on facilities and Use of Core Social and Economic Statistics GP/GSS/HISWAP/PPA/MCMT/1 Regional component: 3/20 / Materials for field work Harmonization, Data and training of Census Under Collection, Quality Request for Single Stage - One Enumerators (Flip Charts - IDA / 65730 Post Open - National 0.00 Implementati 2021-07-05 2021-08-30 2021-11-28 Improvement, Dissemination Quotations Envelope 1,900 pieces, A4 Papers - 562 on and Use of Core Social and boxes, Markers - 10,000 pcs, Economic Statistics Pens - 1,470pkts etc) GP/HISWAP/GSS/PPE/PHC/RT/ 09/21 / Procurement of PPEs Regional component: and Sanitary items for Harmonization, Data 2021PHC Regional Training Collection, Quality Request for Single Stage - One IDA / 65760 Post Open - National 6,518.00 Signed 2021-06-05 2021-07-10 2021-06-07 2021-07-31 activities (Face mask - 1,280 Improvement, Dissemination Quotations Envelope pkts, sanitizers - 100 gallons, and Use of Core Social and Tissue papers - 2,912packs Economic Statistics etc) Regional component: GP/HISWAP/GSS/MC/PB/010/ Harmonization, Data Under 20 / Printing of Banners for Collection, Quality Request for Single Stage - One IDA / 65730 Post Open - National 0.00 Implementati 2020-02-14 2020-03-18 2020-04-17 2021PHC Publicity and Improvement, Dissemination Quotations Envelope on Education - 2,750 pcs and Use of Core Social and Economic Statistics Regional component: Harmonization, Data GP/GSS/HISWAP/PHC/OTG/10 Collection, Quality Request for Single Stage - One /21 / Procurement of OTG IDA / 65760 Post Open - National 7,997.65 Signed 2021-07-05 2021-08-12 2021-05-26 2021-08-26 Improvement, Dissemination Quotations Envelope flash drives - 816 pieces and Use of Core Social and Economic Statistics Regional component: GP/HISWAP/GSS/PHC/CCS/01 Harmonization, Data 1/21 / Supply, Design and Collection, Quality Request for Single Stage - One IDA / 65760 Post Open - National 14,102.39 Signed 2021-06-05 2021-07-17 2021-06-14 2021-08-07 installation of Call Centre Improvement, Dissemination Quotations Envelope Services for 2021HC and Use of Core Social and Economic Statistics Regional component: GP/GSS/HISWAP/PHC/FM/012 Harmonization, Data /21 / Procurement of Face Under Collection, Quality Request for Single Stage - One Masks for 2021PHC main IDA / 65760 Post Open - National 0.00 Implementati 2021-07-05 2021-09-06 2021-09-20 Improvement, Dissemination Quotations Envelope training of the field officers - on and Use of Core Social and 15,300 packets Economic Statistics GP/HISWAP/GSS/PHC/HSLS/0 Regional component: 13/21 / Procurement of Hand Harmonization, Data Under Sanitizers - 76500 bottles Collection, Quality Request for Single Stage - One IDA / 65760 Post Open - National 0.00 Implementati 2021-06-20 2021-08-13 2021-08-27 (200ml) and Liquid soaps - Improvement, Dissemination Quotations Envelope on 65,500 gallons for 2021PHC and Use of Core Social and Main training - Economic Statistics GP/HISWAP/GSS/PHC/TS/014 Regional component: /21 / Procurement of Tissue Harmonization, Data Under Papers for (drying of hands) Collection, Quality Request for Single Stage - One IDA / 65760 Post Open - National 0.00 Implementati 2021-06-20 2021-08-13 2021-08-27 for 2021PHC main training of Improvement, Dissemination Quotations Envelope on the field officers - 3,160 and Use of Core Social and packets Economic Statistics Regional component: GP/HISWAP/GSS/PHC/TRL/01 Harmonization, Data 5/21 / Procurement of T - Pending Collection, Quality Request for Single Stage - One Rolls for 2021PHC main IDA / 65760 Post Open - National 0.00 Implementati 2021-08-04 2021-09-27 2021-10-11 Improvement, Dissemination Quotations Envelope training of field officers - on and Use of Core Social and 15,300 packets Economic Statistics Regional component: GP/HISWAP/GSS/MC/S&F/008 Harmonization, Data /20 / Printing of Brochures - Under Collection, Quality Request for Single Stage - One 200,000 copies, Stickers - IDA / 65730 Post Open - National 0.00 Implementati 2021-06-07 2021-08-09 2021-08-23 Improvement, Dissemination Quotations Envelope 100,000 copies for Census on and Use of Core Social and Publicity and Education Economic Statistics Regional component: Harmonization, Data GP/GSS/HISWAP/PHC/CBC/00 Under Collection, Quality Request for Single Stage - One 6/21 / Printing and Supply of IDA / 65760 Post Open - National 0.00 Implementati 2021-06-05 2021-07-31 2021-08-14 Improvement, Dissemination Quotations Envelope Call back cards for 2021PHC on and Use of Core Social and Economic Statistics GP/HISWAP/MOE/PR/038/21 Regional component: / Printing of questionnaires Harmonization, Data for Ministry of Education Pending Collection, Quality Request for Single Stage - One Annual School Census (Basic, IDA / 65760 Post Open - National 0.00 Implementati 2021-09-05 2021-10-31 2021-11-30 Improvement, Dissemination Quotations Envelope SHS, Technical, Management) on and Use of Core Social and for 216 Districts - 93,000 Economic Statistics copies Page 5 Regional component: GD/PHC/HISWAP/PID/001/20 Harmonization, Data Under / Printing of ID Cards for Collection, Quality Request for Single Stage - One IDA / 65760 Post Open - National 0.00 Implementati 2021-06-06 2021-08-01 2021-08-22 2021PHC Enumerators and Improvement, Dissemination Quotations Envelope on Supervisors and Use of Core Social and Economic Statistics Regional component: GP/HISWAP/GSS/MC/PP/009/ Harmonization, Data Under 20 / Printing of Poster for Collection, Quality Request for Single Stage - One IDA / 65730 Post Open - National 0.00 Implementati 2021-06-06 2021-07-28 2021-08-18 Main Census Publicity and Improvement, Dissemination Quotations Envelope on Education - 100,000 pcs and Use of Core Social and Economic Statistics Regional component: GP/GSS/HISWAP/PHC/CT/003 Harmonization, Data Under /21 / Procurement of Car Collection, Quality Request for Single Stage - One IDA / 65760 Post Open - National 0.00 Implementati 2021-06-25 2021-08-27 2021-09-17 Tyres and batteries foe Improvement, Dissemination Quotations Envelope on Census field work operations and Use of Core Social and Economic Statistics Regional component: GP/GSS/HISWAP/CCTV/CC/PH Harmonization, Data Under C/012/21 / Supply and Collection, Quality Request for Single Stage - One IDA / 65760 Post Open - National 4,629.27 Implementati 2021-06-12 2021-08-12 2021-09-02 Installation of CCTV at the Improvement, Dissemination Quotations Envelope on 2021PHC Call Center and Use of Core Social and Economic Statistics Country-Specific Component: GP/HISWAP/GSS/SFTA/017/2 Pending Improving and modernizing Request for Single Stage - One 0 / Procurement of Software - IDA / 65730 Post Open - National 0.00 Implementati 2022-01-05 2022-03-09 2022-06-07 physical and statistical Quotations Envelope 15 and Antivirus - 38 on infrastructure Regional component: GP/HISWAP/GSS/PHC/PCM/01 Harmonization, Data Pending 5/21 / Supply of Packing and Collection, Quality Request for Single Stage - One IDA / 65760 Post Open - National 0.00 Implementati 2021-12-22 2022-01-24 2022-02-23 Covering Materials and for Improvement, Dissemination Quotations Envelope on 2021 PHC and Use of Core Social and Economic Statistics GP/GSS/HISWAP/PO/ITE/015/ 21 / Procurement of ICT equipment for HISWA Project Pending Project Management and Request for Single Stage - One offices (Laptops - 10 units, IDA / 65760 Post Open - National 0.00 Implementati 2021-10-05 2021-11-21 2021-12-21 Monitoring and Evaluation Quotations Envelope Printers - 5 units, Scanners - on Photocopies - 2, Com-biding Machine - 3) Regional component: GP/GSS/HISWAP/PHC/FB/016/ Harmonization, Data Pending 21 / Procurement of Collection, Quality Request for Single Stage - One IDA / 65760 Post Open - National 0.00 Implementati 2021-06-25 2021-07-29 2021-08-12 Additional Field Bags for Improvement, Dissemination Quotations Envelope on 2021PHC - 5,000 pieces and Use of Core Social and Economic Statistics Regional component: GP/GSS/HISWAP/PHC/NP/017 Harmonization, Data /21 / Procurement of Pending Collection, Quality Request for Single Stage - One Additional Notepads for IDA / 65760 Post Open - National 0.00 Implementati 2021-06-26 2021-08-05 2021-08-19 Improvement, Dissemination Quotations Envelope 2021PHC Field work - 5,000 on and Use of Core Social and units Economic Statistics Regional component: GP/GSS/HISWAP/PHC/ALP/01 Harmonization, Data Pending 8/21 / Procurement Collection, Quality IDA / 65760 Post Direct Selection Direct 0.00 Implementati 2021-06-17 2021-06-22 2021-07-25 2021-08-08 Additional laptops for Improvement, Dissemination on 2021PHC Data processing and Use of Core Social and Economic Statistics Regional component: GP/GSS/HISWAP/PHC/ATB/01 Harmonization, Data 9/21 / Procurement of Pending Collection, Quality Additional Tablets for IDA / 65760 Post Direct Selection Direct 0.00 Implementati 2021-06-15 2021-06-20 2021-07-16 2021-08-15 Improvement, Dissemination 2021PHC field work - 7,000 on and Use of Core Social and units Economic Statistics Regional component: GP/GSS/HISWAP/PHC/EC/019 Harmonization, Data /21 / Printing of 2021PHC Pending Collection, Quality Request for Single Stage - One Certificate of Enumeration for IDA / 65760 Post Open - National 0.00 Implementati 2021-06-25 2021-08-25 2021-09-08 Improvement, Dissemination Quotations Envelope Census Night - 500,000 on and Use of Core Social and copies Economic Statistics GP/GSS/HISWAP/PPA/OC/02/ 20 / Office equipment and Consumables to set up Census Offices (Office Desk & Country-Specific Component: Pending Swivel Chairs -20, Desk Trays- Improving and modernizing Request for Single Stage - One IDA / 65730 Post Open - National 0.00 Implementati 2021-10-05 2021-11-30 2021-12-30 32, Computers - 5 Perforaters physical and statistical Quotations Envelope on 20, Staplers - 50, Staple Pins infrastructure - 50Pkt, Externa HD- 5, Arc Files -100, Shredders - 10, Kettles -5, etc) Regional component: GP/GSS/HISWAP/PHC/PAM/02 Harmonization, Data Pending 0/21 / Printing of additional Collection, Quality Request for Single Stage - One IDA / 65760 Post Open - National 0.00 Implementati 2021-06-25 2021-08-18 2021-09-01 field officer's manual to be Improvement, Dissemination Quotations Envelope on used as on the field - 5,000 and Use of Core Social and Economic Statistics Regional component: GP/GSS/HISWAP/PHC/FL/022/ Harmonization, Data Pending 21 / Printing of Flyers for Collection, Quality Request for Single Stage - One IDA / 65760 Post Open - National 0.00 Implementati 2021-06-23 2021-08-02 2021-09-01 2021PHC School Census Improvement, Dissemination Quotations Envelope on Programme - 50,000 copies and Use of Core Social and Economic Statistics Regional component: GP/GSS/HISWAP/PHC/ARJ/023 Harmonization, Data /21 / Procurement of Pending Collection, Quality Request for Single Stage - One additional Reflective Jackets IDA / 65760 Post Open - National 0.00 Implementati 2021-07-05 2021-08-14 2021-09-13 Improvement, Dissemination Quotations Envelope for 2021PHC Enumerators - on and Use of Core Social and 5,000 pieces Economic Statistics Page 6 Regional component: GP/GSS/HISWAP/PHC/NM/025 Harmonization, Data Pending /21 / Procurement Nose Mask Collection, Quality Request for Single Stage - One IDA / 65760 Post Open - National 0.00 Implementati 2021-06-30 2021-08-09 2021-09-08 for 2021PHC Field work - Improvement, Dissemination Quotations Envelope on 100,000 boxes and Use of Core Social and Economic Statistics Regional component: GP/GSS/HISWAP/PHC/HS/026 Harmonization, Data /21 / Procurement of Hand Pending Collection, Quality Request for Single Stage - One Sanitizers (100ml) for IDA / 65760 Post Open - National 0.00 Implementati 2021-06-30 2021-08-09 2021-09-08 Improvement, Dissemination Quotations Envelope 2021PHC field work - 50,000 on and Use of Core Social and bottles Economic Statistics NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Regional component: Harmonization, Data GSS/HISWAP/NC/PCI/DS/001/ Collection, Quality 21 / Engagement of Public IDA / 65760 Prior Direct Selection Direct 137,465.39 Signed 2021-01-04 2020-12-25 2021-01-09 2021-01-29 2021-01-30 2021-02-18 2021-02-20 Improvement, Dissemination Cloud Infrastructure Provider and Use of Core Social and Economic Statistics CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Regional component: CS/HISWAP/GSS/DBCI/012/20 Harmonization, Data / Designing and building of a Consultant Collection, Quality resilient and reliable private IDA / 65760 Post Qualification Open - National 0.00 Canceled 2020-10-16 2020-03-03 2020-11-06 2020-12-04 2020-10-06 2021-01-03 2021-01-31 2021-04-01 Improvement, Dissemination cloud infrastructure for GSS to Selection and Use of Core Social and support Censuses and Surveys Economic Statistics INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Contract Type Process Status Teams of Reference Identified/Selected Signed Contract Contract Completion No. (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Regional component: Harmonization, Data CS/HISWAP/GSS//PHC/CP/00 Individual Collection, Quality 2/20 / Consultant to develop IDA / 65730 Post Consultant Open 9,438.01 Signed 2020-02-07 2019-10-15 2020-03-11 2019-12-20 2020-03-25 2019-12-20 2020-04-15 2019-12-20 2020-07-14 Improvement, Dissemination Citizen Platform Selection and Use of Core Social and Economic Statistics Regional component: Harmonization, Data CS/HISWAP/GSS//PHC/CC/00 Individual Collection, Quality 4/20 / Consultant to establish IDA / 65730 Post Consultant Open 0.00 Canceled 2020-02-28 2020-04-01 2020-04-15 2020-05-13 2020-08-11 Improvement, Dissemination 2020 PHC Call Center Selection and Use of Core Social and Economic Statistics Regional component: CS/HISWAP/GSS//PHC/LMS/0 Harmonization, Data Individual 03/20 / Consultant to Collection, Quality IDA / 65730 Post Consultant Open 9,438.01 Signed 2020-02-20 2020-01-07 2020-03-24 2020-03-10 2020-04-07 2020-03-11 2020-05-05 2020-03-16 2020-08-03 develop Logistics Improvement, Dissemination Selection Management Systems and Use of Core Social and Economic Statistics Regional component: Harmonization, Data CS/HISWAP/GSS//CPIS/005/2 Individual Collection, Quality 0 / Consultant to upgrade CPI IDA / 65730 Post Consultant 0.00 Canceled 2021-05-20 2021-06-24 2021-07-08 2021-08-12 2021-11-10 Improvement, Dissemination Software Selection and Use of Core Social and Economic Statistics Regional component: CS/HISWAP/GSS//PHC/EB/001 Harmonization, Data Individual /20 / Upgrade and deploy a Collection, Quality IDA / 65730 Post Consultant Open 13,663.54 Signed 2019-10-10 2020-09-09 2019-11-15 2020-10-14 2019-12-06 2020-10-29 2020-02-18 2020-11-17 2020-04-18 customized enumerators Improvement, Dissemination Selection bureau and Use of Core Social and Economic Statistics Regional component: Harmonization, Data CS/HISWAP/GIS/P/CAPI/010/ Individual Collection, Quality 20 / Consultant to develop IDA / 65730 Post Consultant Open 0.00 Canceled 2021-02-26 2021-04-16 2021-05-07 2021-06-11 2021-06-20 Improvement, Dissemination CAPI for data collection Selection and Use of Core Social and Economic Statistics Regional component: CS/HISWAP/GSS/AGRIS/SMP/0 Harmonization, Data 07/20 / Sampling Consultant Individual Collection, Quality Pending (International)- professional IDA / 65730 Post Consultant Open 0.00 2022-04-25 2022-05-28 2022-06-11 2022-07-09 2022-07-18 Improvement, Dissemination Implementation fees (remote sensing survey Selection and Use of Core Social and specialist) for AGRIS Economic Statistics Regional component: Harmonization, Data CS/HISWAP/GSS/CPI/RB/008/ Individual Collection, Quality Pending 20 / Consultant to Review the IDA / 65730 Post Consultant Open 0.00 2022-04-25 2022-05-28 2022-06-11 2022-07-09 2022-10-07 Improvement, Dissemination Implementation CPI Rebase (local) Selection and Use of Core Social and Economic Statistics Regional component: CS/HISWAP/MOGCSP/P/CAPI/ Harmonization, Data 011/20 / Consultant to Individual Collection, Quality Pending develop dissemination IDA / 65730 Post Consultant Open 0.00 2022-06-30 2022-08-18 2022-09-08 2022-10-13 2023-01-11 Improvement, Dissemination Implementation /communication Plan for Selection and Use of Core Social and Gender Statistics Economic Statistics Page 7 Regional component: Harmonization, Data CS/HISWAP/GSS/AGRIS/SMP/0 Individual Collection, Quality Pending 09/20 / Consultant to Review IDA / 65730 Post Consultant Open 0.00 2022-07-25 2022-08-27 2022-09-10 2022-10-15 2023-01-13 Improvement, Dissemination Implementation the PBCI Selection and Use of Core Social and Economic Statistics Regional component: CS/GSS/HISWAP/CSW/IND/00 Harmonization, Data Individual 1/21 / Consultancy for CSWeb Collection, Quality IDA / 65760 Post Consultant Open 26,055.29 Signed 2021-06-11 2021-04-20 2021-07-14 2021-05-19 2021-07-28 2021-05-31 2021-08-18 2021-05-21 2021-09-02 Server Implementation and Improvement, Dissemination Selection Deployment for 2021 PHC and Use of Core Social and Economic Statistics CS/HISWAP/GSS/SEEA/006/20 Regional component: / Consultant for Compilation Harmonization, Data of Environment Statistics Individual Collection, Quality Pending using SEEA on Forestry, IDA / 65730 Post Consultant Open 0.00 2021-09-30 2021-11-02 2021-11-16 2021-12-14 2022-03-14 Improvement, Dissemination Implementation Fisheries, Water, and Selection and Use of Core Social and Environmental goods and Economic Statistics services Page 8 PROCUREMENT PLAN (Textual Part) Project information: Sao Tome and Principe - WACA Resilience Investment Project - P162337 Project Implementation agency: Ministry of Public Works and Natural Resources, Directorate General of Environment Date of the Procurement Plan: July 2017 Period covered by this Procurement Plan: July 1st 2017 to June 30th, 2018 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Regulamento de Licitação e Contratações Publicas such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables: Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables: Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable for those contracts identified in the Procurement Plan tables; Works: is not applicable for those contracts identified in the Procurement Plan tables Other Relevant Procurement Information.: Not Applicable PROCUREMENT Western Africa : West Africa Coastal Areas Resilience Investment Project PLAN General Information Country: Western Africa Bank’s Approval Date of the Original Procurement Plan: 2018-02-19 2021-06-01 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P162337 GPN Date: 2017-12-29 Project Name: West Africa Coastal Areas Resilience Investment Project Loan / Credit No: IDA / V1150, IDA / D2860, IDA / 62130, TF / A7130, TF / A7131 M Executing Agency(ies): inistry of Environnement/Directorate of Environment WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned 39 / Aménagement de Component 4: National Single Stage - One 2019-02- bureaux pour l’unité de IDA / V1150 Post Request for Bids Open - National 90,000.00 81,133.59 Terminated 2018-05-07 2018-04-06 2018-05-12 2018-06-23 2018-05-07 2018-07-23 2018-05-26 2018-08-27 2018-08-29 Coordination Envelope 23 gestion du projet WACA 59 / Travaux d'aménagement du R+1 des bureaux pour l'UGP, Construction du mur de séparation, d'un parking pour 10 voitures, un poste Component 4: National Single Stage - One 2020-04- IDA / D2860 Post Request for Bids Open - National 190,000.00 0.00 Canceled 2019-06-27 2019-07-02 2019-08-13 2019-09-12 2019-10-17 d'hébergement (des Coordination Envelope 14 compteurs et du groupe électrogène) et aménagement de la cour (aires de circulation et jardin) 85 / Travaux d’aménagement de la cour du Ministère de Component 2: Strengthening l'environnement, du Request for Single Stage - One 2021-01- IDA / D2860 the Policy and Institutional Post Limited 105,000.00 126,079.40 Signed 2020-05-19 2020-04-24 2020-07-14 2020-08-28 développement durable et de Quotations Envelope 10 Framework la protection de la nature - en un (01) lot 114 / Travaux de construction de la clôture de Pending Component 4: National Request for Single Stage - One 2020-12- la direction régionale des IDA / D2860 Post Open - National 70,000.00 0.00 Implementat 2020-07-14 2020-09-08 Coordination Quotations Envelope 08 forestiers de la réserve de ion Togodo Nord à ATAKPAME 88 / Travaux d'aménagement Pending du R+1 des bureaux pour Component 4: National Request for Single Stage - One 2021-03- IDA / D2860 Post Limited 152,728.00 0.00 Implementat 2020-07-12 2020-09-06 l'UGP WACA ResIP, en lot Coordination Quotations Envelope 05 ion unique 104 / Travaux de protection Component 3: Strengthening d’urgence de la côte par la 2021-02- IDA / D2860 National Physical and Social Post Direct Selection Direct 909,090.90 899,211.65 Signed 2020-07-08 2020-07-03 2020-07-13 2020-08-19 2020-08-17 2020-09-17 technique de juxtaposition de 13 Investments puits en fûs granulitique. TG-WACA TOGO-204666- Component 3: Strengthening Pending CW-RFB / Réhabilitation de 90 Single Stage - One 2021-08- TF / A7130 National Physical and Social Post Request for Bids Open - National 210,606.00 0.00 Implementat 2021-01-06 2021-01-11 2021-02-10 2021-03-12 2021-04-16 km de piste, 7 ponceaux et 15 Envelope 14 Investments ion radiers à Togodo TG-WACA TOGO-204668- Component 3: Strengthening Request for Single Stage - One 2021-04- CW-RFQ / Construction de TF / A7131 National Physical and Social Post Limited 30,000.00 0.00 Canceled 2021-01-20 2021-03-18 Quotations Envelope 17 deux (02) bâtiments à Investments TOGODO TG-WACA TOGO-204671- Component 3: Strengthening CW-RFQ / Travaux de Request for Single Stage - One 2021-09- TF / A7130 National Physical and Social Post Limited 60,000.00 0.00 Canceled 2021-01-25 2021-03-22 construction de deux (02) Quotations Envelope 18 Investments étangs et de deux (02) forages à TOGODO Component 2: Strengthening 92 / Travaux de construction Request for Single Stage - One 2021-02- IDA / D2860 the Policy and Institutional Post Limited 106,000.00 0.00 Canceled 2020-07-01 2020-08-26 du siège de l'ANGE Quotations Envelope 22 Framework TG-WACA TOGO-222964- National CW-RFQ / renforcement Component 3: Strengthening Procurement Pending (travaux de réhabilitation) du Request for Single Stage - One 2022-04- IDA / D2860 National Physical and Social Post Open - National Document - 1 109,000.00 0.00 Implementat 2021-07-20 2021-10-07 poste secours d'urgence (PSR) Quotations Envelope 05 Investments Envelope process ion du corps des sapeurs - (Non Bank-SPD) pompiers de la Région de Lomé Nord TG-WACA TOGO-239057- CW-RFB / construction de National trois (03) postes de relais Component 2: Strengthening Procurement Pending forestiers équipés de Single Stage - One 2022-02- TF / A7130 the Policy and Institutional Post Request for Bids Open - National Document - 1 90,000.00 0.00 Implementat 2021-07-23 2021-07-28 2021-08-27 2021-09-26 2021-10-31 panneaux solaires et de Envelope 28 Framework Envelope process ion forages à motricité humaine (Non Bank-SPD) dans le complexe d’aires protégées de Togodo. GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 35 / Acquisition de matériels Component 4: National Request for Single Stage - One IDA / V1150 Post Limited 15,000.00 0.00 Canceled 2018-05-13 2018-07-08 2019-01-04 informatiques Coordination Quotations Envelope 37 / Acquisition du mobilier Component 4: National Request for Single Stage - One de bureau pour la IDA / V1150 Post Limited 25,000.00 23,847.22 Signed 2018-07-17 2018-09-03 2018-09-11 2018-10-25 2019-03-10 Coordination Quotations Envelope coordination du projet Page 1 34 / Achat de fournitures de bureau, matériels de bureau et matériels d'entretien de bureau en 03 lots. Lot 1 fournitures de bureau Component 4: National Request for Single Stage - One IDA / V1150 Post Limited 10,000.00 7,637.09 Signed 2018-02-03 2018-02-16 2018-03-31 2018-08-08 2018-09-27 (papiers rames, bics,..) Coordination Quotations Envelope Lot 2 matériels de bureau (reliure) et Lot 3 matériels d'entretien de bureau (gel désinfectant, ...). 35 BIS / Acquisition de fournitures informatiques et de matériels informatiques en 02 lots : Lot 1 fournitures informatiques (cartouches Component 4: National Request for Single Stage - One IDA / V1150 Post Limited 27,000.00 26,469.61 Signed 2018-01-09 2018-01-11 2018-03-06 2018-08-08 2018-09-02 d'encre, antivirus, disques Coordination Quotations Envelope durs) et Lot 2 matériels informatiques (ordinateurs de bureau, ordinateurs portables, scanners ..) 41BIS / Le matériel roulant sera composé comme suit : Lot 1: 2 pick-up 4x4 double Component 4: National Request for Single Stage - One cabine tropicalisés pour les IDA / D2860 Post Limited 294,000.00 172,009.80 Signed 2019-04-20 2019-10-10 2019-06-15 2020-05-26 2019-12-12 Coordination Quotations Envelope missions de terrain, Lot2: 01 station wagon , Lot3: 01 mini bus. 65 / Acquisition de matériel Component 4: National Request for Single Stage - One roulant (moto) pour les 7 TF / A7130 Post Limited 40,000.00 0.00 Canceled 2019-07-01 2019-08-26 2020-02-22 Coordination Quotations Envelope CPDD et le coursier de l'UGP 66 / Acquisition de GPS pour Under les CPDD (07) et l'unité de Component 4: National Request for Single Stage - One TF / A7130 Post Limited 20,000.00 0.00 Implementati 2019-07-02 2019-09-10 2019-08-27 2020-02-23 gestion du projet (5) soit au Coordination Quotations Envelope on total 12 GPS 58 / Acquisition de matériel et fourniture informatique pour le projet (Ordinateur bureau +portable en poste de trav, copieur, imprimante Component 4: National Request for Single Stage - One IDA / D2860 Post Limited 50,000.00 0.00 Canceled 2019-06-16 2019-08-11 2020-02-07 couleur, blanc noir, clé USB Coordination Quotations Envelope multi copieur, disque dure, vidéo projecteur, onduleurs, modem pour connexion Wifi, camera... 74 / Acquisition de 2 Component 2: Strengthening véhicules de terrain pour Request for Single Stage - One IDA / D2860 the Policy and Institutional Post Limited 85,000.00 0.00 Canceled 2019-06-26 2019-08-21 2020-02-17 l'Agence Nationale de Gestion Quotations Envelope Framework de l'Environnement 93 / Fournitures de bureau Pending Component 4: National Request for Single Stage - One pour l'UGP ( Accord cadre TF / A7130 Post Open 20,000.00 0.00 Implementati 2020-04-20 2020-06-15 2020-12-12 Coordination Quotations Envelope attribution par article) on 98 / Production des supports Component 4: National Request for Single Stage - One IDA / D2860 Post Open - National 36,364.00 16,660.05 Signed 2020-04-14 2020-06-09 2021-05-14 2020-12-06 de communications - un lot Coordination Quotations Envelope 83 / Acquisition de matériel et fourniture informatique, et matériels bureautique pour Component 2: Strengthening Single Stage - One les CPDD, l'ANGE,Direction de IDA / D2860 the Policy and Institutional Post Request for Bids Open - National 473,091.00 229,876.88 Signed 2020-06-25 2020-07-23 2020-06-30 2020-08-11 2020-09-25 2020-09-10 2020-10-26 2020-10-15 2021-04-23 2021-01-15 Envelope l'Environnement, Economie Framework Bleue et l'UGP WACA - Lot unique Under 97 / Réalisation des films Component 4: National Request for Single Stage - One IDA / D2860 Post Open - National 27,909.00 0.00 Implementati 2020-05-27 2020-07-22 2021-01-18 documentaires Coordination Quotations Envelope on 107 / Acquisition de Component 2: Strengthening matériels roulants pour le UN Agencies IDA / D2860 the Policy and Institutional Post Direct 232,727.00 0.00 Canceled 2020-06-02 2020-06-07 2020-07-12 2020-09-30 Haut Conseil pour la Mer, (Direct) Framework l’ANGE et l’UGP WACA ResIP 84BIS / Acquisition de Component 2: Strengthening matériels roulants (engins TP) UN Agencies IDA / D2860 the Policy and Institutional Post Direct 531,000.00 0.00 Canceled 2020-06-02 2020-06-07 2020-07-12 2020-11-12 pour la Mairie d’Aného – lot (Direct) Framework unique 81 / Acquisition de matériels Component 2: Strengthening roulants pour le Request for Single Stage - One IDA / D2860 the Policy and Institutional Post Limited 187,272.73 0.00 Canceled 2020-04-13 2020-06-08 2020-12-05 développement de l'économie Quotations Envelope Framework bleue et l'ANGE - 02 Lots 109 / Acquisition de trois Component 4: National Request for Single Stage - One (03) téléphones portables IDA / D2860 Post Limited 2,190.00 3,558.26 Signed 2020-08-16 2020-09-08 2020-10-11 2020-09-14 2020-10-27 Coordination Quotations Envelope pour l’UGP WACA ResIP 118 / Acquisition de mobilier Component 2: Strengthening Under Request for Single Stage - One de bureau pour l'ANGE et IDA / D2860 the Policy and Institutional Post Limited 36,364.00 0.00 Implementati 2020-10-05 2020-11-30 2021-01-28 Quotations Envelope l'Economie Bleue Framework on 120 / Acquisition de technologie des systèmes aériens sans pilotes (drone, Component 2: Strengthening Under logiciels, de matériel et Request for Single Stage - One IDA / D2860 the Policy and Institutional Post Limited 70,000.00 0.00 Implementati 2020-10-05 2020-11-30 2021-03-01 fourniture informatiques, Quotations Envelope Framework on Formations) pour la production d'une cartographie 2D et 3D de gestion de la côte TG-WACA TOGO-211741-GO- Component 2: Strengthening UN / Acquisition de matériel UN Agencies IDA / D2860 the Policy and Institutional Post Direct 836,049.00 836,049.00 Signed 2020-10-15 2020-06-02 2020-10-16 2020-11-25 2020-11-22 2020-12-11 2021-02-20 roulant pour la coordination (Direct) Framework et les partenaires Page 2 TG-WACA TOGO-223544-GO- RFQ / Edition et vulgarisation Component 2: Strengthening Pending Request for Single Stage - One du guide d'intégration de IDA / D2860 the Policy and Institutional Post Limited 5,544.00 0.00 Implementati 2021-05-31 2021-07-26 2021-08-25 Quotations Envelope l'économie bleu dans les Framework on documents de planification TG-WACA TOGO-223532-GO- RFQ / Acquisition d'équipement pour la mise en place d'une base de données Component 2: Strengthening Pending Request for Single Stage - One de gestion des ouvrages IDA / D2860 the Policy and Institutional Post Open - National 50,000.00 0.00 Implementati 2021-07-20 2021-09-14 2021-12-13 Quotations Envelope côtiers (serveur, ordinateurs Framework on portables, disque durs externe, appareil photo professionnel, etc...) TG-WACA TOGO-223620-GO- RFQ / acquisition de matériel Component 2: Strengthening Pending et équipement de laboratoire Single Stage - One IDA / D2860 the Policy and Institutional Post Request for Bids Open - National 110,000.00 0.00 Implementati 2021-07-15 2021-07-20 2021-08-19 2021-09-18 2021-10-23 2021-12-22 pour le département de Envelope Framework on géographie de l'université de Lomé TG-WACA TOGO-222191-GO- RFQ / Achat de véhicule Component 2: Strengthening Pending Station WAGON pour le Request for Single Stage - One IDA / 62130 the Policy and Institutional Post Limited 60,000.00 0.00 Implementati 2021-05-25 2021-07-20 2021-08-19 Ministère de la Protection Quotations Envelope Framework on côtière, de la Pêche et de l'Economie Maritime TG-WACA TOGO-223503-GO- RFQ / Equipements de suivi et Component 2: Strengthening Pending Request for Single Stage - One surveillance pour les TF / A7130 the Policy and Institutional Post Limited 18,182.00 0.00 Implementati 2021-07-05 2021-08-30 2021-09-29 Quotations Envelope communautés locales (30 Framework on tablettes ) TG-WACA TOGO-234936-GO- Component 2: Strengthening Pending Request for Single Stage - One RFQ / achat de deux (02) TF / A7130 the Policy and Institutional Post Limited 5,000.00 0.00 Implementati 2021-08-04 2021-09-29 2021-11-28 Quotations Envelope drones Framework on NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 36 / Edition du plan d'investissement et du Component 4: National Request for Single Stage - One document d'analyse du cadre IDA / V1150 Post Limited 18,000.00 20,365.63 Signed 2018-02-21 2018-02-16 2018-04-18 2018-08-01 2018-10-15 Coordination Quotations Envelope juridique institutionnel de gestion intégrée du littoral 38 / Paramétrage du logiciel Under Component 4: National de gestion financière du IDA / V1150 Post Direct Selection Direct 13,000.00 0.00 Implementati 2018-07-05 2018-11-14 2018-07-10 2018-11-14 2018-08-14 2019-02-10 Coordination PGICT pour le projet WACA on Under 52 / Recrutement d'un Component 4: National Request for Single Stage - One IDA / D2860 Post Limited 4,000.00 0.00 Implementati 2019-06-29 2020-06-08 2019-08-24 2020-02-20 service d'entretien Coordination Quotations Envelope on 77 / Police d'assurance pour Under Component 4: National Request for Single Stage - One le personnel recruté par le IDA / D2860 Post Limited 20,000.00 0.00 Implementati 2019-11-25 2019-09-10 2020-01-20 2020-07-18 Coordination Quotations Envelope projet WACA ResIP on 17 BIS / Mise en place d'un système informatisé de suivi Component 4: National Single Stage - One du projet (acquisition, IDA / D2860 Post Request for Bids Open - National 40,000.00 0.00 Canceled 2019-02-20 2019-05-08 2019-02-25 2019-04-08 2019-05-08 2019-06-12 2019-12-09 Coordination Envelope installation et formation des utilisateurs) 119 / Service de gardiennage Component 4: National Request for Single Stage - One IDA / D2860 Post Limited 8,182.00 8,602.22 Signed 2020-08-17 2020-09-09 2020-10-12 2021-04-23 2021-10-09 des bureaux de l'UGP Coordination Quotations Envelope CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 14 / Etude de faisabilité Component 3: Strengthening technique de la protection Quality And Cost- IDA / V1150 National Physical and Social Prior Open - International 2,000,000.00 0.00 Canceled 2018-02-06 2018-02-27 2018-04-12 2018-05-10 2018-06-09 2018-07-14 2018-08-18 2019-08-18 côtière du segment Based Selection Investments transfrontalier Bénin-Togo 15 / Etude d'Impact Environnemental et Social Component 2: Strengthening Quality And Cost- (EIES) de la protection côtière IDA / V1150 the Policy and Institutional Post Open - International 320,000.00 0.00 Canceled 2018-02-08 2018-03-01 2018-04-14 2018-05-12 2018-06-11 2018-07-16 2018-08-20 2019-08-20 Based Selection du segment transfrontalier Framework Bénin-Togo 19 / Etude d'Impact Environnemental et Social Component 2: Strengthening Consultant (EIES) pour le curage IDA / V1150 the Policy and Institutional Post Qualification Open - National 200,000.00 0.00 Canceled 2018-09-25 2018-10-16 2018-11-29 2018-12-29 2019-02-02 2019-08-01 mécanique du chenal Gbaga Framework Selection et de restauration de ces écosystèmes associés 46 / Evaluation du coût de la Component 2: Strengthening Consultant dégradation historique de la IDA / D2860 the Policy and Institutional Post Qualification Open - National 130,000.00 149,746.25 Signed 2019-01-17 2019-05-22 2019-02-07 2019-07-08 2019-03-23 2019-11-28 2019-04-22 2020-12-22 2019-05-27 2021-04-23 2019-11-23 côte y compris la vulnérabilité Framework Selection des communautés côtières 42BIS / Etude de faisabilité technique de l'installation Component 3: Strengthening d'une vanne au niveau du Quality And Cost- IDA / D2860 National Physical and Social Prior Open - International 650,000.00 0.00 Canceled 2019-03-05 2019-03-26 2019-05-09 2019-06-06 2019-07-06 2019-08-10 2019-09-14 2020-09-13 pont de la lagune d'Aného et Based Selection Investments l'étude hydrodynamique du système fluvio-lagunaire Page 3 43 / Etude approfondie de Component 3: Strengthening faisabilité du traitement des Quality And Cost- IDA / 62130 National Physical and Social Prior Open - International 600,000.00 0.00 Canceled 2019-03-12 2019-04-02 2019-05-16 2019-06-13 2019-07-13 2019-08-17 2019-09-21 2020-09-20 boues de phosphates rejetées Based Selection Investments en mer 44 / Elaboration du plan Component 4: National Quality And Cost- IDA / D2860 Post Open - International 250,000.00 0.00 Canceled 2019-02-11 2019-03-04 2019-04-17 2019-05-15 2019-06-14 2019-07-19 2019-08-23 2020-08-22 spatial marin et côtier Coordination Based Selection Component 2: Strengthening 45 / Evaluation du capital Quality And Cost- IDA / D2860 the Policy and Institutional Post Open - International 300,000.00 0.00 Canceled 2019-02-12 2019-03-05 2019-04-18 2019-05-16 2019-06-15 2019-07-20 2019-08-24 2020-08-23 naturel de la zone côtière Based Selection Framework 49 / Audits financiers et Component 4: National Least Cost comptables du projet - IDA / D2860 Post Open - National 45,000.00 24,687.83 Signed 2019-02-11 2019-04-18 2019-03-04 2019-07-08 2019-04-17 2019-10-10 2019-05-15 2020-02-06 2019-06-14 2020-03-11 2019-07-19 2020-05-19 2019-08-23 2020-06-29 2020-02-19 Coordination Selection exercices 2017, 2018 et 2019 3 BIS / Etudes de faisabilité techniques de dragage et de stabilisation des berges de la Component 3: Strengthening Quality And Cost- lagune et du lac Togo, et pour IDA / D2860 National Physical and Social Post Open - International 250,000.00 1,061,119.41 Signed 2018-10-04 2018-05-18 2018-10-25 2018-12-08 2019-08-28 2019-01-05 2019-10-10 2019-02-04 2019-10-25 2019-03-11 2019-12-13 2019-04-15 2020-08-26 2020-04-14 Based Selection la Construction et le curage Investments de caniveau, de bassin d'orage, de retenue d'eau 48 / Etude d'Impact Environnemental et Social Component 3: Strengthening Consultant (EIES) pour le curage TF / A7130 National Physical and Social Post Qualification Open - National 100,000.00 0.00 Canceled 2018-12-28 2019-01-03 2019-01-18 2019-03-03 2019-04-02 2019-05-07 2019-11-03 mécanique du chenal Gbaga Investments Selection et de restauration de ces écosystèmes associés 47B / Etude de faisabilité technique pour le curage Component 3: Strengthening Quality And Cost- Under mécanique du chenal de TF / A7130 National Physical and Social Prior Open - International 600,000.00 0.00 2019-04-26 2019-04-18 2019-05-17 2019-07-23 2019-06-30 2020-10-17 2019-07-28 2020-10-26 2019-08-27 2021-01-14 2019-10-01 2021-04-13 2019-11-05 2020-11-04 Based Selection Implementation Gbaga et de la restauration de Investments ces écosystèmes associés 47 / Etude de faisabilité technique du curage Component 3: Strengthening Quality And Cost- mécanique du chenal Gbaga TF / A7130 National Physical and Social Post Open - International 300,000.00 0.00 Canceled 2018-12-28 2019-01-03 2019-01-18 2019-03-03 2019-03-31 2019-04-30 2019-06-04 2019-07-09 2020-07-08 Based Selection et de restauration de ces Investments écosystèmes associés 48B / Etude d'Impact Environnemental et Social Component 3: Strengthening Consultant (EIES) pour le curage Under TF / A7130 National Physical and Social Post Qualification Open - International 200,000.00 0.00 2019-04-26 2019-04-17 2019-05-17 2019-06-30 2019-08-13 2019-07-30 2018-08-08 2019-09-03 2020-03-01 mécanique du chenal Gbaga Implementation Investments Selection et de restauration de ces écosystèmes associés 40 / Surveillance et contrôle Consultant Component 4: National des travaux d'aménagement IDA / V1150 Post Qualification Open - National 18,000.00 0.00 Canceled 2018-07-11 2018-08-01 2018-09-14 2018-10-14 2018-11-18 2019-05-17 Coordination des bureaux du Projet WACA Selection 62 / Élaboration du plan Component 3: Strengthening Consultant d'aménagement participatif et TF / A7130 National Physical and Social Post Qualification Open - International 140,000.00 154,345.80 Signed 2019-08-28 2020-01-07 2019-09-18 2020-06-26 2019-11-01 2020-10-26 2019-12-01 2021-02-09 2020-01-05 2021-04-23 2020-07-03 des outils de gestion de la Investments Selection forêt communautaire d'Avévé  63 / Elaboration du plan d'aménagement participatif et Component 3: Strengthening Consultant des outils de gestion de la TF / A7130 National Physical and Social Post Qualification Open - International 150,000.00 154,345.80 Signed 2019-08-28 2020-01-07 2019-09-18 2020-06-26 2019-11-01 2020-10-15 2019-12-01 2021-02-09 2020-01-05 2021-04-23 2020-07-03 forêt communautaire de Kodjo- Investments Selection Gati 60 / Recrutement d'une structure ( centre de formation) pour la formation Component 3: Strengthening Consultant Under et l'accompagnement des TF / A7130 National Physical and Social Post Qualification Open - National 55,000.00 244,722.82 2019-08-28 2019-08-21 2019-09-18 2019-11-01 2020-05-05 2019-12-01 2020-06-10 2020-01-05 2020-07-03 Implementation acteurs communautaires sur Investments Selection les bonnes pratiques en gestion durable des terres. 78 / Assistance technique et Component 2: Strengthening Consultant Under contrôle des activités TF / A7130 the Policy and Institutional Post Qualification Open - National 220,982.00 0.00 2020-01-14 2020-01-15 2020-02-04 2020-03-19 2020-04-18 2020-05-23 2020-11-19 Implementation communautaires Framework Selection 82 / Etude sur la situation des plantes envahissantes, des modèles de gestion et de Component 3: Strengthening Consultant Under valorisation dans la sous- TF / A7130 National Physical and Social Post Qualification Open - International 80,000.00 0.00 2019-12-30 2020-03-30 2020-01-20 2020-03-04 2020-04-03 2020-05-08 2020-11-04 Implementation région et les applications Investments Selection possibles dans la zone du projet 40 C / Surveillance et contrôle des travaux d'aménagement du R + 1 des bureaux de l'UGP, Consultant Component 4: National Construction du mur de IDA / D2860 Post Qualification Open - National 20,000.00 0.00 Canceled 2019-08-28 2019-09-18 2019-11-01 2019-12-01 2020-01-05 2020-07-03 Coordination séparation, d'un parking pour Selection 10 voitures, d'un poste d'achat et d'un aménagement de cour. 105 / Recrutement d'un cabinet pour l'actualisation de l'étude de faisabilité technique du projet d'assainissement Component 3: Strengthening des eaux usées à la plage de Quality And Cost- Under IDA / D2860 National Physical and Social Post Open - International 120,000.00 0.00 2020-06-30 2020-09-16 2020-07-21 2021-01-20 2020-09-03 2021-04-15 2020-10-01 2020-10-31 2020-12-05 2021-01-09 2022-01-09 Lomé, réhabilitation du réseau Based Selection Implementation Investments embryonnaire d'assainissement collectif des eaux usées de la ville de Lomé au Togo 113 / Etude d'avant projet détaillé (APD) pour la construction de la nouvelle Consultant Component 4: National Pending direction régionale des IDA / D2860 Post Qualification Open - National 40,000.00 0.00 2020-07-27 2020-08-17 2020-09-30 2020-10-30 2020-12-04 2021-06-02 Coordination Implementation forestiers de la réserve de Selection faune de Togodo Nord à Atakpamé Page 4 121 / Recrutement d'un cabinet pour le contrôle et surveillance des travaux Component 3: Strengthening Consultant d’urgence de protection IDA / D2860 National Physical and Social Post Qualification Limited 910.00 90,871.35 Signed 2020-08-07 2020-08-09 2020-08-21 2020-08-25 2020-09-20 2020-11-10 2020-10-25 2021-02-01 2021-02-24 contre l’érosion côtière des Investments Selection habitations vulnérables sur le littoral togolais allant de Gbodjomé à Agbodrafo. TG-WACA TOGO-222420-CS- CQS / Elaboration de la carte Component 2: Strengthening Consultant de vulnérabilité de la côte Pending TF / A7130 the Policy and Institutional Post Qualification Open - National 54,545.00 0.00 2021-06-10 2021-07-01 2021-08-14 2021-09-13 2021-10-18 2022-01-16 togolaise face aux menaces Implementation Framework Selection de pollution par les hydrocarbures (ABC) TG-WACA TOGO-223531-CS- CQS / Etude de faisabilité Component 2: Strengthening Consultant technique pour la création et Pending IDA / D2860 the Policy and Institutional Post Qualification Open - National 92,000.00 0.00 2021-06-30 2021-07-21 2021-09-03 2021-10-03 2021-11-07 2022-05-06 l'opérationnalisation de Implementation Framework Selection l'observatoire national sur le littoral TG-WACA TOGO-223546-CS- Component 2: Strengthening Consultant Pending CQS / Elaboration du plan IDA / D2860 the Policy and Institutional Post Qualification Open - National 32,000.00 0.00 2021-07-08 2021-07-29 2021-09-11 2021-10-11 2021-11-15 2021-11-27 Implementation spatial marin et côtier Framework Selection TG-WACA TOGO-224375-CS- CDS / Etude de faisabilité Component 3: Strengthening Consultant Pending technique de la mise en place IDA / 62130 National Physical and Social Post Qualification Open - International 90,909.00 0.00 2021-07-30 2021-08-20 2021-10-03 2021-11-02 2021-12-07 2022-06-05 Implementation d'un bypass au port autonome Investments Selection de Lomé INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 1 / Elaboration du Cadre de Component 2: Strengthening Individual Gestion Environnementale et IDA / V1150 the Policy and Institutional Post Consultant Limited 27,500.00 23,893.15 Signed 2017-07-18 2017-06-22 2017-07-23 2017-09-07 2018-01-29 2017-09-28 2018-03-05 2017-11-29 2018-07-17 Sociale (CGES) Framework Selection 2 / Elaboration du Cadre de Component 2: Strengthening Individual Politique de Réinstallation IDA / V1150 the Policy and Institutional Post Consultant Limited 24,000.00 20,223.92 Signed 2017-06-22 2017-06-22 2017-08-24 2017-09-07 2017-09-29 2017-09-29 2017-11-29 2017-11-29 2018-01-12 (CPR) Framework Selection 4 / Etude d'impact environnemental et social des Component 2: Strengthening Individual Under dragages et de la construction IDA / V1150 the Policy and Institutional Post Consultant Limited 18,000.00 0.00 2017-11-12 2017-11-12 2018-01-27 2018-01-22 2018-02-17 2018-08-08 2018-03-24 2018-04-24 Implementation des ouvrages de lutte contre Framework Selection les inondations 13 / Elaboration de la Component 4: National stratégie de passation des IDA / V1150 Post Direct Selection Direct 14,000.00 13,130.33 Signed 2017-12-12 2017-12-12 2017-12-22 2017-12-22 2018-02-09 2018-08-29 2018-03-29 Coordination marchés (PPSD) 6 / Recrutement d'un Individual Component 4: National spécialiste en passation des IDA / V1150 Post Consultant Open 24,000.00 0.00 Canceled 2018-02-06 2018-03-27 2018-04-17 2018-05-22 2018-11-18 Coordination marchés Selection Individual 8 / Recrutement d'un Component 4: National IDA / V1150 Post Consultant Open 24,000.00 0.00 Canceled 2018-02-06 2018-03-27 2018-04-17 2018-05-22 2018-11-18 spécialiste en suivi-évaluation Coordination Selection 9 / Recrutement d'un Individual Component 4: National spécialiste en sauvegarde IDA / V1150 Post Consultant Open 24,000.00 0.00 Canceled 2018-02-06 2018-03-27 2018-04-17 2018-05-22 2018-11-18 Coordination sociale Selection Individual 10 / Recrutement d'un Component 4: National IDA / V1150 Post Consultant Open 24,000.00 0.00 Canceled 2018-02-20 2018-04-10 2018-05-01 2018-06-05 2018-12-02 spécialiste en communication Coordination Selection 9 BIS / Recrutement d'un Individual Component 4: National Under spécialiste en sauvegarde IDA / V1150 Post Consultant Open 24,000.00 0.00 2018-04-26 2018-05-18 2018-06-14 2018-07-05 2019-04-18 2018-08-09 2019-02-05 Coordination Implementation sociale Selection Individual 10 BIS / Recrutement d'un Component 4: National Under IDA / V1150 Post Consultant Open 24,000.00 0.00 2018-06-03 2018-02-18 2018-07-22 2019-04-11 2018-08-12 2019-06-28 2018-09-16 2019-03-15 spécialiste en communication Coordination Implementation Selection 7 / Recrutement d'un Individual Component 4: National Under ingénieur génie civil (génie IDA / V1150 Post Consultant Open 28,000.00 0.00 2018-05-17 2018-08-13 2018-07-05 2018-07-26 2019-04-18 2018-08-30 2019-02-26 Coordination Implementation côtier) Selection Individual 27 / Recrutement d'un Component 4: National Under IDA / V1150 Post Consultant Open 24,000.00 0.00 2018-05-24 2019-02-03 2018-07-12 2019-06-25 2018-08-02 2018-09-06 2019-03-05 auditeur interne du projet Coordination Implementation Selection Individual 11 / Recrutement de Component 4: National IDA / V1150 Post Consultant Open 12,000.00 0.00 Canceled 2018-02-20 2018-04-10 2018-05-01 2018-06-05 2018-12-02 secrétaire caissière Coordination Selection 7 / Recrutement d'un Individual Component 4: National ingénieur génie civil (génie IDA / V1150 Post Consultant Open 24,000.00 0.00 Canceled 2018-02-06 2018-03-27 2018-04-17 2018-05-22 2018-11-18 Coordination côtier) Selection 3 / Réalisation d'études Component 3: Strengthening Individual techniques d'ouvrages de IDA / V1150 National Physical and Social Post Consultant Limited 53,000.00 0.00 Canceled 2017-11-08 2017-11-13 2018-03-26 2018-04-30 2018-10-27 lutte contre les inondations Investments Selection Individual 12 / Recrutement d'un Component 4: National IDA / V1150 Post Consultant Limited 30,000.00 0.00 Canceled 2017-11-08 2017-11-13 2017-12-04 2018-01-08 2018-07-07 Assistant technique au projet Coordination Selection 25 / Recrutement d'un Individual Component 4: National assistant en passation des IDA / V1150 Post Consultant Open 10,000.00 0.00 Canceled 2018-04-26 2018-06-14 2018-07-05 2018-08-09 2019-02-05 Coordination marchés Selection Page 5 24 BIS / Recrutement d'un Individual Component 4: National Under spécialiste en gestion IDA / D2860 Post Consultant Open 24,000.00 0.00 2018-08-29 2018-09-18 2018-11-02 2018-11-23 2019-04-18 2018-12-28 2019-06-26 Coordination Implementation financière Selection 24 / Recrutement d'un Individual Component 4: National assistant au spécialiste en IDA / V1150 Post Consultant Open 10,000.00 0.00 Canceled 2018-08-29 2018-10-31 2018-11-21 2018-12-26 2019-06-24 Coordination gestion financière Selection 50 / Etude pour la mise en place du système national d'informations côtières Component 2: Strengthening Individual Under (Définition et harmonisation IDA / D2860 the Policy and Institutional Post Consultant Open 70,000.00 0.00 2019-04-02 2019-06-05 2019-05-21 2019-06-11 2019-07-16 2020-01-12 Implementation des standards de collecte, Framework Selection traitement et diffusion de données pour l'observatoire) 6 BIS / Recrutement d'un Individual Component 4: National spécialiste en passation des IDA / D2860 Post Consultant Open 24,000.00 37,051.31 Signed 2018-08-27 2018-10-31 2019-02-15 2018-11-21 2019-08-19 2018-12-26 2019-08-09 2019-06-24 Coordination marchés Selection 69 / Actualisation des Component 2: Strengthening Individual manuels de procédure de IDA / D2860 the Policy and Institutional Post Consultant Open 13,000.00 13,023.07 Signed 2019-06-17 2019-06-07 2019-08-05 2020-11-17 2019-08-26 2020-11-23 2019-09-30 2021-04-23 2020-03-28 l'ANGE Framework Selection 67 / Élaboration du plan de développement des Component 2: Strengthening Individual Ressources Humaines du TF / A7130 the Policy and Institutional Post Consultant Open 15,000.00 0.00 Canceled 2019-06-19 2019-06-17 2019-08-07 2019-08-28 2019-10-02 2020-03-30 Ministère de l'Environnement, Framework Selection du Développement Durable et de la Protection de la Nature 64 / Appui à l'analyse institutionnelle du Ministère de l'Environnement, du Développement Durable et de Component 2: Strengthening Individual la Protection de la Nature TF / A7130 the Policy and Institutional Post Consultant Open 15,000.00 16,668.25 Signed 2019-06-19 2019-06-07 2019-08-07 2020-11-17 2019-08-28 2020-11-23 2019-10-02 2021-04-23 2020-03-30 relative à la mise en œuvre Framework Selection des conventions internationales signées par le Togo Component 3: Strengthening Individual 68 / Élaboration du cadre Under TF / A7130 National Physical and Social Post Consultant Open 24,000.00 0.00 2019-06-17 2019-06-07 2019-08-05 2019-11-04 2019-08-26 2019-09-30 2020-03-28 fonctionnel (procédural) Implementation Investments Selection 40B / Surveillance contrôle des Travaux d'aménagement du R+1 des bureaux pour l'UGP, Construction du mur de Individual séparation, d'un parking pour Component 4: National IDA / V1150 Post Consultant Open 9,000.00 0.00 Canceled 2019-06-20 2019-08-08 2019-08-29 2019-10-03 2020-03-31 10 voitures, un poste Coordination Selection d'hébergement (des compteurs et du groupe électrogène) et aménagement de la cour 61 / Élaboration des textes Component 2: Strengthening Individual d'application de la loi sur le IDA / D2860 the Policy and Institutional Post Consultant Open 20,000.00 22,801.19 Signed 2019-06-20 2019-06-07 2019-08-08 2020-12-18 2019-08-29 2021-01-04 2019-10-03 2021-04-23 2020-03-31 littoral Framework Selection Individual 53 / Recrutement d'un (01) Component 4: National IDA / D2860 Post Consultant Open 3,500.00 4,603.46 Signed 2019-06-26 2019-08-21 2019-08-14 2020-05-13 2019-09-04 2020-09-03 2019-10-09 2020-09-21 2020-04-06 coursier Coordination Selection 55 / Recrutement de deux (2) Individual Component 4: National chauffeurs de permis IDA / D2860 Post Consultant Open 9,000.00 20,845.12 Signed 2019-07-12 2019-08-21 2019-08-30 2020-06-02 2019-09-20 2020-07-15 2019-10-25 2020-09-21 2020-04-22 Coordination catégorie B Selection 54 / Recrutement d'un (01) Individual Component 4: National chauffeur de permis catégorie IDA / D2860 Post Consultant Open 5,500.00 0.00 Canceled 2019-08-22 2019-08-21 2019-10-10 2019-10-31 2019-12-05 2020-06-02 Coordination C Selection 75 / Recrutement d'un Individual Component 4: National Coordonnateur du projet IDA / D2860 Post Consultant Open 33,000.00 40,385.61 Signed 2019-08-19 2019-08-20 2019-10-07 2020-03-04 2019-10-28 2020-03-11 2019-12-02 2020-05-26 2020-05-30 Coordination WACA ResIP Selection 75BIS / Recrutement de Individual Component 4: National coordonnateur pour le projet IDA / D2860 Post Consultant Open 33,000.00 40,486.37 Signed 2019-11-20 2019-11-08 2019-12-23 2020-03-13 2020-01-06 2020-03-25 2020-02-10 2020-05-26 2020-08-08 Coordination WACA ResIP Selection 87 / Recrutement de consultant individuel génie electro-mécanique pour le Component 2: Strengthening Individual Pending contrôles des travaux TF / A7130 the Policy and Institutional Post Consultant Open 18,182.00 0.00 2020-04-15 2020-06-03 2020-06-24 2020-07-29 2021-01-25 Implementation d'aménagement de la cour du Framework Selection MEDDPN et des bureaux de l'UGP (RDC et R+1) 91 / Recrutement d'un Individual Component 4: National Pending secrétaire administratif pour IDA / D2860 Post Consultant Open 12,000.00 0.00 2020-04-09 2020-05-28 2020-06-18 2020-07-23 2021-01-19 Coordination Implementation l'UGP WACAResIP Selection 89 / Recrutement de consultant individuel environnementaliste pour le Component 2: Strengthening Individual contrôles des travaux TF / A7130 the Policy and Institutional Post Consultant Open 11,136.00 0.00 Canceled 2020-04-15 2020-06-03 2020-06-24 2020-07-29 2021-01-25 d'aménagement de la cour du Framework Selection MEDDPN et des bureaux de l'UGP (RDC et R+1) 20 / Recrutement d'un Individual Component 4: National spécialiste en développement IDA / V1150 Post Consultant Open 24,000.00 0.00 Canceled 2018-06-03 2018-07-22 2019-06-25 2018-08-12 2019-08-19 2018-09-16 2019-03-15 Coordination institutionnel Selection Page 6 106 / Recrutement d'un consultant pour la réalisation de l'EIES du projet d'assainissement des eaux Component 3: Strengthening Individual usées à la plage de Lomé, Under IDA / D2860 National Physical and Social Post Consultant Open 50,000.00 0.00 2020-06-02 2020-11-11 2020-07-21 2020-08-11 2020-09-15 2021-01-15 réhabilitation du réseau Implementation Investments Selection embryonnaire d'assainissement collectif des eaux usées de la ville de Lomé- Togo 111 / Recrutement d'un Individual Component 4: National expert en passation de IDA / D2860 Post Consultant Open 28,500.00 34,987.56 Signed 2020-05-29 2020-05-25 2020-07-17 2020-07-23 2020-08-07 2020-10-02 2020-09-11 2020-11-20 2021-09-10 Coordination marché pour le projet WACA Selection ResIP 115 / Recrutement d'un Individual Component 4: National auditeur interne pour le projet IDA / D2860 Post Consultant Open 17,455.00 0.00 Canceled 2020-06-03 2020-07-22 2020-08-12 2020-09-16 2021-11-30 Coordination WACA ResIP Selection 101 / Recrutement de consultant individuel génie électromécanique pour le Component 2: Strengthening Individual contrôle des travaux IDA / D2860 the Policy and Institutional Post Consultant Open 6,200.00 15,039.77 Signed 2020-07-10 2020-06-16 2020-08-28 2020-09-23 2020-09-18 2021-03-24 2020-10-23 2021-04-23 2021-06-23 d'aménagement du cadre de Framework Selection travail de l'ANGE et du bâtiment R+1 de l'UGP WACA ResiP 90 / Recrutement d’un secrétaire pour la passation Individual Component 4: National Under de marché et la gestion IDA / D2860 Post Consultant Open 12,000.00 0.00 2020-06-30 2020-08-11 2020-08-18 2020-09-08 2020-10-13 2021-04-11 Coordination Implementation financière du projet WACA Selection ResIP 117 / Recrutement d'un Individual Component 4: National spécialiste en communication IDA / D2860 Post Consultant Open 24,000.00 0.00 Canceled 2020-08-12 2020-09-30 2020-10-21 2020-11-25 2021-11-24 Coordination pour le projet WACA ResIP Selection 122 / Mise en place d'un système automatisé de Component 2: Strengthening Individual Under gestion des ressources TF / A7130 the Policy and Institutional Post Consultant Open 15,000.00 0.00 2020-09-30 2021-03-29 2020-11-18 2020-12-09 2021-01-13 2021-04-12 Implementation humaines et financières du Framework Selection MEDDPN TG-WACA TOGO-204714-CS- Component 3: Strengthening Individual INDV / élaboration d'un plan Under TF / A7130 National Physical and Social Post Consultant Limited 20,000.00 0.00 2021-01-28 2020-12-30 2021-02-12 2021-03-05 2021-04-09 2021-05-09 d'aménagement et de gestion Implementation Investments Selection de la forêt classée d'Assévé 99 / Recrutement d'un consultant pour la réalisation Component 3: Strengthening Individual d'un plan d'action de IDA / D2860 National Physical and Social Post Consultant Open 22,000.00 0.00 Canceled 2020-04-10 2020-05-29 2020-06-19 2020-07-24 2021-01-20 réinstallation du dragage et Investments Selection stabilisation des berges de la lagune et du lac Togo 95 / Recrutement d'un consultant pour la realisation Component 3: Strengthening Individual d'un plan d'action de TF / A7130 National Physical and Social Post Consultant Open 9,091.00 0.00 Canceled 2020-04-09 2020-04-14 2020-05-28 2020-06-18 2020-07-23 2021-01-19 réinstallation du complexe Investments Selection d'aires protégées de TOGODO 102 / Recrutement de consultant individuel Component 2: Strengthening Individual environnementaliste pour le IDA / D2860 the Policy and Institutional Post Consultant Open 2,727.00 0.00 Canceled 2020-04-09 2020-05-28 2020-06-18 2020-07-23 2021-01-19 contrôle des travaux Framework Selection d'aménagement du cadre de travail de l'ANGE 94 / Recrutement de consultant individuel génie Component 2: Strengthening Individual civil pour le contrôle des IDA / D2860 the Policy and Institutional Post Consultant Open 4,136.00 0.00 Canceled 2020-06-30 2020-08-18 2020-09-08 2020-10-13 2021-05-12 travaux Framework Selection d'aménagement du cadre de travail de l'ANGE 86 / Recrutement de consultant individuel génie Component 2: Strengthening Individual civil pour le contrôles des TF / A7130 the Policy and Institutional Post Consultant Open 18,182.00 0.00 Canceled 2020-04-15 2020-06-03 2020-06-24 2020-07-29 2021-01-25 travaux d'aménagement de la Framework Selection cour du MEDDPN et des bureaux de l'UGP (RDC et R+1) 80 / Etude d'impact Component 3: Strengthening Individual environnementale et sociale TF / A7130 National Physical and Social Post Consultant Open 18,182.00 0.00 Canceled 2020-03-19 2020-03-30 2020-05-07 2020-05-28 2020-07-02 2020-12-29 du complexe d'aires Investments Selection protégées de TOGODO TG-WACA TOGO-222416-CS- Component 2: Strengthening Individual INDV / Etude pour la mise en Pending IDA / D2860 the Policy and Institutional Post Consultant Open 30,000.00 0.00 2021-06-08 2021-07-28 2021-08-18 2021-09-22 2021-10-22 place du MRV de la zone Implementation Framework Selection côtière TG-WACA TOGO-222909-CS- Individual Component 4: National Under INDV / Elaboration du rapport IDA / D2860 Post Consultant Open 46,000.00 0.00 2021-04-15 2021-03-29 2021-06-03 2021-06-24 2021-07-29 2021-08-28 Coordination Implementation d'évaluation à mi-parcours Selection TG-WACA TOGO-223541-CS- INDV / Actualisation du Plan Component 2: Strengthening Individual d'investissement Pending IDA / D2860 the Policy and Institutional Post Consultant Open 27,273.00 0.00 2021-05-28 2021-07-16 2021-08-06 2021-09-10 2022-03-09 multisectoriel pour prendre Implementation Framework Selection en compte les considérations environnementales régionales TG-WACA TOGO-222896-CS- Individual INDV / SELECTION D’UN Component 4: National Pending IDA / D2860 Post Consultant Open 38,000.00 0.00 2021-06-18 2021-08-06 2021-08-27 2021-10-01 2022-10-01 EXPERT OCEANOGRAPHE – Coordination Implementation Selection LITTORALISTE TG-WACA TOGO-222891-CS- Component 2: Strengthening Individual INDV / Elaboration du plan IDA / D2860 the Policy and Institutional Post Consultant Open 32,000.00 0.00 Canceled 2021-05-20 2021-07-08 2021-07-29 2021-09-02 2021-10-02 spatial marin et côtier Framework Selection Page 7 Component 2: Strengthening Individual 51 / Appui à la mise en place IDA / D2860 the Policy and Institutional Post Consultant Open 30,000.00 0.00 Canceled 2019-02-04 2019-06-05 2019-03-25 2019-04-15 2019-05-20 2019-11-16 du MRV de la zone côtière Framework Selection Page 8 Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan[Original: December 2015]: Last Revision of Updated Procurement Plan, Feb 2017] 2. Date of General Procurement Notice: June 25, 2015 3. Period covered by this procurement plan: From December 2015 Till end of December 2017 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Comments Threshold US$ 1. NCB (Goods) Above US$ 1,500,000 All 2. Shopping (Goods) Above US$ 500,000 All 2. Pre-qualification. "Not Applicable" 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: "Not applicable" 4. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan # 8496-EG, Project # P145699 prepared by SSSNP PMU on 6th May 2015 5. Any Other Special Procurement Arrangements: None May 24, 2017 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness 1 2 3 4 5 6 7 Ref. Descripti Estimat Packages Dome Review Comme No. on ed stic by Bank nts Cost Prefe (Prior / US$ rence Post) (yes/ no) Supply of Computers , laptops, software and other IT 400,00 NCB G-05 equipment 1 No Post 0 (Goods) for MOSS Departmen ts in27 Governorat es Printing & Shoppi G-07 Publication 50,000 1 No Post ng s (Goods) Furniture Shoppi & G-08 Equipment 50,000 1 No Post ng for the (Goods) PMU Video & Shoppi Graphics G-09 equipment 4,000 1 No Post ng for MOSS (Goods) Customer Collaborati on Solution Shoppi G-11 for 45,000 1 No Post ng Grievance (Goods) (call center) III. Selection of Consultants May 24, 2017 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comments Threshold 1. QCBS (Consulting Firms) Above US$ 500,000 2. IC (Individual Consultant) Above US$ 200,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: None 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description of Estimat Packa Review Comment Assignment ed ges by Bank s Cost (Prior / US$ Post) CF-05 Institutional consultancy to conduct 120,00 airing 1 Post QCBS 0 adverstismen t+Video + radio CF-06 Local community dialogues 50,000 1 Post QCBS regular administratio n CF-08 Communicati on Firm (Advocacy Strategy, 150,00 Communicati 1 Post QCBS 0 on Strategy, Design materials, etc) CF-09 Technical/the 75,000 1 Post QCBS May 24, 2017 matic capacity building (M&E, MIS, grievance, conditionality , social responsibility , NGOs TOT, etc.) IC-30 Hiring Office Manager for 30,000 1 Post IC the Program May 24, 2017 PROCUREMENT Egypt, Arab Republic of : Strengthening Social Safety Net Project PLAN General Information Country: Egypt, Arab Republic of Bank’s Approval Date of the Original Procurement Plan: 2017-05-31 2021-05-23 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P145699 GPN Date: Project Name: Strengthening Social Safety Net Project Loan / Credit No: IBRD / 84960, IBRD / 89970 Ministry of Social Solidarity Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual EG-MOSS-11483-GO-RFQ / Support SSN Targeting and Request for Single Stage - One IBRD / 84960 Post Limited 50,000.00 2,241.79 Completed 2017-07-06 2017-05-05 2017-08-31 2017-05-14 2018-02-27 2017-05-25 Printing and Publications Operational Systems Quotations Envelope EG-MOSS-11486-GO-RFQ / Support SSN Targeting and Request for Single Stage - One Furniture and Equipment for IBRD / 84960 Post Limited 50,000.00 6,323.62 Completed 2017-08-06 2017-07-19 2017-10-01 2017-07-26 2018-03-30 2017-07-29 Operational Systems Quotations Envelope the PMU EG-MOSS-11489-GO-RFQ / Support SSN Targeting and Request for Single Stage - One Video & Graphics Equipment IBRD / 84960 Post Limited 4,000.00 0.00 Canceled 2017-07-07 2017-09-01 2018-02-28 Operational Systems Quotations Envelope for MOSS EG-MOSS-17356-GO-RFQ / Customer Collaboration Solution (grievance) . This solution combines traditional contact center technology and Project Management and Request for Single Stage - One processes with important IBRD / 84960 Post Limited 45,000.00 0.00 Canceled 2017-07-02 2017-07-23 2018-01-19 Monitoring and Evaluation Quotations Envelope additions in recording, agent workspaces, social media and video to help build deeper relationships with our customers EG-MOSS-18410-GO-RFQ / we want to procure 330 scanner so that the grievance system can work through the Moss units in the Project Management and Request for Single Stage - One governorates and no need for IBRD / 84960 Post Limited 70,000.00 0.00 Canceled 2017-07-06 2017-07-04 2017-08-31 2018-02-27 Monitoring and Evaluation Quotations Envelope the appellant to come to the ministry in Cairo, as the appellant usually submit documents with his complaint so we have to scan EG-MOSS-21361-GO-RFQ / Project Management and Request for Single Stage - One Communication equipment's IBRD / 84960 Post Limited 1,500.00 952.01 Completed 2017-08-08 2017-07-30 2017-10-03 2017-08-03 2018-04-01 2017-08-06 Monitoring and Evaluation Quotations Envelope for PMU staff EG-MOSS-23406-GO-RFQ / Under Project Management and Request for Single Stage - One Procuring Tablets for Social IBRD / 84960 Post Limited 95,000.00 49,070.63 Implementati 2017-09-05 2017-08-14 2017-10-31 2017-09-07 2018-04-29 2017-09-14 Monitoring and Evaluation Quotations Envelope Administration on EG-MOSS-23414-GO-RFQ / Project Management and Request for Single Stage - One Procuring Chargers for IBRD / 84960 Post Limited 5,000.00 7,447.63 Completed 2017-08-18 2017-08-21 2017-10-13 2017-09-13 2018-04-11 2017-11-06 Monitoring and Evaluation Quotations Envelope existing tablets EG-MOSS-23481-GO-RFQ / Project Management and Request for Single Stage - One Procuring Office Machinery for IBRD / 84960 Post Limited 1,000.00 0.00 Canceled 2017-09-08 2017-11-03 2018-05-02 Monitoring and Evaluation Quotations Envelope the PMU EG-MOSS-25146-GO-RFQ / Under Designing and Printing of the Project Management and Request for Single Stage - One IBRD / 84960 Post Limited 100,000.00 0.00 Implementati 2017-10-06 2017-08-29 2017-12-01 2018-05-30 Ministry of Social Solidarity Monitoring and Evaluation Quotations Envelope on (MOSS) Promotional Materials EG-MOSS-25158-GO-RFQ / Project Management and Request for Single Stage - One printing business cards for IBRD / 84960 Post Limited 1,200.00 0.00 Canceled 2017-11-06 2018-01-01 2018-06-30 Monitoring and Evaluation Quotations Envelope the PMU EG-MOSS-25161-GO-RFQ / Under Project Management and Request for Single Stage - One Procuring computers for IBRD / 84960 Post Limited 6,000.00 0.00 Implementati 2017-11-06 2017-09-11 2018-01-01 2018-06-30 Monitoring and Evaluation Quotations Envelope Service improvement unit on EG-MOSS-34988-GO-RFQ / Project Management and Request for Single Stage - One Printing 1,500,000 Takaful & IBRD / 84960 Post Limited 45,000.00 7,635.01 Signed 2018-01-06 2017-11-12 2018-03-03 2018-12-28 2018-08-30 Monitoring and Evaluation Quotations Envelope Karama application EG-MOSS-54103-GO-RFQ / Shopping purchase: 5 laptops, 2 PCs, 5 flash memories, 5 Project Management and Request for Single Stage - One antivirus, 4 external hard IBRD / 84960 Post Limited 7,000.00 0.00 Canceled 2018-03-18 2018-04-15 2018-05-06 Monitoring and Evaluation Quotations Envelope disks, 1 camera stand, 1 hand microphone, 1 ear microphones, EG-MOSS-60796-GO-RFQ / Purchase of IT equipment for Under extended PMU staff (10 Project Management and Request for Single Stage - One IBRD / 84960 Post Limited 6,000.00 0.00 Implementati 2018-04-30 2018-05-28 2018-06-25 2018-12-22 laptops + 10 antivirus + 10 Monitoring and Evaluation Quotations Envelope on electricity connector extensions + 5 modems) Page 1 EG-MOSS-68986-GO-RFQ / Professional Conference call, sound system, projectors, Support SSN Targeting and Request for Single Stage - One IBRD / 84960 Post Limited 50,000.00 28,642.28 Completed 2018-07-29 2018-08-05 2018-08-12 2018-08-29 2018-09-21 2018-09-06 screens and TVs for the Operational Systems Quotations Envelope meeting halls in the ministry (MoSS) head quarter EG-MOSS-70745-GO-RFQ / Purchase 10 photocopier, 20 Support SSN Targeting and Request for Single Stage - One photocopier toners , 65 IBRD / 84960 Post Limited 30,000.00 0.00 Canceled 2018-08-01 2018-08-20 2018-09-19 Operational Systems Quotations Envelope printer toners and 5 inkjet printer. EG-MOSS-66112-GO-RFQ / Purchase Air conditioning, Project Management and Request for Single Stage - One Kitchen electrical devices, IBRD / 84960 Post Limited 15,000.00 4,158.42 Signed 2018-06-23 2018-07-11 2018-07-23 2018-07-30 2018-08-22 Monitoring and Evaluation Quotations Envelope ceiling fans and water cooler tank EG-MOSS-70746-GO-RFQ / Purchase of metal units for Support SSN Targeting and Request for Single Stage - One IBRD / 84960 Post Limited 40,000.00 316,654.86 Signed 2018-07-29 2018-08-28 2018-09-23 2018-09-10 2018-12-22 2018-09-28 filing - Office furniture - Operational Systems Quotations Envelope Curtains for PMU office. EG-MOSS-71078-GO-RFQ / Purchasing: Printing paper Support SSN Targeting and Request for Single Stage - One IBRD / 84960 Post Limited 15,000.00 13,499.54 Completed 2018-08-10 2018-09-06 2018-10-05 2018-09-18 2019-04-03 2018-10-16 size (A4 & A3) and stationary Operational Systems Quotations Envelope (e.g: pen, folders ..etc) EG-MOSS-76938-GO-RFQ / Purchasing Racks for the PMU's equipments: Support SSN Targeting and Request for Single Stage - One IBRD / 84960 Post Limited 4,500.00 0.00 Canceled 2018-09-15 2018-10-11 2018-11-10 1- The main routers in MoSS Operational Systems Quotations Envelope 2- Equipment for discussion systems in MoSS EG-MOSS-78331-GO-RFQ / Providing Compact Stand Kiosk for some social units. Support SSN Targeting and Request for Single Stage - One IBRD / 84960 Post Limited 60,000.00 29,280.82 Signed 2018-09-25 2018-11-01 2018-11-20 2018-12-20 2019-03-20 Each kiosk will include a tablet Operational Systems Quotations Envelope to receive information from T&K beneficiaries. EG-MOSS-71077-GO-RFQ / Printing T&K's logo on block- Under Support SSN Targeting and Request for Single Stage - One notes, personal cards, pen, IBRD / 84960 Post Limited 90,000.00 0.00 Implementati 2018-07-31 2018-10-23 2018-09-25 2018-11-24 Operational Systems Quotations Envelope bags, paper folders ..etc. on Printing Broshers, pock-let EG-MOSS-81693-GO-RFQ / Support SSN Targeting and Request for Single Stage - One Purchase 2650 electricity IBRD / 84960 Post Limited 80,000.00 0.00 Canceled 2018-11-23 2019-01-02 2019-04-02 Operational Systems Quotations Envelope connectors EG-MOSS-85351-GO-RFQ / Under Purchase web application to Project Management and Request for Single Stage - One IBRD / 84960 Post Limited 90,000.00 0.00 Implementati 2018-11-16 2018-11-18 2018-12-21 2019-03-21 manage TKP depository as Monitoring and Evaluation Quotations Envelope on CMS & LMS. EG-MOSS-85354-GO-RFQ / Project Management and Request for Single Stage - One Purchase network cable & IBRD / 84960 Post Limited 3,000.00 0.00 Canceled 2018-11-13 2018-12-15 2019-01-14 Monitoring and Evaluation Quotations Envelope Mobile phones EG-MOSS-81695-GO-RFB / Lot(A) Supply & install 5100 Thin-clients in social units (Lot B) Supply (1,300) LaserJet Printers Support SSN Targeting and Single Stage - One (Lot C) Supply (2,300) IBRD / 84960 Prior Request for Bids Open - International 7,000,000.00 3,537,297.47 Signed 2018-12-12 2018-12-27 2018-12-20 2019-06-18 2019-02-03 2019-03-03 2019-02-17 2019-06-20 2019-03-10 2019-07-11 2019-07-08 Operational Systems Envelope Scanners (Lot D) Supply (2,650) IP Phones (Lot E) Supply 500 LaserJet Toners for existing printers EG-MOSS-81682-GO-RFQ / Purchase Telephone devices, Support SSN Targeting and Request for Single Stage - One Fax devices, IP-Phones & IBRD / 84960 Post Limited 15,000.00 6,998.58 Completed 2018-10-15 2018-10-16 2018-10-26 2018-10-21 2018-11-25 2018-10-23 Operational Systems Quotations Envelope licenses for IP-Phones for the PIU EG-MOSS-130517-GO-RFQ / Supply and install of networking infrastructure for Support SSN Targeting and Request for Single Stage - One IBRD / 84960 Post Limited 90,000.00 73,736.13 Signed 2019-09-10 2019-07-24 2019-11-05 2019-08-19 2020-05-03 200 rehabilitation offices of Operational Systems Quotations Envelope the Ministry of Social Solidarity offices. EG-MOSS-132894-GO-RFQ / Support SSN Targeting and Request for Single Stage - One Printings of the Conditionality IBRD / 84960 Post Limited 35,000.00 25,787.70 Completed 2019-09-10 2019-05-23 2019-11-05 2019-05-30 2020-05-03 2019-06-02 Operational Systems Quotations Envelope Registries EG-MOSS-135529-GO-RFQ / Support SSN Targeting and Request for Single Stage - One IBRD / 84960 Post Limited 10,000.00 6,026.97 Signed 2019-09-29 2019-08-04 2019-11-24 2019-09-15 2020-05-22 Toner cartridges Operational Systems Quotations Envelope EG-MOSS-135562-GO-RFQ / Support SSN Targeting and Request for Single Stage - One Printing Takaful and Karama IBRD / 84960 Post Limited 15,000.00 14,524.10 Signed 2019-09-29 2019-07-15 2019-11-24 2019-08-04 2020-05-22 Operational Systems Quotations Envelope questionnaire . EG-MOSS-121002-GO-RFB / Project Management and Single Stage - One Conditionality Registers and IBRD / 84960 Post Request for Bids Open - National 200,000.00 128,671.06 Completed 2019-06-30 2019-07-02 2019-07-05 2019-08-16 2019-07-10 2019-09-15 2019-07-21 2019-10-20 2019-09-15 2020-04-17 2019-10-01 Monitoring and Evaluation Envelope Booklets BULK Printing EG-MOSS-133550-GO-RFQ / Support SSN Targeting and Request for Single Stage - One IBRD / 84960 Post Limited 1,000.00 807.30 Completed 2019-09-14 2019-07-21 2019-11-09 2019-07-25 2020-05-07 2019-07-29 Conditionality training guide Operational Systems Quotations Envelope EG-MOSS-144416-GO-RFQ / Support SSN Targeting and Request for Single Stage - One Network Fault & performance IBRD / 84960 Post Limited 90,000.00 90,905.31 Signed 2019-11-12 2019-11-21 2020-01-07 2019-12-19 2020-07-05 Operational Systems Quotations Envelope management system Page 2 EG-MOSS-147022-GO-RFB / Supply of networking switches Support SSN Targeting and Single Stage - One IBRD / 84960 Post Request for Bids Open - National 340,000.00 308,079.66 Signed 2019-12-20 2020-01-19 2019-12-25 2020-02-05 2020-02-16 2020-03-06 2020-04-02 2020-04-10 2020-04-15 2020-10-07 for 344 administrations and Operational Systems Envelope directorates of the MoSS EG-MOSS-35566-GO-RFB / Project Management and Single Stage - One Automation of MOSS social IBRD / 84960 Post Request for Bids Open - National 1,000,000.00 0.00 Canceled 2017-11-16 2017-11-21 2018-01-02 2018-02-01 2018-03-08 2018-09-04 Monitoring and Evaluation Envelope units, procuring 4500 tablet EG-MOSS-151897-GO-RFQ / Support SSN Targeting and Request for Single Stage - One Printings of Job evaluation IBRD / 84960 Post Limited 94,000.00 0.00 Canceled 2019-12-31 2020-06-02 2020-02-25 2020-08-23 Operational Systems Quotations Envelope forms EG-MOSS-154634-GO-RFQ / Support SSN Targeting and Request for Single Stage - One IBRD / 84960 Post Limited 45,000.00 19,377.06 Completed 2020-01-25 2019-12-09 2020-03-21 2020-02-19 2020-09-17 2020-03-01 stationery and office supplies Operational Systems Quotations Envelope EG-MOSS-163926-GO-RFQ / Furniture and air condition for Support SSN Targeting and Request for IBRD / 84960 Post 5,000.00 720.63 Completed 2020-03-10 2020-03-10 2020-03-29 2020-03-10 2020-04-12 Takaful and Karama program Operational Systems Quotations director’s office EG-MOSS-165397-GO-RFQ / Supply and install of flexible anti-fire ducts, network Support SSN Targeting and Request for Single Stage - One cables, electricity power exit IBRD / 84960 Post Limited 9,000.00 0.00 Canceled 2020-03-27 2020-05-22 2020-11-18 Operational Systems Quotations Envelope duct socket for rack, face plates to construct fifty (50) network nodes. EG-MOSS-154659-GO-RFQ / The objective of this procurement activity is to purchase disability Support SSN Targeting and Request for Single Stage - One assessment kits. Some of IBRD / 84960 Post Limited 37,000.00 50,811.43 Completed 2020-01-25 2020-02-09 2020-03-21 2020-02-27 2020-09-17 2020-03-01 Operational Systems Quotations Envelope items that the kits contain are alphabet wooden board, coins, group of cubes, scissors, .. etc. EG-MOSS-165406-GO-RFQ / This activity is to purchase queue system, furniture for the grievance room, supply and install both electricity and Support SSN Targeting and Request for Single Stage - One IBRD / 84960 Post Limited 95,000.00 117,830.96 Completed 2020-03-28 2020-04-22 2020-05-23 2020-05-10 2020-11-19 2020-07-17 data cables for the queue Operational Systems Quotations Envelope system, and supply and install a partition for the waiting area annexed to the grievance room. Complete lot. EG-MOSS-172044-GO-RFQ / Support SSN Targeting and Request for Single Stage - One IBRD / 84960 Post Limited 100,000.00 90,000.00 Terminated 2020-05-11 2020-05-07 2020-07-06 2020-05-11 2021-01-02 Database replication server Operational Systems Quotations Envelope EG-MOSS-173387-GO-RFQ / Masks, gloves, alcohol, and Support SSN Targeting and Request for Single Stage - One sterilization materials against IBRD / 84960 Post Limited 9,000.00 10,985.56 Completed 2020-05-22 2020-05-10 2020-07-17 2020-06-17 2021-01-13 2020-06-21 Operational Systems Quotations Envelope Corona Virus for the team work. EG-MOSS-180023-GO-RFQ / Support SSN Targeting and Request for Single Stage - One Laptop computers and IBRD / 84960 Post Limited 50,000.00 25,643.84 Completed 2020-06-30 2020-06-17 2020-08-25 2020-06-22 2021-02-21 2020-06-25 Operational Systems Quotations Envelope photocopiers EG-MOSS-191265-GO-RFQ / Network passive components such as Rj45 Cat6, crimper, Support SSN Targeting and Request for Single Stage - One tester, Box-UTP-Cat6 -305M, IBRD / 84960 Post Limited 13,000.00 6,973.06 Signed 2020-09-11 2020-09-06 2020-11-06 2020-09-24 2021-05-05 Operational Systems Quotations Envelope and unmanaged switch 8 port, for the social administrations’ network. EG-MOSS-191257-GO-RFQ / Furnishing the Information Center of Takaful and Karama Program with chairs, desks, Support SSN Targeting and Request for Single Stage - One smart screen, uniform and ID IBRD / 84960 Post Limited 19,000.00 15,863.49 Signed 2020-09-11 2020-08-16 2020-11-06 2020-09-03 2021-05-05 Operational Systems Quotations Envelope cards for the receptionist team, internal signage, lighting units, data cabling, … etc. EG-MOSS-197489-GO-RFQ / Support SSN Targeting and Request for Single Stage - One Six access control doors IBRD / 84960 Post Limited 10,000.00 7,958.74 Signed 2020-11-03 2020-10-11 2020-12-29 2020-11-02 2021-06-27 Operational Systems Quotations Envelope system. EG-MOSS-197499-GO-RFQ / Number of twenty laptop Support SSN Targeting and Request for Single Stage - One IBRD / 84960 Post Limited 25,000.00 17,455.36 Completed 2020-11-10 2020-10-12 2021-01-05 2020-10-13 2021-07-04 2020-10-18 computers for Takaful and Operational Systems Quotations Envelope Karama. EG-MOSS-203695-GO-RFQ / Support SSN Targeting and Request for Single Stage - One Supplying Tablets for the IBRD / 84960 Post Limited 100,000.00 94,736.84 Completed 2020-11-17 2021-02-01 2021-01-12 2021-03-30 2021-07-11 2021-04-05 Operational Systems Quotations Envelope social unit. EG-MOSS-204563-GO-RFQ / Pending Support SSN Targeting and Request for Single Stage - One Supply and install air- IBRD / 84960 Post Limited 20,000.00 0.00 Implementati 2020-11-22 2021-01-17 2021-07-16 Operational Systems Quotations Envelope conditions. on EG-MOSS-210972-GO-RFB / Sheets for medical beds for Support SSN Targeting and Single Stage - One the isolation hospitals to IBRD / 84960 Post Request for Bids Open - National 950,000.00 0.00 Canceled 2020-12-27 2021-01-01 2021-02-12 2021-03-14 2021-04-18 2021-10-15 Operational Systems Envelope confront the Corona pandemic. EG-MOSS-211213-GO-RFQ / Support SSN Targeting and Request for Single Stage - One Video conference system for IBRD / 84960 Post Limited 44,000.00 31,814.99 Completed 2021-01-05 2020-12-20 2021-03-02 2020-12-30 2021-08-29 2021-01-03 Operational Systems Quotations Envelope H.E. office. EG-MOSS-211220-GO-RFQ / Under UTP-Cat6 cables and power Support SSN Targeting and Request for Single Stage - One IBRD / 84960 Post Limited 40,000.00 34,034.42 Implementati 2021-01-04 2021-01-04 2021-03-01 2021-08-28 distribution units PDUs for the Operational Systems Quotations Envelope on social units Page 3 EG-MOSS-212365-GO-RFQ / Purchasing twenty laptops Support SSN Targeting and Request for Single Stage - One IBRD / 84960 Post Limited 30,000.00 16,332.91 Signed 2021-01-11 2021-01-04 2021-03-08 2021-01-18 2021-09-04 and upgrading four HP Operational Systems Quotations Envelope ProBook 450 G6 laptops. EG-MOSS-225239-GO-RFQ / As a result of the outbreak of the new Corona virus (Covid- 19), cleaning supplies, Support SSN Targeting and Request for Single Stage - One IBRD / 84960 Post Limited 100,000.00 107,747.45 Completed 2021-03-26 2021-03-24 2021-05-21 2021-04-11 2021-11-17 2021-05-09 disinfectants and masks will Operational Systems Quotations Envelope be provided to a number of 135,000 participants in the behavior change sessions. EG-MOSS-225739-GO-RFQ / Pending Audiovisual equipment for the Support SSN Targeting and Request for Single Stage - One IBRD / 84960 Post Limited 95,000.00 0.00 Implementati 2021-04-02 2021-05-28 2021-11-24 main conference room of the Operational Systems Quotations Envelope on MoSS. EG-MOSS-229514-GO-RFB / Pending Supplying a number of (3,000) Support SSN Targeting and Single Stage - One IBRD / 84960 Post Request for Bids Open - National 940,000.00 0.00 Implementati 2021-04-22 2021-04-27 2021-06-08 2021-07-08 2021-08-12 2022-02-08 Tablet computer for the social Operational Systems Envelope on unit. EG-MOSS-197481-GO-RFQ / Support SSN Targeting and Request for Single Stage - One Printing registration forms for IBRD / 84960 Post Limited 50,000.00 0.00 Canceled 2020-11-03 2020-12-29 2021-06-27 Operational Systems Quotations Envelope Takaful and Karama NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual EG-MOSS-52515-NC-DIR / MoSS Social Units SDSL land Support SSN Targeting and IBRD / 84960 Prior Direct Selection Direct 2,000,000.00 1,825,150.37 Signed 2018-03-07 2018-03-12 2018-04-16 2018-07-10 2018-10-13 lines connectivity service Operational Systems provision EG-MOSS-76934-NC-RFQ / Printing 2 million Support SSN Targeting and Request for Single Stage - One questionnaire of IBRD / 84960 Post Limited 27,500.00 27,140.36 Signed 2018-09-14 2018-09-10 2018-09-30 2018-09-18 2018-10-20 Operational Systems Quotations Envelope conditionality under Takaful component EG-MOSS-121629-NC-DIR / eFinance's design and printing Support SSN Targeting and IBRD / 84960 Prior Direct Selection Direct 800,000.00 0.00 Canceled 2019-06-30 2019-07-05 2019-08-09 2020-02-05 of 500,000 integrated Operational Systems services acquisition disability cards EG-MOSS-143574-NC-DIR / Support SSN Targeting and IBRD / 84960 Post Direct Selection Direct 2,300.00 0.00 Canceled 2019-10-30 2019-11-04 2019-12-09 2020-06-06 Office boy Operational Systems EG-MOSS-143576-NC-DIR / Support SSN Targeting and IBRD / 84960 Post Direct Selection Direct 3,000.00 0.00 Canceled 2019-10-30 2019-11-04 2019-12-09 2020-06-06 Office boy Operational Systems EG-MOSS-40100-NC-DIR / Video shooting, due to satisfactory performance of a supplier that was selected Project Management and through shopping package, IBRD / 84960 Post Direct Selection Direct 2,500.00 0.00 Canceled 2017-12-31 2018-01-05 2018-02-09 2018-08-08 Monitoring and Evaluation we want to make a short documentary about Karama's system before and after the reform we had made EG-MOSS-85355-NC-RFQ / Project Management and Request for Single Stage - One Maintenance Service for PIU's IBRD / 84960 Post Limited 2,500.00 0.00 Canceled 2018-11-16 2018-12-16 2019-11-30 Monitoring and Evaluation Quotations Envelope air conditions EG-MOSS-73859-NC-RFQ / Support SSN Targeting and Request for Single Stage - One Providing production services IBRD / 84960 Post Limited 50,000.00 0.00 Canceled 2018-08-19 2018-09-28 2019-08-01 Operational Systems Quotations Envelope for short films/movies. EG-MOSS-78329-NC-DIR / Support SSN Targeting and Providing MoSS's PIU with PRI IBRD / 84960 Post Direct Selection Direct 10,000.00 0.00 Canceled 2018-09-18 2018-09-23 2018-10-28 2019-11-30 Operational Systems service EG-MOSS-34835-NC-RFQ / Developing Video Disc (15 minutes) of the conditionality Project Management and IBRD / 84960 Post Direct Selection Direct 5,000.00 0.00 Canceled 2017-12-03 2017-12-08 2018-01-12 2018-07-11 process for insliting potential Monitoring and Evaluation beneficiaries into and out of the program EG-MOSS-225309-NC-RFQ / The non-consulting service required is having short mobile messages sent via operator networks, with Support SSN Targeting and Request for Single Stage - One associated cost for each SMS IBRD / 84960 Post Limited 100,000.00 50,495.36 Signed 2021-03-26 2021-03-01 2021-05-21 2021-04-06 2021-11-17 Operational Systems Quotations Envelope passing through operator network. No technical consultation or expertise is requested, only using operator infrastructure. CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual EG-MOSS-11508-CS-QCBS / Communication Firm Support SSN Targeting and Quality And Cost- Under (Advocacy Strategy, IBRD / 84960 Post Open - National 150,000.00 0.00 2017-12-03 2017-08-15 2017-12-24 2018-02-06 2017-11-13 2018-03-06 2018-04-05 2018-05-10 2018-06-14 2019-06-14 Operational Systems Based Selection Implementation Communication Strategy, Design Materials etc.) Page 4 EG-MOSS-24306-CS-QCBS / Awareness campaign on "Rights of People with Project Management and Quality And Cost- IBRD / 84960 Post Open - National 230,000.00 256,593.35 Signed 2017-10-01 2017-08-20 2017-10-22 2017-12-05 2017-11-10 2018-01-02 2017-12-28 2018-02-01 2018-01-28 2018-03-08 2018-02-19 2018-04-12 2018-11-04 2019-04-12 Disability" (PwD) Monitoring and Evaluation Based Selection In Social Protection and Inclusion EG-MOSS-11506-CS-QCBS / Consultant Project Management and Local Community Dialogues IBRD / 84960 Post Qualification Open - National 50,000.00 0.00 Canceled 2017-11-01 2017-11-22 2018-01-05 2018-02-02 2018-03-04 2018-04-08 2018-05-13 2019-05-13 Monitoring and Evaluation Regular Administration Selection EG-MOSS-11503-CS-QCBS / Institutional Consultancy to Support SSN Targeting and Quality And Cost- IBRD / 84960 Post Open - National 120,000.00 0.00 Canceled 2017-09-03 2017-09-24 2017-11-07 2017-12-05 2018-01-04 2018-02-08 2018-03-15 2019-03-15 conduct Airing, Operational Systems Based Selection Advertisement, Video, Radio EG-MOSS-46782-CS-QCBS / Institutional capacity building Project Management and Quality And Cost- campaign for building IBRD / 84960 Post Open - National 80,000.00 0.00 Canceled 2018-01-30 2018-02-20 2018-07-08 2018-04-05 2018-05-03 2018-06-02 2018-07-07 2018-08-11 2019-08-11 Monitoring and Evaluation Based Selection capacities on "Takaful" conditionality EG-MOSS-11509-CS-QCBS / Technical / Thematic capacity Support SSN Targeting and Quality And Cost- building (M&E, MIS, Grievance, IBRD / 84960 Post Open - National 75,000.00 0.00 Canceled 2018-01-01 2018-01-22 2018-03-07 2018-04-04 2018-05-04 2018-06-08 2018-07-13 2019-07-13 Operational Systems Based Selection Conditionality, Social responsibility, NGOs TOT, etc) EG-MOSS-165374-CS-CQS / Conducting a Rapid Market Consultant Support SSN Targeting and Assessment for the “FORSA” IBRD / 89970 Post Qualification Open - National 6,500.00 0.00 Canceled 2020-03-24 2020-03-23 2020-04-14 2020-05-28 2020-06-27 2020-08-01 2021-01-28 Operational Systems Economic Empowerment Selection Program in Egypt EG-MOSS-165280-CS-CQS / Capacity building and training for the Master Trainers, a Consultant trainer for each governorate, Support SSN Targeting and IBRD / 89970 Post Qualification Open - National 60,000.00 163,307.79 Signed 2020-03-19 2020-03-29 2020-04-09 2020-05-08 2020-05-23 2020-10-12 2020-06-20 2021-01-03 2020-07-11 2021-01-03 2020-08-15 2021-01-03 2020-09-19 2021-03-08 2021-04-22 who will accordingly train the Operational Systems Selection targeted T&K enrolled candidates in each governorate. EG-MOSS-177408-CS-CQS / Performance Audit. The objective of the performance audit of the Eligible Expenditure Program (EEP) is Consultant Support SSN Targeting and to ascertain whether IBRD / 84960 Post Qualification Open - National 40,000.00 29,439.72 Signed 2020-06-02 2020-05-03 2020-06-23 2020-08-06 2020-05-10 2020-09-05 2020-05-25 2020-10-10 2020-06-04 2021-04-08 Operational Systems payments made under the EEP Selection are reaching eligible beneficiaries and to provide advice regarding the oversight and control framework EG-MOSS-221513-CS-CQS / Providing services for the annual advertising and Consultant promotional campaign for the Support SSN Targeting and Pending IBRD / 84960 Post Qualification Open - National 100,000.00 0.00 2021-02-24 2021-03-17 2021-04-30 2021-05-30 2021-07-04 2021-12-31 mechanisms and programs of Operational Systems Implementation Selection the Ministry of Social Solidarity through various social media platforms. EG-MOSS-235383-CS-QCBS / Hiring a System Integrator firm to design, development and operationalization of an integrated MIS platform. Also, Support SSN Targeting and Quality And Cost- Under to design, build, implement IBRD / 84960 Post Open - International 700,000.00 0.00 2021-05-27 2021-05-24 2021-06-07 2021-05-25 2021-07-08 2021-08-22 2021-09-02 2021-10-07 2021-10-28 2024-08-31 Operational Systems Based Selection Implementation data sharing mechanism for its integration among the relevant systems/modules and provide end users training. INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Individual EG-MOSS-13931-CS-INDV / Project Management and IBRD / 84960 Post Consultant Limited 30,000.00 0.00 Canceled 2017-07-31 2017-08-05 2017-08-26 2017-09-30 2018-03-29 PMU Office Manager Monitoring and Evaluation Selection EG-MOSS-58973-CS-INDV / Individual Project Management and Hiring Disability Advisor (ToR IBRD / 84960 Post Consultant Limited 20,000.00 4,164.58 Signed 2018-04-12 2018-03-14 2018-04-17 2019-01-15 2018-05-08 2019-01-23 2018-06-12 2019-02-01 2018-12-09 Monitoring and Evaluation attached) Selection EG-MOSS-58991-CS-INDV / Individual Project Management and Hiring Disability Operations IBRD / 84960 Post Consultant Limited 7,000.00 7,076.35 Signed 2018-04-12 2018-03-11 2018-04-17 2018-03-21 2018-05-08 2018-03-26 2018-06-12 2018-04-10 2018-12-09 Monitoring and Evaluation Officer Selection EG-MOSS-58992-CS-INDV / Individual Project Management and Hiring Disability Capacity IBRD / 84960 Post Consultant Limited 7,500.00 7,448.79 Signed 2018-04-12 2018-03-11 2018-04-17 2018-03-28 2018-05-08 2018-04-19 2018-06-12 2018-05-02 2018-12-09 Monitoring and Evaluation Development Officer Selection Individual EG-MOSS-58993-CS-INDV / Project Management and IBRD / 84960 Post Consultant Limited 24,000.00 18,622.35 Signed 2018-04-12 2018-03-05 2018-04-17 2018-09-12 2018-05-08 2018-09-20 2018-06-12 2018-10-01 2018-12-09 Hiring M&E Specialist Monitoring and Evaluation Selection EG-MOSS-58995-CS-INDV / Individual Project Management and Hiring Monitoring IBRD / 84960 Post Consultant Limited 8,000.00 8,317.82 Signed 2018-04-12 2018-03-15 2018-04-17 2018-03-19 2018-05-08 2018-03-25 2018-06-12 2018-04-01 2018-12-09 Monitoring and Evaluation Coordinators Selection EG-MOSS-59002-CS-INDV / Individual Project Management and Hiring Radio Episodes IBRD / 84960 Post Consultant Limited 5,500.00 9,310.99 Signed 2018-04-12 2018-03-21 2018-04-17 2018-03-28 2018-05-08 2018-04-11 2018-06-12 2018-04-17 2018-12-09 Monitoring and Evaluation Composer/Producer Selection Page 5 Individual EG-MOSS-70742-CS-INDV / Project Management and IBRD / 84960 Post Consultant Limited 10,000.00 4,840.21 Signed 2018-07-24 2018-06-25 2018-07-26 2018-06-26 2018-07-27 2018-06-27 2018-07-30 2018-07-01 2019-07-30 Photographer Monitoring and Evaluation Selection EG-MOSS-70743-CS-INDV / Individual Project Management and Conditionality Capacity IBRD / 84960 Post Consultant Limited 8,000.00 10,366.23 Signed 2018-07-26 2018-06-24 2018-07-28 2018-07-26 2018-07-29 2018-07-29 2018-07-31 2018-08-01 2019-01-27 Monitoring and Evaluation Building Expert Selection EG-MOSS-76654-CS-INDV / Individual Project Management and Hiring Regulatory & IBRD / 84960 Post Consultant Limited 28,500.00 31,036.63 Signed 2018-09-02 2018-08-21 2018-09-07 2018-08-26 2018-09-12 2018-08-30 2018-09-20 2018-09-04 2019-07-17 Monitoring and Evaluation Governance Consultant Selection EG-MOSS-76655-CS-INDV / Individual Support SSN Targeting and Hiring MIS Database IBRD / 84960 Post Consultant Limited 16,000.00 0.00 Under Review 2018-09-02 2018-08-19 2018-09-07 2018-09-12 2018-09-22 2019-06-30 Operational Systems Administrator Selection Individual EG-MOSS-76656-CS-INDV / Support SSN Targeting and IBRD / 84960 Post Consultant Limited 23,000.00 6,229.37 Signed 2018-09-03 2018-08-09 2018-09-08 2018-10-01 2018-09-14 2018-10-16 2018-09-23 2018-11-01 2019-06-30 Hiring MIS Business Analyst Operational Systems Selection Individual EG-MOSS-76657-CS-INDV / Support SSN Targeting and IBRD / 84960 Post Consultant Limited 24,500.00 29,041.27 Signed 2018-09-03 2018-08-14 2018-09-08 2018-08-22 2018-09-13 2018-08-28 2018-09-19 2018-09-09 2019-06-26 Hiring MIS TA Team Leader Operational Systems Selection Individual EG-MOSS-76658-CS-INDV / Project Management and IBRD / 84960 Post Consultant Limited 17,000.00 18,265.05 Signed 2018-09-02 2018-08-09 2018-09-07 2018-08-13 2018-09-10 2018-08-23 2018-09-17 2018-09-09 2019-06-30 Hiring MIS consultant Monitoring and Evaluation Selection Individual EG-MOSS-76660-CS-INDV / Project Management and IBRD / 84960 Post Consultant Limited 11,000.00 10,621.42 Signed 2018-09-05 2018-08-13 2018-09-10 2018-08-26 2018-09-15 2018-08-29 2018-09-21 2018-09-09 2019-06-30 Hiring IT specialist Monitoring and Evaluation Selection Individual EG-MOSS-76688-CS-INDV / Support SSN Targeting and IBRD / 84960 Post Consultant Limited 7,000.00 8,687.56 Signed 2018-09-03 2018-08-16 2018-09-08 2018-08-21 2018-09-11 2018-08-26 2018-09-18 2018-09-04 2018-10-18 Hiring ESMF Consultant Operational Systems Selection EG-MOSS-76935-CS-INDV / Hiring Bulk Data Entry Individual Consultants. Multiple Support SSN Targeting and IBRD / 84960 Post Consultant Limited 28,000.00 3,099.81 Signed 2018-09-06 2018-08-15 2018-09-26 2018-08-22 2018-10-01 2018-08-27 2018-10-18 2018-09-10 2019-05-16 consultants are expected to Operational Systems Selection be hired to perform such huge task. EG-MOSS-76937-CS-INDV / Individual Support SSN Targeting and Hiring MIS Software IBRD / 84960 Post Consultant Limited 13,500.00 0.00 Canceled 2018-09-05 2018-08-20 2018-09-10 2018-09-15 2018-09-30 2019-06-30 Operational Systems Development Consultant Selection Individual EG-MOSS-81681-CS-INDV / Support SSN Targeting and IBRD / 84960 Post Consultant Limited 23,000.00 0.00 Canceled 2018-10-11 2018-10-15 2018-10-16 2018-10-19 2018-10-24 2019-10-31 Hire GIS Consultant in the PIU Operational Systems Selection EG-MOSS-85352-CS-INDV / Individual Project Management and Hiring Advisor for Community IBRD / 84960 Post Consultant Limited 23,000.00 5,795.16 Signed 2018-11-01 2018-10-08 2018-11-06 2018-10-17 2018-11-11 2018-10-24 2018-11-21 2018-11-01 2019-10-31 Monitoring and Evaluation Affairs Selection EG-MOSS-95771-CS-INDV / Individual Hiring Civil Society Project Management and IBRD / 84960 Post Consultant Limited 22,000.00 25,026.62 Signed 2019-01-22 2018-12-03 2019-01-27 2018-12-23 2019-01-29 2018-12-25 2019-02-01 2019-01-01 2019-11-30 Organizations Coordinator in Monitoring and Evaluation Selection PIU EG-MOSS-95772-CS-INDV / Individual Hiring Strategy and Capacity Project Management and IBRD / 84960 Post Consultant Limited 22,000.00 25,026.62 Signed 2019-01-22 2018-12-18 2019-01-27 2018-12-20 2019-01-29 2018-12-23 2019-02-01 2019-01-01 2019-11-30 Development Coordinator in Monitoring and Evaluation Selection PIU EG-MOSS-95773-CS-INDV / Individual Project Management and Hiring Gender Outreach IBRD / 84960 Post Consultant Limited 22,000.00 25,034.39 Signed 2019-01-22 2018-12-16 2019-01-27 2018-12-12 2019-01-29 2018-12-24 2019-02-01 2019-01-01 2019-11-30 Monitoring and Evaluation Advisor Selection EG-MOSS-95774-CS-INDV / Individual Project Management and Hiring Senior Program IBRD / 84960 Post Consultant Limited 11,000.00 11,380.08 Signed 2019-01-22 2018-12-03 2019-01-27 2018-12-13 2019-01-29 2018-12-20 2019-02-01 2019-01-01 2019-11-30 Monitoring and Evaluation Assistant in PIU Selection EG-MOSS-85353-CS-INDV / Individual Project Management and Hiring Procurement Assistant IBRD / 84960 Post Consultant Limited 11,500.00 0.00 Canceled 2018-11-08 2018-11-13 2018-11-28 2018-12-08 2019-11-30 Monitoring and Evaluation (Jr procurement specialist) Selection EG-MOSS-117748-CS-INDV Individual Project Management and / Program Legal Advisor (6 IBRD / 84960 Post Consultant Limited 8,000.00 7,446.48 Signed 2019-06-01 2019-05-30 2019-06-06 2019-05-24 2019-06-27 2019-05-27 2019-08-01 2019-06-03 2020-01-28 Monitoring and Evaluation month agreement) Selection Individual EG-MOSS-117819-CS-INDV Project Management and IBRD / 84960 Post Consultant Limited 2,500.00 1,514.50 Signed 2019-06-03 2019-05-30 2019-06-08 2019-05-02 2019-06-29 2019-05-19 2019-08-03 2019-06-03 2020-01-30 / Translator/Interpreter (1) Monitoring and Evaluation Selection Individual EG-MOSS-117825-CS-INDV Project Management and IBRD / 84960 Post Consultant Limited 2,000.00 1,364.95 Signed 2019-06-03 2019-05-02 2019-06-08 2019-05-02 2019-06-29 2019-06-23 2019-08-03 2019-06-03 2020-01-30 / Translator/Interpreter (2) Monitoring and Evaluation Selection Individual EG-MOSS-117826-CS-INDV Project Management and IBRD / 84960 Post Consultant Limited 2,000.00 934.22 Signed 2019-06-03 2019-05-02 2019-06-08 2019-05-02 2019-06-29 2019-05-20 2019-08-03 2019-06-03 2020-01-30 / Translator/Interpreter (3) Monitoring and Evaluation Selection Individual EG-MOSS-117827-CS-INDV Project Management and IBRD / 84960 Post Consultant Limited 1,500.00 1,442.53 Signed 2019-06-03 2019-05-02 2019-06-08 2019-05-02 2019-06-29 2019-05-23 2019-08-03 2019-06-03 2020-01-30 / Translator/Interpreter (4) Monitoring and Evaluation Selection Individual EG-MOSS-117828-CS-INDV Project Management and IBRD / 84960 Post Consultant Limited 2,500.00 659.47 Signed 2019-06-03 2019-05-02 2019-06-08 2019-05-02 2019-06-29 2019-05-21 2019-08-03 2019-06-03 2020-01-30 / Translator/Interpreter (5) Monitoring and Evaluation Selection Individual EG-MOSS-117830-CS-INDV Project Management and IBRD / 84960 Post Consultant Limited 2,000.00 351.72 Signed 2019-06-03 2019-05-02 2019-06-08 2019-05-02 2019-06-29 2019-05-23 2019-08-03 2019-06-03 2020-01-30 / Translator/Interpreter (6) Monitoring and Evaluation Selection Page 6 Individual EG-MOSS-119697-CS-INDV Project Management and IBRD / 84960 Post Consultant Limited 16,000.00 6,884.14 Signed 2019-06-19 2019-06-23 2019-06-24 2019-06-02 2019-07-15 2019-06-18 2019-08-19 2019-07-01 2020-02-15 / Call Center Specialist Monitoring and Evaluation Selection Individual EG-MOSS-70741-CS-INDV / Project Management and IBRD / 84960 Post Consultant Limited 12,000.00 11,421.48 Signed 2018-07-24 2018-07-24 2018-07-26 2018-07-26 2018-07-27 2018-07-29 2018-07-31 2018-08-01 2019-07-31 Senior Multimedia Specialist Monitoring and Evaluation Selection Individual EG-MOSS-128015-CS-INDV Project Management and IBRD / 84960 Post Consultant Limited 10,000.00 0.00 Canceled 2019-08-19 2019-08-19 2019-08-24 2019-09-14 2019-10-19 2020-04-16 / Call Center Specialist Monitoring and Evaluation Selection Individual EG-MOSS-135023-CS-CQS / Support SSN Targeting and IBRD / 84960 Post Consultant Limited 10,000.00 10,276.20 Signed 2019-09-23 2019-07-15 2019-09-28 2019-07-11 2019-10-19 2019-07-16 2019-11-23 2019-07-22 2020-05-21 Disability Advisor Operational Systems Selection Individual EG-MOSS-141172-CS-INDV Support SSN Targeting and IBRD / 84960 Post Consultant Limited 1,000.00 5,797.64 Signed 2019-10-01 2019-10-01 2019-10-06 2019-09-15 2019-10-27 2019-09-22 2019-12-01 2019-10-01 2020-05-29 / Administrative Assistant Operational Systems Selection Individual EG-MOSS-141576-CS-INDV Support SSN Targeting and IBRD / 84960 Post Consultant Limited 5,000.00 24,821.60 Signed 2019-09-15 2019-09-15 2019-09-20 2019-09-17 2019-10-11 2019-09-19 2019-11-15 2019-10-01 2020-05-13 / Disability Officer Operational Systems Selection EG-MOSS-141559-CS-INDV Individual / The Consultant shall Support SSN Targeting and IBRD / 84960 Post Consultant Limited 3,400.00 3,447.41 Signed 2019-09-15 2019-08-08 2019-09-20 2019-08-15 2019-10-11 2019-08-28 2019-11-15 2019-09-15 2020-05-13 perform the Services as Social Operational Systems Selection Protection Officer. Individual EG-MOSS-141185-CS-INDV Support SSN Targeting and IBRD / 84960 Post Consultant Limited 15,000.00 14,089.14 Signed 2019-10-01 2019-10-01 2019-10-06 2019-10-03 2019-10-27 2019-10-06 2019-12-01 2019-10-15 2020-05-29 / Monitoring Coordinator Operational Systems Selection Individual EG-MOSS-143552-CS-INDV Support SSN Targeting and IBRD / 84960 Post Consultant Limited 2,700.00 2,325.73 Signed 2019-10-30 2019-09-12 2019-11-04 2019-09-17 2019-11-25 2019-09-22 2019-12-30 2019-10-01 2020-06-27 / Administrative Assistant Operational Systems Selection Individual EG-MOSS-143561-CS-INDV Support SSN Targeting and IBRD / 84960 Post Consultant Limited 5,000.00 4,153.43 Signed 2019-10-30 2019-09-10 2019-11-04 2019-09-17 2019-11-25 2019-09-24 2019-12-30 2019-10-01 2020-06-27 / Administrative Assistant Operational Systems Selection Individual EG-MOSS-143566-CS-INDV Support SSN Targeting and IBRD / 84960 Post Consultant Limited 5,000.00 4,580.45 Signed 2019-10-30 2019-10-30 2019-11-04 2019-10-22 2019-11-25 2019-10-27 2019-12-30 2019-11-01 2020-06-27 / Administrative Assistant Operational Systems Selection Individual EG-MOSS-143579-CS-INDV Support SSN Targeting and Pending IBRD / 84960 Post Consultant Limited 30,000.00 0.00 2019-11-25 2019-12-25 / Field Operation Manager Operational Systems Implementation Selection Individual EG-MOSS-143589-CS-INDV Support SSN Targeting and IBRD / 84960 Post Consultant Limited 34,000.00 30,813.99 Signed 2019-10-30 2019-10-15 2019-11-04 2019-10-17 2019-11-25 2019-10-22 2019-12-30 2019-11-01 2020-06-27 / GIS Consultant Operational Systems Selection Individual EG-MOSS-143591-CS-INDV Support SSN Targeting and IBRD / 84960 Post Consultant Limited 30,000.00 29,981.26 Signed 2019-10-30 2019-10-15 2019-11-04 2019-10-01 2019-11-25 2019-10-27 2019-12-30 2019-11-01 2020-06-27 / Senior researcher Operational Systems Selection EG-MOSS-147248-CS-INDV Individual Support SSN Targeting and / Monitoring & Evaluation and IBRD / 84960 Post Consultant Limited 40,000.00 42,221.15 Signed 2019-11-26 2019-11-25 2019-12-01 2019-11-24 2019-12-22 2019-12-01 2020-01-26 2019-12-15 2020-07-24 Operational Systems Research Advisor Selection EG-MOSS-147260-CS-INDV Individual Support SSN Targeting and / Health Conditionality IBRD / 84960 Post Consultant Limited 40,000.00 25,332.99 Signed 2019-11-26 2019-11-25 2019-12-01 2019-12-01 2019-12-22 2019-12-08 2020-01-26 2019-12-15 2020-07-24 Operational Systems Advisor Selection EG-MOSS-118096-CS-CDS / Provision of integrated social Project Management and protection services to enhance IBRD / 84960 Post Direct Selection Direct 200,000.00 0.00 Canceled 2019-06-04 2019-06-04 2019-06-14 2019-08-18 2020-02-14 Monitoring and Evaluation "Takaful and Karama" program among local communities EG-MOSS-151080-CS-INDV Individual Support SSN Targeting and / Education Conditionality IBRD / 84960 Post Consultant Limited 23,000.00 22,486.65 Signed 2019-12-18 2019-11-28 2019-12-23 2019-12-01 2020-01-13 2019-12-12 2020-02-17 2019-12-19 2020-08-15 Operational Systems Advisor Selection EG-MOSS-169705-CS-INDV Individual Support SSN Targeting and / Self-Employment and IBRD / 84960 Post Consultant Limited 42,000.00 42,116.23 Signed 2020-04-21 2020-05-01 2020-04-26 2020-04-19 2020-05-17 2020-04-26 2020-06-21 2020-05-01 2020-12-18 Operational Systems Livelihoods Manager Selection EG-MOSS-190238-CS-CDS / The objective of the financial audit service is to enable the auditor to express a single professional opinion on the Support SSN Targeting and IBRD / 84960 Post Direct Selection Direct 55,000.00 55,946.72 Signed 2020-08-25 2020-08-23 2020-09-04 2020-09-01 2020-11-08 2020-09-15 2021-05-07 financial position of the Operational Systems project at the end of each fiscal year, and on funds received and expenditures for a relevant accounting period Individual EG-MOSS-193761-CS-CQS / Support SSN Targeting and IBRD / 89970 Post Consultant Limited 15,000.00 13,775.51 Signed 2020-09-24 2020-09-21 2020-09-29 2020-11-10 2020-10-20 2020-11-15 2020-11-24 2020-11-25 2021-05-23 Program officer. Operational Systems Selection EG-MOSS-193762-CS-CQS / Individual Support SSN Targeting and Monitoring, Evaluation and IBRD / 89970 Post Consultant Limited 27,000.00 11,483.25 Signed 2020-09-24 2020-09-21 2020-09-29 2020-10-14 2020-10-20 2020-10-19 2020-11-24 2020-11-01 2021-05-23 Operational Systems Data Management Specialist. Selection Individual EG-MOSS-193766-CS-CQS / Support SSN Targeting and Under IBRD / 89970 Post Consultant Limited 12,000.00 0.00 2020-09-24 2020-09-21 2020-09-29 2020-10-20 2020-11-24 2021-05-23 Governorate Field Coordinator Operational Systems Implementation Selection Individual EG-MOSS-194034-CS-CQS / Support SSN Targeting and IBRD / 89970 Post Consultant Limited 27,000.00 22,959.18 Signed 2020-09-24 2020-09-21 2020-09-29 2020-10-14 2020-10-20 2020-10-18 2020-11-24 2020-11-01 2021-05-23 Senior employment officer. Operational Systems Selection Page 7 EG-MOSS-194311-CS-CQS / Individual Support SSN Targeting and Self-Employment and IBRD / 89970 Post Consultant Limited 27,000.00 26,768.64 Signed 2020-09-24 2020-09-21 2020-09-29 2020-12-15 2020-10-20 2020-12-20 2020-11-24 2021-01-01 2021-05-23 Operational Systems Livelihoods Senior Officer. Selection Individual EG-MOSS-194319-CS-CQS / Support SSN Targeting and IBRD / 89970 Post Consultant Limited 15,000.00 13,014.35 Signed 2020-09-24 2020-09-21 2020-09-29 2020-09-30 2020-10-20 2020-10-07 2020-11-24 2020-10-20 2021-05-23 Agribusiness officer. Operational Systems Selection Individual EG-MOSS-194329-CS-CQS / Support SSN Targeting and Under IBRD / 89970 Post Consultant Limited 38,000.00 0.00 2020-09-24 2020-09-21 2020-09-29 2020-10-20 2020-11-24 2021-05-23 wage employment manager. Operational Systems Implementation Selection Individual EG-MOSS-194348-CS-CQS / Support SSN Targeting and IBRD / 89970 Post Consultant Limited 23,000.00 20,676.45 Signed 2020-09-24 2020-09-21 2020-09-29 2020-09-28 2020-10-20 2020-10-01 2020-11-24 2020-10-15 2021-05-23 FORSA coordinator. Operational Systems Selection Individual EG-MOSS-194417-CS-CQS / Support SSN Targeting and Under IBRD / 89970 Post Consultant Limited 19,000.00 0.00 2020-09-24 2020-09-21 2020-09-29 2020-10-20 2020-11-24 2021-05-23 advocacy coordinator. Operational Systems Implementation Selection Individual EG-MOSS-215456-CS-CQS / Support SSN Targeting and IBRD / 84960 Post Consultant Limited 8,000.00 6,130.27 Signed 2021-01-25 2021-01-05 2021-01-30 2021-01-20 2021-02-20 2021-01-25 2021-03-27 2021-02-03 2021-09-23 M&E assistant Operational Systems Selection EG-MOSS-225235-CS-INDV / Financial manager that will prepare and extract regular Individual Support SSN Targeting and Under financial reports to assist IBRD / 84960 Post Consultant Limited 27,000.00 0.00 2021-03-17 2021-02-09 2021-03-22 2021-04-12 2021-05-17 2021-11-13 Operational Systems Implementation FORSA Program Director in Selection making decisions that affect the program. EG-MOSS-235090-CS-INDV / M & E Senior Advisor for 10 Individual Support SSN Targeting and Under days to provide technical IBRD / 84960 Post Consultant Limited 1,000.00 0.00 2021-05-23 2021-05-16 2021-05-28 2021-06-18 2021-07-23 2022-01-19 Operational Systems Implementation assistance to the FORSA Selection program. EG-MOSS-235353-CS-INDV Individual Support SSN Targeting and Under / Agribusiness & livestock IBRD / 84960 Post Consultant Limited 4,000.00 0.00 2021-05-23 2021-05-16 2021-05-28 2021-06-18 2021-07-23 2022-01-19 Operational Systems Implementation advisor. Selection Page 8 PROCUREMENT PLAN (Textual Part) Project information: [Mozambique] [Sustainable Rural Economy Program] [P-174002] Project Implementation agency: [Ministério da Agricultura e Desenvolvimento Rural] Date of the Procurement Plan: [2021, 01 April] Period covered by this Procurement Plan: [18 months] Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (November 2020) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in “Regulamento de Contratação de Empreitada de Obras Públicas, Fornecimento de Bens e Prestação de Serviços ao Estado” of the Republic of Mozambique of March 8, 2016 (“the Regulation”), as per Decree No. 5/2016, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). NA Goods: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables]; To be identified Works: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables]: To be identified Other Relevant Procurement Information. NA PROCUREMENT Mozambique : Sustainable Rural Economy Program PLAN General Information Country: Mozambique Bank’s Approval Date of the Original Procurement Plan: 2021-05-07 2021-05-20 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P174002 GPN Date: Project Name: Sustainable Rural Economy Program Loan / Credit No: / Foundation for the Conservation of Biodiversity Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 10/ANAC/SREP/G/21 / Under Enhancing natural resources Acquisition of 5 motorbike for / Post Direct Selection Direct 5,000.00 0.00 Implementati 2021-06-15 2021-06-03 2021-06-20 2021-07-25 2022-01-21 management Tchuma Tchato on NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 08/ANAC/SREP/CQS/21 / Consultant Development of the Enhancing natural resources / Post Qualification Open - National 23,200.00 0.00 Under Review 2021-05-31 2021-06-03 2021-06-21 2021-08-04 2021-09-03 2021-10-08 2022-04-06 Management Plan for the management Selection Mágoe National Park 09/ANAC/SREP/CQS/21 / Development of an Integrated Consultant Enhancing natural resources Development Plan for the / Post Qualification Open - National 80,000.00 0.00 Under Review 2021-05-31 2021-06-03 2021-06-21 2021-08-04 2021-09-03 2021-10-08 2022-04-06 management Tchuma Tchato Community Selection Program INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 01/BIOFUND/SREP/IC/21 / Individual Strengthening institutions Under Procurement Officer for / Prior Consultant Open 72,000.00 0.00 2021-05-31 2021-06-09 2021-07-19 2021-08-09 2021-09-13 2022-03-12 and policies Implementation BIOFUND Selection Individual 02/BIOFUND/SREP/IC/21 / Strengthening institutions Under / Post Consultant Open 60,000.00 0.00 2021-05-31 2021-06-03 2021-07-19 2021-08-09 2021-09-13 2022-03-12 Accountant for BIOFUND and policies Implementation Selection 07/ANAC/SREP/IC/21 / Individual Finance and Human Resources Enhancing natural resources Under / Post Consultant Open 60,000.00 0.00 2021-05-31 2021-06-03 2021-07-19 2021-08-09 2021-09-13 2022-03-12 Officer for Mágoe National management Implementation Selection Park 06/ANAC/SREP/IC/21 / Community Development and Individual Enhancing natural resources Under Environmental Education / Post Consultant Open 60,000.00 0.00 2021-05-31 2021-06-03 2021-07-19 2021-08-09 2021-09-13 2022-03-12 management Implementation Officer for the Mágoe National Selection Park 04/ANAC/SREP/IC/21 / Individual Enhancing natural resources Under Operations Manager for / Post Consultant Open 103,200.00 0.00 2021-05-31 2021-06-10 2021-07-19 2021-08-09 2021-09-13 2022-03-12 management Implementation Tchuma Tchato Selection 05/ANAC/SREP/IC/21 / Community Development and Individual Enhancing natural resources Under Environmental Education / Post Consultant Open 60,000.00 0.00 2021-05-31 2021-06-03 2021-07-19 2021-08-09 2021-09-13 2022-03-12 management Implementation Officer for the Tchuma Tchato Selection Community Program 03/ANAC/SREP/IC/21 / Individual Enhancing natural resources Under Operations Manager for / Post Consultant Open 103,200.00 0.00 2021-05-31 2021-06-03 2021-07-19 2021-08-09 2021-09-13 2022-03-12 management Implementation Mágoe National Park Selection Page 1 Programa de Inversiones para el Desarrollo Sostenible, P147342 PRESUPUESTO GLOBAL CONSOLIDADO (Expresado en millones de US$.) COSTOS DEL PROGRAMA Costo Total BANCO Componentes OEFA % de Financiamiento Programa MUNDIAL Componente 1: Monitoreo y USD USD USD 61,432,392 87.2% Análisis Ambiental 37,277,479 24,154,913 Componente 2: Divulgación de USD USD 4,829,837 USD 2,107,316 6.9% Información y Participación Pública 2,722,521 Componente 3: Gestión del USD 4,159,319 USD 4,159,319 5.9% Programa USD USD Costo Total USD 70,421,548 100% 40,000,000 30,421,548 From: Selene del Rocio La Vera Sent: Tuesday, November 08, 2016 9:37 AM To: Fernando Loayza Subject: FW: Plan de Adquisiciones Estimado Fernando He revisado esta versión del plan de adquisiciones, correspondiente a los primeros 18 meses de implementación del Proyecto, y la encuentro aceptable, por lo que si estás de acuerdo desde el punto de vista técnico, se podría dar la No Objeción. Saludos, Rocío La Vera Zavaleta Procurement Specialist Governance T PROCUREMENT Peru : Peru: Enhancement of Environmental Quality Services PLAN General Information Country: Peru Bank’s Approval Date of the Original Procurement Plan: 2017-08-10 2021-05-26 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P147342 GPN Date: 2017-08-09 Project Name: Peru: Enhancement of Environmental Quality Services Loan / Credit No: IBRD / 86800 O Executing Agency(ies): rganismo de Evaluación y Fiscalización Ambiental WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned PE-OEFA-163557-CW-RFQ / Information Information 2.2.1 Implementacion e Disclosure and Public Request for Single Stage - One 2020-11- Instalación del Cable IBRD / 86800 Participation for Post Open - National 104,860.00 61,401.64 Completed 2020-03-14 2020-05-09 2020-12-01 Quotations Envelope 05 Alimentador eléctrico al Area Environmental Quality del Data Center del MINAM Control PE-OEFA-225725-CW-RFB / Actividad 1.3.10: Construcción de Improve Environmental 27,614,667.5 Under 2022-10- IBRD / 86800 Prior Request for Bids 0.00 2021-03-24 2021-04-02 2021-05-14 2021-05-29 2021-07-03 infraestructura de laboratorio Quality Control 4 Review 12 e implementación de equipamiento GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PE-OEFA-52991-GO-RFB / 2.1.2 Mejoramiento de las Information Information capacidades tecnológicas del Disclosure and Public SENAMHI para la provisión de Single Stage - One IBRD / 86800 Participation for Prior Request for Bids Open - National 1,121,965.00 0.00 Canceled 2018-07-23 2018-08-07 2018-09-21 2018-10-21 2018-11-25 2019-03-25 datos meteorológicos, Envelope Environmental Quality hidrológicos, Control agrometeorológicos y ambientales al SINIA-SICCA PE-OEFA-52993-GO-RFB / 2.2.1 Mejoramiento de infraestructura Informatica del Information Information Data Center del MINAM que Disclosure and Public Single Stage - One posibilite el almacenamiento, IBRD / 86800 Participation for Prior Request for Bids Open - National 1,003,060.00 0.00 Canceled 2018-07-23 2018-08-07 2018-09-21 2018-10-21 2018-11-25 2019-04-24 Envelope adecuación, procesamiento y Environmental Quality distribución de información Control para el control de la calidad ambiental PE-OEFA-121005-GO-APA / 2.1.2 Mejoramiento de las capacidades tecnológicas del Information Information SENAMHI para la provisión de Disclosure and Public Single Stage - One datos meteorológicos, IBRD / 86800 Participation for Post Request for Bids Open - National 1,121,965.00 0.00 Canceled 2019-09-01 2019-09-13 2019-09-06 2019-09-13 2019-10-18 2019-11-17 2019-12-22 2020-06-19 Envelope hidrológicos, Environmental Quality agrometeorológicos y Control ambientales al SINIA-SICCA (PE-OEFA-52991-GO-RFB) PE-OEFA-121007-GO-RFB / 2.2.1 Mejoramiento de infraestructura Informatica del Information Information Data Center del MINAM que Disclosure and Public posibilite el almacenamiento, Single Stage - One IBRD / 86800 Participation for Post Request for Bids Open - National 1,003,060.00 0.00 Canceled 2020-05-01 2020-05-06 2020-06-17 2020-07-17 2020-08-21 2021-02-17 adecuación, procesamiento y Envelope Environmental Quality distribución de información Control para el control de la calidad ambiental (PE-OEFA-52993- GO-RFB) PE-OEFA-194432-GO-RFB / 2.2.1 Adquisición de bienes para el mejoramiento de infraestructura informática del Information Information Data Center del MINAM y Disclosure and Public Single Stage - One SENAMHI que posibilite el IBRD / 86800 Participation for Prior Request for Bids Open - International 5,322,948.00 0.00 Canceled 2020-09-17 2020-10-30 2020-09-22 2020-10-30 2020-11-03 2021-03-26 2020-11-18 2021-04-12 2020-12-16 2021-06-14 Envelope almacenamiento, adecuación, Environmental Quality procesamiento y distribución Control de información para el control de la calidad ambiental (121007) PE-OEFA-230141-GO-RFB / 2.2.1 Adquisición de bienes para el mejoramiento de infraestructura informática del Information Information Data Center del MINAM y Disclosure and Public Under Single Stage - One SENAMHI que posibilite el IBRD / 86800 Participation for Prior Request for Bids Open - International 5,322,948.00 0.00 Implementati 2021-04-19 2021-05-02 2021-04-25 2021-05-05 2021-06-06 2021-06-21 2021-07-19 2022-01-15 Envelope almacenamiento, adecuación, Environmental Quality on procesamiento y distribución Control de información para el control de la calidad ambiental (194432) PE-OEFA-238838-GO-RFB / 1.2.7 Implementación de Improve Environmental Single Stage - One Estaciones y equipos de IBRD / 86800 Prior Request for Bids Open - International 13,875,586.72 0.00 Under Review 2021-06-10 2021-06-15 2021-07-27 2021-08-26 2021-09-30 2022-03-29 Quality Control Envelope monitoreo de la calidad del agua y suelo NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 1 PE-OEFA-81024-NC-RFQ / Servicio de gestión integral para la habilitación urbana del terreno para la construcción Improve Environmental Request for Single Stage - One IBRD / 86800 Post Open - National 25,000.00 12,178.82 Completed 2018-10-17 2018-12-12 2018-11-26 2019-06-10 2019-10-08 del laboratorio de análisis de Quality Control Quotations Envelope muestras ambientales y de validación y dirimencia del OEFA PE-OEFA-163551-NC-RFQ / Information Information 2.2.1 Servicio de Adecuación Disclosure and Public Request for Single Stage - One de Ambientes para el Nuevo IBRD / 86800 Participation for Post Open - National 39,320.00 46,430.96 Signed 2020-03-14 2020-05-09 2020-10-19 2020-11-05 Quotations Envelope Data Center del Ministerio del Environmental Quality Ambiente (MINAM) Control CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PE-OEFA-17166-CS-CQS / 1.1.3 Consultoría para la elaboración de propuesta de Protocolo Nacional de Consultant Improve Environmental Monitoreo de la Calidad de IBRD / 86800 Post Qualification Open - International 50,000.00 99,162.14 Signed 2017-08-21 2017-08-16 2017-09-05 2017-09-25 2017-09-15 2017-10-15 2017-10-27 2017-11-04 2017-11-20 2018-04-03 Quality Control Aire y Directiva para realizar Selection auditorias de aseguramiento de monitoreo de calidad de aire. Information Information PE-OEFA-17381-CS-CQS / Disclosure and Public Consultant 2.5.0.3 Elaboración del IBRD / 86800 Participation for Post Qualification Open - International 60,976.36 57,205.50 Signed 2017-08-21 2017-09-13 2017-09-05 2017-09-25 2017-10-26 2017-10-12 2017-12-04 2017-10-25 2017-12-06 2017-12-24 estudio de demanda Environmental Quality Selection Control PE-OEFA-17288-CS-QCBS / 1.1.12 Elaboración de estudios base que sirvan de Improve Environmental Quality And Cost- insumo para la elaboración de IBRD / 86800 Post Open - International 91,373.00 0.00 Canceled 2017-10-16 2017-11-22 2017-10-31 2017-11-30 2018-01-22 2017-12-30 2018-02-28 2018-01-09 2018-04-04 2018-02-06 2018-03-02 2018-09-28 Quality Control Based Selection propuestas técnicas de ECA y LMP para Efluentes que se prioricen PE-OEFA-17290-CS-QCBS / 1.1.15 Identificar las actividades extractivas Improve Environmental Quality And Cost- relacionadas a sustancias IBRD / 86800 Post Open - International 73,098.30 0.00 Canceled 2017-11-01 2017-11-22 2018-01-05 2018-02-02 2018-03-04 2018-04-08 2018-05-13 2018-11-19 Quality Control Based Selection peligrosas que pueden afectar al suelo en la cuenca del río Rímac PE-OEFA-34855-CS-QBS / 1.2.1 Estudio para la determinación de la ubicación Improve Environmental Quality Based IBRD / 86800 Post Open - National 179,274.00 269,007.69 Signed 2017-10-31 2017-09-06 2017-10-31 2018-01-18 2017-11-02 2017-11-06 2017-11-30 2017-12-12 2017-12-05 2018-01-05 2017-12-20 2018-03-08 2017-12-29 2018-03-19 2018-06-27 de las estaciones fijas del Quality Control Selection monitoreo de aire en provincias PE-OEFA-17353-CS-QCBS / 1.2.1 Estudio para la determinación de la ubicación Improve Environmental Quality And Cost- IBRD / 86800 Post Open - International 182,930.00 0.00 Canceled 2017-09-11 2017-09-06 2017-09-26 2017-10-06 2017-11-05 2017-11-11 2017-11-20 2017-12-16 2018-07-14 de las estaciones fijas del Quality Control Based Selection monitoreo de aire en provincias PE-OEFA-17360-CS-QCBS / 1.2.6.1 Consultoría para el monitoreo integral de la cuenca del rio Rimac Improve Environmental Quality And Cost- IBRD / 86800 Prior Open - International 1,184,603.00 1,496,522.47 Signed 2018-03-12 2018-06-19 2018-03-27 2018-06-21 2018-05-01 2018-10-24 2018-05-31 2018-12-27 2018-06-25 2019-01-24 2018-07-30 2019-06-03 2018-08-19 2019-07-12 2019-04-16 (Consultoría para el diseño y Quality Control Based Selection planificacion de la red de monitoreo de calidad de agua y suelo) PE-OEFA-48940-CS-QCBS / 1.2.6.2 Consultoría para el monitoreo integral de la cuenca del Río Moche Improve Environmental Quality And Cost- IBRD / 86800 Post Open - International 394,868.00 0.00 Canceled 2018-10-08 2018-10-23 2018-11-22 2018-12-22 2019-01-11 2019-02-11 2019-02-26 2020-01-22 (Consultoría para el diseño y Quality Control Based Selection planificacion de la red de monitoreo de calidad de agua y suelo) PE-OEFA-17165-CS-CQS / 1.1.2 Consultoría para Consultant elaborar la propuesta de ECA Improve Environmental IBRD / 86800 Post Qualification Open - International 80,792.00 154,830.00 Signed 2018-03-26 2018-03-23 2018-04-10 2018-05-10 2018-05-24 2018-06-09 2018-09-27 2018-07-04 2019-01-18 2018-12-21 aire respecto a metales Quality Control Selection pesados (Incluye el análisis de impacto regulatorio) PE-OEFA-48951-CS-CQS / 1.1.4 Consultoría para la elaboración de propuesta de LMP de emisiones para las Consultant Improve Environmental siguientes actividades: a) IBRD / 86800 Post Qualification Open - National 84,732.00 0.00 Canceled 2018-03-26 2018-04-11 2018-05-16 2018-06-05 2018-07-01 2019-03-08 Quality Control siderúrgica y fundiciones, b) Selection actividades minero metalúrgicas, c) calderos industriales, y d) Ladrilleras. PE-OEFA-49972-CS-CQS / 1.1.17 Elaboración del Manual de determinación de la línea Consultant Improve Environmental base de calidad de suelos, en IBRD / 86800 Post Qualification Open - National 19,797.00 0.00 Canceled 2018-07-30 2018-08-15 2018-09-14 2018-10-14 2018-11-08 2019-02-16 Quality Control el marco de la elaboración de Selection estudios de impacto ambiental. PE-OEFA-17354-CS-QCBS / 1.2.2.1 Elaboración de estudio Improve Environmental Quality And Cost- definitivo para las estaciones IBRD / 86800 Post Open - International 320,613.00 0.00 Canceled 2018-08-27 2018-09-11 2018-10-11 2018-11-10 2018-11-25 2018-12-25 2019-01-14 2019-04-14 Quality Control Based Selection y equipos de monitoreo de la calidad del aire Page 2 PE-OEFA-17357-CS-QCBS / 1.2.4 Diseño y ejecución de un programa de Improve Environmental Quality And Cost- fortalecimiento y/o desarrollo IBRD / 86800 Post Open - International 338,730.00 0.00 Canceled 2018-06-25 2018-07-11 2018-08-10 2018-09-09 2018-09-29 2018-11-08 2018-11-28 2020-12-27 Quality Control Based Selection de capacidades para las actividades de monitoreo ambiental PE-OEFA-17367-CS-CQS / Consultant Improve Environmental 1.3.3 Estudio de IBRD / 86800 Post Qualification Open - International 50,000.00 0.00 Canceled 2019-06-24 2019-07-09 2019-08-08 2019-09-02 2019-10-02 2020-03-20 Quality Control sostenibilidad financiera Selection PE-OEFA-17376-CS-QCBS / 1.3.15 Consultoría para la Improve Environmental Quality And Cost- IBRD / 86800 Post Open - International 194,000.00 0.00 Canceled 2018-04-30 2018-05-15 2018-06-14 2018-07-14 2018-08-03 2018-09-07 2018-09-27 2019-01-25 generación de línea base del Quality Control Based Selection proyecto Information Information PE-OEFA-17383-CS-QCBS / Disclosure and Public 2.5.0.5.2 Supervisión de la Quality And Cost- Pending IBRD / 86800 Participation for Post Open - International 151,304.00 0.00 2018-10-01 2018-10-16 2018-11-10 2018-12-10 2018-12-30 2019-01-29 2019-02-08 2020-06-30 implementación del Based Selection Implementation Environmental Quality Componente 2 Control Information Information PE-OEFA-49993-CS-CQS / Disclosure and Public Consultant 2.5.0.5.1 Supervisión del IBRD / 86800 Participation for Post Qualification Open - International 50,000.00 0.00 Canceled 2018-06-25 2018-07-11 2018-08-10 2018-08-30 2018-09-24 2019-02-21 estudio definitivo del Environmental Quality Selection Componente 2 Control PE-OEFA-17364-CS-QCBS / 1.2.10.1 Servicio de supervisión de la adquisición Improve Environmental Quality And Cost- de equipos e implementación IBRD / 86800 Prior Open - International 533,585.00 0.00 Canceled 2019-01-21 2019-02-11 2019-03-27 2019-04-24 2019-05-24 2019-06-28 2019-08-02 2020-06-27 Quality Control Based Selection de las estaciones de monitoreo de la calidad del aire PE-OEFA-17370-CS-QCBS / 1.3.6 Elaboración de Expediente Técnico de la Improve Environmental Quality And Cost- IBRD / 86800 Prior Open - International 1,100,210.22 570,738.00 Signed 2018-04-30 2018-05-22 2018-05-20 2018-05-25 2018-06-19 2018-10-23 2018-07-19 2018-12-12 2018-08-08 2019-01-16 2018-09-12 2019-05-19 2018-10-12 2019-06-10 2019-08-08 Infraestructura de Laboratorio Quality Control Based Selection y Especificaciones Técnicas de Equipos de Laboratorio PE-OEFA-62963-CS-QBS / 1.3.15 Consultoría para la Improve Environmental Quality Based IBRD / 86800 Post Open - National 194,000.00 194,000.00 Signed 2018-05-16 2018-04-12 2018-05-16 2018-05-20 2018-05-16 2018-06-19 2018-06-18 2018-07-04 2018-06-27 2018-08-03 2018-07-03 2018-08-13 2018-08-24 2018-12-21 generación de la Línea Base Quality Control Selection del Programa PE-OEFA-64697-CS-QCBS / 1.1.4 Elaboración de propuesta de LMP de emisiones para las siguientes Improve Environmental Quality And Cost- actividades: a) siderúrgica y IBRD / 86800 Post Open - International 235,001.00 236,885.00 Signed 2018-06-11 2018-05-30 2018-06-26 2018-07-16 2018-10-10 2018-08-15 2018-11-27 2018-09-04 2019-01-31 2018-10-14 2019-03-11 2018-11-03 2019-04-17 2019-05-02 Quality Control Based Selection fundiciones, b) actividades minero metalúrgicas, c) calderos industriales y d) ladrilleras PE-OEFA-49986-CS-QCBS / 1.2.2.2 Elaboración de estudio Improve Environmental Quality And Cost- definitivo para las estaciones IBRD / 86800 Prior Open - National 530,649.35 746,903.40 Signed 2018-06-25 2018-07-20 2018-07-11 2018-07-25 2018-08-20 2018-11-12 2018-09-19 2019-01-28 2018-10-09 2019-02-18 2018-11-18 2019-05-24 2019-01-02 2019-08-21 2019-07-11 Quality Control Based Selection y equipos de monitoreo de la calidad del agua y/o suelo PE-OEFA-17371-CS-QCBS / 1.3.8.1 Servicio de Improve Environmental Quality And Cost- supervisión del expediente IBRD / 86800 Prior Open - International 407,009.23 574,210.49 Signed 2019-02-25 2018-06-20 2019-03-12 2018-07-06 2019-04-11 2018-12-07 2019-05-11 2019-01-21 2019-05-31 2019-02-13 2019-07-10 2019-05-23 2019-08-04 2019-06-27 2019-11-02 Quality Control Based Selection técnico (diseño) de la infraestructura y equipos de laboratorio PE-OEFA-17358-CS-QCBS / 1.2.5 Consultoría de Improve Environmental Quality And Cost- inventario de emisiones, IBRD / 86800 Prior Open - International 1,000,000.00 1,044,513.91 Signed 2018-07-23 2018-10-17 2018-08-08 2018-10-19 2018-09-07 2019-04-08 2018-10-07 2019-05-27 2018-10-27 2021-04-12 2018-12-06 2021-04-19 2018-12-26 2020-02-03 2019-10-22 Quality Control Based Selection evaluación de red de monitoreo de Lima PE-OEFA-17289-CS-QCBS / 1.1.14.1 Consultoría para la realización de un inventario de actividades productivas, Improve Environmental Quality And Cost- extractivas y de servicios IBRD / 86800 Post Open - International 136,604.00 0.00 Canceled 2018-08-06 2018-08-22 2018-09-21 2018-10-21 2018-11-15 2018-12-25 2019-01-14 2019-07-23 Quality Control Based Selection relacionadas a sustancias peligrosas que pueden afectar al suelo en la cuenca del río Rímac. PE-OEFA-17374-CS-CQS / Consultant 1.3.9 Consultoría para la Improve Environmental IBRD / 86800 Post Qualification Open - International 60,000.00 0.00 Canceled 2019-01-21 2019-02-05 2019-03-07 2019-04-06 2019-05-01 2019-09-08 elaboración del estudio de Quality Control Selection impacto ambiental PE-OEFA-52983-CS-CQS / 1.1.8 Elaboración del diagnóstico de las tecnologías de procesos productivos y de las tecnologías de Consultant Improve Environmental tratamiento de las aguas IBRD / 86800 Post Qualification Open - National 46,419.00 0.00 Canceled 2019-01-14 2019-01-29 2019-02-28 2019-03-30 2019-04-24 2019-10-21 Quality Control residuales industriales Selection procedentes de las principales actividades económicas productivas ubicadas en la cuenca del rio Moche PE-OEFA-17380-CS-QCBS / 2.5.0.2.2 Elaboración de estudios definitivos para la Information Information implementación del Disclosure and Public Componente 2 Quality And Cost- IBRD / 86800 Participation for Prior Open - International 539,218.01 557,486.28 Signed 2018-07-02 2018-10-16 2018-07-17 2018-10-29 2018-08-16 2019-01-14 2018-09-15 2019-04-05 2018-10-05 2019-05-09 2018-11-04 2019-10-04 2018-11-24 2019-11-06 2019-02-22 (estandarización de Based Selection Environmental Quality procedimientos para el Control intercambio de datos sobre el control de la calidad ambiental) Page 3 PE-OEFA-82610-CS-QCBS / 1.1.12 Elaboración de Propuesta de LMP de efluentes para la industria Improve Environmental Quality And Cost- IBRD / 86800 Post Open - International 333,118.00 278,981.95 Signed 2018-10-24 2019-03-20 2018-11-14 2018-12-28 2019-05-13 2019-01-25 2019-06-24 2019-02-24 2019-07-31 2019-03-31 2020-05-07 2019-05-05 2020-07-20 2020-05-04 manufacturera, actividades Quality Control Based Selection agroindustriales, camales, plantas de beneficio y energía eléctrica PE-OEFA-88464-CS-QCBS / 1.2.3.2 Consultoría para revisión del estudio definitivo Improve Environmental Quality And Cost- (especificaciones técnicas / IBRD / 86800 Post Open - National 128,517.00 209,992.00 Signed 2018-11-29 2019-01-16 2018-12-20 2019-02-02 2019-04-16 2019-03-02 2019-05-28 2019-04-01 2019-06-07 2019-05-06 2019-09-11 2019-06-10 2019-11-20 2020-06-09 Quality Control Based Selection expediente técnico) para las estaciones de monitoreo de la calidad del agua y/o suelo PE-OEFA-112769-CS-QCBS / 1.2.2.1 ELABORACIÓN DE ESTUDIO DEFINITIVO (ESPECIFICACIONES TÉCNICAS Improve Environmental Quality And Cost- IBRD / 86800 Prior Open - International 1,095,671.00 386,860.73 Signed 2019-04-30 2019-05-23 2019-05-21 2019-05-30 2019-07-04 2021-04-28 2019-08-01 2019-10-24 2019-08-31 2021-04-28 2019-10-05 2021-04-29 2019-11-09 2020-11-09 2020-11-08 / EXPEDIENTE TÉCNICO) PARA Quality Control Based Selection LAS ESTACIONES Y EQUIPOS DE MONITOREO DE LA CALIDAD DEL AIRE PE-OEFA-120854-CS-QCBS / 1.2.10.1 Servicio de supervisión de la adquisición de equipos e implementación Improve Environmental Quality And Cost- Pending IBRD / 86800 Post Open - International 533,585.00 0.00 2021-06-01 2021-06-22 2021-08-05 2021-09-02 2021-10-02 2021-11-06 2021-12-11 2022-12-11 de las estaciones de Quality Control Based Selection Implementation monitoreo de la calidad del aire (PE-OEFA-17364-CS- QCBS) PE-OEFA-124818-CS-QCBS / 1.2.3.1 Revisión de estudio definitivo para las estaciones Improve Environmental Quality And Cost- IBRD / 86800 Post Open - International 291,699.00 281,298.97 Signed 2019-07-25 2019-08-02 2019-08-15 2019-09-28 2019-11-13 2019-10-26 2020-02-05 2019-11-25 2020-03-04 2019-12-30 2020-05-18 2020-02-03 2020-11-11 2021-02-02 de monitoreo de la calidad del Quality Control Based Selection aire (PE-OEFA-49987-CS- INDV) PE-OEFA-233773-CS-QCBS / 1.3.8.2 “Servicio de supervisión de la Improve Environmental Quality And Cost- Under IBRD / 86800 Post Open - International 1,106,016.83 0.00 2021-05-12 2021-05-18 2021-06-02 2021-06-20 2021-07-16 2021-08-13 2021-09-12 2021-10-17 2021-11-21 2022-11-21 infraestructura e Quality Control Based Selection Implementation implementación de los equipos de laboratorio” PE-OEFA-236741-CS-CQS / Consultant 1.2.11 Mejora del Sistema de Improve Environmental Under IBRD / 86800 Post Qualification Open - National 23,223.68 0.00 2021-05-28 2021-06-03 2021-06-18 2021-08-01 2021-08-31 2021-10-05 2022-04-03 Gestión de Residuos Sólidos Quality Control Implementation Selection (SIGERSOL) PE-OEFA-240186-CS-QCBS / 1.3.10 Consultoría para la Elaboración del Estudio definitivo y Expediente Improve Environmental Quality And Cost- Pending Técnico para la rehabilitación IBRD / 86800 Post Open - International 68,069.72 0.00 2021-06-21 2021-07-12 2021-08-25 2021-09-22 2021-10-22 2021-11-26 2021-12-31 2022-12-31 Quality Control Based Selection Implementation del servicio de alcantarillado en el terreno donde se construirá el laboratorio del OEFA INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PE-OEFA-17368-CS-INDV / 1.3.5 Elaboración de TdR para la elaboración del Expediente Individual Improve Environmental Técnico de la infraestructura IBRD / 86800 Post Consultant Limited 15,000.00 15,081.48 Signed 2017-09-08 2017-11-20 2017-09-18 2017-11-27 2017-09-28 2017-12-13 2017-10-18 2017-12-29 2018-01-26 Quality Control de laboratorio y las Selection Especificaciones Técnicas de los equipos de laboratorio PE-OEFA-17365-CS-INDV / Individual Improve Environmental 1.3.1 Estudio detallado de la IBRD / 86800 Post Consultant Limited 24,317.00 24,569.89 Signed 2017-08-29 2017-10-17 2017-09-08 2017-10-17 2017-09-15 2017-11-02 2017-09-27 2017-11-07 2017-12-26 Quality Control demanda y análisis de riesgo Selection PE-OEFA-17366-CS-INDV / Individual 1.3.2 Análisis legal para Improve Environmental IBRD / 86800 Post Consultant Limited 7,599.00 10,827.10 Signed 2017-10-03 2017-10-30 2017-10-13 2017-11-08 2017-10-20 2017-12-01 2017-11-01 2017-12-05 2017-12-21 implementar el laboratorio de Quality Control Selection dirimencia PE-OEFA-17379-CS-INDV / Information Information 2.5.0.1 Elaboración de Disclosure and Public Individual Términos de Referencia para IBRD / 86800 Participation for Post Consultant Limited 5,519.00 6,629.62 Signed 2017-09-14 2017-10-18 2017-09-24 2017-10-21 2017-10-02 2017-11-09 2017-10-14 2017-11-15 2017-12-03 expediente técnico del Environmental Quality Selection componente 2 Control Information Information PE-OEFA-17382-CS-INDV / Disclosure and Public Individual 2.5.0.4 Elaboración de IBRD / 86800 Participation for Post Consultant Limited 7,622.00 6,629.62 Signed 2017-09-15 2017-10-18 2017-09-25 2017-10-20 2017-10-05 2017-11-10 2017-10-22 2017-11-15 2017-12-11 Términos de Referencia para Environmental Quality Selection supervisión Control PE-OEFA-17164-CS-INDV / 1.1.1 Consultoría para la elaboración de Guía Metodológica para la Individual Improve Environmental Estimación de Costos y IBRD / 86800 Post Consultant Limited 25,510.00 30,812.00 Signed 2018-04-23 2018-03-20 2018-05-03 2018-03-23 2018-05-10 2018-05-25 2018-05-22 2018-06-13 2018-09-19 Quality Control Beneficios de la Normativa de Selection Calidad de Aire, en el Marco del Análisis de Impacto Regulatorio (RIA) PE-OEFA-49967-CS-INDV / 1.1.18 Elaboración de Individual Improve Environmental propuesta base para la IBRD / 86800 Post Consultant Limited 34,732.00 0.00 Canceled 2018-07-23 2018-07-30 2018-08-09 2018-08-29 2018-12-27 Quality Control confección de una Estrategia Selection Nacional de Aire Limpio. Page 4 PE-OEFA-49987-CS-INDV / 1.2.3.1 Revisión de estudio Individual Improve Environmental definitivo para las estaciones IBRD / 86800 Post Consultant Limited 40,358.00 0.00 Canceled 2019-01-28 2019-02-07 2019-02-17 2019-02-28 2019-06-28 Quality Control de monitoreo de la calidad del Selection aire PE-OEFA-23507-CS-INDV / 1.2.9 Términos de referencia Individual para el servicio de supervisión Improve Environmental IBRD / 86800 Post Consultant Limited 15,000.00 0.00 Canceled 2018-11-26 2018-12-06 2018-12-16 2018-12-26 2019-05-25 de la adquisición de equipos e Quality Control Selection implementación de las estaciones de monitoreo PE-OEFA-18189-CS-INDV / 1.3.7 Elaboración de TdR para Individual la supervisión de la Improve Environmental IBRD / 86800 Post Consultant Limited 12,000.00 0.00 Canceled 2018-12-17 2018-12-27 2019-01-06 2019-01-21 2019-04-29 implementación de la Quality Control Selection infraestructura y equipos de laboratorio PE-OEFA-49992-CS-INDV / Information Information 2.5.0.2.1 Elaboración de Disclosure and Public Individual estudios definitivos de la IBRD / 86800 Participation for Post Consultant Limited 20,000.00 19,582.09 Signed 2018-05-28 2018-04-25 2018-06-07 2018-05-13 2018-06-17 2018-06-05 2018-06-30 2018-06-19 2018-08-29 infraestructura tecnológica del Environmental Quality Selection Componente 2 Control PE-OEFA-118481-CS-CDS / 2.5.0.2.1 Servicio de Consultoría para la Information Information Actualización del estudio Disclosure and Public definitivo de la Infraestructura IBRD / 86800 Participation for Prior Direct Selection Direct 5,000.00 0.00 Canceled 2019-06-07 2019-06-17 2019-08-21 2020-02-17 Tecnológica del Componente Environmental Quality 2 del Programa Control Correspondiente al Data Center del SENAMHI (PE-OEFA- 49992-CS-INDV) PE-OEFA-118486-CS-INDV / 1.1.17 Elaboración del Manual de determinación de la línea Individual Improve Environmental base de calidad de suelos, en IBRD / 86800 Post Consultant Limited 28,639.00 31,614.00 Signed 2019-06-24 2019-07-24 2019-06-29 2019-09-06 2019-07-20 2019-09-18 2019-08-24 2019-10-03 2020-02-20 Quality Control el marco de la elaboración de Selection estudios de impacto ambiental. PE-OEFA-120040-CS-CDS / 2.5.0.2.1 Servicio de Consultoría para la Information Information Actualización del estudio Disclosure and Public definitivo de la Infraestructura IBRD / 86800 Participation for Post Direct Selection Direct 5,000.00 4,885.20 Completed 2019-06-20 2019-06-25 2019-06-30 2019-06-06 2019-09-03 2019-07-05 2020-03-01 2019-07-28 Tecnológica del Componente Environmental Quality 2 del Programa Control Correspondiente al Data Center del SENAMHI (PE-OEFA- 118481-CS-CDS) PE-OEFA-123790-CS-INDV / 2.5.0.2.1 Servicios de Consultoria para la Information Information Elaboración del Expediente Disclosure and Public Individual Técnico (Diseño) para el IBRD / 86800 Participation for Post Consultant Limited 7,500.00 7,525.83 Signed 2019-07-19 2019-07-24 2019-07-24 2019-08-05 2019-08-14 2019-08-16 2019-09-18 2019-08-22 2020-03-16 Montaje e Instalación del Environmental Quality Selection Cable Alimentador Eléctrico al Control área del Data Center de MINAM PE-OEFA-123792-CS-INDV / 2.5.0.2.1 Servicio de Consultoria para la Information Information Supervisión de la Elaboración Disclosure and Public Individual del Expediente Técnico IBRD / 86800 Participation for Post Consultant Limited 5,500.00 5,500.00 Completed 2019-07-19 2019-07-24 2019-07-24 2019-08-05 2019-08-14 2019-08-16 2019-09-18 2019-08-22 2020-03-16 2019-09-21 (Diseño) para el Montaje e Environmental Quality Selection Instalación del cable Control Alimentador eléctrico al área del Data Center de MINAM PE-OEFA-128862-CS-INDV / 1.2.6.1 Servicios de Consultoría para la supervisión en aguas Individual Improve Environmental superficiales y calidad del IBRD / 86800 Post Consultant Limited 44,118.00 44,776.12 Signed 2019-08-23 2019-09-06 2019-08-28 2019-09-12 2019-09-18 2019-09-23 2019-10-23 2019-10-03 2020-04-20 Quality Control agua de las actividades de la Selection “Consultoría para el Monitoreo Integral de la cuenca del río Rímac” PE-OEFA-128863-CS-INDV / 1.2.6.1 Servicios de Consultoría para la Individual supervisión en aguas Improve Environmental IBRD / 86800 Post Consultant Limited 44,118.00 44,776.12 Signed 2019-08-23 2019-08-28 2019-08-28 2019-09-12 2019-09-18 2019-09-19 2019-10-23 2019-09-25 2020-04-20 subterráneas de las Quality Control Selection actividades de la “Consultoría para el Monitoreo Integral de la cuenca del río Rímac” PE-OEFA-128864-CS-INDV / 1.2.6.1 Servicios de Consultoría para la Individual supervisión en hidrobiología Improve Environmental IBRD / 86800 Post Consultant Limited 44,118.00 0.00 Canceled 2019-08-23 2019-08-28 2019-09-18 2019-10-23 2020-04-20 de las actividades de la Quality Control Selection “Consultoría para el Monitoreo Integral de la cuenca del río Rímac” PE-OEFA-150794-CS-INDV / 2.5.0.2.1 SERVICIO DE CONSULTORIA PARA LA ACTUALIZACIÓN DEL ESTUDIO Information Information DEFINITIVO DE LA Disclosure and Public Individual INFRAESTRUCTURA IBRD / 86800 Participation for Post Consultant Open 27,280.00 26,285.05 Completed 2019-12-20 2019-12-26 2020-02-07 2020-02-28 2020-02-28 2020-03-12 2020-04-03 2020-05-18 2020-09-30 2021-01-03 TECNOLÓGICA DEL Environmental Quality Selection COMPONENTE 2 DEL Control PROGRAMA CORRESPONDIENTE AL DATA CENTER DEL MINAM y SENAMHI Page 5 PE-OEFA-158278-CS-INDV / 1.2.5.1 Supervisión de las Individual Actividades de la Consultoría Improve Environmental Under IBRD / 86800 Post Consultant Limited 35,223.88 34,680.38 2020-02-07 2020-02-10 2020-02-12 2020-02-24 2020-03-04 2020-03-12 2020-04-08 2020-10-05 de Inventario de Emisiones, Quality Control Implementation Selection Evaluación de Red de Monitoreo de Lima PE-OEFA-163556-CS-INDV / Information Information 2.2.1 Supervisión del Servicio Disclosure and Public Individual de adecuación de ambientes IBRD / 86800 Participation for Post Consultant Limited 7,540.00 9,736.01 Signed 2020-03-09 2020-06-26 2020-03-14 2020-08-19 2020-04-04 2020-09-11 2020-05-09 2020-10-16 2020-11-05 para el Nuevo Data Center del Environmental Quality Selection MINAM Control PE-OEFA-164266-CS-INDV / 1.2.6.1. CONSULTORIA INDIVIDUAL PARA REALIZAR PERICIA A IMÁGENES Individual Improve Environmental FOTOGRÁFICAS DEL IBRD / 86800 Post Consultant Open 2,841.00 2,747.33 Completed 2020-03-13 2020-03-31 2020-05-01 2020-06-08 2020-05-22 2020-06-09 2020-06-26 2020-06-18 2020-12-23 2020-07-03 Quality Control PRODUCTO N°3 DE LA Selection CONSULTORIA:"MONITOREO INTEGRAL DE LA CUENCA DEL RIÓ RIMAC" PE-OEFA-163558-CS-CDS / Information Information 2.2.1 Supervision de la Disclosure and Public Implementacion e Instalación IBRD / 86800 Participation for Post Direct Selection Direct 7,540.00 7,796.16 Completed 2020-03-09 2020-07-14 2020-03-19 2020-07-13 2020-05-23 2020-10-26 2020-11-19 2021-03-31 del Cable Alimentador Environmental Quality eléctrico al área del Data Control Center del MINAM PE-OEFA-204155-CS-INDV / Individual 1.3.16 Consultoria para la Improve Environmental IBRD / 86800 Post Consultant Open 25,000.00 25,000.00 Signed 2020-11-11 2020-11-16 2020-12-15 2021-01-26 2020-12-20 2021-01-26 2020-12-30 2021-01-29 2021-02-28 Evaluación Intermedia del Quality Control Selection Programa PE-OEFA-211470-CS-INDV / 1.2.11 Especialista en Análisis Individual y Diseño de base de datos Improve Environmental IBRD / 86800 Post Consultant Open 10,135.00 0.00 Canceled 2020-12-29 2021-03-10 2021-02-16 2021-03-09 2021-04-13 2021-10-10 para lograr mejoras al sistema Quality Control Selection de gestión de residuos sólidos (SIGERSOL) PE-OEFA-211473-CS-INDV / 1.2.11 Especialista en diseño Individual Improve Environmental de interfaces de las mejoras al IBRD / 86800 Post Consultant Open 6,081.00 0.00 Canceled 2020-12-29 2021-03-10 2021-02-16 2021-03-09 2021-04-13 2021-10-10 Quality Control sistema de gestión de Selection residuos sólidos (SIGERSOL) PE-OEFA-211475-CS-INDV / 1.2.11 Especialista en Análisis y Programación de Individual Improve Environmental requerimientos para las IBRD / 86800 Post Consultant Open 6,757.00 0.00 Canceled 2020-12-29 2021-03-10 2021-02-16 2021-03-09 2021-04-13 2021-10-10 Quality Control Mejoras al Sistema de Gestión Selection de Residuos Sólidos (SIGERSOL) PE-OEFA-213729-CS-INDV / 2.5 Servicio de consultoría para la Actualización de la Information Information Plataforma MOODLE, Disclosure and Public Individual virtualización de los IBRD / 86800 Participation for Post Consultant Limited 17,669.00 0.00 Canceled 2021-01-15 2021-05-11 2021-01-20 2021-02-10 2021-03-17 2021-09-13 contenidos e Instalaciones del Environmental Quality Selection curso de educación ambiental Control para docentes desde el aula ambiental del MINAM PE-OEFA-213730-CS-INDV / 2.5 Servicio de Consultoría para la generación de Information Information contenidos y elaboración de Disclosure and Public Individual recursos educativos digitales IBRD / 86800 Participation for Post Consultant Limited 5,135.00 0.00 Canceled 2021-01-15 2021-04-09 2021-01-20 2021-02-10 2021-03-17 2021-09-13 dirigidos a escolares en Environmental Quality Selection materia de calidad ambiental Control que serán difundidos en el aula ambiental del MINAM PE-OEFA-235360-CS-CDS / 2.5.0.2.1 Consultoría para el Acompañamiento y Absolución de Consultas Information Information Realizadas en el Marco del Disclosure and Public Under Proceso de Licitación Pública IBRD / 86800 Participation for Post Direct Selection Direct 5,264.00 0.00 2021-05-19 2021-05-26 2021-05-29 2021-08-02 2022-01-29 Implementation Internacional (LPI) Referido a Environmental Quality la Adquisición de Bienes para Control el Mejoramiento de Infraestructura Informática del Data Center PE-OEFA-236735-CS-INDV / 2.5 Consultoría para la Generación de contenidos y Information Information elaboración de recursos Disclosure and Public Individual Under educativos digitales a IBRD / 86800 Participation for Post Consultant Limited 10,805.26 0.00 2021-05-28 2021-06-03 2021-06-02 2021-06-23 2021-07-28 2022-01-24 Implementation escolares en materia de Environmental Quality Selection calidad ambiental que serán Control difundidos en el aula ambiental PE-OEFA-236736-CS-INDV / 2.5 Consultoría para la Information Information actualización de la plataforma Disclosure and Public Individual MOODLE, virtualización de los Under IBRD / 86800 Participation for Post Consultant Limited 17,204.42 0.00 2021-05-28 2021-06-03 2021-06-02 2021-06-23 2021-07-28 2022-01-24 contenidos e instalacion del Implementation Environmental Quality Selection curso de educación ambiental Control para docentes desde el aula ambiental del MINAM Page 6 Procurement Plan I. General 2. Bank’s approval Date of the procurement Plan 3. Date of General Procurement Notice: 4. Period covered by this procurement plan: July 1, 2018 to Dec 31, 2019 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: 2. Procurement Method Prior Review Comments Threshold US$ 1. ICB (Goods & NCS) Above US$ 500,000 All 2. Shopping (Goods & NCS) N/A 3. Direct Contracting (Goods & Above US$500,000 All NCS) 4. ICB (Works) Above US$ 1 million All 5. Shopping (Works) N/A 6. Direct Contracting (Works) Above US$ 1 million All 2. Prequalification. Not applicable_ 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: Not applicable 4. Reference to (if any) Project Operational/Procurement Manual: 5. Any Other Special Procurement Arrangements: [including advance procurement and retroactive financing, if applicable] III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comments Threshold 1. Competitive Methods (Firms) Above US$ 500,000 All 2. Single Source (Firms) All July 9, 2010 Above US$ 500,000 3. Individual Above US$ 200,000 All 2. Short list comprising entirely of national consultants: Not Applicable 3. Any Other Special Selection Arrangements: [including advance procurement and retroactive financing, if applicable or delete if not applicable] July 9, 2010 PROCUREMENT Micronesia, Federated States of : Pacific Islands Regional Oceanscape Program - Federated States of Micronesia PLAN General Information Country: Micronesia, Federated States of Bank’s Approval Date of the Original Procurement Plan: 2018-09-04 2021-05-19 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P151754 GPN Date: Project Name: Pacific Islands Regional Oceanscape Program - Federated States of Micronesia Loan / Credit No: IDA / D0140 National Oceanic Resource Management Authority Executing Agency(ies): WORKS Procureme Activity Reference No. / Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH nt Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) Justification for Award Type Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual FM-NORMA-205046-CW-RFB Component 1: Sustainable Pending Single Stage - One 2021-06- / Satellite Office IDA / D0140 Management of Oceanic Post Request for Bids Open - National 0.00 Implementat 2021-01-17 2021-01-22 2021-03-05 2021-04-04 2021-05-09 Envelope 09 Refurbishment Fisheries ion GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual FM-NORMA-50002-GO-RFQ Component 1: Sustainable Request for Single Stage - One / Vehicles to support satellite IDA / D0140 Management of Oceanic Post Limited 41,290.00 Completed 2018-06-20 2020-03-25 2018-08-15 2020-06-05 2019-02-11 2020-08-17 Quotations Envelope offices in States Fisheries FM-NORMA-49996-GO-RFP Component 1: Sustainable / GENSETS to provide Request for Single Stage - One IDA / D0140 Management of Oceanic Post Open - National 19,950.00 Completed 2018-09-12 2018-11-07 2019-01-02 2019-05-06 2020-02-01 continuous power to VMS and Quotations Envelope Fisheries systems FM-NORMA-67074-GO-RFQ Component 1: Sustainable / Boats for monitoring Request for Single Stage - One IDA / D0140 Management of Oceanic Post Open - International 0.00 Canceled 2019-02-20 2019-04-17 2019-10-14 transhipment and support Quotations Envelope Fisheries satellite offices FM-NORMA-67089-GO-RFQ Component 1: Sustainable / Supply of computer Request for Single Stage - One IDA / D0140 Management of Oceanic Post Open - International 0.00 Canceled 2018-07-21 2018-09-15 2019-03-14 Hardware and Software for Quotations Envelope Fisheries IT/IMS FM-NORMA-46587-GO-RFQ Component 1: Sustainable / Supply of Observer IDA / D0140 Management of Oceanic Post Direct Selection Direct 0.00 Canceled 2020-01-26 2020-01-31 2020-03-06 2020-09-02 monitoring equipment (e.g Fisheries calibers, etc) FM-NORMA-50397-GO-RFQ Component 1: Sustainable / Supply of Marine Safety Request for Single Stage - One IDA / D0140 Management of Oceanic Post Open - International 0.00 Canceled 2020-01-17 2020-03-13 2020-09-09 Equipment (lot 2) for Quotations Envelope Fisheries observers and MCS Officers FM-NORMA-67047-GO-RFQ Component 1: Sustainable Request for Single Stage - One / Fisheries promotional IDA / D0140 Management of Oceanic Post Limited 3,168.00 Terminated 2020-02-14 2020-07-29 2020-04-10 2021-04-30 2020-05-10 Quotations Envelope materials Fisheries FM-NORMA-50386-NC-RFP Component 1: Sustainable Request for Single Stage - One / Unmanned aerial vehicle IDA / D0140 Management of Oceanic Post Open - International 16,263.34 Signed 2020-02-07 2020-03-02 2020-04-03 2020-06-23 2020-07-02 Quotations Envelope (UAV) Fisheries FM-NORMA-67147-GO-RFQ Component 1: Sustainable / Supply of lab and Request for Single Stage - One IDA / D0140 Management of Oceanic Post Open - International 18,123.86 Signed 2020-02-07 2020-02-11 2020-04-03 2020-07-14 2020-07-02 specialized Equipment for Quotations Envelope Fisheries Competent Authority FM-NORMA-105807-GO- Component 1: Sustainable RFQ / CA Offices and NORMA Request for Single Stage - One IDA / D0140 Management of Oceanic Post Open - National 28,511.45 Signed 2020-01-25 2020-02-11 2020-03-21 2020-06-29 2020-06-19 Office equipment and Quotations Envelope Fisheries furniture FM-NORMA-67071-GO-RFQ Component 1: Sustainable / Supply of marine ICT and Request for Single Stage - One IDA / D0140 Management of Oceanic Post Open - National 23,403.84 Signed 2020-01-22 2020-02-11 2020-03-18 2020-06-26 2020-09-14 safety equipment for MCS and Quotations Envelope Fisheries observers FM-NORMA-67158-GO-RFQ / Supply of Component 1: Sustainable Request for Single Stage - One Hardware/Software for IDA / D0140 Management of Oceanic Post Open - International 52,639.31 Signed 2020-02-07 2020-02-11 2020-04-03 2020-07-14 2020-07-02 2020-12-09 Quotations Envelope NORMA IMS and Competent Fisheries Authority offices FM-NORMA-183357-GO- Component 1: Sustainable Under RFQ / Lot 2 Marine Safety and Request for Single Stage - One IDA / D0140 Management of Oceanic Post Open - International 0.00 Implementati 2020-07-24 2020-10-30 2020-09-18 2021-03-17 ICT equipment and supplies Quotations Envelope Fisheries on for MCS and observers FM-NORMA-183359-GO- Component 1: Sustainable Under RFQ / Lot 2 Supply of IT Request for Single Stage - One IDA / D0140 Management of Oceanic Post Open - International 0.00 Implementati 2020-07-31 2020-10-30 2020-09-25 2020-12-24 hardware and Software to Quotations Envelope Fisheries on support IMS FM-NORMA-192171-GO- Component 1: Sustainable RFQ / Supply of Observer Request for Single Stage - One IDA / D0140 Management of Oceanic Post Limited 11,821.00 Signed 2020-09-12 2020-08-27 2020-11-07 2021-04-09 2021-05-06 Monitoring Equipment (e.g./ Quotations Envelope Fisheries calipers, etc.). FM-NORMA-67074-GO-RFQ- Component 1: Sustainable Under Request for Single Stage - One 2 / Rigid Hull Inflatable Boats IDA / D0140 Management of Oceanic Post Open - International 105,131.00 Implementati 2020-11-30 2021-01-11 2021-01-25 2021-05-25 Quotations Envelope for Transshipment monitoring Fisheries on FM-NORMA-205032-GO- Component 1: Sustainable Under Request for Single Stage - One RFQ / GENSET to replace small IDA / D0140 Management of Oceanic Post Open - National 0.00 Implementati 2020-11-30 2021-01-11 2021-01-25 2021-05-25 Quotations Envelope backup generator Fisheries on Page 1 FM-NORMA-205040-GO- Component 1: Sustainable Pending RFQ / Micro-Canning Request for Single Stage - One IDA / D0140 Management of Oceanic Post Open - International 0.00 Implementati 2020-12-05 2021-01-30 2021-05-30 Equipment for Pilot Quotations Envelope Fisheries on demonstration NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 1: Sustainable FM-NORMA-67161-NC-DIR / IDA / D0140 Management of Oceanic Post Direct Selection Direct 13,000.00 Completed 2018-07-01 2018-07-28 2018-07-06 2018-06-29 2018-08-03 2018-07-23 2018-12-31 2020-01-31 Video Producer Fisheries FM-NORMA-165684-NC- Component 1: Sustainable Under Request for Single Stage - One RFQ / CA Fish Samples IDA / D0140 Management of Oceanic Post Open - International 24,888.41 Implementati 2020-03-30 2020-04-23 2020-05-15 2020-09-20 Quotations Envelope Testing Fisheries on FM-NORMA-140619-NC-DIR Component 1: Sustainable Request for Single Stage - One / World Tuna Day Organizer IDA / D0140 Management of Oceanic Prior Open - National 0.00 Canceled 2020-04-01 2020-04-27 2020-07-31 Quotations Envelope (YAP) Fisheries FM-NORMA-205035-NC- Component 1: Sustainable Pending Request for Single Stage - One RFQ / World Tuna Day IDA / D0140 Management of Oceanic Post Open - National 0.00 Implementati 2021-01-11 2021-02-06 2021-07-06 Quotations Envelope Organizer (Yap) Fisheries on FM-NORMA-205037-NC- Component 1: Sustainable Request for Single Stage - One RFQ / World Tuna Day IDA / D0140 Management of Oceanic Post Open - National 0.00 Canceled 2021-01-11 2021-02-06 2021-07-06 Quotations Envelope Organizer (Chuuk) Fisheries FM-NORMA-205038-NC- Component 1: Sustainable Pending Request for Single Stage - One RFQ / World Tuna Day IDA / D0140 Management of Oceanic Post Open - National 0.00 Implementati 2021-01-11 2021-02-06 2021-07-06 Quotations Envelope (Kosrae) Fisheries on FM-NORMA-205039-NC- Component 1: Sustainable Pending Request for Single Stage - One RFQ / World Tuna Day IDA / D0140 Management of Oceanic Post Open - National 0.00 Implementati 2021-01-13 2021-02-08 2021-07-08 Quotations Envelope Organizer (Pohnpei) Fisheries on Component 1: Sustainable Pending FM-NORMA-205047-NC- Request for Single Stage - One IDA / D0140 Management of Oceanic Post Open - National 0.00 Implementati 2021-01-22 2021-03-19 2021-09-15 RFQ / Satellite office lease Quotations Envelope Fisheries on FM-NORMA-231607-NC-DIR Component 1: Sustainable / World Tuna Day Organizer IDA / D0140 Management of Oceanic Post Direct Selection Direct 20,053.00 Signed 2021-04-29 2021-05-01 2021-04-30 2021-05-12 2021-05-11 2021-06-07 2021-07-01 (Chuuk) Fisheries CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Contract Type Process Status Teams of Reference Identified/Selected Signed Contract Contract Completion No. (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual FM-NORMA-46585-CS-INDV Component 1: Sustainable Individual / Information Management IDA / D0140 Management of Oceanic Post Consultant Open 0.00 Canceled 2018-04-02 2018-05-21 2018-06-11 2018-07-16 2020-07-05 System Manager Fisheries Selection FM-NORMA-67081-CS-INDV Component 1: Sustainable Individual / Local E-Reporting/E- IDA / D0140 Management of Oceanic Post Consultant Open 26,180.70 Signed 2019-01-07 2018-06-22 2019-02-25 2019-01-21 2019-03-18 2019-02-03 2019-04-22 2019-02-03 2020-04-17 Monitoring Coordinator Fisheries Selection Component 1: Sustainable Individual FM-NORMA-67068-CS-INDV IDA / D0140 Management of Oceanic Post Consultant Open 14,297.40 Completed 2018-08-15 2018-09-17 2018-10-03 2019-01-07 2018-10-24 2019-02-04 2018-11-28 2019-02-03 2019-11-23 2020-02-03 / License Assistant Fisheries Selection Component 1: Sustainable Individual FM-NORMA-50012-CS-INDV IDA / D0140 Management of Oceanic Post Consultant Open 28,657.20 Signed 2018-05-15 2018-04-19 2018-07-03 2018-08-27 2018-07-24 2018-09-14 2018-08-28 2019-09-14 2020-08-27 / E-Reporting Officer Fisheries Selection FM-NORMA-67045-CS-INDV Component 3: National Individual / PROP PROJECT IDA / D0140 Program Management, Post Consultant Open 265,800.20 Signed 2018-07-01 2015-08-30 2018-08-19 2017-07-18 2018-09-09 2017-08-31 2018-10-14 2015-08-13 2020-04-10 COORDINATOR Monitoring and Evaluation Selection Component 3: National Individual FM-NORMA-50337-CS-INDV IDA / D0140 Program Management, Post Consultant Open 27,999.45 Completed 2018-12-15 2015-11-02 2019-01-10 2017-01-30 2019-01-31 2017-02-19 2019-02-20 2017-02-19 2020-09-30 2020-02-01 / PROP Program Assistant Monitoring and Evaluation Selection Component 3: National Individual FM-NORMA-67085-CS-INDV IDA / D0140 Program Management, Post Consultant Open 29,674.95 Completed 2018-04-16 2018-07-19 2018-05-20 2018-05-25 2018-08-03 2018-06-29 2018-01-31 2019-06-24 2020-08-05 / PROP Accounts Officer Monitoring and Evaluation Selection FM-NORMA-67165-CS-INDV / Information Component 1: Sustainable Individual Technology/Information IDA / D0140 Management of Oceanic Post Consultant Open 150,000.00 Signed 2018-06-19 2018-02-06 2018-08-07 2018-10-26 2018-08-28 2020-01-29 2018-10-02 2020-03-20 2019-10-02 Management System (IT/IMS) Fisheries Selection Developer Component 1: Sustainable FM-NORMA-67067-CS-CDS IDA / D0140 Management of Oceanic Post Direct Selection Direct 3,500.00 Terminated 2018-07-01 2018-07-28 2018-07-11 2018-07-30 2018-09-04 2018-09-21 2018-11-30 / Observer Program Profiling Fisheries Component 1: Sustainable FM-NORMA-67075-CS-CDS IDA / D0140 Management of Oceanic Post Direct Selection Direct 5,000.00 Completed 2018-06-15 2018-04-16 2018-06-25 2018-04-30 2018-08-29 2018-05-21 2019-08-24 2020-01-01 / Fisheries Ambassador Fisheries Page 2 Component 1: Sustainable Individual FM-NORMA-67083-CS-INDV IDA / D0140 Management of Oceanic Post Consultant Open 0.00 Canceled 2018-08-01 2018-09-19 2018-10-10 2018-10-29 2019-10-25 / VDS/Fisheries Economist Fisheries Selection FM-NORMA-81703-CS-CDS Component 1: Sustainable / SENIOR FISHERIES IDA / D0140 Management of Oceanic Post Direct Selection Direct 54,839.46 Completed 2018-10-12 2018-10-03 2018-10-17 2018-10-29 2018-11-26 2020-04-29 2020-04-25 ECONOMIST for FSM NORMA Fisheries FM-NORMA-81707-CS-INDV Component 1: Sustainable Individual / VESSEL DAY SCHEME (VDS) IDA / D0140 Management of Oceanic Post Consultant Open 17,778.00 Signed 2018-10-15 2018-10-29 2018-12-19 2019-06-25 2019-01-09 2019-07-08 2019-02-13 2019-06-27 2020-08-14 ADMINISTRATOR Fisheries Selection FM-NORMA-49412-CS-INDV Component 1: Sustainable Individual / Communications Adviser for IDA / D0140 Management of Oceanic Post Consultant Open 0.00 Canceled 2018-08-15 2018-10-03 2018-10-24 2018-11-28 2019-05-27 communications strategy for Fisheries Selection public, industry and internally. Component 1: Sustainable Individual FM-NORMA-140616-CS- IDA / D0140 Management of Oceanic Post Consultant Open 21,886.80 Completed 2019-10-16 2017-08-21 2019-11-15 2019-02-28 2019-11-15 2019-03-21 2019-11-15 2019-04-05 2020-08-23 2020-12-31 INDV / CA Inspector (Kosrae) Fisheries Selection FM-NORMA-140617-CS- Component 1: Sustainable Individual INDV / CA INSPECTOR IDA / D0140 Management of Oceanic Post Consultant Open 21,886.80 Completed 2019-10-16 2017-08-21 2019-10-16 2019-02-10 2019-10-16 2019-04-04 2019-10-16 2019-04-04 2020-08-23 2020-04-27 (Pohnpei 1) Fisheries Selection FM-NORMA-140618-CS- Component 1: Sustainable Individual INDV / CA INSPECTOR IDA / D0140 Management of Oceanic Post Consultant Open 36,246.60 Completed 2019-10-16 2017-08-21 2019-10-16 2018-10-09 2019-10-16 2019-04-04 2019-10-16 2019-04-04 2020-08-23 2020-12-31 (Pohnpei 2) Fisheries Selection FM-NORMA-89603-CS-INDV Component 1: Sustainable Individual / Corporate Services Local IDA / D0140 Management of Oceanic Post Consultant Limited 0.00 Canceled 2019-12-16 2020-11-13 2019-12-31 2020-01-15 2020-02-09 2020-08-07 Consultant Fisheries Selection FM-NORMA-67087-CS-INDV Component 3: National Individual / PROP Procurement/Project IDA / D0140 Program Management, Post Consultant Open 37,381.89 Signed 2018-07-02 2019-07-01 2018-08-20 2019-07-04 2018-09-10 2019-07-09 2018-10-15 2019-07-12 2019-10-11 Officer Monitoring and Evaluation Selection FM-NORMA-105808-CS-CDS Component 1: Sustainable Individual / Fisheries Reporting IDA / D0140 Management of Oceanic Post Consultant Direct 0.00 Canceled 2020-02-16 2020-02-26 2020-03-04 2020-04-01 2020-05-01 Consultant Fisheries Selection FM-NORMA-105826-CS- Component 1: Sustainable Individual INDV / Competent Authority IDA / D0140 Management of Oceanic Prior Consultant Open 83,411.10 Signed 2019-03-13 2019-05-01 2019-05-22 2020-04-03 2019-06-26 2019-03-28 2020-08-26 Technical Officer Fisheries Selection FM-NORMA-105827-CS- Component 1: Sustainable Individual INDV / Competent Authority IDA / D0140 Management of Oceanic Prior Consultant Open 22,000.00 Under Review 2019-03-15 2019-05-03 2019-02-11 2019-05-24 2020-04-03 2019-06-28 2019-04-04 2020-08-23 Inspectors (Yap) Fisheries Selection FM-NORMA-105809-CS-CDS Component 1: Sustainable Individual / Communications IDA / D0140 Management of Oceanic Post Consultant Open 12,000.00 Completed 2020-02-15 2020-01-10 2020-03-06 2020-04-15 2020-03-13 2020-04-15 2020-03-23 2020-05-04 2020-09-19 2021-01-20 Plan/Strategy Consultant Fisheries Selection FM-NORMA-49410-CS-INDV Component 1: Sustainable Individual / Well being review of IDA / D0140 Management of Oceanic Post Consultant Direct 3,000.00 Completed 2020-01-15 2020-02-01 2020-02-04 2020-02-10 2020-02-08 2020-02-15 2020-02-17 2020-11-10 2020-03-18 2020-11-23 members of Observer Fisheries Selection Program Component 3: National Individual FM-NORMA-159070-CS- IDA / D0140 Program Management, Post Consultant Open 10,000.00 Signed 2020-02-15 2020-02-20 2020-03-12 2020-04-10 2020-04-02 2020-04-03 2020-04-22 2020-05-05 2020-09-30 INDV / Project Assistant Monitoring and Evaluation Selection FM-NORMA-180873-CS- Component 1: Sustainable Individual Under INDV / CA INSPECTOR IDA / D0140 Management of Oceanic Post Consultant Open 0.00 2020-06-24 2020-07-27 2020-07-17 2020-07-24 2020-07-28 2021-07-25 Implementation (Pohnpei 1) Fisheries Selection FM-NORMA-180874-CS- Component 3: National Individual INDV / Project Operations IDA / D0140 Program Management, Post Consultant Limited 5,000.00 Completed 2020-07-03 2020-09-29 2020-07-06 2020-10-07 2020-07-10 2020-11-27 2020-07-31 2021-01-06 2020-08-30 2021-02-26 Manual Development Monitoring and Evaluation Selection FM-NORMA-67082-CS-INDV Component 1: Sustainable Individual / Catch Documentation IDA / D0140 Management of Oceanic Post Consultant Open 0.00 Canceled 2018-05-15 2018-09-24 2018-07-03 2018-07-24 2018-08-28 2019-08-26 Scheme Officer Fisheries Selection FM-NORMA-182535-CS- Component 3: National Individual INDV / DLI Report Verification IDA / D0140 Program Management, Post Consultant Direct 0.00 Canceled 2020-10-01 2020-10-11 2020-11-01 2020-12-06 2021-06-04 Consultancy Monitoring and Evaluation Selection FM-NORMA-205031-CS- Component 1: Sustainable Individual Under INDV / Corporate Services IDA / D0140 Management of Oceanic Post Consultant Open 20,000.00 2020-11-20 2020-12-01 2021-01-08 2021-04-12 2021-01-29 2021-04-12 2021-03-05 2021-09-01 Implementation Consultant Fisheries Selection FM-NORMA-205033-CS- Component 1: Sustainable Individual Under INDV / Local Fisheries IDA / D0140 Management of Oceanic Post Consultant Open 0.00 2020-11-17 2020-12-01 2020-12-08 2020-12-15 2020-12-22 2021-09-30 Implementation Economist Fisheries Selection FM-NORMA-205041-CS- Component 1: Sustainable Individual INDV / Fisheries Compliance IDA / D0140 Management of Oceanic Post Consultant Open 65,000.00 Signed 2020-11-22 2020-12-02 2020-12-25 2021-04-12 2020-12-30 2021-04-12 2021-01-15 2021-05-12 2021-09-15 Consultant Fisheries Selection FM-NORMA-205043-CS- Component 1: Sustainable Individual Under INDV / Accounting System IDA / D0140 Management of Oceanic Post Consultant Open 15,000.00 2020-11-25 2020-12-01 2020-12-28 2021-04-12 2021-01-11 2021-04-12 2021-02-03 2021-08-02 Implementation Consultant Fisheries Selection FM-NORMA-205044-CS- Component 3: National Individual INDV / Implementation IDA / D0140 Program Management, Post Consultant Open 23,000.00 Signed 2020-11-29 2021-03-17 2021-01-17 2021-05-14 2021-02-07 2021-05-17 2021-03-14 2021-06-04 2021-06-12 Completion Report Consultant Monitoring and Evaluation Selection FM-NORMA-205045-CS- Component 1: Sustainable Individual Pending INDV / Observer Classification IDA / D0140 Management of Oceanic Post Consultant Open 0.00 2021-01-29 2021-03-03 2021-03-24 2021-04-28 2021-06-27 Implementation Study Fisheries Selection FM-NORMA-215242-CS- Component 3: National Individual INDV / DLI Verification Report IDA / D0140 Program Management, Post Consultant Open 8,000.00 Signed 2021-01-24 2021-02-04 2021-03-07 2021-05-14 2021-03-14 2021-05-18 2021-03-24 2021-06-04 2021-05-23 Consultancy Monitoring and Evaluation Selection Page 3 FM-NORMA-235444-CS- INDV / Information Technology/Information Management System (IT/IMS) Developer to deliver 4 fisheries systems (Observer Component 1: Sustainable Individual placement, Observer IDA / D0140 Management of Oceanic Post Consultant Direct 158,604.12 Signed 2021-05-20 2021-05-20 2021-05-21 2021-05-14 2021-05-21 2021-05-14 2021-06-11 2021-06-03 2021-08-31 Recruitment, Ports Fisheries Selection Management, Vessel Inspection) with corresponding data infrastructure along with IMS Policy and SOP. Page 4 PROCUREMENT PLAN (Textual Part) Project information: Afghanistan Naghlu Hydropower Rehabilitation Project (P132944) Project Implementation agency: DABS Date of the Procurement Plan: May 2017 Period covered by this Procurement Plan: December 2018 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in [insert appropriate references to the national procurement legislation], such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. List only the applicable conditions required to ensure consistency with paragraph 5.4 of the Procurement Regulations. If no conditions apply, delete the phrase “and the following conditions”. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Otherwise state “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables Otherwise state “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Specify for each Goods: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables]; Works: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables] Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. [Include this sentence only if the Bank has formally agreed to provide the Borrower with HEIS. Otherwise delete] Other Relevant Procurement Information. Provide any other relevant procurement information such as procedures for CDD components, Procurement in Situations of Urgent Need of Assistance or Capacity Constraints etc. PROCUREMENT Afghanistan : Naghlu Hydropower Rehabilitation Project PLAN General Information Country: Afghanistan Bank’s Approval Date of the Original Procurement Plan: 2017-05-15 2021-05-28 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P132944 GPN Date: Project Name: Naghlu Hydropower Rehabilitation Project Loan / Credit No: TF / A1691, TF / 14861 Da Afghanistan Breshna Sherkat Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned AF-DABS-14178-CW-RFB / Procurement of WOrks for Component 1: Mechanical, Single Stage - One 2018-09- Security Upgrading and site TF / A1691 Electrical, and Post Request for Bids Open - National 900,000.00 0.00 Canceled 2017-06-03 2017-12-08 2017-06-08 2017-07-20 2017-08-19 2017-09-23 Envelope 22 utility improvement for Electromechanical Works Naghlu Dam Component 3: Environmental AF-DABS-31611-CW-RFQ / and Social Sustainability, Request for Single Stage - One 2018-06- Repair Work of Building TF / A1691 Post Limited 40,000.00 16,889.77 Completed 2017-10-19 2017-10-17 2017-12-14 2017-11-11 Project Management Support, Quotations Envelope 12 Dedicated for WB-PIU and Future Project Preparation AF-DABS-5686-CW-RFB / Component 1: Mechanical, Pending Single Stage - One 2018-10- construction of whorehouse at TF / A1691 Electrical, and Post Request for Bids Open - National 549,580.00 0.00 Implementat 2018-01-12 2018-01-17 2018-02-28 2018-03-30 2018-05-04 Envelope 31 Naghlu Hydro power station Electromechanical Works ion AF-DABS-14835-CW-RFB / Rehabilitation Unit#1 and Component 1: Mechanical, Under Single Stage - One 10,000,000.0 2018-10- overall of unit #3 with supply TF / A1691 Electrical, and Prior Request for Bids Open - International 0.00 Implementat 2018-01-12 2018-01-17 2018-02-28 2015-06-07 2018-03-30 2018-05-04 Envelope 0 31 and installation of spare parts Electromechanical Works ion at NHPS AF-DABS-43776-CW-RFB / Procurement of Works for Component 2: Dam Safety Single Stage - One 2019-03- Security Upgrading and site TF / A1691 and Power Generation Post Request for Bids Open - National 900,000.00 491,795.19 Signed 2017-12-10 2017-12-07 2017-12-15 2018-01-19 2018-01-15 2018-02-18 2018-02-24 2018-03-25 2018-04-16 Envelope 25 utility improvement for Capacity Improvement Naghlu Dam AF-DABS-59566-CW-RFQ / Component 3: Environmental Renovation Work of relay and and Social Sustainability, Request for Single Stage - One 2018-04- TF / A1691 Post Open - National 30,000.00 25,141.02 Completed 2018-01-25 2018-03-22 2018-05-12 Protection building Dedicated Project Management Support, Quotations Envelope 21 for World Bank-PIU and Future Project Preparation AF-DABS-79326-CW-RFB / Procurement of goods, Works and Services for Design, manufacture, supply, Component 3: Environmental installation, Testing and Social Sustainability, &commissioning for Single Stage - One 10,555,326. 2021-02- TF / A1691 Project Management Support, Prior Request for Bids Open - International 8,500,000.00 Signed 2018-10-15 2019-05-23 2018-10-20 2019-06-02 2018-12-01 2019-08-28 2018-12-31 2020-03-18 2019-02-04 2020-09-26 renovation, up gradation with Envelope 62 03 and Future Project complete replacement of Unit Preparation No. 1,2&3, switch-yard and construction of Admin building, and Ware house for DH AF-DABS-4510-CW-RFB / PROCUREMENT OF Component 1: Mechanical, Pending Design, Supply, Construction, Single Stage - One 2019-08- TF / A1691 Electrical, and Post Request for Bids Open - International 3,200,000.00 0.00 Implementat 2018-01-12 2018-01-17 2018-02-28 2018-03-30 2018-05-04 Erection, Testing and Envelope 02 Electromechanical Works ion Commissioning of 110/20kV Sarobi Substation AF-DABS-178060-CW-RFB / Component 3: Environmental procurement of design, and Social Sustainability, Under Single Stage - One 2021-10- supply, installation, testing TF / A1691 Project Management Support, Post Request for Bids Open - National 3,600,000.00 0.00 Implementat 2020-06-20 2021-02-23 2020-06-25 2021-04-20 2020-08-06 2021-05-19 2020-09-05 2020-10-10 Envelope 10 and commissioning of Tagab and Future Project ion Electrification (Phase I) Preparation AF-DABS-220317-CW-RFB / Procurement of Design, Component 1: Mechanical, Under Supply and installation of Single Stage - One 2022-09- TF / A1691 Electrical, and Post Request for Bids Open - International 1,000,000.00 0.00 Implementat 2021-02-20 2021-04-07 2021-02-25 2021-05-10 2021-04-08 2021-06-07 2021-05-08 2021-06-12 Goods for Electrification of Envelope 05 Electromechanical Works ion Sorobi district remaining villages of Naghlu HPP GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual AF-DABS-19909-GO-RFQ / Component 3: Environmental Procurement of Small and and Social Sustainability, Request for Single Stage - One Heavy Duty Printers for TF / A1691 Project Management Support, Post Limited 47,500.00 29,638.72 Completed 2017-07-20 2017-07-12 2017-09-07 2017-07-25 2017-10-07 2017-08-21 Quotations Envelope Procurement directorate of and Future Project DABS Preparation AF-DABS-19919-GO-RFQ / Procurement/supply and Component 3: Environmental installation of Carpet for and Social Sustainability, Request for Single Stage - One flooring and cabin partitions TF / A1691 Project Management Support, Post Limited 41,000.00 17,850.17 Completed 2017-07-20 2017-07-26 2017-09-07 2017-08-15 2017-10-07 2017-08-19 Quotations Envelope for new location of and Future Project procurement directorate of Preparation DABS AF-DABS-19920-GO-RFQ / Procurement , Supply and installation of Networking Component 3: Environmental facilities (switches, modems, and Social Sustainability, Request for Single Stage - One wireless hubs..etc) ,Security TF / A1691 Project Management Support, Post Limited 25,000.00 30,209.04 Completed 2017-07-20 2017-07-12 2017-09-07 2017-07-19 2017-10-07 2017-07-22 Quotations Envelope cameras, CCTV and lockable and Future Project room facilities for Preparation procurement directorate of DABS Page 1 AF-DABS-14854-GO-RFQ / Component 3: Environmental Procurement of Office and Social Sustainability, Request for Single Stage - One TF / A1691 Post Open - National 50,000.00 21,492.51 Completed 2017-08-06 2017-10-01 2018-09-29 2017-12-01 2018-10-06 Furniture ( Disks,Chairs , Project Management Support, Quotations Envelope carpets ...etc) and Future Project Preparation AF-DABS-14852-GO-RFQ / Component 3: Environmental Procurement of Office and Social Sustainability, Request for Single Stage - One Equipment ( Printers TF / A1691 Project Management Support, Post Open - National 50,000.00 19,738.24 Completed 2017-05-16 2017-07-11 2016-11-16 2017-07-31 2016-11-20 Quotations Envelope ,Computers ,Laptops,..etc) for and Future Project PIU Preparation AF-DABS-19916-GO-RFQ / Procurement of office Component 3: Environmental Furniture ( Office table/disk , and Social Sustainability, Request for Single Stage - One meeting table , storing TF / A1691 Project Management Support, Post Limited 31,000.00 35,119.23 Completed 2017-07-20 2017-07-29 2017-09-07 2017-08-09 2017-09-30 2017-08-19 Quotations Envelope cabinets...etc) for and Future Project procurement directorate of Preparation DABS AF-DABS-19893-GO-RFQ / Component 3: Environmental Procurement of Laptop and and Social Sustainability, Request for Single Stage - One desktop Computers for TF / A1691 Project Management Support, Post Limited 27,000.00 34,814.34 Completed 2017-07-20 2017-09-17 2017-09-02 2017-10-10 2017-09-30 2017-11-12 Quotations Envelope Procurement directorate of and Future Project DABS Preparation AF-DABS-41885-GO-DIR / Component 1: Mechanical, Purchase of 7 items required TF / A1691 Electrical, and Post Direct Selection Direct 35,000.00 0.00 Canceled 2017-12-31 2018-01-05 2018-02-09 2018-03-11 for Unit#2 of Naghlu dam on Electromechanical Works emergency basis. AF-DABS-14174-GO-RFQ / Component 1: Mechanical, Procurement of 2 Nos of Request for Single Stage - One TF / A1691 Electrical, and Post Open - National 15,000.00 13,155.70 Completed 2018-01-15 2018-03-12 2018-02-06 2018-03-23 2018-03-12 Water Pumps for Emptying Quotations Envelope Electromechanical Works the drainage galary in Naghlu AF-DABS-14177-GO-RFB / Procurement and Supply of Component 1: Mechanical, Pending Construction Materials and Single Stage - One TF / A1691 Electrical, and Post Request for Bids Open - National 195,000.00 0.00 Implementati 2018-01-12 2018-01-17 2018-02-28 2018-03-30 2018-05-04 2018-10-31 Associated Services for Envelope Electromechanical Works on Installation of poles for sorobi Electrification AF-DABS-96068-GO-RFB / Procurement of Additional 2 Component 2: Dam Safety Single Stage - One nos Heavy duty Pumps for TF / A1691 and Power Generation Post Request for Bids Open - National 140,000.00 0.00 Canceled 2019-02-09 2019-02-14 2019-03-28 2019-04-27 2019-06-01 2019-09-29 Envelope drainage Gallery of Naghlu Capacity Improvement Hydro power Plant AF-DABS-109974-GO-RFQ / Component 2: Dam Safety Procurement of Echo sounder, Request for Single Stage - One TF / A1691 and Power Generation Post Open - National 35,000.00 29,530.27 Completed 2019-04-25 2019-06-20 2019-10-09 2019-07-20 2019-11-19 bathymetric surveys for Quotations Envelope Capacity Improvement Naghlu Dam AF-DABS-118555-GO-RFB / Procurement of Goods and Component 1: Mechanical, Under Services for supply, Single Stage - One TF / A1691 Electrical, and Prior Request for Bids Open - International 2,750,000.00 3,138,030.00 Implementati 2019-07-15 2020-02-18 2019-07-20 2020-06-14 2019-09-03 2020-07-15 2019-10-03 2021-03-10 2019-11-07 2020-05-05 installation, Testing, Envelope Electromechanical Works on Commissioning of overhauling Unit No#2 of Naghlu HPP AF-DABS-14220-GO-RFB / Component 1: Mechanical, Under Single Stage - One Procurement of Spare parts TF / A1691 Electrical, and Prior Request for Bids Open - International 6,000,000.00 0.00 Implementati 2019-09-07 2021-02-18 2019-09-14 2021-04-26 2019-10-26 2021-05-18 2019-11-25 2019-12-30 2020-12-29 Envelope for Naghlu Power Plant Electromechanical Works on AF-DABS-103190-GO-DIR / Procurement of Additional 2 Component 2: Dam Safety nos Heavy duty Pumps for TF / A1691 and Power Generation Post Direct Selection Direct 320,000.00 316,290.00 Completed 2019-03-10 2019-03-09 2019-03-15 2019-08-25 2019-04-19 2020-01-25 2019-10-16 2020-08-12 drainage Gallery of Naghlu Capacity Improvement Hydro power Plant AF-DABS-167154-GO-RFQ / Component 3: Environmental Pending Procurement of IT Equipment and Social Sustainability, Request for Single Stage - One TF / A1691 Post Limited 14,146.00 0.00 Implementati 2020-04-30 2020-06-25 2020-07-25 for Kajaki Phase II project Project Management Support, Quotations Envelope on Staff and Future Project Preparation Component 3: Environmental AF-DABS-167160-GO-RFQ / Pending and Social Sustainability, Request for Single Stage - One Procurement of Furniture for TF / A1691 Post Limited 5,200.00 0.00 Implementati 2020-04-30 2020-06-25 2020-07-25 Project Management Support, Quotations Envelope Kajaki Phase II project Staff on and Future Project Preparation AF-DABS-185830-GO-RFQ / Component 1: Mechanical, Procurement of one unit 8 Request for Single Stage - One TF / A1691 Electrical, and Post Open - National 6,000.00 6,334.58 Completed 2020-08-01 2020-09-26 2020-05-11 2020-10-03 2020-06-11 inch water pump for Naghlu Quotations Envelope Electromechanical Works HPP AF-DABS-192060-GO-RFQ / Component 2: Dam Safety Procurement of One unit Boat Request for Single Stage - One TF / A1691 and Power Generation Post Open - National 30,000.00 34,424.53 Signed 2020-10-01 2020-11-26 2020-11-23 2021-01-10 for survey of Naghlu Dam Quotations Envelope Capacity Improvement reservoir AF-DABS-14173-GO-RFB / Procurement of Design, Supply and installation of Component 1: Mechanical, Pending Single Stage - One Goods for Electrification of TF / A1691 Electrical, and Post Request for Bids Open - International 1,000,000.00 0.00 Implementati 2020-10-31 2020-11-05 2020-12-17 2021-01-16 2021-02-20 2022-05-16 Envelope Sorobi district remaining Electromechanical Works on villages upstream of Naghlu HPP Component 3: Environmental AF-DABS-197781-GO-RFQ / and Social Sustainability, Request for Single Stage - One Procurement of Deep well for TF / A1691 Post Open - National 35,000.00 29,957.49 Signed 2020-11-05 2020-12-31 2020-09-05 2021-01-30 Project Management Support, Quotations Envelope DABS Training Center and Future Project Preparation AF-DABS-197778-GO-DIR / Component 3: Environmental Procurement of Training Aid and Social Sustainability, Pending Equipment for Training Center TF / A1691 Project Management Support, Post Direct Selection Direct 516,320.00 0.00 Implementati 2020-10-31 2020-11-05 2020-12-10 2021-06-08 amended to DABS Staff and Future Project on Capacity Building project Preparation Page 2 Component 3: Environmental AF-DABS-197782-GO-RFB / Pending and Social Sustainability, Single Stage - One Procurement of Furniture for TF / A1691 Post Request for Bids Open - National 153,000.00 0.00 Implementati 2020-10-31 2020-11-05 2020-12-17 2021-01-16 2021-02-20 2021-06-20 Project Management Support, Envelope DABS Training Center on and Future Project Preparation AF-DABS-235140-GO-RFQ / Component 2: Dam Safety Pending Procurement of ArcGIS Request for Single Stage - One TF / A1691 and Power Generation Post Open - National 30,000.00 0.00 Implementati 2021-06-03 2021-07-29 2021-08-28 software for DABS Energy Quotations Envelope Capacity Improvement on Information Center NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual AF-DABS-129893-NC-DIR / Component 3: Environmental Procurement of sediment, soil and Social Sustainability, TF / A1691 Post Direct Selection 20,000.00 10,590.00 Signed 2019-09-21 2019-09-12 2019-10-01 2019-09-30 2019-11-05 2019-10-19 2019-11-30 water and POPs tests of Project Management Support, Naghlu Dam and Future Project Preparation AF-DABS-133337-NC-RFB / Procurement of Sediment Component 2: Dam Safety Pending Single Stage - One Analysis and Selective TF / A1691 and Power Generation Prior Request for Bids Open - International 4,500,000.00 0.00 Implementati 2019-12-07 2019-12-12 2020-01-23 2020-02-22 2020-03-28 2021-09-19 Envelope Removal incl. UXOs for Capacity Improvement on Naghlu Dam AF-DABS-220313-NC-DIR / Component 3: Environmental Pending Procurement of sediment, soil and Social Sustainability, TF / A1691 Post Direct Selection Direct 10,000.00 0.00 Implementati 2021-02-21 2021-02-26 2021-04-02 2021-05-02 water and POPs tests of Project Management Support, on Naghlu Dam and Future Project Preparation CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual AF-DABS-4497-CS-QCBS / Component 2: Dam Safety Consulting Services for Quality And Cost- TF / A1691 and Power Generation Prior Open - International 6,000,000.00 0.00 Canceled 2016-12-13 2017-01-03 2017-02-16 2017-03-16 2017-04-15 2017-05-20 2017-06-24 2019-06-24 Rehabilitation of Naghlu Based Selection Capacity Improvement Hydropower Dam AF-DABS-4498-CS-QCBS / Component 2: Dam Safety Consultancy Services for ESIA Quality And Cost- TF / A1691 and Power Generation Prior Open - International 1,263,100.00 649,993.00 Signed 2016-12-13 2017-01-03 2017-02-16 2018-09-27 2017-03-16 2018-12-01 2017-04-15 2019-07-17 2017-05-20 2020-02-03 2017-06-24 2020-04-19 2018-12-24 for Naghlu Dam Rehabilitation Based Selection Capacity Improvement Project AF-DABS-14188-CS-QCBS / Consultancy Services for Monitoring & Supervision of Component 1: Mechanical, Unit No.1 Rehabilitation, Quality And Cost- TF / A1691 Electrical, and Prior Open - International 2,400,000.00 0.00 Canceled 2017-05-01 2017-05-22 2017-07-05 2017-08-02 2017-09-01 2017-10-06 2017-11-10 2018-11-10 Overhaul and Maintenance of Based Selection Electromechanical Works Unit No.3 and Supervision of Spare Parts Contract No: DABS-94-ICB-008 AF-DABS-14834-CS-QCBS / consultancy Services of Component 1: Mechanical, Quality And Cost- training program for TF / A1691 Electrical, and Prior Open - International 1,759,642.00 0.00 Canceled 2017-06-20 2017-06-19 2017-07-11 2017-08-24 2017-08-24 2017-09-21 2017-10-21 2017-11-25 2017-12-30 2019-12-31 Based Selection operation and maintenance of Electromechanical Works Naghlu Dam Hydro power plant AF-DABS-14221-CS-QBS / Consultancy Services for Component 1: Mechanical, updating supervisory control Quality Based TF / A1691 Electrical, and Post Open - International 200,000.00 0.00 Canceled 2018-01-01 2018-01-22 2018-03-07 2018-04-04 2018-05-04 2018-06-03 2018-07-08 2019-07-08 software to make computer Selection Electromechanical Works displays readable in National Languages AF-DABS-14665-CS-QCBS / Component 3: Environmental Vocational Skill training for and Social Sustainability, Quality And Cost- upstream and downstream TF / A1691 Project Management Support, Prior Open - International 2,960,000.00 0.00 Canceled 2017-10-07 2017-10-28 2017-12-11 2018-01-08 2018-02-07 2018-03-14 2018-04-18 2021-04-21 Based Selection residence of Naghlu Power and Future Project Plant. Preparation Component 3: Environmental AF-DABS-14172-CS-QCBS / Consultant and Social Sustainability, Pending Consultancy Services for TF / 14861 Post Qualification Open - National 90,000.00 0.00 2017-10-07 2017-10-28 2017-12-11 2018-01-10 2018-02-14 2018-08-13 Project Management Support, Implementation Social Survey Selection and Future Project Preparation AF-DABS-92012-CS-QCBS / Consultancy Services for Component 3: Environmental ENVIRONMENTAL AND SOCIAL and Social Sustainability, Quality And Cost- IMPACT ASSESSMENT (ESIA) TF / A1691 Project Management Support, Prior Open - International 1,352,403.00 0.00 Under Review 2018-12-26 2019-03-26 2019-01-16 2019-04-01 2019-03-01 2019-03-29 2019-04-28 2019-06-02 2019-07-07 2020-07-06 Based Selection AND RESETTLEMENT ACTION and Future Project PLAN (RAP) For KAJAKI DAM Preparation PHASE-II AF-DABS-95594-CS-QCBS / Consultancy Services for Dam Component 2: Dam Safety Quality And Cost- Safety and Hydro mechanical TF / A1691 and Power Generation Prior Open - International 4,225,000.00 1,100,000.00 Signed 2019-02-16 2019-02-10 2019-03-09 2019-03-27 2019-04-22 2020-05-12 2019-05-20 2020-02-10 2019-06-19 2020-06-09 2019-07-24 2020-12-15 2019-08-28 2021-03-08 2021-02-26 Based Selection Works of Naghlu Hydro power Capacity Improvement plant area . AF-DABS-14649-CS-QCBS / Component 3: Environmental Environmental and Social and Social Sustainability, Quality And Cost- TF / A1691 Post Open - International 588,085.00 0.00 Canceled 2019-06-30 2019-07-21 2019-09-03 2019-10-01 2019-10-31 2019-12-05 2020-01-09 2021-01-08 Impact Assessment ( ESIA) for Project Management Support, Based Selection Component 2 and 3 and Future Project Preparation AF-DABS-116166-CS-QCBS / Consultancy Services for Component 1: Mechanical, Operation and Maintenance Quality And Cost- TF / A1691 Electrical, and Prior Open - International 1,213,040.00 0.00 Under Review 2019-06-01 2019-07-30 2019-06-22 2019-09-17 2019-08-05 2020-06-28 2019-09-02 2020-10-17 2019-10-02 2021-04-06 2019-11-06 2019-12-11 2021-08-02 Training Program for Naghlu Based Selection Electromechanical Works Hydro Electric Power Plant Personnel INDIVIDUAL CONSULTANTS Page 3 Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 3: Environmental AF-DABS-14679-CS-INDV / Individual and Social Sustainability, Hiring of Environmental TF / A1691 Post Consultant Open 150,000.00 73,250.00 Signed 2018-01-01 2018-07-15 2018-02-19 2018-12-10 2018-03-12 2018-12-23 2018-04-16 2019-01-01 2018-10-13 Project Management Support, Specialist Selection and Future Project Preparation Component 3: Environmental Individual AF-DABS-14680-CS-INDV / and Social Sustainability, TF / A1691 Post Consultant Open 150,000.00 0.00 Canceled 2017-05-09 2017-06-27 2017-07-18 2017-08-22 2018-02-18 Hiring of Social Specialist Project Management Support, Selection and Future Project Preparation AF-DABS-14681-CS-INDV / Component 3: Environmental Individual Project Director for Naghlu and Social Sustainability, TF / A1691 Prior Consultant Open 240,000.00 0.00 Canceled 2018-01-01 2018-02-19 2018-03-12 2018-04-16 2018-10-13 Hydro Power Rehabilitation Project Management Support, Selection Project (NHRP) and Future Project Preparation Component 3: Environmental AF-DABS-14684-CS-INDV / Individual and Social Sustainability, Hiring Knowledge and TF / A1691 Post Consultant Open 150,000.00 0.00 Canceled 2018-01-01 2018-02-19 2018-03-12 2018-04-16 2018-10-13 Project Management Support, Learning Specialist Selection and Future Project Preparation Component 3: Environmental AF-DABS-14690-CS-INDV / Individual and Social Sustainability, Hiring of Monitoring and TF / A1691 Post Consultant Open 150,000.00 0.00 Canceled 2018-01-01 2018-02-19 2018-03-12 2018-04-16 2018-10-13 Project Management Support, evaluation specialist Selection and Future Project Preparation Component 3: Environmental AF-DABS-14694-CS-INDV / Individual and Social Sustainability, Hiring of Communication TF / A1691 Post Consultant Open 150,000.00 0.00 Canceled 2018-01-01 2018-02-19 2018-03-12 2018-04-16 2018-10-13 Project Management Support, Specialist Selection and Future Project Preparation Component 3: Environmental AF-DABS-14695-CS-INDV / Individual and Social Sustainability, Hiring of Civil Engineer TF / A1691 Post Consultant Open 120,000.00 0.00 Canceled 2018-01-01 2018-02-19 2018-03-12 2018-04-16 2018-10-13 Project Management Support, Supervisor Selection and Future Project Preparation Component 3: Environmental AF-DABS-14726-CS-INDV / Individual and Social Sustainability, Hiring of Electrical and elector TF / A1691 Prior Consultant Open 120,000.00 0.00 Canceled 2018-01-01 2018-02-19 2018-03-12 2018-04-16 2019-04-16 Project Management Support, Mechanical Supervisor Selection and Future Project Preparation Component 3: Environmental AF-DABS-14727-CS-INDV / Individual and Social Sustainability, Hiring of Financial TF / A1691 Post Consultant Open 150,000.00 0.00 Canceled 2017-05-11 2017-06-29 2017-06-29 2017-07-25 2020-12-31 Project Management Support, Management Specialist Selection and Future Project Preparation Component 3: Environmental AF-DABS-14837-CS-INDV / Individual and Social Sustainability, Pending Hiring of Project Technical TF / A1691 Prior Consultant Open 300,000.00 0.00 2017-05-11 2017-06-29 2017-07-20 2017-08-24 2019-01-01 Project Management Support, Implementation Advisor Selection and Future Project Preparation AF-DABS-14838-CS-INDV / Component 3: Environmental Individual Hiring of International and Social Sustainability, TF / A1691 Prior Consultant Open 240,000.00 0.00 Canceled 2017-08-01 2017-08-22 2017-09-19 2017-10-10 2017-11-14 2018-11-13 Procurement and Contract Project Management Support, Selection Management Advisor and Future Project Preparation Component 3: Environmental AF-DABS-14842-CS-INDV / Individual and Social Sustainability, Hiring of International Spare TF / A1691 Post Consultant Open 40,000.00 0.00 Canceled 2018-01-01 2018-02-19 2018-03-12 2018-04-16 2018-08-13 Project Management Support, Part Advisor Selection and Future Project Preparation AF-DABS-14856-CS-INDV / Component 3: Environmental Hiring of International and Social Sustainability, Individual Electrical Engineer to support TF / A1691 Project Management Support, Prior Consultant Open 240,000.00 0.00 Canceled 2017-05-31 2017-07-19 2017-08-09 2017-09-13 2019-09-01 all World Bank funded Project and Future Project Selection as per the ToR Preparation AF-DABS-19922-CS-INDV / International Procurement and Component 3: Environmental Contract management and Social Sustainability, Individual specialist to Support Under TF / A1691 Project Management Support, Prior Consultant Open 360,000.00 0.00 2017-07-30 2019-01-27 2017-09-17 2017-10-08 2017-11-12 2019-11-12 Procurement Directorate of Implementation and Future Project Selection DABS in overall capacity Preparation building of Staff and provide on job training for Staff AF-DABS-14832-CS-INDV / Component 3: Environmental Hiring of International INDV and Social Sustainability, Individual consultant for Preparation of Pending TF / A1691 Project Management Support, Post Consultant Open 25,000.00 0.00 2018-01-01 2018-02-19 2018-03-12 2018-04-16 2018-10-13 ToRs and RFPs for Vocational Implementation and Future Project Selection Training of Local People Preparation whom are closed to Reservoir AF-DABS-14839-CS-INDV / Component 3: Environmental Hiring of International INDV and Social Sustainability, Individual Consultant for Preparation of TF / A1691 Project Management Support, Post Consultant Open 24,000.00 0.00 Canceled 2018-01-01 2018-02-28 2018-03-28 2018-04-28 2018-10-24 Framework for EPP and O&M and Future Project Selection Plans Preparation Component 3: Environmental AF-DABS-14840-CS-INDV / Individual and Social Sustainability, Hiring of International TF / A1691 Post Consultant Open 60,000.00 0.00 Canceled 2018-01-01 2018-02-19 2018-03-12 2018-04-16 2018-10-13 Project Management Support, Feasibility Study Adviser Selection and Future Project Preparation AF-DABS-14638-CS-INDV / Component 3: Environmental Individual International Hydrology and and Social Sustainability, Pending TF / A1691 Post Consultant Open 30,000.00 0.00 2017-05-09 2017-06-27 2017-07-18 2017-08-22 2018-02-18 Flood Routing Expert (PTAP Project Management Support, Implementation Selection Member) and Future Project Preparation AF-DABS-14639-CS-INDV / Component 3: Environmental Individual Hiring of International and Social Sustainability, Pending TF / A1691 Post Consultant Open 30,000.00 0.00 2017-05-09 2017-06-27 2017-07-18 2017-08-22 2018-02-18 Geology and Geo technical Project Management Support, Implementation Selection Expert (PTAP member) and Future Project Preparation AF-DABS-14671-CS-INDV / Component 3: Environmental Individual Hiring International and Social Sustainability, Pending TF / A1691 Post Consultant Open 162,000.00 0.00 2017-05-09 2017-06-27 2017-07-18 2017-08-22 2018-02-18 Environmental expert (ESAP Project Management Support, Implementation Selection member) and Future Project Preparation Page 4 AF-DABS-14676-CS-INDV / Component 3: Environmental Individual Hiring of International Social and Social Sustainability, Pending TF / A1691 Post Consultant Open 162,000.00 0.00 2017-05-09 2017-06-27 2017-07-18 2017-08-22 2018-02-18 Development Expert ( ESAP Project Management Support, Implementation Selection Member) and Future Project Preparation AF-DABS-14851-CS-INDV / Component 3: Environmental Hiring of International INDV and Social Sustainability, Individual consultant for Preparing of TF / A1691 Project Management Support, Post Consultant Open 40,000.00 0.00 Canceled 2017-05-11 2017-06-29 2017-07-20 2017-08-24 2018-02-20 ToRs and RFPs for training and Future Project Selection program and software Preparation translation by IC AF-DABS-14187-CS-INDV / Component 1: Mechanical, Individual Hiring of International Pending TF / A1691 Electrical, and Post Consultant Direct 130,000.00 0.00 2017-05-01 2017-05-11 2017-06-01 2017-07-06 2018-01-02 Consultant ( International Site Implementation Electromechanical Works Selection Supervisor) For NHRP AF-DABS-14624-CS-INDV / Component 3: Environmental Individual International Dam Design and and Social Sustainability, Pending TF / A1691 Post Consultant Open 135,000.00 0.00 2017-05-09 2017-06-27 2017-07-18 2017-08-22 2018-02-18 construction expert (PTAP Project Management Support, Implementation Selection Member) and Future Project Preparation AF-DABS-14625-CS-INDV / Component 3: Environmental Individual International Hydraulic and and Social Sustainability, Pending TF / A1691 Post Consultant Open 120,000.00 0.00 2017-09-01 2017-10-20 2017-11-10 2017-12-15 2018-06-13 sidemen Expert ( PTAP Project Management Support, Implementation Selection Member) and Future Project Preparation AF-DABS-14626-CS-INDV / Component 3: Environmental Individual Hiring of International Elector and Social Sustainability, Pending TF / A1691 Post Consultant Open 60,000.00 0.00 2017-05-09 2017-06-27 2017-07-18 2017-08-22 2018-02-18 Mechanical Expert (PTAP Project Management Support, Implementation Selection Member) and Future Project Preparation AF-DABS-14621-CS-INDV / Component 3: Environmental Individual Team Leader cum Hydro and Social Sustainability, Pending TF / A1691 Post Consultant Open 150,000.00 0.00 2017-05-09 2017-06-27 2017-07-18 2017-08-22 2019-02-13 Power Erection Expert Project Management Support, Implementation Selection (Mechanical Engineer) for and Future Project NHRP Preparation AF-DABS-70279-CS-CDS / Consultancy Services for Component 3: Environmental ENVIRONMENTAL AND SOCIAL and Social Sustainability, IMPACT ASSESSMENT (ESIA) TF / A1691 Project Management Support, Prior Direct Selection Direct 2,265,822.00 0.00 Canceled 2018-07-31 2018-08-10 2018-10-14 2019-10-14 AND RESETTLEMENT ACTION and Future Project PLAN (RAP) For KAJAKI DAM Preparation PHASE-II (MEW) Component 3: Environmental AF-DABS-70281-CS-INDV / Individual and Social Sustainability, INTERNATIONAL SOCIAL TF / A1691 Post Consultant Open 75,000.00 0.00 Canceled 2018-08-01 2018-07-23 2018-09-19 2018-10-10 2018-11-14 2019-02-12 Project Management Support, SAFEGUARD SPECIALIST Selection and Future Project Preparation AF-DABS-70283-CS-INDV / Component 3: Environmental Individual INTERNATIONAL and Social Sustainability, TF / A1691 Prior Consultant Open 240,000.00 0.00 Canceled 2018-08-01 2018-09-29 2018-09-19 2018-10-10 2018-11-14 2019-07-12 ENVIRONMENTAL SAFEGUARD Project Management Support, Selection SPECIALIST and Future Project Preparation AF-DABS-128996-CS-INDV / Component 3: Environmental Individual Hiring of International Site and Social Sustainability, TF / A1691 Post Consultant Direct 30,000.00 38,860.00 Signed 2019-09-07 2019-09-22 2019-09-17 2019-11-19 2019-10-08 2020-02-24 2019-11-12 2020-10-30 2020-05-10 Supervisor cum governor Project Management Support, Selection systems (Andritz) engineer and Future Project Preparation AF-DABS-128998-CS-INDV / Component 3: Environmental Individual Hiring of International Site and Social Sustainability, TF / A1691 Post Consultant Direct 30,000.00 36,360.00 Signed 2019-09-07 2019-09-22 2019-09-17 2019-11-19 2019-10-08 2020-07-05 2019-11-12 2020-09-30 2020-05-10 Supervisor Short Term Control Project Management Support, Selection (Metso) Systems Engineer and Future Project Preparation Component 3: Environmental AF-DABS-128999-CS-INDV / Individual and Social Sustainability, Hiring of International TF / A1691 Post Consultant Open 150,000.00 107,900.00 Signed 2019-09-07 2019-09-29 2019-10-11 2020-02-01 2019-11-01 2020-03-26 2019-12-06 2020-04-25 2020-12-05 Project Management Support, electrical systems engineer Selection and Future Project Preparation AF-DABS-129093-CS-INDV / Component 3: Environmental Individual Hiring of International and Social Sustainability, Under TF / A1691 Post Consultant Open 100,000.00 0.00 2019-09-14 2020-02-04 2019-10-18 2019-11-08 2019-12-13 2020-12-12 Hydrology and flood routing Project Management Support, Implementation Selection Expert for (PTAP Panel) and Future Project Preparation AF-DABS-129897-CS-INDV / Component 3: Environmental Individual Hiring of International Electro and Social Sustainability, Under TF / A1691 Post Consultant Open 110,000.00 0.00 2019-09-21 2020-02-04 2019-10-25 2019-11-15 2019-12-20 2020-12-19 Mechanical Engineering Project Management Support, Implementation Selection Expert for (PTAP Panel) and Future Project Preparation AF-DABS-128993-CS-INDV / Component 3: Environmental Individual Hiring of International Site and Social Sustainability, TF / A1691 Post Consultant Direct 30,000.00 30,720.00 Signed 2019-09-07 2019-09-24 2019-09-17 2019-11-19 2019-10-08 2020-02-24 2019-11-12 2020-04-25 2020-05-10 Supervisor cum excitation Project Management Support, Selection systems engineer and Future Project Preparation AF-DABS-129084-CS-INDV / Component 3: Environmental Individual Hiring of International Social and Social Sustainability, TF / A1691 Post Consultant Open 110,000.00 23,680.00 Signed 2019-09-14 2020-01-28 2019-11-02 2020-06-10 2019-11-23 2020-08-20 2019-12-28 2020-11-01 2020-12-27 Development Expert for (ESAP Project Management Support, Selection Panel) and Future Project Preparation AF-DABS-129090-CS-INDV / Component 3: Environmental Individual Hiring of International Dam and Social Sustainability, Under TF / A1691 Post Consultant Open 110,000.00 0.00 2019-09-14 2020-01-28 2019-10-18 2019-11-08 2019-12-13 2020-12-12 Designs and Construction Project Management Support, Implementation Selection Expert for (PTAP Panel) and Future Project Preparation AF-DABS-129895-CS-INDV / Component 3: Environmental Individual Hiring of International and Social Sustainability, Under TF / A1691 Post Consultant Open 100,000.00 0.00 2019-09-21 2020-02-04 2019-10-25 2019-11-15 2019-12-20 2020-12-19 Geology and Geo-technical Project Management Support, Implementation Selection Expert for (PTAP Panel) and Future Project Preparation AF-DABS-129899-CS-INDV / Component 3: Environmental Individual Hiring of International and Social Sustainability, TF / A1691 Post Consultant Open 150,000.00 118,400.00 Signed 2019-09-14 2019-09-26 2019-11-02 2019-12-30 2019-11-23 2020-06-22 2019-12-28 2021-01-05 2020-12-27 Technical Advisor for World Project Management Support, Selection Bank Funded projects at DABS and Future Project Preparation AF-DABS-129080-CS-INDV / Component 3: Environmental Individual Hiring of International and Social Sustainability, TF / A1691 Post Consultant Open 100,000.00 25,680.00 Signed 2019-09-14 2020-01-28 2019-10-18 2020-06-13 2019-11-08 2020-08-20 2019-12-13 2020-11-01 2020-12-12 Environmental Expert for Project Management Support, Selection (ESAP Panel) and Future Project Preparation Page 5 AF-DABS-179951-CS-INDV / Component 3: Environmental Hiring of International Dam and Social Sustainability, Individual Under Design and Construction TF / A1691 Project Management Support, Post Consultant Open 66,900.00 0.00 2020-06-27 2020-06-25 2020-08-15 2020-09-05 2020-10-10 2021-10-10 Implementation Specialist for Kajaki Phase II and Future Project Selection PTAP member Preparation AF-DABS-179952-CS-INDV / Component 3: Environmental Hiring of International and Social Sustainability, Individual Under Hydrology / Hydraulic TF / A1691 Project Management Support, Post Consultant Open 66,900.00 0.00 2020-06-27 2020-06-25 2020-08-15 2020-09-05 2020-10-10 2021-10-10 Implementation Specialist for Kajaki Phase II and Future Project Selection PTAP Member Preparation AF-DABS-179953-CS-INDV / Component 3: Environmental Hiring of International and Social Sustainability, Individual Under Geology / Geotechnical TF / A1691 Project Management Support, Post Consultant Open 66,900.00 0.00 2020-06-27 2020-06-29 2020-08-15 2020-09-05 2020-10-10 2021-10-10 Implementation Specialist for Kajaki Phase II and Future Project Selection PTAP Member Preparation AF-DABS-179954-CS-INDV / Component 3: Environmental Hiring of International Hydro / and Social Sustainability, Individual Under Electromechanical Specialist TF / A1691 Project Management Support, Post Consultant Open 66,900.00 0.00 2020-06-30 2020-06-29 2020-08-18 2020-09-08 2020-10-13 2021-10-13 Implementation for Kajaki Phase II PTAP and Future Project Selection Member Preparation AF-DABS-179955-CS-INDV / Component 3: Environmental Hiring of International and Social Sustainability, Individual Under Environmental Safeguard TF / A1691 Project Management Support, Post Consultant Open 66,900.00 0.00 2020-07-04 2020-06-29 2020-08-22 2020-09-12 2020-10-17 2021-10-17 Implementation Specialist for Kajaki Phase II and Future Project Selection ESAP panel member Preparation AF-DABS-179956-CS-INDV / Component 3: Environmental Hiring of International Social and Social Sustainability, Individual Under Development Specialist for TF / A1691 Project Management Support, Post Consultant Open 66,900.00 0.00 2020-07-04 2020-06-29 2020-08-22 2020-09-12 2020-10-17 2021-10-17 Implementation Kajaki Phase II ESAP panel and Future Project Selection Member Preparation AF-DABS-209414-CS-INDV / Component 3: Environmental Hiring of International and Social Sustainability, Individual Under Environmental Safeguard TF / A1691 Project Management Support, Post Consultant Open 162,000.00 0.00 2020-12-26 2020-12-30 2021-02-13 2021-03-06 2021-04-10 2021-07-09 Implementation Specialist for Kajaki Phase 2 and Future Project Selection Project Preparation AF-DABS-209415-CS-INDV / Component 3: Environmental Individual Hiring of International Social and Social Sustainability, Under TF / A1691 Post Consultant Open 162,000.00 0.00 2020-12-26 2020-12-30 2021-02-13 2021-03-06 2021-04-10 2021-07-09 Safeguard Specialist for Kajaki Project Management Support, Implementation Selection Phase 2 Project and Future Project Preparation AF-DABS-209416-CS-INDV / Component 3: Environmental Hiring of International Quality and Social Sustainability, Individual Under Assurance Hydro Mechanical TF / A1691 Project Management Support, Post Consultant Open 162,000.00 0.00 2020-12-31 2021-01-21 2021-02-18 2021-03-11 2021-04-15 2021-07-14 Implementation Engineer for Kajaki Phase 2 and Future Project Selection Project Preparation Page 6 PE Modernization of WSS Services (P157043) Procurement Plan Country: Peru Region: LATIN AMERICA AND CARIBBEAN Approval Date: 26-July-2018 July 9, 2010 PROCUREMENT Peru : Modernization of Water Supply and Sanitation Services PLAN General Information Country: Peru Bank’s Approval Date of the Original Procurement Plan: 2019-07-18 2021-05-27 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P157043 GPN Date: 2019-10-31 Project Name: Modernization of Water Supply and Sanitation Services Loan / Credit No: IBRD / 88990 T Executing Agency(ies): he Technical Organization for the Administration of WSS Services WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SDO N° 0001-2020-MVCS- Improving Governance of Single Stage - One UE003-OTASS / Servidor IBRD / 88990 Water Supply and Sanitation Post Request for Bids Open - National 75,757.58 0.00 Canceled 2020-04-20 2020-04-26 2020-06-02 2020-06-08 2020-06-26 2020-07-31 Envelope VMCS Service Providers SDO N° 0002-2020-MVCS- Improving Governance of UE003-OTASS / Adquisición Single Stage - One IBRD / 88990 Water Supply and Sanitation Post Request for Bids Open - National 185,206.06 0.00 Canceled 2020-04-20 2020-04-26 2020-06-02 2020-06-08 2020-06-26 2020-07-31 de otros equipos de apoyo a Envelope Service Providers las EPS y OSN SDC N° 005-2020-MVCS- General Project Request for Single Stage - One IBRD / 88990 Post Limited 33,147.27 0.00 Canceled 2020-05-13 2020-05-27 2020-06-26 UE003-OTASS / Licencia CAD Administration Quotations Envelope SDC N° 006-2020-MVCS- General Project Request for Single Stage - One IBRD / 88990 Post Limited 12,765.45 0.00 Canceled 2020-05-20 2020-06-03 2020-06-30 UE003-OTASS / Licencia S10 Administration Quotations Envelope SDC N° 007-2020-MVCS- General Project Request for Single Stage - One UE003-OTASS / Licencia MS IBRD / 88990 Post Limited 18,593.94 0.00 Canceled 2020-05-08 2020-05-20 2020-06-19 Administration Quotations Envelope Project SDC N° 008-2020-MVCS- General Project Request for Single Stage - One IBRD / 88990 Post Limited 46,484.85 0.00 Canceled 2020-05-11 2020-05-29 2020-07-30 UE003-OTASS / Camioneta Administration Quotations Envelope SDO N° 0003-2020-MVCS- General Project Single Stage - One UE003-OTASS / IBRD / 88990 Post Request for Bids Open - National 102,911.82 0.00 Canceled 2020-05-04 2020-05-09 2020-06-20 2020-06-25 2020-07-15 2020-08-17 Administration Envelope Videoconferencia SDC N° 09-2020-MVCS- General Project Request for Single Stage - One UE003-OTASS / Licencia Arc IBRD / 88990 Post Limited 49,850.00 0.00 Canceled 2020-05-04 2020-05-14 2020-05-29 Administration Quotations Envelope Gis SDC N° 010-2020-MVCS- General Project Request for Single Stage - One IBRD / 88990 Post Limited 4,290.91 0.00 Canceled 2020-05-07 2020-05-18 2020-05-26 UE003-OTASS / Lap Top Administration Quotations Envelope SDC N° 011-2020-MVCS- General Project Request for Single Stage - One UE003-OTASS / IBRD / 88990 Post Limited 25,030.30 0.00 Canceled 2020-05-05 2020-05-18 2020-05-29 Administration Quotations Envelope Computadoras de ingenieria SDC N° 012-2020-MVCS- General Project Request for Single Stage - One UE003-OTASS / IBRD / 88990 Post Limited 42,909.09 0.00 Canceled 2020-05-06 2020-05-18 2020-05-28 Administration Quotations Envelope Computadoras de escritorio NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SDC 001 / SERVICIO DE CONTRATACIÓN Improving Governance of CONVOCATORIA Y ESCENARIO Request for Single Stage - One IBRD / 88990 Water Supply and Sanitation Post Limited 21,060.00 19,161.09 Signed 2020-02-12 2020-02-17 2020-02-18 2020-02-25 2020-04-03 PRINCIPAL IMPLEMENTACIÓN Quotations Envelope Service Providers PRIMER ENCUENTRO AGUA TODAS SDC 002 / SERVICIO DE CONTRATACIÓN Improving Governance of ACREDITACIÓN, PROTOCOLO, Request for Single Stage - One IBRD / 88990 Water Supply and Sanitation Post Limited 30,394.00 23,298.76 Signed 2020-02-12 2020-02-17 2020-02-18 2020-02-25 2020-04-03 SEGURIDAD Y CATERING Quotations Envelope Service Providers IMPLEMENTACION DEL PRIMER ENCUENTRO AGUAS TODAS SDC 003 / SERVICIO DE Improving Governance of CONTRATACION GESTION DE Request for Single Stage - One IBRD / 88990 Water Supply and Sanitation Post Limited 8,400.00 7,372.85 Signed 2020-02-12 2020-02-17 2020-02-18 2020-02-28 2020-04-03 PRENSA PRIMER ENCUENTRO Quotations Envelope Service Providers AGUA TODAS SDC N 015 / SERVICIO DE CONTRATACIÓN DEL SISTEMA Improving Governance of STREAMING PARA LA Request for Single Stage - One IBRD / 88990 Water Supply and Sanitation Post Limited 7,575.76 6,382.38 Signed 2020-06-09 2020-06-26 2020-06-22 2020-06-19 2020-07-13 TRANSMISIÓN VIRTUAL DEL Quotations Envelope Service Providers “PRIMER ENCUENTRO AGUAS TODAS SDC 16 / CONTRATACIÓN DEL SERVICIO DE GESTIÓN DE PAUTA PUBLICITARIA Y MONITOREO Y REPORTE DE Improving Governance of Request for Single Stage - One INDICADORES PARA REDES IBRD / 88990 Water Supply and Sanitation Post Limited 24,242.22 22,215.68 Signed 2020-08-05 2020-10-29 2020-08-13 2020-11-02 2021-04-30 Quotations Envelope SOCIALES FACEBOOK Y Service Providers WHATSAPP EN EL MARCO DE LA CAMPANA GUERREROS/AS POR EL AGUA Page 1 SDC 17 / CONTRATACIÓN DEL SERVICIO DE PRODUCCION Y DIFUSION DE Improving Governance of Request for Single Stage - One SPOT RADIALES EN EMISORAS IBRD / 88990 Water Supply and Sanitation Post Limited 30,303.03 27,762.61 Signed 2020-08-05 2020-10-27 2020-08-13 2020-11-02 2021-04-30 Quotations Envelope LOCALES Y REGIONALES EN EL Service Providers MARCO DE LA CAMPANA GUERREROS/AS POR EL AGUA CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 1.3.6.1 / Contratación de Firma “Programa de Capacitación Especializado Improving Governance of para el Desarrollo de Quality And Cost- IBRD / 88990 Water Supply and Sanitation Post Open - International 817,621.00 0.00 Canceled 2020-01-06 2020-02-17 2020-01-12 2020-02-07 2020-03-06 2020-04-05 2020-05-10 2020-06-14 2021-06-14 Capacidades de Gestión, Based Selection Service Providers Administración y Operación de Empresas Prestadoras de Servicios de Saneamiento" SDP N° 001-2020-MVCS- UE003-OTASS / Contratación de Firma “Programa de Capacitación Especializado Improving Governance of Quality And Cost- para el Desarrollo de IBRD / 88990 Water Supply and Sanitation Prior Open - International 1,220,884.79 0.00 Canceled 2020-02-28 2020-03-02 2020-03-01 2020-04-14 2020-05-12 2020-06-11 2020-07-16 2020-08-20 2021-08-20 Based Selection Capacidades de Gestión, Service Providers Administración y Operación de Empresas Prestadoras de Servicios de Saneamiento" SDP N° 0001-2020-MVCS- UE003-OTASS / Contratación de Firma “Programa de Capacitación Especializado Improving Governance of Quality And Cost- Under para el Desarrollo de IBRD / 88990 Water Supply and Sanitation Prior Open - National 1,220,884.79 0.00 2020-03-05 2020-03-05 2020-03-08 2020-07-14 2020-04-21 2020-09-23 2020-05-19 2020-10-26 2020-06-18 2020-12-22 2020-07-23 2020-08-27 2021-08-27 Based Selection Implementation Capacidades de Gestión, Service Providers Administración y Operación de Empresas Prestadoras de Servicios de Saneamiento" SDP N° 0005-2020-MVCS- Improving Governance of UE003-OTASS / Operatividad Quality And Cost- IBRD / 88990 Water Supply and Sanitation Post Open - National 86,363.64 0.00 Canceled 2020-06-01 2020-06-07 2020-06-30 2020-07-30 2020-08-04 2020-08-13 2020-08-31 2021-02-26 de la Estrategia del ¨Programa Based Selection Service Providers de Modernización SDP N° 0006-2020-MVCS- Improving Governance of Consultant UE003-OTASS / Pagina Web IBRD / 88990 Water Supply and Sanitation Post Qualification Open - National 10,606.06 0.00 Canceled 2020-05-01 2020-05-10 2020-06-24 2020-06-26 2020-07-10 2020-08-10 UE 003 Service Providers Selection SDP N° 0002-2020-MVCS- UE003-OTASS / Revisíon del Marco normativo para elaborar y aplicar una escala Improving Governance of Consultant salarial y una política salarial IBRD / 88990 Water Supply and Sanitation Post Qualification Open - National 23,636.36 0.00 Canceled 2020-04-20 2020-04-26 2020-05-13 2020-05-28 2020-06-01 2020-08-03 integral en las EPS en RAT; y Service Providers Selection elaboración de propuesta de Política salarial integral para las EPS en RAT. SDP N° 0004-2020-MVCS- UE003-OTASS / Elaboración Improving Governance of Consultant de un plan de desarrollo y IBRD / 88990 Water Supply and Sanitation Post Qualification Open - National 18,181.82 0.00 Canceled 2020-04-20 2020-04-26 2020-05-13 2020-05-28 2020-06-01 2020-08-31 línea de carrera para el Service Providers Selection personal en las EPS. SDP N° 0007-2020-MVCS- UE003-OTASS / Servicio de Consultoria en el análisis y la elaboración del marco normativo para el diseño e Improving Governance of Quality And Cost- implementacion del sistema IBRD / 88990 Water Supply and Sanitation Post Open - National 45,250.78 0.00 Canceled 2020-08-17 2020-08-19 2020-08-22 2020-09-17 2020-10-27 2020-10-30 2020-11-13 2020-12-07 2021-05-07 Based Selection salarial integral, evaluación de Service Providers rendimiento, plan de desarrollo y línea de carrera para las Empresas Prestadoras de Servicios de Sanea SDP N° 0003-2020-MVCS- UE003-OTASS / Servicio de Improving Governance of Consultoria para el Diseño de Quality And Cost- IBRD / 88990 Water Supply and Sanitation Post Open - National 167,888.85 0.00 Canceled 2020-08-17 2020-08-19 2020-08-22 2020-09-17 2020-10-27 2020-10-30 2020-11-13 2020-12-07 2021-04-07 un Sistema Salarial Integral Based Selection Service Providers para las Empresas Prestadoras de Servicios de Sanea SDP N° 0008-2020-MVCS- UE003-OTAS / Servicio de Consultoria para el Diseño de Improving Governance of un Sistema de Evaluación del Quality And Cost- IBRD / 88990 Water Supply and Sanitation Post Open - National 107,182.56 0.00 Canceled 2020-08-17 2020-08-19 2020-08-22 2020-09-17 2020-10-27 2020-10-30 2020-11-13 2020-12-07 2021-03-22 Rendimiento, Plan de Based Selection Service Providers desarrollo y Linea de Carrera para las Empresas Prestadoras de Servicios Municipales SDP N° 0009-2020-MVCS- UE003-OTASS / Servicio de Consultoría para el Diseño de Improving Governance of Consultant un Sistema Salarial Integral IBRD / 88990 Water Supply and Sanitation Post Qualification Open - National 167,888.85 161,814.51 Signed 2020-09-15 2020-09-25 2020-09-22 2020-11-03 2020-10-07 2020-11-26 2020-10-29 2021-02-24 2020-11-04 2021-03-09 2021-03-05 para las Empresas Prestadoras Service Providers Selection de Servicios de Saneamiento Municipales SDP N° 0010-2020-MVCS- UE003-OTASS / Servicio de Consultoría para el Diseño de Improving Governance of Consultant un Sistema de Evaluación del IBRD / 88990 Water Supply and Sanitation Post Qualification Open - National 107,182.56 100,235.38 Signed 2020-09-15 2020-09-25 2020-09-22 2020-11-03 2020-10-07 2020-11-28 2020-10-29 2021-03-22 2020-11-04 2021-03-30 2021-02-17 Rendimiento, Plan de Service Providers Selection desarrollo y Línea de Carrera para las Empresas Prestadoras de Servicios Municipales Page 2 PE-OTASS-211887-CS-LCS / Auditoría Financiera al Programa “Modernización de la Prestación de los Servicios de Agua Potable y Improving Governance of Saneamiento de las EPS Least Cost Under IBRD / 88990 Water Supply and Sanitation Post Open - National 333,880.73 0.00 2021-01-08 2021-03-12 2021-01-29 2021-03-14 2021-03-25 2021-04-11 2021-05-11 2021-06-15 2021-07-20 2022-01-16 EMAPACOP, SEDACUSCO, Selection Implementation Service Providers SEDAPAR, SEMAPA BARRANCA, EMAPA HUARAL Y EMAPA HUACHO” financiado con “Contrato de Préstamo No 8899-PE” PE-OTASS-225691-CS-QCBS / Contratación de una solución informática mediante un software integrado con los Improving Governance of Quality And Cost- Under procesos administrativos, IBRD / 88990 Water Supply and Sanitation Prior Open - International 6,863,774.28 0.00 2021-03-22 2021-06-01 2021-04-12 2021-05-26 2021-06-23 2021-07-23 2021-08-27 2021-10-01 2022-10-01 Based Selection Implementation comerciales, operacionales y Service Providers corporativos, alineado al modelo propuesto por OTASS - PROYECTO GO PE-OTASS-228498-CS-CQS / consultoría para asesoría de la Improving Governance of Consultant formulación de reglas, Under IBRD / 88990 Water Supply and Sanitation Post Qualification Open - National 20,000.00 0.00 2021-04-20 2021-04-26 2021-05-11 2021-06-24 2021-07-24 2021-08-28 2021-09-06 disposiciones y procedimiento Implementation Service Providers Selection especial, Articulo 103 del D.L. N°1280 PE-OTASS-229755-CS-CQS / Análisis de la implementación Improving Governance of Consultant Under de la reforma sectorial en IBRD / 88990 Water Supply and Sanitation Post Qualification Open - National 67,429.00 0.00 2021-05-03 2021-05-14 2021-05-24 2021-07-07 2021-08-06 2021-09-10 2022-03-09 Implementation servicios de saneamiento Service Providers Selection 2016-2021 PE-OTASS-229756-CS-CQS / Diseño de cursos de Improving Governance of Consultant capacitación para el Pending IBRD / 88990 Water Supply and Sanitation Post Qualification Open - National 40,457.00 0.00 2021-05-03 2021-05-24 2021-07-07 2021-08-06 2021-09-10 2022-03-09 fortalecimiento de Implementation Service Providers Selection capacidades de funcionarios de las EPS y del sector. PE-OTASS-229757-CS-CQS / Elaboración de propuesta para Improving Governance of Consultant la actualización de la Política IBRD / 88990 Water Supply and Sanitation Post Qualification Open - National 26,971.00 0.00 Canceled 2021-05-03 2021-04-26 2021-05-24 2021-07-07 2021-08-06 2021-09-10 2022-03-09 Nacional de Saneamiento Service Providers Selection (PNS). PE-OTASS-229758-CS-CQS / Elaboración de una nueva Improving Governance of Consultant Pending propuesta de reestructuración IBRD / 88990 Water Supply and Sanitation Post Qualification Open - National 16,857.00 0.00 2021-05-03 2021-05-24 2021-07-07 2021-08-06 2021-09-10 2022-03-09 Implementation del esquema de Gobierno Service Providers Selection Corporativo para las EPS. PE-OTASS-229759-CS-CQS / Estudio de análisis de la Improving Governance of Consultant Pending problemática de las IBRD / 88990 Water Supply and Sanitation Post Qualification Open - National 25,286.00 0.00 2021-05-03 2021-05-24 2021-07-07 2021-08-06 2021-09-10 2022-03-09 Implementation inversiones de las EPS Service Providers Selection medianas y grandes. PE-OTASS-229760-CS-CQS / Diseño y validación del marco normativo para regulación, Improving Governance of Consultant Pending supervisión y sanción de IBRD / 88990 Water Supply and Sanitation Post Qualification Open - National 43,896.00 0.00 2021-05-03 2021-05-24 2021-07-07 2021-08-06 2021-09-10 2022-03-09 Implementation prestadores de pequeñas Service Providers Selection ciudades y comunidades rurales. PE-OTASS-229761-CS-CQS / Diseño e implementación de Improving Governance of Consultant un programa de capacitación Pending IBRD / 88990 Water Supply and Sanitation Post Qualification Open - National 87,657.00 0.00 2021-05-03 2021-05-24 2021-07-07 2021-08-06 2021-09-10 2022-03-09 para el personal de los Implementation Service Providers Selection Centros de Atención al Ciudadano (CAC) del PNSU PE-OTASS-229762-CS-CQS / Estudio de factibilidad para la implementación de "Call Improving Governance of Consultant Pending Centers" de alcance regional o IBRD / 88990 Water Supply and Sanitation Post Qualification Open - National 57,143.00 0.00 2021-05-03 2021-05-24 2021-07-07 2021-08-06 2021-09-10 2022-03-09 Implementation macroregional, para las EPS Service Providers Selection EMAPACOP, SEDACUSCO, SEDAPAR y EMAPA HUACHO PE-OTASS-229763-CS-CQS / Estudio de factibilidad para la implementación de Improving Governance of Consultant "Laboratorios de Control de Pending IBRD / 88990 Water Supply and Sanitation Post Qualification Open - National 57,143.00 0.00 2021-05-03 2021-05-24 2021-07-07 2021-08-06 2021-09-10 2022-03-09 Calidad" de alcance regional o Implementation Service Providers Selection macroregional, para las EPS EMAPACOP, SEDACUSCO, SEDAPAR y EMAPA HUACHO. PE-OTASS-229764-CS-CQS / Estudio de factibilidad para la implementación de "Bancos de Improving Governance of Consultant Medidores" de alcance Pending IBRD / 88990 Water Supply and Sanitation Post Qualification Open - National 57,143.00 0.00 2021-05-03 2021-05-24 2021-07-07 2021-08-06 2021-09-10 2022-03-09 regional o macroregional, Implementation Service Providers Selection para las EPS EMAPACOP, SEDACUSCO, SEDAPAR y EMAPA HUACHO. INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 3 1.1.1.1-CI-8899 / Diagnóstico de la situación actual de los sistemas de información de prestadores Improving Governance of Individual urbanos y rurales y propuesta IBRD / 88990 Water Supply and Sanitation Post Consultant Limited 30,303.00 0.00 Canceled 2019-09-02 2019-09-07 2019-09-28 2019-11-02 2019-12-17 de sistema integrado Service Providers Selection considerando el componente georreferenciado y la contabilidad regulatoria 1.1.1.2-CI-8899 / Diagnóstico para la identificación de la información necesaria y Improving Governance of Individual relevante de los prestadores IBRD / 88990 Water Supply and Sanitation Post Consultant Limited 30,303.00 0.00 Canceled 2019-09-02 2019-09-07 2019-09-28 2019-11-02 2019-12-17 urbanos y rurales para el Service Providers Selection sector saneamiento y las estrategias para su recopilación e integración 1.1.5.1-CI-8899 / Levantamiento y procesamiento de información Improving Governance of Individual de la implementacion de los IBRD / 88990 Water Supply and Sanitation Post Consultant Limited 16,787.00 0.00 Canceled 2019-09-16 2019-09-21 2019-10-12 2019-11-16 2019-12-31 proyectos contenidos en los Service Providers Selection Planes Regionales de Saneamiento vinculados al cierre de brechas 3.3.4-CI-8899 / Consultoría Individual General Project Pending para la Elaboración Línea de IBRD / 88990 Post Consultant Limited 121,212.00 0.00 2019-09-09 2019-09-14 2019-10-05 2019-11-09 2020-03-08 Administration Implementation Base Selection 3.3.5-CI-8899 / Diseño del Individual General Project software de evaluación y IBRD / 88990 Post Consultant Limited 15,152.00 0.00 Canceled 2019-09-13 2019-09-18 2019-10-09 2019-11-13 2020-01-12 Administration seguimiento Selection 3.4.14-CI-8899 / Proceso de Individual General Project Contratación del Especialista IBRD / 88990 Post Consultant Limited 78,787.88 0.00 Canceled 2019-08-22 2019-09-07 2019-08-27 2019-09-17 2019-10-22 2023-12-31 Administration 02 para Componente 1 Selection 3.4.1-SD-8899 / Proceso de Contratación del Director de General Project IBRD / 88990 Prior Direct Selection Direct 310,909.00 0.00 Canceled 2019-07-26 2019-08-20 2019-07-28 2019-07-31 2023-12-31 la Unidad Ejecutora del Administration Programa (UE003) 3.4.3-SD-8899 / Proceso de Contratación del Especialista General Project IBRD / 88990 Post Direct Selection Direct 241,818.00 0.00 Canceled 2019-07-19 2019-09-19 2019-07-21 2019-07-24 2023-12-31 en Adquisiciones (Jefe Área de Administration Adquisiciones) 3.4.2-CI-8899 / Proceso de Individual General Project Contratación del Coordinador IBRD / 88990 Post Consultant Limited 271,515.00 26,690.27 Signed 2019-08-05 2020-01-08 2019-08-10 2020-01-08 2019-08-31 2020-01-15 2019-10-05 2020-01-20 2023-12-31 Administration Administrativo Selection 3.4.7-CI-8899 / Proceso de Individual Contratación del Especialista General Project IBRD / 88990 Post Consultant Limited 237,576.00 67,005.41 Signed 2019-08-05 2019-08-20 2019-08-10 2019-10-08 2019-08-31 2019-10-17 2019-10-05 2019-10-17 2023-12-31 Financiero (Jefe Área de Administration Selection Finanzas) 3.4.8-CI-8899 / Proceso de Individual Contratación del Especialista General Project IBRD / 88990 Post Consultant Limited 233,333.00 9,108.22 Signed 2019-08-22 2019-10-21 2019-08-27 2020-02-10 2019-09-17 2020-02-24 2019-10-22 2020-02-28 2023-12-31 en Contabilidad (Jefe Área de Administration Selection Contabilidad) 3.4.11-CI-8899 / Proceso de Individual Contratación del Especialista General Project IBRD / 88990 Post Consultant Limited 159,090.91 17,737.88 Signed 2019-08-22 2019-10-21 2019-08-27 2019-11-05 2019-09-17 2019-11-18 2019-10-22 2019-11-19 2023-12-31 en Comunicación (Jefe Área de Administration Selection Comunicaciones) 3.4.22-CI-8899 / Proceso de Individual Contratación de Especialista General Project Under IBRD / 88990 Post Consultant Limited 151,515.15 0.00 2019-08-26 2021-06-10 2019-08-31 2019-09-21 2019-10-26 2023-12-31 en indicadores y Base de Administration Implementation Selection Datos 3.4.10-CI-8899 / Proceso de Individual General Project Contratación del Asesor Legal IBRD / 88990 Post Consultant Limited 263,030.30 30,832.93 Signed 2019-08-05 2020-02-21 2019-08-10 2020-02-27 2019-08-31 2020-03-02 2019-10-05 2020-03-03 2023-12-31 Administration (Jefe Área de Asesoría Legal) Selection 3.4.6-CI-8899 / Proceso de Contratación del Especialista Individual General Project en Planeamiento y IBRD / 88990 Post Consultant Limited 248,939.00 10,718.00 Terminated 2019-08-05 2019-09-03 2019-08-10 2019-10-01 2019-08-31 2019-10-03 2019-10-05 2019-10-15 2023-12-31 Administration Presupuesto (Jefe Área de Selection Planeam. Ppto) 3.4.12-CI-8899 / Proceso de Individual General Project Contratación del Coordinador IBRD / 88990 Post Consultant Limited 240,909.09 10,593.22 Signed 2019-08-05 2019-09-03 2019-08-10 2021-03-16 2019-08-31 2021-03-29 2019-10-05 2021-04-07 2023-12-31 Administration Técnico Componente 1 Selection 3.4.21-CI-8899 / Proceso de Individual General Project Contratación de Especialista IBRD / 88990 Post Consultant Limited 151,515.15 0.00 Canceled 2019-08-26 2019-08-31 2019-09-21 2019-10-26 2023-12-31 Administration en presupuesto Selection 3.4.13-CI-8899 / Proceso de Individual General Project Contratación del Especialista IBRD / 88990 Post Consultant Limited 151,515.15 70,204.62 Signed 2019-08-22 2019-09-03 2019-08-27 2019-09-04 2019-09-17 2019-09-09 2019-10-22 2019-09-10 2023-12-31 Administration 01 para Componente 1 Selection 3.4.9-CI-8899 / Proceso de Contratación del Especialista Individual General Project en Monitoreo y Evaluación IBRD / 88990 Post Consultant Limited 263,030.30 87,164.03 Completed 2019-08-05 2019-09-03 2019-08-10 2019-09-04 2019-08-31 2019-09-11 2019-10-05 2019-09-11 2023-12-31 2021-01-18 Administration (Jefe Área de Monitoreo y Selection Evaluación) 3.4.20-CI-8899 / Proceso de Contratación de Analista Individual General Project Ambiental y Social IBRD / 88990 Post Consultant Limited 151,515.15 14,813.38 Signed 2019-08-05 2019-10-21 2019-08-10 2019-11-06 2019-08-31 2019-11-18 2019-10-05 2019-11-20 2023-12-31 Administration (Especialista en Salvaguarda Selection Ambiental y Social) Page 4 3.4.23-CI-8899 / Individual Coordinador Responsable del General Project IBRD / 88990 Post Consultant Limited 237,576.00 86,519.11 Signed 2019-07-29 2019-09-03 2019-08-03 2019-09-26 2019-08-24 2019-10-04 2019-09-28 2019-10-04 2023-12-31 Componente 2 (apoyo al Administration Selection PNSU) 3.4.24-CI-8899 / Individual General Project Especialista Adquisiciones IBRD / 88990 Post Consultant Limited 186,667.00 52,215.98 Signed 2019-07-29 2019-09-03 2019-08-03 2019-09-25 2019-08-24 2019-10-04 2019-09-28 2019-10-04 2023-12-31 Administration (apoyo al PNSU) Selection 3.4.28-CI-8899 / Individual General Project Especialista Presupuesto IBRD / 88990 Post Consultant Limited 176,667.00 60,525.03 Signed 2019-07-29 2019-09-03 2019-08-03 2019-10-01 2019-08-24 2019-10-15 2019-09-28 2019-10-15 2023-12-31 Administration (apoyo al PNSU) Selection 3.4.29-CI-8899 / Individual General Project Especialista Financiero IBRD / 88990 Post Consultant Limited 186,667.00 45,421.56 Terminated 2019-07-29 2019-09-03 2019-08-03 2019-10-04 2019-08-24 2019-10-15 2019-09-28 2019-10-15 2023-12-31 Administration (apoyo al PNSU) Selection Individual 3.4.30.CI-8899 / Especialista General Project IBRD / 88990 Post Consultant Limited 183,333.00 11,616.49 Signed 2019-08-12 2019-11-29 2019-08-17 2019-12-04 2019-09-07 2019-12-20 2019-10-12 2019-12-27 2023-12-31 en Contabilidad Administration Selection 3.4.31-CI.8899 / Especialista Individual General Project Legal IBRD / 88990 Post Consultant Limited 176,667.00 38,389.02 Signed 2019-08-12 2019-10-10 2019-08-17 2019-10-11 2019-09-07 2019-10-18 2019-10-12 2019-10-30 2023-12-31 Administration (apoyo al PNSU) Selection 3.4.32-CI-8899 / Individual Coordinador técnico del General Project IBRD / 88990 Post Consultant Limited 208,333.00 41,882.09 Signed 2019-08-12 2019-10-16 2019-08-17 2019-10-16 2019-09-07 2019-10-24 2019-10-12 2019-10-30 2023-12-31 componente 2 Administration Selection (apoyo al PNSU) 3.4.33-CI-8899 / Individual General Project Coordinador 01 de Proyecto IBRD / 88990 Post Consultant Limited 103,333.00 36,757.44 Signed 2019-08-12 2019-10-11 2019-08-17 2019-10-14 2019-09-07 2019-10-18 2019-10-12 2019-10-18 2021-12-31 Administration (apoyo al PNSU) Selection 3.4.34-CI.8899 / Individual General Project Coordinador 02 de Proyecto IBRD / 88990 Post Consultant Limited 53,333.00 36,508.33 Signed 2019-08-12 2019-10-11 2019-08-17 2019-10-11 2019-09-07 2019-10-18 2019-10-12 2019-10-18 2020-12-31 Administration (apoyo al PNSU) Selection 3.4.35-CI-8899 / Individual General Project Coordinador 03 de Proyecto IBRD / 88990 Post Consultant Limited 50,000.00 36,455.71 Signed 2019-09-15 2019-10-11 2019-09-20 2019-10-11 2019-10-11 2019-10-14 2019-11-15 2019-10-18 2020-12-31 Administration (apoyo al PNSU) Selection 3.4.50-CI-8899 / Individual General Project Especialista Social IBRD / 88990 Post Consultant Limited 173,333.00 32,347.38 Signed 2019-08-12 2019-09-03 2019-08-17 2019-10-14 2019-09-07 2019-10-28 2019-10-12 2019-10-28 2023-12-31 Administration (apoyo al PNSU) Selection 3.4.51-CI-8899 / Individual General Project Especialista Ambiental IBRD / 88990 Post Consultant Limited 173,333.00 32,347.38 Signed 2019-08-12 2019-09-03 2019-08-17 2019-10-28 2019-09-07 2019-11-05 2019-10-12 2019-11-05 2023-12-31 Administration (apoyo al PNSU) Selection 3.4.52-CI-8899 / Individual Especialista en proyectos de General Project IBRD / 88990 Post Consultant Limited 133,333.00 9,025.83 Signed 2019-08-12 2019-11-07 2019-08-17 2019-12-13 2019-09-07 2019-12-26 2019-10-12 2020-01-02 2022-12-31 inversión Administration Selection (apoyo al PNSU) 3.4.57-CI-8899 / Individual Especialista en Saneamiento General Project IBRD / 88990 Post Consultant Limited 121,212.00 26,707.96 Signed 2019-08-12 2019-11-26 2019-08-17 2019-12-11 2019-09-07 2019-12-16 2019-10-12 2019-12-16 2022-12-31 Fisico Legal Administration Selection (apoyo al PNSU) 3.4.36-CI-8899 / Improving Governance of Individual COORDINADOR DE IBRD / 88990 Water Supply and Sanitation Post Consultant Limited 90,000.00 32,599.11 Signed 2019-10-10 2019-10-09 2019-10-15 2019-11-18 2019-11-05 2019-11-26 2019-12-10 2019-11-26 2020-06-07 PROYECTOS 2 - SEDACUSCO Service Providers Selection UIC2 PE-OTASS-144409-CS-INDV Individual General Project / Especialista en IBRD / 88990 Post Consultant Limited 216,363.00 57,120.96 Completed 2019-10-01 2019-09-24 2019-10-06 2019-09-26 2019-10-27 2019-10-03 2019-12-01 2019-10-07 2020-05-29 2020-10-27 Administration Adquisiciones UE003 Selection CONS IND 3.4.24 / Individual ESPECIALISTA EN General Project IBRD / 88990 Post Consultant Limited 174,242.00 6,697.76 Signed 2020-02-20 2020-10-23 2020-02-21 2020-11-05 2020-02-26 2020-11-06 2020-02-28 2020-11-09 2023-12-31 PLANEAMIENTO Y Administration Selection PRESUPUESTO DE LA UE 003 1.2.7.2 ARQUITECTURA DE SISTEMAS / Consultoria Improving Governance of Individual Individual Diagnostico de IBRD / 88990 Water Supply and Sanitation Post Consultant Limited 6,666.67 6,066.46 Signed 2020-03-04 2020-06-16 2020-03-06 2020-07-15 2020-03-10 2020-08-20 2020-03-16 2020-08-20 2020-05-15 procesos de evaluación de Service Providers Selection expedientes técnicos - Arquitectura de Sistemas 1.2.7.1 ARQUITECTURA DE PROCESOS / Consultoria Improving Governance of Individual Diagnostico de procesos de IBRD / 88990 Water Supply and Sanitation Post Consultant Limited 6,666.67 6,066.46 Signed 2020-03-04 2020-06-04 2020-03-06 2020-07-29 2020-03-10 2020-08-17 2020-03-16 2020-09-18 2020-05-15 evaluación de expedientes Service Providers Selection técnicos - Arquitectura de Procesos 3.4.27 ESPECIALISTA EN Individual PLANEAMIENTO UIC2 / General Project IBRD / 88990 Post Consultant Limited 150,000.00 8,002.63 Signed 2020-03-04 2020-03-09 2020-03-06 2021-03-29 2020-03-10 2021-03-31 2020-03-16 2021-04-05 2023-12-31 ESPECIALISTA EN Administration Selection PLANEAMIENTO UIC 2 3.4.4 PROFESIONAL EN Individual ADQUISICIONES / General Project IBRD / 88990 Post Consultant Limited 136,363.64 0.00 Canceled 2020-03-13 2020-03-16 2020-03-24 2020-03-31 2023-12-31 PROFESIONAL EN Administration Selection ADQUISICIONES UE 003 CONS IND 1.1.7.5 METOD DE INDICADORES / Contratación de servicio de consul individ para la elaboración de un instrumento de planificación Improving Governance of Individual asociado a la metodología e IBRD / 88990 Water Supply and Sanitation Post Consultant Limited 11,363.64 0.00 Canceled 2020-04-15 2020-04-18 2020-04-20 2020-04-27 2020-04-30 2020-07-31 indicadores de los criterios Service Providers Selection para el cofinanciamiento de los costos de operación y mantenimiento de proyectos APP de Saneamiento Page 5 CONS IND 1.1.7.6 PROYECTOS APP / Contratación de servicio de consultoría individual para la Improving Governance of Individual elaboración de una propuesta IBRD / 88990 Water Supply and Sanitation Post Consultant Limited 5,454.55 0.00 Canceled 2020-04-15 2020-04-18 2020-04-20 2020-04-27 2020-04-30 2020-06-30 de instrumento de Service Providers Selection planificación de los proyectos en Asociaciones Público Privadas del Sector Saneamiento CONS IND 1.1.7.7 ING. SANIT CHINCHA-CUS / Contratación de servicio de consultoría Improving Governance of Individual individual para la evaluación IBRD / 88990 Water Supply and Sanitation Post Consultant Limited 10,909.09 0.00 Canceled 2020-04-15 2020-04-18 2020-04-20 2020-04-27 2020-04-30 2020-07-31 de aspectos de ingeniería Service Providers Selection sanitaria de los proyectos APP PTAR Chincha y PTAR Cusco CONS IND 1.1.7.8 ING. SANITARIA TARAPOTO / Contratación de servicio de Improving Governance of Individual consultoría individual para la IBRD / 88990 Water Supply and Sanitation Post Consultant Limited 10,909.09 0.00 Canceled 2020-04-15 2020-04-18 2020-04-20 2020-04-27 2020-04-30 2020-07-31 evaluación de aspectos de Service Providers Selection ingeniería sanitaria de los proyectos APP PTAR Tarapoto y PTAR Cajamarca CONS IND 1.1.7.9 GEOTECNIA, SUELOS Y TOP / Contratación de servicio de consultoría individual para la Improving Governance of Individual evaluación de aspectos de IBRD / 88990 Water Supply and Sanitation Post Consultant Limited 10,909.09 0.00 Canceled 2020-04-15 2020-04-18 2020-04-20 2020-04-27 2020-04-30 2020-07-31 geotecnia, mecánica de suelos Service Providers Selection y topografía de los proyectos APP PTAR Chincha, PTAR Tarapoto, PTAR Cusco y PTAR Cajamarca CONS IND 1.1.7.10 INTERFERENCIAS / Contratación de servicio de consultoría individual para la Improving Governance of Individual evaluación de los aspectos de IBRD / 88990 Water Supply and Sanitation Post Consultant Limited 10,909.09 0.00 Canceled 2020-04-15 2020-04-18 2020-04-20 2020-04-27 2020-04-30 2020-07-31 interferencias y estudio de Service Providers Selection canteras de los proyectos APP PTAR Chincha, PTAR Tarapoto, PTAR Cusco y PTAR Cajamarca CONS IND 1.1.7.11 ANALISIS DE RIESGO / Contratación de servicio de consultoría individual para la evaluación de los aspectos de análisis de Improving Governance of Individual riesgos referido a la IBRD / 88990 Water Supply and Sanitation Post Consultant Limited 10,909.09 0.00 Canceled 2020-04-15 2020-04-18 2020-04-20 2020-04-27 2020-04-30 2020-07-31 integridad física y/o Service Providers Selection estructural de la infraestructura de los proyectos APP PTAR Chincha, PTAR Cusco, PTARTarapoto y PTAR Cajamarca CONS IND 1.1.7.12 GESTIÓN SOCIAL / Contratación de servicio de consultoría Improving Governance of Individual individual para la gestión IBRD / 88990 Water Supply and Sanitation Post Consultant Limited 9,090.91 0.00 Canceled 2020-04-15 2020-04-18 2020-04-20 2020-04-27 2020-04-30 2020-07-31 social para obtener la Service Providers Selection aceptación social de los proyectos APP PTAR Chincha, PTAR Tarapoto y PTAR Cusco CONS IND 1.1.7.13 GESTIÓN DE PROYECTOS / Contratación de servicio de consultoría Improving Governance of Individual individual para la gestión IBRD / 88990 Water Supply and Sanitation Post Consultant Limited 9,090.91 0.00 Canceled 2020-04-15 2020-04-18 2020-04-20 2020-04-27 2020-04-30 2020-07-31 oportuna de los proyectos APP Service Providers Selection y articulación con los gobiernos subnacionales CONS IND 1.2.3.1 ESTRATEGIA DE COMUNICAC / Improving Governance of Individual Elaboración de la Estrategia IBRD / 88990 Water Supply and Sanitation Post Consultant Limited 7,878.79 0.00 Canceled 2020-04-24 2020-04-29 2020-05-08 2020-05-13 2020-07-13 de Comunicación del Service Providers Selection ¨Programa de Modernización SD 1.2.3.4 DISEÑO E IMPLEMENT-CORNAVI / Diseño e Implementación de Improving Governance of Individual Campana de Valorización del IBRD / 88990 Water Supply and Sanitation Post Consultant Direct 13,939.39 13,579.14 Signed 2020-04-15 2020-04-16 2020-04-16 2020-04-21 2020-04-17 2020-04-22 2020-04-17 2020-04-22 2020-07-31 Servicio de Agua y Service Providers Selection Saneamiento Brindado por las EPS a Nivel Nacional en Tiempos de Coronavirus SD 1.2.3.4 CREATIVO Y PRODUCCIÓN / Diseno Creativo y Producción de Improving Governance of Individual Materiales de la Campana IBRD / 88990 Water Supply and Sanitation Post Consultant Direct 12,909.09 12,575.46 Signed 2020-04-15 2020-04-16 2020-04-16 2020-04-21 2020-04-17 2020-04-22 2020-04-17 2020-04-22 2020-05-30 Valorización del Servicio de Service Providers Selection Agua y Saneamiento Brindado por las EPS a Nivel Nacional en Tiempos de Coronavirus CONS IND 1.3.2.4 ESTRATEGIA COMUNICACIO / Consultoria para el Improving Governance of Individual Diagnóstico y el Inventario de IBRD / 88990 Water Supply and Sanitation Post Consultant Limited 15,151.52 0.00 Canceled 2020-05-04 2020-05-08 2020-05-18 2020-05-25 2020-07-27 los equipos que soportan los Service Providers Selection sistemas administrativos y gerenciales de las EPS CONS IND 1.3.4.5.DIAGNOSTICO E INVENTARI / Consultoria para Improving Governance of Individual el Diagnóstico y el Inventario IBRD / 88990 Water Supply and Sanitation Post Consultant Limited 15,151.52 0.00 Canceled 2020-05-04 2020-05-08 2020-05-15 2020-05-20 2020-07-21 de los equipos que soportan Service Providers Selection los sistemas comerciales de las EPS Page 6 SD 1.3.1.1 DETERMINACION ALCANCE EPS / SERVICIO DE CONSULTORIA PARA LA DETERMINACIÓN DEL ALCANCE Y CONTENIDO DEL PLAN DE ACCIONES DE Improving Governance of Individual URGENCIA Y DEL PLAN DE IBRD / 88990 Water Supply and Sanitation Post Consultant Direct 10,000.00 9,598.46 Signed 2020-05-13 2020-05-15 2020-05-14 2020-05-15 2020-05-15 2020-05-15 2020-05-18 2020-05-15 2020-06-18 REFLOTAMIENTO DE LAS Service Providers Selection EMPRESAS PRESTADORAS DE SERVICIOS DE SANEAMIENTO DE ACCIONARIADO MUNICIPAL INCORPORADAS AL RÉGIMEN DE APOYO TRANSITOR CONS IND 1.2.1.1 / CONTRATACIÓN DE Improving Governance of Individual CONSULTORIA INDIVIDIAL Under IBRD / 88990 Water Supply and Sanitation Post Consultant Limited 182,424.24 0.00 2020-06-03 2020-06-08 2020-06-12 2020-06-19 2023-12-30 SUPERVISION DE PROYECTOS Implementation Service Providers Selection DEL COMPONENTE 2 DEL PROGRAMA SD 1.2.3.2 SEGUIMIENTO ESTRATEGIA / SERVICIO PARA EL SEGUMIENTO A LA Improving Governance of Individual IMPLEMENTACIÓN DE IBRD / 88990 Water Supply and Sanitation Post Consultant Direct 4,848.48 0.00 Canceled 2020-06-15 2020-06-17 2020-06-16 2020-06-17 2020-06-18 2020-08-17 ACCIONES PREVIAS DE LA Service Providers Selection ESTRATEGIA DE COMUNICACIONES SD N° 1.3.4.3 Improving Governance of Individual SISTEMATIZACION / IBRD / 88990 Water Supply and Sanitation Post Consultant Direct 3,030.30 0.00 Canceled 2020-06-22 2020-06-23 2020-06-24 2020-06-25 2020-07-24 SISTEMATIZACION DEL PRIMER Service Providers Selection ENCUENTRO AGUAS TODAS SD 1.2.3.6 PG WEB MIGRACION A PLATAFORMA / CONTRACION DEL SERVICIO DE CONSULTORIA PARA LA Improving Governance of Individual IMPLEMENTACION DE LA IBRD / 88990 Water Supply and Sanitation Post Consultant Direct 6,060.61 5,553.94 Signed 2020-08-10 2020-10-13 2020-08-17 2020-10-19 2020-08-19 2020-10-30 2020-08-20 2020-10-30 2020-10-08 PAGINA WEB INSTITUSIONAL Service Providers Selection Y MIGRACIÓN A LA PLATAFORMA ÚNICA DIGITAL GOB.PE DE UE 003 CI 1.2.3.2 ESP EN COMUNICACIONES / CONSULTORIA INDIVIDUAL PARA EL SERVICIO DE UN Improving Governance of Individual ESPECIALISTA EN IBRD / 88990 Water Supply and Sanitation Post Consultant Limited 8,181.82 0.00 Canceled 2020-08-10 2020-08-17 2020-08-20 2020-08-24 2020-11-23 COMUNICACIONES PARA EL Service Providers Selection DSARROLLO DE LAS ACCIONES DE PROMOCIÓN Y DIFUSIÓN DE LA ESTRATEGIA DE COMUNICACIONES CONS IND 1.1.7 / CONSULTORIA ASESORIA EN Improving Governance of Individual LA ESTANDARIZACION DE IBRD / 88990 Water Supply and Sanitation Post Consultant Limited 9,090.91 8,272.44 Signed 2020-08-17 2020-08-04 2020-08-25 2020-08-20 2020-08-31 2020-08-25 2020-09-04 2020-08-28 2020-11-03 CONTENIDOS DE Service Providers Selection PLANTEAMIENTO TÉCNICO DE LOS PROYECTOS DE APP CI 1.2.2.1.1 / Servicio de consultora individual, para la revision,evaluacion, analisis y diagnostico de la Improving Governance of Individual normatividad y jurisprudencia IBRD / 88990 Water Supply and Sanitation Post Consultant Direct 7,272.73 6,617.95 Signed 2020-09-07 2020-09-24 2020-09-10 2020-10-05 2020-09-11 2020-10-06 2020-09-15 2020-10-12 2020-11-04 vigentes y aplicables a las EPS Service Providers Selection municipales, para el diseño e implementacion de un sistema salarial integral. CI 1.2.2.1.2 / Serv. C.I.. para la revision,evaluacion, analisis y diagnostico de la normatividad y jurisprudencia Improving Governance of Individual vigentes y aplicables a las EPS IBRD / 88990 Water Supply and Sanitation Post Consultant Direct 7,272.73 0.00 Canceled 2020-09-07 2020-11-12 2020-09-10 2020-09-11 2020-09-15 2020-11-04 municipales, diseño e Service Providers Selection implementacion del sistema de evaluacion de rendimiento, plan de desarrollo y linea de carrera CI 1.2.2.1.3 / Serv CI revision,evaluacion, analisis y diagnostico de los convenios colectivos, suscritos por las Improving Governance of Individual 18 EPS en RAT y 01 UE Agua IBRD / 88990 Water Supply and Sanitation Post Consultant Direct 7,272.73 6,617.95 Signed 2020-09-07 2020-09-24 2020-09-10 2020-10-05 2020-09-11 2020-10-08 2020-09-15 2020-10-12 2020-11-14 Tumbes y la problemática y Service Providers Selection obstaculos que influyen en la definicion de un sistema salarial integral CI 3.4.15 ESP 3 COMP 1 / Individual Contratacion de Especialista General Project IBRD / 88990 Post Consultant Limited 147,727.27 8,625.21 Signed 2020-09-07 2020-09-26 2020-09-14 2020-10-05 2020-09-18 2020-10-12 2020-09-22 2020-10-15 2023-12-31 Técnico 03 DEL COMPONENTE Administration Selection 1 CI 3.4.14 ESP 2 COMP 1 / Individual CONTRATACIÓN DE General Project IBRD / 88990 Post Consultant Limited 147,727.27 7,558.74 Signed 2020-09-15 2020-09-26 2020-09-22 2020-10-21 2020-09-28 2020-10-22 2020-09-30 2020-10-26 2023-12-31 ESPECIALISTA TÉCNICO 02 Administration Selection DEL COMPONENTE 1 Individual CI 3.4.58 COMUNICACIONES General Project IBRD / 88990 Post Consultant Limited 94,545.45 2,205.98 Signed 2020-09-21 2020-09-24 2020-09-24 2020-10-02 2020-09-28 2020-10-08 2020-09-30 2020-10-12 2023-12-31 / ESP EN COMUNICACIONES Administration Selection PE-OTASS-213910-CS-INDV Individual / Especialista en General Project IBRD / 88990 Post Consultant Limited 136,000.00 13,388.49 Signed 2021-02-01 2021-02-05 2021-02-10 2021-02-23 2021-02-22 2021-02-24 2021-03-01 2021-03-02 2022-02-28 adquisiciones - Jefe área de Administration Selection adquisiciones PE-OTASS-213911-CS-INDV Individual General Project / Especialista en Contabilidad IBRD / 88990 Post Consultant Limited 136,000.00 9,730.15 Signed 2021-02-01 2021-02-12 2021-02-08 2021-03-15 2021-02-15 2021-03-29 2021-03-01 2021-03-31 2022-02-28 Administration - Jefe del Área de Selection Contabilidad Page 7 PE-OTASS-213919-CS-INDV Individual / Especialista en Planeamiento General Project IBRD / 88990 Post Consultant Limited 136,000.00 9,942.97 Signed 2021-02-01 2021-01-21 2021-02-06 2021-03-16 2021-02-23 2021-03-29 2021-03-01 2021-04-07 2022-02-28 y Presupuesto - Jefe Área de Administration Selection Planeamiento y Presupuesto PE-OTASS-213923-CS-INDV Individual / Director de la Unidad General Project IBRD / 88990 Prior Consultant Limited 310,909.00 60,232.72 Signed 2021-02-01 2021-01-21 2021-02-05 2021-01-27 2021-02-15 2021-02-02 2021-03-01 2021-02-02 2022-02-28 Ejecutora del Programa Administration Selection (UE003) PE-OTASS-218456-CS-INDV Individual / Especialista en Monitoreo y General Project IBRD / 88990 Post Consultant Limited 159,696.97 4,238.97 Signed 2021-03-01 2021-02-12 2021-03-06 2021-02-18 2021-03-27 2021-02-22 2021-05-01 2021-02-27 2023-12-31 Evaluación (Jefe Área de Administration Selection Monitoreo y Evaluación) PE-OTASS-220816-CS-INDV Individual General Project / Especialista GIS en IBRD / 88990 Post Consultant Limited 6,794.57 7,155.45 Signed 2021-03-15 2021-03-09 2021-03-20 2021-03-31 2021-04-04 2021-04-12 2021-05-04 2021-04-21 2021-07-18 Administration Fotogrametria Selection Improving and Expanding PE-OTASS-220824-CS-INDV Individual Water Supply and Sanitation / Especialista GIS en Modelo IBRD / 88990 Post Consultant Limited 7,360.14 7,430.55 Signed 2021-03-15 2021-03-09 2021-03-20 2021-04-05 2021-04-04 2021-04-12 2021-05-10 2021-04-21 2021-07-24 Services in the Participating Digital de Terreno Selection EPS Improving and Expanding PE-OTASS-220828-CS-INDV Individual Water Supply and Sanitation / Analista GIS en Sistema de IBRD / 88990 Post Consultant Limited 6,340.58 6,677.35 Signed 2021-03-15 2021-03-09 2021-03-20 2021-03-26 2021-04-04 2021-04-12 2021-05-10 2021-04-21 2021-05-17 Services in the Participating Agua Potable Selection EPS Improving and Expanding PE-OTASS-220830-CS-INDV Individual Water Supply and Sanitation / Especialista GIS en Sistemas IBRD / 88990 Post Consultant Limited 6,190.94 6,250.16 Signed 2021-03-15 2021-03-09 2021-03-20 2021-04-05 2021-04-04 2021-04-12 2021-05-10 2021-04-21 2021-05-17 Services in the Participating de Alcantarillado Selection EPS Improving and Expanding Individual PE-OTASS-220832-CS-INDV Water Supply and Sanitation IBRD / 88990 Post Consultant Limited 6,431.88 6,493.41 Signed 2021-03-15 2021-03-18 2021-03-20 2021-04-05 2021-04-04 2021-04-12 2021-05-10 2021-04-21 2021-07-24 / Analista BIM en Arquitectura Services in the Participating Selection EPS Improving and Expanding Individual PE-OTASS-220834-CS-INDV Water Supply and Sanitation IBRD / 88990 Post Consultant Limited 6,892.21 6,951.73 Signed 2021-03-15 2021-03-18 2021-03-20 2021-04-05 2021-04-04 2021-04-12 2021-05-10 2021-04-21 2021-07-24 / Analista BIM en Sanitaria Services in the Participating Selection EPS Improving and Expanding PE-OTASS-220835-CS-INDV Individual Water Supply and Sanitation / Especialista GIS en Sistema IBRD / 88990 Post Consultant Limited 6,018.48 6,076.05 Signed 2021-03-15 2021-03-09 2021-03-20 2021-04-05 2021-04-04 2021-04-12 2021-05-10 2021-04-21 2021-07-24 Services in the Participating Comercial Selection EPS PE-OTASS-224959-CS-INDV Individual General Project Under / Especialista técnico 04 del IBRD / 88990 Post Consultant Open 123,134.32 0.00 2021-04-01 2021-04-06 2021-05-05 2021-05-26 2021-06-30 2021-12-27 Administration Implementation componente 1 Selection PE-OTASS-224960-CS-INDV Individual / Especialista en supervisión General Project IBRD / 88990 Post Consultant Open 123,134.32 5,761.11 Signed 2021-04-01 2021-03-12 2021-05-05 2021-04-26 2021-05-26 2021-04-28 2021-06-30 2021-05-06 2021-12-27 en actividades y proyectos del Administration Selection programa PE-OTASS-224962-CS-INDV Individual General Project / Profesional en IBRD / 88990 Post Consultant Open 78,805.97 3,081.23 Signed 2021-04-01 2021-03-12 2021-04-21 2021-04-26 2021-05-12 2021-04-27 2021-06-16 2021-05-03 2021-12-13 Administration comunicaciones Selection PE-OTASS-225692-CS-INDV / Generación de capacidades Improving Governance of Individual Under de planificación, articulación y IBRD / 88990 Water Supply and Sanitation Post Consultant Limited 9,571.42 0.00 2021-03-22 2021-04-05 2021-03-27 2021-04-17 2021-05-22 2021-11-18 Implementation seguimiento del sector Service Providers Selection saneamiento en el MVCS Individual PE-OTASS-229598-CS-INDV General Project IBRD / 88990 Post Consultant Limited 136,363.64 18,059.42 Signed 2021-05-03 2021-04-29 2021-05-06 2021-05-19 2021-05-14 2021-05-27 2021-06-07 2021-05-28 2025-02-19 / Profesional en Adquisiciones Administration Selection PE-OTASS-229754-CS-INDV Individual General Project / Coordinador administrativo IBRD / 88990 Post Consultant Open 200,000.00 26,840.93 Signed 2021-05-03 2021-04-29 2021-06-21 2021-05-21 2021-07-12 2021-05-24 2021-08-16 2021-05-31 2022-02-12 Administration del Componente 3 Selection PE-OTASS-235401-CS-INDV / Elaboración de propuesta Improving Governance of Individual Under para la actualización de la IBRD / 88990 Water Supply and Sanitation Post Consultant Limited 26,971.00 0.00 2021-05-24 2021-05-31 2021-05-29 2021-06-19 2021-07-24 2022-01-20 Implementation Política Nacional de Service Providers Selection Saneamiento (PNS). PE-OTASS-235831-CS-INDV Individual / COORDINADOR DE General Project Under IBRD / 88990 Post Consultant Limited 60,789.00 0.00 2021-05-24 2021-06-16 2021-05-29 2021-06-19 2021-07-24 2022-01-20 PROYECTOS 1 PARA EL Administration Implementation Selection AMBITO DE LA EPS SEDAPAR PE-OTASS-234106-CS-INDV Individual General Project / Especialista en IBRD / 88990 Post Consultant Open 104,729.73 0.00 Canceled 2021-05-17 2021-05-13 2021-07-05 2021-07-26 2021-08-30 2022-02-26 Administration Adquisiciones Componente 3 Selection PE-OTASS-234106-CS-INDV- Individual General Project 2 / Especialista en IBRD / 88990 Prior Consultant Open 104,729.73 0.00 Under Review 2021-06-04 2021-06-09 2021-07-23 2021-08-13 2021-09-17 2022-03-16 Administration Adquisiciones Componente 3 Selection PE-OTASS-238337-CS-CDS / Individual General Project Under Especialista de Contabilidad: IBRD / 88990 Post Consultant Open 99,000.00 0.00 2021-06-30 2021-06-18 2021-08-18 2021-09-08 2021-10-13 2022-04-11 Administration Implementation Jefe del Área de Contabilidad Selection PE-OTASS-238821-CS-INDV Improving Governance of Individual Under / Implementación Sistema de IBRD / 88990 Water Supply and Sanitation Post Consultant Open 12,631.00 0.00 2021-06-30 2021-06-16 2021-08-18 2021-09-08 2021-10-13 2022-04-11 Implementation evaluación de rendimiento Service Providers Selection PE-OTASS-238825-CS-INDV Improving Governance of Individual / Implementación de un IBRD / 88990 Water Supply and Sanitation Post Consultant Open 12,631.00 0.00 Under Review 2021-06-30 2021-06-16 2021-08-18 2021-09-08 2021-10-13 2022-04-11 Sistema Salarial Integral Service Providers Selection Page 8 PROCUREMENT PLAN (Textual Part) Project information: China: Green Urban Financing and Innovation Project Project Implementation agency: Shanghai Chengtou Financial Service Company Date of the Procurement Plan: Apr. 2019 Period covered by this Procurement Plan: Apr. 2019 till Jun. 2021 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016, Revised November 2017 and August 2018) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. A. The Bank’s Standard Procurement Documents (SPDs): The Bank’s SPDs shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. B. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures (Tendering and Bidding Law of the Peoples’ Republic of China, i.e. TBL promulgated by its Order No. 21 dated August 30, 1999 and the Implementation Regulations of the TBL promulgated by its State Council Order No. 613 dated November 30, 2011 and any amendments thereof) may be used with the following conditions to meet the requirements for open competitive procurement of paragraph 5.4 of the Procurement Regulations: a) All procurement notices shall be published in a national newspaper of wide circulation, or on a widely-used website / electronic portal with free access. b) A minimum of twenty (20) business days shall be given to Bidders between the date of such advertisement (or the date of availability of procurement documents, whichever is later and the deadline for the submission of bids). The advertisement and procurement documents shall specify the deadline for the submission of bids. Potential Bidders shall be allowed to inspect and purchase procurement documents at any time prior to the deadline for the submission of bids. c) Any Bidder/Consultant should be eligible to participate in a procurement process and to be awarded a Bank-financed contract as defined in paragraphs 3.21, 3.22 and 3.23 of the Procurement Regulations. d) Bidders/Consultants shall be allowed to submit bids/proposals by mail or in person. Bidders/consultants shall not be mandatory required to be present at the bid/proposal opening session. e) Bidders should not be required to register as a condition for inspecting or purchasing procurement documents, submitting its bid or receiving contract award. A winner Bidder, shall be given reasonable opportunity of registering (if required) before contract signing without any let or hindrance. Bidding shall not be restricted to any class of contractors. f) The winning bidder shall not be required, as a condition of award, to reduce its bid price No contract negotiation shall be permitted unless agreed in the procurement plan. g) No bid may be rejected solely on the basis that the bid price exceeds any cost estimate. Rejection of all bids or re-bidding shall not be allowed solely because the number of bids is less than three (3). Rebidding shall not take place without any sound justification. h) The Bank’s procurement documents for approaching the national market or any procurement document acceptable to the Bank shall be used. All procurement documents must require that bidders/consultants present a signed acceptance at the time of bidding or submitting a proposal, to be incorporated in any resulting contract, confirming application of and compliance with the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. i) The procurement documents shall disclose the newspaper and / or the electronic means in which the information on contract award shall be published. j) The contract award notification shall identify: (a) name and address of the Borrower’s Project Implementing Unit, (b) name and reference number of the contract being awarded and the selection method used (c) names of all Bidders/Consultants that submitted bids/proposals and their prices as read out at the bid opening meeting and as evaluated (d) names of all Bidders/ Consultants whose bids/proposals were rejected either as nonresponsive or as not meeting qualification criteria or were not evaluated, with the reasons therefor and (e) the name of the successful Bidder/Consultant, the final contract price, the contract duration and a summary of its scope. i) The Borrower shall implement an effective complaint mechanism allowing bidders or consultants to complain, and have their complaints handled and responded in a timely manner. Procurement documents should indicate the complaint mechanism procedure and provide the professional title and address of the officials to whom such protests should be sent. j) The Bank shall be allowed to review procurement documentation and activities related to the activities included in the procurement plan. C. Other national procurement arrangements: When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. D. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. E. Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations is not applicable: F. Domestic Preference as specified under paragraph 5.51 of the Procurement Regulations: Goods: Domestic Preference is applicable for those contracts identified in the Procurement Plan tables. Works: Domestic Preference is not applicable G. Other Relevant Procurement Information:.                              2019-2021   -                 Procurement Plan for Component 3 Institutional Strengthening and Project Management (2019-2021) Green Urban Financing and Innovation Project  Awarded Contracts financed with WB loan  上上上上 Updated on上May11, 2021                             Contra         Implementa Updated Procure    ct    Service No. tion Estimated ment WB Term Notes Content Method Cost Method Review (month s) 上上上上上上上上上上上上上上 上上上上上上上上上上上上上上 2020 上 上上上 A 6 上 1 上上 Green Urban 2025 上 Financing & 上上上上 上上 6 上 30 上 IDP2.3 $250,000.0 Innovation Consulting CQS Post June 1, . A 0 Project- service review 2020 - Environmental June Management 30, Consulting 2025 Service Contract 上上上上上上上上上上上上上上 2020 上 上上上上上上上上上上上上上 B 11 上 1 上 Green Urban 上 2025 Financing & 上 6 上 30 Innovation 上上上上 上上 上 IDP2.3 $250,000.0 Project- Consulting CQS Post Novemb B 0 Environmental service review er 1, Management 2020 - Consulting June Service Contract 30, B 2025 上上上上上上上上上上上上上上 上上上上上上上上上上上上上 A 2020 上 Green Urban 7 上 1 上上 Financing & 2025 上 上上上上 上上 IDP2.4 Innovation $300,000.0 6 上 30 上 Consulting CQS Post A Project- Social 0 July 1, service review Management 2020 - Consulting June 30, Service Contract 2025 A 2020 上 上上上上上上上上上上上上上上 11 上 1 上 上上上上上上上上上 B 上 2025 Green Urban 上 6 上 30 Financing & 上上上上 上上 上 IDP2.4 Innovation $200,000.0 Consulting CQS Post Novemb B Project- Social 0 service review er 1, Management 2020 - Consulting June Service Contract 30, B 2025 2019 上 6 上 7 上上 上上上上上上上上上上上上 2020 上 Legal Advisor 上上上上 上上 $200,000.0 6上6上 IDP2.5 Consulting Consulting CQS Post 0 June 7, Service Contract service review 2019 - (signed in 2019) June 6, 2020            Total 上上上上上1USD=6.5RMB yuan (上上 2021 上 5 上 6 上上上上上上上上上上上上上1 上上上上上上 6.4895 上上 Exchange rate: quoted in calculation: 1 USD = 6.5 RMB yuan (referred exchange rate announced by People's Bank of China: 1 USD = 6.4895 RMB yuan) PROCUREMENT China : Green Urban Financing and Innovation Project PLAN General Information Country: China Bank’s Approval Date of the Original Procurement Plan: 2021-05-24 2021-05-24 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P158124 GPN Date: 2021-05-18 Project Name: Green Urban Financing and Innovation Project Loan / Credit No: IBRD / 89590 S Executing Agency(ies): hanghai Green Urban Financing and Services Co., Ltd. WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IDP2.3A / GUFIP- Consultant Institutional Strengthening Environmental Management IBRD / 89590 Post Qualification Limited 250,000.00 47,589.60 Signed 2021-05-28 2019-10-11 2021-06-11 2020-06-17 2021-07-11 2020-12-04 2021-08-15 2020-12-17 2025-06-30 and Project Management Consulting Service Contract A Selection IDP2.3B / GUFIP- Consultant Institutional Strengthening Environmental Management IBRD / 89590 Post Qualification Limited 250,000.00 47,746.15 Signed 2021-05-31 2019-10-11 2021-06-14 2020-06-17 2021-07-14 2020-12-04 2021-08-18 2020-12-17 2025-06-30 and Project Management Consulting Service Contract B Selection IDP2.4A / GUFIP-Social Consultant Institutional Strengthening Management Consulting IBRD / 89590 Post Qualification Limited 300,000.00 93,770.30 Signed 2021-05-31 2020-05-27 2021-06-14 2020-06-17 2021-07-14 2020-12-17 2021-08-18 2020-12-17 2025-06-30 and Project Management Service Contract A Selection IDP2.4B / GUFIP-Social Consultant Institutional Strengthening Management Consulting IBRD / 89590 Post Qualification Limited 200,000.00 42,267.08 Signed 2021-05-31 2020-05-27 2021-06-14 2020-06-17 2021-07-14 2021-01-15 2021-08-18 2021-01-21 2025-06-30 and Project Management Service Contract B Selection Consultant IDP2.5 / Legal Advisor Institutional Strengthening IBRD / 89590 Post Qualification Limited 200,000.00 50,094.32 Signed 2021-05-31 2019-04-28 2021-06-14 2019-05-16 2021-07-14 2019-08-01 2021-08-18 2019-08-01 2025-06-30 Consulting Service Contract and Project Management Selection INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 1 Years from April 2015 to July 2019 PMU Submit to IDA for NO: Supplier/Contractor/Consu PMU Finalize Shortlist, TS, Bidding Doc/Invitation to Bidding Doc/Invitation to Doc/Invitation to Quote Shortlist, TS, TOR, RF, Shortlist, TS, TOR, RF, Contract signing date Procurement Method Delivery/ completion Aprooved date for SPN Date (Tender Bid Opening date Contract amount Prior/Post review TOR, RF, Bidding Package IFB Nr. Techn/Financial Invitation Date) Starting year Latest Date ('000US$) Category Quote Quote ltant Description Vehicles for 1 MSTs,Secretariat,Value Chain Secretariat, PIU 201 2-Apr- 22-Apr- 30-Apr- 26- 29- Global Motors Contra CARMAC2-PG-15-01/1 G NCB Prior 2-Apr-15 4-Jun-15 84.87 5 15 15 15 Jun-15 Jun-15 CJSC 12- 14-Jul- Contra CARMAC2-PG-15-01/2 15 Sep- 98.74 Vekar LLC 15 Special Vehicles for VCS (Vet 201 13-Oct- 13-Oct- 13-Nov- 2 Service Centers, 1 vehicle) G NCB*** Post 5 1-Oct-15 15 15 15 Special Vehicles for VCS (Vet 17- 201 23-Dec- 1-Feb- 8-Mar- Service Centers, 1 vehicle) Contra G NCB Post 2-Dec-15 3-Dec-15 Feb- 14.84 Megna LLC 5 15 16 16 16 CARMAC2-PG-16-09 Servers for SSFS 201 15-Jul- 6-Aug- 7-Sep- 9-Nov- 8-Mar- Doxx Computers 2A Contra CARMAC2-PG-15-06 G NCB Post 5 27-Jul-15 15 4-Aug-15 15 15 15 16 124.16 LLC Special Vehicles for SSFS CVFS&P (State Service for Food Safety and 18- 201 9-Aug- 17- 3 Centre Veterinary, Food G SH Post 6 28-Jul-16 28-Jul-16 28-Jul-16 16 Aug- Oct-16 91.13 Galoper LLC Safety&Phytosanitary) Contra 16 CARMAC2-PG-16-12 Special Vehicles for VCS (Vet 201 4 Service Centers, 4 vehicles) G NCB Post 7 IT Equipment for 201 5 Secretariat,Value Chain G SH Post 6 Secretariat, PIU 13- 22- IT Equipment for MSTs Contra 201 14-May- 22-May- 24-Jul- 5A CARMAC2-PG-15-02 G SH Prior 5 12-May-15 May- 15 15 9-Jun-15 15 Sep- 11.56 Dolphin LLC 15 15 23- IT Equipment for PIU Contra 201 10-May- 17-May- 23-Jul- Doxx Computers 5B CARMAC2-PG-16-10 G SH Post 6 16 16 May- 16 6.03 LLC 16 Information Dissemination 201 6 (leaflets,sign-boards, etc) G SH Post 5 TBD Contra CARMAC2-PG-15-04 201 9-Jun- 9-Aug- 6A (Booklet) G SH Post 5 1-Jun-15 1-Jun-15 8-Jun-15 15 15 0.33 Uniprint LLC Contra CARMAC2-PG-16-11 201 10-Jun- 13- 23- 6B (Register) G SH Post 6 1-Jun-16 3-Jun-16 16 Jun-16 Jun-16 0.53 Uniprint LLC 201 7 Office furniture for PIU and MSTs G SH Post 5 TBD Contra CARMAC2-PG-15-03 201 29-May- 11- 11-Jul- 7A (Furniture) for MTS G SH Post 5 29-May-15 15 8-Jun-15 Jun-15 15 3.56 PE H.Avetisyan 25- Contra CARMAC2-PG-15-08 201 10-Nov- 17-Nov- 24- G SH Post 29-May-15 Nov- 4.05 PE H.Avetisyan (Furniture) for APIU 5 15 15 15 Jan-16 Commun. Vets equipment and 201 8 consumables G SH Post 6 Equipment and furnitures for 201 9 VSCs G SH Post 6 30- Safeguard system for Mets Parni 201 17-Aug- 17-Aug- 24-Aug- 1-Sep- 9A VSC G SH Post 7 7-Aug-17 17 17 17 17 Sep- 17 30- 1C software with scanning 201 18-Aug- 18-Aug- 25-Aug- 1-Sep- 9B equipment for Mets Parni VSC G SH Post 7 7-Aug-17 17 17 17 17 Sep- 17 201 10 Medicines and supplies for VSCs G SH Post 6 11- Analitical and Lab Equipment for 13, 201 Local Food Inspectors, SSFS, G NCB Post 16- CV&P, SVC 6 17 Furniture for SSFS One stop shop 15- 25- 11 201 14-Feb- Contra CARMAC2-PG-17-16 (SSFS G SH Post 25-Jan-17 3-Feb-17 8-Feb-17 Feb- Feb- 7.18 Gaudi LLC A Furniture) 7 17 16 16 IT Equipment for SSFS One stop 15- 11 201 15-Feb- 6-Mar- shop Contra CARMAC2- G SH Post 25-Jan-17 3-Feb-17 9-Feb-17 Feb- 3.51 SRS-Zvezda LLC B PG-17-17 (SSFS Equipm) 7 17 16 16 Field equipment for SVC 30- Concern (Scientific Center for Vegetables) 201 20-Oct- 28-Oct- 9-Nov- 30- 14 Contra CARMAC2-PG-15-07 (GH G SH Post 5 20-Jul-15 15 15 15 Nov- Jun-17 70.85 Energomash 15 CJSC Equip) Field equipment for SVC 14 (Scientific Center for Vegetables) 201 26-Aug- 26-Aug- 5-Sep- 4-Oct- 3-Dec- G SH Post 26-Aug-16 27.33 SpecmashLLC A Contra CARMAC2-PG-16-13 (GH 6 16 16 16 16 16 Equip) Greenhouse equipment for SCV 201 23-Sep- 23-Sep- 3-Oct- 7-Oct- 6-Dec- HGH Company 15 Contra CARMAC2-PG-16-14 (GH G SH Post 6 23-Sep-16 16 16 16 16 16 33.10 LLC Equip) Office equipment (IT and 201 30-Jan- 19-Feb- 5-Apr- 4-Jun- 18 furniture) for SCV G SH Post 6 10-Jan-17 17 4-Feb-17 17 17 17 Analytical Equipment for Concern 201 10-Feb- 15-Feb- 25-Feb- 1-Mar- 1-May- 19 Agrochemical Center Contra G SH Post 7 10-Feb-17 17 17 17 17 17 86.28 Energomash CARMAC2-PG-17-18 (Lab Equip) CJSC 30- 29- Analytical Equipment for 201 1-Aug- 16-Aug- 20 Agrochemical Center G SH Post 8 7-Jul-18 27-Jul-18 18 18 Sep- Nov- 18 18 Additional IT equipment (MIS) 201 1-Sep- 11-Sep- 1-Oct- 1-Dec- Doxx Computers 21 Contra CARMAC2-PG-15-05 (MIS G SH Post 5 20-Jul-15 1-Sep-15 15 15 15 15 9.24 LLC Equipm) 677.3 13- 201 12-Feb- 14-Mar- 9-Nov- 22 VSC Civil works CW SH Post 6 9-Dec-16 7-Feb-17 17 17 May- 17 17 SSFS One stop shop renovation 15- 11- Master- 22 201 14-Feb- CW Contra CARMAC2-CW-17-6/02 CW SH Post 25-Jan-17 3-Feb-17 8-Feb-17 Feb- Mar- 30.07 Constracshen A (SSFS CW) 7 17 16 16 LLC SSFS One stop shop renovation 15- 11- 22 supervision 201 16-Feb- 9-Feb- CS CQ Post 25-Jan-17 Feb- Mar- 0.54 Micto HEK LLC B Contra CARMAC2-CW-17-6/02 7 16 17 16 16 (SSFS CW) 22 Contra CARMAC2-CW-16-5/01-04 1-Aug- 9-Aug- 6-Sep- QVE nakhagits 1-Aug-16 4.83 C (Parni VSC Design&Author) 16 16 16 LLC 22 Contra CARMAC2-CW-16-5/02 20-Sep- 20-Sep- 30-Sep- 7-Oct- 9-Jun- 20-Sep-16 94.77 Vordi Hrair LLC D (Parni VSC CW) 16 16 16 16 17 22 Contra CARMAC2-CW-16-5/03 13-Sep- 7-Oct- 9-Jun- 13-Sep-16 1.86 Alternative LLC E (Parni VSC Supervision) 16 16 17 Reconstruction of Glass 201 23 Greenhouses for SCV CW SH Post 5 Contra CARMAC2-CW-15-1/01-04 23 201 15-May- 1-Jun- 31-Jul- (Glass Greenhouse CS CQ Post 4-Feb-15 5.95 HGSHN LLC A Design&Author) 5 15 15 15 23 Contra CARMAC2-CW-15-1/02 201 25-Sep- 15-Oct- 30- 2-May- CW SH Post 31-Jul-15 5-Oct-15 202.20 Saz-Agro LLC B (Glass Greenhouse CW) 5 15 15 Oct-15 16 23 Contra CARMAC2-CW-15-1/03 201 15-Oct- 30- 2-May- Shinindustria CS CQ Post 4-Feb-15 2.96 C (Glass Greenhouse Supervis) 5 15 Oct-15 16 LLC Reconstruction of Glass 201 CW SH Post Greenhouses for SCV 6 Contra CARMAC2-CW-16-4/01-04 31- 23 201 16-Feb- 19-Jul- 29-Jul- (Glass Greenhouse CS CQ Post Aug- 7.90 HGSHN LLC D Design&Author) 6 16 16 16 16 22- 23- 23 Contra CARMAC2-CW-16-4/02 201 25-Sep- 30-Aug- 9-Sep- Nik-Dav Group CW SH Post 19-Sep-15 Sep- May- 199.28 E (Glass Greenhouse CW) 6 15 16 16 16 17 CJSC 22- 23- 23 Contra CARMAC2-CW-16-4/03 201 16-Feb- 1-Sep- Shinindustria CS CQ Post Sep- May- 3.25 F (Glass Greenhouse Supervis) 6 16 16 16 17 LLC Refurbishment of Plastic 24 Greenhouses for SCV CW SH 24 201 SCV Plastic Greenhouses CW CW SH Post 7-Apr-17 A 7 24 SCV Plastic Greenhouses 201 CS CQ Post B Supervision 7 24 201 SCV improvement CW CW SH Post 7-Mar-17 C 7 24 201 SCV improvement CW Supervision CS CQ Post D 7 Refurbishment of Phytopathology 201 25 Lab CW SH Post 5 10-Nov-15 Contra CARMAC2-CW-15-2/01-04 10- 10- 25 201 2-Sep- (Glass Greenhouse CS CQ Post 4-Feb-15 Sep- Nov- 9.28 HGSHN LLC A Design&Author) 5 15 15 15 10- 25 Contra CARMAC2-CW-15-2/02 201 30-Oct- 30-Oct- 9-Nov- 7-Jun- Hydroveranorog CW SH Post 30-Oct-15 Dec- 197.38 B (Glass Greenhouse CW) 5 15 15 15 15 16 um LLC 10- 25 Contra CARMAC2-CW-15-2/03 201 25-Nov- 7-Jun- Shinindustria CS CQ Post 4-Feb-15 Dec- 2.57 C (Glass Greenhouse Supervision) 5 15 15 16 LLC Reconstruction of Glass 201 CW SH Post Greenhous Boiler for SCV 6 Contra CARMAC2-CW-16-3/01-04 29- 25 201 20- (Glass Greenhouse Boiler CS CQ Post 4-Feb-15 8-Jan-16 Feb- 9.52 HGSHN LLC D Design&Author) 6 Jan-16 16 25 Contra CARMAC2-CW-16-3/02 201 11-Apr- 6-May- 6-Jan- Hydroveranorog CW SH Post 4-Mar-16 1-Apr-16 1-Apr-16 194.22 E (Glass Greenhouse Boiler CW) 6 16 16 17 um LLC Contra CARMAC2-CW-16-3/03 25 201 16-Feb- 29-Apr- 6-May- 6-Jan- Shinindustria (Glass Greenhouse Boiler CS CQ Post 3.15 F Supervision) 6 16 16 16 17 LLC 969.7 Prior/ 201 27 Preparation of PLMDP CS QCBS/ CQ Post 5 Preparation of PLMDP for 50 15- 15- 28- 27 201 22-Mar- 25-Mar- 9-Apr- communities Contra CS CQ Prior 10-Mar-15 Mar- May- Feb- 192.00 Wide Gate LLC A CARMAC2-CS-15/02 (PMP) 5 15 15 15 15 15 16 Preparation of PLMDP for 50 27- 28- 27 201 20- 27-Apr- 29-Apr- 14-May- communities Contra CS CQ Post 15-Apr-16 May- Feb- 187.30 Wide Gate LLC B CARMAC2-CS-16/13 (PMP) 6 Apr-16 16 16 16 16 17 27 Preparation of PLMDP for 4 201 29-May- 13-Jun- 3-Jul- 30- CS CQ Post 29-May-17 15.42 Wide Gate LLC C communities 7 17 17 17 Oct-17 Ongoing 201 through 28 Grassland/pasture expert CS IC Post 6 the Project 201 29 Expert depending on needs CS IC Post 5 Community Development expert 12- 29 201 14-May- 15-May- 3-Jun- 30- Contra CARMAC2-CS-15/07 CS IC Post 10-May-15 May- 1-Jun-15 21.79 T. Apoyan A (ComDev Spec) 5 15 15 15 15 Jun-17 Community Development 29 consultant for Gegharkunik MST 201 3-Dec- 11-Dec- 25-Dec- 1-Feb- 30- CS IC Post 1-Dec-15 8-Dec-15 4.18 G.Badalyan B Contra CARMAC2-CS-16/09 6 15 15 15 16 Jun-17 (ComDev Spec) Ongoing 201 through 30 Livestock economist local expert CS IC Post 6 the Project Ongoing Other local TA depending on 201 through 31 emerging needs CS IC Post 6 the Project Preparation of vegetation 31 recovery measures for degraded 201 1-May- 15-May- CS IC Post 1-Dec-15 1-May-17 A nearby village pastures of the 7 17 17 communities Women/Youth Special Support 201 6-Aug- 13-Aug- 16-Aug- 31-Aug- 35 Program CS CQ Post 6 1-Aug-17 17 17 17 17 30- 30- Technical Review Contra 201 10- 24-Jun- 24-Jun- 36 CARMAC2-CS-15/05 (Value Chain) CS CQ Post 5 1-Apr-15 Jun-15 15 15 8-Jul-15 Sep- Dec- 32.00 AM Partners LLC 15 16 201 37 Selection Committee meetings CS IC Post 5 201 18-May- 18-May- 1-Jul- 1-Jul- Contra ASHZH-1/1 CS IC***** Post 1-Jul-15 1.05 A.Gasparyan 5 15 15 15 18 201 18-May- 18-May- 1-Jul- 1-Jul- Contra ASHZH-1/2 CS IC***** Post 1-Jul-15 0.7 H.Tspnetsyan 5 15 15 15 18 201 18-May- 18-May- 1-Jul- 1-Jul- Contra ASHZH-1/3 CS IC***** Post 1-Jul-15 0.7 G.Ghazaryan 5 15 15 15 18 201 18-May- 18-May- 1-Jul- 1-Jul- Contra ASHZH-1/4 CS IC***** Post 1-Jul-15 0.7 M.Saponjyan 5 15 15 15 18 201 18-May- 18-May- 1-Jul- 1-Jul- Contra ASHZH-1/5 CS IC***** Post 1-Jul-15 0.7 Kh.Poghosyan 5 15 15 15 18 201 18-May- 18-May- 1-Jul- 1-Jul- Contra ASHZH-1/6 CS IC***** Post 1-Jul-15 0.7 N.Darbinyan 5 15 15 15 18 201 18-May- 18-May- 1-Jul- 1-Jul- Contra ASHZH-1/7 CS IC***** Post 1-Jul-15 0.7 G.Sardaryan 5 15 15 15 18 201 18-May- 18-May- 1-Jul- 1-Jul- Contra ASHZH-1/8 CS IC***** Post 1-Jul-15 0.7 G.Sargsyan 5 15 15 15 18 201 18-May- 18-May- 1-Jul- 1-Jul- Contra ASHZH-1/9 CS IC***** Post 1-Jul-15 0.7 L.Aydinyan 5 15 15 15 18 28- Evaluation of all sub-project 201 4-May- 11-May- 4-May- 18-May- 19- 38 investments CS CQ Post 7 1-Apr-17 17 17 17 17 Jun-17 Feb- 12.00 Argument LLC 18 10- 201 6-Jan- 13-Jan- 16-Jan- 31-Jan- 39 Dairy/Livestock specialist CS IC Post 6 1-Jan-17 17 17 17 17 Feb- 17 10- 201 6-Jan- 13-Jan- 16-Jan- 31-Jan- 40 Horticulture specialist CS IC Post 6 1-Jan-17 17 17 17 17 Feb- 17 Other local expert depending on 201 41 emerging needs CS IC Post 5 Food Safety specialist for the VCD 41 201 8-Jul- 11-Aug- 13-Aug- 27-Aug- 1-Sep- 30- Contra CARMAC2-CS-15/08 (Food CS IC Post 8-Jul-15 19.06 G. Hovhannisyan A Safety Spec) 5 15 15 15 15 15 Jun-17 27- CARD Mobilisation of comm. Vets 201 11-Mar- 11-Mar- 4-May- 27- 42 Contra CARMAC2-CS-16/10 CS CQ Post 6 1-Mar-16 16 16 16 Jun-16 Dec- 54.35 Agroservice 17 CJSC 13- 201 6-Feb- 13-Feb- 16-Feb- 3-Mar- 43 Impact evaluation CS CQ Post 9 1-Feb-19 19 19 19 19 Mar- 19 Training of Local Food Safety IMS LLC & 201 11-Mar- 11-Mar- 29-Mar- 6-May- 7-Oct- Irazek ev 44 Inspectors Contra CS CQ Post 6 1-Mar-16 16 16 16 16 16 50.06 pashpamvac CARMAC2-CS-16/11 sparogh NGO GAP Survey for preparation of 201 6-Apr- 13-Apr- 16-Apr- 1-May- 45 guidelines CS CQ Post 6 1-Apr-17 17 17 17 17 Guidelines preparation, printing, 201 6-Jun- 13-Jun- 46 dissemination CS TBD Post 7 1-Jun-17 17 17 20- Guidelines preparation, printing, 201 27-Feb- 9-Mar- 5-Sep- 47 dissemination CS TBD Post 8 15-Feb-18 Feb- 18 18 18 18 Environmental specialist 201 1-Apr- 13-Apr- 15-Apr- 29-Apr- 5-May- 30- 48 Contra CARMAC2-CS-15/06 CS IC Post 5 1-Apr-15 15 15 15 15 15 Jun-17 15.24 A. Savadyan (Environmenthal Spec) Social specialist 12- 201 16-Mar- 24-Mar- 6-Apr- 4-May- 30- 49 Contra CARMAC2-CS-15/04 (Social CS IC Post 5 10-Mar-15 Mar- 15 15 15 15 Jun-17 23.02 E. Mkrtchyan Spec) 15 Ongoing 201 through 50 Short-term consultancies (local) CS IC Post 6 the Project Development of MIS 201 5-Mar- 12-Mar- 15-Mar- 30-Mar- 1-Jun- 30- 52 Contra CARMAC2-CS-15/03 (MIS) CS CQ/IC Post 5 28-Feb-15 15 15 15 15 15 Oct-15 38.14 Shogersoft LLC 15- External Evaluation & Impact 201 22-Aug- 25-Aug- 9-Sep- 53 Assessment CS CQ Post 7 10-Aug-17 Aug- 17 17 17 17 To be Special studies on erosion control, 201 54 biodiversity, etc. CS CQ/IC Post 8 determin ed 201 6-Mar- 13-Mar- 16-Mar- 31-Mar- 10- 55 Public awareness CS CQ Post 7 1-Mar-17 17 17 17 17 Apr-17 18- 30- 201 21-Feb- 22-Feb- 15-Mar- 4-Apr- 56 Audit Contra CARMAC2-CS-16/12 CS LCS Post 5 18-Feb-16 Feb- 16 16 16 16 Dec- 51.98 SOS Audit LLC 16 20 723.2 Ongoing Grant NCB/SH/CQ/F Prior/ 201 through 57 Community Funds (1 year) s A Post** 5 the 1895.00 Project Ongoing Grant NCB/SH/CQ/F 201 through 58 Community Funds (2 year) s A Post 6 the 7293.70 Project Ongoing Grant NCB/SH/CQ/F 201 through 59 Community Funds (3 year) s A Post 7 the Project Ongoing 60- Sub-projects under Component 2 Grant 201 through SH/CQ Post 1075 61 including Beneficiary contribution s 5 the Project 10,263 .7 Ongoing Operating Costs for 201 through 62 Components 1 - 4 SOE Post 5 the Project Ongoing Training under Component 1 TR*** 201 through 26 (Component staff) * NA Post 6 the Project Ongoing Trainings on PMC TR*** 201 through 32 Mobilization/Planning * NA Post 5 the Project Ongoing PMC Annual Planning Meetings (2 TR*** 201 through 33 per year) * NA Post 5 the Project Special trainings on the role of Ongoing PMC, pasture management, TR*** 201 through 34 feeding and feed management, * NA Post 5 the animal nutrition, etc. Project Ongoing Training under Component 4 TR*** 201 through 51 (staff training abroad, finance, * NA Post 4 the procurement, other) Project PROCUREMENT Armenia : Second Community Agriculture Resource Management and Competitiveness Project PLAN General Information Country: Armenia Bank’s Approval Date of the Original Procurement Plan: 2017-11-06 2021-05-20 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P133705 GPN Date: Project Name: Second Community Agriculture Resource Management and Competitiveness Project Loan / Credit No: IBRD / 83740 Ministry of Agriculture of RA Executing Agency(ies): WORKS Procureme Activity Reference No. / Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH nt Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) Justification for Award Type Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CARMAC2-CP-15/02 / Construction of the watering Component 1: Request for system in Lichk community of IBRD / 83740 Community/Pasture Livestock Prior Open - International 74,563.87 Signed 2015-07-29 Quotations Gegharquniq marz of the RA Management System for Lichk community needs NCB-CARMAC2-CP-15-A- 1/02 / Procurement of Civil Component 1: works for construction of Single Stage - One IBRD / 83740 Community/Pasture Livestock Prior Request for Bids Open - National 290,048.82 Signed 2016-05-23 2016-05-30 watering system in Artashavan Envelope Management System community pastures of Aragotsotn marz of the RA CARMAC2-CP-18-V-6/02 / Construction of the watering Component 1: Request for Single Stage - One 2018-06- system in Karmrashen IBRD / 83740 Community/Pasture Livestock Post Limited 59,503.55 Signed 2018-01-23 2018-07-19 2018-02-19 2018-08-24 Quotations Envelope 19 community of Vayots Dzor Management System marz of the RA CARMAC2-CW-18-4/02 / Component 3: Strengthening Request for Single Stage - One 2018-05- Refurbishment of Plastic IBRD / 83740 Post Limited 77,407.95 Signed 2017-12-18 2018-02-21 2018-01-18 2018-04-05 Public Sector Institutions Quotations Envelope 18 Greenhouses for SCV CARMAC2-CP-17-G-15/02 / Construction of the watering Component 1: Single Stage - One 2019-08- system in Vaghashen IBRD / 83740 Community/Pasture Livestock Post Request for Bids Open - National 440,209.79 Signed 2018-02-07 2018-04-16 2018-02-14 2018-03-14 2018-05-07 2018-04-13 2018-06-29 2018-05-12 2018-08-02 Envelope 05 community of Gegharquniq Management System marz of the RA CARMAC2-CP-18-SH-7/02 / Construction of the watering Component 1: Request for Single Stage - One 2018-07- system in Aghvorik IBRD / 83740 Community/Pasture Livestock Post Limited 89,709.18 Signed 2018-01-30 2018-05-04 2018-02-22 2018-06-13 Quotations Envelope 22 community of Shirak marz of Management System the RA CARMAC2-PG-18-25 / Component 3: Strengthening Request for Single Stage - One 2018-06- Procurement of refrigeration IBRD / 83740 Post Limited 0.00 Canceled 2018-03-03 2018-02-28 2018-04-03 Public Sector Institutions Quotations Envelope 02 equipment CARMAC2-CP-18-S-J-1/02 / Const. of a waterwashing water line in Kornidzor community pastures, Component 1: installation of 1 drinking Request for Single Stage - One 2018-07- IBRD / 83740 Community/Pasture Livestock Post Limited 78,470.25 Signed 2018-03-17 2018-06-14 2018-04-17 2018-08-20 water, road profiling and Quotations Envelope 16 Management System smoothing works and const. of irrigation system in the pastures of N.Kndzoresk and Tashtun communities CARMAC2-CP-18-S-J-2/02 / Component 1: Construction of irrigation Request for Single Stage - One 2018-08- IBRD / 83740 Community/Pasture Livestock Post Limited 61,740.45 Signed 2018-03-19 2018-06-14 2018-04-19 2018-08-03 system in Balaq and Vorotan Quotations Envelope 17 Management System community pastures CARMAC2-CP-18-T-J-1/02 / Component 1: Construction of irrigation Request for Single Stage - One 2018-07- IBRD / 83740 Community/Pasture Livestock Post Limited 38,736.65 Signed 2018-03-21 2018-09-07 2018-04-21 2018-10-15 system in V. Tsakhkavan and Quotations Envelope 20 Management System Movses community pastures CARMAC2-CP-17-A-6/02 / Component 1: Construction of the watering Request for Single Stage - One 2018-09- IBRD / 83740 Community/Pasture Livestock Post Limited 185,421.03 Signed 2018-02-07 2018-02-07 2018-03-23 2018-04-05 system in Aparan community Quotations Envelope 19 Management System of Aragatsotn marz of the RA CARMAC2-CP-18-L-7/02 / Component 1: Construction of the watering Request for Single Stage - One 2018-05- IBRD / 83740 Community/Pasture Livestock Post Limited 58,769.35 Signed 2017-12-14 2018-02-21 2018-01-15 2018-04-19 system in Jrashen community Quotations Envelope 30 Management System of Lori marz of the RA CARMAC2-CP-18-G-J-1/02 / Construction of the watering Component 1: Request for Single Stage - One 2018-09- system in Chambarak and IBRD / 83740 Community/Pasture Livestock Post Limited 92,183.03 Signed 2018-05-09 2018-07-17 2018-06-09 2018-08-16 Quotations Envelope 07 Vahan communities of Management System Gegharquniq marz of the RA CARMAC2-CP-18-K-6/02 / Component 1: Construction of the watering Request for Single Stage - One 2018-12- IBRD / 83740 Community/Pasture Livestock Post Limited 160,014.08 Signed 2018-05-12 2018-06-14 2018-06-12 2018-08-06 system in Kaputan community Quotations Envelope 09 Management System of Kotayq marz of the RA CARMAC2-CP-18-G-J-2/02 / Construction of the watering system in settlement Aghberq Component 1: of Shoghakat community, in Request for Single Stage - One 2019-02- IBRD / 83740 Community/Pasture Livestock Post Limited 151,049.62 Signed 2018-06-18 2018-10-15 2018-07-19 2018-11-13 settlement Aygut of Quotations Envelope 14 Management System Chambarak community and Varser community of Gegharquniq marz of the RA Page 1 CARMAC2-CP-18-K-7/02 / Construction of the watering Component 1: Request for Single Stage - One 2019-01- system in settlement Arzakan IBRD / 83740 Community/Pasture Livestock Post Limited 0.00 Canceled 2018-06-20 2018-07-03 2018-07-21 Quotations Envelope 21 of Charencavan community of Management System Kotayq marz of the RA CARMAC2-CP-18-G-21/02 / Construction of the watering Component 1: Request for Single Stage - One 2019-02- system in community IBRD / 83740 Community/Pasture Livestock Post Limited 71,952.44 Signed 2018-09-03 2018-10-25 2018-10-04 2018-12-28 Quotations Envelope 01 Akhpradzor of Gegharqunik Management System marz CARMAC2-CP-18-K-7/02-1 / Construction of the watering Component 1: Request for Single Stage - One 2019-03- system in settlement Arzakan IBRD / 83740 Community/Pasture Livestock Post Open - National 0.00 Canceled 2018-08-21 2018-09-26 Quotations Envelope 29 of Charencavan community of Management System Kotayq marz of the RA CARMAC2-CW-18-7/02 / Construction of a veterinary Component 3: Strengthening Request for Single Stage - One 2019-05- IBRD / 83740 Post Open - National 0.00 Canceled 2018-11-13 2018-12-17 service center in Hrazdan city Public Sector Institutions Quotations Envelope 16 community of Kotayk marz CARMAC2-CW-19-7/02 / Construction of a veterinary Component 3: Strengthening Request for Single Stage - One 2020-06- IBRD / 83740 Post Limited 0.00 Canceled 2019-10-15 2019-12-10 service center in Hrazdan city Public Sector Institutions Quotations Envelope 07 community of Kotayk marz CARMAC2-CW-20-7/02 / Construction of a veterinary Component 3: Strengthening Request for Single Stage - One 2020-06- IBRD / 83740 Post Open - National 0.00 Canceled 2019-11-20 2020-01-10 service center in Hrazdan city Public Sector Institutions Quotations Envelope 08 community of Kotayk marz CARMAC2-CP-20-GK-1/02 / Construction of the watering system in Khachaghbyur Component 1: community of Gegharquniq Single Stage - One 2020-09- IBRD / 83740 Community/Pasture Livestock Post Request for Bids Open - National 0.00 Canceled 2019-11-20 2019-11-25 2019-12-23 2020-01-12 2020-02-09 marz and in settlement Envelope 06 Management System Arzakan of Charentsavan community of Kotayk marz of RA CARMAC2-CP-19-GK-1/02 / Construction of the watering system in Khachaghbyur Component 1: community of Gegharquniq Single Stage - One 2020-09- IBRD / 83740 Community/Pasture Livestock Post Request for Bids Open - National 227,330.44 Signed 2019-11-20 2020-02-19 2019-11-25 2019-12-23 2020-03-19 2020-02-01 2020-04-21 2020-03-07 2020-06-16 marz and in settlement Envelope 23 Management System Arzakan of Charentsavan community of Kotayk marz of RA N. CARMAC2-CW-19-7/02 / Construction of a veterinary Component 3: Strengthening Request for Single Stage - One 2020-06- IBRD / 83740 Post Open - National 0.00 Canceled 2019-11-20 2020-02-01 service center in Hrazdan city Public Sector Institutions Quotations Envelope 30 community of Kotayk marz CARMAC2-CP-19-J-2/02 / Construction of water supply Component 1: Single Stage - One 2020-10- pipeline systems in pastures IBRD / 83740 Community/Pasture Livestock Post Request for Bids Open - National 213,434.26 Signed 2020-01-14 2020-01-22 2020-01-19 2020-02-16 2020-02-21 2020-03-17 2020-05-14 2020-04-17 2020-06-16 Envelope 14 of Gegharquniq, Syuniq, Lori Management System and Aragatsotn marzes of RA CARMAC2-CP-20-T-J-2/02 / Construction of pasture water supply pipeline systems in Ditavan and N.Karmir Aghbyur Component 1: Single Stage - One 2021-03- communities, Varagavan and IBRD / 83740 Community/Pasture Livestock Post Request for Bids Open - National 133,425.18 Signed 2020-05-14 2020-05-15 2020-05-15 2020-06-04 2020-06-04 2020-07-04 2020-06-18 2020-07-19 2020-07-09 Envelope 16 Berd settlements of Berd Management System community, Koti settlement of Noyemberyan community, Tavush Marz CARMAC2-CP-20-S-J-4/02 / Construction of pasture water supply pipeline systems in Component 1: Single Stage - One 2021-04- Lor, Noravan and Nzhdeh IBRD / 83740 Community/Pasture Livestock Post Request for Bids Open - National 123,326.58 Signed 2020-05-26 2020-05-26 2020-05-28 2020-06-17 2020-06-16 2020-07-17 2020-07-06 2020-08-06 2020-08-13 Envelope 04 settlements of Sisian Management System commynity of Syuniq marz of RA. CARMAC2-CW-19-7/02/2 / Construction of a veterinary Component 3: Strengthening Single Stage - One 2021-02- IBRD / 83740 Post Request for Bids Open - National 103,476.95 Signed 2020-06-03 2020-01-17 2020-06-13 2020-07-11 2020-02-17 2020-09-09 2020-04-17 2020-09-24 2020-05-11 service center in Hrazdan city Public Sector Institutions Envelope 06 community of Kotayk marz CARMAC2-CP-20-J-5/02 / Construction of pasture water supply pipeline system in of Component 1: Hartashen settlement of Single Stage - One 2021-07- IBRD / 83740 Community/Pasture Livestock Post Request for Bids Open - National 346,389.81 Signed 2020-06-04 2020-06-05 2020-06-05 2020-06-25 2020-06-25 2020-07-25 2020-07-27 2020-08-11 2020-08-27 Sarapat community of Shirak Envelope 12 Management System Marz, and Quchak settlement of Aparan community of Aragatsotn Marz. CARMAC2-CP-20-K-J-6/02 / Construction of pasture water supply pipeline system in Component 1: Single Stage - One 2021-06- Qarashamb community and IBRD / 83740 Community/Pasture Livestock Post Request for Bids Open - National 101,486.93 Signed 2020-09-09 2020-10-09 2020-09-14 2020-10-05 2020-11-05 2020-11-14 2020-11-23 2020-12-15 2021-01-12 Envelope 18 Bjni settlement of Management System Charentsavan community, Kotayq Marz. CARMAC2-CP-20-S-11/02 / Construction of pasture water Component 1: supply pipeline system in Request for Single Stage - One 2021-02- IBRD / 83740 Community/Pasture Livestock Post Limited 0.00 Canceled 2020-09-20 2020-10-25 2020-10-13 Goris city settlement of Goris Quotations Envelope 12 Management System community, Syuniq marz of RA CARMAC2-CP-20-S-11/02/1 / Construction of pasture Component 1: water supply pipeline system Request for Single Stage - One 2021-05- IBRD / 83740 Community/Pasture Livestock Post Open - National 27,283.93 Signed 2020-12-10 2021-01-10 2021-03-03 in Goris city settlement of Quotations Envelope 15 Management System Goris community, Syuniq marz of RA Page 2 CARMAC2-CP-20-J-5/02-1 / Construction of pasture water Component 1: supply pipeline system in Single Stage - One 2021-08- IBRD / 83740 Community/Pasture Livestock Post Request for Bids Open - National 180,162.47 Signed 2020-12-15 2020-12-18 2020-12-17 2021-01-14 2021-01-18 2021-01-25 2021-02-02 2021-02-24 2021-03-23 Quchak settlement of Aparan Envelope 28 Management System community of Aragatsotn Marz CARMAC2-CP-21-J-SH-7/02 / Construction of pasture water supply pipeline systems Component 1: Single Stage - One 2021-11- in Ghazanchi, Mets Sepasar IBRD / 83740 Community/Pasture Livestock Post Request for Bids Open - National 431,188.81 Signed 2021-02-08 2021-02-11 2021-02-13 2021-03-15 2021-03-05 2021-04-14 2021-03-31 2021-05-22 2021-05-06 Envelope 23 and Zuygaghbyur settlements Management System of Ashotsk community of Shirak marz of RA GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CARMAC2-NCB-15-01-1 / Component 1: Single Stage - One Procurement of Short Base 3 IBRD / 83740 Community/Pasture Livestock Prior Request for Bids Open - National 84,909.49 Completed 2015-06-16 2015-06-26 2015-06-29 Envelope doors 4WD Vehicles Management System CARMAC2-NCB-15-01/2 / Component 1: Single Stage - One Procurement of short Base 5 IBRD / 83740 Community/Pasture Livestock Prior Request for Bids Open - National 98,780.84 Completed 2015-06-16 2015-07-14 2015-08-12 Envelope doors 4WD Vehicles Management System CARMAC2-CP-J-15-01 / Component 1: Request for Procurement of Balers for IBRD / 83740 Community/Pasture Livestock Prior Open - International 47,000.00 Completed 2015-06-16 2015-07-20 Quotations PUCs Management System CARMAC2-PG-15-02 / Component 1: Request for Procurement of IT equipment IBRD / 83740 Community/Pasture Livestock Prior Open - International 11,610.05 Completed 2015-06-22 2015-06-24 Quotations for MSTs Management System CARMAC2-CP-J-17-54 / Component 1: General-purpose crawler Request for Single Stage - One IBRD / 83740 Community/Pasture Livestock Post Limited 47,900.00 Completed 2017-12-06 2017-11-30 2017-12-25 2017-12-28 2018-02-23 2018-03-28 tractor (min 90 h.p., quantity: Quotations Envelope Management System 1) CARMAC2-CP-J-17-55 / Component 1: Request for Single Stage - One General purpose wheel IBRD / 83740 Community/Pasture Livestock Post Limited 87,800.00 Completed 2017-12-08 2017-12-05 2017-12-27 2017-12-27 2018-02-25 2017-12-28 Quotations Envelope tractors (4 pc) Management System CARMAC2-PG-18-22 / Procurement of Lab Component 3: Strengthening Single Stage - One equipment for Scientific IBRD / 83740 Post Request for Bids Open - National 113,671.09 Completed 2018-01-18 2018-04-04 2018-01-23 2018-03-06 2018-04-25 2018-04-05 2018-05-07 2018-05-10 2018-05-29 2018-11-06 2018-07-17 Public Sector Institutions Envelope Center of Vegetable and Industrial Crops of MoA (SCV) Component 1: CARMAC2-CP-J-17-56 / Request for Single Stage - One IBRD / 83740 Community/Pasture Livestock Post Limited 0.00 Canceled 2017-12-14 2017-12-20 2017-12-29 2018-02-27 Agricultural machinery Quotations Envelope Management System Component 1: CARMAC2-CP-J-18-56 / Request for Single Stage - One IBRD / 83740 Community/Pasture Livestock Post Limited 94,022.49 Completed 2018-02-02 2018-02-02 2018-03-02 2018-02-23 2018-05-01 2018-03-26 Agricultural machinery Quotations Envelope Management System CARMAC2-PG-17-21 / Component 3: Strengthening Request for Single Stage - One IBRD / 83740 Post Limited 0.00 Canceled 2017-12-13 2018-01-24 2017-12-28 2018-02-26 Veterinary Equipment Public Sector Institutions Quotations Envelope CARMAC2-PG-18-23 / Component 3: Strengthening Request for Single Stage - One Procurement of Furniture for IBRD / 83740 Post Limited 0.00 Canceled 2017-12-14 2018-02-01 2017-12-28 2018-02-26 Public Sector Institutions Quotations Envelope SCV CARMAC2-PG-18-23-2 / Component 3: Strengthening Request for Single Stage - One Procurement of furniture for IBRD / 83740 Post Limited 0.00 Canceled 2018-03-03 2018-02-28 2018-04-03 2018-06-02 Public Sector Institutions Quotations Envelope SVC CARMAC2-PG-17-21-2 / Procurement of Veterinary Component 3: Strengthening Request for Single Stage - One Equipment for veterinarians of IBRD / 83740 Post Limited 57,090.39 Completed 2018-03-05 2018-02-28 2018-04-05 2018-03-27 2018-06-04 2018-05-25 Public Sector Institutions Quotations Envelope Kotayq and Vayots Dzor marzes CARMAC2-PG-18-24 / Component 3: Strengthening Request for Single Stage - One Procurement of IT Equipment IBRD / 83740 Post Limited 0.00 Canceled 2017-12-15 2018-02-01 2017-12-29 2018-02-27 Public Sector Institutions Quotations Envelope for SCV CARMAC2-PG-18-24-2 / Component 3: Strengthening Request for Single Stage - One Procurement of IT Equipment IBRD / 83740 Post Limited 0.00 Canceled 2018-03-07 2018-03-02 2018-04-03 2018-06-02 Public Sector Institutions Quotations Envelope for SCV CARMAC2-PG-17-20 / 1C Component 3: Strengthening Request for Single Stage - One software with scanning IBRD / 83740 Post Limited 0.00 Canceled 2017-12-13 2018-02-05 2017-12-28 2018-01-27 Public Sector Institutions Quotations Envelope equipment for Mets Parni VSC CARMAC2-PG-17-20-2 / 1C Component 3: Strengthening Request for Single Stage - One software with scanning IBRD / 83740 Post Limited 0.00 Canceled 2018-03-07 2018-03-02 2018-04-03 2018-05-03 Public Sector Institutions Quotations Envelope equipment for Mets Parni VSC Component 1: CARMAC2-CP-NCB-J-18-57 Single Stage - One IBRD / 83740 Community/Pasture Livestock Post Request for Bids Open - National 291,357.58 Completed 2018-02-28 2018-03-02 2018-03-02 2018-03-16 2018-03-16 2018-03-30 2018-03-21 2018-04-27 2018-03-26 2018-07-26 2018-05-18 / Procurement of tractors Envelope Management System CARMAC2-PG-18-23-2/1 / Component 3: Strengthening Request for Single Stage - One Procurement of furniture for IBRD / 83740 Post Open - National 3,257.20 Completed 2018-04-18 2018-05-28 2018-06-20 2018-07-27 2018-08-07 Public Sector Institutions Quotations Envelope SVC Page 3 CARMAC2-PG-18-24-2/1 / Component 3: Strengthening Request for Single Stage - One Procurement of IT Equipment IBRD / 83740 Post Limited 0.00 Canceled 2018-04-18 2018-05-21 2018-07-20 Public Sector Institutions Quotations Envelope for SCV CARMAC2-PG-18-20-2/1 / Component 3: Strengthening Request for Single Stage - One 1C software with scanning IBRD / 83740 Post Open - National 0.00 Canceled 2018-04-18 2018-05-23 2018-07-22 Public Sector Institutions Quotations Envelope equipment for Mets Parni VSC CARMAC2-PG-18-25-2 / Component 3: Strengthening Request for Single Stage - One IBRD / 83740 Post Open - National 0.00 Canceled 2018-04-18 2018-05-23 2018-07-22 Procurement of refrigerators Public Sector Institutions Quotations Envelope CARMAC2-CP-NCB-J-18-59 Component 1: Single Stage - One / Procurement of agricultural IBRD / 83740 Community/Pasture Livestock Post Request for Bids Open - National 0.00 Canceled 2018-05-10 2018-05-11 2018-05-17 2018-06-07 2018-06-04 2018-07-07 2018-08-01 2018-08-18 2018-10-17 Envelope machinery Management System CARMAC2-PG-18-24-2/2 / Component 3: Strengthening Request for Single Stage - One Procurement of IT Equipment IBRD / 83740 Post Open - National 5,623.45 Completed 2018-06-08 2018-07-13 2018-08-01 2018-09-11 2018-09-10 Public Sector Institutions Quotations Envelope for SCV CARMAC2-PG-18-26 / Procurement of Veterinary Component 3: Strengthening Request for Single Stage - One equipment for the Center IBRD / 83740 Post Limited 61,316.78 Completed 2018-06-20 2018-07-19 2018-07-20 2018-08-16 2018-09-18 2018-09-24 Public Sector Institutions Quotations Envelope Veterinary, Food Safety and Phitosanitary of RA MoA CARMAC2-CP-NCB-J-18-58 Component 1: Single Stage - One / Procurement of agricultural IBRD / 83740 Community/Pasture Livestock Post Request for Bids Open - National 0.00 Canceled 2018-03-26 2018-04-11 2018-04-02 2018-04-23 2018-05-03 2018-05-23 2018-06-01 2018-07-04 2018-09-02 Envelope machinery Management System CARMAC2-CP-NCB-J-18-58- Component 1: Single Stage - One 2 / Procurement of IBRD / 83740 Community/Pasture Livestock Post Request for Bids Open - National 166,066.38 Completed 2018-06-29 2018-07-25 2018-07-03 2018-07-17 2018-08-03 2018-07-31 2018-10-01 2018-08-28 2018-11-03 2018-10-27 2018-12-27 Envelope agricultural machinery Management System CARMAC2-CP-NCB-J-18-60 Component 1: Single Stage - One / Procurement of general IBRD / 83740 Community/Pasture Livestock Post Request for Bids Open - National 156,375.54 Completed 2018-07-04 2018-07-25 2018-07-08 2018-07-29 2018-08-16 2018-08-19 2018-10-18 2018-09-16 2018-10-27 2018-11-15 2018-12-24 Envelope purpose wheel tractors Management System CARMAC2-PG-18-25-2/2 / Procurement of refrigerators for the needs of the "Scientific Component 3: Strengthening Request for Single Stage - One IBRD / 83740 Post Open - National 5,555.55 Completed 2018-08-01 2018-09-05 2018-09-07 2018-11-04 2018-09-13 Center for Vegetable and Public Sector Institutions Quotations Envelope Industrial Crops" SNCO of MoA of RA CARMAC2-CP-NCB-J-18-61 Component 1: Single Stage - One / Procurement of agricultural IBRD / 83740 Community/Pasture Livestock Post Request for Bids Open - National 147,795.91 Completed 2018-08-28 2018-09-13 2018-09-01 2018-09-22 2018-10-05 2018-10-13 2018-12-03 2018-11-10 2018-12-27 2019-01-09 2019-08-12 Envelope machinery Management System CARMAC2-PG-18-27 / Procurement of equipment Component 3: Strengthening Request for Single Stage - One IBRD / 83740 Post Open - National 13,958.25 Completed 2018-08-25 2018-10-09 2018-11-19 2018-12-08 2018-12-24 for the Local Food Inspectors Public Sector Institutions Quotations Envelope of SSFS CARMAC2-PG-18-28 / Component 3: Strengthening Request for Single Stage - One Equipment for SSFS Central IBRD / 83740 Post Open - National 26,474.19 Completed 2018-10-22 2018-11-17 2018-12-14 2019-01-16 2019-03-05 Public Sector Institutions Quotations Envelope Lab CARMAC2-PG-18-29 / Component 3: Strengthening Request for Single Stage - One IBRD / 83740 Post Open - National 42,564.38 Completed 2018-10-22 2018-11-17 2018-11-23 2019-01-16 2019-01-21 Agrochem Equipment Public Sector Institutions Quotations Envelope CARMAC2-CP-NCB-J-18-62 / Procurement of tractors and agricultural machines for PUA cooperatives of Varser, Vardenik, Lchashen, Martuni Component 1: Single Stage - One town, Shatvan, Aygut, Vahan IBRD / 83740 Community/Pasture Livestock Post Request for Bids Open - National 271,599.74 Completed 2018-10-22 2018-10-27 2018-10-26 2018-11-16 2018-11-21 2018-12-07 2018-12-20 2019-01-04 2019-01-18 2019-04-04 2019-04-14 Envelope of Gegharqunik marz, Njdeh, Management System Shaghat, Kornidzor, Vorotan, N.Khndzoresk of Syuniq marz, Hartagyugh of Lori marz, Akunq CARMAC2-CP-NCB-J-18-63 / Proc. of tractors and agricultural machines for PUA cooperatives of Ayrq, Martuni town, Shatvan, Vardenik, Component 1: Single Stage - One Aghberq of Gegharqunik IBRD / 83740 Community/Pasture Livestock Post Request for Bids Open - National 0.00 Canceled 2018-11-19 2018-12-17 2018-11-23 2018-12-14 2018-01-15 2019-01-04 2019-02-01 2019-05-02 Envelope marz, Njdeh, Shaghat of Management System Syuniq marz, Vernashen of Vayots Dzor marz, Gagarin of Lori marz and N.Armanos, Quchak of Aragatsotn CARMAC2-CP-NCB-J-19-63 / Procurement of tractors and Component 1: agricultural machines for PUA Single Stage - One IBRD / 83740 Community/Pasture Livestock Post Request for Bids Open - National 188,416.29 Completed 2019-10-10 2020-02-20 2019-10-15 2019-11-26 2020-03-16 2019-12-26 2020-04-07 2020-01-30 2020-04-14 2020-07-28 2020-05-25 cooperatives of Gegharqunik, Envelope Management System Syuniq, Vayots Dzor, Lori and Aragatsotn marzes. CARMAC2-CW-19-7/02 / Construction of a veterinary Component 3: Strengthening Single Stage - One IBRD / 83740 Post Request for Bids Open - National 0.00 Canceled 2019-12-09 2020-01-17 2019-12-19 2020-01-16 2020-02-17 2020-03-16 2020-04-07 2020-03-31 2020-08-13 service center in Hrazdan city Public Sector Institutions Envelope community of Kotayk marz CARMAC2-CP-NCB-J-20-64 / Procurement of tractors and agricultural machines for PUA Component 1: Single Stage - One cooperatives of Gegharqunik, IBRD / 83740 Community/Pasture Livestock Post Request for Bids Open - National 251,355.60 Completed 2020-04-06 2020-04-07 2020-04-08 2020-04-30 2020-04-30 2020-05-30 2020-06-11 2020-06-07 2020-07-23 2020-08-06 2020-10-18 Envelope Tavush, Vayots Dzor, Lori, Management System Kotayk and Aragatsotn marzes. Page 4 CARMAC2-CP-NCB-J-19- 63/LOTS3,4,6 / Procurement of tractors and agricultural Component 1: machines for PUA Single Stage - One IBRD / 83740 Community/Pasture Livestock Post Request for Bids Open - National 58,007.04 Completed 2020-06-16 2020-02-20 2020-06-17 2020-07-10 2020-03-16 2020-08-09 2020-04-07 2020-08-19 2020-05-11 2020-10-19 2020-07-31 cooperatives of Gegharqunik, Envelope Management System Syuniq, Vayots Dzor, Lori and Aragatsotn marzes (Lots 3, 4 and 6). CARMAC2-PG-20-31 / IT Component 3: Strengthening Request for Single Stage - One IBRD / 83740 Post Open - National 0.00 Canceled 2020-06-24 2020-07-20 2020-09-18 equipment for ANAU Public Sector Institutions Quotations Envelope CARMAC2-PG-20-30 / Component 3: Strengthening Request for Single Stage - One Artificial insemination tools IBRD / 83740 Post Open - National 45,253.02 Completed 2020-06-24 2020-07-20 2020-08-12 2020-10-03 2020-12-07 Public Sector Institutions Quotations Envelope and training equipment CARMAC2-PG-18-20-3 / 1C Component 3: Strengthening Request for Single Stage - One IBRD / 83740 Post Open - National 0.00 Canceled 2018-10-22 2018-11-17 2018-12-17 Equipment Public Sector Institutions Quotations Envelope CARMAC2-CP-NCB-J-20-65 / Procurement of tractors and Component 1: light trucks for PUA Single Stage - One IBRD / 83740 Community/Pasture Livestock Post Request for Bids Open - National 462,259.48 Completed 2020-07-07 2020-07-20 2020-07-08 2020-07-31 2020-08-11 2020-08-30 2020-09-09 2020-09-30 2020-10-05 2020-11-29 2020-12-02 cooperatives of Gegharqunik, Envelope Management System Vayots Dzor, Lori, Kotayk and Aragatsotn marzes. CARMAC2-CP-NCB-J-20-66 Component 1: / Procurement of agricultural Single Stage - One IBRD / 83740 Community/Pasture Livestock Post Request for Bids Open - National 180,754.69 Completed 2020-07-27 2020-07-30 2020-07-28 2020-08-20 2020-08-14 2020-09-19 2020-09-02 2020-10-20 2020-10-08 2020-12-19 2020-12-22 machines for PUA Envelope Management System cooperatives of RA marzes. CARMAC2-PG-20-33 / Artificial insemination Component 3: Strengthening Request for Single Stage - One equipment for Veterinary IBRD / 83740 Post Open - National 5,176.24 Completed 2020-09-21 2020-10-15 2020-11-16 2020-12-14 2021-01-12 Public Sector Institutions Quotations Envelope Center in Hrazdan community of Kotayq marz of RA CARMAC2-PG-20-32 / Furniture for Veterinary Component 3: Strengthening Request for Single Stage - One IBRD / 83740 Post Open - National 5,749.54 Completed 2020-11-25 2020-10-17 2021-03-01 2020-12-17 2021-03-12 Center in Hrazdan community Public Sector Institutions Quotations Envelope of Kotayq marz of RA CARMAC2-CP-NCB-J-21-67 / Procurement of tractors and light trucks for PUA Component 1: Single Stage - One cooperatives of Gegharqunik, IBRD / 83740 Community/Pasture Livestock Post Request for Bids Open - National 464,877.15 Completed 2021-01-21 2021-01-29 2021-01-22 2021-02-11 2021-02-19 2021-03-03 2021-03-03 2021-04-01 2021-03-26 2021-05-31 2021-05-31 Envelope Vayots Dzor, Tavush, Syunik, Management System Kotayk and Aragatsotn marzes. CARMAC2-PG-21-35 / Procurement of special Pending Component 3: Strengthening Request for Single Stage - One vehicles for Mets Parni, IBRD / 83740 Post Open - National 0.00 Implementati 2021-03-04 2021-04-06 2021-07-06 Public Sector Institutions Quotations Envelope Hrazdan and Odzun on Veterinary Centers CARMAC2-CP-NCB-J-21-68 Component 1: Single Stage - One / Procurement of agricultural IBRD / 83740 Community/Pasture Livestock Post Request for Bids Open - National 186,910.36 Signed 2021-02-03 2021-02-05 2021-02-04 2021-02-23 2021-02-24 2021-03-14 2021-04-02 2021-04-14 2021-05-07 2021-06-14 Envelope machinery for 18 cooperatives Management System Under CARMAC2-PG-20-31-1 / IT Component 3: Strengthening Request for Single Stage - One IBRD / 83740 Post Open - National 0.00 Implementati 2021-04-28 2021-05-30 2021-07-30 equipment for ANAU Public Sector Institutions Quotations Envelope on CARMAC2-PG-21-34 / Pending Equipment for Veterinary Component 3: Strengthening Request for Single Stage - One IBRD / 83740 Post Open - National 0.00 Implementati 2021-05-11 2021-06-07 2021-08-07 Center in Hrazdan community Public Sector Institutions Quotations Envelope on of Kotayq marz of RA NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CARMAC2-CS-15/02 / Assessment of community Component 1: Consultant fodder areas and development IBRD / 83740 Community/Pasture Livestock Prior Qualification Open - International 189,743.63 Signed 2015-05-14 2015-05-15 of pasture management plans Management System Selection and mapping CARMAC2-CS-18/21 / Independent Evaluator for the Consultant Component 2: Value Chain Value Chain Development IBRD / 83740 Post Qualification Open - National 21,111.08 Signed 2018-02-01 2018-02-07 2018-02-15 2018-04-05 2018-03-23 2018-04-19 2018-04-03 2018-05-12 2018-04-03 2018-11-08 Development Component finished sub- Selection projects CARMAC2-CP-CS-18-04 / Component 1: Consultant CW Design for 26 IBRD / 83740 Community/Pasture Livestock Post Qualification Open - National 107,377.40 Signed 2018-03-26 2018-03-23 2018-04-09 2018-05-14 2018-06-13 2018-06-13 2018-08-03 2018-06-16 2018-08-03 2018-12-28 communities Management System Selection CARMAC2-CP-CS-18-03 / Component 1: Consultant CW Supervision for 20 IBRD / 83740 Community/Pasture Livestock Post Qualification Open - National 29,718.47 Signed 2018-03-26 2018-03-26 2018-04-09 2018-05-14 2018-05-25 2018-06-13 2018-06-25 2018-06-25 2018-06-26 2019-09-28 communities Management System Selection Page 5 CARMAC2-CW-18-8/03 / Technical supervision of the quality of const. works of a veterinary service center in Consultant the Hrazdan city community Component 3: Strengthening IBRD / 83740 Post Qualification Open - National 3,583.95 Signed 2018-03-21 2018-04-03 2018-04-04 2018-05-03 2018-05-25 2018-05-15 2018-06-15 2018-05-25 2018-06-19 2018-10-09 of Kotayk marz and of the Public Sector Institutions Selection quality of refurbishment of membranous greenhouses of the Scientific Center of Veg. and Ind. Crops of the MoA RA Component 1: Consultant CARMAC2-CP-CS-18-05 / IBRD / 83740 Community/Pasture Livestock Post Qualification Open - National 0.00 Canceled 2018-08-08 2018-08-10 2018-08-22 2018-09-19 2018-09-24 2018-09-27 2018-12-26 Training for cooperatives Management System Selection CARMAC2-CP-CS-18-06 / Design and auth. supervision for the const. of watering Component 1: Consultant system in pastures of IBRD / 83740 Community/Pasture Livestock Post Qualification Open - National 32,447.07 Signed 2018-11-07 2020-01-21 2018-11-21 2018-12-26 2020-04-13 2019-01-25 2020-05-04 2019-01-28 2020-05-20 2020-01-23 2020-10-05 Ghazanchi, Mets Sepasar and Management System Selection Zuiqaghbyur settlements of Ashotsk community of Shirak marz CARMAC2-CS-19/31 / Independent Evaluator for the Consultant Component 2: Value Chain Value Chain Development IBRD / 83740 Post Qualification Open - National 11,941.36 Completed 2019-08-12 2019-08-14 2019-09-02 2019-10-16 2019-11-05 2019-11-15 2019-11-15 2019-12-20 2019-11-15 2020-06-17 2020-10-27 Development Component finished Selection subprojects CARMAC2-CS-19/34 / Evaluation of the sub-projects (business applications) Consultant Component 2: Value Chain presented within the IBRD / 83740 Post Qualification Open - National 9,024.44 Completed 2019-09-24 2019-09-24 2019-10-15 2019-11-28 2019-12-25 2019-12-28 2020-01-10 2020-02-01 2020-01-14 2020-07-30 2020-04-09 Development framework of Value Chain Selection Development component of the project CARMAC2-CP-CS-20-J-3/03 / CW technical supervision of Component 1: Consultant construction of watering IBRD / 83740 Community/Pasture Livestock Post Qualification Open - National 7,501.87 Signed 2020-03-20 2020-03-20 2020-04-03 2020-04-10 2020-04-30 2020-04-12 2020-06-03 2020-04-19 2020-06-03 2020-10-16 systems in the pastures of 9 Management System Selection communities (settlements) of RA CARMAC2-CP-CS-20-J-4/03 / Technical supervision of construction quality of Component 1: Consultant pasture water supply pipeline IBRD / 83740 Community/Pasture Livestock Post Qualification Open - National 11,966.58 Signed 2020-05-26 2020-06-01 2020-06-10 2020-06-26 2020-06-22 2020-07-07 2020-07-09 2020-07-14 2020-07-09 2021-06-29 systems in 10 Management System Selection communities/settlements of RA CARMAC2-CP-CS-20-J-5/03 / Technical supervision of the construction pasture water supply pipeline systems in Component 1: Consultant Bjni settlement of IBRD / 83740 Community/Pasture Livestock Post Qualification Open - National 1,788.41 Signed 2020-09-22 2020-09-22 2020-09-25 2020-09-29 2020-10-27 2020-10-05 2020-12-09 2020-10-11 2020-12-09 2021-05-08 Charentsavan community of Management System Selection Kotayk marz and Goris city settlement of Goris community of Syuniq CARMAC2-CP-CS-20-J-6/01 / Design and auth. supervision for the const. of Component 1: Consultant watering system in pastures IBRD / 83740 Community/Pasture Livestock Post Qualification Open - National 11,912.77 Signed 2020-12-15 2021-01-20 2020-12-29 2021-01-03 2021-02-16 2021-01-08 2021-03-23 2021-01-16 2021-03-23 2021-03-18 of 6 communities (or Management System Selection community’ settlements) of 3 marzes of RA CARMAC2-CP-CS-21/07 / Trainings of PUCs Component 1: Consultant members/chairmen's and Under IBRD / 83740 Community/Pasture Livestock Post Qualification Open - National 0.00 2021-01-21 2021-02-15 2021-02-11 2021-03-18 2021-03-25 2021-04-13 2021-10-10 community Implementation Management System Selection majors/administrative representatives. CARMAC2-CP-CS-21-J-7/01 / Design of construction of pasture water pipeline systems in Artabuynk and Shatin settlements of the Component 1: Consultant Yeghegis community and the IBRD / 83740 Community/Pasture Livestock Post Qualification Open - National 19,604.79 Signed 2021-02-03 2021-02-03 2021-02-17 2021-02-24 2021-03-22 2021-03-06 2021-04-07 2021-03-15 2021-04-16 2021-05-15 Zedeya settlement of Vayk Management System Selection community of the Vayots Dzor marz and Vardenis community of the Gegharkunik marz, and author supervis CARMAC2-CW-21-8/01 / Design of construction of VSC in Odzun community of Lori marz of RA and author’s Consultant Component 3: Strengthening supervision and design of IBRD / 83740 Post Qualification Open - National 5,763.51 Signed 2021-02-04 2021-02-12 2021-02-19 2021-03-08 2021-03-22 2021-03-13 2021-04-27 2021-03-15 2021-04-28 2021-05-15 Public Sector Institutions construction of animal Selection gathering places in the territory of 70 communities of RA Component 4: Project Consultant CARMAC2-CS-21-39 / Under IBRD / 83740 Coordination and Post Qualification Open - National 0.00 2021-02-10 2021-02-26 2021-02-25 2021-03-26 2021-03-29 2021-04-05 2022-04-20 Impact Assessment Implementation Management Selection CARMAC2-CP-CS-21-J-9/03 / Technical supervision of construction of pasture water Component 1: Consultant supply pipeline systems in IBRD / 83740 Community/Pasture Livestock Post Qualification Open - National 7,987.73 Signed 2021-02-25 2021-03-03 2021-03-07 2021-03-18 2021-03-31 2021-03-24 2021-04-13 2021-03-30 2021-05-06 2021-10-01 Ghazanchi, Mets Sepasar and Management System Selection Zuygaghbyur settlements of Ashotsk community of Shirak marz of RA Page 6 CARMAC2-CW-21-10/01 / Design-estimate documents for construction of a laboratory for providing Consultant veterinary and food safety Component 3: Strengthening Under IBRD / 83740 Post Qualification Open - National 0.00 2021-05-20 2021-06-09 2021-06-03 2021-06-20 2021-06-25 2021-06-27 2022-04-23 services in Torosgyugh Public Sector Institutions Implementation Selection village, Sarapat Community, Shirak Marz, RA as well as author’s supervision during construction INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Contract Type Process Status Teams of Reference Identified/Selected Signed Contract Contract Completion No. (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 4: Project CARMAC2-CS-17/18 / Social IBRD / 83740 Coordination and Post Direct Selection Direct 21,551.33 Signed 2017-12-27 2018-01-20 2018-01-29 2018-01-31 2019-12-31 specialist Management Component 4: Project CARMAC2-CS-17/17 / IBRD / 83740 Coordination and Post Direct Selection Direct 14,367.55 Signed 2017-12-25 2017-12-26 2018-01-29 2018-01-31 2019-12-31 Environmental specialist Management CARMAC2-CS-17/20 / Food Component 2: Value Chain IBRD / 83740 Post Direct Selection Direct 21,285.26 Terminated 2017-12-27 2017-12-28 2018-01-29 2018-01-31 2019-12-31 Safety specialist Development CARMAC2-CS-17/19 / Component 1: Community development IBRD / 83740 Community/Pasture Livestock Post Direct Selection Direct 21,496.49 Terminated 2017-12-27 2017-12-28 2018-01-30 2018-01-29 2018-01-31 2019-12-31 specialist Management System CARMAC2-CS-18/23 / Component 1: Individual Community Development IBRD / 83740 Community/Pasture Livestock Post Consultant Open 0.00 Canceled 2018-04-20 2018-04-10 2018-05-23 2018-06-06 2018-06-13 2018-12-10 Consultant (Assistant) for Management System Selection Gegharkunik Marz CARMAC2-CS-18/24 / Component 1: Individual Community Development IBRD / 83740 Community/Pasture Livestock Post Consultant Open 0.00 Canceled 2018-04-23 2018-05-14 2018-05-26 2018-06-09 2018-06-16 2020-02-06 Specialist Management System Selection CARMAC2-CS-18-27 / Individual Component 2: Value Chain "Value Chain Development" IBRD / 83740 Post Consultant Open 0.00 Canceled 2018-07-31 2018-08-09 2018-09-02 2018-09-16 2018-09-23 2019-09-18 Development (VCD) Component Consultant Selection CARMAC2-CS-18/26 / Consulting services of the Component 4: Project Management Information IBRD / 83740 Coordination and Post Direct Selection Direct 4,670.77 Signed 2018-08-06 2018-08-06 2018-08-06 2018-08-16 2018-12-06 2019-09-30 System (MIS) development, Management implementation and maintenance AM-MOA-114462-CS-INDV / Component 4: Project Individual Selection of CARMAC2 Project IBRD / 83740 Coordination and Post Consultant Limited 29,850.88 Terminated 2019-05-13 2019-05-22 2019-05-20 2019-05-24 2019-05-22 2019-05-30 2019-05-25 2019-05-30 2020-05-24 manager Management Selection CARMAC2-CS-18/25 / CONSULTANT EVALUATING Component 1: Individual THE DEGRADED AREAS OF 24 IBRD / 83740 Community/Pasture Livestock Post Consultant Open 0.00 Canceled 2018-04-20 2018-05-10 2018-05-23 2018-06-06 2018-06-13 2018-09-11 COMMUNITIES THAT HAVE Management System Selection BEEN REHABILITATED CARMAC2-CS-19/30 / THE EVALUATION OF THE NEARBY Component 1: Individual PASTURE AREAS IN TWENTY- IBRD / 83740 Community/Pasture Livestock Post Consultant Limited 3,993.27 Completed 2019-08-06 2019-06-27 2019-08-07 2019-07-11 2019-08-08 2019-07-11 2019-08-10 2019-07-11 2019-10-09 2019-09-12 FOUR COMMUNITIES THAT Management System Selection HAVE BEEN REHABILITATED UNDER CARMAC PROJECT CARMAC2-CS-19/32 / Component 4: Project Establishment of the financial IBRD / 83740 Coordination and Prior Direct Selection Direct 9,451.80 Completed 2019-09-06 2019-09-12 2019-09-16 2019-09-12 2019-11-20 2019-09-16 2020-05-18 2020-05-31 management system for the Management CARMAC2 Project CARMAC2-CS-19/33 / Food Individual Component 2: Value Chain Safety Consultant for VCD IBRD / 83740 Post Consultant Open 5,128.19 Signed 2019-09-06 2019-09-13 2019-10-25 2019-10-22 2019-11-15 2019-11-01 2019-12-20 2019-11-01 2020-06-17 Development component Selection Individual CARMAC2-CS-20/35 / VCD Component 2: Value Chain IBRD / 83740 Post Consultant Open 0.00 Canceled 2019-12-27 2019-12-26 2020-01-16 2020-01-17 2020-01-19 2020-05-30 COMPONENT ASSISTANT Development Selection CARMAC2-CS-20/36 / Component 4: Project Individual Selection of CARMAC2 Project IBRD / 83740 Coordination and Post Consultant Open 6,007.80 Signed 2020-02-06 2020-02-06 2020-02-26 2020-03-12 2020-02-27 2020-03-23 2020-03-01 2020-03-23 2020-05-31 manager Management Selection CARMAC2-CS-20/37 / Component 4: Project Project Financial Management IBRD / 83740 Coordination and Post Direct Selection Direct 35,803.24 Signed 2020-05-18 2020-05-25 2020-05-22 2020-05-25 2020-06-01 2020-06-01 2022-05-31 Consultant Management CARMAC2-CS-17/21 / Component 4: Project Individual Financial management IBRD / 83740 Coordination and Post Consultant Open 0.00 Canceled 2017-12-26 2018-01-18 2018-01-23 2018-01-25 2020-06-13 consultant Management Selection CARMAC2-CS-20/38 / Evaluation of the sub-projects (business applications) Component 2: Value Chain presented within the IBRD / 83740 Post Direct Selection Direct 7,711.12 Completed 2020-09-15 2020-09-18 2020-09-18 2020-09-26 2020-09-27 2020-10-01 2021-01-26 2020-11-11 Development framework of Value Chain Development component of the project Page 7 Sample Procurement Plan (Text in italic font is meant for instruction to staff and should be deleted in the final version of the PP) (This is only a sample with the minimum content that is required to be included in the PAD. The detailed procurement plan is still mandatory for disclosure on the Bank’s website in accordance with the guidelines. The initial procurement plan will cover the first 18 months of the project and then updated annually or earlier as necessary). I. General 1. Bank’s approval Date of the procurement Plan [Original: December 2007]: Revision 15 of Updated Procurement Plan, June 2010] 2. Date of General Procurement Notice: Dec 24, 2006 3. Period covered by this procurement plan: The procurement period of project covered from year June 2010 to December 2012 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: [Thresholds for applicable procurement methods (not limited to the list below) will be determined by the Procurement Specialist /Procurement Accredited Staff based on the assessment of the implementing agency’s capacity.] Procurement Method Prior Review Comments Threshold US$ 1. ICB and LIB (Goods) Above US$ 500,000 All 2. NCB (Goods) Above US$ 100,000 First contract 3. ICB (Works) Above US$ 15 million All 4. NCB (Works) Above US$ 5 million All 5. (Non-Consultant Services) Below US$ 100,000 First contract [Add other methods if necessary] 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. July 9, 2010 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: [Refer to the relevant CDD project implementation document approved by the Bank or delete if not applicable] 4. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan Project XYZ 04/01/2010 issued by 5. Any Other Special Procurement Arrangements: [including advance procurement and retroactive financing, if applicable] 5 ICB works packages will be financed under retroactive financing 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness ( including those that are subject to retroactive financing and advanced procurement) [List the Packages which require Bank’s prior review first and then the other packages] 1 2 3 4 5 6 7 Ref. Descripti Estimat Packages Dome Review Comme No. on ed stic by Bank nts Cost Prefe (Prior / US$ rence Post) million (yes/ no) Summary 82 5 No Prior of the ICB (Works) Summary 43.77 15 No Prior of the ICB (Goods) Summary 64.53 18 No Post 1st of the NCB contrac (Works) t for Prior Review Summary 1.86 4 No Post 1st of the NCB contrac (Goods) t for Prior Review Summary 0.45 1 No Prior of the ICB (Non- Consultant Services) July 9, 2010 III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comments Threshold 1. Competitive Methods (Firms) Above US$ 100,000 2. Single Source (Firms) All 3. Individual Above US$ 50,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: [including advance procurement and retroactive financing, if applicable or delete if not applicable] 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description Estimat Package Review Comment of ed s by Bank s Assignmen Cost (Prior / t US$ Post) million Summary 4.17 7 Prior of number of contracts that will be let under QCBS Summary 0.83 1 Prior CQS of number of contracts that will be let under other July 9, 2010 methods July 9, 2010 PROCUREMENT Kenya : Kenya Youth Employment and Opportunities PLAN General Information Country: Kenya Bank’s Approval Date of the Original Procurement Plan: 2017-02-12 2021-05-24 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P151831 GPN Date: 2017-04-03 Project Name: Kenya Youth Employment and Opportunities Loan / Credit No: IDA / 58120 M Executing Agency(ies): inistry of Public Service, Youth and Gender Affairs WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KE-MPYG-12189-GO-RFB / Strengthening youth policy Under Single Stage - One Procurement of Motor IDA / 58120 development and project Post Request for Bids Open - National 700,000.00 623,868.69 Implementati 2017-04-07 2017-09-15 2017-04-12 2017-05-24 2017-06-23 2017-07-28 2018-01-24 Envelope Vehicles. management on KE-MPYG-12022-GO-RFQ / Strengthening youth policy Pending Request for Single Stage - One Supply and delivery of interim IDA / 58120 development and project Post Limited 75,000.00 0.00 Implementati 2017-05-17 2017-07-12 2018-01-08 Quotations Envelope MIS equipment management on KE-MPYG-12182-GO-RFQ / Strengthening youth policy Pending Procurement of equipment for Request for Single Stage - One IDA / 58120 development and project Post Limited 5,300.00 0.00 Implementati 2017-04-30 2017-06-25 2017-12-22 PCU (Boardroom Chairs and Quotations Envelope management on Lockable Cabinets) KE-MPYG-14305-GO-RFQ / Strengthening youth policy Pending Procurement of ICT Single Stage - One IDA / 58120 development and project Post Request for Bids Open - National 150,000.00 0.00 Implementati 2017-08-07 2017-08-12 2017-09-23 2017-10-23 2017-11-27 2018-05-26 equipment for PCU and Envelope management on targeted Counties. KE-MPYG-53596-GO-RFQ / Strengthening youth policy Pending Request for Single Stage - One Procurement of 40 No tablets IDA / 58120 development and project Post Limited 16,000.00 0.00 Implementati 2018-05-02 2018-06-27 2018-12-24 Quotations Envelope for capturing data for Cycle 2 management on KE-MPYG-53606-GO-RFQ / Strengthening youth policy Pending Procurement of 20 No. Request for Single Stage - One IDA / 58120 development and project Post Limited 14,500.00 0.00 Implementati 2018-05-30 2018-07-25 2019-01-21 Laptops for Cycle two Quotations Envelope management on counties KE-MPYG-88634-GO-RFQ / Strengthening youth policy Pending Purchase of 40 No of tablets Request for Single Stage - One IDA / 58120 development and project Post Limited 31,500.00 0.00 Implementati 2019-01-23 2019-03-20 2019-09-16 for Cycle 3 Counties and 30 Quotations Envelope management on No for Cycle 4 Counties KE-MPYG-88635-GO-RFQ / Strengthening youth policy Pending Request for Single Stage - One Purchase of 10 No IDA / 58120 development and project Post Limited 5,400.00 0.00 Implementati 2019-01-30 2019-03-27 2019-09-23 Quotations Envelope tablets(Rugged) for PCU management on KE-MPYG-53579-GO-DIR / Strengthening youth policy Single Stage - One Procurement of 6 No.Motor IDA / 58120 development and project Post Request for Bids Open - National 420,000.00 0.00 Canceled 2018-04-13 2018-04-18 2018-05-30 2018-06-29 2018-08-03 2019-01-30 Envelope Vehicles for Cycle 2 counties. management Strengthening youth policy Under KE-MPYG-108685-GO-RFQ / Request for Single Stage - One IDA / 58120 development and project Post Limited 2,400.00 0.00 Implementati 2019-04-17 2019-06-12 2019-12-09 4 No Glass Cabinets Quotations Envelope management on Strengthening youth policy Pending KE-MPYG-108687-GO-RFQ / Request for Single Stage - One IDA / 58120 development and project Post Limited 300.00 0.00 Implementati 2019-04-17 2019-06-12 2019-12-09 1 No. Coffee Table Quotations Envelope management on Strengthening youth policy Pending KE-MPYG-108688-GO-RFQ / Request for Single Stage - One IDA / 58120 development and project Post Limited 750.00 0.00 Implementati 2019-04-17 2019-06-12 2019-12-09 2 No. Secretarial desks Quotations Envelope management on Strengthening youth policy Pending KE-MPYG-108689-GO-RFQ / Request for Single Stage - One IDA / 58120 development and project Post Limited 2,960.00 0.00 Implementati 2019-04-17 2019-06-12 2019-12-09 2 No. Workstation (4 way) Quotations Envelope management on KE-MPYG-108690-GO-RFQ / Strengthening youth policy Pending Request for Single Stage - One 1 No. Boardroom table 28 IDA / 58120 development and project Post Limited 5,600.00 0.00 Implementati 2019-04-17 2019-06-12 2019-12-09 Quotations Envelope seater management on Strengthening youth policy Pending KE-MPYG-108691-GO-RFQ / Request for Single Stage - One IDA / 58120 development and project Post Limited 3,600.00 0.00 Implementati 2019-04-17 2019-06-12 2019-12-09 4 No. Workstation (2 way) Quotations Envelope management on Strengthening youth policy Pending KE-MPYG-108692-GO-RFQ / Request for Single Stage - One IDA / 58120 development and project Post Limited 1,000.00 0.00 Implementati 2019-04-17 2019-06-12 2019-12-09 1 No. Reception desk Quotations Envelope management on KE-MPYG-108693-GO-RFQ / Strengthening youth policy Pending Request for Single Stage - One 3 No. High Back Orthopedic IDA / 58120 development and project Post Limited 1,050.00 0.00 Implementati 2019-04-17 2019-06-12 2019-12-09 Quotations Envelope Chairs management on Strengthening youth policy Pending KE-MPYG-108694-GO-RFQ / Request for Single Stage - One IDA / 58120 development and project Post Limited 6,860.00 0.00 Implementati 2019-04-17 2019-06-12 2019-12-09 28 No. Office Chairs Quotations Envelope management on Strengthening youth policy Pending KE-MPYG-108695-GO-RFQ / Request for Single Stage - One IDA / 58120 development and project Post Limited 370.00 0.00 Implementati 2019-04-17 2019-06-12 2019-12-09 2 No. Executive Visitors Chair Quotations Envelope management on Page 1 Strengthening youth policy Pending KE-MPYG-108696-GO-RFQ / Request for Single Stage - One IDA / 58120 development and project Post Limited 720.00 0.00 Implementati 2019-04-17 2019-06-12 2019-12-09 4 No. Secretarial chairs Quotations Envelope management on KE-MPYG-108697-GO-RFQ / Strengthening youth policy Pending Request for Single Stage - One 3 Sets of Visitors Chairs (3 IDA / 58120 development and project Post Limited 630.00 0.00 Implementati 2019-04-20 2019-06-11 2019-12-08 Quotations Envelope Way) management on Strengthening youth policy Pending KE-MPYG-108699-GO-RFQ / Request for Single Stage - One IDA / 58120 development and project Post Limited 475.00 0.00 Implementati 2019-04-21 2019-06-12 2019-12-09 5 No. Coat hangers Quotations Envelope management on Strengthening youth policy Pending KE-MPYG-108700-GO-RFQ / Request for Single Stage - One IDA / 58120 development and project Post Limited 1,440.00 0.00 Implementati 2019-04-20 2019-06-11 2019-12-08 8 No. Visitors chair Quotations Envelope management on Strengthening youth policy Pending KE-MPYG-108701-GO-RFQ / Request for Single Stage - One IDA / 58120 development and project Post Limited 5,040.00 0.00 Implementati 2019-04-22 2019-06-13 2019-12-10 28 No Boardroom chairs Quotations Envelope management on KE-MPYG-108702-GO-RFQ / Strengthening youth policy Pending Request for Single Stage - One 10 No. Filing metallic Cabinet IDA / 58120 development and project Post Limited 3,500.00 0.00 Implementati 2019-04-21 2019-06-12 2019-12-09 Quotations Envelope with four drawers management on KE-MPYG-108703-GO-RFQ / Strengthening youth policy Pending Request for Single Stage - One 5 No. Wooden In and Out tray IDA / 58120 development and project Post Limited 850.00 0.00 Implementati 2019-04-21 2019-06-12 2019-12-09 Quotations Envelope (4 shelves) with stand management on Strengthening youth policy Pending KE-MPYG-108704-GO-RFQ / Request for Single Stage - One IDA / 58120 development and project Post Limited 1,040.00 0.00 Implementati 2019-04-21 2019-06-12 2019-12-09 2 Sets of Filling Racks Quotations Envelope management on KE-MPYG-108705-GO-RFQ / Strengthening youth policy Pending Request for Single Stage - One 3 No. Water dispensers Hot IDA / 58120 development and project Post Limited 840.00 0.00 Implementati 2019-04-23 2019-06-14 2019-12-11 Quotations Envelope and Cold management on KE-MPYG-108706-GO-RFQ / Strengthening youth policy Pending Request for Single Stage - One Supply and fitting of Curtain IDA / 58120 development and project Post Limited 5,800.00 0.00 Implementati 2019-04-23 2019-06-14 2019-12-11 Quotations Envelope shears (all offices) - 100 Mtrs management on KE-MPYG-108707-GO-RFQ / Removal of old Locks and Strengthening youth policy Pending Request for Single Stage - One installation of new locks for IDA / 58120 development and project Post Limited 1,630.00 0.00 Implementati 2019-04-23 2019-06-14 2019-12-11 Quotations Envelope the main door, offices and management on stores - 10 No KE-MPYG-108708-GO-RFQ / Strengthening youth policy Pending Request for Single Stage - One Installation of 2 No. Grill IDA / 58120 development and project Post Limited 520.00 0.00 Implementati 2019-04-22 2019-06-13 2019-12-10 Quotations Envelope doors management on KE-MPYG-108680-GO-RFQ / Strengthening youth policy Pending Request for Single Stage - One Executive desk 2.0 m with IDA / 58120 development and project Post Limited 11,000.00 0.00 Implementati 2019-06-22 2019-08-17 2020-02-13 Quotations Envelope side units and drawers management on KE-MPYG-108681-GO-RFQ / Strengthening youth policy Pending Request for Single Stage - One 4 No. Executive desk 1.8 m IDA / 58120 development and project Post Limited 38,000.00 0.00 Implementati 2019-06-23 2019-08-18 2020-02-14 Quotations Envelope with side units and drawers management on KE-MPYG-135006-GO-RFQ / Procurement of 10 No all Strengthening youth policy Pending Request for Single Stage - One terrain tyres size 275/70/R16 IDA / 58120 development and project Post Limited 4,500.00 0.00 Implementati 2019-10-30 2019-12-25 2020-06-22 Quotations Envelope for vehicles attached to Kitui management on and Turkana Counties KE-MPYG-135010-GO-RFQ / Procurement of 30 No. of ordinary tyres size Strengthening youth policy Pending Request for Single Stage - One 255/70/R16 for vehicles IDA / 58120 development and project Post Limited 10,500.00 0.00 Implementati 2019-10-30 2019-12-25 2020-06-22 Quotations Envelope attached to management on Kiambu,Kisumu,Migori,Momb asa and Nakuru counties KE-MPYG-135011-GO-RFQ / Strengthening youth policy Pending Procurement of 15 No. of Request for Single Stage - One IDA / 58120 development and project Post Limited 6,750.00 0.00 Implementati 2019-11-05 2019-12-31 2020-06-28 tyres size 265/65/R17 for Quotations Envelope management on vehicles at the PCU Nairobi. KE-MPYG-135013-GO-RFQ / Strengthening youth policy Pending Procurement of 7No. of tyres Request for Single Stage - One IDA / 58120 development and project Post Limited 3,150.00 0.00 Implementati 2019-11-05 2019-12-31 2020-06-28 size 9.5/R17.5 for the KYEOP Quotations Envelope management on mini bus KE-MPYG-70217-GO-RFB / Strengthening youth policy Pending Procurement of 34 No of Single Stage - One IDA / 58120 development and project Post Request for Bids Open - National 1,350,000.00 0.00 Implementati 2018-08-31 2018-09-05 2018-10-17 2018-11-16 2018-12-21 2019-06-19 Motor Vehicles for KYEOP -for Envelope management on all cycles. NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KE-MPYG-12206-NC-RFQ / Strengthening youth policy Pending Request for Single Stage - One Printing of Promotional IDA / 58120 development and project Post Open - National 100,000.00 0.00 Implementati 2017-04-12 2017-06-07 2017-12-04 Quotations Envelope materials management on KE-MPYG-130596-NC-RFB / Strengthening youth policy Provision of insurance cover Single Stage - One IDA / 58120 development and project Post Request for Bids Limited 169,730.00 1.84 Signed 2019-09-27 2019-11-19 2019-10-02 2019-12-04 2019-11-13 2019-12-04 2019-12-13 2019-03-06 2020-01-17 2020-06-25 2020-07-15 for LST and CBST trainees - Envelope management All Cycles KE-MPYG-206745-NC-RFQ / Request for Single Stage - One Business Plan Competition IDA / 58120 Support for job creation Post Limited 35,000.00 0.00 Canceled 2020-12-08 2021-02-02 2021-08-01 Quotations Envelope Award Ceremony Page 2 Pending KE-MPYG-217131-NC-RFQ / Request for Single Stage - One IDA / 58120 Support for job creation Post Limited 60,000.00 0.00 Implementati 2021-02-02 2021-02-21 2021-03-14 BPC Award Ceremony Firm Quotations Envelope on CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KE-MPYG-6162-CS-QCBS / Consultancy Services for Strengthening youth policy Quality And Cost- development and design of a IDA / 58120 development and project Post Open - National 250,000.00 246,559.14 Signed 2017-02-09 2017-02-16 2017-03-02 2017-04-15 2018-02-01 2017-05-13 2017-06-12 2017-07-17 2018-05-16 2017-08-21 2018-03-30 2018-08-21 Based Selection Management Information management System (MIS) KE-MPYG-12239-CS-CQS / Strengthening youth policy Consultant Consultancy services for a Pending IDA / 58120 development and project Post Qualification Open - National 13,500.00 0.00 2017-04-07 2017-04-28 2017-06-11 2017-07-11 2017-08-15 2018-02-11 firm to carry out beneficiary Implementation management Selection assessment on catalytic funds KE-MPYG-12280-CS-CQS / Consultancy services for development of a Strengthening youth policy Consultant Pending communication strategy and IDA / 58120 development and project Post Qualification Open - National 98,000.00 0.00 2017-04-10 2017-05-01 2017-06-14 2017-07-14 2017-08-18 2018-02-14 Implementation management of major management Selection communication events under KYEOP KE-MPYG-6667-CS-QCBS / Consultancy Services for Strengthening youth policy provision of Core Business Quality And Cost- IDA / 58120 development and project Prior Open - National 1,400,000.00 0.00 Canceled 2017-02-09 2017-02-21 2017-03-02 2017-04-15 2017-05-13 2017-06-12 2017-07-17 2017-08-21 2018-08-21 Skills Training Providers for Based Selection management the Kenya Youth Employment and Opportunities Project. KE-MPYG-6658-CS-QCBS / Consultancy services for Strengthening youth policy Provision of Life Skills Quality And Cost- IDA / 58120 development and project Prior Open - National 1,400,000.00 0.00 Canceled 2017-02-09 2017-02-16 2017-03-02 2017-04-15 2017-05-13 2017-06-12 2017-07-17 2017-08-21 2018-08-21 Training under Kenya Youth Based Selection management Employment and Opportunities Project. KE-MPYG-14169-CS-QCBS / Strengthening youth policy Consultancy services for Quality And Cost- IDA / 58120 development and project Post Open - International 350,000.00 296,519.12 Signed 2017-05-05 2017-05-09 2017-05-26 2017-07-09 2017-05-09 2017-08-06 2017-09-05 2017-10-10 2017-11-14 2017-11-28 2018-11-14 development of core business Based Selection management skills training curriculum KE-MPYG-14170-CS-QCBS / Consultancy services for Strengthening youth policy Provision of Life Skills Quality And Cost- IDA / 58120 development and project Post Open - International 350,000.00 273,245.89 Signed 2017-05-05 2017-05-09 2017-05-26 2017-07-09 2017-05-09 2017-08-06 2017-09-05 2017-10-10 2017-11-14 2017-11-28 2018-11-14 Training under Kenya Youth Based Selection management Employment and Opportunities Project. KE-MPYG-52520-CS-FBS / Delivery of core business Strengthening youth policy skills training to youth Fixed Budget IDA / 58120 development and project Prior Open - International 6,500,000.00 6,398,006.40 Signed 2018-04-06 2018-04-27 2018-04-03 2018-06-10 2018-07-25 2018-07-08 2018-09-05 2018-08-07 2018-09-06 2018-09-11 2018-10-17 2018-10-16 2018-10-31 2019-10-16 selected to participate in the Selection management Kenya Youth Employment and Opportunities Project (KYEOP) KE-MPYG-52522-CS-FBS / Consultancy Services for Strengthening youth policy Fixed Budget Delivery of life skills training IDA / 58120 development and project Prior Open - International 6,500,000.00 6,332,196.00 Signed 2018-04-09 2018-04-30 2018-03-29 2018-06-13 2018-08-24 2018-07-11 2018-08-13 2018-08-10 2018-09-06 2018-09-14 2018-10-05 2018-10-19 2018-10-30 2019-10-19 Selection to youth selected to management participate in the KYEOP KE-MPYG-68522-CS-QCBS / Strengthening youth policy Monitoring of the Kenya Youth Quality And Cost- IDA / 58120 development and project Prior Open - International 700,000.00 165,341.02 Under Review 2018-08-10 2018-08-31 2018-10-23 2018-10-14 2019-02-04 2018-11-11 2018-12-11 2019-05-22 2019-01-15 2019-10-22 2019-02-19 2020-02-05 2020-02-19 Employment and Based Selection management Opportunities Project KE-MPYG-68861-CS-QCBS / Strengthening youth policy Procurement of a firm to Quality And Cost- IDA / 58120 development and project Prior Open - International 300,000.00 388,084.06 Signed 2018-08-17 2018-09-07 2018-10-26 2018-10-21 2019-02-25 2018-11-18 2018-12-18 2019-07-17 2019-01-22 2020-03-09 2019-02-26 2020-03-31 2020-02-26 manage the innovation Based Selection management challenge KE-MPYG-68524-CS-QCBS / Consultancy services of a firm Strengthening youth policy to conduct an extensive Quality And Cost- IDA / 58120 development and project Prior Open - International 400,000.00 184,631.16 Signed 2018-09-30 2018-10-21 2018-10-14 2018-12-04 2019-02-04 2019-01-01 2019-01-31 2019-05-06 2019-03-07 2019-06-19 2019-04-11 2019-07-19 2020-04-10 beneficiary tracer study of Based Selection management the KYEOP from March 2018 to 2021 KE-MPYG-68867-CS-QCBS / Impact Evaluation for Business Strengthening youth policy Quality And Cost- Plan Competition, Grants and IDA / 58120 development and project Prior Open - International 1,300,000.00 2,135,881.04 Under Review 2018-09-28 2018-10-19 2018-11-20 2018-12-02 2019-04-10 2018-12-30 2019-01-29 2019-06-03 2019-03-05 2019-10-01 2019-04-09 2019-11-05 2020-04-08 Based Selection Business Development management Services. KE-MPYG-118557-CS-QCBS Strengthening youth policy / In-Depth Financial Quality And Cost- IDA / 58120 development and project Post Open - National 120,000.00 110,573.66 Signed 2019-07-01 2020-03-30 2019-07-22 2019-09-04 2020-05-28 2019-10-02 2020-06-30 2019-11-01 2020-07-07 2019-12-06 2020-01-10 2020-09-23 2021-01-09 Management and Based Selection management Management Information Systems Review KE-MPYG-149648-CS-CQS / Consultancy Services for Digital Training on Strengthening youth policy Consultant Government Catalytic Funds IDA / 58120 development and project Post Qualification Open - National 200,000.00 0.00 Canceled 2019-12-27 2020-01-17 2020-01-17 2020-03-01 2020-03-31 2020-05-05 2020-11-01 and Access to Government management Selection Procurement Opportunities (AGPO) to youth KE-MPYG-164235-CS-QCBS / Consultancy Services for Digital Training on Improving youth Quality And Cost- Government Catalytic Funds IDA / 58120 Post Open - National 250,000.00 189,973.63 Signed 2020-03-13 2020-03-18 2020-03-27 2020-05-10 2020-05-14 2020-06-07 2020-06-16 2020-07-07 2020-06-23 2020-08-11 2020-06-26 2020-09-15 2020-07-10 2021-09-15 employability Based Selection and Access to Government Procurement Opportunities (AGPO) to youth Page 3 KE-MPYG-88626-CS-QCBS / Consultancy Services for Digital Delivery of Strengthening youth policy Quality And Cost- Government Catalytic Funds IDA / 58120 development and project Post Open - National 350,000.00 0.00 Canceled 2019-01-24 2019-04-04 2019-02-14 2019-03-30 2019-04-27 2019-05-27 2019-07-01 2019-08-05 2020-08-04 Based Selection and Access to Government management Procurement Opportunities (AGPO) to youth. KE-MPYG-239154-CS-CQS / Consultant Provision of Online Internship Improving labor market Under IDA / 58120 Post Qualification Open - National 250,000.00 0.00 2021-06-10 2021-06-14 2021-07-01 2021-08-14 2021-09-13 2021-10-18 2022-04-16 and Employment Placement information Implementation Selection Services For KYEOP Trainees INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KE-MPYG-12269-CS-INDV / Strengthening youth policy Individual Individual Consultancy Pending IDA / 58120 development and project Post Consultant Limited 15,000.00 0.00 2017-04-07 2017-04-12 2017-05-03 2017-06-07 2017-12-04 services for review of the Implementation management Selection National Youth Policy KE-MPYG-12230-CS-CQS / Strengthening youth policy Individual Pending Individual Consultancy IDA / 58120 development and project Post Consultant Open 25,000.00 0.00 2017-04-27 2017-06-15 2017-07-06 2017-08-10 2018-02-06 Implementation services for Life Skills Training management Selection KE-MPYG-12237-CS-CQS / Strengthening youth policy Individual Consultancy services for an Pending IDA / 58120 development and project Post Consultant Open 25,000.00 0.00 2017-04-27 2017-06-15 2017-07-06 2017-08-10 2018-02-06 individual consultant for Core Implementation management Selection Business Skills training KE-MPYG-6641-CS-INDV / Consultancy services for Strengthening youth policy Individual preparation of IDA / 58120 development and project Post Consultant Open 98,000.00 0.00 Canceled 2017-02-09 2017-03-30 2017-04-20 2017-05-25 2017-11-21 Communication Strategy and management Selection implementation of major KYEOP events. KE-MPYG-14304-CS-INDV / Strengthening youth policy Individual Individual Consultancy for Under IDA / 58120 development and project Post Consultant Limited 35,000.00 63,999.98 2017-05-15 2017-05-20 2017-06-10 2017-07-15 2017-07-28 2018-01-11 development of KYEOP interim Implementation management Selection MIS KE-MPYG-12034-CS-CQS / Strengthening youth policy Individual Consultancy services for a Pending IDA / 58120 development and project Post Consultant Open 72,000.00 0.00 2017-05-18 2017-07-06 2017-07-27 2017-08-31 2018-02-27 Monitoring and Evaluation Implementation management Selection officer. KE-MPYG-12033-CS-CQS / Consultancy services for a Strengthening youth policy Individual Procurement Specialist to IDA / 58120 development and project Prior Consultant Open 43,269.00 78,739.90 Signed 2017-05-18 2017-07-06 2017-07-27 2017-08-07 2017-08-31 2017-08-01 2018-02-27 support the implementing management Selection agencies KE-MPYG-51146-CS-INDV / Design of an innovation challenge for organizations Strengthening youth policy Individual Pending dealing with the hard-to- IDA / 58120 development and project Post Consultant Open 60,000.00 0.00 2018-02-26 2018-04-16 2018-05-07 2018-06-11 2018-12-08 Implementation serve Youth and Terms of management Selection Reference for firm that will implement the challenge KE-MPYG-77912-CS-CDS / Individual Consultant - Strengthening youth policy Procurement support for IDA / 58120 development and project Prior Direct Selection Direct 60,000.00 106,850.63 Signed 2018-09-28 2018-10-23 2018-10-08 2018-12-12 2019-05-17 2019-06-10 KYEOP Implementing management Agencies, KE-MPYG-77911-CS-CDS / Strengthening youth policy Individual Consultancy - IDA / 58120 development and project Prior Direct Selection Direct 72,000.00 129,775.49 Signed 2018-09-27 2018-10-23 2018-10-07 2018-12-11 2019-05-17 2019-06-09 Monitoring and Evaluation management Specialist for KYEOP KE-MPYG-52585-CS-INDV / Strengthening youth policy Individual Consultancy Services for Roll IDA / 58120 development and project Prior Consultant Direct 36,000.00 62,314.56 Signed 2018-04-20 2018-12-14 2018-04-30 2018-05-21 2019-04-15 2018-06-25 2019-05-17 2018-12-22 out and Capacity support management Selection Technical Assistant for KYEOP KE-MPYG-104837-CS-CDS / Development of Interim MIS system - the consultant will develop and embed new modules into the interim Strengthening youth policy management information IDA / 58120 development and project Prior Direct Selection Direct 160,000.00 158,259.20 Signed 2019-03-29 2019-04-08 2019-06-12 2019-05-17 2019-12-09 system to meet the expanding management needs of the project and also offer continued technical assistance to the implementing agencies. KE-MPYG-118556-CS-CDS / Strengthening youth policy Communication Consultant on IDA / 58120 development and project Prior Direct Selection Direct 20,000.00 18,441.68 Signed 2019-09-19 2019-12-04 2019-09-29 2019-11-18 2019-12-03 2020-02-10 2020-05-31 short term basis (4 months) management KE-MPYG-123194-CS-INDV / Engagement of Individual Strengthening youth policy Individual Under Consultant for IDA / 58120 development and project Post Consultant Open - National 72,000.00 0.00 2019-10-02 2020-11-26 2019-11-20 2020-12-22 2019-12-11 2021-02-18 2020-01-15 2020-07-13 Implementation Communication for KYEOP for management Selection a period of one year. KE-MPYG-159134-CS-INDV Individual / MIS Assistant Developer and Improving youth Under IDA / 58120 Post Consultant Limited 65,000.00 0.00 2020-02-17 2020-03-10 2020-02-22 2020-09-24 2020-03-14 2021-01-19 2020-04-18 2021-04-18 Infrastructure Support employability Implementation Selection Consultant KE-MPYG-181809-CS-CDS / Improving youth Under KYEOP Tracer Studies for IDA / 58120 Prior Direct Selection Direct 200,000.00 0.00 2020-09-11 2020-12-11 2020-09-16 2020-12-11 2020-11-20 2021-11-20 employability Implementation Cycle 2 and 3 Page 4 KE-MPYG-88615-CS-INDV- REV / Individual Consultant for a Filed Supervisor to help supervise data collection and Individual Pending implementation of IDA / 58120 Support for job creation Post Consultant Open 60,000.00 0.00 2019-02-25 2019-07-09 2019-07-23 2019-08-27 2020-08-26 Implementation interventions for the Impact Selection Evaluations of Business Development Services and Business Plan Competition KE-MPYG-88615-CS-INDV / Individual Consultant Services(3 years contract) for a Field Supervisor to help Strengthening youth policy Individual supervise the data collection IDA / 58120 development and project Prior Consultant Open 210,000.00 0.00 Canceled 2019-01-25 2019-02-25 2019-03-15 2019-07-03 2019-04-05 2019-05-10 2019-11-06 and implementation of management Selection interventions for the impact evaluations of the Business Development Services and Business Plan Competition. KE-MPYG-123390-CS-INDV / Individual Consultant Services (one year, renewable) for a Field Supervisor to help Individual supervise the data collection Improving youth IDA / 58120 Post Consultant Open 150,000.00 0.00 Canceled 2019-07-18 2019-01-10 2019-09-05 2019-09-26 2019-10-31 2020-04-28 and implementation of employability Selection interventions for the impact evaluations of the Business Development Services and Business Plan Competition. KE-MPYG-200072-CS-INDV Individual Improving youth / Selection of 2000 Individual IDA / 58120 Prior Consultant Limited 1,500,000.00 0.00 Under Review 2020-12-04 2020-12-15 2020-12-09 2021-02-02 2020-12-16 2021-01-06 2022-01-06 employability Master Craftsmen as IC Selection KE-MPYG-206748-CS-CDS / Strengthening youth policy Under Impact Evaluation Field IDA / 58120 development and project Post Direct Selection Direct 78,000.00 0.00 2020-12-11 2020-11-12 2020-12-21 2021-02-24 2021-08-23 Implementation Coordinator management KE-MPYG-173269-CS-CDS / PRIVATE SECTOR Improving youth IDA / 58120 Prior Direct Selection Direct 2,800,000.00 0.00 Canceled 2020-05-12 2020-06-11 2020-05-22 2020-07-26 2021-07-26 ORGANIZATION FOR employability PLACEMENT OF YOUTH KE-MPYG-230272-CS-INDV Strengthening youth policy Individual Under / Engagement of Impact IDA / 58120 development and project Post Consultant Limited 78,000.00 0.00 2021-04-30 2021-06-15 2021-05-05 2021-05-26 2021-06-30 2021-12-27 Implementation Evaluation Field Coordinator management Selection Page 5 Procurement Plan Urban Development Project July 9, 2010 PROCUREMENT Kyrgyz Republic : Urban Development Project PLAN General Information Country: Kyrgyz Republic Bank’s Approval Date of the Original Procurement Plan: 2017-02-23 2021-05-26 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P151416 GPN Date: Project Name: Urban Development Project Loan / Credit No: TF / 19293, IDA / 57620, IDA / D1010, TF / A1993 Community Development and Investment Agency Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned IDA-UDP-CW-2017-3 / Component A: Urban Single Stage - One 2018-02- Improvement of street IDA / 57620 Post Request for Bids Open - National 150,000.00 144,840.63 Signed 2017-05-21 2017-05-19 2017-05-26 2017-07-07 2017-06-19 2017-07-27 2017-07-14 2017-08-31 2017-09-04 Development Envelope 27 lightning in Toktogul/ IDA-UDP-CW-17-1 / "Rehabilitation of water supply Component A: Urban Single Stage - One 3,321,894.4 2018-08- IDA / 57620 Post Request for Bids Open - National 3,800,000.00 Signed 2017-10-17 2017-10-20 2017-10-22 2017-12-03 2017-11-21 2018-01-02 2018-03-27 2018-02-06 2018-04-20 system in Kerben city, Djalal- Development Envelope 5 05 Abad oblast" (2 lots). IDA-UDP-CW-2017-4 / Component A: Urban Request for Single Stage - One 2019-01- Improvement of street IDA / 57620 Post Open - National 190,000.00 0.00 Canceled 2018-02-06 2018-02-11 2018-03-24 2018-04-23 2018-05-28 Development Proposals Envelope 10 lightning in Balykchy IDA-UDP-CW-2018-5 / Construction works of Component A: Urban Single Stage - One 2019-02- IDA / 57620 Post Request for Bids Open - National 959,126.00 849,451.05 Signed 2018-04-29 2018-05-04 2018-05-04 2018-06-15 2018-06-25 2018-07-15 2018-09-11 2018-08-19 2018-10-19 Aytmatov school, Balykchy Development Envelope 15 city. IDA-UDP-CW-2018-6 / Component A: Urban Single Stage - One 2019-02- Construction works of IDA / 57620 Post Request for Bids Open - National 856,014.00 884,766.49 Signed 2018-04-29 2018-05-04 2018-05-04 2018-06-15 2018-06-25 2018-07-15 2018-09-04 2018-08-19 2018-10-19 Development Envelope 15 Toktogul school, Toktogul city IDA-UDP-CW-2018-2 / Rehabilitation of water supply Component A: Urban Single Stage - One 3,194,335.0 2019-11- IDA / 57620 Post Request for Bids Open - National 4,250,000.00 Signed 2018-04-25 2018-05-16 2018-05-04 2018-06-15 2018-06-11 2018-07-15 2018-07-12 2018-08-19 2018-09-01 system in Sulyukta city Batken Development Envelope 4 30 oblast (5 Lots) IDA-UDP-CW-2018-7 / Construction works of Jakypov Component A: Urban Single Stage - One 2019-05- school and Ak-Tilek TF / A1993 Post Request for Bids Open - National 823,834.00 740,789.72 Signed 2018-08-10 2018-07-27 2018-08-15 2018-09-26 2018-09-04 2018-10-26 2018-10-26 2018-11-30 2018-12-21 Development Envelope 29 kindergarten, Balykchy city (2 Lots) IDA-UDP-CW-2018-8 / Construction works of Component A: Urban Single Stage - One 1,154,757.6 2019-05- Bokonbaev school and Archa- TF / A1993 Post Request for Bids Open - National 1,314,328.00 Signed 2018-08-10 2018-07-27 2018-08-15 2018-09-26 2018-09-04 2018-10-26 2018-10-19 2018-11-30 2018-12-21 Development Envelope 5 29 Beshik kindergarten, Toktogul city (2 Lots) IDA-UDP-CW-2021-1 / Component A: Urban 2021-08- Rehabilitation of water supply IDA / 57620 Prior Direct Selection Direct 329,000.00 0.00 Canceled 2020-12-28 2021-01-02 2021-02-06 Development 05 system in Sulyukta (Phase 2) IDA-UDP-CW-2021-2 / Component A: Urban 2021-08- Rehabilitation of water supply IDA / 57620 Prior Direct Selection Direct 255,495.00 0.00 Canceled 2020-12-28 2021-01-02 2021-02-06 Development 05 system in Sulyukta (Phase 2) IDA-UDP-CW-2021-1/1 / Component A: Urban 2021-08- Additional extension of the IDA / 57620 Post Direct Selection Direct 329,000.00 313,940.62 Signed 2021-01-13 2021-01-13 2021-01-18 2021-01-13 2021-02-22 2021-02-15 Development 21 Sulukta water supply network IDA-UDP-CW-2021-2/2 / Component A: Urban 2021-08- Additional extension of the IDA / 57620 Post Direct Selection Direct 255,495.00 243,797.14 Signed 2021-01-13 2021-01-13 2021-01-18 2021-01-13 2021-02-22 2021-02-15 Development 21 Sulukta water supply network IDA-UDP-SHOPPING-WORKS- Pending 2021-1 / Repair of fencing of Component A: Urban Request for Single Stage - One Other (with field 2021-08- IDA / 57620 Post Open - National 20,000.00 0.00 Implementat 2021-07-09 2021-07-22 Ak-Tilek kindergarten Development Quotations Envelope for explanation) 31 ion territory GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ARIS-UDP-G-18-1 / Purchase of special machinery (back loading waste Component A: Urban Single Stage - One TF / A1993 Post Request for Bids Open - National 150,000.00 131,057.90 Completed 2018-08-10 2018-08-10 2018-08-17 2018-09-28 2018-09-07 2018-10-28 2018-12-02 2018-10-23 2019-05-31 2019-01-31 machinery) for Toktogul, Development Envelope Kerben, Balykchy and Sulyukta towns IDA-UDP-G-2020-1 / Purchase of computer Component A: Urban Request for Single Stage - One IDA / D1010 Post Open - National 5,500.00 0.00 Canceled 2020-12-19 2020-12-16 2021-02-13 2021-08-12 equipment for billing systems Development Quotations Envelope for municipalities ( Sulukta) IDA-UDP-G-2020-2 / Purchase of furniture Component A: Urban Request for Single Stage - One equipment for input of billing IDA / D1010 Post Open - National 1,500.00 0.00 Canceled 2020-12-19 2020-12-16 2021-02-13 2021-08-12 Development Quotations Envelope systems for municipalities (Sulyukta) IDA-UDP-NCB-GOODS-2020- Under 6 / Purchase of special Component A: Urban Single Stage - One IDA / D1010 Post Request for Bids Open - National 250,000.00 0.00 Implementati 2020-12-14 2020-12-18 2020-12-19 2020-12-21 2021-01-30 2021-01-15 2021-03-01 2021-04-05 2021-10-02 equipment for cities Sulukta, Development Envelope on Kerben, Balykchy,Toktogul Page 1 IDA-UDP-NCB-GOODS-2020- Under 4 / Purchase of furniture for Component A: Urban Single Stage - One IDA / D1010 Post Request for Bids Open - National 210,000.00 208,075.19 Implementati 2020-12-14 2020-12-18 2020-12-19 2020-12-21 2021-01-30 2021-01-22 2021-03-01 2021-02-15 2021-04-05 2021-10-02 schools and kindergarten in Development Envelope on the city Balykchy,Toktogul IDA-UDP-GOODS-2020-5 / Purchase of equipment and Component A: Urban Request for Single Stage - One inventory for schools and IDA / D1010 Post Open - National 20,000.00 23,130.89 Signed 2020-12-19 2020-12-16 2021-02-13 2021-02-15 2021-08-12 Development Quotations Envelope kindergartens in the city Toktogul, Balykchy IDA-UDP-G-2020-1-RT1 / Pending Purchase of computer Component A: Urban Request for Single Stage - One IDA / 57620 Post Open - National 5,500.00 0.00 Implementati 2021-02-02 2021-03-30 2021-09-26 equipment for billing systems Development Quotations Envelope on for municipalities ( Sulukta) IDA-UDP-G-2020-2-RT1 / Purchase of furniture Pending Component A: Urban Request for Single Stage - One equipment for input of billing IDA / 57620 Post Open - National 1,500.00 0.00 Implementati 2021-02-02 2021-03-30 2021-09-26 Development Quotations Envelope systems for municipalities on (Sulyukta) IDA-UDP-NCB-GOODS-2021- 1 / Purchase of special Under Component A: Urban Single Stage - One equipment for cities Sulukta, IDA / 57620 Post Request for Bids Open - National 356,000.00 0.00 Implementati 2021-03-26 2021-03-26 2021-03-31 2021-03-26 2021-05-12 2021-06-11 2021-07-16 2022-01-12 Development Envelope Kerben, Balykchy,Toktogul on (#Lot4) IDA-UDP-G-2021-1 / Under Purchase of labarator Component A: Urban Request for Single Stage - One IDA / 57620 Post Open - National 7,000.00 0.00 Implementati 2021-03-29 2021-03-26 2021-05-24 2021-11-20 equipment for Sulyukta and Development Quotations Envelope on Kerben towns IDA-UDP-G-2021-2 / Purchase of safety signs for Under Component A: Urban Request for Single Stage - One schools and kindergartens in IDA / 57620 Post Open - National 2,500.00 0.00 Implementati 2021-05-25 2021-06-02 2021-07-20 2022-01-16 Development Quotations Envelope the cities of Balykchy and on Toktogul Pending IDA-UDP-GOODS-2021-2 / Component A: Urban Request for Single Stage - One IDA / 57620 Post Open - National 10,000.00 0.00 Implementati 2021-07-09 2021-07-22 2021-08-21 Supply of furniture for schools Development Quotations Envelope on IDA-UDP-GOODS-2021-3 / Pending Supply of office equipment Component A: Urban Request for Single Stage - One IDA / 57620 Post Open - National 90,000.00 0.00 Implementati 2021-07-09 2021-07-24 2021-08-23 and other for schools and Development Quotations Envelope on kindergartens NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual UDP PPG-FBS-2015-3 / Preparation of Feasibility Component A: Urban Fixed Budget Studies and Detailed Designs TF / 19293 Prior Open - International 0.00 346,000.00 Signed 2015-12-22 2016-01-02 Development Selection of water supply systems in Sulukta and Kerben UDP PPG-QCBS-2016-4 / Preparation of Feasibility Studies and Designs for Improved Seismic Safety and Component A: Urban Quality And Cost- IDA / 57620 Prior Open - International 0.00 647,522.22 Signed 2016-11-10 2016-11-15 Energy Efficiency of Schools Development Based Selection and Kindergartens and Technical Supervision of construction. ARIS-AUDIT-LCS-2017-1 / Component C: Least Cost IDA / 57620 Post Open - International 60,000.00 71,433.00 Signed 2017-10-17 2017-10-09 2017-11-07 2018-03-12 2017-12-21 2018-03-28 2018-01-18 2018-04-18 2018-02-17 2018-04-18 2018-03-24 2018-04-23 2018-04-28 2018-04-26 2018-10-25 Audit of project funds Implementation Support Selection IDA-UDP-CS-CQS-2018-1 / Consultant Component A: Urban Contract supervision for IDA / 57620 Post Qualification Open - National 150,000.00 168,921.90 Signed 2018-10-03 2018-10-31 2018-10-24 2018-11-02 2018-12-07 2018-12-03 2019-01-06 2018-12-14 2019-02-10 2018-12-14 2019-08-09 Development schools local company Selection IDA-UDP-CQS-2018-2 / Consultants services to carry out hydrogeological studies of Consultant Component A: Urban springs pinching out on the IDA / 57620 Post Qualification Open - National 20,000.00 0.00 Canceled 2019-03-05 2019-03-14 2019-03-26 2019-03-19 2019-05-09 2019-06-08 2019-07-13 2020-01-09 Development left bank of the Padysha-Ata Selection river in Kerben town, Jalal- Abad oblast Consultant IDA-UDP-CQ-2019-3 / Component A: Urban IDA / 57620 Post Qualification Open - National 35,000.00 0.00 Canceled 2020-01-30 2020-02-20 2020-04-04 2020-05-04 2020-06-08 2020-12-05 Impact Assesment Development Selection INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual UDP-ECAPDEV-CS-2015-1 / Consultancy Services for the Results Assessment of the Component A: Urban Urban Development Project TF / 19293 Prior Direct Selection Direct 0.00 43,758.68 Signed 2015-07-01 Development (UDP) and Bishkek and Osh Urban Infrastructure Project (BOUIP) Page 2 IDA-UDP-CS-IC-17-1 / Component A: Urban Consulatnt for development of IDA / 57620 Post Direct Selection Direct 3,000.00 3,936.30 Completed 2017-05-14 2018-05-18 2017-05-24 2017-05-12 2017-07-28 2017-05-15 2018-01-24 2017-08-31 Development streetlightning design Individual IDA-UDP-CS-IC-2017-2 / Component A: Urban IDA / D1010 Post Consultant Open 18,530.00 5,947.69 Signed 2017-05-28 2018-05-17 2017-07-16 2018-04-10 2017-08-06 2018-04-10 2017-09-10 2018-04-23 2018-03-09 Resident engineer in Kerben Development Selection Individual IDA-UDP-CS-IC-2017-3 / Component A: Urban IDA / 57620 Post Consultant Open 18,530.00 3,018.73 Signed 2017-05-28 2018-05-17 2017-07-16 2018-09-05 2017-08-06 2018-09-05 2017-09-10 2018-09-13 2018-03-09 Resident engineer in Sulyukta Development Selection IDA-UDP-CS-IC-2017-4 / Individual Component A: Urban Assistant resident engineer in IDA / D1010 Post Consultant Open 8,824.00 4,758.15 Signed 2017-05-28 2018-05-18 2017-07-16 2018-04-10 2017-08-06 2018-04-10 2017-09-10 2018-04-23 2018-03-09 Development Kerben Selection IDA-UDP-CS-IC-2017-5 / Individual Component A: Urban Assistant resident engineers IDA / D1010 Post Consultant Open 8,824.00 2,082.41 Signed 2017-05-28 2018-05-18 2017-07-16 2018-09-05 2017-08-06 2018-09-05 2017-09-10 2018-09-13 2018-03-09 Development in Sulyukta Selection Individual IDA-UDP-IC-2018-2 / Social Component B: Institutional IDA / 57620 Post Consultant Open 11,118.00 5,146.54 Signed 2018-06-29 2018-06-01 2018-11-18 2018-04-10 2018-12-09 2018-04-10 2019-01-13 2018-04-16 2019-07-12 mobilizers Strengthening Selection Individual IDA-UDP-IC-2018-3 / Social Component B: Institutional IDA / 57620 Post Consultant Open 11,118.00 2,185.97 Signed 2018-07-01 2018-05-16 2018-08-19 2018-09-05 2018-09-09 2018-09-12 2018-10-14 2018-09-13 2019-04-12 mobilizers Strengthening Selection IDA-UDP-IC-2018-11 / Individual Component C: Strengthening of technical IDA / 57620 Post Consultant Open 100,000.00 104,946.40 Terminated 2018-02-06 2018-01-17 2018-03-27 2018-04-18 2018-04-17 2018-04-16 2018-05-22 2018-04-30 2018-11-18 Implementation Support supervision Selection IDA-UDP-SSS-17-4 / Component A: Urban Consulatnt for author IDA / 57620 Post Direct Selection Direct 1,500.00 1,371.78 Completed 2017-09-06 2017-09-07 2017-09-27 2017-09-21 2017-09-28 2017-09-28 2018-03-30 2018-03-03 Development supervision Toktogul IDA-UDP-SSS-18-1 / Component A: Urban Consulatnt for author IDA / 57620 Post Direct Selection Direct 1,500.00 1,371.78 Completed 2017-09-06 2018-05-18 2017-09-26 2018-04-02 2018-02-28 2018-04-02 2018-09-30 2018-09-30 Development supervision Balykchy IDA-UDP-IC-18-18 / Individual Consultant on improving the Component B: Institutional IDA / 57620 Post Consultant Open 40,000.00 48,310.29 Terminated 2018-04-04 2018-06-01 2018-06-29 2018-07-09 2018-07-20 2018-07-20 2018-08-24 2018-08-01 2019-02-20 activity of the water utilities of Strengthening Selection Kerben, Sulukta IDA-UDP-IC-18-17 / Local Individual consultant on improving the Component B: Institutional IDA / 57620 Post Consultant Open 11,600.00 6,955.62 Completed 2018-04-04 2018-06-01 2018-05-23 2018-08-10 2018-06-13 2018-08-27 2018-07-18 2018-09-04 2019-01-14 2019-11-30 activity of the water utilities of Strengthening Selection Kerben, Sulukta IDA-UDP-IC-2017-1 / Individual Contract supervision for Component B: Institutional IDA / 57620 Post Consultant Open 6,500.00 1,575.93 Completed 2017-06-15 2017-10-01 2017-08-26 2017-10-10 2017-09-16 2017-10-10 2017-11-01 2017-11-01 2018-03-31 2018-03-30 lightning/Electrical engineer Strengthening Selection in Toktogul city IDA-UDP-IC-2018-17 / Individual Consultant for author Component A: Urban TF / A1993 Post Consultant Limited 7,500.00 12,987.62 Signed 2018-05-31 2018-05-24 2018-06-05 2018-06-20 2018-06-26 2018-06-20 2018-07-31 2018-06-20 2019-10-31 supervision in Kerben city Development Selection Djalal-Abad oblast IDA-UDP-IC-2018-18 / Individual Consultant for author Component A: Urban TF / A1993 Post Consultant Limited 7,500.00 12,627.73 Signed 2018-05-31 2018-05-24 2018-06-05 2018-06-20 2018-06-26 2018-06-20 2018-08-01 2018-06-20 2020-01-31 supervision in Sulyukta city Development Selection Batken oblast IDA-UDP-IC-2018-1 / Individual Contract supervision for Component B: Institutional IDA / 57620 Post Consultant Open 6,500.00 6,911.70 Completed 2018-05-18 2018-03-01 2018-07-06 2018-03-30 2018-07-27 2018-03-30 2018-08-31 2018-04-02 2019-02-27 2018-12-31 lightning/Electrical engineer Strengthening Selection in Balykchy city IDA-UDP-IC-2018-25 / Individual Component A: Urban International consultant for IDA / 57620 Post Consultant Open 50,000.00 21,035.00 Signed 2018-10-03 2018-10-30 2018-11-21 2018-11-16 2018-12-12 2018-12-24 2019-01-16 2018-12-28 2019-07-15 Development seismic Selection IDA-UDP-IC-2018-26 / Individual Component A: Urban international consultant on IDA / 57620 Post Consultant Open 50,000.00 32,571.00 Signed 2018-10-03 2018-10-30 2018-11-21 2018-11-16 2018-12-12 2018-12-27 2019-01-16 2018-12-28 2019-07-15 Development energy efficiency Selection IDA-UDP-CS-DS-2018-1 / Component A: Urban Local consulatnt for author IDA / 57620 Post Direct Selection Direct 61,500.00 87,093.37 Signed 2018-10-03 2018-12-06 2018-10-13 2018-10-25 2018-12-17 2018-12-17 2019-06-15 Development supervision for school IDA-UDP-IC-2018-21 / Individual Component B: Institutional Consultant on legal zoning IDA / 57620 Post Consultant Open 10,230.00 0.00 Canceled 2018-10-05 2018-11-29 2018-11-23 2018-12-14 2019-01-18 2019-07-17 Strengthening and land use. (Consultant#3) Selection IDA-UDP-IC-2018-22 / Consultant on planning socio- economic development, local Individual Component B: Institutional governance and citizen IDA / 57620 Post Consultant Open 15,750.00 0.00 Canceled 2018-10-05 2018-12-19 2018-11-23 2018-12-14 2019-01-18 2019-07-17 Strengthening participation in the decision- Selection making process (Consultant#1 Team Leader) IDA-UDP-IC-2018-23 / Individual Component B: Institutional Consultant on spatial IDA / 57620 Post Consultant Open 15,000.00 0.00 Canceled 2018-10-05 2018-11-29 2018-11-23 2018-12-14 2019-01-18 2019-07-17 Strengthening planning. (Consultant #2) Selection IDA-UDP-IC-2018-28 / Local Individual Component A: Urban consultant to adapt the IDA / 57620 Post Consultant Open 8,000.00 3,582.18 Completed 2018-11-30 2018-12-04 2019-01-18 2019-02-11 2019-02-08 2019-02-11 2019-03-15 2019-02-12 2019-09-11 2020-07-31 Development Manual Selection IDA-UDP-IC-2018-29 / Individual International consultant on Component A: Urban IDA / 57620 Post Consultant Open 60,000.00 26,468.00 Signed 2018-12-07 2018-12-10 2019-01-25 2019-01-30 2019-02-15 2019-02-11 2019-03-22 2019-02-12 2020-03-21 Strengthening of techncial Development Selection supervision Page 3 IDA-UDP-CS-DS-2018-2 / International consultant - advisor on construction Component A: Urban IDA / 57620 Post Direct Selection Direct 15,000.00 0.00 Canceled 2018-10-05 2018-10-15 2018-12-19 2019-06-17 technical supervision of water Development supply projects in Kerben and Sulyukta towns IDA-UDP-IC-2018-31 / Individual Technical support consultant Component B: Institutional IDA / 57620 Post Consultant Open 15,000.00 24,550.00 Signed 2018-12-25 2018-12-19 2019-02-12 2019-02-07 2019-03-05 2019-02-11 2019-04-09 2019-02-12 2019-10-06 of the UDP on water supply Strengthening Selection projects IDA-UDP-IC-2018-32 / Individual Consultant on improving the Component A: Urban IDA / 57620 Post Consultant Open 50,000.00 36,457.00 Completed 2018-12-20 2018-12-19 2019-02-07 2018-12-04 2019-02-28 2018-12-27 2019-04-04 2018-12-28 2019-10-01 2019-11-30 activity of the water utilities of Development Selection Kerben, Sulukta IDA-UDP-IC-2018-27 / Individual Component A: Urban Consultant on legal issues IDA / 57620 Post Consultant Open 7,500.00 0.00 Canceled 2018-11-12 2018-11-29 2018-12-31 2019-01-21 2019-02-25 2019-08-24 Development (Consultant#4) Selection Individual IDA-UDP-IC-2018-33 / Component A: Urban IDA / 57620 Post Consultant Open 13,500.00 0.00 Canceled 2018-12-20 2018-12-27 2019-02-07 2019-02-28 2019-04-04 2019-10-01 lawyer (Consultant#4) Development Selection IDA-UDP-IC-2019-22 / Consultant on planning socio- economic development, local Component B: Institutional governance and citizen IDA / 57620 Post Direct Selection Direct 15,750.00 12,074.00 Completed 2019-03-05 2019-03-18 2019-03-15 2019-03-20 2019-05-19 2019-04-01 2019-11-15 2019-12-25 Strengthening participation in the decision- making process (Consultant#1 Team Leader) IDA-UDP-IC-2019-23 / Component B: Institutional Consultant on spatial IDA / 57620 Post Direct Selection Direct 15,000.00 11,146.29 Completed 2019-03-05 2019-03-18 2019-03-15 2019-03-20 2019-05-19 2019-03-25 2019-11-15 2019-12-25 Strengthening planning. (Consultant #2) IDA-UDP-IC-2019-21 / Component B: Institutional Consultant on legal zoning IDA / 57620 Post Direct Selection Direct 10,230.00 8,917.03 Completed 2019-03-05 2019-03-18 2019-03-15 2019-03-20 2019-05-19 2019-03-29 2019-11-15 2019-12-25 Strengthening and land use. (Consultant#3) IDA-UDP-IC-2019-33 / Component B: Institutional IDA / 57620 Post Direct Selection Direct 13,500.00 12,074.00 Completed 2019-03-05 2019-03-18 2019-03-15 2019-03-20 2019-05-19 2019-04-01 2019-11-15 2019-12-25 lawyer (Consultant#4) Strengthening IDA-UDP-IC-2019-35 / Individual Component B: Institutional Institutional Development IDA / 57620 Post Consultant Open 17,000.00 28,627.81 Signed 2019-05-06 2019-05-08 2019-06-24 2019-06-21 2019-07-15 2019-06-24 2019-08-19 2019-07-01 2020-02-15 Strengthening Specialist Selection Individual IDA-UDP-IC-2019-37 / Component A: Urban IDA / 57620 Post Consultant Limited 3,750.00 4,350.45 Signed 2019-07-12 2019-08-01 2019-07-17 2019-09-02 2019-08-07 2019-09-05 2019-09-11 2019-09-09 2020-03-09 Hydrogeologist Development Selection IDA-UDP-IC-2019-39 / Individual Component A: Urban Electrical and mechanical IDA / 57620 Post Consultant Limited 7,500.00 4,372.19 Completed 2019-07-12 2019-08-01 2019-07-17 2019-09-02 2019-08-07 2019-09-05 2019-09-11 2019-09-05 2020-03-09 2020-08-31 Development engineer Selection IDA-UDP-SSS-19-1 / Consulting services for Component A: Urban amending previously IDA / 57620 Post Direct Selection Direct 10,000.00 10,384.65 Signed 2019-10-31 2020-02-27 2019-11-10 2019-11-04 2020-01-14 2019-11-13 2020-07-12 Development developed Design and Estimate Documentation Individual IDA-UDP-IC-2020-1 / Civil Component B: Institutional IDA / 57620 Post Consultant Limited 2,700.00 20,647.16 Signed 2020-02-04 2020-02-03 2020-02-09 2020-01-31 2020-03-01 2020-02-04 2020-04-05 2020-02-04 2020-10-02 Engineer Strengthening Selection Individual IDA-UDP-IC-2019-38 / Component A: Urban IDA / 57620 Post Consultant Limited 3,750.00 0.00 Canceled 2019-07-12 2019-07-17 2019-08-07 2019-09-11 2020-03-09 Quality control Engineer Development Selection IDA-UDP-SSS-2020-3 / Component C: Under IDA / D1010 Post Direct Selection Direct 18,000.00 0.00 2020-12-28 2020-12-25 2021-01-07 2021-03-13 2021-09-09 Impact Assesment Implementation Support Implementation IDA-UDP-SSS-21-1 / Consulting services for author supervision of the additional Component A: Urban Under IDA / D1010 Post Direct Selection Direct 20,000.00 0.00 2021-05-04 2021-05-17 2021-05-07 2021-05-16 2021-09-06 expansion of the water supply Development Implementation network in the cities of Kerben and Sulukta (phase 2) IDA-UDP-IC-2021-1 / Consultant for the Individual Component A: Urban Under environmental and sanitary IDA / 57620 Post Consultant Limited 3,000.00 0.00 2021-05-21 2021-06-01 2021-05-26 2021-06-16 2021-07-21 2022-01-17 Development Implementation assessment of the sewage Selection system of the city of Sulukta Page 4 PLAN DE PASSATION DE MARCHÉS (Partie Textuelle) Information sur le Projet : Le Projet de Résilience et de Compétitivité Agricole est un Projet d’un coût global de $US259.6 millions dont $US200 millions de L’Association international pour le développement (IDA) pour un montant de $US50 millions, la Facilité pour la mise à échelle (SUF) pour un montant de $US150 millions. La contribution du Gouvernement du Burkina Faso est de $US13 millions, celle des bénéficiaires de $US29.4 millions. Il est attendu des institutions financières partenaires un co-financement des sous- projets de l’ordre de $US17.2 millions. L’objectif de développement du Projet est d’accroître la productivité du secteur agricole et l’accès au marché pour les petits producteurs et les petites et moyennes entreprises (PME) dans les chaines de valeur ciblées. Il est organisé autour de trois composantes opérationnelles qui sont : (i) amélioration de la productivité agricole ; (ii) amélioration de la compétitivité et accès au marché et (iii) le développement de l’agribusiness par la promotion du secteur privé. Agence d’exécution du Projet : Projet de Développement et de Compétitivité Agricole Date du plan de passation des marchés : Juin 2019 Période couverte par ce plan de passation des marchés : Juillet 2019 au 31 Décembre 2020 Préambule Conformément au paragraphe 5.9 du “Règlement de Passation des Marchés pour les Emprunteurs sollicitant le Financement de Projets d’Investissement (FPI)” (Juillet 2016 tel que révisé en Novembre 2017 et Aout 2018) (“Règlement de Passation des Marchés”) l’Emprunteur utilise les outils électroniques de planification et de suivi de la passation des marchés (STEP) pour préparer, valider et actualiser ses plans de passation des marchés et effectuer toutes les transactions liées à la passation des marchés du projet. Cette partie textuelle ainsi que les tableaux du plan de passation des marchés dans STEP constituent le plan de passation des marchés du projet. Les conditions suivantes s'appliquent à toutes les activités de passation de marchés du plan de passation de marchés. Les autres éléments du plan de passation des marchés tels que requis au paragraphe 4.4 du Règlement de passation des marchés sont énoncés dans STEP. Les Dossiers types d’appel d’offres publiés par la Banque devront être utilisés pour tous les contrats soumis à la concurrence internationale ainsi que pour tous les autres contrats spécifiés dans les tableaux du plan de passation des marchés inclus dans STEP. Procédures nationales de passation des marchés : En accord avec les paragraphes 5.3 à 5.6 du Règlement de passation des marchés, au cas où la procédure de passation des marchés est retenue (telle que spécifiée dans les tableaux du plan de passation des marchés inclus dans STEP), les procédures de passation de marchés du pays considéré peuvent être appliquées. Si l’Emprunteur utilise ses propres procédures d’appel d’offres national ouvert telles qu’énoncées dans le code des marchés publics (Décret N°2017- 0049/PRES/PM/MINEFID portant procédures de passation, d’exécution et de règlement des marchés publics et des délégations de service public le 1er février 2017), ainsi que les DAOs standards nationaux, ces arrangements sont soumis aux dispositions du paragraphe 5.4 du Règlement de passation des marchés et aux conditions suivantes : (i)Les clauses ci-dessous du décret visé ci-dessus ne sont pas pplicables  108 relative à la notion d’offre anormalement basse ou haute (inférieure ou supérieure à 15 % de la moyenne du montant prévisionnel du client et de la moyenne des offres reconnues conformes  111 à 115 sur la marge de préférence nationale, communautaire et locale  145 signature d’un nouveau marché lorsque la variation du montant dun marché et de plus de 30 % du montant initial (ii) Les dispositions ci-dessous des DAOs pour marchés de travaux et fournitures ne seront pas applicables  IS 32.3 (a) pour les marchés de travaux et 33.3 (b) pour les marchés de fournitures et d’équipement relatives au rejet de l’offre si elle est rectifiee de plus ou moins 15 %  IS 32.6 marché de travaux et 33.6 marché de fourniture et équipement relatives à la notion d’offres anormalement basses (iii) le dossier d’appel d’offres/à propositions devront avoir une disposition obligeant le Soumissionnaire/Proposant présentant une Offre/Proposition à déposer un agrément signé, qui sera joint à tout contrat éventuel, pour confirmer qu’il applique et respecte les Directives de la Banque pour la lutte contre la corruption, y compris sans limitation, le droit de la Banque de sanctionner et les droits de la Banque pour l’inspection et l’audit ; (iv) les documents de passation des marchés contiennent des dispositions convenues avec la Banque, destinées à atténuer les risques et impacts environnementaux, sociaux (y compris l’exploitation et les abus sexuels et les violences à caractère sexiste), et sur l’hygiène et la sécurité (« ESHS Lorsque l’Emprunteur utilise d’autres procédures que l’appel d’offres national ouvert, ces procédures devront être en accord avec les dispositions du paragraphe 5.5 du Règlement de passation des marchés. Crédit-bail tel que spécifié au paragraphe 5.10 du Règlement de Passation des marchés : Le crédit-bail peut être utilisé pour les contrats indiqués dans le Plan de passation des marchés. « Sans objet » Achat de biens d’occasion tel que spécifié au paragraphe 5.11 du Règlement de Passation des Marchés est autorisé pour les contrats indiqués dans le Plan de passation des marchés. « Sans objet » Préférence nationale telle que spécifiée au paragraphe 5.51 du Règlement de Passation des Marchés (Fournitures et Travaux). Fournitures : s’applique lister les marchés ou mentionner ne s’applique pas Travaux : s’applique lister les marchés ou mentionner ne s’applique pas Autres informations pertinentes sur la passation des marchés « Sans objet ». PROCUREMENT Burkina Faso : Burkina Faso Agriculture Resilience and Competitiveness Project PLAN General Information Country: Burkina Faso Bank’s Approval Date of the Original Procurement Plan: 2020-01-23 2021-05-21 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P167945 GPN Date: Project Name: Burkina Faso Agriculture Resilience and Competitiveness Project Loan / Credit No: IDA / 64910, IDA / 64920 Agriculture Resilience and Competitiveness Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned BF-PRECA-215424-CW-RFB / Project Coordination, Sécurisation et réhabilitation Pending Institutional Strengthening Single Stage - One 2021-10- des locaux de la Direction IDA / 64920 Post Request for Bids Open - National 236,300.00 0.00 Implementat 2021-05-01 2021-05-08 2021-06-07 2021-06-14 2021-07-12 and Contigent Emergency Envelope 10 Générale de la Coopération ion Response Component (DGCOOP) BF-PRECA-215479-CW-RFB / Project Coordination, Pending Construction d’un local au Institutional Strengthening Single Stage - One 2022-08- IDA / 64920 Post Request for Bids Open - National 1,712,330.00 0.00 Implementat 2021-06-01 2021-06-08 2021-07-23 2021-07-30 2021-08-27 profit de l’unité de gestion du and Contigent Emergency Envelope 22 ion projet Response Component Project Coordination, BF-PRECA-215447-CW-RFB / Pending Institutional Strengthening Single Stage - One 2021-12- Construction des offices au IDA / 64920 Post Request for Bids Open - National 231,165.00 0.00 Implementat 2021-07-01 2021-07-06 2021-08-05 2021-08-10 2021-09-07 and Contigent Emergency Envelope 06 profit des ZAT ion Response Component BF-PRECA-212967-CW-RFB / Pending Improving Competitiviness Single Stage - One 2021-09- Construction de magasins de IDA / 64920 Post Request for Bids Open - National 1,077,000.00 0.00 Implementat 2021-03-01 2021-03-08 2021-04-07 2021-04-14 2021-05-12 and Fostering Market Access Envelope 09 stockage et d'aires de séchage ion BF-PRECA-215393-CW-RFQ / Travaux de réhabilitation des comptoirs d'achat, des infrastructures des postes de Pending contrôle phytosanitaire des Improving Competitiviness Single Stage - One 2021-09- IDA / 64910 Post Request for Bids Open - National 470,000.00 0.00 Implementat 2021-04-15 2021-04-20 2021-05-20 2021-05-27 2021-06-17 locaux des Directions and Fostering Market Access Envelope 15 ion Provinciales de l'Agriculture et des Aménagements Hydro- agricoles et des magasins de stockage BF-PRECA-235380-CW-RFB / Project Coordination, Request for Bids - Pending Réhabilitation des locaux au Institutional Strengthening Single Stage - One Small Works SPD 2021-11- IDA / 64910 Post Request for Bids Open - National 203,200.00 0.00 Implementat 2021-06-10 2021-06-17 2021-07-17 2021-07-24 2021-08-14 profit des unités de gestion and Contigent Emergency Envelope (1 envelope 12 ion régionales du PReCA Response Component process) GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BF-PRECA-151445-GO-RFQ Under / Acquisition de mobilier de Enhancing Agriculture Request for Single Stage - One IDA / 64910 Post Limited 78,000.00 0.00 Implementati 2020-03-14 2020-04-18 2020-05-02 bureau pour l'UGP au profit Productivity Quotations Envelope on du PRéCA BF-PRECA-151521-GO-RFQ / Acquisition de matériel et bureautique informatique Under Enhancing Agriculture Request for Single Stage - One (ordinateurs, onduleurs, IDA / 64910 Post Limited 78,000.00 0.00 Implementati 2020-03-15 2020-04-19 2020-05-19 Productivity Quotations Envelope imprimantes et on photocopieurs, scanner etc) au profit du PReCA BF-PRECA-151443-GO-UN / Acquisition de matériel roulant (01 station wagon V8, Under Enhancing Agriculture UN Agencies 05 stations Wagon de type IDA / 64910 Post Direct 2,268,000.00 0.00 Implementati 2020-04-15 2020-05-26 2020-04-20 2020-05-25 2020-08-23 Productivity (Direct) PRADO, 10 berline, 30 Pick Up on et 50 motocyclette) au profit du PReCA BF-PRECA-151523-GO-RFB / Under Acquisition d'un logiciel de Enhancing Agriculture Request for Single Stage - One IDA / 64910 Post Limited 100,000.00 0.00 Implementati 2020-03-09 2020-04-20 2020-06-19 suivi évaluation au profit du Productivity Quotations Envelope on PReCA BF-PRECA-151522-GO-DIR / Under Acquisition du logiciel de Enhancing Agriculture Request for Single Stage - One IDA / 64910 Post Limited 100,000.00 0.00 Implementati 2020-06-15 2020-08-10 2020-09-09 gestion financière et Productivity Quotations Envelope on comptable au profit du PReCA Project Coordination, BF-PRECA-214864-GO-RFQ Pending Institutional Strengthening Request for Single Stage - One / Acquisition de fournitures IDA / 64920 Post Limited 34,245.00 0.00 Implementati 2021-02-17 2021-03-23 2021-12-18 and Contigent Emergency Quotations Envelope de bureau au profit de l'UGP on Response Component BF-PRECA-214900-GO-RFQ Pending / Acquisition de smartphones, Enhancing Agriculture Request for Single Stage - One IDA / 64910 Post Limited 34,250.00 0.00 Implementati 2021-03-04 2021-04-04 2021-05-04 de GPS et d'appareil photo Productivity Quotations Envelope on pour la collecte de données Project Coordination, BF-PRECA-215172-GO-RFB / Pending Institutional Strengthening Single Stage - One Acquisition et installation de IDA / 64920 Post Request for Bids Open - National 102,740.00 0.00 Implementati 2021-03-01 2021-03-11 2021-04-10 2021-04-15 2021-05-06 2021-07-05 and Contigent Emergency Envelope groupes électrogènes on Response Component BF-PRECA-215464-GO-RFQ Project Coordination, / Acquisition et installation Pending Institutional Strengthening Request for Single Stage - One d'équipements de IDA / 64910 Post Limited 34,245.00 0.00 Implementati 2021-05-05 2021-06-16 2021-08-15 and Contigent Emergency Quotations Envelope communication au profit de on Response Component l’Unité de gestion du PReCA Page 1 BF-PRECA-215467-GO-RFB / Acquisition d’équipements Project Coordination, Pending informatiques au titre de Institutional Strengthening Single Stage - One IDA / 64920 Post Request for Bids Open - National 196,915.00 0.00 Implementati 2021-04-01 2021-04-11 2021-05-11 2021-05-16 2021-06-06 2021-08-20 l'appui institutionnel et and Contigent Emergency Envelope on installation de connexion Response Component internet BF-PRECA-215115-GO-RFB / Acquisition d'équipements pour les points de contrôle sanitaire et phyto sanitaires, les laboratoires nationaux Pending Improving Competitiviness Single Stage - One spécialisés dans le contrôle IDA / 64920 Post Request for Bids Open - National 765,750.00 0.00 Implementati 2021-03-01 2021-03-06 2021-04-05 2021-04-10 2021-05-01 2021-07-15 and Fostering Market Access Envelope sanitaire et de la DGPV on (Microscope optiques, Loupe, Humidimètre, Microscopes, Appareil HPLC, lecteur de barette) BF-PRECA-215203-GO-RFB / Acquisition d'équipements de Project Coordination, Pending bureau au titre de l'appui Institutional Strengthening Single Stage - One IDA / 64920 Post Request for Bids Open - National 216,180.00 0.00 Implementati 2021-04-01 2021-04-11 2021-05-11 2021-05-16 2021-06-06 2021-08-20 institutionnel (armoires de and Contigent Emergency Envelope on rangement, bureaux , Response Component fauteuils , chaises...) BF-PRECA-217711-GO-RFQ Pending / Acquisition d'un véhicule Enhancing Agriculture Request for Single Stage - One IDA / 64910 Post Limited 160,000.00 0.00 Implementati 2021-03-20 2021-04-24 2021-06-08 automobile Station Wagon de Productivity Quotations Envelope on type V8 BF-PRECA-228905-GO-RFB / Pending Acquisition de matériel pour Improving Competitiviness Single Stage - One IDA / 64920 Post Request for Bids Open - National 375,770.00 0.00 Implementati 2021-05-15 2021-05-20 2021-06-19 2021-07-03 2021-07-31 2021-09-29 l'équipement des magasins de and Fostering Market Access Envelope on stockage BF-PRECA-229181-GO-RFQ Project Coordination, / fourniture et pose Pending Institutional Strengthening Request for Single Stage - One d'extincteurs, de climatiseurs IDA / 64920 Post Limited 26,500.00 0.00 Implementati 2021-05-03 2021-06-17 2021-07-17 and Contigent Emergency Quotations Envelope et de cloisons alu vitrés aux on Response Component profit de l'UGP et des UGR BF-PRECA-229182-GO-RFQ Project Coordination, / Réalisation d'outils de Pending Institutional Strengthening Request for Single Stage - One communication au profit du IDA / 64910 Post Limited 36,200.00 0.00 Implementati 2021-06-04 2021-07-23 2021-07-26 and Contigent Emergency Quotations Envelope PReCA (dépliants, enseigne, on Response Component support audiovisuel...) BF-PRECA-235386-GO-RFQ / Acquisition de petits Pending Enhancing Agriculture Request for Single Stage - One matériels et intrants agricoles IDA / 64910 Post Limited 16,930.00 0.00 Implementati 2021-06-02 2021-06-17 2021-07-01 Productivity Quotations Envelope pour la réalisation des on activités de champs écoles NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Project Coordination, BF-PRECA-214853-NC-RFQ / Under Institutional Strengthening Request for Single Stage - One Assurance véhicules IDA / 64920 Post Limited 34,250.00 0.00 Implementati 2021-02-08 2021-03-11 2021-04-01 and Contigent Emergency Quotations Envelope automobiles on Response Component Project Coordination, BF-PRECA-214859-NC-RFQ / Under Institutional Strengthening Request for Single Stage - One Assurance santé du personnel IDA / 64920 Post Limited 85,600.00 0.00 Implementati 2021-02-18 2021-03-21 2021-04-11 and Contigent Emergency Quotations Envelope de l'UGP on Response Component BF-PRECA-215173-NC-RFQ / Project Coordination, Pending Service d’entretien et de Institutional Strengthening Request for Single Stage - One IDA / 64920 Post Limited 15,410.00 0.00 Implementati 2021-02-04 2021-02-28 2022-02-23 nettoyage des locaux de and Contigent Emergency Quotations Envelope on l’Unité de gestion PRéCA Response Component Project Coordination, BF-PRECA-215182-NC-RFQ / Pending Institutional Strengthening Request for Single Stage - One Services de gardiennage des IDA / 64920 Post Limited 15,410.00 0.00 Implementati 2021-02-18 2021-03-16 2022-03-11 and Contigent Emergency Quotations Envelope locaux du projet on Response Component BF-PRECA-216422-NC-RFQ / Project Coordination, Pending Location de bureaux au profit Institutional Strengthening Request for Single Stage - One IDA / 64920 Post Limited 102,740.00 0.00 Implementati 2021-01-28 2021-02-14 2022-02-09 de l'Unité de Gestion du and Contigent Emergency Quotations Envelope on PReCA Response Component BF-PRECA-215184-NC-RFQ / Project Coordination, Pending Fourniture de services Institutional Strengthening IDA / 64920 Post Direct Selection Direct 42,800.00 0.00 Implementati 2021-03-01 2021-03-06 2021-04-03 2022-04-03 d'entretien des véhicules and Contigent Emergency on automobiles Response Component CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BF-PRECA-151524-CS-CQS / Consultant Etudes d'impact Enhancing Agriculture IDA / 64910 Post Qualification Limited 35,000.00 0.00 Under Review 2020-01-06 2021-03-03 2020-01-13 2020-01-20 2020-02-03 2020-03-04 environnementales et sociales Productivity Selection du site de Dangoumana (EIES) BF-PRECA-151527-CS-CQS / Etude du Plan d'Actions de Consultant Enhancing Agriculture Réinstallation des personnes IDA / 64910 Post Qualification Limited 65,000.00 0.00 Under Review 2020-01-06 2021-03-03 2020-01-13 2020-01-20 2020-02-03 2020-03-29 Productivity affectées (PAR) du site de Selection Dangoumana Page 2 BF-PRECA-151528-CS-CQS / Consultant Etudes d'impact Enhancing Agriculture IDA / 64910 Post Qualification Limited 35,000.00 0.00 Under Review 2020-01-13 2021-03-03 2020-01-20 2020-01-27 2020-02-10 2020-03-11 environnementales et sociales Productivity Selection du site de Bissan (EIES) BF-PRECA-151529-CS-CQS / Etude du Plan d'Actions de Consultant Enhancing Agriculture Réinstallation des personnes IDA / 64910 Post Qualification Limited 65,000.00 0.00 Under Review 2020-01-13 2021-03-03 2020-01-20 2020-01-27 2020-02-10 2020-04-05 Productivity affectées (PAR) du site de Selection Bissan BF-PRECA-151530-CS-CQS / Consultant Etudes d'impact Enhancing Agriculture IDA / 64910 Post Qualification Limited 35,000.00 0.00 Under Review 2020-01-27 2021-03-03 2020-02-03 2020-02-10 2020-02-24 2020-03-25 environnementales et sociales Productivity Selection du site de Sindou (EIES) BF-PRECA-151531-CS-CQS / Etude du Plan d'Actions de Consultant Enhancing Agriculture Réinstallation des personnes IDA / 64910 Post Qualification Limited 65,000.00 0.00 Under Review 2020-01-27 2021-03-03 2020-02-03 2020-02-10 2020-02-24 2020-04-19 Productivity affectées (PAR) du site de Selection Sindou BF-PRECA-151532-CS-CQS / Etudes d'impact Consultant Enhancing Agriculture environnementales et sociales IDA / 64910 Post Qualification Limited 35,000.00 0.00 Under Review 2020-01-27 2021-03-03 2020-02-03 2020-02-10 2020-02-24 2020-03-25 Productivity du site de Lémourdougou Selection (EIES) BF-PRECA-151533-CS-CQS / Etude du Plan d'Actions de Consultant Enhancing Agriculture Réinstallation des personnes IDA / 64910 Post Qualification Limited 65,000.00 0.00 Under Review 2020-01-27 2021-03-03 2020-02-03 2020-02-10 2020-02-24 2020-04-19 Productivity affectées (PAR) du site de Selection Lémourdougou BF-PRECA-151534-CS-QCBS / Etudes d’avant-projet sommaire et détaille pour la réhabilitation et l’extension Enhancing Agriculture Quality And Cost- IDA / 64910 Post Open - International 240,000.00 0.00 Under Review 2020-01-30 2020-04-01 2020-02-20 2020-03-19 2020-04-16 2020-05-16 2020-06-20 2020-07-25 2020-10-23 de la plaine aménagée de Productivity Based Selection Banzon dans la province du Kénédougou, région des Hauts-Bassins BF-PRECA-151535-CS-QCBS / Etude d’avant-projet détaille pour la l’aménagement de bas- Enhancing Agriculture Quality And Cost- Under IDA / 64910 Post Open - International 345,000.00 0.00 2020-01-30 2020-04-01 2020-02-20 2020-12-29 2020-04-04 2020-05-02 2020-06-01 2020-07-06 2020-08-10 2020-12-08 fonds dans les provinces de la Productivity Based Selection Implementation Léraba et de la Comoé, région des cascades BF-PRECA-151576-CS-LCS / Recrutement d'un auditeur Enhancing Agriculture Least Cost Under pour l'audit externe annuel IDA / 64910 Post Open - National 94,000.00 0.00 2020-01-30 2020-04-01 2020-02-20 2020-03-19 2020-04-16 2020-05-16 2020-06-20 2020-07-25 2020-09-08 Productivity Selection Implementation du Projet (2020-2021 - 2022) dans le cadre du PReCA BF-PRECA-151577-CS-QCBS Consultant / Recrutement du personnel Enhancing Agriculture IDA / 64910 Post Qualification Open - National 60,000.00 53,359.22 Completed 2020-02-04 2019-11-20 2020-02-18 2020-03-10 2020-03-23 2020-03-17 2020-04-23 2020-04-07 2020-05-18 2020-07-06 2020-05-20 du Projet de Résilience et de Productivity Selection Compétitivité Agricole (PReCA) BF-PRECA-174009-CS-CQS / Études d’impact environnemental et social (EIES) dans le cadre des travaux d’aménagement Consultant Improving Competitiviness Under d’environ 130 km de pistes IDA / 64910 Post Qualification Open - National 76,362.00 0.00 2020-06-01 2021-05-06 2020-06-22 2020-07-13 2020-07-27 2020-08-31 2020-09-30 and Fostering Market Access Implementation rurales et la réhabilitation Selection d’environ 215 km de routes non-revêtues dans les régions de Boucle du Mouhoun, des Cascades, des Hauts Bassins BF-PRECA-174010-CS-CQS / Etudes pour la préparation d’un Plan d’Actions pour la Réinstallation des personnes affectées des travaux Consultant Improving Competitiviness Under d’aménagement d’environ IDA / 64910 Post Qualification Open - National 109,567.00 0.00 2020-06-01 2021-05-06 2020-06-22 2020-07-13 2020-07-27 2020-08-31 2020-09-30 and Fostering Market Access Implementation 130 km de pistes rurales et la Selection réhabilitation d’environ 215 km de routes non-revêtues dans les régions de Boucle du Mouhoun, Project Coordination, BF-PRECA-211881-CS-CQS / Consultant Institutional Strengthening Etude sur la situation de IDA / 64920 Post Qualification Open - National 82,000.00 0.00 Under Review 2021-01-15 2021-01-12 2021-01-29 2021-02-19 2021-03-05 2021-03-24 2021-05-23 and Contigent Emergency référence Selection Response Component BF-PRECA-215013-CS-CQS / Etude d'avant Projet Détaillée Consultant Enhancing Agriculture Pending (APD) de la construction de la IDA / 64920 Post Qualification Open - National 42,800.00 0.00 2021-03-01 2021-03-15 2021-04-12 2021-05-12 2021-05-31 2021-08-29 Productivity Implementation ligne de haute tension (HT) Selection de Bissan BF-PRECA-215026-CS-CQS / Etude d’Impact Consultant Enhancing Agriculture Pending Environnemental et Social IDA / 64920 Post Qualification Open - National 34,245.00 0.00 2021-07-30 2021-08-13 2021-09-03 2021-09-17 2021-10-08 2021-12-07 Productivity Implementation (EIES) de la construction de la Selection ligne électrique de Bissan BF-PRECA-215030-CS-CQS / Elaboration du Plan d'action Consultant de réinstallation des Enhancing Agriculture Pending IDA / 64910 Post Qualification Open - National 51,370.00 0.00 2021-08-30 2021-09-13 2021-10-04 2021-10-18 2021-10-22 2022-01-20 personnes affectées par le Productivity Implementation Selection projet de construction de la ligne électrique de Bissan BF-PRECA-215481-CS-CQS / Etudes et analyses sur la Consultant protection et le Enhancing Agriculture Pending IDA / 64920 Post Qualification Open - National 34,245.00 0.00 2021-03-15 2021-03-29 2021-04-19 2021-05-03 2021-05-17 2021-08-15 développement des bassins Productivity Implementation Selection versants Conservation de l'eau et des sols Page 3 BF-PRECA-215491-CS-CQS / Développement de la Consultant Enhancing Agriculture plateforme électronique de IDA / 64920 Post Qualification Open - National 111,300.00 0.00 Canceled 2021-03-15 2021-03-29 2021-04-19 2021-05-03 2021-05-17 2021-11-13 Productivity distribution des intrants et du Selection matériel agricole BF-PRECA-214887-CS-CQS / Project Coordination, Consultant Elaboration stratégie de Institutional Strengthening Pending IDA / 64910 Post Qualification Open - National 17,120.00 0.00 2021-02-21 2021-03-07 2021-03-20 2021-03-27 2021-04-02 2021-06-01 communication assortie d'un and Contigent Emergency Implementation Selection plan de communication Response Component BF-PRECA-215216-CS-QCBS / Etude d'avant projet détaillé Enhancing Agriculture Quality And Cost- Under (APD) pour la réalisation des IDA / 64920 Post Open - International 1,100,000.00 0.00 2021-03-01 2021-04-08 2021-03-15 2021-05-19 2021-03-27 2021-05-08 2021-05-15 2021-06-05 2021-06-26 2021-12-23 Productivity Based Selection Implementation travaux d'aménagement de la plaine de Bissan BF-PRECA-215495-CS-QCBS / Etudes techniques pour la réalisation des travaux de réhabilitation et de Enhancing Agriculture Quality And Cost- Under IDA / 64920 Post Open - International 1,179,450.00 0.00 2021-02-01 2021-02-01 2021-02-15 2021-03-02 2021-03-08 2021-04-22 2021-05-06 2021-06-03 2021-07-01 2021-11-28 construction des pistes Productivity Based Selection Implementation rurales dans les régions du Boucle du Mouhoun, Hauts Bassins, Cascades et du Nord BF-PRECA-215499-CS-CQS / Maitrise d'ouvrage déléguée Enhancing Agriculture Quality And Cost- Under IDA / 64920 Post Open - International 845,685.00 0.00 2021-02-15 2021-02-11 2021-03-01 2021-02-28 2021-03-22 2021-05-03 2021-05-10 2021-05-31 2021-06-28 2025-06-07 pour la mise en œuvre des Productivity Based Selection Implementation activités du Guichet 2 BF-PRECA-228922-CS-CQS / recrutement d'une ONG chargée de la mise en œuvre Consultant du Plan d'action de Enhancing Agriculture IDA / 64920 Post Qualification Open - National 142,000.00 0.00 Under Review 2021-04-15 2021-05-14 2021-04-25 2021-05-16 2021-05-30 2021-06-20 2021-10-18 réinstallation des personnes Productivity Selection affectées par les travaux d'aménagement hydroagricole de BANZON BF-PRECA-212975-CS-CQS / Consultant Suivi contrôle des travaux de Improving Competitiviness Under IDA / 64920 Post Qualification Open - National 72,200.00 0.00 2021-02-15 2021-06-10 2021-03-01 2021-03-22 2021-04-05 2021-04-19 2021-10-16 construction de magasins et and Fostering Market Access Implementation Selection aires de séchage BF-PRECA-228928-CS-CQS / Etude technique et suivi Project Coordination, contrôle des travaux de Consultant Institutional Strengthening Under sécurisation et de IDA / 64920 Post Qualification Open - National 25,685.00 0.00 2021-04-30 2021-05-14 2021-05-14 2021-06-02 2021-06-09 2021-06-30 2021-10-28 and Contigent Emergency Implementation réhabilitation des bureaux de Selection Response Component la Direction Générale de la Coopération (DGCOOP) BF-PRECA-228932-CS-CQS / Etude technique en vue de la Consultant Improving Competitiviness Pending réalisation de chambres IDA / 64920 Post Qualification Limited 13,700.00 0.00 2021-04-30 2021-05-14 2021-05-28 2021-06-11 2021-07-11 and Fostering Market Access Implementation froides solaires pour stockage Selection de légumes BF-PRECA-229092-CS-CQS / Suivi contrôle des travaux de réhabilitation des magasins de stockage, des comptoirs Project Coordination, d'achat, des locaux au profit Consultant Institutional Strengthening Pending des postes de contrôle IDA / 64920 Post Qualification Open - National 44,520.00 0.00 2021-04-30 2021-05-14 2021-06-04 2021-06-18 2021-07-09 2021-12-06 and Contigent Emergency Implementation phytosanitaire et des Selection Response Component directions provinciales de l'agriculture, des aménagements hydro- agricoles BF-PRECA-215427-CS-INDV Project Coordination, / Elaboration des dossiers Consultant Institutional Strengthening Under techniques et suivi contrôle IDA / 64920 Post Qualification Open - National 25,685.00 0.00 2021-03-15 2021-06-10 2021-03-29 2021-04-17 2021-04-24 2021-05-15 2021-11-11 and Contigent Emergency Implementation des travaux de construction Selection Response Component des offices au profit des ZAT BF-PRECA-229086-CS-CQS / Etude architecturale et suivi Project Coordination, Consultant architectural des travaux de Institutional Strengthening Pending IDA / 64920 Post Qualification Open - National 85,620.00 0.00 2021-06-25 2021-07-09 2021-07-30 2021-08-29 2021-09-19 2022-11-13 construction d’un local au and Contigent Emergency Implementation Selection profit de l’unité de gestion du Response Component projet BF-PRECA-229089-CS-CQS / Project Coordination, Etude d'ingénierie et direction Consultant Institutional Strengthening Pending des travaux de construction IDA / 64920 Post Qualification Open - National 85,620.00 0.00 2021-05-25 2021-06-08 2021-06-27 2021-07-04 2021-07-25 2022-09-18 and Contigent Emergency Implementation d’un local au profit de l’unité Selection Response Component de gestion du projet BF-PRECA-235762-CS-CQS / Project Coordination, Développement de la Consultant Institutional Strengthening Pending plateforme électronique de IDA / 64920 Post Qualification Limited 68,500.00 0.00 2021-06-15 2021-06-22 2021-07-02 2021-07-16 2021-09-29 and Contigent Emergency Implementation distribution des intrants et Selection Response Component matériels agricoles INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BF-PRECA-151578-CS-INDV / Etude d’évaluation de la Individual Enhancing Agriculture Pending sécurité du complexe barrage IDA / 64910 Post Consultant Limited 69,000.00 0.00 2019-12-30 2020-01-04 2020-01-11 2020-01-25 2020-03-25 Productivity Implementation Mouhoun -vanne de Léry et Selection ouvrages associés BF-PRECA-151579-CS-INDV Individual / Etude d’évaluation de la Enhancing Agriculture Pending IDA / 64910 Post Consultant Limited 69,000.00 0.00 2019-12-30 2020-01-04 2020-01-11 2020-01-25 2020-03-25 sécurité du barrage de Productivity Implementation Selection Samendéni Page 4 BF-PRECA-205793-CS-INDV Individual / Etude d'impact Enhancing Agriculture IDA / 64920 Post Consultant Limited 35,000.00 0.00 Under Review 2020-12-15 2020-11-24 2020-12-20 2020-12-27 2021-01-10 2021-03-11 environnemental et social de Productivity Selection plaine de BAMA BF-PRECA-205794-CS-INDV / Elaboration du Plan d'Action Individual de Réinstallation des Enhancing Agriculture IDA / 64920 Post Consultant Limited 65,000.00 0.00 Under Review 2020-12-15 2020-11-24 2020-12-20 2020-12-27 2021-01-10 2021-04-10 Personnes Affectées par le Productivity Selection Projet de réhabilitation de la plaine de BAMA BF-PRECA-205796-CS-INDV Individual / Elaboration d’un Cadre de Enhancing Agriculture Under IDA / 64920 Post Consultant Limited 25,000.00 0.00 2020-12-05 2020-11-24 2020-12-10 2020-12-17 2020-12-31 2021-03-01 Gestion Environnmentale et Productivity Implementation Selection Sociale (CGES) du PRSA BF-PRECA-205797-CS-INDV / Elaboration d’un Cadre de Individual Enhancing Agriculture Under Politique de Réinstallation IDA / 64920 Post Consultant Limited 25,000.00 0.00 2020-12-05 2020-11-24 2020-12-10 2020-12-17 2020-12-31 2021-03-01 Productivity Implementation (CPR) des populations Selection affectées par le PRSA BF-PRECA-205799-CS-INDV / Elaboration d’un Plan de Individual Enhancing Agriculture Under Gestion des Pestes et IDA / 64920 Post Consultant Limited 25,000.00 0.00 2020-12-05 2020-11-24 2020-12-10 2020-12-17 2020-12-31 2021-03-01 Productivity Implementation Pesticides dans le cadre de la Selection mise en oeuvre du PRSA BF-PRECA-206165-CS-INDV / Recrutement d'un consultant individuel pour la finalisation Individual des TDRS relatifs aux études Enhancing Agriculture IDA / 64920 Post Consultant Limited 6,200.00 0.00 Under Review 2020-12-01 2020-12-03 2020-12-06 2020-12-13 2020-12-27 2021-09-23 d'impact environnemental et Productivity Selection social (EIES), à l'élaboration des PAR et à l’assurance qualité des rapports BF-PRECA-215480-CS-INDV / Etudes visant à renforcer la Individual Enhancing Agriculture Pending définition des politiques et IDA / 64920 Post Consultant Limited 17,120.00 0.00 2021-04-01 2021-04-15 2021-04-29 2021-05-13 2021-07-12 Productivity Implementation des bonnes pratiques Selection agricoles BF-PRECA-215501-CS-INDV Individual / Recrutement d’un expert en Enhancing Agriculture Pending IDA / 64920 Post Consultant Limited 34,245.00 0.00 2021-02-15 2021-02-22 2021-03-08 2021-04-05 2021-12-31 irrigation pour la revue qualité Productivity Implementation Selection des rapports d'études BF-PRECA-215236-CS-INDV / Contrôle à pied d'oeuvre des Project Coordination, travaux de réhabilitation des Individual Institutional Strengthening locaux des directions IDA / 64920 Post Consultant Limited 8,560.00 0.00 Canceled 2021-03-31 2021-04-05 2021-04-26 2021-05-31 2021-08-14 and Contigent Emergency provinciales de l'agriculture et Selection Response Component des aménagements hydro- agricoles BF-PRECA-215398-CS-INDV / Mission de contrôle à pied Individual Improving Competitiviness d'oeuvre des travaux de IDA / 64920 Post Consultant Limited 1,275.00 0.00 Canceled 2021-04-01 2021-04-06 2021-04-20 2021-05-11 2021-07-25 and Fostering Market Access réhabilitation des comptoirs Selection d'achat BF-PRECA-215312-CS-INDV / Contrôle à pied d'oeuvre des Individual Improving Competitiviness travaux de réhabilitation des IDA / 64920 Post Consultant Limited 6,850.00 0.00 Canceled 2021-03-01 2021-03-06 2021-03-27 2021-05-01 2021-07-30 and Fostering Market Access locaux au profit des postes de Selection contrôle phytosanitaire BF-PRECA-235394-CS-INDV Project Coordination, / Elaboration d'un plan de Individual Institutional Strengthening Pending renforcement des capacités IDA / 64920 Post Consultant Limited 17,120.00 0.00 2021-06-30 2021-07-05 2021-07-12 2021-07-26 2021-09-09 and Contigent Emergency Implementation techniques du personnel du Selection Response Component PReCA BF-PRECA-235550-CS-INDV / Conception de modèle Individual économiques assortis du plan Improving Competitiviness Pending IDA / 64920 Post Consultant Limited 29,110.00 0.00 2021-06-15 2021-06-29 2021-07-13 2021-07-27 2021-10-10 d’affaire du système and Fostering Market Access Implementation Selection d’information des marchés agro-sylvo-pastoraux (SIMA) Page 5 PROCUREMENT PLAN Project information: URUGUAY – P159771 – Providing Quality Education in Uruguay Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. PROCUREMENT Uruguay : Improving the Quality of Initial and Primary Education in Uruguay PLAN General Information Country: Uruguay Bank’s Approval Date of the Original Procurement Plan: 2017-05-11 2021-05-21 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P159771 GPN Date: Project Name: Improving the Quality of Initial and Primary Education in Uruguay Loan / Credit No: IBRD / 86750 National administration of Public Education Executing Agency(ies): WORKS Activity Reference No. / Procurement Estimated Actual Draft Pre- Draft Bidding Bid Evaluation Report Loan / Credit Market Procurement Prequalification High SEA/SH Process Prequalification Specific Procurement Bidding Documents as Proposal Submission Contract Description Component Review Type Method Document Amount Amount qualification Document / and Recommendation Signed Contract No. Approach Process (Y/N) Risk Status Evaluation Report Notice / Invitation Issued / Opening / Minutes Completion Type (US$) (US$) Documents Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned UY-ANEP-14468-CW-RFB ESC RIVERA 2017 / Refacción Single Stage - One 2017-09- 2017-09- 2017-10- 2017-10- 2018-01- 2019-01- IBRD / 86750 Early Education Post Request for Bids Open - National 1,400,000.00 0.00 Canceled y Rehabilitación en Escuela - Envelope 01 01 02 12 20 15 Departamento de Rivera UY-ANEP-14484-CW-RFB ESC87 PAYSANDU 2017 / Single Stage - One 1,637,706.8 2017-01- 2017-01- 2017-01- 2017-02- 2017-02- 2017-03- 2017-03- 2017-07- 2017-06- 2018-07- IBRD / 86750 Early Education Post Request for Bids Open - National 1,400,000.00 Signed Obra Refacción y Envelope 9 13 13 13 15 23 15 15 07 29 01 Rehabilitación Esc 87 Dep de Paysandú UY-ANEP-14560-CW-RFB- ESC-16-TYTRES 2017 / Obras Single Stage - One 1,117,654.6 2017-03- 2017-03- 2017-03- 2017-05- 2017-05- 2017-05- 2017-10- 2017-08- 2017-10- 2018-05- IBRD / 86750 Early Education Post Request for Bids Open - National 1,400,000.00 Signed en Escuela - Departamento de Envelope 9 27 27 31 12 12 19 27 31 27 31 Treinta y Tres UY-ANEP-14469-CW-RFB ESC 160 MDEO 2017 / Single Stage - One 2017-06- 2017-06- 2017-06- 2017-07- 2017-08- 2017-08- 2017-08- 2017-11- 2017-11- 2018-11- IBRD / 86750 Early Education Post Request for Bids Open - National 530,000.00 918,830.08 Signed Refacción y Rehabilitación Envelope 15 29 26 27 10 06 22 14 15 09 Escuela 160 Montevideo UY-ANEP-14486-CW-RFB ESC 8 FLORIDA 2017 / Obra Single Stage - One 1,211,792.7 2017-03- 2017-03- 2017-03- 2017-05- 2017-05- 2017-05- 2017-05- 2017-08- 2017-09- 2018-05- IBRD / 86750 Early Education Post Request for Bids Open - National 1,400,000.00 Signed Nueva, REfacción y Ampliación Envelope 9 27 27 31 12 12 19 15 31 06 31 Esc 8 Dep. de Florida UY-ANEP-17779-CW-RFB- ESC 11 SALTO / Obra Single Stage - One 1,256,108.9 2017-06- 2017-06- 2017-06- 2017-07- 2017-08- 2017-08- 2017-08- 2017-11- 2017-11- 2018-11- refacción y rehabiliatación IBRD / 86750 Early Education Post Request for Bids Open - National 1,200,000.00 Signed Envelope 6 20 29 26 26 03 04 18 30 16 30 Escuela N° 11 Salto, Departamento de Salto UY-ANEP-17781-CW-RFB-8 FRAILE MUERTO / Obra Refacción y Rehabilitación Single Stage - One 1,203,959.2 2017-06- 2017-06- 2017-06- 2017-07- 2017-07- 2017-08- 2017-08- 2017-11- 2017-11- 2018-10- IBRD / 86750 Early Education Post Request for Bids Open - National 1,200,000.00 Signed Escuela N° 8 Fraile Muerto, Envelope 1 20 21 26 26 26 04 02 30 15 01 Melo, Departamento de Cerro Largo. UY-ANEP-17782-CW-RFB- 124 MELILLA / Obra de Single Stage - One 2017-06- 2017-06- 2017-06- 2017-07- 2017-07- 2017-08- 2017-08- 2017-11- 2017-10- 2018-06- Refacción y Rehabilitación IBRD / 86750 Early Education Post Request for Bids Open - National 800,000.00 795,495.80 Signed Envelope 20 22 26 26 26 04 14 30 23 29 Escuela N° 124 Melilla, Departamento de Montevideo. UY-ANEP-17923-CW-RFB- ESC 39 MERCEDES / Obra en Single Stage - One 1,425,178.3 2015-06- 2015-06- 2015-06- 2015-07- 2015-07- 2015-07- 2015-07- 2015-11- 2015-11- 2017-07- IBRD / 86750 Early Education Post Request for Bids Open - National 357,961.38 Signed Escuela N° 39 Mercedes Envelope 5 14 11 14 20 20 24 24 03 05 31 Departamento de Soriano UY-ANEP-17918-CW-RFB- ESC 44 MDEO / Obra en Single Stage - One 2016-03- 2016-03- 2016-03- 2016-05- 2016-05- 2016-05- 2018-05- 2016-12- 2016-12- 2017-12- IBRD / 86750 Early Education Post Request for Bids Open - National 470,274.41 853,981.17 Signed Escuela N° 44 Departamento Envelope 31 31 31 03 03 10 10 23 23 31 Montevideo UY-ANEP-17917-CW-RFB- ESC 385 MARACANA / Obra Single Stage - One 1,156,827.1 2016-08- 2016-08- 2016-08- 2016-09- 2016-09- 2016-09- 2016-09- 2017-02- 2017-02- 2017-12- en Escuela N° 385 Barrio IBRD / 86750 Early Education Post Request for Bids Open - National 817,953.59 Signed Envelope 5 08 08 08 09 09 19 19 23 24 31 Maracana Departamento Montevideo UY-ANEP-17789-CW-RFB ESC 24 VICHADER0 / Obra en Single Stage - One 2016-08- 2016-08- 2016-08- 2016-09- 2016-09- 2016-09- 2016-09- 2017-02- 2017-02- 2017-07- IBRD / 86750 Early Education Post Request for Bids Open - National 446,174.48 519,247.43 Signed Escuela N° 24 Vichadero Envelope 01 01 01 12 12 27 27 15 15 31 Departamento Rivera UY-ANEP-17922-CW-RFB- 130 COLONIA / Obra en Single Stage - One 1,092,332.8 2015-06- 2015-06- 2015-06- 2015-07- 2015-07- 2015-07- 2015-07- 2016-02- 2016-02- 2017-06- IBRD / 86750 Early Education Post Request for Bids Open - National 67,330.59 Signed Escuela N° 130 Colonia, Envelope 0 17 17 21 22 22 31 31 24 24 30 Departamento de Colonia UY-ANEP-17921-CW-RFB- ESC 122 CARAGUATA / Obra Single Stage - One 1,176,404.1 2015-07- 2015-07- 2015-07- 2015-08- 2015-08- 2015-08- 2015-08- 2016-02- 2016-02- 2017-06- en Escuela N° 122 Toscas IBRD / 86750 Early Education Post Request for Bids Open - National 110,459.28 Signed Envelope 6 01 01 05 05 05 18 18 24 24 30 Caraguatá, Departamento Tacuarembó UY-ANEP-17919-CW-RFB- ESC 154 PENAROL / Obra en Single Stage - One 1,157,239.9 2015-07- 2015-07- 2015-07- 2015-08- 2015-08- 2015-11- 2015-11- 2016-03- 2016-03- 2017-06- IBRD / 86750 Early Education Post Request for Bids Open - National 57,439.21 Signed Escuela N° 154 Barrio Peñarol Envelope 5 08 08 12 12 12 27 27 29 29 30 Departamento Montevideo UY-ANEP-14465-CW-RFB - ESC 17 MALDONADO / Single Stage - One 2017-06- 2017-06- 2017-07- 2017-07- 2017-10- 2018-10- Refacción y Rehabilitación IBRD / 86750 Early Education Post Request for Bids Open - National 921,000.00 0.00 Canceled Envelope 01 01 02 12 20 15 Escuela 17 Gregorio Aznares Departamento Maldonado UY-ANEP-14470-CW-RFB ESC LAS PIEDRAS2017 / Single Stage - One 2017-08- 2017-08- 2017-09- 2017-09- 2017-12- 2018-12- Rehabilitación y Refacción IBRD / 86750 Early Education Post Request for Bids Open - National 1,400,000.00 0.00 Canceled Envelope 01 01 01 11 20 15 Escuela Las Piedras, Departamento de Canelones UY-ANEP-14467-CW-RFB ESC SAN JOSE 2017 / Single Stage - One 2017-09- 2017-09- 2017-10- 2017-10- 2018-01- 2019-01- Refacción y Rehabilitación IBRD / 86750 Early Education Post Request for Bids Open - National 2,000,000.00 0.00 Canceled Envelope 01 05 06 16 24 19 Escuela - Departamento de San Jose UY-ANEP-71639-CW-RFB- ESC 117 MDEO / Obra nueva y Single Stage - One 1,344,266.8 2018-08- 2018-07- 2018-08- 2018-09- 2018-09- 2018-09- 2018-09- 2018-12- 2019-02- 2019-09- IBRD / 86750 Early Education Post Request for Bids Open - National 1,400,000.00 Signed refacción Escuela N°117 de Envelope 4 01 30 01 06 06 16 18 21 01 16 Montevideo UY-ANEP-71670-CW-RFB- ESC 65 MEDEO / Ampliación y Single Stage - One 2018-08- 2018-08- 2018-09- 2018-09- 2018-12- 2019-07- IBRD / 86750 Early Education Post Request for Bids Open - National 900,000.00 0.00 Canceled Refacción Escuela 65 Envelope 15 15 20 30 28 28 Montevideo UY-ANEP-88457-CW-RFQ- OBRA ESC 35 BUCEO / Reforma de dos baños, realización accesos discapacitados, Request for Single Stage - One 2019-01- 2019-03- 2019-06- 2019-05- IBRD / 86750 Early Education Post Open - National 180,000.00 205,377.85 Signed reforma integral de Quotations Envelope 07 06 20 31 instalación eléctrica, realización de instalación de gas para conectar gas natural, pintura interior de escuela, reparaciones varias instalación sanitaria. UY-ANEP-96774-CW-RFQ- ESC105-LACAZE 2019 / Request for Single Stage - One 2019-02- 2019-03- 2019-06- 2019-05- IBRD / 86750 Early Education Post Open - National 100,000.00 153,394.79 Signed Ampliacion y reforma Esc. 105 Quotations Envelope 14 25 12 04 Juan Lacaze, Colonia UY-ANEP-99825-CW-RFB- ESC 184 MDEO 2019 / Reforma y ampliación de dos Single Stage - One 2019-02- 2019-03- 2019-04- 2019-04- 2019-07- 2020-02- IBRD / 86750 Early Education Post Request for Bids Open - National 350,000.00 0.00 Canceled aulas nuevas, SSHH y espacios Envelope 28 04 03 10 10 09 exteriores en Escuela N° 184 Barrio Lavalleja, Montevideo Page 1 UY-ANEP-99829-CW-RFB- ESC 326 MDEO 2019 / Reforma y ampliación de aulas Single Stage - One 2019-06- 2019-07- 2019-07- 2019-08- 2019-11- 2020-11- IBRD / 86750 Early Education Post Request for Bids Open - National 350,000.00 0.00 Canceled SSHH, dirección y sala de Envelope 27 01 31 07 06 06 maestros en Escuela N° 326 Nuevo Ellauri, Montevideo UY-ANEP-99838-CW-RFQ- ESC 111SORIANO 2019 / Rehabilitación general de la Request for Single Stage - One 2019-02- 2019-04- 2019-08- IBRD / 86750 Early Education Post Open - National 95,000.00 0.00 Canceled eléctrica y Refacción cocina de Quotations Envelope 27 23 23 la Escuela N° 111 Mercedes, Soriano. UY-ANEP-99840-CW-RFQ- ESC 44 MALDON 2019 / Reforma y ampliación cocina, Request for Single Stage - One 2019-02- 2019-04- 2019-09- IBRD / 86750 Early Education Post Open - National 55,000.00 0.00 Canceled SSHH y espacios exteriores en Quotations Envelope 26 22 23 Escuela N° 44 Rincón de Olivera, Maldonado UY-ANEP-99843-CW-RFQ- ESC 60 MDEO 2019 / Rehabilitación SSHH de Request for Single Stage - One 2019-02- 2019-04- 2019-09- 2019-08- preescolares e IBRD / 86750 Early Education Post Open - National 100,000.00 146,751.51 Signed Quotations Envelope 18 10 02 12 impermeabilización general de azoteas en Escuela N° 60 Solferino, Montevideo UY-ANEP-99844-CW-RFQ- ESC 267 MDEO 2019 / Reforma y rehabilitación de Request for Single Stage - One 2019-02- 2019-04- 2019-08- IBRD / 86750 Early Education Post Open - National 180,000.00 0.00 Canceled cocina, comedor, SSHH y aulas Quotations Envelope 25 17 19 en Escuela N° 267 Euskalerría, Montevideo UY-ANEP-99845-CW-RFQ- ESC 35 DURAZNO 2019 / Impermeabilización de Request for Single Stage - One 2019-03- 2019-05- 2019-08- IBRD / 86750 Early Education Post Open - National 65,000.00 0.00 Canceled azotea, cambio de pisos y Quotations Envelope 08 03 05 sellado de aberturas en Escuela N°35 Sandú, Durazno. UY-ANEP-99842-CW-RFB- ESC 2 RIONEGRO 2019 / Reforma y ampliación dos Single Stage - One 2019-04- 2019-05- 2019-06- 2019-06- 2019-09- 2020-02- aulas nuevas, cocina, IBRD / 86750 Early Education Post Request for Bids Open - National 650,000.00 0.00 Canceled Envelope 29 03 02 09 08 10 comedor, SSHH y espacios exteriores en Escuela N° 2 Río Negro, Fray Bentos UY-ANEP-99834-CW-RFB- ESC 6 TACREMBO 2019 / Reforma y ampliación de aulas nuevas, dirección, sala de Single Stage - One 2019-07- 2019-08- 2019-09- 2019-09- 2019-12- 2020-06- IBRD / 86750 Early Education Post Request for Bids Open - National 900,000.00 0.00 Canceled maestros y espacios Envelope 30 03 02 09 09 10 exteriores en Escuela N° 6 Ciudad de Tacuarembó Departamento de Tacuarembó UY-ANEP-105805-CW-RFB- OBRA IFS 2019 / Obra de reforma y adecuación local existente para IFS : 2 aulas magnas para 100 personas Single Stage - One 1,188,073.1 2019-03- 2019-05- 2019-03- 2019-04- 2019-06- 2019-04- 2019-07- 2019-07- 2019-11- 2020-01- IBRD / 86750 Early Education Post Request for Bids Open - National 1,750,000.00 Signed c/u, administración, Envelope 1 13 17 25 25 28 29 19 29 20 25 Dirección, Coordinación operativa, Secretaría, 8 oficinas, Comedor, Bibliteca, SSHH a nuevo. UY-ANEP-107930-CW-RFB- 142-MONTEVIDEO / Reforma Single Stage - One 1,397,846.3 2019-03- 2019-04- 2019-04- 2019-05- 2019-05- 2019-05- 2019-06- 2019-08- 2019-09- 2020-06- IBRD / 86750 Early Education Post Request for Bids Open - National 1,800,000.00 Signed y Ampliación, cocina, Envelope 9 27 23 01 02 24 12 10 09 12 08 comedor, SSHH y aulas UY-ANEP-118368-CW-RFB- ESC 184 MDEO 2019 / Obra nueva, refacción y ampliación Single Stage - One 2019-06- 2019-06- 2019-06- 2019-07- 2019-07- 2019-08- 2019-08- 2019-11- 2019-11- 2020-08- IBRD / 86750 Early Education Post Request for Bids Open - National 451,000.00 672,961.02 Signed en la Escuela N° 184 Barrio Envelope 28 20 28 29 24 05 08 04 20 30 Lavalleja, Departamento de Montevideo UY-ANEP-119213-CW-RFQ- ESC 20 MDEO 2019 / Obras Request for Single Stage - One 2019-07- 2019-09- 2019-09- 2019-11- IBRD / 86750 Early Education Post Open - National 140,000.00 152,424.60 Signed de ampliación de la cocina de Quotations Envelope 15 12 30 11 la Escuela N° 20 Montevideo UY-ANEP-121366-CW-RFQ- ESC 117 SAN RAMON / Re- adecuación baños existentes, Request for Single Stage - One 2019-07- 2019-09- 2019-11- 2019-11- construcción baños nuevos IBRD / 86750 Early Education Post Open - National 80,000.00 77,872.23 Signed Quotations Envelope 15 13 13 12 para Educación Inicial, acondicionamiento del sistema de saneamiento UY-ANEP-99836-CW-RFB- ESC 124 TMBO 2019 / Reforma cocina, comedor, Single Stage - One 1,253,596.2 2019-07- 2019-08- 2019-08- 2019-09- 2019-09- 2019-09- 2019-09- 2019-12- 2020-02- 2020-06- aulas y espacios exteriores en IBRD / 86750 Early Education Post Request for Bids Open - National 1,200,000.00 Signed Envelope 4 29 05 02 01 04 08 30 08 14 09 Escuela N° 124 Ciudad de Tacuarembó, Departamento de Tacuarembó UY-ANEP-99811-CW-RFB- ESC 65 MDEO 2019 / Reforma y ampliación de aulas, SSHH y Single Stage - One 1,243,966.4 2019-08- 2019-08- 2019-08- 2019-09- 2019-09- 2019-10- 2019-10- 2020-01- 2020-02- 2020-11- IBRD / 86750 Early Education Post Request for Bids Open - National 1,400,000.00 Signed espacios exteriores en Escuela Envelope 4 18 26 23 22 26 04 14 10 14 06 N° 65 Ciudad Vieja Montevideo UY-ANEP-128557-CW-RFQ- 111 SORIANO 2019 / Ampliación, reforma, Request for Single Stage - One 2019-08- 2019-10- 2020-02- 2020-01- acondicionamiento sanitario y IBRD / 86750 Early Education Post Open - National 130,000.00 222,747.32 Signed Quotations Envelope 30 22 10 20 eléctrico en Escuela N° 111 Mercedes, Departamento de Soriano UY-ANEP-151242-CW-DIR- ESC CHINA 201 / Trabajos exigidos por la Intendencia Municipal de Montevideo 2020-01- 2019-12- 2020-01- 2019-12- 2020-02- 2020-02- 2020-04- referidos a la extensión del IBRD / 86750 Early Education Post Direct Selection Direct 110,000.00 117,003.22 Signed 22 18 29 16 14 13 14 colector existente en la obra Escuela nueva de Tiempo Completo N° 304 República Popular de China. UY-ANEP-156549-CW-RFQ- ESC 4 MONTEVIDEO / Reforma Request for Single Stage - One 2020-02- 2020-04- 2020-06- 2020-05- batería de baños y sector IBRD / 86750 Early Education Post Open - National 110,000.00 76,735.23 Signed Quotations Envelope 06 03 01 22 Administración en Escuela N° 4 de Montevideo. UY-ANEP-99819-CW-RFB- ESC 98 SORIANO 2019 / Obra Single Stage - One 1,713,090.4 2019-05- 2020-05- 2019-06- 2019-07- 2020-07- 2019-07- 2020-08- 2019-10- 2021-03- 2020-10- IBRD / 86750 Early Education Post Request for Bids Open - National 1,200,000.00 Signed nueva Escuela N° 98 Envelope 7 29 20 03 03 02 10 05 09 15 09 Mercedes, Soriano UY-ANEP-157310-CW-RFB- ESC 267 MDEO 2020 / Obra Single Stage - One 2020-04- 2020-07- 2020-04- 2020-05- 2020-08- 2020-05- 2020-09- 2020-08- 2021-04- 2021-04- rehabilitación en Escuela 267 IBRD / 86750 Early Education Post Request for Bids Open - National 800,000.00 545,514.43 Signed Envelope 02 24 06 06 28 13 22 12 15 12 Barrio Malvín Norte Departamento de Montevideo UY-ANEP-185650-CW-RFB- 5 RIO BRANCO 2020 / Rehabilitación y acondicionamiento local Single Stage - One 2020-07- 2020-08- 2020-09- 2020-09- 2020-12- 2021-04- IBRD / 86750 Early Education Post Request for Bids Open - National 250,000.00 0.00 Canceled escolar Escuela 5 de Río Envelope 31 04 03 10 10 12 Branco, incluye re ubicación cocina, reforma baños, adecuación aulas. UY-ANEP-157309-CW-RFQ- Under ESC 5 FLORIDA 2020 / Obra Request for Single Stage - One 2021-04- 2021-06- 2021-09- IBRD / 86750 Early Education Post Open - National 105,000.00 0.00 Implementat de Rehabilitación en Escuela 5 Quotations Envelope 01 25 23 ion Florida, Departamento Florida Page 2 UY-ANEP-157313-CW-RFB- ESC 320 MDEO 2020 / Obra Single Stage - One 2020-08- 2020-08- 2020-09- 2020-09- 2020-12- 2021-08- IBRD / 86750 Early Education Post Request for Bids Open - National 800,000.00 0.00 Canceled de rehabilitación en Escuela Envelope 03 07 06 13 13 13 N° 320 Casavalle, Montevideo UY-ANEP-99822-CW-RFB- ESC 129 MDEO 2019 / Obra Single Stage - One 2019-04- 2019-05- 2019-06- 2019-06- 2019-09- 2020-04- de ampliación y refacción en IBRD / 86750 Early Education Post Request for Bids Open - National 1,100,000.00 0.00 Canceled Envelope 29 03 02 09 08 09 Escuela N° 129 Hipódromo, Montevideo UY-ANEP-157311-CW-RFB- ESC301 MARIND 2020 / Obra Single Stage - One 2020-08- 2020-08- 2020-09- 2020-09- 2020-12- 2021-09- de ampliación en Escuela N° IBRD / 86750 Early Education Post Request for Bids Open - National 1,100,000.00 0.00 Canceled Envelope 03 07 06 13 13 13 301 Marindia, Departamento Canelones UY-ANEP-157306-CW-RFB- ESC 9 LA TEJA 2020 / Obra de Pending Single Stage - One 2021-04- 2021-04- 2021-05- 2021-05- 2021-08- 2022-05- rehabilitación en Escuela 9 La IBRD / 86750 Early Education Post Request for Bids Open - National 1,300,000.00 0.00 Implementat Envelope 02 06 06 13 06 25 Teja, Departamento de ion Montevideo UY-ANEP-218440-CW-RFB- ESC 4 MONTEVIDEO / Pending Rehabilitación general del Single Stage - One 2021-03- 2021-04- 2021-05- 2021-05- 2021-08- 2022-02- IBRD / 86750 Early Education Post Request for Bids Open - National 466,000.00 0.00 Implementat edificio, ampliación comedor, Envelope 31 05 05 12 31 28 ion reforma cocina y sshh y acceso para discapacitados. UY-ANEP-218438-CW-RFB- ESC 131 MONTEVIDEO / Pending Single Stage - One 2021-03- 2021-03- 2021-04- 2021-04- 2021-08- 2022-05- Ampliación dos aulas, IBRD / 86750 Early Education Post Request for Bids Open - National 698,000.00 0.00 Implementat Envelope 01 06 05 12 01 28 rehabilitación general y ion acondicionamiento de patio UY-ANEP-234351-CW-RFQ Request for Pending ESC. 4 DE ROCHA / Request for Single Stage - One 2021-06- 2021-07- 2021-12- IBRD / 86750 Early Education Post Open - National Quotations (Non 220,000.00 0.00 Implementat Ampliación. Un aula, mas Quotations Envelope 06 30 31 Bank-SPD) ion comedor y cocina. UY-ANEP-234355-CW-RFQ ESC. 63 LAVALLEJA / Request for Under Request for Single Stage - One 2021-06- 2021-07- 2021-12- Ampliación. Dentro de la IBRD / 86750 Early Education Post Open - National Quotations (Non 220,000.00 0.00 Implementat Quotations Envelope 06 30 29 construcción existente, en el Bank-SPD) ion área de comedor y cocina. UY-ANEP-234354-CW-RFQ ESC. 36 DE ARTIGAS / Request for Pending Request for Single Stage - One 2021-06- 2021-07- 2021-12- Ampliación. Dentro de la IBRD / 86750 Early Education Post Open - National Quotations (Non 220,000.00 0.00 Implementat Quotations Envelope 06 31 17 construcción existente en el Bank-SPD) ion área de comedor y cocina. GOODS Activity Reference No. / Draft Pre- Draft Bidding Bid Evaluation Report Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Prequalification Specific Procurement Bidding Documents as Proposal Submission Description Component Review Type Method qualification Document / and Recommendation Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Evaluation Report Notice / Invitation Issued / Opening / Minutes Documents Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual UY-ANEP-14475-GO-RFQ Request for Single Stage - One 2017-08- 2017-09- 2017-09- 2017-11- CORTINAS 2017 / Cortinas, IBRD / 86750 Primary Education Post Open - National 8,800.00 16,976.28 Signed Quotations Envelope 23 15 18 01 Alfombras y colchonetas UY-ANEP-14485-GO-RFQ FOTOCOPIAS 2017 / 80.000 Request for Single Stage - One 2017-03- 2017-03- 2017-03- 2017-12- IBRD / 86750 Primary Education Post Open - National 1,220.00 1,081.87 Signed Fotocopias para Formación en Quotations Envelope 16 29 29 31 Servicio año 2017 UY-ANEP-14488-GO-RFQ ESCURRIDORES 2017 / 30 Request for Single Stage - One 2017-05- 2017-06- 2017-05- 2017-07- IBRD / 86750 Primary Education Post Open - National 24,000.00 630.86 Signed escurridores de acero Quotations Envelope 17 02 29 05 inoxidable UY-ANEP-14573-GO-RFQ- COL ANDARIEGA 2017 / 21 Request for Single Stage - One 2017-05- 2017-05- 2017-10- 2017-06- IBRD / 86750 Primary Education Post Open - National 30,000.00 10,186.37 Signed Bibliotecas y carros para Quotations Envelope 17 31 02 14 almohadones UY-ANEP-14717-GO-RFQ- LIBROS TECNICO 2017 / Libros Técnicos para los Request for Single Stage - One 2017-05- 2017-06- 2017-03- 2017-08- IBRD / 86750 Primary Education Post Open - National 3,500.00 1,571.18 Signed Equipos de Cultura Quotations Envelope 22 15 30 14 Institucional, Matemáticas y Ciencias Sociales UY-ANEP-14476-GO-RFB EQ Single Stage - One 2017-07- 2017-08- 2017-07- 2017-08- 2017-09- 2017-08- 2017-09- 2017-09- 2017-12- 2017-11- SEMI IND 2017 / IBRD / 86750 Primary Education Post Request for Bids Open - National 230,000.00 250,222.00 Signed Envelope 07 01 12 14 01 24 26 04 06 15 Equipamiento Semi Industrial UY-ANEP-14481-GO-RFB MOB DIRECCION 2017 / Single Stage - One 2017-07- 2017-08- 2017-07- 2017-08- 2017-09- 2017-08- 2017-09- 2017-09- 2017-12- 2017-11- IBRD / 86750 Primary Education Post Request for Bids Open - National 100,000.00 115,457.79 Signed Mobiliario Dirección y Sala de Envelope 03 01 08 07 01 17 26 18 04 15 Maestros ETC UY-ANEP-14479-GO-RFB Single Stage - One 2017-05- 2017-06- 2017-05- 2017-06- 2017-07- 2017-07- 2017-07- 2017-10- 2017-11- 2018-01- MOB ESCOLAR 2017 / IBRD / 86750 Primary Education Post Request for Bids Open - National 550,000.00 608,157.10 Signed Envelope 17 01 26 26 03 06 21 16 29 14 Mobiliario Escolar UY-ANEP-14483-GO-RFB Single Stage - One 2017-02- 2017-02- 2017-02- 2017-03- 2017-03- 2017-04- 2017-04- 2017-07- 2017-06- 2017-08- VAJILLA 2017 / Vajila y IBRD / 86750 Early Education Post Request for Bids Open - National 100,000.00 72,641.23 Signed Envelope 09 09 09 13 13 03 03 13 30 27 Utensilios para cocina UY-ANEP-14477-GO-RFB EQ Single Stage - One 2017-07- 2017-10- 2017-07- 2017-08- 2017-10- 2017-09- 2017-11- 2017-10- 2017-12- 2017-12- INFORM 2017 / Equipamiento IBRD / 86750 Primary Education Post Request for Bids Open - National 60,000.00 42,308.80 Signed Envelope 18 27 23 23 27 04 14 05 22 31 Informático UY-ANEP-14804-GO-RFB- PLATOS ETC 2017 / Platos Single Stage - One 2017-05- 2017-06- 2017-05- 2017-06- 2017-07- 2017-06- 2017-07- 2017-07- 2017-09- 2017-10- IBRD / 86750 Early Education Post Request for Bids Open - National 96,000.00 74,233.28 Signed hondos 15.000 y Platos llanos Envelope 12 13 15 14 13 19 24 03 06 02 8.000 para ETC UY-ANEP-17152-GO-RFQ / Material fotocopiado en formato de libro para Request for Single Stage - One 2017-06- 2017-07- 2017-06- 2018-01- capacitación ETC que se IBRD / 86750 Primary Education Post Open - National 1,500.00 1,550.01 Signed Quotations Envelope 19 03 27 07 entregan mensualmente a Formadores de junio a diciembre (15 por mes) UY-ANEP-17783-GO-RFQ- LIBROS-COL-ANDARIEG / Request for Single Stage - One 2017-06- 2017-07- 2017-07- 2017-08- IBRD / 86750 Early Education Post Open - National 42,000.00 32,331.15 Signed LIBROS PARA LA COLECCIÓN Quotations Envelope 24 14 06 14 ANDARIEGA (DLI) UY-ANEP-14480-GO-RFQ EQ Request for Single Stage - One 2017-07- 2017-08- 2017-09- 2017-10- AUDIOVISUAL 2017 / IBRD / 86750 Primary Education Post Open - National 23,000.00 23,423.50 Signed Quotations Envelope 24 16 05 16 Equipamiento Audiovisual UY-ANEP-30193-GO-DIR- LIBROS COL ANDARIEG / CD. 2017-09- 2017-09- 2017-10- 2017-10- IBRD / 86750 Early Education Post Direct Selection Direct 3,800.00 0.00 Canceled LIBROS COLECCIÓN 26 29 04 20 ANDARIEGA UY-ANEP-31180-GO-RFQ LIBROS II / Complemento Request for Single Stage - One 2017-10- 2017-10- 2017-10- 2017-11- IBRD / 86750 Early Education Post Open - National 3,800.00 3,084.72 Signed Libros de la Colección Quotations Envelope 12 20 20 30 "Andariega" (DLI) UY-ANEP-31207-GO-RFQ- PROYECTOR Y OTROS / Request for Single Stage - One 2017-10- 2017-11- 2017-11- 2017-12- IBRD / 86750 Primary Education Post Open - National 15,000.00 27,109.60 Signed Proyectores y pantallas para Quotations Envelope 16 07 28 08 Escuelas de Tiempo Completo UY-ANEP-36028-GO-DIR / 2017-11- 2017-11- 2017-11- 2017-12- Adquisición 20 Bibliotecas IBRD / 86750 Primary Education Prior Direct Selection Direct 12,000.00 0.00 Canceled 08 13 13 15 Andariegas Page 3 UY-ANEP-37562-GO-RFQ- CERTIFICADOS / Certificados Request for Single Stage - One 2017-11- 2017-11- 2017-12- 2017-12- 2017-12- IBRD / 86750 Primary Education Post Open - National 2,000.00 985.66 Completed a entregar a Docentes Fines Quotations Envelope 24 30 01 05 08 de Cursos 2018 UY-ANEP-37564-GO-RFQ- LIBROS ANDARI 2018 / Libros Request for Single Stage - One 2017-11- 2017-12- 2017-12- 2018-02- Colección Andariega para IBRD / 86750 Early Education Post Open - National 42,000.00 34,662.17 Signed Quotations Envelope 24 12 07 15 2018 - 100 títulos con 20 ejemplares de cada uno. UY-ANEP-39537-GO-RFQ- FOTOCOPIAS DIC-JUL / 200.000 Fotocopias para los Request for Single Stage - One 2017-12- 2017-12- 2018-01- 2018-07- IBRD / 86750 Primary Education Post Open - National 8,300.00 3,168.33 Signed cursos de capacitación Quotations Envelope 13 21 04 31 docente desde diciembre 2017 a julio 2018 UY-ANEP-39545-GO-RFQ- MATERIAL E IMPRESOS / Request for Single Stage - One 2018-01- 2018-02- 2018-10- 2018-12- Materiales e impresiones IBRD / 86750 Primary Education Post Open - National 45,000.00 222.96 Signed Quotations Envelope 22 23 30 31 Formación en Servicio de Febrero a Diciembre 2018 UY-ANEP-39591-GO-RFB-EQ Single Stage - One 2018-08- 2018-08- 2018-09- 2018-09- 2018-11- 2018-12- SEMI IND 2018 / IBRD / 86750 Primary Education Post Request for Bids Open - National 192,000.00 0.00 Canceled Envelope 01 01 03 21 08 23 Electrodomésticos Industriales UY-ANEP-39594-GO-RFB- Single Stage - One 2018-01- 2018-01- 2018-01- 2018-02- 2018-02- 2018-02- 2018-03- 2018-04- 2018-05- 2018-05- VAJILLA ALUM 2018 / Vajilla y IBRD / 86750 Early Education Post Request for Bids Open - National 150,000.00 152,430.84 Signed Envelope 09 24 12 13 23 28 12 16 07 31 Aluminio para ETC 2018 UY-ANEP-39598-GO-RFQ- ELECTROD 2018 / Request for Single Stage - One 2018-01- 2018-02- 2018-01- 2018-04- IBRD / 86750 Primary Education Post Open - National 43,000.00 39,963.78 Signed Electrodomésticos (heladeras Quotations Envelope 12 09 25 10 y freezer) 2018 para ETC UY-ANEP-41033-GO-RFQ- BIBLIOG FORM INICIA / Request for Single Stage - One 2018-01- 2018-01- 2018-01- 2018-02- Biografiara para Formadores IBRD / 86750 Early Education Post Open - National 1,000.00 1,191.17 Signed Quotations Envelope 08 22 19 08 de Educación Inicial - 27 Títulos UY-ANEP-63176-GO-RFQ- LIB ANDAR COMP 2018 / Request for Single Stage - One 2018-05- 2018-06- 2018-06- 2018-07- Complemento de títulos IBRD / 86750 Early Education Post Open - National 12,000.00 1,920.34 Signed Quotations Envelope 25 08 07 09 Colección Andariega (DLI) para 2018 UY-ANEP-63182-GO-RFB- CARROS COL AND 2018 / Single Stage - One 2018-05- 2018-05- 2018-05- 2018-06- 2018-06- 2018-07- 2018-07- 2018-08- 2018-08- 2018-11- Adquisición de bibliotecas y IBRD / 86750 Primary Education Post Request for Bids Open - National 55,000.00 935,008.00 Signed Envelope 25 24 29 28 26 06 05 17 22 30 carros para colección andariega UY-ANEP-68136-GO-DIR- LIBROS C-A- 2018 / 2018-06- 2018-06- 2018-06- 2018-07- 2018-07- 2018-07- 2018-07- Complemento 9 Libros para IBRD / 86750 Early Education Post Direct Selection Direct 2,000.00 1,001.69 Signed 27 27 30 19 05 25 21 Biblioteca Colección Andariega UY-ANEP-79041-GO-RFQ- LIBROS COL AND 2019 / Libros para la Colección de Request for Single Stage - One 2018-10- 2018-10- 2018-06- 2019-02- IBRD / 86750 Early Education Post Open - National 40,000.00 1,654.17 Signed Carros Andariegos de Quotations Envelope 01 31 07 15 Educación Inicial a entregarse en febrero 2019 UY-ANEP-80467-GO-RFQ- Request for Single Stage - One 2018-10- 2018-11- 2018-12- 2018-12- ANAFES 2018 / 20 Anafes dos IBRD / 86750 Primary Education Post Open - National 26,000.00 25,620.00 Signed Quotations Envelope 10 06 13 21 fuegos a gas UY-ANEP-81645-GO-RFQ- ELECTROD-2018 / Request for Single Stage - One 2018-10- 2018-11- 2018-11- 2018-12- 2019-02- Electrodomésticos semi IBRD / 86750 Primary Education Post Open - National 46,500.00 36,743.00 Completed Quotations Envelope 19 09 09 24 15 industrial (licuadoras- batidoras y procesadoras) UY-ANEP-88454-GO-RFQ- COMP LIBROS 2019 / Complemento Libros Colección Andariega 2019. Request for Single Stage - One 2018-12- 2018-12- 2018-12- 2019-02- IBRD / 86750 Early Education Post Open - National 18,000.00 5,866.14 Signed Títulos que quedaron Quotations Envelope 04 20 19 15 desiertos y nuevos títulos que complementan colecciones anteriores UY-ANEP-99854-GO-RFB- Single Stage - One 2019-03- 2019-03- 2019-03- 2019-04- 2019-04- 2019-05- 2019-05- 2019-06- 2019-07- 2019-08- 2019-08- VAJILLA 2019 / Vajilla y IBRD / 86750 Early Education Post Request for Bids Open - National 98,000.00 77,280.72 Signed Envelope 20 19 20 19 23 02 28 03 08 17 06 utensilios de cocina UY-ANEP-99855-GO-RFB- MOB DIRECCION 2019 / Mobiliario de Dirección y Sala Single Stage - One 2019-06- 2019-10- 2019-06- 2019-07- 2019-10- 2019-07- 2019-11- 2019-08- 2019-12- 2019-11- IBRD / 86750 Early Education Post Request for Bids Open - National 65,000.00 63,027.64 Signed de Maestros (escritorios, Envelope 01 25 09 09 25 22 13 21 26 04 mesas, sillas, cajoneras, bibliotecas, etc) UY-ANEP-100302-GO-RFQ- MAT IMPRESOS 2019 / Materiales y Fotocopias del Request for Single Stage - One 2019-03- 2019-03- 2019-04- 2019-12- IBRD / 86750 Primary Education Post Open - National 24,000.00 1,599.10 Signed Componente Formación en Quotations Envelope 04 29 30 31 Servicio de Abril a Diciembre 2019 UY-ANEP-100308-GO-RFQ- PUBLICACIONES 2019 / Publicaciones para el Request for Single Stage - One 2019-03- 2019-03- 2019-12- IBRD / 86750 Primary Education Post Open - National 22,000.00 0.00 Canceled Componente Formación en Quotations Envelope 04 29 31 Servicio a realizarse entre ABRIL y DICIEMBRE 2019 UY-ANEP-99061-GO-DIR- COMP-LBROS 2019 / Libro 2019-02- 2019-02- 2019-02- 2019-02- 2019-02- 2019-02- 2019-02- para la Colección Andariega IBRD / 86750 Early Education Post Direct Selection Direct 400.00 377.56 Signed 05 12 08 20 11 22 28 2019 - Cantidad 23 del mismo titulo. UY-ANEP-99851-GO-RFB- MOBILIARIO ESC 2019 / Mobiliario Escolar, mesas, sillas y bancos para salas de Single Stage - One 2019-02- 2019-03- 2019-02- 2019-03- 2019-04- 2019-04- 2019-05- 2019-07- 2019-10- 2019-10- IBRD / 86750 Early Education Post Request for Bids Open - National 620,000.00 450,504.00 Signed preescolares, escolares y Envelope 14 11 22 24 12 06 20 05 29 03 comedor. Total de aulas: Ed. Inicial 3, 4 y 5 años: 67, 1° a 3°: 75 y 4° a 6° 77 UY-ANEP-99852-GO-RFB- EQUIP SEMI IND 2019 / Equipamiento Semi Industrial: Single Stage - One 2019-03- 2019-05- 2019-03- 2019-04- 2019-06- 2019-04- 2019-06- 2019-05- 2019-08- 2019-08- 2019-10- 10 Anafes 1 fuego, 35 IBRD / 86750 Early Education Post Request for Bids Open - National 250,000.00 188,795.00 Completed Envelope 06 03 14 13 06 26 21 26 15 09 14 Cocinas con horno, 10 Horno Eléctrico con base y 30 Anafes 2 fuegos. UY-ANEP-109107-GO-RFQ- ESCURRIDORES 2019 / Request for Single Stage - One 2019-04- 2019-05- 2019-05- 2019-06- Compra de 40 escurridores IBRD / 86750 Primary Education Post Open - National 26,600.00 19,520.00 Signed Quotations Envelope 29 26 20 25 industriales para cocina de las Escuelas de Tiempo Completo UY-ANEP-118343-GO-RFQ- CARROS ANDAR 2019 / Request for Single Stage - One 2019-06- 2019-07- 2019-07- 2019-09- Adquisición de 26 Bibliotecas IBRD / 86750 Primary Education Post Open - National 17,000.00 19,844.95 Signed Quotations Envelope 17 24 17 22 y 25 carros para Colección Andariega- año 2020 UY-ANEP-99849-GO-RFB- ELECTROD 2019 / Heladeras, Single Stage - One 2019-08- 2019-08- 2019-08- 2019-09- 2019-09- 2019-10- 2019-10- 2019-11- 2019-11- 2019-12- IBRD / 86750 Early Education Post Request for Bids Open - National 150,000.00 132,771.80 Signed freezer y electrodomésticos Envelope 28 29 29 28 30 11 14 17 25 27 industriales Page 4 UY-ANEP-141781-GO-RFQ- LIBROS ANDAR 2019 / 2.300 Libros de Colección Andariega Request for Single Stage - One 2019-10- 2019-12- 2019-11- 2020-02- para armar 23 Bibliotecas con IBRD / 86750 Early Education Post Open - National 44,000.00 31,167.17 Signed Quotations Envelope 30 06 21 28 100 títulos cada una a entregar en Escuelas de Tiempo Completo 2020 UY-ANEP-141818-NC-RFQ- CAJAS LIBROS 2020 / 60 Cajas multiuso en PVC con tapa Request for Single Stage - One 2019-10- 2019-11- 2019-11- 2019-11- IBRD / 86750 Early Education Post Open - National 500.00 333.68 Signed para guardar y transportar Quotations Envelope 28 07 22 22 los libros de la colección Andariega UY-ANEP-143901-GO-DIR- BIBLIOTECAS 2017 / 2017-11- 2017-10- 2017-11- 2017-11- 2017-11- 2017-11- 2017-12- IBRD / 86750 Primary Education Post Direct Selection Direct 12,000.00 7,666.93 Signed Adquisición 20 Bibliotecas 08 31 13 22 13 22 15 Andariegas UY-ANEP-141808-NC-RFQ- ETIQ LIBROS 2020 / Planchas de etiquetas auto adhesivas que poseen un número de Request for Single Stage - One 2019-10- 2019-11- 2019-11- IBRD / 86750 Early Education Post Open - National 1,800.00 0.00 Canceled referencia, para colocar en los Quotations Envelope 28 07 22 libros de la colección andariega, a distribuir en la ETC UY-ANEP-99847-GO-RFQ- ALFOMBRAS 2019 / Alfombras Request for Single Stage - One 2019-03- 2019-04- 2019-06- IBRD / 86750 Primary Education Post Open - National 17,000.00 0.00 Canceled y colchonetas para Educación Quotations Envelope 07 29 15 Inicial UY-ANEP-99848-GO-RFQ- EQ AUDIOVISUAL 2019 / Request for Single Stage - One 2019-05- 2019-06- 2019-08- Combo parlantes activos, IBRD / 86750 Primary Education Post Open - National 16,500.00 0.00 Canceled Quotations Envelope 07 09 15 radiograbadores y equipamiento audiovisual UY-ANEP-156960-GO-RFB- MOB ESCOLAR 2020 / Under Single Stage - One 2020-04- 2021-02- 2020-04- 2020-05- 2021-03- 2020-05- 2021-04- 2020-08- 2020-12- Mobiliario Escolar e inicial IBRD / 86750 Early Education Post Request for Bids Open - National 700,000.00 0.00 Implementati Envelope 02 25 03 04 25 15 27 20 18 para 23 Escuelas de Tiempo on Completo UY-ANEP-156964-GO-RFB- Single Stage - One 2020-04- 2020-04- 2020-04- 2020-05- 2020-05- 2020-05- 2020-06- 2020-06- 2020-08- 2020-09- VAJILLA 2020 / Vajilla y IBRD / 86750 Early Education Post Request for Bids Open - National 145,000.00 90,448.20 Signed Envelope 02 21 02 04 25 20 03 26 03 24 Aluminio para ETC UY-ANEP-156969-GO-RFB- MOB MAESTROS 2020 / Single Stage - One 2020-05- 2020-08- 2020-05- 2020-06- 2020-09- 2020-06- 2020-12- 2020-07- 2021-01- 2020-10- IBRD / 86750 Early Education Post Request for Bids Open - National 190,000.00 53,794.00 Signed Mobiliario de Dirección y Sala Envelope 04 26 05 04 25 15 23 24 13 22 de Maestros de ETC UY-ANEP-156972-GO-RFB- ELECTRODOM 2020 / Single Stage - One 2020-06- 2020-08- 2020-06- 2020-07- 2020-09- 2020-07- 2020-09- 2020-10- 2020-12- 2020-12- IBRD / 86750 Early Education Post Request for Bids Open - National 370,000.00 191,601.00 Signed Electrodomésticos industriales Envelope 15 04 16 16 04 29 15 27 17 27 para ETC UY-ANEP-157785-GO-RFQ- FOTOCOPIAS 2020 / Fotocopias de material a entregar en los encuentros Monitoring and Evaluation Request for Single Stage - One 2020-02- 2020-02- 2020-02- 2020-12- IBRD / 86750 Post Open - National 6,000.00 5,431.00 Signed docentes en el año 2020. System Quotations Envelope 10 25 27 30 Cantidad estimada 195.000 fotocopias en blanco y negro y 5.000 a color UY-ANEP-157786-GO-RFQ- MATER INICIAL 2020 / Monitoring and Evaluation Request for Single Stage - One 2020-02- 2020-02- 2020-02- 2020-02- Materiales fungibles para IBRD / 86750 Post Open - National 500.00 57.77 Signed System Quotations Envelope 06 19 20 26 encuentros docentes de Educación Inicial 2020 UY-ANEP-166127-GO-RFQ ALF. Y COLCH 2020 / Adquisición de 800 alfombras Request for Single Stage - One 2020-04- 2020-04- 2020-04- 2020-06- IBRD / 86750 Early Education Post Open - National 12,000.00 10,882.40 Signed de goma eva y 700 Quotations Envelope 01 30 30 15 colchonetas para aulas de Educación inicial de ETC UY-ANEP-156958-GO-RFQ- RADIOGRAB 2020 / Request for Single Stage - One 2020-04- 2020-04- 2020-04- 2020-06- 2020-05- IBRD / 86750 Early Education Post Open - National 30,000.00 10,399.28 Completed Radiograbadores y Kit de Quotations Envelope 01 24 27 24 02 audio para ETC UY-ANEP-189888-GO-RFQ- KIT AUDIO 2020 / 30 Combos Request for Single Stage - One 2020-08- 2020-09- 2020-10- 2020-12- Parlantes activos, micrófonos, IBRD / 86750 Early Education Post Open - National 25,000.00 19,650.00 Signed Quotations Envelope 28 25 20 24 trípodes y jirafas para Escuelas de Tiempo Completo UY-ANEP-156952-GO-RFQ- CORTINAS,ALF. 2020 / Request for Single Stage - One 2020-02- 2020-03- 2020-05- IBRD / 86750 Early Education Post Open - National 7,500.00 0.00 Canceled Cortinas, alfombras y Quotations Envelope 20 17 04 colchonetas para ETC UY-ANEP-156955-GO-RFQ- EQ AUDIOVISUA 2020 / Request for Single Stage - One 2020-02- 2020-03- 2020-05- IBRD / 86750 Early Education Post Open - National 9,000.00 0.00 Canceled Equipamiento Audiovisual Quotations Envelope 17 11 11 para ETC - Amplificadores UY-ANEP-193322-GO-RFQ- CARROS ANDAR 2020 / Request for Single Stage - One 2020-09- 2020-11- 2020-11- 2021-01- Adquisiciones de 16 IBRD / 86750 Primary Education Post Open - National 12,000.00 11,910.48 Signed Quotations Envelope 23 20 18 19 Bibliotecas y 16 carros para la Colección Andariega 2020 UY-ANEP-199051-GO-RFQ- LIBROS ANDAR 2020 / 1800 Libros para la Colección Under Andariega para armar 18 Request for Single Stage - One 2020-10- 2020-12- 2021-02- IBRD / 86750 Early Education Post Open - National 42,000.00 0.00 Implementati bibliotecas con 100 títulos Quotations Envelope 14 03 26 on cada una a entregar en los niveles de Educación Inicial de ETC en el año 2021 UY-ANEP-199057-GO-RFQ- CAJAS LIBROS 2020 / 54 Cajas Multiuso en PVC con tapa para Request for Single Stage - One 2020-10- 2020-10- 2020-10- 2020-12- IBRD / 86750 Early Education Post Open - National 320.00 231.09 Signed guardar y transportar los Quotations Envelope 14 26 26 04 libros de la Colección Andariega UY-ANEP-217877-GO-RFQ- Pending VAJILLA 2021 / VAJILLA Y Request for Single Stage - One 2021-05- 2021-07- 2021-10- IBRD / 86750 Early Education Post Open - National 43,000.00 0.00 Implementati ALUMINIO PARA ESCUELAS DE Quotations Envelope 03 23 21 on TIEMPO COMPLETO UY-ANEP-218344-GO-RFQ- ELECTRODOM 2021 / Pending Request for Single Stage - One 2021-05- 2021-07- 2021-09- Electrodomésticos semi IBRD / 86750 Early Education Post Open - National 43,000.00 0.00 Implementati Quotations Envelope 03 16 14 industrial para Escuelas de on Tiempo Completo UY-ANEP-156965-GO-RFQ- HELADERAS 2020 / Heladeras Request for Single Stage - One 2020-05- 2020-06- 2020-08- IBRD / 86750 Early Education Post Open - National 44,000.00 0.00 Canceled con freezer y freezer Quotations Envelope 04 19 18 horizontal para ETC UY-ANEP-229505-GO-RFQ- LIC ZOOM EDUC 2021 / 20 Licencias de Zoom educativo Request for Single Stage - One 2021-04- 2021-05- 2021-05- 2022-05- que permitan cumplir con la IBRD / 86750 Early Education Post Open - National 2,500.00 2,196.00 Signed Quotations Envelope 26 12 03 11 planificación de los cursos de Formación en Servicio para el año 2021. NON CONSULTING SERVICES Activity Reference No. / Draft Pre- Draft Bidding Bid Evaluation Report Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Prequalification Specific Procurement Bidding Documents as Proposal Submission Description Component Review Type Method qualification Document / and Recommendation Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Evaluation Report Notice / Invitation Issued / Opening / Minutes Documents Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 5 UY-ANEP-14561-NC-RFQ- INSPECTORES 2017 / Jornada Request for Single Stage - One 2017-05- 2017-06- 2017-05- 2017-12- IBRD / 86750 Early Education Post Open - National 28,000.00 20,436.68 Signed de Inspectores TC . 2 Quotations Envelope 15 06 29 05 jornadas/año - 115 personas UY-ANEP-14487-NC-RFQ FORMADORES 2017 / 9 Request for Single Stage - One 2017-05- 2017-06- 2017-05- 2017-12- Encuentros de Formadores de IBRD / 86750 Early Education Post Open - National 48,000.00 28,990.00 Signed Quotations Envelope 15 06 29 31 TC de junio a diciembre - 65 participantes por fecha UY-ANEP-14716-NC-RFQ- GESTION ESC NUEVAS / 2017 Request for Single Stage - One 2017-03- 2017-03- 2017-03- 2017-07- - 4 Encuentros Gestión IBRD / 86750 Early Education Post Open - National 17,906.00 16,122.38 Signed Quotations Envelope 08 24 24 15 Escuelas Nuevas de TC - 90 participantes UY-ANEP-14562-NC-RFQ- DIRECTORES 2017 / Jornada Request for Single Stage - One 2017-05- 2017-06- 2017-06- 2017-11- IBRD / 86750 Early Education Post Open - National 36,000.00 32,676.93 Signed Directores . 2 jornadas/año - Quotations Envelope 15 06 13 07 145 personas UY-ANEP-15335-NC-RFQ / Jornadas apoyo a la Request for Single Stage - One 2017-05- 2017-05- 2017-05- 2017-06- Coordinación de Tiempo IBRD / 86750 Early Education Post Open - National 10,500.00 8,576.61 Signed Quotations Envelope 17 29 30 01 Completo del CEIP - Junio 2017 UY-ANEP-17531-NC-RFQ- ALOJ SEMINARIO INT / Alojamiento para docentes del Interior que participarán en el Request for Single Stage - One 2017-06- 2017-08- 2017-07- 2017-08- IBRD / 86750 Early Education Post Open - National 12,000.00 3,247.89 Signed Seminario Internacional a Quotations Envelope 20 01 27 31 realizarse en la IMM de Educación Inicial los días 28 y 29 de agosto 2017. UY-ANEP-19221-NC-RFQ / Encuentro 14 de julio 2017 Directores de Tiempo Request for Single Stage - One 2017-07- 2017-07- 2017-07- 2017-07- Completo de Rivera, IBRD / 86750 Early Education Post Open - National 3,000.00 1,302.95 Signed Quotations Envelope 03 10 06 14 Tacuarembó, Salto y Paysandú con equipo de Cultura Institucional UY-ANEP-19230-NC-RFQ / Jornadas apoyo a la Request for Single Stage - One 2017-07- 2017-07- 2017-08- 2017-12- Coordinación de Tiempo IBRD / 86750 Early Education Post Open - National 15,000.00 16,651.49 Signed Quotations Envelope 04 18 16 31 Completo del CEIP. Agosto- Diciembre 2017 UY-ANEP-14802-NC-RFB- CONGRESO ETC 2017 / Single Stage - One 2017-06- 2017-06- 2017-07- 2017-07- 2017-07- 2017-08- IBRD / 86750 Early Education Post Request for Bids Open - National 60,000.00 0.00 Canceled Congreso de Tiempo Envelope 01 05 05 17 27 31 Completo 2017 UY-ANEP-19868-NC-RFQ / ALOJAMIENTO 35 docentes Request for Single Stage - One 2017-07- 2017-07- 2017-07- 2017-07- ETC Interior ENCUENTRO IBRD / 86750 Early Education Post Open - National 1,100.00 173.76 Signed Quotations Envelope 12 21 24 29 EDUCACIÓN INICIAL 29 JULIO 2017 UY-ANEP-23913-NC-RFQ- IMPRESOS SEMINARIO / Folletería, banners, certificados e invitaciones Request for Single Stage - One 2017-08- 2017-08- 2017-08- 2017-08- 2017-08- IBRD / 86750 Early Education Post Open - National 2,000.00 562.06 Completed para el SEMINARIO Quotations Envelope 06 15 09 25 22 INTERNACIONAL a realizarse en la IMM, el 28 y 29 de agosto 2017 UY-ANEP-27748-NC-RFQ- DIRECTORES / ESCUELAS Request for Single Stage - One 2017-09- 2017-09- 2017-09- IBRD / 86750 Early Education Post Open - National 1,500.00 0.00 Canceled NUEVAS - LOGÍSTICA PARA Quotations Envelope 14 25 30 JORNADA CON DIRECTORES UY-ANEP-29308-NC-RFQ- ETIQUETAS LIBROS / Etiquetas Request for Single Stage - One 2017-09- 2017-09- 2017-10- 2017-10- IBRD / 86750 Early Education Post Open - National 1,800.00 732.06 Signed auto adhesivas para colección Quotations Envelope 21 29 03 04 libros carros ANDARIEGOS UY-ANEP-14718-NC-RFQ- ENCUENTRO DIR 2017 / Encuentro 27 junio 2017 Request for Single Stage - One 2017-05- 2017-06- 2017-06- 2017-06- IBRD / 86750 Early Education Post Open - National 1,800.00 1,184.10 Signed Directores de Montevideo y Quotations Envelope 22 05 01 27 Canelones con equipo de Cultura Institucional UY-ANEP-34709-NC-RFQ- COFFEE JORNADA / Servicio Request for Single Stage - One 2017-11- 2017-11- 2017-11- 2017-11- de coffee break para jornada IBRD / 86750 Early Education Post Open - National 1,200.00 970.48 Signed Quotations Envelope 03 08 07 13 de Maestros de Tiempo Completo UY-ANEP-19225-NC-DIR / Sala y Coffee Break para Seminario Internacional a 2017-06- 2017-06- 2017-06- 2017-06- 2017-07- 2017-07- 2017-08- IBRD / 86750 Early Education Post Direct Selection Direct 8,500.00 4,242.13 Signed realizarse en la Intendencia 27 22 27 27 10 27 29 Municipal de Montevideo el 28 y 29 agosto 2017 UY-ANEP-39581-NC-RFQ- JORNADA C-ANDARIEGA / Jornadas Colección Andariega . Logística para jornadas - Request for Single Stage - One 2018-02- 2018-03- 2018-04- 2018-11- alquiler de salones equipados, IBRD / 86750 Early Education Post Open - National 45,000.00 23,714.97 Signed Quotations Envelope 09 04 03 03 servicio de catering (desayunos, cofee break, almuerzos, cenas) , alojamiento, traslados . UY-ANEP-39566-NC-RFQ- APOYO TC DIRECTORES / Apoyo a la Inspección Nacional de Tiempo Completo Encuentro de Directores de Marzo a Diciembre 2018. Request for Single Stage - One 2018-03- 2018-03- 2018-08- 2018-12- IBRD / 86750 Early Education Post Open - National 32,000.00 15,188.32 Signed Logística para jornadas - Quotations Envelope 05 23 16 31 alquiler de salones equipados, servicio de catering (desayunos, cofee break, almuerzos, cenas) , alojamiento, traslados . UY-ANEP-39572-NC-RFQ- APOYO TC INSPECT / Apoyo a la Inspección Nacional de Tiempo Completo Encuentro de Inspectores desde marzo a Request for Single Stage - One 2018-03- 2018-03- 2018-03- 2018-12- diciembre 2018. Logística IBRD / 86750 Early Education Post Open - National 18,000.00 5,692.71 Signed Quotations Envelope 05 23 20 31 para jornadas - alquiler de salones equipados, servicio de catering (desayunos, cofee break, almuerzos, cenas) , alojamiento, traslados . UY-ANEP-39578-NC-RFQ- INSPECTORES ETC / Jornadas de Inspectores de ETC. Logística para jornadas - Request for Single Stage - One 2018-03- 2018-03- 2018-03- 2018-10- alquiler de salones equipados, IBRD / 86750 Early Education Post Open - National 15,000.00 10,612.08 Signed Quotations Envelope 02 18 20 29 servicio de catering (desayunos, cofee break, almuerzos, cenas) , alojamiento, traslados . UY-ANEP-39552-NC-RFB- FORMADORES FEB-JUL / Encuentros de Formadores ETC . Logística para jornadas Single Stage - One 2018-01- 2018-03- 2018-01- 2018-02- 2018-04- 2018-02- 2018-04- 2018-02- 2018-04- 2018-12- - alquiler de salones IBRD / 86750 Early Education Post Request for Bids Open - National 75,000.00 38,562.73 Signed Envelope 04 02 04 05 04 08 04 15 06 07 equipados, servicio de catering (desayunos, cofee break, almuerzos, cenas) , alojamiento, traslados . Page 6 UY-ANEP-39576-NC-RFB- DIRECTORES ETC / Jornadas encuentros de Maestros Directores de ETC. Logística Single Stage - One 2018-01- 2018-02- 2018-01- 2018-02- 2018-03- 2018-02- 2018-03- 2018-02- 2018-03- 2018-10- para jornadas - alquiler de IBRD / 86750 Early Education Post Request for Bids Open - National 65,000.00 41,494.40 Signed Envelope 17 05 17 16 08 28 12 28 13 22 salones equipados, servicio de catering (desayunos, cofee break, almuerzos, cenas) , alojamiento, traslados . UY-ANEP-39557-NC-RFB- JORNADAS ED INICIAL / Jornadas de Educación Inicial. Logística para jornadas - Single Stage - One 2018-02- 2018-02- 2018-02- 2018-03- 2018-02- 2018-03- 2018-02- 2018-03- 2018-03- 2018-10- alquiler de salones equipados, IBRD / 86750 Early Education Post Request for Bids Open - National 90,000.00 24,124.72 Signed Envelope 12 07 12 12 23 16 27 23 01 27 servicio de catering (desayunos, cofee break, almuerzos, cenas) , alojamiento, traslados . UY-ANEP-48227-NC-RFQ- JORNADAS CON SOUTO / Jornadas de Formadores PAEPU con experta Marta Souto, Logística para Request for Single Stage - One 2018-02- 2018-02- 2018-06- 2018-07- IBRD / 86750 Early Education Post Open - National 20,000.00 10,886.04 Signed jornadas: alquiler de salones Quotations Envelope 16 28 13 31 equipados, servicio de catering (desayuno, coffee break, almuerzos y cenas), alojamiento y transporte. UY-ANEP-52242-NC-RFQ- CURSO I 2018 / Jornadas para Maestros y Directores de ETC - CURSO 1 a realizarse en 2018. Logística para Request for Single Stage - One 2018-03- 2018-04- 2018-04- 2018-11- IBRD / 86750 Early Education Post Open - National 40,000.00 32,896.60 Signed jornadas: alquiler de salones Quotations Envelope 12 03 04 17 equipados, servicio de catering (desayuno, coffee break, almuerzos y cenas), alojamiento y transporte. UY-ANEP-58126-NC-RFQ- JORNADA 24-4-18 / JORNADA CAPACITACIÓN Request for Single Stage - One 2018-04- 2018-04- 2018-04- 2018-04- Directores y Maestros de IBRD / 86750 Early Education Post Open - National 7,000.00 5,811.64 Signed Quotations Envelope 13 19 18 24 Escuelas que participan en observación de aula a realizarse el 24 de abril 2018 UY-ANEP-63188-NC-DIR- DIRECTORE COMPL2018 / Logística para dos jornadas de 2018-05- 2018-05- 2018-05- 2018-05- 2018-06- 2018-05- 2018-07- IBRD / 86750 Early Education Post Direct Selection Direct 15,000.00 13,980.18 Signed capacitación de Directores de 17 16 22 14 22 24 31 ETC a realizarse en mayo y julio 2018 UY-ANEP-81638-NC-RFQ- ETIQUETAS 2018 / Etiquetas Request for Single Stage - One 2018-10- 2018-10- 2018-10- para libros colección IBRD / 86750 Early Education Post Open - National 1,500.00 0.00 Canceled Quotations Envelope 18 26 31 andariega a ser entregados principio 2019 UY-ANEP-45071-NC-DIR- IMPRESION CATALOGO / 2018-01- 2018-01- 2018-12- 2018-12- 2018-12- 2018-12- 2019-02- Impresión de Catálogos para IBRD / 86750 Early Education Post Direct Selection Direct 3,700.00 4,295.23 Signed 22 02 10 05 14 18 28 la Colección Andariega - IMPRENTA MASTERGRAF SRL UY-ANEP-94804-NC-RFQ- JORNADA BIRF 2019 / ENCUENTRO con EXPERTA BANCO MUNDIAL Request for Single Stage - One 2019-01- 2019-01- 2019-01- 2019-02- Alojamientos para Directores IBRD / 86750 Early Education Post Open - National 1,200.00 580.52 Signed Quotations Envelope 21 25 22 12 y Maestros de TC que participarán en la Jornada con Experta enviada por el Banco Mundial el 12/2/19 UY-ANEP-94805-NC-RFQ- FORM FEB-MAR 2019 / FORMADORES DE TC - Logística para encuentro de Formadores de TC a realizarse Request for Single Stage - One 2019-01- 2019-02- 2019-02- 2019-03- IBRD / 86750 Early Education Post Open - National 13,000.00 10,398.45 Signed en Febrero y Marzo 2019 Quotations Envelope 21 05 01 08 Alojamientos, Alquiler del salón equipado, Servicio de Catering (Desayunos, Coffee Break, Almuerzo y Cena). UY-ANEP-94891-NC-RFQ- JORN-DIREC-MAR2019 / EDUCACIÓN INICIAL - DIRECTORES Logística para Jornada con Directores de Request for Single Stage - One 2019-01- 2019-02- 2019-02- 2019-03- IBRD / 86750 Early Education Post Open - National 4,000.00 3,102.07 Signed Educación Inicial a realizarse Quotations Envelope 28 13 07 29 en Marzo 2019 Alojamientos, Alquiler del salón equipado, Servicio de Catering (Desayuno y Coffee Break). UY-ANEP-94892-NC-RFQ- JOR-ED INIC 3-2019 / DOCENTES EDUCACIÓN INICIAL Una Mirada Integradora. Logística para Request for Single Stage - One 2019-02- 2019-02- 2019-02- 2019-03- encuentro de Docentes de IBRD / 86750 Early Education Post Open - National 5,500.00 3,909.73 Signed Quotations Envelope 05 18 27 30 Educación Inicial . Alojamientos, Alquiler del salón equipado, Servicio de Catering (Desayuno y Coffee Break). UY-ANEP-94895-NC-RFQ- CURSO I MARZO 2019 / CURSO I Logística para encuentro de docentes a Request for Single Stage - One 2019-01- 2019-02- 2019-02- 2019-03- realizarse en Marzo 2019 IBRD / 86750 Early Education Post Open - National 6,000.00 4,693.60 Signed Quotations Envelope 30 19 07 16 Alojamientos, Alquiler del salón equipado, Servicio de Catering (Desayunos, Coffee Break, Almuerzo y Cena). UY-ANEP-94897-NC-RFQ- JORNADA MARZO 2019 / DIRECTORES E INSPECTORES TC. Logística para encuentro de Directores e Inspectores Request for Single Stage - One 2019-01- 2019-02- 2019-02- 2019-03- IBRD / 86750 Early Education Post Open - National 11,000.00 9,663.32 Signed TC a realizarse en Marzo Quotations Envelope 30 19 07 12 2019 Alojamientos, Alquiler del salón equipado, Servicio de Catering (Desayunos, Coffee Break, Almuerzo y Cena). UY-ANEP-94898-NC-RFQ- JORNADA MARZO 2019 / ENCUENTRO con MARTA SOUTO. Logística para encuentro de Formadores de TC con la Consultora Marta Request for Single Stage - One 2019-02- 2019-02- 2019-02- 2019-03- 2019-03- IBRD / 86750 Early Education Post Open - National 5,000.00 3,629.25 Completed Souto a realizarse en Marzo Quotations Envelope 05 18 12 27 27 2019 Alojamientos, Alquiler del salón equipado, Servicio de Catering (Desayunos, Coffee Break, Almuerzo y Cena). UY-ANEP-100260-NC- RFQJOR-ED INIC 2019 / DOCENTES EDUCACIÓN INICIAL Una Mirada Integradora. Logística para Request for Single Stage - One 2019-03- 2019-04- 2019-04- 2019-10- encuentro de Docentes de IBRD / 86750 Early Education Post Open - National 26,000.00 11,297.16 Signed Quotations Envelope 15 05 12 19 Educación Inicial. Alojamientos, Alquiler del salón equipado, Servicio de Catering (Desayuno y Coffee Break). ABRIL A OCTUBRE 2019 Page 7 UY-ANEP-100269-NC-RFQ- JORN-DIREC-2019 / EDUCACIÓN INICIAL - DIRECTORES Logística para Jornada con Directores de Request for Single Stage - One 2019-03- 2019-03- 2019-03- 2019-10- IBRD / 86750 Early Education Post Open - National 28,000.00 21,681.41 Signed Educación Inicial. Quotations Envelope 15 30 26 25 Alojamientos, Alquiler del salón equipado, Servicio de Catering (Desayuno y Coffee Break). ABRIL A OCTUBRE 2019 UY-ANEP-100270-NC-RFQ- CONFERENCIAS 2019 / EDUCACIÓN INICIAL. Dos Request for Single Stage - One 2019-04- 2019-04- 2019-04- 2019-08- conferencias con Consultoras IBRD / 86750 Early Education Post Open - National 5,000.00 11,124.21 Signed Quotations Envelope 02 21 12 17 Expertas a realizarse en mayo y agosto 2019. Servicio de Catering (Coffee Break). UY-ANEP-100271-NC-RFQ- ALOJ ANDARIEGA-19 / ALOJAMIENTOS COLECCIÓN ANDARIEGA - Para docentes Request for Single Stage - One 2019-03- 2019-03- 2019-03- 2019-10- IBRD / 86750 Early Education Post Open - National 7,000.00 4,764.31 Signed de Educación Inicial que Quotations Envelope 13 31 12 26 participaran en encuentros a realizarse entre abril y octubre 2019. UY-ANEP-100274-NC-RFQ- CURSO I 201 / CURSO I Logística para encuentro de docentes . Alojamientos, Request for Single Stage - One 2019-03- 2019-04- 2019-03- 2019-10- Alquiler del salón equipado, IBRD / 86750 Early Education Post Open - National 35,000.00 25,778.44 Signed Quotations Envelope 15 01 07 19 Servicio de Catering (Desayunos, Coffee Break) a realizarse de ABRIL a OCTUBRE 2019 UY-ANEP-100279-NC-RFQ- JORNAD SOUTO 2019 / ENCUENTROS con MARTA SOUTO. Logística para encuentros de Formadores de TC con la Consultora Marta Request for Single Stage - One 2019-06- 2019-06- 2019-05- 2019-10- 2019-10- IBRD / 86750 Early Education Post Open - National 16,000.00 16,266.71 Completed Souto. Alojamientos, Alquiler Quotations Envelope 06 25 09 30 30 del salón equipado, Servicio de Catering (Desayunos, Coffee Break, Almuerzo y Cena) a realizarse en JULIO Y OCTUBRE 2019 UY-ANEP-100284-NC- DIRECT E INSPECT 2019 / DIRECTORES E INSPECTORES TC. Logística para encuentro de Directores e Inspectores Request for Single Stage - One 2019-02- 2019-03- 2019-03- 2019-10- TC Alojamientos, Alquiler del IBRD / 86750 Early Education Post Open - National 44,300.00 41,725.67 Signed Quotations Envelope 21 18 18 10 salón equipado, Servicio de Catering (Desayunos, Coffee Break, Almuerzo y Cena) a realizarse desde ABRIL a NOVIEMBRE 2019 UY-ANEP-100295-NC-RFQ- COHORTE 1 - 2019 / DIRECTORES TC COHORTE 1 Proceso formativo 2017- 2018. Logística para encuentros de Directores TC . Request for Single Stage - One 2019-04- 2019-04- 2019-04- 2019-09- IBRD / 86750 Early Education Post Open - National 11,000.00 18,287.87 Signed Alojamientos, Alquiler del Quotations Envelope 05 24 30 10 salón equipado, Servicio de Catering (Desayunos, Coffee Break, Almuerzo y Cena) a realizarse entre MAYO y SETIEMBRE 2019 UY-ANEP-100299-NC-RFQ- JORN-COORD-2019 / ENCUENTROS con COORDINACIÓN GENERAL y asesora GRACIELA FRIGERIO . Logística para el desarrollo de Request for Single Stage - One 2019-03- 2019-03- 2019-04- 2019-12- IBRD / 86750 Early Education Post Open - National 18,000.00 13,830.56 Signed jornadas: Alojamientos, Quotations Envelope 05 25 24 03 Alquiler del salón equipado, Servicio de Catering (desayunos, coffee, almuerzo y cena), a realizarse desde ABRIL a DICIEMBRE 2019 UY-ANEP-100315-NC-RFQ- FORMADORES 2019 / FORMADORES DE TC - Logística para encuentro de Formadores de TC . Request for Single Stage - One 2019-02- 2019-03- 2019-04- 2019-12- Alojamientos, Alquiler del IBRD / 86750 Early Education Post Open - National 48,000.00 42,103.39 Signed Quotations Envelope 20 20 01 06 salón equipado, Servicio de Catering (Desayunos, Coffee Break, Almuerzo y Cena) a realizarse entre ABRIL y DICIEMBRE 2019 UY-ANEP-106181-NC-DIR- AMPL CATALOGOS2019 / Ampliación impresión Catálogos Colección 2019-03- 2019-03- 2019-03- 2019-03- 2019-03- 2019-03- 2019-04- IBRD / 86750 Early Education Post Direct Selection Direct 4,200.00 3,773.25 Signed Andariega para entregar junto 14 14 18 14 21 28 30 con las Bibliotecas en Escuelas que constituyen cohorte 2017- 2018-2019 UY-ANEP-113313-NC-RFQ- JORN INSP TC-2019 / Jornada para Inspectores referente (apoyo a la Inspección Nacional de T.C). Logística para el desarrollo de la Request for Single Stage - One 2019-05- 2019-05- 2019-05- 2019-12- IBRD / 86750 Early Education Post Open - National 10,000.00 7,376.51 Signed jornadas : Alojamiento, Quotations Envelope 10 20 17 03 alquiler de salón equipado, servicio de Catering ( desayuno, coffe, almuerzo, cena ) en Mayo y diciembre 2019. UY-ANEP-113315-NC-RFQ- JORN DIREC TC-2019 / Encuentro Directores - Apoyo a la Inspección Nacional de TC- Logística para el desarrollo de Request for Single Stage - One 2019-05- 2019-05- 2019-05- 2019-10- las jornadas : Alojamiento, IBRD / 86750 Early Education Post Open - National 12,000.00 9,065.31 Signed Quotations Envelope 13 29 17 29 Alquiler de salón equipado, Servicio de Catering ( desayuno, cofee,almuerzo, cena) a realizarse en Octubre del 2019 UY-ANEP-116997-NC-RFQ- ALOJ-SEMINARIOS / Alojamientos para docentes de los pueblos de Nico Pérez, Florida y Batlle y Ordoñez, Request for Single Stage - One 2019-05- 2019-06- 2019-06- 2019-09- IBRD / 86750 Early Education Post Open - National 1,100.00 681.72 Terminated Lavalleja que participarán en Quotations Envelope 31 05 05 06 los seminarios territorio a efectuarse en Montevideo los días 7/06, 19/07, 09/08 y 06/09. Cantidad 10 UY-ANEP-128558-NC-RFQ- ALOJAMIENTOS 2019 / Alojamientos para docentes del Interior que participarán Request for Single Stage - One 2019-08- 2019-08- 2019-08- 2019-10- IBRD / 86750 Early Education Post Open - National 2,500.00 1,242.32 Signed en jornadas de capacitación el Quotations Envelope 26 31 30 25 6 de setiembre y el 25 de octubre 2019 (40 y 30 alojamientos respectivamente) UY-ANEP-157748-NC-RFQ- FORM FEB/MZO 2020 / Servicio de alojamiento con Request for Single Stage - One 2020-02- 2020-02- 2020-02- 2020-03- desayuno para docentes del IBRD / 86750 Early Education Post Open - National 2,700.00 2,466.04 Signed Quotations Envelope 10 17 14 20 Interior que participarán en los encuentros de Formadores febrero/marzo 2020 Page 8 UY-ANEP-157749-NC-RFQ- FORM ABR-DIC 2020 / Servicio de alojamiento con Request for Single Stage - One 2020-03- 2020-03- 2020-03- 2020-12- desayuno para docentes del IBRD / 86750 Early Education Post Open - National 6,700.00 2,003.22 Signed Quotations Envelope 02 22 16 30 Interior que participarán en los encuentros de Formadores abril- diciembre 2020 UY-ANEP-157751-NC-RFQ- CURSOI ABR-NOV2020 / CURSO I Logística para encuentro de docentes. Request for Single Stage - One 2020-03- 2020-03- 2020-03- 2020-11- Alojamientos, Alquiler del IBRD / 86750 Early Education Post Open - National 31,000.00 26,351.46 Signed Quotations Envelope 02 19 12 19 salón equipado, Servicio de Catering (Desayunos, Coffee Break) a realizarse de ABRIL a NOVIEMBRE 2020 UY-ANEP-157753-NC-RFQ- DIREC INICIAL 2020 / DIRECTORES DE EDUCACIÓN INICIAL - Logística para encuentro de docentes . Request for Single Stage - One 2020-03- 2020-03- 2020-03- 2020-10- IBRD / 86750 Early Education Post Open - National 41,000.00 4,385.66 Signed Alojamientos, Alquiler del Quotations Envelope 02 27 12 31 salón equipado, Servicio de Catering (Desayunos, Coffee Break, Almuerzos) a realizarse de ABRIL a OCTUBRE 2020 UY-ANEP-157763-NC-RFQ- DIRECT. MARZO 2020 / DIRECTORES - Logística para encuentro de docentes . Request for Single Stage - One 2020-02- 2020-02- 2020-02- 2020-03- Alojamientos, Alquiler del IBRD / 86750 Early Education Post Open - National 6,300.00 6,348.01 Signed Quotations Envelope 12 21 27 31 salón equipado, Servicio de Catering (Desayunos, Coffee Break, Almuerzo) a realizarse en MARZO 2020 UY-ANEP-157768-NC-RFQ- DIREC ABR-OCT 2020 / DIRECTORES - Logística para encuentro de docentes . Request for Single Stage - One 2020-03- 2020-03- 2020-03- 2020-10- Alojamientos, Alquiler del IBRD / 86750 Early Education Post Open - National 32,000.00 22,138.15 Signed Quotations Envelope 02 17 17 30 salón equipado, Servicio de Catering (Desayunos, Coffee Break, Almuerzo) a realizarse desde ABRIL a OCTUBRE 2020 UY-ANEP-157775-NC-RFQ- INSP MARZO 2020 / INSPECTORES- Logística para encuentro de docentes . Request for Single Stage - One 2020-02- 2020-02- 2020-02- 2020-03- Alojamientos, Alquiler del IBRD / 86750 Early Education Post Open - National 2,300.00 4,255.53 Signed Quotations Envelope 11 21 27 31 salón equipado, Servicio de Catering (Desayunos, Coffee Break, Almuerzo) a realizarse en MARZO 2020 UY-ANEP-157776-NC-RFQ- INSP JUN-OCT 2020 / INSPECTORES - Logística para encuentro de docentes . Request for Single Stage - One 2020-05- 2020-05- 2020-02- 2020-10- Alojamientos, Alquiler del IBRD / 86750 Early Education Post Open - National 7,000.00 3,769.55 Signed Quotations Envelope 04 19 27 30 salón equipado, Servicio de Catering (Desayunos, Coffee Break, Almuerzo) a realizarse en JUNIO a OCTUBRE 2020 UY-ANEP-157781-NC-RFQ- AUDIO INICIAL 2020 / Servicio audio, video y apoyo Request for Single Stage - One 2020-03- 2020-03- 2020-11- IBRD / 86750 Early Education Post Open - National 2,000.00 0.00 Canceled tecnológico para jornadas de Quotations Envelope 04 15 30 Educación Inicial a realizarse entre abril y noviembre 2020 UY-ANEP-157782-NC-RFQ- MAESTROS MZO 2020 / MAESTROS ED INICIAL - Logística para encuentro de Request for Single Stage - One 2020-02- 2020-02- 2020-02- 2020-03- docentes . Alojamientos, IBRD / 86750 Early Education Post Open - National 5,000.00 4,564.84 Signed Quotations Envelope 10 19 27 31 Alquiler del salón equipado, Servicio de Catering (Desayunos, Coffee Break) a realizarse en MARZO 2020 UY-ANEP-157783-NC-RFQ- MAEST ABR-NOV 2020 / MAESTROS INICIAL - Logística para encuentro de docentes . Request for Single Stage - One 2020-03- 2020-03- 2020-06- 2020-11- IBRD / 86750 Early Education Post Open - National 40,000.00 35,670.12 Signed Alojamientos, Servicio de Quotations Envelope 04 30 01 30 Catering (Desayunos, Coffee Break, ) a realizarse desde ABRIL - NOVIEMBRE 2020 UY-ANEP-157780-NC-RFQ- ANDAR ABR-NOV 2020 / COLECCIÓN ANDARIEGA- Logística para encuentro de docentes . Alojamientos ,alquiler de salon equipado , Request for Single Stage - One 2020-03- 2020-03- 2020-03- 2020-11- IBRD / 86750 Early Education Post Open - National 15,000.00 8,269.02 Signed Servicio de Catering Quotations Envelope 11 27 25 14 (Desayunos, Coffee Break, ) a realizarse en 5 encuentros entre ABRIL y NOVIEMBRE 2020- Participantes - 80 por jornada. UY-ANEP-199059-NC-RFQ- IMP CATALOGO 2020 / Request for Single Stage - One 2020-10- 2020-10- 2020-11- 2021-02- Impresión de 25 catálogos de IBRD / 86750 Early Education Post Open - National 1,500.00 351.92 Signed Quotations Envelope 14 28 09 08 libros para la colección andariega CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual UY-ANEP-14569-CS-INDV- Individual Monitoring and Evaluation 2017-06- 2017-06- 2017-06- 2017-12- AS TERMICO 2017 / Asesores IBRD / 86750 Post Consultant Limited 3,000.00 0.00 Canceled 2017-06-01 System 01 01 01 29 Técnicos Eventuales Térmicos Selection UY-ANEP-14803-CS-INDV- Individual SARAVIA / Carola Saravia, Monitoring and Evaluation 2017-04- 2017-05- 2017-05- 2017-06- 2017-08- 2017-09- IBRD / 86750 Post Consultant Direct 7,500.00 6,335.77 Signed 2017-05-12 contratación Técnica Gestión System 05 15 18 19 09 19 Selection Cultural UY-ANEP-14559-CS-CDS- THE LEARNING 2017 / Desarrollo y gestión de sistema de Información para Monitoring and Evaluation 2017-04- 2017-05- 2017-09- 2017-08- 2017-12- la detección temprana de IBRD / 86750 Post Direct Selection Direct 120,000.00 120,000.00 Signed 2017-05-22 System 26 22 05 02 31 debilidades en el desarrollo evolutivo de los niños de Inicial - año 2107 (The Learning Bar) UY-ANEP-14571-CS-INDV- Individual DIRECT OBRA 2017 / 8 Pending 2017-06- 2017-06- 2017-06- 2017-12- IBRD / 86750 Primary Education Post Consultant Limited 48,500.00 0.00 2017-06-01 Directores de Obra para obras Implementation 01 01 01 29 Selection a iniciar 2017 UY-ANEP-14482-CS-INDV Individual MARTA SOUTO 2017 / Asesor Monitoring and Evaluation 2018-03- 2017-06- 2017-04- 2017-06- 2017-04- 2017-07- 2017-04- 2017-08- 2017-08- IBRD / 86750 Post Consultant Direct 1,400.00 4,200.00 Completed 2017-06-14 externo para Formación en System 09 19 18 26 18 03 27 31 31 Selection Servicio Dra. Marta Souto Page 9 UY-ANEP-14556-CS-INDV- Individual UCP 2017 / Coordinación 2017-06- 2017-06- 2017-06- 2017-06- 2017-06- 2017-06- 2022-05- IBRD / 86750 Early Education Post Consultant Direct 119,064.00 83,195.86 Signed 2017-06-01 Administrativa 1 contrato 01 01 01 01 01 01 31 Selection junio 2017 - mayo 2022 UY-ANEP-14555-CS-INDV- Individual UCP-2017 / Equipamiento 2 2017-06- 2017-06- 2017-06- 2017-06- 2017-06- 2017-06- 2017-06- 2022-05- IBRD / 86750 Early Education Post Consultant Direct 359,672.00 223,748.09 Signed 2017-06-01 contratos junio 2017 - mayo 01 01 01 01 01 01 01 31 Selection 2022 UY-ANEP-14553-CS-INDV- Individual UCP-2017 / Adquisiciones 4 2017-06- 2017-06- 2017-06- 2017-06- 2017-06- 2017-06- 2017-06- 2022-05- IBRD / 86750 Early Education Post Consultant Direct 776,072.00 320,430.42 Signed 2017-06-01 contratos junio 2017 - mayo 01 01 01 01 01 01 01 31 Selection 2022 UY-ANEP-14558-CS-INDV- Individual UCP 2017 / Asesoramiento 2017-06- 2017-06- 2017-06- 2017-06- 2017-06- 2017-06- 2022-05- IBRD / 86750 Early Education Post Consultant Direct 169,276.00 96,730.90 Signed 2017-06-01 Jurídico 1 Contrato junio 01 01 01 01 01 01 31 Selection 2017 - mayo 2022 UY-ANEP-14557-CS-INDV- Individual UCP-2017 / Apoyo 2017-06- 2017-06- 2017-06- 2017-06- 2017-06- 2017-06- 2017-06- 2022-05- IBRD / 86750 Early Education Post Consultant Direct 395,295.00 243,385.63 Signed 2017-06-01 Informático 3 contratos junio 01 01 01 01 01 01 01 31 Selection 2017 - mayo 2022 UY-ANEP-14552-CS-INDV- Individual UCP 2017 / Programación y 2017-06- 2017-06- 2017-06- 2017-06- 2017-06- 2017-06- 2017-06- 2022-05- IBRD / 86750 Early Education Post Consultant Direct 483,820.00 304,287.96 Signed 2017-06-01 Monitoreo 3 contratos junio 01 01 01 01 01 01 01 31 Selection 2017 - mayo 2022 UY-ANEP-14551-CS-INDV- Individual UCP-2017 / Planta Física 19 2017-06- 2017-06- 2017-06- 2017-06- 2017-06- 2017-06- 2017-06- 2022-05- IBRD / 86750 Early Education Post Consultant Direct 3,362,686.00 2,690,843.69 Signed 2017-06-01 contratos junio 2017 - mayo 01 01 01 01 01 01 01 31 Selection 2022 UY-ANEP-14550-CS-INDV- Individual UCP-2017 / Formación en 2017-06- 2017-06- 2017-06- 2017-06- 2017-06- 2017-06- 2018-01- 2022-05- IBRD / 86750 Early Education Post Consultant Direct 388,337.00 89,517.33 Signed 2017-06-01 Servicio 3 contratos junio 01 01 01 01 01 01 01 31 Selection 2017 - mayo 2022 UY-ANEP-14554-CS-INDV- Individual UCP-2017 / Finanzas y 2017-07- 2017-06- 2017-06- 2017-06- 2017-06- 2017-06- 2017-06- 2022-05- IBRD / 86750 Early Education Post Consultant Direct 225,700.00 109,249.62 Signed 2017-06-01 Desembolsos 1 contrato junio 01 01 01 01 01 01 01 31 Selection 2017 - mayo 2022 UY-ANEP-14563-CS-INDV- Individual AS CIVILES 2017 / 5 Asesores Monitoring and Evaluation Under 2017-06- 2017-06- 2017-06- 2017-12- IBRD / 86750 Post Consultant Limited 33,000.00 0.00 2017-06-01 Técnicos Eventuales System Implementation 01 01 01 29 Selection Ingenieros Civiles UY-ANEP-14548-CS-INDV- UCP 2017 / División Individual 2017-06- 2017-06- 2017-06- 2017-06- 2017-06- 2017-06- 2019-05- 2022-05- Investigación, Evaluación y IBRD / 86750 Early Education Post Consultant Direct 314,292.00 90,660.04 Signed 2017-06-01 01 01 01 01 01 01 07 31 Estadística 2 contratos junio Selection 2017 - mayo 2022 UY-ANEP-14564-CS-INDV- Individual AS ELECTRICOS 2017 / 5 Monitoring and Evaluation Under 2017-06- 2017-06- 2017-06- 2017-12- IBRD / 86750 Post Consultant Limited 18,700.00 0.00 2017-06-01 Asesores Técnicos Eventuales System Implementation 01 01 01 29 Selection - Ingenieros Eléctricos UY-ANEP-14565-CS-INDV- Individual AS SANITARIOS 2017 / 5 Monitoring and Evaluation Under 2017-06- 2017-06- 2017-06- 2017-12- IBRD / 86750 Post Consultant Limited 10,900.00 0.00 2017-06-01 Asesores Técnicos Eventuales System Implementation 01 01 01 29 Selection Ingenieros Sanitarios UY-ANEP-14566-CS-INDV- Individual AS AGRIMENSOR 2017 / 5 Monitoring and Evaluation Under 2017-06- 2017-06- 2017-06- 2017-12- IBRD / 86750 Post Consultant Limited 4,700.00 0.00 2017-06-01 Asesores Técnicos Eventuales System Implementation 01 01 01 29 Selection Ingenieros Agrimensores UY-ANEP-14567-CS-INDV- Individual METRAJISTAS 2017 / 5 Monitoring and Evaluation Under 2017-06- 2017-06- 2017-06- 2017-12- IBRD / 86750 Post Consultant Limited 3,700.00 0.00 2017-06-01 Asesores Técnicos Eventuales System Implementation 01 01 01 29 Selection Metrajistas UY-ANEP-16524-CS-INDV / Individual Monitoring and Evaluation 2019-03- 2017-08- 2019-03- 2017-08- 2019-03- 2017-09- 2018-09- Ayudante para Investigación " IBRD / 86750 Post Consultant Open 8,700.00 0.00 Canceled 2017-06-19 System 26 18 26 25 26 04 04 Diagnostico de Género" Selection UY-ANEP-19234-CS-CDS / Instituto Nacional de Monitoring and Evaluation 2015-11- 2017-06- 2015-12- 2017-06- 2017-05- 2021-05- IBRD / 86750 Post Direct Selection Direct 1,500,000.00 1,500,000.00 Signed 2017-06-27 Evaluación Educativa (INEED) System 19 27 18 27 31 31 2017-2021 UY-ANEP-45069-CS-CDS- DISENO GRAFICO / Diseño 2018-01- 2018-02- 2018-04- IBRD / 86750 Early Education Post Direct Selection Direct 1,000.00 0.00 Canceled 2018-01-22 Gráfico del Catálogo para la 22 15 15 Colección Andariega UY-ANEP-48225-CS-INDV- SOUTO 2018 / CONSULTOR Individual Monitoring and Evaluation 2018-02- 2018-02- 2018-02- 2018-03- 2018-02- 2018-07- 2018-07- EXTERNO PARA INFORMACIÓN IBRD / 86750 Post Consultant Direct 8,000.00 8,000.00 Completed 2018-02-08 System 01 08 23 02 27 31 31 EN SERVICIO Dr. MARTA Selection SOUTO. UY-ANEP-53689-CS-INDV- PABLO GARCIA 2018 / CONSULTOR PABLO GARCIA - Individual Monitoring and Evaluation 2018-03- 2018-03- 2018-04- 2018-05- 2018-06- 2018-06- Encuentro con equipo Curso I IBRD / 86750 Post Consultant Direct 1,000.00 1,000.00 Signed 2018-03-20 System 06 22 20 10 25 26 y Conferencia a Directores de Selection Tiempo Completo. Tema Tránsito escolar e inclusión UY-ANEP-53694-CS-INDV G- UNTOIGLICH 2018 / CONSULTOR GISELA Individual UNTOIGLICH - Conferencia Monitoring and Evaluation 2018-03- 2018-03- 2018-04- 2018-05- 2018-05- 2018-05- IBRD / 86750 Post Consultant Direct 1,000.00 1,000.00 Signed 2018-03-20 para Docentes de Educación System 01 22 20 10 26 26 Selection Inicial. Tema: Los diagnósticos en la 1ra infancia se escriben con lapiz " UY-ANEP-52250-CS-INDV- RICARDO BAQUERO / Honorarios Consultor : Lic. Psicopedagogia esp. en re- Individual Monitoring and Evaluation 2018-03- 2018-03- 2018-03- 2018-04- 2018-04- 2018-04- 2018-04- 2018-04- educación Ricardo Baquero IBRD / 86750 Post Consultant Direct 1,700.00 1,700.00 Signed 2018-03-20 System 12 22 20 02 03 10 13 14 para brindar 2 conferencias el Selection día 13 y 14 de abril del 2018 con maestros y Directores de ETC UY-ANEP-16521-CS-CQS / Individual Coordinador Investigación " Monitoring and Evaluation 2018-06- 2018-05- 2018-12- 2018-06- 2018-12- 2019-06- IBRD / 86750 Post Consultant Open 37,000.00 3,258.11 Signed 2018-03-21 Diagnósito de de Género -40 System 01 27 07 06 07 06 Selection hs. UY-ANEP-55153-CS-INDV / Individual 2 Investigadores para el Monitoring and Evaluation 2018-06- 2018-05- 2018-09- 2018-05- 2018-12- 2018-06- 2018-12- 2019-06- IBRD / 86750 Post Consultant Open 51,000.00 3,233.58 Signed 2018-03-22 proyecto de Investigación " System 01 21 11 28 13 07 13 07 Selection Diagnóstico de Género ". UY-ANEP-55396-CS-INDV- INFORMATICO 2018 / Individual 2018-04- 2018-05- 2018-06- 2018-05- 2018-06- 2018-06- 2019-01- 2022-05- Informático para UCP - IBRD / 86750 Early Education Post Consultant Open 70,000.00 963.51 Signed 2018-03-22 13 11 07 20 07 01 01 31 Contrato mayo 2018 - mayo Selection 2022 UY-ANEP-55399-CS-INDV- MESA AYUDA 2018 / 2 Individual 2018-04- 2018-05- 2018-05- 2018-06- 2018-07- 2022-05- Asistentes Técnicos para IBRD / 86750 Early Education Post Consultant Open 194,000.00 3,650.28 Signed 2018-03-22 12 11 20 01 25 31 soporte Mesa de Ayuda Selection Plataforma Gurí. UY-ANEP-58036-CS-INDV-G FRIGERIO / CONSULTOR Graciela Frigerio. Visitas a Individual Escuelas TC y 2 Conferencias Monitoring and Evaluation 2018-04- 2018-04- 2018-04- 2018-05- 2018-05- 2018-05- 2018-07- 2018-09- 2018-09- IBRD / 86750 Post Consultant Direct 3,000.00 3,000.00 Completed 2018-04-10 para Directores y Maestros System 18 12 20 11 21 31 12 29 29 Selection nuevos de ETC. Tema: "Gestión y Organización educativa de las Escuelas" Page 10 UY-ANEP-59853-CS-INDV- Individual AS ELECTRICOS 2018 / 5 Monitoring and Evaluation Under 2018-04- 2018-04- 2018-04- 2018-12- IBRD / 86750 Post Consultant Limited 20,100.00 0.00 2018-04-18 Asesores Técnicos Eventuales System Implementation 18 18 18 28 Selection - Ingenieros Eléctricos UY-ANEP-59854-CS-INDV- Individual AS CIVILES 2018 / 5 Asesores Monitoring and Evaluation Under 2018-04- 2018-04- 2018-04- 2018-12- IBRD / 86750 Post Consultant Limited 35,000.00 0.00 2018-04-18 Técnicos Eventuales - System Implementation 18 18 18 28 Selection Ingenieros Civiles UY-ANEP-59855-CS-INDV- Individual AS SANITARIOS 2018 / 5 Monitoring and Evaluation Under 2018-04- 2018-04- 2018-04- 2018-12- IBRD / 86750 Post Consultant Limited 11,800.00 0.00 2018-04-18 Asesores Técnicos Eventuales System Implementation 18 18 18 28 Selection - Ingenieros Sanitarios UY-ANEP-59857-CS-INDV- Individual AS AGRIMENSOR 2018 / 5 Monitoring and Evaluation Under 2018-04- 2018-04- 2018-04- 2018-12- IBRD / 86750 Post Consultant Limited 5,000.00 0.00 2018-04-18 Asesores Técnicos Eventuales System Implementation 18 18 18 28 Selection - Ingenieros Agrimensores UY-ANEP-59858-CS-INDV- Individual METRAJISTAS 2018 / 5 Monitoring and Evaluation Under 2018-04- 2018-04- 2018-04- 2018-12- IBRD / 86750 Post Consultant Limited 4,000.00 0.00 2018-04-18 Asesores Técnicos Eventuales System Implementation 18 18 18 28 Selection - Metrajistas UY-ANEP-59860-CS-INDV- Individual AS ACUSTICO 2018 / 1 Asesor Monitoring and Evaluation 2018-03- 2018-08- 2018-03- 2018-08- 2018-04- 2018-09- 2018-07- 2018-10- IBRD / 86750 Post Consultant Limited 3,200.00 3,529.88 Signed 2018-08-01 Técnico Eventual - Ac. System 05 06 09 13 09 03 05 03 Selection Acústico UY-ANEP-63169-CS-INDV- ING-COLON 2018 / ING. CARLOS COLON. Asesoría Individual Monitoring and Evaluation 2018-05- 2018-05- 2018-05- 2018-06- 2018-07- 2018-07- técnica por modificación IBRD / 86750 Post Consultant Direct 1,300.00 1,094.19 Signed 2018-05-17 System 17 19 28 11 10 12 proyecto de estructura en la Selection Escuela N° 8 de Fraile Muerto, Cerro Largo UY-ANEP-63185 CS INDV Individual DISEN GRAF 2018 / Diseñador Monitoring and Evaluation 2018-05- 2018-05- 2018-06- 2018-06- 2018-07- 2018-07- 2018-09- IBRD / 86750 Post Consultant Limited 1,200.00 1,964.51 Signed 2018-05-17 de Catálogo Colección System 17 28 01 29 13 30 28 Selection Andariega UY-ANEP-66203-CS-INDV- ARQ SPOSITO 2018 / Contratación de la Arq. María Individual Monitoring and Evaluation 2018-05- 2018-06- 2018-05- 2018-06- 2018-11- 2018-07- 2019-02- 2018-08- Spósito para el metraje y IBRD / 86750 Post Consultant Direct 1,900.00 1,455.20 Signed 2018-06-11 System 15 13 10 22 29 06 07 06 presupuesto de nueva Selection propuesta arquitectónica de la Escuela N° 41 de Montevideo UY-ANEP-66204-CS-INDV- ING MOLINOLO / Contratación Individual Asesoría Técnica Proyecto Monitoring and Evaluation 2018-06- 2018-06- 2018-06- 2018-06- 2018-07- 2018-09- 2018-08- IBRD / 86750 Post Consultant Direct 3,400.00 2,728.49 Signed 2018-06-11 sanitario de la nueva System 11 13 11 22 06 05 06 Selection propuesta arquitectónica de la Escuela 41 de Montevideo. UY-ANEP-66205-CS-INDV- ING LOPEZ / Contratación Asesoría Técnica Ing. Gonzalo Individual Monitoring and Evaluation 2018-05- 2018-06- 2018-05- 2018-06- 2018-07- 2019-03- 2018-08- López por proyecto eléctrico IBRD / 86750 Post Consultant Direct 6,600.00 5,559.66 Signed 2018-06-11 System 09 13 18 22 06 20 06 de la nueva propuesta Selection arquitectónica de la Escuela 41 de Montevideo UY-ANEP-66206-CS-INDV- AS-ELECT 2018 / Individual 2018-06- 2018-07- 2018-07- 2018-08- 2018-07- 2018-08- 2018-11- 2022-05- Contratación de un Técnico IBRD / 86750 Early Education Post Consultant Open 115,000.00 0.03 Signed 2018-06-11 11 27 30 05 30 17 20 16 Electricista para UCP período Selection agosto 2018 - mayo 2022 UY-ANEP-66208-CS-INDV- AS-SANIT 2018 / Individual 2018-06- 2018-07- 2018-08- 2018-08- 2018-08- 2018-08- 2018-11- 2022-05- Contratación Asesor Técnico IBRD / 86750 Early Education Post Consultant Open 115,000.00 107,237.13 Signed 2018-06-11 11 27 06 05 06 17 19 16 Sanitario para UCP agosto Selection 2018 - mayo 2022 UY-ANEP-68128-CS-INDV- ARQ-D-OBRAS2018 / Individual Directores de Obra para las 2018-08- 2018-09- 2019-08- 2018-09- 2019-12- 2018-09- 2019-12- 2022-05- IBRD / 86750 Early Education Post Consultant Open 250,000.00 47,003.59 Signed 2018-06-26 obras a llevarse a cabo desde 09 01 20 10 30 18 30 31 Selection 2018 al 2022. Se estima 24 Directores de Obra. UY-ANEP-78959-CS-INDV- Individual CHOFER 2018 / Contratación Under 2019-08- 2018-10- 2018-11- 2018-12- 2022-05- IBRD / 86750 Early Education Post Consultant Open 45,000.00 0.00 2018-09-20 de un Chófer para UCP Implementation 13 21 10 18 31 Selection período 2018-2022 UY-ANEP-90275-CS-INDV- M SOUTO 2019 / Servicio de Consultoría para realizar un Individual espacio de formación con Monitoring and Evaluation 2018-12- 2018-12- 2018-12- 2019-02- 2019-03- 2019-03- 2019-07- 2019-10- 2019-10- IBRD / 86750 Post Consultant Direct 8,100.00 8,000.00 Completed 2018-12-10 integrantes del equipo, System 10 10 10 28 20 10 29 30 30 Selection Formadores y Coordinadores del Componente Formación en Servicio del PAEPU UY-ANEP-98323-CS-INDV- DORA RIESTRA 2019 / Contratación directa Dra. Dora Riestra, Experta de Formación Individual Monitoring and Evaluation 2019-02- 2019-02- 2019-02- 2019-03- 2019-03- 2019-03- 2019-04- 2019-04- 2019-04- Permanente en Ciencias del IBRD / 86750 Post Consultant Direct 3,800.00 3,000.00 Completed 2019-02-04 System 04 04 04 20 20 27 04 06 06 Lenguaje, que participará en Selection jornadas de trabajo con Equipo de Lenguaje y Formadores de PAEPU. UY-ANEP-98331-CS-INDV- PATRIC SARLE 2019 / Contratación Directa Lic. Patricia Sarlé, Profesora en Educación Preescolar, que Individual Monitoring and Evaluation 2019-02- 2019-02- 2019-02- 2019-05- 2019-03- 2019-05- 2019-08- 2019-08- 2019-08- participará en la IBRD / 86750 Post Consultant Direct 2,700.00 2,000.00 Completed 2019-02-03 System 05 04 06 07 20 14 16 17 17 inplementación de un espacio Selection de de formación para docentes de Inicial y Primaria, brindando dos conferencias a realizarse en agosto 2019 UY-ANEP-98337-CS-INDV-G UNTOIGLICH 2019 / Contratación Directa Psic. Gisela Untoiglich, asesoramiento y participación Individual Monitoring and Evaluation 2019-02- 2019-02- 2018-12- 2019-03- 2019-03- 2019-03- 2019-05- 2019-05- 2019-05- en el área de la Educación IBRD / 86750 Post Consultant Direct 2,700.00 2,000.00 Completed 2019-02-04 System 05 06 13 07 20 27 24 25 25 Inicial con énfasis en el Selection vínculo Familia-Escuela , reuniones con el Equipo de trabajo y autoridades, encuentros con Maestros . UY-ANEP-98342-CS-INDV- GRAC FRIGERIO 2019 / Contratación directa Dra. Graciela Frigerio que participará en encuentros de Individual Monitoring and Evaluation 2019-02- 2019-02- 2019-02- 2019-02- 2019-02- 2019-04- 2019-12- 2019-12- marzo a diciembre con con IBRD / 86750 Post Consultant Direct 21,400.00 14,994.00 Completed 2019-02-04 System 05 04 05 14 25 03 03 03 Equipo de PAEPU, Inspectores, Selection Directores y Maestros de ETC con el objetivo de profundizar sobre aspectos relevantes en la tarea de los docentes. UY-ANEP-98345-CS-INDV- ANA CERUTTI 2019 / Contratación directa Lic Ana Cerutti Experta en Psicomotricidad, que Individual participará en encuentros Monitoring and Evaluation 2019-02- 2019-02- 2019-02- 2019-02- 2019-02- 2019-02- 2019-02- 2019-10- 2019-10- IBRD / 86750 Post Consultant Direct 12,500.00 8,898.31 Completed 2019-02-04 presenciales y trabajos a System 05 04 05 07 20 21 27 31 19 Selection distancia por 7 meses entre febrero y octubre 2019 dirigido al Componente Educación Inicial, Directores, Maestros de ETC. Page 11 UY-ANEP-98347-CS-INDV- PABLO GARCIA 2019 / Contratación directa Mag Pablo García, experto en la temática de inclusión social y Individual Monitoring and Evaluation 2019-02- 2019-02- 2019-02- 2019-03- 2019-03- 2019-04- 2019-09- 2019-09- 2019-09- tránsito educativo, IBRD / 86750 Post Consultant Direct 3,000.00 2,000.00 Completed 2019-02-04 System 04 04 04 04 20 01 03 05 05 participando en encuentros Selection con el equipo de gestión del PAEPU, Inspectores y Directores de ETC a realizarse en Setiembre 2019. UY-ANEP-105801-CS-INDV- ARQ DUARTE 2019 / Contratación Directa del Arq. Individual Fernando Duarte para Monitoring and Evaluation 2019-02- 2019-03- 2019-03- 2019-03- 2019-06- 2019-04- 2019-06- 2019-05- IBRD / 86750 Post Consultant Direct 1,000.00 489.23 Signed 2019-03-13 Dirección de Obra en la System 20 15 13 24 04 07 05 17 Selection Escuela N° 24 Localidad de Vichadero, Departamento de Rivera UY-ANEP-105804-CS-INDV- MARIANA GOL 2019 / Contratación de la Consultora Individual Metrajista Arq. Mariana Gol Monitoring and Evaluation 2019-02- 2019-03- 2019-06- 2019-04- 2019-06- 2019-04- 2019-07- 2019-05- IBRD / 86750 Post Consultant Direct 6,260.00 321.20 Signed 2019-03-15 para al actualización de System 20 15 04 07 28 16 19 16 Selection presupuesto de obra del Instituto de Formación en Servicio. UY-ANEP-105793-CS-INDV- Individual AS CIVILES 2019 / 5 Asesores Monitoring and Evaluation 2019-03- 2019-04- 2019-07- 2019-04- 2019-08- 2019-04- 2019-09- 2019-12- IBRD / 86750 Post Consultant Open 35,000.00 30,654.65 Signed 2019-03-22 Técnicos Eventuales - System 30 15 03 22 20 22 09 31 Selection Ingenieros Civiles UY-ANEP-105796-CS-INDV- AS ELECTRICO 2019 / 5 Individual Monitoring and Evaluation Under 2019-04- 2019-04- 2019-04- 2019-12- Asesores Técnicos Eventuales IBRD / 86750 Post Consultant Open 19,700.00 0.00 2019-03-22 System Implementation 15 22 22 31 - Ingenieros Eléctricos/ Selection Técnicos Electricistas UY-ANEP-105798-CS-INDV- AS SANITARIO 2019 / 5 Individual Asesores Técnicos Eventuales Monitoring and Evaluation Under 2019-04- 2019-04- 2019-04- 2019-12- IBRD / 86750 Post Consultant Open 11,500.00 0.00 2019-03-22 - Ingenieros/Arquitecto System Implementation 15 22 22 31 Selection /Técnico en Instalaciones Sanitarias UY-ANEP-105799-CS-INDV- Individual AS AGRIMENSO 2019 / 5 Monitoring and Evaluation 2019-03- 2019-04- 2019-06- 2019-04- 2019-07- 2019-04- 2019-08- 2019-12- IBRD / 86750 Post Consultant Open 5,000.00 1,655.71 Signed 2019-03-22 Asesores Técnicos Eventuales System 31 15 12 22 30 22 01 31 Selection - Ingenieros Agrimensores UY-ANEP-105800-CS-INDV- AS METRAJ 2019 / 5 Asesores Individual Monitoring and Evaluation Under 2019-04- 2019-04- 2019-04- 2019-12- Técnicos Eventuales - IBRD / 86750 Post Consultant Open 3,800.00 0.00 2019-03-22 System Implementation 15 22 22 31 Ingeniero/Arquitecto Selection Metrajistas UY-ANEP-109134-CS-INDV- ASIST GENERO 2019 / ASISTENTE ADMINISTRATIVO "Ayudante A" 20 horas, que Individual Monitoring and Evaluation 2019-04- 2019-06- 2019-06- 2019-07- 2019-12- 2019-07- 2019-07- 2020-07- apoyará en la estrategia de IBRD / 86750 Post Consultant Open 8,900.00 650.69 Signed 2019-04-09 System 11 11 25 09 10 27 17 26 investigación para la Selection construcción de un Plan Nacional de Igualdad de Género de ANEP. UY-ANEP-118445-CS-INDV- ALONSO-184-2019 / Contratación Arq. Alonso para Individual ajuste de metraje y Monitoring and Evaluation 2019-06- 2019-06- 2019-06- 2019-06- 2019-08- 2019-06- 2019-09- 2019-06- IBRD / 86750 Post Consultant Direct 175.00 130.25 Signed 2019-06-07 presupuestación para la Obra System 04 07 04 13 23 21 06 28 Selection en Escuela N° 184, Montevideo por cambio en el proyecto ejecutivo. UY-ANEP-121831-CS-INDV / Contratación Agrimensor Andrés Pisón para realizar la Individual asesoría en Agrimensura Monitoring and Evaluation 2019-06- 2019-07- 2019-07- 2019-07- 2019-07- 2019-08- 2019-08- 2019-09- IBRD / 86750 Post Consultant Direct 1,000.00 920.86 Signed 2019-07-08 (medición, determinación y System 04 08 01 15 30 19 01 18 Selection graficación ) de los padrones donde se ubicará la Escuela Nº 224 de Montevideo, UY-ANEP-59861-CS-INDV- Individual AS FORESTAL 2018 / 1 Asesor Monitoring and Evaluation 2018-06- 2018-06- 2018-07- 2018-08- IBRD / 86750 Post Consultant Limited 3,200.00 0.00 Canceled 2018-06-01 Técnico Eventual - Ac. System 04 11 05 06 Selection Forestal UY-ANEP-59859-CS-INDV- Individual AS TERMICO 2018 / 1 Asesor Monitoring and Evaluation 2018-08- 2018-08- 2018-09- 2018-10- IBRD / 86750 Post Consultant Limited 3,200.00 0.00 Canceled 2018-08-01 Técnico Eventual - Ac. System 06 13 03 03 Selection Térmico UY-ANEP-156786-CS-INDV- ELECT ESC 9 MDEO / Individual Monitoring and Evaluation 2020-03- 2020-03- 2020-04- 2020-05- Contratación Asesor para IBRD / 86750 Post Consultant Open 3,700.00 0.00 Canceled 2020-02-18 System 02 05 03 04 Proyecto de eléctrica para la Selection Escuela 9 La Teja, Montevideo UY-ANEP-156789-CS-INDV- AGRIM ESC 9 MDEO / Individual Monitoring and Evaluation 2020-03- 2020-03- 2020-04- 2020-05- Contratación Asesor para IBRD / 86750 Post Consultant Open 900.00 0.00 Canceled 2020-02-18 System 02 05 03 04 Proyecto Agrimensura para la Selection Escuela 9 La Teja, Montevideo UY-ANEP-157316-CS-INDV- CIVIL ESC320 2020 / Asesor Individual para proyecto de estructura Monitoring and Evaluation 2020-03- 2020-03- 2020-04- 2020-05- IBRD / 86750 Post Consultant Open 6,500.00 0.00 Canceled 2020-03-02 Escuela N° 320 Barrio System 15 18 16 17 Selection Casavalle, Departamento de Montevideo UY-ANEP-157317-CS-INDV- ELECT-ESC320-2020 / Asesor Individual para proyecto de eléctrica Monitoring and Evaluation 2020-03- 2020-03- 2020-04- 2020-05- IBRD / 86750 Post Consultant Open 3,700.00 0.00 Canceled 2020-03-02 Escuela N° 320 Barrio System 15 18 16 17 Selection Casavalle, Departamento de Montevideo UY-ANEP-157318-CS-INDV- SANIT ESC320-2020 / Asesor Individual para proyecto de sanitaria Monitoring and Evaluation 2020-03- 2020-03- 2020-04- 2020-05- IBRD / 86750 Post Consultant Open 2,200.00 0.00 Canceled 2020-03-02 Escuela N° 320 Barrio System 15 18 16 17 Selection Casavalle, Departamento de Montevideo UY-ANEP-157319-CS-INDV- AGRIM ESC320-2020 / Asesor Individual para proyecto de agrimensura Monitoring and Evaluation 2020-03- 2020-03- 2020-04- 2020-05- IBRD / 86750 Post Consultant Open 900.00 0.00 Canceled 2020-03-02 Escuela N° 320 Barrio System 15 18 16 17 Selection Casavalle, Departamento de Montevideo UY-ANEP-157321-CS-INDV- METRA ESC320-2020 / Individual Asesor para proyecto de Monitoring and Evaluation 2020-03- 2020-03- 2020-04- 2020-05- IBRD / 86750 Post Consultant Open 700.00 0.00 Canceled 2020-03-02 metraje Escuela N° 320 Barrio System 15 18 16 17 Selection Casavalle, Departamento de Montevideo UY-ANEP-157794-CS-INDV- DIR OBRA 154-2020 / Director de Obra para asesoramiento, ejecución de recaudos y dirección de las Individual obras del plan de 2020-02- 2020-03- 2020-02- 2020-03- 2020-03- 2020-04- 2020-03- 2021-04- IBRD / 86750 Early Education Post Consultant Open 12,000.00 10,517.88 Signed 2020-02-05 mantenimiento de diferentes 03 09 07 25 12 01 12 01 Selection escuelas del Dep Rivera, de obras menores en la Esc 88 del mismo departamento y la dirección de obras de la Escuela 124 Tacuarembó Page 12 UY-ANEP-157795-CS-DIR OBRA 65 MDEO-2020 / Individual 2020-03- 2020-03- 2020-03- 2020-03- 2020-03- 2020-04- 2020-03- 2020-12- Director obra para la Escuela IBRD / 86750 Early Education Post Consultant Open 11,000.00 9,407.49 Signed 2020-02-10 02 14 11 30 30 06 30 07 65 de Ciudad Vieja del Selection Departamento de Montevideo UY-ANEP-166125-CS-INDV- ARQ M. GOL 2020 / Actualización del presupuesto Individual realizado para las obras en la Monitoring and Evaluation 2020-03- 2020-03- 2020-04- 2020-04- 2020-05- 2020-05- 2020-05- 2020-06- 2020-08- IBRD / 86750 Post Consultant Direct 200.00 192.58 Completed 2020-03-24 Escuela Nº 65 de Montevideo , System 24 24 24 22 12 12 12 01 11 Selection debido a cambios que se debieron realizar en el proyecto ejecutivo UY-ANEP-181959-CS-INDV- CIVIL ESC163 2020 / Asesor Individual Monitoring and Evaluation Pending 2020-07- 2020-07- 2020-08- 2020-09- para proyecto de estructura IBRD / 86750 Post Consultant Open 6,500.00 0.00 2020-06-25 System Implementation 08 11 09 08 Escuela N° 163, Departamento Selection de Montevideo UY-ANEP-181961-CS-INDV- ELEC 163 MDEO2020 / Asesor Individual Monitoring and Evaluation Pending 2020-07- 2020-07- 2020-08- 2020-09- para proyecto de eléctrica IBRD / 86750 Post Consultant Open 3,700.00 0.00 2020-06-25 System Implementation 08 11 09 08 Escuela N° 163, Departamento Selection de Montevideo UY-ANEP-181962-CS-INDV- SANIT ESC163 2020 / Asesor Individual Monitoring and Evaluation Pending 2020-07- 2020-07- 2020-08- 2020-09- para proyecto de sanitaria IBRD / 86750 Post Consultant Open 2,200.00 0.00 2020-06-25 System Implementation 08 11 09 08 Escuela N° 163, Departamento Selection de Montevideo UY-ANEP-181964-CS-INDV- AGRIM ESC163 2020 / Asesor Individual Monitoring and Evaluation Pending 2020-07- 2020-07- 2020-08- 2020-09- para proyecto de agrimensura IBRD / 86750 Post Consultant Open 900.00 0.00 2020-06-25 System Implementation 08 11 09 08 Escuela N° 163, Departamento Selection de Montevideo UY-ANEP-181968-CS-INDV- Individual METRAJIS 163 2020 / Asesor Monitoring and Evaluation Pending 2020-07- 2020-07- 2020-08- 2020-09- IBRD / 86750 Post Consultant Open 700.00 0.00 2020-06-25 para metraje Escuela N° 163, System Implementation 08 11 09 08 Selection Departamento de Montevideo UY-ANEP-182125-CS-INDV- BURGUEÑO 2020 / Ajuste del proyecto de instalación Individual Monitoring and Evaluation 2020-06- 2020-06- 2020-06- 2020-07- 2020-09- 2020-08- 2020-09- 2020-09- 2020-10- eléctrica realizado en el 2014 IBRD / 86750 Post Consultant Direct 2,200.00 1,650.69 Completed 2020-06-26 System 25 26 17 25 01 14 07 03 09 para el reciclaje del Liceo N° Selection 34 a transformarse en Formación en Servicio UY-ANEP-182162-CS-INDV- SANIT E6 TBO 2020 / Asesor Individual Monitoring and Evaluation 2020-06- 2020-07- 2020-10- 2020-07- 2020-10- 2020-08- 2020-12- 2020-09- para proyecto de sanitaria IBRD / 86750 Post Consultant Open 2,200.00 2,157.02 Signed 2020-06-26 System 26 09 19 12 19 10 09 09 Escuela N° 6, Departamento Selection de Tacuarembó UY-ANEP-182163-CS-INDV METRAJ 6 TBO 2020 / Asesor Individual Monitoring and Evaluation 2020-10- 2020-08- 2020-10- 2020-09- 2020-11- 2020-10- 2021-05- 2021-04- para proyecto de metraje IBRD / 86750 Post Consultant Open 700.00 1,970.50 Signed 2020-06-29 System 26 17 26 07 09 12 04 10 Escuela N° 6, Departamento Selection de Tacuarembó UY-ANEP-156790-CS-INDV- METRAJ ESC 9 MDEO / Individual Monitoring and Evaluation Under 2021-02- 2020-07- 2021-01- 2020-07- 2021-03- 2020-08- 2020-09- Contratación Asesor para IBRD / 86750 Post Consultant Open 700.00 0.00 2020-06-29 System Implementation 01 12 22 15 03 13 12 Proyecto de metraje para la Selection Escuela 9 La Teja, Montevideo UY-ANEP-156783-CS-INDV- CIVIL ESC 9 MDEO / Individual Monitoring and Evaluation 2020-07- 2020-07- 2020-07- 2020-07- 2020-07- 2020-08- 2020-10- 2020-09- Contratación Asesor para IBRD / 86750 Post Consultant Open 6,500.00 2,764.25 Signed 2020-06-29 System 01 12 20 15 29 13 15 12 Proyecto de estructura para la Selection Escuela 9 La Teja, Montevideo UY-ANEP-157322-CS-INDV- CIVIL ESC161-2020 / Asesor Individual Monitoring and Evaluation Under 2021-05- 2020-07- 2020-07- 2020-08- 2020-09- para proyecto de estructura IBRD / 86750 Post Consultant Open 6,500.00 0.00 2020-06-29 System Implementation 10 12 15 13 13 Escuela N° 161 Barrio Sayago, Selection Departamento de Montevideo UY-ANEP-157323-CS-INDV- ELECT ESC161-2020 / Asesor Individual Monitoring and Evaluation Under 2021-05- 2020-07- 2020-07- 2020-08- 2020-09- para proyecto de eléctrica IBRD / 86750 Post Consultant Open 3,700.00 0.00 2020-06-29 System Implementation 10 12 15 13 12 Escuela N° 161 Barrio Sayago, Selection Departamento de Montevideo UY-ANEP-157334-CS-INDV- SANIT ESC161 2020 / Asesor Individual Monitoring and Evaluation Under 2021-05- 2020-07- 2020-07- 2020-08- 2020-09- para proyecto de sanitaria IBRD / 86750 Post Consultant Open 2,200.00 0.00 2020-06-29 System Implementation 10 12 15 13 13 Escuela N° 161 Barrio Sayago, Selection Departamento de Montevideo UY-ANEP-157335-CS-INDV- AGRIM ESC161 2020 / Asesor Individual Monitoring and Evaluation Under 2021-05- 2020-07- 2020-07- 2020-08- 2020-09- para proyecto de agrimensura IBRD / 86750 Post Consultant Open 900.00 0.00 2020-06-29 System Implementation 07 12 15 13 13 Escuela N° 161 Barrio Sayago, Selection Departamento de Montevideo UY-ANEP-157338-CS-INDV- METRA ESC161 2020 / Asesor Individual Monitoring and Evaluation Under 2021-05- 2020-07- 2020-07- 2020-08- 2020-09- para proyecto de metraje IBRD / 86750 Post Consultant Open 700.00 0.00 2020-06-29 System Implementation 10 12 15 13 12 Escuela N° 161 Barrio Sayago, Selection Departamento de Montevideo UY-ANEP-182435-CS-INDV- CIVIL 114RIV 2020 / Asesor Individual Monitoring and Evaluation Pending 2020-07- 2020-07- 2020-08- 2020-09- para proyecto de estructura IBRD / 86750 Post Consultant Open 6,500.00 0.00 2020-06-29 System Implementation 12 15 13 12 Escuela N° 114 Departamento Selection de Rivera UY-ANEP-182436-CS-INDV- ELECT 114RIV 2020 / Asesor Individual Monitoring and Evaluation Pending 2020-07- 2020-07- 2020-08- 2020-09- para proyecto de eléctrica IBRD / 86750 Post Consultant Open 3,700.00 0.00 2020-06-29 System Implementation 12 15 13 12 Escuela N° 114 Departamento Selection de Rivera UY-ANEP-182438-CS-INDV- METRA 114RIV 2020 / Asesor Individual Monitoring and Evaluation Pending 2020-07- 2020-07- 2020-08- 2020-09- para proyecto de metraje IBRD / 86750 Post Consultant Open 700.00 0.00 2020-06-29 System Implementation 12 15 13 12 Escuela N° 114 Departamento Selection de Rivera UY-ANEP-182439-CS-INDV- SANIT 114RIV 2020 / Asesor Individual Monitoring and Evaluation Pending 2020-07- 2020-07- 2020-08- 2020-09- para proyecto de sanitaria IBRD / 86750 Post Consultant Open 2,200.00 0.00 2020-06-29 System Implementation 12 15 13 12 Escuela N° 114 Departamento Selection de Rivera UY-ANEP-184946-CS-INDV- INST BOMBERO2020 / Individual Monitoring and Evaluation Pending 2020-08- 2020-08- 2020-09- 2020-10- Escuelas 6 de Tacuarembó - IBRD / 86750 Post Consultant Open 3,400.00 0.00 2020-07-27 System Implementation 09 12 10 10 Asesor de instalaciones de Selection protección contra incendios UY-ANEP-185628-CS-INDV- INST BOMBEROS2020 / Individual Escuelas 224 Y 9 de Monitoring and Evaluation Under 2020-11- 2020-08- 2020-11- 2020-08- 2020-11- 2020-09- 2020-10- IBRD / 86750 Post Consultant Open 6,700.00 0.00 2020-07-27 Montevideo - Asesor de System Implementation 03 09 13 12 23 10 10 Selection instalaciones de protección contra incendios UY-ANEP-185632-CS-INDV- INST BOMBEROS2020 / Individual Escuela 301 Marindia Monitoring and Evaluation Pending 2020-08- 2020-08- 2020-09- 2020-10- IBRD / 86750 Post Consultant Open 3,400.00 0.00 2020-07-27 Canelones - Asesor de System Implementation 09 12 10 10 Selection instalaciones de protección contra incendios UY-ANEP-185633-CS-INDV- INST BOMBEROS2020 / Individual Monitoring and Evaluation Pending 2020-08- 2020-08- 2020-09- 2020-10- Escuela 114 de Rivera - IBRD / 86750 Post Consultant Open 3,400.00 0.00 2020-07-27 System Implementation 09 12 10 10 Asesor de instalaciones de Selection protección contra incendios Page 13 UY-ANEP-185634-CS-INDV- INST BOMBEROS2020 / Individual Monitoring and Evaluation Under 2021-05- 2020-08- 2020-08- 2020-09- 2020-10- Escuela 161 Montevideo - IBRD / 86750 Post Consultant Open 3,400.00 0.00 2020-07-27 System Implementation 10 09 12 10 10 Asesor de instalaciones de Selection protección contra incendios UY-ANEP-185649-CS-INDV- SANITARIO 2020 / Escuelas 131, 151 Mdeo y 9 Colonia - Individual Monitoring and Evaluation 2020-08- 2020-08- 2020-09- 2020-10- Contratación de un Consultor IBRD / 86750 Post Consultant Open 6,600.00 0.00 Canceled 2020-07-27 System 09 12 10 10 para Proyecto de sanitaria en Selection las obras en las Escuelas de referencia UY-ANEP-190084-CS-INDV- PSICOMETRIA 2020 / Individual Monitoring and Evaluation Under 2020-10- 2020-09- 2020-10- 2020-09- 2020-10- 2021-03- Consultor en Piscometría con IBRD / 86750 Post Consultant Open 12,000.00 0.00 2020-08-24 System Implementation 13 14 19 16 02 31 especialización en medición Selection de aprendizajes UY-ANEP-193305-CS-CDS- LIC NUTRICION / Licenciada Isabel Aldabe - Consultor especializado en Nutrición Individual para contribuir a mejorar y Monitoring and Evaluation 2020-09- 2020-09- 2020-09- 2020-09- 2020-09- 2020-09- 2021-09- IBRD / 86750 Post Consultant Direct 29,000.00 2,455.79 Signed 2020-09-10 fortalecer el Programa de System 09 10 10 26 30 30 30 Selection Alimentación Escolar (PAE) en los aspectos relacionados con la eficiencia, eficacia y profesionalización del mismo. UY-ANEP-197261-CS-INDV RAPETTI 2020 / Ajuste proyecto de Calculo y estructura realizado en el año 2014 por el Ing. Daniel Individual Monitoring and Evaluation 2020-09- 2020-09- 2020-09- 2020-11- 2020-11- 2020-11- 2020-11- 2020-12- 2020-12- Rapetti para el reciclaje del IBRD / 86750 Post Consultant Direct 1,500.00 1,353.03 Completed 2020-09-30 System 30 30 30 30 03 30 17 31 11 Liceo N° 34 a transformarse Selection en el Instituto de Formación en Servicio, por cambios solicitados por la Unidad de Protección de Patrimonio. UY-ANEP-218444-CS-INDV CIVIL 5 FLORIDA / Asesor para Individual Monitoring and Evaluation Pending 2021-02- 2021-03- 2021-04- 2021-05- Proyecto de estructura para la IBRD / 86750 Post Consultant Open 6,500.00 0.00 2021-02-15 System Implementation 28 03 01 01 Escuela 5 Florida, Selection Departamento FLORIDA UY-ANEP-218446-CS-INDV AGRIM 5 FLORIDA / Asesor Individual Monitoring and Evaluation Pending 2021-02- 2021-03- 2021-04- 2021-05- para proyecto de agrimensura IBRD / 86750 Post Consultant Open 900.00 0.00 2021-02-15 System Implementation 28 03 01 01 Escuela N° 5 Florida, Selection Departamento de FLORIDA UY-ANEP-218447-CS-INDV- METRAJE 5 FLORIDA / Asesor Individual Monitoring and Evaluation Pending 2021-02- 2021-03- 2021-04- 2021-05- para metraje Escuela N° 5 IBRD / 86750 Post Consultant Open 700.00 0.00 2021-02-15 System Implementation 28 03 01 01 Florida, Departamento de Selection FLORIDA UY-ANEP-218448-CS-INDV CIVIL 131 MDEO / Asesor para Individual Monitoring and Evaluation Under 2021-04- 2021-05- 2021-05- 2021-06- 2021-07- Proyecto de estructura para la IBRD / 86750 Post Consultant Open 6,500.00 0.00 2021-04-30 System Implementation 21 13 16 14 14 Escuela 131 Departamento de Selection Montevideo UY-ANEP-218449-CS-INDV Individual METRAJE 131 MDEO / Asesor Monitoring and Evaluation Under 2021-05- 2021-05- 2021-05- 2021-06- 2021-07- IBRD / 86750 Post Consultant Open 700.00 0.00 2021-04-30 para metraje Escuela N° 131 System Implementation 07 13 16 14 14 Selection Departamento de Montevideo UY-ANEP-218451-CS-INDV CIVIL 4 MDEO / Asesor para Individual Monitoring and Evaluation 2021-06- 2021-05- 2021-05- 2021-06- 2021-07- Proyecto de estructura para la IBRD / 86750 Post Consultant Open 6,500.00 0.00 Under Review 2021-04-30 System 18 13 16 14 14 Escuela 4 Departamento de Selection Montevideo UY-ANEP-218452-CS-INDV Individual METRAJE 4 MDEO / Asesor Monitoring and Evaluation Pending 2021-05- 2021-05- 2021-06- 2021-07- IBRD / 86750 Post Consultant Open 700.00 0.00 2021-04-30 para metraje Escuela N° 4 System Implementation 13 16 14 14 Selection Departamento de Montevideo UY-ANEP-218453-CS-INDV BOMBERO 2 R.NEGRO / Asesor Individual de instalaciones de protección Monitoring and Evaluation Pending 2021-08- 2021-08- 2021-09- 2021-10- IBRD / 86750 Post Consultant Open 3,400.00 0.00 2021-08-02 contra incendios Escuela N° 2 System Implementation 15 18 16 16 Selection Fray Bentos, Departamento de Río Negro. UY-ANEP-222791-CS-CDS- COORD GRAL 2021-22 / Contratación de la Monitoring and Evaluation 2020-12- 2020-12- 2020-12- 2021-01- 2021-01- 2022-05- Coordinadora General para el IBRD / 86750 Post Direct Selection Direct 65,000.00 32,823.31 Signed 2020-12-15 System 15 15 15 25 25 31 Proyecto, designada por las Autoridades del CODICEN previsto hasta mayo 2022 UY-ANEP-228349-CS-CDS- COORD FS 2021-2022 / Individual Monitoring and Evaluation Under 2021-04- 2021-04- 2021-05- 2021-05- 2022-05- Coordinador del Componente IBRD / 86750 Post Consultant Open 43,000.00 0.00 2021-04-12 System Implementation 15 23 03 03 31 Formación en Servicio desde Selection abril 2021 a mayo 2022 UY-ANEP-156787-CS-INDV- SANIT ESC 9 MDEO / Individual Monitoring and Evaluation 2020-07- 2020-07- 2020-08- 2020-09- Contratación Asesor para IBRD / 86750 Post Consultant Open 2,200.00 0.00 Canceled 2020-06-29 System 12 15 13 12 Proyecto de sanitaria para la Selection Escuela 9 La Teja, Montevideo UY-ANEP-234484-CS-INDV CIVIL 9 DURAZNO / Cateo, Individual Monitoring and Evaluation Under 2021-05- 2021-06- 2021-06- 2021-07- 2021-08- análisis y diagnóstico IBRD / 86750 Post Consultant Open 3,500.00 0.00 2021-06-01 System Implementation 27 14 17 16 16 estructural de los perfiles del Selection techo del local escolar. UY-ANEP-234523-CS-INDV LUIS BELORA 2021 / Especialista en discapacidad intelectual- 9 jornadas con Individual Formadores del Componente Monitoring and Evaluation Under 2021-05- 2021-05- 2021-05- 2021-05- 2021-12- IBRD / 86750 Post Consultant Direct 3,300.00 0.00 2021-05-17 3 de PAEPU y maestros , System Implementation 27 17 24 24 31 Selection directores e inspectores de Educación Primaria de ETC, con énfasis en el rezago y la transición . UY-ANEP-234486-CS-INDV A, CERUTTI 2021 / Contratación directa experta en psicomotricidad que Individual Monitoring and Evaluation Under 2021-05- 2021-05- 2021-05- 2021-05- 2021-12- participara en 10 jornadas IBRD / 86750 Post Consultant Direct 8,600.00 0.00 2021-05-17 System Implementation 27 17 24 24 31 entre los meses de mayo a Selection diciembre 2021 dirigido a Inspectores, Directores y maestros de ETC. Page 14 PROCUREMENT PLAN Project information: Mozambique, Smallholder Irrigated Agriculture and Market Access Project, Grant Number D3510-MZ. Project Implementation agency: Ministry of Agriculture and Food Security-AIMU-Agriculture Investment Management Unit. Date of the Procurement Plan: April 5, 2019. Period covered by this Procurement Plan:18 (Eighteen months) Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in The Mozambique Procurement Regulations, Decree 5/2016 of March 8, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables. Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is applicable for those contracts identified in the Procurement Plan tables; Works: is applicable for those contracts identified in the Procurement Plan tables. Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Not Applicable . PROCUREMENT Mozambique : Smallholder Irrigated Agriculture and Market Access Project- IRRIGA 1 PLAN General Information Country: Mozambique Bank’s Approval Date of the Original Procurement Plan: 2019-04-25 2021-06-01 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P164431 GPN Date: Project Name: Smallholder Irrigated Agriculture and Market Access Project- IRRIGA 1 Loan / Credit No: IDA / D3510 NATIONAL INSTITUTE OF IRRIGATION Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned MZ-INIR-174293-CW-RFB / Component 2-Smallholder Five Irrigation System Single Stage - One 2,281,957.9 2021-07- IDA / D3510 Irrigation Development and Post Request for Bids Open - National 2,690,000.00 Signed 2020-09-30 2020-08-26 2020-10-05 2020-09-02 2020-11-16 2020-09-29 2020-12-16 2020-11-16 2021-01-20 2020-12-31 Construction in Manica Envelope 8 19 Management Province MZ-INIR-174295-CW-RFB / Component 2-Smallholder Request for Single Stage - One 2021-05- Rehabilitating IRRIGA Project IDA / D3510 Irrigation Development and Post Limited 170,000.00 179,150.65 Signed 2020-10-05 2020-09-16 2020-11-30 2020-12-31 Quotations Envelope 29 Office in Zambezia Province Management MZ-INIR-174296-CW-RFB / Component 2-Smallholder Request for Single Stage - One 2021-05- Rehabilitating IRRIGA Project IDA / D3510 Irrigation Development and Post Limited 150,000.00 182,597.32 Signed 2020-10-05 2020-09-08 2020-11-30 2020-12-02 Quotations Envelope 29 Office in Manica Province Management MZ-INIR-180509-CW-RFB / Component 2-Smallholder Pending Acaboco Irrigation System 2021-08- IDA / D3510 Irrigation Development and Post Request for Bids 2,500,000.00 0.00 Implementat 2020-10-20 2020-10-25 2020-12-06 2021-01-05 2021-02-09 Construction, 314 Ha, Buzi 08 Management ion District, Sofala Province MZ-INIR-197130-CW-RFB / Component 2-Smallholder M'ziva Irrigation Ssytem Single Stage - One 1,252,617.8 2021-11- IDA / D3510 Irrigation Development and Post Request for Bids Open - National 1,300,000.00 Signed 2021-01-18 2021-01-06 2021-01-23 2021-04-29 2021-03-06 2021-02-12 2021-04-05 2021-03-05 2021-05-10 2021-04-26 Construction, 165, Nicoadala Envelope 3 06 Management District, Zambézia MZ-INIR-207153-CW-RFQ / Rehabilitation Works of Component 1-Institutional Request for Single Stage - One 2021-08- IDA / D3510 Post Limited 150,000.00 177,045.29 Signed 2020-12-23 2021-01-06 2021-02-17 2021-03-11 IRRIGA Project Offices in Beira, Capacity Building Quotations Envelope 16 Sofala Provínce MZ-INIR-180508-CW-RFB / M´ziva Irrigation System Component 2-Smallholder Single Stage - One 2021-10- Construction, 165 Ha, IDA / D3510 Irrigation Development and Post Request for Bids Open - National 1,300,000.00 0.00 Canceled 2020-12-17 2020-12-22 2021-02-02 2021-03-04 2021-04-08 Envelope 05 Nicoadala District, Zambezia Management Province MZ-INIR-227956-CW-RFQ / Under Rehabilitation Works of IRRIGA Component 1-Institutional Request for Single Stage - One 2021-12- IDA / D3510 Post Limited 100,000.00 0.00 Implementat 2021-04-28 2021-04-22 2021-06-23 Project Offices in Nampula Capacity Building Quotations Envelope 20 ion province. National MZ-INIR-207152-CW-RFB / Component 2-Smallholder Procurement Pending ACABOCO IRRIGATION Single Stage - One 2022-05- IDA / D3510 Irrigation Development and Post Request for Bids Open - National Document - 1 2,500,000.00 0.00 Implementat 2021-01-12 2021-01-17 2021-02-28 2021-03-30 2021-05-04 SYSTEM CONSTRUCTION, 314 Envelope 04 Management Envelope process ion Ha, BÚZI DISTRICT, SOFALA (Non Bank-SPD) PROVINCE National MZ-INIR-180497-CW-RFB / Component 2-Smallholder Procurement Pending Chiverano Irrigation System Single Stage - One 2022-05- IDA / D3510 Irrigation Development and Post Request for Bids Open - National Document - 1 1,000,000.00 0.00 Implementat 2021-07-13 2021-07-18 2021-08-29 2021-09-28 2021-11-02 Construction, 110 Ha, Mopeia Envelope 01 Management Envelope process ion District, Zambezia Province (Non Bank-SPD) National MZ-INIR-231415-CW-RFB / Component 2-Smallholder Procurement Pending Single Stage - One 2022-05- Reahabilitation of Tsetsera IDA / D3510 Irrigation Development and Post Request for Bids Open - National Document - 1 1,100,000.00 0.00 Implementat 2021-07-15 2021-07-20 2021-08-31 2021-09-30 2021-11-04 Envelope 03 Irrigation Schemes Management Envelope process ion (Non Bank-SPD) GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MZ-INIR-109235-GO-RFQ / Equipamento informático (16 Component 4- Project Under Request for Single Stage - One Computadores tipo Laptop, 6 IDA / D3510 Management and Monitoring Post Limited 78,900.00 0.00 Implementati 2019-04-16 2019-06-26 2019-06-11 2019-12-08 Quotations Envelope Datashow, 6 Impressoras e 5 and Evaluation on Video Conferencias) MZ-INIR-109256-GO-RFQ / Component 4- Project Under Request for Single Stage - One Aquisição de 5 Smart TV IDA / D3510 Management and Monitoring Post Limited 7,500.00 0.00 Implementati 2019-04-16 2019-06-26 2019-06-11 2019-12-08 Quotations Envelope (Televisores) and Evaluation on MZ-INIR-129230-GO-RFQ / Component 1-Institutional Request for Single Stage - One IDA / D3510 Post Limited 950,000.00 393,283.34 Signed 2019-09-14 2019-09-23 2019-11-09 2019-12-03 2020-05-07 Purchase of Production Kits Capacity Building Quotations Envelope MZ-INIR-129114-GO-RFB / Component 1-Institutional Single Stage - One IDA / D3510 Post Request for Bids Open - National 300,000.00 236,899.15 Signed 2019-09-09 2019-12-16 2019-09-14 2020-01-08 2019-10-26 2020-02-06 2019-11-25 2020-02-27 2019-12-30 2020-03-06 2020-06-27 Purchase of 55 Motorcycles Capacity Building Envelope MZ-INIR-139505-GO-RFQ / Aquisition of computer Component 1-Institutional Request for Single Stage - One equipment for the elaboration IDA / D3510 Post Limited 100,000.00 112,209.52 Signed 2019-10-21 2019-11-14 2019-12-16 2019-12-17 2020-06-13 Capacity Building Quotations Envelope of the integrated agrarian survey MZ-INIR-140873-GO-RFQ / Acquisition of Protective Component 1-Institutional Request for Single Stage - One Material for Extension IDA / D3510 Post Limited 100,000.00 0.00 Canceled 2019-11-02 2019-12-28 2020-06-25 Capacity Building Quotations Envelope Technicians in Manica and Sofala Provinces MZ-INIR-109253-GO-RFB / Component 4- Project Single Stage - One Aquisicao de 6 Viaturas 4X4, IDA / D3510 Management and Monitoring Post Request for Bids Open - National 240,000.00 0.00 Canceled 2019-04-11 2019-06-06 2019-04-16 2019-08-26 2019-05-28 2019-06-27 2019-08-01 2020-01-28 Envelope Dupla Cabine. and Evaluation Page 1 MZ-INIR-146499-GO-RFB / Acquisition of Protective Material for Extension Component 1-Institutional Single Stage - One IDA / D3510 Post Request for Bids Open - National 200,000.00 187,317.36 Signed 2019-11-28 2019-12-16 2019-12-03 2020-01-08 2020-01-14 2020-02-04 2020-02-13 2020-04-03 2020-03-19 2020-06-04 2020-09-15 Technicians in Manica, Sofala, Capacity Building Envelope Zambezia and Nampula Provinces MZ-INIR-146504-GO-RFB / Component 4- Project Purchase of 6 (six) 4x4 double Single Stage - One IDA / D3510 Management and Monitoring Post Request for Bids Open - National 290,000.00 333,854.45 Signed 2019-11-29 2019-12-17 2019-12-04 2020-01-08 2020-01-15 2020-02-05 2020-02-14 2020-02-13 2020-03-20 2020-02-26 2020-09-16 cab vehicles and one (01) Mini Envelope and Evaluation Bus MZ-INIR-166426-GO-RFQ / Supply and installation of integrated sound and video Component 1-Institutional Request for Single Stage - One system for the Consultative IDA / D3510 Post Limited 35,000.00 85,468.54 Signed 2020-04-15 2020-04-08 2020-06-10 2020-06-01 2020-12-07 Capacity Building Quotations Envelope Council of Meeting Room of the Ministry of Agriculture and Rural Development MZ-INIR-109262-GO-RFQ / Component 4- Project Aquisição de Software de Request for Single Stage - One IDA / D3510 Management and Monitoring Post Limited 40,000.00 29,336.14 Signed 2020-07-05 2020-06-10 2020-08-30 2020-09-14 2021-02-26 Gestão Financeira Quotations Envelope and Evaluation (Parametrização) MZ-INIR-180461-GO-RFQ / Acquisition of Information Component 1-Institutional Request for Single Stage - One IDA / D3510 Post Limited 20,000.00 23,903.10 Signed 2020-07-18 2020-07-10 2020-09-12 2020-07-23 2021-03-11 Equipment for the Fund Capacity Building Quotations Envelope Mobilization Unit MZ-INIR-180512-GO-RFB / Acquisition and Installation of Component 2-Smallholder Under Single Stage - One 6 Pivo Systems for Irrigating IDA / D3510 Irrigation Development and Prior Request for Bids Open - International 2,750,000.00 0.00 Implementati 2020-07-27 2020-08-01 2020-09-12 2020-10-12 2020-11-16 2021-05-15 Envelope 330ha, Chemba District, Management on Sofala Province MZ-INIR-206315-GO-RFQ / Pending Component 1-Institutional Request for Single Stage - One Acquisition of various graphic IDA / D3510 Post Limited 100,000.00 0.00 Implementati 2021-07-16 2021-09-10 2021-12-09 Capacity Building Quotations Envelope material on MZ-INIR-216077-GO-RFB / Under Component 1-Institutional Single Stage - One Acquisition of IT Equipment IDA / D3510 Post Request for Bids Open - National 160,000.00 0.00 Implementati 2021-07-14 2021-06-23 2021-07-29 2021-06-23 2021-09-09 2021-10-09 2021-11-28 2022-05-27 Capacity Building Envelope for PIU and PMU on NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MZ-INIR-185455-NC-RFQ / Contracting of sound, image, printing services for provincial Under Component 1-Institutional Request for Single Stage - One replicas in the ambit of the IDA / D3510 Post Limited 60,000.00 0.00 Implementati 2020-08-01 2020-09-26 2021-03-25 Capacity Building Quotations Envelope launch of the program on SUSTENTA in Manica, Sofala, Zambezia and Nampula. MZ-INIR-217221-NC-RFQ / Component 3-Agriculture Under Services Provider of the IDA / D3510 Intensification and Market Post Direct Selection Direct 35,000.00 0.00 Implementati 2021-02-14 2021-02-18 2021-02-19 2021-02-23 2021-03-26 2021-09-22 Electronic Producer Support Linkages on latform (ONE STOP SOLUTION) MZ-INIR-217227-NC-RFB / Hiring of E-vouchers Service Component 3-Agriculture Under Provider for the Irrigations Single Stage - One IDA / D3510 Intensification and Market Post Request for Bids Open - National 220,000.00 0.00 Implementati 2021-02-14 2021-03-17 2021-02-19 2021-03-31 2021-03-21 2021-04-20 2021-05-25 2022-05-25 Schemes of Manica, Sofala, Envelope Linkages on Zambezia and Nampula Provinces CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MZ-INIR-129100-CS-QCBS / Impact Assessment and Executive Rehabilitation Component 2-Smallholder Quality And Cost- Project Preparation for some IDA / D3510 Irrigation Development and Post Open - National 300,000.00 275,000.00 Signed 2019-09-02 2019-09-19 2019-09-23 2019-12-19 2019-11-06 2020-03-19 2019-12-04 2020-05-29 2020-01-03 2020-07-22 2020-02-07 2020-08-14 2020-03-13 2020-09-30 2020-04-17 Based Selection Irrigation Systems Affected by Management IDAI Cyclone in Manica Province MZ-INIR-129103-CS-QCBS / Impact Assessment and Executive Rehabilitation Component 2-Smallholder Quality And Cost- Project Preparation for some IDA / D3510 Irrigation Development and Post Open - National 150,000.00 132,153.48 Signed 2019-09-02 2019-09-19 2019-09-23 2019-12-19 2019-11-06 2020-03-19 2019-12-04 2020-05-29 2020-01-03 2020-07-27 2020-02-07 2020-08-26 2020-03-13 2020-09-16 2020-03-16 Based Selection Irrigation Systems Affected by Management IDAI Cyclone in Sofala Province MZ-INIR-129104-CS-QCBS / Impact Assessment and Executive Rehabilitation Component 2-Smallholder Quality And Cost- Project Preparation for some IDA / D3510 Irrigation Development and Post Open - National 150,000.00 121,956.07 Signed 2019-09-02 2019-09-19 2019-09-23 2019-12-19 2019-11-06 2020-03-19 2019-12-04 2020-05-29 2020-01-03 2020-07-27 2020-02-07 2020-08-19 2020-03-13 2020-09-30 2020-04-17 Based Selection Irrigation Systems Affected by Management IDAI Cyclone in Zambezia Province MZ-INIR-129111-CS-QCBS / Irrigation Infrastructure Component 2-Smallholder Quality And Cost- Investment Pre-Feasibility and IDA / D3510 Irrigation Development and Post Open - National 200,000.00 0.00 Canceled 2019-09-09 2019-09-19 2019-09-30 2019-11-13 2019-12-11 2020-01-10 2020-02-14 2020-03-20 2020-07-18 Based Selection Feasibility Studies in Sofala Management Province. MZ-INIR-129110-CS-QCBS / Irrigation Infrastructure Component 2-Smallholder Quality And Cost- Investment Pre-Feasibility and IDA / D3510 Irrigation Development and Post Open - National 200,000.00 0.00 Canceled 2019-09-09 2019-09-19 2019-09-30 2019-11-13 2019-12-11 2020-01-10 2020-02-14 2020-03-20 2020-07-18 Based Selection Feasibility Studies in Management Zambezia Province. Page 2 MZ-INIR-129106-CS-QCBS / Irrigation Infrastructure Component 2-Smallholder Quality And Cost- Investment Pre-Feasibility and IDA / D3510 Irrigation Development and Post Open - National 200,000.00 0.00 Canceled 2019-09-09 2019-09-19 2019-09-30 2019-11-13 2019-12-11 2020-01-10 2020-02-14 2020-03-20 2020-07-18 Based Selection Feasibility Studies in Nampula Management Province. MZ-INIR-129112-CS-QCBS / Irrigation Infrastructure Component 2-Smallholder Quality And Cost- Investment Pre-Feasibility and IDA / D3510 Irrigation Development and Post Open - National 200,000.00 0.00 Canceled 2019-09-09 2019-09-19 2019-09-30 2019-11-13 2019-12-11 2020-01-10 2020-02-14 2020-03-20 2020-07-18 Based Selection Feasibility Studies in Manica Management Province. MZ-INIR-146515-CS-CQS / Contracting a company to Component 4- Project Consultant recruit technicians for the IDA / D3510 Management and Monitoring Post Qualification Open - National 100,000.00 0.00 Canceled 2019-12-23 2019-12-17 2020-01-13 2020-02-26 2020-03-27 2020-05-01 2020-10-28 IRRIGA Project at central and and Evaluation Selection provincial levels MZ-INIR-146523-CS-QCBS / Irrigation infrastructure investment Pre-feasibility and Feasibility Studies and elaboration of executive Component 2-Smallholder Quality And Cost- projects for IDA / D3510 Irrigation Development and Prior Open - International 750,000.00 0.00 Canceled 2019-12-23 2020-02-11 2020-01-13 2020-02-26 2020-03-25 2020-04-24 2020-05-29 2020-07-03 2021-07-03 Based Selection construction/rehabilitation of Management 750 hectares of irrigation systems in Nampula province and Supervision of the respective works MZ-INIR-146521-CS-QCBS / Irrigation infrastructure investment Pre-feasibility and Feasibility Studies and elaboration of executive Component 2-Smallholder Quality And Cost- projects for IDA / D3510 Irrigation Development and Prior Open - International 750,000.00 0.00 Canceled 2019-12-23 2020-02-11 2020-01-13 2020-02-26 2020-03-25 2020-04-24 2020-05-29 2020-07-03 2021-07-03 Based Selection construction/rehabilitation of Management 750 hectares of irrigation systems in Zambezia province and Supervision of the respective works MZ-INIR-146520-CS-QCBS / Irrigation infrastructure investment Pre-feasibility and Feasibility Studies and elaboration of executive Component 2-Smallholder Quality And Cost- projects for IDA / D3510 Irrigation Development and Prior Open - International 750,000.00 0.00 Canceled 2019-12-23 2020-02-11 2020-01-13 2020-02-26 2020-03-25 2020-04-24 2020-05-29 2020-07-03 2021-07-03 Based Selection construction/rehabilitation of Management 750 hectares of irrigation systems in Manica province and Supervision of the respective works MZ-INIR-146518-CS-QCBS / Irrigation infrastructure investment Pre-feasibility and Feasibility Studies and elaboration of executive Component 2-Smallholder Quality And Cost- projects for IDA / D3510 Irrigation Development and Prior Open - International 750,000.00 0.00 Canceled 2019-12-23 2020-02-11 2020-01-13 2020-02-26 2020-03-25 2020-04-24 2020-05-29 2020-07-03 2021-07-03 Based Selection construction/rehabilitation of Management 750 hectares of irrigation systems in Sofala province and Supervision of the respective works MZ-INIR-183480-CS-CQS / Component 2-Smallholder Consultant Munda Munda Irrigation IDA / D3510 Irrigation Development and Post Qualification Limited 360,000.00 290,377.40 Signed 2020-07-30 2020-07-15 2020-08-13 2020-07-15 2020-09-12 2020-08-19 2020-10-17 2020-10-07 2021-04-15 System Supervision Management Selection MZ-INIR-180472-CS-QCBS / Component 2-Smallholder Five Irrigation System Quality And Cost- IDA / D3510 Irrigation Development and Post Open - National 270,000.00 244,915.65 Signed 2020-08-31 2020-08-26 2020-09-21 2020-11-25 2020-11-04 2020-12-22 2020-12-02 2021-01-27 2021-01-01 2021-03-24 2021-02-05 2021-03-18 2021-03-12 2021-04-27 2022-03-12 Supervision in Manica Based Selection Management Province MZ-INIR-180481-CS-CQS / Component 2-Smallholder Consultant Environmental Audit of IDA / D3510 Irrigation Development and Post Qualification Limited 90,000.00 94,851.91 Signed 2020-08-31 2020-08-03 2020-09-14 2020-08-03 2020-10-14 2021-03-24 2020-11-18 2021-05-05 2021-05-17 PROIRRI irrigations Management Selection MZ-INIR-180484-CS-CQS / Component 2-Smallholder Consultant Resettlement Action Plan IDA / D3510 Irrigation Development and Post Qualification Limited 50,000.00 126,181.54 Signed 2020-08-31 2020-08-03 2020-09-14 2020-08-03 2020-10-14 2021-02-11 2020-11-18 2021-04-08 2021-05-17 (PAR) for the Chirimonio - Management Selection ACABOCO Irrigation MZ-INIR-180476-CS-QCBS / Component 2-Smallholder Quality And Cost- Munda Munda Irrigation IDA / D3510 Irrigation Development and Post Open - National 360,000.00 0.00 Canceled 2020-07-20 2020-07-15 2020-08-10 2020-09-23 2020-10-21 2020-11-20 2020-12-25 2021-01-29 2022-01-29 Based Selection System Supervision Management MZ-INIR-185302-CS-QCBS / 750 ha Irrigation Component 2-Smallholder Quality And Cost- Infrastructure Projection and IDA / D3510 Irrigation Development and Post Open - International 750,000.00 0.00 Canceled 2020-08-31 2020-08-18 2020-09-21 2020-11-04 2020-12-02 2021-01-01 2021-02-05 2021-03-12 2022-03-12 Based Selection Its Construction Supervision Management in Manica Province MZ-INIR-185308-CS-QCBS / 750 ha Irrigation Component 2-Smallholder Quality And Cost- Infrastructure Projection and IDA / D3510 Irrigation Development and Post Open - International 750,000.00 0.00 Canceled 2020-08-31 2020-08-18 2020-09-21 2020-11-04 2020-12-02 2021-01-01 2021-02-05 2021-03-12 2022-03-12 Based Selection Its Construction Supervision Management in Nampula Province MZ-INIR-185306-CS-QCBS / 750 ha Irrigation Component 2-Smallholder Quality And Cost- Infrastructure Projection and IDA / D3510 Irrigation Development and Post Open - International 750,000.00 0.00 Canceled 2020-08-31 2020-08-18 2020-09-21 2020-11-04 2020-12-02 2021-01-01 2021-02-05 2021-03-12 2022-03-12 Based Selection Its Construction Supervision Management in Zambezia Province MZ-INIR-185305-CS-QCBS / 750 ha Irrigation Component 2-Smallholder Quality And Cost- Infrastructure Projection and IDA / D3510 Irrigation Development and Post Open - International 750,000.00 0.00 Canceled 2020-08-31 2020-08-18 2020-09-21 2020-11-04 2020-12-02 2021-01-01 2021-02-05 2021-03-12 2022-03-12 Based Selection Its Construction Supervision Management in Sofala Province Page 3 MZ-INIR-189875-CS-CQS / IRRIGA Project Office Component 2-Smallholder Consultant Rehabilitation Works IDA / D3510 Irrigation Development and Post Qualification Limited 35,000.00 84,296.31 Signed 2020-09-15 2020-09-23 2020-09-29 2020-10-01 2020-10-29 2021-04-26 2020-12-03 2021-04-27 2021-06-01 Supervision in Manica and Management Selection Zambezia Provinces MZ-INIR-197081-CS-QCBS / Manica and Sofala 1 500 ha Component 2-Smallholder Quality And Cost- Under Irrigation Infrastructure IDA / D3510 Irrigation Development and Prior Open - International 1,500,000.00 0.00 2020-10-12 2020-10-06 2020-11-02 2020-10-30 2021-01-16 2021-02-15 2021-03-17 2021-04-21 2021-05-26 2022-05-26 Based Selection Implementation Projection and Its Management Construction Supervision MZ-INIR-197082-CS-QCBS / Zambézia and Nampula 1 500 Component 2-Smallholder Quality And Cost- Under ha Irrigation Infrastructure IDA / D3510 Irrigation Development and Prior Open - International 1,500,000.00 0.00 2020-10-12 2020-10-01 2020-11-02 2020-10-30 2021-01-16 2021-02-15 2021-03-17 2021-05-07 2021-06-11 2022-06-11 Based Selection Implementation Projection and Its Management Construction Supervision MZ-INIR-197084-CS-CQS / Component 4- Project Consultant Supervision Construction Under IDA / D3510 Management and Monitoring Post Qualification Open - National 130,000.00 0.00 2020-12-14 2021-01-04 2021-01-04 2021-02-09 2021-02-17 2021-03-19 2021-04-23 2021-10-20 Works for Mziva Irrigation Implementation and Evaluation Selection System MZ-INIR-197087-CS-CQS / Component 4- Project Consultant Supervision Construction IDA / D3510 Management and Monitoring Post Qualification Open - National 100,000.00 0.00 Canceled 2020-10-19 2020-11-09 2020-12-23 2021-01-22 2021-02-26 2021-08-25 Works for CRIDF Irrigation and Evaluation Selection System MZ-INIR-206197-CS-QCBS / Service provider for training Component 3-Agriculture and coordination of farmer Quality And Cost- Under IDA / D3510 Intensification and Market Post Open - National 350,000.00 0.00 2020-12-15 2021-01-07 2021-01-14 2021-03-17 2021-03-15 2021-04-12 2021-05-12 2021-06-16 2021-07-21 2022-07-21 associations with acess to the Based Selection Implementation Linkages market in Intabo irrigation scheme in Zambézia province MZ-INIR-206312-CS-LCS / Development and Installation of an Electronic Platform Component 4- Project (online) for the Least Cost Under IDA / D3510 Management and Monitoring Post Open - National 60,000.00 0.00 2020-12-21 2021-01-07 2021-01-11 2021-06-08 2021-02-24 2021-03-24 2021-04-23 2021-05-28 2021-07-02 2021-07-05 implementation of the and Selection Implementation and Evaluation Complaints Management Mechanism of the IRRIGA Project. MZ-INIR-206919-CS-CQS / Risk Analysis of Gender-Based Component 3-Agriculture Consultant Violence (VBG) at Project Under IDA / D3510 Intensification and Market Post Qualification Limited 70,000.00 0.00 2021-01-14 2021-01-18 2021-01-28 2021-02-27 2021-04-03 2021-09-30 Implementation Sites: Implementation Linkages Selection Development of intervention strategy and action plan MZ-INIR-215845-CS-CQS / Consultant Component 1-Institutional Irrigation Speciaslist IDA / D3510 Post Qualification Limited 36,000.00 0.00 Canceled 2021-02-28 2021-01-28 2021-03-14 2021-04-13 2021-05-18 2022-05-18 Capacity Building (Zambézia) Selection MZ-INIR-222388-CS-CQS / Supervision Services for Consultant Component 1-Institutional Under Rehabilitation Works of IDA / D3510 Post Qualification Limited 70,000.00 0.00 2021-04-16 2021-04-14 2021-04-30 2021-05-30 2021-07-04 2021-12-31 Capacity Building Implementation Nampula and Sofala IRRIGA Selection Offices Project MZ-INIR-222378-CS-QCBS / Organization and Training of Component 3-Agriculture Producers and Establishiment Quality And Cost- Pending IDA / D3510 Intensification and Market Post Open - National 200,000.00 0.00 2021-07-02 2021-07-23 2021-09-05 2021-10-03 2021-11-02 2021-12-07 2022-01-11 2023-01-11 of Market Link in the Based Selection Implementation Linkages Irrigations Schemes in Sofala Provínce INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MZ-INIR-109288-CS-INDV / Individual Component 1-Institutional Especialista em Procurement IDA / D3510 Prior Consultant Open 90,000.00 0.00 Canceled 2019-04-05 2019-05-24 2019-06-14 2019-07-19 2020-01-15 Capacity Building (baseado em Maputo) Selection MZ-INIR-129523-CS-CDS / Surveying damage caused by IDAI Cyclone and preparing Component 2-Smallholder the Executive Acaboco IDA / D3510 Irrigation Development and Post Direct Selection Direct 45,000.00 50,000.00 Signed 2019-09-02 2019-09-19 2019-09-12 2019-09-30 2019-11-16 2019-12-30 2019-12-16 Irrigation System Works Management Completion Project, 316 ha, Buzi District, Sofala Province MZ-INIR-129528-CS-CDS / Surveying damage caused by IDAI Cyclone and preparing Component 2-Smallholder the Executive Mziva and IDA / D3510 Irrigation Development and Post Direct Selection Direct 90,000.00 90,000.00 Signed 2019-09-02 2019-09-19 2019-09-12 2019-09-30 2019-11-16 2019-12-18 2019-12-16 Chiverano Irrigation System Management Works Completion Project, Zambeze Province MZ-INIR-139499-CS-INDV / Component 3-Agriculture Individual Hire a consultant to boost the IDA / D3510 Intensification and Market Post Consultant Limited 30,000.00 0.00 Canceled 2019-10-14 2019-10-19 2019-11-09 2019-12-14 2020-06-11 2019/2020 agricultural Linkages Selection company in Manica Province MZ-INIR-139496-CS-INDV / Hire a consultant to boost the Component 3-Agriculture Individual 2019/2020 agricultural IDA / D3510 Intensification and Market Post Consultant Limited 35,000.00 0.00 Canceled 2019-10-14 2019-10-19 2019-11-09 2019-12-14 2020-06-11 company in Sofala and Linkages Selection Zambezia Provinces MZ-INIR-140872-CS-CDS / Service provider for the preparation of PEDSA II and Component 2-Smallholder PNISA II as part of the IDA / D3510 Irrigation Development and Post Direct Selection Direct 300,000.00 0.00 Canceled 2019-12-10 2019-12-20 2020-02-23 2020-08-21 institutional support to DPCI. Management Services performed via UN system. Page 4 Individual MZ-INIR-150739-CS-INDV / Component 1-Institutional IDA / D3510 Prior Consultant Limited 72,000.00 0.00 Canceled 2019-12-22 2020-02-11 2019-12-27 2020-02-13 2020-01-17 2020-02-21 2020-08-19 Procurement Specialist Capacity Building Selection MZ-INIR-153140-CS-CDS / Component 3-Agriculture Service Provider for Operation IDA / D3510 Intensification and Market Post Direct Selection Direct 180,000.00 199,447.47 Signed 2020-01-26 2020-01-17 2020-02-05 2020-01-22 2020-04-10 2020-03-30 2020-10-07 of da Paz Irrigation in Linkages Zambezia Province Individual MZ-INIR-167041-CS-INDV / Component 1-Institutional IDA / D3510 Prior Consultant Open 72,000.00 52,500.00 Signed 2020-05-18 2020-05-05 2020-07-06 2020-07-22 2020-07-27 2020-08-18 2020-08-31 2020-09-15 2021-02-27 Procurement Specialist Capacity Building Selection MZ-INIR-175070-CS-CDS / Organising and Building Component 3-Agriculture Capacity of Producers and IDA / D3510 Intensification and Market Post Direct Selection Direct 100,000.00 130,950.00 Signed 2020-06-30 2020-06-30 2020-07-10 2020-06-10 2020-09-13 2020-08-05 2021-03-12 Establishing Market Linkages Linkages in Manica Province MZ-INIR-178882-CS-INDV / Individual Component 1-Institutional Monitoring and Evaluation IDA / D3510 Post Consultant Limited 57,600.00 57,600.00 Signed 2020-07-13 2020-06-24 2020-07-18 2020-06-24 2020-08-08 2020-06-30 2020-09-12 2020-07-01 2021-03-11 Capacity Building Specialist Selection MZ-INIR-178865-CS-INDV / Individual Component 1-Institutional Funds Mobilization Unit IDA / D3510 Post Consultant Limited 144,000.00 144,000.00 Signed 2020-07-13 2020-06-24 2020-07-18 2020-06-24 2020-08-08 2020-06-29 2020-09-12 2020-07-01 2021-03-11 Capacity Building Coordinator Selection MZ-INIR-178878-CS-INDV / Individual Component 1-Institutional Funds Mobilization Unit IDA / D3510 Post Consultant Limited 57,600.00 57,600.00 Signed 2020-07-13 2020-06-24 2020-07-18 2020-08-05 2020-08-08 2020-08-20 2020-09-12 2020-08-20 2021-03-11 Capacity Building Environment Management Selection MZ-INIR-178874-CS-INDV / Individual Component 1-Institutional Funds Mobilization Unit IDA / D3510 Post Consultant Limited 57,600.00 57,600.00 Signed 2020-07-13 2020-06-24 2020-07-18 2020-06-24 2020-08-08 2020-06-30 2020-09-12 2020-07-01 2021-03-11 Capacity Building Finance Management Selection Individual MZ-INIR-178872-CS-INDV / Component 1-Institutional IDA / D3510 Post Consultant Limited 72,000.00 72,000.00 Signed 2020-07-13 2020-06-24 2020-07-18 2020-06-24 2020-08-08 2020-06-29 2020-09-12 2020-07-01 2021-03-11 P4R Unit Coordinator Capacity Building Selection Individual MZ-INIR-109291-CS-INDV / Component 1-Institutional IDA / D3510 Prior Consultant Direct 36,000.00 0.00 Canceled 2019-05-23 2019-06-02 2019-06-23 2019-07-28 2020-01-24 Procurement Assistant Capacity Building Selection MZ-INIR-197120-CS-INDV / Individual Consultant for Component 2-Smallholder Individual project design and Pending IDA / D3510 Irrigation Development and Post Consultant Limited 180,000.00 0.00 2020-12-10 2020-12-30 2021-01-19 2021-02-23 2022-03-20 supervision for supply and Implementation Management Selection installation of the Chemba irrigation system Individual MZ-INIR-206913-CS-INDV / Component 1-Institutional IDA / D3510 Prior Consultant Direct 36,000.00 36,000.00 Signed 2020-12-07 2021-01-12 2020-12-17 2021-03-15 2021-01-07 2021-04-11 2021-02-11 2021-04-16 2022-02-11 Procurement Assistant Capacity Building Selection Individual MZ-INIR-215703-CS-INDV / Component 1-Institutional Under IDA / D3510 Post Consultant Open 50,000.00 0.00 2021-02-10 2021-01-28 2021-03-31 2021-04-21 2021-05-26 2021-11-22 Irrigation Specialist (UGISA) Capacity Building Implementation Selection Individual MZ-INIR-215704-CS-INDV / Component 1-Institutional Under IDA / D3510 Post Consultant Limited 100.00 0.00 2021-02-10 2021-01-28 2021-02-15 2021-03-08 2021-04-12 2021-10-09 Civil Engineer Capacity Building Implementation Selection Individual MZ-INIR-215833-CS-INDV / Component 1-Institutional IDA / D3510 Post Consultant Limited 36,000.00 0.00 Canceled 2021-02-28 2021-01-28 2021-03-05 2021-03-26 2021-04-30 2022-04-30 Irrigation Specialist (Manica) Capacity Building Selection Individual MZ-INIR-215836-CS-INDV / Component 1-Institutional IDA / D3510 Post Consultant Limited 36,000.00 0.00 Canceled 2021-02-28 2021-01-28 2021-03-05 2021-03-26 2021-04-30 2022-04-30 Irrigation Specialist (Sofala) Capacity Building Selection Individual MZ-INIR-215841-CS-INDV / Component 1-Institutional IDA / D3510 Post Consultant Limited 36,000.00 0.00 Canceled 2021-02-28 2021-01-28 2021-03-05 2021-03-26 2021-04-30 2022-04-30 Irrigation Specialist (Nampula) Capacity Building Selection MZ-INIR-215847-CS-INDV / Individual Component 1-Institutional Safeguards Specislist IDA / D3510 Post Consultant Limited 30,000.00 30,000.00 Signed 2021-02-28 2021-02-24 2021-03-05 2021-03-25 2021-03-26 2021-04-09 2021-04-30 2021-04-26 2022-04-30 Capacity Building (Zambézia) Selection MZ-INIR-215851-CS-INDV / Individual Component 1-Institutional Safeguards Specialist IDA / D3510 Post Consultant Limited 30,000.00 516.57 Signed 2021-02-28 2021-02-24 2021-03-05 2021-03-25 2021-03-26 2021-04-09 2021-04-30 2021-04-26 2022-04-30 Capacity Building (Nampula) Selection Individual MZ-INIR-215857-CS-INDV / Component 1-Institutional IDA / D3510 Post Consultant Limited 30,000.00 516.57 Signed 2021-02-28 2021-02-24 2021-03-05 2021-03-25 2021-03-26 2021-04-09 2021-04-30 2021-04-26 2022-04-30 Safeguards Specialist (Manica) Capacity Building Selection Individual MZ-INIR-215859-CS-INDV / Component 1-Institutional IDA / D3510 Post Consultant Limited 30,000.00 516.57 Signed 2021-02-28 2021-02-22 2021-03-05 2021-03-25 2021-03-26 2021-04-09 2021-04-30 2021-04-26 2022-04-30 Safeguards Specialist (Sofala) Capacity Building Selection Page 5 Procurement Plan for Project of Integrated Urban and Tourism Development I. General 1. Bank’s approval Date of the procurement Plan [Original: July 15,2016]: Revision 1 of Updated Procurement Plan, May 2017 2. Date of General Procurement Notice: April 26, 2017 3. Period covered by this procurement plan: The procurement period of project covered from year May 2017 to October 2018 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Expenditur Contract Procurement Bank Prior Review e Category Value Method (USD) >= ICB All >/=US$10 million 5,000,000 contracts < NCB First contract Civil Works 5,000,000 <200,000 Shopping First contract NA DC US$60,000 >= ICB All >/=US$1million 1,000,000 contracts Goods <1,000,000 NCB First contract <100,000 Shopping First contract NA DC US$60,000 4. Reference to (if any) Project Operational/Procurement Manual: Project Operational Manual for World Bank Loan Project P155875 PIUDT issued by Albanian Development Fund on 24.04.2017 5. Summary of the Procurement Packages planned during the first 18 months after project effectiveness (including those that are subject to retroactive financing and advanced procurement) 1 2 3 4 5 6 Domestic Review Comme Ref. No. Description Packages Preference by Bank nts (yes/no) (Prior/Post) Summary of the ICB 2 No (Works) Berat Town of AL- integrated ADF15547- Prior Urban CW-RFB upgrading Saranda tourism gateway C1W-S3 No Prior integrated urban upgrading Summary of the NCB 14 No Post (Works) Saranda AL- staircase ADF15534- No Post rehabilitation CW-RFB Project Urban Regeneration of the AL- existing ADF15536- No Post promenade CW-RFB “Naim Frasheri” in Saranda Ali Pasha AL- historic trail ADF15538- and slopes No Post CW-RFB stabilization – Gjirokastra Street AL- lightening ADF15539- historic No Post CW-RFB center – Gjirokstra AL- Bazaar coble ADF15540- stone roads No Post CW-RFB rehabilitation Gjirokastra AL- museum city ADF15541- integrated No Post CW-RFB urban upgrading Upgrading AL- the ADF15536- renovation of No Post CW-RFB systems of museums Rehabilitation of AL- Cobblestone ADF28554- No Prior road “Mihal CW-RFB Komneno”, Berat castle Upgrading to AL- vehicle ADF15545- No Post access road CW-RFB “Muzak Topia”, Berat Castle Visual No AL- upgrading of ADF15542- selected Post CW-RFB heritage landscape AL- Street ADF15548- lightening – No Post CW-RFB Permet Permet AL- integrated ADF15549- No Post urban CW-RFB upgrading Integrated AL- upgrading of ADF15550- No Post selected CW-RFB touristic area Tourism AL- Product ADF15551- development No Post CW-RFB in 4 municipalities Summary of the NCB 6 No Post (Goods) Solid waste AL-ADF- equipment 15581-GO- for Himara No Prior RFB transfer station Solid W AL-ADF- collection 15582-GO- equipment(Gjir No Post RFB okastra/other as needed Financial AL-ADF- Management 15583-GO- Equipment No Post RFB for 4 municipalities Asset AL-ADF- Management 15609-GO- Equipment No Post RFB for 4 municipalities GIS AL-ADF- equipment 15584-GO- and licenses No Post RFB for 4 municipalities Equipment for tourism AL-ADF- information 15586-GO- No Post management RFB and statistic improvement Summary of the SH 4 No Post (Goods) Equipment AL-ADF- for local 15585-GO- destination No Prior RFB management entities Office equipment AL-ADF- and licenses 15588-GO- No Post for project RFB implementati on Purchase of AL-ADF- additional 44382-GO- accessories No Post RFB for smart board of ADF AL-ADF- 44382-GO- Vehicles No Post RFB III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: QCBS, QBS, FBS, >/= USD 500,000 ; NA Consultant LCS and CQS* >=US$200,000 for IC Services NA SSS and >/=US$5,000 for NA IC SSS 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 Review Ref. No. Description of Assignment Comme Packages by Bank nts (Prior/ Post) Summary of QCBS 8 AL-ADF- Concept, Design and Supervision 44317-CS- of Saranda Urban Upgrading (line Post QCBS 3) AL-ADF- Concept, Design and Supervision 39736-CS- Urban Upgrading Gjirokastra (line Post QCBS 7) Concept, Design and Supervision AL-ADF- of the Berat and Permet 31055-CS- Post Integrated Urban Upgrading (line QCBS 12 and14) Site Management, Detailed AL-ADF- design and construction 15563-CS- Prior supervision for Infrastructure of QCBS IUTS AL-ADF- Market Research & Development 15567-CS- Strategy for the South of Albania Post QCBS & four municipalities Market Development for the AL-ADF- South of Albania (Tourism 15568-CS- Prior products promotion, line 16 and QCBS component 2 works) AL-ADF- Tourism Product and value chain 15570-CS- development in selected Prior QCBS municipalities (line 16) AL-ADF- Guesthouse branding and market 44317-CS- Prior delivery QCBS Summary of CQS 9 Post AL-ADF- Design and Supervision 15556-CS- Gjirokastra system of museums Post CQS (line 8) AL-ADF- Supervision of fast truck 37871-CS- Post subproject Berat & Permet CQS AL-ADF- Supervision of fast truck 37532-CS- Post subproject Gjirokastra & Saranda CQS Detailed design and construction AL-ADF- supervision for Infrastructure for 15562-CS- Post Viewpoints along the touristic CQS circuit AL-ADF- Asset Management system - 15565-CS- assessment and technical Post CQS specification for goods (line 43) AL-ADF- Geographic Information Systems 15566-CS- - assessment and technical Post CQS specification for goods (line 44) Tourism Information AL-ADF- Management system and 15574-CS- Statistics Improvement - Post CQS assessment and technical specification of goods (line 46) AL-ADF- 15580-CS- Results Assessment (M&E) Post INDV AL-ADF- Design and urban regeneration 15557-CS- of the existing promenade “Naim Post CQS Frasheri”, Sarande Summary of IC 7 Post International expert on AL-ADF- conservation and structural 15559-CS- Post restoration of monuments and INDV historic buildings. (line 4) Financial Management Systems - AL-ADF- assessment and technical 15566-CS- Post specifications for goods. (line INDV 42) AL-ADF- Project Coordinator - Urban 15576-CS- Prior Specialist PCU INDV AL-ADF- 15576-CS- Tourism Specialist - PCU Prior INDV AL-ADF- 15577-CS- Architect - PCU Prior INDV AL-ADF- 15578-CS- Cultural Heritage Consultant Post INDV AL-ADF- 15579-CS- Site Management Consultant Post INDV PROCUREMENT Albania : Project for Integrated Urban and Tourism Development (PIUTD) PLAN General Information Country: Albania Bank’s Approval Date of the Original Procurement Plan: 2017-05-22 2021-05-17 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P155875 GPN Date: 2017-05-23 Project Name: Project for Integrated Urban and Tourism Development (PIUTD) Loan / Credit No: IBRD / 86560 A Executing Agency(ies): lbanian Development Fund WORKS Procureme Activity Reference No. / Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH nt Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) Justification for Award Type Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual AL-ADF-15534-CW-RFB / Component 1: Urban Single Stage - One 2018-02- Saranda Staircase IBRD / 86560 Upgrading and Infrastructure Post Request for Bids Open - National 894,776.70 Signed 2017-05-19 2017-07-17 2017-05-24 2017-07-05 2017-08-30 2017-08-04 2017-09-08 2017-12-15 Envelope 08 Rehabilitation Project Improvement AL-ADF-15543-CW-RFB / Component 1: Urban Rehabilitation of Cobblestone Single Stage - One 2018-02- IBRD / 86560 Upgrading and Infrastructure Prior Request for Bids Open - National 0.00 Canceled 2017-05-18 2017-05-23 2017-07-04 2017-08-03 2017-09-07 Road "Mihal Komneno" to Envelope 07 Improvement Berat castle AL-ADF-16753-CW-RFB / Component 1: Urban Rehabilitation of Cobblestone Single Stage - One 2018-03- IBRD / 86560 Upgrading and Infrastructure Prior Request for Bids Open - National 0.00 Canceled 2017-06-02 2017-06-28 2017-06-07 2017-07-19 2017-08-18 2017-09-22 Road "Mihal Komneno" to Envelope 21 Improvement Berat castle AL-ADF-28554-CW-RFB / Component 1: Urban Under Rehabilitimi i rrugës hyrëse Single Stage - One 2018-07- IBRD / 86560 Upgrading and Infrastructure Post Request for Bids Open - National 0.00 Implementat 2017-09-14 2017-09-21 2017-09-19 2017-09-25 2017-10-31 2017-11-10 2017-11-30 2018-01-04 "Mihal Komneno" për në Kala Envelope 03 Improvement ion dhe Tabja AL-ADF-15545-CW-RFB / Component 1: Urban Upgrading of vehicle access Single Stage - One 2,685,893.1 2019-01- IBRD / 86560 Upgrading and Infrastructure Post Request for Bids Open - National Signed 2018-03-01 2018-03-06 2018-04-17 2018-05-25 2018-05-17 2018-06-20 2018-06-21 2018-11-14 road "Muzak Topia" to Berat Envelope 3 19 Improvement castle AL-ADF-15540-CW-RFB / Component 1: Urban Single Stage - One 2019-05- Bazaar cobble stone roads IBRD / 86560 Upgrading and Infrastructure Post Request for Bids Open - National 0.00 Canceled 2018-02-28 2018-03-05 2018-04-16 2018-03-05 2018-05-16 2018-06-20 Envelope 20 rehabilitation Improvement Component 1: Urban AL-ADF-15548-CW-RFB / Single Stage - One 2018-10- IBRD / 86560 Upgrading and Infrastructure Post Request for Bids Open - National 0.00 Canceled 2018-03-29 2018-04-03 2018-05-15 2018-06-14 2018-07-19 Street lighting - Permet Envelope 18 Improvement AL-ADF-15550-CW-RFB / Pending Component 2: Touristic Sites Single Stage - One 2021-02- Integrated upgrading of IBRD / 86560 Post Request for Bids Open - National 0.00 Implementat 2019-04-16 2019-04-21 2019-06-02 2019-07-02 2019-08-06 Upgrading Envelope 02 selected touristic sites. ion AL-ADF-62551-CW-RFB / Component 1: Urban Under Single Stage - One 2019-03- Bazaar cobblestone roads IBRD / 86560 Upgrading and Infrastructure Post Request for Bids Open - National 0.00 Implementat 2018-05-15 2018-05-20 2018-07-01 2018-06-18 2018-07-31 2018-09-04 Envelope 03 rehabilitation Improvement ion Component 1: Urban AL-ADF-63100-CW-RFQ / Request for Single Stage - One 2019-01- IBRD / 86560 Upgrading and Infrastructure Post Limited 41,757.91 Signed 2018-06-04 2018-06-18 2018-07-30 2018-07-16 Street lighting - Permet Quotations Envelope 26 Improvement AL-ADF-15541-CW-RFB / Component 1: Urban Pending Single Stage - One 2021-12- Gjirokastra Museum City IBRD / 86560 Upgrading and Infrastructure Post Request for Bids Open - National 0.00 Implementat 2020-01-06 2020-01-11 2020-02-22 2020-03-23 2020-04-27 Envelope 26 Integrated Urban Upgrading Improvement ion AL-ADF-15539-CW-RFB / Component 1: Urban Pending Single Stage - One 2020-02- Street lighting historic center IBRD / 86560 Upgrading and Infrastructure Post Request for Bids Open - National 0.00 Implementat 2019-05-30 2019-06-04 2019-07-16 2019-08-15 2019-09-19 Envelope 19 - Gjirokastra Improvement ion AL-ADF-15542-CW-RFB / Component 1: Urban Single Stage - One 1,279,964.6 2021-05- Upgrading and renovation of IBRD / 86560 Upgrading and Infrastructure Post Request for Bids Open - National Signed 2019-09-16 2020-11-09 2019-09-21 2021-01-08 2019-11-02 2020-12-10 2019-12-02 2020-12-23 2020-01-06 2021-01-18 Envelope 7 07 system of museums Improvement AL-ADF-15546-CW-RFB / Component 1: Urban Pending Single Stage - One 2020-04- Visual Upgrading of selected IBRD / 86560 Upgrading and Infrastructure Post Request for Bids Open - National 0.00 Implementat 2019-09-09 2019-09-14 2019-10-26 2019-11-25 2019-12-30 Envelope 30 heritage landscape Improvement ion AL-ADF-15549-CW-RFB / Component 1: Urban Single Stage - One 3,882,016.8 2021-05- Permet integrated urban IBRD / 86560 Upgrading and Infrastructure Post Request for Bids Open - National Signed 2019-10-07 2020-11-05 2019-10-12 2021-01-08 2019-11-23 2020-12-11 2019-12-23 2021-01-11 2020-01-27 2021-02-26 Envelope 2 28 upgraded Improvement AL-ADF-15551-CW-RFB / Component 3:Tourism Pending Single Stage - One 2021-12- Tourism Product development IBRD / 86560 Market and Product Post Request for Bids Open - National 0.00 Implementat 2020-01-06 2020-01-11 2020-02-22 2020-03-23 2020-04-27 Envelope 18 in 4 municpalities Development ion Pending AL-ADF-51671-CW-RFB / Component 2: Touristic Sites Single Stage - One 2020-11- IBRD / 86560 Post Request for Bids Open - National 0.00 Implementat 2020-01-15 2020-01-20 2020-03-02 2020-04-01 2020-05-06 Construction of viewpoints Upgrading Envelope 02 ion AL-ADF-15537-CW-RFB / Component 1: Urban Pending Single Stage - Two 2022-02- Saranda Tourism Gateway IBRD / 86560 Upgrading and Infrastructure Post Request for Bids Open - International 0.00 Implementat 2020-01-15 2020-01-20 2020-03-02 2020-05-15 2020-06-19 Envelope 17 Integrated Urban Upgrading. Improvement ion AL-ADF-15547-CW-RFB / Component 1: Urban Under Single Stage - Two 2021-09- Berat Town of Integrated IBRD / 86560 Upgrading and Infrastructure Post Request for Bids Open - International 0.00 Implementat 2019-09-16 2021-02-17 2019-09-21 2019-11-02 2020-01-15 2020-02-19 Envelope 19 Urban Upgrading Improvement ion AL-ADF-15536-CW-RFB / Component 1: Urban Urban Regeneration of the Single Stage - One 5,016,039.7 2020-03- IBRD / 86560 Upgrading and Infrastructure Post Request for Bids Open - International Signed 2019-05-28 2019-05-27 2019-06-02 2019-05-28 2019-07-14 2019-07-10 2019-08-13 2019-07-10 2019-09-17 2019-09-16 Existing Promenade "Naim Envelope 6 15 Improvement Frasheri" in Saranda Page 1 AL-ADF-203245-CW-RFB / Integrated upgrading of Component 2: Touristic Sites Single Stage - One 2021-10- IBRD / 86560 Post Request for Bids Open - National 0.00 Canceled 2020-12-23 2020-11-09 2020-12-28 2021-01-08 2021-02-08 2020-12-10 2021-03-10 2020-12-31 2021-04-14 Zvenec – Narta & Benja Upgrading Envelope 11 thermal waters AL-ADF-213482-CW-RFB / Integrated upgrading of Component 2: Touristic Sites Single Stage - One 2021-11- IBRD / 86560 Post Request for Bids Open - National 0.00 Canceled 2021-01-20 2021-01-21 2021-01-25 2021-01-21 2021-03-08 2021-02-22 2021-04-07 2021-03-30 2021-05-12 Zvenec – Narta & Benja Upgrading Envelope 08 thermal waters AL-ADF-221470-CW-RFB / Component 1: Urban Single Stage - One 4,035,771.3 2021-12- Berat town of integrated IBRD / 86560 Upgrading and Infrastructure Post Request for Bids Open - National Signed 2021-03-02 2021-02-25 2021-03-07 2021-04-18 2021-03-31 2021-05-18 2021-04-13 2021-06-22 2021-05-19 Envelope 1 19 urban upgrading/Package 1 – Improvement Gorica AL-ADF-15538-CW-RFB / Prioritized measures to Component 1: Urban Under address urgent safety Single Stage - One 2018-11- IBRD / 86560 Upgrading and Infrastructure Post Request for Bids Open - National 0.00 Implementat 2018-01-07 2021-04-16 2018-01-12 2018-02-23 2021-05-17 2018-03-25 2021-06-04 2018-04-29 concerns and prevent loss of Envelope 29 Improvement ion heritage structures in the Castle of Gjirokastra AL-ADF-240553-CW-RFB / Integrated urban upgrading of Berat/package no. 2 – Urban rehabilitation of Iliaz Vrioni Request for square; Visual improvement Component 1: Urban Bids - Small Pending Single Stage - One 2022-04- of the urban silhouette along IBRD / 86560 Upgrading and Infrastructure Post Request for Bids Open - National Works SPD (1 0.00 Implementat 2021-06-28 2021-07-03 2021-08-14 2021-09-13 2021-10-18 Envelope 16 Antipatrea street in the city Improvement envelope ion center; Tourist signage and process) information board;/Management plans, interpretation GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual AL-ADF-15581-GO-RFB / Component 3:Tourism Single Stage - One Solid waste equipment for IBRD / 86560 Market and Product Prior Request for Bids Open - National 0.00 Canceled 2017-05-30 2017-06-04 2017-07-16 2018-01-31 2017-08-15 2017-09-19 2018-01-19 Envelope Himara transfer station Development AL-ADF-15589-GO-RFQ / Component 4: Request for Single Stage - One IBRD / 86560 Post Open - National 131,517.71 Signed 2017-07-05 2017-08-30 2017-11-20 2017-11-30 Vehicles Implementation Support Quotations Envelope AL-ADF-44382-GO-RFQ / Pending Purchase of additional Component 4: Request for Single Stage - One IBRD / 86560 Post Open - National 0.00 Implementati 2018-01-24 2018-03-21 2018-09-17 accessories for smart board of Implementation Support Quotations Envelope on ADF's meeting room AL-ADF-54729-GO-RFB / Component 3:Tourism Single Stage - One Solid waste equipment for IBRD / 86560 Market and Product Post Request for Bids Open - National 434,959.17 Signed 2018-04-10 2018-06-25 2018-04-15 2018-03-28 2018-05-27 2018-05-14 2018-06-26 2018-05-25 2018-07-31 2018-07-13 2019-01-27 Envelope Himara transfer station Development AL-ADF-15582-GO-RFB / Component 3:Tourism Pending Solid W collection Single Stage - One IBRD / 86560 Market and Product Post Request for Bids Open - National 0.00 Implementati 2020-02-10 2020-02-15 2020-03-28 2020-04-27 2020-06-01 2020-10-30 equipment(Gjirokastra/other Envelope Development on as needed) AL-ADF-15586-GO-RFB / Component 3:Tourism Pending Equipment for tourism Single Stage - One IBRD / 86560 Market and Product Post Request for Bids Open - National 0.00 Implementati 2019-11-18 2019-11-23 2020-01-04 2020-02-03 2020-03-09 2020-07-10 information management and Envelope Development on statistic improvement AL-ADF-15588-GO-RFQ / Component 4: Request for Single Stage - One Office equipment and licenses IBRD / 86560 Post Open - National 33,806.30 Signed 2018-03-25 2018-05-20 2018-08-30 2018-08-20 Implementation Support Quotations Envelope for project implementation AL-ADF-15584-GO-RFB / Component 3:Tourism Pending Single Stage - One GIS equipment and licenses IBRD / 86560 Market and Product Post Request for Bids Open - National 0.00 Implementati 2020-02-17 2020-02-22 2020-04-04 2020-05-04 2020-06-08 2020-12-06 Envelope for 4 municipalities Development on AL-ADF-15583-GO-RFB / Component 3:Tourism Pending Financial Management Single Stage - One IBRD / 86560 Market and Product Post Request for Bids Open - National 0.00 Implementati 2020-03-02 2020-03-07 2020-04-18 2020-05-18 2020-06-22 2020-11-22 Equipment for 4 Envelope Development on municipalities AL-ADF-15609-GO-RFB / Component 3:Tourism Pending Single Stage - One Asset Management Equipment IBRD / 86560 Market and Product Post Request for Bids Open - National 0.00 Implementati 2020-02-06 2020-02-11 2020-03-24 2020-04-23 2020-05-28 2020-12-26 Envelope for 4 municipalities Development on AL-ADF-111910-GO-RFQ / Component 3:Tourism Pending Equipment for local Request for Single Stage - One IBRD / 86560 Market and Product Post Open - National 0.00 Implementati 2019-10-19 2019-12-14 2020-03-13 destination management Quotations Envelope Development on entities NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual AL-ADF-15552-CS-QCBS / Component 1: Urban Concept, Design and Quality And Cost- IBRD / 86560 Upgrading and Infrastructure Prior Open - International 0.00 Canceled 2017-05-30 2017-06-20 2017-08-03 2017-08-31 2017-09-30 2017-11-04 2017-12-09 2020-07-09 Supervision of Saranda Urban Based Selection Improvement Upgrading (line 3) Page 2 AL-ADF-15557-CS-CQS / Design of Urban Regeneration Component 1: Urban Consultant of the Existing Promenade IBRD / 86560 Upgrading and Infrastructure Post Qualification Open - National 211,251.73 Signed 2017-07-11 2017-05-25 2017-08-01 2017-09-14 2017-06-28 2017-10-14 2017-06-28 2017-11-18 2017-09-10 2018-05-20 "Naim Frasheri" in Saranda. Improvement Selection (line 2) AL-ADF-15562-CS-CQS / Detailed design and Consultant Component 2: Touristic Sites construction supervision for IBRD / 86560 Post Qualification Open - International 103,802.40 Signed 2017-05-29 2017-09-28 2017-06-19 2017-09-28 2017-08-02 2018-03-26 2017-09-01 2018-03-19 2017-10-06 2018-03-30 2019-05-06 Upgrading Infrastructure for Viewpoints Selection along the touristic circuit AL-ADF-15567-CS-QCBS / Market Research & Component 3:Tourism Quality And Cost- Development Strategy for the IBRD / 86560 Market and Product Post Open - International 306,336.24 Signed 2017-05-26 2017-06-16 2017-06-15 2017-07-30 2017-10-17 2017-08-27 2017-11-17 2017-09-26 2018-01-15 2017-10-31 2018-02-08 2017-12-05 2018-04-04 2018-07-05 Based Selection South of Albania & four Development municipalities Consultant AL-ADF-15580-CS-INDV / Component 4: IBRD / 86560 Post Qualification Open - National 0.00 Canceled 2019-03-12 2019-03-26 2019-05-21 2019-06-25 2022-06-25 Results Assessment (M&E) Implementation Support Selection AL-ADF-15561-CS-CQS / Component 1: Urban Consultant Supervision of fast truck IBRD / 86560 Upgrading and Infrastructure Post Qualification Open - International 0.00 Canceled 2017-05-31 2017-06-21 2017-08-04 2017-09-03 2017-10-08 2019-02-08 subproject ( line Improvement Selection 1,2,4,5,6,9,10,13) AL-ADF-15555-CS-QCBS / Concept, Design and Component 1: Urban Quality And Cost- Supervision of the Berat and IBRD / 86560 Upgrading and Infrastructure Prior Open - International 0.00 Canceled 2017-05-31 2017-09-26 2017-06-21 2017-08-04 2017-09-01 2017-10-01 2017-11-05 2017-12-10 2020-06-09 Based Selection Permet Integrated Urban Improvement Upgrading ( line 12 and14) AL-ADF-31055-CS-QCBS / Concept, Detail Designs and Component 1: Urban supervision for Integrated Quality And Cost- IBRD / 86560 Upgrading and Infrastructure Post Open - International 1,119,945.08 Signed 2017-10-04 2017-10-25 2017-10-04 2017-12-08 2018-01-30 2018-01-05 2018-03-01 2018-02-04 2018-03-11 2018-04-15 2018-05-31 2019-04-15 Urban Upgrading Based Selection Improvement Municipalities of Berati and Përmeti AL-ADF-21339-CS-QBS / Component 1: Urban Supervision of fast truck sub- Quality Based IBRD / 86560 Upgrading and Infrastructure Post Open - National 0.00 Canceled 2017-07-20 2017-08-10 2017-09-23 2017-10-21 2017-11-20 2017-12-20 2018-01-24 2019-01-24 project (Saranda and Selection Improvement Gjirokastra) AL-ADF-37532-CS-CQS / Component 1: Urban Consultant Supervision of fast truck Pending IBRD / 86560 Upgrading and Infrastructure Post Qualification Open - National 0.00 2017-11-20 2017-12-11 2018-01-24 2018-02-23 2018-03-30 2018-09-26 subproject (Saranda and Implementation Improvement Selection Gjirokastra) AL-ADF-21342-CS-QBS / Component 1: Urban Quality Based Supervision of fast truck sub- IBRD / 86560 Upgrading and Infrastructure Post Open - National 0.00 Canceled 2017-07-21 2017-08-11 2017-09-24 2017-10-22 2017-11-21 2017-12-21 2018-01-25 2019-01-25 Selection project (Berat and Permet) Improvement AL-ADF-37871-CS-CQS / Supervision services for fast- Component 1: Urban Consultant truck sub-project in urban Pending IBRD / 86560 Upgrading and Infrastructure Post Qualification Open - National 0.00 2017-11-22 2017-12-13 2018-01-26 2018-02-25 2018-04-01 2018-09-28 upgrading and infrastructure Implementation Improvement Selection improvement (Berat and Permet) AL-ADF-15553-CS-QCBS / Component 1: Urban Concept, Design and Quality And Cost- IBRD / 86560 Upgrading and Infrastructure Prior Open - International 0.00 Canceled 2017-06-30 2017-07-21 2017-09-03 2017-10-01 2017-10-31 2017-12-05 2018-01-09 2020-07-09 Supervision Urban Upgrading Based Selection Improvement Gjirokastra (line 7) AL-ADF-44317-CS-QCBS / Municipality of Saranda - Detailed Designs and Component 2: Touristic Sites Quality And Cost- Under IBRD / 86560 Post Open - International 785,770.71 2018-01-17 2018-01-17 2018-02-07 2018-03-23 2018-04-10 2018-04-20 2018-05-17 2018-05-20 2018-07-17 2018-06-24 2018-07-29 2019-07-29 Construction Supervision for Upgrading Based Selection Implementation Saranda Tourism Gateway Integrated Urban Upgrading AL-ADF-39736-CS-QCBS / Component 1: Urban Concept, Design and Quality And Cost- IBRD / 86560 Upgrading and Infrastructure Post Open - International 458,168.07 Signed 2017-12-07 2017-12-07 2017-12-28 2018-02-28 2018-03-13 2018-03-28 2018-04-17 2018-04-27 2018-06-14 2018-06-01 2018-07-06 2018-09-20 2019-07-06 Supervision Urban Upgrading Based Selection Improvement Gjirokastra (line 7) AL-ADF-15556-CS-CQS / Component 1: Urban Consultant Design and Supervision IBRD / 86560 Upgrading and Infrastructure Post Qualification Open - National 242,675.38 Signed 2018-03-15 2018-04-05 2018-05-19 2018-10-29 2018-06-18 2018-12-21 2018-07-23 2018-12-24 2020-08-21 Gjirokastra system of Improvement Selection museums (line 8) AL-ADF-62578-CS-CQS / Primary Data Collection, Development of Mid-Term Consultant Component 4: and End Follow up Surveys, IBRD / 86560 Post Qualification Open - National 94,515.12 Signed 2018-05-14 2018-05-30 2018-05-16 2018-06-29 2018-06-14 2018-07-29 2018-07-13 2018-09-02 2018-07-23 2019-03-01 Implementation Support Assessment of PDO findings Selection achievement in the framework of PIUTD AL-ADF-15563-CS-QCBS / Site Management, Detailed Component 2: Touristic Sites Quality And Cost- Under design and construction IBRD / 86560 Post Open - International 0.00 2018-03-30 2020-11-02 2018-04-20 2018-06-03 2018-07-01 2018-07-31 2018-09-04 2018-10-09 2020-06-07 Upgrading Based Selection Implementation supervision for Infrastructure of IUTS AL-ADF-67670-CS-CQS / Site management, interpretive Consultant Component 2: Touristic Sites and visitor experience plans IBRD / 86560 Post Qualification Open - International 105,612.88 Signed 2018-09-10 2018-06-27 2018-10-01 2018-11-14 2018-08-20 2018-12-14 2018-09-26 2019-01-18 2018-10-24 2019-07-17 Upgrading for Zvernec - Narta & Benja Selection thermal waters touristic sites AL-ADF-15565-CS-CQS / Asset Management system - Component 3:Tourism Consultant Pending assessment and technical IBRD / 86560 Market and Product Post Qualification Open - National 0.00 2019-10-15 2019-11-05 2019-12-19 2020-01-18 2020-02-22 2020-09-21 Implementation specification for goods (line Development Selection 43) Page 3 AL-ADF-15566-CS-CQS / Geographic Information Component 3:Tourism Consultant Pending Systems - assessment and IBRD / 86560 Market and Product Post Qualification Open - National 0.00 2019-10-30 2019-11-20 2020-01-03 2020-02-02 2020-03-08 2020-09-07 Implementation technical specification for Development Selection goods (line 44) AL-ADF-15568-CS-QCBS / Market Development for the Component 3:Tourism Quality And Cost- South of Albania (Tourism IBRD / 86560 Market and Product Post Open - International 782,186.61 Signed 2019-05-16 2020-01-22 2019-06-06 2020-01-22 2019-07-20 2020-03-10 2019-08-17 2020-05-04 2019-09-16 2020-05-08 2019-10-21 2020-05-29 2019-11-25 2020-08-14 2022-09-24 Based Selection products promotion, line 16 Development and component 2 works) AL-ADF-15573-CS-QCBS / Component 3:Tourism Quality And Cost- Pending Guesthouse branding and IBRD / 86560 Market and Product Post Open - International 0.00 2019-10-31 2019-11-21 2020-01-04 2020-02-01 2020-03-02 2020-04-06 2020-05-11 2023-07-12 Based Selection Implementation market delivery Development AL-ADF-15574-CS-CQS / Tourism Information Management system and Component 3:Tourism Consultant Under Statistics Improvement - IBRD / 86560 Market and Product Post Qualification Open - National 0.00 2019-04-30 2021-05-07 2019-05-21 2021-05-25 2019-07-04 2019-08-03 2019-09-07 2020-04-08 Implementation assessment and technical Development Selection specification of goods (line 46) AL-ADF-15570-CS-QCBS / Component 3:Tourism Tourism Product and value Quality And Cost- Under IBRD / 86560 Market and Product Prior Open - International 0.00 2019-12-02 2020-11-03 2019-12-23 2020-11-09 2020-02-05 2021-04-12 2020-03-04 2021-04-16 2020-04-03 2020-05-08 2020-06-12 2023-07-13 chain development in selected Based Selection Implementation Development municipalities (line 16) AL-ADF-123249-CS-CQS / “Identification, Design of prioritized measures to Component 1: Urban Consultant address urgent safety IBRD / 86560 Upgrading and Infrastructure Post Qualification Open - International 599,204.68 Signed 2019-07-28 2019-07-23 2019-08-18 2019-10-01 2019-09-20 2019-10-31 2019-09-26 2019-12-05 2019-12-27 2020-06-02 concerns and prevent loss of Improvement Selection heritage structures in the castle of Gjirokastra AL-ADF-189626-CS-CQS / Detailed Designs and Consultant Construction Supervision for Component 2: Touristic Sites IBRD / 86560 Post Qualification Open - International 115,922.92 Signed 2020-08-26 2020-08-26 2020-09-16 2021-02-02 2020-10-30 2021-01-25 2020-11-29 2021-03-01 2021-01-03 2021-03-31 2021-07-02 Infrastructure for Viewpoints Upgrading Selection along the touristic circuit in Southern Albania AL-ADF-194223-CS-CQS / Mobility Plan and Detailed Component 1: Urban Consultant Design of project investments IBRD / 86560 Upgrading and Infrastructure Post Qualification Open - International 350,002.97 Signed 2020-09-18 2020-10-02 2020-10-09 2021-01-27 2020-11-22 2020-12-24 2020-12-22 2021-03-29 2021-01-26 2021-04-06 2021-07-25 for Integrated Urban Improvement Selection Upgrading of Gjirokastra AL-ADF-217475-CS-CQS / Component 1: Urban Consultant Supervision of work contract IBRD / 86560 Upgrading and Infrastructure Post Qualification Limited 0.00 Canceled 2021-02-08 2021-02-04 2021-02-22 2021-03-24 2021-04-28 2021-10-25 for Permet urban upgrading Improvement Selection AL-ADF-219890-CS-CQS / Supervision services for the Component 1: Urban Consultant works contract – “Permet IBRD / 86560 Upgrading and Infrastructure Post Qualification Limited 128,121.29 Signed 2021-02-19 2021-02-25 2021-03-05 2021-03-02 2021-04-04 2021-03-05 2021-05-09 2021-03-12 2021-11-05 urban upgrading” and Improvement Selection “Gjirokstra system of museums” AL-ADF-220974-CS-CQS / Consultant Gjirokastra Castle Sustainable Component 2: Touristic Sites Under IBRD / 86560 Post Qualification Open - International 0.00 2021-02-26 2021-03-04 2021-03-19 2021-05-02 2021-06-01 2021-07-06 2022-01-02 Management and Tourism Upgrading Implementation Selection Valorization Masterplan AL-ADF-222324-CS-CQS / Component 1: Urban Consultant Supervision for integrated IBRD / 86560 Upgrading and Infrastructure Post Qualification Open - International 279,052.02 Signed 2021-03-05 2021-03-03 2021-03-26 2021-03-05 2021-05-09 2021-04-20 2021-06-08 2021-05-17 2021-07-13 2021-05-20 2022-01-09 urban upgrading works - Improvement Selection Municipality of Berat AL-ADF-222330-CS-CQS / Consultant Gjirokastra Castle Sustainable Component 2: Touristic Sites Under IBRD / 86560 Post Qualification Open - International 0.00 2021-03-05 2021-03-03 2021-03-26 2021-03-05 2021-05-09 2021-04-16 2021-06-08 2021-07-13 2022-01-09 Management and Tourism Upgrading Implementation Selection Valorization Masterplan AL-ADF-231637-CS-CQS / Supervision services for Component 1: Urban Consultant Under Integrated Urban Upgrading IBRD / 86560 Upgrading and Infrastructure Post Qualification Open - International 0.00 2021-04-30 2021-05-04 2021-05-21 2021-05-13 2021-07-04 2021-08-03 2021-09-07 2022-03-06 Implementation works - Municipality of Improvement Selection Gjirokastra AL-ADF-235051-CS-QCBS / Component 3:Tourism Product Development – Quality And Cost- Under IBRD / 86560 Market and Product Post Open - International 0.00 2021-05-21 2021-06-07 2021-06-11 2021-06-23 2021-07-25 2021-08-22 2021-09-21 2021-10-26 2021-11-30 2022-11-30 package 2 (outdoor & Based Selection Implementation Development museums) INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Contract Type Process Status Teams of Reference Identified/Selected Signed Contract Contract Completion No. (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual AL-ADF-15172-CS-INDV / Individual Component 4: Under Project Coordinator - Urban IBRD / 86560 Post Consultant Open 0.00 2017-05-13 2017-05-25 2017-07-01 2017-04-03 2017-07-22 2017-08-26 2022-09-26 Implementation Support Implementation Specialist PCU Selection Individual AL-ADF-15576-CS-INDV / Component 4: Under IBRD / 86560 Post Consultant Open 0.00 2017-05-18 2017-05-25 2017-07-06 2017-04-03 2017-07-27 2017-08-31 2022-10-01 Tourism Specialist - PCU Implementation Support Implementation Selection Individual AL-ADF-15577-CS-INDV / Component 4: Under IBRD / 86560 Post Consultant Open 0.00 2017-05-18 2017-05-25 2017-07-06 2017-03-31 2017-07-27 2017-05-05 2017-08-31 2022-10-01 Architect - PCU Implementation Support Implementation Selection AL-ADF-15559-CS-INDV / International expert on Component 1: Urban Individual conservation and structural IBRD / 86560 Upgrading and Infrastructure Post Consultant Open 25,348.68 Signed 2017-05-29 2017-11-01 2017-07-17 2017-12-01 2017-08-07 2018-03-05 2018-03-07 2018-03-07 2018-04-06 restoration of monuments and Improvement Selection historic buildings. (line 4) Page 4 AL-ADF-67092-CS-INDV / Individual Consultant for Preparation of a Property Evaluation Report of Project Individual Component 4: Affected Persons due to the IBRD / 86560 Post Consultant Open 5,358.00 Signed 2018-06-29 2018-06-19 2018-08-17 2018-06-22 2018-09-07 2018-06-26 2018-10-12 2018-06-29 2019-04-10 Implementation Support planned implementation of Selection subproject "Upgrading of the vehicle road segment Muzak Topia to Berat Castle" AL-ADF-95814-CS-INDV / Assessment of social impact Individual at proposed Blue Eye touristic Component 4: IBRD / 86560 Post Consultant Limited 3,971.16 Signed 2019-01-22 2019-01-27 2019-01-29 2019-02-17 2019-01-27 2019-03-24 2019-01-29 2019-04-13 site Implementation Support Selection Project for Integrated Tourism Development AL-ADF-15564-CS-INDV / Financial Management Component 3:Tourism Individual Pending Systems - assessment and IBRD / 86560 Market and Product Post Consultant Open 0.00 2019-09-18 2019-11-06 2019-11-27 2020-01-01 2020-05-31 Implementation technical specifications for Development Selection goods. (line 42) Individual AL-ADF-15578-CS-INDV / Component 4: IBRD / 86560 Post Consultant Open 51,395.04 Signed 2019-09-10 2020-07-15 2019-10-29 2020-09-08 2019-11-19 2020-09-08 2019-12-24 2020-09-29 2024-11-23 Cultural Heritage Consultant Implementation Support Selection Individual AL-ADF-15579-CS-INDV / Component 4: Pending IBRD / 86560 Post Consultant Open 0.00 2019-12-16 2020-02-03 2020-02-24 2020-03-30 2025-02-28 Site Management Consultant Implementation Support Implementation Selection Individual AL-ADF-217478-CS-INDV / Component 4: IBRD / 86560 Post Consultant Limited 35,975.63 Signed 2021-02-08 2021-02-05 2021-02-13 2021-02-08 2021-03-06 2021-05-06 2021-04-10 2021-05-11 2021-10-07 Project coordinator Implementation Support Selection Individual AL-ADF-234570-CS-INDV / Component 4: Under IBRD / 86560 Post Consultant Limited 0.00 2021-05-18 2021-05-19 2021-05-23 2021-05-20 2021-06-13 2021-07-18 2022-01-14 Senior Architect Exxpert Implementation Support Implementation Selection Page 5 Procurement Plan (Textual Part) I. General 1. Project Information Country: Zambia Project Name: Zambia Education Enhancement Project Project Id: P158570 2. Project Implementation Agency: Ministry of General Education 3. Date of the Procurement Plan: 4. Period Covered by this procurement plan: June 01, 2018 to Nov 30, 2019 II. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. III. Bank’s Standard Procurement Documents: The Bank’s Standard Procurement Documents shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. IV. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in The Zambia - Public Procurement Act, 2008, Amendment Act of 2013 and the Public procurement Regulations, of 2013, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions: (the “Procurement Guidelines”), and the additional provisions in the following paragraphs: 1 (a) Eligibility: Eligibility to participate in a procurement process and to be awarded an Association-financed contract shall be as defined under Section I of the Procurement Guidelines; accordingly, no bidder or potential bidder shall be declared ineligible for contracts financed by the Association for reasons other than those provided in Section I of the Procurement Guidelines. No restriction based on nationality of bidders and/or origin of goods shall apply, and foreign bidders shall be allowed to participate in NCB without application of restrictive conditions, such as, but not limited to, mandatory partnering or subcontracting with national entities. (b) Domestic Preference: No margins of preference of any sort shall be applied in the bid evaluation. (c) Bidding Documents: Procuring entities shall use bidding documents acceptable to the Association. (d) Bid validity: An extension of bid validity, if justified by exceptional circumstances, may be requested in accordance with Appendix 1 of the Procurement Guidelines. A corresponding extension of any bid guarantee shall be required in all cases of extension of bid validity. A bidder may refuse a request for extension of bid validity without forfeiting its bid guarantee. (e) Qualification: Qualification criteria shall be clearly specified in the bidding documents. All criteria so specified, and only such specified criteria, shall be used to determine whether a bidder is qualified. Qualification shall be assessed on a “pass or fail” basis, and merit points shall not be used. Such assessment shall be based entirely upon the bidder’s or prospective bidder’s capability and resources to effectively perform the contract, taking into account objective and measurable factors, including: (i) relevant general and specific experience, and satisfactory past performance and successful completion of similar contracts over a given period; (ii) financial position; and where relevant (ii) capability of construction and/or manufacturing facilities (f) Prequalification procedures and documents acceptable to the Association shall be used for large, complex and/or specialized works. Verification of the information upon which a bidder was prequalified, including current commitments, shall be carried out at the time of contract award, along with the bidder’s capability with respect to personnel and equipment. Where pre-qualification is not used, the qualification of the bidder who is recommended for award of contract shall be assessed by post-qualification, applying the qualification criteria stated in the bidding documents. (g) Bid Evaluation: All bid evaluation criteria other than price shall be quantifiable in monetary terms. Merit points shall not be used, and no minimum point or percentage value shall be assigned to the evaluation criteria or significance of price in bid evaluation. No negotiations shall be permitted. (h) Guarantees: Guarantees shall be in the format, shall have the period of validity and shall be submitted when and as specified in the bidding documents. (i) Cost Estimates: Detailed cost estimates shall be confidential and shall not be disclosed to prospective bidders. No bids shall be rejected on the basis of 2 comparison with the cost estimates without the Association’s prior written concurrence. (j) Rejection of bids and re-bidding: No bid shall be rejected solely because it falls outside of a predetermined price range or exceeds the estimated cost. All bids (or the sole bid if only one bid is received) shall not be rejected, the procurement process shall not be cancelled, and new bids shall not be solicited without the Association’s prior written concurrence. (k) Fraud and corruption: In accordance with the Procurement Guidelines, each bidding document and contract shall include provisions stating the Association’s policy to sanction firms or individuals found to have engaged in fraud and corruption as set forth in the Procurement Guidelines. (l) Inspection and audit rights: In accordance with the Procurement Guidelines, each bidding document and contract shall include provisions stating the Bank’s policy with respect to inspection and audit of accounts, records and other documents relating to the submission of bids and contract performance. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. In accordance with paragraph 5.4(c) and 5.5 of the Procurement Regulations, the request for bids/request for proposals/request for quotations document shall require that Bidders/Proposers submitting Bids/Proposals/quotations present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti- Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. The form of the Letter of Acceptance is attached in Appendix 1. V. Prequalification: Not applicable VI. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not applicable VII. Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations: Not applicable VIII. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Specify for each. (a) Goods: Not applicable 3 (b) Works: Not applicable Domestic preference is not applicable for National Open Competitive Procurement IX. Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable: Not applicable X. Other Relevant Procurement Information Not applicable XI. Procurement Prior Review Thresholds (US$ millions) Type of Procurement High Substantial Moderate Low Risk Risk Risk Risk Works (including turnkey, supply 15 & installation of plant and equipment, and PPP) Goods, information technology 2 and non-consulting services Consultants: firms 0.3 Consultants: Individuals 0.1 Post Review: All contacts not subject to prior review shall be subject to post review. XII. Thresholds for Procurement Approaches and Method (US$ millions) Works Goods, IT and Non-consulting Shortlist of National Services Consultants Open Open Request Open Open Request Consulti Engineeri Internatio Nationa for Internatio Nation for ng ng & nal l Quotati nal al Quotati Services Construct on on ion ≥ < ≥ < Supervisi ≤ ≤ on 15 15 0.2 2 2 0.1 0.3 0.3 4 XIII. Summary of the procurement packages: (Planned for the first 18 months after project effectiveness): Category: Sr. Contract Description Estimat Rev Market Selectio Evalua Procure- Prequa Domesti Expect Expecte No ed Cost iew Approa n -tion ment li- c ed d date (US$) by ch Method Option Process fication Preferen date of of Ban (Open- (RFP, s (Single (Yes/ ce bid/ Contrac k Nation RFB, (BAFO, stage- No) (Yes/No) propos t (Pri al/ QCBS Rated single al Signatur or/ Limite etc.) Criteria envelope openin e Post d etc.) etc.) etc.) g ) 1 Procure materials for 19,557. Post Limite RFQ BAFO Single NO NO 16/07/ 3/08/20 ZEEP Launch 28 d 2018 18 2 Procure Consultancy 16,176. Post Open DS BAFO Single NO NO 8/10/2 26/10/2 services for 47 018 018 development of Project Implementation Unit Training Needs Assessment 3 Procure Consultancy 25,171. Prio Open DS BAFO Single NO NO 26/03/ 15/05/2 services for Year 0 57 r 2018 018 Independent Verification Audit by Auditor General 4 Procure Consultancy 14,705. Post Open CQS BAFO Single NO NO 12/07/ 03/08/2 services for 88 2018 018 development of Communication Strategy 5 Procure furniture for 13,284. Post Limite RFQ BAFO Single NO NO 06/07/ 20/07/2 PIU Office 31 d 2018 018 6 Procure Office 29,277. Post Limite RFQ BAFO Single NO NO 29/06/ 13/07/2 equipment for PIU 47 d 209 018 Office 7 Procure Consultancy 31,552. Post Open CQS BAFO Two Yes NO 9/07/2 7/09/20 services for the 94 Stage 018 18 development of the Monitoring & Evaluation Project Sub System 8 127,60 Post Open CQS BAFO Two Yes NO 23/07/ 21/09/2 Procure Consultancy 0 Stage 2018 08 services to develop a school mapping framework 9 598,00 Prio Open QCBS BAFO Two Yes NO 23/07/ 12/10/2 Procure consultancy 0 r Stage 2018 08 services for development of the EEMIS Software 10 Procure Consultancy to 230,00 Post Open CQS BAFO Two Yes NO 23/07/ 21/09/2 migrate the Legacy 0 Stage 2018 08 Access Based EMIS into the desired on new requirements from the Business Process 11 Procure Consultancy 175,00 Post Open CQS BAFO Two Yes NO 23/07/ 21/09/2 services to develop 0 Stage 2018 08 tools and standards for school records management systems 12 Procure Consultancy 168,90 Post Open CQS BAFO Two Yes NO 23/07/ 21/09/2 services to develop 0 Stage 2018 08 Specific EMIS Modules 5 13 Procurement 50,000 Prio Open DS Single NO NO 16/07/ 31/07/2 Consultant services for r 2018 018 Component 3 Coordinator 14 Procurement 50,000 Prio Open DS Single NO NO 16/07/ 31/07/2 Consultant services for r 2018 018 Communication Officer 15 Procure services for PIU 15,900 Post Limite RFQ BAFO Single NO NO 6/07/2 13/07/2 Office Partitioning d 018 018 16 Procurement of project 3,190,0 Prio Direct UNOPS BAFO Single NO NO 20/07/ 24/08/2 motor vehicles 00 r 2018 018 17 Procurement of project 301,00 Prio Direct UNOPS BAFO Single NO NO 20/07/ 24/08/2 motor cycles 0 r 2018 018 6 Appendix 1 Letter of Acceptance of the World Bank’s Anti-Corruption Guidelines and Sanctions Framework Date: Invitation of Bids/Proposals No.__________ To: ___________________________________________________________________________ We, along with our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not) consultants and personnel, acknowledge and agree to abide by the World Bank’s policy regarding Fraud and Corruption (corrupt, fraudulent, collusive, coercive, and obstructive practices), as set out and defined in the World Bank’s Anti-Corruption Guidelines1 in connection with the procurement and execution of the contract (in case of award), including any amendments thereto. We declare and warrant that we, along our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not), consultants and personnel, , are not subject to, and are not controlled by any entity or individual that is subject to, a temporary suspension, early temporary suspension, or debarment imposed by a member of the World Bank Group, including, inter alia, a cross-debarment imposed by the World Bank Group as agreed with other international financial institutions (including multilateral development banks), or through the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement. Further, we are not ineligible under the laws or official regulations of [Insert name of Employer as per bidding document] or pursuant to a decision of the United Nations Security Council. We confirm our understanding of the consequences of not complying with the World Bank’s Anti-Corruption Guidelines, which may include the following: a. rejection of our Proposal/Bid for award of contract; b. in the case of award, termination of the contract, without prejudice to any other remedy for breach of contract; and c. sanctions, pursuant to the Bank’s Anti-corruption Guidelines and in accordance with its prevailing sanctions policies and procedures as set forth in the Bank’s Sanctions Framework. This may include a public declaration of ineligibility, either indefinitely or for a stated period of time, (i) to be awarded or otherwise benefit from a Bank-financed 1Guidelines on Preventing and Combating Fraud and Corruption in Projects Financed by International Bank for Reconstruction and Development Loans and the International Development Agency Credits and Grants, dated October 15, 2006, and revised in January 2011 and July 2016, as they may be revised from time to time. 7 contract, financially or in any other manner;2 (ii) to be a nominated3 sub- contractor, consultant, manufacturer or supplier, or service provider of an otherwise eligible firm being awarded a Bank-financed contract; and (iii) to receive the proceeds of any loan made by the Bank or otherwise to participate further in the preparation or implementation of any Bank- financed project. We understand that we may be declared ineligible as set out above upon: a. completion of World Bank Group sanctions proceedings according to its prevailing sanctions procedures; b. cross-debarment as agreed with other international financial institutions (including multilateral development banks); c. the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement; or d. temporary suspension or early temporary suspension in connection with an ongoing World Bank Group sanctions proceeding. For avoidance of doubt, the foregoing effects of ineligibility do not extend to a sanctioned firm’s or individual’s execution of its ongoing Bank-financed contracts (or its ongoing sub-agreements under such contracts) that are not the subject of a material modification, as determined by the Bank. We shall permit, and shall cause our sub-contractors, sub-consultants, agents (whether declared or not), personnel, consultants, service providers or suppliers, to permit the Bank to inspect4 all accounts, records, and other documents relating to the procurement process and/or contract execution (in 2 For the avoidance of doubt, a sanctioned party’s ineligibility to be awarded a contract shall include, without limitation, (i) applying for pre-qualification, expressing interest in a consultancy, and bidding, either directly or as a nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider, in respect of such contract, and (ii) entering into an addendum or amendment introducing a material modification to any existing contract. 3 A nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider (different names are used depending on the particular bidding document) is one which has been: (i) included by the bidder in its pre-qualification application or bid because it brings specific and critical experience and know-how that allow the bidder to meet the qualification requirements for the particular bid; or (ii) appointed by the Borrower. 4 Inspections in this context are usually investigative (i.e., forensic) in nature: they involve fact-finding activities undertaken by the Bank or persons appointed by the Bank to address specific matters related to investigations/audits, such as evaluating the veracity of an allegation of possible Fraud and Corruption, through the appropriate mechanisms. Such activity includes but is not limited to accessing and examining a firm's or individual's financial records and information, and making copies thereof as relevant; accessing and examining any other documents, data, and information (whether in hard copy or electronic format) deemed relevant for the investigation/audit, and making copies thereof as relevant; interviewing staff and other relevant individuals; performing physical inspections and site visits; and obtaining third-party verification of information. 8 the case of award), and to have them audited by auditors appointed by the Bank. We agree to preserve all accounts, records, and other documents (whether in hard copy or electronic format) related to the procurement and execution of the contract. Name of the Bidder/Consultant: Name of the person duly authorized to sign the Bid/Proposal on behalf of the Bidder/Consultant: Title of the person signing the Letter: 9 PROCUREMENT Zambia : Zambia Education Enhancement Project PLAN General Information Country: Zambia Bank’s Approval Date of the Original Procurement Plan: 2018-06-28 2021-05-15 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P158570 GPN Date: Project Name: Zambia Education Enhancement Project Loan / Credit No: IDA / 61360 Ministry of General Education Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Enhancing Planning, ZM-MOGE-18 / Procure Management and Monitoring Request for Single Stage - One 2019-01- services for PIU Office IDA / 61360 Post Limited 15,900.00 39,895.75 Signed 2018-06-06 2018-07-05 2018-08-01 2018-09-10 and Evaluation Capacity, and Quotations Envelope 28 partitioning Project Coordination ZM-MOGE-170335-CW-RFB / Supply and installation of Increasing Equitable Access Single Stage - One 2021-02- IDA / 61360 Prior Request for Bids National 8,000,000.00 0.00 Canceled 2020-05-04 2020-05-09 2020-06-20 2020-07-20 2020-08-24 solar water pumps to ZEEP to Secondary Education Envelope 20 schools GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZM-MOGE-64790-GO-UN / Improving the Quality of UN Agencies procurement of project motor IDA / 61360 Post Direct 3,190,000.00 467,135.40 Signed 2018-07-18 2018-07-23 2018-07-25 2018-08-27 2018-09-21 2019-02-23 Teaching and Learning (Direct) vehicles ZM-MOGE-64800-GO-UN / Increasing Equitable Access UN Agencies procurement of project motor IDA / 61360 Post Direct 301,000.00 0.00 Canceled 2018-07-18 2018-07-23 2018-08-27 2019-02-23 to Secondary Education (Direct) bikes Enhancing Planning, ZM-MOGE-01 / Procure Management and Monitoring Request for Single Stage - One IDA / 61360 Post Limited 19,557.28 0.00 Canceled 2018-06-08 2018-08-03 2019-01-30 materials for ZEEP launch and Evaluation Capacity, and Quotations Envelope Project Coordination ZM-MOGE-05 / Procure Enhancing Planning, Under office for furniture Project Management and Monitoring Request for Single Stage - One IDA / 61360 Post Limited 13,284.31 0.00 Implementati 2018-06-20 2018-08-21 2018-08-15 2019-02-11 Implementation Unit (PIU) and Evaluation Capacity, and Quotations Envelope on office Project Coordination Enhancing Planning, ZM-MOGE-06 / Procure Under Management and Monitoring Request for Single Stage - One Office equipment for the PIU IDA / 61360 Post Limited 29,277.47 0.00 Implementati 2018-06-20 2018-08-21 2018-08-15 2019-02-11 and Evaluation Capacity, and Quotations Envelope office on Project Coordination ZM-MOGE-118828-GO-RFB / Supply and Delivery of Grades 5 and 8 Textbooks Improving the Quality of Single Stage - Two (Revised Curriculum) to IDA / 61360 Prior Request for Bids Open - International 2,300,000.00 0.00 Canceled 2019-06-19 2019-06-18 2019-06-24 2019-08-30 2019-08-05 2019-10-16 2019-11-22 2020-05-20 Teaching and Learning Envelope selected Districts in Zambia on the basis of a 3 years framework agreement ZM-MOGE-169658-GO-RFB / Supply and Delivery of Grades 5 and 8 Textbooks Improving the Quality of Single Stage - Two (Revised Curriculum) to IDA / 61360 Prior Request for Bids International 2,300,000.00 193,256.30 Signed 2020-04-21 2020-04-21 2020-04-26 2020-06-07 2019-10-11 2020-08-20 2020-04-27 2020-09-24 2020-07-24 2021-03-23 Teaching and Learning Envelope selected Districts in Zambia on the basis of a 3 years framework agreement ZM-MOGE-186831-GO-RFQ / Procurement of 512 Increasing Equitable Access Request for Single Stage - One IDA / 61360 Post Limited 9,000.00 9,320.74 Signed 2020-08-05 2019-11-04 2020-09-30 2019-12-16 2021-03-29 Suggestion Boxes for the ZEEP to Secondary Education Quotations Envelope Schools ZM-MOGE-183335-GO-RFB / SUPPLY AND DELIVERY OF GRADES 1,2,4 6,9,10 AND 11 TEXTBOOKS AND TEACHERS Under GUIDES (REVISED Improving the Quality of Single Stage - Two IDA / 61360 Prior Request for Bids Open - International 2,137,115.68 0.00 Implementati 2020-07-13 2020-09-21 2020-07-18 2020-12-29 2020-08-29 2021-04-29 2020-11-11 2020-12-16 2021-06-14 CURRICULUM) TO SELECTED Teaching and Learning Envelope on DISTRICTS IN ZAMBIA ON BASIS OF A 3 YEARS FRAMEWORK AGREEMENT BASIS ON LOT BY LOT BASIS ZM-MOGE-183343-GO-RFB Under / SUPPLY AND DELIVERY OF Increasing Equitable Access Single Stage - One IDA / 61360 Post Request for Bids Open - International 1,411,764.70 0.00 Implementati 2020-07-31 2020-10-16 2020-08-05 2021-02-10 2020-09-16 2021-01-15 2020-10-16 2021-04-07 2020-11-20 2021-05-19 LABORATORY EQUIPMENT to Secondary Education Envelope on AND REAGENTS ZM-MOGE-193596-GO-RFB Under / Supply and Delivery of Home Improving the Quality of Single Stage - One IDA / 61360 Post Request for Bids Open - National 418,200.00 0.00 Implementati 2020-09-18 2020-10-16 2020-09-23 2020-11-04 2020-12-03 2020-12-04 2021-02-09 2021-01-08 2021-07-07 Economics Equipment for 82 Teaching and Learning Envelope on ZEEP Schools ZM-MOGE-172553-GO-RFB / Supply and Delivery of Grades 1,2 and 4 Textbooks Improving the Quality of IDA / 61360 Prior Request for Bids 6,000,000.00 0.00 Canceled 2020-05-11 2020-05-11 2020-05-11 2020-05-11 2020-05-11 2020-05-11 and Teacher's Guides to Teaching and Learning Selected Districts in Zambia on Basis of 3 years Framework Agreement ZM-MOGE-233912-GO-RFB Under / Supply and Installation of Increasing Equitable Access Single Stage - One IDA / 61360 Post Request for Bids Open - International 350,162.16 0.00 Implementati 2021-04-27 2021-06-01 2021-05-10 2021-06-11 2021-06-21 2021-07-21 2021-08-25 2022-02-21 Solar Water Pumps to 82 ZEEP to Secondary Education Envelope on Scools Page 1 ZM-MOGE-233911-GO-RFB Under / Supply and Installation of Increasing Equitable Access Single Stage - One IDA / 61360 Post Request for Bids Open - International 1,680,459.77 0.00 Implementati 2021-05-04 2021-06-01 2021-05-16 2021-06-11 2021-06-27 2021-07-27 2021-08-31 2022-02-27 Solar Panels to Selected ZEEP to Secondary Education Envelope on Schools NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Enhancing Planning, ZM-MOGE-204292-NC-RFP / Management and Monitoring Request for Single Stage - Two IDA / 61360 Post Open - National 60,000.00 0.00 Canceled 2020-11-11 2021-01-27 2021-01-27 2020-11-16 2021-04-07 2021-07-25 2023-01-16 Procurement of Office Space and Evaluation Capacity, and Proposals Envelope Project Coordination Enhancing institutional Under ZM-MOGE-232696-NC-RFQ Request for Single Stage - One IDA / 61360 capacity for implementation Post Open - National 35,714.29 0.00 Implementati 2021-05-17 2021-06-11 2021-07-12 2022-01-08 / Procurement of Office Space Quotations Envelope of safe school program on ZM-MOGE-234313-NC-RFQ Pending Increasing Equitable Access / Procurement of Helpline IDA / 61360 Post Direct Selection Direct 95,238.10 0.00 Implementati 2021-05-20 2021-05-25 2021-08-01 2022-01-28 to Secondary Education Phone Services on CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZM-MOGE-74751-CS-CQS / Enhancing Planning, Procurement of Consultancy Management and Monitoring Least Cost IDA / 61360 Post Open - National 250,000.00 0.00 Canceled 2018-10-04 2018-10-25 2018-12-08 2019-01-05 2019-02-04 2019-03-11 2019-04-15 2019-10-12 Services for an Independent and Evaluation Capacity, and Selection Verification Agency. Project Coordination ZM-MOGE-08 / Procure Enhancing Planning, Consultancy services for the Consultant Management and Monitoring development of the IDA / 61360 Post Qualification Open - National 31,552.94 0.00 Canceled 2018-06-15 2018-07-06 2018-08-19 2018-09-18 2018-10-23 2019-04-21 and Evaluation Capacity, and Monitoring & Evaluation Selection Project Coordination Project Sub System. ZM-MOGE-81154-CS-CQS / Enhancing Planning, Consultant Consultancy Services for Management and Monitoring Under IDA / 61360 Post Qualification Limited 250,000.00 0.00 2018-10-10 2018-08-01 2018-10-24 2018-11-23 2018-11-23 2019-01-11 2018-12-28 2019-06-26 Independent Verification and Evaluation Capacity, and Implementation Selection Agent (IVA) Project Coordination ZM-MOGE-102110-CS-CQS / Enhancing Planning, Consultant Consultancy Services for the Management and Monitoring Under IDA / 61360 Post Qualification Open - National 50,000.00 0.00 2019-02-25 2019-04-10 2019-03-18 2019-08-26 2019-05-01 2019-08-26 2019-05-31 2019-11-08 2019-07-05 2020-01-01 Development of a and Evaluation Capacity, and Implementation Selection Communication Strategy Project Coordination ZM-MOGE-117563-CS-LCS / Consultancy Services for the Third-party Agency of Construction Quality Review. The consulting services ("the Increasing Equitable Access Least Cost Under Services") include the IDA / 61360 Post Open - National 175,000.00 0.00 2019-06-18 2019-06-18 2019-07-09 2019-10-11 2019-08-22 2019-10-11 2019-09-19 2019-09-09 2019-10-19 2019-09-09 2019-11-23 2019-10-11 2019-12-28 2020-06-25 to Secondary Education Selection Implementation reviewing of the quality of construction and its compliance with the drawings and Technical Specifications and ESMF ZM-MOGE-193584-CS-CQS / Consultancy to Develop a Project Implementation Consultant Improving the Quality of Manual (PIM) For the Zambia IDA / 61360 Post Qualification Limited 12,500.00 0.00 Canceled 2020-09-11 2020-11-20 2020-09-25 2020-10-25 2020-11-29 2021-05-28 Teaching and Learning Education Enhancement Selection Project Additional Financing (ZEEP-AF) INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZM-MOGE-04 / Procure Enhancing Planning, Consultancy services for Management and Monitoring IDA / 61360 Post Direct Selection Direct 14,705.88 0.00 Canceled 2018-06-15 2018-08-31 2018-06-25 2018-08-29 2019-02-25 development of and Evaluation Capacity, and Communication Strategy Project Coordination Enhancing Planning, ZM-MOGE-15 / Procurement Management and Monitoring Consultant services for IDA / 61360 Prior Direct Selection Direct 50,000.00 0.00 Canceled 2018-06-02 2018-06-12 2018-08-16 2019-02-12 and Evaluation Capacity, and Component 3 Coordinator Project Coordination Enhancing Planning, ZM-MOGE-16 / Procurement Management and Monitoring Consultant services for IDA / 61360 Prior Direct Selection Direct 50,000.00 0.00 Canceled 2018-06-02 2018-06-12 2018-08-16 2019-02-12 and Evaluation Capacity, and Communication Officer Project Coordination ZM-MOGE-77552-CS-CDS / Consultancy for the Enhancing Planning, development of Monitoring & Management and Monitoring Under IDA / 61360 Post Direct Selection Direct 184,552.94 0.00 2018-10-03 2018-09-27 2018-10-13 2018-11-28 2018-12-17 2019-06-15 Evaluation Plan and Project and Evaluation Capacity, and Implementation Management Information Project Coordination System ZM-MOGE-81026-CS-CDS / Enhancing Planning, Consultancy Services for Management and Monitoring IDA / 61360 Post Direct Selection Direct 250,000.00 0.00 Canceled 2018-10-08 2018-10-18 2018-12-22 2019-06-20 Independent Verification and Evaluation Capacity, and Agent (IVA) Project Coordination Page 2 ZM-MOGE-130526-CS-INDV / CONSULTANCY SERVICES FOR THE DEVELOPMENT OF A PROJECT PROCUREMENT STRATEGY FOR DEVELOPMENT Enhancing Planning, Individual (PPSD), PROCUREMENT PLAN Management and Monitoring Under IDA / 61360 Post Consultant Limited 7,000.00 0.00 2019-09-04 2019-09-09 2019-09-09 2019-10-11 2019-09-30 2019-11-14 2019-11-04 2020-05-02 AND GENERAL PROCUREMENT and Evaluation Capacity, and Implementation Selection NOTICE FOR THE ADDITIONAL Project Coordination FINANCING FOR THE “ZAMBIA EDUCATION ENHANCEMENT PROJECT - P170513” ZM-MOGE-233753-CS-INDV / Consultancy Services to Develop a Project Individual Implementation Manual (PIM) Improving the Quality of IDA / 61360 Post Consultant Limited 12,500.00 0.00 Under Review 2021-05-12 2021-05-15 2021-05-17 2021-06-07 2021-07-12 2022-01-08 for the Zambia Education Teaching and Learning Selection Enhancement Project Additional Financing (ZEEP- AF) ZM-MOGE-183340-CS-CDS / Enhancing Planning, CONSULTANCY SERVICES FOR Management and Monitoring IDA / 61360 Prior Direct Selection Direct 96,000.00 0.00 Canceled 2020-07-13 2021-02-08 2020-07-23 2020-07-01 2020-09-26 2021-03-25 DEVELOPING A BOOK and Evaluation Capacity, and TRACKING SYSTEM Project Coordination ZM-MOGE-234061-CS-CDS / Enhancing Planning, Consultancy Services for the Management and Monitoring Under IDA / 61360 Post Direct Selection Direct 300,000.00 0.00 2020-07-13 2021-05-15 2020-07-23 2021-06-01 2020-09-26 2021-03-25 Development of a Book and Evaluation Capacity, and Implementation Tracking System Project Coordination Enhancing Planning, Individual IC 042021 / Hiring of Management and Monitoring IDA / 61360 Post Consultant Open 89,910.00 0.00 Under Review 2021-05-14 2021-05-21 2021-07-02 2021-07-23 2021-08-27 2022-02-23 Procurement Specialist and Evaluation Capacity, and Selection Project Coordination Page 3 Sample Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan: Original, December 2016; Revision 1 of Updated Procurement Plan, February 2017. 2. Date of General Procurement Notice: Not Applicable 3. Period covered by this procurement plan: From June 2017 to June 2018 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Comments Threshold US$ 1. NCB (Works) From US$ 15 million All 2. NCB (Goods and Non- From US$ 4 million All Consulting Services) 3. Shopping (Works) None None 4. Shopping (Goods and Non- None None Consulting Services) 5. Direct Contracting (Works) From US$ 15 million All Direct Contracting (Goods From US$ 4 million All and Non-Consulting Services) 6. Community Participation None None 2. Prequalification. Bidders for Not applicable shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.19 of the Guidelines: The Operations Manual describes the methods and procedures applicable to the Community Participation under CDD Component and Subprojects. 4. Reference to (if any) Project Operational/Procurement Manual: The Operations Manual issued by the Alternative Agriculture Center of the North of Minas Gerais State (Project Implementation Unit) describes the methods and procedures applicable to all procurement of goods, July 9, 2010 works, non-consulting services and consulting services financed by the Grant Agreement # TF018765. 5. Any Other Special Procurement Arrangements: Not Applicable 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness (including those that are subject to retroactive financing and advanced procurement) 1 2 3 4 5 6 7 Ref. Descripti Estimat Packages Dome Review Comme No. on ed stic by Bank nts Cost Prefe (Prior/Pos US$ rence t) million (yes/ no) 1 Summary 0.18 1 No Post of the NCBs (Non- Consulting Services) 2 Summary 0.05 10 No Post of the Shoppings (Goods) 3 Summary 0.24 20 No Post of the Shoppings (Non- Consulting Services) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comments Threshold 1. Competitive Methods (Firms) From US$ 2 million All 2. Single Source Selection (Firms) From US$ 2 million All 3. Individual Consultant From US$ 400,000 All 4 Single Source Selection From US$ 400,000 All (Individuals) 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than USD 1,500,000 equivalent per contract, may comprise entirely of national consultants in July 9, 2010 accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: Not Applicable 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description Estimat Package Review Comment of ed s by Bank s Assignmen Cost (Prior / t US$ Post) million 1 Summary 0.01 3 Post IC of number of contracts that will be let under methods other than QCBS July 9, 2010 PROCUREMENT Brazil : BR DGM for Indigenous People and Traditional Communities PLAN General Information Country: Brazil Bank’s Approval Date of the Original Procurement Plan: 2016-12- 12 2021-05- Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P143492 GPN Date: 25 2017-06- Project Name: BR DGM for Indigenous People and Traditional Communities 23 Loan / Credit No: TF / 18765 Alternative Agriculture Center of the North of Minas Gerais State Executing Agency(ies): WORKS Procure Bid Evaluation Activity Reference No. Actual Draft Pre- Draft Bidding Specific Proposal Loan / Credit Market Procurement Prequalificati High SEA/SH ment Process Prequalification Bidding Documents Report and Contract / Description Component Review Type Method Amount qualification Document / Procurement Notice Submission / Signed Contract No. Approach Process on (Y/N) Risk Docume Status Evaluation Report as Issued Recommendation Completion (US$) Documents Justification / Invitation Opening / Minutes nt Type for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planne Actu d al SUB 55-12 / CT55.12 Patio para a instalacao do conjunto modular com 70 metros quadrado em piso Component 1: Sustainable Pending Request for Single Stage - One 2017-06- 2017-07- 2017- de concreto. Base estrutural TF / 18765 and Adaptive Community Post Limited 0.00 Implemen Quotations Envelope 27 25 10-23 com cobertura baneiro Initiatives tation vestuario em alvenaria instalacao de esgoto sanitario e cercamento do perimetro SUB 61-17 / CQ61.17 Contratação de serviços de Component 1: Sustainable 2019- Request for Single Stage - One Complete 2017-07- 2019-04- 2017-07- 2019-05- 2017- reforma do prédio onde sera TF / 18765 and Adaptive Community Post Limited 8,847.95 11- Quotations Envelope d 07 17 31 17 10-29 instalado a unidade de Initiatives 27 beneficiamento SUB 212-4 / Serviço de Component 1: Sustainable 2020- Obra civil de construção da Request for Single Stage - One 13,219.5 Complete 2019-11- 2019-11- 2019-12- 2020-01- 2020- TF / 18765 and Adaptive Community Post Limited 05- cozinha comunitária, Quotations Envelope 6 d 24 26 14 02 03-13 Initiatives 15 incluindo mão de obra e materiais SUB 166 SC 11/2019 / Serviço de obra civil de Component 1: Sustainable Under Request for Single Stage - One 22,457.9 2019-12- 2021-01- 2020-01- 2020- construção da Cozinha TF / 18765 and Adaptive Community Post Limited Implemen Quotations Envelope 2 14 21 03 04-02 Comunitária, incluindo mão Initiatives tation de obra e materiais GOODS Activity Reference No. Actual Draft Pre- Draft Bidding Specific Proposal Bid Evaluation Loan / Credit Market Procurement Prequalificati Process Prequalification Bidding Documents Contract / Description Component Review Type Method Amount qualification Document / Procurement Notice Submission / Report and Signed Contract No. Approach Process on (Y/N) Status Evaluation Report as Issued Completion (US$) Documents Justification / Invitation Opening / Minutes Recommendation Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned for Award Actual Planned Actual Planned Actual BR-CAA-3305-GO-RFQ / aquisicao de quarenta e um tablets para uso dos Component 1: Sustainable Pending Request for Single Stage - One 2016-12- 2017-01- 2017-03- subprojetos para TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 21 13 14 acompanhamento e Initiatives ation monitoramento dos subprojetos BR-CAA-3264-GO-RFQ / aquisicao de televisor smart Component 3: Project Pending tv sessenta e cinco Request for Single Stage - One 2017-02- 2017-03- 2017-05- TF / 18765 Management, Monitoring Post Limited 0.00 Implement polegadas e curva para Quotations Envelope 13 06 05 and Evaluation ation transmissao audio visual para estruturacao da sala reunioes projeto BR-CAA-4664-GO-RFQ / aquisicao de material pedagogico tipo bloco e Component 3: Project Pending papel e caneta e papel sufite Request for Single Stage - One 2015-12- 2015-12- 2016-02- TF / 18765 Management, Monitoring Post Limited 0.00 Implement para impressao e pasta Quotations Envelope 01 23 21 and Evaluation ation papel para realizar uma reuniao anual e duas extraordinaria do comite gestor nacional BR-CAA-4669-GO-RFQ / aquisicao de material pedagogico tipo canetas e Component 1: Sustainable Pending Request for Single Stage - One 2016-01- 2016-02- 2016-04- papel para realizacao de TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 11 03 03 tres oficinas de divulgacao e Initiatives ation duas de elaboracao e tres seminarios BR-CAA-4663-GO-RFQ / aquisicao de seis computadores para equipe chave e assessora do Component 3: Project projeto e uma impressora Request for Single Stage - One 2016-02- 2016-02- 2016-04- 2016-04- 2016-06- TF / 18765 Management, Monitoring Post Limited 5,396.72 Signed multifuncional para o Quotations Envelope 18 08 08 08 07 and Evaluation escritorio do projeto situado em brasilia para desenvolvimento das atividades BR-CAA-4666-GO-RFQ / aquisicao de vinte tablets para uso da equipe chave de Component 3: Project apoio e estagiarios durante Request for Single Stage - One 2016-06- 2016-06- 2016-06- 2016-06- 2016-08- 2016-08- TF / 18765 Management, Monitoring Post Limited 6,367.03 Completed monitoramento do projeto e Quotations Envelope 03 03 20 20 19 20 and Evaluation aquiscao de cabo para equipamentos audivisuais durante reunioes do projeto BR-CAA-5585-GO-RFQ / Aquisição de material pedagógico para duas oficinas de elaboração de Component 1: Sustainable projetos, tipo: pincel, Request for Single Stage - One 2017-01- 2017-01- 2017-01- 2017-01- 2017-01- 2017-01- TF / 18765 and Adaptive Community Post Limited 437.58 Completed hidrocor, canetas Quotations Envelope 13 17 17 18 22 20 Initiatives hidrográficas coloridas grossas, kits de tintas com pinceis, papel tipo oficio, rolo de papel kraft, rolo de fita adesiva, rolo de barbante, etc BR-CAA-3252-GO-RFQ / Aquisição de 24 poltronas com estrutura de assento e encosto em forma de Component 3: Project Pending Request for Single Stage - One 2017-06- 2017-07- 2017-09- concha inteiriça resistente a TF / 18765 Management, Monitoring Post Limited 0.00 Implement Quotations Envelope 27 16 14 120kg, sem braço, base em and Evaluation ation aço, revestimento de encosto e assento em couro sintético para sala reuniões DGM. BR-CAA-17780-GO-RFQ / Serviço de confecção de Mesa de reuniões em MDF medindo 2,75m x 1,40 com Component 3: Project Pending fiação embutida no centro Request for Single Stage - One 2017-06- 2017-07- 2017-09- TF / 18765 Management, Monitoring Post Limited 0.00 Implement para acesso de Quotations Envelope 28 24 22 and Evaluation ation computadores e eletrônicos E Aparador medindo 1,10 por 30cm de profundidade em MDF para a sala reuniões DGM. BR-CAA-3324-GO-RFQ / Aquisição de lousa de vidro jateado e medindo dois metros de comprimento por Component 3: Project Pending um e dez metros de largura Request for Single Stage - One 2017-06- 2017-07- 2017-09- TF / 18765 Management, Monitoring Post Open - National 0.00 Implement com todos os acessorios Quotations Envelope 30 18 16 and Evaluation ation para fixacao em parede e aquisicao de porta de vidro e aquisicao de vidro temperados para sala reunioes BR-CAA-3317-GO-RFQ / Aquisição de ar Component 3: Project Pending condicionado teto split com Request for Single Stage - One 2017-07- 2017-07- 2017-10- TF / 18765 Management, Monitoring Post Limited 0.00 Implement potencia trinta e seis mil Quotations Envelope 07 27 25 and Evaluation ation btus para estruturacao da sala reunioes projeto SUB 4-8 / CT4.8. Aquisição Component 1: Sustainable Request for Single Stage - One 2017-07- 2018-04- 2017-08- 2018-05- 2017-08- 2018-06- de kits de materiais TF / 18765 and Adaptive Community Post Limited 205.74 Completed Quotations Envelope 13 18 03 17 13 16 didáticos. Initiatives SUB 16-1 / CQ16-1 Aquisição de mudas Component 1: Sustainable Pending Request for Single Stage - One 2017-12- 2018-01- 2018-03- espécies nativas do cerrado TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 20 13 24 para reflorestamento da Initiatives ation área de vinte nascentes. SUB 16-3 / CQ16-3 Aquisição de um veiculo para fiscalização de áreas Component 1: Sustainable Request for Single Stage - One 2017-06- 2018-05- 2017-07- 2018-06- 2017-10- 2018-09- de nascentes isoladas e TF / 18765 and Adaptive Community Post Limited 9,999.02 Completed Quotations Envelope 29 08 23 08 01 04 recuperadas mobilização Initiatives atividades e gestão operacional do subprojeto SUB 16-10 / CQ16-10 Aquisição de 1920 estacas Component 1: Sustainable Request for Single Stage - One 2017-06- 2017-10- 2017-07- 2017-10- 2017-08- 2017-11- de eucalipto tratado para o TF / 18765 and Adaptive Community Post Limited 7,100.65 Completed Quotations Envelope 30 19 24 30 08 28 isolamento de vinte Initiatives nascentes na comunidade. Component 1: Sustainable Pending SUB 25-4 / CQ25.4 Request for Single Stage - One 2017-07- 2017-08- 2017-10- TF / 18765 and Adaptive Community Post Limited 0.00 Implement Aquisição de um veiculo Quotations Envelope 02 09 08 Initiatives ation SUB 25-7 / CQ25.7 Component 1: Sustainable Pending Request for Single Stage - One 2017-07- 2017-07- 2018-01- Aquisição de materiais de TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 06 28 24 expediente tela de projeção Initiatives ation pranchetas SUB 25-8 / CQ25.8 Component 1: Sustainable Pending Request for Single Stage - One 2017-06- 2017-07- 2017-09- Aquisição de uma câmera TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 24 28 06 fotográfica digital Initiatives ation SUB 25-9 / CQ25.9 Component 1: Sustainable Pending Request for Single Stage - One 2017-06- 2017-07- 2017-09- Aquisição de um notebook e TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 28 28 16 um data show Initiatives ation SUB 25-11 / CQ25.11 Component 1: Sustainable Pending Request for Single Stage - One 2018-01- 2018-01- 2018-02- Aquisição de postes de TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 02 24 23 eucalipto tratado para cerca Initiatives ation SUB 26-1 / CT26.1 Aquisição de gêneros alimentícios para as Component 1: Sustainable Pending atividade de proteção ao Request for Single Stage - One 2017-06- 2017-07- 2018-02- TF / 18765 and Adaptive Community Post Limited 0.00 Implement cerrado em Caceres Quotations Envelope 30 18 13 Initiatives ation acompanhamento de consultoria técnica para mapeamento e construção do viveiro de mudas SUB 2-8 / CT26.8 Component 1: Sustainable Request for Single Stage - One 2017-06- 2018-05- 2017-07- 2018-05- 2017-09- 2018-06- Aquisicao de maquina TF / 18765 and Adaptive Community Post Limited 359.97 Completed Quotations Envelope 24 29 18 29 01 28 fotografica Initiatives SUB 45-2 / CT45.2 Aquisicao de veiculo tipo Component 1: Sustainable pick up para coleta de Request for Single Stage - One 2017-06- 2018-01- 2017-07- 2018-02- 2017-09- 2018-03- TF / 18765 and Adaptive Community Post Limited 10,257.25 Completed materia prima escoamento Quotations Envelope 25 18 25 15 23 24 Initiatives da produção e apoio as atividades de campo capacitação e monitoramento SUB 45-6 / CT45.6 Component 1: Sustainable Pending Aquisicao de moveis para Request for Single Stage - One 2017-06- 2017-07- 2017-08- TF / 18765 and Adaptive Community Post Limited 0.00 Implement escritorio sendo estante de Quotations Envelope 27 24 23 Initiatives ation aco armário em aco cadeira e mesa SUB 45-17 / CT45.17 Component 1: Sustainable Pending Aquisicao de equipamento Request for Single Stage - One 2017-06- 2017-07- 2017-08- TF / 18765 and Adaptive Community Post Limited 0.00 Implement para a Unidade de Quotations Envelope 25 17 16 Initiatives ation Beneficiamento SUB 55-2 / CT55.2 Component 1: Sustainable Pending Request for Single Stage - One 2017-06- 2017-07- 2017-09- Aquisicao de um Triturador TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 25 26 04 Forrageiro Initiatives ation SUB 55-3 / CT55.3 Component 1: Sustainable Pending Aquisicao de uma balanca Request for Single Stage - One 2017-06- 2017-07- 2017-08- TF / 18765 and Adaptive Community Post Limited 0.00 Implement eletronica com capacidade Quotations Envelope 27 18 17 Initiatives ation de carga para 100 quilo SUB 55-7 / CT55.7 Component 1: Sustainable Pending Request for Single Stage - One 2017-06- 2017-07- 2017-08- Aquisicao de tres carrinhos TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 26 27 26 de mao para coleta de Initiatives ation frutos SUB 55-8 / CT55.8 Component 1: Sustainable Pending Request for Single Stage - One 2017-06- 2017-07- 2017-08- Aquisicao de duas estantes TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 27 17 21 metalicas em aco inox Initiatives ation SUB 55-10 / CT55.10 Component 1: Sustainable Pending Request for Single Stage - One 2017-06- 2017-07- 2017-08- Aquisicao de uma Panela em TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 30 18 07 aco inoxidavel de trinta Initiatives ation litros SUB 56-2 / CT56.2 Component 1: Sustainable Request for Single Stage - One 2017-07- 2018-03- 2017-07- 2018-03- 2017-08- 2018-04- Aquisição de um fogão TF / 18765 and Adaptive Community Post Limited 175.37 Completed Quotations Envelope 02 07 17 07 26 06 industrial de quatro bocas Initiatives SUB 56-3 / CT56.3 Aquisição de ferramentas Component 1: Sustainable Pending para recuperação de áreas Request for Single Stage - One 2017-12- 2018-01- 2018-02- TF / 18765 and Adaptive Community Post Limited 0.00 Implement degradadas como pá Quotations Envelope 10 08 12 Initiatives ation enxada carro de mão cavadeira entre outros Component 1: Sustainable SUB 56-4 / CT56.4 Request for Single Stage - One 2017-07- 2018-05- 2017-07- 2018-05- 2017-08- 2018-06- TF / 18765 and Adaptive Community Post Limited 260.10 Completed Aquisição de um notebook Quotations Envelope 01 24 20 24 29 23 Initiatives SUB 56-7 / CT56.7 Aquisição de mudas para Component 1: Sustainable Pending Request for Single Stage - One 2017-12- 2018-01- 2018-02- recuperação de áreas TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 12 08 17 degradadas nas margens de Initiatives ation córregos com sistemas agroflorestais SUB 56-8 / CT56.8 Component 1: Sustainable Request for Single Stage - One 2017-07- 2017-11- 2017-07- 2017-11- 2017-08- 2017-12- Aquisicao de um portao de TF / 18765 and Adaptive Community Post Limited 205.67 Completed Quotations Envelope 01 14 18 28 17 22 correr com trilhos Initiatives SUB 56-9 / CT56.9 Component 1: Sustainable Aquisicao de materiais de Request for Single Stage - One 2017-07- 2017-11- 2017-07- 2017-11- 2017-08- 2017-12- TF / 18765 and Adaptive Community Post Limited 2,384.99 Signed construcao como sacos de Quotations Envelope 02 14 20 28 19 13 Initiatives cimento tijolos telhas outros necessarios SUB 56-16 / CT56.16 Aquisição de materiais pedagógicos para oito oficinas comunitária de Component 1: Sustainable Pending capacitação mapeamento e Request for Single Stage - One 2017-07- 2017-07- 2017-08- TF / 18765 and Adaptive Community Post Limited 0.00 Implement planejamento participativo e Quotations Envelope 03 28 27 Initiatives ation uma oficina de capacitação sobre recuperação e proteção de microbacias e construção de plano de trabalho SUB 61-4 / CQ61.4 Aquisição de moveis para Component 1: Sustainable escritório como quatro Request for Single Stage - One 2017-07- 2017-08- 2017-09- TF / 18765 and Adaptive Community Post Limited 0.00 Canceled armários um arquivo vinte Quotations Envelope 21 15 24 Initiatives e uma cadeiras uma estrutura com três cadeiras doze mesas SUB 61-5 / CQ61.5 Component 1: Sustainable Request for Single Stage - One 2017-07- 2017-08- 2017-09- Aquisição de uma estufa de TF / 18765 and Adaptive Community Post Limited 0.00 Canceled Quotations Envelope 25 18 27 secagem Initiatives SUB 61-8 / CQ61.8 Component 1: Sustainable Request for Single Stage - One 2017-07- 2017-08- 2017-09- Aquisicao de um Forno TF / 18765 and Adaptive Community Post Limited 0.00 Canceled Quotations Envelope 28 21 30 Turbo com dez bandejas Initiatives SUB 61-10 / CQ61.10 Component 1: Sustainable Request for Single Stage - One 2017-08- 2017-08- 2017-09- Aquisição de doze facas de TF / 18765 and Adaptive Community Post Limited 0.00 Canceled Quotations Envelope 01 23 22 inox Initiatives SUB 61-12 / CQ61.12 Aquisição de dez computadores um Notebook uma caixa de som para Component 1: Sustainable computador uma Request for Single Stage - One 2017-07- 2019-05- 2017-07- 2019-06- 2017-09- 2019-06- TF / 18765 and Adaptive Community Post Limited 7,443.53 Completed impressora um projetor Quotations Envelope 08 30 31 13 29 14 Initiatives multimídia cinco estabilizadores um modem cartuchos de tinta para impressora e uma calculadora eletrônica SUB 61-20 / CQ61.20 Aquisicão de gêneros alimentícios dos Component 1: Sustainable Pending Request for Single Stage - One 2017-09- 2017-10- 2017-12- comunitários para a TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 19 16 05 capacitação da valoração da Initiatives ation produção artesanal quilombola existente na Comunidade SUB 71-1 / CT71.1 Component 1: Sustainable Request for Single Stage - One 2017-07- 2017-07- 2017-09- Aquisição de um ônibus TF / 18765 and Adaptive Community Post Limited 0.00 Canceled Quotations Envelope 07 31 14 usado de linha Initiatives SUB 75-1 / CQ75.1 Component 1: Sustainable Aquisição de equipamentos Request for Single Stage - One 2017-07- 2018-01- 2017-07- 2018-01- 2017-09- 2018-02- TF / 18765 and Adaptive Community Post Limited 1,214.25 Completed de informatica sendo Quotations Envelope 07 10 31 10 09 09 Initiatives Projetor multimídia e Notebook SUB 90-5 / CT90.5 Component 1: Sustainable Request for Single Stage - One 2017-07- 2019-10- 2017-07- 2019-10- 2017-09- 2019-11- Aquisição de embalagens de TF / 18765 and Adaptive Community Post Limited 3,706.64 Completed Quotations Envelope 08 03 28 16 11 11 conteúdo inferior ou igual a Initiatives um quilo Page 1 SUB 99-1 / CT99.1 Component 1: Sustainable Aquisicao de materiais Request for Single Stage - One 2017-07- 2018-01- 2017-07- 2018-02- 2017-09- 2018-03- TF / 18765 and Adaptive Community Post Limited 1,318.66 Completed eletricos e hidraulicos para Quotations Envelope 07 18 28 07 01 08 Initiatives implantacao das unidades produtivas SUB 99-2 / CT99.2 Aquisição de materiais para Component 1: Sustainable Request for Single Stage - One 2017-07- 2018-01- 2017-07- 2018-02- 2017-09- 2018-03- infraestrutura para TF / 18765 and Adaptive Community Post Limited 26,237.06 Completed Quotations Envelope 09 18 28 06 11 08 implantação das unidades Initiatives produtivas SUB 99-3 / CT99.3 Aquisição de bens para Component 1: Sustainable implantação das unidades Request for Single Stage - One 2017-07- 2018-01- 2017-08- 2018-02- 2017-09- 2018-03- TF / 18765 and Adaptive Community Post Limited 372.93 Completed produtivas como bandejas Quotations Envelope 09 18 02 07 11 08 Initiatives de isopor bebedouros e comedouros para aves SUB 99-4 / CT99.4 Component 1: Sustainable Request for Single Stage - One 2017-07- 2018-01- 2017-08- 2018-02- 2017-09- 2018-03- Aquisição de bombas de TF / 18765 and Adaptive Community Post Limited 317.04 Completed Quotations Envelope 08 18 02 07 06 08 água submersa completa Initiatives novecentos w SUB 99-5 / CT99.5 Component 1: Sustainable Aquisição de materiais de Request for Single Stage - One 2017-07- 2018-05- 2017-08- 2018-05- 2017-09- 2018-06- TF / 18765 and Adaptive Community Post Limited 915.03 Completed construção para Quotations Envelope 10 09 04 24 08 23 Initiatives implantação das unidades produtivas SUB 99-6 / CT99.6 Component 1: Sustainable Request for Single Stage - One 2017-07- 2018-01- 2017-08- 2018-02- 2017-09- 2018-04- Aquisição de Caixas de água TF / 18765 and Adaptive Community Post Limited 1,687.86 Completed Quotations Envelope 13 18 02 07 01 06 de cinco mil litros Initiatives SUB 99-7 / CT99.7 Component 1: Sustainable Aquisição de materiais de Request for Single Stage - One 2017-07- 2018-01- 2017-08- 2018-02- 2017-10- 2018-03- TF / 18765 and Adaptive Community Post Limited 5,102.58 Completed madereira para implantação Quotations Envelope 12 18 03 07 02 08 Initiatives das unidades produtivas SUB 99-8 / CT99.8 Aquisicao de insumos para Component 1: Sustainable Pending Request for Single Stage - One 2017-07- 2017-08- 2017-08- as unidades produtivas TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 12 01 26 como Sacos de calcario Initiatives ation Substratos e Composto organico SUB 99-9 / CT99.9 Aquisicao de insumos para Component 1: Sustainable as unidades produtivas Request for Single Stage - One 2017-07- 2018-05- 2017-08- 2018-05- 2017-09- 2018-06- TF / 18765 and Adaptive Community Post Limited 490.24 Completed como Pacote de semente de Quotations Envelope 10 09 07 24 06 23 Initiatives hortalica Sacos sementes de milho grao crioulo e Sacos de milho grao SUB 99-10 / CT99.10 Aquisicao de animais para Component 1: Sustainable Request for Single Stage - One 2017-07- 2018-05- 2017-08- 2018-05- 2017-09- 2018-06- as unidades produtivas TF / 18765 and Adaptive Community Post Limited 620.21 Completed Quotations Envelope 14 09 07 24 06 25 como Galos reprodutores e Initiatives Galinhas caipira SUB 99-11 / CT99.11 Component 1: Sustainable Request for Single Stage - One 2017-07- 2018-05- 2017-08- 2018-05- 2017-09- 2018-06- Aquisicao de camera TF / 18765 and Adaptive Community Post Limited 825.48 Completed Quotations Envelope 16 22 07 22 16 21 fotografica profissional Initiatives SUB 99-12 / CT99.12 Component 1: Sustainable Pending Aquisicao de kit de material Request for Single Stage - One 2017-07- 2017-07- 2017-08- TF / 18765 and Adaptive Community Post Limited 0.00 Implement didatico para cursos oficinas Quotations Envelope 10 28 27 Initiatives ation e intercambios SUB 105-6 / CQ105.6 Aquisição de gêneros alimentícios comunitários em diversas comunidades Component 1: Sustainable Pending para os eventos Oficinas de 2017-07- 2017-07- 2017-08- 2018-07- TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Implement formação em direitos 19 24 05 31 Initiatives ation territoriais Oficinas de elaboração do plano de gestão territorial Encontro da juventude e Caravana quilombola SUB 105-7 / CQ105.7 Aquisição de materiais Component 1: Sustainable Request for Single Stage - One 2017-07- 2018-11- 2017-08- 2018-11- 2017-09- 2018-12- pedagógicos para a Oficina TF / 18765 and Adaptive Community Post Limited 1,402.58 Completed Quotations Envelope 17 14 07 22 01 21 de formação em direitos Initiatives territoriais SUB 105-8 / CQ105.8 Component 1: Sustainable Request for Single Stage - One 2017-07- 2018-04- 2017-08- 2018-04- 2017-09- 2018-04- Aquisição de quatro TF / 18765 and Adaptive Community Post Limited 1,665.16 Completed Quotations Envelope 16 09 04 09 08 24 maquinas fotográficas e Initiatives quatro GPS. SUB 109-3 / CT109.3 Component 1: Sustainable Pending Aquisição de materiais de Request for Single Stage - One 2017-07- 2017-08- 2017-12- TF / 18765 and Adaptive Community Post Limited 0.00 Implement construção para reforma do Quotations Envelope 20 07 05 Initiatives ation entreposto SUB 109-4 / CT109.4 Component 1: Sustainable Pending Aquisição de materiais de Request for Single Stage - One 2017-07- 2017-08- 2017-12- TF / 18765 and Adaptive Community Post Limited 0.00 Implement madeira para o telhado para Quotations Envelope 18 04 02 Initiatives ation reforma do entreposto SUB 109-6 / CT109.6 Component 1: Sustainable Pending Aquisição de estante Request for Single Stage - One 2017-09- 2017-10- 2017-11- TF / 18765 and Adaptive Community Post Limited 0.00 Implement modular metálica com seis Quotations Envelope 16 13 27 Initiatives ation prateleiras para o entreposto SUB 109-7 / CT109.7 Aquisição de forno turbo Component 1: Sustainable Pending Request for Single Stage - One 2017-09- 2017-10- 2017-12- lenha para panificação com TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 22 16 20 dez esteiras e controle de Initiatives ation temperatura para o entreposto SUB 109-9 / CT109.09 Aquisição de mesa em aço Component 1: Sustainable Pending Request for Single Stage - One 2017-09- 2017-10- 2017-11- inox com estrutura tubular TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 18 12 26 total em aço inox para o Initiatives ation entreposto SUB 109-10 / CT109.10 Component 1: Sustainable Pending Aquisição de carrinho tipo Request for Single Stage - One 2017-09- 2017-10- 2017-11- TF / 18765 and Adaptive Community Post Limited 0.00 Implement plataforma baixa em aço Quotations Envelope 13 06 10 Initiatives ation carbono para o entreposto SUB 109-11 / CT109.11 Aquisição de balança Component 1: Sustainable Pending Request for Single Stage - One 2017-09- 2017-10- 2017-11- eletrônica digital de TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 27 20 29 bancada capacidade trinta Initiatives ation quilos para o entreposto SUB 109-14 / CT109.14 Aquisição de refeições dos comunitários para Primeiro e Segundo encontro para Component 1: Sustainable Pending elaboração do plano de 2017-08- 2017-09- 2017-09- 2018-03- TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Implement comercialização Curso de 22 01 07 06 Initiatives ation boas praticas de beneficiamento e Encontro para construção dos acordos de boas praticas SUB 110-1 / CQ110.1 Aquisição de equipamentos para construção do viveiro e Component 1: Sustainable Request for Single Stage - One 2017-11- 2018-01- 2018-02- sala de armazenamento de TF / 18765 and Adaptive Community Post Limited 0.00 Canceled Quotations Envelope 24 16 25 sementes como Initiatives Pulverizadores Bomba plastica de cem litros SUB 110-5 / CQ110.5 Component 1: Sustainable Request for Single Stage - One 2017-09- 2017-10- 2017-11- Aquisição de caixas d água TF / 18765 and Adaptive Community Post Limited 0.00 Canceled Quotations Envelope 28 18 17 de dois mil litros Initiatives SUB 110-7 / CQ110.7 Component 1: Sustainable Aquisição de ship e Request for Single Stage - One 2017-07- 2017-08- 2017-10- TF / 18765 and Adaptive Community Post Limited 0.00 Canceled equipamentos para Quotations Envelope 26 21 20 Initiatives transmissão de dados SUB 110-8 / CQ110.8 Component 1: Sustainable Request for Single Stage - One 2017-11- 2017-12- 2018-01- Aquisição de armário, mesa TF / 18765 and Adaptive Community Post Limited 0.00 Canceled Quotations Envelope 22 13 27 e cadeira de escritório Initiatives SUB 110-9 / CQ110.9 Component 1: Sustainable Under Request for Single Stage - One 2017-11- 2020-07- 2017-12- 2018-02- Aquisição de carreta para TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 29 10 22 05 trator Initiatives ation SUB 110-10 / CQ110.10 Component 1: Sustainable Request for Single Stage - One 2017-09- 2018-01- 2017-10- 2018-02- 2017-11- 2018-02- Aquisição de cavadeira TF / 18765 and Adaptive Community Post Limited 90.13 Completed Quotations Envelope 20 25 16 07 20 23 articulada em aço Initiatives SUB 110-11 / CQ110.11 Aquisição de Notebook, Component 1: Sustainable Request for Single Stage - One 2017-07- 2018-04- 2017-08- 2018-04- 2017-09- 2018-05- impressora, maquina TF / 18765 and Adaptive Community Post Limited 1,338.22 Completed Quotations Envelope 25 24 18 24 27 24 fotográfica, Aparelho de GPS Initiatives e Cartuchos impressora SUB 110-12 / CQ110.12 Component 1: Sustainable Aquisição de geladeira para Request for Single Stage - One 2017-09- 2017-10- 2017-11- TF / 18765 and Adaptive Community Post Limited 0.00 Canceled viveiro e sala de Quotations Envelope 30 23 27 Initiatives armazenamento de sementes SUB 110-15 / CQ110.15 Component 1: Sustainable Request for Single Stage - One 2017-08- 2018-01- 2017-08- 2018-02- 2017-10- 2018-03- Aquisição de implemento TF / 18765 and Adaptive Community Post Limited 1,027.37 Completed Quotations Envelope 04 24 29 07 18 15 perfurador de solo Initiatives SUB 110-16 / CQ110.16 Component 1: Sustainable Request for Single Stage - One 2017-09- 2020-07- 2017-10- 2020-07- 2017-12- 2020-10- Aquisição de tanque TF / 18765 and Adaptive Community Post Limited 1,039.50 Completed Quotations Envelope 19 15 13 27 02 01 reboque Initiatives SUB 110-17 / CQ110.17 Component 1: Sustainable Request for Single Stage - One 2017-11- 2017-12- 2018-01- Aquisição de tambores de TF / 18765 and Adaptive Community Post Limited 0.00 Canceled Quotations Envelope 22 18 27 plastico de duzentos litros Initiatives SUB 110-18 / CQ110.18 Component 1: Sustainable Request for Single Stage - One 2017-09- 2017-10- 2017-11- Aquisição de catraca para TF / 18765 and Adaptive Community Post Limited 0.00 Canceled Quotations Envelope 23 16 20 esticar arame Initiatives SUB 110-26 / CQ110.26 Component 1: Sustainable Request for Single Stage - One 2017-08- 2017-08- 2017-10- Aquisição de materiais TF / 18765 and Adaptive Community Post Limited 0.00 Canceled Quotations Envelope 01 24 23 expediente Initiatives SUB 110-28 / CQ110.28 Component 1: Sustainable Aquisição de gênero 2017-11- 2017-12- 2018-01- 2018-09- TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled alimentícios de 28 08 02 09 Initiatives comunitários para realizar capacitações SUB 116-7 / CT116.7 Aquisição de materiais de Component 1: Sustainable Request for Single Stage - One 2017-08- 2018-12- 2017-08- 2018-12- 2017-10- 2019-01- ferragens para implantação TF / 18765 and Adaptive Community Post Limited 3,335.96 Completed Quotations Envelope 05 11 28 17 02 28 de unidade de Initiatives processamento e hortas SUB 116-8 / CT116.8 Component 1: Sustainable Aquisição de sementes Request for Single Stage - One 2017-08- 2018-12- 2017-08- 2018-12- 2017-09- 2018-12- TF / 18765 and Adaptive Community Post Limited 534.83 Completed diversas para Implantação Quotations Envelope 01 11 21 18 25 17 Initiatives de Hortas de Quintais SUB 116-10 / CT116.10 Aquisição de estercos de Component 1: Sustainable Pending gado para implantação de 2017-07- 2017-08- 2017-08- 2017-09- TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Implement hortas reflorestamento e 25 04 14 23 Initiatives ation enriquecimento de agroquintais SUB 116-14 / CT116.14 Component 1: Sustainable Aquisição de calcário para Request for Single Stage - One 2017-08- 2019-01- 2017-08- 2019-01- 2017-09- 2019-01- TF / 18765 and Adaptive Community Post Limited 17.88 Completed enriquecimento de Quotations Envelope 04 04 28 09 22 30 Initiatives Agroquintais SUB 116-15 / CT116.15 Component 1: Sustainable Pending Request for Single Stage - One 2017-08- 2017-08- 2017-10- Aquisição de câmera TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 07 24 08 fotográfica Initiatives ation SUB 116-17 / CT116.17 Component 1: Sustainable Pending Aquisição de veiculo Request for Single Stage - One 2017-08- 2017-08- 2017-10- TF / 18765 and Adaptive Community Post Limited 0.00 Implement motocicleta cento e Quotations Envelope 01 25 09 Initiatives ation cinquenta cilindradas SUB 116-18 / CT116.18 Component 1: Sustainable Pending Request for Single Stage - One 2017-08- 2017-08- 2017-10- Aquisição de kit EPI para TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 10 29 03 coleta de lixo Initiatives ation SUB 116-21 / CT116.21 Component 1: Sustainable Pending Request for Single Stage - One 2017-08- 2017-08- 2017-10- Aquisição de dez kits de TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 03 23 02 material didático para Initiatives ation eventos SUB 130-1 / CT130.1 Component 1: Sustainable Pending Aquisição de matérias Request for Single Stage - One 2017-08- 2017-08- 2017-09- TF / 18765 and Adaptive Community Post Limited 0.00 Implement primas para beneficiamento Quotations Envelope 01 21 25 Initiatives ation do Jatobá Pequi e Baru SUB 130-3 / CT130.3 Component 1: Sustainable Aquisição de embalagens de Request for Single Stage - One 2017-07- 2018-12- 2017-08- 2018-12- 2017-09- 2019-01- TF / 18765 and Adaptive Community Post Limited 1,458.51 Completed vidraria para Jatobá Baru e Quotations Envelope 31 11 18 18 27 18 Initiatives Pequi SUB 130-4 / CT130.4 Component 1: Sustainable Under Request for Single Stage - One 2017-07- 2018-05- 2017-08- 2017-10- Aquisição de empacotadeira TF / 18765 and Adaptive Community Post Limited 12,713.30 Implement Quotations Envelope 28 21 18 02 a Vácuo. Initiatives ation SUB 3-3 / Aquisição de equipamentos de Component 1: Sustainable Request for Single Stage - One 2017-08- 2018-06- 2017-09- 2018-06- 2017-11- 2018-07- informática: notebook, TF / 18765 and Adaptive Community Post Limited 2,057.41 Completed Quotations Envelope 14 05 04 05 03 05 projeto multimídia, câmera Initiatives fotográfica, câmera filmadora. SUB 3-4 / Aquisição de Component 1: Sustainable Request for Single Stage - One 2017-08- 2017-08- 2017-09- utensílios de copa e TF / 18765 and Adaptive Community Post Limited 0.00 Canceled Quotations Envelope 09 25 25 cozinha. Initiatives SUB 3-5 / Aquisição de Component 1: Sustainable ferramentas agrícolas Request for Single Stage - One 2017-08- 2018-07- 2017-09- 2018-09- 2017-10- 2018-10- TF / 18765 and Adaptive Community Post Limited 1,960.99 Completed manual (enxada, enxadão, Quotations Envelope 16 25 06 03 13 03 Initiatives machado, cavadeira, facão, etc). Component 1: Sustainable SUB 3-6 / Aquisição de Request for Single Stage - One 2017-09- 2017-10- 2018-01- TF / 18765 and Adaptive Community Post Limited 0.00 Canceled gêneros alimentícios. Quotations Envelope 05 11 11 Initiatives SUB 3-7 / Aquisição de kit Request for Single Stage - One 2017-08- 2017-08- 2017-10- TF / 18765 Post Limited 0.00 Canceled de material pedagógico. Quotations Envelope 11 28 27 Component 1: Sustainable SUB 3-8 / Aquisição de 20 Request for Single Stage - One 2017-08- 2017-09- 2017-10- TF / 18765 and Adaptive Community Post Limited 0.00 Canceled litros de graxa lubrificante Quotations Envelope 18 04 16 Initiatives Component 1: Sustainable SUB 3-9 / Aquisição de Request for Single Stage - One 2017-08- 2019-12- 2017-09- 2019-12- 2018-01- 2020-01- TF / 18765 and Adaptive Community Post Limited 11,540.78 Completed 4.000 mudas. Quotations Envelope 23 05 28 23 08 22 Initiatives Component 1: Sustainable SUB 47-3 / Aquisição de Request for Single Stage - One 2017-08- 2018-02- 2017-08- 2018-02- 2017-09- 2018-03- TF / 18765 and Adaptive Community Post Limited 424.04 Completed projetor multimídia Quotations Envelope 02 19 16 20 15 22 Initiatives Component 1: Sustainable SUB 47-4 / Aquisição de Request for Single Stage - One 2018-02- 2018-02- 2018-04- 2018-02- 2018-05- 2018-03- TF / 18765 and Adaptive Community Post Limited 321.32 Completed fogão a gás, 4 bocas Quotations Envelope 23 19 02 20 14 21 Initiatives SUB 47-6 / Aquisição de materiais de construção Component 1: Sustainable Request for Single Stage - One 2017-08- 2018-08- 2017-10- 2018-09- 2017-11- 2018-10- para reforma da unidade de TF / 18765 and Adaptive Community Post Limited 8,474.42 Completed Quotations Envelope 28 20 02 24 13 24 beneficiamento de polpas Initiatives (areia, cimento, pedras, etc) Component 1: Sustainable SUB 74-12 / Aquisição de Request for Single Stage - One 2017-08- 2019-07- 2017-08- 2019-07- 2017-12- 2019-08- TF / 18765 and Adaptive Community Post Limited 834.65 Completed gêneros alimentícios Quotations Envelope 07 11 21 17 18 09 Initiatives Component 1: Sustainable SUB 28-10 / Aquisição de Request for Single Stage - One 2018-02- 2018-03- 2019-01- TF / 18765 and Adaptive Community Post Limited 0.00 Canceled gêneros alimentícios Quotations Envelope 09 12 08 Initiatives SUB 28-11 / Aquisição de Component 1: Sustainable Request for Single Stage - One 2017-09- 2018-02- 2017-09- 2018-03- 2018-07- 2018-04- mudas para instalação de TF / 18765 and Adaptive Community Post Limited 18,006.29 Completed Quotations Envelope 04 20 19 26 16 24 campos de frutíferas Initiatives Component 1: Sustainable SUB 113-10 / Aquisição de Request for Single Stage - One 2017-09- 2019-06- 2017-09- 2019-06- 2017-11- 2019-06- TF / 18765 and Adaptive Community Post Limited 1,853.70 Completed kits para apicultura. Quotations Envelope 12 03 29 18 30 28 Initiatives SUB 113-11 / Aquisição de Component 1: Sustainable Pending Request for Single Stage - One 2017-09- 2017-10- 2017-11- Kit de ferramentas para TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 15 04 03 montagem de colméias Initiatives ation SUB 113-12 / Aquisição de kit de ferramentas para Component 1: Sustainable Request for Single Stage - One 2017-09- 2019-06- 2017-10- 2019-06- 2017-12- 2019-06- construção de cercas e TF / 18765 and Adaptive Community Post Limited 2,720.03 Completed Quotations Envelope 18 07 06 18 06 28 preparação de leitos para Initiatives plantio de mudas SUB 113-13 / Aquisição de Component 1: Sustainable Pending Request for Single Stage - One 2017-09- 2017-10- 2017-11- 2 kits para instalação de TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 20 06 28 viveiros comunitários Initiatives ation Component 1: Sustainable SUB 113-14 / Aquisição de Request for Single Stage - One 2018-02- 2019-03- 2018-03- 2019-03- 2018-05- 2019-04- TF / 18765 and Adaptive Community Post Limited 2,675.68 Completed materiais de irrigação. Quotations Envelope 14 08 16 25 18 15 Initiatives SUB 113-16 / Aquisição de Component 1: Sustainable Pending Request for Single Stage - One 2017-12- 2018-01- 2018-06- 1.000 mudas de espécies da TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 05 05 06 região Initiatives ation Page 2 SUB 113-17 / Aquisição de Component 1: Sustainable Pending kit de materiais para Oficina Request for Single Stage - One 2018-03- 2018-04- 2018-05- TF / 18765 and Adaptive Community Post Limited 0.00 Implement de Transferência de saberes Quotations Envelope 01 02 14 Initiatives ation entre anciões e jovens. Component 1: Sustainable SUB 113-18 / Aquisição de Request for Single Stage - One 2017-09- 2019-09- 2017-09- 2019-09- 2018-12- 2019-09- TF / 18765 and Adaptive Community Post Limited 445.91 Completed gêneros alimentícios Quotations Envelope 11 12 29 16 25 17 Initiatives SUB 120-10 / Aquisição de Barco em alumínio com 6 Component 1: Sustainable metros de comprimento Request for Single Stage - One 2017-09- 2017-11- 2017-10- 2017-12- 2017-12- 2018-01- TF / 18765 and Adaptive Community Post Limited 1,948.43 Completed com capacidade para Quotations Envelope 15 28 03 15 04 15 Initiatives receber motores de 30 a 40 hp de potência. SUB 120-11 / Aquisição de Component 1: Sustainable Request for Single Stage - One 2017-09- 2017-11- 2017-10- 2017-12- 2017-12- 2018-02- motor de popa de 40hp de TF / 18765 and Adaptive Community Post Limited 3,967.92 Completed Quotations Envelope 18 28 05 20 05 19 potência. Initiatives SUB 120-12 / Aquisição de Component 1: Sustainable Pending Request for Single Stage - One 2017-09- 2017-10- 2017-11- 10 kits de equipamentos de TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 20 09 07 proteção individual Initiatives ation Component 1: Sustainable SUB 120-13 / Aquisição de Request for Single Stage - One 2017-11- 2018-07- 2017-11- 2018-08- 2017-12- 2018-09- TF / 18765 and Adaptive Community Post Limited 1,212.20 Completed kit de coletas de sementes Quotations Envelope 03 23 20 16 29 15 Initiatives Component 1: Sustainable Pending SUB 135-8 / Aquisição de Request for Single Stage - One 2017-09- 2017-10- 2017-12- TF / 18765 and Adaptive Community Post Limited 0.00 Implement Gêneros alimentícios Quotations Envelope 21 06 06 Initiatives ation Component 1: Sustainable SUB 135-9 / Aquisição de Request for Single Stage - One 2017-09- 2017-09- 2017-10- 2017-09- 2017-11- 2017-10- TF / 18765 and Adaptive Community Post Limited 167.12 Completed uma caixa de som portátil Quotations Envelope 21 20 04 25 04 26 Initiatives SUB 135-10 / Aquisição de equipamentos - notebook - Component 1: Sustainable Aquisição de projetor Request for Single Stage - One 2017-09- 2017-12- 2017-10- 2017-12- 2017-11- 2018-01- TF / 18765 and Adaptive Community Post Limited 1,676.86 Completed multimídia - Aquisição de Quotations Envelope 21 15 04 18 14 10 Initiatives câmera filmadora/fotográfica profissional SUB 135-11 / Aquisição de Component 1: Sustainable Request for Single Stage - One 2017-09- 2018-03- 2017-10- 2018-04- 2017-11- 2018-05- kit de ferramentas para obra TF / 18765 and Adaptive Community Post Limited 1,178.62 Completed Quotations Envelope 23 16 08 16 18 05 em bio construção Initiatives SUB 135-12 / Aquisição de Component 1: Sustainable kit de ferramentas para Request for Single Stage - One 2017-09- 2018-03- 2017-10- 2018-04- 2017-11- 2018-05- TF / 18765 and Adaptive Community Post Limited 202.20 Completed auxiliar na produção de Quotations Envelope 23 16 09 13 18 28 Initiatives sementes SUB 135-15 / Aquisição de Component 1: Sustainable Pending Request for Single Stage - One 2017-09- 2017-10- 2017-11- prensa para farinha de TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 21 06 16 mandioca Initiatives ation SUB 135-18 / Aquisição de Component 1: Sustainable utensílios para estruturação Request for Single Stage - One 2017-09- 2018-03- 2017-10- 2018-04- 2017-11- 2018-05- TF / 18765 and Adaptive Community Post Limited 64.21 Completed da cozinha do espaço Quotations Envelope 23 16 09 16 09 16 Initiatives multiuso SUB 135-19 / Aquisição de Component 1: Sustainable Pending kit de materiais para obra Request for Single Stage - One 2017-09- 2017-10- 2017-11- TF / 18765 and Adaptive Community Post Limited 0.00 Implement do espaço mullti uso - Quotations Envelope 16 11 11 Initiatives ation materiais de construção - madeireira SUB 135-20 / Aquisição de Component 1: Sustainable Request for Single Stage - One 2017-09- 2017-10- 2017-10- 2017-10- 2017-11- 2017-11- 1000 m3 de hiper adobe TF / 18765 and Adaptive Community Post Limited 283.42 Completed Quotations Envelope 25 11 10 23 10 18 (bobina) Initiatives Component 1: Sustainable SUB 135-21 / Aquisição de Request for Single Stage - One 2017-09- 2017-10- 2017-10- 2017-11- 2017-11- 2017-11- TF / 18765 and Adaptive Community Post Limited 1,870.59 Completed 145 telhas ecológicas Quotations Envelope 25 23 10 01 10 30 Initiatives Component 1: Sustainable SUB 42-23 / Aquisição de Request for Single Stage - One 2017-09- 2017-11- 2017-10- 2017-12- 2017-12- 2017-12- TF / 18765 and Adaptive Community Post Limited 7,617.93 Completed 02 motocicletas Quotations Envelope 26 17 13 04 13 20 Initiatives SUB 42-24 / Aquisição de Component 1: Sustainable Request for Single Stage - One 2017-09- 2017-11- 2017-10- 2017-12- 2017-12- 2017-12- Barco e Motor para apoiar TF / 18765 and Adaptive Community Post Limited 4,216.30 Completed Quotations Envelope 29 08 16 20 16 20 vigilância. Initiatives SUB 42-26 / Aquisição de Component 1: Sustainable armário em aço fechado e Request for Single Stage - One 2017-10- 2019-01- 2017-10- 2019-01- 2017-11- 2019-01- TF / 18765 and Adaptive Community Post Limited 634.76 Completed mesa para 6 lugares, com Quotations Envelope 02 14 18 23 18 31 Initiatives cadeiras. SUB 42-28 / Aquisição de Component 1: Sustainable Request for Single Stage - One 2017-09- 2018-03- 2017-10- 2018-03- 2017-11- 2018-04- três Rádios Walk Talk Bivolt, TF / 18765 and Adaptive Community Post Limited 181.46 Completed Quotations Envelope 22 23 09 23 09 21 25 km Initiatives SUB 42-29 / Aquisição de Component 1: Sustainable Request for Single Stage - One 2017-09- 2018-05- 2017-10- 2018-05- 2017-12- 2018-06- 01 notebook e de 01 TF / 18765 and Adaptive Community Post Limited 836.96 Completed Quotations Envelope 27 08 14 09 14 08 máquina fotográfica Initiatives SUB 42-30 / Aquisição de Component 1: Sustainable Pending Request for Single Stage - One 2017-10- 2017-10- 2017-11- Kit telefone rural com TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 10 27 27 internet. Initiatives ation SUB 30 - 15 / Aquisição de arame liso n°. 12 e 20 Rolos Component 1: Sustainable Request for Single Stage - One 2017-10- 2018-08- 2017-10- 2018-08- 2018-01- 2018-09- de arame liso, sendo 1000 TF / 18765 and Adaptive Community Post Limited 2,266.03 Completed Quotations Envelope 13 01 30 14 01 12 metros cada rolo e bitola Initiatives 1/2''. Component 1: Sustainable SUB 42-31 / Aquisição de Request for Single Stage - One 2017-10- 2017-10- 2017-10- 2017-11- 2017-11- 2017-11- TF / 18765 and Adaptive Community Post Limited 102.55 Completed fogão industrial Quotations Envelope 03 25 20 06 20 08 Initiatives SUB 42-32 / Utensílios de cozinha: 5 panelas grandes, 4 bacias, 2 baldes plásticos, Component 1: Sustainable 2 garrafas térmicas de 5 Request for Single Stage - One 2017-09- 2017-10- 2017-11- TF / 18765 and Adaptive Community Post Limited 0.00 Canceled litros, 2 garrafas térmicas Quotations Envelope 23 10 10 Initiatives para café, 4 conchas grandes, 4 facas, 2 lampiões, 1 caixa térmica grande. SUB 42-33 / Aquisição de Kit de vestuário para ações Component 1: Sustainable Request for Single Stage - One 2017-09- 2017-11- 2017-10- 2017-12- 2017-11- 2018-01- de vigilância e fiscalização TF / 18765 and Adaptive Community Post Limited 582.24 Completed Quotations Envelope 23 07 10 08 10 06 com 2 camisetas, 1 boné e Initiatives 1 colete de identificação de vigilância. SUB 42-34 / Aquisição de Component 1: Sustainable Request for Single Stage - One 2017-10- 2018-06- 2017-10- 2018-07- 2017-11- 2018-08- kit padrão de energia TF / 18765 and Adaptive Community Post Limited 195.27 Completed Quotations Envelope 02 19 18 12 18 11 monofásico Initiatives SUB 42-35 / Aquisição de Component 1: Sustainable Request for Single Stage - One 2017-10- 2018-06- 2017-10- 2018-07- 2017-11- 2018-08- kit para banheiro: Vaso TF / 18765 and Adaptive Community Post Limited 195.91 Completed Quotations Envelope 04 19 21 12 21 11 sanitário, chuveiro, Initiatives encanamento, etc. SUB 30 - 20 / Aquisição de Component 1: Sustainable Request for Single Stage - One 2017-10- 2018-01- 2017-10- 2018-03- 2017-11- 2018-03- 02 (dois) fogões industriais TF / 18765 and Adaptive Community Post Limited 534.47 Completed Quotations Envelope 02 30 19 02 20 31 quatro bocas. Initiatives Component 1: Sustainable SUB 42-36 / Aquisição de Request for Single Stage - One 2017-09- 2017-10- 2017-10- 2017-11- 2017-12- 2018-01- TF / 18765 and Adaptive Community Post Limited 3,545.52 Completed alimentos. Quotations Envelope 19 25 06 06 06 08 Initiatives SUB 30 - 21 / Aquisição de Component 1: Sustainable 02 (duas) Caixas d'água e Request for Single Stage - One 2017-10- 2018-08- 2017-10- 2018-08- 2017-11- 2018-09- TF / 18765 and Adaptive Community Post Limited 220.78 Completed 02 (dois) Carrinhos de mão Quotations Envelope 13 01 30 14 30 13 Initiatives galvanizado. SUB 30 - 24 / Aquisição de Component 1: Sustainable Impressora monocromática Request for Single Stage - One 2017-09- 2018-12- 2017-10- 2018-12- 2017-12- 2019-02- TF / 18765 and Adaptive Community Post Limited 1,222.96 Completed a laser wi-fi, tonner e Quotations Envelope 29 19 16 19 16 04 Initiatives Computador desktop. SUB 30 - 26 / Aquisições de machados, podões e ferramentas semelhantes com gume- machados, Tijo Component 1: Sustainable furado 8 furos, Kit de Request for Single Stage - One 2017-10- 2018-08- 2017-10- 2018-08- 2017-11- 2018-09- TF / 18765 and Adaptive Community Post Limited 1,012.69 Completed ferramentas para Quotations Envelope 02 01 18 14 18 12 Initiatives construção do viveiro, Peças de treliça c/ 6 m de altura fig. nº 1 e 2, Janela veneziana 1,20m x 1m, Porta veneziana 2,10m x 0,80m. SUB 30 - 27 / Aquisição de Component 1: Sustainable jogos de pratos, talheres, Request for Single Stage - One 2017-09- 2018-12- 2017-10- 2018-12- 2017-11- 2019-01- TF / 18765 and Adaptive Community Post Limited 881.80 Completed utensílios de cozinha e Quotations Envelope 29 13 16 19 06 18 Initiatives panelas grandes. SUB 30 - 30 / Aquisição de generos alimenticios (kit: Component 1: Sustainable arroz, feijão, carne, Request for Single Stage - One 2017-09- 2018-06- 2017-10- 2018-07- 2019-12- 2018-08- TF / 18765 and Adaptive Community Post Limited 1,815.17 Completed macarrão, salada, sucos, Quotations Envelope 29 27 16 19 26 17 Initiatives sobremesas) refeições para os participantes. SUB 30 - 32 / Aquisição de Kit de material de escritório (papel a4, canetas, grampeador, pasta arquivo, Component 1: Sustainable envelopes, pasta Request for Single Stage - One 2017-09- 2018-07- 2017-10- 2018-08- 2017-11- 2018-09- TF / 18765 and Adaptive Community Post Limited 826.09 Completed catálogo),04 Kits material Quotations Envelope 29 26 16 14 16 12 Initiatives didático (caneta, papel a4, pasta, apostilas, papel pardo, pincel atômico), Kit de material de papelaria contendo caderno SUB 120-16 / Aquisição de gêneros alimentícios Component 1: Sustainable Pending adquiridos direto da 2017-12- 2017-12- 2018-01- 2018-07- TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Implement comunidade para Realização 05 19 09 28 Initiatives ation do encontro anual dos coletores do tix SUB 4-4 / CT4.4. Aquisição Component 1: Sustainable Request for Single Stage - One 2017-10- 2018-11- 2017-11- 2018-11- 2019-03- 2018-12- de gêneros alimentícios fora TF / 18765 and Adaptive Community Post Limited 467.92 Completed Quotations Envelope 07 13 10 22 05 20 comunidade. Initiatives SUB 4-5 / CT4.5. Aquisição de ferramentas e de arame Component 1: Sustainable Request for Single Stage - One 2017-10- 2018-08- 2017-11- 2018-09- 2017-11- 2018-10- farpado de ferro ou aço TF / 18765 and Adaptive Community Post Limited 1,263.66 Completed Quotations Envelope 20 02 20 03 30 03 para cercamento e Initiatives isolamento das nascentes. SUB 4-7 / CT4.7. Aquisição Component 1: Sustainable Request for Single Stage - One 2017-08- 2017-09- 2017-10- de equipamentos para TF / 18765 and Adaptive Community Post Limited 0.00 Canceled Quotations Envelope 24 26 16 brigada de combate a Initiatives incêndios. SUB 135-16 / Aquisição de Component 1: Sustainable Pending utensílios para estruturação Request for Single Stage - One 2017-09- 2017-10- 2017-11- TF / 18765 and Adaptive Community Post Limited 0.00 Implement da cozinha do espaço Quotations Envelope 25 09 09 Initiatives ation multiuso - tacho para farinha SUB 135-13 / Aquisição de Component 1: Sustainable Request for Single Stage - One 2017-09- 2018-03- 2017-10- 2018-04- 2017-11- 2018-05- kit para construção de TF / 18765 and Adaptive Community Post Limited 471.31 Completed Quotations Envelope 25 16 09 13 09 28 espaço multiuso Initiatives SUB 135-14 / Aquisição de Component 1: Sustainable Pending kit de materiais para Request for Single Stage - One 2017-09- 2017-10- 2017-11- TF / 18765 and Adaptive Community Post Limited 0.00 Implement construção de espaço Quotations Envelope 25 09 09 Initiatives ation multiuso SUB 135-17 / Aquisição de Component 1: Sustainable Pending utensílios para estruturação Request for Single Stage - One 2017-09- 2017-10- 2017-12- TF / 18765 and Adaptive Community Post Limited 0.00 Implement da cozinha do espaço Quotations Envelope 23 09 08 Initiatives ation multiuso SUB 4-3 / CT4.3. Aquisição Component 1: Sustainable Pending 2017-07- 2017-08- 2017-08- 2018-12- de gêneros alimentícios TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Implement 11 02 25 18 direto da comunidade Initiatives ation SUB 56-17 / CT56.17 Aquisição de gêneros alimentícios direto da comunidade para oficinas Component 1: Sustainable comunitária de capacitação 2017-06- 2017-07- 2017-07- 2019-06- TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled mapeamento e 29 08 18 18 Initiatives planejamento participativo e oficinas de construção do plano de gestão dos recursos hidricos comunitario Component 1: Sustainable Under SUB 56 - 19 / Aquisição de Request for Single Stage - One 2017-11- 2018-02- 2017-12- 2019-11- TF / 18765 and Adaptive Community Post Limited 0.00 Implement Gêneros alimentícios Quotations Envelope 25 15 16 18 Initiatives ation SUB 134-4 / Aquisição de Component 1: Sustainable Request for Single Stage - One 2017-12- 2018-02- 2017-12- 2018-03- 2018-01- 2018-03- ferramentas e utensilios TF / 18765 and Adaptive Community Post Limited 2,830.03 Completed Quotations Envelope 04 15 21 02 20 31 para construcao do viveiro Initiatives Component 1: Sustainable SUB 110 - 29 / Aquisição Request for Single Stage - One 2017-11- 2018-06- 2017-12- 2018-06- 2018-05- 2018-07- TF / 18765 and Adaptive Community Post Limited 78.44 Completed de Trena Digital. Quotations Envelope 16 12 07 12 08 26 Initiatives Component 1: Sustainable SUB 134-5 / Aquisicao de Request for Single Stage - One 2017-12- 2018-11- 2017-12- 2018-11- 2018-02- 2018-12- TF / 18765 and Adaptive Community Post Limited 489.86 Completed compostos para viveiro Quotations Envelope 04 26 21 27 19 12 Initiatives SUB 134-6 / Aquisiacao de Component 1: Sustainable Request for Single Stage - One 2017-12- 2017-12- 2018-01- sacolas plasticas para TF / 18765 and Adaptive Community Post Limited 0.00 Canceled Quotations Envelope 09 22 21 mudas e regador Initiatives Component 1: Sustainable Under SUB 134-7 / Aquisicao de Request for Single Stage - One 2017-11- 2018-04- 2017-12- 2018-02- TF / 18765 and Adaptive Community Post Limited 575.36 Implement projetor e tela de projecao Quotations Envelope 29 04 21 19 Initiatives ation SUB 134-8 / Aquisicao de Component 1: Sustainable Request for Single Stage - One 2017-12- 2018-01- 2018-02- arquivo de aco ultra em TF / 18765 and Adaptive Community Post Limited 0.00 Canceled Quotations Envelope 05 06 05 chapa Initiatives SUB 134-9 / Aquisicao de camera fotografica Component 1: Sustainable Request for Single Stage - One 2017-11- 2018-01- 2017-12- 2018-01- 2018-01- 2018-02- profissional com tripe TF / 18765 and Adaptive Community Post Limited 838.42 Completed Quotations Envelope 24 11 19 11 18 09 profissional e cartao de Initiatives memoria Component 1: Sustainable SUB 134-10 / Aquisição de Request for Single Stage - One 2017-12- 2017-12- 2018-02- TF / 18765 and Adaptive Community Post Limited 0.00 Canceled caixa de som amplificada Quotations Envelope 04 20 18 Initiatives SUB 134-11 / Aquisicao de Component 1: Sustainable Request for Single Stage - One 2017-12- 2018-01- 2017-12- 2018-01- 2018-02- 2018-02- computador notebook e TF / 18765 and Adaptive Community Post Limited 769.55 Completed Quotations Envelope 04 10 20 10 18 14 impressora multifuncional Initiatives Component 1: Sustainable SUB 134-12 / Aquisicao de Request for Single Stage - One 2017-12- 2018-01- 2018-03- TF / 18765 and Adaptive Community Post Limited 0.00 Canceled moto bomba a diesel Quotations Envelope 08 07 08 Initiatives Component 1: Sustainable SUB 134-13 / Aquisicao de Request for Single Stage - One 2017-11- 2017-12- 2018-01- TF / 18765 and Adaptive Community Post Limited 0.00 Canceled vigota de madeira Quotations Envelope 30 18 17 Initiatives SUB 127-23 / Aquisição de generos alimenticios direto Component 1: Sustainable 2017-11- 2017-11- 2017-12- 2018-02- da comunidade durante a TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled 17 30 14 12 construcao e reunioes do Initiatives Centro SUB 127-24 / Aquisicao de demais generos alimeniícios Component 1: Sustainable Request for Single Stage - One 2017-11- 2019-01- 2017-12- 2019-01- 2018-02- 2019-02- para consumo durante TF / 18765 and Adaptive Community Post Limited 492.64 Completed Quotations Envelope 29 07 15 28 13 26 reunioes para realizacao do Initiatives Centro de Revitalizacao SUB 127-25 / Aquisicao de Component 1: Sustainable Request for Single Stage - One 2017-12- 2018-12- 2018-01- 2018-12- 2018-01- 2019-01- armario arquivo em aco TF / 18765 and Adaptive Community Post Limited 172.57 Completed Quotations Envelope 08 20 02 20 22 20 para escritorio Initiatives SUB 127-27 / Aquisicao de equipamentos de Component 1: Sustainable Request for Single Stage - One 2017-12- 2018-05- 2017-12- 2018-05- 2018-02- 2018-06- informatica uma impressora TF / 18765 and Adaptive Community Post Limited 1,933.60 Completed Quotations Envelope 04 21 18 21 16 22 um notebook um projetor Initiatives multimidia e uma camera semi profissional SUB 127-28 / Aquisicao de Component 1: Sustainable Pending materiais de construcao Request for Single Stage - One 2017-12- 2017-12- 2018-02- TF / 18765 and Adaptive Community Post Limited 0.00 Implement para obra do Centro de Quotations Envelope 08 26 24 Initiatives ation Revitalizacao SUB 127-29 / Aquisicao de Component 1: Sustainable Pending Request for Single Stage - One 2017-12- 2017-12- 2018-01- roda d agua com vazao de TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 08 27 26 8500l e instalacao Initiatives ation Component 1: Sustainable SUB 127-30 / Aquisicao de Request for Single Stage - One 2017-12- 2018-04- 2018-01- 2018-05- 2018-03- 2018-06- TF / 18765 and Adaptive Community Post Limited 3,527.67 Completed motocicleta Quotations Envelope 18 04 09 07 10 11 Initiatives SUB 127-31 / Aquisicao de Component 1: Sustainable Request for Single Stage - One 2017-12- 2018-01- 2018-03- geladeira e freezer vertical TF / 18765 and Adaptive Community Post Limited 0.00 Canceled Quotations Envelope 20 15 16 capacidade de 900l Initiatives SUB 105-10 / CQ105.10 Component 1: Sustainable Request for Single Stage - One 2017-11- 2018-05- 2017-12- 2018-05- 2018-01- 2018-06- Aquisição de (04) quatro TF / 18765 and Adaptive Community Post Limited 503.81 Completed Quotations Envelope 20 16 11 16 27 15 caixas de som amplificadas Initiatives Page 3 Component 1: Sustainable SUB 105 - 12 / Aquisição Request for Single Stage - One 2017-11- 2018-02- 2017-12- 2018-02- 2018-01- 2018-02- TF / 18765 and Adaptive Community Post Limited 2,580.24 Completed de 05 (cinco) Notebooks. Quotations Envelope 20 05 13 05 27 05 Initiatives Component 1: Sustainable SUB 105 -13 / Aquisição de Request for Single Stage - One 2017-11- 2018-05- 2017-12- 2018-05- 2018-01- 2018-06- TF / 18765 and Adaptive Community Post Limited 1,058.41 Completed 04 (quatro) Projetores. Quotations Envelope 17 15 11 16 27 15 Initiatives SUB 105 -14 / Aquisição de Component 1: Sustainable Request for Single Stage - One 2017-11- 2018-05- 2017-12- 2018-05- 2018-01- 2018-06- 04 (quatro) gravadores de TF / 18765 and Adaptive Community Post Limited 369.97 Completed Quotations Envelope 20 15 13 16 29 15 voz digitais. Initiatives SUB 88-1 / Aquisição de Component 1: Sustainable veículo, motor 1.0 ou 1.2 ou Request for Single Stage - One 2017-12- 2018-01- 2017-12- 2018-03- 2018-03- 2019-03- TF / 18765 and Adaptive Community Post Limited 9,836.30 Completed 1.3, ar condicionado, Quotations Envelope 11 24 28 07 09 07 Initiatives direção hidraulica, flex, way SUB 88-2 / Aquisição de Component 1: Sustainable aparelho de GPS rural para Request for Single Stage - One 2017-12- 2018-04- 2017-12- 2018-04- 2018-01- 2018-05- TF / 18765 and Adaptive Community Post Limited 332.21 Completed utilização do trabalho de Quotations Envelope 11 20 28 20 29 21 Initiatives campo SUB 88-3 / Aquisição de câmera fotográfica profissional com o kit: Component 1: Sustainable câmera, case, cartão de Request for Single Stage - One 2017-12- 2018-05- 2017-12- 2018-05- 2018-02- 2018-07- TF / 18765 and Adaptive Community Post Limited 744.21 Completed memória e tripé. Quotations Envelope 12 08 29 08 08 07 Initiatives Aquisição de gravador de voz digital com cartão de memória. SUB 88-4 / Aquisição de Dronner com câmera full HD e Wifi para registros Component 1: Sustainable Request for Single Stage - One 2017-12- 2018-05- 2017-12- 2018-05- 2018-02- 2018-06- fotográficos e vídeo para TF / 18765 and Adaptive Community Post Limited 543.10 Completed Quotations Envelope 11 08 28 08 27 07 mapeamentos dos Initiatives potenciais e vulnerabilidades no território. SUB 88-5 / Aquisição de kits de materiais didáticos Component 1: Sustainable Request for Single Stage - One 2017-12- 2017-12- 2018-04- para atividades de gestão, TF / 18765 and Adaptive Community Post Limited 0.00 Canceled Quotations Envelope 12 29 09 monitoramento, Initiatives mobilização e oficinas Component 1: Sustainable SUB 88-6 / Aquisição de Request for Single Stage - One 2017-12- 2017-12- 2018-09- TF / 18765 and Adaptive Community Post Limited 0.00 Canceled kits de Gênero alimentícios Quotations Envelope 12 29 06 Initiatives Component 1: Sustainable Community Pending SUB 142 -4 / Aquisição de 2017-12- 2017-12- 2018-01- 2018-01- 2018-01- 2018-03- TF / 18765 and Adaptive Community Post Driven Limited 0.00 Implement gerador 1200 w 15 29 08 09 15 17 Initiatives Development ation Component 1: Sustainable Community SUB 98 -5 / Aquisição de 2017-12- 2018-09- 2017-12- 2018-09- 2017-12- 2018-09- 2018-01- 2018-10- 2018-01- 2018-10- 2018-02- 2019-02- TF / 18765 and Adaptive Community Post Driven Limited 326.58 Completed Sacola de muda. 08 13 22 13 28 21 02 01 09 01 08 05 Initiatives Development SUB 142 -5 / Aquisição de Hd externo 1tb, Hd externo Component 1: Sustainable Community 2017-12- 2018-05- 2017-12- 2018-05- 2018-01- 2018-05- 2018-01- 2018-05- 2018-01- 2018-05- 2018-03- 3tb No break, Impressora, TF / 18765 and Adaptive Community Post Driven Limited 1,289.75 Signed 15 11 29 11 08 11 09 11 15 14 17 Tinta para impressora Initiatives Development Computador desktop. SUB 142 -6 / Aquisição de itens para construção: Lima chata para enxada, Enxada, Rastelo, Cutelo, Foice, Component 1: Sustainable Community Pending 2017-12- 2017-12- 2018-01- 2018-01- 2018-01- 2018-02- Matraca, Pá, Carrinho de TF / 18765 and Adaptive Community Post Driven Limited 0.00 Implement 15 29 08 09 15 15 mão, Regador, Facão, Initiatives Development ation Tambor de plástico 30L, Mangueira 100 ml, Mangueira micro perfurada. SUB 142 -7 / Aquisição de Component 1: Sustainable Community Câmera Digital para registro 2017-12- 2018-05- 2018-01- 2018-05- 2018-01- 2018-05- 2018-01- 2018-05- 2018-01- 2018-05- 2018-02- 2018-06- TF / 18765 and Adaptive Community Post Driven Limited 597.80 Completed audiovisual: Cartão SD 32 18 07 01 07 10 07 12 07 18 08 19 23 Initiatives Development GB, Cartão SD 64 GB. SUB 98 - 8 / Sistema de Component 1: Sustainable Community energia solar para 2017-12- 2018-05- 2017-12- 2018-05- 2018-01- 2018-06- 2018-01- 2018-07- 2018-01- 2018-07- 2018-03- 2018-08- TF / 18765 and Adaptive Community Post Driven Limited 2,654.39 Completed bombeamento de água para 13 14 27 14 03 12 05 24 13 26 15 24 Initiatives Development o viveiro. SUB 98 - 9 / Aquisição Component 1: Sustainable Community 2017-12- 2018-09- 2017-12- 2018-09- 2018-01- 2018-09- 2018-01- 2018-09- 2018-01- 2018-09- 2018-03- 2018-10- Bomba dágua para TF / 18765 and Adaptive Community Post Driven Limited 1,637.88 Completed 13 13 27 13 03 14 08 24 15 25 16 24 irrigação. Initiatives Development SUB 98 -10 / Aquisição de ferramentas e equipamentos, sendo: Rolo Component 1: Sustainable Community tela de arame, Caixa dágua 2017-12- 2018-07- 2018-01- 2018-07- 2018-01- 2018-07- 2018-01- 2018-07- 2018-01- 2018-07- 2018-03- 2018-08- TF / 18765 and Adaptive Community Post Driven Limited 5,188.89 Completed polietileno capacidade 5, 20 10 03 10 12 17 15 25 22 26 23 24 Initiatives Development Sombrite , Pá, Kit irrigação, Rolo de arame liso, Fio para o sistema de energia solar. SUB 98 - 11 / Aquisição de Postes de eucalipto tratado , Component 1: Sustainable Community 2017-12- 2018-05- 2018-01- 2018-05- 2018-01- 2018-06- 2018-01- 2018-07- 2018-01- 2018-07- 2018-03- 2018-08- Poste de madeira , Poste de TF / 18765 and Adaptive Community Post Driven Limited 3,286.40 Completed 22 22 05 22 15 12 16 25 22 25 23 25 madeira, Poste de madeira e Initiatives Development Poste de madeira. Component 1: Sustainable Community SUB 142 -10 / Aquisição de 2017-12- 2018-03- 2018-01- 2018-03- 2018-01- 2018-03- 2018-01- 2018-03- 2018-01- 2018-03- 2018-02- 2018-03- TF / 18765 and Adaptive Community Post Driven Limited 1,611.67 Completed freezer 19 01 02 01 11 01 13 01 19 01 19 31 Initiatives Development SUB 91-3 / Aquisição de Component 1: Sustainable Community 2017-12- 2018-09- 2017-12- 2018-09- 2018-01- 2018-09- 2018-01- 2018-09- 2018-01- 2018-09- 2018-03- 2018-10- materiais para construção TF / 18765 and Adaptive Community Post Driven Limited 917.98 Completed 14 10 28 13 04 21 08 24 14 25 16 25 de viveiros Initiatives Development Component 1: Sustainable Community SUB 142 -11 / Aquisição de 2017-12- 2018-03- 2018-01- 2018-03- 2018-01- 2018-03- 2018-01- 2018-03- 2018-01- 2018-03- 2018-02- 2018-03- TF / 18765 and Adaptive Community Post Driven Limited 494.53 Completed liquidificadores 19 02 02 02 11 02 13 02 19 02 19 19 Initiatives Development SUB 98 - 12 / Aquisição de Component 1: Sustainable Community Kit epi - equipamento de 2017-12- 2018-05- 2018-01- 2018-05- 2018-01- 2018-06- 2018-01- 2018-06- 2018-01- 2018-06- 2018-02- 2018-07- TF / 18765 and Adaptive Community Post Driven Limited 38.67 Completed proteção individual para os 22 30 05 30 12 04 13 13 23 18 22 17 Initiatives Development viveiristas e ajudante. Component 1: Sustainable Community SUB 98 -13 / Aquisição de 2017-12- 2018-05- 2018-01- 2018-05- 2018-01- 2018-06- 2018-01- 2018-06- 2018-01- 2018-06- 2018-02- 2018-07- TF / 18765 and Adaptive Community Post Driven Limited 132.29 Completed ferramenta elétrica. 22 30 05 30 12 04 16 13 23 18 22 18 Initiatives Development Component 1: Sustainable Community Pending SUB 142 -12 / Aquisição de 2017-12- 2018-01- 2018-01- 2018-01- 2018-01- 2018-02- TF / 18765 and Adaptive Community Post Driven Limited 0.00 Implement embalagens 20 03 12 15 20 20 Initiatives Development ation SUB 98 - 14 / Aquisição de Component 1: Sustainable Community 2017-12- 2018-05- 2018-01- 2018-05- 2018-01- 2018-06- 2018-01- 2018-06- 2018-01- 2018-06- 2018-02- Cavadeira articulada em TF / 18765 and Adaptive Community Post Driven Limited 47.92 Signed 22 30 05 30 12 04 15 13 23 18 22 aço. Initiatives Development SUB 142 -13 / Aquisição de Component 1: Sustainable Community 2017-12- 2018-05- 2018-01- 2018-05- 2018-01- 2018-05- 2018-01- 2018-05- 2018-01- 2018-05- 2018-02- 2018-05- gravador de áudio e TF / 18765 and Adaptive Community Post Driven Limited 414.70 Completed 20 08 03 08 12 08 15 08 20 08 20 08 microfone , para gravação Initiatives Development de áudio SUB 125 - 9 / Aquisição de material de escritório as as Component 1: Sustainable Community Pending 2017-12- 2018-01- 2018-01- 2018-01- 2018-01- 2018-02- reuniões bimestrais e TF / 18765 and Adaptive Community Post Driven Limited 0.00 Implement 20 03 12 15 22 22 semestrais e para confecção Initiatives Development ation dos etno mapas. SUB 91-4 / Aquisição de Component 1: Sustainable Community Pending 2017-12- 2017-12- 2018-01- 2018-01- 2018-01- 2018-02- materiais para produção de TF / 18765 and Adaptive Community Post Driven Limited 0.00 Implement 14 28 04 08 14 14 mudas Initiatives Development ation SUB 125 -10 / Aquisição de 40 toneladas de calcário Component 1: Sustainable Community Pending para correção do ph do solo 2017-12- 2018-01- 2018-01- 2018-01- 2018-01- 2018-02- TF / 18765 and Adaptive Community Post Driven Limited 0.00 Implement para ser entregue na Aldeia 20 03 15 15 22 21 Initiatives Development ation Bananal Distrito de Taunay - Aquidauana -MS. SUB 91-5 / Aquisição de Component 1: Sustainable Community 2017-12- 2018-04- 2017-12- 2018-04- 2018-01- 2018-04- 2018-01- 2018-05- 2018-01- 2018-05- 2018-03- 2018-06- equipamentos para TF / 18765 and Adaptive Community Post Driven Limited 4,806.80 Completed 15 06 29 06 05 18 09 07 15 07 17 06 bombeamento de água Initiatives Development SUB 125 - 11 / Aquisição de equipamentos de informática, sendo: 02 Component 1: Sustainable Community 2017-12- 2018-02- 2018-01- 2018-02- 2018-01- 2018-02- 2018-01- 2018-02- 2018-01- 2018-02- 2018-03- 2018-03- notebook, 01 máquinas TF / 18765 and Adaptive Community Post Driven Limited 2,272.11 Completed 20 28 03 23 15 23 15 23 22 23 23 20 fotográfica, 01 GPS, 01 Initiatives Development Projetor multimídia - data show e 01 Impressora multifuncional. SUB 125 - 12 / Aquisição Component 1: Sustainable Community Pending de rama de mandioca 2018-01- 2018-01- 2018-02- 2018-02- 2018-02- 2018-04- TF / 18765 and Adaptive Community Post Driven Limited 0.00 Implement amarela, para ser plantada 17 31 02 12 19 20 Initiatives Development ation nas áreas enriquecidas. Component 1: Sustainable Community Pending SUB 91-6 / Aquisição de 2017-12- 2017-12- 2018-01- 2018-01- 2018-01- 2018-02- TF / 18765 and Adaptive Community Post Driven Limited 0.00 Implement terra vegetal 15 29 05 09 15 15 Initiatives Development ation SUB 91-8 / Aquisição de Component 1: Sustainable Community 2017-12- 2018-03- 2018-01- 2018-03- 2018-01- 2018-04- 2018-01- 2018-04- 2018-01- 2018-04- 2018-04- 2018-05- máquinas e equipamentos TF / 18765 and Adaptive Community Post Driven Limited 26,959.48 Completed 20 22 03 22 10 13 14 16 20 26 21 08 agrícolas Initiatives Development SUB 93 - 4 / Aquisição de caixa de som com Component 1: Sustainable Community Pending microfone para realização 2018-01- 2018-02- 2018-02- 2018-02- 2018-02- 2018-03- TF / 18765 and Adaptive Community Post Driven Limited 0.00 Implement de reuniões com a 18 01 08 12 19 21 Initiatives Development ation comunidade afim de promover a boa execução do projeto. SUB 143 -2 / Aquisição de Component 1: Sustainable Community 2018-01- 2019-01- 2018-01- 2019-01- 2018-01- 2019-01- 2018-01- 2019-01- 2018-01- 2019-01- 2018-03- 2019-02- kits de material para TF / 18765 and Adaptive Community Post Driven Limited 474.55 Completed 10 10 20 23 25 23 29 24 30 24 02 27 acampamento. Initiatives Development Component 1: Sustainable Community Pending SUB 143 -3 / Aquisição de 2018-01- 2018-01- 2018-01- 2018-01- 2018-01- 2018-03- TF / 18765 and Adaptive Community Post Driven Limited 0.00 Implement fitas para filmadora 10 20 27 29 30 02 Initiatives Development ation SUB 124 - 9 / Aquisição de enxadas com cabo, aquisição de roçadeiras semimecanizadas, aquisição Component 1: Sustainable Community 2018-01- 2018-06- 2018-02- 2018-06- 2018-02- 2018-06- 2018-02- 2018-07- 2018-03- 2018-07- 2018-04- 2018-08- de cavadeiras, aquisição de TF / 18765 and Adaptive Community Post Driven Limited 818.96 Completed 30 08 13 08 24 26 24 10 03 25 02 04 limas para amolar Initiatives Development ferramentas, aquisição de enxadões aquisição de 10 f e outros. SUB 143 -4 / Aquisição de Component 1: Sustainable Community 2018-01- 2018-08- 2018-01- 2018-08- 2018-02- 2018-08- 2018-02- 2018-09- 2018-02- 2018-09- 2018-04- 2018-11- duas motocicletas on-off TF / 18765 and Adaptive Community Post Driven Limited 6,914.67 Completed 05 10 24 10 02 11 03 03 05 06 07 05 Road. Initiatives Development Component 1: Sustainable Community Pending SUB 143 -5 / Aquisição de 2018-01- 2018-01- 2018-02- 2018-02- 2018-02- 2019-03- TF / 18765 and Adaptive Community Post Driven Limited 0.00 Implement gêneros alimentícios. 15 24 02 03 05 13 Initiatives Development ation SUB 143 -6 / Aquisição de Component 1: Sustainable Community 2018-01- 2018-08- 2018-01- 2018-08- 2018-02- 2018-08- 2018-02- 2018-09- 2018-02- 2018-09- 2018-04- 2018-11- Motor de popa de 15hp com TF / 18765 and Adaptive Community Post Driven Limited 2,224.49 Completed 16 13 30 14 06 20 09 03 12 06 13 06 motor 2t Initiatives Development Component 1: Sustainable Community SUB 143 - 9 / Aquisição de 2018-01- 2018-08- 2018-02- 2018-08- 2018-02- 2018-08- 2018-02- 2018-09- 2018-02- 2018-09- 2018-04- 2018-10- TF / 18765 and Adaptive Community Post Driven Limited 1,738.53 Completed Barco. 20 13 03 14 10 15 12 03 16 06 17 06 Initiatives Development Component 1: Sustainable Community SUB 143 - 8 / Aquisição de 2018-01- 2018-05- 2018-01- 2018-05- 2018-02- 2018-05- 2018-02- 2018-05- 2018-02- 2018-05- 2018-04- 2018-06- TF / 18765 and Adaptive Community Post Driven Limited 725.65 Completed aparelho de GPS. 16 24 30 24 08 24 09 24 12 24 13 23 Initiatives Development SUB 143 -7 / Aquisição de Component 1: Sustainable Community 2018-01- 2018-05- 2018-01- 2018-05- 2018-02- 2018-05- 2018-02- 2018-05- 2018-02- 2018-05- 2018-04- 2018-06- câmera fotográfica e TF / 18765 and Adaptive Community Post Driven Limited 1,187.94 Completed 16 23 30 24 08 24 09 24 12 24 13 23 Aquisição de Notebook Initiatives Development SUB 100 -8 / Aquisição de Component 1: Sustainable Community equipamentos de 2018-01- 2018-03- 2018-01- 2018-04- 2018-01- 2018-04- 2018-01- 2018-04- 2018-02- 2018-04- 2018-03- 2018-05- TF / 18765 and Adaptive Community Post Driven Limited 517.01 Completed informática: HD Externo 1TB 05 12 19 11 29 11 30 16 05 11 08 11 Initiatives Development : projetor portátil. Component 1: Sustainable Community SUB 100 - 2 / Aquisição de 2017-12- 2018-07- 2018-01- 2018-07- 2018-01- 2018-07- 2018-01- 2018-08- 2018-01- 2018-08- 2018-02- 2018-09- TF / 18765 and Adaptive Community Post Driven Limited 2,032.07 Completed roçadeira e moto serra . 20 09 03 09 12 11 15 08 22 16 21 07 Initiatives Development Component 1: Sustainable Community Pending SUB 100 - 4 / Aquisição de 2017-12- 2018-01- 2018-01- 2018-01- 2018-01- 2018-02- TF / 18765 and Adaptive Community Post Driven Limited 0.00 Implement kit ferramentas agrícolas. 20 03 12 15 22 21 Initiatives Development ation Component 1: Sustainable Community SUB 100 - 5 / Aquisição de 2017-12- 2018-01- 2018-01- 2018-01- 2018-01- 2018-03- TF / 18765 and Adaptive Community Post Driven Limited 0.00 Canceled kit material do viveiro. 20 03 10 15 22 23 Initiatives Development Component 1: Sustainable Community SUB 100 - 6 / Aquisição de 2017-12- 2018-01- 2018-01- 2018-01- 2018-01- 2018-05- TF / 18765 and Adaptive Community Post Driven Limited 0.00 Canceled gêneros alimentícios 20 03 10 15 22 22 Initiatives Development SUB 100 -7 / Aquisição de Component 1: Sustainable Community 2018-01- 2018-04- 2018-01- 2018-04- 2018-01- 2018-04- 2018-01- 2018-04- 2018-02- 2018-04- 2018-03- 2018-04- caixa de som amplificada TF / 18765 and Adaptive Community Post Driven Limited 154.02 Completed 05 09 19 10 29 10 30 10 05 11 08 30 com usb Initiatives Development SUB 85 -14 / Aquisição de notebook Impressora laser Component 1: Sustainable Community 2018-01- 2018-02- 2018-01- 2018-02- 2018-02- 2018-02- 2018-02- 2018-02- 2018-02- 2018-02- 2018-04- 2018-05- multifuncional e toner TF / 18765 and Adaptive Community Post Driven Limited 1,237.90 Completed 10 20 24 20 02 20 05 21 10 21 12 02 impressora, projetor Initiatives Development portátil, Tela de Projeção Component 1: Sustainable Community SUB 85 - 7 / Aquisição de 2018-01- 2018-08- 2018-01- 2018-08- 2018-01- 2018-08- 2018-02- 2018-08- 2018-02- 2018-09- 2018-04- 2018-10- TF / 18765 and Adaptive Community Post Driven Limited 3,351.10 Completed motocicleta . 08 07 22 07 29 07 02 27 09 06 10 05 Initiatives Development SUB 85 -12 / Aquisição de Component 1: Sustainable Community 2018-01- 2018-02- 2018-01- 2018-02- 2018-02- 2018-02- 2018-02- 2018-02- 2018-02- 2018-02- 2018-03- 2018-03- caixa de som amplificada TF / 18765 and Adaptive Community Post Driven Limited 212.34 Completed 10 08 24 19 02 19 05 19 10 20 23 22 com microfone . Initiatives Development Component 1: Sustainable Community SUB 85 - 8 / Aquisição de 2018-01- 2019-10- 2018-01- 2019-10- 2018-01- 2019-10- 2018-02- 2019-10- 2018-02- 2019-10- 2018-05- 2020-01- TF / 18765 and Adaptive Community Post Driven Limited 886.99 Completed materiais para irrigação. 08 23 22 23 31 23 02 30 09 31 21 21 Initiatives Development SUB 85 -11 / Aquisição de Porteira,Ripas de madeira Component 1: Sustainable Community 2018-01- 2019-02- 2018-01- 2019-02- 2018-01- 2019-03- 2018-02- 2019-03- 2018-02- 2019-03- 2018-07- 2019-03- mista, Postes de eucalipto TF / 18765 and Adaptive Community Post Driven Limited 4,107.59 Completed 08 27 22 27 31 12 02 13 08 13 09 28 tratado e Esticadores de Initiatives Development cerca ,para estrutura de viveiro. SUB 85 - 9 / Aquisição de materiais: Sombrite, bolas de arame, Prego, Prego com Component 1: Sustainable Community 2018-01- 2018-08- 2018-01- 2018-08- 2018-01- 2018-09- 2018-02- 2018-09- 2018-02- 2018-09- 2018-05- 2018-10- cabeça, Arame, Materiais de TF / 18765 and Adaptive Community Post Driven Limited 4,939.45 Completed 08 07 22 09 29 05 02 11 09 24 21 24 construção: areia, cimento, Initiatives Development pedra, ferragens, Cabo de aço e outros. SUB 85 -10 / Aquisição de Component 1: Sustainable Community 2018-01- 2018-08- 2018-01- 2018-08- 2018-01- 2018-08- 2018-02- 2018-09- 2018-02- 2018-09- 2018-05- 2018-10- materiais elétricos e TF / 18765 and Adaptive Community Post Driven Limited 4,808.28 Completed 08 08 22 09 31 22 02 12 08 24 21 24 hidráulicos e elétrico. Initiatives Development AI1 - 5 / Aquisição de materiais Component 1: Sustainable Community Pending consumo/didáticos para 2017-12- 2017-12- 2017-12- 2017-12- 2018-01- 2018-01- TF / 18765 and Adaptive Community Post Driven Limited 0.00 Implement realizar 02 articuladores 06 18 26 27 03 23 Initiatives Development ation indígenas, que terão bases de trabalho em Palmas - TO e Campo Grande. AI3 - 4 / Aquisição de kits Component 1: Sustainable Community Pending 2018-01- 2018-02- 2018-02- 2018-02- 2018-02- 2018-03- de material de didático para TF / 18765 and Adaptive Community Post Driven Limited 0.00 Implement 22 05 12 16 23 26 oficina. Initiatives Development ation SUB 134-3 / Aquisição de Gêneros alimentícios para Component 1: Sustainable atividade de reunião de 2017-11- 2018-11- 2017-11- 2018-11- 2017-12- 2018-02- TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled planejamento pratico das 17 26 22 26 19 17 Initiatives atividades e inicio do registro audiovisual. SUB 116-4 / CT116.4 Aquisição de material de Component 1: Sustainable Request for Single Stage - One 2017-08- 2017-08- 2017-10- madeireira para implantação TF / 18765 and Adaptive Community Post Limited 0.00 Canceled Quotations Envelope 04 28 27 de unidade de Initiatives processamento e hortas SUB 116-12 / CT116.12 Component 1: Sustainable Pending Aquisição de utensílios para Request for Single Stage - One 2017-08- 2017-08- 2017-10- TF / 18765 and Adaptive Community Post Limited 0.00 Implement implantação de unidades de Quotations Envelope 08 28 02 Initiatives ation processamento SUB 116-5 / CT116.5 Component 1: Sustainable Aquisição de barros para 2017-07- 2017-08- 2017-08- 2017-10- TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled implantação de unidade de 27 02 14 03 Initiatives processamento e hortas SUB 116-6 / CT116.6 Aquisição de bens para Component 1: Sustainable Request for Single Stage - One 2017-08- 2017-08- 2017-09- Implantação de Hortas de TF / 18765 and Adaptive Community Post Limited 0.00 Canceled Quotations Envelope 04 23 27 Quintais como Bombas e Initiatives Caixa d água dez mil litros SUB 134-2 / Aquisição de gêneros alimentícios para Component 1: Sustainable preparo de refeições, para 2017-11- 2017-12- 2017-12- 2018-02- TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled trabalhadores que atuarão 24 01 21 19 Initiatives no mutirão de construção do viveiro. Page 4 BR-CAA-39549-GO-RFQ / Aquisicao de equipamentos de informatica para execucao projeto DGM Component 3: Project Pending sendo 01 equipamento Request for Single Stage - One 2018-01- 2018-02- 2018-04- TF / 18765 Management, Monitoring Post Limited 0.00 Implement externo de seguranca e Quotations Envelope 19 05 06 and Evaluation ation backup do Banco de Dados do Sistema do projeto e 01 HD externo para armazenamento dos produtos de comunicacao do projeto. SUB 134 -15 / Aquisição de gêneros alimentícios para Component 1: Sustainable Community preparo de refeições, para 2017-12- 2017-12- 2017-12- 2018-01- 2018-01- 2018-03- TF / 18765 and Adaptive Community Post Driven Limited 0.00 Canceled trabalhadores que atuarão 06 20 29 02 08 09 Initiatives Development no mutirão de construção do viveiro. SUB 116-11 / CT116.11 Aquisição de itens para Component 1: Sustainable implantação da unidade de Request for Single Stage - One 2017-08- 2017-08- 2017-09- TF / 18765 and Adaptive Community Post Limited 0.00 Canceled processamento como Portas Quotations Envelope 07 25 24 Initiatives com caixile Dobradicas e Basculantes SUB 116-13 / CT116.13 Component 1: Sustainable Request for Single Stage - One 2017-08- 2017-08- 2017-09- Aquisição de extintor contra TF / 18765 and Adaptive Community Post Limited 0.00 Canceled Quotations Envelope 09 28 27 incêndio Initiatives SUB 116-19 / CT116.19 Component 1: Sustainable Request for Single Stage - One 2017-08- 2017-08- 2017-09- Aquisição de forrageira TF / 18765 and Adaptive Community Post Limited 0.00 Canceled Quotations Envelope 04 25 29 cinco kw Initiatives Component 1: Sustainable SUB 116-20 / CT116.20 Request for Single Stage - One 2017-08- 2017-08- 2017-09- TF / 18765 and Adaptive Community Post Limited 0.00 Canceled Aquisicao de rocadeiras Quotations Envelope 04 24 23 Initiatives SUB 142-14 / Aquisição de Component 1: Sustainable Community 2018-01- 2018-05- 2018-01- 2018-05- 2018-02- 2018-05- 2018-02- 2018-05- 2018-02- 2018-05- 2018-04- 2018-06- generos alimenticios para TF / 18765 and Adaptive Community Post Driven Limited 1,785.45 Completed 15 18 24 14 05 14 09 21 16 28 17 25 plantio e oficinas Initiatives Development SUB 116-9 / CT116.9 Aquisição de mudas Component 1: Sustainable Request for Single Stage - One 2017-08- 2018-11- 2017-08- 2018-12- 2017-10- 2019-01- diversas para TF / 18765 and Adaptive Community Post Limited 526.43 Completed Quotations Envelope 03 29 22 17 11 16 Enriquecimento de Initiatives Agroquintais com SAF Biodiversos SUB 116-34 / Aquisição de Component 1: Sustainable Community 2018-01- 2018-11- 2018-01- 2018-11- 2018-02- 2018-12- 2018-02- 2018-12- 2018-02- 2018-12- 2018-04- 2019-01- mudas para reflorestamento TF / 18765 and Adaptive Community Post Driven Limited 3,403.17 Completed 15 30 25 30 07 14 09 14 15 14 18 14 e cercamento de rio Initiatives Development SUB 110-6 / CQ110.6 Component 1: Sustainable Request for Single Stage - One 2017-07- 2017-08- 2018-02- Aquisição de sacos para TF / 18765 and Adaptive Community Post Limited 0.00 Canceled Quotations Envelope 29 21 17 mudas Initiatives SUB 93 - 2 / Aquisição de Component 1: Sustainable Community equipamentos, sendo 01 2018-01- 2018-02- 2018-02- 2018-02- 2018-02- 2018-04- TF / 18765 and Adaptive Community Post Driven Limited 0.00 Canceled aparelho GPS e 01 Telão de 18 01 08 10 19 20 Initiatives Development projetor para data show. Component 1: Sustainable Community SUB 105 -15 / Aquisição de 2018-01- 2019-03- 2018-01- 2019-03- 2018-02- 2019-03- 2018-02- 2019-03- 2018-02- 2019-03- 2018-03- 2019-04- TF / 18765 and Adaptive Community Post Driven Limited 462.74 Completed 06 cadeiras giratórias. 11 18 22 20 03 20 05 21 12 21 15 30 Initiatives Development SUB 91-7 / Aquisição de Component 1: Sustainable Request for Single Stage - One 2018-02- 2018-04- 2018-02- 2018-05- 2018-05- 2018-09- materiais para o sistema de TF / 18765 and Adaptive Community Post Limited 8,763.53 Completed Quotations Envelope 02 06 21 07 22 28 bombeamento de água Initiatives Component 1: Sustainable Community Pending SUB 91-2 / Fornecimento 2018-01- 2018-02- 2018-02- 2018-02- 2018-02- 2018-04- TF / 18765 and Adaptive Community Post Driven Limited 0.00 Implement de Óleo Diesel 22 02 13 15 22 23 Initiatives Development ation SUB 93 - 3 / Aquisição de insumos para horticultura Component 1: Sustainable Community 2018-01- 2019-01- 2018-02- 2019-01- 2018-02- 2019-01- 2018-02- 2019-01- 2018-02- 2019-02- 2018-07- 2019-03- (ferramentas manuais, TF / 18765 and Adaptive Community Post Driven Limited 386.28 Completed 18 23 01 23 08 28 12 31 19 01 19 12 sementes, sombrite, tela Initiatives Development lateral, kit irrigação. Component 1: Sustainable Community SUB 93-5 / Aquisição de 2018-01- 2018-02- 2018-02- 2018-02- 2018-02- 2018-07- TF / 18765 and Adaptive Community Post Driven Limited 0.00 Canceled Sacos para Mudas 18 01 08 10 19 19 Initiatives Development Component 1: Sustainable Community SUB 93-6 / Aquisição de 2018-01- 2018-02- 2018-02- 2018-02- 2018-02- 2018-07- TF / 18765 and Adaptive Community Post Driven Limited 0.00 Canceled Brita 18 01 08 10 19 19 Initiatives Development Component 1: Sustainable Community SUB 93-7 / kit EPI (Botas, 2018-01- 2019-01- 2018-02- 2019-01- 2018-02- 2019-01- 2018-02- 2019-01- 2018-02- 2019-01- 2018-07- 2019-02- TF / 18765 and Adaptive Community Post Driven Limited 154.17 Completed luvas, óculos,avental) 18 04 01 04 08 10 10 14 19 15 19 14 Initiatives Development Component 1: Sustainable SUB 120-9 / Aquisição de 2017-09- 2017-09- 2017-10- 2019-05- TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled gêneros alimentícios 05 19 06 29 Initiatives SUB 130-2 / CT130.2 Component 1: Sustainable Request for Single Stage - One 2017-08- 2018-12- 2017-08- 2018-12- 2017-10- 2019-01- Aquisição de embalagens TF / 18765 and Adaptive Community Post Limited 1,051.87 Completed Quotations Envelope 02 11 22 18 01 10 diversas de plastico Initiatives Component 1: Sustainable SUB 130 - 9 / CT130.9 Request for Single Stage - One 2018-01- 2018-12- 2018-02- 2018-12- 2018-03- 2019-01- TF / 18765 and Adaptive Community Post Limited 1,147.55 Completed Embalagens de papelão. Quotations Envelope 29 12 24 18 31 18 Initiatives Component 1: Sustainable SUB 47-7 / Aquisição de Request for Single Stage - One 2018-02- 2018-03- 2018-03- 2018-03- 2018-05- 2018-05- TF / 18765 and Adaptive Community Post Limited 26,979.80 Completed um veículo, tipo caminhão. Quotations Envelope 19 09 27 23 28 28 Initiatives SUB 25-1 N / Aquisição de Component 1: Sustainable um carro de passeio visando Request for Single Stage - One 2018-02- 2018-07- 2018-03- 2018-08- 2018-05- 2018-09- TF / 18765 and Adaptive Community Post Limited 12,685.96 Completed viabilizar atividades do Quotations Envelope 26 30 16 16 15 17 Initiatives projeto. SUB 25-2 N / Aquisição de um Notebook, Datashow, Component 1: Sustainable Request for Single Stage - One 2018-03- 2018-09- 2018-03- 2018-09- 2018-05- 2018-10- tela com suporte para TF / 18765 and Adaptive Community Post Limited 1,237.38 Completed Quotations Envelope 15 03 31 04 10 18 projeção de data show e Initiatives câmera fotográfica SUB 25-5 N / Aquisição de ferramentas e materiais, botas para serviço, chapéus para serviço, bolas de arame Component 1: Sustainable Request for Single Stage - One 2018-03- 2018-10- 2018-04- 2018-11- 2018-05- 2018-12- para cerca de 500 metros, TF / 18765 and Adaptive Community Post Limited 3,569.05 Completed Quotations Envelope 19 17 03 06 03 05 grampos de fio curvado, Initiatives cavadeira, facão, enxada com cabo, enxadão com cabo, pé-de-cabra, regador. SUB 16-17 / Aquisição de Component 1: Sustainable Request for Single Stage - One 2018-03- 2018-03- 2018-04- 2018-04- 2018-05- 2018-05- arames e distanciadores TF / 18765 and Adaptive Community Post Limited 1,932.27 Completed Quotations Envelope 05 09 11 13 11 14 para cercamento. Initiatives Component 1: Sustainable SUB 47-9 / Aquisição de Request for Single Stage - One 2018-04- 2018-04- 2018-05- 2018-05- 2018-07- 2018-07- TF / 18765 and Adaptive Community Post Limited 3,854.26 Completed carroceria para caminhão. Quotations Envelope 06 10 12 04 13 04 Initiatives SUB 25-3 N / Aquisição de gêneros alimentícios de fornecedores para capacitação, Formação da Component 1: Sustainable Pending comunidade sobre Request for Single Stage - One 2018-03- 2018-04- 2018-05- TF / 18765 and Adaptive Community Post Limited 0.00 Implement recuperação ambiental, Quotations Envelope 30 24 24 Initiatives ation Cercamento de nascentes, Oficina sobre plantio de mudas, Seminário temático em agroecologia e avaliação SUB 25-4 N / Aquisição de mudas-plantas apropriadas Component 1: Sustainable Pending Request for Single Stage - One 2018-03- 2018-04- 2018-06- para recuperação de áreas TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 20 03 02 degradadas com frete Initiatives ation incluído. SUB 25-6 N / Aquisição Component 1: Sustainable Request for Single Stage - One 2018-04- 2018-10- 2018-05- 2018-11- 2018-06- 2018-12- poste de eucalipto tratado TF / 18765 and Adaptive Community Post Limited 3,399.94 Completed Quotations Envelope 12 23 12 22 11 26 para cercamento Initiatives SUB 129 - 2 / Aquisição de Component 1: Sustainable Pending Request for Single Stage - One 2018-05- 2018-06- 2018-08- 3 máquinas para furar TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 07 14 13 sementes. Initiatives ation Component 1: Sustainable Pending SUB 129 - 3 / Aquisição de Request for Single Stage - One 2018-05- 2018-06- 2018-08- TF / 18765 and Adaptive Community Post Limited 0.00 Implement duas máquinas de costura. Quotations Envelope 07 14 13 Initiatives ation Component 1: Sustainable SUB 129 - 4 / Aquisição de Request for Single Stage - One 2018-05- 2018-06- 2018-08- TF / 18765 and Adaptive Community Post Limited 0.00 Canceled três pirógrafos. Quotations Envelope 07 14 13 Initiatives Component 1: Sustainable Pending SUB 129 - 15 / Aquisição Request for Single Stage - One 2018-07- 2018-08- 2018-10- TF / 18765 and Adaptive Community Post Limited 0.00 Implement de kit para expedição . Quotations Envelope 23 30 29 Initiatives ation SUB 55-5 / CT55.5 Component 1: Sustainable Request for Single Stage - One 2017-06- 2018-03- 2017-07- 2018-03- 2017-08- 2018-04- Aquisição de dois Freezers TF / 18765 and Adaptive Community Post Limited 905.73 Completed Quotations Envelope 27 27 25 27 29 23 horizontais. Initiatives SUB 135- 7 / Aquisição de Component 1: Sustainable Pending 2018-03- 2018-03- 2018-04- 2018-06- veículo, 4x4, motor a diesel TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Implement 13 18 22 21 e carroceria. Initiatives ation SUB 135-7 / Aquisição de Component 1: Sustainable Request for Single Stage - One 2017-09- 2018-03- 2017-10- 2017-11- veículo, 4x4, motor a diesel TF / 18765 and Adaptive Community Post Limited 0.00 Canceled Quotations Envelope 22 26 09 08 e carroceria. Initiatives SUB 123 -5 / Aquisição de Component 1: Sustainable kit de materiais para manejo Request for Single Stage - One 2018-03- 2018-04- 2018-06- TF / 18765 and Adaptive Community Post Limited 0.00 Canceled do forno para produção de Quotations Envelope 28 10 11 Initiatives cerâmica. SUB 123 -7 / Aquisição de Component 1: Sustainable kit de material para Request for Single Stage - One 2018-03- 2019-02- 2018-04- 2019-02- 2018-06- 2019-03- TF / 18765 and Adaptive Community Post Limited 501.89 Completed silkscreen (tela, tinta,rodo, Quotations Envelope 28 07 10 19 11 11 Initiatives papel vegetal, calha etc..) SUB 123 -9 / Aquisição de Component 1: Sustainable Barco de alumínio de Request for Single Stage - One 2018-03- 2018-08- 2018-04- 2018-09- 2018-05- 2018-10- TF / 18765 and Adaptive Community Post Limited 5,377.71 Completed aproximadamente 5 metros Quotations Envelope 28 14 10 06 31 06 Initiatives com motor. SUB 123 -10 / Aquisição de impressora de mesa multifuncional (R$ 500,00). Component 1: Sustainable Aquisição de computador - Request for Single Stage - One 2018-03- 2018-06- 2018-04- 2018-06- 2018-06- 2018-07- TF / 18765 and Adaptive Community Post Limited 1,438.38 Completed 2 notebook completo (R$ Quotations Envelope 28 04 10 05 11 05 Initiatives 4000,00), Aquisição de câmera fotográfica (R$ 1000,00). SUB 123 -12 / Component 1: Sustainable Request for Single Stage - One 2018-03- 2018-04- 2018-04- Equipamentos para instação TF / 18765 and Adaptive Community Post Limited 0.00 Canceled Quotations Envelope 28 10 26 de internet a rádio. Initiatives SUB 129 - 6 / Aquisição de Component 1: Sustainable Under materiais de construção Request for Single Stage - One 2018-07- 2020-01- 2018-08- 2018-10- TF / 18765 and Adaptive Community Post Limited 0.00 Implement para construção do ateliê de Quotations Envelope 23 23 30 29 Initiatives ation produção de artesanato. SUB 129 - 1 / Aquisição de gêneros alimentícios para os agentes de Component 1: Sustainable Pending Request for Single Stage - One 2018-05- 2018-06- 2018-08- monitoramento durante as TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 07 14 13 expedições e alimentação Initiatives ation dos participantes em 3 oficinas que serão realizadas pelo projeto. SUB 129 - 5 / Aquisição de Component 1: Sustainable Request for Single Stage - One 2018-05- 2018-06- 2018-08- uma bancada de apoio para TF / 18765 and Adaptive Community Post Limited 0.00 Canceled Quotations Envelope 07 14 13 equipamentos. Initiatives SUB 56-1 / CT56.1 Component 1: Sustainable Request for Single Stage - One 2017-07- 2018-05- 2017-07- 2018-06- 2017-08- 2018-07- Aquisição cadeiras para TF / 18765 and Adaptive Community Post Limited 321.36 Completed Quotations Envelope 01 25 18 14 27 13 estrutura da sede do Initiatives projeto. SUB 56- 19 / Aquisição de Component 1: Sustainable Request for Single Stage - One 2018-04- 2018-05- 2018-05- 2018-04- 2018-06- 2018-05- pratos, copos, jogo de TF / 18765 and Adaptive Community Post Limited 510.25 Completed Quotations Envelope 28 30 21 10 20 24 panelas e colheres Initiatives SUB 88-9 / Aquisição de Component 1: Sustainable combustível e lubrificantes Request for Single Stage - One 2018-04- 2018-05- 2018-11- TF / 18765 and Adaptive Community Post Limited 0.00 Canceled para execução das Quotations Envelope 30 21 17 Initiatives atividades do projeto. SUB 142-17 / Aquisição de Component 1: Sustainable Pending Request for Single Stage - One 2018-04- 2018-05- 2018-06- miçangas para produção de TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 30 25 24 artesanato. Initiatives ation Component 1: Sustainable SUB 130-5 / Aquisição de Request for Single Stage - One 2017-07- 2018-05- 2017-08- 2018-06- 2017-09- 2018-07- TF / 18765 and Adaptive Community Post Limited 9,378.99 Completed moinho de pedra Quotations Envelope 31 18 21 18 30 16 Initiatives Component 1: Sustainable SUB 130-10 / Aquisição de Request for Single Stage - One 2018-04- 2018-05- 2018-05- 2018-07- 2018-08- 2018-10- TF / 18765 and Adaptive Community Post Limited 5,579.26 Completed moinho de facas Quotations Envelope 30 18 20 11 18 09 Initiatives SUB 4-20 / Aquisição de Component 1: Sustainable Request for Single Stage - One 2018-04- 2018-07- 2018-05- 2018-07- 2018-07- 2018-08- carroceria para veículo tipo TF / 18765 and Adaptive Community Post Limited 1,867.07 Completed Quotations Envelope 30 09 21 16 20 15 caminhão leve Initiatives BR-CAA-39550-GO-RFQ / Aquisição de 19 equipamentos portátil de Component 1: Sustainable Under informática - tablets - para Request for Single Stage - One 2018-04- 2018-06- 2018-05- 2018-07- TF / 18765 and Adaptive Community Post Limited 0.00 Implement acompanhamento de metas Quotations Envelope 27 20 12 11 Initiatives ation e atividades dos subprojetos - 2º edital de seleção de propostas DGM/FIP/BRASIL SUB 125 -8 / Aquisição de máquinas-trator agrícola Component 1: Sustainable Request for Single Stage - One 2018-05- 2018-10- 2018-06- 2018-10- 2018-07- 2019-02- para execução do projeto TF / 18765 and Adaptive Community Post Limited 29,811.62 Completed Quotations Envelope 12 08 01 23 31 23 nas áreas degradadas, Initiatives nascente e reboque de trator. Component 1: Sustainable SUB 4-2 / CT4.2. Aquisição Request for Single Stage - One 2018-05- 2018-05- 2018-06- 2018-06- 2018-11- 2018-10- TF / 18765 and Adaptive Community Post Limited 32,555.05 Completed de veiculo novo Quotations Envelope 12 29 01 22 28 20 Initiatives SUB 61-7 / CQ61.7 Component 1: Sustainable Pending Request for Single Stage - One 2017-07- 2017-08- 2017-09- Aquisição de Embaladora a TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 26 21 30 vácuo Initiatives ation SUB 42-22 / Aquisição de Component 1: Sustainable Request for Single Stage - One 2017-10- 2017-10- 2017-11- 02 capacetes para TF / 18765 and Adaptive Community Post Limited 0.00 Canceled Quotations Envelope 09 26 27 motocicleta. Initiatives SUB 42-25 / Aquisição de Component 1: Sustainable pneus especializado para Request for Single Stage - One 2017-09- 2017-10- 2017-11- TF / 18765 and Adaptive Community Post Limited 0.00 Canceled andar em lugares de difícil Quotations Envelope 29 16 16 Initiatives acesso e terras alagadas. SUB 142-9 / Aquisição de Component 1: Sustainable Request for Single Stage - One 2018-05- 2018-05- 2018-06- 2018-05- 2018-07- 2018-06- duas baterias recarregáveis TF / 18765 and Adaptive Community Post Limited 63.07 Completed Quotations Envelope 30 25 08 25 23 25 para câmera fotográfica Initiatives SUB 42-27 / Aquisição de carrinho de mão - Tijolo de 8 furos - Cimento comum - Telha de cerâmica plan com Component 1: Sustainable Request for Single Stage - One 2017-09- 2018-06- 2017-10- 2018-07- 2017-11- 2018-07- cumieira - Prego para TF / 18765 and Adaptive Community Post Limited 4,439.56 Completed Quotations Envelope 25 19 11 05 11 27 caibros (pacote de pregos Initiatives 17 X 21 mm) e demais materiais para construção de uma barracão de alvenaria. SUB 26-6 / CT26.6 Aquisição de equipamentos Component 1: Sustainable Pending Request for Single Stage - One 2017-06- 2017-07- 2017-09- de informatica como TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 26 20 18 computador, impressora e Initiatives ation suprimentos SUB 45-4 / CT45.4 Aquisicao de materiais Component 1: Sustainable eletricos hidraulicos e de Request for Single Stage - One 2017-06- 2017-07- 2017-08- TF / 18765 and Adaptive Community Post Limited 0.00 Canceled construcao para a construir Quotations Envelope 26 18 17 Initiatives a Unidade de Beneficiamento de Producao de Azeite de Coco Babacu SUB 45-5 / CT45.5 Component 1: Sustainable Aquisicao de materiais para Request for Single Stage - One 2017-06- 2017-07- 2017-08- TF / 18765 and Adaptive Community Post Limited 0.00 Canceled forro e telhado da Unidade Quotations Envelope 26 19 18 Initiatives de Beneficiamento SUB 45-25 / Fornecimento de Combustível para Component 1: Sustainable Request for Single Stage - One 2018-06- 2018-06- 2018-12- acompanhamento técnico TF / 18765 and Adaptive Community Post Limited 0.00 Canceled Quotations Envelope 05 25 22 do Subprojeto (São João do Initiatives Arraial - PI) SUB 45-1 / CT45.1 Servico Component 1: Sustainable Pending de fornecimento de Request for Single Stage - One 2018-06- 2018-06- 2018-12- TF / 18765 and Adaptive Community Post Limited 0.00 Implement combustivel para Quotations Envelope 05 21 18 Initiatives ation acompanhamento tecnico do subprojeto em Teresina (PI) Page 5 SUB 142 -8 / Aquisição de Component 1: Sustainable carne bovina para Request for Single Stage - One 2018-06- 2018-06- 2018-06- 2018-06- 2018-06- 2018-06- TF / 18765 and Adaptive Community Post Limited 2,141.41 Completed atividades: Oficina de Polpas Quotations Envelope 13 13 15 15 30 25 Initiatives e Festa do Milho. SUB 99-16 / Aquisição de Component 1: Sustainable Pending materiais hidráulicos para Request for Single Stage - One 2018-07- 2018-07- 2018-08- TF / 18765 and Adaptive Community Post Limited 0.00 Implement implementação de unidade Quotations Envelope 05 22 21 Initiatives ation produtiva. SUB 110-29 / Fornecimento de gêneros Component 1: Sustainable Request for Single Stage - One 2018-08- 2018-08- 2018-09- alimentícios para 4 TF / 18765 and Adaptive Community Post Limited 0.00 Canceled Quotations Envelope 07 28 27 Reuniões mensais Initiatives organizativas e de monitoramento SUB 110-34 / Fornecimento de gêneros alimentícios para Component 1: Sustainable Request for Single Stage - One 2018-08- 2018-08- 2018-09- Cercamento da área crítica TF / 18765 and Adaptive Community Post Limited 0.00 Canceled Quotations Envelope 04 25 24 para fins de regeneração Initiatives natural,manejo agroflorestal agroecológico de espécies nativas. BR-CAA-39551-GO-RFQ / Aquisição de notebook, celular, cartão de memória micro SD, estabilizar para Component 2: Capacity filmar com celular, tripé Request for Single Stage - One 2018-09- 2018-11- 2018-09- 2019-02- 2018-11- 2018-12- TF / 18765 Building and Institutional Post Limited 2,657.62 Completed para celular, microfone de Quotations Envelope 10 13 17 13 16 13 Strengthening lapela e mochila para notebook - a serem utilizados pela equipe de comunicação do CAA/DGM Brasil BR-CAA-39552-GO-RFQ / Aquisição de câmera digital profissional para fotografia Component 2: Capacity Request for Single Stage - One 2018-09- 2018-11- 2018-09- 2018-11- 2018-11- 2018-12- e filmagem, lente para TF / 18765 Building and Institutional Post Limited 1,112.15 Completed Quotations Envelope 07 12 12 12 11 12 câmera digital profissional, Strengthening cabo de transferência de dados para câmera digital. 125-15 / Aquisição de 01 Drone para fazer o Component 1: Sustainable Request for Single Stage - One 2018-09- 2018-10- 2018-09- 2018-10- 2018-11- 2018-11- diagnóstico ambiental e TF / 18765 and Adaptive Community Post Limited 2,569.18 Completed Quotations Envelope 09 08 19 23 18 22 territorial, com treinamento Initiatives para uso. Component 1: Sustainable SUB 28-12 / Aquisição de Request for Single Stage - One 2018-11- 2020-12- 2018-12- 2020-12- 2019-01- 2020-12- TF / 18765 and Adaptive Community Post Limited 3,999.58 Completed materiais para construção Quotations Envelope 22 01 15 23 14 23 Initiatives SUB 28-17 / Aquisição de Component 1: Sustainable mudas de banana e coco Request for Single Stage - One 2018-11- 2018-11- 2018-12- 2018-12- 2019-01- 2019-01- TF / 18765 and Adaptive Community Post Limited 2,846.33 Completed para instalação de campos Quotations Envelope 17 26 12 11 11 10 Initiatives de frutíferas. SUB 100 - 12 / Aquisição Component 1: Sustainable Pending de gêneros alimentícios Request for Single Stage - One 2018-11- 2018-12- 2019-01- TF / 18765 and Adaptive Community Post Limited 0.00 Implement para realização de Quotations Envelope 17 15 14 Initiatives ation atividades do projeto SUB 100 - 14 / Contratação Component 1: Sustainable Pending de serviços para confecção Request for Single Stage - One 2018-11- 2018-12- 2019-02- TF / 18765 and Adaptive Community Post Limited 0.00 Implement de camisetas e bonés para o Quotations Envelope 17 10 08 Initiatives ation concurso de roça do Xingu. Component 1: Sustainable SUB 100 - 16 / Aquisição Request for Single Stage - One 2018-11- 2019-08- 2018-12- 2019-08- 2019-01- 2019-10- TF / 18765 and Adaptive Community Post Limited 2,287.09 Completed de motor de popa 25hp Quotations Envelope 17 14 10 27 09 01 Initiatives BR-CAA-39553-GO-RFQ / Component 1: Sustainable Aquisição de notebooks e Request for Single Stage - One 2018-11- 2018-11- 2019-01- 2018-11- 2019-04- 2018-12- TF / 18765 and Adaptive Community Post Limited 2,990.95 Completed computadores para equipe Quotations Envelope 17 30 25 30 25 31 Initiatives do projeto SUB 120-18 / Aquisição de um barco e um motor de Component 1: Sustainable Pending popa para transporte de Request for Single Stage - One 2018-11- 2018-12- 2019-02- TF / 18765 and Adaptive Community Post Limited 0.00 Implement comunitários - saída do Quotations Envelope 17 10 08 Initiatives ation Território Xingu a outras localidades. SUB 116-1 / 27725Aquisição de Component 1: Sustainable Request for Single Stage - One 2017-08- 2018-12- 2017-08- 2018-12- 2017-09- 2019-01- materiais elétricos e TF / 18765 and Adaptive Community Post Limited 1,116.10 Completed Quotations Envelope 03 10 25 18 29 17 hidráulicos para Initiatives implantação das unidade de processamento e hortas SUB 116-2 / Aquisição de Component 1: Sustainable Pending Request for Single Stage - One 2017-08- 2017-08- 2017-10- materiais para implantação TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 03 24 08 de Hortas de Quintais Initiatives ation SUB 116-3 / CT116.3 Aquisição de materiais de Component 1: Sustainable Request for Single Stage - One 2017-08- 2017-08- 2017-11- construção para TF / 18765 and Adaptive Community Post Limited 0.00 Canceled Quotations Envelope 04 29 07 implantação de unidade de Initiatives processamento e hortas SUB 116-36 / Aquisição de materiais de construção Component 1: Sustainable Pending Request for Single Stage - One 2018-11- 2018-12- 2019-02- como: cimento, areia, brita TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 29 16 14 e tijolos para implantação Initiatives ation da unidade de beneficiamento. SUB 116-37 / Aquisição de Component 1: Sustainable Request for Single Stage - One 2018-12- 2019-09- 2018-12- 2019-10- 2019-02- 2019-10- materiais de irrigação para TF / 18765 and Adaptive Community Post Limited 831.51 Completed Quotations Envelope 01 25 20 02 18 31 hortas Initiatives SUB 116-6-2 / Aquisição Component 1: Sustainable de bens para Implantação Request for Single Stage - One 2018-12- 2019-01- 2018-12- 2019-01- 2019-02- 2019-02- TF / 18765 and Adaptive Community Post Limited 2,804.87 Completed de Hortas de Quintais, como Quotations Envelope 01 04 20 26 18 25 Initiatives bombas e caixas d'águas. SUB 125-17 / Aquisição de Component 1: Sustainable ferramentas para Request for Single Stage - One 2018-12- 2019-11- 2018-12- 2019-11- 2019-02- 2019-12- TF / 18765 and Adaptive Community Post Limited 1,108.38 Completed construção de cercas, para Quotations Envelope 01 23 20 29 18 04 Initiatives cercamento de duas nascentes. SUB 125-16 / Aquisição de Component 1: Sustainable adubos orgânicos e Request for Single Stage - One 2018-11- 2020-10- 2018-12- 2020-11- 2019-01- 2020-11- TF / 18765 and Adaptive Community Post Limited 1,044.39 Completed sementes para plantio e Quotations Envelope 25 29 14 17 13 25 Initiatives recuperação de áreas degradadas. SUB 71-8 / Aquisição de Component 1: Sustainable Request for Single Stage - One 2018-12- 2020-07- 2018-12- 2020-07- 2019-02- 2020-08- embalagens para produtos TF / 18765 and Adaptive Community Post Limited 2,076.23 Completed Quotations Envelope 01 20 20 23 18 06 beneficiados Initiatives SUB 108-9 / Aquisição de gêneros alimentícios para: Component 1: Sustainable Pending Capacitação em boas Request for Single Stage - One 2018-12- 2018-12- 2019-01- TF / 18765 and Adaptive Community Post Limited 0.00 Implement prátcas para produção de Quotations Envelope 01 20 19 Initiatives ation alimentos e capacitação em gestão da unidade de beneficiamento. SUB 108-10 / Aquisição de equipamentos para Component 1: Sustainable Pending estruturação da unidade de Request for Single Stage - One 2018-12- 2018-12- 2019-02- TF / 18765 and Adaptive Community Post Limited 0.00 Implement beneficiamento - Quotations Envelope 01 22 20 Initiatives ation liquidificador, fogão e forno industrial. SUB 108-11 / Aquisição de Component 1: Sustainable equipamentos para cozinha: Request for Single Stage - One 2018-12- 2020-06- 2018-12- 2020-06- 2019-02- TF / 18765 and Adaptive Community Post Limited 1,343.66 Signed batedeira, amassadeira e Quotations Envelope 01 25 26 25 24 Initiatives modeladora de pães. SUB 108-19 / Aquisição de cuba (tanque) de inox, pia Component 1: Sustainable Pending Request for Single Stage - One 2018-12- 2018-12- 2019-01- com cubas de inox para TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 01 26 25 estruturação da unidade Initiatives ation multiuso. SUB 108-20 / Aquisição de mesa de inox e facas de Component 1: Sustainable Pending Request for Single Stage - One 2018-12- 2018-12- 2019-01- inox, prateleira industrial TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 01 26 25 para estruturação da Initiatives ation unidade multiuso SUB 108-23 / Aquisição de Component 1: Sustainable Under Request for Single Stage - One 2018-12- 2020-06- 2018-12- 2019-01- 2 freezers para estruturação TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 01 24 26 25 da unidade multi-uso Initiatives ation Component 1: Sustainable SUB 108-24 / Aquisição de Request for Single Stage - One 2018-12- 2019-05- 2018-12- 2019-06- 2019-01- 2019-06- TF / 18765 and Adaptive Community Post Limited 1,012.55 Completed engenho elétrico Quotations Envelope 01 02 26 07 25 28 Initiatives Component 1: Sustainable SUB 108-25 / Aquisição de Request for Single Stage - One 2018-12- 2019-04- 2018-12- 2019-04- 2019-01- 2019-05- TF / 18765 and Adaptive Community Post Limited 720.56 Completed notebook e impressora Quotations Envelope 01 08 26 12 25 29 Initiatives SUB 25-6 / CQ25.6 Aquisição de ferramentas e Component 1: Sustainable Pending Request for Single Stage - One 2017-09- 2017-09- 2018-07- materiais como botas TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 04 26 23 chapéu arames ferro aço Initiatives ation cavadeira enxadas entre outros SUB 127-35 / Aquisição de gêneros para construtores Component 1: Sustainable Pending Request for Single Stage - One 2018-12- 2018-12- 2019-02- tradicionais e para evento TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 01 20 18 de inauguração do centro Initiatives ation de revitalização. SUB 127-36 / Aquisição de conjuntos (cama + box) - 2 Component 1: Sustainable Pending Request for Single Stage - One 2018-12- 2018-12- 2019-02- de casal e 8 de solteiro para TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 01 20 18 estruturação do Centro de Initiatives ation Revitalização SUB 127-41 / Aquisição de artigos para estruturação da hospedaria do Centro de Revitalização da cultura e Component 1: Sustainable Pending Request for Single Stage - One 2018-12- 2018-12- 2019-02- visitação (lençóis de casal e TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 01 20 18 solteiro, travesseiros, Initiatives ation cobertores de casal e solteiro, toalhas, fronhas, forro de mesa) SUB 75-5 / Aquisição de ferramentas básicas para Component 1: Sustainable Request for Single Stage - One 2018-12- 2019-07- 2018-12- 2019-08- 2019-01- 2019-08- construção do Projeto de TF / 18765 and Adaptive Community Post Limited 2,324.94 Completed Quotations Envelope 01 15 20 02 19 22 Turismo Sustentável, dos Initiatives Festejos Kalungas. SUB 75-6 / Aquisição de Ferramentas elétricas e de Component 1: Sustainable Alvenaria para construção Request for Single Stage - One 2018-12- 2020-01- 2018-12- 2020-01- 2019-01- 2020-07- TF / 18765 and Adaptive Community Post Limited 399.11 Completed do Projeto de Turismo Quotations Envelope 01 27 20 27 19 03 Initiatives Sustentável, para os festejos Kalungas. Component 1: Sustainable SUB 75-7 / Aquisição de Request for Single Stage - One 2018-12- 2019-07- 2018-12- 2019-08- 2019-01- 2019-08- TF / 18765 and Adaptive Community Post Limited 1,701.52 Completed materiais de irrigação Quotations Envelope 01 08 20 05 19 22 Initiatives SUB 75-8 / Aquisição de materiais de construção, Component 1: Sustainable Request for Single Stage - One 2018-12- 2019-06- 2018-12- 2019-06- 2019-01- 2019-07- para construção da sede do TF / 18765 and Adaptive Community Post Limited 8,865.62 Completed Quotations Envelope 01 11 20 18 19 01 Projeto de Turismo Initiatives Sustentável, para os Festejos Kalungas. SUB 75-9 / Aquisição de Component 1: Sustainable Pending materiais para construção Request for Single Stage - One 2018-12- 2018-12- 2019-01- TF / 18765 and Adaptive Community Post Limited 0.00 Implement de lavanderia do Centro de Quotations Envelope 01 20 19 Initiatives ation Turismo Sustentável. SUB 75-10 / Aquisição de materiais hidráulicos para Component 1: Sustainable Request for Single Stage - One 2018-12- 2019-07- 2018-12- 2019-08- 2019-01- 2019-08- construção de banheiros, do TF / 18765 and Adaptive Community Post Limited 1,131.26 Completed Quotations Envelope 01 17 20 05 19 15 Centro de Turismo Initiatives Sustentável para os festejos Kalungas. AI3 - 5 / Aquisição de gêneros alimentícios para preparar refeição para as Component 1: Sustainable Community 2018-03- 2018-04- 2018-04- 2018-04- 2018-04- 2018-05- mulheres quebradeiras de TF / 18765 and Adaptive Community Post Driven Limited 0.00 Canceled 20 03 10 14 21 21 coco babaçu evento VIII Initiatives Development Encontrão das Quebradeiras de Coco Babaçu. BR-CAA-39554-GO-RFQ / Aquisição de notebooks para membros do Comitê Component 3: Project Request for Single Stage - One 2019-01- 2019-03- 2019-02- 2019-04- 2019-04- 2019-04- Gestor Nacional, para TF / 18765 Management, Monitoring Post Limited 6,834.14 Completed Quotations Envelope 24 28 14 17 15 25 realização de and Evaluation acompanhamento e monitoramento das atividades do projeto. SUB 110-2 / Aquisição de materiais rolos arame liso para cercamento e restauração de área com Component 1: Sustainable erosão, Construção de Request for Single Stage - One 2017-11- 2019-02- 2018-01- 2019-04- 2018-02- 2019-04- TF / 18765 and Adaptive Community Post Limited 2,899.41 Completed viveiro e sala de Quotations Envelope 25 28 19 16 28 17 Initiatives armazenamento de sementes - Grampo, Arame liso ovalado de aço zincado, Arame galvanizado, Tela de arame e outros necessários SUB 110-14 / Aquisição de Component 1: Sustainable postes de eucalipto tratado, Request for Single Stage - One 2017-08- 2019-03- 2017-08- 2019-03- 2017-09- 2019-04- TF / 18765 and Adaptive Community Post Limited 1,545.68 Completed Postes , Postes, Postes Quotations Envelope 02 01 25 15 29 15 Initiatives finos para paliçadas. SUB 110-35 / Fornecimento de gêneros Component 1: Sustainable alimentícios refeições para Request for Single Stage - One 2018-12- 2018-12- 2019-01- TF / 18765 and Adaptive Community Post Limited 0.00 Canceled os trabalhadores que vão Quotations Envelope 05 26 25 Initiatives perfurar os buracos para fazer o cercamento das nascentes. SUB 110-30 / Fornecimento de gêneros Component 1: Sustainable Request for Single Stage - One 2018-09- 2018-09- 2018-10- alimentícios para 4 TF / 18765 and Adaptive Community Post Limited 0.00 Canceled Quotations Envelope 04 25 25 Reuniões mensais Initiatives organizativas e de monitoramento SUB 110-31 / Fornecimento de gêneros Component 1: Sustainable Request for Single Stage - One 2018-10- 2018-10- 2018-11- alimentícios para 4 TF / 18765 and Adaptive Community Post Limited 0.00 Canceled Quotations Envelope 05 26 25 Reuniões mensais Initiatives organizativas e de monitoramento SUB 110-33 / Fornecimento de gêneros Component 1: Sustainable Request for Single Stage - One 2018-11- 2018-11- 2018-12- alimentícios para 4 TF / 18765 and Adaptive Community Post Limited 0.00 Canceled Quotations Envelope 04 25 25 Reuniões mensais Initiatives organizativas e de monitoramento SUB 110-32 / Fornecimento de gêneros Component 1: Sustainable Request for Single Stage - One 2018-11- 2018-11- 2018-12- alimentícios para 4 TF / 18765 and Adaptive Community Post Limited 0.00 Canceled Quotations Envelope 04 25 25 Reuniões mensais Initiatives organizativas e de monitoramento SUB 110-27 / Gêneros alimentícios para Component 1: Sustainable preparação de refeições Request for Single Stage - One 2017-08- 2019-02- 2017-08- 2019-02- 2018-01- 2019-03- TF / 18765 and Adaptive Community Post Limited 415.87 Completed para os participantes das Quotations Envelope 03 21 28 27 25 27 Initiatives reuniões/atividades do projeto. SUB 123-4 / 123.4 Contratação serviço fornecimento de Component 1: Sustainable combustível para: Gasolina Request for Single Stage - One 2018-04- 2019-03- 2018-05- 2019-04- 2019-12- 2019-07- TF / 18765 and Adaptive Community Post Limited 1,000.35 Completed para expedição de coleta e Quotations Envelope 15 07 08 03 29 01 Initiatives transporte de artesanato. Óleo 2tp para expedição de coleta e transporte de artesanato SUB 123 -6 / Aquisição de Component 1: Sustainable Request for Single Stage - One 2018-03- 2019-03- 2018-04- 2019-03- 2018-06- 2019-05- 400 camisetas brancas para TF / 18765 and Adaptive Community Post Limited 1,598.19 Completed Quotations Envelope 28 11 10 19 11 29 uso na Oficina de Serigrafia. Initiatives SUB 123 -8 / Aquisição de gêneros alimentícios para Component 1: Sustainable Oficinas, Treinamentos, Request for Single Stage - One 2018-03- 2018-04- 2019-11- TF / 18765 and Adaptive Community Post Limited 0.00 Canceled Assembleias e demais Quotations Envelope 23 05 27 Initiatives atividades envolvendo a comunidade. SUB 123 -11 / Aquisição de materiais para produção de Component 1: Sustainable artesanato (miçangas, linha Request for Single Stage - One 2018-03- 2018-04- 2018-06- TF / 18765 and Adaptive Community Post Limited 0.00 Canceled encerada, linha de nylon, Quotations Envelope 28 10 11 Initiatives agulha, feixos e ganchos, etc...) SUB 268 SC 01 / Aquisição Component 1: Sustainable Request for Single Stage - One 2019-02- 2019-10- 2019-03- 2019-11- 2019-05- de ferramentas para TF / 18765 and Adaptive Community Post Limited 1,620.48 Signed Quotations Envelope 19 30 09 27 09 produção de artesanato em Initiatives madeira SUB 268 SC 02 / Aquisição de combustível (óleo diesel Component 1: Sustainable Pending Request for Single Stage - One 2019-02- 2019-03- 2020-01- e gasolina) para atividade TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 19 09 04 Aquisição de insumos para Initiatives ation produção dos artesanatos. Page 6 SUB 268 SC 04 / Aquisição de combustível (óleo diesel Component 1: Sustainable Pending e gasolina) para atividade Request for Single Stage - One 2019-02- 2019-03- 2020-01- TF / 18765 and Adaptive Community Post Limited 0.00 Implement Realizar atividades de Quotations Envelope 19 09 04 Initiatives ation vigilância territorial da TI Menkü SUB 173 SC 003 / Aquisição de material de Component 1: Sustainable Request for Single Stage - One 2019-02- 2019-08- 2019-03- 2019-09- 2019-04- 2019-10- construção para obra de TF / 18765 and Adaptive Community Post Limited 7,908.73 Completed Quotations Envelope 19 20 09 16 09 07 estruturação da unidade de Initiatives beneficiamento comunitária SUB 173 SC 006 / Component 1: Sustainable Pending Aquisição de material Request for Single Stage - One 2019-02- 2019-03- 2019-04- TF / 18765 and Adaptive Community Post Limited 0.00 Implement hidráulico para construção Quotations Envelope 19 09 09 Initiatives ation da unidade de beneficiamento SUB 173 SC 012 / Component 1: Sustainable Aquisição de despolpadeira Request for Single Stage - One 2019-05- 2019-05- 2019-06- TF / 18765 and Adaptive Community Post Limited 0.00 Canceled e fogão industrial para Quotations Envelope 09 27 27 Initiatives estruturação da unidade de beneficiamento. SUB 263 SC 001 / Component 1: Sustainable Aquisição de material de Request for Single Stage - One 2019-02- 2019-08- 2019-03- 2019-08- 2019-04- 2019-10- TF / 18765 and Adaptive Community Post Limited 7,378.24 Completed construção e acabamentos Quotations Envelope 19 08 09 16 09 01 Initiatives para reforma da casa de artesanato. SUB 250 SC 001 / Component 1: Sustainable Request for Single Stage - One 2019-02- 2019-03- 2019-03- 2019-03- 2019-06- 2019-04- Aquisição de dois TF / 18765 and Adaptive Community Post Limited 1,027.13 Completed Quotations Envelope 19 07 09 07 08 06 notebooks para Initiatives estruturação da cooperativa SUB 45-3 / Aquisição de materiais de construção sendo areias, britas, tijolos, Component 1: Sustainable Request for Single Stage - One 2017-06- 2019-09- 2017-07- 2019-10- 2017-08- 2019-10- cimento, pedras e cal para TF / 18765 and Adaptive Community Post Limited 7,404.37 Completed Quotations Envelope 26 27 20 10 19 22 construir Unidade de Initiatives Beneficiamento de Produção de Azeite de Coco Babaçu. SUB 45-16 / Componentes de cozinha industrial: Luvas, Bacia de Alumínio, Colher grande e rasa de alumínio, Component 1: Sustainable Pending concha de alumínio grande, Request for Single Stage - One 2017-06- 2017-07- 2017-08- TF / 18765 and Adaptive Community Post Limited 0.00 Implement bacia de alumínio grande, Quotations Envelope 28 19 18 Initiatives ation Colher de Pau grande, Caldeirão para cozimento inox, Tacho de alumínio de 100L e de 50L. SUB 45-24 / CT45.24 Aquisicao de generos alimenticios das comunidades para os Component 1: Sustainable treinamentos de Oficina de 2017-06- 2017-07- 2017-07- 2019-03- TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled Gestao Organizacional 30 05 17 09 Initiatives Oficina de Planejamento Participativo Intercambio Curso de Seguranca do Trabalho Saude da Mulher dentre outros SUB 45-18 / CT45.18 Component 1: Sustainable Pending Aquisicao de mesa de Request for Single Stage - One 2017-07- 2017-07- 2017-08- TF / 18765 and Adaptive Community Post Limited 0.00 Implement granizo para manipulacao e Quotations Envelope 01 24 23 Initiatives ation envase do azeite SUB 45-20 / CT45.20 Component 1: Sustainable Pending Aquisicao de embalagens Request for Single Stage - One 2017-07- 2017-07- 2017-08- TF / 18765 and Adaptive Community Post Limited 0.00 Implement plasticas rotulos funis Quotations Envelope 01 20 19 Initiatives ation bacias e peneiras SUB 55-4 / CT55.4 Component 1: Sustainable Aquisicao de barraca feira Request for Single Stage - One 2017-06- 2017-07- 2017-08- TF / 18765 and Adaptive Community Post Limited 0.00 Canceled para exposicao e venda dos Quotations Envelope 28 27 26 Initiatives produtos dos comunitarios SUB 179 SC 003 / Component 1: Sustainable Request for Single Stage - One 2019-02- 2019-03- 2019-05- Aquisição de Materiais TF / 18765 and Adaptive Community Post Limited 0.00 Canceled Quotations Envelope 19 09 09 Hidráulicos para construção Initiatives de obras SUB 211 SC 002 / Aquisição de materiais de Component 1: Sustainable Under Request for Single Stage - One 2019-02- 2020-08- 2019-03- 2019-04- construção/elétricos para TF / 18765 and Adaptive Community Post Limited 1,933.72 Implement Quotations Envelope 23 04 13 13 construção da Casa de Initiatives ation Cultura: SUB 211 SC 001 / Aquisição de: notebook, modem para replicação, Component 1: Sustainable datashow, lâmpada para Request for Single Stage - One 2019-02- 2019-10- 2019-03- 2019-10- 2019-04- 2019-10- TF / 18765 and Adaptive Community Post Limited 824.80 Completed datashow, impressora Quotations Envelope 23 16 13 16 13 30 Initiatives multifuncional, repetidor de sinal de internet para estruturação da Associação dos Artesões e extrativistas SUB 218 SC 003 / Component 1: Sustainable Request for Single Stage - One 2019-02- 2019-04- 2019-03- 2019-04- 2019-04- 2019-08- Aquisição de linha para TF / 18765 and Adaptive Community Post Limited 906.06 Completed Quotations Envelope 19 16 09 26 09 30 bordado, diversas cores Initiatives SUB 218 SC 006 / Component 1: Sustainable Request for Single Stage - One 2019-02- 2019-03- 2019-03- 2019-04- 2019-04- 2019-09- Aquisição de algodão TF / 18765 and Adaptive Community Post Limited 4,564.02 Completed Quotations Envelope 19 28 09 03 09 16 orgânica cardado cru Initiatives SUB 71-5 / CT71.5 Component 1: Sustainable Aquisicao de generos Request for Single Stage - One 2017-07- 2017-08- 2019-02- TF / 18765 and Adaptive Community Post Limited 0.00 Canceled alimenticios para os Quotations Envelope 18 15 06 Initiatives encontros coletivos do projeto SUB 61-1 / CQ61.1 Aquisição de duas antenas Component 1: Sustainable Request for Single Stage - One 2017-07- 2017-08- 2017-09- distribuidora de sinal antena TF / 18765 and Adaptive Community Post Limited 0.00 Canceled Quotations Envelope 15 07 26 receptora de sinal e Initiatives duzentos metros de cabo de transmissão de dados Component 1: Sustainable SUB 61-2 / CQ61.2 Request for Single Stage - One 2017-07- 2017-08- 2017-09- TF / 18765 and Adaptive Community Post Limited 0.00 Canceled Aquisicao de mesa inox Quotations Envelope 17 07 16 Initiatives SUB 61-3 / CQ61.3 Component 1: Sustainable Aquisição de quatro Request for Single Stage - One 2017-07- 2017-08- 2017-09- TF / 18765 and Adaptive Community Post Limited 0.00 Canceled armários para resfriamento Quotations Envelope 19 14 23 Initiatives de produtos com vinte bandejas cada SUB 93- 4 / Aquisiçao de Component 1: Sustainable Pending generos alimenticios para Request for Single Stage - One 2019-03- 2019-03- 2019-05- TF / 18765 and Adaptive Community Post Limited 0.00 Implement participantes durante Quotations Envelope 05 20 19 Initiatives ation implementaçao da horta SUB 61-9 / CQ61.9 Aquisição de quatro palletts Component 1: Sustainable Request for Single Stage - One 2017-07- 2017-08- 2017-09- de plastico utilizado na TF / 18765 and Adaptive Community Post Limited 0.00 Canceled Quotations Envelope 31 21 20 unidade de beneficiamento Initiatives e de trinta caixas plasticas brancas SUB 61-11 / CQ61.11 Component 1: Sustainable Request for Single Stage - One 2018-01- 2018-02- 2018-03- Aquisição de mil sacos de TF / 18765 and Adaptive Community Post Limited 0.00 Canceled Quotations Envelope 24 16 18 rafia Initiatives SUB 61-13 / CQ61.13 Aquisição de materiais de Component 1: Sustainable Request for Single Stage - One 2017-08- 2017-08- 2017-09- escritório e didáticos para TF / 18765 and Adaptive Community Post Limited 0.00 Canceled Quotations Envelope 01 25 24 uma capacitação de boas Initiatives praticas SUB 61-15 / CQ61.15 Component 1: Sustainable Aquisição de um programa Request for Single Stage - One 2017-08- 2017-09- 2017-10- TF / 18765 and Adaptive Community Post Limited 0.00 Canceled de edição de vídeo Quotations Envelope 09 04 04 Initiatives compatível sony vegas SUB 93- 9 / Aquisição de gêneros alimentícios para Component 1: Sustainable Pending Request for Single Stage - One 2019-03- 2019-03- 2019-05- participantes durante TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 05 22 01 Manutenção do viveiro e Initiatives ation preparo de mudas SUB 93- 8 / Aquisição de gêneros alimentícios para Component 1: Sustainable Pending participantes durante Request for Single Stage - One 2019-03- 2019-03- 2019-04- TF / 18765 and Adaptive Community Post Limited 0.00 Implement Expedição para coleta de Quotations Envelope 05 22 21 Initiatives ation sementes em sistema de mutirão SUB 113- 22 / Aquisição de Component 1: Sustainable insumos para povoamente Request for Single Stage - One 2019-03- 2019-03- 2019-04- TF / 18765 and Adaptive Community Post Limited 0.00 Canceled de coméia e implantação de Quotations Envelope 10 21 20 Initiatives apiário SUB 113- 24 / Aquisiçao de 2 kits para instalaçao de viveiros (Telas de Component 1: Sustainable Request for Single Stage - One 2019-03- 2019-03- 2019-05- sombreamento, Arames, TF / 18765 and Adaptive Community Post Limited 0.00 Canceled Quotations Envelope 14 25 24 pregos, catracas, Initiatives mangueiras, gotejadores, microaspersores, fios eletricos, conexoes etc.) SUB 250-3 / Aquisição de 1200, Garrafas de vidros Component 1: Sustainable Request for Single Stage - One 2019-02- 2019-09- 2019-03- 2019-09- 2019-05- 2019-10- 500ml, 700 Garrafas de TF / 18765 and Adaptive Community Post Limited 911.13 Completed Quotations Envelope 21 03 18 10 16 11 vidros 250ml + Tampas + Initiatives Lacres, para Azeite de Babaçu. SUB 250-4 / Aquisição de Component 1: Sustainable Pending 30 kits de vestuário de uso Request for Single Stage - One 2019-02- 2019-03- 2019-05- TF / 18765 and Adaptive Community Post Limited 0.00 Implement feminino - (Kit oculo, Quotations Envelope 23 18 16 Initiatives ation sapato, calça, aventa, touca). SUB 0- 1 / Aquisicao de Component 1: Sustainable Request for Single Stage - One 2019-03- 2019-10- 2019-03- 2019-10- 2019-04- 2019-12- mudas frutíferas e nativas TF / 18765 and Adaptive Community Post Limited 2,918.25 Completed Quotations Envelope 18 10 26 31 25 05 para replantio Initiatives SUB 0- 2 / Aquisição de kit Component 1: Sustainable Request for Single Stage - One 2019-03- 2019-09- 2019-03- 2019-10- 2019-04- 2019-10- horta e materiais para TF / 18765 and Adaptive Community Post Limited 223.43 Completed Quotations Envelope 18 30 26 10 25 29 viveiro Initiatives SUB 26-9 / CT26.9 Component 1: Sustainable Request for Single Stage - One 2017-07- 2017-08- 2017-10- Aquisicao de sementes e TF / 18765 and Adaptive Community Post Limited 0.00 Canceled Quotations Envelope 12 07 06 mudas Initiatives SUB 170- 1 / Aquisiçao de notebook, Projetor Component 1: Sustainable Request for Single Stage - One 2019-03- 2019-03- 2019-03- 2019-03- 2019-05- 2019-04- multimidia - data show, TF / 18765 and Adaptive Community Post Limited 2,212.81 Completed Quotations Envelope 18 06 26 06 25 06 Camera fotografica , Tela Initiatives com suporte para projeçao de data show SUB 210- 3 / Aquisição de Component 1: Sustainable equipamentos: computador, Request for Single Stage - One 2019-03- 2019-03- 2019-05- TF / 18765 and Adaptive Community Post Limited 0.00 Canceled impressora, projetor e Quotations Envelope 16 24 23 Initiatives balança eletrônica SUB 210- 4 / Aquisição de Component 1: Sustainable Request for Single Stage - One 2019-03- 2019-09- 2019-03- 2019-09- 2019-05- 2019-10- materiais para construçao TF / 18765 and Adaptive Community Post Limited 1,624.01 Completed Quotations Envelope 15 20 23 30 22 04 de viveiro Initiatives SUB 210- 5 / Aquisiçao de materiais para estruturaçao do viveiro: Caixa D'agua 400 L, Boia de Caixa D'agua, Component 1: Sustainable Request for Single Stage - One 2019-03- 2019-03- 2019-04- Micro aspersor invertido, TF / 18765 and Adaptive Community Post Limited 0.00 Canceled Quotations Envelope 16 24 23 Bomba de agua submersa Initiatives completa, mangueira de Polietileno 3/4'', mangueira de Polietileno 1/2'' rolo de 50m, Pulverizadores Component 1: Sustainable SUB 30-36 / Aquisição de Request for Single Stage - One 2019-03- 2019-04- 2019-04- 2019-05- 2019-07- 2019-05- TF / 18765 and Adaptive Community Post Limited 3,074.71 Completed uma motocicleta Quotations Envelope 15 24 18 20 17 29 Initiatives SUB 105-9 / CQ105.9 Component 1: Sustainable Request for Single Stage - One 2017-07- 2017-07- 2017-09- Aquisição de duas mesas de TF / 18765 and Adaptive Community Post Limited 0.00 Canceled Quotations Envelope 13 31 04 escritório. Initiatives SUB 124 - 8 / Aquisição de touca protetora individual, aquisição de luvas de Component 1: Sustainable Community borracha,aquisição de 2018-01- 2018-02- 2018-02- 2018-02- 2018-03- 2018-04- TF / 18765 and Adaptive Community Post Driven Limited 0.00 Canceled perneiras de proteção 29 12 19 22 01 30 Initiatives Development individual, aquisição de luvas de raspas, aquisição de botas para trabalho no campo. Component 1: Sustainable SUB 113-15 / Aquisição de Request for Single Stage - One 2017-09- 2019-03- 2017-10- 2019-04- 2018-01- 2019-04- TF / 18765 and Adaptive Community Post Limited 3,604.08 Completed 2 motos Quotations Envelope 29 29 30 15 30 26 Initiatives SUB 113- 23 / Caçamba Component 1: Sustainable Request for Single Stage - One 2019-03- 2019-04- 2019-04- 2019-04- 2019-07- 2019-05- rural : semirreboques, para TF / 18765 and Adaptive Community Post Limited 1,732.44 Completed Quotations Envelope 24 12 14 29 13 10 transporte de mercadorias: Initiatives SUB 179 SC 002 / Veículo utilitário tipo camionete Component 1: Sustainable Request for Single Stage - One 2019-02- 2019-05- 2019-03- 2019-06- 2019-04- 2019-07- pick -up, Motor: 1.4, TF / 18765 and Adaptive Community Post Limited 11,127.64 Completed Quotations Envelope 19 21 09 03 09 05 Combustível: Álcool e Initiatives Gasolina, Motor: No mínimo 120 cavalos SUB 210- 2 / Aquisiçao de veículo utilitário tipo camionete pick -up, Motor: Component 1: Sustainable 1.4, Combustível: Álcool e Request for Single Stage - One 2019-03- 2019-06- 2019-03- 2019-06- 2019-07- 2019-08- TF / 18765 and Adaptive Community Post Limited 11,175.64 Completed Gasolina, Motor: No mínimo Quotations Envelope 15 03 23 19 21 05 Initiatives 120 cavalos, Ano/modelo: 2015 a 2018, Portas: mínimo 02 (portas). SUB 26-3 / CT26.3 Component 1: Sustainable Request for Single Stage - One 2017-06- 2017-07- 2017-10- Aquisição de itens para TF / 18765 and Adaptive Community Post Limited 0.00 Canceled Quotations Envelope 24 18 16 construção do viveiro de Initiatives mudas SUB 120-15 / Aquisição de gêneros alimentícios Component 1: Sustainable adquiridos direto da 2017-10- 2017-11- 2017-11- 2018-11- TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled comunidade para realização 20 03 21 06 Initiatives do encontro anual dos coletores do tix SUB 120-8 / Aquisição de Component 1: Sustainable gêneros alimentícios, para Request for Single Stage - One 2019-04- 2019-05- 2019-05- 2019-05- 2019-06- 2019-05- TF / 18765 and Adaptive Community Post Limited 2,921.87 Completed encontro anual dos Quotations Envelope 20 07 03 17 02 27 Initiatives coletores do TIX. BR-CAA-110409-GO-RFQ / Aquisição de Bolsa para transporte de câmera Component 2: Capacity Pending profissional e acessórios Request for Single Stage - One 2019-04- 2019-05- 2019-06- TF / 18765 Building and Institutional Post Limited 0.00 Implement (lentes, carregador, bateria Quotations Envelope 29 16 15 Strengthening ation e cartão de memória) para uso durante acompanhamento do projeto DGM e subprojetos Component 1: Sustainable SUB 250-2 / Aquisição de Request for Single Stage - One 2019-02- 2019-08- 2019-03- 2019-08- 2019-06- 2019-08- TF / 18765 and Adaptive Community Post Limited 1,944.07 Completed 05 Forrageiras. Quotations Envelope 21 07 18 07 17 30 Initiatives BR-CAA-110418-GO-RFQ / Aquisição de materiais Component 2: Capacity Pending didáticos para as Request for Single Stage - One 2019-04- 2019-05- 2019-06- TF / 18765 Building and Institutional Post Limited 0.00 Implement capacitações e eventos do Quotations Envelope 29 16 15 Strengthening ation plano de capacitações do DGM que serão realizadas em 2019 SUB 124 - 5 / Aquisição de Component 1: Sustainable Community 2018-01- 2018-02- 2018-02- 2018-02- 2018-02- 2018-03- kits de material didáticos TF / 18765 and Adaptive Community Post Driven Limited 0.00 Canceled 22 05 14 16 23 25 para capacitação. Initiatives Development SUB 124 - 11 / Aquisição de 1 Droner e duas Component 1: Sustainable baterias, para fazer o Request for Single Stage - One 2019-05- 2019-10- 2019-05- 2019-11- 2019-07- 2019-11- TF / 18765 and Adaptive Community Post Limited 2,694.56 Completed mapeamento e o Quotations Envelope 10 28 26 01 25 26 Initiatives diagnóstico de cada trecho a ser recuperado na terra indígena Araribé. BR-CAA-110424-GO-RFQ / Aquisição de materiais Component 2: Capacity pedagógicos específicos Request for Single Stage - One 2019-04- 2019-05- 2019-05- 2019-05- 2019-06- 2019-05- TF / 18765 Building and Institutional Post Limited 161.73 Completed para o curso de Quotations Envelope 29 03 16 10 15 10 Strengthening Agroindústria a ser realizado em Montes Claros/MG Component 1: Sustainable Pending SUB 250-7 / Aquisição de Request for Single Stage - One 2019-04- 2019-05- 2019-08- TF / 18765 and Adaptive Community Post Limited 0.00 Implement 03 Fornos para Torrefação Quotations Envelope 29 16 14 Initiatives ation Component 1: Sustainable SUB 250-8 / Aquisição de Request for Single Stage - One 2019-04- 2020-01- 2019-05- 2020-01- 2019-08- 2020-02- TF / 18765 and Adaptive Community Post Limited 1,073.83 Completed 12 panelas de alumínio Quotations Envelope 29 16 16 29 14 28 Initiatives SUB 195 - 1 / Aquisição de Component 1: Sustainable Request for Single Stage - One 2019-04- 2020-09- 2019-05- 2020-10- 2019-08- 2020-12- veículo tipo hatch, 1.0, TF / 18765 and Adaptive Community Post Limited 8,293.61 Completed Quotations Envelope 30 23 31 08 29 22 0KM. Initiatives BR-CAA-110415-GO-RFQ / Aquisição de 400 pen- Component 2: Capacity Request for Single Stage - One 2019-04- 2019-05- 2019-05- 2019-05- 2019-07- 2019-05- drives para utilização dos TF / 18765 Building and Institutional Post Limited 2,884.94 Completed Quotations Envelope 29 08 16 10 15 13 participantes nos cursos de Strengthening capacitação do DGM SUB 218 SC 005 / Component 1: Sustainable Request for Single Stage - One 2019-02- 2019-05- 2019-03- 2019-06- 2019-04- 2019-08- Aquisição de tecido de TF / 18765 and Adaptive Community Post Limited 1,957.69 Completed Quotations Envelope 19 20 09 03 09 16 algodão Initiatives Page 7 BR-CAA-110433-GO-RFQ / Aquisição de itens periféricos e acessórios de Component 3: Project Request for Single Stage - One 2019-06- 2019-06- 2019-06- 2019-06- 2019-09- informática, como mouses, TF / 18765 Management, Monitoring Post Limited 787.65 Signed Quotations Envelope 03 25 13 25 11 teclados, suportes de and Evaluation notebook componentes de computores - SSD e adpatadores SUB 56-5 / CT56.5 Component 1: Sustainable Aquisição de materiais para Request for Single Stage - One 2017-08- 2019-07- 2017-09- 2019-07- 2018-03- 2019-10- TF / 18765 and Adaptive Community Post Limited 5,542.35 Completed cercamento de nascente: Quotations Envelope 28 01 20 25 19 17 Initiatives arames (bola 500 metros). SUB 56-6 / CT56.6 Component 1: Sustainable Request for Single Stage - One 2017-07- 2019-07- 2017-08- 2019-07- 2019-06- 2019-09- Aquisição de postes de TF / 18765 and Adaptive Community Post Limited 7,098.60 Completed Quotations Envelope 22 01 14 25 15 06 eucalipto tratado para Initiatives cercamento de nascente SUB 218 - SC 007.2019 / Component 1: Sustainable Pending Contratação de serviços Request for Single Stage - One 2019-06- 2019-08- 2019-12- TF / 18765 and Adaptive Community Post Limited 0.00 Implement para produção de folders, Quotations Envelope 16 11 08 Initiatives ation banners personalizadas. SUB 2120-1 / Aquisição de materiais de construção, Component 1: Sustainable Pending Request for Single Stage - One 2019-06- 2019-07- 2019-08- elétrico e hidráulico para TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 24 17 17 construção da cozinha Initiatives ation comunitária SUB 201-1 / Aquisição de Component 1: Sustainable Request for Single Stage - One 2019-07- 2019-07- 2019-07- 2019-10- 2019-11- 2019-10- um veículo, tipo pickup para TF / 18765 and Adaptive Community Post Limited 11,626.39 Completed Quotations Envelope 03 30 21 02 11 22 dois passageiros Initiatives SUB 201-2 / Gêneros alimentícios para Realizar o resgate e o fortalecimento da festa pon hy pry (bola Component 1: Sustainable Request for Single Stage - One 2019-06- 2019-09- 2019-07- 2019-10- 2019-09- 2019-10- confeccionada com palha de TF / 18765 and Adaptive Community Post Limited 3,953.37 Completed Quotations Envelope 28 30 19 07 20 11 milho); Gêneros alimentícios Initiatives para Festa do mentowaji (corrida de tora, flechas, cantorias a noite no pátio). SUB 241-4 / Aquisição de Component 1: Sustainable Request for Single Stage - One 2019-06- 2019-06- 2019-07- 2019-07- 2019-07- 2019-08- bomba d'agua hidráulica e TF / 18765 and Adaptive Community Post Limited 0.00 Canceled Proposals Envelope 17 25 05 08 13 13 mangueira 32mm Initiatives SUB 56 - 20 / Aquisição de Component 1: Sustainable Request for Single Stage - One 2019-07- 2019-10- 2019-07- 2019-10- 2019-08- 2019-11- materiais de construção TF / 18765 and Adaptive Community Post Limited 1,101.26 Completed Quotations Envelope 02 10 26 17 27 22 para reforma da associação. Initiatives SUB 241-5 / Aquisição de matrizes de porcos caipira Component 1: Sustainable Pending Request for Single Stage - One 2019-06- 2019-06- 2019-07- 2019-07- 2019-07- 2019-08- para implementação de TF / 18765 and Adaptive Community Post Limited 0.00 Implement Proposals Envelope 17 25 05 09 13 13 sistema de produção de Initiatives ation porcos caipiras SUB 2120-3 / Aquisição de materiais para estruturação Component 1: Sustainable Pending Request for Single Stage - One 2019-06- 2019-08- 2019-08- da cozinha comunitária (Pias TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 24 04 18 inox, mesas inox, prateleira Initiatives ation de aço, armário de aço) SUB 211 SC 008 / Aquisição de móveis Component 1: Sustainable Pending (camas, estantes/armários, Request for Single Stage - One 2019-07- 2019-07- 2019-08- TF / 18765 and Adaptive Community Post Limited 0.00 Implement expositório com portas de Quotations Envelope 09 26 15 Initiatives ation vidro, jogo de sofá e cadeiras etc. SUB 211 SC 009 / Component 1: Sustainable Pending Aquisição de geladeira, Request for Single Stage - One 2019-07- 2019-07- 2019-08- TF / 18765 and Adaptive Community Post Limited 0.00 Implement freezers, máquina de lavar, Quotations Envelope 10 27 16 Initiatives ation forno micro-ondas etc. SUB 224 SC 002 / Component 1: Sustainable Request for Single Stage - One 2019-06- 2019-08- 2019-07- 2019-08- 2019-10- 2019-08- Aquisição de 01 TF / 18765 and Adaptive Community Post Limited 3,593.73 Completed Quotations Envelope 26 01 19 09 18 20 motocicletas para atividades Initiatives de vigilância SUB 224 SC 001 / Aquisição de um veículo utilitário tipo camionete Component 1: Sustainable pick -up, Motor: 1.4, Request for Single Stage - One 2019-06- 2019-07- 2019-07- 2019-07- 2019-10- 2019-09- TF / 18765 and Adaptive Community Post Limited 14,254.00 Completed Combustível: Álcool e Quotations Envelope 26 26 19 30 18 26 Initiatives Gasolina, Motor: No mínimo 120 cavalos, Ano/modelo: 2015 a 2018, Portas: mínimo 02 (portas) Component 1: Sustainable Pending SUB 75-12 / Aquisição de Request for Single Stage - One 2019-07- 2019-08- 2019-09- TF / 18765 and Adaptive Community Post Limited 0.00 Implement madeiras Quotations Envelope 30 10 12 Initiatives ation Component 1: Sustainable Pending SUB 28 - 2 / Aquisição de Request for Single Stage - One 2019-07- 2019-09- 2019-10- TF / 18765 and Adaptive Community Post Limited 0.00 Implement gêneros alimentícios Quotations Envelope 28 13 23 Initiatives ation SUB 169 -1 / Aquisição de Component 1: Sustainable Under Request for Single Stage - One 2019-07- 2019-08- 2019-09- 2020-03- equipamentos de TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 30 29 24 22 Informática Initiatives ation SUB 61-21 / Aquisição de móveis para escritório: 01 arquivo para escritório com 04 gavetas R$ 600,00; 01 Component 1: Sustainable armário de escritório R$ Request for Single Stage - One 2019-08- 2019-08- 2019-09- 2019-09- 2019-11- 2019-10- TF / 18765 and Adaptive Community Post Limited 4,276.50 Completed 300,00; 01 armário balcão Quotations Envelope 22 01 12 09 03 18 Initiatives R$ 200,00; 20 cadeiras R$ 6.000,00; 01 cadeira de escritório R$ 300,00; 01 estrutura com 03 cadeiras R$ 500,00; SUB 61-22 / Aquisição de mesa inox; Aquisição de quatro armários para resfriamento de produtos Component 1: Sustainable Request for Single Stage - One 2019-08- 2019-09- 2019-09- 2019-10- 2019-10- 2019-11- com 20 bandejas cada; TF / 18765 and Adaptive Community Post Limited 3,057.93 Completed Quotations Envelope 22 24 12 14 14 07 Aquisição de um Forno Initiatives Turbo com 10 bandejas; Aquisição de 12 facas de inox; 02 armários crescimento com 20 bandejas. SUB 75- SC 009-2019 / Aquisição de 2 caixas d Component 1: Sustainable Request for Single Stage - One 2019-08- 2019-08- 2019-09- 2019-09- 2019-10- 2019-09- água 5 mil litros para os TF / 18765 and Adaptive Community Post Limited 1,052.55 Completed Quotations Envelope 29 22 21 02 06 03 Festejos Kalungas - Initiatives Comunidade Vão de Almas SUB 123-SC 012-2019 / Component 1: Sustainable Aquisição de combustível e Request for Single Stage - One 2019-08- 2019-10- 2020-04- TF / 18765 and Adaptive Community Post Limited 0.00 Canceled óleo 2T para atividades de Quotations Envelope 23 18 15 Initiatives Assembléia Geral SUB 123 -SC 007.2019 / Component 1: Sustainable Aquisição de combustível Request for Single Stage - One 2019-08- 2019-10- 2020-04- TF / 18765 and Adaptive Community Post Limited 0.00 Canceled para expedições de coleta Quotations Envelope 23 18 15 Initiatives de material SUB 169-SC 001/2019 / Component 1: Sustainable Aquisição de materiais de Request for Single Stage - One 2019-09- 2019-08- 2019-10- 2019-09- 2019-11- 2019-10- TF / 18765 and Adaptive Community Post Limited 1,786.04 Completed construção e materiais Quotations Envelope 17 30 05 06 05 17 Initiatives elétricos e hidráulicos SUB 61-6 / CQ61.6 Component 1: Sustainable Request for Single Stage - One 2019-09- 2019-09- 2019-10- 2019-10- 2019-11- 2020-01- Aquisição de uma TF / 18765 and Adaptive Community Post Limited 11,505.56 Completed Quotations Envelope 19 12 10 15 21 28 despolpadeira Initiatives SUB 263 SC 002 / Component 1: Sustainable Request for Single Stage - One 2019-02- 2019-09- 2019-03- 2019-09- 2019-07- 2019-10- Aquisição de alimentação TF / 18765 and Adaptive Community Post Limited 2,050.52 Completed Quotations Envelope 19 13 09 30 08 01 durante a reforma da casa Initiatives do artesanato SUB 166 SC 015 / Aquisição de materiais de Component 1: Sustainable Pending construção, elétrico e Request for Single Stage - One 2019-09- 2019-09- 2019-10- TF / 18765 and Adaptive Community Post Limited 0.00 Implement hidráulicos para obra de Quotations Envelope 09 22 22 Initiatives ation cozinha para processamento de frutos do cerrado. SUB 166 SC 018 / Component 1: Sustainable Pending Aquisição de materiais Request for Single Stage - One 2019-10- 2019-10- 2019-11- TF / 18765 and Adaptive Community Post Limited 0.00 Implement elétricos para obra da Quotations Envelope 08 25 27 Initiatives ation cozinha para processamento de frutos SUB 75 - 13 / Aquisição de materiais de construção Component 1: Sustainable Request for Single Stage - One 2019-10- 2019-10- 2019-10- 2019-10- 2019-11- 2019-10- para continuação da obra TF / 18765 and Adaptive Community Post Limited 1,765.45 Completed Quotations Envelope 04 07 20 11 19 29 para estruturação do espaço Initiatives comunitário. SUB 169 -2 / Aquisição de móveis e eletrodomésticos Component 1: Sustainable para equipar o centro Request for Single Stage - One 2019-10- 2019-10- 2019-11- 2019-10- 2020-05- 2019-11- TF / 18765 and Adaptive Community Post Limited 1,229.19 Completed comunitário: geladeira 300l; Quotations Envelope 01 07 26 09 24 11 Initiatives ventiladores; Cadeiras de escritorio; Bebedouro e mesas Component 1: Sustainable SUB 170 - 6 / aquisição de Request for Single Stage - One 2019-10- 2019-10- 2019-11- 2019-10- 2019-12- 2019-11- TF / 18765 and Adaptive Community Post Limited 2,066.10 Completed ferramentas agrícolas Quotations Envelope 09 08 14 16 14 12 Initiatives SUB 85 -13 / Aquisição de Component 1: Sustainable Community 2018-01- 2018-01- 2018-02- 2018-02- 2018-02- 2018-03- caixa de papel A4, Sacos TF / 18765 and Adaptive Community Post Driven Limited 0.00 Canceled 10 24 02 05 10 13 de papel kraft 1/2 kg 1000 Initiatives Development un. Component 1: Sustainable Community SUB 85 -15 / Aquisição de 2018-01- 2018-01- 2018-02- 2018-02- 2018-02- 2019-10- TF / 18765 and Adaptive Community Post Driven Limited 0.00 Canceled gêneros alimentícios. 12 26 05 06 12 07 Initiatives Development SUB 85-15 / Materiais de Component 1: Sustainable Pending Request for Single Stage - One 2019-11- 2019-11- 2019-12- construção e elétrico para TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 08 27 27 construção do viveiro Initiatives ation SUB 16-8 / CQ16-8 Aquisição de ferramentas e Component 1: Sustainable Request for Single Stage - One 2017-08- 2017-09- 2017-10- materiais elétricos TF / 18765 and Adaptive Community Post Limited 0.00 Canceled Quotations Envelope 30 23 23 hidráulicos e para Initiatives implantação produção agroecológica e horta. SUB 16-23 / Aquisição de Component 1: Sustainable Request for Single Stage - One 2019-10- 2019-11- 2019-11- 2019-12- 2019-12- 2020-01- caixa d'água de 20.000 TF / 18765 and Adaptive Community Post Limited 1,365.96 Completed Quotations Envelope 13 27 01 10 01 02 litros para instalação no Initiatives viveiro SUB 3-1 / aquisição de Component 1: Sustainable combustíveis para ser Request for Single Stage - One 2017-08- 2017-09- 2018-04- TF / 18765 and Adaptive Community Post Limited 0.00 Canceled utilizado para o plantio de Quotations Envelope 25 29 20 Initiatives mudas e coletas de sementes. SUB 3-2 / Aquisição de kit Component 1: Sustainable Request for Single Stage - One 2018-07- 2018-08- 2018-10- de material de construção TF / 18765 and Adaptive Community Post Limited 0.00 Canceled Quotations Envelope 23 28 29 (areia, cimento, pedra, Initiatives telha, etc.) SUB 98-18 / Aquisição de gêneros alimentícios para Component 1: Sustainable Request for Single Stage - One 2018-12- 2018-12- 2019-02- mutirão durante a TF / 18765 and Adaptive Community Post Limited 0.00 Canceled Quotations Envelope 01 24 22 construção da casa de Initiatives cultura e cercamento das nascentes. Component 1: Sustainable Community SUB 98 -6 / Aquisição de 2017-12- 2017-12- 2018-01- 2018-01- 2018-01- 2018-03- TF / 18765 and Adaptive Community Post Driven Limited 0.00 Canceled móveis para escritório. 13 27 03 05 15 16 Initiatives Development Component 1: Sustainable SUB 55-1 / CT55.1 Request for Single Stage - One 2019-10- 2019-11- 2019-11- 2019-12- 2020-02- TF / 18765 and Adaptive Community Post Limited 20,776.86 Signed Aquisicao de Container Quotations Envelope 08 21 01 10 29 Initiatives SUB 127-26 / Aquisicao de Component 1: Sustainable Request for Single Stage - One 2017-12- 2017-12- 2018-01- arreios e demais acessorios TF / 18765 and Adaptive Community Post Limited 0.00 Canceled Quotations Envelope 01 18 07 para montaria Initiatives SUB 127-37 / Aquisição de Component 1: Sustainable Request for Single Stage - One 2018-12- 2018-12- 2019-02- 3 equinos para passeios TF / 18765 and Adaptive Community Post Limited 0.00 Canceled Quotations Envelope 01 20 18 turísticos Initiatives SUB 30 - 14 / Aquisição de balaios para transporte de sementes, tesouras para sebes, tesouras de podar e Component 1: Sustainable Request for Single Stage - One 2017-10- 2017-10- 2017-11- ferramentas semelhantes, TF / 18765 and Adaptive Community Post Limited 0.00 Canceled Quotations Envelope 13 30 30 manipuladas com as duas Initiatives mãos, adubo químico 4-14- 8 e regador de água para plantas . SUB 30 - 16 / Aquisição de Component 1: Sustainable Request for Single Stage - One 2017-09- 2017-11- 2017-11- areia lavada do rio, calhaus, TF / 18765 and Adaptive Community Post Limited 0.00 Canceled Quotations Envelope 30 17 17 cascalho, pedras britadas. Initiatives SUB 30 - 17 / Aquisição de móveis de escritório sendo: Component 1: Sustainable mesa de reunião com 4 Request for Single Stage - One 2017-10- 2017-11- 2018-01- TF / 18765 and Adaptive Community Post Limited 0.00 Canceled cadeiras, mesa e cadeira de Quotations Envelope 16 01 01 Initiatives escritório, armário para escritório, armário em aço. SUB 30 - 18 / Aquisição de Component 1: Sustainable Request for Single Stage - One 2017-10- 2017-10- 2017-11- bebedouro refrigerador TF / 18765 and Adaptive Community Post Limited 0.00 Canceled Quotations Envelope 02 18 18 industrial 50 l com filtro Initiatives SUB 30 - 19 / Aquisição de Component 1: Sustainable Request for Single Stage - One 2017-09- 2017-10- 2017-11- 02 (dois) Botijões de gás 13 TF / 18765 and Adaptive Community Post Limited 0.00 Canceled Quotations Envelope 30 17 17 kg Initiatives Component 1: Sustainable SUB 30 - 23 / Aquisição de Request for Single Stage - One 2017-09- 2017-10- 2017-11- TF / 18765 and Adaptive Community Post Limited 0.00 Canceled 01 (uma) câmara digital. Quotations Envelope 29 16 16 Initiatives Component 1: Sustainable SUB 30 - 25 / Aquisições Request for Single Stage - One 2017-10- 2017-10- 2017-11- TF / 18765 and Adaptive Community Post Limited 0.00 Canceled de Telhas de eternit. Quotations Envelope 02 18 18 Initiatives SUB 30 - 28 / Aquisição de kit de antenas receptoras Component 1: Sustainable Request for Single Stage - One 2017-10- 2017-10- 2017-11- com baterias, placas TF / 18765 and Adaptive Community Post Limited 0.00 Canceled Quotations Envelope 04 21 21 solares,cabos e demais Initiatives equipamentos para comunicação via internet. SUB 30 - 29 / Aquisição de kit de equipamentos de Component 1: Sustainable Request for Single Stage - One 2017-10- 2017-10- 2017-11- segurança contendo botas, TF / 18765 and Adaptive Community Post Limited 0.00 Canceled Quotations Envelope 12 30 20 luvas, óculos, chapéu de Initiatives palha e avental. Component 1: Sustainable SUB 30 - 31 / Aquisição Request for Single Stage - One 2017-11- 2018-12- 2017-11- 2017-12- TF / 18765 and Adaptive Community Post Limited 0.00 Canceled saco plástico preto Quotations Envelope 03 12 20 11 Initiatives Component 1: Sustainable SUB 30 -22 / Aquisição de Request for Single Stage - One 2017-10- 2017-10- 2017-11- TF / 18765 and Adaptive Community Post Limited 0.00 Canceled cimentos e argamassas. Quotations Envelope 02 19 20 Initiatives SUB 98 -7 / Aquisição de equipamentos de Component 1: Sustainable informática, sendo: 01 Request for Single Stage - One 2019-10- 2019-10- 2019-11- 2019-10- 2019-12- TF / 18765 and Adaptive Community Post Limited 1,087.58 Signed impressoras, 01 notebooks, Quotations Envelope 23 17 02 19 17 Initiatives 01 Tela com suporte para projeção de data show, 01 Projetor multimidia. SUB 210-3 NOVA / Aquisicao de equipamentos: Component 1: Sustainable Request for Single Stage - One 2019-03- 2019-03- 2019-03- 2019-03- 2019-05- 2019-03- computador, impressora, TF / 18765 and Adaptive Community Post Limited 1,278.43 Completed Quotations Envelope 03 13 14 13 13 27 projetor - para estruturacao Initiatives da associacao. SUB 139-2 / Aquisição de equipamentos para estruturação da cozinha comunitária: um fogão Component 1: Sustainable Pending Request for Single Stage - One 2019-10- 2019-11- 2020-01- industrial a gás; forno à gás; TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 30 09 08 liquidificador industrial para Initiatives ation o beneficiamento de alimentos e refrigeradores tipo domésticos, tabuleiro de inox. SUB 139-3 / Aquisição de material de consumo para Component 1: Sustainable Pending realização de oficinas de Request for Single Stage - One 2019-10- 2019-11- 2019-12- TF / 18765 and Adaptive Community Post Limited 0.00 Implement capacitações e reuniões de Quotations Envelope 27 11 11 Initiatives ation planejamento: papel, canetas, canetões, etc. SUB 139-4 / Aquisição de gêneros alimentícios para Component 1: Sustainable Pending Request for Single Stage - One 2020-01- 2020-01- 2020-02- atividade de TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 12 25 24 Avaliação/Aprovação do Initiatives ation Plano de Gestão Ambiental SUB 110-13 / CQ110.13 Aquisição de equipamentos para a infraestrutura do Component 1: Sustainable Pending viveiro como Termômetro Request for Single Stage - One 2019-11- 2019-11- 2019-12- TF / 18765 and Adaptive Community Post Limited 0.00 Implement de vara Motobomba Sistema Quotations Envelope 04 17 27 Initiatives ation de irrigação Medidor de umidade de solo entre outros necessários SUB 110-3 / Aquisição de matérias hidraulicos para Component 1: Sustainable Pending Request for Single Stage - One 2019-11- 2019-11- 2019-12- construção do viveiro e sala TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 01 14 14 de armazenamento de Initiatives ation sementes Page 8 SUB 16-24 / Aquisição de Component 1: Sustainable Pending combustível para trator - Request for Single Stage - One 2019-10- 2019-11- 2019-12- TF / 18765 and Adaptive Community Post Limited 0.00 Implement construção de curvas de Quotations Envelope 30 10 10 Initiatives ation nível e bacias de contenção SUB 166 SC 006 / Aquisição de batedor ou processador tritura gelo, Component 1: Sustainable Under Request for Single Stage - One 2019-11- 2020-08- 2019-11- 2020-01- liquidificador com copo TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 07 12 20 19 completo inox, Balança Initiatives ation digital eletrônica, Balança digital, refrigerador grande e freezer horizontal. SUB 166 SC 010 / Aquisição de itens para estruturação da cozinha: talheres grandes para Component 1: Sustainable Pending Request for Single Stage - One 2019-11- 2019-11- 2020-01- cozinha, jogo de panela, TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 07 20 19 conjunto talheres de mesa, Initiatives ation concha térmica para sorvete, conjunto de pratos de louça, copos tipo americanos, lixeira. Component 1: Sustainable SUB 170 - 7 / Mudas Request for Single Stage - One 2019-12- 2019-12- 2019-12- 2019-12- 2020-01- 2020-02- TF / 18765 and Adaptive Community Post Limited 1,165.06 Completed frutíferas nativas Quotations Envelope 06 04 21 17 20 18 Initiatives SUB 263 - 4 / Aquisição de Component 1: Sustainable materiais fabricação Request for Single Stage - One 2019-11- 2019-11- 2019-11- 2019-11- 2020-01- 2019-11- TF / 18765 and Adaptive Community Post Limited 1,397.08 Completed artesanatos, como Quotations Envelope 06 05 17 07 16 18 Initiatives barbantes, linhas, lastex e cordões SUB 263 - 5 / Aquisição de Component 1: Sustainable Request for Single Stage - One 2019-11- 2019-11- 2019-11- 2019-11- 2020-01- 2020-02- miçangas para produção de TF / 18765 and Adaptive Community Post Limited 1,048.58 Completed Quotations Envelope 06 19 17 21 16 01 artesanato Initiatives SUB 100 - 3 / Aquisição de Component 1: Sustainable Community 2017-12- 2018-01- 2018-01- 2018-01- 2018-01- 2018-02- kit equipamento proteção TF / 18765 and Adaptive Community Post Driven Limited 0.00 Canceled 20 03 10 15 22 20 individual. Initiatives Development SUB 100-18 / Aquisição de Component 1: Sustainable Pending vestimentas de proteção Request for Single Stage - One 2019-11- 2019-11- 2020-01- TF / 18765 and Adaptive Community Post Limited 0.00 Implement individual: calças, camisetas Quotations Envelope 08 21 20 Initiatives ation e chapéus com proteção Component 1: Sustainable Pending SUB 100-19 / Aquisição de Request for Single Stage - One 2019-11- 2019-11- 2020-01- TF / 18765 and Adaptive Community Post Limited 0.00 Implement Botas - EPI's Quotations Envelope 08 21 20 Initiatives ation Component 1: Sustainable SUB 110-36 / Aquisição de Request for Single Stage - One 2019-11- 2019-11- 2019-11- 2019-12- 2020-01- 2019-12- TF / 18765 and Adaptive Community Post Limited 1,064.57 Completed adubo orgânico para plantio Quotations Envelope 08 21 21 04 20 20 Initiatives SUB 268 - 8 / Aquisição de material de construção para Component 1: Sustainable Request for Single Stage - One 2019-11- 2019-11- 2019-12- espaço sede para a TF / 18765 and Adaptive Community Post Limited 0.00 Canceled Quotations Envelope 08 21 21 cooperativa/ associação Initiatives indígena SUB 166 SC 004 / Aquisição de Seladora de Component 1: Sustainable embalagens plásticas a Request for Single Stage - One 2019-11- 2019-11- 2020-01- TF / 18765 and Adaptive Community Post Limited 0.00 Canceled vácuo e despolpadeira de Quotations Envelope 04 17 16 Initiatives fruta , para estruturação da cozinha de processamento. SUB 74-13 / Aquisição de Component 1: Sustainable Request for Single Stage - One 2017-09- 2017-10- 2017-12- câmera de ação, TF / 18765 and Adaptive Community Post Limited 0.00 Canceled Quotations Envelope 08 05 06 profissional. Initiatives SUB 74-14 / Aquisição de Component 1: Sustainable Request for Single Stage - One 2017-08- 2017-08- 2017-09- utensílios para cozinha TF / 18765 and Adaptive Community Post Limited 0.00 Canceled Quotations Envelope 07 21 14 comunitária Initiatives SUB 74-15 / Aquisição de Component 1: Sustainable Request for Single Stage - One 2017-08- 2017-08- 2017-09- kits de material didático TF / 18765 and Adaptive Community Post Limited 0.00 Canceled Quotations Envelope 07 21 14 para Oficinas Initiatives Component 1: Sustainable SUB 74-17 / Aquisição de Request for Single Stage - One 2017-08- 2017-09- 2017-10- TF / 18765 and Adaptive Community Post Limited 0.00 Canceled calças e botas Quotations Envelope 25 08 30 Initiatives SUB 47-5 / Aquisição de kit de materiais didáticos Component 1: Sustainable (caneta,papel Request for Single Stage - One 2019-03- 2019-03- 2019-04- TF / 18765 and Adaptive Community Post Limited 0.00 Canceled madeira,pastas, cartolina, Quotations Envelope 05 19 08 Initiatives lápis de cor,bloco de anotação, borracha,lápis de escrever, pincel e papel A4 SUB 173 - 13 / Aquisição de material de construção Component 1: Sustainable Request for Single Stage - One 2019-11- 2019-11- 2019-12- 2019-12- 2020-01- 2019-12- (complemento) para TF / 18765 and Adaptive Community Post Limited 1,214.10 Completed Quotations Envelope 23 26 05 09 04 17 estruturação da unidade de Initiatives beneficiamento comunitária SUB 47-10 / Aquisição de materiais de construção para conclusão dos Component 1: Sustainable Request for Single Stage - One 2019-11- 2019-11- 2019-12- 2019-12- 2019-12- 2019-12- banheiros e parte do TF / 18765 and Adaptive Community Post Limited 1,340.67 Completed Quotations Envelope 23 22 04 03 19 05 acabamento da unidade de Initiatives beneficiamento como forros, areia, cimento, entre outros. SUB 98-20 / Aquisição de Component 1: Sustainable Request for Single Stage - One 2019-11- 2020-01- 2019-12- 2020-02- 2020-05- 2020-02- material de irrigação para TF / 18765 and Adaptive Community Post Limited 1,134.54 Completed Quotations Envelope 22 31 03 17 31 24 viveiro e horta comunitária Initiatives SUB 25-18 / Aquisição de Component 1: Sustainable Pending Request for Single Stage - One 2019-11- 2019-12- 2020-01- materiais de construção TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 25 06 20 para obra do galpão Initiatives ation comunitário Component 1: Sustainable SUB 98-19 / Aquisição de Request for Single Stage - One 2018-12- 2020-02- 2018-12- 2020-03- 2019-01- 2020-03- TF / 18765 and Adaptive Community Post Limited 4,082.13 Completed materiais de construção Quotations Envelope 01 18 22 04 21 09 Initiatives SUB 210- 7 / Aquisição de materiais para implantação de hortas: adubo organico, Cálcario agricola, tesoura Component 1: Sustainable Pending de poda, Rolo tela de Arame Request for Single Stage - One 2019-12- 2020-01- 2020-02- TF / 18765 and Adaptive Community Post Limited 0.00 Implement 1,80x50m, exadao com Quotations Envelope 17 10 10 Initiatives ation cabo, enxada com cabo, cavadeira articulada, mangueira 1/3 para irrigacao de gotejamento, boia de caixa d'água SUB 210- 8 / Aquisição de Component 1: Sustainable Request for Single Stage - One 2019-12- 2019-12- 2020-01- 2019-12- 2020-02- 2020-01- material para produção de TF / 18765 and Adaptive Community Post Limited 1,783.17 Completed Quotations Envelope 17 09 03 23 04 13 artesanato Initiatives SUB 224 SC 003 / Aquisição de equipamentos Component 1: Sustainable Under para gestão do projeto e Request for Single Stage - One 2019-12- 2019-12- 2020-01- 2020-02- TF / 18765 and Adaptive Community Post Limited 0.00 Implement uso da brigada voluntária: Quotations Envelope 24 20 10 10 Initiatives ation Gps, Rádio comunicador e Câmera fotográfica. SUB 201- 3 / Aquisição de Gêneros alimentícios para Realizar o resgate e o Component 1: Sustainable fortalecimento da festa pon Request for Single Stage - One 2019-12- 2019-12- 2020-01- 2019-12- 2020-03- 2019-12- TF / 18765 and Adaptive Community Post Limited 1,831.82 Completed hy pry (bola confeccionada Quotations Envelope 13 17 03 18 06 27 Initiatives com palha de milho) e resgate e o fortalecimento da festa rurut (esteira). SUB 129 -16 / Aquisição de câmera fotográfica, câmera Component 1: Sustainable Under Request for Single Stage - One 2019-12- 2020-01- 2020-03- filmadora, GPS, móveis de TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 22 29 29 escritório (mesa e cadeiras) Initiatives ation e notebook Component 1: Sustainable SUB 71-13 / Request for Single Stage - One 2019-12- 2020-06- 2020-01- 2020-06- 2020-02- 2020-07- TF / 18765 and Adaptive Community Post Limited 2,522.70 Completed Monocultivador Quotations Envelope 28 09 22 18 21 03 Initiatives Component 1: Sustainable Under SUB 61-25 / Aquisição de Request for Single Stage - One 2020-01- 2020-05- 2020-01- 2020-03- TF / 18765 and Adaptive Community Post Limited 0.00 Implement Estufa de secagem Quotations Envelope 02 26 29 09 Initiatives ation AI2-5 / Aquisição de kits Component 1: Sustainable Pending para agricultura: enxadas, Request for Single Stage - One 2020-01- 2020-01- 2020-03- TF / 18765 and Adaptive Community Post Limited 0.00 Implement picaretas, pás, carrinho de Quotations Envelope 11 25 25 Initiatives ation mão, etc AI2-9 / Aquisição de Component 1: Sustainable Pending Request for Single Stage - One 2020-01- 2020-02- 2020-03- combustível para moto TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 22 01 02 bomba Initiatives ation AI2-12 / Aquisição de Component 1: Sustainable generos alimentícios para Request for Single Stage - One 2020-01- 2020-02- 2020-01- 2020-03- 2020-02- TF / 18765 and Adaptive Community Post Limited 569.32 Signed assembleia geral do povo Quotations Envelope 09 27 24 05 23 Initiatives Terena AI2-13 / Aquisição de câmera fotográfica Component 1: Sustainable Under Request for Single Stage - One 2020-01- 2020-06- 2020-02- 2020-04- profissional e lente para TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 22 10 04 04 fortalecimento/estruturação Initiatives ation Articulação Pacary SUB 56 - 21 / Aquisição de Component 1: Sustainable equipamentos para Request for Single Stage - One 2020-01- 2020-01- 2020-02- 2020-02- 2020-03- 2020-03- TF / 18765 and Adaptive Community Post Limited 2,646.53 Completed funcionamento do poço Quotations Envelope 30 30 13 12 14 13 Initiatives artesiano comunitário. SUB 110-4 / Aquisição de materiais para construção do viveiro e sala de armazenamento de semente Component 1: Sustainable Request for Single Stage - One 2017-09- 2020-01- 2017-10- 2020-02- 2018-01- 2020-03- e reformar do banheiro para TF / 18765 and Adaptive Community Post Limited 2,406.82 Completed Quotations Envelope 23 28 17 21 15 10 dar suporte ao viveiro, Initiatives Materias construção diversos, Ripa plainada de 4metros, Tinta pva branca externa. SUB 110-37 / Aquisição de materiais elétricos para construção do viveiro e sala Component 1: Sustainable Request for Single Stage - One 2020-02- 2020-01- 2020-03- 2020-02- 2020-04- 2020-03- de armazenamento de TF / 18765 and Adaptive Community Post Limited 344.20 Completed Quotations Envelope 07 28 02 17 01 13 semente e reforma do Initiatives banheiro para dar suporte ao viveiro BR-CAA-156151-GO-RFQ / Aquisição de materiais Component 2: Capacity Pending pedagógicos (ingredientes) Request for Single Stage - One 2020-02- 2020-02- 2020-03- TF / 18765 Building and Institutional Post Limited 0.00 Implement específicos para o curso de Quotations Envelope 04 16 17 Strengthening ation plantas medicinais - Plano de Capacitação DGM Brasil BR-CAA-156152-GO-RFQ / Aquisição de materiais de Component 2: Capacity Pending higiente e proteção para Request for Single Stage - One 2020-02- 2020-02- 2020-03- TF / 18765 Building and Institutional Post Limited 0.00 Implement manipulção durante o curso Quotations Envelope 05 17 18 Strengthening ation de plantas medicinais - Plano de Capacitação do DGM Brasil Component 1: Sustainable SUB 134 -16 / Aquisição de Request for Single Stage - One 2020-02- 2020-02- 2020-02- 2020-02- 2020-02- TF / 18765 and Adaptive Community Post Limited 2,842.94 Signed roda d´água com bomba Quotations Envelope 01 11 12 17 27 Initiatives SUB 263 - 6 / Aquisição de equipamentos para estruturação da casa de Component 1: Sustainable Pending Request for Single Stage - One 2020-02- 2020-02- 2020-02- artesanato: 2 armários de TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 07 18 19 aço; geladeira comum 300l; Initiatives ation bebedouro; fogão industrial, com forno à gás. SUB 263 - 7 / Aquisição de Component 1: Sustainable Request for Single Stage - One 2020-02- 2020-02- 2020-02- 2020-02- 2020-02- 2020-03- máquina de costura reta e TF / 18765 and Adaptive Community Post Limited 772.22 Completed Quotations Envelope 04 10 16 12 26 03 máquina de costura Initiatives overlock SUB 216 - 2 / Aquisição de Component 1: Sustainable 3 GPS, 3 Notebooks e 1 Request for Single Stage - One 2020-02- 2020-02- 2020-02- 2020-06- 2020-02- TF / 18765 and Adaptive Community Post Limited 242.70 Signed câmera fotográfica para Quotations Envelope 04 13 14 13 24 Initiatives estruturar o Conselho Terena Component 1: Sustainable SUB 30 - 37 / Aquisição de Request for Single Stage - One 2020-02- 2020-02- 2020-02- 2020-02- 2020-03- 2020-03- TF / 18765 and Adaptive Community Post Limited 2,148.80 Completed Materiais de Construção Quotations Envelope 18 14 26 27 28 19 Initiatives SUB 30 - 38 / Aquisição de Component 1: Sustainable Request for Single Stage - One 2020-03- 2020-05- 2020-04- 2020-05- 2020-06- 2020-08- móveis para escritório, TF / 18765 and Adaptive Community Post Limited 1,049.61 Completed Quotations Envelope 25 19 06 29 05 05 como: armários, mesas e Initiatives cadeiras SUB 268 -2 / Aquisição de material de construção para construção do galpão para Component 1: Sustainable Request for Single Stage - One 2020-03- 2020-09- 2020-04- 2020-10- 2020-05- fabricação de artesanato e TF / 18765 and Adaptive Community Post Limited 3,229.69 Signed Quotations Envelope 25 21 07 07 07 armazenamento da matéria- Initiatives prima e construção da sede da associação. SUB 250-5 / Aquisição de Component 1: Sustainable Pending 10 Armários / Roupeiros, Request for Single Stage - One 2020-03- 2020-04- 2020-06- TF / 18765 and Adaptive Community Post Limited 0.00 Implement Aquisição de 10 estantes de Quotations Envelope 25 19 17 Initiatives ation ferro SUB 195 - 3 / Aquisição de Component 1: Sustainable Pending gêneros alimentícios para Request for Single Stage - One 2020-03- 2020-04- 2020-05- TF / 18765 and Adaptive Community Post Limited 0.00 Implement preparo das refeições Quotations Envelope 25 07 07 Initiatives ation durante atividades do projeto SUB 268 -9 / Aquisição de Component 1: Sustainable Pending ferramentas para produção Request for Single Stage - One 2020-03- 2020-04- 2020-06- TF / 18765 and Adaptive Community Post Limited 0.00 Implement de artesanato: Quotations Envelope 25 06 05 Initiatives ation esmeriladeiras, etc (aquisição complementar) SUB 99 - 20 / Bombas Component 1: Sustainable Pending Request for Single Stage - One 2020-03- 2020-04- 2020-05- Submersa para poço TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 30 22 22 artesiano com placa solar Initiatives ation SUB 120 - 18 / Aquisição Component 1: Sustainable Pending Request for Single Stage - One 2020-04- 2020-04- 2020-05- de celulares par o TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 03 21 21 subprojeto Initiatives ation Component 1: Sustainable Pending SUB 116.25 / Aquisição de Request for Single Stage - One 2020-04- 2020-05- 2020-06- TF / 18765 and Adaptive Community Post Limited 0.00 Implement roçadeira Quotations Envelope 05 02 01 Initiatives ation SUB 113 - 30 / Aquisição Component 1: Sustainable Request for Single Stage - One 2020-04- 2021-01- 2020-05- 2021-01- 2020-06- 2021-05- de equipamentos para TF / 18765 and Adaptive Community Post Limited 2,212.18 Completed Quotations Envelope 17 14 16 25 05 13 extração de mel Initiatives Component 1: Sustainable SUB 113 - 31 / Aquisição Request for Single Stage - One 2020-04- 2021-01- 2020-05- 2021-01- 2020-06- 2021-02- TF / 18765 and Adaptive Community Post Limited 881.48 Completed de Freezers Quotations Envelope 17 06 05 18 04 17 Initiatives BR-CAA-175571-GO-RFQ Component 3: Project Pending / Aquisição de um notebook Request for Single Stage - One 2020-05- 2020-06- 2020-07- TF / 18765 Management, Monitoring Post Limited 0.00 Implement para membro do Comite Quotations Envelope 29 09 09 and Evaluation ation Gestor Nacional SUB 100 - 20 / Aquisição Component 1: Sustainable Request for Single Stage - One 2020-05- 2020-07- 2020-06- 2020-07- 2020-07- 2020-08- de tachos de ferro para TF / 18765 and Adaptive Community Post Limited 3,529.30 Completed Quotations Envelope 28 10 11 22 11 12 produção de farinha Initiatives SUB 129 - 17 / Aquisição de peças de reposição para Component 1: Sustainable Request for Single Stage - One 2020-06- 2020-06- 2020-06- 2020-06- 2020-07- 2020-08- veículo de apoio às TF / 18765 and Adaptive Community Post Limited 2,629.73 Completed Quotations Envelope 04 12 15 16 15 05 atividades de vigilância e Initiatives fiscalização da Terra Indígena Krahô. SUB 91-11 / Aquisição de Component 1: Sustainable implemento agrícola - Request for Single Stage - One 2020-06- 2020-06- 2020-07- 2020-07- 2020-07- 2020-09- TF / 18765 and Adaptive Community Post Limited 1,837.78 Completed Grade Aradora Mecânica Quotations Envelope 26 19 16 01 22 11 Initiatives para o subprojeto 91 SUB 109-8 / CT109.8 Component 1: Sustainable Pending Aquisição de Moinho para Request for Single Stage - One 2017-09- 2017-09- 2017-11- TF / 18765 and Adaptive Community Post Limited 0.00 Implement unidade de beneficiamento Quotations Envelope 05 29 28 Initiatives ation do subprojeto SUB 109-5 / CT109.5 Component 1: Sustainable Pending Aquisição de equipamentos Request for Single Stage - One 2017-09- 2017-10- 2018-02- TF / 18765 and Adaptive Community Post Limited 0.00 Implement para a unidade de Quotations Envelope 11 04 01 Initiatives ation beneficiamento SUB 170 - 8 / Aquisição de Component 1: Sustainable ferramentas agrícolas para Request for Single Stage - One 2020-07- 2020-07- 2020-07- 2020-07- 2020-08- 2020-08- TF / 18765 and Adaptive Community Post Limited 1,958.62 Completed implementação dos Quotations Envelope 13 13 25 22 24 03 Initiatives pomares e roça coletiva SUB 170 - 9 / Aquisição de Component 1: Sustainable gêneros alimentícios Request for Single Stage - One 2020-07- 2020-07- 2020-07- 2020-07- 2020-08- 2020-08- TF / 18765 and Adaptive Community Post Limited 221.54 Completed durante o trabalho na Quotations Envelope 13 13 25 22 24 03 Initiatives criação de pomares e roça coletiva SUB 2120 - 5 / Aquisição de freezer horizontal 385 Component 1: Sustainable Pending Request for Single Stage - One 2020-07- 2020-07- 2020-08- litros, Geladeira 400 L para TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 17 25 24 estruturação de cozinha Initiatives ation comunitária. Page 9 SUB 2120 - 6 / Aquisição de balança digital, seladora Component 1: Sustainable Pending Request for Single Stage - One 2020-07- 2020-07- 2020-08- automática industrial, TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 19 28 27 despolpadeira de frutas 10 Initiatives ation litros, seladora à vácuo. SUB 211 SC 010 / Component 1: Sustainable Pending Aquisição de: Request for Single Stage - One 2019-07- 2019-07- 2019-08- TF / 18765 and Adaptive Community Post Limited 0.00 Implement Liquidificadores de alta Quotations Envelope 09 17 16 Initiatives ation rotação, batedeira industrial e fogão industrial SUB 211 - SC 011 / Component 1: Sustainable Pending Request for Single Stage - One 2020-07- 2020-07- 2020-08- Aquisição de máquina para TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 17 25 24 fabricação de sorvete e Initiatives ation picolé SUB 91 - 10 / Aquisição de equipamentos Component 1: Sustainable Pending Request for Single Stage - One 2020-07- 2020-08- 2020-08- complementares para TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 22 03 23 instalação do bombeamento Initiatives ation de água SUB 241-7 / Aquisição de Component 1: Sustainable Pending Request for Single Stage - One 2020-08- 2020-08- 2020-09- bomba d'água com placas TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 03 17 16 solares Initiatives ation SUB 241-8 / Aquisição de Component 1: Sustainable Pending Request for Single Stage - One 2020-08- 2020-08- 2020-09- kit para irrigação e TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 01 13 12 mangueira Initiatives ation AI2 - 14 / Kit de irrigação Component 1: Sustainable Request for Single Stage - One 2020-08- 2020-10- 2020-08- 2020-10- 2020-09- 2021-01- para instalar o campo de TF / 18765 and Adaptive Community Post Limited 1,097.02 Completed Quotations Envelope 03 19 15 22 14 28 sementes Initiatives AI2 - 15 / Aquisição de Component 1: Sustainable material de construção para Request for Single Stage - One 2020-08- 2020-10- 2020-08- 2020-10- 2020-08- 2021-01- TF / 18765 and Adaptive Community Post Limited 2,167.06 Completed instalação de reservatório Quotations Envelope 03 08 12 16 27 28 Initiatives de água SUB 170 - 10 / Aquisição Component 1: Sustainable Request for Single Stage - One 2020-08- 2020-07- 2020-08- 2020-08- 2020-09- 2020-08- de mudas para TF / 18765 and Adaptive Community Post Limited 1,014.92 Completed Quotations Envelope 03 31 17 05 06 13 reflorestamento Initiatives AI2- 16 / Aquisição de Component 1: Sustainable Request for Single Stage - One 2020-08- 2020-08- 2020-08- 2020-09- 2020-09- 2020-09- material para instalação de TF / 18765 and Adaptive Community Post Limited 1,939.96 Completed Quotations Envelope 09 25 20 03 19 25 viveiros Initiatives Component 1: Sustainable Pending AI2 -18 / Aquisição de Request for Single Stage - One 2020-08- 2020-08- 2020-09- TF / 18765 and Adaptive Community Post Limited 0.00 Implement mudas e sementes variadas Quotations Envelope 09 23 12 Initiatives ation SUB 45 - 26 / Aquisição de equipamentos de Component 1: Sustainable Pending Request for Single Stage - One 2020-08- 2020-09- 2020-10- informática: computador de TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 26 15 15 mesa, notebook, projetor Initiatives ation multimídia, entre outros SUB 124 - 15 / Aquisição Component 1: Sustainable Pending Request for Single Stage - One 2020-08- 2020-09- 2020-10- de micro-trator com TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 26 09 09 caçamba Initiatives ation AI2 - 19 / Aquisição de aparelhos eletrônicos para Component 1: Sustainable Pending Request for Single Stage - One 2020-08- 2020-09- 2020-11- gravação e eventos, como: TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 26 08 07 celular, caixa de som, tripé Initiatives ation e microfone. AI2 - 20 / Aquisição de equipamentos para Component 1: Sustainable Pending gravação, filmagem e Request for Single Stage - One 2020-08- 2020-09- 2020-11- TF / 18765 and Adaptive Community Post Limited 0.00 Implement fotografia como: lente para Quotations Envelope 26 08 07 Initiatives ation câmera, tripé, iluminador, bateria para câmera. AI2 - 21 / Aquisição de Component 1: Sustainable Request for Single Stage - One 2020-08- 2020-08- 2020-09- 2020-09- 2020-10- 2021-01- itens para instalação de TF / 18765 and Adaptive Community Post Limited 2,869.94 Completed Quotations Envelope 26 25 06 29 06 28 sistema de irrigação Initiatives AI2 - 22 / Aquisição de combustível para manutenção de roça de Component 1: Sustainable Pending Request for Single Stage - One 2020-08- 2020-09- 2020-10- subsistência para TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 29 03 03 fortalecimento de segurança Initiatives ation alimentar nas terras indígenas Cachoeirinha, Lalima e Pilad Rebuá SUB 179 - 10 / Aquisição Component 1: Sustainable Request for Single Stage - One 2020-04- 2020-06- 2020-05- 2020-06- 2020-05- 2020-08- de materiais para TF / 18765 and Adaptive Community Post Limited 2,011.04 Completed Quotations Envelope 17 19 06 26 26 05 construção dos galinheiros Initiatives SUB 179 - 11 / Aquisição Component 1: Sustainable Pending Request for Single Stage - One 2020-09- 2020-09- 2020-10- de insumos para TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 11 25 15 estruturação das hortas Initiatives ation comunitárias Component 1: Sustainable SUB 108 - 30 / Aquisição Request for Single Stage - One 2020-10- 2020-10- 2020-10- 2020-10- 2020-12- 2020-11- TF / 18765 and Adaptive Community Post Limited 1,343.02 Completed de gerador Quotations Envelope 03 03 24 03 23 18 Initiatives SUB 123 - 13 / Aquisição Component 1: Sustainable Pending Request for Single Stage - One 2020-10- 2020-10- 2020-12- de materiais para produção TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 08 21 20 de artesanato - miçangas Initiatives ation COVID 19 - RS27 PRO TERRA / Aquisição de itens Component 1: Sustainable Pending de higiene e proteção Request for Single Stage - One 2020-10- 2020-10- 2020-11- TF / 18765 and Adaptive Community Post Limited 0.00 Implement individual: álcool em gel, Quotations Envelope 09 24 13 Initiatives ation água sanitária, sabão em barra, máscaras, detergente e sabonete COVID 19 - RS50 PEDRA PRETA / Aquisição de itens de higiene e proteção Component 1: Sustainable Pending Request for Single Stage - One 2020-10- 2020-10- 2020-11- individual: máscaras, água TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 09 24 13 sanitária, álcool em gel, Initiatives ation sabonete, detergente, sabão em pó e papel higiênico. COVID 19 - RS54 CIMQCB / Aquisição de itens de higiene e proteção Component 1: Sustainable Pending Request for Single Stage - One 2020-10- 2020-10- 2020-11- individual: medidor de TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 09 24 13 temperatura, totem para Initiatives ation alcool em gel, alcool em gel, máscaras, água sanitária e sabão em barra COVID 19 - RS44 ASSEMA / Aquisição de itens de higiene e proteção Component 1: Sustainable Pending Request for Single Stage - One 2020-10- 2020-10- 2020-11- individual: sabão de coco, TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 09 24 13 sabonete, alcool gel, água Initiatives ation sanitária, desinfetante, sabão líquido, sabão em pó, máscaras de tecido SUB 110 - 37 / Aquisição Component 1: Sustainable de uma moto serra e um Request for Single Stage - One 2020-10- 2020-10- 2020-12- TF / 18765 and Adaptive Community Post Limited 0.00 Canceled triturador de galhos e Quotations Envelope 09 31 30 Initiatives troncos para equipar a associação AI2 - 23 / Aquisição de Component 1: Sustainable 2020-10- 2020-10- 2020-10- 2020-10- 2020-10- 2020-10- 2020-12- 2020-11- sementes orgânicas e não- TF / 18765 and Adaptive Community Post Direct Selection Direct 940.72 Completed 11 20 16 24 22 27 21 05 transgênicas certificadas. Initiatives SUB 28 - 18 / Aquisição de Component 1: Sustainable Pending Request for Single Stage - One 2020-10- 2020-11- 2020-12- materiais para sistema de TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 28 08 08 irrigação Initiatives ation SUB 45 - 27 / Aquisição de Component 1: Sustainable mobiliário para escritório, Request for Single Stage - One 2020-10- 2020-11- 2020-11- 2020-11- 2020-12- 2020-12- TF / 18765 and Adaptive Community Post Limited 1,237.34 Completed incluindo mesas, cadeiras, Quotations Envelope 28 25 13 26 13 15 Initiatives armários. SUB 116 - 38 / Aquisição Component 1: Sustainable Under de material para construção Request for Single Stage - One 2020-10- 2020-11- 2020-11- 2020-12- TF / 18765 and Adaptive Community Post Limited 7,711.33 Implement do galpão de Quotations Envelope 28 24 13 13 Initiatives ation beneficiamento do azeite COVID 19 - RS68 PACARY / Aquisição de material de higiene e limpeza: xampu, condicionador, desodorante, Component 1: Sustainable Pending sabonetes, óleo de Request for Single Stage - One 2020-10- 2020-11- 2020-12- TF / 18765 and Adaptive Community Post Limited 0.00 Implement macauba, absorventes de Quotations Envelope 28 05 05 Initiatives ation pano, sabão em barra, desifentante, bucha vegetal, álcool líquido, álcool em gel, máscaras, sacola de pano e material para xarope COVID 19 - RS11 MIQCB / Aquisição de itens de higiene e proteção individual: água sanitária, Component 1: Sustainable Pending Request for Single Stage - One 2020-10- 2020-11- 2020-12- detergente líquido, sabão TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 28 05 05 em barra, alcool em gel para Initiatives ation mãos, máscaras de tecido, creme dental, embalagens plásticas para alcool em gel. COVID 19 - RS61 GORUTUBA / Aquisição de Component 1: Sustainable Pending Request for Single Stage - One 2020-10- 2020-11- 2020-12- itens de higiene e proteção TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 28 05 05 individual: máscaras, água Initiatives ation sanitária, sabão neutro e álcool em gel. COVID 19 - RS47 ENAWENE / Aquisição de itens de higiene e proteção Component 1: Sustainable Pending Request for Single Stage - One 2020-10- 2020-11- 2020-12- individual: sabão em barra, TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 28 05 05 álcool em gel para mãos, Initiatives ation máscaras de tecido, sabonete em barra e vitamina C efervescente COVID 19 - RS2 NAX / Aquisição de ferramentas Component 1: Sustainable Pending para roça: machado, foice, Request for Single Stage - One 2020-10- 2020-11- 2020-12- TF / 18765 and Adaptive Community Post Limited 0.00 Implement enxada, rastelo de ferro, Quotations Envelope 28 06 06 Initiatives ation facão, lima, carrinho de mão, agulha para saco, fitilho de plástico. COVID 19 - RS35 HANAITI / Aquisição de itens de informática e equipamentos para estruturar a Component 1: Sustainable Pending Request for Single Stage - One 2020-10- 2020-11- 2020-12- associação: notebbok, TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 28 08 08 transmissor de radio, mesa Initiatives ation digital, microfones, mesa, cadeira, antena de rádio, kit som, alcool em gel para mãos SUB 123 - 16 / Aquisição Component 1: Sustainable de materiais para produção Request for Single Stage - One 2020-11- 2020-11- 2020-12- 2020-12- 2021-01- 2020-12- TF / 18765 and Adaptive Community Post Limited 1,302.52 Completed de artesanato - Quotations Envelope 22 25 12 04 01 22 Initiatives miçangas III COVID 19 - RS48 ISA / Aquisição de carrinho de Component 1: Sustainable Pending mão, facão, peneira fina, Request for Single Stage - One 2020-11- 2020-12- 2020-12- TF / 18765 and Adaptive Community Post Limited 0.00 Implement bacia, caldeirão, faca Quotations Envelope 21 07 27 Initiatives ation peixeira, máscara de tecido, álcool em gel e álcool 70 SUB 123 17 / Aquisição de Component 1: Sustainable Request for Single Stage - One 2020-11- 2020-11- 2020-12- 2020-11- 2021-02- combustível e oleo para as TF / 18765 and Adaptive Community Post Limited 2,013.95 Signed Quotations Envelope 22 18 06 24 04 atividades do projeto Initiatives COVID 19 - RS26 AMANU / Aquisição de seladora e Component 1: Sustainable Pending Request for Single Stage - One 2020-11- 2020-12- 2020-12- embalagens, à vácuo, para TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 22 11 12 apoio em decorrência da Initiatives ation COVID SUB 98 - 21 / Aquisição de Component 1: Sustainable Request for Single Stage - One 2020-11- 2021-01- 2020-12- 2021-01- 2021-01- sombrite, perfurador de TF / 18765 and Adaptive Community Post Limited 1,342.09 Signed Quotations Envelope 22 18 14 26 13 solo e roçadeira Initiatives Component 1: Sustainable SUB 110-38 / Aquisição de Request for Single Stage - One 2020-11- 2020-12- 2020-12- 2020-12- 2021-01- 2020-12- TF / 18765 and Adaptive Community Post Limited 2,007.03 Completed triturador Quotations Envelope 23 03 13 08 12 16 Initiatives COVID 19 - RS70 APOINME / Ferramentas para plantio, abastecimento de água: moto serra, sabre, corrente, Component 1: Sustainable Pending caixa d'água, calha, suporte Request for Single Stage - One 2020-11- 2020-12- 2021-01- TF / 18765 and Adaptive Community Post Limited 0.00 Implement de calha, tela Quotations Envelope 26 05 04 Initiatives ation sombreamento, tela galinheiro, válvula, mangueira, enxada, foice, cavadeira, rastelo, regador, tubo e adesivo PVC, serrote, alicate. SUB 224 - SC 004 / Component 1: Sustainable Pending Request for Single Stage - One 2020-11- 2020-12- 2021-01- Aquisição de gêneros TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 28 12 11 alimentícios para atividades Initiatives ation do projeto COVID 19 - RS14 SÃO MODESTO / Aquisição de itens de higiene e proteção Component 1: Sustainable Pending Request for Single Stage - One 2020-11- 2020-12- 2021-01- individual: álcool em gel, TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 29 07 06 álcool líquido, sabão em Initiatives ation barra, detergente, sabão em pó e máscara de tecido. SUB 109 - 16 / Aquisição Component 1: Sustainable Pending Request for Single Stage - One 2020-12- 2020-12- 2021-01- de telhas tipo sanduíche TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 16 29 28 para reforma do entreposto Initiatives ation SUB 129 - 18 / Aquisição Component 1: Sustainable Pending Request for Single Stage - One 2020-12- 2020-12- 2021-01- de miçangas para produção TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 18 27 16 de artesanato Initiatives ation COVID 19 - RS59 RAIS / Aquisição de filtros de Component 1: Sustainable Pending Request for Single Stage - One 2020-12- 2020-12- 2021-01- barros, álcool em gel, água TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 13 21 20 sanitária, sabão em barra, Initiatives ation sabonete em barra e borrifadores COVID 19 - RS22 SUMARÉ PERUAÇÚ / Aquisição de itens de higiene e proteção Component 1: Sustainable Pending Request for Single Stage - One 2020-12- 2020-12- 2021-01- individual: álcool em gel, TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 13 21 20 água sanitária, sabonete Initiatives ation líquido para as mãos, luva descartável e máscara descartável COVID 19 - RS43 REDE CERRADO / Aquisição de Component 1: Sustainable Pending equipamentos de Request for Single Stage - One 2020-12- 2020-12- 2021-01- TF / 18765 and Adaptive Community Post Limited 0.00 Implement informática: notebook, Quotations Envelope 13 24 23 Initiatives ation celular, impressora, antena de internet, hd externo. SUB 125 - 18 / Aquisição Component 1: Sustainable Request for Single Stage - One 2020-12- 2021-03- 2021-01- 2021-03- 2021-01- de materiais de materiais de TF / 18765 and Adaptive Community Post Limited 1,239.59 Signed Quotations Envelope 24 09 03 31 13 escritório Initiatives Component 1: Sustainable Pending SUB 181 - 4 / Aquisição de Request for Single Stage - One 2020-12- 2021-01- 2021-02- TF / 18765 and Adaptive Community Post Limited 0.00 Implement mudas para plantio Quotations Envelope 24 06 05 Initiatives ation SUB 211 - 11 / Aquisição de eletrodomésticos para Component 1: Sustainable Pending estruturação da cozinha Request for Single Stage - One 2020-12- 2021-01- 2021-02- TF / 18765 and Adaptive Community Post Limited 0.00 Implement comunitária: geladeira, Quotations Envelope 25 05 04 Initiatives ation freezers, micro-ondas e máquina de lavar SUB 181 - 5 / Aquisição de Component 1: Sustainable Pending Request for Single Stage - One 2021-01- 2021-01- 2021-02- kit de ferramentas para TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 06 19 18 plantio Initiatives ation SUB 25 - 19 / Aquisição de Component 1: Sustainable Request for Single Stage - One 2021-01- 2021-01- 2021-01- 2021-02- 2021-02- 2021-02- portas e janelas para galpão TF / 18765 and Adaptive Community Post Limited 567.91 Completed Quotations Envelope 16 15 27 03 26 10 comunitário Initiatives COVID 19 - RS52 NROZAWI / Aquisição de itens de higiene e proteção: creme Component 1: Sustainable Pending Request for Single Stage - One 2021-01- 2021-02- 2021-03- dental, escova de dente, TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 27 04 06 sabão em barra, água Initiatives ation sanitária, máscaras, luvas, termômetros, sabonete, sabão líquido. BR-CAA-215507-GO-RFQ Component 3: Project Pending / Aquisição de climatizador Request for Single Stage - One 2021-01- 2021-02- 2021-03- TF / 18765 Management, Monitoring Post Limited 0.00 Implement para utilização no escritório Quotations Envelope 29 11 13 and Evaluation ation da agência executora SUB 25-1 / CQ25.1 Component 1: Sustainable Aquisição de mudas plantas Request for Single Stage - One 2018-04- 2018-05- 2018-07- TF / 18765 and Adaptive Community Post Limited 0.00 Canceled apropriadas para Quotations Envelope 06 09 08 Initiatives recuperação de áreas degradadas SUB 26-10 / CT26.10 Component 1: Sustainable Request for Single Stage - One 2017-08- 2017-08- 2017-09- Aquisicao de materiais TF / 18765 and Adaptive Community Post Limited 0.00 Canceled Quotations Envelope 02 25 19 didaticos Initiatives Component 1: Sustainable SUB 26-5 / CT26.5 Request for Single Stage - One 2017-06- 2018-05- 2017-07- 2019-03- TF / 18765 and Adaptive Community Post Limited 0.00 Canceled Aquisição de GPS Quotations Envelope 30 28 18 10 Initiatives FS_1.5 01 / Aquisição de Component 1: Sustainable Pending Request for Single Stage - One 2021-04- 2021-04- 2021-06- saca de sementes de milho TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 04 26 25 e feijão Initiatives ation Page 10 AI2 - 24 / Aquisição de material de irrigação para Component 2: Capacity Pending Request for Single Stage - One 2021-04- 2021-04- 2021-05- Aldeia Tuxá (MG): aspersor, TF / 18765 Building and Institutional Post Limited 0.00 Implement Quotations Envelope 03 14 14 tubo, registro, curva, entre Strengthening ation outros. AI2 - 25 / Aquisição de Component 2: Capacity Pending Request for Single Stage - One 2021-04- 2021-04- 2021-05- arames e telas para TF / 18765 Building and Institutional Post Limited 0.00 Implement Quotations Envelope 03 14 14 instalação na Aldeia Tuxá Strengthening ation (MG) FS_1.3 03 / Aquisição de câmera filmadora, câmera Component 1: Sustainable Pending Request for 2021-04- 2021-04- 2021-06- fotográfica e câmera de TF / 18765 and Adaptive Community Post 0.00 Implement Quotations 04 26 25 ação e Aquisição de kit para Initiatives ation vídeo conferência. FS_1.2 01 / Aquisição de equipamentos de informática, sendo: notebooks, computadores tipo desktop, nobreak, Component 1: Sustainable Pending Request for Single Stage - One 2021-04- 2021-05- 2021-07- mouses sem fio e kits de TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 27 25 24 mouse e teclado sem fio; Initiatives ation equipamentos para projeção de imagens (projetor e tela); aquisição de impressoras e aquisição de smartphones. SUB 109 - 18 / Aquisição Component 1: Sustainable Pending de estrutura metálica para Request for Single Stage - One 2021-04- 2021-05- 2021-06- TF / 18765 and Adaptive Community Post Limited 0.00 Implement instalação do telhado do Quotations Envelope 29 14 13 Initiatives ation entreposto do babaçu SUB 16 - 27 / Aquisição de Component 1: Sustainable Pending bomba para retirada de Request for Single Stage - One 2021-05- 2021-05- 2021-06- TF / 18765 and Adaptive Community Post Limited 0.00 Implement água do poço artesiano Quotations Envelope 01 16 15 Initiatives ation instalado na comunidade SUB 195 - 4 / Aquisição de gêneros alimentícios para Component 1: Sustainable Pending Request for Single Stage - One 2021-05- 2021-05- 2021-06- oficina formativa, com TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 14 27 26 representantes mulheres Initiatives ation das aldeias da TI Sangradouro FS_26 1.1 / Aquisição de Component 2: Capacity Pending Request for Single Stage - One 2021-05- 2021-06- 2021-07- balanças digitais e seladoras TF / 18765 Building and Institutional Post Limited 0.00 Implement Quotations Envelope 21 07 07 de pedal Strengthening ation FS_25 1.1 1 / Aquisição de forno elétrico para torrar Component 2: Capacity Pending farinha, aquisição de prensa Request for Single Stage - One 2021-05- 2021-06- 2021-09- TF / 18765 Building and Institutional Post Limited 0.00 Implement de ferro para produção de Quotations Envelope 31 18 16 Strengthening ation farinha e aquisição de ralador de mandioca FS_4 1.1 / Aquisição de Component 2: Capacity Pending ferramentas agrícolas: Request for Single Stage - One 2021-05- 2021-06- 2021-07- TF / 18765 Building and Institutional Post Limited 0.00 Implement enxadas, foices e Quotations Envelope 28 10 10 Strengthening ation plantadeiras manuais. FS_195 1.1_SUB 99 - 22 / Component 1: Sustainable Pending Request for Single Stage - One 2021-05- 2021-06- 2021-08- Aquisição de geradores à TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 31 21 20 energia a diesel Initiatives ation BR-CAA-238190-GO-RFQ / Aquisição de Component 3: Project Pending equipamentos para internet Request for Single Stage - One 2021-06- 2021-06- 2021-08- TF / 18765 Management, Monitoring Post Limited 0.00 Implement rural - apoio membro do Quotations Envelope 11 30 29 and Evaluation ation CGN: antena, cabos, conectores, torre, swicht, entre outros. BR-CAA-238191-GO-RFQ / Aquisição de Component 3: Project Pending Request for Single Stage - One 2021-06- 2021-06- 2021-08- equipamentos para internet TF / 18765 Management, Monitoring Post Limited 0.00 Implement Quotations Envelope 11 30 29 rural - apoio membro do and Evaluation ation CGN: antena, modem e roteador SUB 90 - 7 / Aquisição de Component 1: Sustainable Pending impressora para impressão Request for Single Stage - One 2021-06- 2021-06- 2021-06- TF / 18765 and Adaptive Community Post Limited 0.00 Implement de lotes e validade, para Quotations Envelope 15 27 30 Initiatives ation rotulagem de produtos SUB 98 - 22 / Aquisição de Component 1: Sustainable Pending material de construção Request for Single Stage - One 2021-06- 2021-07- 2021-08- TF / 18765 and Adaptive Community Post Limited 0.00 Implement complementar para Quotations Envelope 20 12 11 Initiatives ation construção do galpão SUB 109 - 19 / Aquisição de material de construção Component 1: Sustainable Pending para fase de acabamento da Request for Single Stage - One 2021-06- 2021-06- 2021-07- TF / 18765 and Adaptive Community Post Limited 0.00 Implement construção do galpão do Quotations Envelope 16 29 29 Initiatives ation entreposto de babaçu - materiais elétricos SUB 268 - 11 / Aquisição Component 1: Sustainable Pending de uma betoneira para Request for Single Stage - One 2021-06- 2021-07- 2021-07- TF / 18765 and Adaptive Community Post Limited 0.00 Implement auxiliar nas obras do Quotations Envelope 18 01 31 Initiatives ation galpão, na comunidade SUB 109 - 20 / Aquisição de materiais hidráulicos e Component 1: Sustainable Pending materiais de construção Request for Single Stage - One 2021-06- 2021-07- 2021-08- TF / 18765 and Adaptive Community Post Limited 0.00 Implement (para reservatório) para fase Quotations Envelope 20 16 15 Initiatives ation final de construção de entreposto de babaçu. NON CONSULTING SERVICES Activity Reference No. Actual Draft Pre- Draft Bidding Specific Proposal Bid Evaluation Loan / Credit Market Procurement Prequalificati Process Prequalification Bidding Documents Contract / Description Component Review Type Method Amount qualification Document / Procurement Notice Submission / Report and Signed Contract No. Approach Process on (Y/N) Status Evaluation Report as Issued Completion (US$) Documents Justification / Invitation Opening / Minutes Recommendation Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned for Award Actual Planned Actual Planned Actual BR-CAA-3291-NC-RFB / contratacao de empresa especializada em servicos de agenciamento de viagens Component 1: Sustainable Single Stage - One 2015-06- 2015-07- 2015-07- 2019-09- 2015-09- 2015-09- 2015-10- 2015-11- 2015-12- 2015-11- 2016-12- e fornecimento de TF / 18765 and Adaptive Community Post Request for Bids Open - National 291,879.28 Signed Envelope 24 08 09 20 01 01 28 09 16 24 16 passagens aereas regionais Initiatives nacionais e internacionais e passagens terrestres para realizacao das atividades BR-CAA-3309-NC-RFQ / contratacao de servico de nao consultoria durante primeiro edital para Component 2: Capacity producao de videos com Request for Single Stage - One 2016-12- 2016-12- 2017-01- 2017-01- 2018-04- TF / 18765 Building and Institutional Post Limited 14,630.04 Signed captacao de imagens e Quotations Envelope 21 22 18 25 13 Strengthening decupagem e roteiro e edicao e tratamento de imagem e finalizacao de quatro videos curtos e um video institucional BR-CAA-3319-NC-RFQ / contratacao de empresa especializada em servicos Component 3: Project Pending de auditoria externa para Request for Single Stage - One 2017-01- 2017-02- 2018-02- TF / 18765 Management, Monitoring Post Limited 0.00 Implement auditar os documentos Quotations Envelope 04 02 08 and Evaluation ation projeto referente ao exercicio dois mil e quinze e dois mil e dezesseis BR-CAA-3257-NC-RFQ / contratacao de servico de nao consultoria para de impressao cartilhas Component 2: Capacity Pending Request for Single Stage - One 2017-02- 2017-03- 2019-03- tematicas para apresentacao TF / 18765 Building and Institutional Post Limited 0.00 Implement Quotations Envelope 19 31 27 do projeto e publicacao da Strengthening ation avaliacao dos resultados por edicao dos relatorios finais do primeiro edital BR-CAA-3289-NC-RFQ / contratacao de servico para producao de pecas graficas de cartilha com construcao Component 2: Capacity Pending de layout e definicao de Request for Single Stage - One 2017-02- 2017-03- 2017-06- TF / 18765 Building and Institutional Post Limited 0.00 Implement fonte e espacamento e Quotations Envelope 12 20 18 Strengthening ation marca de texto e elemento grafico e diretrizes de diagramacao do material que sera diagramado pela equipe BR-CAA-4658-NC-RFQ / contratacao de empresa para prestacao de servico Component 3: Project nao continuados para Request for Single Stage - One 2015-12- 2015-12- 2015-12- 2015-12- 2016-02- 2016-02- TF / 18765 Management, Monitoring Post Limited 787.27 Completed realizacao de um evento de Quotations Envelope 02 01 23 23 21 20 and Evaluation reuniao anual do comite gestor nacional com locacao de sala e servico de coffee break BR-CAA-4671-NC-RFQ / contratacao de empresa para prestacao de servico de transporte para o primeiro Component 2: Capacity Under Request for Single Stage - One 2016-01- 2016-01- 2016-01- 2016-03- intercambio nacional TF / 18765 Building and Institutional Post Limited 0.00 Implement Quotations Envelope 06 06 14 14 membros do comite gestor Strengthening ation nacional a ser ralizado em sao joao das missoes em minas gerais BR-CAA-4665-NC-RFQ / contratacao de empresa para prestacao de servicos para oficina de divugacao Component 1: Sustainable Pending de editais e treinamento Request for Single Stage - One 2016-01- 2016-02- 2016-04- TF / 18765 and Adaptive Community Post Limited 0.00 Implement para qualificacao propostas Quotations Envelope 19 02 02 Initiatives ation com fornecimento de coffee break e refeicoes e locacao de espaco e hospedagem realizacao em brasilia BR-CAA-4659-NC-RFQ / contratacao de empresa para prestacao de servicos para oficina de divugacao Component 1: Sustainable Pending de editais e treinamento Request for Single Stage - One 2015-12- 2016-02- 2016-04- TF / 18765 and Adaptive Community Post Limited 0.00 Implement para qualificacao propostas Quotations Envelope 28 11 11 Initiatives ation com fornecimento de coffee break e refeicoes e locacao de espaco e hospedagem realizacao em imperatriz BR-CAA-4661-NC-RFQ / contratacao de empresa para prestacao de servicos para oficina de divugacao Component 1: Sustainable Under de editais e treinamento Request for Single Stage - One 2016-01- 2017-02- 2016-02- 2016-04- TF / 18765 and Adaptive Community Post Limited 31,807.01 Implement para qualificacao propostas Quotations Envelope 13 02 04 04 Initiatives ation com fornecimento de coffee break e refeicoes e locacao de espaco e hospedagem realizacao em cuiaba BR-CAA-4673-NC-RFQ / contratacao de servicos graficos para material pedagogico tipo impressao Component 1: Sustainable Pending Request for Single Stage - One 2016-01- 2016-03- 2016-05- de cracha de bloco e pasta TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 26 22 21 de papel realizacao de tres Initiatives ation oficinas de divulgacao e duas de elaboracao projeto e tres seminarios BR-CAA-4668-NC-RFQ / Component 2: Capacity contratacao de servico de Request for Single Stage - One 2016-04- 2016-04- 2016-04- 2016-04- 2016-06- 2016-06- TF / 18765 Building and Institutional Post Limited 307.10 Completed impressao de folder para Quotations Envelope 20 20 25 25 24 25 Strengthening apresentacao do projeto BR-CAA-4660-NC-RFQ / contratacao de empresa para prestacao de servicos de coffee break para Component 3: Project Pending realizacao de reunioes do Request for Single Stage - One 2016-06- 2016-06- 2017-01- TF / 18765 Management, Monitoring Post Limited 0.00 Implement comite gestor nacional Quotations Envelope 03 12 29 and Evaluation ation sendo a segunda reuniao extraordinaria e a terceira reuniao ordinaria do ano de dois mil e dezesseis a ser realizado em brasilia BR-CAA-4672-NC-RFQ / contratacao de empresa para prestacao de servicos com fornecimento de coffee Component 2: Capacity Request for Single Stage - One 2016-06- 2016-06- 2016-07- 2016-07- 2016-08- 2016-08- break e refeicao e locacao TF / 18765 Building and Institutional Post Limited 8,014.75 Completed Quotations Envelope 25 27 11 11 10 09 de espaco e hospedagem e Strengthening sistema de projecao de som e flip chart para seminario nacional de fortalecimento institucional BR-CAA-4667-NC-RFQ / contratacao de empresa para a prestacao de servicos com fornecimento de coffee Component 3: Project Pending break refeicao e locacao de Request for Single Stage - One 2015-11- 2015-12- 2016-02- TF / 18765 Management, Monitoring Post Limited 0.00 Implement espaco com hospedagem e Quotations Envelope 17 23 21 and Evaluation ation sistema de projecao de som e flip chart para oficina de elaboracao de projeto a ser realizado em montes claros BR-CAA-4670-NC-RFQ / contratacao de empresa para a prestacao de servicos com fornecimento de coffee Component 1: Sustainable Pending break refeicao e locacao de Request for Single Stage - One 2016-11- 2016-12- 2017-04- TF / 18765 and Adaptive Community Post Limited 0.00 Implement espaco com hospedagem e Quotations Envelope 22 28 07 Initiatives ation sistema de projecao de som e flip chart para oficina de elaboracao de projeto a ser realizado em cuiaba BR-CAA-3259-NC-RFQ / contratacao de empresa para a prestacao de servicos com fornecimento de coffee Component 2: Capacity Pending Request for Single Stage - One 2017-07- 2017-08- 2017-10- break refeicao e locacao de TF / 18765 Building and Institutional Post Limited 0.00 Implement Quotations Envelope 29 18 17 espaco com hospedagem e Strengthening ation sistema de projecao de som e flip chart para Primeiro Seminário - tema de Redd. Local: Brasilia BR-CAA-17761-NC-RFQ / Contratação de empresa para a prestação de serviços técnicos, não continuados, Component 2: Capacity Pending Request for Single Stage - One 2017-07- 2017-08- 2017-10- para Oficina Interna REDD+. TF / 18765 Building and Institutional Post Limited 0.00 Implement Quotations Envelope 15 04 03 Fornecimento de: Coffe Strengthening ation break, Refeição (almoço/jantar), locação espaço e hospedagem, sala. BR-CAA-3263-NC-RFQ / Contratacao de empresa Component 2: Capacity Pending para prestacao de servico de Request for Single Stage - One 2017-09- 2017-09- 2017-11- TF / 18765 Building and Institutional Post Limited 0.00 Implement transporte nao continuados Quotations Envelope 04 24 23 Strengthening ation para segundo intercambio nacional. Tema sobre Redd. BR-CAA-3269-NC-RFQ / Contratacao de empresa para a prestacao de servicos com fornecimento de coffee break refeicao e locacao de Component 2: Capacity Pending Request for Single Stage - One 2017-07- 2017-09- 2017-11- espaco com hospedagem e TF / 18765 Building and Institutional Post Limited 0.00 Implement Quotations Envelope 28 11 10 sistema de projecao de som Strengthening ation e flip chart para segundo seminario temático. Tema: Atuando com Povos e Comunidades Tradicionais BR-CAA-3213-NC-RFQ / Contratacao de empresa para prestacao de servico de Component 2: Capacity Pending Request for Single Stage - One 2017-09- 2017-11- 2018-01- transporte nao continuados TF / 18765 Building and Institutional Post Limited 0.00 Implement Quotations Envelope 22 06 05 para terceiro intercambio Strengthening ation nacional local evento a ser definido. Tema RAI. BR-CAA-3260-NC-RFQ / Contratacao de empresa para a prestacao de servicos com fornecimento de coffee break refeicao e locacao de Component 2: Capacity Pending Request for Single Stage - One 2018-03- 2018-05- 2018-06- espaco com hospedagem e TF / 18765 Building and Institutional Post Limited 0.00 Implement Quotations Envelope 17 01 30 sistema de projecao de som Strengthening ation e flip chart para terceiro seminario temático. Tema: Políticas Públicas, Programas e ações govern BR-CAA-17790-NC-RFQ / Serviço de Instalação de Ar Component 3: Project Pending Condicionado Piso/Teto Request for Single Stage - One 2017-09- 2017-10- 2017-11- TF / 18765 Management, Monitoring Post Limited 0.00 Implement Split, potência 36.000btus - Quotations Envelope 11 01 30 and Evaluation ation para estruturação da sala reuniões DGM BR-CAA-17792-NC-RFQ / Prestação de serviço para readequação, suporte, no sistema informatizado Component 3: Project SIG/CAA, de mecanismos 2017-06- 2017-10- 2017-07- 2017-10- 2019-12- TF / 18765 Management, Monitoring Post Direct Selection Direct 18,540.50 Signed deimplementações para 19 10 10 10 27 and Evaluation gestão e monitoramento financeiro e de progresso de execução do projeto DGM/FIP/Brasil. Component 1: Sustainable Pending SUB 4-1 / CT4.1 Serviços 2017-07- 2017-07- 2017-08- 2017-09- TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Implement gerais de mateiro 20 25 04 03 Initiatives ation Page 11 SUB 4-9 / CT4.9. Serviços Component 1: Sustainable Pending Request for Single Stage - One 2018-02- 2018-03- 2018-05- de confecção de folder TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 06 16 05 camisetas e bonés. Initiatives ation SUB 4-10 / CT4.10. Contratação de assessoria Component 1: Sustainable Request for Single Stage - One 2017-06- 2018-01- 2017-08- 2018-03- 2018-11- técnica para acompanhar e TF / 18765 and Adaptive Community Post Limited 12,344.98 Signed Quotations Envelope 24 25 02 22 25 subsidiar a execução das Initiatives atividades do projeto. SUB 16-11 / CQ16-11 Serviço gerais de jovens Component 1: Sustainable Pending comunitários para Request for Single Stage - One 2017-06- 2017-07- 2017-08- TF / 18765 and Adaptive Community Post Limited 0.00 Implement realização do diagnostico Quotations Envelope 30 24 23 Initiatives ation socioambiental participativo com trinta e seis famílias SUB 25-2 / CQ25.2 Component 1: Sustainable Pending Aquisição de diversos 2017-06- 2017-07- 2017-07- 2019-03- TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Implement lanches e refeiçoes com a 19 06 28 20 Initiatives ation comunidade para cercamento de nascentes SUB 25-3 / CQ25.3 Contratação de profissional Component 1: Sustainable Pending para moderar e instruir Request for Single Stage - One 2018-03- 2018-05- 2018-07- TF / 18765 and Adaptive Community Post Limited 0.00 Implement sobre plantio manejo Quotations Envelope 25 11 10 Initiatives ation monitoramento e cuidados com as mudas SUB 25-5 / CQ25.5 Serviços gráficos de diagramação ou produção Component 1: Sustainable Pending de arte e produção de cento Request for Single Stage - One 2017-07- 2017-07- 2018-03- TF / 18765 and Adaptive Community Post Limited 0.00 Implement e cinquenta cartilhas para Quotations Envelope 06 28 25 Initiatives ation divulgação e reprodução de vinte e cinco apostilas para formação sobre o plantio e manejo de mudas SUB 25-10 / CQ25.10 Component 1: Sustainable Pending Contratação de serviços de 2018-01- 2018-01- 2018-02- 2018-03- TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Implement mão de obra para 05 22 13 25 Initiatives ation construção de cerca SUB 25-12 / CQ25.12 Component 1: Sustainable Pending Contratação de serviço de Request for Single Stage - One 2018-01- 2018-02- 2018-03- TF / 18765 and Adaptive Community Post Limited 0.00 Implement frete para transporte de Quotations Envelope 24 21 23 Initiatives ation produtos e insumo SUB 25-14 / CQ25.13 Component 1: Sustainable Pending Contratação de serviço de Request for Single Stage - One 2018-07- 2018-08- 2019-02- TF / 18765 and Adaptive Community Post Limited 0.00 Implement aluguel de veiculo para o Quotations Envelope 01 02 28 Initiatives ation transporte de pessoas SUB 25-13 / CQ25.14 Contratação de profissional para formar as famílias Component 1: Sustainable Pending 2017-06- 2017-07- 2017-07- 2017-09- envolvidas quanto a TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Implement 20 07 28 12 questões ligadas a Initiatives ation preservação e proteção das nascentes envolvendo gênero e geração SUB 25-15 / CQ25.15 Contratação de profissional com formação politica quanto a gênero e etinia por Component 1: Sustainable Pending diária para instruir na 2017-08- 2017-09- 2017-09- 2017-11- TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Implement oficina de treinamento de 16 01 22 06 Initiatives ation apoio a formação das famílias quanto as questões de preservação e protecao das nascentes envolvendo genero SUB 25-16 / CQ25.16 Contratação de profissional com formação na área de Component 1: Sustainable Pending meio ambiente por diária 2017-10- 2017-11- 2017-11- 2018-01- TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Implement para atuar em uma oficina 20 07 29 28 Initiatives ation de formação das famílias sobre questões de catalogação de nascentes envolvendo gênero e geração SUB 26-4 / CT26.4 Contratação de servicos Component 1: Sustainable Request for Single Stage - One 2017-08- 2018-09- 2017-08- 2018-09- 2017-09- 2018-09- gráficos para confecção de TF / 18765 and Adaptive Community Post Limited 155.19 Completed Quotations Envelope 02 04 21 06 30 15 camisetas banners e Initiatives impressão de caderno SUB 26-7 / CT26.7 Contratacao de servicos de logistica de evento no municipio de Caceres em Component 1: Sustainable Request for Single Stage - One 2017-07- 2018-08- 2017-07- 2018-09- 2017-09- 2018-10- defesa e protecao ao bioma TF / 18765 and Adaptive Community Post Limited 229.11 Completed Quotations Envelope 03 22 21 03 19 03 cerrado como forma de Initiatives sensibilizacao e tambem para a amostra de produtos sustentaveis SUB 26-12 / CT26.12 Component 1: Sustainable Pending Contratacao profissionais Request for Single Stage - One 2017-07- 2017-08- 2019-01- TF / 18765 and Adaptive Community Post Limited 0.00 Implement para servicos de articulacao Quotations Envelope 15 08 30 Initiatives ation por diaria SUB 45-8 / CT45.8 Contratacao de servico de Component 1: Sustainable Pending Request for Single Stage - One 2017-06- 2017-07- 2017-08- moderacao e instrutoria TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 27 21 30 para oficina de gestao Initiatives ation organizacional SUB 45-10 / CT45.10 Contratacao de servico de Component 1: Sustainable Pending Request for Single Stage - One 2017-12- 2018-01- 2018-02- moderacao e instrutoria TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 19 16 25 para curso de seguranca do Initiatives ation trabalho SUB 45-11 / CT45.11 Component 1: Sustainable Pending Contratacao de servico de Request for Single Stage - One 2017-11- 2017-12- 2018-01- TF / 18765 and Adaptive Community Post Limited 0.00 Implement moderacao e instrutoria Quotations Envelope 18 15 29 Initiatives ation para curso sobre a saude da mulher SUB 45-19 / CT45.19 Component 1: Sustainable Aquisicao de kit de material Request for Single Stage - One 2017-06- 2017-11- 2017-07- 2017-11- 2017-08- 2017-12- TF / 18765 and Adaptive Community Post Limited 394.95 Completed didatico para cursos oficinas Quotations Envelope 28 06 17 09 16 08 Initiatives e intercambios SUB 45-21 / CT45.21 Contratacao de servicos Component 1: Sustainable Request for Single Stage - One 2017-07- 2018-05- 2017-08- 2018-07- 2017-09- 2018-09- graficos para impressao de TF / 18765 and Adaptive Community Post Limited 782.73 Completed Quotations Envelope 10 21 03 27 12 04 folder banners e confeccao Initiatives de camisetas SUB 45-22 / CT45.22 Component 1: Sustainable Pending Locacao de veiculo micro Request for Single Stage - One 2017-07- 2017-08- 2017-09- TF / 18765 and Adaptive Community Post Limited 0.00 Implement onibus com capacidade para Quotations Envelope 29 21 30 Initiatives ation 20 passageiros SUB 55-6 / CT55.6 Component 1: Sustainable Pending Aquisicao e instalacao de Request for Single Stage - One 2017-06- 2017-07- 2017-08- TF / 18765 and Adaptive Community Post Limited 0.00 Implement uma Cisterna para captacao Quotations Envelope 25 18 27 Initiatives ation de agua de chuva SUB 55-9 / CT55.9 Locacao Component 1: Sustainable de veiculos para Request for Single Stage - One 2017-07- 2017-09- 2017-07- 2017-10- 2018-05- TF / 18765 and Adaptive Community Post Limited 2,185.39 Signed atendimento de diversas Quotations Envelope 01 27 18 17 14 Initiatives finalidades de execucao do Subprojeto SUB 55-13 / CT55.13 Contratacao de profissional Component 1: Sustainable para assessoria tecnica Request for Single Stage - One 2017-07- 2018-01- 2017-07- 2018-03- 2018-05- 2019-03- TF / 18765 and Adaptive Community Post Limited 11,568.52 Completed para acompanhar e Quotations Envelope 02 25 27 20 23 20 Initiatives subsidiar a execucao das atividades do projeto SUB 55-17 / CT55.17 Contratacao de profissional especializado com Component 1: Sustainable Pending Request for Single Stage - One 2017-08- 2017-09- 2017-10- experiencia em TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 25 21 31 agroindustria familiar e Initiatives ation comunitaria para ministrar Oficina de Capacitacao em Compostagem SUB 55-18 / CT55.18 Contratacao de profissional Component 1: Sustainable Pending especializado para ministrar Request for Single Stage - One 2017-08- 2017-09- 2017-11- TF / 18765 and Adaptive Community Post Limited 0.00 Implement Oficina de Capacitacao em Quotations Envelope 31 22 11 Initiatives ation Uso e Aproveitamento de Cagaita SUB 55-19 / CT55.19 Contratacao de profissional Component 1: Sustainable Pending Request for Single Stage - One 2017-12- 2018-01- 2018-02- especializado para ministrar TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 18 15 24 oficina de capacitacao em Initiatives ation uso e aproveitamento do Araticum SUB 56-11 / CT56.11 Servico de hora maquina de Component 1: Sustainable Request for Single Stage - One 2017-09- 2019-06- 2017-10- 2019-06- 2019-01- 2019-07- pa carregadeira para TF / 18765 and Adaptive Community Post Limited 3,341.01 Completed Quotations Envelope 21 03 16 12 09 25 construcao de bacias de Initiatives contencao de aguas pluviais SUB 56-12 / CT56.12 Component 1: Sustainable Pending Servico de horas maquina Request for Single Stage - One 2017-10- 2017-11- 2019-05- TF / 18765 and Adaptive Community Post Limited 0.00 Implement de trator para retirada dos Quotations Envelope 25 20 19 Initiatives ation eucaliptos nas areas de recarga SUB 56-13 / CT56.13 Contratacao de servicos de Component 1: Sustainable Pending Request for Single Stage - One 2017-12- 2018-01- 2018-03- instrutor para ministrar TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 20 15 26 quatro oficinas para Initiatives ation implantacao de sistemas agroflorestais SUB 56-14 / CT56.14 Contratacao de servicos Component 1: Sustainable Pending Request for Single Stage - One 2017-08- 2017-09- 2017-10- graficos para confeccao de TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 25 20 30 materiais de divulgacao Initiatives ation boletins SUB 61-16 / CQ61.16 Component 1: Sustainable Pending Contratação de profissional Request for Single Stage - One 2017-07- 2017-07- 2018-04- TF / 18765 and Adaptive Community Post Limited 0.00 Implement para realizar assessoria Quotations Envelope 06 26 22 Initiatives ation técnica ao subprojeto SUB 61-18 / CQ61.18 Contratação de profissional técnico para realizar Component 1: Sustainable Pending Request for Single Stage - One 2017-08- 2017-09- 2018-04- capacitação de valoração da TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 30 30 18 produção artesanal Initiatives ation quilombola existente na comunidade SUB 71-4 / CT71.4 Component 1: Sustainable Request for Single Stage - One 2017-07- 2018-06- 2017-07- 2018-08- 2019-03- Contratação de agentes TF / 18765 and Adaptive Community Post Limited 5,274.07 Signed Quotations Envelope 04 20 24 29 16 locais comunitários Initiatives SUB 71-6 / CT71.6 Contratação de assessoria Component 1: Sustainable Under Request for Single Stage - One 2017-07- 2018-02- 2017-07- 2019-04- técnica para acompanhar e TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 08 08 28 19 subsidiar a execução das Initiatives ation atividades do subprojeto SUB 75-2 / CQ75.2 Contratação de servicos de Component 1: Sustainable Pending comunicação e imprensa Request for Single Stage - One 2017-07- 2017-07- 2017-09- TF / 18765 and Adaptive Community Post Limited 0.00 Implement para acompanhamento a Quotations Envelope 06 31 04 Initiatives ation eventos criação e suporte da pagina de facebook SUB 90-2 / CT90.2 Contratação de servicos de identidade visual para desenvolver e aprimorar Component 1: Sustainable embalagens com identidade Request for Single Stage - One 2017-07- 2017-07- 2017-09- TF / 18765 and Adaptive Community Post Limited 0.00 Canceled visual coerente as Quotations Envelope 08 31 09 Initiatives comunidades e com linguagem visual que torne os produtos ecossociais mais interessantes no mercado SUB 90-3 / CT90.3 Contratação de servicos Component 1: Sustainable gráficos de confecção de Request for Single Stage - One 2017-07- 2017-07- 2017-09- TF / 18765 and Adaptive Community Post Limited 0.00 Canceled rótulos diversos com Quotations Envelope 09 31 09 Initiatives identidade e linguagem visual das comunidades SUB 90-4 / CT90.4 Component 1: Sustainable Request for Single Stage - One 2017-07- 2017-08- 2017-10- Contratação de servicos TF / 18765 and Adaptive Community Post Limited 0.00 Canceled Quotations Envelope 08 02 01 para realização de quinze Initiatives fretes SUB 99-13 / CT99.13 Component 1: Sustainable Pending Contratacao de servicos Request for Single Stage - One 2017-07- 2017-08- 2017-09- TF / 18765 and Adaptive Community Post Limited 0.00 Implement graficos para impressao de Quotations Envelope 12 04 03 Initiatives ation folder e banners SUB 99-14 / CT99.14 Fornecimento de alimentação para Oficina Component 1: Sustainable Pending sobre agroecologia 2017-07- 2017-07- 2017-08- 2018-01- TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Implement Funcionamento do PAIS 06 16 03 30 Initiatives ation Intercambio Oficina de agroecologia Oficinas sobre o manejo do sistema PAIS SUB 99-15 / CT99.15 Contratação de profissional Component 1: Sustainable Pending para assessoria técnica no Request for Single Stage - One 2017-07- 2017-08- 2019-02- TF / 18765 and Adaptive Community Post Limited 0.00 Implement processo de produção Quotations Envelope 13 03 24 Initiatives ation agrícola e manejo da unidade produtiva SUB 105-1 / CQ105.1 Contratação de serviços de técnicos para elaboração e Component 1: Sustainable Pending Request for Single Stage - One 2018-09- 2018-10- 2018-11- socialização do caderno de TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 19 16 30 planos de gestão e praticas Initiatives ation de produção tradicionais quilombolas SUB 105-3 / CQ105.3 Contratação de serviço de Component 1: Sustainable locação de veículos para os 2017-07- 2019-06- 2017-07- 2019-06- 2017-08- 2019-07- 2018-03- 2019-07- TF / 18765 and Adaptive Community Post Direct Selection Direct 1,933.97 Completed eventos de Encontro da 10 25 20 27 02 09 30 29 Initiatives juventude e Caravana quilombola do jalapão SUB 105-5 / CQ105.5 Component 1: Sustainable Pending Contratação de serviços de Request for Single Stage - One 2017-07- 2017-08- 2017-10- TF / 18765 and Adaptive Community Post Limited 0.00 Implement diagnostico e elaboração do Quotations Envelope 17 08 07 Initiatives ation plano de gestão territorial SUB 105-11 / CQ105.11 Contratação de serviços gerais de Cozinheira em Component 1: Sustainable Pending diversas comunidades por 2017-07- 2017-07- 2017-07- 2018-07- TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Implement diária para Oficinas 11 16 27 22 Initiatives ation Elaboração do plano de gestão territorial Encontro da juventude e Caravana quilombola do jalapão SUB 109-1 / CT109.1 Contratação de serviços Component 1: Sustainable Pending Request for Single Stage - One 2017-07- 2017-08- 2017-12- gerais de pedreiro para TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 27 14 12 reforma do entreposto dos Initiatives ation produtos do babaçu SUB 110-23 / CQ110.23 Contratação de serviços gerais, por diária, de Component 1: Sustainable 2017-07- 2017-08- 2017-08- 2017-09- tratorista para fazer a TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled 28 07 21 30 marcação das curvas de Initiatives nível e terraceamento na área com erosão SUB 110-25 / CQ110.25 Component 1: Sustainable Contratação de serviços de Request for Single Stage - One 2018-01- 2018-02- 2018-11- TF / 18765 and Adaptive Community Post Limited 0.00 Canceled locação de veículos ônibus Quotations Envelope 23 19 16 Initiatives para intercâmbios SUB 116-16 / CT116.16 Component 1: Sustainable Pending Request for Single Stage - One 2017-08- 2017-09- 2017-10- Serviço de confecção de TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 14 04 09 camisetas de divulgação Initiatives ation SUB 116-22 / CT116.22 Component 1: Sustainable Pending Contratação de serviços 2017-08- 2017-08- 2017-09- 2017-09- TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Implement locação de lancha para 11 19 04 29 Initiatives ation expedição fluvial SUB 116-23 / CT116.23 Contratação de serviços Component 1: Sustainable Pending 2017-08- 2017-08- 2017-08- 2017-09- gerais de pedreiro, por TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Implement 01 08 21 25 diária, para construção do Initiatives ation reservatório de água SUB 116-24 / CT116.24 Component 1: Sustainable Pending Request for Single Stage - One 2017-08- 2017-08- 2017-10- Contratação de serviços TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 08 28 02 para instalação elétrica e Initiatives ation hidráulico SUB 130-6 / CT130.6 Contratação de serviços Component 1: Sustainable Request for Single Stage - One 2017-08- 2019-01- 2017-08- 2018-01- 2017-09- 2018-02- gráficos para impressão de TF / 18765 and Adaptive Community Post Limited 558.86 Completed Quotations Envelope 01 16 21 29 30 28 capa do catálogo dos Initiatives produtos Jatobá Pequi e Baru Page 12 SUB 130-8 / CT130.8 Contratação de serviços Component 1: Sustainable para analise final Request for Single Stage - One 2017-08- 2019-06- 2017-08- 2019-06- 2017-10- 2019-08- TF / 18765 and Adaptive Community Post Limited 2,990.65 Completed microbiológica e Quotations Envelope 04 10 25 19 04 15 Initiatives bromatológica do beneficiamento do Jatobá Pequi e Baru Component 1: Sustainable SUB 3-16 / Contratação de 2017-07- 2017-08- 2017-08- 2018-02- TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled serviços de cozinheiras/os 26 09 25 26 Initiatives SUB 3-18 / Contratação de Component 1: Sustainable Request for Single Stage - One 2017-07- 2017-08- 2017-11- serviço para construção de TF / 18765 and Adaptive Community Post Limited 0.00 Canceled Quotations Envelope 26 31 01 um barracão rústico Initiatives SUB 74-4 / Contratação de Component 1: Sustainable Request for Single Stage - One 2017-08- 2019-10- 2017-08- 2019-10- 2018-01- 2019-10- empresas locação de TF / 18765 and Adaptive Community Post Limited 750.60 Completed Quotations Envelope 02 15 16 17 03 17 veículos. Initiatives Component 1: Sustainable Pending SUB 108-1 / Contratação 2018-08- 2018-08- 2018-10- 2018-12- TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Implement de serviços de cozinheira. 03 24 01 03 Initiatives ation SUB 28-2 / Contratação de Component 1: Sustainable serviços de aluguel de micro- Request for Single Stage - One 2018-01- 2018-02- 2018-04- TF / 18765 and Adaptive Community Post Limited 0.00 Canceled ônibus para transporte de Quotations Envelope 05 06 09 Initiatives passageiros Component 1: Sustainable SUB 28-3 / Contratação de 2018-01- 2018-02- 2018-03- 2018-04- TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled serviços de cozinheiras. 15 06 09 16 Initiatives SUB 113-5 / Contratação Component 1: Sustainable Pending Request for Single Stage - One 2017-10- 2017-11- 2018-12- de serviço para produção de TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 06 07 14 materiais de divulgação. Initiatives ation BR-CAA-23125-NC-RFQ / Contratação de empresa para prestação de serviço, Component 3: Project Request for Single Stage - One 2017-08- 2016-12- 2017-08- 2016-12- 2018-02- 2017-02- não continuados, para TF / 18765 Management, Monitoring Post Limited 21,956.12 Completed Quotations Envelope 03 01 09 20 05 17 realização de 04 (quatro) and Evaluation eventos - reuniões do comitê gestor nacional SUB 113-8 / Serviços de Component 1: Sustainable Pending digramação de impressão Request for Single Stage - One 2017-10- 2017-11- 2018-12- TF / 18765 and Adaptive Community Post Limited 0.00 Implement de materiais de divulgação Quotations Envelope 02 03 10 Initiatives ation da cultura indígena Chiquitana SUB 120-4 / Contratação Component 1: Sustainable Pending Request for Single Stage - One 2017-09- 2017-10- 2019-05- de serviço de locação TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 14 02 24 veículo Initiatives ation Component 1: Sustainable Pending SUB 120-6 / Contratação Request for Single Stage - One 2017-09- 2017-10- 2019-05- TF / 18765 and Adaptive Community Post Limited 0.00 Implement de serviços de contabilidade Quotations Envelope 14 02 24 Initiatives ation Component 1: Sustainable Pending SUB 120-7 / Contratação Request for Single Stage - One 2017-11- 2017-11- 2018-07- TF / 18765 and Adaptive Community Post Limited 0.00 Implement de serviços de transporte Quotations Envelope 09 27 16 Initiatives ation SUB 135-4 / Contratação de profissional em áudio Component 1: Sustainable Pending Request for Single Stage - One 2017-10- 2017-10- 2017-12- visual, para registro das TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 09 26 25 etapas do projeto e Initiatives ation capacitação de jovens cineastas Component 1: Sustainable Pending SUB 135-5 / Contratação Request for Single Stage - One 2017-09- 2017-10- 2017-10- TF / 18765 and Adaptive Community Post Limited 0.00 Implement de serviços de tratorista Quotations Envelope 18 02 23 Initiatives ation SUB 42-1 / Serviços de Component 1: Sustainable Pending Request for Single Stage - One 2017-09- 2017-10- 2017-12- capturas de imagens para TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 25 11 11 construção de um vídeo Initiatives ation SUB 42-2 / Serviço de Component 1: Sustainable Pending Request for Single Stage - One 2018-09- 2018-09- 2018-11- confecção de Banner de TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 11 28 28 90cmX1,20m Initiatives ation SUB 42-3 / Serviço de Component 1: Sustainable Pending confecção de Placa de Request for Single Stage - One 2017-12- 2018-02- 2018-08- TF / 18765 and Adaptive Community Post Limited 0.00 Implement identificação do projeto de Quotations Envelope 19 05 04 Initiatives ation vigilância irom cati. SUB 42-4 / Serviço de Component 1: Sustainable Pending Request for Single Stage - One 2017-09- 2017-10- 2018-02- fornecimento de TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 29 16 14 combustíveis e lubrificantes Initiatives ation SUB 120-3 / Contratação Component 1: Sustainable Pending de serviços de locação de Request for Single Stage - One 2017-09- 2017-10- 2019-02- TF / 18765 and Adaptive Community Post Limited 0.00 Implement caminhonete comunitária Quotations Envelope 25 11 23 Initiatives ation para transporte de combustível SUB 113-2 / Contratação de agente de animação na comunidade, para realizar: 1-organização para Component 1: Sustainable construção dos apiários - 2- Request for Single Stage - One 2017-09- 2017-10- 2018-11- TF / 18765 and Adaptive Community Post Limited 0.00 Canceled organização e Quotations Envelope 15 02 06 Initiatives acompanhamento da instalação e funcionamento dos viveiros e monitoramento do processo de produção de mudas SUB 30 - 2 / Serviço de Component 1: Sustainable Pending Request for Single Stage - One 2017-09- 2017-10- 2018-11- fornecimento de TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 23 10 15 combustível para o projeto. Initiatives ation Component 1: Sustainable SUB 26-2 / CT26.2 Request for Single Stage - One 2017-06- 2018-09- 2017-07- 2018-11- 2018-02- TF / 18765 and Adaptive Community Post Limited 2,842.63 Signed Locações de veículos. Quotations Envelope 30 19 17 06 12 Initiatives SUB 135-1 / Contratação Component 1: Sustainable Pending de serviços de cozinheira 2017-09- 2017-09- 2017-10- 2017-12- TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Implement que será realizado por 11 21 04 04 Initiatives ation pessoa local. SUB 135-2 / Contratação Component 1: Sustainable Pending de indígena especializado 2017-09- 2017-09- 2017-10- 2017-12- TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Implement em madeiramento nativo - 11 21 04 04 Initiatives ation indígena 1 SUB 135-3 / Contratação Component 1: Sustainable Pending de marceneiro para 2017-09- 2017-09- 2017-10- 2017-11- TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Implement construção de estrutura 11 23 06 06 Initiatives ation para armazenamento de sementes SUB 135-23 / Contratação Component 1: Sustainable Pending 2017-09- 2017-09- 2017-10- 2017-12- de 01 indígena TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Implement 11 20 03 04 especializados em Initiatives ation madeiramento nativo SUB 28-13 / Serviços de Component 1: Sustainable fornecimento de lanche para 2017-09- 2017-09- 2017-09- 2017-10- TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled manejo e produção de 04 10 26 26 Initiatives adubo verde SUB 28-14 / Serviços de Component 1: Sustainable fornecimento de lanche para 2017-09- 2017-10- 2017-10- 2017-12- TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled manejo ecológico de pragas 25 02 17 16 Initiatives e doenças de frutíferas SUB 28-15 / Serviços de Component 1: Sustainable fornecimento de lanche para 2018-03- 2018-03- 2018-04- 2018-06- TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled associativismo e 23 31 16 15 Initiatives comercialização SUB 28-16 / Serviços de fornecimento de lanche para Component 1: Sustainable 2018-10- 2018-10- 2018-11- 2019-01- produção de mudas de TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled 15 21 06 05 frutíferas para Initiatives comercialização SUB 3-15 / Contratação de serviços de tratoristas para Component 1: Sustainable 2017-09- 2017-10- 2017-11- 2018-01- plantio de mudas e TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled 12 04 11 30 sementes no entorno das Initiatives aldeias Aopá - Madzabdze SUB 28-9 / erviços de fornecimento de lanche para Component 1: Sustainable participantes da 2017-09- 2017-09- 2017-09- 2017-10- TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled capacitações em: manejo 04 10 26 26 Initiatives ecológico de frutíferas e manejo ecológico do solo SUB 4-6 / CT4.6. Component 1: Sustainable Pending Contratação de serviços 2017-11- 2017-12- 2018-01- 2018-03- TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Implement gerais para o realizar o 15 02 02 03 Initiatives ation cercamento do isolamento das nascentes. SUB 42-7 / Contração de Component 1: Sustainable Pending agente comunitário 1 para 2017-09- 2017-09- 2017-10- 2019-03- TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Implement serviço para vigilância e 15 29 16 01 Initiatives ation fiscalização SUB 42-8 / Contração de Component 1: Sustainable Pending agente comunitário 2 para 2017-09- 2017-09- 2017-10- 2019-03- TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Implement serviço para vigilância e 15 29 16 01 Initiatives ation fiscalização SUB 42-9 / Contração de Component 1: Sustainable Pending agente comunitário 3 para 2017-09- 2017-09- 2017-10- 2019-03- TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Implement serviço para vigilância e 15 29 16 01 Initiatives ation fiscalização SUB 42-10 / Contração de Component 1: Sustainable Pending agente comunitário 4 para 2017-09- 2017-09- 2017-10- 2019-03- TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Implement serviço para vigilância e 15 29 16 01 Initiatives ation fiscalização SUB 42-11 / Contração de Component 1: Sustainable Pending agente comunitário 5 para 2017-09- 2017-09- 2017-10- 2019-03- TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Implement serviço para vigilância e 15 29 16 01 Initiatives ation fiscalização SUB 42-12 / Contração de Component 1: Sustainable Pending agente comunitário 6 para 2017-09- 2017-09- 2017-10- 2019-03- TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Implement serviço para vigilância e 15 29 16 01 Initiatives ation fiscalização SUB 42-13 / Contração de Component 1: Sustainable Pending agente comunitário 7 para 2017-09- 2017-09- 2017-10- 2019-03- TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Implement serviço para vigilância e 15 29 16 01 Initiatives ation fiscalização SUB 42-14 / Contração de Component 1: Sustainable Pending agente comunitário 8 para 2017-09- 2017-09- 2017-10- 2019-03- TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Implement serviço para vigilância e 15 29 16 01 Initiatives ation fiscalização SUB 42-15 / Contração de Component 1: Sustainable Pending agente comunitário 9 para 2017-09- 2017-09- 2017-10- 2019-03- TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Implement serviço para vigilância e 15 29 16 01 Initiatives ation fiscalização SUB 42-16 / Contração de Component 1: Sustainable Pending agente comunitário 10 para 2017-09- 2017-09- 2017-10- 2019-03- TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Implement serviço para vigilância e 15 29 16 01 Initiatives ation fiscalização SUB 42-18 / Serviços de serraria para realizar Component 1: Sustainable Pending adequação de barracão para 2017-09- 2017-10- 2017-10- 2018-02- TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Implement servir de sede do projeto e 23 07 24 02 Initiatives ation para acondicionar equipamentos SUB 4-11 / CT4.11. Component 1: Sustainable Pending Contratação de serviços 2017-11- 2017-12- 2018-01- 2018-03- TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Implement gerais para o realizar o 15 02 02 03 Initiatives ation cercamento do isolamento das nascentes. SUB 4-12 / CT4.12. Component 1: Sustainable Pending Contratação de serviços 2017-11- 2017-12- 2018-01- 2018-03- TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Implement gerais para o realizar o 15 02 02 03 Initiatives ation cercamento do isolamento das nascentes. SUB 4-13 / CT4.13 Component 1: Sustainable Pending Contratação de serviços 2017-11- 2017-12- 2018-01- 2018-03- TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Implement gerais para o realizar o 15 02 02 03 Initiatives ation cercamento do isolamento das nascentes SUB 4-14 / CT4.14. Component 1: Sustainable Pending Contratação de serviços 2017-11- 2017-12- 2018-01- 2018-03- TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Implement gerais para o realizar o 15 02 02 03 Initiatives ation cercamento do isolamento das nascentes SUB 4-15 / CT4.15. Component 1: Sustainable Pending Contratação de serviços 2017-11- 2017-12- 2018-01- 2018-03- TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Implement gerais para o realizar o 15 02 02 03 Initiatives ation cercamento do isolamento das nascentes SUB 4-16 / CT4.16. Component 1: Sustainable Pending Contratação de serviços 2017-11- 2017-12- 2018-01- 2018-03- TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Implement gerais para o realizar o 15 02 02 03 Initiatives ation cercamento do isolamento das nascentes SUB 4-17 / CT4.17. Component 1: Sustainable Pending Contratação de serviços 2017-11- 2017-12- 2018-01- 2018-03- TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Implement gerais para o realizar o 15 02 02 03 Initiatives ation cercamento do isolamento das nascentes. SUB 4-18 / CT4.18. Component 1: Sustainable Pending Contratação de serviços 2017-11- 2017-12- 2018-01- 2018-03- TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Implement gerais para o realizar o 15 02 02 03 Initiatives ation cercamento do isolamento das nascentes. SUB 4-19 / CT4.19. Component 1: Sustainable Pending Contratação de serviços 2017-11- 2017-12- 2018-01- 2018-03- TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Implement gerais para o realizar o 15 02 02 03 Initiatives ation cercamento do isolamento das nascentes. SUB 16-2 / CQ16-2 Component 1: Sustainable Request for Single Stage - One 2017-06- 2018-01- 2017-07- 2018-03- 2017-10- Serviços de perfuração de TF / 18765 and Adaptive Community Post Limited 8,037.54 Signed Quotations Envelope 30 23 24 02 02 poço artesiano. Initiatives SUB 134-1 / Serviço de Component 1: Sustainable 2017-11- 2017-12- 2017-12- 2019-03- mão de obra geral de TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled 27 04 22 17 viveirista Initiatives SUB 56-10 / CT56.10 Component 1: Sustainable 2017-06- 2017-07- 2017-07- 2017-08- Contratacao de servico de TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled 29 08 19 28 pedreiro por diaria Initiatives SUB 56-15 / CT56.15 Contratacao de servico de Component 1: Sustainable cozinheira por diaria para 2017-07- 2017-07- 2017-08- 2017-09- TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled quatro oficinas comunitaria 10 15 07 21 Initiatives de capacitacao mapeamento e planejamento participativo SUB 42-5 / Serviço de cozinheira para 01 oficina de capacitação sobre o Component 1: Sustainable 2017-09- 2017-09- 2017-10- 2017-10- trabalho de vigilância, TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled 05 19 06 27 planejamento e orientação Initiatives sobre como serão formados os grupos de trabalho a cada etapa SUB 42-37 / Serviço de cozinheira 2 para 01 oficina de capacitação sobre o Component 1: Sustainable trabalho de vigilância, 2017-09- 2017-09- 2017-10- 2017-10- TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled planejamento e orientação 05 19 06 27 Initiatives sobre como serão formados os grupos de trabalho a cada etapa SUB 127-1 / Servico de cozinheira 1 para Component 1: Sustainable cozimentos alimentos da 2017-11- 2017-12- 2017-12- 2018-01- TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled primeira etapa construcao 20 04 18 07 Initiatives de centro de revitalizacao da cultura e visitacao SUB 127-2 / Servico de cozinheira 2 para Component 1: Sustainable cozimentos alimentos 2017-11- 2017-12- 2017-12- 2018-01- TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled primeira etapa construcao 20 04 18 07 Initiatives de centro de revitalizacao da cultura e visitacao. SUB 127-3 / Servico de cozinheira 1 para Component 1: Sustainable cozimentos alimentos 2017-12- 2017-12- 2018-01- 2018-02- TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled segunda etapa construcao 15 28 15 04 Initiatives de centro de revitalizacao da cultura e visitacao SUB 127-4 / Servico de cozinheira 2 para Component 1: Sustainable cozimentos alimentos 2017-12- 2017-12- 2018-01- 2018-02- TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled segunda etapa construcao 15 28 15 04 Initiatives de centro de revitalizacao da cultura e visitacao Page 13 SUB 127-5 / Servico de mao de obra indigena 1 Component 1: Sustainable 2017-11- 2017-12- 2017-12- 2018-04- para construcao e instalacao TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled 22 07 26 05 do centro cultural nos Initiatives moldes tradicional indigena SUB 127-6 / Servico de mao de obra indigena 2 Component 1: Sustainable 2017-11- 2017-12- 2017-12- 2018-04- para construcao e instalacao TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled 22 07 26 05 do centro cultural nos Initiatives moldes tradicional indígena SUB 127-7 / Servico de mao de obra indigena 3 Component 1: Sustainable 2017-11- 2017-12- 2017-12- 2018-04- para construcao e instalacao TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled 22 07 26 05 do centro cultural nos Initiatives moldes tradicional indígena SUB 127-8 / Servico de mao de obra indigena 4 Component 1: Sustainable 2017-11- 2017-12- 2017-12- 2018-04- para construcao e instalacao TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled 22 07 26 05 do centro cultural nos Initiatives moldes tradicional indígena SUB 127-9 / Servico de mao de obra indigena 5 Component 1: Sustainable 2017-11- 2017-12- 2017-12- 2018-04- para construcao e instalacao TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled 22 07 26 05 do centro cultural nos Initiatives moldes tradicional indígena SUB 127-10 / Servico de mao de obra profissional Component 1: Sustainable indigena para retirada de 2017-11- 2017-12- 2017-12- 2018-01- TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled madeiras para construcao 24 08 21 30 Initiatives do centro de revitalizacao da cultura e visita SUB 127-11 / Servico de auxiliar mao de obra 1 para Component 1: Sustainable retirada de madeiras para 2017-11- 2017-12- 2017-12- 2018-01- TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled construcao do centro de 24 08 21 30 Initiatives revitalizacao da cultura e visita SUB 127-12 / Servico de auxiliar mao de obra 2 para Component 1: Sustainable retirada de madeiras para 2017-11- 2017-12- 2017-12- 2018-01- TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled construcao do centro de 24 08 21 30 Initiatives revitalizacao da cultura e visita SUB 127-13 / Servico de auxiliar mao de obra 3 para Component 1: Sustainable retirada de madeiras para 2017-11- 2017-12- 2017-12- 2018-01- TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled construcao do centro de 24 08 21 30 Initiatives revitalizacao da cultura e visita SUB 127-14 / Servico de de Component 1: Sustainable desenvolvimento de website Request for Single Stage - One 2017-12- 2018-01- 2018-02- TF / 18765 and Adaptive Community Post Limited 0.00 Canceled e treinamento para Quotations Envelope 12 03 22 Initiatives alimentacao do site SUB 127-15 / Contratação de frete comunitário Component 1: Sustainable indigena para transporte de Request for Single Stage - One 2017-12- 2018-01- 2018-02- TF / 18765 and Adaptive Community Post Limited 0.00 Canceled madeira e palhas que serão Quotations Envelope 12 04 03 Initiatives utilizadas na construção do Centro de Revitalizacao - frete 1 SUB 127-17 / Servico de frete comunitario indigena Component 1: Sustainable para transporte de madeira Request for Single Stage - One 2017-12- 2017-12- 2018-01- TF / 18765 and Adaptive Community Post Limited 0.00 Canceled e palhas que serao Quotations Envelope 07 26 25 Initiatives utilizadas na construcao do Centro de Revitalizacao - frete 3 SUB 127-18 / Servico de frete comunitario indigena Component 1: Sustainable para transporte de madeira Request for Single Stage - One 2017-12- 2017-12- 2018-01- TF / 18765 and Adaptive Community Post Limited 0.00 Canceled e palhas que serao Quotations Envelope 07 26 25 Initiatives utilizadas na construcao do Centro de Revitalizacao - frete 4 SUB 127-19 / Servicos para Component 1: Sustainable criacao de layout e Request for Single Stage - One 2017-12- 2017-12- 2018-02- TF / 18765 and Adaptive Community Post Limited 0.00 Canceled impreessao de folders para Quotations Envelope 07 21 19 Initiatives divulgacao do projeto SUB 127-20 / Servicos de Component 1: Sustainable confeccao de camisetas para Request for Single Stage - One 2017-12- 2017-12- 2018-02- TF / 18765 and Adaptive Community Post Limited 0.00 Canceled divulgacao do Centro de Quotations Envelope 04 22 10 Initiatives Revitalizacao SUB 127-22 / Servico de Component 1: Sustainable empreita de mao de obra de Request for Single Stage - One 2017-12- 2018-01- 2018-04- TF / 18765 and Adaptive Community Post Limited 0.00 Canceled ajudante de pedreiro para Quotations Envelope 28 15 25 Initiatives construcao do centro SUB 16-5 / CQ16-5 Serviço Component 1: Sustainable Request for Single Stage - One 2017-06- 2018-01- 2017-07- 2018-01- 2017-08- 2018-02- de confecção de banner TF / 18765 and Adaptive Community Post Limited 70.49 Completed Quotations Envelope 29 10 23 24 07 05 para divulgação do Initiatives subprojeto SUB 26-11 / CT26.11 Contratacao de maquinario Component 1: Sustainable Pending Request for Single Stage - One 2017-11- 2017-12- 2018-01- por hora para fazer TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 29 23 22 barraginhas em duas grotas Initiatives ation da comunidade SUB 16-16 / Serviços de Component 1: Sustainable Request for Single Stage - One 2017-11- 2017-12- 2017-12- 2018-02- 2017-12- 2018-03- Confecção de camisetas de TF / 18765 and Adaptive Community Post Limited 396.51 Completed Quotations Envelope 20 11 12 22 29 28 divulgação do Subprojeto. Initiatives SUB 142 -3 / Servicos acompanhamento do Component 1: Sustainable Community Pending 2018-01- 2018-02- 2018-02- 2018-02- 2018-02- 2018-12- processo de abertura da TF / 18765 and Adaptive Community Post Driven Limited 0.00 Implement 23 06 15 18 23 21 roCa e producao do Initiatives Development ation relatorio - comunitário 1 SUB 125 - 1 / Serviço de Component 1: Sustainable Community Pending 2017-12- 2018-01- 2018-01- 2018-01- 2018-01- 2018-03- tratorista indígena para TF / 18765 and Adaptive Community Post Driven Limited 0.00 Implement 18 01 08 10 19 20 correção do solo. Initiatives Development ation SUB 125 - 2 / Serviço de Component 1: Sustainable Community Pending instrutor para ministrar 2017-12- 2018-01- 2018-01- 2018-01- 2018-01- 2018-03- TF / 18765 and Adaptive Community Post Driven Limited 0.00 Implement oficina de capacitação na 18 01 08 12 19 20 Initiatives Development ation correção de solo. Component 1: Sustainable Community Pending SUB 125 - 4 / Serviço de 2017-12- 2018-01- 2018-01- 2018-01- 2018-01- 2018-03- TF / 18765 and Adaptive Community Post Driven Limited 0.00 Implement confecção de camisetas. 22 05 15 16 23 26 Initiatives Development ation SUB 125 - 6 / Serviço de Component 1: Sustainable Community Pending 2017-12- 2018-01- 2018-01- 2018-01- 2018-01- 2018-03- análise de amostra de solo TF / 18765 and Adaptive Community Post Driven Limited 0.00 Implement 28 11 18 22 29 30 em laboratório. Initiatives Development ation SUB 125 - 7 / Serviço de instrutor para ministrar Component 1: Sustainable Community 2017-12- 2018-01- 2018-01- 2018-01- 2018-01- 2018-02- oficina de aplicação de TF / 18765 and Adaptive Community Post Driven Limited 0.00 Canceled 28 11 18 22 29 28 composto de Initiatives Development micronutrientes e adubos orgânicos. SUB 124 - 1 / Contratação de serviços para Component 1: Sustainable Community acompanhamento técnico 2018-01- 2018-09- 2018-01- 2018-09- 2018-02- 2018-09- 2018-02- 2018-10- 2018-02- 2018-11- 2019-10- TF / 18765 and Adaptive Community Post Driven Limited 4,254.74 Signed do projeto para Orientação 12 27 26 28 05 27 06 23 13 01 07 Initiatives Development técnica de plantio e manutenção de áreas de SAF. SUB 124 - 6 / Aquisição de Component 1: Sustainable Community 2018-01- 2019-04- 2018-02- 2019-04- 2018-02- 2019-04- 2018-02- 2019-04- 2018-02- 2019-04- 2018-04- 2019-10- mudas de plantas nativas TF / 18765 and Adaptive Community Post Driven Limited 4,304.14 Completed 24 08 07 08 16 09 19 11 26 11 26 09 para recuperação de áreas. Initiatives Development SUB 124 - 7 / Aquisição de sementes diversas de Component 1: Sustainable Community 2018-01- 2019-10- 2018-02- 2019-10- 2018-02- 2019-10- 2018-02- 2019-11- 2018-02- 2019-11- 2018-04- 2019-12- leguminosas e ou crioulas, TF / 18765 and Adaptive Community Post Driven Limited 1,326.13 Completed 29 29 12 29 20 29 22 11 28 18 30 18 aquisição de calcário para Initiatives Development correção de PH do solo AI2 - 2 / Contratação de Component 1: Sustainable Community serviço de impressão para 2017-12- 2018-08- 2017-12- 2018-09- 2018-01- 2018-10- 2018-01- 2018-10- 2018-01- 2018-10- 2019-01- 2019-07- TF / 18765 and Adaptive Community Post Driven Limited 3,358.93 Completed produção de peças de 16 28 30 12 06 11 08 11 17 17 12 17 Initiatives Development comunicação. SUB 100 - 1 / Contratação de serviço de mediador para Component 1: Sustainable Community Pending 2018-01- 2018-02- 2018-02- 2018-02- 2018-02- 2018-05- encontro do grupo de TF / 18765 and Adaptive Community Post Driven Limited 0.00 Implement 25 08 17 19 26 28 soberania alimentar - roças Initiatives Development ation tradicionais e desafio de hoje. SUB 85 - 1 / Serviço de Component 1: Sustainable Community Assessoria técnica para 2018-01- 2018-03- 2018-01- 2018-03- 2018-02- 2018-03- 2018-02- 2018-04- 2018-02- 2018-05- 2019-07- TF / 18765 and Adaptive Community Post Driven Limited 11,516.31 Signed recuperação das áreas 15 23 29 23 05 26 09 24 16 07 21 Initiatives Development degradadas. AI1 - 1 / Serviço de articulação indígena para Component 1: Sustainable Community Pending dar suporte no 2018-01- 2018-01- 2018-01- 2018-01- 2018-02- 2018-04- TF / 18765 and Adaptive Community Post Driven Limited 0.00 Implement planejamento, mobilizar os 09 22 30 31 06 07 Initiatives Development ation participantes indígenas, elaborar relatoria - ARTICULADOR 1 AI1 - 2 / Serviço de articulação indígena para Component 1: Sustainable Community Pending dar suporte no 2018-01- 2018-01- 2018-01- 2018-01- 2018-02- 2018-04- TF / 18765 and Adaptive Community Post Driven Limited 0.00 Implement planejamento, mobilizar os 22 29 30 31 06 07 Initiatives Development ation participantes indígenas, elaborar relatoria - ARTICULADOR 2. AI1 - 3 / Contratação de serviço de técnico especializado de terceiros Component 1: Sustainable Community Pending 2017-12- 2017-12- 2017-12- 2017-12- 2018-01- 2018-05- para elaboração de site TF / 18765 and Adaptive Community Post Driven Limited 0.00 Implement 05 18 26 28 02 02 institucional e treinamento Initiatives Development ation de indígena para atualização de conteúdos. AI1 - 4 / Contratação de serviço logística com locação de espaço de Component 1: Sustainable Community Pending reunião, hospedagem e 2017-12- 2017-12- 2017-12- 2017-12- 2018-01- 2018-05- TF / 18765 and Adaptive Community Post Driven Limited 0.00 Implement alimentação para realização 05 18 26 27 02 02 Initiatives Development ation de eventos do Planejamento Estratégico para fortalecimento político e institucional da MOPIC. AI3 - 1 / Contratação de serviço de confecção de material de divulgação da Component 1: Sustainable Community 2017-12- 2019-01- 2018-02- 2019-01- 2018-02- 2019-01- 2018-02- 2019-01- 2018-02- 2019-02- 2018-05- 2019-02- feira dos produtos do TF / 18765 and Adaptive Community Post Driven Limited 761.39 Completed 26 25 08 25 15 29 19 31 26 01 28 11 babaçu e agricultura Initiatives Development familiar como banners, bandeiras e faixas e outros. BR-CAA-39558-NC-RFQ / Contratacao de empresa para fornecimento de serviço de coffe break para Component 3: Project Pending realizacao de treinamento e Request for Single Stage - One 2018-01- 2018-02- 2018-03- TF / 18765 Management, Monitoring Post Limited 0.00 Implement planejamento equipe e Quotations Envelope 15 03 05 and Evaluation ation estagiarios para visita de checagem do segundo edital do projeto DGM. A ser realizado em Montes Claros MG SUB 98 - 16 / Contratacao de profissional tecnica para Component 1: Sustainable Community Pending 2018-01- 2018-01- 2018-02- 2018-02- 2018-02- 2018-04- assessorar no mapeamento TF / 18765 and Adaptive Community Post Driven Limited 0.00 Implement 19 29 12 14 20 21 das areas de abundância no Initiatives Development ation entorno da aldeia Porteira. SUB 135-24 / Serviços de mao de obra especializada Component 1: Sustainable Community Pending em bio construcao para 2018-01- 2018-02- 2018-02- 2018-02- 2018-02- 2018-05- TF / 18765 and Adaptive Community Post Driven Limited 0.00 Implement execucao e 22 01 09 12 16 17 Initiatives Development ation acompanhamento de construcao de galpao para armazenamento de sementes SUB 26-17 / CT26.17 Contratacao de profissional Component 1: Sustainable tecnico para fazer o Request for Single Stage - One 2017-07- 2017-08- 2017-10- TF / 18765 and Adaptive Community Post Limited 0.00 Canceled mapeamento da morraria Quotations Envelope 31 30 29 Initiatives com entrega do mapa etnoambiental SUB 108-27 / Contratacao de prestação de servicos Component 1: Sustainable Community Pending para realizacao de 2018-01- 2018-02- 2018-02- 2018-02- 2018-02- 2018-05- TF / 18765 and Adaptive Community Post Driven Limited 0.00 Implement capacitacao em boas 22 02 12 15 22 23 Initiatives Development ation praticas para produção de alimentos tecnicas comunitarias SUB 108-28 / Contratacao de prestacao de servicos Component 1: Sustainable Community Pending para realizacao de 2018-01- 2018-02- 2018-02- 2018-02- 2018-02- 2018-05- TF / 18765 and Adaptive Community Post Driven Limited 0.00 Implement capacitacao em gestao da 22 05 12 15 22 23 Initiatives Development ation unidade de beneficiamento produtos locais SUB 113-21 / Contratacao Component 1: Sustainable Community Pending 2018-01- 2018-02- 2018-02- 2018-02- 2018-03- 2018-05- de oficineiro para realizacao TF / 18765 and Adaptive Community Post Driven Limited 0.00 Implement 25 08 15 21 01 20 de oficina de apicultura Initiatives Development ation SUB 142-16 / Serviços acompanhamento do Component 1: Sustainable Community Pending 2018-01- 2018-02- 2018-02- 2018-02- 2018-02- 2018-12- processo de abertura da TF / 18765 and Adaptive Community Post Driven Limited 0.00 Implement 23 06 15 19 24 21 roça e produção do relatório Initiatives Development ation - comunitário 2 SUB 91-10 / Serviço Técnico de apoio para execução do projeto no processo de implantação do Component 1: Sustainable Community 2018-01- 2020-07- 2018-02- 2020-07- 2018-02- 2020-07- 2018-02- 2020-07- 2018-02- 2020-07- 2018-07- 2020-08- viveiro de mudas, de TF / 18765 and Adaptive Community Post Driven Limited 1,144.36 Completed 25 17 07 17 15 22 19 24 26 28 06 11 beneficiamento de sementes Initiatives Development para plantio na fase de estufa, planejamento e orientação técnica na recuperação da APP. SUB 98 - 4 / Serviço Técnico de apoio para execução do projeto para Component 1: Sustainable Community 2018-01- 2018-01- 2018-02- 2018-02- 2018-02- 2018-04- ministrar um curso aos TF / 18765 and Adaptive Community Post Driven Limited 0.00 Canceled 22 30 12 16 23 24 membros da diretoria da Initiatives Development associação e comunidade sobre rotinas administrativas. SUB 88-7 / Serviço Técnico Component 1: Sustainable Request for Single Stage - One 2018-01- 2018-02- 2019-05- de apoio para execução do TF / 18765 and Adaptive Community Post Limited 0.00 Canceled Quotations Envelope 29 15 12 projeto. Initiatives SUB 30 - 11 / Serviço de Component 1: Sustainable instrutor para capacitação Request for Single Stage - One 2017-11- 2017-11- 2018-01- TF / 18765 and Adaptive Community Post Limited 0.00 Canceled na área de gestão Quotations Envelope 11 28 29 Initiatives administrativa e financeira . SUB 30 - 12 / Serviço de Component 1: Sustainable instrutor para capacitação Request for Single Stage - One 2017-10- 2017-11- 2017-12- TF / 18765 and Adaptive Community Post Limited 0.00 Canceled na área de elaboração de Quotations Envelope 28 14 15 Initiatives projetos. SUB 30 - 13 / Serviço de Component 1: Sustainable Request for Single Stage - One 2017-10- 2017-10- 2017-11- instrutor para capacitação TF / 18765 and Adaptive Community Post Limited 0.00 Canceled Quotations Envelope 09 25 25 em gestão e legislação Initiatives ambiental. SUB 30-34 / SUB 30-34 Component 1: Sustainable Community Pending Serviço de apoio operacional 2018-01- 2018-01- 2018-02- 2018-02- 2018-02- 2019-06- TF / 18765 and Adaptive Community Post Driven Limited 0.00 Implement para execução das 15 22 05 09 16 01 Initiatives Development ation atividades subprojeto TAPAGUIA. SUB 143 -1 / SUB 143 -1 Serviço de apoio operacional Component 1: Sustainable Community Pending 2018-01- 2018-01- 2018-02- 2018-02- 2018-02- 2019-03- para execução das TF / 18765 and Adaptive Community Post Driven Limited 0.00 Implement 15 25 02 03 05 14 atividades subprojeto Povos Initiatives Development ation do Roncador. SUB 93-1 / SUB 93-1 Component 1: Sustainable Community Serviço de apoio operacional 2018-01- 2018-04- 2018-01- 2018-04- 2018-02- 2018-04- 2018-02- 2018-05- 2018-02- 2018-05- 2018-12- TF / 18765 and Adaptive Community Post Driven Limited 3,615.52 Signed para execução das 12 19 19 19 02 20 06 04 13 28 10 Initiatives Development atividades subprojeto Pyka Mix. SUB 125 - 5 / SUB 125 - 5 Component 1: Sustainable Community Pending serviço de apoio operacional 2018-01- 2018-02- 2018-02- 2018-02- 2018-02- 2019-10- TF / 18765 and Adaptive Community Post Driven Limited 0.00 Implement para execução das 19 02 09 12 19 13 Initiatives Development ation atividades subprojeto Terena. SUB 108-26 / SUB 108-26 Component 1: Sustainable Community Pending serviço de apoio operacional 2018-01- 2018-01- 2018-02- 2018-02- 2018-02- 2019-07- TF / 18765 and Adaptive Community Post Driven Limited 0.00 Implement para execução das 16 22 05 09 16 01 Initiatives Development ation atividades subprojeto Yomono. SUB 134-14 / SUB 134-14 Component 1: Sustainable Community Serviço de apoio operacional 2018-01- 2018-06- 2018-01- 2018-06- 2018-02- 2018-06- 2018-02- 2018-06- 2018-02- 2018-07- 2019-03- TF / 18765 and Adaptive Community Post Driven Limited 3,022.75 Signed para execução das 19 20 29 20 12 20 14 20 21 27 28 Initiatives Development atividades subprojeto UBAWAWE. SUB 25-8 N / Serviços Component 1: Sustainable gráficos de impressão de Request for Single Stage - One 2018-05- 2018-06- 2018-07- TF / 18765 and Adaptive Community Post Limited 0.00 Canceled apostila para atividade Quotations Envelope 15 04 06 Initiatives Oficina sobre plantio de mudas. SUB 25-11 N / Serviços Component 1: Sustainable Request for Single Stage - One 2019-01- 2019-02- 2019-03- gráficos de impressão de TF / 18765 and Adaptive Community Post Limited 0.00 Canceled Quotations Envelope 30 19 23 cartilha. Initiatives Page 14 SUB 120-1 / Contratação Component 1: Sustainable 2017-09- 2017-10- 2017-10- 2019-03- de serviços de TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled 21 05 23 07 cozinheiras/os Initiatives SUB 120-2 / Contratação Component 1: Sustainable 2017-08- 2017-09- 2017-09- 2019-05- de serviços de articuladores TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled 28 11 28 22 indígenas. Initiatives SUB 26 -15 / SUB 26.15 Component 1: Sustainable Community Under Serviço de apoio operacional 2018-02- 2017-10- 2018-03- 2017-10- 2018-04- 2017-11- 2018-05- 2018-06- 2018-12- TF / 18765 and Adaptive Community Post Driven Limited 0.00 Implement para execução das 28 24 05 31 16 07 16 20 17 Initiatives Development ation atividades subprojeto ARPEP SUB 25- 7 N / Serviço de Component 1: Sustainable Community Pending 2018-02- 2018-02- 2018-03- 2018-03- 2018-03- 2019-12- apoio operacional para a TF / 18765 and Adaptive Community Post Driven Limited 0.00 Implement 22 28 09 12 16 26 execução do subprojeto. Initiatives Development ation SUB 25-9 N / Serviço de fornecimento diversos lanches produzidos para as capacitações, Formação da Component 1: Sustainable Pending comunidade sobre Request for Single Stage - One 2018-03- 2018-04- 2018-08- TF / 18765 and Adaptive Community Post Limited 0.00 Implement recuperação ambiental, Quotations Envelope 20 06 04 Initiatives ation Identificação de nascentes, Oficina sobre plantio de mudas, Seminário temático em agroecologia e avaliação. SUB 100 -10 / Contratação de serviço de apoio Component 1: Sustainable Community 2018-03- 2018-06- 2018-03- 2018-06- 2018-04- 2018-06- 2018-04- 2018-07- 2018-04- 2018-07- 2019-12- operacional para TF / 18765 and Adaptive Community Post Driven Limited 8,646.39 Signed 15 06 22 06 05 21 09 20 16 20 07 implantação de sistemas Initiatives Development agroflorestais e práticas de manejo SUB 116-25 / CT116.25 Component 1: Sustainable Contratação de serviços Request for Single Stage - One 2017-08- 2020-07- 2017-09- 2020-08- 2017-10- 2020-08- TF / 18765 and Adaptive Community Post Limited 1,410.36 Completed para montagem de seis Quotations Envelope 21 20 13 06 23 12 Initiatives sistemas de irrigação SUB 116-26 / CT116.26 Component 1: Sustainable Contratação de serviços Request for Single Stage - One 2017-08- 2017-09- 2017-10- TF / 18765 and Adaptive Community Post Limited 0.00 Canceled para montagem de seis Quotations Envelope 25 14 19 Initiatives estufas das hortas SUB 116-27 / CT116.27 Contratação de serviços técnico as famílias beneficiarias para Component 1: Sustainable Implantação dos três Request for Single Stage - One 2017-08- 2017-08- 2017-10- TF / 18765 and Adaptive Community Post Limited 0.00 Canceled Agroquintais Aspectos de Quotations Envelope 02 25 24 Initiatives abertura de berços e plantio das mudas Preparo de defensivos naturais Orientação das familias sobre tratos culturais e adubacao SUB 116-28 / CT116.28 Cotratacao de serviços técnicos para Mobilização Curso teórico e pratico Component 1: Sustainable Request for Single Stage - One 2017-08- 2017-08- 2018-06- sobre a coleta seletiva e TF / 18765 and Adaptive Community Post Limited 0.00 Canceled Quotations Envelope 03 28 24 destinação do lixo Initiatives Monitoramento da coleta seletiva do lixo e elaboração de relatórios sobre a poluicao da comunidade SUB 116-29 / CT116.29 Contratação de serviços técnicos para: Mobilização Component 1: Sustainable Request for Single Stage - One 2017-08- 2017-09- 2019-06- de famílias aptas a TF / 18765 and Adaptive Community Post Limited 0.00 Canceled Quotations Envelope 28 18 10 comercializar Initiatives Acompanhamento e orientação dos produtores nas feiras SUB 116-30 / CT116.30 Contratação de serviços Component 1: Sustainable técnicos para orientação Request for Single Stage - One 2017-10- 2017-11- 2018-01- TF / 18765 and Adaptive Community Post Limited 0.00 Canceled pratica sobre o processo de Quotations Envelope 31 23 02 Initiatives decantação simples da água do rio SUB 116-31 / CT116.31 Contratação de serviços Component 1: Sustainable técnicos para mapeamento Request for Single Stage - One 2018-01- 2018-02- 2018-03- TF / 18765 and Adaptive Community Post Limited 0.00 Canceled das famílias que precisam Quotations Envelope 20 12 24 Initiatives do CAR e Georeferenciamento das áreas para gerar o CAR SUB 116-32 / CT116.32 Contratação de serviços técnico para treinamento as família quanto a Preparação Component 1: Sustainable das áreas para receber as Request for Single Stage - One 2017-08- 2017-09- 2017-12- TF / 18765 and Adaptive Community Post Limited 0.00 Canceled hortas Preparação e plantio Quotations Envelope 11 04 03 Initiatives de canteiros Transplante das mudas Orientação as famílias sobre preparo de defensivos natuais SUB 116-33 / CT116.33 Contratação de serviços de assessoramento técnico Component 1: Sustainable Request for Single Stage - One 2017-09- 2017-10- 2018-05- para Avaliação e TF / 18765 and Adaptive Community Post Limited 0.00 Canceled Quotations Envelope 28 19 17 monitoramento dos Initiatives resultados e Estruturação de quatro relatórios descritivos de atividades SUB 116-35 / Serviço de Component 1: Sustainable Community apoio operacional para 2018-03- 2018-06- 2018-03- 2018-06- 2018-04- 2018-06- 2018-04- 2018-06- 2018-04- 2018-07- 2019-12- TF / 18765 and Adaptive Community Post Driven Limited 15,211.48 Signed execução das atividades 15 19 22 19 04 28 09 30 17 31 08 Initiatives Development subprojeto ASSEMA SUB 129 - 8 / Contratação de serviços de apoio Component 1: Sustainable Community Pending 2018-07- 2018-07- 2018-08- 2018-08- 2018-08- 2018-10- operacional para articulação TF / 18765 and Adaptive Community Post Driven Limited 0.00 Implement 11 23 02 10 30 30 de atividades de produção Initiatives Development ation do artesanato e monitoramento do território. SUB 129 - 10 / Contratação Component 1: Sustainable Pending Request for Single Stage - One 2018-07- 2018-08- 2018-11- de serviços de moderador TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 23 30 01 de oficina sobre comércio Initiatives ation justo. SUB 129 - 12 / Contratação Component 1: Sustainable Pending de serviços de edição de Request for Single Stage - One 2018-07- 2018-08- 2018-10- TF / 18765 and Adaptive Community Post Limited 0.00 Implement vídeos, a ser realizado por Quotations Envelope 23 30 01 Initiatives ation um indígena da comunidade. SUB 129 - 13 / Contratação Component 1: Sustainable Pending Request for Single Stage - One 2018-07- 2018-08- 2018-10- de mão de obra de pedreiro TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 23 30 01 para construção de galpão. Initiatives ation SUB 129 - 14 / Contratação Component 1: Sustainable Pending Request for Single Stage - One 2018-06- 2018-08- 2018-10- de serviços de transporte de TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 22 30 01 passageiros para Initiatives ation expedições. SUB 123 -3 / Contratação de técnico em Component 1: Sustainable bioconstrução para Request for Single Stage - One 2018-03- 2018-04- 2018-06- TF / 18765 and Adaptive Community Post Limited 0.00 Canceled construção de forno para Quotations Envelope 28 10 11 Initiatives queima de cerâmica, conforme os conhecimentos tradicionais. SUUB 129 - 9 / Contratação Component 1: Sustainable Pending de serviços de moderador Request for Single Stage - One 2018-07- 2018-08- 2018-10- TF / 18765 and Adaptive Community Post Limited 0.00 Implement de oficina sobre economia Quotations Envelope 23 30 31 Initiatives ation solidária. SUB 129 - 11 / Contratação Component 1: Sustainable de serviços de captação de Request for Single Stage - One 2018-07- 2018-08- 2018-10- TF / 18765 and Adaptive Community Post Limited 0.00 Canceled imagens das atividades do Quotations Envelope 23 30 30 Initiatives projeto na aldeia. SUB 142-15 / Serviços de edição de videos a partir Component 1: Sustainable Community 2018-01- 2018-01- 2018-02- 2018-02- 2018-02- 2018-08- dos registros audiovisuais TF / 18765 and Adaptive Community Post Driven Limited 0.00 Canceled 15 29 05 09 16 15 realizados nas oficinas e na Initiatives Development festa de colheita do milho SUB 142 -2 / Contratação de apoio operacional para Component 1: Sustainable Community acompanhamento e 2018-01- 2018-05- 2018-02- 2018-05- 2018-02- 2018-05- 2018-02- 2019-05- 2018-02- 2019-06- 2018-03- 2020-02- TF / 18765 and Adaptive Community Post Driven Limited 3,764.56 Completed avaliação de oficinas e 23 14 06 16 15 25 18 28 23 11 26 20 Initiatives Development atividades do projeto e apoio à edição e registro de imagens captadas. SUB 98 -3 / Contratação de profissional técnico para Component 1: Sustainable Community elaboração do projeto do 2017-12- 2017-12- 2018-01- 2018-01- 2018-01- 2018-03- TF / 18765 and Adaptive Community Post Driven Limited 0.00 Canceled viveiro para produção de 15 29 05 09 16 17 Initiatives Development 10.000 mudas/ano (nativas e frutíferas). SUB 105-16 / Contratação de agente local para Component 1: Sustainable Community Pending mobilização e 2018-05- 2018-05- 2018-05- 2018-05- 2018-06- 2020-01- TF / 18765 and Adaptive Community Post Driven Limited 0.00 Implement acompanhamento das 10 13 23 28 03 24 Initiatives Development ation atividades do projeto na Comunidade Quilombola Carrapato. SUB 105-19 / Contratação Component 1: Sustainable Community Pending de agente local para 2018-05- 2018-05- 2018-06- 2018-06- 2018-06- 2019-06- TF / 18765 and Adaptive Community Post Driven Limited 0.00 Implement acompanhamento a 20 23 02 05 13 08 Initiatives Development ation Caravana Quilombola do Jalapão. SUB 105-17 / Contratação de agente local para Component 1: Sustainable Community Pending mobilização e 2018-05- 2018-05- 2018-05- 2018-06- 2018-06- 2020-01- TF / 18765 and Adaptive Community Post Driven Limited 0.00 Implement acompanhamento das 10 13 23 04 09 30 Initiatives Development ation atividades do projeto na comunidade quilombola Barra do Aroeira. SUB 129 - 7 / Contratação de serviços com Component 1: Sustainable Pending Request for Single Stage - One 2018-07- 2018-08- 2018-10- acompanhamento da obra TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 23 30 29 do ateliê, nos moldes da Initiatives ation bioconstrução. SUB 105-4 / CQ105.4 Contratação de Agente Local Component 1: Sustainable Community comunitário para 2018-05- 2018-08- 2018-05- 2018-08- 2018-05- 2018-07- 2018-05- 2018-08- 2018-05- 2018-08- 2019-10- TF / 18765 and Adaptive Community Post Driven Limited 3,561.71 Signed mobilização e apoio nas 10 03 13 03 16 20 19 29 24 29 06 Initiatives Development atividades para Comunidade Quilombola Prada. SUB 105-18 / Contratação de agente local para Component 1: Sustainable Community Pending mobilização e 2018-05- 2018-05- 2018-06- 2018-07- 2018-08- 2019-02- TF / 18765 and Adaptive Community Post Driven Limited 0.00 Implement acompanhamento das 10 13 24 24 28 24 Initiatives Development ation atividades do projeto na comunidade quilombola Boa Esperança. SUB 16-18 / Contratação Component 1: Sustainable Community de serviço de apoio 2018-03- 2018-03- 2018-03- 2018-04- 2018-04- 2019-11- TF / 18765 and Adaptive Community Post Driven Limited 0.00 Canceled operacional para execução 15 20 30 04 08 29 Initiatives Development do projeto técnico subprojeto 16 SUB 42-17 / Serviços de serraria para construção de Component 1: Sustainable uma base de apoio para 2017-09- 2017-10- 2017-10- 2018-02- TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled vigilância (barracão) em 22 06 24 02 Initiatives local estratégico na terra indígena krahô-kanela SUB 42-19 / Serviços de Component 1: Sustainable 2017-10- 2017-11- 2017-11- 2018-01- mão de obra 1 para TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled 25 08 25 25 abertura de poço Initiatives SUB 42-20 / Serviços de Component 1: Sustainable 2017-10- 2017-11- 2017-11- 2018-01- mão de obra 2 para TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled 25 08 25 25 abertura de poço Initiatives SUB 42-21 / Serviços de Component 1: Sustainable 2017-10- 2017-11- 2017-11- 2018-01- mão de obra 3 para TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled 25 08 25 25 abertura de poço. Initiatives SUB 3-12 / Contratação de serviços de operador de Component 1: Sustainable Request for Single Stage - One 2017-09- 2017-11- 2017-12- máquina para oficina de TF / 18765 and Adaptive Community Post Limited 0.00 Canceled Quotations Envelope 27 03 14 capacitação de construção Initiatives de barraginhas. SUB 3-13 / Contratação de Component 1: Sustainable serviços de locação de Request for Single Stage - One 2017-10- 2017-11- 2017-12- TF / 18765 and Adaptive Community Post Limited 0.00 Canceled caminhão para transporte Quotations Envelope 02 07 19 Initiatives de pá carregadeira. SUB 3-17 / Serviço de Component 1: Sustainable Request for Single Stage - One 2017-10- 2017-10- 2017-11- manutenção de pá TF / 18765 and Adaptive Community Post Limited 0.00 Canceled Quotations Envelope 13 30 29 carregadeira. Initiatives SUB 16-15 / CQ16-15 Contratação de profissional Component 1: Sustainable Request for Single Stage - One 2017-06- 2017-08- 2017-11- para ministrar oficina para TF / 18765 and Adaptive Community Post Limited 0.00 Canceled Quotations Envelope 25 03 01 implantação de sistemas Initiatives agroflorestais SUB 16-22 / Contratação Component 1: Sustainable de profissional para realizar Request for Single Stage - One 2018-05- 2018-08- 2018-06- 2018-08- 2018-10- 2019-05- TF / 18765 and Adaptive Community Post Limited 1,980.00 Completed serviço de cercamento das Quotations Envelope 30 01 17 23 15 23 Initiatives nascentes. SUB 120-5 / Contratação de serviços para captação e edição de imagens para Component 1: Sustainable Pending produção de vídeo Request for Single Stage - One 2017-09- 2017-10- 2019-06- TF / 18765 and Adaptive Community Post Limited 0.00 Implement documentário sobre o Quotations Envelope 29 17 10 Initiatives ation movimento das Mulheres Yarang, no Território Indígena do Xingu. SUB 109-12 / CT109.12 Contratação de profissional para assessoramento da reforma e da planta da Component 1: Sustainable Request for Single Stage - One 2017-07- 2017-08- 2018-04- agroindústria com os TF / 18765 and Adaptive Community Post Limited 0.00 Canceled Quotations Envelope 28 16 03 gestores públicos Initiatives regulamentadores da legislação sanitária e Realizar treinamento boas praticas comercialização SUB 42-6 / Serviço de 01 pedreiro para realizar a Component 1: Sustainable adequação de barracão para Request for Single Stage - One 2017-09- 2018-07- 2017-10- 2018-08- 2017-11- 2018-12- TF / 18765 and Adaptive Community Post Limited 2,342.53 Completed servir de sede do projeto e Quotations Envelope 19 18 06 22 06 20 Initiatives para acondicionar equipamentos BR-CAA-39551-NC-RFQ / Contratação de serviços para realização de evento para cerca de 20 pessoas, Component 1: Sustainable em Montes Claros-MG: Request for Single Stage - One 2018-07- 2018-07- 2018-08- 2018-07- 2018-09- 2018-08- TF / 18765 and Adaptive Community Post Limited 5,943.86 Completed Oficina de Elaboração de Quotations Envelope 17 24 03 31 02 30 Initiatives Projetos, incluindo as etapas de hospedagem, alimentação e locação de espaço e equipamentos. BR-CAA-39552-NC-RFQ / Contratação de serviços para realização de evento para cerca de 20 pessoas, Component 1: Sustainable Pending em Brasília-DF: Oficina de Request for Single Stage - One 2018-07- 2018-08- 2018-09- TF / 18765 and Adaptive Community Post Limited 0.00 Implement Elaboração de Projetos, Quotations Envelope 22 08 07 Initiatives ation incluindo as etapas de hospedagem, alimentação e locação de espaço e equipamentos. BR-CAA-39553-NC-RFQ / Contratação de serviços para realização de evento para cerca de 20 pessoas, Component 1: Sustainable em Cuiabá-MT: Oficina de Request for Single Stage - One 2018-07- 2018-08- 2018-08- 2018-08- 2018-09- 2018-09- TF / 18765 and Adaptive Community Post Limited 11,589.51 Completed Elaboração de Projetos, Quotations Envelope 27 02 13 14 12 28 Initiatives incluindo as etapas de hospedagem, alimentação e locação de espaço e equipamentos. BR-CAA-39554-NC-RFQ / Contratação de profissional especializado em Component 1: Sustainable Pending Educomunicação /midias Request for Single Stage - One 2018-07- 2018-08- 2018-09- TF / 18765 and Adaptive Community Post Limited 0.00 Implement sociais para sensibilização Quotations Envelope 17 03 02 Initiatives ation dos subprojetos na importância do uso do plano de comunicação. BR-CAA-39555-NC-RFQ / Contratação de serviços de projeto e produção gráfica Component 2: Capacity Pending Request for Single Stage - One 2018-07- 2018-08- 2018-09- de cartilha para divulgação TF / 18765 Building and Institutional Post Limited 0.00 Implement Quotations Envelope 17 03 02 dos projetos, com entrega Strengthening ation de arquivos para publicação digital e para impressão. AI2 - 1 / Contratação de Component 1: Sustainable Community serviços de contabilidade 2018-08- 2018-10- 2018-08- 2018-10- 2018-09- 2018-11- 2018-09- 2018-11- 2018-09- 2018-11- 2019-09- 2019-02- TF / 18765 and Adaptive Community Post Driven Limited 3,655.28 Completed para realização de 20 30 25 30 04 01 06 14 13 26 08 08 Initiatives Development balancetes anuais da Rede Cerrado. Page 15 BR-CAA-39550-NC-RFQ / Contratação de serviços para fornecimento de alimentação (lanche, almoço Component 2: Capacity e jantar) para 4 Request for Single Stage - One 2018-09- 2018-09- 2018-09- 2018-10- 2018-11- 2018-12- TF / 18765 Building and Institutional Post Limited 6,800.12 Completed capacitações, para público Quotations Envelope 10 12 30 11 29 10 Strengthening composto de sócios do CAA e membros dos subprojetos, a ser realizada em Montes Claros - Público total de 130 pessoas. BR-CAA-39556-NC-RFQ / Contratação de serviços de tabulação de dados das Component 2: Capacity Pending Request for Single Stage - One 2018-09- 2018-10- 2018-12- pesquisas realizadas TF / 18765 Building and Institutional Post Limited 0.00 Implement Quotations Envelope 12 04 03 durante as visitas de Strengthening ation checagem dos subprojetos dos editais 1 e 2 (marco 0). SUB 100 -15 / Serviços de Component 1: Sustainable Pending diagramação e impressão de Request for Single Stage - One 2018-11- 2018-12- 2019-02- TF / 18765 and Adaptive Community Post Limited 0.00 Implement materiais de divulgação da Quotations Envelope 17 10 08 Initiatives ation cultura indígena chiquitano. SUB 100 -17 / Contratação de serviços de locação de Component 1: Sustainable Pending Request for Single Stage - One 2018-11- 2018-12- 2019-01- transporte - participantes TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 17 10 09 de intercâmbio e atividades Initiatives ation do projeto. SUB 125-29 / Contratação Component 1: Sustainable Pending de Empresa de Engenharia e Request for Single Stage - One 2018-12- 2018-12- 2019-04- TF / 18765 and Adaptive Community Post Limited 0.00 Implement obras para construção de Quotations Envelope 01 20 19 Initiatives ation unidade de beneficiamento SUB 127-21 / Servico de Component 1: Sustainable Pending empreita de mao de obra de Request for Single Stage - One 2017-12- 2018-01- 2018-04- TF / 18765 and Adaptive Community Post Limited 0.00 Implement pedreiro para construcao do Quotations Envelope 28 15 25 Initiatives ation centro SUB 75-11 / Contratação de serviços de pedreiro para Component 1: Sustainable Pending Request for Single Stage - One 2018-12- 2019-01- 2019-07- construção do Centro de TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 01 26 25 Turismo Sustentável, para Initiatives ation os Festejos Kalungas. AI3 - 2 / Contratação de serviço transporte de duas vans da regional Pará até Component 1: Sustainable Community Pending 2019-01- 2019-01- 2019-01- 2019-01- 2019-02- 2019-03- São Domingos do Araguaia, TF / 18765 and Adaptive Community Post Driven Limited 0.00 Implement 21 23 30 31 03 05 para participar do VIII Initiatives Development ation Encontrão das Quebradeiras de Coco Babaçu AI3 - 3 / Contratação de serviço transporte de ônibus para deslocamento das mulheres da regional Component 1: Sustainable Request for Single Stage - One 2019-01- 2019-02- 2019-02- 2019-02- 2019-03- 2019-02- Imperatiz até São Domingos TF / 18765 and Adaptive Community Post Limited 3,169.34 Completed Quotations Envelope 23 01 03 05 05 12 do Araguaia - PA, para Initiatives participar do VIII Encontrão das Quebradeiras de Coco Babaçu AI3- 4 / Contratação de serviço transporte de ônibus para deslocamento das mulheres da regional Component 1: Sustainable Pending Request for Single Stage - One 2019-01- 2019-02- 2019-03- Tocantins até São Domingos TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 23 03 05 do Araguaia - PA, para Initiatives ation participar do VIII Encontrão das Quebradeiras de Coco Babaçu AI3 - 6 / Contratação de serviço transporte de ônibus para deslocamento das mulheres das regionais Component 1: Sustainable Pending Request for Single Stage - One 2019-01- 2019-02- 2019-03- Baixada e Mearim Tocantins TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 23 03 05 até São Domingos do Initiatives ation Araguaia - PA, para participar do VIII Encontrão das Quebradeiras de Coco Babaçu AI3 - 7 / Contratação de serviço transporte de ônibus para deslocamento das Component 1: Sustainable mulheres da regional Piauí Request for Single Stage - One 2019-01- 2019-02- 2019-02- 2019-02- 2019-03- 2019-02- TF / 18765 and Adaptive Community Post Limited 1,804.30 Completed até São Domingos do Quotations Envelope 23 01 03 04 05 12 Initiatives Araguaia - PA, para participar do VIII Encontrão das Quebradeiras de Coco Babaçu AI3 - 3 / Contratação de serviços audiovisuais pessoa Component 1: Sustainable Community 2018-03- 2018-03- 2018-04- 2018-04- 2018-04- 2018-07- física para produção de TF / 18765 and Adaptive Community Post Driven Limited 0.00 Canceled 14 28 04 09 16 16 filmes, fotografias, áudio, Initiatives Development entre outras atividades. BR-CAA-39560-NC-RFQ / Contratação de serviços de transporte para realização Component 2: Capacity Under de traslado - aeroporto- Request for Single Stage - One 2019-01- 2019-02- 2019-02- 2019-03- TF / 18765 Building and Institutional Post Limited 0.00 Implement rodoviária/hotel/aeroporto- Quotations Envelope 26 06 09 11 Strengthening ation rodoviária e dia de campo, durante participação de curso a ser realizado em Brasília/DF BR-CAA-39561-NC-RFQ / Component 2: Capacity Pending Contratação de serviços Request for Single Stage - One 2019-01- 2019-02- 2019-03- TF / 18765 Building and Institutional Post Limited 0.00 Implement para impressão de agendas Quotations Envelope 26 09 26 Strengthening ation personalizadas. BR-CAA-39562-NC-RFQ / Contratação de empresa especializada, para Component 3: Project Request for Single Stage - One 2019-02- 2019-04- 2019-03- 2019-04- 2020-12- realização de auditoria TF / 18765 Management, Monitoring Post Limited 12,739.29 Signed Quotations Envelope 07 04 07 26 16 externa na documentação and Evaluation relativa ao projeto, nos exercícios de 2018, 2019 e 2020. SUB 16-6 / CQ16-6 Serviços de moderação e Component 1: Sustainable instrução de instrutor da 2017-06- 2017-07- 2017-07- 2017-09- TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled comunidade para ministrar 19 09 23 06 Initiatives a oficina de Conhecimentos de Plantas Medicinais do Cerrado SUB 26-13 / CT26.13 Component 1: Sustainable 2017-08- 2017-08- 2017-09- 2017-11- Contratacao de serviço geral TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled 18 23 15 14 de viveirista por diarias Initiatives SUB 26-14 / CT26.14 Component 1: Sustainable 2017-11- 2017-11- 2017-12- 2018-02- Contratacao de servico de TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled 22 27 20 18 pedreiro por diaria Initiatives SUB 110-19 / Serviços gráficos de impressão de Component 1: Sustainable Pending material didático para as Request for Single Stage - One 2017-08- 2017-08- 2018-01- TF / 18765 and Adaptive Community Post Limited 0.00 Implement oficinas de capacitação em Quotations Envelope 02 24 21 Initiatives ation Recuperação Ambiental e Agroecologia. + Banner SUB 110-20 / CQ110.20 Contratação de serviços gerais, por diária, para Component 1: Sustainable 2017-07- 2017-08- 2017-08- 2017-11- cercamento da área critica TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled 26 05 14 12 para fins de regeneração Initiatives natural manejo agroflorestal agroecológico SUB 110-21 / CQ110.21 Contratação de serviços Component 1: Sustainable gerais, por diária, de 2017-11- 2017-11- 2017-12- 2018-01- TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled pedreiro para construção do 20 30 11 30 Initiatives viveiro e sala de armazenamento de sementes SUB 110-22 / CQ110.22 Contratação de serviços Component 1: Sustainable gerais, por diária, para 2017-07- 2017-08- 2017-08- 2017-09- TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled implantação de paliçadas 26 05 15 24 Initiatives para barreiras de contenção em voçorocas SUB 110-24 / CQ110.24 Contratação de serviços gerais, por diária, de Component 1: Sustainable 2017-07- 2017-08- 2017-08- 2019-04- cozinheira para oficinas de TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled 27 06 23 15 capacitação, reuniões Initiatives mensais organizativas e de monitoramento SUB 268 SC 6 / Contratação de oficineiro para realização Component 1: Sustainable Pending Request for Single Stage - One 2019-02- 2019-03- 2019-06- de 3 oficinas de TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 15 05 04 aperfeiçoamento do Initiatives ation artesanato produzido SUB 268 SC 07 / Component 1: Sustainable Pending Request for Single Stage - One 2019-02- 2019-03- 2019-06- Contratação de profissional TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 19 09 08 para construção de web site Initiatives ation SUB 173 SC 004 / Contratação de serviços de Component 1: Sustainable Request for Single Stage - One 2019-02- 2019-09- 2019-03- 2019-10- 2020-01- pedreiro comunitário para TF / 18765 and Adaptive Community Post Limited 3,822.67 Signed Quotations Envelope 19 30 09 09 04 execução da obra de Initiatives unidade de beneficiamento SUB 218 SC 002 / Aluguel de micro-ônibus/ônibus Component 1: Sustainable Pending Request for Single Stage - One 2019-02- 2019-03- 2020-01- para transporte dos TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 16 06 01 participantes dos mutirões Initiatives ation de resgate das tradições SUB 166 SC 001 / Component 1: Sustainable Contratação de empresa Request for Single Stage - One 2019-02- 2019-03- 2019-04- TF / 18765 and Adaptive Community Post Limited 0.00 Canceled para realização de obra da Quotations Envelope 19 09 09 Initiatives cozinha para processamento SUB 45-7 / CT45.7 Component 1: Sustainable Request for Single Stage - One 2017-06- 2017-07- 2017-09- Contratacao de servicos de TF / 18765 and Adaptive Community Post Limited 0.00 Canceled Quotations Envelope 28 17 15 pedreiros Initiatives SUB 45-9 / CT45.9 Contratacao de servico de Component 1: Sustainable moderacao e instrutoria Request for Single Stage - One 2017-07- 2017-07- 2017-09- TF / 18765 and Adaptive Community Post Limited 0.00 Canceled para curso sobre Quotations Envelope 04 28 06 Initiatives planejamento participativo e gestao compartilhada SUB 45-12 / CT45.12 Contratacao de servico de Component 1: Sustainable Request for Single Stage - One 2017-08- 2017-09- 2017-11- moderacao e instrutoria TF / 18765 and Adaptive Community Post Limited 0.00 Canceled Quotations Envelope 27 26 10 para uma oficina de gestao Initiatives financeira SUB 45-14 / CT45.14 Contratacao de servico de Component 1: Sustainable moderacao e instrutoria Request for Single Stage - One 2018-04- 2018-05- 2018-07- TF / 18765 and Adaptive Community Post Limited 0.00 Canceled para curso de prevencao de Quotations Envelope 22 28 12 Initiatives acidentes com animais peconhentos SUB 45-15 / CT45.15 Contratacao de servico de Component 1: Sustainable moderacao e instrutoria Request for Single Stage - One 2018-08- 2018-09- 2018-11- TF / 18765 and Adaptive Community Post Limited 0.00 Canceled para curso sobre manejo Quotations Envelope 13 17 01 Initiatives adequado e conservacao dos recursos naturais SUB 45-23 / CT45.23 Contratacao de um profissional tecnico com Component 1: Sustainable experiencia na area Request for Single Stage - One 2017-06- 2017-07- 2019-03- TF / 18765 and Adaptive Community Post Limited 0.00 Canceled agropecuaria vivencia em Quotations Envelope 25 19 11 Initiatives trabalhos com grupos de mulheres e que vem atuando na area da agricultura famíliar SUB 45-13 / CT45.13 Contratacao de servico de Component 1: Sustainable moderacao e instrutoria Request for Single Stage - One 2018-02- 2018-03- 2018-04- TF / 18765 and Adaptive Community Post Limited 0.00 Canceled para curso sobre boas Quotations Envelope 10 13 27 Initiatives praticas na manipulacao do azeite de coco SUB 55-11 / 55.11 Contratacao de servicos de Component 1: Sustainable Pending Request for Single Stage - One 2019-03- 2019-03- 2019-06- impressão de rótulos e TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 01 22 30 aquisição de um Datador Initiatives ation Automático. SUB 211 SC 004 / Contratação de serviços de Component 1: Sustainable Request for Single Stage - One 2019-02- 2019-10- 2019-03- 2019-10- 2019-04- pedreiro para construção, TF / 18765 and Adaptive Community Post Limited 1,689.50 Signed Quotations Envelope 23 03 13 11 13 instalação elétrica e Initiatives hidráulica da Casa de Cultura SUB 211 SC 005 / Contratação de serviços de Component 1: Sustainable mão-de-obra para estrutura Request for Single Stage - One 2019-02- 2019-03- 2019-04- TF / 18765 and Adaptive Community Post Limited 0.00 Canceled em madeira e cobertura em Quotations Envelope 23 13 13 Initiatives palha e piaçava para construção da Casa de Cultura SUB 179 SC 004 / Component 1: Sustainable Under Contratação de serviços Request for Single Stage - One 2019-02- 2020-09- 2019-03- 2019-04- TF / 18765 and Adaptive Community Post Limited 2,639.19 Implement para instalação do poço Quotations Envelope 23 17 13 13 Initiatives ation artesiano com placas de energia solar. BR-CAA-39559-NC-RFQ / Contratação de profissional para apoio junto as equipes de licitação e financeira das atividades físico-financeira Component 2: Capacity para implementação dos Request for Single Stage - One 2019-01- 2019-04- 2019-02- 2019-05- 2020-02- 2020-12- TF / 18765 Building and Institutional Post Limited 11,508.58 Completed cursos e Quotations Envelope 26 03 15 02 10 17 Strengthening Organização e acompanhamento logístico para implementação de cada curso, previstos no Plano de Capacitação. SUB 90-1 / CT90.1 Contratação de servicos de Component 1: Sustainable Pending rotulagem técnica Request for Single Stage - One 2017-07- 2017-07- 2017-09- TF / 18765 and Adaptive Community Post Limited 0.00 Implement obrigatória com Quotations Envelope 08 31 09 Initiatives ation levantamento e analise nutricional dos componentes dos produtos SUB 61-14 / CQ61.14 Contratação de serviço de Component 1: Sustainable Request for Single Stage - One 2017-08- 2017-09- 2017-10- instancio de dez TF / 18765 and Adaptive Community Post Limited 0.00 Canceled Quotations Envelope 09 04 04 computadores adquiridos Initiatives para o tele centro SUB 61-19 / CQ61.19 Contratação de profissional técnico para realizar Component 1: Sustainable Request for Single Stage - One 2018-01- 2018-02- 2018-04- capacitação sobre a TF / 18765 and Adaptive Community Post Limited 0.00 Canceled Quotations Envelope 17 12 03 participação dos jovens na Initiatives produção de mídias em redes sociais SUB 109-2 / CT109.2 Contratação de serviços de agente de comercialização para garantir o acesso ao Component 1: Sustainable Request for Single Stage - One 2017-08- 2017-09- 2018-11- mercado local com a TF / 18765 and Adaptive Community Post Limited 0.00 Canceled Quotations Envelope 29 21 15 realização de levantamentos Initiatives acordos com mercados elaboração de projetos de venda e acompanhamento SUB 108- 29 / Contratação Component 1: Sustainable Request for Single Stage - One 2019-03- 2019-11- 2019-03- 2019-11- 2020-08- 2020-06- de Empresa de Engenharia TF / 18765 and Adaptive Community Post Limited 11,649.37 Completed Quotations Envelope 04 11 20 26 01 23 para construção de Initiatives beneficiamento SUB 108-5 / Contratação Component 1: Sustainable de serviços para confecção Request for Single Stage - One 2017-09- 2017-09- 2017-11- TF / 18765 and Adaptive Community Post Limited 0.00 Canceled de banners e folders para Quotations Envelope 12 29 29 Initiatives divulgação/informativo SUB 113-1 / Contratação Component 1: Sustainable de agente da comunidade 2017-09- 2017-09- 2017-10- 2017-12- TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled para Capacitação de grupos 01 22 24 26 Initiatives produtivos. SUB 113-3 / serviço de mobilização comunitária junto às famílias envolvidas no projeto para realizar a Component 1: Sustainable produção local e Request for Single Stage - One 2017-09- 2017-09- 2017-11- TF / 18765 and Adaptive Community Post Limited 0.00 Canceled identificação de mudas Quotations Envelope 08 25 24 Initiatives nativas a serem adquiridas para restauração de áreas degradadas, no âmbito das nascentes do córrego fazendinha. SUB 250-6 / Contratação Component 1: Sustainable Pending de serviços de impressão Request for Single Stage - One 2019-02- 2019-03- 2019-06- TF / 18765 and Adaptive Community Post Limited 0.00 Implement dos rótulos, livretos de Quotations Envelope 26 18 17 Initiatives ation receita e folders. SUB 113-7 / Contratação Component 1: Sustainable Under Request for Single Stage - One 2017-09- 2019-08- 2017-09- 2018-12- de serviços de locação de TF / 18765 and Adaptive Community Post Limited 857.28 Implement Quotations Envelope 12 30 29 24 veículo Initiatives ation Page 16 SUB 113- 25 / Contratação Component 1: Sustainable Pending de serviços de locação de Request for Single Stage - One 2019-03- 2019-03- 2020-06- TF / 18765 and Adaptive Community Post Limited 0.00 Implement transporte para eventos Quotations Envelope 17 28 20 Initiatives ation regionais ( 4.000,00). SUB 113- 26 / . Contratação de serviços de Component 1: Sustainable Pending Request for Single Stage - One 2019-03- 2019-03- 2020-06- locação de veículo durante 3 TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 17 28 20 meses para realização dos Initiatives ation trabalhos previstos (5.400,00). SUB 113-20 / SUB 113-20 Component 1: Sustainable Community serviço de apoio operacional 2018-01- 2018-01- 2018-02- 2018-02- 2018-02- 2019-04- TF / 18765 and Adaptive Community Post Driven Limited 0.00 Canceled para execução das 15 22 05 12 19 25 Initiatives Development atividades subprojeto CTA. Component 1: Sustainable 71- 12 / Serviços de Arte Request for Single Stage - One 2019-03- 2019-09- 2019-03- 2019-09- 2019-04- 2020-03- TF / 18765 and Adaptive Community Post Limited 1,174.90 Completed Gráfico (Design) Quotations Envelope 08 18 23 27 22 19 Initiatives BR-CAA-103028-NC-RFQ / Serviços gráficos para Component 2: Capacity Request for Single Stage - One 2019-03- 2019-03- 2019-04- 2019-03- 2019-06- 2019-05- confecção dos materiais TF / 18765 Building and Institutional Post Limited 867.37 Completed Quotations Envelope 18 06 12 28 11 27 pedagógicos para as Strengthening oficinas do plano de capacitação SUB 124 - 3 / Contratação Component 1: Sustainable Community 2018-01- 2019-01- 2018-02- 2018-02- 2018-02- 2018-02- 2018-03- de serviços para confecção TF / 18765 and Adaptive Community Post Driven Limited 0.00 Canceled 22 11 05 12 14 20 23 de camisetas Initiatives Development personalizadas. SUB 124 - 2 / Serviço de movimento de terra com Component 1: Sustainable Community 2018-01- 2018-02- 2018-02- 2018-02- 2018-02- 2018-04- trator ou terraplenagem TF / 18765 and Adaptive Community Post Driven Limited 0.00 Canceled 22 05 12 14 20 23 para viabilizar a construção Initiatives Development de barragens. SUB 91-1 / Serviço de mão Component 1: Sustainable Community de obra (civil, hidráulico e 2017-12- 2017-12- 2018-01- 2018-01- 2018-01- 2018-03- TF / 18765 and Adaptive Community Post Driven Limited 0.00 Canceled elétrico) para montagem do 15 29 05 09 15 17 Initiatives Development sistema de bombeamento SUB 71-7 / CT71.7 Contratação de profissional para elaboração do Component 1: Sustainable Request for Single Stage - One 2017-09- 2017-10- 2018-02- Regimento Interno das TF / 18765 and Adaptive Community Post Limited 0.00 Canceled Quotations Envelope 23 17 24 Casas do Coco e elaboração Initiatives do manual de boas praticas para os produtos do coco SUB 71-3 / CT71.3 Contratação de profissional Component 1: Sustainable para estruturação do plano Request for Single Stage - One 2017-07- 2017-08- 2017-09- TF / 18765 and Adaptive Community Post Limited 0.00 Canceled de negócios que contenha o Quotations Envelope 20 16 25 Initiatives desenvolvimento de logística de venda e distribuição BR-CAA-105071-NC-RFQ / Contratação de prestação de serviços de tradução de Component 3: Project textos (em português para o Request for Single Stage - One 2019-03- 2019-08- 2019-04- 2019-09- 2019-07- TF / 18765 Management, Monitoring Post Limited 2,061.90 Signed idioma inglês, e do inglês Quotations Envelope 20 09 08 06 07 and Evaluation para o idioma português) para produção de publicação do projeto DGM/FIP/Brasil SUB 210- 6 / Contratação de serviços para capacitação Component 1: Sustainable Request for Single Stage - One 2019-03- 2019-03- 2019-06- em construção de viveiro TF / 18765 and Adaptive Community Post Limited 0.00 Canceled Quotations Envelope 17 25 23 para produção de mudas e Initiatives implantação dos quintais SUB 124 - 4 / Contratação Component 1: Sustainable Community de serviços de alimentação 2018-01- 2018-02- 2018-02- 2018-02- 2018-02- 2018-04- TF / 18765 and Adaptive Community Post Driven Limited 0.00 Canceled para participantes do dia de 26 09 19 20 26 30 Initiatives Development campo, durante curso de SAF. SUB 124 - 10 / Aluguel de implementos agrícolas (Aluguel de trator equipado com carreta para transporte, Component 1: Sustainable tanque de água com bomba, Request for Single Stage - One 2019-04- 2019-05- 2019-05- 2019-05- 2019-09- 2019-10- TF / 18765 and Adaptive Community Post Limited 7,273.25 Completed container d'água, susolador Quotations Envelope 22 02 11 15 08 15 Initiatives e esteira rotativa para preparo de linhas de plantio , plantio e irrigação - instalação dos SAFs) SUB 124 - 12 / Contratação de profissional em Educação Component 1: Sustainable Ambiental para condução de Request for Single Stage - One 2019-05- 2019-10- 2019-05- 2019-10- 2019-07- 2019-12- TF / 18765 and Adaptive Community Post Limited 1,946.50 Completed oficinas participativas para Quotations Envelope 07 16 30 25 29 06 Initiatives levantamento de dados com os atores do projeto. BR-CAA-110425-NC-RFQ / Contratação de serviço para fornecimento de alimentação (lanche, almoço e jantar) para 02 (duas) Component 2: Capacity Pending Request for Single Stage - One 2019-04- 2019-05- 2019-10- capacitações (Mudanças TF / 18765 Building and Institutional Post Limited 0.00 Implement Quotations Envelope 29 16 13 climáticas e a política de Strengthening ation REDD+ E Agroindústria), para público de 75 participantes a serem realizados em Montes Claros/MG. SUB 124 - 13 / Contratação de profissional para Component 1: Sustainable Pending ministrar capacitação Request for Single Stage - One 2019-05- 2019-06- 2019-08- TF / 18765 and Adaptive Community Post Limited 0.00 Implement teórico/pratico sobre Quotations Envelope 10 04 03 Initiatives ation produtos e comercio de produtos obtidos através da mandioca. BR-CAA-110426-NC-DIR / Serviço do Facebook ADS para impulsionamento da Component 2: Capacity Pending 2019-04- 2019-04- 2019-05- 2020-04- página através das TF / 18765 Building and Institutional Post Direct Selection Direct 0.00 Implement 22 29 12 06 publicações, especificando o Strengthening ation público de interesse do projeto DGM e Subprojetos BR-CAA-110427-NC-DIR / Serviço Do Instagram ADS para impulsionamento da Component 2: Capacity Pending 2019-04- 2019-04- 2019-05- 2020-04- página e posts através do TF / 18765 Building and Institutional Post Direct Selection Direct 0.00 Implement 22 29 12 06 Instagram objetivando Strengthening ation atingir o público do projeto DGM e Subprojetos SUB 124 - 14 / Contratação Component 1: Sustainable Under Request for Single Stage - One 2019-05- 2020-02- 2019-06- 2019-08- de serviços de impressão de TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 18 21 08 07 cartilhas Initiatives ation BR-CAA-110428-NC-DIR / Contratação de licença de uso da ferramenta de envio Component 2: Capacity de e-mail em massa, design 2019-04- 2019-04- 2019-04- 2019-05- 2019-05- 2019-05- 2020-04- TF / 18765 Building and Institutional Post Direct Selection Direct 1,059.93 Signed de newsletter e mailing 22 22 29 13 12 13 06 Strengthening jornalístico objetivando atingir o público do projeto DGM e Subprojetos BR-CAA-110431-NC-RFQ / Contratação de serviços de hospedagem e translado Component 2: Capacity para participantes dos Request for Single Stage - One 2019-05- 2019-05- 2019-05- 2019-05- 2019-08- 2019-08- TF / 18765 Building and Institutional Post Limited 20,407.69 Completed módulos I e II do Curso de Quotations Envelope 09 23 24 31 22 15 Strengthening Sustentabilidade e Indidência política (30 participantes - Brasília, DF). BR-CAA-110432-NC-RFQ / Contratação de serviços de transporte para 35 pessoas, Component 2: Capacity Request for Single Stage - One 2019-06- 2019-07- 2019-06- 2019-07- 2019-07- 2019-07- para deslocamento dos TF / 18765 Building and Institutional Post Limited 149.90 Completed Quotations Envelope 03 10 28 23 28 29 participantes no Curso de Strengthening REDD - percurso Montes Claros a AEFA (local do curso). SUB 218 SC 004 / Contratação de serviços Component 1: Sustainable Request for Single Stage - One 2019-02- 2019-06- 2019-03- 2019-07- 2019-05- 2019-09- para produção de sacolas TF / 18765 and Adaptive Community Post Limited 1,465.27 Completed Quotations Envelope 19 28 10 29 09 20 de papel e caixas de Initiatives papelão personalizadas. SUB 241-3 / Contratação de horas-máquina para Component 1: Sustainable Pending Request for Single Stage - One 2019-06- 2019-06- 2019-07- 2019-07- 2019-07- 2019-09- implantação de tecnologias TF / 18765 and Adaptive Community Post Limited 0.00 Implement Proposals Envelope 17 25 05 09 13 12 de barramento de água Initiatives ation (barraginha) SUB 216-2 / Serviços de impressão de documento Component 1: Sustainable Request for Single Stage - One 2019-06- 2019-07- 2019-10- base com os diagnósticos TF / 18765 and Adaptive Community Post Limited 0.00 Canceled Quotations Envelope 26 19 18 para construção dos planos Initiatives de gestão territorial e ambiental SUB 179 SC 001 / Component 1: Sustainable Contratação de serviços Request for Single Stage - One 2019-02- 2019-03- 2019-04- TF / 18765 and Adaptive Community Post Limited 0.00 Canceled para: perfuração E Quotations Envelope 19 09 09 Initiatives revestimento de poço artesiano BR-CAA-105072-NC-RFQ / Contratação de serviços de Component 2: Capacity transporte para Request for Single Stage - One 2019-07- 2019-08- 2019-09- 2019-08- 2019-11- 2019-08- TF / 18765 Building and Institutional Post Limited 168.74 Completed deslocamento durante Quotations Envelope 31 08 25 16 19 30 Strengthening reunião dos membros do CGN em Montes Claros no mês de Agosto. BR-CAA-105074-NC-RFQ / Contratação de Component 2: Capacity Hospedagem para o Request for Single Stage - One 2019-08- 2019-09- 2019-08- 2019-09- 2019-09- 2019-10- TF / 18765 Building and Institutional Post Limited 2,984.86 Completed Colóquio Internacional de Quotations Envelope 14 10 31 19 30 21 Strengthening PICTs/ Oficina de Turismo de Base Comunitária em Montes Claros. BR-CAA-127223-NC-RFQ / Serviços de hospedagens e Component 2: Capacity transfer para os Request for Single Stage - One 2019-09- 2019-09- 2019-09- 2019-10- 2019-12- 2019-12- TF / 18765 Building and Institutional Post Limited 10,996.84 Completed participantes do 3º e 4º Quotations Envelope 04 20 11 01 11 20 Strengthening módulo do cursos de Sustentabilidade em  parceria com a Unb. BR-CAA-127227-NC-RFQ / Serviço de buffer/alimentação para os Component 2: Capacity Request for Single Stage - One 2019-09- 2019-09- 2019-09- 2019-10- 2019-12- 2019-12- cursos a serem realizadas TF / 18765 Building and Institutional Post Limited 15,380.55 Completed Quotations Envelope 04 20 11 01 10 06 na AEFA = Energia Strengthening fotovoltaica ( 30 participantes) + Produção Agroecológica (35 participantes) BR-CAA-105073-NC-RFQ / Contratação de profissional para apoio junto a equipe Component 3: Project financeira para lançamentos Request for Single Stage - One 2019-07- 2019-09- 2019-11- TF / 18765 Management, Monitoring Post Limited 0.00 Canceled e correções no sistema de Quotations Envelope 31 25 29 and Evaluation gestão, referente receitas e despesas dos anos 2015- 2018 BR-CAA-129374-NC-RFQ / Contratação de pessoa física para prestação de serviços de Contratação de pessoa Component 2: Capacity física para prestação de Request for Single Stage - One 2019-09- 2019-09- 2019-12- TF / 18765 Building and Institutional Post Limited 0.00 Canceled serviços de criação, Quotations Envelope 09 26 25 Strengthening concepção, produção musical, gravação, mixagem, masterização de trilha sonora vídeo musical do DGM/FIP/Brasil. BR-CAA-129375-NC-RFQ / Contratação de serviços especializados de fotografia em câmera profissional full frame, com Component 2: Capacity Request for Single Stage - One 2019-09- 2019-11- 2019-09- 2019-11- 2019-12- resolução acima de 22.3 TF / 18765 Building and Institutional Post Limited 1,434.60 Signed Quotations Envelope 09 07 26 27 25 megapixels, para produção Strengthening de acervo fotográfico do Projeto DGM FIP Brasil, para uso institucional do CAA, BM e Subprojetos. BR-CAA-133682-NC-RFQ / Contratação de serviços de transporte para deslocamento dos Component 2: Capacity Request for Single Stage - One 2019-09- 2019-11- 2019-10- 2019-11- 2019-10- 2020-04- participantes do Curso de TF / 18765 Building and Institutional Post Limited 1,234.67 Completed Quotations Envelope 23 11 09 14 18 01 Formação e Agroecologia Strengthening (Módulos I e II) e Capacitação em energia fotovoltaica, a ser realizados em Montes Claros - 2º semestre de 2019 Component 1: Sustainable SUB 218 -SC 008-2019 / Request for Single Stage - One 2019-08- 2019-10- 2019-10- TF / 18765 and Adaptive Community Post Limited 0.00 Canceled Cardagem algodão orgânico Quotations Envelope 27 14 15 Initiatives SUB 218 -CD 002.2019 / Component 1: Sustainable Under 2019-09- 2019-08- 2019-09- 2019-08- 2019-10- 2019-11- Cardagem do algodão TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Implement 23 28 26 28 02 02 orgânico Initiatives ation BR-CAA-110430-NC-RFQ / Serviço de comunicação com foco em ministrar oficinas quanto ao direito a Component 2: Capacity Request for Single Stage - One 2019-05- 2019-05- 2019-08- comunicação e a nova visão TF / 18765 Building and Institutional Post Limited 0.00 Canceled Quotations Envelope 06 23 21 de fotografar, filmar, Strengthening escrever, entrevistar e contar histórias visando a comunicação popular SUB 169-3 / Confecção de placa de inauguração do Component 1: Sustainable Request for Single Stage - One 2019-11- 2020-07- 2019-12- 2020-07- 2019-12- 2020-08- centro e placas TF / 18765 and Adaptive Community Post Limited 195.08 Completed Quotations Envelope 17 08 06 24 12 06 sinalizadores dos pontos Initiatives turísticos da região do Delta do Parnaíba. SUB 169-4 / Contratação de serviços gráficos: Component 1: Sustainable Pending sinalização dos pontos; Request for Single Stage - One 2019-11- 2019-12- 2020-02- TF / 18765 and Adaptive Community Post Limited 0.00 Implement produção de identidade; e Quotations Envelope 17 06 04 Initiatives ation impressão de cartazes da associações e do projeto. SUB 85 - 3 / Serviço de Component 1: Sustainable Community 2018-01- 2018-01- 2018-01- 2018-02- 2018-02- 2018-05- mão de obra para TF / 18765 and Adaptive Community Post Driven Limited 0.00 Canceled 08 22 29 02 09 21 construção de cercas - Mão Initiatives Development Obra 1 SUB 85 - 4 / Serviço de Component 1: Sustainable Community 2018-01- 2018-01- 2018-01- 2018-02- 2018-02- 2018-05- mão de obra para TF / 18765 and Adaptive Community Post Driven Limited 0.00 Canceled 08 22 29 02 09 21 construção de cercas - Mão Initiatives Development Obra 2. Component 1: Sustainable Community SUB 85 - 2 / Serviço de 2017-12- 2018-01- 2018-01- 2018-01- 2018-01- 2018-03- TF / 18765 and Adaptive Community Post Driven Limited 0.00 Canceled locação de micro-ônibus. 26 09 16 18 27 28 Initiatives Development Component 1: Sustainable Community SUB 85 - 5 / Serviço de 2018-01- 2018-02- 2018-02- 2018-02- 2018-03- 2018-06- TF / 18765 and Adaptive Community Post Driven Limited 0.00 Canceled aragem de terra com trator. 29 12 19 23 02 10 Initiatives Development SUB 85 - 6 / Serviço de Component 1: Sustainable Community 2017-12- 2018-01- 2018-01- 2018-01- 2018-01- 2018-02- Instalação de sistema de TF / 18765 and Adaptive Community Post Driven Limited 0.00 Canceled 26 09 18 20 26 26 irrigação. Initiatives Development SUB 16-19 / Contratação de serviço de apoio Component 1: Sustainable Community 2018-03- 2018-03- 2018-03- 2018-04- 2018-04- 2019-11- operacional de comunicação TF / 18765 and Adaptive Community Post Driven Limited 0.00 Canceled 15 20 30 02 06 27 para execução das Initiatives Development atividades subprojeto CEDRO. SUB 16-20 / Contratação de Agente Local para Component 1: Sustainable Community mobilização, 2018-05- 2018-05- 2018-06- 2018-06- 2018-06- 2019-09- TF / 18765 and Adaptive Community Post Driven Limited 0.00 Canceled acompanhamento e apoio 25 30 09 11 21 14 Initiatives Development no planejamento das atividades do projeto. SUB 16-21 / Contratação de agente local para registros fotográficos e Component 1: Sustainable Community 2018-06- 2018-06- 2018-06- 2018-06- 2018-07- 2019-09- organização das atividades TF / 18765 and Adaptive Community Post Driven Limited 0.00 Canceled 09 14 24 26 06 29 previstas no projeto (como Initiatives Development oficinas, seminários, construção, cercamento das nascentes). SUB 16-4 / CQ16-4 Serviço Component 1: Sustainable Request for Single Stage - One 2017-07- 2017-08- 2019-01- de elaboração de vídeo TF / 18765 and Adaptive Community Post Limited 0.00 Canceled Quotations Envelope 20 13 31 sobre as ações do projeto. Initiatives SUB 16-7 / CQ16-7 Serviço de preparo do solo para a Implantar uma Produção Component 1: Sustainable agroecológica Sustentável e 2017-08- 2017-08- 2017-09- 2017-10- TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled dezesseis ortas famílias 10 20 13 13 Initiatives objetivando fortalecer a soberania e a segurança alimentar na comunidade SUB 16-9 / CQ16-9 Serviço de hora maquina para a Component 1: Sustainable Request for Single Stage - One 2017-09- 2017-10- 2017-12- construção de curvas de TF / 18765 and Adaptive Community Post Limited 0.00 Canceled Quotations Envelope 30 24 08 nível e bacias de contenção Initiatives de enxurrada SUB 3-20 / Contratação de serviços de máquina (trator) Component 1: Sustainable Pending com motorista para Request for Single Stage - One 2018-05- 2018-06- 2018-09- TF / 18765 and Adaptive Community Post Limited 0.00 Implement construção de barraginhas, Quotations Envelope 28 14 12 Initiatives ation para captação de água da chuva, na TI Maraiwatsede. Page 17 SUB 3-11 / Contratação de profissional para ministrar Oficina de práticas agroecológicas para Component 1: Sustainable Request for Single Stage - One 2017-08- 2017-09- 2017-11- restauração do cerrado na TF / 18765 and Adaptive Community Post Limited 0.00 Canceled Quotations Envelope 18 22 24 Aldeia A'opa com a Initiatives participação das aldeias Maraiwatsede, Etewawe e Madmabdze. SUB 3-14 / Contratação de Component 1: Sustainable serviços de pedreiro para Request for Single Stage - One 2017-09- 2017-11- 2018-01- TF / 18765 and Adaptive Community Post Limited 0.00 Canceled construção de galpão em Quotations Envelope 29 06 05 Initiatives madeira e alvenaria - 100 dias SUB 3-19 / Contratação de serviços de tratoristas para Component 1: Sustainable 2017-09- 2017-10- 2017-11- 2018-01- plantio de mudas e TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled 12 04 08 27 sementes no entorno das Initiatives aldeias Etewawê - Maraiwatsede SUB 3-21 / Contratação de serviços de operador de Component 1: Sustainable Pending Request for Single Stage - One 2019-10- 2019-11- 2020-01- máquina para oficina de TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 18 05 04 capacitação de construção Initiatives ation de barraginhas. SUB 3-22 / Contratação de serviços de tratoristas para Component 1: Sustainable Pending plantio de mudas e Request for Single Stage - One 2019-10- 2019-11- 2020-01- TF / 18765 and Adaptive Community Post Limited 0.00 Implement sementes e plantio de 1000 Quotations Envelope 18 05 04 Initiatives ation mudas no entorno das aldeias Aopá - Madzabdze SUB 98 -2 / Serviço de Locação de uma Van para Component 1: Sustainable Community transportar representantes 2017-12- 2017-12- 2018-01- 2018-01- 2018-01- 2018-03- TF / 18765 and Adaptive Community Post Driven Limited 0.00 Canceled indígenas, para a realização 15 29 05 09 15 17 Initiatives Development de um intercâmbio no municipio de Taquaral. SUB 98 -20 / Contratação de profissional técnico para Component 1: Sustainable Pending elaboração do projeto do Request for Single Stage - One 2019-10- 2019-11- 2019-12- TF / 18765 and Adaptive Community Post Limited 0.00 Implement viveiro para produção de Quotations Envelope 25 10 25 Initiatives ation 10.000 mudas/ano (nativas e frutíferas) AI - 3 / Serviço de confecção de kits Component 1: Sustainable Request for Single Stage - One 2019-10- 2019-10- 2019-10- 2019-10- 2019-11- 2019-10- pedagógicos como TF / 18765 and Adaptive Community Post Limited 1,537.41 Completed Quotations Envelope 15 18 22 25 06 29 camisetas, bolsas e bloco de Initiatives anotações para utilização durante Assembleia AI - 4 / Serviços de fornecimento de refeição / Component 1: Sustainable Request for Single Stage - One 2019-10- 2019-10- 2019-10- 2019-10- 2019-11- 2019-11- buffer para atividade de TF / 18765 and Adaptive Community Post Limited 6,662.11 Completed Quotations Envelope 14 18 21 22 05 04 assembleia da Wyty Cati Initiatives junto aos povos Timbiras SUB 127-16 / Servico de frete comunitario indigena Component 1: Sustainable para transporte de madeira Request for Single Stage - One 2017-12- 2017-12- 2018-01- TF / 18765 and Adaptive Community Post Limited 0.00 Canceled e palhas que serao Quotations Envelope 12 26 25 Initiatives utilizadas na construcao do Centro de Revitalizacao - frete 2 SUB 30 - 1 / Serviço de Component 1: Sustainable Request for Single Stage - One 2017-12- 2017-12- 2018-12- confecção de Banners, TF / 18765 and Adaptive Community Post Limited 0.00 Canceled Quotations Envelope 12 29 15 Folders para divulgação do Initiatives subprojeto SUB 30 - 10 / Serviço de Component 1: Sustainable mão de obra para retirada 2017-09- 2017-10- 2017-10- 2017-11- TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled da madeira para Construção 22 06 23 23 Initiatives do viveiro. SUB 30 - 3 / Serviço de Component 1: Sustainable Request for Single Stage - One 2017-10- 2017-10- 2017-11- moderador para o encontro TF / 18765 and Adaptive Community Post Limited 0.00 Canceled Quotations Envelope 09 25 25 de mulheres Initiatives SUB 30 - 5 / Serviço de Component 1: Sustainable cozinheira para Capacitação 2017-09- 2017-10- 2017-10- 2018-01- TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled na área de elaboração de 27 11 31 30 Initiatives projetos. SUB 30 - 6 / Serviço de Component 1: Sustainable cozinheira para Capacitação 2017-09- 2017-10- 2017-10- 2018-01- TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled na área de gestão 27 11 28 27 Initiatives administrativa e financeira. SUB 30 - 7 / Serviço de cozinheira para Encontro de Component 1: Sustainable mulheres indígenas bakairi 2017-09- 2017-10- 2017-10- 2017-11- TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled para discussão da gestão 20 04 21 21 Initiatives ambiental e territorial do povo bakairi realizado. SUB 30 - 8 / Serviço de Component 1: Sustainable mão de obra (civil, 2017-09- 2017-10- 2017-11- 2017-11- TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled hidráulico e elétrico) para a 25 09 25 25 Initiatives construção do viveiro. SUB 30 - 9 / Serviço de Component 1: Sustainable mão de obra para retirada 2017-09- 2017-10- 2017-10- 2017-11- TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled da madeira para Construção 22 06 23 23 Initiatives do escritório do projeto. SUB 30 -4 / Serviço de Component 1: Sustainable cozinheira para Capacitação 2017-09- 2017-10- 2017-10- 2018-01- TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled em gestão e legislação 27 11 28 27 Initiatives ambiental para 40 pessoas. SUB 139-1 / Confecção de Component 1: Sustainable Pending banners e impressão de Request for Single Stage - One 2019-11- 2019-11- 2020-01- TF / 18765 and Adaptive Community Post Limited 0.00 Implement cartilhas para divulgar Quotations Envelope 15 25 24 Initiatives ation atividades e ações do projeto SUB 218 - 9 / Contratação Component 1: Sustainable de serviços para produção Request for Single Stage - One 2019-11- 2019-11- 2019-11- 2019-11- 2020-01- 2019-11- TF / 18765 and Adaptive Community Post Limited 140.74 Completed de folders, banners Quotations Envelope 08 18 21 23 20 29 Initiatives personalizadas. SUB 74-76 / SUB 74-76 Component 1: Sustainable Community Serviço de apoio operacional 2018-01- 2018-01- 2018-01- 2018-01- 2018-02- 2018-03- TF / 18765 and Adaptive Community Post Driven Limited 0.00 Canceled para execução das 11 19 26 29 02 24 Initiatives Development atividades subprojeto Wyty Cati. SUB 74-30 / Contratação, via diária, de agentes indígenas capacitados em Component 1: Sustainable 2017-09- 2017-10- 2017-11- 2018-05- monitoramento e TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled 20 12 16 25 fiscalização ambiental para Initiatives realizar expedições na TI Kanela - Agente Nº 14 SUB 74-31 / Contratação, via diária, de agentes indígenas capacitados em Component 1: Sustainable 2017-09- 2017-10- 2017-11- 2018-05- monitoramento e TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled 20 12 16 25 fiscalização ambiental para Initiatives realizar expedições na TI Kanela - Agente Nº 15 SUB 74-32 / Contratação, via diária, de agentes indígenas capacitados em Component 1: Sustainable 2017-09- 2017-10- 2017-11- 2018-05- monitoramento e TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled 20 12 16 25 fiscalização ambiental para Initiatives realizar expedições na TI Kanela - Agente Nº 16 SUB 74-33 / Contratação, via diária, de agentes indígenas capacitados em Component 1: Sustainable 2017-09- 2017-10- 2017-11- 2018-05- monitoramento e TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled 20 12 16 25 fiscalização ambiental para Initiatives realizar expedições na TI Kanela - Agente Nº 17 SUB 74-34 / Contratação, via diária, de agentes indígenas capacitados em Component 1: Sustainable 2017-09- 2017-10- 2017-11- 2018-05- monitoramento e TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled 20 12 16 25 fiscalização ambiental para Initiatives realizar expedições na TI Kanela - Agente Nº 18 SUB 74-35 / Contratação, via diária, de agentes indígenas capacitados em Component 1: Sustainable 2017-09- 2017-10- 2017-11- 2018-05- monitoramento e TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled 20 12 16 25 fiscalização ambiental para Initiatives realizar expedições na TI Kanela - Agente Nº 19 SUB 74-36 / Contratação, via diária, de agentes indígenas capacitados em Component 1: Sustainable 2017-09- 2017-10- 2017-11- 2018-05- monitoramento e TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled 20 12 16 25 fiscalização ambiental para Initiatives realizar expedições na TI Kanela - Agente Nº 20 SUB 74-37 / Contratação, via diária, de agentes indígenas capacitados em Component 1: Sustainable 2017-09- 2017-10- 2017-11- 2018-05- monitoramento e TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled 20 12 16 25 fiscalização ambiental para Initiatives realizar expedições na TI Kanela - Agente Nº 21 SUB 74-38 / Contratação, via diária, de agentes indígenas capacitados em Component 1: Sustainable 2017-09- 2017-10- 2017-11- 2018-05- monitoramento e TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled 20 12 16 25 fiscalização ambiental para Initiatives realizar expedições na TI Kanela - Agente Nº 22 SUB 74-39 / Contratação, via diária, de agentes indígenas capacitados em Component 1: Sustainable 2017-09- 2017-10- 2017-11- 2018-05- monitoramento e TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled 20 12 16 25 fiscalização ambiental para Initiatives realizar expedições na TI Kanela - Agente Nº 23 SUB 74-40 / Contratação, via diária, de agentes indígenas capacitados em Component 1: Sustainable 2017-09- 2017-10- 2017-11- 2018-05- monitoramento e TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled 20 12 16 25 fiscalização ambiental para Initiatives realizar expedições na TI Kanela - Agente Nº 24 SUB 74-41 / Contratação, via diária, de agentes indígenas capacitados em Component 1: Sustainable 2017-09- 2017-10- 2017-11- 2018-05- monitoramento e TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled 20 12 16 25 fiscalização ambiental para Initiatives realizar expedições na TI Kanela - Agente Nº 25 SUB 74-42 / Contratação, via diária, de agentes indígenas capacitados em Component 1: Sustainable 2017-09- 2017-10- 2017-11- 2018-05- monitoramento e TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled 20 12 16 25 fiscalização ambiental para Initiatives realizar expedições na TI Kanela - Agente Nº 26 SUB 74-43 / Contratação, via diária, de agentes indígenas capacitados em Component 1: Sustainable 2017-09- 2017-10- 2017-11- 2018-05- monitoramento e TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled 20 12 16 25 fiscalização ambiental para Initiatives realizar expedições na TI Kanela - Agente Nº 27 SUB 74-1 / Contratação, via diária, de agentes indígenas capacitados em Component 1: Sustainable 2017-09- 2017-10- 2017-11- 2018-05- monitoramento e TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled 20 12 17 28 fiscalização ambiental para Initiatives realizar expedições na TI Kanela - Agente Nº 1 SUB 74-10 / Contratação Component 1: Sustainable Request for Single Stage - One 2017-08- 2017-08- 2017-10- de serviços de impressão de TF / 18765 and Adaptive Community Post Limited 0.00 Canceled Quotations Envelope 04 18 18 cartazes e panfletos Initiatives SUB 74-16 / Contratação Component 1: Sustainable Request for Single Stage - One 2017-08- 2017-08- 2017-09- de serviço de confecção de TF / 18765 and Adaptive Community Post Limited 0.00 Canceled Quotations Envelope 08 22 21 blusas com logo Initiatives SUB 74-18 / Contratação, via diária, de agentes indígenas capacitados em Component 1: Sustainable 2017-09- 2017-10- 2017-11- 2018-05- monitoramento e TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled 20 12 16 25 fiscalização ambiental para Initiatives realizar expedições na TI Kanela - Agente Nº 2 SUB 74-19 / Contratação, via diária, de agentes indígenas capacitados em Component 1: Sustainable 2017-09- 2017-10- 2017-11- 2018-05- monitoramento e TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled 20 12 16 25 fiscalização ambiental para Initiatives realizar expedições na TI Kanela - Agente Nº 3 SUB 74-2 / Contratação, via diária, de agentes indígenas capacitados em Component 1: Sustainable 2017-11- 2017-12- 2018-01- 2018-07- monitoramento e TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled 20 12 17 27 fiscalização ambiental para Initiatives realizar expedições na TI Porquinhos - Agente N.º 01 SUB 74-20 / Contratação, via diária, de agentes indígenas capacitados em Component 1: Sustainable 2017-09- 2017-10- 2017-11- 2018-05- monitoramento e TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled 20 12 16 25 fiscalização ambiental para Initiatives realizar expedições na TI Kanela - Agente Nº 4 SUB 74-21 / Contratação, via diária, de agentes indígenas capacitados em Component 1: Sustainable 2017-09- 2017-10- 2017-11- 2018-05- monitoramento e TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled 20 12 16 25 fiscalização ambiental para Initiatives realizar expedições na TI Kanela - Agente Nº 5 SUB 74-22 / Contratação, via diária, de agentes indígenas capacitados em Component 1: Sustainable 2017-09- 2017-10- 2017-11- 2018-05- monitoramento e TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled 20 12 16 25 fiscalização ambiental para Initiatives realizar expedições na TI Kanela - Agente Nº 6 SUB 74-23 / Contratação, via diária, de agentes indígenas capacitados em Component 1: Sustainable 2017-09- 2017-10- 2017-11- 2018-05- monitoramento e TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled 20 12 16 25 fiscalização ambiental para Initiatives realizar expedições na TI Kanela - Agente Nº 7 SUB 74-24 / Contratação, via diária, de agentes indígenas capacitados em Component 1: Sustainable 2017-09- 2017-10- 2017-11- 2018-05- monitoramento e TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled 20 12 16 25 fiscalização ambiental para Initiatives realizar expedições na TI Kanela - Agente Nº 8 SUB 74-25 / Contratação, via diária, de agentes indígenas capacitados em Component 1: Sustainable 2017-09- 2017-10- 2017-11- 2018-05- monitoramento e TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled 20 12 16 25 fiscalização ambiental para Initiatives realizar expedições na TI Kanela - Agente Nº 9 SUB 74-26 / Contratação, via diária, de agentes indígenas capacitados em Component 1: Sustainable 2017-09- 2017-10- 2017-11- 2018-05- monitoramento e TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled 20 12 16 25 fiscalização ambiental para Initiatives realizar expedições na TI Kanela - Agente Nº 10 SUB 74-27 / Contratação, via diária, de agentes indígenas capacitados em Component 1: Sustainable 2017-09- 2017-10- 2017-11- 2018-05- monitoramento e TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled 20 12 16 25 fiscalização ambiental para Initiatives realizar expedições na TI Kanela - Agente Nº 11 SUB 74-28 / Contratação, via diária, de agentes indígenas capacitados em Component 1: Sustainable 2017-09- 2017-10- 2017-11- 2018-05- monitoramento e TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled 20 12 16 25 fiscalização ambiental para Initiatives realizar expedições na TI Kanela - Agente Nº 12 Page 18 SUB 74-29 / Contratação, via diária, de agentes indígenas capacitados em Component 1: Sustainable 2017-09- 2017-10- 2017-11- 2018-05- monitoramento e TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled 20 12 16 25 fiscalização ambiental para Initiatives realizar expedições na TI Kanela - Agente Nº 13 SUB 74-47 / Contratação, via diária, de agentes indígenas capacitados em Component 1: Sustainable 2017-11- 2017-12- 2018-01- 2018-07- monitoramento e TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled 20 12 17 26 fiscalização ambiental para Initiatives realizar expedições na TI Porquinhos - Agente N.º 02 SUB 74-48 / Contratação, via diária, de agentes indígenas capacitados em Component 1: Sustainable 2017-11- 2017-12- 2018-01- 2018-07- monitoramento e TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled 20 12 17 26 fiscalização ambiental para Initiatives realizar expedições na TI Porquinhos - Agente N.º 03 SUB 74-49 / Contratação, via diária, de agentes indígenas capacitados em Component 1: Sustainable 2017-11- 2017-12- 2018-01- 2018-07- monitoramento e TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled 20 12 17 26 fiscalização ambiental para Initiatives realizar expedições na TI Porquinhos - Agente N.º 04 SUB 74-5 / Contratação de Component 1: Sustainable indígena facilitador na 2017-07- 2017-08- 2017-08- 2017-10- TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled Oficina de Monitoramento e 25 02 16 16 Initiatives fiscalização do território SUB 74-50 / Contratação, via diária, de agentes indígenas capacitados em Component 1: Sustainable 2017-11- 2017-12- 2018-02- 2018-08- monitoramento e TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled 20 12 04 13 fiscalização ambiental para Initiatives realizar expedições na TI Porquinhos - Agente N.º 05 SUB 74-51 / Contratação, via diária, de agentes indígenas capacitados em Component 1: Sustainable 2017-11- 2017-12- 2018-01- 2018-07- monitoramento e TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled 20 12 17 26 fiscalização ambiental para Initiatives realizar expedições na TI Porquinhos - Agente N.º 06 SUB 74-52 / Contratação, via diária, de agentes indígenas capacitados em Component 1: Sustainable 2017-11- 2017-12- 2018-01- 2018-07- monitoramento e TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled 20 12 17 26 fiscalização ambiental para Initiatives realizar expedições na TI Porquinhos - Agente N.º 07 SUB 74-53 / Contratação, via diária, de agentes indígenas capacitados em Component 1: Sustainable 2017-11- 2017-12- 2018-01- 2018-07- monitoramento e TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled 20 12 17 26 fiscalização ambiental para Initiatives realizar expedições na TI Porquinhos - Agente N.º 08 SUB 74-54 / Contratação, via diária, de agentes indígenas capacitados em Component 1: Sustainable 2017-11- 2017-12- 2018-01- 2018-07- monitoramento e TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled 20 12 17 26 fiscalização ambiental para Initiatives realizar expedições na TI Porquinhos - Agente N.º 09 SUB 74-55 / Contratação, via diária, de agentes indígenas capacitados em Component 1: Sustainable 2017-11- 2017-12- 2018-01- 2018-07- monitoramento e TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled 20 12 17 26 fiscalização ambiental para Initiatives realizar expedições na TI Porquinhos - Agente N.º 10 SUB 74-56 / Contratação, via diária, de agentes indígenas capacitados em Component 1: Sustainable 2017-11- 2017-12- 2018-01- 2018-07- monitoramento e TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled 20 12 17 26 fiscalização ambiental para Initiatives realizar expedições na TI Porquinhos - Agente N.º 11 SUB 74-57 / Contratação, via diária, de agentes indígenas capacitados em Component 1: Sustainable 2017-11- 2017-12- 2018-01- 2018-07- monitoramento e TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled 20 12 17 26 fiscalização ambiental para Initiatives realizar expedições na TI Porquinhos - Agente N.º 12 SUB 74-58 / Contratação, via diária, de agentes indígenas capacitados em Component 1: Sustainable 2017-11- 2017-12- 2018-01- 2018-07- monitoramento e TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled 20 12 17 26 fiscalização ambiental para Initiatives realizar expedições na TI Porquinhos - Agente N.º 13 SUB 74-59 / Contratação, via diária, de agentes indígenas capacitados em Component 1: Sustainable 2017-11- 2017-12- 2018-01- 2018-07- monitoramento e TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled 20 12 17 26 fiscalização ambiental para Initiatives realizar expedições na TI Porquinhos - Agente N.º 14 SUB 74-6 / Contratação de Component 1: Sustainable indígena facilitador na 2017-09- 2017-09- 2017-09- 2017-11- TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled Oficina de Monitoramento e 01 09 23 23 Initiatives fiscalização do território SUB 74-60 / Contratação, via diária, de agentes indígenas capacitados em Component 1: Sustainable 2017-11- 2017-12- 2018-01- 2018-07- monitoramento e TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled 20 12 17 26 fiscalização ambiental para Initiatives realizar expedições na TI Porquinhos - Agente N.º 15 SUB 74-61 / Contratação, via diária, de agentes indígenas capacitados em Component 1: Sustainable 2017-11- 2017-12- 2018-01- 2018-07- monitoramento e TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled 20 12 17 26 fiscalização ambiental para Initiatives realizar expedições na TI Porquinhos - Agente N.º 16 SUB 74-62 / Contratação, via diária, de agentes indígenas capacitados em Component 1: Sustainable 2017-11- 2017-12- 2018-01- 2018-07- monitoramento e TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled 20 12 17 26 fiscalização ambiental para Initiatives realizar expedições na TI Porquinhos - Agente N.º 17 SUB 74-63 / Contratação, via diária, de agentes indígenas capacitados em Component 1: Sustainable 2017-11- 2017-12- 2018-01- 2018-07- monitoramento e TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled 20 12 17 26 fiscalização ambiental para Initiatives realizar expedições na TI Porquinhos - Agente N.º 18 SUB 74-64 / Contratação, via diária, de agentes indígenas capacitados em Component 1: Sustainable 2017-11- 2017-12- 2018-01- 2018-07- monitoramento e TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled 20 12 17 26 fiscalização ambiental para Initiatives realizar expedições na TI Porquinhos - Agente N.º 19 SUB 74-65 / Contratação, via diária, de agentes indígenas capacitados em Component 1: Sustainable 2017-11- 2017-12- 2018-01- 2018-07- monitoramento e TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled 20 12 17 26 fiscalização ambiental para Initiatives realizar expedições na TI Porquinhos - Agente N.º 20 SUB 74-66 / Contratação, via diária, de agentes indígenas capacitados em Component 1: Sustainable 2017-11- 2017-12- 2018-01- 2018-07- monitoramento e TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled 20 12 17 26 fiscalização ambiental para Initiatives realizar expedições na TI Porquinhos - Agente N.º 21 SUB 74-67 / Contratação, via diária, de agentes indígenas capacitados em Component 1: Sustainable 2017-11- 2017-12- 2018-01- 2018-07- monitoramento e TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled 20 12 17 26 fiscalização ambiental para Initiatives realizar expedições na TI Porquinhos - Agente N.º 22 SUB 74-68 / Contratação, via diária, de agentes indígenas capacitados em Component 1: Sustainable 2017-11- 2017-12- 2018-01- 2018-07- monitoramento e TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled 20 12 17 26 fiscalização ambiental para Initiatives realizar expedições na TI Porquinhos - Agente N.º 23 SUB 74-69 / Contratação, via diária, de agentes indígenas capacitados em Component 1: Sustainable 2017-11- 2017-12- 2018-01- 2018-07- monitoramento e TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled 20 12 17 26 fiscalização ambiental para Initiatives realizar expedições na TI Porquinhos - Agente N.º 24 Component 1: Sustainable SUB 74-7 / Contratação de 2017-07- 2017-08- 2017-08- 2017-10- TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled cozinheiro (a) 25 02 16 16 Initiatives SUB 74-70 / Contratação, via diária, de agentes indígenas capacitados em Component 1: Sustainable 2017-11- 2017-12- 2018-01- 2018-07- monitoramento e TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled 20 12 17 26 fiscalização ambiental para Initiatives realizar expedições na TI Porquinhos - Agente N.º 25 SUB 74-71 / Contratação, via diária, de agentes indígenas capacitados em Component 1: Sustainable 2017-11- 2017-11- 2018-01- 2018-07- monitoramento e TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled 20 25 17 26 fiscalização ambiental para Initiatives realizar expedições na TI Porquinhos - Agente N.º 26 SUB 74-72 / Contratação, via diária, de agentes indígenas capacitados em Component 1: Sustainable 2017-11- 2017-12- 2018-01- 2018-07- monitoramento e TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled 20 12 17 26 fiscalização ambiental para Initiatives realizar expedições na TI Porquinhos - Agente N.º 27 SUB 74-73 / Contratação, via diária, de agentes indígenas capacitados em Component 1: Sustainable 2017-11- 2017-12- 2018-01- 2018-07- monitoramento e TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled 20 12 17 26 fiscalização ambiental para Initiatives realizar expedições na TI Porquinhos - Agente N.º 28 SUB 74-74 / Contratação, via diária, de agentes indígenas capacitados em Component 1: Sustainable 2017-11- 2017-12- 2018-01- 2018-07- monitoramento e TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled 20 12 17 26 fiscalização ambiental para Initiatives realizar expedições na TI Porquinhos - Agente N.º 29 SUB 74-75 / Contratação, via diária, de agentes indígenas capacitados em Component 1: Sustainable 2017-11- 2017-12- 2018-01- 2018-07- monitoramento e TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled 20 12 17 26 fiscalização ambiental para Initiatives realizar expedições na TI Porquinhos - Agente N.º 30 Component 1: Sustainable SUB 74-8 / Contratação de 2017-07- 2017-08- 2017-08- 2017-10- TF / 18765 and Adaptive Community Post Direct Selection Direct 0.00 Canceled cozinheiro (a) 25 02 16 16 Initiatives SUB 74-9 / Contratação de Component 1: Sustainable Request for Single Stage - One 2017-08- 2017-08- 2017-10- serviço de fornecimento de TF / 18765 and Adaptive Community Post Limited 0.00 Canceled Quotations Envelope 02 16 16 combustível Initiatives SUB 47-1 / Contratação de Component 1: Sustainable mão-de-obra de pedreiro Request for Single Stage - One 2017-10- 2017-11- 2018-06- TF / 18765 and Adaptive Community Post Limited 0.00 Canceled para reforma da unidade de Quotations Envelope 04 13 01 Initiatives beneficiamento de polpas. SUB 47-2 / Contratação de mão-de-obra de auxiliar de Component 1: Sustainable Request for Single Stage - One 2017-10- 2017-11- 2018-06- pedreiro para reforma da TF / 18765 and Adaptive Community Post Limited 0.00 Canceled Quotations Envelope 04 13 01 unidade de beneficiamento Initiatives de polpas. SUB 173 - 14 / Contratação de serviços de ajudante de Component 1: Sustainable Pending Request for Single Stage - One 2019-11- 2019-12- 2020-02- pedreiro para etapa de TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 23 05 03 finalização da cozinha Initiatives ation comunitária SUB 173 - 15 / Aluguel de Component 1: Sustainable ônibus para transporte dos Request for Single Stage - One 2020-01- 2020-02- 2020-01- 2020-02- 2020-03- TF / 18765 and Adaptive Community Post Limited 835.73 Signed participantes do Quotations Envelope 08 06 20 11 20 Initiatives intercâmbio e seminário SUB 74-77 / Contratação Component 1: Sustainable serviços de locação de Request for Single Stage - One 2019-11- 2019-11- 2019-12- 2019-12- 2020-01- TF / 18765 and Adaptive Community Post Limited 763.30 Signed veículo Modelo 4x4 para Quotations Envelope 22 29 03 09 02 Initiatives expedição na TI Porquinhos. SUB 71-2 / Contratação de Component 1: Sustainable Request for Single Stage - One 2019-11- 2020-02- 2019-12- 2020-02- 2020-01- 2020-02- servicos gráficos de TF / 18765 and Adaptive Community Post Limited 617.02 Completed Quotations Envelope 24 04 14 11 13 20 materiais de divulgação Initiatives (placas e faixas) SUB 181-3 / Contratação de aluguel de ônibus para Component 1: Sustainable Pending Request for Single Stage - One 2019-12- 2019-12- 2020-02- viagem de intercâmbio - TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 11 28 26 Visitas às comunidades Initiatives ation Guarani do Paraguai SUB 105-2 / Serviços de impressão gráfica para Component 1: Sustainable produzir o caderno de Request for Single Stage - One 2019-12- 2019-12- 2020-01- 2020-01- 2020-02- 2020-04- TF / 18765 and Adaptive Community Post Limited 3,527.07 Completed planos de gestão e práticas Quotations Envelope 17 18 06 14 03 09 Initiatives de produção tradicionais quilombolas personalizadas SUB 105 -20 / Serviços de Diagramação/produção de arte para produzir o Component 1: Sustainable Under Request for Single Stage - One 2019-12- 2019-12- 2020-01- 2020-02- caderno de planos de TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 19 18 15 29 gestão e práticas de Initiatives ation produção tradicionais quilombolas e para confecção de camisetas personalizadas SUB 105 -21 / Serviços Component 1: Sustainable Request for Single Stage - One 2019-12- 2020-02- 2020-01- 2020-03- 2020-02- Técnicos em Cartografia/ TF / 18765 and Adaptive Community Post Limited 2,562.64 Signed Quotations Envelope 15 19 04 12 03 Mapeamento Initiatives SUB 26-20 / Impressão de Component 1: Sustainable 1000 cadernos, com Request for Single Stage - One 2019-12- 2020-02- 2020-01- 2020-02- 2020-02- 2020-03- TF / 18765 and Adaptive Community Post Limited 926.23 Completed informativos dos resultados Quotations Envelope 20 03 02 11 01 19 Initiatives do projeto Component 1: Sustainable SUB 120.17 / Serviços Request for Single Stage - One 2019-12- 2020-02- 2020-01- 2020-02- 2020-02- 2020-05- TF / 18765 and Adaptive Community Post Limited 1,711.62 Completed gráficos Quotations Envelope 27 06 30 17 19 27 Initiatives AI2-6 / Serviços de Component 1: Sustainable Pending Request for Single Stage - One 2020-01- 2020-02- 2020-04- Impressão de materiais TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 25 06 06 informativos para o projeto Initiatives ation AI2-7 / Serviços de Component 1: Sustainable impressão de material para Request for Single Stage - One 2020-01- 2020-01- 2020-01- 2020-01- 2020-03- 2020-02- TF / 18765 and Adaptive Community Post Limited 178.47 Completed ser distribuído no seminário Quotations Envelope 09 20 23 22 23 10 Initiatives da APOINME AI2-8 / Serviços de tratorista para realização de Component 1: Sustainable Pending Request for Single Stage - One 2020-01- 2020-02- 2020-02- marcação de curvas de TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 17 05 11 níveis e terracemanento nas Initiatives ation áreas de erosão AI2-10 / Confecção de Component 1: Sustainable Under Request for Single Stage - One 2020-01- 2020-03- 2020-01- 2020-02- camisetas personalizadas TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 09 10 26 25 para Conselho Terena Initiatives ation AI2-11 / Locação de ônibus Component 1: Sustainable Pending Request for Single Stage - One 2020-01- 2020-01- 2020-02- para assembleia do povo TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 09 26 25 terena Initiatives ation Page 19 AI3 - 8 / Serviço de pessoa Component 1: Sustainable jurídica para construção e Request for Single Stage - One 2020-01- 2020-01- 2020-02- 2020-02- 2020-03- TF / 18765 and Adaptive Community Post Limited 1,197.60 Signed desenvolvimento de novo Quotations Envelope 30 31 13 17 14 Initiatives layout do site do MIQCB BR-CAA-156149-NC-RFQ / Contratação de traslado - MOCxAEFAxMOC para os participantes dos cursos de Component 2: Capacity Pending Request for Single Stage - One 2020-02- 2020-02- 2020-05- Plantas Medicianais ( 30 TF / 18765 Building and Institutional Post Limited 0.00 Implement Quotations Envelope 04 16 16 participantes) + Strengthening ation Empoderamento Feminino e Incidência Política (30 participantes - 2 módulos) BR-CAA-156150-NC-RFQ / Serviço de buffer/alimentação para os Component 2: Capacity Pending cursos a serem realizadas Request for Single Stage - One 2020-02- 2020-02- 2020-05- TF / 18765 Building and Institutional Post Limited 0.00 Implement na AEFA = Plantas Quotations Envelope 04 16 16 Strengthening ation Medicianais ( 30 participantes) + Empoderamento Feminino e Incidência Política (30 participantes - 2 módulos) SUB 268 - 10 / Contratação de serviços de filmagens Component 1: Sustainable Pending Request for Single Stage - One 2020-05- 2020-06- 2020-07- para elaboração de 3 curtas TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 28 15 15 sobre a produção de Initiatives ation artesanato dos Myky SUB 16 - 25 / Serviços de Component 1: Sustainable Pending Request for Single Stage - One 2020-05- 2020-06- 2020-07- mão de obra para instalação TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 30 13 13 de postes elétricos Initiatives ation SUB 100 - 21 / Contratação Component 1: Sustainable Pending de serviços de ilustração e Request for 2020-05- 2020-06- 2020-07- TF / 18765 and Adaptive Community Post 0.00 Implement diagramação para material Quotations 28 11 11 Initiatives ation gráfico SUB 100 - 22 / Contração Component 1: Sustainable Pending Request for Single Stage - One 2020-06- 2020-06- 2020-07- de serviços de gráfica para TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 01 15 15 impressão de cartilhas Initiatives ation BR-CAA-110429-NC-DIR / Contratação de licenças de pacote de programas, Component 2: Capacity Under ADOBE, de edição de 2020-06- 2020-08- 2020-06- 2020-08- 2020-06- 2020-12- TF / 18765 Building and Institutional Post Direct Selection Direct 2,123.80 Implement imagem, vídeo, áudio, 01 13 08 13 14 11 Strengthening ation arquivos PDF, de diagramação, entre outros, objetivando atingir o público do projeto DGM e Subprojetos AI3-6 / Aquisição de um Component 1: Sustainable Request for Single Stage - One 2020-06- 2020-06- 2020-08- 2020-07- 2020-10- 2020-07- sistema pronto para gestão TF / 18765 and Adaptive Community Post Limited 3,250.11 Completed Quotations Envelope 19 30 14 07 13 09 financeira do MIQCB. Initiatives Component 1: Sustainable Pending SUB 211 - 10 / Contratação Request for Single Stage - One 2020-07- 2020-07- 2020-07- TF / 18765 and Adaptive Community Post Limited 0.00 Implement de serviços de internet rural Quotations Envelope 03 28 31 Initiatives ation SUB 99-17 / Contratação Component 1: Sustainable Pending de serviço de limpeza e Request for Single Stage - One 2018-07- 2018-07- 2018-09- TF / 18765 and Adaptive Community Post Limited 0.00 Implement revestimento de poço Quotations Envelope 05 22 20 Initiatives ation artesiano. BR-CAA-181729-NC-RFQ / Component 2: Capacity Pending Request for Single Stage - One 2020-07- 2020-08- 2020-09- Contratação de serviço de TF / 18765 Building and Institutional Post Limited 0.00 Implement Quotations Envelope 15 31 30 impressão para guia de Strengthening ation povos SUB 16 - 26 / Serviços de Component 1: Sustainable 2020-07- 2020-07- 2020-07- 2020-07- 2020-07- 2020-07- 2020-08- 2020-08- mão de obra para instalação TF / 18765 and Adaptive Community Post Direct Selection Direct 1,288.06 Completed 17 24 22 29 28 28 27 19 de postes elétricos Initiatives AI2- 17 / Contratação de Component 1: Sustainable Request for Single Stage - One 2020-08- 2020-08- 2020-09- serviço para instalação do TF / 18765 and Adaptive Community Post Limited 0.00 Canceled Quotations Envelope 08 23 22 sistema de irrigação Initiatives SUB 90 - 6 / Criação de identidade visual e Component 1: Sustainable Pending Request for Single Stage - One 2020-08- 2020-08- 2020-10- confecção e impressão de TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 09 23 22 rotulagem dos produtos da Initiatives ation Central do Cerrado BR-CAA-189883-NC-RFQ / Contratação de serviços de Component 2: Capacity Pending Request for Single Stage - One 2020-10- 2020-10- 2020-11- diagramação de Cartilha TF / 18765 Building and Institutional Post Limited 0.00 Implement Quotations Envelope 04 19 18 sobre Formação de Strengthening ation Lideranças para mulheres SUB 99 - 21 / Contratação Component 1: Sustainable Request for Single Stage - One 2020-09- 2020-10- 2020-10- 2020-10- 2020-12- de serviços para perfuração TF / 18765 and Adaptive Community Post Limited 8,221.77 Signed Quotations Envelope 13 13 02 21 01 de poço artesiano Initiatives SUB 250-10 / Aquisição de um sistema pronto para Component 1: Sustainable Pending Request for Single Stage - One 2020-10- 2020-11- 2021-01- gestão TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 15 09 08 administrativa/financeira da Initiatives ation CIMQCB. BR-CAA-198604-NC-DIR / Component 2: Capacity Pending Contratação de Serviços do 2020-10- 2020-10- 2020-10- 2021-06- TF / 18765 Building and Institutional Post Direct Selection Direct 0.00 Implement Google WorkSpace 07 10 14 11 Strengthening ation Enterprise Plus SUB 25-10 N / Serviço de Component 1: Sustainable Request for Single Stage - One 2020-11- 2020-12- 2020-12- 2020-12- 2021-01- 2020-12- diagramação e impressão de TF / 18765 and Adaptive Community Post Limited 790.60 Completed Quotations Envelope 26 01 08 08 07 30 cartilhas Initiatives BR-CAA-156155-NC-RFQ / Contratacao de empresa especializada em servicos de agenciamento de viagens Component 1: Sustainable Pending Request for Single Stage - One 2020-02- 2020-03- 2020-11- e fornecimento de TF / 18765 and Adaptive Community Post Open - National 0.00 Implement Quotations Envelope 07 08 13 passagens aereas regionais Initiatives ation nacionais e internacionais e passagens terrestres para realizacao das atividades DGM Brasil SUB 109 - 17 / Aquisição Component 1: Sustainable de moinho industrial para 2021-01- 2021-01- 2021-01- 2021-01- 2021-01- 2021-02- 2021-05- TF / 18765 and Adaptive Community Post Direct Selection Direct 8,868.71 Signed unidade de beneficiamento 12 21 17 25 26 19 26 Initiatives do projeto SUB 26-18 / CT26.18 Contratacao de um profissional tecnico para Component 1: Sustainable realizar uma oficina de Request for Single Stage - One 2017-10- 2017-11- 2018-01- TF / 18765 and Adaptive Community Post Limited 0.00 Canceled dezesseis horas sobre Quotations Envelope 11 15 14 Initiatives aprendizados conhecimentos e uso das ervas medicinais do cerrado BR-CAA-231407-NC-RFQ / Contratação de Serviço de Component 3: Project Pending Diagramação do livro sobre Request for Single Stage - One 2021-05- 2021-05- 2021-07- TF / 18765 Management, Monitoring Post Limited 0.00 Implement o Plano de Capacitação para Quotations Envelope 01 27 26 and Evaluation ation os subprojetos do Mecanismo de Doação Dedicado BR-CAA-231409-NC-RFQ / Contratação de Serviços Component 3: Project Pending para Ilustração do livro Request for Single Stage - One 2021-05- 2021-05- 2021-07- TF / 18765 Management, Monitoring Post Limited 0.00 Implement sobre o Plano de Quotations Envelope 01 27 26 and Evaluation ation Capacitação para os subprojetos do Mecanismo de Doação Dedicado SUB 241 - 9 / Aquisição de material pedagógico para Component 1: Sustainable Pending Request for Single Stage - One 2021-06- 2021-07- 2021-08- realização de atividades TF / 18765 and Adaptive Community Post Limited 0.00 Implement Quotations Envelope 22 12 09 previstas no plano de Initiatives ation gestão do território CONSULTING FIRMS Activity Reference No. Short List and Draft Opening of Combined Loan / Credit Market Contract Type Actual Process Expression of Request for Evaluation of Contract / Description Component Review Type Method Terms of Reference Request for Technical Proposals Evaluation Report Signed Contract No. Approach Amount (US$) Status Interest Notice Proposals as Issued Technical Proposal Completion Proposals / Minutes and Draft Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Negotiated Contract Actual Planned Actual Planned Actual BR-CAA-184206-CS-CQS / Contratação de empresa especializada para Component 2: Capacity Consultant realização de formação em Pending 2020-07- 2020-08- 2020-08- 2020-10- TF / 18765 Building and Institutional Post Qualification Open - National 0.00 viabilidade econômica, Implementation 19 04 10 09 Strengthening Selection gestão democrática e inserção no mercado, para projetos apoiados pelo DGM/FIP/Brasil. BR-CAA-197005-CS-QBS / Consultoria empresarial para prover orientações Component 2: Capacity Consultant técnicas e assessoria na Under 2020-10- 2020-10- 2020-10- 2021-01- 2020-12- 2020-12- 2020-12- 2021-03- TF / 18765 Building and Institutional Post Qualification Open - National 0.00 regularização fiscal, jurídica Implementation 01 05 22 08 05 15 25 25 Strengthening Selection e contábil das organizações proponentes dos subprojetos e beneficiárias do DGM. INDIVIDUAL CONSULTANTS Activity Reference No. Invitation to Loan / Credit Market Actual Process Draft Negotiated Contract / Description Component Review Type Method Contract Type Teams of Reference Identified/Selected Signed Contract No. Approach Amount (US$) Status Contract Completion Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BR-CAA-3212-CS-INDV / contratacao de consultoria Component 1: Sustainable Individual Pending 2016-09- 2016-11- 2016-11- 2016-11- 2017-05- individual para realizar duas TF / 18765 and Adaptive Community Post Consultant Open 0.00 Implementation 09 04 08 16 15 oficinas anuais elaboracao Initiatives Selection de projetos BR-CAA-3248-CS-INDV / contratacao de consultoria individual para realizar segundo seminario tematico Component 2: Capacity Individual 2017-02- 2017-03- 2017-04- 2017-05- 2017-07- anual de sustentabilidade TF / 18765 Building and Institutional Post Consultant Open 0.00 Canceled 06 22 12 02 01 socioambiental situando o Strengthening Selection projeto na politica global sobre mudancas climaticas e seus componentes BR-CAA-3254-CS-INDV / Contratacao de consultoria individual para realizar Component 2: Capacity Individual terceiro seminario tematico Pending 2018-02- 2018-03- 2018-04- 2018-04- 2018-07- TF / 18765 Building and Institutional Post Consultant Open 0.00 anual de politicas publicas e Implementation 01 30 02 04 03 Strengthening Selection programas e acoes governamentais relacionados aos objetivos do projeto BR-CAA-17586-CS-INDV / Contratacao de consultoria Component 2: Capacity Individual individual para realizar Pending 2017-06- 2017-08- 2017-08- 2017-09- 2018-02- TF / 18765 Building and Institutional Post Consultant Open 0.00 primeiro Implementation 14 02 23 27 24 Strengthening Selection seminario tematico anual e oficina sobre REDD SUB 55-14 / CT55.14 Contratacao de consultoria tecnica especializada na Component 1: Sustainable Individual 2017-07- 2018-04- 2017-07- 2018-05- 2017-07- 2018-05- 2017-07- 2018-05- 2017-09- area de engenharia de TF / 18765 and Adaptive Community Post Consultant Limited 2,579.38 Signed 07 02 12 21 22 29 31 31 29 alimentos com experiencia Initiatives Selection em agroindustria familiar e comunitaria SUB 55-15 / CT55.15 Contratacao de profissional para realizar estudo ecologico da cagaita e do Component 1: Sustainable Individual araticum realizando o 2017-07- 2017-12- 2017-07- 2018-03- 2017-07- 2018-04- 2017-08- 2018-04- 2017-09- 2018-12- TF / 18765 and Adaptive Community Post Consultant Limited 2,636.75 Completed inventario e pesquisa 05 20 10 28 25 05 01 10 30 10 Initiatives Selection ecologica para avaliacao da densidade e produtividade de cagaita e araticum no territorio quilombola SUB 55-16 / CT55.16 Contratacao de profissional com experiencia em Component 1: Sustainable Individual Pending 2017-07- 2017-07- 2017-07- 2017-08- 2017-09- producao de mudas de TF / 18765 and Adaptive Community Post Consultant Limited 0.00 Implementation 07 12 28 04 13 pequi para realizar Oficina Initiatives Selection de Capaciracao em producao de mudas de pequi SUB 56-18 / CT56.18 Contratacao de consultoria Component 1: Sustainable Individual 2017-07- 2017-07- 2017-08- 2018-01- 2017-08- 2017-08- 2017-08- 2018-01- 2019-06- 2018-03- tecnica especializada em TF / 18765 and Adaptive Community Post Consultant Limited 18,828.57 Completed 12 10 01 09 06 10 17 22 08 28 recuperacao de nascentes e Initiatives Selection microbacias na regiao SUB 75-3 / CQ75.3 Contratação de consultoria Component 1: Sustainable Individual para realizar diagnostico Pending 2017-07- 2017-07- 2017-07- 2017-08- 2017-11- TF / 18765 and Adaptive Community Post Consultant Limited 0.00 com objetivo a elaboração Implementation 05 15 30 17 15 Initiatives Selection de plano de desenvolvimento de turismo sustentável SUB 75-4 / CQ75.4 Contratação de profissional para realizar diagnostico ambiental com objetivo a Component 1: Sustainable Individual Pending 2017-07- 2017-07- 2017-08- 2017-08- 2017-11- elaboração de dois planos TF / 18765 and Adaptive Community Post Consultant Limited 0.00 Implementation 10 20 10 17 15 de gestão ambiental e dois Initiatives Selection projetos arquitetônicos com memorial descritivo e orçamento SUB 90-6 / CT90.6 Contratação de consultoria Component 1: Sustainable Individual 2017-07- 2017-07- 2017-08- 2017-08- 2017-11- para a formação em Gestão TF / 18765 and Adaptive Community Post Consultant Limited 0.00 Canceled 11 21 05 14 12 de Operações de Remessa e Initiatives Selection Transporte de produtos SUB 109-13 / CT109.13 Contratação de consultoria especializado na área de Component 1: Sustainable Individual administração gestão de Pending 2017-08- 2017-09- 2017-09- 2017-10- 2018-07- TF / 18765 and Adaptive Community Post Consultant Limited 0.00 associação comunitária e Implementation 15 02 22 02 09 Initiatives Selection comercialização para elaborar plano de comercialização dos produtos do babaçu SUB 28-1 / Contratação de Component 1: Sustainable Individual serviços de assessoria Pending 2017-09- 2017-09- 2017-09- 2017-10- 2019-02- TF / 18765 and Adaptive Community Post Consultant Limited 0.00 técnica para Implementation 15 20 25 14 26 Initiatives Selection acompanhamento das atividades do projeto SUB 113-19 / Contratação de consultoria para Component 1: Sustainable Individual realização de estudo Pending 2017-09- 2017-10- 2017-10- 2017-10- 2018-01- TF / 18765 and Adaptive Community Post Consultant Limited 0.00 etnográfico, com ênfase nos Implementation 15 05 16 27 25 Initiatives Selection recursos hídricos da Terra Indígena Portal do Encantado. SUB 120-14 / Contratação de profissional para Component 1: Sustainable Individual realização de estudo Under 2018-01- 2018-02- 2018-03- 2018-04- 2018-07- TF / 18765 and Adaptive Community Post Consultant Limited 0.00 antropológico para Implementation 25 24 26 12 11 Initiatives Selection compreensão da visão econômica e gênero nos grupos de coletores do tix. SUB 127-32 / Consultoria individual para elaboracao Component 1: Sustainable Individual Pending 2017-11- 2017-12- 2017-12- 2018-01- 2018-02- de planta baixa do Centro TF / 18765 and Adaptive Community Post Consultant Limited 0.00 Implementation 22 05 15 03 12 de Revitalizacao da cultura e Initiatives Selection visitacao AI1 - 7 / Consultoria técnica para elaboração da propostas metodológica e conteúdo programático da Component 1: Sustainable Individual Pending 2017-12- 2017-12- 2018-01- 2018-01- 2018-03- reunião. Moderação da TF / 18765 and Adaptive Community Post Consultant Limited 0.00 Implementation 06 26 05 19 20 reunião, sistematização da Initiatives Selection relatoria e elaboração de relatórios técnico e interlocução com os articuladores indígenas. SUB 25-17 / CQ25.17 Component 1: Sustainable Individual 2017-06- 2017-07- 2017-07- 2017-07- 2019-03- Contratação de assessoria TF / 18765 and Adaptive Community Post Consultant Limited 0.00 Canceled 19 05 15 31 23 técnica para execução Initiatives Selection projeto SUB 74-11 / Contratação de profissional técnico Component 1: Sustainable Individual 2017-09- 2017-09- 2017-09- 2017-10- 2018-09- especializada para TF / 18765 and Adaptive Community Post Consultant Limited 0.00 Canceled 13 18 23 10 15 assessoria e Initiatives Selection acompanhamento das atividades do projeto. SUB 108-4 / Contratação Component 1: Sustainable Individual 2017-09- 2017-09- 2017-09- 2017-10- 2019-03- de serviços de assessoria TF / 18765 and Adaptive Community Post Consultant Limited 0.00 Canceled 08 13 23 04 08 para execução do projeto Initiatives Selection SUB 113-4 / Contratação Component 1: Sustainable Individual de serviços de assessoria 2017-09- 2017-09- 2017-09- 2017-10- 2018-12- TF / 18765 and Adaptive Community Post Consultant Limited 0.00 Canceled técnica especializada na 08 13 21 20 24 Initiatives Selection execução do projeto Component 1: Sustainable Individual SUB 30 - 33 / Contratação 2017-09- 2017-09- 2017-10- 2017-10- 2019-02- TF / 18765 and Adaptive Community Post Consultant Limited 0.00 Canceled de assessoria técnica. 10 30 10 24 06 Initiatives Selection SUB 88-8 / Consultoria individual para desenvolvimento de laudo Component 1: Sustainable Individual antropológico para a Under 2018-01- 2018-02- 2018-02- 2018-03- 2018-10- TF / 18765 and Adaptive Community Post Consultant Limited 0.00 consecução dos objetivos Implementation 24 14 23 09 25 Initiatives Selection do Projeto destacando os potenciais e as vulnerabilidades do território. Page 20 CT26-18 / Contratacao de um profissional para Component 1: Sustainable Individual realizar uma avaliacao Pending 2018-01- 2018-02- 2018-02- 2018-02- 2019-10- TF / 18765 and Adaptive Community Post Consultant Limited 0.00 tecnica e dar Implementation 18 07 12 26 19 Initiatives Selection recomendacoes sobre a recuperacao de duas areas que acessavam agua SUB 88 - 9 / Consultoria individual para desenvolvimento de um diagnóstico socioambiental Component 1: Sustainable Individual por meio da produção de Under 2018-01- 2018-02- 2018-02- 2018-03- 2018-10- TF / 18765 and Adaptive Community Post Consultant Limited 0.00 laudo ambiental para a Implementation 24 13 23 09 25 Initiatives Selection consecução dos objetivos do projeto destacando os potenciais e as vulnerabilidades do território SUB 135-22 / Contratação Component 1: Sustainable Individual 2017-09- 2017-09- 2017-09- 2017-10- 2018-01- de profissional TF / 18765 and Adaptive Community Post Consultant Limited 0.00 Canceled 15 20 27 07 05 especializado em bio Initiatives Selection construção SUB 26-19 / Contratacao Component 1: Sustainable Individual de consultoria para fazer o 2018-01- 2019-08- 2018-02- 2019-09- 2018-02- 2019-10- 2018-02- 2019-11- 2018-05- 2020-02- TF / 18765 and Adaptive Community Post Consultant Limited 2,330.55 Completed mapeamento da morraria 18 19 07 05 12 18 26 01 27 28 Initiatives Selection mapa etnoambiental SUB 108-2 / Contratação de prestação de serviços Component 1: Sustainable Individual especializado para 2017-09- 2017-10- 2017-10- 2017-10- 2018-01- TF / 18765 and Adaptive Community Post Consultant Limited 0.00 Canceled realização de capacitação 15 05 16 30 28 Initiatives Selection em boas práticas para produção de alimentos. SUB 108-3 / Contratação de prestação de serviços Component 1: Sustainable Individual 2017-09- 2017-10- 2017-10- 2017-11- 2018-02- especializado para TF / 18765 and Adaptive Community Post Consultant Limited 0.00 Canceled 25 13 25 08 06 realização de capacitação Initiatives Selection em gestão da unidade de beneficiamento. SUB 113-9 / Contratação Component 1: Sustainable Individual 2017-09- 2017-09- 2017-10- 2017-10- 2018-01- de instrutor para realização TF / 18765 and Adaptive Community Post Consultant Limited 0.00 Canceled 11 16 07 23 11 de oficina de apicultura. Initiatives Selection AI1 - 6 / Consultoria para suporte no planejamento, proposta metodológica e conteúdo programático, Component 1: Sustainable Individual com foco nos aspectos Pending 2017-12- 2017-12- 2018-01- 2018-01- 2018-03- TF / 18765 and Adaptive Community Post Consultant Limited 0.00 jurídicos, preparação dos Implementation 06 26 05 19 20 Initiatives Selection materiais de apoio, elaboração de relatório sobre processo de constituição de personalidade jurídica SUB 26-15 / CT26.15 Component 1: Sustainable Individual 2017-06- 2017-06- 2017-07- 2017-08- 2017-11- Contratacao de consultoria TF / 18765 and Adaptive Community Post Consultant Limited 0.00 Canceled 19 24 15 03 01 para assessoria tecnica Initiatives Selection SUB 16-12 / CQ16-12 Component 1: Sustainable Individual 2017-06- 2017-07- 2017-07- 2017-08- 2019-03- Contratação de assessoria TF / 18765 and Adaptive Community Post Consultant Limited 0.00 Canceled 19 09 19 02 25 técnica especializada. Initiatives Selection SUB 16-13 / CQ16-13 Component 1: Sustainable Individual 2017-06- 2017-07- 2017-07- 2017-08- 2019-03- Contratação de assessoria TF / 18765 and Adaptive Community Post Consultant Limited 0.00 Canceled 19 09 19 02 25 técnica em comunicao Initiatives Selection SUB 100 - 9 / Consultoria Component 1: Sustainable Individual individual para implantação 2017-12- 2018-01- 2018-01- 2018-02- 2018-03- TF / 18765 and Adaptive Community Post Consultant Limited 0.00 Canceled de modelos de sistemas 20 09 19 02 14 Initiatives Selection agroflorestais. SUB 135-6 / Contratação Component 1: Sustainable Individual de assessoria para 2017-09- 2017-09- 2017-10- 2017-10- 2019-07- TF / 18765 and Adaptive Community Post Consultant Limited 0.00 Canceled acompanhamento e das 25 30 07 17 29 Initiatives Selection ações do projeto SUB 123-14 / Contratação de consultoria para Component 1: Sustainable Individual Under 2018-04- 2019-11- 2018-05- 2018-05- 2018-06- 2018-12- construção coletiva de TF / 18765 and Adaptive Community Post Consultant Limited 0.00 Implementation 27 07 02 29 06 03 estratégias de Initiatives Selection comercialização para o artesanato Karajá SUB 123-13 / Contratação consultoria para desenvolvimento da identidade visual da Component 1: Sustainable Individual associação. Produtos: 2018-04- 2018-05- 2018-05- 2018-06- 2020-01- TF / 18765 and Adaptive Community Post Consultant Limited 0.00 Canceled marca, blog/site, catalogo 27 04 25 04 25 Initiatives Selection virtual, embalagens, rótulos, etiquetas, redes sociais, etc...) e acompanhamento técnico projeto. SUB 109-15 / Contratação de profissional para elaboração da planta e Component 1: Sustainable Individual memorial descritivo da Under 2018-06- 2019-08- 2018-06- 2018-06- 2018-07- 2018-09- TF / 18765 and Adaptive Community Post Consultant Limited 0.00 reforma da agroindústria, Implementation 10 08 20 25 05 03 Initiatives Selection de acordo com a legislação vigente e realização de curso de boas práticas de produção. 122-13 / Contratação de consultor individual em geoprocessamento para Component 1: Sustainable Individual elaboracao de etno mapas, Pending 2018-09- 2018-09- 2018-09- 2018-10- 2019-04- TF / 18765 and Adaptive Community Post Consultant Limited 0.00 de localização, Implementation 06 11 26 06 04 Initiatives Selection espacializacaoo de nascentes, mapas históricos, relevo e hidrografico. 125-14 / Contratacao de Component 1: Sustainable Individual consultoria individual para Under 2018-09- 2019-05- 2018-09- 2018-09- 2018-10- 2019-04- TF / 18765 and Adaptive Community Post Consultant Limited 0.00 elaboracao de plano de Implementation 06 08 16 26 13 11 Initiatives Selection gestao ambiental e territorial SUB 143 - 12 / Contratação Component 1: Sustainable Individual de consultoria individual Under 2019-01- 2019-04- 2019-01- 2019-01- 2019-01- 2019-07- TF / 18765 and Adaptive Community Post Consultant Limited 0.00 para elaboração de plano de Implementation 07 02 12 15 25 24 Initiatives Selection gestão ambiental e territorial. SUB 26 -16 / Contratação de uma consultoria técnica especializada para realizar Component 1: Sustainable Individual 2019-02- 2019-07- 2019-02- 2019-03- 2019-02- 2019-09- 2019-02- 2019-10- 2019-08- 2020-04- uma avaliação técnica e dar TF / 18765 and Adaptive Community Post Consultant Limited 1,750.36 Completed 06 19 12 08 18 07 27 09 26 30 recomendações sobre a Initiatives Selection recuperação de duas áreas que corriam água antes. BR-CAA-102339-CS-CDS / Contratação de consultoria individual especializada para orientação e promoção Component 2: Capacity Individual 2019-02- 2019-03- 2019-03- 2019-04- 2019-07- de informação qualificada TF / 18765 Building and Institutional Post Consultant Limited 0.00 Canceled 28 05 19 09 08 sobre a estratégia de Strengthening Selection REDD+ no contexto nacional e global, para público diversificado do Projeto DGM/Brasil SUB 16-14 / CQ16-14 Contratação de consultoria Component 1: Sustainable Individual Pending 2017-06- 2017-07- 2017-07- 2017-08- 2017-11- para elaboração de projeto TF / 18765 and Adaptive Community Post Consultant Limited 0.00 Implementation 20 10 20 03 01 técnico de recuperação de Initiatives Selection nascentes e das áreas SUB 71 CI 01 / Consultoria Individual para elaboração do manual de boas práticas para os produtos do coco, realização do plano de Component 1: Sustainable Individual 2019-03- 2019-06- 2019-05- 2019-05- 2019-05- 2019-08- negócios. Estudo, TF / 18765 and Adaptive Community Post Consultant Open 0.00 Canceled 25 05 01 06 26 24 Padronização, adaptação Initiatives Selection dos produtos e da produção, boas práticas, armazenamento, estoque, dos produtos da Raízes do Campo BR-CAA-110404-CS-INDV / Contratação de consultoria individual para aplicar metodologia, técnicas e procedimentos Component 2: Capacity Individual 2019-04- 2019-07- 2019-05- 2019-06- 2019-07- 2019-12- associados à autoprodução TF / 18765 Building and Institutional Post Consultant Limited 0.00 Canceled 29 16 19 13 18 15 comunitária de painéis-kits Strengthening Selection solares, dimensionamento, montagem e instalação de pequenos sistemas de geração de energia elétrica solar. AI4 - 1 / Contratação de consultoria individual para Component 1: Sustainable Individual oficinas sobre tema REDD+, 2019-05- 2019-06- 2019-06- 2019-07- 2019-06- 2019-10- 2019-06- 2019-10- 2019-08- 2020-04- TF / 18765 and Adaptive Community Post Consultant Limited 3,124.74 Completed e produzir uma minuta de 27 12 06 11 14 15 22 15 21 30 Initiatives Selection conteúdo do folder que será distribuído SUB 195 - 2 / Contratação Component 1: Sustainable Individual de consultoria para Under 2019-06- 2019-10- 2019-07- 2019-07- 2019-08- 2019-10- TF / 18765 and Adaptive Community Post Consultant Limited 0.00 elaboração de Plano Implementation 25 18 10 25 04 03 Initiatives Selection Territorial e Ambiental da TI Sandradouro. SUB 2120-2 / Contratação Component 1: Sustainable Individual de consultoria para Pending 2019-06- 2019-07- 2019-07- 2019-08- 2019-10- TF / 18765 and Adaptive Community Post Consultant Limited 0.00 realização de planta baixa Implementation 24 09 24 03 02 Initiatives Selection para construção da cozinha comunitária SUB 241-6 / Contratação Component 1: Sustainable Individual de consultoria para Under 2019-06- 2019-08- 2019-06- 2019-09- 2019-07- 2019-10- 2019-08- 2019-10- TF / 18765 and Adaptive Community Post Consultant Limited 0.00 elaboração de Plano de Implementation 17 26 22 06 13 14 17 16 Initiatives Selection Gestão Territorial, Produtiva e Ambiental SUB 71 CI 02 / Consultoria Individual para elaboração do manual de boas práticas para os produtos do coco. Component 1: Sustainable Individual Under 2019-06- 2019-08- 2019-07- 2019-08- 2019-08- 2019-12- Estudo, Padronização, TF / 18765 and Adaptive Community Post Consultant Open 0.00 Implementation 27 08 26 05 20 18 adaptação dos produtos e Initiatives Selection da produção, boas práticas, armazenamento, estoque, dos produtos da Raízes do Campo. BR-CAA-110405-CS-INDV / Contratação de consultoria individual, para aplicar metodologias, técnicas e procedimentos Component 2: Capacity 2019-07- 2019-06- 2019-08- 2019-10- 2020-04- associados a autoprodução TF / 18765 Building and Institutional Post Direct Selection Direct 0.00 Under Review 22 05 01 05 02 comunitária de painéis-kits Strengthening solares, dimensionamento, montagem e instalação de pequenos sistemas de geração, de elétrica solar SUB 169- CI 001.2019 / Component 1: Sustainable Individual Contratação de Consultoria 2019-09- 2019-09- 2019-10- 2019-09- 2019-10- 2019-11- 2019-11- 2019-12- 2020-01- 2020-06- TF / 18765 and Adaptive Community Post Consultant Limited 1,010.71 Completed Individual para 20 23 05 24 20 28 15 02 14 26 Initiatives Selection Levantamento dos atrativos turísticos. BR-CAA-133672-CS-INDV / Contratação de pessoa física para de criação, Component 2: Capacity Individual envolvendo pesquisas, Under 2019-09- 2019-10- 2019-09- 2019-10- 2019-10- 2020-02- TF / 18765 Building and Institutional Post Consultant Limited 0.00 concepção, produção Implementation 15 14 30 05 15 12 Strengthening Selection musical, gravação, mixagem, masterização de trilha sonora vídeo musical do DGM/FIP/Brasil. BR-CAA-133677-CS-INDV / Contratação de profissional, pessoa física, para prover orientações técnicas junto aos Component 1: Sustainable Individual Under 2019-09- 2019-10- 2019-09- 2019-10- 2019-10- 2020-02- subprojetos que estão TF / 18765 and Adaptive Community Post Consultant Limited 0.00 Implementation 15 03 30 05 15 12 executando e/ou vão iniciar Initiatives Selection a execução de pequenas obras de reforma e/ou construções simples, adequadas às condições de vida dos povos indígenas, SUB 170 - CI 1 / Contratação de consultoria Component 1: Sustainable Individual Under 2019-09- 2019-09- 2019-09- 2019-10- 2019-10- 2020-02- para desenvolvimento de TF / 18765 and Adaptive Community Post Consultant Limited 0.00 Implementation 20 23 30 05 12 09 SAFs e plantios Initiatives Selection consorciados (Ciências Agrárias) SUB 169- CI 002.2019 / Component 1: Sustainable Individual Contratação de Consultoria Under 2019-10- 2019-09- 2019-11- 2019-11- 2019-12- 2020-03- TF / 18765 and Adaptive Community Post Consultant Limited 0.00 Individual para diagnóstico Implementation 22 25 06 21 01 01 Initiatives Selection do conflito das associações BR-CAA-135088-CS-INDV / Contratação de Component 2: Capacity Individual 2019-10- 2020-08- 2019-10- 2020-03- 2019-10- 2020-06- 2019-11- 2020-09- 2020-02- 2021-05- profissional para realização TF / 18765 Building and Institutional Post Consultant Limited 7,584.71 Completed 10 13 15 09 30 10 15 01 13 05 de curso de formação de Strengthening Selection lideranças voltado para mulheres. BR-CAA-135429-CS-INDV / Consultoria individual para realização de oficina sobre comunicação estratégica Component 2: Capacity Individual 2019-09- 2020-08- 2019-10- 2019-10- 2019-10- 2020-04- 2019-10- 2020-09- 2020-02- 2021-06- junto a povos indígenas, TF / 18765 Building and Institutional Post Consultant Limited 8,458.05 Completed 24 13 09 25 14 10 22 16 19 04 quilombolas, comunidades Strengthening Selection tradicionais e parceiros do projeto e CAA, tendo por foco a juventude. SUB 3-10 / Contratação de serviços técnico especializado para Component 1: Sustainable Individual elaboração de planta baixa, 2017-09- 2017-09- 2017-10- 2017-10- 2017-12- TF / 18765 and Adaptive Community Post Consultant Limited 0.00 Canceled com memorial descritivo e 11 16 01 10 09 Initiatives Selection orçamento para construção de um galpão para armazenamento e uso das comunidades indígenas. SUB 98 - 15 / Contratacao de assessoria tecnica para Component 1: Sustainable Individual elaborar projeto tecnico da 2018-01- 2018-02- 2018-02- 2018-03- 2018-10- TF / 18765 and Adaptive Community Post Consultant Limited 0.00 Canceled casa cultura incluindo 22 09 19 05 21 Initiatives Selection projeto arquitetonico, memorial descritivo BR-CAA-133560-CS-INDV / Contratação de profissional para apoio Component 3: Project Individual junto a equipe financeira 2019-09- 2019-09- 2019-09- 2019-09- 2019-10- 2020-01- TF / 18765 Management, Monitoring Post Consultant Limited 0.00 Canceled para análise dos 15 17 25 30 07 05 and Evaluation Selection lançamentos e correções no sistema de gestão, referente receitas e despesas dos anos 2015-2018 SUB 127-33 / Contratacao de profissional para elaboracao de Plano de Component 1: Sustainable Individual 2017-11- 2017-12- 2017-12- 2018-01- 2018-03- Funcionando do Centro de TF / 18765 and Adaptive Community Post Consultant Limited 0.00 Canceled 28 12 26 08 09 Revitalizacao e treinamento Initiatives Selection aos colaboradores que irao trabalhar no local SUB 127-34 / Contratação de serviços para Component 1: Sustainable Individual criação/desenvolvimento de 2018-05- 2018-06- 2018-06- 2018-07- 2019-01- TF / 18765 and Adaptive Community Post Consultant Limited 0.00 Canceled site - incluindo design e 31 05 26 06 02 Initiatives Selection programação e treinamento para alimentação do site. SUB 47-8 / Contratação de serviços especializados de Component 1: Sustainable Individual engenharia, para elaboração 2017-09- 2017-09- 2017-09- 2017-10- 2017-12- TF / 18765 and Adaptive Community Post Consultant Limited 0.00 Canceled de projeto básico de 11 16 26 10 09 Initiatives Selection reforma de um galpão e um ponto de beneficiamento de frutos. BR-CAA-166615-CS-INDV / Contratação de consultoria individual Component 2: Capacity Individual especializada, para a 2020-04- 2020-04- 2020-05- 2020-06- 2020-08- TF / 18765 Building and Institutional Post Consultant Direct 0.00 Canceled realização do módulo Curso 06 26 17 21 20 Strengthening Selection de aprofundamento em Energia Fotovoltaica junto a público diversificado do Projeto BR-CAA-197009-CS-INDV / Contratação de consultor individual para profissional da área de educação à Component 2: Capacity Individual distância ou ambiente Pending 2020-10- 2020-10- 2020-11- 2020-11- 2021-02- TF / 18765 Building and Institutional Post Consultant Open 0.00 virtual de aprendizagem Implementation 04 31 10 18 16 Strengthening Selection para ministrar cursos sobre o domínio de plataformas digitais, ferramentas e recursos disponíveis BR-CAA-239241-CS-INDV / Contratacao de consultoria individual especializada para Component 2: Capacity Individual Pending 2021-06- 2021-08- 2021-08- 2021-09- 2022-03- orientacao e promocao de TF / 18765 Building and Institutional Post Consultant Open 0.00 Implementation 14 02 23 27 26 informacao qualificada Strengthening Selection sobre a estrategia de REDD+ no contexto nacional e global, para publico diversificado do Projeto DGM Brasil Page 21 PROCUREMENT PLAN Project information: Uganda, East Africa Skills for Transformation and Regional Integration Project (EASTRIP) P163399 Project Implementation agency: Inter-University Council for East Africa Date of the Procurement Plan: April 27, 2018 Period covered by this Procurement Plan: May 2018- January 2019 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international and national competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: As IUCEA does not follow Uganda PPDA, when approaching the national market (as specified in the Procurement Plan tables in STEP), Bank’s Procurement Regulations will be followed. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations –Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is applicable for those contracts identified in the Procurement Plan tables; Works: is applicable for those contracts identified in the Procurement Plan tables Other Relevant Procurement Information. None PROCUREMENT Eastern Africa : East Africa Skills for Transformation and Regional Integration Project (EASTRIP) PLAN General Information Country: Eastern Africa Bank’s Approval Date of the Original Procurement Plan: 2019-04-12 2021-05-17 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P163399 GPN Date: 2019-08-06 Project Name: East Africa Skills for Transformation and Regional Integration Project (EASTRIP) Loan / Credit No: IDA / 63350 M Executing Agency(ies): inistry of Science and Higher Education - ET WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned ET-MOSHE - ET-109520-CW- RFB / Construction of Building Pending Creating national TVET Single Stage - One 2021-01- Lot-1 TVET QA Authority IDA / 63350 Post Request for Bids Open - National 1,600,000.00 0.00 Implementat 2020-04-13 2020-04-18 2020-05-30 2020-06-29 2020-08-03 enabling environment Envelope 30 Lot-2 Research and ion Development Institute (at TI) GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-MOSHE - ET-109515-GO- Creating national TVET Single Stage - One IDA / 63350 Prior Request for Bids Open - International 2,100,000.00 0.00 Canceled 2019-06-28 2019-07-03 2019-08-14 2019-09-13 2019-10-18 2020-04-15 RFB / Procurement of Vehicles enabling environment Envelope ET-MOSHE - ET-135533-GO- Creating national TVET Request for Single Stage - One RFQ / Procurement of Office IDA / 63350 Post Open - National 76,000.00 0.00 Canceled 2019-10-06 2019-12-01 2020-05-29 enabling environment Quotations Envelope Furniture ET-MOSHE - ET-138762-GO- Creating national TVET Request for Single Stage - One RFQ / Purchase of office IDA / 63350 Post Open - National 5,000.00 2,276.13 Signed 2019-10-14 2019-12-09 2020-08-04 2020-06-06 enabling environment Quotations Envelope stationary ET-MOSHE - ET-167220-GO- Creating national TVET Request for Single Stage - One IDA / 63350 Post Limited 15,000.00 14,059.94 Signed 2020-04-08 2020-04-06 2020-06-03 2020-05-20 2020-11-30 RFQ / Laptop purchase enabling environment Quotations Envelope ET-MOSHE - ET-173744-GO- RFQ / Office Furniture Creating national TVET Request for Single Stage - One IDA / 63350 Post Limited 38,000.00 21,240.35 Signed 2020-05-23 2020-06-12 2020-07-18 2020-06-09 2021-01-14 Procurement for the new enabling environment Quotations Envelope project office ET-MOSHE - ET-176097-GO- Creating national TVET UN Agencies UN / Procurement of different IDA / 63350 Post Direct 1,000,000.00 960,539.47 Signed 2020-06-05 2020-06-12 2020-06-10 2020-06-18 2020-07-15 2020-07-17 2021-01-11 enabling environment (Direct) types of Vehicles ET-MOSHE - ET-181056-GO- Pending RFQ / Procurement of Creating national TVET Request for Single Stage - One IDA / 63350 Post Limited 5,300.00 0.00 Implementati 2020-06-30 2020-08-14 2020-08-24 Sanitation and Canteen enabling environment Quotations Envelope on Materials for the project office ET-MOSHE - ET-181058-GO- Pending Creating national TVET Request for Single Stage - One RFQ / Procurement of Office IDA / 63350 Post Limited 6,700.00 0.00 Implementati 2020-06-30 2020-08-10 2020-08-20 enabling environment Quotations Envelope Furniture and Fixtures on ET-MOSHE - ET-181057-GO- Pending Creating national TVET Request for Single Stage - One RFQ / Procurement of Office IDA / 63350 Post Limited 43,000.00 0.00 Implementati 2020-06-30 2020-08-10 2020-08-20 enabling environment Quotations Envelope Equipment on ET-MOSHE - ET-181288-GO- Pending Creating national TVET Request for Single Stage - One RFQ / Procurement of IDA / 63350 Post Limited 7,000.00 0.00 Implementati 2020-06-30 2020-07-22 2020-08-01 enabling environment Quotations Envelope Stationery Materials on ET-MOSHE - ET-198515-GO- Pending Creating national TVET Single Stage - One RFB / Procurement of Diesel IDA / 63350 Post Request for Bids Open - National 150,000.00 0.00 Implementati 2020-10-30 2020-11-04 2020-12-04 2020-12-19 2021-01-23 2021-04-23 enabling environment Envelope Generator on ET-MOSHE - ET-198533-GO- Creating national TVET Single Stage - One RFB / Supply and Delivery of IDA / 63350 Post Request for Bids Open - International 1,000,000.00 0.00 Canceled 2020-11-25 2020-11-30 2021-01-11 2021-02-10 2021-03-17 2021-09-13 enabling environment Envelope Vehicles ET-MOSHE - ET-198496-GO- RFB / TVET Campus Network Creating national TVET Single Stage - One IDA / 63350 Prior Request for Bids Open - International 8,000,000.00 0.00 Canceled 2020-11-03 2021-04-13 2020-11-08 2020-12-20 2021-01-19 2021-02-23 2021-08-22 Infrastructure for the 19 enabling environment Envelope Colleges Strengthening selected ET-MOSHE - ET-225571-GO- Regional Flagship TVET Under RFQ / Procurement of Office Request for Single Stage - One IDA / 63350 Institutes for high quality Post Limited 75,000.00 0.00 Implementati 2021-03-28 2021-05-13 2021-05-17 2021-05-21 Furniture and Fixtures for Quotations Envelope skills development in priority on MoSHE sectors Strengthening selected ET-MOSHE - ET-225566-GO- Regional Flagship TVET Pending Single Stage - One RFB / Supply, Installation and IDA / 63350 Institutes for high quality Prior Request for Bids Open - International 2,300,000.00 0.00 Implementati 2021-03-31 2021-04-15 2021-05-30 2021-06-29 2021-07-24 2021-10-22 Envelope Commissioning of TVET MIS skills development in priority on sectors ET-MOSHE - ET-229183-GO- Pending Creating national TVET DIR / Procurement of IDA / 63350 Post Direct Selection Direct 1,000,000.00 0.00 Implementati 2021-04-20 2021-04-25 2021-05-30 2021-11-26 enabling environment Different Types of Vehicles on ET-MOSHE - ET-236746-GO- Under RFB / TVET Campus Network Creating national TVET Single Stage - One IDA / 63350 Prior Request for Bids Open - International 5,000,000.00 0.00 Implementati 2021-05-31 2021-06-18 2021-06-05 2021-06-24 2021-07-17 2021-08-16 2021-09-20 2022-03-19 Infrastructure for 10 selected enabling environment Envelope on Poly Technic Colleges NON CONSULTING SERVICES Page 1 Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-MOSHE - ET-173347-NC- Under RFQ / Renovation and Creating national TVET Request for Single Stage - One IDA / 63350 Post Limited 18,000.00 0.00 Implementati 2020-05-20 2020-05-22 2020-07-15 2021-01-11 painting service of the newly enabling environment Quotations Envelope on rented Project Office Building ET-MOSHE - ET-173356-NC- RFQ / Selecting a firm that Creating national TVET Request for Single Stage - One manages the cleaning of the IDA / 63350 Post Limited 5,500.00 4,495.54 Signed 2020-05-20 2020-05-22 2020-07-15 2020-06-23 2021-01-11 enabling environment Quotations Envelope newly rented project office for one year period ET-MOSHE - ET-173367-NC- RFQ / Security Service- Under Creating national TVET Request for Single Stage - One Selecting a firm that manages IDA / 63350 Post Limited 6,500.00 0.00 Implementati 2020-05-27 2020-05-22 2020-07-22 2021-01-18 enabling environment Quotations Envelope the security of the office on building and office property CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-MOSHE - ET-198440-CS- QCBS / Development of 17 Creating national TVET Quality And Cost- Under IDA / 63350 Prior Open - International 1,800,000.00 0.00 2020-10-20 2020-11-13 2020-11-10 2020-11-22 2020-12-24 2021-03-23 2021-01-21 2021-02-20 2021-03-27 2021-05-01 2021-10-28 Occupational Standards in enabling environment Based Selection Implementation EASTRIP priority sectors ET-MOSHE - ET-198487-CS- Creating national TVET Quality And Cost- QCBS / Ethiopian Sustainable IDA / 63350 Prior Open - International 300,000.00 0.00 Canceled 2020-10-23 2020-11-13 2020-11-13 2020-11-22 2020-12-27 2021-01-24 2021-02-23 2021-03-30 2021-05-04 2021-10-31 enabling environment Based Selection TVET Financing Strategy ET-MOSHE - ET-198462-CS- QCBS / Selection of a Consulting Firm that develop Creating national TVET Quality And Cost- Under IDA / 63350 Post Open - National 27,000.00 0.00 2020-10-20 2020-10-27 2020-11-10 2020-11-02 2020-12-14 2020-12-11 2020-12-29 2021-01-28 2021-02-26 2021-04-02 2021-07-31 a strategic document for the enabling environment Based Selection Implementation Establishment of TVET Quality Assurance Agency ET-MOSHE - ET-198478-CS- QCBS / Development of Creating national TVET Quality And Cost- Under Strategic Framework for the IDA / 63350 Post Open - National 13,500.00 0.00 2020-10-25 2020-10-27 2020-11-15 2020-11-02 2020-12-29 2020-12-11 2021-01-13 2021-02-12 2021-03-13 2021-04-17 2021-08-15 enabling environment Based Selection Implementation Establishment of TVET Research Institute ET-MOSHE - ET-192202-CS- Creating national TVET Least Cost QCBS / External Audit for the IDA / 63350 Post Open - National 35,000.00 0.00 Canceled 2020-09-08 2020-09-21 2020-09-29 2020-10-15 2020-11-12 2020-12-10 2021-01-09 2021-02-13 2021-03-20 2021-09-16 enabling environment Selection FY 2019/2020 ET-MOSHE - ET-203190-CS- Creating national TVET Least Cost LCS / Selection of Financial IDA / 63350 Post Open - National 35,000.00 2,244.66 Signed 2020-11-09 2020-11-13 2020-11-19 2020-12-09 2020-11-19 2020-12-19 2020-12-07 2021-01-03 2020-12-07 2021-01-20 2020-12-11 2021-02-06 2020-12-15 2021-03-23 enabling environment Selection Audit Firm ET-MOSHE-ET-198487-CS- QCBS-2 / Selection of a Creating national TVET Quality And Cost- Under Consulting Firm to Develop IDA / 63350 Post Open - National 300,000.00 0.00 2021-02-20 2021-02-22 2021-02-23 2021-03-20 2021-04-10 2021-04-25 2021-05-30 2021-06-28 2021-10-26 enabling environment Based Selection Implementation Sustainable TVET Financing Strategy ET-MOSHE - ET-109513-CS- QCBS / Consultancy Service for Detail Engineering Design, Tender Document Creating national TVET Quality And Cost- IDA / 63350 Post Open - National 200,000.00 0.00 Canceled 2019-05-30 2021-04-06 2019-06-20 2019-08-03 2019-08-31 2019-09-30 2019-11-04 2019-12-09 2022-05-27 Preparation, Construction enabling environment Based Selection Supervision and contracts administration of QA Authority and Research and Development Institute. ET-MOSHE - ET-229572-CS- CQS / Consultancy Service for Detail Engineering Design, Consultant Tender Document Creating national TVET Under IDA / 63350 Post Qualification Limited 200,000.00 0.00 2021-04-25 2021-04-20 2021-05-09 2021-05-03 2021-06-08 2021-07-13 2023-01-04 Preparation, Construction enabling environment Implementation Selection Supervision and contracts administration of QA Authority and Research and Development Institute ET-MOSHE - ET-229840-CS- CQS / Selection of a Consultant Creating national TVET Under Consulting Firm to Develop an IDA / 63350 Post Qualification Limited 84,000.00 0.00 2021-04-23 2021-05-07 2021-05-07 2021-06-06 2021-07-11 2021-09-09 enabling environment Implementation Environment and Social Selection Impact Assessment (ESIA) INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Individual ET-MOSHE - ET-109517-CS- Creating national TVET IDA / 63350 Prior Consultant Open 16,800.00 0.00 Canceled 2019-04-15 2019-09-30 2019-06-03 2019-06-24 2019-07-29 2020-07-28 INDV / Procurement Specialist enabling environment Selection ET-MOSHE - ET-110227-CS- Individual Creating national TVET Under INDV / Financial Management IDA / 63350 Post Consultant Open 14,400.00 0.00 2019-04-12 2019-09-03 2019-05-31 2019-06-21 2019-07-26 2020-07-25 enabling environment Implementation Specialist Selection Individual ET-MOSHE - ET-110232-CS- Creating national TVET Under IDA / 63350 Post Consultant Open 30,000.00 0.00 2019-04-18 2019-10-04 2019-06-06 2019-06-27 2019-08-01 2020-07-31 INDV / Safeguard Specialist enabling environment Implementation Selection Individual ET-MOSHE - ET-110321-CS- Creating national TVET IDA / 63350 Post Consultant Open 40,000.00 25,529.04 Signed 2019-04-12 2019-10-20 2019-05-31 2020-01-01 2019-06-21 2020-01-01 2019-07-26 2020-01-01 2020-07-25 INDV / Project Coordinator enabling environment Selection Page 2 ET-MOSHE - ET-129298-NC- Individual Creating national TVET Under RFP / Recruitment of TVET IDA / 63350 Post Consultant Open 14,400.00 0.00 2019-09-05 2019-09-13 2019-10-24 2019-11-14 2019-12-19 2020-12-18 enabling environment Implementation Specialist at MoSHE Selection Strengthening selected ET-MOSHE - ET-151599-CS- Regional Flagship TVET Individual INDV / Recruitment of IDA / 63350 Institutes for high quality Prior Consultant Limited 18,000.00 0.00 Canceled 2019-12-23 2019-12-25 2019-12-28 2019-12-26 2020-01-18 2020-02-22 2020-08-20 Procurement Specialist for skills development in priority Selection EASTRIP-MoSHE sectors ET-MOSHE - ET-155038-CS- Individual CDS / Recruitment of Creating national TVET IDA / 63350 Prior Consultant Limited 21,000.00 2,115.44 Signed 2020-01-24 2020-01-23 2020-01-29 2020-01-23 2020-02-19 2020-03-17 2020-03-25 2020-04-01 2020-09-21 Procurement Specialist for enabling environment Selection MoSHE ET-MOSHE - ET-110229-CS- Individual Creating national TVET INDV / Monitoring & IDA / 63350 Post Consultant Open 14,400.00 0.00 Canceled 2019-04-12 2019-10-04 2019-05-31 2019-06-21 2019-07-26 2020-07-25 enabling environment Evaluation Specialist Selection Strengthening selected ET-MOSHE - ET-164193-CS- Regional Flagship TVET Individual CQS / Procurement Specialist IDA / 63350 Institutes for high quality Prior Consultant Limited 20,000.00 17,587.48 Signed 2020-03-20 2020-05-01 2020-03-25 2020-08-24 2020-04-15 2020-10-08 2020-05-20 2020-10-15 2020-11-16 #2 skills development in priority Selection sectors Strengthening selected Regional Flagship TVET Individual ET-MOSHE - ET-164194-CS- Under IDA / 63350 Institutes for high quality Post Consultant Limited 15,000.00 0.00 2020-03-23 2020-04-02 2020-03-28 2020-04-18 2020-05-23 2020-11-19 CQS / Finance Specialist # 2 Implementation skills development in priority Selection sectors Strengthening selected ET-MOSHE - ET-164195-CS- Regional Flagship TVET Individual CQS / Recruitment of IDA / 63350 Institutes for high quality Post Consultant Limited 20,000.00 15,366.96 Signed 2020-03-20 2020-03-23 2020-03-25 2020-05-15 2020-04-15 2020-11-11 2020-05-20 2020-10-12 2020-11-16 Monitoring and Evaluation skills development in priority Selection Specialist sectors Strengthening selected ET-MOSHE - ET-165716-CS- Regional Flagship TVET Individual Pending INDV / Gender Specialist IDA / 63350 Institutes for high quality Post Consultant Open 20,000.00 0.00 2020-03-27 2020-05-15 2020-06-05 2020-07-10 2021-01-06 Implementation Recruitment skills development in priority Selection sectors Strengthening selected ET-MOSHE - ET-172339-CS- Regional Flagship TVET Individual INDV / Contract Under IDA / 63350 Institutes for high quality Prior Consultant Open 22,000.00 0.00 2020-05-06 2020-05-11 2020-06-24 2020-07-15 2020-08-19 2021-02-15 Administration Officer Implementation skills development in priority Selection recruitment sectors ET-MOSHE - ET-173745-CS- Individual Creating national TVET Under INDV / Hiring an IDA / 63350 Post Consultant Limited 10,000.00 0.00 2020-05-20 2020-06-16 2020-05-25 2020-06-15 2020-07-20 2021-01-16 enabling environment Implementation Administrative Officer Selection ET-MOSHE - ET-201291-CS- INDV / Selection of Individual Individual Creating national TVET Consultant that supports in IDA / 63350 Post Consultant Limited 30,000.00 32,126.34 Signed 2020-11-05 2020-11-04 2020-11-10 2020-11-18 2020-11-25 2020-12-14 2020-12-06 2020-12-15 2021-06-04 enabling environment reviewing the College Building Selection Designs ET-MOSHE - ET-234036-CS- Individual INDV / TVET Specialist- Creating national TVET Under IDA / 63350 Post Consultant Limited 14,400.00 0.00 2021-05-16 2021-05-17 2021-05-21 2021-06-11 2021-07-16 2022-01-12 recruitment of TVET specialist enabling environment Implementation Selection for the NPCU ET-MOSHE - ET-234043-CS- Individual INDV / M&E Specialist- Creating national TVET Under IDA / 63350 Post Consultant Open 20,000.00 0.00 2021-05-12 2021-05-17 2021-06-30 2021-07-21 2021-08-25 2022-02-21 recruitment of M&E specialist enabling environment Implementation Selection at the NPCU level ET-MOSHE - ET-234849-CS- Individual Creating national TVET Under INDV / Procurement Officer IDA / 63350 Prior Consultant Open 21,000.00 0.00 2021-05-24 2021-06-03 2021-07-12 2021-08-02 2021-09-06 2022-09-01 enabling environment Implementation Selection Selection ET-MOSHE - ET-239009-CS- Individual INDV / Construction Finance Creating national TVET Pending IDA / 63350 Post Consultant Open 12,000.00 0.00 2021-06-18 2021-07-08 2021-07-11 2021-07-21 2021-07-26 Training Individual Consultant enabling environment Implementation Selection Selection Page 3 Proyecto de Gestión Integral de los Riesgos en el Sistema Agroindustrial Rural (GIRSAR) Monto – USD150 MILLONES PROCUREMENT Argentina : Integrated Risk Management in the Rural Agroindustrial System PLAN General Information Country: Argentina Bank’s Approval Date of the Original Procurement Plan: 2019-03-22 2021-05-14 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P162316 GPN Date: Project Name: Integrated Risk Management in the Rural Agroindustrial System Loan / Credit No: IBRD / 88670 Rural Change Unit - Ministry of Agriculture Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned AR-UCAR-186659-CW-RFB / Subproyecto "Prevención y control de incendios forestales de la Provincia de Mendoza" Pending Obras a realizar: Component 2 - Agricultural Single Stage - One 2022-02- IBRD / 88670 Post Request for Bids Open - National 4,963,200.00 0.00 Implementat 2021-05-03 2021-05-17 2021-06-28 2021-07-26 2021-08-30 1 central de coordinación risk mitigation investments Envelope 28 ion operativa, logística y de capacitación regional 2 bases de incendios 2 torres de observación 1 pista de aterrizaje AR-UCAR-216686-CW-RFB / Pending Subproyecto "Fortalecimiento Component 2 - Agricultural Single Stage - One 2022-02- IBRD / 88670 Post Request for Bids Open - National 832,160.00 0.00 Implementat 2021-05-03 2021-05-08 2021-06-19 2021-07-19 2021-08-23 Sanitario del rodeo bovino risk mitigation investments Envelope 19 ion provincial". Neuquén AR-UCAR-216690-CW-RFB / Subproyecto Pending Component 2 - Agricultural Single Stage - One 2022-02- "Reacondicionamiento y IBRD / 88670 Post Request for Bids Open - National 340,028.00 0.00 Implementat 2021-05-03 2021-05-08 2021-06-19 2021-07-19 2021-08-23 risk mitigation investments Envelope 19 Mejora del Sistema de Riego ion de Buta Ranquil". Neuquén AR-UCAR-216705-CW-RFB / Subproyecto "Readecuación de Pending Component 2 - Agricultural Single Stage - One 11,200,000.0 2022-05- caminos rurales: RP S/N IBRD / 88670 Prior Request for Bids Open - National 0.00 Implementat 2021-08-02 2021-08-07 2021-09-18 2021-10-18 2021-11-22 risk mitigation investments Envelope 0 21 Tramo RPN 32 (Seguí) – RPN ion 34". Entre Ríos. AR-UCAR-186648-CW-RFB / Subproyecto "Acueducto Pending Component 2 - Agricultural Single Stage - One 2021-06- Ganadero La Providencia, La IBRD / 88670 Post Request for Bids Open - National 5,848,818.00 0.00 Implementat 2020-08-24 2020-09-01 2020-10-13 2020-11-10 2020-12-15 risk mitigation investments Envelope 15 Ramada y Santa Ana" - ion Provincia de Córdoba AR-UCAR-216721-CW-RFB / Pending Subproyecto "Mejora de la red Component 2 - Agricultural Single Stage - One 2022-06- IBRD / 88670 Post Request for Bids Open - National 2,955,039.00 0.00 Implementat 2021-09-06 2021-09-11 2021-10-23 2021-11-22 2021-12-27 de riego del Valle de Jáchal". risk mitigation investments Envelope 25 ion San Juan. AR-UCAR-216723-CW-RFB / Subproyecto "Sistema Pending Component 2 - Agricultural Single Stage - One 2022-06- Provincial de Información Para IBRD / 88670 Post Request for Bids Open - National 335,000.00 0.00 Implementat 2021-09-06 2021-09-11 2021-10-23 2021-11-22 2021-12-27 risk mitigation investments Envelope 25 La Gestión del Riesgo ion Agrario". Neuquén. AR-UCAR-216712-CW-RFB / Subproyecto "Readecuación de Pending Component 2 - Agricultural Single Stage - One 2022-05- Los sistemas de Riego IBRD / 88670 Post Request for Bids Open - National 5,800,000.00 0.00 Implementat 2021-08-02 2021-08-07 2021-09-18 2021-10-18 2021-11-22 risk mitigation investments Envelope 21 superficiales de San Blas de ion Los Sauces". La Rioja. AR-UCAR-216700-CW-RFB / Subproyecto "Fortalecimiento de la Cadena Productiva de National Pequeños Productores Procurement Pending Component 2 - Agricultural Single Stage - One 2022-06- Hortícolas y Florícolas"- IBRD / 88670 Post Request for Bids Open - National Document - 1 2,470,146.00 0.00 Implementat 2021-09-06 2021-09-11 2021-10-23 2021-11-22 2021-12-27 risk mitigation investments Envelope 25 Construcción de invernaderos Envelope process ion y mejora de la (Non Bank-SPD) comercialización. Provincia de Jujuy. AR-UCAR-186653-CW-RFB / Subproyecto "Rehabilitación National de la dinámica hidráulica del Procurement Pending subsistema de la Cuenca del Component 2 - Agricultural Single Stage - One 2022-02- IBRD / 88670 Post Request for Bids Open - National Document - 1 9,726,000.00 0.00 Implementat 2021-05-03 2021-05-03 2021-06-14 2021-07-12 2021-08-16 Arroyo Baí" - Readecuación risk mitigation investments Envelope 14 Envelope process ion de los escurrimientos de la (Non Bank-SPD) Cuenca del Arroyo Baí - Provincia de Corrientes AR-UCAR-216698-CW-RFB / Subproyecto "Desarrollo National Ganadero de la Provincia de Procurement Pending Jujuy (Etapa I)". Mejoramiento Component 2 - Agricultural Single Stage - One 2022-05- IBRD / 88670 Post Request for Bids Open - National Document - 1 2,700,000.00 0.00 Implementat 2021-08-02 2021-08-07 2021-09-18 2021-10-18 2021-11-22 en los sistemas productivos y risk mitigation investments Envelope 21 Envelope process ion la generación de nueva (Non Bank-SPD) estructura de faena . Provincia de Jujuy. AR-UCAR-216714-CW-RFB / Subproyecto "Rehabilitación de la dinámica hídrica de la National cuenca alta del Riachuelo: Procurement Pending Component 2 - Agricultural Single Stage - One 2022-05- subsistema de La Palmira" - IBRD / 88670 Post Request for Bids Open - National Document - 1 3,100,000.00 0.00 Implementat 2021-08-02 2021-08-07 2021-09-18 2021-10-18 2021-11-22 risk mitigation investments Envelope 21 Construcción de un sistema Envelope process ion de vertedero de excedentes (Non Bank-SPD) hídricos . Provincia de Corrientes. GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 1 AR-UCAR-94920-GO-DIR / Plataforma de Integración, Component 1 - Validación y publicación de IBRD / 88670 Strengthening agro-climatic Prior Direct Selection Direct 1,800,000.00 1,509,027.90 Signed 2019-04-15 2019-09-02 2019-04-20 2019-09-03 2019-05-25 2019-09-26 2021-05-14 Información information systems Agrometeorológica AR-UCAR-94928-GO-RFB / Component 1 - Adquisición de instrumentos y Single Stage - One IBRD / 88670 Strengthening agro-climatic Post Request for Bids Open - International 240,000.00 0.00 Canceled 2019-05-15 2019-05-20 2019-07-01 2019-07-31 2019-09-04 2020-03-02 emplazamiento de estaciones Envelope information systems meteorológicas AR-UCAR-94931-GO-RFB / Adquisición y Actualización Component 1 - Under Tecnológica (Hardware - Single Stage - One IBRD / 88670 Strengthening agro-climatic Post Request for Bids Open - National 150,000.00 0.00 Implementati 2020-09-10 2021-01-28 2020-09-17 2020-10-29 2020-11-26 2020-12-31 2021-07-01 Software) para Puesta en Envelope information systems on Producción. Convenio MFI - SMN - MAGyP AR-UCAR-186695-GO-DIR / Component 1 - Pending Repuestos Radares - IBRD / 88670 Strengthening agro-climatic Post Direct Selection Direct 230,000.00 0.00 Implementati 2021-03-20 2022-03-20 Convenio MAGyP - INTA information systems on AR-UCAR-216745-GO-RFB / Convenio CONAE - Component 1 - Pending Single Stage - One Adquisición de sistema de IBRD / 88670 Strengthening agro-climatic Post Request for Bids Open - National 614,000.00 0.00 Implementati 2021-02-05 2021-02-10 2021-03-24 2021-04-23 2021-05-28 2021-11-24 Envelope discos para almacenamiento information systems on de red de alta AR-UCAR-216747-GO-RFB / Convenio CONAE - Adquisición de un sistema de Component 1 - Pending antena para recepción y Single Stage - One IBRD / 88670 Strengthening agro-climatic Post Request for Bids Open - International 350,000.00 0.00 Implementati 2021-02-05 2021-02-10 2021-03-24 2021-04-23 2021-05-28 2021-11-24 adquisición de Envelope information systems on datos satelitales de observación de la tierra en banda L y X. AR-UCAR-216754-GO-RFB / Convenio MAGyP - INTA - Component 1 - Pending Adquisición de equipamiento Single Stage - One IBRD / 88670 Strengthening agro-climatic Post Request for Bids Open - National 110,000.00 0.00 Implementati 2021-05-03 2021-05-08 2021-06-19 2021-07-19 2021-08-23 2022-02-19 Informatico Sistema Back up / Envelope information systems on storage / procesamiento (Hardware y software) Component 3 - Agricultural AR-UCAR-216771-GO-RFQ / Pending Emergency Response Request for Single Stage - One Fortalecimiento Informático IBRD / 88670 Post Open - National 25,000.00 0.00 Implementati 2021-11-20 2022-01-15 2022-07-14 Financing and Transfer of Quotations Envelope MAGYP y Provincias (3.1.1.3) on Agroclimatic Risks AR-UCAR-224910-GO-RFB / Pending Component 2 - Agricultural Single Stage - One Ocho (8) Camionetas tipo pick IBRD / 88670 Post Request for Bids Open - National 320,000.00 0.00 Implementati 2021-05-03 2021-05-08 2021-06-19 2021-07-19 2021-08-23 2022-02-19 risk mitigation investments Envelope up doble cabina on AR-UCAR-226703-GO-RFB / Pending Component 2 - Agricultural Single Stage - One ELMI - Adquisición de IBRD / 88670 Post Request for Bids Open - National 212,000.00 0.00 Implementati 2021-07-01 2021-07-06 2021-08-17 2021-09-16 2021-10-21 2022-04-19 risk mitigation investments Envelope reservorios y parcelas on AR-UCAR-231943-GO-RFQ / Component 1 - Pending Request for Single Stage - One Placas de telemetría 3G - IBRD / 88670 Strengthening agro-climatic Post Open - National 49,368.00 0.00 Implementati 2021-05-15 2021-07-10 2022-01-06 Quotations Envelope Bolsa de Cereales Entre Ríos information systems on AR-UCAR-231949-GO-RFB / Component 1 - Pending Estaciones Meteorológicas Single Stage - One IBRD / 88670 Strengthening agro-climatic Post Request for Bids Open - National 140,000.00 0.00 Implementati 2021-05-10 2021-05-15 2021-06-26 2021-07-26 2021-08-30 2022-02-26 Automáticas (EMA) - provincia Envelope information systems on de Formosa AR-UCAR-186660-GO-RFQ / Adquisición de instrumentos Component 1 - Pending para estaciones Single Stage - One IBRD / 88670 Strengthening agro-climatic Post Request for Bids Open - National 326,000.00 0.00 Implementati 2021-06-14 2021-06-19 2021-07-31 2021-08-30 2021-10-04 2022-04-02 meteorológicas Envelope information systems on convencionales - Convenio MAGyP - INTA AR-UCAR-240328-GO-RFQ / Equipamiento informático - Component 1 - Pending Request for Single Stage - One Fortalecimiento interno IBRD / 88670 Strengthening agro-climatic Post Open - National 20,000.00 0.00 Implementati 2021-07-06 2021-08-31 2022-02-27 Quotations Envelope Oficina de Riesgo information systems on Agropecuario AR-UCAR-186688-GO-DIR / Component 1 - Pending Actualización Antenas. IBRD / 88670 Strengthening agro-climatic Post Direct Selection Direct 570,000.00 0.00 Implementati 2020-09-09 2020-09-16 2021-10-04 2022-05-23 Convenio MAGyP - INTA information systems on NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual AR-UCAR-216769-CS-CQS / Contratación de firma consultora /universidad Component 3 - Agricultural Consultant especialista en programación Emergency Response Pending IBRD / 88670 Post Qualification Open - National 21,500.00 0.00 2021-04-01 2021-04-22 2021-06-05 2021-07-05 2021-08-09 2022-02-05 web para plataforma de carga Financing and Transfer of Implementation Selection y consulta base histórica de Agroclimatic Risks Emergencia Agropecuaria.3.1.1.1 y 3.1.1.2 Page 2 AR-UCAR-216775-CS-CQS / Contratación de firma consultora especialista en programación de sistemas Component 3 - Agricultural para la publicación web de Consultant Emergency Response Pending herramientas de monitoreo y IBRD / 88670 Post Qualification Open - National 40,000.00 0.00 2021-04-05 2021-04-26 2021-06-09 2021-07-09 2021-08-13 2022-02-09 Financing and Transfer of Implementation gestión de riesgos, desarrollo Selection Agroclimatic Risks y publicación de Índices climáticos e informes de estudios técnicos. 3.1.6.1 y 3.1.6.2. AR-UCAR-216770-CS-CQS / Contratación de firma Component 3 - Agricultural Consultant consultora/universidad para Emergency Response Pending IBRD / 88670 Post Qualification Open - National 50,000.00 0.00 2021-04-06 2021-04-27 2021-06-10 2021-07-10 2021-08-14 2022-02-10 diseño de estrategia de Financing and Transfer of Implementation Selection financiamiento de riesgos. Agroclimatic Risks 3.1.5.1 AR-UCAR-226701-CS-CQS / Consultant Component 2 - Agricultural Pending ELMI - Desarrollo de una app IBRD / 88670 Post Qualification Open - National 10,000.00 0.00 2021-05-03 2021-05-24 2021-07-07 2021-08-06 2021-09-10 2022-03-09 risk mitigation investments Implementation en gestión del conocimiento Selection INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual AR-UCAR-186662-CS-INDV Individual / Contratación Consultor/a Component 2 - Agricultural Pending IBRD / 88670 Post Consultant Open 9,285.70 0.00 2020-08-17 2020-10-05 2020-10-26 2020-11-30 2021-05-29 Especialista en Ingeniería Civil risk mitigation investments Implementation Selection para Formulación de Proyectos AR-UCAR-186673-CS-INDV / Contratación Consultor/a Individual Component 2 - Agricultural Pending Especialista en Formulación y IBRD / 88670 Post Consultant Open 7,000.00 0.00 2020-08-17 2020-10-05 2020-10-26 2020-11-30 2021-05-29 risk mitigation investments Implementation Evaluación Económica de Selection Proyectos AR-UCAR-186678-CS-INDV Individual / Contratación Consultor/a Component 2 - Agricultural Pending IBRD / 88670 Post Consultant Open 9,285.70 0.00 2020-08-17 2020-10-05 2020-10-26 2020-11-30 2021-05-29 especialista ambiental para risk mitigation investments Implementation Selection formulación de proyectos AR-UCAR-186680-CS-INDV / Contratación Consultor/a Individual Component 2 - Agricultural Pending especialista en afectación de IBRD / 88670 Post Consultant Open 6,964.30 0.00 2020-08-17 2020-10-05 2020-10-26 2020-11-30 2021-05-29 risk mitigation investments Implementation activos para formulación de Selection proyecto AR-UCAR-186681-CS-INDV / Contratación Consultor/a Individual Component 2 - Agricultural Pending especialista en pueblos IBRD / 88670 Post Consultant Open 6,964.30 0.00 2020-08-17 2020-10-05 2020-10-26 2020-11-30 2021-05-29 risk mitigation investments Implementation indígenas para formulación de Selection proyecto AR-UCAR-186676-CS-INDV / Contratación 3 Individual Consultores/as especialistas Component 2 - Agricultural Pending IBRD / 88670 Post Consultant Open 36,000.00 0.00 2020-08-17 2020-10-05 2020-10-26 2020-11-30 2021-05-29 en conectividad rural y risk mitigation investments Implementation Selection sistemas de información para formulación de proyectos Component 3 - Agricultural Individual AR-UCAR-186683-CS-INDV Emergency Response IBRD / 88670 Post Consultant Open 5,285.70 0.00 Canceled 2020-08-17 2020-10-05 2020-10-26 2020-11-30 2021-05-29 / Contratración de Data Entry Financing and Transfer of Selection Agroclimatic Risks AR-UCAR-186685-CS-INDV / Contratación de 4 Component 3 - Agricultural Individual Especialistas, Master o Doctor Emergency Response IBRD / 88670 Post Consultant Open 59,214.30 0.00 Canceled 2020-08-17 2020-10-05 2020-10-26 2020-11-30 2021-05-29 en economía agropecuaria y Financing and Transfer of Selection finanzas públicas.- Buenos Agroclimatic Risks Aires AR-UCAR-186687-CS-CDS / Buenos Aires- Comité Técnico Component 2 - Agricultural Pending de Evaluación de IBRD / 88670 Post Direct Selection Direct 74,000.00 0.00 2021-04-01 2021-04-11 2021-06-15 2021-12-12 risk mitigation investments Implementation Subproyectos - Contrato Servicios de Consultoría IICA AR-UCAR-216774-CS-INDV Component 3 - Agricultural / Especialista en economía Individual Emergency Response Pending agraria para estudio de IBRD / 88670 Post Consultant Open 6,224.00 0.00 2021-05-03 2021-06-21 2021-07-12 2021-08-16 2022-02-12 Financing and Transfer of Implementation prefactibilidad para seguro en Selection Agroclimatic Risks Ganadería AR-UCAR-216778-CS-INDV / Contratación de un Component 3 - Agricultural Individual consultor/ra especialista en Emergency Response Pending IBRD / 88670 Post Consultant Open 15,000.00 0.00 2021-04-01 2021-05-20 2021-06-10 2021-07-15 2022-01-11 seguros para adecuación Financing and Transfer of Implementation Selection póliza seguro horticola. Agroclimatic Risks 3.2.2.2. AR-UCAR-216779-CS-INDV / Contratación de un Component 3 - Agricultural Individual consultor/ra especialista en Emergency Response Pending IBRD / 88670 Post Consultant Open 15,000.00 0.00 2021-04-01 2021-05-20 2021-06-10 2021-07-15 2022-01-11 abogacía y/o administración Financing and Transfer of Implementation Selection publica para proceso de Agroclimatic Risks adquisición seguro. 3.2.2.3 AR-UCAR-216780-CS-INDV / Contratación de 2 consultores/as profesionales Component 3 - Agricultural en agronomía, economía Individual Emergency Response Pending agraria o actuarios con IBRD / 88670 Post Consultant Open 30,000.00 0.00 2021-04-01 2021-05-20 2021-06-10 2021-07-15 2022-01-11 Financing and Transfer of Implementation conocimientos y experiencia Selection Agroclimatic Risks en seguros agropecuarios. Estudio de Factibilidad seguro sequía en Santa Fé. 3.2.3.1 Page 3 AR-UCAR-216761-CS-INDV / Convenio INTA - Component 1 - Individual Contratación de 1 Pending IBRD / 88670 Strengthening agro-climatic Post Consultant Open 27,000.00 0.00 2021-04-30 2021-06-18 2021-07-09 2021-08-13 2022-02-09 Especialista, Master o Doctor Implementation information systems Selection en agronomia, SIG, Teledetección.- Buenos Aires AR-UCAR-216756-CS-INDV Component 1 - Individual / Convenio INTA - Pending IBRD / 88670 Strengthening agro-climatic Post Consultant Open 72,000.00 0.00 2021-04-30 2021-06-18 2021-07-09 2021-08-13 2022-02-09 Contratración de 2 Implementation information systems Selection Programadores AR-UCAR-216760-CS-INDV Component 1 - Individual / Convenio INTA - Pending IBRD / 88670 Strengthening agro-climatic Post Consultant Open 36,000.00 0.00 2021-04-30 2021-06-18 2021-07-09 2021-08-13 2022-02-09 Contratración de 1 Ing. Implementation information systems Selection Electrónico AR-UCAR-186682-CS-INDV Component 3 - Agricultural Individual / Contratración de 2 Emergency Response Pending IBRD / 88670 Post Consultant Open 14,857.10 0.00 2021-04-01 2021-05-20 2021-06-10 2021-07-15 2022-01-11 Programador web Symfony Financing and Transfer of Implementation Selection SENIOR (Front-Backend) Agroclimatic Risks Component 3 - Agricultural AR-UCAR-216772-CS-INDV Individual Emergency Response Pending / Especialista en economía IBRD / 88670 Post Consultant Open 7,780.00 0.00 2021-05-03 2021-06-21 2021-07-12 2021-08-16 2022-02-12 Financing and Transfer of Implementation agraria/seguros Selection Agroclimatic Risks Component 3 - Agricultural AR-UCAR-216776-CS-INDV Individual Emergency Response Pending / Contratación de un actuario. IBRD / 88670 Post Consultant Open 15,000.00 0.00 2021-06-01 2021-07-20 2021-08-10 2021-09-14 2022-03-13 Financing and Transfer of Implementation 3.2.1.1 Selection Agroclimatic Risks AR-UCAR-216762-CS-INDV / Especialista SIG- Teledetección con formación Component 1 - Individual en geografía o ciencias Pending IBRD / 88670 Strengthening agro-climatic Post Consultant Open 6,224.00 0.00 2021-06-01 2021-07-20 2021-08-10 2021-09-14 2022-03-13 ambientales/sociales para Implementation information systems Selection monitoreo de eventos extremos con impacto agroproductivo AR-UCAR-216763-CS-INDV / Convenio INTA - Component 1 - Individual Pending Contratración de IBRD / 88670 Strengthening agro-climatic Post Consultant Open 24,000.00 0.00 2021-04-30 2021-06-18 2021-07-09 2021-08-13 2022-02-09 Implementation Administrador datos - Data information systems Selection Entry AR-UCAR-225069-CS-INDV Individual / Contratación de cuatro (4) Component 2 - Agricultural Pending IBRD / 88670 Post Consultant Open 29,045.00 0.00 2021-04-01 2021-05-20 2021-06-10 2021-07-15 2022-01-11 Consultores Especialistas en risk mitigation investments Implementation Selection Riego AR-UCAR-226535-CS-INDV / ELMI - 6 consultores/as en Individual Ingeniería Agrónoma o Component 2 - Agricultural Pending IBRD / 88670 Post Consultant Open 37,000.00 0.00 2021-04-01 2021-05-20 2021-06-10 2021-07-15 2022-01-11 Técnicos/as Universitarios/as risk mitigation investments Implementation Selection en Sistemas de Riego o carreras afines AR-UCAR-227311-CS-INDV Component 1 - Individual / Especialista en Ciencias Pending IBRD / 88670 Strengthening agro-climatic Post Consultant Open 8,714.00 0.00 2021-06-01 2021-07-20 2021-08-10 2021-09-14 2022-03-13 Ambientales-Cambio Implementation information systems Selection climático AR-UCAR-227312-CS-INDV Component 1 - Individual / Especialista en hidrología Pending IBRD / 88670 Strengthening agro-climatic Post Consultant Open 3,112.00 0.00 2021-04-01 2021-05-20 2021-06-10 2021-07-15 2022-01-11 para cálculo de precipitación Implementation information systems Selection por satélites AR-UCAR-227313-CS-INDV / Especialista informático con Component 1 - Individual conocimiento agropecuario Pending IBRD / 88670 Strengthening agro-climatic Post Consultant Open 6,224.00 0.00 2021-06-01 2021-07-20 2021-08-10 2021-09-14 2022-03-13 para estudio de prefactibilidad Implementation information systems Selection de Sistema de datos de daños y pérdidas AR-UCAR-227314-CS-INDV Individual Component 2 - Agricultural Pending / Cuatro (4) Consultores IBRD / 88670 Post Consultant Open 29,045.00 0.00 2021-05-03 2021-06-21 2021-07-12 2021-08-16 2022-02-12 risk mitigation investments Implementation Especialistas en Riego Selection AR-UCAR-227315-CS-INDV / Dos (2) Consultores/as Individual Component 2 - Agricultural Pending Economistas o idóneos IBRD / 88670 Post Consultant Open 19,087.00 0.00 2021-04-01 2021-05-20 2021-06-10 2021-07-15 2022-01-11 risk mitigation investments Implementation especialistas en evaluación Selection económica de proyectos AR-UCAR-227316-CS-INDV / Dos (2) Consultores/as Individual Component 2 - Agricultural Pending Especialistas en Formulación IBRD / 88670 Post Consultant Open 19,087.00 0.00 2021-04-01 2021-05-20 2021-06-10 2021-07-15 2022-01-11 risk mitigation investments Implementation de proyectos con Selection financiamiento internacional AR-UCAR-227318-CS-INDV / Cuatro (4) Consultores/as Individual Component 2 - Agricultural Pending Especialistas en Ingeniería IBRD / 88670 Post Consultant Open 38,174.00 0.00 2021-04-01 2021-05-20 2021-06-10 2021-07-15 2022-01-11 risk mitigation investments Implementation Civil para Formulación de Selection Proyectos AR-UCAR-227319-CS-INDV / Cuatro (4) Consultores/as Individual Especialistas Socio- Component 2 - Agricultural Pending IBRD / 88670 Post Consultant Open 38,174.00 0.00 2021-04-01 2021-05-20 2021-06-10 2021-07-15 2022-01-11 ambientales para la risk mitigation investments Implementation Selection Formulación de Proyectos con financiamiento internacional AR-UCAR-227320-CS-INDV / Dos (2) Consultores/as en Individual Component 2 - Agricultural Pending Ingeniaría Agrónoma o IBRD / 88670 Post Consultant Open 19,087.00 0.00 2021-04-01 2021-05-20 2021-06-10 2021-07-15 2022-01-11 risk mitigation investments Implementation especialistas idóneos en Selection producción rural Page 4 AR-UCAR-216777-CS-INDV / Contratación de dos Component 3 - Agricultural Individual consultores/as agronomos Emergency Response Pending IBRD / 88670 Post Consultant Open 20,000.00 0.00 2021-05-01 2021-06-19 2021-07-10 2021-08-14 2022-02-10 especialistas en horticultura Financing and Transfer of Implementation Selection para relevamiento sector Agroclimatic Risks horticola BsAs (3.2.2.1) AR-UCAR-226536-NC-DIR / ELMI - Diplomatura en Riego y Component 2 - Agricultural Pending IBRD / 88670 Post Direct Selection Direct 30,000.00 0.00 2021-05-03 2021-05-13 2021-07-17 2022-01-13 Drenaje. Universidad Nacional risk mitigation investments Implementation de Cuyo AR-UCAR-226709-CS-CDS / Convenio CONAE - Component 1 - Contratación de firma Pending IBRD / 88670 Strengthening agro-climatic Prior Direct Selection Direct 1,325,000.00 0.00 2021-06-14 2021-06-24 2021-08-28 2022-02-24 consultora para desarrollo de Implementation information systems productos, distribución y capacitación AR-UCAR-216781-CS-INDV / Contratación de consultor Component 1 - Individual Pending Especialista en Comunicación IBRD / 88670 Strengthening agro-climatic Post Consultant Open 10,000.00 0.00 2021-06-28 2021-08-16 2021-09-06 2021-10-11 2022-04-09 Implementation para difusión de acciones y information systems Selection alcances del Programa AR-UCAR-240331-CS-INDV / Contratación de Analista Component 1 - Individual Funcional para los sistemas Pending IBRD / 88670 Strengthening agro-climatic Post Consultant Open 7,000.00 0.00 2021-06-28 2021-08-16 2021-09-06 2021-10-11 2022-04-09 existentes en sitio web de la Implementation information systems Selection Oficina de Riesgo Agropecuario (ORA) Page 5 PROCUREMENT PLAN (Textual Part) Project information: Rwanda Renewable Energy Fund (REF) Project (P160699) Project Implementation agency: Development Bank of Rwanda (BRD) Date of the Procurement Plan: January 22, 2018 Period covered by this Procurement Plan: January 2018 – December 2019 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. All Consultancy Services shall be procured following Procurement Regulations and Bank’s SPDs. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Public Procurement Law of Rwanda, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions: In accordance with paragraph 5.3 of the Procurement Regulations, the request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. The form of the Letter of Acceptance is attached in Appendix 1. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables: Not Applicable. Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables: Not Applicable. Thresholds*, Procurement Methods, and Prior Review Goods, Works, and Non-Consulting Services Method of Procurement Thresholds for Method (US$ equivalent) Open International (Goods) Equal to or more than US$ 2 million Open National (Goods) – Open < US$2 million and > US$ 2,500 Tender as per Ministerial Order 2014 RFQ (Goods) Less than US$ 2,500 or as stipulated in Rwanda Procurement Regulations Open International (Works) Equal to or more than US$ 10 million Open National (Works) - Open Less than US$ 10 million Tender as per Ministerial Order 2014 RFQ (works) Less than US$ 2,500 or as stipulated in Rwanda Procurement Regulations Open International (Non-consulting Equal to or More than US$ 2 million Services) Open National (Non-consulting Less than US$ 2 million Services) - Open Tender as per Ministerial Order 2014 Direct Contracting No threshold; meet requirements of Bank’s Procurement Regulations (Special procurement arrangements like direct contracting, use of SOEs, UN Agencies, third party monitors, local NGOs, Force Account, servants need, results based arrangements. It is not expected that there will need for prequalification in the procurement arrangements under Rwanda Pilot Program for Climate Resilience project) Thresholds for selection of consultant Prior Review Thresholds: The details of the Procurement review / oversight are defined in the Annex II of the Regulations for borrowers. The following would be subject to Prior review of the Bank regardless of the Method of selection: (a). Consulting Firm: First procurement under the project irrespective of value and all procurements estimated to cost more than US$ 1 million. (b). Individual Consultant: all procurements estimated to cost more than US$ 0.3 million The short list may consist of all National consultants in case the estimated cost is less than US$ 200,000 per contract. PROCUREMENT Rwanda : Renewable Energy Fund PLAN General Information Country: Rwanda Bank’s Approval Date of the Original Procurement Plan: 2018-01-23 2021-05-25 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P160699 GPN Date: Project Name: Renewable Energy Fund Loan / Credit No: TF / A4990 Development Bank of Rwanda Ltd Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Technical Assistance, RW-BRD-44062-CS-QCBS / Quality And Cost- TF / A4990 Capacity Building, and Project Prior Open - International 330,000.00 277,750.00 Signed 2018-01-29 2018-02-02 2018-02-19 2018-02-20 2018-04-04 2018-08-14 2018-05-02 2018-09-14 2018-06-01 2019-02-14 2018-07-06 2019-06-19 2018-08-10 2019-06-20 2019-08-10 Capacity building of SACCOs Based Selection Implementation Support Technical Assistance, RW-BRD-47798-CS-CQS / Quality And Cost- TF / A4990 Capacity Building, and Project Prior Open - International 300,000.00 252,947.49 Signed 2018-03-22 2018-04-17 2018-04-12 2018-05-14 2018-05-26 2018-12-07 2018-06-23 2019-01-10 2018-07-23 2019-04-18 2018-08-27 2019-07-12 2018-10-01 2019-07-03 2019-10-01 Public awareness campain Based Selection Implementation Support RW-BRD-80709-CS-QCBS / Developping a Monitoring, Technical Assistance, Quality And Cost- Evaluation and Learning plan TF / A4990 Capacity Building, and Project Post Open - National 55,000.00 44,190.00 Completed 2018-10-31 2018-10-25 2018-11-21 2019-01-04 2019-02-27 2019-02-01 2019-03-08 2019-03-03 2019-04-09 2019-04-07 2019-04-26 2019-05-12 2019-06-25 2019-08-10 2020-04-28 Based Selection and capacity building for the Implementation Support REF INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Technical Assistance, Individual RW-BRD-44081-CS-INDV / TF / A4990 Capacity Building, and Project Prior Consultant Open 120,000.00 189,240.00 Signed 2018-01-29 2018-02-02 2018-03-19 2018-04-09 2018-12-11 2018-05-14 2019-01-03 2019-05-09 Senior Financial Advisor Implementation Support Selection RW-BRD-44085-CS-INDV / Technical Assistance, Individual Social and Environmental TF / A4990 Capacity Building, and Project Post Consultant Open 5,000.00 0.00 Canceled 2018-01-29 2018-01-31 2018-03-19 2018-04-09 2018-05-14 2018-11-10 Specialist Implementation Support Selection RW-BRD-52554-CS-INDV / Technical Assistance, Individual Recruitment of Investment TF / A4990 Capacity Building, and Project Post Consultant Open 27,000.00 2,504.08 Signed 2018-03-07 2018-03-28 2018-04-25 2019-04-10 2018-05-16 2019-04-11 2018-06-20 2019-04-11 2019-06-20 Officer Implementation Support Selection Technical Assistance, Individual RW-BRD-52607-CS-INDV / TF / A4990 Capacity Building, and Project Post Consultant Open 27,000.00 29,946.99 Signed 2018-03-07 2018-04-04 2018-04-25 2018-03-12 2018-05-16 2018-03-12 2018-06-20 2018-04-25 2019-06-20 Contract Drafting Officer Implementation Support Selection Technical Assistance, Individual RW-BRD-52610-CS-INDV / TF / A4990 Capacity Building, and Project Post Consultant Open 27,000.00 25,992.97 Signed 2018-03-07 2018-03-28 2018-04-25 2018-06-07 2018-05-16 2018-06-20 2018-06-20 2018-07-09 2019-06-20 Accountant Implementation Support Selection Technical Assistance, Individual RW-BRD-52616-CS-INDV / TF / A4990 Capacity Building, and Project Post Consultant Open 27,000.00 26,659.14 Signed 2018-03-07 2018-04-04 2018-04-25 2018-07-09 2018-05-16 2018-10-25 2018-06-20 2018-11-01 2019-06-20 Financial Reporting Officer Implementation Support Selection Technical Assistance, Individual RW-BRD-52618-CS-INDV / TF / A4990 Capacity Building, and Project Post Consultant Open 27,000.00 1,419.87 Signed 2018-03-07 2019-10-11 2018-04-25 2019-04-05 2018-05-16 2019-04-05 2018-06-20 2019-05-02 2019-06-20 Credit Risk Officer Implementation Support Selection Technical Assistance, Individual RW-BRD-52650-CS-INDV / TF / A4990 Capacity Building, and Project Post Consultant Limited 1,666.00 1.81 Completed 2018-06-28 2018-05-04 2018-07-03 2018-05-04 2018-07-24 2018-08-02 2018-08-28 2018-09-19 2019-08-28 2020-09-18 Mini-Technical Specialist 1 Implementation Support Selection Technical Assistance, Individual RW-BRD-54310-CS-INDV / TF / A4990 Capacity Building, and Project Post Consultant Open 1,666.00 1,813.27 Signed 2018-03-15 2018-05-04 2018-05-03 2018-10-02 2018-05-24 2018-08-02 2018-06-28 2018-09-19 2019-06-28 Mini grid technical Expert 2 Implementation Support Selection RW-BRD-52602-CS-INDV / Technical Assistance, Individual Recrutment of Technology TF / A4990 Capacity Building, and Project Prior Consultant Open 60,000.00 2,485.55 Signed 2018-03-27 2018-04-03 2018-05-15 2018-06-05 2018-11-21 2018-07-10 2018-11-29 2019-07-10 Officer Implementation Support Selection RW-BRD-72105-CS-INDV / Technical Assistance, Individual Hiring an Environmental and TF / A4990 Capacity Building, and Project Post Consultant Limited 2,500.00 2,756.20 Signed 2018-08-13 2018-08-28 2018-08-18 2018-09-05 2018-09-08 2018-09-12 2018-10-13 2018-09-05 2019-10-13 Social Safeguards Specialist 2 Implementation Support Selection Page 1 RW-BRD-72106-CS-INDV / Technical Assistance, Individual Hiring an Environmental and TF / A4990 Capacity Building, and Project Post Consultant Limited 2,500.00 2,756.20 Completed 2018-08-13 2018-08-28 2018-08-18 2018-09-05 2018-09-08 2019-04-29 2018-10-13 2018-09-05 2019-10-13 2020-10-05 Social Safeguards Implementation Support Selection RW-BRD-72235-CS-CDS / Technical Assistance, Hiring a consultant to TF / A4990 Capacity Building, and Project Post Direct Selection Direct 40,000.00 0.00 Canceled 2018-08-13 2018-08-23 2018-10-27 2018-12-11 appraise banks Implementation Support RW-BRD-72235-CS-CDS-2 / Technical Assistance, Hiring a consultant to TF / A4990 Capacity Building, and Project Post Direct Selection Direct 40,000.00 28,588.00 Completed 2019-01-31 2019-01-01 2019-01-31 2019-01-15 2019-02-05 2019-02-04 2019-03-07 2020-02-28 appraise banks Implementation Support RW-BRD-136112-CS-CDS / Technical Assistance, CREATION OF ORACLE ERP – TF / A4990 Capacity Building, and Project Post Direct Selection Direct 28,000.00 28,000.00 Signed 2019-10-09 2019-10-21 2019-10-19 2019-10-23 2019-11-18 2020-03-05 2020-02-16 FINANCE FOR REF PROJECT Implementation Support RW-BRD-234551-CS-INDV / Technical Assistance, Individual Hiring a Senior financial Under TF / A4990 Capacity Building, and Project Post Consultant Open 117,600.00 0.00 2021-05-17 2021-05-25 2021-06-26 2021-07-10 2021-08-07 2022-08-07 advisor to support the REF Implementation Implementation Support Selection project RW-BRD-234553-CS-INDV / Hiring an expert to support Technical Assistance, Individual coordination of verification Under TF / A4990 Capacity Building, and Project Post Consultant Open 135,240.00 0.00 2021-08-09 2021-05-28 2021-08-30 2021-09-20 2021-10-18 2022-10-18 and facilitate knowledge Implementation Implementation Support Selection transfer from propoor to window 5 staff. RW-BRD-234555-CS-INDV / Technical Assistance, Individual Under Hiring the REF technology TF / A4990 Capacity Building, and Project Post Consultant Open 30,250.00 0.00 2021-05-30 2021-05-26 2021-07-09 2021-07-23 2021-08-20 2021-09-25 Implementation officer Implementation Support Selection Technical Assistance, Individual RW-BRD-234557-CS-INDV / Under TF / A4990 Capacity Building, and Project Post Consultant Open 30,250.00 0.00 2021-05-30 2021-05-26 2021-07-09 2021-07-23 2021-08-20 2022-08-20 Hiring the REF M&E officer Implementation Implementation Support Selection RW-BRD-234558-CS-INDV / Technical Assistance, Individual Under Hiring the REF investment TF / A4990 Capacity Building, and Project Post Consultant Open 30,250.00 0.00 2021-06-30 2021-05-26 2021-08-09 2021-08-23 2021-09-20 2022-09-20 Implementation officer Implementation Support Selection RW-BRD-234560-CS-INDV / Technical Assistance, Individual Under Hiring of REF investment TF / A4990 Capacity Building, and Project Post Consultant Open 30,250.00 0.00 2021-06-30 2021-05-26 2021-08-02 2021-08-23 2021-09-20 2022-09-20 Implementation officer for window 5 - 1 Implementation Support Selection RW-BRD-234561-CS-INDV / Technical Assistance, Individual Under Hiring of REF investment TF / A4990 Capacity Building, and Project Post Consultant Open 30,250.00 0.00 2021-06-30 2021-05-26 2021-08-02 2021-08-23 2021-09-20 2022-09-20 Implementation officer for window 5 -2 Implementation Support Selection Technical Assistance, Individual RW-BRD-54319-CS-INDV / TF / A4990 Capacity Building, and Project Post Consultant Open 1,668.00 0.00 Canceled 2018-03-15 2018-05-03 2018-05-24 2018-06-28 2019-06-28 Mini grid technical expert 3 Implementation Support Selection RW-BRD-237743-CS-CDS / Hiring a consultant firm to Technical Assistance, Pending provide maintenance and TF / A4990 Capacity Building, and Project Post Direct Selection Direct 47,040.00 0.00 2021-08-19 2021-08-29 2021-10-17 2022-10-17 Implementation upgrade services of the REF Implementation Support MEL Page 2 Procurement Plan I. General 1. Project Information Country: Tanzania Project Name: Resilient Natural Resources Management for Growth Project Project ID: P150523 2. Project Implementation Agency: Ministry of Natural Resources and Tourism (MNRT) Tanzania National Parks (TANAPA) Tanzania Wildlife Management Authority (TAWA) National Irrigation Commission (NIrC) Rufiji Basin Water Board (RBWB) 3. Date of the Procurement Plan: June 2017 4. Period Covered by this Procurement Plan: First 18 Months Procurement Plan II. Thresholds for Prior Review, Procurement Approaches and Methods A. Goods, Works and Non-Consulting Services Procurement Approaches and Methods (US$ Prior Review millions) Category (US$ Open Open Request for millions) International National Quotation (RfQ) Works ≥5 ≥ 15.0 < 15 < 0.2 Goods, IT, and non- ≥1.5 ≥5 <5 < 0.1 consulting services B. Consulting Services Category Prior Review Short List of National Consultants (US$ (US$ million) millions) Consulting Engineering and Services Construction Supervision Consultants ≥ 0.5 <0.3 < 0.3 (Firms) Individual ≥ 0.2 NA. NA. 1 Consultants [Overall Project Procurement Risk is HIGH] Notes: Terms of Reference: Terms of Reference for all contracts shall be cleared by the Bank, regardless of whether the assignment is for prior or post review. Advertisement: Consultancy Service for Contracts estimated to cost US$ 300,000 equivalent and above per contract shall be advertised in UNDB online in addition to advertising in National News Paper(s) of wide circulation and/or Regional News Paper(s). 2 III. Packages for Goods, Works and Non-Consulting Services Sr./ No Contract Description Estimate Review Market Selection Evaluation Procurement Prequa Domesti Expected Expected d Cost by Bank Approach Method Options Process: lificatio c date of date of (US$) (Prior/Pos (Open- (RFP, RFB, (BAFO, (Single/Multipl n Preferen bid/ Contract t) National/ RFQ, DS Rated e Stages; (Yes/ ce proposal Signature International etc.) Criteria One/Two No) (Yes/No) opening Limited etc.) etc.) Envelopes etc) Goods Works Non-Consulting Services 3 I. Packages for Consulting Services Sr. No Contract Description Estimated Review Market Selection Shortlisti Expected date of Expected date Cost (US$) by Bank Approach Method ng bid/ proposal of Contract (Prior/Pos (Open- (QCBS, FBBS, (Yes/ No) opening Signature t) National/ LCBS, QBS, International CQS, DS etc.) Limited etc.) 4 PROCUREMENT Tanzania : Tanzania: Resilient Natural Resource Management for Tourism and Growth PLAN General Information Country: Tanzania Bank’s Approval Date of the Original Procurement Plan: 2017-06-07 2021-05-17 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P150523 GPN Date: 2018-08-17 Project Name: Tanzania: Resilient Natural Resource Management for Tourism and Growth Loan / Credit No: IDA / Q9740, IDA / 61430 M Executing Agency(ies): inistry of Natural Resources and Tourism WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 4. Project management, TZ-MNRT-16999-GO-RFQ / institutional strengthening, Request for Single Stage - One Procurement of Printers and IDA / Q9740 quality assurance and Post Open - National 20,000.00 7,222.94 Completed 2017-06-11 2017-07-09 2019-04-10 2018-01-05 2019-05-01 Quotations Envelope Computers control, and monitoring and evaluation 4. Project management, TZ-MNRT-40866-GO-RFQ / institutional strengthening, Request for Single Stage - One Supply of IT Equipment for IDA / 61430 quality assurance and Post Open - National 80,000.00 0.00 Canceled 2018-02-11 2018-04-08 2018-10-05 Quotations Envelope PCU and M&E control, and monitoring and evaluation 4. Project management, TZ-MNRT-40876-GO-DIR / institutional strengthening, License for financial IDA / 61430 quality assurance and Post Direct Selection Direct 15,000.00 0.00 Canceled 2018-01-28 2018-02-02 2018-03-09 2018-09-05 management control, and monitoring and evaluation TZ-MNRT-82691-GO-UN / 4. Project management, Procurement of Motor institutional strengthening, UN Agencies Vehicles for the Project IDA / 61430 quality assurance and Prior Direct 629,024.00 339,714.00 Signed 2018-10-25 2019-11-25 2018-10-30 2021-04-09 2018-12-04 2020-08-05 2019-06-02 (Direct) Coordination Unit and control, and monitoring and Implementing Agencies evaluation TZ-MNRT-129698-GO-RFQ / 4. Project management, Supply of office equipment institutional strengthening, Request for Single Stage - One and computers to support IDA / 61430 quality assurance and Post Limited 95,000.00 11,042.03 Completed 2019-09-14 2019-11-07 2019-11-09 2020-04-04 2020-05-07 2020-04-29 Quotations Envelope improvement of institution control, and monitoring and capacities evaluation 4. Project management, TZ-MNRT-130397-GO-DIR / institutional strengthening, Supply of EPICOR Licences, IDA / 61430 quality assurance and Post Direct Selection Direct 66,200.00 0.00 Canceled 2019-09-16 2019-09-21 2019-10-26 2020-04-23 Configuration and Training of control, and monitoring and users under REGROW Project evaluation TZ-MNRT-187392-GO-RFQ / 4. Project management, Supply of office equipment, institutional strengthening, Research equipment's and Request for Single Stage - One IDA / 61430 quality assurance and Post Open - National 205,674.00 0.00 Canceled 2020-08-10 2020-10-05 2021-04-03 computers to support Quotations Envelope control, and monitoring and improvement of institutional evaluation capacities- TAWIRI 4. Project management, TZ-MNRT-194866-GO-RFQ / institutional strengthening, Procurement of Moto vehicles Request for Single Stage - One IDA / 61430 quality assurance and Post Limited 80,000.00 0.00 Canceled 2020-10-03 2020-11-28 2021-05-27 for the Project Coordination Quotations Envelope control, and monitoring and Unit evaluation TZ-MNRT-187377-GO-RFQ / 4. Project management, Supply of office equipment institutional strengthening, Request for Single Stage - One and computers to support IDA / 61430 quality assurance and Post Limited 4,750.00 3,579.13 Completed 2020-09-26 2020-10-10 2020-11-21 2020-11-30 2021-05-20 2021-02-23 Quotations Envelope improvement of institutional control, and monitoring and capacities for TFS evaluation 4. Project management, TZ-MNRT-60449-GO-RFB / institutional strengthening, Request for Single Stage - One supply of office furniture's for IDA / 61430 quality assurance and Post Limited 2,950.00 2,808.79 Signed 2020-09-26 2020-09-08 2020-11-21 2021-04-16 2021-05-20 Quotations Envelope TAWIRI office control, and monitoring and evaluation 4. Project management, institutional strengthening, TZ-MNRT-195448-GO-RFQ / Request for Single Stage - One IDA / 61430 quality assurance and Post Limited 47,950.00 0.00 Canceled 2020-09-26 2020-09-06 2020-11-21 2021-05-20 Supply of ICT Equipment's Quotations Envelope control, and monitoring and evaluation TZ-MNRT-205778-GO-RFQ / 1. Strengthen management Supply of soil sampling Request for Single Stage - One IDA / 61430 and improve infrastructure in Post Limited 30,000.00 20,982.00 Signed 2020-11-25 2020-12-23 2021-01-20 2021-04-16 2021-07-19 equipment's and pasture Quotations Envelope priority Protected Areas meter TZ-MNRT-205782-GO-RFQ / 1. Strengthen management Request for Single Stage - One Supply of range finder, IDA / 61430 and improve infrastructure in Post Limited 30,000.00 15,415.30 Signed 2020-11-25 2020-11-30 2021-01-20 2021-04-16 2021-07-19 Quotations Envelope binocular and walker talker priority Protected Areas 1. Strengthen management TZ-MNRT-205784-GO-RFQ / Request for Single Stage - One IDA / 61430 and improve infrastructure in Post Limited 3,750.00 6,831.17 Signed 2020-11-25 2020-11-30 2021-01-20 2021-04-16 2021-07-19 supply of Sharman traps Quotations Envelope priority Protected Areas 1. Strengthen management TZ-MNRT-205786-GO-DIR / IDA / 61430 and improve infrastructure in Post Direct Selection Direct 29,609.00 18,568.33 Signed 2020-11-20 2021-02-19 2020-11-25 2020-09-04 2020-12-30 2021-04-16 2021-06-28 Supply of Animal Drugs priority Protected Areas Page 1 4. Project management, TZ-MNRT-201735-GO-RFB / institutional strengthening, Supply of Collar Equipment's IDA / 61430 quality assurance and Prior Direct Selection Direct 128,000.00 0.00 Canceled 2020-11-20 2020-11-25 2020-12-30 2021-06-28 for TAWIRI office control, and monitoring and evaluation 4. Project management, TZ-MNRT-208411-GO-DIR / institutional strengthening, Procurement of One Unit of IDA / 61430 quality assurance and Post Direct Selection Direct 80,000.00 0.00 Canceled 2020-12-07 2021-02-19 2020-12-12 2020-12-17 2021-01-16 2021-07-15 Motor vehicle for PCU control, and monitoring and evaluation 4. Project management, TZ-MNRT-226293-GO-RFQ / institutional strengthening, Under Request for Single Stage - One SUPPLY OF ICT EQUIPMENTS IDA / 61430 quality assurance and Post Limited 47,950.00 0.00 Implementati 2021-04-04 2021-04-06 2021-05-30 2021-11-26 Quotations Envelope FOR TAWIRI control, and monitoring and on evaluation 4. Project management, institutional strengthening, TZ-MNRT-228083-GO-RFQ / Request for Single Stage - One IDA / 61430 quality assurance and Post Limited 3,200.00 2,900.39 Signed 2021-01-24 2021-01-19 2021-03-21 2021-05-17 2021-09-17 Supply of Laptop for TTB Quotations Envelope control, and monitoring and evaluation 4. Project management, institutional strengthening, TZ-MNRT-228080-GO-RFQ / Request for Single Stage - One IDA / 61430 quality assurance and Post Limited 7,000.00 6,884.60 Completed 2019-05-24 2020-05-21 2019-07-19 2021-02-16 2020-01-15 2021-04-20 Supply of ICT Equipments Quotations Envelope control, and monitoring and evaluation 4. Project management, institutional strengthening, TZ-MNRT-228082-GO-RFQ / Request for Single Stage - One IDA / 61430 quality assurance and Post Limited 6,000.00 4,397.11 Completed 2019-05-24 2020-05-21 2019-07-19 2021-02-16 2020-01-15 2021-04-20 Supply of Furnitures Quotations Envelope control, and monitoring and evaluation 4. Project management, TZ-MNRT-234689-GO-DIR / institutional strengthening, Pending SUPPLY OF COLLAR IDA / 61430 quality assurance and Post Direct Selection Direct 128,000.00 0.00 Implementati 2021-05-31 2021-06-05 2021-07-10 2022-01-06 EQUIPMENT FOR TAWIRI control, and monitoring and on evaluation NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TZ-MNRT-17017-CS-QCBS / 2. Strengthen alternative Provision of consultancy livelihoods for targeted Quality And Cost- services for environmental IDA / Q9740 Prior Open - International 400,000.00 396,851.50 Signed 2017-06-06 2017-06-06 2017-06-06 2017-06-06 2017-06-06 2017-06-06 2017-06-22 2017-06-27 2016-10-31 2018-06-27 communities in proximity to Based Selection and social impact assessment the priority Protected Areas including ESMF, RPF and PF TZ-MNRT-17022-CS-CQS / Consultancy services to conduct a curriculum 2. Strengthen alternative development workshop and Consultant livelihoods for targeted Pending elaborate a farmer field school IDA / Q9740 Post Qualification Open - National 100,000.00 0.00 2017-06-06 2017-06-06 2017-06-06 2017-06-06 2017-06-27 2017-12-24 communities in proximity to Implementation program on on-farm water Selection the priority Protected Areas and crop management in the irrigation scheme on the usangu plains TZ-MNRT-17027-CS-QCBS / Provision of consultancy 3. Strengthen landscape services to undertake a management and reconnaissance study of Quality And Cost- IDA / Q9740 infrastructure investments in Prior Open - International 400,000.00 385,180.00 Signed 2017-06-06 2017-06-27 2017-06-27 2017-06-27 2017-06-27 2017-07-04 2017-10-27 2017-08-08 2016-10-30 2018-08-08 structural measure to Based Selection and upstream of the Ruaha augment dry season flows in National Park Ruaha National Park, Southern Tanzania TZ-MNRT-17052-CS-QCBS / Consultancy on locally based tourism product development 1. Strengthen management Quality And Cost- and socio- economic IDA / Q9740 and improve infrastructure in Prior Open - National 300,000.00 460,881.13 Signed 2017-06-06 2017-06-06 2017-06-06 2017-06-06 2017-06-06 2017-06-06 2017-07-22 2017-06-27 2017-07-25 2018-06-27 Based Selection assessment of communities priority Protected Areas adjacent to selected protected areas in southern Tanzania TZ-MNRT-17054-CS-QCBS / 3. Strengthen landscape consultancy service to management and undertake a reconnaissance Quality And Cost- IDA / Q9740 infrastructure investments in Prior Open - National 380,000.00 562,591.20 Signed 2017-06-06 2017-06-23 2017-06-06 2017-06-06 2017-06-06 2017-06-06 2017-06-06 2017-07-17 2017-06-27 2017-07-21 2018-06-27 survey of agricultural water Based Selection and upstream of the Ruaha management in usangu flats National Park Southern Tanzania 4. Project management, TZ-MNRT-40665-CS-QCBS / institutional strengthening, Quality And Cost- Under Market research and product IDA / 61430 quality assurance and Prior Open - National 500,000.00 0.00 2018-01-30 2018-05-13 2018-02-20 2018-06-12 2018-04-05 2019-01-22 2018-05-03 2019-02-25 2018-06-02 2019-08-01 2018-07-07 2018-08-11 2019-08-11 Based Selection Implementation market development strategy control, and monitoring and evaluation TZ-MNRT-40894-CS-CQS / Option for PPP and private 1. Strengthen management Consultant sector investment IDA / 61430 and improve infrastructure in Post Qualification Open - National 120,000.00 0.00 Canceled 2018-03-05 2018-03-26 2018-05-09 2018-06-08 2018-07-13 2019-01-09 opportunities in the project priority Protected Areas Selection area Page 2 TZ-MNRT-57587-CS-QCBS / Consultancy services for designing drawing and 1. Strengthen management Quality And Cost- preparation of bill of quantity IDA / 61430 and improve infrastructure in Post Open - National 250,000.00 0.00 Canceled 2018-04-13 2018-05-04 2018-06-17 2018-07-15 2018-08-14 2018-09-18 2018-10-23 2019-10-23 Based Selection and tender document for priority Protected Areas construction of southern circuit management center TZ-MNRT-40895-CS-CQS / The Preparation of an 2. Strengthen alternative Implementation Plan to Consultant livelihoods for targeted Develop Viable Goods and IDA / 61430 Post Qualification Open - National 250,000.00 0.00 Canceled 2018-02-06 2018-02-27 2018-09-19 2018-04-12 2018-05-12 2018-06-16 2018-12-13 communities in proximity to Services Supply Capacity in Selection the priority Protected Areas Selected Communities under the REGROW Project INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TZ-MNRT-17056-CS-INDV / undertaking of an assessment 2. Strengthen alternative of current benefit sharing Individual livelihoods for targeted models associated with with IDA / Q9740 Post Consultant Open 30,000.00 31,500.00 Signed 2017-06-06 2016-01-15 2017-06-06 2016-08-15 2017-06-06 2016-10-10 2017-06-27 2016-10-20 2017-12-24 communities in proximity to natural resources and tourism Selection the priority Protected Areas and lesson learned from best practises 4. Project management, institutional strengthening, Individual TZ-MNRT-17058-CS-INDV / IDA / Q9740 quality assurance and Post Consultant Open 30,000.00 28,331.15 Completed 2017-06-06 2017-06-06 2017-06-06 2016-10-20 2017-06-06 2016-12-05 2017-06-27 2016-12-15 2017-12-24 2018-01-31 Institutional assessment control, and monitoring and Selection evaluation TZ-MNRT-18592-CS-INDV / Consultancy Services for 4. Project management, reviewing the existing institutional strengthening, Individual documents and preparation of IDA / Q9740 quality assurance and Post Consultant Open 30,000.00 99,957.00 Signed 2017-06-20 2017-07-20 2017-06-20 2015-11-17 2017-06-20 2016-02-15 2017-07-11 2016-03-14 2018-01-07 Project Implementation control, and monitoring and Selection manual (PIM) for REGROW evaluation Project. 4. Project management, institutional strengthening, Individual TZ-MNRT-40659-CS-INDV / IDA / 61430 quality assurance and Post Consultant Open 80,000.00 0.00 Canceled 2018-01-28 2018-03-18 2018-04-08 2018-05-13 2018-11-09 Training need asesment control, and monitoring and Selection evaluation 4. Project management, institutional strengthening, Individual TZ-MNRT-40899-CS-INDV / IDA / 61430 quality assurance and Post Consultant Open 20,000.00 0.00 Canceled 2018-02-28 2018-04-18 2018-05-09 2018-06-13 2018-12-10 Development of web page control, and monitoring and Selection evaluation TZ-MNRT-57593-CS-INDV / Consultancy service for 4. Project management, preparation of communication institutional strengthening, Individual strategy for Resilient natural IDA / 61430 quality assurance and Post Consultant Open 50,000.00 0.00 Canceled 2018-04-23 2019-11-21 2018-06-11 2018-07-02 2018-08-06 2019-02-02 Resources management for control, and monitoring and Selection Tourism and Growth evaluation (REGROW) Project TZ-MNRT-57596-CS-INDV / Consultancy services for 4. Project management, establishment of baseline for institutional strengthening, Individual Under Monitoring and Evaluation for IDA / 61430 quality assurance and Post Consultant Open 90,000.00 0.00 2018-04-20 2020-02-04 2018-06-08 2021-04-14 2018-06-29 2018-08-03 2019-01-30 Implementation Resilient natural Resource control, and monitoring and Selection Management for Tourism and evaluation Growth (REGROW) Project 4. Project management, TZ-MNRT-57448-CS-INDV / institutional strengthening, Individual provision of Financial IDA / 61430 quality assurance and Prior Consultant Open 132,000.00 0.00 Canceled 2018-04-15 2018-05-13 2018-06-03 2018-06-24 2018-07-29 2019-01-25 Management support services control, and monitoring and Selection by June 2018 evaluation 4. Project management, TZ-MNRT-57449-CS-INDV / institutional strengthening, Individual Provision of procurement IDA / 61430 quality assurance and Prior Consultant Open 132,000.00 0.00 Canceled 2018-04-10 2018-05-13 2018-05-29 2018-06-19 2018-07-24 2019-01-20 support services by June 2018 control, and monitoring and Selection evaluation TZ-MNRT-65394-CS-INDV / 4. Project management, Consultancy Services for institutional strengthening, Individual provision of Environmental IDA / 61430 quality assurance and Post Consultant Open 90,000.00 0.00 Canceled 2018-06-07 2018-06-07 2018-07-26 2018-08-16 2018-09-20 2019-03-19 and Social Safeguards control, and monitoring and Selection Management and supervision. evaluation TZ-MNRT-187352-CS-INDV / Facilitate the establishment 1. Strengthen management Individual of an e- learning training Under IDA / 61430 and improve infrastructure in Post Consultant Open 15,000.00 0.00 2020-09-01 2021-03-10 2020-10-20 2020-11-10 2020-12-15 2021-06-13 platform on southern tourism Implementation priority Protected Areas Selection circuit for international travel agents for TTB TZ-MNRT-196123-CS-INDV / Consultancy services for 1. Strengthen management Individual Under preparation of design and IDA / 61430 and improve infrastructure in Post Consultant Limited 10,200.00 0.00 2020-10-01 2021-03-10 2020-10-06 2020-10-27 2020-12-01 2021-05-30 Implementation printing Southern Circuit priority Protected Areas Selection Tourism Map for TTB Page 3 Procurement Plan Governance and Policy Project for Federally Administered Tribal Areas (P156412) I. General 1. Bank’s approval Date of the procurement Plan Original: June 2,2016: Revision 3 of Updated Procurement Plan, February 5,2017 2. Date of General Procurement Notice: June 2016 3. Period covered by this procurement plan: The procurement period of project covered, 24 months II. Goods and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Expenditure Contract Value Procurement Contracts Subject to Category (Threshold) Method Prior Review US $ US$ thousand 1.Civil Works Not applicable 2. Goods >600,000 ICB First contract by all entities <600,000 NCB First contract by all entities <100,000 Shopping First contract by all entities Regardless of value Direct Contracting All 2. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan Project XYZ 04/01/2010 issued by 3. Summary of the Procurement Packages planned during the first 18 months after project effectiveness ( including those that are subject to retroactive financing and advanced procurement) July 9, 2010 [List the Packages which require Bank’s prior review first and then the other packages] 1 2 3 4 5 6 7 Ref. Descripti Estimat Packages Dome Review Comme No. on ed stic by Bank nts Cost Prefe (Prior / US$ rence Post) million (yes/ no) Summary 0.2 2 No Post 1st of the NCB contrac (Goods) t for Prior Review III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: 3. Consulting All ToRs and training Services programs to be reviewed by the World Bank’s task team leader (A) Firms >500,000 QCBS, QBS,FBS,LCS, First contract by any process <500,000 CQS, First CQS contract Regardless of value SSS All (B) Individual Up to 200,000 Under Section V (i) First contract Consultants and; (ii) Procurement Specialist regardless of value >200,000 Under Section V All Regardless of value SSS First > 15,000 SSS All July 9, 2010 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_500,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description Estimat Package Review Comment of ed s by Bank s Assignmen Cost (Prior / t US$ Post) million Summary 8.5 5 1 Prior/ of number 4 Post of contracts that will be let under QCBS Summary 0.5 1 Prior CQS of number of contracts that will be let under other methods July 9, 2010 PROCUREMENT Pakistan : Governance and Policy Project for Balochistan PLAN General Information Country: Pakistan Bank’s Approval Date of the Original Procurement Plan: 2017-08-04 2021-05-18 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P156411 GPN Date: Project Name: Governance and Policy Project for Balochistan Loan / Credit No: TF / A3352 FD Governance and Policy Project Balochistan Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-FD GPP-23286-GO-RFQ / Purchase of IT equipment i.e. Increasing effectiveness of Request for Single Stage - One TF / A3352 Prior Limited 50,437.00 18,086.15 Signed 2017-09-10 2017-11-05 2018-05-03 2018-05-04 laptops, desktops, printers, sales tax collection Quotations Envelope photocopiers, etc. PK-FD GPP-23288-GO-RFQ / Increasing effectiveness of Request for Single Stage - One TF / A3352 Post Limited 43,903.00 4,156.59 Signed 2017-08-08 2017-12-15 2017-10-03 2018-01-08 2018-04-01 Purchase of furniture. sales tax collection Quotations Envelope PK-FD GPP-23291-GO-RFQ / Purchase of office equipment Increasing effectiveness of Request for Single Stage - One i.e. air conditioner, TF / A3352 Post Limited 9,757.00 0.00 Canceled 2017-09-08 2017-11-03 2018-05-02 sales tax collection Quotations Envelope refrigerator, microwave oven, etc.) PK-FD GPP-24550-GO-RFQ / Development of database and Increasing effectiveness of Request for Single Stage - One TF / A3352 Post Limited 9,709.00 0.00 Canceled 2017-09-25 2017-11-20 2018-05-19 website for Balochistan's sales tax collection Quotations Envelope Public Accounts Committee. PK-FD GPP-107321-GO-RFQ Increasing effectiveness of Request for Single Stage - One / Purchase of furniture for TF / A3352 Post Limited 2,885.00 0.00 Canceled 2019-04-20 2019-06-15 2019-12-12 sales tax collection Quotations Envelope NFC strengthening. PK-FD GPP-107325-GO-RFQ Increasing effectiveness of Request for Single Stage - One / Purchase of furniture for TF / A3352 Post Limited 38,029.00 27,690.43 Signed 2019-04-27 2020-08-23 2019-06-22 2019-11-08 2019-12-19 sales tax collection Quotations Envelope BRA regional offices. PK-FD GPP-110297-GO-RFQ Increasing effectiveness of Request for Single Stage - One / Purchase of IT equipment TF / A3352 Post Limited 84,692.00 58,645.06 Signed 2019-05-04 2020-08-23 2019-06-29 2019-11-08 2019-12-26 sales tax collection Quotations Envelope for BRA regional offices. PK-FD GPP-144473-GO-RFQ Strengthening accountability / Purchase of Air Conditioners Request for Single Stage - One TF / A3352 in public financial Post Limited 2,800.00 3,967.81 Signed 2019-12-22 2020-09-12 2020-02-16 2020-09-30 2020-08-14 for various CN's under Finance Quotations Envelope management Department. PK-FD GPP-144447-GO-RFQ Strengthening accountability / Purchase of IT equipment Request for Single Stage - One TF / A3352 in public financial Post Limited 54,700.00 103,031.97 Signed 2019-12-22 2020-09-12 2020-02-16 2020-09-30 2020-08-14 for various CN's under Finance Quotations Envelope management Department. PK-FD GPP-144459-GO-RFQ Strengthening accountability Pending / Purchase of furniture for Request for Single Stage - One TF / A3352 in public financial Post Limited 12,440.00 0.00 Implementati 2021-04-20 2021-06-15 2021-12-12 various CN's under Finance Quotations Envelope management on Department. PK-FD GPP-107320-GO-RFQ Increasing effectiveness of Request for Single Stage - One / Purchase of IT equipment TF / A3352 Prior Limited 5,529.00 0.00 Canceled 2019-04-20 2019-06-15 2019-12-12 sales tax collection Quotations Envelope for NFC strengthening. PK-FD GPP-220587-GO-RFQ Strengthening accountability Under / Purchase of Electrical items Request for Single Stage - One TF / A3352 in public financial Post Limited 92,000.00 0.00 Implementati 2021-03-08 2021-03-11 2021-05-03 2021-10-30 for Balochistan Public Service Quotations Envelope management on Commission. PK-FD GPP-220591-GO-RFQ Strengthening accountability Under / Purchase of Furniture for Request for Single Stage - One TF / A3352 in public financial Post Limited 45,000.00 0.00 Implementati 2021-03-15 2021-03-11 2021-05-10 2021-11-06 Balochistan Public Service Quotations Envelope management on Commission. PK-FD GPP-220584-GO-RFB Strengthening accountability Under / Purchase of IT Equipment Single Stage - One TF / A3352 in public financial Post Request for Bids Open - National 455,000.00 0.00 Implementati 2021-02-25 2021-04-28 2021-03-02 2021-05-31 2021-04-13 2021-04-27 2021-06-01 2021-11-28 for Balochistan Public Service Envelope management on Commission. PK-FD GPP-220593-GO-RFQ Strengthening accountability Under / Renovation of computer labs Request for Single Stage - One TF / A3352 in public financial Post Limited 75,000.00 0.00 Implementati 2021-03-22 2021-03-11 2021-05-17 2021-11-13 of Balochistan Public Service Quotations Envelope management on Commission. PK-FD GPP-144469-GO-RFQ Strengthening accountability Request for Single Stage - One / Purchase of AC for Debt TF / A3352 in public financial Post Limited 667.00 0.00 Canceled 2021-04-20 2021-06-15 2021-12-12 Quotations Envelope Management Unit. management PK-FD GPP-230244-GO-RFQ Strengthening accountability Pending Request for Single Stage - One / Purchase of furniture for TF / A3352 in public financial Post Limited 3,500.00 0.00 Implementati 2021-06-05 2021-07-20 2021-08-19 Quotations Envelope BPPRA management on PK-FD GPP-230240-GO-RFB Strengthening accountability Under Single Stage - One / Purchase of Office TF / A3352 in public financial Post Request for Bids Open - National 135,000.00 0.00 Implementati 2021-05-31 2021-05-28 2021-06-05 2021-05-31 2021-07-17 2021-07-18 2021-08-22 2021-11-20 Envelope Equipment for BPPRA management on Page 1 PK-FD GPP-230246-GO-RFQ Strengthening accountability Pending Request for Single Stage - One / Sound proofing and lighting TF / A3352 in public financial Post Limited 17,000.00 0.00 Implementati 2021-07-04 2021-08-18 2021-09-17 Quotations Envelope of conference hall for BPPRA management on PK-FD GPP-230237-GO-RFB Strengthening accountability Under Single Stage - One / Procurement of IT goods for TF / A3352 in public financial Post Request for Bids Open - National 130,000.00 0.00 Implementati 2021-05-31 2021-04-28 2021-06-05 2021-05-31 2021-07-17 2021-07-27 2021-08-31 2021-11-29 Envelope BPPRA and BRA. management on PK-FD GPP-230242-GO-RFQ Strengthening accountability Pending / Purchase of electrical items Request for Single Stage - One TF / A3352 in public financial Post Open - National 30,000.00 0.00 Implementati 2021-06-05 2021-08-03 2021-08-24 (UPS, Generator, AC, Mosquito Quotations Envelope management on Repellent.) NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-FD GPP-23299-CS-CQS / Consultant Hiring of institutional support Increasing effectiveness of TF / A3352 Prior Qualification Open - National 310,680.00 0.00 Canceled 2017-09-14 2017-10-05 2017-11-18 2017-12-18 2018-01-22 2018-07-21 for Balochistan Revenue sales tax collection Selection Authority. PK-FD GPP-23294-CS-CQS / Hiring of firm for providing Consultant strategic support in the areas Increasing effectiveness of TF / A3352 Post Qualification Open - National 78,641.00 0.00 Canceled 2017-10-18 2017-11-08 2017-12-22 2018-01-21 2018-02-25 2018-08-24 of communication and sales tax collection Selection reporting and other related services. PK-FD GPP-23296-CS-CQS / Consultant Increasing effectiveness of Hiring of firm for assessing TF / A3352 Post Qualification Open - National 87,739.00 228,530.80 Signed 2017-09-13 2017-03-15 2017-10-04 2017-11-17 2019-02-25 2017-12-17 2019-04-22 2018-01-21 2019-04-22 2018-07-20 sales tax collection Balochistan's tax revenue. Selection PK-FD GPP-23323-CS-QCBS / Hiring of firm/(s) for Increasing effectiveness of Quality And Cost- TF / A3352 Prior Open - International 692,718.00 0.00 Canceled 2017-08-31 2017-09-21 2017-11-04 2017-12-04 2018-01-03 2018-02-07 2018-03-14 2019-03-14 providing strategic support in sales tax collection Based Selection the areas of PFM. PK-FD GPP-66584-CS-CQS / Strengthening accountability Consultant Hiring of actuarial firm for TF / A3352 in public financial Post Qualification Open - National 38,835.00 28,596.96 Signed 2018-06-21 2018-06-20 2018-07-12 2018-08-25 2018-07-19 2018-09-24 2018-11-06 2018-10-29 2018-11-28 2019-04-27 assessment of Balochistan's management Selection end of service liabilities. PK-FD GPP-25473-CS-LCS / Hiring of firm/(s) for Increasing effectiveness of Least Cost TF / A3352 Prior Open - National 692,718.00 0.00 Canceled 2017-08-31 2017-09-12 2017-09-21 2017-11-04 2017-12-02 2018-01-01 2018-02-05 2018-03-12 2018-09-08 providing strategic support in sales tax collection Selection the areas of PFM. PK-FD GPP-110768-CS-CQS Consultant Increasing effectiveness of / Development of BRA's IT TF / A3352 Post Qualification Open - National 38,462.00 0.00 Canceled 2019-08-22 2019-09-12 2019-10-26 2019-11-25 2019-12-30 2020-06-27 sales tax collection solution. Selection PK-FD GPP-178171-CS-CQS Strengthening accountability Consultant Under / Hiring of firm for TF / A3352 in public financial Post Qualification Open - National 18,750.00 0.00 2020-06-16 2021-03-19 2020-07-07 2021-03-26 2020-08-20 2021-04-28 2020-09-19 2020-10-24 2021-04-22 Implementation Balochistan's sector scanning management Selection PK-FD GPP-144499-CS-CQS Strengthening accountability Consultant / Drafting Rules for Provincial TF / A3352 in public financial Post Qualification Open - National 80,000.00 0.00 Canceled 2019-12-31 2020-01-21 2020-03-05 2020-04-04 2020-05-09 2020-11-05 Revenue Management Unit. management Selection PK-FD GPP-218991-CS-CQS Consultant / Hiring of firm for Increasing effectiveness of Under TF / A3352 Post Qualification 100,000.00 0.00 2021-02-18 2021-02-19 2021-03-11 2021-02-24 2021-04-24 2021-05-24 2021-06-28 2021-12-25 Balochistan's Non-Tax sales tax collection Implementation Selection Revenue Mobilization. PK-FD GPP-220595-CS-CQS / Development of SRS and Strengthening accountability Consultant Under Online Testing System ERP TF / A3352 in public financial Post Qualification Open - National 124,000.00 0.00 2021-03-24 2021-04-16 2021-04-14 2021-06-03 2021-04-24 2021-05-01 2021-06-05 2021-12-02 Implementation Software for Balochistan management Selection Public Service Commission. PK-FD GPP-226833-CS-CQS / Hiring of firm for conducting Strengthening accountability Consultant Under feasibility study on TF / A3352 in public financial Post Qualification Open - National 31,250.00 0.00 2021-04-08 2021-04-02 2021-04-29 2021-04-05 2021-05-23 2021-07-02 2021-08-06 2022-02-02 Implementation establishing a bank for management Selection government of Balochistan. Strengthening accountability Consultant PK-FD GPP-144496-CS-CQS TF / A3352 in public financial Post Qualification Open - National 33,333.00 0.00 Canceled 2019-12-31 2020-01-21 2020-03-05 2020-04-04 2020-05-09 2020-11-05 / Drafting of Act for PFM Unit. management Selection PK-FD GPP-144493-CS-CQS Strengthening accountability Consultant / Drafting of Regulatory TF / A3352 in public financial Post Qualification Open - National 13,333.00 0.00 Canceled 2019-12-31 2020-01-21 2020-03-05 2020-04-04 2020-05-09 2020-11-05 Framework for Debt management Selection Management Unit. PK-FD GPP-144492-CS-CQS Strengthening accountability Consultant / Development of database TF / A3352 in public financial Post Qualification Open - National 66,667.00 0.00 Canceled 2021-03-31 2021-04-21 2021-06-04 2021-07-04 2021-08-08 2022-02-04 for Debt Management Unit. management Selection PK-FD GPP-144497-CS-CQS Consultant Increasing effectiveness of / Website development for TF / A3352 Post Qualification Open - National 20,000.00 0.00 Canceled 2021-03-31 2021-04-21 2021-06-04 2021-07-04 2021-08-08 2022-02-04 sales tax collection Public Accounts Committee. Selection INDIVIDUAL CONSULTANTS Page 2 Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-FD GPP-34506-CS-INDV / Hiring of Engineer for strengthening of Public Strengthening accountability Individual Accounts Committee for TF / A3352 in public financial Post Consultant Open 11,462.00 0.00 Canceled 2017-10-31 2017-11-02 2017-12-19 2018-01-09 2018-02-13 2018-08-12 scrutiny of audit reports in management Selection Balochistan under component 2 of GPP Balochistan. PK-FD GPP-34507-CS-INDV / Hiring of Communication, Media and Research Specialist Strengthening accountability Individual for strengthening of Public TF / A3352 in public financial Post Consultant Open 11,462.00 5,185.82 Signed 2017-10-31 2017-11-02 2017-12-19 2018-02-05 2018-01-09 2018-02-07 2018-02-13 2018-02-07 2018-08-12 Accounts Committee under management Selection component 2 of GPP Balochistan. PK-FD GPP-34502-CS-INDV / Hiring of Auditor for Public Strengthening accountability Individual Accounts Committee's TF / A3352 in public financial Post Consultant Open 19,103.00 7,562.66 Signed 2017-11-29 2017-11-02 2018-01-17 2017-12-26 2018-02-07 2018-01-08 2018-03-14 2018-01-08 2018-09-10 strengthening towards management Selection legislative scrutiny of audit reports in Balochistan. Strengthening accountability Individual PK-FD GPP-38241-CS-INDV TF / A3352 in public financial Post Consultant Open 19,103.00 7,562.66 Signed 2017-11-29 2017-11-01 2018-01-17 2018-01-17 2018-02-07 2018-01-19 2018-03-14 2018-01-19 2018-09-10 / Hiring of auditor for PAC. management Selection PK-FD GPP-23309-CS-CDS / Analysis, Design and Development of Public Increasing effectiveness of TF / A3352 Prior Direct Selection Direct 281,553.00 759,014.13 Signed 2017-12-04 2017-12-20 2017-12-14 2018-04-11 2018-02-17 2018-06-28 2018-08-16 Financial Management's sales tax collection Professional Accreditation Program. PK-FD GPP-23308-CS-CDS / Increasing effectiveness of Designing of Professional TF / A3352 Post Direct Selection Direct 14,563.00 0.00 Canceled 2017-09-21 2017-10-01 2017-12-05 2018-06-03 sales tax collection Accreditation Program. PK-FD GPP-79488-CS-INDV Strengthening accountability Individual / Hiring of Chief Internal TF / A3352 in public financial Post Consultant Open 43,689.00 27,866.46 Signed 2018-10-03 2018-11-21 2018-11-21 2019-02-04 2018-12-12 2019-03-11 2019-01-16 2019-03-11 2020-07-09 Auditor for Internal Audit management Selection Unit. PK-FD GPP-79496-CS-INDV Strengthening accountability Individual / Hiring of Internal Audit TF / A3352 in public financial Post Consultant Open 34,951.00 22,030.01 Signed 2018-10-03 2018-11-21 2018-11-21 2019-02-14 2018-12-12 2019-03-18 2019-01-16 2019-03-18 2020-07-09 Manager for Internal Audit management Selection Unit. PK-FD GPP-79498-CS-INDV Strengthening accountability Individual / Hiring of Debt Management TF / A3352 in public financial Post Consultant Open 52,427.00 46,966.75 Signed 2018-10-03 2018-11-28 2018-11-21 2019-02-04 2018-12-12 2019-06-24 2019-01-16 2019-06-24 2020-07-09 Specialist for Debt management Selection Management Unit. PK-FD GPP-79504-CS-INDV Strengthening accountability Individual / Hiring of Financial Analyst TF / A3352 in public financial Post Consultant Open 34,951.00 23,222.05 Signed 2018-10-03 2018-11-21 2018-11-21 2019-01-08 2018-12-12 2019-02-15 2019-01-16 2019-02-15 2020-07-09 for Debt Management Unit. management Selection PK-FD GPP-107322-CS-INDV Strengthening accountability Individual / Hiring of Technical Research TF / A3352 in public financial Post Consultant Open 23,077.00 15,481.37 Signed 2019-04-15 2019-04-16 2019-06-03 2019-05-20 2019-06-24 2019-05-20 2019-07-29 2019-05-20 2021-01-19 Expert for NFC. management Selection PK-FD GPP-125866-CS-INDV Strengthening accountability Individual / Hiring of Internal Audit Under TF / A3352 in public financial Post Consultant Open 34,951.00 0.00 2019-08-08 2019-09-03 2019-10-10 2019-10-31 2019-12-05 2021-05-28 Manager for Internal Audit Implementation management Selection Unit. PK-FD GPP-144479-CS-INDV Strengthening accountability Individual / Hiring of Legal Expert for TF / A3352 in public financial Post Consultant Open 10,000.00 0.00 Canceled 2019-12-24 2020-02-11 2020-03-03 2020-04-07 2020-10-04 Public Accounts Committee. management Selection PK-FD GPP-144474-CS-INDV Individual Increasing effectiveness of / Hiring of Senior Revenue TF / A3352 Post Consultant Open 32,000.00 14,928.52 Signed 2019-12-24 2020-01-07 2020-02-11 2020-01-29 2020-03-03 2020-02-06 2020-04-07 2020-02-06 2021-04-02 sales tax collection Consultant for 12 months. Selection PK-FD GPP-193573-CS-INDV / Hiring of PFM Expert to Strengthening accountability Individual review the contents of ACCA's TF / A3352 in public financial Post Consultant Open 37,500.00 25,318.84 Signed 2020-09-11 2020-09-16 2020-10-30 2021-02-04 2020-11-20 2021-02-04 2020-12-25 2021-02-04 2021-03-31 deliverables against PFM-PAP management Selection Contract with an estimated amount of PKR 6 M. PK-FD GPP-144478-CS-INDV Strengthening accountability Individual / Hiring of Audit and Financial TF / A3352 in public financial Post Consultant Open 14,000.00 0.00 Canceled 2019-12-24 2020-02-11 2020-03-03 2020-04-07 2020-10-04 Analyst for Public Accounts management Selection Committee for 6 months. PK-FD GPP-144479-CS-INDV- Strengthening accountability Individual 2 / Hiring of Legal Expert for TF / A3352 in public financial Post Consultant Open 10,000.00 0.00 Canceled 2020-08-19 2020-11-07 2020-10-07 2020-10-28 2020-12-02 2021-05-31 Public Accounts Committee. management Selection PK-FD GPP-144485-CS-INDV Strengthening accountability Individual / Hiring of Internal Audit TF / A3352 in public financial Post Consultant Open 32,000.00 0.00 Canceled 2019-12-24 2020-02-11 2020-03-03 2020-04-07 2021-04-02 Manager for Internal Audit management Selection Unit for 12 months. PK-FD GPP-144490-CS-INDV Strengthening accountability Individual / Hiring of Financial Analyst TF / A3352 in public financial Post Consultant Open 24,000.00 0.00 Canceled 2019-12-31 2020-02-18 2020-03-10 2020-04-14 2021-04-09 for Debt Management Unit for management Selection 12 months. PK-FD GPP-144491-CS-INDV Strengthening accountability Individual / Hiring of Financial Analyst TF / A3352 in public financial Post Consultant Open 24,000.00 0.00 Canceled 2019-12-31 2020-02-18 2020-03-10 2020-04-14 2021-04-09 for Debt Management Unit for management Selection 12 months. Page 3 PK-FD GPP-144489-CS-INDV / Hiring of Debt Management Strengthening accountability Individual Specialist for Debt TF / A3352 in public financial Post Consultant Open 52,000.00 0.00 Canceled 2019-12-31 2020-02-18 2020-03-10 2020-04-14 2021-04-09 Management Unit for 12 management Selection months. Strengthening accountability Individual PK-FD GPP-38242-CS-INDV TF / A3352 in public financial Post Consultant Open 19,103.00 0.00 Canceled 2017-11-29 2017-11-02 2018-01-17 2017-12-22 2018-02-07 2018-03-14 2018-09-10 / Hiring of auditor for PAC. management Selection PK-FD GPP-144480-CS-INDV / Hiring of Communication Strengthening accountability Individual and Reporting Expert for TF / A3352 in public financial Post Consultant Open 8,000.00 0.00 Canceled 2019-12-24 2020-02-11 2020-03-03 2020-04-07 2020-10-04 Public Accounts Committee management Selection for 6 months. PK-FD GPP-219833-CS-INDV Strengthening accountability Individual Under / Hiring of Senior PFM TF / A3352 in public financial Post Consultant Open 52,000.00 0.00 2021-02-23 2021-02-17 2021-04-13 2021-05-04 2021-06-08 2022-06-08 Implementation Specialist for PFM Unit. management Selection PK-FD GPP-226834-CS-INDV Strengthening accountability Individual / Hiring of Banking Advisor TF / A3352 in public financial Post Consultant Open 37,500.00 50,830.88 Signed 2021-04-08 2021-04-02 2021-05-11 2021-05-05 2021-06-01 2021-05-20 2021-07-06 2021-05-20 2022-05-31 for establishing Balochistan management Selection bank. PK-FD GPP-79508-CS-INDV / Hiring of Public Investment Strengthening accountability Individual Management Specialist for TF / A3352 in public financial Post Consultant Open 34,951.00 0.00 Canceled 2021-02-11 2021-04-01 2021-04-22 2021-05-27 2022-11-18 Balochistan Board of management Selection Investment. PK-FD GPP-79506-CS-INDV Strengthening accountability Individual / Hiring of Legal Framework TF / A3352 in public financial Post Consultant Open 34,951.00 0.00 Canceled 2021-02-11 2021-04-01 2021-04-22 2021-05-27 2022-11-18 Specialist for Balochistan management Selection Board of Investment. PK-FD GPP-144475-CS-INDV / Hiring of Financial Strengthening accountability Individual Management Specialist for TF / A3352 in public financial Post Consultant Open 28,000.00 0.00 Canceled 2021-03-31 2021-05-19 2021-06-09 2021-07-14 2022-07-09 Corporate Governance Unit for management Selection 12 months. PK-FD GPP-233990-CS-INDV Individual / Hiring of Legal Consultant Increasing effectiveness of Under TF / A3352 Post Consultant Open 14,000.00 0.00 2021-05-26 2021-06-07 2021-06-30 2021-07-05 2021-08-09 2022-02-05 for Balochistan Revenue sales tax collection Implementation Selection Authority PK-FD GPP-233995-CS-INDV Individual Increasing effectiveness of Under / Hiring of Sales Tax TF / A3352 Post Consultant Open 14,000.00 0.00 2021-05-25 2021-05-19 2021-06-29 2021-07-06 2021-07-27 2022-01-23 sales tax collection Implementation Consultant Selection PK-FD GPP-233999-CS-INDV Individual Increasing effectiveness of Under / Hiring of Capacity Building & TF / A3352 Post Consultant Open 14,000.00 0.00 2021-05-26 2021-05-19 2021-06-30 2021-07-07 2021-07-28 2022-01-24 sales tax collection Implementation Financial Expert Selection PK-FD GPP-234000-CS-INDV Individual Increasing effectiveness of Under / Hiring of Auditor for TF / A3352 Post Consultant Open 5,833.00 0.00 2021-05-26 2021-05-19 2021-06-30 2021-07-07 2021-07-28 2022-01-24 sales tax collection Implementation Balochistan Revenue Authority Selection PK-FD GPP-234001-CS-INDV Individual Increasing effectiveness of Under / Hiring of Auditor for TF / A3352 Post Consultant Open 5,833.00 0.00 2021-05-26 2021-05-19 2021-06-30 2021-07-07 2021-07-28 2022-01-24 sales tax collection Implementation Balochistan Revenue Authority Selection PK-FD GPP-234002-CS-INDV Individual Increasing effectiveness of Under / Hiring of Auditor for TF / A3352 Post Consultant Open 5,833.00 0.00 2021-05-26 2021-05-19 2021-06-30 2021-07-07 2021-07-28 2022-01-24 sales tax collection Implementation Balochistan Revenue Aurhority Selection PK-FD GPP-234004-CS-INDV Individual Increasing effectiveness of Under / Hiring of Auditor for TF / A3352 Post Consultant Open 5,833.00 0.00 2021-05-26 2021-05-19 2021-06-30 2021-07-07 2021-07-28 2022-01-24 sales tax collection Implementation Balochistan Revenue Authority Selection PK-FD GPP-234006-CS-INDV Individual Increasing effectiveness of Under / Hiring of Auditor for TF / A3352 Post Consultant Open 5,833.00 0.00 2021-05-26 2021-05-19 2021-06-30 2021-07-07 2021-07-28 2022-01-24 sales tax collection Implementation Balochistan Revenue Authority Selection PK-FD GPP-234007-CS-INDV Individual / Hiring of Tax Enforcement Increasing effectiveness of Under TF / A3352 Post Consultant Open 5,833.00 0.00 2021-05-28 2021-05-19 2021-07-02 2021-07-09 2021-07-30 2022-01-26 Inspector for Balochistan sales tax collection Implementation Selection Revenue Authority PK-FD GPP-234008-CS-INDV Individual / Hiring of Tax Enforcement Increasing effectiveness of Under TF / A3352 Post Consultant Open 5,833.00 0.00 2021-05-28 2021-06-04 2021-07-02 2021-07-09 2021-07-30 2022-01-26 Inspector for Balochistan sales tax collection Implementation Selection Revenue Authority PK-FD GPP-234009-CS-INDV Individual / Hiring of Tax Enforcement Increasing effectiveness of Under TF / A3352 Post Consultant Open 5,833.00 0.00 2021-05-28 2021-06-04 2021-07-02 2021-07-09 2021-07-30 2022-01-26 Inspector for Balochistan sales tax collection Implementation Selection Revenue Authority PK-FD GPP-234010-CS-INDV Individual / Hiring of Tax Enforcement Increasing effectiveness of Under TF / A3352 Post Consultant Open 5,833.00 0.00 2021-05-28 2021-06-04 2021-07-02 2021-07-09 2021-07-30 2022-01-26 Inspector for Balochistan sales tax collection Implementation Selection Revenue Authority PK-FD GPP-234011-CS-INDV Individual / Hiring of Tax Enforcement Increasing effectiveness of Under TF / A3352 Post Consultant Open 5,833.00 0.00 2021-05-28 2021-06-04 2021-07-02 2021-07-09 2021-07-30 2022-01-26 Inspector for Balochistan sales tax collection Implementation Selection Revenue Authority PK-FD GPP-235142-CS-INDV Strengthening accountability Individual / Hiring of Communication/ Under TF / A3352 in public financial Post Consultant Open 14,000.00 0.00 2021-05-26 2021-05-19 2021-06-25 2021-07-02 2021-07-23 2022-01-19 Media Expert for Balochistan Implementation management Selection Revenue Authority PK-FD GPP-237830-CS-CDS Strengthening accountability / Hiring of Accountability Lab Under TF / A3352 in public financial Post Direct Selection Direct 350,000.00 0.00 2021-06-08 2021-06-03 2021-06-18 2021-07-28 2022-01-24 for strengthening of Public Implementation management Accounts Committee. Page 4 PROCUREMENT PLAN (Textual Part) Project information: Mongolia Export Development Project (P147438) Project Implementation agency: Agricultural Reinsurance Joint Stock Company (AgRe) Date of the Procurement Plan: March 07, 2017 Period covered by this Procurement Plan: March 01, 2017 - March 01, 2018 1.Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. 2. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. 3. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. 3.1 National Open Competitive Procurement When the Borrower uses its own national open competitive procurement arrangements as set forth in Chapter Two of the Public Procurement Law of Mongolia enacted on December 1, 2005, as amended several times with the latest amendment on February 9, 2017, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. (a) Participation in Bidding and Preferences (i) Government-owned enterprises in Mongolia shall be eligible to participate in bidding only if they can establish that they are legally and financially autonomous, operate under commercial law, and are not a dependent of the agency contracting them. (ii) A bidder declared ineligible by the World Bank, based on a determination by the World Bank that the bidder has engaged in corrupt, fraudulent, collusive, coercive or obstructive practices in competing for or in executing a World Bank-financed contract, shall be ineligible to participate and be awarded a World Bank- financed contract during the period determined by the World Bank. (iii) A firm which has been engaged by the Borrower to provide consulting services for the preparation or implementation of a project, and any of its affiliates, shall be disqualified from subsequently providing goods or works resulting from or directly related to the firm’s consulting services for such preparation or implementation. This provision does not apply to the various firms which together are performing the contractor’s obligations under a turnkey or design and build contract. (iv) Interested foreign bidders from eligible countries shall be allowed to participate without being required to associate or form joint ventures with local bidders. Foreign bidders shall be eligible to participate in bidding under the same conditions as local bidders. Mongolian bidders and goods of Mongolian origin shall be given no preference over foreign bidders, either in the bidding process or in the evaluation of bids. (v) Prior registration shall not be a requirement for any bidder to participate in bidding. (b) Request for Bids / Request for Proposals Documents (i) The request for bids/request for proposals documents shall be acceptable to the World Bank (ii) The request for bids / request for proposals documents and the signed contract shall include the clauses related to World Bank’s Policy in regard to corrupt and fraudulent practices. (iii) In the case of contracts of more than eighteen (18) months’ duration, the bidding documents and the resultant contract shall provide for price adjustment, based on a formula acceptable to the World Bank, which shall be disclosed to the bidders in the bidding documents. (v) There shall be no post-bidding negotiations with the lowest evaluated bidder or any other bidder. No bidder shall be required, as a condition for the award of contract, to change his bid price or otherwise materially alter his bid after it has been submitted. (c) Assessment of Bidder’s Qualification Qualification criteria shall be clearly specified in the bidding documents, and only criteria so specified, shall be used to determine whether a bidder is qualified. The evaluation of the bidder’s qualifications shall be conducted separately from the technical and commercial evaluation of the bid. When post qualification is applied, the assessment of bidder’s qualifications shall be carried out only after the preliminary and detailed evaluation of bids has been completed by the Recipient and, in doing so, the qualifications of the bidder who has submitted the lowest evaluated substantially responsive bid or most advantageous bid shall be assessed first. The evaluation of a bidder’s qualifications shall only take into account the bidder’s capacity and resources to perform the contract, specifically its experience and past performance on similar contracts, capabilities with respect to personnel, equipment and construction or manufacturing facilities and financial capacity. In carrying out the post-qualification assessment, the Recipient shall exercise reasonable judgment in requesting, in writing, from a bidder only missing factual or historical supporting information related to the bidder’s qualifications and shall provide a reasonable time period (that is, a minimum of seven days) to the bidder to provide his response. No bidders shall be disqualified on the ground that the bidder has tax debt. 3.2 Other National Procurement Arrangements When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. The request for bids / request for proposals / request for quotations documents should be acceptable to the Bank and jointly with the signed contract shall include the clauses related to World Bank’s Policy in regard to corrupt and fraudulent practices. The request for bids / request for proposals / request for quotations documents and the signed contract shall also include the clauses allowing the World Bank to inspect the site and/or all accounts and records relating to the performance of the contract and the submission of the bid or proposal, and to have such accounts and records audited. The standard text is attached hereafter. 4. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not applicable. 5. Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations: Not applicable. 6. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations: Not applicable. 7. Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations: Not applicable. 8. Other Relevant Procurement Information: Not applicable. Fraud and The Bank requires compliance with the Bank’s Anti- Corruption Corruption Guidelines and its prevailing sanctions policies and procedures as set forth in the WBG’s Sanctions Framework, as set forth in Appendix to the GC. The Employer / Purchaser / Client requires the Contractor / Supplier / the Consultant to disclose any commissions or fees that may have been paid or are to be paid to agents or any other party with respect to the bidding /selection process or execution of the Contract. The information disclosed must include at least the name and address of the agent or other party, the amount and currency, and the purpose of the commission, gratuity or fee. Failure to disclose such commissions, gratuities or fees may result in termination of the Contract and/or sanctions by the Bank. Inspections The Contractor / Supplier / Consultant shall keep, and and Audit shall make all reasonable efforts to cause its by the Subcontractors and Sub-consultants to keep, accurate Bank and systematic accounts and records in respect of the Works / Goods / Services in such form and details as will clearly identify relevant time changes and costs. Pursuant to paragraph 2.2 e. of Appendix to the General Conditions the Contractor / Supplier / Consultant shall permit and shall cause its subcontractors and sub-consultants to permit, the Bank and/or persons appointed by the Bank to inspect the Site and/or the accounts and records relating to the performance of the Contract and the submission of the bid / proposal, and to have such accounts and records audited by auditors appointed by the Bank if requested by the Bank. The Contractor’s / Supplier’s / Consultant’s and its Subcontractors’ and sub- consultants’ acts intended to materially impede the exercise of the Bank’s inspection and audit rights constitute a prohibited practice subject to contract termination (as well as to a determination of ineligibility pursuant to the Bank’s prevailing sanctions procedures). APPENDIX TO GENERAL CONDITIONS Fraud and Corruption (Text in this Appendix shall not be modified) 1. Purpose 1.1 The Bank’s Anti-Corruption Guidelines and this annex apply with respect to procurement under Bank Investment Project Financing operations. 2. Requirements 2.1 The Bank requires that Borrowers (including beneficiaries of Bank financing); bidders, consultants, contractors and suppliers; any sub- contractors, sub-consultants, service providers or suppliers; any agents (whether declared or not); and any of their personnel, observe the highest standard of ethics during the procurement process, selection and contract execution of Bank-financed contracts, and refrain from Fraud and Corruption. 2.2 To this end, the Bank: a. Defines, for the purposes of this provision, the terms set forth below as follows: i. “corrupt practice” is the offering, giving, receiving, or soliciting, directly or indirectly, of anything of value to influence improperly the actions of another party; ii. “fraudulent practice” is any act or omission, including misrepresentation, that knowingly or recklessly misleads, or attempts to mislead, a party to obtain financial or other benefit or to avoid an obligation; iii. “collusive practice” is an arrangement between two or more parties designed to achieve an improper purpose, including to influence improperly the actions of another party; iv. “coercive practice” is impairing or harming, or threatening to impair or harm, directly or indirectly, any party or the property of the party to influence improperly the actions of a party; v. “obstructive practice” is: (a) deliberately destroying, falsifying, altering, or concealing of evidence material to the investigation or making false statements to investigators in order to materially impede a Bank investigation into allegations of a corrupt, fraudulent, coercive, or collusive practice; and/or threatening, harassing, or intimidating any party to prevent it from disclosing its knowledge of matters relevant to the investigation or from pursuing the investigation; or (b) acts intended to materially impede the exercise of the Bank’s inspection and audit rights provided for under paragraph 2.2 e. below. b. Rejects a proposal for award if the Bank determines that the firm or individual recommended for award, any of its personnel, or its agents, or its sub-consultants, sub-contractors, service providers, suppliers and/ or their employees, has, directly or indirectly, engaged in corrupt, fraudulent, collusive, coercive, or obstructive practices in competing for the contract in question; c. In addition to the legal remedies set out in the relevant Legal Agreement, may take other appropriate actions, including declaring miss-procurement, if the Bank determines at any time that representatives of the Borrower or of a recipient of any part of the proceeds of the loan engaged in corrupt, fraudulent, collusive, coercive, or obstructive practices during the procurement process, selection and/or execution of the contract in question, without the Borrower having taken timely and appropriate action satisfactory to the Bank to address such practices when they occur, including by failing to inform the Bank in a timely manner at the time they knew of the practices; d. Pursuant to the Bank’s Anti- Corruption Guidelines and in accordance with the Bank’s prevailing sanctions policies and procedures, may sanction a firm or individual, either indefinitely or for a stated period of time, including by publicly declaring such firm or individual ineligible (i) to be awarded or otherwise benefit from a Bank-financed contract, financially or in any other manner;1 (ii) to be a nominated2 sub-contractor, consultant, manufacturer or supplier, or service provider of an otherwise eligible firm being awarded a Bank-financed contract; and (iii) to receive the proceeds of any loan made by the Bank or otherwise to participate further in the preparation or implementation of any Bank-financed project; e. Requires that a clause be included in bidding/request for proposals documents and in contracts financed by a Bank loan, requiring (i) bidders, consultants, contractors, and suppliers, and their sub- contractors, sub-consultants, service providers, suppliers, agents 1 For the avoidance of doubt, a sanctioned party’s ineligibility to be awarded a contract shall include, without limitation, (i) applying for pre-qualification, expressing interest in a consultancy, and bidding, either directly or as a nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider, in respect of such contract, and (ii) entering into an addendum or amendment introducing a material modification to any existing contract. 2 A nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider (different names are used depending on the particular bidding document) is one which has been: (i) included by the bidder in its pre-qualification application or bid because it brings specific and critical experience and know-how that allow the bidder to meet the qualification requirements for the particular bid; or (ii) appointed by the Borrower. personnel, permit the Bank to inspect3 all accounts, records and other documents relating to the submission of bids and contract performance, and to have them audited by auditors appointed by the Bank. 3 Inspections in this context usually are investigative (i.e., forensic) in nature. They involve fact- finding activities undertaken by the Bank or persons appointed by the Bank to address specific matters related to investigations/audits, such as evaluating the veracity of an allegation of possible Fraud and Corruption, through the appropriate mechanisms. Such activity includes but is not limited to: accessing and examining a firm's or individual's financial records and information, and making copies thereof as relevant; accessing and examining any other documents, data and information (whether in hard copy or electronic format) deemed relevant for the investigation/audit, and making copies thereof as relevant; interviewing staff and other relevant individuals; performing physical inspections and site visits; and obtaining third party verification of information. PROCUREMENT Mongolia : Mongolia Export Development Project PLAN General Information Country: Mongolia Bank’s Approval Date of the Original Procurement Plan: 2017-02-13 2021-05-19 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P147438 GPN Date: 2017-02-09 Project Name: Mongolia Export Development Project Loan / Credit No: IDA / 58790 E Executing Agency(ies): DP Project Implementation Unit WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual EDP/3/GO/003 / Purchase of IT goods for MGF (PCs, UPS, Component 3: Project Request for Single Stage - One IDA / 58790 Post Open - National 13,500.00 11,504.70 Completed 2017-02-14 2017-02-24 2017-03-13 2017-03-10 2017-03-31 Copier machine, Printer and Implementation Support Quotations Envelope Scanner) EDP/3/GO/001 / Accounting Component 3: Project IDA / 58790 Prior Direct Selection Direct 3,150.00 3,107.97 Completed 2017-02-15 2017-03-02 2017-02-20 2017-02-24 2017-03-13 2021-06-23 2017-04-25 software for EDP Implementation Support EDP/1/GO/001 / Component 1: Development Underwriting and insurance IDA / 58790 of a new line of export Prior Direct Selection Direct 60,000.00 0.00 Canceled 2019-01-02 2019-01-07 2019-02-11 2021-02-10 policy management system finance products (MIS) EDP/3/GO/004 / Publications on printing MGF brochure and Component 3: Project Request for Single Stage - One IDA / 58790 Post Open - National 5,000.00 0.00 Canceled 2017-04-08 2017-06-03 2017-07-03 other required manuals Implementation Support Quotations Envelope (multiple contracts) EDP/3/GO/002 / Purchase of Component 3: Project Request for Single Stage - One IDA / 58790 Post Open - National 4,500.00 0.00 Canceled 2017-02-14 2017-02-24 2017-03-10 office furniture Implementation Support Quotations Envelope EDP/3/GO/0002 / Purchase Component 3: Project Request for Single Stage - One IDA / 58790 Post Open - National 4,950.00 4,336.59 Completed 2017-08-12 2017-10-07 2017-03-13 2018-04-05 2017-03-27 of office furniture Implementation Support Quotations Envelope EDP/3/GO/005 / Purchase of Component 3: Project Request for Single Stage - One IDA / 58790 Post Open - National 736.40 640.05 Completed 2017-12-11 2018-02-05 2017-11-28 2018-08-04 2017-12-12 Office Furniture Implementation Support Quotations Envelope EDP/3/GO/006 / Purchase of Component 3: Project Request for Single Stage - One IDA / 58790 Post Open - National 5,482.20 2,333.13 Completed 2017-12-11 2018-02-05 2017-11-21 2018-08-04 2017-12-05 IT Goods for Office Implementation Support Quotations Envelope EDP/21/GO/001 / Print-out Component 2: Export Request for Single Stage - One handbook "Guide to IDA / 58790 competitiveness Post Open - National 2,000.00 0.00 Canceled 2018-09-05 2018-10-31 2019-04-29 Quotations Envelope exporting" enhancement. EDP/21/GO/002 / Printing Component 2: Export out handbooks for Mongolian Request for Single Stage - One IDA / 58790 competitiveness Post Open - National 2,000.00 0.00 Canceled 2018-12-08 2019-02-02 2019-03-04 councils and diplomats in Quotations Envelope enhancement. abroad. G-3-1B/20 / PIU office Component 3: Project Request for Single Stage - One equipment (refrig., IDA / 58790 Post Limited 5,000.00 4,441.37 Signed 2020-03-30 2020-06-25 2020-05-25 2020-07-06 2020-06-08 Implementation Support Quotations Envelope microwave, water dispenser, and etc) G-3-1A/20 / PIU office Component 3: Project Request for Single Stage - One equipment (pcs, desktops, IDA / 58790 Post Limited 10,000.00 10,165.03 Completed 2020-03-30 2020-06-18 2020-05-25 2020-07-06 2020-06-08 2020-07-25 Implementation Support Quotations Envelope laptop, ups and etc.) G-3-2A/20 / PIU office Component 3: Project Request for Single Stage - One furniture (desks, chairs, filing IDA / 58790 Post Limited 10,000.00 8,513.09 Completed 2020-03-30 2020-06-18 2020-05-25 2020-07-06 2020-05-28 2020-08-07 Implementation Support Quotations Envelope cabinets, and etc) G-3-2B/20 / PIU office furniture (training room tables Component 3: Project Request for Single Stage - One IDA / 58790 Post Limited 5,000.00 3,585.39 Completed 2020-03-30 2020-06-18 2020-06-03 2020-07-06 2020-06-06 2020-07-10 chairs, boards, credenzas, Implementation Support Quotations Envelope small items and etc) G-3-3/20 / Printing of the Component 2: Export Pending Request for Single Stage - One project introduction and IDA / 58790 competitiveness Post Limited 10,000.00 0.00 Implementati 2020-10-20 2020-12-15 2021-01-14 Quotations Envelope brochures enhancement. on NCS-3-1/20 / Service to Under Component 3: Project Request for Single Stage - One develop and maximize public IDA / 58790 Post Open - National 20,000.00 0.00 Implementati 2020-10-20 2020-12-15 2021-06-13 Implementation Support Quotations Envelope awareness of the project on G-2-33/21 / Procurement of Component 2: Export Under research and studies from IDA / 58790 competitiveness Post Direct Selection Direct 25,000.00 0.00 Implementati 2021-03-26 2021-04-09 2021-03-31 2021-05-05 2021-11-01 International Research enhancement. on Institutes Pending G-4-38/21 / Equipment for Component 3: Project Request for Single Stage - One IDA / 58790 Post Open - National 15,000.00 0.00 Implementati 2021-04-29 2021-07-09 2021-08-08 Project Implementation Unit Implementation Support Quotations Envelope on Page 1 G-3-1/21 / Provide necessary laboratory equipment for Central Leather Laboratory of Food, Agriculture, Light Industry Component 3: Strengthening Pending Single Stage - One Research and Development IDA / 58790 Certification Services and Post Request for Bids Open - International 1,000,000.00 0.00 Implementati 2021-08-01 2021-08-16 2021-09-27 2021-10-27 2021-12-01 2022-05-30 Envelope Center and Central Laboratory Quality Management on for Wool and Cashmere Testing of Light industry Research and Development Institute NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NCS-2-34/21 / Translation Component 2: Export Under Request for Single Stage - One service for International IDA / 58790 competitiveness Post Limited 15,000.00 0.00 Implementati 2021-04-19 2021-05-29 2021-12-31 Quotations Envelope studies and research papers enhancement. on CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual EDP/3/CS/004 / Auditng of Consultant Component 3: Project PMU accounts (National IDA / 58790 Post Qualification Open - National 7,500.00 0.00 Canceled 2018-03-01 2018-03-22 2018-05-05 2018-06-04 2018-07-09 2018-10-07 Implementation Support consulting firms) Selection EDP/3/CS/0003 / National IT consulting firm for development of Project Consultant Implementation Monitoring Component 3: Project IDA / 58790 Prior Qualification Open - National 20,000.00 19,950.00 Completed 2017-07-01 2017-06-22 2017-07-22 2017-09-04 2017-10-16 2017-10-04 2020-03-25 2017-11-08 2017-10-20 2018-05-07 2018-02-27 Information System (PIMIS) to Implementation Support Selection register, track, monitor and report the project implementation EDP/1/CS/002 / Consultant or consultancy firm to conduct comprehensive Component 1: Development Consultant research along with client IDA / 58790 of a new line of export Post Qualification Open - National 60,000.00 0.00 Canceled 2017-06-05 2017-06-26 2017-08-09 2017-09-08 2017-10-13 2018-04-11 survey focusing on SME's on finance products Selection the market demand in the areas of export insurance products EDP/21/CS/029 / National Component 2: Export Consultant consulting firm to conduct IDA / 58790 competitiveness Post Qualification Open - National 36,800.00 0.00 Canceled 2018-07-31 2018-08-21 2018-10-04 2018-11-03 2018-12-08 2019-06-06 research and develop road- enhancement. Selection mapping of IT export services. EDP/21/CS/030 / National Component 2: Export Consultant consulting firm to conduct IDA / 58790 competitiveness Post Qualification Open - National 10,000.00 0.00 Canceled 2018-09-24 2018-10-15 2018-11-28 2018-12-28 2019-02-01 2019-07-31 needs assessment of the enhancement. Selection Foreign Academy of MNCCI EDP/1/CS/008 / Master service agreement with an international partner who will Component 1: Development Quality And Cost- provide technical assistance IDA / 58790 of a new line of export Prior Open - International 500,000.00 0.00 Canceled 2019-03-25 2019-04-15 2019-05-29 2019-06-26 2019-07-26 2019-08-30 2019-10-13 2020-04-10 Based Selection for institutional development, finance products product development and capacity building Component 2: Export Consultant CS-2-4/20 / Export process IDA / 58790 competitiveness Post Qualification Open - National 20,000.00 0.00 Canceled 2020-04-20 2020-07-27 2020-05-11 2020-06-24 2020-07-24 2020-08-28 2020-11-26 analysis enhancement. Selection Component 2: Export Consultant CS-2-4*/20 / Export Process Under IDA / 58790 competitiveness Post Qualification Open - National 30,000.00 0.00 2020-08-13 2020-08-12 2020-09-03 2020-10-17 2020-11-16 2020-12-21 2021-02-19 Analysis Implementation enhancement. Selection CS-2-21/20 / The consultancy to support export Component 2: Export Consultant Under value added production and IDA / 58790 competitiveness Post Qualification Open - National 50,000.00 0.00 2020-10-01 2020-10-19 2020-10-22 2020-12-05 2021-01-04 2021-02-08 2021-06-08 Implementation create a favorable tax enhancement. Selection environment CS-2-23/20 / Research and Component 2: Export Consultant recommendations on available Under IDA / 58790 competitiveness Post Qualification Open - National 50,000.00 0.00 2020-10-01 2020-12-08 2020-10-22 2020-12-05 2021-01-04 2021-02-08 2021-06-08 opportunities and actual Implementation enhancement. Selection export in service trade CS-2-24/20 / The consultancy to identify unofficial export data and Component 2: Export Consultant Under develop the recommendations IDA / 58790 competitiveness Post Qualification Open - National 30,000.00 0.00 2020-10-01 2020-10-19 2020-10-22 2020-12-05 2021-01-04 2021-02-08 2021-05-09 Implementation (on border points of Russian enhancement. Selection Federation and People's Republic of China) CS-3-27/20 / The Consultant Component 3: Project consultancy for external IDA / 58790 Post Qualification Open - National 30,000.00 0.00 Canceled 2020-11-01 2020-11-22 2021-01-05 2021-02-04 2021-03-11 2021-03-23 Implementation Support auditing and monitoring Selection CS-2-5A/20 / Market Component 2: Export Consultant research for exporting meat IDA / 58790 competitiveness Post Qualification Open - National 100,000.00 0.00 Canceled 2020-09-15 2020-10-06 2020-11-19 2020-12-19 2021-01-23 2021-05-23 and meat products enhancement. Selection CS-2-5B/20 / Market Component 2: Export Consultant research for exporting fruit IDA / 58790 competitiveness Post Qualification Open - National 100,000.00 0.00 Canceled 2020-03-25 2020-04-15 2020-05-29 2020-06-28 2020-08-02 2021-01-29 and dairy products enhancement. Selection CS-2-5C/20 / Market Component 2: Export Consultant research for exporting natural IDA / 58790 competitiveness Post Qualification Open - National 100,000.00 0.00 Canceled 2020-03-25 2020-04-15 2020-05-29 2020-06-28 2020-08-02 2021-01-29 fibers and byproducts enhancement. Selection Page 2 CS-2-18/21 / Market reseach for potential exporting possibility of major Component 2: Export Consultant Pending well known unique IDA / 58790 competitiveness Post Qualification Open - National 60,000.00 0.00 2021-05-17 2021-06-07 2021-07-21 2021-08-20 2021-09-24 2021-12-23 Implementation agricultural products of enhancement. Selection Mongolia on consumer preferences and statutory requirements CS-2-19/21 / Prime Meat Component 2: Export Consultant Market Research for new Pending IDA / 58790 competitiveness Post Qualification Open - National 80,000.00 0.00 2021-05-17 2021-06-07 2021-07-21 2021-08-20 2021-09-24 2021-12-23 market opportunities other Implementation enhancement. Selection than China CS-2-20/21 / Market Component 2: Export Consultant research for export oriented Pending IDA / 58790 competitiveness Post Qualification Open - National 45,000.00 0.00 2021-05-17 2021-06-07 2021-07-21 2021-08-20 2021-09-24 2021-12-23 (potential) food products and Implementation enhancement. Selection its export requirements CS-2-21/21 / Market research for exporting crop Component 2: Export Consultant Pending products from Mongolia on IDA / 58790 competitiveness Post Qualification Open - National 45,000.00 0.00 2021-05-21 2021-06-11 2021-07-25 2021-08-24 2021-09-28 2021-12-27 Implementation consumer preferences and enhancement. Selection statutory requirements CS-1-2/21 / International Component 1: Development Consultant Consultancy service to provide Pending IDA / 58790 of a new line of export Post Qualification Open - National 72,000.00 0.00 2021-05-21 2021-06-11 2021-07-25 2021-08-24 2021-09-28 2022-03-27 information service on export Implementation finance products Selection credit insurance INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual EDP/3/CS/001 / Training coordinator for sub- component 2.1. During the first year, the contract shall be Individual signed with a consultant for Component 3: Project IDA / 58790 Post Consultant Open 57,000.00 13,800.00 Completed 2017-02-13 2017-02-02 2017-02-16 2017-02-20 2017-02-16 2017-02-20 2017-02-20 2017-02-20 2021-02-19 2019-02-28 the duration of 12 months, Implementation Support Selection with 3 months probationary period. The contract will be extended on annual basis for next 3 years. EDP/1/CS/003 / Short term senior international consultants for institutional Component 1: Development Individual development of EID (EIS) IDA / 58790 of a new line of export Prior Consultant Open 60,000.00 0.00 Canceled 2017-06-05 2017-07-24 2017-08-14 2017-09-18 2018-01-16 which will provide finance products Selection international best practices in export trade credit insurance and product development EDP/1/CS/004 / Short term consultant to conduct Component 1: Development Individual assesment on existing export IDA / 58790 of a new line of export Prior Consultant Open 40,000.00 13,500.00 Completed 2017-06-05 2020-03-24 2017-07-24 2018-01-22 2017-08-14 2020-05-27 2017-09-18 2018-01-22 2018-03-17 2019-01-21 insurance related mongolian finance products Selection laws, rules and regulations jointly with EID staff EDP/1/CS/005 / Resident Component 1: Development Individual advisor/international expert IDA / 58790 of a new line of export Prior Consultant Open 80,000.00 0.00 Canceled 2018-02-05 2018-03-10 2018-03-31 2018-04-06 2019-04-06 on trade credit insurance finance products Selection EDP/1/CS/006 / Short term senior international consultants for institutional Component 1: Development Individual development of EID (EIS) IDA / 58790 of a new line of export Post Consultant Open 40,000.00 0.00 Canceled 2018-02-05 2018-03-26 2018-04-16 2018-05-21 2018-08-19 pricing methodology, finance products Selection underwriting guidelines, optimization of claim payment and recovery processes) EDP/2-1/CS/003 / Local consultants/Trainers to share Component 2: Export Individual experience, know-how, IDA / 58790 competitiveness Post Consultant Open 20,000.00 2,400.00 Completed 2017-06-05 2017-06-06 2017-07-24 2017-07-05 2017-08-14 2017-07-05 2017-09-18 2017-07-05 2017-12-17 2017-07-31 seminars on export enhancement. Selection development (multiple contracts) EDP/2-1/CS/004 / Component 2: Export Individual Consultants/Hiring sign IDA / 58790 competitiveness Post Consultant Open 1,000.00 0.00 Canceled 2017-06-05 2017-07-08 2017-07-29 2017-09-02 2018-09-02 language interpreters enhancement. Selection (multiple contracts) EDP/2-2/CS/002 / MGF Component 2: Export Individual Business Development IDA / 58790 competitiveness Prior Consultant Open 89,400.00 34,800.00 Completed 2017-03-27 2017-06-05 2017-05-15 2017-04-11 2017-06-05 2020-03-24 2017-07-10 2017-04-11 2021-07-09 2018-04-10 Specialist (Local consultant) enhancement. Selection EDP/1/CS/001 / Coordinating consultant/Local Component 1: Development consultant of Comp#1 for IDA / 58790 of a new line of export Prior Direct Selection Direct 36,000.00 0.00 Canceled 2017-04-03 2017-04-13 2017-06-17 2017-12-14 supporting AgRe (duration of finance products 2 years) EDP/1/CS/0001 / Coordinating consultant/Local Component 1: Development Individual consultant of Comp#1 for IDA / 58790 of a new line of export Prior Consultant Direct 36,000.00 47,550.00 Completed 2017-05-01 2017-06-12 2017-05-11 2017-05-10 2017-06-01 2020-07-29 2017-07-06 2017-05-10 2018-01-02 2019-12-31 supporting AgRe (duration of finance products Selection 2 years) EDP/2-2/CS/004 / IT consulting firm to develop customized registration Component 2: Export system-Matching Grant IDA / 58790 competitiveness Prior Direct Selection Direct 6,000.00 0.00 Canceled 2017-04-03 2017-03-28 2017-04-13 2017-06-01 2017-08-30 Administration System (MGAS) enhancement. for recording all MG related activities, including maitenance fee Page 3 EDP/3/CS/003 / National IT consulting firm for development of Project Implementation Monitoring Component 3: Project IDA / 58790 Prior Direct Selection Direct 14,000.00 0.00 Canceled 2017-06-05 2017-03-28 2017-06-15 2017-08-19 2017-09-18 Information System (PIMIS) for Implementation Support monitoring overall project activities, including maintenance fee EDP/3/CS/005 / Employment Individual of PIU staff: Project Component 3: Project IDA / 58790 Prior Consultant Direct 120,000.00 3,738.33 Completed 2017-06-21 2017-06-23 2017-07-01 2017-06-29 2017-07-22 2020-03-25 2017-08-26 2017-06-29 2018-02-22 2019-06-30 Coordinator (duration of 4 Implementation Support Selection years) EDP/3/CS/006 / Employment Individual Component 3: Project of PIU staff: Procurement IDA / 58790 Prior Consultant Direct 86,400.00 1,403.38 Completed 2017-06-21 2017-06-23 2017-07-01 2017-06-29 2017-07-22 2020-03-25 2017-08-26 2017-06-29 2018-02-22 2018-06-30 Implementation Support specialist (duration of 4 years) Selection EDP/3/CS/007 / Employment Individual of PIU staff: Financial Component 3: Project IDA / 58790 Prior Consultant Direct 86,400.00 2,723.23 Completed 2017-06-21 2017-06-23 2017-07-01 2017-06-29 2017-07-22 2020-03-25 2017-08-26 2017-06-29 2018-02-22 2019-06-30 Management Specialist Implementation Support Selection (duration of 4 years) EDP/3/CS/008 / Employment Individual of PIU staff: Monitoring and Component 3: Project IDA / 58790 Prior Consultant Direct 86,400.00 1,343.76 Completed 2017-06-21 2017-06-23 2017-07-01 2017-06-29 2017-07-22 2020-05-27 2017-08-26 2017-06-29 2018-02-22 2018-06-30 Evaluation Specialist (duration Implementation Support Selection of 4 years) EDP/3/CS/009 / Employment Individual Component 3: Project of PIU staff: Procurement IDA / 58790 Prior Consultant Direct 72,000.00 857.55 Terminated 2017-06-21 2017-06-23 2017-07-01 2017-06-29 2017-07-22 2020-05-27 2017-08-26 2017-06-29 2018-02-22 Implementation Support assistant (duration of 4 years) Selection EDP/1/CS/0002 / Consultant to conduct comprehensive research along with client Component 1: Development Individual survey focusing on SME's on IDA / 58790 of a new line of export Post Consultant Open 60,000.00 38,550.00 Completed 2017-08-04 2017-08-11 2017-09-22 2017-09-21 2017-10-13 2017-10-20 2017-11-17 2017-10-20 2018-05-16 2017-12-23 the market demand in the finance products Selection areas of export insurance products EDP/2-2/CS/001 / Component 2: Export Individual International consultant/MGF IDA / 58790 competitiveness Prior Consultant Open 120,000.00 0.00 Canceled 2017-06-05 2017-03-17 2017-07-24 2017-08-14 2017-09-18 2018-09-18 coordinator to support MGF enhancement. Selection team EDP/2-2/CS/005 / MGF Component 2: Export Individual Business Development IDA / 58790 competitiveness Prior Consultant Open 90,000.00 18,000.00 Terminated 2017-08-14 2017-08-15 2017-10-02 2017-10-12 2017-10-23 2020-03-25 2017-11-27 2017-10-12 2018-05-26 Specialist (Local consultant- enhancement. Selection Finance) EDP/2-2/CS/006 / MGF Component 2: Export Individual Business Development IDA / 58790 competitiveness Prior Consultant Open 90,000.00 36,000.00 Completed 2017-08-14 2017-08-15 2017-10-02 2017-09-06 2017-10-23 2020-05-27 2017-11-27 2017-09-06 2018-05-26 2018-09-05 Specialist (Local Consultant- enhancement. Selection Marketing) EDP/2-2/CS/007 / National consultants (2) for conducting Component 2: Export Individual market research for IDA / 58790 competitiveness Post Consultant Open 4,000.00 4,000.00 Completed 2017-08-14 2017-08-01 2017-10-02 2017-08-23 2017-10-23 2017-08-30 2017-11-27 2017-08-30 2018-05-26 2017-11-30 component 2 "Export enhancement. Selection competitiveness enhancement". EDP/2-2/CS/0001 / Component 2: Export Individual International consultant/MGF IDA / 58790 competitiveness Prior Consultant Open 120,000.00 0.00 Canceled 2017-08-14 2017-08-08 2017-10-02 2017-10-23 2017-11-27 2018-05-26 coordinator to support MGF enhancement. Selection team EDP/2-1/CS/001 / Consultancy service on conducting export-related Component 2: Export Individual research which would benefit IDA / 58790 competitiveness Post Consultant Open 50,000.00 5,400.00 Terminated 2017-09-11 2017-10-12 2017-10-30 2017-11-27 2017-11-20 2017-11-27 2017-12-25 2017-11-27 2018-12-25 specific export-oriented enhancement. Selection industries or other group of exporters (multiple contracts) EDP/2-1/CS/002 / International consultants/Trainers to share Component 2: Export Individual experience, know-how, IDA / 58790 competitiveness Post Consultant Open 60,000.00 9,550.00 Completed 2017-09-18 2017-09-13 2017-11-06 2017-10-03 2017-11-27 2017-10-03 2018-01-01 2017-10-03 2019-01-01 2018-01-22 seminars on export enhancement. Selection development (multiple contracts) EDP/2-2/CS/009 / National consultant to develop public Component 2: Export Individual awareness framework for IDA / 58790 competitiveness Post Consultant Open 1,000.00 0.00 Canceled 2017-10-31 2017-12-26 2018-01-16 2018-02-20 2018-08-19 component 2.2 "Matching enhancement. Selection Grant Facility" of the Export Development project EDP/2-2/CS/1 / International Component 2: Export Individual consultant to support MGF IDA / 58790 competitiveness Prior Consultant Open 60,000.00 25,400.00 Completed 2017-12-25 2017-12-18 2018-02-12 2018-03-23 2018-03-05 2020-03-25 2018-04-09 2018-04-12 2018-10-06 2018-11-13 team enhancement. Selection EDP/2-2/CS/01 / Component 2: Export Individual International consultant/MGF IDA / 58790 competitiveness Prior Consultant Open 110,000.00 0.00 Canceled 2017-08-21 2017-08-17 2017-10-09 2017-10-30 2017-12-04 2018-12-04 coordinator to support MGF enhancement. Selection team EDP/1/CS/007 / Short term consultant for Institutional development of EID (EIS) Component 1: Development which will provide IDA / 58790 of a new line of export Prior Direct Selection Direct 60,000.00 0.00 Canceled 2018-03-26 2018-04-05 2018-06-02 2018-08-01 international best practices in finance products export trade credit insurance, including product development EDP/2-1/CS/006 / Short term International consultant Component 2: Export to deliver an intensive course IDA / 58790 competitiveness Post Direct Selection Direct 17,500.00 17,500.00 Completed 2018-03-12 2018-03-06 2018-03-22 2018-03-06 2018-05-26 2018-03-06 2018-06-25 2018-06-18 for Mongolian Professional enhancement. Tour Guides Page 4 EDP/2-1/CS/007 / National Component 2: Export Individual consultant to assist the IDA / 58790 competitiveness Post Consultant Open 8,400.00 8,400.00 Terminated 2018-03-26 2018-03-06 2018-05-14 2018-03-14 2018-06-04 2018-03-14 2018-07-09 2018-03-14 2019-07-09 training coordination and enhancement. Selection logistics EDP/21/CS/008 / National consultant to develop e- Component 1: Development Individual learning training module on IDA / 58790 of a new line of export Post Consultant Open 4,500.00 3,000.00 Completed 2018-04-30 2018-05-07 2018-06-18 2018-05-25 2018-07-09 2018-05-28 2018-08-13 2018-05-28 2018-11-11 2018-08-06 Foreign Trade: Module#1-The finance products Selection export cycle EDP/1/CS/010 / International consultant on Institutional Development of Export Credit Component 1: Development Individual Insurance in Mongolia. The IDA / 58790 of a new line of export Post Consultant Open 30,000.00 29,850.00 Completed 2018-04-30 2018-05-05 2018-06-18 2018-05-10 2018-07-09 2018-05-17 2018-08-13 2018-05-17 2018-09-12 2018-07-04 consultant will focus on finance products Selection scoping the master service agreement EDP/1/CS/011 / International consultant on Institutional Development of Export Credit Component 1: Development Individual Insurance in Mongolia. The IDA / 58790 of a new line of export Prior Consultant Direct 30,000.00 0.00 Canceled 2018-05-31 2018-06-10 2018-07-01 2018-08-05 2018-09-04 consultant will focus on finance products Selection drafting the TOR and the Master service agreement. EDP/21/CS/009 / National consultant to develop e- Component 1: Development Individual learning training module on IDA / 58790 of a new line of export Post Consultant Open 4,500.00 4,500.00 Completed 2018-04-30 2018-05-07 2018-06-18 2018-05-25 2018-07-09 2018-05-28 2018-08-13 2018-05-28 2018-11-11 2018-09-05 Foreign trade. The consultant finance products Selection will develop module # 2: The Export Management EDP/21/CS/010 / National consultant to develop e- Component 1: Development Individual learning training module on IDA / 58790 of a new line of export Post Consultant Open 4,500.00 4,500.00 Completed 2018-04-30 2018-05-07 2018-06-18 2018-05-25 2018-07-09 2018-05-28 2018-08-13 2018-05-28 2018-11-11 2018-06-12 Foreign Trade: Module#3- finance products Selection Export documentation EDP/21/CS/011 / National consultant to develop e- Component 1: Development Individual learning training module on IDA / 58790 of a new line of export Post Consultant Open 4,500.00 2,250.00 Completed 2018-04-30 2018-05-07 2018-06-18 2018-05-25 2018-07-09 2018-05-28 2018-08-13 2018-05-28 2018-11-11 2018-09-26 Foreign Trade: Module#4- finance products Selection Understand Incoterms Used for International Trade EDP/21/CS/012 / National consultant to develop e- Component 1: Development Individual learning training module on IDA / 58790 of a new line of export Post Consultant Open 4,500.00 4,500.00 Completed 2018-04-30 2018-05-07 2018-06-18 2018-05-25 2018-07-09 2018-05-28 2018-08-13 2018-05-28 2018-11-11 2018-09-26 Foreign Trade: Module#5 - finance products Selection International transport services EDP/21/CS/013 / National consultant to develop e- Component 1: Development Individual learning training module on IDA / 58790 of a new line of export Post Consultant Open 4,500.00 4,500.00 Completed 2018-04-30 2018-05-07 2018-06-18 2018-05-25 2018-07-09 2018-05-28 2018-08-13 2018-05-28 2018-11-11 2018-09-27 Foreign Trade: Module#6 - finance products Selection International trade and trade agreement EDP/21/CS/014 / National consultant to develop e- Component 1: Development Individual learning training module on IDA / 58790 of a new line of export Post Consultant Open 4,500.00 4,500.00 Completed 2018-04-30 2018-05-07 2018-06-18 2018-05-25 2018-07-09 2018-05-28 2018-08-13 2018-05-28 2018-11-11 2018-09-26 Foreign Trade: Module#7 - finance products Selection Tax environment of Mongolia EDP/21/CS/015 / National consultant to design e- learning video course, video Component 1: Development Individual record, upload to the project IDA / 58790 of a new line of export Post Consultant Open 6,750.00 0.00 Canceled 2018-05-14 2018-07-02 2018-07-23 2018-08-27 2018-11-25 website. Senior shooter to finance products Selection record e-learning training course. EDP/21/CS/016 / National consultant to design e- learning video courses, video record and upload to the Component 1: Development Individual project website. The video IDA / 58790 of a new line of export Post Consultant Open 5,400.00 0.00 Canceled 2018-05-28 2018-07-16 2018-08-06 2018-09-10 2018-12-09 shooter to record e-learning finance products Selection training course, design presentations and maintain the website training session. EDP/21/CS/017 / National Component 1: Development Individual consultant to translate e- IDA / 58790 of a new line of export Post Consultant Open 4,500.00 0.00 Canceled 2018-05-28 2018-07-16 2018-08-06 2018-09-10 2018-12-09 learning course from finance products Selection Mongolian to Kazakh language EDP/21/CS/018 / National consultant to translate e- learning course for the Component 2: Export Individual disabled people who has IDA / 58790 competitiveness Post Consultant Open 4,500.00 0.00 Canceled 2018-06-04 2018-07-23 2018-08-13 2018-09-17 2018-12-16 difficulty in speaking and enhancement. Selection listening. The consultant will translate Module 1-3 EDP/21/CS/019 / National consultant to translate e- learning course for the Component 2: Export Individual disabled people who has IDA / 58790 competitiveness Post Consultant Open 4,500.00 0.00 Canceled 2018-06-04 2018-07-23 2018-08-13 2018-09-17 2018-12-16 difficulty in speaking and enhancement. Selection listening. The consultant will translate Module 4-7 EDP/21/CS/020 / National consultant to create database Component 2: Export Individual on Foreign Trade Issues IDA / 58790 competitiveness Post Consultant Open 1,800.00 0.00 Canceled 2018-07-30 2018-09-17 2018-10-08 2018-11-12 2019-02-10 including researches, study enhancement. Selection reports, international standards Page 5 EDP/21/CS/021 / National consultant to create database Component 2: Export Individual on Foreign Trade Issues IDA / 58790 competitiveness Post Consultant Open 1,800.00 0.00 Canceled 2018-07-30 2018-09-17 2018-10-08 2018-11-12 2019-02-10 including legal framework, enhancement. Selection policies and statistical data EDP/21/CS/022 / Component 2: Export Individual International consultant to IDA / 58790 competitiveness Post Consultant Direct 15,000.00 0.00 Canceled 2018-11-30 2018-12-10 2018-12-31 2019-02-04 2019-04-05 improve cashmere product to enhancement. Selection export EDP/21/CS/023 / National Component 2: Export Individual consultant to mentor the SMEs IDA / 58790 competitiveness Post Consultant Open 6,000.00 0.00 Canceled 2018-07-30 2018-09-17 2018-10-08 2018-11-12 2019-02-10 (1-3) in product designing of enhancement. Selection the cashmere product EDP/21/CS/024 / National Component 2: Export Individual consultant to mentor the SMEs IDA / 58790 competitiveness Post Consultant Open 6,000.00 0.00 Canceled 2018-07-30 2018-09-17 2018-10-08 2018-11-12 2019-05-11 (4-6) in product designing of enhancement. Selection the cashmere product EDP/21/CS/025 / National Component 2: Export Individual consultant to mentor the SMEs IDA / 58790 competitiveness Post Consultant Open 6,000.00 0.00 Canceled 2018-07-30 2018-09-17 2018-10-08 2018-11-12 2019-05-11 (7-9) in product designing of enhancement. Selection the cashmere product EDP/21/CS/026 / National consultant to develop skills and knowledge of SME's IT Component 2: Export Individual staff to develop export. The IDA / 58790 competitiveness Post Consultant Open 7,500.00 0.00 Canceled 2018-07-30 2018-09-17 2018-10-08 2018-11-12 2019-05-11 consultant will focus on enhancement. Selection Envanto Market and Themeforest: Coding EDP/21/CS/027 / National consultant to develop skills and knowledge of SME's IT Component 2: Export Individual staff to develop export. The IDA / 58790 competitiveness Post Consultant Open 7,500.00 0.00 Canceled 2018-07-30 2018-09-17 2018-10-08 2018-11-12 2019-05-11 consultant will focus on the enhancement. Selection subject of Themeforest: Design EDP/21/CS/028 / National consultant to develop skills Component 2: Export Individual and knowledge of SME's IT IDA / 58790 competitiveness Post Consultant Open 7,500.00 0.00 Canceled 2018-07-30 2018-09-17 2018-10-08 2018-11-12 2019-05-11 staff to develop export. The enhancement. Selection consultant will focus on the subject of Upload and Support EDP/21/CS/031 / National consultant to develop Component 2: Export Individual handbook on legal IDA / 58790 competitiveness Post Consultant Open 3,600.00 0.00 Canceled 2018-07-30 2018-09-17 2018-10-08 2018-11-12 2019-05-11 environment for Mongolian enhancement. Selection councils and diplomats in abroad. EDP/21/CS/032 / National consultant to develop Component 2: Export Individual handbook on International IDA / 58790 competitiveness Post Consultant Open 3,600.00 0.00 Canceled 2018-08-06 2018-09-24 2018-10-15 2018-11-19 2019-02-17 Standards for Mongolian enhancement. Selection councils and diplomats in abroad. EDP/21/CS/033 / National consultant to develop Component 2: Export Individual handbook on Foreign Trade IDA / 58790 competitiveness Post Consultant Open 3,600.00 0.00 Canceled 2018-07-30 2018-09-17 2018-10-08 2018-11-12 2019-02-10 Issues for Mongolian councils enhancement. Selection and diplomats in abroad. EDP/22/CS/012 / MGF Component 2: Export Individual Business Development IDA / 58790 competitiveness Prior Consultant Open 89,400.00 17,400.00 Completed 2018-04-30 2020-03-25 2018-06-18 2018-05-11 2018-07-09 2020-05-28 2018-08-13 2018-05-11 2022-08-12 2019-05-10 Specialist (Local consultant) enhancement. Selection EDP/22/CS/007 / MGF Component 2: Export Individual Administrative Assistant IDA / 58790 competitiveness Post Consultant Open 47,400.00 9,000.00 Terminated 2018-04-30 2017-03-13 2018-05-24 2017-04-10 2018-05-27 2017-04-10 2018-06-02 2017-04-10 2022-06-01 2017-04-10 (Local consultant) enhancement. Selection EDP/3/CS/002 / Environment Individual Component 3: Project and Social screening IDA / 58790 Post Consultant Open 4,500.00 4,500.00 Completed 2018-04-30 2018-03-28 2018-06-02 2018-05-02 2018-06-23 2018-05-02 2018-07-28 2018-06-05 2018-10-26 2018-09-20 Implementation Support consultant Selection EDP/21/CS/034 / International consultant to Component 2: Export Individual conduct 1st part of 3-day IDA / 58790 competitiveness Post Consultant Direct 4,000.00 3,240.00 Completed 2018-04-30 2018-04-23 2018-05-10 2018-05-07 2018-05-31 2018-05-07 2018-07-05 2018-05-07 2018-07-10 2018-05-25 workshop on "Benefits of WTO enhancement. Selection agreements for Mongolian Non-mining Exporters" EDP/21/CS/035 / International consultant to Component 2: Export Individual conduct 2nd part of the 3-day IDA / 58790 competitiveness Post Consultant Direct 4,000.00 3,240.00 Completed 2018-04-30 2018-04-23 2018-05-10 2018-05-07 2018-05-31 2018-05-07 2018-07-05 2018-05-07 2018-07-10 2018-06-18 training on "Benefits of WTO enhancement. Selection agreements for Mongolian Non-mining Exporters". EDP/21/CS/036 / Short term Component 2: Export Individual national consultant to conduct IDA / 58790 competitiveness Post Consultant Open 7,000.00 0.00 Canceled 2018-06-25 2018-08-13 2018-09-03 2018-10-08 2019-01-16 a study on tourism market enhancement. Selection strategy EDP/21/CS/15 / National consultant to design e- learning video course, video Component 1: Development Individual record, upload to the project IDA / 58790 of a new line of export Post Consultant Direct 6,750.00 0.00 Canceled 2018-09-10 2018-09-20 2018-10-11 2018-11-15 2019-05-14 website. Senior shooter to finance products Selection record e-learning training course. Page 6 EDP/21/CS/16 / National consultant to design e- learning video courses, video record and upload to the Component 1: Development Individual project website. The video IDA / 58790 of a new line of export Post Consultant Direct 5,400.00 0.00 Canceled 2018-09-10 2018-09-20 2018-10-11 2018-11-15 2019-05-14 shooter to record e-learning finance products Selection training course, design presentations and maintain the website training session. EDP/21/CS/17 / National Component 1: Development Individual consultant to translate e- IDA / 58790 of a new line of export Post Consultant Direct 4,500.00 0.00 Canceled 2018-09-10 2018-09-20 2018-10-11 2018-11-15 2019-05-14 learning course from finance products Selection Mongolian to Kazakh language EDP/21/CS/18 / National Component 2: Export Individual consultant to translate e- IDA / 58790 competitiveness Post Consultant Direct 4,500.00 0.00 Canceled 2018-09-10 2018-09-20 2018-10-11 2018-11-15 2019-05-14 learning course from enhancement. Selection Mongolian to Kazakh language EDP/21/CS/19 / National Component 2: Export Individual consultant to translate e- IDA / 58790 competitiveness Post Consultant Direct 4,500.00 0.00 Canceled 2018-09-10 2018-09-20 2018-10-11 2018-11-15 2019-05-14 learning course from enhancement. Selection Mongolian to Kazakh language EDP/3/CS/010 / Employment Individual Component 3: Project of PIU : Procurement Specialist IDA / 58790 Prior Consultant Open 86,400.00 1,489.74 Completed 2018-09-24 2018-09-12 2018-11-12 2018-08-30 2018-12-03 2020-03-25 2019-01-07 2018-08-30 2023-01-06 2019-06-30 Implementation Support (duration 4 years) Selection EDP/3/CS/011 / Employment Individual of PIU Staff: Procurement Component 3: Project IDA / 58790 Prior Consultant Open 72,000.00 676.12 Terminated 2018-09-24 2018-09-12 2018-11-12 2018-08-30 2018-12-03 2020-05-27 2019-01-07 2018-08-30 2023-01-06 Assistant ( duration of 4 Implementation Support Selection years) Individual EDP/3/CS/08 / Monitoring Component 3: Project IDA / 58790 Prior Consultant Open 86,400.00 16,686.10 Terminated 2018-10-22 2020-05-27 2018-12-10 2018-11-01 2018-12-31 2020-06-12 2019-02-04 2018-11-01 2019-08-03 and evaluation specialist Implementation Support Selection EDP/2-1/CS/07 / National Component 2: Export Individual consultant to assist the IDA / 58790 competitiveness Post Consultant Open 8,400.00 8,400.00 Completed 2018-03-06 2018-02-27 2018-04-24 2018-06-18 2018-05-15 2018-06-18 2018-06-19 2018-06-18 2019-06-19 2019-06-21 training coordination and enhancement. Selection logistics Component 2: Export Individual EDP/22/CS/008 / MGF IDA / 58790 competitiveness Post Consultant Open 9,000.00 9,000.00 Terminated 2017-03-17 2017-03-13 2017-04-23 2018-01-15 2017-04-28 2018-01-15 2017-05-17 2018-01-15 2018-05-17 Administrative Assistant enhancement. Selection Component 2: Export Individual EDP/22/CS/009 / MGF IDA / 58790 competitiveness Post Consultant Open 9,000.00 11,160.00 Completed 2017-03-17 2017-03-31 2018-01-14 2018-10-04 2018-01-15 2018-10-04 2018-02-05 2018-10-04 2018-08-04 2019-12-31 Administrative Assistant enhancement. Selection Component 2: Export Individual EDP/22/CS/010 / MGF IDA / 58790 competitiveness Post Consultant Open 9,000.00 9,000.00 Terminated 2017-03-17 2017-03-17 2018-09-25 2017-05-03 2018-09-26 2017-05-03 2018-10-18 2017-05-03 2019-04-16 Administrative Assistant enhancement. Selection EDP/2-2/CS/003 / MGF Component 2: Export Individual Administrative Assistant IDA / 58790 competitiveness Post Consultant Open 47,400.00 9,000.00 Terminated 2017-03-06 2017-03-13 2017-03-30 2017-04-10 2017-04-02 2017-04-10 2017-04-08 2017-04-10 2021-04-07 (Local consultant) enhancement. Selection Individual EDP/3/CS/8 / Monitoring and Component 3: Project IDA / 58790 Prior Consultant Open 86,400.00 0.00 Canceled 2018-09-26 2018-11-14 2018-12-05 2019-01-09 2020-01-09 Evaluation Specialist Implementation Support Selection EDP/21/CS/20 / International Component 2: Export Individual consultant to review and IDA / 58790 competitiveness Post Consultant Open 40,000.00 0.00 Canceled 2018-11-27 2019-01-15 2019-02-05 2019-03-12 2019-09-08 support the training enhancement. Selection component EDP/2-1/CS/010 / Component 2: Export Individual International consultant to IDA / 58790 competitiveness Post Consultant Open 70,000.00 0.00 Canceled 2018-11-27 2019-01-15 2019-02-05 2019-03-12 2019-09-08 advice and support the enhancement. Selection matching grants facility EDP/1/CS/012 / International consultant to draft the detailed TOR for the Master Component 1: Development Service Agreement and IDA / 58790 of a new line of export Prior Direct Selection Direct 80,000.00 0.00 Canceled 2018-11-27 2018-12-07 2019-02-10 2019-08-09 provide related capacity finance products building and support to the Mongolian National Reinsurance Company EDP/2-2/CS/008 / MGF Component 2: Export Individual Business Development IDA / 58790 competitiveness Prior Consultant Open 54,000.00 18,000.00 Terminated 2017-12-21 2020-03-25 2018-02-08 2018-01-10 2018-03-01 2020-05-28 2018-04-05 2018-01-10 2018-10-02 Specialists (3-year contract) enhancement. Selection EDP/2-2/CS/010 / MGF Component 2: Export Individual Business Development IDA / 58790 competitiveness Prior Consultant Open 54,000.00 18,000.00 Completed 2017-12-21 2020-03-25 2018-02-08 2018-01-10 2018-03-01 2020-06-30 2018-04-05 2018-01-10 2018-10-02 2019-01-10 Specialists (3-year contract) enhancement. Selection EDP/3/CS/02 / Environmental and Social Component 3: Project IDA / 58790 Prior Direct Selection Direct 54,000.00 0.00 Canceled 2018-11-15 2018-11-25 2019-01-29 2019-07-28 screening consultant (duration Implementation Support of 3 years) Individual CS-3-10/20 / PIU Business Component 3: Project IDA / 58790 Post Consultant Open 27,250.00 11,718.12 Signed 2020-03-25 2020-04-09 2020-05-13 2020-05-14 2020-06-03 2020-05-25 2020-06-24 2020-05-18 2021-06-30 development specialist Implementation Support Selection Individual CS-3-11/20 / Export market Component 3: Project IDA / 58790 Post Consultant Open 27,250.00 8,421.12 Signed 2020-03-25 2020-03-27 2020-05-13 2020-05-14 2020-06-03 2020-05-18 2020-06-24 2020-05-18 2021-06-30 analyst Implementation Support Selection CS-3-12/20 / PIU Office Individual Component 3: Project manager- administrative IDA / 58790 Post Consultant Open 13,250.00 4,894.78 Signed 2020-03-25 2020-04-09 2020-05-13 2020-05-15 2020-06-03 2020-05-25 2020-06-24 2020-05-25 2021-06-30 Implementation Support assistant Selection Individual CS-3-13/20 / Training and Component 3: Project IDA / 58790 Post Consultant Open 21,000.00 8,105.33 Signed 2020-03-25 2020-04-09 2020-05-13 2020-05-15 2020-06-03 2020-05-15 2020-06-24 2020-05-18 2021-06-30 expo consultant Implementation Support Selection Page 7 Individual CS-3-14/20 / Sanitary and Component 3: Project IDA / 58790 Post Consultant Open 27,000.00 8,105.33 Signed 2020-03-25 2020-04-20 2020-05-13 2020-05-29 2020-06-03 2020-05-29 2020-06-24 2020-05-29 2021-06-19 Phytosanitary Specialist Implementation Support Selection CS-3-15/20 / Environment Individual Component 3: Project and social impact assessment IDA / 58790 Post Consultant Open 18,000.00 8,105.33 Signed 2020-03-25 2020-04-09 2020-05-13 2020-05-17 2020-06-03 2020-05-17 2020-06-24 2020-05-27 2021-06-19 Implementation Support consultant Selection Component 1: Development Individual CS-1-1/20 / Coordinating IDA / 58790 of a new line of export Post Consultant Open 18,000.00 17,239.08 Signed 2019-01-02 2020-04-23 2019-01-02 2020-01-01 2019-01-02 2020-01-01 2019-01-02 2020-01-01 2019-12-28 consultant for Component 1 finance products Selection Individual Component 3: Project Under CS-3-6/20 / PIU coordinator IDA / 58790 Prior Consultant Open 29,500.00 0.00 2020-01-10 2020-02-21 2020-03-13 2021-04-23 2020-04-06 2021-06-30 Implementation Support Implementation Selection Individual CS-3-7/20 / PIU Component 3: Project Under IDA / 58790 Prior Consultant Open 25,000.00 0.00 2020-01-10 2021-03-31 2020-02-21 2020-02-14 2020-03-13 2020-04-06 2021-06-30 procurement specialist Implementation Support Implementation Selection Individual CS-3-8/20 / PIU financial Component 3: Project Under IDA / 58790 Prior Consultant Open 25,000.00 0.00 2020-01-10 2021-03-31 2020-02-21 2020-03-13 2020-04-06 2021-06-30 specialist Implementation Support Implementation Selection CS-2-3/20 / Needs Component 2: Export Individual assessment and analysis of IDA / 58790 competitiveness Post Consultant Direct 6,000.00 5,866.94 Completed 2020-03-25 2020-03-25 2020-04-04 2020-03-31 2020-04-18 2020-05-09 2020-04-13 2020-05-30 2020-06-02 barrier hindering small and enhancement. Selection medium enterprises’ exports Individual CS-3-9/20 / PIU M&E Component 3: Project IDA / 58790 Post Consultant Open 25,000.00 4.54 Signed 2020-01-10 2020-01-02 2020-02-21 2020-02-18 2020-03-13 2020-02-25 2020-04-06 2020-03-02 2021-06-30 specialist Implementation Support Selection Individual CS-3-16/20 / Business Component 3: Project IDA / 58790 Post Consultant Open 16,800.00 8,119.42 Signed 2020-07-01 2020-07-03 2020-08-19 2020-04-27 2020-09-09 2020-06-24 2020-10-14 2020-07-09 2021-04-12 Development Consultant Implementation Support Selection Individual CS-3-17/20 / Business Component 3: Project Under IDA / 58790 Post Consultant Open 16,800.00 0.00 2020-05-31 2020-07-09 2020-07-19 2020-08-09 2020-09-13 2021-03-12 Development Consultant Implementation Support Implementation Selection Individual CS-3-18/20 / Business Component 3: Project Under IDA / 58790 Post Consultant Open 16,800.00 0.00 2020-07-01 2020-07-03 2020-08-19 2020-09-09 2020-10-14 2021-04-12 Development Consultant Implementation Support Implementation Selection CS-3-19/20 / Associate Individual Component 3: Project Business Development IDA / 58790 Post Consultant Open 14,400.00 6,947.42 Signed 2020-07-01 2020-07-05 2020-08-19 2020-06-30 2020-09-09 2020-07-06 2020-10-14 2020-07-06 2021-04-12 Implementation Support Consultant Selection EDP/2-1/CS/01 / Consultancy service on conducting export-related Component 2: Export Individual research which would benefit IDA / 58790 competitiveness Post Consultant Open 50,000.00 4,500.00 Completed 2017-11-27 2017-10-12 2018-01-15 2017-11-27 2018-02-05 2017-11-27 2018-03-12 2017-11-27 2018-09-08 2018-02-28 specific export-oriented enhancement. Selection industries or other group of exporters (multiple contracts) EDP/2-1/CS/1 / Consultancy service on conducting export- related research which would Component 2: Export Individual benefit specific export- IDA / 58790 competitiveness Post Consultant Open 50,000.00 4,500.00 Completed 2017-11-27 2017-10-12 2018-01-15 2017-11-27 2018-02-05 2017-11-27 2018-03-12 2017-11-27 2018-09-08 2018-02-28 oriented industries or other enhancement. Selection group of exporters (multiple contracts) EDP/2-1/CS/0001 / Consultancy service on conducting export-related Component 2: Export Individual research which would benefit IDA / 58790 competitiveness Post Consultant Open 50,000.00 4,500.00 Completed 2017-11-27 2017-10-12 2018-01-15 2017-11-22 2018-02-05 2017-11-22 2018-03-12 2017-11-27 2018-09-08 2018-02-28 specific export-oriented enhancement. Selection industries or other group of exporters (multiple contracts) EDP/3/CS/11 / Employment Individual Component 3: Project of PIU staff: Procurement IDA / 58790 Post Consultant Open 18,000.00 954.49 Terminated 2017-06-18 2018-07-18 2017-08-06 2018-01-12 2017-08-27 2018-01-16 2017-10-01 2018-01-16 2018-03-30 Implementation Support assistant Selection EDP/1/CS/04 / Short term consultant to conduct assessment on existing Component 1: Development Individual export insurance related IDA / 58790 of a new line of export Post Consultant Open 40,000.00 11,000.00 Completed 2018-01-22 2017-12-21 2018-03-12 2018-01-15 2018-04-02 2018-01-22 2018-05-07 2018-01-22 2018-11-03 2018-10-22 mongolian laws, rules and finance products Selection regulations jointly with EID staff EDP/3/CS/2 / Environmental Individual and Social screening Component 3: Project IDA / 58790 Post Consultant Direct 54,000.00 0.00 Canceled 2018-05-02 2018-05-12 2018-06-02 2018-07-07 2019-01-03 consultant (duration of 3 Implementation Support Selection years) EDP/3/CS/0002 / Individual Environmental and Social Component 3: Project IDA / 58790 Post Consultant Open 54,000.00 4,500.00 Terminated 2018-05-02 2018-04-04 2018-06-20 2018-05-01 2018-07-11 2018-05-01 2018-08-15 2018-05-02 2019-02-11 screening consultant (duration Implementation Support Selection of 3 years) CS-2-22A/20 / Logistics Centers’ Development Plan for Component 2: Export Individual Under Agricultural Commodity IDA / 58790 competitiveness Post Consultant Open 10,000.00 0.00 2020-08-30 2020-10-19 2020-10-18 2020-11-08 2020-12-13 2021-03-13 Implementation Exchange to support export of enhancement. Selection agricultural raw materials CS-2-22B/20 / Analysis and Development Plan for Component 2: Export Individual Under Agricultural Commodity IDA / 58790 competitiveness Post Consultant Open 10,000.00 0.00 2020-08-30 2020-10-19 2020-10-14 2020-11-04 2020-12-09 2021-03-09 Implementation Exchange to support export of enhancement. Selection agricultural raw materials CS-2-28/20 / The Component 2: Export consultancy to develop an IDA / 58790 competitiveness Post Direct Selection Direct 15,000.00 14,999.54 Signed 2020-11-30 2020-12-02 2020-12-10 2020-12-02 2021-02-13 2021-01-07 2022-02-13 electronic system of Effective enhancement. Partnership Schemes Page 8 CS-1-2A/20 / Product Development of Export Credit Insurance in Mongolia (international) Component 1: Development Individual IDA / 58790 of a new line of export Post Consultant Open 40,000.00 40,000.00 Signed 2020-08-20 2020-08-25 2020-10-08 2020-12-31 2020-10-29 2021-03-05 2020-12-03 2021-03-08 2021-02-01 Product Development of finance products Selection Export Credit Insurance in Mongolia (international) CS-1-2B/20 / Product Component 1: Development Individual Development of Export Credit IDA / 58790 of a new line of export Post Consultant Open 40,000.00 40,000.00 Signed 2020-08-20 2020-08-25 2020-10-08 2020-12-31 2020-10-29 2021-03-05 2020-12-03 2021-03-08 2021-02-01 Insurance in Mongolia finance products Selection (international) CS-3-20/20 / The study on the economic impact assessment of the Free Trade Agreement between Mongolia Component 2: Export Individual Under and Euro Asian Economic IDA / 58790 competitiveness Post Consultant Open 20,000.00 0.00 2020-08-20 2020-08-28 2020-10-08 2020-10-29 2020-12-03 2021-03-03 Implementation Union and the development of enhancement. Selection National Benchmarking Mechanism for Products and Services Individual CS-3-26/20 / Legal Component 3: Project IDA / 58790 Post Consultant Open 18,000.00 18,000.90 Signed 2020-08-20 2020-09-07 2020-10-04 2020-12-28 2020-10-25 2020-12-31 2020-11-29 2021-01-31 2021-11-29 consultant Implementation Support Selection CS-1-2/20 / New Product Component 1: Development Individual Development of Export Credit IDA / 58790 of a new line of export Post Consultant Open 40,000.00 0.00 Canceled 2020-03-25 2020-05-13 2020-06-03 2020-07-08 2021-01-04 Insurance in Mongolia finance products Selection (international) CS-3-25/20 / The consultancy to strengthen Component 3: Strengthening certification services and IDA / 58790 Certification Services and Prior Direct Selection Direct 2,000,000.00 0.00 Under Review 2020-11-30 2020-12-17 2021-02-20 2023-12-31 quality management Quality Management (international) Individual CS-4-17/21 / Business Component 3: Project IDA / 58790 Post Consultant Open 18,000.00 8,105.33 Signed 2021-01-15 2020-07-03 2021-03-05 2020-06-30 2021-03-26 2020-07-06 2021-04-30 2020-07-15 2022-04-30 Development Consultant Implementation Support Selection CS-4-15/21 / Environment Individual Component 3: Project and social impact assessment IDA / 58790 Post Consultant Open 18,000.00 19,996.72 Signed 2021-01-15 2021-03-03 2021-03-05 2020-12-02 2021-03-26 2020-12-30 2021-04-16 2020-12-30 2022-04-11 Implementation Support consultant Selection Individual Component 3: Project Under CS-4-6/21 / PIU Coordinator IDA / 58790 Prior Consultant Open 22,000.00 0.00 2021-02-09 2021-02-24 2021-03-30 2020-02-14 2021-04-20 2021-05-21 2021-05-25 2022-05-25 Implementation Support Implementation Selection Individual CS-4-1/21 / PIU Monitoring Component 3: Project Under IDA / 58790 Post Consultant Open 16,440.00 0.00 2021-01-15 2021-03-03 2021-03-05 2021-03-26 2021-04-30 2022-04-30 and Evaluation Specialist Implementation Support Implementation Selection Individual CS-4-29/21 / Export Market Component 3: Project Under IDA / 58790 Post Consultant Open 17,000.00 0.00 2021-03-03 2021-03-04 2021-04-21 2021-05-12 2021-06-16 2022-06-16 Analyst Implementation Support Implementation Selection Individual CS-4-38/21 / PIU Financial Component 3: Project Under IDA / 58790 Post Consultant Open 15,000.00 0.00 2021-03-05 2021-03-04 2021-04-23 2021-05-14 2021-06-18 2021-12-31 Management Specialist Implementation Support Implementation Selection CS-4-32/21 / National consultant for Export competitiveness for co- Component 3: Project Under IDA / 58790 Post Direct Selection Direct 20,000.00 0.00 2021-03-26 2021-04-05 2021-04-05 2021-06-09 2022-06-30 handling the overall Implementation Support Implementation component 2 and development of relevant TORs Individual CS-4-16/21 / Business Component 3: Project Under IDA / 58790 Post Consultant Open 20,400.00 0.00 2021-04-12 2021-04-14 2021-05-31 2021-06-21 2021-07-26 2021-12-31 Development Consultant Implementation Support Implementation Selection Individual CS-4-39/21 / Business Component 3: Project Under IDA / 58790 Post Consultant Open 20,400.00 0.00 2021-04-12 2021-04-14 2021-05-31 2021-06-21 2021-07-26 2021-12-31 Development Consultant Implementation Support Implementation Selection CS-1-1/21 / International consultant to support Component 1: Development Individual Pending Mongolian Re for export IDA / 58790 of a new line of export Post Consultant Open 40,000.00 0.00 2021-05-17 2021-07-05 2021-07-26 2021-08-30 2022-01-31 Implementation credit insurance operation and finance products Selection enhancement CS-2-12/21 / Undertake market intelligence studies for specific market segments like Adventure tourism (for Component 2: Export Individual Pending backpacker/over-lander IDA / 58790 competitiveness Post Consultant Open 45,000.00 0.00 2021-05-17 2021-07-05 2021-07-26 2021-08-30 2022-12-30 Implementation markets, EU market, USA enhancement. Selection market, Asian markets) and recommend potential tourism products (international) CS-2-13/21 / Undertake baseline survey on creative industry on art, paintings, hand made products and Component 2: Export Individual Pending tangible/intangible heritage IDA / 58790 competitiveness Post Consultant Open 45,000.00 0.00 2021-05-17 2021-07-05 2021-07-26 2021-08-30 2022-12-30 Implementation products and provide general enhancement. Selection assistance on how to market the products being developed (international) Page 9 CS-2-14/21 / Study on the impact of Mongolia's accession to the Asia-Pacific Trade Agreement on its Component 2: Export Individual exports and recommendations Pending IDA / 58790 competitiveness Post Consultant Open 15,000.00 0.00 2021-05-17 2021-07-05 2021-07-26 2021-08-30 2022-04-30 on Mongolia's negotiating Implementation enhancement. Selection position for the 5th round of negotiations for the increase and diversification of its exports. CS-2-15/21 / Study on the impact on exports of Component 2: Export Individual Pending Mongolia's accession to the IDA / 58790 competitiveness Post Consultant Open 15,000.00 0.00 2021-05-17 2021-07-05 2021-07-26 2021-08-30 2022-04-30 Implementation Comprehensive Regional enhancement. Selection Partnership Agreement CS-2-16/21 / Prepare a draft Component 2: Export Individual Pending regulation on anti-dumping IDA / 58790 competitiveness Post Consultant Open 10,000.00 0.00 2021-05-17 2021-07-05 2021-07-26 2021-08-30 2021-12-28 Implementation and countervailing measures. enhancement. Selection CS-2-17/21 / Study on the impact of the future Economic Partnership Agreement Component 2: Export Individual Pending between Mongolia and the IDA / 58790 competitiveness Post Consultant Open 7,000.00 0.00 2021-05-17 2021-07-05 2021-07-26 2021-08-30 2021-11-28 Implementation Republic of Korea on enhancement. Selection mongolian exports, in particular SMEs (international) CS-2-22/21 / National consultant to conduct gap analysis of existing all trade Component 2: Export Individual Pending legislation and regulation in IDA / 58790 competitiveness Post Consultant Open 20,000.00 0.00 2021-05-17 2021-07-05 2021-07-26 2021-08-30 2021-11-28 Implementation Mongolia and recommend enhancement. Selection possible trade and investment policy CS-2-23/21 / National consultant to conduct a Component 2: Export Individual feasibility study and a needs Pending IDA / 58790 competitiveness Post Consultant Open 20,000.00 0.00 2021-05-17 2021-07-05 2021-07-26 2021-08-30 2022-01-31 assessment on e-commerce Implementation enhancement. Selection law and regulation in Mongolia CS-2-24/21 / National consultant to develop a Component 2: Export Individual manual for SMEs in Mongolia Pending IDA / 58790 competitiveness Post Consultant Open 15,000.00 0.00 2021-05-17 2021-07-05 2021-07-26 2021-08-30 2021-11-30 for participating international Implementation enhancement. Selection trade fairs, exhibition, expos, trade shows CS-4-46/21 / Legal Individual Component 3: Project Under Consultant (Second IDA / 58790 Post Consultant Open 18,000.00 0.00 2021-06-20 2021-06-21 2021-08-08 2021-08-29 2021-10-03 2022-10-03 Implementation Support Implementation recruitment) Selection Page 10 Plan de Passation des Marchés Projet de Promotion de la Compétitivité de la Chaîne des Valeurs de l’Anacarde (PPCA) FINANCEMENT SUR LE PPF I. Généralités 1. Information sur le projet: Pays : Côte d’Ivoire Emprunteur : Conseil Coton-Anacarde (CCA) Nom du Projet : Projet de Promotion de la Compétitivité de la Chaîne des Valeurs de l’Anacarde (PPCA Numéro du Crédit : Unité de Gestion du Projet : Le risque lié au projet : modéré (d’après les seuils proposés. Ce risque sera confirmé après évaluation des capacités en PM de l’unité de gestion du projet) II. Fournitures, Travaux et Services Assimilés 2.1. Seuils d’examen préalable Les marchés qui seront soumis à l'examen préalable de la Banque Nouveaux seuils de revue de la Banque élaborés en décembre 2012 et proposés au Gouvernement le 05 décembre 2012, révisés en juillet 2016 et liés au niveau de risque du projet. Nature des Méthode de Valeur seuil Contrats soumis à dépenses passation de du marché examen préalable marchés $EU de l’IDA 1. Travaux AOI ≥ 10,000,000 (y compris clés AON < 10,000,000 Tous les contrats de en main, Demande de cotation – < 200,000 15.000.000 $EU et Fourniture et au moins 3 offres plus montage Entente Directe (*) d’installations et Pas de seuil PPP) 2. Fournitures, AOI ≥ 1,000,000 Systèmes AON < 1,000,000 d’Informations Consultation de Tous les contrats de et Services Fournisseurs - Au moins < 100,000 4.000.000 $EU et plus autres que les 3 offres services de Consultation de < 500 000 Consultants Fournisseurs - Au moins 1 3 offres pour les véhicules et le carburant Entente directe (*) Pas de seuil (*) Le justificatif de toute entente directe doit être transmis avec le PPM 3. Procédures applicables aux Composantes relatives au Développement Conduit par les Communautés : N/A 4. Référence (si nécessaire) au Manuel opérationnel/de passation de marchés : 5. Autres arrangements spécifiques pour la passation de marchés : [y inclus passation anticipée de marchés et financement rétroactif, si applicables] Citer le paragraphe inscrit dans l’Accord de Financement le cas échéant) 6. Marchés et Planning et Méthode de Passation : 2 1 2 3 4 5 6 7 8 9 Méth Examen Monta ode préalable Date nt de Pré- Préféren de la prévue Estima Ref. Contract passa qualificati ce Banque pour tif Commentaires No. (Description) tion on nationale (a l’ouvert (en de (oui/non) (oui/non) priori/a ure des milliers march posterior offres $EU) és i) Acquisition de matériels informatiques (ordinateur portable, desktop, disque dur externe, imprimante, serveurs et onduleur) et A 31 Août F/01 matériels bureautiques 99 Non Non posteriori 2018 (photocopieuses, CFN scanneurs, téléphones fixes et mobiles, fax)- DOCKIN STATION pour l’UGP Acquisition de 20 motos pour renforcer le A 29 Août F/02 34 CFN Non Non dispositif de collecte posteriori 2018 des données Acquisition de véhicules pour l’UGP (3), la A 28 Août F/03 CFN Non Non DOPA(1) l’ARRE (1) et le 351 posteriori 2018 CCA(1 ) S/TOTAL FOURNITURE 484 Montant total prévisionnel : 484 $US 3 3. Marchés de Services Assimilés 1 2 3 4 5 6 7 8 9 Examen Montan Pré- Préféren préalable Date t Méthode Ref quali ce de la prévue Estimat de . Contract ficati national Banque pour Commentaires if passation No. (Description) on e (a l’ouvertur (en de (oui/ (oui/non priori/a e des milliers marchés non) ) posteriori offres $EU) ) Veuillez fournir le Contrat de Entente justificatif de location des directe A l’entente directe S/1 locaux de 53 Non Non Mai 2018 Avec SCI Posteriori comme demandé l'UGP pour 7 JAFI dé par la Banque mois Assurance des 5 CFN A 16 Août S/2 véhicules et 34 Non Non posteriori 2018 des 20 motos Fourniture de carburant CFN A 16 Août S/3 pour les 13 Non Non posteriori 2018 activités (5) véhicules TOTAL 100 MARCHES DE 4 SERVICES ASSIMILES Montant total prévisionnel : 100 $US 5 III. Sélection de Consultants 3.1. Seuil d’examen préalable Les marchés qui seront soumis à l'examen préalable de la banque conformément aux Nouveaux seuils de revue de la Banque élaborés en décembre 2012 et proposés au Gouvernement le 05 décembre 2012, révisés en juillet 2016 et liés au niveau de risque du projet. : Nature de Méthode de passation Valeur Contrats soumis à dépenses de marchés seuil du examen préalable contrat $EU Consultan SFQC1, SFQ2, SMC3, ≥ 300.000 ts SCBD4, Tout contrat de 2.000.000 Firmes SFQC, SFQ, SMC, SCBD, < 300.000 $EU ou plus QC5 Pas de Entente directe (*) seuil Consultan Consultant individuel (AMI) ≥ 100.000 ts Consultant individuel (3 Tout contrat de 400.000 $ Individuel < 100.000 CV) EU ou plus s Pas de Entente directe (*) seuil Tous les TDRs, quelle que soit la valeur du contrat, sont soumis à examen préalable. (*) Le justificatif de toute sélection par entente directe doit être transmis avec le PPM 2. Liste restreinte composée entièrement de Consultants Nationaux : La liste restreinte de Consultants pour les services, d'un coût estimatif inférieur à 300 0000 $ US ou équivalent par contrat, peut être entièrement composée de Consultants nationaux conformément aux dispositions du paragraphe 7.25 du Règlement de Passation de Marchés dans le Cadre du Financement de Projets d’Investissement (FPI) pour Fournitures, Travaux, Services Autres que des Services de Consultants et Services de Consultants – Juillet 2016. 1 SFQC : Sélection Fondée sur la Qualité et le Coût 2 SFQ : Sélection fondée sur la qualité 3 SMC : Sélection au moindre coût 4 SCBD : Sélection dans le cadre d’un budget déterminé 5 QC : Sélection basée sur les Qualifications des Consultants CI : Consultant Individuel : AMI : Avis à Manifestation d’Intérêt 6 3. Autres arrangements spécifiques pour la sélection : [y compris passation anticipée de marchés et financement rétroactif, si applicables] 7 4. Contrats de Consultants avec Méthode de Sélection et Planning 1 2 3 4 5 6 7 Examen Ref Montant Méthod Date prévue préalable de . Description du contrat estimatif e de pour la la Banque Commentaires No. (en sélectio soumission des (a priori / a milliers n propositions posteriori) $EU) Sélection du C/1 cabinet en cours Recrutement d’un consultant pour la L ANO de la réalisation des études Banque sur les environnementale et sociale 250 QC A posteriori 17 Avril 2018 TDR a été stratégique (EESS) de la zone agro obtenu/ Ce industrielle de KORHOGO marché figurait dans la version initiale du PPM Sélection du C/2 cabinet en cours Recrutement d’un consultant pour la L ANO de la réalisation de l’étude Banque sur les environnementale et sociale 250 QC A postériori 05 Juin 2018 TDR a été stratégique (EESS) de la zone agro obtenu/ Ce industrielle BOUAKE marché figurait dans la version initiale du PPM Sélection du Recrutement d’un consultant pour la C/3 cabinet en cours réalisation de études environnementale et sociale 250 QC A postériori 07 Mai 2018 L ANO de la stratégique (EESS) de la zone agro Banque sur les industrielle de BONDOUKOU TDR a été 8 1 2 3 4 5 6 7 Examen Ref Montant Méthod Date prévue préalable de . Description du contrat estimatif e de pour la la Banque Commentaires No. (en sélectio soumission des (a priori / a milliers n propositions posteriori) $EU) obtenu/ Ce marché figurait dans la version initiale du PPM Sélection du C/4 cabinet en cours Recrutement de consultants pour la L ANO de la réalisation de l’ études Banque sur les environnementale et sociale 250 QC A postériori 07 Avril 2018 TDR a été stratégique (EESS) de la zone agro obtenu/ Ce industrielle de SEGUELA marché figurait dans la version initiale du PPM C/ Recrutement d’un consultant 5 individuel pour le constat d’impact environnemental et social ( CIES) de AMI en cours 100 CI A Postériori 1er Juin 2018 travaux de 184 km de routes rurales dans les régions du GBEKE, HAMBOL et GONTOUGOU C/6 Recrutement d’un consultant AMI en cours individuel pour l’étude d’impact 50 CI A Postériori 1er Juin 2018 environnemental et social (EIES) de 18 km dans les régions du HAMBOL Selon le nouveau Recrutement d’un consultant pour cadre de passation l’actualisation de la structure des prix C/7 50 QC A Posteriori 11 Juin 2018 des marchés de la de la commercialisation de la noix Banque Mondiale, brute de cajou en Côte d’Ivoire en sa section VII, le 9 1 2 3 4 5 6 7 Examen Ref Montant Méthod Date prévue préalable de . Description du contrat estimatif e de pour la la Banque Commentaires No. (en sélectio soumission des (a priori / a milliers n propositions posteriori) $EU) point 7.11, la publication d’ un avis à manifestations d’intérêt n’est pas obligatoire C/8 ED avec 31 Juillet 2018 Justificatif en Recrutement d’un coordonnateur M 21 A priori annexe adjoint chargé de l’industrie KARIM Contrat pour 3 BERTHE mois TOTAL/CONSULTANT 1221 Montant prévisionnel des consultants : 1221 $US TOTAL PREVISIONNEL GENERAL : 1 805 000 $US 10 PROCUREMENT Cote d'Ivoire : Cashew Value Chain Competitiveness Project PLAN General Information Country: Cote d'Ivoire Bank’s Approval Date of the Original Procurement Plan: 2018-08- 13 2021-05- Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P158810 GPN Date: 18 Project Name: Cashew Value Chain Competitiveness Project Loan / Credit No: IBRD / 88450, IDA / V0300 Interprofessional Fund for Agricultural Research and Advisory Executing Agency(ies): WORKS Activity Reference No. Procurement Estimate Actual Draft Pre- Draft Bidding Specific Proposal Bid Evaluation Loan / Credit Market Procurement Prequalificatio High SEA/SH Process Prequalification Bidding Documents Contract / Description Component Review Type Method Document d Amount qualification Document / Procurement Notice Submission / Report and Signed Contract No. Approach Process n (Y/N) Risk Status Evaluation Report as Issued Completion Type Amount (US$) Documents Justification / Invitation Opening / Minutes Recommendation (US$) Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned for Award Actual Planned Actual Planne d CI-FIRCA-74743-CW-RFQ 1. Institutional Request for Single Stage - One Complete 2018-10- 2018-10- 2018-12- 2018-11- 2019- / Travaux d'aménagement IBRD / 88450 strengthening and value Post Limited 20,000.00 50,739.77 Quotations Envelope d 16 08 11 14 06-09 des locaux de la DOPA chain governance CI-FIRCA-74746-CW-RFQ 1. Institutional / Travaux d'aménagement Request for Single Stage - One Complete 2018-11- 2018-11- 2019-01- 2019-01- 2019- IBRD / 88450 strengthening and value Post Limited 42,000.00 72,846.99 du Bâtiment à usage de Quotations Envelope d 19 21 14 08 07-13 chain governance local technique de l'ARRE CI-FIRCA-82585-CW-RFQ 4. Program coordination, Request for Single Stage - One Complete 2018-10- 2018-11- 2018-12- 2018-12- 2019- / Travaux d'aménagement IBRD / 88450 monitoring and knowledge Post Limited 40,000.00 36,736.19 Quotations Envelope d 29 27 24 21 06-22 de l'UCP PPCA management CI-FIRCA-74728-CW-RFB / Sélection d'une entreprise 3. Support to private pour la construction de la investment in post-harvest Open - Single Stage - One 14,335,00 2019-01- 2019-06- 2019-02- 2019-06- 2019-03- 2019-08- 2019-04- 2019-05- 2019- IBRD / 88450 Post Request for Bids 0.00 Canceled plateforme industrielle de and processing International Envelope 0.00 28 14 02 19 16 02 15 20 11-16 Korhogo dédiée à la infrastructure transformation de l'anacarde CI-FIRCA-106689-CW-RFQ 2. Productivity / Aménagement d'un enhancement and Request for Single Stage - One 117,174.3 2019-05- 2019-12- 2019-06- 2020-02- 2019- IBRD / 88450 Post Limited 56,000.00 Signed bâtiment pour abriter le improved access to Quotations Envelope 4 05 23 30 21 12-27 laboratoire de pédologie markets CI-FIRCA-106693-CW-RFB 2. Productivity / Travaux de réhabilitation Pending enhancement and Single Stage - One 3,445,000. 2019-03- 2019-03- 2019-05- 2019-06- 2019-07- 2020- par RC et RLTPC d'environ IBRD / 88450 Post Request for Bids Open - National 0.00 Implemen improved access to Envelope 00 18 23 04 03 08 01-04 146,04 km de routes tation markets rurales (Régions du GBEKE et du HAMBOL) CI-FIRCA-106694-CW-RFB 2. Productivity / Travaux de réhabilitation Pending enhancement and Single Stage - One 2,793,000. 2019-03- 2019-03- 2019-05- 2019-06- 2019-07- 2020- par RC et RLTPC d'environ IBRD / 88450 Post Request for Bids Open - National 0.00 Implemen improved access to Envelope 00 18 23 04 03 08 01-04 116,90 km de routes tation markets rurales (Région du GONTOUGO) CI-FIRCA-106697-CW-RFB 2. Productivity Pending / Travaux de réhabilitation enhancement and Single Stage - One 6,517,000. 2019-09- 2019-09- 2019-10- 2019-11- 2019-12- 2020- IBRD / 88450 Post Request for Bids Open - National 0.00 Implemen par RC et RLTPC d'environ improved access to Envelope 00 01 06 18 17 22 06-19 tation 448 km de routes rurales markets CI-FIRCA-106699-CW-RFQ / Sélection d'un 3. Support to private entrepreneur pour les investment in post-harvest Request for Single Stage - One 121,000.0 107,711.3 2019-03- 2019-03- 2019-05- 2019-04- 2019- Travaux d'aménagement IBRD / 88450 Post Limited Signed and processing Quotations Envelope 0 0 23 19 18 24 11-14 des locaux de l'UCP-PPCA infrastructure (courant fort, courant faible et d'enseigne lumineuse des locaux du PPCA CI-FIRCA-126713-CW-RFB 2. Productivity Pending / Faire réaliser le forage + enhancement and Single Stage - One 200,000.0 2019-09- 2019-09- 2019-10- 2019-11- 2019-12- 2020- IBRD / 88450 Post Request for Bids Open - National 0.00 Implemen équipements pour improved access to Envelope 0 10 15 27 26 31 06-28 tation l'adduction d'eau des 3 CDC markets priorisés CI-FIRCA-82341-CW-RFQ 4. Program coordination, Request for Single Stage - One 2018-12- 2019-02- 2019- / Aménagement de la salle IBRD / 88450 monitoring and knowledge Post Limited 33,000.00 0.00 Canceled Quotations Envelope 22 16 08-15 de réunion de l'annexe 2 du management CCA CI-FIRCA-126705-CW-RFQ 1. Institutional Request for Single Stage - One 2019-09- 2019-11- 2020- / Travaux de Réhabilitation IBRD / 88450 strengthening and value Post Limited 60,000.00 0.00 Canceled Quotations Envelope 25 20 05-18 des bureaux de l’ANDE du chain governance PORO CI-FIRCA-74724-CW-RFB / 3. Support to private Recrutement d'un entreprise investment in post-harvest Open - Single Stage - One 8,600,000. 2019-04- 2019-05- 2019-06- 2019-07- 2019-08- 2020- pour la construction de la IBRD / 88450 Post Request for Bids 0.00 Canceled and processing International Envelope 00 29 04 15 15 19 02-15 plate forme agro infrastructure industrielle de Bouaké CI-FIRCA-82345-CW-RFB / Travaux de réhabilitation 2. Productivity par RC et RLTPC du second enhancement and Single Stage - One 6,550,000. 2019-04- 2019-04- 2019-05- 2019-06- 2019-07- 2020- IBRD / 88450 Post Request for Bids Open - National 0.00 Canceled programme de 250 km de improved access to Envelope 00 01 06 18 17 22 01-18 routes rurales (10 Lots de markets travaux CI-FIRCA-82340-CW-RFB / 3. Support to private Sélection de cabinets pour investment in post-harvest Single Stage - One 132,000.0 2018-12- 2018-12- 2019-02- 2019-03- 2019-04- 2019- le contrôle des travaux de IBRD / 88450 Post Request for Bids Open - National 0.00 Canceled and processing Envelope 0 20 25 05 07 11 10-08 construction des centres de infrastructure services de la plateforme CI-FIRCA-82339-CW-RFB / Travaux d'Aménagement et de construction des 3. Support to private infrastructures de base des investment in post-harvest Single Stage - One 1,800,000. 2019-06- 2019-06- 2019-07- 2019-08- 2019-09- 2020- IBRD / 88450 Post Request for Bids Open - National 0.00 Canceled 6 Centres de and processing Envelope 00 03 08 20 19 23 03-21 Développement du Cajou infrastructure (bâtiments, locaux techniques, clôtures, parcs météos...) CI-FIRCA-74739-CW-RFB / 2. Productivity Travaux de réhabilitation enhancement and Single Stage - One 6,700,000. 2019-01- 2019-01- 2019-02- 2019-03- 2019-04- 2019- par RC et RLTPC d'environ IBRD / 88450 Post Request for Bids Open - National 0.00 Canceled improved access to Envelope 00 07 12 23 25 29 10-26 258 km de routes rurales markets (10 Lots de travaux) CI-FIRCA-82344-CW-RFB / Travaux de réhabilitation par RLTPC d'environ 170 km de routes rurales (06 Lots 2. Productivity de travaux) enhancement and Single Stage - One 3,800,000. 2018-10- 2018-11- 2018-12- 2019-01- 2019-02- 2019- IBRD / 88450 Post Request for Bids Open - National 0.00 Canceled Travaux de réhabilitation improved access to Envelope 00 30 04 16 15 19 08-18 par RC et RLTPC du second markets programme de 250 km de routes rurales (10 Lots de travaux) CI-FIRCA-74732-CW-RFB / 1. Institutional Pending Single Stage - One 1,500,000. 2020-07- 2020-07- 2020-09- 2020-10- 2020-11- 2021- Construction des bâtiments IBRD / 88450 strengthening and value Post Request for Bids Open - National 0.00 Implemen Envelope 00 20 25 05 05 09 05-08 pour l'extension du CITA chain governance tation CI-FIRCA-126708-CW-RFQ 1. Institutional Pending Request for Single Stage - One 2020-05- 2020-07- 2021- / Travaux d’aménagement IBRD / 88450 strengthening and value Post Limited 27,000.00 0.00 Implemen Quotations Envelope 25 20 01-16 des locaux du PPCA chain governance tation CI-FIRCA-106920-CW-RFQ / Travaux d'aménagement 1. Institutional Pending Request for Single Stage - One 112,000.0 2020-04- 2020-06- 2020- des locaux des 4 DR du CCA IBRD / 88450 strengthening and value Post Limited 0.00 Implemen Quotations Envelope 0 06 01 11-28 Bondoukou, Bouaké, chain governance tation Korhogo et Séguéla CI-FIRCA-126718-CW-RFQ / installer le système 2. Productivity Pending d'électrification solaire enhancement and Request for Single Stage - One 100,000.0 2020-08- 2020-10- 2021- IBRD / 88450 Post Limited 0.00 Implemen (équipements +installation) improved access to Quotations Envelope 0 15 10 04-08 tation d'opérationnalisation des 3 markets CDC priorisés CI-FIRCA-158141-CW-RFQ 2. Productivity Pending Request for Single Stage - One 2020-05- 2020-07- 2021- / Travaux de réhabilitation IBRD / 88450 enhancement and Post Limited 75,000.00 0.00 Implemen Quotations Envelope 23 18 01-14 du batiment existant improved access to tation markets CI-FIRCA-74729-CW-RFB / Sélection d'une entreprise 3. Support to private pour la construction de la investment in post-harvest Open - Single Stage - One 8,600,000. 16,857,19 2020-03- 2020-05- 2020-03- 2020-05- 2020-07- 2020-06- 2020-07- 2020-07- 2020-10- 2021- IBRD / 88450 Post Request for Bids Signed plateforme industrielle de and processing International Envelope 00 0.84 16 18 21 02 14 01 28 06 12 01-02 Bondoukou dédiée à la infrastructure transformation de l'anacarde CI-FIRCA-140336-CW-RFB 3. Support to private / Sélection d’un Under investment in post-harvest Open - Single Stage - One 15,000,00 2020-03- 2020-06- 2020-03- 2020-08- 2020-04- 2020-08- 2020-05- 2020-10- 2020-06- 2020- entrepreneur pour les IBRD / 88450 Prior Request for Bids 0.00 Implemen and processing International Envelope 0.00 06 08 11 04 22 25 22 26 26 12-23 travaux de construction de tation infrastructure la plateforme de Korhogo CI-FIRCA-126720-CW-RFB 2. Productivity / Acquérir un forage + enhancement and Single Stage - One 150,000.0 2019-09- 2019-09- 2019-10- 2019-11- 2019-12- 2020- IBRD / 88450 Post Request for Bids Open - National 0.00 Canceled équipements pour improved access to Envelope 0 02 07 19 18 23 06-20 l'adduction d'eau des 3 CDC markets priorisés CI-FIRCA-82346-CW-RFB / Travaux d'entretien par 2. Productivity RLEP du 1er programme de enhancement and Single Stage - One 428,000.0 2019-12- 2019-12- 2020-01- 2020-02- 2020-03- 2020- IBRD / 88450 Post Request for Bids Open - National 0.00 Canceled 428 (258+170) km de improved access to Envelope 0 02 07 18 17 23 09-19 routes rurales réhabilités markets (05 Lots de travaux) CI-FIRCA-179998-CW-RFQ 4. Program coordination, / TRAVAUX Request for Single Stage - One 2020-06- 2020-06- 2020-08- 2020-08- 2021- IBRD / 88450 monitoring and knowledge Post Limited 46,000.00 47,705.10 Signed SUPPLEMENTAIRES Quotations Envelope 21 12 16 10 02-12 management D'AMENAGEMENT DES LOCAUX DU PPCA EN 3 LOTS CI-FIRCA-157378-CW-RFQ 2. Productivity Request for Single Stage - Two 112,000.0 2020-04- 2020-07- 2020-07- 2020-09- 2020-12- 2022- / Travaux d’aménagement IBRD / 88450 enhancement and Post Limited 0.00 Canceled Proposals Envelope 0 15 01 01 09 27 06-20 des sites des 3 CDC improved access to markets CI-FIRCA-201791-CW-RFB / Travaux de réhabilitation 2. Productivity Pending par RC et RLTPC du second enhancement and Single Stage - One 7,200,000. 2020-11- 2020-11- 2020-12- 2021-01- 2021-02- 2021- IBRD / 88450 Post Request for Bids Open - National 0.00 Implemen programme de 250 km de improved access to Envelope 00 02 07 19 18 22 08-21 tation routes rurales ( 16 Lots de markets travaux) CI-FIRCA-201799-CW-RFB / Travaux d’entretien par 2. Productivity Pending RLEP de 465 Km routes enhancement and Single Stage - One 435,000.0 2020-11- 2020-11- 2021-01- 2021-02- 2021-03- 2021- IBRD / 88450 Post Request for Bids Open - National 0.00 Implemen rurales dans les Régions du improved access to Envelope 0 17 24 05 04 11 09-07 tation Gbèkè, du Hambol et du markets Gontougo (10 Lots) CI-FIRCA-201802-CW-RFQ / Travaux de réhabilitation 2. Productivity Pending du bâtiment existant à enhancement and Request for Single Stage - One 112,000.0 2020-11- 2021-01- 2021- IBRD / 88450 Post Limited 0.00 Implemen usage d'hébergement du improved access to Quotations Envelope 0 21 16 07-15 tation site du Laboratoire markets Agropédologique de Sinématiali CI-FIRCA-157696-CW-RFB / Travaux de réhabilitation 1. Institutional Pending Single Stage - One 280,000.0 2020-12- 2020-12- 2021-01- 2021-03- 2021-04- 2021- et d'extension des IBRD / 88450 strengthening and value Post Request for Bids Open - National 0.00 Implemen Envelope 0 15 20 31 02 06 10-03 batiments des délégations chain governance tation régionales du CCA (Bondoukou) CI-FIRCA-157707-CW-RFB / Travaux de réhabilitation 1. Institutional Pending Single Stage - One 280,000.0 2020-07- 2020-07- 2020-08- 2020-09- 2020-11- 2021- et d'extension des IBRD / 88450 strengthening and value Post Request for Bids Open - National 0.00 Implemen Envelope 0 13 18 29 28 02 05-01 batiments des délégations chain governance tation régionales du CCA (Bouaké) CI-FIRCA-157713-CW-RFQ / Travaux de réhabilitation 1. Institutional Pending Request for Single Stage - One 233,000.0 2020-12- 2021-02- 2021- et d'extension des IBRD / 88450 strengthening and value Post Limited 0.00 Implemen Quotations Envelope 0 20 14 08-13 batiments des délégations chain governance tation régionales du CCA (Korhogo) CI-FIRCA-157722-CW-RFB / Travaux de réhabilitation 1. Institutional Pending Single Stage - One 280,000.0 2020-12- 2020-12- 2021-01- 2021-03- 2021-04- 2021- et d'extension des IBRD / 88450 strengthening and value Post Request for Bids Open - National 0.00 Implemen Envelope 0 15 20 31 02 06 10-03 batiments des délégations chain governance tation régionales du CCA (Séguéla) CI-FIRCA-157691-CW-RFQ 1. Institutional / Travaux d'aménagement Request for Single Stage - One 186,000.0 2020-04- 2020-06- 2020- IBRD / 88450 strengthening and value Post Limited 0.00 Canceled des locaux du laboratoire Quotations Envelope 0 20 15 12-12 chain governance central du CITA CI-FIRCA-106687-CW-RFQ 1. Institutional Request for Single Stage - One 2020-11- 2021-01- 2021- / Travaux de Réhabilitation IBRD / 88450 strengthening and value Post Limited 60,000.00 0.00 Canceled Quotations Envelope 16 11 07-10 des bureaux de l' ANDE du chain governance PORO CI-FIRCA-191631-CW-RFQ 2. Productivity Request for Single Stage - One 112,000.0 2020-11- 2021-01- 2021- / Travaux d’aménagement IBRD / 88450 enhancement and Post Limited 0.00 Canceled Quotations Envelope 0 21 16 07-15 des sites des 3 CDC improved access to markets CI-FIRCA-157377-CW-RFQ 2. Productivity / Travaux de construction enhancement and Request for Single Stage - One 168,000.0 2020-11- 2021-01- 2021- IBRD / 88450 Post Limited 0.00 Canceled des infrastructures de base improved access to Quotations Envelope 0 22 17 07-16 des 3 CDC markets CI-FIRCA-126711-CW-RFQ / Réalisation de travaux 2. Productivity agricoles enhancement and Request for Single Stage - One 100,000.0 2020-09- 2020-10- 2021- d'opérationnalisation des 3 IBRD / 88450 Post Limited 0.00 Canceled improved access to Quotations Envelope 0 05 31 04-29 CDC priorisés pour la mise markets en place des essais de recherche agronomique 2019 CI-FIRCA-157564-CW-RFB / Travaux de construction 3. Support to private du centre de vie, du poste investment in post-harvest Single Stage - One 4,413,000. 2020-10- 2020-10- 2020-11- 2020-12- 2021-01- 2021- IBRD / 88450 Post Request for Bids Open - National 0.00 Canceled de police, bureaux and processing Envelope 00 01 06 17 17 21 07-20 administratifs et du centre infrastructure de secours (GSPM) de ZAI de Korhogo CI-FIRCA-157380-CW-RFB 2. Productivity / Travaux de réhabilitation enhancement and Single Stage - One 4,640,000. 2020-05- 2020-05- 2020-07- 2020-08- 2020-09- 2021- par RC et RLTPC d’environ IBRD / 88450 Post Request for Bids Open - National 0.00 Canceled improved access to Envelope 00 24 29 10 09 13 03-12 159,4 km de routes rurales markets (Régions du GBEKE et du HAMBOL) CI-FIRCA-157382-CW-RFB 2. Productivity / Travaux de réhabilitation enhancement and Single Stage - One 3,160,000. 2020-05- 2020-05- 2020-07- 2020-08- 2020-09- 2021- par RC et RLTPC d’environ IBRD / 88450 Post Request for Bids Open - National 0.00 Canceled improved access to Envelope 00 25 30 11 10 14 03-13 94,2 km de routes rurales markets (Région du GONTOUGO) CI-FIRCA-74738-CW-RFB / 3. Support to private Sélection d'entreprises pour investment in post-harvest Single Stage - One 1,300,000. 2020-09- 2020-09- 2020-11- 2020-12- 2021-01- 2021- la réalisation des travaux de IBRD / 88450 Post Request for Bids Open - National 0.00 Canceled and processing Envelope 00 21 26 07 07 11 07-10 construction des centres de infrastructure services de la plateforme CI-FIRCA-74731-CW-RFB / Sélection d'une entreprise 3. Support to private pour la construction de la investment in post-harvest Open - Single Stage - One 8,600,000. 2020-03- 2020-04- 2020-05- 2020-06- 2020-07- 2021- IBRD / 88450 Post Request for Bids 0.00 Canceled plateforme industrielle de and processing International Envelope 00 30 04 16 15 20 01-16 SEGUELA dédiée à la infrastructure transformation de l'anacarde CI-FIRCA-106676-CW-RFB 1. Institutional Pending Single Stage - One 372,000.0 2020-11- 2020-11- 2020-12- 2021-01- 2021-03- 2021- / Travaux d'aménagement IBRD / 88450 strengthening and value Post Request for Bids Open - National 0.00 Implemen Envelope 0 10 15 27 26 02 08-29 des locaux du CCA au chain governance tation Vallon CI-PPCA-225082-CW-RFB / Travaux de construction 3. Support to private Pending du centre de vie, du poste investment in post-harvest Single Stage - One 3,352,000. 2021-09- 2021-10- 2021-11- 2021-12- 2022-01- 2022- IBRD / 88450 Post Request for Bids Open - National 0.00 Implemen de police, bureaux and processing Envelope 00 30 05 16 16 20 07-19 tation administratifs et du centre infrastructure de secours (GSPM) de ZAI de Korhogo CI-PPCA-225086-CW-RFB / Travaux de construction 3. Support to private Pending du centre de vie, du poste investment in post-harvest Single Stage - One 2,235,000. 2021-09- 2021-10- 2021-11- 2021-12- 2022-01- 2022- IBRD / 88450 Post Request for Bids Open - National 0.00 Implemen de police, bureaux and processing Envelope 00 30 05 16 16 20 07-19 tation administratifs et du centre infrastructure de secours (GSPM) de ZAI de Bondoukou Page 1 CI-PPCA-225088-CW-RFQ 3. Support to private Pending / Travaux d’aménagement investment in post-harvest Request for Single Stage - One 186,000.0 2021-09- 2021-10- 2022- IBRD / 88450 Post Limited 0.00 Implemen des locaux du laboratoire and processing Quotations Envelope 0 05 31 04-29 tation central du CITA infrastructure CI-PPCA-225094-CW-RFB 3. Support to private / Travaux d’aménagement Pending investment in post-harvest Single Stage - One 372,000.0 2021-07- 2021-08- 2021-09- 2021-10- 2021-11- 2022- des sites des unités de IBRD / 88450 Post Request for Bids Open - National 0.00 Implemen and processing Envelope 0 30 04 15 15 19 05-18 décorticage (Construction tation infrastructure de bâtiments divers) CI-PPCA-225095-CW-RFQ 3. Support to private / Travaux d’aménagement Pending investment in post-harvest Request for Single Stage - One 150,000.0 2021-08- 2021-10- 2022- d’un atelier agro- IBRD / 88450 Post Limited 0.00 Implemen and processing Quotations Envelope 0 29 24 04-22 alimentaire d’incubation tation infrastructure pour les produits dérives de l’amande de cajou CI-PPCA-225589-CW-RFB 2. Productivity Pending / Travaux d'aménagement enhancement and Single Stage - One 3,725,000. 2021-05- 2021-06- 2021-07- 2021-08- 2021-09- 2022- IBRD / 88450 Post Request for Bids Open - National 0.00 Implemen des infrastructures de base improved access to Envelope 00 31 05 17 16 20 03-19 tation des 3 CDC (forages, clôture markets etc.) CI-PPCA-225598-CW-RFB / Travaux de réhabilitation 2. Productivity Pending par RC et RLTPC d’environ enhancement and Single Stage - One 5,400,000. 2021-08- 2021-09- 2021-10- 2021-11- 2021-12- 2022- IBRD / 88450 Post Request for Bids Open - National 0.00 Implemen 261,3 km de routes rurales improved access to Envelope 00 31 05 17 16 21 06-19 tation (Régions du GBEKE, du markets HAMBOL et du GONTOUGO) CI-PPCA-225621-CW-RFB 2. Productivity / Travaux d'entretien par Pending enhancement and Single Stage - One 435,000.0 2021-08- 2021-09- 2021-10- 2021-11- 2021-12- 2022- RLEP d’environ 465 km de IBRD / 88450 Post Request for Bids Open - National 0.00 Implemen improved access to Envelope 0 31 05 17 16 21 06-19 routes rurales (Régions du tation markets GBEKE, du HAMBOL et du GONTOUGO) CI-PPCA-225624-CW-RFB 2. Productivity / Travaux de réhabilitation Pending enhancement and Single Stage - One 1,117,000. 2021-08- 2021-09- 2021-10- 2021-11- 2021-12- 2022- par RC et RLTPC d’environ IBRD / 88450 Post Request for Bids Open - National 0.00 Implemen improved access to Envelope 00 31 05 17 16 21 06-19 200 km de routes rurales de tation markets la Région du Béré CI-PPCA-225626-CW-RFQ / Réalisation de travaux 2. Productivity agricoles Pending enhancement and Request for Single Stage - One 100,000.0 2021-07- 2021-08- 2022- d'opérationnalisation des 3 IBRD / 88450 Post Limited 0.00 Implemen improved access to Quotations Envelope 0 01 26 02-22 CDC priorisés pour la mise tation markets en place des essais de recherche agronomique 2021 GOODS Activity Reference No. Estimated Actual Draft Pre- Draft Bidding Specific Proposal Bid Evaluation Loan / Credit Market Procurement Prequalificatio Process Prequalification Bidding Documents Contract / Description Component Review Type Method Amount Amount qualification Document / Procurement Notice Submission / Report and Signed Contract No. Approach Process n (Y/N) Status Evaluation Report as Issued Completion (US$) (US$) Documents Justification / Invitation Opening / Minutes Recommendation Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned for Award Actual Planned Actual Planned Actual CI-FIRCA-67982-GO-RFQ 4. Program coordination, / Acquisition de 20 motos Request for Single Stage - One 2018-09- 2018-07- 2018-10- 2018-09- 2019-04- 2018-10- IBRD / 88450 monitoring and knowledge Post Limited 34.00 26,617.94 Completed pour renforcer le dispositif Quotations Envelope 03 27 29 27 27 27 management de collecte des données CI-FIRCA-74132-GO-RFB / 1. Institutional FOURNITURES DE SACS AUX Single Stage - One 2018-10- 2019-01- 2018-10- 2018-12- 2019-02- 2019-01- 2019-02- 2019-02- 2019-04- 2019-08- 2019-06- IBRD / 88450 strengthening and value Post Request for Bids Open - National 975,000.00 790,751.50 Completed PRODUCTEURS DES NOIX DE Envelope 18 04 23 04 15 03 22 07 24 14 07 chain governance CAJOU CI-FIRCA-68046-GO-RFB / Acquisition de véhicules 4. Program coordination, Single Stage - One 2018-07- 2018-08- 2018-09- 2018-10- 2018-11- 2019-05- pour l'UGP (3), la DOPA(1) IBRD / 88450 monitoring and knowledge Post Request for Bids Open - National 351.00 0.00 Canceled Envelope 31 05 16 16 20 19 l'ARRE (1) et le management CCA(1 ) CI-FIRCA-74620-GO-RFQ 4. Program coordination, Request for Single Stage - One 2018-09- 2018-08- 2018-10- 2018-11- 2019-04- 2018-12- / Acquisitions de véhicules IBRD / 88450 monitoring and knowledge Post Limited 499,000.00 526,591.31 Completed Quotations Envelope 01 31 27 02 25 15 pour l' UCP management CI-FIRCA-74630-GO-RFQ / Acquisition de matériel informatique (ordinateur 4. Program coordination, Request for Single Stage - One 2018-10- 2018-12- 2019-06- portable, desktop, disque IBRD / 88450 monitoring and knowledge Post Limited 99,000.00 0.00 Canceled Quotations Envelope 09 04 02 dur externe, imprimante, management serveurs et onduleur) pour l'UCP et le CCA CI-FIRCA-74643-GO-RFQ 4. Program coordination, / Acquisition de mobiliers Request for Single Stage - One 2018-10- 2018-11- 2018-12- 2019-01- 2019-06- 2019-02- IBRD / 88450 monitoring and knowledge Post Limited 99,000.00 19,353.34 Completed de bureau pour le CCA et Quotations Envelope 09 27 04 08 02 10 management la DOPA CI-FIRCA-74713-GO-RFB / Acquisition des équipements informatiques 1. Institutional Single Stage - One 2019-10- 2018-01- 2019-10- 2019-12- 2019-02- 2020-01- 2019-03- 2020-02- 2019-05- 2020-08- pour (i) la Plateforme IBRD / 88450 strengthening and value Post Request for Bids Open - National 320,000.00 415,851.84 Signed Envelope 22 15 27 08 19 07 06 11 14 09 électronique du Registre chain governance central de l'ARRE, (ii) des 10 entrepôts SRE et (iii) le local technique CI-FIRCA-74715-GO-RFQ / Acquisition du matériel et 1. Institutional Request for Single Stage - One 2018-09- 2018-09- 2018-10- 2018-11- 2019-04- 2018-11- mobilier de bureau pour le IBRD / 88450 strengthening and value Post Limited 50,000.00 32,166.47 Completed Quotations Envelope 04 05 30 13 28 27 local technique chain governance (15 bureaux complets) ARRE CI-FIRCA-82269-GO-RFQ 2. Productivity / Acquérir des prototypes Pending enhancement and Request for Single Stage - One 2018-11- 2018-12- 2019-06- d'outils mécaniques à IBRD / 88450 Post Limited 60,000.00 0.00 Implement improved access to Quotations Envelope 03 29 27 adapter au ramassage de la ation markets récolte en cajou culture CI-FIRCA-82285-GO-RFQ / Acquisition de matériel informatique (ordinateur portable, desktop, disque 4. Program coordination, Pending Request for Single Stage - One 2018-10- 2018-12- 2019-06- dur externe, imprimante, IBRD / 88450 monitoring and knowledge Post Limited 99,000.00 0.00 Implement Quotations Envelope 23 18 16 serveurs et onduleur) et management ation bureautique (photocopieuses, scanneurs, téléphones fixes et mobiles, fax) pour l'UCP et le CCA CI-FIRCA-82289-GO-RFQ 2. Productivity Request for Single Stage - One 2018-11- 2019-01- 2019-07- / Acquisition d'un véhicule IBRD / 88450 enhancement and Post Limited 64,000.00 0.00 Canceled Quotations Envelope 07 02 01 de type 4x4 pour improved access to l'AGEROUTE markets CI-FIRCA-82291-GO-RFQ / Acquisition de matériel 2. Productivity informatique et bureautique enhancement and Request for Single Stage - One 2018-12- 2019-01- 2019-07- (ordinateurs, imprimantes, IBRD / 88450 Post Limited 19,000.00 0.00 Canceled improved access to Quotations Envelope 05 30 29 etc.), de consommables markets informatiques pour l'année 1 et 2 CI-FIRCA-82292-GO-RFQ / Acquisition de matériel 2. Productivity informatique et bureautique enhancement and Request for Single Stage - One 2019-04- 2019-05- 2019-11- (ordinateurs, imprimantes, IBRD / 88450 Post Limited 19,000.00 0.00 Canceled improved access to Quotations Envelope 03 29 25 etc.), de consommables markets informatiques pour l'année 1 et 2 CI-FIRCA-82591-GO-RFQ 4. Program coordination, Request for Single Stage - One 2018-10- 2018-09- 2018-12- 2018-11- 2019-06- 2019-04- / Acquisition de mobiliers IBRD / 88450 monitoring and knowledge Post Limited 50,000.00 31,795.01 Completed Quotations Envelope 23 05 18 13 16 02 de bureau management CI-FIRCA-74612-GO-DIR / Acquisition et installation d'équipements 1. Institutional Pending 2018-11- 2018-12- 2019-01- 2019-07- technologiques de IBRD / 88450 strengthening and value Post Direct Selection Direct 850,000.00 0.00 Implement 30 05 09 08 transformation du CITA chain governance ation dans le cadre du partenariat entre le CCA et l'Université de HO CHI MIN CI-FIRCA-76396-GO-RFQ 4. Program coordination, Request for Single Stage - One 2018-12- 2018-12- 2019-01- 2019-02- 2019-07- 2019-04- / Acquisition de carburant IBRD / 88450 monitoring and knowledge Post Limited 100,000.00 91,975.21 Signed Quotations Envelope 05 04 30 20 29 06 pour le projet management CI-FIRCA-82274-GO-DIR / Entente directe avec ICRAF pour la Fourniture et l' 2. Productivity installation de 34 stations enhancement and 2018-11- 2019-01- 2018-12- 2019-01- 2019-01- 2019-02- 2019-07- 2019-05- IBRD / 88450 Post Direct Selection Direct 22,348,000.00 217,424.35 Completed agro-météorologiques improved access to 29 22 04 22 08 20 07 31 additionnelles pour une markets meilleure couverture de la zone du projet CI-FIRCA-97637-GO-DIR / 1. Institutional Fourniture d'imprimés 2019-02- 2019-02- 2019-02- 2019-03- 2019-02- 2019-09- 2019-03- IBRD / 88450 strengthening and value Post Direct Selection Direct 151,000.00 138,128.49 Completed sécurisées de récépissés 08 13 04 20 20 16 20 chain governance d'entreposage pour l'ARRE CI-FIRCA-106486-GO-RFQ 1. Institutional Request for Single Stage - One 2019-04- 2019-05- 2019-06- 2019-07- 2019-11- 2019-07- / Acquisition du Matériel IBRD / 88450 strengthening and value Post Limited 56,000.00 37,306.84 Completed Quotations Envelope 06 03 01 02 28 17 Informatique pour le CCA chain governance CI-FIRCA-106494-GO-RFB / Acquisition de 80 000 1. Institutional cartes destinées aux Single Stage - One 2019-03- 2019-06- 2019-04- 2019-06- 2019-05- 2019-07- 2019-06- 2019-07- 2019-07- 2019-09- 2020-01- IBRD / 88450 strengthening and value Post Request for Bids Open - National 112,000.00 195,631.53 Signed producteurs bénéficiaires Envelope 30 12 04 23 16 11 15 11 20 05 16 chain governance du projet, pour la collecte électronique de données CI-FIRCA-106496-GO-DIR / Entente directe avec SOTIC pour l'acquisition de petits équipements de 1. Institutional 2019-03- 2019-03- 2019-05- 2019-04- 2019-05- 2019-10- 2019-09- transformation pour la mise IBRD / 88450 strengthening and value Post Direct Selection Direct 325,000.00 396,659.00 Completed 18 23 02 27 08 24 04 en œuvre d'un programme chain governance d'accompagnement des sociétés coopératives pour la transformation CI-FIRCA-106497-GO-RFQ / Fourniture d'un photocopieur à grand tirage, de kits composés de 1. Institutional trois vidéoprojecteurs et de Request for Single Stage - One 2019-04- 2019-04- 2019-06- 2019-05- 2019-11- 2019-06- IBRD / 88450 strengthening and value Post Limited 33,000.00 28,753.82 Completed quatre ordinateurs Quotations Envelope 06 10 01 08 28 07 chain governance portables pour la DOPA et dotation la salle des serveurs d'un rack et d'un système de détection anti- humidité CI-FIRCA-106502-GO-DIR / Entente directe avec 1. Institutional l'université HO CHI MIN 2019-03- 2019-03- 2019-05- 2019-05- 2019-05- 2019-10- 2019-08- IBRD / 88450 strengthening and value Post Direct Selection Direct 130,000.00 100,132.25 Completed pour l'acquisition de 130 25 30 02 04 08 31 13 chain governance humidimètres pour les agents du CCA CI-FIRCA-106547-GO-DIR / Entente directe avec ICRAF 2. Productivity pour la fourniture et enhancement and 2019-03- 2019-05- 2019-03- 2019-05- 2019-05- 2019-06- 2019-10- IBRD / 88450 Post Direct Selection Direct 267,000.00 349,059.19 Signed l'installation d' un improved access to 22 20 27 28 01 06 28 laboratoire d'analyse markets pédologique de développement CI-FIRCA-106548-GO-DIR 2. Productivity Under / Entente directe avec le enhancement and 2019-04- 2019-03- 2019-04- 2019-05- 2019-11- IBRD / 88450 Post Direct Selection Direct 56,000.00 0.00 Implement CNRA pour la fourniture de improved access to 10 04 15 20 16 ation greffons aux pépiniéristes markets privés CI-FIRCA-106600-GO-RFB 2. Productivity Single Stage - One 2019-03- 2019-03- 2019-03- 2019-05- 2019-04- 2019-06- 2019-05- 2019-07- 2019-06- 2020-01- 2019-06- / Acquisition de 309 motos IBRD / 88450 enhancement and Post Request for Bids Open - National 999,000.00 793,227.58 Completed Envelope 25 15 30 11 29 10 02 15 03 11 05 pour l'ANADER improved access to markets CI-FIRCA-106662-GO-RFQ 4. Program coordination, Request for Single Stage - One 2019-04- 2019-05- 2019-05- 2019-05- 2019-11- 2019-05- / Fournitures de bureau IBRD / 88450 monitoring and knowledge Post Limited 60,000.00 36,243.38 Completed Quotations Envelope 05 02 31 17 27 31 pour l'UCP management CI-FIRCA-106672-GO-RFQ 4. Program coordination, / Equipement des locaux Request for Single Stage - One 2019-03- 2019-03- 2019-05- 2019-04- 2019-11- 2019-07- IBRD / 88450 monitoring and knowledge Post Limited 65,000.00 49,985.36 Completed aménagés du PPCA Quotations Envelope 23 14 18 05 14 11 management (mobiliers et matériel de bureau) CI-FIRCA-106890-GO-RFQ 3. Support to private / Edition de supports de investment in post-harvest Request for Single Stage - One 2019-07- 2019-10- 2019-08- 2019-11- 2020-02- 2020-03- communication sur les IBRD / 88450 Post Limited 28,000.00 939.50 Completed and processing Quotations Envelope 06 18 31 14 27 12 mécanismes de financement infrastructure à coûts partagés CI-FIRCA-107947-GO-RFQ 4. Program coordination, Request for Single Stage - One 2019-04- 2019-06- 2019-06- 2019-07- 2019-12- 2019-07- / Fourniture de IBRD / 88450 monitoring and knowledge Post Limited 40,000.00 35,460.81 Completed Quotations Envelope 28 14 23 11 20 22 consommables management informatiques pour l'UCP CI-FIRCA-106538-GO-RFQ 2. Productivity / Acquisition des enhancement and Request for Single Stage - One 2019-04- 2020-04- 2019-05- 2019-05- 2019-11- IBRD / 88450 Post Limited 84,000.00 54,524.74 Signed équipements informatiques improved access to Quotations Envelope 05 17 31 07 27 pour les prestataires du markets PNRA CI-FIRCA-126660-GO-DIR 2. Productivity / Fourniture de greffons Pending enhancement and 2019-08- 2019-08- 2019-09- 2020-03- aux pépiniéristes privés et IBRD / 88450 Post Direct Selection Direct 25,000.00 0.00 Implement improved access to 13 18 22 20 des plants greffés aux ation markets producteurs. CI-FIRCA-126674-GO-DIR 2. Productivity / Fourniture de greffons Pending enhancement and 2019-08- 2019-08- 2019-09- 2020-03- aux pépiniéristes privés et IBRD / 88450 Post Direct Selection Direct 28,000.00 0.00 Implement improved access to 15 20 24 22 des plants greffés aux ation markets producteurs CI-FIRCA-126681-GO-DIR 2. Productivity Pending / Fourniture des plants enhancement and 2019-08- 2019-08- 2019-09- 2020-03- IBRD / 88450 Post Direct Selection Direct 195,000.00 0.00 Implement greffés par les pépiniéristes improved access to 15 20 24 22 ation privés aux producteurs markets CI-FIRCA-126692-GO-RFB / Acquisition et installation 2. Productivity Pending des infrastructures de base enhancement and Single Stage - One 2019-10- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- IBRD / 88450 Post Request for Bids Open - National 150,000.00 0.00 Implement (conteneurs aménagés) improved access to Envelope 30 04 16 15 19 17 ation d’opérationnalisation des 3 markets CDC priorisés CI-FIRCA-126695-GO-DIR / Acquisition de 7 véhicules doubles cabines pour le 1. Institutional renforcement de la 2019-08- 2019-10- 2019-08- 2019-10- 2019-09- 2019-10- 2020-03- 2019-12- IBRD / 88450 strengthening and value Post Direct Selection Direct 210,000.00 202,762.83 Completed coordination des activités à 20 03 25 03 29 10 27 04 chain governance mettre en œuvre par le CCA sur le terrain et le programme anacarde du CNRA Korhogo CI-FIRCA-126702-GO-DIR 2. Productivity / Acquisition de matériels enhancement and 2019-08- 2019-08- 2019-08- 2019-08- 2019-09- 2019-09- 2020-03- 2019-10- de réhabilitation de IBRD / 88450 Post Direct Selection Direct 146,000.00 111,297.31 Completed improved access to 20 20 25 27 29 24 27 18 plantations d’anacarde markets (Tronçonneurs, secateurs….) CI-FIRCA-106534-GO-RFQ 2. Productivity / Acquisition de 2 enhancement and Request for Single Stage - One 2019-03- 2019-05- 2019-11- véhicules pickup up 4 x 4 IBRD / 88450 Post Limited 112,000.00 0.00 Canceled improved access to Quotations Envelope 25 20 16 pour le Programme markets Anacarde du CNRA Korhogo CI-FIRCA-74716-GO-RFQ 1. Institutional Request for Single Stage - One 2018-10- 2018-12- 2019-06- / Fournitures et IBRD / 88450 strengthening and value Post Limited 83,000.00 0.00 Canceled Quotations Envelope 30 25 23 installations de climatiseurs chain governance a l'ARRE CI-FIRCA-82300-GO-RFQ 2. Productivity / Acquisition de divers enhancement and Request for Single Stage - One 2018-11- 2019-01- 2019-07- IBRD / 88450 Post Limited 5,000.00 0.00 Canceled mobiliers de bureau pour improved access to Quotations Envelope 07 02 01 l'AGEROUTE markets CI-FIRCA-74623-GO-RFQ 2. Productivity / Edition des outils enhancement and Request for Single Stage - One 2018-12- 2019-02- 2019-08- IBRD / 88450 Post Limited 40,000.00 0.00 Canceled didactiques du Conseil improved access to Quotations Envelope 15 09 08 Agricole dédié à l'Anacarde markets Page 2 CI-FIRCA-67980-GO-RFQ / Acquisition de matériels informatiques (ordinateur portable, desktop, disque dur externe, imprimante, 4. Program coordination, Request for Single Stage - One 2018-09- 2018-10- 2019-04- serveurs et onduleur) et IBRD / 88450 monitoring and knowledge Post Limited 99,000.00 0.00 Canceled Quotations Envelope 05 31 29 matériels bureautiques management (photocopieuses, scanneurs, téléphones fixes et mobiles, fax)-DOCKIN STATION pour l'UGP CI-FIRCA-82302-GO-RFQ 2. Productivity / Acquisition de carburant enhancement and Request for Single Stage - One 2018-11- 2019-01- 2019-07- IBRD / 88450 Post Limited 41,000.00 0.00 Canceled et lubrifiant pour la durée improved access to Quotations Envelope 07 02 01 du Projet pour l'AGEROUTE markets CI-FIRCA-82287-GO-RFQ 2. Productivity Request for Single Stage - One 2018-12- 2019-01- 2019-07- / Acquisition d'un véhicule IBRD / 88450 enhancement and Post Limited 64,000.00 0.00 Canceled Quotations Envelope 05 30 29 de type 4x4 pour improved access to l'AGEROUTE markets CI-FIRCA-106498-GO-RFQ / Acquisition de 4 véhicules dont 3 doubles cabines 1. Institutional Request for Single Stage - One 2019-03- 2019-05- 2019-11- pour le renforcement de la IBRD / 88450 strengthening and value Post Limited 97,000.00 0.00 Canceled Quotations Envelope 23 18 14 coordination des activités à chain governance mettre en œuvre par le CCA sur le terrain CI-FIRCA-126875-GO-RFQ 1. Institutional / Acquisition et installation Request for Single Stage - One 2019-10- 2019-12- 2020-06- IBRD / 88450 strengthening and value Post Limited 60,000.00 0.00 Canceled de locaux préfabriqués pour Quotations Envelope 15 10 07 chain governance abriter le labo de pédologie CI-FIRCA-74652-GO-RFB / 1. Institutional Acquisitions d'équipements Single Stage - One 2019-04- 2019-04- 2019-05- 2019-06- 2019-07- 2020-01- IBRD / 88450 strengthening and value Post Request for Bids Open - National 150.00 0.00 Canceled d'entrepôt dans le cadre de Envelope 08 13 25 24 29 25 chain governance l'amélioration post récolte CI-FIRCA-74712-GO-RFB / Acquisition d'équipements informatiques pour la 1. Institutional dématérialisation des Single Stage - One 2018-10- 2018-11- 2018-12- 2019-01- 2019-02- 2019-08- IBRD / 88450 strengthening and value Post Request for Bids Open - National 500,000.00 0.00 Canceled procédures d'exportation Envelope 30 04 16 15 19 18 chain governance des noix brutes de cajou (plateforme d'Echanges de Données Informatisées CI-FIRCA-74634-GO-RFB / Acquisition d'équipements 2. Productivity audiovisuel pour faciliter la enhancement and Single Stage - One 2019-02- 2019-02- 2019-03- 2019-04- 2019-05- 2019-11- IBRD / 88450 Post Request for Bids Open - National 218,000.00 0.00 Canceled sensibilisation des improved access to Envelope 06 11 25 24 29 25 producteurs par les agents markets de vulgarisation et pour l'UCP CI-FIRCA-157483-GO-RFB / Sélection de fournisseurs 2. Productivity pour la fourniture des enhancement and Single Stage - One 2020-03- 2020-06- 2020-03- 2020-05- 2020-06- 2020-05- 2020-06- 2020-07- 2020-07- 2021-01- semences pour la mise en IBRD / 88450 Post Request for Bids Open - National 28,000.00 24,086.32 Signed improved access to Envelope 15 15 20 01 19 31 19 05 06 01 place de tests de cultures markets vivrières en intercalaire dans les parcelles de démonstration des CEP CI-FIRCA-157485-GO-DIR / Sélection par Entente 2. Productivity Pending Directe du CNRA pour la enhancement and 2020-03- 2020-03- 2020-04- 2020-10- IBRD / 88450 Post Direct Selection Direct 20,000.00 0.00 Implement fourniture des greffons aux improved access to 02 07 11 08 ation pépiniéristes pour la markets production des plants greffés CI-FIRCA-157486-GO-DIR / Sélection par Entente Directe de M NIAMKE André 2. Productivity Pending Claude, pépiniériste de enhancement and 2020-03- 2020-03- 2020-04- 2020-10- IBRD / 88450 Post Direct Selection Direct 13,000.00 0.00 Implement Yamoussoukro pour la improved access to 02 07 11 08 ation fourniture des greffons aux markets pépiniéristes pour la production des plants greffés CI-FIRCA-157487-GO-DIR / Sélection par Entente 2. Productivity Directe de M CHERIF Pending enhancement and 2020-03- 2020-03- 2020-04- 2020-10- Mamadou , pépiniériste de IBRD / 88450 Post Direct Selection Direct 17,000.00 0.00 Implement improved access to 02 07 11 08 Séguéla pour la fourniture ation markets des greffons aux pépiniéristes pour la production des plants greffés CI-FIRCA-157497-GO-RFB 2. Productivity / Sélection de fournisseurs enhancement and Single Stage - One 2020-03- 2020-04- 2020-03- 2020-04- 2020-04- 2020-06- 2020-05- 2020-06- 2020-06- 2020-07- 2020-12- 2020-10- d'engrais foliaires IBRD / 88450 Post Request for Bids Open - National 978,000.00 1,021,038.04 Completed improved access to Envelope 02 17 07 22 18 12 18 06 22 03 19 16 organiques pour la markets fertilisation des vergers réhabilités CI-FIRCA-157503-GO-DIR 2. Productivity / Sélection de fournisseurs enhancement and 2020-03- 2020-05- 2020-04- 2020-05- 2020-05- 2020-07- 2020-11- 2020-08- des équipements et IBRD / 88450 Post Direct Selection Direct 131,000.00 121,628.64 Completed improved access to 31 19 05 22 10 03 06 11 matériels techniques des markets OPCA (tronçonneurs) CI-FIRCA-157507-GO-RFB 2. Productivity / Sélection de fournisseurs enhancement and Single Stage - One 2020-02- 2020-04- 2020-03- 2020-04- 2020-04- 2020-06- 2020-05- 2020-06- 2020-06- 2020-07- 2020-12- 2020-11- de produits insecticides IBRD / 88450 Post Request for Bids Open - National 326,000.00 341,972.18 Completed improved access to Envelope 29 17 05 22 16 02 16 06 20 03 17 25 pour la protection des markets vergers réhabilités CI-FIRCA-82266-GO-RFB / 2. Productivity Contractualiser avec les enhancement and Single Stage - One 2018-10- 2018-11- 2018-12- 2019-01- 2019-02- 2019-08- IBRD / 88450 Post Request for Bids Open - National 123,000.00 0.00 Canceled pépiniéristes privés pour la improved access to Envelope 29 03 15 14 18 17 production des plants markets greffés CI-FIRCA-82275-GO-RFB / 2. Productivity Acquisition de 130 enhancement and Single Stage - One 2018-12- 2018-12- 2019-02- 2019-03- 2019-04- 2019-10- IBRD / 88450 Post Request for Bids Open - National 130,000.00 0.00 Canceled humidimètres pour les improved access to Envelope 26 31 11 13 17 14 agents du CCA markets CI-FIRCA-106543-GO-RFB 2. Productivity / Acquisition des enhancement and Single Stage - One 2019-04- 2019-05- 2019-06- 2019-07- 2019-08- 2020-02- IBRD / 88450 Post Request for Bids Open - National 240,000.00 0.00 Canceled équipements techniques improved access to Envelope 30 05 16 16 20 16 pour les prestataires du markets PNRA CI-FIRCA-106489-GO-RFB / Acquisition de mobilier de bureau pour le Conseil du Coton et de l'Anacarde pour 1. Institutional Pending Single Stage - One 2020-04- 2020-04- 2020-06- 2020-07- 2020-08- 2021-02- l'Annexe du CCA au 2 IBRD / 88450 strengthening and value Post Request for Bids Open - National 101,000.00 0.00 Implement Envelope 15 20 01 01 05 01 Plateaux Vallon et pour les chain governance ation 4 DR du Conseil du Coton et de l'Anacarde devant accueillir les Consultants CI-FIRCA-106490-GO-RFB 1. Institutional Pending / Acquisition des Single Stage - One 2020-08- 2020-08- 2020-10- 2020-10- 2020-12- 2021-06- IBRD / 88450 strengthening and value Post Request for Bids Open - National 110,000.00 0.00 Implement équipements pour Envelope 15 20 01 31 05 03 chain governance ation l'interconnexion entre les différents sites du CCA CI-FIRCA-157581-GO-RFQ 4. Program coordination, Request for Single Stage - One 2020-03- 2020-04- 2020-05- 2020-06- 2020-11- / Acquisition d'ordinateurs IBRD / 88450 monitoring and knowledge Post Limited 20,000.00 17,717.11 Signed Quotations Envelope 11 15 06 15 02 portables pour l'UCP management CI-FIRCA-157597-GO-RFQ / Acquisition de matériel informatique (Rack pour 4. Program coordination, Server HP Proliant DL580 Request for Single Stage - One 2020-03- 2020-04- 2020-05- 2020-06- 2020-11- IBRD / 88450 monitoring and knowledge Post Limited 4,000.00 4,763.79 Signed Gen9, Cordon réseau Quotations Envelope 21 15 16 16 12 management Ethernet RJ45 de 3m (10) - Trousse maintenance info (Réseau, souffleur)….) CI-FIRCA-157599-GO-RFQ / Acquisition d'appareil 4. Program coordination, audiovisuel (Ecran TV 52" , Request for Single Stage - One 2020-03- 2020-04- 2020-05- 2020-06- 2020-11- 2020-07- IBRD / 88450 monitoring and knowledge Post Limited 19,000.00 12,623.80 Completed Appareil photos, Sono Quotations Envelope 21 15 16 10 12 15 management Mobile, dictaphones ...), vidéo projecteurs CI-FIRCA-157684-GO-RFQ 1. Institutional / Acquisition de tablettes Request for Single Stage - One 2020-03- 2020-09- 2020-05- 2020-11- 2020-11- 2021-03- IDA / V0300 strengthening and value Post Limited 28,000.00 23,190.55 Completed pour la collecte électronique Quotations Envelope 14 30 09 09 05 04 chain governance et le suivi des activités CI-FIRCA-157951-GO-RFQ 1. Institutional / Acquisition de matériel de Request for Single Stage - One 2020-03- 2020-10- 2020-05- 2020-12- 2020-11- IBRD / 88450 strengthening and value Post Limited 9,000.00 29,425.47 Signed nettoyage Haute Pression Quotations Envelope 22 16 17 01 13 chain governance (HP) (01 en station et 01 mobile) CI-FIRCA-157965-GO-RFQ 1. Institutional Request for Single Stage - One 2020-03- 2020-10- 2020-05- 2020-11- 2020-11- / Acquisition d'une station IBRD / 88450 strengthening and value Post Limited 11,000.00 47,681.14 Signed Quotations Envelope 28 16 23 26 19 de stockage d'azote chain governance CI-FIRCA-157972-GO-RFQ 1. Institutional / Acquisition de l'outillage Request for Single Stage - One 2020-03- 2020-05- 2020-05- 2020-07- 2020-11- IBRD / 88450 strengthening and value Post Limited 93,000.00 73,099.45 Signed du CITA (caisses à outils, Quotations Envelope 28 14 23 15 19 chain governance poste à souder...) CI-FIRCA-157977-GO-RFQ / Acquisition d'un ensemble 1. Institutional Request for Single Stage - One 2020-03- 2020-10- 2020-05- 2020-11- 2020-11- pour la maîtrise des bilans IBRD / 88450 strengthening and value Post Limited 19,000.00 58,684.48 Signed Quotations Envelope 28 16 23 26 19 matières (balances de chain governance pesées, poids étalons ...) CI-FIRCA-157984-GO-RFQ 1. Institutional Pending Request for Single Stage - One 2020-03- 2020-05- 2020-11- / Acquisition du mobilier IBRD / 88450 strengthening and value Post Limited 56,000.00 0.00 Implement Quotations Envelope 28 23 19 complémentaire du CITA chain governance ation CI-FIRCA-158227-GO-RFQ / Acquisition au profit de la 1. Institutional DOPA de compléments Request for Single Stage - One 2020-03- 2020-07- 2020-04- 2020-08- 2020-10- 2020-09- IBRD / 88450 strengthening and value Post Limited 9,000.00 9,163.40 Completed d'ordinateurs portables Quotations Envelope 04 28 29 25 26 09 chain governance destinés aux missions de terrain CI-FIRCA-77660-GO-RFB / 4. Program coordination, acquisition de 20 motos Single Stage - One 2018-07- 2018-10- 2018-10- 2018-12- 2019-01- 2019-02- 2020-08- IBRD / 88450 monitoring and knowledge Post Request for Bids Limited 34,000.00 0.00 Canceled pour renforcer le dispositif Envelope 25 10 10 19 18 22 15 management de collecte de données. CI-FIRCA-106493-GO-RFB / Acquisition de lecteurs 1. Institutional Single Stage - One 2019-03- 2019-04- 2019-05- 2019-06- 2019-07- 2020-01- (terminaux) des cartes IBRD / 88450 strengthening and value Post Request for Bids Open - National 110,000.00 0.00 Canceled Envelope 30 04 16 15 20 16 acquises pour les chain governance bénéficiaires du projet CI-FIRCA-157477-GO-DIR / Acquisition d'équipements 2. Productivity Pending technique et scientifique enhancement and 2020-03- 2020-04- 2020-05- 2020-11- IBRD / 88450 Post Direct Selection Direct 140,000.00 0.00 Implement complémentaires pour les improved access to 31 05 10 06 ation INRA du PNRA : markets equipement d’Analyse des sols CI-FIRCA-157478-GO-DIR / Acquisition d'équipements 2. Productivity Pending technique et scientifique enhancement and 2020-03- 2020-04- 2020-05- 2020-11- IBRD / 88450 Post Direct Selection Direct 140,000.00 0.00 Implement complémentaires pour les improved access to 31 05 10 06 ation INRA du PNRA:Equipements markets de physiologie végétale. CI-FIRCA-157472-GO-DIR / Acquisition d'équipements 2. Productivity Pending technique et scientifique enhancement and 2020-03- 2020-03- 2020-05- 2020-10- IBRD / 88450 Post Direct Selection Direct 280,000.00 0.00 Implement complémentaires pour les improved access to 22 27 01 28 ation INRA du PNRA : markets equipements de Biotechnologie CI-FIRCA-167394-GO-RFQ 4. Program coordination, 2020-04- 2019-08- 2020-04- 2019-09- 2020-05- 2019-09- 2020-11- / Acquisition de matériels IBRD / 88450 monitoring and knowledge Post Direct Selection Direct 6,000.00 4,789.51 Signed 15 28 20 02 25 19 21 de bureau pour l'UCP-PPCA management CI-FIRCA-179996-GO-RFQ / ACQUISITION DE 4. Program coordination, Request for Single Stage - One 2020-06- 2020-07- 2020-08- 2020-08- 2021-02- 2020-11- MOBILIERS DE BUREAU POUR IBRD / 88450 monitoring and knowledge Post Limited 19,000.00 13,288.20 Completed Quotations Envelope 23 10 18 06 14 11 LE PERSONNEL DE GESTION management FIDUCIAIRE DU PPCA CI-FIRCA-180002-GO-RFQ 2. Productivity / SELECTION D'UN Pending enhancement and Request for Single Stage - One 2020-06- 2020-08- 2021-02- PRESTATAIRE POUR IBRD / 88450 Post Limited 30,000.00 0.00 Implement improved access to Quotations Envelope 21 16 12 L'EDITION DES FICHES DE ation markets VALIDATION DES PARCELLES REHABILITEES CI-FIRCA-157479-GO-RFQ 2. Productivity / Sélection d'un enhancement and Request for Single Stage - One 2020-02- 2020-04- 2020-10- fournisseurs pour IBRD / 88450 Post Limited 39,000.00 0.00 Canceled improved access to Quotations Envelope 29 25 22 l'acquisition des matières markets d'œuvres de construction des équipements CI-FIRCA-157480-GO-RFB / Sélection de fournisseur 2. Productivity Pending pour la fourniture enhancement and Single Stage - One 2020-02- 2020-02- 2020-04- 2020-05- 2020-06- 2020-12- IBRD / 88450 Post Request for Bids Open - National 14,000.00 0.00 Implement d'équipements improved access to Envelope 20 25 07 07 11 08 ation informatiques dans le cadre markets de la mise en oeuvre de l'e- extension CI-FIRCA-157502-GO-RFB 2. Productivity / Sélection de fournisseurs enhancement and Single Stage - One 2020-03- 2020-04- 2020-03- 2020-04- 2020-04- 2020-05- 2020-06- 2020-12- de produits fongicides pour IBRD / 88450 Post Request for Bids Open - National 326,000.00 0.00 Canceled improved access to Envelope 02 17 07 22 18 18 22 19 la protection des vergers markets réhabilités CI-FIRCA-191626-GO-RFQ / Acquisition des équipements informatiques 2. Productivity Pending pour la SODEXAM dans le enhancement and Request for Single Stage - One 2020-10- 2020-12- 2021-05- IBRD / 88450 Post Limited 20,000.00 0.00 Implement cadre de l'appui à la gestion improved access to Quotations Envelope 06 01 30 ation de la résilience des markets producteurs d'anacarde au changement climatique CI-FIRCA-191629-GO-RFQ / Acquisition de Logiciels de 2. Productivity Pending traitement et d'analyse enhancement and Request for Single Stage - One 2020-10- 2020-12- 2021-05- IBRD / 88450 Post Limited 20,000.00 0.00 Implement agrométéorologique improved access to Quotations Envelope 07 02 31 ation (licence tableau Creator, markets Viewer, Explorer) version serveur CI-FIRCA-82267-GO-RFQ / Acquérir un véhicule type 2. Productivity 4x4 pour les missions de enhancement and Request for Single Stage - One 2020-09- 2020-09- 2020-11- 2020-11- 2021-05- 2020-11- collecte des données de la IBRD / 88450 Post Limited 60,000.00 36,607.56 Completed improved access to Quotations Envelope 26 22 21 03 20 17 veille sanitaire dans le cadre markets du volet défense des cultures du PNRA CI-FIRCA-157493-GO-RFB 2. Productivity / Sélection de fournisseurs enhancement and Single Stage - One 2020-03- 2020-04- 2020-05- 2020-06- 2020-07- 2021-01- de semences et de plants IBRD / 88450 Post Request for Bids Open - National 298,000.00 0.00 Canceled improved access to Envelope 31 05 17 16 21 17 dans le cadre du markets reboisement compensatoire CI-FIRCA-192569-GO-RFQ 1. Institutional / Acquisition du matériel Request for Single Stage - One 2020-09- 2020-09- 2020-11- 2020-11- 2021-05- 2020-11- IBRD / 88450 strengthening and value Post Limited 145,000.00 147,116.40 Completed roulant ( véhicules et Quotations Envelope 27 18 22 08 21 17 chain governance autobus) pour le CITA CI-FIRCA-192581-GO-RFQ 1. Institutional Pending Request for Single Stage - One 2020-09- 2020-11- 2021-05- / Acquisition de motos IBRD / 88450 strengthening and value Post Limited 4,000.00 0.00 Implement Quotations Envelope 26 21 20 pour le CITA chain governance ation CI-FIRCA-157939-GO-RFB 1. Institutional / Acquisition du matériel Single Stage - One 2020-03- 2020-03- 2020-05- 2020-06- 2020-07- 2021-01- IBRD / 88450 strengthening and value Post Request for Bids Open - National 149,000.00 0.00 Canceled roulant (moto, véhicules et Envelope 17 22 03 02 07 03 chain governance autobus) pour le CITA CI-FIRCA-191620-GO-DIR / Sélection par entente 2. Productivity directe de INTEL AFRIQUE enhancement and 2020-09- 2020-11- 2020-10- 2020-10- 2020-11- 2020-12- 2021-05- 2020-12- pour l'acquisition de la IBRD / 88450 Post Direct Selection Direct 41,000.00 36,837.80 Completed improved access to 30 12 05 06 09 08 08 16 Licence informatique de markets communication de l'E- extension anacarde Page 3 CI-FIRCA-140582-GO-DIR / Acquisition d'équipements 2. Productivity techniques dans le cadre du enhancement and 2019-10- 2019-12- 2019-10- 2019-12- 2019-11- 2020-07- 2020-05- IBRD / 88450 Post Direct Selection Direct 140,000.00 231,547.62 Signed PNRA : équipements de improved access to 15 04 20 13 24 03 22 physiologie végétale (2ème markets tranche) CI-FIRCA-158219-GO-RFQ / Acquisition d'ordinateurs 1. Institutional portables dans le cadre du Request for Single Stage - One 2020-04- 2020-05- 2020-11- IBRD / 88450 strengthening and value Post Limited 82,000.00 0.00 Canceled renouvellement des Quotations Envelope 04 30 26 chain governance équipements des agents relais du CCA CI-FIRCA-158226-GO-RFQ / Acquisition de motos pour les agents relais et les 1. Institutional Pending Request for Single Stage - One 2020-03- 2020-05- 2020-11- Assistants des DR CCA de IBRD / 88450 strengthening and value Post Limited 50,000.00 0.00 Implement Quotations Envelope 21 16 12 Bondoukou, Bouna, chain governance ation Boundiali, Dimbokro, Katiola, Korhogo, Mankono, Odienné CI-FIRCA-157669-GO-RFQ / Acquisition de 1. Institutional Pending Request for Single Stage - One 2020-11- 2021-01- 2021-07- consommables IBRD / 88450 strengthening and value Post Limited 93,000.00 0.00 Implement Quotations Envelope 25 20 19 informatiques pour les chain governance ation imprimantes de cartes de producteurs CI-FIRCA-157685-GO-RFQ / Acquisition d'imprimantes 1. Institutional Request for Single Stage - One 2020-11- 2020-11- 2021-01- 2021-01- 2021-07- 2021-03- supplémentaires pour IBRD / 88450 strengthening and value Post Limited 28,000.00 56,925.66 Completed Quotations Envelope 25 30 20 11 19 16 imprimer les cartes des chain governance producteurs et autres acteurs CI-FIRCA-157678-GO-DIR 1. Institutional 2020-03- 2020-03- 2020-03- 2020-03- / Acquisition de 330 puces IBRD / 88450 strengthening and value Post Direct Selection 29,000.00 0.00 Canceled 07 07 07 07 data MTN avec 3 G0 par chain governance Mois CI-FIRCA-201985-GO-DIR 1. Institutional Pending 2020-11- 2020-11- 2020-12- 2021-06- / Acquisition de 330 puces IBRD / 88450 strengthening and value Post Direct Selection Direct 37,000.00 0.00 Implement 16 21 26 24 data avec 3 G0 par mois chain governance ation CI-FIRCA-158229-GO-RFQ / Acquisition au profit des 1. Institutional Pending Request for Single Stage - One 2021-01- 2021-03- 2021-09- SCOOP de transformation IBRD / 88450 strengthening and value Post Limited 93,000.00 0.00 Implement Quotations Envelope 25 22 18 de l'anacarde de kits pour le chain governance ation contrôle de qualité CI-FIRCA-157933-GO-RFQ / Acquisition et 1. Institutional installation de l'unité de Request for Single Stage - One 2020-07- 2020-08- 2021-02- IBRD / 88450 strengthening and value Post Limited 56,000.00 0.00 Canceled pyrolyse pour la Quotations Envelope 05 30 26 chain governance valorisation des coques en charbon au profit des ménages (sur le site du CITA) CI-FIRCA-157944-GO-RFB / Acquisition de matériel de 1. Institutional Single Stage - One 2020-03- 2020-03- 2020-05- 2020-06- 2020-07- 2021-01- manutention pour le CITA IBRD / 88450 strengthening and value Post Request for Bids Open - National 112,000.00 0.00 Canceled Envelope 17 22 03 02 07 03 (Chariots 3T; 1,5T; 02 chain governance transpalettes...) CI-FIRCA-201986-GO-RFQ 1. Institutional Under / Acquisition de matériels Request for Single Stage - One 2020-12- 2020-12- 2021-01- 2021-07- IBRD / 88450 strengthening and value Post Limited 25,000.00 0.00 Implement de manutention Quotations Envelope 05 10 30 29 chain governance ation électromécanisée pour le CITA CI-FIRCA-201987-GO-RFQ 1. Institutional Under / Acquisition de matériels Request for Single Stage - One 2020-12- 2020-12- 2021-01- 2021-07- IBRD / 88450 strengthening and value Post Limited 31,000.00 0.00 Implement de manutention manuelle Quotations Envelope 05 03 30 29 chain governance ation pour le CITA CI-FIRCA-201988-GO-RFQ 1. Institutional Pending / Acquisition de matériels Request for Single Stage - One 2020-12- 2021-01- 2021-07- IBRD / 88450 strengthening and value Post Limited 56,000.00 0.00 Implement de manutention motorisée Quotations Envelope 05 30 29 chain governance ation pour le CITA CI-FIRCA-157979-GO-RFQ / Acquisition du matériel 1. Institutional Pending Request for Single Stage - One 2021-01- 2021-03- 2021-09- de Communication IBRD / 88450 strengthening and value Post Limited 60,000.00 0.00 Implement Quotations Envelope 10 07 03 audiovisuel du CITA chain governance ation (Téléphone, Internet, vidéosurveillance) CI-FIRCA-157987-GO-RFQ / Acquisition d' 1. Institutional Equipements du centre Request for Single Stage - One 2020-03- 2020-05- 2020-11- IBRD / 88450 strengthening and value Post Limited 19,000.00 0.00 Canceled médical du CITA (table de Quotations Envelope 28 23 19 chain governance consultation, lits d'observation, matériel médical...) CI-FIRCA-157934-GO-RFQ / Acquisition du matériel 1. Institutional Pending Request for Single Stage - One 2020-12- 2021-02- 2021-08- didactique pour le centre de IBRD / 88450 strengthening and value Post Limited 60,000.00 0.00 Implement Quotations Envelope 15 09 08 formation (matériel de chain governance ation projection) CI-FIRCA-201993-GO-RFQ / Acquisition du matériel 1. Institutional Pending Request for Single Stage - One 2020-12- 2021-02- 2021-08- didactique pour le centre de IBRD / 88450 strengthening and value Post Limited 50,000.00 0.00 Implement Quotations Envelope 15 09 08 formation (matériel de chain governance ation visioconférence) CI-FIRCA-74650-GO-RFQ 1. Institutional Pending Request for Single Stage - One 2020-11- 2021-01- 2021-07- / Acquisition d'équipements IBRD / 88450 strengthening and value Post Limited 20,000.00 0.00 Implement Quotations Envelope 14 09 08 pour le contrôle qualité chain governance ation CI-FIRCA-126701-GO-RFB 1. Institutional / Acquisition et installation Single Stage - One 2020-08- 2020-08- 2020-10- 2020-11- 2020-12- 2021-06- IBRD / 88450 strengthening and value Post Request for Bids Open - National 260,000.00 0.00 Canceled des équipements du Envelope 20 25 06 05 10 08 chain governance laboratoire du CITA CI-FIRCA-106402-GO-RFB / Acquisition du matériel 1. Institutional Pending Single Stage - One 2020-11- 2020-12- 2021-01- 2021-02- 2021-03- 2021-09- pour le systeme IBRD / 88450 strengthening and value Post Request for Bids Open - National 838,000.00 0.00 Implement Envelope 30 05 16 15 22 18 d'information du CCA chain governance ation (besoins du SYSPER et autres besoins) CI-FIRCA-126699-GO-RFQ / Acquisition et installation 2. Productivity de système d'électrification enhancement and Request for Single Stage - One 2020-11- 2021-01- 2021-07- solaire (équipements + IBRD / 88450 Post Limited 70,000.00 0.00 Canceled improved access to Quotations Envelope 14 09 08 installation) markets d’opérationnalisation des 3 CDC priorisés CI-FIRCA-126698-GO-RFQ 2. Productivity / Acquisition de matériel enhancement and Request for Single Stage - One 2020-11- 2021-01- 2021-07- roulant (moto et tricycle) IBRD / 88450 Post Limited 30,000.00 0.00 Canceled improved access to Quotations Envelope 11 06 05 /site pour markets l’opérationnalisation des 3 CDC priorisés CI-FIRCA-126704-GO-RFQ 2. Productivity / Acquisition de matériels enhancement and Request for Single Stage - One 2021-02- 2021-04- 2021-09- d’arrosage des essais des 3 IBRD / 88450 Post Limited 15,000.00 0.00 Canceled improved access to Quotations Envelope 06 03 30 CDC priorisés (Koflandé, markets Badikaha, Koro Sana-koro) CI-FIRCA-106664-GO-RFQ / Acquisition de logiciels 4. Program coordination, Request for Single Stage - One 2020-05- 2020-06- 2020-12- bureautiques et de gestion IBRD / 88450 monitoring and knowledge Post Limited 10,000.00 0.00 Canceled Quotations Envelope 05 30 27 de données et des management graphiques (Office, edraw max) CI-FIRCA-157482-GO-DIR / Sélection de fournisseurs 2. Productivity de plants greffés pour la enhancement and 2020-03- 2020-04- 2020-05- 2020-11- création de nouvelles IBRD / 88450 Post Direct Selection Direct 255,000.00 0.00 Canceled improved access to 31 05 10 06 plantations (105 plants/ha markets sur une superficie de 2000 ha) à raison de 650 CFA/plant greffé CI-FIRCA-157489-GO-RFB 2. Productivity / sélection de fournisseurs enhancement and Single Stage - One 2020-11- 2020-11- 2020-12- 2021-01- 2021-02- 2021-08- pour l'acquisition IBRD / 88450 Post Request for Bids Open - National 140,000.00 0.00 Canceled improved access to Envelope 02 07 19 18 22 21 d'équipements techniques markets des 3 CDC CI-FIRCA-126684-GO-RFQ / Acquisition et installation 2. Productivity des équipements enhancement and Request for Single Stage - One 2020-10- 2020-11- 2021-05- informatiques pour IBRD / 88450 Post Limited 20,000.00 0.00 Canceled improved access to Quotations Envelope 04 29 28 l’opérationnalisation de la markets Coordination scientifique du PNRA et des 3 CDC priorisés CI-FIRCA-157569-GO-RFB / Selection d'un prestataire 3. Support to private pour l'acquisition et investment in post-harvest Single Stage - One 2020-03- 2020-03- 2020-05- 2020-05- 2020-07- 2021-01- IBRD / 88450 Post Request for Bids Open - National 149,000.00 0.00 Canceled l'installation de 100 kits and processing Envelope 15 20 01 31 05 01 pour poursuivre le infrastructure programme d'installation des unités de décorticage CI-FIRCA-106668-GO-RFQ 4. Program coordination, Request for Single Stage - One 2020-05- 2020-07- 2021-01- / Achats petits matériels et IBRD / 88450 monitoring and knowledge Post Limited 10,000.00 0.00 Canceled Quotations Envelope 23 18 14 outillages techniques management CI-FIRCA-82283-GO-RFQ 4. Program coordination, / Acquisition et installation Request for Single Stage - One 2020-10- 2020-12- 2021-06- IBRD / 88450 monitoring and knowledge Post Limited 33,000.00 0.00 Canceled de mobiliers de bureau pour Quotations Envelope 24 19 17 management l'annexe 2 du PPCA CI-FIRCA-157583-GO-RFB / Acquisition des licences 4. Program coordination, utilisateurs (systèmes Single Stage - One 2020-03- 2020-04- 2020-05- 2020-06- 2020-07- 2021-01- IBRD / 88450 monitoring and knowledge Post Request for Bids Open - National 186,000.00 0.00 Canceled d'exploitation, suite Envelope 30 04 16 15 20 16 management bureautique, EndpointSecurity, BI, 3CX)… CI-FIRCA-157598-GO-RFQ / Production et installation 4. Program coordination, Pending de panneaux et pancartes Request for Single Stage - One 2021-01- 2021-03- 2021-09- IBRD / 88450 monitoring and knowledge Post Limited 19,000.00 0.00 Implement signalétiques GRIN CITA Quotations Envelope 20 17 13 management ation etc., plaque d’identification pour bureau CI-FIRCA-157600-GO-RFQ 4. Program coordination, Pending Request for Single Stage - One 2021-01- 2021-03- 2021-09- / Acquisition de fournitures IBRD / 88450 monitoring and knowledge Post Limited 16,000.00 0.00 Implement Quotations Envelope 13 10 06 informatiques management ation CI-FIRCA-157601-GO-RFQ 4. Program coordination, Pending Request for Single Stage - One 2021-01- 2021-03- 2021-09- / Acquisition de fournitures IBRD / 88450 monitoring and knowledge Post Limited 47,000.00 0.00 Implement Quotations Envelope 13 10 06 de bureau pour l'UCP management ation CI-FIRCA-157595-GO-RFQ / Renouvellement antivirus, 4. Program coordination, Request for Single Stage - One 2020-04- 2020-05- 2020-11- cartouches d'imprimantes, IBRD / 88450 monitoring and knowledge Post Limited 9,000.00 0.00 Canceled Quotations Envelope 04 30 26 domaine ;Achat de disque management dur 3T pour le serveur (2) CI-FIRCA-157593-GO-RFQ / Renouvellement antivirus, 4. Program coordination, Pending Request for Single Stage - One 2021-01- 2021-03- 2021-09- cartouches d'imprimantes, IBRD / 88450 monitoring and knowledge Post Limited 9,000.00 0.00 Implement Quotations Envelope 16 13 09 domaine ;Achat de disque management ation dur 3T pour le serveur (2) CI-FIRCA-202091-GO-RFQ / Sélection d'une entreprise 4. Program coordination, Pending Request for Single Stage - One 2021-01- 2021-03- 2021-08- pour la production de IBRD / 88450 monitoring and knowledge Post Limited 65,000.00 0.00 Implement Quotations Envelope 04 01 28 supports de sensibilisation management ation (MGP, PGP, SCP) CI-FIRCA-202092-GO-RFQ 1. Institutional Pending Request for Single Stage - One 2020-11- 2021-01- 2021-07- / Acquisition d'un véhicule IBRD / 88450 strengthening and value Post Limited 51,000.00 0.00 Implement Quotations Envelope 15 10 09 pour l'ESA chain governance ation CI-FIRCA-158228-GO-RFQ / Acquisition du matériel de 1. Institutional Request for Single Stage - One 2020-04- 2020-06- 2020-12- stickage des IBRD / 88450 strengthening and value Post Limited 56,000.00 0.00 Canceled Quotations Envelope 18 13 10 immobilisations du Conseil chain governance du Coton et de l'Anacarde CI-FIRCA-74625-GO-RFB / Acquisition de logiciel comprenant la formation 4. Program coordination, (finance et Comptabilité, Single Stage - One 2020-05- 2020-05- 2020-06- 2020-07- 2020-08- 2021-02- IBRD / 88450 monitoring and knowledge Post Request for Bids Open - National 125,000.00 0.00 Canceled Suivi et évaluation, Envelope 05 10 21 21 25 21 management Microsoft Office, Statistique et Planification) pour l'UCP et pour le CCA CI-FIRCA-203484-GO-RFQ / Acquisition de logiciel comprenant la formation 4. Program coordination, Pending Request for Single Stage - One 2020-12- 2021-01- 2021-07- (Analyse de données, IBRD / 88450 monitoring and knowledge Post Limited 50,000.00 0.00 Implement Quotations Envelope 05 30 29 Statistique) pour l'UCP et management ation pour le CCA STATA, SPSS, POWER BI CI-FIRCA-203557-GO-RFB / Acquisition d'équipements 2. Productivity Pending techniques dans le cadre du enhancement and Single Stage - One 2020-11- 2020-12- 2021-01- 2021-02- 2021-03- 2021-09- IBRD / 88450 Post Request for Bids Open - National 140,000.00 0.00 Implement PNRA : Equipements improved access to Envelope 30 05 16 15 22 18 ation d'analyse des sols et markets mesures (2ème tranche) CI-FIRCA-203574-GO-RFB / Acquisition d'équipements 2. Productivity Pending techniques dans le cadre du enhancement and Single Stage - One 2020-11- 2020-12- 2021-01- 2021-02- 2021-03- 2021-09- IBRD / 88450 Post Request for Bids Open - National 280,000.00 0.00 Implement PNRA : équipements improved access to Envelope 30 05 16 15 22 18 ation biotechnologiques (2ème markets tranche) CI-PPCA-224879-GO-RFB 3. Support to private Pending / Acquérir et installer les investment in post-harvest Single Stage - One 2021-08- 2021-08- 2021-10- 2021-11- 2021-12- 2022-06- IBRD / 88450 Post Request for Bids Open - National 372,000.00 0.00 Implement équipements du laboratoire and processing Envelope 16 21 02 01 06 04 ation central du CITA (provision) infrastructure CI-PPCA-224881-GO-RFB / Acquisition et installation 3. Support to private Pending de kits de décorticage au investment in post-harvest Single Stage - One 2021-09- 2021-09- 2021-10- 2021-11- 2021-12- 2022-06- IBRD / 88450 Post Request for Bids Open - National 745,000.00 0.00 Implement sein des sociétés and processing Envelope 01 06 18 17 22 20 ation coopératives de la zone de infrastructure production pour la phase de mise à échelle CI-PPCA-225015-GO-RFQ 4. Program coordination, Pending Request for Single Stage - One 2021-06- 2021-08- 2022-02- / Achat de consommable IBRD / 88450 monitoring and knowledge Post Limited 28,000.00 0.00 Implement Quotations Envelope 20 15 11 informatique management ation CI-PPCA-225018-GO-RFQ / Achat de ordinateurs (portables et desktop), Scanners, et d’imprimantes 4. Program coordination, Pending Request for Single Stage - One 2021-05- 2021-07- 2022-01- et achat de licences IBRD / 88450 monitoring and knowledge Post Limited 65,000.00 0.00 Implement Quotations Envelope 15 10 06 antivirus, Licence de logiciel management ation et produit de nettoyage de PC, clé USB, disques durs externe pour le transfert des documents CI-PPCA-225022-GO-RFQ / Achat de logiciels 4. Program coordination, Pending Request for Single Stage - One 2021-05- 2021-07- 2022-01- informatiques (plateforme IBRD / 88450 monitoring and knowledge Post Limited 19,000.00 0.00 Implement Quotations Envelope 15 10 06 collaborative, traitement management ation d'images et de vidéos etc.) CI-PPCA-225030-GO-RFQ 4. Program coordination, Pending Request for Single Stage - One 2021-04- 2021-06- 2021-12- / Achat d'un photocopieur IBRD / 88450 monitoring and knowledge Post Limited 6,000.00 0.00 Implement Quotations Envelope 25 20 17 pour l'UCP management ation CI-PPCA-225035-GO-RFQ / Acquérir et fournir à des centres de santé locales des 4. Program coordination, Pending Request for Single Stage - One 2021-05- 2021-07- 2022-01- équipements et produits IBRD / 88450 monitoring and knowledge Post Limited 37,000.00 0.00 Implement Quotations Envelope 25 20 16 médicaux de prise en management ation charge médicale des personnes intoxiquées aux pesticides CI-PPCA-225046-GO-RFQ / Acquérir des Equipements 4. Program coordination, Pending Request for Single Stage - One 2021-05- 2021-07- 2022-01- de Protection Individuelle IBRD / 88450 monitoring and knowledge Post Limited 94,000.00 0.00 Implement Quotations Envelope 12 07 03 (EPI) et extincteurs pour le management ation personnel de l'UC PPCA Page 4 CI-PPCA-225054-GO-RFQ / Acquérir des matériels techniques pour la gestion 4. Program coordination, Pending Request for Single Stage - One 2021-07- 2021-09- 2022-03- des mesures de sauvegarde IBRD / 88450 monitoring and knowledge Post Limited 8,000.00 0.00 Implement Quotations Envelope 10 04 03 environnementale (appareils management ation GPS, appareils photo et sonomètres) CI-PPCA-225078-GO-RFQ / Acquérir des gadgets et 4. Program coordination, Pending Request for Single Stage - One 2021-06- 2021-08- 2022-02- supports de communication IBRD / 88450 monitoring and knowledge Post Limited 37,000.00 0.00 Implement Quotations Envelope 27 22 18 (plaquette, gilet multipoche, management ation chasuble, t-shirt, polo, etc.) CI-PPCA-225080-GO-RFQ / Acquérir des équipements 4. Program coordination, Pending Request for Single Stage - One 2021-05- 2021-07- 2022-01- pour le renforcement de la IBRD / 88450 monitoring and knowledge Post Limited 10,000.00 0.00 Implement Quotations Envelope 10 05 01 couverture réseau wifi des management ation locaux du PPCA CI-PPCA-225567-GO-RFQ / Acquérir le mobilier de 1. Institutional Pending bureau pour l'Annexe du Request for Single Stage - One 2021-06- 2021-08- 2022-02- IBRD / 88450 strengthening and value Post Limited 67,000.00 0.00 Implement CCA au 2 Plateaux Vallon et Quotations Envelope 22 17 13 chain governance ation pour les 4 DR CCA de Bondoukou, Bouaké, Korhogo et Séguéla CI-PPCA-225570-GO-RFQ 1. Institutional Pending Request for Single Stage - One 2021-07- 2021-09- 2022-03- / Acquérir l'outillage IBRD / 88450 strengthening and value Post Limited 37,000.00 0.00 Implement Quotations Envelope 17 11 10 complémentaire du CITA (.) chain governance ation CI-PPCA-225576-GO-RFQ 1. Institutional Pending / Acquérir d’équipements Request for Single Stage - One 2021-05- 2021-07- 2022-01- IBRD / 88450 strengthening and value Post Limited 93,000.00 0.00 Implement audiovisuel (camera, Quotations Envelope 10 05 01 chain governance ation audiovisuel) 1. Institutional Pending CI-PPCA-225581-GO-RFQ Request for Single Stage - One 2021-06- 2021-07- 2022-01- IBRD / 88450 strengthening and value Post Limited 3,000.00 0.00 Implement / Acquérir un sonomètre Quotations Envelope 05 31 27 chain governance ation CI-PPCA-225586-GO-RFB 2. Productivity / Acquérir la deuxième Pending enhancement and Single Stage - One 2021-06- 2021-06- 2021-08- 2021-09- 2021-10- 2022-04- tranche des équipements IBRD / 88450 Post Request for Bids Open - National 559,000.00 0.00 Implement improved access to Envelope 25 30 11 10 15 13 techniques et scientifiques ation markets des INRA du PNRA CI-PPCA-225590-GO-RFQ 2. Productivity Pending Request for Single Stage - One 2021-07- 2021-09- 2022-03- / Acquérir le matériel IBRD / 88450 enhancement and Post Limited 95,000.00 0.00 Implement Quotations Envelope 31 25 24 technique des INRA du improved access to ation PNRA markets CI-PPCA-225594-GO-RFB 2. Productivity Pending Single Stage - One 2021-07- 2021-07- 2021-09- 2021-10- 2021-11- 2022-05- / Acquérir les équipements IBRD / 88450 enhancement and Post Request for Bids Open - National 140,000.00 0.00 Implement Envelope 21 26 06 06 10 09 techniques de 3 CDC improved access to ation markets CI-PPCA-225595-GO-RFB 2. Productivity Pending / Acquérir des équipements enhancement and Single Stage - One 2021-06- 2021-07- 2021-08- 2021-09- 2021-10- 2022-04- IBRD / 88450 Post Request for Bids Open - National 250,000.00 0.00 Implement techniques pour 100 kits improved access to Envelope 30 05 16 15 20 18 ation d'OPCA markets CI-PPCA-225597-GO-RFQ 2. Productivity Pending / Acquérir des équipements enhancement and Request for Single Stage - One 2021-09- 2021-10- 2022-04- IBRD / 88450 Post Limited 60,000.00 0.00 Implement informatiques de la improved access to Quotations Envelope 04 30 28 ation SODEXAM et du CIRES markets CI-PPCA-225602-GO-RFB / Acquérir des produits 2. Productivity (insecticides, fongicides, Pending enhancement and Single Stage - One 2021-06- 2021-06- 2021-08- 2021-08- 2021-10- 2022-04- engrais foliaires organiques) IBRD / 88450 Post Request for Bids Open - National 1,511,000.00 0.00 Implement improved access to Envelope 15 20 01 31 05 03 pour la protection, ation markets fertilisation des vergers réhabilités CI-PPCA-225604-GO-RFQ 2. Productivity / Acquérir des semences Pending enhancement and Request for Single Stage - One 2021-06- 2021-07- 2022-01- pour les cultures IBRD / 88450 Post Limited 47,000.00 0.00 Implement improved access to Quotations Envelope 03 29 25 intercalaires (autres que le ation markets soja) dans les parcelles de producteurs CI-PPCA-225610-GO-RFB 2. Productivity / Acquérir un lysimètre Pending enhancement and Single Stage - One 2021-07- 2021-07- 2021-09- 2021-10- 2021-11- 2022-05- pour la sélection des IBRD / 88450 Post Request for Bids Open - National 112,000.00 0.00 Implement improved access to Envelope 21 26 06 06 10 09 anacardiers tolérants au ation markets déficit hydrique pour le CNRA CI-FIRCA-234283-GO-RFQ / Acquisition et installation 1. Institutional Pending de l'unité de pyrolyse pour Request for Single Stage - One 2021-07- 2021-08- 2022-02- IBRD / 88450 strengthening and value Post Limited 55,866.00 0.00 Implement la valorisation des coques Quotations Envelope 05 30 26 chain governance ation en charbon au profit des ménages (sur le site du CITA) NON CONSULTING SERVICES Activity Reference No. Estimated Actual Draft Pre- Draft Bidding Specific Proposal Bid Evaluation Loan / Credit Market Procurement Prequalificatio Process Prequalification Bidding Documents Contract / Description Component Review Type Method Amount Amount qualification Document / Procurement Notice Submission / Report and Signed Contract No. Approach Process n (Y/N) Status Evaluation Report as Issued Completion (US$) (US$) Documents Justification / Invitation Opening / Minutes Recommendation Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned for Award Actual Planned Actual Planned Actual CI-FIRCA-68053-NC-RFQ / 4. Program coordination, Request for Single Stage - One 2018-10- 2018-11- 2019-05- Fourniture de carburant IBRD / 88450 monitoring and knowledge Post Limited 13,000.00 0.00 Canceled Quotations Envelope 05 30 29 pour les activités management CI-FIRCA-76398-NC-DIR / 3. Support to private Location d'un Bâtiment à investment in post-harvest 2018-11- 2018-11- 2018-12- 2019-01- 2019-06- 2019-04- IBRD / 88450 Post Direct Selection Direct 50,000.00 47,066.00 Completed usage de local technique and processing 09 14 19 17 17 30 pour l'ARRE infrastructure CI-FIRCA-76423-NC-RFQ / 4. Program coordination, Request for Single Stage - One 2018-10- 2019-06- 2018-12- 2019-08- 2019-06- Entretien des climatiseurs et IBRD / 88450 monitoring and knowledge Post Limited 40,000.00 1,257.24 Signed Quotations Envelope 10 28 05 19 03 Splits de l'UCP management CI-FIRCA-76712-NC-RFQ / 4. Program coordination, Recrutement d'un Request for Single Stage - One 2018-11- 2019-11- 2018-12- 2019-12- 2019-06- IBRD / 88450 monitoring and knowledge Post Limited 15,000.00 51,451.00 Signed prestataire pour la Quotations Envelope 04 06 30 23 28 management maintenance informatique de l'UCP CI-FIRCA-76713-NC-RFQ / Assurance Maladie 4. Program coordination, Request for Single Stage - One 2018-10- 2018-12- 2018-12- 2019-05- 2019-06- 2019-07- Individuel Accident des IBRD / 88450 monitoring and knowledge Post Limited 99,000.00 45,369.30 Completed Quotations Envelope 09 18 04 11 02 04 agents de l'UCP , accident management multirisques professionnels CI-FIRCA-68047-NC-DIR / 4. Program coordination, 2018-07- 2018-08- 2018-09- 2018-10- 2019-03- Contrat de location des IBRD / 88450 monitoring and knowledge Post Direct Selection Direct 53,000.00 51,158.70 Signed 31 05 09 12 08 locaux de l'UGP pour 7 management mois CI-FIRCA-82348-NC-RFQ / 1. Institutional Request for Single Stage - One 2018-10- 2018-10- 2018-12- 2018-11- 2019-06- 2018-11- Aménagement d'espaces IBRD / 88450 strengthening and value Post Limited 99,000.00 15,185.61 Completed Quotations Envelope 23 19 18 02 16 06 d'exposition pour le SIETTA chain governance CI-FIRCA-82350-NC-RFQ / 1. Institutional Fourniture et installation Request for Single Stage - One 2018-10- 2018-10- 2018-12- 2018-11- 2019-06- 2018-11- IBRD / 88450 strengthening and value Post Limited 99,000.00 85,974.74 Completed d'un système audio vidéo au Quotations Envelope 27 19 22 06 20 06 chain governance SIETTA CI-FIRCA-82349-NC-DIR / 1. Institutional Location d'espace couvert 2018-10- 2018-10- 2018-10- 2018-12- 2018-11- 2019-05- 2018-11- IBRD / 88450 strengthening and value Post Direct Selection Direct 36,000.00 30,695.22 Completed au palais de la culture pour 22 27 19 01 06 30 10 chain governance le SIETTA CI-FIRCA-82352-NC-DIR / Contrat de maintenance avec DATASOFT pour la 1. Institutional Pending maintenance du Système 2018-12- 2018-12- 2019-01- 2019-07- IBRD / 88450 strengthening and value Post Direct Selection Direct 12,000.00 0.00 Implement électronique de gestion 17 22 26 25 chain governance ation intégrée des règlements des dépenses relatives à la mise en œuvre du projet CI-FIRCA-106704-NC-RFQ / Doter la DOPA d'un Wifi performant et d'un réseau informatique filaire dans les 1. Institutional bureaux de la DOPA en vue Request for Single Stage - One 2019-04- 2019-12- 2019-06- 2020-02- 2019-11- 2020-10- IBRD / 88450 strengthening and value Post Limited 13,000.00 15,548.41 Completed d'assurer une fluidité de Quotations Envelope 06 03 01 18 28 27 chain governance communication avec les différents acteurs et d'une connexion internet par fibre optique CI-FIRCA-106722-NC-RFQ / Sélection d'un prestataire 1. Institutional Pending Request for Single Stage - One 2019-04- 2019-06- 2019-11- pour la Maintenance et IBRD / 88450 strengthening and value Post Limited 19,000.00 0.00 Implement Quotations Envelope 06 01 28 l'assistance annuelles du chain governance ation matériel dédié au LOGISCOOP CI-FIRCA-106728-NC-RFQ 4. Program coordination, / Sélection d'une structure Request for Single Stage - One 2019-03- 2019-04- 2019-05- 2019-06- 2019-11- IBRD / 88450 monitoring and knowledge Post Limited 50,000.00 21,302.07 Signed de Gardiennage des Quotations Envelope 23 16 18 18 14 management bureaux de l'UCP PPCA CI-FIRCA-106737-NC-RFQ 4. Program coordination, Request for Single Stage - One 2019-03- 2019-04- 2019-05- 2019-04- 2019-11- / Sélection d'un prestataire IBRD / 88450 monitoring and knowledge Post Limited 37,000.00 22,021.96 Signed Quotations Envelope 23 04 18 30 14 pour le Nettoyage de l'UCP management CI-FIRCA-106927-NC-RFQ 4. Program coordination, / Abonnement et mise en Request for Single Stage - One 2019-03- 2019-06- 2019-05- 2019-07- 2019-11- IBRD / 88450 monitoring and knowledge Post Limited 37,000.00 6,239.53 Signed place d'une ligne de Quotations Envelope 24 14 19 30 15 management connexion internet haut débit UCP CI-FIRCA-68051-NC-RFQ / 4. Program coordination, Request for Single Stage - One 2018-10- 2018-12- 2019-06- Assurance des 5 véhicules IBRD / 88450 monitoring and knowledge Post Limited 34,000.00 0.00 Canceled Quotations Envelope 09 04 02 et des 20 motos management CI-FIRCA-76394-NC-RFQ / 4. Program coordination, recrutement d'une Request for Single Stage - One 2018-10- 2018-12- 2019-05- IBRD / 88450 monitoring and knowledge Post Limited 80,000.00 0.00 Canceled assurance pour l'assurance Quotations Envelope 06 01 30 management des véhicules du projet CI-FIRCA-106724-NC-RFQ 4. Program coordination, Pending / Entente directe avec 2020-05- 2020-05- 2020-06- 2020-12- IBRD / 88450 monitoring and knowledge Post Direct Selection Direct 9,000.00 0.00 Implement GEDEX pour le transport de 08 13 17 14 management ation plis au niveau national CI-FIRCA-157512-NC-DIR 2. Productivity Pending 2020-04- 2020-05- 2020-06- 2020-12- / Entretien et surveillance IBRD / 88450 enhancement and Post Direct Selection Direct 65,000.00 0.00 Implement 30 05 09 06 des sites du PAVA improved access to ation markets CI-FIRCA-82351-NC-DIR / Transport et dédouanement 1. Institutional des équipements pour 2018-11- 2018-11- 2018-12- 2019-06- IBRD / 88450 strengthening and value Post Direct Selection Direct 100,000.00 0.00 Canceled l'exposition en vue de la 08 13 18 16 chain governance vulgarisation des technologies lors du SIETTA CI-FIRCA-157723-NC-RFQ 1. Institutional Pending Request for Single Stage - One 2020-03- 2020-05- 2020-11- / Location d'un Datacenter IBRD / 88450 strengthening and value Post Limited 55,000.00 0.00 Implement Quotations Envelope 11 06 02 pour l'ARRE chain governance ation CI-FIRCA-108083-NC-DIR 4. Program coordination, Pending / Entente directe avec 2020-05- 2020-05- 2020-06- 2020-12- IBRD / 88450 monitoring and knowledge Post Direct Selection Direct 18,000.00 0.00 Implement AFRICAUTO pour l'entretien 11 16 20 17 management ation et les réparations des véhicules CI-FIRCA-106734-NC-DIR / Entente directe avec le 4. Program coordination, Pending 2020-05- 2020-05- 2020-06- 2020-12- concessionnaire CFAO pour IBRD / 88450 monitoring and knowledge Post Direct Selection Direct 19,000.00 0.00 Implement 12 17 21 18 l'entretien et les réparations management ation de véhicules CI-FIRCA-158888-NC-RFQ 4. Program coordination, Pending / Sélection d'un prestataire Request for Single Stage - One 2020-03- 2020-04- 2020-10- IBRD / 88450 monitoring and knowledge Post Limited 19,000.00 0.00 Implement pour la Maintenance Quotations Envelope 04 29 26 management ation préventive des équipements CI-FIRCA-158231-NC-DIR 4. Program coordination, Pending 2020-09- 2020-09- 2020-10- 2021-04- / Renouvellement du IBRD / 88450 monitoring and knowledge Post Direct Selection Direct 67,000.00 0.00 Implement 15 20 25 23 Contrat de bail du management ation PPCA(renouvellement) CI-FIRCA-158233-NC-DIR 4. Program coordination, 2020-05- 2020-04- 2020-05- 2019-04- 2020-06- 2020-04- 2020-12- / Sélection d'un prestataire IBRD / 88450 monitoring and knowledge Post Direct Selection Direct 22,000.00 24,479.00 Signed 15 30 20 04 24 30 21 pour l'entretien des locaux management du PPCA CI-FIRCA-158234-NC-DIR / Sélection d'un prestataire 4. Program coordination, 2020-05- 2020-06- 2020-05- 2020-06- 2020-06- 2020-06- 2020-12- pour le gardiennage des IBRD / 88450 monitoring and knowledge Post Direct Selection Direct 28,000.00 23,335.20 Signed 15 18 20 18 24 18 21 bureaux du PPCA management (renouvellement) CI-FIRCA-82347-NC-DIR / Location d'un Datacenter 3. Support to private auprès d'un Opérateur Local investment in post-harvest Request for Single Stage - One 2018-12- 2019-01- 2019-07- IBRD / 88450 Post Limited 80,000.00 0.00 Canceled pour l'hébergement de la and processing Quotations Envelope 05 30 29 Plateforme électronique infrastructure pour l'ARRE CI-FIRCA-76403-NC-RFQ / 4. Program coordination, Request for Single Stage - One 2018-11- 2018-12- 2019-06- Entretien des bureaux de IBRD / 88450 monitoring and knowledge Post Limited 30,000.00 0.00 Canceled Quotations Envelope 05 31 29 l'UCP management CI-FIRCA-76716-NC-RFQ / 4. Program coordination, Gardiennage des locaux de Request for Single Stage - One 2018-11- 2018-12- 2019-06- IBRD / 88450 monitoring and knowledge Post Limited 50,000.00 0.00 Canceled l'UCP et la Géolocalisation Quotations Envelope 04 30 28 management des véhicules CI-FIRCA-106923-NC-DIR 4. Program coordination, / Entente directe avec DHL 2019-03- 2019-03- 2019-04- 2019-10- IBRD / 88450 monitoring and knowledge Post Direct Selection Direct 10,000.00 0.00 Canceled pour le transport de plis au 19 24 28 25 management niveau international CI-FIRCA-159698-NC-DIR 1. Institutional Pending / Entente Directe avec 3D 2020-03- 2020-03- 2020-04- 2020-10- IBRD / 88450 strengthening and value Post Direct Selection Direct 12,000.00 0.00 Implement Solution pour la 02 07 11 08 chain governance ation maintenance du LOGISCOOP CI-FIRCA-160033-NC-DIR / Sélection d'OPCA pour la 2. Productivity Pending réalisation des travaux de enhancement and 2020-03- 2020-03- 2020-04- 2020-10- IBRD / 88450 Post Direct Selection Direct 1,847,000.00 0.00 Implement réhabilitation des vergers improved access to 16 21 25 22 ation d'anacardiers de la DR markets NORD ANADER CI-FIRCA-160035-NC-DIR / Sélection d'OPCA pour la 2. Productivity Pending réalisation des travaux de enhancement and 2020-03- 2020-03- 2020-04- 2020-10- IBRD / 88450 Post Direct Selection Direct 375,000.00 0.00 Implement réhabilitation des vergers improved access to 15 20 24 21 ation d'anacardiers de la DR markets OUEST ANADER CI-FIRCA-160037-NC-DIR / Sélection d'OPCA pour la 2. Productivity Pending réalisation des travaux de enhancement and 2020-03- 2020-03- 2020-04- 2020-10- IBRD / 88450 Post Direct Selection Direct 744,000.00 0.00 Implement réhabilitation des vergers improved access to 15 20 24 21 ation d'anacardiers de la DR markets Centre-Ouest ANADER CI-FIRCA-160038-NC-DIR / Sélection d'OPCA pour la 2. Productivity Pending réalisation des travaux de enhancement and 2020-03- 2020-03- 2020-04- 2020-10- IBRD / 88450 Post Direct Selection Direct 1,358,000.00 0.00 Implement réhabilitation des vergers improved access to 16 21 25 22 ation d'anacardiers de la DR markets CENTRE ANADER CI-FIRCA-160041-NC-DIR / Sélection d'OPCA pour la 2. Productivity Pending réalisation des travaux de enhancement and 2020-03- 2020-03- 2020-04- 2020-10- IBRD / 88450 Post Direct Selection Direct 981,000.00 0.00 Implement réhabilitation des vergers improved access to 16 21 25 22 ation d'anacardiers de la DR markets Centre-Est ANADER CI-FIRCA-180151-NC-RFQ 2. Productivity / EDITION DES FICHES DE enhancement and Request for Single Stage - One 2020-06- 2020-06- 2020-08- 2020-06- 2021-02- 2020-07- IBRD / 88450 Post Limited 30,000.00 27,823.10 Completed VALIDATION DES PARCELLES improved access to Quotations Envelope 24 09 19 19 15 08 RÉHABILITÉES markets Page 5 CI-FIRCA-191632-NC-RFB / Recrutement des 2. Productivity Pending prestataires pour la enhancement and Single Stage - One 2020-11- 2020-11- 2021-01- 2021-02- 2021-03- 2021-09- IBRD / 88450 Post Request for Bids Open - National 186,000.00 0.00 Implement réalisation des opérations improved access to Envelope 19 24 05 04 11 07 ation de reboisement markets compensatoire de 150 ha en 2021 CI-FIRCA-106702-NC-RFQ 1. Institutional Pending / Mise en place d'une ligne Request for Single Stage - One 2021-01- 2021-03- 2021-09- IBRD / 88450 strengthening and value Post Limited 37,000.00 0.00 Implement de connexion internet haut Quotations Envelope 16 13 09 chain governance ation débit au CCA/CITA CI-FIRCA-106932-NC-DIR / Sélection d'un prestataire 4. Program coordination, pour procéder à la collecte, 2020-07- 2020-07- 2020-08- 2021-02- IBRD / 88450 monitoring and knowledge Post Direct Selection Direct 4,000.00 0.00 Canceled au stockage et à 01 06 10 06 management l'élimination finale des produits chimiques périmés CI-FIRCA-202083-NC-RFQ 1. Institutional / Assurance des matériels Request for Single Stage - One 2020-12- 2020-09- 2021-02- 2020-11- 2021-08- 2020-11- IBRD / 88450 strengthening and value Post Limited 25,000.00 146,720.36 Signed roulant du CITA (Autobus, Quotations Envelope 20 18 14 08 13 17 chain governance Véhicules etc) CI-FIRCA-157576-NC-DIR 2. Productivity / Apporter un appui à la enhancement and 2020-03- 2020-03- 2020-04- 2020-10- mise en place des sites des IBRD / 88450 Post Direct Selection Direct 38,000.00 0.00 Canceled improved access to 16 21 25 22 essais et des tests de markets surgreffage en milieu paysan CI-FIRCA-157585-NC-RFB / Recrutement d'une agence 4. Program coordination, de communication pour la Single Stage - One 2020-03- 2020-03- 2020-05- 2020-05- 2020-07- 2021-01- IBRD / 88450 monitoring and knowledge Post Request for Bids Open - National 131,000.00 0.00 Canceled mise en œuvre de la Envelope 15 20 01 31 05 01 management communication institutionnelle du PPCA CI-FIRCA-157596-NC-RFQ / Sélection d'un agence de 4. Program coordination, Request for Single Stage - One 2020-03- 2020-05- 2020-11- communication pour la IBRD / 88450 monitoring and knowledge Post Limited 65,000.00 0.00 Canceled Quotations Envelope 28 23 19 conception et production de management supports de sensibilisation CI-FIRCA-203491-NC-RFQ / Sélection d'un prestataire en communication 4. Program coordination, Pending évènemetielle pour Request for Single Stage - One 2020-12- 2021-01- 2021-07- IBRD / 88450 monitoring and knowledge Post Limited 80,000.00 0.00 Implement l'organisation des Quotations Envelope 06 31 30 management ation cérémonies de lancement et d'inauguration d'infrastructures et autres manifestations CI-FIRCA-203493-NC-RFQ 4. Program coordination, Pending / Installation d’Internet par Request for Single Stage - One 2020-12- 2021-01- 2021-07- IBRD / 88450 monitoring and knowledge Post Limited 65,000.00 0.00 Implement BLR (Boucle Locale Radio) au Quotations Envelope 05 30 29 management ation CITA avec 1 an d’abonnement CI-FIRCA-203502-NC-RFQ 4. Program coordination, Pending / Installation d’Internet par Request for Single Stage - One 2020-12- 2021-01- 2021-07- IBRD / 88450 monitoring and knowledge Post Limited 10,000.00 0.00 Implement Fibre optioque (FO° à Quotations Envelope 05 30 29 management ation l’annexe 1 du CCA Vallon CI-FIRCA-76397-NC-DIR / 4. Program coordination, Pending 2021-01- 2021-01- 2021-03- 2021-08- Entretien et réparation des IBRD / 88450 monitoring and knowledge Post Direct Selection Direct 60,000.00 0.00 Implement 20 25 01 28 véhicules management ation CI-PPCA-225097-NC-RFQ 4. Program coordination, Pending / Recruter un prestataire Request for Single Stage - One 2021-06- 2021-07- 2022-01- IBRD / 88450 monitoring and knowledge Post Limited 28,000.00 0.00 Implement pour la maintenance Quotations Envelope 05 31 27 management ation préventive des équipements PPCA CI-PPCA-225100-NC-RFQ 4. Program coordination, Pending Request for Single Stage - One 2021-05- 2021-06- 2021-12- / Recruter un prestataire IBRD / 88450 monitoring and knowledge Post Limited 9,000.00 0.00 Implement Quotations Envelope 05 30 27 transport de plis management ation CI-PPCA-225101-NC-RFQ 4. Program coordination, Pending Request for Single Stage - One 2021-08- 2021-09- 2022-03- / Recruter un prestataire IBRD / 88450 monitoring and knowledge Post Limited 28,000.00 0.00 Implement Quotations Envelope 04 29 28 Gardiennage bureau management ation CI-PPCA-225102-NC-RFQ / Recruter un prestataire 4. Program coordination, Pending Request for Single Stage - One 2021-05- 2021-06- 2021-12- pour l’entretien des IBRD / 88450 monitoring and knowledge Post Limited 14,000.00 0.00 Implement Quotations Envelope 05 30 27 installations électriques, management ation climatiseurs, sanitaires et plomberies CI-PPCA-225103-NC-RFQ 4. Program coordination, Pending / Recruter un prestataire Request for Single Stage - One 2021-05- 2021-06- 2021-12- IBRD / 88450 monitoring and knowledge Post Limited 37,000.00 0.00 Implement pour autres entretiens et Quotations Envelope 04 29 26 management ation réparations (Nettoyage ) CI-PPCA-225104-NC-RFQ / Recruter un prestataire 4. Program coordination, Pending Request for Single Stage - One 2021-05- 2021-07- 2021-12- pour l’assurance maladie et IBRD / 88450 monitoring and knowledge Post Limited 75,000.00 0.00 Implement Quotations Envelope 08 03 30 Individuel accident (maladie management ation et accident) CI-PPCA-225106-NC-RFQ 4. Program coordination, Pending / l’assurance multirisque Request for Single Stage - One 2021-05- 2021-07- 2021-12- IBRD / 88450 monitoring and knowledge Post Limited 3,000.00 0.00 Implement professionnelle (Assurance Quotations Envelope 08 03 30 management ation du bâtiment) CI-PPCA-225108-NC-RFQ 4. Program coordination, Pending / Recruter un prestataire en Request for Single Stage - One 2021-05- 2021-07- 2021-12- IBRD / 88450 monitoring and knowledge Post Limited 7,000.00 0.00 Implement vue de la production du Quotations Envelope 09 04 31 management ation premier numéro du magazine du PPCA CI-PPCA-225110-NC-RFQ / Recruter un prestataire en 4. Program coordination, Pending Request for Single Stage - One 2021-05- 2021-07- 2022-01- vue de la réalisation d'un IBRD / 88450 monitoring and knowledge Post Limited 28,000.00 0.00 Implement Quotations Envelope 25 20 16 film documentaire sur les management ation résultats du projet CI-PPCA-225111-NC-RFQ / Recruter un prestataire en 4. Program coordination, Pending Request for Single Stage - One 2021-05- 2021-07- 2022-01- vue de l’édition de carte des IBRD / 88450 monitoring and knowledge Post Limited 19,000.00 0.00 Implement Quotations Envelope 25 20 16 interventions du projet management ation format A0 CI-PPCA-225112-NC-RFQ / Recruter un prestataire en 4. Program coordination, Pending vue de la production et de Request for Single Stage - One 2021-05- 2021-07- 2022-01- IBRD / 88450 monitoring and knowledge Post Limited 19,000.00 0.00 Implement l’installation de panneaux et Quotations Envelope 25 20 16 management ation pancartes signalétiques GRIN et autres réalisations etc., CI-PPCA-225114-NC-RFQ 4. Program coordination, Pending / Recruter un prestataire en Request for Single Stage - One 2021-05- 2021-07- 2022-01- IBRD / 88450 monitoring and knowledge Post Limited 9,310.00 0.00 Implement vue de la réalisation d'un Quotations Envelope 25 20 16 management ation branding des locaux du PPCA CI-PPCA-225120-NC-RFQ / Recruter un prestataire en 4. Program coordination, Pending vue de la production de Request for Single Stage - One 2021-05- 2021-07- 2022-01- IBRD / 88450 monitoring and knowledge Post Limited 79,490.00 0.00 Implement supports de sensibilisation Quotations Envelope 25 20 16 management ation (IEC) Affiche illustrés (SCP, MGP ; GBF, GBH, VBG, PGP...) CI-PPCA-225613-NC-RFQ 2. Productivity / Sélection d’un prestataire Pending enhancement and Request for Single Stage - One 2021-07- 2021-08- 2022-02- pour assurer la maintenance IBRD / 88450 Post Limited 19,000.00 0.00 Implement improved access to Quotations Envelope 05 30 26 préventive des équipements ation markets de la DOPA CI-PPCA-225617-NC-RFB / Acquérir les plants 2. Productivity Pending forestiers et réaliser le enhancement and Single Stage - One 2021-06- 2021-07- 2021-08- 2021-09- 2021-10- 2022-04- IBRD / 88450 Post Request for Bids Open - National 225,000.00 0.00 Implement reboisement de 200 ha improved access to Envelope 30 05 16 15 20 18 ation dans le cadre du markets programme de reboisement compensatoire CI-PPCA-225627-NC-RFQ / Location de camion 4. Program coordination, Pending Request for Single Stage - One 2021-06- 2021-08- 2022-02- podium pour la promotion IBRD / 88450 monitoring and knowledge Post Limited 67,000.00 0.00 Implement Quotations Envelope 28 23 19 itinérante de la management ation consommation locale du cajou CONSULTING FIRMS Activity Reference No. Actual Short List and Draft Opening of Combined Loan / Credit Market Contract Type Estimated Process Expression of Request for Evaluation of Contract / Description Component Review Type Method Amount Terms of Reference Request for Technical Proposals Evaluation Report Signed Contract No. Approach Amount (US$) Status Interest Notice Proposals as Issued Technical Proposal Completion (US$) Proposals / Minutes and Draft Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Negotiated Contract Actual Planned Actual Planned Actual CI-FIRCA-70966-CS-QBS / Recrutement d'un consultant individuel pour 3. Support to private le constat d'impact investment in post-harvest Quality Based Open - 2018-05- 2018-02- 2018-05- 2018-07- 2018-07- 2018-06- 2018-08- 2018-06- 2018-09- 2018-06- 2018-11- 2018-08- 2019-11- IBRD / 88450 Post 100,000.00 63,970.24 Signed environnemental et social ( and processing Selection International 03 01 24 07 30 06 29 26 28 20 02 13 02 CIES) de travaux de 184 km infrastructure de routes rurales dans les régions du GBEKE, HAMBOL et GONTOUGOU CI-FIRCA-71186-CS-QBS / Recrutement d'un 2. Productivity consultant pour enhancement and Quality Based 2015-04- 2018-04- 2015-05- 2015-06- 2018-06- 2015-07- 2018-07- 2015-08- 2018-07- 2015-09- 2018-07- 2015-10- 2018-08- 2016-10- 2018-12- IBRD / 88450 Post Open - National 50,000.00 57,817.90 Completed l'actualisation de la improved access to Selection 16 02 07 20 13 18 04 17 04 16 18 21 17 20 24 structure des prix de la markets commercialisation de la noix brute de cajou en Côte d'Ivoire CI-FIRCA-70226-CS-QBS / Recrutement d'un 3. Support to private consultant pour l'Étude de investment in post-harvest Quality Based Open - 2017-06- 2018-03- 2018-03- 2018-04- 2018-03- 2018-05- 2018-04- 2018-05- 2018-04- 2018-05- 2018-07- 2018-08- 2019-07- IBRD / 88450 Post 250,000.00 243,625.86 Signed l'évaluation and processing Selection International 29 07 07 17 19 31 12 31 17 31 04 13 04 Environnementale et infrastructure Stratégique de la Zone Industrielle de SEGUELA CI-FIRCA-74797-CS-QCBS / Recrutement de cabinets 4. Program coordination, pour les audits annuels Quality And Cost- Open - 2018-10- 2018-11- 2018-12- 2019-01- 2019-02- 2019-03- 2019-04- 2020-04- IBRD / 88450 monitoring and knowledge Post 240,000.00 0.00 Canceled (financiers de l'agence Based Selection International 11 01 15 12 11 18 22 21 management fiduciaire et des agences d'exécution (sur les 3 premières années) du projet CI-FIRCA-74808-CS-CQS / Recrutement de Cabinet 3. Support to private pour l'assistance technique Consultant investment in post-harvest Open - Pending 2019-01- 2019-01- 2019-03- 2019-04- 2019-05- 2019-11- pour la conception et le IBRD / 88450 Post Qualification 50,000.00 0.00 and processing International Implementation 04 25 10 09 14 10 développement de plans Selection infrastructure d'affaires au profit des gestionnaires d'entrepôts CI-FIRCA-74843-CS-CQS / Recrutement de cabinets 3. Support to private Consultant pour la réalisation d'une investment in post-harvest Open - Pending 2018-11- 2018-12- 2019-01- 2019-02- 2019-03- 2019-09- IBRD / 88450 Post Qualification 180,000.00 0.00 étude de faisabilité and processing International Implementation 12 03 16 15 22 18 Selection technique et financière des infrastructure plateformes de service CI-FIRCA-70381-CS-QBS / Recrutement d'un 3. Support to private consultant pour les Études investment in post-harvest Quality Based Open - Pending 2017-06- 2018-03- 2018-05- 2018-06- 2018-06- 2018-06- 2018-07- 2019-07- IBRD / 88450 Post 250,000.00 0.00 d'Évaluation and processing Selection International Implementation 29 31 31 26 26 26 17 17 Environnementales et infrastructure Sociales Stratégiques (EEES) de la zone industrielle de . CI-FIRCA-70952-CS-QCBS / Recrutement d"un 3. Support to private consultant pour l'évaluation investment in post-harvest Quality And Cost- Open - 2017-06- 2018-04- 2018-05- 2018-06- 2018-07- 2018-07- 2018-07- 2018-08- 2019-08- IBRD / 88450 Post 250,000.00 0.00 Canceled environnementale et sociale and processing Based Selection International 29 02 17 07 13 19 23 23 23 stratégique ( EEES) de la infrastructure zone agro industrielle de BOUAKE CI-FIRCA-77817-CS-QBS / Recrutement d'un 3. Support to private consultant pour la investment in post-harvest Quality Based Open - 2017-06- 2018-05- 2018-06- 2018-03- 2018-07- 2018-04- 2018-08- 2018-09- 2018-06- 2018-10- 2018-08- 2019-10- 2019-04- IBRD / 88450 Post 250,000.00 267,037.19 Completed réalisation des études and processing Selection International 29 17 21 26 19 12 18 17 12 22 13 22 02 environnementale et sociale infrastructure stratégique (EESS) de la zone agro industrielle de KORHOGO CI-FIRCA-78373-CS-QBS / Recrutement d'un cabinet 4. Program coordination, Quality Based 2018-10- 2019-09- 2018-10- 2019-12- 2018-12- 2020-03- 2019-01- 2020-05- 2019-02- 2020-05- 2019-03- 2020-06- 2019-04- 2020-07- 2020-04- pour le diagnostique et IBRD / 88450 monitoring and knowledge Post Open - National 30,000.00 86,707.62 Signed Selection 05 30 26 31 09 04 06 05 05 05 07 09 11 08 10 proposition de plan management stratégique du Système Informatique du CCA CI-FIRCA-82252-CS-INDV 4. Program coordination, Quality And Cost- Open - 2018-10- 2018-11- 2019-01- 2019-01- 2019-03- 2019-04- 2019-05- 2020-05- / Recrutement d'un cabinet IBRD / 88450 monitoring and knowledge Post 100.00 0.00 Canceled Based Selection International 30 20 03 31 02 06 11 10 pour l'étude de référence du management projet CI-FIRCA-82277-CS-QCBS / Recrutement de cabinets 4. Program coordination, pour les audits Quality And Cost- Open - 2018-10- 2019-01- 2018-11- 2018-12- 2019-02- 2019-01- 2019-02- 2019-02- 2019-02- 2019-04- 2019-03- 2019-05- 2015-05- 2020-05- IBRD / 88450 monitoring and knowledge Post 240,000.00 62,110.45 Signed annuels(financiers de Based Selection International 26 10 16 30 15 27 18 26 26 02 21 07 15 06 management l'agence fiduciaire et des agences d'éxécution(sur les 3 premières années) du projet CI-FIRCA-82335-CS-CQS / 2. Productivity Sélection d'un cabinet pour Consultant enhancement and Open - 2018-10- 2018-12- 2018-11- 2019-01- 2019-04- 2019-02- 2019-06- 2019-03- 2019-07- 2019-09- 2019-12- pour l'étude de faisabilité IBRD / 88450 Post Qualification 43,000.00 52,515.17 Completed improved access to International 30 09 20 03 11 02 07 09 04 05 16 de l'e-extension dans la Selection markets filière Anacarde CI-FIRCA-82454-CS-CQS / Sélectionner un cabinet 2. Productivity Consultant pour réaliser l'étude de enhancement and Open - 2018-10- 2018-12- 2018-11- 2019-01- 2019-03- 2019-02- 2019-06- 2019-03- 2019-07- 2019-09- IBRD / 88450 Post Qualification 43,000.00 127,208.83 Signed faisabilité d'un programme improved access to International 31 09 21 04 29 03 03 10 02 06 Selection des Opérateurs markets Professionnels du Cajou (OPCA) CI-FIRCA-82462-CS-CQS / 2. Productivity Sélectionner un cabinet Consultant enhancement and Open - Pending 2018-11- 2018-12- 2019-02- 2019-03- 2019-04- 2019-10- pour réaliser les missions IBRD / 88450 Post Qualification 86,000.00 0.00 improved access to International Implementation 29 20 02 04 08 05 de suivi des activités du Selection markets conseil agricole dédié par un Cabinet CI-FIRCA-82478-CS-CQS / Sélectionner un cabinet 2. Productivity Consultant pour réaliser l'étude de enhancement and Open - Pending 2018-10- 2018-11- 2019-01- 2019-02- 2019-03- 2019-09- IBRD / 88450 Post Qualification 69,000.00 0.00 mécanisation des activités improved access to International Implementation 31 21 04 03 10 06 Selection de ramassage de la récolte markets de l'anacarde en Côte d'ivoire CI-FIRCA-82484-CS-CQS / 2. Productivity Sélectionner un cabinet Consultant enhancement and Open - 2018-10- 2019-09- 2018-11- 2019-01- 2019-11- 2019-02- 2019-03- 2019-12- 2019-09- pour réaliser l'étude IBRD / 88450 Post Qualification 34,000.00 66,227.70 Signed improved access to International 31 02 21 04 11 03 10 13 06 technique de sécurisation Selection markets des sites du PAVA CI-FIRCA-82487-CS-CQS / 2. Productivity Sélection d'un cabinet pour Consultant enhancement and Open - Pending 2018-10- 2018-11- 2019-01- 2019-02- 2019-03- 2019-09- l'étude d'impact du conseil IBRD / 88450 Post Qualification 45,000.00 0.00 improved access to International Implementation 31 21 04 03 10 06 agricole dédié sur les Selection markets producteurs agricoles CI-FIRCA-105971-CS- 3. Support to private QCBS / Sélection d'un investment in post-harvest Quality And Cost- Open - 2019-06- 2019-07- 2019-07- 2019-09- 2019-09- 2019-10- 2019-12- 2020-01- 2021-01- cabinet pour réaliser l'EESS IBRD / 88450 Post 559,000.00 0.00 Under Review and processing Based Selection International 28 19 19 01 29 29 03 07 06 de la zone agro-industrielle infrastructure de Yamousssoukro CI-FIRCA-105978-CS- 3. Support to private QCBS / Sélection d'un investment in post-harvest Quality And Cost- Open - 2019-03- 2019-02- 2019-04- 2019-05- 2019-04- 2019-06- 2019-04- 2019-07- 2019-04- 2019-08- 2019-05- 2019-09- 2019-06- 2020-09- IBRD / 88450 Post 47,000.00 65,763.25 Signed consultant pour réaliser le and processing Based Selection International 13 27 03 17 23 14 23 14 23 18 29 22 25 21 CIES de Bondoukou infrastructure CI-FIRCA-106186-CS-CQS 1. Institutional Consultant / Sélection d'un cabinet 2019-03- 2019-07- 2019-03- 2019-07- 2019-04- 2019-08- 2019-06- 2019-09- 2019-11- IBRD / 88450 strengthening and value Post Qualification Limited 38,000.00 23,945.90 Signed pour réaliser l'audit 15 24 29 29 28 27 02 19 29 chain governance Selection technique des ouvrages du CITA CI-FIRCA-106445-CS-CQS / Recruter un cabinet pour la sensibilisation et la formation des acteurs 3. Support to private Consultant (ONG& Association) et des investment in post-harvest 2019-05- 2019-12- 2019-05- 2019-07- 2019-08- 2019-09- 2020-03- IBRD / 88450 Post Qualification Open - National 37,000.00 0.00 Canceled membres des commissions and processing 03 03 24 07 06 10 08 Selection d'évaluation et de purge des infrastructure droits coutumiers sur les différentes étapes de la réinstallation à Korhogo Page 6 CI-FIRCA-106449-CS- 3. Support to private QCBS / Sélection d'un investment in post-harvest Quality And Cost- 2019-05- 2019-07- 2019-06- 2019-12- 2019-08- 2020-03- 2019-08- 2020-04- 2019-09- 2020-04- 2019-11- 2020-05- 2019-12- 2020-10- 2020-12- IBRD / 88450 Post Open - National 837,000.00 740,085.45 Signed consultant pour Suivre les and processing Based Selection 30 26 20 12 03 03 31 02 30 14 04 14 09 09 08 travaux de la plateforme de infrastructure Korhogo CI-FIRCA-106458-CS-CQS 3. Support to private / Sélection de deux cabinet Consultant investment in post-harvest 2019-07- 2019-07- 2019-09- 2019-10- 2019-11- 2020-05- pour réaliser les études IBRD / 88450 Post Qualification Open - National 186,000.00 0.00 Canceled and processing 01 22 04 04 08 06 techniques de réhabilitation Selection infrastructure et de construction CI-FIRCA-106578-CS-CQS 2. Productivity / Sélection d'un cabinet Consultant enhancement and Under 2019-03- 2019-05- 2019-04- 2019-05- 2019-06- 2019-12- pour réaliser une étude sur IBRD / 88450 Post Qualification Limited 112,000.00 0.00 improved access to Implementation 31 29 14 14 18 15 le compte d'exploitation Selection markets des producteurs d'anacarde. CI-FIRCA-106593-CS- 2. Productivity QCBS / Sélection d'un enhancement and Quality And Cost- Open - Under 2019-03- 2019-11- 2019-04- 2019-06- 2020-01- 2019-07- 2020-01- 2019-08- 2019-09- 2019-10- 2020-10- IBRD / 88450 Post 316,000.00 0.00 consultant pour réaliser les improved access to Based Selection International Implementation 31 08 21 04 17 02 17 01 05 10 09 études de CIES /EIES des markets CDC . CI-FIRCA-106616-CS-CQS 2. Productivity Consultant / Sélection d'un consultant enhancement and 2019-03- 2019-09- 2019-04- 2019-10- 2019-05- 2019-11- 2019-06- 2019-12- 2019-12- IBRD / 88450 Post Qualification Limited 60,000.00 66,212.21 Signed pour réaliser les études improved access to 29 17 12 30 12 18 16 13 13 Selection techniques des sites de markets CDC. CI-FIRCA-106622-CS-CQS / Sélection d'un cabinet 2. Productivity Consultant pour réaliser deux missions enhancement and 2019-03- 2019-05- 2019-04- 2019-06- 2019-05- 2019-06- 2019-06- 2019-07- 2019-12- IBRD / 88450 Post Qualification Limited 80,000.00 82,836.36 Signed de suivi et d'évaluation des improved access to 29 07 12 03 12 25 16 11 13 Selection activité du Conseil Agricole markets dédié a l'Anacarde ( CAA). CI-FIRCA-106632-CS-CQS / Sélection d'un consultant pour faire le contrôle de 2. Productivity Consultant l'exécution des travaux de enhancement and Open - Pending 2019-03- 2019-04- 2019-05- 2019-06- 2019-07- 2020-01- IBRD / 88450 Post Qualification 261,000.00 0.00 réhabilitation et improved access to International Implementation 18 08 22 21 26 22 Selection construction et 146.04 Km markets de routes rurales ( Régions du GBEKE et du HAMBOL) . CI-FIRCA-106638-CS-CQS / Sélection d'un consultant pour faire le contrôle de 2. Productivity Consultant l'exécution des travaux de enhancement and Open - Pending 2019-03- 2019-04- 2019-05- 2019-06- 2019-07- 2020-01- IBRD / 88450 Post Qualification 261,000.00 0.00 réhabilitation et improved access to International Implementation 18 08 22 21 26 22 Selection construction de 116.90 Km markets de routes rurales (Région du GONTOUGO). CI-FIRCA-106644-CS-CQS 2. Productivity / Sélection d'un consultant Consultant enhancement and 2019-06- 2019-07- 2019-08- 2019-09- 2020-03- pour réaliser les études EIES IBRD / 88450 Post Qualification Limited 187,000.00 0.00 Canceled improved access to 28 12 11 15 13 /CIES des 448 Km à Selection markets réhabiliter et a construire. CI-FIRCA-106670-CS-CQS 2. Productivity / Sélection d'un consultant Consultant enhancement and Open - Pending 2019-03- 2019-04- 2019-05- 2019-06- 2019-07- 2020-01- pour réaliser les études IBRD / 88450 Post Qualification 243,000.00 0.00 improved access to International Implementation 18 08 22 21 26 22 techniques détaillées des Selection markets 448Km à réhabiliter et à construire. CI-FIRCA-106675-CS-CQS / sélection d'un consultant 2. Productivity Consultant pour faire le contrôle de enhancement and Open - Pending 2019-03- 2019-04- 2019-05- 2019-06- 2019-08- 2020-01- IBRD / 88450 Post Qualification 279,000.00 0.00 l'exécution des travaux de improved access to International Implementation 27 17 31 30 04 31 Selection réhabilitation de 448 Km markets (Mission 1 Gontougo ) CI-FIRCA-106678-CS-CQS / sélection d'un consultant 2. Productivity Consultant pour faire le contrôle de enhancement and Open - Pending 2019-09- 2019-10- 2019-11- 2019-12- 2020-01- 2020-07- IBRD / 88450 Post Qualification 279,000.00 0.00 l'exécution des travaux de improved access to International Implementation 16 07 20 20 24 22 Selection réhabilitation de 448 Km markets (Mission 1 Gontougo ) CI-FIRCA-106679-CS-CQS 2. Productivity / sélection d'un consultant Consultant enhancement and Open - Pending 2019-09- 2019-10- 2019-11- 2019-12- 2020-01- 2020-07- pour faire le contrôle de IBRD / 88450 Post Qualification 279,000.00 0.00 improved access to International Implementation 16 07 20 20 24 22 l'exécution des travaux de Selection markets réhabilitation de 448 Km (Mission2 hambol) CI-FIRCA-106701-CS-CQS 2. Productivity / Sélection d'un cabinet Consultant enhancement and Open - Pending 2019-09- 2019-10- 2019-11- 2019-12- 2020-01- 2020-07- pour faire le contrôle de IBRD / 88450 Post Qualification 186,000.00 0.00 improved access to International Implementation 16 07 20 20 24 22 l'exécution des travaux de Selection markets réhabilitation de 448Km (mission 3 GBEkE) CI-FIRCA-106869-CS-CQS / Recrutement d'un cabinet 1. Institutional Consultant Open - 2019-03- 2019-12- 2019-04- 2019-12- 2019-06- 2019-07- 2019-08- 2020-02- pour la viabilité technique IBRD / 88450 strengthening and value Post Qualification 112,000.00 0.00 Canceled International 30 10 20 17 03 03 07 03 et financière des 29 chain governance Selection sociétés coopératives. CI-FIRCA-107746-CS- QCBS / Recrutement d'une Firme de consultants chargé 1. Institutional Quality And Cost- Under 2019-03- 2019-07- 2019-04- 2019-05- 2020-02- 2019-06- 2019-07- 2019-08- 2019-10- 2020-10- de la mise en place et de IBRD / 88450 strengthening and value Post Open - National 250,000.00 0.00 Based Selection Implementation 25 07 15 29 28 26 26 30 04 03 l'opérationnalisation de la chain governance fonction d'audit interne au sein du CCA CI-FIRCA-107777-CS- 3. Support to private QCBS / Sélection d'un investment in post-harvest Quality And Cost- Pending 2019-04- 2019-05- 2019-06- 2019-07- 2019-08- 2019-09- 2019-10- 2020-10- IBRD / 88450 Post Open - National 100,000.00 0.00 consultant pour définir le and processing Based Selection Implementation 15 06 19 17 16 20 25 24 mode de gestion des sites infrastructure CI-FIRCA-126663-CS-CQS 2. Productivity Consultant / Sélection d'un consultant enhancement and Pending 2019-08- 2019-09- 2019-10- 2019-11- 2020-05- IBRD / 88450 Post Qualification Limited 28,000.00 0.00 pour réaliser les études improved access to Implementation 30 13 13 17 15 Selection techniques du sites CDC de markets Badikaha CI-FIRCA-126677-CS-CQS / Sélection d'un cabinet 2. Productivity pour la réalisation de deux Consultant enhancement and Pending 2019-08- 2019-08- 2019-09- 2019-11- 2020-04- missions de suivi des IBRD / 88450 Post Qualification Limited 92,000.00 0.00 improved access to Implementation 15 29 28 02 30 prestations du conseil Selection markets agricole dédié aux producteurs d'anacarde au titre de la campagne 2019. CI-FIRCA-126682-CS-CQS 2. Productivity / Sélection de consultants Consultant enhancement and 2019-09- 2021-04- 2019-09- 2019-12- 2019-10- 2020-03- 2019-12- 2020-03- 2020-05- pour Réaliser les études IBRD / 88450 Post Qualification Limited 47,000.00 58,570.42 Signed improved access to 15 02 29 20 29 13 03 30 31 EIES/CIES des 448 Km à Selection markets réhabiliter et à construire Mission 3 GBEKE) CI-FIRCA-126694-CS-CQS 1. Institutional Consultant / Recrutement d’un cabinet Under 2019-09- 2019-11- 2019-09- 2019-12- 2019-11- 2019-12- 2020-01- 2020-07- IBRD / 88450 strengthening and value Post Qualification Open - National 187,000.00 0.00 pour l’élaboration du code Implementation 01 25 22 31 05 05 09 07 chain governance Selection de l’environnement CI-FIRCA-126714-CS-CQS / Sélection de consultants 2. Productivity Consultant pour Réaliser les études enhancement and 2019-09- 2019-12- 2019-09- 2019-12- 2019-10- 2020-03- 2019-12- 2020-03- 2020-06- IBRD / 88450 Post Qualification Limited 70,000.00 60,832.53 Signed EIES/CIES des 448 Km à improved access to 16 09 30 19 30 13 04 30 01 Selection réhabiliter et à construire ( markets Mission 1Gountougo) CI-FIRCA-126717-CS-CQS / Sélection de consultants 2. Productivity Consultant pour Réaliser les études enhancement and 2019-09- 2021-04- 2019-09- 2019-12- 2019-10- 2020-03- 2019-12- 2020-03- 2020-06- IBRD / 88450 Post Qualification Limited 70,000.00 44,849.15 Signed EIES/CIES des 448 Km à improved access to 16 02 30 18 30 13 04 30 01 Selection réhabiliter et à construire markets ((Mission 2 Hambol) CI-FIRCA-126950-CS-CQS 2. Productivity / Sélection d'un consultant Consultant enhancement and 2019-08- 2018-05- 2019-09- 2019-10- 2018-06- 2019-11- 2019-12- 2018-08- 2020-06- chargé de l'EIES de 18 km IBRD / 88450 Post Qualification Open - National 100,000.00 35,127.38 Signed improved access to 12 09 02 16 26 15 20 13 17 de routes rurales de la Selection markets région du Hambol et Gontougo CI-FIRCA-140407-CS-CQS 4. Program coordination, Consultant / Réalisation de la situation 2019-10- 2019-05- 2019-10- 2019-05- 2019-11- 2019-08- 2020-01- 2019-08- 2020-06- IBRD / 88450 monitoring and knowledge Post Qualification Limited 320,000.00 286,441.03 Signed de référence et du suivi de 15 10 29 27 28 06 02 06 30 management Selection l'impact du PPCA CI-FIRCA-106198-CS-CQS / Sélection d'un cabinet pour la formation sur les différentes étapes du 1. Institutional Consultant 2019-03- 2019-04- 2019-05- 2019-06- 2019-07- 2020-01- processus de IBRD / 88450 strengthening and value Post Qualification Open - National 93,000.00 0.00 Canceled 15 05 19 18 23 19 transformation de la noix chain governance Selection de cajou désagrégées selon la qualification (technicien,superviseurs ,managers /gestions ) CI-FIRCA-74830-CS-CQS / Recrutement d'un cabinet 1. Institutional Consultant pour l'étude de référence de Open - 2018-10- 2018-11- 2018-12- 2019-01- 2019-02- 2019-08- IBRD / 88450 strengthening and value Post Qualification 50,000.00 0.00 Canceled satisfaction des acteurs sur International 15 05 19 18 22 21 chain governance Selection les mesures prises par le Gouvernement CI-FIRCA-106450-CS- 3. Support to private QCBS / Sélection d'un investment in post-harvest Quality And Cost- 2019-07- 2019-08- 2019-09- 2019-10- 2019-11- 2019-12- 2020-01- 2021-01- IBRD / 88450 Post Open - National 502,000.00 0.00 Canceled consultant pour Suivre les and processing Based Selection 15 05 18 16 15 20 24 23 travaux de la plateforme de infrastructure Bondoukou CI-FIRCA-82236-CS-QBS / Recrutement d'un Cabinet pour la mission de contrôle 2. Productivity technique du second enhancement and Quality Based 2019-04- 2019-04- 2019-06- 2019-07- 2019-08- 2019-09- 2019-10- 2020-10- programme de travaux de IBRD / 88450 Post Open - National 240,000.00 0.00 Canceled improved access to Selection 01 22 05 03 02 01 06 05 réhabilitation par RC et markets RLTPC de 125 km de routes rurales dans les Régions du Gbèkè et du Hambol (Mission II.1) CI-FIRCA-82307-CS-QBS / Recruter un cabinet pour 3. Support to private réaliser des études investment in post-harvest Quality Based 2018-11- 2018-12- 2019-01- 2019-02- 2019-03- 2019-04- 2019-05- 2020-05- IBRD / 88450 Post Open - National 28,000.00 0.00 Canceled techniques et de and processing Selection 15 06 19 16 18 17 22 21 sauvegarde infrastructure environnementale et sociale des sites des CDC CI-FIRCA-82246-CS-QBS / Recrutement d'un Cabinet pour la mission de contrôle 2. Productivity technique du second enhancement and Quality Based 2019-04- 2019-04- 2019-06- 2019-07- 2019-08- 2019-09- 2019-10- 2020-10- programme de travaux de IBRD / 88450 Post Open - National 240,000.00 0.00 Canceled improved access to Selection 01 22 05 03 02 01 06 05 réhabilitation par RC et markets RLTPC de 125 km de routes rurales dans les Régions du Gontougo et du Hambol (Mission II.2) CI-FIRCA-82234-CS-QBS / Recrutement d'un Cabinet 2. Productivity pour le contrôle technique enhancement and Quality Based 2018-10- 2018-11- 2019-01- 2019-01- 2019-03- 2019-04- 2019-05- 2020-05- des Travaux de IBRD / 88450 Post Open - National 280,000.00 0.00 Canceled improved access to Selection 30 20 03 31 02 01 06 05 réhabilitation par RLTPC de markets 170 km dans la Région du Gontougo (Mission I.3) CI-FIRCA-82248-CS-QBS / Recrutement d'un Cabinet pour la mission de contrôle 2. Productivity technique des travaux enhancement and Quality Based 2019-12- 2019-12- 2020-02- 2020-03- 2020-04- 2020-05- 2020-06- 2021-06- IBRD / 88450 Post Open - National 100,000.00 0.00 Canceled d'entretien par RLEP du 1er improved access to Selection 02 23 05 04 03 03 07 07 programme de 428 markets (258+170) km de routes rurales réhabilités CI-FIRCA-74812-CS-QBS / 3. Support to private Recrutement de consultants investment in post-harvest Quality Based 2018-10- 2018-11- 2018-12- 2019-01- 2019-02- 2019-03- 2019-04- 2020-04- pour le contrôle des travaux IBRD / 88450 Post Open - National 100,000.00 0.00 Canceled and processing Selection 15 05 19 16 15 17 21 20 de réhabilitation des infrastructure entrepôts de stockage CI-FIRCA-70158-CS-QBS / Recrutement d'un 3. Support to private consultant pour l 'évaluation investment in post-harvest Quality Based Open - 2017-06- 2018-03- 2018-03- 2018-05- 2018-05- 2018-05- 2018-06- 2018-07- 2019-07- IBRD / 88450 Post 250,000.00 0.00 Canceled environnementale et sociale and processing Selection International 29 12 31 14 14 29 20 25 25 stratégique (EEES) de la infrastructure zone industrielle de KORHOGO. CI-FIRCA-82265-CS-QCBS 3. Support to private / Recrutement d'un cabinet investment in post-harvest Quality And Cost- Open - 2019-04- 2019-05- 2019-06- 2019-07- 2019-08- 2019-09- 2019-10- 2020-10- pour l'accompagnement à la IBRD / 88450 Post 310,000.00 0.00 Canceled and processing Based Selection International 15 06 19 17 16 20 25 24 certification BPF et HACCP infrastructure pour les transformateurs CI-FIRCA-74788-CS-QCBS / Recrutement d'un bureau 3. Support to private d'études pour le suivi et le investment in post-harvest Quality And Cost- Open - 2019-02- 2019-02- 2019-04- 2019-05- 2019-06- 2019-07- 2019-08- 2020-08- IBRD / 88450 Post 660,000.00 0.00 Canceled contrôle des travaux and processing Based Selection International 01 22 07 05 04 09 13 12 d'aménagement de la zone infrastructure industrielle de Bouaké CI-FIRCA-74781-CS-QCBS 2. Productivity / Recrutement de enhancement and Quality And Cost- Open - 2019-01- 2019-01- 2019-03- 2019-04- 2019-05- 2019-06- 2019-07- 2020-07- prestataires pour la collecte IBRD / 88450 Post 350,000.00 0.00 Canceled improved access to Based Selection International 03 24 09 06 06 10 15 14 des données nécessaires markets pour alimenter le SIG CI-FIRCA-157329-CS-QBS / Recrutement d'un 2. Productivity consultant pour la enhancement and Quality Based 2020-02- 2020-03- 2020-03- 2020-05- 2020-04- 2020-05- 2020-04- 2020-06- 2020-04- 2020-07- 2020-04- 2020-09- 2020-04- 2021-09- réalisation d'une mission IBRD / 88450 Post Open - National 75,000.00 72,331.42 Signed improved access to Selection 26 03 18 01 15 29 06 28 08 28 20 01 21 01 d'évaluation des parcs à markets bois des pépiniéristes privées et d'une mission d'audit des pépinières privées CI-FIRCA-126687-CS- QCBS / Recrutement d’une 3. Support to private Entreprise Spécialisée pour investment in post-harvest Quality And Cost- 2019-10- 2019-11- 2019-12- 2020-01- 2020-02- 2020-03- 2020-04- 2021-04- la conception, la réalisation IBRD / 88450 Post Open - National 150,000.00 0.00 Canceled and processing Based Selection 15 05 19 16 15 21 25 25 et la gestion du centre de infrastructure valorisation des déchets sur la ZAI de Korhogo CI-FIRCA-106116-CS- 3. Support to private QCBS / Recruter un investment in post-harvest Quality And Cost- Open - 2019-12- 2020-01- 2020-03- 2020-03- 2020-04- 2020-06- 2020-07- 2021-07- IBRD / 88450 Post 60,000.00 0.00 Canceled consultant pour la and processing Based Selection International 27 17 01 29 28 02 07 07 réalisation des EIES/CIES de infrastructure Bouaké CI-FIRCA-106106-CS- 3. Support to private QCBS / Sélection d'un investment in post-harvest Quality And Cost- Open - 2019-05- 2019-05- 2019-07- 2019-08- 2019-09- 2019-10- 2019-11- 2020-11- IBRD / 88450 Post 47,000.00 0.00 Canceled consultant pour réaliser and processing Based Selection International 02 23 06 03 02 07 11 10 l'EIES/CIES de Séguéla infrastructure CI-FIRCA-157337-CS-CQS 2. Productivity Consultant / Recrutement d'un cabinet enhancement and Under 2020-02- 2020-07- 2020-03- 2020-10- 2020-04- 2020-05- 2020-11- IBRD / 88450 Post Qualification Limited 41,000.00 0.00 pour la formation des OPCA improved access to Implementation 25 10 10 26 09 14 10 Selection à la méthodologie GERME markets du BIT CI-FIRCA-157340-CS-CQS 2. Productivity / Recrutement d'un cabinet Consultant enhancement and Under 2020-02- 2020-03- 2020-03- 2020-04- 2020-05- 2020-06- 2020-12- pour la formation des OPCA IBRD / 88450 Post Qualification Open - National 19,000.00 0.00 improved access to Implementation 10 30 02 15 15 19 16 aux opérations de greffage Selection markets et surgreffage CI-FIRCA-157371-CS-CQS 2. Productivity / Recruter un consultant Consultant enhancement and 2020-02- 2021-02- 2020-03- 2020-05- 2020-08- 2020-06- 2020-09- 2020-07- 2020-09- 2021-01- pour la réalisation du EIES IBRD / 88450 Post Qualification Open - National 75,000.00 42,742.59 Signed improved access to 29 25 21 04 19 03 21 08 28 04 de 75,90 km de routes Selection markets rurales dans la région du Hambol CI-FIRCA-74846-CS-CQS / 3. Support to private Recrutement d'un cabinet Consultant investment in post-harvest Open - 2018-10- 2018-11- 2018-12- 2019-01- 2019-03- 2019-08- pour l'élaboration du guide IBRD / 88450 Post Qualification 40,000.00 0.00 Canceled and processing International 24 14 28 27 03 30 de l'investisseur de Selection infrastructure l'industrie de cajou CI-FIRCA-157375-CS-QBS / Recrutement d'un 2. Productivity consultant pour faire le enhancement and Quality Based Pending 2020-06- 2020-06- 2020-08- 2020-09- 2020-10- 2020-11- 2020-12- 2021-12- contrôle de l’exécution des IBRD / 88450 Post Open - National 219,000.00 0.00 improved access to Selection Implementation 08 29 12 09 09 08 13 13 travaux de réhabilitation et markets construction de 94,2 km de routes rurales (Région du GONTOUGO) Page 7 CI-FIRCA-157376-CS-CQS / Recrutement d'un consultant pour faire le 2. Productivity Consultant contrôle de l’exécution des enhancement and Pending 2020-06- 2020-06- 2020-08- 2020-09- 2020-10- 2021-04- IBRD / 88450 Post Qualification Open - National 322,000.00 0.00 travaux de réhabilitation et improved access to Implementation 08 29 12 11 16 14 Selection construction de 159,4 km markets de routes rurales (Régions du GBEKE et du HAMBOL) CI-FIRCA-157549-CS-CQS 3. Support to private Consultant Under 2020-02- 2020-03- 2020-03- 2020-04- 2020-05- 2020-07- 2020-12- / Sélection d'un consultant IBRD / 88450 investment in post-harvest Post Qualification Open - National 47,000.00 0.00 Implementation 22 05 14 27 27 01 28 pour réaliser l'EIES/CIES de and processing Selection Séguéla infrastructure CI-FIRCA-157551-CS-CQS / Recrutement d'un cabinet pour réaliser le suivi et le 3. Support to private Consultant contrôle des travaux de investment in post-harvest Under 2020-07- 2020-03- 2020-07- 2020-09- 2020-10- 2020-11- 2021-05- IBRD / 88450 Post Qualification Open - National 221,000.00 0.00 construction du centre de and processing Implementation 01 09 22 04 04 08 07 Selection vie, du poste de police, infrastructure bureaux administratifs et du centre de secours (GSPM) de la ZAI de Korhogo CI-FIRCA-157554-CS-CQS / Recrutement d'un cabinet pour la conception et la 3. Support to private Consultant réalisation des études investment in post-harvest Under 2020-03- 2020-10- 2020-03- 2020-05- 2020-06- 2020-07- 2021-01- IBRD / 88450 Post Qualification Open - National 188,000.00 0.00 techniques des and processing Implementation 08 09 29 12 11 16 12 Selection équipements du centre de infrastructure vie, du poste de police, bureaux administratifs et du centre de secours (GSPM) CI-FIRCA-106902-CS- QCBS / Recrutement d'un cabinet pour la conception 3. Support to private et la réalisation des études investment in post-harvest Quality And Cost- 2019-11- 2019-12- 2020-01- 2020-02- 2020-03- 2020-04- 2020-05- 2021-05- IBRD / 88450 Post Open - National 188,000.00 0.00 Canceled techniques des and processing Based Selection 15 06 19 16 17 21 26 26 équipements du centre de infrastructure vie, du poste de police, bureaux administratifs et du centre de secours (GSPM) CI-FIRCA-157759-CS-CQS / Recrutement d'un consultant (FIRME)pour faire 1. Institutional Consultant l'étude et la conception des 2020-03- 2020-03- 2020-03- 2020-05- 2020-08- 2020-06- 2020-09- 2020-07- 2020-10- 2021-01- IBRD / 88450 strengthening and value Post Qualification Open - National 65,000.00 92,723.50 Signed plans d'exécution des 02 27 23 06 25 05 25 10 09 06 chain governance Selection bâtiments abritant les DR du CCA (Bondoukou, Bouaké, Korhogo et Séguéla) CI-FIRCA-157769-CS-CQS / Recrutement d'un cabinet 1. Institutional Consultant 2020-03- 2020-06- 2020-03- 2020-07- 2020-05- 2020-08- 2020-06- 2020-08- 2020-07- 2020-09- 2021-01- pour l'évaluation externe du IBRD / 88450 strengthening and value Post Qualification Open - National 112,000.00 92,437.50 Signed 06 15 27 08 10 13 09 26 14 25 10 conseil agricole dédié aux chain governance Selection producteurs d'anacarde CI-FIRCA-106904-CS-CQS / Recrutement d'un 3. Support to private consultant pour la Consultant investment in post-harvest Pending 2020-02- 2020-03- 2020-05- 2020-06- 2020-07- 2021-01- modélisation en 3 IBRD / 88450 Post Qualification Open - National 19,000.00 0.00 and processing Implementation 28 20 03 02 07 03 Dimensions et la réalisation Selection infrastructure d'une vidéo de synthèse (film d'animation) de la plateforme agro industrielle de Korhogo CI-FIRCA-74787-CS-CQS / Recrutement d'un bureau 3. Support to private Consultant d'études pour le suivi et le investment in post-harvest 2019-02- 2019-02- 2019-04- 2019-05- 2019-06- 2019-12- IBRD / 88450 Post Qualification Open - National 1,100,000.00 0.00 Canceled contrôle des travaux and processing 01 22 07 07 11 08 Selection d'aménagement de la zone infrastructure industrielle de Korhogo CI-FIRCA-74789-CS-QCBS / Recrutement d'un bureau 3. Support to private d'études pour le suivi et le investment in post-harvest Quality And Cost- Open - Pending 2020-03- 2020-03- 2020-05- 2020-06- 2020-07- 2020-08- 2020-09- 2021-09- IBRD / 88450 Post 600,000.00 0.00 contrôle des travaux and processing Based Selection International Implementation 02 23 06 03 03 07 11 11 d'aménagement de la zone infrastructure industrielle de Séguéla CI-FIRCA-126685-CS- QCBS / Recrutement d'un 3. Support to private bureau d'études pour le investment in post-harvest Quality And Cost- 2020-03- 2020-03- 2020-03- 2020-05- 2020-05- 2020-08- 2020-06- 2020-10- 2020-07- 2020-10- 2020-08- 2020-11- 2020-09- 2020-12- 2021-09- IBRD / 88450 Post Open - National 400,000.00 747,618.67 Signed suivi et le contrôle des and processing Based Selection 04 31 25 18 08 19 05 05 05 21 09 09 13 10 13 travaux d'aménagement de infrastructure la zone industrielle de Bondoukou CI-FIRCA-74811-CS-CQS / Recrutement d'un Cabinet pour le contrôle technique 2. Productivity Consultant des Travaux de enhancement and Open - 2018-10- 2018-11- 2018-12- 2019-01- 2019-02- 2019-08- IBRD / 88450 Post Qualification 250,000.00 0.00 Canceled réhabilitation par RC et improved access to International 15 05 19 18 22 21 Selection RLTPC de 130 km dans la markets Région du Gbèkè et le Département de Niakara (Mission 1) CI-FIRCA-82311-CS-CQS / 1. Institutional Consultant Recrutement d'un bureau de Open - 2018-10- 2018-11- 2019-01- 2019-02- 2019-03- 2019-09- IBRD / 88450 strengthening and value Post Qualification 35,000.00 0.00 Canceled contrôle des travaux International 31 21 04 03 10 06 chain governance Selection d'aménagement de l'UGP CI-FIRCA-74833-CS-CQS / 1. Institutional Consultant Recrutement d'un Cabinet Open - 2018-09- 2018-10- 2018-11- 2018-12- 2019-01- 2019-07- IBRD / 88450 strengthening and value Post Qualification 50,000.00 0.00 Canceled pour former les acteurs du International 18 09 22 22 26 25 chain governance Selection SRE (GE, IE, CPQ) CI-FIRCA-74831-CS-CQS / Recrutement d'un cabinet 1. Institutional Consultant pour former les institutions Open - 2018-09- 2018-10- 2018-11- 2018-12- 2019-01- 2019-07- IBRD / 88450 strengthening and value Post Qualification 20,000.00 0.00 Canceled financières sur le SRE International 13 04 17 17 21 20 chain governance Selection (Banques, Assurances, autres acteurs financiers) CI-FIRCA-126730-CS-CQS 2. Productivity / Recruter un consultant Consultant enhancement and 2019-09- 2019-10- 2019-11- 2019-12- 2020-01- 2020-07- (firme) pour l'appui à IBRD / 88450 Post Qualification Open - National 47,000.00 0.00 Canceled improved access to 15 06 19 19 23 21 l'établissement des Selection markets certificats fonciers des sites du PAVA CI-FIRCA-126668-CS-CQS 2. Productivity / Sélection d'un cabinet Consultant enhancement and 2019-08- 2019-09- 2019-10- 2019-11- 2020-05- pour réaliser les études IBRD / 88450 Post Qualification Limited 28,000.00 0.00 Canceled improved access to 30 13 13 17 15 techniques du site de CDC Selection markets de Koflandé (BOUNA) CI-FIRCA-82464-CS-CQS / 2. Productivity Sélectionner un cabinet Consultant enhancement and Open - 2018-11- 2018-12- 2019-01- 2019-02- 2019-03- 2019-09- pour réaliser les missions IBRD / 88450 Post Qualification 86,000.00 0.00 Canceled improved access to International 15 06 19 18 25 21 de suivi des activités du Selection markets conseil agricole dédié CI-FIRCA-82466-CS-CQS / 2. Productivity Sélectionner un cabinet Consultant enhancement and Open - 2018-10- 2018-11- 2019-01- 2019-02- 2019-03- 2019-09- pour réaliser l'évaluation IBRD / 88450 Post Qualification 43,000.00 0.00 Canceled improved access to International 31 21 04 03 10 06 finale du projet de conseil Selection markets agricole dédié par un Cabinet CI-FIRCA-106448-CS-CQS / Recruter un cabinet pour la sensibilisation et la formation des acteurs 3. Support to private Consultant (ONG& Association) et des investment in post-harvest Pending 2020-04- 2020-05- 2020-06- 2020-07- 2020-08- 2021-02- IBRD / 88450 Post Qualification Open - National 37,000.00 0.00 membres des commissions and processing Implementation 20 11 24 24 28 24 Selection d'évaluation et de purge des infrastructure droits coutumiers sur les différentes étapes de la réinstallation à Bouaké CI-FIRCA-75272-CS-CQS / Recrutement d'un cabinet 1. Institutional Consultant 2018-10- 2018-11- 2018-12- 2019-01- 2019-02- 2019-08- pour l'actualisation du IBRD / 88450 strengthening and value Post Qualification Open - National 50,000.00 0.00 Canceled 16 06 20 19 23 22 système de contrôle qualité chain governance Selection des noix de cajou. CI-FIRCA-82457-CS-CQS / 2. Productivity Recrutement d'un Consultant enhancement and Open - 2018-11- 2018-12- 2019-01- 2019-02- 2019-03- 2019-09- consultant pour IBRD / 88450 Post Qualification 64,000.00 0.00 Canceled improved access to International 15 06 19 18 25 21 sélectionner et former des Selection markets postulants (pépiniéristes privés) au programme OPCA CI-FIRCA-106182-CS-CQS / Sélection d'un cabinet 1. Institutional Consultant pour réaliser l'étude de 2019-03- 2019-04- 2019-06- 2019-07- 2019-08- 2020-02- IBRD / 88450 strengthening and value Post Qualification Open - National 50,000.00 0.00 Canceled référence de satisfaction 31 21 04 04 08 04 chain governance Selection des acteurs sur les mesures prises du gouvernement CI-FIRCA-74838-CS-CQS / 3. Support to private Recrutement d'un cabinet Consultant investment in post-harvest Open - 2018-10- 2018-11- 2018-12- 2019-01- 2019-02- 2019-08- pour l'élaboration d'un IBRD / 88450 Post Qualification 34,000.00 0.00 Canceled and processing International 17 07 21 20 24 23 manuel sur les bonnes Selection infrastructure pratiques de stockage dans les entrepôts CI-FIRCA-82336-CS-CQS / 2. Productivity sélectionner un consultant Consultant enhancement and Open - 2018-10- 2018-11- 2019-01- 2019-02- 2019-03- 2019-09- pour réaliser l'étude de IBRD / 88450 Post Qualification 75,000.00 0.00 Canceled improved access to International 31 21 04 03 10 06 mise en place d'un Selection markets laboratoire de vitro plants d'anacardier CI-FIRCA-82475-CS-CQS / 2. Productivity Consultant Sélectionner un cabinet enhancement and Open - 2018-10- 2018-11- 2019-01- 2019-02- 2019-03- 2019-09- IBRD / 88450 Post Qualification 67,000.00 0.00 Canceled pour réaliser l'étude de improved access to International 31 21 04 03 10 06 Selection faisabilité de création des markets CDC CI-FIRCA-106194-CS-CQS / Sélection d'un cabinet pour la formation sur les différentes étapes du 1. Institutional Consultant 2020-04- 2020-05- 2020-07- 2020-08- 2020-09- 2021-03- processus de IBRD / 88450 strengthening and value Post Qualification Open - National 22,000.00 0.00 Canceled 29 20 03 02 06 05 transformation de la noix chain governance Selection de cajou désagrégées selon la qualification (technicien,superviseurs ,managers /gestions ) CI-FIRCA-106446-CS-CQS / Recruter un cabinet pour la sensibilisation et la formation des acteurs 3. Support to private Consultant (ONG& Association) et des investment in post-harvest Pending 2020-05- 2020-05- 2020-07- 2020-08- 2020-09- 2021-03- IBRD / 88450 Post Qualification Open - National 37,000.00 0.00 membres des commissions and processing Implementation 04 25 08 07 11 10 Selection d'évaluation et de purge des infrastructure droits coutumiers sur les différentes étapes de la réinstallation à Bondoukou CI-FIRCA-126671-CS-CQS 2. Productivity / Sélection d'un cabinet Consultant enhancement and 2019-08- 2019-09- 2019-10- 2019-11- 2020-05- pour réaliser les études IBRD / 88450 Post Qualification Limited 28,000.00 0.00 Canceled improved access to 30 13 13 17 15 techniques du sites CDC de Selection markets Koro sanankoro ( Touba) CI-FIRCA-126731-CS-CQS / Recruter 1 consultant 2. Productivity Consultant pour la mission d'audit et enhancement and 2019-09- 2019-09- 2019-10- 2019-11- 2020-05- IBRD / 88450 Post Qualification Limited 38,000.00 0.00 Canceled de contrôle des pépinières improved access to 09 23 23 27 25 Selection privées pour la production markets des plants greffés par les Pépiniéristes CI-FIRCA-74802-CS-CQS / 2. Productivity Recrutement d'un Consultant enhancement and Open - 2018-11- 2018-12- 2019-01- 2019-02- 2019-03- 2019-09- consultant pour la IBRD / 88450 Post Qualification 80,000.00 0.00 Canceled improved access to International 15 06 19 18 25 21 conception et l'illustration Selection markets des outils didactiques CI-FIRCA-74815-CS-CQS / Recrutement d'un Cabinet pour le contrôle technique 2. Productivity Consultant des Travaux de enhancement and Open - 2018-10- 2018-11- 2018-12- 2019-01- 2019-02- 2019-08- IBRD / 88450 Post Qualification 250,000.00 0.00 Canceled réhabilitation par RC et improved access to International 15 05 19 18 22 21 Selection RLTPC de 128 km dans la markets Région du Gontougo et les Départements de Katiola et Dabakala (Mission 2) CI-FIRCA-75277-CS-CQS / Recrutement de cabinets pour la mission d'étude environnementale et 2. Productivity Consultant sociales du second enhancement and 2018-09- 2018-10- 2018-11- 2018-12- 2019-01- 2019-07- IBRD / 88450 Post Qualification Open - National 150,000.00 0.00 Canceled programme construction de improved access to 18 09 22 22 26 25 Selection 100 km et de réhabilitation markets de par RC et RLTPC 250 km de routes rurales (à faire par l'AGEROUTE) CI-FIRCA-106447-CS-CQS / Recruter un cabinet pour la sensibilisation et la formation des acteurs 3. Support to private Consultant (ONG& Association) et des investment in post-harvest Pending 2020-06- 2020-07- 2020-08- 2020-09- 2020-10- 2021-04- IBRD / 88450 Post Qualification Open - National 37,000.00 0.00 membres des commissions and processing Implementation 19 10 23 22 27 25 Selection d'évaluation et de purge des infrastructure droits coutumiers sur les différentes étapes de la réinstallation à Séguéla CI-FIRCA-82309-CS-QCBS 2. Productivity / Recrutement d'un cabinet enhancement and Quality And Cost- Open - 2019-01- 2019-02- 2019-03- 2019-04- 2019-05- 2019-06- 2019-08- 2020-08- IBRD / 88450 Post 700,000.00 0.00 Canceled en vue d'identifier les improved access to Based Selection International 23 13 29 26 26 30 04 03 producteurs de noix de markets cajou CI-FIRCA-74777-CS-QCBS 4. Program coordination, Quality And Cost- Open - 2018-12- 2019-01- 2019-02- 2019-03- 2019-04- 2019-05- 2019-07- 2020-06- / Recrutement de IBRD / 88450 monitoring and knowledge Post 300,000.00 0.00 Canceled Based Selection International 20 10 23 23 22 27 01 30 consultants pour le management coaching des OPA CI-FIRCA-157368-CS-CQS / Recrutement d'un consultant pour réaliser 2. Productivity l’étude d’identification et de Consultant enhancement and 2020-11- 2020-09- 2020-11- 2021-01- 2020-11- 2021-02- 2020-12- 2021-03- 2020-12- 2021-09- cartographie des parcelles IBRD / 88450 Post Qualification Open - National 112,000.00 102,457.73 Signed improved access to 04 29 25 08 13 07 01 14 11 10 potentielles pour le Selection markets reboisement suivant les espèces identifiées et leur caractérisation CI-FIRCA-192595-CS-CQS / recrutement d’un cabinet 1. Institutional Consultant Under 2020-09- 2020-09- 2020-10- 2020-11- 2020-12- 2020-12- 2021-01- 2021-07- pour l’accompagnement à la IBRD / 88450 strengthening and value Post Qualification Open - National 50,000.00 0.00 Implementation 18 22 09 22 28 22 26 25 mise en œuvre d’un chain governance Selection laboratoire central au CITA. CI-FIRCA-192599-CS-CQS / recrutement d’un 1. Institutional Consultant consultant pour l’appui à Under 2020-09- 2020-09- 2020-10- 2020-11- 2020-12- 2020-12- 2021-01- 2021-07- IBRD / 88450 strengthening and value Post Qualification Open - National 76,000.00 0.00 l’élaboration de la stratégie Implementation 18 22 09 22 28 22 26 25 chain governance Selection national pour le développement des équipementiers CI-FIRCA-201742-CS-CQS / Recrutement d’un Cabinet pour la mission de contrôle 2. Productivity technique du second Consultant enhancement and Under 2020-12- 2021-04- 2020-12- 2021-01- 2021-02- 2021-08- programme de travaux de IBRD / 88450 Post Qualification Limited 280,000.00 0.00 improved access to Implementation 01 19 15 14 18 17 réhabilitation par RC et Selection markets RLTPC de 125 km de routes rurales dans les Régions du Gbèkè et du Hambol (Mission II.1) CI-FIRCA-201745-CS-CQS / Recrutement d’un Cabinet pour la mission de contrôle 2. Productivity technique du second Consultant enhancement and Under 2020-12- 2021-04- 2020-12- 2021-01- 2021-02- 2021-08- programme de travaux de IBRD / 88450 Post Qualification Limited 280,000.00 0.00 improved access to Implementation 01 19 15 14 18 17 réhabilitation par RC et Selection markets RLTPC de 125 km de routes rurales dans les Régions du Gontougo et du Hambol (Mission II.2) CI-FIRCA-201793-CS-CQS / Recrutement d’un Cabinet pour la mission d'études 2. Productivity Consultant techniques détaillé du enhancement and Under 2020-12- 2020-11- 2020-12- 2021-01- 2021-02- 2021-08- IBRD / 88450 Post Qualification Limited 280,000.00 0.00 troisième programme de improved access to Implementation 01 17 15 14 18 17 Selection réhabilitation par RC ou markets RLTPC de 400,3 km de routes rurales dans la Région du BERE CI-FIRCA-201800-CS-CQS / Recrutement d’un Cabinet pour la mission de contrôle 2. Productivity Consultant technique des travaux enhancement and Under 2020-12- 2021-02- 2020-12- 2021-01- 2021-02- 2021-08- IBRD / 88450 Post Qualification Limited 100,000.00 0.00 d'entretien par RLEP de 465 improved access to Implementation 01 09 15 14 18 17 Selection km de routes rurales dans markets les Régions du Gbèkè, du Hambol et du Gontougo Page 8 CI-FIRCA-201805-CS-CQS / Recruter 3 consultants 2. Productivity pour la réalisation des Consultant enhancement and Pending 2020-11- 2020-12- 2021-01- 2021-02- 2021-03- 2021-09- EIES/CIES du troisième IBRD / 88450 Post Qualification Open - National 180,000.00 0.00 improved access to Implementation 20 11 24 23 30 26 programme de Selection markets réhabilitation par RC ou RLTPC de 400,3 km de routes rurales dans la Région du BERE CI-FIRCA-157658-CS-CQS / Recrutement d'un consultant (FIRME)pour faire 1. Institutional Consultant le suivi et le contrôle des Pending 2021-01- 2021-01- 2021-03- 2021-04- 2021-05- 2021-11- IBRD / 88450 strengthening and value Post Qualification Open - National 65,000.00 0.00 travaux de réhabilitation et Implementation 04 25 10 09 14 10 chain governance Selection d'extension des bâtiments des délégations régionales du CCA (Korhogo, Bouaké,Bondoukou, Séguéla) CI-FIRCA-158224-CS-CQS / Recrutement d'un consultant individuel pour 1. Institutional Consultant la réalisation d'une étude 2020-04- 2020-05- 2020-06- 2020-07- 2020-08- 2021-02- IBRD / 88450 strengthening and value Post Qualification Open - National 37,000.00 0.00 Canceled sur la stratégie de 10 01 14 14 18 14 chain governance Selection développement communautaire dans les zones de production de l'anacarde CI-FIRCA-201962-CS-CQS / Recruter un Cabinet pour 1. Institutional Consultant l'appui au bilan de la Pending 2020-11- 2020-11- 2021-01- 2021-02- 2021-03- 2021-09- IBRD / 88450 strengthening and value Post Qualification Open - National 131,000.00 0.00 réforme de la filière Implementation 05 26 09 08 15 11 chain governance Selection anacarde (Étude, élaboration de textes réglementaires/législatifs) CI-FIRCA-157370-CS-CQS 2. Productivity / Recrutement de Consultant enhancement and 2021-03- 2021-04- 2021-05- 2021-06- 2021-07- 2022-01- consultants pour le suivi IBRD / 88450 Post Qualification Open - National 75,000.00 0.00 Canceled improved access to 15 05 19 18 23 19 technique des opérations de Selection markets reboisement compensatoire CI-FIRCA-157362-CS-CQS / Recrutement de 2. Productivity Consultant consultants pour le enhancement and 2020-11- 2020-12- 2021-01- 2021-02- 2021-03- 2021-09- IBRD / 88450 Post Qualification Open - National 56,000.00 0.00 Canceled renforcement de capacités improved access to 13 04 17 16 23 19 Selection des agents du conseil markets agricole dédié à la mise en œuvre du PGP CI-FIRCA-157332-CS-CQS / Recrutement d'un cabinet 2. Productivity pour le suivi des travaux Consultant enhancement and 2020-09- 2020-10- 2020-12- 2021-01- 2021-02- 2021-08- d'aménagement et de IBRD / 88450 Post Qualification Open - National 56,000.00 0.00 Canceled improved access to 30 21 04 03 07 06 construction des Selection markets infrastructures de base des 3 CDC CI-FIRCA-106907-CS- QCBS / Recrutement d'un 3. Support to private bureau d'étude pour le investment in post-harvest Quality And Cost- 2019-07- 2019-08- 2019-10- 2019-10- 2019-11- 2020-01- 2020-02- 2021-02- dimensionnement et l'étude IBRD / 88450 Post Open - National 940,000.00 0.00 Canceled and processing Based Selection 30 20 03 31 30 04 08 07 technique du centre de infrastructure valorisation des sous produits Anacarde CI-FIRCA-201999-CS-CQS / Recrutement d'un cabinet pour réaliser le suivi et le 3. Support to private Consultant contrôle des travaux de investment in post-harvest Pending 2021-04- 2021-04- 2021-06- 2021-07- 2021-08- 2022-02- IBRD / 88450 Post Qualification Open - National 132,000.00 0.00 construction du centre de and processing Implementation 01 22 05 05 09 05 Selection vie, du poste de police, infrastructure bureaux administratifs et du centre de secours (GSPM) de la ZAI de Bondoukou CI-FIRCA-157552-CS-CQS / recrutement d'une entreprise spécialisé pour la conception , l'élaboration 3. Support to private Consultant d'un mode de gestion et la investment in post-harvest Pending 2020-03- 2020-03- 2020-05- 2020-06- 2020-07- 2021-01- IBRD / 88450 Post Qualification Open - National 186,000.00 0.00 realisation des etiudes and processing Implementation 06 27 10 09 14 10 Selection techniques du centre de infrastructure valorisation des coques de noix de cajoux sur les ZAI de Korhogo Bondoukou Séguéla et Yamoussoukro CI-FIRCA-202007-CS-CQS / Recrutement d'un consultant pour la 3. Support to private Consultant réalisation de l'EIES/CIES du investment in post-harvest Pending 2020-11- 2020-12- 2021-02- 2021-03- 2021-04- 2021-10- IBRD / 88450 Post Qualification Open - National 80,000.00 0.00 sous-projet de centre de and processing Implementation 30 21 03 05 09 06 Selection valorisation des coques de infrastructure noix de cajou sur la zone industrielle de Yamoussoukro CI-FIRCA-157561-CS-CQS / Recrutement d'un cabinet 3. Support to private Consultant pour la conception et la investment in post-harvest Pending 2021-01- 2021-01- 2021-01- 2021-01- 2021-02- 2021-03- IBRD / 88450 Post Qualification Open - National 37,000.00 0.00 réalisation des études and processing Implementation 15 15 17 30 04 07 Selection techniques des infrastructure équipements et infrastructures du HUB CI-FIRCA-157557-CS-CQS / Recruter une firme pour réaliser une étude de marché en vue de la 3. Support to private Consultant promotion de la investment in post-harvest Pending 2020-11- 2020-11- 2021-01- 2021-02- 2021-03- 2021-09- IBRD / 88450 Post Qualification Open - National 75,000.00 0.00 consommation des produits and processing Implementation 05 26 09 08 15 11 Selection dérivés de l'anacarde et infrastructure proposer une stratégie de promotion de la consommation de ces produits CI-FIRCA-157562-CS-CQS / Sélection d'un laboratoire pour la détermination des caractéristiques/paramètres 3. Support to private Consultant physico-chimiques (valeurs investment in post-harvest Pending 2020-10- 2020-11- 2021-01- 2021-02- 2021-03- 2021-09- IBRD / 88450 Post Qualification Open - National 28,000.00 0.00 énergétiques, minéraux et and processing Implementation 29 19 02 01 08 04 Selection vitamines), organoleptiques infrastructure des produits dérivés de l'anacarde fabriqués localement CI-FIRCA-201964-CS-CDS / Recrutement d'un cabinet 1. Institutional Consultant Pending 2021-01- 2021-02- 2021-03- 2021-04- 2021-05- 2021-11- pour l'évaluation externe du IBRD / 88450 strengthening and value Post Qualification Open - National 112,000.00 0.00 Implementation 20 10 26 25 30 26 conseil agricole dédié aux chain governance Selection producteurs d'anacarde CI-FIRCA-213689-CS-CQS 1. Institutional Consultant / Recrutement d'un Pending 2021-01- 2021-02- 2021-04- 2021-05- 2021-06- 2021-12- IBRD / 88450 strengthening and value Post Qualification Open - National 40,000.00 0.00 Consultant pour Implementation 30 20 05 05 09 06 chain governance Selection l'actualisation du Manuel de procédure du PPCA CI-PPCA-224283-CS-CQS / Recruter un consultant 1. Institutional Consultant pour réaliser l'étude de Pending 2021-07- 2021-08- 2021-09- 2021-10- 2021-11- 2022-05- IBRD / 88450 strengthening and value Post Qualification Open - National 50,000.00 0.00 référence de satisfaction Implementation 15 05 18 18 22 21 chain governance Selection des acteurs sur les mesures prises par le Gouvernement CI-PPCA-224284-CS-CQS 3. Support to private / Recruter un Consultant investment in post-harvest Pending 2021-06- 2021-07- 2021-08- 2021-09- 2021-10- 2022-04- Consultant/firme pour la IBRD / 88450 Post Qualification Open - National 196,000.00 0.00 and processing Implementation 21 12 25 24 29 27 réalisation de l'EIES/CIES de Selection infrastructure la ZI de Yamoussoukro (250 ha) CI-PPCA-224287-CS-CQS / Recruter un consultant pour réaliser une mission 3. Support to private de contrôle pour suivre les Consultant investment in post-harvest Pending 2021-07- 2021-08- 2021-09- 2021-10- 2021-11- 2022-05- travaux de construction du IBRD / 88450 Post Qualification Open - National 168,000.00 0.00 and processing Implementation 12 02 15 15 19 18 centre de vie, du poste de Selection infrastructure police, bureaux administratifs et du centre de secours (GSPM) de la ZAI de Korhogo CI-PPCA-224288-CS-CQS / Recruter un consultant 1. Institutional Consultant Pending 2021-05- 2021-06- 2021-07- 2021-08- 2021-10- 2022-03- pour former les formateurs IBRD / 88450 strengthening and value Post Qualification Open - National 56,000.00 0.00 Implementation 24 14 28 27 01 30 du CITA (andragogie, chain governance Selection sécurité au travail, etc.,) CI-PPCA-224291-CS-CQS / Recruter un consultant pour réaliser une mission 3. Support to private de contrôle pour suivre les Consultant investment in post-harvest Pending 2021-09- 2021-10- 2021-12- 2022-01- 2022-02- 2022-08- travaux de construction du IBRD / 88450 Post Qualification Open - National 112,000.00 0.00 and processing Implementation 30 21 04 03 07 06 centre de vie, du poste de Selection infrastructure police, bureaux administratifs et du centre de secours (GSPM) de la ZAI de Bondoukou CI-PPCA-224296-CS-CQS / Recruter un consultant 3. Support to private pour réaliser une mission Consultant investment in post-harvest Pending 2021-08- 2021-08- 2021-10- 2021-11- 2021-12- 2022-06- de contrôle pour contrôler IBRD / 88450 Post Qualification Open - National 71,000.00 0.00 and processing Implementation 10 31 14 13 18 16 les travaux de construction Selection infrastructure d'infrastructures relatives au HUB pilote CI-PPCA-224298-CS-CQS / Recruter un laboratoire pour réaliser analyses qualité des eaux usées de 1. Institutional Consultant Under 2021-05- 2021-05- 2021-06- 2021-07- 2021-08- 2022-02- process, fumées de la IBRD / 88450 strengthening and value Post Qualification Limited 7,000.00 0.00 Implementation 25 19 08 08 12 08 chaudière et niveau de bruit chain governance Selection sur le site (dans le cadre de l'attribution de l'Arrêté d'autorisation d'Exploitation au CITA) CI-PPCA-224299-CS-CQS / Recruter un consultant 3. Support to private Consultant pour réaliser les études en investment in post-harvest Pending 2021-08- 2021-09- 2021-10- 2021-11- 2021-12- 2022-06- IBRD / 88450 Post Qualification Open - National 75,000.00 0.00 vue des mesures de and processing Implementation 23 13 27 26 31 29 Selection sauvegardes infrastructure environnementales et sociales des plateformes de services CI-PPCA-224301-CS-CQS / Recruter un cabinet pour 3. Support to private Consultant la réalisation des études investment in post-harvest Pending 2021-07- 2021-08- 2021-09- 2021-10- 2021-11- 2022-05- IBRD / 88450 Post Qualification Open - National 279,000.00 0.00 techniques des and processing Implementation 15 05 18 18 22 21 Selection infrastructures d'appui à la infrastructure zone industrielle de Yamoussoukro CI-PPCA-224305-CS-CQS / Recruter une firme pour réaliser une étude de marché sur la promotion de 3. Support to private Consultant la consommation des sous- investment in post-harvest Pending 2021-09- 2021-10- 2021-12- 2022-01- 2022-02- 2022-08- IBRD / 88450 Post Qualification Open - National 75,000.00 0.00 produits de l'anacarde et and processing Implementation 30 21 04 03 07 06 Selection proposer une stratégie de infrastructure promotion de la consommation des sous- produits de l'anacarde CI-PPCA-224307-CS-CQS / Recruter une firme pour 3. Support to private renforcer les capacités de Consultant investment in post-harvest Pending 2021-06- 2021-07- 2021-09- 2021-10- 2021-11- 2022-05- 12 PME transformatrices en IBRD / 88450 Post Qualification Open - National 47,000.00 0.00 and processing Implementation 30 21 03 03 07 06 techniques de promotion Selection infrastructure sur lieu de vente et en marketing-management CI-PPCA-224308-CS-CQS 1. Institutional Consultant Pending 2021-05- 2021-06- 2021-07- 2021-08- 2021-09- 2022-03- / Recruter un consultant IBRD / 88450 strengthening and value Post Qualification Open - National 94,000.00 0.00 Implementation 17 07 21 20 24 23 pour actualiser le SYGES chain governance Selection Anacarde CI-PPCA-224311-CS-CQS / Recruter des Consultants 3. Support to private Consultant individuels pour la investment in post-harvest Pending 2021-10- 2022-04- IBRD / 88450 Post Qualification Open - National 56,000.00 0.00 réalisation des EIES/CIES and processing Implementation 20 18 Selection des petites unités de infrastructure décorticage de noix de cajou CI-PPCA-224862-CS-QCBS 4. Program coordination, / Recruter un cabinet pour Quality And Cost- Pending 2021-06- 2021-07- 2021-08- 2021-09- 2021-10- 2021-11- 2021-12- 2022-12- IBRD / 88450 monitoring and knowledge Post Open - National 70,000.00 0.00 l'audit externe pour Based Selection Implementation 10 01 14 11 11 15 20 20 management l'exercice 2021, 2022 et 2023 CI-PPCA-224870-CS-CQS 4. Program coordination, Consultant / Recruter un cabinet en vue Pending 2021-04- 2021-05- 2021-07- 2021-07- 2021-09- 2022-03- IBRD / 88450 monitoring and knowledge Post Qualification Open - National 30,000.00 0.00 d'évaluer le comportement Implementation 27 18 01 31 04 03 management Selection des génotypes en diffusion CI-PPCA-225010-CS-CQS / Recruter un consultant en 2. Productivity Consultant vue de réaliser l'évaluation enhancement and Pending 2021-05- 2021-06- 2021-07- 2021-08- 2021-09- 2022-03- IBRD / 88450 Post Qualification Open - National 101,000.00 0.00 externe des activités du improved access to Implementation 20 10 24 23 27 26 Selection Programme National de markets Recherche sur l'Anacarde (PNRA) CI-PPCA-225013-CS-QCBS / Recruter un consultant en 2. Productivity vue de réaliser des études enhancement and Quality And Cost- Pending 2021-05- 2021-06- 2021-07- 2021-08- 2021-09- 2021-10- 2021-11- 2022-11- IBRD / 88450 Post Open - National 372,000.00 0.00 techniques pour la mise en improved access to Based Selection Implementation 20 10 24 21 20 25 29 29 place de laboratoires markets agronomiques au CITA CI-PPCA-225017-CS-CQS / Recruter un/des bureau(x) 2. Productivity de contrôle pour assurer le Consultant enhancement and Pending 2021-05- 2021-06- 2021-07- 2021-08- 2021-10- 2022-03- contrôle et le suivi IBRD / 88450 Post Qualification Open - National 373,000.00 0.00 improved access to Implementation 25 15 29 28 02 31 techniques, Selection markets environnementaux et sociaux des travails relatifs aux 3 CDC CI-PPCA-225023-CS-CQS / Recruter un cabinet pour 2. Productivity Consultant réaliser deux missions de enhancement and Pending 2021-05- 2021-05- 2021-07- 2021-08- 2021-09- 2022-03- IBRD / 88450 Post Qualification Open - National 94,000.00 0.00 suivi et d'évaluation des improved access to Implementation 10 31 14 13 17 16 Selection activités du Conseil Agricole markets dédié à l'Anacarde (CAA) 2021 CI-PPCA-225109-CS-CQS / Recruter un Consultant 2. Productivity pour le contrôle de Consultant enhancement and Pending 2021-07- 2021-08- 2021-10- 2021-11- 2021-12- 2022-06- l’exécution des travaux de IBRD / 88450 Post Qualification Open - National 280,000.00 0.00 improved access to Implementation 31 21 04 03 08 06 réhabilitation et Selection markets construction de 200 km de routes rurales de la Région du Béré (Mission 3.1) CI-PPCA-225202-CS-CQS / Recruter un Consultant 2. Productivity pour le contrôle de Consultant enhancement and Pending 2021-06- 2021-07- 2021-08- 2021-09- 2021-10- 2022-04- l’exécution des travaux de IBRD / 88450 Post Qualification Open - National 280,000.00 0.00 improved access to Implementation 15 06 19 18 23 21 réhabilitation et Selection markets construction de 200 km de routes rurales de la Région du Béré (Mission 3.1) CI-PPCA-225206-CS-CQS / Recruter un Consultant 2. Productivity pour le contrôle de Consultant enhancement and Pending 2021-06- 2021-07- 2021-08- 2021-09- 2021-10- 2022-04- l’exécution des travaux de IBRD / 88450 Post Qualification Open - National 280,000.00 0.00 improved access to Implementation 18 09 22 21 26 24 réhabilitation et Selection markets construction de 200 km de routes rurales de la Région du Béré Mission 3.2) CI-PPCA-225288-CS-CQS / Sélection d'une agence événementielle pour la mise 3. Support to private Consultant en œuvre de la stratégie de investment in post-harvest Pending 2021-07- 2021-08- 2021-09- 2021-10- 2021-11- 2022-05- IBRD / 88450 Post Qualification Open - National 140,000.00 0.00 promotion de la and processing Implementation 14 04 17 17 21 20 Selection consommation locale du infrastructure cajou et l'organisation des événements INDIVIDUAL CONSULTANTS Activity Reference No. Actual Invitation to Loan / Credit Market Contract Type Estimated Process Draft Negotiated Contract / Description Component Review Type Method Amount Terms of Reference Identified/Selected Signed Contract No. Approach Amount (US$) Status Contract Completion (US$) Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CI-FIRCA-71017-CS-INDV 4. Program coordination, Individual / Recrutement d'un 2018-07- 2018-08- 2018-08- 2018-10- 2019-04- IBRD / 88450 monitoring and knowledge Prior Consultant Direct 21,000.00 0.00 Canceled coordonnateur adjoint 31 10 31 05 03 management Selection chargé de l'industrie CI-FIRCA-72423-CS-INDV 4. Program coordination, Individual / Recrutement d'un 2018-02- 2018-08- 2018-09- 2018-10- 2019-04- IBRD / 88450 monitoring and knowledge Prior Consultant Direct 21,000.00 0.00 Canceled coordonnateur adjoint 27 20 10 15 13 management Selection chargé de l'industrie Page 9 CI-FIRCA-74764-CS-INDV / Recrutement de 5 4. Program coordination, Individual 2018-10- 2018-11- 2018-12- 2019-01- 2019-07- consultants pour l'appui à la IBRD / 88450 monitoring and knowledge Post Consultant Open 63,000.00 0.00 Canceled 11 29 20 24 23 mise en œuvre des activités management Selection sur le terrain par le CCA CI-FIRCA-74768-CS-INDV 4. Program coordination, Individual / Recrutement d'un 2018-10- 2019-05- 2018-12- 2019-01- 2019-02- 2019-08- IBRD / 88450 monitoring and knowledge Post Consultant Open 72,000.00 0.00 Under Review spécialiste assistance 29 13 17 07 11 10 management Selection technique industrielle CI-FIRCA-74769-CS-INDV 4. Program coordination, Individual 2019-03- 2019-05- 2019-06- 2019-07- 2020-01- / Recrutement d'un IBRD / 88450 monitoring and knowledge Post Consultant Open 24,000.00 0.00 Canceled 28 16 06 11 07 spécialiste marché et management Selection commerce CI-FIRCA-74772-CS-INDV 4. Program coordination, Individual 2018-10- 2019-07- 2018-12- 2019-07- 2018-12- 2019-09- 2019-01- 2019-09- 2019-07- / Recrutement d'une IBRD / 88450 monitoring and knowledge Post Consultant Open 24,000.00 998.30 Signed 18 19 06 26 27 05 31 30 30 assistante volet production management Selection CI-FIRCA-74775-CS-INDV 4. Program coordination, Individual 2018-10- 2018-12- 2018-11- 2019-01- 2018-12- 2019-01- 2019-03- 2019-07- / Recrutement d'une IBRD / 88450 monitoring and knowledge Post Consultant Open 24,000.00 14,423.72 Signed 11 12 29 10 20 24 29 23 assistante volet management Selection transformation CI-FIRCA-74779-CS-INDV / Recrutement d un 4. Program coordination, Individual spécialiste pour l'appui à la 2018-10- 2019-05- 2018-10- 2018-11- 2018-11- 2018-12- 2018-12- 2018-12- 2019-06- 2019-01- IBRD / 88450 monitoring and knowledge Post Consultant Direct 22,000.00 18,127.43 Completed mise en œuvre des mesures 17 13 27 07 17 21 22 21 20 25 management Selection de sauvegarde sociale et environnementale CI-FIRCA-74821-CS-INDV / Recrutement de 4. Program coordination, Individual 2018-10- 2018-12- 2019-01- 2019-02- 2019-08- consultants individuels sur IBRD / 88450 monitoring and knowledge Post Consultant Open 200,000.00 0.00 Canceled 30 18 08 19 18 les mesures de sauvegarde management Selection environnements et sociales. CI-FIRCA-75270-CS-CDS / Recrutement d'un 1. Institutional consultant pour faire 2018-10- 2018-11- 2019-01- 2019-07- IBRD / 88450 strengthening and value Post Direct Selection Direct 100,000.00 0.00 Canceled l'évaluation des 29 08 12 11 chain governance performances de 10 OPA de la filière anacarde avec des outils disponibles. CI-FIRCA-77855-CS-INDV 4. Program coordination, Individual 2018-03- 2019-05- 2018-06- 2018-07- 2018-07- 2019-01- / Recrutement du IBRD / 88450 monitoring and knowledge Post Consultant Open 84,000.00 0.00 Under Review 22 13 19 05 31 27 Spécialiste en sauvegarde management Selection environnementale CI-FIRCA-77904-CS-INDV 4. Program coordination, Individual / Recrutement du 2018-03- 2019-05- 2018-06- 2018-07- 2018-07- 2019-01- IBRD / 88450 monitoring and knowledge Post Consultant Open 84,000.00 0.00 Under Review SPÉCIALISTE 22 13 19 05 31 27 management Selection INFRASTRUCTURES INDUSTRIELLES CI-FIRCA-77910-CS-INDV 4. Program coordination, Individual / RECRUTEMENT DU 2018-03- 2019-05- 2018-06- 2018-07- 2018-08- 2018-07- 2019-02- IBRD / 88450 monitoring and knowledge Post Consultant Open 84,000.00 46,920.01 Signed SPÉCIALISTE EN 22 13 18 05 31 31 27 management Selection VULGARISATION AGRICOLE CI-FIRCA-77937-CS-INDV 4. Program coordination, Individual / RECRUTEMENT D4UN 2018-03- 2018-02- 2018-06- 2018-06- 2018-07- 2018-07- 2018-08- 2018-08- 2019-02- IBRD / 88450 monitoring and knowledge Post Consultant Open 84,000.00 46,920.01 Signed SPÉCIALISTE EN 15 25 19 15 20 20 30 13 26 management Selection INFRASTRUCTURES RURALES CI-FIRCA-77946-CS-INDV 4. Program coordination, Individual / RECRUTEMENT DU 2018-03- 2019-05- 2018-06- 2018-07- 2018-07- 2018-07- 2019-01- IBRD / 88450 monitoring and knowledge Post Consultant Open 84,000.00 0.00 Under Review SPÉCIALISTE EN SUIVI- 15 13 19 10 31 31 27 management Selection EVALUATION CI-FIRCA-77956-CS-INDV / RECRUTEMENT DU SPÉCIALISTE DE L'APPUI 4. Program coordination, Individual 2018-03- 2019-05- 2018-06- 2018-07- 2018-08- 2019-02- AUX ORGANISATIONS IBRD / 88450 monitoring and knowledge Post Consultant Open 84,000.00 0.00 Under Review 22 13 19 05 09 05 PROFESSIONNELLES ET management Selection DÉVELOPPEMENT COMMUNAUTAIRE CI-FIRCA-77991-CS-INDV 4. Program coordination, Individual / RECRUTEMENT DU 2018-03- 2019-05- 2018-08- 2018-08- 2018-09- 2018-10- 2019-04- IBRD / 88450 monitoring and knowledge Post Consultant Open 84,000.00 0.00 Under Review SPÉCIALISTE GENRE ET 15 13 24 24 28 09 07 management Selection INCLUSION SOCIALE CI-FIRCA-82009-CS-INDV 4. Program coordination, Individual 2018-10- 2018-12- 2018-12- 2019-02- 2019-08- / Recrutement d'un auditeur IBRD / 88450 monitoring and knowledge Post Consultant Open 84,000.00 0.00 Canceled 22 10 31 04 03 interne management Selection CI-FIRCA-82235-CS-CDS / Convention avec le BNETD pour la réalisation des 3. Support to private études techniques investment in post-harvest 2018-10- 2018-10- 2018-10- 2019-01- 2019-01- 2019-07- 2019-06- IBRD / 88450 Post Direct Selection Direct 340,000.00 216,785.14 Completed (APS,APD), pour and processing 19 12 29 02 07 01 03 l'aménagement de la zone infrastructure industrielle de Korhogo et préparation des DAO pour les appels d'offres CI-FIRCA-82313-CS-CDS / 4. Program coordination, Under 2018-11- 2018-12- 2019-02- 2019-08- contrat CCA FIRCA pour la IBRD / 88450 monitoring and knowledge Prior Direct Selection Direct 2,400,000.00 0.00 Implementation 29 09 12 11 gestion Fiduciaire du PPCA management CI-FIRCA-74748-CS-CDS / 2. Productivity Convention CCA FIRCA pour enhancement and 2018-10- 2019-05- 2018-10- 2018-12- 2019-06- la gestion de la sous IBRD / 88450 Post Direct Selection Direct 1,082,000.00 0.00 Under Review improved access to 01 13 11 15 13 composante 2.1 et la sous markets composante 2.2 CI-FIRCA-74756-CS-CDS / 4. Program coordination, Recrutement d'un 2018-11- 2019-05- 2018-11- 2019-02- 2019-08- IBRD / 88450 monitoring and knowledge Post Direct Selection Direct 84,000.00 0.00 Under Review spécialiste recherche- 20 13 30 03 02 management développement agricole CI-FIRCA-74823-CS-CDS / Recrutement de l'ESA par entente directe pour faire 1. Institutional 2018-11- 2019-04- 2018-12- 2019-05- 2019-02- 2019-06- 2019-08- 2019-09- l'évaluation des IBRD / 88450 strengthening and value Post Direct Selection Direct 100,000.00 73,097.53 Completed 30 24 10 24 13 18 12 02 performances de 10 OPA de chain governance la filière anacarde avec des outils disponibles CI-FIRCA-74825-CS-CDS / Recrutement d'un cabinet 1. Institutional 2018-10- 2018-10- 2018-11- 2018-10- 2019-01- 2018-11- 2019-07- 2019-01- pour l'installation du IBRD / 88450 strengthening and value Post Direct Selection Direct 140,000.00 69,061.82 Completed 27 12 06 22 10 14 09 13 Logiciel LOGISCOOP et la chain governance formation de 100 OPA à son utilisation CI-FIRCA-75208-CS-CDS / Convention avec l'AGEDI 3. Support to private pour les APS et APD et investment in post-harvest 2018-11- 2018-10- 2018-11- 2018-11- 2019-01- 2019-01- 2019-07- 2019-06- IBRD / 88450 Post Direct Selection Direct 250,000.00 189,156.84 Completed préparation des dossiers and processing 05 12 15 13 19 07 18 06 d'appels pour les sites de infrastructure Korhogo, Bondoukou, Bouaké et Seguéla. CI-FIRCA-75271-CS-CDS / Convention avec le BNETD 1. Institutional pour la conception d'un Pending 2018-11- 2018-12- 2019-02- 2019-08- IBRD / 88450 strengthening and value Post Direct Selection Direct 84,000.00 0.00 dispositif d'analyse et de Implementation 30 10 13 12 chain governance veille économique sur la filière anacarde. CI-FIRCA-82299-CS-CDS / 2. Productivity Convention avec AGEROUTE enhancement and 2018-11- 2018-11- 2018-11- 2018-11- 2019-02- 2019-01- 2019-07- IBRD / 88450 Post Direct Selection Direct 350,000.00 523,477.40 Signed sur les travaux d'entretien improved access to 18 05 28 27 01 07 31 et de réhabilitation des markets pistes CI-FIRCA-82319-CS-CDS / Contrat entre FIRCA et ANADER pour la mise en 2. Productivity œuvre des activités du enhancement and Under 2018-11- 2018-10- 2018-12- 2019-02- 2019-08- IBRD / 88450 Post Direct Selection Direct 1,900,000.00 0.00 conseil agricole dédié aux improved access to Implementation 30 15 10 13 12 producteurs d'anacarde, markets campagne 2017/2018 (août 2017 à juillet 2018) CI-FIRCA-82318-CS-CDS / Contrat FIRCA et ICRAF pour la mise en œuvre des 2. Productivity activités de surveillance de enhancement and 2018-11- 2019-01- 2018-12- 2018-10- 2019-02- 2019-05- 2019-08- IBRD / 88450 Post Direct Selection Direct 555,000.00 1,155,412.93 Signed la santé et la fertilité des improved access to 30 10 10 09 13 24 12 sols sous anacardiers markets (PNRA) et appui aux services de transfert de technologies sur l'anacarde CI-FIRCA-82323-CS-CDS / Contrat entre FIRCA et ANADER pour la mise en 2. Productivity œuvre des activités du enhancement and Under 2019-01- 2019-02- 2019-02- 2019-04- 2019-10- IBRD / 88450 Post Direct Selection Direct 1,992,000.00 0.00 conseil agricole dédié aux improved access to Implementation 24 05 03 09 06 producteurs d'anacarde, markets campagne 2019 (janvier à Décembre 2019) CI-FIRCA-82322-CS-CDS / Contrat entre le FIRCA et le 2. Productivity CNRA pour la poursuite du enhancement and 2018-11- 2018-12- 2018-12- 2018-10- 2019-02- 2019-06- 2019-08- programme d'amélioration IBRD / 88450 Post Direct Selection Direct 290,000.00 1,272,793.49 Signed improved access to 30 26 10 09 13 06 12 variétale(PNRA) et de markets fourniture du matériel végétal amélioré aux producteurs CI-FIRCA-82324-CS-CDS / Contrat entre FIRCA et ANADER pour la mise en 2. Productivity œuvre des activités du enhancement and 2018-11- 2018-08- 2018-12- 2018-10- 2019-02- 2018-12- 2019-08- IBRD / 88450 Post Direct Selection Direct 795,000.00 1,691,598.83 Signed conseil agricole dédié aux improved access to 30 01 10 15 13 04 12 producteurs d'anacarde, markets campagne 2017/2018 (août 2018 à Décembre 2018) CI-FIRCA-82327-CS-CDS / 2. Productivity Contrat entre FIRCA et UNA enhancement and 2018-11- 2019-01- 2018-12- 2018-10- 2019-02- 2019-05- 2019-08- pour la mise en œuvre des IBRD / 88450 Post Direct Selection Direct 214,000.00 83,690.68 Signed improved access to 30 16 10 09 13 17 12 activités de biotechnologie markets du PNRA CI-FIRCA-82329-CS-CDS / 2. Productivity Contrat entre FIRCA et UFHB enhancement and 2018-11- 2019-01- 2018-12- 2018-10- 2019-02- 2019-05- 2019-08- pour la mise en œuvre des IBRD / 88450 Post Direct Selection Direct 177,000.00 661,269.23 Signed improved access to 30 14 10 09 13 24 12 activités de Défense des markets Cultures du PNRA CI-FIRCA-82333-CS-CDS / 2. Productivity Contrat FIRCA et UPGC enhancement and 2018-11- 2019-01- 2018-12- 2018-10- 2019-02- 2019-05- 2019-08- KORHOGO pour la mise en IBRD / 88450 Post Direct Selection Direct 110,000.00 779,502.13 Signed improved access to 30 14 10 08 13 24 12 œuvre des activités du markets volet fertilité des sols du PNRA CI-FIRCA-82334-CS-CDS / Contrat entre FIRCA et l'INP- 2. Productivity HB YAKRO pour la mise en enhancement and 2018-11- 2019-01- 2018-12- 2018-10- 2019-02- 2019-05- 2019-08- IBRD / 88450 Post Direct Selection Direct 110,000.00 494,324.29 Signed œuvre des activités du volet improved access to 30 15 10 09 13 28 12 valorisation des produits de markets l'anacarde du PNRA CI-FIRCA-85965-CS-CDS / Entente directe avec 1. Institutional Pending 2018-11- 2018-12- 2019-02- 2019-08- l'université HO CHI MIN IBRD / 88450 strengthening and value Post Direct Selection Direct 150,000.00 0.00 Implementation 26 06 09 08 pour l'assistance au CCA chain governance dans le cadre du partenariat CI-FIRCA-106131-CS- INDV / sélection de cinq (5) consultants individuels 1. Institutional Individual pour le renforcement de la 2019-03- 2019-04- 2019-05- 2019-06- 2019-05- 2019-07- 2019-06- 2019-09- 2019-12- IBRD / 88450 strengthening and value Post Consultant Open 116,000.00 111,818.49 Signed coordination des activités à 15 24 03 27 24 26 28 04 25 chain governance Selection mettre en œuvre par le CCA sur le terrain le terrain (OPA,productivité ,ect ) CI-FIRCA-106151-CS-CDS / Sélection par entente directe du cabinet ANKOUVI 1. Institutional NAYO pour la conception (y 2019-03- 2019-04- 2019-03- 2019-06- 2019-05- 2019-07- 2019-11- IBRD / 88450 strengthening and value Post Direct Selection Direct 100,000.00 91,758.15 Signed compris spécifications 14 30 24 24 28 23 24 chain governance techniques du matériel à acquérir) et le suivi de la collecte électronique de données. CI-FIRCA-106176-CS- 1. Institutional Individual INDV / Recrutement d'un 2019-04- 2019-03- 2019-04- 2019-04- 2019-04- 2019-05- 2019-06- 2019-06- 2019-11- 2019-07- IBRD / 88450 strengthening and value Post Consultant Limited 10,000.00 10,080.04 Completed consultant individuel pour 01 05 06 11 27 31 01 26 28 26 chain governance Selection réaliser une évaluation du LOGISCOOP CI-FIRCA-106189-CS- INDV / Sélection d'un 1. Institutional Individual 2019-03- 2019-07- 2019-03- 2019-10- 2019-04- 2020-01- 2019-05- 2020-02- 2019-11- consultant individuel pour IBRD / 88450 strengthening and value Post Consultant Limited 19,000.00 13,843.90 Signed 15 23 20 28 10 08 15 05 11 l'audit environnemental et chain governance Selection social du CITA CI-FIRCA-106441-CS- 3. Support to private INDV / Recruter un Individual investment in post-harvest 2019-03- 2019-03- 2019-05- 2019-04- 2019-05- 2019-05- 2019-06- 2019-06- 2019-12- 2020-05- consultant pour la IBRD / 88450 Post Consultant Open 19,000.00 42,314.44 Completed and processing 15 15 03 26 24 29 28 05 25 07 réalisation du PAR de la Selection infrastructure zone agro-industrielle de Korhogo CI-FIRCA-106442-CS- 3. Support to private INDV / Recruter un Individual investment in post-harvest 2019-03- 2019-04- 2019-05- 2019-04- 2019-05- 2019-09- 2019-06- 2019-10- 2019-12- consultant pour la IBRD / 88450 Post Consultant Open 19,000.00 41,281.98 Signed and processing 15 26 03 26 24 23 28 21 25 réalisation du PAR de la Selection infrastructure zone agro-industrielle de Bondoukou CI-FIRCA-106443-CS- 3. Support to private INDV / Recruter un Individual investment in post-harvest 2019-03- 2021-04- 2019-05- 2019-12- 2019-05- 2020-01- 2019-06- 2020-02- 2019-12- consultant pour la IBRD / 88450 Post Consultant Open 19,000.00 43,875.44 Signed and processing 15 01 03 18 24 08 28 05 25 réalisation du PAR de la Selection infrastructure zone agro-industrielle de Séguéla CI-FIRCA-106451-CS-CDS 3. Support to private / Convention avec l'AGEDI investment in post-harvest Under 2019-06- 2019-07- 2019-09- 2020-03- IBRD / 88450 Post Direct Selection Direct 194,000.00 0.00 pour superviser les travaux and processing Implementation 30 10 13 11 des plateformes infrastructure industrielles CI-FIRCA-106462-CS-CDS / Recrutement d'un cabinet 4. Program coordination, Pending 2019-04- 2019-05- 2019-07- 2020-01- de formation (PANSS) sur la IBRD / 88450 monitoring and knowledge Post Direct Selection Direct 19,000.00 0.00 Implementation 30 10 14 10 présentation efficace de management DALE CARNEGIE CI-FIRCA-106557-CS- INDV / Recrutement d'un 1. Institutional Individual spécialiste pour l'appui à la 2019-03- 2019-07- 2019-05- 2018-11- 2019-05- 2018-11- 2019-07- 2018-07- 2019-12- IBRD / 88450 strengthening and value Post Consultant Open 40,000.00 51,513.30 Signed mise en œuvre des mesures 18 11 06 07 27 07 01 31 28 chain governance Selection de sauvegarde sociale et environnementale CI-FIRCA-106562-CS- 2. Productivity Individual INDV / Recrutement d'un enhancement and 2019-03- 2019-02- 2019-05- 2019-05- 2019-05- 2019-05- 2019-07- 2019-06- 2019-12- IBRD / 88450 Post Consultant Open 67,000.00 33,084.10 Signed Coordonnateur Scientifique improved access to 18 19 06 02 27 27 01 04 28 Selection (CS) du PNRA. markets CI-FIRCA-106569-CS- INDV / Recrutement d'un 1. Institutional Individual Pending 2019-03- 2019-05- 2019-06- 2019-07- 2020-01- consultant individuel pour IBRD / 88450 strengthening and value Post Consultant Open 20,000.00 0.00 Implementation 29 17 07 12 08 l'élaboration de la stratégie chain governance Selection de communication du PPCA . CI-FIRCA-106576-CS-CDS / Recrutement de 2. Productivity consultant pour faire le enhancement and 2019-03- 2019-11- 2019-03- 2019-12- 2019-06- 2020-01- 2019-11- IBRD / 88450 Post Direct Selection Direct 84,000.00 16,937.79 Signed suivi -évaluation improved access to 18 28 28 16 01 06 28 scientifique des projets mis markets en œuvre dans le cadre du PNRA. CI-FIRCA-106602-CS- 2. Productivity Individual INDV / Sélection d'un enhancement and 2019-03- 2021-02- 2019-04- 2019-09- 2019-04- 2019-11- 2019-05- 2019-11- 2019-11- 2020-12- IBRD / 88450 Post Consultant Limited 35,000.00 44,717.31 Completed consultant pour la improved access to 31 25 05 17 26 11 31 19 27 15 Selection réalisation du PAR du CDC markets de Badikaha (Hambol). CI-FIRCA-106641-CS- 2. Productivity INDV / Sélection de trois Individual enhancement and 2019-03- 2019-01- 2019-04- 2019-03- 2019-04- 2019-05- 2019-05- 2019-06- 2019-11- 2019-12- consultants pour réaliser le IBRD / 88450 Post Consultant Limited 47,000.00 25,967.74 Completed improved access to 29 28 03 04 24 29 29 18 25 20 screening environnemental Selection markets et social de 448 Km Page 10 CI-FIRCA-106666-CS- 2. Productivity INDV / sélection de cinq Individual enhancement and 2019-03- 2019-05- 2019-04- 2019-05- 2019-04- 2019-08- 2019-05- 2019-09- 2019-11- consultants individuels pour IBRD / 88450 Post Consultant Limited 47,000.00 48,177.36 Signed improved access to 29 17 03 22 24 09 29 04 25 réaliser l'évaluation sociale Selection markets des 448 Km. CI-FIRCA-106877-CS-CDS 3. Support to private 2019-03- 2019-04- 2019-04- 2019-04- 2019-06- 2019-05- 2019-12- 2019-06- / Entente directe avec SERF IBRD / 88450 investment in post-harvest Post Direct Selection Direct 60,000.00 50,508.79 Completed 22 01 01 12 05 10 02 22 pour réaliser le CIES de and processing Korhogo infrastructure CI-FIRCA-107751-CS- 1. Institutional QCBS / Recrutement par 2019-04- 2019-06- 2019-04- 2019-06- 2019-12- IBRD / 88450 strengthening and value Post Direct Selection Direct 32,000.00 0.00 Under Review entente directe de 01 07 11 15 12 chain governance l'Informaticien archiviste DOUDOU Casimir CI-FIRCA-107754-CS- 2. Productivity INDV / recrutement du Individual enhancement and Pending 2019-04- 2019-04- 2019-04- 2019-06- 2019-11- consultant pour IBRD / 88450 Post Consultant Limited 40,000.00 0.00 improved access to Implementation 01 06 27 01 28 l'accompagnement des Selection markets unités de décorticage ''Grins de décorticage" CI-FIRCA-107784-CS- 4. Program coordination, Individual 2019-04- 2019-04- 2019-06- 2019-08- 2019-06- 2019-08- 2019-07- 2019-10- 2020-01- INDV / Recrutement d'un(e) IBRD / 88450 monitoring and knowledge Post Consultant Open 28,000.00 24,943.65 Signed 15 24 03 14 24 14 29 24 25 assistant(e) communication management Selection CI-FIRCA-118485-CS-CDS / Contrat entre FIRCA et ANADER pour la mise en 2. Productivity œuvre des activités du enhancement and Pending 2018-10- 2018-10- 2021-09- 2022-03- IBRD / 88450 Prior Direct Selection Direct 19,000,000.00 0.00 conseil agricole dédié aux improved access to Implementation 09 19 20 19 producteurs d'anacarde, markets campagne 2017/2018 (août 2017 à juillet 2018) CI-FIRCA-106114-CS-CDS / sélection par entente directe du BNETD pour 1. Institutional concevoir et mettre en place 2019-03- 2019-04- 2019-03- 2019-02- 2019-05- 2019-05- 2019-11- IBRD / 88450 strengthening and value Post Direct Selection Direct 234,000.00 197,604.82 Signed le SYSPER ,Système 14 23 24 26 28 03 24 chain governance Permanent de collecte et d'analyse de données de la filière anacarde . CI-FIRCA-126690-CS-CDS / Contrat en Entente Directe de la Direction Régionale 2. Productivity NORD de l'ANADER pour la enhancement and 2019-08- 2021-04- 2019-08- 2019-10- 2020-04- gestion des travaux de IBRD / 88450 Post Direct Selection Direct 754,000.00 0.00 Under Review improved access to 15 02 25 29 26 réhabilitation des vergers markets d'anacardiers par les tronçonneurs dans le cadre du programme des Opérateurs Professionnels du Cajou . CI-FIRCA-126703-CS-CDS / Recrutement d’un 3. Support to private consultant individuel pour investment in post-harvest 2019-08- 2019-07- 2019-08- 2019-07- 2019-10- 2019-09- 2020-04- la promotion des IBRD / 88450 Post Direct Selection Direct 50,000.00 43,903.61 Signed and processing 13 23 23 27 27 04 24 opportunités infrastructure d’investissements dans la chaine de valeur de l’anacarde en Côte d’Ivoire CI-FIRCA-126700-CS-CDS / Contrat en Entente Directe de la Direction Régionale Centre de l'ANADER pour la 2. Productivity gestion des travaux de enhancement and Under 2019-08- 2021-04- 2019-08- 2019-10- 2020-04- IBRD / 88450 Post Direct Selection Direct 558,000.00 0.00 réhabilitation des vergers improved access to Implementation 17 02 27 31 28 d'anacardiers par les markets tronçonneurs dans le cadre du programme des Opérateurs Professionnels du Cajou ( OPCA ) CI-FIRCA-126706-CS-CDS / Recruter un Cabinet pour l’extension du Système 1. Institutional 2019-08- 2019-10- 2019-09- 2019-10- 2019-11- 2019-12- 2020-05- Informatisé de Gestion des IBRD / 88450 strengthening and value Post Direct Selection Direct 60,000.00 91,736.70 Signed 30 03 09 23 13 13 11 Mouvements de l’Anacarde chain governance (SIGEMA) dans le cadre du SYSPER CI-FIRCA-126707-CS-CDS / Contrat en Entente Directe de la Direction Régionale CENTRE-OUEST de 2. Productivity l’ANADER pour la gestion enhancement and 2019-08- 2021-04- 2019-08- 2019-10- 2020-04- des travaux de IBRD / 88450 Post Direct Selection Direct 290,000.00 0.00 Under Review improved access to 15 02 25 29 26 réhabilitation des vergers markets d’anacardiers par les tronçonneurs dans le cadre du programme des Opérateurs Professionnels du Cajou (OPCA) CI-FIRCA-126712-CS-CDS / Contrat en Entente Directe de la Direction Régionale OUEST de l’ANADER pour la 2. Productivity gestion des travaux de enhancement and 2019-08- 2021-04- 2019-08- 2019-10- 2020-04- IBRD / 88450 Post Direct Selection Direct 157,000.00 0.00 Under Review réhabilitation des vergers improved access to 15 02 25 29 26 d’anacardiers par les markets tronçonneurs dans le cadre du programme des Opérateurs Professionnels du Cajou (OPCA) CI-FIRCA-126715-CS-CDS / Recruter un Cabinet pour 1. Institutional le renforcement du Système 2019-08- 2019-10- 2019-09- 2019-10- 2019-11- 2019-12- 2020-05- IBRD / 88450 strengthening and value Post Direct Selection Direct 60,000.00 75,907.95 Signed Informatisé de 30 15 09 23 13 13 11 chain governance Commercialisation extérieur dans le cadre du SYSPER CI-FIRCA-126723-CS-CDS 3. Support to private / Sélection d'un Consultant investment in post-harvest 2019-09- 2019-10- 2019-09- 2019-11- 2019-09- 2020-01- 2019-09- pour l'accompagnement des IBRD / 88450 Post Direct Selection 60,000.00 40,140.02 Signed and processing 15 17 15 01 15 16 15 unités de décorticage dans infrastructure la mise en oeuvre des BPF et BPH CI-FIRCA-126736-CS-CDS / Sélection d’un consultant pour installer le LOGISCOOP 1. Institutional 2019-08- 2019-11- 2019-08- 2019-12- 2019-10- 2020-02- 2020-04- dans 30 nouvelles SCOOP IBRD / 88450 strengthening and value Post Direct Selection Direct 97,000.00 77,371.99 Signed 16 26 26 05 30 07 27 les former à son utilisation chain governance et assurer le suivi post- formation CI-FIRCA-126842-CS-CDS / Sélection d’un consultant pour la réalisation de 2. Productivity la mission d’audit et de enhancement and 2019-08- 2019-08- 2019-08- 2019-08- 2019-10- 2019-08- 2020-04- IBRD / 88450 Post Direct Selection Direct 28,000.00 30,407.71 Signed contrôle des pépinières improved access to 15 15 25 20 29 23 26 de production des plants markets greffes d’anacardier au titre de la campagne 2019 CI-FIRCA-126872-CS-CDS / Sélection d'un cabinet pour le diagnostic global et 3. Support to private évaluation des capacités investment in post-harvest 2019-08- 2018-11- 2019-08- 2018-12- 2019-10- 2018-12- 2020-04- 2019-12- techniques et financières IBRD / 88450 Post Direct Selection Direct 230,000.00 258,856.95 Completed and processing 10 01 20 04 24 21 21 18 des entreprises de infrastructure transformation de l’anacarde et élaboration d’un plan de mise à niveau du PPCA CI-FIRCA-140337-CS-CDS / Contrat en Entente Directe de la Direction Régionale CENTRE-EST de l’ANADER 2. Productivity pour la gestion des travaux enhancement and 2019-10- 2021-04- 2019-10- 2019-10- 2019-10- de réhabilitation des IBRD / 88450 Post Direct Selection 392,000.00 0.00 Under Review improved access to 15 02 15 15 15 vergers d’anacardiers par markets les tronçonneurs dans le cadre du programme des Opérateurs Professionnels du Cajou (OPCA) CI-FIRCA-140595-CS-CDS / Contrat par entente 2. Productivity directe avec le CIRES de enhancement and Under 2019-10- 2020-07- 2019-11- 2020-10- 2020-01- 2020-07- IBRD / 88450 Post Direct Selection Direct 112,000.00 0.00 l'UFHB pour la réalisation du improved access to Implementation 23 21 02 21 06 04 compte d'exploitation du markets producteur de l'anacarde. CI-FIRCA-126710-CS-CDS 3. Support to private / Sélection d’un Consultant investment in post-harvest 2019-09- 2019-09- 2019-11- 2020-05- pour l’accompagnement des IBRD / 88450 Post Direct Selection Direct 60,000.00 0.00 Canceled and processing 16 26 30 28 unités de décorticage dans infrastructure la mise en œuvre des BPF et BPH CI-FIRCA-106175-CS-CDS / Sélection par entente 1. Institutional directe du cabinet 3D 2019-07- 2019-07- 2019-09- 2020-03- IBRD / 88450 strengthening and value Post Direct Selection Direct 97,000.00 0.00 Canceled solution pour la poursuite 01 11 14 12 chain governance de l'installation du LOGISCOOP dans de nouvelles SCOOP CI-FIRCA-106586-CS- 2. Productivity Individual INDV / Sélection d'un enhancement and 2019-06- 2019-07- 2019-07- 2019-08- 2020-02- IBRD / 88450 Post Consultant Limited 38,000.00 0.00 Canceled consultant individuel pour improved access to 28 03 24 28 24 Selection réaliser les PAR des sites du markets PAVA. CI-FIRCA-126673-CS-CDS / Sélection d’un consultant pour installer le LOGISCOOP 1. Institutional 2019-08- 2019-08- 2019-10- 2020-04- dans 30 nouvelles SCOOP IBRD / 88450 strengthening and value Post Direct Selection Direct 97,000.00 0.00 Canceled 16 26 30 27 les former à son utilisation chain governance et assurer le suivi post- formation CI-FIRCA-126734-CS-CDS / Sélection d’un consultant 2. Productivity pour installer le LOGISCOOP enhancement and 2019-08- 2019-08- 2019-10- 2020-04- dans 30 nouvelles SCOOP IBRD / 88450 Post Direct Selection Direct 97,000.00 0.00 Canceled improved access to 16 26 30 27 les former à son utilisation markets et assurer le suivi post- formation CI-FIRCA-74758-CS-INDV / Recrutement de 4. Program coordination, Individual 2018-10- 2018-11- 2018-10- 2018-11- 2018-12- 2019-06- Consultants pour le IBRD / 88450 monitoring and knowledge Post Consultant Limited 40,000.00 0.00 Canceled 25 21 30 20 25 23 démarrage des paper work management Selection mises en œuvre par le CCA CI-FIRCA-74844-CS-INDV / Recrutement d'un 1. Institutional Individual consultant pour définir le 2018-11- 2019-01- 2019-01- 2019-03- 2019-08- IBRD / 88450 strengthening and value Post Consultant Open 20,000.00 0.00 Canceled cadre identification et de 19 07 28 04 31 chain governance Selection géo référencement des acteurs de la filière anacarde CI-FIRCA-106886-CS- 2. Productivity Individual INDV / Sélection d' un enhancement and 2019-05- 2019-05- 2019-06- 2019-07- 2020-01- IBRD / 88450 Post Consultant Limited 35,000.00 0.00 Canceled consultant pour la improved access to 15 20 10 15 11 Selection réalisation du PAR du CDC markets de Goulia Kanasso CI-FIRCA-74803-CS-INDV 3. Support to private / Recrutement de Individual investment in post-harvest 2019-01- 2019-03- 2019-03- 2019-05- 2019-11- consultants pour la IBRD / 88450 Post Consultant Open 225,000.00 0.00 Canceled and processing 20 10 31 05 01 formation d'un pool Selection infrastructure d'experts sur le marchés de cajou CI-FIRCA-106485-CS- INDV / Sélection d'un 4. Program coordination, Individual consultant pour mettre en 2019-12- 2019-12- 2020-01- 2020-02- 2020-08- IBRD / 88450 monitoring and knowledge Post Consultant Limited 10,000.00 0.00 Canceled place une base de données 15 20 10 14 12 management Selection permettant de suivre les cas d'intoxication (2 régions) CI-FIRCA-74827-CS-INDV / Recrutement de 2 1. Institutional Individual 2018-10- 2018-10- 2018-11- 2018-12- 2019-06- consultants pour l'analyse IBRD / 88450 strengthening and value Post Consultant Limited 50,000.00 0.00 Canceled 18 23 13 18 16 technique et financière de la chain governance Selection viabilité des OPA CI-FIRCA-106604-CS- 2. Productivity INDV / Sélection d'un Individual enhancement and 2019-03- 2019-04- 2019-04- 2019-05- 2019-11- consultant pour la IBRD / 88450 Post Consultant Limited 35,000.00 0.00 Canceled improved access to 31 05 26 31 27 réalisation du PAR du CDC Selection markets de Bondoukou (Gontougo) CI-FIRCA-74806-CS-INDV / Recrutement d'un 3. Support to private Individual consultant pour investment in post-harvest 2019-02- 2019-03- 2019-04- 2019-05- 2019-11- IBRD / 88450 Post Consultant Open 20,000.00 0.00 Canceled l'élaboration du manuel and processing 04 25 15 20 16 Selection d'exportateurs pour le infrastructure secteur du cajou (noix brutes, amandes, etc.) CI-FIRCA-82315-CS-INDV 3. Support to private / Recrutement d'un Individual investment in post-harvest 2018-11- 2018-12- 2018-12- 2019-01- 2019-07- consultant individuel pour IBRD / 88450 Post Consultant Limited 50,000.00 0.00 Canceled and processing 26 01 22 26 25 l'élaboration de PAR sur 100 Selection infrastructure km à Bondoukou CI-FIRCA-106880-CS- 2. Productivity INDV / Sélection d'un Individual enhancement and 2019-05- 2019-05- 2019-06- 2019-07- 2020-01- consultant individuel pour IBRD / 88450 Post Consultant Limited 35,000.00 0.00 Canceled improved access to 15 20 10 15 11 la réalisation du PAR du Selection markets CDC de Toumbokro CI-FIRCA-82268-CS-INDV / Recrutement de 4. Program coordination, Individual 2018-10- 2018-11- 2018-11- 2018-12- 2019-06- consultants individuels pour IBRD / 88450 monitoring and knowledge Post Consultant Limited 200,000.00 0.00 Canceled 30 04 25 30 28 les mesures de sauvegarde management Selection environnementales et sociales CI-FIRCA-82317-CS-INDV / Recrutement de deux 3. Support to private Individual consultants individuels pour investment in post-harvest 2018-11- 2019-01- 2019-02- 2019-03- 2019-09- IBRD / 88450 Post Consultant Open 100,000.00 0.00 Canceled l'appui à l'amélioration des and processing 27 15 05 12 08 Selection bonnes pratiques de infrastructure fabrication CI-FIRCA-106455-CS- 3. Support to private INDV / Sélection d'un Individual investment in post-harvest 2019-04- 2019-05- 2019-05- 2019-06- 2019-12- consultant individuel pour IBRD / 88450 Post Consultant Limited 47,000.00 0.00 Canceled and processing 30 05 26 30 27 le Screening Selection infrastructure environnemental des entrepôts CI-FIRCA-106456-CS- 3. Support to private Individual INDV / Sélection de investment in post-harvest 2019-04- 2019-05- 2019-05- 2019-06- 2019-12- IBRD / 88450 Post Consultant Limited 46,000.00 0.00 Canceled consultants pour réaliser and processing 30 05 26 30 27 Selection l'évaluation sociale des infrastructure entrepôts CI-FIRCA-74762-CS-INDV / Recrutement de 4. Program coordination, Individual consultants pour 2018-10- 2018-10- 2018-11- 2018-12- 2019-06- IBRD / 88450 monitoring and knowledge Post Consultant Limited 50,000.00 0.00 Canceled l'élaboration des termes de 18 23 13 18 16 management Selection référence des activités/spécifications techniques des fournitures CI-FIRCA-74848-CS-INDV / Recrutement de consultants individuels pour 2. Productivity la mission d'études sociales Individual enhancement and 2018-10- 2018-12- 2018-12- 2019-01- 2019-07- en vue de l'élaboration d'un IBRD / 88450 Post Consultant Open 96,000.00 0.00 Canceled improved access to 18 06 27 31 30 PAR concernant le second Selection markets programme de réhabilitation de par RC et RLTPC 250KM en route rurale CI-FIRCA-82232-CS-INDV 4. Program coordination, Individual 2018-10- 2018-12- 2018-12- 2019-02- 2019-08- / Recrutement d'un auditeur IBRD / 88450 monitoring and knowledge Post Consultant Open 84,000.00 0.00 Canceled 22 10 31 04 03 interne management Selection CI-FIRCA-106464-CS- INDV / Sélection d'un 4. Program coordination, Individual 2019-12- 2020-02- 2020-02- 2020-03- 2020-09- consultant individuel pour IBRD / 88450 monitoring and knowledge Post Consultant Open 38,000.00 0.00 Canceled 15 02 23 29 25 l'élaboration d'un guide de management Selection bonne pratique sanitaire et d'hygiène CI-FIRCA-106444-CS- 3. Support to private INDV / Recruter un Individual investment in post-harvest 2019-03- 2019-05- 2019-05- 2019-06- 2019-12- consultant pour la IBRD / 88450 Post Consultant Open 19,000.00 0.00 Canceled and processing 15 03 24 28 25 réalisation du PAR de la Selection infrastructure zone agro-industrielle de Bouaké CI-FIRCA-74774-CS-INDV 4. Program coordination, Individual / Recrutement de 2 2018-10- 2018-10- 2018-11- 2018-12- 2019-06- IBRD / 88450 monitoring and knowledge Post Consultant Limited 200,000.00 0.00 Canceled consultants pour la 11 16 06 11 09 management Selection promotion des investissements industriels Page 11 CI-FIRCA-82312-CS-INDV 3. Support to private / Recrutement de deux Individual investment in post-harvest 2018-10- 2018-12- 2019-01- 2019-02- 2019-08- consultants individuels pour IBRD / 88450 Post Consultant Open 100,000.00 0.00 Canceled and processing 30 18 08 12 11 l'appui à l'installation des Selection infrastructure unités industrielles CI-FIRCA-106894-CS- 2. Productivity Individual INDV / Sélection d'un enhancement and 2019-05- 2019-05- 2019-06- 2019-07- 2020-01- IBRD / 88450 Post Consultant Limited 35,000.00 0.00 Canceled consultant individuel pour improved access to 15 20 10 15 11 Selection la réalisation d'un PAR du markets CDC de Koro CI-FIRCA-74837-CS-INDV 3. Support to private / Recrutement de Individual investment in post-harvest 2018-10- 2018-12- 2018-12- 2019-01- 2019-07- consultants pour la mise en IBRD / 88450 Post Consultant Open 100,000.00 0.00 Canceled and processing 18 06 27 31 30 œuvre des activités de Selection infrastructure réhabilitation et de construction des entrepôts CI-FIRCA-82314-CS-INDV 3. Support to private / Recrutement d'un Individual investment in post-harvest 2018-11- 2019-01- 2019-01- 2019-02- 2019-08- consultant individuel pour IBRD / 88450 Post Consultant Open 30,000.00 0.00 Canceled and processing 15 03 24 28 27 l'élaboration de PAR sur 60 Selection infrastructure km à Bondoukou CI-FIRCA-106154-CS-CDS / Sélection par entente 1. Institutional directe du cabinet COOP 2019-03- 2019-04- 2019-06- 2019-12- IBRD / 88450 strengthening and value Post Direct Selection Direct 56,000.00 0.00 Canceled France pour former les 22 01 05 02 chain governance acteurs sur les modules de gouvernance des sociétés CI-FIRCA-74828-CS-CDS / Recrutement d'un 4. Program coordination, 2019-02- 2019-02- 2019-02- 2019-02- consultant pour l'extension IBRD / 88450 monitoring and knowledge Post Direct Selection Direct - National 75,000.00 0.00 Canceled 21 21 21 21 du système informatisé de management suivi-évaluation. CI-FIRCA-106588-CS-CDS / Convention avec l'AFOR 2. Productivity pour le processus de enhancement and 2019-07- 2019-07- 2019-09- 2020-03- IBRD / 88450 Post Direct Selection Direct 75,000.00 0.00 Canceled délivrance des certificats improved access to 15 25 28 26 fonciers sur les parcelles du markets PAVA (pour les villes ) CI-FIRCA-107773-CS-CDS 4. Program coordination, / Convention avec l'ANDE 2019-04- 2019-04- 2019-06- 2019-12- IBRD / 88450 monitoring and knowledge Post Direct Selection Direct 150,000.00 0.00 Canceled pour la validation des 15 25 29 26 management quatre études environnementales CI-FIRCA-106463-CS-CDS / Convention avec DPVCQ 4. Program coordination, pour développer une base 2019-06- 2019-07- 2019-09- 2020-03- IBRD / 88450 monitoring and knowledge Post Direct Selection Direct 10,000.00 0.00 Canceled de données avec des 30 10 13 11 management formats adéquats en collaboration avec La DPVQ CI-FIRCA-157277-CS- 2. Productivity Individual INDV / Recrutement de enhancement and 2020-05- 2020-06- 2020-07- 2020-08- 2020-08- 2020-08- 2020-09- 2020-08- 2021-03- 2020-12- IBRD / 88450 Post Consultant Open 74,000.00 41,942.90 Completed consultants pour réaliser le improved access to 31 15 19 13 09 20 13 28 12 28 Selection suivi des activités du PNRA markets CI-FIRCA-157283-CS-CDS / Recrutement d'un 2. Productivity consultant pour la enhancement and Pending 2020-03- 2020-04- 2020-06- 2020-12- IBRD / 88450 Post Direct Selection Direct 250,000.00 0.00 réalisation des études socio- improved access to Implementation 31 10 14 11 économiques des markets innovations et autres activités de la Filière Anacarde CI-FIRCA-157300-CS- INDV / Recrutement d'un 2. Productivity Individual consultant pour le enhancement and Pending 2020-02- 2020-02- 2020-03- 2020-04- 2020-10- IBRD / 88450 Post Consultant Direct 19,000.00 0.00 renforcement des capacités improved access to Implementation 12 22 14 18 15 Selection des chercheurs et des markets autres acteurs de la Filière en hybridation CI-FIRCA-157330-CS-CDS / Sélection par entente 2. Productivity directe d'un cabinet pour la enhancement and Under 2020-05- 2020-06- 2020-06- 2020-08- 2021-02- poursuite de l'appui à la IBRD / 88450 Post Direct Selection Direct 75,000.00 0.00 improved access to Implementation 31 30 10 14 10 mise en oeuvre du markets programme des Opérateurs Professionnels du Cajou (OPCA) CI-FIRCA-157339-CS-CDS 2. Productivity / Convention avec l'ANADER enhancement and Pending 2020-02- 2020-03- 2020-05- 2020-11- IBRD / 88450 Prior Direct Selection Direct 1,993,000.00 0.00 pour le Conseil Agricole improved access to Implementation 28 09 13 09 dédié à l'anacarde markets CI-FIRCA-157341-CS-CDS 2. Productivity / Convention avec l'ANADER enhancement and 2020-02- 2020-04- 2020-03- 2020-06- 2020-05- 2020-09- 2020-11- IBRD / 88450 Post Direct Selection Direct 271,000.00 296,080.22 Signed pour la mise en œuvre de la improved access to 20 17 01 23 05 21 01 E-extension markets CI-FIRCA-157344-CS- INDV / Recrutement de 2. Productivity consultants pour la Individual enhancement and Pending 2020-03- 2020-05- 2020-06- 2020-07- 2021-01- réalisation de deux (2) IBRD / 88450 Post Consultant Open 94,000.00 0.00 improved access to Implementation 31 19 09 14 10 missions de suivi et Selection markets d'évaluation interne des activités du Conseil Agricole dédié à l'Anacarde (CAA) 2019 CI-FIRCA-157343-CS- INDV / Recrutement de 2. Productivity consultants pour la Individual enhancement and 2020-02- 2020-03- 2020-02- 2020-05- 2020-03- 2020-06- 2020-04- 2020-07- 2020-10- formation des pépiniéristes IBRD / 88450 Post Consultant Limited 19,000.00 10,811.56 Signed improved access to 19 30 24 15 16 12 20 03 17 et greffeurs sur les Selection markets bioagresseurs, les méthodes de lutte et de sécurité sanitaire CI-FIRCA-157345-CS-CDS / Sélection par Entente Directe de la DR NORD 2. Productivity ANADER pour le suivi, le enhancement and 2020-03- 2020-04- 2020-03- 2020-05- 2020-05- 2020-09- 2020-11- IBRD / 88450 Post Direct Selection Direct 93,000.00 115,176.67 Signed contrôle et la validation des improved access to 16 23 26 19 30 18 26 travaux de réhabilitation markets des vergers d'anacardiers à réaliser par les OPCA CI-FIRCA-157346-CS-CDS / Recrutement d'un cabinet 2. Productivity pour la formation des enhancement and 2020-03- 2020-08- 2020-04- 2020-07- 2020-06- 2020-12- 2020-12- IBRD / 88450 Post Direct Selection Direct 28,000.00 63,314.92 Signed applicateurs des OPCA à la improved access to 31 02 10 09 14 11 11 maitrise de la manipulation markets et l'utilisation des produits phytosanitaires CI-FIRCA-157352-CS-CDS / Sélection par Entente Directe de la DR CENTRE 2. Productivity ANADER pour le suivi, le enhancement and 2020-03- 2020-04- 2020-03- 2020-05- 2020-05- 2020-09- 2020-11- IBRD / 88450 Post Direct Selection Direct 77,000.00 85,361.81 Signed contrôle et la validation des improved access to 16 23 26 25 30 18 26 travaux de réhabilitation markets des vergers d'anacardiers à réaliser par les OPCA CI-FIRCA-157358-CS-CDS / Sélection par Entente Directe de la DR Centre-Est 2. Productivity ANADER pour le suivi, le enhancement and 2020-03- 2020-04- 2020-03- 2020-05- 2020-05- 2020-09- 2020-11- IBRD / 88450 Post Direct Selection Direct 48,000.00 59,987.85 Signed contrôle et la validation des improved access to 16 23 26 19 30 18 26 travaux de réhabilitation markets des vergers d'anacardiers à réaliser par les OPCA CI-FIRCA-157360-CS-CDS / Sélection par Entente Directe de la DR Centre- 2. Productivity Ouest ANADER pour le suivi, enhancement and 2020-03- 2020-04- 2020-03- 2020-05- 2020-05- 2020-09- 2020-11- IBRD / 88450 Post Direct Selection Direct 36,000.00 44,600.00 Signed le contrôle et la validation improved access to 16 23 26 19 30 18 26 des travaux de markets réhabilitation des vergers d'anacardiers à réaliser par les OPCA CI-FIRCA-157363-CS-CDS / Sélection par Entente Directe de la DR OUEST 2. Productivity ANADER pour le suivi, le enhancement and 2020-03- 2020-04- 2020-03- 2020-05- 2020-05- 2020-09- 2020-11- IBRD / 88450 Post Direct Selection Direct 19,000.00 24,045.58 Signed contrôle et la validation des improved access to 16 23 26 25 30 18 26 travaux de réhabilitation markets des vergers d'anacardiers à réaliser par les OPCA CI-FIRCA-157367-CS-CDS / Sélection par Entente 2. Productivity Directe de la SODEXAM pour enhancement and Under 2020-02- 2020-05- 2020-03- 2020-05- 2020-11- apporter un appui à la mise IBRD / 88450 Post Direct Selection Direct 151,000.00 0.00 improved access to Implementation 29 20 10 14 10 en œuvre des activités de markets résilience des producteurs d'anacarde au changement climatique CI-FIRCA-157372-CS- 2. Productivity INDV / Recrutement d'un Individual enhancement and Pending 2020-02- 2020-04- 2020-04- 2020-06- 2020-11- consultant pour le suivi et le IBRD / 88450 Post Consultant Open 6,000.00 0.00 improved access to Implementation 17 06 27 01 28 contrôle des travaux Selection markets d'aménagement du laboratoire de pédologie CI-FIRCA-157374-CS- INDV / Recruter cinq consultants individuels pour preparation de Plans 2. Productivity d’Action de Reinstallation Individual enhancement and 2020-02- 2020-03- 2020-04- 2020-06- 2020-05- 2020-06- 2020-06- 2020-07- 2020-12- (PAR) relatifs aux travaux de IBRD / 88450 Post Consultant Open 139,000.00 136,894.66 Signed improved access to 25 09 14 03 05 15 09 03 06 Rehabilitation en reprofilage Selection markets Lourd avec Traitement de Points Critiques (RLTPC) de 349 km de routes rurales dans les regions du Gonto CI-FIRCA-157546-CS- 3. Support to private INDV / Recrutement d'un Individual investment in post-harvest Under 2020-03- 2020-03- 2020-04- 2020-05- 2020-06- 2020-12- consultant individuel pour IBRD / 88450 Post Consultant Open 4,000.00 0.00 and processing Implementation 05 30 23 14 18 15 l'accompagnement social Selection infrastructure des PAPs de la ZAI de Bondoukou CI-FIRCA-157571-CS-CDS 3. Support to private / Sélection d'un consultant investment in post-harvest 2020-04- 2020-05- 2020-05- 2020-05- 2020-07- 2020-06- 2021-01- par entente directe pour IBRD / 88450 Post Direct Selection Direct 75,000.00 53,239.65 Signed and processing 28 11 08 14 12 15 08 l'assistance à la promotion infrastructure des investissements CI-FIRCA-157573-CS- 4. Program coordination, Individual INDV / Recruter un 2020-02- 2020-01- 2020-04- 2020-03- 2020-04- 2020-04- 2020-06- 2020-04- 2020-12- IBRD / 88450 monitoring and knowledge Post Consultant Open 78,000.00 47,151.05 Signed consultant individuel en 20 06 09 24 30 08 04 30 01 management Selection mesure de Sauvegarde Environnementale CI-FIRCA-157582-CS-CDS / Recrutement de 4. Program coordination, 2020-03- 2020-03- 2020-04- 2020-04- 2020-06- 2020-05- 2020-12- Consultant pour IBRD / 88450 monitoring and knowledge Post Direct Selection Direct 56,000.00 55,016.70 Signed 31 31 10 21 14 04 11 l'élaboration de la stratégie management de communication du PPCA CI-FIRCA-157931-CS-CDS 3. Support to private / Sélection par entente investment in post-harvest Under 2020-03- 2020-08- 2020-03- 2020-10- 2020-05- 2020-11- directe d'une firme pour IBRD / 88450 Post Direct Selection Direct 38,000.00 38,849.78 and processing Implementation 02 26 12 21 16 12 actualiser les modèles infrastructure économiques de la transformation de l'anacarde CI-FIRCA-157932-CS-CDS / Convention avec l'IECD 1. Institutional pour la mise en œuvre Under 2020-02- 2020-10- 2020-03- 2020-05- 2020-11- IBRD / 88450 strengthening and value Post Direct Selection Direct 466,000.00 0.00 d'un centre d'incubation Implementation 26 26 07 11 07 chain governance pour le développement de produits dérivés de l'anacarde CI-FIRCA-158118-CS-CDS / Sélection de l'ESA pour 1. Institutional appuyer l'élaboration et le Under 2020-03- 2020-09- 2020-03- 2020-10- 2020-05- 2020-11- IBRD / 88450 strengthening and value Post Direct Selection Direct 372,000.00 0.00 suivi de la mise en œuvre Implementation 02 04 12 21 16 12 chain governance des plans de développement des sociétés coopératives CI-FIRCA-106483-CS- 4. Program coordination, Individual INDV / Sélection d'un 2020-03- 2020-03- 2020-04- 2020-05- 2020-11- IBRD / 88450 monitoring and knowledge Post Consultant Limited 10,000.00 0.00 Canceled consultant pour le Plan 20 25 15 20 16 management Selection d'amélioration des performances CI-FIRCA-158217-CS- INDV / Recrutement d'un consultant individuel pour 1. Institutional Individual 2020-03- 2021-06- 2020-05- 2020-05- 2020-06- 2020-12- l'élaboration de la IBRD / 88450 strengthening and value Post Consultant Open 47,000.00 0.00 Under Review 16 21 04 25 29 26 procédure de traitement chain governance Selection phytosanitaire des noix de cajou et d'agrément des applicateurs CI-FIRCA-158938-CS- INDV / Recrutement d'un consultant individuel pour 3. Support to private Individual la modélisation en 3 investment in post-harvest 2020-02- 2020-03- 2020-03- 2020-07- 2020-03- 2020-09- 2020-04- 2020-09- 2020-10- 2020-12- IBRD / 88450 Post Consultant Limited 19,000.00 18,641.11 Completed Dimensions et la réalisation and processing 28 09 04 30 25 09 29 24 26 02 Selection d'une vidéo de synthèse infrastructure (film d'animation) de la plateforme agro industrielle de Korhogo CI-FIRCA-126727-CS- 2. Productivity INDV / Recruter 2 Individual enhancement and Under 2020-03- 2020-11- 2020-04- 2020-04- 2020-05- 2020-11- consultants pour apporter IBRD / 88450 Post Consultant Limited 19,000.00 0.00 improved access to Implementation 31 04 05 26 31 27 un appui à la relecture du Selection markets document du PNRA CI-FIRCA-106560-CS- INDV / Recrutement d'un 1. Institutional Individual Assistant Spécialiste en Pending 2020-05- 2020-06- 2020-07- 2020-08- 2021-02- IBRD / 88450 strengthening and value Post Consultant Open 22,000.00 0.00 Social pour l'appui à la mise Implementation 01 19 10 14 10 chain governance Selection en œuvre des mesures de sauvegarde sociales. CI-FIRCA-106454-CS- INDV / Sélection d'un 3. Support to private Individual consultant individuel pour investment in post-harvest 2019-05- 2019-06- 2019-06- 2019-07- 2020-01- IBRD / 88450 Post Consultant Limited 56,000.00 0.00 Canceled concevoir des supports de and processing 30 04 25 30 26 Selection communication sur les infrastructure mécanismes de financement à coûts partagés CI-FIRCA-126729-CS- 2. Productivity Individual INDV / Sélection d’un enhancement and 2019-10- 2019-11- 2019-11- 2019-12- 2020-06- IBRD / 88450 Post Consultant Limited 38,000.00 0.00 Canceled consultant individuel pour improved access to 30 04 25 30 27 Selection Réaliser les PAR des sites du markets PAVA CI-FIRCA-106607-CS- 2. Productivity INDV / Sélection d'un Individual enhancement and 2019-04- 2019-04- 2019-05- 2019-06- 2019-12- consultant pour la IBRD / 88450 Post Consultant Limited 35,000.00 0.00 Canceled improved access to 15 20 11 15 12 réalisation du PAR d'un Selection markets CDC de BOUNA (Bounkani). CI-FIRCA-106873-CS- 2. Productivity Individual INDV / Sélection d'un enhancement and 2019-03- 2019-04- 2019-04- 2019-05- 2019-11- IBRD / 88450 Post Consultant Limited 35,000.00 0.00 Canceled consultant pour la improved access to 31 05 26 31 27 Selection réalisation du PAR du CDC markets de Dabakala (Hambol) CI-FIRCA-106892-CS- 2. Productivity Individual INDV / Sélection d'un enhancement and 2019-05- 2019-05- 2019-06- 2019-07- 2020-01- IBRD / 88450 Post Consultant Limited 35,000.00 0.00 Canceled consultant individuel pour improved access to 15 20 10 15 11 Selection la réalisation du PAR du markets CDC de Wongué CI-FIRCA-126691-CS- 1. Institutional Individual INDV / Recrutement d'un 2019-09- 2019-09- 2019-10- 2019-11- 2020-05- IBRD / 88450 strengthening and value Post Consultant Limited 30,000.00 0.00 Canceled consultant pour 16 21 12 16 14 chain governance Selection l'actualisation du CGES CI-FIRCA-126697-CS-CDS / Recrutement d’un 3. Support to private Consultant pour l’étude investment in post-harvest 2019-09- 2019-10- 2019-12- 2020-06- IBRD / 88450 Post Direct Selection Direct 94,000.00 0.00 Canceled technique de centres de and processing 30 10 14 11 valorisation des sous- infrastructure produits Anacarde en lien avec les ZAI CI-FIRCA-106867-CS-CDS 2. Productivity / Convention avec les OPCA enhancement and 2019-04- 2019-05- 2019-07- 2020-01- pour l'acquisition des IBRD / 88450 Post Direct Selection Direct 466,000.00 0.00 Canceled improved access to 30 10 14 10 équipements techniques markets d'installation des OPCA CI-FIRCA-106667-CS- 2. Productivity INDV / Sélection de Individual enhancement and 2019-06- 2019-07- 2019-07- 2019-08- 2020-02- consultant s individuels IBRD / 88450 Post Consultant Limited 187,000.00 0.00 Canceled improved access to 28 03 24 28 24 pour réaliser les études des Selection markets PAR des 448 Km à réhabiliter et à construire . Page 12 CI-FIRCA-126728-CS-CDS 2. Productivity / Recrutement d’un enhancement and Pending 2019-09- 2019-09- 2019-11- 2020-05- consultant pour réaliser une IBRD / 88450 Post Direct Selection Direct 47,000.00 0.00 improved access to Implementation 15 25 29 27 mission d'audit technique markets des stations agro-météo installées CI-FIRCA-157305-CS-CDS / Sélection par entente directe de firmes pour la 2. Productivity réalisation des activités enhancement and Pending 2020-02- 2020-02- 2020-04- 2020-10- IBRD / 88450 Post Direct Selection Direct 94,000.00 0.00 d'obtention des Certificats improved access to Implementation 12 22 27 24 Fonciers (CF) au profit des markets propriétaires coutumiers des CDC en création et des sites du PAVA CI-FIRCA-157249-CS-CDS / Sélection par entente d'un 2. Productivity consultant pour réaliser les enhancement and 2020-05- 2020-06- 2020-06- 2020-07- 2020-08- 2020-06- 2021-02- activités de la Coordination IBRD / 88450 Post Direct Selection Direct 64,000.00 35,576.45 Signed improved access to 31 30 10 13 14 05 10 Scientifique (CS) du PNRA markets (prestations,fonctionnement et missions) CI-FIRCA-126661-CS-CDS / Entente directe avec l'association Technologies & 1. Institutional Pending 2020-06- 2020-06- 2020-08- 2021-02- Solidarité de France pour IBRD / 88450 strengthening and value Post Direct Selection Direct 56,000.00 0.00 Implementation 10 20 24 20 l'organisation de missions chain governance d'appui aux sociétés coopératives CI-FIRCA-167249-CS-CDS / Entente directe avec KPMG 1. Institutional 2020-04- 2020-05- 2020-04- 2020-04- 2020-06- 2020-06- 2020-12- pour l’opérationnalisation IBRD / 88450 strengthening and value Post Direct Selection Direct 250,000.00 243,633.15 Signed 08 25 18 14 22 18 19 de la fonction d’audit au chain governance sein du CCA CI-FIRCA-167375-CS- INDV / RECRUTEMENT D'UN 1. Institutional Individual INFORMATICIEN POUR LE 2020-04- 2020-04- 2020-04- 2020-04- 2020-05- 2020-04- 2020-06- 2020-04- 2020-12- IBRD / 88450 strengthening and value Post Consultant Limited 32,000.00 23,839.97 Signed RENFORCEMENT DES 08 07 13 16 04 28 08 30 05 chain governance Selection CAPACITES DE LA DSIPE A L'ANNEXE 2 DU CCA CI-FIRCA-180001-CS- INDV / SELECTION D'UN CONSULTANT INDIVIDUEL 1. Institutional Individual 2020-06- 2020-10- 2020-08- 2020-08- 2020-10- 2021-04- POUR L'ACCOMPAGNEMENT IBRD / 88450 strengthening and value Post Consultant Open 13,000.00 0.00 Canceled 22 07 10 31 05 03 DU CITA POUR LA MISE EN chain governance Selection PLACE DE LA MATRICE DES PRIX CI-FIRCA-180135-CS- 4. Program coordination, Individual INDV / RECRUTEMENT DE Under 2020-06- 2020-08- 2020-07- 2020-08- 2020-11- 2020-10- 2021-03- IBRD / 88450 monitoring and knowledge Prior Consultant Open 92,000.00 0.00 DEUX SPECIALISTES EN Implementation 19 07 03 28 19 02 31 management Selection PASSATION DE MARCHES POUR LE PPCA CI-FIRCA-180147-CS-CDS 2. Productivity / Recrutement de huit enhancement and Pending 2020-06- 2020-06- 2020-09- 2021-03- pépiniéristes expérimentés IBRD / 88450 Post Direct Selection Direct 8,000.00 0.00 improved access to Implementation 19 29 02 01 pour la formation des OPCA markets aux techniques de greffage CI-FIRCA-180150-CS- 2. Productivity INDV / RÉALISATION D'UN Individual enhancement and 2020-06- 2021-02- 2020-06- 2019-10- 2020-07- 2019-10- 2020-08- 2019-12- 2021-02- PLAN D'ACTION DE IBRD / 88450 Post Consultant Limited 35,000.00 39,231.76 Signed improved access to 19 25 24 11 15 28 19 13 15 RÉINSTALLATION (PAR) DE Selection markets SANANKORO CI-FIRCA-167384-CS- INDV / RECRUTEMENT D'UN ASSISTANT SPECIALISTE EN 1. Institutional Individual SAUVEGARDE Under 2020-06- 2020-06- 2020-06- 2020-07- 2020-08- 2021-02- IBRD / 88450 strengthening and value Post Consultant Limited 23,000.00 0.00 ENVIRONNEMENTALE POUR Implementation 24 17 29 20 24 20 chain governance Selection L'APPUI A LA MISE EN OEUVRE DES MESURES DE SAUVEGARDE ENVIRONNEMENTALE CI-FIRCA-180143-CS- INDV / RECRUTEMENT D'UN 4. Program coordination, Individual Pending 2020-06- 2020-08- 2020-08- 2020-10- 2021-03- RESPONSABLE COMPTABLE IBRD / 88450 monitoring and knowledge Post Consultant Open 75,000.00 0.00 Implementation 19 07 28 02 31 ET FINANCIER (RCF) POUR LE management Selection PPCA CI-FIRCA-180146-CS- 4. Program coordination, Individual Pending 2020-06- 2020-08- 2020-08- 2020-10- 2021-03- INDV / RECRUTEMENT DE IBRD / 88450 monitoring and knowledge Post Consultant Open 64,000.00 0.00 Implementation 19 07 28 02 31 DEUX COMPTABLES POUR LE management Selection PPCA CI-FIRCA-157262-CS- 2. Productivity Individual INDV / Recrutement d'un enhancement and 2020-03- 2020-04- 2020-04- 2020-05- 2020-11- IBRD / 88450 Post Consultant Limited 6,000.00 0.00 Canceled consultant pour la improved access to 31 05 26 31 27 Selection modération de l'atelier de markets relecture du PNRA CI-FIRCA-157369-CS- INDV / Recrutement d'un 2. Productivity consultant pour la Individual enhancement and 2020-11- 2020-09- 2020-11- 2020-10- 2020-12- 2020-11- 2021-01- 2020-11- 2021-07- formation des pépiniéristes IBRD / 88450 Post Consultant Limited 19,000.00 9,529.81 Signed improved access to 05 29 10 27 01 25 05 30 04 de la Filière Anacarde sur Selection markets les techniques de production des plants forestiers CI-FIRCA-126722-CS-CDS / Recrutement d’un 1. Institutional Individual 2020-03- 2020-03- 2020-03- 2020-05- 2020-10- consultant individuel pour IBRD / 88450 strengthening and value Post Consultant Limited 25,000.00 0.00 Canceled 02 07 28 02 29 l’étude portant sur la mise chain governance Selection en place d’un laboratoire central au CITA CI-FIRCA-157555-CS- INDV / Recrutement d'un 3. Support to private Individual consultant pour investment in post-harvest 2020-02- 2020-04- 2020-05- 2020-06- 2020-12- IBRD / 88450 Post Consultant Open 38,000.00 0.00 Canceled l'élaboration de la stratégie and processing 28 17 08 12 09 Selection nationale sur la plateforme infrastructure des équipementiers CI-FIRCA-201740-CS- INDV / Recruter un consultant individuel agréé par le Ministère en charge 1. Institutional Individual Pending 2020-11- 2020-11- 2020-12- 2021-01- 2021-07- de l'Environnement pour IBRD / 88450 strengthening and value Post Consultant Limited 12,000.00 0.00 Implementation 10 15 06 10 09 réaliser le Plan de Gestion chain governance Selection Environnementale - Audit (PGE-Audit) du CITA (audit réglementaire) CI-FIRCA-201801-CS-CDS / Recrutement de cinq consultants individuels pour la préparation de Plans 2. Productivity d'Action de Réinstallation Individual enhancement and 2020-11- 2021-02- 2021-01- 2021-01- 2021-02- 2021-08- (PAR) relatifs aux travaux de IBRD / 88450 Post Consultant Open 181,000.00 0.00 Under Review improved access to 15 09 03 24 28 27 Rehabilitation en reprofilage Selection markets Lourd avec Traitement de Points Critiques (RLTPC) de 370,5 km de routes rurales dans la régi CI-FIRCA-158220-CS- INDV / Recrutement d'un consultant individuel pour 1. Institutional Individual 2020-03- 2020-05- 2020-05- 2020-07- 2020-12- la mise en place des IBRD / 88450 strengthening and value Post Consultant Open 8,000.00 0.00 Canceled 20 08 29 03 30 plateformes de travail chain governance Selection collaboratif (gestion de courrier, espace collaboratif, archivage, médiathèque...) CI-FIRCA-158222-CS- INDV / Recrutement d'un 1. Institutional Individual consultant individuel pour 2020-04- 2020-05- 2020-06- 2020-07- 2021-01- IBRD / 88450 strengthening and value Post Consultant Open 19,000.00 0.00 Canceled l'élaboration d'un plan de 10 29 19 24 20 chain governance Selection formation des agents du Conseil du Coton et de l'Anacarde CI-FIRCA-201960-CS- INDV / Recruter un 1. Institutional Individual Pending 2020-11- 2020-11- 2020-11- 2021-01- 2021-07- consultant pour l'étude de IBRD / 88450 strengthening and value Post Consultant Limited 30,000.00 0.00 Implementation 02 07 28 02 01 dimensionnement d'une chain governance Selection unité de pirolyse au CITA CI-FIRCA-74834-CS-CQS / Recrutement de 1. Institutional Individual consultants pour la Pending 2020-11- 2021-01- 2021-02- 2021-03- 2021-09- IBRD / 88450 strengthening and value Post Consultant Open 50,000.00 0.00 formation de 100 Implementation 30 18 08 15 11 chain governance Selection techniciens des unités de transformation de noix de cajou CI-FIRCA-82297-CS-INDV / Recrutement d'un juriste pour l'élaboration et la 1. Institutional Individual 2020-11- 2020-11- 2020-12- 2021-01- 2021-07- finalisation des textes pour IBRD / 88450 strengthening and value Post Consultant Limited 25,000.00 0.00 Under Review 16 21 12 16 15 la constitution des collèges chain governance Selection des acheteurs, exportateurs et transformateurs CI-FIRCA-82587-CS-INDV 3. Support to private / Recrutement d'un Individual investment in post-harvest 2020-03- 2020-03- 2020-04- 2020-05- 2020-11- consultant individuel pour IBRD / 88450 Post Consultant Limited 30,000.00 0.00 Canceled and processing 19 24 14 19 15 la réalisation des études Selection infrastructure pour l'interconnexion des sites CI-FIRCA-157304-CS-CDS 2. Productivity / Recrutement d'une Individual enhancement and Pending 2020-12- 2020-12- 2020-12- 2021-01- 2021-07- structure spécialisée en IBRD / 88450 Post Consultant Limited 10,000.00 0.00 improved access to Implementation 01 06 27 31 30 organisation d'un e-forum Selection markets pour le CIESA 2020 CI-FIRCA-157331-CS- 2. Productivity INDV / Recrutement d'un Individual enhancement and 2020-11- 2020-12- 2020-12- 2021-01- 2021-07- consultant pour la IBRD / 88450 Post Consultant Limited 10,000.00 0.00 Canceled improved access to 30 05 26 30 29 modération des travaux de Selection markets l'atelier bilan des activités des pépiniéristes CI-FIRCA-157342-CS- INDV / Recrutement d'un 2. Productivity Individual consultant pour la enhancement and 2020-04- 2020-06- 2020-05- 2020-05- 2020-06- 2020-12- IBRD / 88450 Post Consultant Limited 10,000.00 0.00 Canceled modération des travaux de improved access to 30 15 05 26 30 27 Selection la revue semestrielle des markets activités du conseil agricole dédié CI-FIRCA-157355-CS- INDV / Recrutement d'un 2. Productivity Individual consultant pour la enhancement and 2020-09- 2020-10- 2020-10- 2020-11- 2021-05- IBRD / 88450 Post Consultant Limited 10,000.00 0.00 Canceled modération des travaux de improved access to 30 05 26 30 29 Selection l'atelier bilan de mise en markets œuvre du programme OPCA CI-FIRCA-157336-CS- 2. Productivity INDV / Recrutement d'un Individual enhancement and 2020-11- 2020-12- 2021-01- 2021-02- 2021-08- consultant pour la IBRD / 88450 Post Consultant Open 24,000.00 0.00 Canceled improved access to 02 21 11 15 14 formation du personnel Selection markets technique des 3 CDC CI-FIRCA-201989-CS- INDV / Recrutement d'un 2. Productivity consultant en appui à Individual enhancement and Under 2020-11- 2020-11- 2020-11- 2020-12- 2021-01- 2021-07- l'organisation de l'atelier IBRD / 88450 Post Consultant Limited 4,000.00 0.00 improved access to Implementation 10 20 15 06 10 09 bilan des activités du Selection markets conseil agricole, de la réhabilitation et distribution des plants greffés CI-FIRCA-126732-CS- INDV / Recrutement de trois 2. Productivity Individual (3) techniciens pour le suivi enhancement and 2019-08- 2019-09- 2019-09- 2019-10- 2020-04- IBRD / 88450 Post Consultant Limited 30,000.00 0.00 Canceled des essais de recherche sur improved access to 30 05 26 31 28 Selection les sites de Badikaha, markets Koflandé et de KORO Sanankoro CI-FIRCA-157548-CS- 3. Support to private INDV / Recrutement d'un Individual investment in post-harvest 2020-12- 2021-02- 2021-03- 2021-04- 2021-10- consultant individuel pour IBRD / 88450 Post Consultant Open 4,000.00 0.00 Canceled and processing 23 10 03 07 04 l'accompagnement social Selection infrastructure des PAPs de la ZAI de Séguéla CI-FIRCA-157559-CS- INDV / Recrutement d'un 3. Support to private consultant pour Individual investment in post-harvest 2020-03- 2020-05- 2020-06- 2020-07- 2021-01- l'élaboration des documents IBRD / 88450 Post Consultant Open 30,000.00 0.00 Canceled and processing 29 17 07 12 08 relatifs aux plateformes de Selection infrastructure services de la filière anacarde en Côte d’Ivoire CI-FIRCA-158119-CS-CDS / entente directe avec 3. Support to private l'ADCI pour l'évaluation des investment in post-harvest 2020-03- 2020-03- 2020-05- 2020-11- IBRD / 88450 Post Direct Selection Direct 432,000.00 0.00 Canceled capacités techniques et and processing 02 12 16 12 financieres des entreprises infrastructure de transformation de cajou CI-FIRCA-74794-CS-CDS / 3. Support to private 2020-03- 2020-04- 2020-06- 2020-12- Convention avec le BNETD IBRD / 88450 investment in post-harvest Post Direct Selection Direct 200,000.00 0.00 Canceled 30 09 13 10 dans le cadre de l'AMO and processing infrastructure CI-FIRCA-157577-CS- INDV / Recrutement d'un 4. Program coordination, Individual consultant assistant pour 2020-02- 2020-04- 2020-05- 2020-06- 2020-12- IBRD / 88450 monitoring and knowledge Post Consultant Open 16,000.00 0.00 Canceled assurer le suivi des activités 28 17 08 12 09 management Selection et l'actualisation du système informatisé de suivi- évaluation CI-FIRCA-157366-CS- INDV / Recrutement d'un consultant pour identifier les techniques et 2. Productivity Individual technologies ainsi que les enhancement and Under 2021-03- 2020-11- 2021-03- 2021-04- 2021-05- 2021-11- IBRD / 88450 Post Consultant Limited 10,000.00 0.00 produits de valorisation des improved access to Implementation 21 15 26 16 21 17 Selection sous-produits de la markets réhabilitation des vergers d'anacarde et proposer un plan de renforcement des capacités des bénéficiaires CI-FIRCA-157553-CS- INDV / Recrutement d'un 3. Support to private Individual consultant individuel pour investment in post-harvest Pending 2020-11- 2020-11- 2020-12- 2021-01- 2021-07- IBRD / 88450 Post Consultant Limited 100,000.00 0.00 la réalisation de l'étude and processing Implementation 05 10 01 05 04 Selection pour la définition du mode infrastructure de gestion des zones agro- industrielles CI-FIRCA-157558-CS- INDV / Recruter une firme 3. Support to private pour renforcer les capacités Individual investment in post-harvest Pending 2020-02- 2020-04- 2020-05- 2020-06- 2020-12- techniques de 12 IBRD / 88450 Post Consultant Open 18,000.00 0.00 and processing Implementation 28 17 08 12 09 entreprises en promotion Selection infrastructure sur lieu de vente (PLV) et en Marketing-Management CI-FIRCA-202096-CS- INDV / Recruter un 3. Support to private consultant pour renforcer Individual investment in post-harvest Pending 2020-11- 2020-11- 2020-12- 2021-01- 2021-07- les capacités techniques de IBRD / 88450 Post Consultant Limited 18,000.00 0.00 and processing Implementation 05 10 01 05 04 12 entreprises en Selection infrastructure promotion sur lieu de vente (PLV) et en Marketing- Management CI-FIRCA-157560-CS- INDV / Recrutement de 3. Support to private Individual consultants individuels pour investment in post-harvest Pending 2021-02- 2021-03- 2021-04- 2021-05- 2021-11- IBRD / 88450 Post Consultant Open 187,000.00 0.00 l’accompagnement des and processing Implementation 01 22 12 17 13 Selection unités de transformation infrastructure dans une démarche qualité CI-FIRCA-106460-CS- 3. Support to private Individual INDV / Recrutement de investment in post-harvest Pending 2021-01- 2021-01- 2021-02- 2021-03- 2021-09- IBRD / 88450 Post Consultant Limited 93,000.00 0.00 consultants individuels pour and processing Implementation 15 20 10 17 13 Selection réaliser les études de PAR infrastructure des entrepôts CI-FIRCA-106459-CS- 3. Support to private Individual INDV / Recrutement d'un investment in post-harvest Pending 2021-01- 2021-01- 2021-02- 2021-03- 2021-09- IBRD / 88450 Post Consultant Limited 187,000.00 0.00 cabinet pour réaliser les and processing Implementation 15 20 10 17 13 Selection EIES / CIES des entrepôts infrastructure CI-FIRCA-202097-CS- INDV / Recrutement d'un 3. Support to private Consultant pour l'évaluation Individual investment in post-harvest Under 2020-11- 2020-11- 2020-12- 2020-12- 2021-01- 2021-07- de la phase pilote IBRD / 88450 Post Consultant Limited 28,000.00 0.00 and processing Implementation 30 15 05 26 30 29 d'installation de kits de Selection infrastructure décorticage de noix au sein des sociétés coopératives Page 13 CI-FIRCA-157575-CS- INDV / Recrutement d'un 4. Program coordination, Individual consultant individuel en vue Pending 2021-02- 2021-04- 2021-04- 2021-05- 2021-11- IBRD / 88450 monitoring and knowledge Post Consultant Open 37,000.00 0.00 d'élaborer un plan d'action Implementation 15 05 26 31 27 management Selection pour le renforcement des actions de prises en compte du genre CI-FIRCA-158939-CS- INDV / Recrutement de 4. Program coordination, Individual Pending 2021-01- 2021-03- 2021-03- 2021-04- 2021-10- consultants pour la mise en IBRD / 88450 monitoring and knowledge Post Consultant Open 56,000.00 0.00 Implementation 15 05 26 30 27 oeuvre des activités de management Selection sensibilisation sur le MGP CI-FIRCA-126686-CS- INDV / Recrutement de 4. Program coordination, Individual Pending 2021-01- 2021-01- 2021-02- 2021-03- 2021-09- consultants junior en appui IBRD / 88450 monitoring and knowledge Post Consultant Limited 40,000.00 0.00 Implementation 11 16 06 13 09 aux spécialistes pour la management Selection mise en oeuvre des activités CI-FIRCA-106484-CS- INDV / Sélection d'un consultant pour la 4. Program coordination, Individual Pending 2021-01- 2021-01- 2021-01- 2021-03- 2021-08- formation des agents de IBRD / 88450 monitoring and knowledge Post Consultant Limited 10,000.00 0.00 Implementation 01 06 27 03 30 santé des régions du projet management Selection sur la prise en charge des personnes intoxiquées aux pesticides. CI-FIRCA-202104-CS- 4. Program coordination, Individual Under 2020-11- 2021-05- 2020-11- 2020-12- 2021-01- 2021-07- INDV / Recrutement d'un IBRD / 88450 monitoring and knowledge Post Consultant Limited 20,000.00 0.00 Implementation 16 26 21 12 16 15 consultant infographe management Selection CI-FIRCA-202105-CS- 4. Program coordination, Individual INDV / Recrutement de Pending 2020-11- 2020-11- 2020-12- 2021-01- 2021-07- IBRD / 88450 monitoring and knowledge Post Consultant Limited 60,000.00 0.00 traducteurs et d'interprètes Implementation 20 25 16 20 19 management Selection (anglais, vietnamien) CI-FIRCA-158230-CS- INDV / Recruter un 1. Institutional Individual 2020-03- 2020-05- 2020-06- 2020-07- 2021-01- consultant pour l'étude IBRD / 88450 strengthening and value Post Consultant Open 32,000.00 0.00 Canceled 30 18 08 13 09 relative à la construction de chain governance Selection l'entrepôt du CITA CI-FIRCA-74840-CS-CDS / 3. Support to private Convention complémentaire investment in post-harvest Pending 2020-11- 2020-12- 2021-02- 2021-08- avec des radios de IBRD / 88450 Post Direct Selection Direct 100,000.00 0.00 and processing Implementation 30 10 13 12 proximité (URPCI) pour la infrastructure promotion des activités du PPCA CI-FIRCA-203497-CS-CDS / Conception et réalisation 3. Support to private des études techniques du investment in post-harvest Under 2020-12- 2020-11- 2020-12- 2021-02- 2021-08- IBRD / 88450 Post Direct Selection Direct 224,000.00 0.00 centre de valorisation des and processing Implementation 01 15 11 14 13 coques de noix de cajou sur infrastructure la Zone Industrielle de Yamoussoukro CI-FIRCA-157580-CS- INDV / Recrutement de 4. Program coordination, Individual Pending 2020-11- 2021-01- 2021-02- 2021-03- 2021-09- consultants individuels pour IBRD / 88450 monitoring and knowledge Post Consultant Open 38,000.00 0.00 Implementation 30 18 08 15 11 faciliter l'organisation des management Selection évaluations participatives de 2020 CI-FIRCA-74759-CS-CDS / Recrutement d'un consultant (M KAMA BERTE) 4. Program coordination, pour la formation de l'UCP 2020-03- 2020-04- 2020-06- 2020-12- IBRD / 88450 monitoring and knowledge Post Direct Selection Direct 10,000.00 0.00 Canceled et des autres acteurs de 30 09 13 10 management mise en œuvre sur le plan d'amélioration des performances CI-FIRCA-203516-CS- INDV / Recrutement d'un consultant individuel pour 4. Program coordination, Individual la formation de l'UCP et des Pending 2020-12- 2020-12- 2021-01- 2021-02- 2021-08- IBRD / 88450 monitoring and knowledge Post Consultant Limited 10,000.00 0.00 autres acteurs de mise en Implementation 14 19 09 13 12 management Selection œuvre, sur le plan d'amélioration des performances CI-FIRCA-203478-CS-CDS / Entente directe avec le 1. Institutional BNETD pour le Under 2020-11- 2021-03- 2020-12- 2021-02- 2021-08- IBRD / 88450 strengthening and value Post Direct Selection Direct 102,000.00 0.00 renforcement du dispositif Implementation 27 09 07 10 09 chain governance de collecte et de traitement des données du SYSPER CI-FIRCA-203506-CS-CDS / Recrutement d'un consultant pour la 3. Support to private Individual modélisation en 3 investment in post-harvest Pending 2021-01- 2021-01- 2021-02- 2021-03- 2021-09- IBRD / 88450 Post Consultant Limited 40,000.00 0.00 Dimensions et la réalisation and processing Implementation 20 25 15 22 18 Selection d'une vidéo de synthèse infrastructure (film d'animation) des plateformes agro industrielles Bondoukou et Séguéla CI-FIRCA-203482-CS-CDS / Entente directe avec le cabinet Capacity Building Consultants Ltd pour 1. Institutional l'élaboration des documents Under 2020-11- 2021-03- 2020-12- 2021-02- 2021-08- IBRD / 88450 strengthening and value Post Direct Selection Direct 480,000.00 0.00 conceptuels du projet Implementation 27 09 07 10 09 chain governance portant sur la contribution de la filière anacarde à l'amélioration de l'empreinte carbone de la Côte d'Ivoire CI-FIRCA-203505-CS-CDS / Sélection d'un laboratoire pour la détermination des caractéristiques/paramètres 3. Support to private physico-chimiques (valeurs investment in post-harvest Pending 2020-11- 2020-12- 2021-02- 2021-08- IBRD / 88450 Post Direct Selection Direct 28,000.00 0.00 énergétiques, minéraux et and processing Implementation 30 10 13 12 vitamines), organoleptiques infrastructure des produits dérivés de l'anacarde fabriqués localement CI-FIRCA-212375-CS- INDV / Recrutement d'un consultant individuel devant 1. Institutional Individual réaliser la mission Under 2021-01- 2021-03- 2021-01- 2021-02- 2021-03- 2021-09- IBRD / 88450 strengthening and value Post Consultant Limited 13,000.00 0.00 d’accompagnement à Implementation 20 12 25 15 22 18 chain governance Selection l’élaboration et à la mise en place de matrices des prix des prestations de services du CITA. CI-PPCA-224177-CS-INDV / Recruter un Ingénieur des 1. Institutional Individual Pending 2021-06- 2021-08- 2021-08- 2021-10- 2022-04- statistiques pour appuyer le IBRD / 88450 strengthening and value Post Consultant Open 37,000.00 0.00 Implementation 21 09 30 04 02 CCA dans la collecte et le chain governance Selection traitement des données CI-PPCA-224279-CS-CDS 1. Institutional Pending 2021-05- 2021-05- 2021-07- 2022-01- / Recruter un Consultant IBRD / 88450 strengthening and value Post Direct Selection Direct 28,000.00 0.00 Implementation 14 24 28 24 informatique pour le PPCA chain governance CI-PPCA-224192-CS-INDV 1. Institutional Individual / Recruter un consultant Pending 2021-05- 2021-05- 2021-06- 2021-07- 2022-01- IBRD / 88450 strengthening and value Post Consultant Direct 19,000.00 0.00 pour former les agents de Implementation 10 20 10 15 11 chain governance Selection terrain du CCA CI-PPCA-224281-CS-INDV / Recruter un consultant 1. Institutional Individual pour réaliser une enquête Pending 2021-06- 2021-08- 2021-08- 2021-10- 2022-04- IBRD / 88450 strengthening and value Post Consultant Open 37,000.00 0.00 en vue d'évaluer la Implementation 21 09 30 04 02 chain governance Selection proportion de producteurs adhérant aux sociétés coopératives CI-PPCA-224292-CS-INDV / Recruter un consultant 1. Institutional Individual Pending 2021-06- 2021-06- 2021-07- 2021-08- 2022-02- pour organiser la formation IBRD / 88450 strengthening and value Post Consultant Limited 9,000.00 0.00 Implementation 15 20 11 15 11 du personnel aux soins de chain governance Selection premiers secours CI-PPCA-224293-CS-INDV 3. Support to private Individual / Recruter un consultant investment in post-harvest Under 2021-06- 2021-05- 2021-08- 2021-08- 2021-10- 2022-04- IBRD / 88450 Post Consultant Open 36,000.00 0.00 individuel pour la and processing Implementation 21 27 09 30 04 02 Selection conception de modèle HUB infrastructure CI-PPCA-224295-CS-INDV 1. Institutional Individual Pending 2021-05- 2021-05- 2021-06- 2021-07- 2022-01- / Recruter un consultant IBRD / 88450 strengthening and value Post Consultant Limited 11,000.00 0.00 Implementation 19 24 14 19 15 pour la réalisation du PGE- chain governance Selection Audit CI-PPCA-224306-CS-INDV / Recruter un consultant pour la réalisation de l'Etude de Dangers et 1. Institutional Individual Pending 2021-06- 2021-08- 2021-09- 2021-10- 2022-04- l'élaboration du Plan IBRD / 88450 strengthening and value Post Consultant Open 22,000.00 0.00 Implementation 30 18 08 13 11 d'Opération Interne chain governance Selection (disposition de prévention et gestion de la sécurité incendies et la santé et sécurité des personnes) CI-PPCA-224359-CS-INDV 1. Institutional Individual / Recruter des consultants Pending 2021-09- 2021-10- 2021-10- 2021-11- 2022-05- IBRD / 88450 strengthening and value Post Consultant Limited 28,000.00 0.00 pour la formation des OPEA Implementation 30 05 26 30 29 chain governance Selection en apiculture CI-PPCA-224449-CS-INDV / Recruter des consultants 3. Support to private Individual individuels pour réaliser les investment in post-harvest Pending 2021-06- 2021-08- 2021-08- 2021-09- 2022-03- IBRD / 88450 Post Consultant Open 56,000.00 0.00 études de PAR des petites and processing Implementation 15 03 24 28 27 Selection unités de décorticage de infrastructure noix de cajou CI-PPCA-224859-CS-INDV / Recruter des consultants 4. Program coordination, Individual pour renforcer les capacités Pending 2021-06- 2021-08- 2021-08- 2021-09- 2022-03- IBRD / 88450 monitoring and knowledge Prior Consultant Open 309,000.00 0.00 du CCA en vue du suivi de Implementation 17 05 26 30 29 management Selection la mise en œuvre des activités sur le terrain par les consultants CI-PPCA-224865-CS-INDV / Recruter un consultant en 4. Program coordination, Individual vue de réaliser une étude Pending 2021-06- 2021-08- 2021-08- 2021-10- 2022-04- IBRD / 88450 monitoring and knowledge Post Consultant Open 28,000.00 0.00 sur la prise en compte du Implementation 22 10 31 05 03 management Selection genre y compris l'évaluation des risques liés au VBG/EAS/HS CI-PPCA-224867-CS-INDV / Recruter un consultant pour former les agents de 4. Program coordination, Individual Pending 2021-05- 2021-05- 2021-06- 2021-07- 2022-01- santé des régions du projet IBRD / 88450 monitoring and knowledge Post Consultant Limited 11,000.00 0.00 Implementation 20 25 15 20 16 sur la prise en charge management Selection médicale des personnes intoxiquées aux pesticides CI-PPCA-224868-CS-INDV / Recruter deux (02) 4. Program coordination, Individual Pending 2021-05- 2021-07- 2021-07- 2021-09- 2022-03- consultants individuels pour IBRD / 88450 monitoring and knowledge Post Consultant Open 26,000.00 0.00 Implementation 20 08 29 02 01 faciliter l'organisation des management Selection évaluations participatives de 2020 CI-PPCA-224873-CS-INDV 4. Program coordination, Individual Pending 2021-04- 2021-05- 2021-05- 2021-06- 2021-12- / Recruter un consultant IBRD / 88450 monitoring and knowledge Post Consultant Limited 10,000.00 0.00 Implementation 27 02 23 27 24 pour team building management Selection CI-PPCA-225025-CS-INDV 2. Productivity / Recruter un consultant Individual enhancement and Pending 2021-06- 2021-07- 2021-08- 2021-09- 2022-03- pour la revue à mi-parcours IBRD / 88450 Post Consultant Open 30,000.00 0.00 improved access to Implementation 10 29 19 23 22 des activités du Conseil Selection markets Agricole dédié CI-PPCA-225037-CS-INDV / Recruter un consultant en 2. Productivity Individual vue de la réalisation de enhancement and Pending 2021-05- 2021-07- 2021-08- 2021-09- 2022-03- IBRD / 88450 Post Consultant Open 47,000.00 0.00 l'étude du coût de improved access to Implementation 24 12 02 06 05 Selection production des noix brutes markets de cajou et des plants greffés CI-PPCA-225041-CS-INDV 2. Productivity / Recruter un consultant Individual enhancement and 2021-06- 2021-06- 2021-07- 2021-07- 2021-08- 2022-02- pour la formation des IBRD / 88450 Post Consultant Limited 12,000.00 0.00 Under Review improved access to 30 09 05 26 30 26 ménages à la confection des Selection markets mets à base de soja CI-PPCA-225107-CS-INDV 2. Productivity Individual / Recruter un Consultant enhancement and Pending 2021-06- 2021-06- 2021-07- 2021-08- 2022-02- IBRD / 88450 Post Consultant Limited 10,000.00 0.00 toxicologue pour la mise en improved access to Implementation 22 27 18 22 18 Selection œuvre du PGP markets CI-PPCA-225636-CS-CDS / Recruter par Sélection 2. Productivity Directe d'un consultant enhancement and Pending 2021-07- 2021-07- 2021-09- 2022-03- IBRD / 88450 Post Direct Selection Direct 36,000.00 0.00 pour réaliser les activités de improved access to Implementation 12 22 25 24 la Coordination Scientifique markets (CS) du PNRA CI-PPCA-225638-CS-CDS 2. Productivity / Convention avec l’ANADER enhancement and Pending 2021-06- 2021-07- 2021-09- 2022-03- en vue de la poursuite du IBRD / 88450 Prior Direct Selection Direct 1,993,000.00 0.00 improved access to Implementation 24 04 07 06 soutien au Conseil Agricole markets dédié à l'Anacarde CI-PPCA-225639-CS-CDS 2. Productivity / Convention avec l’ANADER enhancement and Pending 2021-06- 2021-07- 2021-09- 2022-03- en vue de la poursuite de la IBRD / 88450 Post Direct Selection Direct 280,000.00 0.00 improved access to Implementation 22 02 05 04 vulgarisation électronique markets dans la Filière Anacarde CI-PPCA-225642-CS-CDS 2. Productivity / Convention avec l’ANADER enhancement and Pending 2021-06- 2021-06- 2021-08- 2022-02- en vue du suivi et du IBRD / 88450 Post Direct Selection Direct 280,000.00 0.00 improved access to Implementation 15 25 29 25 contrôle des activités de markets réhabilitation des vergers CI-PPCA-225643-CS-CDS / Recruter un cabinet pour 2. Productivity la poursuite de l’appui à la enhancement and Pending 2021-05- 2021-05- 2021-08- 2022-01- IBRD / 88450 Post Direct Selection Direct 50,000.00 0.00 mise en œuvre du improved access to Implementation 20 30 03 30 programme des Opérateurs markets Professionnels du Cajou (OPCA) CI-PPCA-225645-CS-CDS / Recruter un consultant en 2. Productivity vue de poursuivre la enhancement and Pending 2021-06- 2021-07- 2021-09- 2022-03- IBRD / 88450 Post Direct Selection Direct 121,000.00 0.00 formation des applicateurs improved access to Implementation 24 04 07 06 des OPCA en vue d’en faire markets des applicateurs professionnels du cajou CI-PPCA-225646-CS-CDS 2. Productivity / Recruter un consultant enhancement and Pending 2021-06- 2021-06- 2021-08- 2022-02- IBRD / 88450 Post Direct Selection Direct 56,000.00 0.00 pour l’accompagnement des improved access to Implementation 16 26 30 26 parcelles tests de soja markets CI-FIRCA-234885-CS-CDS 4. Program coordination, / Recruter un consultant en Pending 2021-05- 2021-05- 2021-08- 2022-01- IBRD / 88450 monitoring and knowledge Post Direct Selection Direct 56,000.00 0.00 communication en appui à Implementation 20 30 03 30 management la mise en œuvre du projet Page 14 PROCUREMENT PLAN (Textual Part) Project information: Philippines, Metro Manila Flood Management Project P153814 Project Implementation agency: Department of Public Works and Metro Manila Development Authority Date of the Procurement Plan: 13 April 2018 Period covered by this Procurement Plan: April 16, 2018 to October 15, 2019 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Government Procurement Reform Act (RA9184), such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions: 1. The procurement is open to all eligible firms from any country; 2. The request for bids/request for proposals document shall require the Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting signed contracts, confirming application of, and compliance with, the Bank's Anti- Corruption Guidelines, including without limitation the Bank's right to sanction and the Bank's inspection and audit rights; 3. Rights for the Bank to review procurement documentation and activities; and 4. An effective complaints mechanism. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations: Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Work) Goods: 15%; Works: is not applicable. PROCUREMENT Philippines : Metro Manila Flood Management Project PLAN General Information Country: Philippines Bank’s Approval Date of the Original Procurement Plan: 2018-04-19 2021-05-30 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P153814 GPN Date: 2018-03-15 Project Name: Metro Manila Flood Management Project Loan / Credit No: IBRD / 87840, COFN / C1450 M Executing Agency(ies): etro Manila Development Authority WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned PH-MMDA-CO203-4 / Design and Construction of Warehouse for Solid Waste Management Tools and Under Equipment with Office and 2. Minimizing Solid Waste in Single Stage - One 2022-02- IBRD / 87840 Post Request for Bids Open - National 480,292.40 0.00 Implementat 2021-04-16 2021-04-19 2021-04-21 2021-06-02 2021-07-02 2021-08-06 Quarters at Labasan PS. This Waterways Envelope 02 ion will be a solid structure where we will store tools and equipment for the implementation of the project. PH-MMDA-230683-CW-RFB National / Fabrication of Conveyor, Procurement Under Modification of Existing 2. Minimizing Solid Waste in 2021-08- IBRD / 87840 Post Direct Selection Direct Document - 1 50,000.00 0.00 Implementat 2021-04-30 2021-05-11 2021-05-05 2021-06-09 Conveyor and Civil Works on Waterways 08 Envelope process ion Staging Area and Perimeter (Non Bank-SPD) Fence. PH-MMDA-238497-CW-RFB National / Design and Construction of Procurement Pending 2. Minimizing Solid Waste in Single Stage - One 2022-04- Trash Traps on Selected Sites IBRD / 87840 Post Request for Bids Open - National Document - 1 702,300.00 0.00 Implementat 2021-06-18 2021-06-23 2021-08-04 2021-09-03 2021-10-08 Waterways Envelope 06 of Estero de Paco and San Envelope process ion Juan River and its Tributary (Non Bank-SPD) GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PH-MMDA-58579-GO-RFB / Trucks/Loader/Vehicle Package to include garbage compactor truck, rear end 2. Minimizing Solid Waste in Single Stage - One loading garbage compactor, IBRD / 87840 Prior Request for Bids Open - International 2,177,788.00 0.00 Canceled 2018-04-23 2018-04-28 2018-06-09 2018-07-09 2018-08-13 2019-02-09 Waterways Envelope garbage bins, hook lift loader truck, fork lift, hook lift container, dump truck, wheel pay loader, service vehicle PH-MMDA-59025-GO-RFQ / Solid Waste Management Tools that will be used for the implementation of community- based management program 2. Minimizing Solid Waste in Request for Single Stage - One (buggy, push carts, trolley IBRD / 87840 Post Open - National 96,154.00 0.00 Canceled 2018-10-06 2018-12-01 2019-05-30 Waterways Quotations Envelope bins, shovel, rakes, broomsticks, dust pans, plastic bags, gloves, face masks, rubber coats, raincoats) PH-MMDA-63617-GO-RFQ / Multi-purpose Vehicle (MPV) that will be used for project 4. Project Management and Request for Single Stage - One IBRD / 87840 Post Open - National 57,692.31 0.00 Canceled 2018-05-30 2018-07-25 2019-01-21 monitoring, site inspections, Coordination Quotations Envelope filed visits and coordination meetings PH-MMDA-63620-GO-RFB / Truck/Loader package to include garbage compactor truck, rear end loading 2. Minimizing Solid Waste in Single Stage - One garbage compactor, garbage IBRD / 87840 Prior Request for Bids Open - International 2,120,096.15 2,095,970.98 Signed 2018-05-25 2018-07-13 2018-05-30 2018-07-16 2018-07-11 2018-08-10 2019-03-28 2018-09-14 2019-04-29 2019-03-13 Waterways Envelope bins, hook lift loader truck, fork lift, hook lift container, dump truck and wheel pay loader PH-MMDA-144289-GO-RFB / Sound Trucks will be utilized as a modern and interactive approach in the community- based education & 2. Minimizing Solid Waste in Single Stage - One communications campaign of COFN / C1450 Post Request for Bids Open - National 214,384.00 223,435.91 Signed 2019-11-15 2019-11-20 2019-11-20 2020-01-01 2019-12-11 2020-01-31 2020-03-30 2020-03-06 2020-11-06 2020-09-02 Waterways Envelope proper Solid Waste Management at the barangay level as laid out in the MMFMP- Component 2. Two sound trucks will be purchased. PH-MMDA-144305-GO-RFB / Mobile Material Recovery Facilities (MRFs) are trucks operated by the MMDA-SWMO that will roam around 2. Minimizing Solid Waste in Single Stage - One different barangays involved COFN / C1450 Post Request for Bids Open - National 178,602.21 177,071.22 Signed 2019-11-15 2019-11-20 2019-11-20 2020-01-01 2019-12-11 2020-01-31 2019-12-26 2020-03-06 2019-12-27 2020-09-02 Waterways Envelope in MMFMP-Component 2 and collect recyclable materials in exchange of basic necessities. Three trucks will be purchased. Page 1 PH-MMDA-145500 / The Geographic Information Systems (GIS) is a computer platform for mapping/visual representation and will be 4. Project Management and COFN / C1450 Post Direct Selection Direct 32,030.65 0.00 Canceled 2019-09-26 2019-09-23 2019-10-01 2019-11-05 2020-05-03 used for gathering and Coordination analyzing existing/supplementary data in the pumping stations and nearby areas. PH-MMDA-145501 / The Solid Waste Granulator is a unique technology that prolongs the service life of landfills through reduction of 2. Minimizing Solid Waste in COFN / C1450 Prior Direct Selection Direct 492,332.25 517,212.75 Signed 2019-10-22 2020-02-15 2019-10-27 2020-08-21 2019-12-01 2019-12-27 2020-05-29 solid waste volume dumped Waterways along waterways/drainage areas. Bio-wastes and plastics will be refined and converted into by-products. PH-MMDA-63617 / The Multi- Purpose Vehicle (MPV) will be used for project monitoring, 4. Project Management and Request for Single Stage - One site inspections, filed visits, COFN / C1450 Post Open - National 49,414.50 49,096.63 Signed 2019-05-30 2019-07-25 2019-06-17 2020-01-21 Coordination Quotations Envelope and coordination meetings. Two (2) units will be purchased. PH-MMDA-63622 / Miscellaneous SWM Tools & Equipment (in units) as part of MMFMP Phase 1 - Component 2. Minimizing Solid Waste in Request for Single Stage - One 2: Pushcarts (75), Bicycle Bell COFN / C1450 Post Open - National 98,882.90 102,709.50 Terminated 2019-03-19 2019-05-14 2019-12-30 2019-11-10 Waterways Quotations Envelope Rings (75), Boats (30), Buggies/Wheelbarrows (30), Tribikes (80), and Rolling Bins (160). PH-MMDA-2019202 / Water bottles and canvas bags to support the Information, Education & Communications (IEC) campaigns to raise 2. Minimizing Solid Waste in Request for Single Stage - One COFN / C1450 Post Limited 10,590.00 0.00 Canceled 2019-10-15 2019-12-10 2020-06-07 awareness and encourage Waterways Quotations Envelope behavior change for improved solid waste management at the individual and household levels. PH-MMDA-2019203 / LED Wall Rental for the 2019 Solid Waste Management (SWM) Summit to kickoff and support Under 2. Minimizing Solid Waste in Request for Single Stage - One the IEC campaigns, engage COFN / C1450 Post Limited 4,410.00 0.00 Implementati 2019-11-03 2019-11-15 2019-12-29 2020-06-26 Waterways Quotations Envelope barangay officials, and on introduce the concept of circular resource management through interactive activities. PH-MMDA-2019204 / Shirts for the 2019 Solid Waste Management (SWM) Summit to kickoff and support the IEC 2. Minimizing Solid Waste in Request for Single Stage - One campaigns, engage barangay COFN / C1450 Post Limited 2,940.00 1,496.50 Signed 2019-11-03 2019-10-14 2019-12-29 2019-12-03 2020-06-26 Waterways Quotations Envelope officials, and introduce the concept of circular resource management through interactive activities. PH-MMDA-144308-GO-RFB / CCTV cameras/infra will be installed at strategic locations in MM barangays to monitor waste disposal activities Under 2. Minimizing Solid Waste in Single Stage - One along/beside creeks and COFN / C1450 Prior Request for Bids Open - National 536,640.00 0.00 Implementati 2019-11-15 2020-11-15 2019-11-20 2020-01-01 2021-01-04 2020-01-31 2021-06-06 2020-03-06 2020-09-02 Waterways Envelope esteros (estuaries). CCTV on control & monitoring systems/rooms will also be provided in the respective Barangay Halls. PH-MMDA-CO201-1 / Pilot Barangay-Based SWM Technologies - Procurement of proposed Solid Waste Pending 2. Minimizing Solid Waste in Request for Single Stage - One Collection Technologies and COFN / C1450 Post Open - National 24,306.81 0.00 Implementati 2020-11-08 2021-01-03 2021-07-02 Waterways Quotations Envelope installation in the pilot on barangays for the implementation of Component 2 PH-MMDA-CO201-7 / Purchase of ICT equipment for priority barangays as part of community quarantine 2. Minimizing Solid Waste in Request for Single Stage - One IBRD / 87840 Post Open - National 11,472.53 15,187.90 Signed 2020-11-08 2021-01-03 2020-12-29 2021-07-02 implementation during the Waterways Quotations Envelope COVID-19 pandemic. This is under the implementation of Component 2. PH-MMDA-CO202-4 / Pending 2. Minimizing Solid Waste in Request for Single Stage - One Signages for Heavy Equipment IBRD / 87840 Post Open - National 1,346.15 0.00 Implementati 2020-11-08 2021-01-03 2021-07-02 Waterways Quotations Envelope and Vehicles on PH-MMDA-CO202-5 / Washable Overall PPEs for Garbage Collectors, Landfill Staff, and FCSMO Staff - Procurement of personal Pending 2. Minimizing Solid Waste in Request for Single Stage - One protective equipment for the IBRD / 87840 Post Open - National 19,903.85 0.00 Implementati 2020-11-08 2021-01-03 2021-07-02 Waterways Quotations Envelope waste management and on pumping stations personnel as part of COVID-10 pandemic response under the Component 2 Page 2 Under PH-MMDA-CO204-3 / MPV - 2. Minimizing Solid Waste in Request for Single Stage - One COFN / C1450 Post Open - National 65,384.62 81,197.19 Implementati 2020-11-08 2021-01-03 2021-07-02 21 seater (MPV 5, 6) Waterways Quotations Envelope on PH-MMDA-CO204-2 / MPV - 7 seater (MPV 3, 4) - Procurement of vehicles to be 2. Minimizing Solid Waste in Request for Single Stage - One IBRD / 87840 Post Open - National 73,076.92 76,070.07 Signed 2020-11-08 2021-01-03 2020-10-01 2021-07-02 utilized by project team for Waterways Quotations Envelope the implementation of Component 2 PH-MMDA-CO204-5 / Conduct of Operation and Maintenance for Solid Waste Pending Granulator - Procurement of 2. Minimizing Solid Waste in Request for Single Stage - One IBRD / 87840 Post Open - National 19,230.76 0.00 Implementati 2020-11-08 2021-01-03 2021-07-02 additional parts and Waterways Quotations Envelope on accessories for a more effective utilization of Solid Waste Granulator PH-MMDA-CO205-2 / GNSS RTK System with CORS - Procurement of scanning 2. Minimizing Solid Waste in Request for Single Stage - One system for immediate data IBRD / 87840 Post Open - National 66,250.00 70,805.21 Signed 2020-11-08 2021-01-03 2020-12-29 2021-07-02 Waterways Quotations Envelope collection within the catchment areas of pumping stations PH-MMDA-CO207 / Staff Uniform and PPEs - Procurement of personal Pending 2. Minimizing Solid Waste in Request for Single Stage - One protective equipment for the COFN / C1450 Post Open - National 23,480.77 0.00 Implementati 2020-11-08 2021-01-03 2021-07-02 Waterways Quotations Envelope project team as part of COVID- on 10 pandemic response under the Component 2 PH-MMDA-CO42-3 / Project Management Office Pending Operations, Manpower, 4. Project Management and Request for Single Stage - One COFN / C1450 Post Open - National 8,076.92 0.00 Implementati 2020-11-08 2021-01-03 2021-07-02 Supplies, Equipment, Coordination Quotations Envelope on Furniture and Meeting (Operations - Additional Office Furniture) PH-MMDA-CO42-4 / Project Management Office Pending Operations, Manpower, 4. Project Management and Request for Single Stage - One IBRD / 87840 Post Open - National 4,807.69 0.00 Implementati 2020-11-08 2021-01-03 2021-07-02 Supplies, Equipment, Coordination Quotations Envelope on Furniture and Meeting (Operations - Office Applicances) PH-MMDA-CO204-4 / Payloader - Procurement of vehicles to be utilized by project team for the collection 2. Minimizing Solid Waste in Request for Single Stage - One COFN / C1450 Post Open - National 94,230.77 0.00 Canceled 2020-11-08 2021-01-03 2021-07-02 of waste in the pumping Waterways Quotations Envelope stations as part of the implementation of Component 2 PH-MMDA-200986-GO-RFB- 2 / Miscellaneous SWM Tools and Equipment - - as part of MMFMP Phase 1 - Component 2. Minimizing Solid Waste in Single Stage - One 2: Pushcarts (75), Bicycle IBRD / 87840 Post Request for Bids Open - National 98,882.90 0.00 Canceled 2019-03-14 2019-03-19 2019-04-30 2019-05-30 2019-07-04 2019-12-31 Waterways Envelope Bell Rings (75), Boats (30), Buggies/Wheelbarrows (30), Tribikes (80), and Rolling Bins (160) Under PH-MMDA-CO205-3 / 2. Minimizing Solid Waste in Single Stage - One COFN / C1450 Post Request for Bids Open - National 137,500.00 0.00 Implementati 2020-11-03 2020-07-22 2020-11-08 2020-12-20 2020-08-17 2021-01-19 2021-02-23 2021-08-22 Scanning Station Waterways Envelope on PH-MMDA-CO205-4 / Other Pending 2. Minimizing Solid Waste in Single Stage - One Survey Equipment, Software IBRD / 87840 Post Request for Bids Open - National 208,653.85 0.00 Implementati 2020-11-03 2020-11-08 2020-12-20 2021-01-19 2021-02-23 2021-08-22 Waterways Envelope and Accessories on Pending PH-MMDA-CO204-6 / 2. Minimizing Solid Waste in Single Stage - One COFN / C1450 Post Request for Bids Open - National 182,692.31 0.00 Implementati 2020-11-03 2020-11-08 2020-12-20 2021-01-19 2021-02-23 2021-08-22 Payloader Waterways Envelope on PH-MMDA-CO42-7 / Project Management Office Under Operations, Manpower, 4. Project Management and Single Stage - One IBRD / 87840 Post Request for Bids Open - National 154,086.19 0.00 Implementati 2020-11-03 2021-04-21 2020-11-08 2020-12-20 2021-01-19 2021-02-23 2021-08-22 Supplies, Equipment, Coordination Envelope on Furniture and Meeting (ICT Year 3 EQUIPMENT) PH-MMDA-CO42-8 / Project Management Office Operations, Manpower, Supplies, Equipment, Pending Furniture and Meeting (ICT 4. Project Management and Request for Single Stage - One IBRD / 87840 Post Limited 31,200.40 0.00 Implementati 2020-11-08 2021-01-03 2021-07-02 Year 3- SOFTWARE) - Coordination Quotations Envelope on Microsoft Office and AutoCAD for ICT YR 3 Equipment that will be distributed to MMDA offices that takes part in the project PH-MMDA-2019201 / Posters and flyers to suppor the Information, Education & Communications (IEC) campaigns to raise awareness 2. Minimizing Solid Waste in Request for Single Stage - One COFN / C1450 Post Limited 9,095.00 0.00 Canceled 2019-10-15 2019-11-15 2019-12-10 2020-06-07 and encourage behavior Waterways Quotations Envelope change for improved solid waste management at the individual and household levels. Page 3 PH-MMDA-200986-GO-RFQ- 3 / Miscellaneous SWM Tools and Equipment - - as part of MMFMP Phase 1 - Component 2. Minimizing Solid Waste in Request for Single Stage - One 2: Pushcarts (75), Bicycle Bell IBRD / 87840 Post Open - National 96,153.84 100,848.94 Signed 2020-03-19 2020-05-14 2019-12-30 2020-11-10 Waterways Quotations Envelope Rings (75), Boats (30), Buggies/Wheelbarrows (30), Tribikes (80), and Rolling Bins (160) PH-MMDA-230214-GO-RFB / The Supply, Fabrication, and Delivery of SWM Equipment Pending 2. Minimizing Solid Waste in Single Stage - One and Tools will strengthen the IBRD / 87840 Post Request for Bids Open - National 650,464.00 0.00 Implementati 2021-04-30 2021-05-14 2021-06-25 2021-07-25 2021-08-29 2022-03-27 Waterways Envelope capacity of both MMDA and on the barangays on regular operations. PH-MMDA-234925-GO-RFQ Pending / 45 Composite Tumbler with 2. Minimizing Solid Waste in Request for Single Stage - One IBRD / 87840 Post Open - National 24,930.00 0.00 Implementati 2021-06-04 2021-07-30 2021-10-28 Manual Sieve with Tools & Waterways Quotations Envelope on Equipment. NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PH-MMDA-CO201-2 / Barangay-based Waste Collection from Waterways- Pending Enforcement of Solid Waste 2. Minimizing Solid Waste in Request for Single Stage - One IBRD / 87840 Post Open - National 14,198.60 0.00 Implementati 2020-11-08 2021-01-03 2021-07-02 Management system in Waterways Quotations Envelope on barangays for the implementation of Component 2 PH-MMDA-CO201-8 / Capacity Building for Barangays- Knowledge enhancement initiative for Pending 2. Minimizing Solid Waste in Request for Single Stage - One barangays in the adoption of COFN / C1450 Post Open - National 19,592.31 0.00 Implementati 2020-11-08 2021-01-03 2021-07-02 Waterways Quotations Envelope improved solid waste on management system under Component 2 programs and projects PH-MMDA-200985-NC-RFQ / Audio Visual Presentation 2. Minimizing Solid Waste in Request for Single Stage - One IBRD / 87840 Post Open - National 57,692.30 52,026.13 Signed 2019-10-15 2019-12-10 2019-12-27 2020-06-07 for IEC-BCC campaigns of the Waterways Quotations Envelope MMFMP Component 2 CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PH-MMDA-59028-CS-QCBS / Services of Consultancy Firm that will develop the 2. Minimizing Solid Waste in Quality And Cost- Under IBRD / 87840 Prior Open - International 769,231.00 0.00 2018-04-23 2018-10-12 2018-05-14 2019-01-21 2018-06-27 2020-01-29 2018-07-25 2020-03-09 2018-08-24 2020-10-14 2018-09-28 2020-11-23 2018-11-02 2019-11-02 Community-based Waterways Based Selection Implementation Management System under Component 2 PH-MMDA-59026-CS-QCBS / Procurement of consulting 2. Minimizing Solid Waste in Quality And Cost- firm services that will develop IBRD / 87840 Prior Open - International 1,153,846.00 1,120,732.95 Signed 2018-04-23 2018-06-22 2018-05-14 2018-08-09 2018-06-27 2019-06-05 2018-07-25 2019-08-15 2018-08-24 2020-02-18 2018-09-28 2020-10-05 2018-11-02 2020-12-01 2019-11-02 Waterways Based Selection the Metro Manila Solid Waste Master Plan PH-MMDA-CO202-2 / Procurement of Consultancy 2. Minimizing Solid Waste in Quality And Cost- IBRD / 87840 Prior Open - International 2,842,204.42 0.00 Under Review 2020-11-03 2021-05-12 2020-11-24 2021-01-07 2021-02-04 2021-03-06 2021-04-10 2021-05-15 2022-05-15 Services for the CBSWMP Year Waterways Based Selection 2 PH-MMDA-CO202-1 / Waste Analysis and Characterization Study for the LGUs of Metro Manila- Study to be 2. Minimizing Solid Waste in Quality And Cost- Pending IBRD / 87840 Post Open - International 311,538.46 0.00 2020-11-03 2020-11-24 2021-01-07 2021-02-04 2021-03-06 2021-04-10 2021-05-15 2022-05-15 conducted for the purposes of Waterways Based Selection Implementation data refinement and validation under the implementation of Component 2. INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PH-MMDA-59027-CS-INDV / Project Management Specialist Individual (PMS) who shall oversee and 4. Project Management and IBRD / 87840 Post Consultant Open 85,000.00 87,785.49 Signed 2018-04-16 2018-05-21 2018-06-04 2018-09-03 2018-06-25 2018-10-08 2018-07-30 2018-10-15 2019-01-26 manage the over-all technical, Coordination Selection administrative and document control of the project PH-MMDA-64559-CS-INDV / Additional Project Management Specialist (PMS) who shall oversee and Individual manage technical, 4. Project Management and IBRD / 87840 Post Consultant Open 85,000.00 15,563.58 Signed 2018-06-04 2019-08-01 2018-07-23 2019-06-10 2018-08-13 2019-07-01 2018-09-17 2019-08-01 2019-03-16 administrative and document Coordination Selection control of the project and shall head a group of specialists with the actual community-based SWM activities. Page 4 PH-MMDA-122170-CS-INDV- 1 / The Project Manager shall oversee and manage the Individual 4. Project Management and overall day-to-day technical, COFN / C1450 Post Consultant Open 101,923.00 23,943.97 Signed 2019-05-28 2019-05-28 2019-07-16 2019-12-11 2019-08-06 2020-01-23 2019-09-10 2020-03-13 2020-03-08 Coordination administrative, and document Selection control in MMDA’s Project Management Office (PMO). PH-MMDA-110488-CS-INDV- 1 / The Project Officer shall serve as the substitute of the Project Manager to oversee Individual and manage the overall 4. Project Management and COFN / C1450 Post Consultant Open 86,634.62 20,365.38 Signed 2019-07-30 2019-07-30 2019-09-17 2019-09-09 2019-10-08 2019-09-13 2019-11-12 2019-12-23 2020-05-10 technical, administrative, and Coordination Selection document control of the project in consultation with the MMDA Project Management Office (PMO). PH-MMDA-110487-CS-INDV- 1 / The Procurement Specialist shall manage the Individual 4. Project Management and overall procurement activity of COFN / C1450 Post Consultant Open 86,634.62 20,365.38 Completed 2019-04-29 2019-04-29 2019-06-17 2019-09-18 2019-07-08 2019-09-23 2019-08-12 2019-11-25 2020-02-08 2020-10-14 Coordination the project in consultation Selection with the MMDA Project Management Office (PMO). PH-MMDA-119346-CS-INDV- 1 / The Finance Management Specialist shall oversee and manage the overall financial Individual management aspect including 4. Project Management and COFN / C1450 Post Consultant Open 86,634.62 20,365.38 Signed 2019-04-29 2019-04-29 2019-06-17 2019-10-23 2019-07-08 2019-10-28 2019-08-12 2019-11-13 2020-02-08 technical, administrative, and Coordination Selection document controls of the project in consultation with the MMDA Project Management Office (PMO). PH-MMDA-148143-CS-INDV / Additional Community Development Specialist (CDS) who shall be responsible for coordinating and monitoring Individual 2. Minimizing Solid Waste in the community development COFN / C1450 Post Consultant Open 65,000.00 16,114.71 Signed 2019-12-02 2019-12-02 2020-01-20 2020-09-21 2020-02-10 2020-09-30 2020-03-16 2020-10-07 2020-09-12 Waterways aspects of Component 2 of Selection MMFMP. The CDS shall support the Project Management Office and Solid Waste Management Office. PH-MMDA-122171-CS-INDV- 1 / The Community Development Specialist (CDS) Individual shall be responsible for 4. Project Management and COFN / C1450 Post Consultant Open 66,250.00 0.00 Canceled 2019-06-20 2019-06-20 2019-08-08 2019-08-29 2019-10-03 2020-03-31 coordinating and monitoring Coordination Selection the community development aspects of the Component 2 of MMFMP. PH-MMDA-205051-CS-INDV / The Procurement Specialist shall manage the overall Individual 4. Project Management and Under procurement activity of the COFN / C1450 Post Consultant Open 60,480.76 0.00 2020-11-17 2020-11-17 2021-01-05 2021-01-26 2021-03-02 2021-08-29 Coordination Implementation project in consultation with Selection the MMDA Project Management Office (PMO) PH-MMDA-CO41-2 / Project Management Office Individual 4. Project Management and Pending Operations - (Manpower - IBRD / 87840 Post Consultant Open 125,673.08 0.00 2020-01-01 2020-02-19 2020-03-11 2020-04-15 2020-10-12 Coordination Implementation PMO Consultants Selection Renumeration) PH-MMDA-122171-INDV-2 / The Community Development Specialist (CDS) shall be Individual responsible for coordinating 4. Project Management and Under COFN / C1450 Post Consultant Open 66,250.00 0.00 2019-11-30 2020-11-30 2020-01-18 2020-11-18 2020-02-08 2020-11-23 2020-03-14 2020-09-10 and monitoring the Coordination Implementation Selection community development aspects of the Component 2 of MMFMP. PH-MMDA-216929-CS-INDV Individual / Individual Consultancy 4. Project Management and Under IBRD / 87840 Post Consultant Open 61,837.50 0.00 2021-01-04 2021-01-04 2021-02-22 2021-03-01 2021-03-15 2021-03-12 2021-04-19 2021-10-16 Services/Monitoring & Coordination Implementation Selection Evaluation (M&E) Specialist PH-MMDA / Individual Individual Consultancy Services/PMO 4. Project Management and IBRD / 87840 Post Consultant Open 3,557.69 0.00 Canceled 2021-01-04 2021-01-04 2021-02-22 2021-03-15 2021-04-19 2021-10-16 Internal Midterm Assessment Coordination Selection Consultant PH-MMDA-220061-CS-INDV / Individual Consultancy Individual 4. Project Management and Under Services/PMO Internal IBRD / 87840 Post Consultant Direct 3,557.69 0.00 2021-01-04 2021-01-04 2021-01-14 2021-02-19 2021-02-04 2021-02-19 2021-03-11 2021-09-07 Coordination Implementation Midterm Assessment Selection Consultant PH-MMDA-229420-CS-INDV / The overall function covers maintaining and facilitating Individual 4. Project Management and Under positive relationships between IBRD / 87840 Post Consultant Open 1,300.00 0.00 2021-04-16 2021-04-19 2021-06-04 2021-06-25 2021-07-30 2022-07-30 Coordination Implementation the public and other Selection organizations often using media outlets. Page 5 Sample Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan Original: February 24, 2017 2. Date of General Procurement Notice: To Be Published 3. Period covered by this procurement plan: August 2017 to February 2019 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Type of Procurement Prior Review Threshold (>=US million) Works (including turnkey, supply and 5 installation of plant and equipment, and Public Private Partnership (PPP) Goods, information technology and 1.5 non-consulting services 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: Not Applicable. 4. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual Issued by the Ministry of Water, Irrigation and Electricity, August 2017. 5. Any Other Special Procurement Arrangements: Not Applicable. Summary of the Procurement Packages planned during the first 18 months after project effectiveness 1 2 3 4 5 6 7 July 9, 2010 Ref. Descripti Estimated Packag Domestic Review Com No. on Cost es Preference by Bank men US$ (yes/no) (Prior / ts million Post) 1 Summary 32 2 To be Prior of the ICB Determine (Works) d 2 Summary 10.2 6 To be Prior of the ICB Determine (Goods) d 3 Summary 19.4 5 No Post of the NCB (Works) 4 Summary 0.28 1 No Post of the NCB (Goods) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: 2. Type of Procurement Prior Review Threshold (>=US million) Consultants: firms 0.5 Consultants: Individuals 0.2 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: Not Applicable. 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. Description of Estimat Package Review Comment No. Assignment ed s by Bank s Cost (Prior / US$ Post) million 1 Summary of 3.5 3 Prior number of July 9, 2010 contracts that will be let under QCBS 2 Summary of 11.8 14 Post number of contracts that will be let under QCBS 3 Summary of 10.1 31 Post CQS/IC number of contracts that will be let under other methods July 9, 2010 PROCUREMENT Ethiopia : Second Ethiopia Urban Water Supply and Sanitation Project PLAN General Information Country: Ethiopia Bank’s Approval Date of the Original Procurement Plan: 2018-01-15 Revised Plan Date(s): (comma delineated, leave blank if none)2021-05-31 Project ID: P156433 GPN Date: 2018-02-02 Project Name: Second Ethiopia Urban Water Supply and Sanitation Project Loan / Credit No: IDA / 60070, IDA / 60080 Executing Agency(ies):Ministry of Water Irrigation and Electricity, WSS Program Management Unit WORKS Activity Reference No. / Procurement Estimated Actual Draft Pre- Draft Bidding Bid Evaluation Report Loan / Credit Market Procurement Prequalification High SEA/SH Process Prequalification Specific Procurement Bidding Documents Proposal Submission Contract Description Component Review Type Method Document Amount Amount qualification Document / and Recommendation Signed Contract No. Approach Process (Y/N) Risk Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Completion Type (US$) (US$) Documents Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned ET-MOWIE-77733-CW-DIR / Component 2: Sanitation and Pending Pipe laying for Dire Dewa town water supply services 2018-11- 2018-12- 2019-01- 2019-05- IDA / 60070 Post Direct Selection Direct 458,379.00 0.00 Implementat water supply project by Dire improvement in secondary 28 03 07 07 ion Dewa town cities ET-MOWIE-143512-CW-RFB Component 2: Sanitation and / Construction of public and Pending water supply services Single Stage - One 2019-11- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- communal toilet for Asosa IDA / 60070 Post Request for Bids Open - National 2,000,000.00 0.00 Implementat improvement in secondary Envelope 20 25 25 24 28 26 town by Asosa Water Supply ion cities and Sewerage Authority ET-MOWIE-143682-CW-RFB Component 2: Sanitation and / Construction of public and Pending water supply services Single Stage - One 2019-11- 2019-12- 2020-01- 2020-01- 2020-03- 2021-05- communal latrines for IDA / 60070 Post Request for Bids Open - National 1,626,000.00 0.00 Implementat improvement in secondary Envelope 27 02 01 31 06 30 Bahirdar town by Bahirdar ion cities town Water Supply Project ET-MOWIE-143697-CW-RFB / Construction of public and Component 2: Sanitation and Pending communal latrines for water supply services Single Stage - One 2019-11- 2019-12- 2020-01- 2020-02- 2020-03- 2021-05- IDA / 60070 Post Request for Bids Open - National 1,002,000.00 0.00 Implementat Adama Town By Adama improvement in secondary Envelope 28 03 02 01 07 31 ion Town Waste Water cities Management Project ET-MOWIE-143699-CW-RFB / Construction of public and Component 2: Sanitation and Pending communal latrines for water supply services Single Stage - One 2019-11- 2019-12- 2020-01- 2020-02- 2020-03- 2021-05- IDA / 60070 Post Request for Bids Open - National 1,192,000.00 0.00 Implementat Diredewa Town by Diredewa improvement in secondary Envelope 28 03 02 01 07 31 ion Town Water Supply and cities Sewerage Enterprise ET-MOWIE-143704-CW-RFB / Construction of public and Component 2: Sanitation and Pending communal latrines for water supply services Single Stage - One 2019-11- 2019-12- 2020-01- 2020-02- 2020-03- 2021-05- IDA / 60070 Post Request for Bids Open - National 1,436,000.00 0.00 Implementat Hawasa Town by Hawasa improvement in secondary Envelope 28 03 02 01 07 31 ion Town Water supply and cities sewerage service ET-MOWIE-143535-CW-RFB Component 2: Sanitation and / Construction of public and Pending water supply services Single Stage - One 2019-11- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- communal toilet for Dessie IDA / 60070 Post Request for Bids Open - National 2,000,000.00 0.00 Implementat improvement in secondary Envelope 20 25 25 24 28 26 town by Water Supply and ion cities Sewerage Authority ET-MOWIE-143530-CW-RFB / Construction of public and Component 2: Sanitation and Pending communal toilet for Deghabur water supply services Single Stage - One 2019-11- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- IDA / 60070 Post Request for Bids Open - National 2,000,000.00 0.00 Implementat town by Deghabur Water improvement in secondary Envelope 20 25 25 24 28 26 ion Supply and Sewerage cities Enterprise ET-MOWIE-143532-CW-RFB Component 2: Sanitation and / Construction of public and Pending water supply services Single Stage - One 2019-11- 2019-12- 2020-01- 2020-02- 2020-03- 2020-09- communal toilet for Sodo IDA / 60070 Post Request for Bids Open - National 2,000,000.00 0.00 Implementat improvement in secondary Envelope 28 03 02 01 07 03 town by Sodo Water Supply ion cities and Sewerage Authority ET-MOWIE-142793-CW-RFB / Construction of FSM (fecal Component 2: Sanitation and sludge management) for water supply services Open - Single Stage - One 2019-12- 2019-12- 2020-02- 2020-03- 2020-04- 2021-11- IDA / 60070 Post Request for Bids 8,610,620.78 0.00 Canceled Bahirdar and Hawasa Towns improvement in secondary International Envelope 25 30 10 11 15 06 by water development cities commission ET-MOWIE-143521-CW-RFB / Construction of public and Component 2: Sanitation and Pending communal toilet for Semera water supply services Single Stage - One 2019-11- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- IDA / 60070 Post Request for Bids Open - National 2,000,000.00 0.00 Implementat towns by Semera Water improvement in secondary Envelope 20 25 25 24 28 26 ion Supply and Sewerage cities Authority ET-MOWIE-143537-CW-RFB / Construction of public and Component 2: Sanitation and Pending communal toilet for water supply services Single Stage - One 2019-11- 2019-12- 2020-01- 2020-02- 2020-03- 2020-09- IDA / 60070 Post Request for Bids Open - National 2,000,000.00 0.00 Implementat Debrebirhan town by improvement in secondary Envelope 28 03 02 01 07 03 ion Debrebirhan Water Supply and cities Sewerage Authority ET-MOWIE-143510-CW-RFB Component 2: Sanitation and / Construction of public and Pending water supply services Single Stage - One 2019-11- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- communal toilet for Asella IDA / 60070 Post Request for Bids Open - National 2,000,000.00 0.00 Implementat improvement in secondary Envelope 20 25 25 24 28 26 Town by Asella Water Supply ion cities and Sewerage Enterprise ET-MOWIE-143522-CW-RFB Component 2: Sanitation and / Construction of public and water supply services Single Stage - One 2019-11- 2020-02- 2019-11- 2019-12- 2020-04- 2020-01- 2020-05- 2020-02- 2020-06- 2020-08- communal toilet for Adigrat IDA / 60070 Post Request for Bids Open - National 2,000,000.00 490,071.10 Signed improvement in secondary Envelope 20 13 25 25 28 24 12 28 30 26 towns by Adigrat Water cities Supply and Sewerage service ET-MOWIE-143528-CW-RFB Component 2: Sanitation and / Construction of public and Pending water supply services Single Stage - One 2019-11- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- communal toilet for Jigjiga IDA / 60070 Post Request for Bids Open - National 2,000,000.00 0.00 Implementat improvement in secondary Envelope 20 25 25 24 28 26 town by Jigjiga Water Supply ion cities and Sewerage Enterprise ET-MOWIE-143501-CW-RFB Component 2: Sanitation and / construction of public and Pending water supply services Single Stage - One 2019-11- 2019-12- 2020-01- 2020-02- 2020-03- 2020-09- communal toilet for Bishoftu IDA / 60070 Post Request for Bids Open - National 2,000,000.00 0.00 Implementat improvement in secondary Envelope 28 03 14 13 19 15 town by Bishoftu Water ion cities Supply and Sewerage Authority ET-MOWIE-143272-CW-RFB / construction of public and Component 2: Sanitation and Pending communal toilet for Nekemte water supply services Single Stage - One 2019-11- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- IDA / 60070 Post Request for Bids Open - National 2,000,000.00 0.00 Implementat Town By Nekemte Water improvement in secondary Envelope 20 25 25 24 28 26 ion supply and Sewerage cities Enterprise . ET-MOWIE-143519-CW-RFB / Construction of public and Component 2: Sanitation and Pending communal toilet for Gambella water supply services Single Stage - One 2019-11- 2019-12- 2020-01- 2020-02- 2020-03- 2020-09- IDA / 60070 Post Request for Bids Open - National 2,000,000.00 0.00 Implementat towns by Gambella Water improvement in secondary Envelope 28 03 02 01 07 03 ion Supply and Sewerage cities Authority ET-MOWIE-143478-CW-RFB Component 2: Sanitation and / Construction of public and Pending water supply services Single Stage - One 2019-11- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- communal toilet for Jima town IDA / 60070 Post Request for Bids Open - National 2,000,000.00 0.00 Implementat improvement in secondary Envelope 20 25 25 24 28 26 by Jima Water Supply and ion cities Sewerage Authority ET-MOWIE-143524-CW-RFB Component 2: Sanitation and / Construction of public and Under water supply services Single Stage - One 2019-11- 2020-05- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- communal toilet for Harar IDA / 60070 Post Request for Bids Open - National 2,000,000.00 0.00 Implementat improvement in secondary Envelope 20 20 25 25 24 28 26 town by Harar Water Supply ion cities and Sewerage Authority ET-MOWIE-143531-CW-RFB / Construction of public and Component 2: Sanitation and Pending communal toilet for water supply services Single Stage - One 2019-11- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- IDA / 60070 Post Request for Bids Open - National 2,000,000.00 0.00 Implementat Arbaminch town by improvement in secondary Envelope 20 25 25 24 28 26 ion Arbaminch Water Supply and cities Sewerage Authority ET-MOWIE-143536-CW-RFB Component 2: Sanitation and / Construction of public and Pending water supply services Single Stage - One 2019-11- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- communal toilet for Gonder IDA / 60070 Post Request for Bids Open - National 2,000,000.00 0.00 Implementat improvement in secondary Envelope 20 25 25 24 28 26 town by Gonder Water Supply ion cities and Sewerage Authority Page 1 ET-MOWIE-143503-CW-RFB / Construction of public and Component 2: Sanitation and Pending communal toilet for water supply services Single Stage - One 2019-11- 2019-11- 2019-12- 2020-01- 2020-02- 2020-08- IDA / 60070 Post Request for Bids Open - National 2,000,000.00 0.00 Implementat Shashamene town by improvement in secondary Envelope 20 25 25 24 28 26 ion Shashamene Water Supply cities and Sewerage Enterprise ET-MOWIE-139087-CW-RFB / Design, Construction and Operation of Five Cities Faecal Component 2: Sanitation and Sludge Treatment Plant (FSTP) Pending water supply services Open - Single Stage - One 21,643,000.0 2020-03- 2020-04- 2020-06- 2020-07- 2020-08- 2020-10- under two lots ( Lot I Adama, IDA / 60070 Prior Request for Bids 0.00 Implementat improvement in secondary International Envelope 0 13 17 01 02 24 17 Dire Dewa and Mekelle and ion cities Lot II Bahir Dar and Hawasa). Implementing Agency: Water Development Commission. ET-MOWIE-172250-CW-RFQ / construction of civil work, Component 2: Sanitation and supply and installation of Pending water supply services Request for Single Stage - One 2020-05- 2020-07- 2020-10- pipes and fittings for IDA / 60070 Post Limited 73,970.00 0.00 Implementat improvement in secondary Quotations Envelope 25 20 18 Shashamene town WSSE low ion cities income are by Shashamene town WSSE ET-MOWIE-172255-CW-RFQ / Civil work and supply and Component 2: Sanitation and Pending installation of water supply services Request for Single Stage - One 2020-05- 2020-07- 2020-10- IDA / 60070 Post Limited 90,640.00 0.00 Implementat electromagnetical equipment improvement in secondary Quotations Envelope 25 20 18 ion for Nekemte town low income cities are by Nekemte town WSSE ET-MOWIE-172258-CW-RFQ Component 2: Sanitation and / Expansion of Water Supply Pending water supply services Request for Single Stage - One 2020-05- 2020-07- 2020-10- system for Adigrat town low IDA / 60070 Post Limited 75,260.00 0.00 Implementat improvement in secondary Quotations Envelope 25 20 18 income area by Adigrat town ion cities WSSE ET-MOWIE-172259-CW-RFQ Component 2: Sanitation and / Earth Work, supply and water supply services Request for Single Stage - One 2020-05- 2020-04- 2020-07- 2020-04- 2020-10- installation of pipes and fitting IDA / 60080 Post Limited 75,800.00 29,363.01 Completed improvement in secondary Quotations Envelope 25 18 20 30 18 for Jigjiga town low income cities are by Jigijiga town WSSE ET-MOWIE-172260-CW-RFQ / Earth work and supply and Component 2: Sanitation and installation of pipes and fitting water supply services Request for Single Stage - One 2020-05- 2020-04- 2020-07- 2020-04- 2020-09- for Degahabur town low IDA / 60070 Post Limited 75,800.00 16,028.61 Signed improvement in secondary Quotations Envelope 25 09 20 27 18 income area water supply cities project by Deghabur town WSSE ET-MOWIE-172944-CW-RFP / Design, Construction and Operation of Five Cities Faecal Component 2: Sanitation and Sludge Treatment Plant (FSTP) water supply services Request for Open - Single Stage - Two 21,643,000.0 Under 2020-06- 2020-08- 2020-08- 2021-04- 2020-08- 2020-06- 2020-09- 2020-10- 2021-01- 2021-02- 2022-08- under two lots ( Lot I Adama, IDA / 60070 Prior 0.00 improvement in secondary Proposals International Envelope 0 Review 05 21 21 07 21 10 08 30 12 16 10 Dire Dewa and Mekelle and cities Lot II Bahir Dar and Hawasa). Implementing Agency: Water Development Commission. ET-MOWIE-208763-CW-RFB / Procurement of construction and rehabilitation 20 public Component 2: Sanitation and Pending and communal latrines (10 water supply services Single Stage - One 2020-12- 2020-12- 2021-01- 2021-02- 2021-03- 2021-09- IDA / 60070 Post Request for Bids Open - National 488,000.00 0.00 Implementat new construction and 10 improvement in secondary Envelope 25 30 29 13 20 16 ion existing latrines rehabilitation) cities for Bahir Dar Town by Bahir Dar Town WSSA ET-MOWIE-208771-CW-RFB / Construction of 22 public Component 2: Sanitation and and communal latrines for Pending water supply services Single Stage - One 2020-12- 2020-12- 2021-01- 2021-02- 2021-03- 2021-08- Dire Dewa town Under two IDA / 60070 Post Request for Bids Open - National 816,000.00 0.00 Implementat improvement in secondary Envelope 15 20 19 03 03 30 lots (lot I 11 public and lot II ion cities 11 communal) by Dire Dewa WSSE ET-MOWIE-208775-CW-RFB / Construction of civil works Component 2: Sanitation and Pending for completing the sludge water supply services Single Stage - One 2020-12- 2020-12- 2021-01- 2021-02- 2021-03- 2021-09- IDA / 60070 Post Request for Bids Open - National 369,000.00 0.00 Implementat drying bed for fecal sludge improvement in secondary Envelope 22 27 26 10 17 13 ion management for Arbaminch cities town by Arbaminch town WSS ET-MOWIE-227378-CW-RFB / Construction of ten(10) Component 2: Sanitation and Pending public and communal toilet water supply services Single Stage - One 2021-04- 2021-05- 2021-06- 2021-06- 2021-07- 2022-01- IDA / 60070 Post Request for Bids Open - National 509,670.00 0.00 Implementat for shashamane town by improvement in secondary Envelope 30 10 09 29 20 16 ion shashamane Water Supply cities and Sewerage Authority ET-MOWIE-143701-CW-RFB / Construction of 32 public and communal latrines under Component 2: Sanitation and Pending two lots ( Lot I #14 and Lot II water supply services Single Stage - One 2021-04- 2021-04- 2021-05- 2021-06- 2021-07- 2022-07- IDA / 60070 Post Request for Bids Open - National 1,600,000.00 0.00 Implementat 18) for Mekelle Town by improvement in secondary Envelope 20 25 25 24 29 29 ion Mekelle Town Water Supply cities and Sewerage Enterprise by Mekelle town WSSE. GOODS Activity Reference No. / Draft Pre- Draft Bidding Bid Evaluation Report Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Prequalification Specific Procurement Bidding Documents Proposal Submission Description Component Review Type Method qualification Document / and Recommendation Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Documents Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-MOWIE-43004-GO-DIR / Component 2: Sanitation and Supply of pipes and fittings Under water supply services 2018-01- 2018-01- 2018-02- 2018-05- for the remaining work of Dire IDA / 60070 Prior Direct Selection Direct 1,897,466.00 0.00 Implementati improvement in secondary 12 17 24 25 Dewa City Water Supply and on cities Sanitation Project ET-MOWIE-43329-GO-RFQ / Procurement of office equipment (printers, desk top Component 3: Project Pending computers, scanners, photo Request for Single Stage - One 2018-03- 2018-05- 2018-06- IDA / 60070 management & institutional Post Limited 10,000.00 0.00 Implementati copy machines and lap top Quotations Envelope 29 17 16 strengthening on computers) for Gambella City Water Supply and Sewerage Service ET-MOWIE-43286-GO-RFQ / procurement of office equipment (printers, desk top Component 3: Project computers, scanners, photo Request for Single Stage - One 2018-03- 2019-09- 2018-05- 2020-03- 2018-06- 2020-04- IDA / 60070 management & institutional Post Limited 10,000.00 5,098.59 Completed copy machines and lap top Quotations Envelope 22 10 03 21 02 10 strengthening computers)for Deghabur Town Water Supply and Sewerage Service ET-MOWIE-43289-GO-RFQ / procurement of office equipment (printers, desk top Component 3: Project Under computers, scanners, photo Request for Single Stage - One 2018-03- 2020-09- 2018-05- 2018-06- IDA / 60070 management & institutional Post Limited 10,000.00 0.00 Implementati copy machines and lap top Quotations Envelope 22 17 03 02 strengthening on computers) for Arbaminch Town Water Supply and Sewerage Service ET-MOWIE-43291-GO-RFQ / procurement of office equipment (printers, desk top Component 3: Project Pending computers, scanners, photo Request for Single Stage - One 2018-03- 2018-05- 2018-06- IDA / 60070 management & institutional Post Limited 10,000.00 0.00 Implementati copy machines and lap top Quotations Envelope 22 03 02 strengthening on computers) for Harar Town Water Supply and Sewerage Service ET-MOWIE-43294-GO-RFQ / procurement of office equipment(printers, desk top Component 3: Project computers, scanners, photo Request for Single Stage - One 2018-03- 2019-11- 2018-05- 2020-06- 2018-06- IDA / 60070 management & institutional Post Limited 10,000.00 6,182.79 Signed copy machines and lap top Quotations Envelope 29 25 10 23 09 strengthening computers) for Bishoftu Town Water Supply and Sewerage Service Page 2 ET-MOWIE-43297-GO-RFQ / Procurement of office equipment (printers, desk top Component 3: Project Pending computers, scanners, photo Request for Single Stage - One 2018-03- 2018-05- 2018-06- IDA / 60070 management & institutional Post Limited 10,000.00 0.00 Implementati copy machines and lap top Quotations Envelope 29 17 16 strengthening on computers) for Shashemane City Water Supply and Sewerage Service ET-MOWIE-43299-GO-RFQ / procurement of office equipment(printers, desk top Component 3: Project computers, scanners, photo Request for Single Stage - One 2018-03- 2017-09- 2018-05- 2020-04- 2018-06- 2020-04- IDA / 60070 management & institutional Post Limited 10,000.00 11,105.57 Completed copy machines and lap top Quotations Envelope 29 11 17 02 16 02 strengthening computers) for Jigjiga City Water Supply and Sewerage Service ET-MOWIE-43300-GO-RFQ / Procurement of office equipment (printers, desk top Component 3: Project Pending computers, scanners, photo Request for Single Stage - One 2018-03- 2018-05- 2018-06- IDA / 60070 management & institutional Post Limited 10,000.00 0.00 Implementati copy machines and lap top Quotations Envelope 29 10 09 strengthening on computers) for Hawassa City Water Supply and Sewerage Service ET-MOWIE-43035-GO-RFQ / Procurement of IT equipment Component 3: Project Pending (printers, desk top computers, Request for Single Stage - One 2018-04- 2018-06- 2018-07- IDA / 60070 management & institutional Post Limited 50,000.00 0.00 Implementati scanners, photo copy Quotations Envelope 14 09 09 strengthening on machines and lap top computers) for Ministry PIU ET-MOWIE-43317-GO-RFQ / Procurement of office equipment (printers, desk top Component 3: Project Pending computers, scanners, photo Request for Single Stage - One 2018-03- 2018-05- 2018-06- IDA / 60070 management & institutional Post Limited 10,000.00 0.00 Implementati copy machines and lap top Quotations Envelope 29 17 16 strengthening on computers) for Assosa City Water Supply and Sewerage Service ET-MOWIE-43319-GO-RFQ / Procurement of office equipment (printers, desk top Component 3: Project Pending computers, scanners, photo Request for Single Stage - One 2018-03- 2018-05- 2018-06- IDA / 60070 management & institutional Post Limited 10,000.00 0.00 Implementati copy machines and lap top Quotations Envelope 29 10 09 strengthening on computers) for Asella City Water Supply and Sewerage Service ET-MOWIE-43322-GO-RFQ / Procurement of office equipment (printers, desk top Component 3: Project Pending computers, scanners, photo Request for Single Stage - One 2018-03- 2018-05- 2018-06- IDA / 60070 management & institutional Post Limited 10,000.00 0.00 Implementati copy machines and lap top Quotations Envelope 29 10 09 strengthening on computers) for Sodo City Water Supply and Sewerage Service ET-MOWIE-43324-GO-RFQ / Procurement of office equipment (printers, desk top Component 3: Project computers, scanners, photo Request for Single Stage - One 2018-03- 2018-12- 2018-05- 2019-02- 2018-06- IDA / 60070 management & institutional Post Limited 10,000.00 3,436.18 Signed copy machines and lap top Quotations Envelope 29 27 10 07 09 strengthening computers) for Debre Berhan City Water Supply and Sewerage Service ET-MOWIE-43326-GO-RFQ / Procurement of office equipment (printers, desk top Component 3: Project Pending computers, scanners, photo Request for Single Stage - One 2018-03- 2018-05- 2018-06- IDA / 60070 management & institutional Post Limited 10,000.00 0.00 Implementati copy machines and lap top Quotations Envelope 29 10 09 strengthening on computers) for Dessie City Water Supply and Sewerage Service ET-MOWIE-43328-GO-RFQ / Procurement of office equipment (printers, desk top Component 3: Project Pending computers, scanners, photo Request for Single Stage - One 2018-03- 2018-05- 2018-06- IDA / 60070 management & institutional Post Limited 10,000.00 0.00 Implementati copy machines and lap top Quotations Envelope 29 10 09 strengthening on computers) for Gonder City Water Supply and Sewerage Service ET-MOWIE-43331-GO-RFQ / Procurement of office equipment (printers, desk top Component 3: Project computers, scanners, photo Request for Single Stage - One 2018-03- 2018-09- 2018-05- 2018-09- 2018-06- IDA / 60070 management & institutional Post Limited 10,000.00 3,362.55 Signed copy machines and lap top Quotations Envelope 29 06 10 29 09 strengthening computers) for Nekmte City Water Supply and Sewerage Service ET-MOWIE-43333-GO-RFQ / Procurement of office equipment (printers, desk top Component 3: Project computers, scanners, photo Request for Single Stage - One 2018-03- 2018-09- 2018-05- 2018-11- 2018-06- IDA / 60070 management & institutional Post Limited 10,000.00 1,386.08 Signed copy machines and lap top Quotations Envelope 29 19 10 03 09 strengthening computers) for Jimma City Water Supply and Sewerage Service ET-MOWIE-43303-GO-RFQ / Procurement of office equipment (printers, desk top Component 3: Project computers, scanners, photo Request for Single Stage - One 2018-03- 2019-09- 2018-05- 2019-10- 2018-06- IDA / 60070 management & institutional Post Limited 10,000.00 8,151.84 Signed copy machines and lap top Quotations Envelope 29 26 10 19 09 strengthening computers) for Adama City Water Supply and Sewerage Service ET-MOWIE-43304-GO-RFQ / Procurement of office equipment (printers, desk top Component 3: Project Pending computers, scanners, photo Request for Single Stage - One 2018-03- 2018-05- 2018-06- IDA / 60070 management & institutional Post Limited 10,000.00 0.00 Implementati copy machines and lap top Quotations Envelope 29 10 09 strengthening on computers) for Mekelle City Water Supply and Sewerage Service ET-MOWIE-43307-GO-RFQ / Procurement of office equipment(printers, desk top Component 3: Project Pending computers, scanners, photo Request for Single Stage - One 2018-03- 2018-05- 2018-06- IDA / 60070 management & institutional Post Limited 10,000.00 0.00 Implementati copy machines and lap top Quotations Envelope 29 10 09 strengthening on computers) for Bahir Dar City Water Supply and Sewerage Service ET-MOWIE-43310-GO-RFQ / Procurement of office equipment for Dire Dawa City Component 3: Project Pending Water Supply and Sewerage Request for Single Stage - One 2018-03- 2018-05- 2018-06- IDA / 60070 management & institutional Post Limited 10,000.00 0.00 Implementati Service(Printers, desk top Quotations Envelope 29 10 09 strengthening on computers, scanners, photo copy machines and lap top computers) ET-MOWIE-43311-GO-RFQ / Procurement of office equipment for Semera City Component 3: Project Pending Water Supply and Sewerage Request for Single Stage - One 2018-03- 2018-05- 2018-06- IDA / 60070 management & institutional Post Limited 10,000.00 0.00 Implementati Service(Printers, desk top Quotations Envelope 29 10 09 strengthening on computers, scanners, photo copy machines and lap top computers) ET-MOWIE-43313-GO-RFQ / Procurement of office equipment for Adegrat City Component 3: Project Pending Water Supply and Sewerage Request for Single Stage - One 2018-03- 2018-05- 2018-06- IDA / 60070 management & institutional Post Limited 10,000.00 0.00 Implementati Service (printers, desk top Quotations Envelope 29 10 09 strengthening on computers, scanners, photo copy machines and lap top computers) ET-MOWIE-50407-GO-DIR / Component 2: Sanitation and Procurement of Bulk Flow water supply services 2018-02- 2018-04- 2018-03- 2018-04- 2018-07- meter for Mekelle Town Water IDA / 60070 Prior Direct Selection Direct 433,013.00 0.00 Canceled improvement in secondary 28 05 05 06 05 Supply and Sewerage Service cities by Mekelle town WSSS Component 2: Sanitation and ET-MOWIE-55837-GO-RFB / Pending water supply services Single Stage - One 2018-06- 2018-06- 2018-07- 2018-08- 2018-09- 2018-12- Procurement of Automatic IDA / 60070 Post Request for Bids Open - National 250,000.00 0.00 Implementati improvement in secondary Envelope 20 25 25 24 28 27 Water Meter Test Bench on cities Page 3 ET-MOWIE-75633-GO-RFQ / Procurement of office equipment (printers, desk top computers, scanners photocopy machines and Component 3: Project Pending Request for Single Stage - One 2018-09- 2018-11- 2018-12- laptop computers for Amhara IDA / 60070 management & institutional Post Limited 10,000.00 0.00 Implementati Quotations Envelope 15 10 10 Region Water,Irrigation and strengthening on Energy Development Bureau by Amhara Region Water,Irrigation and Energy Development Bureau ET-MOWIE-75634-GO-RFQ / Procurement of office equipment (printers, desk top computers, scanners Component 3: Project Pending photocopy machines and Request for Single Stage - One 2018-09- 2018-11- 2018-12- IDA / 60070 management & institutional Post Limited 10,000.00 0.00 Implementati laptop computers for Oromia Quotations Envelope 15 10 10 strengthening on Region Water,Mineral and Energy Bureau by Oromia Region Water,Mineral and Energy Bureau. ET-MOWIE-75635-GO-RFQ / Procurement of office equipment (printers, desk top computers, scanners photocopy machines and Component 3: Project Pending Request for Single Stage - One 2018-09- 2018-11- 2018-12- laptop computers for SNNPR IDA / 60070 management & institutional Post Limited 10,000.00 0.00 Implementati Quotations Envelope 15 10 10 Region Water,Irrigation and strengthening on Energy Development Bureau by SNNPR Region Water,Irrigation and Energy Development Bureau ET-MOWIE-75636-GO-RFQ / Procurement of office equipment (printers, desk top computers, scanners Component 3: Project Pending photocopy machines and Request for Single Stage - One 2018-09- 2018-11- 2018-12- IDA / 60070 management & institutional Post Limited 10,000.00 0.00 Implementati laptop computers for Afar Quotations Envelope 15 10 10 strengthening on Region Water Resource Development Bureau by Afar Region Water Resource Development Bureau ET-MOWIE-75637-GO-RFQ / Procurement of office equipment (printers, desk top computers, scanners Component 3: Project Pending photocopy machines and Request for Single Stage - One 2018-09- 2018-11- 2018-12- IDA / 60070 management & institutional Post Limited 10,000.00 0.00 Implementati laptop computers for Somali Quotations Envelope 15 10 10 strengthening on Region Water Resource Development Bureau by Somali Region Water Resource Development Bureau ET-MOWIE-75641-GO-RFQ / Procurement of office equipment (printers, desk top computers, scanners photocopy machines and Component 3: Project Pending laptop computers for Request for Single Stage - One 2018-09- 2018-11- 2018-12- IDA / 60070 management & institutional Post Limited 10,000.00 0.00 Implementati Gambella Region Quotations Envelope 15 10 10 strengthening on Water,Irrigation and Energy Development Bureau by Gambella Region Water,Irrigation and Energy Development Bureau ET-MOWIE-75643-GO-RFQ / Procurement of office equipment (printers, desk top computers, scanners photocopy machines and Component 3: Project Pending laptop computers for Request for Single Stage - One 2018-09- 2018-11- 2018-12- IDA / 60070 management & institutional Post Limited 10,000.00 0.00 Implementati Benshangul Gumuz Region Quotations Envelope 15 10 10 strengthening on Water,Irrigation and Energy Development Bureau by Benshangul Region Water,Irrigation and Energy Development Bureau ET-MOWIE-75646-GO-RFQ / Procurement of Office Equipment (printers, desktop Component 3: Project Pending computers, scanners, Request for Single Stage - One 2018-09- 2018-11- 2018-12- IDA / 60070 management & institutional Post Limited 10,000.00 0.00 Implementati photocopy machines and Quotations Envelope 15 10 10 strengthening on laptop computers) for Tigray Region Water Bureau by Tigray Region Water Bureau ET-MOWIE-84615-GO-RFB / Procurement of 44 Double Component 3: Project Open - Single Stage - One 2018-11- 2019-02- 2018-11- 2019-02- 2019-01- 2019-04- 2019-01- 2019-07- 2019-03- 2019-09- 2019-09- 2020-06- Cup vehicles for 22 Secondary IDA / 60080 management & institutional Prior Request for Bids 1,800,000.00 1,412,937.01 Completed International Envelope 15 02 20 27 01 15 31 10 07 05 03 29 Cities, Regional Water Bureaus strengthening PMU, and Federal PMU ET-MOWIE-98176-GO-RFB / Supply and Installation Component 2: Sanitation and Equipment for Water Quality Pending water supply services Open - Single Stage - One 2019-03- 2019-03- 2019-04- 2019-05- 2019-07- 2019-11- Laboratory and Training IDA / 60070 Post Request for Bids 1,000,000.00 0.00 Implementati improvement in secondary International Envelope 14 19 30 30 04 01 Center for Mekelle Town Water on cities Supply Project by Mekelle Town Water Supply Office ET-MOWIE-143211-GO-RFB / Procurement of 25 (twenty five ) 10m3 and 8m3 size Component 2: Sanitation and Under vacuum track for 5 towns( water supply services Open - Single Stage - One 2019-11- 2020-08- 2019-11- 2020-09- 2020-01- 2020-11- 2020-02- 2021-04- 2020-03- 2020-09- IDA / 60070 Prior Request for Bids 5,500,000.00 0.00 Implementati Adama,Mekele,Diredewa, improvement in secondary International Envelope 29 19 30 01 14 22 13 23 19 15 on Bahirdar ,and Hawasa) of cities UWSSP-2 By Water Development Commission . ET-MOWIE-156913-GO-RFB / procurement of 44 (forty- Component 2: Sanitation and four) Motorcycles for 22 water supply services Single Stage - One 2020-02- 2020-07- 2020-03- 2020-04- 2020-07- 2020-05- 2020-12- 2020-06- 2020-12- Towns of Urban Water Supply IDA / 60070 Post Request for Bids Open - National 180,000.00 0.00 Canceled improvement in secondary Envelope 12 07 13 12 21 12 23 16 13 and Sanitation project II cities (UWSSP-2) by Water Development Commission ET-MOWIE-166460-GO-DIR / Procurement of IT Equipment (E-video (ten in number) Modem with subscription 4GB Component 3: Project Pending and Fixed Wireless Broadband 2020-03- 2020-04- 2020-05- 2020-06- IDA / 60070 management & institutional Post Direct Selection Direct 3,600.00 0.00 Implementati (WIFI) (3) three apparatuses for 30 04 09 18 strengthening on water Development Commission offices and Staffs will be implemented by WDC ET-MOWIE-166453-GO-RFQ / Procurement of Core i7 7 Component 3: Project Pending (seven) Laptops for Water Request for Single Stage - One 2020-04- 2020-05- 2020-07- IDA / 60070 management & institutional Post Limited 10,937.50 0.00 Implementati Development commission Quotations Envelope 04 30 29 strengthening on Staffs which will be implemented by WDC. ET-MOWIE-168265-GO-RFB / procurement of pipes and Component 2: Sanitation and fittings, water meters and leak Under water supply services Open - Single Stage - One 2020-04- 2020-01- 2020-05- 2020-06- 2021-02- 2020-07- 2021-04- 2020-08- 2020-12- detection equipment for IDA / 60070 Post Request for Bids 907,000.00 0.00 Implementati improvement in secondary International Envelope 30 29 05 04 03 04 29 08 06 Gonder town Water Supply and on cities Sewerage service enterprise by Gonder town WSSE ET-MOWIE-172211-GO-RFQ Component 2: Sanitation and / Procurement of Pipes and water supply services Request for Single Stage - One 2020-05- 2020-07- 2020-07- 2020-07- 2020-08- fittings and water meters for IDA / 60070 Post Limited 75,800.00 60,209.31 Signed improvement in secondary Quotations Envelope 20 06 15 22 14 Arbaminch Town WSSE by cities Arbaminch town WSSE ET-MOWIE-172215-GO-RFQ Component 2: Sanitation and / Procurement of Pipes and water supply services Request for Single Stage - One 2020-05- 2020-06- 2020-07- 2020-07- 2020-08- fittings and water meters for IDA / 60070 Post Limited 75,700.00 61,772.81 Signed improvement in secondary Quotations Envelope 20 29 15 03 14 Wolaita Sodo Town WSSE by cities Wolaita town WSSE ET-MOWIE-172221-GO-RFQ Component 2: Sanitation and / Procurement of Pipes and Pending water supply services Request for Single Stage - One 2020-05- 2020-07- 2020-08- fittings Hawasa Town WSSE by IDA / 60070 Post Limited 75,800.00 0.00 Implementati improvement in secondary Quotations Envelope 20 15 14 Hawasa town WSSE for low on cities income area Page 4 ET-MOWIE-172233-GO-RFQ / Procurement of HDPE Pipes Component 2: Sanitation and Pending and fittings and water meters water supply services Request for Single Stage - One 2020-05- 2020-07- 2020-08- IDA / 60070 Post Limited 75,800.00 0.00 Implementati for Debre Brerhan Town WSSE improvement in secondary Quotations Envelope 20 15 14 on by DebreBerhan town WSSE for cities low income area ET-MOWIE-172236-GO-RFQ Component 2: Sanitation and / Procurement of Pipes and Pending water supply services Request for Single Stage - One 2020-05- 2020-07- 2020-08- fittings for Dessie Town WSSE IDA / 60070 Post Limited 75,700.00 0.00 Implementati improvement in secondary Quotations Envelope 20 15 14 by Dessie town WSSE for low on cities income area ET-MOWIE-172241-GO-RFQ Component 2: Sanitation and / Procurement of Pipes and water supply services Request for Single Stage - One 2020-05- 2020-01- 2020-07- 2020-03- 2020-08- fittings for Gonder Town WSSE IDA / 60070 Post Limited 75,800.00 39,738.87 Signed improvement in secondary Quotations Envelope 23 29 18 17 17 by Gonder town WSSE for low cities income area ET-MOWIE-172244-GO-RFQ Component 2: Sanitation and / Procurement of Pipes and Pending water supply services Request for Single Stage - One 2020-05- 2020-07- 2020-08- fittings for Bahir Dar Town low IDA / 60070 Post Limited 75,800.00 0.00 Implementati improvement in secondary Quotations Envelope 20 15 14 income area WSSE by Bahir Dar on cities town WSSE ET-MOWIE-172245-GO-RFQ / Procurement of HDPE Pipes Component 2: Sanitation and Pending and fittings and water meters water supply services Request for Single Stage - One 2020-05- 2020-07- 2020-08- IDA / 60070 Post Limited 75,690.00 0.00 Implementati for Bishftu Town WSSE by improvement in secondary Quotations Envelope 25 20 19 on Bishftu town WSSE for low cities income area ET-MOWIE-172248-GO-RFQ / Procurement of HDPE Pipes Component 2: Sanitation and Pending and fittings and Water meters water supply services Request for Single Stage - One 2020-05- 2020-07- 2020-08- IDA / 60070 Post Limited 74,980.00 0.00 Implementati for Jimma Town WSSE by improvement in secondary Quotations Envelope 25 20 19 on Jimma town WSSE for low cities income area ET-MOWIE-172256-GO-RFQ / Procurement of pipes and Component 2: Sanitation and Pending fittings, leak detection and water supply services Request for Single Stage - One 2020-05- 2020-07- 2020-09- IDA / 60070 Post Limited 75,800.00 0.00 Implementati water quality test equipment improvement in secondary Quotations Envelope 25 20 18 on for Assela town low income cities area by Assela town WSSE ET-MOWIE-172257-GO-RFQ / Supply and installation of Component 2: Sanitation and Pending pipes and fittings for Mekelle water supply services Request for Single Stage - One 2020-05- 2020-07- 2020-10- IDA / 60070 Post Limited 75,800.00 0.00 Implementati town low income area water improvement in secondary Quotations Envelope 20 15 13 on supply project by Mekelle cities town WSSP ET-MOWIE-172262-GO-RFQ / Procurement of pipes and Component 2: Sanitation and Pending fittings for Gambella town water supply services Request for Single Stage - One 2020-05- 2020-07- 2020-09- IDA / 60070 Post Limited 75,800.00 0.00 Implementati town low income area water improvement in secondary Quotations Envelope 25 20 18 on supply project by Gambella cities town WSSP ET-MOWIE-172263-GO-RFQ Component 2: Sanitation and / Procurement of pipe fittings Pending water supply services Request for Single Stage - One 2020-05- 2020-07- 2020-08- for Asosa town low income IDA / 60070 Post Limited 5,000.00 0.00 Implementati improvement in secondary Quotations Envelope 25 20 19 area water supply project by on cities Asosa WSSE ET-MOWIE-172265-GO-RFQ Component 2: Sanitation and / procurement of pipes and Pending water supply services Request for Single Stage - One 2020-05- 2020-07- 2020-09- fittings for Harar town low IDA / 60070 Post Limited 69,500.00 0.00 Implementati improvement in secondary Quotations Envelope 25 20 18 income area water supply on cities project by Harar town WSSE ET-MOWIE-172275-GO-RFQ Component 2: Sanitation and / supply of pipes and fittings Pending water supply services Request for Single Stage - One 2020-05- 2020-07- 2020-09- for Semera Logia town low IDA / 60070 Post Limited 72,500.00 0.00 Implementati improvement in secondary Quotations Envelope 31 26 24 income area water supply on cities project by Semera Logia WSSE ET-MOWIE-172933-GO-RFQ / Procurement of pipes and Component 2: Sanitation and Pending fittings for Dire Dewa town water supply services Request for Single Stage - One 2020-05- 2020-07- 2020-09- IDA / 60070 Post Limited 75,800.00 0.00 Implementati low income area water supply improvement in secondary Quotations Envelope 30 25 23 on project by Dire Dewa Town cities WSSE ET-MOWIE-168264-GO-RFB / Procurement of Water meters, Bulk flow meters, Component 2: Sanitation and Under pipes and fittings and leak water supply services Open - Single Stage - One 2020-05- 2021-03- 2020-06- 2020-07- 2020-08- 2020-09- 2021-01- IDA / 60070 Post Request for Bids 1,565,000.00 0.00 Implementati detection Equipments for Jima improvement in secondary International Envelope 28 16 02 02 01 05 03 on Town Water Supply and cities Sewerage Enterprise by Jima town WSSE ET-MOWIE-174562-GO-RFQ / Procurement of Aluminium sulfate for covid-19 Component 2: Sanitation and intervention in Gmbella water supply services Request for Single Stage - One 2020-05- 2020-07- 2020-07- IDA / 60070 Post Limited 46,154.00 0.00 Canceled towns health stations, improvement in secondary Quotations Envelope 31 05 19 hospitals, isolation centers cities and areas with acute waster supply shortage by WDC ET-MOWIE-174573-GO-RFQ Component 2: Sanitation and / Procurement of filter media water supply services Request for Single Stage - One 2020-05- 2020-07- 2020-07- Sand for Gambella town Water IDA / 60070 Post Limited 46,154.00 0.00 Canceled improvement in secondary Quotations Envelope 31 05 19 Treatment plant by Gambella cities Town Water Utility ET-MOWIE-175708-GO-RFQ / Procurement of Pipes and Component 2: Sanitation and Pending fittings for Adama town low water supply services Request for Single Stage - One 2020-06- 2020-07- 2020-08- IDA / 60070 Post Limited 76,900.00 0.00 Implementati income area water supply improvement in secondary Quotations Envelope 10 15 14 on project by Adama town Water cities Utility ET-MOWIE-43018-GO-RFB / Procurement of 44 vehicles(double Cabins) for secondary city utilities, Component 3: Project 2018-06- 2018-06- 2018-07- 2018-11- Regional Water Bureaus and 2 IDA / 60070 management & institutional Prior Direct Selection Direct 1,800,000.00 0.00 Canceled 20 25 30 27 Vehicles( double Cabins) for strengthening Ministry PIU by the Ministry of Water Irrigation and Electricity through UNOPS ET-MOWIE-181638-GO-RFB / Procurement of Pipes and Fittings for covid-19 Component 2: Sanitation and Under intervention in 13 towns water supply services Open - Single Stage - One 2020-07- 2020-09- 2020-07- 2020-09- 2020-08- 2020-08- 2020-09- 2020-12- IDA / 60070 Post Request for Bids 573,766.00 0.00 Implementati health stations, hospitals, improvement in secondary International Envelope 06 04 11 08 01 15 05 04 on isolation centers and areas cities with acute waster supply shortage by WDC ET-MOWIE-174564-GO-RFQ / Procurement of Water Component 2: Sanitation and treatment Chemicals and water supply services Request for Single Stage - One 2020-07- 2020-08- 2020-08- Reagents for covid-19 IDA / 60070 Post Limited 110,769.00 0.00 Canceled improvement in secondary Quotations Envelope 11 15 29 intervention in Bonga town cities to areas with acute waster supply shortage by WDC ET-MOWIE-181653-GO-RFQ Component 2: Sanitation and Pending / Procurement of pipe fittings water supply services Request for Single Stage - One 2020-07- 2020-08- 2020-09- IDA / 60070 Post Limited 2,700.00 0.00 Implementati for Harar town water supply improvement in secondary Quotations Envelope 11 29 12 on project by Harar town cities ET-MOWIE-181625-GO-RFB / Procurement of Electromechanical Equipment (59 submersible water pumps Component 2: Sanitation and (lot I) ,11 surface pumps (lot Under water supply services Open - Single Stage - One 2020-07- 2020-09- 2020-07- 2020-09- 2020-08- 2020-10- 2020-08- 2020-09- 2020-12- II) ,2 Surge Vessels (Lot III) IDA / 60070 Post Request for Bids 4,139,530.00 0.00 Implementati improvement in secondary International Envelope 08 04 13 08 03 21 17 07 06 and 29 Generators (lot IV) for on cities 25 towns covid-19 intervention in acute water supply shortage areas by WDC. ET-MOWIE-183159-GO-DIR / Component 2: Sanitation and Procurement of filter media Pending water supply services 2020-07- 2020-07- 2020-08- 2020-09- Sand for Gambella town Water IDA / 60070 Post Direct Selection Direct 46,154.00 0.00 Implementati improvement in secondary 15 20 10 09 Treatment plant by Gambella on cities Town Water Utility Page 5 ET-MOWIE-185679-GO-RFQ / Procurement of Office Equipment (#12 laptop Component 3: Project Pending computers, #1 Led Projector, Request for Single Stage - One 2020-08- 2020-10- 2020-10- IDA / 60070 management & institutional Post Limited 50,000.00 0.00 Implementati #2 Heavy duty color printers, Quotations Envelope 10 05 20 strengthening on #1 scanner and #1 heavy duty photo copy machine) for WDC PIU by WDC ET-MOWIE-208762-GO-RFB / Procurement of pipes and Component 2: Sanitation and Pending fitting for expansion of water water supply services Single Stage - One 2020-12- 2020-12- 2021-01- 2021-02- 2021-03- 2021-05- IDA / 60070 Post Request for Bids Open - National 132,000.00 0.00 Implementati supply system to low income improvement in secondary Envelope 21 26 25 09 02 01 on area of Mekelle town by cities Mekelle town WSS ET-MOWIE-208765-GO-RFQ / Procurement of pipes and Component 2: Sanitation and Pending fitting for expansion of water water supply services Request for Single Stage - One 2021-01- 2021-03- 2021-03- IDA / 60070 Post Limited 65,000.00 0.00 Implementati supply system for unserved improvement in secondary Quotations Envelope 04 01 31 on low income area by Bahir Dar cities WSS ET-MOWIE-208767-GO-RFB / Procurement of pipes and Component 2: Sanitation and Pending fittings for expansion of water water supply services Single Stage - One 2020-12- 2020-12- 2021-01- 2021-02- 2021-03- 2021-04- IDA / 60070 Post Request for Bids Open - National 132,000.00 0.00 Implementati supply system for unserved improvement in secondary Envelope 21 26 25 09 02 01 on low income are for Adama cities town by Adama town WSSE ET-MOWIE-208769-GO-RFB / Procurement of pipes and Component 2: Sanitation and Pending fittings for expansion of water water supply services Single Stage - One 2020-12- 2020-12- 2021-01- 2021-02- 2021-03- 2021-05- IDA / 60070 Post Request for Bids Open - National 132,000.00 0.00 Implementati supply system for unserved improvement in secondary Envelope 22 27 26 10 03 02 on low income area of Hawasa cities town by Hawasa town WSSE ET-MOWIE-208770-GO-RFB / Procurement of pipes and Component 2: Sanitation and Pending fittings for expansion of water water supply services Single Stage - One 2020-12- 2020-12- 2021-01- 2021-02- 2021-03- 2021-05- IDA / 60070 Post Request for Bids Open - National 132,000.00 0.00 Implementati supply system for unserved improvement in secondary Envelope 22 27 26 10 03 02 on low income area of Dire Dewa cities town by Dire Dewa town WSSE ET-MOWIE-208774-GO-RFQ / procurement of pumps and Component 2: Sanitation and Pending generators for Debre Birhan water supply services Request for Single Stage - One 2021-01- 2021-02- 2021-03- IDA / 60070 Post Limited 79,000.00 0.00 Implementati town Water Supply Project by improvement in secondary Quotations Envelope 10 21 23 on Debre Birhan town Dar Town cities WSSE ET-MOWIE-220715-GO-RFB / Procurement of operational service improvement equipment's under two lots ( Component 2: Sanitation and lot I Water Meters, lot II leak water supply services Open - Single Stage - One 2021-03- 2021-03- 2021-04- 2021-05- 2021-06- 2021-11- IDA / 60070 Prior Request for Bids 8,900,000.00 0.00 Under Review detection equipment, welding improvement in secondary International Envelope 10 15 26 26 30 27 machines, Bulk flow meters, cities and test bench) for improvement of 22 town Water supply projects by WDC ET-MOWIE-220716-GO-RFB / procurement of pipes and Component 2: Sanitation and Under fittings for 22 towns water water supply services Open - Single Stage - One 2021-03- 2021-06- 2021-03- 2021-06- 2021-04- 2021-05- 2021-06- 2021-11- IDA / 60070 Prior Request for Bids 2,800,000.00 0.00 Implementati supply projects operational improvement in secondary International Envelope 10 04 15 21 26 26 30 27 on efficiency improvement by cities WDC ET-MOWIE-221971-GO-DIR / Procurement of Water Component 2: Sanitation and treatment Chemicals and Pending water supply services 2021-03- 2021-03- 2021-04- 2021-06- Reagents for covid-19 IDA / 60070 Post Direct Selection Direct 110,769.00 0.00 Implementati improvement in secondary 01 06 10 09 intervention in Bonga town on cities to areas with acute waster supply shortage by WDC ET-MOWIE-221972-GO-DIR / Procurement of Aluminium sulfate for covid-19 Component 2: Sanitation and Pending intervention in Gmbella towns water supply services 2021-03- 2021-03- 2021-04- 2021-06- IDA / 60070 Post Direct Selection Direct 46,154.00 0.00 Implementati health stations, hospitals, improvement in secondary 01 06 10 09 on isolation centers and areas cities with acute waster supply shortage by WDC ET-MOWIE-221973-GO-UN / Procurement of Electromechanical Equipment Component 2: Sanitation and Under (59 submersible water pumps water supply services UN Agencies 2021-03- 2021-04- 2021-03- 2021-04- 2021-04- 2021-07- IDA / 60070 Post Direct 1,500,000.00 0.00 Implementati (lot I) and 11 surface pumps improvement in secondary (Direct) 02 17 07 17 11 10 on (lot II) ) for 25 towns covid- cities 19 intervention in acute water supply shortage ET-MOWIE-228528-GO-RFB- RE-BID / Procurement of 44 Component 3: Project Pending Motorcycles for 22 Towns of Single Stage - One 2021-04- 2021-05- 2021-06- 2021-06- 2021-07- 2021-11- IDA / 60070 management & institutional Post Request for Bids Open - National 150,000.00 0.00 Implementati Urban Water Supply and Envelope 30 05 04 19 24 21 strengthening on Sanitation Project II (UWSSP-2) by WDC (Re-bid) ET-MOWIE-232948-GO-DIR / Procurement of Electromechanical Equipment lot I (# 4 water pump motors, Component 2: Sanitation and #6 surface pumps, #7 Pending water supply services 2021-05- 2021-05- 2021-07- 2021-10- submersible pumps), lot II (# IDA / 60070 Post Direct Selection Direct 1,179,000.00 0.00 Implementati improvement in secondary 25 30 04 02 12 Generators) lot III control on cities panel parts for Mekelle and Adegarat towns water utilities emergency situation by WDC from UNOPS. ET-MOWIE-232953-GO-RFQ / Procurement of water quality Component 2: Sanitation and Pending chemicals and instruments for water supply services Request for Single Stage - One 2021-06- 2021-08- 2021-08- IDA / 60070 Post Limited 70,000.00 0.00 Implementati Mekelle town Water supply improvement in secondary Quotations Envelope 15 10 25 on service emergency situation cities by WDC ET-MOWIE-232956-GO-RFQ Component 2: Sanitation and / Procurement of riser pipes Pending water supply services Request for Single Stage - One 2021-05- 2021-07- 2021-08- for Mekelle town water supply IDA / 60070 Post Limited 78,050.00 0.00 Implementati improvement in secondary Quotations Envelope 17 12 11 service emergency situation on cities by WDC ET-MOWIE-232961-GO-RFQ / Procurement of Office Component 2: Sanitation and Pending Furniture (#72 chairs and #25 water supply services Request for Single Stage - One 2021-05- 2021-07- 2021-09- IDA / 60070 Post Limited 28,000.00 0.00 Implementati tables) for Adegarat town improvement in secondary Quotations Envelope 25 20 18 on water utility by Tigray Region cities Water Bureau ET-MOWIE-232977-GO-RFQ Component 2: Sanitation and / Procurement of #2 Pending water supply services Request for Single Stage - One 2021-05- 2021-07- 2021-08- Generator batters for Mekelle IDA / 60070 Post Limited 1,000.00 0.00 Implementati improvement in secondary Quotations Envelope 26 21 05 town water utility by Mekelle on cities town utility ET-MOWIE-232959-GO-RFQ / procurement of Office equipment lot I (#48 desk top Component 2: Sanitation and Pending computers and #13 laptop water supply services Request for Single Stage - One 2021-06- 2021-08- 2021-09- IDA / 60070 Post Limited 143,000.00 0.00 Implementati computers) and lot II (#1 fax improvement in secondary Quotations Envelope 20 15 14 on machine, #2 Scanners and # 2 cities printers) for Adegarat town utility by WDC. NON CONSULTING SERVICES Activity Reference No. / Draft Pre- Draft Bidding Bid Evaluation Report Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Prequalification Specific Procurement Bidding Documents Proposal Submission Description Component Review Type Method qualification Document / and Recommendation Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Documents Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-MOWIE-174570-NC-RFQ Component 2: Sanitation and / Procurement of maintenance Pending water supply services Request for Single Stage - One 2020-05- 2020-07- 2020-07- service of Generators and IDA / 60070 Post Limited 30,769.00 0.00 Implementati improvement in secondary Quotations Envelope 31 05 19 transformer for shire town by on cities shire town Water Utility CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Page 6 Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-MOWIE-43244-CS-QCBS / Consultancy service for Development of an integrated Component 2: Sanitation and City Wide Sanitation plan and water supply services Quality And Cost- 2018-07- 2018-05- 2018-07- 2018-03- 2018-07- 2018-12- 2018-09- 2018-01- 2018-11- 2019-04- 2018-12- 2019-07- 2019-09- Feasibility Study and Detail IDA / 60070 Post Open - National 250,000.00 214,456.00 Signed 2018-04-20 improvement in secondary Based Selection 17 11 01 03 29 31 27 15 08 27 20 04 16 Design of Waste Water cities Management System for Harari town by Harari Town water supply and sewerage service ET-MOWIE-50559-CS-QCBS / Consultancy Service for Establishment of Urban Water Component 2: Sanitation and Supply and Waste Water water supply services Quality And Cost- Under 2018-07- 2018-09- 2018-09- 2018-10- 2018-12- 2019-01- 2020-01- IDA / 60070 Post Open - National 200,000.00 0.00 2018-06-20 Management Service improvement in secondary Based Selection Implementation 20 02 30 30 04 08 08 Regulation in Ethiopia by cities Ministry of Water Irrigation and Electricity ET-MOWIE-43193-CS-QCBS / Consultancy service for Development of an integrated City Wide Sanitation plan and Component 2: Sanitation and Feasibility Study and Detail water supply services Quality And Cost- Open - 2018-08- 2018-07- 2018-10- 2018-08- 2019-06- 2018-09- 2019-09- 2018-10- 2020-02- 2018-11- 2020-09- 2018-12- 2020-10- 2019-09- IDA / 60070 Prior 600,000.00 995,043.88 Signed 2018-06-20 Design of Waste Water improvement in secondary Based Selection International 10 11 03 24 27 21 02 21 12 25 03 30 01 26 Management System for cities Jimma and Nekemte Towns by Oromia Water Mineral and Energy Bureau ET-MOWIE-43212-CS-QCBS / Consultancy Service for Development of an Integrated Component 2: Sanitation and City Wide Sanitation plan and water supply services Quality And Cost- 2018-05- 2018-07- 2018-07- 2018-09- 2018-11- 2018-12- 2019-09- IDA / 60070 Post Open - National 250,000.00 0.00 Canceled 2018-04-20 Feasibility Study and Detail improvement in secondary Based Selection 11 01 29 27 08 20 16 Design for Asella Town WSSS cities by Asella Town water supply and sewerage service ET-MOWIE-43209-CS-QCBS / Consultancy Service for Development of an Integrated Component 2: Sanitation and City Wide Sanitation plan and water supply services Quality And Cost- Under 2018-04- 2018-05- 2018-06- 2018-08- 2018-10- 2018-11- 2019-08- IDA / 60070 Post Open - National 500,000.00 0.00 2018-03-20 Feasibility Study and Detail improvement in secondary Based Selection Implementation 10 31 28 27 08 19 16 Design for Sodo and cities Arbaminch Towns by SNNPR Water Bureau ET-MOWIE-43208-CS-QCBS / Consultancy Service for Development of an Integrated Component 2: Sanitation and City Wide Sanitation plan and water supply services Quality And Cost- 2018-04- 2018-05- 2018-06- 2018-08- 2018-10- 2018-11- 2019-08- IDA / 60070 Post Open - National 250,000.00 0.00 Canceled 2018-03-20 Feasibility Study and Detail improvement in secondary Based Selection 10 31 28 27 01 12 09 Design for Sodo Town WSSS by cities Sodo Town water supply and sewerage service ET-MOWIE-43214-CS-QCBS / Consultancy service for Development of an integrated Component 2: Sanitation and City Wide Sanitation plan and water supply services Quality And Cost- 2018-08- 2018-05- 2018-07- 2018-08- 2018-07- 2019-03- 2018-09- 2019-06- 2018-11- 2019-09- 2018-12- 2019-09- 2019-09- Feasibility Study and Detail IDA / 60070 Post Open - National 250,000.00 217,285.63 Signed 2018-04-20 improvement in secondary Based Selection 01 11 01 01 29 09 27 03 08 18 20 27 16 Design of Waste Water cities Management System for Adegrat town by Tigray Region Water Bureau ET-MOWIE-43206-CS-QCBS / Consultancy service for Development of an integrated City Wide Sanitation plan and Component 2: Sanitation and Feasibility Study and Detail water supply services Quality And Cost- 2018-05- 2018-07- 2018-07- 2018-09- 2018-11- 2018-12- 2019-09- IDA / 60070 Post Open - National 250,000.00 0.00 Canceled 2018-04-20 Design of Waste Water improvement in secondary Based Selection 11 01 29 27 08 20 16 Management System for cities Dessie town by Dessie Town water supply and sewerage service ET-MOWIE-43200-CS-QCBS / Consultancy service for Development of an integrated City Wide Sanitation plan and Component 2: Sanitation and Feasibility Study and Detail water supply services Quality And Cost- 2018-05- 2018-07- 2018-07- 2018-09- 2018-11- 2018-12- 2019-09- IDA / 60070 Post Open - National 250,000.00 0.00 Canceled 2018-04-20 Design of Waste Water improvement in secondary Based Selection 11 01 29 27 08 20 16 Management System for cities Gambella town by Gambella Town water supply and sewerage service ET-MOWIE-43198-CS-QCBS / Consultancy service for Development of an integrated City Wide Sanitation plan and Component 2: Sanitation and Feasibility Study and Detail water supply services Quality And Cost- 2018-05- 2018-06- 2018-07- 2018-09- 2018-11- 2018-12- 2019-09- IDA / 60070 Post Open - National 250,000.00 0.00 Canceled 2018-04-20 Design of Waste Water improvement in secondary Based Selection 11 24 22 20 01 13 09 Management System for cities Nekemet town by Nekemet Town water supply and sewerage service ET-MOWIE-43237-CS-QCBS / Consultancy service for Development of an integrated City Wide Sanitation plan and Component 2: Sanitation and Feasibility Study and Detail water supply services Quality And Cost- 2018-05- 2018-07- 2018-07- 2018-09- 2018-11- 2018-12- 2019-09- IDA / 60070 Post Open - National 250,000.00 0.00 Canceled 2018-04-20 Design of Waste Water improvement in secondary Based Selection 11 01 29 27 08 20 16 Management System for cities Jigjiga town by Jigijiga Town water supply and sewerage service ET-MOWIE-43239-CS-QCBS / Consultancy service for Development of an integrated City Wide Sanitation plan and Component 2: Sanitation and Feasibility Study and Detail water supply services Quality And Cost- 2018-05- 2018-07- 2018-07- 2018-09- 2018-11- 2018-12- 2019-09- IDA / 60070 Post Open - National 250,000.00 0.00 Canceled 2018-04-20 Design of Waste Water improvement in secondary Based Selection 11 01 29 27 08 20 16 Management System for cities Shashemene town by Shashemene Town water supply and sewerage service ET-MOWIE-43216-CS-QCBS / Consultancy service for Development of an integrated City Wide Sanitation plan and Component 2: Sanitation and Feasibility Study and Detail water supply services Quality And Cost- 2018-05- 2018-07- 2018-07- 2018-09- 2018-11- 2018-12- 2019-09- IDA / 60070 Post Open - National 250,000.00 0.00 Canceled 2018-04-20 Design of Waste Water improvement in secondary Based Selection 11 01 29 27 08 20 16 Management System for cities Semera town by Semera Town water supply and sewerage service ET-MOWIE-43241-CS-QCBS / Consultancy service for Development of an integrated City Wide Sanitation plan and Component 2: Sanitation and Feasibility Study and Detail water supply services Quality And Cost- 2018-05- 2018-07- 2018-07- 2018-09- 2018-11- 2018-12- 2019-09- IDA / 60070 Post Open - National 250,000.00 0.00 Canceled 2018-04-20 Design of Waste Water improvement in secondary Based Selection 11 01 29 27 08 20 16 Management System for cities Bishoftu town by Bishoftu Town water supply and sewerage service ET-MOWIE-43059-CS-QCBS / Consultancy service for Development of an integrated City Wide Sanitation plan and Component 2: Sanitation and Feasibility Study and Detail water supply services Quality And Cost- 2018-05- 2018-07- 2018-07- 2018-09- 2018-11- 2018-12- 2019-09- IDA / 60070 Post Open - National 250,000.00 0.00 Canceled 2018-04-20 Design of Waste Water improvement in secondary Based Selection 11 01 29 27 08 20 16 Management System for cities Deghabur town by Deghabur Town water supply and sewerage service ET-MOWIE-43248-CS-QCBS / Consultancy service for Development of an integrated City Wide Sanitation plan and Component 2: Sanitation and Feasibility Study and Detail water supply services Quality And Cost- 2018-05- 2018-07- 2018-07- 2018-09- 2018-11- 2018-12- 2019-09- IDA / 60070 Post Open - National 250,000.00 0.00 Canceled 2018-04-20 Design of Waste Water improvement in secondary Based Selection 11 01 29 27 08 20 16 Management System for cities Arbaminch town by Arbaminch Town water supply and sewerage service Page 7 ET-MOWIE-43203-CS-QCBS / Consultancy service for Development of an integrated City Wide Sanitation plan and Component 2: Sanitation and Feasibility Study and Detail water supply services Quality And Cost- 2018-05- 2018-07- 2018-07- 2018-09- 2018-11- 2018-12- 2019-09- IDA / 60070 Post Open - National 250,000.00 0.00 Canceled 2018-04-20 Design of Waste Water improvement in secondary Based Selection 11 01 29 27 08 20 16 Management System for cities Gonder town by Gonder Town water supply and sewerage service ET-MOWIE-65731-CS-QCBS / Consultancy service for Development of an integrated City Wide Sanitation plan and Component 2: Sanitation and Feasibility Study and Detail water supply services Quality And Cost- Open - 2018-08- 2018-07- 2018-09- 2018-08- 2019-01- 2018-09- 2019-03- 2018-10- 2019-08- 2018-11- 2019-12- 2018-12- 2019-12- 2019-09- IDA / 60080 Prior 900,000.00 1,246,690.99 Signed 2018-06-20 Design of Waste Water improvement in secondary Based Selection International 06 11 04 24 14 21 05 21 30 25 08 30 18 26 Management System for cities Gambella, Semera and Asosa Towns by Ministry of Water Irrigation and Electricity ET-MOWIE-65735-CS-QCBS / Consultancy service for Development of an integrated City Wide Sanitation plan and Component 2: Sanitation and Feasibility Study and Detail water supply services Quality And Cost- Open - Under 2018-08- 2018-07- 2018-10- 2018-09- 2019-08- 2018-09- 2019-11- 2018-10- 2020-02- 2018-12- 2020-09- 2019-01- 2019-10- Design of Waste Water IDA / 60080 Prior 900,000.00 0.00 2018-06-28 improvement in secondary Based Selection International Implementation 10 19 05 01 14 29 12 29 26 03 22 07 04 Management System for cities Asella, Shashemene and Bishoftu towns by Oromia Water, Mineral and Energy Bureau ET-MOWIE-65737-CS-QCBS / Consultancy service for Development of an integrated City Wide Sanitation plan and Component 2: Sanitation and Feasibility Study and Detail water supply services Quality And Cost- Open - 2018-08- 2018-07- 2018-10- 2018-09- 2019-06- 2018-09- 2019-09- 2018-10- 2019-12- 2018-12- 2020-06- 2019-01- 2020-08- 2019-10- IDA / 60080 Prior 900,000.00 1,163,667.22 Signed 2018-06-28 Design of Waste Water improvement in secondary Based Selection International 10 19 14 01 27 29 17 29 08 03 02 07 21 04 Management System for cities Gonder, Dessie and Debreberhan towns by Amehara Water Bureau ET-MOWIE-65751-CS-QCBS / Consultancy service for Development of an integrated Component 2: Sanitation and City Wide Sanitation plan and water supply services Quality And Cost- Open - Under 2018-08- 2018-07- 2018-10- 2018-08- 2020-02- 2018-09- 2020-05- 2018-10- 2020-12- 2018-11- 2021-02- 2018-12- 2019-09- Feasibility Study and Detail IDA / 60080 Prior 600,000.00 0.00 2018-06-20 improvement in secondary Based Selection International Implementation 10 11 17 24 16 21 21 21 16 25 22 30 26 Design of Waste Water cities Management System for Sodo and Arbaminch Towns by SNNPR Water Bureau ET-MOWIE-65753-CS-QCBS / Consultancy service for Development of an integrated City Wide Sanitation plan and Component 2: Sanitation and Feasibility Study and Detail water supply services Quality And Cost- Open - 2018-08- 2018-07- 2018-10- 2018-08- 2019-07- 2018-09- 2019-09- 2018-10- 2019-10- 2018-12- 2020-05- 2019-01- 2020-06- 2019-10- IDA / 60080 Prior 600,000.00 1,279,278.48 Signed 2018-06-26 Design of Waste Water improvement in secondary Based Selection International 06 17 05 30 16 27 05 27 31 01 30 05 30 02 Management System for Jijiga cities and Deghabur Towns by Somali Region Water Resource Development Bureau ET-MOWIE-43213-CS-QCBS / Consultancy Service for Development of an Integrated Component 2: Sanitation and City Wide Sanitation plan and water supply services Quality And Cost- 2018-05- 2018-07- 2018-07- 2018-09- 2018-11- 2018-12- 2019-09- IDA / 60070 Post Open - National 250,000.00 0.00 Canceled 2018-04-20 Feasibility Study and Detail improvement in secondary Based Selection 11 01 29 27 08 20 16 Design for Aossosa Town cities WSSS by Assosa Town water supply and sewerage service ET-MOWIE-55840-CS-QCBS / Procurement of re-innovation Component 2: Sanitation and of Enterprise level Information water supply services Quality And Cost- Pending 2018-07- 2018-08- 2018-09- 2018-10- 2018-11- 2018-12- 2019-12- IDA / 60070 Post Open - National 250,000.00 0.00 2018-06-20 Management System by improvement in secondary Based Selection Implementation 11 24 21 21 25 30 30 Mekele Town Water Supply cities and Sewerage Service ET-MOWIE-43218-CS-QCBS / Consultancy service for Component 2: Sanitation and Development of an integrated water supply services Quality And Cost- 2018-04- 2018-05- 2018-06- 2018-08- 2018-10- 2018-11- 2019-08- Town Sanitation plan for Dire IDA / 60070 Post Open - National 200,000.00 0.00 Canceled 2018-03-20 improvement in secondary Based Selection 10 31 28 27 08 19 16 Dewa town by Dire Dawa cities Town water supply and sewerage service ET-MOWIE-43231-CS-QCBS / Consultancy service for Component 2: Sanitation and Development of an integrated water supply services Quality And Cost- 2018-04- 2018-05- 2018-06- 2018-08- 2018-10- 2018-11- 2019-08- Town Sanitation plan for IDA / 60070 Post Open - National 200,000.00 0.00 Canceled 2018-03-20 improvement in secondary Based Selection 10 31 28 27 01 12 09 Adama town by Adama Town cities water supply and sewerage service ET-MOWIE-43234-CS-QCBS / Consultancy service for Component 2: Sanitation and Development of an integrated water supply services Quality And Cost- 2018-04- 2018-05- 2018-06- 2018-08- 2018-10- 2018-11- 2019-08- Town Sanitation plan for IDA / 60070 Post Open - National 200,000.00 0.00 Canceled 2018-03-20 improvement in secondary Based Selection 10 31 28 27 01 12 09 Hawassa town by Hawassa cities Town water supply and sewerage service ET-MOWIE-43227-CS-QCBS / Consultancy service for Component 2: Sanitation and Development of an integrated water supply services Quality And Cost- 2018-04- 2018-05- 2018-06- 2018-08- 2018-10- 2018-11- 2019-08- Town Sanitation plan for IDA / 60070 Post Open - National 200,000.00 0.00 Canceled 2018-03-20 improvement in secondary Based Selection 10 31 28 27 08 19 16 Mekelle town by Mekelle Town cities water supply and sewerage service ET-MOWIE-43222-CS-QCBS / Consultancy service for Component 2: Sanitation and Development of an integrated water supply services Quality And Cost- 2018-05- 2018-07- 2018-07- 2018-08- 2018-10- 2018-11- 2019-08- City Wide Sanitation plan for IDA / 60070 Post Open - National 200,000.00 0.00 Canceled 2018-04-20 improvement in secondary Based Selection 11 01 29 28 09 20 17 Bahir Dar town by Bahir Dar cities Town water supply and sewerage service ET-MOWIE-77764-CS-QCBS / consultancy service for Component 2: Sanitation and preparation of business plan water supply services Quality And Cost- 2018-10- 2018-12- 2018-12- 2019-01- 2019-03- 2019-04- 2019-08- for Jima, Nekemte and IDA / 60070 Post Open - National 110,000.00 0.00 Canceled 2018-09-27 improvement in secondary Based Selection 18 01 29 28 04 08 06 Bishoftu Towns Water Supply cities project by Oromia Water, Mineral and Energy Bureau ET-MOWIE-75929-CS-QCBS / Selection and employment of consultant for situational Component 2: Sanitation and assessment and development water supply services Quality And Cost- 2018-10- 2018-12- 2018-12- 2019-01- 2019-03- 2019-04- 2019-08- IDA / 60070 Post Open - National 110,000.00 0.00 Canceled 2018-09-27 of NRW reduction and improvement in secondary Based Selection 18 01 29 28 04 08 06 management interventions for cities Jigjiga and Deghabur towns by Somali Region Water Bureau ET-MOWIE-75924-CS-QCBS / Selection and employment of consultant for situational Component 2: Sanitation and assessment and development water supply services Quality And Cost- 2018-10- 2018-12- 2018-12- 2019-01- 2019-03- 2019-04- 2019-10- of NRW reduction and IDA / 60070 Post Open - National 110,000.00 0.00 Canceled 2018-09-27 improvement in secondary Based Selection 18 01 29 28 04 08 05 management interventions for cities Bahirdar, D/berhan and Dessie towns by Amhara Water Bureau ET-MOWIE-77752-CS-QCBS / Consultancy service for Component 2: Sanitation and preparation of business plan water supply services Quality And Cost- 2018-10- 2018-12- 2018-12- 2019-01- 2019-03- 2019-04- 2019-08- for Mekele and Adegrat towns IDA / 60070 Post Open - National 110,000.00 0.00 Canceled 2018-09-27 improvement in secondary Based Selection 18 01 29 28 04 08 06 Water supply and Sewerage cities authorities by Tigray Region Water Bureau ET-MOWIE-75935-CS-QCBS / Selection and employment of consultant for situational Component 2: Sanitation and assessment and development water supply services Quality And Cost- 2018-10- 2018-12- 2019-01- 2019-02- 2019-03- 2019-04- 2019-07- IDA / 60070 Post Open - National 50,000.00 0.00 Canceled 2018-10-02 of NRW reduction and improvement in secondary Based Selection 23 06 03 02 09 13 12 management interventions for cities Harari town by Harari water supply and sewerage service Page 8 ET-MOWIE-77885-CS-QCBS / Consultancy Service for Component 2: Sanitation and preparation of Business plan water supply services Quality And Cost- 2018-10- 2018-12- 2019-01- 2019-02- 2019-03- 2019-04- 2019-08- for Adama, Asella and IDA / 60070 Post Open - National 110,000.00 0.00 Canceled 2018-10-05 improvement in secondary Based Selection 26 09 06 05 12 16 14 Shashamene towns by Oromia cities Water Mineral and Energy Bureau ET-MOWIE-75932-CS-QCBS / Selection and employment of consultant for Consultancy service for preparation of Component 2: Sanitation and business plan and NRW water supply services Quality And Cost- Pending 2018-12- 2019-01- 2019-02- 2019-03- 2019-04- 2019-05- 2019-09- IDA / 60070 Post Open - National 130,000.00 0.00 2018-11-15 Reduction strategic plan and improvement in secondary Based Selection Implementation 06 19 16 18 22 27 24 implementation mechanisms cities for Soda, Hawasa and Arbamich towns by SNNP reginal water bureaus ET-MOWIE-75927-CS-QCBS / Selection and employment of consultant for situational Component 2: Sanitation and assessment and development water supply services Quality And Cost- 2018-10- 2018-12- 2018-12- 2019-01- 2019-03- 2019-04- 2019-10- IDA / 60070 Post Open - National 110,000.00 0.00 Canceled 2018-09-27 of NRW reduction and improvement in secondary Based Selection 18 01 29 28 04 08 05 management interventions for cities Gambella, Semera and Asosa towns by MoWIE ET-MOWIE-84640-CS-QCBS / Component 2: Sanitation and Consultancy Service for water supply services Quality And Cost- Open - Under 2018-12- 2018-12- 2019-02- 2019-02- 2019-11- 2019-03- 2020-04- 2019-04- 2020-06- 2019-05- 2021-06- 2019-06- 2020-06- Preparation of Urban Water IDA / 60080 Prior 540,000.00 0.00 2018-11-30 improvement in secondary Based Selection International Implementation 05 21 14 03 27 03 03 02 09 07 01 11 10 Supply Study and Design cities Criteria ET-MOWIE-77886-CS-QCBS / Component 2: Sanitation and Consultancy Service for water supply services Quality And Cost- Under 2019-09- 2018-12- 2019-01- 2019-02- 2019-03- 2019-04- 2019-06- 2019-09- preparation of Business plan IDA / 60070 Post Open - National 50,000.00 0.00 2018-11-20 improvement in secondary Based Selection Implementation 04 11 24 21 23 27 01 29 for Dire Dewa town by cities Diredewa town water utility ET-MOWIE-75898-CS-QCBS / Selection and Employment of Consultant for Development of Billing and Accounting System, Customer Care, FM Component 3: Project Quality And Cost- 2018-12- 2019-01- 2019-02- 2019-03- 2019-04- 2019-05- 2019-11- improvement, network IDA / 60070 management & institutional Post Open - National 51,000.00 0.00 Canceled 2018-11-15 Based Selection 06 19 16 18 22 27 23 management and and capacity strengthening Building for Deghabur and Jigjiga towns by Somali Region Water Resource Development Bureau ET-MOWIE-75900-CS-QCBS / Selection and Employment of Consultant for Development of Billing and Accounting Component 3: Project System, Customer Care, FM Quality And Cost- 2018-12- 2019-01- 2019-02- 2019-03- 2019-04- 2019-05- 2019-11- IDA / 60070 management & institutional Post Open - National 51,000.00 0.00 Canceled 2018-11-15 improvement, network Based Selection 06 19 16 18 22 27 23 strengthening management and and capacity Building for Adegrat and Mekelle towns by Tigray Region Water Bureau ET-MOWIE-75896-CS-QCBS / Selection and Employment of Consultant for Development of Billing and Accounting Component 3: Project System, Customer Care, FM Quality And Cost- 2018-12- 2019-01- 2019-02- 2019-03- 2019-04- 2019-05- 2019-11- IDA / 60070 management & institutional Post Open - National 76,000.00 0.00 Canceled 2018-11-15 improvement, network Based Selection 06 19 16 18 22 27 23 strengthening management and and capacity Building for Bahirdar, Gonder, Debrebrihan and Dessie towns by Amahara Water Bureau ET-MOWIE-75897-CS-QCBS / Selection and Employment of Consultant for Development of Billing and Accounting Component 3: Project System, Customer Care, FM Quality And Cost- 2018-12- 2019-01- 2019-02- 2019-03- 2019-04- 2019-05- 2019-11- IDA / 60070 management & institutional Post Open - National 76,000.00 0.00 Canceled 2018-11-15 improvement, network Based Selection 06 19 16 18 22 27 23 strengthening management and and capacity Building for Gambella, Semera, and Asosa towns by MoWIE ET-MOWIE-75892-CS-QCBS / Selection and Employment of Consultant for Development of Billing and Accounting Component 3: Project System, Customer Care, FM Quality And Cost- 2018-12- 2019-01- 2019-02- 2019-03- 2019-04- 2019-05- 2019-11- IDA / 60070 management & institutional Post Open - National 76,000.00 0.00 Canceled 2018-11-15 improvement, network Based Selection 06 19 16 18 22 27 23 strengthening management and and capacity Building for Nekemte and Jimma towns by by Oromia WMEB ET-MOWIE-75903-CS-QCBS / Selection and Employment of Consultant for Development of Billing and Accounting Component 3: Project System, Customer Care, FM Quality And Cost- 2018-12- 2019-01- 2019-02- 2019-03- 2019-04- 2019-05- 2019-11- IDA / 60070 management & institutional Post Open - National 76,000.00 0.00 Canceled 2018-11-14 improvement, network Based Selection 05 18 15 17 21 26 22 strengthening management and and capacity Building for Hawassa, Sodo, and Arbaminch towns by SNRPR Water Bureau ET-MOWIE-75888-CS-INDV / Selection and Employment of Consultant for Development of Billing and Accounting Component 3: Project System, Customer Care, FM Quality And Cost- 2018-12- 2019-01- 2019-02- 2019-03- 2019-04- 2019-05- 2019-11- IDA / 60070 management & institutional Post Open - National 76,000.00 0.00 Canceled 2018-11-15 improvement, network Based Selection 06 19 16 18 22 27 23 strengthening management and Capacity Building for Adama, Assela, Bishoftu and Shashamene towns by Oromia WMEB ET-MOWIE-75899-CS-QCBS / Selection and Employment of Consultant for Development of Billing and Accounting Component 3: Project Quality And Cost- 2018-12- 2019-01- 2019-02- 2019-03- 2019-04- 2019-05- 2019-08- System, Customer Care, FM IDA / 60070 management & institutional Post Open - National 75,000.00 0.00 Canceled 2018-11-15 Based Selection 06 19 16 18 22 27 25 improvement, network strengthening management and and capacity Building for Harar town by by Harar WMEB ET-MOWIE-75905-CS-QCBS / Selection and Employment of Consultant for Development of Billing and Accounting Component 3: Project Quality And Cost- 2018-12- 2019-01- 2019-02- 2019-03- 2019-04- 2019-05- 2019-08- System, Customer Care, FM IDA / 60070 management & institutional Post Open - National 100,000.00 0.00 Canceled 2018-11-15 Based Selection 06 19 16 18 22 27 25 improvement, network strengthening management and and capacity Building for Diredewa town WSSS by diredewa town WSSS ET-MOWIE-107046-CS-QCBS / Consultancy Service for Design and Implementation of Component 2: Sanitation and an Integrated Management water supply services Quality And Cost- Open - Under 2019-09- 2019-09- 2019-11- 2019-10- 2020-05- 2019-12- 2020-06- 2020-01- 2020-11- 2020-02- 2020-03- 2021-09- IDA / 60070 Prior 4,067,243.00 0.00 2019-08-20 Information System for Urban improvement in secondary Based Selection International Implementation 16 10 07 24 07 05 26 04 17 08 14 05 Water Utilities in Ethiopia, by cities Water Development Commission ET-MOWIE-139130-CS-QCBS / consultancy service on the construction supervision of Component 2: Sanitation and FSM (fecal sludge water supply services Quality And Cost- Open - Under 2020-06- 2019-12- 2020-07- 2020-01- 2021-04- 2020-02- 2020-03- 2020-04- 2020-06- 2022-01- IDA / 60070 Prior 1,400,000.00 0.00 2019-11-21 management ) for Adama, improvement in secondary Based Selection International Implementation 12 12 14 25 27 24 25 29 03 24 Bahirdar, Hawasa, DireDewa, cities and Mekele Towns by Water Development Comision. ET-MOWIE-143194-CS-QCBS / Selection and Employment of Independent procurement Audit service for multi years Component 2: Sanitation and procurement Audit (2009- water supply services Quality And Cost- 2020-01- 2020-01- 2020-01- 2020-03- 2020-05- 2020-04- 2020-07- 2020-05- 2020-11- 2020-06- 2021-04- 2020-07- 2021-06- 2022-02- IDA / 60070 Prior Open - National 300,000.00 243,328.50 Signed 2019-12-25 2013 EFY) for 23 towns o f improvement in secondary Based Selection 01 08 27 08 12 07 14 07 09 11 21 16 04 06 Urban Water and Sanitation cities Project II (UWSSP-2) by Water Development Commission Page 9 ET-MOWIE-152576-CS-QCBS / Consultancy service for preparation of business plan and NRW Reduction strategic Component 2: Sanitation and plan and implement for water supply services Quality And Cost- Open - Under 2020-03- 2020-02- 2020-06- 2020-03- 2020-04- 2020-05- 2020-06- 2020-08- 2022-01- IDA / 60070 Prior 3,105,582.00 0.00 2020-01-23 Adama, Asela, Shashamene, improvement in secondary Based Selection International Implementation 13 13 08 28 25 25 29 03 25 Nekemete, Jima and Bishoftu cities towns Water supply and Sewerage authorities by Oromia Region Water Bureau ET-MOWIE-152577-CS-QCBS / Consultancy service for preparation of business plan Component 2: Sanitation and and NRW Reduction strategic water supply services Quality And Cost- Open - Under 2020-03- 2020-02- 2020-05- 2020-03- 2020-04- 2020-05- 2020-06- 2020-08- 2021-11- plan and implement for Bhir IDA / 60070 Prior 2,552,791.00 0.00 2020-01-23 improvement in secondary Based Selection International Implementation 13 13 28 28 25 25 29 03 26 Dar, Gonder, Dessie and cities Debre-birhan towns Water supply and Sewerage authorities by Amhara Region Water Bureau ET-MOWIE-152580-CS-QCBS / Consultancy service for preparation of business plan Component 2: Sanitation and and NRW Reduction strategic water supply services Quality And Cost- Open - Under 2021-02- 2020-02- 2021-04- 2020-03- 2020-04- 2020-05- 2020-06- 2020-08- 2021-09- plan and implement for IDA / 60070 Prior 2,258,370.00 0.00 2020-01-23 improvement in secondary Based Selection International Implementation 26 13 07 28 25 25 29 03 27 Gambella, Semera and Asosa cities towns Water supply and Sewerage authorities by Water Development Commission ET-MOWIE-77756-CS-QCBS / Consultancy service for preparation of business plan Component 2: Sanitation and and NRW Reduction strategic water supply services Quality And Cost- 2019-09- 2018-12- 2019-01- 2019-02- 2019-03- 2019-04- 2019-05- 2019-09- plan and implementation for IDA / 60070 Post Open - National 110,000.00 0.00 Canceled 2018-11-15 improvement in secondary Based Selection 04 06 19 16 18 22 27 24 JIjiga and Deghabur towns cities Water supply and Sewerage authorities by Somali Region Water Bureau ET-MOWIE-77754-CS-QCBS / Consultancy service for preparation of business plan Component 2: Sanitation and and NRW Reduction strategic water supply services Quality And Cost- 2019-09- 2018-12- 2019-01- 2019-02- 2019-03- 2019-04- 2019-05- 2019-09- plan and implement for IDA / 60070 Post Open - National 130,000.00 0.00 Canceled 2018-11-14 improvement in secondary Based Selection 04 05 18 15 17 21 26 23 A/Minch, Sodo and Hawassa cities towns Water supply and Sewerage authorities by SNNPR Region Water Bureau ET-MOWIE-75930-CS-QCBS / Selection and employment of consultant for Consultancy Component 2: Sanitation and service for preparation of water supply services Quality And Cost- 2019-09- 2018-12- 2019-02- 2019-03- 2019-04- 2019-05- 2019-06- 2019-10- business plan and NRW IDA / 60070 Post Open - National 110,000.00 0.00 Canceled 2018-11-30 improvement in secondary Based Selection 04 21 03 03 02 07 11 09 Reduction strategic plan and cities implementation mechanisms Mekele and Adigrat towns by Tigray regional water bureau ET-MOWIE-77755-CS-QCBS / Consultancy service service for preparation of business plan and NRW Reduction Component 2: Sanitation and strategic plan and water supply services Quality And Cost- 2019-09- 2018-12- 2019-02- 2019-03- 2019-04- 2019-05- 2019-06- 2019-10- implementation m for IDA / 60070 Post Open - National 130,000.00 0.00 Canceled 2018-11-29 improvement in secondary Based Selection 04 20 02 02 01 06 10 08 Gambella, Semera and Asosa cities towns Water supply and Sewerage authorities by Ministry of Water Irrigation and Electricity ET-MOWIE-107044-CS-QCBS / Selection and employment of consultant for Consultancy service for preparation of Component 2: Sanitation and business plan and NRW water supply services Quality And Cost- 2019-09- 2019-05- 2019-06- 2019-07- 2019-08- 2019-09- 2019-10- 2020-04- Reduction strategic plan and IDA / 60070 Post Open - National 200,000.00 0.00 Canceled 2019-04-10 improvement in secondary Based Selection 04 01 14 12 11 15 20 17 implementation mechanisms cities for Adama, Asella, Shashamene, Nekemte, Jimma and Bishoftu towns by Oromia WMEB ET-MOWIE-75921-CS-QCBS / Selection and employment of consultant for Consultancy service for preparation of Component 2: Sanitation and business plan and NRW water supply services Quality And Cost- 2018-12- 2019-01- 2019-02- 2019-03- 2019-04- 2019-06- 2019-11- IDA / 60070 Post Open - National 150,000.00 0.00 Canceled 2018-11-22 Reduction strategic plan and improvement in secondary Based Selection 13 26 23 25 29 03 30 implementation mechanisms cities for for Adama, Asella, Shashamene and Bishoftu towns by Oromia WMEB ET-MOWIE-77757-CS-QCBS / Consultancy service for preparation of business plan and NRW Reduction strategic Component 2: Sanitation and plan and implementation water supply services Quality And Cost- 2019-09- 2018-12- 2019-02- 2019-03- 2019-04- 2019-05- 2019-06- 2019-10- IDA / 60070 Post Open - National 60,000.00 0.00 Canceled 2018-11-30 mechanisms for Harar town improvement in secondary Based Selection 04 21 03 03 02 07 11 09 Water supply and Sewerage cities authorities by Harar town Water supply and Sewerage authorities ET-MOWIE-75919-CS-QCBS / Selection and employment of consultant for Consultancy service for preparation of Component 3: Project Quality And Cost- 2018-12- 2019-02- 2019-03- 2019-04- 2019-05- 2019-06- 2019-12- business plan and NRW IDA / 60070 management & institutional Post Open - National 110,000.00 0.00 Canceled 2018-11-30 Based Selection 21 03 03 02 07 11 08 Reduction strategic plan and strengthening implementation mechanisms for Jimma and Nekemte towns by Oromia WMEB ET-MOWIE-77761-CS-QCBS / Consultancy service for preparation of business plan Component 2: Sanitation and and NRW Reduction strafor water supply services Quality And Cost- 2019-09- 2018-12- 2019-01- 2019-02- 2019-03- 2019-04- 2019-05- 2019-09- Gonder, Dessie, Debreberhan IDA / 60070 Post Open - National 150,000.00 0.00 Canceled 2018-11-15 improvement in secondary Based Selection 04 06 19 16 18 22 27 24 and Bahirdar towns Water cities supply and Sewerage authorities by Amhara Region Water Bureau ET-MOWIE-152586-CS-QCBS / Consultancy service for preparation of business plan Component 2: Sanitation and and NRW Reduction strategic water supply services Quality And Cost- Open - Under 2020-07- 2020-03- 2020-04- 2020-05- 2020-06- 2020-07- 2020-08- 2021-08- plan and implement for Jigjiga IDA / 60070 Post 1,505,580.00 0.00 2020-02-19 improvement in secondary Based Selection International Implementation 13 11 24 22 21 26 30 30 and Degnabur towns Water cities supply and Sewerage authorities by somali Region Water Bureau ET-MOWIE-152559-CS-QCBS / Consultancy service for preparation of business plan Component 2: Sanitation and and NRW Reduction strategic water supply services Quality And Cost- Open - Under 2020-03- 2020-03- 2020-04- 2020-05- 2020-06- 2020-07- 2020-08- 2021-10- plan and implement for IDA / 60070 Post 1,700,000.00 0.00 2020-02-20 improvement in secondary Based Selection International Implementation 16 12 25 23 22 27 31 25 A/Minch, Sodo and Hawassa cities towns Water supply and Sewerage authorities by SNNPR Region Water Bureau ET-MOWIE-152583-CS-QCBS / Consultancy service for preparation of business plan Component 2: Sanitation and and NRW Reduction strategic water supply services Quality And Cost- Open - Under 2020-07- 2020-03- 2020-04- 2020-05- 2020-06- 2020-07- 2020-08- 2021-08- plan and implement for IDA / 60070 Post 1,500,000.00 0.00 2020-02-20 improvement in secondary Based Selection International Implementation 13 12 25 23 22 27 31 31 Adegrat and Mekelle towns cities Water supply and Sewerage authorities by Tigray Region Water Bureau ET-MOWIE-152591-CS-QCBS / Consultancy service for preparation of business plan Component 2: Sanitation and and NRW Reduction strategic water supply services Quality And Cost- Open - Under 2020-04- 2020-03- 2020-04- 2020-05- 2020-06- 2020-07- 2020-08- 2021-08- IDA / 60070 Post 1,500,000.00 0.00 2020-02-20 plan and implement for Harar improvement in secondary Based Selection International Implementation 15 12 25 23 22 27 31 31 town Water supply and cities Sewerage authority by Harar Region Water Bureau ET-MOWIE-146021-CS-QBS / Selection and Employment of Component 2: Sanitation and Consultant Environmental & Social Impact water supply services 2020-02- 2020-03- 2020-04- 2020-05- 2020-11- IDA / 60070 Post Qualification Open - National 29,100.00 0.00 Canceled 2020-01-14 Assessment for Arba Minch & improvement in secondary 04 19 18 23 19 Selection Wolaita Sodoby water cities Development commission Page 10 ET-MOWIE-146020-CS-QBS / Selection and Employment of Component 2: Sanitation and Environmental & Social Impact Consultant water supply services Under 2020-04- 2020-03- 2020-05- 2020-06- 2020-07- 2020-12- Assessment for Gondar, IDA / 60070 Post Qualification Open - National 60,000.00 0.00 2020-02-28 improvement in secondary Implementation 03 13 02 01 06 03 Dessie, Debre Berhan, Jigjiga Selection cities and Degehabur by water Development commission. ET-MOWIE-146016-CS-QBS / Selection and Employment of Environmental & Social Impact Component 2: Sanitation and Consultant Assessment for Jimma, water supply services Under 2020-04- 2020-03- 2020-05- 2020-06- 2020-07- 2020-12- IDA / 60070 Post Qualification Open - National 91,300.00 0.00 2020-02-28 Nekemte, Bishoftu, improvement in secondary Implementation 03 13 02 01 06 03 Selection Shashemene, Assela, W/Sodo cities and Arba Minch by water Development commission ET-MOWIE-146024-CS-QBS / Selection and Employment of Component 2: Sanitation and Environmental & Social Impact Consultant water supply services Under 2020-04- 2020-03- 2020-05- 2020-06- 2020-07- 2020-12- Assessment for Harar, IDA / 60070 Post Qualification Open - National 52,200.00 0.00 2020-02-28 improvement in secondary Implementation 03 13 02 01 06 03 Adigrat, Gambella, Semera- Selection cities Logia and, Assosa by water Development commission ET-MOWIE-205117-CS-QCBS / Consultancy Service for Component 2: Sanitation and Preparing Technical Design water supply services Quality And Cost- Open - Under 2020-12- 2021-01- 2021-02- 2021-03- 2021-05- 2021-06- 2022-11- IDA / 60080 Prior 1,700,000.00 0.00 2020-11-25 Manual, Operation, improvement in secondary Based Selection International Implementation 16 29 26 28 02 06 28 Maintenance and Management cities for Urban Sanitation by WDC INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-MOWIE-55842-CS-INDV / Selection and Employment of Component 3: Project Individual Pending 2018-07- 2018-08- 2018-09- 2024-08- Procurement Specialist for IDA / 60070 management & institutional Post Consultant Open 54,000.00 0.00 2018-06-18 Implementation 22 12 16 15 Mekelle Town Water Utility by strengthening Selection Mekelle Town Utility ET-MOWIE-63893-CS-INDV / Selection and Employment of Component 3: Project Individual Financial specialist for Adama 2020-06- 2018-07- 2018-07- 2018-07- 2019-07- 2018-08- 2018-07- 2019-08- IDA / 60080 management & institutional Post Consultant Open 5,185.00 3,908.81 Signed 2018-06-14 Town Waste Water 16 13 26 27 27 31 27 26 strengthening Selection Management project by Adama Town Utility office. ET-MOWIE-70084-CS-INDV / Selection and employment of Component 3: Project Individual 2018-12- 2018-09- 2019-03- 2018-09- 2019-03- 2018-10- 2019-03- 2019-10- Technical specialist for IDA / 60070 management & institutional Post Consultant Open 7,500.00 6,474.26 Signed 2018-08-07 02 05 07 15 10 13 10 13 Amhara regional bureau by strengthening Selection Amhara regional bureau ET-MOWIE-70090-CS-INDV / Selection and Employment of Component 3: Project Individual Technical specialist for Pending 2018-09- 2018-09- 2018-10- 2019-10- IDA / 60070 management & institutional Post Consultant Open 7,500.00 0.00 2018-08-07 Oromia Region Water Mineral Implementation 05 15 13 13 strengthening Selection and Energy Bureau by Oromia OWMEB ET-MOWIE-70097-CS-INDV / selection and employment of Component 3: Project Individual 2018-12- 2018-09- 2019-02- 2018-09- 2019-03- 2018-10- 2019-03- 2019-10- Technical specialist for IDA / 60070 management & institutional Post Consultant Open 7,500.00 6,470.41 Signed 2018-08-07 03 05 20 12 10 10 10 10 Amhara regional bureau by strengthening Selection Amhara regional bureau ET-MOWIE-70098-CS-INDV / Selection and Employment of Component 3: Project Individual Technical specialist for Pending 2018-09- 2018-09- 2018-10- 2019-10- IDA / 60070 management & institutional Post Consultant Open 7,500.00 0.00 2018-08-07 Oromia Region Water Mineral Implementation 05 26 24 24 strengthening Selection and Energy Bureau by Oromia OWMEB ET-MOWIE-70101-CS-INDV / Selection and Employment of Component 3: Project Individual Technical specialist for SNNPR 2019-02- 2018-09- 2020-04- 2018-09- 2019-04- 2018-10- 2019-04- 2019-10- IDA / 60070 management & institutional Post Consultant Open 7,500.00 5,366.75 Signed 2018-08-07 Region Water Resource 18 05 11 26 15 24 15 24 strengthening Selection Development Bureau by SNNPR Water Resource Bureau ET-MOWIE-70102-CS-INDV / Selection and Employment of Component 3: Project Individual Technical specialist for SNNPR Pending 2018-09- 2018-09- 2018-10- 2019-10- IDA / 60070 management & institutional Post Consultant Open 7,500.00 0.00 2018-08-07 Region Water Mineral and Implementation 05 19 24 24 strengthening Selection Energy Bureau by SNNPR Water Resource Bureau ET-MOWIE-70104-CS-INDV / Selection and Employment of Technical specialist for Component 3: Project Individual Ethiopian Somali Region Water Pending 2018-09- 2018-09- 2018-10- 2019-10- IDA / 60070 management & institutional Post Consultant Open 7,500.00 0.00 2018-08-07 Resource Development Bureau Implementation 05 26 31 31 strengthening Selection by Ethiopian Somali Region Water Resource Development Bureau ET-MOWIE-70107-CS-INDV / Selection and Employment of Technical specialist for Component 3: Project Individual Pending 2018-09- 2018-09- 2018-10- 2019-10- Benishangulegumuz Region IDA / 60070 management & institutional Post Consultant Open 7,500.00 0.00 2018-08-07 Implementation 05 26 31 31 Water Mineral and Energy strengthening Selection Bureau by Benshangulgumuz Region Water Bureau ET-MOWIE-70109-CS-INDV / Selection and Employment of Project Coordinator for Adama Component 3: Project Individual 2018-12- 2018-09- 2018-12- 2018-09- 2018-08- 2018-11- 2018-08- 2019-11- Town Waste Water IDA / 60070 management & institutional Post Consultant Open 8,800.00 5,556.55 Signed 2018-08-08 07 06 28 27 28 01 28 01 Management Project by strengthening Selection Adama Town Water Supply and Sewerage Authority ET-MOWIE-70111-CS-INDV / Selection and employment of financial specialist for Mekele Component 3: Project Individual Pending 2018-09- 2018-09- 2018-10- 2019-10- Town Water supply and IDA / 60070 management & institutional Post Consultant Open 6,600.00 0.00 2018-08-08 Implementation 06 13 18 18 sewerage service by mekele strengthening Selection town water supply and sewerage Authority ET-MOWIE-70119-CS-INDV / Selection and Employment of Component 3: Project Individual 2018-11- 2018-09- 2019-03- 2018-09- 2019-03- 2018-11- 2019-03- 2019-11- Project coordinator for Hawasa IDA / 60070 management & institutional Post Consultant Open 8,800.00 5,364.91 Signed 2018-08-15 06 13 18 27 19 01 19 01 Town by Hawasa Town Water strengthening Selection Supply and Sewerage Service ET-MOWIE-70125-CS-INDV / Selection and employment of financial specialist for Hawasa Component 3: Project Individual Pending 2018-09- 2018-09- 2018-11- 2019-11- Town Water supply and IDA / 60070 management & institutional Post Consultant Open 6,600.00 0.00 2018-08-15 Implementation 13 27 01 01 sewerage service by Hawasa strengthening Selection town water supply and sewerage Authority ET-MOWIE-70129-CS-INDV / Selection and Employment of Component 3: Project Individual Project Coordinator for Asela 2018-07- 2018-09- 2018-10- 2018-09- 2018-10- 2018-10- 2018-10- 2019-10- IDA / 60070 management & institutional Post Consultant Open 8,800.00 6,509.16 Signed 2018-08-06 town by Asela town Water 15 04 02 18 12 23 12 23 strengthening Selection Supply and Sewerage Authority ET-MOWIE-70150-CS-INDV / Selection and Employment of Project Coordinator for Component 3: Project Individual 2019-12- 2018-09- 2019-12- 2018-09- 2020-06- 2018-11- 2020-06- 2019-11- Shashamene town by IDA / 60070 management & institutional Post Consultant Open 8,800.00 6,514.68 Signed 2018-08-15 01 13 20 27 08 01 08 01 Shashamene town Water strengthening Selection Supply and Sewerage Authority ET-MOWIE-70157-CS-INDV / Selection and Employment of Component 3: Project Individual Project Coordinator for 2018-06- 2018-09- 2018-08- 2018-09- 2018-08- 2018-10- 2018-08- 2019-10- IDA / 60070 management & institutional Post Consultant Open 8,800.00 7,801.64 Signed 2018-08-10 Nekemte town by Nekemte 17 08 03 22 03 27 03 27 strengthening Selection town Water Supply and Sewerage Authority Page 11 ET-MOWIE-70166-CS-INDV / Selection and Employment of Component 3: Project Individual Project Coordinator for 2018-07- 2018-09- 2018-09- 2018-09- 2018-09- 2018-11- 2018-09- 2019-11- IDA / 60070 management & institutional Post Consultant Open 8,800.00 5,530.78 Signed 2018-08-15 Arbaminch town by 01 13 02 27 11 01 11 01 strengthening Selection Arbaminch town Water Supply and Sewerage Authority ET-MOWIE-70176-CS-INDV / Selection and Employment of Component 3: Project Individual Project Coordinator for Pending 2018-09- 2018-09- 2018-10- 2019-10- IDA / 60070 management & institutional Post Consultant Open 8,800.00 0.00 2018-08-13 Gambella town by Gambella Implementation 11 25 30 30 strengthening Selection town Water Supply and Sewerage Autrity ET-MOWIE-70184-CS-INDV / Selection and Employment of Component 3: Project Individual Project Coordinator for Asosa Pending 2018-09- 2018-09- 2018-10- 2019-10- IDA / 60070 management & institutional Post Consultant Open 8,800.00 0.00 2018-08-14 town by Asosa town Water Implementation 12 26 31 31 strengthening Selection Supply and Sewerage Authority ET-MOWIE-70191-CS-INDV / Selection and employment of Component 3: Project Individual Under 2018-12- 2018-09- 2019-12- 2018-09- 2020-01- 2018-10- 2019-10- project coordinator for Adigrat IDA / 60070 management & institutional Post Consultant Open 8,800.00 0.00 2018-08-07 Implementation 06 05 02 19 12 24 24 town by Adigrat town water strengthening Selection supply and sewerage service ET-MOWIE-70193-CS-INDV / Selection and Employment of Component 3: Project Individual Procurement Specialist for Pending 2018-09- 2018-09- 2018-10- 2019-10- IDA / 60070 management & institutional Post Consultant Open 7,921.00 0.00 2018-08-13 Asosa town by Asosa town Implementation 11 25 30 30 strengthening Selection Water Supply and Sewerage Authority ET-MOWIE-70194-CS-INDV / Selection and Employment of Component 3: Project Individual financial spcialist for Asosa Pending 2018-09- 2018-09- 2018-10- 2019-10- IDA / 60070 management & institutional Post Consultant Open 6,600.00 0.00 2018-08-13 town by Asosa town Water Implementation 11 25 30 30 strengthening Selection Supply and Sewerage Authority ET-MOWIE-70198-CS-INDV / Selection and Employment of Component 3: Project Individual Procurement Specialist for Pending 2018-09- 2018-09- 2018-11- 2019-11- IDA / 60070 management & institutional Post Consultant Open 7,921.00 0.00 2018-08-15 Adigrat town by Adigerat town Implementation 13 27 01 01 strengthening Selection Water Supply and Sewerage Authority ET-MOWIE-70199-CS-INDV / Selection and Employment of Component 3: Project Individual Financial Specialist for Adigrat Under 2018-09- 2018-09- 2018-11- 2019-11- IDA / 60070 management & institutional Post Consultant Open 6,600.00 0.00 2018-08-15 town by Adigerat town Water Implementation 13 27 01 01 strengthening Selection Supply and Sewerage Authority ET-MOWIE-70202-CS-INDV / Selection and Employment of Component 3: Project Individual financial Specialist for Jijiga Pending 2018-09- 2018-09- 2018-10- 2019-10- IDA / 60070 management & institutional Post Consultant Open 6,600.00 0.00 2018-08-15 town by Jijiga town Water Implementation 13 20 18 18 strengthening Selection Supply and Sewerage Authority ET-MOWIE-75716-CS-INDV / Selection and Employmnt of Component 3: Project Individual Financial Specialist for 2019-01- 2018-11- 2019-02- 2018-11- 2019-02- 2018-12- 2019-02- 2019-12- IDA / 60070 management & institutional Post Consultant Open 6,600.00 4,713.49 Signed 2018-09-14 Bahirdar town Water Supply 10 02 12 23 12 28 16 28 strengthening Selection and Sewerage Authority by Bahirdar Town ET-MOWIE-75723-CS-INDV / Selection and Employment of Component 3: Project Individual Financial Specialist for Gonder 2018-05- 2018-11- 2018-05- 2018-11- 2018-05- 2018-12- 2019-05- 2019-12- IDA / 60070 management & institutional Post Consultant Open 6,600.00 4,884.75 Signed 2018-09-13 town Water Supply and 01 01 01 22 01 27 01 27 strengthening Selection Sewerage Authority by Gonder Town ET-MOWIE-75730-CS-INDV / Selection and Employment of Component 3: Project Individual Financial Specialist for Dessie 2018-09- 2018-11- 2019-04- 2018-11- 2019-04- 2018-12- 2019-04- 2019-12- IDA / 60070 management & institutional Post Consultant Open 6,600.00 4,716.23 Signed 2018-09-14 town Water Supply and 10 02 25 23 26 28 26 28 strengthening Selection Sewerage Authority by Dessie Town ET-MOWIE-75736-CS-INDV / Selection and Employmentasw2q of Component 3: Project Individual 2018-09- 2018-11- 2019-12- 2018-11- 2019-12- 2018-12- 2019-12- 2019-12- Financial Specialist for IDA / 60070 management & institutional Post Consultant Open 6,600.00 4,575.98 Signed 2018-09-14 12 02 18 23 18 28 18 28 Bishoftu town Water Supply strengthening Selection and Sewerage Authority by Bishoftu Town ET-MOWIE-75738-CS-INDV / Selection and Employment of Component 3: Project Individual Financial Specialist for Pending 2018-11- 2018-11- 2018-12- 2019-12- IDA / 60070 management & institutional Post Consultant Open 6,600.00 0.00 2018-09-14 Gambella town Water Supply Implementation 02 23 28 28 strengthening Selection and Sewerage Authority by Gambella Town ET-MOWIE-75746-CS-INDV / Selection and Employment of Component 3: Project Individual Financial Specialist for Jima Pending 2018-11- 2018-11- 2018-12- 2019-12- IDA / 60070 management & institutional Post Consultant Open 6,600.00 0.00 2018-09-14 town Water Supply and Implementation 02 23 28 28 strengthening Selection Sewerage Authority by Jima Town ET-MOWIE-75749-CS-INDV / Selection and Employment of Component 3: Project Individual Financial Specialist for Semera Pending 2018-11- 2018-11- 2018-12- 2019-12- IDA / 60070 management & institutional Post Consultant Open 6,600.00 0.00 2018-09-14 town Water Supply and Implementation 02 23 28 28 strengthening Selection Sewerage Authority by Semera Town ET-MOWIE-75750-CS-INDV / Selection and Employment of Component 3: Project Individual Financial Specialist for Pending 2018-11- 2018-11- 2018-12- 2019-12- IDA / 60070 management & institutional Post Consultant Open 6,600.00 0.00 2018-09-14 Deghabur town Water Supply Implementation 02 23 28 28 strengthening Selection and Sewerage Authority by Deghabur Town ET-MOWIE-75753-CS-INDV / Selection and Employmnt of Component 3: Project Individual Financial Specialist for Harar Pending 2018-11- 2018-11- 2018-12- 2019-12- IDA / 60070 management & institutional Post Consultant Open 6,600.00 0.00 2018-09-14 town Water Supply and Implementation 02 23 28 28 strengthening Selection Sewerage Authority by Harar Town ET-MOWIE-75755-CS-INDV / Selection and Employmnt of Component 3: Project Individual Financial Specialist for Pending 2018-11- 2018-11- 2018-12- 2019-12- IDA / 60070 management & institutional Post Consultant Open 6,600.00 0.00 2018-09-14 Diredewa town Water Supply Implementation 02 23 28 28 strengthening Selection and Sewerage Authority by Diredewa Town ET-MOWIE-75757-CS-INDV / Selection and Employment of Component 3: Project Individual Financial Specialist for Sodo 2018-07- 2018-11- 2019-01- 2018-11- 2019-02- 2018-12- 2019-02- 2019-12- IDA / 60070 management & institutional Post Consultant Open 6,600.00 4,716.23 Signed 2018-09-14 town Water Supply and 03 02 17 23 15 28 15 28 strengthening Selection Sewerage Authority by Sodo Town ET-MOWIE-75758-CS-INDV / Selection and Employment of Financial Specialist for Component 3: Project Individual 2018-06- 2018-11- 2018-08- 2018-11- 2018-10- 2018-12- 2018-11- 2019-12- Debreberhan town Water IDA / 60070 management & institutional Post Consultant Open 6,600.00 4,735.33 Signed 2018-09-14 01 02 01 23 29 28 29 28 Supply and Sewerage strengthening Selection Authority by Debreberhan Town ET-MOWIE-75810-CS-INDV / Selection and Employment of Component 3: Project Individual 2018-06- 2018-10- 2019-02- 2018-11- 2019-02- 2018-12- 2019-02- 2019-12- Project Coordinator for IDA / 60070 management & institutional Post Consultant Open 8,800.00 5,536.05 Signed 2018-09-12 01 31 18 21 16 26 16 26 Bahirdar Town Water Supply strengthening Selection Project by Bahirdar Town ET-MOWIE-75811-CS-INDV / Selection and Employment of Component 3: Project Individual 2018-05- 2018-10- 2018-10- 2018-11- 2018-11- 2018-12- 2018-11- 2019-12- Project Coordinator for IDA / 60070 management & institutional Post Consultant Open 8,800.00 5,698.88 Signed 2018-09-12 01 31 30 21 01 26 01 26 Gonder Town Water Supply strengthening Selection Project by Gonder Town ET-MOWIE-75866-CS-INDV / Selection and Employment of Component 3: Project Individual Project Coordinator for Dessie Pending 2018-12- 2018-12- 2019-01- 2020-01- IDA / 60070 management & institutional Post Consultant Open 8,800.00 0.00 2018-10-15 Town Water Supply and Implementation 03 24 28 28 strengthening Selection Sewerage Enterprise by Dessie Town Page 12 ET-MOWIE-75871-CS-INDV / Selection and Employment of Project Coordinator for Component 3: Project Individual 2018-06- 2018-12- 2018-10- 2018-12- 2019-11- 2019-01- 2018-11- 2019-07- Debrebirhan Town Water IDA / 60070 management & institutional Post Consultant Open 8,800.00 5,550.54 Signed 2018-10-15 28 03 08 24 25 28 25 27 Supply and Sewerage strengthening Selection Enterprise by Debrabrihan Town ET-MOWIE-75872-CS-INDV / Selection and Employment of Component 3: Project Individual Project Coordinator for 2019-12- 2018-12- 2019-12- 2018-12- 2019-12- 2019-01- 2019-12- 2020-01- IDA / 60070 management & institutional Post Consultant Open 8,800.00 6,537.11 Signed 2018-10-15 Bishoftu Town Water Supply 19 03 10 24 18 28 18 28 strengthening Selection and Sewerage Enterprise by Bishoftu Town ET-MOWIE-75873-CS-INDV / Selection and Employment of Component 3: Project Individual Project Coordinator for Jimma Pending 2018-12- 2018-12- 2019-01- 2020-01- IDA / 60070 management & institutional Post Consultant Open 8,800.00 0.00 2018-10-15 Town Water Supply and Implementation 03 24 28 28 strengthening Selection Sewerage Enterprise by Jimma Town ET-MOWIE-75874-CS-INDV / Selection and Employment of Component 3: Project Individual Project Coordinator for Pending 2018-12- 2018-12- 2019-01- 2020-01- IDA / 60070 management & institutional Post Consultant Open 8,800.00 0.00 2018-10-15 Semera Town Water Supply Implementation 03 24 28 28 strengthening Selection and Sewerage Enterprise by Semera Town ET-MOWIE-75875-CS-INDV / Selection and Employment of Component 3: Project Individual Project Coordinator for Harar Pending 2018-12- 2018-12- 2019-01- 2020-01- IDA / 60070 management & institutional Post Consultant Open 8,800.00 0.00 2018-10-15 Town Water Supply and Implementation 03 24 28 28 strengthening Selection Sewerage Enterprise by Harar Town ET-MOWIE-75876-CS-INDV / Selection and Employment of Component 3: Project Individual Project Coordinator for Pending 2018-12- 2018-12- 2019-01- 2020-01- IDA / 60070 management & institutional Post Consultant Open 8,800.00 0.00 2018-10-15 Diredewa Town Water Supply Implementation 03 24 28 28 strengthening Selection and Sewerage Enterprise by Diredewa Town ET-MOWIE-75877-CS-INDV / Selection and Employment of Component 3: Project Individual Project Coordinator for Pending 2018-12- 2018-12- 2019-01- 2020-01- IDA / 60070 management & institutional Post Consultant Open 8,800.00 0.00 2018-10-15 Mekelle Town Water Supply Implementation 03 24 28 28 strengthening Selection and Sewerage Enterprise by Mekelle Town ET-MOWIE-75880-CS-INDV / Selection and Employment of Component 3: Project Individual Project Coordinator for Jigjiga Pending 2018-12- 2018-12- 2019-01- 2020-01- IDA / 60070 management & institutional Post Consultant Open 8,800.00 0.00 2018-10-15 Town Water Supply and Implementation 03 24 28 28 strengthening Selection Sewerage Enterprise by Jigijiga Town ET-MOWIE-75881-CS-INDV / Selection and Employment of Component 3: Project Individual Project Coordinator for Pending 2018-12- 2018-12- 2019-01- 2020-01- IDA / 60070 management & institutional Post Consultant Open 8,800.00 0.00 2018-10-15 DeghaburTown Water Supply Implementation 03 24 28 28 strengthening Selection and Sewerage Enterprise by DeghaburTown ET-MOWIE-75882-CS-INDV / Selection and Employment of Component 3: Project Individual Under 2018-07- 2018-12- 2018-12- 2019-01- 2020-01- Technical Specialist for MOWIE IDA / 60070 management & institutional Post Consultant Open 7,500.00 0.00 2018-10-15 Implementation 01 03 24 28 28 Program management unit by strengthening Selection MoWIE ET-MOWIE-75883-CS-INDV / Component 3: Project Individual Selection and Employment of Under 2018-12- 2018-12- 2019-01- 2020-01- IDA / 60070 management & institutional Prior Consultant Open 7,500.00 0.00 2018-10-15 Procurement Specialist for Implementation 03 24 28 28 strengthening Selection MoWIE PMU by MoWIE ET-MOWIE-77731-CS-INDV / Selection and Employment of Component 3: Project Individual Project Coordinator for 2018-06- 2018-11- 2018-09- 2018-12- 2020-01- 2019-01- 2020-01- 2020-01- IDA / 60070 management & institutional Post Consultant Open 8,800.00 5,204.12 Signed 2018-09-26 SodoTown Water Supply and 11 14 30 05 20 09 20 09 strengthening Selection Sewerage Enterprise by Sodo Town ET-MOWIE-77735-CS-INDV / Selection and employment of Component 3: Project Individual 2018-07- 2018-11- 2018-07- 2018-12- 2018-09- 2019-01- 2018-09- 2020-01- financial specialist for IDA / 60070 management & institutional Post Consultant Open 6,600.00 4,880.10 Signed 2018-09-26 02 14 25 05 11 09 11 09 Arbaminch town WSSE for strengthening Selection Arbaminch Town ET-MOWIE-77736-CS-INDV / Selection and Employment of Component 3: Project Individual Financial specialist for 2018-08- 2018-11- 2018-07- 2018-12- 2018-08- 2019-01- 2018-08- 2020-01- IDA / 60070 management & institutional Post Consultant Open 6,600.00 2,676.54 Signed 2018-09-26 Nekemte Town Water Supply 16 14 03 05 01 09 01 09 strengthening Selection and Sewerage Enterprise by Nekemte Town ET-MOWIE-77737-CS-INDV / Selection and Employment of Component 3: Project Individual Financial specialist for Asella Pending 2018-11- 2018-12- 2019-01- 2020-01- IDA / 60070 management & institutional Post Consultant Open 6,600.00 0.00 2018-09-26 Town Water Supply and Implementation 14 05 09 04 strengthening Selection Sewerage Enterprise by Asella Town ET-MOWIE-77738-CS-INDV / Selection and Employment of Financial specialist for Component 3: Project Individual 2019-05- 2018-11- 2018-09- 2018-12- 2018-07- 2019-01- 2018-09- 2020-01- Shashamene Town Water IDA / 60070 management & institutional Post Consultant Open 6,600.00 3,922.27 Signed 2018-09-26 11 14 09 05 11 09 17 09 Supply and Sewerage strengthening Selection Enterprise by Shashamene Town ET-MOWIE-77734-CS-CDS / Selection and employment of Component 2: Sanitation and consultant for construction water supply services Under 2018-09- 2018-12- 2019-02- 2019-08- supervision and contract IDA / 60070 Post Direct Selection Direct 110,011.00 0.00 2018-11-30 improvement in secondary Implementation 12 10 13 12 administration for Dire Dewa cities Town WSSE by Dire Dewa Town ET-MOWIE-107048-CS-INDV / Selection and Employment of Component 3: Project Individual Under 2019-05- 2019-05- 2020-02- 2019-05- 2020-05- 2019-06- 2023-06- Individual Procurement IDA / 60070 management & institutional Prior Consultant Open 100,000.00 0.00 2019-04-01 Implementation 09 05 27 26 06 30 29 Consultant/Specialist by Water strengthening Selection Development Commission ET-MOWIE-107059-CS-INDV / Selection and Employment of Component 3: Project Individual Individual Technical Pending 2019-05- 2019-05- 2019-06- 2023-04- IDA / 60070 management & institutional Post Consultant Open 100,000.00 0.00 2019-04-01 Consultant/ Specialist by Implementation 04 18 22 27 strengthening Selection Water Development Commission ET-MOWIE-107052-CS-INDV / Selection and Employment of Contract Management Component 3: Project Individual 2019-04- 2019-05- 2019-08- 2019-05- 2019-11- 2019-06- 2019-11- 2023-07- Specialist for Water IDA / 60070 management & institutional Post Consultant Open 100,000.00 22,948.29 Signed 2019-04-01 30 04 30 25 05 29 13 08 Development commission strengthening Selection Urban WSSP II by Water Development Commission ET-MOWIE-107049-CS-INDV / Selection and Employment of Individual Financial Component 3: Project Individual 2019-04- 2019-05- 2019-10- 2019-05- 2019-11- 2019-06- 2019-11- 2023-07- Management Consultant/ IDA / 60070 management & institutional Post Consultant Open 100,000.00 24,407.63 Signed 2019-04-01 30 04 11 25 05 29 14 08 Specialist for Urban WSSP II by strengthening Selection Water Development Commission ET-MOWIE-110854-CS-INDV Component 3: Project Individual Under 2019-06- 2019-06- 2019-06- 2022-12- / Selection and Employment of IDA / 60070 management & institutional Post Consultant Open 50,000.00 0.00 2019-04-30 Implementation 02 09 30 28 Social Safeguard Senior strengthening Selection ET-MOWIE-107057-CS-INDV / Selection and Employment of Environmental and Social Component 2: Sanitation and Individual Safeguard Specialist for review water supply services Pending 2019-07- 2019-08- 2019-09- 2019-11- IDA / 60070 Post Consultant Open 52,000.00 0.00 2019-06-20 of 3 towns ( Adama, Dire improvement in secondary Implementation 24 14 07 06 Selection Dewa, Mekele) feasibility study cities and detail design by Water Development Commission Page 13 ET-MOWIE-118398-CS-INDV / Selection and Employment of Environmental and Social Component 2: Sanitation and Individual Safeguard Specialist for review water supply services Pending 2019-08- 2019-08- 2019-10- 2019-12- IDA / 60070 Post Consultant Open 35,000.00 0.00 2019-06-20 of 2 towns ( Hawasa and improvement in secondary Implementation 08 29 03 02 Selection Bahirdar) feasibility study and cities detail design by Water Development Commission ET-MOWIE-143029-CS-INDV Component 3: Project Individual / Selection and employment of 2019-12- 2020-01- 2020-04- 2020-01- 2020-06- 2020-02- 2020-06- 2020-05- IDA / 60070 management & institutional Post Consultant Open 25,000.00 21,813.30 Signed 2019-11-15 Sociologist for WDC by Water 20 03 03 24 23 28 23 28 strengthening Selection Development Commission ET-MOWIE-143055-CS-INDV Component 2: Sanitation and / Selection and Employment of Individual water supply services 2018-07- 2020-01- 2019-02- 2020-02- 2019-02- 2020-03- 2019-01- 2021-03- sanitation and Hygiene IDA / 60070 Post Consultant Open 30,000.00 5,536.05 Signed 2019-11-28 improvement in secondary 25 16 28 06 22 12 28 12 specialist by water Selection cities Development Commission. ET-MOWIE-143022-CS-INDV / Selection and Employment of Component 3: Project Individual Under 2020-01- 2020-01- 2020-02- 2020-06- Water Supply and Sanitation IDA / 60070 management & institutional Prior Consultant Open 30,000.00 0.00 2019-11-15 Implementation 03 24 28 27 Regulatory Specialist for WDC strengthening Selection by World Bank country office ET-MOWIE-143032-CS-INDV / Selection and employment of Component 3: Project Individual 2019-04- 2020-01- 2020-04- 2020-01- 2020-06- 2020-02- 2020-06- 2020-07- Environmental specialist for IDA / 60070 management & institutional Post Consultant Open 35,000.00 20,755.86 Signed 2019-11-15 30 03 03 24 23 28 23 27 Water Development strengthening Selection Commission by WDC ET-MOWIE-143016-CS-INDV / Selection and employment of Component 3: Project Individual 2019-12- 2020-01- 2020-04- 2020-02- 2020-06- 2020-03- 2020-06- 2020-08- legal specialist for WDC by IDA / 60070 management & institutional Post Consultant Open 40,000.00 21,341.44 Signed 2019-11-28 19 16 03 06 23 12 23 09 Water Development strengthening Selection Commission ET-MOWIE-143025-CS-INDV / Selection and Employment of Component 3: Project Individual 2019-12- 2020-01- 2020-04- 2020-01- 2020-06- 2020-02- 2020-06- 2020-07- Technical Specialist for WDC IDA / 60070 management & institutional Post Consultant Open 35,000.00 31,319.66 Signed 2019-11-15 18 03 03 24 23 28 23 27 by Water Development strengthening Selection Commission ET-MOWIE-143026-CS-INDV Component 3: Project Individual / Selection and Employment of 2019-12- 2020-01- 2020-04- 2020-01- 2020-06- 2020-02- 2020-06- 2020-07- IDA / 60070 management & institutional Post Consultant Open 30,000.00 28,520.21 Signed 2019-11-15 Economist for WDC by Water 20 03 03 24 23 28 23 27 strengthening Selection Development Commission ET-MOWIE-143012-CS-INDV / Selection and Employment of Component 3: Project Individual 2019-12- 2020-01- 2020-04- 2020-01- 2020-06- 2020-03- 2020-06- 2020-09- Governance/Public Policy IDA / 60070 management & institutional Post Consultant Open 50,000.00 48,149.24 Signed 2019-11-22 20 10 03 31 23 06 23 02 Specialist for WDC by Water strengthening Selection Development Commission ET-MOWIE-145062-CS-QBS / Component 2: Sanitation and Selection and Employment of Individual water supply services Pending 2020-01- 2020-02- 2020-03- 2021-03- business management IDA / 60070 Post Consultant Open 30,000.00 0.00 2019-11-28 improvement in secondary Implementation 16 06 12 12 specialist by the Water Selection cities Development Commission ET-MOWIE-75885-CS-INDV / Component 3: Project Individual Selection and Employment of Under 2019-01- 2019-01- 2019-02- 2020-02- IDA / 60070 management & institutional Prior Consultant Open 7,500.00 0.00 2018-11-15 Procurement Specialist for Implementation 03 24 28 28 strengthening Selection MoWIE PMU by MoWIE ET-MOWIE-181047-CS-INDV / Selection and Employment of one Additional Individual Component 3: Project Individual Under 2020-10- 2020-08- 2020-09- 2020-10- 2021-10- Procurement Consultant for IDA / 60070 management & institutional Prior Consultant Open 30,000.00 0.00 2020-07-08 Implementation 28 26 16 21 21 Water Development strengthening Selection Commission implemented by WDC ET-MOWIE-189851-CS-INDV / Selection and Employment of Individual Consultant who Component 3: Project Individual Pending 2020-11- 2020-11- 2020-12- 2021-12- provide support in selection of IDA / 60070 management & institutional Post Consultant Open 75,000.00 0.00 2020-09-15 Implementation 03 24 29 29 contractor and contract strengthening Selection administration of 5 towns FSTP DBO contract. ET-MOWIE-227402-CS-INDV Component 2: Sanitation and Individual / Individual consultants for water supply services Under 2021-04- 2021-06- 2021-07- 2021-08- 2021-11- IDA / 60070 Post Consultant Open 14,034.00 0.00 2021-04-15 Resettlement Action Plan (RAP) improvement in secondary Implementation 22 13 04 08 06 Selection Preparation for Hawassa cities Page 14 PROCUREMENT PLAN (Textual Part) Project information: Jiangxi Integrated Rural And Urban Water Supply And Wastewater Management Project Project Implementation agency: Jiangxi Integrated Rural And Urban Water Supply And Wastewater Management Project Management Office Date of the Procurement Plan: Sept. 2019 Period covered by this Procurement Plan: 24 months Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016, Revised November 2017 and August 2018) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. A. The Bank’s Standard Procurement Documents (SPDs): The Bank’s SPDs shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. B. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures (Tendering and Bidding Law of the Peoples’ Republic of China, i.e. TBL promulgated by its Order No. 21 dated August 30, 1999 and the Implementation Regulations of the TBL promulgated by its State Council Order No. 613 dated November 30, 2011 and any amendments thereof) may be used with the following conditions to meet the requirements for open competitive procurement of paragraph 5.4 of the Procurement Regulations: a) All procurement notices shall be published in a national newspaper of wide circulation, or on a widely- used website / electronic portal with free access. b) A minimum of twenty (20) business days shall be given to Bidders between the date of such advertisement (or the date of availability of procurement documents, whichever is later and the deadline for the submission of bids). The advertisement and procurement documents shall specify the deadline for the submission of bids. Potential Bidders shall be allowed to inspect and purchase procurement documents at any time prior to the deadline for the submission of bids. c) Any Bidder/Consultant should be eligible to participate in a procurement process and to be awarded a Bank-financed contract as defined in paragraphs 3.21, 3.22 and 3.23 of the Procurement Regulations. d) Bidders/Consultants shall be allowed to submit bids/proposals by mail or in person. Bidders/consultants shall not be mandatory required to be present at the bid/proposal opening session. e) Bidders should not be required to register as a condition for inspecting or purchasing procurement documents, submitting its bid or receiving contract award. A winner Bidder, shall be given reasonable opportunity of registering (if required) before contract signing without any let or hindrance. Bidding shall not be restricted to any class of contractors. f) The winning bidder shall not be required, as a condition of award, to reduce its bid price No contract negotiation shall be permitted unless agreed in the procurement plan. g) No bid may be rejected solely on the basis that the bid price exceeds any cost estimate. Rejection of all bids or re-bidding shall not be allowed solely because the number of bids is less than three (3). Rebidding shall not take place without any sound justification. h) The Bank’s procurement documents for approaching the national market or any procurement document acceptable to the Bank shall be used. All procurement documents must require that bidders/consultants present a signed acceptance at the time of bidding or submitting a proposal, to be incorporated in any resulting contract, confirming application of and compliance with the Bank’s Anti- Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. i) The procurement documents shall disclose the newspaper and / or the electronic means in which the information on contract award shall be published. j) The contract award notification shall identify: (a) name and address of the Borrower’s Project Implementing Unit, (b) name and reference number of the contract being awarded and the selection method used (c) names of all Bidders/Consultants that submitted bids/proposals and their prices as read out at the bid opening meeting and as evaluated (d) names of all Bidders/ Consultants whose bids/proposals were rejected either as nonresponsive or as not meeting qualification criteria or were not evaluated, with the reasons therefor and (e) the name of the successful Bidder/Consultant, the final contract price, the contract duration and a summary of its scope. i) The Borrower shall implement an effective complaint mechanism allowing bidders or consultants to complain, and have their complaints handled and responded in a timely manner. Procurement documents should indicate the complaint mechanism procedure and provide the professional title and address of the officials to whom such protests should be sent. j) The Bank shall be allowed to review procurement documentation and activities related to the activities included in the procurement plan. C. Other national procurement arrangements: When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. D. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. E. Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations is not applicable: F. Domestic Preference as specified under paragraph 5.51 of the Procurement Regulations: Goods: Domestic Preference is applicable for those contracts identified in the Procurement Plan tables. Works: Domestic Preference is not applicable G. Other Relevant Procurement Information:. Please insert the Procurement Plan   PROCUREMENT PLAN FOR THE JIANGXI INTEGRATED RURAL AND URBAN WATER SUPPLY AND WASTEWATER MANAGEMENT PROJECT Date of procurement plan:   1 USD = 6.68 RMB               2019/ Estim Estima Estim Estim ated Origin Estimate Lo New Fundi ted ated Procur Evalu Bank ated Date al Contr Market d Date N ca Contr ng Contract Cost Cost ement ation Review Date of Contr act Metho of Remarks o. tio act Sourc Name (10,00 (10,0 Metho Stand (Prior/P of Bid Contr act Type d Advertis n No. e 0 00 d ard ost  Open act No. ement RMB  USD  ning Signi ng Purchasing Contract on Ductile Iron Pipe for Pipes for Water Supply raw water Infrastructur pipeline e Lump Open / project from D Construction Lowes SH- -sum Reque Domes Hengshan on SHST- World and t DX- Contr 1522.3 227.9 st for tic / 2019. 2019. reservoir- 1 gx WB- Bank Renovation Evalu Post 2019.6 GC- act / 7 0 Bid Post- 7 7 Chengdong ia 0049 Loan Project ated 01 Good (RFB  qualific waterworks ng (Water Cost s ation ,Hofang Intake Reservoir- Project) in Chengdong Dongxiang waterworks County loaned by the wold bank General Including Contract for the raw BoQ Construction water based of Water installation, Adme Open / D Supply Lowes intake asure Reque Domes on SH- SHST- World Infrastructur t pumping ment 1523.9 228.1 st for tic / 2019. 2019. 2 gx DX- WB- Bank e Evalu Post 2019.6 house and Contr 4 3 Bid Post- 7 7 ia SG-02 0050 Loan Construction ated integrated act / (RFB  qualific ng and Cost pumping Const ation Renovation station ructio Project works and n (Water equipment Intake installation. Project) in Dongxiang County loaned by the World Bank Purchasing Contract on Ductile Iron Pipe for Water Supply Infrastructur e Lump Open / Construction Lowes SH- -sum Reque Domes Le SHST- World and t LP- Contr 6457.6 966.7 st for tic / 2019. 2019. Raw water 3 pi WB- Bank Renovation Evalu Prior 2019.6 GC- act / 6 2 Bid Post- 7 7 installation ng 0051 Loan Project ated 01 Good (RFB  qualific (Water Cost s ation Intake Project) in Leping County, loaned by the wold bank General Contract for Construction Including of Water the raw BoQ Supply water based Infrastructur installation, Adme e Open / Lowes intake asure Construction Reque Domes Le SH- SHST- World t pumping ment and 8753.4 1310. st for tic / 2019. 2019. 4 pi LP- WB- Bank Evalu Prior 2019.6 house and Contr Renovation 3 39 Bid Post- 7 7 ng SG-01 0052 Loan ated integrated act / Project (RFB  qualific Cost pumping Const (Water ation station ructio Intake works and n Project) in equipment Leping installation. County loaned by the World Bank Purchasing Contract on Smart Water Meters for Leping Lump CouontyWate Open / Lowes -sum r Supply Reque Domes Le SH- SHST- World t Smart Contr Infrastructur 5005.8 749.3 st for tic / 2019. 2019. 5 pi LP- WB- Bank Evalu Prior 2019.6 Water act / e 0 7 Bid Post- 7 7 ng SB-01 0053 Loan ated Meters Good Construction (RFB  qualific Cost s and ation Renovation Project, loaned by the wold bank Purchasing Contract on Ductile Iron Pipe for Pipes Water Supply DN800 used Infrastructur from the e Lump Open / Emergency Construction Lowes Li SH- -sum Reque Domes water SHST- World and t nc LC- Contr st for tic / 2019. 2019. source 6 WB- Bank Renovation 444.48 66.54 Evalu Post 2019.6 hu GC- act / Bid Post- 7 7 intake 0054 Loan Project ated an 01 Good (RFB  qualific pumping (Water Cost s ation station to Intake Lingchuan Project) in NO.2 Linchuan waterworks County loaned by the wold bank . General Contract for Construction of Water Supply Including BoQ Infrastructur the based e installation Adme Construction Open / Lowes of raw Li asure and Reque Domes SH- SHST- World t water pipes nc ment Renovation 5113.0 765.4 st for tic / 2019. 2019. 7 LC- WB- Bank Evalu Post 2019.6 and the hu Contr Project 2 2 Bid Post- 7 7 SG-02 0055 Loan ated infrastructio an act / (Water (RFB  qualific Cost n Const Intake ation construction ructio Project and of new n Water Plant) waterworks in Linchuan County loaned by the world bank Purchasing Contract on Ductile Iron Pipe for Water Supply Infrastructur e Lump Open / Construction Lowes Xi SH- -sum Reque Domes SHST- World and t us XS- Contr 2801.7 419.4 st for tic / 2019. 2019. Raw water 8 WB- Bank Renovation Evalu Prior 2019.6 hu GC- act / 2 2 Bid Post- 7 7 pipeline 0056 Loan Project ated i 01 Good (RFB  qualific (Water Cost s ation Intake Project) in Xiushui County loaned by the wold bank General Including BoQ Contract for the raw based Construction water Adme Open / of Water Lowes installation, Xi asure Reque Domes SH- SHST- World Supply t intake us ment 4154.7 621.9 st for tic / 2019. 2019. 9 XS- WB- Bank Infrastructur Evalu Post 2019.6 pumping hu Contr 0 6 Bid Post- 7 7 SG-01 0057 Loan e ated house and i act / (RFB  qualific Construction Cost integrated Const ation and pumping ructio Renovation station n Project works and (Water equipment Intake installation. Project) in Xiushui County loaned by the World Bank Purchasing Contract on Smart Water Meters for Leping Lump CouontyWate Open / Lowes Xi -sum r Supply Reque Domes SH- SHST- World t Smart 1 us Contr Infrastructur 4326.0 647.6 st for tic / 2019. 2019. XS- WB- Bank Evalu Prior 2019.6 Water 0 hu act / e 0 0 Bid Post- 7 7 SB-01 0058 Loan ated Meters i Good Construction (RFB  qualific Cost s and ation Renovation Project, loaned by the wold bank General Contract on Including BoQ Pipeline general based Installation contracting Adme for Xiushui Open / Lowes for Pipeline asure County Reque Domes Zh SH- SHST- World t installation, 1 ment Zhajin 3126.4 468.0 st for tic / 2019. 2019. aji XSZJ- WB- Bank Evalu Post 2019.6 newly built 1 Contr Township 6 3 Bid Post- 7 7 n SG-02 0059 Loan ated inspection act / Wastewater (RFB  qualific Cost wells,house Const management ation hold ructio Project connection n loaned by project the world bank Purchasing Contract on Lump PE Pipes for Open / Lowes -sum Xiushui Reque Domes Zh SH- SHST- World t 1 Contr County 1072.5 160.5 st for tic / 2019. 2019. aji XSZJ- WB- Bank Evalu Post 2019.6 PE Pipes 2 act / Zhajin 1 6 Bid Post- 7 7 n PE-03 0060 Loan ated Good Township (RFB  qualific Cost s Wastewater ation management Project loaned by the world bank Purchasing Contract on Ductile Iron Pipe for Water Supply Infrastructur e Lump Open / Construction Lowes Yo SH- -sum Reque Domes Pipes for SHST- World and t 1 ng YX- Contr 4335.5 649.0 st for tic / 2019. 2019. water WB- Bank Renovation Evalu Prior 2019.6 3 xi GC- act / 8 4 Bid Post- 7 7 intake 0061 Loan Project ated n 01 Good (RFB  qualific projects (Water Cost s ation Intake Project) in Yongxin County loaned by the wold bank General Contract for Construction of Water Including Supply the raw BoQ Infrastructur water based e installation, Adme Open / Construction Lowes intake Yo asure Reque Domes SH- SHST- World and t pumping 1 ng ment 6163.7 922.7 st for tic / 2019. 2019. YX- WB- Bank Renovation Evalu Post 2019.6 house and 4 xi Contr 1 1 Bid Post- 7 7 SG-01 0062 Loan Project ated integrated n act / (RFB  qualific (Water Cost pumping Const ation Intake station ructio Project) in works and n Yongxin equipment County installation. loaned by the World Bank Purchasing Contract on Smart Water Meters for Yongxin Lump CouontyWate Open / Lowes Yo -sum r Supply Reque Domes SH- SHST- World t Smart 1 ng Contr Infrastructur st for tic / 2019. 2019. YX- WB- Bank 324.82 48.63 Evalu Post 2019.6 Water 5 xi act / e Bid Post- 7 7 SB-01 0063 Loan ated Meters n Good Construction (RFB  qualific Cost s and ation Renovation Project, loaned by the wold bank Purchasing contract WB Integrated Rural and Urban Water Lump all Supply and Reque Lowes -sum co SH- SHST- World Wastewater st for t 1 Contr Domes 2019. 2019. Office un BG- WB- Bank Management 92.40 13.83 Quota Evalu Post 2019.6 6 act / tic 7 7 Supplies tie 01 0064 Loan Project tion ated Good s Provision of (RFQ  Cost s Office Supplies for the Project Management Office Purchasing contract on Vehicle for Jiangxi Lump all Integrated Reque Lowes -sum co SH- SHST- World Rural and st for t 1 Contr Domes 2019. 2019. un BG- WB- Bank Urban Water 150.00 22.46 Quota Evalu Post 2019.6 Vehicle 7 act / tic 7 7 tie 01 0065 Loan Supply and tion ated Good s Wastewater (RFQ  Cost s Management Projec ,loane d by the world bank Purchasing Contract on Ductile Iron Lump Open / D Pipe for Lowes PT- -sum Reque Domes on SHST- World urban water t 1 DX- Contr 2233.0 314.5 st for tic / 2019.1 gx WB- Bank supply Evalu Post 2019.10 2019.11 8 GC- act / 0 1 Bid Post- 1 ia 0092 Loan network ated 01 Good (RFB  qualific ng reconstructio Cost s ation n in Dongxiang County Purchasing Contract on Lump Ductile Iron Open / Lowes PT- -sum Pipe for Reque Domes Le SHST- World t 1 LP- Contr urban water 129.5 st for tic / 2019.1 pi WB- Bank 919.98 Evalu Post 2019.10 2019.11 9 GC- act / supply 7 Bid Post- 1 ng 0093 Loan ated 03 Good network (RFB  qualific Cost s reconstructio ation n in Leping County Purchasing Contract on Lump Ductile Iron Open / Lowes Li PT- -sum Pipe for Reque Domes SHST- World t 2 nc LC- Contr urban water 1272.0 179.1 st for tic / 2019.1 WB- Bank Evalu Post 2019.10 2019.11 0 hu GC- act / supply 0 5 Bid Post- 1 0094 Loan ated an 02 Good network (RFB  qualific Cost s reconstructio ation n in Linchuan County Purchasing Contract on Lump Ductile Iron Open / Lowes Xi PT- -sum Pipe for Reque Domes SHST- World t 2 us XS- Contr urban water 3066.0 431.8 st for tic / 2019.1 WB- Bank Evalu Prior 2019.10 2019.11 1 hu GC- act / supply 0 3 Bid Post- 1 0095 Loan ated i 03 Good network (RFB  qualific Cost s reconstructio ation n in Xiushui County Purchasing Contract on Lump Ductile Iron Open / Lowes Yo PT- -sum Pipe for Reque Domes SHST- World t 2 ng YX- Contr urban water st for tic / 2019.1 WB- Bank 275.00 38.73 Evalu Post 2019.10 2019.11 2 xi GC- act / supply Bid Post- 1 0096 Loan ated n 02 Good network (RFB  qualific Cost s reconstructio ation n in Yongxin County PROCUREMENT China : Jiangxi Integrated Rural and Urban Water Supply and Wastewater Management Project PLAN General Information Country: China Bank’s Approval Date of the Original Procurement Plan: 2019-05-28 2021-05-29 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P158760 GPN Date: 2018-04-24 Project Name: Jiangxi Integrated Rural and Urban Water Supply and Wastewater Management Project Loan / Credit No: IBRD / 88490 J Executing Agency(ies): iangxi water WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned SHST-WB-0050 / Jiangxi Integrated Rural and Urban Water Supply and Wastewater Management Project loaned Expansion, Rehabilitation, by the World Bank—General Single Stage - One 2021-02- IBRD / 88490 and Modernization of Water Post Request for Bids Open - National 2,281,300.00 0.00 Canceled 2019-06-03 2019-06-08 2019-07-08 2019-07-15 2019-08-19 Contract for Construction of Envelope 17 Supply System Raw Water Pipe Installation Project at ChengDong Water Treatment Plant in Dongxiang County SHST-WB-0055 / Jiangxi Integrated Rural and Urban Water Supply and Wastewater Management Project loaned Expansion, Rehabilitation, by the World Bank—General Single Stage - One 6,107,417.3 2021-08- IBRD / 88490 and Modernization of Water Post Request for Bids Open - National 7,654,200.00 Signed 2019-06-03 2019-11-14 2019-06-08 2019-11-14 2019-07-08 2019-12-12 2019-07-15 2019-12-31 2019-08-19 2020-03-26 Contract for Water Plant Envelope 3 18 Supply System Construction Project and Raw Water Pipe installation Project of Linchuan NO.2 Water Treatment Plant SHST-WB-0059 / Jiangxi Integrated Rural and Urban Water Supply and Wastewater Management Project loaned by the World Bank—General Demonstration of Rural Single Stage - One 3,768,384.5 2021-08- IBRD / 88490 Post Request for Bids Open - National 4,680,300.00 Signed 2019-06-03 2019-11-14 2019-06-08 2019-11-14 2019-07-08 2019-12-12 2019-07-15 2019-12-31 2019-08-19 2020-03-25 Contract on Pipeline Wastewater Management Envelope 3 18 Installation for Xiushui County Zhajin Township Wastewater management Project SHST-WB-0068 / Jiangxi Integrated Rural and Urban Water Supply and Wastewater Management Project loaned Expansion, Rehabilitation, Single Stage - One 2021-11- by the World Bank—General IBRD / 88490 and Modernization of Water Post Request for Bids Open - National 8,439,500.00 0.00 Canceled 2019-08-25 2019-08-30 2019-09-29 2019-10-06 2019-11-10 Envelope 09 Contract for Construction of Supply System ChengDong Water Treatment Plant project in Dongxiang County SHST-WB-0070 / Jiangxi Integrated Rural and Urban Water Supply and Wastewater Management Project loaned Expansion, Rehabilitation, Single Stage - One 1,749,048.6 2021-11- by the World Bank—General IBRD / 88490 and Modernization of Water Post Request for Bids Open - National 2,352,400.00 Signed 2019-08-25 2020-03-03 2019-08-30 2020-03-23 2019-09-29 2020-03-31 2019-10-09 2020-05-14 2019-11-13 2020-06-30 Envelope 3 12 Contract for Construction of Supply System rehabilitation and expansion project at RunQuan and LiLin Water Plant in Leping County SHST-WB-0072 / Jiangxi Integrated Rural and Urban Water Supply and Wastewater Management Project loaned Expansion, Rehabilitation, Single Stage - One 1,568,156.6 2021-05- by the World Bank—General IBRD / 88490 and Modernization of Water Post Request for Bids Open - National 3,355,800.00 Signed 2019-08-25 2020-03-03 2019-08-30 2020-03-23 2019-09-29 2020-03-31 2019-10-09 2020-05-14 2019-11-13 2020-06-30 Envelope 3 14 Contract for rehabilitation Supply System and expansion Project of Xiushui No.3 Water Treatment Plant SHST-WB-0073 / Jiangxi Integrated Rural and Urban Water Supply and Wastewater Management Project loaned Expansion, Rehabilitation, Single Stage - One 13,262,600.0 9,211,763.2 2021-11- by the World Bank—General IBRD / 88490 and Modernization of Water Post Request for Bids Open - National Signed 2019-08-25 2020-03-03 2019-08-30 2020-03-23 2019-09-29 2020-03-31 2019-10-09 2020-05-14 2019-11-13 2020-07-02 Envelope 0 8 12 Contract for Construction of Supply System ChengNan water treatment plant project in Yongxin County SHST-WB-0052 / Jiangxi Integrated Rural and Urban Water Supply and Wastewater Management Project loaned Expansion, Rehabilitation, Single Stage - One 6,087,119.6 2021-02- by the World Bank—General IBRD / 88490 and Modernization of Water Prior Request for Bids Open - National 6,442,900.00 Signed 2019-06-03 2019-08-31 2019-06-08 2019-09-11 2019-07-08 2019-10-11 2019-07-15 2019-11-07 2019-08-19 2019-12-30 Envelope 6 16 Contract for Raw Water Pipe Supply System Installation Project of RunQuan Water Treatment Plant in Leping County SHST-WB-0057 / Jiangxi Integrated Rural and Urban Water Supply and Wastewater Management Project loaned Expansion, Rehabilitation, Single Stage - One 1,711,008.6 2021-02- by the World Bank—General IBRD / 88490 and Modernization of Water Post Request for Bids Open - National 1,804,200.00 Signed 2019-06-03 2019-09-05 2019-06-08 2019-09-09 2019-07-08 2019-10-11 2019-07-15 2019-11-06 2019-08-19 2019-12-30 Envelope 4 17 Contract for Construction of Supply System Raw Water Pipe Installation Project at Xiushui NO.3 Water Treatment Plant Page 1 SHST-WB-0062 / Jiangxi Integrated Rural and Urban Water Supply and Wastewater Management Project loaned Expansion, Rehabilitation, Single Stage - One 3,250,711.9 2021-02- by the World Bank—General IBRD / 88490 and Modernization of Water Post Request for Bids Open - National 3,429,300.00 Signed 2019-06-03 2019-09-05 2019-06-08 2019-09-09 2019-07-08 2019-10-11 2019-07-15 2019-11-06 2019-08-19 2019-12-16 Envelope 6 17 Contract for Raw Water Pipe Supply System Installation Project of ChengNan Water Treatment Plant in Yongxin County SHST-SH-0097 / General Contract for Construction of Expansion, Rehabilitation, ChengDong Water Treatment Single Stage - One 9,188,436.6 2022-01- IBRD / 88490 and Modernization of Water Post Request for Bids Open - National 8,450,700.00 Signed 2019-10-30 2019-11-14 2019-11-04 2019-11-14 2019-12-04 2019-12-12 2019-12-19 2019-12-31 2020-01-23 2020-03-11 Plant project and Raw Water Envelope 5 22 Supply System Pipe Installation project in Dongxiang County SHST-WB-0127 / General Construction contract on installation of rural water Expansion, Rehabilitation, Single Stage - One 7,997,675.7 2021-09- distribution network and IBRD / 88490 and Modernization of Water Post Request for Bids Open - National 8,028,200.00 Signed 2020-07-01 2020-08-11 2020-07-06 2020-08-11 2020-08-05 2020-09-10 2020-08-20 2020-10-11 2020-09-24 2020-12-08 Envelope 2 24 reconstruction of water supply Supply System network in some urban areas of Dongxiang District SHST-WB-0128 / General Construction Contract on rural water distribution network in Expansion, Rehabilitation, Jinxi County, water plant Single Stage - One 5,351,659.7 2021-09- IBRD / 88490 and Modernization of Water Post Request for Bids Open - National 8,450,700.00 Signed 2020-07-01 2020-08-11 2020-07-06 2020-08-11 2020-08-05 2020-09-10 2020-08-20 2020-10-11 2020-09-24 2021-03-18 construction at Huangtong Envelope 0 24 Supply System Township and part of the urban water supply network reconstruction in Jinxi County SHST-WB-0130 / General Construction contract on installation of rural water Expansion, Rehabilitation, Single Stage - One 2,799,382.4 2021-09- distribution network and IBRD / 88490 and Modernization of Water Post Request for Bids Open - National 3,413,700.00 Signed 2020-07-01 2020-08-11 2020-07-06 2020-08-11 2020-08-05 2020-09-10 2020-08-20 2020-10-20 2020-09-24 2021-01-05 Envelope 1 24 reconstruction of water supply Supply System network in some urban area of Linchuan County SHST-WB-0131 / General Construction contract on installation of rural water Expansion, Rehabilitation, Single Stage - One 14,084,500.0 2021-09- distribution network and IBRD / 88490 and Modernization of Water Prior Request for Bids Open - National 0.00 Canceled 2020-07-01 2020-07-30 2020-07-06 2020-08-09 2020-08-05 2020-09-10 2020-08-20 2020-11-19 2020-09-24 Envelope 0 24 reconstruction of water supply Supply System network in some urban areas of Xiushui County SHST-WB-0132 / General Construction contract on installation of rural water Expansion, Rehabilitation, Single Stage - One 6,608,050.5 2021-09- distribution network and IBRD / 88490 and Modernization of Water Post Request for Bids Open - National 5,633,800.00 Signed 2020-07-01 2020-08-11 2020-07-06 2020-08-11 2020-08-05 2020-09-10 2020-08-20 2020-10-20 2020-09-24 2021-03-18 Envelope 3 24 reconstruction of water supply Supply System network in some urban areas of Yongxin County SHST-WB-0133 / General Construction contract on Expansion, Rehabilitation, Single Stage - One 3,087,172.1 2021-09- installation of rural water IBRD / 88490 and Modernization of Water Post Request for Bids Open - National 3,943,700.00 Signed 2020-07-01 2020-08-11 2020-07-06 2020-08-11 2020-08-05 2020-09-10 2020-08-20 2020-10-20 2020-09-24 2020-12-10 Envelope 5 24 distribution network in Supply System Nanfeng County SHST-WB-0129 / General Construction contract on installation of rural water Expansion, Rehabilitation, Single Stage - One 8,879,969.1 2021-11- distribution network and IBRD / 88490 and Modernization of Water Post Request for Bids Open - National 4,368,000.00 Signed 2020-07-19 2020-08-11 2020-07-24 2020-08-11 2020-09-04 2020-09-10 2020-10-04 2020-10-11 2020-11-08 2021-03-18 Envelope 5 08 reconstruction of water supply Supply System network in some urban areas of Leping county SHST-WB-0131-1 / General Construction contract on installation of rural water Expansion, Rehabilitation, Under Single Stage - One 20,704,200.0 2021-12- distribution network and IBRD / 88490 and Modernization of Water Prior Request for Bids Open - National 0.00 Implementat 2021-03-12 2021-03-23 2021-03-17 2021-04-02 2021-04-28 2021-05-07 2021-05-28 2021-06-15 2021-07-02 Envelope 0 29 reconstruction of water supply Supply System ion network in some urban areas of Xiushui County GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SHST-WB-0063 / Jiangxi Integrated Rural and Urban Water Supply and Wastewater Management Project loaned Expansion, Rehabilitation, Single Stage - One by the World IBRD / 88490 and Modernization of Water Post Request for Bids Open - National 486,300.00 421,719.06 Signed 2019-06-03 2020-01-16 2019-06-08 2020-01-16 2019-07-08 2020-03-26 2019-07-15 2020-05-20 2019-08-19 2020-07-03 2020-08-18 Envelope Bank—Purchasing Contract on Supply System Smart Water Meters for urban water supply network reconstruction in Yongxin County SHST-WB-0058 / Jiangxi Integrated Rural and Urban Water Supply and Wastewater Management Project loaned Expansion, Rehabilitation, Single Stage - One by the World IBRD / 88490 and Modernization of Water Prior Request for Bids Open - National 6,476,000.00 3,393,075.78 Signed 2019-06-03 2020-01-11 2019-06-08 2020-01-16 2019-07-08 2020-03-26 2019-07-15 2020-05-19 2019-08-19 2020-06-23 2020-08-18 Envelope Bank—Purchasing Contract on Supply System Smart Water Meters for urban water supply network reconstruction in Xiushui County SHST-WB-0049 / Jiangxi Integrated Rural and Urban Water Supply and Wastewater Management Project loaned Expansion, Rehabilitation, by the World Single Stage - One IBRD / 88490 and Modernization of Water Post Request for Bids Open - National 2,279,000.00 1,540,379.09 Signed 2019-06-03 2019-11-19 2019-06-08 2019-11-19 2019-07-08 2020-01-06 2019-07-15 2020-01-06 2019-08-19 2020-04-15 2020-08-18 Bank—Purchasing Contract on Envelope Supply System Ductile Iron Pipe for Raw Water Pipe Installation Project of ChengDong Water Treatment Plant in Dongxiang County Page 2 SHST-WB-0053 / Jiangxi Integrated Rural and Urban Water Supply and Wastewater Management Project loaned Expansion, Rehabilitation, Single Stage - One by the World IBRD / 88490 and Modernization of Water Prior Request for Bids Open - National 7,493,700.00 2,332,483.15 Signed 2019-06-03 2020-01-11 2019-06-08 2020-01-16 2019-07-08 2020-03-26 2019-07-15 2020-05-19 2019-08-19 2020-06-23 2020-08-18 Envelope Bank—Purchasing Contract on Supply System Smart Water Meters for urban water supply network reconstruction in Leping County SHST-WB-0060 / Jiangxi Integrated Rural and Urban Water Supply and Wastewater Management Project loaned Demonstration of Rural Single Stage - One by the World IBRD / 88490 Post Request for Bids Open - National 1,605,600.00 1,357,501.00 Signed 2019-06-03 2019-11-19 2019-06-08 2019-11-19 2019-07-08 2019-12-17 2019-07-15 2020-01-10 2019-08-19 2020-03-20 2020-08-18 Wastewater Management Envelope Bank—Purchasing Contract on HDPE Pipes for Xiushui County Zhajin Township Wastewater management Project SHST-WB-0054 / Jiangxi Integrated Rural and Urban Water Supply and Wastewater Management Project loaned Expansion, Rehabilitation, by the World Single Stage - One IBRD / 88490 and Modernization of Water Post Request for Bids Open - National 665,400.00 464,961.69 Signed 2019-06-03 2019-11-19 2019-06-08 2019-11-19 2019-07-08 2020-01-06 2019-07-15 2020-01-06 2019-08-19 2020-04-15 2020-08-18 Bank—Purchasing Contract on Envelope Supply System Ductile Iron Pipe for Raw Water Pipe Installation Project of Linchuan NO.2 Water Treatment Plant SHST-WB-0065 / Jiangxi Integrated Rural and Urban Water Supply and Wastewater Public Engagement and Request for Single Stage - One Management Project loaned IBRD / 88490 Post Limited 224,600.00 140,398.94 Signed 2019-06-08 2019-11-07 2019-07-28 2019-12-10 2020-01-24 Project Management Quotations Envelope by the World Bank—Purchasing contract on Vehicle for the Project SHST-WB-0064 / Jiangxi Integrated Rural and Urban Water Supply and Wastewater Management Project loaned Public Engagement and Request for Single Stage - One IBRD / 88490 Post Limited 138,300.00 65,137.22 Signed 2019-06-08 2019-12-04 2019-07-28 2020-01-16 2020-01-24 by the World Project Management Quotations Envelope Bank—Purchasing contract on Provision of Office Supplies for the Project Management Office SHST-WB-0069 / Jiangxi Integrated Rural and Urban Water Supply and Wastewater Management Project loaned Expansion, Rehabilitation, Request for Single Stage - One by the World IBRD / 88490 and Modernization of Water Post Limited 373,100.00 0.00 Canceled 2019-08-30 2019-10-19 2020-04-16 Quotations Envelope Bank—Purchasing contract on Supply System Floating Pumping Station for Water Intake Project of Hengshan Reservoir in Dongxiang County SHST-WB-0071 / Jiangxi Integrated Rural and Urban Water Supply and Wastewater Management Project loaned Expansion, Rehabilitation, Pending by the World Single Stage - One IBRD / 88490 and Modernization of Water Post Request for Bids Open - National 625,300.00 0.00 Implementati 2019-08-25 2019-08-30 2019-09-29 2019-10-09 2019-11-13 2020-11-12 Bank—Purchasing contract on Envelope Supply System on Matching Equipment for Modernization and Reconstruction in Linchuan No.1 Water treatment plant SHST-WB-0074 / Jiangxi Integrated Rural and Urban Water Supply and Wastewater Management Project loaned Expansion, Rehabilitation, Single Stage - One by the World IBRD / 88490 and Modernization of Water Post Request for Bids Open - National 1,197,600.00 722,749.67 Signed 2019-08-25 2019-10-15 2019-08-30 2019-10-14 2019-09-29 2019-11-21 2019-10-09 2019-12-24 2019-11-13 2020-03-16 2020-11-12 Envelope Bank—Purchasing contract on Supply System Valves for Raw Water Pipe Installation Project in Leping,Xiushui and Yongxin County SHST-WB-0051 / Jiangxi Integrated Rural and Urban Water Supply and Wastewater Management Project loaned Expansion, Rehabilitation, by the World Single Stage - One IBRD / 88490 and Modernization of Water Prior Request for Bids Open - National 11,994,400.00 10,363,507.16 Signed 2019-06-03 2019-08-19 2019-06-08 2019-08-23 2019-07-08 2019-09-29 2019-07-15 2019-10-25 2019-08-19 2019-12-16 2020-08-18 Bank—Purchasing Contract on Envelope Supply System Ductile Iron Pipe for Raw Water Pipe Installation Project of RunQuan Water Treatment Plant in Leping County SHST-WB-0061 / Jiangxi Integrated Rural and Urban Water Supply and Wastewater Management Project loaned Expansion, Rehabilitation, by the World Single Stage - One IBRD / 88490 and Modernization of Water Prior Request for Bids Open - National 7,682,400.00 6,718,546.18 Signed 2019-06-03 2019-08-19 2019-06-08 2019-08-28 2019-07-08 2019-09-29 2019-07-15 2019-10-25 2019-08-19 2019-12-16 2020-08-18 Bank—Purchasing Contract on Envelope Supply System Ductile Iron Pipe for Raw Water Pipe Installation Project of ChengNan Water Treatment Plant in Yongxin County SHST-WB-0056 / Jiangxi Integrated Rural and Urban Water Supply and Wastewater Management Project loaned Expansion, Rehabilitation, Single Stage - One by the World IBRD / 88490 and Modernization of Water Post Request for Bids Open - National 2,818,600.00 2,501,795.98 Signed 2019-06-03 2019-08-21 2019-06-08 2019-08-21 2019-07-08 2019-09-29 2019-07-15 2019-10-26 2019-08-19 2019-12-16 2020-08-18 Envelope Bank—Purchasing Contract on Supply System Ductile Iron Pipe for Raw Water Pipe Installation Project of Xiushui NO.3 Water Treatment Plant SHST-WB-0092 / Purchase Contract on ductile iron pipe for reconstruction of pipe Expansion, Rehabilitation, Single Stage - One network for urban water IBRD / 88490 and Modernization of Water Post Request for Bids Open - National 3,686,000.00 3,654,811.89 Signed 2019-10-21 2019-11-19 2019-10-26 2019-11-19 2019-11-25 2020-01-06 2019-12-10 2020-01-06 2020-01-14 2020-04-15 2023-01-13 Envelope supply and extension of rural Supply System pipe network in Dongxiang county Page 3 SHST-WB-0093 / Purchase Contract on ductile iron pipe Expansion, Rehabilitation, for reconstruction of pipe Single Stage - One IBRD / 88490 and Modernization of Water Prior Request for Bids Open - National 5,614,100.00 3,884,383.04 Signed 2019-10-21 2019-11-15 2019-10-26 2019-11-20 2019-11-25 2020-01-06 2019-12-10 2020-03-24 2020-01-14 2020-04-29 2023-01-13 network for urban water Envelope Supply System supply and extension of rural pipe network in Leping County SHST-WB-0094 / Purchase Contract on ductile iron pipe for reconstruction of pipe Expansion, Rehabilitation, Single Stage - One network for urban water IBRD / 88490 and Modernization of Water Post Request for Bids Open - National 2,806,500.00 2,803,583.14 Signed 2019-10-21 2019-11-19 2019-10-26 2019-11-19 2019-11-25 2020-01-06 2019-12-10 2020-01-06 2020-01-14 2020-04-15 2023-01-13 Envelope supply and extension of rural Supply System pipe network in Linchuan County SHST-WB-0095 / Purchase Contract on ductile iron pipe for reconstruction of pipe Expansion, Rehabilitation, Single Stage - One network for urban water IBRD / 88490 and Modernization of Water Prior Request for Bids Open - National 11,074,800.00 9,593,788.11 Signed 2019-10-21 2019-11-15 2019-10-26 2019-11-20 2019-11-25 2020-01-06 2019-12-10 2020-03-25 2020-01-14 2020-04-29 2023-01-13 Envelope supply and extension of rural Supply System pipe network in Xiushui County SHST-WB-0096 / Purchase Contract on ductile iron pipe for reconstruction of pipe Expansion, Rehabilitation, Single Stage - One network for urban water IBRD / 88490 and Modernization of Water Prior Request for Bids Open - National 4,111,200.00 4,215,409.66 Signed 2019-10-21 2019-11-15 2019-10-26 2019-11-20 2019-11-25 2020-01-06 2019-12-10 2020-03-24 2020-01-14 2020-04-29 2023-01-13 Envelope supply and extension of rural Supply System pipe network in Yongxin County SHST-WB-0111 / Purchase contract of electrical equipments for construction, Expansion, Rehabilitation, Single Stage - One rehabilitation and expansion IBRD / 88490 and Modernization of Water Prior Request for Bids Open - National 5,070,400.00 1,802,137.63 Signed 2020-06-25 2020-07-19 2020-06-30 2020-07-24 2020-07-30 2020-08-31 2020-08-14 2020-11-10 2020-09-18 2020-12-09 2021-09-18 Envelope of water plant in Leping, Supply System Dongxiang, Yongxin, Linchuan and Xiushui counties SHST-WB-0112 / Purchase contract of process equipments for construction, Expansion, Rehabilitation, Single Stage - One rehabilitation and expansion IBRD / 88490 and Modernization of Water Prior Request for Bids Open - National 6,338,000.00 5,922,229.19 Signed 2020-06-25 2020-07-19 2020-06-30 2020-07-23 2020-07-30 2020-08-31 2020-08-14 2020-11-19 2020-09-18 2020-12-20 2021-09-18 Envelope of water plant in Leping, Supply System Dongxiang, Yongxin, Linchuan and Xiushui counties SHST-WB-0113 / Purchase contract of automatic control equipments for construction, Expansion, Rehabilitation, Single Stage - One rehabilitation and expansion IBRD / 88490 and Modernization of Water Post Request for Bids Open - National 2,323,900.00 1,204,975.09 Signed 2020-06-25 2020-07-23 2020-06-30 2020-07-23 2020-07-30 2020-08-31 2020-08-14 2020-09-17 2020-09-18 2020-11-30 2021-09-18 Envelope of water plant in Leping, Supply System Dongxiang, Yongxin, Linchuan and Xiushui counties SHST-WB-0114 / Purchase contract of valves for construction, rehabilitation Expansion, Rehabilitation, Single Stage - One and expansion of water plant IBRD / 88490 and Modernization of Water Post Request for Bids Open - National 2,816,900.00 2,707,491.96 Signed 2020-06-25 2020-07-23 2020-06-30 2020-07-23 2020-07-30 2020-12-10 2020-08-14 2020-12-10 2020-09-18 2021-01-20 2021-09-18 Envelope in Leping, Dongxiang, Supply System Yongxin, Linchuan and Xiushui counties SHST-WB-0115 / Purchase contract of water pumps for construction, rehabilitation Expansion, Rehabilitation, Single Stage - One and expansion of water plant IBRD / 88490 and Modernization of Water Post Request for Bids Open - National 2,957,700.00 651,839.04 Signed 2020-06-25 2020-07-23 2020-06-30 2020-07-23 2020-07-30 2020-08-31 2020-08-14 2020-09-17 2020-09-18 2020-11-20 2021-09-18 Envelope in Leping, Dongxiang, Supply System Yongxin, Linchuan and Xiushui counties SHST-WB-0119 / Purchase C ontract on PE pipe for rural pi Expansion, Rehabilitation, peline installation from villag Single Stage - One IBRD / 88490 and Modernization of Water Post Request for Bids Open - National 2,911,800.00 2,475,882.82 Signed 2020-07-05 2020-07-10 2020-07-10 2020-07-13 2020-08-09 2020-08-13 2020-08-24 2020-08-27 2020-09-28 2020-10-26 2021-09-28 e to household) in Nanfeng, L Envelope Supply System eping county and Linchuan co unty of Fuzhou City SHST-WB-0124 / The Second Purchase Contract on ductile iron pipe for reconstruction of pipe network for urban water Expansion, Rehabilitation, Single Stage - One supply and extension of rural IBRD / 88490 and Modernization of Water Post Request for Bids Open - National 2,920,400.00 3,467,504.12 Signed 2020-07-12 2020-07-10 2020-07-17 2020-07-13 2020-08-16 2020-08-13 2020-08-31 2020-08-27 2020-10-05 2020-10-26 2021-10-05 Envelope pipe network in Supply System Yongxin,Xiushui,Nanfeng County and Linchuan county of Fuzhou City SHST-WB-0123 / The Second Purchase Contract on ductile iron pipe for reconstruction of Expansion, Rehabilitation, pipe network for urban water Single Stage - One IBRD / 88490 and Modernization of Water Post Request for Bids Open - National 3,810,500.00 1,885,187.85 Signed 2020-07-05 2020-07-10 2020-07-10 2020-07-13 2020-08-09 2020-08-13 2020-08-24 2020-08-27 2020-09-28 2020-10-26 2021-09-28 supply and extension of rural Envelope Supply System pipe network in Leping, Jinxi county and Dongxiang of Fuzhou city SHST-WB-0120 / Purchase Contract on PE pipe for urban pipeline reconstruction and Expansion, Rehabilitation, rural pipeline installation(from Single Stage - One IBRD / 88490 and Modernization of Water Post Request for Bids Open - National 3,411,600.00 2,727,750.86 Signed 2020-07-12 2020-07-10 2020-07-17 2020-07-13 2020-08-28 2020-08-13 2020-09-27 2020-08-27 2020-11-01 2020-10-26 2021-11-01 village to household) in Envelope Supply System Yongxin,Xiushui,Jinxi County and Dongxiang county of Fuzhou City SHST-WB-0121 / Purchasing Contract on smart water meters for reconstruction of Expansion, Rehabilitation, Single Stage - One urban water supply network IBRD / 88490 and Modernization of Water Prior Request for Bids Open - National 4,881,400.00 0.00 Canceled 2020-08-20 2020-08-25 2020-10-06 2020-11-05 2020-12-10 2021-12-10 Envelope and for rural drinking water Supply System users newly increased in Dongxiang County Page 4 SHST-WB-0125 / Purchasing Contract on smart water meters for Reconstruction of Expansion, Rehabilitation, Under Single Stage - One urban water supply network IBRD / 88490 and Modernization of Water Post Request for Bids Open - National 3,730,400.00 1,380,394.18 Implementati 2020-08-20 2021-02-25 2020-08-25 2021-02-25 2020-10-06 2021-03-25 2020-11-05 2021-03-25 2020-12-10 2021-06-08 Envelope and for rural drinking water Supply System on users newly increased in Linchuan County SHST-WB-0126 / Purchasing Contract on Smart Water Meters for reconstruction of Expansion, Rehabilitation, Under Single Stage - One urban water supply network IBRD / 88490 and Modernization of Water Post Request for Bids Open - National 1,631,200.00 1,398,722.53 Implementati 2020-08-20 2021-02-25 2020-08-25 2021-02-25 2020-10-06 2021-03-25 2020-11-05 2021-03-25 2020-12-10 2021-12-10 Envelope and for rural drinking water Supply System on users newly increased in Nanfeng County SHST-WB-0135 / Purchasing Expansion, Rehabilitation, Contract on sensors used for Single Stage - One IBRD / 88490 and Modernization of Water Post Request for Bids Open - National 3,367,600.00 2,559,686.18 Signed 2020-08-25 2020-09-04 2020-08-30 2020-09-04 2020-10-11 2020-10-13 2020-11-10 2020-10-13 2020-12-15 2020-11-25 2021-06-13 pipe network of smart water Envelope Supply System supply system SHST-WB-0138 / Purchasing Contract on Smart Water Meters for reconstruction of Expansion, Rehabilitation, Under Single Stage - One urban water supply network IBRD / 88490 and Modernization of Water Post Request for Bids Open - National 2,647,900.00 976,232.66 Implementati 2020-11-10 2021-02-25 2020-11-15 2021-02-25 2020-12-27 2021-03-25 2021-01-26 2021-03-25 2021-03-02 2021-08-29 Envelope and for rural drinking water Supply System on users newly increased in Jinxi County SHST-WB-0152 / Purchasing contract on Floating Pumping Expansion, Rehabilitation, Under Station for Water Intake Single Stage - One IBRD / 88490 and Modernization of Water Post Request for Bids Open - National 769,200.00 0.00 Implementati 2021-02-22 2021-02-20 2021-02-27 2021-02-21 2021-03-29 2021-03-19 2021-04-28 2021-03-19 2021-06-02 2021-11-29 Project of Hengshan Reservoir Envelope Supply System on and Hefang Reservior in Dongxiang County SHST-WB-0121-1 / The First Purchase Contract on smart water meters for Expansion, Rehabilitation, Under Reconstruction of urban water Single Stage - One IBRD / 88490 and Modernization of Water Post Request for Bids Open - National 2,606,100.00 1,943,036.58 Implementati 2021-02-28 2021-02-25 2021-03-05 2021-02-25 2021-04-16 2021-03-25 2021-05-16 2021-03-25 2021-06-20 2021-12-17 supply network and for rural Envelope Supply System on drinking water users newly increased in Dongxiang County SHST-WB-0153 / The Second Purchase Contract on ductile iron pipe for reconstruction of pipe network for urban water Expansion, Rehabilitation, Under Single Stage - One supply and extension of rural IBRD / 88490 and Modernization of Water Prior Request for Bids Open - National 6,818,200.00 0.00 Implementati 2021-04-05 2021-04-01 2021-04-10 2021-04-02 2021-05-22 2021-05-08 2021-06-21 2021-06-01 2021-07-26 2022-01-22 Envelope pipe network in Supply System on Leping,Dongxiang,Jinxi,Yongx in,Xiushui,Linchuan and Nanfeng County SHST-WB-0155 / The Second Expansion, Rehabilitation, Pending Request for Single Stage - One Purchasing Contract on IBRD / 88490 and Modernization of Water Post Open - National 57,600.00 0.00 Implementati 2021-06-01 2021-07-27 2022-01-23 Quotations Envelope Vehicle for the Project Supply System on NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 5 PROCUREMENT PLAN (Textual Part) Project information: Caribbean Region, Caribbean Digital Transformation Program, P171528 Project Implementation agency: Organisation of Eastern Caribbean States (OECS) Date of the Procurement Plan: November 11, 2020. Period covered by this Procurement Plan: The whole project life. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: The implementing agency is not a national state; hence, there is not a national market and there are no national procurement regulations. This notwithstanding, the implementing agency’s procurement procedures (OECS Procurement Manual Revised June 2016) were found acceptable to the Bank and therefore they may be applied for the Procurement of Works, Goods and Non-consulting Services below the mandatory thresholds for international competition (as specified in the Procurement Plan tables in STEP). These procurements should be in accordance with paragraph 5.3, 5.4 and 5.5 of the Procurement Regulations.. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: not applicable Procurement of Second-Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – not applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: not applicable; Works: not applicable Other Relevant Procurement Information: The Implementing Agency will proceed with advance contracting in the amount of not exceeding SDR1,180,000.- (US$1.600,000.- equivalent) in accordance with the provisions of paragraph 5.1 – 5.2 of the Procurement Regulations. PROCUREMENT Caribbean : Caribbean Digital Transformation Project PLAN General Information Country: Caribbean Bank’s Approval Date of the Original Procurement Plan: 2020-11-11 2021-05-20 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P171528 GPN Date: 2021-01-20 Project Name: Caribbean Digital Transformation Project Loan / Credit No: IDA / 66790, IDA / 66820, IDA / 66850 M Executing Agency(ies): inistry of Public Works and Digital Economy WORKS Procureme Activity Reference No. / Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH nt Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) Justification for Award Type Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual DM-MPWDE-200369-CW- Pending Digital Skills and Technology Request for Single Stage - One 2022-09- RFQ / Refurbishment of co- IDA / 66850 Post Open - National 0.00 Implementat 2022-01-09 2022-03-06 Adoption Quotations Envelope 02 working space ion GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual DM-MPWDE-200381-GO-DIR Pending Project Implementation / Expansion of Smart Stream IDA / 66790 Post Direct Selection Direct 0.00 Implementati 2021-07-01 2021-07-06 2021-08-10 2022-02-06 Support functionality on DM-MPWDE-200376-GO-RFB / Systems integration, support with introduction of unique Digital Government Pending Single Stage - One digital identifier, development IDA / 66850 Infrastructure, Platforms and Post Request for Bids Open - International 0.00 Implementati 2021-11-01 2021-11-06 2021-12-18 2022-01-17 2022-02-21 2023-09-29 Envelope and implementation of citizen Services on authentication and digital signature solution DM-MPWDE-200379-GO-RFB Digital Government Pending / Supply and Installation of Single Stage - One IDA / 66850 Infrastructure, Platforms and Prior Request for Bids Open - International 0.00 Implementati 2022-08-02 2022-08-07 2022-09-18 2022-10-18 2022-11-22 2023-11-22 Health Management Envelope Services on Information System DM-MPWDE-200375-GO-RFB / Procurement of Hardware and Software Platform for Digital Government Pending Systems Integration and Single Stage - One IDA / 66850 Infrastructure, Platforms and Post Request for Bids Open - International 0.00 Implementati 2022-10-10 2022-10-15 2022-11-26 2022-12-26 2023-01-30 2023-07-29 Implementation of Unique Envelope Services on Digital Identifier, Citizen Authentication and Digital Signature DM-MPWDE-200377-GO-RFB Digital Government Pending Single Stage - One / Roll-out of National ID IDA / 66850 Infrastructure, Platforms and Post Request for Bids Open - International 0.00 Implementati 2023-07-31 2023-08-05 2023-09-16 2023-10-16 2023-11-20 2024-05-18 Envelope Cards Services on DM-MPWDE-200371-GO-RFB Digital Government Pending Single Stage - One / Supply and Installation of IDA / 66850 Infrastructure, Platforms and Post Request for Bids Open - International 0.00 Implementati 2022-10-04 2022-10-09 2022-11-20 2022-12-20 2023-01-24 2023-07-23 Envelope Cybersecurity System Services on DM-MPWDE-221583-GO-DIR Pending Project Implementation / Expansion of SmartStream IDA / 66850 Post Direct Selection Direct 0.00 Implementati 2021-07-01 2021-07-06 2021-08-10 2022-06-28 Support Functionality on DM-MPWDE-220448-CS- Digital Government Pending QCBS / Addition of e- Request for Single Stage - One IDA / 66850 Infrastructure, Platforms and Post Open - National 0.00 Implementati 2021-06-06 2021-08-01 2022-07-27 Payments Services on GoCD Quotations Envelope Services on Platform Under DM-MPWDE-200380-GO-RFB Digital Skills and Technology Single Stage - One IDA / 66850 Post Request for Bids Open - International 0.00 Implementati 2021-03-24 2021-03-26 2021-04-03 2021-03-30 2021-05-03 2021-04-30 2021-05-17 2021-05-07 2021-06-07 2021-08-06 / Procurement of Tablets Adoption Envelope on DM-MPWDE-220449-CS- QCBS / Establishment of an Digital Government Pending Single Stage - One online web and mobile portal IDA / 66850 Infrastructure, Platforms and Post Request for Bids Open - International 0.00 Implementati 2021-06-01 2021-06-06 2021-09-04 2021-10-04 2021-11-08 2023-09-29 Envelope for accessing public services Services on and information DM-MPWDE-200378-GO-RFB Digital Government Pending / Supply and installation of Single Stage - One IDA / 66850 Infrastructure, Platforms and Post Request for Bids Open - International 0.00 Implementati 2024-01-11 2024-01-16 2024-02-27 2024-03-28 2024-05-02 2024-10-29 immigration kiosks at ports Envelope Services on and airports NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual DM-MPWDE-200383-CS- Digital Government QCBS / TA for Digital Strategy, Quality And Cost- Pending IDA / 66850 Infrastructure, Platforms and Post Open - International 0.00 2021-07-01 2021-07-22 2021-09-04 2021-10-02 2021-11-01 2021-12-06 2022-01-10 2022-06-29 Standards, Business Based Selection Implementation Services Continuity and Protocols Page 1 DM-MPWDE-200487-CS- QCBS / Development and Digital Skills and Technology Quality And Cost- Pending IDA / 66850 Prior Open - International 0.00 2022-08-16 2022-09-06 2022-10-20 2022-11-17 2022-12-17 2023-01-21 2023-02-25 2024-02-25 Delivery of Digital Skills Adoption Based Selection Implementation Training DM-MPWDE-200485-CS- Digital Government Quality And Cost- Pending QCBS / Bulk Disbursements IDA / 66850 Infrastructure, Platforms and Prior Open - International 0.00 2022-12-12 2023-01-02 2023-02-15 2023-03-15 2023-04-14 2023-05-19 2023-06-23 2024-06-22 Based Selection Implementation Digitization Services DM-MPWDE-200489-CS- QCBS / Development and Digital Skills and Technology Quality And Cost- Pending IDA / 66850 Post Open - International 0.00 2022-08-16 2022-09-06 2022-10-20 2022-11-17 2022-12-17 2023-01-21 2023-02-25 2024-02-25 Delivery of Managerial Adoption Based Selection Implementation Training DM-MPWDE-200482-CS- QCBS / Development of Technical Requirements for ID Digital Government System Implementation and Quality And Cost- Pending IDA / 66850 Infrastructure, Platforms and Post Open - International 0.00 2021-10-01 2021-10-22 2021-12-05 2022-01-02 2022-02-01 2022-03-08 2022-04-12 2022-10-09 business process re- Based Selection Implementation Services engineering and end-to-end digitization of citizen facing services DM-MPWDE-200483-CS- QCBS / TA for Development of Digital Skills and Technology Quality And Cost- Pending IDA / 66850 Post Open - International 0.00 2022-07-01 2022-07-22 2022-09-04 2022-10-02 2022-11-01 2022-12-06 2023-01-10 2024-01-10 Electronic Entry Permit Adoption Based Selection Implementation Mechanism DM-MPWDE-200490-CS-CQS Consultant Digital Skills and Technology Pending / Digital content for distance IDA / 66850 Post Qualification Open - International 0.00 2022-12-08 2022-12-29 2023-02-11 2023-03-13 2023-04-17 2023-10-14 Adoption Implementation learning Selection DM-MPWDE-200492-CS- Project Implementation Quality And Cost- Under QCBS / Project IDA / 66850 Prior Open - International 0.00 2021-05-01 2021-06-15 2021-05-22 2021-06-21 2021-07-05 2021-08-02 2021-09-01 2021-10-06 2021-11-10 2026-06-22 Support Based Selection Implementation Implementation Support DM-MPWDE-200382-CS- QCBS / Support for Quality And Cost- Pending IDA / 66850 Digital Enabling Environment Post Open - International 0.00 2022-08-02 2022-08-23 2022-10-06 2022-11-03 2022-12-03 2023-01-07 2023-02-11 2024-02-11 Development of National Based Selection Implementation Cybersecurity Capability DM-MPWDE-220442-CS- QCBS / Development, Digital Government Quality And Cost- Pending Establishment and Adoption IDA / 66850 Infrastructure, Platforms and Post Open - International 0.00 2021-10-01 2021-10-22 2021-12-05 2022-01-02 2022-02-01 2022-03-08 2022-04-12 2023-04-12 Based Selection Implementation of a Digital Signature Services Framework DM-MPWDE-200484-CS- QCBS / Feasibility for Digital Government Quality And Cost- Pending Implementation of Health IDA / 66850 Infrastructure, Platforms and Post Open - International 0.00 2021-06-01 2021-06-22 2021-08-05 2021-09-02 2021-10-02 2021-11-06 2021-12-11 2022-07-29 Based Selection Implementation Management Information Services System DM-MPWDE-200480-CS- QCBS / TA for Review of Policies, Legislations and Regulations and Development of Recommendations on Digital Government Quality And Cost- Pending Necessary Reforms to IDA / 66850 Infrastructure, Platforms and Post Open - International 0.00 2021-05-02 2021-05-23 2021-07-06 2021-08-03 2021-09-02 2021-10-07 2021-11-11 2022-09-30 Based Selection Implementation Implement an Integrated ID Services System, Authentication Platform, Digital Signature and Electronic Entry Permit Mechanism INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Contract Type Process Status Teams of Reference Identified/Selected Signed Contract Contract Completion No. (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual DM-MPWDE-200496-CS- Individual Project Implementation INDV / Recruitment of Project IDA / 66820 Post Consultant Open 48,708.49 Signed 2020-11-02 2020-11-13 2020-12-21 2020-12-08 2021-01-11 2020-12-08 2021-02-15 2020-12-14 2021-08-14 Support Manager Selection DM-MPWDE-200499-CS- Individual Project Implementation INDV / Recruitment of IDA / 66820 Post Consultant Open 39,852.40 Terminated 2020-11-02 2020-11-16 2020-12-21 2020-12-03 2021-01-11 2021-04-05 2021-02-15 2020-12-14 2021-08-14 Support Procurement Specialist Selection DM-MPWDE-200501-CS- Individual INDV / Recruitment of Project Implementation IDA / 66820 Post Consultant Open 35,424.35 Signed 2020-11-02 2020-11-16 2020-12-21 2020-12-03 2021-01-11 2021-04-05 2021-02-15 2020-12-14 2021-08-14 Financial Management Support Selection Specialist DM-MPWDE-200504-CS- Individual Project Implementation Under INDV / Recruitment of IDA / 66820 Post Consultant Open 0.00 2021-01-01 2021-03-16 2021-02-19 2021-03-12 2021-04-16 2021-10-13 Support Implementation Safeguards Specialist, PIU Selection DM-MPWDE-227720-CS- Individual Project Implementation Pending INDV / Recruitment of IDA / 66850 Post Consultant Limited 0.00 2021-04-01 2021-04-06 2021-04-11 2021-04-15 2023-04-14 Support Implementation Procurement Specialist Selection DM-MPWDE-234257-CS- Individual Project Implementation Under INDV / Recruitment of IDA / 66820 Post Consultant Open 0.00 2020-11-02 2020-11-16 2020-12-21 2021-01-11 2021-02-15 2026-07-01 Support Implementation Procurement Specialist Selection Page 2 FOREST CONSERVATION AND SUSTAINABILITY IN THE HEART OF THE COLOMBIAN AMAZON PROJECT – TF018478 PROCUREMENT PLAN I. General 1. Bank’s approval Date of the procurement Plan 2. Date of General Procurement Notice: Dec 09, 2015 3. Period covered by this procurement plan: Until Dec 31, 2017 July 9, 2010 PROCUREMENT Colombia : Forest Conservation and Sustainability in the Heart of the Colombian Amazon PLAN General Information Country: Colombia Bank’s Approval Date of the Original Procurement Plan: 2017-10-12 2021-05-24 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P144271 GPN Date: Project Name: Forest Conservation and Sustainability in the Heart of the Colombian Amazon Loan / Credit No: TF / 18478, TF / A5789 Amazonian Institute of Scientific Research Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 3 - Sectoral CO-SINCHI-62172-GO-RFQ / Request for Single Stage - One TF / 18478 Programs for Sustainable Post Open - National 4,642.86 4,037.63 Completed 2018-09-17 2018-11-01 2019-01-14 2018-12-01 2019-04-24 Adquisición de balanzas Quotations Envelope Landscape Management Component 3 - Sectoral CO-SINCHI-62173-GO-RFQ / Request for Single Stage - One TF / 18478 Programs for Sustainable Post Open - National 7,142.86 6,073.89 Completed 2018-09-17 2018-11-01 2018-12-28 2018-12-31 2019-02-28 Adquisición de calibradores Quotations Envelope Landscape Management Component 3 - Sectoral CO-SINCHI-62175-GO-RFQ / Request for Single Stage - One TF / 18478 Programs for Sustainable Post Open - National 5,000.00 2,051.59 Completed 2018-09-17 2018-11-01 2018-12-21 2018-12-31 2019-02-21 Adquisición de barrenos Quotations Envelope Landscape Management CO-SINCHI-62177-GO-RFQ / Component 3 - Sectoral Adquisición de Request for Single Stage - One TF / 18478 Programs for Sustainable Post Open - National 5,357.14 0.00 Canceled 2018-09-17 2018-11-01 2018-12-01 conductimetros y Quotations Envelope Landscape Management multiparametrico CO-SINCHI-62178-GO-RFQ / Component 3 - Sectoral Adquisición de Request for Single Stage - One TF / 18478 Programs for Sustainable Post Open - National 2,468.76 1,438.28 Completed 2018-09-17 2018-11-01 2018-11-29 2018-12-01 2019-04-29 deshumidificadores Quotations Envelope Landscape Management industriales CO-SINCHI-62179-GO-RFQ / Component 3 - Sectoral Request for Single Stage - One Adquisición de agitador TF / 18478 Programs for Sustainable Post Open - National 1,714.29 882.65 Completed 2018-09-17 2018-11-01 2018-12-17 2018-12-31 2019-04-18 Quotations Envelope magnético Landscape Management Component 3 - Sectoral CO-SINCHI-77812-GO-RFQ / Request for Single Stage - One TF / 18478 Programs for Sustainable Post Open - National 18,700.43 13,837.87 Completed 2018-10-06 2018-11-04 2018-12-18 2019-01-03 2019-04-22 Adquisición de micrótomo Quotations Envelope Landscape Management Component 3 - Sectoral CO-SINCHI-77815-GO-RFQ / Request for Single Stage - One TF / 18478 Programs for Sustainable Post Open - National 1,428.57 2,294.54 Completed 2018-10-06 2018-11-04 2019-01-21 2019-01-03 2019-04-21 Contador de semillas Quotations Envelope Landscape Management Component 3 - Sectoral CO-SINCHI-77816-GO-RFQ / Request for Single Stage - One TF / 18478 Programs for Sustainable Post Open - National 1,079.69 918.62 Completed 2018-10-06 2018-11-04 2019-01-29 2019-01-03 2019-03-01 Phmetro digital Quotations Envelope Landscape Management CO-SINCHI-77818-GO-RFQ / Component 3 - Sectoral Request for Single Stage - One Centrífuga de mesas TF / 18478 Programs for Sustainable Post Open - National 7,500.00 4,918.77 Completed 2018-10-06 2018-11-04 2019-01-10 2019-01-03 2019-03-10 Quotations Envelope multifuncional Landscape Management Component 3 - Sectoral CO-SINCHI-77822-GO-RFQ / Request for Single Stage - One TF / 18478 Programs for Sustainable Post Open - National 7,044.64 6,216.79 Completed 2018-10-06 2018-11-04 2018-12-21 2019-01-03 2019-03-21 Tejas de Zinc Quotations Envelope Landscape Management Component 3 - Sectoral CO-SINCHI-20363-GO-RFB / Request for Single Stage - One TF / 18478 Programs for Sustainable Post Open - National 23,545.00 14,907.58 Completed 2018-10-20 2018-11-24 2019-04-30 2019-01-23 2019-06-30 Microscopio especializado Quotations Envelope Landscape Management Component 3 - Sectoral CO-SINCHI-82754-GO-RFQ / Request for Single Stage - One TF / 18478 Programs for Sustainable Post Open - National 26,714.29 0.00 Canceled 2018-11-06 2018-12-11 2019-02-09 Mobiliario para el laboratorio Quotations Envelope Landscape Management CO-SINCHI-83710-GO-RFQ / Component 3 - Sectoral Request for Single Stage - One Adquisición de equipos para TF / A5789 Programs for Sustainable Post Open - National 7,966.75 4,408.22 Completed 2018-12-08 2019-01-12 2019-04-26 2019-03-13 2019-05-30 Quotations Envelope ascenso y coberturas Landscape Management CO-SINCHI-83711-GO-RFQ / Component 3 - Sectoral Request for Single Stage - One Adquisición de equipos para TF / A5789 Programs for Sustainable Post Open - National 7,142.86 7,021.84 Completed 2018-12-08 2019-01-12 2019-12-31 2019-03-13 2020-04-30 Quotations Envelope suelos Landscape Management Component 3 - Sectoral CO-SINCHI-88273-GO-RFQ / Request for Single Stage - One TF / A5789 Programs for Sustainable Post Open - National 459.72 348.29 Completed 2018-12-17 2019-01-21 2019-02-05 2019-03-22 2019-02-20 Materiales para piscicultura Quotations Envelope Landscape Management CO-SINCHI-88274-GO-RFQ / Component 3 - Sectoral Request for Single Stage - One Alimento granulado para TF / A5789 Programs for Sustainable Post Open - National 1,158.62 667.35 Completed 2018-12-17 2019-01-21 2019-01-22 2019-03-22 2019-02-06 Quotations Envelope peces Landscape Management CO-SINCHI-82759-GO-RFQ / Component 3 - Sectoral Adquisición equipos computo, Request for Single Stage - One TF / A5789 Programs for Sustainable Post Open - National 8,392.86 7,428.23 Completed 2018-12-08 2019-01-12 2019-03-05 2019-03-13 2019-04-05 impresoras, escáner, licencias, Quotations Envelope Landscape Management tablets CO-SINCHI-82763-GO-RFQ / Component 3 - Sectoral Request for Single Stage - One Adquisición de motor fuera de TF / A5789 Programs for Sustainable Post Open - National 11,428.57 9,685.18 Completed 2018-12-01 2019-01-05 2019-02-18 2019-03-06 2019-04-18 Quotations Envelope borda Landscape Management Page 1 CO-SINCHI-82765-GO-RFQ / Component 3 - Sectoral Request for Single Stage - One Adquisición de GPS para el TF / A5789 Programs for Sustainable Post Open - National 1,392.86 1,021.43 Completed 2018-12-05 2019-01-09 2019-02-12 2019-03-10 2019-03-15 Quotations Envelope Diagnóstico de fauna Landscape Management CO-SINCHI-82767-GO-RFQ / Component 3 - Sectoral Adquisición de Cámaras Request for Single Stage - One TF / A5789 Programs for Sustainable Post Open - National 7,857.14 5,368.14 Completed 2018-12-05 2019-01-09 2019-03-11 2019-03-10 2019-04-11 trampa para el Diagnóstico de Quotations Envelope Landscape Management fauna CO-SINCHI-82772-GO-RFQ / Adquisición de balanzas y Component 3 - Sectoral dinamómetros portátiles para Request for Single Stage - One TF / A5789 Programs for Sustainable Post Open - National 1,071.43 1,320.54 Completed 2018-12-05 2019-01-19 2019-03-01 2019-02-18 2019-05-01 pesaje en campo para el Quotations Envelope Landscape Management Diagnóstico y seguimiento de fauna Component 3 - Sectoral CO-SINCHI-93144-GO-RFQ / Request for Single Stage - One TF / 18478 Programs for Sustainable Post Open - National 26,714.29 21,337.34 Completed 2019-03-09 2019-04-13 2019-05-07 2019-05-28 2019-06-30 Mobiliario para el laboratorio Quotations Envelope Landscape Management CO-SINCHI-100837-GO-RFQ / Materiales de campo para parcelas e identificación de poblaciones (Alcohol Component 3 - Sectoral Request for Single Stage - One antiséptico, Bolsas plásticas TF / A5789 Programs for Sustainable Post Open - National 1,935.48 1,717.06 Completed 2019-04-03 2019-05-08 2019-10-01 2019-07-07 2019-11-01 Quotations Envelope (resellables y de papel), Cinta Landscape Management flagging de diferentes colores, Cintas métricas, neveras de icopor, pilas, pintura, etc.) CO-SINCHI-100872-GO-RFQ Component 3 - Sectoral / Alimento para crecimiento, Request for Single Stage - One TF / A5789 Programs for Sustainable Post Open - National 2,709.68 2,042.18 Completed 2019-03-16 2019-04-20 2019-08-23 2019-06-19 2019-09-23 engorde y sostenimiento de Quotations Envelope Landscape Management Arawanas CO-SINCHI-100874-GO-RFQ / Insumos agrícolas y Component 3 - Sectoral Request for Single Stage - One elementos de transporte TF / A5789 Programs for Sustainable Post Open - National 707.35 643.73 Completed 2019-03-18 2019-04-22 2020-01-21 2019-06-21 2020-02-21 Quotations Envelope utilizados en actividad Landscape Management piscícola CO-SINCHI-100881-GO-RFQ Component 3 - Sectoral / equipamiento eléctrico o Request for Single Stage - One TF / A5789 Programs for Sustainable Post Open - National 2,741.94 2,534.19 Completed 2019-03-25 2019-04-29 2019-12-04 2019-06-28 2020-01-30 mecánico para el marcaje y/o Quotations Envelope Landscape Management monitoreo de peces CO-SINCHI-100882-GO-RFQ Component 3 - Sectoral Request for Single Stage - One / Equipos para suministrar TF / A5789 Programs for Sustainable Post Open - National 1,290.32 1,198.82 Completed 2019-04-20 2019-05-25 2019-12-31 2019-07-24 2020-01-31 Quotations Envelope agua o aireación de agua Landscape Management CO-SINCHI-100948-GO-DIR Component 3 - Sectoral / Adquisición de imágenes de TF / A5789 Programs for Sustainable Post Direct Selection Direct 13,738.02 10,420.40 Signed 2019-04-24 2019-10-30 2019-04-29 2019-12-06 2019-06-03 2020-02-25 2019-11-30 sensores remotos Landscape Management CO-SINCHI-100888-GO-RFQ / Adquisición de rack para Component 2 - Forest Request for Single Stage - One comunicación que incluya el TF / A5789 Governance, Management Post Open - National 12,903.23 11,539.92 Completed 2019-04-28 2019-06-02 2019-06-07 2019-08-01 2019-07-22 Quotations Envelope servicio de instalación y and Monitoring adecuaciones CO-SINCHI-100922-GO-RFQ / Adquisición de materiales para salida de campo tales como Alcohol antiséptico, Component 3 - Sectoral Bolsas plásticas, Cinta Request for Single Stage - One TF / 18478 Programs for Sustainable Post Open - National 5,776.13 5,149.77 Completed 2019-04-16 2019-05-21 2019-05-13 2019-07-20 2019-06-30 flagging de diferentes colores, Quotations Envelope Landscape Management Cintas métricas, Fibra en polipropileno amarilla, Flexómetros, Hipoclorito de sodio, Lonas de, Metro, etc. CO-SINCHI-100943-GO-RFQ / Adquisición de reactivos como giberellic acid, kinetina, Component 3 - Sectoral Request for Single Stage - One indoloe 3 acetic acid, butyric TF / 18478 Programs for Sustainable Post Open - National 10,968.88 5,524.06 Completed 2019-04-10 2019-05-15 2019-06-07 2019-07-14 2019-06-28 Quotations Envelope acid, ácido bórico, cloruro de Landscape Management sodio, glucosa, fosfato, glicerol, sulfato de cobre, etc. CO-SINCHI-100945-GO-RFQ / Adquisición de materiales EE El Trueno y CEA tales como Bolsas plástica para vivero, Component 3 - Sectoral Tierra, Arena, Limo, Sulfatos, Request for Single Stage - One TF / 18478 Programs for Sustainable Post Open - National 22,851.23 13,289.18 Completed 2019-04-14 2019-05-19 2019-05-24 2019-07-18 2019-06-20 Melaza, Canecas plásticas, Quotations Envelope Landscape Management Tubería pvc, Palines, Polisombra, Semillas de especies forestales, frutales y forrajeras, Alambre liso, etc. CO-SINCHI-100864-GO-RFQ / Adquisición de Implementos Component 3 - Sectoral para pesca, biometrías, Request for Single Stage - One TF / A5789 Programs for Sustainable Post Open - National 2,580.65 2,282.79 Completed 2019-04-15 2019-05-20 2019-09-20 2019-07-19 2019-10-20 manejo de peces tales como Quotations Envelope Landscape Management gramera, ictiometro, dinamómetros, básculas, etc. CO-SINCHI-100870-GO-RFQ / Adquisición de materiales para operar la Component 3 - Sectoral infraestructura piscícolas tales Request for Single Stage - One TF / A5789 Programs for Sustainable Post Open - National 1,129.03 996.27 Completed 2019-04-15 2019-05-20 2019-09-20 2019-07-19 2019-10-20 como Baldes, palas, picos, Quotations Envelope Landscape Management tuberías, machetes, limas triangulares, 'chinchorro, bolsas plásticas, etc. Page 2 CO-SINCHI-100926-GO-RFQ / Adquisición de equipos de analítica y medición tales como Medidor de radiación PAR, Higrometro, Termómetro Component 3 - Sectoral Request for Single Stage - One infrarrojo, Medidor de TF / 18478 Programs for Sustainable Post Open - National 14,828.71 19,456.56 Completed 2019-04-14 2019-05-19 2019-06-14 2019-07-18 2019-06-30 Quotations Envelope máximas y mínimas, Timer, Landscape Management Motortool, Agitador con incubadora, Cabina de bioseguridad, Micropipetas x 4, Autoclave, etc. CO-SINCHI-100946-GO-RFQ / Adquisición de equipos para talleres tales como Video Component 2 - Forest Request for Single Stage - One beam, Parlante, estaciones de TF / 18478 Governance, Management Post Open - National 35,806.35 29,645.60 Completed 2019-04-14 2019-05-19 2019-06-20 2019-07-18 2019-06-30 Quotations Envelope trabajo, teclados, mouse, and Monitoring discos duros, adaptadores de server module, etc.etc. Component 3 - Sectoral CO-SINCHI-100910-GO-DIR TF / A5789 Programs for Sustainable Post Direct Selection Direct 11,516.13 0.00 Canceled 2019-04-11 2019-04-16 2019-05-21 2019-11-17 / Combustible en Inírida Landscape Management CO-SINCHI-108709-GO-RFQ Component 3 - Sectoral Request for Single Stage - One / Adquisición de puestos de TF / 18478 Programs for Sustainable Post Open - National 19,354.84 16,360.41 Completed 2019-04-27 2019-06-01 2019-06-10 2019-06-30 2019-06-28 Quotations Envelope trabajo para la sede Bogotá Landscape Management CO-SINCHI-130061-GO-RFQ Component 3 - Sectoral Request for Single Stage - One / Cámaras fotográficas TF / A5789 Programs for Sustainable Post Open - National 4,193.55 3,729.52 Completed 2019-10-05 2019-11-02 2019-11-19 2020-01-01 2019-12-19 Quotations Envelope compactas Landscape Management CO-SINCHI-130070-GO-RFQ Component 3 - Sectoral Request for Single Stage - One / Trailer para cargar el motor TF / A5789 Programs for Sustainable Post Open - National 4,193.55 3,181.61 Completed 2019-10-14 2019-11-11 2019-12-31 2020-01-10 2020-02-29 Quotations Envelope del bote Landscape Management CO-SINCHI-130109-GO-RFQ Component 3 - Sectoral Request for Single Stage - One / Guías aves McMullan y Guías TF / A5789 Programs for Sustainable Post Open - National 754.84 661.15 Completed 2019-10-05 2019-11-19 2019-12-30 2020-01-18 2020-01-30 Quotations Envelope aves Ayerbe Landscape Management Component 3 - Sectoral CO-SINCHI-140544-GO-RFQ Request for Single Stage - One TF / A5789 Programs for Sustainable Post Open - National 4,516.13 165,923.41 Completed 2019-11-05 2019-12-03 2020-02-14 2020-02-01 2020-07-30 / Adquisición de binoculares Quotations Envelope Landscape Management CO-SINCHI-140607-GO-RFQ Component 3 - Sectoral Request for Single Stage - One / Equipos de cómputo y TF / A5789 Programs for Sustainable Post Open - National 2,898.10 1,794.33 Completed 2019-11-16 2019-12-21 2020-03-16 2020-02-19 2020-07-30 Quotations Envelope licencias Landscape Management Component 3 - Sectoral CO-SINCHI-130110-GO-RFQ Request for Single Stage - One TF / A5789 Programs for Sustainable Post Open - National 4,516.13 0.00 Canceled 2019-10-28 2019-12-23 2020-06-20 / Adquisición de Binoculares Quotations Envelope Landscape Management CO-SINCHI-100833-GO-RFQ / Materiales para vivero Component 3 - Sectoral (Bolsas plástica , Tierra, Limo, Request for Single Stage - One TF / A5789 Programs for Sustainable Post Open - National 13,774.19 11,180.07 Completed 2019-03-23 2019-04-27 2020-06-05 2019-06-26 2020-08-15 Sulfatos, Melaza, Canecas, Quotations Envelope Landscape Management Tubería, Palines, Polisombra, Semillas, Alambre, etc.) CO-SINCHI-100858-GO-RFQ Component 3 - Sectoral Request for Single Stage - One / Insumos y reactivos para TF / A5789 Programs for Sustainable Post Open - National 6,451.61 8,163.62 Completed 2020-07-25 2020-09-08 2020-09-29 2020-10-08 2021-01-31 Quotations Envelope análisis de suelos Landscape Management CO-SINCHI-170514-GO-RFQ / Implementos para pesca, para biometrías y/o manejo Component 3 - Sectoral Request for Single Stage - One de peces y Sonda(s) TF / A5789 Programs for Sustainable Post Open - National 7,071.43 5,617.52 Completed 2020-08-09 2020-09-06 2020-11-30 2020-11-05 2021-01-18 Quotations Envelope electrónicas para monitorear Landscape Management variables fisicoquímicas del agua (dos lotes) CO-SINCHI-170515-GO-RFQ Component 3 - Sectoral / 'Alimento para crecimiento , Request for Single Stage - One TF / A5789 Programs for Sustainable Post Open - National 3,571.43 2,702.11 Completed 2020-08-22 2020-09-26 2021-01-14 2020-11-25 2021-01-29 engorde y sostenimiento de Quotations Envelope Landscape Management Arawanas CO-SINCHI-170517-GO-RFQ Component 3 - Sectoral Request for Single Stage - One / 'Computador, equipos de TF / A5789 Programs for Sustainable Post Open - National 3,571.43 1,967.83 Completed 2021-02-13 2021-03-20 2020-11-26 2021-05-19 2021-01-23 Quotations Envelope impresión y/o tabletas Landscape Management CO-SINCHI-170516-GO-RFQ Component 3 - Sectoral / Insumos agrícolas y otros Request for Single Stage - One TF / A5789 Programs for Sustainable Post Open - National 6,875.39 5,373.28 Completed 2020-12-19 2021-01-23 2020-09-24 2021-03-24 2020-10-15 elementos utilizados en Quotations Envelope Landscape Management actividades piscicolas CO-SINCHI-229286-GO-RFQ / El contratista se obliga con el Instituto Amazónico de Component 3 - Sectoral Pending Investigaciones Científicas Request for Single Stage - One TF / A5789 Programs for Sustainable Post Open - National 747.56 0.00 Implementati 2021-07-06 2021-08-06 2021-09-05 “Sinchi” a realizar el Quotations Envelope Landscape Management on suministro de materiales de papelería para el componente 3.3.1.1 NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CO-SINCHI-100884-NC-RFQ Component 3 - Sectoral / Servicio para establecer Request for Single Stage - One TF / A5789 Programs for Sustainable Post Open - National 3,225.81 2,633.31 Completed 2019-04-13 2019-06-08 2019-10-28 2019-12-05 2019-12-28 estanques piscícolas para Quotations Envelope Landscape Management manejo de arawana plateada CO-SINCHI-200792-NC-RFQ Component 3 - Sectoral Pending / Registro y edición de Request for Single Stage - One TF / A5789 Programs for Sustainable Post Open - National 3,333.33 0.00 Implementati 2021-03-13 2021-05-08 2021-11-04 fotografías de peces en río Quotations Envelope Landscape Management on Putumayo y río Caquetá Page 3 CO-SINCHI-107576-NC-RFQ Component 3 - Sectoral Request for Single Stage - One / Impresión de guía de aves y TF / A5789 Programs for Sustainable Post Open - National 20,645.16 0.00 Canceled 2021-04-10 2021-06-05 2021-12-02 Quotations Envelope libro (fauna) Landscape Management CO-SINCHI-234407-NC-RFQ / Prestar sus servicios de impresión para los materiales de apoyo necesario para el Component 3 - Sectoral Pending desarrollo de talleres del Request for Single Stage - One TF / A5789 Programs for Sustainable Post Open - National 1,364.95 0.00 Implementati 2021-07-17 2021-08-22 2021-12-20 componente 3.3.1.1. Apoyo al Quotations Envelope Landscape Management on diagnóstico y monitoreo de la fauna terrestre de consumo, comercialización o con conflictos de uso. CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CO-SINCHI-20472-CS-LCS / Consultoría para la Component 3 - Sectoral Implementación y desarrollo Least Cost TF / 18478 Programs for Sustainable Post Open - National 134,761.00 0.00 Canceled 2017-07-04 2017-07-25 2017-11-02 2017-12-28 2018-01-27 2018-02-06 2018-02-21 2018-08-20 de estrategias de ventas y Selection Landscape Management Mercadeo de portafolio de productos del bosque. INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CO-SINCHI-20500-CS-INDV Component 3 - Sectoral Individual / consultor para apoyo a la TF / 18478 Programs for Sustainable Post Consultant Limited 20,448.00 0.00 Canceled 2017-02-22 2017-02-27 2017-03-20 2017-04-24 2017-10-21 gestion y formulacion del Landscape Management Selection PDRIET Guaviare CO-SINCHI-20480-CS-INDV Component 3 - Sectoral Individual / consultor de apoyo para TF / 18478 Programs for Sustainable Post Consultant Limited 9,737.00 0.00 Canceled 2017-07-19 2017-07-24 2017-08-14 2017-09-18 2018-03-17 alcaldias en formulacion PGAT Landscape Management Selection 1 CO-SINCHI-20344-CS-INDV Component 3 - Sectoral Individual / consultor de apoyo para TF / 18478 Programs for Sustainable Post Consultant Limited 9,737.00 0.00 Canceled 2017-07-17 2017-07-22 2017-08-12 2017-09-16 2018-03-15 alcaldias en formulacion PGAT Landscape Management Selection 2 CO-SINCHI-20501-CS-INDV Component 3 - Sectoral Individual / consultor de apoyo para TF / 18478 Programs for Sustainable Post Consultant Limited 9,737.00 0.00 Canceled 2017-02-22 2017-02-27 2017-03-20 2017-04-24 2017-10-21 alcaldias en formulacion PGAT Landscape Management Selection 3 CO-SINCHI-20497-CS-INDV / Consultoría para la Component 3 - Sectoral Individual construcción de modelo de TF / 18478 Programs for Sustainable Post Consultant Limited 21,908.00 0.00 Canceled 2017-06-22 2017-06-27 2017-07-18 2017-08-22 2018-02-18 bosques de paz en municipios Landscape Management Selection priorizados de Amazonia CO-SINCHI-20498-CS-INDV / Consultoría para la consolidación oportunidades de uso de productos no Component 3 - Sectoral Individual maderables del bosque e TF / 18478 Programs for Sustainable Post Consultant Limited 43,817.00 0.00 Canceled 2017-06-22 2017-06-27 2017-07-18 2017-08-22 2018-02-18 identificación barreras y Landscape Management Selection vacíos normativos para generar una dinámica formal y legal CO-SINCHI-20447-CS-INDV / Consultoría para realizar el Component 3 - Sectoral Individual enlace de modelos de negocio TF / 18478 Programs for Sustainable Post Consultant Limited 58,423.00 0.00 Canceled 2017-06-22 2017-06-27 2017-07-18 2017-08-22 2018-02-18 forestal a fondos de inversión Landscape Management Selection y opciones de fomento administradas por MADR CO-SINCHI-20499-CS-INDV / Consultoría para el desarrollo acuerdo MADR - Apoyo formulación Planes de Component 3 - Sectoral Individual Asistencia Técnica - TF / 18478 Programs for Sustainable Post Consultant Limited 14,606.00 0.00 Canceled 2017-06-22 2017-06-27 2017-07-18 2017-08-22 2018-02-18 Componente forestal, Landscape Management Selection municipios SVC, CCH, Solano, Retorno, Calamar y SJG, para acceso a incentivo MADR CO-SINCHI-20496-CS-INDV / Consultoría para la valoración económica de Component 3 - Sectoral Individual todas las opciones de uso del TF / 18478 Programs for Sustainable Post Consultant Limited 37,975.00 0.00 Canceled 2017-06-22 2017-06-27 2017-07-18 2017-08-22 2018-02-18 suelo ya identificadas y Landscape Management Selection análisis de sensibilidad en Guaviare y Caquetá) CO-SINCHI-20468-CS-INDV Component 3 - Sectoral Individual / Consultor estadístico para TF / 18478 Programs for Sustainable Post Consultant Limited 23,369.00 0.00 Canceled 2017-06-22 2017-06-27 2017-07-18 2017-08-22 2018-02-18 análisis del paisaje Landscape Management Selection CO-SINCHI-20454-CS-INDV / Consultor Para gestion de PGAT en el marco del Component 3 - Sectoral Individual convenio Sinchi- TF / 18478 Programs for Sustainable Post Consultant Open 36,832.00 0.00 Canceled 2017-06-22 2017-08-10 2017-08-31 2017-10-05 2018-04-03 Gobernaciones y ruta de Landscape Management Selection trabajo con Direccion de Innovacion del MADR plataforma 360 Page 4 CO-SINCHI-20453-CS-INDV / Consultoría para el desarrollo acuerdo MADR - Component 3 - Sectoral Individual Apoyo formulación Planes de TF / 18478 Programs for Sustainable Post Consultant Limited 14,606.00 0.00 Canceled 2017-06-22 2017-06-27 2017-07-18 2017-08-22 2018-02-18 Asistencia Técnica - Landscape Management Selection Componente forestal, municipio CCH CO-SINCHI-20448-CS-INDV / Consultoría para el desarrollo acuerdo MADR - Component 3 - Sectoral Individual Apoyo formulación Planes de TF / 18478 Programs for Sustainable Post Consultant Limited 14,606.00 0.00 Canceled 2017-06-22 2017-06-27 2017-07-18 2017-08-22 2018-02-18 Asistencia Técnica - Landscape Management Selection Componente forestal, municipio Solano CO-SINCHI-20450-CS-INDV / Consultoría para el desarrollo acuerdo MADR - Component 3 - Sectoral Individual Apoyo formulación Planes de TF / 18478 Programs for Sustainable Post Consultant Limited 14,606.00 0.00 Canceled 2017-06-22 2017-06-27 2017-07-18 2017-08-22 2018-02-18 Asistencia Técnica - Landscape Management Selection Componente forestal, municipio Retorno, para acceso a incentivo MADR CO-SINCHI-20458-CS-INDV / Consultoría para el desarrollo acuerdo MADR - Component 3 - Sectoral Individual Apoyo formulación Planes de TF / 18478 Programs for Sustainable Post Consultant Limited 14,606.00 0.00 Canceled 2017-06-22 2017-06-27 2017-07-18 2017-08-22 2018-02-18 Asistencia Técnica - Landscape Management Selection Componente forestal, municipio Calamar para acceso a incentivo MADR CO-SINCHI-20457-CS-INDV / Consultoría para el desarrollo acuerdo MADR - Component 3 - Sectoral Individual Apoyo formulación Planes de TF / 18478 Programs for Sustainable Post Consultant Limited 14,606.00 0.00 Canceled 2017-06-22 2017-06-27 2017-07-18 2017-08-22 2018-02-18 Asistencia Técnica - Landscape Management Selection Componente forestal, municipio SJG, para acceso a incentivo MADR CO-SINCHI-20574-CS-INDV Component 3 - Sectoral Individual / Asesor para le gestion TF / 18478 Programs for Sustainable Post Consultant Direct 42,587.00 46,883.40 Completed 2017-05-15 2018-02-28 2017-05-25 2017-06-15 2018-04-02 2017-07-20 2018-04-02 2018-01-16 2019-06-30 interinstitucional Landscape Management Selection CO-SINCHI-51790-CS-INDV / Consultoría para apoyar el Component 3 - Sectoral Individual proceso de acuerdo sectorial TF / 18478 Programs for Sustainable Post Consultant Direct 35,357.15 34,458.93 Completed 2018-03-19 2018-03-13 2018-03-29 2018-04-19 2018-03-23 2018-05-24 2018-04-11 2018-11-20 2019-01-11 para la gestión y articulación Landscape Management Selection proyectos GEF - MADR - Pilar 3 de Visión Amazonia. CO-SINCHI-51791-CS-INDV / Consultoría para la implementación del programa Component 3 - Sectoral Individual Bosques de Paz desde la TF / 18478 Programs for Sustainable Post Consultant Limited 19,286.00 14,617.80 Completed 2018-03-28 2018-04-03 2018-04-02 2018-04-03 2018-04-23 2018-05-23 2018-05-28 2018-05-23 2018-11-24 2019-06-23 dimensión social y facilitar su Landscape Management Selection articulación en los territorios de la región Amazonía CO-SINCHI-62154-CS-INDV / Consultor para la construcción de los planes generales de asistencia Component 3 - Sectoral Individual técnica rural PGAT con TF / 18478 Programs for Sustainable Post Consultant Direct 11,607.14 11,111.10 Completed 2018-05-16 2018-05-22 2018-05-23 2018-05-28 2018-05-23 2018-06-04 2018-05-25 2018-11-05 2018-10-30 enfoque agroambiental con Landscape Management Selection base en la plataforma productores 360 Asistencia Técnica CO-SINCHI-51789-CS-INDV / Consultoria para el Component 3 - Sectoral Individual desarrollo e Implementación TF / 18478 Programs for Sustainable Post Consultant Limited 22,500.00 0.00 Canceled 2018-07-09 2018-07-14 2018-08-04 2018-09-08 2019-03-07 de una estrategia de Landscape Management Selection sostenbilidad del enfoque socioempresarial CO-SINCHI-100890-CS-INDV Component 3 - Sectoral Individual / Gestor Predial para piloto TF / 18478 Programs for Sustainable Post Consultant Limited 12,903.23 11,925.60 Completed 2019-03-04 2019-03-07 2019-03-09 2019-03-29 2019-03-19 2019-05-13 2019-03-29 2019-05-13 2019-06-27 2019-06-30 formalización tierras y Landscape Management Selection derechos de uso - Guaviare CO-SINCHI-100893-CS-INDV Component 3 - Sectoral Individual / Gestor Predial para piloto TF / 18478 Programs for Sustainable Post Consultant Limited 12,903.23 11,703.60 Completed 2019-03-04 2019-03-07 2019-03-09 2019-03-28 2019-03-19 2019-05-07 2019-03-29 2019-05-13 2019-06-27 2019-06-30 formalización tierras y Landscape Management Selection derechos de uso - Caquetá CO-SINCHI-100902-CS-INDV Component 3 - Sectoral Individual / Crear el contenido de TF / 18478 Programs for Sustainable Post Consultant Limited 13,322.58 689,252.40 Completed 2019-03-04 2019-03-12 2019-03-09 2019-03-22 2019-03-19 2019-03-27 2019-03-29 2019-03-29 2019-06-27 2019-06-30 comunicación para la Landscape Management Selection culminación del GEF 5 CO-SINCHI-100904-CS-INDV / Consultoría para la valoración económica de Component 3 - Sectoral Individual todas las opciones de uso del TF / 18478 Programs for Sustainable Post Consultant Limited 9,761.68 0.00 Canceled 2019-03-04 2019-03-09 2019-03-19 2019-03-29 2019-06-27 suelo ya identificadas y Landscape Management Selection análisis de sensibilidad en Guaviare y Caquetá) CO-SINCHI-100908-CS-INDV Component 3 - Sectoral Individual / Consultor estadístico para TF / 18478 Programs for Sustainable Post Consultant Limited 10,446.77 9,424.36 Completed 2019-03-04 2019-03-22 2019-03-09 2019-04-03 2019-03-19 2019-05-02 2019-03-29 2019-05-03 2019-06-27 2019-06-30 análisis del paisaje Landscape Management Selection CO-SINCHI-100942-CS-INDV Component 3 - Sectoral Individual / Diseño de publicidad e TF / 18478 Programs for Sustainable Post Consultant Limited 3,548.39 1,895.99 Completed 2019-03-04 2019-03-07 2019-03-09 2019-04-03 2019-03-30 2019-06-03 2019-05-04 2019-06-07 2019-10-31 2019-06-30 identidad de marcas Landscape Management Selection CO-SINCHI-107578-CS-INDV / Coordinador metodológico y Component 2 - Forest Individual temático para ecología del TF / 18478 Governance, Management Post Consultant Limited 7,741.94 6,984.24 Completed 2019-04-01 2019-03-13 2019-04-06 2019-04-01 2019-04-16 2019-05-13 2019-04-26 2019-05-13 2019-07-25 2019-06-30 paisaje, planificación and Monitoring Selection territorial y modelamiento ecológico. Page 5 CO-SINCHI-107579-CS-INDV / Profesional para desarrollar el componente biofísico para Component 2 - Forest Individual el modelamiento ecológico, TF / 18478 Governance, Management Post Consultant Limited 7,741.94 6,984.24 Completed 2019-04-01 2019-03-19 2019-04-06 2019-04-02 2019-04-16 2019-05-03 2019-04-26 2019-05-03 2019-07-25 2019-06-30 ecología del paisaje, manejo, and Monitoring Selection conservación y planificación territorial. CO-SINCHI-107580-CS-INDV / 'Profesional para desarrollar el componente SIG para el Component 2 - Forest Individual modelamiento ecológico, TF / 18478 Governance, Management Post Consultant Limited 6,774.19 6,104.49 Completed 2019-04-01 2019-03-19 2019-04-06 2019-03-27 2019-04-16 2019-05-24 2019-04-26 2019-05-24 2019-07-25 2019-06-30 ecología del paisaje, manejo, and Monitoring Selection conservación y planificación territorial. CO-SINCHI-107581-CS-INDV Component 3 - Sectoral Individual / Consultoría para el TF / 18478 Programs for Sustainable Post Consultant Limited 16,309.50 10,563.87 Completed 2019-04-01 2019-03-28 2019-04-06 2019-04-05 2019-04-16 2019-05-16 2019-04-26 2019-05-24 2019-07-25 2019-06-30 diagnóstico y desarrollo de la Landscape Management Selection cadena productiva forestal CO-SINCHI-130076-CS-INDV Component 3 - Sectoral Individual / Asesor para la gestión TF / A5789 Programs for Sustainable Post Consultant Direct 19,306.45 18,135.15 Completed 2019-09-30 2019-12-03 2019-10-10 2019-11-17 2019-10-31 2019-11-26 2019-12-05 2019-12-20 2020-06-02 2020-10-31 institucional Landscape Management Selection Component 3 - Sectoral Individual CO-SINCHI-130075-CS-INDV TF / A5789 Programs for Sustainable Post Consultant Direct 32,903.23 29,844.18 Completed 2019-09-30 2019-10-17 2019-10-10 2019-10-31 2019-10-31 2019-11-15 2019-12-05 2019-11-15 2020-11-29 2020-11-15 / Comunicador social Landscape Management Selection CO-SINCHI-135551-CS-INDV Component 3 - Sectoral Individual / Consultor para valoración TF / A5789 Programs for Sustainable Post Consultant Limited 9,677.42 7,340.40 Completed 2019-10-15 2019-11-07 2019-10-20 2020-02-25 2019-11-10 2020-03-20 2019-12-15 2020-03-30 2020-06-12 2020-09-15 económica y pago por Landscape Management Selection servicios ambientales CO-SINCHI-170511-CS-INDV Component 3 - Sectoral Individual / Diagramación del libro Sitio TF / A5789 Programs for Sustainable Post Consultant Limited 2,666.67 2,109.12 Completed 2020-05-10 2020-06-10 2020-05-15 2020-07-01 2020-06-05 2020-08-06 2020-07-10 2020-08-18 2021-01-06 2021-02-26 Ramsar Landscape Management Selection CO-SINCHI-130111-CS-INDV Component 3 - Sectoral Individual / Profesional para elaborar TF / A5789 Programs for Sustainable Post Consultant Limited 6,451.61 0.00 Canceled 2020-06-21 2020-06-26 2020-07-17 2020-08-21 2021-02-17 tipografía especial lenguas Landscape Management Selection indígenas CO-SINCHI-170512-CS-INDV Component 3 - Sectoral Individual / 'Profesional para apoyo a Under TF / A5789 Programs for Sustainable Post Consultant Limited 2,666.67 0.00 2021-02-01 2021-06-15 2021-02-06 2021-02-27 2021-04-03 2021-09-30 Coordinación para el Implementation Landscape Management Selection componente piscicola CO-SINCHI-200728-CS-INDV Component 3 - Sectoral Individual / Diagramación y corrección TF / A5789 Programs for Sustainable Post Consultant Limited 4,838.71 0.00 Canceled 2020-11-26 2020-12-17 2020-12-01 2020-12-22 2021-01-26 2021-07-25 de estilo Landscape Management Selection CO-SINCHI-211257-CS-INDV / Realizar la diagramación y corrección de estilo de dos Component 3 - Sectoral Individual libros: Caso de Estudio El TF / A5789 Programs for Sustainable Post Consultant Limited 4,477.61 4,118.55 Signed 2021-02-15 2021-02-22 2021-02-20 2021-02-23 2021-03-02 2021-04-14 2021-03-17 2021-04-14 2021-05-16 Capricho y Evaluación de la Landscape Management Selection cadena productiva forestal (productos maderables y no maderables) CO-SINCHI-210047-CS-INDV / Se obliga para con el Component 3 - Sectoral Individual Instituto Sinchi a gestionar los TF / A5789 Programs for Sustainable Post Consultant Direct 14,328.36 0.00 Canceled 2021-02-15 2021-03-25 2021-02-25 2021-03-02 2021-03-12 2021-08-09 componentes necesarios para Landscape Management Selection una comunicación efectiva y asertiva del proyecto CO-SINCHI-210052-CS-INDV Component 3 - Sectoral Individual / Profesional para generación TF / A5789 Programs for Sustainable Post Consultant Limited 2,842.39 0.00 Canceled 2021-03-15 2021-03-20 2021-04-10 2021-05-15 2021-11-11 de información biológica y Landscape Management Selection pesquera de especies CO-SINCHI-230147-CS-INDV / desarrollar un Plan de Comunicaciones del componente 3.3 Desarrollo de planes para promover Component 3 - Sectoral Individual Pending prácticas sostenibles de TF / A5789 Programs for Sustainable Post Consultant Limited 7,992.54 0.00 2021-06-14 2021-06-19 2021-07-10 2021-07-20 2021-10-18 Implementation gestión Landscape Management Selection del uso de la tierra y de los recursos naturales que contribuyan a reducir la presión sobre los bosques CO-SINCHI-100860-CS-INDV / El contratista se obliga con el Instituto Amazónico de Investigaciones Científicas Component 3 - Sectoral Individual “Sinchi” a prestar sus servicios Pending TF / A5789 Programs for Sustainable Post Consultant Limited 9,288.18 0.00 2021-07-01 2021-07-06 2021-07-27 2021-08-20 2021-10-19 profesionales para realizar la Implementation Landscape Management Selection diagramación y corrección de estilo de la Guía de aves y libro de los resultados del componente 3.3.1.1. Page 6 PROCUREMENT PLAN (Textual Part) Project information: St Lucia Human Capital Resilience Project 6556- LC Project Implementation agencies: Ministry of Education, Innovation and Gender Relations and Ministry of Equity, Social Justice, Local Government and Empowerment Date of the Procurement Plan: 1 February 2021 Period covered by this Procurement Plan: 28 July 2020 to 27 January 2022 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). “Not Applicable” Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. Other Relevant Procurement Information. PROCUREMENT St. Lucia : Saint Lucia Human Capital Resilience Project PLAN General Information Country: St. Lucia Bank’s Approval Date of the Original Procurement Plan: 2021-02-10 2021-05-27 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P170445 GPN Date: 2021-04-14 Project Name: Saint Lucia Human Capital Resilience Project Loan / Credit No: IDA / 65560 M Executing Agency(ies): INISTRY OF EDUCATION, INNOVATION, GENDER RELATIONS AND SUSTAINABLE DEVELOPMENT WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 01/G/HCRP/04/2021 / Technical Assistance, Under Supply of computer devices Capacity Building, TVET Request for Single Stage - One IDA / 65560 Post Open - National 14,000.00 0.00 Implementati 2021-04-18 2021-05-03 2021-05-18 for the Project Implementation Equipment and Furniture, and Quotations Envelope on Unit (PIU) Project Management 02/G/HCRP/00/2021 / Strengthening Technical and Pending Request for Single Stage - One Supply of office equipment for IDA / 65560 Vocational Education and Post Open - National 6,000.00 0.00 Implementati 2021-02-17 2021-04-14 2021-10-11 Quotations Envelope the TVET Unit Training (TVET) on Technical Assistance, 03/G/HCRP/ 05/2021 / Pending Capacity Building, TVET Request for Single Stage - One Supply of office furniture for IDA / 65560 Post Limited 15,000.00 0.00 Implementati 2021-06-02 2021-07-28 2021-09-27 Equipment and Furniture, and Quotations Envelope the PIU office on Project Management NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 00/CS/HCRP/00/2020 / Year Strengthening Technical and Consultant Pending 1 Labor Market Needs IDA / 65560 Vocational Education and Post Qualification Limited 120,000.00 0.00 2021-02-11 2021-02-25 2021-03-27 2021-05-01 2021-10-28 Implementation Assessment Training (TVET) Selection 016/CS/HCRP/00/2021 / Consulting services to develop Technical Assistance, a communication strategy and Consultant Capacity Building, TVET Under implementation plan for the IDA / 65560 Post Qualification Open - National 60,000.00 0.00 2021-03-05 2021-06-10 2021-03-26 2021-05-09 2021-06-08 2021-07-13 2022-01-09 Equipment and Furniture, and Implementation MoEQ and support for the Selection Project Management implementation of the strategy 021/CS/HCRP/00/2021 / Consultancy Services - IT Technical Assistance, System implementation: Capacity Building, TVET Quality And Cost- Pending Provide technical assistance to IDA / 65560 Post Open - International 1,500,000.00 0.00 2021-03-26 2021-04-16 2021-05-30 2021-06-27 2021-07-27 2021-08-31 2021-10-05 2022-10-05 Equipment and Furniture, and Based Selection Implementation the MoEQ and GITS and to Project Management develop an integrated social information system 020/CS/HCRP/00/2021 / Living Condition Survey: Technical assistance to the Consultant CSO to support review of the Strengthening the Social Pending IDA / 65560 Post Qualification Open - National 100,000.00 0.00 2021-04-02 2021-04-23 2021-06-06 2021-07-06 2021-08-10 2022-02-06 instrument and carry out Protection System Implementation Selection implementation analysis of the round of survey which is planned for 2022 INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Technical Assistance, 002/CSIC/HCRP/00/2020 / Individual Capacity Building, TVET Under Finance Officer for the Project IDA / 65560 Post Consultant Open 39,900.00 0.00 2021-02-09 2020-06-01 2021-03-30 2021-04-20 2021-05-25 2021-11-21 Equipment and Furniture, and Implementation Implementation Unit Selection Project Management Technical Assistance, 004/CSIC/HCRP/00/2020 / Individual Capacity Building, TVET Under Technical Coordinator for the IDA / 65560 Post Consultant Open 43,950.00 0.00 2021-03-01 2021-03-29 2021-04-19 2021-05-10 2021-06-14 2021-12-11 Equipment and Furniture, and Implementation Project Implementation Unit Selection Project Management Technical Assistance, 005/CSIC/HCRP/00/2020 / Individual Capacity Building, TVET Pending Monitoring and Evaluation IDA / 65560 Post Consultant Open 39,000.00 0.00 2021-02-16 2021-04-06 2021-04-27 2021-06-01 2021-11-28 Equipment and Furniture, and Implementation Officer for the PIU Selection Project Management 006/CSIC/HCRP/00/2020 / Technical Assistance, Individual Social and Environmental Capacity Building, TVET Pending IDA / 65560 Post Consultant Open 35,100.00 0.00 2021-03-01 2021-04-19 2021-05-10 2021-06-14 2021-12-11 Specialist for the Project Equipment and Furniture, and Implementation Selection Implementation Unit Project Management Page 1 Technical Assistance, 008/CSIC/HCRP/00/2020 / Individual Capacity Building, TVET Pending Accounts Clerk for the Project IDA / 65560 Post Consultant Open 19,772.00 0.00 2021-02-10 2021-03-31 2021-04-21 2021-05-26 2021-11-22 Equipment and Furniture, and Implementation Implementation Unit Selection Project Management 009/CSIC/HCRP/02/2021 / Technical Assistance, Individual Consultancy services to review Capacity Building, TVET Under IDA / 65560 Post Consultant Open 37,037.00 0.00 2021-02-10 2021-02-11 2021-03-31 2021-04-21 2021-05-26 2021-11-22 the National Social Protection Equipment and Furniture, and Implementation Selection Policy for the MoEQ Project Management 010/CSIC/HCRP/02/2021 / Technical Assistance, Consultancy services to Individual Capacity Building, TVET Under provide technical assistance IDA / 65560 Post Consultant Limited 35,000.00 0.00 2021-02-12 2021-06-03 2021-02-17 2021-03-10 2021-04-14 2021-10-11 Equipment and Furniture, and Implementation to MoEQ and draft the Selection Project Management Graduation\Exit Strategy 011/CSIC/HCRP/02/2021 / Consultancy services to develop Programme Technical Assistance, Individual Operations Manual for PAP Capacity Building, TVET Pending IDA / 65560 Post Consultant Limited 50,000.00 0.00 2021-02-11 2021-02-16 2021-03-09 2021-04-13 2021-10-10 and KSL (to include Referral Equipment and Furniture, and Implementation Selection Protocols, Feedback Project Management Mechanisms and Appeals and Grievance Mechanism) Technical Assistance, 003/CSIC/HCRP/00/2020 / Individual Capacity Building, TVET Pending Procurement Officer for the IDA / 65560 Post Consultant Open 35,100.00 0.00 2021-02-02 2021-03-23 2021-04-13 2021-05-18 2021-11-14 Equipment and Furniture, and Implementation Project Implementation Unit Selection Project Management Technical Assistance, 001/CSIC/HCRP/00/2020 / Individual Capacity Building, TVET Pending Project Manager for the IDA / 65560 Post Consultant Open 79,950.00 0.00 2021-05-09 2021-06-27 2021-07-18 2021-08-22 2022-02-18 Equipment and Furniture, and Implementation Project Implementation Unit Selection Project Management 007/CSIC/HCRP/00/2021 / Technical Assistance, Individual Administrative Assistant for Capacity Building, TVET Pending IDA / 65560 Post Consultant Open 26,489.00 0.00 2021-02-10 2021-03-31 2021-04-21 2021-05-26 2021-11-22 the Project Implementation Equipment and Furniture, and Implementation Selection Unit Project Management 013/CSIC/HCRP/00/2021 / Technical Assistance, Procuring the services of an Individual Capacity Building, TVET Under international procurement IDA / 65560 Post Consultant Limited 25,000.00 0.00 2021-05-21 2021-05-04 2021-05-26 2021-06-10 2021-07-09 2022-03-08 Equipment and Furniture, and Implementation specialist to provide technical Selection Project Management assistance to the PIU 014/CSIC/HCRP/00/2021 / Technical Assistance, Individual Engagement of an Auditor to Capacity Building, TVET Under IDA / 65560 Post Consultant Open 10,000.00 0.00 2021-05-28 2021-05-26 2021-06-28 2021-07-08 2021-07-25 2021-09-27 conduct an Annual Audit of Equipment and Furniture, and Implementation Selection the finances of the HCRP Project Management 017/CSIC/HCRP/00/2021 / Consultancy to Technical Assistance, Individual develop\implement a Capacity Building, TVET Under IDA / 65560 Post Consultant Open 20,000.00 0.00 2021-05-30 2021-05-26 2021-07-18 2021-08-08 2021-09-12 2022-03-11 National Apprenticeship Equipment and Furniture, and Implementation Selection Programme for TVET in St Project Management Lucia Technical Assistance, 000/CSIC072021 / Individual Capacity Building, TVET Pending Consultancy for the Social IDA / 65560 Post Consultant Open 40,000.00 0.00 2021-06-30 2021-08-18 2021-09-08 2021-10-13 2022-04-11 Equipment and Furniture, and Implementation Information System (ICT) Selection Project Management Page 2 Procurement Plan For Integrated Development for Source Sustainability and Climate Resilient Rain-fed Agriculture Project A World Bank Financed Project Project ID: P165129 [Procurement Plan Period: First 18 months of the Project] Covering the Period: January 2020 to June 2021 Submitted By Project Management Unit [PMU] Himachal Pradesh Forest Department Government of Himachal Pradesh India 2 3 PROCUREMENT PLAN Country: INDIA Borrower: Government of India on behalf of Government of Himachal Pradesh Project Name: Integrated Development for Source Sustainability and Climate Resilient Rain-fed Agriculture Project Project Implementation Agency: Project Management Unit [PMU], Himachal Pradesh Forestry Department [HPFD], Government of Himachal Pradesh Date of General Procurement Notice: December 18, 2019 Bank’s Approval Date of the Procurement Plan: Original … Revision 1: Revision 2: Date of the Procurement Plan: December 2019 Period covered by this Procurement Plan: January 2020 to June 2021 Applicable Procurement Rules. The Procurement of goods, works, consulting and non-consulting services to be financed by the Loan will be carried out in accordance with the World Bank’s Procurement Regulations for IPF Borrowers [dated July 2016; revised November 2017 and August 2018], and the provisions of the Loan Agreement. If there is conflict between government decrees, rules, and regulations and the Bank Procurement Regulations, then Bank’s Procurement Regulations shall prevail. The project will be subject to World Bank Guidelines on Preventing and Combating Fraud and Corruption in Projects Financed by IBRD Loans and IDA Credits and Grants [“Anti-Corruption Guidelines”], dated October 15, 2006 and revised in January 2011 and as of July 1, 2016. The project will use the online tool Systematic Tracking of Exchanges in Procurement [STEP] to prepare, clear, and update its procurement plan, for monitoring procurement activities and for communication between the Borrower and the Bank. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under Paragraph 4.4 of the Procurement Regulations are set forth in STEP. Unless otherwise agreed with the World Bank, the World Bank’s Standard Procurement Documents [SPD], Requests for Proposals, and Forms of Consultant Contract will be used. Procurement under national procedures will be carried out based on National Procurement Procedures [NPP] conditions agreed with the Government of India. Procurement estimated at Indian Rupees [INR] 5 Lakhs and above will be submitted through government eProcurement systems provided by NIC 4 www.hptender.gov.in which have been assessed and deemed acceptable by the Bank against Multilateral Development Bank [MDB] requirements. Financial Management [FM] Manual. The FM Manual prepared for the project shall have a separate chapter on Procurement which will provide clear guidance on applicable procurement arrangement, procedures and thresholds, and shall be made available on the project website. Community Operations Manual [COM]. The COM prepared for the project will have clear directives for the community [GPs/individual beneficiaries] with regard to eligible procurement expenditures and agreed procurement arrangements, procedures and thresholds, and shall be made available on the project website. This will serve as a guidebook for procurement, with a view to providing operating instructions and bring in greater transparency and predictability in procurement procedures under the Project. Procurement Arrangements and Profile. Procurement under the Project will be carried out at the central level by the Project Management Unit [PMU] headed by the Chief Project Director [CPD] established for the Project, at the District level by the District Project Officers assisted by the Accounts Assistant at the District Level in each of the 10 District Project Offices [DPOs] located in the Districts covered under the Project [Shimla, Solan, Sirmour, Bilaspur, Hamirpur, Mandi, Kullu, Chamba, Kangra and Una], and by beneficiary GPs [supported by DPOs] at the GP level, in accordance with their approved Gram Panchayat Resource Management Plans [GP-RMP]/MG/OMIF. Officials of the PMU have prior experience of implementing a World Bank financed project and have also undergone training in STEP. GPs will need to be capacitated and provided basic procurement training on applicable procurement procedures and procurement documentation requirements outlined in COM, before initiating their procurements. To meet the readiness requirements of the Department of Economic Affairs [DEA] of the Government of India, the Project has already initiated and awarded contract for critical consultancy package for Environmental and Social Assessment to be retroactively financed by the Bank. The project envisages procurement of low-risk, low-value goods, works and services as below: a. Goods and Non-Consulting Services to be procured under the project are likely to include the following. At State/PMU level, purchase of IT Equipment such laptops, computers, printer, etc., procurement of printing services for IEC, office vehicles, office furniture, etc. are envisaged. At District and GP level, procurement activities will include procurement of Barbed Wire, U/Staple, Tools, Gunny Bags, Vermicompost/ Farm yard Manure, Sand, Seeds, Wooden posts/ poles, Seedlings, Grass tufts, Sign boards/hand prints, seed testing instrument, Seed, Fertilizer, Pesticide, Livestock - Small and Large Ruminants, Agricultural Tools and Implements, equipment, Farm machinery, e.g., power tiller, chaff cutters, pipes, tarpaulins, Medicines, supplements, sprinklers, seedlings, etc. b. Procurement of Minor Civil Works is likely to include the following. At State/ PMU level, procurement of minor civil works will include extension, refurbishment and repair of office buildings, etc. At District and GP level, procurement activities will include procurement of works for construction of Water storage tanks, water channels, vermicompost pits, livestock Mangers, foot bridges, water lifting pumps, GI pipes, accessories, installation of ropeways, Ponds, Check Dams, Subsurface Dykes, Sump Wells etc. and labor contracts for preparing land 5 for nursery, preparing nursery beds, water tank, works of filling gunny bags, sowing of seeds, preparing temporary nursery sheds, watering, hoeing, weeding, , fencing, bush cutting, pit digging, planting seedlings, preparing contour trenches, planting grass tufts, drainage line treatment works, fire management works, allowances and incentives for fire management, Spring development, eradication of exotic weed- lantana, etc. It may be noted that civil works at GP level are demand driven. There are no major civil works contracts envisaged in the project. c. Consultancy Services to be procured under the project are likely to include services for developing a web-based portal for Integrated Financial Management Information System [IFMS], Water Monitoring and Modelling, Value Chain Scoping Studies, Technical Support Study for addressing the needs of Transhumant, M and E, MIS, Baseline Survey, External and Internal Audit, Third Party Verification agent to verify achievement of Disbursement Related Results [DLR]s, need based assessments and studies, individual experts, etc. No consultancy services contracts envisaged at the District/Sub-district levels. The project includes several features of a decentralized, demand-driven project, and activities to be taken up at the community level by selected beneficiaries shall be as per the GP-RMP approved by the PMU of the HP Forestry Department/MG/OMIF. The threshold of procurement activities at community level is expected not to exceed Request for Quotation [RFQ] threshold. Community-level procurement shall follow Community-Driven Development [CDD] arrangements as per the Bank’s Procurement Regulations and as outlined in the Community Operations Manual [COM] currently under preparation. Given other on-going government programs, the activities to be funded following COM shall be identified upfront to avoid double-dipping and will require very close monitoring and oversight. Project Procurement Strategy for Development [PPSD] and Procurement Plan. According to the requirement of the Regulations, a Project Procurement Strategy for Development [PPSD] has been developed, based on which the Procurement Plan for the first 18 months has been prepared. The PPSD describes how procurement in this project will support the Project Development Objective [PDO] and deliver value for money under a risk-based approach. It provides adequate supporting market analysis for the selection methods detailed in the procurement plan. The procurement plan specifies for each contract: [i] a description of the activities/contracts; [ii] selection methods to be applied; [iii] estimated cost; [iv] time schedules; [v] World Bank review requirements; and [vi] any other relevant procurement information. PMU shall submit to the World Bank, for its review and approval, any updates of the procurement plan approved by the World Bank. The project will use Systematic Tracking of Exchanges in Procurement [STEP] system for all its procurement activities carried out at the PMU [Centre] and District levels. Summary from PPSD. The project is preparing its Procurement Strategy document. As per the draft document, the project’s total value is US $100 million of which procurement spend is approximately 80 %. Extensive market analysis has been carried out for procurement packages and decisions on packages are made to ensure adequate participation of bidders. Consultancy contracts are framed based on market research and packaging decided in terms of scope of services and period. Based on the need assessment, the project has decided to 6 use Government e Marketplace [GeM]1 for procurement of Goods up to US $100,000 and as mentioned under the paragraph in the Procurement Plan on National Procurement Procedures. Procurement Capacity Building. Though project staff has past experience of implementing World Bank financed HP Mid-Himalayan Watershed Development Project [HPMHWDP] governed by the Bank’s Procurement Guidelines, however, they need to be exposed to the Procurement Regulations applicable to the Project. HP Forestry Department will be sending key procurement staff of PMU and DPOs to the Indian Institute of Management [IIM], Lucknow or the Administrative Staff College of India [ASCI], Hyderabad from time to time to attend procurement training on World Bank Procurement Framework [PF] applicable to the project. Presently, project staff from PMU and two DPOs will be attending the two-week residential training program on World Bank Procurement Regulations conducted at ASCI, Hyderabad in February 2020. These officials will subsequently provide training to other project staffs prior to implementation of the procurement activities in the project. The PMU/DPOs/APOs will also provide basic procurement training to GPs/Beneficiaries once the Gram Panchayat Resource Management Plan [GP-RMP] is approved by DPO/PMU, and before commencing implementation of GP-RMP. The project officials can also avail of the free Massive Open Online Course on public procurement www.procurementlearning.org offered by the Bank to build their capacity. The Bank had already conducted one training on STEP for PMU officials and will organize STEP training again on need basis for the concerned DPOs staff in near future. Procurement Planning. For each contract to be financed by the Loan, the different procurement methods or consultant selection methods to be used, the need for pre-qualification, estimated costs, prior review requirements, and time frame will be reflected in the Procurement Plan to be agreed between the Borrower and the Bank team. The Procurement Plan will be uploaded in STEP by PMU/DPOs and the approved procurement plan will be disclosed on the project website and Bank’s external website. The procurement plan for the first 18 months of project implementation and all its updates will be submitted to the Bank through STEP, and will lay out the appropriate, fit for purpose market approach and selection methods for procurement of goods, works, non-consulting and consulting services financed by the Bank. It will be updated at least annually or as required to reflect the actual project implementation needs and improvements in institutional capacity. eProcurement. Currently, the Himachal Pradesh Forestry Department of the Government of Himachal Pradesh is using e-procurement system for its procurement. However, PMU housed in the Forestry Department will be carrying out procurement using eProcurement for the first time in the project, therefore, their capacity building needs to be done for eProcurement. The project will make use of Government of India’s National Informatics Centre [NIC] platform assessed by the Bank against Multilateral Development Bank [MDB] requirements for procurements estimated at INR 5 Lakhs and above. Advance Contracting with Retroactive Financing. For effective project implementation and start-up, the project has initiated advance contracting of critical consultancies for Preparation of Environmental and Social Framework [ESF] and Project Implementation Plan [PIP], and procurement of small value goods such 1 https://gem.gov.in/ 7 as tools, gunny bags, seeds, IT equipment and accessories, vehicles, etc.] and works [very small value labor contracts for Development of Nurseries [52 nos.] in 26 clusters in 10 Districts covering 428 GPs. The total value of this spend is approximately 1.2 % of the Bank loan. Payment made by PMU/HPFD for these contracts following World Bank procurement procedures during the 12 months prior to the tentative Loan signing date shall be eligible for retroactive financing. Record Keeping. All records pertaining to award of tenders/selection of consultants, including tender notification/advertisement, register pertaining to sale and receipt of bids, bid/proposal opening minutes, bid/technical and financial evaluation reports, comparative statements, Goods, Receipt Note [GRN] and all correspondence pertaining to bid evaluation, communication sent to/with the Bank in the process, bid securities, and approval of invitation/evaluation of bids/proposals would be maintained by the PMU and at DPO/GP level. Contract Management. The PMU, HPFD will be responsible for overall procurement and contract management under the project. At the Centre, procurement staff will be responsible for contract monitoring and supervision of contracts awarded by PMU. At DPO level, contract monitoring and supervision will be done by technical staff at DPOs/APOs level [Agriculture, Animal Husbandry/Engineering staff of technical wing of DPO level and Forest Extension and Social Extension staff at APO level] to ensure timely delivery of quality outputs from the procurement contracts in the project areas. All payments will be made by DPOs for district and sub-district level procurements after receipt of Goods receipt Note [GRN]. Work Completion Certificates, etc. The Integrated Financial Management Information System [IFMIS] being developed under the Project will facilitate monitoring of various procurement activities in terms of physical and financial achievements on a monthly basis. The day to day monitoring of procurement activities will be done by APOs/DPOs at field level which will be updated in the online web-based system at district level and will be reviewed by PMU at the Centre. Complaint Handling Mechanism. A complaint handling mechanism to address procurement-related complaints under the Project will be developed and implemented by the PMU/DPOs to the satisfaction of the Bank. Upon receipt of complaints, immediate action would be initiated to acknowledge the complaint and to redress it within a reasonable timeframe. All complaints will be addressed at levels higher than the level at which the procurement process was undertaken, or the decision was taken. Any complaint received will also be forwarded to the Bank for information, and the Bank would be kept informed after the complaint is redressed. Leased Assets: Not Applicable Procurement of Secondhand Goods: Not Applicable Domestic Preference: The provision of domestic preference will be applied in the evaluation of bids in accordance with Annex VI of the Regulations. Procurement Thresholds and Prior Review Thresholds. The table below describes various procurement methods to be used for activities financed by the Loan. 8 Table 1: Procurement Thresholds Procurement approach and method Thresholds [US$ equivalent] Open International [Goods, IT, and >10 million Non-consulting services] – Request for Bids [RFB] Open National [Goods, IT, and Non- >100,000 and up to 10 million consulting services] – Request for Bids [RFB] National Request for Quotation Up to 100,000 [RFQ] – [Goods/Works/Non- consulting Services] Open International [Works] – >40 million Request for Bids [RFB] Open National [Works] - Request for >100,000 and up to 40 million Bids [RFB] Direct Selection With prior agreement, based on justification Framework Agreement For Goods/Works/Non-consulting services: According to paragraphs 6.57-6.59 of Section VI of the Regulations. For Consulting services: According to paragraph 7.33 of Section VII the Regulations. Force Account In accordance with paragraphs 6.54 and 6.55 of Section VI of the Procurement Regulations, and with prior agreement in Procurement plan with the Bank. Consulting Services [Firms] CQS: As per requirements of paragraphs 7.11 and 7.12 of Section VII of the Regulations. LCS, FBS: in justified cases QCBS, QBS: in all other packages Shortlist of National Consultants Up to 800,000 Procurement prior-review thresholds2. Based on the current procurement risk rating of ‘Moderate’, the World Bank will prior review the following contracts: (a) Works [including turnkey, supply and installation of plant and equipment and PPP]: All contracts more than US $15 million equivalent 2 Determination of whether a contract meets the prior review threshold is based on : (i) the total value of the contract, including all taxes and duties payable under the contract; (ii) a contract whose cost estimate was below the Bank’s prior review threshold is subject to prior review if the price of the lowest evaluated responsive bid (or, in the case of consulting services, the financial offer of the selected firm) exceeds such threshold at the bid evaluation stage; and (iii) in the case of a slice and package arrangement, the prior review threshold is determined based on the aggregate value of individual contracts to be awarded under such arrangement. 9 (b) Goods and Information Technology: All contracts > US $4 million equivalent (c) Non-consulting Services: All contracts > US $4 million equivalent (d) Consulting Services: Firms: All contracts >US $2 million equivalent (e) Consulting Services: Individuals: All contracts > US $400,000 equivalent (f) Direct Selection: The justification of Direct Selection for all contracts The above thresholds are for the initial 18-month implementation period. Based on the procurement performance of the project, these thresholds may be subsequently modified. Even for large-value post review cases, the inputs of the World Bank on technical specifications will be obtained by the project. Irrespective of the thresholds, Terms of Reference shall be prior reviewed by Bank. The prior review thresholds will also be indicated in the Procurement Plan. The Procurement Plan will be subsequently updated annually [or at any other time if required] and will reflect any change in the prior review thresholds. The details of National Procurement Procedures are outlined in the Procurement Plan. Prior review contracts. In the case of contracts subject to prior review, PMU, HPFD/DPOs will seek the World Bank’s no objection before granting/agreeing to: [a] an extension of the stipulated time for performance of a contract that either increases the contract price or has an impact on the planned completion of the project; [b] any substantial modification of the scope of Works, goods, IT system; non-consulting services, or consulting services and other significant changes to the terms and conditions of the contract; [c] any variation order or amendment [except in cases of extreme urgency] that, singly or combined with all variation orders or amendments previously issued, increases the original contract amount by more than 15 percent; and [d] the proposed termination of the contract. Complaints received in all prior review cases shall be sent to Bank for review and the response to the complaint in such cases, shall be cleared with the Bank. Complaints with allegations of fraud and corruption, shall be shared with Bank, irrespective of the thresholds. Disclosure of procurement information. The following documents shall be disclosed on the project/state websites: [a] Procurement Plan and its updates; [b] an invitation for bids for procurement of Works, Goods, IT system procurement and non-consulting services; [c] request for expression of interest for selection/hiring of consulting services; [d] contract awards of Works, Goods, IT system procurement and non-consulting services procured following international and national procedures; [e] a list of contracts/purchase orders placed following RFQ [Request for Quotation] procedures on a quarterly basis; [f] a list of contracts following direct contracting [DC] on a quarterly basis; [g] an annual financial and physical progress report of all contracts; and [h] an action taken report on the complaints received on a quarterly basis. The following details shall be sent to the World Bank for publishing on the United Nations Development Business and the World Bank external website: [a] Specific Procurement Notice [i.e., invitation for bids] for procurement of Works, Goods, IT system procurement and non-consulting services using open international procedures; [b] Requests for Expression of Interests above US $800,000; [c] contract award details of all procurement of Works, Goods, IT system procurement and non-consulting services using open international procedure; and [d] a list of contracts/purchase orders placed following DC procedures on a quarterly basis. Further, the implementing agency will also publish on their websites any information required under the provisions of ‘suo moto’ disclosure as specified by the Right to Information Act. 10 National Procurement Procedure Conditions. National competition for the procurement of Works, Goods, IT system procurement and non-consulting services according to the established thresholds will be conducted in accordance with paragraphs 5.3–5.5 of Section V of the Regulations and the following provisions: I. Only the model bidding documents for National Competitive Procurement [NCP] agreed with the GOI Task Force [and as amended for time to time], shall be used for bidding. II. Invitations to bid shall be advertised on a widely used website or electronic portal with free open access at least 30 days prior to the deadline for the submission of bids, unless otherwise agreed in the approved procurement plan. III. No special preference will be accorded to any bidder either for price or for other terms and conditions when competing with foreign bidders, state- owned enterprises, small-scale enterprises or enterprises from any given State. IV. Except with the prior concurrence of the Bank, there shall be no negotiation of price with the bidders, even with the lowest evaluated bidder. V. Government e-Marketplace [GeM] set-up by Ministry of Commerce, Government of India will be acceptable for procurement under Request for Quotations [RFQ] method. VI. At the Borrower’s request, the Bank may agree to the Borrower’s use, in whole or in part, of its electronic procurement system, provided that the Bank is satisfied with the adequacy of such system. VII. Procurement will be open to eligible firms from any country. This eligibility shall be as defined under Section III of the Procurement Regulations. Accordingly, no bidder or potential bidder shall be declared ineligible for contracts financed by the Bank for reasons other than those provided in Section III of the Procurement Regulations. VIII. The request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals include a signed acceptance in the bid, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. IX. The Borrower shall use an effective complaints mechanism for handling procurement related complaints in a timely manner. X. Procurement Documents will include provisions, as agreed with the Bank, intended to adequately mitigate against environmental, social [including sexual exploitation and abuse and gender-based violence], health and safety [“ESHS”] risks and impacts. Oversight and Monitoring by the Bank. All contracts not covered under prior review by the Bank will be subject to post review during implementation support missions and/or special post review missions, including missions by consultants hired by the Bank. The Bank may conduct, at any time, Independent Procurement Reviews [IPRs] of all the contracts financed under the loan. High risk procurements, if any, will be identified for increased procurement and contract management support and indicated in the procurement plan. Bank team will provide additional due diligence and independent review of the contract performance of such identified procurements. 11 Procurement Review by the PMU, HPFD. Independent procurement post review [PPR] with reporting requirements and agreed with the Bank [As per Para 4 of Annex II of the Procurement Regulations] will be undertaken for the project for PMU’s own internal due diligence. PMU will hire PPR consultants as per Terms of Reference and reporting requirements agreed with the Bank to conduct PPR of PMU and DPOs on a half yearly basis. Other Special Selection Arrangements/Requirement Procurement by communities will be governed by the procedures outlined in the Community Operations Manual [COM] currently under preparation and in accordance with Paras 6.52 and 6.53 of Section VI of the Regulations. COM will be disclosed on the Project website. Procurement Plan as per STEP Tables: 12 PROCUREMENT India : Integrated Project for Source Sustainability and Climate Resilient Rain-fed Agriculture in Himachal Pradesh PLAN General Information Country: India Bank’s Approval Date of the Original Procurement Plan: 2020-10-20 Revised Plan Date(s): (comma delineated, leave blank if none) 2021-05-27 Project ID: P165129 GPN Date: 2019-12-19 Project Name: Integrated Project for Source Sustainability and Climate Resilient Rain-fed Agriculture in Himachal Pradesh Loan / Credit No: IBRD / 90410 D Executing Agency(ies): istrict Project Office, Hamirpur, Himachal Pradesh Forestry Department WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned IN-DPO, HAMIRPUR-176307- CW-RFQ / Development of New Forest Nursery at Kalwal and Khazian under APO Unit Component 1. Sustainable Request for Single Stage - One 2021-03- Barsar. Keeping in view of low IBRD / 90410 Land and Water Resource Post Limited 7,570.00 6,217.92 Completed 2020-07-15 2020-01-04 2020-09-09 2020-02-04 Quotations Envelope 08 value and availability of Management perspective bidder, limited market approach was adopted. This does not come under RF. IN-DPO, HAMIRPUR-176312- CW-RFQ / Raising of Nursery Component 1. Sustainable Request for Single Stage - One 2021-03- in GP Kalwal & Khazian. Total IBRD / 90410 Land and Water Resource Post Limited 4,612.00 22,051.60 Signed 2020-07-13 2020-02-11 2020-09-07 2020-03-02 Quotations Envelope 06 No. of Plants in Nurseries Management =150000 No. IN-DPO, HAMIRPUR-177115- CW-RFQ / RFQ for Cutting/Removal/Disposal of Component 1. Sustainable Request for Single Stage - One 2021-03- Lantana By (CRS Method) IBRD / 90410 Land and Water Resource Post Limited 36,514.00 30,124.27 Signed 2020-07-12 2021-01-15 2020-09-06 2020-03-02 Quotations Envelope 05 Infestation Exten 140 ha. Management upto50% & 75%.for the Financial Year 2019-20. IN-DPO, HAMIRPUR-177117- CW-RFQ / Development of New Forest Nursery at Badehar under APO Unit Component 1. Sustainable Request for Single Stage - One 2021-03- Hamirpur. Keeping in view of IBRD / 90410 Land and Water Resource Post Limited 1,208.00 998.92 Signed 2020-07-12 2020-01-04 2020-09-06 2020-02-04 Quotations Envelope 05 low value and availability of Management perspective bidder, limited market approach was adopted. This does not come under RF. IN-DPO, HAMIRPUR-179206- CW-RFQ / Raising of Seedling at Badehar Forest Nursery under APO Unit Component 1. Sustainable Request for Single Stage - One 2021-03- Barsar.Keeping in view of low IBRD / 90410 Land and Water Resource Post Limited 59,329.00 3,691.75 Signed 2020-07-12 2020-02-11 2020-09-06 2020-03-02 Quotations Envelope 05 value and availability of Management perspective bidder, limited market approach was adopted.This does not come under RF. IN-DPO, HAMIRPUR-179308- CW-RFQ / Development of New Forest Nursery at Kalwal Component 1. Sustainable and Khazian under APO Unit Request for Single Stage - One 2021-01- IBRD / 90410 Land and Water Resource Post Limited 8,253.00 5,519.52 Signed 2020-06-30 2020-03-03 2020-08-02 2020-03-13 Barsar. Keeping in view of low Quotations Envelope 29 Management value and availability of perspective bidder, limited market approach was adopted. IN-DPO, HAMIRPUR-179319- CW-RFQ / Raising of plantations in the rainy season of 2020 (1100 plants/ha) . It involves Component 1. Sustainable Request for Single Stage - One 2020-12- multiple contracts.Limited IBRD / 90410 Land and Water Resource Post Limited 77,645.00 34,784.18 Signed 2020-06-18 2020-07-08 2020-09-04 2020-08-06 Quotations Envelope 23 approach is adopted as the Management perspective bidders are available at different locations and also based on value of contract. IN-DPO, HAMIRPUR-179333- CW-RFQ / Contour trenching in plantation area including grass seeding at 48 locations Component 1. Sustainable Request for Single Stage - One 2021-02- in the entire IBRD / 90410 Land and Water Resource Post Limited 91,703.00 92,801.87 Signed 2020-06-22 2020-07-08 2020-08-17 2020-07-29 Quotations Envelope 13 district.Cumulative value of Management this activity involves multiple contracts based on low value and small minor labor works IN-DPO, HAMIRPUR-179337- CW-RFQ / Vegetative Check Component 1. Sustainable Pending Barriers . There will be 10 to Request for Single Stage - One 2021-02- IBRD / 90410 Land and Water Resource Post Limited 58,067.00 0.00 Implementat 2020-06-30 2020-08-19 15 jobs (contract) of 22000 Quotations Envelope 15 Management ion Rmt. for the Financial Year 2020-21. IN-DPO, HAMIRPUR-179364- CW-RFQ / Clearing of Lantana infested upto 25% to 50% 1st Component 1. Sustainable Pending Request for Single Stage - One 2021-05- year. There will be 10 to 15 IBRD / 90410 Land and Water Resource Post Limited 32,546.00 0.00 Implementat 2020-08-20 2020-11-20 Quotations Envelope 06 jobs (contract) of 100 ha. area Management ion in different catchment.for the Financial Year 2020-21. IN-DPO, HAMIRPUR-179418- CW-RFQ / Construction of 11813 ponds (manual excavation) at different Component 1. Sustainable Pending Request for Single Stage - One 2021-04- locations (2 APO units) . The IBRD / 90410 Land and Water Resource Post Limited 105,294.00 0.00 Implementat 2020-09-07 2020-10-27 Quotations Envelope 25 estimated cost of each pond Management ion is approx Rs 76 lakh (105294 $) .It involves Multiple contracts Page 1 IN-DPO, HAMIRPUR-179470- CW-RFQ / Development of Forest Nursery at Khazian under APO Barsar. Keeping in Component 1. Sustainable Under Request for Single Stage - One 2021-02- view of low value and IBRD / 90410 Land and Water Resource Post Limited 11,554.00 0.00 Implementat 2020-06-30 2020-03-03 2020-08-10 Quotations Envelope 06 availability of perspective Management ion bidder, limited market approach was adopted. This does not come under RF. IN-DPO, HAMIRPUR-179516- CW-RFQ / Lantana maintenance from various GPs in APO Unit Barsar 140 ha by CRS method (50 to 75% Component 1. Sustainable Pending Request for Single Stage - One 2021-02- ).Keeping in view of low value IBRD / 90410 Land and Water Resource Post Limited 3,362.00 0.00 Implementat 2020-08-20 2020-09-10 Quotations Envelope 24 and availability of perspective Management ion bidder, limited market approach was adopted. This does not come under RF for yr 2019-20 IN-DPO, HAMIRPUR-179722- CW-RFQ / Next year advance Component 1. Sustainable Request for Single Stage - One 2021-05- works in 400 ha. for the year IBRD / 90410 Land and Water Resource Post Limited 250,448.00 275,872.27 Signed 2020-10-08 2020-07-08 2020-11-27 2020-08-06 Quotations Envelope 26 2021-22. There will be 50- Management 70 jobs. IN-DPO, HAMIRPUR-183964- CW-RFQ / Renovation of Component 1. Sustainable Pending Request for Single Stage - One 2021-03- Water Bouries. There will be IBRD / 90410 Land and Water Resource Post Limited 82,481.00 0.00 Implementat 2020-07-18 2020-09-12 Quotations Envelope 11 15 to 20 jobs(Contract) for Management ion the financial year 2020-21. IN-DPO, HAMIRPUR-183970- CW-RFQ / Raising of Nursery Component 1. Sustainable Pending Request for Single Stage - One 2021-03- at Badehar GP Badehar . Total IBRD / 90410 Land and Water Resource Post Limited 2,561.00 0.00 Implementat 2020-07-18 2020-09-12 Quotations Envelope 11 no. of plants in nursery = Management ion 25000. IN-DPO, HAMIRPUR-179326- CW-RFQ / Raising of plantations in the rainy season of 2020 (800 Component 1. Sustainable plants/ha) . It involves 20 Request for Single Stage - One 2021-02- IBRD / 90410 Land and Water Resource Post Limited 288,684.00 123,913.59 Signed 2020-06-18 2020-07-08 2020-07-03 2020-08-06 Jobs.Limited approach is Quotations Envelope 08 Management adopted as the perspective bidders are available at different locations and also based on value of contract. IN-DPO, HAMIRPUR-179330- CW-RFQ / Raising of plantations in the rainy season of 2020 (400 plants/ha) . It involves 8 Component 1. Sustainable Request for Single Stage - One 2021-02- Jobs.Limited approach is IBRD / 90410 Land and Water Resource Post Limited 166,282.00 50,567.04 Signed 2020-06-18 2020-07-08 2020-07-03 2020-08-06 Quotations Envelope 08 adopted as the perspective Management bidders are available at different locations and also based on value of contract for the year 2020. IN-DPO, HAMIRPUR-216824- Component 1. Sustainable Pending CW-RFQ / Construction of Dry Request for Single Stage - One 2021-03- IBRD / 90410 Land and Water Resource Post Limited 150,690.00 0.00 Implementat 2021-01-30 2021-03-02 Stone Structures under soil & Quotations Envelope 31 Management ion moisture conservation IN-DPO, HAMIRPUR-216942- Component 1. Sustainable Pending CW-RFQ / construction of Request for Single Stage - One 2021-03- IBRD / 90410 Land and Water Resource Post Limited 132,949.00 0.00 Implementat 2021-02-01 2021-03-02 Crate Wire Structures under Quotations Envelope 31 Management ion soil & moisture conservation IN-DPO, HAMIRPUR-216974- CW-RFQ / Construction of Component 1. Sustainable Under Request for Single Stage - One 2021-03- cement concrete Check IBRD / 90410 Land and Water Resource Post Limited 106,760.00 0.00 Implementat 2021-02-01 2021-01-30 2021-03-08 Quotations Envelope 31 Barriers in different catchment Management ion areasf IN-DPO, HAMIRPUR-218814- CW-RFQ / Construction of Component 1. Sustainable Request for Single Stage - One 2021-03- Modern Nursery U-97 Paprol IBRD / 90410 Land and Water Resource Post Limited 68,635.00 24,936.86 Signed 2021-02-15 2021-02-15 2021-03-13 2021-03-15 Quotations Envelope 31 Brahmna Under APO Unit Management Barsar 20-21. IN-DPO, HAMIRPUR-218807- CW-RFQ / Clearing of Lantana infested areas up to (25% to 50%,50% to 75%, 75% to 100%) Component 1. Sustainable Request for Single Stage - One 2021-03- Ist year. There will be IBRD / 90410 Land and Water Resource Post Limited 69,498.30 71,713.23 Signed 2021-02-15 2021-01-27 2021-03-10 2021-02-17 Quotations Envelope 31 approximately 23 jobs of 175 Management Ha. area in different catchment for the financial year 2020-21. IN-DPO, HAMIRPUR-208299- CW-RFQ / Clearing of Lantana infested upto (25% to 50%, Component 1. Sustainable 50%to 75%, 75% to 100% ) 1st Request for Single Stage - One 2021-03- IBRD / 90410 Land and Water Resource Post Limited 45,989.00 46,290.81 Completed 2020-12-13 2020-11-26 2021-02-07 2020-12-17 year. There will be 16 Quotations Envelope 25 Management jobs(contract) of 119Ha. area in different catchment for the Financial year 2020-21 IN-DPO, HAMIRPUR-226433- CW-RFQ / Maintenance of 4 No Nurseries at Kalwal, Component 1. Sustainable Pending Khazian , Badahar & Paplol Request for Single Stage - One 2021-09- IBRD / 90410 Land and Water Resource Post Limited 24,000.00 0.00 Implementat 2021-04-05 2021-04-23 Brahmana (Modern Nursery Quotations Envelope 30 Management ion under APO Barsar and Hamirpur of DPO, IDP Hamirpur. IN-DPO, HAMIRPUR-232667- Component 1. Sustainable Request for Pending CW-RFQ / Raising of Request for Single Stage - One 2022-07- IBRD / 90410 Land and Water Resource Post Limited Quotations (Non 63,986.00 0.00 Implementat 2021-10-25 2021-11-26 Seedlings at Kalwal, Badehar Quotations Envelope 31 Management Bank-SPD) ion and Khazian Forest Nursery Page 2 IN-DPO, HAMIRPUR-232669- CW-RFQ / Modern Nursery Component 1. Sustainable Request for Pending development raising and Request for Single Stage - One 2022-07- IBRD / 90410 Land and Water Resource Post Limited Quotations (Non 53,977.32 0.00 Implementat 2021-05-25 2021-06-18 maintenance U-97 Paprol Quotations Envelope 20 Management Bank-SPD) ion Brahmna Under APO Unit Barsar 21-22. IN-DPO, HAMIRPUR-232680- CW-RFQ / Contour trenching Component 1. Sustainable Request for Pending Request for Single Stage - One 2022-01- in plantation area including IBRD / 90410 Land and Water Resource Post Limited Quotations (Non 33,974.40 0.00 Implementat 2021-06-06 2021-07-15 Quotations Envelope 11 grass seeding at 48 locations Management Bank-SPD) ion in the entire district. IN-DPO, HAMIRPUR-233142- Component 1. Sustainable Request for Pending CW-RFQ / Construction of Request for Single Stage - One 2022-03- IBRD / 90410 Land and Water Resource Post Limited Quotations (Non 9,185.86 0.00 Implementat 2021-06-25 2021-08-03 ponds (manual excavation) at Quotations Envelope 16 Management Bank-SPD) ion different locations IN-DPO, HAMIRPUR-233144- Component 1. Sustainable Request for Pending Request for Single Stage - One 2022-02- CW-RFQ / Construction of IBRD / 90410 Land and Water Resource Post Limited Quotations (Non 40,482.99 0.00 Implementat 2021-07-08 2021-08-18 Quotations Envelope 14 Earthen Check Dam Management Bank-SPD) ion IN-DPO, HAMIRPUR-233146- Component 1. Sustainable Request for Pending CW-RFQ / Vegetative Check Request for Single Stage - One 2022-01- IBRD / 90410 Land and Water Resource Post Limited Quotations (Non 600.00 0.00 Implementat 2021-05-25 2021-07-08 Barriers along the drainage Quotations Envelope 04 Management Bank-SPD) ion line IN-DPO, HAMIRPUR-233148- CW-RFQ / Construction of Dry Component 1. Sustainable Request for Pending Request for Single Stage - One 2022-02- Stone check dam Structures IBRD / 90410 Land and Water Resource Post Limited Quotations (Non 44,000.00 0.00 Implementat 2021-07-05 2021-08-11 Quotations Envelope 07 under soil & moisture Management Bank-SPD) ion conservation IN-DPO, HAMIRPUR-233149- Component 1. Sustainable Request for Pending CW-RFQ / construction of Request for Single Stage - One 2022-02- IBRD / 90410 Land and Water Resource Post Limited Quotations (Non 93,207.78 0.00 Implementat 2021-07-05 2021-08-30 Crate Wire Structures under Quotations Envelope 26 Management Bank-SPD) ion soil & moisture conservation IN-DPO, HAMIRPUR-233150- Component 1. Sustainable Request for Pending Request for Single Stage - One 2022-01- CW-RFQ / Renovation of IBRD / 90410 Land and Water Resource Post Limited Quotations (Non 65,871.63 0.00 Implementat 2021-05-30 2021-07-25 Quotations Envelope 21 Water Bouries/springs Management Bank-SPD) ion IN-DPO, HAMIRPUR-233151- Component 1. Sustainable Request for Pending CW-RFQ / Maintenance of Request for Single Stage - One 2022-01- IBRD / 90410 Land and Water Resource Post Limited Quotations (Non 48,512.33 0.00 Implementat 2021-06-06 2021-07-15 plantations carried out during Quotations Envelope 11 Management Bank-SPD) ion 2020-21 for 490 ha. IN-DPO, HAMIRPUR-233157- CW-RFQ / 1st year Lantana Component 1. Sustainable Request for Pending Request for Single Stage - One 2022-03- eradication maintenance IBRD / 90410 Land and Water Resource Post Limited Quotations (Non 18,545.72 0.00 Implementat 2021-10-25 2021-12-02 Quotations Envelope 30 works in 294 ha by CRS Management Bank-SPD) ion method IN-DPO, HAMIRPUR-233164- CW-RFQ / 2nd year Lantana Component 1. Sustainable Request for Pending Request for Single Stage - One 2022-03- eradication maintenance work IBRD / 90410 Land and Water Resource Post Limited Quotations (Non 20,273.27 0.00 Implementat 2021-10-25 2021-12-20 Quotations Envelope 25 for 140 ha by Cut Root Stock Management Bank-SPD) ion method IN-DPO, HAMIRPUR-233168- Component 1. Sustainable Request for Pending CW-RFQ / Construction of Request for Single Stage - One 2022-03- IBRD / 90410 Land and Water Resource Post Limited Quotations (Non 81,118.92 0.00 Implementat 2021-07-15 2021-09-09 Tanks, Sump wells, etc for Quotations Envelope 08 Management Bank-SPD) ion water harvesting IN-DPO, HAMIRPUR-235194- Component 1. Sustainable Request for Pending CW-RFQ / Demonstrations Request for Single Stage - One 2022-07- IBRD / 90410 Land and Water Resource Post Limited Quotations (Non 4,101.58 0.00 Implementat 2021-11-09 2022-01-04 and Promotion of Climate Quotations Envelope 03 Management Bank-SPD) ion smart agriculture IN-DPO, HAMIRPUR-235198- Component 1. Sustainable Request for Pending Request for Single Stage - One 2022-09- CW-RFQ / Fire Management IBRD / 90410 Land and Water Resource Post Limited Quotations (Non 6,835.97 0.00 Implementat 2022-01-30 2022-03-27 Quotations Envelope 23 and awareness. Management Bank-SPD) ion IN-DPO, HAMIRPUR-235202- Component 2. Improved Request for Pending Request for Single Stage - One 2022-02- CW-RFQ / Primary and IBRD / 90410 Agricultural Productivity and Post Limited Quotations (Non 82,031.64 0.00 Implementat 2021-07-07 2021-09-01 Quotations Envelope 28 Secondary water Distribution. Value Addition Bank-SPD) ion IN-DPO, HAMIRPUR-232672- CW-RFQ / Raising of Component 1. Sustainable Request for Pending Request for Single Stage - One 2022-01- plantations in the rainy IBRD / 90410 Land and Water Resource Post Limited Quotations (Non 73,059.36 0.00 Implementat 2021-06-29 2021-07-22 Quotations Envelope 18 season of 2021 (800 Management Bank-SPD) ion plants/ha model). IN-DPO, HAMIRPUR-233143- CW-RFQ / Construction of Component 1. Sustainable Request for Pending Request for Single Stage - One 2022-03- cement concrete Check IBRD / 90410 Land and Water Resource Post Limited Quotations (Non 93,000.00 0.00 Implementat 2021-06-15 2021-08-01 Quotations Envelope 20 Barriers in different catchment Management Bank-SPD) ion areas IN-DPO, HAMIRPUR-232678- CW-RFQ / Raising of Component 1. Sustainable Request for Pending Request for Single Stage - One 2022-01- plantations in the rainy IBRD / 90410 Land and Water Resource Post Limited Quotations (Non 48,410.00 0.00 Implementat 2021-06-15 2021-07-09 Quotations Envelope 05 season of 2021 (400 Management Bank-SPD) ion plants/ha model) . IN-DPO, HAMIRPUR-233145- Component 1. Sustainable Request for Pending CW-RFQ / Construction of Request for Single Stage - One 2022-02- IBRD / 90410 Land and Water Resource Post Limited Quotations (Non 90,000.00 0.00 Implementat 2021-07-15 2021-08-27 Roof Rain Water Harvesting Quotations Envelope 23 Management Bank-SPD) ion structures (RRWHS) IN-DPO, HAMIRPUR-237512- CW-RFQ / Advance plantation work 400 Plant/ha model Component 1. Sustainable Request for Pending (Fencing ) for 145 Hac. This Request for Single Stage - One 2022-02- IBRD / 90410 Land and Water Resource Post Limited Quotations (Non 97,900.00 0.00 Implementat 2021-06-15 2021-08-10 activity involves multiple Quotations Envelope 06 Management Bank-SPD) ion contract at different location of Hamirpur District. Limited market approach is adopted Page 3 IN-DPO, HAMIRPUR-237514- CW-RFQ / Advance plantation work in 800 Plant/ha model Component 1. Sustainable Request for Pending (Fencing ) for 123 Hac. This Request for Single Stage - One 2022-02- IBRD / 90410 Land and Water Resource Post Limited Quotations (Non 83,050.00 0.00 Implementat 2021-06-15 2021-08-10 activity involves multiple Quotations Envelope 06 Management Bank-SPD) ion contract at different location of Hamirpur District. Limited market approach is adopted GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-DPO, HAMIRPUR-175972- GO-RFQ / Black Recycled Poly Bags 5' x 9' of 250 Gauge double sealed with six holes Component 1. Sustainable in 2 rows of 3 holes in each in Request for Single Stage - One IBRD / 90410 Land and Water Resource Post Limited 2,021.93 1,860.76 Completed 2020-07-20 2020-01-08 2020-09-14 2020-01-18 2021-03-13 2020-02-20 the lower 2 by 3 portion, Dia. Quotations Envelope Management of hole 3 mm.Keeping in view of low value and availability of perspective bidder, limited market approach was adopted IN-DPO, HAMIRPUR-175979- GO-RFQ / Supply of Forestry Component 1. Sustainable Seeds and cuttings (Amla, Request for Single Stage - One IBRD / 90410 Land and Water Resource Post Limited 2,241.26 2,061.90 Completed 2020-07-22 2020-01-15 2020-09-16 2020-02-04 2021-03-15 2020-03-07 Behra, Kachnaar, Bamboo, Quotations Envelope Management Dehu and Teak cuttings) for the financial year 2019-20 IN-DPO, HAMIRPUR-175982- GO-RFQ / Quotation for Hot- Dripped Galvanized Steel Component 1. Sustainable Request for Single Stage - One Barbed Wire for fencing (ISI IBRD / 90410 Land and Water Resource Post Limited 11,595.92 10,640.19 Completed 2020-07-18 2020-02-24 2020-09-12 2020-03-15 2021-03-11 2020-03-15 Quotations Envelope marked) and U. Nails Staples Management for fencing the Barbed Wire.for the Financial Year 2019-20. IN-DPO, HAMIRPUR-179483- Component 1. Sustainable Pending GO-RFQ / Supply of P.Bags for Request for Single Stage - One IBRD / 90410 Land and Water Resource Post Limited 9,904.00 0.00 Implementati 2020-06-16 2020-08-11 2021-02-07 raising of nursery Qty. 30 qtl. Quotations Envelope Management on for the financial year 2020-21 IN-DPO, HAMIRPUR-179488- GO-RFQ / Raising of Seedling at Kalwal and Khazian Forest Nursery under APO Unit Component 1. Sustainable Pending Barsar.Keeping in view of low Request for Single Stage - One IBRD / 90410 Land and Water Resource Post Limited 2,641.00 0.00 Implementati 2020-06-22 2020-08-17 2021-02-13 value and availability of Quotations Envelope Management on perspective bidder, limited market approach was adopted.This does not come under RF. 2021-22. IN-DPO, HAMIRPUR-218812- Component 2. Improved Pending GO-RFQ / Procurement of IBRD / 90410 Agricultural Productivity and Post Direct Selection Direct 935.00 0.00 Implementati 2021-03-22 2021-03-22 2021-03-25 2021-03-31 wheat seed and fertilizers for Value Addition on demonstration plots IN-DPO, HAMIRPUR-216985- Component 1. Sustainable Pending GO-RFQ / Purchase of Request for Single Stage - One IBRD / 90410 Land and Water Resource Post Limited 4,050.00 0.00 Implementati 2021-02-01 2021-02-18 2021-03-25 Forestry Seeds during 2020- Quotations Envelope Management on 21 IN-DPO, HAMIRPUR-222259- GO-RFQ / Seed, cultivation Component 2. Improved Pending Request for Single Stage - One material and fertilizers for IBRD / 90410 Agricultural Productivity and Post Limited 10,000.00 0.00 Implementati 2021-03-08 2021-03-30 2021-09-26 Quotations Envelope high value crops Value Addition on demonstration plots IN-DPO, HAMIRPUR-233176- GO-RFQ / Purchase of Component 1. Sustainable Pending Request for Single Stage - One Polythene bags and Forestry IBRD / 90410 Land and Water Resource Post Limited 5,000.00 0.00 Implementati 2021-11-06 2021-11-30 2022-03-31 Quotations Envelope seed for raising of nurseries Management on 2021-22 NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 4 PROCUREMENT PLAN - Textual Part Project information: Uzbekistan Medium-Size Cities Integrated Urban Development Project (P162929) Project Implementation agency: “State Investment Committee” or “SIC” means the Borrower’s governmental body established pursuant to the Borrower’s Presidential Decree No. УП-4996 “On the Formation of the State Committee of the Republic of Uzbekistan for Investments” dated March 31, 2017 Date of the Procurement Plan: November 7, 2018 Period covered by this Procurement Plan: From November 2018 to November 2019 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Law of Republic of Uzbekistan “On Public Procurement” dated January 25, 2018 such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions: 1. The request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. The Bank’s Anti-Corruption Guidelines and Sanctions Framework shall be incorporated into the national bidding documents by adding a page entitled “Letter of Acceptance of the World Bank’s Anti-Corruption Guidelines and Sanctions Framework”. 2. Contracts with an appropriate allocation of responsibilities, risks, and liabilities between the Borrower and the contractors/suppliers/consultants. 3. Rights for the Bank to review procurement documentation and activities. In accordance with the Procurement Regulations, each bidding document and contract shall include provisions stating the Bank's policy to sanction firms or individuals, found to have engaged in fraud and/or corruption as defined in the Procurement Regulations. In accordance with the Procurement Regulations, each bidding document and contract financed out of the proceeds of the Financing Agreement shall provide that bidders, suppliers, contractors and their subcontractors, agents, personnel, consultants, service providers, or suppliers shall permit the Bank to inspect all accounts, records and other documents relating to the bid submission and performance of the contract and to have said accounts and records audited by auditors appointed by the Bank. Acts intended to materially impede the exercise of the Bank's inspection and audit rights provided for in the Procurement Regulations constitute an obstructive practice as defined in the Regulations. 4. No bids shall be rejected solely because they fall below or exceed the estimated cost. All bids (including in the case when less than two bids are received) shall not be rejected, the procurement process shall not be cancelled, and new bids shall not be solicited without the Bank's prior written concurrence. The Bidding Documents template to be used under “national open competitive procurement arrangements” are subject to prior written concurrence by the Bank. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable. Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations: Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: applicable for those contracts identified in the Procurement Plan tables; Works: is applicable for those contracts identified in the Procurement Plan tables. PROCUREMENT Uzbekistan : Medium-Size Cities Integrated Urban Development Project PLAN General Information Country: Uzbekistan Bank’s Approval Date of the Original Procurement Plan: 2019-01-15 2021-05-24 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P162929 GPN Date: Project Name: Medium-Size Cities Integrated Urban Development Project Loan / Credit No: TF / A7556, IBRD / 89140 State Investment Committee of the Republic of Uzbekistan Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned MSC/UZB-C/W/1.6 / Restoration/strengthening and adaptive reuse in Component 1: Improvement accordance to modern energy of Urban Services and Single Stage - One 2020-11- IBRD / 89140 Post Request for Bids Open - National 500,553.00 0.00 Canceled 2020-02-12 2020-02-12 2020-02-17 2020-02-15 2020-03-30 2020-05-14 2020-04-29 2020-09-09 2020-06-03 efficiency norms of the former Enhancement of Public Urban Envelope 30 Kindergarten #17 and Spaces Administrative building at the Chartak city MSC/UZB-C/W/1.6.1 / Restoration/strengthening and adaptive reuse in Component 1: Improvement accordance to modern energy of Urban Services and Single Stage - One 2021-06- IBRD / 89140 Post Request for Bids Open - National 500,553.00 0.00 Canceled 2020-09-09 2020-09-11 2020-09-14 2020-09-11 2020-10-26 2020-08-05 2020-11-18 2020-09-11 2020-12-23 efficiency norms of the former Enhancement of Public Urban Envelope 21 Kindergarten #17 and Spaces Administrative building at the Chartak city MSC/UZB-C/W/1.6.2 / Restoration/strengthening and adaptive reuse in Component 1: Improvement accordance to modern energy of Urban Services and Single Stage - One 2021-06- IBRD / 89140 Post Request for Bids Open - National 500,553.00 459,525.50 Signed 2020-09-11 2020-07-04 2020-09-16 2020-10-28 2020-08-05 2020-11-27 2020-08-28 2021-01-01 2020-10-05 efficiency norms of the former Enhancement of Public Urban Envelope 30 Kindergarten #17 and Spaces Administrative building at the Chartak city. MSC-CKY/W/2.1 / Component 2: Institutional Construction / Repair of Single Stage - One 2021-08- IBRD / 89140 Strengthening and Capacity Post Request for Bids Open - National 340,000.00 0.00 Canceled 2020-10-23 2020-11-24 2020-11-02 2020-11-24 2020-12-14 2020-12-24 2021-01-13 2021-01-21 2021-02-17 Garage Premises for Municipal Envelope 16 Building Equipment in the Chartak city MSC-CKY/W/2.2 / Component 2: Institutional Construction / Repair of Single Stage - One 2021-08- IBRD / 89140 Strengthening and Capacity Post Request for Bids Open - National 300,000.00 0.00 Canceled 2020-10-23 2020-11-24 2020-10-28 2020-11-24 2020-12-09 2020-12-24 2021-01-08 2021-01-21 2021-02-12 Garage Premises for Municipal Envelope 11 Building Equipment in the Kagan city MSC-CKY/W/2.3 / Component 2: Institutional Construction / Repair of Single Stage - One 2021-08- IBRD / 89140 Strengthening and Capacity Post Request for Bids Open - National 330,000.00 0.00 Canceled 2020-10-23 2020-11-24 2020-10-28 2020-11-24 2020-12-09 2020-12-24 2021-01-08 2021-01-21 2021-02-12 Garage Premises for Municipal Envelope 11 Building Equipment in the Yangiyul city MSC-СKY/W/2.1.1 / Construction of garages for Component 2: Institutional Single Stage - One 2021-12- parking and maintenance of IBRD / 89140 Strengthening and Capacity Post Request for Bids Open - National 340,000.00 332,777.08 Signed 2021-02-11 2021-02-15 2021-02-21 2021-02-16 2021-04-04 2021-03-19 2021-05-04 2021-05-07 2021-06-08 2021-06-09 Envelope 05 special equipment in Chartak, Building Namangan region. MSC-СKY/W/2.2.1 / Construction of garages for Component 2: Institutional Single Stage - One 2021-12- parking and maintenance of IBRD / 89140 Strengthening and Capacity Post Request for Bids Open - National 300,000.00 300,299.26 Signed 2021-02-11 2021-02-15 2021-02-21 2021-02-16 2021-04-04 2021-03-19 2021-05-04 2021-05-07 2021-06-08 2021-06-14 Envelope 05 special equipment in Kagan, Building Bukhara region. MSC-СKY/W/2.3.1 / Construction of garages for Component 2: Institutional Single Stage - One 2021-12- parking and maintenance of IBRD / 89140 Strengthening and Capacity Post Request for Bids Open - National 330,000.00 0.00 Canceled 2021-02-11 2021-02-15 2021-02-21 2021-02-16 2021-04-04 2021-03-19 2021-05-04 2021-05-07 2021-06-08 Envelope 05 special equipment in Yangiyul, Building Tashkent region. MSC-C/W/1.4 / Component 1: Improvement Request for Bids - Reconstruction of the existing Under of Urban Services and Single Stage - One Small Works SPD 2022-09- building of the "Old Bazaar" IBRD / 89140 Post Request for Bids Open - National 746,158.55 0.00 Implementat 2021-05-24 2021-05-27 2021-06-01 2021-05-31 2021-07-15 2021-08-16 2021-09-27 Enhancement of Public Urban Envelope (1 envelope 30 located in Chartak city, ion Spaces process) Namangan region MSC-СKY/W/2.3.1.1 / Request for Bids - Construction of garages for Component 2: Institutional Under Single Stage - One Small Works SPD 2022-03- parking and maintenance of IBRD / 89140 Strengthening and Capacity Post Request for Bids Open - National 330,000.00 0.00 Implementat 2021-05-31 2021-05-31 2021-06-05 2021-05-31 2021-07-17 2021-08-16 2021-09-20 Envelope (1 envelope 19 special equipment in Yangiyul, Building ion process) Tashkent region. GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MSC/UZB-G-RFQ/2.1 / Strengthening the material Component 2: Institutional Request for Single Stage - One and technical base of the IBRD / 89140 Strengthening and Capacity Post Open - National 115,000.00 98,087.01 Completed 2020-02-12 2020-02-26 2020-02-27 2020-02-24 2020-04-30 2020-05-14 Quotations Envelope State Committee Tourism Building Development MSC/UZB-G/2.1 / Procurement of Special Component 2: Institutional Single Stage - One equipment for khokimiyats of IBRD / 89140 Strengthening and Capacity Prior Request for Bids Open - International 2,600,000.00 0.00 Canceled 2020-02-28 2020-02-27 2020-02-29 2020-03-05 2020-03-31 2020-05-14 2020-04-30 2020-09-15 2020-06-04 2020-12-01 Envelope Chartak, Kagan and Yangiyul Building cities Page 1 MSC/UZB-G/2.1.1 / Procurement of Special Component 2: Institutional Single Stage - One equipment for khokimiyats of IBRD / 89140 Strengthening and Capacity Prior Request for Bids Open - International 3,330,000.00 3,087,093.00 Signed 2020-09-14 2020-09-16 2020-09-19 2020-09-17 2020-10-31 2020-01-03 2020-11-30 2021-03-04 2021-01-04 2021-03-31 2021-07-03 Envelope Chartak, Kagan and Yangiyul Building cities NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MSCIUDP-CS/QCBS-03-02 / Development of feasibility study,detailed designs and construction supervision, for Component 1: Improvement the upgrading and of Urban Services and Quality And Cost- improvements of three cities TF / A7556 Prior Open - International 1,235,000.00 1,028,000.00 Signed 2018-10-04 2018-10-08 2018-11-21 2019-03-28 2018-12-19 2019-01-18 2019-05-02 2019-02-22 2019-09-11 2019-03-29 2019-11-08 2020-03-28 Enhancement of Public Urban Based Selection of Uzbekistan. The first Lump- Spaces Sum contract to be financed by ECAPDEV Grant and Second and Third contracts by IBRD Loans. UDP-CS/CQS-5 / Consultant Component 1: Improvement Consultant Firm for Environmental and of Urban Services and TF / A7556 Post Qualification Open - International 25,000.00 0.00 Canceled 2019-01-23 2018-08-06 2019-02-13 2019-03-29 2019-04-28 2019-06-02 2019-11-29 Social Safeguards, including Enhancement of Public Urban Selection training and RPF Spaces Component 1: Improvement UDP-CS/CQS-6 / M&E Consultant of Urban Services and surveys (beneficiary TF / A7556 Post Qualification Open - International 19,000.00 0.00 Canceled 2019-01-23 2018-11-15 2019-02-13 2019-03-29 2019-04-28 2019-01-17 2019-06-02 2019-11-29 Enhancement of Public Urban satisfaction survey) Selection Spaces Component 1: Improvement Consultant UDP-CS/CQS-04 / Grant of Urban Services and TF / A7556 Post Qualification Open - International 6,000.00 0.00 Canceled 2019-01-30 2019-02-20 2019-04-05 2019-05-05 2019-06-09 2019-12-06 Audit Enhancement of Public Urban Selection Spaces UDP-CS/CQS-01 / Preparation of detailed Component 1: Improvement designs DDs and Bidding Consultant of Urban Services and Documents, and construction IBRD / 89140 Post Qualification Open - International 80,000.00 80,000.00 Signed 2019-03-06 2019-03-05 2019-03-08 2019-03-25 2019-03-20 2019-03-28 2019-04-05 2019-04-01 2019-04-09 2019-09-30 Enhancement of Public Urban supervision. For the Phase 1 - Selection Spaces US $ 30 000 Lump Sum, Phase 2 - US $ 50 000 Time Based. MSCIUDP-CS/QCBS-05-02 / Development of a National Component 2: Institutional Monitoring and Evaluation Quality And Cost- IBRD / 89140 Strengthening and Capacity Post Open - International 270,000.00 0.00 Canceled 2019-09-27 2019-10-18 2019-12-01 2019-12-29 2020-01-28 2020-03-03 2020-04-07 2021-04-07 (M&E) system for the Based Selection Building sustainable Tourism & Travel sector in Uzbekistan MSCIUDP-CS/QCBS-06-01 / Analysis and Assessment of Component 2: Institutional the Financing of Urban Quality And Cost- IBRD / 89140 Strengthening and Capacity Prior Open - International 1,000,000.00 0.00 Canceled 2019-09-27 2019-10-18 2019-12-01 2019-12-29 2020-01-28 2020-03-03 2020-04-07 2021-04-07 Development and Based Selection Building Intergovernmental Fiscal Relations in Uzbekistan MSCIUDP-CS/QCBS-05-01 / Development of new susainable tourism destinations, including Component 2: Institutional Quality And Cost- Pending promotion, marketing & IBRD / 89140 Strengthening and Capacity Post Open - International 480,000.00 0.00 2019-11-05 2019-11-26 2020-01-09 2020-02-06 2020-03-07 2020-04-11 2020-05-16 2021-05-16 Based Selection Implementation branding strategy and action Building plan, for (i) the Fergana Valley and (ii) Bukhara Region in Uzbekistan MSC-PA/3.1 / Consultant for Component 3: Least Cost IBRD / 89140 Post Open - International 70,000.00 29,500.00 Signed 2020-06-19 2020-06-24 2020-07-10 2020-07-29 2020-08-23 2020-12-21 2020-09-20 2021-01-22 2020-10-20 2021-04-14 2020-11-24 2021-05-05 2020-12-29 2021-05-10 2021-06-27 Audit Implementation Support Selection MSC-CKY/CS/1.1 / Preparation of Detailed Design Component 1: Improvement and Bidding Documents, and of Urban Services and Quality And Cost- Under IBRD / 89140 Prior Open - International 2,200,000.00 0.00 2020-06-26 2020-06-30 2020-07-17 2020-08-27 2020-08-30 2021-01-08 2020-09-27 2021-02-11 2020-10-27 2021-06-17 2020-12-01 2021-01-05 2022-01-05 Construction Supervision for Enhancement of Public Urban Based Selection Implementation integrated urban upgrading in Spaces the three pilot cities. MSC-MA/3.2 / Project Monitoring and Evaluation Component 3: Fixed Budget IBRD / 89140 Post Open - International 80,000.00 79,700.00 Signed 2020-06-29 2020-09-11 2020-07-20 2020-09-11 2020-09-02 2021-02-01 2020-09-30 2021-03-09 2020-10-30 2021-04-14 2020-12-04 2021-05-05 2021-01-08 2021-05-10 2022-01-08 Baseline Survey and Implementation Support Selection Beneficiary Satisfaction MSC-CS/2.3 / Advisory Services to State Committee Component 2: Institutional Quality And Cost- Under on Tourism Development on IBRD / 89140 Strengthening and Capacity Prior Open - International 800,000.00 0.00 2020-06-29 2020-06-30 2020-07-20 2020-08-31 2020-09-02 2021-02-11 2020-09-30 2021-03-17 2020-10-30 2020-12-04 2021-01-08 2022-01-08 Based Selection Implementation developing comprehensive Building strategy MSCIUDP-CS/QCBS-04-01 / Detailed Design, Bidding Documents, and Supervision Component 1: Improvement for Restoration and adaptive of Urban Services and Quality And Cost- Under reuse of (i) Emir's Palace; (ii) IBRD / 89140 Prior Open - International 1,300,000.00 0.00 2019-09-30 2020-08-17 2019-10-21 2020-08-31 2019-12-04 2021-05-27 2020-01-01 2020-01-31 2020-03-06 2020-04-10 2021-04-10 Enhancement of Public Urban Based Selection Implementation Italian Hotel; and (iii) Russian Spaces Consulate (Makhalla Committee Building) in Kagan (Bukhara region) Page 2 MSC-CS/2.2 / Analysis and Assessment of the Financing Component 2: Institutional Quality And Cost- Under of Urban Development and IBRD / 89140 Strengthening and Capacity Prior Open - International 1,000,000.00 0.00 2020-12-01 2020-12-02 2020-12-01 2020-12-07 2021-01-19 2021-06-02 2021-02-16 2021-03-18 2021-04-22 2021-05-27 2022-05-27 Based Selection Implementation Intergovernmental Fiscal Building Relations in Uzbekistan INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 1: Improvement UDP-CS/SSS-01 / Feasibility of Urban Services and Studies and detailed designs TF / A7556 Prior Direct Selection Direct 30,000.00 0.00 Under Review 2019-01-23 2019-02-02 2019-04-08 2019-10-05 Enhancement of Public Urban for Year-1 Chartak Eco-trail Spaces MSCIUDP-CS/IND-02/1 / Individual Component 3: Project Implementation Unit TF / A7556 Prior Consultant Open 9,600.00 0.00 Canceled 2019-01-23 2019-03-13 2019-04-03 2019-05-08 2019-11-04 Implementation Support Manager Selection Individual MSCIUDP-CS/IND-02/4 / Component 3: TF / A7556 Post Consultant Open 5,600.00 0.00 Canceled 2019-01-23 2018-08-31 2019-03-13 2019-04-03 2019-05-08 2019-11-04 Sociologist Implementation Support Selection Individual MSCIUDP-CS/IND-02/5 / Component 3: TF / A7556 Post Consultant Open 5,200.00 0.00 Canceled 2019-01-23 2018-09-28 2019-03-13 2019-04-03 2019-05-08 2019-11-04 Ecologist Implementation Support Selection Individual MSCIUDP-CS/IND-02/6 / Component 3: TF / A7556 Post Consultant Open 5,200.00 0.00 Canceled 2019-01-23 2018-09-10 2019-03-13 2019-04-03 2019-05-08 2019-11-04 Engineer Implementation Support Selection MSCIUDP-CS/IND-02/3 / Individual Component 3: Financial management TF / A7556 Post Consultant Open 4,000.00 0.00 Canceled 2019-01-23 2019-03-13 2019-04-03 2019-05-08 2019-11-04 Implementation Support specialist Selection Individual MSCIUDP-CS/IND-02/2 / Component 3: TF / A7556 Post Consultant Open 8,800.00 0.00 Canceled 2019-03-06 2019-04-24 2019-05-15 2019-06-19 2019-12-16 Procurement specialist Implementation Support Selection MSC-C/CS/1.1 / Consulting services for the development Component 1: Improvement of detailed design, bidding of Urban Services and documents and construction IBRD / 89140 Post Direct Selection Direct 425,000.00 0.00 Canceled 2020-03-26 2020-02-03 2020-04-05 2020-02-28 2020-06-09 2021-04-01 Enhancement of Public Urban supervision of the Chartak Eco- Spaces Trail for non-motorized mobility in the city of Chartak MSC-CKY/CS/2.3.1.1 / Advisory Services to Ministry of Construction on Component 2: Institutional Individual modernization of Urban and IBRD / 89140 Strengthening and Capacity Post Consultant Open 132,000.00 0.00 Canceled 2020-06-29 2020-06-29 2020-08-17 2021-01-08 2020-09-07 2020-10-12 2021-04-10 Regional Planning Practices in Building Selection Uzbekistan (phase 1 - international) MSC-CKY/CS/2.3.1.2 / Advisory Services to Ministry Component 2: Institutional Individual of Construction on IBRD / 89140 Strengthening and Capacity Post Consultant Open 21,000.00 16,000.00 Signed 2020-06-29 2020-06-29 2020-08-17 2020-11-25 2020-09-07 2020-12-07 2020-10-12 2021-02-25 2021-04-10 modernization of Urban and Building Selection Regional Planning Practices in Uzbekistan (phase 1 - local) MSC-C/CS/1.1.1 / Consulting services for the development of detailed Component 1: Improvement design, bidding documents of Urban Services and IBRD / 89140 Post Direct Selection Direct 424,900.00 424,900.00 Signed 2020-08-05 2020-08-05 2020-08-05 2020-08-05 2020-08-05 2020-04-22 2021-10-05 and construction supervision Enhancement of Public Urban of the Chartak Eco-Trail for Spaces non-motorized mobility in the city of Chartak MSC-CKY/CS/2.1 / Consultant for Development of Detailed Designs and Bid documents, and Construction Component 2: Institutional Supervision for the IBRD / 89140 Strengthening and Capacity Post Direct Selection Direct 91,600.00 91,600.00 Signed 2020-03-26 2020-04-07 2020-04-05 2020-05-13 2020-06-09 2020-05-15 2020-12-06 Construction / Repair of Building Garage Premises in the cities of Chartak, Kagan and Yangiyul. MSC-CKY/CS/2.3.1.1.1 / Advisory Services to Ministry of Construction on Component 2: Institutional Individual Under modernization of Urban and IBRD / 89140 Strengthening and Capacity Post Consultant Open 132,000.00 0.00 2021-04-12 2021-04-14 2021-05-31 2021-06-21 2021-07-26 2022-01-22 Implementation Regional Planning Practices in Building Selection Uzbekistan (phase 1 - international) Page 3 COMOROS FINANCIAL SECTOR DEVELOPMENT PROJECT (P166193) PLAN DE PASSATION DE MARCHES I. Généralités 1. L'information sur le projet : Pays : UNION DES COMORES Projet : Projet de Développement du Secteur Financier des Comores Numero du crédit : PPA Agence d’exécution : Unité de gestion du Projet BCC 2. Date d’approbation du Plan de passation de marchés par la Banque [original : ......... ; Révision : ... ] 3. Date de notification de l’Avis Général de Passation de marchés : 4. Période couverte par le Plan de Passation de marchés : II-FOURNITURES, TRAVAUX et SERVICES DE NON-CONSULTANT 1. Seuil de Revue préalable : Les seuils requis pour les décisions de passation de marchés sujet aux revues préalables de la Banque sont indiqués par l’APS du pojet Méthode de Passation de Seuil de revue à Commentaires marchés priori Fournitures, Système d’information, et Services autres que les services de consultant 1. AOI >1.500.000$ M>500.000 2. AON Néant M<500.000 3. Cotation Néant M<100.000 4. UNOPS >1.500.000 Travaux 4. AOI >5,000,000 M>3,000,000 5. AON Néant M<3,000,000 6. Demande de dévis Néant M<200,000 7. Entente directe Même que AOI 2. Pré-qualification Les soumissionnaires pour _____________ seront pré- qualifiés selon les dispositions des paragraphes 2.9 et 2.10 des Directives. N/A 3. Procédures proposées pour les composantes CDD (selon le paragraphe. 3.17 des Directives : N/A 4. Référence (s’il y en a) au Manuel d’exécution du projet / Manuel de Passation de marchés : Manuel du projet ……………… à mettre à jour pour le besoin du PPA 5. Tout autre arrangement spécial en passation de marchés : Néant 6. Allotissement de fournitures avec méthodes et calendrier : 1 2 3 4 5 6 7 8 9 Pré- Préféren Revue de Date qualificatio ce la prévue Coût Méthode n nationale Banque Réf. d’ouvertur Commentair Description Contrat estimat de (à priori No e des es if (en $) sélection /à Oui / Non Oui / Non soumissio posterior ns i) F00 Achat de logiciels, 10 000 CF Non Non Post Decembre 1 2018 F00 IT équipement 10 000 CF Non Non Post Decembre 2 2018 F00 Mobilier 10 000 CF Non Non Post Decembre 3 2018 Total 30 000 B-SELECTION DE CONSULTANTS 1. Seuil de Revue Préalable : Décisions de sélection sujet à la revue préalable de la Banque comme indiqué dans l'Annexe 1 des Directives Sélection et Emploi de consultants : Méthode de sélection Seuil de revue à Commentaires priori 1. Toute méthode confondue pour une >500,000 firme 2. Entente directe pour une firme >500,000 3. Consultation individuelle >200,000 4. Entente directe pour un CI >200,000 2. Liste restreinte composée entièrement de consultants nationaux : Liste restreinte de consultants pour prestations de services, estimés à moins de $ 100 000 par contrat, peut comporter entièrement des consultants nationaux selon les dispositions du paragraphe 2.7 des directives de sélection de consultants. 3. Tout autre arrangement spécial de Sélection de consultants : [y compris passation de marchés anticipée et financement rétroactif, si applicable] : N/A 4. Tâches de consultation avec des méthodes de sélection et calendrier 1 2 3 4 5 6 7 Date prévue Revue de la Coût Méthode de Description des Banque (à Commentair Réf. No. estimatif de soumission missions priori / à es (en $) sélection des posteriori) propositions 1. Travaux de préparation de projet Elaboration du PPSD Post Novembre 45j pour G001 Atelier et consultant 50,000 SED 2018 finaliser Elaboration manuel de Post Novembre G002 procédures 75,000 SED 2018 Atelier+AT G003 Total 1125 000 2. Mise en place de l’Unité de Gestion du Projet G004 Coordonnateur, 25,000 SCI Post Novembre 2018 Spécialiste en SCI Post Novembre G005 passation de 12,000 2018 marchés, Spécialiste Gestion SCI Post Novembre G006 12,000 2018 Financière G007 Comptable, 8,000 SCI Post Novembre 2018 G008 Auditeur Externe 20,000 SCI Post Novembre 2018 Personnel 8,000 SCI Post Novembre G009 2018 Administratif. Spécialiste 15,000 SCI Post Novembre G010 environnemental et 2018 social, Spécialiste en Suivi 8,000 SCI Post Novembre G011 2018 Evaluation, G012 Auditeur Interne 15,000 SCI Post Novembre 2018 SOUS-TOTAL 2 123,000 3. Préparation à la mise en œuvre Mise à jour de Post l’environnement légal et G013 règlementaire 300,000 SQC/SCI 30 Octobre 2018 pour l’implémentation de la SNP Mise en place du Post Decembre G014 CNP 50,000 SCI 2018 Assistance sur la Post gouvernance de Novembre G003 100,000 SCI la SNPSF 2018 AT au SNPSF Mise en place de Post Decembre G015 100,000 SCI l’équipe projet au 2018 sein de la BCC pour la mise en œuvre de l’infrastructure financière G016 Sauvegarde 30,000 SCI Post Decembre 2018 G017 Voyages d’études NA Post Mars 2019 SOUS-TOTAL 3 580.000 TOTAL CONSULTANCE 848.000 4. Coûts opérationnel Revue de la Pré- Description Méthode de Banque Coût estimatif (en $) qualificat Date de Contrat sélection (à priori / à Commentair ion posteriori) e Frais de fonctionneme nt de l’UGP : Location de bureau entretien, Internet, Multiple annonces et 100,000 DC Non Post N/A publications, médias, frais bancaires, consommabl es, ateliers, communicati on. Total 100,000 Acronymes : AOI : Appel d’Offre International AON : Appel d’Offre National DC : Demande de Cotation SCBD : Sélection dans le cadre d’un budget déterminé SED : Sélection par entente directe SFQC : Sélection Fondée sur la Qualité et le Cout SMC : Sélection au « moindre coût» SQC : Sélection fondée sur les qualifications des consultants SCI : Consultant individuel PROCUREMENT Comoros : Comoros Financial Inclusion Project PLAN General Information Country: Comoros Bank’s Approval Date of the Original Procurement Plan: 2019-11-14 2021-06-02 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P166193 GPN Date: 2020-09-29 Project Name: Comoros Financial Inclusion Project Loan / Credit No: IDA / V2770, IDA / 67070, IDA / D6760 U Executing Agency(ies): nité de gesion du Projet BCC WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned KM-UGPBCC-179696-CW- Component 2: Project and RFQ / Travaux d'entretien et Request for Single Stage - One 2020-09- IDA / V2770 Payment Systems Post Limited 2,353.00 2,225.37 Completed 2020-06-27 2020-05-21 2020-08-25 2020-06-16 d'amenagement des toillettes Quotations Envelope 25 Management bureau UGP KM-UGPBCC-189612-CW- Component 1: Increasing RFQ / Petits travaux Request for Single Stage - One 2020-11- IDA / V2770 Access to and Usage of Post Limited 6,353.00 21,766.90 Signed 2020-09-03 2020-09-17 2020-10-09 2020-10-27 d'entretiens, aménagements Quotations Envelope 09 Financial Services et réhabilitations Request for KM-UGPBCC-235547-CW- Component 1: Increasing Quotations - Small Pending RFQ / Travaux d'entretien, Request for Single Stage - One 2021-09- IDA / D6760 Access to and Usage of Post Limited Works 32,220.00 0.00 Implementat 2021-06-01 2021-07-09 Aménagement salle serveur Quotations Envelope 07 Financial Services (Emergency) SPD - ion site secours Competitive GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KM-UGPBCC-146092-GO- Component 1: Increasing Request for Single Stage - One RFQ / ACHAT DE MATÉRIELS IDA / V2770 Access to and Usage of Post Limited 60,000.00 5,243.42 Completed 2019-11-30 2020-01-27 2020-01-25 2020-01-31 2020-07-23 2020-06-03 Quotations Envelope INFORMATIQUE POUR UGP Financial Services KM-UGPBCC-161733-GO- Component 2: Project and Request for Single Stage - One RFQ / Acquisition du logiciel IDA / V2770 Payment Systems Post Limited 25,000.00 5,208.00 Signed 2020-04-08 2020-03-31 2020-06-03 2020-06-09 2020-11-30 Quotations Envelope comptable Management KM-UGPBCC-145795-GO- Component 2: Project and Request for Single Stage - One RFQ / achat d'un véhicules IDA / V2770 Payment Systems Post Limited 35,000.00 31,849.21 Completed 2020-04-05 2020-03-30 2020-05-31 2020-04-30 2020-11-27 2020-06-08 Quotations Envelope pour le projet Management KM-UGPBCC-146100-GO- Component 2: Project and Request for Single Stage - One RFQ / achat mobilier de IDA / V2770 Payment Systems Post Limited 5,000.00 2,657.98 Signed 2020-05-20 2020-11-25 2020-07-15 2020-11-30 2020-09-13 Quotations Envelope bureau Management KM-UGPBCC-167462-GO- Component 2: Project and Request for RFQ / Acquisition des IDA / V2770 Payment Systems Post 32,000.00 10,769.26 Completed 2020-02-21 2020-04-06 2020-04-01 2020-05-06 2020-08-19 Quotations materiels informatiques Management KM-UGPBCC-179680-GO- RFQ / Acquisition de trois Component 2: Project and Request for Single Stage - One ordinateurs portable ( IDA / V2770 Payment Systems Post Limited 5,700.00 5,973.59 Completed 2020-07-02 2020-07-20 2020-07-28 2020-08-24 2020-08-11 2020-10-14 Quotations Envelope Comptable, Responsable de Management communication, SG BCC) KM-UGPBCC-189593-GO- Component 1: Increasing DIR / Acquisition des IDA / V2770 Access to and Usage of Post Direct Selection Direct 26,824.00 19,278.03 Signed 2020-09-04 2020-09-15 2020-09-09 2020-09-16 2020-09-22 2020-10-07 2020-10-22 matériels et équipements des Financial Services salles serveur KM-UGPBCC-187624-GO- Component 2: Project and RFQ / Acquisition d'une Request for Single Stage - One IDA / V2770 Payment Systems Post Limited 529.41 544.22 Completed 2020-04-22 2020-04-21 2020-05-18 2020-04-29 2020-05-25 2020-07-21 imprimante multifonction noir Quotations Envelope Management et blanc KM-UGPBCC-199778-GO- Component 1: Increasing DIR / Adoption d’un logiciel IDA / 67070 Access to and Usage of Post Direct Selection Direct 500,000.00 219,275.00 Signed 2020-10-26 2020-11-10 2020-10-31 2020-10-14 2020-12-21 2021-03-08 2021-06-19 de supervision bancaire pour Financial Services la surveillance prudentielle KM-UGPBCC-203928-GO- Component 2: Project and Request for Single Stage - One RFQ / Acquisition d'un IDA / V2770 Payment Systems Post Limited 35,000.00 33,687.64 Completed 2020-10-10 2020-10-09 2020-11-10 2020-11-12 2020-11-17 2020-11-30 Quotations Envelope véhicule 4X4 Management KM-UGPBCC-221526-GO- Component 1: Increasing Under RFB / Acquisition d'un Single Stage - One IDA / D6760 Access to and Usage of Prior Request for Bids Open - International 2,000,000.00 0.00 Implementati 2021-03-10 2021-03-19 2021-03-15 2021-03-25 2021-05-17 2021-07-15 2021-08-19 2022-08-14 Système d'information Envelope Financial Services on Bancaire KM-UGPBCC-235552-GO- RFQ / Acquisition, Component 1: Increasing Pending Request for Single Stage - One installations matériels et IDA / D6760 Access to and Usage of Post Limited 72,819.00 0.00 Implementati 2021-05-27 2021-07-05 2021-09-06 Quotations Envelope équipements salle serveur site Financial Services on secours NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 1 KM-UGPBCC-145411-NC- DIR / Communication / médias pour sensibilisation sur le projet. une plage pleine Component 2: Project and Under du Jeune Afrique sur le IDA / V2770 Payment Systems Post Direct Selection 13,200.00 0.00 Implementati 2019-11-13 2019-11-19 2019-11-13 2019-11-19 2019-11-26 l'inclusion financière et le Management on projet Banque Mondiale dans le cadre de la conférence des bailleurs. CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KM-UGPBCC-146105-CS- Component 2: Project and QCBS / recrutement d'un Quality And Cost- IDA / V2770 Payment Systems Post Open - International 20,000.00 0.00 Canceled 2019-11-20 2019-12-23 2019-11-25 2019-12-26 2019-12-19 2020-01-16 2020-02-15 2020-03-21 2020-04-25 2021-04-25 consultant en sauvegarde Based Selection Management environnementale et sociale KM-UGPBCC-199891-CS- QCBS / Recrutement d’un cabinet pour l’évaluation de la Component 1: Increasing Quality And Cost- situation patrimoniale de la IDA / 67070 Access to and Usage of Post Open - International 80,000.00 0.00 Canceled 2020-10-22 2020-11-05 2020-11-05 2020-12-02 2020-11-26 2020-11-18 2020-12-28 2021-01-11 2021-02-08 2021-02-24 2021-03-26 Based Selection SNPSF en vue de la scission de Financial Services ses activités bancaires et postales KM-UGPBCC-221745-CS- Component 2: Project and QCBS / Recrutement d’un Quality And Cost- IDA / D6760 Payment Systems Post Open - International 5,678.00 0.00 Under Review 2020-08-10 2020-08-10 2020-08-24 2020-09-14 2020-10-14 2020-11-04 2020-12-09 2021-01-06 2022-01-06 cabinet pour l'audit interne du Based Selection Management projet KM-UGPBCC-235682-CS- QCBS / Recrutement d’un Component 1: Increasing consultant pour la conception Quality And Cost- Pending IDA / D6760 Access to and Usage of Post Open - International 100,000.00 0.00 2021-07-05 2021-07-19 2021-08-16 2021-09-15 2021-09-22 2021-10-13 2021-10-18 2022-10-18 et mise en œuvre d’un Based Selection Implementation Financial Services programme d’éducation financière INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KM-UGPBCC-146115-CS- Component 2: Project and Individual INDV / Coordonnateur de IDA / V2770 Payment Systems Post Consultant Open 25,000.00 7,224.02 Completed 2019-11-19 2020-03-27 2019-11-19 2019-12-16 2019-11-25 2019-12-18 2019-12-02 2020-02-03 2020-12-01 2020-05-31 Projet Management Selection KM-UGPBCC-146116-CS- Component 2: Project and Individual INDV / recrutement du IDA / V2770 Payment Systems Post Consultant Open 18,000.00 4,612.63 Signed 2019-11-19 2019-11-21 2019-11-19 2019-12-16 2019-11-25 2019-12-18 2019-12-02 2020-02-10 2020-12-01 Responsable Passation Marché Management Selection KM-UGPBCC-146127-CS- Component 2: Project and Individual INDV / recrutement du IDA / V2770 Payment Systems Post Consultant Open 18,000.00 0.00 Canceled 2019-11-19 2020-02-25 2019-11-20 2019-12-16 2019-11-25 2019-12-18 2019-12-02 2020-12-01 Responsable Administratif et Management Selection Financier KM-UGPBCC-154512-CS- Component 1: Increasing CDS / Recrutement d'un IDA / V2770 Access to and Usage of Post Direct Selection Direct 40,000.00 29,374.47 Signed 2020-01-20 2020-01-23 2020-01-30 2020-01-30 2020-03-01 2020-02-10 2020-08-28 consultant en sauvegarde Financial Services environnementale et sociale KM-UGPBCC-161714-CS- Component 2: Project and Individual INDV / Recrutement du IDA / V2770 Payment Systems Post Consultant Open 2,895.00 2,800.18 Signed 2020-04-06 2020-03-27 2020-05-25 2020-05-04 2020-06-08 2020-06-01 2020-06-29 2020-06-03 2020-07-09 comptable du projet Management Selection KM-UGPBCC-165220-CS- CDS / Recrutement d'un consultant chargé de faire l'élaboration d'un cahier de Component 1: Increasing charge pour l'acquisition du IDA / V2770 Access to and Usage of Post Direct Selection Direct 65,000.00 61,750.00 Signed 2020-04-13 2020-03-27 2020-04-25 2020-04-06 2020-06-29 2020-04-30 2020-09-27 Système d'Information Financial Services Bancaire et de la mise place d'un SIB et le réseau intezrbancaire KM-UGPBCC-146112-CS- CDS / Préparation du PPSD (plan et stratégie de passation Component 2: Project and du marché) et Plan de IDA / V2770 Payment Systems Post Direct Selection Direct 15,000.00 3,368.10 Signed 2020-03-30 2020-05-13 2020-04-09 2020-05-14 2020-06-07 2020-05-15 2020-07-07 passation des marchés (18 Management premiers mois) et atelier consultant KM-UGPBCC-146107-CS- Component 1: Increasing Individual INDV / elaboration du manuel IDA / V2770 Access to and Usage of Post Consultant Open 20,000.00 0.00 Canceled 2019-11-30 2019-12-17 2020-01-18 2020-02-08 2020-03-14 2020-09-10 de procédure Financial Services Selection KM-UGPBCC-161723-CS- Component 2: Project and Individual INDV / Recrutement d'un IDA / V2770 Payment Systems Post Consultant Open 2,475.00 0.00 Canceled 2020-04-06 2020-03-31 2020-05-02 2020-05-07 2020-05-26 2020-07-25 assitant de direction Management Selection KM-UGPBCC-168875-CS- CDS / Recrutement d'un bureau en charge d’assister la Banque Centrale des Comores Component 1: Increasing (BCC) dans l’acquisition d’une IDA / V2770 Access to and Usage of Post Direct Selection Direct 130,000.00 100,000.00 Signed 2020-04-22 2020-04-23 2020-04-27 2020-04-23 2020-06-01 2020-05-27 2020-07-31 connectivité réseau pour le Financial Services Système National des Paiements et d’un Système Bancaire de Base pour la BCC KM-UGPBCC-179292-CS- INDV / Responsable chargé de Component 2: Project and Individual la communication, et de IDA / V2770 Payment Systems Post Consultant Open 4,940.17 3,386.26 Signed 2020-06-19 2020-06-29 2020-07-15 2020-08-24 2020-07-20 2020-08-26 2020-08-03 2020-09-04 2020-10-31 sauvegardes Management Selection Environnementale et Sociale. Page 2 KM-UGPBCC-165323-CS- Component 2: Project and Individual QCBS / Elaboration du manuel IDA / V2770 Payment Systems Post Consultant Open 20,000.00 0.00 Canceled 2020-04-10 2020-04-23 2020-05-13 2020-05-27 2020-06-10 2020-07-27 de procédure Administratif, Management Selection comptable et Financier KM-UGPBCC-187621-CS- Component 2: Project and CDS / Recrutement du IDA / V2770 Payment Systems Post Direct Selection Direct 6,176.50 7,557.61 Signed 2020-06-04 2020-06-04 2020-06-06 2020-06-08 2020-06-15 2020-06-15 2020-08-29 Coordonnateur National Management remplaçant KM-UGPBCC-189616-CS- Component 2: Project and Individual INDV / Recrutement de IDA / V2770 Payment Systems Post Consultant Open 2,475.00 2,128.95 Signed 2020-08-31 2020-09-09 2020-09-21 2020-11-13 2020-09-25 2020-11-16 2020-10-12 2020-12-01 2020-10-31 l'assistant de direction Management Selection KM-UGPBCC-189619-CS- Component 2: Project and Individual INDV / Recrutement du IDA / V2770 Payment Systems Post Consultant Limited 1,765.00 1,109.75 Signed 2020-08-28 2020-09-09 2020-08-29 2020-12-18 2020-08-31 2020-12-21 2020-09-04 2020-12-22 2020-11-03 Chauffeur / planton Management Selection KM-UGPBCC-203924-CS- Component 2: Project and CDS / Recrutemnt d'un IDA / V2770 Payment Systems Post Direct Selection Direct 15,000.00 0.00 Canceled 2020-11-13 2020-11-19 2020-11-23 2020-12-07 2020-12-18 consultant pour la mise à Management jour du PPSD KM-UGPBCC-203929-CS- Component 2: Project and Individual INDV / Recrutement du IDA / V2770 Payment Systems Post Consultant Open 18,000.00 5,174.57 Signed 2018-10-22 2018-10-23 2018-12-01 2019-12-23 2018-12-08 2019-12-27 2019-01-12 2020-02-03 2019-04-12 Responsable Administratif et Management Selection financier du projet KM-UGPBCC-211064-CS- INDV / Recrutement d'un Component 1: Increasing Individual consultant pour assister la IDA / V2770 Access to and Usage of Post Consultant Limited 1,765.00 2,484.51 Signed 2020-12-28 2021-02-15 2020-12-29 2020-09-25 2021-01-05 2021-02-22 2021-01-09 2021-02-22 2021-01-19 BCC à la réception des travaux Financial Services Selection de réhabilitation de salle serveur KM-UGPBCC-218994-CS- CDS / Recrutement d’un cabinet pour l’évaluation de la Component 1: Increasing situation patrimoniale de la IDA / D6760 Access to and Usage of Post Direct Selection Direct 80,000.00 269,752.50 Signed 2021-01-22 2021-02-17 2021-01-24 2021-01-22 2021-03-03 2021-03-18 2021-04-02 SNPSF en vue de la scission de Financial Services ses activités bancaires et postales KM-UGPBCC-189624-CS-LCS Component 2: Project and Individual / Recrutement de l'auditeur IDA / V2770 Payment Systems Post Consultant Open 5,212.00 0.00 Canceled 2020-10-15 2020-11-24 2020-12-08 2020-12-29 2021-06-27 interne Management Selection KM-UGPBCC-225953-CS- Component 1: Increasing CDS / Recrutement d'un IDA / D6760 Access to and Usage of Post Direct Selection Direct 35,000.00 40,000.00 Signed 2021-03-29 2021-03-24 2021-04-09 2021-03-26 2021-05-31 2021-04-20 2021-07-30 conseiller en resolution Financial Services bancaire KM-UGPBCC-222252-CS- Component 1: Increasing Individual INDV / Recrutement d'un IDA / D6760 Access to and Usage of Post Consultant Open 200,000.00 0.00 Canceled 2021-03-05 2021-03-09 2021-03-31 2021-04-14 2021-04-23 2022-04-22 consiller résident pour la Financial Services Selection DSBR KM-UGPBCC-210576-CS- Component 1: Increasing Individual INDV / Elaboration d'un APS et IDA / V2770 Access to and Usage of Post Consultant Limited 35,294.00 0.00 Canceled 2020-12-24 2020-12-25 2021-01-01 2021-01-08 2021-02-10 APD pour la contruction d'un Financial Services Selection site secours serveur KM-UGPBCC-189584-CS- INDV / Recrutement d'un Component 1: Increasing Individual conseiller permanent auprés IDA / V2770 Access to and Usage of Post Consultant Open 150,000.00 0.00 Canceled 2020-09-07 2020-09-15 2020-10-02 2020-10-26 2020-10-09 2020-10-22 2020-11-21 de la Direction de la Financial Services Selection Surveillance des BEF et de la Règlementation (DSBR) KM-UGPBCC-235681-CS- Component 1: Increasing Individual Pending INDV / Etudes et prestations IDA / D6760 Access to and Usage of Post Consultant Open 7,049.00 0.00 2021-05-31 2021-06-26 2021-07-09 2021-07-14 2021-09-14 Implementation de services/ site secours Financial Services Selection KM-UGPBCC-235687-CS- INDV / Consultant pour appui Component 1: Increasing Individual à l’acquisition du logiciel CBS, Pending IDA / D6760 Access to and Usage of Post Consultant Limited 30,000.00 0.00 2021-05-26 2021-05-27 2021-05-31 2021-06-03 2021-08-03 matériels et autres Implementation Financial Services Selection équipements (évaluation, livraison, installation…etc. ;) KM-UGPBCC-235678-CS- CDS / Consultant pour appui à l’élaboration des Component 1: Increasing Under spécifications techniques IDA / D6760 Access to and Usage of Post Direct Selection Direct 130,000.00 0.00 2021-06-10 2021-06-10 2021-06-13 2021-07-08 2022-01-04 Implementation SAT+ et Soutien à l’équipe Financial Services projet de la BCC pour l’implémentation du CBS KM-UGPBCC-235679-CS- Component 1: Increasing CDS / Dotation et soutien à la Pending IDA / D6760 Access to and Usage of Post Direct Selection Direct 29,809.00 0.00 2021-06-21 2021-07-01 2021-08-09 2022-04-06 maintenance de salle serveur Implementation Financial Services et site secours Page 3 Procurement Plan Governance and Policy Project for Federally Administered Tribal Areas (P156412) I. General 1. Bank’s approval Date of the procurement Plan Original: June 2,2016: Revision 3 of Updated Procurement Plan, February 5,2017 2. Date of General Procurement Notice: June 2016 3. Period covered by this procurement plan: The procurement period of project covered, 24 months II. Goods and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Expenditure Contract Value Procurement Contracts Subject to Category (Threshold) Method Prior Review US $ US$ thousand 1.Civil Works Not applicable 2. Goods >600,000 ICB First contract by all entities <600,000 NCB First contract by all entities <100,000 Shopping First contract by all entities Regardless of value Direct Contracting All 2. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan Project XYZ 04/01/2010 issued by 3. Summary of the Procurement Packages planned during the first 18 months after project effectiveness ( including those that are subject to retroactive financing and advanced procurement) July 9, 2010 [List the Packages which require Bank’s prior review first and then the other packages] 1 2 3 4 5 6 7 Ref. Descripti Estimat Packages Dome Review Comme No. on ed stic by Bank nts Cost Prefe (Prior / US$ rence Post) million (yes/ no) Summary 0.2 2 No Post 1st of the NCB contrac (Goods) t for Prior Review III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: 3. Consulting All ToRs and training Services programs to be reviewed by the World Bank’s task team leader (A) Firms >500,000 QCBS, QBS,FBS,LCS, First contract by any process <500,000 CQS, First CQS contract Regardless of value SSS All (B) Individual Up to 200,000 Under Section V (i) First contract Consultants and; (ii) Procurement Specialist regardless of value >200,000 Under Section V All Regardless of value SSS First > 15,000 SSS All July 9, 2010 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_500,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description Estimat Package Review Comment of ed s by Bank s Assignmen Cost (Prior / t US$ Post) million Summary 8.5 5 1 Prior/ of number 4 Post of contracts that will be let under QCBS Summary 0.5 1 Prior CQS of number of contracts that will be let under other methods July 9, 2010 PROCUREMENT Pakistan : Federally Administered Tribal Areas (FATA) Governance and Policy Program PLAN General Information Country: Pakistan Bank’s Approval Date of the Original Procurement Plan: 2017-03-16 2021-05-21 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P156412 GPN Date: Project Name: Federally Administered Tribal Areas (FATA) Governance and Policy Program Loan / Credit No: TF / A3301 FATA Governance and Policy Program Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-GPP FATA-10515-GO- Improving public investment RFQ / Procurement of Request for Single Stage - One TF / A3301 management and service Prior Open - National 86,338.00 0.00 Canceled 2017-04-11 2017-06-11 2017-12-08 Motorbikes for Independent Quotations Envelope delivery Monitoring Unit (IMU) PK-GPP FATA-110773-GO- Improving public investment RFQ / Purchase of Solar UPS Request for Single Stage - One TF / A3301 management and service Post Open - National 8,255.00 6,732.79 Completed 2019-05-06 2019-07-01 2019-09-11 2019-12-28 2019-10-02 for extension of RTPS to Quotations Envelope delivery merged areas PK-GPP FATA-110772-GO- Improving public investment RFQ / Procurement of IT Request for Single Stage - One TF / A3301 management and service Post Open - National 7,547.00 8,199.58 Completed 2019-05-05 2019-06-30 2019-09-06 2019-12-27 2019-09-13 Equipment for extension of Quotations Envelope delivery RTPS to merged areas PK-GPP FATA-110769-GO- RFQ / Procurement of Improving public investment Request for Single Stage - One Furniture & Fixture for TF / A3301 management and service Post Open - National 9,852.00 4,245.87 Completed 2019-05-04 2019-06-29 2019-09-06 2019-12-26 2019-09-27 Quotations Envelope extension of RTPS to merged delivery areas PK-GPP FATA-117396-GO- Improving public investment RFQ / Procurement of Five Request for Single Stage - One TF / A3301 management and service Post Open - National 5,800.00 6,011.42 Completed 2019-06-25 2019-08-25 2019-09-11 2020-02-21 2019-09-18 (05) Laptops for P&D Quotations Envelope delivery Department, MAs PK-GPP FATA-121999-GO- RFQ / Purchase of Licenses for Antivirus (60 Users), Improving public investment Pending Integrated Development Request for Single Stage - One TF / A3301 management and service Post Open - National 26,500.00 0.00 Implementati 2019-08-27 2019-10-22 2020-04-19 Environment (IDE) and Google Quotations Envelope delivery on API for GIS Portal for Geo Tagging of Infrastructure Assets PK-GPP FATA-122009-GO- RFQ / Purchase of 2 Nos 360 Improving public investment Pending Request for Single Stage - One Degree Cameras for Geo TF / A3301 management and service Post Open - National 2,500.00 0.00 Implementati 2019-09-03 2019-10-29 2020-04-26 Quotations Envelope Tagging of Infrastructure delivery on Asset PK-GPP FATA-122014-GO- Improving public investment Pending RFQ / Purchase of 9 GPS Request for Single Stage - One TF / A3301 management and service Post Open - National 1,969.00 0.00 Implementati 2019-09-03 2019-10-29 2020-04-26 Devices for Geo Tagging of Quotations Envelope delivery on Infrastructure Asset PK-GPP FATA-126049-GO- RFP / Purchase of 40 Desktop Computers, 08 Heavy Duty Photocopier (All in One), 08 Improving transparency and Laser Fax Machines, 40 Laser Request for Single Stage - One TF / A3301 accountability in the use of Post Open - National 83,125.00 80,145.65 Completed 2019-08-28 2019-10-23 2019-11-05 2020-03-19 2019-11-26 Printers, 08 Scanners with Quotations Envelope public resources ADF and 36 UPS for Desktop PCs under Support to Finance Department for extending IFMIS to Merged Areas PK-GPP FATA-122004-GO- RFQ / Purchase and Improving public investment Pending Installation of 10 Security Request for Single Stage - One TF / A3301 management and service Post Open - National 1,250.00 0.00 Implementati 2019-09-03 2019-10-29 2020-04-26 Cameras for GIS Hub under Quotations Envelope delivery on Geo Tagging of Infrastructure Assets PK-GPP FATA-191897-GO- RFQ / Purchase of IT Improving public investment Request for Single Stage - One Equipment & Peripherals for TF / A3301 management and service Post Open - National 24,458.00 0.00 Canceled 2020-09-13 2020-11-08 2021-05-07 Quotations Envelope P&D Department, Khyber delivery Pakhtunkhwa PK-GPP FATA-197571-GO- Improving transparency and Pending RFQ / Procurement of Five Request for Single Stage - One TF / A3301 accountability in the use of Post Open - National 24,458.00 0.00 Implementati 2020-10-13 2020-12-08 2021-06-06 Desktops for P&D department Quotations Envelope public resources on KPK PK-GPP FATA-206953-GO- RFQ / Purchase of Furniture Improving transparency and Pending Request for Single Stage - One for Finance Department for TF / A3301 accountability in the use of Post Open - National 10,750.00 0.00 Implementati 2020-12-09 2021-02-03 2021-08-02 Quotations Envelope extension of NFIMS to Merged public resources on Areas. PK-GPP FATA-206955-GO- RFQ / Purchase of 8 Air Improving transparency and Pending Request for Single Stage - One conditioners for District F&P TF / A3301 accountability in the use of Post Open - National 4,250.00 0.00 Implementati 2020-12-09 2021-02-03 2021-08-02 Quotations Envelope Offices under NFMIS Concept public resources on Note Page 1 Ensuring effective support for PK-GPP FATA-214741-GO- the coordination of Pending RFQ / Purchase of Desktops Request for Single Stage - One TF / A3301 governance reforms and the Post Open - National 14,000.00 0.00 Implementati 2021-02-02 2021-03-30 2021-09-26 and Printers for Right to Quotations Envelope operational management of on Information Commission the GPP Ensuring effective support for PK-GPP FATA-214754-GO- the coordination of Pending RFQ / Purchase of Photo Request for Single Stage - One TF / A3301 governance reforms and the Post Open - National 10,000.00 0.00 Implementati 2021-02-02 2021-03-30 2021-09-26 Copiers for Right to Quotations Envelope operational management of on Information Commission. the GPP Ensuring effective support for PK-GPP FATA-214763-GO- the coordination of Pending RFQ / Purchase of Water Request for Single Stage - One TF / A3301 governance reforms and the Post Open - National 1,150.00 0.00 Implementati 2021-02-02 2021-03-30 2021-09-26 Dispenser for Right to Quotations Envelope operational management of on Information Commission. the GPP Ensuring effective support for PK-GPP FATA-214768-GO- the coordination of Pending RFQ / Purchase of UPS/Solar Request for Single Stage - One TF / A3301 governance reforms and the Post Open - National 5,700.00 0.00 Implementati 2021-02-03 2021-03-31 2021-09-27 System for Right to Quotations Envelope operational management of on Information Commission. the GPP Ensuring effective support for PK-GPP FATA-214776-GO- the coordination of Pending RFQ / Purchase of Furnitures Request for Single Stage - One TF / A3301 governance reforms and the Post Open - National 9,400.00 0.00 Implementati 2021-02-03 2021-03-31 2021-09-27 for Right to Information Quotations Envelope operational management of on Commission. the GPP PK-GPP FATA-214832-GO- Ensuring effective support for RFQ / Printing and Publication the coordination of Pending Request for Single Stage - One of Brochures, Pamphlets, TF / A3301 governance reforms and the Post Open - National 12,500.00 0.00 Implementati 2021-02-02 2021-03-30 2021-09-26 Quotations Envelope Reports and Manuals for Right operational management of on to Services Commission. the GPP PK-GPP FATA-217761-GO- RFQ / Improving public investment Pending Establishment/Renovation of Request for Single Stage - One TF / A3301 management and service Post Open - National 7,500.00 0.00 Implementati 2021-02-23 2021-04-20 2021-10-17 3 Nos of divisional offices for Quotations Envelope delivery on Right to Information Commission. PK-GPP FATA-224695-GO- Improving public investment Pending RFQ / Procurement of Video Request for Single Stage - One TF / A3301 management and service Post Open - National 17,500.00 0.00 Implementati 2021-03-31 2021-05-26 2021-11-22 Conference system for Right Quotations Envelope delivery on To Services. PK-GPP FATA-121996-GO- RFB / Purchase of 34 Laptops, 34 Desktop Computers, 24 Improving public investment Single Stage - One Printers and 2 Servers for GEO TF / A3301 management and service Post Request for Bids Open - National 114,813.00 0.00 Canceled 2020-04-20 2020-04-22 2020-06-03 2020-07-03 2020-08-07 2021-02-03 Envelope Tagging of Infrastructure delivery Assets and 08 Laptops for OSU GPP, Merged Areas PK-GPP FATA-226171-GO- RFQ / Purchase of 34 Laptops, Improving public investment Pending 34 Desktop Computers, for Request for Single Stage - One TF / A3301 management and service Post Open - National 94,700.00 0.00 Implementati 2021-04-11 2021-06-06 2021-12-03 GEO Tagging of Infrastructure Quotations Envelope delivery on Assets and 08 Laptops for OSU GPP, Merged Areas PK-GPP FATA-224744-GO- RFQ / Procurement of Improving transparency and Request for Single Stage - One Furniture for Integrated TF / A3301 accountability in the use of Post Open - National 33,515.00 0.00 Canceled 2021-04-03 2021-05-29 2021-11-25 Quotations Envelope Financial Management public resources Information System (FMIS). PK-GPP FATA-222285-GO- RFQ / Procurement of Improving transparency and Request for Single Stage - One Furniture for Capacity Building TF / A3301 accountability in the use of Post Open - National 9,200.00 0.00 Canceled 2021-04-10 2021-06-05 2021-12-02 Quotations Envelope o Drawing & Disbursement public resources Officers(DDOs). PK-GPP FATA-226443-GO- Improving transparency and Pending RFQ / Procurement of Request for Single Stage - One TF / A3301 accountability in the use of Post Open - National 42,715.00 0.00 Implementati 2021-04-05 2021-05-31 2021-11-27 Furniture under the CNs of Quotations Envelope public resources on FMIS and DDO’s training. Improving public investment Pending PK-GPP FATA-228084-GO- Request for Single Stage - One TF / A3301 management and service Post Open - National 21,000.00 0.00 Implementati 2021-04-30 2021-06-25 2021-12-22 RFQ / Purchase of 21 Laptops. Quotations Envelope delivery on Improving public investment Pending PK-GPP FATA-228422-GO- Request for Single Stage - One TF / A3301 management and service Post Open - National 1,875.00 0.00 Implementati 2021-05-08 2021-07-03 2021-12-30 RFQ / Purchase of Stationery. Quotations Envelope delivery on PK-GPP FATA-228421-GO- Improving public investment Pending Request for Single Stage - One RFQ / Printing & Publication of TF / A3301 management and service Post Open - National 3,125.00 0.00 Implementati 2021-05-08 2021-07-03 2021-12-30 Quotations Envelope Publicity Material. delivery on PK-GPP FATA-231458-GO- Improving public investment Pending Request for Single Stage - One RFQ / Purchase of 14 Printers, TF / A3301 management and service Post Open - National 6,157.00 0.00 Implementati 2021-05-01 2021-06-26 2021-12-23 Quotations Envelope 8 WiFi Routers and 7 Scanners delivery on Improving public investment Pending PK-GPP FATA-226178-GO- Request for Single Stage - One TF / A3301 management and service Post Open - National 17,500.00 0.00 Implementati 2021-04-13 2021-06-08 2021-12-05 RFQ / 2 No. of Servers Quotations Envelope delivery on Improving public investment Pending PK-GPP FATA-226174-GO- Request for Single Stage - One TF / A3301 management and service Post Open - National 12,000.00 0.00 Implementati 2021-05-29 2021-07-24 2022-01-20 RFQ / Purchase of 24 Printers Quotations Envelope delivery on PK-GPP FATA-235688-GO- Improving public investment Pending Request for Single Stage - One RFQ / Purchase of Furniture TF / A3301 management and service Post Open - National 60,114.00 0.00 Implementati 2021-06-09 2021-08-04 2022-01-31 Quotations Envelope for 34 District Offices delivery on PK-GPP FATA-235693-GO- Improving public investment Pending Request for Single Stage - One RFQ / Purchase of Office TF / A3301 management and service Post Open - National 37,921.00 0.00 Implementati 2021-06-12 2021-08-07 2022-02-03 Quotations Envelope Equipment for 34 Offices delivery on Page 2 PK-GPP FATA-238205-GO- Improving public investment Pending Request for Single Stage - One RFQ / Purchase of Laptop and TF / A3301 management and service Post Open - National 26,000.00 0.00 Implementati 2021-06-12 2021-08-07 2022-02-03 Quotations Envelope IT Peripherals delivery on PK-GPP FATA-238209-GO- Improving public investment Pending Request for Single Stage - One RFQ / Purchas of Server TF / A3301 management and service Post Open - National 27,860.00 0.00 Implementati 2021-06-12 2021-08-07 2022-02-03 Quotations Envelope Machines and Firewall delivery on NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-GPP FATA-110777-NC- RFQ / Printing, Pusblication Improving public investment Pending Request for Single Stage - One and Promotional material for TF / A3301 management and service Post Open - National 9,434.00 0.00 Implementati 2019-06-30 2019-08-25 2020-02-21 Quotations Envelope Extension of RTPS to merged delivery on areas PK-GPP FATA-110778-NC- Improving public investment Pending RFQ / Citizen Perception Request for Single Stage - One TF / A3301 management and service Post Open - National 9,434.00 0.00 Implementati 2020-05-05 2020-06-30 2020-12-27 Survey for extension of RTPS Quotations Envelope delivery on to merged areas CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-GPP FATA-5476-CS-QCBS Improving public investment / Hiring of Firm for Enhancing Quality And Cost- TF / A3301 management and service Post Open - International 1,500,000.00 0.00 Canceled 2017-03-30 2017-04-14 2017-05-06 2017-06-05 2017-06-20 2017-07-10 2017-07-27 2018-07-27 Citizen Engagement using ICT Based Selection delivery Tools PK-GPP FATA-10503-CS- Improving public investment Consultant CQS / Hiring of Firm for TF / A3301 management and service Post Qualification Open - National 500,000.00 0.00 Canceled 2017-03-30 2017-03-30 2017-04-14 2017-04-27 2017-05-29 2017-06-13 2017-07-03 2018-07-03 Strengthening Regulatory delivery Selection Regime of Public Procurement PK-GPP FATA-10504-CS- Improving public investment Consultant CQS / Hiring of Firm for TF / A3301 management and service Post Qualification Open - National 500,000.00 0.00 Canceled 2018-07-01 2018-07-16 2018-08-30 2018-09-14 2018-10-04 2019-10-04 Strengthening Procurement delivery Selection MIS PK-GPP FATA-5475-CS-QCBS Improving public investment / Hiring of Firm for Public Quality And Cost- TF / A3301 management and service Prior Open - International 3,000,000.00 0.00 Canceled 2017-03-30 2017-12-21 2017-04-14 2018-06-29 2017-05-24 2017-06-08 2017-06-18 2017-07-08 2017-08-08 2018-08-08 Investment Management Based Selection delivery Reforms PK-GPP FATA-5468-CS-QCBS Improving transparency and Quality And Cost- / Hiring of Firm for PFM TF / A3301 accountability in the use of Prior Open - International 3,000,000.00 0.00 Canceled 2017-03-30 2017-06-23 2017-04-14 2018-06-14 2017-05-14 2017-06-13 2017-06-28 2017-07-23 2017-08-12 2018-08-12 Based Selection Strengthening public resources PK-GPP FATA-14346-CS-LCS Improving transparency and / Hiring of Firm for provision Least Cost TF / A3301 accountability in the use of Prior Open - National 1,100,000.00 0.00 Canceled 2017-06-01 2017-05-15 2017-06-19 2017-05-16 2017-07-18 2017-08-22 2017-09-06 2017-10-05 2017-10-27 2020-07-05 of Technical Support on IDC Selection public resources basis PK-GPP FATA-7411-CS-CQS Improving public investment Consultant / Establishment of TF / A3301 management and service Post Qualification Open - National 450,000.00 0.00 Canceled 2017-03-30 2017-03-31 2017-04-14 2017-04-27 2017-05-09 2017-05-24 2017-06-13 2017-12-30 Independent Monitoring Unit delivery Selection in FATA Secretariat PK-GPP FATA-224692-CS- LCS / Hiring of FIRM for Improving public investment Consultant Pending proactive disclosure of data TF / A3301 management and service Post Qualification Open - National 31,250.00 0.00 2021-04-02 2021-04-23 2021-05-13 2021-05-20 2021-05-31 2021-08-14 Implementation under Right to Information delivery Selection Commission. INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-GPP FATA-10508-CS- Improving public investment CDS / Hiring of Firm for PFM TF / A3301 management and service Prior Direct Selection Direct 500,000.00 0.00 Canceled 2017-03-25 2017-03-27 2017-04-04 2017-04-03 2017-06-08 2018-06-08 Certification Program delivery PK-GPP FATA-22289-CS- Improving public investment Individual INDV / Hiring of Reforms TF / A3301 management and service Post Consultant Open 171,000.00 36,089.16 Terminated 2017-07-31 2017-08-09 2017-09-03 2017-08-09 2017-09-18 2017-10-13 2017-08-15 2020-06-24 Advisor delivery Selection Ensuring effective support for the coordination of Individual PK-GPP FATA-31397-CS- TF / A3301 governance reforms and the Prior Consultant Open 152,000.00 0.00 Canceled 2017-10-12 2017-11-28 2017-12-01 2018-08-27 2017-12-22 2018-01-20 2020-06-30 INDV / Coordinator OSU operational management of Selection the GPP Ensuring effective support for PK-GPP FATA-31399-CS- the coordination of Individual INDV / Financial Management TF / A3301 governance reforms and the Prior Consultant Open 121,500.00 0.00 Canceled 2017-10-13 2017-11-28 2017-12-02 2017-12-23 2018-08-01 2018-01-21 2020-06-30 Specialist OSU operational management of Selection the GPP PK-GPP FATA-31400-CS- Improving transparency and Individual INDV / Procurement Officer TF / A3301 accountability in the use of Post Consultant Open 30,500.00 0.00 Canceled 2017-10-12 2017-12-01 2017-12-22 2018-01-20 2020-06-30 Component 1 public resources Selection PK-GPP FATA-31401-CS- Improving transparency and Individual INDV / Finance Officer TF / A3301 accountability in the use of Post Consultant Open 30,500.00 0.00 Canceled 2017-10-12 2017-12-01 2017-12-22 2018-01-20 2020-06-30 Component 1 public resources Selection Page 3 PK-GPP FATA-31404-CS- Improving public investment Individual INDV / Procurement Officer TF / A3301 management and service Post Consultant Open 30,500.00 0.00 Canceled 2017-10-12 2017-12-01 2017-12-22 2018-01-20 2020-06-30 Component 2 delivery Selection PK-GPP FATA-31406-CS- Improving public investment Individual INDV / Finance Officer TF / A3301 management and service Post Consultant Open 30,500.00 0.00 Canceled 2017-10-12 2017-12-01 2017-12-22 2018-01-20 2020-06-30 Component 2 delivery Selection Ensuring effective support for PK-GPP FATA-34021-CS- the coordination of Individual INDV / Procurement Specialist TF / A3301 governance reforms and the Prior Consultant Open 107,000.00 0.00 Canceled 2017-12-22 2018-01-24 2018-01-27 2018-02-05 2020-08-26 for OSU operational management of Selection the GPP Ensuring effective support for PK-GPP FATA-71817-CS- the coordination of Individual INDV / Coordinator OSU - TF / A3301 governance reforms and the Post Consultant Open 152,000.00 36,133.68 Terminated 2018-07-27 2018-02-09 2018-09-15 2018-08-27 2018-10-06 2018-09-03 2018-11-04 2018-09-05 2021-04-14 Post Review operational management of Selection the GPP PK-GPP FATA-126047-CS- Improving public investment Individual INDV / Hiring of GIS Analyst TF / A3301 management and service Post Consultant Open 43,875.00 0.00 Canceled 2019-08-22 2020-05-24 2020-05-27 2020-06-05 2021-06-04 for GEO Tagging of Public delivery Selection Infrastructure PK-GPP FATA-216081-CS- INDV / Hiring of Expert/ Improving public investment Individual Analyst for Appraisal of Pending TF / A3301 management and service Post Consultant Open 7,500.00 0.00 2021-01-28 2021-03-18 2021-04-08 2021-05-13 2021-11-09 Merged Areas ADP Schemes Implementation delivery Selection /PC-I under M&E Concept Note PK-GPP FATA-224750-CS- Improving public investment Individual INDV / Hiring of Consultant Pending TF / A3301 management and service Post Consultant Limited 2,500.00 0.00 2021-03-22 2021-03-27 2021-04-17 2021-05-22 2021-11-18 to developed and integrate Implementation delivery Selection appraisal module in to DPMIS. PK-GPP FATA-224736-CS- INDV / Hiring of Individual Improving transparency and Individual Pending Consultant for IFMIS/SAP TF / A3301 accountability in the use of Post Consultant Limited 30,000.00 0.00 2021-03-22 2021-03-27 2021-04-17 2021-05-22 2022-05-22 Implementation Human Capital Management public resources Selection (HCM). PK-GPP FATA-227733-CS- INDV / Hiring of Focal Person Improving public investment Individual Pending Complaints for Right To TF / A3301 management and service Post Consultant Open 6,000.00 0.00 2021-04-05 2021-05-24 2021-06-14 2021-07-19 2022-01-15 Implementation Information (RTI) Commission delivery Selection at Divisional Office Peshawar PK-GPP FATA-227737-CS- INDV / Hiring of Focal Person Improving public investment Individual Pending Complaints for Right To TF / A3301 management and service Post Consultant Open 6,000.00 0.00 2021-04-05 2021-05-24 2021-06-14 2021-07-19 2022-01-15 Implementation Information (RTI) Commission delivery Selection at Divisional Office Bannu PK-GPP FATA-227738-CS- INDV / Hiring of Focal Person Improving public investment Individual Pending Complaints for Right To TF / A3301 management and service Post Consultant Open 6,000.00 0.00 2021-04-05 2021-05-24 2021-06-14 2021-07-19 2022-01-15 Implementation Information (RTI) Commission delivery Selection at Divisional Office Kohat Page 4 Himachal Pradesh Horticulture Development Project Project ID : P151744 Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan : Original: March 22, 2016 2. Date of General Procurement Notice: May 19, 2015 3. Period covered by this procurement plan: 18 months II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Table 1: Procurement Methods Category Method of Threshold (US$ Procurement Equivalent) Goods and non- ICB >3,000,000 consulting LIB Wherever agreed by the services (including World Bank IT contracts) NCB Up to 3,000,000 (with NCB conditions) Shopping Up to 100,000 From UN Agencies As per para 3.10 of Guidelines DC As per para 3.7 of Guidelines Force Account As per para 3.9 of Guidelines Framework As per para 3.6 of Guidelines Agreements Works ICB >40,000,000 NCB Up to 40,000,000 (with NCB conditions) Shopping Up to 100,000 DC As per para 3.7 of Guidelines Force Account As per para 3.9 of Guidelines  Prior Review by the Bank : The World Bank will prior review all Terms of Reference and the following contracts: March 22, 2015 • Works: All contracts more than US$15.0 million equivalent; • Goods: All contracts more than US$3.0 million equivalent; • Non-Consulting Services: All contracts more than US$3.0 million equivalent;  The HPHDS will prior review the first contract issued by each implementing entity, if the estimates of those contracts are below the prior review threshold value. The Bank will conduct prior review for only those contracts whose estimates fall in the prior review threshold value. In addition, justifications for all contracts to be issued on Limited International Bidding (LIB), direct contracting or single sourcing (>US$100,000) basis will be subject to prior review by the World Bank. These thresholds are set for the initial 18 months of project implementation and are based on the procurement performance of the project, and may be modified. In addition, the Bank will carry out an annual ex post procurement review of the procurement falling below the prior review threshold mentioned above.  All contracts below the specified prior review threshold value will be subject to Post Procurement Review (PPR). The implementing agency will prepare a list of contracts and submit it to the World Bank for this purpose. The PPR will be conducted on an annual basis. 2. Prequalification. Not applicable 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: [Refer to the relevant CDD project implementation document approved by the Bank or delete if not applicable] 4. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan Project XYZ 04/01/2010 issued by 5. Any Other Special Procurement Arrangements:  International Competitive Bidding (ICB) is the preferred method for procurement of goods, works and non-consulting services using the World Bank’s standard bidding document. In addition, the following methods may be adopted depending upon size and complexity of subprojects in accordance with Procurement Guidelines, and as agreed in the Procurement Plan: (a) Limited International Bidding (LIB), (b) National Competitive Bidding (NCB), (c) Shopping, (d) Framework Agreements, (e) Direct Contracting, (f) Force Account, and (g) Procurement of UN agencies. Limited International Bidding is essentially ICB by direct invitation, is used only under exceptional circumstances, and will be March 22, 2015 adopted only for packages that are specifically agreed by the World Bank to be procured following LIB.  National Competitive Bidding (NCB) for procurement of goods and works will be conducted in accordance with paragraphs 3.3 and 3.4 of the Procurement Guidelines and the following provisions: (i) Only the model bidding documents for NCB as agreed with the GoI Task Force (and as amended from time to time), will be used for bidding. (ii) Invitation to bid will be advertised in at least one widely circulated national daily newspaper (or on a widely used website or electronic portal with free national and international access along with an abridged version of the said advertisement published in a widely circulated national daily giving the website/electronic portal details from which the details of the invitation to bid can be downloaded), at least 30 days prior to the deadline for the submission of bids. (iii) No special preference will be accorded to any bidder either for price or for other terms and conditions when competing with foreign bidders, government-owned enterprises, small-scale enterprises or enterprise from any given regional government; (iv) Except with the prior concurrence of the World Bank, there will be no negotiation of price with the bidders, even with the lowest evaluated bidder; (v) For prior review contracts, extension of bid validity will not be allowed without the prior concurrence of the World Bank (i) for the first request for extension if it is longer than four weeks; and (ii) for all subsequent requests for extension irrespective of the period (such concurrence will be considered by the World Bank only in cases of Force Majeure and circumstance beyond the control of the Purchaser/Employer); (vi) For prior review contracts, re-bidding will not be carried out without the prior concurrence of the World Bank; (vii) The system of rejecting bids outside a pre-determined margin or “bracket” of prices will not be used in the Project; (viii) Rates contracts entered into by the Directorate General of Supplies and Disposal (DGS & D) will not be acceptable as a substitute for NCB procedures unless agreed with the World Bank on a case-by- case basis. Such contracts will be acceptable however, for any procurement under the shopping procedure; (ix) The two or three envelop system will not be used (expect when using the e-procurement system assessed and agreed by the World Bank). March 22, 2015  Shopping. Procurement of goods, works and non-consulting services may be carried out using the shopping method (paragraph 3.5 of the Procurement Guidelines) for readily available, off-the-shelf products, or simple civil works valued at less than US$100,000 and which do not require tailor made designs as agreed with the World Bank or concerned expert agencies. Such method, if any, will be agreed in the Procurement Plan. The implementing agency and entities will solicit at least three price quotations for the purchase of goods, materials, small works, or services (non-consulting), to formulate a cost comparison report. If agreed by the World Bank, under exceptional circumstances, (such as design sensitivity due to location near a monument or appropriate technology), International Shopping may be used wherein quotations will be solicited from at least three suppliers in two different countries. Goods that otherwise qualify for shopping could be procured directly from UN agencies. In specific cases agreed with the World Bank, procurement may be made from UN agencies as per paragraph 3.10 of the Procurement Guidelines.  Direct Contracting. Direct contracting for the procurement of civil works and goods (paragraph 3.7 of the Procurement Guidelines) may be used to extend an existing contract or award a new contract. For such contracting to be justified, the World Bank must agree that the price is reasonable and that no advantage could be obtained by further competition. Direct contracting can be used to procure from the private sector, UN agencies/programs (for goods), or contractors or NGOs that are already mobilized and working in the target areas.  Force Account. When contractors/suppliers are unlikely to bid at reasonable prices because of the location and risk associated with the subproject or a certain government agency has exclusive rights to a certain type of works/supply, the borrower may use its own department’s personnel and equipment or government owned construction units, provided that the borrower has sufficient managerial capacity and possesses the required technical and financial controls to report to the World Bank on expenditure, as per paragraph 3.9 of the Procurement Guidelines.  Framework Agreements. Directorate General of Supplies and Disposal rate contracts will be acceptable as framework agreements for the procurement of goods. Regional government level rate contracts will be examined by the World Bank and if agreed upon, may also be used as framework agreements. Implementing entities also have the option to set up new framework agreements as per paragraph 3.6 of the Procurement Guidelines. March 22, 2015  Use of government institutions and enterprise. Government owned enterprise or institutions in India may be hired based on their unique and exceptional nature if their participation is considered critical to the Project implementation. In such cases, the conditions given in clauses 1.13 of the Consultant Guidelines will be satisfied and each case will be subject to prior review by the World Bank. 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness : Available in separate Excel file III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Table 2: Procurement Methods Category Method of Threshold (US$ Procurement Equivalent) Consultants’ QCBS As per Section II of Guidelines services CQS Up to 300,000 SSS As per para 3.8-3.11 of Guidelines Individuals As per Section V of Guidelines LCS As per para 3.6 of Guidelines QBS As per para 3.2 of Guidelines FBS As per para 3.5 of Guidelines (i) International >800,000 shortlist Up to 800,000 (ii) Shortlist may comprise national consultants only  The World Bank will prior review all Terms of Reference and the following contracts: • All contracts more than US$1.0 million equivalent for firm; and • All contracts more US$300,000 equivalent for individuals. The HPHDS will prior review the first contract issued by each implementing entity, if the estimates of those contracts are below the March 22, 2015 prior review threshold value. The Bank will conduct prior review for only those contracts whose estimates fall in the prior review threshold value. In addition, justifications for all contracts to be issued on direct contracting or single sourcing (>US$100,000) basis will be subject to prior review by the World Bank. These thresholds are set for the initial 18 months of project implementation and are based on the procurement performance of the project, and may be modified. In addition, the Bank will carry out an annual ex post procurement review of the procurement falling below the prior review threshold mentioned above. All contracts below the specified prior review threshold value will be subject to Post Procurement Review (PPR). The implementing agency will prepare a list of contracts and submit it to the World Bank for this purpose. The PPR will be conducted on an annual basis. 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than US $ 800,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements:  Selection of Consultants—Quality and Cost Based Selection: Consultant Services may be procured under contracts awarded on the basis of Quality- and Cost-based Selection in accordance with the provisions of Section II of Consultant Guidelines using the World Bank’s Standard RFP. In addition, the following selection methods may be adopted depending upon size and complexity of tasks and as agreed in the Procurement Plan: • Quality Based Selection (QBS) • Selection under Fixed Budget (FBS) • Least Cost Selection (LCS) • Single Source Selection (SSS) • Individual Consultant (IC) Single-Source Selection of consulting firms or individual experts may be used only if it presents a clear advantage over competition for the required consulting services in accordance with paragraph 3.8 of the World Bank’s Consultant Guidelines. Selection of consulting firms based on Consultants’ Qualifications (CQS) may be appropriate for assignments estimated to cost up to US$300,000 or equivalent in accordance with paragraph 3.7 of the Consultant Guidelines. Advertisement for expression of interest may be limited to the regional level for assignments estimated to cost less than US$100,000. For assignments that are estimated to cost less than US$50,000, March 22, 2015 advertisement is not mandatory as long as a shortlist of at least three proven qualified firms is established. Shortlists of consultants for services estimated to cost less than US$800,000 or the equivalent per contract may be composed entirely of national consultants (paragraph 2.7 of Consultant Guidelines). Services for assignments that meet the requirements set forth in paragraph 5.1 of the Consultant Guidelines may be procured under contracts awarded to individual consultants in accordance with the provisions of paragraphs 5.2 to 5.5 of the Consultant Guidelines. Under the circumstances described in paragraph 5.6 of the Consultant Guidelines, such contracts may be awarded to individual consultants on a sole source basis. 4. Consultancy Assignments with Selection Methods and Time Schedule: Available in separate Excel file. March 22, 2015 PROCUREMENT India : Himachal Pradesh Horticulture Development Project PLAN General Information Country: India Bank’s Approval Date of the Original Procurement Plan: 2017-09-12 2021-05-28 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P151744 GPN Date: 2017-04-03 Project Name: Himachal Pradesh Horticulture Development Project Loan / Credit No: IDA / 58380 D Executing Agency(ies): r Y S Parmar University of Horticulture and Forestry, Nauni, Solan WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned HPHDP PIU UHF WORKS 2 / Providing solar fencing, Component A: Horticulture establishment of metrological Request for Single Stage - One 2018-09- IDA / 58380 Production and Post Open - National 280,000.00 0.00 Canceled 2018-01-20 2018-03-17 observatories, supply and Quotations Envelope 13 Diversification erection of training structure for trees HPHDP PIU UHF WORKS 3 / Construction, Upgradation Component A: Horticulture Single Stage - Two 2018-08- and renovation of IDA / 58380 Production and Post Request for Bids Open - National 510,000.00 0.00 Canceled 2017-09-14 2017-09-19 2017-10-31 2018-01-13 2018-02-17 Envelope 16 Laboratories, sitting space, Diversification renovation of PIU Cell WORKS PACKAGE-2 / Component A: Horticulture Request for Single Stage - One 2019-05- Creating of HP-HDP Cell for IDA / 58380 Production and Post Limited 769.00 0.00 Canceled 2018-10-05 2018-11-30 Quotations Envelope 29 PIU at UH&F,Nauni Diversification WORKS PACKAGE-6 / Component A: Horticulture Request for Single Stage - One 2020-05- Construction of sample IDA / 58380 Production and Post Limited 76,000.00 39,034.94 Signed 2019-10-02 2019-12-23 2019-11-27 2020-05-13 Quotations Envelope 25 digestion facility under HPHDP Diversification IN-UNIVERSITY HORTICULT- 119676-CW-RFQ / Renovation of culture room, Component A: Horticulture Request for Single Stage - One 2020-03- Laboratory and sitting space IDA / 58380 Production and Post Limited 17,457.00 17,246.09 Completed 2019-07-27 2017-06-30 2019-09-21 2017-11-11 Quotations Envelope 19 etc. for the department of Diversification plant pathology at main campus nauni, Solan IN-UNIVERSITY HORTICULT- 119686-CW-RFQ / Renovation/Scaling up of Bio- Component A: Horticulture control unit for the Request for Single Stage - One 2020-03- IDA / 58380 Production and Post Limited 25,169.00 24,761.60 Completed 2019-07-27 2018-02-12 2019-09-21 2018-06-08 department of Entomology at Quotations Envelope 19 Diversification main campus Nauni, Solan. SH: Civil works along with module lab IN-UNIVERSITY HORTICULT- 119701-CW-RFQ / Renovation and strengthening of laboratory and sitting space Component A: Horticulture Request for Single Stage - One 2020-03- for the department of Fruit IDA / 58380 Production and Post Limited 28,810.00 29,429.74 Completed 2019-07-28 2017-08-17 2019-09-22 2017-10-04 Quotations Envelope 20 Science at main campus Diversification Nauni, Solan. SH:Civil work along with module lab WORKS PACKAGE-1 / Supply Component A: Horticulture and erection of training Request for Single Stage - One 2020-04- IDA / 58380 Production and Post Limited 40,000.00 33,859.96 Signed 2019-08-27 2018-05-26 2019-10-22 2018-06-19 structures for training of trees Quotations Envelope 19 Diversification under HPHDP WORKS PACKAGE-3 / Component A: Horticulture Request for Single Stage - One 2020-03- Purchase and installation of IDA / 58380 Production and Post Limited 10,000.00 1,349.89 Signed 2019-08-04 2017-07-24 2019-09-29 2017-08-28 Quotations Envelope 27 Drip Irrigation Facilities Diversification WORKS PACKAGE-8 / Component A: Horticulture Development of culture room Request for Single Stage - One 2020-04- IDA / 58380 Production and Post Limited 20,000.00 0.00 Canceled 2019-09-03 2019-10-29 and humidity maintenance Quotations Envelope 26 Diversification and monitoring system WORKS PACKAGE-7 / Construction of building for Component A: Horticulture Under Single Stage - Two 2020-07- creating facilities for queen IDA / 58380 Production and Post Request for Bids Open - National 230,000.00 116,316.60 Implementat 2019-08-22 2020-06-03 2019-08-27 2020-06-04 2019-10-08 2020-07-07 2019-12-21 2020-09-21 2020-01-25 Envelope 23 production and bumble bee Diversification ion rearing WORKS PACKAGE-5 / Component A: Horticulture Development of water supply Single Stage - Two 2020-08- IDA / 58380 Production and Post Request for Bids Open - National 126,000.00 0.00 Canceled 2019-09-16 2019-09-21 2019-11-02 2020-01-15 2020-02-19 facilities and water harvesting Envelope 17 Diversification structures under HPHDP PACKAGE-19 / Supply and Component A: Horticulture Request for Single Stage - One 2021-08- Installation of Drip Irrigation IDA / 58380 Production and Post Limited 11,000.00 0.00 Canceled 2020-12-20 2021-02-14 Quotations Envelope 13 System for new Fruit Orchards Diversification WORKS PACKAGE-4 / Component A: Horticulture Under Providing Solar Fencing of Request for Single Stage - One 2021-08- IDA / 58380 Production and Post Limited 70,000.00 0.00 Implementat 2020-12-20 2021-05-18 2021-02-14 Experimental Area under Quotations Envelope 13 Diversification ion HPHDP PACKAGE-20 / Creation of Component A: Horticulture Pending Request for Single Stage - One 2021-09- water facilities under new IDA / 58380 Production and Post Limited 27,000.00 0.00 Implementat 2021-01-08 2021-03-05 Quotations Envelope 01 component gene bank Diversification ion PACKAGE -19 / Supply and Component A: Horticulture Request for Under Request for Single Stage - One 2022-01- Installation of Drip Irrigation IDA / 58380 Production and Post Limited Quotations (Non 70,000.00 0.00 Implementat 2021-06-08 2021-05-20 2021-08-03 Quotations Envelope 30 System. Diversification Bank-SPD) ion GOODS Page 1 Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual HPHDP PIU UHF COM SOFT Component A: Horticulture Request for Single Stage - One PROC / Purchase of Computer IDA / 58380 Production and Post Open - National 110,000.00 18,304.44 Completed 2018-01-06 2018-03-03 2018-03-16 2018-08-30 2018-04-18 Quotations Envelope software Weather Station Diversification GOODS PACKAGE 2 / Component A: Horticulture Request for Single Stage - One Procurement of Silent Gensets IDA / 58380 Production and Post Open - National 85,077.00 11,237.52 Signed 2018-07-12 2018-09-06 2018-12-14 2019-03-05 Quotations Envelope 4 Diversification HPHDP PIU UHF FARM MACH Component A: Horticulture Request for Single Stage - One / Procurement of Farm IDA / 58380 Production and Post Open - National 50,000.00 0.00 Canceled 2017-08-21 2017-10-16 2018-04-14 Quotations Envelope Machineries and Tools Diversification Component A: Horticulture HPHDP PIU UHF GEN PURCH / Request for Single Stage - One IDA / 58380 Production and Post Open - National 80,000.00 0.00 Canceled 2017-09-25 2017-11-20 2018-05-19 Purchase of Generator Quotations Envelope Diversification IN-UNIVERSITY HORTICULT- 61535-GO-RFB / Component A: Horticulture Procurement of Transmission Single Stage - Two IDA / 58380 Production and Post Request for Bids Open - National 770,000.00 0.00 Canceled 2018-07-25 2019-01-02 2018-07-30 2018-09-10 2019-02-05 2018-11-23 2018-12-28 2019-06-26 Electron Microscope and Ultra Envelope Diversification Microtome Upgradable to Cryo with Accessories GOODS PACKAGE-8 / AC-5, Deep Freezer-5, Digital temperature & RH Recorder- 10, Flame Photometer-1, Fume Hoods-1, GPS-9, Hot Component A: Horticulture Request for Single Stage - One Plate-2, Hygrometer-5, IDA / 58380 Production and Post Limited 1,523.00 0.00 Canceled 2018-09-29 2018-11-24 2019-05-23 Quotations Envelope Incubator-cum-shaker-6, Diversification Microwave-2, Mixing machine & trays-1, Media pump with tank, mixer-grinder, pressure tester-1, etc. GOODS PACKAGE-7 / Autoclave-5, BOD Incubator- 9, Centrifuge-2, CHNS Analyzer-1, Canopy Analyzer- Component A: Horticulture 1, CO2 Analyzer, Dehumidifer- Single Stage - Two IDA / 58380 Production and Post Request for Bids Open - National 4,154.00 0.00 Canceled 2018-09-17 2018-09-22 2018-11-03 2019-01-16 2019-02-20 2019-08-19 1, Hot air oven-7, leaf area Envelope Diversification meter-2, Laminar Air Flow-5, Mite brushing and Counting Machine-1, Microcentrifuge-2 etc. GOODS PACKAGE-5 / Procurement of Scientific Equipments (Atomic Absorption Spectrophotometer-1, Component A: Horticulture Deionizer-1, Electrophoresis Single Stage - Two IDA / 58380 Production and Post Request for Bids Open - National 8,615.00 0.00 Canceled 2018-09-17 2018-09-22 2018-11-03 2019-01-16 2019-02-20 2019-08-19 apparatus-2, Fermenter-1, Envelope Diversification Gas Chromatograph-1, Gel Documentation System-1, ICAP-1, KD Pro Thermal Imager-1, LCMS-1, Microwave digestion system-1 etc. GOODS PACKAGE-13 / Component A: Horticulture Request for Single Stage - One Procurement of software and IDA / 58380 Production and Post Limited 308.00 0.00 Canceled 2018-09-22 2018-11-17 2019-05-16 Quotations Envelope software development charges Diversification GOODS PACKAGE 5 / Gel documentation, Inductively Coupled, UV Spectrophotometer, Root Length Scanner, Soil Moisture Component A: Horticulture Single Stage - Two Meter, KD Pro-3, Pressure IDA / 58380 Production and Post Request for Bids Open - National 560,000.00 140,543.45 Signed 2019-09-26 2019-01-02 2019-10-01 2019-11-12 2019-02-14 2020-01-25 2019-07-17 2020-02-29 2019-12-03 2020-08-27 Envelope Plate Apparatus, Diversification Electrophoresis Unit, Spectrometer, Deionizer, Nano Pico drop, Micreowave Digestion System etc. GOODS PACKAGE 7 / Laboratory and Field Equipment (Leaf Area Mater, Plant Canopy Analyzer, Component A: Horticulture Single Stage - Two Laminar Air Flow, BOD IDA / 58380 Production and Post Request for Bids Open - National 270,000.00 93,898.33 Signed 2019-08-23 2019-01-02 2019-08-28 2019-10-09 2019-02-07 2019-12-22 2019-07-03 2020-01-26 2019-08-30 2020-07-24 2019-11-29 Envelope Incubator, Autoclave, Real Diversification Time PCR, Dehumidifier, Hot Air Oven, Centrifuge,CHNS Analyzer etc.) GOODS PACKAGE-4 / Microscopes and Cameras ( Component A: Horticulture Stereozoom , Binocular, Single Stage - Two IDA / 58380 Production and Post Request for Bids Open - National 120,000.00 2,925.19 Signed 2019-09-19 2019-01-02 2019-09-24 2019-11-05 2019-01-29 2020-01-18 2019-02-21 2020-02-22 2019-08-08 2020-08-20 Fluorescent, Phase Contrast Envelope Diversification Microscopes and video & digital cameras) IN-UNIVERSITY HORTICULT- 68678-GO-RFQ / Procurement of computer Component A: Horticulture Request for Single Stage - One systems (Desktops-04, IDA / 58380 Production and Post Open - National 17,290.00 0.00 Canceled 2018-07-12 2018-08-20 2019-02-16 Quotations Envelope Laptops-7, Printer-cum- Diversification Scanner-8, UPS-5, MS Office 2016-11 Nos.) through GeM GOODS PACKAGE-6 / Procurement of Scientific Equipment: GPS, High Precision Weighing, Microwave, Deep Freezer, Component A: Horticulture Refrigerator, Air Conditioner, Request for Single Stage - One IDA / 58380 Production and Post Open - National 99,000.00 24,967.98 Signed 2019-02-16 2019-04-13 2019-11-28 2019-10-10 Vacuum Cleaner, Quotations Envelope Diversification Thermometer, Water Bath, Digital Refractometer, Mixer- cum- Grinder, Hot Plate, Mixing Machine Flame Photometer etc Page 2 IN-UNIVERSITY HORTICULT- 119690-GO-RFQ / Establishment of Soil and and Plant testing laboratories in existing training hall building Component A: Horticulture Request for Single Stage - One for the department of Soil IDA / 58380 Production and Post Limited 57,806.00 56,494.76 Signed 2019-07-28 2017-10-21 2019-09-22 2018-01-08 2020-03-20 Quotations Envelope Science and Water Diversification Management (SSWM) at main campus Nauni, Solan. SH: Civil work along with Module labs GOODS PACKAGE 8 / Farm Component A: Horticulture Machinery ( Tractor with Request for Single Stage - One IDA / 58380 Production and Post Limited 29,200.00 20,894.89 Completed 2019-09-30 2019-06-14 2019-11-25 2019-07-03 2020-05-23 2019-08-08 Accessories, Rotavator, Power Quotations Envelope Diversification Tiller, Power Sprayer) GOODS PACKAGE -11 / Portable Photosynthesis System, Deep Freezers, Vortex Multipurpose, Shaking Water Bath, Hot Air Oven, CHNS Component D: Project Single Stage - Two Analyzer, Orbital Shaker, IDA / 58380 Management, Monitoring and Post Request for Bids Open - National 273,000.00 243,172.14 Signed 2020-01-28 2020-01-20 2020-02-02 2020-03-15 2020-02-17 2020-05-28 2020-07-20 2020-07-02 2020-07-20 2020-12-29 Envelope Centrifuge, Spectronic 20D, Learning GPS, Elisa Plate Reader, Fluorescent microscope, Mite Brushing & Counting Machine, etc PACKAGE-14(TEM-GOODS) / Component A: Horticulture Procurement of Transmission Single Stage - Two IDA / 58380 Production and Post Request for Bids Open - National 700,000.00 0.00 Canceled 2020-07-30 2020-09-04 2020-08-04 2020-10-07 2020-09-15 2020-11-12 2020-11-28 2021-01-02 2021-07-01 Electron Microscope under Envelope Diversification component A1.7e PACKAGE-15 ( ULTRAMICROTOME-GOODS) / Component A: Horticulture Single Stage - Two Procurement of IDA / 58380 Production and Post Request for Bids Open - National 169,500.00 0.00 Canceled 2020-07-30 2020-09-04 2020-08-04 2020-10-07 2020-09-15 2020-11-12 2020-11-28 2021-01-02 2021-07-01 Envelope Ultramicrotome under Diversification Component A1.7e PACKAGE-16 / Procurement Component A: Horticulture Pending of Farm Tool Under Gene Bank Request for Single Stage - One IDA / 58380 Production and Post Limited 12,000.00 0.00 Implementati 2020-12-12 2021-02-06 2021-08-05 and other components (need Quotations Envelope Diversification on based) Component A: Horticulture Pending PACKAGE-17 / Procurement Request for Single Stage - One IDA / 58380 Production and Post Limited 3,500.00 0.00 Implementati 2020-12-11 2021-02-05 2021-08-04 of Minor Farm Tools Quotations Envelope Diversification on PACKAGE-18 / Procurement Component A: Horticulture Pending Request for Single Stage - One of Various Scientific IDA / 58380 Production and Post Limited 60,000.00 0.00 Implementati 2020-12-11 2021-02-05 2021-08-04 Quotations Envelope Equipments under HPHDP Diversification on PACKAGE-14(RETENDER) TEM- GOODS / Procurement of Component A: Horticulture Under Single Stage - Two Transmission Electron IDA / 58380 Production and Post Request for Bids Open - National 700,000.00 0.00 Implementati 2021-02-01 2021-02-03 2021-02-06 2021-03-20 2021-03-06 2021-06-02 2021-07-07 2022-01-03 Envelope Microscope under component Diversification on A1.7e PACKAGE-15 (RETENDER) ULTRA MICROTOME / Component A: Horticulture Under Single Stage - Two Procurement of Ultra IDA / 58380 Production and Post Request for Bids Open - National 169,500.00 0.00 Implementati 2021-02-01 2021-02-03 2021-02-06 2021-03-20 2021-03-06 2021-06-02 2021-07-07 2022-01-03 Envelope microtome under component Diversification on A1.7e NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NON-CONSULTING SERVICE Component A: Horticulture PACKAGE-1 / Engagement of Single Stage - Two IDA / 58380 Production and Post Request for Bids Open - National 140,000.00 0.00 Canceled 2019-03-11 2019-03-16 2019-04-27 2019-07-10 2019-08-14 2020-02-10 Contractual Labourers (Labour Envelope Diversification Agency) HPHDP PIU UHF NON Component A: Horticulture CONSUL / Engagement of Request for Single Stage - Two IDA / 58380 Production and Post Open - National 780,000.00 0.00 Canceled 2017-10-12 2017-10-17 2017-11-28 2018-02-10 2018-03-17 2018-09-13 Contractual Labourers Labour Proposals Envelope Diversification Agency CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual HPHDP PIU UHF CONSULTANCY / Consultancy Component A: Horticulture Quality And Cost- services for providing IDA / 58380 Production and Post Open - International 320,000.00 0.00 Canceled 2019-09-25 2019-10-16 2019-11-29 2019-12-27 2020-01-26 2020-03-01 2020-04-05 2021-04-05 Based Selection international best practices Diversification for rearing of bumble bees INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTANCY PACKAGE-3 / Component A: Horticulture Individual Hiring of individual consultant IDA / 58380 Production and Post Consultant Open 72,000.00 0.00 Canceled 2019-01-31 2019-03-21 2019-04-11 2019-05-16 2019-11-12 services of Senior Reserch Diversification Selection Fellows CONSULTANT PACKAGE-2 / Component A: Horticulture Individual Hiring of individual consultant IDA / 58380 Production and Post Consultant Open 13,000.00 0.00 Canceled 2019-01-31 2019-03-21 2019-04-11 2019-05-16 2019-11-12 services of Research Associate Diversification Selection Page 3 CONSULTANT PACKAGE-4 / Hiring of individual consultant services of Technical Component A: Horticulture Individual Assistants, Field Assistant, IDA / 58380 Production and Post Consultant Open 37,000.00 0.00 Canceled 2019-02-15 2019-04-05 2019-04-26 2019-05-31 2019-11-27 Trained Pruners, Farm Tool Diversification Selection Operators, Technicians, Bee Keeper, Data Entry Operator etc. Page 4 Procurement Plan for Punjab RWSS (P150520) I. General 1. Bank’s approval Date of the procurement Plan 2012 2. Date of General Procurement Notice: [October 01, 2014 ] 3. Period covered by this procurement plan: January 2020 onwards II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as per the Procurement Risk Rating of the Project: 2. Procurement Method Prior Review Threshold US$ 1. ICB and LIB (Goods) Above US$ 2M 2. NCB (Goods) Above US$ 1M 3. ICB (Works) Above US$ 40 million 4. NCB (Works) Above US$ 10 million 5. (Non-Consultant Services) Above US$ 1M 2. Prequalification for Bidders _Not applicable_ 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: NA 4. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan Project P150520 5. Any Other Special Procurement Arrangements: In addition, the justification for all contracts to be issued on the basis of LIB, single-source or direct contracting (except for contracts less than US$50,000 in value) will be subject to prior review. III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Threshold 1. Competitive Methods (Firms) Above US$ 1M 2. Single Source (Firms) Above US$ 500,000 3. Individual Above US$ 300,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. PROCUREMENT India : Punjab Rural Water and Sanitation Sector Improvement Project PLAN General Information Country: India Bank’s Approval Date of the Original Procurement Plan: 2018-08-29 2021-05-26 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P150520 GPN Date: Project Name: Punjab Rural Water and Sanitation Sector Improvement Project Loan / Credit No: IBRD / 84870 Division Pathankot (EE- 2nd) Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned DWSS-W-DIV83-5317-1 / W/S Scheme Bamial and Village Anial Block Bamial Inclusive Household Water Request for Single Stage - One 2018-07- District Pathankot:- Providing, IBRD / 84870 Post Open - National 12,700.00 11,259.45 Completed 2018-07-13 2018-07-13 2016-12-23 and Sanitation Services Quotations Envelope 13 laying, fixing, Pipe Line And Water Connection under component 2B PRWSS-S-DIV83-5452-1 / Renovation of rooms for new Je sections (S125 to S133) under jurisdiction of Division Strengthening Institutions Request for Single Stage - One 2019-05- Pathankot EE-2nd including IBRD / 84870 Post Open - National 2,230.00 2,078.67 Signed 2018-09-08 2018-11-03 2018-11-19 and Project Management Quotations Envelope 02 white washing repair of room fixing electric fans and lights e.t.c under component 4A of PRWSSIP DWSS-W-DIV83-6233-1 / WSS Vill Jaini Chack Block Narot Jaimal Singh District Pathanklot: Pkg-2 OHSR, Civil Transformation - Improved Request for Single Stage - One 2020-01- IBRD / 84870 Post Open - National 32,400.00 25,263.78 Signed 2019-04-08 2019-06-03 2019-05-29 Work,Pump Chamber, Livability of Villages Quotations Envelope 29 Pumping Machinery Distribution Pipe Line under component 1A(ii) of PRWSSIP. DWSS-W-DIV83-6505-1 / WSS Chack Amir,Block Bamial, district Pathankot:Providing and Installing of 200mm i/d, Transformation - Improved Request for Single Stage - One 2020-01- IBRD / 84870 Post Open - National 25,000.00 22,208.16 Signed 2019-07-20 2019-10-29 2019-08-16 straight tubewell, upto 125 Livability of Villages Quotations Envelope 27 metres depth with percussion rig under component 1A(ii) of PRWSSIP. DWSS-W-DIV83-6969-1 / WSS Village Saharanpur, Block N.J. Singh, Distt. Pathankot.: Inclusive Household Water Request for Single Stage - One 2020-06- Providing Improved Access to IBRD / 84870 Post Open - National 11,000.00 10,062.63 Signed 2019-10-07 2020-02-12 2020-02-10 2019-11-26 and Sanitation Services Quotations Envelope 09 Water Through Household Connections & Distribution System DWSS-W-DIV83-7165-1 / WSS Village Attepur of Villages Attepur & Bhool chack, Block Sujanpur Distt. Pathankot. Transformation - Improved Request for Single Stage - One 2020-07- IBRD / 84870 Post Open - National 82,100.00 20,263.77 Signed 2019-11-18 2020-03-23 2020-05-18 Providing and installing of Livability of Villages Quotations Envelope 21 200mm i/d straight tubewell, upto 125 mtr depth with percussion rig. DWSS-W-DIV83-7166-1 / WSS Village Jhanjeli , Block Sujanpur Distt. Pathankot. Transformation - Improved Request for Single Stage - One 2020-07- Providing and installing of IBRD / 84870 Post Open - National 67,000.00 20,263.77 Signed 2019-11-18 2020-03-23 2020-05-18 Livability of Villages Quotations Envelope 21 200mm i/d straight tubewell, upto 125 mtr depth with percussion rig. DWSS-W-DIV83-6505-2 / WSS Chack Amir, Block Bamial Distt. Pathankot: Const. of OHSR, Pump Chamber & Transformation - Improved Request for Single Stage - One 2020-12- Pumping machinery, IBRD / 84870 Post Open - National 60,600.00 56,696.37 Signed 2020-02-10 2020-06-15 2020-01-17 Livability of Villages Quotations Envelope 12 Disinfection Unit, Development of Water Works, & Distribution System complete in all respect. DWSS-W-DIV83-8169-1 / WSS Village Bhatoa, Block Narot Jaimal Singh Distt. Pathankot: Providing and Transformation - Improved Request for Single Stage - One 2021-09- IBRD / 84870 Post Open - National 24,000.00 22,631.70 Signed 2020-08-31 2021-05-18 2020-10-07 installing of 200mm i/d Livability of Villages Quotations Envelope 15 straight tubewell, upto 125 mtr depth with percussion rig at DWSS-W-DIV83-8280-1 / WSS Majra, Block Narot Jaimal Singh Distt. Pathankot : Transformation - Improved Request for Single Stage - One 2021-09- Providing and installing of IBRD / 84870 Post Open - National 24,000.00 22,697.78 Signed 2020-08-31 2021-05-18 2020-09-16 Livability of Villages Quotations Envelope 15 200mm i/d straight tubewell, upto 125 mtr depth with percussion rig at PRWSS-W-DIV83-8281-1 / WSS Village Manwal, Block Bamial, Distt. Pathankot : Construction of OHSR & Pump Transformation - Improved Request for Single Stage - One 2021-09- IBRD / 84870 Post Open - National 56,200.00 54,449.64 Signed 2020-08-31 2021-05-18 2020-10-07 chamber, installation of new Livability of Villages Quotations Envelope 15 machinery, Development of water works & Distribution System Page 1 DWSS-W-DIV83-7165-2 / WSS Village Attepur & Bhool Chack, Block Sujanpur Distt. Pathankot: Construction of Transformation - Improved Request for Single Stage - One 2021-09- IBRD / 84870 Post Open - National 56,000.00 56,015.99 Signed 2020-08-31 2021-05-18 2020-10-07 OHSR, Pump Chamber, Livability of Villages Quotations Envelope 15 Development of water works & Distribution System for bifurcation . DWSS-W-DIV83-7166-2 / WSS Village Jhanjeli & Nihalpur, Block Sujanpur Distt. Pathankot: Construction Transformation - Improved Request for Single Stage - One 2021-09- IBRD / 84870 Post Open - National 41,500.00 45,764.89 Signed 2020-08-31 2021-05-18 2020-11-05 of OHSR, Pump Chamber, Livability of Villages Quotations Envelope 15 Development of water works & Distribution System for bifurcation PRWSS-S-DIV83-8073-1 / Construction of Office Strengthening Institutions Request for Single Stage - One 2022-07- Building Sub Divisional Office IBRD / 84870 Post Open - National 50,500.00 47,078.13 Signed 2020-10-12 2021-10-07 2020-08-25 and Project Management Quotations Envelope 04 Narot Jaimal Singh, Distt. Pathankot DWSS-W-DIV83-7930-2 / WSS Village Dhesian Ram Colony Block Sujanpur Distt. Under Pathankot.: Construction of Transformation - Improved Request for Single Stage - One 2021-03- IBRD / 84870 Post Open - National 65,700.00 0.00 Implementat 2021-01-13 2021-02-17 OHSR, Pump Chamber, Prov. & Livability of Villages Quotations Envelope 19 ion Installing New Machinery & Distribution Syste at Water supply scheme DWSS-W-DIV83-7930-1 / WSS Village Dhesian Ram Colony Block Sujanpur Distt. Pathankot.Providing and Transformation - Improved Request for Single Stage - One 2021-03- IBRD / 84870 Post Open - National 23,000.00 28,376.03 Signed 2021-01-13 2021-02-24 2021-02-12 installing of 200mm i/d Livability of Villages Quotations Envelope 26 straight tubewell, upto 125 mtr depth with percussion rig at DWSS-W-DIV83-8169-2 / WSS Bhatoa, Block Narot Jaimal Singh Distt. PathankotConstruction of Under Transformation - Improved Request for Single Stage - One 2021-09- OHSR, Pump Chamber, Prov. & IBRD / 84870 Post Open - National 62,500.00 0.00 Implementat 2021-01-13 2021-03-11 Livability of Villages Quotations Envelope 07 insatlling new machinery, ion Development of water works & Distribution system at Water Supply Scheme DWSS-W-DIV83-8280-2 / WSS Village Majra, Block Narot Jaimal Singh Distt. PathankotConstruction of Under Transformation - Improved Request for Single Stage - One 2021-09- OHSR, Pump Chamber, Prov. & IBRD / 84870 Post Open - National 70,000.00 0.00 Implementat 2021-01-13 2021-03-11 Livability of Villages Quotations Envelope 07 insatlling new machinery, ion Development of water works & Distribution system at Water Supply Scheme DWSS-W-DIV83-8419-1 / WSS Village Kotli Jawahar, Block Bamial, Distt. Transformation - Improved Request for Single Stage - One 2021-09- PathankotProviding & IBRD / 84870 Post Open - National 18,000.00 15,094.50 Signed 2021-01-13 2021-03-13 2021-02-12 Livability of Villages Quotations Envelope 09 Installing new tubewell 125 mm id upto 75 mtr depth. at water supply scheme DWSS-W-DIV83-8419-2 / WSS Village Kotli Jawahar, Block Bamial, Distt. Pathankot: Construction of OHSR & Pump Under Transformation - Improved Request for Single Stage - One 2021-09- chamber, installation of new IBRD / 84870 Post Open - National 8,000.00 0.00 Implementat 2021-01-13 2021-03-11 Livability of Villages Quotations Envelope 07 machinery, Development of ion water works & Distribution System at water supply scheme DWSS-W-DIV83-8591-1 / WSS Village Narianpur, Block Narot Jaimal Singh, Distt. Pathankot: Providing and Transformation - Improved Request for Single Stage - One 2021-09- IBRD / 84870 Post Open - National 25,000.00 24,059.24 Signed 2021-01-13 2021-03-11 2021-02-12 installing new tubewll 200 Livability of Villages Quotations Envelope 07 mm i/d upto 115 mtr depth with percussion at water supply scheme DWSS-W-DIV83-8591-2 / WSS Village Narianpur, Block Narot Jaimal Singh, Distt. Pathankot: Construction of Under Transformation - Improved Request for Single Stage - One 2021-09- OHSR, pump chamber, Prov. & IBRD / 84870 Post Open - National 86,000.00 0.00 Implementat 2021-01-13 2021-03-11 Livability of Villages Quotations Envelope 07 Installing machinery, ion Development of Water Works & Distribution System at water supply scheme DWSS-W-DIV83-9288-1 / WSS Village Naroli, Block Narot Jaimal Singh Distt. Under Pathankot : Providing and Transformation - Improved Request for Single Stage - One 2021-11- IBRD / 84870 Post Open - National 23,000.00 22,294.44 Implementat 2021-04-20 2021-04-19 2021-05-27 installing new tubewll 200 Livability of Villages Quotations Envelope 23 ion mm i/d upto 100 mtr depth with percussion rig at water supply scheme DWSS-W-DIV83-9288-2 / WSS village Naroli, Block Narot Jaimal Singh Distt. Pathankot, Construction of Under Transformation - Improved Request for Single Stage - One 2021-11- OHSR, Pump Chamber, IBRD / 84870 Post Open - National 70,000.00 0.00 Implementat 2021-04-20 2021-05-27 Livability of Villages Quotations Envelope 23 Providing and installing new ion machinery, Development of water works and distribution syste at water supply scheme Page 2 DWSS-W-DIV83-9592-1 / WSS VILL PHOOL PIARA, BLOCK SUJANPUR, DISTT. National PATHANKOT : PROVIDING Procurement Pending Transformation - Improved Request for Single Stage - One 2021-09- 100% FUNCTIONAL IBRD / 84870 Post Open - National Document - 1 17,000.00 0.00 Implementat 2021-05-23 2021-06-30 Livability of Villages Quotations Envelope 28 HOUSEHOLD TAP Envelope process ion CONNECTIONS (FHTC) TO (2 (Non Bank-SPD) NOS.) HABITATIONS PHOOL PIARA AND ASSA BANO GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PRWSS-G-DIV83-5450-1 / Procurement of Office furniture, Electric fans tools and plants and other facilities Strengthening Institutions Request for Single Stage - One for New JE sections (S125 to IBRD / 84870 Post Open - National 4,450.00 4,152.41 Signed 2018-09-08 2018-11-03 2018-11-19 2019-05-02 and Project Management Quotations Envelope S133) under jurisdiction of Division PathankotEE-2nd under Component 4 A of PRWSSIP NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 3 Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan: negotiations May, 2019. 2. Date of General Procurement Notice: to be published in Aug 2020 3. Period covered by this procurement plan: The procurement period of project covered from year July 2020 to Jun 2021, no procurements have commenced as yet. II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement for Moderate Risk Projects: Procurement Method Prior Review Comments Threshold US$ 1. ICB and LIB (Goods) US$ 4 million All 2. NCB (Goods) US$ 4 million All 3. ICB (Works) US$ 15 million All 4. NCB (Works) US$ 15 million All 5. (Non-Consultant Services) US$ 4 million All 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Reference to (if any) Project Operational/Procurement Manual: Operations Manual has been prepared and procurement is a component of it. Arrangements for local government component have been given in detail. 4. Any Other Special Procurement Arrangements: Not Applicable 5. Summary of the Procurement Packages planned during the first 18 months after project effectiveness The main contracts identified so far for the three implementing entities are provided in the annex below. There are no large ICBs of Works or Goods; only some consultancies are beyond the national firms thresholds, and some non consultancy contracts of ETD. III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comments Threshold 1. Competitive Methods (Firms) Above US$ 2 m 2. Single Source (Firms) Above US $ 2 m Justification alongwith identification of SSS in procurement plan 3. Individual Above US$ 400, 000 In addition the selection of procurement staff 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_500,000_equivalent per contract, may comprise entirely of national consultants in accordance with the OPCS guidance. 3. Any Other Special Selection Arrangements: [including advance procurement and retroactive financing, if applicable or delete if not applicable] 4. Consultancy Assignments with Selection Methods and Time Schedule: There are a number of activities for consultancy contracts. The procurement activity table is annexed which indicted the identified activities. Procurement Activities Estimat Sr. Risk Bank Procureme Evaluation ed Cost Selection No Activity Catego oversig nt selection USD method . ry ht Approach method 000s Project Implementation Unit Office - Local Government Department Annual performanc QCBS e Substant QCBS Firms Highest 1 assessment 1,230 ial Prior Selection internation ranked al of Local Councils Environme nt and Social QCBS Moderat QCBS Firms Highest 2 Safeguard 4,920 e Prior Selection internation ranked s al consultanc y Project Implementation Unit Office - Excise and Taxation Department Disaster Lowest Substant 1 recovery 5,100 ial Prior RFB ICB IT evaluated site responsive Consultanc y for QCBS Modera QCBS Firms Highest 2 software 5,000 te Prior Selection internation ranked developme al nt 14,000 RFB non Lowest Property 5-7 Moderat Single stage 3 survey e post one envelope consultanc evaluated package y responsive s 10,000 Single stage Lowest IT 2-3 Substanti 4 hardware al Prior one envelope RFB evaluated package responsive s Consulting firm for QCBS Substanti QCBS Firms Highest 5 developing 1,680 al Prior Selection internation ranked ICT al strategy Project Implementation Unit Office - Sindh Investment Department Estimat Sr. Risk Bank Procureme Evaluation ed Cost Selection No Activity Catego oversig nt selection USD method . ry ht Approach method 000s Consultanc y for QCBS Substant QCBS Firms Highest 1 bussiness 5,250 ial Prior Selection internation ranked process al mapping Automatio QCBS n of Substant QCBS Firms Highest 2 business 6,000 ial Prior Selection internation ranked al processes Sindh Solid Waste Management Board (to be executed by LGD) Baseline QCBS study for Moderat QCBS Firms Highest 1 landfill 2,000 e Prior Selection internation ranked al sites Study for mapping QCBS Moderat QCBS Firms Highest 2 of 2,100 e Prior Selection internation ranked collection al systems Review of QCBS informal Substant QCBS Firms Highest 3 sector for 1,500 ial Prior Selection internation ranked al recycling PROCUREMENT Pakistan : Competitive and Livable City of Karachi Project PLAN General Information Country: Pakistan Bank’s Approval Date of the Original Procurement Plan: 2020-08-21 2021-05-25 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P161402 GPN Date: Project Name: Competitive and Livable City of Karachi Project Loan / Credit No: IBRD / 89980 Local Government Department, Sindh Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned PK-LGD -187684-CW-RFQ / Performance-based Grants to UPGRADATION, RENOVATION Request for Single Stage - One 2021-04- IBRD / 89980 Local Councils and Capacity Post Limited 100,000.00 97,012.25 Signed 2020-08-11 2020-02-20 2020-10-06 2020-03-18 AND REDESIGNING FOR Quotations Envelope 04 Building OFFICE PK-LGD -237541-CW-RFQ / Performance-based Grants to Request for Pending Upgradation, Renovation And Request for Single Stage - One 2021-11- IBRD / 89980 Local Councils and Capacity Post Limited Quotations (Non 100,000.00 0.00 Implementat 2021-06-08 2021-08-03 Redesigning For DMC South Quotations Envelope 01 Building Bank-SPD) ion Office PK-LGD -237728-CW-RFQ / Performance-based Grants to Request for Pending Upgradation, Renovation And Request for Single Stage - One 2021-11- IBRD / 89980 Local Councils and Capacity Post Limited Quotations (Non 100,000.00 0.00 Implementat 2021-06-09 2021-08-04 Redesigning For DMC Central Quotations Envelope 02 Building Bank-SPD) ion Office PK-LGD -237795-CW-RFQ / Performance-based Grants to Request for Pending Upgradation, Renovation And Request for Single Stage - One 2021-11- IBRD / 89980 Local Councils and Capacity Post Limited Quotations (Non 100,000.00 0.00 Implementat 2021-06-09 2021-08-04 Redesigning For DMC East Quotations Envelope 02 Building Bank-SPD) ion Office PK-LGD -237874-CW-RFQ / Performance-based Grants to Request for Pending Upgradation, Renovation And Request for Single Stage - One 2021-11- IBRD / 89980 Local Councils and Capacity Post Limited Quotations (Non 100,000.00 0.00 Implementat 2021-06-09 2021-08-04 Redesigning For DMC West Quotations Envelope 02 Building Bank-SPD) ion Office PK-LGD -237882-CW-RFQ / Performance-based Grants to Request for Pending Upgradation, Renovation And Request for Single Stage - One 2021-11- IBRD / 89980 Local Councils and Capacity Post Limited Quotations (Non 100,000.00 0.00 Implementat 2021-06-09 2021-08-04 Redesigning For DMC Malir Quotations Envelope 02 Building Bank-SPD) ion Office PK-LGD -237906-CW-RFQ / Performance-based Grants to Request for Pending Upgradation, Renovation And Request for Single Stage - One 2021-11- IBRD / 89980 Local Councils and Capacity Post Limited Quotations (Non 100,000.00 0.00 Implementat 2021-06-09 2021-08-04 Redesigning For DMC Korangi Quotations Envelope 02 Building Bank-SPD) ion Office PK-LGD -237915-CW-RFQ / Performance-based Grants to Request for Pending Upgradation, Renovation and Request for Single Stage - One 2021-11- IBRD / 89980 Local Councils and Capacity Post Limited Quotations (Non 100,000.00 0.00 Implementat 2021-06-09 2021-08-04 Redesigning for District Quotations Envelope 02 Building Bank-SPD) ion Council Office PK-LGD -237922-CW-RFQ / Performance-based Grants to Request for Pending Request for Single Stage - One 2021-11- Upgradation, Renovation And IBRD / 89980 Local Councils and Capacity Post Limited Quotations (Non 50,000.00 0.00 Implementat 2021-06-09 2021-08-04 Quotations Envelope 02 Redesigning For KMC Office Building Bank-SPD) ion PK-LGD -237925-CW-RFQ / Performance-based Grants to Request for Pending Request for Single Stage - One 2021-11- Repair & rehabilitation of IBRD / 89980 Local Councils and Capacity Post Limited Quotations (Non 90,000.00 0.00 Implementat 2021-06-09 2021-08-04 Quotations Envelope 02 washrooms at KMC building Building Bank-SPD) ion GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Performance-based Grants to Under PK-LGD -187687-GO-RFQ / Request for Single Stage - One IBRD / 89980 Local Councils and Capacity Post Limited 25,000.00 0.00 Implementati 2020-08-11 2020-08-24 2020-10-06 2021-04-04 Power Generator for PIU Quotations Envelope Building on PK-LGD -187603-GO-RFQ / IT Equipment for PIU (Computer Equipments Performance-based Grants to (Laptops, Desktops, Laser Request for Single Stage - One IBRD / 89980 Local Councils and Capacity Post Limited 70,000.00 62,025.57 Signed 2020-08-11 2020-05-07 2020-10-06 2020-06-08 2021-01-04 Printers, Multimedia Quotations Envelope Building Equipment, Camera Cartridges, Photocopier and Softwares)) Performance-based Grants to PK-LGD -187629-GO-RFQ / Request for Single Stage - One IBRD / 89980 Local Councils and Capacity Post Limited 70,000.00 68,841.78 Signed 2020-08-11 2020-04-01 2020-10-06 2020-04-24 2021-04-04 Furniture and Fixture for PIU Quotations Envelope Building PK-LGD -187677-GO-RFQ / Performance-based Grants to Office Appliances, Machinery Request for Single Stage - One IBRD / 89980 Local Councils and Capacity Post Limited 35,000.00 35,811.48 Signed 2020-08-11 2020-05-07 2020-10-06 2020-06-08 2020-12-05 and Communication System Quotations Envelope Building for PIU Performance-based Grants to PK-LGD -187683-GO-RFQ / Request for Single Stage - One IBRD / 89980 Local Councils and Capacity Post Limited 3,500.00 2,386.22 Signed 2020-08-11 2020-04-21 2020-10-06 2020-05-30 2021-04-04 Motorbikes for PIU Quotations Envelope Building Performance-based Grants to Pending PK-LGD -187682-GO-RFQ / Request for Single Stage - One IBRD / 89980 Local Councils and Capacity Post Limited 90,000.00 0.00 Implementati 2020-08-11 2020-10-06 2021-04-04 Office Vehicles for PIU Quotations Envelope Building on PK-LGD -227730-GO-RFQ / Procurement of Additional IT Performance-based Grants to Pending Equipment for PIU (Computer Request for Single Stage - One IBRD / 89980 Local Councils and Capacity Post Limited 75,000.00 0.00 Implementati 2021-05-30 2021-07-25 2021-10-23 Equipments (Laptops, Quotations Envelope Building on Desktops, Laser Printers, Multimedia Equipment) Page 1 PK-LGD -237546-GO-RFQ / Performance-based Grants to Pending Request for Single Stage - One Procurement of Furniture and IBRD / 89980 Local Councils and Capacity Post Limited 50,000.00 0.00 Implementati 2021-06-08 2021-08-03 2021-11-01 Quotations Envelope Fixture for DMC South office Building on PK-LGD -237549-GO-RFQ / Performance-based Grants to Pending Request for Single Stage - One Procurement of IT Equipment IBRD / 89980 Local Councils and Capacity Post Limited 30,000.00 0.00 Implementati 2021-06-08 2021-08-03 2021-10-02 Quotations Envelope for DMC South Office Building on PK-LGD -237551-GO-RFQ / Performance-based Grants to Pending Procurement of Office Request for Single Stage - One IBRD / 89980 Local Councils and Capacity Post Limited 20,000.00 0.00 Implementati 2021-06-08 2021-08-03 2021-10-02 Appliances and Machinery For Quotations Envelope Building on DMC South PK-LGD -237732-GO-RFQ / Performance-based Grants to Pending Request for Single Stage - One Procurement of Furniture and IBRD / 89980 Local Councils and Capacity Post Limited 50,000.00 0.00 Implementati 2021-06-09 2021-08-04 2021-11-02 Quotations Envelope Fixture for DMC Central office Building on PK-LGD -237746-GO-RFQ / Performance-based Grants to Request for Single Stage - One Procurement of IT Equipment IBRD / 89980 Local Councils and Capacity Post Limited 30,000.00 24,700.73 Signed 2021-06-09 2020-10-22 2021-08-04 2020-11-18 2021-10-03 Quotations Envelope for DMC Central Office Building PK-LGD -237785-GO-RFQ / Performance-based Grants to Pending Procurement of Office Request for Single Stage - One IBRD / 89980 Local Councils and Capacity Post Limited 20,000.00 0.00 Implementati 2021-06-09 2021-08-04 2021-10-03 Appliances and Machinery for Quotations Envelope Building on DMC Central office PK-LGD -237796-GO-RFQ / Performance-based Grants to Pending Request for Single Stage - One Procurement of Furniture and IBRD / 89980 Local Councils and Capacity Post Limited 50,000.00 0.00 Implementati 2021-06-09 2021-08-04 2021-11-02 Quotations Envelope Fixture for DMC East office Building on PK-LGD -237803-GO-RFQ / Performance-based Grants to Request for Single Stage - One Procurement of IT Equipment IBRD / 89980 Local Councils and Capacity Post Limited 30,000.00 26,429.24 Signed 2021-06-09 2020-10-29 2021-08-04 2020-11-18 2021-10-03 Quotations Envelope for DMC East Building PK-LGD -237875-GO-RFQ / Performance-based Grants to Pending Request for Single Stage - One Procurement of Furniture and IBRD / 89980 Local Councils and Capacity Post Limited 50,000.00 0.00 Implementati 2021-06-09 2021-08-04 2021-11-02 Quotations Envelope Fixture for DMC West office Building on PK-LGD -237877-GO-RFQ / Performance-based Grants to Pending Request for Single Stage - One Procurement of IT Equipment IBRD / 89980 Local Councils and Capacity Post Limited 30,000.00 0.00 Implementati 2021-06-09 2021-08-04 2021-10-03 Quotations Envelope for DMC West Office Building on PK-LGD -237900-GO-RFQ / Performance-based Grants to Pending Request for Single Stage - One Procurement of Furniture and IBRD / 89980 Local Councils and Capacity Post Limited 50,000.00 0.00 Implementati 2021-06-09 2021-08-04 2021-11-02 Quotations Envelope Fixture for DMC Malir office Building on PK-LGD -237901-GO-RFQ / Performance-based Grants to Pending Request for Single Stage - One Procurement of IT Equipment IBRD / 89980 Local Councils and Capacity Post Limited 30,000.00 0.00 Implementati 2021-06-09 2021-08-04 2021-10-03 Quotations Envelope for DMC Malir Office Building on PK-LGD -237908-GO-RFQ / Performance-based Grants to Pending Request for Single Stage - One Procurement of Furniture and IBRD / 89980 Local Councils and Capacity Post Limited 50,000.00 0.00 Implementati 2021-06-09 2021-08-04 2021-11-02 Quotations Envelope Fixture for DMC Korangi office Building on PK-LGD -237909-GO-RFQ / Performance-based Grants to Pending Request for Single Stage - One Procurement of IT Equipment IBRD / 89980 Local Councils and Capacity Post Limited 30,000.00 0.00 Implementati 2021-06-09 2021-08-04 2021-10-03 Quotations Envelope for DMC Korangi Office Building on PK-LGD -237910-GO-RFQ / Performance-based Grants to Pending Procurement of Office Request for Single Stage - One IBRD / 89980 Local Councils and Capacity Post Limited 20,000.00 0.00 Implementati 2021-06-09 2021-08-04 2021-10-03 Appliances and Machinery for Quotations Envelope Building on DMC Korangi office PK-LGD -237916-GO-RFQ / Performance-based Grants to Pending Procurement of Furniture and Request for Single Stage - One IBRD / 89980 Local Councils and Capacity Post Limited 50,000.00 0.00 Implementati 2021-06-09 2021-08-04 2021-11-02 Fixture for District Council Quotations Envelope Building on office PK-LGD -237917-GO-RFQ / Performance-based Grants to Pending Request for Single Stage - One Procurement of IT Equipment IBRD / 89980 Local Councils and Capacity Post Limited 30,000.00 0.00 Implementati 2021-06-09 2021-08-04 2021-10-03 Quotations Envelope for District Council Office Building on PK-LGD -237930-GO-RFQ / Performance-based Grants to Pending Request for Single Stage - One Procurement of Furniture and IBRD / 89980 Local Councils and Capacity Post Limited 15,000.00 0.00 Implementati 2021-06-09 2021-08-04 2021-11-02 Quotations Envelope Fixture for KMC office Building on PK-LGD -237931-GO-RFQ / Performance-based Grants to Pending Request for Single Stage - One Procurement of IT Equipment IBRD / 89980 Local Councils and Capacity Post Limited 20,000.00 0.00 Implementati 2021-06-09 2021-08-04 2021-10-03 Quotations Envelope for KMC Office Building on PK-LGD -237932-GO-RFQ / Performance-based Grants to Pending Procurement of Office Request for Single Stage - One IBRD / 89980 Local Councils and Capacity Post Limited 10,000.00 0.00 Implementati 2021-06-09 2021-08-04 2021-10-03 Appliances and Machinery for Quotations Envelope Building on KMC office NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-LGD -187689-NC-RFQ / PRE-POST CLEANING SURVEY Pending Technical Assistance for Solid Request for Single Stage - One OF NALLAH’S (THROUGH IBRD / 89980 Post Limited 19,000.00 0.00 Implementati 2020-08-11 2020-10-06 2020-12-05 Waste Management Quotations Envelope DRONE CAMERA AND / OR on PHYSICAL MEANS). CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 2 PK-LGD -187691-CS-CQS / Consultancy Services for Consultant Environmental and Social Technical Assistance for Solid Under IBRD / 89980 Post Qualification Limited 35,000.00 0.00 2020-08-06 2020-06-26 2020-08-20 2020-09-19 2020-10-24 2021-01-22 Baseline Survey under WB Waste Management Implementation Selection Environmental Social Safeguard Framework PK-LGD -188167-CS-QCBS / Hiring of Consultancy Services for GIS Mappinng of Karachi Performance-based Grants to Quality And Cost- Pending along with Utility mappinng IBRD / 89980 Local Councils and Capacity Prior Open - International 5,000,000.00 0.00 2020-08-10 2020-08-31 2020-10-14 2020-11-11 2020-12-11 2021-01-15 2021-02-19 2022-08-18 Based Selection Implementation and Own Source Revenue Building Survey for all the LCs of Karachi PK-LGD -188171-CS-QCBS / Hiring of Firm for designing comprehensive ERP System for LCs (KMC, DMCs and Dist Performance-based Grants to Council) with FMIS, HRMIS, Quality And Cost- Pending IBRD / 89980 Local Councils and Capacity Post Open - International 1,500,000.00 0.00 2020-11-02 2020-12-23 2021-02-05 2021-03-05 2021-04-04 2021-05-09 2021-06-13 2022-06-13 Asset Mannagement, Own Based Selection Implementation Building Source revenue and Budgeting and Complaint Redressal Mechannism.along with separate Website PK-LGD -201920-CS-QCBS / Consultancy Services For Performance-based Grants to Engineering Design and Quality And Cost- Under IBRD / 89980 Local Councils and Capacity Post Open - International 1,500,000.00 0.00 2020-11-30 2020-11-17 2020-12-21 2020-11-25 2021-02-03 2021-03-03 2021-04-02 2021-05-07 2021-06-11 2024-06-30 Supervision of Sub Projects Based Selection Implementation Building (Works) for Local Councils of Karachi PK-LGD -203742-CS-CQS / Consultancy Services for Preparation of Procurement Performance-based Grants to Consultant Pending Standard Operating IBRD / 89980 Local Councils and Capacity Post Qualification Open - National 100,000.00 0.00 2020-11-23 2020-12-14 2021-01-27 2021-02-26 2021-04-02 2021-09-29 Implementation Procedures (SOP's) for Local Building Selection Councils for Compliance with SPPRA Rules PK-LGD -201917-CS-CQS / Consultancy Services For Performance-based Grants to Consultant Under Design & Development of IBRD / 89980 Local Councils and Capacity Post Qualification Open - National 55,000.00 0.00 2020-11-23 2020-11-24 2020-12-14 2020-12-14 2021-01-27 2021-02-26 2021-04-02 2021-09-29 Implementation Websites for CLICK and Local Building Selection Councils in Karachi PK-LGD -201874-CS-CQS / Consultancy Services For Performance-based Grants to Consultant Under Annual Performance IBRD / 89980 Local Councils and Capacity Post Qualification Open - National 200,000.00 0.00 2020-11-23 2020-12-03 2020-12-14 2020-12-14 2021-01-27 2021-02-26 2021-04-02 2024-06-30 Implementation Assessment of Local Councils Building Selection in Karachi PK-LGD -203999-CS-CQS / Consultancy Services for Consultant Technical Assistance for Solid Pending Performance Management For IBRD / 89980 Post Qualification Open - National 300,000.00 0.00 2020-11-23 2020-12-14 2021-01-27 2021-02-26 2021-04-02 2022-04-02 Waste Management Implementation Sindh Solid Waste Selection Management Board (SSWMB) PK-LGD -203986-CS-CQS / Consultancy Services For Performance-based Grants to Consultant Under Engineering Design, Quality IBRD / 89980 Local Councils and Capacity Post Qualification Open - National 300,000.00 0.00 2020-11-23 2020-11-17 2020-12-14 2020-11-24 2021-01-27 2020-12-11 2021-02-26 2021-01-29 2021-04-02 2022-04-02 Implementation Control and Supervision of Building Selection Subprojects (Works) PK-LGD -227732-CS-CQS / Technical, Financial and Legal Consultancy and Transaction Advisory Services for Performance-based Solid Consultant Technical Assistance for Solid Pending Waste Management IBRD / 89980 Post Qualification Limited 150,000.00 0.00 2021-04-08 2021-04-22 2021-05-22 2021-06-26 2021-12-23 Waste Management Implementation for Selection Sindh Solid Waste Management Board for District Central and District Korangi of Karachi Division PK-LGD -235723-CS-CQS / Performance-based Grants to Consultant Pending Consultancy Services for IBRD / 89980 Local Councils and Capacity Post Qualification Limited 250,000.00 0.00 2021-05-25 2021-06-08 2021-07-08 2021-08-12 2022-08-12 Implementation Hiring of Legal firm Building Selection PK-LGD -235726-CS-CQS / Performance-based Grants to Consultant Pending Procurement of Data Entry IBRD / 89980 Local Councils and Capacity Post Qualification Open - National 50,000.00 0.00 2021-05-26 2021-06-16 2021-07-30 2021-08-29 2021-10-03 2022-04-01 Implementation Firm for ERP Building Selection INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-LGD -187695-CS-INDV / Technical Assistance Designing Comprehensive ERP System for Local Councils of Karachi (KMC, DMC’s And Performance-based Grants to Individual Pending Distt Council) With IFmis, IBRD / 89980 Local Councils and Capacity Post Consultant Limited 6,500.00 0.00 2020-08-06 2020-08-11 2020-09-01 2020-10-06 2021-04-04 Implementation Hrmis, Asset Management, Building Selection Own Source Revenue, Budgeting, Complaint Redressal Mechanism Along with Separate Website. PK-LGD -188165-CS-INDV / Technical Assistance / Individual Consultant for GIS Performance-based Grants to Individual Pending Mapping of Karachi along with IBRD / 89980 Local Councils and Capacity Post Consultant Limited 6,500.00 0.00 2020-08-10 2020-08-15 2020-09-05 2020-10-10 2021-04-08 Implementation Utility mapping for all the LCs Building Selection of Karachi ( Short Term Contract) PK-LGD -187856-CS-INDV / Performance-based Grants to Individual Pending Assistant Contract & IBRD / 89980 Local Councils and Capacity Post Consultant Open 50,830.00 0.00 2020-08-07 2020-09-25 2020-10-16 2020-11-20 2023-11-20 Implementation Procurement Specialist Building Selection Page 3 Performance-based Grants to Individual PK-LGD -187870-CS-INDV / Pending IBRD / 89980 Local Councils and Capacity Post Consultant Open 50,830.00 0.00 2020-08-07 2020-09-25 2020-10-16 2020-11-20 2023-11-20 Assistant Finance Manager Implementation Building Selection PK-LGD -187877-CS-INDV / Performance-based Grants to Individual Pending Environment Safeguard IBRD / 89980 Local Councils and Capacity Post Consultant Open 63,537.00 0.00 2020-08-07 2020-09-25 2020-10-16 2020-11-20 2023-11-20 Implementation Specialist Building Selection Performance-based Grants to Individual PK-LGD -187882-CS-INDV / Pending IBRD / 89980 Local Councils and Capacity Post Consultant Limited 63,537.00 0.00 2020-08-09 2020-08-14 2020-09-04 2020-10-09 2023-10-09 Communication Specialist Implementation Building Selection PK-LGD -187883-CS-INDV / Performance-based Grants to Individual Pending Monitoring & Evaluation IBRD / 89980 Local Councils and Capacity Post Consultant Limited 65,000.00 0.00 2020-08-09 2020-08-14 2020-09-04 2020-10-09 2023-10-09 Implementation Specialist Building Selection Performance-based Grants to Individual PK-LGD -187885-CS-INDV / Pending IBRD / 89980 Local Councils and Capacity Post Consultant Limited 25,415.00 0.00 2020-08-07 2020-08-12 2020-09-02 2020-10-07 2023-10-07 IT Support officer Implementation Building Selection PK-LGD -187875-CS-INDV / Performance-based Grants to Individual Pending Assistant Social Safeguard IBRD / 89980 Local Councils and Capacity Post Consultant Open 50,830.00 0.00 2020-08-07 2020-09-25 2020-10-16 2020-11-20 2023-11-20 Implementation Specialist Building Selection Performance-based Grants to Individual PK-LGD -187880-CS-INDV / Pending IBRD / 89980 Local Councils and Capacity Post Consultant Open 63,537.00 0.00 2020-08-07 2020-09-25 2020-10-16 2020-11-20 2023-11-20 Manager Technical (Civil) Implementation Building Selection PK-LGD -187850-CS-INDV / TECHNICAL ASSISTANCE / Individual Technical Assistance for Solid Pending FOCAL PERSON FOR SWEEP IBRD / 89980 Post Consultant Limited 7,000.00 0.00 2020-08-07 2020-08-12 2020-09-02 2020-10-07 2021-01-05 Waste Management Implementation NULLAH CLEANING (Short Selection Term Contract) PK-LGD -202053-CS-INDV / Performance-based Grants to Individual Under Geographic Information IBRD / 89980 Local Councils and Capacity Post Consultant Limited 102,000.00 0.00 2020-11-15 2020-11-17 2020-11-20 2020-12-11 2021-01-15 2024-06-30 Implementation System (GIS) Specialist Building Selection Performance-based Grants to Individual PK-LGD -203751-CS-INDV / Pending IBRD / 89980 Local Councils and Capacity Post Consultant Limited 63,537.00 0.00 2020-11-16 2020-11-21 2020-12-12 2021-01-16 2024-06-30 Social Safeguard Specialist Implementation Building Selection PK-LGD -203754-CS-INDV / Performance-based Grants to Individual Pending Assistant Environment IBRD / 89980 Local Councils and Capacity Post Consultant Limited 50,830.00 0.00 2020-11-16 2020-11-21 2020-12-12 2021-01-16 2024-06-30 Implementation Safeguard Specialist Building Selection PK-LGD -203755-CS-INDV / Performance-based Grants to Individual Pending Assistant Manager (Internal IBRD / 89980 Local Councils and Capacity Post Consultant Limited 50,830.00 0.00 2020-11-30 2020-12-05 2020-12-26 2021-01-30 2024-06-30 Implementation Audit) Building Selection PK-LGD -203757-CS-INDV / Performance-based Grants to Individual Pending Junior Communication IBRD / 89980 Local Councils and Capacity Post Consultant Limited 50,830.00 0.00 2020-11-16 2020-11-21 2020-12-12 2021-01-16 2024-06-30 Implementation Specialist Building Selection PK-LGD -203760-CS-INDV / Procurement and Contract Individual Technical Assistance for Solid Under Management Specialist for IBRD / 89980 Post Consultant Limited 65,000.00 0.00 2020-11-16 2020-11-18 2020-11-21 2020-12-12 2021-01-16 2024-06-30 Waste Management Implementation Sindh Solid Waste Selection Management Board (SSWMB) PK-LGD -203786-CS-INDV / Individual Technical Assistance for Solid Pending Financial Management IBRD / 89980 Post Consultant Limited 50,830.00 0.00 2020-11-30 2020-12-05 2020-12-26 2021-01-30 2024-06-30 Waste Management Implementation Specialist for SSWMB Selection PK-LGD -203787-CS-INDV / Individual Technical Assistance for Solid Under Environmental Safeguard IBRD / 89980 Post Consultant Limited 50,830.00 0.00 2020-11-16 2020-11-18 2020-11-21 2020-12-12 2021-01-16 2024-06-30 Waste Management Implementation Specialist For SSWMB Selection PK-LGD -203808-CS-INDV / Individual Technical Assistance for Solid Under Social Safeguard Specialist for IBRD / 89980 Post Consultant Limited 50,830.00 0.00 2020-11-16 2020-11-18 2020-11-21 2020-12-12 2021-01-16 2024-06-30 Waste Management Implementation SSWMB Selection PK-LGD -203996-CS-INDV / Individual Technical Assistance for Solid Pending Waste to Energy Specialist For IBRD / 89980 Post Consultant 50,830.00 0.00 2020-11-30 2020-12-05 2020-12-26 2021-01-30 2024-06-30 Waste Management Implementation SSWMB Selection PK-LGD -204015-CS-INDV / Individual Technical Assistance for Solid Pending Solid Waste Management IBRD / 89980 Post Consultant Limited 50,830.00 0.00 2020-11-30 2020-12-05 2020-12-26 2021-01-30 2024-06-30 Waste Management Implementation Specialist for SSWMB Selection Performance-based Grants to Individual PK-LGD -204017-CS-INDV / Under IBRD / 89980 Local Councils and Capacity Post Consultant Limited 65,000.00 0.00 2020-11-16 2020-11-17 2020-11-21 2020-12-12 2021-01-16 2024-06-30 Financial Advisor For PPP Unit Implementation Building Selection Performance-based Grants to Individual PK-LGD -204018-CS-INDV / Under IBRD / 89980 Local Councils and Capacity Post Consultant Limited 65,000.00 0.00 2020-11-16 2020-11-17 2020-11-21 2020-12-12 2021-01-16 2024-06-30 Technical Advisor For PPP Unit Implementation Building Selection Performance-based Grants to Individual PK-LGD -204022-CS-INDV / Under IBRD / 89980 Local Councils and Capacity Post Consultant Limited 65,000.00 0.00 2020-11-16 2020-11-17 2020-11-21 2020-12-12 2021-01-16 2024-06-30 Legal Advisor for PPP Unit Implementation Building Selection Performance-based Grants to Individual PK-LGD -207879-CS-INDV / Pending IBRD / 89980 Local Councils and Capacity Post Consultant Limited 32,000.00 0.00 2020-12-10 2020-12-15 2021-01-05 2021-02-09 2022-02-09 ERP Specialist Implementation Building Selection PK-LGD -186638-CS-CDS / Consultancy Services for Third Technical Assistance for Solid Pending Party Monitoring and Spot IBRD / 89980 Post Direct Selection Direct 200,000.00 0.00 2020-07-30 2020-08-09 2020-10-13 2021-01-11 Waste Management Implementation Checking of Nala Cleaning Work at Karachi Page 4 PROCUREMENT PLAN Project information: Uganda, East Africa Skills for Transformation and Regional Integration Project (EASTRIP) P163399 Project Implementation agency: Inter-University Council for East Africa Date of the Procurement Plan: April 27, 2018 Period covered by this Procurement Plan: May 2018- January 2019 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international and national competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: As IUCEA does not follow Uganda PPDA, when approaching the national market (as specified in the Procurement Plan tables in STEP), Bank’s Procurement Regulations will be followed. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations –Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is applicable for those contracts identified in the Procurement Plan tables; Works: is applicable for those contracts identified in the Procurement Plan tables Other Relevant Procurement Information. None PROCUREMENT Eastern Africa : East Africa Skills for Transformation and Regional Integration Project (EASTRIP) PLAN General Information Country: Eastern Africa Bank’s Approval Date of the Original Procurement Plan: 2019-03-14 2021-05-24 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P163399 GPN Date: 2019-08-06 Project Name: East Africa Skills for Transformation and Regional Integration Project (EASTRIP) Loan / Credit No: IDA / 63350, IDA / D3950 G Executing Agency(ies): eneral Wingate Polytechnic College WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Strengthening selected GW/NCB/W/01/2019 / Regional Flagship TVET Pending Construction of workshops Single Stage - One 2020-07- IDA / 63350 Institutes for high quality Prior Request for Bids Open - National 5,321,000.00 0.00 Implementat 2019-10-01 2019-10-06 2019-11-17 2019-12-17 2020-01-21 admin offices, clinic, staff and Envelope 19 skills development in priority ion trainee's lounge and walkway sectors Strengthening selected GW/NCB/W/02/2019 / Regional Flagship TVET Pending Single Stage - One 2020-05- Maintenance of existing IDA / 63350 Institutes for high quality Post Request for Bids Open - National 450,000.00 0.00 Implementat 2019-08-01 2019-08-06 2019-09-17 2019-10-17 2019-11-21 Envelope 19 workshop skills development in priority ion sectors ET-ET WINGATE-212240-NC- Strengthening selected RFQ / Procurement of supply Regional Flagship TVET Under Request for Single Stage - One 2021-02- and fix partition wall on the IDA / 63350 Institutes for high quality Post Limited 3,700.00 0.00 Implementat 2021-01-16 2021-01-13 2021-02-09 Quotations Envelope 19 existing building for gender skills development in priority ion unit office sectors GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Strengthening selected GW/NCB/G/02/2019 / Regional Flagship TVET Pending Single Stage - One Supply, installation, and IDA / 63350 Institutes for high quality Post Request for Bids Open - National 200,000.00 0.00 Implementati 2019-06-20 2019-06-25 2019-08-06 2019-09-05 2019-10-10 2020-04-07 Envelope integration of network system skills development in priority on sectors Strengthening selected Regional Flagship TVET Pending GW/NCB/G/03/2019 / Office Single Stage - One IDA / 63350 Institutes for high quality Post Request for Bids Open - National 500,000.00 0.00 Implementati 2019-06-20 2019-06-25 2019-08-06 2019-09-05 2019-10-10 2020-04-07 & workshop furniture Envelope skills development in priority on sectors Strengthening selected Regional Flagship TVET Pending GW/NCB/G/04/2019 / IT and Single Stage - One IDA / 63350 Institutes for high quality Post Request for Bids Open - National 520,000.00 0.00 Implementati 2019-06-28 2019-07-03 2019-08-14 2019-09-13 2019-10-18 2020-04-15 Office Equipment Envelope skills development in priority on sectors Strengthening selected Regional Flagship TVET Pending GW/NCB/G/05/2019 / Digital Single Stage - One IDA / 63350 Institutes for high quality Post Request for Bids Open - National 263,000.00 0.00 Implementati 2020-06-01 2020-06-06 2020-07-18 2020-08-17 2020-09-21 2021-03-20 Library Envelope skills development in priority on sectors Strengthening selected Regional Flagship TVET Pending Single Stage - One GW/NCB/G/07/2019 / Books IDA / 63350 Institutes for high quality Post Request for Bids Open - National 100,000.00 0.00 Implementati 2019-08-05 2019-08-10 2019-09-21 2019-10-21 2019-11-25 2020-05-23 Envelope skills development in priority on sectors Strengthening selected Regional Flagship TVET Pending GW/NCB/G/08/2019 / Request for Single Stage - One IDA / 63350 Institutes for high quality Post Limited 80,000.00 0.00 Implementati 2019-09-07 2019-11-02 2020-04-30 medical supplies Quotations Envelope skills development in priority on sectors Strengthening selected Regional Flagship TVET Pending GW/NCB/G/09/2019 / Single Stage - One IDA / 63350 Institutes for high quality Post Request for Bids Open - National 110,000.00 0.00 Implementati 2021-04-01 2021-04-06 2021-05-18 2021-06-17 2021-07-22 2022-01-18 kitchen tools and equipment Envelope skills development in priority on sectors Strengthening selected Regional Flagship TVET Pending GW/NCB/G/06/2019 / Request for Single Stage - One IDA / 63350 Institutes for high quality Post Open - National 20,000.00 0.00 Implementati 2019-09-07 2019-11-02 2020-04-30 Personal protective equipment Quotations Envelope skills development in priority on sectors Strengthening selected GW/ICB/G/01/2019 / Regional Flagship TVET Pending Single Stage - One Procurement of Workshop IDA / 63350 Institutes for high quality Prior Request for Bids Open - International 2,280,000.00 0.00 Implementati 2019-06-20 2019-06-25 2019-08-06 2019-09-05 2019-10-10 2020-04-07 Envelope Equipment skills development in priority on sectors Strengthening selected ET-ET WINGATE-206172-GO- Regional Flagship TVET Under RFQ / Procurement of ICT and Request for Single Stage - One IDA / 63350 Institutes for high quality Post Limited 70,000.00 0.00 Implementati 2020-12-04 2020-12-10 2020-12-28 2021-01-12 Office Equipment for PIU and Quotations Envelope skills development in priority on Administrative staff sectors Strengthening selected ET-ET WINGATE-206584-GO- Regional Flagship TVET Under RFQ / Procurement of office Request for Single Stage - One IDA / 63350 Institutes for high quality Post Limited 20,000.00 0.00 Implementati 2020-12-04 2020-12-15 2020-12-30 2021-01-06 furniture for administrative Quotations Envelope skills development in priority on and PIU staff sectors Page 1 ET-ET WINGATE-229637-GO- Strengthening selected RFB / Procurement of Regional Flagship TVET Pending Single Stage - Two Equipment for Electrical IDA / 63350 Institutes for high quality Post Request for Bids Open - International 1,150,000.00 0.00 Implementati 2021-05-15 2021-06-29 2021-07-04 2021-09-16 2021-10-21 2022-02-18 Envelope Laboratory Workstation for on skills development in priority on going trainings sectors ET-ET WINGATE-233737-GO- Strengthening selected RFQ / Procurement of tools Regional Flagship TVET Pending Request for Single Stage - One and equipment for existing IDA / 63350 Institutes for high quality Post Limited 14,200.00 0.00 Implementati 2021-05-22 2021-07-08 2021-07-22 Quotations Envelope electrical maintenance skills development in priority on workshop sectors ET-ET WINGATE-231689-GO- Strengthening selected RFB / Procurement of Regional Flagship TVET Pending Request for Single Stage - One Supply,Installation and IDA / 63350 Institutes for high quality Post Limited 100,000.00 0.00 Implementati 2021-05-15 2021-07-03 2021-07-17 Quotations Envelope Commissioning of Heavy Duty skills development in priority on Silent Generator sectors ET-ET WINGATE-235716-GO- Strengthening selected RFQ / Procurement of ICT Regional Flagship TVET Pending Request for Single Stage - One equipment for on-going IDA / 63350 Institutes for high quality Post Limited 100,000.00 0.00 Implementati 2021-06-01 2021-07-02 2021-07-12 Quotations Envelope trainings of General Wingate skills development in priority on Polytechnic College sectors ET-ET WINGATE-235733-GO- Strengthening selected RFB / Procurement of Regional Flagship TVET Pending Single Stage - One furniture for on-going IDA / 63350 Institutes for high quality Post Request for Bids Open - National 120,000.00 0.00 Implementati 2021-06-07 2021-06-21 2021-07-21 2021-08-11 2021-09-15 2021-10-15 Envelope training of General Wingate skills development in priority on Polytechnic College. sectors NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-ET WINGATE-206963-NC- Strengthening selected RFQ / Procurement of 15 Regional Flagship TVET Under Minutes base line Request for Single Stage - One IDA / 63350 Institutes for high quality Post Limited 10,000.00 0.00 Implementati 2020-12-13 2021-01-20 2021-02-07 2021-04-08 documentary video Quotations Envelope skills development in priority on production on GWPTC and on sectors its electrical and digitization center. CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Strengthening selected GW/QCBS/CS/01/2019 / Regional Flagship TVET Quality And Cost- Under Design, supervision and IDA / 63350 Institutes for high quality Post Open - National 250,000.00 0.00 2019-09-02 2020-07-22 2019-09-23 2020-08-03 2019-11-06 2020-11-23 2019-12-04 2020-12-24 2020-01-03 2020-02-07 2020-03-13 2021-03-13 Based Selection Implementation contract Administration skills development in priority sectors Strengthening selected GW/QCS/CS/12/2019 / Regional Flagship TVET Consultant Pending consultants for equipment IDA / 63350 Institutes for high quality Post Qualification Open - International 225,000.00 0.00 2019-06-24 2019-07-15 2019-08-28 2019-09-27 2019-11-01 2020-04-29 Implementation specification development skills development in priority Selection sectors Strengthening selected ET-ET WINGATE-206967-CS- Regional Flagship TVET QCBS / Consultancy services Quality And Cost- Pending IDA / 63350 Institutes for high quality Post Open - National 225,000.00 0.00 2020-12-24 2021-01-14 2021-02-27 2021-03-27 2021-04-26 2021-05-31 2021-07-05 2022-07-05 for the institutes strategic Based Selection Implementation skills development in priority plan development . sectors Strengthening selected ET-ET WINGATE-206925-CS- Regional Flagship TVET Consultant CQS / Consultancy service for Under IDA / 63350 Institutes for high quality Post Qualification Open - National 60,000.00 0.00 2020-12-24 2020-12-17 2021-01-14 2021-02-27 2021-03-13 2021-04-06 2021-06-05 labor market assessment for Implementation skills development in priority Selection energy sector of Ethiopia. sectors ET-ET WINGATE-208703-CS- Strengthening selected CQS / Consultancy service for Regional Flagship TVET Consultant Under conducting skill gap IDA / 63350 Institutes for high quality Post Qualification Open - National 15,000.00 0.00 2020-12-31 2021-02-28 2021-01-21 2021-02-25 2021-03-18 2021-04-15 2021-06-14 Implementation assessment of industry skills development in priority Selection workers. sectors ET-ET WINGATE-206975-CS- CQS / Consultancy service for Strengthening selected conducting skill gap Regional Flagship TVET Consultant assessment and identification Under IDA / 63350 Institutes for high quality Post Qualification Open - National 38,000.00 0.00 2020-12-31 2021-02-28 2021-01-21 2021-03-06 2021-04-05 2021-05-10 2021-11-06 of occupations and Implementation skills development in priority Selection qualifications of College sectors managers, leaders and trainers. ET-ET WINGATE-206980-CS- Strengthening selected CQS / Consultancy service for Regional Flagship TVET Consultant conducting problem focused Under IDA / 63350 Institutes for high quality Post Qualification Open - National 15,000.00 0.00 2020-12-25 2021-03-24 2021-01-15 2021-02-28 2021-03-30 2021-05-04 2021-10-31 research for project Implementation skills development in priority Selection beneficiary manufacturing sectors industries in Addis Ababa. ET-ET WINGATE-231220-CS- CQS / Procurement of Design Strengthening selected and Develop Website, Regional Flagship TVET Consultant Under Registrar system and E- IDA / 63350 Institutes for high quality Post Qualification Open - National 30,000.00 0.00 2021-04-29 2021-04-23 2021-05-20 2021-06-17 2021-07-08 2021-08-12 2021-10-11 Implementation learning platform for General skills development in priority Selection Wingate polytechnic College ( sectors GWPTC) ET-ET WINGATE-233733-CS- Strengthening selected CQS / Consultancy service for Regional Flagship TVET Consultant Pending conducting tracer study of IDA / 63350 Institutes for high quality Post Qualification Open - National 50,000.00 0.00 2021-05-14 2021-05-28 2021-06-25 2021-07-16 2021-08-20 2021-10-04 Implementation General Wingate Polytechnic skills development in priority Selection College sectors Page 2 INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Strengthening selected GW/IC/CS/02/2019 / "Project Regional Flagship TVET Individual Manager IDA / 63350 Institutes for high quality Post Consultant Open 110,000.00 1,438.78 Signed 2019-03-20 2019-06-26 2019-05-08 2020-06-01 2019-05-29 2020-06-11 2019-07-03 2020-06-15 2019-12-30 skills development in priority Selection " sectors Strengthening selected Regional Flagship TVET Individual GW/IC/CS/03/2019 / Deputy Under IDA / 63350 Institutes for high quality Post Consultant Open 95,000.00 0.00 2019-03-20 2020-12-16 2019-05-08 2019-05-29 2019-07-03 2019-12-30 project manager Implementation skills development in priority Selection sectors Strengthening selected Regional Flagship TVET Individual GW/IC/CS/04/2019 / IDA / 63350 Institutes for high quality Prior Consultant Open 95,000.00 0.00 Canceled 2019-03-20 2019-05-10 2019-05-08 2019-05-29 2019-07-03 2019-12-30 Procurement specialist skills development in priority Selection sectors Strengthening selected GW/IC/CS/06/2019 / Regional Flagship TVET Individual Financial management IDA / 63350 Institutes for high quality Post Consultant Open 95,000.00 0.00 Canceled 2019-03-20 2019-06-26 2019-05-08 2019-05-29 2019-07-03 2019-12-30 specialist skills development in priority Selection sectors Strengthening selected GW/IC/CS/09/2019 / Regional Flagship TVET Individual Under Monitoring and Evaluation IDA / 63350 Institutes for high quality Post Consultant Open 75,000.00 0.00 2019-03-20 2019-06-26 2019-05-08 2019-05-29 2019-07-03 2019-12-30 Implementation officer skills development in priority Selection sectors Strengthening selected Regional Flagship TVET Individual GW/IC/CS/11/2019 / Under IDA / 63350 Institutes for high quality Post Consultant Open 100,000.00 0.00 2019-06-03 2020-07-22 2019-07-22 2020-11-11 2019-08-12 2020-11-11 2019-09-16 2020-03-14 contract administration staff Implementation skills development in priority Selection sectors Strengthening selected GW/IC/CS/10/2019 / Regional Flagship TVET Individual Under Environmental and social IDA / 63350 Institutes for high quality Post Consultant Open 60,000.00 0.00 2019-05-28 2019-06-26 2019-07-16 2019-08-06 2019-09-10 2020-03-08 Implementation safeguard specialist skills development in priority Selection sectors Strengthening selected Regional Flagship TVET Individual GW/IC/CS/07/2019 / IDA / 63350 Institutes for high quality Post Consultant Open 80,000.00 0.00 Canceled 2019-03-20 2019-05-08 2019-05-29 2019-07-03 2019-12-30 Accountant skills development in priority Selection sectors Strengthening selected Regional Flagship TVET Individual GW/IC/CS/05/2019 / IDA / 63350 Institutes for high quality Prior Consultant Open 80,000.00 0.00 Canceled 2019-03-20 2019-05-08 2019-05-29 2019-07-03 2019-12-30 Procurement officer skills development in priority Selection sectors Strengthening selected Regional Flagship TVET Individual GW/IC/CS/08/2019 / Internal IDA / 63350 Institutes for high quality Post Consultant Open 65,000.00 0.00 Canceled 2019-12-02 2020-01-20 2020-02-10 2020-03-16 2020-09-12 auditor skills development in priority Selection sectors Strengthening selected Regional Flagship TVET Individual GW/IC/CS/13/2019 / Under IDA / 63350 Institutes for high quality Post Consultant Open 65,000.00 0.00 2019-05-28 2019-06-26 2019-07-16 2019-08-06 2019-09-10 2020-03-08 Industry liaise officer Implementation skills development in priority Selection sectors Strengthening selected Regional Flagship TVET Individual GW/IC/CS/14/2020 / IDA / 63350 Institutes for high quality Prior Consultant Limited 95,000.00 0.00 Canceled 2020-03-16 2020-04-16 2020-03-21 2020-04-15 2020-04-11 2020-07-24 2020-05-16 2020-11-12 procurement Specialist skills development in priority Selection sectors Strengthening selected GW/IC/CS/15/2020 / Regional Flagship TVET Individual Financial Management IDA / 63350 Institutes for high quality Post Consultant Limited 95,000.00 814.90 Signed 2020-03-16 2020-03-26 2020-03-21 2020-03-27 2020-04-11 2020-05-15 2020-05-16 2020-06-15 2020-11-12 Specialist skills development in priority Selection sectors Strengthening selected GW/IC/CS/16/2020 / Regional Flagship TVET Individual Under Monitoring and Evaluation IDA / D3950 Institutes for high quality Post Consultant Open 75,000.00 0.00 2020-05-06 2020-05-08 2020-06-24 2020-09-25 2020-07-15 2020-08-19 2021-02-15 Implementation Officer skills development in priority Selection sectors Strengthening selected Regional Flagship TVET Individual GW/IC/CS/17/2020 / Under IDA / 63350 Institutes for high quality Post Consultant Open 65,000.00 0.00 2020-05-06 2020-05-08 2020-06-24 2020-07-15 2020-08-19 2021-02-15 Industry liaison officer Implementation skills development in priority Selection sectors Strengthening selected GW/IC/CS/18/2020 / Regional Flagship TVET Individual Under Environmental and Social IDA / 63350 Institutes for high quality Post Consultant Open 60,000.00 0.00 2020-05-04 2020-05-08 2020-06-22 2020-07-13 2020-08-17 2021-02-13 Implementation safeguard specialist skills development in priority Selection sectors Strengthening selected GW/IC/CS/14/2020-R / Regional Flagship TVET Individual Selection of Procurement IDA / 63350 Institutes for high quality Prior Consultant Limited 95,000.00 17,835.16 Signed 2020-10-16 2020-10-20 2020-10-21 2020-10-26 2020-10-31 2020-11-22 2020-11-11 2020-11-23 2021-11-06 Specialist skills development in priority Selection sectors Strengthening selected ET-ET WINGATE-208885-CS- Regional Flagship TVET Individual INDV / Consultancy service Under IDA / 63350 Institutes for high quality Post Consultant Open 95,000.00 0.00 2020-12-24 2020-12-14 2021-02-02 2021-02-16 2021-03-16 2022-03-16 for Financial Management Implementation skills development in priority Selection Specialist sectors Page 3 PROCUREMENT PLAN Project information: Sint Maarten Emergency Debris Management Project (P167347) Project Implementation agency: NRPB Date of the Procurement Plan: 04/18/2020 Period covered by this Procurement Plan: April 2020 to April 2022 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: [is applicable for those contracts identified in the Procurement Plan tables]; Works: [is applicable for those contracts identified in the Procurement Plan tables] Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. PROCUREMENT St Maarten : Sint Maarten Emergency Debris Management Project PLAN General Information Country: St Maarten Bank’s Approval Date of the Original Procurement Plan: 2019-08-21 2021-05-24 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P167347 GPN Date: Project Name: Sint Maarten Emergency Debris Management Project Loan / Credit No: TF / A9261 National Recovery Program Bureau Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned SX-NRPB-140867-CW-RFB / Debris Clearance and Single Stage - One 12,220,000. 2020-08- Ship salvaging and shoreline TF / A9261 Prior Request for Bids Open - International 2,850,000.00 Signed 2019-10-25 2019-11-11 2019-10-25 2019-11-13 2019-12-06 2020-02-17 2020-01-05 2020-09-29 2020-02-09 2021-02-22 Management Envelope 00 07 debris clearance Pending SX-NRPB-159745-CW-RFB / Debris Clearance and Single Stage - One 2021-01- TF / A9261 Post Request for Bids Open - National 500,000.00 0.00 Implementat 2020-03-18 2020-03-23 2020-05-04 2020-06-03 2020-07-08 Access road to TDSR Management Envelope 04 ion SX-NRPB-226241-CW-RFB / TDSR - Roads installation, Pending temporary debris storage and Debris Clearance and Single Stage - One 2022-05- TF / A9261 Post Request for Bids Open - International 7,000,000.00 0.00 Implementat 2021-07-18 2021-07-23 2021-09-03 2021-10-03 2021-11-07 reduction equipment Management Envelope 06 ion purchase and Installation: including Tire Shredder, Wood Chipper, SX-NRPB-142837-CW-RFB / Pending Debris Clearance and Single Stage - One 2020-09- Car wreck removal and TF / A9261 Post Request for Bids Open - International 500,000.00 0.00 Implementat 2019-11-29 2019-12-04 2020-01-15 2020-02-14 2020-03-20 Management Envelope 16 disposal ion GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SX-NRPB-126809-GO-DIR / Debris Clearance and TF / A9261 Prior Direct Selection Direct 600,000.00 0.00 Canceled 2019-08-12 2019-08-17 2019-09-21 2020-03-19 Landfill COmpactor Management SX-NRPB-126810-GO-DIR / Debris Clearance and TF / A9261 Prior Direct Selection Direct 600,000.00 600,000.00 Signed 2019-08-12 2019-10-18 2019-08-17 2019-11-14 2019-09-21 2019-10-08 2020-03-19 D8T Waste Handling Bulldozer Management SX-NRPB-126833-GO-RFQ / Debris Clearance and Request for Single Stage - One TF / A9261 Post Limited 3,000.00 0.00 Canceled 2019-08-12 2019-08-13 2019-10-11 2020-04-08 Oil, Fuel and anti-freeze Management Quotations Envelope Pending SX-NRPB-141416-GO-RFB / Debris Clearance and Request for Single Stage - One TF / A9261 Post Open - International 150,000.00 0.00 Implementati 2019-12-02 2019-12-07 2020-01-18 2020-02-17 2020-03-23 2020-09-19 Weighbridge Management Quotations Envelope on Pending SX-NRPB-152796-GO-RFQ / Debris Clearance and Request for Single Stage - One TF / A9261 Post Limited 220,000.00 0.00 Implementati 2020-01-11 2020-03-07 2020-09-03 Wheel-Loader Equipment Management Quotations Envelope on SX-NRPB-126809-GO-RFQ / Debris Clearance and Request for Single Stage - One TF / A9261 Prior Limited 600,000.00 0.00 Canceled 2020-04-22 2020-06-17 2020-12-14 Landfill Compactor Management Quotations Envelope SX-NRPB-169181-GO-DIR / Debris Clearance and TF / A9261 Prior Direct Selection Direct 35,000.00 34,050.00 Signed 2020-04-17 2021-03-25 2020-04-22 2021-03-29 2020-05-27 2020-04-07 2020-11-23 Posi-Shell Management SX-NRPB-184298-GO-DIR / Debris Clearance and TF / A9261 Post Direct Selection Direct 800,000.00 738,000.00 Signed 2020-07-20 2020-07-01 2020-07-25 2020-06-23 2020-08-29 2020-10-30 2021-02-25 Landfill Waste Compactor Management SX-NRPB-179886-GO-RFQ / Debris Clearance and Request for Single Stage - One TF / A9261 Post Open - National 50,000.00 0.00 Canceled 2020-06-17 2020-08-12 2021-02-08 2 40ft storage containers Management Quotations Envelope SX-NRPB-142850-GO-RFQ / Debris Clearance and Request for Single Stage - One TF / A9261 Post Open - International 100,000.00 0.00 Canceled 2019-12-04 2020-01-29 2020-07-27 Tire Shredder Management Quotations Envelope SX-NRPB-142847-GO-RFQ / Debris Clearance and Request for Single Stage - One TF / A9261 Post Open - International 50,000.00 0.00 Canceled 2019-12-04 2020-01-29 2020-07-27 Wood chipper Management Quotations Envelope SX-NRPB-141408-GO-RFQ / Pending Debris Clearance and Request for Single Stage - One Storage containers with TF / A9261 Post Open - National 50,000.00 0.00 Implementati 2019-11-13 2020-01-08 2020-07-06 Management Quotations Envelope climate control on SX-NRPB-226244-GO-RFQ / Project Management and Request for Single Stage - One Purchase of Portland Cement TF / A9261 Post Limited 50,000.00 0.00 Canceled 2021-04-10 2021-06-05 2021-12-02 Implementation Support Quotations Envelope Class 1 Pending SX-NRPB-142843-GO-DIR / Debris Clearance and TF / A9261 Post Direct Selection Direct 150,000.00 0.00 Implementati 2020-01-06 2020-01-11 2020-02-15 2020-08-13 Personal Protective Equipment Management on Pending SX-NRPB-229732-GO-DIR / Debris Clearance and TF / A9261 Post Direct Selection Direct 30,000.00 0.00 Implementati 2021-04-20 2021-04-25 2021-05-30 2021-11-26 Front Loader Bucket: RIMCO Management on Pending SX-NRPB-235566-GO-DIR / Project Management and TF / A9261 Post Direct Selection Direct 50,000.00 0.00 Implementati 2021-05-21 2021-05-26 2021-06-30 2021-12-27 Purchase of Portland Cement Implementation Support on NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 1 SX-NRPB-169182-NC-DIR / Pending Project Management and Heavy Equipment TF / A9261 Post Direct Selection Direct 100,000.00 0.00 Implementati 2020-04-17 2020-04-22 2020-05-27 2020-11-23 Implementation Support Maintenance: RIMCO on SX-NRPB-225232-NC-DIR / Under Project Management and Heavy Equipment TF / A9261 Post Direct Selection Direct 10,000.00 0.00 Implementati 2021-03-18 2021-03-17 2021-03-23 2021-03-18 2021-04-27 2021-10-24 Implementation Support Maintenance: JMP on Hydraulique CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SX-NRPB-140869-CS-QCBS / Debris Clearance and Quality And Cost- Supervision Ship Salvaging TF / A9261 Prior Open - International 300,000.00 1,486,745.00 Signed 2019-10-25 2019-11-16 2019-11-15 2019-11-18 2019-12-29 2020-03-30 2020-01-26 2020-05-08 2020-02-25 2020-09-29 2020-03-31 2021-01-21 2020-05-05 2021-02-12 2021-05-05 Management Based Selection and Shoreline Debris SX-NRPB-142839-CS-QCBS / Debris Clearance and Quality And Cost- Pending Supervision car wreck removal TF / A9261 Post Open - International 100,000.00 0.00 2019-11-29 2019-12-20 2020-02-02 2020-03-01 2020-03-31 2020-05-05 2020-06-09 2021-06-09 Management Based Selection Implementation and disposal SX-NRPB-140864-CS-QCBS / Quality And Cost- TF / A9261 Technical Assistance Post Open - International 50,000.00 0.00 Canceled 2020-01-14 2020-02-04 2020-03-19 2020-04-16 2020-05-16 2020-06-20 2020-07-25 2021-07-25 Draft Medical Waste Policy Based Selection Consultant SX-NRPB-142855-CS-CQS / Debris Clearance and TF / A9261 Post Qualification Limited 300,000.00 249,990.00 Signed 2019-11-22 2021-04-14 2019-12-06 2021-04-19 2020-01-05 2021-04-20 2020-02-09 2019-05-06 2020-08-07 Resettlement Action Plan Management Selection SX-NRPB-210410-CS-NPO / Debris Clearance and Non-Profit TF / A9261 Post Direct 100,000.00 33,190.00 Signed 2020-12-18 2021-04-01 2021-01-29 2021-04-01 2021-03-05 2021-04-22 2021-09-01 Environmental Monitoring Management Organizations SX-NRPB-146735-CS-QCBS / Quality And Cost- Pending Vector control plan and tools TF / A9261 Technical Assistance Post Open - International 250,000.00 0.00 2020-01-27 2020-02-17 2020-04-01 2020-04-29 2020-05-29 2020-07-03 2020-08-07 2021-08-07 Based Selection Implementation + Supervision for TDSR INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SX-NRPB-135800-CS-CDS / Project Management and TF / A9261 Post Direct Selection Direct 80,000.00 131,806.58 Signed 2019-09-25 2019-08-06 2019-10-05 2019-08-14 2019-12-09 2020-01-20 2020-06-06 Resettlement expert Implementation Support SX-NRPB-142854-CS-CDS / Debris Clearance and TF / A9261 Prior Direct Selection Direct 1,000,000.00 938,168.00 Signed 2019-10-25 2020-08-10 2019-11-04 2019-03-12 2020-01-08 2019-05-20 2020-07-06 ESIA Fire Suppression Management Individual SX-NRPB-159742-CS-INDV / Project Management and Under TF / A9261 Post Consultant Open 150,000.00 0.00 2020-02-17 2020-03-27 2020-04-06 2021-05-04 2020-04-27 2020-06-01 2020-11-28 Project Engineer Implementation Support Implementation Selection SX-NRPB-179890-CS-CDS / Interim Resettlement Expert TF / A9261 Technical Assistance Post Direct Selection Direct 5,000.00 9,000.00 Signed 2020-06-12 2020-06-11 2020-06-22 2019-08-18 2020-08-26 2020-06-19 2021-02-22 Contract SX-NRPB-187037-CS-CDS / Project Management and TF / A9261 Post Direct Selection Direct 65,000.00 76,200.00 Signed 2020-08-03 2020-08-06 2020-08-13 2020-08-06 2020-10-17 2020-08-26 2021-04-15 Interim Project Manager Implementation Support Individual SX-NRPB-192966-CS-INDV / Debris Clearance and Under TF / A9261 Post Consultant Open 20,000.00 0.00 2020-09-14 2020-11-12 2020-11-02 2020-11-23 2020-12-28 2021-06-26 Pre-design TDSR site Management Implementation Selection SX-NRPB-220241-CS-INDV / Individual Strategic Programme Project Management and Under TF / A9261 Post Consultant Open 250,000.00 0.00 2021-03-01 2021-02-25 2021-04-19 2021-05-06 2021-05-10 2021-06-11 2021-06-14 2021-12-11 Coordinator Waste Implementation Support Implementation Selection Management Individual SX-NRPB-142851-CS-INDV / Pending TF / A9261 Technical Assistance Post Consultant Open 50,000.00 0.00 2020-01-06 2020-02-24 2020-03-16 2020-04-20 2020-10-17 Draft Medical Waste policy Implementation Selection Individual SX-NRPB-227298-CS-INDV / Project Management and Pending TF / A9261 Post Consultant Open 150,000.00 0.00 2021-04-09 2021-05-12 2021-05-22 2021-05-25 2021-11-21 Resettlement Coordinator Implementation Support Implementation Selection SX-NRPB-228360-CS-CDS / Project Management and Under Interim Contract Project TF / A9261 Post Direct Selection Direct 10,000.00 0.00 2021-04-09 2021-04-13 2021-04-19 2021-04-07 2021-06-23 2021-12-20 Implementation Support Implementation Manager Individual SX-NRPB-231294-CS-INDV / Project Management and Under TF / A9261 Post Consultant Direct 180,000.00 0.00 2021-04-23 2021-04-29 2021-05-03 2021-05-10 2021-05-14 2022-05-09 Resettlement Coordinator Implementation Support Implementation Selection SX-NRPB-232744-CS-CDS / Project Management and Under Interim Remote Resettlement TF / A9261 Post Direct Selection Direct 15,000.00 0.00 2021-05-03 2021-05-05 2021-05-13 2021-05-25 2021-07-17 2022-01-13 Implementation Support Implementation Specialist SX-NRPB-237087-CS-CDS / Project Management and Under Interim remote - Program TF / A9261 Post Direct Selection Direct 16,500.00 0.00 2021-05-28 2021-06-01 2021-06-07 2021-06-07 2021-08-11 2022-02-07 Implementation Support Implementation Coordinator Waste Page 2 PROCUREMENT PLAN General 1. Project Information a. Country: Federal Republic of Somalia b. Project Name: Water For Agro-Pastoral and Reselience Productivity c. Project Number: P167826 d. Total Finance: USD 5 Million 2. Project Implementation Agency: South West State of Somalia 3. Date of Project Plan: October 2018 4. Period Covered by this Procurement: January 2019 – June 2020 I. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016 revised November 2017 and August 2018) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. II. Bank’s Standard Procurement Document: The Bank’s standard Procurement Documents shall be used for all contracts subject to international competitive procurement and those contracts as specified into Procurement Plan tables in STEP III. National Procurement Arrangements: Not applicable IV. Prequalification: Not applicable V. Leased Assets: Not Applicable 1 VI. Procurement of Second hand Goods: Not Applicable VII. Domestic Preference: Not Applicable VIII. Hands on Expanded Implementation Support (HEIS): Not Applicable IX. Other Relevant Procurement Information: Not Applicable X. Thresholds for Procurement Approaches and Method (US$ millions) Thresholds for Procurement Approaches and Methods (US$ millions)– Goods, Works, and Non-Consulting Services Category Prior Open Open Request for Review Internation Nation Quotation (US$ al al (RfQ) millions) Works all ≥ 5.0 < 5.0 ≤ 0.2 Goods, IT, and all ≥ 0.5 < 0.5 ≤ 0.1 non-consulting services Thresholds for Procurement Approaches and Methods (US$, millions) – Consulting Services Category Prior Short List of National Consultants Review Consulting Engineering and (US$, Services Construction millions) Supervision Consultants n.a n.a. all (Firms) Individual all n.a. n.a. Consultants 2 South West Procurement Plan XI. Packages for Goods, Works and Non-Consulting Services (At Negotiations – to be entered in STEP) R Contract Estimate Revie Market Sel Eval Procure Preq Do Expected Expected ef Description d Cost w by Approac ecti uati ment ualif mes date of date of . (US$) Bank h (Open- on on Process icati tic bid/ Contract N (Prior National Me Opti (Single on Pref proposal Signatur o / / Limited tho ons stage- (Yes/ ere opening e Post) etc.) d (BA single No) nce (RF FO envelop (Yes P, Rat e etc.) /No) RF ed B, Crit RF eria Q etc. etc ) .) GOODS Low est Single G Purchase of 5 Open Eval stage 02/Mar/20 02/Apr/20 $175,000 Prior RFB N/A N/A 1 vehicles National uate One- 19 19 d Envelop Cost Low Office Equipment est Singe (Laptops, G Eval stage 04/Mar/20 04/Apr/20 Desktops, $30,000 Prior Limited RFQ N/A N/A 2 Projector, Printers uate One - 19 19 and accessories) d Envelop Cost 3 Low est Single G Eval Stage 05/May/20 05/Jun/201 GIS Equipment $25,000 Prior Limited RFQ N/A N/A 3 uate One- 19 9 d Envelop Cost Low est Single Hydrological G Eval Stage 15/Oct/20 16/Nov/20 Water Monitoring $12,000 Prior Limited RFQ N/A N/A 4 Tools uate One- 19 19 d Envelop Cost Low est Single G Open Eval Stage 21/Mar/20 22/Apr/20 Vehicle Fuels $80,000 Prior RFQ N/A N/A 6 National uate One- 19 19 d Envelop Cost Low est Single G Office furniture Eval Stage 12/Jun/202 13/Jul/202 $30,000 Prior Limited RFQ N/A N/A 7 (Chairs, Tables, ) uate One- 0 0 d Envelop Cost Total Goods $352,000 WORKS Construction of Low Sand Dams/Sub- est Single W surface Dams Open Eval stage – 09/Nov/20 10/Dec/20 $90,000 Prior RFQ N/A N/A 1 National uate one 19 19 d envelope Cost 4 Construction of Low Earth Dams est Single W Open Eval stage – 01/Oct/20 02/Nov/20 $90,000 Prior RFQ N/A N/A 2 National uate one 19 19 d envelope Cost Construction/Reh Low abilitation of 10 est Single W Berkads Open Eval stage – 01/Sep/20 01/Oct/20 $42,000 Prior RFQ N/A N/A 3 National uate one 19 19 d envelope Cost Rehabilitation of Low Boreholes/Shallow est Single W Wells Open Eval stage – 18/Aug/20 19/Sep/20 $50,000 Prior RFQ N/A N/A 4 National uate one 19 19 d envelope Cost Office Low Construction/Reh est Single W abilitation Open Eval stage – 01/Aug/20 01/Sep/20 $70,000 Prior RFQ N/A N/A 5 National uate one 19 19 d envelope Cost Total Works $342,000 Non -Consulting Services Total Non- Consultant Service Consulting Services 5 Re Contract Estimate Review Market Selecti Shortli Expected Expected f Description d Cost by Bank Approach on sting Date of Date of No (US$) (Prior/Po (Open- Metho (Yes/N Bid Contract . st) National/ d o) Proposal Signatur Limited (QCBS Opening e etc.) , LCBCS , QBS, DS Site selection, geophysical surveying, Open – 16/Mar/201 15/Apr/20 C1 100,000 Prior CQS N/A contracting and National 9 19 engineering support Develop GIS map Prior Open - CQS 08/Aug/20 C2 for potential sites 20,000 N/A 08/Jul/2019 National 19 creation of village livelihood development Open - 13/May/202 10/Jun/202 C3 plans & water 500,000 Prior QCBS N/A International 0 0 budgets implement rural development policies and laws Open 12/Feb/20 C4 to regulate sector 50,000 Prior CQS N/A 15/Jan/2020 and ensure National 20 sustainability technical assistance agency Open 22/Feb/202 19/Mar/20 C5 for training 60,000 Prior CQS N/A assessment, National 0 20 selecting, training 6 and monitoring field service support, acquisition and application of geo-spatial Open – 01/Mar/202 01/Apr/20 C6 imagery for 20,000 Prior CQS N/A before and after National 0 20 satelite photos Procurement 05/Feb/20 C7 50,000 Prior Open INDV N/A 05/Jan/2019 Specialist 19 Open INDV 05/Feb/20 C8 Finance Specialist 50,000 Prior N/A 05/Jan/2019 19 Open INDV 10/Feb/201 10/Mar/20 C9 Project Engineer 72,000 Prior N/A 9 19 C1 Open INDV 31/Oct/20 2 Site Engineers 21,000 Prior N/A 01/Oct/2019 0 19 Total $943,000 Consulting Services $1,637,0 Grand Total 00 7 PROCUREMENT Somalia : Somalia - Water for Agro-pastoral Productivity and Resilience PLAN General Information Country: Somalia Bank’s Approval Date of the Original Procurement Plan: 2020-02-18 2021-05-25 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P167826 GPN Date: Project Name: Somalia - Water for Agro-pastoral Productivity and Resilience Loan / Credit No: IDA / D4970 Puntland Ministry of Planning, Economic Development and International Cooperation Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned SO-MOPIC - PL-174463-CW- RFB / Construction of Ministry Component 4: Project of Planning, Economic Management, M & E, Single Stage - One 2021-03- IDA / D4970 Prior Request for Bids Open - National 285,000.00 341,801.64 Signed 2020-05-24 2020-10-16 2020-05-29 2020-10-19 2020-07-10 2020-11-25 2020-08-09 2021-01-04 2020-09-13 2021-01-12 Development and Knowledge Management and Envelope 12 International Cooperation Learning offices. SO-MOPIC - PL-178126-CW- RFQ / Rehabilitation and Component 2. Institutional Request for Single Stage - One 2021-02- IDA / D4970 Prior Open - National 180,000.00 179,968.80 Completed 2020-06-26 2020-08-21 2020-08-21 2020-10-28 Extending of MoEACC Office and Capacity Development Quotations Envelope 17 in Garowe Component 4: Project SO-MOPIC - PL-182498-CW- Management, M & E, Request for Single Stage - One 2021-03- RFQ / Construction of MoLAH IDA / D4970 Prior Limited 50,000.00 49,139.25 Completed 2020-07-09 2020-09-18 2020-09-03 2020-10-14 Knowledge Management and Quotations Envelope 02 Conference Hall Learning SO-MOPIC - PL-178198-CW- Component 4: Project RFQ / Rehabilitation of Management, M & E, Request for Single Stage - One 2021-02- Meeting Room at the Puntland IDA / D4970 Prior Limited 10,000.00 9,853.76 Completed 2020-06-25 2020-09-14 2020-08-20 2020-10-07 Knowledge Management and Quotations Envelope 16 Ministry of Energy, Mineral Learning and Water (MoEMW) SO-MOPIC - PL-214242-CW- RFQ / Construction of Component 1: Support the Request for Single Stage - One 2021-09- Subsurface Dam in Rabable IDA / D4970 Development of Multiple Use Prior Limited 101,982.95 97,940.72 Signed 2021-01-30 2021-03-11 2021-03-27 2021-04-22 Quotations Envelope 23 Village, Nugaal Region, Water Sources Puntland, Somalia SO-MOPIC - PL-218499-CW- RFQ / Rehabilitation of four Pending Community Centers and Component 2. Institutional Request for Single Stage - One 2021-10- IDA / D4970 Prior Limited 135,000.00 0.00 Implementat 2021-03-04 2021-04-29 Rangeland in Meeladeen, and Capacity Development Quotations Envelope 26 ion Raydable, Lasodawoco and Xamxama. SO-MOPIC - PL-232616-CW- RFQ / Construction of Arc Component 1: Support the Request for Under Request for Single Stage - One 2022-01- Gravity Dam in Ceel Dahir IDA / D4970 Development of Multiple Use Prior Limited Quotations (Non 120,795.94 0.00 Implementat 2021-05-13 2021-06-13 2021-07-08 Quotations Envelope 04 Village, Bari Region, Puntland Water Sources Bank-SPD) ion Somalia GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SO-MOPIC - PL-173788-GO- RFB / Procurement of 9 Vehicles for Puntland Ministry of Environment Agriculture Component 3: Supporting and Climate Change, Ministry Sustainable Land Single Stage - One of Planning, Economic IDA / D4970 Management and Livelihoods Prior Request for Bids Open - National 395,000.00 256,000.00 Completed 2020-05-17 2020-06-13 2020-05-22 2020-06-14 2020-07-03 2020-08-23 2020-08-02 2020-09-12 2020-09-06 2020-09-16 2021-03-05 2021-01-09 Envelope Development and Development Around Water International Cooperation, Points Ministry of Livestock & Animal Husbandry and Puntland Water Development Agency. SO-MOPIC - PL-173790-GO- RFQ / Purchase of Office Component 4: Project Equipments (Laptops, Management, M & E, Request for Single Stage - One Desktops, Projector, Printers, IDA / D4970 Prior Limited 56,000.00 40,797.75 Completed 2020-05-24 2020-06-26 2020-07-19 2020-08-29 2021-01-15 2020-10-06 Knowledge Management and Quotations Envelope and accessories) for Biyoole Learning Puntland Implementing agencies. Component 4: Project SO-MOPIC - PL-178199-GO- Management, M & E, Request for Single Stage - One RFQ / Hydrological Monitoring IDA / D4970 Prior Limited 18,000.00 16,990.00 Signed 2020-06-14 2020-11-10 2020-08-09 2020-11-28 2021-02-05 Knowledge Management and Quotations Envelope Equipment (GPS tools) Learning SO-MOPIC - PL-183182-GO- Component 3: Supporting RFB / 4x4WD Double Cabin Sustainable Land Single Stage - One Pickup Vehicles with its IDA / D4970 Management and Livelihoods Prior Request for Bids Open - National 150,000.00 112,700.00 Completed 2020-07-15 2020-07-22 2020-07-20 2020-07-27 2020-08-31 2020-09-16 2020-09-30 2020-10-03 2020-11-04 2020-10-13 2021-05-03 2021-04-03 Envelope Accessories for Mobile Development Around Water Veterinary Clinics Points SO-MOPIC - PL-185015-GO- Component 4: Project RFQ / Procurement of Office Management, M & E, Request for Single Stage - One IDA / D4970 Prior Limited 3,500.00 3,410.00 Completed 2020-07-28 2020-08-11 2020-09-22 2020-08-19 2021-03-21 2020-08-28 Furniture (tables, chairs, Knowledge Management and Quotations Envelope shelves etc.) for Puntland PIUs Learning Component 3: Supporting SO-MOPIC - PL-204178-GO- Sustainable Land Request for Single Stage - One RFQ / Purchase of Mobile IDA / D4970 Management and Livelihoods Prior Limited 49,908.00 54,683.20 Completed 2020-11-20 2020-12-23 2021-01-15 2021-01-18 2021-07-14 2021-02-21 Quotations Envelope veterinary clinics kits Development Around Water Points Page 1 SO-MOPIC - PL-214237-GO- Component 4: Project RFQ / Procurement of Management, M & E, Request for Single Stage - One Monitoring and Evaluation IDA / D4970 Prior Limited 8,000.00 8,506.30 Completed 2021-01-25 2021-02-16 2021-03-22 2021-03-04 2021-09-18 2021-03-08 Knowledge Management and Quotations Envelope equipment (drones, Learning smartphones, GPS, etc) SO-MOPIC - PL-219383-GO- Component 4: Project RFQ / Conference room Management, M & E, Request for Single Stage - One furniture for newly IDA / D4970 Prior Limited 14,140.00 19,959.47 Completed 2021-02-28 2021-03-01 2021-04-25 2021-03-21 2021-10-22 2021-05-10 Knowledge Management and Quotations Envelope constructed MoLAH's Learning Conference Hall SO-MOPIC - PL-226152-GO- RFQ / Procurement of Office Furniture (tables, chairs, Component 2. Institutional Request for Single Stage - One shelves etc.) for Puntland IDA / D4970 Post Limited 36,000.00 0.00 Canceled 2021-04-04 2021-05-30 2021-11-26 and Capacity Development Quotations Envelope Ministry of Environment, Agriculture and Climate Change. SO-MOPIC - PL-231286-GO- RFQ / Procurement of Office Furniture (tables, chairs, Component 2. Institutional Request for Single Stage - One shelves etc.) for Puntland IDA / D4970 Prior Limited 36,000.00 0.00 Canceled 2021-05-01 2021-06-26 2021-12-23 and Capacity Development Quotations Envelope Ministry of Environment, Agriculture and Climate Change. SO-MOPIC - PL-231558-GO- RFQ / Purchase of Office Equipments (Laptops, Desktops, Projector, Printers, Component 2. Institutional Request for Single Stage - One IDA / D4970 Prior Limited 22,825.00 24,985.80 Signed 2021-05-05 2021-05-10 2021-06-30 2021-06-03 2021-12-27 and accessories) for Puntland and Capacity Development Quotations Envelope Ministry of Environment, Agriculture and Climate Change. SO-MOPIC - PL-232799-GO- RFQ / Procurement of Office Furniture (tables, chairs, Component 2. Institutional Request for Single Stage - One shelves etc.) for Puntland IDA / D4970 Prior Limited 13,175.00 25,042.00 Signed 2021-05-10 2021-05-10 2021-07-05 2021-06-03 2022-01-01 and Capacity Development Quotations Envelope Ministry of Environment, Agriculture and Climate Change. SO-MOPIC - PL-235843-GO- Component 3: Supporting RFQ / Procurement of Sustainable Land Under Request for Single Stage - One Laboratory Kits for Puntland IDA / D4970 Management and Livelihoods Prior Limited 57,810.00 0.00 Implementati 2021-06-05 2021-06-13 2021-07-31 2022-01-27 Quotations Envelope Ministry of Livestock and Development Around Water on Animal Husbandry Points Component 3: Supporting SO-MOPIC - PL-240954-GO- Sustainable Land Under RFQ / Procurement of seeds Request for Single Stage - One IDA / D4970 Management and Livelihoods Prior Limited 15,000.00 0.00 Implementati 2021-07-05 2021-08-30 2022-02-26 and tools for fodder Quotations Envelope Development Around Water on production Points NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SO-MOPIC - PL-169621-CS- CQS / Consulting Firm for Provision of continuous Component 1: Support the Consultant engineering support - Site IDA / D4970 Development of Multiple Use Prior Qualification International 213,150.00 300,000.00 Signed 2020-04-25 2020-05-12 2020-05-16 2020-05-20 2020-06-29 2020-07-21 2020-07-29 2020-09-18 2020-09-02 2020-09-19 2021-03-01 selection, surveying, Water Sources Selection designing & BOQs, bidding & Contracting SO-MOPIC - PL-224681-CS- Consultant CQS / Consultant Firm for Component 2. Institutional IDA / D4970 Prior Qualification Limited 50,000.00 0.00 Under Review 2021-03-26 2021-04-22 2021-04-09 2021-05-09 2021-06-13 2021-12-10 Developing 10 Community and Capacity Development Selection Investment Plans in Puntland. INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 4: Project Individual SO-MOPIC - PL-160036-CS- Management, M & E, IDA / D4970 Prior Consultant Limited 150,000.00 75,120.00 Signed 2020-02-24 2020-02-23 2020-02-29 2020-03-10 2020-03-21 2020-04-06 2020-04-25 2020-03-28 2021-02-28 INDV / Project Coordinator Knowledge Management and Selection Learning Component 4: Project SO-MOPIC - PL-160043-CS- Individual Management, M & E, INDV / Finance Management IDA / D4970 Prior Consultant Limited 90,000.00 50,775.00 Signed 2020-02-24 2020-03-09 2020-02-29 2020-03-10 2020-03-21 2020-04-06 2020-04-25 2020-03-28 2021-02-28 Knowledge Management and Specialist Selection Learning Component 4: Project Individual SO-MOPIC - PL-160039-CS- Management, M & E, IDA / D4970 Prior Consultant Limited 90,000.00 56,640.00 Signed 2020-02-24 2020-02-20 2020-02-29 2020-02-21 2020-03-21 2020-04-08 2020-04-25 2020-03-28 2021-02-28 INDV / Procurement Specialist Knowledge Management and Selection Learning Component 4: Project SO-MOPIC - PL-160034-CS- Individual Management, M & E, INDV / Environmental and IDA / D4970 Prior Consultant Limited 72,000.00 43,305.00 Signed 2020-02-24 2020-02-21 2020-02-29 2020-02-23 2020-03-21 2020-04-06 2020-04-25 2020-03-28 2021-02-28 Knowledge Management and Social Safeguards Specialist Selection Learning Page 2 Component 4: Project SO-MOPIC - PL-160042-CS- Individual Management, M & E, INDV / Monitoring and IDA / D4970 Prior Consultant Limited 90,000.00 43,305.00 Signed 2020-02-24 2020-02-20 2020-02-29 2020-02-23 2020-03-21 2020-04-07 2020-04-25 2020-03-28 2021-02-28 Knowledge Management and Evaluation Specialist Selection Learning Component 4: Project SO-MOPIC - PL-168511-CS- Individual Management, M & E, CDS / Senior Rangeland IDA / D4970 Prior Consultant Limited 43,200.00 93,990.00 Signed 2020-04-23 2020-04-26 2020-04-28 2020-05-06 2020-05-05 2020-05-07 2020-05-15 2020-05-09 2020-05-20 Knowledge Management and Specialist Consultant Selection Learning Component 4: Project SO-MOPIC - PL-168512-CS- Individual Management, M & E, CDS / Community IDA / D4970 Prior Consultant Limited 43,200.00 84,240.00 Signed 2020-04-23 2020-05-10 2020-04-28 2020-05-13 2020-05-05 2020-05-14 2020-05-15 2020-05-13 2020-05-20 Knowledge Management and Development Specialist Selection Learning Component 4: Project SO-MOPIC - PL-168513-CS- Individual Management, M & E, CDS / Senior institutional IDA / D4970 Prior Consultant Limited 48,000.00 98,160.00 Signed 2020-04-23 2020-04-29 2020-04-28 2020-05-09 2020-05-05 2020-05-11 2020-05-15 2020-05-09 2020-05-20 Knowledge Management and Development Advisor Selection Learning Component 4: Project SO-MOPIC - PL-168514-CS- Individual Management, M & E, CDS / Senior Water Engineer IDA / D4970 Prior Consultant Limited 48,000.00 92,880.00 Signed 2020-04-23 2020-05-10 2020-04-28 2020-06-03 2020-05-05 2020-06-09 2020-05-15 2020-06-03 2020-05-20 Knowledge Management and Consultant Selection Learning SO-MOPIC - PL-174621-CS- Component 1: Support the Individual INDV / 1st - Site Supervision IDA / D4970 Development of Multiple Use Prior Consultant Open 18,000.00 0.00 Canceled 2020-05-27 2020-05-27 2020-07-15 2020-08-05 2020-09-09 2021-03-08 Engineer Water Sources Selection SO-MOPIC - PL-175171-CS- Component 1: Support the Individual INDV / 2nd - Site Supervision IDA / D4970 Development of Multiple Use Prior Consultant Open 18,000.00 0.00 Canceled 2020-05-27 2020-05-27 2020-07-15 2020-08-05 2020-09-09 2021-03-08 Engineer Water Sources Selection SO-MOPIC - PL-175173-CS- Component 1: Support the Individual INDV / 3rd - Site Supervision IDA / D4970 Development of Multiple Use Prior Consultant Open 18,000.00 0.00 Canceled 2020-05-27 2020-05-27 2020-07-15 2020-08-05 2020-09-09 2021-03-08 Engineer Water Sources Selection SO-MOPIC - PL-175175-CS- Component 1: Support the Individual INDV / 4th - Site Supervision IDA / D4970 Development of Multiple Use Prior Consultant Open 18,000.00 0.00 Canceled 2020-05-27 2020-05-27 2020-07-15 2020-08-05 2020-09-09 2021-03-08 Engineer Water Sources Selection SO-MOPIC - PL-176299-CS- Component 1: Support the Individual INDV / 1st - Site Supervision IDA / D4970 Development of Multiple Use Prior Consultant Limited 18,000.00 18,000.00 Signed 2020-05-30 2020-05-31 2020-06-04 2020-06-25 2020-06-25 2020-06-29 2020-07-30 2020-08-01 2021-01-26 Engineer Water Sources Selection SO-MOPIC - PL-176300-CS- Component 1: Support the Individual INDV / 2nd - Site Supervision IDA / D4970 Development of Multiple Use Prior Consultant Limited 18,000.00 18,000.00 Signed 2020-05-30 2020-05-31 2020-06-04 2020-06-24 2020-06-25 2020-06-29 2020-07-30 2020-08-01 2021-01-26 Engineer Water Sources Selection SO-MOPIC - PL-176302-CS- Component 1: Support the Individual INDV / 3rd - Site Supervision IDA / D4970 Development of Multiple Use Prior Consultant Limited 18,000.00 18,000.00 Signed 2020-05-30 2020-05-31 2020-06-04 2020-06-25 2020-06-25 2020-06-29 2020-07-30 2020-08-01 2021-01-26 Engineer Water Sources Selection SO-MOPIC - PL-176303-CS- Component 1: Support the Individual INDV / 4th - Site Supervision IDA / D4970 Development of Multiple Use Prior Consultant Limited 18,000.00 18,000.00 Signed 2020-05-30 2020-05-31 2020-06-04 2020-06-25 2020-06-25 2020-07-08 2020-07-30 2020-08-01 2021-01-26 Engineer Water Sources Selection Component 3: Supporting SO-MOPIC - PL-214244-CS- Sustainable Land Individual INDV / Livestock Development IDA / D4970 Management and Livelihoods Prior Consultant Limited 39,840.00 39,840.00 Signed 2021-01-22 2021-02-11 2021-01-27 2021-03-01 2021-02-17 2021-03-03 2021-03-24 2021-03-04 2021-09-20 Specialists Development Around Water Selection Points Page 3 UNITED REPUBLIC OF TANZANIA Procurement Plan General 1. Project Information Country: Tanzania Project Name: Secondary Education Quality Improvement Program Project ID: P170480 2. Project Implementation Agency: President’s Office, Regional Administration and Local Government 3. Date of the Procurement Plan: December 5, 2019 4. Period Covered by this procurement plan: January 2020 to June 2021 I. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016, Revised November 2017 and August 2018) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. II. Bank’s Standard Procurement Documents: The Bank’s Standard Procurement Documents shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. III. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. 1 When the Borrower uses its own national open competitive procurement arrangements as set forth in The Public Procurement Act, 2011, The Public Procurement (Amendment) Act, 2016, the Public Procurement Regulations, 2013 and the Public Procurement (Amendment) Regulations, 2016, such arrangements shall be subject to paragraph 5.3 and 5.4 of the Procurement Regulations and the following conditions: o Procurement Documents include provisions, as agreed with the Bank, intended to adequately mitigate against environmental, social (including sexual exploitation and abuse and gender-based violence), health and safety (“ESHS”) risks and impacts o There should be no mandatory requirements for inclusion of local experts and firms for the consulting assignments; o There should be no exclusive preference based on threshold prescribed in PPA and its Regulations; o Negotiations with the lowest evaluated bidder to reduce price in the case of goods, works and non-consulting services where competitive methods have been used shall not be allowed; o The fixed budget method shall not be used for goods, works and non- consulting services; o Established and approved procurement standards by the government may be used, provided that they are not restrictive When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. In accordance with paragraph 5.4(c) and 5.5 of the Procurement Regulations, the request for bids/request for proposals/request for quotations document shall require that Bidders/Proposers submitting Bids/Proposals/quotations present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. The form of the Letter of Acceptance is attached in Appendix 1. IV. Prequalification: Not Applicable V. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable VI. Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations: Not Applicable VII. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Not Applicable 2 Domestic preference is not applicable for National Open Competitive Procurement VIII. Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. Not Applicable IX. Other Relevant Procurement Information Not Applicable 3 X. Threshold for Prior Review, Procurement Approaches and Methods – Good, Works and Non-Consulting Services Procurement Approaches and Methods Prior (US$ millions) Review Category Open Open Request for (US$ millions) International National Quotation (RfQ) Works ≥ 10 ≥ 15 < 15 ≤ 0.2 Goods, IT, and non- ≥2 ≥5 <5 ≤ 0.1 consulting services Post Review: All contracts not subject to prior review shall be subject to post review. Summary of the procurement packages for Good, Works and Non-Consulting Services (Planned for the first 18 months after project effectiveness): XI. Thresholds for Prior Review, Selection Approaches and Methods – Consulting Services Category Prior Short List of National Consultants Review Consulting Engineering and Construction (US$ Services Supervision millions) Consultants ≥1 ≤ 0.3 ≤ 0.3 (Firms) Individual ≥ 0.3 n.a. n.a. Consultants Note: Consultancy services estimated to cost equivalent to US $ 300,000 and above per contract shall be advertised in the United Nations Development Business (UNDB) online in addition to advertising in national newspaper(s) of wide circulation and/or regional newspaper. 4 PROCUREMENT Tanzania : Tanzania Secondary Education Quality Improvement Project (SEQUIP) PLAN General Information Country: Tanzania Bank’s Approval Date of the Original Procurement Plan: 2021-05-24 2021-05-24 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P170480 GPN Date: 2021-06-09 Project Name: Tanzania Secondary Education Quality Improvement Project (SEQUIP) Loan / Credit No: IDA / 65340 P Executing Agency(ies): RESIDENT’S OFFICE- REGIONAL ADMINISTRATION AND LOCAL GOVERNMENT WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TZ-PO-RALG-235742-GO- RFB / Procurement of 5 Motor Component 4: Project Pending Single Stage - One vehicles for Project IDA / 65340 Coordination, Monitoring and Post Request for Bids Open - National 570,000.00 0.00 Implementati 2021-07-26 2021-07-31 2021-08-21 2021-10-02 2021-11-06 2022-05-05 Envelope Coordination and Monitoring Evaluation on at PO -RALG TZ-PO-RALG-235746-GO- RFB / Procurement of Office Component 4: Project Pending Single Stage - One equipment (Desktop and IDA / 65340 Coordination, Monitoring and Post Request for Bids Open - National 150,000.00 0.00 Implementati 2021-07-26 2021-07-31 2021-09-11 2021-10-11 2021-11-15 2022-05-14 Envelope Laptops computers, Printers Evaluation on and Photocopies) TZ-PO-RALG-235750-GO- Component 4: Project Pending Request for Single Stage - One RFQ / procurement of IDA / 65340 Coordination, Monitoring and Post Limited 50,000.00 0.00 Implementati 2021-07-31 2021-09-25 2022-03-24 Quotations Envelope furniture and fittings Evaluation on NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TZ-PO-RALG-235766-CS- CQS / Consultancy services Component 4: Project Consultant for Under IDA / 65340 Coordination, Monitoring and Post Qualification Open - National 300,000.00 0.00 2021-05-25 2021-06-04 2021-06-15 2021-07-29 2021-08-28 2021-10-02 2022-03-31 supervision/Implementation Implementation Evaluation Selection of the ESF instruments of the SEQUIP INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 1 PPA PROCUREMENT PLAN I. General Project information: Niger Smart Villages for rural growth and digital inclusion, P167543 Project Implementation agency: UNITE DE GESTION DU PROJET (UGP) Agence Nationale de la Société d’Information (ANSI) UGP Transitoire: Public Sector Capacity and Performance for Service Delivery (PCDS) Date of the PPA Procurement Plan: November 16, 2018 Period covered by this Procurement Plan: The procurement period of project covered from November 2018 to August 2020. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016, revised November 2017 and in August 2018) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Act 2011-37 of October 28, 2011 on the general principles, control and regulation of public procurement and delegations of public service in Niger and the Decree No. 2016- 1 641/PRN/PM of December 1, 2016 on the Public Procurement Code and delegations of public service, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions: a. open advertising of the procurement opportunity at the national level; b. the procurement is open to eligible firms from any country; c. the request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights; d. Procurement Documents include provisions, as agreed with the Bank, intended to adequately mitigate against environmental, social (including sexual exploitation and abuse and gender-based violence), health and safety (“ESHS”) risks and impacts; e. contracts with an appropriate allocation of responsibilities, risks, and liabilities; f. publication of contract award information; g. rights for the Bank to review procurement documentation and activities; h. an effective complaints mechanism; and i. maintenance of records of the Procurement Process. Other national procurement arrangements (other than national open competitive procurement), that may be applied by the Borrower (such as limited/restricted competitive bidding, request for quotations/shopping, direct contracting), shall be consistent with the Bank’s Core Procurement Principles and ensure that the Bank’s Anti- Corruption Guidelines and Sanctions Framework and contractual remedies set out in its Legal Agreement apply. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” 2 Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables. “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is applicable for those contracts identified in the Procurement Plan tables; Other Relevant Procurement Information. “Not Applicable” 3 Activity Reference No. Procurement Review Procurement Market Estimated Amount Component /Description Category Type Method Approach (US$) CS-INDV-1 Selection of Préparation d’un Cadre de Gestion Components 1-5 Consultant Post Individual Open 100,000.00 Environnementaux et Sociaux (full project) Services Consultants (IC) (CGES) CS-INDV-2 Component 2 – Consultant Etude d’Evaluation des pilotes « Post IC Open 100,000.00 Rural Connectivity Services Villages Intelligents » CS-INDV-3 Component 1 – Etude réglementaire sur le partage Consultant Enabling Post IC Open 100,000.00 des infrastructures et le « Roaming Services Environment national » CS-INDV-4 Components 1-5 Post Open 50,000.00 Consultant (spécialiste ressources (full project) Consultant IC humaines) pour préparer des Services termes de références CS-INDV-5 Component 1 Post Open 100,000.00 Etude sur l’utilisation du Fond sur Enabling Consultant IC l’Accès Universel (FAU) Evironment Services CS-INDV-6 Components 1-5 Post Open 50,000.00 Consultant pour préparer le manuel (full project) Consultant IC de procédures pour le projet Services CS-INDV-7 Component 3 Post Open 100,000.00 Evaluation des besoins en Digital and Consultant infrastructures de paiements des Financial Inclusion IC Services différentes parties : Direction du Trésor, CAIMA, et autres 4 CS-FIRME-8 Component 2 Rural Post Quality Cost Open/National 300,000.00 Etude pour définir le modèle pour Connectivity Based Selection octroi des subventions (enchères (QCBS) Consultant inverses) : Préparation de Services documents pour l’appel aux offres / cahiers des charges et appui au processus CS-FIRME-9 Component 3 Post Consultant’s Open/National 200,000.00 Etude sur l’utilisation de l’argent Digital and Consultant Qualifications mobile dans les zones rurales Financial Inclusion Services Based Selection (CQS) CS-FIRME-10 Components 1-5 Post QCBS Open/National 300,000.00 Définition du concept d’un village (full project) Consultant intelligent, PPP, et programme de Services sensibilisation dans les villages CS-FIRME-11 Components 2 Post CQS Open/National 200,000.00 Etude sur les besoins numériques (Rural Consultant des camps refugies Connectivity) and 3 Services Digital and Financial Inclusion CS-FIRME-12 Components 1-5 Post Least Cost-based Open/National 50,000.00 Audit Externe (full project) Consultant Selection Services CS-INDV-13 Component 4 Post IC Open 50,000.00 Coordinateur UGP Project Consultant Management Services CS-INDV-14 Component 4 Post IC Open 40,000.00 Spécialiste, Passation des Marches Project Consultant Management Services CS-INDV -15 Component 4 Post IC Open 40,000.00 Spécialiste, gestion Financière Project Consultant Management Services CS-INDV-16 Component 4 Post IC Open 40,000.00 Spécialiste, Sauvegardes Project Consultant Environnementaux et Sociaux Management Services 5 CS-INDV-17 Component 4 Post IC Open 28,000.00 Spécialiste, Développement Rural Project Consultant Management Services CS-INDV-18 Component 4 Post IC Open 28,000.00 Spécialiste, Technologies Project Consultant Numérique Management Services CS-INDV-19 Component Post IC Open 28,000.00 Spécialiste, Finance inclusive / 4 Project Consultant Finance numérique Management Services CS-INDV-20 Component 4 Post IC Open 20,000.00 Assistant au coordinateur Project Consultant Management Services CS-INDV-21 Component 4 Post IC Open 20,000.00 Assistant, Passation des marches Project Consultant Management Services CS-INDV-22 Component 4 Post IC Open 20,000.00 Assistant, Gestion Financière Project Consultant Management Services Acquisition d’ordinateurs, de Component 4 Goods Post Request for Bids Open/National 200,000.00 vidéoprojecteurs, d’imprimantes et Project de mobiliers Management Acquisition de véhicule Component 4 Goods Post Request for Open/Limited 50,000.00 Project Quotations Management 6 PROCUREMENT Niger : Niger: Smart Villages for rural growth and digital inclusion PLAN General Information Country: Niger Bank’s Approval Date of the Original Procurement Plan: 2020-02-05 2021-05-28 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P167543 GPN Date: Project Name: Niger: Smart Villages for rural growth and digital inclusion Loan / Credit No: IDA / V2450, IDA / 66880 COORDINATION UNIT OF NIGER SMART VILLAGES PROJECT Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 4. Strengthening project GS-2 / Transportation car for Request for Single Stage - One IDA / V2450 management and stakeholder Post Open - National 50,000.00 45,492.48 Signed 2019-11-20 2020-01-15 2019-09-26 2020-07-13 office Quotations Envelope capacity-building GS-1 / Acquistion 4. Strengthening project d'ordinateurs, video Request for Single Stage - One IDA / V2450 management and stakeholder Post Limited 100,000.00 0.00 Canceled 2020-03-04 2020-04-29 2020-10-26 projecteurs, imprimantes, Quotations Envelope capacity-building mobiliers de bureaux NE-PCU-SV-203071-GO-RFQ / Fourniture, Installation et Configuration des 4. Strengthening project Request for Single Stage - One équipements photovoltaïque IDA / V2450 management and stakeholder Post Limited 100,000.00 59,802.67 Signed 2020-11-18 2020-12-08 2021-01-13 2021-01-21 2021-07-12 Quotations Envelope pour l'alimentation de sites capacity-building VSAT et KITS WIFI pour le compte de l’ANSI NE-PCU-SV-209290-GO-RFQ / Fourniture, Installations et 4. Strengthening project Under Configurations des Request for Single Stage - One IDA / V2450 management and stakeholder Post Limited 30,000.00 24,346.33 Implementati 2020-12-23 2021-05-28 2021-02-17 2021-08-16 équipements de Visio- Quotations Envelope capacity-building on Conférence pour le compte du Projet Villages Intelligents. NE-PCU-SV-212558-GO-DIR / Fourniture, installation et 4. Strengthening project mise en service du logiciel de IDA / 66880 management and stakeholder Post Direct Selection Direct 50,000.00 33,234.68 Signed 2021-02-09 2021-02-04 2021-02-14 2021-01-27 2021-03-21 2021-03-17 2021-09-17 Gestion Comptable et capacity-building Financière intégré « Tom²Pro » GS-3 / Acquisition 01 Under véhicule 4x4 Station Wagon 2. Developing rural Request for Single Stage - One IDA / 66880 Post Open - National 200,000.00 0.00 Implementati 2021-03-03 2021-06-08 2021-04-28 2021-10-25 Tout Terrain et 01 véhicule connectivity Quotations Envelope on 4x4 Hard Top wc NE-PCU-SV-229729-GO-RFQ / Fourniture et installation de 4. Strengthening project Request for Single Stage - One matériels informatiques pour IDA / 66880 management and stakeholder Post Limited 60,000.00 48,010.44 Signed 2021-05-05 2019-11-20 2021-06-30 2019-12-02 2021-12-27 Quotations Envelope le compte du Projet Villages capacity-building Intelligents NE-PCU-SV-229731-GO-RFQ / Fourniture et installation de 4. Strengthening project Request for Single Stage - One mobilier de bureau pour le IDA / 66880 management and stakeholder Post Limited 20,000.00 17,167.58 Signed 2021-05-05 2019-11-04 2021-06-30 2019-11-15 2021-12-27 Quotations Envelope compte du projet villages capacity-building intelligents NE-PCU-SV-229733-GO-RFQ / Fourniture et installation 4. Strengthening project Request for Single Stage - One d'un groupe électrogène pour IDA / 66880 management and stakeholder Post Limited 40,000.00 33,379.02 Signed 2021-05-05 2019-11-29 2021-06-30 2019-12-17 2021-12-27 Quotations Envelope le compte du Projet villages capacity-building Intelligents NE-PCU-SV-239226-GO-RFQ / Acquisition complément matériels informatiques pour 4. Strengthening project Under Request for Single Stage - One UGP (ordinateurs portables , IDA / 66880 management and stakeholder Post Limited 15,000.00 0.00 Implementati 2021-06-23 2021-06-14 2021-08-18 2022-02-14 Quotations Envelope ordinateurs tout-en-un, capacity-building on licences anti virus, et accessoires ) NE-PCU-SV-239225-GO-RFB Pending 3. Improving digital financial Single Stage - One / Equipement de 50 centres IDA / 66880 Prior Request for Bids Open - International 3,000,000.00 0.00 Implementati 2021-07-20 2021-07-25 2021-09-05 2021-10-05 2021-11-09 2022-05-08 inclusion Envelope numériques en zones rurales on NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NE-PCU-SV-185945-NC-RFP 4. Strengthening project / Recrutement d’un transitaire Request for Single Stage - One IDA / V2450 management and stakeholder Post Limited 20,000.00 17,997.05 Signed 2020-09-05 2020-08-24 2020-10-31 2020-10-16 2021-04-29 / cabinet de transit pour le Quotations Envelope capacity-building compte de l’ANSI CS-FIRME-13 / Cartographie 2. Developing rural Single Stage - One IDA / V2450 Post Request for Bids Open - National 170,000.00 0.00 Canceled 2020-08-31 2020-09-05 2020-10-17 2020-11-16 2020-12-21 2021-06-19 des 200 villages pilotes connectivity Envelope CONSULTING FIRMS Page 1 Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CS-FIRME-8 / Etude pour definir le modele dóctroi des subventions ( encheres 2. Developing rural Quality And Cost- Under inversees): Preparation de IDA / V2450 Post Open - National 300,000.00 0.00 2019-11-27 2020-02-24 2019-12-18 2020-01-31 2021-03-08 2020-02-28 2021-04-15 2020-03-29 2021-05-05 2020-05-03 2021-06-04 2020-06-07 2021-06-07 connectivity Based Selection Implementation documents pour l'appel d'offres / Cahiers des charges et appui au processus CS-FIRME-9 / Etude sur Consultant 3. Improving digital financial Under l'utilisation du Mobile money IDA / V2450 Post Qualification Open - National 200,000.00 223,321.14 2019-11-20 2020-02-24 2019-12-11 2020-01-24 2021-02-01 2020-02-23 2021-03-29 2020-03-29 2020-09-25 inclusion Implementation dans les zones rurales Selection Quality And Cost- Under CS-FIRME-12 / Audit externe IDA / V2450 1. Enabling environment Post Open - National 50,000.00 25,088.81 2020-03-16 2020-07-08 2020-04-06 2020-05-20 2021-03-05 2020-06-17 2021-03-25 2020-07-17 2021-03-30 2020-08-21 2021-04-30 2020-09-25 2021-09-25 Based Selection Implementation NE-PCU-SV-191268-CS-CQS / Sélection d’un cabinet de consultance charge d’élaborer Consultant un manuel d’exécution des 3. Improving digital financial IDA / V2450 Post Qualification Open - International 200,000.00 87,686.13 Signed 2020-10-02 2020-10-21 2020-10-23 2020-12-06 2021-03-20 2021-01-05 2021-03-20 2021-02-09 2021-05-07 2021-08-08 activités de la composante 3 inclusion Selection du PVI : (Inclusion financière et services financiers numériques). NE-PCU-SV-200538-CS-CQS / Étude des infrastructures Consultant des TIC’s au Niger et 2. Developing rural IDA / V2450 Post Qualification Open - International 170,000.00 168,351.88 Signed 2020-10-30 2020-11-04 2020-11-20 2021-01-03 2021-02-01 2021-02-02 2021-04-01 2021-03-09 2021-05-17 2021-09-05 Identification de 200 villages connectivity Selection pilotes pour la couverture large bande des zones rurales NE-PCU-SV-225496-CS- QCBS / Sélection d’un cabinet de consultants (Firme) pour 2. Developing rural Quality And Cost- Under une évaluation des IDA / V2450 Post Open - International 150,000.00 0.00 2021-03-23 2021-03-21 2021-04-13 2021-05-10 2021-05-27 2021-06-24 2021-07-24 2021-08-28 2021-10-02 2022-10-02 connectivity Based Selection Implementation infrastructures digitales de paiement et de traitement de données au Niger CS-FIRME-10 / Definition du concept d'un village Quality And Cost- intelligent, PPP, et Programme IDA / V2450 1. Enabling environment Post Open - National 300,000.00 0.00 Canceled 2019-12-19 2020-01-09 2020-02-22 2020-03-21 2020-04-20 2020-05-25 2020-06-29 2021-06-29 Based Selection de sensibilisation dans les villages CS-FIRME-11 / Etude sur les Consultant 2. Developing rural besoins numeriques des IDA / V2450 Post Qualification Open - National 200,000.00 0.00 Canceled 2020-01-08 2020-01-29 2020-03-13 2020-04-12 2020-05-17 2020-11-13 connectivity camps de refugies Selection NE-PCU-SV-161011-CS-CQS / Recrutement d'une firme Consultant chargée de l’élaboration des IDA / V2450 1. Enabling environment Post Qualification Open - International 60,000.00 0.00 Canceled 2020-03-23 2020-04-13 2020-05-27 2020-06-26 2020-07-31 2021-01-27 études préparatoires du Projet Selection Villages Intelligents. NE-PCU-SV-186068-CS- QCBS / Sélection d’un cabinet de consultance pour 3. Improving digital financial Quality And Cost- l’élaboration d’un Manuel IDA / V2450 Post Open - International 100,000.00 0.00 Canceled 2020-09-07 2020-01-06 2020-09-28 2020-11-11 2020-12-09 2021-01-08 2021-02-12 2021-03-19 2022-03-19 inclusion Based Selection d’exécution des activités relatives à l’inclusion financière numérique INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NE-PCU-SV-144372-CS- Individual INDV / Preparation d'un Cadre IDA / V2450 1. Enabling environment Post Consultant Open 100,000.00 44,118.70 Signed 2019-11-06 2020-02-24 2019-12-25 2019-04-30 2020-01-15 2019-05-16 2020-02-19 2020-06-12 2020-08-17 de Gestion Environnemental et Selection Social (CGES) CS-INDV-3 / Etude Individual reglementaire sur le partage Under IDA / V2450 1. Enabling environment Post Consultant Open 100,000.00 0.00 2019-12-02 2021-03-09 2020-01-20 2020-02-10 2020-03-16 2020-09-12 des infrastructure et le Implementation Selection "Roaming national" CS-INDV-5 / Etude sur Individual l'utilisation du Fond d'Acces IDA / V2450 1. Enabling environment Post Consultant Open 100,000.00 0.00 Canceled 2019-12-15 2020-02-24 2020-02-02 2020-02-23 2020-03-29 2020-09-25 Universel ( FAU) Selection CS-INDV-6 / Consultant pour Individual preparer le Manuel de IDA / V2450 1. Enabling environment Post Consultant Open 50,000.00 15,826.53 Signed 2019-11-20 2020-02-24 2020-01-08 2019-08-26 2020-01-29 2021-03-12 2020-03-04 2021-04-30 2020-08-31 Procedures du Projet Selection CS-INDV-7 / Evaluation des besoins en infrastrutures de Individual 3. Improving digital financial paiement des differentes IDA / V2450 Post Consultant Open 100,000.00 0.00 Canceled 2019-12-20 2020-02-07 2020-02-28 2020-04-03 2020-09-30 inclusion parties : Direction du Tresor, Selection CAIMA, etc.. CS-INDV-19 / Specialiste , 4. Strengthening project Individual Finance Inclusive et Finance IDA / V2450 management and stakeholder Post Consultant Open 40,000.00 33,063.48 Signed 2020-02-24 2020-05-22 2020-04-13 2021-01-22 2020-05-04 2021-01-25 2020-06-08 2021-01-26 2020-12-05 Numerique capacity-building Selection 4. Strengthening project Individual CS-INDV-14 / Specialiste, IDA / V2450 management and stakeholder Post Consultant Open 40,000.00 2,770.26 Signed 2020-02-28 2019-02-04 2020-04-17 2019-06-28 2020-05-08 2019-10-07 2020-06-12 2019-10-10 2020-12-09 Passation des Marches capacity-building Selection 4. Strengthening project Individual CS-INDV-22 / Assistant, Under IDA / V2450 management and stakeholder Post Consultant Open 20,000.00 0.00 2020-02-28 2020-12-11 2020-04-17 2020-05-08 2020-06-12 2020-12-09 Gestion Financiere Implementation capacity-building Selection Page 2 4. Strengthening project Individual CS-INDV-13 / IDA / V2450 management and stakeholder Post Consultant Open 50,000.00 3,676.16 Signed 2020-02-28 2018-10-01 2020-04-17 2019-04-15 2020-05-08 2019-06-25 2020-06-12 2019-06-29 2020-12-09 Coordonnateur UGP capacity-building Selection 4. Strengthening project Individual CS-INDV-15 / Specialiste, IDA / V2450 management and stakeholder Post Consultant Open 40,000.00 2,762.37 Signed 2020-02-28 2019-02-04 2020-04-17 2019-07-01 2020-05-08 2019-09-20 2020-06-12 2019-09-20 2020-12-09 Gestion Financiere capacity-building Selection 4. Strengthening project Individual CS-INDV-20 / Assisstant IDA / V2450 management and stakeholder Post Consultant Open 20,000.00 0.00 Canceled 2020-02-28 2020-12-11 2020-04-17 2020-05-08 2020-06-12 2020-12-09 Coordonnateur capacity-building Selection 4. Strengthening project Individual CS-INDV-21 / Assisstant, Under IDA / V2450 management and stakeholder Post Consultant Open 20,000.00 1,365.70 2020-02-28 2020-12-23 2020-04-17 2021-06-02 2020-05-08 2021-06-18 2020-06-12 2020-12-09 Passation des marches Implementation capacity-building Selection 4. Strengthening project Individual CS-INDV-23 / Comptable IDA / V2450 management and stakeholder Post Consultant Open 28,000.00 1,988.91 Signed 2020-02-24 2019-02-04 2020-04-13 2019-06-28 2020-05-04 2019-09-20 2020-06-08 2019-09-20 2020-12-05 Principal capacity-building Selection CS-INDV-16 / Specialiste, 4. Strengthening project Individual Sauvegardes Environnnmt et IDA / V2450 management and stakeholder Post Consultant Open 40,000.00 2,781.59 Signed 2020-02-28 2019-02-21 2020-04-17 2019-07-19 2020-05-08 2019-09-17 2020-06-12 2019-09-20 2020-12-09 Sociales capacity-building Selection NE-PCU-SV-161008-CS- 4. Strengthening project Individual INDV / Recrutement d'un IDA / V2450 management and stakeholder Post Consultant Open 40,000.00 2,394.05 Signed 2020-02-28 2020-07-08 2020-04-17 2021-04-13 2020-05-08 2021-05-02 2020-06-12 2021-05-18 2020-12-09 spécialiste en paiement capacity-building Selection numérique CS-INDV-4 / Consultant ( Individual Under Expert TDRS) pour préparer IDA / V2450 1. Enabling environment Post Consultant Open 50,000.00 0.00 2019-12-05 2021-03-01 2020-01-23 2020-02-13 2020-03-19 2020-09-15 Implementation des termes de référence Selection NE-PCU-SV-161006-CS- INDV / Recrutement d’un consultant individuel pour 4. Strengthening project Individual Under élaborer la Stratégie de IDA / V2450 management and stakeholder Post Consultant Open 40,000.00 13,792.81 2020-03-16 2020-05-22 2020-05-04 2020-02-17 2020-05-25 2021-02-22 2020-06-29 2020-12-26 Implementation Passation des Marches du capacity-building Selection Projet Villages Intelligents (PPSD). 4. Strengthening project Individual CS-INDV-24 / Specialiste en IDA / V2450 management and stakeholder Post Consultant Open 30,000.00 2,788.44 Signed 2020-05-22 2020-07-08 2020-07-10 2021-03-15 2020-07-31 2021-05-14 2020-09-04 2021-06-15 2021-03-03 Suivi-Evaluation capacity-building Selection 4. Strengthening project Individual CS-INDV-18 / Specialiste, IDA / V2450 management and stakeholder Post Consultant Open 40,000.00 2,712.53 Signed 2020-05-22 2020-07-08 2020-07-10 2021-03-03 2020-07-31 2021-03-23 2020-09-04 2021-03-23 2021-03-03 Technologies Numeriques capacity-building Selection NE-PCU-SV-203313-CS- INDV / Recrutement d’un (e) 4. Strengthening project Individual consultant (e) individuel (le) IDA / V2450 management and stakeholder Post Consultant Limited 25,000.00 17,102.43 Signed 2020-11-13 2020-12-23 2020-11-18 2021-03-08 2020-12-09 2021-03-25 2021-01-13 2021-03-31 2021-07-12 pour la mise en place du site capacity-building Selection Web institutionnel du Projet Villages Intelligents. NE-PCU-SV-209288-CS- 4. Strengthening project Individual Under INDV / Recrutement d’un (e) IDA / V2450 management and stakeholder Post Consultant Open 40,000.00 0.00 2020-12-18 2020-12-23 2021-02-05 2021-02-26 2021-04-02 2021-09-29 Implementation Auditeur (e) Interne capacity-building Selection CS-INDV-30 / Spécialiste de 4. Strengthening project Individual la Prospective et du Under IDA / 66880 management and stakeholder Post Consultant Open 40,000.00 0.00 2021-02-26 2021-02-26 2021-04-16 2021-05-07 2021-06-11 2021-12-08 Développement des Usages Implementation capacity-building Selection Numériques (SPDUN) CS-INDV-31 / Spécialiste des 4. Strengthening project Individual Under Systèmes d’Information et du IDA / 66880 management and stakeholder Post Consultant Open 40,000.00 0.00 2021-02-26 2021-02-26 2021-04-16 2021-05-07 2021-06-11 2021-12-08 Implementation Numérique (SSIN) capacity-building Selection CS-INDV-25 / Etude sur la Individual Under gouvernance du Fonds d' IDA / V2450 1. Enabling environment Post Consultant Open 20,000.00 0.00 2021-05-14 2021-05-16 2021-07-02 2021-07-23 2021-08-27 2022-02-23 Implementation Acces Universel (FAU) au Niger Selection Individual CS-INDV-26 / Charge de Under IDA / 66880 1. Enabling environment Post Consultant Limited 10,000.00 0.00 2021-05-20 2021-05-19 2021-05-25 2021-06-03 2021-06-15 2021-07-20 2022-01-16 Communication Implementation Selection CS-INDV-2 / Etude Individual 2. Developing rural d'Evaluation des pilotes IDA / V2450 Post Consultant Open 100,000.00 0.00 Canceled 2019-12-02 2020-01-20 2020-02-10 2020-03-16 2020-09-12 connectivity "Villages Intelligents Selection Page 3 Viet Nam: Investing and Innovating for Grassroots Service Delivery Reform PROJECT Procurement Plan (as of February 20, 2019) 1. Project information: Country: Viet Nam Borrower/Recipient: Socialist Republic of Viet Nam Project Name: Investing and Innovating for Grassroots Service Delivery Reform Project Project ID No: P161283 Project Implementing Agency: MoH and participating provinces 2. Bank’s approval date of the Procurement Plan • Original Plan: at project negotiation. • First Revision: … 3. Date of General Procurement Notice: …. 4. Period covered by this procurement plan: the first 18 months implementation I. Works and Goods and Non-Consultant Services: 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Annex II of the Procurement Regulations: Procurement Method Prior Review Thresholds Thresholds Applicable Category thresholds Applicable (in US$ Remarks thresholds Remarks equivalent (in US$) ) Works RFB through ≥ 20 million – Above US$ 10 Open million International market approach RFB through ≥ 200,000 – Above US$ 10 Open National < 20 million million market approach Request for < 200,000 – None Quotation Direct None No threshold; Same as for Selection meet competitive requirements selection 1 of regulations 7.13-7.15 Goods and Non-Consulting Services RFB through ≥ 3 million – Above US$ 2 Open million International market approach RFB through ≥ 100,000 - Above US$ 2 Open National < 3 million million market approach Request for < 100,000 None Quotation Direct None No threshold; Same as for Selection meet competitive requirements selection of regulations 7.13-7.15 2. Prequalification. Not expected for the works/goods packages. 3. Any Other Special Procurement Arrangements: National procurement procedures as specified under paragraph 5.4 of the Procurement Regulations and the conditions specified in Annex 1 to this Procurement Plan 4. Leased assets as specified under paragraph 5.10 of the Procurement Regulations: Not applicable. 5. Procurement of second hand Goods as specified under paragraph 5.11 of the Procurement Regulations: Not applicable. 6. Hands-on Expanded Implementation Support (HEIS) as specified under paragraph 3.10 and 3.11 of the Procurement Regulations: Not applicable. 7. Procurement packages for Goods (prior and post reviews) with method and Time Schedule Works Estimat Expecte Contract Revie Market Evaluati Ref. ed Cost Procureme d bid (Description w by approa on No. (US$10 nt Method opening ) Bank ch Method 00) time Works by provinces A Component 1 - Construction/Renovations of CHS/DHC Bac Can - construction of CHSs in Lowest Ngoc Phai, W_1_BC 440 RFB Post Q3 2020 National Evaluate Quang Bach d Cost commune (Cho Don District) 2 Works Estimat Expecte Contract Revie Market Evaluati Ref. ed Cost Procureme d bid (Description w by approa on No. (US$10 nt Method opening ) Bank ch Method 00) time Works by provinces A Component 1 - Construction/Renovations of CHS/DHC Bac Can - Renovation of Lowest W_2_BC 5 CHSs in 286 RFB Post Q2 2020 National Evaluate Ngan Son d Cost District Bac Can - Lowest Renovation of W_3_BC 158 RFQ Post Q3 2020 National Evaluate 3 CHSs in Na d Cost Ri District Ha Giang - construction of CHSs in Lowest W_1_H Ngam La, 704 RFB Post Q3 2020 National Evaluate G Sung Thai d Cost (Yen Minh District) Ha Giang - - Lowest W_2_H Renovation of 440 RFB Post Q2 2020 National Evaluate G 5 CHSs in Meo d Cost Vac District Ha Giang - - Renovation of Lowest W_3_H 3 CHSs in 528 RFB Post Q3 2020 National Evaluate G Quan Ba d Cost District Son La - construction Lowest W_1_SL of 4 CHSs in 880 RFB Post Q2 2020 National Evaluate Thuan Chau d Cost District Son La - construction Lowest W_2_SL of 4 CHSs in 880 RFB Post Q3 2020 National Evaluate Luc Yen d Cost District Yen Bai- construction of CHSs in Lowest Lang Nhi, Ta W_1_YB 540 RFB Post Q3 2020 National Evaluate Xi Lang d Cost communes (Tram Tau District) Yen Bai - Lowest Renovation of W_2_YB 265 RFB Post Q2 2020 National Evaluate 4 CHSs in Yen d Cost Binh District Yen Bai - Lowest Renovation of W_3_YB 735 RFB Post Q3 2020 National Evaluate 4 CHSs in Luc d Cost Yen District 3 Works Estimat Expecte Contract Revie Market Evaluati Ref. ed Cost Procureme d bid (Description w by approa on No. (US$10 nt Method opening ) Bank ch Method 00) time Works by provinces A Component 1 - Construction/Renovations of CHS/DHC Hoa Binh - construction of CHS in Tan Lowest W_1_HB Son 364 RFB Post Q3 2020 National Evaluate Commune in d Cost Mai Chau District Hoa Binh - Lowest Renovation of W_2_HB 440 RFB Post Q2 2020 National Evaluate 3 CHSs in Mai d Cost Chau District Hoa Binh - Lowest Renovation of W_3_HB 295 RFB Post Q3 2020 National Evaluate 3 CHSs in Da d Cost Bac District Quang Binh - construction of 2 CHSs in Lowest W_1_Q Tan Trach, 140 RFQ Post Q3 2020 National Evaluate B Thuong Trach d Cost communes in Bo Trach District Quang Binh - Renovation of Lowest W_2_Q 4 CHSs in 194 RFQ Post Q2 2020 National Evaluate B Quang Ninh d Cost District Quang Binh - Renovation of Lowest W_3_Q 3 CHSs in 195 RFQ Post Q3 2020 National Evaluate B Quang Trach d Cost District Quang Tri - construction of 2 CHSs in Lowest Cam Tuyen, W_1_QT 300 RFB Post Q3 2020 National Evaluate Cam Chinh d Cost communes in Cam Lo District Quang Tri - Renovation of Lowest W_3_QT 3 CHSs in 466 RFB Post Q2 2020 National Evaluate Vinh Linh d Cost District Quang Ngai - construction Lowest W_1_Q of 3 CHSs in 660 RFB Post Q2 2020 National Evaluate B Binh Son d Cost District 4 Works Estimat Expecte Contract Revie Market Evaluati Ref. ed Cost Procureme d bid (Description w by approa on No. (US$10 nt Method opening ) Bank ch Method 00) time Works by provinces A Component 1 - Construction/Renovations of CHS/DHC Quang Ngai - Renovation of Lowest W_1_Q 3 CHSs in 352 RFB Post Q2 2020 National Evaluate N Quang Ninh d Cost District Quang Ngai - Lowest W_2_Q Renovation of 264 RFB Post Q3 2020 National Evaluate N 3 CHSs in Tra d Cost Bong District Ninh Thuan - construction of CHS in Lowest W_1_NT Phuong Hai 119 RFQ Post Q3 2020 National Evaluate communes in d Cost Ninh Hai District Ninh Thuan - Renovation of Lowest W_2_NT 4 CHSs in 185 RFQ Post Q2 2020 National Evaluate Thuan Nam d Cost District Bac Lieu - construction of CHS in Lowest Long Dien W_1_BL 264 RFB Post Q3 2020 National Evaluate Dong A d Cost commune in Dong Hai District Bac Lieu - Lowest Renovation of W_2_BL 132 RFQ Post Q2 2021 National Evaluate 2 CHSs in Hoa d Cost Binh District Tra Vinh - construction of 2 CHSs in Lowest W_1_TV Ham Giang, 380 RFB Post Q2 2020 National Evaluate Kim Son d Cost communes in Tra Cu District Tra Vinh - Lowest Renovation of W_2_TV 332 RFB Post Q2 2020 National Evaluate 4 CHSs in Cau d Cost Ngang District Hau Giang - construction Lowest W_1_H of CHS in Mai 704 RFB Post Q3 2020 National Evaluate G Dam town in d Cost Chau Thanh District 5 Works Estimat Expecte Contract Revie Market Evaluati Ref. ed Cost Procureme d bid (Description w by approa on No. (US$10 nt Method opening ) Bank ch Method 00) time Works by provinces A Component 1 - Construction/Renovations of CHS/DHC Hau Giang - Renovation of Lowest W_2_H 4 CHSs in 372 RFB Post Q2 2020 National Evaluate G Long My d Cost District Long An - construction Lowest W_1_LA of 3 CHSs in 572 RFB Post Q2 2020 National Evaluate Tan Hung d Cost District Long An - Lowest Renovation of W_2_LA 334 RFB Post Q2 2020 National Evaluate 4 CHSs in Moc d Cost Hoa District Long An - Lowest Renovation of W_3_LA 202 RFB Post Q3 2020 National Evaluate 3 CHSs in Ben d Cost Luc District Total Works 12,758 Goods Estimat Expecte Contract Revie Market Evaluati Ref. ed Cost Procureme d bid (Description w by approa on No. (US$10 nt Method opening ) Bank ch Method 00) time Goods by provinces B Component 2 GeneXpert equipment Ha Giang - G_1_HG GeneXpert 34.29 DS Post Q3 2020 DS NA equipment Ye Bai - 34.29 G_1_YB GeneXpert DS Post Q3 2020 DS NA equipment Hoa Binh - 68.57 G_1_HB GeneXpert DS Post Q3 2020 DS NA equipment Quang Binh - 102.86 G_1_QB GeneXpert DS Post Q3 2020 DS NA equipment Quang Tri - 102.86 G_1_QT GeneXpert DS Post Q3 2020 DS NA equipment Quang Ngai - 205.71 G_1_QN GeneXpert DS Post Q3 2020 DS NA equipment 6 Goods Estimat Expecte Contract Revie Market Evaluati Ref. ed Cost Procureme d bid (Description w by approa on No. (US$10 nt Method opening ) Bank ch Method 00) time Goods by provinces B Component 2 Ninh Thuan - 137.14 G_1_NT GeneXpert DS Post Q3 2020 DS NA equipment Bac Lieu - 102.86 G_1_BL GeneXpert DS Post Q3 2020 DS NA equipment Tra Vinh - 137.14 G_1_TV GeneXpert DS Post Q3 2020 DS NA equipment Hau Giang - G_1_Hu 68.57 GeneXpert DS Post Q3 2020 DS NA G equipment Long An - 205.71 G_1_LA GeneXpert DS Post Q3 2020 DS NA equipment Total GE 1,200 Vaccine Cold Chain equipment Bac Can - 77.89 G_2_BC Vaccine Cold DS Post Q3 2020 DS NA Chain Ha Giang - 168.38 G_2_HG Vaccine Cold DS Post Q3 2020 DS NA Chain Son La - 148.91 G_2_SL Vaccine Cold DS Post Q3 2020 DS NA Chain Yen Bai - 103.09 G_2_YB Vaccine Cold DS Post Q3 2020 DS NA Chain Hoa Binh - 126.00 G_2_HB Vaccine Cold DS Post Q3 2020 DS NA Chain Quang Binh - 68.73 G_2_QB Vaccine Cold DS Post Q3 2020 DS NA Chain Quang Tri - 59.56 G_2_QT Vaccine Cold DS Post Q3 2020 DS NA Chain Quang Ngai - 95.07 G_2_QN Vaccine Cold DS Post Q3 2020 DS NA Chain Ninh Thuan - 27.49 G_2_NT Vaccine Cold DS Post Q3 2020 DS NA Chain Bac Lieu - 27.49 G_2_BL Vaccine Cold DS Post Q3 2020 DS NA Chain Tra Vinh - 45.82 G_2_TV Vaccine Cold DS Post Q3 2020 DS NA Chain 7 Goods Estimat Expecte Contract Revie Market Evaluati Ref. ed Cost Procureme d bid (Description w by approa on No. (US$10 nt Method opening ) Bank ch Method 00) time Goods by provinces B Component 2 Hau Giang - G_2_Hu 13.75 Vaccine Cold DS Post Q3 2020 DS NA G Chain Long An - 37.80 G_2_LA Vaccine Cold DS Post Q3 2020 DS NA Chain Total VCC 1,000 DS Post Q3 2020 DS NA Total Works and 14,958 Goods 8 II. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Annex II of the Procurement Regulations: Procurement Method Prior Review Thresholds Thresholds Applicable Category Applicable thresholds thresholds (in US$ Remarks Remarks (in US$, equivalent millions) ) QCBS, QBS, ≥ 300,000 Shortlist of only ≥ 1.0 million FBS, LCS National (Using the Consultants most (Firms) for appropriate contract agreed market in the PP approach) CQS (Open or < 300,000 QCBS, QBS, FBS, None limited LCS) can be competition applied for through contracts with national or value under international $300,000 market approach, specified in the PP and agreed with the Bank. Direct None No threshold; Same as for Selection of meet competitive firms requirements of selection regulations 7.13- 7.15 Individual N/A Essential ≥ 300,000 depending individual and for the Consultants on nature of assignments will positions as services be defined in the specified in Procurement the PP agreed Plan agreed with with the Bank the Bank and in line with regulations 7.34- 7.39 using the most appropriate market approach 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than US$ 500,000 equivalent per contract, may comprise entirely of national consultants in 9 accordance with the provisions of paragraph 7.1, Section VII of the Procurement Regulations. 3. Consultancy Assignments with Selection Methods and Time Schedule Consulting Services Expecte Estimate Selecti d Revie Market Ref. Description of d Cost on Proposa Remar w by approa No. Assignment (US$ Metho l k Bank ch 1000) d Submiss ion Time B. Component 2 Post Training need assessment, development 12 and revisions of C_2b_ Nationa months professional 24 IC Post Q1 2020 1 l in 3 and years management training material C_2b_ IEC and Health Nationa 200 CQS Post Q1 2020 1 promotion l Development of the Balanced 6 C_2c_ Score cards - Nationa months 12 IC Post Q1 2020 1 health l in 1 system/public year health expert Development of 6 C_2c_ the Balanced Nationa months 12 IC Post Q1 2020 2 Score cards - l in 1 clinical expert year C. Component 3 Development of decree on functions and responsibilities of District 5 man- C_3a_ Health Center Nationa months 25 CQS/IC Post Q2 2020 1 (that cover l in a Regional clinic year and CHS) for primary health care at grassroot level Evidence for tracer conditions in the project to 5 man- C_3a_ provide inputs Nationa months 25 CQS/IC Post Q2 2020 2 for l in a development of year guidelines for Primary Healthcare at 10 commune level (to replace Decision 2919/QD-BYT International Experience on e-learning for continuous training, to 3 man- C_3a_ provide inputs Nationa months 15 CQS/IC Post Q3 2020 3 for the l in 6 development of months new decree replacing decree 22/2013/TT-BYT Development and supervision of the implementation 36 of electronic man- C_3b_ health record Nationa 500 QCBS Post Q3 2020 month 1 module at l in 5 commune level years (trans district- commune), balanced score card software Design and pilot C_3b_ implementation Nationa 25 CQS/IC Post Q2 2021 2 of community l health screening Design and C_3b_ implementation Nationa 6 25 CQS/IC Post Q4 2020 3 of tools for l months clinical decision C_3b_ Nationa 6 Quality service 25 CQS/IC Post Q2 2021 4 l months C_3d_ Auditing Nationa 50 CQS Post Q2 2021 1 Service l C_3d_ Nationa Coordinator 36 IC Post Q1 2020 2 l C_3d_ Nationa Planning Expert 27 IC Post Q1 2021 3 l C_3d_ Disbursement Nationa 27 IC Post Q1 2022 4 Expert l C_3d_ Nationa FM expert 27 IC Post Q1 2023 5 l C_3d_ Procurement Nationa 27 IC Post Q1 2024 6 Expert l Total consulting services 1,082 Total Works, Goods and Consulting 16,040 Services 11 12 Annex 1 - Additional National Procurement Provisions. In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. 1. Open Competitive Procurement: When the Recipient uses its own national open competitive procurement arrangements as set forth in (a) Article 20 on Open Bidding of the Recipient’s Law on Procurement No. 43/2013/QH13 dated November 26, 2013 and related provisions necessary to effect the same; and (b) the Recipient’s Decree No. 63/2014/ND-CP dated June 26, 2014 Guiding Implementation of the Law on the Procurement (collectively, “National Procurement Laws”), such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. (i) No domestic preference over foreign bidders shall be granted to national bidders in bid evaluation, nor shall foreign bidders be asked or required to form joint ventures with or be subcontractors to national bidders in order to submit a bid. (ii) The model bidding documents (harmonized model bidding documents) agreed with the Association shall be used. (iii) No bid shall be eliminated from detailed evaluation on the basis of minor, non-substantive deviations. The evaluation of bidder’s qualifications shall be conducted separately subsequent to the technical and commercial evaluation of the bid. (iv) A bidder shall neither be required nor permitted, as a condition for award, to undertake obligations not specified in the bidding documents or otherwise to modify the bid as originally submitted. (v) No bid shall be rejected on the basis of a comparison with the employer’s estimate and budget ceiling. (vi) The Recipient shall implement an effective mechanism allowing bidders to complaint and have their complaints handled in a timely manner. The complaints mechanism shall allow the submission of anonymous complaints. 13 PROCUREMENT Vietnam : Investing and Innovating for Grassroots Health Service Delivery PLAN General Information Country: Vietnam Bank’s Approval Date of the Original Procurement Plan: 2020-09-22 2021-05-24 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P161283 GPN Date: 2020-09-14 Project Name: Investing and Innovating for Grassroots Health Service Delivery Loan / Credit No: IDA / 64390 T Executing Agency(ies): ra Vinh Provincial Project Management Unit for GSD WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned TV-C1-XL1: / Building and I mproving, upgrading commun e health satations in Tra Vinh province, phase 1 - Lot 01: "An Trưong A and N Component 1: Upgrading of Single Stage - One 2021-04- hi Long" IDA / 64390 Post Request for Bids Open - National 1,251,289.00 989,449.38 Signed 2020-09-25 2020-11-06 2020-09-30 2020-11-09 2020-10-30 2020-12-10 2020-11-13 2020-12-22 2020-11-27 2021-02-02 CHS Infrastructure Envelope 26 - Lot 02: "Long Hoa" - Lot 03: "Long Hiep and An Q uang Huu" - Lot 04: "Binh Phu and Đuc M y" TV-C1-XL2 / Xây dựng TYT x Request for Bids - ã Hưng Mỹ, TYT xã Lương Hòa Under Component 1: Upgrading of Single Stage - One Small Works SPD 2022-08- A huyện Châu Thành và TYT x IDA / 64390 Post Request for Bids Open - National 603,182.00 0.00 Implementat 2021-06-10 2021-06-24 2021-06-15 2021-07-17 2021-08-16 2021-09-05 CHS Infrastructure Envelope (1 envelope 21 ã Mỹ Long Bắc huyện Cầu Nga ion process) ng TV-C1-XL3 / Xây dựng TYT x Request for Bids - Under ã Hàm Giang, TYT xã Kim Sơn Component 1: Upgrading of Single Stage - One Small Works SPD 2022-08- IDA / 64390 Post Request for Bids Open - National 413,158.00 0.00 Implementat 2021-06-10 2021-06-24 2021-06-15 2021-07-17 2021-08-16 2021-09-05 huyện Trà Cú và TYT xã Phú C CHS Infrastructure Envelope (1 envelope 21 ion ần huyện Tiểu Cần process) LÔ 02, GÓI THẦU TV-C1-XL1 / Lô 02 TV-C1-XL01.02: Xây mới Trạm Y tế xã Long Hòa, h Request for Bids - Under uyện Châu Thành, thuộc Gói t Component 1: Upgrading of Single Stage - One Small Works SPD 2021-12- IDA / 64390 Post Request for Bids Open - National 262,507.00 0.00 Implementat 2021-05-24 2021-05-24 2021-05-25 2021-06-25 2021-07-05 2021-07-19 hầu TV-C1-XL1: Xây dựng và CHS Infrastructure Envelope (1 envelope 16 ion nâng cấp sửa chữa các Trạm Y process) tế trên địa bàn tỉnh Trà Vinh đ ợt 1 GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 1 Procurement Plan (Text Part) Bangladesh Insurance Sector Development Project (BISDP) Project information: (i) Country: Bangladesh (ii) Project Name: Bangladesh Insurance Sector Development Project (BISDP) (iii) P-Number: P156823 Project Implementation agency: Insurance Development and Regulatory Authority (IDRA) Period covered by this Procurement Plan: Entire Project Period 1. Preamble The Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to record all procurement actions for the Project, including preparing, updating and clearing its Procurement Plan, and seeking and receiving the Bank’s review and No-objection to procurement actions as required. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. 2. Prior Review Thresholds Procurement Prior Review Thresholds (US$ millions) Type of Substantial High risk Moderate risk Low risk Procurement risk Works (including turnkey, supply & installation of plant 5 10 15 20 and equipment, and PPP) Goods, information technology and 1.5 2 4 6 non-consulting services Consulting services: 0.5 1 2 4 firms Consulting services: 0.2 0.3 0.4 0.5 individuals Notes: 1. These thresholds apply to all procurement activities regardless of their procurement/selection methods. There is no automatic requirement to undertake prior review for direct selection for value less than these thresholds. Consultant services covers a range of services that are of an advisory or professional nature. 2. Use of Standard Procurement Documents: For all procurements under the project, the Bank’s Standard Procurement Documents (or other documents agreed with the Bank) shall be used; 3. Request for Bids (Open-National) will be carried out under the Bank Procurement Guidelines following procedures for Open Tendering Method (OTM) of the People’s Republic of Bangladesh (Public Procurement Act, 2006 – PPA, 2006 and The Public Procurement Rules, 2008 – PPR, 2008 using standard bidding documents satisfactory to the Bank. For the purpose of Request for Bids (Open-National) the following shall apply: a. Post bidding negotiations shall not be allowed with the lowest evaluated or any other bidder; b. Bids should be submitted and opened in public in one location immediately after the deadline for submission; c. Lottery in award of contracts shall not be allowed; d. Bidders’ qualification/experience requirement shall be mandatory; e. Bids shall not be invited or rejected on the basis of percentage above or below the estimated cost and contract award shall be based on the lowest evaluated bid price of compliant bid from eligible and qualified bidder; and f. Single stage two (2) envelope procurement system shall not be allowed. 2. Prequalification. Not Applicable. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: Not Applicable. 4. Reference to (if any) Project Operational/Procurement Manual: Not Applicable 5. Any Other Special Procurement Arrangements: Not Applicable. 6. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $ 500,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. Any Other Special Selection Arrangements: Not Applicable. PROCUREMENT Bangladesh : Bangladesh Insurance Sector Development Project PLAN General Information Country: Bangladesh Bank’s Approval Date of the Original Procurement Plan: 2017-01-09 2021-05-20 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P156823 GPN Date: 2019-04-03 Project Name: Bangladesh Insurance Sector Development Project Loan / Credit No: / , IDA / 59720 I Executing Agency(ies): nsurance Development and Regulatory Authority WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual G1-1 / IT & Supporting Project Implementation, Single Stage - One / Post Request for Bids Open - National 80,000.00 52,937.96 Signed 2017-04-05 2019-02-01 2017-04-10 2017-05-01 2019-02-16 2017-05-31 2019-03-14 2017-07-12 2019-04-30 2017-10-10 Equipment : Office Equipment Management, and Monitoring Envelope Project Implementation, Single Stage - One G1-2 / Furniture & Fixture IDA / 59720 Post Request for Bids Open - National 60,000.00 12,390.56 Signed 2019-03-15 2019-04-11 2019-04-04 2019-05-24 2019-05-06 2019-06-23 2019-05-09 2019-08-04 2019-05-22 2019-11-02 Management, and Monitoring Envelope Project Implementation, Single Stage - One G1-3 / IT Equipment IDA / 59720 Post Request for Bids Open - National 100,000.00 26,521.42 Signed 2019-02-25 2019-04-10 2019-03-12 2019-05-01 2019-04-30 2019-05-31 2019-05-08 2019-07-12 2019-05-21 2019-10-10 Management, and Monitoring Envelope Improving the Capacity of the G5 / Distance learning center Insurance Development and Single Stage - One with Videoconference and IDA / 59720 Regulatory Authority (IDRA) Post Request for Bids Open - National 600,000.00 377,300.03 Signed 2020-04-11 2019-11-21 2020-05-01 2020-07-05 2019-12-17 2020-09-13 2020-01-27 2020-10-25 2020-03-02 2021-01-23 Envelope audio visual facilities and the Bangladesh Insurance Academy ( BIA) Modernization, Strengthening G2-2-1 / Supply and and Increasing the Efficiency Single Stage - One IDA / 59720 Post Request for Bids Open - National 225,000.00 231,284.43 Signed 2019-04-14 2019-04-09 2019-04-19 2019-05-10 2019-04-29 2019-05-20 2019-06-09 2019-06-24 2019-05-20 2019-08-08 installation of IT equipment of the State-owned Insurance Envelope Corporations Improving the Capacity of the Insurance Development and G3-1 / Modernization Single Stage - One IDA / 59720 Regulatory Authority (IDRA) Post Request for Bids Open - National 500,000.00 235,182.08 Signed 2019-12-24 2019-12-12 2019-12-25 2020-01-08 2020-01-08 2020-02-10 2020-02-12 2020-03-19 2020-06-03 2020-06-15 Classroom Envelope and the Bangladesh Insurance Academy ( BIA) Improving the Capacity of the Insurance Development and G15 / Supply of Training Request for Single Stage - One IDA / 59720 Regulatory Authority (IDRA) Post Limited 6,250.00 5,727.23 Signed 2020-01-21 2019-06-10 2020-02-14 2019-06-16 2020-02-29 Materials (Bag) Quotations Envelope and the Bangladesh Insurance Academy ( BIA) G16 / Supply and Installation Project Implementation, Request for Single Stage - One IDA / 59720 Post Limited 6,250.00 5,817.07 Signed 2020-01-26 2019-08-07 2020-02-19 2019-08-22 2020-02-22 of IT Accessories for BISDP Management, and Monitoring Quotations Envelope G18 / Supply of Computer, Project Implementation, Request for Single Stage - One IDA / 59720 Post Limited 6,000.00 5,674.26 Signed 2020-01-21 2018-10-10 2020-02-16 2018-10-17 2020-03-07 Laptop, Printer and UPS Management, and Monitoring Quotations Envelope G19 / Supply of Digital Giant Project Implementation, Request for Single Stage - One screen / LED Television, IDA / 59720 Post Limited 6,200.00 5,837.30 Signed 2020-01-24 2019-03-21 2020-02-14 2019-03-27 2020-03-15 Management, and Monitoring Quotations Envelope Camera and Accessories G20 / Supply of Photocopier Project Implementation, Request for Single Stage - One IDA / 59720 Post Limited 6,150.00 5,791.98 Signed 2020-01-26 2019-01-17 2020-02-21 2019-01-23 2020-03-27 and Tablet Management, and Monitoring Quotations Envelope G21 / Supply of Furniture and Project Implementation, Request for Single Stage - One IDA / 59720 Post Limited 6,200.00 5,871.81 Signed 2020-02-27 2019-09-10 2020-03-31 2019-09-19 2020-05-30 Fixture Management, and Monitoring Quotations Envelope Improving the Capacity of the G2-2-2 / Supply and Insurance Development and Single Stage - One Installation of Computers and IDA / 59720 Regulatory Authority (IDRA) Post Request for Bids Open - National 941,000.00 776,334.81 Signed 2020-03-16 2020-03-19 2020-03-17 2020-04-14 2020-10-11 2020-04-21 2020-06-25 2020-05-19 2020-09-29 2020-06-28 Envelope Accessories and the Bangladesh Insurance Academy ( BIA) Improving the Capacity of the G6 / Development and Insurance Development and Single Stage - One Implementation of Interactive IDA / 59720 Regulatory Authority (IDRA) Post Request for Bids Open - National 600,000.00 0.00 Canceled 2020-11-10 2020-11-28 2021-01-09 2021-04-02 2021-05-14 2021-11-10 Envelope Portal and the Bangladesh Insurance Academy ( BIA) Improving the Capacity of the Insurance Development and G7-1 / Online approval of Single Stage - One IDA / 59720 Regulatory Authority (IDRA) Post Request for Bids Open - International 500,000.00 0.00 Canceled 2020-11-15 2020-12-16 2021-02-04 2021-05-15 2021-06-26 2022-02-21 agents Envelope and the Bangladesh Insurance Academy ( BIA) G7-2 / Certification of Project Implementation, Single Stage - One IDA / 59720 Post Request for Bids Open - International 500,000.00 0.00 Canceled 2020-12-29 2021-01-30 2021-03-25 2021-06-23 2021-08-04 2022-04-01 employers of agents & Management, and Monitoring Envelope brokers Improving the Capacity of the G10-1 / Business Intelligence Insurance Development and Single Stage - One and data analytics at IDRA & IDA / 59720 Regulatory Authority (IDRA) Post Request for Bids Open - International 1,600,000.00 0.00 Canceled 2020-12-07 2021-01-12 2021-03-07 2021-06-07 2021-07-19 2022-01-15 Envelope BIA and the Bangladesh Insurance Academy ( BIA) Improving the Capacity of the Insurance Development and G13 / Motor road accident Single Stage - One IDA / 59720 Regulatory Authority (IDRA) Post Request for Bids Open - National 700,000.00 0.00 Canceled 2020-11-10 2020-12-02 2021-01-21 2021-03-22 2021-05-03 2021-08-31 database Envelope and the Bangladesh Insurance Academy ( BIA) Page 1 Modernization, Strengthening G8 / Core Insurance and Increasing the Efficiency Single Stage - One IDA / 59720 Prior Request for Bids Open - International 7,500,000.00 0.00 Canceled 2020-11-25 2020-12-15 2021-02-03 2021-05-04 2021-06-15 2022-02-10 applications at SBC and JBC of the State-owned Insurance Envelope Corporations Modernization, Strengthening G9-2 / Document and Increasing the Efficiency Single Stage - One Management System for SBC IDA / 59720 Prior Request for Bids Open - International 3,000,000.00 0.00 Canceled 2020-10-13 2020-11-02 2020-12-22 2021-03-22 2021-05-03 2021-10-30 of the State-owned Insurance Envelope and JBC Corporations Improving the Capacity of the G9-1 / Document Insurance Development and Single Stage - One Management System for IDRA IDA / 59720 Regulatory Authority (IDRA) Prior Request for Bids Open - International 2,000,000.00 0.00 Canceled 2020-10-14 2020-11-03 2020-12-23 2021-03-23 2021-05-04 2021-10-31 Envelope & BIA and the Bangladesh Insurance Academy ( BIA) Modernization, Strengthening G14 / Call center & Customer and Increasing the Efficiency Single Stage - One Relationship Management IDA / 59720 Prior Request for Bids Open - International 4,000,000.00 0.00 Canceled 2020-12-15 2021-01-04 2021-02-23 2021-05-24 2021-07-05 2022-01-01 of the State-owned Insurance Envelope system at SBC and JBC Corporations Improving the Capacity of the Insurance Development and G12 / Centralized rating Single Stage - One IDA / 59720 Regulatory Authority (IDRA) Post Request for Bids Open - International 600,000.00 0.00 Canceled 2020-11-11 2020-11-26 2021-01-15 2021-04-15 2021-05-27 2021-09-24 system Envelope and the Bangladesh Insurance Academy ( BIA) G4-2 / Basic automation Modernization, Strengthening including ERP, HRMIS and and Increasing the Efficiency Single Stage - One IDA / 59720 Prior Request for Bids Open - International 6,000,000.00 0.00 Canceled 2020-10-20 2020-11-09 2020-12-29 2021-03-29 2021-05-10 2022-05-10 Enterprise E-mail System at of the State-owned Insurance Envelope SBC and JBC Corporations Improving the Capacity of the G4-1 / Basic automation Insurance Development and including ERP, HRMIS and Single Stage - One IDA / 59720 Regulatory Authority (IDRA) Prior Request for Bids Open - International 4,000,000.00 0.00 Canceled 2020-11-30 2020-12-20 2021-02-08 2021-05-09 2021-06-20 2022-06-20 Enterprice E-mail System for Envelope and the Bangladesh Insurance IDRA & BIA Academy ( BIA) Modernization, Strengthening G10-2 / Business Intelligence and Increasing the Efficiency Single Stage - One and data analytics at SBC and IDA / 59720 Prior Request for Bids Open - International 3,000,000.00 0.00 Canceled 2020-11-18 2020-12-08 2021-01-27 2021-04-27 2021-06-08 2021-12-05 of the State-owned Insurance Envelope JBC Corporations Improving the Capacity of the Insurance Development and G11 / Fraud detection and Single Stage - One IDA / 59720 Regulatory Authority (IDRA) Post Request for Bids Open - International 700,000.00 0.00 Canceled 2020-10-18 2020-11-02 2020-12-22 2021-03-22 2021-05-03 2021-08-31 prevention system Envelope and the Bangladesh Insurance Academy ( BIA) G2-1 / IT and Supporting Improving the Capacity of the Power Infrastructure (Tier 3 Insurance Development and Under Single Stage - One Data Centre & DR (Passive) for IDA / 59720 Regulatory Authority (IDRA) Prior Request for Bids Open - International 6,500,000.00 0.00 Implementati 2020-10-08 2021-02-02 2020-10-23 2020-12-04 2021-01-18 2021-02-25 2021-06-25 Envelope JBC, SBC, & IDRA and BIA Mini and the Bangladesh Insurance on Data Centre) Academy ( BIA) Improving the Capacity of the G4 / Basic automation Insurance Development and including ERP, HRMIS, Intranet Single Stage - One IDA / 59720 Regulatory Authority (IDRA) Prior Request for Bids Open - International 7,647,050.00 0.00 Under Review 2021-03-20 2021-04-04 2021-05-16 2021-06-30 2021-08-11 2022-08-15 and Enterprise E-mail System Envelope and the Bangladesh Insurance for IDRA, JBC, SBC and BIA Academy ( BIA) G23 / Software Applications (Fraud detection, Centralized rating system, Motor road Improving the Capacity of the accident database, Insurance Development and Single Stage - One Development of interactive IDA / 59720 Regulatory Authority (IDRA) Prior Request for Bids Open - International 9,411,764.00 0.00 Under Review 2021-06-16 2021-06-21 2021-08-02 2021-09-16 2021-10-28 2022-04-26 Envelope portal, online agent approval and the Bangladesh Insurance Certification agents , brokers, Academy ( BIA) Call centre and Business Intelligence for IDRA G24 / Supply of Air- Project Implementation, Request for Single Stage - One IDA / 59720 Post Limited 5,847.00 5,869.85 Signed 2021-01-24 2019-07-23 2021-01-24 2020-07-31 2021-01-24 conditioner Management, and Monitoring Quotations Envelope G-25 / Installation of Tally Project Implementation, Request for Single Stage - One IDA / 59720 Post Limited 2,415.00 2,394.58 Signed 2021-01-24 2019-12-23 2021-01-24 2019-12-29 2021-01-24 ERP Software Management, and Monitoring Quotations Envelope G-26 / Supply of Stationary Project Implementation, Request for Single Stage - One IDA / 59720 Post Limited 5,894.00 5,727.91 Signed 2021-01-25 2019-09-23 2021-01-25 2019-09-30 2021-01-25 and Goods Management, and Monitoring Quotations Envelope G-27 / Supply of Goods (Bag) Project Implementation, Request for Single Stage - One IDA / 59720 Post Limited 5,824.00 5,810.80 Signed 2021-01-25 2020-02-02 2021-01-25 2020-02-10 2021-01-25 for Training and Workshop Management, and Monitoring Quotations Envelope G-28 / Supply of Office Project Implementation, Request for Single Stage - One IDA / 59720 Post Limited 5,540.00 5,365.88 Signed 2021-01-26 2020-09-29 2021-01-26 2020-10-05 2021-01-26 Equipment (IT Accessories) Management, and Monitoring Quotations Envelope G-29 / Supply of Stationary & Project Implementation, Request for Single Stage - One IDA / 59720 Post Limited 5,882.00 5,729.63 Signed 2021-01-27 2020-09-29 2021-01-27 2020-10-05 2021-01-27 Goods Management, and Monitoring Quotations Envelope G-30 / Supply of Furniture & Project Implementation, Request for Single Stage - One IDA / 59720 Post Limited 5,730.00 5,637.13 Signed 2021-01-27 2020-09-29 2021-01-27 2020-10-05 2021-01-27 Fixture Management, and Monitoring Quotations Envelope G-31 / Supply of Office Project Implementation, Request for Single Stage - One IDA / 59720 Post Limited 5,843.00 5,843.51 Signed 2021-02-02 2020-11-12 2021-02-02 2020-11-18 2021-02-02 Equipment Management, and Monitoring Quotations Envelope Improving the Capacity of the G9 / Document management Insurance Development and Single Stage - One system for IDRA, SBC, JBC & IDA / 59720 Regulatory Authority (IDRA) Prior Request for Bids Open - International 5,000,000.00 0.00 Under Review 2021-03-15 2021-03-30 2021-05-11 2021-06-25 2021-08-06 2022-02-02 Envelope BIA and the Bangladesh Insurance Academy ( BIA) Improving the Capacity of the Insurance Development and Pending G3-2 / Setting up Research Single Stage - One IDA / 59720 Regulatory Authority (IDRA) Post Request for Bids Open - National 300,000.00 0.00 Implementati 2021-03-31 2021-04-20 2021-06-09 2021-09-07 2021-10-19 2022-02-16 Center Envelope and the Bangladesh Insurance on Academy ( BIA) Page 2 G10 / Core Insurance applications, Business Modernization, Strengthening Under Intelligence, Call center and and Increasing the Efficiency Single Stage - One IDA / 59720 Prior Request for Bids Open - International 11,176,470.00 0.00 Implementati 2021-03-15 2021-03-30 2021-05-11 2021-06-30 2021-08-11 2022-02-07 Customer Relationship of the State-owned Insurance Envelope on Management System for JBC & Corporations SBC Modernization, Strengthening G4-1-1 / Supply and Under and Increasing the Efficiency Single Stage - One Installation of Computer and IDA / 59720 Post Request for Bids Open - National 1,882,352.00 0.00 Implementati 2021-04-04 2020-12-22 2021-04-14 2021-05-12 2021-01-20 2021-06-01 2021-06-13 2021-07-13 2021-10-11 of the State-owned Insurance Envelope Accessories on Corporations G2-2 / IT & Supporting Improving the Capacity of the Network infrastructure Insurance Development and Single Stage - One Systems, Server & Storage IDA / 59720 Regulatory Authority (IDRA) Prior Request for Bids Open - International 9,500,000.00 0.00 Under Review 2021-04-13 2021-05-06 2021-05-03 2021-05-16 2021-06-22 2021-09-20 2021-11-01 2022-08-31 Envelope (Active) for JBC, SBC, BIA & and the Bangladesh Insurance IDRA Academy ( BIA) Modernization, Strengthening Pending G22 / Supply of Training and Increasing the Efficiency Single Stage - One IDA / 59720 Post Request for Bids Open - National 15,000.00 0.00 Implementati 2021-07-31 2021-08-02 2021-08-16 2021-08-21 2021-09-04 2021-10-04 Bags of the State-owned Insurance Envelope on Corporations Improving the Capacity of the Insurance Development and Pending G32 / IT Equipment for end Request for Single Stage - One IDA / 59720 Regulatory Authority (IDRA) Post Limited 17,500.00 0.00 Implementati 2021-06-15 2021-07-20 2021-08-19 user Quotations Envelope and the Bangladesh Insurance on Academy ( BIA) NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual G17 / Supply of Printing Project Implementation, Request for Single Stage - One IDA / 59720 Post Limited 5,937.00 3,819.70 Signed 2020-01-21 2019-09-23 2020-02-13 2019-09-30 2020-02-28 Document Management, and Monitoring Quotations Envelope CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Improving the Capacity of the Insurance Development and S4 / Sector-wide Protection Quality And Cost- / Regulatory Authority (IDRA) Post Open - International 500,000.00 603,750.00 Signed 2017-10-17 2019-03-13 2017-11-07 2019-03-21 2017-12-26 2019-07-11 2018-01-23 2019-08-25 2018-04-01 2019-11-03 2018-05-06 2019-12-02 2018-06-17 2020-01-27 2020-06-16 Gap study - Firm Based Selection and the Bangladesh Insurance Academy ( BIA) Improving the Capacity of the S5 / Awareness and Insurance Development and Quality And Cost- Insurance Literacy program - / Regulatory Authority (IDRA) Post Open - International 600,000.00 718,750.00 Signed 2018-04-18 2019-07-15 2018-05-09 2019-07-15 2018-06-30 2019-10-10 2018-07-28 2019-11-14 2018-10-03 2019-11-20 2018-11-07 2020-02-27 2018-12-19 2020-02-27 2021-12-18 Based Selection Firm and the Bangladesh Insurance Academy ( BIA) Improving the Capacity of the S2-1 / International Insurance Development and Quality And Cost- Under Regulatory and Supervisor IDA / 59720 Regulatory Authority (IDRA) Prior Open - International 2,000,000.00 0.00 2019-02-26 2019-03-09 2019-03-28 2019-04-03 2019-06-16 2019-10-17 2019-06-18 2019-12-02 2019-08-07 2020-03-15 2019-09-04 2020-10-22 2019-10-16 2022-10-15 Based Selection Implementation Expert Firm and the Bangladesh Insurance Academy ( BIA) Modernization, Strengthening S8-1 / Review of Financial and Increasing the Efficiency Quality And Cost- / Post Open - International 400,000.00 0.00 Canceled 2017-12-31 2018-01-21 2018-03-06 2018-04-03 2018-06-02 2018-07-07 2018-08-18 2020-08-07 Condition of SBC - Firm of the State-owned Insurance Based Selection Corporations Modernization, Strengthening S8-2 / Review of Financial and Increasing the Efficiency Quality And Cost- / Post Open - International 300,000.00 0.00 Canceled 2017-12-31 2018-01-21 2018-03-06 2018-04-03 2018-06-02 2018-07-07 2018-08-18 2020-08-17 Condition of JBC - Firm of the State-owned Insurance Based Selection Corporations S13-3-1 / Selection of Modernization, Strengthening International IT Consulting and Increasing the Efficiency Quality And Cost- Firm for review of IT IDA / 59720 Prior Open - International 1,000,000.00 1,025,121.70 Signed 2019-07-15 2019-07-17 2019-08-05 2019-07-29 2019-09-18 2019-12-11 2019-10-16 2020-01-15 2019-11-15 2020-07-30 2019-12-20 2020-09-28 2020-01-24 2020-10-19 2022-07-12 of the State-owned Insurance Based Selection requirements and Corporations Implementation Support Modernization, Strengthening S11 / Asset Liability and Increasing the Efficiency Quality And Cost- IDA / 59720 Prior Open - International 1,000,000.00 700,677.05 Signed 2019-07-14 2019-07-16 2019-08-04 2019-07-30 2019-09-17 2019-12-06 2019-10-15 2020-01-13 2019-12-14 2020-03-12 2020-01-18 2020-07-16 2020-02-29 2020-08-18 2022-08-31 Management Study - Firm of the State-owned Insurance Based Selection Corporations Modernization, Strengthening S7 / Review existing product and Increasing the Efficiency Quality And Cost- IDA / 59720 Post Open - International 500,000.00 0.00 Canceled 2021-01-11 2021-02-01 2021-03-17 2021-04-14 2021-07-03 2021-08-07 2021-09-18 2022-07-15 lines - Firm of the State-owned Insurance Based Selection Corporations Modernization, Strengthening S12 / Life Insurance and Increasing the Efficiency Quality And Cost- Distribution Network Expert IDA / 59720 Post Open - International 500,000.00 0.00 Canceled 2021-01-10 2021-01-31 2021-03-27 2021-04-24 2021-06-23 2021-07-28 2021-09-08 2022-07-05 of the State-owned Insurance Based Selection (Broker Agent) - Firm Corporations Improving the Capacity of the Insurance Development and S2-2 / Legal and Regulatory Quality And Cost- IDA / 59720 Regulatory Authority (IDRA) Prior Open - International 1,000,000.00 0.00 Canceled 2021-01-12 2021-02-26 2021-05-27 2021-07-16 2021-10-19 2021-11-30 2022-01-11 2022-08-09 Expert - Firm Based Selection and the Bangladesh Insurance Academy ( BIA) Modernization, Strengthening S14 / Review of existing and Increasing the Efficiency Quality And Cost- Pending product lines & Insurance IDA / 59720 Prior Open - International 1,000,000.00 0.00 2021-04-15 2021-05-06 2021-07-17 2021-08-14 2021-09-13 2021-10-18 2021-11-22 2022-08-31 of the State-owned Insurance Based Selection Implementation Distribution Network-Firm Corporations Modernization, Strengthening and Increasing the Efficiency Quality And Cost- Pending S10-1 / Acturial Firm - Firm IDA / 59720 Prior Open - International 1,000,000.00 0.00 2021-05-31 2021-06-21 2021-08-04 2021-09-01 2021-10-31 2021-12-05 2022-01-16 2022-08-31 of the State-owned Insurance Based Selection Implementation Corporations Page 3 Improving the Capacity of the Insurance Development and Consultant S15 / Selection of Client Under IDA / 59720 Regulatory Authority (IDRA) Post Qualification Open - National 100,000.00 0.00 2021-03-31 2021-05-19 2021-04-21 2021-06-04 2021-07-04 2021-08-08 2022-08-31 Satisfaction Survey firm Implementation and the Bangladesh Insurance Selection Academy ( BIA) Consultant S16 / External Audit Firm for Project Implementation, IDA / 59720 Post Qualification Open - National 5,870.00 0.00 Under Review 2021-05-31 2021-06-13 2021-06-03 2021-06-17 2021-06-24 2021-06-30 2022-08-31 Internal Audit Management, and Monitoring Selection INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Individual S1-3 / Senior Financial Project Implementation, IDA / 59720 Post Consultant Open 265,000.00 179,062.51 Signed 2019-03-04 2019-03-01 2019-04-08 2019-03-04 2019-04-29 2019-03-10 2019-06-10 2018-08-19 2022-09-22 Management Specialist Management, and Monitoring Selection Individual S1-9 / Project Associate - 4 Project Implementation, Under IDA / 59720 Post Consultant Open 210,000.00 0.00 2019-03-13 2019-02-06 2019-05-17 2019-06-07 2019-07-19 2022-12-30 Nos Management, and Monitoring Implementation Selection Individual S1-2 / Scenior Procurement Project Implementation, IDA / 59720 Post Consultant Open 240,000.00 219,953.81 Signed 2019-03-07 2018-08-23 2019-05-11 2018-11-18 2019-06-01 2019-02-12 2019-06-15 2019-02-12 2022-11-09 Specialist Management, and Monitoring Selection Individual S1-4 / Monitoring & Project Implementation, IDA / 59720 Post Consultant Open 240,000.00 198,363.59 Signed 2019-03-12 2018-07-08 2019-05-16 2019-04-09 2019-06-06 2019-04-30 2019-07-18 2019-04-30 2022-12-29 Evaluation Specialist Management, and Monitoring Selection Individual Project Implementation, S1-6 / IT Specialist IDA / 59720 Post Consultant Open 210,000.00 222,029.65 Signed 2019-03-13 2019-02-06 2019-05-17 2019-05-02 2019-06-07 2019-05-06 2019-07-19 2019-06-13 2022-12-30 Management, and Monitoring Selection Individual S1-5 / Project Management Project Implementation, IDA / 59720 Post Consultant Open 240,000.00 219,386.44 Signed 2019-03-13 2019-02-06 2019-05-17 2019-04-16 2019-06-07 2019-04-17 2019-07-19 2019-06-10 2022-12-30 Specialist- Individual Management, and Monitoring Selection Individual S1-1 / Deputy Project Project Implementation, / Prior Consultant Open 320,000.00 0.00 Canceled 2016-11-30 2017-02-03 2017-02-24 2017-04-07 2023-03-07 Director Management, and Monitoring Selection Improving the Capacity of the Insurance Development and Individual S13-1 / ERP Specialist / Regulatory Authority (IDRA) Prior Consultant Open 600,000.00 0.00 Canceled 2017-06-29 2017-10-12 2017-11-02 2017-12-14 2021-12-13 and the Bangladesh Insurance Selection Academy ( BIA) Modernization, Strengthening Individual S13-4 / Document and Increasing the Efficiency / Post Consultant Open 200,000.00 0.00 Canceled 2018-06-28 2018-08-27 2018-09-17 2018-10-29 2020-11-27 Management Specialist of the State-owned Insurance Selection Corporations Individual S1-8 / Account Associate - Project Implementation, IDA / 59720 Post Consultant Open 240,000.00 63,437.04 Signed 2019-03-13 2019-02-06 2019-05-17 2019-04-16 2019-06-07 2019-04-17 2019-07-19 2019-06-24 2022-12-30 Individual Management, and Monitoring Selection Improving the Capacity of the Insurance Development and Individual S10-3-1 / Selection of Life IDA / 59720 Regulatory Authority (IDRA) Prior Consultant Open 420,000.00 479,484.90 Signed 2019-03-11 2019-04-03 2019-06-24 2019-08-29 2019-07-15 2019-11-16 2019-08-19 2019-11-20 2022-12-01 Insurance Actuary and the Bangladesh Insurance Selection Academy ( BIA) Modernization, Strengthening S6-3 / Resident Adviser Individual and Increasing the Efficiency (Reinsurance/ Insurance / Prior Consultant Open 500,000.00 0.00 Canceled 2017-07-31 2017-11-03 2017-11-24 2018-01-05 2021-12-15 of the State-owned Insurance Expert) Selection Corporations Modernization, Strengthening Individual S10-3 / Life Insurance and Increasing the Efficiency IDA / 59720 Prior Consultant Open 600,000.00 0.00 Canceled 2019-02-26 2019-06-11 2019-07-02 2019-08-13 2024-08-11 Actuary of the State-owned Insurance Selection Corporations Modernization, Strengthening S13-1-1 / Selection of IT Individual and Increasing the Efficiency Specialist (Information/Cyber IDA / 59720 Post Consultant Open 180,000.00 88,663.18 Signed 2019-07-07 2019-07-08 2019-08-25 2020-07-01 2019-09-15 2020-07-01 2019-10-20 2020-08-23 2022-08-31 of the State-owned Insurance Security) Selection Corporations Modernization, Strengthening Individual S13-2 / Data Analytics and Increasing the Efficiency IDA / 59720 Prior Consultant Open 420,000.00 0.00 Canceled 2019-08-22 2019-12-15 2020-01-05 2020-02-16 2022-02-15 Specialist of the State-owned Insurance Selection Corporations Modernization, Strengthening Individual and Increasing the Efficiency S13-3 / IT Specialist for IDRA / Post Consultant Open 200,000.00 0.00 Canceled 2018-06-28 2018-08-27 2018-09-17 2018-10-29 2020-11-27 of the State-owned Insurance Selection Corporations Improving the Capacity of the S6-3-1 / Resident Adviser Insurance Development and Individual (Insurance and Reinsurance IDA / 59720 Regulatory Authority (IDRA) Post Consultant Open 270,000.00 0.00 Canceled 2019-03-11 2019-03-18 2019-06-24 2019-07-15 2019-08-19 2022-12-01 Expert) and the Bangladesh Insurance Selection Academy ( BIA) Modernization, Strengthening S13-2-1 / Selection of IT Individual and Increasing the Efficiency Specialist (Insurance Core IDA / 59720 Post Consultant Open 180,000.00 0.00 Canceled 2019-07-22 2019-07-08 2019-09-09 2019-09-30 2019-11-04 2022-08-31 of the State-owned Insurance applications) Selection Corporations Modernization, Strengthening S6-3-2 / Resident Adviser Individual and Increasing the Efficiency (Insurance & Reinsurance IDA / 59720 Prior Consultant Limited 270,000.00 562,024.62 Signed 2020-02-24 2019-10-10 2020-02-29 2019-12-05 2020-03-07 2020-07-30 2020-03-21 2020-09-01 2022-04-10 of the State-owned Insurance Expert) Selection Corporations Page 4 Modernization, Strengthening Individual and Increasing the Efficiency S6-1 / Reinsurance Expert IDA / 59720 Post Consultant Open 250,000.00 0.00 Canceled 2020-12-22 2021-03-17 2021-04-07 2021-05-19 2022-07-13 of the State-owned Insurance Selection Corporations Improving the Capacity of the S2-3 / International Insurance Development and Individual Regulatory/ Supervisory IDA / 59720 Regulatory Authority (IDRA) Prior Consultant Open 350,000.00 0.00 Canceled 2020-12-30 2021-06-13 2021-07-04 2021-08-15 2022-08-30 Expert and the Bangladesh Insurance Selection Academy ( BIA) Modernization, Strengthening Individual S9 / Non-Life Distribution and Increasing the Efficiency IDA / 59720 Prior Consultant Open 300,000.00 0.00 Canceled 2021-01-13 2021-04-28 2021-05-19 2021-06-30 2022-08-24 Network Expert of the State-owned Insurance Selection Corporations Individual S1-7 / Finance Associate - Project Implementation, Under IDA / 59720 Post Consultant Open 100,000.00 0.00 2021-01-13 2019-02-06 2021-03-19 2021-04-09 2021-05-21 2022-06-25 Individual Management, and Monitoring Implementation Selection Improving the Capacity of the Insurance Development and Individual S3 / Insurance Data IDA / 59720 Regulatory Authority (IDRA) Prior Consultant Open 400,000.00 0.00 Canceled 2021-01-19 2021-06-23 2021-07-14 2021-08-25 2022-08-20 Specialist/ non-life Actuary and the Bangladesh Insurance Selection Academy ( BIA) Modernization, Strengthening Individual S6-2 / Reinsurance/ and Increasing the Efficiency IDA / 59720 Post Consultant Open 296,250.00 0.00 Canceled 2020-11-18 2021-02-21 2021-03-14 2021-04-25 2022-06-19 Insurance Expert of the State-owned Insurance Selection Corporations Modernization, Strengthening Individual S10-2 / Life Insurance Expert and Increasing the Efficiency IDA / 59720 Post Consultant Open 185,000.00 0.00 Canceled 2021-01-03 2021-02-28 2021-03-21 2021-05-02 2022-05-02 - Actuary of the State-owned Insurance Selection Corporations S13-2-2 / Selection of IT Individual Project Implementation, Specialist (Insurance Core IDA / 59720 Post Consultant Limited 180,000.00 0.00 Canceled 2020-10-21 2020-10-31 2020-11-15 2020-12-13 2022-02-06 Management, and Monitoring Applications) Selection Individual S1-2-2 / Senior Procurement Project Implementation, IDA / 59720 Post Consultant Open 106,000.00 82,552.05 Signed 2021-02-15 2020-12-02 2021-04-05 2021-04-12 2021-04-26 2021-04-12 2021-05-31 2021-06-01 2022-08-31 Specialist Management, and Monitoring Selection Individual S1-2-1 / Senior Procurement Project Implementation, IDA / 59720 Post Consultant Limited 106,000.00 0.00 Canceled 2020-09-21 2020-09-26 2020-10-06 2020-11-04 2022-08-26 Specialist Management, and Monitoring Selection Page 5 PROCUREMENT PLAN (Mandatory Requirement) Project information: Country: Bhutan Project Name: COVID-19 Emergency Response and Health Systems Preparedness Project P-number: P173787 Project Implementation agency: Ministry of Health (MoH) Period covered by this Procurement Plan: Entire Project Period Preamble In accordance with paragraph 5.9 of the World Bank Procurement Regulations for IPF Borrowers, July 2016, revised November 2017 and August 2018 (“Procurement Regulations”), the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to record all procurement actions for the Project, including preparing, updating and clearing its Procurement Plan, and seeking and receiving the Bank’s review and No-objection to procurement actions as required. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: The Bank’s Standard Procurement Documents (SPDs) shall be used for all contracts subject to international competitive procurement and those contract as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the World Bank Procurement Regulations, when approaching the national market, as agreed in the Procurement Plan, the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Procurement Rules and Regulations, 2019, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions: 1) At the Borrower’s request, the Bank may agree to the Borrower’s use, in whole or in part, of its electronic procurement system, provided that the Bank is satisfied with the adequacy of such system. 2) Procurement shall be open to eligible bidders as defined under Section III of the Procurement Regulations. Accordingly, no bidder or potential bidder shall be declared ineligible for contracts financed by the Bank for reasons other than those provided in Section III of the Procurement Regulations. 3) The request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance (in the form attached) at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. 4) Procurement Documents include provisions, as agreed with the Bank, intended to adequately mitigate against environmental, social (including sexual exploitation and abuse and gender-based violence), health and safety (“ESHS”) risks and impacts. 5) The Bank shall have the right to review procurement documentation and activities. When other national procurement arrangements (other than national open competitive procurement) are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. As per paragraph 5.4 of the Procurement Regulations, the “Letter of Acceptance of the World Bank’s Anticorruption Guidelines and Sanctions Framework” as attached to this document shall form part of the Model Bidding Documents. Leased Assets: Not Applicable. Procurement of Second-Hand Goods: as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables – Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Specify for each Goods: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables]; Works: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables] Hands-on Expanded Implementation Support (HEIS): as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. Bank’s Procurement Prior Review Thresholds: As this is an emergency response project, there will be no prior review for all procurement during the immediate response period. The project will also have increased threshold for Request for Quotations (RFQ) and national procurement, as applicable in emergency projects. Procurement under Retroactive Financing: Contracts that were procured during the period January 1, 2020 and prior to signing of the Financing Agreement will be eligible for the World Bank’s retroactive financing, if: (i) the procurement procedures, including advertising, are consistent with Sections I, II and III of the Procurement Regulations; and (ii) the contractor/supplier/consultant has explicitly agreed to comply with the relevant provisions of the World Bank’s Anti-Corruption Guidelines, including the World Bank’s right to inspect and audit all accounts, records, and other documents relating to the project that are required to be maintained pursuant to the Financing Agreement. However, there are practical limits to the application of the Anti-Corruption Guidelines in the case of unsuccessful bidders for these retroactively financed contracts. Accordingly, the waiver of paragraph 6 (requiring that the Anti-Corruption Guidelines be applied to all procurement) and paragraphs 9(d) and 10 (requiring agreement by bidders and contractors to comply with the Anti- Corruption Guidelines) of the Anti-Corruption Guidelines, as requested by the Global MPA, will apply to the project. Letter of Acceptance of the World Bank’s Anticorruption Guidelines and Sanctions Framework1 Date: Invitation of Bids/Proposals No.__________ To: ___________________________________________________________________________ We, along with our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not) consultants and personnel, acknowledge and agree to abide by the World Bank’s policy regarding Fraud and Corruption (corrupt, fraudulent, collusive, coercive, and obstructive practices), as set out and defined in the World Bank’s Anti-Corruption Guidelines2 in connection with the procurement and execution of the contract (in case of award), including any amendments thereto. 1[Drafting note: This document shall be signed by bidders/proposers/consultants and submitted as part of their bids/proposals. In addition, this document shall be signed by the winning bidder/consultant and incorporated as part of the contract.] 2Guidelines on Preventing and Combating Fraud and Corruption in Projects Financed by International Bank for Reconstruction and Development Loans and the International Development Agency Credits and Grants, dated October 15, 2006, and revised in January 2011 and July 2016, as they may be revised from time to time. We declare and warrant that we, along our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not), consultants and personnel, are not subject to, and are not controlled by any entity or individual that is subject to, a temporary suspension, early temporary suspension, or debarment imposed by a member of the World Bank Group, including, inter alia, a cross-debarment imposed by the World Bank Group as agreed with other international financial institutions (including multilateral development banks), or through the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement. Further, we are not ineligible under the laws or official regulations of [Insert name of Employer as per bidding document] or pursuant to a decision of the United Nations Security Council. We confirm our understanding of the consequences of not complying with the World Bank’s Anti-Corruption Guidelines, which may include the following: a. rejection of our Proposal/Bid for award of contract; b. in the case of award, termination of the contract, without prejudice to any other remedy for breach of contract; and c. sanctions, pursuant to the Bank’s Anti-Corruption Guidelines and in accordance with its prevailing sanctions policies and procedures as set forth in the Bank’s Sanctions Framework. This may include a public declaration of ineligibility, either indefinitely or for a stated period of time, (i) to be awarded or otherwise benefit from a Bank-financed contract, financially or in any other manner;3 (ii) to be a nominated4 sub-contractor, sub-consultant, consultant, manufacturer or supplier, or service provider of an otherwise eligible firm being awarded a Bank-financed contract; and (iii) to receive the proceeds of any loan made by the Bank or otherwise to participate further in the preparation or implementation of any Bank-financed project. We understand that we may be declared ineligible as set out above upon: a. completion of World Bank Group sanctions proceedings according to its prevailing sanctions procedures; b. cross-debarment as agreed with other international financial institutions (including multilateral development banks); 3For the avoidance of doubt, a sanctioned party’s ineligibility to be awarded a contract shall include, without limitation, (i) applying for pre-qualification or initial selection), expressing interest in a consultancy, and bidding, either directly or as a nominated sub- contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider, in respect of such contract, and (ii) entering into an addendum or amendment introducing a material modification to any existing contract. 4A nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider (different names are used depending on the bidding document) is one which has been: (i) included by the bidder in its pre-qualification or initial selection application or bid because it brings specific and critical experience and know- how that allow the bidder to meet the qualification requirements for the particular bid; or (ii) appointed by the Borrower. c. the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement; or d. temporary suspension or early temporary suspension in connection with an ongoing World Bank Group sanctions proceeding. For avoidance of doubt, the foregoing effects of ineligibility do not extend to a sanctioned firm’s or individual’s execution of its ongoing Bank-financed contracts (or its ongoing sub-agreements under such contracts) that are not the subject of a material modification, as determined by the Bank. We shall permit, and shall cause our sub-contractors, sub-consultants, agents (whether declared or not), personnel, consultants, service providers or suppliers, to permit the Bank to inspect5 all accounts, records, and other documents relating to the procurement process and/or contract execution (in the case of award), and to have them audited by auditors appointed by the Bank. We agree to preserve all accounts, records, and other documents (whether in hard copy or electronic format) related to the procurement and execution of the contract. Name of the Bidder/Proposer/Consultant: Name of the person duly authorized to sign the Bid/Proposal on behalf of the Bidder/Proposer/ Consultant: Title of the person signing the Letter: 5Inspections in this context are usually investigative (i.e., forensic) in nature: they involve fact-finding activities undertaken by the Bank or persons appointed by the Bank to address specific matters related to investigations/audits, such as evaluating the veracity of an allegation of possible Fraud and Corruption, through the appropriate mechanisms. Such activity includes but is not limited to accessing and examining a firm's or individual's financial records and information, and making copies thereof as relevant; accessing and examining any other documents, data, and information (whether in hard copy or electronic format) deemed relevant for the investigation/audit, and making copies thereof as relevant; interviewing staff and other relevant individuals; performing physical inspections and site visits; and obtaining third-party verification of information. PROCUREMENT Bhutan : Bhutan: COVID-19 Emergency Response and Health Systems Preparedness Project PLAN General Information Country: Bhutan Bank’s Approval Date of the Original Procurement Plan: 2020-05-18 2021-05-19 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P173787 GPN Date: 2020-07-21 Project Name: Bhutan: COVID-19 Emergency Response and Health Systems Preparedness Project Loan / Credit No: IDA / 66270 M Executing Agency(ies): inistry of Health, RGoB WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned MOH-PPD/WB- WORKS/2020/01 / Civil and electrical works for the extension and modification of Under Emergency COVID-19 Request for Single Stage - One 2021-03- loading/unloading area into IDA / 66270 Post Limited 24,200.00 0.00 Implementat 2020-11-08 2020-11-20 2020-12-09 Response Quotations Envelope 31 Walk-in cooler room and ion construction of pre-casualty unit at Mongar Regional Referral Hospital. W1-RFQ-LIMITED / Office refurbishment including electrical works, partition, , Community Engagement and Request for Single Stage - One 2020-08- working table and chair, for IDA / 66270 Post Limited 15,000.00 0.00 Canceled 2020-06-20 2020-07-12 Risk Communication Quotations Envelope 09 the three consultants and officers deputed from the MoH. MOH-PPD/WB- WORKS/2020/02 / Civil and Pending Emergency COVID-19 Request for Single Stage - One 2021-12- electrical works for the IDA / 66270 Post Limited 28,000.00 0.00 Implementat 2021-05-06 2021-07-01 Response Quotations Envelope 28 construction of Dialysis unit at ion Wangdiphodrang Hospital. MOH-PPD/WB- WORKS/2021/03 / Civil and Pending Emergency COVID-19 Other (with field 2021-12- electrical works for the IDA / 66270 Post Direct Selection Direct 70,000.00 0.00 Implementat 2021-05-17 2021-05-22 2021-06-26 Response for explanation) 23 construction of Flu Clinic at ion Thimphu. GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MOH/DMSHI/COVID- Emergency COVID-19 Request for Single Stage - One IDA / 66270 Post Open - National 10,000.00 10,589.51 Completed 2020-06-09 2020-08-04 2020-06-24 2021-01-31 2020-10-16 19/2020 / ICU Beds Response Quotations Envelope MOH-PPD/WB- PROCUREMENT/2020 / Implementation Management Request for Single Stage - One procurement of desktop, IDA / 66270 and Monitoring and Post Limited 7,000.00 0.00 Canceled 2020-07-06 2020-08-31 2021-02-27 Quotations Envelope laptop and printers for project Evaluation staff and project office. MOH-PPD/WB- PROCUREMENT/2020/02 / Surgical N95 respirator mask, Under Emergency COVID-19 good breathability with the IDA / 66270 Post Direct Selection Direct 500,000.00 0.00 Implementati 2020-07-24 2020-06-21 2022-07-25 2020-07-13 2022-08-29 2023-02-25 Response design that does not collapse on against mouth. No valve Quantity : 90,000 number. MSPD/COVID-19/2020/2230 / Supply of medicines: Emergency COVID-19 Lopinavir + Ritonavir : Qty. IDA / 66270 Post Direct Selection Direct 14,000.00 13,641.88 Completed 2020-08-03 2020-01-30 2020-08-08 2020-01-30 2020-09-12 2020-03-27 2021-03-11 2020-04-13 Response (20010) Azithromycin: Qty. (1500) MSPD/COVID-19/2020/2128 Emergency COVID-19 / Supply of medicines Qty. IDA / 66270 Post Direct Selection Direct 11,000.00 10,648.00 Completed 2020-08-03 2020-01-30 2020-08-08 2020-01-30 2020-09-12 2020-03-17 2021-03-11 2020-04-21 Response (50000) MOH/DMSHI/MSPD/NCORON Emergency COVID-19 O/2020/2167 / Supply of face IDA / 66270 Post Direct Selection Direct 11,666.67 11,677.09 Completed 2020-08-03 2020-01-30 2020-08-08 2020-01-30 2020-09-12 2020-03-14 2021-03-11 2020-04-02 Response masks: Qty: (50000) MOH/DMSHI/MSPD/NCORON O/2020/2087 / Supply of Emergency COVID-19 IDA / 66270 Post Direct Selection Direct 7,541.33 0.00 Canceled 2020-08-03 2020-01-30 2020-08-08 2020-01-30 2020-09-12 2021-03-11 blankets and pillows: Qty. Response (334) MOH/DMSHI/MSPD/NCORON Emergency COVID-19 O/2020/1953 / Supply of face IDA / 66270 Post Direct Selection Direct 58,500.00 58,931.03 Completed 2020-08-03 2020-01-30 2020-08-08 2020-01-30 2020-09-12 2020-02-19 2021-03-11 2020-03-10 Response mask. Qty. (150000) MOH/DMSHI/MSPD/NCORON O/2020/2093 / procurement Emergency COVID-19 IDA / 66270 Post Direct Selection Direct 3,000.00 3,003.51 Completed 2020-08-03 2020-01-30 2020-08-08 2020-01-30 2020-09-12 2020-03-17 2021-03-11 2020-04-09 of Suction machine. Response Qty: (10) MSPD/COVID-19/2020/2229 / Procurement of Emergency COVID-19 IDA / 66270 Post Direct Selection Direct 150.00 109.22 Completed 2020-08-03 2020-01-30 2020-08-08 2020-01-30 2020-09-12 2020-03-27 2021-03-11 2020-04-09 Azithromycin, 500mg. Response Qty:(500) MOH/COVID-19/2019- Emergency COVID-19 20/11961 / Procurement of IDA / 66270 Post Direct Selection Direct 130,000.00 120,000.00 Completed 2020-08-03 2020-04-03 2020-08-08 2020-04-03 2020-09-12 2020-04-03 2021-03-11 2020-04-14 Response 1200 tests/pkts (10 packets ) Page 1 MOH/DMSHI/MSPD/NCORON O/2020/2041 / Procurement Emergency COVID-19 IDA / 66270 Post Direct Selection Direct 10,000.00 9,867.23 Completed 2020-08-03 2020-01-30 2020-08-08 2020-01-30 2020-09-12 2020-02-20 2021-03-11 2020-04-02 of GC-Alcohol based hand rub Response of 150ml: Qty.(2450) MOH/DMSHI/MSPD/NCORON O/2020/1951 / Supply of GC Emergency COVID-19 IDA / 66270 Post Direct Selection Direct 250,000.00 223,889.84 Completed 2020-08-03 2020-01-30 2020-08-08 2020-01-30 2020-09-12 2020-02-01 2021-03-11 2020-03-13 General Consumables) : Qty: Response (48800) MOH/DMSHI/MSPD/NCORON Emergency COVID-19 O/2020/2145 / Procurement IDA / 66270 Post Direct Selection Direct 7,000.00 7,099.22 Completed 2020-08-03 2020-01-30 2020-08-08 2020-01-30 2020-09-12 2020-03-18 2021-03-11 2020-04-02 Response of Disinfectants (Qty: 1300) MOH/COVID-19/2019- 20/12196 / Procurement of Emergency COVID-19 IDA / 66270 Post Direct Selection Direct 17,000.00 16,880.88 Completed 2020-08-03 2020-04-15 2020-08-08 2020-04-15 2020-09-12 2020-04-15 2021-03-11 2020-04-23 masks N95; approved by Response NIOSH. Qty ( 3,200) MOH/DMSHI/MSPD/NCORON O/2020/1896 / Procurement of GC & PPEs: 1.Supply of N95/ V410 : Qty. (1600) Emergency COVID-19 IDA / 66270 Post Direct Selection Direct 290,000.00 288,226.84 Completed 2020-08-03 2020-01-30 2020-08-08 2020-01-30 2020-09-12 2020-01-30 2021-03-11 2020-03-26 2. Googles : Qty. (2000) Response 3. Plastic apron disposable: Qty.(2000) 4.Coverall size S: Qty.(7500) 5.Coverall size M: Qty.(7500) MOH/DMSHI/MSPD/NCORON O/2020/1950 / Procurement of GC: 1.oxygen flow meter and pulse oximeter: Qty. (30 each) Emergency COVID-19 IDA / 66270 Post Direct Selection Direct 26,000.00 19,424.41 Completed 2020-08-03 2020-01-30 2020-08-08 2020-01-30 2020-09-12 2020-01-30 2021-03-11 2020-04-02 2.Hydrogen Peroxide & Response glycerin: Qty.(1350 and 940 each) 3. Hand rub & Gloves Qty. (1050 and 69000 each) MOH/DMSHI/MSPD/NCORON O/2020/2144 / Procurement Emergency COVID-19 IDA / 66270 Post Direct Selection Direct 90,000.00 145,118.91 Completed 2020-08-03 2020-01-30 2020-08-08 2020-01-30 2020-09-12 2020-03-18 2021-03-11 2020-03-30 of PPEs: coverall size L&M Response (Qty: 5275) MOH/DMSHI/MSPD/NCORON Emergency COVID-19 O/2020/2196 / Procurement IDA / 66270 Post Direct Selection Direct 4,500.00 4,647.26 Completed 2020-08-03 2020-01-30 2020-08-08 2020-03-07 2020-09-12 2020-03-07 2021-03-11 2020-04-02 Response of GE; bed rail. Qt:(23) MOH/DMSHI/MSPD/NCORON O/2020/2021 / Procurement Emergency COVID-19 IDA / 66270 Post Direct Selection Direct 12,000.00 10,887.74 Completed 2020-08-03 2020-01-30 2020-08-08 2020-01-30 2020-09-12 2020-03-08 2021-03-11 2020-04-06 of PPEs and GC; (glycerine). Response Qty: (2900) MOH/DMSHI/MSPD/NCORON O/2020/2224 / Procurement Emergency COVID-19 IDA / 66270 Post Direct Selection Direct 7,800.00 7,618.01 Completed 2020-08-03 2020-01-30 2020-08-08 2020-01-30 2020-09-12 2020-03-25 2021-03-11 2020-04-07 of oxygen concentrator Qty. Response (12) MOH/DMSHI/MSPD/NCORON O/2020/2211 / Procurement of PPEs and Consumables; Emergency COVID-19 IDA / 66270 Post Direct Selection Direct 25,000.00 24,646.91 Completed 2020-08-03 2020-01-30 2020-08-08 2020-01-30 2020-09-12 2020-03-14 2021-03-11 2020-04-13 (surgical gowns disposable Response Size: L & M) Quantity: (24071) MOH/DMSHI/MSPD/NCORONA /2020/2087 / Procurement of Emergency COVID-19 IDA / 66270 Post Direct Selection Direct 7,541.33 7,722.58 Completed 2020-09-06 2020-01-30 2020-09-11 2020-03-14 2020-10-16 2020-03-14 2021-04-14 2020-04-02 equipments (blankets and Response pillow) MOH-PPD/WB- PROCUREMENT/2020/1 / Implementation Management Procurement of Laptops for IDA / 66270 and Monitoring and Post Direct Selection Direct 4,000.00 3,599.05 Completed 2020-10-11 2020-08-06 2020-10-16 2020-08-07 2020-11-20 2020-10-05 2021-05-19 2020-12-15 PMU staffs Evaluation Qty: 3 MOH/DMSHI/MSPD/COVID- 19/2020/2057 / Procurement Emergency COVID-19 Request for Single Stage - One of equipments & consumables- IDA / 66270 Post Open - National 100,600.00 0.00 Canceled 2020-11-05 2020-12-31 2021-06-29 Response Quotations Envelope Portable Ventilators, Astral 150 (QTY: 13) MOH/DMSHI/MSPD/NCORONA /2020/2097 / Procurement of Emergency COVID-19 Request for Single Stage - One IDA / 66270 Post Open - National 145,000.00 0.00 Canceled 2020-11-05 2020-12-31 2021-06-29 PPEs: Surgical Face Mask Response Quotations Envelope (QTY: 598,700) MOH/DMSHI/MSPD/COVID- 19/2020/2433 / supply of Emergency COVID-19 Request for Single Stage - One PPEs & consumables IDA / 66270 Post Open - National 93,000.00 0.00 Canceled 2020-11-05 2020-12-31 2021-06-29 Response Quotations Envelope -Surgical Face Mask (QTY: 300,000 nos) MOH/DMSHI/MSPD/COVID- 19/2020/2458 / Supply of Emergency COVID-19 Request for Single Stage - One Consumables IDA / 66270 Post Open - National 30.00 0.00 Canceled 2020-11-05 2020-12-31 2021-06-29 Response Quotations Envelope -Breathing circuit, Anesthesia, adult 22 mm (QTY: 5 sets) MOH/DMSHI/MSPD/COVID- 19/2020/2143 / Supply of Emergency COVID-19 Request for Single Stage - One PPEs IDA / 66270 Post Open - National 200.00 0.00 Canceled 2020-11-05 2020-12-31 2021-06-29 Response Quotations Envelope -Operation cap, size medium (50cm) (QTY: 14,000 nos) MOH/DMSHI/MSPD/COVID- 19/2020/2446 / Supply of Emergency COVID-19 Request for Single Stage - One PPEs IDA / 66270 Post Open - National 1,500.00 0.00 Canceled 2020-11-05 2020-12-31 2021-06-29 Response Quotations Envelope -surgical cap, non woven, disposable (QTY:126,900) Page 2 MOH/DMSHI/MSPD/COVID- 19/2020/2500 / Supply of Emergency COVID-19 Request for Single Stage - One consumables IDA / 66270 Post Open - National 6,000.00 0.00 Canceled 2020-11-05 2020-12-31 2021-06-29 Response Quotations Envelope -Disposable gloves , Size M & L (QTY: 100,000) MOH/DMSHI/MSPD/COVID- 19/2020/2418 / Supply of Emergency COVID-19 Request for Single Stage - One IDA / 66270 Post Open - National 5,000.00 0.00 Canceled 2020-11-05 2020-12-31 2021-06-29 Equipment-Foam mattress Response Quotations Envelope (QTY: 128) MOH/DMSHI/MSPD/COVID- 19/2020/2144 / Supply of PPEs & consumables Emergency COVID-19 Request for Single Stage - One -Coverall size S, White tyvek IDA / 66270 Post Open - National 150,000.00 0.00 Canceled 2020-11-05 2020-12-31 2021-06-29 Response Quotations Envelope (QTY: 4300) -Coverall size M, White Tyvek (QTY: 4300) MOH/DMSHI/MSPD/COVID- 19/2020/2194 / Supply of GC & Consumables-Oxygen Cylinder D type (QTY: 100 Emergency COVID-19 Request for Single Stage - One IDA / 66270 Post Open - National 23,000.00 0.00 Canceled 2020-11-05 2020-12-31 2021-06-29 nos) Response Quotations Envelope Supply of GC & Consumables- Oxygen Stand B type (QTY: 10 nos) MOH/DMSHI/MSPD/COVID- 19/2020/2092 / Supply of Emergency COVID-19 Request for Single Stage - One Equipment IDA / 66270 Post Open - National 26,000.00 0.00 Canceled 2020-11-05 2020-12-31 2021-06-29 Response Quotations Envelope -Defibrillator(Pediatric paddle) (QTY: 4) MOH/DMSHI/MSPD/COVID- 19/2020/2191 / Supply of Emergency COVID-19 Request for Single Stage - One IDA / 66270 Post Open - National 24,000.00 0.00 Canceled 2020-11-05 2020-12-31 2021-06-29 Equipment-Reverse Osmosis Response Quotations Envelope system (QTY: 1) MSDD/MED.GAS/2019- 2020/2065 / Filled Medical Oxygen Gas cylinders (QTY: Pending Emergency COVID-19 99 ) IDA / 66270 Post Direct Selection Direct 170.00 0.00 Implementati 2020-10-31 2020-11-05 2020-12-10 2021-06-08 Response [ Empty oxygen 'B' Type- 80 on nos and Empty Oxygen 'D' type- 19 nos ] MSDD/MED.GAS/2019- Pending 2020/2072 / Filled Medical Emergency COVID-19 IDA / 66270 Post Direct Selection Direct 260.00 0.00 Implementati 2020-10-31 2020-11-05 2020-12-10 2021-06-08 Oxygen Gas cylinders [Empty Response on Oxygen 'B' type] (QTY: 193) MSDD/MED.GAS/2019- Pending 2020/2105 / Filled Medical Emergency COVID-19 IDA / 66270 Post Direct Selection Direct 120.00 0.00 Implementati 2020-10-31 2020-11-05 2020-12-10 2021-06-08 Oxygen Gas cylinders[ Empty Response on Oxygen 'B' type] (QTY: 78 nos) MSDD/MED.GAS/2019- 2020/2047 / Filled Medical Oxygen Gas cylinders (QTY: Pending Emergency COVID-19 600 ) IDA / 66270 Post Direct Selection Direct 1,500.00 0.00 Implementati 2020-10-31 2020-11-05 2020-12-10 2021-06-08 Response [ Empty Oxygen 'D' type-300 on nos & purging ang blowing- 300 nos] MSDD/MED.GAS/2019- 2020/2104 / Filled Medical Oxygen Gas cylinders (QTY: Pending Emergency COVID-19 89) IDA / 66270 Post Direct Selection Direct 170.00 0.00 Implementati 2020-10-31 2020-11-05 2020-12-10 2021-06-08 Response [Empty Oxygen 'B' type-54 on nos & Empty Oxygen 'D' type- 35 nos] MSDD/MED.GAS/2019- Pending 2020/2103 / Filled Medical Emergency COVID-19 IDA / 66270 Post Direct Selection Direct 160.00 0.00 Implementati 2020-10-31 2020-11-05 2020-12-10 2021-06-08 Oxygen Gas cylinders [ Empty Response on Oxygen 'D' type] (QTY: 60 ) MSDD/MED.GAS/2019- 2020/2111 / Filled Medical Oxygen Gas cylinders (QTY: Pending Emergency COVID-19 136 nos) IDA / 66270 Post Direct Selection Direct 300.00 0.00 Implementati 2020-10-31 2020-11-05 2020-12-10 2021-06-08 Response [ Empty Oxygen 'B' type- 72 on nos & Empty Oxygen 'D' type- 64 nos ] MOH/DMSHI/MSPD/COVID- 19/2020/2170 / Supply of Emergency COVID-19 Request for Single Stage - One IDA / 66270 Post Open - National 1,000.00 0.00 Canceled 2020-11-05 2020-12-31 2021-06-29 Equipment- Trolley (QTY) : 3 Response Quotations Envelope sets MOH/DMSHI/MSPD/COVID- 19/2020/2055 / Supply of Emergency COVID-19 Request for Single Stage - One IDA / 66270 Post Open - National 1,000.00 0.00 Canceled 2020-11-05 2020-12-31 2021-06-29 Equipment -Semi fowler's bed Response Quotations Envelope (QTY: 8 nos) MOH/DMSHI/MSPD/NCORONA /2020/2086 / Procurement of Equipments: 1. Arterial Blood Gas unit Emergency COVID-19 Request for Single Stage - One IDA / 66270 Post Open - National 64,000.00 0.00 Canceled 2020-11-05 2020-12-31 2021-06-29 (QTY: 6 nos) Response Quotations Envelope 2. Infusion Pump (QTY: 15 nos ) 3. Bed ICU (QTY: 18 nos) MOH/DMSHI/MSPD/NCORON O/2020/2078 / Supply of Emergency COVID-19 Request for Single Stage - One IDA / 66270 Post Open - National 1,400.00 0.00 Canceled 2020-11-05 2020-12-31 2021-06-29 PPEs and GC-Glycerin (QTY: Response Quotations Envelope 1150 nos) BT-MOH-173319-GO-RFQ / Emergency COVID-19 Request for Single Stage - One IDA / 66270 Post Limited 44,836.90 0.00 Canceled 2020-05-22 2020-06-09 2020-08-08 Supply of PPEs for COVID-19 Response Quotations Envelope Page 3 MOH/DMSHI/MSPD/NCORONA /2020/2076 / Supply of Emergency COVID-19 Request for Single Stage - One IDA / 66270 Post Open - National 61,500.00 0.00 Canceled 2020-11-05 2020-12-31 2021-06-29 Equipment-Infrared Response Quotations Envelope Thermometer (QTY: 95) MOH/DMSHI/MSPD/COVID- 19/2020/2174 / Supply of Emergency COVID-19 Request for Single Stage - One IDA / 66270 Post Open - National 1,200.00 0.00 Canceled 2020-11-05 2020-12-31 2021-06-29 Equipment & Consumable: Response Quotations Envelope -Electrocardiograph (QTY: 1) MOH/DMSHI/MSPD/NCORONA /2020/2059 / Supply of Emergency COVID-19 Request for Single Stage - One IDA / 66270 Post Open - National 4,800.00 0.00 Canceled 2020-11-05 2020-12-31 2021-06-29 Equipment: Response Quotations Envelope -Infusion Pump (QTY: 13 sets) MOH/DMSHI/MSPD/COVID- 19/2020/2190 / Supply of Emergency COVID-19 Request for Single Stage - One Equipment: IDA / 66270 Post Open - National 11,500.00 0.00 Canceled 2020-11-05 2020-12-31 2021-06-29 Response Quotations Envelope -Cartridge (test card) (QTY: 30) MOH/DMSHI/MSPD/COVID- 19/2020/2077 / Procurement Emergency COVID-19 Request for Single Stage - One of PPEs and GC: IDA / 66270 Post Open - National 1,600.00 0.00 Canceled 2020-11-05 2020-12-31 2021-06-29 Response Quotations Envelope - Glutaraldehyde, 5 ltr (QTY: 305 nos.) MOH/DMSHI/MSPD/COVID- 19/2020/2140 / Supply of PPEs Emergency COVID-19 Request for Single Stage - One -Clean gloves /non sterile IDA / 66270 Post Open - National 49,500.00 0.00 Canceled 2020-11-05 2020-12-31 2021-06-29 Response Quotations Envelope medium (QTY: 216,000) -Clean gloves/ non sterile large (QTY: 90,000) MOH/DMSHI/MSPD/NCORON O/2020/2895 / Supply of Equipment & GC: Emergency COVID-19 Request for Single Stage - One IDA / 66270 Post Open - National 4,000.00 0.00 Canceled 2020-11-05 2020-12-31 2021-06-29 - Mattress Foam with Response Quotations Envelope waterproof synthetic cover, Size 78*37*4" (QTY: 94 ) MOH/DMSHI/MSPD/COVID- 19/2020/2453 / Supply of PPEs & Consumables Emergency COVID-19 Request for Single Stage - One -Coverall size L, white Tyvek IDA / 66270 Post Open - National 660,000.00 0.00 Canceled 2020-11-05 2020-12-31 2021-06-29 Response Quotations Envelope (QTY: 3600) -Coverall size M, White Tyvek (QTY: 3600) MOH/DMSHI/MSPD/COVID- 19/2020/2216 / Supply of Equipment -Infrared Emergency COVID-19 Request for Single Stage - One IDA / 66270 Post Open - National 54,000.00 0.00 Canceled 2020-11-05 2020-12-31 2021-06-29 Thermometer, Digital, Response Quotations Envelope Forehead (sensor) Battery (QTY: 400) 13(02)DMS/HCDD/MSQU/201 9-2020/2910 / Procurement Under of reagents and consumables Emergency COVID-19 IDA / 66270 Post Direct Selection Direct 94,200.00 0.00 Implementati 2021-01-14 2020-11-21 2021-01-19 2020-12-01 2021-02-23 2021-08-22 for Biochemistry and Response on Haematology analyzers. (QTY: 1416 nos.) MOH-PPD/WB- PROCUREMENT/2020/03 / Emergency COVID-19 Request for Single Stage - One IDA / 66270 Post Limited 25,000.00 0.00 Canceled 2021-03-05 2021-04-30 2021-10-27 Ultra Refrigerator -70, 900 Response Quotations Envelope litres (QTY:2) MOH-PPD/WB- PROCUREMENT/2020/04 / Emergency COVID-19 Request for Single Stage - One Auto- Disable Syringes, 0.3 IDA / 66270 Post Limited 1,000.00 0.00 Canceled 2021-03-05 2021-04-30 2021-10-27 Response Quotations Envelope ML or 1 ML Needle with 23 Gauge (QTY:22000) MOH-PPD/WB- PROCUREMENT/2020/05 / AD Emergency COVID-19 Request for Single Stage - One IDA / 66270 Post Limited 1,000.00 0.00 Canceled 2021-03-05 2021-04-30 2021-10-27 syringes, 2 Ml with 21 gauge Response Quotations Envelope needle (QTY: 22,000) MOH-PPD/WB- PROCUREMENT/2020/06 / Emergency COVID-19 Request for Single Stage - One Diluent, 0.9% sodium chloride IDA / 66270 Post Limited 25,000.00 0.00 Canceled 2021-03-05 2021-04-30 2021-10-27 Response Quotations Envelope solution for injection 2ml USP( QTY: 22,000) MOH-PPD/WB- PROCUREMENT/2020/07 / Emergency COVID-19 Request for Single Stage - One IDA / 66270 Post Limited 500.00 0.00 Canceled 2021-03-05 2021-04-30 2021-10-27 Adrenaline 1mg/m Response Quotations Envelope Injection(1ml) (QTY:4000) MOH-PPD/WB- PROCUREMENT/2020/08 / Emergency COVID-19 Request for Single Stage - One IDA / 66270 Post Limited 1,800.00 0.00 Canceled 2021-03-05 2021-04-30 2021-10-27 Hydrocortisone 100mg/ml Response Quotations Envelope Injection(2ml) (QTY:4000) MOH-PPD/WB- PROCUREMENT/2020/09 / Emergency COVID-19 Request for Single Stage - One IDA / 66270 Post Limited 500.00 0.00 Canceled 2021-03-05 2021-04-30 2021-10-27 Promethazine 25mg/ml Response Quotations Envelope Injection(2ml) (QTY:4000) MOH-PPD/WB- PROCUREMENT/2020/10 / Emergency COVID-19 Request for Single Stage - One "0.5 ML AD syringes (with IDA / 66270 Post Limited 50,000.00 0.00 Canceled 2021-03-05 2021-04-30 2021-10-27 Response Quotations Envelope 23x1” Gauze needle size) (0.6x25mm)" (QTY:919,800) MOH-PPD/WB- PROCUREMENT/2020/11 / Emergency COVID-19 Request for Single Stage - One Biohazard Safety Box 5 litres, IDA / 66270 Post Limited 6,000.00 0.00 Canceled 2021-03-05 2021-04-30 2021-10-27 Response Quotations Envelope WHO/PSO/E-10/SB01.1 Code PQS E10/04 9QTY: 9,200) Page 4 RBC/HEALTH/09/2020- 21/642 / procurement of: Under 1. Hydrocortisone 100mg/ml Emergency COVID-19 IDA / 66270 Post Direct Selection Direct 1,500.00 0.00 Implementati 2021-03-07 2020-11-21 2021-03-12 2020-11-25 2021-04-16 2021-10-13 injection(2ml)- (QTY:4000) Response on 2. Promethazine 25mg/ml Injection ( 2ml)- (QTY-4000) MOH/DMSHI/MSPD/VPDP PROGRAM/2021/1342 / Pending Procurement of consumables- Emergency COVID-19 IDA / 66270 Post Direct Selection Direct 5,000.00 0.00 Implementati 2021-03-07 2021-03-12 2021-04-16 2021-10-13 Auto Disable syringes, 0.3 ML Response on or 1 ML Needle with 23 gauge (QTY:110,000). MOH/DMSHI/MSPD/VPDP PROGRAM/2021/1316 / Emergency COVID-19 Procurement of Equipment; IDA / 66270 Post Direct Selection Direct 23,000.00 23,477.43 Completed 2021-02-26 2020-11-21 2021-03-03 2021-01-22 2021-03-16 2021-02-15 2021-03-30 2021-06-22 Response Ultra Refrigerator, -70 degree Celcius, 900 liters (QTY-2) RBC/HEALTH/09/2020- Pending 21/641 / Procurement of Emergency COVID-19 Request for Single Stage - One IDA / 66270 Post Limited 400.00 0.00 Implementati 2021-03-05 2021-04-12 2021-05-18 Adrenaline 1mg/ml Response Quotations Envelope on Injection(1ml) (QTY:4000) MOH/DMSHI/MSPD/VPDP PROGRAM/2021/1317 / Pending Procurement of Biohazard Emergency COVID-19 Request for Single Stage - One IDA / 66270 Post Limited 6,000.00 0.00 Implementati 2021-03-05 2021-04-23 2021-05-26 Safety Box 5 litres, Response Quotations Envelope on WHO/PSO/E-10/SB01.1 Code PQS E10/04 (QTY:9200) BT-MOH-225373-GO-DIR / Procurement of 0.5ml AD Emergency COVID-19 IDA / 66270 Post Direct Selection Direct 15,000.00 0.00 Canceled 2021-03-22 2021-03-23 2021-04-28 2021-10-25 Syringes (23GX1") Response QTY:363,600 R1- MOH/DMSHI/MSPD/COVID- Emergency COVID-19 Request for Single Stage - One 19/2020/2055 / Supply of IDA / 66270 Post Limited 1,000.00 992.03 Completed 2021-04-16 2020-03-09 2021-06-11 2020-03-19 2021-12-08 2020-06-22 Response Quotations Envelope Equipment -Semi fowler's bed (QTY: 8 nos) R2- MOH/DMSHI/MSPD/COVID- 19/2020/2077 / Procurement Emergency COVID-19 Request for Single Stage - One of PPEs and General IDA / 66270 Post Limited 1,600.00 1,622.19 Completed 2021-04-16 2020-03-09 2021-06-11 2020-03-13 2021-12-08 2020-06-10 Response Quotations Envelope Consumable: - Glutaraldehyde, 5 ltr (QTY: 305 nos.) R3- MOH/DMSHI/MSPD/NCORONA Emergency COVID-19 Request for Single Stage - One /2020/2059 / Supply of IDA / 66270 Post Limited 4,800.00 4,760.74 Completed 2021-04-16 2020-03-09 2021-06-11 2020-03-19 2021-12-08 2020-06-10 Response Quotations Envelope Equipment: -Infusion Pump (QTY: 13 sets) R4- MOH/DMSHI/MSPD/COVID- 19/2020/2140 / Supply of PPEs Emergency COVID-19 Request for Single Stage - One IDA / 66270 Post Limited 49,500.00 20,713.32 Completed 2021-04-16 2020-03-09 2021-06-11 2020-03-18 2021-12-08 2020-06-22 -Clean gloves /non sterile Response Quotations Envelope medium (QTY: 216,000) -Clean gloves/ non sterile large (QTY: 90,000) R5- MOH/DMSHI/MSPD/NCORON O/2020/2895 / Supply of Emergency COVID-19 Request for Single Stage - One Equipment & GC: - Mattress IDA / 66270 Post Limited 4,000.00 3,596.16 Completed 2021-04-16 2020-03-09 2021-06-11 2020-03-14 2021-12-08 2020-06-10 Response Quotations Envelope Foam with waterproof synthetic cover, Size 78*37*4" (QTY: 94 ) R6- MOH/DMSHI/MSPD/COVID- 19/2020/2216 / Supply of Emergency COVID-19 Request for Single Stage - One Equipment -Infrared IDA / 66270 Post Limited 54,000.00 21,825.12 Completed 2021-04-16 2020-03-09 2021-06-11 2020-03-25 2021-12-08 2020-06-10 Response Quotations Envelope Thermometer, Digital, Forehead (sensor) Battery (QTY: 400) R7- MOH/DMSHI/MSPD/NCORONA Emergency COVID-19 Request for Single Stage - One /2020/2076 / Supply of IDA / 66270 Post Limited 61,500.00 2,958.08 Completed 2021-04-16 2020-03-09 2021-06-11 2020-03-13 2021-12-08 2020-06-22 Response Quotations Envelope Equipment-Infrared Thermometer (QTY: 95) R8- MOH/DMSHI/MSPD/COVID- Emergency COVID-19 Request for Single Stage - One 19/2020/2190 / Supply of IDA / 66270 Post Limited 11,500.00 0.00 Canceled 2021-04-16 2021-06-11 2021-12-08 Response Quotations Envelope Equipment: -Cartridge (test card) (QTY: 30) R9- MOH/DMSHI/MSPD/COVID- Emergency COVID-19 Request for Single Stage - One 19/2020/2174 / Supply of IDA / 66270 Post Limited 1,200.00 1,116.69 Completed 2021-04-16 2020-03-09 2021-06-11 2020-03-20 2021-12-08 2020-06-24 Response Quotations Envelope Equipment & Consumable: - Electrocardiograph (QTY: 1) R10- MOH/DMSHI/MSPD/COVID- 19/2020/2453 / Supply of PPEs & Consumables: Emergency COVID-19 Request for Single Stage - One IDA / 66270 Post Limited 660,000.00 120,964.78 Completed 2021-04-16 2020-03-09 2021-06-11 2020-04-20 2021-12-08 2020-06-10 -Coverall size L, white Tyvek Response Quotations Envelope (QTY: 3600) -Coverall size M, White Tyvek (QTY: 3600) R11- MOH/DMSHI/MSPD/COVID- 19/2020/2446 / Supply of Emergency COVID-19 Request for Single Stage - One IDA / 66270 Post Limited 1,500.00 1,504.66 Completed 2021-04-16 2020-03-09 2021-06-11 2020-04-20 2021-12-08 2020-06-26 PPEs -surgical cap, non Response Quotations Envelope woven, disposable (QTY:126,900) Page 5 R12- MOH/DMSHI/MSPD/NCORONA /2020/2086 / Procurement of Equipment: Emergency COVID-19 Request for Single Stage - One 1. Arterial Blood Gas unit IDA / 66270 Post Limited 64,000.00 64,064.63 Completed 2021-04-16 2020-03-09 2021-06-11 2020-03-14 2021-12-08 2020-06-10 Response Quotations Envelope (QTY: 6 nos) 2. Infusion Pump (QTY: 15 nos ) 3. Bed ICU (QTY: 18 nos) R13- MOH/DMSHI/MSPD/NCORON Emergency COVID-19 Request for Single Stage - One O/2020/2078 / Supply of IDA / 66270 Post Limited 1,400.00 1,409.49 Completed 2021-04-16 2020-03-09 2021-06-11 2020-03-13 2021-12-08 2020-06-10 Response Quotations Envelope PPEs and GC-Glycerin (QTY: 1150 nos) R14- MOH/DMSHI/MSPD/NCORONA Emergency COVID-19 Request for Single Stage - One /2020/2097 / Procurement of IDA / 66270 Post Limited 145,000.00 143,973.11 Completed 2021-04-16 2020-03-09 2021-06-11 2020-03-16 2021-12-08 2020-06-10 Response Quotations Envelope PPEs: Surgical Face Mask (QTY: 598,700) R15- MOH/DMSHI/MSPD/COVID- 19/2020/2144 / Supply of PPEs & consumables: Emergency COVID-19 Request for Single Stage - One IDA / 66270 Post Limited 150,000.00 70,727.29 Completed 2021-04-16 2020-03-09 2021-06-11 2020-03-18 2021-12-08 2020-06-10 -Coverall size S, White tyvek Response Quotations Envelope (QTY: 4300) -Coverall size M, White Tyvek (QTY: 4300) R16- MOH/DMSHI/MSPD/COVID- 19/2020/2194 / Supply of GC & Consumables: Emergency COVID-19 Request for Single Stage - One IDA / 66270 Post Limited 23,000.00 22,837.64 Completed 2021-04-16 2020-03-20 2021-06-11 2020-03-23 2021-12-08 2020-06-10 -Oxygen Cylinder D type Response Quotations Envelope (QTY: 100 nos) -Oxygen Stand B type (QTY: 10 nos) R17- MOH/DMSHI/MSPD/COVID- Pending Emergency COVID-19 19/2020/2170 / Supply of IDA / 66270 Post Direct Selection Direct 1,000.00 0.00 Implementati 2021-04-11 2021-04-16 2021-05-21 2021-11-17 Response Equipment- Trolley (QTY) : 3 on sets R18- MOH/DMSHI/MSPD/COVID- 19/2020/2092 / Supply of Emergency COVID-19 Request for Single Stage - One IDA / 66270 Post Open - National 26,000.00 26,456.83 Completed 2021-04-16 2021-06-11 2020-03-14 2021-12-08 2020-06-22 Equipment - Response Quotations Envelope Defibrillator(Pediatric paddle) (QTY: 4) R19- MOH/DMSHI/MSPD/COVID- Emergency COVID-19 Request for Single Stage - One 19/2020/2191 / Supply of IDA / 66270 Post Limited 24,000.00 0.00 Canceled 2021-04-16 2021-06-11 2021-12-08 Response Quotations Envelope Equipment-Reverse Osmosis system (QTY: 1) R20- MOH/DMSHI/MSPD/COVID- 19/2020/2143 / Supply of Emergency COVID-19 Request for Single Stage - One IDA / 66270 Post Limited 200.00 162.06 Completed 2021-04-16 2020-03-09 2021-06-11 2020-03-18 2021-12-08 2020-06-22 PPEs -Operation cap, size Response Quotations Envelope medium (50cm) (QTY: 14,000 nos) R21- MOH/DMSHI/MSPD/COVID- Pending 19/2020/2458 / Supply of Emergency COVID-19 IDA / 66270 Post Direct Selection Direct 30.00 0.00 Implementati 2021-04-11 2021-04-16 2021-05-21 2021-11-17 Consumables -Breathing Response on circuit, Anesthesia, adult 22 mm (QTY: 5 sets) R22- MOH/DMSHI/MSPD/COVID- Emergency COVID-19 Request for Single Stage - One 19/2020/2433 / supply of IDA / 66270 Post Limited 93,000.00 93,448.43 Completed 2021-04-16 2020-03-09 2021-06-11 2020-04-21 2021-12-08 2020-06-10 Response Quotations Envelope PPEs & consumables -Surgical Face Mask (QTY: 300,000 nos) R23- MOH/DMSHI/MSPD/COVID- 19/2020/2500 / Supply of Emergency COVID-19 Request for Single Stage - One IDA / 66270 Post Limited 6,000.00 5,940.76 Completed 2021-04-16 2020-03-09 2021-06-11 2020-04-25 2021-12-08 2020-06-22 consumables -Disposable Response Quotations Envelope gloves , Size M & L (QTY: 100,000) R24- MOH/DMSHI/MSPD/COVID- 19/2020/2057 / Procurement Emergency COVID-19 Request for Single Stage - One IDA / 66270 Post Limited 100,600.00 100,732.82 Completed 2021-04-16 2020-03-09 2021-06-11 2020-03-19 2021-12-08 2020-06-11 of equipment & consumables- Response Quotations Envelope Portable Ventilators, Astral 150 (QTY: 13) R25- MOH/DMSHI/MSPD/COVID- Emergency COVID-19 Request for Single Stage - One 19/2020/2418 / Supply of IDA / 66270 Post Limited 5,000.00 4,903.40 Completed 2021-04-16 2020-03-09 2021-06-11 2020-04-17 2021-12-08 2020-06-24 Response Quotations Envelope Equipment-Foam mattress (QTY: 128) DMSHI/MSPD/VACCINATION/ 2020-21 / Procurement of Emergency COVID-19 Request for Single Stage - One IDA / 66270 Post Limited 20,000.00 0.00 Canceled 2021-04-06 2021-06-01 2021-11-28 0.5ml AD Syringes (23GX1") Response Quotations Envelope QTY:363,600 R1- DMSHI/MSPD/VACCINATION/ Emergency COVID-19 2020-21 / Procurement of IDA / 66270 Post Direct Selection Direct 20,000.00 17,956.05 Completed 2021-04-25 2021-03-19 2021-04-30 2021-04-06 2021-06-04 2021-04-20 2021-12-01 2021-06-22 Response 0.5ml AD Syringes (23GX1") QTY:363,600 R-MOH/DMSHI/MSPD/COVID- Pending 19/2020/2190 / Supply of Emergency COVID-19 IDA / 66270 Post Direct Selection Direct 11,500.00 0.00 Implementati 2021-05-27 2021-06-01 2021-07-06 2022-01-02 Equipment: -Cartridge (test Response on card) (QTY: 30) Page 6 R-MOH/DMSHI/MSPD/COVID- Pending 19/2020/2191 / Supply of Emergency COVID-19 IDA / 66270 Post Direct Selection Direct 24,000.00 0.00 Implementati 2021-05-27 2021-06-01 2021-07-06 2022-01-02 Equipment-Reverse Osmosis Response on system (QTY: 1) NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual VPDP(12)DOPH/2020/ / Under Transportation of vaccine to Emergency COVID-19 IDA / 66270 Post Direct Selection Direct 20,000.00 0.00 Implementati 2021-03-24 2021-03-18 2021-03-24 2021-03-24 2021-04-13 2021-05-15 different districts in Bhutan Response on (using helicopter services) CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PPD/WB(COVID- 10)PROC/2020 / Hiring of Procurement Individual Emergency COVID-19 Officer/Consultant for COVID- IDA / 66270 Post Consultant Limited 46,500.00 13,229.72 Signed 2020-05-19 2020-05-23 2020-05-24 2020-05-27 2020-06-14 2020-06-15 2020-07-19 2020-06-15 2021-01-15 Response 19 Emergency Response and Selection Health Systems Preparedness Project. PPD/WB(COVID-19)M&E2020 / Hiring of M&E Individual Officer/Consultant for COVID- Emergency COVID-19 IDA / 66270 Post Consultant Limited 55,800.00 13,358.71 Signed 2020-05-19 2020-05-23 2020-05-24 2020-05-27 2020-06-14 2020-06-15 2020-07-19 2020-06-15 2021-01-15 19 Emergency Response and Response Selection Health Systems Preparedness Project PPD/WB(COVID- 19)CIVIL/2020 / Hiring of Individual Civil Engineer/Consultant for Emergency COVID-19 IDA / 66270 Post Consultant Limited 49,600.00 13,228.11 Signed 2020-05-19 2020-05-23 2020-05-24 2020-05-27 2020-06-14 2020-06-18 2020-07-19 2020-06-18 2021-01-15 COVID-19 Emergency Response Selection Response and Health Systems Preparedness Project. Page 7 PROCUREMENT PLAN Textual Part Project information: North Macedonia, Primary Education Improvement Project (P171973) Project Implementation agency: Ministry of Education and Science Date of the Procurement Plan: February 2021 Period covered by this Procurement Plan: First 18 months of project implementation In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: for all procurement activities - both with international and national approach. Respectively, the complaints arising in connection with contracts for which the Bank’s SPDs are used shall be administered and handled in accordance with Annex III of the Regulations. For international procedures the procurement notices will be published automatically through STEP on the Bank’s external website and UNDB, as well as locally on the Ministry’s website, daily newspaper as relevant, and on the portal of Public Procurement Bureau at: (https://e-nabavki.gov.mk/PublicAccess/home.aspx#/notices) 1 Thresholds for Procurement Approaches and Methods (€ thousands) Works Goods, IT and non- Shortlist of national consulting services consultants Open Open RfQ Open Open RfQ Consulti Engineerin internati nationa internati nation ng g and onal l onal al services constructio n supervisio ≤ ≤ ≥ < ≥ < ≤ n ≤ 5,000 5,000 200 1 000 1 000 100 300 N/A Review Arrangements First contract for each First contract for each First contract for each approach and method and approach and method approach and method, all all >3 000 and all >3 000 TORs and all contracts > 1 000 Individual consultants all Direct Selection all > 80 000 Direct Selection all > 80 TORs and all contracts > 000 300 Direct Selection all >10 000 2 PROCUREMENT North Macedonia : Primary Education Improvement Project PLAN General Information Country: North Macedonia Bank’s Approval Date of the Original Procurement Plan: 2021-02-12 2021-05-20 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P171973 GPN Date: 2021-01-25 Project Name: Primary Education Improvement Project Loan / Credit No: IBRD / 91820 M Executing Agency(ies): inistry of Education and Science WORKS Procureme Activity Reference No. / Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH nt Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) Justification for Award Type Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MK-MES-217476-GO-RFQ / Reform of the Monitoring and Under Procurement of laptop Request for Single Stage - One IBRD / 91820 Evaluation of the National Post Open - National 0.00 Implementati 2021-02-20 2021-04-14 2021-07-13 computers for National Quotations Envelope Progress in Learning on Examination Center Pending MK-MES-217499-GO-RFQ / Sector management, Project Request for Single Stage - One IBRD / 91820 Post Open - National 0.00 Implementati 2021-05-08 2021-07-03 2021-09-01 Procurement of vehicle management and M&E Quotations Envelope on MK-MES-217526-GO-RFB / Under Improving Learning at the Single Stage - One Procurement of ICT IBRD / 91820 Post Request for Bids Open - International 0.00 Implementati 2021-05-20 2021-05-20 2021-05-25 2021-05-20 2021-07-06 2021-08-05 2021-09-09 2022-03-08 School Level Envelope equipment for primary on schools MK-MES-217529-GO-RFQ / Pending Procurement of air- Improving Learning at the Request for Single Stage - One IBRD / 91820 Post Open - National 0.00 Implementati 2021-12-06 2022-01-31 2022-05-31 conditioning devices for School Level Quotations Envelope on primary schools MK-MES-217538-GO-RFB / Pending Procurement of network Improving Learning at the Single Stage - One IBRD / 91820 Post Request for Bids Open - National 0.00 Implementati 2021-05-05 2021-05-10 2021-06-21 2021-07-21 2021-08-25 2022-02-21 infrastructure for primary School Level Envelope on schools MK-MES-217541-GO-RFB / Pending Improving Learning at the Single Stage - One Procurement of IT equipment IBRD / 91820 Post Request for Bids Open - International 0.00 Implementati 2021-05-19 2021-05-24 2021-07-05 2021-08-04 2021-09-08 2022-03-07 School Level Envelope for special schools on MK-MES-217549-GO-RFB / Improving Learning at the Single Stage - One Procurement of school IBRD / 91820 Post Request for Bids Open - National 0.00 Canceled 2021-06-01 2021-06-06 2021-07-18 2021-08-01 2021-09-05 2022-01-03 School Level Envelope furniture for primary schools MK-MES-217553-GO-RFB / Under Procurement of science Improving Learning at the Single Stage - One IBRD / 91820 Prior Request for Bids Open - International 0.00 Implementati 2021-03-15 2021-06-21 2021-03-20 2021-05-01 2021-05-22 2021-06-26 2021-10-24 laboratories equipment and School Level Envelope on resources for primary schools MK-MES-217817-GO-RFQ / Pending Improving Learning at the Request for Single Stage - One Procurement of Hardware for IBRD / 91820 Post Open - National 0.00 Implementati 2021-06-14 2021-08-09 2021-11-07 School Level Quotations Envelope MOES on MK-MES-217821-GO-RFQ / Reform of the Monitoring and Pending Single Stage - One Procurement of hardware and IBRD / 91820 Evaluation of the National Post Request for Bids Open - National 0.00 Implementati 2021-07-12 2021-07-17 2021-08-28 2021-09-27 2021-11-01 2021-12-31 Envelope equipment for NEC Progress in Learning on MK-MES-217829-GO-RFQ / Pending Sector management, Project Request for Single Stage - One Hardware and office IBRD / 91820 Post Limited 0.00 Implementati 2021-10-12 2021-12-07 2022-02-05 management and M&E Quotations Envelope equipment for PMU on MK-MES-217549-2-GO- Under RFB/018-21 / Procurement of Improving Learning at the Single Stage - One IBRD / 91820 Post Request for Bids Open - National 0.00 Implementati 2021-05-14 2021-05-10 2021-05-19 2021-06-30 2021-06-09 2021-07-30 2021-06-17 2021-09-03 2022-03-02 school furniture for primary School Level Envelope on schools MK-MES-233647-GO- Improving Learning at the Request for Single Stage - One RFQ/019-21 / Procurement of IBRD / 91820 Post Open - National 5,755.96 Signed 2021-05-30 2021-07-21 2021-06-08 2021-08-20 School Level Quotations Envelope office equipment NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MK-MES-217472-CS-CQS / Consultant Functional Analysis of the Improving Learning at the Pending IBRD / 91820 Post Qualification Open - National 0.00 2021-03-24 2021-04-14 2021-05-28 2021-06-27 2021-08-01 2022-01-28 State Administrative School Level Implementation Selection Inspectorate Consultant MK-MES-217500-CS-CQS / Sector management, Project Pending IBRD / 91820 Post Qualification Limited 0.00 2021-09-01 2021-09-15 2021-10-15 2021-11-19 2026-08-31 Project Audit management and M&E Implementation Selection Page 1 MK-MES-217501-CS-QCBS / Technical Assistance for revision of the school Improving Learning at the Quality And Cost- Pending IBRD / 91820 Post Open - International 0.00 2021-05-04 2021-05-25 2021-06-23 2021-07-21 2021-08-10 2021-09-07 2021-10-12 2026-02-27 improvement framework and School Level Based Selection Implementation design and rollout of the school grants program MK-MES-217515-CS-CQS / Consultant Preparation of designs for Improving Learning at the Pending IBRD / 91820 Post Qualification Open - National 0.00 2021-05-20 2021-06-03 2021-07-01 2021-07-22 2021-08-26 2021-11-24 upgrading of the physical School Level Implementation Selection learning environment MK-MES-217814-CS-CQS / Consultant Design, development and Improving Learning at the Pending IBRD / 91820 Post Qualification Open - National 0.00 2021-12-15 2022-01-05 2022-02-18 2022-03-20 2022-04-24 2022-10-21 implementation of School Level Implementation Selection information sharing platform MK-MES-217818-CS-CQS / Outreach activities and Consultant Improving Learning at the Pending logistical support in IBRD / 91820 Post Qualification Open - National 0.00 2021-07-06 2021-07-27 2021-09-09 2021-10-09 2021-11-13 2026-02-27 School Level Implementation organization of project related Selection training and events MK-MES-217819-CS-QCBS / Technical assistance and strengthening of NEC and MOES capacities for Reform of the Monitoring and development and Quality And Cost- Pending IBRD / 91820 Evaluation of the National Post Open - International 0.00 2021-05-18 2021-06-08 2021-07-22 2021-08-19 2021-09-18 2021-10-23 2021-11-27 2026-02-27 implementation of National Based Selection Implementation Progress in Learning Assessment Program and training for data analysis and reporting following international standards MK-MES-217820-CS-CQS / Reform of the Monitoring and Consultant Pending Development of software for IBRD / 91820 Evaluation of the National Post Qualification Open - National 0.00 2021-10-12 2021-11-02 2021-12-16 2022-01-15 2022-02-19 2022-08-18 Implementation national assessment Progress in Learning Selection MK-MES-217825-CS-CQS / Outreach activities including Reform of the Monitoring and Consultant citizen engagement activities Pending IBRD / 91820 Evaluation of the National Post Qualification Open - National 0.00 2022-01-11 2022-02-01 2022-03-17 2022-04-16 2022-05-21 2026-02-27 and logistical support in Implementation Progress in Learning Selection organization of events related to NEC activities MK-MES-217827-CS-CQS / Enhancing Teacher, Multi- Consultant Procurement of software for Professional Support Teams, Pending IBRD / 91820 Post Qualification Open - National 0.00 2021-08-10 2021-08-31 2021-10-14 2021-11-13 2021-12-18 2022-06-16 Bureau for Development of and School Leader Implementation Selection Education Competences MK-MES-217828-CS-CQS / Consultant Feasibility study for Sector management, Project IBRD / 91820 Post Qualification Open - National 0.00 Canceled 2021-06-02 2021-06-23 2021-08-06 2021-09-05 2021-10-10 2022-04-08 optimization of the school management and M&E Selection network MK-MES-217838-CS-CQS / Consultant Sector management, Project Pending Performance Audit of the IBRD / 91820 Post Qualification Open - National 0.00 2022-03-16 2022-04-06 2022-05-20 2022-06-19 2022-07-24 2026-02-27 management and M&E Implementation School Grants Program Selection MK-MES-217841-CS-CQS / Consultant Data collection for following Sector management, Project Pending IBRD / 91820 Post Qualification Open - National 0.00 2021-09-16 2021-10-07 2021-11-20 2021-12-20 2022-01-24 2026-02-27 project indicators and citizen management and M&E Implementation Selection engagement MK-MES-235217-CS- Consultant CQS/023-21 / Design and Improving Learning at the Under IBRD / 91820 Post Qualification Open - National 0.00 2021-05-25 2021-05-26 2021-06-09 2021-06-24 2021-07-04 2021-07-14 2021-08-26 Development of Digital School Level Implementation Selection Educational Materials MK-MES-235695-CS- Consultant CQS/024-21 / Design and Improving Learning at the Under IBRD / 91820 Post Qualification Open - National 0.00 2021-05-25 2021-05-26 2021-06-08 2021-06-22 2021-06-27 2021-07-07 2022-02-28 development of mobile School Level Implementation Selection applications MK-MES-235696-CS- CQS/025-21 / Development Consultant Improving Learning at the Under of Interactive Materials for IBRD / 91820 Post Qualification Open - National 0.00 2021-05-25 2021-05-26 2021-06-08 2021-06-22 2021-06-27 2021-07-07 2021-08-31 School Level Implementation Mathematics and Natural Selection sciences INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Contract Type Process Status Teams of Reference Identified/Selected Signed Contract Contract Completion No. (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Individual MK-MES-217477-CS-INDV / Improving Learning at the IBRD / 91820 Prior Consultant Direct 0.00 Canceled 2021-03-01 2021-03-12 2021-03-11 2021-04-07 2021-03-16 2021-04-20 2026-01-28 Primary Education Coordinator School Level Selection Individual MK-MES-217479-CS-INDV / Improving Learning at the IBRD / 91820 Post Consultant Direct 131,584.02 Signed 2021-03-01 2021-03-15 2021-03-11 2021-04-07 2021-03-16 2021-04-26 2021-04-20 2021-04-28 2026-02-27 Grants Coordinator School Level Selection MK-MES-217480-CS-INDV / Individual Improving Learning at the School Infrastructure IBRD / 91820 Post Consultant Direct 131,584.02 Signed 2021-03-01 2021-03-12 2021-03-11 2021-04-07 2021-03-16 2021-04-26 2021-04-20 2021-04-28 2026-02-27 School Level Specialist Selection Individual MK-MES-217482-CS-INDV / Improving Learning at the IBRD / 91820 Post Consultant Direct 103,587.42 Signed 2021-03-01 2021-03-16 2021-03-11 2021-04-07 2021-03-16 2021-04-26 2021-04-20 2021-04-28 2026-02-27 Architect (1) School Level Selection Individual MK-MES-217483-CS-INDV / Improving Learning at the IBRD / 91820 Post Consultant Direct 103,587.42 Signed 2021-03-01 2021-03-16 2021-03-11 2021-04-07 2021-03-16 2021-04-26 2021-04-20 2021-04-28 2026-02-27 Architect (2) School Level Selection MK-MES-217484-CS-INDV / Reform of the Monitoring and Individual Administrative Assistant for IBRD / 91820 Evaluation of the National Post Consultant Direct 65,092.10 Signed 2021-03-01 2021-03-15 2021-03-11 2021-04-07 2021-03-16 2021-04-26 2021-04-20 2021-04-28 2026-02-27 National Examination Center Progress in Learning Selection Page 2 MK-MES-217486-CS-INDV / Reform of the Monitoring and Individual Coordinator for National IBRD / 91820 Evaluation of the National Post Consultant Direct 131,584.02 Signed 2021-03-01 2021-03-15 2021-03-11 2021-04-07 2021-03-16 2021-04-26 2021-04-20 2021-04-28 2026-02-27 Assessment Progress in Learning Selection Enhancing Teacher, Multi- MK-MES-217487-CS-INDV / Individual Professional Support Teams, Coordinator for Professional IBRD / 91820 Prior Consultant Direct 0.00 Canceled 2021-03-01 2021-03-15 2021-03-11 2021-04-07 2021-03-16 2021-04-20 2026-02-27 and School Leader Development Selection Competences Enhancing Teacher, Multi- Individual MK-MES-217488-CS-INDV / Professional Support Teams, IBRD / 91820 Post Consultant Direct 65,092.10 Signed 2021-03-01 2021-03-16 2021-03-11 2021-04-07 2021-03-16 2021-04-26 2021-04-20 2021-04-28 2026-02-27 Career Development Specialist and School Leader Selection Competences Individual MK-MES-217489-CS-INDV / Sector management, Project IBRD / 91820 Post Consultant Direct 156,780.96 Signed 2021-03-01 2021-03-11 2021-03-11 2021-04-07 2021-03-16 2021-04-26 2021-04-20 2021-04-28 2026-02-27 Project Director management and M&E Selection Individual MK-MES-217490-CS-INDV / Sector management, Project IBRD / 91820 Post Consultant Direct 131,584.02 Signed 2021-03-01 2021-03-11 2021-03-11 2021-04-07 2021-03-16 2021-04-26 2021-04-20 2021-04-28 2026-02-27 Procurement Specialist management and M&E Selection MK-MES-217491-CS-INDV / Individual Sector management, Project Financial Management IBRD / 91820 Post Consultant Direct 131,584.02 Signed 2021-03-01 2021-03-11 2021-03-11 2021-04-07 2021-03-16 2021-04-26 2021-04-20 2021-04-28 2026-02-27 management and M&E Specialist Selection MK-MES-217492-CS-INDV / Individual Sector management, Project Information Technology IBRD / 91820 Post Consultant Direct 131,584.02 Signed 2021-03-01 2021-03-12 2021-03-11 2021-04-07 2021-03-16 2021-04-26 2021-04-20 2021-04-28 2026-02-27 management and M&E Specialist Selection Individual MK-MES-217493-CS-INDV / Sector management, Project IBRD / 91820 Post Consultant Direct 158,880.71 Signed 2021-03-01 2021-03-12 2021-03-11 2021-04-07 2021-03-16 2021-04-26 2021-04-20 2021-04-28 2026-02-27 IT Consultant management and M&E Selection MK-MES-217494-CS-INDV / Individual Sector management, Project Monitoring and Evaluation IBRD / 91820 Post Consultant Direct 131,584.02 Signed 2021-03-01 2021-03-12 2021-03-11 2021-04-07 2021-03-16 2021-04-26 2021-04-20 2021-04-28 2026-02-27 management and M&E Specialist Selection Individual MK-MES-217496-CS-INDV / Sector management, Project IBRD / 91820 Prior Consultant Direct 0.00 Canceled 2021-03-01 2021-03-12 2021-03-11 2021-04-07 2021-03-16 2021-04-20 2026-02-27 Social Specialist management and M&E Selection MK-MES-217497-CS-INDV / Individual Sector management, Project Citizen Engagement IBRD / 91820 Prior Consultant Direct 0.00 Canceled 2021-03-01 2021-03-12 2021-03-11 2021-04-07 2021-03-16 2021-04-20 2026-02-27 management and M&E Consultant Selection MK-MES-217498-CS-CDS / Sector management, Project Pending Financial Management IBRD / 91820 Post Direct Selection Direct 0.00 2021-03-01 2021-03-11 2021-04-20 2026-02-27 management and M&E Implementation Software Maintenance Individual MK-MES-217518-CS-INDV / Improving Learning at the Pending IBRD / 91820 Post Consultant Open 0.00 2021-04-01 2021-05-04 2021-05-18 2021-06-22 2026-02-27 Environmental Consultant School Level Implementation Selection MK-MES-217812-CS-INDV / Consultant for designing Individual Improving Learning at the Pending mechanisms for promoting IBRD / 91820 Post Consultant Open 0.00 2021-09-01 2021-10-20 2021-11-10 2021-12-15 2022-03-15 School Level Implementation accountability through Selection information sharing MK-MES-217824-CS-INDV / Reform of the Monitoring and Individual Local consultant for Under IBRD / 91820 Evaluation of the National Post Consultant Open 0.00 2021-12-06 2022-01-24 2022-02-14 2022-03-21 2022-09-17 strengthening NEC capacity in Implementation Progress in Learning Selection application of IRT MK-MES-217837-CS-INDV / Individual Sector management, Project Consultant for processing and IBRD / 91820 Post Consultant Direct 156,081.05 Signed 2021-03-01 2021-03-12 2021-03-11 2021-04-07 2021-03-16 2021-04-26 2021-04-20 2021-04-28 2026-02-27 management and M&E analyzing data Selection MK-MES-217840-CS-INDV / Individual Sector management, Project Pending Impact Evaluation of the IBRD / 91820 Post Consultant Open 0.00 2022-03-15 2022-05-03 2022-05-24 2022-06-28 2026-02-27 management and M&E Implementation Schools Grants Program Selection Individual MK-MES-218027-CS-INDV / Improving Learning at the Pending IBRD / 91820 Post Consultant Open 0.00 2022-03-09 2022-04-27 2022-05-18 2022-06-22 2026-02-27 Grants Financial Officer School Level Implementation Selection MK-MES-218036-CS-INDV / Reform of the Monitoring and Individual Pending Psychometric analysis IBRD / 91820 Evaluation of the National Post Consultant Open 0.00 2021-12-14 2022-02-01 2022-02-22 2022-03-29 2026-02-27 Implementation specialist Progress in Learning Selection MK-MES-217477-2-CS-INDV Individual Improving Learning at the / Primary Education IBRD / 91820 Post Consultant Direct 141,965.01 Signed 2021-04-14 2021-04-19 2021-04-19 2021-04-21 2021-04-22 2021-04-23 2021-04-30 2021-04-28 2026-02-27 School Level Coordinator Selection Enhancing Teacher, Multi- MK-MES-217487-2-CS-INDV Individual Professional Support Teams, / Coordinator for Professional IBRD / 91820 Post Consultant Direct 141,965.01 Signed 2021-04-14 2021-04-19 2021-04-19 2021-04-21 2021-04-22 2021-04-23 2021-04-30 2021-04-28 2026-02-27 and School Leader Development Selection Competences MK-MES-217497-2-CS-INDV Individual Sector management, Project / Citizen Engagement IBRD / 91820 Post Consultant Direct 65,038.16 Signed 2021-04-14 2021-04-19 2021-04-19 2021-04-21 2021-04-22 2021-04-23 2021-04-30 2021-04-28 2026-02-27 management and M&E Consultant Selection Individual MK-MES-217496-2-CS-INDV Sector management, Project Pending IBRD / 91820 Post Consultant Open 0.00 2021-05-10 2021-06-28 2021-07-19 2021-08-23 2026-02-27 / Social Specialist management and M&E Implementation Selection MK-MES-235211-CS- CDS/022-21 / Improving cost Sector management, Project Under IBRD / 91820 Post Direct Selection Direct 0.00 2021-05-20 2021-05-20 2021-05-26 2021-06-15 2022-01-31 efficiency in primary and management and M&E Implementation secondary education Page 3 MK-MES-237011-CS- INDV/027-21 / Consultant for Enhancing Teacher, Multi- improvement of the design of Individual Professional Support Teams, Under the INSET provision and IBRD / 91820 Post Consultant Open 0.00 2021-06-15 2021-06-03 2021-07-11 2021-07-21 2021-07-31 2021-12-28 and School Leader Implementation implementation of Selection Competences professional development program for teachers MK-MES-237016-CS- Individual Improving Learning at the Under INDV/028-21 / Digital IBRD / 91820 Post Consultant Open 0.00 2021-05-31 2021-06-03 2021-06-24 2021-06-29 2021-07-05 2022-01-01 School Level Implementation Learning Coordinator Selection MK-MES-237017-CS- Enhancing Teacher, Multi- INDV/029-21 / Individual Professional Support Teams, Under Administrative Officer for IBRD / 91820 Post Consultant Open 0.00 2021-05-31 2021-06-03 2021-06-29 2021-07-04 2021-07-14 2026-02-27 and School Leader Implementation teacher pre- service training Selection Competences for the needs of the BDE MK-MES-237021-CS- Reform of the Monitoring and Individual INDV/030-21 / IT Specialist Pending IBRD / 91820 Evaluation of the National Post Consultant Open 0.00 2021-07-01 2021-08-03 2021-08-17 2021-09-14 2026-02-27 for National Examination Implementation Progress in Learning Selection Center Page 4 UNITED REPUBLIC OF TANZANIA Procurement Plan General 1. Project Information Country: Tanzania Project Name: Secondary Education Quality Improvement Program Project ID: P170480 2. Project Implementation Agency: President’s Office, Regional Administration and Local Government 3. Date of the Procurement Plan: December 5, 2019 4. Period Covered by this procurement plan: January 2020 to June 2021 I. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016, Revised November 2017 and August 2018) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. II. Bank’s Standard Procurement Documents: The Bank’s Standard Procurement Documents shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. III. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. 1 When the Borrower uses its own national open competitive procurement arrangements as set forth in The Public Procurement Act, 2011, The Public Procurement (Amendment) Act, 2016, the Public Procurement Regulations, 2013 and the Public Procurement (Amendment) Regulations, 2016, such arrangements shall be subject to paragraph 5.3 and 5.4 of the Procurement Regulations and the following conditions: o Procurement Documents include provisions, as agreed with the Bank, intended to adequately mitigate against environmental, social (including sexual exploitation and abuse and gender-based violence), health and safety (“ESHS”) risks and impacts o There should be no mandatory requirements for inclusion of local experts and firms for the consulting assignments; o There should be no exclusive preference based on threshold prescribed in PPA and its Regulations; o Negotiations with the lowest evaluated bidder to reduce price in the case of goods, works and non-consulting services where competitive methods have been used shall not be allowed; o The fixed budget method shall not be used for goods, works and non- consulting services; o Established and approved procurement standards by the government may be used, provided that they are not restrictive When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. In accordance with paragraph 5.4(c) and 5.5 of the Procurement Regulations, the request for bids/request for proposals/request for quotations document shall require that Bidders/Proposers submitting Bids/Proposals/quotations present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. The form of the Letter of Acceptance is attached in Appendix 1. IV. Prequalification: Not Applicable V. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable VI. Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations: Not Applicable VII. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Not Applicable 2 Domestic preference is not applicable for National Open Competitive Procurement VIII. Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. Not Applicable IX. Other Relevant Procurement Information Not Applicable 3 X. Threshold for Prior Review, Procurement Approaches and Methods – Good, Works and Non-Consulting Services Procurement Approaches and Methods Prior (US$ millions) Review Category Open Open Request for (US$ millions) International National Quotation (RfQ) Works ≥ 10 ≥ 15 < 15 ≤ 0.2 Goods, IT, and non- ≥2 ≥5 <5 ≤ 0.1 consulting services Post Review: All contracts not subject to prior review shall be subject to post review. Summary of the procurement packages for Good, Works and Non-Consulting Services (Planned for the first 18 months after project effectiveness): XI. Thresholds for Prior Review, Selection Approaches and Methods – Consulting Services Category Prior Short List of National Consultants Review Consulting Engineering and Construction (US$ Services Supervision millions) Consultants ≥1 ≤ 0.3 ≤ 0.3 (Firms) Individual ≥ 0.3 n.a. n.a. Consultants Note: Consultancy services estimated to cost equivalent to US $ 300,000 and above per contract shall be advertised in the United Nations Development Business (UNDB) online in addition to advertising in national newspaper(s) of wide circulation and/or regional newspaper. 4 PROCUREMENT Tanzania : Tanzania Secondary Education Quality Improvement Project (SEQUIP) PLAN General Information Country: Tanzania Bank’s Approval Date of the Original Procurement Plan: 2021-05-24 2021-05-24 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P170480 GPN Date: 2021-06-09 Project Name: Tanzania Secondary Education Quality Improvement Project (SEQUIP) Loan / Credit No: IDA / 65340 M Executing Agency(ies): inistry of Education, Science and Technology - TZ WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TZ-MOEST-TZ-235084-GO- RFB / Procurement of Seven Component 4: Project Pending Single Stage - One (7) Motor Vehicles for Project IDA / 65340 Coordination, Monitoring and Post Request for Bids Open - National 800,000.00 0.00 Implementati 2021-07-27 2021-08-01 2021-09-12 2021-10-12 2021-11-16 2022-05-15 Envelope Coordination and Monitoring Evaluation on for MoEST (5) and IAE (2) TZ-MOEST-TZ-235154-GO- Component 4: Project Pending RFB / Procurement of Office Single Stage - One IDA / 65340 Coordination, Monitoring and Post Request for Bids Open - National 420,000.00 0.00 Implementati 2021-08-22 2021-08-27 2021-10-08 2021-11-07 2021-12-12 2022-06-10 equipment and consumables Envelope Evaluation on for Project Management Team TZ-MOEST-TZ-235161-GO- RFB / Procurement of ICT Component 1: Empowering Pending Single Stage - One equipment for information IDA / 65340 Girls Through Secondary Post Request for Bids Open - National 500,000.00 0.00 Implementati 2021-07-31 2021-08-19 2021-09-18 Envelope system to track secondary Education and Life Skills on dropout (for IAE center) TZ-MOEST-TZ-235158-GO- Component 4: Project Pending RFQ / Procurement of Office Request for Single Stage - One IDA / 65340 Coordination, Monitoring and Post Limited 100,000.00 0.00 Implementati 2021-09-04 2021-10-30 2022-04-28 furniture and fittings for Quotations Envelope Evaluation on project management team NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TZ-MOEST-TZ-235087-CS- QCBS / Consultancy services Component 1: Empowering for development of Quality And Cost- Pending IDA / 65340 Girls Through Secondary Post Open - National 400,000.00 0.00 2021-08-31 2021-09-21 2021-11-04 2021-12-02 2022-01-01 2022-02-05 2022-03-12 2023-03-12 guidelines, training modules, Based Selection Implementation Education and Life Skills training of trainers and monitoring tools for Safe School Model TZ-MOEST-TZ-235222-CS- QCBS / Consultancy Services for development of costed Component 1: Empowering Quality And Cost- Pending plan for improving learning IDA / 65340 Girls Through Secondary Post Open - National 450,000.00 0.00 2021-08-31 2021-09-21 2021-11-04 2021-12-02 2022-01-01 2022-02-05 2022-03-12 2023-03-12 Based Selection Implementation outcome for secondary Education and Life Skills school’s student aligned with inclusive education strategy TZ-MOEST-TZ-235224-CS- QCBS / Consultancy Services Component 2: Digitally- Quality And Cost- Pending for development of national IDA / 65340 Enabled Effective Teaching Post Open - National 490,000.00 0.00 2021-10-18 2021-11-08 2021-12-22 2022-01-19 2022-02-18 2022-03-25 2022-04-29 2023-04-29 Based Selection Implementation secondary school teacher and Learning deployment strategy TZ-MOEST-TZ-235229-CS- QCBS / Consultancy services Component 2: Digitally- Quality And Cost- Pending for development of national IDA / 65340 Enabled Effective Teaching Post Open - National 400,000.00 0.00 2021-11-22 2021-12-13 2022-01-26 2022-02-23 2022-03-25 2022-04-29 2022-06-03 2023-06-03 Based Selection Implementation ICT strategy and costed plan and Learning for implementation TZ-MOEST-TZ-235231-CS- QCBS / Consultancy Services Component 3: Reducing for development of guidelines Barriers to Girls' Education Quality And Cost- Pending IDA / 65340 Post Open - National 450,000.00 0.00 2022-02-15 2022-03-08 2022-04-21 2022-05-19 2022-06-18 2022-07-23 2022-08-27 2023-08-27 and tools for carrying out through Facilitating Access to Based Selection Implementation learning Evaluation for Secondary Schools Secondary Schools TZ-MOEST-TZ-235234-CS- QCBS / Consultancy Services Component 1: Empowering for training of Tutors on Quality And Cost- Pending IDA / 65340 Girls Through Secondary Post Open - National 370,000.00 0.00 2022-01-25 2022-02-15 2022-03-31 2022-04-28 2022-05-28 2022-07-02 2022-08-06 2023-08-06 information systems to track Based Selection Implementation Education and Life Skills secondary school dropout (for IAE center) TZ-MOEST-TZ-235238-CS- QCBS / Consultancy Services Component 3: Reducing for training on School Barriers to Girls' Education Quality And Cost- Pending Construction Strategy and IDA / 65340 Post Open - National 420,000.00 0.00 2021-09-20 2021-10-11 2021-11-24 2021-12-22 2022-01-21 2022-02-25 2022-04-01 2023-04-01 through Facilitating Access to Based Selection Implementation ESSF to LGA, Head of Schools Secondary Schools and School construction committee. Page 1 TZ-MOEST-TZ-235241-CS- QCBS / Consultancy services for provision of technical Component 4: Project Quality And Cost- Pending Assistance to support overall IDA / 65340 Coordination, Monitoring and Post Open - National 490,000.00 0.00 2021-11-15 2021-12-06 2022-01-19 2022-02-16 2022-03-18 2022-04-22 2022-05-27 2023-05-27 Based Selection Implementation project coordination and M&E, Evaluation including conducting a capacity assessment TZ-MOEST-TZ-235256-CS- Component 4: Project QCBS / Consultancy Service Quality And Cost- Pending IDA / 65340 Coordination, Monitoring and Prior Open - National 485,000.00 0.00 2021-07-30 2021-08-20 2021-10-03 2021-10-31 2021-11-30 2022-01-04 2022-02-08 2023-02-08 for Provision of Independent Based Selection Implementation Evaluation Project Verification INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 2 AR Chronic Conditions and Injuries (P133193) Argentina, IBRD/IDA, FY: 2015, Team Leader(s): Maria Eugenia Bonilla-Chacin, Luis Orlando Perez , Lending Instrument: Investment Project Financing • PROCUREMENT Argentina : Protecting Vulnerable People Against Noncommunicable Diseases Project PLAN General Information Country: Argentina Bank’s Approval Date of the Original Procurement Plan: 2017-04-03 2021-05-26 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P133193 GPN Date: Project Name: Protecting Vulnerable People Against Noncommunicable Diseases Project Loan / Credit No: IBRD / 85080, / Ministry of Health Executing Agency(ies): WORKS Activity Reference No. / Procurement Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Market Procurement Prequalification High SEA/SH Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Document Amount Amount Document / and Recommendation Signed Contract No. Approach Process (Y/N) Risk Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion Type (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Document / and Recommendation Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 3: Supporting the National and Provincial Ministries of Health to AR-NA-1-B-CP / improve surveillance, Request for 2017-01- 2017-03- 2017-11- 2017-04- IBRD / 85080 Post Limited - National 83,031.25 45,503.90 Signed Equipamiento Informático monitoring, promotion, Quotations 24 16 27 30 prevention and control of NCDs, injuries, and risk factors. AR-NA-10-B-LPN / KIT PARA 2019-04- 2019-05- 2019-06- 2019-08- 2019-08- 2019-11- DESARROLLO DE ACTIVIDAD / Post Request for Bids Open - National 173,191.62 0.00 Canceled 18 03 07 06 31 29 FÍSICA 2019 Component 3: Supporting the National and Provincial Ministries of Health to AR-NA-2-B-CP / improve surveillance, Request for Single Stage - One 2017-09- 2017-11- 2018-06- 2018-01- IBRD / 85080 Post Limited - National 95,000.00 35,760.31 Signed EQUIPAMIENTO OFICINA monitoring, promotion, Quotations Envelope 14 29 19 13 prevention and control of NCDs, injuries, and risk factors. Component 3: Supporting the National and Provincial Ministries of Health to AR-NA-9-B-LPN / KIT PARA improve surveillance, Single Stage - One 2017-09- 2017-10- 2017-11- 2017-11- 2018-01- 2018-02- 2018-05- DESARROLLO DE ACTIVIDAD IBRD / 85080 Post Request for Bids Open - National 346,383.00 0.00 Canceled monitoring, promotion, Envelope 25 10 30 14 13 07 08 FÍSICA 2017 prevention and control of NCDs, injuries, and risk factors. Component 3: Supporting the National and Provincial Ministries of Health to AR-MSAL-18969-GO-RFB / improve surveillance, Single Stage - One 2017-11- 2017-12- 2017-11- 2018-01- 2018-03- 2018-04- 2018-08- IBRD / 85080 Post Request for Bids Open - National 3,010,700.00 0.00 Canceled Espirómetros y accesorios monitoring, promotion, Envelope 24 10 30 14 15 09 07 prevention and control of NCDs, injuries, and risk factors. Component 3: Supporting the National and Provincial Ministries of Health to AR-MSAL-34714-GO-RFB / improve surveillance, Single Stage - One 2017-11- 2017-12- 2017-11- 2018-01- 2018-03- 2018-04- 2018-06- IBRD / 85080 Post Request for Bids Open - National 781,887.29 0.00 Canceled Adquisición de Gazebos monitoring, promotion, Envelope 25 10 30 14 15 09 08 prevention and control of NCDs, injuries, and risk factors. Component 3: Supporting the National and Provincial Ministries of Health to AR-MSAL-34717-GO-RFP / improve surveillance, Request for Single Stage - One 2017-11- 2018-02- 2018-03- Adquisición de IBRD / 85080 Post Open - National 48,360.00 0.00 Canceled monitoring, promotion, Quotations Envelope 22 06 23 monofilamentos prevention and control of NCDs, injuries, and risk factors. Component 3: Supporting the National and Provincial Ministries of Health to AR-MSAL-34719-GO-RFB / improve surveillance, Single Stage - One 2017-11- 2017-11- 2017-12- 2017-11- 2018-01- 2018-01- 2018-03- 2018-03- 2018-04- 2018-06- 2019-10- Adquisición de Test de sangre IBRD / 85080 Post Request for Bids Open - National 850,000.00 639,000.00 Signed monitoring, promotion, Envelope 25 28 10 30 14 10 15 12 09 25 01 oculta prevention and control of NCDs, injuries, and risk factors. Component 3: Supporting the National and Provincial AR-MSAL-34723-GO-RFB / Ministries of Health to Equipamiento para el STEP 2 y improve surveillance, Single Stage - One 2017-11- 2017-11- 2017-12- 2017-11- 2018-01- 2018-02- 2018-03- 2018-03- 2018-04- 2018-06- 2018-06- IBRD / 85080 Post Request for Bids Open - National 300,000.00 90,646.71 Signed 3 de la encuesta de monitoring, promotion, Envelope 25 29 10 30 14 05 15 27 09 25 08 mediciones objetivas prevention and control of NCDs, injuries, and risk factors. Component 3: Supporting the National and Provincial Ministries of Health to AR-MSAL-13413-GO-RFB / improve surveillance, Open - Single Stage - One 2018-02- 2018-02- 2018-04- 2018-07- 2018-08- 2019-02- IBRD / 85080 Prior Request for Bids 18,019,891.89 0.00 Canceled Estaciones Saludables monitoring, promotion, International Envelope 08 23 09 02 09 05 prevention and control of NCDs, injuries, and risk factors. Component 3: Supporting the National and Provincial Ministries of Health to AR-NA-13-B-LPI / improve surveillance, Open - Single Stage - One 2017-09- 2017-09- 2017-11- 2018-02- 2018-03- 2018-07- Adquisición de PC all in one IBRD / 85080 Prior Request for Bids 4,052,895.20 0.00 Canceled monitoring, promotion, International Envelope 11 26 10 02 12 10 para caps prevention and control of NCDs, injuries, and risk factors. Component 3: Supporting the National and Provincial Ministries of Health to AR-MSAL-55434-GO-RFB / improve surveillance, Single Stage - One 2018-04- 2018-06- 2018-05- 2018-06- 2018-07- 2018-08- 2018-07- 2018-09- 2018-10- 2019-01- Adquisición de PC All in One IBRD / 85080 Post Request for Bids Open - National 1,482,646.23 1,111,196.83 Signed monitoring, promotion, Envelope 25 01 10 14 13 13 31 07 16 05 para CAPS prevention and control of NCDs, injuries, and risk factors. Component 3: Supporting the National and Provincial Ministries of Health to AR-MSAL-52279-GO-RFB / improve surveillance, Single Stage - One 2018-04- 2018-05- 2018-05- 2018-06- 2018-07- 2018-08- 2018-07- 2018-09- 2018-10- 2019-01- IBRD / 85080 Post Request for Bids Open - National 247,843.68 468,834.95 Signed Estaciones Saludables monitoring, promotion, Envelope 26 29 11 15 12 14 23 08 05 06 prevention and control of NCDs, injuries, and risk factors. Component 3: Supporting the National and Provincial Ministries of Health to AR-NA-6-B-LPI / improve surveillance, Open - Single Stage - One 2017-09- 2017-10- 2017-09- 2018-01- 2017-11- 2017-12- 2018-01- 2018-03- 2018-06- IBRD / 85080 Prior Request for Bids 14,807,204.00 0.00 Canceled ADQUISICION DE MOVILES monitoring, promotion, International Envelope 08 31 23 09 07 27 30 09 07 prevention and control of NCDs, injuries, and risk factors. Page 1 Component 3: Supporting the National and Provincial AR-MSAL-60905-GO-RFQ / Ministries of Health to Equipamiento para el STEP 2 y improve surveillance, Request for Single Stage - One 2018-05- 2018-07- 2018-09- 2018-09- 3 de la encuesta de IBRD / 85080 Post Open - National 58,307.20 37,447.47 Signed monitoring, promotion, Quotations Envelope 11 26 05 09 mediciones objetivas prevention and control of (renglones desiertos) NCDs, injuries, and risk factors. Component 3: Supporting the National and Provincial Ministries of Health to AR-MSAL-26176-GO-RFB / improve surveillance, Open - Single Stage - One 2017-10- 2017-10- 2017-12- 2018-03- 2018-04- 2019-03- Adquisición de colonoscopios IBRD / 85080 Prior Request for Bids 6,281,000.00 0.00 Canceled monitoring, promotion, International Envelope 09 24 08 02 04 30 e insumos - INC prevention and control of NCDs, injuries, and risk factors. Component 3: Supporting the National and Provincial Ministries of Health to AR-MSAL-34715-GO-RFB / improve surveillance, Single Stage - One 2017-11- 2017-12- 2017-11- 2018-01- 2018-03- 2018-04- 2018-06- Adquisición de tensiometros IBRD / 85080 Post Request for Bids Open - National 199,440.00 0.00 Canceled monitoring, promotion, Envelope 25 10 30 14 15 09 08 y balanzas prevention and control of NCDs, injuries, and risk factors. Component 3: Supporting the National and Provincial Ministries of Health to AR-MSAL-60914-GO-RFB / improve surveillance, Single Stage - One 2018-06- 2018-07- 2018-08- 2018-10- 2018-11- 2019-05- Adquisición de colonoscopios IBRD / 85080 Prior Request for Bids Open - National 4,173,303.11 0.00 Canceled monitoring, promotion, Envelope 18 03 07 16 14 13 e insumos- INC prevention and control of NCDs, injuries, and risk factors. Component 3: Supporting the National and Provincial Ministries of Health to AR-MSAL-70188-GO-RFB / Under improve surveillance, Open - Single Stage - One 2018-08- 2018-12- 2018-09- 2019-01- 2018-10- 2019-02- 2019-01- 2019-02- 2019-08- Adquisición de colonoscopios IBRD / 85080 Prior Request for Bids 4,130,500.00 0.00 Implementati monitoring, promotion, International Envelope 18 17 02 09 17 22 09 16 15 e insumos- INC on prevention and control of NCDs, injuries, and risk factors. Component 3: Supporting the National and Provincial Ministries of Health to AR-MSAL-26166-GO-RFB / improve surveillance, Open - Single Stage - One 2018-01- 2018-02- 2018-03- 2018-06- 2018-07- 2018-11- IBRD / 85080 Prior Request for Bids 4,884,595.80 0.00 Canceled Notebook y Tablets para Caps monitoring, promotion, International Envelope 25 09 26 18 26 23 prevention and control of NCDs, injuries, and risk factors. Component 3: Supporting the National and Provincial Ministries of Health to AR-NA-7-B-LPI / GIMNASIOS improve surveillance, Open - Single Stage - One 2017-09- 2017-09- 2017-11- 2018-02- 2018-03- 2018-07- IBRD / 85080 Prior Request for Bids 14,615,567.32 0.00 Canceled AL AIRE LIBRE monitoring, promotion, International Envelope 10 25 09 01 11 09 prevention and control of NCDs, injuries, and risk factors. Component 3: Supporting the National and Provincial Ministries of Health to AR-MSAL-14591-GO-RFB / improve surveillance, Open - Single Stage - One 2018-01- 2018-02- 2018-03- 2018-06- 2018-07- 2018-11- IBRD / 85080 Prior Request for Bids 6,909,901.60 0.00 Canceled Instrumental Médico monitoring, promotion, International Envelope 25 09 26 18 26 23 prevention and control of NCDs, injuries, and risk factors. Component 3: Supporting the National and Provincial Ministries of Health to improve surveillance, Open - Single Stage - One 2017-09- 2017-09- 2017-11- 2018-02- 2018-03- 2018-07- AR-NA-8-B-LPI / BICICLETAS IBRD / 85080 Prior Request for Bids 5,217,310.55 0.00 Canceled monitoring, promotion, International Envelope 11 26 10 02 12 10 prevention and control of NCDs, injuries, and risk factors. Component 3: Supporting the National and Provincial Ministries of Health to AR-MSAL-60917-GO-RFQ / improve surveillance, Request for Single Stage - One 2018-05- 2018-08- 2018-11- IBRD / 85080 Post Open - National 26,461.40 0.00 Canceled Adquisición de Tensiometros monitoring, promotion, Quotations Envelope 18 02 30 prevention and control of NCDs, injuries, and risk factors. Component 3: Supporting the National and Provincial Ministries of Health to AR-MSAL-52282-GO-RFQ / improve surveillance, Request for Single Stage - One 2018-04- 2018-07- 2018-08- Adquisición de tablets para la IBRD / 85080 Post Open - National 71,592.00 0.00 Canceled monitoring, promotion, Quotations Envelope 22 07 06 realización de la ENNyS prevention and control of NCDs, injuries, and risk factors. Component 3: Supporting the National and Provincial Ministries of Health to AR-NA-12-B-LPN / improve surveillance, Single Stage - One 2018-02- 2018-02- 2018-04- 2018-06- 2018-06- 2018-10- EQUIPAMIENTO IBRD / 85080 Post Request for Bids Open - National 2,844,000.00 0.00 Canceled monitoring, promotion, Envelope 11 26 02 01 26 24 LABORATORIO prevention and control of NCDs, injuries, and risk factors. Component 3: Supporting the National and Provincial Ministries of Health to AR-MSAL-14592-GO-RFQ / improve surveillance, Request for Single Stage - One 2017-11- 2018-02- 2018-03- Equipamiento Informático IBRD / 85080 Post Open - National 80,000.00 0.00 Canceled monitoring, promotion, Quotations Envelope 22 06 23 para DENT prevention and control of NCDs, injuries, and risk factors. Component 3: Supporting the National and Provincial Ministries of Health to AR-MSAL-14593-GO-RFB / improve surveillance, Open - Single Stage - One 2017-10- 2017-10- 2017-12- 2018-03- 2018-04- 2018-08- IBRD / 85080 Prior Request for Bids 9,678,126.72 0.00 Canceled Adquisición de medicamentos monitoring, promotion, International Envelope 09 24 08 02 09 07 prevention and control of NCDs, injuries, and risk factors. Component 1: Improving the readiness of public health care facilities to provide 80-0002-CDI17 / higher quality services for 2020-08- 2017-06- 2020-08- 2017-03- 2020-10- 2018-02- 2021-04- IBRD / 85080 Post Direct Selection Direct 2,019,673.39 1,803,762.14 Signed Adquisición de Trastuzumab NCDs for vuln erable 25 01 30 14 04 03 02 population groups and expanding the scope of selected services. Component 1: Improving the readiness of public health care facilities to provide 80-0034-CDI18 / higher quality services for 2020-08- 2018-01- 2020-08- 2018-05- 2020-10- 2018-08- 2021-04- IBRD / 85080 Post Direct Selection Direct 203,160.60 181,441.91 Signed Adquisición de ciclosporina NCDs for vuln erable 26 18 31 08 05 02 03 population groups and expanding the scope of selected services. Page 2 Component 1: Improving the readiness of public health care facilities to provide 80-0063-CDI18 / higher quality services for 2020-08- 2018-09- 2020-08- 2018-11- 2020-10- 2019-02- 2021-04- IBRD / 85080 Post Direct Selection Direct 180,367.79 622,873.29 Signed Adquisición de Sunitinib. NCDs for vuln erable 26 19 31 14 05 07 03 population groups and expanding the scope of selected services. Component 1: Improving the readiness of public health care facilities to provide 80-0007-LPU17 / higher quality services for Single Stage - One 2020-08- 2017-06- 2020-08- 2020-09- 2017-07- 2021-01- 2017-07- 2021-03- 2018-02- 2021-09- Adquisición de medicamentos IBRD / 85080 Post Request for Bids Open - National 2,468,627.87 2,204,721.26 Signed NCDs for vuln erable Envelope 24 01 25 09 21 07 21 23 02 19 inmunosupresores population groups and expanding the scope of selected services. Component 1: Improving the readiness of public health 80-0028-LPU17 / care facilities to provide Adquisición de medicamentos higher quality services for Single Stage - One 2020-08- 2018-02- 2020-08- 2020-10- 2018-06- 2020-11- 2018-11- 2020-12- 2019-03- 2021-06- IBRD / 85080 Post Request for Bids Open - National 3,581,200.87 3,557,240.81 Signed inmusupresores INCUCAI NCDs for vuln erable Envelope 25 01 30 11 25 10 28 15 14 13 2018-2019 population groups and expanding the scope of selected services. Component 3: Supporting the National and Provincial Ministries of Health to AR-MSAL-136976-GO-RFB / improve surveillance, Single Stage - One 2019-10- 2019-11- 2019-12- 2020-02- 2020-03- 2021-01- Adquisición de parches de IBRD / 85080 Post Request for Bids Open - National 950,000.00 0.00 Canceled monitoring, promotion, Envelope 25 09 14 12 08 02 nicotina prevention and control of NCDs, injuries, and risk factors. Component 3: Supporting the National and Provincial Ministries of Health to AR-MSAL-124339-GO-RFB / improve surveillance, Single Stage - One 2019-10- 2019-10- 2019-11- 2020-01- 2020-02- 2020-06- Adquisición de tensiometros IBRD / 85080 Post Request for Bids Open - National 1,641,570.00 0.00 Canceled monitoring, promotion, Envelope 10 25 29 28 22 21 y balanzas prevention and control of NCDs, injuries, and risk factors. Component 3: Supporting the National and Provincial Ministries of Health to Under AR-MSAL-200459-GO-RFB / improve surveillance, Open - Single Stage - One 2021-01- 2021-06- 2021-01- 2021-06- 2021-02- 2021-02- 2021-03- 2021-04- IBRD / 85080 Prior Request for Bids 9,340,000.00 0.00 Implementati Adquisición de PC monitoring, promotion, International Envelope 07 15 12 17 11 21 13 27 on prevention and control of NCDs, injuries, and risk factors. Component 2: Protecting AR-MSAL-201408-GO-RFQ / Pending vulnerable population groups Request for Single Stage - One 2021-01- 2021-03- 2021-03- Adquisición de Test Sangro IBRD / 85080 Post Open - National 89,600.00 0.00 Implementati against prevalent NCD risk Quotations Envelope 16 13 16 Oculta en Materia Fecal on factors. Component 1: Improving the readiness of public health 80-0027-LPU17 / care facilities to provide Under Medicamentos Esenciales higher quality services for Single Stage - One 2020-12- 2020-12- 2021-02- 2021-03- 2021-04- 2021-10- IBRD / 85080 Post Request for Bids Open - National 4,957,679.62 0.00 Implementati para el Primer Nivel de NCDs for vuln erable Envelope 16 21 01 03 07 04 on Atención population groups and expanding the scope of selected services. Component 1: Improving the readiness of public health care facilities to provide 80-0029-CDI18 / higher quality services for 2020-12- 2018-01- 2020-12- 2018-05- 2021-01- 2019-01- 2021-07- IBRD / 85080 Post Direct Selection Direct 9,289.37 36,024.98 Signed Adquisición de Vinorelbina NCDs for vuln erable 16 18 21 23 25 29 24 population groups and expanding the scope of selected services. Component 1: Improving the readiness of public health 80-0024-LPU17 / care facilities to provide ADQUISICION DE higher quality services for Single Stage - One 2020-12- 2018-04- 2020-12- 2021-02- 2018-04- 2021-03- 2018-04- 2021-04- 2019-02- 2021-10- IBRD / 85080 Post Request for Bids Open - National 2,583,252.98 1,893,264.02 Signed MEDICAMENTOS NCDs for vuln erable Envelope 16 03 21 01 20 03 26 07 04 04 ONCOLOGICOS population groups and expanding the scope of selected services. Component 1: Improving the readiness of public health 80-0004-CDI18 / care facilities to provide ADQUISICION DE HORMONA higher quality services for 2020-12- 2016-09- 2020-12- 2018-01- 2021-01- 2018-03- 2021-07- IBRD / 85080 Post Direct Selection Direct 38,411.91 41,166.62 Signed DE CRECIMIENTO NCDs for vuln erable 16 27 21 26 25 19 24 SOMATOTROFINA population groups and expanding the scope of selected services. Component 1: Improving the readiness of public health care facilities to provide 80-0017-LPU18 / Under higher quality services for Single Stage - One 2020-12- 2018-10- 2020-12- 2021-02- 2018-11- 2021-03- 2019-03- 2021-04- 2021-10- Adquisición Medicamentos IBRD / 85080 Post Request for Bids Open - National 1,958,398.97 0.00 Implementati NCDs for vuln erable Envelope 18 29 23 03 21 05 19 09 06 Oncológicos on population groups and expanding the scope of selected services. Component 3: Supporting the National and Provincial Ministries of Health to AR-MSAL-212405-GO-RFQ / Under improve surveillance, Request for Single Stage - One 2021-05- 2021-07- 2021-09- Adquisición de Tensiómetros IBRD / 85080 Post Open - National 59,100.00 0.00 Implementati monitoring, promotion, Quotations Envelope 12 06 04 Automáticos on prevention and control of NCDs, injuries, and risk factors. Component 3: Supporting the National and Provincial Ministries of Health to AR-MSAL-124340-GO-RFB / improve surveillance, Single Stage - One 2019-08- 2019-09- 2019-10- 2019-12- 2020-01- 2020-06- Adquisición de IBRD / 85080 Post Request for Bids Open - National 188,609.00 0.00 Canceled monitoring, promotion, Envelope 26 10 15 14 08 06 monofilamentos prevention and control of NCDs, injuries, and risk factors. Component 1: Improving the readiness of public health care facilities to provide AR-MSAL-201407-GO-RFB / Pending higher quality services for Single Stage - One 2021-06- 2021-06- 2021-07- 2021-07- 2021-08- 2022-02- Adquisición de Test de VPH y IBRD / 85080 Post Request for Bids Open - National 2,895,690.72 0.00 Implementati NCDs for vuln erable Envelope 04 09 09 29 27 23 colectores DNA on population groups and expanding the scope of selected services. Component 1: Improving the readiness of public health AR-MSAL-234252-GO-RFB / care facilities to provide Under Adquisición de Medicamentos higher quality services for Open - Single Stage - One 2021-05- 2021-06- 2021-07- 2021-08- 2021-09- 2021-12- IBRD / 85080 Prior Request for Bids 8,855,541.15 0.00 Implementati para Patologías Oncológicas - NCDs for vuln erable International Envelope 31 05 20 19 29 28 on BDE population groups and expanding the scope of selected services. Component 1: Improving the readiness of public health care facilities to provide AR-MSAL-231566-GO-RFB / Pending higher quality services for Open - Single Stage - One 2021-06- 2021-07- 2021-09- 2021-10- 2021-12- 2022-03- Adquisición de equipamiento IBRD / 85080 Prior Request for Bids 6,130,329.80 0.00 Implementati NCDs for vuln erable International Envelope 21 06 04 14 03 03 médico para el INC on population groups and expanding the scope of selected services. Page 3 Component 3: Supporting the National and Provincial AR-MSAL-124334-GO-RFB / Ministries of Health to Adquisición del equipamiento improve surveillance, Single Stage - One 2019-10- 2019-10- 2019-11- 2020-01- 2020-02- 2021-02- IBRD / 85080 Post Request for Bids Open - National 203,350.00 0.00 Canceled necesario para la realización monitoring, promotion, Envelope 10 25 29 28 22 16 de Espirometría prevention and control of NCDs, injuries, and risk factors. Component 3: Supporting the National and Provincial AR-MSAL-201406-GO-RFB / Ministries of Health to Pending Adquisición de improve surveillance, Single Stage - One 2021-08- 2021-08- 2021-09- 2021-10- 2021-11- 2022-01- IBRD / 85080 Post Request for Bids Open - National 453,804.00 0.00 Implementati Monofilamentos de Semmes- monitoring, promotion, Envelope 07 12 11 11 11 10 on Weinstein prevention and control of NCDs, injuries, and risk factors. Component 1: Improving the readiness of public health AR-MSAL-201404-GO-RFQ / care facilities to provide Pending Adquisición de Equipamiento higher quality services for Single Stage - One 2021-07- 2021-07- 2021-08- 2021-08- 2021-09- 2021-12- IBRD / 85080 Post Request for Bids Open - National 448,000.00 0.00 Implementati para el abordaje territorial de NCDs for vuln erable Envelope 01 06 05 30 28 27 on población indígena population groups and expanding the scope of selected services. Component 3: Supporting the National and Provincial AR-MSAL-201405-NC-RFB / Ministries of Health to Adquisición de Hardware y improve surveillance, Single Stage - One 2021-03- 2021-03- 2021-04- 2021-05- 2021-06- 2021-11- Software para nueva IBRD / 85080 Post Request for Bids Open - National 1,289,200.00 0.00 Canceled monitoring, promotion, Envelope 17 22 21 11 01 08 infraestructura en el marco de prevention and control of la escalabilidad del proyecto NCDs, injuries, and risk factors. Component 3: Supporting the National and Provincial AR-MSAL-147029-GO-RFB / Ministries of Health to Equipamiento para la improve surveillance, Single Stage - One 2019-12- 2020-01- 2020-02- 2020-04- 2020-05- 2020-07- IBRD / 85080 Post Request for Bids Open - National 150,000.00 0.00 Canceled determinación de sodio de monitoring, promotion, Envelope 23 07 11 11 06 05 alimentos prevention and control of NCDs, injuries, and risk factors. NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Document / and Recommendation Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 3: Supporting the National and Provincial Ministries of Health to AR-NA-25-S-LPN / improve surveillance, Single Stage - One 2017-10- 2017-10- 2017-11- 2017-12- 2018-01- 2018-03- 2018-02- 2018-04- 2018-05- 2018-10- ENCUESTA DE VIGILANCIA IBRD / 85080 Post Request for Bids Open - National 1,600,000.00 95,043.59 Signed monitoring, promotion, Envelope 09 24 30 08 09 02 19 09 08 06 TELEFONICA prevention and control of NCDs, injuries, and risk factors. Component 3: Supporting the National and Provincial Ministries of Health to AR-MSAL-26177-NC-RFB / improve surveillance, Single Stage - One 2017-09- 2017-10- 2017-11- 2017-11- 2018-01- 2018-01- 2018-03- IBRD / 85080 Post Request for Bids Open - National 331,809.00 0.00 Canceled Material de promoción monitoring, promotion, Envelope 18 03 29 07 06 31 17 prevention and control of NCDs, injuries, and risk factors. Component 3: Supporting the National and Provincial Ministries of Health to AR-MSAL-38858-NC-RFB / improve surveillance, Single Stage - One 2017-11- 2017-11- 2017-12- 2018-01- 2018-02- 2018-03- 2018-02- 2018-04- 2018-05- 2018-07- Encuesta de mediciones IBRD / 85080 Post Request for Bids Open - National 1,600,346.00 1,690,000.00 Signed monitoring, promotion, Envelope 30 30 11 15 05 16 23 10 07 09 objetivas prevention and control of NCDs, injuries, and risk factors. Component 3: Supporting the National and Provincial Ministries of Health to AR-MSAL-52281-NC-RFB / improve surveillance, Single Stage - One 2018-04- 2018-04- 2018-04- 2018-05- 2018-05- 2018-07- 2018-06- 2018-08- 2018-08- 2019-03- Mediciones bioquimicas para IBRD / 85080 Post Request for Bids Open - National 500,000.00 231,638.41 Signed monitoring, promotion, Envelope 11 03 26 31 11 30 21 24 03 22 la ENNyS prevention and control of NCDs, injuries, and risk factors. Component 3: Supporting the National and Provincial AR-MSAL-34725-NC-RFB / Ministries of Health to Encuesta nacional de improve surveillance, Single Stage - One 2018-02- 2018-03- 2018-04- 2018-06- 2018-07- 2019-05- Nutrición y Salud y primera IBRD / 85080 Prior Request for Bids Open - National 4,500,000.00 0.00 Canceled monitoring, promotion, Envelope 18 05 09 17 12 08 encuesta nacional de prevention and control of consumo de alimentos NCDs, injuries, and risk factors. Component 3: Supporting the National and Provincial Ministries of Health to AR-MSAL-18977-NC-RFB / improve surveillance, Single Stage - One 2017-11- 2017-11- 2017-12- 2018-03- 2018-03- 2018-07- Realización de eventos IBRD / 85080 Post Request for Bids Open - National 120,000.00 0.00 Canceled monitoring, promotion, Envelope 11 26 31 01 26 24 deportivos prevention and control of NCDs, injuries, and risk factors. Component 3: Supporting the National and Provincial Ministries of Health to AR-MSAL-34720-NC-RFB / improve surveillance, Single Stage - One 2017-11- 2017-12- 2018-01- 2018-03- 2018-04- 2018-05- Material de merchandising - IBRD / 85080 Post Request for Bids Open - National 663,581.00 0.00 Canceled monitoring, promotion, Envelope 25 10 14 15 09 24 Campaña 2 prevention and control of NCDs, injuries, and risk factors. Component 3: Supporting the National and Provincial Ministries of Health to AR-MSAL-18980-NC-RFB / improve surveillance, Single Stage - One 2018-01- 2018-01- 2018-03- 2018-06- 2018-07- 2018-10- Impresiones de tripticos, IBRD / 85080 Post Request for Bids Open - National 1,668,191.00 0.00 Canceled monitoring, promotion, Envelope 08 23 09 01 09 07 banners y otros prevention and control of NCDs, injuries, and risk factors. Component 3: Supporting the National and Provincial AR-NA-50-S-CP / Ministries of Health to IMPRESIONES MATERIAL ENT Y improve surveillance, Request for Single Stage - One 2018-04- 2018-06- 2018-07- IBRD / 85080 Post Limited - National 60,000.00 0.00 Canceled ABORDAJE CON PUEBLOS monitoring, promotion, Quotations Envelope 18 06 21 INDÍGENAS prevention and control of NCDs, injuries, and risk factors. Component 3: Supporting the National and Provincial Ministries of Health to AR-NA-24-S-LPN / improve surveillance, 2018-01- 2018-01- 2018-03- 2018-05- 2018-05- 2018-08- IBRD / 85080 Post Request for Bids Open - National 1,600,000.00 0.00 Canceled IMPRESIONES monitoring, promotion, 11 26 02 01 26 24 prevention and control of NCDs, injuries, and risk factors. Page 4 Component 3: Supporting the National and Provincial Ministries of Health to AR-MSAL-18979-NC-RFB / improve surveillance, Single Stage - One 2017-10- 2017-11- 2017-12- 2018-02- 2018-03- 2019-01- Análisis químicos y tabla de IBRD / 85080 Post Request for Bids Open - National 1,600,000.00 0.00 Canceled monitoring, promotion, Envelope 25 09 14 12 09 03 composición de alimentos prevention and control of NCDs, injuries, and risk factors. Component 1: Improving the readiness of public health AR-MSAL-237622-NC-RFQ / care facilities to provide Contratación del servicio de Pending higher quality services for Request for Single Stage - One 2021-07- 2021-09- 2021-12- realización de la “2° Encuesta IBRD / 85080 Post Open - National 85,000.00 0.00 Implementati NCDs for vuln erable Quotations Envelope 01 11 10 Nacional de Vigilancia on population groups and Telefónica (Vigitel 2021)” expanding the scope of selected services. Component 3: Supporting the National and Provincial AR-MSAL-201411-NC-DIR / Ministries of Health to Capacitaciones para la improve surveillance, 2021-03- 2021-04- 2021-05- 2021-11- plataforma virtual de IBRD / 85080 Post Direct Selection Direct 24,500.00 0.00 Canceled monitoring, promotion, 27 11 16 12 estandares de prevention and control of interioperatibilidad HL7-FHIR NCDs, injuries, and risk factors. CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 3: Supporting the National and Provincial Ministries of Health to AR-NA-15-CF-SBCC / improve surveillance, Quality And Cost- Open - 2017-01- 2017-05- 2016-07- 2017-11- 2016-08- 2017-12- 2017-05- 2018-06- 2017-07- 2018-08- 2017-08- 2018-09- 2019-01- IBRD / 85080 Prior 2,880,000.00 584,460.13 Signed AUDITORIA OPERATIVA monitoring, promotion, Based Selection International 05 08 26 21 09 20 21 27 18 16 28 12 18 prevention and control of NCDs, injuries, and risk factors. Component 3: Supporting the National and Provincial Ministries of Health to AR-NA-14-CF-SBCC / improve surveillance, Quality And Cost- 2016-11- 2017-02- 2017-09- 2017-10- 2017-06- 2017-11- 2017-07- 2017-12- 2017-08- 2018-02- 2018-02- AUDITORIA DE PROGRAMAS IBRD / 85080 Post Open - National 600,000.00 418,916.67 Signed monitoring, promotion, Based Selection 11 13 26 24 10 09 14 22 14 06 10 ELEGIBLES prevention and control of NCDs, injuries, and risk factors. AR-NA-18-CF-SBCC / Quality And Cost- 2017-03- 2017-07- 2017-08- 2017-09- 2018-03- ENCUESTA DE VIGILANCIA / Post Open - National 230,000.00 0.00 Canceled Based Selection 15 10 13 13 12 LESIONES Component 3: Supporting the National and Provincial Ministries of Health to AR-MSAL-26193-CS-QCBS / improve surveillance, Quality And Cost- Open - 2017-11- 2017-11- 2017-12- 2018-01- 2018-03- 2018-04- 2018-05- 2018-11- Encuesta de mediciones IBRD / 85080 Post 1,700,000.00 0.00 Canceled 2017-11-15 monitoring, promotion, Based Selection International 30 30 30 31 27 30 31 17 objetivas prevention and control of NCDs, injuries, and risk factors. Component 3: Supporting AR-MSAL-26198-CS-QCBS / the National and Provincial Convocatoria de programas Ministries of Health to de implementación, improve surveillance, Quality And Cost- Open - 2017-10- 2017-12- 2018-01- 2018-02- 2018-04- 2018-05- 2018-11- IBRD / 85080 Prior 2,000,000.00 0.00 Canceled 2017-10-15 diseminación y escalamiento monitoring, promotion, Based Selection International 30 23 25 23 20 28 24 de estrategias clínicas para prevention and control of disminución del tabaquismo. NCDs, injuries, and risk factors. Component 3: Supporting AR-MSAL-26197-CS-QCBS / the National and Provincial Convocatoria de programas Ministries of Health to de implementación, improve surveillance, Quality And Cost- Open - 2017-10- 2017-12- 2018-01- 2018-02- 2018-04- 2018-05- 2018-11- diseminación y escalamiento IBRD / 85080 Prior 5,000,000.00 0.00 Canceled 2017-10-15 monitoring, promotion, Based Selection International 30 23 25 23 20 28 24 de estrategias clínicas prevention and control of parareducción de NCDs, injuries, and risk hipertensión factors. Component 3: Supporting the National and Provincial AR-MSAL-26196-CS-QCBS / Ministries of Health to Implementación del plan de improve surveillance, Quality And Cost- Open - 2017-12- 2018-01- 2018-02- 2018-04- 2018-05- 2018-06- 2019-02- diseminación e implantación IBRD / 85080 Post 1,600,000.00 0.00 Canceled 2017-12-01 monitoring, promotion, Based Selection International 16 15 16 12 16 16 11 de las guías de práctica prevention and control of clínica NCDs, injuries, and risk factors. Component 3: Supporting the National and Provincial AR-MSAL-18984-CS-QCBS / Ministries of Health to Paquetes de revisiones improve surveillance, Quality And Cost- 2017-12- 2017-12- 2018-01- 2018-03- 2018-04- 2018-05- 2018-11- IBRD / 85080 Post Open - National 400,000.00 0.00 Canceled 2017-11-11 sistemáticas sobre impacto monitoring, promotion, Based Selection 11 28 27 23 26 27 23 de políticas de ENT prevention and control of NCDs, injuries, and risk factors. Component 3: Supporting the National and Provincial AR-MSAL-18982-CS-QCBS / Ministries of Health to Estudio de carga de improve surveillance, Quality And Cost- 2017-12- 2017-12- 2018-01- 2018-03- 2018-04- 2018-05- 2018-09- enfermedades y evaluaciones IBRD / 85080 Post Open - National 100,000.00 0.00 Canceled 2017-11-11 monitoring, promotion, Based Selection 11 28 27 23 26 27 24 económicas para estimar prevention and control of impacto de la ENT NCDs, injuries, and risk factors. Component 3: Supporting the National and Provincial Ministries of Health to AR-NA-20-CF-SBCC / Portal improve surveillance, Quality And Cost- 2018-01- 2018-03- 2018-03- 2018-04- 2018-05- 2018-06- 2018-07- 2018-11- web y herramientas IBRD / 85080 Post Open - National 198,995.70 0.00 Canceled 2018-01-15 monitoring, promotion, Based Selection 30 01 03 02 27 30 31 28 interactivas prevention and control of NCDs, injuries, and risk factors. Component 3: Supporting the National and Provincial AR-NA-19-CF-SBCC / Ministries of Health to Monitoreo de implementación improve surveillance, Quality And Cost- 2018-01- 2018-02- 2018-02- 2018-03- 2018-05- 2018-06- 2018-07- 2018-10- IBRD / 85080 Post Open - National 70,000.00 0.00 Canceled 2018-01-01 de estrategia integral de monitoring, promotion, Based Selection 16 15 17 19 13 16 17 15 comunicación prevention and control of NCDs, injuries, and risk factors. Component 3: Supporting the National and Provincial AR-MSAL-26194-CS-QCBS / Ministries of Health to Propuestas de reformulación improve surveillance, Quality And Cost- 2017-12- 2018-01- 2018-02- 2018-04- 2018-05- 2018-06- 2018-10- de alimentos (tecnología de IBRD / 85080 Post Open - National 300,000.00 0.00 Canceled 2017-12-01 monitoring, promotion, Based Selection 16 07 08 14 18 08 06 alimentos) sodio, grasas trans prevention and control of y azúcar NCDs, injuries, and risk factors. Component 3: Supporting the National and Provincial AR-MSAL-26182-CS-QCBS / Ministries of Health to Estudio cuali/cuantitativo de improve surveillance, Quality And Cost- 2017-09- 2017-10- 2017-11- 2018-01- 2018-02- 2018-03- 2018-07- IBRD / 85080 Post Open - National 280,000.00 0.00 Canceled 2017-09-01 evaluación de rotulado frontal monitoring, promotion, Based Selection 16 08 09 13 16 09 07 de alimentos prevention and control of NCDs, injuries, and risk factors. Page 5 Component 3: Supporting the National and Provincial AR-NA-22-CF-SBCC / Ministries of Health to Comunicación educativa para improve surveillance, Quality And Cost- 2018-04- 2018-07- 2018-08- 2018-09- 2018-12- IBRD / 85080 Post Open - National 50,000.00 0.00 Canceled niños, niñas y adolescentes monitoring, promotion, Based Selection 12 13 16 16 15 Línea de Tabaco prevention and control of NCDs, injuries, and risk factors. Component 3: Supporting AR-MSAL-26191-CS-QCBS / the National and Provincial Consultoría para el estudio Ministries of Health to cuanti cualitativo sobre improve surveillance, Quality And Cost- 2017-09- 2017-10- 2017-11- 2018-01- 2018-02- 2018-03- 2018-07- percepciones información y IBRD / 85080 Post Open - National 280,000.00 0.00 Canceled 2017-09-01 monitoring, promotion, Based Selection 16 08 09 13 16 09 07 representaciones de la prevention and control of población con relación a las NCDs, injuries, and risk ENT y la comunicación factors. Component 3: Supporting the National and Provincial AR-NA-17-CF-SBCC / Ministries of Health to DESARROLLO DE LA improve surveillance, Quality And Cost- 2017-10- 2017-11- 2017-11- 2017-12- 2018-02- 2018-03- 2018-04- 2018-10- IBRD / 85080 Post Open - National 200,000.00 0.00 Canceled 2017-10-01 ESTRATEGIA DE LA LINEA monitoring, promotion, Based Selection 31 17 17 17 10 16 16 13 0800 prevention and control of NCDs, injuries, and risk factors. Component 3: Supporting the National and Provincial Ministries of Health to AR-NA-21-CF-SBCC / Plan improve surveillance, Quality And Cost- 2018-02- 2018-03- 2018-03- 2018-04- 2018-05- 2018-06- 2018-07- 2019-01- de eventos y marketing IBRD / 85080 Post Open - National 500,000.00 0.00 Canceled 2018-01-15 monitoring, promotion, Based Selection 14 01 03 02 27 30 31 27 directo Salud y ENT prevention and control of NCDs, injuries, and risk factors. Component 3: Supporting the National and Provincial AR-MSAL-26195-CS-QCBS / Ministries of Health to Propuesta de evaluación de la improve surveillance, Quality And Cost- 2017-12- 2018-01- 2018-02- 2018-04- 2018-05- 2018-06- 2018-10- IBRD / 85080 Post Open - National 300,000.00 0.00 Canceled 2017-12-01 regulación de productos de monitoring, promotion, Based Selection 16 07 08 14 18 08 06 tabaco prevention and control of NCDs, injuries, and risk factors. Component 3: Supporting the National and Provincial Ministries of Health to AR-MSAL-124345-CS-QCBS improve surveillance, Quality And Cost- 2019-08- 2019-09- 2019-10- 2019-12- 2020-01- 2020-02- 2021-12- / Auditoria a Provincias 2019- IBRD / 85080 Post Open - National 500,000.00 0.00 Canceled 2019-08-01 monitoring, promotion, Based Selection 31 17 17 11 14 14 30 2022 prevention and control of NCDs, injuries, and risk factors. Component 3: Supporting the National and Provincial Ministries of Health to AR-MSAL-124341-CS-QCBS improve surveillance, Quality And Cost- Open - 2020-02- 2019-09- 2020-05- 2019-10- 2019-11- 2019-12- 2020-01- 2020-03- 2021-12- IBRD / 85080 Prior 1,100,000.00 0.00 Canceled 2019-08-01 / Auditoria de IVT 2019-2022 monitoring, promotion, Based Selection International 19 15 14 12 11 10 26 13 28 prevention and control of NCDs, injuries, and risk factors. Component 1: Improving the readiness of public health care facilities to provide AR-MSAL-124341-CS-QCBS- higher quality services for Quality And Cost- 2020-05- 2020-09- 2020-10- 2020-11- 2020-11- 2020-12- 2020-12- 2020-12- 2021-02- 2021-02- 2021-03- 2021-04- 2022-03- IBRD / 85080 Post Open - National 668,905.00 149,128.52 Signed 2020-08-27 / Auditoría IVT 2019-2022 NCDs for vuln erable Based Selection 15 17 31 02 28 02 28 30 01 01 08 21 08 population groups and expanding the scope of selected services. Component 3: Supporting the National and Provincial Ministries of Health to Consultant AR-MSAL-201412-CS-QCBS improve surveillance, Under 2021-03- 2021-04- 2021-05- 2021-06- 2021-05- 2021-06- 2021-12- IBRD / 85080 Post Qualification Open - National 41,475.85 0.00 2021-03-13 / Auditoria PGE 2020 monitoring, promotion, Implementation 11 03 02 04 17 08 05 Selection prevention and control of NCDs, injuries, and risk factors. AR-MSAL-201410-CS-QCBS Component 2: Protecting / Adecuación del RITA, vulnerable population groups Quality And Cost- 2021-03- 2021-04- 2021-04- 2021-04- 2021-05- 2021-05- 2021-11- SITAM, crónicos y sanidad de IBRD / 85080 Post Open - National 936,400.00 0.00 Canceled 2021-02-26 against prevalent NCD risk Based Selection 12 02 16 23 07 21 17 fronteras con microservicios factors. interoperables INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual AR-NA-35-CI-3CV / Contratación individual posición 'Responsable de la Individual Unidad de Articulación con la Pending 2016-05- 2020-12- / Post Consultant Limited 102,037.00 0.00 Dirección de Promoción y Implementation 01 31 Selection Control de Enfermedades No Transmisibles y las Provincias' (1 consultor) Component 3: Supporting the National and Provincial AR-NA-28-CI-3CV / Ministries of Health to Individual Contratación individual improve surveillance, 2016-06- 2016-05- 2017-04- 2020-12- IBRD / 85080 Post Consultant Limited 91,024.00 7,224.77 Signed posición 'Asesor Legal' (1 monitoring, promotion, 08 01 15 31 Selection consultor) prevention and control of NCDs, injuries, and risk factors. AR-NA-27-CI-3CV / Component 2: Protecting Individual Contratación individual vulnerable population groups 2016-06- 2016-05- 2017-12- 2020-12- 2018-10- IBRD / 85080 Post Consultant Limited 107,909.00 1,209.16 Terminated posición 'Coordinador against prevalent NCD risk 08 01 01 31 31 Selection General' (1 consultor) factors. AR-NA-45-CI-3CV / Contratación individual Individual Pending 2016-05- 2020-12- posición 'Staff Técnico para el / Post Consultant Limited 135,069.00 0.00 Implementation 01 31 Fortalecimiento del INAL' (2 Selection consultores) AR-NA-36-CI-3CV / Contratación individual posición 'Staff de Apoyo a la Individual Unidad de Articulación con la Pending 2016-05- 2020-12- / Post Consultant Limited 182,047.00 0.00 Dirección de Promoción y Implementation 01 31 Selection Control de Enfermedades No Transmisibles y las Provincias' (2 consultores) Component 3: Supporting AR-NA-40-CI-3CV / the National and Provincial Contratación individual Ministries of Health to Individual posición 'Staff Técnico de improve surveillance, 2017-05- 2017-05- 2016-05- 2017-08- 2020-12- IBRD / 85080 Post Consultant Limited 202,604.00 7,772.55 Signed Apoyo al Área de monitoring, promotion, 09 24 01 01 31 Selection reorientación de los Servicios prevention and control of de Salud' (3 consultores) NCDs, injuries, and risk factors. Page 6 AR-NA-55-CI-3CV / LO- Contratación individual posición 'Especialista Legal Senior para la puesta en Individual Pending 2016-07- 2016-12- marcha del Proyecto de / Post Consultant Limited 7,443.00 0.00 Implementation 01 31 Protección de la Población Selection Vulnerable contra las Enfermedades Crónicas No Transmisibles' (1 consultor) AR-NA-57-CI-3CV / LO- Contratación individual posición 'Staff de apoyo a la Individual Pending 2016-07- 2016-11- Unidad de Articulación con la / Post Consultant Limited 12,404.00 0.00 Implementation 01 30 Dirección de Promoción y Selection ECNT y Provincias' (2 consultores) AR-NA-62-CI-3CV / LO- Component 2: Protecting Especialista en Diseño de Individual vulnerable population groups 2017-09- 2017-01- 2017-10- 2017-12- 2018-03- Sistemas de Vigilancia de IBRD / 85080 Post Consultant Limited 22,427.00 2,774.18 Completed against prevalent NCD risk 25 01 01 31 31 Enfermedades Crónicas No Selection factors. Transmisibles (1 consultor) AR-NA-64-CI-3CV / LO- Apoyo funcional para la Individual Unidad de Articulación con la Pending 2017-01- 2017-12- / Post Consultant Limited 41,760.00 0.00 Dirección de Promoción y Implementation 01 31 Selection ECNT y Provincias (2 consultores) Component 3: Supporting the National and Provincial AR-NA-65-CI-3CV / LO- Ministries of Health to Individual Apoyo funcional a la unidad improve surveillance, 2017-05- 2017-01- 2017-07- 2017-12- IBRD / 85080 Post Consultant Limited 77,332.00 4,304.71 Signed de Monitoreo y evaluación (4 monitoring, promotion, 08 01 01 31 Selection consultores) prevention and control of NCDs, injuries, and risk factors. AR-NA-59-CI-3CV / LO- Individual Apoyo Funcional para la Pending 2017-01- 2017-12- / Post Consultant Limited 63,638.00 0.00 coordinación general (3 Implementation 01 31 Selection consultores) Component 3: Supporting the National and Provincial AR-NA-51-CI-3CV / LO- Ministries of Health to Contratación individual Individual improve surveillance, 2017-07- 2016-07- 2017-08- 2016-12- posición 'Staff de apoyo a la IBRD / 85080 Post Consultant Limited 22,328.00 2,741.87 Signed monitoring, promotion, 24 01 01 31 Coordinación General' (3 Selection prevention and control of consultores) NCDs, injuries, and risk factors. AR-NA-52-CI-3CV / LO- Contratación individual posición 'Asistencia técnica Individual para estudios de la Pending 2016-07- 2016-12- / Post Consultant Limited 10,031.00 0.00 estructura, elaboración de Implementation 01 31 Selection diagnóstico y desarrollo de un plan estratégico de ENT' (1 consultor) AR-NA-53-CI-3CV / LO- Contratación individual Individual posición 'Fortalecimiento de Pending 2016-07- 2016-12- / Post Consultant Limited 7,443.00 0.00 herramientas para la Implementation 01 31 Selection promoción en salud alimentaria' (1 consultor) AR-NA-63-CI-3CV / LO- Asesor Legal Senior para el Component 2: Protecting fortalecimiento del Proyecto Individual vulnerable population groups 2017-08- 2017-01- 2017-09- 2017-12- 2018-08- de Protección de la Población IBRD / 85080 Post Consultant Limited 17,786.00 2,657.28 Completed against prevalent NCD risk 17 01 01 31 31 Vulnerable contra las Selection factors. Enfermedades Crónicas No Transmisibles (1 consultor) AR-NA-60-CI-3CV / LO- Asistencia técnica para analisis de la estructura, Individual Pending 2017-01- 2017-12- elaboración de diagnóstico y / Post Consultant Limited 62,638.00 0.00 Implementation 01 31 desarrollo de un plan Selection estratégico de ENT (3 consultores) Component 3: Supporting AR-NA-61-CI-3CV / LO- the National and Provincial Especialista para el Desarrollo Ministries of Health to Individual de herramientas para el improve surveillance, 2017-07- 2017-01- 2017-08- 2017-12- 2018-05- IBRD / 85080 Post Consultant Limited 20,880.00 4,118.71 Completed Fortalecimiento de la monitoring, promotion, 24 01 01 31 31 Selection promoción en salud prevention and control of alimentaria (1 consultor) NCDs, injuries, and risk factors. AR-NA-66-CI-3CV / LO- Component 2: Protecting Equipos de Apoyo para el Individual vulnerable population groups 2017-02- 2017-01- 2018-07- 2018-12- 2018-06- Fortalecimiento del Proyecto a IBRD / 85080 Post Consultant Limited 1,076,460.00 33,696.63 Signed against prevalent NCD risk 28 01 01 31 30 nivel provincial y/o municipal Selection factors. (24 consultores) Component 3: Supporting the National and Provincial AR-MSAL-15119-CS-INDV / Ministries of Health to Consultor para el Desarrollo Individual improve surveillance, 2017-08- 2017-05- 2017-05- 2017-06- 2017-10- 2017-12- 2018-04- de investigación cualitativa en IBRD / 85080 Post Consultant Open 10,442.00 2,385.43 Completed 2017-05-15 monitoring, promotion, 29 23 24 01 15 31 15 evaluación de digestos (1) Selection prevention and control of L.O. NCDs, injuries, and risk factors. Component 3: Supporting the National and Provincial AR-MSAL-15120-CS-INDV / Ministries of Health to Consultor para revisiones Individual improve surveillance, 2017-10- 2017-05- 2017-05- 2017-06- 2017-11- 2017-12- 2018-04- sistémicas de rotulados y IBRD / 85080 Post Consultant Open 10,442.00 1,316.10 Completed 2017-05-15 monitoring, promotion, 23 23 23 01 01 31 30 nutrientes de alimentos y Selection prevention and control of tabaco (1) L.O. NCDs, injuries, and risk factors. Component 3: Supporting the National and Provincial AR-MSAL-15122-CS-INDV / Ministries of Health to Consultor para realizar Individual improve surveillance, 2017-08- 2017-05- 2017-05- 2017-06- 2017-09- 2017-12- 2018-03- estudios de regulación de IBRD / 85080 Post Consultant Open 10,442.00 2,741.90 Completed 2017-05-15 monitoring, promotion, 29 22 22 01 01 31 31 productos alimenticios y Selection prevention and control of tabaco (1) L.O. NCDs, injuries, and risk factors. Component 3: Supporting AR-MSAL-15127-CS-INDV / the National and Provincial Consultor especialista en Ministries of Health to Individual actividades de Capacitación improve surveillance, 2017-08- 2017-05- 2017-05- 2017-06- 2017-09- 2017-12- IBRD / 85080 Post Consultant Open 10,442.00 3,399.89 Signed 2017-05-15 para Interoperabilidad y monitoring, promotion, 28 22 22 01 01 31 Selection Gestión de la Historia Clínica prevention and control of Electrónica (1) L.O. NCDs, injuries, and risk factors. Component 3: Supporting the National and Provincial AR-MSAL-15128-CS-INDV / Ministries of Health to Individual Consultor para el desarrollo improve surveillance, 2017-08- 2017-05- 2017-05- 2017-06- 2017-09- 2017-12- 2018-02- IBRD / 85080 Post Consultant Open 20,883.00 3,235.56 Completed 2017-05-15 del Diccionario de monitoring, promotion, 28 22 22 01 01 31 28 Selection establecimientos (2) L.O. prevention and control of NCDs, injuries, and risk factors. Page 7 Component 3: Supporting AR-MSAL-15129-CS-INDV / the National and Provincial Consultor especialista en Ministries of Health to actividades de Capacitación Individual improve surveillance, 2017-08- 2017-05- 2017-05- 2017-06- 2017-09- 2017-12- 2017-10- para Interoperabilidad y IBRD / 85080 Post Consultant Open 31,325.00 3,783.75 Completed 2017-05-15 monitoring, promotion, 29 22 22 01 01 31 31 Gestión de la Historia Clínica Selection prevention and control of Electrónica para el curso NCDs, injuries, and risk virtual (3) L.O. factors. Component 3: Supporting AR-MSAL-15130-CS-INDV / the National and Provincial Consultor Tutor de Ministries of Health to Individual Capacitación para improve surveillance, 2017-08- 2017-05- 2017-05- 2017-06- 2017-09- 2017-12- 2018-02- IBRD / 85080 Post Consultant Open 31,325.00 4,441.95 Completed 2017-05-15 Interoperabilidad y Gestión de monitoring, promotion, 28 22 22 01 01 31 28 Selection la Historia Clínica Electrónica prevention and control of para el curso virtual (3) L.O. NCDs, injuries, and risk factors. Component 3: Supporting AR-MSAL-15131-CS-INDV / the National and Provincial Consultor de Apoyo Ministries of Health to Individual Administrativo para la improve surveillance, 2017-09- 2017-05- 2017-05- 2017-06- 2017-09- 2017-12- 2018-03- IBRD / 85080 Post Consultant Open 7,832.00 1,919.31 Completed 2017-05-15 organización de las monitoring, promotion, 07 22 22 01 15 31 15 Selection actividades de capacitación prevention and control of para el curso virtual (1) L.O. NCDs, injuries, and risk factors. Component 3: Supporting the National and Provincial AR-MSAL-15133-CS-INDV / Ministries of Health to Especialista en Gestión y Individual improve surveillance, Pending 2017-05- 2017-05- 2017-06- 2017-12- Coordinación de estructuras IBRD / 85080 Post Consultant Open 10,442.00 0.00 2017-05-15 monitoring, promotion, Implementation 22 22 01 31 de apoyo a las Provincias (1) Selection prevention and control of L.O. NCDs, injuries, and risk factors. Component 3: Supporting the National and Provincial AR-MSAL-15688-CS-INDV / Ministries of Health to Individual Responsable de la Unidad de improve surveillance, 2017-05- 2017-05- 2017-05- 2017-06- 2018-01- 2020-12- IBRD / 85080 Post Consultant Open 93,903.00 6,862.76 Signed 2017-05-19 Asistencia Administrativa (1) monitoring, promotion, 09 22 22 01 01 31 Selection LS prevention and control of NCDs, injuries, and risk factors. Component 3: Supporting the National and Provincial Ministries of Health to AR-MSAL-15689-CS-INDV / Individual improve surveillance, 2017-05- 2017-05- 2017-05- 2017-06- 2018-04- 2020-12- Consultor Administrativo (3) IBRD / 85080 Post Consultant Open 186,449.00 12,097.01 Signed 2017-05-19 monitoring, promotion, 09 22 22 01 01 31 LS Selection prevention and control of NCDs, injuries, and risk factors. Component 3: Supporting the National and Provincial Ministries of Health to Individual AR-MSAL-15691-CS-INDV / improve surveillance, 2017-05- 2017-05- 2017-05- 2017-05- 2018-05- 2020-12- IBRD / 85080 Post Consultant Open 62,150.00 1,316.52 Signed 2017-05-19 Soporte Informático (1) LS monitoring, promotion, 09 19 19 29 01 31 Selection prevention and control of NCDs, injuries, and risk factors. Component 3: Supporting the National and Provincial AR-MSAL-15696-CS-INDV / Ministries of Health to Individual Consultor de Gestión de las improve surveillance, 2017-05- 2017-05- 2017-05- 2017-06- 2017-12- 2020-12- IBRD / 85080 Post Consultant Open 62,150.00 720.94 Terminated 2017-05-19 comunicaciones internas y monitoring, promotion, 09 22 22 01 01 31 Selection externas (1) LS prevention and control of NCDs, injuries, and risk factors. Component 3: Supporting the National and Provincial AR-MSAL-15697-CS-INDV / Ministries of Health to Individual Responsable de la Unidad de improve surveillance, 2017-05- 2017-05- 2017-05- 2017-06- 2018-01- 2020-12- IBRD / 85080 Post Consultant Open 93,903.00 3,431.38 Terminated 2017-05-19 Apoyo Operativo a las monitoring, promotion, 09 22 22 01 01 31 Selection Provincias (1) LS prevention and control of NCDs, injuries, and risk factors. Component 3: Supporting the National and Provincial Ministries of Health to AR-MSAL-15698-CS-INDV / Individual improve surveillance, 2016-06- 2017-05- 2017-05- 2017-06- 2018-05- 2020-12- 2018-06- Coordinadores Regionales (5) IBRD / 85080 Post Consultant Open 418,836.00 10,581.22 Signed 2017-05-19 monitoring, promotion, 08 22 22 01 01 31 30 LS Selection prevention and control of NCDs, injuries, and risk factors. Component 3: Supporting the National and Provincial Ministries of Health to Individual AR-MSAL-15699-CS-INDV / improve surveillance, 2017-05- 2017-05- 2017-05- 2017-06- 2017-09- 2020-12- IBRD / 85080 Post Consultant Open 372,898.00 1,919.31 Signed 2017-05-19 Staff de Apoyo Regional (6) LS monitoring, promotion, 09 22 22 01 15 31 Selection prevention and control of NCDs, injuries, and risk factors. Component 3: Supporting the National and Provincial Ministries of Health to AR-MSAL-15706-CS-INDV / Individual improve surveillance, 2017-05- 2017-05- 2017-05- 2017-05- 2017-06- 2017-06- 2020-12- Coordinadores Unidad de IBRD / 85080 Post Consultant Open 167,534.00 5,609.23 Terminated 2017-05-19 monitoring, promotion, 09 22 21 22 01 15 31 Monitoreo y Evaluación (2) LS Selection prevention and control of NCDs, injuries, and risk factors. Component 3: Supporting the National and Provincial AR-MSAL-15710-CS-INDV / Ministries of Health to Individual Especialista en Planificación improve surveillance, 2016-06- 2017-05- 2017-05- 2017-06- 2018-07- 2020-12- 2018-06- IBRD / 85080 Post Consultant Open 167,534.00 21,112.33 Signed 2017-05-19 operativa y Control de monitoring, promotion, 08 22 22 01 01 31 30 Selection Gestión (2) LS prevention and control of NCDs, injuries, and risk factors. Component 3: Supporting the National and Provincial Ministries of Health to AR-MSAL-15712-CS-INDV / Individual improve surveillance, 2017-05- 2017-05- 2017-05- 2017-06- 2017-09- 2020-12- Analista de Planificación y IBRD / 85080 Post Consultant Open 124,299.00 2,193.50 Signed 2017-05-19 monitoring, promotion, 09 22 22 01 01 31 Seguimiento Operativo (2) LS Selection prevention and control of NCDs, injuries, and risk factors. Component 3: Supporting the National and Provincial AR-MSAL-15714-CS-INDV / Ministries of Health to Coordinación del Staff de Individual improve surveillance, 2017-05- 2017-05- 2017-12- 2017-05- 2017-06- 2018-02- 2020-12- Apoyo a la Unidad de IBRD / 85080 Post Consultant Open 83,767.00 5,100.24 Signed 2017-05-19 monitoring, promotion, 09 22 20 22 01 01 31 Relaciones con las Provincias Selection prevention and control of (1) LS NCDs, injuries, and risk factors. Component 3: Supporting the National and Provincial AR-MSAL-15722-CS-INDV / Ministries of Health to Individual Técnico de Apoyo al Área de improve surveillance, 2017-05- 2017-05- 2017-05- 2017-06- 2017-08- 2020-12- IBRD / 85080 Post Consultant Open 83,767.00 3,427.37 Signed 2017-05-19 Reorientación de los Servicios monitoring, promotion, 09 22 22 01 01 31 Selection de Salud (Diabetes) (1) LS prevention and control of NCDs, injuries, and risk factors. Page 8 Component 3: Supporting the National and Provincial AR-MSAL-15729-CS-INDV / Ministries of Health to Técnico de Apoyo al Área de Individual improve surveillance, 2017-05- 2017-05- 2017-05- 2017-06- 2017-08- 2020-12- Reorientación de los Servicios IBRD / 85080 Post Consultant Open 83,767.00 2,570.53 Signed 2017-05-19 monitoring, promotion, 09 22 22 01 01 31 de Salud (Cardiovascular) (1) Selection prevention and control of LS NCDs, injuries, and risk factors. Component 3: Supporting the National and Provincial AR-MSAL-15732-CS-INDV / Ministries of Health to Individual Técnico de Apoyo al Área de improve surveillance, 2017-05- 2017-05- 2017-05- 2017-06- 2017-06- 2020-12- 2018-06- IBRD / 85080 Post Consultant Open 83,767.00 5,949.81 Completed 2017-05-19 Promoción de la salud y monitoring, promotion, 09 22 22 01 01 31 30 Selection Alimentación Saludable (1) LS prevention and control of NCDs, injuries, and risk factors. Component 3: Supporting the National and Provincial AR-MSAL-15737-CS-INDV / Ministries of Health to Individual Técnico de Apoyo al Área de improve surveillance, 2017-05- 2017-05- 2017-05- 2017-06- 2017-12- 2020-12- IBRD / 85080 Post Consultant Open 83,767.00 822.57 Signed 2017-05-19 promoción de la salud monitoring, promotion, 09 22 22 01 01 31 Selection (Equipo Económico) (1) LS prevention and control of NCDs, injuries, and risk factors. Component 3: Supporting the National and Provincial AR-MSAL-15740-CS-INDV / Ministries of Health to Técnico de Apoyo al Área de Individual improve surveillance, 2017-05- 2017-05- 2017-05- 2017-06- 2017-08- 2020-12- Vigilancia epidemiológica de IBRD / 85080 Post Consultant Open 124,299.00 5,369.84 Signed 2017-05-19 monitoring, promotion, 09 22 22 01 15 31 enfermedades no Selection prevention and control of transmisibles (2) LS NCDs, injuries, and risk factors. Component 3: Supporting the National and Provincial AR-MSAL-15746-CS-INDV / Ministries of Health to Staff Técnico de la Unidad de Individual improve surveillance, 2017-05- 2017-05- 2017-05- 2017-06- 2018-02- 2020-12- interoperabilidad y gestión de IBRD / 85080 Post Consultant Open 124,299.00 5,696.05 Signed 2017-05-19 monitoring, promotion, 09 22 22 01 15 31 la historia clínica electrónica Selection prevention and control of (2) LS NCDs, injuries, and risk factors. Component 3: Supporting the National and Provincial Ministries of Health to AR-MSAL-16719-CS-INDV / Individual improve surveillance, 2017-05- 2017-06- 2017-06- 2017-06- 2017-08- 2017-12- Staff Técnico de Auditoría (1) IBRD / 85080 Post Consultant Open 83,767.00 3,975.75 Signed 2017-06-01 monitoring, promotion, 09 04 04 14 01 31 LS Selection prevention and control of NCDs, injuries, and risk factors. Component 3: Supporting the National and Provincial AR-MSAL-15733-CS-INDV / Ministries of Health to Individual Staff Técnico de Apoyo al improve surveillance, 2016-06- 2017-05- 2016-05- 2017-05- 2017-06- 2017-07- 2020-12- 2018-06- IBRD / 85080 Post Consultant Open 186,449.00 13,284.53 Signed 2017-05-19 Área de Promoción de la monitoring, promotion, 08 22 29 22 01 01 31 30 Selection salud (3) LS prevention and control of NCDs, injuries, and risk factors. Component 3: Supporting the National and Provincial AR-MSAL-15735-CS-INDV / Ministries of Health to Individual Staff Técnico de Apoyo al improve surveillance, 2017-05- 2017-05- 2017-05- 2017-06- 2017-06- 2020-12- 2018-06- IBRD / 85080 Post Consultant Open 124,299.00 4,126.77 Completed 2017-05-19 Área de Promoción de la monitoring, promotion, 09 22 22 01 01 31 30 Selection Salud (sector legal) (2) LS prevention and control of NCDs, injuries, and risk factors. Component 3: Supporting AR-NA-39-CI-3CV / the National and Provincial Contratación individual Ministries of Health to Individual posición 'Staff de Apoyo improve surveillance, 2017-05- 2017-05- 2016-05- 2017-08- 2020-12- 2018-06- IBRD / 85080 Post Consultant Limited 350,000.00 20,961.91 Signed 2017-08-29 Técnico a la Unidad de monitoring, promotion, 09 24 01 01 31 30 Selection Relaciones con las Provincias' prevention and control of (6 consultores) NCDs, injuries, and risk factors. Component 3: Supporting AR-NA-37-CI-3CV / the National and Provincial Contratación individual Ministries of Health to Individual posición : Responsable de la improve surveillance, 2018-03- 2017-09- 2017-09- 2017-09- 2018-04- 2020-12- IBRD / 85080 Post Consultant Limited 91,024.00 2,550.12 Signed 2017-09-05 Unidad de interoperabilidad y monitoring, promotion, 06 05 05 05 15 31 Selection gestión de la historia clínica prevention and control of electrónica (1 Consultor) LS NCDs, injuries, and risk factors. AR-MSAL-27901-CS-INDV / Consultor Individual - Component 3: Supporting Investigador del equipo the National and Provincial elaborador de la guía de Ministries of Health to Individual práctica clínica de improve surveillance, 2017-11- 2017-09- 2017-09- 2017-09- 2017-11- 2019-03- IBRD / 85080 Post Consultant Open 19,362.41 884.83 Signed 2017-09-15 Hipertensión arterial y monitoring, promotion, 10 26 27 29 15 31 Selection prevención de las prevention and control of enfermedades NCDs, injuries, and risk cardiovasculares (1 factors. Consultor) LO Component 3: Supporting AR-MSAL-27913-CS-INDV / the National and Provincial Consultor individual - Ministries of Health to Individual Investigador del equipo improve surveillance, 2017-10- 2017-09- 2017-09- 2017-09- 2017-11- 2019-05- IBRD / 85080 Post Consultant Open 21,514.00 913.01 Signed 2017-09-15 elaborador de guías de monitoring, promotion, 09 26 27 29 15 31 Selection alimentarias para la población prevention and control of infantil (1 Consultor) LO NCDs, injuries, and risk factors. Component 3: Supporting AR-MSAL-27916-CS-INDV / the National and Provincial Consultor individual - Ministries of Health to Investigador para el Individual improve surveillance, 2018-01- 2017-09- 2017-09- 2017-09- 2018-02- 2019-05- desarrollo de contenidos para IBRD / 85080 Post Consultant Open 23,259.00 2,962.18 Signed 2017-09-15 monitoring, promotion, 16 26 27 29 15 31 curso virtual sobre Selection prevention and control of alimentación saludable (1 NCDs, injuries, and risk Consultor) LO factors. Component 3: Supporting AR-MSAL-27918-CS-INDV / the National and Provincial Consultor Individual - Ministries of Health to Individual Especialista en diseño de improve surveillance, 2017-11- 2017-09- 2017-09- 2017-09- 2018-01- 2018-03- 2018-06- IBRD / 85080 Post Consultant Open 6,978.00 3,655.67 Completed 2017-09-15 protocolo para llamadas y monitoring, promotion, 06 26 27 29 01 31 30 Selection respuestas - Cesación prevention and control of Tabáquica (1 Consultor) LO NCDs, injuries, and risk factors. AR-MSAL-27919-CS-INDV / Component 3: Supporting Consultor Individual - the National and Provincial Especialista en análisis y Ministries of Health to desarrollo de software para Individual improve surveillance, 2017-11- 2017-09- 2017-09- 2017-09- 2017-11- 2018-03- 2018-05- estrategias de información y IBRD / 85080 Post Consultant Open 13,956.00 1,913.22 Completed 2017-09-15 monitoring, promotion, 06 26 27 29 15 31 15 comunicación del "SUATS" Selection prevention and control of (Sistema único de atención NCDs, injuries, and risk telefónica en Salud) 2 factors. Consultores - LO AR-NA-31-CI-3CV / Contratación individual Individual 2017-01- 2020-12- posición 'Especialista en / Post Consultant Limited 115,774.00 0.00 Canceled 01 31 salvaguarda indígena' (2 Selection consultores) AR-NA-30-CI-3CV / Contratación individual Individual 2017-01- 2020-12- posición 'Especialista en / Post Consultant Limited 115,774.00 0.00 Canceled 01 31 Salvaguarda Ambiental' (2 Selection consultores) Page 9 AR-NA-41-CI-3CV / Contratación individual Individual 2016-05- 2020-12- posición 'Staff Técnico de / Post Consultant Limited 337,673.00 0.00 Canceled 01 31 Apoyo al Área de Promoción Selection de la Salud' (5 consultores) Component 3: Supporting AR-MSAL-28120-CS-INDV / the National and Provincial Consultor Individual - Ministries of Health to Especialista para la Individual improve surveillance, 2017-12- 2017-10- 2017-10- 2017-11- 2018-01- 2018-11- investigación de campo para IBRD / 85080 Post Consultant Open 21,631.00 2,988.42 Signed 2017-09-28 monitoring, promotion, 26 09 10 15 01 30 el rotulado y nutrientes de Selection prevention and control of alimentos y tabaco(1 NCDs, injuries, and risk Consultor) L.O factors. AR-MSAL-28885-CS-INDV / Component 3: Supporting Contratación individual the National and Provincial posición - Consultor Experto Ministries of Health to para la redacción de un Individual improve surveillance, 2017-11- 2017-10- 2017-10- 2017-11- 2017-11- 2018-04- 2018-05- manual de Buenas Prácticas y IBRD / 85080 Post Consultant Open 7,745.00 1,105.84 Completed 2017-10-01 monitoring, promotion, 13 12 13 01 15 30 15 Procedimientos de gestión Selection prevention and control of para RAEE (Residuos de NCDs, injuries, and risk Aparatos Eléctricos y factors. Electrónicos) 1 consultor L.O AR-MSAL-33613-CS-INDV / Component 3: Supporting Contratación individual the National and Provincial posición : "Asistencia Técnica Ministries of Health to para el Desarrollo de Individual improve surveillance, 2017-11- 2017-10- 2017-10- 2017-11- 2017-11- 2019-10- Herramientas Informáticas IBRD / 85080 Post Consultant Open 75,730.00 1,100.09 Signed 2017-10-24 monitoring, promotion, 06 29 30 01 15 30 para la adopción de Selection prevention and control of estándares de NCDs, injuries, and risk interoperabilidad" (2 factors. consultores) Component 3: Supporting the National and Provincial AR-MSAL-14574-CS-INDV / Ministries of Health to Individual Consultor para el análisis del improve surveillance, 2018-02- 2018-02- 2018-03- 2018-09- IBRD / 85080 Post Consultant Open 8,619.00 0.00 Canceled 2018-02-15 Código Alimentario Argentino monitoring, promotion, 26 27 01 30 Selection (1 posición) L.O. prevention and control of NCDs, injuries, and risk factors. Component 3: Supporting the National and Provincial AR-MSAL-15121-CS-INDV / Ministries of Health to Consultor para la Individual improve surveillance, 2018-02- 2018-02- 2018-03- 2018-09- actualización del Estudio de IBRD / 85080 Post Consultant Open 8,619.00 0.00 Canceled 2018-02-15 monitoring, promotion, 24 25 01 30 Carga de Enfermedad de ENT Selection prevention and control of (1) L.O. NCDs, injuries, and risk factors. Component 3: Supporting the National and Provincial AR-MSAL-15123-CS-INDV / Ministries of Health to Consultor para elaborar el Individual improve surveillance, 2018-03- 2018-02- 2018-02- 2018-03- 2018-04- 2018-09- 2018-09- protocolo e instrumentos de IBRD / 85080 Post Consultant Open 8,619.00 2,271.26 Completed 2018-02-15 monitoring, promotion, 12 24 25 01 01 30 30 la encuesta de consumo de Selection prevention and control of alimentos (1) L.O. NCDs, injuries, and risk factors. Component 3: Supporting AR-MSAL-44093-CS-INDV / the National and Provincial Consultoría individual - Ministries of Health to Individual Especialista en Diseño improve surveillance, 2018-03- 2018-02- 2018-02- 2018-03- 2018-04- 2018-08- 2018-09- IBRD / 85080 Post Consultant Open 11,920.00 2,965.71 Completed 2018-02-20 Muestral para la Encuesta monitoring, promotion, 01 26 27 01 01 31 30 Selection Nacional de Nutrición y Salud prevention and control of - ENNYS. (1 Consultor L.O) NCDs, injuries, and risk factors. Component 3: Supporting AR-MSAL-37233-CS-INDV / the National and Provincial Contratación individual Ministries of Health to posición : Especialista para el Individual improve surveillance, 2018-04- 2018-02- 2018-02- 2018-03- 2018-05- 2019-02- Desarrollo y Fortalecimiento IBRD / 85080 Post Consultant Open 23,840.00 7,622.55 Signed 2018-02-22 monitoring, promotion, 23 26 27 01 15 28 de políticas y programas de Selection prevention and control of Actividades Físicas (1 NCDs, injuries, and risk consultor) - L.O factors. Component 3: Supporting AR-MSAL-46541-CS-INDV / the National and Provincial Consultorio Individual - Ministries of Health to Individual Consultores para el improve surveillance, 2018-03- 2018-03- 2018-04- 2019-04- IBRD / 85080 Post Consultant Open 68,436.00 0.00 Canceled 2018-03-25 Desarrollo de Software para monitoring, promotion, 29 30 01 01 Selection encuestas Poblacionales - L.O prevention and control of (3 Puestos) NCDs, injuries, and risk factors. Component 3: Supporting the National and Provincial AR-MSAL-55403-CS-INDV / Ministries of Health to Individual Consultoria individual : Apoyo improve surveillance, 2018-03- 2018-04- 2018-04- 2018-05- 2018-05- 2020-12- IBRD / 85080 Post Consultant Open 89,730.00 1,136.06 Terminated 2018-04-11 Administrativo de Mesa de monitoring, promotion, 06 22 24 01 01 31 Selection Entrada L.S (2 puestos) prevention and control of NCDs, injuries, and risk factors. Component 3: Supporting AR-MSAL-55406-CS-INDV / the National and Provincial Consultoria Individual Puesto: Ministries of Health to Staff Técnico de Apoyo al Individual improve surveillance, 2018-03- 2018-04- 2018-05- 2018-04- 2018-05- 2018-06- 2020-12- Área de Servicios de Salud IBRD / 85080 Post Consultant Open 60,445.00 9,075.45 Signed 2018-04-13 monitoring, promotion, 06 24 15 26 01 01 31 (programa de prevención Selection prevention and control of cardiovascular) - L.S (1 NCDs, injuries, and risk Puesto) factors. Component 3: Supporting the National and Provincial Ministries of Health to AR-MSAL-15690-CS-INDV / Individual improve surveillance, 2016-06- 2018-05- 2018-05- 2018-06- 2018-06- 2020-12- Consultor de Apoyo IBRD / 85080 Post Consultant Open 135,737.00 17,073.75 Signed 2018-05-10 monitoring, promotion, 08 24 27 01 01 31 Administrativo (6) LS Selection prevention and control of NCDs, injuries, and risk factors. Component 3: Supporting the National and Provincial AR-NA-42-CI-3CV / Ministries of Health to Contratación individual Individual improve surveillance, 2017-05- 2018-05- 2018-05- 2018-06- 2018-02- 2020-12- posición 'Staff Técnico de IBRD / 85080 Post Consultant Limited 26,019.00 3,046.39 Signed 2018-05-10 monitoring, promotion, 09 24 27 01 01 31 Apoyo al Área de Selection prevention and control of Comunicación' (1 consultor) NCDs, injuries, and risk factors. Component 3: Supporting AR-NA-43-CI-3CV / the National and Provincial Contratación individual Ministries of Health to posición 'Staff Técnico de Individual improve surveillance, 2017-05- 2018-05- 2018-05- 2018-06- 2017-08- 2020-12- Apoyo al Área de Vigilancia IBRD / 85080 Post Consultant Limited 104,077.19 8,588.80 Signed 2018-05-10 monitoring, promotion, 09 24 27 01 15 31 epidemiológica de Selection prevention and control of Enfermedades No NCDs, injuries, and risk Transmisibles (4) LS factors. AR-NA-38-CI-3CV / Component 3: Supporting Contratación individual the National and Provincial posición 'Técnico de apoyo a Ministries of Health to la Unidad de Gestión de Individual improve surveillance, 2016-06- 2018-05- 2018-05- 2018-06- 2018-06- 2020-12- 2018-03- Registros clínicos IBRD / 85080 Post Consultant Limited 280,453.19 20,423.72 Signed 2018-05-10 monitoring, promotion, 08 23 26 01 01 31 31 electrónicos, Historia Clínica Selection prevention and control of Electrónica e NCDs, injuries, and risk Interoperabilidad de sistemas factors. de información" (8) L.S Page 10 AR-MSAL-87670-CS-INDV / Component 3: Supporting Consultoría Individual - the National and Provincial Equipo de Especialistas de Ministries of Health to Individual Planificación y Organización improve surveillance, Pending 2018-12- 2018-12- 2019-01- 2020-12- IBRD / 85080 Post Consultant Open 75,407.00 0.00 2018-12-13 de Estrategias para el monitoring, promotion, Implementation 26 27 01 31 Selection fortalecimiento del Proyecto a prevention and control of Nivel Provincial (Locación de NCDs, injuries, and risk Obra) (4). factors. AR-MSAL-87674-CS-INDV / Component 3: Supporting Consultoría Individual - the National and Provincial Equipo de Especialistas de Ministries of Health to Individual Actividades de promoción de improve surveillance, Pending 2018-12- 2018-12- 2019-01- 2020-12- IBRD / 85080 Post Consultant Open 235,697.00 0.00 2018-12-14 la Salud para el monitoring, promotion, Implementation 26 28 01 31 Selection Fortalecimiento del Proyecto prevention and control of (Locación de Obra) (10 NCDs, injuries, and risk Consultores) factors. Component 3: Supporting the National and Provincial Ministries of Health to AR-MSAL-109088-CS-INDV Individual improve surveillance, 2018-03- 2019-04- 2019-04- 2019-04- 2018-06- 2021-01- 2019-12- / Coordinadores Unidad de IBRD / 85080 Post Consultant Open 25,483.00 6,524.78 Completed 2019-04-11 monitoring, promotion, 06 14 15 17 01 07 31 Monitoreo y Evaluación (1) LS Selection prevention and control of NCDs, injuries, and risk factors. Component 3: Supporting the National and Provincial AR-MSAL-114294-CS-INDV Ministries of Health to / Técnico de Apoyo al Área de Individual improve surveillance, 2018-03- 2019-09- 2017-05- 2019-09- 2018-12- 2019-09- 2019-02- 2020-12- Promoción de la Salud y IBRD / 85080 Post Consultant Open 58,265.00 9,637.37 Signed 2019-09-01 monitoring, promotion, 06 08 24 09 26 11 01 31 Alimentación Saludable (1) - Selection prevention and control of L.S NCDs, injuries, and risk factors. Component 3: Supporting the National and Provincial AR-MSAL-127081-CS-INDV Ministries of Health to Individual / Consultor de apoyo improve surveillance, 2018-03- 2019-08- 2018-05- 2019-08- 2019-08- 2019-09- 2019-09- 2020-12- IBRD / 85080 Post Consultant Open 15,005.00 2,802.01 Signed 2019-08-28 administrativo ( Cantidad 1) - monitoring, promotion, 06 30 15 30 14 01 01 31 Selection L.S prevention and control of NCDs, injuries, and risk factors. AR-MSAL-85680-CS-INDV / Component 2: Protecting Individual Consultoría Individual vulnerable population groups Pending 2019-12- 2019-12- 2019-12- 2021-12- IBRD / 85080 Post Consultant Limited 36,631.00 0.00 2019-12-09 "Coordinador General" (1 against prevalent NCD risk Implementation 10 11 15 31 Selection consultor) factors. Component 3: Supporting the National and Provincial AR-MSAL-148628-CS-INDV Ministries of Health to / Soporte Operativo de la Individual improve surveillance, Pending 2019-12- 2019-12- 2020-01- 2021-12- Coordinación General - IBRD / 85080 Post Consultant Open 29,308.00 0.00 2019-12-15 monitoring, promotion, Implementation 18 19 01 31 Cantidad 1 - Locación de Selection prevention and control of Servicios NCDs, injuries, and risk factors. Component 3: Supporting the National and Provincial AR-MSAL-148637-CS-INDV Ministries of Health to / Consultor de Apoyo a la Individual improve surveillance, Under 2019-11- 2019-12- 2019-12- 2020-01- 2021-12- coordinación General - IBRD / 85080 Post Consultant Direct 21,091.00 0.00 2019-12-16 monitoring, promotion, Implementation 22 22 26 01 31 Cantidad 1 consultor - Selection prevention and control of Locación de Servicios NCDs, injuries, and risk factors. Component 3: Supporting the National and Provincial AR-MSAL-148643-CS-INDV Ministries of Health to / Coordinador del Área de Individual improve surveillance, Pending 2019-12- 2019-12- 2020-01- 2021-12- Apoyo a las Provincias - IBRD / 85080 Post Consultant Open 29,308.00 0.00 2019-12-16 monitoring, promotion, Implementation 19 20 01 31 Cantidad 1 consultor - Selection prevention and control of Locación de Servicios NCDs, injuries, and risk factors. Component 3: Supporting the National and Provincial AR-MSAL-148646-CS-INDV Ministries of Health to Individual / Referentes Regionales - improve surveillance, Pending 2019-12- 2019-12- 2020-01- 2021-12- IBRD / 85080 Post Consultant Open 130,355.00 0.00 2019-12-16 Cantidad 5 consultores - monitoring, promotion, Implementation 19 20 01 31 Selection Locación de Servicios prevention and control of NCDs, injuries, and risk factors. Component 3: Supporting the National and Provincial AR-MSAL-148647-CS-INDV Ministries of Health to Individual / Staff de Apoyo Regional - improve surveillance, Pending 2019-12- 2019-12- 2020-01- 2021-12- IBRD / 85080 Post Consultant Open 210,911.00 0.00 2019-12-16 Cantidad 10 consultores - monitoring, promotion, Implementation 19 20 01 31 Selection Locación de Servicios prevention and control of NCDs, injuries, and risk factors. Component 3: Supporting the National and Provincial Ministries of Health to AR-MSAL-15700-CS-INDV / Individual improve surveillance, Pending 2019-12- 2019-12- 2020-01- 2021-12- Consultor Apoyo General (1) IBRD / 85080 Post Consultant Open 18,089.00 0.00 2019-12-16 monitoring, promotion, Implementation 17 17 01 31 LS Selection prevention and control of NCDs, injuries, and risk factors. Component 3: Supporting AR-MSAL-148790-CS-INDV the National and Provincial / Coordinador de Ministries of Health to Individual Planificación Operativa y improve surveillance, 2019-11- 2019-12- 2019-12- 2019-12- 2019-12- 2020-01- 2020-01- 2021-12- IBRD / 85080 Post Consultant Open 29,308.00 2,084.00 Signed 2019-12-16 Monitoreo - Cantidad 1 monitoring, promotion, 22 19 16 24 21 01 01 31 Selection consultor - Locación de prevention and control of Servicios NCDs, injuries, and risk factors. Component 3: Supporting the National and Provincial AR-MSAL-15708-CS-INDV / Ministries of Health to Analistas de Informes e Individual improve surveillance, Under 2019-06- 2019-12- 2019-12- 2020-01- 2021-12- Indicadores - Cantidad 4 IBRD / 85080 Post Consultant Open 84,364.34 0.00 2019-12-16 monitoring, promotion, Implementation 08 23 28 01 31 consultores - Locación de Selection prevention and control of Servicios NCDs, injuries, and risk factors. Component 3: Supporting the National and Provincial AR-MSAL-148798-CS-INDV Ministries of Health to Individual / Apoyo Técnico - Cantidad 1 improve surveillance, Pending 2019-12- 2019-12- 2020-01- 2021-12- IBRD / 85080 Post Consultant Open 18,088.53 0.00 2019-12-16 consultor - Locación de monitoring, promotion, Implementation 19 23 01 31 Selection Servicios prevention and control of NCDs, injuries, and risk factors. Component 3: Supporting the National and Provincial AR-MSAL-148800-CS-INDV Ministries of Health to / Coordinador del Área de Individual improve surveillance, Pending 2019-12- 2019-12- 2020-01- 2021-12- Administración - Cantidad 1 IBRD / 85080 Post Consultant Open 29,307.82 0.00 2019-12-16 monitoring, promotion, Implementation 19 22 01 31 Consultor - Locación de Selection prevention and control of Servicios NCDs, injuries, and risk factors. Component 3: Supporting AR-MSAL-148803-CS-INDV the National and Provincial / Consultor de Ministries of Health to Individual Contrataciones y improve surveillance, Pending 2019-12- 2019-12- 2020-01- 2021-12- IBRD / 85080 Post Consultant Open 42,182.17 0.00 2019-12-16 Adquisiciones - Cantidad 2 monitoring, promotion, Implementation 21 25 01 31 Selection consultores - Locación de prevention and control of Servicios NCDs, injuries, and risk factors. Page 11 Component 3: Supporting the National and Provincial AR-MSAL-148806-CS-INDV Ministries of Health to Individual / Responsable de Finanzas - improve surveillance, Pending 2019-12- 2019-12- 2020-01- 2021-12- IBRD / 85080 Post Consultant Open 26,070.92 0.00 2019-12-16 Cantidad 1 Consultor - monitoring, promotion, Implementation 25 27 01 31 Selection Locación de Servicios prevention and control of NCDs, injuries, and risk factors. Component 3: Supporting the National and Provincial AR-MSAL-148810-CS-INDV Ministries of Health to / Consultor de Planificación Individual improve surveillance, Pending 2019-12- 2019-12- 2020-01- 2021-12- Presupuestaria - Cantidad 1 IBRD / 85080 Post Consultant Open 21,091.08 0.00 2019-12-16 monitoring, promotion, Implementation 20 26 01 31 consultor - Locación de Selection prevention and control of Servicios NCDs, injuries, and risk factors. Component 3: Supporting the National and Provincial AR-MSAL-148817-CS-INDV Ministries of Health to / Consultor de Cuentas a Individual improve surveillance, Under 2019-11- 2019-12- 2019-12- 2020-01- 2021-12- Pagar - Cantidad 2 IBRD / 85080 Post Consultant Direct 42,182.17 0.00 2019-12-16 monitoring, promotion, Implementation 22 18 20 01 31 consultores - Locación de Selection prevention and control of Servicios NCDs, injuries, and risk factors. Component 3: Supporting the National and Provincial AR-MSAL-148819-CS-INDV Ministries of Health to / Asistente Técnico de Individual improve surveillance, Under 2019-11- 2019-12- 2019-12- 2020-01- 2021-12- Cuentas a Pagar - Cantidad 1 IBRD / 85080 Post Consultant Direct 18,088.53 0.00 2019-12-16 monitoring, promotion, Implementation 22 18 19 01 31 Consultor - Locación de Selection prevention and control of Servicios NCDs, injuries, and risk factors. Component 3: Supporting the National and Provincial AR-MSAL-55397-CS-INDV / Ministries of Health to Coordinadores Unidad de Individual improve surveillance, Pending 2019-12- 2019-12- 2020-01- 2021-12- Asistencia Administrativa - IBRD / 85080 Post Consultant Open 26,070.92 0.00 2019-12-16 monitoring, promotion, Implementation 25 26 01 31 Cantidad 1 consultor - Selection prevention and control of Locación de Servicios NCDs, injuries, and risk factors. Component 3: Supporting AR-MSAL-148827-CS-INDV the National and Provincial / Asistente Técnico de Ministries of Health to Individual Producción de Contenidos e improve surveillance, Pending 2019-12- 2019-12- 2020-01- 2021-12- IBRD / 85080 Post Consultant Open 18,088.53 0.00 2019-12-16 Información - Cantidad 1 monitoring, promotion, Implementation 22 29 01 31 Selection consultor - Locación de prevention and control of Servicios NCDs, injuries, and risk factors. Component 3: Supporting AR-MSAL-148831-CS-INDV the National and Provincial / Coordinador del Área de Ministries of Health to Individual Gestión Clínica y calidad de improve surveillance, Pending 2019-12- 2019-12- 2020-01- 2021-12- IBRD / 85080 Post Consultant Open 29,307.82 0.00 2019-12-16 atención - Cantidad 1 monitoring, promotion, Implementation 22 24 01 31 Selection Consultor - Locación de prevention and control of Servicios NCDs, injuries, and risk factors. Component 3: Supporting the National and Provincial AR-MSAL-148837-CS-INDV Ministries of Health to / Staff Técnico del equipo de Individual improve surveillance, Pending 2019-12- 2019-12- 2020-01- 2021-12- facilitadores provinciales - IBRD / 85080 Post Consultant Open 234,638.00 0.00 2019-12-16 monitoring, promotion, Implementation 23 29 01 31 Cantidad 9 Consultores - Selection prevention and control of Locación de Servicios NCDs, injuries, and risk factors. Component 3: Supporting the National and Provincial AR-MSAL-148853-CS-INDV Ministries of Health to / Consultor Especialista en Individual improve surveillance, Pending 2019-12- 2019-12- 2020-01- 2021-12- Salud Familiar y Comunitaria IBRD / 85080 Post Consultant Open 78,212.77 0.00 2019-12-16 monitoring, promotion, Implementation 22 26 01 31 - Cantidad 3 consultores - Selection prevention and control of Locación de Servicios NCDs, injuries, and risk factors. Component 3: Supporting AR-MSAL-148854-CS-INDV the National and Provincial / Staff de Apoyo Técnico a la Ministries of Health to Individual Unidad de Relaciones con las improve surveillance, Pending 2019-12- 2019-12- 2020-01- 2021-12- IBRD / 85080 Post Consultant Open 19,230.98 0.00 2019-12-16 Provincias - Cantidad de monitoring, promotion, Implementation 21 23 01 31 Selection vacantes 1 - Locación de prevention and control of Servicios NCDs, injuries, and risk factors. Component 3: Supporting the National and Provincial AR-MSAL-148862-CS-INDV Ministries of Health to / Staff Técnico de Apoyo al Individual improve surveillance, Pending 2019-12- 2019-12- 2020-01- 2021-12- Área de Promoción de la IBRD / 85080 Post Consultant Open 19,231.00 0.00 2019-12-16 monitoring, promotion, Implementation 22 26 01 31 Salud - Cantidad 1 consultor Selection prevention and control of - Locacion de Servicios NCDs, injuries, and risk factors. Component 3: Supporting the National and Provincial AR-MSAL-15734-CS-INDV / Ministries of Health to Individual Técnico de Apoyo al Área de improve surveillance, Pending 2019-12- 2019-12- 2020-01- 2021-12- IBRD / 85080 Post Consultant Open 26,071.00 0.00 2019-12-17 Promoción de la salud (sector monitoring, promotion, Implementation 22 26 01 31 Selection legal) (1) LS prevention and control of NCDs, injuries, and risk factors. Component 3: Supporting AR-MSAL-148863-CS-INDV the National and Provincial / Staff Técnico de Apoyo al Ministries of Health to Individual Área de Promoción de la improve surveillance, Pending 2019-12- 2019-12- 2020-01- 2021-12- IBRD / 85080 Post Consultant Open 38,462.00 0.00 2019-12-16 Salud (Sector Legal) - monitoring, promotion, Implementation 27 29 01 31 Selection Cantidad 2 consultores - prevention and control of locación de servicios NCDs, injuries, and risk factors. Component 3: Supporting AR-MSAL-148864-CS-INDV the National and Provincial / Técnico de apoyo a la Ministries of Health to Dirección Nacional de Individual improve surveillance, Pending 2019-12- 2019-12- 2020-01- 2021-12- Sistemas de Información en IBRD / 85080 Post Consultant Open 130,355.00 0.00 2019-12-16 monitoring, promotion, Implementation 22 24 01 31 Salud - Cantidad 5 Selection prevention and control of consultores - Locacion de NCDs, injuries, and risk Servicios factors. Component 3: Supporting the National and Provincial AR-MSAL-55427-CS-INDV / Ministries of Health to Consultoría individual puesto: Individual improve surveillance, Pending 2019-12- 2019-12- 2020-01- 2021-12- Consultor Experto en IBRD / 85080 Post Consultant Open 26,071.00 0.00 2019-12-16 monitoring, promotion, Implementation 27 29 01 31 Asistencia Operativa a Selection prevention and control of Provincias - L.S (1 puesto) NCDs, injuries, and risk factors. Component 3: Supporting AR-MSAL-55428-CS-INDV / the National and Provincial Consultor de Apoyo Ministries of Health to administrativo a la Dirección Individual improve surveillance, Pending 2019-12- 2019-12- 2020-01- 2021-12- Nacional de Sistemas de IBRD / 85080 Post Consultant Open 18,089.00 0.00 2019-12-16 monitoring, promotion, Implementation 27 29 01 31 Información en Salud - 1 Selection prevention and control of consultor - Locacion de NCDs, injuries, and risk Servicios factors. Page 12 Component 3: Supporting the National and Provincial AR-MSAL-135802-CS-INDV Ministries of Health to / Staff Técnico de la Dirección Individual improve surveillance, Pending 2019-12- 2019-12- 2020-01- 2021-12- Nacional de Sistemas de IBRD / 85080 Post Consultant Open 21,091.08 0.00 2019-12-16 monitoring, promotion, Implementation 24 25 21 31 Información en Salud - Selection prevention and control of Cantidad consultor -(L.S) NCDs, injuries, and risk factors. Component 3: Supporting the National and Provincial AR-MSAL-160489-CS-INDV Ministries of Health to / Consultor de Gestión Clínica Individual improve surveillance, Pending 2020-02- 2020-02- 2020-03- 2021-12- y calidad de atención, IBRD / 85080 Post Consultant Open 18,194.80 0.00 2020-02-24 monitoring, promotion, Implementation 27 28 01 31 Cantidad 1 consultor - Selection prevention and control of Locación de Servicios NCDs, injuries, and risk factors. Component 3: Supporting AR-MSAL-160490-CS-INDV the National and Provincial / Asistente Técnico de Ministries of Health to Individual Gestión Clínica y calidad de improve surveillance, Pending 2020-02- 2020-02- 2020-03- 2021-12- IBRD / 85080 Post Consultant Open 15,604.57 0.00 2020-02-24 atención, Cantidad 1 monitoring, promotion, Implementation 27 28 01 31 Selection consultor - Locación de prevention and control of Servicios NCDs, injuries, and risk factors. Component 3: Supporting the National and Provincial AR-MSAL-160491-CS-INDV Ministries of Health to / Consultor de Gestión y Individual improve surveillance, Pending 2020-02- 2020-02- 2020-03- 2021-12- Seguimiento de RRHH, IBRD / 85080 Post Consultant Open 18,194.80 0.00 2020-02-24 monitoring, promotion, Implementation 27 28 01 31 Cantidad 1 consultor - Selection prevention and control of Locación de Servicios NCDs, injuries, and risk factors. Component 3: Supporting the National and Provincial AR-MSAL-160493-CS-INDV Ministries of Health to / Asistente Técnico de Individual improve surveillance, Under 2019-11- 2020-02- 2020-02- 2020-03- 2021-12- Gestión y Seguimiento de IBRD / 85080 Post Consultant Open 15,604.57 0.00 2020-02-24 monitoring, promotion, Implementation 22 27 28 01 31 RRHH, Cantidad 1 consultor - Selection prevention and control of Locación de Servicios NCDs, injuries, and risk factors. Component 3: Supporting AR-MSAL-160898-CS-INDV the National and Provincial / Asistente Técnico para Ministries of Health to Individual Contrataciones y improve surveillance, Pending 2020-02- 2020-02- 2020-03- 2021-12- IBRD / 85080 Post Consultant Open 15,604.57 0.00 2020-02-24 Adquisiciones, Cantidad 1 monitoring, promotion, Implementation 27 28 01 31 Selection consultor - Locación de prevention and control of Servici NCDs, injuries, and risk factors. Component 3: Supporting the National and Provincial AR-MSAL-165595-CS-INDV Ministries of Health to / Responsable de Individual improve surveillance, Pending 2020-03- 2020-03- 2020-04- 2021-12- Contrataciones y IBRD / 85080 Post Consultant Open 20,974.00 0.00 2020-03-23 monitoring, promotion, Implementation 26 28 01 31 Adquisiciones de Bienes y Selection prevention and control of Servicios (L.S - 1 posición) NCDs, injuries, and risk factors. Component 3: Supporting the National and Provincial AR-MSAL-165596-CS-INDV Ministries of Health to Individual / Consultor Legal para el Área improve surveillance, Pending 2020-03- 2020-03- 2020-04- 2021-12- IBRD / 85080 Post Consultant Open 16,967.00 0.00 2020-03-23 Técnico-Jurídica (L.S - 1 monitoring, promotion, Implementation 28 29 01 31 Selection posición) prevention and control of NCDs, injuries, and risk factors. Component 3: Supporting the National and Provincial AR-MSAL-165597-CS-INDV Ministries of Health to / Staff Técnico de la Dirección Individual improve surveillance, Pending 2020-03- 2020-03- 2020-04- 2021-12- Nacional de Sistemas de IBRD / 85080 Post Consultant Open 16,967.00 0.00 2020-03-23 monitoring, promotion, Implementation 29 30 01 31 Información en Salud (L.S - 1 Selection prevention and control of posición) NCDs, injuries, and risk factors. Component 3: Supporting the National and Provincial AR-MSAL-181897-CS-INDV Ministries of Health to / Coordinador de Individual improve surveillance, Pending 2020-07- 2020-07- 2020-08- 2021-12- Planificación Operativa y IBRD / 85080 Post Consultant Open 16,994.62 0.00 2020-07-20 monitoring, promotion, Implementation 26 29 01 31 Monitoreo - Locación de Selection prevention and control of Servicios (1 consultor) NCDs, injuries, and risk factors. Component 3: Supporting the National and Provincial AR-MSAL-187039-CS-INDV Ministries of Health to Individual / Responsable de improve surveillance, Pending 2020-08- 2020-08- 2020-09- 2021-12- IBRD / 85080 Post Consultant Open 35,757.35 0.00 2020-08-15 Planificación Operativa y monitoring, promotion, Implementation 18 19 01 31 Selection Monitoreo - (2 consultores) prevention and control of NCDs, injuries, and risk factors. Component 3: Supporting the National and Provincial AR-MSAL-187754-CS-INDV Ministries of Health to Individual / Staff Técnico del equipo de improve surveillance, Pending 2020-08- 2020-08- 2020-09- 2021-12- IBRD / 85080 Post Consultant Open 40,865.53 0.00 2020-08-20 facilitadores provinciales (3 monitoring, promotion, Implementation 27 28 01 31 Selection consultores) prevention and control of NCDs, injuries, and risk factors. Component 3: Supporting the National and Provincial AR-MSAL-209740-CS-INDV Ministries of Health to Individual / Consultor Legal para el Área improve surveillance, Pending 2020-12- 2020-12- 2021-01- 2021-12- IBRD / 85080 Post Consultant Open 9,218.63 0.00 2020-12-21 Técnico-Jurídica - Locación monitoring, promotion, Implementation 25 26 01 31 Selection de Servicios - (1 posición) prevention and control of NCDs, injuries, and risk factors. Component 3: Supporting AR-MSAL-209763-CS-INDV the National and Provincial / Coordinación del Staff de Ministries of Health to Individual Apoyo a la Unidad de improve surveillance, Pending 2020-12- 2020-12- 2021-01- 2021-12- IBRD / 85080 Post Consultant Open 11,395.25 0.00 2020-12-20 Relaciones con las Provincias monitoring, promotion, Implementation 24 25 01 31 Selection - Locacion de Servicios - 1 prevention and control of vacante NCDs, injuries, and risk factors. Component 3: Supporting AR-MSAL-209776-CS-INDV the National and Provincial / Técnico de Apoyo al Área de Ministries of Health to Individual Reorientación de los Servicios improve surveillance, Pending 2020-12- 2020-12- 2021-01- 2021-12- IBRD / 85080 Post Consultant Open 11,395.25 0.00 2020-12-21 de Salud (Diabetes) - monitoring, promotion, Implementation 25 29 01 31 Selection Locacion de Servicios - 1 prevention and control of Posición NCDs, injuries, and risk factors. Component 3: Supporting AR-MSAL-209781-CS-INDV the National and Provincial / Técnico de Apoyo al Área de Ministries of Health to Individual Reorientación de los Servicios improve surveillance, Pending 2020-12- 2020-12- 2021-01- 2021-12- IBRD / 85080 Post Consultant Open 11,395.25 0.00 2020-12-22 de Salud (Cardiovascular) - monitoring, promotion, Implementation 26 27 01 31 Selection "Locacion de Servicios" - 1 prevention and control of posición NCDs, injuries, and risk factors. Page 13 Component 3: Supporting the National and Provincial AR-MSAL-209789-CS-INDV Ministries of Health to / Staff Técnico de Apoyo al Individual improve surveillance, Pending 2020-12- 2020-12- 2021-01- 2021-12- Área de Reorientación de los IBRD / 85080 Post Consultant Open 25,216.80 0.00 2020-12-23 monitoring, promotion, Implementation 26 27 01 31 Servicios de Salud - Locación Selection prevention and control of de Servicios - "3 Posiciones" NCDs, injuries, and risk factors. Component 3: Supporting AR-MSAL-209793-CS-INDV the National and Provincial / Staff Técnico de Apoyo al Ministries of Health to Individual Área de Servicios de Salud improve surveillance, Pending 2020-12- 2020-12- 2021-01- 2021-12- IBRD / 85080 Post Consultant Open 11,395.25 0.00 2020-12-21 (programa de prevención monitoring, promotion, Implementation 25 26 01 31 Selection cardiovascular) - Locación de prevention and control of Servicios - 1 posición NCDs, injuries, and risk factors. Component 3: Supporting the National and Provincial AR-MSAL-209802-CS-INDV Ministries of Health to / Staff Técnico de Apoyo al Individual improve surveillance, Pending 2020-12- 2020-12- 2021-01- 2021-12- Área de Promoción de la IBRD / 85080 Post Consultant Open 16,811.20 0.00 2020-12-21 monitoring, promotion, Implementation 24 26 01 31 Salud - Locación de Servicios Selection prevention and control of - 2 posiciones NCDs, injuries, and risk factors. Component 3: Supporting the National and Provincial AR-MSAL-209806-CS-INDV Ministries of Health to / Técnico de Apoyo al Área de Individual improve surveillance, Pending 2020-12- 2020-12- 2021-01- 2021-12- Vigilancia Epidemiológica de IBRD / 85080 Post Consultant Open 22,790.51 0.00 2020-12-23 monitoring, promotion, Implementation 27 29 01 31 ENT - Locación de Servicios - Selection prevention and control of 2 Posiciones NCDs, injuries, and risk factors. Component 3: Supporting AR-MSAL-209807-CS-INDV the National and Provincial / Staff Técnico de Apoyo al Ministries of Health to Individual Área de Vigilancia improve surveillance, Pending 2020-12- 2020-12- 2021-01- 2021-12- IBRD / 85080 Post Consultant Open 36,874.53 0.00 2020-12-21 Epidemiológica de ENT - monitoring, promotion, Implementation 27 29 01 31 Selection Locación de Servicios - 4 prevention and control of posiciones NCDs, injuries, and risk factors. Component 3: Supporting the National and Provincial AR-MSAL-209811-CS-INDV Ministries of Health to / Responsable de Sistemas de Individual improve surveillance, Pending 2020-12- 2020-12- 2021-01- 2021-12- Información en Salud - IBRD / 85080 Post Consultant Open 11,395.25 0.00 2020-12-21 monitoring, promotion, Implementation 27 28 01 31 Locación de Servicios - 1 Selection prevention and control of posición NCDs, injuries, and risk factors. Component 3: Supporting AR-MSAL-209812-CS-INDV the National and Provincial / Técnico de apoyo a la Ministries of Health to Individual Dirección Nacional de improve surveillance, Pending 2020-12- 2020-12- 2021-01- 2021-12- IBRD / 85080 Post Consultant Open 34,185.76 0.00 2020-12-21 Sistemas de Información en monitoring, promotion, Implementation 28 29 01 31 Selection Salud - Locación de Servicios prevention and control of - 3 Posiciones NCDs, injuries, and risk factors. Component 3: Supporting AR-MSAL-209816-CS-INDV the National and Provincial / Técnico de Apoyo al Área de Ministries of Health to Individual Promoción de la Salud improve surveillance, Pending 2020-12- 2020-12- 2021-01- 2021-12- IBRD / 85080 Post Consultant Open 11,395.25 0.00 2020-12-21 (Equipo Económico) - monitoring, promotion, Implementation 26 28 01 31 Selection Locación de Servicios - 1 prevention and control of posición NCDs, injuries, and risk factors. Component 3: Supporting the National and Provincial AR-MSAL-209817-CS-INDV Ministries of Health to / Staff Técnico del equipo de Individual improve surveillance, Pending 2020-12- 2020-12- 2021-01- 2021-12- facilitadores provinciales - IBRD / 85080 Post Consultant Open 45,581.02 0.00 2020-12-22 monitoring, promotion, Implementation 29 30 01 31 Locación de Servicios - 4 Selection prevention and control of posiciones NCDs, injuries, and risk factors. Component 3: Supporting the National and Provincial Ministries of Health to AR-MSAL-147033-CS-CDS / improve surveillance, 2019-12- 2019-12- 2020-03- 2020-02- 2022-01- Auditoría a Provincias 2019- IBRD / 85080 Post Direct Selection Direct 500,000.00 0.00 Canceled 2019-12-05 monitoring, promotion, 22 16 13 11 31 2022 prevention and control of NCDs, injuries, and risk factors. Component 3: Supporting the National and Provincial AR-MSAL-238949-CS-INDV Ministries of Health to / Staff Técnico de Apoyo al Individual improve surveillance, Pending 2021-06- 2021-06- 2021-07- 2021-12- Área de Servicios de Salud IBRD / 85080 Post Consultant Open 5,883.00 0.00 2021-06-13 monitoring, promotion, Implementation 24 26 01 31 (programa de prevención Selection prevention and control of cardiovascular) NCDs, injuries, and risk factors. Page 14 SUMMARY O F PROCUREMENT PLAN Project Preparation Advancement Project information: Liberia Integrated Public Financial Management Reform Project II P165000 Project Implementation agency: Ministry of Finance and Development Planning Date of the Procurement Plan: April 24, 2018 Period covered by this Procurement Plan: July 1, 2017- December 31, 2018 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 1, 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Public Procurement and Concessions Act, 2010 of the Republic of Liberia, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. In accordance with paragraph 5.3 of the Procurement Regulations, the request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. The form of the Letter of Acceptance is attached in Appendix 1. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables. Not Applicable. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: Not Applicable for those contracts identified in the Procurement Plan tables; Works: Not Applicable for those contracts identified in the Procurement Plan tables. Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations: Not Applicable. Other Relevant Procurement Information: - (a). Prior Procurement Arrangements: The Procurement Arrangements as indicated in the below table and within the thresholds indicated in the below tables will be used. The thresholds for the Bank’s prior review requirements are also provided in the table below: Table: Thresholds*, Procurement Arrangements, and Prior Review (The table below depicts the Thresholds and Procurement Methods to be used under the IPFMRP II): Thresholds*, Procurement Methods, and Prior Review Contract (C) Value Expenditure Procurement Contracts Subject to No Threshold* [eq. Category Method Prior Review /[eq. US$] USD] All contracts at or above USD Open Competition 5,000,000 are subject to International Market international advertising and C ≥ 5,000,000 Approach and Direct the use of the Bank’s SPDs (or Contracting other documents agreed with the Bank). 1 Works Open Competition National Market 200,000 < C < 5,000,000 None Approach C ≤ 200,000 RfQ None All contracts at or above USD Open Competition 500,000 are subject to International Market international advertising and C ≥ 500,000 Approach and Direct the use of the Bank’s SPDs (or Goods, IT and Contracting other documents agreed with 2 non-consulting the Bank). services Open Competition 100,000 < C < 500,000 National Market None Approach C ≤ 100,000 RfQ None All contracts at or above USD 100,000 are subject to for international advertising and C < 100,000 Consulting Services the use of the Bank’s SPDs (or National other documents agreed with shortlist for the Bank). 3 selection of All contracts at or above USD consultant firms for 200,000 are subject to Engineering and international advertising and C ≤ 200,000 Construction the use of the Bank’s SPDs (or Supervision other documents agreed with the Bank). Contract (C) Value Expenditure Procurement Contracts Subject to No Threshold* [eq. Category Method Prior Review /[eq. US$] USD] Selection of All values ≥ 100,000 4 Individual All Approaches consultants Training, Based on approved Workshops, This line activity is not subject 5 All Values Annual Work Plan & Study Tours to Procurement Review. Budgets (AWPB) by TTL (Special procurement arrangements like direct contracting, use of SOEs, UN Agencies, third party monitors, local NGOs, Force Account, servants needs, results based arrangements. It is not expected that there will need for prequalification in the procurement arrangements under IPFMRP II *These thresholds are for the purposes of the initial procurement plan for the PPA and for first 18 months. The thresholds will be revised periodically based on re-assessment of risks. All contracts not subject to prior review will be post-reviewed. Prequalification. Not expected for the packages of works/goods packages in the procurement plan. Proposed Procedures for CDD Components: Not Applicable Reference to (if any) Project Operational/Procurement Manual: The IPFMRP II Program team will prepare Procurement manuals. The Procurement Plan will also form part of the Project Implementation Manual. Any Other Special Procurement Arrangements: None Procurement Packages/PLAN with Procurement Arrangements and Time Schedule: as per the Table below: b) PROCUREMENT PLAN Works There are no works under the Project Preparation Advance Goods and Non-Consulting Services 1 2 3 4 5 6 7 8 9 Ref. Description of Estimat Selection Review Expecte Expecte Expecte Comme No. Assignment ed Method/ by Bank d date d d nts Cost in Arrangem (Prior / of Contrac Completi US$ ent Post) proposa t on l Signatu Date submiss re ion Date 1. SLA for Wimax 99,000.0 RFQ Post N/A 21 Sep 31 Aug 18 Complet 0 17 e 2. SLA for Battery 52,998.0 DS Post N/A 27 Jul 17 31 Jul 18 Complet Bank 0 e 3. SLA for Data Center 52,998.0 RFQ Post N/A 27 Jul 17 20 Jul 18 Complet 0 e 4. Firm to configure 750,000. RFB (IMA) Prior 10 Jul 17 21 Nov 20 May and roll out SIGTAS 00 17 18 to revenue collection point 5. Procurement of 551,860. RFB (NMA) Post N/A 22 Jan 18 15 Jun 18 Evaluatio hardware, data 00 n Report storage, network & under communication review devices, and licenses, etc. to secure stability of SIGTAS 6. Procurement of a 28,000.0 RFQ Post N/A 5 Mar 18 30 Apr 18 Complet Vehicle for LRA to 0 e facilitate Regional Dialogue on DRM Consultancy Services 1 2 3 4 5 6 7 8 9 Ref. Description of Estimate Selection Review Expecte Expecte Expected Comments No. Assignment d Method/ by Bank d date d Completi Cost in Arrangem (Prior / of Contrac on US$ ent Post) proposa t Date l submiss Signatu ion re Date 1. PSM for various 143,954.0 DS Post 05 Jul 17 28 Jul 17 30 Jun 18 Received IDA FreeBalance 0 No objection Application for Direct Modules Selection 2. TA (ITAS Advisor) 271,014.0 IC Post 15 Jan 18 21 Feb 30 Jun 18 ToR submitted; to provide support 0 18 Received IDA for system No Objection. stability Complete 3. TA to cost and 45,000.00 IC Post 6 Dec 17 15 Jan 18 21 Mar 18 ToR submitted; validate the Received IDA Domestic No Objection. Resource Complete. Mobilization Strategy 4. TA (Senior DBA) 132,000.0 IC Post 6 Dec 17 15 Jan 18 30 Jun 18 ToR submitted; to provide support 0 Received IDA to SIGTAS No Objection. stability Complete 5. TA (Local ITAS 72,000.00 IC Post 6 Dec 17 15 Jan 18 30 Jun 18 ToR submitted; Advisor) to Received IDA provide support No Objection. for the stability of Complete the current SIGTAS System 6. TA to conduct 150,000.0 CQS Post 6 Dec 17 30 Jan 18 26 Mar 18 ToR to be Business Process 0 submitted to Reengineering of IDA for Review the ITAS for LRA and No Objection. 7. TA to develop 25,000.00 IC Post 20 Jul 17 29 Sep 28 Mar 18 ToR to be Open Budget 17 submitted to national action IDA for Review plan and No Objection. 8. TA to undertake 190,000.0 CQS Post 12 Jul 17 21 Sep 20 Mar 18 ToR submitted; PFM/Procurement 0 17 Received IDA Capacity Needs No Objection. Assessment and Complete. develop Capacity building strategy 9. TA to develop the 50,000.00 CQS Post 03 Jul 17 13 Sep 12 Nov 17 ToR to be M&E Results 17 submitted to Framework for the IDA for Review PFM Strategy and No Objection. 10. International DS Prior 05 Jul 17 02 Aug 17 30 Jun 18 ToR submitted; Procurement Received IDA Specialist No Objection. 199,800.00 Complete 11. Data Center DS Post 05 Jul 17 02 Aug 17 30 Jun 18 ToR submitted; Manager Received IDA No Objection. 90,000.00 Complete 12. M & E Officer DS Post 05 Jul 17 02 Aug 17 30 Jun 18 ToR submitted; Received IDA No Objection. 45,000.00 Complete 13. Change DS Post 05 Jul 17 02 Aug 17 30 Jun 18 ToR submitted; Management Received IDA Officer No Objection. 45,000.00 Complete 14. Administration DS Post 05 Jul 17 02 Aug 17 30 Jun 18 ToR submitted; Officer Received IDA No Objection. 36,000.00 Complete 15. Data Base DS Post 05 Jul 17 02 Aug 17 30 Jun 18 ToR submitted; Administrator 1 Received IDA No Objection. 72,000.00 Complete 16. Data Base DS Post 05 Jul 17 02 Aug 17 30 Jun 18 ToR submitted; Administrator 2 Received IDA No Objection. 72,000.00 Complete 17. Economic DS Post 05 Jul 17 02 Aug 17 30 Jun 18 ToR submitted; Consultant 54,000.00 Received IDA No Objection. Complete 18. Administrative DS Post 05 Jul 17 02 Aug 17 30 Jun 18 ToR submitted, Assistant Received IDA No Objection. 12,600.00 Complete 19. NSA Coordinator DS Post 05 Jul 17 02 Aug 17 30 Jun 18 ToR submitted; Received IDA No objection. 54,000.00 Complete 20. Grant Finance DS Post 05 Jul 17 02 Aug 17 30 Jun 18 ToR submitted; Officer received IDA No Objection. 27,000.00 Complete 21. Senior Assistant DS Post 05 Jul 17 02 Aug 17 30 Jun 18 ToR submitted; Internal Auditor received IDA No Objection. 45,000.00 Complete 22. Assistant Internal DS Post 05 Jul 17 02 Aug 17 30 Jun 18 ToR submitted; Auditor received IDA No Objection. 36,000.00 Complete 23. Senior Assistant DS Post 05 Jul 17 02 Aug 17 30 Jun 18 ToR submitted; Project Account received IDA No Objection. 36,000.00 Complete 24. Sylvia A. Squire DS Post 05 Jul 17 02 Aug 17 30 Jun 18 ToR submitted; received IDA No Objection. 47,817.00 Complete 25. Kehleboe Gongloe DS Post 05 Jul 17 02 Aug 17 30 Jun 18 ToR submitted; received IDA No Objection. 93,600.00 Complete 26. Jenkins T. Taylor DS Post 05 Jul 17 02 Aug 17 30 Jun 18 ToR submitted; received IDA No Objection. 77,400.00 Complete 27. Gariston W. Bailey DS Post 05 Jul 17 02 Aug 17 30 Jun 18 ToR submitted; received IDA No Objection. 75,600.00 Complete Training and Workshop (Training & Workshop activities are subject to TTL clearance). Estima Estimated Expected Ref. Training, workshop and ted Duration Training/workshop No. study tours Cost in (Days) Date (US$) National Revenue Summit 10,000. 1. 00 28 9 Apr 18 Validation of national open 25,000. 2. budget national action plan 00 20 16 Apr 18 Validate PFM/Procurement 10,000. 3. Needs Assessment and 00 10 02 Apr 18 Capacity Building Strategy GENERAL NOTES 1. Training and capacity building: Training workshops (including training material and support), conference attendance and study tours, will be carried out based on approved annual training and allied activities plan by the TTL. The beneficiaries, after the training, will be requested to submit a brief report indicating what skills have been acquired and how these skills will contribute to enhance their performance and contribute to the attainment of the Project’s development objective. 2. Operational Costs: These are expenditures incurred by the Recipient to finance: (i) the salaries of locally contracted support staff of the Project entities and units involved in Project implementation (excluding civil servants) and state contributions thereon; (ii) per diem and travel expenses of the operational staff performing their responsibilities under the Project; (iii) fuel and vehicle maintenance and insurance; (iv) communication technology (including, without limitation, internet and telephone) and maintenance of equipment; (v) rental expenses and utilities; (vi) building security and maintenance; (vii) translations services, photocopies and publications; (viii) bank commissions; and (ix) utilities and office supplies as defined in the FA. Appendix 1 Letter of Acceptance of the World Bank’s Anti-Corruption Guidelines and Sanctions Framework Date: Invitation of Bids/Proposals No.__________ To: ___________________________________________________________________________ We, along with our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not) consultants and personnel, acknowledge and agree to abide by the World Bank’s policy regarding Fraud and Corruption (corrupt, fraudulent, collusive, coercive, and obstructive practices), as set out and defined in the World Bank’s Anti-Corruption Guidelines1 in connection with the procurement and execution of the contract (in case of award), including any amendments thereto. We declare and warrant that we, along our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not), consultants and personnel, , are not subject to, and are not controlled by any entity or individual that is subject to, a temporary suspension, early temporary suspension, or debarment imposed by a member of the World Bank Group, including, inter alia, a cross-debarment imposed by the World Bank Group as agreed with other international financial institutions (including multilateral development banks), or through the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement. Further, we are not ineligible under the laws or official regulations of [Insert name of Employer as per bidding document] or pursuant to a decision of the United Nations Security Council. We confirm our understanding of the consequences of not complying with the World Bank’s Anti-Corruption Guidelines, which may include the following: a. rejection of our Proposal/Bid for award of contract; b. in the case of award, termination of the contract, without prejudice to any other remedy for breach of contract; and c. sanctions, pursuant to the Bank’s Anti-corruption Guidelines and in accordance with its prevailing sanctions policies and procedures as set forth in the Bank’s Sanctions Framework. This may include a public declaration of ineligibility, either indefinitely or for a stated period of time, (i) to be awarded or otherwise benefit from a Bank-financed contract, financially or in any other manner;2 (ii) to be a 1Guidelines on Preventing and Combating Fraud and Corruption in Projects Financed by International Bank for Reconstruction and Development Loans and the International Development Agency Credits and Grants, dated October 15, 2006, and revised in January 2011 and July 2016, as they may be revised from time to time. 2 For the avoidance of doubt, a sanctioned party’s ineligibility to be awarded a contract shall include, without limitation, (i) applying for pre-qualification, expressing interest in a nominated3 sub-contractor, consultant, manufacturer or supplier, or service provider of an otherwise eligible firm being awarded a Bank-financed contract; and (iii) to receive the proceeds of any loan made by the Bank or otherwise to participate further in the preparation or implementation of any Bank-financed project. We understand that we may be declared ineligible as set out above upon: a. completion of World Bank Group sanctions proceedings according to its prevailing sanctions procedures; b. cross-debarment as agreed with other international financial institutions (including multilateral development banks); c. the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement; or d. temporary suspension or early temporary suspension in connection with an ongoing World Bank Group sanctions proceeding. For avoidance of doubt, the foregoing effects of ineligibility do not extend to a sanctioned firm’s or individual’s execution of its ongoing Bank-financed contracts (or its ongoing sub-agreements under such contracts) that are not the subject of a material modification, as determined by the Bank. We shall permit, and shall cause our sub-contractors, sub-consultants, agents (whether declared or not), personnel, consultants, service providers or suppliers, to permit the Bank to inspect4 all accounts, records, and other documents relating to consultancy, and bidding, either directly or as a nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider, in respect of such contract, and (ii) entering into an addendum or amendment introducing a material modification to any existing contract. 3 A nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider (different names are used depending on the particular bidding document) is one which has been: (i) included by the bidder in its pre-qualification application or bid because it brings specific and critical experience and know-how that allow the bidder to meet the qualification requirements for the particular bid; or (ii) appointed by the Borrower. 4 Inspections in this context are usually investigative (i.e., forensic) in nature: they involve fact-finding activities undertaken by the Bank or persons appointed by the Bank to address specific matters related to investigations/audits, such as evaluating the veracity of an allegation of possible Fraud and Corruption, through the appropriate mechanisms. Such activity includes but is not limited to accessing and examining a firm's or individual's financial records and information, and making copies thereof as relevant; accessing and examining any other documents, data, and information (whether in hard copy or electronic format) deemed relevant for the investigation/audit, and making copies thereof as relevant; interviewing staff and other relevant individuals; performing physical inspections and site visits; and obtaining third-party verification of information. the procurement process and/or contract execution (in the case of award), and to have them audited by auditors appointed by the Bank. We agree to preserve all accounts, records, and other documents (whether in hard copy or electronic format) related to the procurement and execution of the contract. Name of the Bidder/Consultant: Name of the person duly authorized to sign the Bid/Proposal on behalf of the Bidder/Consultant: Title of the person signing the Letter: PROCUREMENT Liberia : Public Financial Management Reforms for Institutional Strengthening PLAN General Information Country: Liberia Bank’s Approval Date of the Original Procurement Plan: 2019-01-15 2021-05-21 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P165000 GPN Date: 2019-11-01 Project Name: Public Financial Management Reforms for Institutional Strengthening Loan / Credit No: IDA / V1080, IDA / D5060 M Executing Agency(ies): inistry of Finance and Development Planning WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LR-MFDP-97556-GO-RFB / 1: Enhancing DRM Sources Single Stage - One Procurement of Hardware IDA / V1080 Post Request for Bids Open - National 551,860.00 0.00 Canceled 2018-01-22 2018-01-27 2018-03-10 2018-04-09 2018-05-14 2018-07-31 and Systems Envelope Data Storage and Network Devices LR-MFDP-97544-GO-RFQ / 1: Enhancing DRM Sources Request for Single Stage - One Procurement of Laptops for IDA / V1080 Post Limited 8,635.00 8,430.00 Completed 2018-08-25 2018-08-27 2018-10-20 2018-09-14 2018-10-30 2018-10-24 and Systems Quotations Envelope LRA LR-MFDP-97550-GO-RFQ / 1: Enhancing DRM Sources Request for Single Stage - One Procurement of Vehicle for IDA / V1080 Post Limited 28,000.00 28,000.00 Completed 2018-02-12 2018-02-07 2018-04-09 2018-05-21 2018-06-04 2018-06-04 and Systems Quotations Envelope LRA LR-MFDP-145523-GO-RFQ / Procurement of 10 doors, 200 3: Improving Public-Sector Under chairs, 2 overhead projectors, Request for Single Stage - One IDA / D5060 Capacity for Enhanced Post Limited 100,000.00 0.00 Implementati 2019-12-21 2020-08-03 2020-02-15 2020-08-13 1 speaker stand and 10 air Quotations Envelope Oversight and Accountability on conditions for UL Resource Center PFMRISP-REF-11 / Request for Single Stage - One Procurement of 4 office chairs IDA / D5060 5: Project Management Post Limited 30,000.00 0.00 Canceled 2020-01-25 2020-03-21 2020-06-19 Quotations Envelope and 3 desks for PMU LR-MFDP-151032-GO-RFB / Procurement of Desktops, 1: Enhancing DRM Sources Single Stage - One IDA / D5060 Post Request for Bids Open - National 300,000.00 0.00 Canceled 2020-01-06 2020-01-06 2020-01-11 2020-01-06 2020-02-22 2020-02-10 2020-03-23 2020-04-27 2020-10-24 Laptops and Other Office and Systems Envelope Equipment LR-MFDP-151054-GO-RFQ / Procurement of 4 chairs and 3 Request for Single Stage - One IDA / D5060 5: Project Management Post Limited 5,000.00 3,165.00 Completed 2020-01-17 2020-02-07 2020-03-13 2020-02-10 2020-09-09 2020-02-28 desks for Project Management Quotations Envelope Unit LR-MFDP-145295-GO-RFQ / 3: Improving Public-Sector Request for Single Stage - One Procurement and Installation IDA / D5060 Capacity for Enhanced Post Limited 70,000.00 0.00 Canceled 2019-12-25 2020-02-19 2020-08-17 Quotations Envelope of CAAT software for IAA Oversight and Accountability 3: Improving Public-Sector LR-MFDP-152772-GO-RFQ / Request for Single Stage - One IDA / D5060 Capacity for Enhanced Post Limited 150,000.00 72,500.00 Completed 2020-01-20 2020-01-07 2020-03-16 2020-02-07 2020-09-12 2020-06-11 Procurement of 4 vehicles Quotations Envelope Oversight and Accountability LR-MFDP-163495-GO-RFQ / 4: Improving Upstream and Request for Single Stage - One Procurement of 3 vehicles for IDA / D5060 Downstream PFM Systems in Post Limited 135,000.00 89,500.00 Signed 2020-03-23 2020-03-18 2020-05-18 2020-05-05 2020-11-14 Quotations Envelope RCU, PMU and DMA Selected Sectors LR-MFDP-164547-GO-RFB / 2: Stabilizing and Procurement of Desktops, Strengthening Performance of Single Stage - One IDA / D5060 Post Request for Bids Open - National 450,000.00 0.00 Canceled 2020-03-24 2020-03-29 2020-05-10 2020-06-09 2020-07-14 2021-01-10 Laptops and Other Office Financial Controls and Envelope Equipment Systems LR-MFDP-170135-GO-RFB / Procurement of Desktops, 1: Enhancing DRM Sources Single Stage - One IDA / D5060 Post Request for Bids Open - National 450,000.00 291,956.00 Signed 2020-01-06 2020-01-06 2020-01-11 2020-02-22 2020-02-10 2020-03-23 2020-05-12 2020-04-27 2020-07-28 2020-10-24 Laptops, Printers and Other and Systems Envelope ICT Equipment 2: Stabilizing and LR-MFDP-150793-GO-RFQ / Strengthening Performance of Request for Single Stage - One Refurbishment of the IFMIS IDA / D5060 Post Limited 50,000.00 0.00 Canceled 2020-01-04 2020-02-29 2020-08-27 Financial Controls and Quotations Envelope Training Room Systems LR-MFDP-196967-GO-RFQ / 2: Stabilizing and Procurement of Scanners and Pending Strengthening Performance of Request for Single Stage - One printers for rollout of IDA / D5060 Post Limited 15,000.00 0.00 Implementati 2020-12-20 2021-02-14 2021-08-13 Financial Controls and Quotations Envelope Electronic Data Management on Systems System LR-MFDP-197169-GO-RFQ / 3: Improving Public-Sector Procurement of 1 laptop, Request for Single Stage - One IDA / D5060 Capacity for Enhanced Post Limited 3,000.00 2,930.00 Completed 2020-11-15 2020-11-19 2021-01-10 2020-11-24 2021-07-09 2020-12-02 desks, printer, projector and Quotations Envelope Oversight and Accountability camera for NSA LR-MFDP-196983-GO-RFQ / Procurement of 10 air 3: Improving Public-Sector Pending Request for Single Stage - One conditioners, projectors and IDA / D5060 Capacity for Enhanced Post Limited 20,000.00 0.00 Implementati 2020-11-15 2021-01-10 2021-07-09 Quotations Envelope electronic equpiment for the Oversight and Accountability on University of Liberia LR-MFDP-196956-GO-RFQ / 3: Improving Public-Sector Pending Procurement of resource Request for Single Stage - One IDA / D5060 Capacity for Enhanced Post Open - International 100,000.00 0.00 Implementati 2021-03-27 2021-05-22 2021-11-18 materials (text books) for the Quotations Envelope Oversight and Accountability on University of Liberia Page 1 LR-MFDP-196925-GO-RFQ / Pending Procurement of 5 laptops, 3 Request for Single Stage - One IDA / D5060 5: Project Management Post Limited 20,000.00 0.00 Implementati 2020-09-07 2020-11-02 2021-05-01 desks and 1 printer & Quotations Envelope on catridges for PMU LR-MFDP-197180-GO-RFQ / Procurement of one vehicle Request for Single Stage - One IDA / D5060 5: Project Management Post Limited 60,000.00 54,461.00 Signed 2020-11-21 2020-10-06 2021-01-16 2020-12-15 2021-07-15 for Office of the Minister of Quotations Envelope Finance 2: Stabilizing and LR-MFDP-200528-GO-RFQ / Pending Strengthening Performance of Request for Single Stage - One Refurbishment of the IFMIS IDA / D5060 Post Limited 75,000.00 0.00 Implementati 2020-12-18 2021-02-12 2021-08-11 Financial Controls and Quotations Envelope Training Room at MFDP on Systems 2: Stabilizing and LR-MFDP-203883-GO-RFQ / Strengthening Performance of Request for Single Stage - One Procurement of Hardware for IDA / D5060 Post Limited 85,000.00 72,473.00 Completed 2021-01-11 2020-11-23 2021-03-08 2020-12-15 2021-09-04 2021-01-07 Financial Controls and Quotations Envelope EFT Implementation Systems LR-MFDP-203882-GO-RFQ / 3: Improving Public-Sector Refurbishment of the Request for Single Stage - One IDA / D5060 Capacity for Enhanced Post Limited 30,000.00 27,501.64 Signed 2021-01-13 2020-12-01 2021-03-10 2021-02-10 2021-09-06 University of Liberia Resource Quotations Envelope Oversight and Accountability Center LR-MFDP-197168-GO-RFQ / Procurement of office Request for Single Stage - One IDA / D5060 5: Project Management Post Limited 25,000.00 0.00 Canceled 2021-03-29 2021-05-24 2021-11-20 furniture (desks and chairs) Quotations Envelope for PMU LR-MFDP-196969-GO-RFQ / 2: Stabilizing and Procurement of incident Strengthening Performance of Request for Single Stage - One IDA / D5060 Post Limited 50,000.00 0.00 Canceled 2021-02-15 2021-04-12 2021-10-09 management software (help Financial Controls and Quotations Envelope desk) Systems LR-MFDP-225491-GO-RFQ / 3: Improving Public-Sector Pending Procurement of Servers and Request for Single Stage - One IDA / D5060 Capacity for Enhanced Post Limited 35,000.00 0.00 Implementati 2021-01-27 2021-03-24 2021-09-20 Software for Pentana Quotations Envelope Oversight and Accountability on Implementation LR-MFDP-145528-GO-DIR / 4: Improving Upstream and Procurement of STATA for IDA / D5060 Downstream PFM Systems in Post Direct Selection Direct 5,400.00 0.00 Canceled 2020-01-16 2020-01-21 2020-02-25 2020-08-23 PETS Selected Sectors LR-MFDP-145144-GO-RFQ / 4: Improving Upstream and Procurement of 2 Windows Request for Single Stage - One IDA / D5060 Downstream PFM Systems in Post Open - National 67,500.00 0.00 Canceled 2019-12-15 2020-02-09 2020-08-07 Servers and backup, and Quotations Envelope Selected Sectors operating systems licenses LR-MFDP-197187-GO-RFB / 2: Stabilizing and Procurement of 90 desktops, Strengthening Performance of Single Stage - One IDA / D5060 Post Request for Bids Open - National 150,000.00 0.00 Canceled 2021-01-08 2021-01-13 2021-02-24 2021-03-26 2021-04-30 2021-10-27 and 90 printers for IFMIS Financial Controls and Envelope rollout to 20 sites Systems LR-MFDP-235374-GO-RFQ / Pending Procurement of 10 laptops, 2 1: Enhancing DRM Sources Request for Single Stage - One IDA / D5060 Post Limited 20,000.00 0.00 Implementati 2021-06-15 2021-08-10 2021-11-08 printers and 1 projector with and Systems Quotations Envelope on screen LR-MFDP-235389-GO-RFQ / Pending 1: Enhancing DRM Sources Request for Single Stage - One Procurement of office IDA / D5060 Post Limited 100,000.00 0.00 Implementati 2021-06-15 2021-08-10 2021-11-08 and Systems Quotations Envelope furniture and fixture on NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 2: Stabilizing and LR-MFDP-97553-NC-RFQ / Strengthening Performance of Request for Single Stage - One IDA / V1080 Post Limited 99,000.00 99,500.00 Completed 2018-01-09 2018-01-04 2018-03-06 2018-02-28 2019-02-28 2019-02-28 SLA for Wimax Financial Controls and Quotations Envelope Systems 2: Stabilizing and LR-MFDP-97594-NC-DIR / Strengthening Performance of IDA / V1080 Post Direct Selection Direct 52,998.00 28,800.00 Completed 2017-12-15 2017-12-15 2017-12-20 2017-12-18 2018-01-24 2017-12-28 2018-12-26 2018-12-26 SLA for Battery Bank Financial Controls and Systems 2: Stabilizing and LR-MFDP-97441-NC-RFQ / Strengthening Performance of Request for Single Stage - One SLA for Data Center IDA / V1080 Post Limited 52,998.00 98,658.67 Completed 2018-04-01 2018-03-08 2018-05-27 2018-07-30 2019-02-28 2019-01-31 Financial Controls and Quotations Envelope Maintenance Systems 2: Stabilizing and LR-MFDP-135160-NC-DIR / Strengthening Performance of SLA for IFMIS Infrastructure IDA / D5060 Post Direct Selection Direct 100,000.00 0.00 Canceled 2019-09-20 2019-06-17 2019-09-25 2019-09-04 2019-10-30 2020-09-30 Financial Controls and Support and Maintenance Systems 2: Stabilizing and LR-MFDP-135377-NC-DIR / Strengthening Performance of Redeployment of Electronic IDA / V1080 Post Direct Selection Direct 98,000.00 0.00 Canceled 2019-07-13 2019-07-15 2019-07-18 2019-08-16 2019-08-22 2019-12-16 Financial Controls and Data Management System Systems 2: Stabilizing and LR-MFDP-135395-NC-DIR / Strengthening Performance of IDA / V1080 Prior Direct Selection Direct 352,406.00 0.00 Canceled 2019-06-27 2019-10-14 2019-07-02 2019-10-14 2019-08-06 2019-10-31 Activation of Budget Module Financial Controls and Systems LR-MFDP-145529-NC-DIR / 2: Stabilizing and Pending Activation of key Strengthening Performance of IDA / D5060 Post Direct Selection Direct 250,000.00 0.00 Implementati 2019-12-12 2019-12-17 2020-01-21 2020-07-19 functionalities by FreeBalance Financial Controls and on for IFMIS improvement Systems LR-MFDP-145292-NC-DIR / 2: Stabilizing and SLA for IFMIS Infrastructure Strengthening Performance of IDA / D5060 Post Direct Selection Direct 86,000.00 86,000.00 Signed 2019-10-02 2019-10-02 2019-10-07 2019-10-04 2019-11-11 2019-10-15 2020-11-10 Support and Maintenance Financial Controls and Services Systems Page 2 LR-MFDP-151076-NC-DIR / 2: Stabilizing and Enhancement of the Electronic Strengthening Performance of IDA / D5060 Post Direct Selection Direct 98,000.00 98,000.00 Completed 2019-07-15 2019-07-15 2019-07-20 2019-08-15 2019-08-24 2019-09-13 2020-02-20 2020-05-29 Document Management Financial Controls and System Systems LR-MFDP-145269-NC-RFB / 2: Stabilizing and Implement the EFT system Strengthening Performance of Single Stage - One IDA / D5060 Post Request for Bids Open - International 300,000.00 0.00 Canceled 2020-01-13 2020-01-18 2020-02-29 2020-03-30 2020-05-04 2020-10-31 within the MFDP to automatic Financial Controls and Envelope GoL recurrent payment Systems LR-MFDP-196968-NC-RFQ / 2: Stabilizing and SLA for Support and Strengthening Performance of Request for Single Stage - One IDA / D5060 Post Limited 50,000.00 0.00 Canceled 2021-01-10 2021-03-07 2022-03-07 Maintenance of IFMIS Financial Controls and Quotations Envelope hardward environment Systems 2: Stabilizing and LR-MFDP-145263-NC-RFQ / Strengthening Performance of Request for Single Stage - One Deployment of LAN to 20 IDA / D5060 Post Limited 100,000.00 0.00 Canceled 2019-12-01 2020-01-26 2020-07-24 Financial Controls and Quotations Envelope IFMIS rollout sites Systems CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LR-MFDP-81212-CS-CQS / 4: Improving Upstream and Consultant Consultant to Develop the M & IDA / V1080 Downstream PFM Systems in Post Qualification Open - National 39,600.00 0.00 Canceled 2018-11-08 2018-11-29 2019-01-12 2019-02-11 2019-03-18 2019-09-14 E Results Framework for PFM Selected Sectors Selection Strategy 2: Stabilizing and LR-MFDP-81208-CS-CQS / Consultant Strengthening Performance of Consultant to Develop Open IDA / V1080 Post Qualification Open - National 25,000.00 0.00 Canceled 2018-11-06 2018-11-27 2019-01-10 2019-02-09 2019-03-16 2019-09-12 Financial Controls and Budget National Action Plan Selection Systems LR-MFDP-81211-CS-LCS / Least Cost IDA / V1080 5: Project Management Post Open - National 20,000.00 0.00 Canceled 2018-11-12 2018-12-03 2019-01-16 2019-02-13 2019-03-15 2019-04-19 2019-05-24 2019-11-20 Firm to Conduct Audit of PPA Selection LR-MFDP-135794-CS-CQS / Consultant Consultancy for Independent IDA / D5060 5: Project Management Post Qualification Open - National 25,000.00 0.00 Canceled 2019-10-06 2019-10-02 2019-10-27 2019-12-10 2020-01-09 2020-02-13 2021-02-12 Verification Selection LR-MFDP-152805-CS-CQS / Consultant to facilitate Consultant 1: Enhancing DRM Sources technical workshop for IDA / D5060 Post Qualification Open - International 75,000.00 0.00 Canceled 2020-01-15 2019-12-19 2020-02-05 2020-01-09 2020-03-20 2020-03-05 2020-04-19 2020-05-24 2020-11-20 and Systems validation of VAT White Paper, Selection law and Migration Paper LR-MFDP-196923-CS-CQS / 2: Stabilizing and Consultancy for design, Consultant Strengthening Performance of Under installation, configuration and IDA / D5060 Post Qualification Open - National 185,000.00 0.00 2021-02-24 2021-02-24 2021-03-17 2021-03-12 2021-04-30 2021-05-30 2021-07-04 2021-12-31 Financial Controls and Implementation integration of the Local Area Selection Systems Network LR-MFDP-196918-CS-CQS / 2: Stabilizing and Consultant Consultancy to design, Strengthening Performance of Pending IDA / D5060 Post Qualification Open - International 300,000.00 0.00 2021-02-16 2021-03-09 2021-04-22 2021-05-22 2021-06-26 2021-12-23 develop and install GoL Data Financial Controls and Implementation Selection Portal at MFDP Systems LR-MFDP-212901-CS-CQS / Consulting Services for the Consultant 1: Enhancing DRM Sources Finalization and Validation of IDA / D5060 Post Qualification Open - International 100,000.00 0.00 Under Review 2019-12-19 2019-12-19 2020-01-09 2020-02-22 2020-03-23 2020-04-27 2020-10-24 and Systems the VAT Implementation Selection Package LR-MFDP-222825-CS-QBS / 2: Stabilizing and Consultancy to Provide PFM Strengthening Performance of Quality Based Under System Help Desk IDA / D5060 Prior Open - International 300,000.00 0.00 2021-04-02 2021-04-06 2021-04-23 2021-04-27 2021-06-06 2021-07-04 2021-08-03 2021-09-02 2021-10-07 2022-04-05 Financial Controls and Selection Implementation Management Solution for Systems MFDP LR-MFDP-197161-CS-CQS / 2: Stabilizing and Consultant Consultancy to conduct an Strengthening Performance of IDA / D5060 Post Qualification Open - National 100,000.00 0.00 Canceled 2021-01-18 2021-02-08 2021-03-24 2021-04-23 2021-05-28 2021-11-24 assessment of the additional Financial Controls and Selection 57 IFMIS rollout sites Systems INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Individual LR-MFDP-97537-CS-INDV / 1: Enhancing DRM Sources IDA / V1080 Post Consultant Open 176,850.00 216,000.00 Completed 2017-11-13 2017-10-05 2018-01-01 2018-02-14 2018-01-22 2018-02-22 2018-02-26 2018-04-30 2019-02-28 2019-02-28 Consultant for ITAS Advisor and Systems Selection LR-MFDP-97573-CS-INDV / Individual 1: Enhancing DRM Sources Consultant for Domestic IDA / V1080 Post Consultant Open 45,000.00 145,000.00 Completed 2017-12-06 2017-12-06 2018-01-24 2018-02-14 2018-02-14 2018-02-16 2018-03-21 2018-03-01 2019-01-31 2019-01-31 and Systems Resource Mobilization Selection LR-MFDP-97591-CS-INDV / Individual 1: Enhancing DRM Sources Senior Data Base IDA / V1080 Post Consultant Open 132,000.00 148,000.00 Completed 2017-12-06 2017-12-12 2018-01-24 2018-04-27 2018-02-14 2018-04-30 2018-03-21 2018-07-02 2019-02-28 2019-02-28 and Systems Administrator Selection LR-MFDP-97569-CS-INDV / Individual 1: Enhancing DRM Sources Consultant for Local ITAS IDA / V1080 Post Consultant Open 72,000.00 44,444.48 Completed 2017-12-06 2017-12-06 2018-01-24 2018-03-28 2018-02-14 2018-07-05 2018-03-21 2018-06-05 2019-02-28 2019-02-28 and Systems Advisor Selection LR-MFDP-97533-CS-INDV / Individual Consultant to Conduct 1: Enhancing DRM Sources IDA / V1080 Post Consultant Open 150,000.00 20,365.00 Completed 2018-01-29 2018-01-29 2018-03-19 2018-07-17 2018-04-09 2018-07-30 2018-05-14 2018-08-02 2019-02-28 2018-12-20 Business Process and Systems Selection Reengineering Page 3 LR-MFDP-97539-CS-INDV / Consultant to Undertake PFM 3: Improving Public-Sector Individual and Procurement Capacity IDA / V1080 Capacity for Enhanced Post Consultant Open 190,000.00 600.92 Completed 2018-04-23 2018-04-23 2018-06-11 2018-06-22 2018-07-02 2018-08-06 2018-08-06 2018-08-08 2018-11-30 2019-02-28 Needs Assessment and Oversight and Accountability Selection Develop LR-MFDP-97567-CS-CDS / International Procurement IDA / V1080 5: Project Management Post Direct Selection Direct 67,600.00 67,600.00 Completed 2018-07-02 2018-06-28 2018-07-12 2018-07-23 2018-09-15 2018-07-30 2018-12-31 2018-12-31 Specialist 2: Stabilizing and LR-MFDP-97582-CS-CDS / Strengthening Performance of IDA / V1080 Post Direct Selection Direct 30,000.00 30,000.00 Completed 2018-07-02 2018-06-28 2018-07-12 2018-07-23 2018-09-15 2018-08-02 2019-02-28 2019-02-28 Data Center Manager Financial Controls and Systems LR-MFDP-97563-CS-CDS / IDA / V1080 5: Project Management Post Direct Selection Direct 18,000.00 24,000.00 Completed 2018-07-02 2018-06-28 2018-07-12 2018-07-23 2018-09-15 2018-08-01 2019-02-28 2019-02-28 M and E Officer LR-MFDP-97546-CS-CDS / IDA / V1080 5: Project Management Post Direct Selection Direct 15,000.00 15,000.00 Completed 2018-07-02 2018-06-28 2018-07-12 2018-07-23 2018-09-15 2018-08-02 2019-02-28 2019-02-28 Change Management Officer LR-MFDP-97595-CS-CDS / IDA / V1080 5: Project Management Post Direct Selection Direct 12,000.00 16,000.00 Completed 2018-07-02 2018-06-28 2018-07-12 2018-07-23 2018-09-15 2018-07-30 2019-02-28 2019-02-28 Administration Officer 2: Stabilizing and LR-MFDP-97574-CS-CDS / Strengthening Performance of IDA / V1080 Post Direct Selection Direct 24,000.00 32,000.00 Completed 2018-07-02 2018-06-28 2018-07-12 2018-07-23 2018-09-15 2018-07-30 2019-02-28 2019-02-28 Data Base Administrator 1 Financial Controls and Systems 2: Stabilizing and LR-MFDP-97572-CS-CDS / Strengthening Performance of IDA / V1080 Post Direct Selection Direct 24,000.00 32,000.00 Completed 2018-07-02 2018-06-28 2018-07-12 2018-07-23 2018-09-15 2018-07-30 2019-02-28 2019-02-28 Data Base Administrator 2 Financial Controls and Systems LR-MFDP-97577-CS-CDS / IDA / V1080 5: Project Management Post Direct Selection Direct 18,000.00 18,000.00 Completed 2018-07-02 2018-06-28 2018-07-12 2018-07-23 2018-09-15 2018-08-02 2019-02-28 2019-02-28 Coordinator NSA LR-MFDP-97585-CS-CDS / IDA / V1080 5: Project Management Post Direct Selection Direct 9,000.00 12,000.00 Completed 2018-07-02 2018-06-28 2018-07-12 2018-07-23 2018-09-15 2018-08-02 2019-02-28 2019-02-28 Grant Finance Officer LR-MFDP-97566-CS-CDS / Senior Assitant Internal IDA / V1080 5: Project Management Post Direct Selection Direct 19,500.00 119.82 Completed 2018-07-02 2018-06-28 2018-07-12 2018-07-23 2018-09-15 2018-07-30 2019-02-28 2019-02-28 Auditor LR-MFDP-97442-CS-CDS / IDA / V1080 5: Project Management Post Direct Selection Direct 12,000.00 0.00 Canceled 2018-07-02 2018-07-12 2018-09-15 2018-12-30 Assistant Internal Auditor 3: Improving Public-Sector LR-MFDP-97535-CS-CDS / IDA / V1080 Capacity for Enhanced Post Direct Selection Direct 15,939.00 15,939.00 Completed 2018-07-02 2018-06-28 2018-07-12 2018-07-23 2018-09-15 2018-08-02 2018-12-31 2018-12-31 Registrar for FMTP and IPTP Oversight and Accountability 3: Improving Public-Sector LR-MFDP-97543-CS-CDS / IDA / V1080 Capacity for Enhanced Post Direct Selection Direct 31,200.00 31,200.00 Completed 2018-07-02 2018-06-28 2018-07-12 2018-07-23 2018-09-15 2018-08-02 2019-02-28 2019-02-28 Director for FMTP and IPTP Oversight and Accountability LR-MFDP-97538-CS-CDS / 3: Improving Public-Sector Resident Coordinator for IDA / V1080 Capacity for Enhanced Post Direct Selection Direct 25,800.00 33,800.00 Completed 2018-07-02 2018-06-28 2018-07-12 2018-07-23 2018-09-15 2018-08-02 2019-02-28 2019-02-28 FMTP and IPTP Oversight and Accountability LR-MFDP-97536-CS-CDS / 3: Improving Public-Sector National Team Leader for IDA / V1080 Capacity for Enhanced Post Direct Selection Direct 25,200.00 25,200.00 Completed 2018-07-02 2018-06-28 2018-07-12 2018-07-23 2018-09-15 2018-08-02 2018-12-31 2018-12-31 FMTP and IPTP Oversight and Accountability LR-MFDP-97575-CS-CDS / Senior Assistant Project IDA / V1080 5: Project Management Post Direct Selection Direct 12,000.00 16,000.00 Completed 2018-07-02 2018-06-28 2018-07-12 2018-07-23 2018-09-15 2018-08-02 2019-02-28 2019-02-28 Accountant 2: Stabilizing and LR-MFDP-97596-CS-CDS / Strengthening Performance of PSM for various FreeBalance IDA / V1080 Post Direct Selection Direct 143,954.00 143,954.00 Completed 2017-07-28 2018-06-20 2017-08-07 2017-11-27 2017-10-11 2018-09-19 2018-07-02 2018-07-31 Financial Controls and Applications Modules Systems Individual LR-MFDP-135157-CS-INDV / IDA / V1080 5: Project Management Post Consultant Open 144,000.00 0.00 Canceled 2019-10-10 2019-09-23 2019-11-28 2019-12-09 2019-12-19 2020-01-23 2020-07-21 International IFMIS Advisor Selection LR-MFDP-135156-CS-INDV / Individual International Procurement IDA / D5060 5: Project Management Prior Consultant Open 144,000.00 39,250.00 Signed 2019-10-10 2019-10-02 2019-11-28 2019-12-17 2019-12-19 2020-01-27 2020-01-23 2020-01-28 2020-12-31 Advisor Selection LR-MFDP-135410-CS-INDV / 4: Improving Upstream and Individual Consultant to Develop IDA / D5060 Downstream PFM Systems in Prior Consultant Open 205,000.00 0.00 Canceled 2019-12-22 2020-02-09 2020-03-01 2020-04-05 2020-12-01 Electronic Personnel Action Selected Sectors Selection Notice LR-MFDP-135988-CS-INDV / 4: Improving Upstream and Individual Database Administrator for IDA / V1080 Downstream PFM Systems in Post Consultant Open 10,000.00 0.00 Canceled 2019-10-16 2019-10-18 2019-12-04 2019-12-25 2020-01-29 2020-07-27 PETS Selected Sectors Selection LR-MFDP-145141-CS-INDV / Consultant to conduct 2: Stabilizing and Individual detailed needs assessment for Strengthening Performance of IDA / D5060 Post Consultant Open 50,000.00 32,950.00 Completed 2019-12-12 2019-11-20 2020-01-30 2020-02-12 2020-02-20 2020-07-01 2020-03-26 2020-07-16 2020-09-22 2020-08-20 Technical and Functional Financial Controls and Selection System Requirements for Systems Open Data LR-MFDP-145145-CS-CDS / IDA / D5060 5: Project Management Post Direct Selection Direct 42,000.00 72,150.00 Signed 2019-11-12 2019-11-15 2019-11-22 2019-11-18 2020-01-26 2019-11-20 2021-01-25 M & E Officer for PMU LR-MFDP-145268-CS-CDS / Administration Officer for IDA / D5060 5: Project Management Post Direct Selection Direct 24,000.00 39,000.00 Signed 2019-11-12 2019-11-15 2019-11-22 2019-11-18 2020-01-26 2019-11-20 2021-01-25 PMU LR-MFDP-145266-CS-CDS / 3: Improving Public-Sector Coordinator for Non-State IDA / D5060 Capacity for Enhanced Post Direct Selection Direct 36,000.00 58,500.00 Signed 2019-11-12 2019-11-15 2019-11-22 2019-11-18 2020-01-26 2019-11-20 2021-01-25 Actors Secretariat Oversight and Accountability Page 4 LR-MFDP-145290-CS-INDV / 3: Improving Public-Sector Individual Institutional Support IDA / D5060 Capacity for Enhanced Post Consultant Open 36,000.00 36,000.00 Signed 2019-11-26 2019-11-11 2020-01-14 2020-01-30 2020-02-04 2020-03-11 2020-03-10 2020-03-12 2021-03-10 Consultant for UL Oversight and Accountability Selection LR-MFDP-145146-CS-CDS / 3: Improving Public-Sector Grants Finance Officer for Non- IDA / D5060 Capacity for Enhanced Post Direct Selection Direct 18,000.00 29,250.00 Signed 2019-11-19 2019-11-15 2019-11-29 2019-11-18 2020-02-02 2019-11-20 2021-02-01 State Actors Secretariat Oversight and Accountability LR-MFDP-145274-CS-INDV / Consultant to train members 3: Improving Public-Sector Individual of Parliament on the IDA / D5060 Capacity for Enhanced Post Consultant Limited 35,000.00 0.00 Canceled 2020-01-07 2020-01-12 2020-02-02 2020-03-08 2020-09-04 examination of statement of Oversight and Accountability Selection accountants of State Owned Enterprises 2: Stabilizing and LR-MFDP-150792-CS-CDS / Strengthening Performance of Activation of the IFMIS Budget IDA / D5060 Post Direct Selection Direct 380,000.00 306,440.00 Completed 2019-12-17 2019-07-12 2019-12-27 2019-07-22 2020-03-01 2019-07-16 2020-08-28 2020-12-30 Financial Controls and Module Systems 2: Stabilizing and LR-MFDP-145304-CS-CDS / Strengthening Performance of IDA / D5060 Post Direct Selection Direct 48,000.00 50,000.00 Signed 2019-11-19 2019-12-20 2019-11-29 2019-11-19 2020-02-02 2019-11-22 2021-02-01 Database Administrator 2 Financial Controls and Systems 2: Stabilizing and LR-MFDP-145302-CS-CDS / Strengthening Performance of IDA / D5060 Post Direct Selection Direct 48,000.00 50,000.00 Signed 2019-11-19 2019-11-20 2019-11-29 2019-11-19 2020-02-02 2019-11-22 2021-02-01 Database Administrator 1 Financial Controls and Systems LR-MFDP-145284-CS-CDS / 2: Stabilizing and Consultant to update and Strengthening Performance of IDA / D5060 Post Direct Selection Direct 100,000.00 120,000.00 Completed 2019-11-18 2019-10-28 2019-11-28 2019-11-18 2020-02-01 2020-01-16 2020-07-30 2020-03-10 revamp the 5 - Year IFMIS Financial Controls and Strategy Systems LR-MFDP-145526-CS-INDV / Consultant to conduct 2: Stabilizing and Individual institutional needs Strengthening Performance of IDA / D5060 Post Consultant Open 75,000.00 50,550.00 Signed 2020-02-17 2020-11-01 2020-04-06 2021-01-07 2020-04-27 2021-02-04 2020-06-01 2021-02-10 2020-11-28 assessment and develop Financial Controls and Selection capacity building plan for Systems MTEF Implementation LR-MFDP-150791-CS-CDS / 4: Improving Upstream and Develop, configure, integrate IDA / D5060 Downstream PFM Systems in Prior Direct Selection Direct 300,000.00 246,086.20 Completed 2020-01-06 2020-02-25 2020-01-16 2020-03-13 2020-03-21 2020-09-18 2020-09-17 2021-02-04 and deploy e-PAN Application Selected Sectors LR-MFDP-145278-CS-INDV / Consultant to facilitate Individual 1: Enhancing DRM Sources technical workshop for IDA / D5060 Post Consultant Open 25,000.00 0.00 Canceled 2020-02-12 2020-04-01 2020-04-22 2020-05-27 2020-11-23 and Systems Validation of VAT White Paper, Selection Law, and Migration Paper LR-MFDP-152800-CS-CDS / 4: Improving Upstream and Consultancy for Independent IDA / D5060 Downstream PFM Systems in Prior Direct Selection Direct 100,000.00 15,000.00 Completed 2020-01-15 2020-01-29 2020-01-25 2020-01-31 2020-03-30 2020-03-02 2020-09-26 2020-12-30 Verification Selected Sectors LR-MFDP-152801-CS-CDS / 2: Stabilizing and Consultancy to implement the Strengthening Performance of EFT System within the MFDP IDA / D5060 Prior Direct Selection Direct 300,000.00 654,059.82 Signed 2020-01-15 2020-02-25 2020-01-25 2020-02-12 2020-03-30 2020-08-19 2020-09-26 Financial Controls and to Automatic GoL Recurrent Systems Payment LR-MFDP-157299-CS-INDV / 4: Improving Upstream and Individual Database Administrator for IDA / D5060 Downstream PFM Systems in Post Consultant Limited 10,000.00 9,900.00 Signed 2020-02-12 2020-01-10 2020-02-17 2020-02-21 2020-03-09 2020-09-17 2020-04-13 2020-10-23 2020-10-10 PETS Selected Sectors Selection LR-MFDP-163491-CS-INDV / Individual 1: Enhancing DRM Sources Technical Focal Person for IDA / D5060 Post Consultant Open 48,000.00 54,000.00 Signed 2020-03-20 2020-03-25 2020-05-08 2020-07-02 2020-05-29 2020-08-25 2020-07-03 2020-08-31 2021-07-03 and Systems Revenue Selection LR-MFDP-163500-CS-INDV / Individual 1: Enhancing DRM Sources Technical Focal Person for IDA / D5060 Post Consultant Open 48,000.00 54,000.00 Signed 2020-03-20 2020-03-25 2020-05-08 2020-06-04 2020-05-29 2020-07-09 2020-07-03 2020-07-28 2021-07-03 and Systems Expenditure Selection 2: Stabilizing and Individual LR-MFDP-163487-CS-INDV / Strengthening Performance of IDA / D5060 Post Consultant Limited 180,000.00 197,633.33 Signed 2020-02-05 2020-02-13 2020-02-10 2020-02-19 2020-03-02 2020-09-03 2020-04-06 2020-10-20 2021-04-07 International IFMIS Advisor Financial Controls and Selection Systems LR-MFDP-163936-CS-INDV / 3: Improving Public-Sector Individual Consultant to Develop IDA / D5060 Capacity for Enhanced Post Consultant Open 75,000.00 35,000.00 Completed 2020-03-24 2020-03-10 2020-05-12 2020-06-01 2020-06-02 2020-07-10 2020-07-07 2020-07-17 2021-01-03 2020-08-20 Business/Strategic Plan for Oversight and Accountability Selection LICPA LR-MFDP-170136-CS-CDS / IDA / D5060 5: Project Management Post Direct Selection Direct 65,000.00 72,150.00 Signed 2020-03-03 2020-03-03 2020-03-13 2020-03-13 2020-05-17 2020-04-01 2021-05-17 Project Manager for PFMRISP LR-MFDP-175683-CS-CDS / 3: Improving Public-Sector Firm to configure and IDA / D5060 Capacity for Enhanced Post Direct Selection Direct 100,000.00 77,250.00 Signed 2020-04-02 2020-06-02 2020-04-12 2020-07-03 2020-06-16 2020-10-29 2020-12-13 enhance PENTANA Audit Oversight and Accountability Software LR-MFDP-179865-CS-CDS / Intwrnational Procurement IDA / D5060 5: Project Management Prior Direct Selection Direct 150,000.00 170,204.00 Signed 2020-06-10 2020-06-16 2020-06-20 2020-06-11 2020-08-24 2020-09-08 2021-08-24 Advisor 2: Stabilizing and LR-MFDP-135414-CS-INDV / Individual Strengthening Performance of Consultant to Provide Support IDA / D5060 Post Consultant Open 90,000.00 0.00 Canceled 2019-10-14 2019-10-18 2019-12-02 2020-01-14 2019-12-23 2020-02-26 2020-01-27 2020-07-31 Financial Controls and to GRPB Unit Selection Systems LR-MFDP-145520-CS-INDV / Individual Consultant to draft excise 1: Enhancing DRM Sources IDA / D5060 Post Consultant Open 10,000.00 0.00 Canceled 2020-02-12 2020-04-01 2020-04-22 2020-05-27 2020-11-23 stamp tax implementation and Systems Selection manual LR-MFDP-196970-CS-INDV / Individual Consultant to review and 1: Enhancing DRM Sources Pending IDA / D5060 Post Consultant Open 100,000.00 0.00 2021-02-23 2021-04-13 2021-05-04 2021-06-08 2021-12-05 redraft provision of the tax and Systems Implementation Selection code Page 5 LR-MFDP-196974-CS-INDV / 2: Stabilizing and Consultant to develop. Individual Strengthening Performance of Under Validate, and produce training IDA / D5060 Post Consultant Open 35,000.00 0.00 2021-03-10 2021-02-07 2021-04-28 2021-05-19 2021-06-23 2021-12-20 Financial Controls and Implementation manual of the IFMIS Budget Selection Systems Module LR-MFDP-197171-CS-INDV / 2: Stabilizing and Individual Consultant to update the Strengthening Performance of IDA / D5060 Post Consultant Open 50,000.00 0.00 Under Review 2021-03-11 2021-01-27 2021-04-29 2021-05-20 2021-06-24 2021-12-21 MTEF Manual and provide Financial Controls and Selection training Systems LR-MFDP-196990-CS-INDV / 2: Stabilizing and Consultant to build the Individual Strengthening Performance of Under capacity of the Gender IDA / D5060 Post Consultant Limited 90,000.00 0.00 2020-12-16 2020-09-24 2020-12-21 2021-01-11 2021-02-15 2021-08-14 Financial Controls and Implementation Responsive and Planning Selection Systems Budgeting (GRPB) Unit LR-MFDP-196916-CS-INDV / Consultant to develop an 3: Improving Public-Sector Individual Under implementation & operation IDA / D5060 Capacity for Enhanced Post Consultant Open 55,000.00 0.00 2021-02-22 2021-02-01 2021-04-12 2021-05-03 2021-06-07 2021-12-04 Implementation manual for PFM Reform Oversight and Accountability Selection Coordination Unit LR-MFDP-196939-CS-INDV / 3: Improving Public-Sector Individual Consultant to revise PFM Under IDA / D5060 Capacity for Enhanced Post Consultant Open 45,000.00 0.00 2021-03-18 2021-03-08 2021-05-06 2021-05-27 2021-07-01 2021-12-28 Regulations for Government Implementation Oversight and Accountability Selection of Liberia LR-MFDP-197166-CS-INDV / Capacity Building & Change Individual Under Management Specialist to IDA / D5060 5: Project Management Post Consultant Open 42,000.00 0.00 2021-02-09 2020-11-04 2021-03-30 2021-04-20 2021-05-25 2022-05-25 Implementation support the PFM Capacity Selection Building Strategy LR-MFDP-196934-CS-INDV / Economic Governance Individual Specialist to provide advisory IDA / D5060 5: Project Management Post Consultant Open 60,000.00 80,004.00 Signed 2020-12-12 2020-10-29 2021-01-30 2021-01-05 2021-02-20 2021-01-26 2021-03-27 2021-01-29 2022-03-27 services to the Minister of Selection Finance LR-MFDP-197179-CS-CDS / 2: Stabilizing and Consultancy for migration of Strengthening Performance of GoL harmonized payroll data IDA / D5060 Post Direct Selection Direct 175,000.00 168,976.40 Signed 2020-08-12 2020-08-26 2020-08-22 2020-08-28 2020-10-26 2020-12-18 2021-04-24 Financial Controls and to Civil Service Management Systems System 2: Stabilizing and LR-MFDP-196996-CS-CDS / Strengthening Performance of Under Consultancy for Migration of IDA / D5060 Post Direct Selection Direct 250,000.00 0.00 2021-03-05 2020-11-10 2021-03-15 2021-05-19 2021-11-15 Financial Controls and Implementation Donor Financed Projects Systems LR-MFDP-201277-CS-CDS / 2: Stabilizing and Consultant to Conduct Gap Strengthening Performance of IDA / D5060 Post Direct Selection Direct 28,000.00 29,655.00 Signed 2020-09-01 2020-10-01 2020-09-11 2020-10-19 2020-11-15 2020-10-23 2021-02-13 Analysis of the Ntional Data Financial Controls and Ware House Systems LR-MFDP-201265-CS-CDS / 3: Improving Public-Sector Consultant to Develop IDA / D5060 Capacity for Enhanced Post Direct Selection Direct 29,655.00 28,000.00 Completed 2020-09-01 2020-10-01 2020-09-11 2020-10-19 2020-11-15 2020-10-23 2021-02-13 2020-12-30 Business Plan, Strategic Plan Oversight and Accountability and Road Map for LICPA LR-MFDP-201983-CS-CDS / 4: Improving Upstream and GAC to Conduct Audit of the Under IDA / D5060 Downstream PFM Systems in Post Direct Selection Direct 20,000.00 0.00 2020-11-16 2020-11-09 2020-11-26 2021-01-30 2021-07-29 Government Harmonized Implementation Selected Sectors Payroll Data LR-MFDP-202587-CS-INDV / Consultant to Conduct Individual 1: Enhancing DRM Sources Under Baseline Review of the Liberia IDA / D5060 Post Consultant Open 75,000.00 0.00 2020-11-18 2020-11-09 2021-01-06 2021-01-27 2021-03-03 2021-08-30 and Systems Implementation Revenue Code as Amended in Selection 2019 LR-MFDP-135409-CS-INDV / 3: Improving Public-Sector Individual Senior Financial Management IDA / V1080 Capacity for Enhanced Post Consultant Open 48,000.00 0.00 Canceled 2019-10-14 2019-10-02 2019-12-02 2020-01-09 2019-12-23 2020-01-27 2021-01-26 Officer Oversight and Accountability Selection LR-MFDP-196975-CS-CDS / 2: Stabilizing and Consultancy to rollout the Strengthening Performance of Civil Service Management IDA / D5060 Post Direct Selection Direct 75,000.00 0.00 Canceled 2021-01-08 2021-01-18 2021-03-24 2021-09-20 Financial Controls and System (CSM) to Internal Systems Audit Agency 2: Stabilizing and LR-MFDP-196978-CS-INDV / Individual Strengthening Performance of Consultant to develop and IDA / D5060 Post Consultant Open 25,000.00 0.00 Canceled 2021-03-04 2021-04-22 2021-05-13 2021-06-17 2021-12-14 Financial Controls and establish risk register in MACs Selection Systems LR-MFDP-196997-CS-INDV / 2: Stabilizing and Individual Consultan to develop content Strengthening Performance of IDA / D5060 Post Consultant Open 50,000.00 0.00 Canceled 2021-02-19 2021-04-09 2021-04-30 2021-06-04 2021-12-01 specific for IFMIS training Financial Controls and Selection strategy for GoL Systems LR-MFDP-197163-CS-INDV / 2: Stabilizing and Consultant to conduct training Individual Strengthening Performance of needs analysis and develop a IDA / D5060 Post Consultant Open 50,000.00 0.00 Canceled 2021-03-21 2021-05-09 2021-05-30 2021-07-04 2021-12-31 Financial Controls and annual training program for Selection Systems IFMIS end users and ICT staff LR-MFDP-201275-CS-INDV / Individual Consultant to Review, Finalize, 1: Enhancing DRM Sources IDA / D5060 Post Consultant Open 75,000.00 0.00 Canceled 2020-11-02 2020-11-09 2020-12-21 2021-01-11 2021-02-15 2021-08-14 and validate existing VAT and Systems Selection Implementation Document LR-MFDP-236434-CS-CDS / 2: Stabilizing and Consultancy for IFMIS Dark Strengthening Performance of Under Fiber Connectivity Network IDA / D5060 Post Direct Selection Direct 175,000.00 0.00 2021-06-08 2021-06-10 2021-06-18 2021-08-22 2022-08-23 Financial Controls and Implementation and Data Center Co-location Systems Services Page 6 LR-MFDP-236435-CS-CDS / Consultant to Develop 2: Stabilizing and Application Programming Strengthening Performance of IDA / D5060 Post Direct Selection Direct 150,000.00 0.00 Under Review 2021-06-10 2021-06-10 2021-06-20 2021-08-24 2022-02-20 interface between IFMIS, Financial Controls and Revenue System, and the EFT Systems System Page 7 Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan: December, 2016 2. Date of General Procurement Notice: 3. Period covered by this procurement plan: Jan 2017 to June 2018 II. Goods, Works, Consultant and Non-Consulting Services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Type of Procurement Prior Review Comments Threshold (PRT) US$ (Millions) 1. Works (Including turnkey, supply & 5 High risk installation of plant and equipment and PPP) 2. (Goods; Information Technology & 1.5 High risk Non-Consulting Services) 3. Consultant Services (Firms) 0.5 High risk 4. Consultant Services (Individual 0.2 High risk Consultants) 2. Prequalification. NA 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: NA 4. Reference to (if any) Project Operational/Procurement Manual: Available in Project files 5. Any Other Special Procurement Arrangements: NA 6. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 7. All TORs for the procurement of consultants services irrespective of the estimated cost of the assignment shall be reviewed and cleared by the TTL 8. Operating expenditures are neither subject to the Procurement and Consultant Guidelines nor prior or post reviews. Operating expenditures are normally verified by TTLs and FM specialists and obtained using the Borrower’s national procurement and administrative procedures. January 11, 2018 9. Renewal or extension of individual consultant’s contracts hired for technical assistance and which are intended for a long-term period but signed for an initial period shorter than the duration of the project, and that have been prior reviewed, do not require procurement clearance if there is no substantial change in the terms and conditions of the contract. January 11, 2018 PROCUREMENT Kenya : Kenya Climate Smart Agriculture Project PLAN General Information Country: Kenya Bank’s Approval Date of the Original Procurement Plan: 2019-10-02 2021-05-20 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P154784 GPN Date: 2018-02-08 Project Name: Kenya Climate Smart Agriculture Project Loan / Credit No: IDA / 59450 E Executing Agency(ies): lgeyo Marakwet County WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned KE-ELGEYO MARAKWET - 168108-CW-RFQ / Component 1: Upscaling REHABILITATION OF KALWAL Climate-Smart Agricultural Pending Request for Single Stage - One 2020-09- WATER PAN- IDA / 59450 Practices (US$163.8 million Post Limited 186,963.00 0.00 Implementat 2020-04-20 2020-06-15 Quotations Envelope 13 EXPANSION,FENCING,PIPE equivalent, of which IDA ion WORK,CATTLE TROUGH AND US$150.0 million eq uivalent) LATRINE KE-ELGEYO MARAKWET - 168110-CW-RFB / Component 1: Upscaling CONSRUCTION OF CHUGOR- Climate-Smart Agricultural Pending KAPTORA IRRIGATION SCHEME- Single Stage - One 2020-11- IDA / 59450 Practices (US$163.8 million Post Request for Bids Open - National 203,419.00 0.00 Implementat 2020-04-15 2020-04-20 2020-06-01 2020-07-01 2020-08-05 INTAKE WORKS,MASONRY Envelope 03 equivalent, of which IDA ion TANK,PIPE US$150.0 million eq uivalent) WORK,FENCING,CANAL LINING AND AGRICULTURAL INPUTS KE-ELGEYO MARAKWET - 171973-CW-RFB / DESILTING Component 1: Upscaling OF KONDABILET HARAMBEE Climate-Smart Agricultural Under Single Stage - One 2020-11- DAM,CONSTRUCTION OF DAM IDA / 59450 Practices (US$163.8 million Post Request for Bids Limited 214,765.00 0.00 Implementat 2020-05-11 2019-03-05 2020-05-16 2019-03-05 2020-06-27 2020-07-27 2020-08-31 Envelope 29 ACCESSORIES(CATTLE equivalent, of which IDA ion TROUGH,LATRINE,PIPELINE US$150.0 million eq uivalent) AND FENCING Component 1: Upscaling KE-ELGEYO MARAKWET - Climate-Smart Agricultural Pending 171976-CW-RFB / Single Stage - One 2020-11- IDA / 59450 Practices (US$163.8 million Post Request for Bids Limited 257,667.00 0.00 Implementat 2020-05-11 2020-05-16 2020-06-27 2020-07-27 2020-08-31 COMPLETION OF KONDABILET Envelope 29 equivalent, of which IDA ion HARAMBEE DAM US$150.0 million eq uivalent) KE-ELGEYO MARAKWET - Component 1: Upscaling 235416-CW-RFQ / Climate-Smart Agricultural Pending ENHANCEMENT OF WATER Request for Single Stage - One Other (with field 2021-11- IDA / 59450 Practices (US$163.8 million Post Limited 136,600.00 0.00 Implementat 2021-06-02 2021-07-28 SUPPLY TO KIPCHUKUKUU Quotations Envelope for explanation) 25 equivalent, of which IDA ion IRRIGATION SCHEME IN US$150.0 million eq uivalent) EMSOO WARD KE-ELGEYO MARAKWET - Component 1: Upscaling 235419-CW-RFQ / Climate-Smart Agricultural Pending REHABILITATION,TESTING Request for Single Stage - One Other (with field 2021-11- IDA / 59450 Practices (US$163.8 million Post Limited 99,121.80 0.00 Implementat 2021-06-02 2021-07-28 AND COMMISSIONING OF Quotations Envelope for explanation) 25 equivalent, of which IDA ion KALWAL-KAPENDICH WATER US$150.0 million eq uivalent) PAN IN SOY SOUTH GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 1: Upscaling Climate-Smart Agricultural KE-ELGEYO MARAKWET - Single Stage - One IDA / 59450 Practices (US$163.8 million Post Request for Bids Open - National 1,000,000.00 0.00 Canceled 2019-10-02 2019-10-07 2019-11-18 2019-12-18 2020-02-07 2020-02-21 137323-GO-RFB / computers Envelope equivalent, of which IDA US$150.0 million eq uivalent) KE-ELGEYO MARAKWET - Component 1: Upscaling 181444-GO-RFB / Climate-Smart Agricultural Pending Single Stage - One VACCINATION OF DAIRY IDA / 59450 Practices (US$163.8 million Post Request for Bids Limited 150,000.00 0.00 Implementati 2020-07-01 2020-07-06 2020-07-27 2020-08-26 2020-08-28 2020-10-27 Envelope COWS/HEIFERS AGAINST EAST equivalent, of which IDA on COAST FEVER DISEASE US$150.0 million eq uivalent) KE-ELGEYO MARAKWET - 194107-GO-RFQ / SUPPLY,DELIVERY AND Component 1: Upscaling INSTALLATION OF THREE IN Climate-Smart Agricultural Pending Request for Single Stage - One NUMBER SOLAR IRRIGATION IDA / 59450 Practices (US$163.8 million Post Limited 4,225.00 0.00 Implementati 2020-09-26 2020-10-21 2020-12-20 Quotations Envelope KITS FOR DEMONSTRATION equivalent, of which IDA on TO FARMER GROUPS IN US$150.0 million eq uivalent) SENGWER,SOY SOUTH AND ENDO WARDS. KE-ELGEYO MARAKWET - 235405-GO-RFQ / PURCHASE Component 4: Project OF NINE MOTORCYCLES FOR Coordination and Pending USE IN MARKET DATA Management (US$29.3 Request for Single Stage - One IDA / 59450 Post Limited 40,500.00 0.00 Implementati 2021-05-30 2021-07-25 2021-09-23 COLLECTION AND SUPPORT million equivalent, of which Quotations Envelope on EXTENSION SERVICES.THE IDA US$20.0 million MODEL IS DT175 OF 151- equivalent) 185CC NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Page 1 Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 2 Plan de Passation de marchés I. Généralités 1. L'information sur le projet : Pays : Madagascar ; Emprunteur : République de Madagascar ; Nom de projet : Projet Filets Sociaux de Sécurité – Financement Additionnel (P160 544) ; Numéro du Crédit : D1450-MG ; Agence d’exécution du Projet : Unité Programme National de Nutrition Communautaire. 2. Date d’approbation du Plan de passation de marchés par la Banque : - ; Révision : - ; 3. Date de notification du Plan Général de Passation de marchés : - ; 4. Période couverte par le Plan de Passation de marchés : DOUZE (12) mois. II. Biens et Travaux et Services hors consultants 1. Seuil de Revue préalable : Les décisions de passation de marchés sujet aux revues préalables de la Banque comme indiqué dans le paragraphe 3.1 de l'Annexe II du Règlement de Passation des Marchés pour les Emprunteurs sollicitant le Financement de Projets d’Investissement (Juillet 2016) et sur la base de l'évaluation de la capacité de l'agence d’exécution : Seuil de Méthode de Passation de revue à Commentaires marchés priori (USD) Les montants 1 Biens : AOI/AON/UN/ED 2 000 000 estimatifs des marchés prévus 2 Travaux : AOI/AON/ED 10 000 000 sont au-dessous des seuils. Niveau de Services autres que 3 2 000 000 risque : consultants : AOI/AON/UN/ED « SUBSTANTIEL » 2. Pré-qualification (selon les dispositions des paragraphes 6.19 à 6.24 de la Section VI du Règlement de Passation des Marchés pour les Emprunteurs sollicitant le Financement de Projets d’Investissement (Juillet 2016)) : Non Applicable. 3. Procédures proposées pour les composantes CDD (selon le paragraphe. 6.52 et 6.53 de la Section VI du Règlement de Passation des Marchés pour les Emprunteurs sollicitant le Financement de Projets d’Investissement (Juillet 2016)) : Non Applicable 4. Référence (s’il y en a) au Manuel d’exécution du projet / Manuel de Passation de marchés : Manuels en cours de mise à jour 5. Tout autre arrangement spécial en passation de marchés : Non Applicable. 6. Allotissement de fournitures avec méthodes et calendrier : [Enumérer d’abord les allotissements qui nécessitent la revue préalable de la Banque, ensuite les autres allotissements] 1 2 3 4 5 6 7 8 9 Réf. No Description Contrat Approche/Méthod Revue de la Coût Pré- Préféren Date Commentaire e de sélection Banque (à estimatif qualificati ce prévue s priori / à (USD) on nationale d’ouverture posteriori) Oui / Non Oui / Non des soumission s Lot 1 : N°9 : Impression et Achevée multiplication de bulletins LIMITE 01 A.11 COT Post 12 000,00 NON NON 21-juin-18 Lot 2 : N°10 : en périodiques (02 numéros NATIONAL attente semestrielles) Maquette Acquisition outils de LIMITE Ordre de Service 03 A.11 COT Post 10 000,00 NON NON 13-mai-18 communication (Pagnes) NATIONAL signé Acquisition divers Pas encore LIMITE 04 A.17 équipements et mobiliers COT Post 5 000,00 NON NON 14-févr-19 lancée NATIONAL de bureau A programmer Acquisition de 293,2 SELECTION 1 475 246 Nouvelle activité 05 A.13 ED Post NON NON 12-févr-19 tonnes de Plumpy Sup DIRECTE ,46 PTA 2019 Acheminement vers LIMITE Nouvelle activité 06 A.13 Districts de 293,2 tonnes COT Post 77 644,55 NON NON 19-févr-19 NATIONAL PTA 2019 de Plumpy Sup Confection d’outils pour les sites : impression et LIMITE Nouvelle activité A.6.0 COT Post 11 812,50 NON NON 04-juin-19 livraison d’outils de NATIONAL PTA 2019 gestion : Registres Confection de plaques d'indication des sites et A.11.0 Supports de LIMITE Nouvelle activité COT Post 27 514,03 NON NON 04-juin-19 .1 communication : NATIONAL PTA 2019 Impression plaque, livrets et bulletins périodiques 1 2 3 4 5 6 7 8 9 Réf. No Description Contrat Approche/Méthod Revue de la Coût Pré- Préféren Date Commentaire e de sélection Banque (à estimatif qualificati ce prévue s priori / à (USD) on nationale d’ouverture posteriori) Oui / Non Oui / Non des soumission s Confection de Pagnes et A.11.0 T-shirt, Blouses pour LIMITE 17 578,13 Nouvelle activité .2 COT Post NON NON 04-juin-19 intervenants (Reny NATIONAL PTA 2019 mavitrika, …) Acquisition de matériels informatiques adaptés à l'actualisation du SIG et LIMITE Nouvelle activité A.14 COT Post 13 312,50 NON NON 04-juin-19 du développement du NATIONAL PTA 2019 Géoportail des données en ligne III. Sélection de consultants 1. Seuil de Revue Préalable : Décisions de sélection sujet à la revue préalable de la Banque comme indiqué dans le paragraphe 3 de l'Annexe II du Règlement de Passation des Marchés pour les Emprunteurs sollicitant le Financement de Projets d’Investissement (Juillet 2016) : Méthode de sélection Seuil de Commentaires revue à priori (USD) 1. Méthode compétitive (firmes) 1 000 000 Les montants 2. Entente directe (firmes) 1 000 000 estimatifs des 3. Méthode compétitive (Consultant 300 000 contrats prévus individuel) sont au-dessous 4. Entente directe (Consultant 300 000 des seuils. individuel) Niveau de risque : « SUBSTANTIEL » 2. Liste restreinte composée entièrement de consultants nationaux : Selon les dispositions du paragraphe 7.25 de l'Annexe II du Règlement de Passation des Marchés pour les Emprunteurs sollicitant le Financement de Projets d’Investissement (Juillet 2016), la liste restreinte de consultants peut comporter entièrement des consultants nationaux pour les cas suivants : Catégorie de Montant estimatif consultant 1. Firmes Inférieur à USD 300 000 2. Consultants individuels Inférieur à USD 100 000 3. Tout autre arrangement spécial de Sélection de consultants : Non applicable 4. Tâches de consultation avec des méthodes de sélection et calendrier 1 2 3 4 5 6 7 Réf. No Description des missions Approche/Méth Revue de la Coût Date Commentaires ode de Banque (à estimatif prévue de sélection priori / à (USD) soumission posteriori) s des proposition s Consultant en charge de la maintenance Nouvelle activité PTA 01 A.14 ED ED Post 12 000,00 29-avril-19 du système Géoportail 2019 Consultants chargés de saisie des Nouvelle activité PTA 02 A.16 Registres des sites ED ED Post 34 321,33 20-mai-19 2019 Consultant Individuel en charge de Nouvelle activité PTA 03 B.2 l’élaboration de l’ICR INDV ED Post 5 000,00 21-mai-19 2019 IV. Activités de renforcement de capacités de l’Agence d’exécution avec calendrier 1. Dans cette section, les activités de renforcement de capacité acceptées (quelques articles pourraient être des recommandations de CPAR) sont énumérées avec le calendrier No. Résultats Coût Durée Date de Commentaires escomptés / estimatif estimative début Description de l’activité PROCUREMENT Madagascar : Improving Nutrition Outcomes using the Multiphase Programmatic Approach PLAN General Information Country: Madagascar Bank’s Approval Date of the Original Procurement Plan: 2018-05-30 2021-05-22 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P160848 GPN Date: 2020-09-07 Project Name: Improving Nutrition Outcomes using the Multiphase Programmatic Approach Loan / Credit No: IDA / D2570, IDA / V0970 H Executing Agency(ies): EALTH PROJECT COORDINATION UNIT - MINISTRY OF HEALTH WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned MG-UCP-191249-CW-RFQ / Scale up coverage and Travaux de construction de Request for Single Stage - One 2021-04- IDA / D2570 utilization of the RMCHN Post Limited 116,433.00 6,518.58 Signed 2020-09-06 2019-10-01 2020-11-01 2019-12-18 283 fosses sécurisées dans Quotations Envelope 30 minimum package les 4 Régions du Projet PARN MG-UCP-01-TRV / Strengthen capacity to Request for Single Stage - One 2020-12- construction de 183 fosses IDA / D2570 manage and deliver the Post Limited 60,390.00 65,591.06 Completed 2020-11-20 2020-12-01 2020-12-16 2021-01-11 Quotations Envelope 31 sécurisées pour le Projet PARN RMCHN minimum package GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MG-UCP-60916-GO-RFQ / Acquisition de mobilier de bureau (table d'ordinateur, Project Management, Request for Single Stage - One table de bureau, armoir de IDA / D2570 Capacity Building and Post Open - National 7,467.00 1,320.46 Signed 2018-06-17 2018-08-12 2019-09-25 2018-11-10 Quotations Envelope rangement, fauteuil de Operations Support direction, chaise visiteur pour UCP et BCCP MG-UCP-61055-GO-DIR / Scale up coverage and Acquérir des plumpy nut pour IDA / D2570 utilization of the RMCHN Post Direct Selection Direct 320,726.00 263,557.20 Completed 2018-07-02 2017-11-06 2018-07-07 2018-08-10 2018-08-21 2019-06-19 2019-02-17 2019-06-19 les CSB minimum package MG-UCP-61587-GO-RFB / Strengthen capacity to Acquérir des Carnet de santé Single Stage - One IDA / D2570 manage and deliver the Post Request for Bids Open - National 369,132.00 196,086.23 Signed 2018-06-18 2019-01-25 2018-06-23 2018-07-23 2019-02-25 2018-08-12 2019-02-26 2018-09-16 2019-05-13 2018-11-15 enfant, Acquérir des Carnets Envelope RMCHN minimum package de santé FE MG-UCP-61593-GO-DIR / Acquisition des lots de Scale up coverage and démarrage en intrants de IDA / D2570 utilization of the RMCHN Post Direct Selection Direct 28,924.00 2,261.90 Completed 2018-06-25 2017-11-06 2018-06-30 2018-09-11 2018-08-19 2018-12-24 2018-10-18 2018-12-24 santé pour les sites minimum package communautaires MG-UCP-61596-GO-DIR / Scale up coverage and Acquisition des lots de IDA / D2570 utilization of the RMCHN Post Direct Selection Direct 168,931.00 282,601.62 Completed 2018-07-02 2017-11-06 2018-07-07 2018-09-11 2018-08-21 2019-03-25 2018-10-20 2019-03-25 démarrage de médicaments minimum package pour les CSB MG-UCP-61602-GO-DIR / Strengthen capacity to Acquisition de véhicule pour IDA / D2570 manage and deliver the Post Direct Selection Direct 153,090.00 167,239.67 Signed 2018-06-18 2017-11-06 2018-06-23 2018-04-24 2018-08-27 2018-11-13 2019-02-23 DRS RMCHN minimum package MG-UCP-61603-GO-DIR / Project Management, Acquisition de voiture 4x4 IDA / D2570 Capacity Building and Post Direct Selection Direct 275,000.00 203,235.91 Signed 2018-06-18 2017-11-06 2018-06-23 2018-04-24 2018-08-27 2018-11-13 2019-02-23 pour BCC/UCP Operations Support MG-UCP-61690-GO-DIR / Acquisition de matériels de Scale up coverage and diagnostic de grossesse pour IDA / D2570 utilization of the RMCHN Post Direct Selection Direct 35,072.00 3,692.68 Signed 2018-06-25 2017-11-06 2018-06-30 2018-09-21 2018-08-19 2018-12-24 2018-10-18 les sites communautaires et minimum package CSB MG-UCP-61800-GO-DIR / Scale up coverage and Acquérir des FAF pour les IDA / D2570 utilization of the RMCHN Post Direct Selection Direct 39,343.00 28,840.82 Completed 2018-07-02 2017-11-06 2018-07-07 2018-09-26 2018-08-21 2018-12-24 2018-10-20 2018-12-24 Femmes enceintes minimum package MG-UCP-61839-GO-RFB / Scale up coverage and Acquisition d'EPI (Equipement Single Stage - One IDA / D2570 utilization of the RMCHN Post Request for Bids Open - National 135,200.00 54,118.59 Completed 2018-06-11 2018-10-01 2018-06-16 2019-06-28 2018-07-16 2018-11-15 2018-08-05 2018-11-22 2018-09-09 2019-03-18 2018-11-08 2019-03-26 de Protection Individuelle) Envelope minimum package pour CSB MG-UCP-61932-GO-DIR / Scale up coverage and Acquisition de motos pour le UN Agencies IDA / D2570 utilization of the RMCHN Post Direct 716,659.00 705,865.63 Signed 2018-06-11 2017-11-06 2018-06-16 2018-04-24 2018-08-05 2018-11-13 2019-02-01 CSB, et pour les Districts à (Direct) minimum package l'UNOPS MG-UCP-61935-GO-DIR / Scale up coverage and Acquérir les réfrigérateurs IDA / D2570 utilization of the RMCHN Post Direct Selection Direct 585,840.00 461,670.12 Completed 2018-07-02 2017-11-06 2018-07-07 2018-09-14 2018-08-26 2018-12-11 2019-02-22 2018-12-11 solaires auprès de DOMETIC minimum package MG-UCP-61939-GO-DIR / Scale up coverage and Acquérir des plaquettes de 10 IDA / D2570 utilization of the RMCHN Post Direct Selection Direct 1,485.00 1,201.25 Completed 2018-07-31 2017-11-06 2018-08-05 2018-10-05 2018-09-09 2018-12-24 2018-11-08 2018-12-24 comprimés de Zinc et sachets minimum package de SRO auprès de la SALAMA MG-UCP-61963-GO-DIR / Scale up coverage and Acquisition des produits IDA / D2570 utilization of the RMCHN Post Direct Selection Direct 157,185.00 133,488.46 Completed 2018-06-27 2017-11-06 2018-07-02 2018-05-22 2018-08-06 2018-12-05 2018-11-04 2018-12-05 contraceptifs auprès de la minimum package SALAMA Page 1 MG-UCP-61966-GO-DIR / Acquisition des tablettes pour les Chefs CSB, des panneaux Strengthen capacity to solaires et matériels IDA / D2570 manage and deliver the Post Direct Selection Direct 579,167.00 493,940.00 Signed 2018-07-18 2017-11-06 2018-07-23 2019-01-30 2018-08-27 2020-06-30 2019-02-23 informatiques pour niveau RMCHN minimum package central - régional et district à UNOPS MG-UCP-61970-GO-DIR / Scale up coverage and Acheter des produits IDA / D2570 utilization of the RMCHN Post Direct Selection Direct 43,503.00 3,298.49 Completed 2018-06-08 2017-11-06 2018-06-13 2018-12-13 2018-07-18 2018-12-24 2018-09-16 2018-12-24 dermatologiques auprès de la minimum package SALAMA MG-UCP-62653-GO-RFB / acquisition des matériels pour la salle de consultation Scale up coverage and Single Stage - One externe, de CPN, IDA / D2570 utilization of the RMCHN Post Request for Bids Open - International 939,128.00 1,066,917.56 Signed 2018-06-18 2019-01-24 2018-06-23 2019-02-04 2018-08-07 2019-03-07 2018-09-06 2019-05-31 2018-10-11 2019-09-10 2019-04-09 Envelope d'accouchement, des minimum package accouchés, DOPLER pour les CSB MG-UCP-62678-GO-RFB / multiplication de document de formation en PCIME clinique, Scale up coverage and Single Stage - One carte conseil PCIME, guides IDA / D2570 utilization of the RMCHN Post Request for Bids Open - National 301,784.00 13,998.13 Completed 2018-07-02 2019-01-25 2018-07-07 2019-06-20 2018-08-06 2019-04-09 2018-08-26 2019-04-09 2018-09-30 2019-08-26 2018-12-29 2019-08-27 Envelope PFI réactualisé, des outils de minimum package gestion CSB, et des carnets de santé FE MG-UCP-62682-GO-RFQ / Scale up coverage and Request for Single Stage - One acquisition de matériels et IDA / D2570 utilization of the RMCHN Post Limited 19,774.00 22,705.33 Signed 2018-07-07 2019-01-28 2018-09-01 2019-04-17 2018-10-31 Quotations Envelope fournitures pour sites minimum package MG-UCP-62692-GO-RFB / acquisition de brassards Scale up coverage and Under Request for Single Stage - One tricolores (MUAC) et montres IDA / D2570 utilization of the RMCHN Post Limited 13,498.00 0.00 Implementati 2018-07-07 2018-12-26 2018-09-01 2018-10-31 Quotations Envelope trotteuses pour sites PCIME minimum package on communautaire MG-UCP-64538-GO-RFQ / Scale up coverage and Request for Single Stage - One Acquisition kit TRO pour site IDA / D2570 utilization of the RMCHN Post Limited 10,540.00 18,798.18 Completed 2018-07-07 2019-01-22 2018-09-01 2019-06-11 2018-10-31 2019-06-11 Quotations Envelope communautaire minimum package Scale up coverage and MG-UCP-64544-GO-DIR / IDA / D2570 utilization of the RMCHN Post Direct Selection Direct 60,000.00 59,925.18 Completed 2018-07-02 2017-11-06 2018-07-07 2018-12-20 2018-08-21 2018-12-24 2018-10-20 2018-12-24 Acquisition PZQ adulte minimum package MG-UCP-64545-GO-RFQ / Scale up coverage and Acquisition matériels Request for Single Stage - One IDA / D2570 utilization of the RMCHN Post Limited 19,774.00 0.00 Canceled 2018-07-07 2018-09-01 2018-10-31 médicaux et fourniture de Quotations Envelope minimum package bureau pour site MG-UCP-62683-GO-RFQ / Scale up coverage and acquisition des mannequins Request for Single Stage - One IDA / D2570 utilization of the RMCHN Post Limited 8,955.00 13,533.98 Completed 2018-07-03 2018-12-26 2018-08-28 2019-08-27 2018-10-27 2019-08-27 pour la formation des agents Quotations Envelope minimum package de santés SONUB MG-UCP-104950-GO-DIR / Project Management, Acquisition de véhicule pour IDA / V0970 Capacity Building and Post Direct Selection Direct 40,000.00 33,574.87 Signed 2019-03-08 2017-10-06 2019-03-09 2018-04-24 2019-03-12 2018-11-13 2019-03-22 DDP Operations Support MG-UCP-106148-GO-RFQ / Project Management, Request for Single Stage - One Doter les CSB en outil de IDA / V0970 Capacity Building and Post Limited 570,492.00 61,821.62 Completed 2019-03-15 2019-01-22 2019-04-21 2019-03-19 2019-04-25 2019-03-19 Quotations Envelope gestion (système Voucher) Operations Support MG-UCP-107047-GO-DIR / Project Management, Acquisition d'un véhicule 4X4 IDA / V0970 Capacity Building and Post Direct Selection Direct 35,821.00 67,335.51 Signed 2019-03-25 2017-10-06 2019-04-09 2019-06-18 2019-06-13 2019-09-13 2019-12-10 pour la CCTN-FBP Operations Support MG-UCP-109325-GO-RFQ / Project Management, Request for Single Stage - One Acquisition kit de retrait IDA / V0970 Capacity Building and Post Limited 7,360.00 31,275.18 Completed 2019-05-14 2019-07-26 2019-07-24 2019-09-25 2020-01-20 2019-09-25 Quotations Envelope Implanon Operations Support Project Management, MG-UCP-111283-GO-RFQ / Request for Single Stage - One IDA / D2570 Capacity Building and Post Limited 2,805.00 31,275.18 Completed 2019-05-20 2019-07-26 2019-07-15 2019-09-25 2020-01-11 2019-09-25 Acquisition kit DIU Quotations Envelope Operations Support MG-UCP-107051-GO-DIR / Acquisition de motocyclette Project Management, pour les EMAD pour la IDA / D2570 Capacity Building and Post Direct Selection Direct 17,910.00 139,246.16 Signed 2019-06-16 2019-03-19 2019-07-01 2019-06-19 2019-09-04 2019-09-13 2020-03-02 réalisation des vérifications de Operations Support la qualité dans les zone inaccesibles MG-UCP-117658-GO-RFQ / Project Management, Acquisition de matériel Request for Single Stage - One IDA / D2570 Capacity Building and Post Limited 15,045.00 35,270.01 Completed 2019-06-10 2019-06-27 2019-08-05 2019-10-07 2020-02-01 2019-10-07 informatique pour les Quotations Envelope Operations Support vérificateurs de la quantité MG-UCP-117662-GO-RFQ / Acquisition mobilier de Project Management, Under bureau des verificateurs de Request for Single Stage - One IDA / D2570 Capacity Building and Post Limited 5,134.00 0.00 Implementati 2019-06-10 2019-06-27 2019-08-05 2020-02-01 quantité (4 tables, 1 armoire, Quotations Envelope Operations Support on 4 chaises, 4 casques par district) FBP MG-UCP-125571-GO-DIR / Project Management, Acquisition de balance pèse IDA / D2570 Capacity Building and Post Direct Selection Direct 31,471.00 18,347.05 Signed 2018-07-12 2018-12-14 2018-08-11 2018-12-17 2018-10-15 2018-12-14 2019-04-13 bébé Operations Support MG-UCP-125581-GO-RFQ / Project Management, Request for Single Stage - One Multiplication les outils de IDA / D2570 Capacity Building and Post Limited 80,984.00 42,531.46 Signed 2019-08-17 2019-09-02 2019-10-12 2019-11-22 2020-04-09 Quotations Envelope gestion des plaintes Operations Support MG-UCP-62675-GO-RFB / Scale up coverage and Single Stage - One acquisition de kit IDA / D2570 utilization of the RMCHN Post Request for Bids Open - International 302,076.00 0.00 Canceled 2018-07-02 2018-11-13 2018-07-07 2018-08-21 2018-09-20 2018-10-25 2019-04-23 Envelope accouchement individuel minimum package MG-UCP-126542-GO-RFQ / Project Management, Pending Request for Single Stage - One Acquisition des 6 motos pour IDA / D2570 Capacity Building and Post Limited 13,433.00 0.00 Implementati 2019-08-13 2019-10-10 2019-12-09 Quotations Envelope les vérificateurs de quantité Operations Support on Page 2 MG-UCP-117653-GO-DIR / Project Management, Acquisition de 8 motocyclette IDA / D2570 Capacity Building and Post Direct Selection Direct 17,910.00 0.00 Canceled 2019-06-16 2019-03-19 2019-06-21 2019-06-19 2019-07-26 2020-01-22 pour les versificateurs de Operations Support quantité MG-UCP-126259-GO-RFQ / Project Management, Single Stage - One Multiplication des cartes IDA / D2570 Capacity Building and Post Request for Bids Open - National 116,065.00 0.00 Canceled 2019-09-02 2019-09-07 2019-10-07 2019-10-22 2019-11-25 2020-05-23 Envelope conseils PCIMEc Operations Support MG-UCP-126264-GO-DIR / Project Management, Acquisition de kit IDA / D2570 Capacity Building and Post Direct Selection Direct 380,446.00 87,761.80 Completed 2018-11-28 2018-11-20 2018-12-13 2018-11-28 2019-02-07 2019-05-23 2019-10-10 2019-05-23 accouchement individuel Operations Support (SALAMA) MG-UCP-135237-GO-RFQ / Project Management, Request for Single Stage - One Multiplication des cartes IDA / D2570 Capacity Building and Post Limited 98,344.00 19,847.78 Signed 2019-09-28 2019-09-02 2019-11-23 2019-11-07 2019-12-23 Quotations Envelope conseils PCIMEc Operations Support MG-UCP-142195-GO-DIR / Contingent Emergency Acquisition d'intrants pour IDA / D2570 Post Direct Selection Direct 7,700.00 183,995.34 Signed 2019-10-23 2019-10-22 2019-10-26 2019-10-24 2019-11-03 2019-10-24 2020-05-01 Response Component (CERC) riposte peste MG-UCP-60706-GO-RFQ / Acquisition de photocopieuse, Project Management, imprimante, vidéo projecteur, Request for Single Stage - One IDA / D2570 Capacity Building and Post Limited 28,314.00 0.00 Canceled 2018-06-15 2018-08-10 2018-10-09 scanner, Desk top, lap top, Quotations Envelope Operations Support imprimante et camera de surveillance pour BCCP et UCP MG-UCP-126620-GO-DIR / Project Management, Acquisition des plumpy nut IDA / D2570 Capacity Building and Post Direct Selection Direct 153,719.00 0.00 Canceled 2019-09-07 2019-09-17 2019-10-22 2019-12-21 pour les CSB (quantité Operations Support restante) MG-UCP-160793-GO-DIR / Scale up coverage and acquisitions de réfrigérateurs IDA / D2570 utilization of the RMCHN Post Direct Selection Direct 1,252,261.00 1,068,660.61 Signed 2020-02-28 2020-02-28 2020-03-04 2020-02-28 2020-04-08 2020-03-12 2020-10-05 solaires destinés aux CSB minimum package MG-UCP-165534-GO-RFB / Fourniture de respirateur pour Contingent Emergency Request for Single Stage - One la prise en charge de qualité IDA / D2570 Post Limited 1,150,000.00 2,807,967.27 Signed 2020-04-03 2020-03-30 2020-04-12 2020-04-01 2020-06-11 Response Component (CERC) Quotations Envelope et humanisée des cas dans les centres de traitement MG-UCP-166613-GO-RFQ / fourniture de gel hydro- alcoolique pour la prise en Contingent Emergency Request for Single Stage - One IDA / D2570 Post Limited 81,081.00 65,246.86 Signed 2020-04-02 2020-03-24 2020-04-09 2020-05-06 2020-05-09 charge de qualité et Response Component (CERC) Quotations Envelope humanisée des cas dans les centres de traitement MG-UCP-167053-GO-RFQ / fourniture de concentrateur d'oxygène pour la prise en Contingent Emergency Request for Single Stage - One IDA / D2570 Post Limited 195,042.00 201,230.69 Signed 2020-04-03 2020-03-30 2020-04-10 2020-04-03 2020-06-09 charge de qualité et Response Component (CERC) Quotations Envelope humanisée des cas dans les centres de traitement MG-UCP-167065-GO-RFQ / fourniture de tentes de désinfection pour la prise en Contingent Emergency Request for Single Stage - One IDA / D2570 Post Limited 328,750.00 78,612.00 Signed 2020-04-04 2020-03-30 2020-04-10 2020-05-27 2020-06-09 charge de qualité et Response Component (CERC) Quotations Envelope humanisée des cas dans les centres de traitement MG-UCP-167062-GO-RFQ / Contingent Emergency Request for Single Stage - One fourniture de radiographie IDA / D2570 Post Limited 4,500,000.00 2,272,493.32 Signed 2020-04-02 2020-03-23 2020-04-09 2020-03-27 2020-06-08 Response Component (CERC) Quotations Envelope numérique MG-UCP-167056-GO-RFQ / fourniture de tentes "negative pressure isolation" pour la Contingent Emergency Request for Single Stage - One IDA / D2570 Post Limited 983,650.00 55,530.00 Signed 2020-04-03 2020-04-06 2020-04-10 2020-05-27 2020-06-09 prise en charge de qualité et Response Component (CERC) Quotations Envelope humanisée des cas dans les centres de traitement MG-UCP-166608-GO-DIR / Fourniture de masques FFP2 Contingent Emergency pour la prise en charge de IDA / D2570 Post Direct Selection Direct 645,000.00 0.00 Canceled 2020-03-31 2020-04-02 2020-04-07 2020-06-06 Response Component (CERC) qualité et humanisée des cas dans les centres de traitement MG-UCP-166609-GO-DIR / fourniture de combinaison Contingent Emergency pour la prise en charge de IDA / D2570 Post Direct Selection Direct 350,200.00 0.00 Canceled 2020-03-31 2020-04-02 2020-04-07 2020-06-06 Response Component (CERC) qualité et humanisée des cas dans les centres de traitement MG-UCP-166611-GO-DIR / fourniture de lunettes de protection pour la prise en Contingent Emergency IDA / D2570 Post Direct Selection Direct 16,068.00 0.00 Canceled 2020-03-31 2020-04-02 2020-04-07 2020-06-06 charge de qualité et Response Component (CERC) humanisée des cas dans les centres de traitement MG-UCP-177369-GO-RFQ / Contingent Emergency Request for Single Stage - One Acquisition de 1 000 000 IDA / D2570 Post Limited 875,000.00 2,997,714.75 Signed 2020-06-22 2020-04-02 2020-07-17 2020-04-14 2020-09-15 Response Component (CERC) Quotations Envelope masques FFP2 MG-UCP-177361-GO-RFQ / Contingent Emergency Request for Single Stage - One acquisition de 15 000 IDA / D2570 Post Limited 350,200.00 500,481.34 Signed 2020-06-21 2020-03-30 2020-07-05 2020-04-03 2020-09-03 Response Component (CERC) Quotations Envelope combinaison de protection MG-UCP-177370-GO-RFQ / Contingent Emergency Request for Single Stage - One Acquisition des masques IDA / D2570 Post Limited 700,000.00 818,181.00 Signed 2020-06-22 2020-03-30 2020-07-17 2020-04-03 2020-09-15 Response Component (CERC) Quotations Envelope chirurgicaux à 3 plis MG-UCP-177367-GO-RFQ / Contingent Emergency Request for Single Stage - One acquisition des 2 600 lunettes IDA / D2570 Post Limited 10,010.00 9,757.00 Completed 2020-06-21 2020-03-30 2020-08-07 2020-04-02 2021-02-03 2020-04-10 Response Component (CERC) Quotations Envelope de protection Page 3 MG-UCP-186168-GO-RFQ / Contingent Emergency Request for Single Stage - One acquisition de médicaments IDA / D2570 Post Limited 1,000,000.00 23,959.97 Signed 2020-08-02 2020-05-21 2020-08-27 2020-06-18 2020-09-26 Response Component (CERC) Quotations Envelope pour la riposte au Covid-19 MG-UCP-186097-GO-RFQ / Contingent Emergency Request for Single Stage - One acquisition de 1000 IDA / D2570 Post Limited 459,200.00 459,200.00 Completed 2020-08-19 2020-07-13 2020-09-02 2020-07-28 2020-09-17 2020-08-15 Response Component (CERC) Quotations Envelope concentrateurs d'oxygène MG-UCP-186082-GO-DIR / Acquisition de 64 respirateurs Pending Contingent Emergency UN Agencies pour la lutte contre la IDA / D2570 Post Direct 23,100.00 0.00 Implementati 2020-08-25 2020-08-30 2020-09-08 2020-11-07 Response Component (CERC) (Direct) pandémie Covid-19 à on Madagascar MG-UCP-186067-GO-DIR / Pending Acquisition des ambulances Contingent Emergency UN Agencies IDA / D2570 Post Direct 595,000.00 0.00 Implementati 2020-08-25 2020-08-30 2020-09-03 2020-10-03 médicalisées pour la lutte Response Component (CERC) (Direct) on contre la pandemie Covid-19 MG-UCP-187215-GO-RFB / Scale up coverage and acquisition de matériels pour Single Stage - One IDA / D2570 utilization of the RMCHN Prior Request for Bids Open - International 5,193,895.00 3,482,700.18 Signed 2020-08-27 2020-10-21 2020-09-01 2020-10-22 2020-10-01 2020-12-03 2020-10-31 2021-03-15 2020-11-21 2021-06-16 2021-02-04 les CSB du projet PARN, Envelope minimum package répartis en quatre lots MG-UCP-64549-GO-RFQ / Scale up coverage and Request for Single Stage - One Acquisition Poster et IDA / D2570 utilization of the RMCHN Post Limited 10,906.00 0.00 Canceled 2018-07-07 2018-09-01 2018-10-31 Quotations Envelope banderole minimum package MG-UCP-62686-GO-RFQ / Project Management, acquisition de tableau Request for Single Stage - One IDA / D2570 Capacity Building and Post Limited 6,000.00 0.00 Canceled 2018-06-16 2018-08-11 2018-10-10 d'affichage et socle Quotations Envelope Operations Support cartographie pour l'UCP MG-UCP-107055-GO-RFQ / Multiplication des kits de Project Management, démarrage en outils de Request for Single Stage - One IDA / V0970 Capacity Building and Post Open - National 63,194.00 0.00 Canceled 2019-04-09 2019-06-11 2019-12-08 gestion FBP et document Quotations Envelope Operations Support d'information plaidoyer sur le FBP MG-UCP-219306-GO-RFB / Scale up coverage and Pending Single Stage - One Fourniture de produits IDA / D2570 utilization of the RMCHN Post Request for Bids Open - National 104,863.61 0.00 Implementati 2021-02-17 2021-03-19 2021-04-30 2021-05-30 2021-07-04 2021-12-31 Envelope contraceptifs LEVOPLANT minimum package on MG-UCP-216107-GO-RFQ / Project Management, Fourniture de matériels Request for Single Stage - One IDA / D2570 Capacity Building and Post Limited 4,096.12 4,367.46 Signed 2021-02-25 2020-11-20 2021-04-13 2021-02-11 2021-06-12 informatiques pour la SDSP Quotations Envelope Operations Support Arivonimamo MG-UCP-217561-GO-RFQ / Project Management, Multiplication des Outils de Request for Single Stage - One IDA / D2570 Capacity Building and Post Limited 96,000.00 76,466.24 Signed 2021-02-13 2021-01-20 2021-03-22 2021-03-22 2021-04-21 Gestion Voucher pour 7 Quotations Envelope Operations Support Régions MG-UCP-216242-GO-RFQ / Project Management, Request for Single Stage - One Acquisition ds conteneurs IDA / D2570 Capacity Building and Post Limited 10,447.76 22,975.64 Signed 2021-02-16 2021-02-09 2021-03-30 2021-03-09 2021-04-29 Quotations Envelope pour les 7 régions PARN Operations Support MG-UCP-215575-GO-RFQ / Project Management, acquisition des kits IDA / D2570 Capacity Building and Post Direct Selection Direct 570,967.78 247,521.49 Signed 2021-01-22 2021-01-29 2021-01-29 2020-11-10 2021-02-22 2019-02-28 2021-06-22 individuels d'accouchement Operations Support (KIA) pour l'année 2021 MG-UCP-220988-GO-RFQ / Acquisition des plaquettes de Project Management, Request for Single Stage - One 10 comprimés de Zinc et SRO IDA / D2570 Capacity Building and Post Limited 14,392.00 16,970.10 Signed 2021-03-20 2021-03-02 2021-05-16 2019-02-28 2021-07-15 Quotations Envelope pour Analamanga et Alaotra Operations Support Mangoro MG-UCP-221732-GO-RFQ / Acquisition des kits TRO pour Scale up coverage and les CSB et les sites Request for Single Stage - One IDA / D2570 utilization of the RMCHN Post Limited 35,000.00 11,842.52 Signed 2021-03-10 2021-03-02 2021-05-05 2021-06-04 2021-11-01 communautaires dans les Quotations Envelope minimum package régions Analamanga et Alaotra Mangoro MG-UCP-221736-GO-RFQ / Acquisition des montres Scale up coverage and trotteuses pour les CSB et Request for Single Stage - One IDA / D2570 utilization of the RMCHN Post Open - National 12,056.34 5,416.52 Signed 2021-04-03 2021-03-25 2021-06-06 2021-06-02 2021-07-06 sites communautaires dans Quotations Envelope minimum package les régions Analamanga et Alaotra Mangoro MG-UCP-233728-GO-DIR / Scale up coverage and Acquisition de 132 motos IDA / D2570 utilization of the RMCHN Post Direct Selection Direct 331,200.00 292,763.76 Signed 2021-05-17 2021-05-18 2021-05-27 2021-05-06 2021-07-03 2021-05-27 2021-09-01 pour les CSB minimum package MG-UCP-224326-GO-RFQ / Acquisition des brassards Scale up coverage and tricolores (MUAC) pour les Request for Single Stage - One IDA / D2570 utilization of the RMCHN Post Open - National 9,946.83 4,212.90 Signed 2021-06-07 2021-06-15 2021-08-17 2021-05-27 2021-09-16 sites communautaires pour Quotations Envelope minimum package les régiosn Analamanga et Alaotra Mangoro MG-UCP-233731-GO-RFQ / acquisition d'un véhicule 4x4 Scale up coverage and Under Request for Single Stage - One pour le Service Sauvegarde et IDA / D2570 utilization of the RMCHN Post Open - National 46,000.00 0.00 Implementati 2021-06-26 2021-06-23 2021-09-04 2021-10-19 Quotations Envelope Environnemental du Ministère minimum package on de al Santé Publique NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Scale up coverage and Under MG-UCP-64542-NC-DIR / IDA / D2570 utilization of the RMCHN Post Direct Selection Direct 645,310.00 0.00 Implementati 2018-06-11 2018-06-16 2018-07-31 2023-07-05 Frais de prestation SALAMA minimum package on Page 4 MG-UCP-127119-NC-RFQ / Project Management, Request for Single Stage - One Location de voiture pour IDA / D2570 Capacity Building and Post Limited 11,172.00 0.00 Canceled 2019-09-02 2019-10-10 2020-04-07 Quotations Envelope acheminement OG Plainte Operations Support MG-UCP-179385-NC-RFB / Strengthen capacity to Single Stage - One multiplication des outils de IDA / D2570 manage and deliver the Post Request for Bids Open - National 397,361.52 170,988.41 Signed 2020-06-16 2020-06-03 2020-06-21 2020-10-02 2020-08-02 2020-07-03 2020-09-01 2020-08-11 2020-10-06 2020-08-25 2020-10-16 Envelope gestion répartis en dix lots RMCHN minimum package MG-UCP-235249-NC-RFB / Scale up coverage and Under Travaux de multiplication des Single Stage - One IDA / D2570 utilization of the RMCHN Post Request for Bids Open - National 261,341.00 0.00 Implementati 2021-06-09 2021-06-01 2021-06-19 2021-06-15 2021-07-19 2021-08-02 2021-08-23 2021-09-22 outils de gestion destinés au Envelope minimum package on Ministère de la Santé Publique MG-UCP-233619-GO-RFQ / travaux de multiplication des Scale up coverage and Pending cartes conseils et documents Request for Single Stage - One IDA / D2570 utilization of the RMCHN Post Open - National 55,444.00 0.00 Implementati 2021-06-10 2021-08-09 2021-09-08 de formations PCIME Clinique Quotations Envelope minimum package on destinés aux sites communautaires et aux CSB MG-UCP-239643-GO-RFQ / Scale up coverage and Under Request for Single Stage - One confection de tee shirt pour la IDA / D2570 utilization of the RMCHN Post Open - National 13,432.84 0.00 Implementati 2021-06-27 2021-06-23 2021-09-09 2021-09-15 Quotations Envelope gestion de plainte minimum package on CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MG-UCP-63926-CS-CQS / Project Management, Consultant Cabinet de recrutement IDA / D2570 Capacity Building and Post Qualification Open - National 7,000.00 5,818.35 Signed 2018-05-23 2018-05-30 2018-05-23 2018-07-06 2018-07-19 2018-08-05 2018-08-10 2018-09-09 2018-10-11 2019-03-08 personnel restant de l'UCP Operations Support Selection MG-UCP-64962-CS-QCBS / Strengthen capacity to Elaborer le document Quality And Cost- IDA / D2570 manage and deliver the Post Open - National 14,155.00 0.00 Canceled 2018-06-07 2018-06-07 2018-06-28 2018-06-20 2018-07-27 2018-08-26 2018-09-15 2018-10-20 2018-11-24 2019-01-23 d'assistance technique en Based Selection RMCHN minimum package partenariat et investissement MG-UCP-87556-CS-LCS / Project Management, Least Cost Under audit des comptes des 2 IDA / D2570 Capacity Building and Post Open - National 15,000.00 0.00 2018-12-03 2018-12-04 2018-12-03 2018-12-17 2018-12-12 2019-01-14 2019-01-11 2019-01-29 2019-01-18 2019-02-27 2019-03-01 2019-04-03 2019-09-30 Selection Implementation UMOP pour l'année 2018 Operations Support MG-UCP-92289-CS-CDS / Project Management, UN Agencies assistance technique de IDA / D2570 Capacity Building and Prior Direct 4,641,998.00 4,641,998.00 Signed 2018-12-26 2019-01-31 2019-02-04 2019-03-11 2019-03-11 2019-03-26 2024-12-31 (Direct) l'UNICEF Operations Support MG-UCP-95218-CS-CDS / Project Management, UN Agencies Appui technique de l'OMS IDA / D2570 Capacity Building and Prior Direct 1,822,067.00 1,822,067.00 Signed 2019-02-04 2019-12-06 2019-02-15 2019-07-08 2019-02-20 2019-09-19 2021-02-19 (Direct) pour les sytème SIS Operations Support MG-UCP-104972-CS-CDS / Project Management, Consultant Contractualiser de personnel Pending IDA / V0970 Capacity Building and Post Qualification Open - National 688,977.00 0.00 2019-03-13 2019-04-03 2019-05-17 2019-06-16 2019-07-21 2020-01-17 de santé (Médecins, Implementation Operations Support Selection Paramédicaux) MG-UCP-109311-CS-CQS / Recrutement de deux Project Management, Consultant vérificateurs de la quantité IDA / V0970 Capacity Building and Post Qualification Open - National 4,567.00 0.00 Canceled 2019-04-09 2019-04-24 2019-05-23 2019-05-30 2019-06-07 2019-12-04 dans la Région de Haute Operations Support Selection Matsiatra MG-UCP-107065-CS-CQS / Project Management, Consultant Recrutement de deux IDA / V0970 Capacity Building and Post Qualification Open - National 7,164.00 0.00 Canceled 2019-04-09 2019-04-30 2019-05-22 2019-05-29 2019-06-12 2019-12-09 vérificateurs au niveau UCP Operations Support Selection MG-UCP-109225-CS-CQS / Recrutement de deux Project Management, Consultant vérificateurs de la quantité IDA / V0970 Capacity Building and Post Qualification Open - National 4,567.00 0.00 Canceled 2019-04-09 2019-04-24 2019-05-16 2019-05-23 2019-05-31 2019-11-27 dans la Région d'Amoron'i Operations Support Selection Mania MG-UCP-107045-CS-CQS / Project Management, Consultant Recrutement de deux IDA / V0970 Capacity Building and Post Qualification Open - National 4,567.00 0.00 Canceled 2019-04-09 2019-04-24 2019-05-16 2019-05-23 2019-06-01 2019-11-28 vérificateurs de la quantité Operations Support Selection dans la Région d'Itasy MG-UCP-109318-CS-CQS / Project Management, Consultant Recrutement d'un Assistant IDA / V0970 Capacity Building and Post Qualification Open - National 3,582.00 0.00 Canceled 2019-04-09 2019-04-15 2019-04-30 2019-05-22 2019-05-29 2019-06-12 2019-12-09 technique Voucher au niveau Operations Support Selection GCR dans la Région d'Itasy MG-UCP-109320-CS-CQS / Recrutement d'un Assistant Project Management, Consultant technique Voucher au niveau IDA / V0970 Capacity Building and Post Qualification Open - National 3,582.00 0.00 Canceled 2019-04-09 2019-04-15 2019-04-30 2019-05-22 2019-05-29 2019-06-12 2019-12-09 GCR dans la Région Operations Support Selection d'Amoron'i Mania MG-UCP-107068-CS-CQS / Recrutement d'un Assistant Project Management, Consultant technique Voucher au niveau IDA / V0970 Capacity Building and Post Qualification Open - National 3,582.00 0.00 Canceled 2019-03-25 2019-04-15 2019-04-15 2019-05-21 2019-05-28 2019-06-14 2019-12-11 GCR dans la Région de Haute Operations Support Selection Matsiatra MG-UCP-109198-CS-CQS / Recrutement de deux Project Management, Consultant vérificateurs de la quantité IDA / V0970 Capacity Building and Post Qualification Open - National 4,567.00 0.00 Canceled 2019-04-09 2019-04-24 2019-05-16 2019-05-23 2019-06-01 2019-11-28 dans la Région de Operations Support Selection Vakinakaratra MG-UCP-109319-CS-CQS / Recrutement d'un Assistant Project Management, Consultant technique Voucher au niveau IDA / V0970 Capacity Building and Post Qualification Open - National 3,582.00 0.00 Canceled 2019-04-09 2019-04-15 2019-04-30 2019-05-22 2019-05-29 2019-06-12 2019-12-09 GCR dans la Région de Operations Support Selection Vakinakaratra Page 5 MG-UCP-163629-CS-CDS / financement du plan de Project Management, UN Agencies contingence national pour la IDA / D2570 Capacity Building and Prior Direct 3,700,000.00 3,700,000.00 Signed 2020-03-07 2020-03-11 2020-04-16 2020-03-16 2020-05-21 2020-03-12 2020-11-17 (Direct) préparation et riposte à Operations Support l'épidémie de coronavirus MG-UCP-179476-CS-QCBS / Project Management, Quality And Cost- Under Sélection d'une agence IDA / D2570 Capacity Building and Post Open - National 47,761.19 86,552.75 2020-06-15 2020-06-12 2020-07-06 2020-09-21 2020-08-19 2020-10-09 2020-09-16 2020-11-19 2020-10-16 2020-11-20 2020-11-20 2020-12-15 2020-12-25 2021-12-25 Based Selection Implementation fiduciaire pour l'UCP Operations Support MG-UCP-157297-CS-QCBS / Project Management, Quality And Cost- sélection d'une agence IDA / D2570 Capacity Building and Post Open - International 47,761.19 0.00 Canceled 2020-02-06 2019-12-05 2020-02-27 2020-04-11 2020-02-14 2020-05-09 2020-03-16 2020-06-08 2020-05-05 2020-07-13 2020-08-17 2021-08-17 Based Selection fiduciaire Operations Support MG-UCP-215578-CS-QCBS / Sélection d'une firme chargée Strengthen capacity to de la réalisation de l'enquête Quality And Cost- IDA / D2570 manage and deliver the Post Open - National 430,000.00 365,555.18 Signed 2021-01-22 2019-11-28 2021-02-12 2021-02-09 2021-02-26 2020-01-24 2021-03-05 2020-02-24 2021-03-12 2020-03-24 2021-03-26 2020-06-10 2021-04-12 2020-09-30 2021-10-09 sur les indicateurs de Based Selection RMCHN minimum package prestation de services dans le secteur santé (SDI) MG-UCP-220922-CS-CQS / Recrutement d'un consultant Project Management, Consultant pour les études IDA / D2570 Capacity Building and Post Qualification Limited 15,000.00 0.00 Canceled 2021-02-23 2021-02-22 2021-02-25 2021-03-07 2021-03-29 2021-05-28 environnementales et sociales Operations Support Selection pour le projet MG-UCP-221493-CS-CQS / recrutement d'un consultant Project Management, Consultant pour les études IDA / D2570 Capacity Building and Post Qualification Limited 15,000.00 68,745.46 Signed 2021-02-24 2021-02-22 2021-03-05 2021-02-23 2021-03-15 2021-03-10 2021-03-27 2021-03-10 2021-05-26 environnementales et sociales Operations Support Selection requises pour le projet MG-UCP-222700-CS-QCBS / Recrutement d’une firme pour la validation des données des Project Management, Quality And Cost- Under agents de l’Etat à travers un IDA / D2570 Capacity Building and Post Open - National 500,000.00 0.00 2021-03-11 2021-03-03 2021-04-01 2021-05-15 2021-06-05 2021-06-20 2021-07-20 2021-08-13 2022-08-13 Based Selection Implementation recensement avec une Operations Support priorisation de secteur santé et éducation INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MG-UCP-61052-CS-INDV / Strengthen capacity to Individual Recrutement CI RBF pour la IDA / D2570 manage and deliver the Post Consultant Direct 123,000.00 93,000.00 Completed 2018-05-15 2018-07-18 2018-05-25 2018-07-31 2018-06-15 2018-07-18 2018-07-20 2018-07-31 2019-06-20 2018-07-31 mise à l'échelle des RBF RMCHN minimum package Selection existants PHILIPPE COMPAORE MG-UCP-64959-CS-CDS / recrutement de consultant Scale up coverage and individuel pour la mise à jour IDA / D2570 utilization of the RMCHN Post Direct Selection Direct 11,931.00 6,626.10 Completed 2018-06-07 2018-05-28 2018-06-17 2018-11-15 2018-08-21 2018-11-29 2018-09-20 2018-11-29 de la politique Nationale de la minimum package Santé de la Reproduction des Adolescents MG-UCP-89393-CS-CDS / Recrutement d'une firme Strengthen capacity to spécialisée pour la conception IDA / D2570 manage and deliver the Post Direct Selection Direct 176,719.00 251,267.10 Signed 2018-12-26 2019-02-26 2019-01-05 2019-06-19 2019-03-11 2019-06-27 2019-09-07 et la mise en place du portail RMCHN minimum package FBP MG-UCP-95246-CS-CDS / Project Management, Cabinet de recrutement IDA / D2570 Capacity Building and Post Direct Selection Direct 7,000.00 9,689.33 Signed 2019-01-27 2019-02-26 2019-02-06 2019-02-26 2019-02-21 2019-03-01 2019-03-13 personnel UCP Operations Support Project Management, Individual MG-UCP-104979-CS-INDV / Under IDA / V0970 Capacity Building and Post Consultant Open 20,149.00 0.00 2019-03-08 2019-03-13 2019-03-08 2019-03-09 2019-03-14 2019-03-10 2019-09-06 Responsable Financier Implementation Operations Support Selection Project Management, Individual MG-UCP-104983-CS-INDV / Under IDA / V0970 Capacity Building and Post Consultant Open 20,149.00 0.00 2019-03-08 2019-03-13 2019-03-27 2019-04-06 2019-04-09 2019-12-11 Auditeur Interne Senior Implementation Operations Support Selection MG-UCP-104986-CS-INDV / Project Management, Individual Under Spécialiste en Sauvegarde IDA / V0970 Capacity Building and Post Consultant Open 20,149.00 0.00 2019-03-08 2019-03-13 2019-03-27 2019-04-10 2019-04-06 2019-10-01 2019-04-28 2019-12-31 Implementation Environnementale et Sociale Operations Support Selection MG-UCP-104989-CS-INDV / Project Management, Individual Responsable de Passation de IDA / V0970 Capacity Building and Post Consultant Open 20,149.00 13,526.49 Terminated 2019-03-08 2019-03-13 2019-04-01 2019-09-17 2019-04-11 2019-10-11 2019-05-06 2019-10-14 2019-12-31 Marchés Operations Support Selection MG-UCP-104968-CS-CDS / Project Management, Accompagnement préalable à IDA / V0970 Capacity Building and Post Direct Selection Direct 406,295.00 328,047.81 Completed 2019-03-08 2018-06-11 2019-03-09 2018-06-20 2019-03-13 2018-12-20 2019-12-31 2018-12-20 l'installation des médecins  Operations Support avec Santé Sud Project Management, Individual MG-UCP-104987-CS-INDV / IDA / V0970 Capacity Building and Post Consultant Open 20,149.00 15,574.09 Signed 2019-03-08 2018-12-01 2019-04-01 2019-04-09 2019-04-11 2019-09-30 2019-04-16 2019-10-01 2019-10-13 Point Focal PARN Operations Support Selection MG-UCP-107067-CS-CQS / Project Management, Individual Recrutement d'un Assistant Under IDA / V0970 Capacity Building and Post Consultant Open 3,582.00 0.00 2019-04-08 2019-11-28 2019-05-13 2019-05-18 2019-06-18 2019-12-15 technique Voucher au niveau Implementation Operations Support Selection DDS MG-UCP-104959-CS-CDS / Project Management, Acquisition de balance pèse IDA / V0970 Capacity Building and Post Direct Selection Direct 31,471.00 0.00 Canceled 2019-03-08 2019-03-18 2019-04-04 2019-04-14 bébé Operations Support MG-UCP-126549-CS-INDV / Project Management, Individual Under Auditeur Interne Senior (2ème IDA / D2570 Capacity Building and Post Consultant Open 5,037.00 0.00 2019-08-20 2019-10-08 2019-09-26 2019-10-03 2019-10-23 2019-12-22 Implementation relance) Operations Support Selection Page 6 MG-UCP-126802-CS-INDV / Project Management, Individual Under Recrutement Auditeur interne IDA / D2570 Capacity Building and Post Consultant Open 5,037.00 0.00 2019-08-20 2019-08-20 2019-09-19 2019-09-29 2019-10-19 2020-04-16 Implementation senior (2ème relance) Operations Support Selection MG-UCP-125575-CS-INDV / Project Management, Individual Recrutement d'un vérificateur IDA / D2570 Capacity Building and Post Consultant Open 2,284.00 214.91 Signed 2019-04-25 2019-04-25 2019-06-13 2019-06-07 2019-07-04 2019-06-11 2019-08-08 2019-06-14 2019-12-31 de la quantité N° 1 A Ikongo Operations Support Selection MG-UCP-126561-CS-INDV / Project Management, Individual Recrutement d'un assistant Under IDA / D2570 Capacity Building and Post Consultant Open 5,838.50 0.00 2019-04-25 2019-11-28 2019-06-13 2019-07-04 2019-08-08 2019-12-31 technique Voucher au niveau Implementation Operations Support Selection Région Itasy MG-UCP-126281-CS-INDV / Project Management, Individual Under Recrutement d'un vérificateur IDA / D2570 Capacity Building and Post Consultant Open 11,677.00 0.00 2019-04-25 2019-04-22 2019-06-13 2019-07-04 2019-08-08 2019-12-31 Implementation N° 1 au niveau de l'UCP Operations Support Selection MG-UCP-128968-CS-INDV / Project Management, Individual Recrutement d'un vérificateur Under IDA / D2570 Capacity Building and Post Consultant Open 2,284.00 0.00 2019-04-25 2019-04-18 2019-06-13 2019-07-04 2019-08-08 2019-12-31 de la quantité N°1 à Implementation Operations Support Selection Ambatolampy MG-UCP-128970-CS-INDV / Project Management, Individual Recrutement d'un vérificateur IDA / D2570 Capacity Building and Post Consultant Open 2,284.00 214.91 Signed 2019-04-25 2019-03-26 2019-06-13 2019-06-07 2019-07-04 2019-06-11 2019-08-08 2019-06-14 2019-12-31 de la quantité N° 1 à Operations Support Selection Vohipeno MG-UCP-128969-CS-INDV / Project Management, Individual Recrutement d'un vérificateur IDA / D2570 Capacity Building and Post Consultant Open 2,284.00 214.85 Signed 2019-04-25 2019-04-26 2019-06-13 2019-06-07 2019-07-04 2020-06-11 2019-08-08 2019-06-14 2019-12-31 de la quantité N° 1 à Betafo Operations Support Selection MG-UCP-129153-CS-INDV / Project Management, Individual Recrutement d'un vérificateur IDA / D2570 Capacity Building and Post Consultant Open 2,284.00 214.91 Signed 2019-04-25 2019-04-24 2019-06-13 2019-06-07 2019-07-04 2019-06-11 2019-08-08 2019-06-14 2019-12-31 de la quantité N° 2 à Operations Support Selection Vohipeno MG-UCP-129152-CS-INDV / Project Management, Individual Under Recrutement d'un vérificateur IDA / D2570 Capacity Building and Post Consultant Open 2,284.00 0.00 2019-04-25 2019-04-25 2019-06-13 2019-07-04 2019-08-08 2019-12-31 Implementation de la quantité N° 2 à Betafo Operations Support Selection MG-UCP-128973-CS-INDV / Project Management, Individual Recrutement d'un assistant Under IDA / D2570 Capacity Building and Post Consultant Open 5,838.50 0.00 2019-04-25 2019-11-28 2019-06-13 2019-07-04 2019-08-08 2019-12-31 technique Voucher au niveau Implementation Operations Support Selection Région Vakinakaratra MG-UCP-128972-CS-INDV / Project Management, Individual Recrutement d'un assistant Under IDA / D2570 Capacity Building and Post Consultant Open 5,838.50 0.00 2019-04-25 2019-11-28 2019-06-13 2019-07-04 2019-08-08 2019-12-31 technique Voucher au niveau Implementation Operations Support Selection Région Haute Matsiatra MG-UCP-128971-CS-INDV / Project Management, Individual Recrutement d'un assistant Under IDA / D2570 Capacity Building and Post Consultant Open 5,838.50 0.00 2019-04-25 2019-11-28 2019-06-13 2019-07-04 2019-08-08 2019-12-31 technique Voucher au niveau Implementation Operations Support Selection Région Amoron'i Mania MG-UCP-128975-CS-CDS / Prestation de service pour le Project Management, dédouanement des IDA / D2570 Capacity Building and Post Direct Selection Direct 98,316.00 0.00 Signed 2018-11-11 2019-01-30 2018-11-21 2018-07-25 2019-01-25 2019-02-12 2019-12-31 fournitures et matériels de Operations Support l’UCP pour la mise en œuvre du Projet PARN MG-UCP-129155-CS-INDV / Project Management, Individual Recrutement d'un vérificateur IDA / D2570 Capacity Building and Post Consultant Open 2,284.00 214.91 Signed 2019-04-25 2019-04-26 2019-06-13 2019-06-07 2019-07-04 2019-06-11 2019-08-08 2019-06-14 2019-12-31 de la quantité N°2 à Operations Support Selection Ambatolampy MG-UCP-129156-CS-INDV / Project Management, Individual Recrutement d'un vérificateur IDA / D2570 Capacity Building and Post Consultant Open 2,284.00 314.63 Signed 2019-04-25 2019-04-24 2019-06-13 2019-06-07 2019-07-04 2019-12-26 2019-08-08 2019-12-30 2019-12-31 de la quantité N°2 à Ikongo Operations Support Selection MG-UCP-129157-CS-INDV / Project Management, Individual Under Recrutement d’un vérificateur IDA / D2570 Capacity Building and Post Consultant Open 2,284.00 0.00 2019-04-25 2019-04-23 2019-06-13 2019-07-04 2019-08-08 2019-12-31 Implementation N° 2 au niveau de l'UCP Operations Support Selection MG-UCP-135235-CS-CDS / Project Management, Accompagnement des IDA / D2570 Capacity Building and Post Direct Selection Direct 233,498.00 652,480.24 Completed 2019-09-23 2019-09-10 2019-10-03 2019-09-23 2019-12-07 2019-12-31 2020-06-04 2019-12-31 formations des prestataires et Operations Support assurance qualité (JHPIEGO) MG-UCP-140172-CS-CDS / Project Management, Cabinet de recrutement de IDA / D2570 Capacity Building and Post Direct Selection Direct 5,000.00 2,587.58 Signed 2019-10-14 2019-10-15 2019-10-24 2019-10-08 2019-12-28 2019-10-17 2020-12-31 l'Auditeur Interne Senior de Operations Support l'UCP MG-UCP-146546-CS-CDS / Strengthen capacity to prestation sur la contre IDA / D2570 manage and deliver the Post Direct Selection Direct 34,355.00 19,876.90 Completed 2019-11-21 2019-11-22 2019-12-01 2019-10-18 2020-02-04 2019-11-25 2020-08-02 2019-11-25 vérification du FBP RMCHN minimum package MG-UCP-126522-CS-INDV / Project Management, Individual Recrutement Agence Fiscal - IDA / D2570 Capacity Building and Post Consultant Open 11,940.00 0.00 Canceled 2019-08-20 2019-09-16 2019-10-08 2019-10-23 2019-11-23 2020-05-21 PARN Operations Support Selection MG-UCP-159670-CS-CDS / Project Management, selection de cabinet pour le IDA / D2570 Capacity Building and Post Direct Selection Direct 15,000.00 5,108.79 Signed 2020-02-17 2020-02-28 2020-02-27 2020-02-28 2020-05-02 2020-03-18 2020-10-29 recrutement de personnel du Operations Support projet MG-UCP-160774-CS-INDV / Strengthen capacity to Individual recrutement d'un consultant IDA / D2570 manage and deliver the Post Consultant Open 15,384.00 9,606.72 Signed 2020-02-21 2020-02-28 2020-04-10 2020-05-14 2020-05-01 2020-06-10 2020-06-05 2020-06-11 2020-12-02 coordinateur d'enquête et RMCHN minimum package Selection atelier de dissémination MG-UCP-160780-CS-INDV / recrutement de deux vérificateurs de la quantité Project Management, Individual pour le District de Under IDA / D2570 Capacity Building and Post Consultant Open 25,000.00 0.00 2020-02-28 2020-03-13 2020-04-17 2020-05-08 2020-06-12 2023-12-31 Tsiroanomandidy et deux Implementation Operations Support Selection vérificateurs de la quantité pour le District de Fenoarivobe Page 7 MG-UCP-172407-CS-INDV / Individual recrutement d'un agent Contingent Emergency IDA / D2570 Post Consultant Open 3,700.00 2,683.82 Completed 2020-05-06 2020-03-18 2020-05-25 2020-04-14 2020-05-27 2020-04-21 2020-05-31 2020-04-22 2020-08-29 2020-07-22 spécialiste en passation de Response Component (CERC) Selection marchés MG-UCP-172420-CS-INDV / Individual Contingent Emergency recrutement d'un gestionnaire IDA / D2570 Post Consultant Open 3,800.00 0.00 Canceled 2020-05-06 2020-03-18 2020-05-24 2020-05-26 2020-05-30 2020-08-28 Response Component (CERC) comptable pour l'UCP Selection MG-UCP-186139-CS-INDV / Individual Recrutement d'un Chef de Contingent Emergency IDA / D2570 Post Consultant Open 8,400.00 15,244.20 Terminated 2020-07-28 2020-01-17 2020-08-31 2020-07-03 2020-09-15 2020-07-03 2020-09-19 2020-07-03 2020-12-18 Service de la Passation de Response Component (CERC) Selection Marchés MG-UCP-186167-CS-CDS / recrutement d'un assistant Contingent Emergency Under IDA / D2570 Post Direct Selection Direct 3,700.00 0.00 2020-08-12 2020-07-07 2020-08-21 2020-09-01 2020-11-30 gestionnaire comptable pour Response Component (CERC) Implementation la riposte au Covid à l'UCP MG-UCP-195430-CS-INDV / Project Management, Individual Recrutement d'un Assistant en IDA / D2570 Capacity Building and Post Consultant Open 2,355.00 6,947.05 Signed 2020-09-21 2020-08-13 2020-11-09 2020-10-13 2020-11-30 2020-11-05 2021-01-04 2020-11-06 2021-07-03 passation des marchés de Operations Support Selection l'UCP MG-UCP-195444-CS-INDV / Project Management, Individual Recrutement d'un Auditeur IDA / D2570 Capacity Building and Post Consultant Open 2,355.00 7,513.33 Terminated 2020-09-21 2020-08-13 2020-11-09 2021-01-11 2020-11-30 2021-03-15 2021-01-04 2021-03-15 2021-07-03 Interne Assistant de l'UCP Operations Support Selection MG-UCP-195449-CS-INDV / Project Management, Individual Under Recrutement d'un Chef Service IDA / D2570 Capacity Building and Post Consultant Open 8,396.00 0.00 2020-09-21 2020-11-14 2020-11-09 2020-11-30 2021-01-04 2021-07-03 Implementation en passation des marchés Operations Support Selection MG-UCP-111049-CS-INDV / Project Management, Individual recrutement Responsable IDA / V0970 Capacity Building and Post Consultant Open 17,000.00 0.00 Canceled 2019-05-27 2019-07-15 2019-08-05 2019-09-09 2020-03-07 Passation de marché Operations Support Selection suppléant MG-UCP-111293-CS-INDV / Project Management, Individual Recrutement de quatre IDA / D2570 Capacity Building and Post Consultant Open 11,463.00 0.00 Canceled 2019-04-19 2019-06-07 2019-06-28 2019-08-02 2020-01-29 chauffeurs de l'UCP Operations Support Selection MG-UCP-213225-CS-CDS / Sélection d'un cabinet pour le Project Management, recrutement d'un chef service IDA / D2570 Capacity Building and Post Direct Selection Direct 2,788.00 2,130.89 Signed 2021-01-12 2021-01-12 2021-01-22 2021-01-14 2021-03-28 2021-02-04 2021-09-24 de la passation des marchés Operations Support de l'UCP MG-UCP-221465-CS-INDV / Recrutement de 4 Assistants Project Management, Individual Under techniques Voucher 2 ATV IDA / D2570 Capacity Building and Post Consultant Open 30,857.08 0.00 2021-02-26 2021-02-25 2021-04-04 2021-04-11 2021-04-19 2021-12-31 Implementation pour Analamanga et 2 ATV Operations Support Selection pour Alaotra Mangoro MG-UCP-235250-CS-CDS / Project Management, Elaboration des documents de IDA / D2570 Capacity Building and Post Direct Selection Direct 38,700.00 0.00 Under Review 2021-05-31 2021-05-25 2021-06-22 2021-07-19 2021-09-17 sauvegarde pour le nouveau Operations Support projet vaccination MG-UCP-240552-CS-INDV / Scale up coverage and Individual recrutement d'un Auditeur IDA / D2570 utilization of the RMCHN Post Consultant Open 7,000.00 0.00 Under Review 2021-06-28 2021-06-23 2021-08-05 2021-08-19 2021-09-16 2022-09-16 Interne Assistant de l'UCP minimum package Selection Page 8 Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan: December, 2016 2. Date of General Procurement Notice: 3. Period covered by this procurement plan: Jan 2017 to June 2018 II. Goods, Works, Consultant and Non-Consulting Services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Type of Procurement Prior Review Comments Threshold (PRT) US$ (Millions) 1. Works (Including turnkey, supply & 5 High risk installation of plant and equipment and PPP) 2. (Goods; Information Technology & 1.5 High risk Non-Consulting Services) 3. Consultant Services (Firms) 0.5 High risk 4. Consultant Services (Individual 0.2 High risk Consultants) 2. Prequalification. NA 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: NA 4. Reference to (if any) Project Operational/Procurement Manual: Available in Project files 5. Any Other Special Procurement Arrangements: NA 6. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 7. All TORs for the procurement of consultants services irrespective of the estimated cost of the assignment shall be reviewed and cleared by the TTL 8. Operating expenditures are neither subject to the Procurement and Consultant Guidelines nor prior or post reviews. Operating expenditures are normally verified by TTLs and FM specialists and obtained using the Borrower’s national procurement and administrative procedures. January 11, 2018 9. Renewal or extension of individual consultant’s contracts hired for technical assistance and which are intended for a long-term period but signed for an initial period shorter than the duration of the project, and that have been prior reviewed, do not require procurement clearance if there is no substantial change in the terms and conditions of the contract. January 11, 2018 PROCUREMENT Kenya : Kenya Climate Smart Agriculture Project PLAN General Information Country: Kenya Bank’s Approval Date of the Original Procurement Plan: 2020-01-28 2021-05-22 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P154784 GPN Date: 2018-02-08 Project Name: Kenya Climate Smart Agriculture Project Loan / Credit No: IDA / 59450 T Executing Agency(ies): aita Taveta County WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Component 1: Upscaling TTCG/AGRI/422/2018-2019 Climate-Smart Agricultural Single Stage - One 2019-11- / Construction of Ufunguo IDA / 59450 Practices (US$163.8 million Post Request for Bids Open - National 138,939.00 116,608.19 Completed 2019-02-07 2019-01-28 2019-02-12 2021-06-09 2019-03-26 2019-03-04 2019-04-25 2019-03-06 2019-05-30 2019-04-16 Envelope 26 Water Pan equivalent, of which IDA US$150.0 million eq uivalent) Component 1: Upscaling TTCG/AGRI/421/2018-2019 Climate-Smart Agricultural Single Stage - One 2019-07- / Rehabilitation of Njoro IDA / 59450 Practices (US$163.8 million Post Request for Bids Open - National 107,076.10 102,678.91 Completed 2019-02-07 2019-01-28 2019-02-08 2021-06-10 2019-03-01 2019-03-04 2019-03-31 2019-03-06 2019-04-15 2019-05-09 Envelope 14 Kubwa Canal equivalent, of which IDA US$150.0 million eq uivalent) Component 1: Upscaling Climate-Smart Agricultural TTCG/AGRI/423/2018-2019 Single Stage - One 2019-11- IDA / 59450 Practices (US$163.8 million Post Request for Bids Open - National 335,458.90 294,683.27 Completed 2019-02-07 2019-01-28 2019-02-12 2021-06-10 2019-03-26 2019-03-04 2019-04-25 2019-03-06 2019-05-30 2019-05-09 / Construction of Mkuru Dam Envelope 26 equivalent, of which IDA US$150.0 million eq uivalent) Component 4: Project TTCG/AGRIC&I/KCSAP/RFQ/9 Coordination and Request for Single Stage - One 2019-12- 67/2018-2019 / Renovation IDA / 59450 Management (US$29.3 Post Limited 24,025.29 22,923.63 Completed 2019-07-22 2019-05-16 2019-09-16 2019-06-18 Quotations Envelope 15 of Office million equivalent, of which IDA US$20.0 million equivalent) KE-TAITA TAVETA COUNTY- Component 1: Upscaling 183953-CW-RFQ / Climate-Smart Agricultural Pending Request for Single Stage - One 2020-11- CONSTRUCTION OF IDA / 59450 Practices (US$163.8 million Post Limited 54,929.83 0.00 Implementat 2020-08-01 2020-08-21 Quotations Envelope 19 ARTIFICIAL INSEMINATION equivalent, of which IDA ion CENTERS AND CRUSHES US$150.0 million eq uivalent) GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 4: Project TTCG/RFQ/KCSAP/967/2018- Coordination and Request for Single Stage - One 2019 / Supply and delivery of IDA / 59450 Management (US$29.3 Post Limited 18,155.34 17,322.84 Completed 2019-06-16 2019-05-28 2019-08-11 2019-06-17 2019-09-10 2019-06-28 Quotations Envelope Office Furniture million equivalent, of which IDA US$20.0 million equivalent) Component 1: Upscaling KE-TAITA TAVETA COUNTY- Climate-Smart Agricultural Pending 173721-GO-RFB / Supply and Single Stage - One IDA / 59450 Practices (US$163.8 million Post Request for Bids Open - National 355,000.00 0.00 Implementati 2020-07-01 2020-07-06 2020-08-05 2020-09-04 2020-09-25 2020-10-09 Delivery of Macadamia and Envelope equivalent, of which IDA on Mango Seedlings US$150.0 million eq uivalent) Component 1: Upscaling KE-TAITA TAVETA COUNTY- Climate-Smart Agricultural Pending 183207-GO-RFQ / SUPPLY Request for Single Stage - One IDA / 59450 Practices (US$163.8 million Post Limited 9,890.00 0.00 Implementati 2020-08-21 2020-09-10 2020-10-10 AND DELIVERY OF ICT Quotations Envelope equivalent, of which IDA on EQUIPMENT US$150.0 million eq uivalent) KE-TAITA TAVETA COUNTY- Component 1: Upscaling 183216-GO-RFQ / SUPPLY Climate-Smart Agricultural Pending AND DELIVERY OF ECF Request for Single Stage - One IDA / 59450 Practices (US$163.8 million Post Limited 38,978.00 0.00 Implementati 2020-08-21 2020-09-10 2020-10-10 VACCINES AND OTHER Quotations Envelope equivalent, of which IDA on ARTIFICIAL AND US$150.0 million eq uivalent) INSEMINATION APPARATUS Component 1: Upscaling KE-TAITA TAVETA COUNTY- Climate-Smart Agricultural Pending Request for Single Stage - One 188528-GO-RFQ / Supply IDA / 59450 Practices (US$163.8 million Post Limited 29,232.00 0.00 Implementati 2020-08-21 2020-09-10 2020-10-10 Quotations Envelope and Delivery of Motorbikes equivalent, of which IDA on US$150.0 million eq uivalent) Component 1: Upscaling KE-TAITA TAVETA COUNTY- Climate-Smart Agricultural Pending 233009-GO-RFQ / Supply Request for Single Stage - One IDA / 59450 Practices (US$163.8 million Post Limited 40,000.00 0.00 Implementati 2021-06-07 2021-07-05 2021-09-03 and Delivery of Motorcycles Quotations Envelope equivalent, of which IDA on for Data Collection US$150.0 million eq uivalent) NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 1 Component 1: Upscaling CGTT/RFP/351/2018-2019 / Climate-Smart Agricultural Quality And Cost- Pending Consultancy Services for IDA / 59450 Practices (US$163.8 million Post Open - National 97,053.40 0.00 2019-03-10 2019-03-31 2019-05-14 2019-06-11 2019-07-11 2019-08-15 2019-09-19 2020-09-18 Based Selection Implementation Advisory Services to Farmers equivalent, of which IDA US$150.0 million eq uivalent) INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 1: Upscaling KE-TAITA TAVETA COUNTY- Climate-Smart Agricultural Individual 189647-CS-INDV / Develop a Pending IDA / 59450 Practices (US$163.8 million Post Consultant Limited 22,000.00 0.00 2020-10-12 2020-10-17 2020-10-24 2020-11-07 2020-12-27 centralized breeding Implementation equivalent, of which IDA Selection information system US$150.0 million eq uivalent) Page 2 Improving the Performance of Non-Criminal Justice Services (P162833) Procurement Plan Country: Peru Region: LATIN AMERICA AND CARIBBEAN Approval Date: 05-Jun-2019 July 9, 2010 PROCUREMENT Peru : Improving the Performance of Non-Criminal Justice Services PLAN General Information Country: Peru Bank’s Approval Date of the Original Procurement Plan: 2020-12-22 2021-05-21 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P162833 GPN Date: Project Name: Improving the Performance of Non-Criminal Justice Services Loan / Credit No: IBRD / 89750 Poder Judicial UE002 Oficiona Coordinación de Proyectos Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PE-PJ-208965-GO-RFQ / Component 1: Strengthening Adquisición de impresora Under the institutionality of the non- Request for Single Stage - One fotocopiadora, escáner de alto IBRD / 89750 Post Limited 50,000.00 0.00 Implementati 2020-12-21 2021-01-04 2021-02-03 criminal justice Quotations Envelope rendimiento y proyector on administration system multimedia Component 1: Strengthening Under PE-PJ-208969-GO-RFQ / the institutionality of the non- Request for Single Stage - One IBRD / 89750 Post Limited 15,000.00 0.00 Implementati 2020-12-21 2021-01-04 2021-02-03 Adquisición de UPS criminal justice Quotations Envelope on administration system PE-PJ-209136-GO-RFQ / Component 1: Strengthening Under Adquisición de Licencias the institutionality of the non- Request for Single Stage - One IBRD / 89750 Post Limited 37,000.00 0.00 Implementati 2020-12-21 2021-01-04 2021-02-03 antivirus para equipos criminal justice Quotations Envelope on informáticos administration system Component 1: Strengthening PE-PJ-209138-GO-RFQ / Under the institutionality of the non- Request for Single Stage - One Adquisición de computadores IBRD / 89750 Post Limited 50,000.00 0.00 Implementati 2020-12-21 2021-01-04 2021-02-03 criminal justice Quotations Envelope portátiles on administration system Component 1: Strengthening PE-PJ-209139-GO-RFQ / Under the institutionality of the non- Request for Single Stage - One Adquisición de computadores IBRD / 89750 Post Limited 50,000.00 0.00 Implementati 2020-12-21 2021-01-04 2021-02-03 criminal justice Quotations Envelope de escritorio on administration system Component 1: Strengthening Under PE-PJ-209141-GO-RFQ / the institutionality of the non- Request for Single Stage - One IBRD / 89750 Post Limited 7,000.00 0.00 Implementati 2020-12-21 2021-01-04 2021-02-03 Adquisición de Monitores Led criminal justice Quotations Envelope on administration system NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PE-PJ-234531-CS-INDV / ESPECIALISTA EN ADQUISICIONES EN EL MARCO DEL PROGRAMA DE INVERSIÓN Component 4: Improving MEJORAMIENTO DE LOS Individual efficiency and efficacy of the Pending SERVICIOS DE JUSTICIA NO IBRD / 89750 Post Consultant Limited 156,156.16 0.00 2021-05-14 2021-05-19 2021-06-09 2021-07-14 2022-01-10 justice administration system Implementation PENALES A TRAVÉS DE LA Selection institutions. IMPLEMENTACIÓN DEL EXPEDIENTE JUDICIAL ELECTRÓNICO (EJE), DE CÓDIGO ÚNICO N° 2413068 PE-PJ-234534-CS-INDV / ESPECIALISTA FINANCIERO EN EL MARCO DEL PROGRAMA DE INVERSIÓN MEJORAMIENTO DE Component 4: Improving Individual LOS SERVICIOS DE JUSTICIA efficiency and efficacy of the Pending IBRD / 89750 Post Consultant Limited 156,156.16 0.00 2021-05-14 2021-05-19 2021-06-09 2021-07-14 2022-01-10 NO PENALES A TRAVÉS DE LA justice administration system Implementation Selection IMPLEMENTACIÓN DEL institutions. EXPEDIENTE JUDICIAL ELECTRÓNICO (EJE), DE CÓDIGO ÚNICO N° 2413068 Page 1 PE-PJ-234535-CS-INDV / ESPECIALISTA EN PROYECTOS EN EL MARCO DEL PROGRAMA DE INVERSIÓN MEJORAMIENTO Component 4: Improving Individual DE LOS SERVICIOS DE JUSTICIA efficiency and efficacy of the Pending IBRD / 89750 Post Consultant Limited 156,156.16 0.00 2021-05-14 2021-05-19 2021-06-09 2021-07-14 2022-01-10 NO PENALES A TRAVÉS DE LA justice administration system Implementation Selection IMPLEMENTACIÓN DEL institutions. EXPEDIENTE JUDICIAL ELECTRÓNICO (EJE), DE CÓDIGO ÚNICO N° 2413068 PE-PJ-234540-CS-INDV / ASESOR/A LEGAL EN EL MARCO DEL PROGRAMA DE INVERSIÓN MEJORAMIENTO DE Component 4: Improving Individual LOS SERVICIOS DE JUSTICIA efficiency and efficacy of the Under IBRD / 89750 Post Consultant Limited 156,156.16 0.00 2021-05-14 2021-05-26 2021-05-19 2021-06-09 2021-07-14 2022-01-10 NO PENALES A TRAVÉS DE LA justice administration system Implementation Selection IMPLEMENTACIÓN DEL institutions. EXPEDIENTE JUDICIAL ELECTRÓNICO (EJE), DE CÓDIGO ÚNICO N ° 2413068 PE-PJ-234541-CS-INDV / DIRECTOR/A DEL PROGRAMA EN EL MARCO DEL PROGRAMA DE INVERSIÓN MEJORAMIENTO Component 4: Improving Individual DE LOS SERVICIOS DE JUSTICIA efficiency and efficacy of the Under IBRD / 89750 Post Consultant Limited 197,101.45 0.00 2021-05-14 2021-05-19 2021-06-09 2021-07-14 2022-01-10 NO PENALES A TRAVÉS DE LA justice administration system Implementation Selection IMPLEMENTACIÓN DEL institutions. EXPEDIENTE JUDICIAL ELECTRÓNICO (EJE), DE CÓDIGO ÚNICO N° 2413068 PE-PJ-234669-CS-INDV / GESTOR/A DE PROYECTO EN EL MARCO DEL PROYECTO " MEJORAMIENTO DE LOS SERVICIOS DE FORMACION Y Component 4: Improving Individual CAPACITACION DE LA efficiency and efficacy of the Under IBRD / 89750 Post Consultant Limited 180,180.18 0.00 2021-05-14 2021-05-19 2021-06-09 2021-07-14 2022-01-10 ACADEMIA DE LA justice administration system Implementation Selection MAGISTRATURA PARA LA institutions. ADECUADA IMPLEMENTACION DEL EXPEDIENTE JUDICIAL ELECTRONICO DE CÓDIGO ÚNICO N ° 2412540 PE-PJ-234670-CS-INDV / ASISTENTE/A ADMINISTRATIVO EN EL MARCO DEL PROYECTO " MEJORAMIENTO DE LOS Component 4: Improving SERVICIOS DE FORMACION Y Individual efficiency and efficacy of the Under CAPACITACION DE LA IBRD / 89750 Post Consultant Limited 72,072.07 0.00 2021-05-14 2021-05-19 2021-06-09 2021-07-14 2022-01-10 justice administration system Implementation ACADEMIA DE LA Selection institutions. MAGISTRATURA PARA LA ADECUADA IMPLEMENTACION DEL EXPEDIENTE JUDICIAL ELECTRONICO DE CÓDIGO ÚNICO N ° 2412540 Page 2 MINISTRY OF HEALTH Transforming Health Systems for Universal Care Project Project Procurement Plan Financial Year 2016/2017 IDA CREDIT No. 5836-KE GFF Grant Agreement TF0A2561 PHRD Grant Agreement TF0A2792 General 1. Project information: The Government of Kenya has applied for a Credit from the International Development Association supporting the Transforming Health Systems or Universal Care Project 2. Bank’s approval Date of the procurement Plan [Original::] 3. Date of General Procurement Notice: 4. Period covered by this procurement plan: 1st June, 2016 to 31st December, 2017 II. Goods and Works and Non-Consulting Services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Method Threshold Prior Review Threshold 1 ICB – Works ≥US$15 million ≥US$10 million 2 NCB- Works 7000 AOI ≥5000 Entre 200 et 7000 AON ≤200 DC 2. Biens et >3000 AOI ≥1500 Services non- Entre 100 et 3000 AON consultants ≤100 DC 3. A >300 SFQC, SCBD, SMC, ≥500 Consultants SFQ, Firmes ≤300 SQC 3.B Quelle que soit la Comparaison de 3 >200 Consultant valeur CV individuels N.B. : Les contrats passés par entente directe n’ont pas de seuils spécifiques (méthodes & seuils de revue préalable) en ce qui concerne la revue préalable de la Banque, il leur est appliqué les seuils indiqués dans le tableau ci-dessus. PROCUREMENT Eastern Africa : Great Lakes Regional Integrated Agriculture Development Project PLAN General Information Country: Eastern Africa Bank’s Approval Date of the Original Procurement Plan: 2018-07-17 2021-05-27 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P161781 GPN Date: Project Name: Great Lakes Regional Integrated Agriculture Development Project Loan / Credit No: / , IDA / D1810 Ministère de l'Agriculture et de l'Elevage Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned BI-PIU-68406-CW-RFQ / Réhabilitation des bureaux 4. Project management and Request for Single Stage - One 2019-03- IDA / D1810 Post Limited 48,000.00 60,102.72 Completed 2018-07-09 2018-09-04 2018-09-03 2019-01-17 pour les Unités provinciales institutional support Quotations Envelope 02 de coordination du Projet BI-PIU-97499-CW-FCA / Travaux en régie pour Under l'entretien des infrastructures 1. Smallholders’ productivity 2019-10- IDA / D1810 Post Force Account Direct 24,380.00 0.00 Implementat 2019-02-25 2019-02-18 2019-03-02 2019-04-06 d'irrigation du périmètre de la and production enhancement 03 ion Société Régionale de Développement de l'Imbo BI-PIU-143954-CW-RFQ / Réhabilitation du hangar de 2. Support to investments in stockage de l’association de Request for Single Stage - One 2020-07- IDA / D1810 agro-processing and market Post Limited 40,000.00 0.00 Canceled 2019-11-20 2020-01-15 Batwa riziculteurs de la Quotations Envelope 13 linkages commune Rugombo/Province Cibitoke BI-PIU-198271-CW-RFB / Réaménagement et sécurisation des bureaux des Pending cinq (05) Unités Provinciales 4. Project management and Single Stage - One 2021-08- IDA / D1810 Post Request for Bids Open - National 80,000.00 0.00 Implementat 2020-10-14 2020-10-19 2020-11-30 2020-12-30 2021-02-03 de Coordination du Projet institutional support Envelope 02 ion Régional de Développement Agricole Intégré dans les Grands Lacs ( PRDAIGL) BI-PIU-203020-CW-RFB / Pending Construction d’abri pour le 1. Smallholders’ productivity Single Stage - One 2021-10- IDA / D1810 Post Request for Bids Open - National 45,000.00 0.00 Implementat 2021-01-04 2021-01-09 2021-02-20 2021-03-22 2021-04-26 liquéfacteur d’azote et ses and production enhancement Envelope 23 ion accessoires BI-PIU-226609-CW-RFB / Construction de trois centres Pending 4. Project management and Single Stage - One 2022-01- communaux de IDA / D1810 Post Request for Bids Open - National 144,600.00 0.00 Implementat 2021-04-12 2021-04-17 2021-05-29 2021-06-28 2021-08-02 institutional support Envelope 29 développement agro-sylvo- ion pastoral. BI-PIU-233913-CW-RFB / 3. Institutional integration, Request for Bids - Pending Construction d'une usine knowledge acquisition, and Single Stage - One Works (without 2022-03- IDA / D1810 Post Request for Bids Open - National 200,000.00 0.00 Implementat 2021-05-14 2021-05-19 2021-06-30 2021-07-30 2021-09-03 modulaire de production dissemination of information Envelope prequalification) 02 ion d'aflasafe at the regional level SPD GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BI-PIU-67839-GO-RFB / 1. Smallholders’ productivity Single Stage - One Acquisition des Motos et / Post Request for Bids Open - National 250,000.00 0.00 Canceled 2018-07-20 2018-07-25 2018-09-05 2018-10-05 2018-11-09 2019-05-08 and production enhancement Envelope accessoires (50 motos) BI-PIU-68443-GO-COMM / 1. Smallholders’ productivity Single Stage - One IDA / D1810 Post Commodities Limited 66,000.00 0.00 Canceled 2018-06-29 2018-08-14 2018-07-04 2018-09-05 2018-08-15 2018-12-04 2018-09-14 2018-12-04 2018-10-19 2019-10-19 Semences de riz pour 2018 and production enhancement Envelope BI-PIU-68444-GO-COMM / 1. Smallholders’ productivity Single Stage - One IDA / D1810 Post Commodities Limited 101,330.00 0.00 Canceled 2018-06-29 2018-08-13 2018-07-04 2018-08-28 2018-08-15 2018-09-14 2018-10-19 2019-10-19 Semences de maîs and production enhancement Envelope BI-PIU-67843-GO-RFB / Acquisition de véhicules pour 4. Project management and Single Stage - One l'Unité Nationale de IDA / D1810 Post Request for Bids Open - National 525,000.00 569,318.74 Completed 2018-07-29 2018-08-07 2018-08-03 2018-09-14 2018-09-11 2018-10-14 2018-10-04 2018-11-18 2018-10-22 2019-01-17 2019-02-07 institutional support Envelope Coordination du Projet et ses Unités Provinciales BI-PIU-68430-GO-RFB / Matériel informatique (portables, ord bureau, photocopieuses petits et Under grands modèles, imprimantes 4. Project management and Request for Single Stage - One / Post Limited 64,400.00 178,043.12 Implementati 2018-08-04 2018-08-30 2018-09-29 2019-03-28 petits et grands modèles, institutional support Quotations Envelope on onduleurs, vidéoprojecteur, tablettes et GPS/Camera) pour l'UCP, UPCP et pour Assistance technique nationale BI-PIU-80735-GO-RFQ / Pending Acquisition de fumure 1. Smallholders’ productivity Request for Single Stage - One IDA / D1810 Post Open - National 169,729.00 0.00 Implementati 2018-10-14 2018-12-09 2019-06-07 organique pour le riz et le and production enhancement Quotations Envelope on maïs, saisons 2019 A BI-PIU-97676-GO-RFB / Acquisition de semences de 1. Smallholders’ productivity Single Stage - One IDA / D1810 Post Request for Bids Open - International 506,667.00 0.00 Canceled 2019-02-25 2019-04-22 2019-03-02 2019-04-13 2019-05-13 2019-06-17 2019-12-14 maïs pour les saisons 2019 C and production enhancement Envelope et 2020 A BI-PIU-97848-GO-RFB / Fourniture d'engrais 1. Smallholders’ productivity Single Stage - One chimiques pour les cultures IDA / D1810 Prior Request for Bids Open - International 2,153,074.00 0.00 Canceled 2019-03-01 2019-04-30 2019-03-06 2019-04-17 2019-05-17 2019-06-21 2019-12-18 and production enhancement Envelope de riz et de maïs des saisons culturales 2019 C et 2020 A Page 1 BI-PIU-97852-GO-RFB / Fourniture de produits 1. Smallholders’ productivity Single Stage - One phytosanitaires pour les IDA / D1810 Post Request for Bids Open - National 334,991.00 127,663.25 Completed 2019-03-01 2019-03-22 2019-03-06 2019-04-17 2019-04-24 2019-05-17 2019-05-14 2019-06-21 2019-06-21 2019-12-18 2019-08-01 and production enhancement Envelope cultures de riz et de maïs des saisons 2019 C et 2020 A BI-PIU-97822-GO-DIR / Under Acquisition de semences de 1. Smallholders’ productivity IDA / D1810 Post Direct Selection Direct 144,442.00 0.00 Implementati 2019-03-11 2019-03-11 2019-03-16 2019-05-27 2019-04-20 2019-10-17 riz pour les saisons culturales and production enhancement on 2019 c et 2020 A BI-PIU-115436-GO-RFQ / 1. Smallholders’ productivity Request for Single Stage - One Acquisition de vaccins contre IDA / D1810 Post Limited 49,630.00 39,695.62 Completed 2019-05-22 2019-05-24 2019-07-17 2019-09-11 2020-01-13 2019-11-14 and production enhancement Quotations Envelope la dermatose nodulaire BI-PIU-116361-GO-RFB / Acquisition d'engrais 1. Smallholders’ productivity Single Stage - One IDA / D1810 Post Request for Bids Limited 497,360.00 519,560.00 Completed 2019-05-23 2019-06-20 2019-05-28 2019-06-20 2019-07-09 2019-07-09 2019-08-08 2019-08-06 2019-09-12 2019-09-03 2020-03-10 2019-10-07 chimiques pour la saison and production enhancement Envelope agricole 2019 BI-PIU-122584-GO-RFQ / 1. Smallholders’ productivity Request for Single Stage - One Fourniture de semences de IDA / D1810 Post Limited 37,000.00 54,035.26 Completed 2019-07-20 2019-07-22 2019-09-14 2019-08-16 2020-03-12 2019-09-09 and production enhancement Quotations Envelope maïs pour la saison 2019 C BI-PIU-122587-GO-RFB / Acquisition de 5 camionnettes double-cabine 4x4 pour les Unités provinciales de 1. Smallholders’ productivity Single Stage - One IDA / D1810 Post Request for Bids Open - National 585,000.00 0.00 Canceled 2019-08-19 2019-09-06 2019-08-24 2019-10-05 2019-11-05 2019-11-04 2019-11-29 2019-12-09 2020-06-06 coordination du Projet et 4 and production enhancement Envelope camionnettes DC 4x4 pour les partenaires nationaux d'exécution du Projet BI-PIU-133018-GO-RFQ / Acquisition de semences Under 1. Smallholders’ productivity Request for Single Stage - One sélectionnées de maïs IDA / D1810 Post Limited 92,500.00 0.00 Implementati 2019-09-14 2019-09-09 2019-11-09 2020-05-07 and production enhancement Quotations Envelope composite pour la saison on culturale 2020 A BI-PIU-134181-GO-RFB / Acquisition d'engrais 1. Smallholders’ productivity Single Stage - One chimiques pour les cultures IDA / D1810 Post Request for Bids Open - National 1,347,000.00 0.00 Canceled 2019-09-17 2019-09-22 2019-11-03 2019-12-03 2020-01-07 2020-07-05 and production enhancement Envelope de riz et de maïs de la saison culturale 2020 A BI-PIU-143967-GO-RFQ / Pending Fourniture d'équipement 1. Smallholders’ productivity Request for Single Stage - One IDA / D1810 Post Limited 95,000.00 0.00 Implementati 2019-11-16 2020-01-11 2020-07-09 scolaire aux enfants Batwa de and production enhancement Quotations Envelope on la zone du PRDAIGL BI-PIU-150324-GO-RFB / Acquisition et fourniture de 1. Smallholders’ productivity Single Stage - One IDA / D1810 Post Request for Bids Open - International 750,000.00 602,927.17 Signed 2020-01-06 2020-01-30 2020-01-11 2020-02-10 2020-02-22 2020-03-19 2020-03-23 2020-04-07 2020-04-27 2020-08-17 2020-10-24 750 vaches laitières aux and production enhancement Envelope bénéficiaires du Projet BI-PIU-159139-GO-RFB / Acquisition de 45 1. Smallholders’ productivity Single Stage - One motocyclettes pour les IDA / D1810 Post Request for Bids Open - National 685,000.00 508,107.68 Completed 2020-02-12 2020-03-06 2020-02-17 2020-03-30 2020-04-09 2020-04-29 2020-05-05 2020-06-03 2020-06-12 2020-11-30 2020-12-10 and production enhancement Envelope partenaires publics d'exécution du Projet BI-PIU-159579-GO-RFB / Fourniture de 35 450 kg de 1. Smallholders’ productivity Single Stage - One IDA / D1810 Post Request for Bids Open - National 174,500.00 0.00 Canceled 2020-03-02 2020-03-07 2020-04-18 2020-05-18 2020-06-22 2020-12-19 Semences de maïs hybride de and production enhancement Envelope la saison 2020 C BI-PIU-169826-GO-RFB / Fourniture d'uniformes et sacs 1. Smallholders’ productivity Single Stage - One IDA / D1810 Post Request for Bids Open - National 97,500.00 79,987.52 Completed 2020-04-30 2020-05-27 2020-05-05 2020-06-16 2020-07-08 2020-07-16 2020-08-03 2020-08-20 2020-09-01 2021-02-16 2021-06-14 scolaires aux enfants Batwa and production enhancement Envelope de la zone du Projet BI-PIU-169919-GO-RFQ / Fourniture de semences Under 1. Smallholders’ productivity Request for Single Stage - One maraîchères aux bénéficiaires IDA / D1810 Post Limited 21,000.00 0.00 Implementati 2020-05-15 2020-05-28 2020-07-10 2021-01-06 and production enhancement Quotations Envelope du PRDAIGL pour la saison on culturale 2020 C BI-PIU-72461-GO-RFQ / 1. Smallholders’ productivity Single Stage - One Achat de pesticides pour le riz IDA / D1810 Post Request for Bids Open - National 147,530.00 138,235.50 Completed 2018-10-08 2018-10-18 2018-10-13 2018-11-24 2018-11-05 2018-12-24 2018-11-15 2019-01-28 2018-12-26 2019-07-27 2019-04-03 and production enhancement Envelope et le maïs BI-PIU-159188-GO-DIR / Fourniture de boutures de patate douce à chair orange aux bénéficiaires du Projet 1. Smallholders’ productivity Request for Single Stage - One des communes Buganda, IDA / D1810 Post Limited 22,600.00 0.00 Canceled 2020-05-16 2020-07-11 2021-01-07 and production enhancement Quotations Envelope Rugombo, Gihanga, Mpanda, Mutimbuzi, Kabezi, Muhuta, Bugarama, Rumonge et Nyanza-Lac BI-PIU-169363-GO-RFB / Fourniture de ciment pour appuyer les 1. Smallholders’ productivity Single Stage - One IDA / D1810 Post Request for Bids Open - National 105,000.00 67,228.39 Signed 2020-06-02 2020-06-30 2020-06-07 2020-07-19 2020-08-13 2020-08-18 2020-09-22 2020-09-22 2020-11-11 2021-03-21 bénéficiaires de bovins de la and production enhancement Envelope zone PRDAIGL dans la construction d'étables BI-PIU-159585-GO-DIR / Fourniture de 23 550 kg de Under Semences de riz de la saison 1. Smallholders’ productivity IDA / D1810 Post Direct Selection Direct 115,900.00 0.00 Implementati 2020-05-31 2020-06-09 2020-06-05 2020-06-10 2020-07-10 2021-01-06 2020 C par la Société and production enhancement on Régionale de Développement de l'Imbo (SRDI) BI-PIU-177131-GO-RFQ / Fourniture de trois mille deux cent (3200) boucles 1. Smallholders’ productivity Request for Single Stage - One IDA / D1810 Post Limited 14,000.00 11,342.48 Signed 2020-06-15 2020-06-16 2020-08-10 2020-09-03 2021-02-06 métalliques et quatre (4) and production enhancement Quotations Envelope pinces de marquage pour l’identification de bovins Page 2 BI-PIU-177662-GO-RFQ / Fourniture de semences sélectionnées de maïs 1. Smallholders’ productivity Request for Single Stage - One IDA / D1810 Post Limited 24,500.00 25,134.57 Completed 2020-06-13 2020-06-08 2020-08-08 2020-07-20 2021-02-04 2020-07-27 composite aux bénéficiaires and production enhancement Quotations Envelope de la zone du Projet pour la saison 2020 C BI-PIU-175670-GO-RFQ / Fourniture de boutures de patate douce à chair orange aux bénéficiaires du Projet 1. Smallholders’ productivity Request for Single Stage - One des communes Buganda, IDA / D1810 Post Limited 22,600.00 18,981.16 Completed 2020-06-14 2020-08-09 2020-07-20 2021-02-05 2020-08-21 and production enhancement Quotations Envelope Rugombo, Gihanga, Mpanda, Mutimbuzi, Kabezi, Muhuta, Bugarama, Rumonge et Nyanza-Lac BI-PIU-80732-GO-RFB / Acquisition d'engrais 1. Smallholders’ productivity Single Stage - One IDA / D1810 Post Request for Bids Open - National 1,400,300.00 700,292.00 Completed 2018-10-09 2018-10-18 2018-10-14 2018-11-25 2018-11-05 2018-12-25 2018-12-05 2019-01-29 2018-12-26 2019-07-28 2019-04-24 chimiques pour le riz et le and production enhancement Envelope maïs, saison 2019 A BI-PIU-191313-GO-RFQ / Fourniture de cahiers et 1. Smallholders’ productivity Request for Single Stage - One autres matériels scolaires aux IDA / D1810 Post Limited 36,400.00 0.00 Canceled 2020-09-13 2020-09-03 2020-11-08 2021-05-07 and production enhancement Quotations Envelope enfants Batwa de la zone du PRDAIGL BI-PIU-192732-GO-RFB / Fourniture de 172 vélos pour les moniteurs agricoles et les 1. Smallholders’ productivity Request for Single Stage - One IDA / D1810 Post Open - National 25,800.00 32,650.70 Completed 2020-09-19 2020-11-14 2021-03-09 2021-05-13 2021-05-05 agents de santé and production enhancement Quotations Envelope communautaire de la zone du PRDAIGL BI-PIU-192831-GO-RFB / Acquisition de kits d’accompagnement de bovins, 1. Smallholders’ productivity Single Stage - One de trousses chirurgicales à IDA / D1810 Post Request for Bids Open - National 263,880.00 113,627.37 Signed 2020-09-16 2020-09-30 2020-09-21 2020-11-02 2020-11-16 2020-12-02 2021-01-11 2021-01-06 2021-04-30 2021-07-05 and production enhancement Envelope usage vétérinaire ainsi que du matériel et équipements d'insémination artificielle BI-PIU-197210-GO-RFQ / 1. Smallholders’ productivity Request for Single Stage - One Fourniture de semences de IDA / D1810 Post Limited 1,320.00 0.00 Canceled 2020-10-10 2020-12-16 2020-12-05 2021-06-03 and production enhancement Quotations Envelope Haricots enrichis en fer BI-PIU-198298-GO-RFQ / Acquisition des boutures de Pending 1. Smallholders’ productivity Request for Single Stage - One bana grass pour appuyer les IDA / D1810 Post Open - National 83,000.00 0.00 Implementati 2020-10-19 2020-12-14 2021-06-12 and production enhancement Quotations Envelope futures bénéficiaires de on bovins BI-PIU-198751-GO-RFB / Under Acquisition du ciment pour 1. Smallholders’ productivity Single Stage - One IDA / D1810 Post Request for Bids Open - National 175,000.00 0.00 Implementati 2020-10-26 2020-12-29 2020-10-31 2021-01-06 2020-12-12 2021-02-22 2021-01-11 2021-02-15 2021-08-14 appuyer les bénéficiaires dans and production enhancement Envelope on la construction des étables BI-PIU-198756-GO-RFB / Under Acquisition de 1250 bovins 1. Smallholders’ productivity Single Stage - One IDA / D1810 Post Request for Bids Open - National 1,250,000.00 0.00 Implementati 2020-10-30 2020-12-21 2020-11-04 2020-12-30 2020-12-16 2021-02-18 2021-01-15 2021-02-19 2021-08-18 pour le développement de la and production enhancement Envelope on filière lait BI-PIU-211238-GO-RFQ / Pending Fourniture des semences 1. Smallholders’ productivity Request for Single Stage - One IDA / D1810 Post Open - National 32,083.00 0.00 Implementati 2021-01-16 2021-03-13 2021-09-09 maraichères pour les saisons and production enhancement Quotations Envelope on culturales 2021 B et C BI-PIU-211483-GO-RFB / Under Fourniture d'un liquéfacteur 1. Smallholders’ productivity Single Stage - One IDA / D1810 Post Request for Bids Open - International 1,200,000.00 0.00 Implementati 2021-01-05 2021-02-16 2021-01-10 2021-02-16 2021-02-21 2021-04-15 2021-03-23 2021-05-25 2021-04-27 2021-10-24 d'azote liquide et ses and production enhancement Envelope on accessoires BI-PIU-218327-GO-RFQ / Under 1. Smallholders’ productivity Request for Single Stage - One Fourniture de semences de IDA / D1810 Post Limited 1,320.00 0.00 Implementati 2021-02-20 2021-02-24 2021-04-17 2021-10-14 and production enhancement Quotations Envelope haricot enrichi en fer on BI-PIU-226611-GO-RFB / Acquisition des équipements, 3. Institutional integration, Pending réactifs et consommables de knowledge acquisition, and Single Stage - One IDA / D1810 Post Request for Bids Open - National 348,357.00 0.00 Implementati 2021-04-12 2021-04-17 2021-05-29 2021-06-28 2021-08-02 2022-01-29 laboratoires pour les Agences dissemination of information Envelope on d’Exécution du Projet at the regional level Nationales BI-PIU-226690-GO-RFB / Under Acquisition de kits 1. Smallholders’ productivity Single Stage - One IDA / D1810 Post Request for Bids Open - National 246,000.00 0.00 Implementati 2021-04-14 2021-05-31 2021-04-19 2021-06-10 2021-05-31 2021-06-30 2021-08-04 2022-01-31 d’accompagnement pour and production enhancement Envelope on 2250 bovins BI-PIU-226752-GO-RFQ / Acquisition de 280 kits Pending d’équipements pour les 1. Smallholders’ productivity Request for Single Stage - One IDA / D1810 Post Open - National 42,000.00 0.00 Implementati 2021-04-24 2021-06-19 2021-12-16 techniciens de terrain des and production enhancement Quotations Envelope on BPEAE et de la SRDI (bottines, imperméables, cartables) BI-PIU-226788-GO-RFQ / Under Fourniture de boutures de 1. Smallholders’ productivity Request for Single Stage - One IDA / D1810 Post Open - National 20,200.00 6,815.05 Implementati 2021-04-17 2021-06-12 2021-12-09 patate douce à chair orange and production enhancement Quotations Envelope on pour la saison 2021 C BI-PIU-226790-GO-RFQ / Fourniture de semences Under 1. Smallholders’ productivity Request for Single Stage - One maraichères aux bénéficiaires IDA / D1810 Post Open - National 16,070.00 10,810.80 Implementati 2021-04-20 2021-06-15 2021-12-12 and production enhancement Quotations Envelope du PRDAIGL pour la saison on 2021 C Page 3 BI-PIU-226749-GO-RFB / Acquisition des équipements informatiques pour l’Unité Nationale de Coordination, le Under 1. Smallholders’ productivity Single Stage - One Ministère de l’Environnement, IDA / D1810 Post Request for Bids Open - National 88,070.00 0.00 Implementati 2021-05-11 2021-05-10 2021-05-16 2021-05-18 2021-06-27 2021-07-27 2021-08-31 2022-02-27 and production enhancement Envelope de l’Agriculture et de l’Elevage on ainsi que les Agences d’Exécution du Projet Nationales BI-PIU-235898-GO-RFQ / Under Acquisition de 156 4. Project management and Request for Single Stage - One IDA / D1810 Post Limited 37,500.00 0.00 Implementati 2021-06-05 2021-06-01 2021-07-31 2022-01-27 smartphones pour la collecte institutional support Quotations Envelope on de données du PRDAIGL BI-PIU-237516-GO-RFB / Pending Fourniture de matériel 1. Smallholders’ productivity Single Stage - One IDA / D1810 Post Request for Bids Open - National 48,000.00 0.00 Implementati 2021-06-11 2021-06-16 2021-07-28 2021-08-27 2021-10-01 2022-03-30 scolaire aux écoliers et élèves and production enhancement Envelope on Batwa pour l’année 2021- 2022 BI-PIU-237625-GO-RFB / Fourniture de matériels de Pending communication et accessoires 4. Project management and Single Stage - One IDA / D1810 Post Request for Bids Open - National 15,250.00 0.00 Implementati 2021-06-11 2021-06-16 2021-07-28 2021-08-27 2021-10-01 2022-03-30 au Ministère de institutional support Envelope on l'Environnement, de l'Agriculture et de l'Elevage NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BI-PIU-68245-CS-CQS / Consultant Réalisation de la situation de 4. Project management and IDA / D1810 Post Qualification Open - National 45,000.00 0.00 Canceled 2018-07-03 2018-08-20 2018-07-24 2018-09-06 2018-10-06 2018-11-10 2019-05-09 référence des indicateurs du institutional support Selection Cadre de résultats BI-PIU-68413-CS-CQS / Consultant 4. Project management and Elaboration du manuel de IDA / D1810 Post Qualification Open - National 10,000.00 8,231.52 Completed 2018-06-29 2018-08-06 2018-07-20 2018-09-02 2018-09-27 2018-10-02 2018-11-22 2018-11-06 2018-12-05 2019-05-05 2020-03-16 institutional support gestion de matching grant Selection BI-PIU-68401-CS-CQS / Consultant 4. Project management and Under Informatisation du système de / Post Qualification Open - National 140,000.00 0.00 2018-06-29 2019-02-11 2018-07-20 2020-03-13 2018-09-02 2018-10-02 2018-11-06 2019-05-05 institutional support Implementation suivi-évaluation du Projet Selection BI-PIU-72463-CS-CQS / Recrutement d'une firme pour Consultant la réalisation d'une étude 4. Project management and IDA / D1810 Post Qualification Open - International 10,000.00 32,029.04 Completed 2018-08-06 2018-08-01 2018-08-27 2018-10-10 2018-11-14 2018-11-09 2018-11-15 2018-12-14 2018-12-06 2019-06-12 2019-04-30 socio-économique et institutional support Selection environnemental de la PPR auBurundi BI-PIU-72441-CS-QCBS / Audit institutionnel de la Consultant 1. Smallholders’ productivity CAPAD/recrutement et IDA / D1810 Post Qualification Limited 5,000.00 4,724.98 Completed 2018-12-19 2019-02-04 2019-01-02 2019-02-13 2019-02-01 2019-03-19 2019-03-08 2019-04-02 2019-09-04 2019-09-17 and production enhancement renforcement des capacités Selection d'une ONG BI-PIU-97229-CS-QCBS / ETUDE SUR LES OPPORTUNITES ET LES CONTRAINTES DE PARTICIPATION DES FEMMES, 1. Smallholders’ productivity Quality And Cost- DES JEUNES ET LES AUTRES IDA / D1810 Post Open - National 35,000.00 0.00 Canceled 2019-01-29 2019-07-28 2019-02-19 2019-04-04 2019-05-02 2019-06-01 2019-07-06 2019-08-10 2020-08-09 and production enhancement Based Selection CATEGORIES VULNERABLES DANS LES CHAINES DE VALEUR DES FILIERES MAIS, RIZ ET LAIT ET L'ELABORATION D'UNE STRATEGIE GENRE DU PROJET BI-PIU-97366-CS-QCBS / Audit institutionnel et organisationnel des Consultant 1. Smallholders’ productivity associations "Unissons-nous IDA / D1810 Post Qualification Open - National 10,000.00 8,899.44 Completed 2019-02-19 2019-05-06 2019-03-12 2019-06-26 2019-04-25 2019-11-29 2019-05-25 2020-01-20 2019-06-29 2020-01-31 2019-12-26 2020-06-29 and production enhancement pour la promotion des batwa" Selection (UNIPROBA) , Action Batwa et ADD BI-PIU-97351-CS-QCBS / Etudes de faisabilité techniques détaillées, surveillance et contrôle des travaux de développement 1. Smallholders’ productivity Quality And Cost- IDA / D1810 Prior Open - International 1,800,000.00 0.00 Under Review 2019-02-19 2019-04-30 2019-03-12 2019-08-12 2019-04-25 2020-02-26 2019-05-23 2020-04-28 2019-06-22 2020-09-02 2019-07-27 2019-08-31 2020-08-30 et/ou réhabilitation des and production enhancement Based Selection infrastructures d'irrigation dans les provinces Cibitoke (lot 1), Makamba et Rumonge (lot 2). BI-PIU-97336-CS-QCBS / Etudes de faisabilité techniques détaillées, surveillance et contrôle des travaux pour la reconstruction 1. Smallholders’ productivity Quality And Cost- IDA / D1810 Post Open - International 120,000.00 811,196.14 Signed 2019-03-13 2019-02-14 2019-04-03 2019-08-02 2019-05-17 2019-09-12 2019-06-14 2020-01-15 2019-07-14 2020-03-03 2019-08-18 2020-04-20 2019-09-22 2020-11-05 2020-09-21 du pont Kavimvira sur la and production enhancement Based Selection rivière Rusizi entre le Burundi et la RDC, au niveau de la TR 16 en commune Buganda, Province Cibitoke Page 4 BI-PIU-108936-CS-CQS / Recrutement d'un consultant Consultant chargé de l'élaboration d'un 4. Project management and IDA / D1810 Post Qualification Open - National 10,000.00 8,134.39 Completed 2019-04-04 2019-02-19 2019-04-25 2019-06-08 2019-09-30 2019-07-08 2019-12-12 2019-08-12 2020-01-06 2020-02-08 2021-05-14 guide de mécanismes de institutional support Selection gestion des plaintes et de recours BI-PIU-111339-CS-CQS / Etude d'évaluation et Consultant d'analyse de risques sanitaires 1. Smallholders’ productivity Under IDA / D1810 Post Qualification Limited 35,000.00 0.00 2019-04-20 2019-03-05 2019-05-04 2019-04-02 2019-06-03 2019-07-08 2020-01-04 liés à l'importation d'animaux and production enhancement Implementation Selection d'espèces bovine, caprine et ovine au Burundi BI-PIU-143963-CS-QCBS / Recrutement d’un bureau d’études pour la réalisation des études, du contrôle et de la surveillance (en option) 2. Support to investments in Quality And Cost- pour la construction IDA / D1810 agro-processing and market Post Open - National 100,000.00 0.00 Canceled 2019-11-18 2019-12-09 2020-01-22 2020-02-19 2020-03-20 2020-04-24 2020-05-29 2021-05-29 Based Selection d'infrastructures de gestion linkages post-récolte du maïs (hangars de stockage et aires de séchage) dans les 11 communes du PRDAIGL BI-PIU-143965-CS-CQS / Recrutement d’un bureau Consultant 4. Project management and Under chargé de la réalisation de la IDA / D1810 Post Qualification Open - National 65,000.00 0.00 2019-11-15 2019-12-13 2019-12-06 2020-01-19 2020-02-18 2020-03-24 2020-09-20 institutional support Implementation première enquête de Selection satisfaction des bénéficiaires BI-PIU-152782-CS-CQS / Recrutement de consultants pour l’actualisation de l'étude Consultant 1. Smallholders’ productivity institutionnelle et juridique de IDA / D1810 Post Qualification Open - National 65,000.00 0.00 Canceled 2020-01-27 2020-02-10 2020-02-17 2020-03-26 2020-04-01 2020-05-01 2020-06-05 2020-12-02 and production enhancement création et le fonctionnement Selection des Associations d'Usagers de l'Eau au niveau national BI-PIU-159612-CS-CQS / Recrutement d’un consultant 2. Support to investments in Consultant Under pour conduire l’incubation IDA / D1810 agro-processing and market Post Qualification Open - National 39,000.00 0.00 2020-03-16 2020-12-15 2020-04-06 2020-05-20 2020-06-19 2020-07-24 2021-01-20 Implementation des jeunes agro- linkages Selection entrepreneurs dans la zone du PRDAIGL BI-PIU-159596-CS-CQS / Recrutement d’un Bureau de consultants pour conduire 2. Support to investments in Consultant l’analyse sectorielle du climat Under IDA / D1810 agro-processing and market Post Qualification Open - National 40,000.00 0.00 2020-03-22 2020-10-20 2020-04-12 2020-12-10 2020-05-26 2021-04-15 2020-06-25 2020-07-30 2021-01-26 des affaires dans les chaînes Implementation linkages Selection de valeur ciblées par le PRDAIGL (riz, maïs et produits laitiers) dans la zone du Projet BI-PIU-164005-CS-CQS / Recrutement d'un bureau Consultant 4. Project management and pour effectuer l'audit externe IDA / D1810 Post Qualification Open - International 90,000.00 6,060.00 Completed 2020-03-23 2020-03-17 2020-04-13 2020-04-03 2020-05-27 2020-10-29 2020-06-26 2020-12-10 2020-07-31 2020-12-25 2021-01-27 2021-01-26 institutional support du PRDAIGL, exercices 2019- Selection 2022 BI-PIU-143961-CS-QCBS / Recrutement d’un bureau d’études chargé de la réalisation des études, du contrôle et de la surveillance 2. Support to investments in Quality And Cost- (en option) pour la IDA / D1810 agro-processing and market Post Open - National 240,000.00 0.00 Canceled 2019-11-18 2020-01-13 2019-12-09 2020-03-02 2020-01-22 2020-02-19 2020-03-20 2020-04-24 2020-05-29 2021-05-29 Based Selection réhabilitation/Construction linkages des pistes de désenclavement et d’accès aux marchés des zones à forte production du maïs, ainsi que BI-PIU-143961-CS-QCBS-2 / Etudes de faisabilité technique détaillées, surveillance et contrôle des travaux de 2. Support to investments in Quality And Cost- réhabilitation d'environ 74 km IDA / D1810 agro-processing and market Post Open - National 240,000.00 304,029.10 Signed 2020-07-27 2020-01-13 2020-08-17 2020-09-30 2020-06-12 2020-10-28 2020-07-24 2020-11-27 2020-08-31 2021-01-01 2020-10-20 2021-02-05 2021-02-22 2022-02-05 Based Selection de pistes de désenclavement linkages et d'accès aux marchés des zones de forte production de maïs et de lait (phase 1) BI-PIU-198765-CS-QCBS / Recrutement d’une Organisation Non Gouvernementale (ONG) locale spécialisée pour assurer la 1. Smallholders’ productivity Quality And Cost- restructuration des IDA / D1810 Prior Open - National 512,000.00 0.00 Canceled 2020-10-19 2021-01-18 2020-11-09 2020-12-23 2021-01-20 2021-02-19 2021-03-26 2021-04-30 2022-04-30 and production enhancement Based Selection organisations des producteurs, les accompagner dans la reconnaissance légale et assurer leur renforcement des capacités BI-PIU-205826-CS-CQS / ETUDE JURIDIQUE ET INSTITUTIONNELLE DE CREATION, STRUCTURATION Consultant ET FONCTIONNEMENT DES 1. Smallholders’ productivity Under IDA / D1810 Post Qualification 85,000.00 0.00 2020-11-27 2020-12-02 2020-12-18 2020-12-15 2021-01-31 2021-03-30 2021-03-02 2021-04-06 2021-10-03 ASSOCIATIONS D’USAGERS DE and production enhancement Implementation Selection L’EAU (AUE) POUR LA GESTION DURABLE DES PERIMETRES AMENAGES ET IRRIGUES AU BURUNDI. BI-PIU-206232-CS-CQS / Recrutement d'une Consultant 1. Smallholders’ productivity Pending Association des Batwa pour la IDA / D1810 Post Qualification Limited 12,000.00 0.00 2020-12-11 2020-12-25 2021-01-24 2021-02-28 2021-08-27 and production enhancement Implementation facilitation de la mise en Selection œuvre des Appuis des Batwa, Page 5 BI-PIU-226687-CS-QCBS / Etudes, surveillance et contrôle pour la construction d'infrastructures de stockage/transformation et de 2. Support to investments in Quality And Cost- Under commercialisation pour le riz IDA / D1810 agro-processing and market Post Open - International 366,200.00 0.00 2021-04-27 2021-05-18 2021-05-18 2021-07-01 2021-07-29 2021-08-28 2021-10-02 2021-11-06 2022-11-06 Based Selection Implementation et le maïs (lot 1), linkages d'infrastructures laitières (lot 2), et d’une usine de transformation de fruits et légumes (lot 3) BI-PIU-231479-CS-QCBS / Recrutement d’une Organisation Non Gouvernementale (ONG) locale spécialisée pour assurer la 1. Smallholders’ productivity Quality And Cost- Under restructuration des IDA / D1810 Prior Open - International 512,000.00 0.00 2021-04-30 2021-04-28 2021-05-21 2021-05-06 2021-07-04 2021-08-01 2021-08-31 2021-10-05 2021-11-09 2022-11-09 and production enhancement Based Selection Implementation organisations de producteurs, les accompagner dans la reconnaissance légale et assurer leur renforcement des capacités INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BI-PIU-68394-CS-CDS / Fourniture d'un logiciel 4. Project management and Under IDA / D1810 Post Direct Selection Direct 25,000.00 17,692.58 2018-06-29 2018-07-20 2018-07-09 2018-05-21 2018-09-12 2019-03-11 TOMPRO à l'Unité Nationale institutional support Implementation de Coordination du Projet BI-PIU-82999-CS-CDS / Formation du personnel du laboratoire national vétérinaire et des 4. Project management and responsables provinciaux IDA / D1810 Post Direct Selection Direct 8,500.00 3,990.00 Completed 2018-12-19 2018-10-30 2019-01-28 2018-11-30 2019-04-03 2019-03-25 2019-09-30 2019-04-04 institutional support d'élevage en bio-sécurité appliquée à la gestion des foyers de la fièvre de la Vallée du Rift BI-PIU-96796-CS-CDS / Convention de collaboration avec l'Institut des Sciences 1. Smallholders’ productivity IDA / D1810 Prior Direct Selection Direct 4,901,413.00 1,345,654.41 Signed 2019-02-19 2019-06-17 2019-03-01 2019-07-16 2019-05-05 2020-10-22 2019-11-01 agronomiques du Burundi and production enhancement (ISABU) dans le domaine de la Recherche-Développement BI-PIU-97439-CS-NPO / Convention de collaboration avec la Société Régionale de 1. Smallholders’ productivity Développement de l'Imbo IDA / D1810 Prior Direct Selection Direct 2,567,463.00 0.00 Canceled 2019-02-19 2019-07-12 2019-03-01 2020-02-12 2019-05-05 2019-11-01 and production enhancement (SRDI) pour l'encadrement des exploitants des périmètres de l'Imbo Centre BI-PIU-97483-CS-CDS / Convention de collaboration avec le Centre National de Technologie Alimentaire 1. Smallholders’ productivity IDA / D1810 Prior Direct Selection Direct 2,466,000.00 95,423.18 Signed 2019-02-25 2019-06-18 2019-03-07 2019-09-09 2019-05-11 2020-12-07 2019-11-07 (CNTA) pour la promotion de and production enhancement de la transformation et l'analyse des produits agro- alimentaires BI-PIU-68409-CS-CDS / Assistance technique IRRI 1. Smallholders’ productivity dans le renforcement des IDA / D1810 Prior Direct Selection Direct 5,653,037.00 5,653,037.00 Signed 2018-11-19 2019-06-14 2018-11-29 2019-09-09 2019-02-02 2020-06-29 2019-08-01 and production enhancement capacités des Institutions Nationales du secteur rizicole. BI-PIU-68081-CS-CDS / Assistance technique l'IITA dans aux institutions de 1. Smallholders’ productivity IDA / D1810 Prior Direct Selection Direct 5,234,185.00 3,784,832.00 Signed 2019-02-25 2019-06-14 2019-03-07 2019-09-06 2019-05-11 2020-06-29 2019-11-07 recherche, de développement and production enhancement et de commercialisation du maïs au Burundi BI-PIU-87427-CS-CDS / Assistance Technique de l'ILRI dans l'amélioration de la 1. Smallholders’ productivity IDA / D1810 Prior Direct Selection Direct 5,196,648.00 3,132,494.00 Signed 2019-02-28 2019-06-17 2019-03-10 2018-01-18 2019-05-14 2020-11-05 2019-11-10 productivité de la filière lait et and production enhancement la commercialisation du lait et des produits laitiers BI-PIU-111611-CS-INDV / Recrutement d'un consultant Individual individuel international 4. Project management and Under IDA / D1810 Post Consultant Open 50,000.00 0.00 2019-04-23 2019-05-21 2019-06-11 2019-09-20 2019-07-02 2019-08-06 2020-02-02 chargé de réaliser la situation institutional support Implementation Selection de référence pour l'évaluation de l'impact du Projet BI-PIU-121522-CS-INDV / Recrutement d'un consultant Individual 4. Project management and Under individuel national pour IDA / D1810 Post Consultant Open 45,000.00 0.00 2019-07-10 2019-07-12 2019-08-28 2019-09-18 2019-10-23 2020-04-20 institutional support Implementation l'étude de la situation de Selection référence de l'impact du Projet BI-PIU-128003-CS-INDV / Etude sur les opportunités et les contraintes de la participation des femmes, des Individual 1. Smallholders’ productivity jeunes et d’autres catégories IDA / D1810 Post Consultant Open 35,000.00 16,198.50 Completed 2019-08-19 2019-08-03 2019-10-07 2020-01-20 2019-10-28 2020-03-11 2019-12-02 2020-04-03 2020-05-30 2020-07-20 and production enhancement vulnérables dans les chaînes Selection de valeur des filières maïs, riz et lait et l’élaboration d’une stratégie genre du projet. Page 6 BI-PIU-128005-CS-INDV / Recrutement d’un consultant Individual 4. Project management and Under chargé de la facilitation IDA / D1810 Post Consultant Limited 2,500.00 0.00 2019-08-19 2019-09-05 2019-08-24 2019-09-14 2019-10-19 2020-04-16 institutional support Implementation /animation d’une retraite du Selection personnel du PRDAIGL. BI-PIU-143909-CS-INDV / Recrutement d’un consultant national chargé de la Individual consolidation des documents 1. Smallholders’ productivity Under IDA / D1810 Post Consultant Open 7,000.00 0.00 2019-11-18 2019-12-17 2020-01-06 2020-01-27 2020-03-02 2020-08-29 et la capitalisation des and production enhancement Implementation Selection expériences pour la formation des Agents Communautaires pour la Santé Animale BI-PIU-143891-CS-CDS / Convention de collaboration avec le Bureau provincial de 1. Smallholders’ productivity IDA / D1810 Post Direct Selection Direct 293,000.00 0.00 Canceled 2019-12-22 2020-01-10 2020-01-01 2020-03-23 2020-03-06 2020-09-02 l’Environnement, de and production enhancement l’Agriculture et de l’Elevage (BPEAE) de Rumonge BI-PIU-143888-CS-CDS / Convention de collaboration avec le Bureau provincial de 1. Smallholders’ productivity IDA / D1810 Post Direct Selection Direct 200,000.00 0.00 Canceled 2019-12-22 2020-01-02 2020-01-01 2020-03-23 2020-03-06 2020-09-02 l’Environnement, de and production enhancement l’Agriculture et de l’Elevage (BPEAE) de Makamba BI-PIU-143609-CS-CDS / Convention de collaboration avec le Bureau provincial de 1. Smallholders’ productivity IDA / D1810 Post Direct Selection Direct 211,000.00 0.00 Canceled 2019-12-22 2020-01-02 2020-01-01 2020-03-23 2020-03-06 2020-09-02 l’Environnement, de and production enhancement l’Agriculture et de l’Elevage (BPEAE) de Bubanza BI-PIU-143616-CS-CDS / Convention de collaboration avec le Bureau provincial de 1. Smallholders’ productivity IDA / D1810 Post Direct Selection Direct 219,000.00 0.00 Canceled 2019-12-22 2020-01-10 2020-01-01 2020-03-23 2020-03-06 2020-09-02 l’Environnement, de and production enhancement l’Agriculture et de l’Elevage (BPEAE) de Bujumbura BI-PIU-143732-CS-CDS / 8. Convention de collaboration avec le Bureau provincial de 1. Smallholders’ productivity IDA / D1810 Post Direct Selection Direct 266,500.00 0.00 Canceled 2019-12-22 2020-01-09 2020-01-01 2020-03-23 2020-03-06 2020-09-02 l’Environnement, de and production enhancement l’Agriculture et de l’Elevage (BPEAE) de Cibitoke BI-PIU-153074-CS-INDV / Individual Traduction du manuel sur la 1. Smallholders’ productivity IDA / D1810 Post Consultant Open 8,000.00 0.00 Canceled 2020-02-03 2020-03-23 2020-04-13 2020-05-18 2020-11-14 méthodologie GALS dans la and production enhancement Selection langue nationale BI-PIU-153088-CS-CDS / Contractualisation de la Chambre Fédérale de Commerce et d’Industrie du 2. Support to investments in Under Burundi (CFCIB) pour assurer IDA / D1810 agro-processing and market Post Direct Selection 33,740.00 0.00 2020-02-03 2020-02-11 2020-02-03 2021-01-13 2020-02-03 2020-02-03 Implementation la sensibilisation pour linkages l’amélioration du climat des affaires dans le domaine agricole BI-PIU-152777-CS-CQS / Individual Elaboration du Plan d'Action 1. Smallholders’ productivity Under IDA / D1810 Post Consultant Open 40,000.00 0.00 2020-02-12 2020-03-03 2020-04-01 2020-07-30 2020-04-22 2020-05-27 2020-11-23 en Faveur des peuples and production enhancement Implementation Selection autochtones Batwa BI-PIU-159386-CS-INDV / Individual Elaboration d'un état des lieux 1. Smallholders’ productivity Under IDA / D1810 Post Consultant Open 10,000.00 0.00 2020-02-20 2020-03-03 2020-04-09 2020-04-30 2020-06-04 2020-12-01 sur la culture et le savoir-faire and production enhancement Implementation Selection des Batwa BI-PIU-198519-CS-INDV / Recrutement d’un consultant Individual national individuel chargé 4. Project management and IDA / D1810 Post Consultant Open 50,000.00 14,764.69 Signed 2020-10-16 2020-10-19 2020-12-04 2020-11-12 2020-12-25 2020-11-16 2021-01-29 2020-11-24 2021-07-28 d’élaborer le rapport institutional support Selection d’avancement du PRDAIGL pour la revue à mi-parcours BI-PIU-201540-CS-INDV / Recructement d'un Consultant Individual 1. Smallholders’ productivity Pending pour la formation des agences IDA / D1810 Post Consultant Open 20,000.00 0.00 2020-12-08 2021-01-26 2021-02-16 2021-03-23 2021-09-19 and production enhancement Implementation d'exécution sur l'approche Selection genre et inclusion sociale BI-PIU-201591-CS-INDV / Recrutement d'un consultant Individual pour l'appui aux institutions, 1. Smallholders’ productivity IDA / D1810 Post Consultant Open 49,500.00 0.00 Canceled 2020-12-04 2021-01-22 2021-02-12 2021-03-19 2021-09-15 structures et organisations and production enhancement Selection partenaires à conduire une auto-analyse genre BI-PIU-211463-CS-INDV / Individual Recrutement d'un consultant 4. Project management and IDA / D1810 Post Consultant Limited 35,000.00 30,801.00 Signed 2020-12-29 2021-01-14 2021-01-03 2021-02-08 2021-01-24 2021-03-30 2021-02-28 2021-04-07 2021-08-27 expérimenté d'appui en institutional support Selection passation des marchés BI-PIU-211905-CS-INDV / Recrutement d'un(e) Individual 4. Project management and Under Informaticien(ne), IDA / D1810 Post Consultant Open 22,000.00 0.00 2021-01-07 2021-01-04 2021-02-25 2021-03-18 2021-04-22 2021-10-19 institutional support Implementation Administrateur (trice) de Selection bases de données du PRDAIGL BI-PIU-212835-CS-INDV / Recrutement de Mr Jery Rambao expert en évaluation Individual 4. Project management and Under d’impact pour l'établissement IDA / D1810 Post Consultant Direct 50,000.00 0.00 2021-01-15 2021-04-27 2021-01-25 2021-05-27 2021-02-15 2021-03-22 2021-09-18 institutional support Implementation de la situation de référence Selection pour l'évaluation de l'impact du PRDAIGL Page 7 BI-PIU-219119-CS-INDV / Recrutement d'un Individual 4. Project management and Under Responsable de IDA / D1810 Post Consultant Open 22,000.00 0.00 2021-02-17 2021-02-20 2021-04-07 2021-04-28 2021-06-02 2021-11-29 institutional support Implementation l'agrobusiness au sein de Selection l'Unité Nationale de Coordination du PRDAIGL BI-PIU-226773-CS-CQS / Recrutement d’un Consultant 3. Institutional integration, chargé de l’élaboration du Individual knowledge acquisition, and Pending Plan Directeur de la Recherche IDA / D1810 Post Consultant Limited 80,000.00 0.00 2021-04-15 2021-04-20 2021-05-11 2021-06-15 2021-12-12 dissemination of information Implementation du Centre National de Selection at the regional level Technologies Agroalimentaires (CNTA) BI-PIU-226775-CS-CQS / Recrutement d’un Consultant chargé de l’évaluation des 3. Institutional integration, Individual besoins des services de knowledge acquisition, and Pending IDA / D1810 Post Consultant Limited 40,000.00 0.00 2021-04-16 2021-04-21 2021-05-12 2021-06-16 2021-12-13 laboratoire de l’ISABU et du dissemination of information Implementation Selection CNTA en fonction des at the regional level priorités des chaines de valeur du maïs, du riz et du lait BI-PIU-226786-CS-INDV / Recrutement de Monsieur Individual 4. Project management and Under NDUHIRUBUSA Jérémie pour IDA / D1810 Post Consultant Direct 33,000.00 0.00 2021-04-12 2021-05-04 2021-04-22 2021-05-28 2021-05-13 2021-06-14 2021-06-17 2021-12-14 institutional support Implementation l’analyse et le suivi des sous- Selection projets BI-PIU-237530-CS-INDV / Recrutement d'un Individual 4. Project management and Under Responsable de la IDA / D1810 Post Consultant Open 17,500.00 0.00 2021-06-08 2021-06-04 2021-07-27 2021-08-17 2021-09-21 2022-03-20 institutional support Implementation Communication au Sein de Selection l'Unité Nationale de Coordination du Projet Page 8 Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan[Original: December 2015]: Last Revision of Updated Procurement Plan, Feb 2017] 2. Date of General Procurement Notice: June 25, 2015 3. Period covered by this procurement plan: From December 2015 Till end of December 2017 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Comments Threshold US$ 1. NCB (Goods) Above US$ 1,500,000 All 2. Shopping (Goods) Above US$ 500,000 All 2. Pre-qualification. "Not Applicable" 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: "Not applicable" 4. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan # 8496-EG, Project # P145699 prepared by SSSNP PMU on 6th May 2015 5. Any Other Special Procurement Arrangements: None May 24, 2017 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness 1 2 3 4 5 6 7 Ref. Descripti Estimat Packages Dome Review Comme No. on ed stic by Bank nts Cost Prefe (Prior / US$ rence Post) (yes/ no) Supply of Computers , laptops, software and other IT 400,00 NCB G-05 equipment 1 No Post 0 (Goods) for MOSS Departmen ts in27 Governorat es Printing & Shoppi G-07 Publication 50,000 1 No Post ng s (Goods) Furniture Shoppi & G-08 Equipment 50,000 1 No Post ng for the (Goods) PMU Video & Shoppi Graphics G-09 equipment 4,000 1 No Post ng for MOSS (Goods) Customer Collaborati on Solution Shoppi G-11 for 45,000 1 No Post ng Grievance (Goods) (call center) III. Selection of Consultants May 24, 2017 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comments Threshold 1. QCBS (Consulting Firms) Above US$ 500,000 2. IC (Individual Consultant) Above US$ 200,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: None 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description of Estimat Packa Review Comment Assignment ed ges by Bank s Cost (Prior / US$ Post) CF-05 Institutional consultancy to conduct 120,00 airing 1 Post QCBS 0 adverstismen t+Video + radio CF-06 Local community dialogues 50,000 1 Post QCBS regular administratio n CF-08 Communicati on Firm (Advocacy Strategy, 150,00 Communicati 1 Post QCBS 0 on Strategy, Design materials, etc) CF-09 Technical/the 75,000 1 Post QCBS May 24, 2017 matic capacity building (M&E, MIS, grievance, conditionality , social responsibility , NGOs TOT, etc.) IC-30 Hiring Office Manager for 30,000 1 Post IC the Program May 24, 2017 PROCUREMENT Egypt, Arab Republic of : Strengthening Social Safety Net Project PLAN General Information Country: Egypt, Arab Republic of Bank’s Approval Date of the Original Procurement Plan: 2017-05-31 2021-05-24 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P145699 GPN Date: Project Name: Strengthening Social Safety Net Project Loan / Credit No: IBRD / 84960, IBRD / 89970 Ministry of Social Solidarity Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual EG-MOSS-11483-GO-RFQ / Support SSN Targeting and Request for Single Stage - One IBRD / 84960 Post Limited 50,000.00 2,241.79 Completed 2017-07-06 2017-05-05 2017-08-31 2017-05-14 2018-02-27 2017-05-25 Printing and Publications Operational Systems Quotations Envelope EG-MOSS-11486-GO-RFQ / Support SSN Targeting and Request for Single Stage - One Furniture and Equipment for IBRD / 84960 Post Limited 50,000.00 6,323.62 Completed 2017-08-06 2017-07-19 2017-10-01 2017-07-26 2018-03-30 2017-07-29 Operational Systems Quotations Envelope the PMU EG-MOSS-11489-GO-RFQ / Support SSN Targeting and Request for Single Stage - One Video & Graphics Equipment IBRD / 84960 Post Limited 4,000.00 0.00 Canceled 2017-07-07 2017-09-01 2018-02-28 Operational Systems Quotations Envelope for MOSS EG-MOSS-17356-GO-RFQ / Customer Collaboration Solution (grievance) . This solution combines traditional contact center technology and Project Management and Request for Single Stage - One processes with important IBRD / 84960 Post Limited 45,000.00 0.00 Canceled 2017-07-02 2017-07-23 2018-01-19 Monitoring and Evaluation Quotations Envelope additions in recording, agent workspaces, social media and video to help build deeper relationships with our customers EG-MOSS-18410-GO-RFQ / we want to procure 330 scanner so that the grievance system can work through the Moss units in the Project Management and Request for Single Stage - One governorates and no need for IBRD / 84960 Post Limited 70,000.00 0.00 Canceled 2017-07-06 2017-07-04 2017-08-31 2018-02-27 Monitoring and Evaluation Quotations Envelope the appellant to come to the ministry in Cairo, as the appellant usually submit documents with his complaint so we have to scan EG-MOSS-21361-GO-RFQ / Project Management and Request for Single Stage - One Communication equipment's IBRD / 84960 Post Limited 1,500.00 952.01 Completed 2017-08-08 2017-07-30 2017-10-03 2017-08-03 2018-04-01 2017-08-06 Monitoring and Evaluation Quotations Envelope for PMU staff EG-MOSS-23406-GO-RFQ / Under Project Management and Request for Single Stage - One Procuring Tablets for Social IBRD / 84960 Post Limited 95,000.00 49,070.63 Implementati 2017-09-05 2017-08-14 2017-10-31 2017-09-07 2018-04-29 2017-09-14 Monitoring and Evaluation Quotations Envelope Administration on EG-MOSS-23414-GO-RFQ / Project Management and Request for Single Stage - One Procuring Chargers for IBRD / 84960 Post Limited 5,000.00 7,447.63 Completed 2017-08-18 2017-08-21 2017-10-13 2017-09-13 2018-04-11 2017-11-06 Monitoring and Evaluation Quotations Envelope existing tablets EG-MOSS-23481-GO-RFQ / Project Management and Request for Single Stage - One Procuring Office Machinery for IBRD / 84960 Post Limited 1,000.00 0.00 Canceled 2017-09-08 2017-11-03 2018-05-02 Monitoring and Evaluation Quotations Envelope the PMU EG-MOSS-25146-GO-RFQ / Under Designing and Printing of the Project Management and Request for Single Stage - One IBRD / 84960 Post Limited 100,000.00 0.00 Implementati 2017-10-06 2017-08-29 2017-12-01 2018-05-30 Ministry of Social Solidarity Monitoring and Evaluation Quotations Envelope on (MOSS) Promotional Materials EG-MOSS-25158-GO-RFQ / Project Management and Request for Single Stage - One printing business cards for IBRD / 84960 Post Limited 1,200.00 0.00 Canceled 2017-11-06 2018-01-01 2018-06-30 Monitoring and Evaluation Quotations Envelope the PMU EG-MOSS-25161-GO-RFQ / Under Project Management and Request for Single Stage - One Procuring computers for IBRD / 84960 Post Limited 6,000.00 0.00 Implementati 2017-11-06 2017-09-11 2018-01-01 2018-06-30 Monitoring and Evaluation Quotations Envelope Service improvement unit on EG-MOSS-34988-GO-RFQ / Project Management and Request for Single Stage - One Printing 1,500,000 Takaful & IBRD / 84960 Post Limited 45,000.00 7,635.01 Signed 2018-01-06 2017-11-12 2018-03-03 2018-12-28 2018-08-30 Monitoring and Evaluation Quotations Envelope Karama application EG-MOSS-54103-GO-RFQ / Shopping purchase: 5 laptops, 2 PCs, 5 flash memories, 5 Project Management and Request for Single Stage - One antivirus, 4 external hard IBRD / 84960 Post Limited 7,000.00 0.00 Canceled 2018-03-18 2018-04-15 2018-05-06 Monitoring and Evaluation Quotations Envelope disks, 1 camera stand, 1 hand microphone, 1 ear microphones, EG-MOSS-60796-GO-RFQ / Purchase of IT equipment for Under extended PMU staff (10 Project Management and Request for Single Stage - One IBRD / 84960 Post Limited 6,000.00 0.00 Implementati 2018-04-30 2018-05-28 2018-06-25 2018-12-22 laptops + 10 antivirus + 10 Monitoring and Evaluation Quotations Envelope on electricity connector extensions + 5 modems) Page 1 EG-MOSS-68986-GO-RFQ / Professional Conference call, sound system, projectors, Support SSN Targeting and Request for Single Stage - One IBRD / 84960 Post Limited 50,000.00 28,642.28 Completed 2018-07-29 2018-08-05 2018-08-12 2018-08-29 2018-09-21 2018-09-06 screens and TVs for the Operational Systems Quotations Envelope meeting halls in the ministry (MoSS) head quarter EG-MOSS-70745-GO-RFQ / Purchase 10 photocopier, 20 Support SSN Targeting and Request for Single Stage - One photocopier toners , 65 IBRD / 84960 Post Limited 30,000.00 0.00 Canceled 2018-08-01 2018-08-20 2018-09-19 Operational Systems Quotations Envelope printer toners and 5 inkjet printer. EG-MOSS-66112-GO-RFQ / Purchase Air conditioning, Project Management and Request for Single Stage - One Kitchen electrical devices, IBRD / 84960 Post Limited 15,000.00 4,158.42 Signed 2018-06-23 2018-07-11 2018-07-23 2018-07-30 2018-08-22 Monitoring and Evaluation Quotations Envelope ceiling fans and water cooler tank EG-MOSS-70746-GO-RFQ / Purchase of metal units for Support SSN Targeting and Request for Single Stage - One IBRD / 84960 Post Limited 40,000.00 316,654.86 Signed 2018-07-29 2018-08-28 2018-09-23 2018-09-10 2018-12-22 2018-09-28 filing - Office furniture - Operational Systems Quotations Envelope Curtains for PMU office. EG-MOSS-71078-GO-RFQ / Purchasing: Printing paper Support SSN Targeting and Request for Single Stage - One IBRD / 84960 Post Limited 15,000.00 13,499.54 Completed 2018-08-10 2018-09-06 2018-10-05 2018-09-18 2019-04-03 2018-10-16 size (A4 & A3) and stationary Operational Systems Quotations Envelope (e.g: pen, folders ..etc) EG-MOSS-76938-GO-RFQ / Purchasing Racks for the PMU's equipments: Support SSN Targeting and Request for Single Stage - One IBRD / 84960 Post Limited 4,500.00 0.00 Canceled 2018-09-15 2018-10-11 2018-11-10 1- The main routers in MoSS Operational Systems Quotations Envelope 2- Equipment for discussion systems in MoSS EG-MOSS-78331-GO-RFQ / Providing Compact Stand Kiosk for some social units. Support SSN Targeting and Request for Single Stage - One IBRD / 84960 Post Limited 60,000.00 29,280.82 Signed 2018-09-25 2018-11-01 2018-11-20 2018-12-20 2019-03-20 Each kiosk will include a tablet Operational Systems Quotations Envelope to receive information from T&K beneficiaries. EG-MOSS-71077-GO-RFQ / Printing T&K's logo on block- Under Support SSN Targeting and Request for Single Stage - One notes, personal cards, pen, IBRD / 84960 Post Limited 90,000.00 0.00 Implementati 2018-07-31 2018-10-23 2018-09-25 2018-11-24 Operational Systems Quotations Envelope bags, paper folders ..etc. on Printing Broshers, pock-let EG-MOSS-81693-GO-RFQ / Support SSN Targeting and Request for Single Stage - One Purchase 2650 electricity IBRD / 84960 Post Limited 80,000.00 0.00 Canceled 2018-11-23 2019-01-02 2019-04-02 Operational Systems Quotations Envelope connectors EG-MOSS-85351-GO-RFQ / Under Purchase web application to Project Management and Request for Single Stage - One IBRD / 84960 Post Limited 90,000.00 0.00 Implementati 2018-11-16 2018-11-18 2018-12-21 2019-03-21 manage TKP depository as Monitoring and Evaluation Quotations Envelope on CMS & LMS. EG-MOSS-85354-GO-RFQ / Project Management and Request for Single Stage - One Purchase network cable & IBRD / 84960 Post Limited 3,000.00 0.00 Canceled 2018-11-13 2018-12-15 2019-01-14 Monitoring and Evaluation Quotations Envelope Mobile phones EG-MOSS-81695-GO-RFB / Lot(A) Supply & install 5100 Thin-clients in social units (Lot B) Supply (1,300) LaserJet Printers Support SSN Targeting and Single Stage - One (Lot C) Supply (2,300) IBRD / 84960 Prior Request for Bids Open - International 7,000,000.00 3,537,297.47 Signed 2018-12-12 2018-12-27 2018-12-20 2019-06-18 2019-02-03 2019-03-03 2019-02-17 2019-06-20 2019-03-10 2019-07-11 2019-07-08 Operational Systems Envelope Scanners (Lot D) Supply (2,650) IP Phones (Lot E) Supply 500 LaserJet Toners for existing printers EG-MOSS-81682-GO-RFQ / Purchase Telephone devices, Support SSN Targeting and Request for Single Stage - One Fax devices, IP-Phones & IBRD / 84960 Post Limited 15,000.00 6,998.58 Completed 2018-10-15 2018-10-16 2018-10-26 2018-10-21 2018-11-25 2018-10-23 Operational Systems Quotations Envelope licenses for IP-Phones for the PIU EG-MOSS-130517-GO-RFQ / Supply and install of networking infrastructure for Support SSN Targeting and Request for Single Stage - One IBRD / 84960 Post Limited 90,000.00 73,736.13 Signed 2019-09-10 2019-07-24 2019-11-05 2019-08-19 2020-05-03 200 rehabilitation offices of Operational Systems Quotations Envelope the Ministry of Social Solidarity offices. EG-MOSS-132894-GO-RFQ / Support SSN Targeting and Request for Single Stage - One Printings of the Conditionality IBRD / 84960 Post Limited 35,000.00 25,787.70 Completed 2019-09-10 2019-05-23 2019-11-05 2019-05-30 2020-05-03 2019-06-02 Operational Systems Quotations Envelope Registries EG-MOSS-135529-GO-RFQ / Support SSN Targeting and Request for Single Stage - One IBRD / 84960 Post Limited 10,000.00 6,026.97 Signed 2019-09-29 2019-08-04 2019-11-24 2019-09-15 2020-05-22 Toner cartridges Operational Systems Quotations Envelope EG-MOSS-135562-GO-RFQ / Support SSN Targeting and Request for Single Stage - One Printing Takaful and Karama IBRD / 84960 Post Limited 15,000.00 14,524.10 Signed 2019-09-29 2019-07-15 2019-11-24 2019-08-04 2020-05-22 Operational Systems Quotations Envelope questionnaire . EG-MOSS-121002-GO-RFB / Project Management and Single Stage - One Conditionality Registers and IBRD / 84960 Post Request for Bids Open - National 200,000.00 128,671.06 Completed 2019-06-30 2019-07-02 2019-07-05 2019-08-16 2019-07-10 2019-09-15 2019-07-21 2019-10-20 2019-09-15 2020-04-17 2019-10-01 Monitoring and Evaluation Envelope Booklets BULK Printing EG-MOSS-133550-GO-RFQ / Support SSN Targeting and Request for Single Stage - One IBRD / 84960 Post Limited 1,000.00 807.30 Completed 2019-09-14 2019-07-21 2019-11-09 2019-07-25 2020-05-07 2019-07-29 Conditionality training guide Operational Systems Quotations Envelope EG-MOSS-144416-GO-RFQ / Support SSN Targeting and Request for Single Stage - One Network Fault & performance IBRD / 84960 Post Limited 90,000.00 90,905.31 Signed 2019-11-12 2019-11-21 2020-01-07 2019-12-19 2020-07-05 Operational Systems Quotations Envelope management system Page 2 EG-MOSS-147022-GO-RFB / Supply of networking switches Support SSN Targeting and Single Stage - One IBRD / 84960 Post Request for Bids Open - National 340,000.00 308,079.66 Signed 2019-12-20 2020-01-19 2019-12-25 2020-02-05 2020-02-16 2020-03-06 2020-04-02 2020-04-10 2020-04-15 2020-10-07 for 344 administrations and Operational Systems Envelope directorates of the MoSS EG-MOSS-35566-GO-RFB / Project Management and Single Stage - One Automation of MOSS social IBRD / 84960 Post Request for Bids Open - National 1,000,000.00 0.00 Canceled 2017-11-16 2017-11-21 2018-01-02 2018-02-01 2018-03-08 2018-09-04 Monitoring and Evaluation Envelope units, procuring 4500 tablet EG-MOSS-151897-GO-RFQ / Support SSN Targeting and Request for Single Stage - One Printings of Job evaluation IBRD / 84960 Post Limited 94,000.00 0.00 Canceled 2019-12-31 2020-06-02 2020-02-25 2020-08-23 Operational Systems Quotations Envelope forms EG-MOSS-154634-GO-RFQ / Support SSN Targeting and Request for Single Stage - One IBRD / 84960 Post Limited 45,000.00 19,377.06 Completed 2020-01-25 2019-12-09 2020-03-21 2020-02-19 2020-09-17 2020-03-01 stationery and office supplies Operational Systems Quotations Envelope EG-MOSS-163926-GO-RFQ / Furniture and air condition for Support SSN Targeting and Request for IBRD / 84960 Post 5,000.00 720.63 Completed 2020-03-10 2020-03-10 2020-03-29 2020-03-10 2020-04-12 Takaful and Karama program Operational Systems Quotations director’s office EG-MOSS-165397-GO-RFQ / Supply and install of flexible anti-fire ducts, network Support SSN Targeting and Request for Single Stage - One cables, electricity power exit IBRD / 84960 Post Limited 9,000.00 0.00 Canceled 2020-03-27 2020-05-22 2020-11-18 Operational Systems Quotations Envelope duct socket for rack, face plates to construct fifty (50) network nodes. EG-MOSS-154659-GO-RFQ / The objective of this procurement activity is to purchase disability Support SSN Targeting and Request for Single Stage - One assessment kits. Some of IBRD / 84960 Post Limited 37,000.00 50,811.43 Completed 2020-01-25 2020-02-09 2020-03-21 2020-02-27 2020-09-17 2020-03-01 Operational Systems Quotations Envelope items that the kits contain are alphabet wooden board, coins, group of cubes, scissors, .. etc. EG-MOSS-165406-GO-RFQ / This activity is to purchase queue system, furniture for the grievance room, supply and install both electricity and Support SSN Targeting and Request for Single Stage - One IBRD / 84960 Post Limited 95,000.00 117,830.96 Completed 2020-03-28 2020-04-22 2020-05-23 2020-05-10 2020-11-19 2020-07-17 data cables for the queue Operational Systems Quotations Envelope system, and supply and install a partition for the waiting area annexed to the grievance room. Complete lot. EG-MOSS-172044-GO-RFQ / Support SSN Targeting and Request for Single Stage - One IBRD / 84960 Post Limited 100,000.00 90,000.00 Terminated 2020-05-11 2020-05-07 2020-07-06 2020-05-11 2021-01-02 Database replication server Operational Systems Quotations Envelope EG-MOSS-173387-GO-RFQ / Masks, gloves, alcohol, and Support SSN Targeting and Request for Single Stage - One sterilization materials against IBRD / 84960 Post Limited 9,000.00 10,985.56 Completed 2020-05-22 2020-05-10 2020-07-17 2020-06-17 2021-01-13 2020-06-21 Operational Systems Quotations Envelope Corona Virus for the team work. EG-MOSS-180023-GO-RFQ / Support SSN Targeting and Request for Single Stage - One Laptop computers and IBRD / 84960 Post Limited 50,000.00 25,643.84 Completed 2020-06-30 2020-06-17 2020-08-25 2020-06-22 2021-02-21 2020-06-25 Operational Systems Quotations Envelope photocopiers EG-MOSS-191265-GO-RFQ / Network passive components such as Rj45 Cat6, crimper, Support SSN Targeting and Request for Single Stage - One tester, Box-UTP-Cat6 -305M, IBRD / 84960 Post Limited 13,000.00 6,973.06 Signed 2020-09-11 2020-09-06 2020-11-06 2020-09-24 2021-05-05 Operational Systems Quotations Envelope and unmanaged switch 8 port, for the social administrations’ network. EG-MOSS-191257-GO-RFQ / Furnishing the Information Center of Takaful and Karama Program with chairs, desks, Support SSN Targeting and Request for Single Stage - One smart screen, uniform and ID IBRD / 84960 Post Limited 19,000.00 15,863.49 Signed 2020-09-11 2020-08-16 2020-11-06 2020-09-03 2021-05-05 Operational Systems Quotations Envelope cards for the receptionist team, internal signage, lighting units, data cabling, … etc. EG-MOSS-197489-GO-RFQ / Support SSN Targeting and Request for Single Stage - One Six access control doors IBRD / 84960 Post Limited 10,000.00 7,958.74 Signed 2020-11-03 2020-10-11 2020-12-29 2020-11-02 2021-06-27 Operational Systems Quotations Envelope system. EG-MOSS-197499-GO-RFQ / Number of twenty laptop Support SSN Targeting and Request for Single Stage - One IBRD / 84960 Post Limited 25,000.00 17,455.36 Completed 2020-11-10 2020-10-12 2021-01-05 2020-10-13 2021-07-04 2020-10-18 computers for Takaful and Operational Systems Quotations Envelope Karama. EG-MOSS-203695-GO-RFQ / Support SSN Targeting and Request for Single Stage - One Supplying Tablets for the IBRD / 84960 Post Limited 100,000.00 94,736.84 Completed 2020-11-17 2021-02-01 2021-01-12 2021-03-30 2021-07-11 2021-04-05 Operational Systems Quotations Envelope social unit. EG-MOSS-204563-GO-RFQ / Pending Support SSN Targeting and Request for Single Stage - One Supply and install air- IBRD / 84960 Post Limited 20,000.00 0.00 Implementati 2020-11-22 2021-01-17 2021-07-16 Operational Systems Quotations Envelope conditions. on EG-MOSS-210972-GO-RFB / Sheets for medical beds for Support SSN Targeting and Single Stage - One the isolation hospitals to IBRD / 84960 Post Request for Bids Open - National 950,000.00 0.00 Canceled 2020-12-27 2021-01-01 2021-02-12 2021-03-14 2021-04-18 2021-10-15 Operational Systems Envelope confront the Corona pandemic. EG-MOSS-211213-GO-RFQ / Support SSN Targeting and Request for Single Stage - One Video conference system for IBRD / 84960 Post Limited 44,000.00 31,814.99 Completed 2021-01-05 2020-12-20 2021-03-02 2020-12-30 2021-08-29 2021-01-03 Operational Systems Quotations Envelope H.E. office. EG-MOSS-211220-GO-RFQ / Under UTP-Cat6 cables and power Support SSN Targeting and Request for Single Stage - One IBRD / 84960 Post Limited 40,000.00 34,034.42 Implementati 2021-01-04 2021-01-04 2021-03-01 2021-08-28 distribution units PDUs for the Operational Systems Quotations Envelope on social units Page 3 EG-MOSS-212365-GO-RFQ / Purchasing twenty laptops Support SSN Targeting and Request for Single Stage - One IBRD / 84960 Post Limited 30,000.00 16,332.91 Signed 2021-01-11 2021-01-04 2021-03-08 2021-01-18 2021-09-04 and upgrading four HP Operational Systems Quotations Envelope ProBook 450 G6 laptops. EG-MOSS-225239-GO-RFQ / As a result of the outbreak of the new Corona virus (Covid- 19), cleaning supplies, Support SSN Targeting and Request for Single Stage - One IBRD / 84960 Post Limited 100,000.00 107,747.45 Completed 2021-03-26 2021-03-24 2021-05-21 2021-04-11 2021-11-17 2021-05-09 disinfectants and masks will Operational Systems Quotations Envelope be provided to a number of 135,000 participants in the behavior change sessions. EG-MOSS-225739-GO-RFQ / Pending Audiovisual equipment for the Support SSN Targeting and Request for Single Stage - One IBRD / 84960 Post Limited 95,000.00 0.00 Implementati 2021-04-02 2021-05-28 2021-11-24 main conference room of the Operational Systems Quotations Envelope on MoSS. EG-MOSS-229514-GO-RFB / Pending Supplying a number of (3,000) Support SSN Targeting and Single Stage - One IBRD / 84960 Post Request for Bids Open - National 940,000.00 0.00 Implementati 2021-04-22 2021-04-27 2021-06-08 2021-07-08 2021-08-12 2022-02-08 Tablet computer for the social Operational Systems Envelope on unit. EG-MOSS-197481-GO-RFQ / Support SSN Targeting and Request for Single Stage - One Printing registration forms for IBRD / 84960 Post Limited 50,000.00 0.00 Canceled 2020-11-03 2020-12-29 2021-06-27 Operational Systems Quotations Envelope Takaful and Karama NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual EG-MOSS-52515-NC-DIR / MoSS Social Units SDSL land Support SSN Targeting and IBRD / 84960 Prior Direct Selection Direct 2,000,000.00 1,825,150.37 Signed 2018-03-07 2018-03-12 2018-04-16 2018-07-10 2018-10-13 lines connectivity service Operational Systems provision EG-MOSS-76934-NC-RFQ / Printing 2 million Support SSN Targeting and Request for Single Stage - One questionnaire of IBRD / 84960 Post Limited 27,500.00 27,140.36 Signed 2018-09-14 2018-09-10 2018-09-30 2018-09-18 2018-10-20 Operational Systems Quotations Envelope conditionality under Takaful component EG-MOSS-121629-NC-DIR / eFinance's design and printing Support SSN Targeting and IBRD / 84960 Prior Direct Selection Direct 800,000.00 0.00 Canceled 2019-06-30 2019-07-05 2019-08-09 2020-02-05 of 500,000 integrated Operational Systems services acquisition disability cards EG-MOSS-143574-NC-DIR / Support SSN Targeting and IBRD / 84960 Post Direct Selection Direct 2,300.00 0.00 Canceled 2019-10-30 2019-11-04 2019-12-09 2020-06-06 Office boy Operational Systems EG-MOSS-143576-NC-DIR / Support SSN Targeting and IBRD / 84960 Post Direct Selection Direct 3,000.00 0.00 Canceled 2019-10-30 2019-11-04 2019-12-09 2020-06-06 Office boy Operational Systems EG-MOSS-40100-NC-DIR / Video shooting, due to satisfactory performance of a supplier that was selected Project Management and through shopping package, IBRD / 84960 Post Direct Selection Direct 2,500.00 0.00 Canceled 2017-12-31 2018-01-05 2018-02-09 2018-08-08 Monitoring and Evaluation we want to make a short documentary about Karama's system before and after the reform we had made EG-MOSS-85355-NC-RFQ / Project Management and Request for Single Stage - One Maintenance Service for PIU's IBRD / 84960 Post Limited 2,500.00 0.00 Canceled 2018-11-16 2018-12-16 2019-11-30 Monitoring and Evaluation Quotations Envelope air conditions EG-MOSS-73859-NC-RFQ / Support SSN Targeting and Request for Single Stage - One Providing production services IBRD / 84960 Post Limited 50,000.00 0.00 Canceled 2018-08-19 2018-09-28 2019-08-01 Operational Systems Quotations Envelope for short films/movies. EG-MOSS-78329-NC-DIR / Support SSN Targeting and Providing MoSS's PIU with PRI IBRD / 84960 Post Direct Selection Direct 10,000.00 0.00 Canceled 2018-09-18 2018-09-23 2018-10-28 2019-11-30 Operational Systems service EG-MOSS-34835-NC-RFQ / Developing Video Disc (15 minutes) of the conditionality Project Management and IBRD / 84960 Post Direct Selection Direct 5,000.00 0.00 Canceled 2017-12-03 2017-12-08 2018-01-12 2018-07-11 process for insliting potential Monitoring and Evaluation beneficiaries into and out of the program EG-MOSS-225309-NC-RFQ / The non-consulting service required is having short mobile messages sent via operator networks, with Support SSN Targeting and Request for Single Stage - One associated cost for each SMS IBRD / 84960 Post Limited 100,000.00 50,495.36 Signed 2021-03-26 2021-03-01 2021-05-21 2021-04-06 2021-11-17 Operational Systems Quotations Envelope passing through operator network. No technical consultation or expertise is requested, only using operator infrastructure. CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual EG-MOSS-11508-CS-QCBS / Communication Firm Support SSN Targeting and Quality And Cost- Under (Advocacy Strategy, IBRD / 84960 Post Open - National 150,000.00 0.00 2017-12-03 2017-08-15 2017-12-24 2018-02-06 2017-11-13 2018-03-06 2018-04-05 2018-05-10 2018-06-14 2019-06-14 Operational Systems Based Selection Implementation Communication Strategy, Design Materials etc.) Page 4 EG-MOSS-24306-CS-QCBS / Awareness campaign on "Rights of People with Project Management and Quality And Cost- IBRD / 84960 Post Open - National 230,000.00 256,593.35 Signed 2017-10-01 2017-08-20 2017-10-22 2017-12-05 2017-11-10 2018-01-02 2017-12-28 2018-02-01 2018-01-28 2018-03-08 2018-02-19 2018-04-12 2018-11-04 2019-04-12 Disability" (PwD) Monitoring and Evaluation Based Selection In Social Protection and Inclusion EG-MOSS-11506-CS-QCBS / Consultant Project Management and Local Community Dialogues IBRD / 84960 Post Qualification Open - National 50,000.00 0.00 Canceled 2017-11-01 2017-11-22 2018-01-05 2018-02-02 2018-03-04 2018-04-08 2018-05-13 2019-05-13 Monitoring and Evaluation Regular Administration Selection EG-MOSS-11503-CS-QCBS / Institutional Consultancy to Support SSN Targeting and Quality And Cost- IBRD / 84960 Post Open - National 120,000.00 0.00 Canceled 2017-09-03 2017-09-24 2017-11-07 2017-12-05 2018-01-04 2018-02-08 2018-03-15 2019-03-15 conduct Airing, Operational Systems Based Selection Advertisement, Video, Radio EG-MOSS-46782-CS-QCBS / Institutional capacity building Project Management and Quality And Cost- campaign for building IBRD / 84960 Post Open - National 80,000.00 0.00 Canceled 2018-01-30 2018-02-20 2018-07-08 2018-04-05 2018-05-03 2018-06-02 2018-07-07 2018-08-11 2019-08-11 Monitoring and Evaluation Based Selection capacities on "Takaful" conditionality EG-MOSS-11509-CS-QCBS / Technical / Thematic capacity Support SSN Targeting and Quality And Cost- building (M&E, MIS, Grievance, IBRD / 84960 Post Open - National 75,000.00 0.00 Canceled 2018-01-01 2018-01-22 2018-03-07 2018-04-04 2018-05-04 2018-06-08 2018-07-13 2019-07-13 Operational Systems Based Selection Conditionality, Social responsibility, NGOs TOT, etc) EG-MOSS-165374-CS-CQS / Conducting a Rapid Market Consultant Support SSN Targeting and Assessment for the “FORSA” IBRD / 89970 Post Qualification Open - National 6,500.00 0.00 Canceled 2020-03-24 2020-03-23 2020-04-14 2020-05-28 2020-06-27 2020-08-01 2021-01-28 Operational Systems Economic Empowerment Selection Program in Egypt EG-MOSS-165280-CS-CQS / Capacity building and training for the Master Trainers, a Consultant trainer for each governorate, Support SSN Targeting and IBRD / 89970 Post Qualification Open - National 60,000.00 163,307.79 Signed 2020-03-19 2020-03-29 2020-04-09 2020-05-08 2020-05-23 2020-10-12 2020-06-20 2021-01-03 2020-07-11 2021-01-03 2020-08-15 2021-01-03 2020-09-19 2021-03-08 2021-04-22 who will accordingly train the Operational Systems Selection targeted T&K enrolled candidates in each governorate. EG-MOSS-177408-CS-CQS / Performance Audit. The objective of the performance audit of the Eligible Expenditure Program (EEP) is Consultant Support SSN Targeting and to ascertain whether IBRD / 84960 Post Qualification Open - National 40,000.00 29,439.72 Signed 2020-06-02 2020-05-03 2020-06-23 2020-08-06 2020-05-10 2020-09-05 2020-05-25 2020-10-10 2020-06-04 2021-04-08 Operational Systems payments made under the EEP Selection are reaching eligible beneficiaries and to provide advice regarding the oversight and control framework EG-MOSS-221513-CS-CQS / Providing services for the annual advertising and Consultant promotional campaign for the Support SSN Targeting and Pending IBRD / 84960 Post Qualification Open - National 100,000.00 0.00 2021-02-24 2021-03-17 2021-04-30 2021-05-30 2021-07-04 2021-12-31 mechanisms and programs of Operational Systems Implementation Selection the Ministry of Social Solidarity through various social media platforms. EG-MOSS-235383-CS-QCBS / Hiring a System Integrator firm to design, development and operationalization of an integrated MIS platform. Also, Support SSN Targeting and Quality And Cost- Under to design, build, implement IBRD / 84960 Post Open - International 700,000.00 0.00 2021-05-27 2021-05-24 2021-06-07 2021-05-25 2021-07-08 2021-08-22 2021-09-02 2021-10-07 2021-10-28 2024-08-31 Operational Systems Based Selection Implementation data sharing mechanism for its integration among the relevant systems/modules and provide end users training. INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Individual EG-MOSS-13931-CS-INDV / Project Management and IBRD / 84960 Post Consultant Limited 30,000.00 0.00 Canceled 2017-07-31 2017-08-05 2017-08-26 2017-09-30 2018-03-29 PMU Office Manager Monitoring and Evaluation Selection EG-MOSS-58973-CS-INDV / Individual Project Management and Hiring Disability Advisor (ToR IBRD / 84960 Post Consultant Limited 20,000.00 4,164.58 Signed 2018-04-12 2018-03-14 2018-04-17 2019-01-15 2018-05-08 2019-01-23 2018-06-12 2019-02-01 2018-12-09 Monitoring and Evaluation attached) Selection EG-MOSS-58991-CS-INDV / Individual Project Management and Hiring Disability Operations IBRD / 84960 Post Consultant Limited 7,000.00 7,076.35 Signed 2018-04-12 2018-03-11 2018-04-17 2018-03-21 2018-05-08 2018-03-26 2018-06-12 2018-04-10 2018-12-09 Monitoring and Evaluation Officer Selection EG-MOSS-58992-CS-INDV / Individual Project Management and Hiring Disability Capacity IBRD / 84960 Post Consultant Limited 7,500.00 7,448.79 Signed 2018-04-12 2018-03-11 2018-04-17 2018-03-28 2018-05-08 2018-04-19 2018-06-12 2018-05-02 2018-12-09 Monitoring and Evaluation Development Officer Selection Individual EG-MOSS-58993-CS-INDV / Project Management and IBRD / 84960 Post Consultant Limited 24,000.00 18,622.35 Signed 2018-04-12 2018-03-05 2018-04-17 2018-09-12 2018-05-08 2018-09-20 2018-06-12 2018-10-01 2018-12-09 Hiring M&E Specialist Monitoring and Evaluation Selection EG-MOSS-58995-CS-INDV / Individual Project Management and Hiring Monitoring IBRD / 84960 Post Consultant Limited 8,000.00 8,317.82 Signed 2018-04-12 2018-03-15 2018-04-17 2018-03-19 2018-05-08 2018-03-25 2018-06-12 2018-04-01 2018-12-09 Monitoring and Evaluation Coordinators Selection EG-MOSS-59002-CS-INDV / Individual Project Management and Hiring Radio Episodes IBRD / 84960 Post Consultant Limited 5,500.00 9,310.99 Signed 2018-04-12 2018-03-21 2018-04-17 2018-03-28 2018-05-08 2018-04-11 2018-06-12 2018-04-17 2018-12-09 Monitoring and Evaluation Composer/Producer Selection Page 5 Individual EG-MOSS-70742-CS-INDV / Project Management and IBRD / 84960 Post Consultant Limited 10,000.00 4,840.21 Signed 2018-07-24 2018-06-25 2018-07-26 2018-06-26 2018-07-27 2018-06-27 2018-07-30 2018-07-01 2019-07-30 Photographer Monitoring and Evaluation Selection EG-MOSS-70743-CS-INDV / Individual Project Management and Conditionality Capacity IBRD / 84960 Post Consultant Limited 8,000.00 10,366.23 Signed 2018-07-26 2018-06-24 2018-07-28 2018-07-26 2018-07-29 2018-07-29 2018-07-31 2018-08-01 2019-01-27 Monitoring and Evaluation Building Expert Selection EG-MOSS-76654-CS-INDV / Individual Project Management and Hiring Regulatory & IBRD / 84960 Post Consultant Limited 28,500.00 31,036.63 Signed 2018-09-02 2018-08-21 2018-09-07 2018-08-26 2018-09-12 2018-08-30 2018-09-20 2018-09-04 2019-07-17 Monitoring and Evaluation Governance Consultant Selection EG-MOSS-76655-CS-INDV / Individual Support SSN Targeting and Hiring MIS Database IBRD / 84960 Post Consultant Limited 16,000.00 0.00 Under Review 2018-09-02 2018-08-19 2018-09-07 2018-09-12 2018-09-22 2019-06-30 Operational Systems Administrator Selection Individual EG-MOSS-76656-CS-INDV / Support SSN Targeting and IBRD / 84960 Post Consultant Limited 23,000.00 6,229.37 Signed 2018-09-03 2018-08-09 2018-09-08 2018-10-01 2018-09-14 2018-10-16 2018-09-23 2018-11-01 2019-06-30 Hiring MIS Business Analyst Operational Systems Selection Individual EG-MOSS-76657-CS-INDV / Support SSN Targeting and IBRD / 84960 Post Consultant Limited 24,500.00 29,041.27 Signed 2018-09-03 2018-08-14 2018-09-08 2018-08-22 2018-09-13 2018-08-28 2018-09-19 2018-09-09 2019-06-26 Hiring MIS TA Team Leader Operational Systems Selection Individual EG-MOSS-76658-CS-INDV / Project Management and IBRD / 84960 Post Consultant Limited 17,000.00 18,265.05 Signed 2018-09-02 2018-08-09 2018-09-07 2018-08-13 2018-09-10 2018-08-23 2018-09-17 2018-09-09 2019-06-30 Hiring MIS consultant Monitoring and Evaluation Selection Individual EG-MOSS-76660-CS-INDV / Project Management and IBRD / 84960 Post Consultant Limited 11,000.00 10,621.42 Signed 2018-09-05 2018-08-13 2018-09-10 2018-08-26 2018-09-15 2018-08-29 2018-09-21 2018-09-09 2019-06-30 Hiring IT specialist Monitoring and Evaluation Selection Individual EG-MOSS-76688-CS-INDV / Support SSN Targeting and IBRD / 84960 Post Consultant Limited 7,000.00 8,687.56 Signed 2018-09-03 2018-08-16 2018-09-08 2018-08-21 2018-09-11 2018-08-26 2018-09-18 2018-09-04 2018-10-18 Hiring ESMF Consultant Operational Systems Selection EG-MOSS-76935-CS-INDV / Hiring Bulk Data Entry Individual Consultants. Multiple Support SSN Targeting and IBRD / 84960 Post Consultant Limited 28,000.00 3,099.81 Signed 2018-09-06 2018-08-15 2018-09-26 2018-08-22 2018-10-01 2018-08-27 2018-10-18 2018-09-10 2019-05-16 consultants are expected to Operational Systems Selection be hired to perform such huge task. EG-MOSS-76937-CS-INDV / Individual Support SSN Targeting and Hiring MIS Software IBRD / 84960 Post Consultant Limited 13,500.00 0.00 Canceled 2018-09-05 2018-08-20 2018-09-10 2018-09-15 2018-09-30 2019-06-30 Operational Systems Development Consultant Selection Individual EG-MOSS-81681-CS-INDV / Support SSN Targeting and IBRD / 84960 Post Consultant Limited 23,000.00 0.00 Canceled 2018-10-11 2018-10-15 2018-10-16 2018-10-19 2018-10-24 2019-10-31 Hire GIS Consultant in the PIU Operational Systems Selection EG-MOSS-85352-CS-INDV / Individual Project Management and Hiring Advisor for Community IBRD / 84960 Post Consultant Limited 23,000.00 5,795.16 Signed 2018-11-01 2018-10-08 2018-11-06 2018-10-17 2018-11-11 2018-10-24 2018-11-21 2018-11-01 2019-10-31 Monitoring and Evaluation Affairs Selection EG-MOSS-95771-CS-INDV / Individual Hiring Civil Society Project Management and IBRD / 84960 Post Consultant Limited 22,000.00 25,026.62 Signed 2019-01-22 2018-12-03 2019-01-27 2018-12-23 2019-01-29 2018-12-25 2019-02-01 2019-01-01 2019-11-30 Organizations Coordinator in Monitoring and Evaluation Selection PIU EG-MOSS-95772-CS-INDV / Individual Hiring Strategy and Capacity Project Management and IBRD / 84960 Post Consultant Limited 22,000.00 25,026.62 Signed 2019-01-22 2018-12-18 2019-01-27 2018-12-20 2019-01-29 2018-12-23 2019-02-01 2019-01-01 2019-11-30 Development Coordinator in Monitoring and Evaluation Selection PIU EG-MOSS-95773-CS-INDV / Individual Project Management and Hiring Gender Outreach IBRD / 84960 Post Consultant Limited 22,000.00 25,034.39 Signed 2019-01-22 2018-12-16 2019-01-27 2018-12-12 2019-01-29 2018-12-24 2019-02-01 2019-01-01 2019-11-30 Monitoring and Evaluation Advisor Selection EG-MOSS-95774-CS-INDV / Individual Project Management and Hiring Senior Program IBRD / 84960 Post Consultant Limited 11,000.00 11,380.08 Signed 2019-01-22 2018-12-03 2019-01-27 2018-12-13 2019-01-29 2018-12-20 2019-02-01 2019-01-01 2019-11-30 Monitoring and Evaluation Assistant in PIU Selection EG-MOSS-85353-CS-INDV / Individual Project Management and Hiring Procurement Assistant IBRD / 84960 Post Consultant Limited 11,500.00 0.00 Canceled 2018-11-08 2018-11-13 2018-11-28 2018-12-08 2019-11-30 Monitoring and Evaluation (Jr procurement specialist) Selection EG-MOSS-117748-CS-INDV Individual Project Management and / Program Legal Advisor (6 IBRD / 84960 Post Consultant Limited 8,000.00 7,446.48 Signed 2019-06-01 2019-05-30 2019-06-06 2019-05-24 2019-06-27 2019-05-27 2019-08-01 2019-06-03 2020-01-28 Monitoring and Evaluation month agreement) Selection Individual EG-MOSS-117819-CS-INDV Project Management and IBRD / 84960 Post Consultant Limited 2,500.00 1,514.50 Signed 2019-06-03 2019-05-30 2019-06-08 2019-05-02 2019-06-29 2019-05-19 2019-08-03 2019-06-03 2020-01-30 / Translator/Interpreter (1) Monitoring and Evaluation Selection Individual EG-MOSS-117825-CS-INDV Project Management and IBRD / 84960 Post Consultant Limited 2,000.00 1,364.95 Signed 2019-06-03 2019-05-02 2019-06-08 2019-05-02 2019-06-29 2019-06-23 2019-08-03 2019-06-03 2020-01-30 / Translator/Interpreter (2) Monitoring and Evaluation Selection Individual EG-MOSS-117826-CS-INDV Project Management and IBRD / 84960 Post Consultant Limited 2,000.00 934.22 Signed 2019-06-03 2019-05-02 2019-06-08 2019-05-02 2019-06-29 2019-05-20 2019-08-03 2019-06-03 2020-01-30 / Translator/Interpreter (3) Monitoring and Evaluation Selection Individual EG-MOSS-117827-CS-INDV Project Management and IBRD / 84960 Post Consultant Limited 1,500.00 1,442.53 Signed 2019-06-03 2019-05-02 2019-06-08 2019-05-02 2019-06-29 2019-05-23 2019-08-03 2019-06-03 2020-01-30 / Translator/Interpreter (4) Monitoring and Evaluation Selection Individual EG-MOSS-117828-CS-INDV Project Management and IBRD / 84960 Post Consultant Limited 2,500.00 659.47 Signed 2019-06-03 2019-05-02 2019-06-08 2019-05-02 2019-06-29 2019-05-21 2019-08-03 2019-06-03 2020-01-30 / Translator/Interpreter (5) Monitoring and Evaluation Selection Individual EG-MOSS-117830-CS-INDV Project Management and IBRD / 84960 Post Consultant Limited 2,000.00 351.72 Signed 2019-06-03 2019-05-02 2019-06-08 2019-05-02 2019-06-29 2019-05-23 2019-08-03 2019-06-03 2020-01-30 / Translator/Interpreter (6) Monitoring and Evaluation Selection Page 6 Individual EG-MOSS-119697-CS-INDV Project Management and IBRD / 84960 Post Consultant Limited 16,000.00 6,884.14 Signed 2019-06-19 2019-06-23 2019-06-24 2019-06-02 2019-07-15 2019-06-18 2019-08-19 2019-07-01 2020-02-15 / Call Center Specialist Monitoring and Evaluation Selection Individual EG-MOSS-70741-CS-INDV / Project Management and IBRD / 84960 Post Consultant Limited 12,000.00 11,421.48 Signed 2018-07-24 2018-07-24 2018-07-26 2018-07-26 2018-07-27 2018-07-29 2018-07-31 2018-08-01 2019-07-31 Senior Multimedia Specialist Monitoring and Evaluation Selection Individual EG-MOSS-128015-CS-INDV Project Management and IBRD / 84960 Post Consultant Limited 10,000.00 0.00 Canceled 2019-08-19 2019-08-19 2019-08-24 2019-09-14 2019-10-19 2020-04-16 / Call Center Specialist Monitoring and Evaluation Selection Individual EG-MOSS-135023-CS-CQS / Support SSN Targeting and IBRD / 84960 Post Consultant Limited 10,000.00 10,276.20 Signed 2019-09-23 2019-07-15 2019-09-28 2019-07-11 2019-10-19 2019-07-16 2019-11-23 2019-07-22 2020-05-21 Disability Advisor Operational Systems Selection Individual EG-MOSS-141172-CS-INDV Support SSN Targeting and IBRD / 84960 Post Consultant Limited 1,000.00 5,797.64 Signed 2019-10-01 2019-10-01 2019-10-06 2019-09-15 2019-10-27 2019-09-22 2019-12-01 2019-10-01 2020-05-29 / Administrative Assistant Operational Systems Selection Individual EG-MOSS-141576-CS-INDV Support SSN Targeting and IBRD / 84960 Post Consultant Limited 5,000.00 24,821.60 Signed 2019-09-15 2019-09-15 2019-09-20 2019-09-17 2019-10-11 2019-09-19 2019-11-15 2019-10-01 2020-05-13 / Disability Officer Operational Systems Selection EG-MOSS-141559-CS-INDV Individual / The Consultant shall Support SSN Targeting and IBRD / 84960 Post Consultant Limited 3,400.00 3,447.41 Signed 2019-09-15 2019-08-08 2019-09-20 2019-08-15 2019-10-11 2019-08-28 2019-11-15 2019-09-15 2020-05-13 perform the Services as Social Operational Systems Selection Protection Officer. Individual EG-MOSS-141185-CS-INDV Support SSN Targeting and IBRD / 84960 Post Consultant Limited 15,000.00 14,089.14 Signed 2019-10-01 2019-10-01 2019-10-06 2019-10-03 2019-10-27 2019-10-06 2019-12-01 2019-10-15 2020-05-29 / Monitoring Coordinator Operational Systems Selection Individual EG-MOSS-143552-CS-INDV Support SSN Targeting and IBRD / 84960 Post Consultant Limited 2,700.00 2,325.73 Signed 2019-10-30 2019-09-12 2019-11-04 2019-09-17 2019-11-25 2019-09-22 2019-12-30 2019-10-01 2020-06-27 / Administrative Assistant Operational Systems Selection Individual EG-MOSS-143561-CS-INDV Support SSN Targeting and IBRD / 84960 Post Consultant Limited 5,000.00 4,153.43 Signed 2019-10-30 2019-09-10 2019-11-04 2019-09-17 2019-11-25 2019-09-24 2019-12-30 2019-10-01 2020-06-27 / Administrative Assistant Operational Systems Selection Individual EG-MOSS-143566-CS-INDV Support SSN Targeting and IBRD / 84960 Post Consultant Limited 5,000.00 4,580.45 Signed 2019-10-30 2019-10-30 2019-11-04 2019-10-22 2019-11-25 2019-10-27 2019-12-30 2019-11-01 2020-06-27 / Administrative Assistant Operational Systems Selection Individual EG-MOSS-143579-CS-INDV Support SSN Targeting and Pending IBRD / 84960 Post Consultant Limited 30,000.00 0.00 2019-11-25 2019-12-25 / Field Operation Manager Operational Systems Implementation Selection Individual EG-MOSS-143589-CS-INDV Support SSN Targeting and IBRD / 84960 Post Consultant Limited 34,000.00 30,813.99 Signed 2019-10-30 2019-10-15 2019-11-04 2019-10-17 2019-11-25 2019-10-22 2019-12-30 2019-11-01 2020-06-27 / GIS Consultant Operational Systems Selection Individual EG-MOSS-143591-CS-INDV Support SSN Targeting and IBRD / 84960 Post Consultant Limited 30,000.00 29,981.26 Signed 2019-10-30 2019-10-15 2019-11-04 2019-10-01 2019-11-25 2019-10-27 2019-12-30 2019-11-01 2020-06-27 / Senior researcher Operational Systems Selection EG-MOSS-147248-CS-INDV Individual Support SSN Targeting and / Monitoring & Evaluation and IBRD / 84960 Post Consultant Limited 40,000.00 42,221.15 Signed 2019-11-26 2019-11-25 2019-12-01 2019-11-24 2019-12-22 2019-12-01 2020-01-26 2019-12-15 2020-07-24 Operational Systems Research Advisor Selection EG-MOSS-147260-CS-INDV Individual Support SSN Targeting and / Health Conditionality IBRD / 84960 Post Consultant Limited 40,000.00 25,332.99 Signed 2019-11-26 2019-11-25 2019-12-01 2019-12-01 2019-12-22 2019-12-08 2020-01-26 2019-12-15 2020-07-24 Operational Systems Advisor Selection EG-MOSS-118096-CS-CDS / Provision of integrated social Project Management and protection services to enhance IBRD / 84960 Post Direct Selection Direct 200,000.00 0.00 Canceled 2019-06-04 2019-06-04 2019-06-14 2019-08-18 2020-02-14 Monitoring and Evaluation "Takaful and Karama" program among local communities EG-MOSS-151080-CS-INDV Individual Support SSN Targeting and / Education Conditionality IBRD / 84960 Post Consultant Limited 23,000.00 22,486.65 Signed 2019-12-18 2019-11-28 2019-12-23 2019-12-01 2020-01-13 2019-12-12 2020-02-17 2019-12-19 2020-08-15 Operational Systems Advisor Selection EG-MOSS-169705-CS-INDV Individual Support SSN Targeting and / Self-Employment and IBRD / 84960 Post Consultant Limited 42,000.00 42,116.23 Signed 2020-04-21 2020-05-01 2020-04-26 2020-04-19 2020-05-17 2020-04-26 2020-06-21 2020-05-01 2020-12-18 Operational Systems Livelihoods Manager Selection EG-MOSS-190238-CS-CDS / The objective of the financial audit service is to enable the auditor to express a single professional opinion on the Support SSN Targeting and IBRD / 84960 Post Direct Selection Direct 55,000.00 55,946.72 Signed 2020-08-25 2020-08-23 2020-09-04 2020-09-01 2020-11-08 2020-09-15 2021-05-07 financial position of the Operational Systems project at the end of each fiscal year, and on funds received and expenditures for a relevant accounting period Individual EG-MOSS-193761-CS-CQS / Support SSN Targeting and IBRD / 89970 Post Consultant Limited 15,000.00 13,775.51 Signed 2020-09-24 2020-09-21 2020-09-29 2020-11-10 2020-10-20 2020-11-15 2020-11-24 2020-11-25 2021-05-23 Program officer. Operational Systems Selection EG-MOSS-193762-CS-CQS / Individual Support SSN Targeting and Monitoring, Evaluation and IBRD / 89970 Post Consultant Limited 27,000.00 11,483.25 Signed 2020-09-24 2020-09-21 2020-09-29 2020-10-14 2020-10-20 2020-10-19 2020-11-24 2020-11-01 2021-05-23 Operational Systems Data Management Specialist. Selection Individual EG-MOSS-193766-CS-CQS / Support SSN Targeting and Under IBRD / 89970 Post Consultant Limited 12,000.00 0.00 2020-09-24 2020-09-21 2020-09-29 2020-10-20 2020-11-24 2021-05-23 Governorate Field Coordinator Operational Systems Implementation Selection Individual EG-MOSS-194034-CS-CQS / Support SSN Targeting and IBRD / 89970 Post Consultant Limited 27,000.00 22,959.18 Signed 2020-09-24 2020-09-21 2020-09-29 2020-10-14 2020-10-20 2020-10-18 2020-11-24 2020-11-01 2021-05-23 Senior employment officer. Operational Systems Selection Page 7 EG-MOSS-194311-CS-CQS / Individual Support SSN Targeting and Self-Employment and IBRD / 89970 Post Consultant Limited 27,000.00 26,768.64 Signed 2020-09-24 2020-09-21 2020-09-29 2020-12-15 2020-10-20 2020-12-20 2020-11-24 2021-01-01 2021-05-23 Operational Systems Livelihoods Senior Officer. Selection Individual EG-MOSS-194319-CS-CQS / Support SSN Targeting and IBRD / 89970 Post Consultant Limited 15,000.00 13,014.35 Signed 2020-09-24 2020-09-21 2020-09-29 2020-09-30 2020-10-20 2020-10-07 2020-11-24 2020-10-20 2021-05-23 Agribusiness officer. Operational Systems Selection Individual EG-MOSS-194329-CS-CQS / Support SSN Targeting and Under IBRD / 89970 Post Consultant Limited 38,000.00 0.00 2020-09-24 2020-09-21 2020-09-29 2020-10-20 2020-11-24 2021-05-23 wage employment manager. Operational Systems Implementation Selection Individual EG-MOSS-194348-CS-CQS / Support SSN Targeting and IBRD / 89970 Post Consultant Limited 23,000.00 20,676.45 Signed 2020-09-24 2020-09-21 2020-09-29 2020-09-28 2020-10-20 2020-10-01 2020-11-24 2020-10-15 2021-05-23 FORSA coordinator. Operational Systems Selection Individual EG-MOSS-194417-CS-CQS / Support SSN Targeting and Under IBRD / 89970 Post Consultant Limited 19,000.00 0.00 2020-09-24 2020-09-21 2020-09-29 2020-10-20 2020-11-24 2021-05-23 advocacy coordinator. Operational Systems Implementation Selection Individual EG-MOSS-215456-CS-CQS / Support SSN Targeting and IBRD / 84960 Post Consultant Limited 8,000.00 6,130.27 Signed 2021-01-25 2021-01-05 2021-01-30 2021-01-20 2021-02-20 2021-01-25 2021-03-27 2021-02-03 2021-09-23 M&E assistant Operational Systems Selection EG-MOSS-225235-CS-INDV / Financial manager that will prepare and extract regular Individual Support SSN Targeting and Under financial reports to assist IBRD / 84960 Post Consultant Limited 27,000.00 0.00 2021-03-17 2021-02-09 2021-03-22 2021-04-12 2021-05-17 2021-11-13 Operational Systems Implementation FORSA Program Director in Selection making decisions that affect the program. EG-MOSS-235090-CS-INDV / M & E Senior Advisor for 10 Individual Support SSN Targeting and Under days to provide technical IBRD / 84960 Post Consultant Limited 1,000.00 0.00 2021-05-23 2021-05-16 2021-05-28 2021-06-18 2021-07-23 2022-01-19 Operational Systems Implementation assistance to the FORSA Selection program. EG-MOSS-235353-CS-INDV Individual Support SSN Targeting and Under / Agribusiness & livestock IBRD / 84960 Post Consultant Limited 4,000.00 0.00 2021-05-23 2021-05-16 2021-05-28 2021-06-18 2021-07-23 2022-01-19 Operational Systems Implementation advisor. Selection Page 8 PROCUREMENT PLAN (Textual Part) Project information: West Bank and Gaza, PFM Improvement, P-162850 Project Implementation agency: MINISTRY OF FINANCE AND PLANNING Date of the Procurement Plan: 10 July 2018 Period covered by this Procurement Plan: First 18 months Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). “Not Applicable” PROCUREMENT West Bank and Gaza : Public Financial Management Improvement Project PLAN General Information Country: West Bank and Gaza Bank’s Approval Date of the Original Procurement Plan: 2018-07-11 2021-05-25 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P162850 GPN Date: 2018-07-17 Project Name: Public Financial Management Improvement Project Loan / Credit No: TF / A6949, / P Executing Agency(ies): alestinian Authority-Ministry of Finance and Planning WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 4: Project GZ-MOFP-114614-GO-RFQ / Request for Single Stage - One TF / A6949 Implementation Support and Post Limited 90,000.00 78,364.00 Completed 2019-10-29 2019-11-25 2019-12-24 2020-01-09 2020-06-21 2020-02-13 PMU and MOFP Equipment Quotations Envelope Management Costs GZ-MOFP-177544-GO-RFQ / Component 2: Improving Request for Single Stage - One Equipment for the benefit of TF / A6949 Financial Accountability of Post Limited 90,000.00 59,658.00 Completed 2020-06-12 2020-06-15 2020-08-07 2020-08-09 2020-10-06 2020-09-22 Quotations Envelope SAACB. the PFM System Component 1: Improving GZ-MOFP-198841-GO-RFQ / Request for Single Stage - One TF / A6949 Budget Expenditure Post Limited 35,000.00 35,484.00 Signed 2020-11-13 2020-11-08 2021-01-08 2020-12-20 2021-03-09 Office and IT Equipment Quotations Envelope Management and Control GZ-MOFP-213643-GO-RFQ / Component 2: Improving Pending Request for Single Stage - One Office equipment/software for TF / A6949 Financial Accountability of Post Limited 58,000.00 0.00 Implementati 2021-04-04 2021-05-30 2021-08-08 Quotations Envelope the benefit of SAACB the PFM System on NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GZ-MOFP-88245-CS-QCBS / Component 4: Project Quality And Cost- Hiring an external auditor to TF / A6949 Implementation Support and Post Open - National 15,000.00 6,612.00 Signed 2018-11-26 2018-11-26 2018-11-26 2018-11-26 2018-11-26 2019-01-06 2019-01-06 2019-01-16 2019-01-06 2019-01-24 2019-01-06 2019-02-21 2019-04-15 2021-06-15 Based Selection audit the PFMI project Management Costs GZ-MOFP-114617-CS-QCBS Component 1: Improving Consultant / Modernize the Functions of TF / A6949 Budget Expenditure Post Qualification Limited 50,000.00 88,879.20 Signed 2019-08-08 2019-08-21 2019-08-22 2019-09-08 2019-09-21 2019-10-16 2019-10-26 2019-12-26 2020-04-23 Financial Controller Management and Control Selection GZ-MOFP-158890-CS-QCBS / Consultantancy firm to work Component 1: Improving on the Israeli deduction from Quality And Cost- TF / A6949 Budget Expenditure Post Open - National 130,000.00 0.00 Canceled 2020-02-16 2020-02-16 2020-03-08 2020-04-21 2020-05-19 2020-06-18 2020-07-23 2020-08-27 2021-08-27 Clearance Revenues Based Selection Management and Control transferred to the Palestinian Government. Component 1: Improving GZ-MOFP-215235-CS-QCBS Quality And Cost- TF / A6949 Budget Expenditure Post Open - National 55,000.00 0.00 Canceled 2021-02-28 2021-04-01 2021-03-21 2021-05-04 2021-06-01 2021-07-01 2021-08-05 2021-09-09 2022-09-09 / Recruiting an IT Audit Firm Based Selection Management and Control GZ-MOFP-239377-CS-CQS / Component 1: Improving Consultant Advisory Support for the Audit TF / A6949 Budget Expenditure Post Qualification Limited 80,000.00 0.00 Under Review 2021-06-20 2021-05-20 2021-07-04 2021-08-03 2021-09-07 2022-03-06 of BISAN System (FMIS) at Management and Control Selection Ministry of Finance INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GZ-MOFP-68910-CS-INDV / Component 4: Project Individual PMU Financial Management TF / A6949 Implementation Support and Post Consultant Direct 33,600.00 33,600.00 Completed 2018-07-10 2018-07-12 2018-07-10 2018-06-07 2018-07-10 2018-06-10 2018-07-10 2018-07-01 2019-07-09 2019-06-30 Specialist Management Costs Selection Component 4: Project Individual GZ-MOFP-68920-CS-INDV / TF / A6949 Implementation Support and Post Consultant Open 48,000.00 4,000.00 Completed 2018-07-10 2018-07-12 2018-08-13 2018-09-17 2018-08-18 2018-12-20 2018-09-01 2019-02-03 2019-08-31 2020-02-02 PMU Manager Management Costs Selection Component 4: Project Individual GZ-MOFP-68927-CS-INDV / TF / A6949 Implementation Support and Post Consultant Open 33,600.00 34,800.00 Completed 2018-07-10 2018-07-12 2018-08-13 2018-09-17 2018-08-18 2018-09-30 2018-09-01 2018-11-01 2019-08-31 2019-10-31 PMU Procurement Specialist Management Costs Selection GZ-MOFP-111771-CS-CDS / Component 2: Improving Individual Financial Expert to Reduce the TF / A6949 Financial Accountability of Post Consultant Direct 64,000.00 64,000.00 Completed 2019-04-29 2019-04-29 2019-04-29 2019-04-29 2019-04-29 2019-04-29 2019-05-01 2019-05-01 2019-12-31 2019-12-31 Backlog of Financial the PFM System Selection Statements of the PA Page 1 GZ-MOFP-69928-CS-CDS / Component 1: Improving Business process analyst for TF / A6949 Budget Expenditure Post Direct Selection Direct 40,005.00 40,020.00 Completed 2018-07-17 2018-07-17 2018-07-22 2018-11-04 2018-08-10 2018-11-11 2018-12-10 2019-04-11 payroll system Management and Control GZ-MOFP-114611-CS-INDV Component 4: Project Individual / Financial Management TF / A6949 Implementation Support and Post Consultant Direct 35,280.00 35,280.00 Completed 2019-05-30 2019-05-23 2019-06-09 2019-05-30 2019-06-14 2019-05-30 2019-07-01 2019-07-01 2020-06-30 2020-06-30 Specialist Management Costs Selection GZ-MOFP-114615-CS-CDS / Component 1: Improving Introducing changes to Bisan Pending TF / A6949 Budget Expenditure Post Direct Selection Direct 30,000.00 0.00 2019-08-11 2019-08-21 2019-10-25 2020-04-22 system- Commitment Control Implementation Management and Control Module and training of users. GZ-MOFP-114612-CS-INDV / Accountant # 1 to support the Accountant General and Component 2: Improving Individual General Accounts Department TF / A6949 Financial Accountability of Post Consultant Open 12,000.00 10,800.00 Completed 2019-08-18 2019-08-25 2019-10-06 2019-11-03 2019-10-27 2019-11-10 2019-12-01 2019-12-03 2020-11-30 2021-01-04 (full-time) (first year) the PFM System Selection budgeted around $1,000 each per month. GZ-MOFP-126227-CS-INDV / Accountant # 2 to support the Accountant General and Component 2: Improving Individual General Accounts Department TF / A6949 Financial Accountability of Post Consultant Open 12,000.00 10,800.00 Completed 2019-08-18 2019-08-25 2019-10-06 2019-11-03 2019-10-27 2019-11-10 2019-12-01 2019-12-03 2020-11-30 2021-01-04 (full-time) (first year) the PFM System Selection budgeted around $1,000 each per month GZ-MOFP-126228-CS-INDV / Accountant # 3 to support the Accountant General and Component 2: Improving Individual General Accounts Department TF / A6949 Financial Accountability of Post Consultant Open 12,000.00 10,800.00 Completed 2019-08-18 2019-08-25 2019-10-06 2019-11-03 2019-10-27 2019-11-10 2019-12-01 2019-12-03 2020-11-30 2021-01-04 (full-time) (first year) the PFM System Selection budgeted around $1,000 each per month Component 4: Project Individual GZ-MOFP-141041-CS-INDV TF / A6949 Implementation Support and Post Consultant Direct 39,600.00 38,280.00 Completed 2019-10-17 2019-10-17 2019-10-17 2019-10-20 2019-10-17 2019-10-20 2019-11-01 2019-11-01 2020-10-31 2020-10-31 / PMU Procurement Specialist Management Costs Selection Component 1: Improving Individual GZ-MOFP-68932-CS-INDV / / Budget Expenditure Post Consultant Open 48,000.00 0.00 Canceled 2018-07-10 2018-07-12 2018-08-28 2018-09-18 2019-01-01 2019-12-31 PFM Advisor Management and Control Selection GZ-MOFP-139966-CS-CDS / IPSAS Expert (Mirabo Component 2: Improving Individual Shammas) for the adoption of TF / A6949 Financial Accountability of Post Consultant Direct 30,000.00 29,881.60 Signed 2019-11-25 2019-12-09 2019-12-05 2019-11-18 2019-12-14 2019-12-15 2020-01-06 2019-12-15 2021-01-04 International Public Sector the PFM System Selection Accounting Standards GZ-MOFP-146530-CS-INDV Component 2: Improving Individual / Financial Expert to Reduce TF / A6949 Financial Accountability of Post Consultant Direct 48,000.00 48,000.00 Completed 2019-11-28 2019-12-09 2019-12-08 2019-12-10 2019-12-29 2019-12-10 2020-02-02 2020-01-01 2020-09-30 2020-08-31 the Backlog of Financial the PFM System Selection Statements of the PA. GZ-MOFP-149443-CS-INDV / Majed Ayyad "IT Expert for Component 1: Improving Individual the supervision and TF / A6949 Budget Expenditure Post Consultant Direct 48,000.00 48,000.00 Signed 2019-12-09 2020-03-12 2019-12-19 2020-06-09 2019-12-20 2020-06-09 2019-12-23 2020-06-29 2022-06-30 implementation of the Payroll Management and Control Selection System" GZ-MOFP-153081-CS-INDV Component 4: Project Individual / PMU Project Manager- TF / A6949 Implementation Support and Post Consultant Direct 50,400.00 50,400.00 Signed 2020-01-15 2020-01-16 2020-01-25 2020-01-02 2020-01-26 2020-01-02 2020-02-03 2020-02-03 2021-02-02 Renewal Management Costs Selection Component 2: Improving Individual GZ-MOFP-153084-CS-INDV TF / A6949 Financial Accountability of Post Consultant Direct 18,000.00 19,200.00 Completed 2020-01-16 2020-02-16 2020-01-26 2020-03-09 2020-02-16 2020-03-09 2020-03-22 2020-04-01 2021-03-21 2021-03-31 / Auditor # 1 for SAACB the PFM System Selection Component 2: Improving Individual GZ-MOFP-153089-CS-INDV TF / A6949 Financial Accountability of Post Consultant Limited 18,000.00 17,400.00 Completed 2020-01-16 2020-02-16 2020-01-21 2020-03-09 2020-02-11 2020-03-09 2020-03-17 2020-04-01 2021-03-16 2021-03-31 / Auditor # 2 for SAACB the PFM System Selection Component 2: Improving Individual GZ-MOFP-153091-CS-INDV TF / A6949 Financial Accountability of Post Consultant Limited 18,000.00 17,400.00 Completed 2020-01-16 2020-02-16 2020-01-21 2020-03-09 2020-02-11 2020-03-17 2020-04-01 2021-03-16 2021-03-31 / Auditor # 3 for SAACB the PFM System Selection GZ-MOFP-173517-CS-INDV Component 4: Project Individual / Financial Management TF / A6949 Implementation Support and Post Consultant Direct 35,280.00 35,280.00 Signed 2020-05-29 2020-05-17 2020-06-08 2020-05-19 2020-06-13 2020-05-19 2020-06-30 2020-07-01 2021-06-30 Specialist Management Costs Selection Component 2: Improving Individual GZ-MOFP-182809-CS-INDV TF / A6949 Financial Accountability of Post Consultant Direct 48,000.00 48,000.00 Signed 2020-07-16 2020-07-16 2020-07-26 2020-07-21 2020-08-16 2020-07-21 2020-09-01 2020-09-01 2021-04-30 / Financial Expert the PFM System Selection GZ-MOFP-123226-CS-INDV / Individual Consultant to Component 1: Improving Individual work on the Israeli Deductions TF / A6949 Budget Expenditure Post Consultant Limited 20,000.00 0.00 Canceled 2019-07-31 2019-12-01 2019-08-05 2019-08-26 2019-09-30 2019-12-31 from Clearance Revenues Management and Control Selection transferred to the Palestinian Government GZ-MOFP-195439-CS-INDV Component 2: Improving Individual / Accountant # 4 to work on TF / A6949 Financial Accountability of Post Consultant Limited 12,000.00 10,800.00 Signed 2020-09-30 2020-09-17 2020-10-05 2020-10-07 2020-10-26 2020-10-07 2020-11-30 2020-12-01 2021-05-29 Net Lending the PFM System Selection GZ-MOFP-195441-CS-INDV Component 2: Improving Individual / Accountant # 5 to work on TF / A6949 Financial Accountability of Post Consultant Limited 12,000.00 10,800.00 Signed 2020-09-30 2020-09-17 2020-10-05 2020-10-07 2020-10-26 2020-10-07 2020-11-30 2020-12-01 2021-05-29 Net Lending the PFM System Selection GZ-MOFP-195299-CS-INDV Component 4: Project Individual / Procurement and Grants TF / A6949 Implementation Support and Post Consultant Direct 46,800.00 46,800.00 Signed 2020-09-30 2020-09-01 2020-09-30 2020-09-01 2020-09-30 2020-09-01 2020-11-01 2020-10-06 2021-10-31 Specialist Management Costs Selection GZ-MOFP-198031-CS-INDV / Contract Renewal for Component 2: Improving Individual Accountant # 1 to support the TF / A6949 Financial Accountability of Post Consultant Direct 12,000.00 10,800.00 Signed 2020-11-30 2020-10-19 2020-12-05 2020-11-01 2020-12-16 2020-11-01 2021-01-05 2020-12-08 2022-01-04 Accountant General and the PFM System Selection General Accounts Department Page 2 GZ-MOFP-198032-CS-INDV / Contract Renewal for Component 2: Improving Individual Accountant # 2 to support the TF / A6949 Financial Accountability of Post Consultant Direct 12,000.00 10,800.00 Signed 2020-11-30 2020-10-19 2020-12-05 2020-11-01 2020-12-16 2020-11-01 2021-01-05 2020-12-08 2022-01-04 Accountant General and the PFM System Selection General Accounts Department GZ-MOFP-198034-CS-INDV / Contract Renewal for Component 2: Improving Individual Accountant # 3 to support the TF / A6949 Financial Accountability of Post Consultant Direct 12,000.00 10,800.00 Signed 2020-11-30 2020-10-19 2020-12-05 2020-11-01 2020-12-16 2020-11-01 2021-01-05 2020-12-08 2022-01-04 Accountant General and the PFM System Selection General Accounts Department GZ-MOFP-208240-CS-INDV Component 4: Project Individual / PMU Project Manager - TF / A6949 Implementation Support and Post Consultant Direct 50,400.00 50,400.00 Signed 2020-12-17 2020-12-10 2020-12-27 2020-12-10 2020-12-28 2020-12-15 2021-02-03 2021-02-03 2022-02-02 Contract renewal. Management Costs Selection Component 2: Improving Individual GZ-MOFP-211945-CS-INDV TF / A6949 Financial Accountability of Post Consultant Direct 48,000.00 48,000.00 Signed 2021-02-28 2021-02-25 2021-03-10 2021-04-13 2021-03-31 2021-04-29 2021-05-01 2021-04-29 2021-12-31 / Financial Expert the PFM System Selection GZ-MOFP-211946-CS-INDV Component 2: Improving Individual / Contract Renewal of Auditor TF / A6949 Financial Accountability of Post Consultant Direct 19,200.00 19,200.00 Signed 2021-01-31 2021-01-11 2021-02-10 2021-01-18 2021-03-03 2021-01-18 2021-04-01 2021-04-01 2022-03-31 # 1 for the benefit of SAACB the PFM System Selection GZ-MOFP-211947-CS-INDV Component 2: Improving Individual / Contract renewal Auditor # TF / A6949 Financial Accountability of Post Consultant Direct 17,400.00 17,400.00 Signed 2021-01-31 2021-01-11 2021-02-10 2021-01-18 2021-03-03 2021-01-18 2021-04-01 2021-04-01 2022-03-31 2 for SAACB the PFM System Selection GZ-MOFP-211950-CS-INDV Component 2: Improving Individual / Contract Renewal for TF / A6949 Financial Accountability of Post Consultant Direct 17,400.00 17,400.00 Signed 2021-01-31 2021-01-11 2021-02-10 2021-01-18 2021-03-03 2021-01-18 2021-04-01 2021-04-01 2021-09-28 Auditor # 3 SAACB the PFM System Selection Component 1: Improving GZ-MOFP-211920-CS-CDS / Pending TF / A6949 Budget Expenditure Post Direct Selection Direct 136,000.00 0.00 2020-12-31 2021-01-31 2021-03-23 2021-12-31 Bisan Service Agreement Implementation Management and Control GZ-MOFP-214311-CS-CDS / Component 4: Project Under Hiring an external auditor for TF / A6949 Implementation Support and Post Direct Selection Direct 6,600.00 0.00 2021-01-31 2021-01-26 2021-02-10 2021-04-16 2022-12-31 Implementation the Project Management Costs GZ-MOFP-214317-CS-INDV Component 2: Improving Individual Under / IT Consultant for the benefit TF / A6949 Financial Accountability of Post Consultant Limited 24,000.00 0.00 2021-02-07 2021-01-28 2021-02-26 2021-04-05 2021-03-19 2021-04-27 2021-04-23 2022-04-22 Implementation of SAACB the PFM System Selection Component 1: Improving Individual GZ-MOFP-214323-CS-INDV Under TF / A6949 Budget Expenditure Post Consultant Open 18,000.00 0.00 2021-01-31 2021-01-27 2021-03-21 2021-04-11 2021-05-16 2022-05-15 / IT Expert-Part Time Implementation Management and Control Selection Component 1: Improving Individual GZ-MOFP-214327-CS-INDV Under TF / A6949 Budget Expenditure Post Consultant Open 36,000.00 0.00 2021-01-31 2021-01-27 2021-03-21 2021-04-11 2021-05-16 2022-05-15 / Resident Senior Accountant Implementation Management and Control Selection GZ-MOFP-226305-CS-INDV Component 4: Project Individual / PMU-Financial Management TF / A6949 Implementation Support and Post Consultant Direct 37,044.00 37,044.00 Signed 2021-04-29 2021-04-11 2021-05-09 2021-04-14 2021-05-14 2021-04-14 2021-05-17 2021-05-03 2022-06-30 Specialist-Contract Renewal Management Costs Selection GZ-MOFP-235900-CS-INDV Component 2: Improving Individual / Replacement Accountant # 1 Under TF / A6949 Financial Accountability of Post Consultant Direct 10,800.00 0.00 2021-06-03 2021-05-25 2021-06-06 2021-06-10 2021-06-11 2021-06-10 2021-07-01 2022-06-30 to Support the general Implementation the PFM System Selection accounts department. GZ-MOFP-235906-CS-INDV / Hire an individual consultant to develop Financial and Component 1: Improving Individual Under Institutional/administrative TF / A6949 Budget Expenditure Post Consultant Limited 30,000.00 0.00 2021-07-06 2021-05-25 2021-07-11 2021-08-01 2021-09-05 2022-03-04 Implementation framework for the net lending Management and Control Selection department established at the MoF Page 3 LIBERIA AGENCY for COMMUNITY EMPOWERMENT Abbreviated Procurement Plan Attachment I – Procurement Plan I. General 1. Project Information: Country: Liberia Project Name: Youth Opportunities Project Project ID No.: P146827 Credit Number: 5621 - LR Executing Agencies: Liberia Agency for Community Empowerment 2. Bank’s approval Date of the procurement Plan: June March16 11, 20157 3. Date of General Procurement Notice: December 20, 2016 4. Period covered by this procurement plan: March 12, 2015 to August 10, 2016June 2017 to May 31, 2018 II. Goods, Supply & Installation of Plant & Equipment, Works & non- Consulting Services. 5. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: World Bank’s Guidelines: Procurement of Goods, Works, and Non-Consulting Services under IBRD Loans and IDA Credits & Grants (January 2011 edition) and revised in July 2014, and is open to all eligible bidders as defined in the guidelines. Consulting services will be selected in accordance with the World Bank’s Guidelines: Selection and Employment of Consultants under IBRD Loans and IDA Credits & Grants by World Bank Borrowers (January 2011 edition) and revised July, 2014 and Guidelines on Preventing and Combating Fraud and Corruption in Projects Financed by IBRD Loans and IDA Credits and Grants, dated October 15, 2006, and revised in January 2011. Table 1: Thresholds for Procurement Methods and Prior Review – Goods and Works and Non Consultant Services Expenditure Procurement Contract Value Threshold Contracts Subject to Category Method For use of Method (US$) Prior Review (US$) 1. Works ICB(Works/Supply & >=5,000,000 All contracts Installation) NCB >=200,000 - <5,000,000 As in procurement plan Shopping <200,000 None Direct Contracting All values All contracts 2. Goods and ICB >=500,000 All contracts Non NCB >=100,000 <500,000 As in procurement plan Consultant Shopping <500,000 (motor vehicles None Services only) Shopping <100,000 000 (rest not None motor vehicles) Direct Contracting All values All contracts Procurement from All values None UNOPS Agency 6. Prequalification. Not expected for the works/goods packages. 7. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: N/A 8. Reference to (if any) Project Operational/Procurement Manual: Yes 9. Any Other Special Procurement Arrangements: None 10. Procurement Packages with Methods and Time Schedule a) Works b) Procurement of Goods and Non Consulting Services 1 2 3 4 5 6 7 8 9 Ref. Contract Estim Procure Prequa Nation Revie Expecte Expect Comme No. (Description) ated ment lificatio al w d bid ed nts Cost Method n Prefer by opening Contra US$ (yes/no ence Bank date ct millio ) (yes/n (Prior Signat n o) / ure Post) Date Goods 1. Procurement of 88,000 Shopping No No Post 12/01/17 12/21/1 .00 7 off road Vehicles (Station wagons) 2 No. 2. Agro Inputs 187,82 Shopping No No Post 11/09/17 11/14/1 4.00 7 (Tools & Planting Materials) (To be procured per county) 3. Motorbikes(14) 53,200 Shopping No No Post 07/24/17 08/15/1 .00 7 for County Coordinators movements in the fifteen counties 4. Supply of 25.200 Shopping No No Post 07/03/17 07/14/1 .00 7 computers (21 laptops and 1 desk top), duplex printer (1) 5. Supply of (6) Air 3,000. Shopping No No Post 07/03/01 07/14/1 00 7 7 conditioners - (2) 12000 btus and (6) 9000 btus; 1 refrigerator and 1 water dispenser. 6. Supply of 6,600. Shopping No No Post 07/03/17 07/14/1 00 7 assorted stationery supplies including cartridges 7. Supply of office 8,500. Shopping No No Post 07/03/17 07/14/1 00 7 furniture (6 wooden desks- 1 executive and 5 L-shape desks; 27 chairs - 6 executive chairs, 10 conference table chairs, and 10 visitors chairs; ) (15 sets window blinders), two doors and (7) cabinets - 1 transparent and 6 ordinary) 8. Supply of office 2,100. Shopping No No Post 07/03/17 07/14/1 00 7 consumables - tea, milk, tissues, sugar, deltol, detergents, air freshner, hand sensitizer, etc. Total 374,4 24 III. Selection of Consultants 11. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Table 2: Thresholds for Consultants Selection Methods and Prior Review Contract Value Threshold Expenditure Contracts Subject to Selection Method For use of Selection Category Prior Review (US$) Method (US$) Firms QCBS,QBS >=200,000 All contracts CQS,LCS,QBS,FBS <200,000 As in procurement plan SSS All values All Contracts Individual Competitive All Contracts >=100,000 Consultants Selection (IC) IC Single Source All Contracts All Values Selection 12. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than US$100,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 13. Consultancy services estimated to cost above US$200,000 equivalent per contract and individual consultants assignments estimated to cost US$100,000 and above and all individual consultants hired on single source basis will be subject to prior review by the Bank. 14. The threshold for the use of Selection of Consultant firms based on Consultants’ Qualifications (CQS) is determined on a case by case basis taking into account the nature and complexity of the assignment but shall not exceed US$300,000 other than in exceptional situations and in accordance with paragraph 3.7 the Guidelines: Selection and Employment of Consultants. 15. Irrespective of the thresholds and category of risk, the Terms of Reference (TOR) for selection of consultants (firms of individuals), whether prior or post review shall be cleared by the Bank. c) Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 7 7 Ref. Description of Estimated Method Revie Expected Expected No. Assignment Cost of w date of Contract Comments US$ Selectio by proposal Signature n Bank submissi Date (Prior on / Post) 1. Production of TOT 6,000.00 ICS Post 09/01/17 09/06/17 Life Skills Training materials 2. Procurement of a 63,000.00 ICS Post N/A 01/02/17 Project Technical Team Manager 3. Procurement of a 45,000.00 ICS Post N/A Productive Public Works Officer 4. Procurement of a 36,000.00 ICS Post N/A 01/02/17 Financial Management Officer 5. Procurement of a 27,000.00 ICS Post N/A 01/02/17 Monitoring & Evaluation and Safeguard Officer 6. Procurement of a 32,400.00 ICS Post N/A 01/02/17 Procurement Officer 7. Procurement of an 32,400.00 ICS Post N/A 01/02/17 Internal Auditor 8. Procurement of an 18,000.00 ICS Post N/A 01/02/17 MIS/ Project Assistant 9. Procurement of a 12,600.00 ICS Post N/A 08/10/17 Montserrado County Coordinator 10. Procurement of a 12,600.00 ICS Post N/A 08/10/17 Bomi County Coordinator 11. Procurement of a 12,600.00 ICS Post N/A 08/10/17 Grand Cape Mount County Coordinator 12. Procurement of a 12,600.00 ICS 08/10/17 Grand Bassa County Coordinator 13. Procurement of a 12,600.00 ICS Post N/A 08/10/17 River Cess County Coordinator 14. Procurement of a 12,600.00 ICS Post N/A 08/10/17 Margibi County Coordinator Procurement of a 12,600.00 ICS Post N/A 08/10/17 Gbarpolu County Coordinator Procurement of a 12,600.00 ICS Post N/A 08/10/17 Bong County Coordinator Procurement of a 12,600.00 ICS Post N/A 08/10/17 Lofa County Coordinator Procurement of a 12,600.00 ICS Post N/A 08/10/17 Nimba County Coordinator Procurement of a 12,600.00 ICS Post N/A 08/10/17 River Gee County Coordinator Procurement of a 12,600.00 ICS Post N/A 08/10/17 Grand Gedeh County Coordinator Procurement of a 12,600.00 ICS Post N/A 08/10/17 Sinoe County Coordinator Procurement of a 12,600.00 ICS post N/A 08/10/17 Maryland County Coordinator Procurement of a 12,600.00 ICS Post N/A 08/10/17 Grand Kru County Coordinator Procurement of a 20,000.00 CQS Post 02/03/17 02/27/17 Bomi Community Facilitator Procurement of a 20,000.00 CQS Post 02/03/17 02/27/17 Grand Cape Mount Community Facilitator Procurement of a 20,000.00 CQS Post 02/03/17 02/27/17 Grand Bassa Community Facilitator Procurement of a 20,000.00 CQS Post 02/03/17 02/27/17 Margibi Community Facilitator Procurement of a 20,000.00 CQS Post 02/03/17 02/27/17 Gbarpolu Community Facilitator Procurement of a 20,000.00 CQS post 02/03/17 02/27/17 Bong Community Facilitator Procurement of a 20,000.00 CQS Post 02/27/17 Lofa Community Facilitator Procurement of a 20,000.00 CQS Post 02/03/17 02/27/17 Nimba Community Facilitator Procurement of a 20,000.00 CQS post 02/03/17 02/27/17 River Gee Community Facilitator Procurement of a 20,000.00 CQS Post 02/03/17 02/27/17 Grand Gedeh Community Facilitator Procurement of a 20,000.00 CQS Post 02/03/17 02/27/17 Grand Kru Community Facilitator Procurement of a 20,000.00 CQS Post 02/27/17 Sinoe Community Facilitator Procurement of a 20,000.00 CQS Post 02/03/17 Rivercee Community Facilitator Consulting 240,000.00 QCBS Post 03/06/17 04/27/17 Services for Apprenticeship training for Household Enterprise beneficiaries Service Providers 287,899.00 QCBS Post 12/27/16 01/23/17 to supervise Household Enterprise beneficiaries Data Management 100,000.00 QCBS Post N/A 12/21/17 Firm (Consultancy Firm) TOTAL d) Training and Workshop Ref. Training, workshop and study Estimated Estimated Expected Training/workshop No. tours Cost (US$) Duration (Days) Date 1. 2. GENERAL NOTES 1. Training and capacity building: Training workshops (including training material and support), conference attendance and study tours, will be carried out based on approved annual training and allied activities plan. A detailed training and workshops’ plan giving nature of training/workshop, number of trainees/participants, duration, staff months, timing and estimated cost will be submitted to the Bank for review and approval prior to initiating the process. The selection methods will derive from the activity requirement, schedule and circumstance. After the training, the beneficiaries will be requested to submit a brief report indicating what skill have been acquired and how these skills will contribute to enhance their performance and contribute to the attainment of the Project’s development objective. 2. Operating costs: Incremental recurrent expenditures during project implementation, including maintenance of vehicles, fuel, equipment, office supplies, utilities, consumables, banking charges, advertising expenses, internet service, car insurance, travel, per diems, and accommodations, but excluding salaries of civil and public servants, will be procured using the implementing agency's administrative procedures reviewed and found acceptable by the Bank. PROCUREMENT Liberia : Liberia Youth Opportunities Project PLAN General Information Country: Liberia Bank’s Approval Date of the Original Procurement Plan: 2018-05-28 2021-05-31 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P146827 GPN Date: Project Name: Liberia Youth Opportunities Project Loan / Credit No: IDA / 56210 Ministry of Youth and Sport Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned LR-MOYS-62740-CW-RFQ / Project Implementation and Request for Single Stage - One 2019-01- IDA / 56210 Post Limited 21,000.00 0.00 Canceled 2018-06-13 2018-07-18 Office Renovation Coordination Quotations Envelope 14 Request for LR-MOYS-232451-CW-RFQ / Project Implementation and Request for Single Stage - One 2021-08- IDA / 56210 Post Limited Quotations (Non 67,950.00 69,141.16 Signed 2021-05-22 2021-05-13 2021-07-17 2021-05-27 Office Renovation Coordination Quotations Envelope 16 Bank-SPD) GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LR-MOYS-62659-GO-RFQ / Procurement of Cross County Project Implementation and Request for Single Stage - One IDA / 56210 Post Limited 88,000.00 0.00 Canceled 2018-06-12 2018-06-29 2018-07-20 Vehicles for operations (2 Coordination Quotations Envelope Nos) LR-MOYS-62670-GO-RFQ / Project Implementation and Request for Single Stage - One Supply of additional laptop (2 IDA / 56210 Post Limited 2,700.00 0.00 Canceled 2018-06-11 2018-08-06 2019-02-02 Coordination Quotations Envelope No); Desktop (new) LR-MOYS-62747-GO-RFQ / Supply of additional air Project Implementation and Request for Single Stage - One IDA / 56210 Post Limited 2,100.00 0.00 Canceled 2018-05-23 2018-07-18 2019-01-14 condition (3) & Refregerators Coordination Quotations Envelope (2) LR-MOYS-62738-GO-RFQ / Project Implementation and Request for Single Stage - One IDA / 56210 Post Limited 10,200.00 0.00 Canceled 2018-06-11 2018-06-29 2018-12-26 Supply of office furnitures Coordination Quotations Envelope LR-MOYS-62704-GO-RFQ / Supply of laptop computers (6 Project Implementation and Request for Single Stage - One Nos); Desktop (1); Duplex IDA / 56210 Post Limited 10,800.00 0.00 Canceled 2018-06-11 2018-07-12 2019-01-08 Coordination Quotations Envelope printer (1); Portable printer (3 No) and Project (1) LR-MOYS-128979-GO-RFQ / Pre-Employment Social Procurement of Pre- Request for Single Stage - One IDA / 56210 Support and Household Post Limited 4,000.00 2,997.00 Completed 2019-10-05 2019-10-18 2019-11-30 2019-10-25 2020-05-28 2019-10-28 Employment Social Support Quotations Envelope Enterprises for Urban Youth Training Materials LR-MOYS-128980-GO-DIR / Pre-Employment Social Access to digital payment IDA / 56210 Support and Household Prior Direct Selection Direct 150,000.00 102,000.00 Signed 2019-09-30 2019-09-17 2019-10-05 2019-10-03 2019-11-09 2019-10-14 2020-05-07 (mobile phones for Enterprises for Urban Youth beneficiaries) LR-MOYS-81962-GO-RFQ / Project Implementation and Request for Single Stage - One Procurement of Portoble IDA / 56210 Post Limited 900.00 0.00 Canceled 2018-11-17 2019-01-30 2019-01-12 2019-07-11 Coordination Quotations Envelope Printersfor office use ( 3 PCS) LR-MOYS-221066-GO-RFQ / Project Implementation and Request for Single Stage - One IDA / 56210 Post Limited 3,750.00 0.00 Canceled 2021-03-04 2021-04-29 2021-05-29 Signboards Coordination Quotations Envelope LR-MOYS-235912-GO-RFQ / Pre-Employment Social Pending Request for Single Stage - One Business Enhancement IDA / 56210 Support and Household Post Limited 31,000.00 0.00 Implementati 2021-06-04 2021-07-30 2021-07-30 Quotations Envelope Support Enterprises for Urban Youth on NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LR-MOYS-128978-NC-RFQ / Pre-Employment Social Request for Single Stage - One Production of Video IDA / 56210 Support and Household Post Limited 4,000.00 0.00 Canceled 2019-09-30 2019-11-25 2020-05-23 Quotations Envelope Documentary Enterprises for Urban Youth LR-MOYS-195976-NC-RFQ / Project Implementation and Request for Single Stage - One Equipment Rental for YOP IDA / 56210 Post Limited 2,950.00 2,949.93 Completed 2020-10-04 2020-09-30 2020-11-09 2020-10-12 2021-06-30 2020-11-07 Coordination Quotations Envelope Information Sharing LR-MOYS-235909-NC-RFQ / Pending Project Implementation and Request for Single Stage - One Production of Video IDA / 56210 Post Limited 9,000.00 0.00 Implementati 2021-06-04 2021-07-31 2021-08-01 Coordination Quotations Envelope Documentary on CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LR-MOYS-62749-CS-QCBS / Pre-Employment Social Consultant Recruitment of IDA / 56210 Support and Household Post Qualification Open - International 135,936.00 0.00 Canceled 2018-06-05 2018-07-03 2018-07-24 2018-08-06 2018-09-10 2019-03-09 firm/Consultant for PESS Enterprises for Urban Youth Selection Page 1 LR-MOYS-80411-CS-CQS / Pre-Employment Social Consultant Pre-Employment & Social IDA / 56210 Support and Household Post Qualification Open - International 125,000.00 124,993.60 Completed 2018-10-19 2018-10-11 2018-11-09 2018-10-11 2018-12-23 2018-12-17 2019-01-22 2019-01-31 2019-02-26 2019-02-14 2019-08-25 2020-02-29 Support Implementation Enterprises for Urban Youth Selection LR-MOYS-62752-CS-LCS / Recruitment of Project Implementation and Least Cost IDA / 56210 Post Open - National 8,000.00 0.00 Canceled 2018-06-08 2016-08-22 2018-06-29 2018-08-12 2018-09-09 2018-10-09 2018-11-13 2018-12-18 2019-06-16 Firm/Consultant for External Coordination Selection Auditor LR-MOYS-81961-CS-CQS / Consultant Recruitment of Project Implementation and IDA / 56210 Post Qualification Open - National 8,000.00 8,000.00 Signed 2016-08-15 2018-11-02 2016-09-05 2016-10-19 2018-09-20 2016-11-18 2018-01-10 2016-12-23 2018-01-10 2017-06-21 Firm/Consultant for External Coordination Selection Auditor LR-MOYS-134874-CS-CQS / Consultant Project Implementation and Annual Beneficiary Satisfaction IDA / 56210 Post Qualification Open - National 86,000.00 72,000.20 Signed 2019-09-30 2019-09-16 2019-10-21 2019-09-25 2019-12-04 2019-11-22 2020-01-03 2020-01-03 2020-02-07 2020-01-10 2020-04-30 Coordination Survey Selection LR-MOYS-128977-CS-LCS / Capacity Building for Cash Least Cost IDA / 56210 Post Open - National 15,000.00 0.00 Canceled 2019-09-30 2019-10-21 2019-12-04 2020-01-01 2020-01-31 2020-03-06 2020-04-10 2020-10-07 External Audit Transfer Program Selection INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LR-MOYS-62728-CS-INDV / Individual Project Implementation and Recruitment of International IDA / 56210 Post Consultant Open 96,000.00 0.00 Canceled 2018-06-07 2016-11-28 2018-07-19 2018-08-09 2018-09-13 2019-03-12 Coordination Procurement Specialist Selection LR-MOYS-62703-CS-INDV / Pre-Employment Social Individual Recruitment Grivence Redress IDA / 56210 Support and Household Post Consultant Limited 27,000.00 0.00 Canceled 2018-06-05 2016-11-01 2018-06-10 2018-07-24 2018-08-28 2019-02-24 Officer Enterprises for Urban Youth Selection LR-MOYS-62665-CS-INDV / Individual Project Implementation and Recruitment of Program IDA / 56210 Post Consultant Limited 18,000.00 0.00 Canceled 2018-06-04 2016-11-01 2018-06-09 2018-06-22 2018-07-27 2019-01-23 Coordination Assistant Selection LR-MOYS-65232-CS-INDV / Individual Project Implementation and Recruitment of Senior IDA / 56210 Post Consultant Open 72,000.00 0.00 Canceled 2018-06-12 2016-09-04 2018-07-31 2018-08-21 2018-09-25 2019-03-24 Coordination Program Officer Selection LR-MOYS-62862-CS-CQS / Individual Project Implementation and Recruitment of Project IDA / 56210 Post Consultant Open 81,800.00 0.00 Canceled 2018-06-12 2016-09-04 2018-07-31 2018-08-21 2018-09-25 2019-03-24 Coordination Coordinator Selection LR-MOYS-62708-CS-INDV / Pre-Employment Social Individual Recruitment of IDA / 56210 Support and Household Post Consultant Limited 36,000.00 0.00 Canceled 2018-06-07 2016-12-01 2018-06-12 2018-06-04 2018-07-03 2018-08-07 2019-02-03 Communication Officer Enterprises for Urban Youth Selection Pre-Employment Social Individual LR-MOYS-62743-CS-INDV / IDA / 56210 Support and Household Post Consultant Limited 27,000.00 0.00 Canceled 2018-06-06 2018-06-11 2018-07-02 2018-08-06 2019-02-02 Recruitment of M & E Officer Enterprises for Urban Youth Selection LR-MOYS-62726-CS-INDV / Individual Project Implementation and Recruitment of Account IDA / 56210 Post Consultant Limited 36,000.00 0.00 Canceled 2018-06-06 2018-06-11 2018-07-02 2018-08-06 2019-02-02 Coordination Management (PFMU) Selection LR-MOYS-81957-CS-CDS / Recruitment of a firm for Project Implementation and IDA / 56210 Post Direct Selection Direct 19,200.00 19,200.00 Completed 2018-07-20 2018-10-17 2018-07-30 2018-10-03 2019-03-01 2019-04-01 2019-03-01 external audit for fiscal year Coordination 2017/2018 LR-MOYS-81954-CS-INDV / Individual Recruitment for Project Implementation and IDA / 56210 Post Consultant Open 24,000.00 24,000.00 Completed 2018-05-15 2018-08-06 2018-07-03 2018-08-31 2018-07-24 2018-09-17 2018-08-28 2018-09-21 2019-02-24 2019-09-30 Communiications Officer FY Coordination Selection 20182019 LR-MOYS-81958-CS-CDS / Project Implementation and Recruitment of Project IDA / 56210 Post Direct Selection Direct 54,120.00 4,000.00 Signed 2016-10-07 2016-08-01 2016-10-17 2016-12-21 2016-09-15 2017-06-19 Coordination Coordinator LR-MOYS-81945-CS-CDS / Project Implementation and Recruitment of Senior IDA / 56210 Post Direct Selection Direct 48,000.00 150,000.00 Signed 2016-10-07 2016-08-01 2016-10-17 2016-11-15 2016-12-21 2016-09-26 2017-06-19 Coordination Program Officer Individual LR-MOYS-81952-CS-INDV / Project Implementation and IDA / 56210 Post Consultant Open 18,000.00 36,000.00 Signed 2016-10-07 2018-11-02 2016-11-25 2017-02-16 2016-12-16 2017-03-06 2017-01-20 2017-03-27 2017-07-19 Recruitment of M & E Officer Coordination Selection LR-MOYS-81947-CS-INDV / Individual Recruitment of Project Implementation and IDA / 56210 Post Consultant Open 24,000.00 19,200.00 Signed 2016-10-07 2016-12-15 2016-11-25 2017-01-26 2016-12-16 2017-03-20 2017-01-20 2017-03-27 2017-07-19 Communication Officer FY Coordination Selection 20172018 LR-MOYS-81955-CS-INDV / Individual Project Implementation and Recruitment of Program IDA / 56210 Post Consultant Open 12,000.00 24,000.00 Signed 2016-10-07 2016-12-16 2016-11-25 2017-03-06 2016-12-16 2017-03-20 2017-01-20 2017-03-24 2017-07-19 Coordination Assistant Selection LR-MOYS-81964-CS-INDV / Individual Project Implementation and Recruitment Grivence Redress IDA / 56210 Post Consultant Open 18,000.00 18,000.00 Signed 2016-11-14 2016-12-15 2017-01-02 2017-03-06 2017-01-23 2017-03-20 2017-02-27 2017-03-24 2017-08-26 Coordination Officer Selection LR-MOYS-81948-CS-CDS / Project Implementation and Recruitment of Account IDA / 56210 Post Direct Selection Direct 24,000.00 24,000.00 Signed 2016-11-10 2017-01-17 2016-11-20 2018-01-29 2017-01-24 2018-01-01 2017-07-23 Coordination Management (PFMU) LR-MOYS-81950-CS-INDV / Individual Project Implementation and Under Recruitment of International IDA / 56210 Prior Consultant Open 96,000.00 0.00 2016-11-10 2021-04-21 2016-12-29 2017-03-06 2017-01-19 2017-02-23 2017-08-22 Coordination Implementation Procurement Specialist Selection LR-MOYS-94777-CS-INDV / Individual Project Implementation and Procurement of a Senior IDA / 56210 Prior Consultant Limited 24,000.00 0.00 Canceled 2019-02-20 2019-03-11 2019-02-25 2019-03-18 2019-04-22 2020-04-16 Coordination Procurement Officer Selection Page 2 LR-MOYS-106128-CS-INDV Individual Project Implementation and / Hiring of a Procurement IDA / 56210 Prior Consultant Limited 24,000.00 0.00 Canceled 2019-03-20 2019-03-19 2019-03-25 2019-03-20 2019-04-15 2019-05-20 2020-05-14 Coordination Specialist Selection LR-MOYS-108034-CS-INDV Individual Project Implementation and / Hiring of a Procurement IDA / 56210 Prior Consultant Limited 24,000.00 24,000.00 Signed 2019-03-19 2019-03-28 2019-03-24 2019-04-03 2019-04-14 2019-06-26 2019-05-19 2019-07-01 2020-05-13 Coordination Specialist Selection Individual LR-MOYS-114073-CS-INDV Project Implementation and IDA / 56210 Post Consultant Open 5,000.00 5,000.00 Completed 2019-05-15 2019-05-13 2019-07-03 2019-08-12 2019-07-24 2019-08-14 2019-08-21 2019-09-02 2020-02-17 2020-09-02 / YOP Website Development. Coordination Selection LR-MOYS-134380-CS-CDS / Project Implementation and IDA / 56210 Post Direct Selection Direct 12,500.00 0.00 Canceled 2019-09-18 2019-09-28 2019-12-02 2020-05-30 MIS Consultant Coordination LR-MOYS-134873-CS-CDS / Project Implementation and IDA / 56210 Post Direct Selection Direct 12,500.00 12,000.00 Signed 2019-09-19 2019-08-23 2019-09-29 2019-10-07 2019-12-03 2019-10-09 2020-05-31 MIS Consultant Coordination LR-MOYS-136594-CS-CDS / Project Implementation and IDA / 56210 Post Direct Selection Direct 33,048.00 33,048.00 Completed 2019-09-30 2019-10-03 2019-10-10 2019-09-27 2019-12-14 2019-10-07 2020-06-11 2020-06-30 Senior Program Officer Coordination LR-MOYS-136590-CS-CDS / Project Implementation and IDA / 56210 Post Direct Selection Direct 37,261.62 86,943.78 Signed 2019-10-04 2019-10-03 2019-10-14 2019-09-27 2019-12-18 2019-10-07 2020-06-15 National Program Coordinator Coordination LR-MOYS-136591-CS-CDS / Project Implementation and IDA / 56210 Post Direct Selection Direct 10,800.00 10,800.00 Completed 2019-09-30 2019-10-03 2019-10-10 2019-09-27 2019-12-14 2019-10-07 2020-06-11 2020-03-31 Communications Officer Coordination LR-MOYS-186219-CS-CDS / Pre-Employment Social Pre-employment Social IDA / 56210 Support and Household Post Direct Selection Direct 108,400.00 104,706.00 Signed 2020-08-29 2020-08-06 2020-09-08 2020-08-11 2020-11-12 2020-09-01 2021-05-11 Support Round Two Enterprises for Urban Youth Individual LR-MOYS-191398-CS-INDV Project Implementation and IDA / 56210 Post Consultant Limited 10,000.00 9,000.00 Signed 2020-09-30 2020-09-02 2020-10-05 2020-09-06 2020-10-26 2020-09-12 2020-11-30 2020-09-14 2021-06-30 / Program Support Officer Coordination Selection LR-MOYS-191403-CS-INDV Individual Project Implementation and / Administrative/GRM IDA / 56210 Post Consultant Limited 5,000.00 4,500.00 Signed 2020-09-30 2020-09-02 2020-10-05 2020-09-04 2020-10-26 2020-09-12 2020-11-30 2020-09-14 2021-06-30 Coordination Assistant Selection LR-MOYS-214934-CS-INDV Individual Project Implementation and / Environmental Social IDA / 56210 Post Consultant Limited 5,000.00 5,000.00 Completed 2021-02-05 2021-01-19 2021-02-10 2021-01-24 2021-03-03 2021-01-29 2021-04-07 2021-01-30 2021-04-30 2021-02-25 Coordination Consultant Selection LR-MOYS-220491-CS-INDV Individual Project Implementation and / Implementation Completion IDA / 56210 Post Consultant Open 40,000.00 35,000.00 Signed 2021-03-29 2021-02-24 2021-05-17 2021-04-11 2021-06-07 2021-04-29 2021-07-12 2021-05-01 2021-09-30 Coordination Report (ICR) Selection LR-MOYS-220490-CS-INDV Individual / Development of Project Project Implementation and IDA / 56210 Post Consultant Limited 10,000.00 8,000.00 Signed 2021-03-29 2021-02-24 2021-04-03 2021-03-02 2021-04-24 2021-03-29 2021-05-29 2021-04-01 2021-08-27 Operations Manual and Coordination Selection handbooks LR-MOYS-234760-CS-CDS / Project Implementation and IDA / 56210 Post Direct Selection Direct 2,000.00 1,000.00 Signed 2021-05-17 2021-05-23 2021-05-27 2021-05-23 2021-07-31 2021-05-25 2021-08-01 MIS/Program Assistant Coordination Page 3 PROCUREMENT PLAN Project information: Lao PDR - Public Finance Management Reform Grant Project Implementation agency: Ministry of Finance Date of the Procurement Plan: October 12, 2018 Period covered by this Procurement Plan: at least 18 months Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Public Procurement Law and the Instruction on Implementation Public Procurement Law, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. a) The request for bids/request for proposals document shall require that bidders/proposers submitting bids/proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, Bank Anti- Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights; b) Information related to award of contract including reasons for rejection of unsuccessful bidders shall be published on the implementing agency websites and/or newspaper of wide circulation. c) All complaints on procurement related matters including complaints arising from procurement under Bank financed Projects whilst using National Procurement Procedures shall be dealt with in accordance with Article 33 of the Procurement Decree. Borrower shall put in place an effective complaints review mechanism for dealing with procurement related complaints, and shall disclose the details in all the bidding documents. All complaints shall be recorded by the 1 Borrower in the appropriate tracking and monitoring system, as agreed between the Bank and the Borrower. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables. Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is applicable for those contracts identified in the Procurement Plan tables; Works: is applicable for those contracts identified in the Procurement Plan tables Other Relevant Procurement Information. I. Works and Goods and Non-Consultant Services 1.1.Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Annex II of the Procurement Regulations: Category Procurement Method Prior Review Thresholds Thresholds Applicable Remarks Applicable Remarks thresholds thresholds (US$) (US$) Works RFB through ≥ 2.0 million – Above 10 million This has not been Open foreseen at the International project preparation market stage. approach RFB through ≥ 200,000 < – None - Open National 2.0 million market approach Request for < 200,000 – None – Quotation Direct Selection None No threshold; Same as for This has not been meet competitive foreseen at the requirements of selection project preparation regulations stage. 7.13-7.15 Goods and Non-Consulting Services 2 RFB through ≥ 0.6 million – Above US$ 2 This has not been Open million foreseen at the International project preparation market stage. approach RFB through ≥ 100,000 < - None Risk-based approach Open National 0.6 million market approach Request for < 100,000 None Quotation Direct Selection None No threshold; Same as for This has not been meet competitive foreseen at the requirements of selection project preparation regulations stage. 7.13-7.15 1.2 Procurement packages for Goods (prior and post reviews) with method and Time Schedule Ref. Contract (Description) Estimat Procurem Revie Expecte Comme No. ed Cost ent w by d Bids nts (US$) Method Bank Opening (Prior Date / Post) G-01 ICT equipment for MoHA 50,000 RFQ Post Feb 15, and Project 2019 Implementation Unit G-02 Office furniture, printers, 10,000 Shopping Post Feb 15, etc for PIU 2019 G-03 Financial Management 5,000 Shopping Post Feb 15, software 2019 Total Goods 65,000 II. Selection of Consultants 2.1 Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Annex II of the Procurement Regulations: Procurement Method Thresholds Prior Review Thresholds Applicable Applicable Category thresholds Remarks thresholds Remarks (US$) (US$) QCBS, QBS, FBS, ≥ 300,000 Shortlist of only ≥ 1.0 million Risk-based LCS (Using the National Consultants approach most appropriate (Firms) for contract market approach) agreed in the PP CQS (Open or < 300,000 QCBS, QBS, FBS, LCS) None limited can be applied for competition contracts with value through national or under $300,000 international market approach, specified in the PP and agreed with the Bank. 3 Direct Selection of None No threshold; meet Same as for This has not firms requirements of competitive been foreseen regulations 7.13-7.15 selection at the project preparation stage. Individual N/A Essential individual ≥ 300,000 Risk-based Consultants depending assignments will be and for the approach on nature of defined in the positions as services Procurement Plan specified in agreed with the Bank the PP and in line with agreed with regulations 7.34-7.39 the Bank using the most appropriate market approach 2.2 Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than US$ 200,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 7.1, Section VII of the Procurement Regulations. 2.3 Consultancy Assignments with Selection Methods and Time Schedule Ref. Description of Estimat Selecti Review Expected Comme No. Assignment ed Cost on by Proposals nts US$ Metho Bank Submissio d (Prior / n Date Post) IC-01 PIU Coordinator 36,000 IC Post Jan. 10, 2019 IC-02 PIU Assistant 15,000 IC Post Jan. 10, 2019 IC-03 Financial Management 36,000 IC Post Jan. 10, Consultant* 2019 IC-04 Procurement Consultant 36,000 IC Post Jan. 10, 2019 IC-05 Procurement Assistant 15,000 IC Post Jan. 10, 2019 IC-06 Accountant* 24,000 IC Post Jan. 10, 2019 IC-07 M&E Consultant 30,000 IC Post Jan. 10, 2019 IC-08 Change Management 30,000 IC Post Feb. 15, Consultant 2019 CQS- Audit Firm* 30,000 CQS Post Feb. 15, 01 2019 QCBS - Consulting services for the 500,000 QCBS Post April 2019 01 preparation of the technical specifications and bidding documents for FMIS* Total consulting services 757,000 Total Goods and Consulting 817,000 Services * Although these packages are subject to procurement Post Review, the World Bank will do technical review. 4 Note: 1. To select external financial audit, project implementing agencies shall send their RFPs to all three qualified firms namely PwC, KPMG and EY; that are acceptable audit firms for bank financed projects in the Lao PDR. 5 PROCUREMENT Lao People's Democratic Republic : Lao PDR Public Finance Management Reform Project PLAN General Information Country: Lao People's Democratic Republic Bank’s Approval Date of the Original Procurement Plan: 2019-01-21 2021-05-24 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P167661 GPN Date: 2019-01-10 Project Name: Lao PDR Public Finance Management Reform Project Loan / Credit No: TF / A9517, / M Executing Agency(ies): inistry of Finance WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 2: Enhanced G-01 / ICT equipment for budget preparation and Request for Single Stage - One MoHA and Project TF / A9517 Post Limited 50,000.00 63,955.08 Signed 2019-07-05 2019-12-12 2019-08-20 2020-01-24 2020-02-16 execution and Quotations Envelope Implementation Unit interoperability of government PFM systems Component 4: Public G-02 / Office furniture, Financial Management (PFM) Request for Single Stage - One TF / A9517 Post Limited 10,000.00 11,468.71 Signed 2019-01-16 2019-07-11 2019-03-13 2019-09-04 2019-09-09 printers, etc for PIU Reform and Program Quotations Envelope Coordination Component 4: Public G-03 / Financial Management Financial Management (PFM) Request for Single Stage - One TF / A9517 Post Limited 5,000.00 2,200.00 Signed 2019-08-03 2019-11-04 2019-09-28 2019-12-17 2020-03-26 software Reform and Program Quotations Envelope Coordination Component 4: Public Financial Management (PFM) Request for Single Stage - One G-04 / IT Equipment for PIU TF / A9517 Post Limited 25,000.00 24,268.51 Signed 2019-07-10 2019-07-03 2019-09-04 2019-08-12 2020-03-02 Reform and Program Quotations Envelope Coordination Component 4: Public Pending Financial Management (PFM) Request for Single Stage - One G-05 / Furniture for FPLD TF / A9517 Post Limited 1,200.00 0.00 Implementati 2020-07-20 2020-09-14 2021-03-13 Reform and Program Quotations Envelope on Coordination Component 4: Public G-06 / IT Equipment for PIU Financial Management (PFM) Request for Single Stage - One TF / A9517 Post Limited 5,000.00 13,556.01 Signed 2020-07-20 2020-09-28 2020-09-14 2020-12-04 2021-03-13 and PPMD Reform and Program Quotations Envelope Coordination NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual QCBS-01 / Consulting Component 4: Public services for the preparation of Financial Management (PFM) Quality And Cost- the technical specifications / Post Open - International 500,000.00 0.00 Canceled 2019-02-01 2019-02-05 2019-02-22 2019-04-07 2019-05-05 2019-06-04 2019-07-09 2019-08-13 2020-08-12 Reform and Program Based Selection and bidding documents for Coordination FMIS Component 4: Public Consultant Financial Management (PFM) CQS-01 / External Audit Firm TF / A9517 Post Qualification Open - National 30,000.00 129,910.00 Signed 2019-02-01 2019-11-06 2019-02-22 2019-04-07 2019-11-11 2019-05-07 2020-05-04 2019-06-11 2020-05-22 2019-12-08 Reform and Program Selection Coordination QCBS-1 / Consulting services Component 2: Enhanced for the preparation of the budget preparation and Quality And Cost- technical specifications, bid TF / A9517 execution and Prior Open - International 500,000.00 1,048,576.00 Signed 2019-02-28 2019-02-11 2019-03-21 2019-02-11 2019-05-04 2019-07-18 2019-06-01 2019-08-30 2019-07-01 2020-01-21 2019-08-05 2020-06-15 2019-09-09 2020-06-30 2020-09-08 Based Selection evaluation and contract interoperability of supervision government PFM systems Component 2: Enhanced CQS-02 / Excel templates Consultant budget preparation and develop for Budget TF / A9517 Post Qualification Open - National 8,000.00 8,811.00 Signed 2019-09-10 2019-08-01 2019-10-01 2019-11-14 2020-08-06 2019-12-14 2020-10-12 2020-01-18 2020-11-20 2020-07-16 execution and Department Selection interoperability of government PFM systems INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 4: Public Individual Financial Management (PFM) IC-01 / PIU Coordinator TF / A9517 Post Consultant Open 36,000.00 1,515.00 Terminated 2019-01-10 2019-01-01 2019-02-28 2019-06-01 2019-03-21 2019-06-07 2019-04-25 2019-06-28 2019-10-22 Reform and Program Selection Coordination Component 4: Public Individual IC-07 / Monitoring and Financial Management (PFM) TF / A9517 Post Consultant Open 30,000.00 21,780.00 Signed 2019-01-18 2019-01-02 2019-03-08 2019-07-18 2019-03-29 2019-07-19 2019-05-03 2019-08-02 2019-10-30 Evaluation (M&E) Specialist Reform and Program Selection Coordination Page 1 Component 2: Enhanced Individual IC-08 / Change Management budget preparation and TF / A9517 Post Consultant Open 30,000.00 0.00 Canceled 2019-01-18 2020-11-24 2019-03-08 2019-03-29 2019-05-03 2019-10-30 Specialist execution and Selection interoperability of government PFM systems Component 4: Public Individual Financial Management (PFM) IC-02 / PIU Assistant TF / A9517 Post Consultant Open 15,000.00 12,000.00 Signed 2019-01-18 2019-01-02 2019-03-08 2019-03-02 2019-03-29 2019-05-29 2019-07-01 2019-05-24 2019-12-28 Reform and Program Selection Coordination Component 4: Public Individual IC-03 / Financial Financial Management (PFM) TF / A9517 Post Consultant Open 36,000.00 25,200.00 Signed 2019-01-18 2019-01-02 2019-03-08 2019-06-03 2019-03-29 2019-05-28 2019-07-01 2019-06-25 2019-12-28 Management Specialist Reform and Program Selection Coordination Component 4: Public Individual IC-04 / Procurement Financial Management (PFM) TF / A9517 Post Consultant Open 36,000.00 25,200.00 Terminated 2019-01-18 2019-01-01 2019-03-08 2019-02-13 2019-03-29 2019-04-01 2019-07-01 2019-06-28 2019-12-28 Specialist Reform and Program Selection Coordination Component 4: Public Individual Financial Management (PFM) IC-06 / Accountant TF / A9517 Post Consultant Open 24,000.00 24,000.00 Signed 2019-01-18 2019-01-02 2019-03-08 2019-06-24 2019-03-29 2019-06-21 2019-07-01 2019-07-19 2019-12-28 Reform and Program Selection Coordination Component 4: Public Individual IC-09 / Procurement Financial Management (PFM) TF / A9517 Post Consultant Open 32,000.00 31,200.00 Signed 2019-07-15 2019-07-15 2019-09-02 2019-10-30 2019-09-23 2019-12-03 2019-10-28 2020-01-02 2020-04-25 Consultant to Support PPMD Reform and Program Selection Coordination Component 1: Improved Individual IC-10 / Consultant to TF / A9517 domestic revenue Post Consultant Open 24,000.00 22,440.00 Signed 2019-11-18 2019-07-31 2020-01-06 2020-02-05 2020-01-27 2020-02-06 2020-03-02 2020-07-01 2020-08-29 support on tax legislation mobilization Selection Component 2: Enhanced Individual IC-11 / Budget reform budget preparation and TF / A9517 Post Consultant Open 9,000.00 0.00 Canceled 2020-02-03 2020-12-18 2020-03-23 2020-04-13 2020-05-18 2020-11-14 Consultant 1 execution and Selection interoperability of government PFM systems Component 2: Enhanced Individual IC-12 / Budget reform budget preparation and TF / A9517 Post Consultant Open 9,000.00 0.00 Canceled 2020-02-03 2020-12-18 2020-03-23 2020-04-13 2020-05-18 2020-11-14 Consultant 2 execution and Selection interoperability of government PFM systems Component 2: Enhanced DS-01 / Methodology budget preparation and Under TF / A9517 Post Direct Selection Direct 2,000.00 0.00 2020-10-05 2020-12-16 2020-10-15 2020-12-19 2021-06-17 training /NUOL execution and Implementation interoperability of government PFM systems DS-02 / Recruit a local consultant to extract Component 1: Improved Under information from Tax TF / A9517 domestic revenue Post Direct Selection Direct 50,000.00 0.00 2021-03-02 2021-03-03 2021-03-14 2021-05-25 2021-11-21 Implementation Management Information mobilization System (TMIS) Component 1: Improved Individual IC-13 / Data Analysis Under TF / A9517 domestic revenue Post Consultant Limited 7,800.00 0.00 2021-05-25 2021-05-28 2021-05-30 2021-06-20 2021-07-25 2022-01-21 Consultant for RBA Implementation mobilization Selection Page 2 Plan de Passation de marchés I. Généralités 1. L'information sur le projet : Pays : Océan Indien ; Emprunteur : COMMISSION DE L’OCEAN INDIEN ; Nom de projet : P132123: First South West Indian Ocean Fisheries Governance and Shared Growth Project – SWIOFish1 Numéro du Crédit : IDA-Grant Number H– 995-3A Agence d’exécution du Projet : COMMISSION DE L’OCEAN INDIEN 2. Date d’approbation du Plan de passation de marchés par la Banque : 30/11/2015 ; Révision : 02/12/2016 ; 3. Date de notification du Plan Général de Passation de marchés : N/A ; 4. Période couverte par le Plan de Passation de marchés : 01/01/2018 au 31/12/2018 II. Biens et Travaux et Services hors consultants 1. Seuil de Revue préalable : Les décisions de passation de marchés sujet aux revues préalables de la Banque comme indiqué dans le paragraphe 3.1 de l'Annexe II du Règlement de Passation des Marchés pour les Emprunteurs sollicitant le Financement de Projets d’Investissement (Juillet 2016) et sur la base de l'évaluation de la capacité de l'agence d’exécution : Seuil de Méthode de Passation de revue à Commentaires marchés priori 1. AOI – Ouvert ou Restreint 2 000 000 Les montants (Biens) estimatifs des 2. AON (Biens) 2 000 000 marchés prévus 3. AOI (Travaux) 10 000 000 sont au-dessous 4. AON (Travaux) 10 000 000 des seuils. 5. AOI (Services) 2 000 000 Niveau de 6. UN -UNOPS (Biens) 2 000 000 risque : 7. ED (Biens/Travaux) 2 000 000 « SUBSTANTIEL » 2. Pré-qualification (selon les dispositions des paragraphes 6.19 à 6.24 de la Section VI du Règlement de Passation des Marchés pour les Emprunteurs sollicitant le Financement de Projets d’Investissement (Juillet 2016)) : Non Applicable. 3. Procédures proposées pour les composantes CDD (selon le paragraphe. 6.52 et 6.53 de la Section VI du Règlement de Passation des Marchés pour les Emprunteurs sollicitant le Financement de Projets d’Investissement (Juillet 2016)) : Non Applicable 4. Référence (s’il y en a) au Manuel d’exécution du projet / Manuel de Passation de marchés : Non Applicable 5. Tout autre arrangement spécial en passation de marchés : Non Applicable. 6. Allotissement de fournitures avec méthodes et calendrier : [Enumérer d’abord les allotissements qui nécessitent la revue préalable de la Banque, ensuite les autres allotissements] 1 2 3 4 5 6 7 8 9 Réf. Description Contrat Coût Approche/Méth Pré- Préféren Revue de la Date Commentair No estimatif ode de qualificati ce Banque (à prévue es sélection on national priori / à d’ouverture Oui / Non e posteriori) des Oui / Non soumission s 0610 2- Acquisition d'équipement des Unita PY03 bureaux de la CPSOOI à Maputo 15,000.00 ire Shopping Non Non Postériori 09/05/2018 - (vidéoconférence) G001 Atelier sur les pratiques 0610 optimales et les leçons 2- d’expérience – Atelier de Forfai PY03 discussion sur des articles de 15,000.00 t Shopping Non Non Postériori 05/01/2018 - publications scientifiques à NC01 Maurice (conférence package & impression) 0610 Appui régional pour la mise en 2- œuvre des résolutions de la Forfai PY03 CTOI et la conformité à ces 2,620.00 Shopping Non Non Postériori 12/03/2018 t - résolutions (frais & conférence NC02 package & impression) 0610 Réunion du Groupe spécial sur 2- les conditions minimales Forfai PY03 d’accès (frais & conférence 2,500.00 Shopping Non Non Postériori 20/01/2018 t - package & impression) NC03 0610 Programme régional Forfai 2- d’observateurs (frais & 2,500.00 Shopping Non Non Postériori 10/08/2018 t 1 2 3 4 5 6 7 8 9 Réf. Description Contrat Coût Approche/Méth Pré- Préféren Revue de la Date Commentair No estimatif ode de qualificati ce Banque (à prévue es sélection on national priori / à d’ouverture Oui / Non e posteriori) des Oui / Non soumission s PY03 conférence package & - impression) NC04 0610 Atelier juridique pour 2- l’établissement d’un protocole PY03 d’échange d’informations dans Forfai - la région du sud-ouest de 2,000.00 Shopping Non Non Postériori 12/03/2018 t NC05 l’océan Indien (frais & conférence package & impression) 0610 Réunion sur les procédures 2- opérationnelles normalisées Forfai PY03 (frais & conférence package & 3,500.00 Shopping Non Non Postériori 10/02/2018 t - impression) NC06 0610 Atelier pour l’Afrique orientale, 2- l’Afrique australe et l’océan Forfai PY03 Indien (AO-AA-OI) - SADC 10,000.00 Shopping Non Non Postériori 09/04/2018 t - (conférence package) NC07 0610 Session de la CPSOOI et réunion 2- du Comité de pilotage régional Forfai PY03 de SWIO-Fish1 (frais & 10,400.00 Shopping Non Non Postériori 04/03/2018 t - conférence package & NC08 impression) 0610 Réunion du Groupe de travail 2- sur la collaboration et la Forfai PY03 coopération dans les pêcheries 10,840.00 Shopping Non Non Postériori 24/12/2017 t - de thon (frais & conférence NC09 package & impression) 1 2 3 4 5 6 7 8 9 Réf. Description Contrat Coût Approche/Méth Pré- Préféren Revue de la Date Commentair No estimatif ode de qualificati ce Banque (à prévue es sélection on national priori / à d’ouverture Oui / Non e posteriori) des Oui / Non soumission s 0610 Réunion du Comité scientifique 2- de la CPSOOI (frais & Forfai PY03 conférence package & 6,000.00 Shopping Non Non Postériori 08/01/2018 t - impression) NC10 0610 Réunion du Groupe de travail 2- de la CPSOOI sur l’évaluation Forfai PY03 des stocks de poissons 7,000.00 Shopping Non Non Postériori 08/09/2018 t - pélagiques (frais & conférence NC11 package & impression) 0610 Formation à l’utilisation du 2- logiciel « Système R » dédié à Forfai PY03 l’évaluation des stocks de 6,500.00 Shopping Non Non Postériori 08/09/2018 t - poissons (frais & conférence NC12 package & impression) III. Sélection de consultants 1. Seuil de Revue Préalable : Décisions de sélection sujet à la revue préalable de la Banque comme indiqué dans le paragraphe 3 de l'Annexe II du Règlement de Passation des Marchés pour les Emprunteurs sollicitant le Financement de Projets d’Investissement (Juillet 2016) : Méthode de sélection Seuil de Commentaires revue à priori 1. Méthode compétitive (firmes) 1 000 000 Les montants 2. Entente directe (firmes) 1 000 000 estimatifs des 3. Méthode compétitive (Consultant 300 000 contrats prévus individuel) sont au-dessous 4. Entente directe (Consultant 300 000 des seuils. individuel) Niveau de risque : « SUBSTANTIEL » 2. Liste restreinte composée entièrement de consultants nationaux : Liste restreinte de consultants pour prestations de services, estimés à moins de USD 150 000 par contrat, peut comporter entièrement des consultants nationaux selon les dispositions du paragraphe 7.25 de l'Annexe II du Règlement de Passation des Marchés pour les Emprunteurs sollicitant le Financement de Projets d’Investissement (Juillet 2016). 3. Tout autre arrangement spécial de Sélection de consultants : Non applicable 4. Tâches de consultation avec des méthodes de sélection et calendrier Réf. Description des missions Coût Approche/Méthode de Revue de la Date prévue Commentaires No. estimatif sélection Banque (à de (en USD) priori / à soumission posteriori) des propositions 0610 Consultance sur l'analyse coûts et 2- bénéfices (SWIOFish 1 framework Consultant PY03 15,000.00 Forfait Postériori 09/08/2018 agreement merging with Fisheries Individuel - Accord) C001 0610 2- Appui à l’institut KMFRI pour la mise en Consultant PY03 service de la base de données du projet 25,000.00 Forfait Postériori 09/08/2018 Individuel - SWIOFP C002 0610 2- Appui à l'élaboration résolutions de la Consultant PY03 5,000.00 Forfait Postériori 12/02/2018 CTOI Individuel - C003 0610 Etude de consultant sur la contribution 2- du secteur des pêches au PIB couvrant Consultant PY03 40,000.00 Forfait Postériori 30/03/2018 les secteurs primaire et secondaire dans Individuel - les Etats membres de la CPSOOI C004 0610 2- Evénements commerciaux à Maurice Consultant PY03 4,000.00 Forfait Postériori 08/02/2018 (interprétation) Individuel - C005 0610 Consultant 2- Programme régional d’observateurs 35,000.00 Forfait Postériori 23/08/2018 Individuel PY03 Réf. Description des missions Coût Approche/Méthode de Revue de la Date prévue Commentaires No. estimatif sélection Banque (à de (en USD) priori / à soumission posteriori) des propositions - C006 0610 2- Session de la CPSOOI et réunion du Consultant PY03 Comité de pilotage régional de SWIO- 6,000.00 Forfait Postériori 20/02/2018 Individuel - Fish1 (interprétation) C007 0610 2- Réunion du Groupe de travail sur la Consultant PY03 collaboration et la coopération dans les 9,000.00 Forfait Postériori 11/01/2018 Individuel - pêcheries de thon (interprétation) C008 0610 Activité de consultant pour l’élaboration 2- de lignes directrices relatives à Consultant PY03 40,000.00 Forfait Postériori 19/10/2018 l’évaluation de plans de gestion des Individuel - pêcheries C009 0610 2- Consultant PY03 Rédacteur scientifique 20,000.00 Forfait Postériori 19/10/2018 Individuel - C010 0610 2- Consultant PY03 Consultance (CPSOOI)/ NC 20,000.00 Forfait Postériori 09/082018 Individuel - C011 IV. Activités de renforcement de capacités de l’Agence d’exécution avec calendrier 1. Dans cette section, les activités de renforcement de capacité acceptées (quelques articles pourraient être des recommandations de CPAR) sont énumérées avec le calendrier No. Résultats Coût Durée Date de Commentaires escomptés / estimatif estimative début Description de l’activité PROCUREMENT Eastern Africa : AFCC2/RI-South West Indian Ocean Fisheries Governance and Shared Growth Project 1 PLAN General Information Country: Eastern Africa Bank’s Approval Date of the Original Procurement Plan: 2018-06-25 2021-06-01 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P132123 GPN Date: Project Name: AFCC2/RI-South West Indian Ocean Fisheries Governance and Shared Growth Project 1 Loan / Credit No: IDA / H9950 Indian Ocean Commission Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 06102-PY03-G001 / Acquisition d'équipement des Component 1. Enhanced Request for Single Stage - One IDA / H9950 Post Limited 15,000.00 0.00 Canceled 2018-08-12 2018-07-18 2018-10-17 2019-04-15 bureaux de la CPSOOI à regional collaboration Quotations Envelope Maputo (vidéoconférence) SWIO1-PY05-G002 / Component 4. Project Request for Single Stage - One Purchase of laptop for PMU's IDA / H9950 management and Post Limited 2,500.00 1,555.01 Signed 2020-11-08 2020-10-28 2021-01-03 2020-12-02 2021-02-22 Quotations Envelope Office -(M&E assistant) coordination SWIO1-PY05-G001 / Component 4. Project Pending Request for Single Stage - One Purchase of laptops for IDA / H9950 management and Post Limited 7,500.00 0.00 Implementati 2020-11-08 2021-01-03 2021-02-22 Quotations Envelope SWIOFC Secretariat coordination on SWIO1-PY06-G001 / Component 4. Project Pending Request for Single Stage - One Purchase of a printer for the IDA / H9950 management and Post Limited 4,000.00 0.00 Implementati 2021-07-03 2021-08-07 2021-08-22 Quotations Envelope PIU coordination on NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 06102-PY03-NC03 / Location de sallle de conférence pour la Réunion Component 1. Enhanced Request for Single Stage - One IDA / H9950 Post Limited 2,500.00 13,768.03 Signed 2018-07-07 2018-06-26 2018-09-11 2018-07-31 2019-03-10 du Groupe spécial sur les regional collaboration Quotations Envelope conditions minimales d'accès (réunion scientifique) 06102-PY03-NC08 / Location de sallle de conférence pour la Session de Component 1. Enhanced Request for Single Stage - One IDA / H9950 Post Limited 10,400.00 4,780.40 Signed 2018-07-07 2018-08-01 2018-09-11 2018-10-02 2019-03-10 la CPSOOI et réunion du regional collaboration Quotations Envelope Comité de pilotage régional de SWIO-Fish1 à Cape Town 06102-PY03-NC09 / Location de salle de réunion Under pour la réunion du Groupe de Component 1. Enhanced Request for Single Stage - One IDA / H9950 Post Limited 10,840.00 13,768.03 Implementati 2018-07-07 2018-06-26 2018-09-11 2019-03-10 travail sur la collaboration et regional collaboration Quotations Envelope on la coopération dans les pêcheries de thon 06102-PY03-NC01 / Location de salle de conférence pour la Atelier sur les pratiques optimales et les Component 1. Enhanced Request for Single Stage - One IDA / H9950 Post Limited 15,000.00 25,832.42 Signed 2018-02-03 2018-01-05 2018-04-10 2018-02-09 2018-10-07 leçons d'expérience - Atelier regional collaboration Quotations Envelope de discussion sur des articles de publications scientifiques (Seychelles) 06102-PY03-NC04 / Location de salle de Component 1. Enhanced Request for Single Stage - One conférence pour la réunion du IDA / H9950 Post Limited 2,500.00 10,904.49 Signed 2018-02-17 2018-01-30 2018-04-24 2018-02-05 2018-10-21 regional collaboration Quotations Envelope programme régional d'observateurs (Cape Town) 06102-PY03-NC07 / Location de sallle de conférence pour la Atelier Component 1. Enhanced Request for Single Stage - One IDA / H9950 Post Limited 10,000.00 5,844.98 Signed 2018-06-12 2018-08-02 2018-08-17 2018-08-03 2019-02-13 pour l'Afrique orientale, regional collaboration Quotations Envelope l'Afrique australe et l'océan Indien (AO-AA-OI) - SADC 06102-PY03-NC10 / Location de salle de Réunion Component 1. Enhanced Request for Single Stage - One IDA / H9950 Post Limited 6,000.00 13,756.99 Signed 2018-01-23 2018-01-08 2018-03-30 2018-01-24 2018-09-26 du Comité scientifique de la regional collaboration Quotations Envelope CPSOOI SWIO1-PY04-NC02 / Location salle de réunion pour Component 1. Enhanced Request for Single Stage - One l'atelier pour l'Afrique de l'Est, IDA / H9950 Post Limited 6,000.00 7,140.11 Signed 2019-01-29 2019-03-21 2019-03-26 2019-06-06 2019-04-02 regional collaboration Quotations Envelope l'Afrique australe et l'océan Indien (EA-SA-IO)-SADC SWIO1-PY04-NC03 / Location salle de réunion pour Component 1. Enhanced Request for Single Stage - One la session de la CPSOOI et IDA / H9950 Post Limited 3,000.00 60,502.72 Signed 2019-08-06 2019-01-28 2019-10-01 2019-06-06 2019-10-08 regional collaboration Quotations Envelope comité de pilotage SWIOFish1: Octobre 2019 (Maldives) Page 1 SWIO1-PY04-NC05 / Under Location salle de réunion du Component 1. Enhanced Request for Single Stage - One IDA / H9950 Post Limited 3,000.00 0.00 Implementati 2019-01-22 2019-04-23 2019-03-19 2019-03-26 Comité scientifique du regional collaboration Quotations Envelope on SWIOFC (Maputo) SWIO1-PY04-NC06 / Location salle de réunion du Component 1. Enhanced Request for Single Stage - One groupe de travail SWIOFC sur IDA / H9950 Post Limited 3,000.00 12,875.00 Signed 2019-07-08 2019-01-31 2019-09-02 2019-02-26 2019-09-09 regional collaboration Quotations Envelope l'évaluation des stocks de poissons pélagiques (Kenya) SWIO1-PY05-NC06 / National Workshop on legal Component 1. Enhanced IDA / H9950 Post Direct Selection Direct 100,243.00 100,243.00 Signed 2020-03-03 2020-03-02 2020-03-08 2020-02-26 2020-04-12 2020-03-11 2020-04-16 and institutional support to regional collaboration Somalia in Mogadishu 06102-PY03-NC11 / Location de sallle de conférence pour la réunion du Component 1. Enhanced Request for Single Stage - One IDA / H9950 Post Limited 7,000.00 0.00 Canceled 2018-10-12 2018-12-07 2019-06-05 Groupe de travail de la regional collaboration Quotations Envelope CPSOOI sur l'évaluation des stocks de poissons pélagiques (Maputo) SWIO1-PY04-NC07 / Component 1. Enhanced Request for Single Stage - One Location salle de réunion pour IDA / H9950 Post Limited 1,410.00 0.00 Canceled 2019-07-16 2019-09-10 2019-09-20 regional collaboration Quotations Envelope le Bureau de la CPSOOI SWIO1-PY04-NC01 / Location salle de réunion pour Component 1. Enhanced Request for Single Stage - One IDA / H9950 Post Limited 5,000.00 0.00 Canceled 2019-04-06 2019-06-01 2019-06-08 la réunion technique sur regional collaboration Quotations Envelope l'accord cadre SWIO1-PY05-NC05 / Organisation and logistic for a Under Component 1. Enhanced Request for Single Stage - One national workshop on IDA / H9950 Post Limited 100,243.00 0.00 Implementati 2020-07-27 2020-02-26 2020-09-21 2020-09-26 regional collaboration Quotations Envelope proposed fisheries bill for on Somalia SWIO1-PY05-NC02 / Location salle de réunion pour le "Regional Technical meeting on Framework Component 1. Enhanced Request for Single Stage - One IDA / H9950 Post Limited 5,500.00 0.00 Canceled 2020-03-30 2020-05-25 2020-06-09 Agreement/ Sustainable regional collaboration Quotations Envelope Financing Mechanism and SWIOFC" et "SWIOFC Scientific Committee Meeting" (Madagascar) SWIO1-PY05-NC04 / Location salle de réunion pour le "SWIOFC Session & RCS" et Component 1. Enhanced Request for Single Stage - One IDA / H9950 Post Limited 6,500.00 0.00 Canceled 2020-07-20 2020-09-14 2020-09-22 "Working Party on regional collaboration Quotations Envelope Collaboration and Cooperation on Tuna Fisheries" (Tanzania) SWIO1-PY05-NC01 / Location salle de réunion pour Component 1. Enhanced Request for Single Stage - One le Meeting on SWIOFC IDA / H9950 Post Limited 5,000.00 0.00 Canceled 2020-03-05 2020-04-30 2020-05-08 regional collaboration Quotations Envelope Working Group on Demersal Fish Stock Assessment (Cape Town) SWIO1-PY05-NC03 / Location salle de réunion pour le "Workshop for Eastern Component 1. Enhanced Request for Single Stage - One IDA / H9950 Post Limited 1,500.00 0.00 Canceled 2020-06-07 2020-08-02 2020-08-09 Africa, Southern Africa and regional collaboration Quotations Envelope Indian Ocean (EA-SA-IO) - SADC" (Johannesburg) SWIO1-PY04-NC04 / Location de salle de réunion du Groupe de travail sur la Component 1. Enhanced Request for Single Stage - One IDA / H9950 Post Limited 3,000.00 0.00 Canceled 2019-07-09 2019-09-03 2019-09-10 collaboration et la coopération regional collaboration Quotations Envelope dans le secteur de la pêche thonière(Johannesburg) SWIO1-PY05-NC07 / Component 4. Project Recruitment of a movie maker IDA / H9950 management and Post Direct Selection Direct 60,000.00 0.00 Canceled 2020-10-30 2020-11-04 2020-12-09 2021-01-28 for SWIOFish1 project under coordination item communication SWIO1-PY06-NC01 / Pending Component 1. Enhanced Request for Single Stage - One translation of "SWIOFsih1 / IDA / H9950 Post Limited 4,000.00 0.00 Implementati 2021-06-02 2021-07-28 2021-08-12 regional collaboration Quotations Envelope SWIOFC documents" on CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SWIO1-PY05-C014 / "Interpretation services for -Workshop for Eastern Africa, Southern Africa and Indian Consultant Component 1. Enhanced Under Ocean (EA-SA-IO) -SADC IDA / H9950 Post Qualification Open - International 7,800.00 0.00 2020-10-12 2020-10-09 2020-10-26 2020-11-24 2020-12-09 2021-01-13 2021-03-19 regional collaboration Implementation - SADC webinar on FiTI and Selection SWIOFC Scientific and technical meetings besides WPCCTF meeting" SWIO1-PY06-C004 / Consultant for Assessment Consultant Component 1. Enhanced and support for the IDA / H9950 Post Qualification Open - International 90,000.00 158,120.00 Signed 2020-12-15 2020-12-15 2021-01-05 2021-01-04 2021-02-18 2021-02-03 2021-03-20 2021-03-22 2021-04-24 2021-03-30 2021-08-22 regional collaboration implementation of MTC Selection guidelines SWIO1-PY06-C002 / Recruitment of a consultant for the Coordination of "the Component 1. Enhanced Non-Profit IDA / H9950 Post Direct 25,500.00 0.00 Canceled 2020-12-15 2020-12-14 2021-02-08 2021-03-15 2021-08-12 development of a catalogue regional collaboration Organizations on Fishing Gears and Methods in the SWIO region" Page 2 SWIO1-PY06-C006 / Consultant Component 1. Enhanced Under Interpretation service for the IDA / H9950 Post Qualification Open - National 14,766.00 0.00 2021-05-28 2021-06-21 2021-06-12 2021-06-24 2021-06-22 2021-07-07 2021-07-22 2021-08-31 regional collaboration Implementation SWIOFC meetings -July 2021 Selection INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Individual MU-IOC-63361-CS-INDV / Component 1. Enhanced IDA / H9950 Post Consultant Limited 20,000.00 20,000.00 Signed 2018-03-16 2018-03-16 2018-03-26 2018-03-20 2018-05-10 2018-06-04 2018-06-10 2018-06-15 2018-09-08 Consultance (CPSOOI)/ NC regional collaboration Selection MU-IOC-62347-CS-INDV / Consultance sur l'analyse Individual Component 1. Enhanced coûts et bénéfices(SWIOFish 1 IDA / H9950 Post Consultant Limited 15,000.00 15,000.00 Signed 2018-04-20 2018-04-20 2018-04-25 2018-05-03 2018-05-30 2018-07-06 2018-07-04 2018-07-31 2018-08-13 regional collaboration framework agreement Selection merging with Fisheries Accord) 06102-PY03-C004 / Etude de consultant sur la contribution du secteur des Individual Component 1. Enhanced pêches au PIB cou-vrant les IDA / H9950 Post Consultant Open 40,000.00 40,040.00 Signed 2018-09-07 2018-09-13 2018-11-02 2019-01-08 2018-11-23 2019-02-01 2018-12-28 2019-02-04 2019-06-26 regional collaboration secteurs primaire et Selection secondaire dans les Etats membres de la CPSOOI Individual 06102-PY03-C010 / Component 1. Enhanced IDA / H9950 Post Consultant Open 20,000.00 18,025.00 Signed 2018-09-07 2018-09-13 2018-10-26 2019-02-26 2018-11-16 2019-08-12 2018-12-21 2019-08-19 2019-06-19 Rédacteur scientifique regional collaboration Selection 06102-PY03-C013 / Project Component 4. Project Individual Coordinateur (salary of the IDA / H9950 management and Post Consultant Direct 144,000.00 302,100.00 Signed 2018-10-02 2018-10-28 2018-10-12 2018-10-28 2018-11-02 2018-12-14 2018-12-07 2018-12-20 2019-06-05 Coordinator SWIOFish1) coordination Selection 06102-PY03-C014 / Component 4. Project Individual Procurement spécialist (salary IDA / H9950 management and Post Consultant Direct 28,632.00 33,035.00 Signed 2018-08-31 2018-08-31 2018-09-10 2018-08-31 2018-10-01 2018-08-31 2018-11-05 2018-08-31 2019-05-04 of the procurement specialist) coordination Selection 06102-PY03-C015 / Component 4. Project Individual Accout/Administratice IDA / H9950 management and Post Consultant Direct 9,530.00 28,590.00 Signed 2018-08-31 2018-08-28 2018-09-10 2018-08-30 2018-10-01 2018-09-25 2018-11-05 2018-09-28 2019-05-04 assistant (Salary of the coordination Selection account assistant) 06102-PY03-C006 / Service Individual d'interprétation pour la Component 1. Enhanced IDA / H9950 Post Consultant Limited 35,000.00 7,060.00 Signed 2018-02-01 2018-01-26 2018-02-16 2018-01-26 2018-03-23 2018-01-31 2018-04-27 2018-02-05 2018-10-24 réunion du programme regional collaboration Selection régional des observateurs SWIO1-PY04-C03 / Consultance pour l'assistance Individual Component 1. Enhanced spéciale à la Somalie en IDA / H9950 Post Consultant Open 60,000.00 0.00 Canceled 2019-01-31 2019-03-21 2019-04-11 2019-05-16 2019-11-12 regional collaboration matière de développement Selection juridique et institutionnel SWIO1-PY04-C06 / Selection of an International Consultant Component 1. Enhanced for Special assistance to IDA / H9950 Post Direct Selection Direct 40,000.00 0.00 Canceled 2019-04-05 2019-04-12 2019-04-15 2019-06-19 2019-09-17 regional collaboration Somalia on legal and institutional development SWIO1-PY04-C07 / Selection of a National Consultant for Individual Component 1. Enhanced Special assistance to Somalia IDA / H9950 Post Consultant Limited 20,000.00 34,294.16 Signed 2019-04-15 2019-05-23 2019-04-20 2019-10-11 2019-05-11 2019-10-16 2019-06-15 2019-11-21 2019-08-14 regional collaboration on legal and institutional Selection development. SWIO1-PY04-C08 / Recruitment of an Individual International Consultant for Component 1. Enhanced IDA / H9950 Post Consultant Limited 40,000.00 34,790.00 Signed 2019-05-10 2019-05-08 2019-05-15 2019-05-23 2019-06-05 2019-10-16 2019-07-10 2019-11-21 2019-09-08 Special assistance to Somalia regional collaboration Selection on legal and institutional development . SWIO1-PY04-C009 / Consultancy on Sustainable Individual Component 1. Enhanced SWIOFC Financing Mechanism IDA / H9950 Post Consultant Open 20,000.00 20,000.00 Signed 2019-05-28 2019-05-23 2019-07-16 2019-06-28 2019-08-06 2019-07-02 2019-09-10 2019-07-09 2019-11-09 regional collaboration and Policy Brief on possible Selection FFA SWIO1-PY05-C004 / Individual Component 1. Enhanced Consultant pour la redaction IDA / H9950 Post Consultant Direct 25,000.00 19,075.00 Signed 2020-03-19 2020-10-23 2020-03-29 2020-10-23 2020-04-19 2020-10-29 2020-05-24 2020-11-06 2021-03-20 regional collaboration scientifique Selection SWIO1-PY05-C005 / Consultant pour les traductions des documents de Individual Component 1. Enhanced Pending "Consultancy reports and IDA / H9950 Post Consultant Limited 10,000.00 0.00 2020-07-02 2020-07-07 2020-07-28 2020-09-01 2020-11-30 regional collaboration Implementation SWIOFC Scientific and Selection technical meetings besides WPCCTF meeting" SWIO1-PY05-C008 / Consultant pour Component 4. Project Individual "Administrative & Financial IDA / H9950 management and Post Consultant Direct 59,700.00 59,697.00 Signed 2020-05-13 2020-06-24 2020-05-23 2020-06-29 2020-06-13 2020-06-30 2020-07-18 2020-07-01 2021-09-11 Manager for SWIOFish1 coordination Selection Regional Project" SWIO1-PY04-C02 / Individual Consultance sur la Component 1. Enhanced IDA / H9950 Post Consultant Open 20,000.00 0.00 Canceled 2019-02-28 2020-01-09 2019-04-18 2019-05-09 2019-06-13 2019-08-12 transparence de l'industrie de regional collaboration Selection la pêche SWIO1-PY05-C009 / Individual Component 1. Enhanced Under Consultant Individuel pour la IDA / H9950 Post Consultant Limited 60,000.00 0.00 2020-01-07 2020-01-31 2020-01-12 2020-02-02 2020-03-08 2020-09-04 regional collaboration Implementation transparence de la Peche (FiTI) Selection Page 3 06102-PY03-C009 / Activité de consultant pour Individual l'élaboration de lignes Component 1. Enhanced IDA / H9950 Post Consultant Open 40,000.00 0.00 Canceled 2018-09-07 2018-09-13 2018-10-26 2018-11-16 2018-12-21 2019-06-19 directrices relatives à regional collaboration Selection l'évaluation de plans de gestion des pêcheries Component 4. Project Individual SWIO1-PY04-C005 / Aide IDA / H9950 management and Post Consultant Direct 20,000.00 0.00 Canceled 2019-06-20 2019-06-30 2019-07-21 2019-08-25 2020-08-24 comptable/administrative coordination Selection SWIO1-PY05-C013 / Consultant -Final Evaluation Component 4. Project Individual Report of the First South West IDA / H9950 management and Post Consultant Limited 50,000.00 38,000.00 Signed 2020-10-30 2020-12-28 2020-11-04 2021-01-11 2020-11-25 2021-03-01 2020-12-30 2021-03-01 2021-03-10 Indian Ocean Fisheries coordination Selection Governance and Shared Growth Project (SWIOFish1) SWIO1-PY05-C001 / Service d'interpretation pour deux Individual Component 1. Enhanced reunion a Madagascar IDA / H9950 Post Consultant Limited 12,500.00 0.00 Canceled 2020-03-20 2020-03-25 2020-04-15 2020-05-20 2020-05-22 regional collaboration WPCCTF et SWIOFC scientific Selection committee meeting SWIO1-PY05-C002 / Service d'interpretation pour la Individual réunion "SWIOFC Session & Component 1. Enhanced IDA / H9950 Post Consultant Limited 13,000.00 0.00 Canceled 2020-07-02 2020-07-07 2020-07-28 2020-09-01 2020-09-09 RCS" et "Working Party on regional collaboration Selection Collaboration and Cooperation on Tuna Fisheries" (Tanzania) SWIO1-PY05-C007 / Consultant pour l' Individual "Establishment of the Component 1. Enhanced IDA / H9950 Post Consultant Limited 20,000.00 0.00 Canceled 2020-05-06 2020-05-11 2020-06-01 2020-07-06 2020-10-04 mechanism for financing regional collaboration Selection agreements, accounts, operations" SWIO1-PY05-C015 / Consultant for a case study on Component 1. Enhanced IDA / H9950 Post Direct Selection Direct 15,000.00 19,250.00 Signed 2020-11-05 2020-11-12 2020-11-15 2020-11-16 2021-01-19 2021-01-15 2021-03-20 Fisheries Transparency regional collaboration Initiative for Madagascar SWIO1-PY05-C016 / IC to complete assignment for Special assistance to Somalia on legal and institutional development : Finalization of Component 1. Enhanced draft Bill and Explanatory IDA / H9950 Post Direct Selection Direct 30,000.00 22,500.00 Signed 2020-11-15 2020-11-12 2020-11-25 2020-11-19 2021-01-29 2020-11-24 2021-03-30 regional collaboration Notes and review of framework for Regulations ii) Preparation of Draft Regulations and Explanatory Notes, SWIO1-PY05-C006 / Consultant- Project Individual Component 1. Enhanced coordinator for the IDA / H9950 Post Consultant Limited 25,500.00 0.00 Canceled 2020-06-22 2020-06-15 2020-06-27 2020-07-18 2020-08-22 2021-02-18 regional collaboration development of a catalogue Selection on fishing gear SWIO1-PY05-C012 / Consultancy for horizontal harmonization of foreign Individual fishing licensing in the Component 1. Enhanced IDA / H9950 Post Consultant Limited 30,000.00 0.00 Canceled 2020-10-15 2020-10-20 2020-11-10 2020-12-15 2021-01-24 SWIOFC region in order to regional collaboration Selection implement MCS related Articles of the Voluntary MTC guidelines SWIO1-PY05-C010 / Consultant - mainland Individual Component 1. Enhanced /SWIOFC States for the IDA / H9950 Post Consultant Limited 31,725.00 0.00 Canceled 2020-06-22 2020-06-15 2020-06-27 2020-07-18 2020-08-22 2020-08-23 regional collaboration development of a catalogue Selection on fishing gears and methods SWIO1-PY05-C011 / Consultant Islands /SWIOFC Individual Component 1. Enhanced States for the development of IDA / H9950 Post Consultant Limited 31,725.00 0.00 Canceled 2020-06-22 2020-06-15 2020-06-27 2020-07-18 2020-08-22 2021-02-18 regional collaboration a catalogue on fishing gears Selection and methods SWIO1-PY04-C004 / Component 4. Project Individual Assistant en passation de IDA / H9950 management and Post Consultant Direct 29,900.00 0.00 Canceled 2019-09-11 2019-09-21 2019-10-12 2019-11-16 2020-11-15 Marché coordination Selection SWIO1-PY06-C008 / Graphic/designer consultant for regional Individual Component 1. Enhanced Pending visibility/communication IDA / H9950 Post Consultant Open 4,000.00 0.00 2021-06-28 2021-07-29 2021-08-02 2021-08-14 2021-08-29 regional collaboration Implementation (press, internet) on project Selection results/outputs and benefits accrued to SWIOFC members SWIO1-PY06-C007 / Individual Consultant for Technical and Component 1. Enhanced Pending IDA / H9950 Post Consultant Direct 18,000.00 0.00 2021-06-30 2021-07-10 2021-07-22 2021-07-31 2021-08-30 SCIENTIFIC EDITOR for regional collaboration Implementation Selection SWIOFC meetings Page 4 PROCUREMENT PLAN Country: Kingdom of Cambodia Full Project Name: ROAD CONNECTIVITY IMPROVMENT PROJECT Total Finance ($): USD 100 (US$M) Project Number: P169930 Project Implementation agency: MINISTRY OF PUBLIC WORKS AND TRANSPORT (MPWT) and MINISTRY RURAL DEVELOPMENT (MRD) Date of the Procurement Plan: 01 May 2020 Period covered by this Procurement Plan: 01 May 2020 to 01 November 2021 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Government Standard Operating Procedures and Procurement Manual issued under Sub-Decree 74 (dated May 22, 2012), which is issued pursuant to Article 3 of the Kingdom of Cambodia’s Law on Public Procurement dated January 14, 2012. In addition to the provisions contained in the PM, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. i. Procurement shall be opened to eligible firms from any country. 1 ii. The request for bids/request for proposals document shall require that bidders/proposers submitting bids/proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, without limitation the World Bank’s right to sanction and the World Bank’s inspection and audit rights as per attached confirming application of, and compliance with, the World Bank’s Anti-Corruption Guidelines, including format. iii. Each project shall put in place an effective complaints review system that includes review by the implementing agency and subsequent review by another party not involved in the procurement process, if not satisfied with the review of the implementing agency. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second-Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). “Not Applicable” Other Relevant Procurement Information. The IA for this project has enough familiar experience with DP and WB funded procurement activities, and procurement capacity in carrying out the similar procurement activities under this project. 2 IMPLEMENTATATION OF THE ROAD CONNECTIVITY IMPROVMENT PROJECT (INTITIAL 18 MONTHS) No. Description Estimat Packa Prior Procurem Selection Evaluation Planned Comment ed ges Bank ent Methods Method Contract Cost Oversig Approach Start (US$) ht / Date in Competiti Million on Component 1- MPWT 48.67 Civil Works 44 1 C1-CW Package 1: NR7 (31km) 7.00 1 Prior Open Internation Most May 2021 Improvement/Periodical Internation al Advantageous Maintenance and Routine al RFB Bid Maintenance 2 C1-CW Package 2: NR73 (50km) 14.00 1 Prior Open Internation Most June 2021 Improvement/Periodical Internation al Advantageous Maintenance and Routine al RFB Bid Maintenance 3 C1-CW Package 3: PR377 & 23.00 1 Prior Open Internation Most Nov 2021 PR377A (51km) Internation al Advantageous Improvement/Periodical al RFB Bid Maintenance and Routine Maintenance Goods 0.17 4 Office Equipment 0.05 1 Post Open National Lowest Apr 2021 National RFQ Evaluation (Shopping) 5 Vehicles (3 pickup, one van) 0.12 1 Post Open National Lowest Apr 2021 Exclude Tax National RFB Evaluation Consultant Services 4.5 6 Consultant firm for Supervision 3.00 1 Prior Open QCBS Quality and Apr 2021 3 and Implementation Support of Internation Cost National & Provincial Roads al 7 Consultant firm for Road Crash 0.50 1 Post Open QCBS Quality and Dec 2021 Data Update & Capacity Internation Cost Building al 8 Road Safety Awareness & Road 0.30 1 Post Open CQS Quality Jan 2021 safety Assessment of MPWT Internation Project Roads al 9 Environment and Social 0.10 2 Post Open IC Individual Dec 2020 18 months consultant(s) Internation al 10 Technical Assistance on MPWT 0.06 1 Post Open IC Individual Oct 2021 24 months gender Mainstreaming Action National Plans 11 International OPBRS adviser 0.20 1 Post Open IC Individual May 2021 10 months internation (Intermitte al nt) 12 Local Procurement Expert 0.05 1 Post Open IC Individual Oct 2020 18 months National 13 International procurement 0.20 1 Prior Open IC Individual Oct 2020 10 months expert Internation (Intermitte al nt) 14 National Assistant Accountants 0.09 1 Post Open IC Individual Jan 2021 36 months National Component 2: Rural Roads 48.76 Improvement-MRD Civil works 44 1 C2-CW Package 1: Rural roads 23.00 1 Prior Open Internation Most Dec 2021 improvement and maintenance Internation al Advantageous through OPBRC in Kratie al RFB Bid province 2 C2-CW Package 2: Rural roads 11.00 1 Prior Open Internation Most Sep 2021 improvement and maintenance Internation al Advantageous through OPBRC in Kampong al RFB Bid Cham province 3 C2-CW Package 3: Rural roads 10.00 1 Prior Open Internation Most July 2021 improvement and maintenance Internation al Advantageous through OPBRC in Tboung al RFB Bid 4 Khmum Province Goods 0.26 4 Office Equipment 0.04 1 Post Open National Lowest Feb 2021 National RFQ Evaluation (Shopping) 5 IT Software 0.01 1 Post Open National Lowest Feb 2021 National RFQ Evaluation (Shopping) 6 Vehicles (6 pickup, 1 SUV) 0.21 1 Post Open National Lowest Mar 2021 National RFB Evaluation Consultant Services 4.50 7 Design and Supervision Services 3.00 1 Prior Open QCBS Quality and Dec 2020 for Rural Roads Internation Cost al 8 Consultant firm for Rural Roads 0.50 1 Post Open QCBS Quality and Aug 2021 Accessibility Financing Strategy Internation Cost and Support in al operationalization of the Rural Roads Asset Management Systems 9 Rural Roads Safety awareness 0.30 1 Post Open CQS Quality Feb 2021 activities and roads safety Internation assessment of project roads al 10 Safe transportation services in 0.10 1 Post Open CQS Quality May 2021 rural areas options study National 11 International Procurement 0.24 1 Post Open IC Individual Oct 2020 12 months Consultant Internation (intermitte al nt) 12 National Procurement 0.09 1 Post Open IC Individual Sep 2020 36 months Consultant National 13 Financial Management 0.09 1 Post Open IC Individual Jan 2021 36 months Consultants National 14 Monitoring & Evaluation 0.09 1 Post Open IC Individual Jan 2021 36 months Consultants National 15 Environmental and Social 0.09 1 Post Open IC Individual Jan 2021 36 months consultants National Total amount for MPWT and MRD 97.43 5 PROCUREMENT Cambodia : Cambodia Road Connectivity Improvement PLAN General Information Country: Cambodia Bank’s Approval Date of the Original Procurement Plan: 2020-08-19 2021-05-24 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P169930 GPN Date: 2020-09-07 Project Name: Cambodia Road Connectivity Improvement Loan / Credit No: IDA / 67670 M Executing Agency(ies): inistry of Rural Development WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MRD-RCIP-FMS-GS5 / supply of one set of the latest version Component 2: Rural Roads Request for Single Stage - One (4 Users) of Sage 50 Premium IDA / 67670 Post Open - National 10,000.00 6,000.00 Signed 2020-11-28 2021-02-16 2021-01-23 2021-03-17 2022-01-23 Improvement Quotations Envelope accounting and related services. MRD-RCIP-SUV-GS7 / MRD plan to procure for 1 SUV vehicle through the direct contract with the UN agency Under Component 2: Rural Roads UN Agencies for the Road Connectivity IDA / 67670 Post Direct 40,310.00 0.00 Implementati 2021-02-08 2021-02-01 2021-02-13 2021-03-20 2021-09-16 Improvement (Direct) Improvement Project_RCIP. on The proposed cost is included the Manufacturing cost, UNOPS fee and Freight. MRD-RCIP-NCB-GS6 / Supply of 6 Units of Pickup Truck Vehicles. The procurement Under Component 2: Rural Roads Single Stage - One will conducted through NCB IDA / 67670 Post Request for Bids Open - National 180,000.00 0.00 Implementati 2021-02-15 2021-02-01 2021-02-20 2021-04-03 2021-05-03 2021-06-07 2021-12-04 Improvement Envelope Procedure specified in the on RGC's Procurement Manual for Externally Financed Projects. Pending MRD-RCIP-RFQ-GS11 / Component 2: Rural Roads Request for Single Stage - One IDA / 67670 Post Open - National 30,000.00 0.00 Implementati 2021-06-08 2021-08-03 2022-01-30 Office Equipment Supply Improvement Quotations Envelope on Pending MRD-RCIP-RFQ-GS12 / Component 2: Rural Roads Request for Single Stage - One IDA / 67670 Post Open - National 10,000.00 0.00 Implementati 2021-06-02 2021-07-21 2022-01-17 Office Furniture Supply Improvement Quotations Envelope on NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MRD-RCIP-DSS-CS4 / The Consulting Firm will be responsible for confirmation of selected roads, design of climate resilient road Component 2: Rural Roads Quality And Cost- Under IDA / 67670 Prior Open - International 3,000,000.00 0.00 2020-10-22 2020-12-07 2020-11-12 2021-01-14 2020-12-26 2021-05-27 2021-01-23 2021-02-22 2021-03-29 2021-05-03 2022-05-03 rehabilitation, civil works Improvement Based Selection Implementation supervision, monitoring and contract administration regardings safeguard implementation. MRD-RCIP-RSA-CQS9 / Rural Road Safety Awareness activities and Roads safety assessment of project roads. Consultant Component 2: Rural Roads Pending MRD plans to procure a IDA / 67670 Post Qualification Open - International 300,000.00 0.00 2021-04-22 2021-05-13 2021-06-26 2021-07-26 2021-08-30 2022-02-26 Improvement Implementation consulting firm to perform Selection task of Rural Roads Safety awareness activities and roads safety assessment of RCIP. INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MRD-RCIP-NPC-CS1 / NPC is Individual an individual consultant. The Component 2: Rural Roads IDA / 67670 Post Consultant Open 90,000.00 115,920.00 Signed 2020-08-11 2020-09-01 2020-09-13 2020-11-17 2020-09-27 2020-11-25 2020-10-25 2020-12-28 2022-10-15 contract duration is for 36 Improvement Selection months full time/intermittent. MRD-RCIP-IPC-CS2 / IPC is Individual contracted for 12 months Component 2: Rural Roads IDA / 67670 Post Consultant Open 240,000.00 240,000.00 Signed 2020-08-11 2020-11-19 2020-09-29 2021-02-01 2020-10-20 2021-02-22 2020-11-24 2021-03-15 2021-08-01 intermittent from the contract Improvement Selection signed date. Page 1 MRD-RCIP-FMC-CS3 / Individual FM specialist will be Individual recruited to work for Component 2: Rural Roads IDA / 67670 Post Consultant Open 90,000.00 2,700.00 Signed 2020-11-17 2020-11-17 2021-01-05 2020-12-30 2021-01-26 2020-12-31 2021-03-02 2021-01-05 2024-02-25 RCIP/MRD for 36 months for Improvement Selection full time/intermittent base from the contract signed date MRD-RCIP-ESC-CS8 / Individual Component 2: Rural Roads Under Environmental and Social IDA / 67670 Post Consultant Open 90,000.00 0.00 2021-03-26 2021-04-08 2021-05-14 2021-06-04 2021-06-25 2024-06-09 Improvement Implementation Consultant Selection MRD-RCIP-MNE-CS10 / Individual Component 2: Rural Roads Pending Monitoring & Evaluation IDA / 67670 Post Consultant Open 90,000.00 0.00 2021-06-17 2021-08-05 2021-08-26 2021-09-30 2024-09-14 Improvement Implementation Consultant (M&E) Selection Page 2 3 MONTHS PROCUREMENT PLAN Project information: P173820 - Kenya Covid-19 Emergency Response Project Implementation agency: Ministry of Health and Kenya Medical Supplies Agency Date of the Procurement Plan: March 25 2021 Period covered by this Procurement Plan: Three months Preamble In accordance with paragraph 5.9 of the World Bank’s Procurement Regulations for IPF Borrowers for Goods, Works, Non-Consulting and Consulting Services, dated July 1, 2016 (revised in November 2017 and August 2018) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: Paragraph 5.3 of the Procurement Regulations will not apply. When approaching the national market, the country’s own procurement procedures shall not be used due to restrictions on eligibility of otherwise eligible firms to participate in NCB. The Regulations will apply. However, the Borrower may use its own procurement arrangements as set forth in the Public Procurement and Disposal Act, 2003 Request for Quotation such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions: In accordance with paragraph 5.3 of the Procurement Regulations, the request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. The form of the Letter of Acceptance is attached in Appendix 1. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables: Not Applicable. Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables: Not Applicable. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods : Applicable for those contracts identified in the Procurement Plan tables Works: applicable for those contracts identified in the Procurement Plan tables This being an emergency project, increased thresholds for Requests for Quotations (RFQ) to US$1 million for goods and services and US$5 million for works; Other Relevant Procurement Information:- Prior Procurement Arrangements: The Procurement Arrangements as indicated in the below table and within the thresholds indicated in the below tables will be used. The thresholds for the Bank’s prior review requirements are also provided in the table below: Table: Prior review Thresholds High Procurement Type Risk Works 5.0 Goods, It & Non-Consulting 1.5 Services Consultants (Firms) 0.5 Individual Consultants 0.2 Prequalification. Not expected for any works or goods packages in the procurement plan. Proposed Procedures for CDD Components: Applicable Reference to (if any) Project Operational/Procurement Manual: the CHERP team will prepare a Procurement manual, which will also be part of the Project Implementation Manual. Any Other Special Procurement Arrangements: None Procurement Packages/PLAN with Procurement Arrangements and Time Schedule: as per the Table below: Appendix 1 Letter of Acceptance of the World Bank’s Anti-Corruption Guidelines and Sanctions Framework Date: Invitation of Bids/Proposals No.__________ To: ___________________________________________________________________________ We, along with our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not) consultants and personnel, acknowledge and agree to abide by the World Bank’s policy regarding Fraud and Corruption (corrupt, fraudulent, collusive, coercive, and obstructive practices), as set out and defined in the World Bank’s Anti-Corruption Guidelines1 in connection with the procurement and execution of the contract (in case of award), including any amendments thereto. We declare and warrant that we, along our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not), consultants and personnel, , are not subject to, and are not controlled by any entity or individual that is subject to, a temporary suspension, early temporary suspension, or debarment imposed by a member of the World Bank Group, including, inter alia, a cross-debarment imposed by the World Bank Group as agreed with other international financial institutions (including multilateral development banks), or through the application of a World Bank Group 1Guidelines on Preventing and Combating Fraud and Corruption in Projects Financed by International Bank for Reconstruction and Development Loans and the International Development Agency Credits and Grants, dated October 15, 2006, and revised in January 2011 and July 2016, as they may be revised from time to time. finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement. Further, we are not ineligible under the laws or official regulations of [Insert name of Employer as per bidding document] or pursuant to a decision of the United Nations Security Council. We confirm our understanding of the consequences of not complying with the World Bank’s Anti-Corruption Guidelines, which may include the following: a. rejection of our Proposal/Bid for award of contract; b. in the case of award, termination of the contract, without prejudice to any other remedy for breach of contract; and c. sanctions, pursuant to the Bank’s Anti-corruption Guidelines and in accordance with its prevailing sanctions policies and procedures as set forth in the Bank’s Sanctions Framework. This may include a public declaration of ineligibility, either indefinitely or for a stated period of time, (i) to be awarded or otherwise benefit from a Bank-financed contract, financially or in any other manner;2 (ii) to be a nominated3 sub- contractor, consultant, manufacturer or supplier, or service provider of an otherwise eligible firm being awarded a Bank-financed contract; and (iii) to receive the proceeds of any loan made by the Bank or otherwise to participate further in the preparation or implementation of any Bank- financed project. We understand that we may be declared ineligible as set out above upon: a. completion of World Bank Group sanctions proceedings according to its prevailing sanctions procedures; b. cross-debarment as agreed with other international financial institutions (including multilateral development banks); 2 For the avoidance of doubt, a sanctioned party’s ineligibility to be awarded a contract shall include, without limitation, (i) applying for pre-qualification, expressing interest in a consultancy, and bidding, either directly or as a nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider, in respect of such contract, and (ii) entering into an addendum or amendment introducing a material modification to any existing contract. 3 A nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider (different names are used depending on the particular bidding document) is one which has been: (i) included by the bidder in its pre-qualification application or bid because it brings specific and critical experience and know-how that allow the bidder to meet the qualification requirements for the particular bid; or (ii) appointed by the Borrower. c. the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement; or d. temporary suspension or early temporary suspension in connection with an ongoing World Bank Group sanctions proceeding. For avoidance of doubt, the foregoing effects of ineligibility do not extend to a sanctioned firm’s or individual’s execution of its ongoing Bank-financed contracts (or its ongoing sub-agreements under such contracts) that are not the subject of a material modification, as determined by the Bank. We shall permit, and shall cause our sub-contractors, sub-consultants, agents (whether declared or not), personnel, consultants, service providers or suppliers, to permit the Bank to inspect4 all accounts, records, and other documents relating to the procurement process and/or contract execution (in the case of award), and to have them audited by auditors appointed by the Bank. We agree to preserve all accounts, records, and other documents (whether in hard copy or electronic format) related to the procurement and execution of the contract. Name of the Bidder/Consultant: Name of the person duly authorized to sign the Bid/Proposal on behalf of the Bidder/Consultant: Title of the person signing the Letter: 4 Inspections in this context are usually investigative (i.e., forensic) in nature: they involve fact-finding activities undertaken by the Bank or persons appointed by the Bank to address specific matters related to investigations/audits, such as evaluating the veracity of an allegation of possible Fraud and Corruption, through the appropriate mechanisms. Such activity includes but is not limited to accessing and examining a firm's or individual's financial records and information, and making copies thereof as relevant; accessing and examining any other documents, data, and information (whether in hard copy or electronic format) deemed relevant for the investigation/audit, and making copies thereof as relevant; interviewing staff and other relevant individuals; performing physical inspections and site visits; and obtaining third-party verification of information. PROCUREMENT Kenya : KENYA COVID-19 HEALTH EMERGENCY RESPONSE PROJECT PLAN General Information Country: Kenya Bank’s Approval Date of the Original Procurement Plan: 2020-04-09 2021-05-24 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P173820 GPN Date: 2020-04-08 Project Name: KENYA COVID-19 HEALTH EMERGENCY RESPONSE PROJECT Loan / Credit No: IDA / 65980 M Executing Agency(ies): inistry of Health WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned KE-MOH-168125-CW-RFQ / Renovations of regional level ambulance command centres in 14 designated high risk Pending countiesthe renovations will Response, capacity building Request for Single Stage - One 2020-12- IDA / 65980 Post Limited 123,900.00 0.00 Implementat 2020-04-22 2020-06-17 be done in the following and training Quotations Envelope 14 ion counties: Nairobi, Mombasa, Kisumu, Kiambu, , Uasingishu, Kajiado, Machakos, Kakamega, Nakuru, Garissa, Wajir, Busia, KE-MOH-168121-CW-RFQ / Construction of 20 bed isolation units in level 5 hospitals in eastern, coast and North eastern regions:These Quarintine, isolation and Request for Single Stage - One 2020-12- IDA / 65980 Post Limited 1,792,000.00 0.00 Canceled 2020-04-22 2020-06-17 units will be constructed in treatement centres Quotations Envelope 14 the following level 5 Hospitals: Machakos, Mombasa, Makueni and Garissa Level 5 Hospitals KE-MOH-168116-CW-RFQ / Construction of 10 bed isolation units in level 4 facilities in western and Quarintine, isolation and Request for Single Stage - One 2020-12- IDA / 65980 Post Limited 1,960,000.00 0.00 Canceled 2020-04-22 2020-06-17 nyanza Regions: in Busia, treatement centres Quotations Envelope 14 Bungoma, Vihiga, Siaya, Migori, Homabay and Nyamira Counties KE-MOH-168118-CW-RFQ / Construction of 10 bed isolation units in 10 level 4 Hospitals in Rift valley region: Quarintine, isolation and Request for Single Stage - One 2020-12- in Bomet,Uasin gishu,West IDA / 65980 Post Limited 2,800,000.00 0.00 Canceled 2020-04-22 2020-06-17 treatement centres Quotations Envelope 14 Pokot, Turkana, Kericho, Narok, Nandi, Baringo, Elgeyo Marakwet and Kajiado Counties KE-MOH-168120-CW-RFQ / Construction of 20 bed isolation unit in level 5 Hospitals in Rift and western Quarintine, isolation and Request for Single Stage - One 2020-12- regions:These units will be IDA / 65980 Post Limited 1,792,000.00 0.00 Canceled 2020-04-22 2020-06-17 treatement centres Quotations Envelope 14 constructed in the following Level 5 hospitals: Kisii, Kisumu,Kakamega and Nakuru level 5 Hospitals KE-MOH-168119-CW-RFQ / Construction of 20 bed isolation units in 3 level 5 hospitals in central region and 3 National Referral Hospitals Quarintine, isolation and Request for Single Stage - One 2020-12- in Nairobi region: in Thika, IDA / 65980 Post Limited 3,136,000.00 0.00 Canceled 2020-04-22 2020-06-17 treatement centres Quotations Envelope 14 Meru ,Nyeri and Embu Level 5 Hospitals and Kenyatta National, Mbagathi IDU and Kenyatta Uni Referral Hospitals KE-MOH-168113-CW-RFQ / Construction of 10 bed isolation units in Level 4 Hospitals in Coast and North Quarintine, isolation and Request for Single Stage - One 2020-12- eastern regions: The units will IDA / 65980 Post Limited 2,240,000.00 0.00 Canceled 2020-04-22 2020-06-17 treatement centres Quotations Envelope 14 be constructed in Kwale, Kilifi, Lamu, Tana river, Wajir, Mandera, Taita Taveta and Kitui Counties KE-MOH-168117-CW-RFQ / Construction of 10 bed isolation units in 10 level 4 Hospitals in Central, Eastern and Nairobi Regions: in Quarintine, isolation and Request for Single Stage - One 2020-12- IDA / 65980 Post Limited 2,800,000.00 0.00 Canceled 2020-04-22 2020-06-17 Marsabit, Isiolo, Samburu, treatement centres Quotations Envelope 14 Laikipia, Nyandarua, Kirinyaga, Tharaka Nithi, Muranga,Kiambu and Nairobi counties. KE-MOH-168126-CW-RFB / Construction of National Response, capacity building Single Stage - One 2021-02- IDA / 65980 Post Request for Bids Open 6,900,000.00 0.00 Canceled 2020-04-17 2020-04-22 2020-06-03 2020-07-03 2020-08-07 Public Health Institute in and training Envelope 03 Nairobi KE-MOH-188956-CW-RFB / Renovation of infectious disease units at Mama Lucy Pending Kibaki Hospital and at Availability of safe blood and Single Stage - One 2021-05- IDA / 65980 Post Request for Bids Open - National 2,600,000.00 0.00 Implementat 2020-08-23 2020-08-28 2020-09-18 2020-10-18 2020-11-22 Kenyatta University teaching blood products Envelope 21 ion and Referal and Research Hospital (KUTRRH) and lady Northey Clinic Page 1 KE-MOH-188962-CW-RFQ / Pending Renovation of 3 regional Availability of safe blood and Request for Single Stage - One 2021-03- IDA / 65980 Post Limited 210,000.00 0.00 Implementat 2020-08-26 2020-09-18 blood centres: Kisii, Embu and blood products Quotations Envelope 17 ion Mombasa blood centres Pending KE-MOH-188964-CW-RFQ / Availability of safe blood and Request for Single Stage - One 2021-02- IDA / 65980 Post Limited 90,000.00 0.00 Implementat 2020-10-16 2020-11-18 Renovation of 6 cold rooms blood products Quotations Envelope 16 ion KE-MOH-196712-CW-RFQ / Proposed Medical Gases Pending Quarintine, isolation and Request for Single Stage - One 2021-03- Installation works at COVID- IDA / 65980 Post Limited 126,000.00 0.00 Implementat 2020-10-21 2020-12-09 treatement centres Quotations Envelope 09 19 Isolation Centre in ion Madalder Level 4 Hospital KE-MOH-196714-CW-RFQ / Proposed Medical Gases Installation works at COVID- Pending Quarintine, isolation and Request for Single Stage - One 2021-04- 19 Isolation Centres in IDA / 65980 Post Limited 235,000.00 0.00 Implementat 2020-11-27 2021-01-15 treatement centres Quotations Envelope 15 Lot 1. Kisumu Level 4 Hospital ion Lot 2. Langalanga Sub-county Hospital in Nakuru County KE-MOH-196704-CW-RFQ / Proposed Medical Gases Installation works at COVID- Pending 19 Isolation Centres: Quarintine, isolation and Request for Single Stage - One 2021-04- IDA / 65980 Post Limited 274,000.00 0.00 Implementat 2020-11-27 2021-01-15 Lot 1. Alupe Sub-County treatement centres Quotations Envelope 15 ion Hospital in Busia County Lot 2. Macalder Level 4 Hospital in Migori County KE-MOH-196713-CW-RFQ / Proposed Medical Gases Installation works at COVID- Pending 19 Isolation Centres: Quarintine, isolation and Request for Single Stage - One 2021-04- IDA / 65980 Post Limited 240,500.00 0.00 Implementat 2020-11-27 2021-01-15 Lot 1. Gede Health Centre in treatement centres Quotations Envelope 15 ion Kilifi County Lot 2. Msambweni Level 4 Hospital in Kwale County KE-MOH-196707-CW-RFQ / Proposed Medical Gases Installation works at COVID- 19 Isolation Centres: Pending Quarintine, isolation and Request for Single Stage - One 2021-04- Lot 1. Mwatate Level 4 IDA / 65980 Post Limited 194,000.00 0.00 Implementat 2020-11-27 2021-01-15 treatement centres Quotations Envelope 15 Hospital in Taita Taveta ion County Lot 2. Kauwi Level 4 Hospital in Kitui County KE-MOH-196711-CW-RFQ / Proposed Medical Gases Installation works at COVID- Pending 19 Isolation Centres: Quarintine, isolation and Request for Single Stage - One 2021-04- IDA / 65980 Post Limited 249,000.00 0.00 Implementat 2020-11-27 2021-01-15 Lot 1. Garissa Referral treatement centres Quotations Envelope 15 ion Hospital Lot 2. Kaimur Isolation Hospital in Mandera County KE-MOH-196710-CW-RFQ / Proposed Medical Gases Installation works at COVID- Pending 19 Isolation Centres: Quarintine, isolation and Request for Single Stage - One 2021-04- IDA / 65980 Post Limited 226,500.00 0.00 Implementat 2020-11-27 2021-01-15 Lot 1. Kangundo Level 4 treatement centres Quotations Envelope 15 ion Hospital in Machakos County Lot 2. Ngong Level 4 Hospital in Kajiado County KE-MOH-196904-CW-RFQ / Proposed Refurbishment of Pending Quarintine, isolation and Request for Single Stage - One 2021-04- Covid-19 Isolation facility at IDA / 65980 Post Limited 550,000.00 0.00 Implementat 2020-11-18 2020-12-30 treatement centres Quotations Envelope 29 Mama Lucy Kibaki Hospital, ion Nairobi County KE-MOH-216886-CW-RFQ / Proposed Renovation works at the Kenyatta University Teaching and Referral Pending Quarintine, isolation and Request for Single Stage - One 2021-06- Hospital to include Interior fit IDA / 65980 Post Limited 350,000.00 0.00 Implementat 2021-02-19 2021-03-24 treatement centres Quotations Envelope 22 outs for the Infectious Disease ion Unit (IDU) and Inclusion of Negative Pressure system at the IDU KE-MOH-227278-NC-DIR / Refurbishment of the Pending Community discussion and Request for Single Stage - One 2021-11- proposed 719 Call Centre IDA / 65980 Post Limited 150,000.00 0.00 Implementat 2021-04-11 2021-05-26 information outreach Quotations Envelope 22 Room in the Ministry of ion Health. KE-MOH-233744-CW-RFQ / Proposed Medical Gas Installation Works at Marimani Outreach Hospital - Request for Mombasa County (Lot Quotations - Small Pending Medical supplies and Request for Single Stage - One 2021-07- 1),Mtongwe Outreach hospital- IDA / 65980 Post Limited Works 432,000.00 0.00 Implementat 2021-05-17 2021-06-30 equipment Quotations Envelope 14 Mombasa County (Lot 2).Port (Emergency) SPD - ion Reitz Subcounty Hospital- Competitive Mombasa County (Lot 3) and Moi Voi Hospital -Taita Taveta county (Lot 4) KE-MOH-233865-CW-RFQ / Proposed Medical Gas Request for Installation works at Quotations - Small Pending Medical supplies and Request for Single Stage - One 2021-08- Chepyakwai Health Centre - IDA / 65980 Post Limited Works 160,000.00 0.00 Implementat 2021-05-19 2021-06-28 equipment Quotations Envelope 20 Uasin Gishu County (Lot 1) (Emergency) SPD - ion and Kamalel Isolation Centre- Competitive Uasin Gishu County (Lot 2) Page 2 KE-MOH-233867-CW-RFQ / Proposed Medical Gas Request for Installation Work at Moiben Quotations - Small Pending Medical supplies and Request for Single Stage - One 2021-07- Sub Hospital-Uasin Gishu IDA / 65980 Post Limited Works 216,000.00 0.00 Implementat 2021-05-16 2021-06-08 equipment Quotations Envelope 16 County( Lot 1) and Kericho (Emergency) SPD - ion County Referral Hospital- Competitive Kericho County( Lot 2) KE-MOH-233868-CW-RFQ / Request for Proposed medical Gas Quotations - Small Pending Installation works at Pumwani Medical supplies and Request for Single Stage - One 2022-01- IDA / 65980 Post Limited Works 216,000.00 0.00 Implementat 2021-05-18 2021-07-05 Hospital - Nairobi County (Lot equipment Quotations Envelope 01 (Emergency) SPD - ion 1) and Kitui County Hospital ( Competitive Lot2) KE-MOH-233869-CW-RFQ / Request for Proposed Medical Gas Quotations - Small Pending Medical supplies and Request for Single Stage - One 2021-09- installation works at Nakuru IDA / 65980 Post Limited Works 225,000.00 0.00 Implementat 2021-05-20 2021-07-21 equipment Quotations Envelope 16 Level 5 Hospital in Nakuru (Emergency) SPD - ion County. Competitive GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KE-MOH-168069-GO-UN / Procure assorted Lab Personal Protective Equipment, Pending Assorted emergency ICU Medical supplies and UN Agencies IDA / 65980 Post Direct 985,175.00 0.00 Implementati 2020-04-20 2020-04-25 2020-05-30 2020-11-26 equipment, supplies and equipment (Direct) on consumables Assorted Lab equipment and Lab supplies KE-MOH-168095-GO-RFQ / Printing and distribution of Pending assorted surveillance , SOP Response, capacity building Request for Single Stage - One IDA / 65980 Post Limited 150,000.00 0.00 Implementati 2020-04-19 2020-06-14 2020-12-11 and data collection tools"4000 and training Quotations Envelope on No. MOH 502, 2000 No. MOH 503 and 10000 No. MOH 505 KE-MOH-168128-GO-RFQ / Print and distribute 250000 Pending Community discussion and Request for Single Stage - One No. A4 size pamphlets, IDA / 65980 Post Limited 234,000.00 0.00 Implementati 2020-04-22 2020-06-17 2020-12-14 information outreach Quotations Envelope 100000 No. A2 posters and on 100 Roll up banners KE-MOH-00001-GO-DIR / Procure 250 No. Gradian Medical supplies and IDA / 65980 Prior Direct Selection Direct 4,000,000.00 1,600,000.00 Signed 2020-03-27 2020-04-27 2020-03-27 2020-05-19 2020-03-30 2020-03-30 2020-12-31 Comprehensive Critical Care equipment ventillators Pending KE-MOH-168074-GO-DIR / Response, capacity building IDA / 65980 Post Direct Selection Direct 150,000.00 0.00 Implementati 2020-04-20 2020-04-25 2020-05-30 2020-11-26 Procure 3000 mobile phones and training on KE-MOH-173622-GO-RFQ / Response, capacity building Request for Single Stage - One Tablet for case management, IDA / 65980 Post Limited 24,750.00 22,142.52 Signed 2020-05-30 2020-05-28 2020-07-25 2020-06-08 2021-01-21 and training Quotations Envelope 75 No KE-MOH-173494-GO-RFQ / procurement of 2 fireproof Project implementation and Request for Single Stage - One IDA / 65980 Post Limited 5,600.00 19,769.48 Completed 2020-06-01 2020-05-28 2020-07-27 2020-06-08 2021-01-23 2020-06-30 cabinets, 2 microwave, 2 monitoring Quotations Envelope water dispensers, 1 fridge KE-MOH-173502-GO-RFQ / Procurement of 11 laptops, 1 LCD projector, 11 mobile Response, capacity building Request for Single Stage - One phones, 1 colour multi- IDA / 65980 Post Limited 27,700.00 26,777.78 Signed 2020-06-02 2020-05-28 2020-07-28 2020-06-08 2021-01-24 and training Quotations Envelope functional printer ,1 b/w light duty printer, 2 wifi routers, 10 modems KE-MOH-173541-GO-RFQ / procurement of furniture as follows: , 2 office desks, 1 Pending executive table , 2 executive Project implementation and Request for Single Stage - One IDA / 65980 Post Limited 15,700.00 0.00 Implementati 2020-06-01 2020-07-27 2021-01-23 chair high back orthopedic, 1 monitoring Quotations Envelope on secretarial chair, 4 visitors chairs, 9 executive chair high back swivel KE-MOH-175673-GO-DIR / Procurement of 15 heavy duty Response, capacity building IDA / 65980 Post Direct Selection Direct 1,020,000.00 797,272.69 Signed 2020-05-27 2020-05-19 2020-06-01 2020-06-04 2020-07-06 2020-06-08 2021-01-02 double cabin vehicle, and 1 and training heavy duty passenger vehicle KE-MOH-173607-GO-DIR / Airtime for 2125 community health extension workers for Pending Project implementation and 3 months @KES 2000 per IDA / 65980 Post Direct Selection Direct 129,150.00 0.00 Implementati 2020-05-28 2020-06-02 2020-07-07 2021-01-03 monitoring month, Airtime for 11 project on personnel for 3 months@ KES 5000 per month KE-MOH-173609-GO-RFQ / Quarintine, isolation and Request for Single Stage - One Procurement of 1840 No. IDA / 65980 Post Limited 147,200.00 0.00 Canceled 2020-06-02 2020-06-09 2020-07-28 2021-01-24 treatement centres Quotations Envelope Thermoguns KE-MOH-168100-GO-RFQ / Print and distribute guidelines, booklets, modules Pending Response, capacity building Request for Single Stage - One and forms: 2000 contact IDA / 65980 Post Limited 75,000.00 0.00 Implementati 2020-06-05 2020-07-31 2021-01-27 and training Quotations Envelope tracing forms, 2000 No. case on investigation forms and training modules Page 3 KE-MOH-178412-GO-RFQ / Procure assorted items to set up grievance hotline: 1.No. Grievance Redress Mechanism Pending Software, 1 No. 4 way work Project implementation and Request for Single Stage - One IDA / 65980 Post Limited 12,500.00 0.00 Implementati 2020-06-10 2020-06-24 2020-12-21 station, 4 No. Desktop monitoring Quotations Envelope on computers, 1 No. Medium duty 3-in -1 printer, 3 No. Telephone handsets and 2 No. mobile phone KE-MOH-182114-GO-RFQ / Pending Procurement of 5 No. Laptop Project implementation and Request for Single Stage - One IDA / 65980 Post Limited 9,500.00 0.00 Implementati 2020-07-02 2020-07-21 2021-01-17 computers and 5 No. mobile monitoring Quotations Envelope on Phones KE-MOH-173603-GO-RFQ / Pending procurement of 368 hand Medical supplies and Request for Single Stage - One IDA / 65980 Post Limited 552,000.00 0.00 Implementati 2020-06-08 2020-08-03 2021-01-30 washing stations and equipment Quotations Envelope on accessories KE-MOH-184648-GO-RFQ / Printing of 500 copies of Grievance Redress Mechanism one pager,1000 copies of Gender Based Violence/SEA Pending Project implementation and Request for Single Stage - One one pager,1000 copies of IDA / 65980 Post Limited 7,700.00 0.00 Implementati 2020-07-20 2020-07-28 2020-10-30 monitoring Quotations Envelope Abbreviated Code of Conduct, on 200 copies of Grievance Redress Mechanism Register Log and 1000 copies of Patient feedback form KE-MOH-188957-GO-RFQ / Pending Printing of 38,286 copies of Availability of safe blood and Request for Single Stage - One IDA / 65980 Post Limited 111,852.00 0.00 Implementati 2020-08-28 2020-09-18 2020-12-23 booklets, forms,charts, blood products Quotations Envelope on Registers and reporting tools KE-MOH-188960-GO-RFQ / Pending Availability of safe blood and Request for Single Stage - One Procure 144 blood donor IDA / 65980 Post Limited 100,800.00 0.00 Implementati 2020-08-26 2020-09-25 2021-03-24 blood products Quotations Envelope coaches on KE-MOH-189116-GO-RFQ / Pending Procurement of 140,000 Availability of safe blood and Request for Single Stage - One IDA / 65980 Post Limited 142,800.00 0.00 Implementati 2020-08-29 2020-10-24 2021-04-22 Haemoglobin estimation blood products Quotations Envelope on cuvettes KE-MOH-189120-GO-RFQ / Pending Availability of safe blood and Request for Single Stage - One Procurement of 3,000 IDA / 65980 Post Limited 24,000.00 0.00 Implementati 2020-08-30 2020-10-25 2021-04-23 blood products Quotations Envelope Quadruple blood bags on KE-MOH-189122-GO-RFQ / Pending Availability of safe blood and Request for Single Stage - One Procurement of 10,000 IDA / 65980 Post Limited 60,000.00 0.00 Implementati 2020-08-30 2020-10-25 2021-04-23 blood products Quotations Envelope Tripple Blood Bags on KE-MOH-189123-GO-RFQ / Pending Availability of safe blood and Request for Single Stage - One Procurement of 12,000 IDA / 65980 Post Limited 60,000.00 0.00 Implementati 2020-08-30 2020-10-25 2021-04-23 blood products Quotations Envelope Double Blood Bags on KE-MOH-189126-GO-RFQ / Pending Availability of safe blood and Request for Single Stage - One Procurement of 2,500 Single IDA / 65980 Post Limited 7,500.00 0.00 Implementati 2020-08-30 2020-10-25 2021-04-23 blood products Quotations Envelope Blood Bags on KE-MOH-189129-GO-RFQ / Pending Availability of safe blood and Request for Single Stage - One Procurement of 2,500 IDA / 65980 Post Limited 17,500.00 0.00 Implementati 2020-08-30 2020-10-25 2021-04-23 blood products Quotations Envelope Paediatric Blood bags on KE-MOH-188959-GO-RFQ / Pending Procure 2 refrigerated vehicles Availability of safe blood and Request for Single Stage - One IDA / 65980 Post Limited 180,000.00 0.00 Implementati 2020-10-20 2021-03-02 2021-02-18 for ferring large amounts of blood products Quotations Envelope on blood KE-MOH-189103-GO-DIR / Procurement of 21,000 TTI Pending Availability of safe blood and screening reagents Murex for IDA / 65980 Post Direct Selection Direct 105,000.00 0.00 Implementati 2020-09-27 2020-10-02 2020-10-28 2020-11-27 blood products Etimax machines in all the 6 on regional testing sites KE-MOH-189093-GO-DIR / Pending Procurement of 54,000 TTI Availability of safe blood and IDA / 65980 Post Direct Selection Direct 594,000.00 0.00 Implementati 2020-09-27 2020-10-02 2020-10-28 2020-11-27 Screening reagents Liaison for blood products on Liasion Equipment KE-MOH-189110-GO-DIR / Procurement of 66,000 Blood Pending Availability of safe blood and Grouping reagents Qwalys for IDA / 65980 Post Direct Selection Direct 264,000.00 0.00 Implementati 2020-09-27 2020-10-02 2020-10-28 2020-11-27 blood products Blood Grouping machines in on Embu and Nakuru KE-MOH-189091-GO-DIR / Pending Procure 54,000 Abbot Availability of safe blood and IDA / 65980 Post Direct Selection Direct 648,000.00 0.00 Implementati 2020-09-27 2020-10-02 2020-10-28 2020-11-27 Reagents Testing Kits for blood products on Abbot Equipment KE-MOH-176216-GO-RFB / Pending PROVISION OF 24-HOUR Medical supplies and Single Stage - One IDA / 65980 Post Request for Bids Open - National 486,000.00 0.00 Implementati 2020-09-24 2020-09-24 2020-10-07 2020-10-14 2020-11-11 2021-05-10 STANDBY AMBULANCE equipment Envelope on SERVICES FOR 6 MONTHS KE-MOH-196696-GO-RFQ / Pending Procurement of assorted Medical supplies and Request for Single Stage - One IDA / 65980 Post Limited 33,600.00 0.00 Implementati 2020-10-12 2020-11-06 2020-12-04 Furniture for use in Mama equipment Quotations Envelope on Lucy Hospital KE-MOH-196698-GO-RFQ / Pending Medical supplies and Request for Single Stage - One Procurement of ICT IDA / 65980 Post Limited 28,000.00 0.00 Implementati 2020-10-09 2020-11-11 2020-12-11 equipment Quotations Envelope equipment for use in Mama on Lucy Hospital KE-MOH-196699-GO-RFQ / Pending Procurement of Laundry Medical supplies and Request for Single Stage - One IDA / 65980 Post Limited 180,000.00 0.00 Implementati 2020-10-12 2020-11-30 2020-12-30 equipment for use in Mama equipment Quotations Envelope on Lucy Hospital Page 4 KE-MOH-189135-GO-RFQ / Pending Procurement of 6 Hematology Availability of safe blood and Request for Single Stage - One IDA / 65980 Post Limited 93,600.00 0.00 Implementati 2020-11-27 2020-12-13 2021-01-22 analyzer and 72 Hematology blood products Quotations Envelope on analyzer kits KE-MOH-196868-GO-RFQ / Procurement of blood collection and processing Pending equipment as follows: Availability of safe blood and Request for Single Stage - One IDA / 65980 Post Limited 584,700.00 0.00 Implementati 2020-11-13 2021-01-01 2021-04-01 1. 15 manual component blood products Quotations Envelope on separator 2. 18 automated component expressor/extractor KE-MOH-196697-GO-RFQ / Procure 100 Pillows with covers, 200 Blankets, 200 Pending pairs of bed sheets (large), Medical supplies and Request for Single Stage - One IDA / 65980 Post Limited 26,500.00 0.00 Implementati 2020-11-11 2020-12-13 2021-01-10 200 Draw sheets, 40 window equipment Quotations Envelope on curtain rails and 40 hospital window curtains for Mama Lucy Hospital KE-MOH-189013-GO-RFQ / Pending Availability of safe blood and Request for Single Stage - One Procure 20 backup diesel IDA / 65980 Post Limited 950,000.00 0.00 Implementati 2020-11-22 2020-12-21 2021-03-22 blood products Quotations Envelope generators 10-12 KVA on KE-MOH-189113-GO-DIR / Procurement of 102,000 Pending Availability of safe blood and blood grouping reagents IDA / 65980 Post Direct Selection Direct 601,800.00 0.00 Implementati 2020-11-06 2020-11-11 2020-11-24 2020-12-24 blood products Immucore for six regional on testing centres KE-MOH-200443-GO-RFQ / Procurement of assorted Pending blood processing equipment Availability of safe blood and Request for Single Stage - One IDA / 65980 Post Limited 260,700.00 0.00 Implementati 2020-11-14 2020-12-19 2021-03-19 broken down as follows: blood products Quotations Envelope on 1. 35 Tube Sealer 2. 155 Tube Strippers KE-MOH-200449-GO-RFQ / Procurement of Pending Availability of safe blood and Request for Single Stage - One 1. 8 refrigerated centrifuges IDA / 65980 Post Limited 571,550.00 0.00 Implementati 2020-11-20 2021-01-01 2021-04-01 blood products Quotations Envelope 2. 8 platelet agitators on 3. 33 blood weighing scales KE-MOH-200457-GO-RFQ / Pending Availability of safe blood and Request for Single Stage - One Procurement of 800 Apheresis IDA / 65980 Post Limited 280,000.00 0.00 Implementati 2020-11-09 2020-12-21 2021-03-21 blood products Quotations Envelope kits on KE-MOH-201450-GO-RFQ / Pending Medical supplies and Request for Single Stage - One Procurement of a Public IDA / 65980 Post Limited 15,000.00 0.00 Implementati 2020-11-20 2020-12-29 2021-01-29 equipment Quotations Envelope Address System on KE-MOH-196873-GO-RFQ / Procurement of assorted Blood cold chain broken down as follows: Pending Availability of safe blood and Request for Single Stage - One 1. 8 blood bank refrigerators IDA / 65980 Post Limited 565,500.00 0.00 Implementati 2020-11-13 2021-01-01 2021-04-01 blood products Quotations Envelope 2. 8 blood bank freezers on 3. 1 bio bank 4. 231 blood transportation boxes KE-MOH-188958-GO-DIR / Procure 10 customized 7 Pending seater passenger vans Availability of safe blood and IDA / 65980 Post Direct Selection Direct 700,000.00 0.00 Implementati 2020-11-29 2020-12-04 2020-12-19 2021-01-18 separate compartment for blood products on commodities and blood bags with overhead carrier KE-MOH-204854-GO-RFQ / Pending Availability of safe blood and Request for Single Stage - One Procurement of Blood cold IDA / 65980 Post Limited 150,000.00 0.00 Implementati 2020-12-05 2021-01-05 2021-02-04 blood products Quotations Envelope rooms on KE-MOH-203440-GO-RFQ / Procurement of parts to Pending Availability of safe blood and Request for Single Stage - One enable repair of equipment at IDA / 65980 Post Limited 15,000.00 0.00 Implementati 2021-01-22 2021-02-22 2021-04-23 blood products Quotations Envelope the Kenya National Blood on Transfusion by the Engineer KE-MOH-189012-GO-RFQ / Supply and Installation of No. 40 Air conditioners (18 BTU) Pending Availability of safe blood and Request for Single Stage - One to be installed in the various IDA / 65980 Post Limited 80,000.00 0.00 Implementati 2021-02-07 2021-03-18 2021-09-14 blood products Quotations Envelope Kenya National Blood on Transfusion Centres countrywide KE-MOH-196881-GO-RFQ / Procurement of assorted Temperature monitors broken down as follows: Pending 1. 78 remote temperature Availability of safe blood and Request for Single Stage - One IDA / 65980 Post Limited 112,200.00 0.00 Implementati 2021-02-08 2021-03-29 2021-06-27 monitor fitted on static cold blood products Quotations Envelope on chain equipment 2. 144 remote temperature monitor fitted on mobile cold chain equipment KE-MOH-215327-GO-RFQ / Procurement of 100 No. Pending High flow nasal cannulas Medical supplies and Request for Single Stage - One IDA / 65980 Post Limited 800,000.00 0.00 Implementati 2021-02-10 2021-03-24 2021-06-22 required during oxygen equipment Quotations Envelope on therapy for critically ill patients including COVID-19 patients KE-MOH-216887-GO-RFQ / Procurement of Furniture for Pending Quarintine, isolation and Request for Single Stage - One use at the Kenyatta University IDA / 65980 Post Limited 47,000.00 0.00 Implementati 2021-02-14 2021-03-26 2021-05-25 treatement centres Quotations Envelope Teaching and Referral on Hospital Isolation Facility Page 5 KE-MOH-226662-GO-RFQ / Pending Procure 2 No laptops ,2 No Project implementation and Request for Single Stage - One IDA / 65980 Post Limited 4,000.00 0.00 Implementati 2021-04-10 2021-05-29 2021-06-28 Modems and 2 No Mobile monitoring Quotations Envelope on phones KE-MOH-227263-GO-RFQ / Pending Supply, Delivery, Installation Community discussion and Request for Single Stage - One IDA / 65980 Post Limited 93,600.00 0.00 Implementati 2021-04-13 2021-06-08 2021-12-05 of hardware and networking information outreach Quotations Envelope on for the Call Centre KE-MOH-229145-GO-DIR / Supply, Delivery ,Installation Pending Medical supplies and of two (2 No) 20,000 liter IDA / 65980 Post Direct Selection Direct 500,000.00 0.00 Implementati 2021-04-13 2021-04-15 2021-04-28 2021-06-08 equipment Bulk Oxygen tank and on Accessories KE-MOH-229791-GO-RFQ / Supply and Delivery of Pending Medical supplies and Request for Single Stage - One Personal Protective IDA / 65980 Post Limited 426,821.00 0.00 Implementati 2021-04-22 2021-04-28 2021-05-11 equipment Quotations Envelope Equipment's for the COVID- on 19 testing laboratories KE-MOH-229861-GO-RFQ / Supply and Delivery of 2,070 Pending pieces of 500 ml Sanitizers Medical supplies and Request for Single Stage - One IDA / 65980 Post Limited 13,747.00 0.00 Implementati 2021-04-26 2021-05-31 2021-06-07 and 42 (No)pack of 100 equipment Quotations Envelope on Biohazard Bags for COVID - 19 Testing Laboratories KE-MOH-233863-GO-DIR / Supply and Delivery of bulk 20,000 liters of cryogenic liquid medical Oxygen in KNH Pending Mbagathi Hospital and bulk Medical supplies and IDA / 65980 Post Direct Selection Direct 1,440,000.00 0.00 Implementati 2021-05-13 2021-05-18 2021-06-22 2022-03-23 20,000 liters of cryogenic equipment on liquid medical Oxygen in Kenyatta University Teaching and Referral Hospital for 24 times in each Hospital. KE-MOH-235971-GO-DIR / Supply, Delivery Installation and commissioning of a Pending 10,000 liter liquid Oxygen Medical supplies and IDA / 65980 Post Direct Selection Direct 490,000.00 0.00 Implementati 2021-05-26 2021-05-31 2021-07-05 2022-05-31 tank (1 No) and supply of equipment on Medical Oxygen for one year (24 times) in Nakuru Level 5 Hospital -Nakuru County KE-MOH-235998-GO-DIR / Supply, Delivery ,Installation and commissioning of a 8,000 Pending liter liquid Oxygen tank (1 No) Medical supplies and IDA / 65980 Post Direct Selection Direct 408,000.00 0.00 Implementati 2021-05-26 2021-05-31 2021-07-05 2022-05-31 and supply of Medical Oxygen equipment on for one year (24 times) in Kericho County Referral Hospital-Kericho County KE-MOH-236003-GO-DIR / Supply, Delivery, Installation and commissioning of a 6 ,000 liter liquid Oxygen tank Pending Medical supplies and (1 No) and supply of Medical IDA / 65980 Post Direct Selection Direct 316,000.00 0.00 Implementati 2021-05-26 2021-05-31 2021-06-23 2022-06-29 equipment Oxygen for one year (24 on times) in Pumwani Hospital - Nairobi County as per specifications. KE-MOH-235999-GO-DIR / Supply, Delivery Installation and commissioning of a 8,000 Pending Medical supplies and liter liquid Oxygen tank (1 No) IDA / 65980 Post Direct Selection Direct 408,000.00 0.00 Implementati 2021-05-31 2021-06-05 2021-07-10 2022-06-29 equipment and supply of Medical Oxygen on for one year (24 times) in Kitui County Hospital-Kitui County KE-MOH-240389-GO-DIR / Supply and Delivery of 384 units of Medical Air in 7,600 Pending Medical supplies and litre cylinder at Moiben Sub IDA / 65980 Post Direct Selection Direct 12,288.00 0.00 Implementati 2021-06-25 2021-06-30 2021-08-04 2022-01-31 equipment Hospital -Uasin Gishu County on (Lot 1) and Kericho County Referral Hospital (Lot 2) KE-MOH-240474-GO-RFQ / Procure Spare parts for repairs Pending of various cold chain Availability of safe blood and Request for Single Stage - One IDA / 65980 Post Limited 43,750.00 0.00 Implementati 2021-06-27 2021-08-12 2022-02-08 equipment and servicing tools blood products Quotations Envelope on for Kenya National Blood Transfusion services NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KE-MOH-168078-NC-RFQ / Development of a platform for Event based surveillance at Response, capacity building IDA / 65980 Post Direct Selection Direct 40,000.00 0.00 Canceled 2020-04-17 2020-04-22 2020-05-27 2020-11-23 the facilities and Community and training based surveillance at the community level KE-MOH-185606-NC-RFB / PROVISION OF 24 HOUR STAND BY AMBULANCE Pending SERVICE: 16 AMBULANCES(6 Response, capacity building Single Stage - One IDA / 65980 Post Request for Bids Open - National 1,752,000.00 0.00 Implementati 2020-07-28 2020-08-02 2020-08-12 2020-08-19 2020-09-03 2021-03-02 ADVANCED CARDIAC LIFE and training Envelope on SUPPORT & 10 BASIC LIFE SUPPORT) FOR A PERIOD OF 1 YEAR(365 DAYS) Page 6 KE-MOH-189139-NC-DIR / Procurement of Courier Services to transport blood Pending samples, components, Availability of safe blood and IDA / 65980 Post Direct Selection Direct 198,000.00 0.00 Implementati 2020-08-26 2020-08-31 2020-10-05 2021-04-03 supplies and other documents blood products on from the National Blood Transfusion centre to the other parts of the country. KE-MOH-204853-NC-RFQ / Pending Availability of safe blood and Request for Single Stage - One Procurement of a Quality IDA / 65980 Post Limited 25,000.00 0.00 Implementati 2020-12-05 2021-01-05 2021-02-04 blood products Quotations Envelope Assurance Scheme on KE-MOH-212377-NC-RFQ / Pending Repair of Cold Rooms in the Availability of safe blood and Request for Single Stage - One IDA / 65980 Post Limited 200,000.00 0.00 Implementati 2021-01-25 2021-02-26 2021-05-27 Kenya National Blood blood products Quotations Envelope on Transfusion centres KE-MOH-212369-NC-RFQ / Pending Repair of Incinerators in the Availability of safe blood and Request for Single Stage - One IDA / 65980 Post Limited 80,000.00 0.00 Implementati 2021-01-27 2021-02-26 2021-05-27 Kenya National Blood blood products Quotations Envelope on Transfusion Centres KE-MOH-212379-NC-RFQ / Pending Repair of Generators at the Availability of safe blood and Request for Single Stage - One IDA / 65980 Post Limited 10,500.00 0.00 Implementati 2021-01-24 2021-02-26 2021-05-27 Kenya National Blood blood products Quotations Envelope on Transfusion Centres KE-MOH-215334-NC-DIR / Provision of 24-Hour ten (No. 10) Standby Ambulance Pending Response, capacity building Service for 6 Months from M/S IDA / 65980 Post Direct Selection Direct 570,000.00 0.00 Implementati 2021-02-04 2021-02-11 2021-03-16 2021-06-14 and training Emergency Plus Medical on Services of P.O Box 40712 – 00100 Nairobi CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KE-MOH-224950-CS-CQS / Procurement of Consultant Communication Consultancy Community discussion and Under IDA / 65980 Post Qualification Limited 750,000.00 0.00 2021-03-24 2021-03-24 2021-03-31 2021-04-14 2021-05-12 2022-05-11 Firm for the Kenya Covid-19 information outreach Implementation Selection Health Emergency Response Project INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KE-MOH-173617-CS-INDV / Hire of 50 temporary staff for Individual Response, capacity building Under call centre @ USD 1000 per IDA / 65980 Post Consultant Limited 150,000.00 0.00 2020-05-29 2020-04-26 2020-06-03 2020-05-26 2020-06-24 2020-05-26 2020-07-29 2021-01-25 and training Implementation person per month for three Selection months renewable monthly KE-MOH-173610-CS-INDV / Individual Community discussion and Pending Consultancy for IDA / 65980 Post Consultant Limited 36,000.00 0.00 2020-06-01 2020-06-06 2020-06-27 2020-08-01 2021-01-28 information outreach Implementation communication specialist Selection KE-MOH-176220-CS-INDV / procurement of 55 Lab Individual technologists to be deployed Response, capacity building Pending IDA / 65980 Post Consultant Limited 123,750.00 0.00 2020-05-29 2020-06-03 2020-06-24 2020-07-29 2021-01-25 at 11 facilities for and training Implementation Selection coordination of lab activities for three months KE-MOH-180881-CS-INDV / Temporary employment of Point of EntryHealth workers Individual Response, capacity building Pending as follows; 15 Public Health IDA / 65980 Post Consultant Limited 112,500.00 0.00 2020-06-23 2020-06-25 2020-06-29 2020-07-07 2021-01-03 and training Implementation officers, 4 Clinical officers and Selection 6 Nurses on 6 month contract basis KE-MOH-181249-CS-INDV / Employment of 55 Psychologists on a temporary Individual Response, capacity building Pending basis on renewable contract IDA / 65980 Post Consultant Limited 131,250.00 0.00 2020-06-23 2020-06-28 2020-07-02 2020-07-17 2021-01-13 and training Implementation for 3 months as follows: 45 Selection assistants Psychologists and 10 senior psychologists KE-MOH-178671-CS-CQS / Hire a consultant to undertake Environmental Impact Assessment on sites for Under installation of 16 incineratos IDA / 65980 Medical waste disposal Post Direct Selection Direct 100,000.00 0.00 2020-06-23 2020-08-07 2020-06-29 2020-07-21 2021-01-17 Implementation for additional tratment facilities in high priority areas and sites forincinerators for 6 specialised laboratories KE-MOH-181245-CS-INDV / Employ Consultant to extract and document the lessons Individual Project implementation and Pending learned and best practices in IDA / 65980 Post Consultant Limited 10,000.00 0.00 2020-06-23 2020-06-24 2020-06-30 2020-08-04 2021-01-31 monitoring Implementation Kenya’s experience in the Selection response to the COVID-19 pandemic KE-MOH-181250-CS-INDV / Employ a Consultant to do a Individual Response, capacity building Pending rapid assessment on the IDA / 65980 Post Consultant Limited 14,000.00 0.00 2020-06-23 2020-06-24 2020-06-30 2020-07-15 2021-01-11 and training Implementation status of Counties to respond Selection to the COVID-19 pandemic Page 7 KE-MOH-196780-CS-INDV / Employment of twenty six Individual Response, capacity building Pending (No. 26) doctors to be paid on IDA / 65980 Post Consultant Limited 187,200.00 0.00 2020-10-05 2020-10-09 2020-10-16 2020-11-13 2020-12-14 and training Implementation a monthly basis for a period Selection of six months KE-MOH-196794-CS-INDV / Employment of Healthcare Individual Workers: Ten (No. 10) Response, capacity building Pending IDA / 65980 Post Consultant Limited 45,000.00 0.00 2020-11-15 2020-11-15 2020-11-22 2020-12-20 2021-01-19 Nutritionists to be paid on a and training Implementation Selection monthly basis for a period of six months KE-MOH-196800-CS-INDV / Employment of Healthcare Individual Workers: Ten (No. 10) Response, capacity building Pending IDA / 65980 Post Consultant Limited 45,000.00 0.00 2020-11-15 2020-11-20 2020-11-27 2020-12-25 2021-01-24 psychologists to be paid on a and training Implementation Selection monthly basis for a period of six months KE-MOH-196790-CS-INDV / Employment of Healthcare Individual Workers: Ten (No. 10) Response, capacity building Pending IDA / 65980 Post Consultant Limited 45,000.00 0.00 2020-11-15 2020-11-18 2020-11-25 2020-12-23 2021-01-22 physiotherapists to be paid on and training Implementation Selection a monthly basis for a period of six months KE-MOH-196770-CS-INDV / Employment of Healthcare Individual Workers: laboratory liaison Response, capacity building Pending IDA / 65980 Post Consultant Limited 10,800.00 0.00 2020-11-15 2020-11-20 2020-11-27 2020-12-25 2021-01-24 officers to be paid on a and training Implementation Selection monthly basis for a period of six months KE-MOH-196786-CS-INDV / Employment of Healthcare Individual Workers: Seven (No.7) public Response, capacity building Pending IDA / 65980 Post Consultant Limited 31,500.00 0.00 2020-11-15 2020-11-19 2020-11-26 2020-12-24 2021-01-24 health technicians to be paid and training Implementation Selection on a monthly basis for a period of six months KE-MOH-196783-CS-INDV / Employment of Healthcare Individual Workers: One Hundred and Response, capacity building Pending IDA / 65980 Prior Consultant Limited 720,000.00 0.00 2020-11-15 2020-11-19 2020-11-26 2020-12-24 2021-01-24 Sixty (No. 160) Nurses to be and training Implementation Selection paid on a monthly basis for a period of six months KE-MOH-196776-CS-INDV / Employment of Healthcare Individual Workers: Two (No. 2) logistics Response, capacity building Pending IDA / 65980 Post Consultant Limited 18,000.00 0.00 2020-11-15 2020-11-18 2020-11-25 2020-12-23 2021-01-22 officers for PHEOC to be paid and training Implementation Selection on a monthly basis for a period of six months KE-MOH-196756-CS-INDV / Employment of Healthcare Workers employed on a Individual monthly basis for a period of Response, capacity building Pending IDA / 65980 Prior Consultant Limited 531,000.00 0.00 2020-11-06 2020-11-09 2020-11-16 2020-12-14 2021-01-13 six (6) months. and training Implementation Selection Employment of One Hundred and Eighteen (No. 118) laboratory technicians. KE-MOH-196766-CS-INDV / Employment of Health Care workers: Fifty Four (No. 54) Individual Response, capacity building Pending Lab Information Management IDA / 65980 Post Consultant Limited 243,000.00 0.00 2020-11-15 2020-11-18 2020-11-25 2020-12-23 2021-01-22 and training Implementation Officers to be paid on a Selection monthly basis for a period of six months KE-MOH-189062-CS-INDV / Employment of One Hundred (No. 100) public health Individual officers for monthly period of Response, capacity building Pending IDA / 65980 Post Consultant Limited 450,000.00 0.00 2020-11-22 2020-11-27 2020-11-30 2020-12-28 2021-01-28 6 months. The contracts will and training Implementation Selection be renewable after 3 months based on performance and need. KE-MOH-196781-CS-INDV / Employment of Healthcare Individual Workers: Thirty-two (No. 32) Response, capacity building Pending IDA / 65980 Post Consultant Limited 144,000.00 0.00 2020-11-22 2020-11-26 2020-12-03 2020-12-24 2021-01-24 Clinical Officers to be paid on and training Implementation Selection a monthly basis for a period of six months KE-MOH-203424-CS-INDV / Engagement of a Consultant Individual for Development of a Five Availability of safe blood and Pending IDA / 65980 Post Consultant Limited 25,000.00 0.00 2020-11-15 2020-11-20 2020-11-25 2020-12-16 2021-02-14 Year Strategic Plan for the blood products Implementation Selection Kenya National Blood Transfusion Services Division KE-MOH-226655-CS-INDV / Hire an individual consultant Individual Community discussion and Pending to support implementation of IDA / 65980 Post Consultant Limited 10,500.00 0.00 2021-03-29 2021-04-03 2021-04-08 2021-04-22 2021-10-19 information outreach Implementation the 5th COVID-19 Knowledge Selection Attitude Practice (KAP) Survey. Page 8 GOVERNANCE TO ENABLE SERVICE DELIVERY IN MALAWI PROJECT PREPARATION ADVANCE (PPA) PROCUREMENT PLAN I. General 1. Project Information Country: Malawi Project Name: Governance to Enable Service Delivery in Malawi Project ID: P164961 2. Project Implementation Agency: National Local Government Finance Committee (NLGFC) 3. Date of the Procurement Plan: February 1, 2019 4. Period Covered by this procurement plan: II. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016 revised November 2017 and August 2018) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations as set forth in STEP. III. Bank’s Standard Procurement Documents: The Bank’s Standard Procurement Documents shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. IV. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. 1 When the Borrower uses its own national open competitive procurement arrangements as set forth in The Public Procurement and Disposal of Assets Act, 2017 and its subsidiary instruments namely: The Public Procurement Regulations, 2004, Desk Instructions (2005), Standard bidding Documents and Circulars for the Public Procurement and Disposal of Assets (PPDA) Authority such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations under the following conditions: o Provision of “set-asides” contracts for small enterprises shall not be applied. o Criteria such as environmental aspect, extent of local content, technology transfer, and managerial, scientific & operational skills development shall not be used in the evaluation of bids unless specifically agreed by the Bank on case to case basis. o Procurement Documents include provisions, intended to adequately mitigate against environmental, social (including sexual exploitation and abuse and gender-based violence), health and safety (“ESHS”) risks and impacts When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. In accordance with paragraph 5.4(c) and 5.5 of the Procurement Regulations, the request for bids/request for proposals/request for quotations document shall require that Bidders/Proposers submitting Bids/Proposals/quotations present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. The form of the Letter of Acceptance is attached in Appendix 1. V. Prequalification: N/A VI. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable. VII. Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations: Not Applicable. VIII. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). (a) Goods: N/A 2 (b) Works: N/A Domestic preference is not applicable for National Open Competitive Procurement IX. Other Relevant Procurement Information Provide any other relevant procurement information such as procedures for CDD components, Procurement in Situations of Urgent Need of Assistance or Capacity Constraints etc.--NONE X. Procurement Prior Review Thresholds (US$ millions): The overall Project procurement Risk is Substantial. The project being a non- emergency project, there would be generally prior reviews of cases unless specifically indicated in the Procurement Plan as a special measure. Post Review: All contracts not subject to prior review shall be subject to post review. XI. Procurement Prior Review Thresholds Based on Substantial Risk Rating (US$ millions) Type of Procurement Threshold (Million USD) Works (including turnkey, supply & installation of plant 5 and equipment, and PPP) Goods, information technology and non-consulting 1.5 services Consultants: firms 0.5 Consultants: Individuals 0.2 XII. Thresholds for procurement approaches and methods 3 Works Goods, IT and Non- Shortlist of Consulting Services National Consultants Open Open Request Open Open Request Consultin Engineering Internation Nation for Internation National for g Services & al al Quotatio al Quotation Construction n < < Supervision ≧ < ≧ ≦ ≦ ≦ 7 7 0.2 1 1 0.1 0.2 0.3 4 PROCUREMENT PACKAGES WITH METHODS AND TIME SCHEDULES A. GOODS B. CONSULTANCY SERVICES Sr. No Contract Description Est. Cost Review by Market Selecti Evaluati Shortlisti Expected Expected (US$) Bank Approach on on ng date of date of (Prior/ Method Options (Yes/ No) proposal Contract Post) opening Signature 1 Design of Performance Based Grant, 270,000. assessment and associated Systems and Prior Direct CDS Yes Feb 2019 Mar 2019 00 Procedures for Local Authorities 5 SUMMARY NO CATEGORY OF VALUE (US$) PROCUREMENT A Goods B Works C Consultancy D Non-Consultancy TOTAL 6 Appendix 1 Letter of Acceptance of the World Bank’s Anti-Corruption Guidelines and Sanctions Framework Date: Invitation of Bids/Proposals No.__________ To: ___________________________________________________________________________ We, along with our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not) consultants and personnel, acknowledge and agree to abide by the World Bank’s policy regarding Fraud and Corruption (corrupt, fraudulent, collusive, coercive, and obstructive practices), as set out and defined in the World Bank’s Anti-Corruption Guidelines1 in connection with the procurement and execution of the contract (in case of award), including any amendments thereto. We declare and warrant that we, along our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not), consultants and personnel, , are not subject to, and are not controlled by any entity or individual that is subject to, a temporary suspension, early temporary suspension, or debarment imposed by a member of the World Bank Group, including, inter alia, a cross-debarment imposed by the World Bank Group as agreed with other international financial institutions (including multilateral development banks), or through the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement. Further, we are not ineligible under the laws or official regulations of [Insert name of Employer as per bidding document] or pursuant to a decision of the United Nations Security Council. We confirm our understanding of the consequences of not complying with the World Bank’s Anti-Corruption Guidelines, which may include the following: a. rejection of our Proposal/Bid for award of contract; b. in the case of award, termination of the contract, without prejudice to any other remedy for breach of contract; and c. sanctions, pursuant to the Bank’s Anti-corruption Guidelines and in accordance with its prevailing sanctions policies and procedures as set forth in the Bank’s Sanctions Framework. This may include a public declaration of ineligibility, either indefinitely or for a stated period of time, 1Guidelines on Preventing and Combating Fraud and Corruption in Projects Financed by International Bank for Reconstruction and Development Loans and the International Development Agency Credits and Grants, dated October 15, 2006, and revised in January 2011 and July 2016, as they may be revised from time to time. 7 (i) to be awarded or otherwise benefit from a Bank-financed contract, financially or in any other manner;2 (ii) to be a nominated3 sub-contractor, consultant, manufacturer or supplier, or service provider of an otherwise eligible firm being awarded a Bank-financed contract; and (iii) to receive the proceeds of any loan made by the Bank or otherwise to participate further in the preparation or implementation of any Bank-financed project. We understand that we may be declared ineligible as set out above upon: a. completion of World Bank Group sanctions proceedings according to its prevailing sanctions procedures; b. cross-debarment as agreed with other international financial institutions (including multilateral development banks); c. the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement; or d. temporary suspension or early temporary suspension in connection with an ongoing World Bank Group sanctions proceeding. For avoidance of doubt, the foregoing effects of ineligibility do not extend to a sanctioned firm’s or individual’s execution of its ongoing Bank-financed contracts (or its ongoing sub-agreements under such contracts) that are not the subject of a material modification, as determined by the Bank. We shall permit, and shall cause our sub-contractors, sub-consultants, agents (whether declared or not), personnel, consultants, service providers or suppliers, to permit the Bank to inspect4 all accounts, records, and other 2 For the avoidance of doubt, a sanctioned party’s ineligibility to be awarded a contract shall include, without limitation, (i) applying for pre-qualification, expressing interest in a consultancy, and bidding, either directly or as a nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider, in respect of such contract, and (ii) entering into an addendum or amendment introducing a material modification to any existing contract. 3 A nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider (different names are used depending on the particular bidding document) is one which has been: (i) included by the bidder in its pre-qualification application or bid because it brings specific and critical experience and know-how that allow the bidder to meet the qualification requirements for the particular bid; or (ii) appointed by the Borrower. 4 Inspections in this context are usually investigative (i.e., forensic) in nature: they involve fact-finding activities undertaken by the Bank or persons appointed by the Bank to address specific matters related to investigations/audits, such as evaluating the veracity of an allegation of possible Fraud and Corruption, through the appropriate mechanisms. Such activity includes but is not limited to accessing and examining a firm's or individual's financial records and information, and making copies thereof as relevant; accessing and examining any 8 documents relating to the procurement process and/or contract execution (in the case of award), and to have them audited by auditors appointed by the Bank. We agree to preserve all accounts, records, and other documents (whether in hard copy or electronic format) related to the procurement and execution of the contract. Name of the Bidder/Consultant: Name of the person duly authorized to sign the Bid/Proposal on behalf of the Bidder/Consultant: Title of the person signing the Letter: other documents, data, and information (whether in hard copy or electronic format) deemed relevant for the investigation/audit, and making copies thereof as relevant; interviewing staff and other relevant individuals; performing physical inspections and site visits; and obtaining third-party verification of information. 9 PROCUREMENT Malawi : Malawi Governance to Enable Service Delivery Project PLAN General Information Country: Malawi Bank’s Approval Date of the Original Procurement Plan: 2019-02-21 2021-05-24 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P164961 GPN Date: Project Name: Malawi Governance to Enable Service Delivery Project Loan / Credit No: IDA / V2660, IDA / D5980 National Local Government Finance Committee Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MW-NLGFC-149068-GO-RFQ Local Government Request for Single Stage - One / Procurement of ICT IDA / V2660 Performance Improvement Post Limited 9,027.00 11,112.34 Completed 2019-12-09 2019-12-11 2019-12-23 2020-04-30 2020-01-20 2020-06-05 Quotations Envelope equipment Support MW-NLGFC-238107-GO-RFQ Local Government Pending Request for Single Stage - One / Procurement of ICT IDA / D5980 Performance Improvement Post Limited 42,000.00 0.00 Implementati 2021-06-09 2021-06-25 2021-07-16 Quotations Envelope Equipment Support on NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MW-NLGFC-197512-CS-CQS Consultant / Consultancy Services for Performance-Based Financing IDA / D5980 Post Qualification Open - National 300,000.00 359,509.78 Completed 2020-10-04 2020-10-04 2020-10-18 2020-11-01 2020-10-20 2020-11-21 2020-11-03 2020-12-19 2020-11-24 2021-06-17 2021-05-21 Conducting Local Authority for Service Delivery Selection Performance Assessment MW-NLGFC-235745-CS- QCBS / Consultancy Services Performance-Based Financing Quality And Cost- Under for Conducting Local IDA / D5980 Post Open - International 300,000.00 0.00 2021-05-30 2021-05-25 2021-06-14 2021-07-05 2021-08-02 2021-08-09 2021-09-13 2021-10-18 2022-04-16 for Service Delivery Based Selection Implementation Authority Performance Assessment INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MW-NLGFC-98182-CS-CDS / Local Government Performance Based Grant IDA / V2660 Post Direct Selection Direct 270,000.00 318,610.00 Completed 2019-02-08 2019-02-22 2019-02-20 2019-03-11 2019-04-15 2019-04-15 2019-07-14 2019-12-19 Design and National Local Government Finance Committee Support MW-NLGFC-149364-CS- Local Government Individual INDV / Deputy Project IDA / V2660 Performance Improvement Post Consultant Limited 39,000.00 39,000.00 Completed 2019-12-06 2019-05-23 2019-12-11 2019-10-08 2019-12-13 2019-10-08 2019-12-15 2019-06-07 2020-06-30 2020-12-18 Coordinator (2) Support Selection MW-NLGFC-149365-CS- Local Government Individual INDV / Deputy Project IDA / V2660 Performance Improvement Post Consultant Limited 39,000.00 39,000.00 Completed 2019-12-10 2019-05-23 2019-12-13 2019-06-04 2019-12-14 2019-10-08 2019-12-16 2019-09-30 2020-07-04 2020-12-18 Coordinator (1) Support Selection MW-NLGFC-149344-CS- Local Government Individual INDV / Project Coordinator - IDA / V2660 Performance Improvement Post Consultant Direct 45,500.00 45,000.00 Completed 2019-12-10 2019-05-23 2019-12-12 2019-06-04 2019-12-16 2019-06-07 2019-12-20 2019-09-30 2020-06-30 2020-12-18 Preparatory phase of GESD Support Selection Project MW-NLGFC-150619-CS- Local Government Individual INDV / Consultancy to IDA / V2660 Performance Improvement Prior Consultant Direct 5,000.00 0.00 Canceled 2019-12-18 2019-12-29 2020-01-19 2020-02-23 2020-08-21 undertake Economic Analysis Support Selection for GESD Project MW-NLGFC-162841-CS-CDS / Technical Assistance in the preparation of Thematic Performance-Based Financing IDA / V2660 Post Direct Selection Direct 80,000.00 52,238.00 Signed 2020-03-15 2020-03-04 2020-03-21 2019-12-16 2020-04-14 2020-04-30 2020-10-11 Performance Improvement for Service Delivery Plans and Finalisation of the LAPA Tool MW-NLGFC-150619-CS- Local Government Individual INDV. / Consultancy to IDA / V2660 Performance Improvement Post Consultant Direct 5,000.00 4,400.00 Completed 2019-11-20 2019-11-20 2019-11-30 2019-12-16 2019-12-21 2020-01-06 2020-01-25 2020-01-21 2020-02-24 2020-02-06 undertake Economic Analysis Support Selection for the GESD Project MW-NLGFC-184482-CS- Local Government Individual INDV / Procurement of a IDA / V2660 Performance Improvement Post Consultant Limited 50,000.00 62.81 Signed 2020-07-20 2020-07-17 2020-07-22 2020-07-23 2020-08-05 2020-10-20 2020-08-14 2020-10-20 2021-02-10 Communication Consultant Support Selection Page 1 MW-NLGFC-198112-CS- Individual Adaptive Management and INDV / Procurement of Project IDA / D5980 Post Consultant Open 36,000.00 86,638.09 Signed 2020-09-20 2020-09-20 2020-11-08 2020-10-19 2020-11-29 2021-01-25 2021-01-03 2021-03-24 2022-01-03 Innovation Support Coordinator Selection MW-NLGFC-198126-CS- Individual Adaptive Management and Under INDV / Procurement of IDA / D5980 Post Consultant Open 24,000.00 0.00 2020-09-20 2020-09-20 2020-11-08 2020-10-19 2020-11-29 2021-01-03 2022-01-03 Innovation Support Implementation Procurement Officer Selection MW-NLGFC-198119-CS- Individual Adaptive Management and Under INDV / Procurement of IDA / D5980 Post Consultant Open 24,000.00 0.00 2020-09-20 2020-09-20 2020-11-08 2020-10-19 2020-11-29 2021-01-03 2022-01-03 Innovation Support Implementation Training Officer Selection MW-NLGFC-198110-CS- Individual Adaptive Management and Under INDV / Procurement of IDA / V2660 Post Consultant Open 24,000.00 0.00 2020-09-20 2020-10-20 2020-11-08 2020-11-29 2021-01-03 2022-01-03 Innovation Support Implementation Planning Officer Selection MW-NLGFC-198134-CS- Individual INDV / Procurement of Adaptive Management and Under IDA / D5980 Post Consultant Open 24,000.00 0.00 2020-09-20 2020-09-20 2020-11-08 2020-11-29 2021-01-03 2022-01-03 Environmental and Social Innovation Support Implementation Selection safeguards Officer MW-NLGFC-198130-CS- Individual INDV / Procurement of Adaptive Management and IDA / D5980 Post Consultant Open 24,000.00 16,762.99 Signed 2020-09-20 2020-09-20 2020-11-08 2020-10-19 2020-11-29 2020-11-13 2021-01-03 2020-12-03 2022-01-03 Communication and outreach Innovation Support Selection Officer MW-NLGFC-198128-CS- Individual Adaptive Management and INDV / Procurement of Budget IDA / D5980 Post Consultant Open 24,000.00 15,366.07 Signed 2020-09-20 2020-09-20 2020-11-08 2020-10-19 2020-11-29 2020-11-27 2021-01-03 2021-02-25 2022-01-03 Innovation Support Analyst Selection Page 2 PROCUREMENT PLAN (Textual Part) Project information: Nepal, [Rural Economic and Enterprise Development Project] [P170215] Project Implementation agency: [Ministry of Agriculture and Livestock Development] Date of the Procurement Plan: September 1, 2020 Period covered by this Procurement Plan: [January 1, 2021 – July 1, 2022] Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used, with applicable caveats as follows. National Procurement Procedures: These procedures are applicable for the procurement of goods, works and non-consulting services only. In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market, as agreed in the Procurement Plan tables in STEP, the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Nepal’s Public Procurement Act, 2007, as amended by Amendment 2073 (2016) – (1st Amendment) and the Public Procurement Regulation, 2007, as amended by 10th Amendment ((27 Apr 2020)), such arrangements shall be subject to paragraph 5.4 of the Bank’s Procurement Regulations and the following conditions: 1) Model bidding documents, including contract conditions agreed with the Bank (as amended from time to time), shall be used. Bidding documents shall be made available, by mail or in person, or through e-GP portal to all who are willing to pay the required fee. 2) The eligibility of bidders shall be as defined under Section III of the Procurement Regulations. Accordingly, no bidder or potential bidder shall be declared ineligible for contracts financed by the Bank for reasons other than those provided in Section III of the Procurement Regulations; 3) The request for bids / request for proposals document shall require that Bidders / Proposers submitting Bids / Proposals present a signed acceptance (in the form attached) at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. 4) Qualification criteria (in case pre-qualifications were not carried out) shall be stated in the bidding documents for all contracts, irrespective of the value, and if a registration process is required, a foreign firm declared as the lowest evaluated bidder shall be given a reasonable opportunity to register, without let or hindrance. 5) Procurement Documents include provisions, as agreed with the Bank, intended to adequately mitigate against environmental, social (including sexual exploitation and abuse and gender-based violence), health and safety (“ESHS”) risks and impacts. 6) Performance security should be an amount of five (5) to ten (10) percent of the contract price and shall not be increased merely based on comparison of the bid price of awarded bidders with the pre-bid cost estimate. 7) If a contract is terminated because of fundamental breach of contract by the contractor, the amount to be recovered from the contractor representing the employer’s additional costs for completing the contract shall be provisioned as agreed with the Bank in model bidding documents. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable. Procurement of Second-Hand Goods as specified under paragraph 5.11 of the Procurement Regulations: Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is applicable for those contracts identified in the Procurement Plan tables; Works: is applicable for those contracts identified in the Procurement Plan tables PROCUREMENT Nepal : Rural Enterprise and Economic Development Project PLAN General Information Country: Nepal Bank’s Approval Date of the Original Procurement Plan: 2020-09-11 2021-05-27 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P170215 GPN Date: 2021-05-18 Project Name: Rural Enterprise and Economic Development Project Loan / Credit No: / , IDA / 67870 M Executing Agency(ies): inistry of Agriculture and Livestock Development WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned NP-MOALD-236984-CW-RFQ- Request for Pending Component 4: Project Request for Single Stage - One 2021-12- OPD-PARQUETING / Floor IDA / 67870 Post Limited Quotations (Non 8,490.00 0.00 Implementat 2021-06-04 2021-06-29 Management Quotations Envelope 26 Parqueting of OPD building Bank-SPD) ion NP-MOALD-236985-CW-RFQ- OPD-MAINTENANCE / Request for Pending Component 4: Project Request for Single Stage - One 2021-07- Maintenance of OPD building: IDA / 67870 Post Limited Quotations (Non 16,980.00 0.00 Implementat 2021-06-03 2021-06-28 Management Quotations Envelope 15 Wiring, Painting, Toilet Bank-SPD) ion renovation GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NP-MOALD-189764-GO-RFB / Procurement of 4WD Service Utility Vehicles 1 Nos, 4WD Component 4: Project Single Stage - One / Post Request for Bids Open - National 742,000.00 0.00 Canceled 2021-01-01 2021-01-06 2021-02-05 2021-03-07 2021-03-28 2021-05-27 Double Cab Pickups 5 Nos Management Envelope and 2WD Cars 3 Nos for OPD and ECOs. NP-MOALD-235502-GO-DIR- Under Component 4: Project 1 / Procurement of SUV cars IDA / 67870 Post Direct Selection Direct 169,650.00 152,972.99 Implementati 2021-05-26 2021-06-01 2021-05-29 2021-06-16 2021-06-16 2021-07-03 Management for OPD (3 Nos) on NP-MOALD-235990-GO-RFQ- DHUNKUTA-FRNITURE / Pending Furniture and Furnishing: Component 4: Project Request for Single Stage - One IDA / 67870 Post Limited 3,932.00 0.00 Implementati 2021-06-05 2021-07-13 2022-01-09 ECO, Dhankuta: Ofice table Management Quotations Envelope on and Chair, Sofa, Steel Cabinet, Carpet and Curtains NP-MOALD-235993-GO-RFQ- BARDIBAS-FRNITURE / Pending Furniture and Furnishing: Component 4: Project Request for Single Stage - One IDA / 67870 Post Limited 3,932.00 0.00 Implementati 2021-06-05 2021-07-13 2022-01-09 Ofice table and Chair, Sofa, Management Quotations Envelope on Steel Cabinet, Carpet and Curtains NP-MOALD-235996-GO-RFQ- BUTWAL-FRNITURE / Furniture Pending Component 4: Project Request for Single Stage - One and Furnishing: Ofice table IDA / 67870 Post Limited 3,932.00 0.00 Implementati 2021-06-05 2021-07-13 2022-01-09 Management Quotations Envelope and Chair, Sofa, Steel Cabinet, on Carpet and Curtains NP-MOALD-235997-GO-RFQ- DADELDHURA-FRNTRE / Pending Furniture and Furnishing: Component 4: Project Request for Single Stage - One IDA / 67870 Post Limited 3,932.00 0.00 Implementati 2021-06-05 2021-07-13 2022-01-09 Ofice table and Chair, Sofa, Management Quotations Envelope on Steel Cabinet, Carpet and Curtains NP-MOALD-189777-GO-RFB / Procurement of 50 Nos of Component 4: Project Single Stage - One / Post Request for Bids Open - National 104,165.00 0.00 Canceled 2021-01-15 2021-01-20 2021-02-19 2021-03-21 2021-04-11 2021-06-10 two wheelers (Motorcycles) for Management Envelope OPD and ECOs NP-MOALD-189784-GO-RFB / Procurement of Branded Desktop Computer 50 Nos, Multifunction Laser Printer 10 Nos, Laser Printer 40 Nos, Component 4: Project Single Stage - One / Post Request for Bids Open - National 102,125.00 0.00 Canceled 2021-02-01 2021-02-06 2021-03-08 2021-04-07 2021-04-28 2021-07-27 Branded Laptop 20 Nos, Management Envelope UPS50 Nos, Multimedia Projector 5 Nos, Heavy Duty Photocopier 1 Nos, Medium Duty Photocopier 4 Nos. NP-MOALD-189793-GO-RFQ Component 4: Project Request for Single Stage - One / Procurement of furniture / Post Open - National 16,665.00 0.00 Canceled 2021-01-06 2021-03-01 2021-04-30 Management Quotations Envelope and furnishing for OPD. NP-MOALD-235981-GO-RFQ- OPD-FURNITURE1 / Procurement of Furniture: Ofice table and chair set 16 Pending Component 4: Project Request for Single Stage - One Nos, Sofa 6 Nos, Table for IDA / 67870 Post Limited 13,499.00 0.00 Implementati 2021-06-04 2021-07-04 2021-07-15 Management Quotations Envelope meeting hall 3 Nos. Chair for on Meeting hall 15 Nos, Team table 2 Nos., Curtains and Carpets NP-MOALD-236991-GO-DIR- Pending OPD-MOTORCYCLE / Component 4: Project IDA / 67870 Post Direct Selection Direct 18,421.00 0.00 Implementati 2021-06-01 2021-06-04 2021-06-21 2021-07-15 Procurement of Motorcycle: Management on Motorcycle 7 Nos NP-MOALD-236988-GO-DIR Pending Component 4: Project / Procurement of Scooter: IDA / 67870 Post Direct Selection Direct 10,187.00 0.00 Implementati 2021-06-01 2021-06-04 2021-06-18 2021-06-18 Management Scooter 4 Not on Page 1 NP-MOALD-236995-GO-RFQ- Pending Component 4: Project Request for Single Stage - One OPD-FURNISHING / Furnishing IDA / 67870 Post Limited 3,396.00 0.00 Implementati 2021-06-05 2021-07-07 2021-07-15 Management Quotations Envelope OPD on NP-MOALD-237009-GO-RFQ- OPD-OE1 / Office Equipment Pending Component 4: Project Request for Single Stage - One for OPD: Photocopy 1No, TV 1 IDA / 67870 Post Limited 13,245.00 0.00 Implementati 2021-06-05 2021-07-02 2021-07-16 Management Quotations Envelope No, Projector 1 No, Camera 1 on No, Printer 12 No. NP-MOALD-237008-GO-RFQ- OE-OPD / Desktop and Pending Component 4: Project Request for Single Stage - One Laptops for OPD and ECOs: IDA / 67870 Post Limited 25,000.00 0.00 Implementati 2021-06-04 2021-07-01 2021-07-15 Management Quotations Envelope Branded Desktop Computer on 13 Nos, Laptop 11 Nos NP-MOALD-238100-GO-RFQ- KITCHEN / Procurement Pending Kitchenware: Refrigerator, Component 4: Project Request for Single Stage - One IDA / 67870 Post Limited 1,095.00 0.00 Implementati 2021-06-10 2021-07-07 2021-07-15 Water Boiler, Vaccume Management Quotations Envelope on cleaner, Induction stove, cooking gas and stove. NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NP-MOALD-189836-CS- QCBS / Procurement of Component 4: Project Quality And Cost- Pending / Prior Open - International 2,800,000.00 0.00 2021-02-01 2021-02-22 2021-04-07 2021-05-05 2021-06-04 2021-07-09 2021-08-06 2025-07-16 Technical Assistance Firm for Management Based Selection Implementation OPD. NP-MOALD-189868-CS-LCS Component 4: Project Least Cost Pending / Consultancy Services of MIS / Post Open - National 40,000.00 0.00 2021-06-15 2021-07-06 2021-08-19 2021-09-16 2021-10-16 2021-11-20 2021-12-25 2022-06-23 Management Selection Implementation Development NP-MOALD-193730-CS- QCBS / Consulting Services Component 4: Project Quality And Cost- Pending / Post Open - National 50,000.00 0.00 2021-02-25 2021-03-18 2021-05-01 2021-05-29 2021-06-28 2021-08-02 2021-09-06 2022-02-03 for conducting baseline Management Based Selection Implementation survey. NP-MOALD-194882-CS- Component 2: Strengthening QCBS / Intermediary the entrepreneurship Quality And Cost- Pending / Post Open - National 300,000.00 0.00 2021-05-10 2021-05-31 2021-07-14 2021-08-11 2021-09-10 2021-10-15 2021-11-19 2024-11-18 Institution to build capacity of ecosystem in the federal Based Selection Implementation agri-SMEs structure INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NP-MOALD-238102-CS- Individual INDV_GOM / Individual Component 4: Project IDA / 67870 Post Consultant Limited 3,820.00 0.00 Under Review 2021-06-07 2021-06-23 2021-06-08 2021-06-12 2021-06-15 2021-12-15 Consultant: Grant Operating Management Selection Manual NP-MOALD-190735-CS- Individual INDV / Recruitment of Component 4: Project IDA / 67870 Post Consultant Open 16,267.00 0.00 Under Review 2021-06-11 2021-06-16 2021-07-12 2021-07-20 2021-08-10 2022-07-15 financial management Management Selection specialist NP-MOALD-189867-CS- Individual Component 4: Project INDV / Monitoring and IDA / 67870 Post Consultant Open 106,158.00 0.00 Under Review 2021-06-11 2021-06-16 2021-07-12 2021-07-16 2021-08-11 2025-07-15 Management Evaluation of Expert Selection NP-MOALD-189828-CS- Individual INDV / Procurement of Component 4: Project Under IDA / 67870 Prior Consultant Open 59,500.00 0.00 2021-06-11 2021-06-16 2021-07-14 2021-07-18 2021-08-04 2025-07-31 individual Procurement Management Implementation Selection Specialist. NP-MOALD-189865-CS- Individual Component 4: Project INDV / Selection of social IDA / 67870 Post Consultant Open 16,267.00 0.00 Under Review 2021-06-11 2021-06-24 2021-07-30 2021-08-20 2021-09-24 2022-03-23 Management safeguard specialist Selection NP-MOALD-189866-CS- Individual Component 4: Project INDV / Selection of IDA / 67870 Post Consultant Open 16,267.00 0.00 Under Review 2021-06-11 2021-06-24 2021-07-25 2021-08-15 2021-09-19 2022-03-18 Management Environment Safeguard Expert Selection Page 2 Procurement Plan for MITP project I. General 1. Bank’s approval Date of the procurement Plan 24th July 2019 2. Date of General Procurement Notice: 15th July 2019 3. Period covered by this procurement plan: The procurement period of project covered from year July 2019 to Dec 2020 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Threshold Comments US$ 1. ICB and LIB (Goods) Above 3000 000 2. NCB (Goods) Less than 3000 000 3. NCB (Non-Consultant Services) Do 4. ICB (Works) Above 40 000 000 5. NCB (Works) Less 40 000 000 6. National shopping Less than 100 000 2. Prequalification. NA. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: NA 4. Reference to (if any) Project Operational/Procurement Manual: Project Procurement Manual will be prepared by MIDFC 5. Any Other Special Procurement Arrangements: Retroactive financing is applicable for this project 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness ( including those that are subject to retroactive financing and advanced procurement) [List the Packages which require Bank’s prior review first and then the other packages] 1 2 3 4 5 6 7 Ref. Descripti Estimat Packages Dome Review Comme No. on ed stic by Bank nts Cost Prefe (Prior / rence Post) July 9, 2010 US$ (yes/ million no) Summary Nil Nil of the ICB (Works) Summary Nil Nil of the ICB (Goods) Summary 100 100 NA Post Nil of the NCB (Works) Road construct ion & rehabilit ation Summary Nil Nil of the NCB (Goods) Summary Nil nil of the ICB (Non- Consultant Services) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comments Threshold 1. Competitive Methods (Firms) Above US$ 1,000,000 2. Single Source (Firms) Do 3. Individual Above US$ 300,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_800,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of Procurement Regulation. 3. Any Other Special Selection Arrangements: Retroactive financing is applicable . 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 July 9, 2010 Ref. No. Description Estimat Package Review Comment of ed s by Bank s Assignmen Cost (Prior / t US$ Post) million Summary Nil of number of contracts that will be let under QCBS Summary 2.4 3 Post All are of number review CQS of contracts that will be let under other methods July 9, 2010 PROCUREMENT India : Meghalaya Integrated Transport Project PLAN General Information Country: India Bank’s Approval Date of the Original Procurement Plan: 2019-09-10 2021-05-24 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P168097 GPN Date: 2019-07-15 Project Name: Meghalaya Integrated Transport Project Loan / Credit No: IBRD / P4980, IBRD / 91690 M Executing Agency(ies): eghalaya infrastructure Development Finance Corporation WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 2: Asset IN-MIDFC-199396-GO-RFQ / Pending Management, Institutional Request for Single Stage - One Office Supplies and Electronic IBRD / P4980 Post Limited 66,000.00 0.00 Implementati 2020-10-27 2020-11-22 2020-12-22 Effectiveness and Transport Quotations Envelope Equipments for the MITP on Services IN-MIDFC-201712-GO-RFQ / Component 2: Asset Procurement of three (3) Pending Management, Institutional Request for Single Stage - One office Vehicles under the IBRD / P4980 Post Limited 52,000.00 0.00 Implementati 2020-11-03 2020-11-20 2020-12-20 Effectiveness and Transport Quotations Envelope Meghalaya Integrated on Services Transport Project (MITP) NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-MIDFC-183421-CS-CQS / Hiring an agency for Component 1: Effective Consultant Under conducting a short study on IBRD / P4980 delivery and maintenance of Post Qualification Open - National 264,000.00 0.00 2020-07-12 2019-03-11 2020-08-02 2020-09-15 2019-09-17 2020-10-15 2020-07-02 2020-11-19 2021-02-17 Implementation "Sustainable Mobility Future transport infrastructure Selection for Meghalaya (SMFM)" IN-MIDFC-133416-CS-QCBS Quality And Cost- / Project Management IBRD / P4980 Prior Open - International 1,572,415.00 0.00 Canceled 2019-09-10 2019-09-20 2019-10-15 2019-11-05 2019-11-11 2019-12-16 2019-12-26 2020-01-08 2020-02-14 2023-02-13 Based Selection Consultancy INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-MIDFC-162085-CS-CDS / Hiring KMPG for the preparation of the SDG framework for the state of Meghalaya. Component 3: Project As part of Vision 2030 for IBRD / P4980 Management and Prior Direct Selection Direct 122,863.00 0.00 Canceled 2020-07-01 2020-07-08 2020-08-01 2020-10-30 Meghalaya, the Government Implementation has taken series of initiatives to achieve SDGs. And therefore need a identify the indicators and develop a long term mon IN-MIDFC-183413-CS-CDS / Hiring CSIR-CRRI to develop an Integrated Transport Network Development Plan Component 1: Effective (ITNDP) to facilitate systematic Under IBRD / P4980 delivery and maintenance of Post Direct Selection Direct 270,000.00 0.00 2020-07-10 2020-01-24 2020-07-20 2020-09-23 2021-09-23 growth of the transport Implementation transport infrastructure network to realise the state’s Vision, for establishing transport network development. IN-MIDFC-183692-CS-CDS / Hiring KPMG for the Component 3: Project Under development of the UN SDG IBRD / P4980 Management and Post Direct Selection Direct 140,000.00 0.00 2020-07-15 2020-01-17 2020-07-22 2020-08-15 2021-08-15 Implementation Pilot Implementation program Implementation in the state of Meghalaya. IN-MIDFC-189263-CS-CDS / Hiring an agency for Component 2: Asset Production of a short Clip/film Management, Institutional Pending on behalf of Public Works IBRD / P4980 Post Direct Selection Direct 920.00 0.00 2020-08-28 2020-08-31 2020-09-04 2020-09-07 Effectiveness and Transport Implementation Department for the Services “Meghalaya Integrated Transport Project Page 1 IN-MIDFC-205437-CS-INDV / DPR Preparation of approach Component 1: Effective Individual roads and trekking paths for Pending IBRD / 91690 delivery and maintenance of Post Consultant Limited 24,500.00 0.00 2020-11-20 2020-11-25 2020-11-30 2020-12-10 2021-06-08 last mile connectivity to the Implementation transport infrastructure Selection Tourist Places in the State of Meghalaya. IN-MIDFC-227169-CS-CDS / Planning Department of Government of Meghalaya vide Letter no: PLR/41/2020/5, Dated 11th Component 1: Effective Under June 2020 requested NISG for IBRD / 91690 delivery and maintenance of Post Direct Selection Direct 237,000.00 0.00 2021-04-05 2020-06-15 2021-04-15 2021-06-19 2023-06-19 Implementation three resources namely transport infrastructure Project Manager, Manager and Project Manager – MIS & Dashboard to cater the necessary requirements for the Project IN-MIDFC-235982-CS-CDS / Allocation of additional consulting service to KPMG for Component 1: Effective Under the preparation of Financial IBRD / 91690 delivery and maintenance of Post Direct Selection Direct 87,200.00 0.00 2021-05-31 2021-04-27 2021-06-10 2021-08-14 2022-02-10 Implementation and Implmentation plan for transport infrastructure the Enhanced Mobility project envisioned under MITP Page 2 PROCUREMENT PLAN (Mandatory Requirements) BANGLADESH SCALNG UP RENEWABLE ENERGY PROJECT (P161869) PROJECT IMPLEMENTATION AGENCIES: Electricity Generation Company of Bangladesh (EGCB) Infrastructure Development Company Limited (IDCOL) Sustainable and Renewable Energy Development Authority (SREDA) Period covered by this Procurement Plan: Entire Project Period Preamble In accordance with paragraph 5.9 of the World Bank Procurement Regulations for IPF Borrowers, July 2016 revised November 2017 (“Procurement Regulations”), the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to record all procurement actions for the Project, including preparing, updating and clearing its Procurement Plan, and seeking and receiving the Bank’s review and No-objection to procurement actions as required. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: The Bank’s Standard Procurement Documents (SPDs) shall be used for goods, works and non-consulting services where international competition is required and for all consulting services, including their respective forms of contract. National Procurement Arrangements: In accordance with paragraph 5.3 of the World Bank Procurement Regulations, when approaching the national market, as agreed in the Procurement Plan, the country’s own 1 procurement procedures may be used. These procurement procedures shall be consistent with the Bank’s Core Procurement Principles and ensure that the Bank’s Anti-Corruption Guidelines and Sanctions Framework and contractual remedies set out in its Legal Agreement apply. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Public Procurement Act 2006 and the Public Procurement Rules 2008, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions: 1) Lottery in award of contracts shall not be allowed; 2) Bidders’ qualification[s]/experience requirement[s] shall be mandatory; 3) Bids shall not be rejected based on percentage above or below the estimated cost; 4) Model Bidding Documents agreed with the Bank shall be used for all national open competitive procurement; 5) The eligibility of bidders shall be as defined under Section III of the Procurement Regulations. Accordingly, no bidder or potential bidder shall be declared ineligible for contracts financed by the Bank for reasons other than those provided in Section III of the Procurement Regulations; 6) The request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance (in the form attached) at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. When the Borrower uses other national procurement arrangements (other than national open competitive procurement), such as limited/restricted competitive bidding, request for quotations/shopping, direct contracting), such arrangements shall be consistent with the above requirements. As per paragraph 5.4 of the Procurement Regulations, the “Letter of Acceptance of the World Bank’s Anticorruption Guidelines and Sanctions Framework” as attached to this document shall form part of the Model Bidding Documents. Leased Assets: Not Applicable. Procurement of Second Hand Goods: Not Applicable. Domestic preference: as specified under paragraph 5.51 of the Procurement Regulations as follows: 2 Works: Not applicable. Plant/Supply and Installation: Not applicable Hands-on Expanded Implementation Support (HEIS): Not Applicable. Bank’s Procurement Prior Review Thresholds: contracts at or above the thresholds set out in table 1 below are subject to the Bank’s procurement prior review. Table 1: Procurement Prior Review Thresholds (US$ millions) Type of High risk Substantial Moderate Low risk procurement risk risk Works (including 5 10 15 20 turnkey, supply & installation of plant and equipment, and PPP) Goods, information 1.5 2 4 6 technology and non-consulting services 3 Consulting 0.5 1 2 4 services: firms Consulting 0.2 0.3 0.4 0.5 services: Individual Notes: 1. These thresholds apply to all procurement activities regardless of their procurement/selection methods. There is no automatic requirement to undertake prior review for direct selection for value less than these thresholds. Consultant services covers a range of services that are of an advisory or professional nature. 2. In addition to the provisions of Table 1 above, and irrespective of the contract value, the following procurement activities are subject to the Bank’s procurement prior review: (a) procurement processes involving contract negotiations, as described in Section VI, paragraphs 6.34-36, of the Procurement Regulations; (b) competitive dialogue; (c) sustainable procurement; (d) selection of probity assurance providers, as described in Section III, paragraph 3.3 of the Procurement Regulations; and (e) best and final offer. 3. The determination of whether a contract meets the procurement prior review threshold is based on the estimated value of the contract or the package -when the selection document contains more than one lot/slice-, including all taxes and duties payable under the contract. 4 Bid/ Proposal Evaluation Committee: EGCB requires to engage (recruited by EGCB as Consultant) one international technical consultant (solar power plant expert) and one international procurement consultants in their bid/proposal evaluation committee for the procurements of solar power plant and supervision consultant/owner’s engineer. Formation and alteration of the bid/proposal evaluation committee shall be subject to Bank’s no objection. Attachment 1 Letter of Acceptance of the World Bank’s Anticorruption Guidelines and Sanctions Framework1 Date: 1[Drafting note: This document shall be signed by bidders/proposers/consultants and submitted as part of their bids/proposals. In addition, this document shall be signed by the winning bidder/consultant and incorporated as part of the contract.] 5 Invitation of Bids/Proposals No.__________ To: ___________________________________________________________________________ We, along with our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not) consultants and personnel, acknowledge and agree to abide by the World Bank’s policy regarding Fraud and Corruption (corrupt, fraudulent, collusive, coercive, and obstructive practices), as set out and defined in the World Bank’s Anti-Corruption Guidelines2 in connection with the procurement and execution of the contract (in case of award), including any amendments thereto. We declare and warrant that we, along our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not), consultants and personnel, are not subject to, and are not controlled by any entity or individual that is subject to, a temporary suspension, early temporary suspension, or debarment imposed by a member of the World Bank Group, including, inter alia, a cross-debarment imposed by the World Bank Group as agreed with other international financial institutions (including multilateral development banks), or through the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement. Further, we are not ineligible under the laws or official regulations of [Insert name of Employer as per bidding document] or pursuant to a decision of the United Nations Security Council. We confirm our understanding of the consequences of not complying with the World Bank’s Anti-Corruption Guidelines, which may include the following: a. rejection of our Proposal/Bid for award of contract; b. in the case of award, termination of the contract, without prejudice to any other remedy for breach of contract; and 2Guidelines on Preventing and Combating Fraud and Corruption in Projects Financed by International Bank for Reconstruction and Development Loans and the International Development Agency Credits and Grants, dated October 15, 2006, and revised in January 2011 and July 2016, as they may be revised from time to time. 6 c. sanctions, pursuant to the Bank’s Anti-Corruption Guidelines and in accordance with its prevailing sanctions policies and procedures as set forth in the Bank’s Sanctions Framework. This may include a public declaration of ineligibility, either indefinitely or for a stated period of time, (i) to be awarded or otherwise benefit from a Bank-financed contract, financially or in any other manner;3 (ii) to be a nominated4 sub-contractor, sub- consultant, consultant, manufacturer or supplier, or service provider of an otherwise eligible firm being awarded a Bank-financed contract; and (iii) to receive the proceeds of any loan made by the Bank or otherwise to participate further in the preparation or implementation of any Bank-financed project. We understand that we may be declared ineligible as set out above upon: a. completion of World Bank Group sanctions proceedings according to its prevailing sanctions procedures; b. cross-debarment as agreed with other international financial institutions (including multilateral development banks); c. the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement; or d. temporary suspension or early temporary suspension in connection with an ongoing World Bank Group sanctions proceeding. For avoidance of doubt, the foregoing effects of ineligibility do not extend to a sanctioned firm’s or individual’s execution of its ongoing Bank-financed contracts (or its ongoing sub-agreements under such contracts) that are not the subject of a material modification, as determined by the Bank. 3 For the avoidance of doubt, a sanctioned party’s ineligibility to be awarded a contract shall include, without limitation, (i) applying for pre-qualification or initial selection), expressing interest in a consultancy, and bidding, either directly or as a nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider, in respect of such contract, and (ii) entering into an addendum or amendment introducing a material modification to any existing contract. 4A nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider (different names are used depending on the bidding document) is one which has been: (i) included by the bidder in its pre-qualification or initial selection application or bid because it brings specific and critical experience and know-how that allow the bidder to meet the qualification requirements for the particular bid; or (ii) appointed by the Borrower. 7 We shall permit, and shall cause our sub-contractors, sub-consultants, agents (whether declared or not), personnel, consultants, service providers or suppliers, to permit the Bank to inspect5 all accounts, records, and other documents relating to the procurement process and/or contract execution (in the case of award), and to have them audited by auditors appointed by the Bank. We agree to preserve all accounts, records, and other documents (whether in hard copy or electronic format) related to the procurement and execution of the contract. Name of the Bidder/Proposer/Consultant: Name of the person duly authorized to sign the Bid/Proposal on behalf of the Bidder/Proposer/ Consultant: Title of the person signing the Letter: 5Inspections in this context are usually investigative (i.e., forensic) in nature: they involve fact-finding activities undertaken by the Bank or persons appointed by the Bank to address specific matters related to investigations/audits, such as evaluating the veracity of an allegation of possible Fraud and Corruption, through the appropriate mechanisms. Such activity includes but is not limited to accessing and examining a firm's or individual's financial records and information, and making copies thereof as relevant; accessing and examining any other documents, data, and information (whether in hard copy or electronic format) deemed relevant for the investigation/audit, and making copies thereof as relevant; interviewing staff and other relevant individuals; performing physical inspections and site visits; and obtaining third-party verification of information. 8 PROCUREMENT Bangladesh : Bangladesh Scaling-up Renewable Energy Project PLAN General Information Country: Bangladesh Bank’s Approval Date of the Original Procurement Plan: 2018-12-11 2021-05-26 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P161869 GPN Date: 2021-05-26 Project Name: Bangladesh Scaling-up Renewable Energy Project Loan / Credit No: / , TF / A7640 I Executing Agency(ies): nfrastructure Development Company Limited WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual G-01 UNDER SREP / Pending Commercial Software for TF / A7640 Technical Assistance Post Direct Selection Direct 3,500.00 0.00 Implementati 2020-11-26 2020-11-29 2020-12-02 2021-12-02 IDCOL Solar Rooftop Project on NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual S-01 UNDER SREP / Consultant Consultant for developing Renewable Energy Financing / Post Qualification Open - National 300,000.00 0.00 Canceled 2019-02-03 2019-02-24 2019-03-24 2019-05-05 2019-06-04 2019-09-02 ESCO model and financing Facility (REFF) Selection instruments for IDCOL S-02 UNDER SREP / Consultant for supporting in Consultant Standardization of appraisal / Technical Assistance Post Qualification Open - International 100,000.00 0.00 Canceled 2019-03-03 2019-03-04 2019-06-02 2019-07-22 2019-08-23 2019-11-21 process, Training, Selection Development of guidelines etc. S-03/01 UNDER SREP / Selection of Firm for Quality And Cost- Pending TF / A7640 Technical Assistance Post Open - National 250,000.00 0.00 2019-10-10 2019-10-31 2019-12-14 2020-01-11 2020-02-10 2020-03-16 2020-04-20 2021-04-20 promoting IDCOL Solar Based Selection Implementation Rooftop system S-04 UNDER SREP / Selection Consultant Renewable Energy Financing Pending of Technical Consultant under TF / A7640 Post Qualification Open - International 400,000.00 0.00 2021-04-15 2021-06-14 2021-08-28 2021-09-27 2021-11-01 2023-10-22 Facility (REFF) Implementation REFF Selection INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual S-03 UNDER SREP / Consultant for Promotion and TF / A7640 Technical Assistance Post Direct Selection Direct 250,000.00 0.00 Canceled 2019-03-03 2019-03-13 2019-05-17 2020-05-16 Outreach Page 1 Procurement Plan Education Quality Reform Project of Mongolia I. General 1. Bank’s approval Date of the procurement Plan: 09 August 2016 2. Date of General Procurement Notice: Dec 24, 2016 3. Period covered by this procurement plan: The procurement period of project covered from year Aug 2016 to December 2017 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Threshold Prior Review Threshold Methods Good International >US$1,000, > US$ 500,000 s Competitive 000 Bidding (ICB) National >US$100,00 Competitive 0 Bidding (NCB) Shopping US$5,000, > US$ 1,500,000 s Competitive 000 Bidding (ICB) National >US$200,00 Competitive 0 Bidding (NCB) Shopping US$ 600,000 (QCBS) for firms Quality-Based Assignments meeting Selection (QBS) the requirements of Article 3.2 of the > US$ 200,000 Consultant Guidelines for individual Consulti Selection Based