Punjab Roads & Bridges Development Board
                         SCF 61-62, Phase-2, S.A.S Nagar (Mohali)

     To

                     Director (F&A),
                     Government of India,
                     Ministry of Rural Development,
                     National Rural Infrastructure Development Agency,
                     15 NBCC Tower, 5" Floor,
                     Bhikaji Cara Place,
                     New Delhi - 110066.

                     Memo no.                                   Dated:       [09/2019


    SUBJECT:-       AUDIT REPORT ON THE ACCOUNT OF PMGSY PROGRAMME FUNDS AND
                    ADMINISTRATIVE_ EXPENSES_ FUND FOR THE YEAR 2018-2019 OF
                    PUNJAB STATE.


                    The Balance Sheet with required schedules of Programme Fund
             Account and Administrative Expenses Fund of PMGSY for the year 2018-
             2019 is enclosed herewith for further necessary action at your end.
            DA: As above
                                                                                  gk-
                                                                                Chief Engineer,
                                                                                PRBDB, Mohali.

            Endst. No.     bl439                                    Dated:   2.6/09/2019
                 Copy of above forwarded to Senior Financial Management
            Specialist, SARFM, World Bank, 70, Lodhi Estate, New Delhi - 110003 for
            information.


                                                                                Ch;efE~
                                                                                PRBDB, Mohali.

                                                                                                   ar9

    Phone Na.: 0172 5134620/ Fax: 0172 5134640/web site: ww, pp@,g2Yi/   Ema#: g!fie
                                                                                   @rptb.sax.i
                                      F BA                      SY2018-2019BalanceSeet Lezer doc
                                          NSALA2courts!PG$Y\BSPAG




•
  SHA MMI GARG & CO.
                                                       SCO 24, UGF,
  Chartered Accountants
                                                       Surya Shopping Arcade,
                                                       National Road, Ghumar Mandi
                                                       Ludhian  a - 141001
                                                       Tele : 0161-4666361
                                                       Email: office@sgargco.com
  SG/2019-20/48                                        20.09.2019

  MANAGEMENT LETTER ON AUDIT OF PUNJAB BOARDS & BRIDGES
  DEVELOPMENT BOARD (PROGRAMME FUND & ADMIN FUND) FOR THE YEAR
  319T MARCH 2019

 The Chief Engineer
 Punjab Road & Bridges Development Board
 SCF 61-62, Phase 2, Mohali-160055

 Sir,

 We have audited the accounts of your PMGSY (Programme Fund & Admin Fund) for
 the year ended 31° March 2013 and our observation and suggestions are narrated
 below:

 A. AREAS COVERED
    1. DPIU of Ludhiana
    2. DPIU of Ropar
    3. DPIU of Nawashaher
    4. DPIU of Sirhind
    5. DPIU of Sangrur
   6. DPIU of Bathinda ( Mansa)
   7. DPIU of Bathinda
   8. DPIU of Patiala
   9. DPIU of Muktsar
  10. DPIU of Faridkot
  11. DPIU of Moga
  12. DPIU of Ferozepur
  13. DPIU of Kapurthala
  14. DPfU of Jalandhar
 15. DPIU of Amritsar
 16. DPIU of Gurdaspur
 17. DPIU of Pathankot
 18. DPIU of Hoshiarpur
 19. DPIU of Tarntaran
 20. DPIU of Fazilka
 21. DPIU of Barnala


B.OBSERVATION ON MAINTENANCE OF RECORDS

During the audit it was observed that cash book of Pathankot division has not been
maintained. We suggest that cash book should be maintained and Nil balance
should be got signed from XEN every month.
C. SUGGESTION

There are Certain entries in cash in chest which we suggest to be written off as
there is no actual cash available against them


Assuring you of our best services at all times.
Thanking you,


Yours Truly

For Shammi Garg & Co.=
                    Z
Chartered Accounlon


arc.f
Portner
  SHAMMI GARG & CO.                                           5CO 24, UGF,
  Chartered Accountants
                                                              Surya Shopping Complex,
                                                              National Road, Ghumar Mandi
                                                              Ludhiana
                                                              Tele :+91 1614666361
                                                              Email : office@sgargco.com

                                                              UDIN : 19095431A.AAABM4526

                                    Independent Auditor' Repor!



  REPORT ON THE FINANCIAL STATEMENTS

 We have audited the attached consolidated fi  nancial statements of the PUNJAB BOARDS &
 BRIDGES DEVELOPMENT BOARD, SCF 61-62, PHASE-II, SECTOR-SS, MOHALL, PUNJAB wh               ich
 comprise the consolidated Balance Sheet as at March 31, 2019, in respect of PRADHAN MANTIRI
 GRAM SADAK YOJANA (PROGRAMME FUND), and a summary of sig          nificant accounting policies
 and other explanatory information.

 MANAGEMENT'S RESPONSIBILITY FOR THE FINANCIAL STATEMENTS

 The Management isresponsible for the preparation of these fi  nancial statements that give a true
 and fair view of the fi                      nancial performance of the Board accordance with
                        nancial position and fi
  the Accounting Standards and in accordance with the accounting principles generally
 accepted in India. This responsibility includes the design, implementation and maintenance of
 internal control relevant to the preparation and presentatio             nancial statements that
                                                                n of the fi
 giv e a true and fairview and are free from material misstatement, whether due to fraud or error,

AUDITOR' RESPONSIBILITY

Our responsibility is to express an opinion on these financial statements based on our audit, We
conducted our audit in accordance with the Standards on Auditing issued by the Institute of
Chartered Accountants of Indi      a. Those Standards require that we comply with ethical
requirements and plan and perform the audit to obtain reasonable assurance about whether
the financial statements are free from material misstatement,

 An audi t involves performing procedures to obtain ed audit evidence about the amounts and
  sclosures in the financial statements. The procedures selected depend on the auditor's
 di
judgment, in   cluding the assessment of the risks of mater    ial misstatement of the fi  nancial
statements, whether due to fraud or error. In making those risk assessments. The auditor considers
internal control relevant to the Board's preparation and fair presentation of the fi       nancial
statements in order to design audit procedures that are appropriate in the circumstances, but
not for the purpose of expressing an opinion on the effectiv eness of the Board's internal control.
An audit also in  cludes evaluating the appropriateness of accounting polic     ies used and the
reasonableness of the accounting estimates made by management, as well as evaluatin          g the
overall presentation of the financial statements, We believe that the audit evidence we have



                                                                                    '
                                                                                    I \
                                                                                        '
  obtained is sufficient and appropriate to provide a basis for our audit opinion. We report on the
  account of the Board, subject to the Notes on Accounts as per schedule-l that;-

     a. We have obtained all the in  formation and explanation which to the best of our
        knowledge and belief were necessary for the purpose of our audit;

     b. In our opinio                                   ed by law have been kept by the Board
                     n, proper books of account as requir
        so far as appears from our examination of those books,

     c. The Balance Sheet dealt with by this Report are in agreement with the books of account,
 OPINION

 In our opinion and to the best of our information and according to the explanations given to us,
 the aforesaid financial statements giv  e the information required by the Act in the manner so
 required and giv e a true and fair view in conformity with the accounting principles generally
 accepted in India:

     (a) In the case of the Balance Sheet, of the state of affairs of the Board as at March 31, 2019

    (b) The Transactions of the Board, except as detailed otherwise, elsewhere in the report,
        which have come to our notice have been within the delegated powers and budge
        approved by the Board.



For Shammi Garg & Co
Chartered Account{-



(Sham ml~"'""'-----"
 Partner
(Membership No.: 095431]
(Firm Registration No. : 017212N)
Place: Chandi   garh
Date: 20/09/2019
PUNJAB ROADS £ BRIDGES DEVELOPMENT BOARD MOHALL CHANDIGARH




   (A) SIGNIFICANT ACCOUNTING POLICIES

   1.    BASIS OF ACCOUNTING

  The Financial Statements are prepared under the historical cost convention as a going
  Concern on hybrid system of accounting and in accordance with the Accounting Standard
  issued by the Institute of Chartered Accountants of India,
  2. FIXED ASSETS

  Fixed Assets are stated at cost of constructin                                           ng
                                                g Rural Roads, up-gradation of Roads includi
  expenses related to construction and up-gradation of Rural Roads in Punjab.
  3. DEPRECIATION

  The Board does not charge Depreciationon the Roads Constructed.

  4.    RECOGINTION OF REVENUE/EXPENDITURE

 The Board follows Double Entry system of Accounting.
 S. SEGMENT REPORTING

 The Board is an apex body of Constructing/Upgradin        g of Roads & Bridges and
 Constructing/Up-gradation of Rural Roads along with Sign Roads etc., which in context of
 AS-17 'Segment Reporting' issued by the ICAI is considered only reporting segment. So
 separate reporting isnot necessary.

 6.     OTHER ACCOUNTING POLICIES

 The Board has been formed under Act for development of Roads & Bridges infrastructure in
  the state of Punjab, it has been funded by Central Govt. under PM.G.S.Y. as an
 autonomous Board and its main objective is construction Main   tenance and strengthening of
 Rural Roads. According, it is not commercial organiza    tion operating for profits, Hence, it
 follows generally accepted accounting principles in respect of accounting policies nof
 specifically referred to hereinabove as applicable to such organizations,
 (B) NOTES TO ACCOUNT
 1. Contingent Liabilities not provided for FY 2018-19 : NIL
2. In the opinion of the Management the Current Assets {Including, Stocks, Stores and
    Consumables, as valued by the management), Loans & Advances are approximately of
    the value stated, if realized in the ordinary course of business,
3. During audit we found that in most of the cases Opening & Closing balances of manual
    cash book was different from the balances shown by online cash book,
4. The Board has been set up by Govt. of Punjab, as an apex body for constructin     g
    upgrading rural roads under, PMGSY scheme in the state of Punjab and by virtue of
                                         ab) of the Income Tax Act, 1961 it is exempt from
         provision of a section 10 (23C)(ii
         payment of Income tax and therefore, no provision for taxation has been made in the
         accounts,
     S. Expenses vis--vis Budget; In case of various expenses incurred, all the expenses are
        within the budgetary limits and in respect of special items, not covered the Budget
        expenditure has been incurred only after obtaining prior approval of the Board.
     6. Related Party Disclosures; The Board is an autonomous body set up the Govt, of Punjab
        having no individual interest. Therefore, there isNIL disclosure under this head, as required
        by the Accounting Standard 22,
    7. Deferred Tax Assets/liabilit ies_; The Board is exempted from taxation under the provision
       of section 10 (23C)(iab) of the Income Tax Act, 1961, In view of this there is no disclosure
       for Deferred Tax Asset/Liabilities as required by Accounting Standard 22.
    8. Previous year's fi gures have been regrouped & re-casted wherever considered
       necessary.
    9. Schedules attached form part and parcel of Balance Sheet of the Board as at
       31.03.2019.




For Shammi Garg &    Co
Chartered Accounton·t'~



•.2rg
    25
 Fortner            \
(Membership No.:; 09¢·
                       ,
                             @g
(Firm Registration No. :O.    [2NJ
Place: Chandigarh
Date: 20/09/2019
   UDIN : 19095431AAA ABM4$26
                                                                                                                                    PMGSY/F-2
                                                               PMGSY PROGRAMME FUND
                                                       PUNJAB STATE BALANCE SHEET
                                            PUNJAB ROADS & BRIDGES DEVELOPMENT BOARD,MOIHALI
                                                  CONSOLIDATED BALANCE SHEET AS AT 31.03.2019

           CAPITAL, FUND AND LIABILITIES                             Schedule              CURRENT YEAR                       PREVIOUS YEAR
   Programme. Fund Roriel from GO]
     - Funds fro NRRDA (MORD)                                  LI (PMGSY/SCH/F-S2AA)                2$,238,709,500.00                    22,857,336,000.00
     - Funds fron NRRDA ( NABARD)                                                                4,36$,300,000.00                         4,365,300,000.00
                                                                                                29,60-4,009,$500.00                      27,222,636,000.00
  Programme FE Ressie!
                and from,Stat
  Funds Received from State Govt. for Cost over Runs                                                   $4,303,000.00
  Funds Received fro State Share of' PMGSY Fund                LI (PMGSY/SCH/F-S2AA)                                                         $4,803,000.00
                                                                                                    2,464,067,167.00                      2,136,747,667.00
  Incidental Funds (from interestand other receipts)           L2 (PMGSY/SCH/F-$2B)                   $19,930,855.57
      llaneous Income
  Misce                                                                                                                                     $12,100,841.47
                                                               L2 (PMGSY/SCH/F-S2B)                     2,$ 13,843.53                         2,$13,843.$3
  Deposits Repayable                                           L.3 (PMGSY/SCH/F-S2C)                 713,703,342.00                        752,418,349.00
              li
  Current Liabi ties                                           14 (PMGSY/SCH/F-S2D)                     4,203,692.00
  Unreconciled Bank Authorizations                                                                                                            7,803,613.00
                                                                LS (PMGSY/SCH/F-S4)
                            TOTAL                                                              33,3     {00 Io
                                                                                                   63231,                                2£,689.023.31469

                                                                     Schedule                Current Year                          Previous Year
                                         nanced By
  Expenditure oa New Roads (Completed), Fi                             Al
      • MORD                                                    (PMGSY/SCH/F-S3A)                   1,099,924,165.00                      1,099,924,165.00
      - World Bank (RRPI)
      - World Bank (RRP?)                                                                              48,435,117.00                         48,435,117.00
      • Asian Development Bank
      - Others

 Expenditure oa New Roads (in Process), Fi
                                         nanced By                     Al
     - MORD                                                     (PMGSY/SCH/F-S3A)                      14,180,492.00
     • World Bank (RRPI)                                                                                                                     14,180,492.00
     • World Bank; (RRP2)
    • AsianDevelopment Bank
     • Others

 Expenditure oa Upgradation of Existing Roads (Completed),
 Fi
  nanced By                                                            A2
     • MORD                                                     (PMGSY/SCH/F-$3B)              13,641,230,007.00                         13,641,230,007.00
     - World Bank (RRPI)
               k (RRP2)
     - World Ban
                                                                                               10,$57,633,402.00                         9,181,336,734.23
     ·Asian Development Bank
     - Others

 Expenditure ona Upgradation of Existing Roads (in Process),
 Financed By                                                           A2
     -MORD                                                     (PMGSY/SCH/F-$3B)                     139,910,783.00                        139,910,783.00
     • World Bank (RRPI)
     • World Bank (RRP2)
                                                                                                     155,816,142.00                      1,446,1$2,221.77
     -Asian Development Bank
     · Others
                                                                      A3
Expenditure oa Sign Boards                                AJ (PMGSY/ISCH/F-$CC)
                                                                                                   10,039,382.00
Expenditure oa UpgradationofPMGSY-II Roads in Plain Areas & Special Areas                                                                   10,039,382.00
                                                                                                7,093,348,910.00                         4,902,869,181.00
Current Assets                                            A4(PMGSY/SCH/F-SSD)                        85,994,45$.00
Stores & Stocks                                                                                                                             91,187,447.00
Cash inChest
Bank Balance with Accredited Bank
                                                                                                          $,000.00                              5,000.00
Automatic Investments with the Accredited Banks
                                                                                                    $16,713,545.10                        113,752,784.00
Un- reconciled Programme fund trfd to PIUS

                          TOTAL
                                                                                             336321,±90 io                                023,346o
                                                                                                                                     0,689,
SOTES ON ACCO!NT AS PER AN
                         NEKRE_ATTACHED
                                                                                    COMPILED FROM THE RECORDS & OTHER DOCUMENTS
                                                                                    PROVIDED BY THE VARIOUS DIVISION AND BOARD
                                                                                    NOTE.-AS PER OUR SEPARATE REPORT OF
                                                                                    EVEN DATE ATTACITED
                                                                                    FOR SIHAMMI GARG AND          CD
                                                                                    CHARTERED ACCOUN
                                                                                    (FIRM REG. 80. 017
                                                                                                         TAI
                                                                                                      2128)           '-Nri6}]
                                                                                                                  ;kA,'
                                                                                                                         ®
                                                                                                                             fG>

                                                                                                                                    {@
                                                                                                                                    #
                                                                                                                 Rs.p         12N},
PLACE:- CHANDIGARH           /'/?:                                                  CA. SHAMMI
                                                                                    PARTNER                      '
                                                                                                                 »<a> 's»&
DATED:- 20092019            (>          '    !
                                                                                    M.NO., 095431                       'er 4LY
                                                                                                                PMGSY/SCH/F-S2A.A
                                                         PMGSY PROGRAMME FUN           D
                                          SCHEDULES FORMING PART OF BALANCE SHEE            T OF SRRDA
                                                 (Referred to in Paragraph 15.4.1 of theManual )
                                                Schedule of Programme fund Receiv   ed by SRRDA
                                                       Balance Sheet as at 31stMarch 2019
                                                     For use with the Annual Balance Sheet

                          .
 NAME OF PIU/STATE : PUNJAB ROADS & BRIDGES DEVELOPME            NT BOARD
 scuyp LE _yQ, LI PROGRAMIE FUNDS)                                                       Current Year              Previous Year
{l Programme ud received fromMinistry of Rural Development, ((0f

MORD Fad Dtui]
Opemining Balance as per last year's Balance Sheet                                         22,8$7,336,000.00           20,38 1,797,000.00
Add: Received during the year MORD                                                          2,381,373,500.00            2,47$,$39,000.00
Less: Received daring the year 201$-16 (State)
Closing Balance
                                                                                                         . I                        .       I
                                                                                           2$5,238,709,$00.00          22,857,336,000.00
SABA RD Fad Detail
Openining Balance as per last year's Balance Sheet                                          4,365,300,000.00            4,365,300,000.00
Add: Received during the yearMORD
Closing Balance
                                                                                                         al
                                                                                                                                    .
                                                                                            4,365,300,000.00            4,36$,300,000.00
TOTAL                                                                  (A)                 29,60-4,009,500.00          27,222,636,000.00
 Dy, Funds Received from State Government     to   meet   cost
orr-runsor its other commitments
Openining Balance as per last year's Balance Sheet                                              $4,803,000.00               ,000,000.00
                                                                                                                           20
Add: Received during the year 2015-16
Closing Balance
                                                                                                         a
                                                                                                                          3-4,803,000.00
                                                                       (B)                      $4,$03,000.00              $4,803,000.00
Ip. Fundy Rgceisyed fro State Share of PM€GSY Fund
Opening Balance as per last year's Balance Sbeet                                            2,136,747,667.00
Add: Received during the year 2017-18                                                                                   1,3n,3J2.U1.ool
Add: Received daring the year 2018-19                                                                                    779,415.000.00
                                                                                            327.319,500.00
Closing Balance                                                       (c)                  2,464,067,167.00              136,747,667.00]
                                                                                                                        2,
TOTAL                                                            (A) + (B)+ (Cy                122,879,667.00
                                                                                          32
                                                                                                                      19414,~
                                                                                                                          PMGSY/SCH/F-S2B
                                                          PMGSY PROGRAMME FUND
                                       NAME OF PIUSTATE : PUNJAB ROADS & BRIDGES DEVELOPME
                                                                                         NT BOARD
                                            SCHEDULES FORMING PART OF BALANCE SHEET OF SRRD A
                                                     (Referred to in paragraphs 1S.4.1 and 15.4.3 ofManual )
                                                      Schedule of Iscidental Funds andMiscellaeous Income

    [scypiro_Lg icgpryrt_rusts aspiscEir 8EoS
                                            A icoiE                                                 Current Year            Previous Year
                                    om Interest and other receipts)
    I. Incidental Funds (generated fr
    As per Last  Balance Sheet                                                                          $12,100,841.47            506,32 1,083.47
    Add: Received During the year                                                                         7,830,0 14,10              $,779,758.00
    Add/(Less): Adjustment during the Year                                                                                                   .
                                Total (A)                                                               $19,930,855.57            $12,100,841.47
    2.
     Miscellaneous Income
    As per Last Balance Sheet                                                                             2,$13,843.53                13,843.53
                                                                                                                                    2,$
    Add/(Less): Received During the year (Net)                                                                     .                         .
    Add/(Liess): Adjustment during the Year                                                                        .                         .
                             Total (B)                                                                    2,$13,843.53              2,513,843.53
I                           Total (A+B)                                                                 $22,444,699.10            514,614,685.00
                                                                                                                         PMGSY/ISCH/F-$2€
                                                      PMGSY PROGRAMME FU  ND
                                    SCHEDULES FORMING PART OF BALANCE SHEET AS AT J1STMARCH, 2019
                                                               Schedule ofDeposits Repayable
                                                 (Referred to in Paragraph 1S.4.1 and 15.4.3 of theManual )

    NAME OF PIUSTATE : PUNJAB ROADS & BRIDGES DEVELOPMENT BOARD

[SCHEELE         _Qt_     _DEPOsTTs REFAYBL.E
                                                                                                 Current Year              Previous Year
    Contractor & Suppliers Outstanding Arount
    As per Last Balance Sheet
                                                                                                      752,418,349.00               ,462,777.00
                                                                                                                                 602
    Add/(Less) : Received During the year(Net)
Add:(Less) Adjustment                                                                                 (38,715,007.00)             149,955,572.00
I                         Total (A+SB)
                                                                                                                  .                         .
                                                                                                      713,70.3,3-42.00           752,418,349.00
                                                                                                             PMGSY/SCH/F-52D
                                                              PMGSY PROGRAMME FUND
                                        SCHEDULES FORMING PART OF BALANCE SHEET AS AT 31STMARCH, 2019
                                                               Schedule of Current Liabilities
                                                (Referred to in Paragraph 1S4.1 and 15.4.3 of theManual )

    SAME OF PIUSTATE : PUNJAB ROADS & BRIDGES DEVELOPMENT BOARD

[sCEDIE_SO_Lt CURRENT E.iii TTiF&
                                                                                       Current Year            Previous Year
    (A) Statutory taxes to be paid
      ·Income Tax/ Sales to be paid
      • Commercial Tax                                                                        4,203,692.00              7,803,61.3.00
      - Other
                                                                                                      .                          .
                                                                                                      .                          .
    (B) Un-paid Bill
    (C ) Amount Payable to the State Govt,
                                                                                                      .                          .
I                               Total
                                                                                             4,203,692.00              7,803,61.3.00
                                                                                                                                                     PMGSYISCH/F-SJA
                                                                                    PMGSY PROGRAMME FUND
                                                      SC HEDULES FORMING PART OF HALANCE SHEET                 AS AT J1STMA RCH, 2019
                                                                               Schedule of Ceas trtioa of Ncw Reads
                                                                   (Referred to la Paragraph 144.2 and 144.7 ef theManual )

            NA ME OF PIUSTATE : PUNJ AB ROADS & BRIDG ES DEVELOPMENT BOARI

            [SCHEDULE0.Ai                                                                    Arum!                          Iner Calame 2               OuterColar
            COsTCTos oF srw oAns
            [Seral No [Nares of Reads                                                      Iner Calame I               (Sub-teal ef tsner Col I]   (Sat-oul of tzr Col. 2)
            I    I    I                    2                                                    3                                 4                          s
             Part Roads funded by the   Mils@ry of Rural
             Development, (Gast. ef fdia
                       (i) Cepleted Roads up to the cad of the Last
                                 Year                                                         1,099,924,16$ 00
                                 Expend»tareo New Roads                                                            .
                                                                            Tetal             1,099,92-4,165 00

                                 (u) Completed Durig the Year                                                      .
                                 Less. Adjastmmert                                                                 .
                                 Total Co p\eted Raad                                                                        1,099,924,16$ 0                 1,099,924,16$.00
                             Raad us Propress                                                   14,110,49200
                             Total
                                                                                                                                14,180,49200                     14,110,49200
        I                    I                    Total for MORD
                                                                                                                                                             1,114,10-4,6$67.00
        Part 1l Rads faded by the World Bak (RRPI)
                             (i) Ceaspletnd Reads up to the end ef the Last
                             Year
                             Epend@are oa New Roads                                                            .
                                                                            Total                              .
                             (i) Cepleted Durlag the Year                                                      .
                             Less. Adjustment                                                                  .
                             Total Cepleted Raad                                                                                             .
                             Raad is Prepress                                                                  .
                             Total
                                                                                                                                             .
    I                    I              Total for World Hal (RRIPI
                                                                                                                                                                          .
        Part 1II Reads funded by the World Bak (RRP2)
                          (l) Caple'ted Roads up ta the end of the Last
                          Year                                                                 39,443,143 00
                          Expend»tare on New Roads                                                             .
                                                                  Tetsl                        39,443,14300
                          (ii) Completed Drisg the Year                                         1,991,974 00
                                                                                                           .
                         Total "earpiece& Read
                                                                                                                               41,43$,117 00                  41,43$,117 00
                         Rea! in Progress                                                                  .                             .                                .
                                                                                                                                         .
                          Total
I                        I      Total fer World Ha (RRP?
                                                                                                                                                              48,4JS, 117.60
    Part IV Roads faded by the Asian Dev
                                       elopment Hans
                         (i) Completed Reads up to the ed of the Last
                          Year                                                                             .
                         Expenditure c NcwRods                                                             .
                                                               Teal                                        .
                         (#) Completed Durig the Year                                                      .
                                                                                                           .
                         Total Cop\eted Roads
                                                                                                                                         .
                         Read       in Progress                                                            .                             .
                         Tetal
I                    I
                                                                                                                                                                    ,c'           s
                                    'Total fer Asian Deselopnest Hal                                       .                                                      ZS.h 3
                                                                            gystow                                                                               %'                   •
                                                                       oo

                                                                                                                                                                                      o
                                                                                                                                                                                      »
                                                                                                                                                                                  &
                                                                                       .                   Mar         A                                                so
                                                                                                                                  PMGSYSCH/F-S3 B
                                                                  PMGSY PROGRAM ME FUND
                                            SCHEDULES FORMI  NG PART OF BALANCE SHEETAS AT J1ST           MARCH, 2019
                                                            Schedule ef Coastrctioa ef E±lstig Roads
                                                    (Referred to ia Paragraph 14,4.2 ad 144.7 ef theManual )

            NAME OF PIUSTATE : PUNJAB ROADS & BRIDGES DEVELOPMENT BOARD

        [SCHEDULE SO. A2                                                      Atort                     Inner Calame2                Outer Column
          GRADATION OF FISTING ROADS
        [Sera} No [Nares of Rads
                                                                          Iner Colee I             (Sub-total of Maner Col. I   (Set-total of Iser    Col.   2)
        I    I    I                            :                                 3                             4                            s
         Part I Reads funded by the Min istry af Rural
         Develop@sea t, Govt. of Lsdia
                         (i) Completed Roads up to the ed ef the Last
                         Year
                         Expend±tareoa Uppradatioe of Roads                   13.$591,2$7,$94 00
                                                                Total         13,$991,2$7,594 00
                         (i) Completed Durig the Year
                         Expenditure os Upgradations ofRoads                     49,972,413 00
                                                                                                         13,641,230,007 .00               13,641,230,007 00
                         Total Cepleted 'Reads
                         Road in Propres                                        139,910,713 o0              139,910.7183 00                  139,910,71500
                         Expenditure en LUppratatoe of Roads                                                               .
                         Tetal
        I            I                 Tetal fer
                                               MORD                                                                                       13,781,1 40,790.00
        Part 1l Read s faded by the Werid Bank, (RRIP I)
                         (i) Completed Road s sp to the ed of the Last
                         Year
                         Epedtare en Uppratatioe of               Rads
                                                                 Total                         .
                         (ii) Copleted Durig the Year                                          .
                         Expend@areoa Uppalate of Roads                                        .
                         Total Completed Read
                         Read in Prepress
                         Expend»tare on Uppatat»oe of Rads

                         Total
    I                I           Total fer Werld Hank (RRIY                                    .                                                                 .
        Fart III Roads faded by the World Bank (RRP2)
                     (l) Cope±ed Read s ep to the ed of the Las t
                     Year
                     FE; ttare con Upgradationof Roads                        9,181,336,734 23
                                                               Total          9,181,336,734 23
                     (u) Cea»pleted Durig the Year                                         .
                     Expend@are ca Upp±astation ofRoads                       1,376,296,667.77
                                                                                                        10,$$1,633,40200                 10,$$57,633,40200
                     Total Cepleted Reads
                     Road in Progress
                     Expenditure os Upprafatioof Roads                                   00
                                                                               1$$,816,142                 1$$,116,14200                    1$$5,816,14200
                     Tetal
I         I       Tetal fer World Haak (RRP2 )                             10,7 13,449,544.00                                            10,713,449,<44.00
 Part IV Roads funded by the Alan Develop@es t Baal
                     (i) Caple±ed Roads sp to the ed of the Last
                     Year
                     Expenditure on Uppradatio ofRoads
                                                               Total                       .
                     (ii) Cop&eted Durig the Year                                         .
                     Expenditure ca Upgradation of Roads                                  .
                     Total Cea#pleted Reads
                                                                                                                       .                                     .
                     Raad in Propes
                     Expenditureoa Upprala±tioaofRoads
                                                                                                                       .                                     .
I                I
                     Total
                             Total for Asa Develoaea t Bal                                .                                                     8rs
                                                                                                                                                       .. ~ -~
                                                                                                                                             s
                                                                                                                                                j
                                                                                                                                                       '»  \
                                                                     per,
                                                                Jg




                                                                                                                                             g          3rslg
                                                                                                                                                                     ;
                                                                                                                                                                     S
                                                                     ,   Ne                    Marage Accounts
                                                                                                                                                    @                h
                                                                                                                                                                     ©
                                                                                                   PMGSY/SCH/F-SJ C
                                                    TMGSY PROGRA MME FUN D
                            SCHEDULES FORMING PART OF BALA       NCE SHEET AS ATJ1STMARCIE, 2019
                                             Schedule of Other Espediture o Raads
                                    (Referred to ia Paragraph I44.2 ad 144.7 of theManual )

NA                                                SNT BOARD
  ME OF PIUSTATE : PUNJAB ROADS& BRIDGES DESELOPSME

IsCED/LE SO. A                                      I                        CurrentYear             nevus 'Year
OTHER EXPENDITURE COssFCTEDwIt ROADS w                     s
                                                                                           .                          .
Expend#are ca Part2tio                                                   0                 .                          .
[ Teta                        (A)                                        o                 .                          .
Expenditureca Spa Boards                                             .           10,039.312 00              10,039 ,34200
Expenditure oa Upgratatio of' PMGSY-II Rads in Pun Areas                      7,093,348,910 00           4,902,1-9,181 00
[ fetal                       (B                                     .        7,103,316$.292 OO          4,91          00
[ Total                    (A) ± (B)                                     0    7,103        2 00          4,912,908,$563GO




                                                                                      -
. .

                                                                                                                      PMGSY/SCH/F-SJ D
                                                               PMGSY PROGRAM       ME FUND
                                      SCHEDULES FORMI      NG PART OF BALA     NCE SHEET AS AT JISTMARCH, 2019
                                                                 Schedule ef Curren t Awets
                                          (Referred to la Paragraph 144.2, 1447,15.4.1 ad 1S.4.3 of theMaual )

        NAME OF PIUSTATE : PUNJAB ROADS & BRIDGES DEVELOPMENT BOARD

        [SCHEDULE NQ A4 CREST ASSETS                                                          Current Year               Previous Year
        A.) Adv to ace
                   'oatractor
           ) Cos dered Safe (Completion date + JMonths is not yet over)
                                                                                                                  .                              .
                                                                                                 61,611,915 00                   67,184,11$00
             » Moblrat Advance

            - Machinery Advance

          i) Cesidered   U-Safe (Cop/let.ion date + J Moathsare over)                                             .
        A.)Misc. 'Weris A@vace
         (a) Against Ceatracter
                                                                                                                  .                              .
             i) Cosidered Safe (within Completion date + J Moaths)
                                                                                                                  .                              .
            u) Coasis&ered Us-Safe
                                                                                                                                                 .
         (b) Against Staff
             ) Less Than Three Moths                                                                          .                              .
            ) Less Tea SrMoths                                                                                .                              .
           u) Over SrMoths                                                                                    .                              .
         (e) Ad+aces ta DIR Preparatiea
             i) DPR reportsAwaited                                                                            .                              .
            u) DPR reportsnot chafed in approved prog                                                         .                              .
            i ) DPR reportsapproved in prog                                                                   .                              .
                adjustment inaccount yet to be ma?
                                                                                                              e
                                                                                                                                             .
         (d) Admiaistrative Espeses approved by NRRDIS/MORD                                                   .                              a

             ta be roerf

       C) Adaisistrative E±pees Recov      erable free the state Gest
          i) Outstanding for less than 6 moths
          tu) Outstanding formore than 6 months
                                                                                                              o
                                                                                                                                             .
                                                                                                              .                              .
       D.) Oher items
         1) Tnx Decorte! at Source
                                                                                                24,382,540.00                  24,003,33200
      [ Tetul
                                                                                                ss,994,4$500                   91,117,44700

                                                                                                                      PMGSY/ISCH/F-S4
                                                              PMG  SY PROGRAMME FUND
                                     SCHEDULES FORMING PART OF HALA            NCE SHEET AS AT J1ST MARCIE., 1019
                                                                Seled ale of Current Asset
                                         (Referred to ia Paragraph 144.2, 144,7, 1S4.1 amd 1S.4.J of theManual )

      NAME OF PIUSTATE : PUNJAB ROADS & BRIDGES DEVELO PMENT BOARD

      SCFITE
      [     O, 1St'grecoriled Hal Auther±ratios
                                                                                            CurrentYear                Previous Year

                                                                                                          .                              .
      I Total
                                                                                                          .                              a
      PMGSY PROGRAMME FUND                                    f
      PUNJAB ROADS S BRIDGES DEVELOPMENT BOARD                g


      S.R.             NAME OF DIVISION                           SCHEDULE A4 Current Assets       As or
     NO.                                                                           19
                                                                                31/03/20
           Advance to Contractors                                 Current Year          Previous Years
      1 CONSTRUCTION DIV. NO. 1 LUDHIANA                            (1,283,400.00)
                                                                                              12.560.75300
      2 CONSTRUCTION DIV. ROPAR                                                   .                              .
      3 PROVINCIAL DIV-NAWANS                   HE            HAR                 .                             .
      4 CONSTRUCTION DIV-SIRHIND                                      (200.000.00)
                                                                                                  200.00000
      s    PROVINCIAL DIV. SANGRUR                                               .                              .
      6 PUN.LAB MANDI BOARD-BAT NDA
                                  HI                                             .                              .
      7 CONSTRUCTION DIV NO.1-BATHINDA                                           a



                                                                                 .                              .
      8 PROVINCIAL DIV NO.2 PATALA
                                                                                                     00
                                                                                                4442.685
       9 CONSTRUCTION DIV-MUKT SAR                                            a
                                                                                                        aaA




      10 PROVINCIAL DIV-FARIDKOT                                              .
                                                                                                1,972.35800
      11 CONSTRUCTION DIV-OGA                                                 a
                                                                                                            a

      12 PROVINCIAL DIV-F                         EROZEPUR          (4,088,800.00)
                                                                                             4,163,652.00
     13 CONSTRUCITON DIV NO 2 KAPUR THALA                                     .                             .
     t4 PROVINCIAL DIV-JALANORA R                                             .                         [$jg {gy
     15 CONSTRUCTION DIV NO.1 AMRITSAR                                        .             as   845.602.00
     16 PUNJAB ANDI BOARD-GURDA                    SPUR                       .
     17 CONSTRUCTION DIV NO. 1 HOSHARP LUR                                   .                              le




                                                                                                            .
     18 OHALI BOARD SRRDA                                         (17,7 10,290.00)
                                                                                            42.092.830.00
     19 Patt              ankot                                              .                              .
     20 BA              RNALA                                                .                              .
     21 TARN 'TARAN                                                          .                              a

     22 FAZILKA
                                                                                                           .
          Total                                                    (5,572,200.00)           67,184,115.00
          G.Total Advances (Current Previous) A                                             61,611,915.00
     1f TDOS                                                      (17,710,290.00)           4    Pr83   a(]

          G.Total TDS (Curre nt + Previous) B                                               24,382,540.00
          Total (A·B)                                     I                                85,994,455.00




Dot pol y Dorn t7200y Dua8AL  22
                            47924Y; SAL»th 3p14- pg nzs                                  $NETT Pg   gCOTED 3218 PNAL
                                                                                                         IDA
                                                                                                        Ace $t4 amt Aas
                                     Paz#Y   Peca }
                                                  Ag

                                     174ff £At If?
                                                 AZ
                   thereti e 3geeg t 4 of e
                                  eg      }
e # fgs got» re » gt 3 g f#].pet vi
rt



                                             ctat                           vgwo Alf


tapes   ggwe hat rrd terr              #/fY./Svf-$
                                                 }AA
        ere? f if
        pwow rt erf ty #at             #/AYO®-$        }4A
                                                         s 4,3M$02 000 0        r 4MS222 000 00
        tog» lg
        an trot re Satre               NE$Y/Cf-$2AA          s 44121000 ¢         £   £4121O0¢0
        ret far cf e P        a
        Fanef rcorg b»gr tat# est
        SY gee mf
        g uh er            weefr
        (Ctr wrem?far
        papft e gf )Y 4 red
        .a Ugo
        yr    wee
          ecru@ rm
        Ctrwere far
        pcl Ava
                   e # rt
        ppr tatgf ,ST
        ppme umtre goref
                                                    r               ....
        th rwg ten pp
        et zAY # rt av4en
        p we hum eef erme
        St.ti# revetfar 'ppfatr
        gt ,{ r 4 rat ct v9es
                                        what

                                                                    ....                  s g02

        fats rec fr    al er
                      wed                                                                 T   J 90
        (art.utan ef r# eat etr
        pet       tpl!j gy
        9Jg
        ha rec@w'liter                                                                    s 909
        (ortnuctosf @rd At
        Arr
        (er gran
        cres rec.ref ty $ale4
        togttr Tryhr
           ®en f Rare! ta.t tr
        cart
              Ct»ff;y y Ripa
               t ar 'tatMa
                            "reg

                                                                    ....                  . ...
        prt ,t {it,'     )
        (tow gwt far tu A                                                                 s 9¢
        erf y 'U¢
        trg @tr Tearyhr Ran
        sat Trg #r e tre
        orgy
        (tr gat    r tat#ar                                        s ¢00
        er@ yT!"
        tug tr 'Teary fr Pi             SY
        of
        (rtr' get r te are                                         s 00
        cemes cwef ty ©a
                  ,$F
        twpf&tr. Try fr g»
        fatef
        Arp I
                    eat» we aw

        (ow gt fr ate Par
        're « rd ty Sp4
        sg Mate TPary fer Lip
                                                                   s 00                   . ...
                                                                                          . ...
        p gf ,SF   toter
                     rt»
        poel Aver
        Cetrai gt far art.r au
        Schemes rd ty Seu
        tog¢tr 'Terry far EAwf
        Asad
        t $h Mt.r wt gf ,$
        ogre fag ti,wf A,
        «2.© g rte
                                                                   s 00                   ....
        Age©y Fee» ts XI                                           s ¢00
        fe    talfry- mt.rerstt a©                        s $22444
                                                               40% tQ
        at.er rgMi)
        et. iere                                                   s ©0                   s   0¢

        2pct @gybe                                        s 71j72$.3420
        'art Lu@toes                                         s 4201    422
                                                                      0¢
        Ls ce¢ ff A!Nert.at                                        sd00                   r2o¢
                Lee ft                                 s 51,141.231,4¢ 1    £   37409.222.1 142¢
        fepters rw #t
        Karper@),std by
        lp

        wart thprongg I
                                                        s too97416 0
                                                                   s d0                   ....
                                                                                s 1 901 .14$
                                                                                          92¢0
                                          Pradhan Mantri Gram Sadak Yojana

    Annexure -I (UC)

                     UTILIZATION CERTIFICATE FOR THE YEAR2018-2019 (AS ON 31-03-2019)
                                UNDER PRADHAN MANTRI GRAM SADAK YO.JANA
                                             PROGRAMME FUND



                                                              t.Certified that a sum of Rs. 238.14 Cr was received as
  Agency: Public Works Department (B and R) /Punjab           grants·in-atd from Goverment of India during the year
  Mandi Bcard State: Punjab                                   2018-2019 & a sum of Rs. 32.73 Cr was received as
                                                              grants-in-aid from Goverrent of Punjab during the year
  A. Unspent balance as on 01-04-2018 Rs. 11.40 Cr            2018-2019 as per details given in the margin, a sum of Rs.
  (begining of the financial year 2018-2019) from             11.40 Cr being the unspent balance of previous year 2017
  Gevererent of India.                                        -2018 has been brought forward for utilization during the
                                                              year 2018-2019, Interest receipt of the Agency during the
  B. Grants received during   the year 2018-2019 from         year 2018-2019 ts Rs. 0.75 Cr, Other miscellaneous receipt
  Government of India.                                        of the Agency during the year so far is Rs. 0.00 Cr.
   Sr.No.             Description            Amount (Rs in    2. It is certified that out of a total available fund of Rs.
                                                Crore)        283.02 Cr a sum of Rs. 222.88 Cr only has been utilized
              Letter no. J-12031/1/2015-              25.00 by the Punjab Public Works Departm ent (B and R)
              RC (FMS 341960) dated                         /Punjab Mandi Board during the year 2018-2019 for the
              23/12/2017 PMGSY-II (Batch                    purpose for which it was sanctioned.
              I) (FY 2017-2018) Rs. 318.73                  Out of the amount utilized, as expenditure amounting to
              Crore already received Rs.                    Rs. 227.64 Cr has been incurred.
              80,59,26,500/- in 2017-18                     Unspent balance as on 31-03-2019 Rs. 51.67 Cr (End of
              part payment Rs. 25 Crore                     the financial year 2018-2019)
              Letter No.ROOOT dated
              11/05/2018 Voucher no   -
              RO002
     2      Letter no, J-12031/1/2015-                25.00
            RC (FMS 341960) dated
            23/12/2017 PNGSY-II (Batch
            I) (FY 2017-2018) Rs. 318.73
            Crore already received Rs.
            80,59,26,500/- in 2017-18,
            Rs 25 Crore part paymen t
            Rs. 25 Crore Letter
            No. ROOO2 dated 11/05/2018
            Voucher no ·RO0OO3
     3      Letter no. J-12031/1/2015-                25.00
            RC (FMS 341960) dated
            23/12/2017 PMGSY·II (Batch
            I) (FY 2017-2018) Rs. 318.73
            Crore already received Rs.
            80,59,26,500/- in 2017-18,
            Rs 25 Crore, Rs 25 Crore
            part payment Rs. 25 Crore
            Letter No,RO003 dated
            11/05/2018 Voucher no ·
            ROO00-4
     4      Letter no. J-12031/1/2015-                25.00
            RC (FMS 341960) dated
            23/12/2017 PMGSY-II (Batch
            y (FY 2017-2018) Rs. 318.73
            Crore already received Rs.
            80,59,26,500/- in 2017-18,
            Rs 25 Crore, Rs. 25 Crore, Rs
            25 Crore part payment Rs.
            25 Crore Letter No.ROOO4
            dated 11/05/2018 Voucher
            no- RO0005



Page t of 4                         Generated On : 25/09/2019 08:16 AM                  2014 NRRDA, All rights reserved.
                                           Pradhan Mantri Gram Sadak Yojana
      10      Letter no, J-12031/1/2015-              24.01
              RC (FMS 341960) dated
              23/12/2017 PNGSY-II (Batch
              I) (FY 2017-2018) Rs. 318.73
              Crore already received Rs.
              805926500 in 2017-18, Rs
              25 Crore, Rs. 25 Crore, Rs 25
              Crore, Rs. 25 Crore, Rs.
              34,13 Crore Balance
              Payment Rs. 1040073500
              Letter No,R0012 dated
              21/03/2019 Voucher no    »


              RO02 7
     1        NABARD (State Share) Letter             14.30
              no. NB(PB)/SPD/69-49/RIDF-
              2005-4/146th PSC/2016-17
              dt 07/03/2017 Loan
              Sanctioned Rs.
              1,30,00,00,0007- Public
              Works/PWD/PrL. Secy. /CGSN
              0321891 dated 02/05/2018
              Letter No.RO05 dated
              30/07/2018 Voucher no    -
              R00008
     12       NABARD (State Share)Letter              17.88
              no. NB(PB)/SPD/69-49/RIDF-
              2005-A/146th PSC/2016-17
              dt 07/03/2017 Loan
              Sanctioned Rs.
              1,30,00,00,000/- Public
              Works/PWD/Prt. Secy. /CGSN
              0323001 dated 06/09/2018
              Letter No,ROOO6 dated
              25/09/2018 Voucher no »
              R00012
     13       State Share received                     0.55
              through FD Letter No
              FD/FE4/SR.ASST
              2/€CG5NO323439 dated
              24/12/2018 against Total
              Release in letter Rs.
              1 0-45600000Letter No, RO013
              dated 21/03/2019 Voucher
              no - RO0O28
                         Total                      270.87
     14       interest received during the             0.75
              year
                      Grand Total                   283.02

  Certified that I have satisfied myself that the conditions on which funds were sanctioned have been duly fulfilled /
  are being fulfilled and that I have exercised the following checks to see that the money has been actully utilized
  for the purpose for which it was sanctioned.

  Kinds of checks exercised:

  (t) It has been ensured that physical and financial performance under PMGSY has been according to the
  requirements as prescribed by the Goverrent of India.

  (ii) It has been checked rra ensured that assistance released by the Goverment of India for implementation of the
  programme (including fry        {rative expenses) has not been diverted and utilized for any item expenditure which
  ts not admtmbleas pc~

      hiet Engineer     3]Q
     P. Roads & Bridges          Sev kc&rd
     SAS,Nagar,       j

Page 3 of 4                          Generated On ; 25/09/2019 O8:16 AM               2014 NRRDA, All rights reserved.
          UTILIZATION CERTIFICATE FOR THE YEAR                               2018-2019 (31/03/2019) UNDER
                  PRADHAN MANTRI GRAM SADAK YOJANA (PROGRAMME FUNDS)

Agency: Punjab Roads & Bridges Development                                    1,    Certified that a sum of Rs. 238.13 Cr
Board, Mohali.                                                                      was received as grants-in-aid from
State: Punjab                                                                       Goverment of India during the year
A. Unspent Balance as on 01/04/2018                                                 2018-2019 & a sum of Rs. 32.73 Cr
      (Beginning of the FY): Rs. 11.38 Crore.                                       was received as grants-in-aid from
B.    Grants received during the year 2018-2019                                     Goverment of Punjab during the year
                                                                                    2018-2019 as per details given in the
      from Government of India.                                                     margin, a sum of Rs. 11.38 Cr being
 S.No.                                                  Amount                      the unspent balance of previous year
                     Letter No. & Date                (Rs. in Crote)
                                                                                    2017-2018 has been brought forward
     1                                                      25.00
          Leer na J-12031/1/2015-RC (FMS                                            for utilization during the year 2018-
     2                                                      25.00
          341960) dated 23/122017 PGSY-I                                            2019, Interest receipt of the Agency
     3    (Batch I) (FY 2017-2018) Rs 318 7.3 Crore         25.00                   during the Year 2018-2019 is Rs. 0.71
     4                                                      25.00                   Cr (31/03/2019), Other miscellaneous
     5    NABARD (State Share) Public                       14.30
          WortsW/Pet Secy /CGSNO321891                                              receipt of the Agency during the year
          dated CZ05/2018                                                           so far is Rs. NIL Cr.
     6    NABARD (State Share) Pubig                        17.88
          Wors.PW-PrtSecy /CGSANO323001
                                                                              2.    It is certified that a sum of Rs. 231.28
          dated 06092018                                                            crore only has been utilized by SRRDA
     7    Lezer ng J-12031/1/2015-RC (FMS                   34.13
          341960)dated 23/122017 PMGSY-                                             Punjab during 2018-20 19 for the
                 y(FY 2017-20181 Rs. 318.73 Crore
                                                                                    purpose for which it was sanctioned. II
      8                                                     24.00
                                                                                    is further certified that the unspent
      9    1Lezerno. .-12031/1/2015-RC(FMS                  20.00
     10   "341960) dated 23/122017 PIGSY-                   20.00                   balance as on 31103/2019 Rs. 51.67
           (Bath I) (FY 2017-2018) Rs. 31873 Crore
     11                                                     20.00                   crore.
     12                                                     20.00
          (State Stare) Letter ne FD-FE/SR.ASST
          2CGSNO323439 dated 24/022018 Rs
     13   1,04,56,00,000/- excess funds Rs,                   0.55
          55.26,500/- received against Certre Sare
          cf Rs 3.18.73.00.000%
                  Total                270.86
C. Interest received during the year 2018-2019
   (31/03/2019) Rs. 0.71 Crore.
0. Other miscellaneous receipts, if any, under
   PMGSY: Rs. NIL Crore.
E. Total funds available Rs.282.95 Crore.

3. Certified that I have satisfied myself that the conditions on which funds were sanctioned
      have been duly fulfilled I are being fulfilled and that I have exercised the following checks
      to see that the money has been actually utilized for the purpose for which it was
      sanctioned.
Kinds of checks exercised:
(i) The Agency's statement of accounts for the year 2017-2018 duly audited by the Chartered
      Accountant has been received and accepted.
(ii) It has been ensured that physical and financial performance under PMGSY has been
      according to the requirements as prescribed by the Government of India.
(iii) It has been checked and ensured that assistance released by the Government of India for
      implementation of the programme (including administrative expenses) has not been
      diverted and utilized for any purpose or on any item of expenditure which is not admissible
      as per the programme guidelines.

                                                                  .f=
                                                                       F BANSAL Arouri ef P035Y8$ #3$ Y 0142
                                                                                                           221 90¢ Prag Fas 21 -1-2821 9 ¢
                                       SBI
         S.C.O. 27-28, Madhya Marg, Sector: 7-C, Chandigarh - 160007.



                    Bank Certificate as on 31° March, 2019

of Punjab Roads & Bridges Development Board, SCF 61-62 Phase 2,
Mohali (PMGSY Program Funds Account)

  Sr. No.                       Bank Ale No.                   Balance
     1                      A/c No. 10506608012                     5,000.00

    2.                           Flexi FDR's                 55.67.92.669.10

                    Total   (PMGSY Program Funds Accou nt)   55,67,97,669.10


(Rs. Fifty-Five Crore Sixty-Seven Lac Ninety-Seven Thousand Six Hundred
Sixty-Nine & Ten Paisa)
                                    SBI
      S.C.O. 27-28, Madhya Marg, Sector: 7-C, Chandigarh - 160007.



            Detail of Accounts linked with SBI Ale No. 10506608012

                  State Bank of India Ale No. 10506608012
    Sr. No.       Balance as on 31/03/2019
        1         SBI 10506608012                               5,000.00
        2         Flexi FDR 37968924600                   2,02,47,114.10
        3         Flexi FDR 38346847612                  53,65,45,555.00
                  Total                                  55,67,97,669.10

(Rs. Fifty-Five Crore Sixty-Seven Lac Ninety-Seven Thousand Six Hundred
Sixty-Nine & Ten Paisa)
             BANK RECONCILIATION STATEMENT (PROG) for the month MARCH 2019
Sr. No.                                          Particulars                                                      Balances
  (a)     Balance as per State Cash Book (31/03/2019)                                                           51,67,18,545.10
  (b)     Cheques issued but not encashed                                                                        4,00,79,124.00
  (c)     Remittances made in the bank but not acknowledged by the bank                                             Nil
  (d)     Balance as per bank passbook (31/03/2019)                                                              55,67,97,669.10

          Online Balance                                                                                         51,67,18,545.10
          Difference                                                                                                        0 00


                                                                                                    «wons"             56f5%9
                                                                                                                            t
                                                                                                                                   Ar
                                                                                                            lo»




                                                                                                                DE31-03-2019\Bank Recorc#ton Prog J1 .03-2019
                            F \BANSAL\Accounts of PMGSYorty For NRRDA'BRS PGSY Wons\1 03-2019 RECONCILE0ON FOX R\Prog
                                          BANK RECONCILIATION STATEMENT MARCH 2019             ·ROG)
                                                                                                       PREVIOU S CHEQUES NOT CLEARED
         Sr.
                      Date         Ch. No.                   Amount (A)            Not Cleared (C) rs Cc Previous Ch.
        No.                                                                                                                        Date
                                                                                                   AtNet Cared (E)] Ng,


                  30/03/2019EPAY  PB1S20                                             48,34,169.00
         52                  18-1903019 Punjab Mandi Board Fazilka

                  30I03/2019 EPAY1PBl12/20                                           34,10,125 00
         12                  18-1903003    p-an Mandi Board Tar Taran
                                           +rev
                                                                                                            (1.00) PFuS Sang/ar   21.08/2018
                  30/03/20 19 £PAY/PB17/20                                           10,07,241.00
                                18-1903005       Provincial Division Sangrut
                  30/03/20 19 EPAYPBT7/2O                                             8.19.466.00
                                1E-1903006       Provincial Division Sangry?
          3       29./03/20 19       130803      Punjab Mandi Board Nawanshe har        35.331.00
          2       27/03/20 19        905904      Construction D
                                                              ivision Moga           2.44,476.00
          4       27/03/20 19        905906      Construction Division Moga          1.33.47660
         6        28/0320 19         905908      Construction Division Moga          1.26.208 00
         6        28/0320 19         906151      Construction Dvision '1 Ludhiana 33,05200
          7       28/03/20 19        906152      Construction Division 1 Ludhiana      84,81400
         8        28/03/20 19        906153      Construction Division 1 Ludhiana    1,56,670.00
         9        28/03/2019         906154      Construction Division 1 Ludhiana      70.6s2o0
         10       28/03/2019         906155      Construction Division 1 Ludhiana       7,353 00
         11       29/03/2019         906161      Construction D
                                                              ivision 1 Ludhiana       66,104.00
         12       29/03/2019         906162      Construction Division 1 Ludhiana    1,69,628.00
         13       29/03/2019         906163      Construction Division 1 Ludhiana    3,13.340 00
         14       29/03/2019         906164      Construction Division 1 Ludhiana         04 0
                                                                                     1,41,3
         15       29/03/2019         906165      Construction Division 1 Ludhiana      14,705.00
          2       30/03/20 19        904-444     Construction Dvision 2 Kapurth ala    96,997.00
          3       30/03/20 19        90-44-45    Construction Division Z Kapurthala    96.997.00
          4       30/03/20 19
                    l
                                     904446      Construction Division 2 Kapur'thala 1,93,994.00
          4       29/03/20 19        10057       Punjab Mandi Board Gurdaspur            ·255.00 Excess amount cleared in Bani Rs 51,028-
         12       28/03/20 19        10065       Purab Mandi Board Gurdaspur         1,38.809.00
                  28/03/20 19 £PAY.  PBS201                                          43,91,841.00
         14
                               8-1903002         Punab Mandi Board Gurdaspur
              ,   30/03/20 19 £PAY.PBS201                                            58,76.366.00
         T                     81903019          Provincial Division Ferozeput
              ,   30/03/2019 £PAY/PSS201                                            1,09,73,398 00
         1%                    31903020          Provincial Division Ferozeput
        19        25/03/2019       906784        Provincial Division Ferozepur        1,18,049.00
        20        25/03/2019       906785        Provincial Division Ferozepur          59,025.00
        21        25/03/2019       906766 Provincial Division Ferozepur               1,18.050.00
        22        25/03/2019       906787        Provincial Division Ferozeput        1,29,511.00
        23        25/03/2019       906788        Provincial Division Feroze
                                                                         pur            64,756.00
        24        25/03/2019       906789        Provincial Division Ferozepu!        1,29,512.00
        25        25/03/2019       906790       Provincial Division Ferozeput         1,64,048.00
        26        25/03/2019       906791        Provincial Division Ferozepur          82,024.00
        27        25/03/2019       906792        Provincial Division Ferozepur        1,64,048.00
        28    No,
                  26/03/2019       906793        Provincial Division Ferzepur           39,047.00
        29        26/03/2019       90679-4       Provincial Division Ferozepur          19,523.00
        30        26/03/2019       906795        Provincial Division Ferozepur          39,048.00
        31        28/03/2019       906796        Provincial Division Ferozepur  20,027.00
        32        28/03/2019       905797        ProvincialDivision Ferozepur   10,013.00
        33        28/03/20 19      906798        Provincial Division Ferozeput  20,028.00
        34        28/03/2019       906799        ProvincialDivision Ferozepur   37.930.00
        35        28/03/2019       906800        Provincial
                                                    .       Division Fe
                                                                ·- e,oz.epur    18,965.00
        36        28/03/2019       906801        Provincial Division Ferozepur 3 7,930.00
        37        28/03/2019       906802        Provincial Division Ferozeput  38,555.00

F BANSAL Accounts e! PMGSY\
                          Monthly Fer NRRDA\BRS PMGSY Wen$\31-03-2019 RECONCI A'TION FOLDER\Prog 31-03-2019\Bani Recanalaton Prag 31-03-
                                                                1                                                                  2019
  SHAMMI GARG & CO.                                          SCO 24, UGF,
  Chartered Accountants                                      Surya Shopping Complex,
                                                             National Road, Ghumar Mandi
                                                             Ludhiana
                                                             Tele :+91 1614666361
                                                             Email : office@sgargco.com

                                                                  UDIN : 19095431AAAABN6619
                                    Independent Auditor' Report


 REPORT ON THE FINANCIAL STATEMENTS

 We have audited the attached consolidated fi   nancial statements of the PUNJAB BOARDS &
 BRIDGES DEVELOPMENT BOARD, SCF 61-62, PHASE-II, SECTOR-S5, MOHALL, PUNJAB which
 comprise the consolidated Balance Sheet as at March 31, 2019 and Income & Expenditure of
 the Board for the year ended in respect of PRADHAN MANTRI GRAM SADAK YOJANA (ADMIN
 FUND), and a summary of significant accounting policies and other explanatory information,

 MANAGEMENT'S RESPONSIBILITY FOR THE FINANCIAL STATEMENTS

 The Management isresponsi                                      nancial statements that give a true
                              ble for the preparation of these fi
                      nanci
and fair view of the fi      al position and financial performance of the Board accordance with
 the Accounti ng Standards and in accordance with the accounting principles generally
accepted in Indi                   lity includes the design, implementation and maintenance of
                  a. This responsibi
internal control relevant to the preparat                                      al statements that
                                             ion and presentation of the financi
give a true and fairview and are free from material misstatement, whether due to fraud or error.
AUDITOR' RESPONSIBILITY

Our responsibility is to express an opinion on these financial statements based on our audit. We
conducted our audit in accordance with the Standards on Auditing issued by the Institute of
Chartered Accountants of India. Those Standards require that we comply with ethical
requirements and plan and perform the audit to obtain reasonable assurance about whether
the financial statements are free from material misstatement,

 An audit involves performing procedures to obtained audit evidence about the amounts and
di                  nancial statements. The procedures selected depend on the auditor's
  sclosures in the fi
judgment, including the assessment of the ris     ks of mater  ial misstatement of the fi nancial
statements, whether due to fraud or error, In making those risk assessments. The auditor considers
internal control relevant to the Board's preparati   on and fair presentation of the fi   nancial
statements in order to design audit procedures that are appropriate in the circumstances, but
not for the purpose of expressing an opinion on the effectiveness of the Board's internal control.
An audit also in cludes evaluating the appropriateness of accounting policies used and the
reasonableness of the accounting estimates made by management, as well as evaluating the
overall presentation of the financial statements. We believe that the audit evidence we have
  obtained is sufficient and appropriate to provide a basis for our audit opinion. We report on the
  account of the Board, subject to the Notes on Accounts as per schedule-l that:-

     a. We have obtained all the information and explanation whic       h to the best of our
        knowledge and belief were necessary for the purpose of our audit;

     b. In our opinion, proper books of account as requir
                                                        ed by law have been kept by the Board
        so far as appears from our examination of those books,

     c. The Balance Sheet and the Income & Expenditure dealt with by this Report are in
        agreement with the books of account,



 OPINION

 In our opinion and to the best of our information and according to the explanations given to us,
 the aforesaid financial statements give the information required by the Act in the manner so
 tequired and give a true and fair view in conformity with the accounting principles generally
 accepted in India:

    (a) In the case of the Balance Sheet, of the state of affairsof the Board as at March 31, 2019

    (b) In the case of the income & Expenditure, of the Surplus of the Board for the year ended
        on that date; and

                                                                               n the report,
    (c) The Transactions of the Board, except as detailed otherwise. elsewhere i
        which have come to our notice have been within the delegated powers and budge
        approved by the Board.



For Shammi Garg & Co
Chartered Accountants



(ShcmmlG~
 Partner
(Membership No.: 095431]
  rm Registration No. : O17212N)
(Fi
Place: Chandi  garh
Date: 20/09/2019
•


    PUNJAB ROADS & BRIDGES DEVELOPMENT BOARD MOHALI CHANDIGARH

       (A) SIGNIFICANT ACCOUNTING POLICIES

       1.   BASIS OF ACCOUNTING

      The Financial Statements are prepared under the historical cost convention as a going
      Concern on hybrid system of accounting and in accordance with the Accounting Standard
      issued by the Institute of Chartered Accountants of India,

      2. FIXED ASSETS

      Fixed Assets are stated at cost of constructing Rural Roads. up-gradation of Roads including
      expenses related to construction and up-gradation of Rural Roads in Punjab.

      3.    DEPRECIATION

      The Board does not charge Depreciation on the Roads Constructed,

      4. RECOGINTION OF REVENUE/EXPENDITURE

      The Board follows Double Entry system of Accounting,
     S. SEGMENT REPORTING

     The Board is an apex body of Constructing/Upgrading of Roads & Bridges and
     Constructing/Up-gradati  on of Rural Roads along with Sign Roads etc. which in context of
     AS-17 'Segment Reporting' issued by the ICAl is considered only reportin  g segment. So
     separate reporting is not necessary,

     6. OTHER ACCOUNTING POLICIES

     The Board has been formed under Act for development of Roads & Bridges infrastructure in
     the state of Punjab, it has been funded by Central Govt. under P.M.G.S.Y. as an
     autonomous Board and its main objectiv    e is construction Maintenance and strengthening of
     Rural Roads. According, it is not commercial organizati     on operating for profits. Hence, it
     follows generally accepted accounting principles in respect of accounting policies nof
     specifically referred to herein above as applicable to such organizations,

    (B) NOTES IQ ACCOUNTS

            ngent Liabilities not provided for FY 2018-19 : NIL
     1. Conti
    2. During audit we found that in most of the cases Opening & Closing balances of manual
       cash book was different from the balances shown by onine cash book,
    3. In most of the cases it was found the expenses were booked under wrong heads or inter-
       heads. All the divisions are using Misc. Office expenses as general head to book different
       expenses, i.e. Petrol Expenses, Vehicle Repair, Telephone etc,
I




          4, In the opinion of the Management the Current Assets [Including stocks, stores and
             consumables, as valued by the management), Loans & Advances are approximately of
                                       zed in the ordinary course of business,
              the value stated, if reali
         5. The Board has been set up by Govt. of Punjab, as an apex body for constructing
            upgrading rural roads, under, PMGSY scheme in the state of Punjab and by virt ue of
            provision of a Section 10 {23C)(iab) of the Income tax Act, 1961 it is exempt from
            payment of income tax and therefore, no provision for taxation has been made in the
            accounts.
         6.   Expenses vis-g-vis Budget;    In case of various expenses incurred, all the expenses are
              within the budgetary limits and in respect of special items, not covered the Budget
              expenditure has been incurred only after obtaining prior approval of the Board.
         7.   Related Party Disclosures; The Board is an autonomous body set up          by Govt. of Punjab
              having no individual interest. Therefore. there is NIL disclosure under this head, as required
              by the Accounting Standard 22
         8. Deferred Tax Assets Liabilities; The Board isexempted from taxation under the provision of
            Section 10 (23CJ(iiab) of the Income Tax Act, 1961.in view of this there is no di
                                                                                            sclosure for
            Deferred Tax Asset/Liabilities as required by Accounting Standard 22,
         9. Previous year's fi gures have been regrouped & re-casted wherever considered
            necessary.
         10. Schedules attached form part and parcel of Balance Sheet of the Board as at 31.03.2019




    For Shammi Garg & Co
    Chartered Accountants,©
                              '3 [CNN'&a

    (Shammi Garg)
     Partner
    (Membership No.: 095431)
    (Firm Registration No. : 017212N]
    Place: Chandi   garh
    Date: 20/09/2019
  t DIN : 19095431AAAAHN619

                                                               PMGSY ADMINISTRA TIVE FUND
                                                                   STATE BALANCE SHEET
                                                UNIAB ROADS & BRIDG ES DEVELOPME             NT BOARD, MOHALI
                                      (Referred to ia Paragraph 1J.4.3 ef the Account»Masual ef Adalaistrati e Espees Fusd)
                                                       CONSOLIDATED BALA         NCE SHEET AS AT 31.03.2019


  Linea                 CA[TL_END Sp LIABILITIES                            Seled ale                   CUR RENT YEAR                  PRESTOL'S YEAR
                                                                    LI (PMGSY/SCH/F-S2A·AD M)                      22,657,829S                 24,941,4638
        2    [State Administrative Expenses Furf                    LI (PMGSY /SCH/F-$2A -ADM)                                     .                          .
                                                                    L2 (PMGSY/SCH/F-S2B-ADM)                          339,704 S4                 340,635.23
                                                                    L2 (PMGSY/SCHF-STB-ADAM)                       12,050,4724                 11,212,960.77


                                                                    LJ (PMGSY/SCH/F-S2C-ADM)
                                                                                                                                                             .
    7       [Current liabilities
                                                                    LA (PMGSY/SCH/F-S2D-ADM)                           10,656 00                      6 o0
                                                                                                                                                  10,6$

                                   TOTAL
                                                                                                                                                    7
             TS
            A,884
                                                                                                          Current Year
    I       Cash inChest with SRRDA

    :       Cash inChest wth PIUs
                                                                                                                     $$4,212 00                  $$4,212 00
    3         k Balance
            Bar
                                                                                                                   14,552,15$ 19              16,361,5188
    4       Imprest with Staff

    s       CurrentAsset                                           AI (PMGSY/ISCH/F-S2E-ADM)                         387,403 0                  32$,0960
    6       Durable Assets                                         A2 (PMGSY/SCH/F-S2F-ADM)                    19,264,889 0                   19,264 ,$39 0
    7       /nrecengile! Bari Authorization
                                   TOTAL,
                                                                                                                                                    715.89
SO1ES ON ACCOST AS FER ASS}XLRE ATTACHED


                                                                                                   CO MPILED FROM THE RECORDS & OTHER
                                                                                                   DOCUMEN  TS PROVIDED BY THE VARIOUS
                                                                                                   DIVISION AND BOARD
                                                                                                   NOTE·AS PER OUR SEPARATEREPORTOF EVEN
                                                                                                   DATE ATTACHIED
                                                                                                   FOR SHAMSI GARG AND CO
                                                                                                   CHARTERED ACCOUNTANTS¥-}-
                                                                                                   (FIRM REG. NO. 0172128)


     - 2009/20 19
DATED:
PLACE: » CHANDIGA RH                                                                              CA, SHAMMI GA
                                                                                                   PARTNER
                                                                                                    N O, 09543 1
                                                                                                  SL.
¢
                                                   .
                                                 CON                     T AS AT 31.03.20 19
                                                    SOLIDATED BALANCE SHEE
         sCHEDT$ -1T(Adi@istrathve FY           ses Fwd)
                                                                                                "urreat Year               Previous Yea n
         PART;L CEN          STRATIVEEXPENSE
                   TRAL ADMINI             S FLSD
         Opening Balance                                                                                30 00
                                                                                                  $45$772                      $41$0444          00
         Add Funds Recered frees MORD Pay & Accounts Officers                                             0          00            26 786 00
         Total                                                                                    5487723000                   $487723000
         Funds froe GOT                                                                                         .
         Deduct as per Iroe & Espediture Aoust
                                                                                                                                             .
         Balance of which
          a) Asets per Contra
                                                                                                 32219400II                    29935766 11
          b) Fors partof Bark Balance, deposits& Current Asset                                                  a                            .
         PART ±J} STATE ADMEN                 y;p         .
     Operimg Balance
     Add. FundsReceived SO FAR
                                                                                                            e


                                                                                                            .
                                                                                                                                             .
                                                                                                                                         .
     Total                                                                                                  .                            .
     Deduct as per Iese A Espeditare A€oua       f
     Balance of which:
      a) Ast»per Contra                                                                                     .
      b) Ferrs pert of Harl Balance, depositsl Curert Assets
                                                                                                                                         .
         TOTAL
                                                                                                            .                            .
                                                                      (A)                      22£67            s9        24,941,463 19


     SC HEDULE -12 SURPLUS                snseyDCEIL_ANEOs ISCoMr                              Current Year               Pre leas Yea
     Oper=ngBalaze (A)
     Add Transf   er of surplus from lcore & Expend@ure Account (B)
     interest from Bar k ( Board )                                                                                                       .
                                                                                               11,973,733 23              11,136,221 77
     Interest froes Harl (Divisions)                                                               76,73923
     Ms Recrips (Beard)                                                                                                       76,73900
                                                                                                   46,$1954                   47,75023
     Ms Ripes ('Divisors)                                                                         292,84.5 00                292,445 00
     Received frees Din XEN                                                                                 .
     Delaet Transferred to the SRRDA daring the year (C )                                                   .                        Q




     .                 Tetal (A) + (B)»   .                                                    1} 399.177,9g              II

    CH LE        _ 13 DEPQs[Ts REAyABLE
                                                                                               "arre st Yran              Treloar Yea
                                              ious year
    Balance as per the Balance Sheet ofthe Prev
    Ad! Received Dung the year                                                                          .
    Les Refunded daringthe year                                                                         .
    [Closing Balance                                                                                    .                            .
    Detuh of D-et O,        ding for over Three Years
                             g,
                                                                                                                                     a
                         Tetal                                                                          .
    • To be ud oly in Annual Balance Sheet                                                                                           .
    SELE_> L4 CURRENT LIABILITIES
                                                                                               'arrest Year                    lets
                                                                                                                          Pre Yea
    Upaid   Bills Outstanding
    Bills Outstanding   for more than SixMoth
                                            s
                                                                                                        .                            .
    Numb er of Parties Amount
    Statutory Liabilities
                                                                                                        .                            .
    Amoart Ref Free Division XEN
                                                                                                                                     .
                                                                                                  10 656 00                    10 656 0
                             Tetul
                                                                                                  To                           I
     To be used only in Annual Balance
                                a      Sheet
?
                                                              ,
                                           CONSO LIDATED BALA NCE SHEET AS AT 31.03.2019
•    SCHEDULE- A1 CURRENT ASSETS                                                            Curr±st Year    rev Year
                                                                                                                  leas
    [A.)  Misc. Adva nces
     i) Considered Safe                                                                                 .
     in) Considered U- Safe
     in) TDS
                                                                                                                      .
                                                                                              317,403 00       32$ ,096 00
    r) Consultation Fees (Soil 'Testing)
                                                                                                     .                .
    v) Wark Doe by Cotractere
                                                                                                     .
                                                                                                     .                .
    vi) Refunded by PRBD
    vu) Traraferto DPT                                                                                                .
                            Total
                                                                                                                      .
                                                                                             317,403 00       325.096% g
    SCHEDULE_> A2 DURABLE ASSETS                                                           Current Yea1     Pries Year
           ASSETS
    DIABLE R
    Opening Balance
                                                                                           19,264,$$9 00    1 9,264,3$9.00
    Ad Additions daring the Year                                                                     .
                     loin» Halate
                                                                                           19,264,889.00    19,264,889.00

    HANK BALANCE
    DI¥A DE
                                                                                           Carres t Yea     Previews Year
    Harl Balance                                                                           14,1$2,158 19
    fL,%4                                                                                                   16,361.518 89
    Cest
                                                                                              $$4,21200
    Bani Balance
                           Tetal
                                                                                                    .          $$4,212.00
                                                                                                                      .
                                                                                                  170.49    16,915.730.89
¢




                                                                             PMGSY-F-1-(I&E-2)
                                                               PMGSY ADMINISTRATIVE EXPENSES FUND
                                                         Income & Exependiture Account (SRRDA) for 2018-19
                                           (Referred to ia paragraph 13.4.2 of the Accounts Manual of Administrative Expenses Fund)
                                                      Name of SRRDA Pun &Brig+s          lab  DevelgmetBoard,Rods  Mohs
                                           Particular                                         SRRDA Amoat             ALL DPR. At          Suto (Cel. 2+3)
                                               1
      of F
                            •    ta   Fett    fgm oyt     gf trqi
                                                                g
                                                                                                    2                         J
                                                                                                                                                  •
      Erpeases
     [Audit 8 Accounts
              Erpese
                                                                                                  1,177,834 00                        .       1,177.83400
                                                                                                  7,852,837.00             2,891,804 .00     10,744,641.00
     Telephone Erper&es
                                                                                                    450,314.00              399.91800             859 217 tr
     Ofie Esper&es
             g
                                                                                                  1,961,111.00             9251.809. 11      1t.212.920.11
                                                                                                    280,010 00               15,644.00          295,654 00
     internetExpenses
                                                                                                    160.972 00                         .
                                                                                                                             334, 966 00        495 934 00
     Corp.uter Mairt,
     Fax 8 Postage
                                                                                                            .                801,791.00           801.791.00
     Otoe Feting
                                                                                                            .                 44. 809.00           44. 809. 00
                                                                                                            .                         .                      .
    Hire ct Vehicle
    Cc» Baiding Rent
                                                                                                            .                (10,500.00           (10,500 00
                                                                                                            .                         .                      .
    [Worth/ Carleen&e / Meeting / Seminar
                                                                                                 3,510,766         0         152,666 00       3,663,432 00
     Stator=ary
                                                                                                 1,257 .710 00             1,693 9090         2 4951,619.00
    kart et Vehicle
    Tairing fer SailDetore=t
                                                                                                            .                (a 970.00            (38   970.00
                                                                                                            .                30.000.O0            30 00000
    TOTAL Expenses tale to the Balance Sheet                                                    16,651,554.00            15,567,846 .11     32,219,400.11
    Part IL State Administrative      Fund         (tr   the State Govt. Expen ses}
    (Lust te expenses Account head wise)

    TOTAL Expenses taken to the Balance Sheet
                                                                                               16,651,554. 00           15,567,846 .11      32,219,400.11
    L Surpluses

    ingot?


                   Income                                                                           46,819.54              292. 885 00         339,704 54
    lrterest lnaore                                                                            11,973,733.23                 76,739.23      12,050,472. 46
    Total
                                                                                               12,020,552.77               369,624.23      12,390,177.00
    Carried to the Surplusesand Reserves i the Balance Sheet)                                  12,020,552.77               369,624.23      12,390,177.00
,


                                          Pet,AF pug hog f,pg
                                                        Ta
                                      3?aft ,A(f f'ITtat tare
                                             fh@put at. A,A}
                             rf e ge opp Fl 4 ofJte 4ct»u
                                  of 4s tr te fagotPat

     we # @ :Apt        toe y {grt#g t gtat
     et




    tot#ties   ('etr   A@tat#tepee
               yd                                               s 22714 754 0         s 25 000.348#2
               tr 4ct>a(pees  e   farf                               s -8,125 00         s -44 00925
                   rs { free test ar
               'orp@
               etwr eorpts)
               pest.Rprye
               (are¢ Ltte
                                            »AFAV-$2
                                            EA©p
                                                   ¢

                                                8-922
                                                                       177 00
                                                                s 12200.



                                                                     s g44
                                                                          s 2o0               ....
                                                                                      s 1ts453S409



                                                                                         T 124s£ oo
               crtet tar tort                at            ore s            d00               s 90


     Anet»

               (a (rs!
                       L Tata pas
               (€a e{art   =ts {#;4
                           p» Ly
                                                                s   31.248.14.2
                                                                          s 49

                                                                    s 44.21200
                                                                              9

                                                                                              ....
                                                                                      s 34.,25.71$


                                                                                        s $84.212 00
                                                                                                       £2




               tar» .we
                    et
               est pf a! tee
               tac arc P
               egret   tea
                                                                          ...
                                                                s 42s2.5%n9



                                                                          .....               . ...
                                                                                               Ea
                                                                                      E 143M1St£



                                                                                              s ad
               (re a8rt
                                                                    s M742102           s 22500% 0
               par Asar®
                     tie
               Ls tared 4root P
               toerred t» L
                               yf


                        Arty 'Ttal
                                            we
                                                                <4 0


                                                                s
                                                                          ....
                                                                    11C£A 4e2
                                                                                      s 19.2M4 BJ
                                                                                              s g 00

                                                                                   n 3MSC24, 71£
                                                                                               48
                                                                                                       Q
          UTILIZATION CERTIFICATE FOR THE YEA R 2018-2019 (31/03/2019) UNDER
             PRADHAN MANTRI GRA M SADAK YOJANA (ADMINISTR ATIVE FUNDS)


                                                                          1.   Certificated that a sum of Rs. NIL crore
Agency: Punjab Roads & Bridges Development
                                                                               only was received as grants - in - aid
Board, Mohall.
                                                                               from Government of India during the
State: Punjab                                                                  year as per details given on the margin.
A. Unspent Balance as on 01/04/2018                                            Rs. 1.63 crore being the unspent
    {Beginning of the FY): Rs. 1.63 Crore.                                     balance     of    the     previous
                                                                                                                year
                                                                               2017-2018, has been brought forward
B. Grants received during the year 2018-2019
                                                                               for utilization during the year 2018-
    from Government of India.
                                                                               2019. Interest receipt of the Agency
                                                    Amount                     during the year 2018-2019 (upto
 S.No.                 Letter No. & Date          [Rs, in Crore)

    1                                                         -                31/03/2019) was Rs. 9.08 crore. Other
    2                                                         a      a         miscellaneous receipts of the Agency
    3    ® a                                                  ooo
                                                                               during the year were Rs. NIL crore. (as
               .   4



                            Total                          NIL                 per details attached)

c   Interest received during the year 2018-2019                           2.   It is certified that a sum of Rs. 0.23
    (31/03/2019) Rs. 0.08 Crore.                                               crore only has been utilized by SRRDA
D. Other miscellaneous receipts, If any, under                                 Punjab during 2018-2019 (31/03/2019)
                                                                               for the purpose for which it was
    PMGSY: Rs. NIL Crore.
                                                                               sanctioned. It is further certified that the
E Total funds available Rs.1.71 Crore.                                         unspent balance of Rs. 1.48 crore
                                                                               remaining at the end of the year
                                                                               (31/03/20 19) will be utilized.

3. Certified that I have satisfied myself that the conditions on which funds were sanctioned have
   been duly fulfilled / are being fulfilled and that I have exercised the following checks to see
   that the money has been actually utilized for the purpose for which it was sanctioned
Kinds of checks exercised:
(i) The Agency's statement of accounts for the year 2017-2018 duly audited by the Chartered
      Accountant has been recei  ved and accepted.
(ii) It has been ensured that physical and financial performance under PMGSY has been
      according to the requirements as prescribed by the Government of India.
(iii) It has been checked and ensured that assistance released by the Government of India for
      implementation of the programme (including administrative expenses) has not been diverted
      and utilized for any purpose or on any item of expenditure which Is not admissible as per the
      programme guidelines.




                                                                    %f»
                                           F ASALtort» sf PSYrtvy fer N@#EA MRSPA3$Y wen" cir =33 8 Arr" Agwt #arc rvy o¢
                                         SBI
         S.C.O. 27-28, Madhya Marg, Sector: 7-C, Chandigarh - 160007.



                    Bank Certificate as on 31° March, 2019

of Punjab Roads & Bridges Development Board, SCF 61-62, Phase 2,
Mohalj (PMGSY Administrative Expenses Fund Account)

  Sr. No.                       Bank Ale No.                          Balance
     1                      A/c No. 10506608056                         1,00,268.00

    2.                            Flexi FDR's                        1,47,51,890.89

                Total (PMGSY Administrative Expenses Fund Account)   1,48,52,158.89


(Rs. One Crore Forty-Eight Lac Fifty-Two Thousand One Hundred Fifty-
Eight & Eighty-Nine Paisa)
                                 SBI
      S.C.O. 27-28, Madhya Marg, Sector: 7-C, Chandigarh - 160007.




         Detail of Accounts linked with SBI A/c No. 10506608056

              State Bank of India Ale No. 10506608056
    Sr. No.   Balance as on 31/03/2019
        1     SBI 10506608056                            1,00.268.00
        2     Flexi FDR 31382972583                   1,47,51,890.89
              Total                                   1,48,52,158.89

(Rs. One Crore Forty-Eight Lac Fifty-Two Thousand One Hundred Fifty-
Eight & Eighty-Nine Paisa)
                                                                                                                                                    g   e




            BANK RECONCILIATION STATEMENT ADMN FUNDS for MARCH 2019
Sr. No.                                  Particulars                                                  Balances
  (a)     Balance as per State Cash Book (31/03/2019)                                                    1,48,52,158.89
  (b)     Cheques issued but not encshed
                                       a                                                                           0.00
  (c)     Remittances made in the bank but not acknowledged by the bank                                   Nil
  (d)     Balance as per bank passbook (31/03/2019)                                                      1,48,52,158 89

                                                                                         Fax Purab Rofr.
                                                                                                       8B
                                                                                                                s.03,-!
                                                                                                 · sRRDA,Punjab
                                                                         Telephone No.            5134632, 5134620
                                                                               Fax No.                     5134640
                                                                              e-mail id. office.prbdb@punjab gov.in

                                                                  Online MARCH 2019                      1,48,52,158.89
                                                                           Difference




                          F BANSAL&countsof PGSYWont\y For NRRDA\BRS PMGSY Wors) 1 -03-2019 RECONCILA'TIN FOLDER&drn 31-03-20199Aimn Recon\ton 31 03-2019
                               BANK RECONCILIATION STATEMENT ADMN FUNDS MARCH 7619

           Sr.                                                                          Prewit enth
                  Date       Ch. No.             Amou nt (A)                                        Previous Ch.
          No.                                                         Not Cleared (C)    CqatsNot
                                                                                          Cared (E)      No.

                                                                                                                   '




                                       Total                                     .              .
                                       G. Total Cheques Not Cleared              .




F BANSALAccountsct PMGSY\Monthly Fer NRRDA\BRS PMGSY Waris\31-03-219 RECONCILATION FLDERA@mn31-03-201%dmn Recantation 31-03-2019