                         Operation Name: Vietnam School Readiness Promotion Project (P117393)               Project Stage:   Implementation         Seq.No: 1      Status: ARCHIVED     Archive Date:   14-Apr-2013
                                                                              Country: Vietnam                                       Approval FY:        2013
                         Product Line: IBRD/IDA                               Region: EAST ASIA AND PACIFIC                          Lending Instrument: Specific Investment Loan
                         Implementing Agency(ies): Ministry of Education and Training

                         Key Dates
                         Board Approval Date      28-Feb-2013          Original Closing Date 30-Jun-2017           Planned Mid Term Review Date                            Last Archived ISR Date
                         Effectiveness Date                            Revised Closing Date 30-Jun-2017            Actual Mid Term Review Date

                         Project Development Objectives
                         Project Development Objective (from Project Appraisal Document)

                         The objective of the Vietnam School Readiness Promotion Project (SRPP) is to raise school readiness for 5 year old children, in particular for those most vulnerable to
                         not succeeding in a school environment, through supporting selected elements of Vietnam's ECE program.
                         Has the Project Development Objective been changed since Board Approval of the Project?

                            Yes           No

                         Component(s)
                         Component Name                                                                                                          Component Cost
                         Component 1: Promoting School Readiness for Disadvantaged Children                                                                95.00
                         Component 2: National Early Childhood Education Policy Development and Capacity                                                    5.00

                         Overall Ratings
                                                                  Previous Rating                       Current Rating
                         Progress towards achievement of PDO                                            Satisfactory
Public Disclosure Copy




                         Overall Implementation Progress (IP)                                           Satisfactory
                         Overall Risk Rating                                                            Substantial

                         Implementation Status Overview
                         The project was approved on 28 February 2013 and is not yet effective.


                         Locations
                         No Location data has been entered




                                                                                                                                                                                                          Page 1 of 3
                             The World Bank                                                                                                                             Report No: ISR10027



                         Results
                         Project Development Objective Indicators
Public Disclosure Copy




                         Indicator Name                                       Core Unit of Measure                 Baseline               Current                       End Target
                         Reduction in the share of 5 year-old children              Percentage          Value      24.00                                                22.00
                         who are vulnerable (in the bottom 10 percent in                                Date       01-Jan-2013                                          31-Dec-2016
                         at least one developmental domain defined by
                                                                                                        Comments
                         the 2012 baseline distribution) on the EDI

                         Number of provinces achieving universal                    Number              Value      10.00                                                50.00
                         preschool for 5 year-old children                                              Date       01-Jan-2013                                          31-Dec-2016
                                                                                                        Comments


                         Intermediate Results Indicators
                         Indicator Name                                       Core Unit of Measure                 Baseline               Current                       End Target
                         Rate of enrolment in preschool of 5 year-old               Percentage          Value      96.40                                                97.50
                         children                                                                       Date       31-May-2012                                          31-May-2015
                                                                                                        Comments
                         Share of 5 year-old children enrolled in                   Percentage          Value      73.70                                                80.00
                         preschool benefiting from full-day provision                                   Date       31-May-2012                                          31-May-2015
                                                                                                        Comments
                         Increase in the share of preschools having                 Percentage          Value      0.00                                                 40.00
                         been accredited at least for level 1 quality level                             Date       01-Jan-2013                                          31-Dec-2016
                                                                                                        Comments
                         Share of preschool teachers having                         Percentage          Value      0.00                                                 90.00
                         successfully completed the priority modules of                                 Date       01-Jan-2013                                          31-Dec-2016
                         the professional development program
                                                                                                        Comments
                         Share of preschool education managers having               Percentage          Value      0.00                                                 90.00
Public Disclosure Copy




                         successfully completed the priority modules of                                 Date       01-Jan-2013                                          31-Dec-2016
                         the professional development program
                                                                                                        Comments


                         Data on Financial Performance (as of 01-Mar-2013)
                         Financial Agreement(s) Key Dates
                         Project                Ln/Cr/Tf                  Status               Approval Date         Signing Date   Effectiveness Date   Original Closing Date   Revised Closing Date
                         P117393                IDA-52070                 Not Effective        28-Feb-2013                                               30-Jun-2017             30-Jun-2017

                         Disbursements (in Millions)


                                                                                                                                                                                          Page 2 of 3
                             The World Bank                                                                                                                               Report No: ISR10027


                         Project               Ln/Cr/Tf             Status          Currency   Original           Revised           Cancelled          Disbursed           Undisbursed      % Disbursed
                         P117393               IDA-52070            Not Effective   XDR                   65.10             65.10               0.00               0.00             65.10          0.00
Public Disclosure Copy




                         Disbursement Graph




                         Key Decisions Regarding Implementation
                         No decisions.

                         Restructuring History
                         There has been no restructuring to date.

                         Related Projects
Public Disclosure Copy




                         There are no related projects.




                                                                                                                                                                                            Page 3 of 3