                                                                                                       Implementation Status & Results
                                                                                                              Indonesia
Public Disclosure Copy




                                                                                         Aceh Economic Development Financing Facility (P109024)

                         Operation Name: Aceh Economic Development Financing Facility (P109024)                Project Stage:   Implementation         Seq.No: 3      Status: ARCHIVED    Last Modified Date: 30-Mar-2011
                                                                                  Country: Indonesia                                    Approval FY:        2009
                         Product Line: Recipient Executed Activities              Region: EAST ASIA AND PACIFIC                         Lending Instrument: Emergency Recovery Loan
                         Implementing Agency(ies): Ministry for The Development of Disadvantaged Areas (KPDT), Bappeda

                         Key Dates
                         Board Approval Date    16-Dec-2008                Original Closing Date 30-Jun-2012          Planned Mid Term Review Date                            Last Archived ISR Date 17-Sep-2010
                         Effectiveness Date     30-Mar-2009                Revised Closing Date 30-Jun-2012           Actual Mid Term Review Date       15-Mar-2011

                         Project Development Objectives
                         Project Development Objective (from Project Appraisal Document)

                         The objective of the Economic Development Financing Facility is to assist the province of Aceh and the local and provincial governments to improve
                         opportunities for private business and private sector jobs and to continue fostering sustainable equitable long term economic development in Aceh.
                         Has the Project Development Objective been changed since Board Approval of the Project?

                            Yes            No

                         Component(s)
                         Component Name                                                                                                             Component Cost
                         Sub-Project Grants                                                                                                                   44.50
                         Consultant Services                                                                                                                   5.25
                         Incremental Operating Costs                                                                                                           0.24
Public Disclosure Copy




                         Overall Ratings
                                                                       Previous Rating                    Current Rating
                         Progress towards achievement of PDO           Moderately Unsatisfactory          Moderately Unsatisfactory
                         Overall Implementation Progress (IP)          Moderately Unsatisfactory          Moderately Unsatisfactory
                         Overall Risk Rating


                         Implementation Status Overview
                         After initial delays and a lengthy preparation period for sub-project proposals, the EDFF project has now gained momentum, although it continues to face important implementation
                         challenges. This was confirmed during the Mid-term Review of the project which was held from February 27, 2011 to March 14, 2011. This review was prepared and conducted
                         jointly with representatives of the World Bank, the project implementing and executing agencies of the central Government, including BAPPENAS and Ministry for Development of
                         Disadvantaged Areas (KPDT) and the Government of Aceh (including the Governor's Office and BAPPEDA Aceh). Representatives of the Multi-Donor Fund for Aceh and Nias
                         (MDF), as well as MDF donors also participated.


                                                                                                                                                                                                               Page 1 of 4
                             The World Bank                                                                                                                                           Report No: ISR3011




                         The mission found that the project has made significant implementation progress overall since June 2010. The Government's main achievement has been to select and sign sub-
Public Disclosure Copy




                         grant agreements with eight international and local non-governmental organizations (sub-project implementing entities, or SIEs) for a total value of USD 42,649,602 . The sub-
                         projects focus broadly in the areas of fisheries, livestock, cocoa, coffee, rice, emping, patchouli and marketing and cooperative development--and are fully in line with the demands of
                         the local economy in Aceh and local government priorities. All eight SIEs have signed MOUs with the district governments to carry out the related activities and started activities in the
                         field. Estimated direct sub-project beneficiaries include approximately 25,000 primary producers, 813 farmer/fisherman/producer groups, 46 cooperatives, and 147 small and medium
                         sized enterprises. The project also has support from local governments, which participate in monitoring the sub-projects, provide office space for some sub-projects and land for
                         project activities and staff to be trained to ensure sustainability. According to Client Connection as of March 21, 2011, 56.2 percent ($28.1 million) of project funds has been disbursed
                         with 12 months left in implementation of sub-projects and 15 months for the project overall.

                         Despite this progress, however, the project requires significant additional support and intensive effort to ensure that the sub-projects reach their overall goals on a sustainable basis.
                         The main findings of the mission were as follows:
                         �        All SIEs have made significant implementation progress in the last six months, mobilizing communities, hiring key project staff, initiating training of beneficiaries, and
                         preparing for construction of physical works. While progress varies substantially across sub-projects, it remains possible, but challenging, for the most to largely deliver on their key
                         project output targets by sub-project closing in March 2012. This will require intensive support from all partners and stakeholders, and sustainability of the gains is highly doubtful
                         given the time constraints.
                         �        Short implementation timeframe. The funding source for the project (the Multi-Donor Fund for Aceh and Nias) definitively closes in December 2012 and therefore EDFF must
                         close by June 2012, without the possibility of extension. This short implementation timeframe brings about three key issues that affect the potential for the EDFF to fully achieve its
                         anticipated outcomes. First, the short timeframe does not leave room for any unexpected implementation delays at the sub-project level. The ability of SIEs to carry out timely
                         procurement of goods and services is a particularly high risk factor. Second, the short timeframe has forced certain SIEs to accelerate their implementation. Third, it has substantially
                         reduced the potential for sustainability of outcomes, without coordinated additional follow up support provided to the beneficiaries, cooperatives, and provincial and district
                         governments. Hence, sustainable returns on the EDFF investment after March 2012 are unlikely without further support to the relevant beneficiary groups, cooperatives and/or district
                         governments.
                         �        Procurement and financial management capacity. Procurement and financial management capacity continue to be a major implementation challenge. Given that the use of
                         World Bank and some Government policies and procedures are new to the SIEs as well as to PMU/PMC, the mission found that a lack of familiarity of the guidelines under the project
                         has created implementation delays.
                         �        Sustainability. As mentioned above, the short remaining implementation timeframe until the closing of the EDFF project puts sustainability of the outcomes at risk for all of
                         the sub-projects. The mission team discussed sustainability options extensively with all partners to gather views and ideas. The mission found strong support from key partners--
                         including the central Government, Government of Aceh, district governments, communities, and SIEs on the need to coordinate follow-up so that sub-projects have the best chance
                         to achieve their full/longer term development objectives. To this end, the mission identified thr ee preliminary options for sustainability, after the sub-projects end in March 2012. All of
                         these options need further evaluation of feasibility, advantages and risks.
Public Disclosure Copy




                         Results

                         Project Development Objective Indicators




                                                                                                                                                                                                         Page 2 of 4
                             The World Bank                                                                                                                                    Report No: ISR3011




                         Indicator                                                   Baseline                                 Current                                  End Target
Public Disclosure Copy




                         Indicator Name                                              Value                                    Value                                    Value
                         Employment generated                                        0.00                                     5818.00                                  25000.00
                                                                                     Date                                     Date                                     Date
                                                                                                                              31-Dec-2010                              30-Jun-2012
                         Type                    Unit of Measure                     Comment                                  Comment                                  Comment
                         Custom Indicator        Number                                                                       This is the number of farmers,           This is the target number of
                                                                                                                              fisherman, and community groups          farmers, fisherman, and community
                                                                                                                              supported, as of Dec 31, 2010, as        groups supported under the sub-
                                                                                                                              reported in EDFF Annual Report           projects, based on project
                                                                                                                              (byPMC).                                 proposals.

                         Intermediate Results Indicators
                         Indicator                                                   Baseline                                 Current                                  End Target
                         Indicator Name                                              Value                                    Value                                    Value
                         Enterprises supported                                       0.00                                     0.00                                     350.00
                                                                                     Date                                     Date                                     Date
                                                                                                                              31-Dec-2010                              30-Jun-2012
                         Type                    Unit of Measure                     Comment                                  Comment                                  Comment
                         Custom Indicator        Number                                                                       This information is based on the         Enterprises are defined as small-
                                                                                                                              EDFF Annual Report (by PMC).             and medium-sized enterprises.
                                                                                                                              Activities are expected to               This is the target number of SMEs
                                                                                                                              accelerate in this area in 2011.         expected under the sub-projects,
                                                                                                                                                                       based on project proposals.

                         Data on Financial Performance (as of 25-Mar-2011)
                         Financial Agreement(s) Key Dates
Public Disclosure Copy




                         Project             Loan No.              Status                   Approval Date               Signing Date                 Effectiveness Date             Closing Date
                         P109024             TF-93358              Effective                30-Dec-2008                 30-Dec-2008                  30-Mar-2009                    30-Jun-2012

                         Disbursements (in Millions)
                         Project             Loan No.              Status      Currency         Original            Revised             Cancelled          Disbursed            Undisbursed        % Disbursed
                         P109024             TF-93358              Effective   USD                          50.00             50.00                 0.00               28.10             21.90           56.00


                         Disbursement Graph




                                                                                                                                                                                                   Page 3 of 4
                             The World Bank                         Report No: ISR3011
Public Disclosure Copy




                         Key Decisions Regarding Implementation
                         None

                         Restructuring History
                         There has been no restructuring to date.

                         Related Projects
                         There are no related projects.