PROCUREMENT PLAN (Textual Part) Project information: Uzbekistan Ferghana Valley Water Resources Management - Phase II (P149610) Project Implementation agency: Agency for Implementation of Projects in Water Sector under Ministry of Water Date of the Procurement Plan: October 2020 Period covered by this Procurement Plan: October 2020 – 31 August 2024 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Public Procurement Law dated January 25, 2018 , such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions: a) Open advertising of the procurement opportunity at the national level - this requirement is met - PPL January 25, 2018: Articles 8; 24; 47; 49; 52; 61. (b) The procurement is open to eligible firms from any country - the requirement is met - PPL January 25, 2018: Articles 17; 28; 29; 34. (c) The request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti- Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights – the requirement is met conditionally - The Bank’s Anti-Corruption Guidelines and Sanctions Framework shall be incorporated into the national bidding documents by adding a page entitled “Letter of Acceptance of the World Bank’s Anti-Corruption Guidelines and Sanctions Framework”. This condition shall be reflected under the list of applicable conditions for National Procurement Arrangements in the textual part of the procurement plan of the project to be financed by the World Bank in Uzbekistan. (d) Contracts with an appropriate allocation of responsibilities, risks, and liabilities - the requirement is met conditionally - This condition shall be reflected under the list of applicable conditions for National Procurement Arrangements in the textual part of the procurement plan of the project to be financed by the WB. (e) Publication of contract award information - the requirement is met - PPL January 25, 2018: Articles 32; 55; 64. (f) Rights for the Bank to review procurement documentation and activities - the requirement is met - PPL January 25, 2018: (g) An effective complaints mechanism - the requirement is met - PPL January 25, 2018: (h) Maintenance of records of the Procurement Process - the requirement is met - PPL January 25, 2018. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable. Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – Not Applicable. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable for those contracts identified in the Procurement Plan tables; Works: is applicable for those contracts identified in the Procurement Plan tables Other Relevant Procurement Information. PROCUREMENT Uzbekistan : Ferghana Valley Water Resources Management - Phase II PLAN General Information Country: Uzbekistan Bank’s Approval Date of the Original Procurement Plan: 2017-08-28 2021-10-26 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P149610 GPN Date: Project Name: Ferghana Valley Water Resources Management - Phase II Loan / Credit No: IDA / 60830, TF / A9862 Ministry of Water Resources Executing Agency(ies): WORKS Procureme Activity Reference No. / Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH nt Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) Justification for Award Type Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual FVWRMP/ICB/01 LOT-1 / Lot 1 "Rehabilitation of main and inter-farm Irrigation canals with structures": • Rehabilitation of main and Component A: Irrigation Single Stage - One 2021-11- inter-farm Irrigation canals IDA / 60830 Prior Request for Bids Open - International 0.00 Canceled 2018-08-10 2018-08-10 2018-08-10 2018-10-05 2018-11-04 2018-11-24 Modernization Envelope 23 with structures - 61.879 km • Volume of Earthworks - 135.5 thousand m3 • Concrete works - 32.9 thousand m3 • Vol FVWRMP/ICB/01 LOT-2 / Lot 2 "Construction of new irrigation wells": • Total number of wells - Component A: Irrigation Single Stage - One 2021-12- 105 (with a drilling diameter IDA / 60830 Prior Request for Bids Open - International 0.00 Canceled 2018-08-10 2018-08-10 2018-08-10 2018-10-05 2018-11-04 2018-12-09 Modernization Envelope 08 of 119 to 400 mm.) • Yield of wells - from 15 to 25 liter/sec. • Depth of wells - from 80 to 170 meters. FVWRMP/ICB/01 LOT-3 / Lot 3 Rehabilitation of Pump Stations": • Rehabilitation of 9 Pump Stations (including Component A: Irrigation Single Stage - One 2021-12- IDA / 60830 Prior Request for Bids Open - International 0.00 Canceled 2018-08-10 2018-08-10 2018-10-05 2018-11-04 2018-12-09 Reconstruction of Pump Modernization Envelope 08 Station Buildings) • Total number of Pump Units - 29 • Capacity of Pump Unit - from 0,25 m3/sec. to 6,3 m3/sec. FVWRMP/ICB/01 / FVWRMP/ICB/01 (Rehabilitation of Padshaota Irrigation Infrastructure in Namangan Region) Component A: Irrigation Single Stage - One 2019-06- IDA / 60830 Prior Request for Bids Open - International 0.00 Canceled 2018-08-17 2018-08-17 2018-08-22 2018-08-17 2018-10-03 2018-11-02 2018-12-07 Consists of the following lots: Modernization Envelope 05 Lot 1 - "Rehabilitation of main and inter-farm Irrigation canals with structures": • Rehabilitation of main and inter-farm Irrigation FVWRMP/ICB/1 / FVWRMP/ICB/01 (Rehabilitation of Padshaota Infrastructure in Namangan Region) Consists of the Component A: Irrigation Single Stage - One 2020-01- following Lots: Lot #1 IDA / 60830 Prior Request for Bids Open - International 0.00 Canceled 2019-04-03 2019-04-08 2019-05-20 2019-06-19 2019-05-21 2019-07-24 Modernization Envelope 20 (Rehabilitation of Canals), Lot #2 (Construction of New Wells) and Lot #3 (Rehabilitation of Pumping Stations) UZ-PIU-119524-CW-RFB / FVWRMP/ICB/01 (Rehabilitation of Padshaota Component A: Irrigation Single Stage - One 15,639,811. 2020-04- IDA / 60830 Prior Request for Bids Open - International Signed 2019-06-18 2019-06-27 2019-06-23 2019-08-04 2018-10-05 2019-09-03 2019-07-16 2019-10-08 2019-04-23 Irrigation Infrastructure in Modernization Envelope 02 05 Namangan Region) Consists of 3 lots. FVWRMP-II/ICB/3-1 / FVWRMP-II/ICB/3-1 Rehabilitation and Component A: Irrigation Single Stage - One 8,346,757.0 2020-05- IDA / 60830 Prior Request for Bids Open - International Signed 2019-07-15 2019-07-19 2019-07-20 2019-07-19 2019-08-31 2019-09-04 2019-09-30 2019-12-11 2019-11-04 2019-12-26 Reconstruction of Existing Modernization Envelope 1 02 Canals and Structures in Andijan Region FVWRMP-II/ICB/2-1 / FVWRMP-II/ICB/2-1 consists of the following lots: Lot-1 “Construction of Component A: Irrigation Single Stage - One 16,535,376. 2020-05- irrigation wells in Ferghana IDA / 60830 Prior Request for Bids Open - International Signed 2019-07-15 2019-07-19 2019-07-20 2019-07-19 2019-08-31 2019-09-04 2019-09-30 2019-12-12 2019-11-04 2019-12-25 Modernization Envelope 84 02 and Kuvasoy districts” Lot-2 “Rehabilitation and reconstruction of existing canals and structures” FVWRMP/ICB/1 LOT-3 / FVWRMP/ICB/01 Lot-3 Component A: Irrigation Single Stage - One 12,059,963. 2020-05- Rehabilitation of Pump IDA / 60830 Prior Request for Bids Open - International Signed 2019-07-15 2019-07-26 2019-07-20 2019-07-26 2019-08-31 2019-09-04 2019-09-30 2019-12-11 2019-11-04 2019-12-30 Modernization Envelope 94 02 Stations in Padshaota Irrigation Infrastructure Page 1 FVWRMP-II/ICB/2-2 / FWRMP- II/ICB/2-2 Rehabilitation of Isfayram-Shahimardon Irrigation Infrastructure: Construction of new Avval- Component A: Irrigation Single Stage - One 2023-08- IDA / 60830 Prior Request for Bids Open - International 0.00 Canceled 2020-04-03 2020-04-15 2020-04-08 2020-04-21 2020-06-07 2020-07-03 2020-07-07 2021-04-09 2020-08-11 Lagon Pump station and Modernization Envelope 11 Rehabilitation and Modernization of Existing Isfayram-Shahimardan Pump Station in Fergana Region FVWRMP-II/ICB/3-2 / FWRMP- II/ICB/3-2 Rehabilitation of Savay-Akburasoy Irrigation Component A: Irrigation Single Stage - One 2023-07- Infrastructure: Rehabilitation IDA / 60830 Prior Request for Bids Open - International 0.00 Canceled 2020-04-03 2020-04-15 2020-04-08 2020-04-21 2020-05-20 2020-07-03 2020-06-19 2021-04-09 2020-07-24 Modernization Envelope 24 and Modernization of Existing Orom and Savay Pump Stations in Andijan Region FVWRMP-II/ICB/2-2/2 / Rehabilitation of Shahimardon Irrigation Infrastructure: Request for Construction of new Avval- Bids - Works Under Component A: Irrigation Single Stage - One 2022-04- Lagon and Rehabilitation and IDA / 60830 Prior Request for Bids Open - International (without 0.00 Implementat 2021-05-21 2021-06-25 2021-05-26 2021-06-26 2021-08-04 2021-09-06 2021-09-03 2021-10-08 Modernization Envelope 06 Modernization of Existing prequalificati ion Isfayram-Shahimardon Pump on) SPD Stations in Fergana Region (re- bidding) FVWRMP-II/ICB/3-2/2 / Rehabilitation of Savay- Request for Akburasoy Irrigation Bids - Works Under Infrastructure: Rehabilitation Component A: Irrigation Single Stage - One 2022-04- IDA / 60830 Prior Request for Bids Open - International (without 0.00 Implementat 2021-05-21 2021-06-25 2021-05-26 2021-06-26 2021-08-04 2021-09-06 2021-09-03 2021-10-08 and Modernization of Existing Modernization Envelope 06 prequalificati ion Orom and Savay-1 Pump on) SPD Stations in Andijan Region (re- bidding) Request for FVWRMP/EUG/W02 / Quotations - Improving working condition Pending Component C: Project Request for Single Stage - One Small Works 2022-03- by ensuring the renovation of TF / A9862 Post Open - National 0.00 Implementat 2021-12-03 2022-01-17 Management Quotations Envelope (Emergency) 23 the PIU office (reconstraction ion SPD - of second floor) Competitive Request for FVWRMP/EUG/W03 / Quotations - Improving working conditions Pending Component C: Project Request for Single Stage - One Small Works 2022-04- by ensuring the renovation of TF / A9862 Post Open - National 0.00 Implementat 2022-01-04 2022-02-04 Management Quotations Envelope (Emergency) 05 the PIU office (reconstruction ion SPD - of third floor) Competitive FVWRMP/EUG/W/05 / Drilling Request for of two irrigation wells. Bids - Works Component B: Support for Single Stage - One 2022-04- Namangan, Uzak village the TF / A9862 Post Request for Bids Open - International (without 0.00 Canceled 2021-08-16 2021-08-21 2021-09-20 2021-10-05 2021-10-15 Agricultural Modernization Envelope 13 180-hectare garden being prequalificati created on rain-fed lands. on) SPD Request for FVWRMP/EUG/W01 / Quotations - Improving working condition Pending Component C: Project Request for Single Stage - One Small Works 2022-03- by ensuring the renovation of TF / A9862 Post Open - National 0.00 Implementat 2021-12-05 2022-01-15 Management Quotations Envelope (Emergency) 02 the PIU office (demolishing of ion SPD - the existing structures) Competitive GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual FVWRMP/EUG/GEQ/1 / IT Component C: Project Request for Single Stage - One TF / A9862 Post Open - National 0.00 Canceled 2020-10-25 2020-12-17 2021-01-13 equipment for PIU Management Quotations Envelope FVWRMP/EUG/GEQ/2 / Component C: Project Request for Single Stage - One TF / A9862 Post Open - National 0.00 Canceled 2020-11-15 2020-12-25 2021-01-05 Vehicles for PIU Management Quotations Envelope FVWRMP/EUG/EQG/1-LOT1 / Procurement of a pilot SPS (solar photovoltaic station) Namangan, Yangikurgan, Component B: Support for Single Stage - One Khakikat KFY Skvazh No. 409, TF / A9862 Post Request for Bids Open - International 94,453.94 Signed 2021-08-16 2021-08-18 2021-08-21 2021-09-20 2021-09-08 2021-10-05 2021-09-28 2021-10-15 2021-09-28 2022-04-13 Agricultural Modernization Envelope 50 kW panels.32kW pump, Installation of a water treatment system with a water capacity of 2000 l / h FVWRMP/EUG/EQG/1-LOT3 / Procurement of a pilot SES (solar photovoltaic plant), Namangan region Chortok Component B: Support for Single Stage - One district Wells No. 25.UNS, 50 TF / A9862 Post Request for Bids Open - International 87,290.56 Signed 2021-08-16 2021-08-16 2021-08-21 2021-09-20 2021-09-08 2021-10-05 2021-09-13 2021-10-15 2021-09-28 2022-04-13 Agricultural Modernization Envelope kW Panel, 32 kW Pump, installation of a water treatment system with a water capacity of 1000 l/h FVWRMP/EUG/EQG/2-LOT1 / Procurement of a pilot SPS (solar photovoltaic station) of 50 kW panels, Ferghana Component B: Support for Single Stage - One TF / A9862 Post Request for Bids Open - International 94,116.96 Signed 2021-08-16 2021-08-18 2021-08-21 2021-09-20 2021-09-08 2021-10-05 2021-09-14 2021-10-15 2021-09-28 2022-04-13 district Okbilol village 210/1, Agricultural Modernization Envelope 32 kW Pump, ECV-10- 120/55. Water treatment plant+C41+A28:X46 FVWRMP/EUG/EQG/2-LOT2 / Procurement of a pilot SPS (solar photovoltaic station) in the Ferghana region, Ok Bilol Component B: Support for Single Stage - One (village), 50 kW panel, 32 kW TF / A9862 Post Request for Bids Open - International 94,232.01 Signed 2021-08-16 2021-08-18 2021-08-21 2021-09-20 2021-09-08 2021-10-05 2021-09-14 2021-10-15 2021-09-28 2022-04-13 Agricultural Modernization Envelope Pump, wells No. 713. Installation of a water treatment system with a water capacity of 2000 l/h Page 2 FVWRMP/EUG/EQG/2-LOT3 / Procurement of a pilot SPS (solar photovoltaic plant), Kuvasai. Sufon village. area Component B: Support for Single Stage - One "Behizor" Ferghana region. TF / A9862 Post Request for Bids Open - International 86,077.32 Signed 2021-08-16 2021-08-16 2021-08-21 2021-09-20 2021-09-08 2021-10-05 2021-09-14 2021-10-15 2021-09-28 2022-04-13 Agricultural Modernization Envelope Kuvasai, 32kW pump, 50kW panel and its installation of a water treatment system with a water capacity of 1000 l/h FVWRMP/EUG/EQG/3-LOT3 / Procurement of a pilot SPS (solar photovoltaic station) Andijon reg, Bulokboshi district. Zhurapolvon vil. Component B: Support for Single Stage - One TF / A9862 Post Request for Bids Open - International 84,302.53 Signed 2021-08-30 2021-08-20 2021-09-04 2021-10-04 2021-09-08 2021-10-19 2021-09-15 2021-11-08 2021-09-28 2022-05-07 Irrigation well # 01-05- Agricultural Modernization Envelope 55.The Panel is 50 kW, the Pump is 32 kW. Installation of a water treatment system with a water capacity of 500 l/h FVWRMP/EUG/EQG/1-LOT2 / Drilling of two irrigation wells in the created garden of 180 Component B: Support for Single Stage - One TF / A9862 Post Request for Bids Open - International 88,562.02 Signed 2021-09-21 2021-08-18 2021-09-26 2021-10-26 2021-09-08 2021-11-10 2021-09-13 2021-11-20 2021-10-08 2022-05-19 hectares on rain-fed lands Agricultural Modernization Envelope located in Uzak MFY, Namangan Region. FVWRMP/EUG/EQG/1-LOT4 / "Purchase of a pilot solar photovoltaic station (SPS) panel with a capacity of 35 kW for power supply of 2 pumps Component B: Support for Request for Single Stage - One TF / A9862 Post Open - International 86,399.84 Signed 2021-09-23 2021-09-27 2021-09-28 2022-09-27 with a capacity of 11 kW and Agricultural Modernization Quotations Envelope 1 set installation of a water treatment system with a water capacity of 1000 l / h for wells No. 202 and No. 401 FVWRMP/EUG/EQG/3-LOT1 / Procurement of a pilot SES (solar photovoltaic station) for Well No. 01-13-08. Pump 26 kW, panel 40 kw. Installation Component B: Support for Single Stage - One TF / A9862 Post Request for Bids Open - International 82,790.45 Signed 2021-08-30 2021-08-18 2021-09-04 2021-10-04 2021-09-08 2021-10-19 2021-09-15 2021-10-29 2021-09-23 2022-10-29 of a water treatment system Agricultural Modernization Envelope with a water capacity of 1000 l/h located at Andijon, Kurgantepa district . Ertibosh MFY. Sharaf Rashidov area FVWRMP/EUG/EQG/3-LOT2 / Procurement of a pilot SPS panel with a capacity of 50 kW for power supply of a pump with a capacity of 32 kW and Component B: Support for Single Stage - One TF / A9862 Post Request for Bids Open - International 66,068.61 Signed 2021-08-30 2021-08-18 2021-09-04 2021-10-04 2021-09-08 2021-10-19 2021-09-15 2021-11-08 2021-09-23 2022-05-07 instal-n of a water treatment Agricultural Modernization Envelope system with a capacity of 2000 l/h for Well No.01-13- 07 located in Ertibosh MFY, Kurgantepa district, Andijan FVWRMP/EUG/EQG/3-LOT4 / Purchase of a pilot FES panel with a capacity of 35 kW for power supply of a pump of 22 kW, installation of a water Component B: Support for Single Stage - One TF / A9862 Post Request for Bids Open - International 66,207.06 Signed 2021-08-30 2021-08-16 2021-09-04 2021-10-04 2021-09-08 2021-10-19 2021-09-15 2021-11-08 2021-09-23 2022-05-07 treatment system with a water Agricultural Modernization Envelope capacity for Well No. 01-11- 2MK located in the village of Cimbulok, Khozhaabad district, Andijan region NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual FVWRMP/CON/1 / The main tasks of the Consultant are: Preparation of the detailed design for construction works and tender documents, as well Component C: Project Quality And Cost- IDA / 60830 Prior Open - International 4,120,410.00 Signed 2017-08-20 2017-09-10 2017-08-29 2017-10-24 2017-11-21 2018-08-30 2017-12-21 2018-11-22 2018-01-25 2018-12-19 2018-03-01 2018-12-20 2019-03-01 as bids evaluation and Management Based Selection preparation of Evaluation Reports, coordination of the reports with authorized agencies of the Republic. FVWRMP/CON/6 / The objective is to express a professional opinion on the project's financial position as Component C: Project Least Cost at the end of December 31, IDA / 60830 Post Open - International 32,640.00 Signed 2018-10-29 2018-11-13 2018-11-13 2018-11-22 2018-12-27 2019-01-09 2019-01-24 2020-02-13 2019-02-23 2019-03-12 2019-03-30 2019-05-19 2019-05-04 2019-05-22 2019-10-31 Management Selection 2018, 2019 and 2020, and of the income and expenditure for the accounting period ending on these dates. FVWRMP/CON/2 / The objective of the services is to monitor and provide feedback on the success in meeting the Component C: Project Quality And Cost- project objectives, and assess IDA / 60830 Prior Open - International 0.00 Canceled 2019-01-10 2019-04-02 2019-01-31 2019-04-18 2019-03-16 2019-04-13 2019-05-13 2019-06-17 2019-07-22 2024-12-31 Management Based Selection its physical, social, and economic impact, the EAMP, the resettlement policy framework requirements. Page 3 FVWRMP/CON/02 / The objective of the services is to monitor and provide feedback on the success in meeting the Component C: Project Quality And Cost- project objectives, and assess IDA / 60830 Prior Open - International 1,028,280.00 Signed 2019-10-08 2019-10-17 2019-10-29 2019-10-17 2019-12-12 2020-02-06 2020-01-09 2020-05-01 2020-02-08 2020-09-15 2020-03-14 2020-11-02 2020-04-18 2020-11-03 2021-04-18 Management Based Selection its physical, social, and economic impact, the EAMP, the resettlement policy framework requirements. FVWRMP/EUG/CON8 / Audit Component C: Project Least Cost TF / A9862 Post Open - National 0.00 Canceled 2020-11-10 2020-12-01 2021-01-14 2021-02-11 2021-03-13 2021-04-17 2021-05-22 2025-03-04 2020-2024 Management Selection FVWRMP/EUG/CON/1 / Consulting services for provision of services such as: a) preparation of bid documentation for Component B: Support for Quality And Cost- Under demonstration plots and/or TF / A9862 Prior Open - International 0.00 2021-03-19 2021-05-05 2021-04-09 2021-05-20 2021-05-19 2021-08-19 2021-06-02 2021-06-09 2021-06-30 2021-07-12 2024-08-31 Agricultural Modernization Based Selection Implementation farmers’ field school and supervision of implementation b) development of the training curriculum and materials, c) conduct trainings FVWRMP/CON/6-1 / The objective is to express a professional opinion on the project's financial position as at the end of December 31, Component C: Project Least Cost Pending IDA / 60830 Post Open - International 0.00 2021-10-18 2021-11-08 2021-12-07 2022-01-04 2022-01-25 2022-03-01 2022-03-16 2024-08-31 2021, 2022, 2023 and 2024, Management Selection Implementation and of the income and expenditure for the accounting period ending on these dates. FVWRMP/EUG/W04 / Preparation of design, cost Consultant estimate for improving Component C: Project TF / A9862 Post Qualification Open - National 0.00 Canceled 2020-10-25 2021-08-10 2020-11-08 2020-11-29 2020-12-29 2021-01-08 2021-02-21 working conditions by Management Selection ensuring the renovation of the PIU office. INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Contract Type Process Status Teams of Reference Identified/Selected Signed Contract Contract Completion No. (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Individual FVWRMP/EUG/CON5 / ITC Component C: Project TF / A9862 Post Consultant Open 0.00 Canceled 2020-11-30 2021-02-03 2021-02-24 2021-03-26 2023-03-24 Consultancy services Management Selection Individual FVWRMP/EUG/CON6 / Legal Component C: Project TF / A9862 Post Consultant Open 0.00 Canceled 2020-11-10 2021-01-19 2021-02-09 2021-03-12 2023-03-24 Consultancy services Management Selection Individual FVWRMP/EUG/CON7 / Component C: Project TF / A9862 Post Consultant Open 0.00 Canceled 2020-11-20 2021-01-18 2021-02-08 2021-03-11 2023-03-24 Gender consultancy services Management Selection FVWRMP/EUG/CON1 / Consultancy for tender documentation, technical Individual needs and cost estimation, Component B: Support for TF / A9862 Prior Consultant Open 0.00 Canceled 2020-11-10 2021-01-19 2021-02-09 2021-03-10 2024-05-20 trainings needs assessment, Agricultural Modernization Selection ToR development and author supervision for intensification and diversification of the crop FVWRMP/EUG/CON3 / Consultancy for tender documentation, technical needs and cost estimation, Individual Component A: Irrigation training needs assessment, TF / A9862 Post Consultant Open 96,120.00 Signed 2021-03-09 2021-03-12 2021-04-19 2021-04-21 2021-04-29 2021-05-18 2021-05-09 2021-05-18 2022-05-09 Modernization ToR development and author Selection supervision for use Solar Energy for Irrigation and Drainage pumps FVWRMP/EUG/CON2 / Consultancy for tender documentation, technical needs and cost estimation, Individual Component B: Support for training needs assessment, TF / A9862 Post Consultant Open 94,800.00 Signed 2021-03-09 2021-03-12 2021-04-19 2021-06-09 2021-04-29 2021-06-17 2021-05-09 2021-06-17 2022-05-09 Agricultural Modernization ToR development and author Selection supervision for introduction of volumetric payment of O&M fees system FVWRMP/CON/4/IPC / Individual Component C: Project International Procurement IDA / 60830 Post Consultant Open 116,826.00 Signed 2021-05-15 2018-06-01 2021-06-08 2017-11-14 2021-06-13 2018-06-01 2021-06-21 2018-06-01 2021-12-18 Management Consultant Selection Individual FVWRMP/EUG/CON/7 / Component B: Support for TF / A9862 Post Consultant Open 0.00 Under Review 2021-10-11 2021-09-05 2021-11-09 2021-11-19 2021-12-04 2024-08-31 Gender Consultancy Services Agricultural Modernization Selection Individual FVWRMP/EUG/CON/05 / ITC Component B: Support for TF / A9862 Post Consultant Open 0.00 Under Review 2021-10-20 2021-09-06 2021-11-23 2021-12-03 2021-12-27 2024-08-31 Consultancy Services Agricultural Modernization Selection FVWRMP/CON/5/IDS / Component A: Irrigation IDA / 60830 Post Direct Selection Direct 0.00 Under Review 2021-10-07 2021-09-13 2021-10-13 2021-10-26 2024-08-26 International Dam Specialist Modernization FVWRMP/CON/5/LGS / Local Component A: Irrigation IDA / 60830 Post Direct Selection Direct 0.00 Under Review 2021-10-07 2021-09-13 2021-10-14 2021-10-26 2024-08-26 Geotechnical specialist Modernization FVWRMP/CON/5/LHS / Local Component A: Irrigation Hydrologist and Hydraulic IDA / 60830 Post Direct Selection Direct 0.00 Under Review 2021-10-07 2021-09-13 2021-10-14 2021-10-26 2024-08-30 Modernization specialist Page 4 FVWRMP/EUG/CON4 / Water Individual Component B: Support for management development TF / A9862 Post Consultant Open 0.00 Canceled 2021-10-24 2021-12-12 2022-01-02 2022-02-06 2024-08-31 Agricultural Modernization consultant Selection Individual FVWRMP/EUG/CON/5 / Legal Component B: Support for TF / A9862 Post Consultant Open 0.00 Canceled 2021-10-15 2021-12-03 2021-12-24 2022-01-28 2024-10-25 Consultancy Services Agricultural Modernization Selection Page 5