The World Bank
         ECOWAS - Regional Electricity Access Project (Phase 1) (P164044)




   Note to Task Teams: The following sections are system generated and can only be edited online in the Portal. Please
   delete this note when finalizing the document.




                        Project Information Document/
                  Integrated Safeguards Data Sheet (PID/ISDS)

                       Concept Stage | Date Prepared/Updated: 08-Mar-2018 | Report No: PIDISDSC22358




Oct 19, 2017                                                                                                   Page 1 of 17
         The World Bank
         ECOWAS - Regional Electricity Access Project (Phase 1) (P164044)


  BASIC INFORMATION


  A. Basic Project Data OPS TABLE

  Country                          Project ID                     Parent Project ID (if any)     Project Name
  Western Africa                   P164044                                                       ECOWAS-Regional
                                                                                                 Electricity Access
                                                                                                 Project (Phase 1)
                                                                                                 (P164044)
  Region                           Estimated Appraisal Date       Estimated Board Date           Practice Area (Lead)
  AFRICA                           Jun 12, 2018                   Sep 25, 2018                   Energy & Extractives

  Financing Instrument             Borrower(s)                    Implementing Agency
  Investment Project Financing     Ministry of Finance and        Energie du Mali (EDM SA),
                                   Economic Affairs of The        National Water and
                                   Gambia,Ministry of Economy     Electricity Company
                                   and Finance of Guinea          (NAWEC), Electricidade e
                                   Bissau,Minister of Finance &   Agua da Guiné - Bissau
                                   Economic Development of        (EAGB)
                                   Mali

   Proposed Development Objective(s)

    The Programmatic Development Objective is to increase access to reliable energy services in targeted areas and to
    enable cross-border electrification between the recipient countries.
    The Project Development Objective for the proposed Phase 1 operation is to increase access to reliable energy services
    in The Gambia, Guinea-Bissau, and Mali and to enable cross-border electrification between those countries.


   Financing (in USD Million)
   Finance OLD
   Financing Source                                                         Amount
   Borrower                                                                  0.00
   International Development Association (IDA)                              285.00
   Korea WB Partnership Facility                                             0.50
   West African Development Bank                                            28.65
   Total Project Cost                                                       314.15
  Environmental Assessment Category                               Concept Review Decision
   B-Partial Assessment                                           Track II-The review did authorize the preparation to
                                                                  continue



Oct 19, 2017                                                                                                    Page 2 of 17
          The World Bank
          ECOWAS - Regional Electricity Access Project (Phase 1) (P164044)




     Note to Task Teams: End of system generated content, document is editable from here. Please delete this note when
     finalizing the document.


     Other Decision (as needed)


     B. Introduction and Context

     Country Context
       1. West Africa is home to 370 million people, of which 55% live in low density rural areas.
          The region is diverse – economically, culturally, and ecologically – presenting both opportunities
          and challenges to economic growth and development. In 1975, 15 countries came together to
          form the Economic Community of West African States (ECOWAS) with the stated goal of
          promoting economic cooperation and achieving “collective self -sufficiency�?.1 The region is also
          home to the G5 Sahel, a group of countries comprising Burkina Faso, Mali, Mauritania, Niger
          and Chad created in 2014 to improve policy and strategy coordination for development and
          security. In July 2017, the European Commission, France and Germany launched the Alliance
          for the Sahel, which seeks to increase financial and technical resources to the Sahel to address
          the multi-faceted challenges and drivers of fragility and to promote increased resilience and
          economic opportunities, including for the most vulnerable. Among the five sectors of focus, the
          Alliance has proposed an ambitious target of doubling energy access during the period 2018-
          2022 to address energy poverty.

       2. Despite recent economic growth, West Africa remains poor and around 50 percent of the
          population still lives on less than US$2/day2. The countries in the region are some of the
          poorest in Sub-Saharan Africa (SSA) with GDP per capita of under $1,000 on average and as
          low as $363 in Niger. A positive economic trend over the past decade has been driven mainly
          by growing domestic demand, robust foreign investment, favorable commodity prices, and
          improved economic governance. However, the annual 5.46 percent GDP growth that the region
          achieved from 2010-2014 decreased severely in 2015 to 2.25 percent due to the impacts of the
          Ebola crisis and oil price collapse. Thus, while the first Millennium Development Goal (MDG)
          target of halving poverty was met at global level, this was not the case in West Africa. Across
          ECOWAS countries, the poverty rate fell by 18 percentage points (from 63 percent in 1990 to 45
          percent in 2015), equivalent to a 29 percent reduction in overall poverty.

       3. The region therefore needs economic growth that is more transformational, sustained,
          and inclusive to reduce extreme poverty and increase shared prosperity on the scale
          required by the Sustainable Development Goals. Both ECOWAS and the G5 Sahel prioritize
          increased access to modern energy services to deliver such economic growth and alleviation in

 1
   These countries, making up the entire sub-region except for Mauritania, are Benin, Burkina Faso, Cape Verde, Cote d’Ivoire, The Gambia, Ghana, Guinea, Guinea
 Bissau, Liberia, Mali, Niger, Nigeria, Sierra Leone, Senegal and Togo.
 2
   The World Bank defines extreme poverty as living on less than US$1.25 per day, and moderate poverty as less than $2 a day


Oct 19, 2017                                                                                                                                            Page 3 of 17
         The World Bank
         ECOWAS - Regional Electricity Access Project (Phase 1) (P164044)


          household poverty. In 1982, ECOWAS doubled down on regional integration by launching a
          regional energy policy to promote the optimal use of energy resources across its countries. This
          political commitment later led to coordinated actions at each stage of the energy supply chain,
          with a focus on developing the use of regional resources to increase electricity production and
          trade. Their overall aim is to boost and optimize the availability and end use of energy, while
          ensuring increased access to energy services in rural and peri-urban communities. The energy
          sector remains a bottleneck to attracting foreign investment programs, providing basic social
          services, and achieving the Sustainable Development Goals nevertheless.

  Sectoral and Institutional Context
     4. Many of West Africa’s countries are challenged by significant growth rates in electricity
        demand, and underperformance in key power sector metrics. These include insecurity of
        supply as well as state-owned utilities in poor financial and operational condition. It therefore
        remains difficult for utilities that often rely on Government subsidies to maintain existing assets,
        carry out new investments, or mobilize private capital for investments across the sector value
        chain, including electricity access. The root causes underlying these short-comings are: (a) a
        lack of sector planning and institutional capacity to expand the electricity sector in a coherent
        and cost-efficient manner; (b) a lack of adequate transmission infrastructure within and between
        national power systems that curtails the possibility to link remote sources of electricity to the
        main consumption centers; and, (c) insufficient investment in electricity access projects such as
        distribution and rural electrification to bring service to the people, even when electricity is
        available.

     5. Less than 50 percent of the population in the West Africa region has access to electricity.
        In practice, this means that despite the region’s large energy endowments, over 170 million
        people do not have access to electricity and the per capita consumption of electricity is among
        the lowest in the world with approximately 160 kWh consumed per capita. The challenge to
        provide reliable, affordable, sustainable energy services is magnified across the Sahel region
        and pronounced further still in the poorest countries. The G5 Sahel and Senegal have together
        only achieved 26% access to electricity. These countries are also among those with lowest
        electrification rates in rural areas, as only Senegal and Mali have rural access rates that exceed
        5%. In the poorest countries, under 30% of the population has access to electricity (compared
        to 37 % in Sub-Saharan Africa), with overall access rates as low as 10% in Guinea Bissau (just
        2 % in rural areas). On average, access across countries to be included in the proposed program
        remains much lower than the rest of the continent.

     6. In 1999, ECOWAS countries established the West African Power Pool (WAPP), a
        specialized agency designed to support the interconnection of power systems and the
        promotion of cross border electricity trade, which seeks to provide electricity services
        for border communities to reduce poverty and promote wealth creation. Cross border
        electrification is a mitigation measure to reduce economic migration across borders which can
        be disruptive. The WAPP was later followed by the West African Gas Pipeline (WAGP) and a
        common regional energy access strategy (WAEMU4). In 2011, ECOWAS also established the
        ECOWAS Infrastructure Project Preparation Development Unit (PPDU). The PPDU is an
        ECOWAS specialized Agency which is responsible for the development of regional integration

Oct 19, 2017                                                                                       Page 4 of 17
         The World Bank
         ECOWAS - Regional Electricity Access Project (Phase 1) (P164044)


          infrastructure projects in ECOWAS Member States, management of a dedicated infrastructure
          fund, and promotion of PPP in investment financing and project management in ECOWAS.

     7. The ECOWAS approach to the energy sector is based on the recognition of the
        differences in energy endowments, the differences in country load profiles, and benefits
        of optimizing energy resources across the region. This in turn creates both the need to
        capitalize on large scale generation plants designed to support multiple countries and
        opportunities for trade to maximize availability and minimize cost. The implementation road map
        of the WAPP Infrastructure Program is based on realizing distinct but mutually reinforcing
        infrastructure sub-programs, which when fully realized will converge into a unified, well-
        functioning regional power pooling mechanism in West Africa. The sub-programs include the
        Coastal Transmission Backbone (Côte d’Ivoire, Ghana, Benin, Togo, and Nigeria), the Inter -
        zonal Transmission Hub (Burkina Faso, Mali, Côte d’Ivoire, Ghana), the North -core
        Transmission (Nigeria, Niger, Burkina Faso, Benin), the OMVG/OMVS Power System
        Development (The Gambia, Guinea, Guinea-Bissau, Mali, and Senegal), the Côte d’Ivoire,
        Liberia, Sierra Leone, Guinea Power System Development, and the WAPP Strategic Generation
        program.

     8. ECOWAS countries have identified the completion of WAPP infrastructure as a key lever
        in increasing access to electricity given its expected ability to increase reliability and
        lower the cost of supply. By extension, it is expected that utilities will be in better financial and
        operational position to invest in rural access and connect last mile customers. One of the
        recurring features of the power sector in the region is that demand outpaces supply. The
        production deficit in OMVG countries, for example, is 32%. This results from the limited
        availability of generation capacity, lack of maintenance or lack of spare parts, and overreliance
        of countries on thermal power production (up to 85% of the power consumed in some cases).
        Only Guinea has installed hydropower capacity of 124.4 MW though this remains a fraction of
        its potential. To address these constraints, countries have implemented restructuring programs
        focused on opening power production to the private sector. OMVS includes a 200 MW Manantali
        hydroelectric plant in Mali and high-voltage transmission line for the evacuation of the energy
        produced to Senegal, Mali and Mauritania.

     9. Considering WAPP’s expected benefits, countries need to increase and harmonize their
        distribution networks. The challenge of expanding access to electricity in the region is
        compounded by a lack of cogent electrification plans. Spatial planning is currently underway to
        fill the gap in target countries to that effect. Nevertheless, widespread access is critical to
        ensuring absorption of electricity made available through the WAPP’s transmission infrastructure
        and to promote a shift towards cross-border trade for less expensive sources of electricity.
        Furthermore, the historically fragmented systems in the region have resulted in varying quality
        standards across distribution networks. Agreement on quality standards for distribution
        equipment among West African countries would benefit both national grids and the private sector
        manufacturers as they get access to a large contiguous market. There is political momentum
        and a broad recognition at the regional level of the potential benefits in harmonizing distribution.




Oct 19, 2017                                                                                        Page 5 of 17
         The World Bank
         ECOWAS - Regional Electricity Access Project (Phase 1) (P164044)


     10. The costs of electrification at the national level currently remain prohibitive and create an
         opportunity for a regional, programmatic approach. Under traditional national electrification
         initiatives, electricity access expansion via grid connections remains an expensive proposition.
         The Bank estimates that the initial cost of connecting a household in the region could reach over
         $1,000. This is often due to small system sizes that are unable to capitalize on economies of
         scale both for materials (poles, cable, transformers, meters, etc.) and logistics/installation.
         Lessons from national grid electrification projects suggest that to successfully attract private
         sector, and to create a sustainable market one needs economies of scale, transparent policies,
         business procedures. This creates an imperative for the roll-out of a large scale, regional
         electrification program across countries that would capitalize on economies of scale and
         standardization to radically reduce the capital cost of a grid connection for last mile customers.

  Relationship to CPF

     11. The proposed project is consistent with pillars 1 and 2 of the most recent WBG Joint
         Partnership Strategy for the Gambia for FY13-16. This strategy aims to enhance productive
         capacity and competitiveness to improve the country’s resilience to external shocks. Pillar 1
         focuses on promoting a competitive investment climate, strengthening rural development, and
         developing key supporting infrastructure with a focus on the energy sector. Pillar 2 focuses on
         strengthening the provision of basic services, to which electricity access is foundational.

     12. The proposed project is in line with both focus areas 1 and 2 of the Country Partnership
         Framework for Guinea-Bissau for FY18-21, which aims at strengthening the provision of
         basic services to the poor and improving economic opportunities. The note specifically
         highlights expanded electricity services, along with health, education, and water as priority areas
         for investment with a view to providing people with the services, resources, and skills they need
         to create and take advantage of economic opportunities as well as achieving access
         to affordable, reliable and modern energy for all in support of the SDGs.

     13. The proposed project supports the implementation of the Country Partnership
         Framework for Mali for FY16-19, and focus area 2 which centers on the creation of
         economic opportunities. The document specifically highlights the need for improve energy
         infrastructure and improve access to electricity services in rural areas. The objective of such
         investments is to address an inequitable distribution of public resources, increase connectivity
         of the social fabric, and strengthen long-term resilience shocks.

     14. The broader program is also consistent with the current strategies for countries expected
         to be included in subsequent phases. In Benin, the program objectives are consistent with
         the first pillar of the World Bank’s FY2013–2017 Country Partnership Strategy (CPS) on
         “sustainable growth, competitiveness, and employment: increased access to and quality of
         infrastructure services�?. In Burkina Faso, the proposed program is aligned with the first strategic
         priority of the WBG FY17 “Priorities for poverty reduction and shared prosperity, Syste matic
         Country Diagnostic�?: Improving Natural Resources Management. In Chad, it is aligned with the
         second engagement theme of the WBG FY16-20 CPF, focusing on improving returns to
         agriculture and building value chains, with a focus on rural areas and improved connectivity. In


Oct 19, 2017                                                                                       Page 6 of 17
            The World Bank
            ECOWAS - Regional Electricity Access Project (Phase 1) (P164044)


                 Guinea, it is consistent with the first pillar of the WBG FY 14-17 Country Partnership Strategy
                 (CPS) for Guinea: Stimulating Growth and Economic Diversification. In Mauritania, it is aligned
                 with the first strategic priority of the WBG FY 17 “Priorities for poverty reduction and shared
                 prosperity, Systematic Country Diagnostic�?: Improving Natural Resources Management. In
                 Niger, it is aligned with the FY13-16 Niger Country Partnership Strategy (CPS) which focuses
                 on achieving resilient growth, reducing vulnerability and strengthening capacity for service
                 delivery. In Senegal, it is consistent with the first pillar of the WBG FY 13-17 Senegal CPF on
                 “Strengthening the Governance Framework and Building Resilience�?. In Togo, it is aligned with
                 the third pillar of the first area of focus of the joint IDA/IFC/MIGA CPF for the period FY 17-20:
                 Economic Productivity and Job Creation: Strengthen energy, ICT and logistics services.

     C. Proposed Development Objective(s)

     Note to Task Teams: The PDO has been pre-populated from the datasheet for the first time for your convenience.
     Please keep it up to date whenever it is changed in the datasheet. Please delete this note when finalizing the
     document.

        15. The Programmatic Development Objective is to increase access to affordable and reliable
            electricity in the region.

        16. The Project Development Objective for the proposed Phase 1 operation is to increase access to
            reliable energy services in the Gambia, Guinea Bissau, and Mali and to enable cross-border
            electrification in those countries.

     Key Results (From PCN)

        17. The expected development outcome for the overall program, as well as each of its phases,
            centers on an increasing electricity access rate that will contribute to the social and economic
            development of the recipient countries. The expected development outcomes for the overall
            program, as well as each of its phases, include: (i) increasing electricity access rate that will
            contribute to the development of the countries and (ii) enabling electrification of border
            communities (cross border electrification).

        18. PDO level indicators will incorporate the new Corporate Results Indicators3. They are expected
            to remain consistent throughout the program, with targets for each phase to be adjusted as a
            function of the countries included in the project. They will include:

           i.       People provided with access to electricity service (number) – measured as the number of
                    people that newly benefit from electricity services; of which in cross border communities
                    (number)
           ii.      People provided with new or improved electricity service (number) (Corporate Results
                    Indicator); of which women (number) and of which in cross border communities (number)


 3   These are all relevant Bank CRI with respective underlying intermediate indicators. At QER stage, it will be decided which indicators will be used.

Oct 19, 2017                                                                                                                                  Page 7 of 17
         The World Bank
         ECOWAS - Regional Electricity Access Project (Phase 1) (P164044)


       iii.    Percent of households connected to electricity service (access rate), of which for cross
               border communities (access rate)


  Program                        To increase access to reliable energy services in targeted areas and to
  Development                    enable cross-border electrification between the countries.
  Objective
  Phase Sequential or            Phase’s        IPF or     Estimated        IBRD,   Estimated Estimated
  #       Simultaneous           Proposed       PForR or   Amount           IDA,    Approval Overall
                                 DO             Guarantees ($million)       TF,     Date      Risk
                                                                            PPP
  1                        In The      IPF            285*                  09/2018
                                                                            IDA          S
                           Gambia,
                           Guinea
                           Bissau,
                           and Mali
  2       Simultaneous In Benin,       IPF            700           IDA     10/2019      S
                           Burkina
                           Faso,
                           Mali,
                           Mauritania,
                           Niger,
                           Senegal,
                           Togo,
  3       Simultaneous In              IPF            200           IDA     2020         S
                           Senegal,
                           Mali
  Estimated for the Program                           1 185
          • *National IDA allocations in phase 1 include $15 million for Guinea Bissau, $40 million for
              the Gambia, and $40 million for Mali. Other financing to be provided through Regional
              IDA allocations.

  D. Concept Description
      19. The ECOWAS Regional Electricity Access Program has the potential to finance the
          reinforcement and extension of the medium voltage (MV) and low voltage (LV) distribution
          network across eleven countries in West Africa, namely: Benin, Burkina Faso, The Gambia,
          Guinea, Guinea Bisssau, Niger, Mali, Mauritania, Togo, and Senegal. The program is expected
          to include the same two components for phases 1 and 2, which will target different countries in
          each project. The components are: (i) the expansion and reinforcement of electricity distribution
          infrastructure (MV and LV) to maximize the number of new connections; and (ii) project
          management and technical assistance to a joint coordination unit as well as national
          implementation teams concerned. In phase 3 of the program, the team envisages leveraging
          additional private sector investment in distribution infrastructure based on the track record of
          successful private sector participation in O&M under phases 1 and 2.


Oct 19, 2017                                                                                        Page 8 of 17
         The World Bank
         ECOWAS - Regional Electricity Access Project (Phase 1) (P164044)


     20. The Phase 1 project will finance work outlined above in the Gambia, Guinea-Bissau, and Mali
         and leverage the constructions of a network of substations currently ongoing under the OMVG
         regional interconnection project and first phase of the OMVS regional interconnector project.
         The project aims to provide access to electricity to 300,000 households in three West African
         Countries benefiting almost three million people. With an estimated connection of over 100 000
         households in each country on average, the project would have a transformational impact in the
         region. The Gambia and Guinea Bissau are expected to reach an access rate of almost 100%,
         while Mali will double its electricity access rate. The expected completion time for the project is
         between 36 to 48 months. The total project amount is expected to be USD 372 million (This
         estimate will be updated by the feasibility studies). Two (2) components are currently under
         consideration on the project

     21. Component 1: The expansion and reinforcement of electricity distribution infrastructure and
         new connections in the Gambia, Guinea Bissau, and Mali. (Project IS Credit US$ 352 million).
         This component will include the extension and reinforcement of distribution networks in target
         localities with the construction of medium and low voltage lines as well as cross-border
         electrification. It also includes last mile connections with the financing for the supply of
         connection equipment, including smart meters for large consumers and prepaid meters for low
         voltage customers in each country.

     22. Component 2: Project Management and Technical Assistance to the joint coordination unit and
         national implementation units (Project IDA Credit US$ 20 million). This component will finance
         the creation of a joint project coordination unit and support national implementation teams as
         well as an owner’s engineer to oversee the works in each country. This component will a lso
         finance preparation of technical and Environmental and social studies for the remaining
         countries of the program. Finally, this component will finance studies to assess/determine
         suitable private sector management of the distribution in newly electrified localities or an effective
         O&M model for target countries.


 Overall Risk and Explanation

     23. The overall risk rating for the program and the operation is substantial. The major risks to the
         program include: (i) socio-political instability (ii) problems of good governance and weak capacity
         of the national electricity companies; and (iii) the sector strategy and policy (iv) the inherent
         complexity embedded in designing and implementing a set of regional projects.

     24. There is substantial political and governance risk to the overall program due to the fact that it will
         be implemented in a number of fragile and volatile environments. For the first phase of the
         program, the biggest risk in this regard is the security situation in Mali. Despite its efforts in the
         recent years, Mali remains a politically fragile country with low capacity and weak institutions. In
         large parts of t Northern Mali, the Government’s control is quite limited. Fighting between rebel
         factions and between rebels and the Malian army occurs regularly despite the presence of a
         United Nations peacekeeping mission. Substations from which the grid is expected to be
         expanded in Mali are located in Bamako, Manantali, Kita, Kayes in the West. However, the


Oct 19, 2017                                                                                          Page 9 of 17
         The World Bank
         ECOWAS - Regional Electricity Access Project (Phase 1) (P164044)


          security situation in the North could create spillover effects in project areas. In addition, following
          a period of optimism after the election of Ibrahim Boubacar Keita as president, several scandals
          have raised governance challenges. In Guinea Bissau, despite progress on the political
          transition and formation of an inclusive Government, concerns persist about possible
          deterioration of the political environment, including involvement of the military. The project team
          will work closely with the office on the ground to closely monitor the political situation, including
          possible scale-back if stability is threatened. In the Gambia, the inauguration of the new regime
          in January 2017 led by President Adama Barrow represents an opportunity for the people of The
          Gambia to consolidate democratic rule. While political and governance risks in The Gambia
          remain elevated, the new Government has made progress with the introduction of a fiscal
          stabilization program and reform measures to define institutional arrangements that enhance
          transparency and accountability in public sector procedures and promote private sector
          participation.

     25. Furthermore, while technical capacity in the countries targeted by the program is satisfactory,
         the national utilities that will be responsible for supervising works are overstretched given the
         immense challenges facing their respective electricity sectors, creating a moderate risk to the
         project. This is compounded by their poor financial condition, inconsistent governance, and
         ongoing fraud and corruption issues throughout the region. Bank-financed projects to improve
         governance and strengthen capacity are ongoing in each of the countries for the first phase of
         the program. In each phase, all countries will be required to leverage existing project
         implementation units/staff from other Bank projects in the sector thereby providing the option for
         close supervision and accountability.

     26. Changing sector strategies and policies in Mali and Senegal present a moderate risk for program
         and the first phase project in the case of Mali. In both countries, the delimitation of responsibilities
         between the rural electrification agency and the national power utility are not clearly defined.
         Several options are being considered to scale-up rural access but also to reform the national
         utilities, EDM and SENELEC, more broadly. In addition, adequate and timely decision-making
         in both Mali and Senegal is hampered by the fragmented and weak leadership in the sector. For
         each phase of the program, the Bank will therefore finance an assessment of possible O&M
         models to be agreed and implemented in the project areas.

     27. The complexity of the program given its regional and phased nature creates substantial risk. The
         first project will therefore emphasize the creation of a joint coordination unit to facilitate the
         implementation of the program and seek to build or reinforce national and regional capacities
         early.

     28. Combined, the risks discussed above also create risk for the preparation cycle itself, be it in the
         first phase or subsequent projects. Political instability and insecurity could impede key
         preparatory activities such as the delivery of pre-requisite studies and/or changes in leadership
         could lead to revised client objectives. With respect to the first phase, the team is closely
         monitoring the political situation in Mali and Guinea Bissau. In addition, the team is reaching out
         to clients to define a robust institutional setup supported by results frameworks that can be
         common to all countries in the program as well as regional entities.

Oct 19, 2017                                                                                           Page 10 of 17
         The World Bank
         ECOWAS - Regional Electricity Access Project (Phase 1) (P164044)




     29. Corporate requirements, including Gender, Citizen Engagement and GHG Accounting will be
         addressed during project preparation.

 Economic Analysis
 Briefly describe Project's development impact in terms of expected benefits and costs

     30. The project aims to provide electricity access to households, SMEs, and institutions that
         currently have no access or extremely limited access to affordable and reliable power sources.
         The project will benefit the populations and various economic sectors across target countries
         and especially those living in the direct project impact areas. In phase 1 of the program,
         beneficiaries are estimated at 3 million people as a result of project activities including network
         extension and last mile connections. These people are severely affected by unemployment and
         under-employment. Thus, the project will have a significant positive impact on the activities of
         the project affected inhabitants in general, and on those of women and young people, in
         particular in terms of new employment opportunities, increased business activities, improved
         access to socio-economic infrastructure, and reduced load-shedding times.

     31. Furthermore, the project is expected to have significant impact on the countries in terms of: (i)
         Increased productivity due improved access to reliable electricity supply, resulting in reduced
         costs of electricity services for industries, businesses and residential consumers; (ii) realized
         potential for cross-border electrification and stepping towards a dynamic energy market in the
         ECOWAS region; (iii) positive environmental externalities, in terms of the reduction of CO2
         emissions due to reliance on grid power rather than alternative diesel generation and or biomass.

     32. The development impact of transitioning to modern energy is unambiguous. There are many
         possible paths by which the use of electricity might benefit households and communities and
         analysis has focused on the estimation of the effects on outcome variables —income, total
         household expenditures, employment, or various dimensions of education, such as time spent
         at home studying or the school enrollment rate.

     33. The main project costs are financial investment costs (estimated to be $325m), as well as social
         and environmental impacts which are typical for distribution network and manageable.


  1. Rationale for public sector provision/financing, if applicable

     34. The investment component of the Project consists of construction of distribution network in urban
         and rural areas. Distribution network and rural electrification are generally difficult to finance
         privately due to their public good nature. In addition, the program (and especially Phase 1) target
         some of the poorest countries in the region, that would not be able to mobilize financing on
         affordable terms. Private sector financing at this early stage would also likely require individual
         national projects that would eliminate the benefits of the current regional approach (regional IDA
         mobilization and joint procurement process with economies of scale).



Oct 19, 2017                                                                                       Page 11 of 17
         The World Bank
         ECOWAS - Regional Electricity Access Project (Phase 1) (P164044)


     35. Public sector financing is therefore the most efficient and least costly financing available under
         the existing institutional framework. Nevertheless, the program creates opportunities for new
         private sector participation by targeting zones that are currently beyond the existing utility
         boundaries in some of the target countries.
  2. Value added of Bank's support

     36. The involvement of the Bank in the project will bring to fruition its efforts to support regional
         integration and cooperation to the last mile connection of households. Indeed, in the area of
         electricity, the Bank has been providing sustained financing over the last ten years to the
         implementation of the WAPP priority projects (CLSG, OMVS , OMVG ), for the implementation
         of feasibility studies and energy master plans / least cost prospectus at country level, and the
         definition of an institutional and regulatory environment that have culminated in the present
         project. Furthermore, the Bank has been providing financial support to the countries in the area
         of rural development. The Bank’s investment is also expected to catalyze additional investment
         in the sector that would otherwise not occur in such due to the standardization and coherence
         of the approach across countries.
  3. Brief description of methodology/scope and next steps

     37. The economic analysis for the project will follow a standard cost benefit framework. Comparing
         the present value of incurred costs to implement the project to the stream of attributable benefits
         it will generate, the EIRR and NPV of benefits will inform the project’s viability over its economic
         lifetime. The team will draw on the recently issued guidance for economic analysis in the energy
         sector to estimate the consumer surplus associated with moving from traditional to modern forms
         of energy. This analysis will be carried out as part of feasibility studies.

 Implementing Agency Assessment

     38. The project implementation arrangements will not support the establishment of new national or
         regional institutions, but rather focus on strengthening and networking with existing
         national/regional institutions to better support on-going or planned national/regional investment
         activities. Each project will also be prepared in close collaboration with national Governments
         and in coordination with other relevant regional entities (such as OMVG and OMVS in the case
         of the proposed Phase 1 project). The program and each project phase will be supported by the
         ECOWAS PPDU, the fiduciary capacities of which will be assessed in depth and confirmed by
         the Bank during appraisal. The role of PPDU in the project implementation will be to provide a
         convening platform for coordination among regional entities and national participants, to provide
         relevant technical assistance to country teams as deemed necessary, and support for
         procurement, monitoring, knowledge management, and communication as well as for all other
         cross-cutting activities leading to necessary regional alignment/harmonization.

     39. During each project phase, each country will be supported by a national project implementation
         unit (PIU). Experienced national entities will be selected during appraisal, such as existing Bank
         funded PIUs showing proven adequate fiduciary capacities, which will be re-assessed. National

Oct 19, 2017                                                                                       Page 12 of 17
         The World Bank
         ECOWAS - Regional Electricity Access Project (Phase 1) (P164044)


          PIUs will be then strengthened for the implementation of component 1. Each PIU is responsible
          for the (i) coordination and planning of the works, (ii) supervision and monitoring/control of the
          project activities, (iii) administrative and financial management and some (iv) procurement
          activities.

     40. Regional coordination for the program will be led by a joint project implementation unit (J-PIU).
         The J-PIU will be composed of the project coordinator of each national PIU, and led by the
         ECOWAS PPDU secretariat. The J-PIU will facilitate the joint procurement process for all
         activities under component 1 and the owner’s engineer under component 2. Once the relevant
         firms have been selected under these procurement processes, individual contracts will be signed
         between them and national PIUs for each country. National PIUs will then be responsible for the
         implementation and supervision of these activities, including all safeguards.

     41. In addition, the J-PIU will be responsible for the overall monitoring and evaluation functions of
         the Project and the implementation of activities under component 2 other than the owner’s
         engineer. J-PIU will provide general orientation on the project activities. Each project in the
         program will therefore combine assistance from the J-PIU (overall regional coordination and
         implementation of some regional activities) with support to countries (national coordination and
         implementation) to fully integrate national and regional priorities.

     42. For each phase, PPDU and recipient countries will sign separate financing agreements, with
         funds disbursed directly through existing institutional structures. Each country will establish a
         subsidiary agreement with their national utilities.

   Note to Task Teams: The following sections are system generated and can only be edited online in the Portal. Please
   delete this note when finalizing the document.



  SAFEGUARDS

  A. Project location and salient physical characteristics relevant to the safeguard analysis (if known)

  The proposed projects has a national coverage in each of the participating three countries, namely Mali, The Gambia and
 Guinea-Bissau. Most of the project’s proposed activities will be developed in the inner-cities and villages located close to
 the 225kV substations built under the OMVG and OMVS projects in Guinea Bissau, The Gambia and Mali. Thought few
 stations/sub-stations sites are known in the participating countries, overall, detailed physical locations of most project
 activities are not yet known, and will only be identified during project preparation / implementation.

  B. Borrower’s Institutional Capacity for Safeguard Policies

  The proposed regional project to be implemented in three different countries. Each country has an established
 regulatory framework, via its national environmental agency (NEA) that ensures the integration of environmental and
 social considerations at the project and program levels, but the borrower’s institutional capacity on social and
 environmental safeguards remains volatile as it varies from one country to another. Recent experience in dealing with

Oct 19, 2017                                                                                                     Page 13 of 17
         The World Bank
         ECOWAS - Regional Electricity Access Project (Phase 1) (P164044)


 similar sectoral operations revealed that in all three countries, the implementation of the existing legal/regulatory
 provisions faces challenges due to the lack of human resources, limited logistical capabilities to conduct field visits to
 ground-truth level of social risks and impacts. The project safeguards instruments will include adequate mitigation
 measures.
  In the Gambia, Implementation and monitoring of social and environmental safeguards risks and impacts still needs to be
 further strengthened. The National Environment Agency (NEA) is supported by focal points at the regional level to
 monitor the implementation of environmental and social safeguards measures.
  In Guinea Bissau, there are some opportunities such as a legal and regulatory framework, clear institutional anchoring
 with the Ministry of Sustainable Development and High Authority for Environmental Assessment (ACCE), public
 consultation procedures in ESIAs, NGOs authorized offices and firms. Just like in the neighboring countries, the ACCE is
 very weak in terms of safeguards handling and therefore would pretty much benefit highly from such technical support.


  C. Environmental and Social Safeguards Specialists on the Team

  Demba Balde, Social Safeguards Specialist
  Cheikh A. T. Sagna, Social Safeguards Specialist
  Medou Lo, Environmental Safeguards Specialist

  D. Policies that might apply

  Safeguard Policies                           Triggered?          Explanation (Optional)
                                                                   The project is classified B because the magnitude of
                                                                   the potential negative impacts and risks are expected
                                                                   to be low to moderate and can be easily mitigated.
                                                                   Since, aside from few stations/sub-stations, most of
                                                                   the targeted localities are not yet known, and will
                                                                   probably be known during project implementation.
                                                                   Most feasibilities studies are currently being
                                                                   prepared with likely outputs in March-April, 2018. To
                                                                   comply with the World bank safeguard policies and
                                                                   the national environmental regulation, the following
  Environmental Assessment OP/BP 4.01          Yes
                                                                   safeguards documents will be prepared by each
                                                                   Borrower: (i) an Environmental and Social Framework
                                                                   (ESMF), and (ii) a resettlement Policy Framework
                                                                   (RPF). The ESMFs and RPFs will be consulted upon and
                                                                   publicly disclosed both in-country and and at the Bank
                                                                   website before project appraisal. Likewise, the rest of
                                                                   the site specific instruments will be further prepared,
                                                                   amply consulted upon and publicly disclosed both in-
                                                                   country and the Bank site prior to the physical
                                                                   implementation of project sub-activities.
                                                                   The policy is not triggered as no project activities are
  Natural Habitats OP/BP 4.04                  No
                                                                   expected to impact natural habitats.




Oct 19, 2017                                                                                                    Page 14 of 17
         The World Bank
         ECOWAS - Regional Electricity Access Project (Phase 1) (P164044)


                                                                     The policy is not triggered as the project activities are
  Forests OP/BP 4.36                           TBD                   not expected to overlap or cause adverse impacts on
                                                                     forests or forestry activities
                                                                     The policy is not triggered as project involves no
  Pest Management OP 4.09                      No
                                                                     activity that would require usage of pesticides.
                                                                     The Project will not support any activities that would
                                                                     adversely impact any known physical cultural
                                                                     resources as defined in OP/BP 4.11. However, the
                                                                     policy is triggered due to potential impacts on
  Physical Cultural Resources OP/BP 4.11       Yes
                                                                     underground artifacts during civil works, the ESMF,
                                                                     ESIA and/or ESMPs will include provisions of “Chance
                                                                     Finds�? to ensure that these aspects will be taken into
                                                                     account in ESIAs to be developed under the ESMF.
                                                                     The policy is not triggered as there are no such
  Indigenous Peoples OP/BP 4.10                No                    Indigenous Peoples as defined by the policy in these
                                                                     participating countries.
                                                                     The policy is triggered because Component 1 provides
                                                                     for the extension and strengthening of electricity
                                                                     distribution infrastructure to allow for maximum new
                                                                     connections. The main social risks and impacts are the
                                                                     possible losses of livelihoods and income, employment
  Involuntary Resettlement OP/BP 4.12          Yes                   , crops, trees, physical buildings, land and loss of
                                                                     community and individual equipment. Each
                                                                     participating country will prepare for unknown sites, a
                                                                     Resettlement Policy Framework (RPF) that will be
                                                                     consulted upon and publicly disclosed prior to
                                                                     appraisal.
                                                                     The policy is not triggered as the project will not
  Safety of Dams OP/BP 4.37                    No                    finance dam works or activities associated to existing
                                                                     dam.
  Projects on International Waterways                                The policy is not triggered as there are no activities
                                               No
  OP/BP 7.50                                                         related to international waterways in the project.
                                                                     The Project is not located in a disputed area as defined
  Projects in Disputed Areas OP/BP 7.60        No
                                                                     by the policy, and thus the policy is not triggered.

  E. Safeguard Preparation Plan

  Tentative target date for preparing the Appraisal Stage PID/ISDS

  May 30, 2018

  Time frame for launching and completing the safeguard-related studies that may be needed. The specific studies and
  their timing should be specified in the Appraisal Stage PID/ISDS

  The project will have two studies before decision meeting: (i) an Environmental and Social management Framework
 (ESMF), and, (ii) a Resettlement Policy Framework (RPF). These studies are under procurement, and they are expected to


Oct 19, 2017                                                                                                      Page 15 of 17
         The World Bank
         ECOWAS - Regional Electricity Access Project (Phase 1) (P164044)


 be completed between January and March 2018. With the results of the feasibility studies, each known site will be
 properly screened and the required additional site-specific social and environmental studies prepared before the physical
 start of subproject implementation.


  CONTACT POINT


  World Bank
  Pedro E. Sanchez, Christopher Saunders
  Lead Energy Specialist


  Borrower/Client/Recipient
  Ministry of Finance and Economic Affairs of The Gambia
  H. Abdou Kolley
  Minister of Finance and Economic Affairs
  abdoukolley@hotmail.com


  Abdou Kolley Kolley
  Honorable
  abdoukolley@hotmail.com

  Ministry of Economy and Finance of Guinea Bissau
  João Alage Mamadu Fadia
  Minister of Economiy and Finances
  hhsantos1959@gmail.com

  Minister of Finance & Economic Development of Mali
  H. Momudu L Kargbo
  Minister of Finance & Economic Development
  mlkargbo@yahoo.com

  Implementing Agencies
  Energie du Mali (EDM SA)
  Coulibaly Dramane
  Managing Director
  drcoulibaly@edm-sa.com.ml

  National Water and Electricity Company (NAWEC)
  Baba S. FATAJO
  Managing Director


Oct 19, 2017                                                                                                  Page 16 of 17
         The World Bank
         ECOWAS - Regional Electricity Access Project (Phase 1) (P164044)


  bsfatajo@hotmail.com

  Electricidade e Agua da Guiné - Bissau (EAGB)
  Rene Barros
  Managing Director
  rbarros58@hotmail.com


  FOR MORE INFORMATION CONTACT
  The World Bank
  1818 H Street, NW
  Washington, D.C. 20433
  Telephone: (202) 473-1000
  Web: http://www.worldbank.org/projects



  APPROVAL

   Task Team Leader(s):                     Pedro E. Sanchez, Christopher Saunders

  Approved By
  APPROVALTBL
  Safeguards Advisor:                       Maman-Sani Issa                          16-Feb-2018

  Practice Manager/Manager:                 Mustafa Zakir Hussain                    01-Mar-2018

  Country Director:                         Indira Konjhodzic                        11-Mar-2018



   Note to Task Teams: End of system generated content, document is editable from here. Please delete this note when
   finalizing the document.




Oct 19, 2017                                                                                               Page 17 of 17