Project: Bhutan - Hydromet Services and Disaster Resilience Regional Project (P154477) Implementing Agencies: 1. Department of Disaster Management, Ministry of Home & Cultural Affairs 2. Department of Hydromet services, Ministry of Economic Affairs 3. Department of Agriculture, Ministry of Agriculture and Forests PROCUREMENT PLAN Version: 1 Date: March 10, 2016 Procurement Threshold Table Expenditure Contract Value Procurement Method Contracts Subject to Prior Review Category (Threshold) Goods >=US$ 200,000 ICB All contracts <US$ 200,000 NCB All post review DC All contracts <=US$ 50,000 National Shopping Post review Works >= US$2,000,000 ICB All contracts. <US$2,000,000 NCB All post reviw <=US$ 50,000 National Shopping Post review DC All contracts Services >=US$200,000 QCBS /QBS All Contracts <US$200,000 QCBS/ FBS LCS All post review IC All contracts valued US$ 40,000 or more SSS All Contracts Procurement Plan Summary Total estimated Total estimated Total number Total number Number of contract Total value of contract value of value of prior of packages of prior awarded up awarded up to contract (in review contract review to…………….. [Date …………[Date of "000 US$) (in "000 US$) packages of Procurement Plan Procurement Plan as per as per Cover Page] Cover Page] 1 Goods 1405.00 2 Works 960.00 3 Non-Consulting 665.00 Services 4 Consultancy 770.00 Services 3800.00 0.00 0.00 0.00 0.00 0.00 Project Effectiveness date: Project Closing date: Procurement Plan Summary for Department of Disaster Management Total estimated Total estimated Total number Total number Number of contract Total value of contract value of value of prior of packages of prior awarded up awarded up to contract (in review contract review to…………….. [Date …………[Date of "000 US$) (in "000 US$) packages of Procurement Plan Procurement Plan as per as per Cover Page] Cover Page] 1 Goods 455.00 2 Works 960.00 3 Non-Consulting 405.00 Services 4 Consultancy 180.00 Services 2000.00 0.00 0.00 0.00 0.00 0.00 Project Effectiveness date: Project Closing date: PROCUREMENT Bhutan : Hydromet Services and Disaster Resilience Regional project PLAN General Information Country: Bhutan Bank’s Approval Date of the Original Procurement Plan: 2016-06-01 2018-11-09 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P154477 GPN Date: Project Name: Hydromet Services and Disaster Resilience Regional project Loan / Credit No: TF / A3511, TF / A3507, TF / A3513, / Executing Agency(ies): Department of Disaster Management, Ministry of Home & Cultural Affairs, Department of Agriculture, Ministry of Agriculture and Forests, National Center for Hydrology and Meteorology WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BT-DDM-155-CW-RFB / Pending Single Stage - One Construction of National TF / A3513 Post Request for Bids Open - National 0.00 Implementati 2016-12-31 2017-01-05 2017-02-16 2017-03-18 2017-04-22 2018-07-18 Envelope Emergency Operation Center on BT-DDM-159-CW-RFB / Single Stage - One Portable Helicopter fuelling TF / A3513 Post Request for Bids Open - National 56,147.68 Signed 2017-01-31 2017-02-21 2017-04-04 2017-05-04 2017-06-08 2018-07-31 Envelope infrastructure BT-DDM-160-CW-RFB / Pending Development of Helipads in Single Stage - One TF / A3513 Post Request for Bids Open - National 0.00 Implementati 2017-02-28 2017-03-21 2017-05-02 2017-06-01 2017-07-06 2019-01-31 ten Districts, including Envelope on safety fencing GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BT-DHMS-145-GO-RFQ / Pending Procurement of workstations, Request for Single Stage - One TF / A3513 Post Open - National 0.00 Implementati 2017-03-20 2017-05-18 2017-11-14 Software and ICT Quotations Envelope on equipment and training BT-DDM-143-GO-RFQ / Procurement of NEOC Pending Request for Single Stage - One hosted server, high capacity TF / A3513 Post Limited 0.00 Implementati 2017-04-14 2017-07-02 2017-10-30 Quotations Envelope GIS work station including on dual monitors BT-DHMS-141-GO-RFB / Procurement and Installation Open - Single Stage - One TF / A3513 Prior Request for Bids 1,046,651.39 Signed 2016-11-01 2016-11-06 2016-12-18 2017-01-17 2017-02-21 2017-08-20 of 2 ceilometers and one International Envelope wind profiler system BT-DDM-153-GO-RFB / Single Stage - One Procurement of equipments TF / A3513 Prior Request for Bids Open - National 0.00 Canceled 2017-07-31 2017-08-14 2017-09-28 2017-10-28 2017-12-02 2018-06-30 Envelope for NEOC BT-DDM-154-GO-RFB / Procurement of emergency Single Stage - One TF / A3513 Post Request for Bids Open - National 96,321.43 Signed 2017-12-31 2018-01-14 2018-02-25 2018-03-27 2018-05-01 2018-08-29 communication and Envelope coordination items Page 1 BT-DHMS-147-GO-RFQ / Procurement of ice Request for Open - Single Stage - One / Post 0.00 Canceled 2016-10-06 2016-12-10 2017-03-31 penetrating equipment for Quotations International Envelope glacier and Snow studies. BT-DDM-144-GO-DIR / Procurement of ArcGIS TF / A3513 Prior Direct Selection Direct 0.00 Canceled 2019-02-01 2019-03-03 2019-04-28 2019-10-25 software BT-DOA-156-GO-RFB / Pending Procurement of computer, Request for Single Stage - One TF / A3507 Post Limited 0.00 Implementati 2018-09-25 2018-11-20 2019-05-19 Software and ICT Quotations Envelope on equipment BT-DDM-66615-GO-RFQ / Procurement of Equipment Request for Single Stage - One TF / A3513 Post Open - National 5,396.27 Completed 2018-06-23 2018-08-18 2019-02-14 for NEOC through direct Quotations Envelope shopping BT-DDM-66621-GO-RFB / Pending Single Stage - One Procurement of equipment TF / A3513 Prior Request for Bids Open - National 0.00 Implementati 2019-01-01 2019-01-06 2019-02-17 2019-03-19 2019-04-23 2019-10-20 Envelope for NEOC on BT-NCHM-76145-GO-RFQ / Supplying and laying of the Under Underground Power cable for Request for Single Stage - One TF / A3513 Post Limited 0.00 Implementati 2018-09-04 2018-09-24 2018-10-24 Automatic Weather Quotations Envelope on Observation Station (AWOS) at Paro International Airport BT-NCHM-78209-GO-RFQ / Supply & Delivery of the Pending Request for Single Stage - One Hydrological Flow & Flood TF / A3513 Post Limited 0.00 Implementati 2018-09-18 2018-10-25 2019-04-23 Quotations Envelope Forecasting Equipment for on Bhutan BT-DDM-85773-GO-DIR / Procurement of additional equipment( two DC Pending convertors) pertaining to TF / A3513 Post Direct Selection Direct 0.00 Implementati 2018-11-12 2018-11-26 2018-12-31 2019-06-29 procurement of emergency on communication and coordination equipment. NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BT-DDM-2263-NC-DIR / Training of 3 helicopter pilots for 4-6 months in Canada for Royal Bhutan Request for Single Stage - One TF / A3511 Prior Limited 268,322.35 Signed 2016-11-06 2017-01-01 2017-04-30 Helicopter Services under Quotations Envelope Component B: Disaster Preparedness and Response Capacity Improvement. CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 2 BT-DOA-142-CS-QCBS / Design an agromet decision support system, generate Quality And Cost- Open - Under TF / A3507 Post 0.00 2016-11-30 2016-12-20 2017-01-09 2017-02-10 2017-02-20 2017-03-04 2017-03-24 2017-07-22 agromet information products Based Selection International Implementation and disseminate to Dzongkhags (DOA) BT-DDM-161-CS-QCBS / Geomatics system training Quality And Cost- Open - TF / A3513 Post 37,288.52 Signed 2016-11-30 2016-12-21 2017-02-03 2017-03-05 2017-04-04 2017-05-09 2017-06-13 2017-12-10 and DMIS development Based Selection International coaching BT-DDM-162-CS-QCBS / Quality And Cost- Open - TF / A3513 Post 0.00 Canceled 2017-02-15 2017-03-08 2017-04-21 2017-05-19 2017-06-18 2017-07-23 2017-08-27 2018-04-17 Technical Design of NEOC Based Selection International BT-DDM-52705-CS-QCBS / Planning, Designing and Quality And Cost- Open - TF / A3507 Post 0.00 Canceled 2018-03-09 2018-03-09 2018-04-22 2018-05-20 2018-06-19 2018-07-24 2018-08-28 2019-08-28 supervision of NEOC Based Selection International construction BT-DHMS-151-CS-QCBS / Develop a Common Quality And Cost- Open - Operating Platform for TF / A3507 Post 0.00 Canceled 2017-07-15 2017-08-14 2017-10-19 2017-11-16 2017-12-16 2018-01-20 2018-02-24 2019-02-24 Based Selection International automated hydro-met services delivery BT-DDM-77063-CS-QCBS / Planning, preparation of the detailed design and drawings, and supervision of the implementation of the Quality And Cost- Under TF / A3513 Post Open - National 0.00 2018-09-10 2018-10-01 2018-11-14 2018-12-12 2019-01-11 2019-02-15 2019-03-22 2020-03-21 approved design and Based Selection Implementation drawings during the construction for the National Emergency Operation Center (NEOC) INDIVIDUAL CONSULTANTS Page 3