PROCUREMENT PLAN (Textual Part) Project: 6O Regional Disaster Vulnerability Reduct. Project (P117871) Implementing agencies: PCU Grenada – Ministry of Finance and SVG – Ministry of Finance, Economic Planning, Sustainable Development, and Information Technology Date of the Procurement Plan: October 23, 2018 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. The Project was approved on June 23, 2011 and is expected to close on Dec. 31, 2018; however, an extension is being processed in parallel at the current time. All works, goods, non-consulting services and consulting services to be procured with this Project’s funds needs to be procured and contracted prior closing date for eligibility purposes. The procurement plan for this Project along with this textual part constitute the Procurement Plan. Procurement Plan The following conditions apply to all the procurement activities foreseen in the Procurement Plan: • The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. • The new Fraud & Corruption clauses shall be incorporated in all contracts to be signed after approval of the procurement plan. PROCUREMENT OECS Countries : Regional Disaster Vulnerability Reduction APL1 - Grenada and St. Vincent and the Grenadines PLAN General Information Country: OECS Countries Bank’s Approval Date of the Original Procurement Plan: 2018-10-31 2021-02-22 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P117871 GPN Date: Project Name: Regional Disaster Vulnerability Reduction APL1 - Grenada and St. Vincent and the Grenadines Loan / Credit No: IDA / 49850, TF / 19396, TF / 11131 Project Coordination Unit - Ministry of Finance Executing Agency(ies): WORKS Procureme Activity Reference No. / Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH nt Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) Justification for Award Type Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GD-PCU - GRENADA-82986- Component 1 - Prevention Single Stage - One 2019-08- CW-RFB / St. Johns' River IDA / 49850 Prior Request for Bids Open - International 0.00 Canceled 2018-10-24 2018-10-29 2018-12-10 2019-01-09 2019-02-13 and Adaptation Investments Envelope 12 Flood Mitigation Project Component 2 - Regional GD-PCU - GRENADA-82988- Platforms for Hazard and Risk Single Stage - One 2020-02- CW-RFB / Construction of TF / 19396 Evaluation, and Applications Post Request for Bids Open - National 354,972.06 Signed 2019-05-08 2019-05-13 2019-06-24 2019-04-30 2019-07-24 2019-07-08 2019-08-28 2019-09-05 Envelope 24 Nursery Facility for Improved Decision Making GD-PCU - GRENADA-136192- Component 1 - Prevention Request for Single Stage - One 2020-04- CW-RFQ / Fencing of Holy TF / 11131 Post Limited 62,011.38 Signed 2019-10-12 2020-02-11 2019-12-07 2020-09-09 and Adaptation Investments Quotations Envelope 05 Cross R.C. School GD-PCU - GRENADA-136195- Component 1 - Prevention Request for Single Stage - One 2020-03- CW-RFQ / Dredging of St. TF / 19396 Post Limited 0.00 Canceled 2019-10-09 2019-12-04 and Adaptation Investments Quotations Envelope 03 John's River GD-PCU - GRENADA-136198- CW-RFQ / Installation of Wire Component 1 - Prevention Request for Single Stage - One 2020-07- TF / 19396 Post Limited 0.00 Canceled 2019-11-09 2020-01-04 Drapery Mesh on Exposed and Adaptation Investments Quotations Envelope 02 Rock Face GD-PCU - GRENADA-171025- Component 2 - Regional CW-RFB / Platforms for Hazard and Risk Under Single Stage - One 2021-02- Rehabilitation/Extension of TF / 19396 Evaluation, and Applications Post Request for Bids Open - National 0.00 Implementat 2020-05-08 2020-06-18 2020-05-13 2020-06-24 2020-07-24 2020-08-28 Envelope 24 Beausejour Implementation for Improved Decision ion Centre Making GD-PCU - GRENADA-162382- Under CW-RFB / Schools Component 1 - Prevention Single Stage - One 2021-04- TF / 19396 Post Request for Bids Open - National 0.00 Implementat 2020-06-15 2020-08-05 2020-06-20 2020-08-01 2020-10-16 2020-08-31 2020-10-05 Rehabilitation - Boca and Adaptation Investments Envelope 03 ion Secondary GD-PCU - GRENADA-178017- CW-RFQ / Schools Under Component 1 - Prevention Request for Single Stage - One 2021-02- Rehabilitation - Boca Pre- TF / 19396 Post Limited 0.00 Implementat 2020-06-20 2020-10-01 2020-08-15 and Adaptation Investments Quotations Envelope 11 School and Constantine ion Mthodist GD-PCU - GRENADA-178018- Under CW-RFQ / Schools Component 1 - Prevention Request for Single Stage - One 2021-02- TF / 19396 Post Limited 0.00 Implementat 2020-06-20 2020-08-15 Rehabilitation - St. Paul's and Adaptation Investments Quotations Envelope 11 ion Government School GD-PCU - GRENADA-162384- CW-RFQ / Schools Under Rehabilitation - Happy Hill Component 1 - Prevention Request for Single Stage - One 2021-02- TF / 19396 Post Limited 0.00 Implementat 2020-06-20 2020-10-01 2020-08-15 Primary School, Presentation and Adaptation Investments Quotations Envelope 11 ion Brothers College, St. Joseph's Convent St. George's GD-PCU - GRENADA-162381- CW-RFQ / Schools Rehabilitation - Anglican Under Component 1 - Prevention Request for Single Stage - One 2021-02- High School, St. George's TF / 19396 Post Limited 0.00 Implementat 2020-06-20 2020-08-15 and Adaptation Investments Quotations Envelope 11 S.D.A., Springs Pre-School, ion Park View Pre-School, Wesley College GD-PCU - GRENADA-162385- Under CW-RFB / Schools Component 1 - Prevention Single Stage - One 2021-04- TF / 19396 Post Request for Bids Open - National 0.00 Implementat 2020-06-15 2020-08-05 2020-06-20 2020-08-01 2020-08-31 2020-10-05 Rehabilitation - St. Mark's and Adaptation Investments Envelope 03 ion Secondary School GD-PCU - GRENADA-178020- CW-RFQ / Schools Under Rehabilitation - Bonair Component 1 - Prevention Request for Single Stage - One 2021-02- TF / 19396 Post Limited 0.00 Implementat 2020-06-20 2020-08-15 Government School, Victoria and Adaptation Investments Quotations Envelope 11 ion School for Special Education and St. Peter's R.C. School GD-PCU - GRENADA-162380- CW-RFB / Schools Rehabilitation - Grenville Under Component 1 - Prevention Single Stage - One 2021-04- Secondary, St. Joseph's TF / 19396 Post Request for Bids Open - National 0.00 Implementat 2020-06-15 2020-08-05 2020-06-20 2020-08-01 2020-08-31 2020-10-05 and Adaptation Investments Envelope 03 Convent Grenville, Paraclete ion Government, Telescope Primary GD-PCU - GRENADA-162389- Under Component 1 - Prevention Single Stage - One 2021-04- CW-RFB / Rehabilitation of TF / 19396 Post Request for Bids Open - National 0.00 Implementat 2020-06-15 2020-08-05 2020-06-20 2020-08-01 2020-08-31 2020-10-05 and Adaptation Investments Envelope 03 Westerhall Secondary School ion GD-PCU - GRENADA-162388- Under Component 1 - Prevention Single Stage - One 2021-04- CW-RFB / Rehabilitation of St. TF / 19396 Post Request for Bids Open - National 0.00 Implementat 2020-06-15 2020-08-05 2020-06-20 2020-08-01 2020-08-31 2020-10-05 and Adaptation Investments Envelope 03 Matthew's R.C. School ion GD-PCU - GRENADA-162390- Under CW-RFQ / Schools Component 1 - Prevention Request for Single Stage - One 2021-02- TF / 19396 Post Limited 0.00 Implementat 2020-06-20 2020-08-15 Rehabilitation - Tivoli R.C. and Adaptation Investments Quotations Envelope 11 ion School and Ford Pre-School Page 1 GD-PCU - GRENADA-162378- CW-RFB / Schools Under Rehabilitation - Westerhall Component 1 - Prevention Single Stage - One 2021-04- TF / 19396 Post Request for Bids Open - National 0.00 Implementat 2020-06-15 2020-08-05 2020-06-20 2020-08-01 2020-08-31 2020-10-05 Pre-School, St. Theresa's R.C. and Adaptation Investments Envelope 03 ion School, Windsor Forest Pre- School GD-PCU - GRENADA-178022- CW-RFB / Schools Under Component 1 - Prevention Single Stage - One 2021-01- Rehabilitation - St. Michael's TF / 19396 Post Request for Bids Open - National 0.00 Implementat 2020-06-15 2020-08-05 2020-06-20 2020-08-01 2020-08-31 2020-10-05 and Adaptation Investments Envelope 03 R.C. School and Holy ion Innocents Anglican School GD-PCU - GRENADA-178023- CW-RFQ / Schools Rehabilitation - St. George's Under Component 1 - Prevention Request for Single Stage - One 2020-11- Methodist, St. George's TF / 19396 Post Limited 0.00 Implementat 2020-06-20 2020-08-15 and Adaptation Investments Quotations Envelope 13 Anglican Sr., St. George's ion Anglican Junior, St. Louis Girls' R.C. GD-PCU - GRENADA-178024- Under CW-RFQ / Rehabilitation of Component 1 - Prevention Request for Single Stage - One 2020-12- TF / 19396 Post Limited 0.00 Implementat 2020-06-20 2020-08-15 Grenada Boys Secondary and Adaptation Investments Quotations Envelope 13 ion School GD-PCU - GRENADA-178025- Under Component 1 - Prevention Request for Single Stage - One 2021-02- CW-RFQ / Rehabilitation of TF / 19396 Post Limited 0.00 Implementat 2020-06-20 2020-08-15 and Adaptation Investments Quotations Envelope 11 Calliste Government School ion GD-PCU - GRENADA-178026- Under Component 1 - Prevention Request for Single Stage - One 2020-12- CW-RFQ / Rehabilitation of TF / 19396 Post Limited 0.00 Implementat 2020-06-20 2020-08-15 and Adaptation Investments Quotations Envelope 13 Samaritan Presbyterian School ion GD-PCU - GRENADA-178027- CW-RFQ / Schools Under Rehabilitation - St. John's Component 1 - Prevention Request for Single Stage - One 2020-12- TF / 19396 Post Limited 0.00 Implementat 2020-06-20 2020-08-15 Christian Secondary School & and Adaptation Investments Quotations Envelope 13 ion St. Rose Modern Secondary School GD-PCU - GRENADA-178028- CW-RFB / Schools Rehabilitation - Mc. Donald Under Component 1 - Prevention Single Stage - One 2021-01- College, St. Patrick's Anglican TF / 19396 Post Request for Bids Open - National 0.00 Implementat 2020-06-15 2020-08-05 2020-06-20 2020-08-01 2020-08-31 2020-10-05 and Adaptation Investments Envelope 03 Primary, Mt. Rose S.D.A. ion Primary, St. Patrick's R.C. Primary School GD-PCU - GRENADA-178029- Under Component 1 - Prevention Request for Single Stage - One 2020-12- CW-RFQ / Rehabilitation of TF / 19396 Post Limited 0.00 Implementat 2020-06-20 2020-08-15 and Adaptation Investments Quotations Envelope 13 Corinth Government School ion GD-PCU - GRENADA-189710- Pending CW-RFB / School Component 1 - Prevention Single Stage - One 2021-06- TF / 19396 Post Request for Bids Open - National 0.00 Implementat 2020-08-21 2020-08-26 2020-10-07 2020-11-06 2020-12-11 Rehabilitation - Harvey-vale and Adaptation Investments Envelope 09 ion Government School GD-PCU - GRENADA-189712- Pending CW-RFQ / School Component 1 - Prevention Request for Single Stage - One 2021-04- TF / 19396 Post Limited 0.00 Implementat 2020-08-26 2020-10-21 Rehabilitation - Harvey-vale and Adaptation Investments Quotations Envelope 19 ion Pre-Primary School GD-PCU - GRENADA-189713- Pending CW-RFQ / School Component 1 - Prevention Request for Single Stage - One 2021-04- TF / 19396 Post Limited 0.00 Implementat 2020-08-26 2020-10-21 Rehabilitation - Mt. Pleasant and Adaptation Investments Quotations Envelope 19 ion Government School GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 2 - Regional GD-PCU - GRENADA-113967- Platforms for Hazard and Risk Pending GO-RFQ / Computer Request for Single Stage - One TF / 19396 Evaluation, and Applications Post Open - National 0.00 Implementati 2019-07-06 2019-08-31 2020-02-27 Equipment for the Audit Quotations Envelope for Improved Decision on Department Making Component 2 - Regional GD-PCU - GRENADA-113975- Platforms for Hazard and Risk Pending Request for Single Stage - One GO-RFQ / Operational Goods TF / 19396 Evaluation, and Applications Post Open - National 0.00 Implementati 2019-11-16 2020-01-11 2020-07-09 Quotations Envelope for Forestry Nursery for Improved Decision on Making Component 2 - Regional GD-PCU - GRENADA-113970- Platforms for Hazard and Risk GO-DIR / Base Stations for TF / 19396 Evaluation, and Applications Post Direct Selection Direct 99,684.15 Completed 2019-08-19 2019-09-17 2019-08-24 2019-10-09 2019-09-28 2019-11-29 2020-03-26 2020-02-12 Ministry of Agriculture/Lands for Improved Decision & Surveys Making Component 2 - Regional GD-PCU - GRENADA-113968- Platforms for Hazard and Risk GO-DIR / ERDAS Image TF / 19396 Evaluation, and Applications Post Direct Selection Direct 0.00 Canceled 2019-07-21 2019-09-17 2019-07-26 2019-08-30 2020-02-26 Analysis Software for the for Improved Decision Physical Planning Unit Making Component 2 - Regional GD-PCU - GRENADA-113974- Platforms for Hazard and Risk GO-RFQ / ArGIS Software for TF / 19396 Evaluation, and Applications Post Direct Selection Direct 0.00 Canceled 2019-07-21 2019-09-17 2019-07-26 2019-08-30 2020-02-26 Physical Planning Unit for Improved Decision Making Component 2 - Regional GD-PCU - GRENADA-114371- Platforms for Hazard and Risk Request for Single Stage - One GO-RFQ / LiDAR Point Cloud TF / 19396 Evaluation, and Applications Post Open - National 0.00 Canceled 2019-09-16 2019-11-11 2020-05-09 Quotations Envelope and Imagery Analysis Software for Improved Decision Making Page 2 GD-PCU - GRENADA-159285- Under Component 1 - Prevention Single Stage - One GO-RFB / Procurement of TF / 19396 Post Request for Bids Open - International 0.00 Implementati 2020-02-16 2020-03-25 2020-02-21 2020-03-25 2020-04-03 2020-05-03 2020-06-07 2020-12-04 and Adaptation Investments Envelope School Furniture on Component 2 - Regional GD-PCU - GRENADA-113973- Platforms for Hazard and Risk Under Request for Single Stage - One GO-RFQ / Desktops for the TF / 19396 Evaluation, and Applications Post Open - National 0.00 Implementati 2020-08-08 2020-10-03 2021-04-01 Quotations Envelope Central Procurement Unit for Improved Decision on Making GD-PCU - GRENADA-186668- GO-RFQ / Procurement of Pending Component 1 - Prevention Single Stage - One Computer Equipment for the TF / 19396 Post Request for Bids Open - National 0.00 Implementati 2020-08-16 2020-08-21 2020-10-02 2020-11-01 2020-12-06 2021-06-04 and Adaptation Investments Envelope Beausejour Implementation on Center GD-PCU - GRENADA-187222- Under GO-RFQ / Procurement of Component 1 - Prevention Request for Single Stage - One TF / 19396 Post Open - National 0.00 Implementati 2020-08-21 2020-10-16 2021-04-14 Furniture for the Beausejour and Adaptation Investments Quotations Envelope on Implementation Center Component 2 - Regional GD-PCU - GRENADA-217874- Platforms for Hazard and Risk Pending Request for Single Stage - One GO-RFQ / Procurement of TF / 19396 Evaluation, and Applications Post Limited 0.00 Implementati 2021-02-10 2021-04-07 2021-10-04 Quotations Envelope Rugged Laptop for Hydromet for Improved Decision on Making NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 2 - Regional GD-PCU - GRENADA-82991- Platforms for Hazard and Risk Pending Request for Single Stage - One NC-RFP / Training in Forestry TF / 19396 Evaluation, and Applications Post Open - National 0.00 Implementati 2019-07-20 2019-09-14 2020-03-12 Quotations Envelope Nusery Management for Improved Decision on Making Component 2 - Regional GD-PCU - GRENADA-114372- Platforms for Hazard and Risk NC-RFP / LiDAR Point Cloud Request for Single Stage - One TF / 19396 Evaluation, and Applications Post Limited 0.00 Canceled 2019-07-13 2019-09-07 2020-03-05 and Imagery Analysis Software Quotations Envelope for Improved Decision Training Making Component 2 - Regional GD-PCU - GRENADA-113979- Platforms for Hazard and Risk Pending NC-RFP / National Forest Single Stage - One TF / 19396 Evaluation, and Applications Post Request for Bids Open - National 0.00 Implementati 2019-09-27 2019-10-02 2019-11-13 2019-12-13 2020-01-17 2020-07-15 Inventory and Lan-cover Envelope for Improved Decision on Mapping Making Component 2 - Regional GD-PCU - GRENADA-113997- Platforms for Hazard and Risk Single Stage - One NC-RFB / Hydromet Network TF / 19396 Evaluation, and Applications Post Request for Bids Open - International 999,847.90 Completed 2019-06-28 2018-01-11 2019-07-03 2019-08-14 2018-04-13 2019-09-13 2018-09-12 2019-10-18 2019-06-06 2020-04-15 2020-02-28 Envelope Upgrade for Improved Decision Making Component 2 - Regional GD-PCU - GRENADA-218117- Platforms for Hazard and Risk Pending NC-DIR / Lidar Point Cloud TF / 19396 Evaluation, and Applications Post Direct Selection Direct 0.00 Implementati 2021-02-08 2021-02-13 2021-03-20 2021-09-16 and Imagery Analysis Software for Improved Decision on and Training Making CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 2 - Regional GD-PCU - GRENADA-113999- Platforms for Hazard and Risk Consultant CS-CQS / Spatial Data Under TF / 19396 Evaluation, and Applications Post Qualification Open - National 0.00 2019-09-09 2020-05-19 2019-09-30 2020-06-02 2019-11-13 2019-12-13 2020-01-17 2020-07-15 Management Training and Implementation for Improved Decision Selection Technical Support Making Component 2 - Regional GD-PCU - GRENADA-82990- Platforms for Hazard and Risk CS-QCBS / Development and Quality And Cost- TF / 19396 Evaluation, and Applications Post Open - International 0.00 Canceled 2019-10-14 2019-10-04 2019-11-04 2019-10-07 2019-12-18 2020-01-15 2020-02-14 2020-03-20 2020-04-24 2021-04-24 Analysis of the National Soil Based Selection for Improved Decision Mapping System. Making Component 2 - Regional GD-PCU - GRENADA-144832- Platforms for Hazard and Risk CS-QCBS / Development & Quality And Cost- Under TF / 19396 Evaluation, and Applications Post Open - International 0.00 2019-11-10 2019-11-08 2019-12-01 2019-11-21 2020-01-14 2020-02-11 2020-03-12 2020-04-16 2020-05-21 2021-05-21 Analysis of National Soil Based Selection Implementation for Improved Decision mapping System Making GD-PCU - GRENADA-159279- CS-CQS / Design of River Component 1 - Prevention Quality And Cost- Under TF / 19396 Post Open - International 0.00 2020-03-06 2020-03-20 2020-03-27 2020-04-28 2020-05-10 2020-06-07 2020-07-07 2020-08-11 2020-09-15 2021-09-15 Mitigation Works for St. John's and Adaptation Investments Based Selection Implementation River INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Contract Type Process Status Teams of Reference Identified/Selected Signed Contract Contract Completion No. (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GD-PCU - GRENADA-115475- Component 2 - Regional CS-INDV / Training in Point Platforms for Hazard and Risk Individual Cloud Data Analysis Algorithm TF / 19396 Evaluation, and Applications Post Consultant Open 0.00 Canceled 2019-06-28 2019-08-16 2019-09-06 2019-10-11 2020-04-08 Development and Future for Improved Decision Selection Topographic mapping Making Program Development Page 3 Component 2 - Regional GD-PCU - GRENADA-119237- Platforms for Hazard and Risk Individual CS-INDV / TA to design and TF / 19396 Evaluation, and Applications Post Consultant Open 0.00 Canceled 2019-06-18 2019-07-08 2019-07-31 2019-08-15 2019-09-12 2020-03-10 supervision Forest Inventory for Improved Decision Selection Making Component 2 - Regional GD-PCU - GRENADA-114000- Platforms for Hazard and Risk Individual CS-INDV / Watershed TF / 19396 Evaluation, and Applications Post Consultant Open 0.00 Canceled 2019-09-17 2020-10-07 2019-11-05 2019-11-26 2019-12-31 2020-06-28 Modelling Training for Improved Decision Selection Making Component 4 - Project Individual GD-PCU - GRENADA-113984- Pending TF / 19396 Management and Post Consultant Open 0.00 2019-06-10 2019-07-29 2019-08-19 2019-09-23 2020-12-31 CS-INDV / Project Engineer Implementation Implementation Support Selection GD-PCU - GRENADA-113995- Component 4 - Project Individual Under CS-INDV / Social TF / 19396 Management and Post Consultant Open 0.00 2019-05-20 2019-10-09 2019-07-08 2018-08-02 2019-07-29 2019-09-02 2020-12-31 Implementation Development Specialist Implementation Support Selection Component 4 - Project Individual GD-PCU - GRENADA-113994- Pending TF / 19396 Management and Post Consultant Open 0.00 2019-06-10 2019-07-29 2019-08-19 2019-09-23 2020-12-31 CS-INDV / Project Manager Implementation Implementation Support Selection Component 2 - Regional GD-PCU - GRENADA-144830- Platforms for Hazard and Risk Individual Under CS-INDV / TA to Design and TF / 19396 Evaluation, and Applications Post Consultant Open 0.00 2019-11-10 2019-11-08 2019-12-29 2020-01-19 2020-02-23 2020-08-21 Implementation Supervise Forestry Inventory for Improved Decision Selection Making Component 2 - Regional GD-PCU - GRENADA-113981- Platforms for Hazard and Risk CS-CDS / Construction TF / 19396 Evaluation, and Applications Prior Direct Selection Direct 0.00 Canceled 2019-09-16 2019-09-26 2019-11-30 2020-05-28 Supervision - St. John's River for Improved Decision Flood Mitigation Making Component 2 - Regional GD-PCU - GRENADA-221048- Platforms for Hazard and Risk Individual Pending CS-INDV / Watershed TF / 19396 Evaluation, and Applications Post Consultant Open 0.00 2021-02-23 2021-04-13 2021-05-04 2021-06-08 2021-10-06 Implementation Modelling Training for Improved Decision Selection Making Page 4