The World Bank OFFICIALSia Tower Telephone: (66) 0 26868300 INTERNATIONAL BANK FOR RECONSTRUCTION AND DEVELO T , Pathumwan Facsimile: (66) 0 26868301 INTERNATIONAL DEVELOPMENT ASSOCIATION t 0 CU hailand www.worldbank.or.th November 19, 2013 Mr. Sisavath Thiravong Managing Director Electricitd du Laos Vientiane Lao People's Democratic Republic Dear Mr. Thiravong: Re: Lao PDR: Greater Mekong Sub-region Power Trade Project (Grant Number H300-LA) Amendment to Project Agreement We refer to the Project Agreement dated September 7, 2007 ("Project Agreement") between the International Development Association ("Association") and the Electricit6 du Laos ("Project Implementing Entity"), for the above-mentioned Project (the Project). We further refer to the letter from H.E. Phouphet Khamphounvong, Minister of Finance of the Lao People's Democratic Republic dated March 5, 2013, requesting certain modifications to the Project Agreement, as well as the discussions between the Recipient and the Association relating to other amendments during the review of the Project, including partial cancellation of the credit equal to three million two hundred thousand Special Drawing Rights (SDR 3,200,000) effective March 5, 2013, as referred to in the aide- memoire transmitted to the Recipient through the Association's letter dated June 19, 2013. We note that the Annex to the aide-memoire mentions only representatives from Electricit6 du Laos. We are pleased to inform you that, after due consideration, the Association concurs with the request and to give effect to such request agrees to amend the Project Agreement as set forth below. 1. Article II, Section 2.01 is amended as follows (emphasis added): "2.01. The Project Implementing Entity declares its commitment to the objectives of the Project. To this end, the Project Implementing Entity shall carry out Parts B, C, D, G and H of the Project in accordance with the provisions of Article IV of the General Conditions, and shall provide, promptly as needed, the funds, facilities, services and other resources required for its Respective Parts of the Project. 2. Paragraphs 4, 5, 6 and 7 of Section II.B of the Schedule to the Project Agreement are by deleted. Mr. Sisavath Thiravong - 2 - November 19, 2013 Except as specifically amended herein, all other provisions of the Project Agreement remain in full force and effect. Please confirm your agreement with this amendment by countersigning, dating, and returning to us the enclosed copy of this letter. Upon receipt by the Association of the countersigned copy of this letter, this amendment shall become effective as of the date of the countersignature. Very truly yours, INTERNATIONAL DEVELOPMENT ASSOCIATION By _ Ulrich Zachau Country Director, South East Asia (Cambodia, Laos PDR, Malaysia, Myanmar, Thailand) East Asia and Pacific Region ELECT IV E D By: -Y~D Name: SiSayath THIRAVONG Title: Managing Director Date: 09 DEC 2013 Confirmed: LAO PEOPLE'S DEMOCRATIC REPUBLIC By: Name: Phouphet KHAMPHOUNVONG Title: Date: 2 3 DEC 2013)