PROJECT NAME: Grant No. PROCUREMENT PLAN I.General 1. Project information: Project Name: Municipal Development Program ( MDP Phase II Cycle I) Country: West Bank and Gaza  Project Code: 2. Bank’s approval Date of the Procurement Plan, 3. Date of General Procurement Notice: 4.Period covered by this procurement plan: 2013-2014 II. Goods, Works and non-consulting services. 1. Procurement Methods and Thresholds Category Method of Threshold Prior Review Threshold Procurement (US$ Equivalent) (US$ Equivalent) Goods ICB > 500,000 First contract and each contract > 3 million NCB >100,000 and <= 500,000 None Shopping <= 100,000 None Direct Contracting No threshold All contracts Category Method of Threshold Prior Review Threshold Procurement (US$ Equivalent) (US$ Equivalent) works ICB > 2000,0000 First contract and each contract > 15 million NCB >200,000 and <= 2000,000 None Shopping <= 200,000 None Direct Contracting No threshold All contracts 2 . Pre-qualification. 3. Reference to Project Operational and Procurement Manual. 4. Any Other Special Procurement Arrangements: 5. Procurement Packages with Methods and Time Schedule – Attachments: for Works (Annex I), Goods (Annex II) and Services other than consultancy (Annex III) III.Selection of Consultants 1 Selection Methods and Thresholds Category Selection Method Threshold Prior Review Threshold (US$ Equivalent) (US$ Equivalent) Consulting QCBS No threshold All contracts > 1 million Services Firms QBS No threshold All contracts > 1 million CQS <=200,000 None LCS <=100,000 None SSS No threshold All Contracts Individuals IC No threshold All contracts above US$300,000 Sole Source No threshold All contracts 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $ 300,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3.Any Other Special Selection Arrangements: 4. Reference to Project Operational and Procurement Manual. 5. Consultancy Assignments with Selection Methods and Time Schedule Attachment ( Annex IV). Procurement Plan Country: WEST BANK AND GAZA Project: MDP Phase II Cycle I Category: Goods & Works Schedule Cost Cost Financier No. of Est. Est. Rev Component Proc. NO. Description Stat. Donor Prep. Of Bids Contract Reference Lots/ Method Prior/ WB no Issue of Evaluation WB no Contract Contract Comple. Bidding submission/ Amount ( Start Date Comments packages objection Doc. Report objection Award Sig. Date Docs Opening EURO) Post (USD $) (Euro) Support to Municipal Responsiveness and 2 565,800 410,000 Innovations 2.1 Piloting Innovations 565,800 410,000 2.1.2 Renewable Solar Energy 282,900 205,000 P 01-Oct-13 NA 08-Oct-13 07-Nov-13 21-Nov-13 NA 26-Nov-13 29-Nov-13 29-Nov-13 28-May-14 1 2.1.2.6 Implementing of Renewable Solar Energy Pilot Project 1 R 276000 200,000 NCB-Goods Post WB A P 01-Feb-15 NA 08-Feb-15 22-Feb-15 08-Mar-15 NA 15-Mar-15 18-Mar-15 18-Mar-15 17-May-15 Supply of Capacity Buildings & Results Dissemination Shopping - 2 2.1.2.7 1 R 6900 5,000 Goods Post WB Material A 3 Capacity Building 1,152,300 835,000 3.1 Capacity Building for Municipalities 1,007,400 730,000 3.1.1 Improved Financial Management 227,700 165,000 Integrated Financial Mangemement Information System 3.1.1.1 227,700 165,000 (IFMIS) P 01-Oct-13 NA 08-Oct-13 22-Oct-13 29-Oct-13 NA 03-Nov-13 06-Nov-13 06-Nov-13 05-Jan-14 Shopping- 3 3.1.1.1.3 Supply of IT Equipments (Hardware and Software) 1 R 89700 65,000 Post KFW Goods A P 01-Sep-13 NA 08-Sep-13 06-Oct-13 20-Oct-13 NA 23-Oct-13 27-Oct-13 27-Oct-13 26-Dec-13 4 3.1.1.1.4 Supply and Install IFMIS Software 1 R 138000 100,000 NCB-Goods Post KFW A 3.1.3 Citizen Service Center 779,700 565,000 3.1.3.1 Establishing Citizen Service Center 779,700 565,000 P 01-Oct-13 NA 08-Oct-13 05-Nov-13 19-Nov-13 NA 24-Nov-13 27-Nov-13 27-Nov-13 25-Feb-14 5 3.1.3.1.1 Supply of IT Equipments 1 R 303,600 220,000 NCB-Goods Post WB A P 01-Sep-13 NA 08-Sep-13 06-Oct-13 20-Oct-13 NA 24-Oct-13 27-Oct-13 27-Oct-13 25-Jan-14 6 3.1.3.1.2 Software Installation and Implementation 1 R 179,400 130,000 NCB-Goods Post KFW A P 01-Oct-13 NA 08-Oct-13 22-Oct-13 29-Oct-13 NA 03-Nov-13 06-Nov-13 06-Nov-13 04-Feb-14 Physical Work to Accommodate the Citizen Service Shopping- 7 3.1.3.1.3 R 110,400 80,000 Post SDC Center - A Works A P 01-Oct-13 NA 08-Oct-13 22-Oct-13 29-Oct-13 NA 03-Nov-13 06-Nov-13 06-Nov-13 04-Feb-14 Physical Work to Accommodate the Citizen Service Shopping- 8 3.1.3.1.4 R 151,800 110,000 Post KFW Center -B Works A P 01-Jun-14 NA 08-Jun-14 22-Jun-14 29-Jun-14 NA 03-Jul-14 03-Jul-14 03-Jul-14 17-Aug-14 Shopping- 9 3.1.3.1.5 Print Service Charter 1 R 34,500 25,000 Post MDTF Goods A 3.2 Capacity Building for MDLF as of Strategic Plan 144,900 105,000 3.2.2 E -MDLF 144,900 105,000 P 01-May-14 NA 08-May-14 05-Jun-14 19-Jun-14 NA 23-Jun-14 23-Jun-14 23-Jun-14 22-Aug-14 Installation of MDLF unified IP communication system NCB - this assignment include purchasing IP PPX switches, IP 10 3.2.2.1 2 R 124,200 90,000 Post AFD in WB and Gaza offices Goods telephony & faxes, network installation, etc. A P 01-May-14 NA 08-May-14 22-May-14 29-May-14 NA 02-Jun-14 02-Jun-14 02-Jun-14 01-Aug-14 Shopping- 11 3.2.2.2 Supply of electric equipment for e-MDLF 1 R 20,700 15,000 Post AFD Goods A Legend P Plan R Revised A Actual WB World Bank Procurement Plan Country: WEST BANK AND GAZA Project: MDP Phase II Cycle I Category: Consultancy Services Schedule Financier Rev Component Prior/ No. Description Stat. Select. Method Donor Technical Reference Financier Prep. of Financier Issue of RFP / Sub. of Open. of Fin. Invitation Neg./ Draft Contract Completion Prep. Of TOR Financier NO REOI ADV. Sub. of EOIs Short List Evaluation/ Financier NO Financier NO Contract Amount Start Date Comments NO RFP NO Invitations Proposals Proposals for Neg. Contract Signing Date Post Interview 2 Support to Municipal Responsiveness and Innovations 2.1 Piloting Innovations 2.1.2 Renewable Solar Energy P 1-Aug-13 8-Aug-13 11-Aug-13 25-Aug-13 1-Sep-13 NA NA NA NA NA 8-Sep-13 NA NA 13-Sep-13 18-Sep-13 NA 22-Sep-13 22-Sep-13 22-Sep-14 Technical Support & Capacity Building for Renewable Energy Pilot 1 2.1.2.1 R I.C Post WB Project / WB A P 1-Aug-13 8-Aug-13 11-Aug-13 25-Aug-13 1-Sep-13 NA NA NA NA NA 8-Sep-13 NA NA 13-Sep-13 18-Sep-13 NA 22-Sep-13 22-Sep-13 22-Sep-13 Technical Support & Capacity Building for Renewable Energy Pilot 2 2.1.2.2 R I.C Post WB Project / Gaza A P 1-Apr-14 8-Apr-14 11-Apr-14 25-Apr-14 2-May-14 NA NA NA NA NA 9-May-14 NA NA 14-May-14 19-May-14 NA 22-May-14 22-May-14 22-May-15 Monitoring & Evaluation for Renewable Energy Pilot Project / West 3 2.1.2.3 R I.C Post WB Bank A P 1-Apr-14 8-Apr-14 11-Apr-14 25-Apr-14 2-May-14 NA NA NA NA NA 9-May-14 NA NA 14-May-14 19-May-14 NA 22-May-14 22-May-14 22-May-15 4 2.1.2.4 Monitoring & Evaluation for Renewable Energy Pilot Project / Gaza R I.C Post WB A P 1-Feb-15 8-Feb-15 11-Feb-15 25-Feb-15 4-Mar-15 NA NA NA NA NA 11-Mar-15 NA NA 16-Mar-15 22-Mar-15 NA 25-Mar-15 25-Mar-15 23-Jul-15 5 2.1.2.5 Results Dissemination for Renewable Energy R I.C Post WB A 2.1.1 E -Governance P 1-Apr-13 8-Apr-13 11-Apr-13 25-Apr-13 2-May-13 NA NA NA NA NA 9-May-13 NA NA 14-May-13 19-May-13 NA 22-May-13 22-May-13 18-Nov-13 6 2.1.1.1 E -Governance advisor R I.C Post WB A 3 Capacity Building 3.1 Capacity Building for Municipalities ` 3.1.1 Improved Financial management 3.1.1.2 Fixed Assets Registration and Valuation (FARV) P 01-Sep-13 15-Sep-13 22-Sep-13 06-Oct-13 20-Oct-13 NA 24-Oct-13 NA 29-Oct-13 27-Nov-13 18-Dec-13 NA 25-Dec-13 02-Jan-14 09-Jan-14 NA 16-Jan-14 16-Jan-14 16-Apr-14 Support in Preparing Fixed Assets Registration and Valuation (FARV)- R 7 3.1.1.2.1 QCBS Post MDTF West Bank A 3.2 Capacity Building for MDLF as of Strategic Plan 3.2.1 Informative Researches P 1-May-13 8-May-13 12-May-13 26-May-13 2-Jun-13 NA NA NA NA NA 9-Jun-13 NA NA 14-Jun-13 19-Jun-13 NA 23-Jun-13 23-Jun-13 22-Aug-13 R 8 3.2.1.1 Institutionalizing Informative Research Functionality in MDLF I.C Post WB the outcome of this assignment will set the bases for further interventions A 4 Program Management 4.2 Technical Supervision and Assistance (LTCs) P 03-Mar-13 17-Mar-13 24-Mar-13 07-Apr-13 21-Apr-13 NA 28-Apr-13 NA 01-May-13 30-May-13 20-Jun-13 NA 27-Jun-13 04-Jul-13 11-Jul-13 NA 18-Jul-13 18-Jul-13 14-May-14 9 4.2.1 Local Technical Consultant / North West Bank R QCBS Post MDTF 02-May-13 16-May-13 23-May-13 06-Jun-13 20-Jun-13 NA 27-Jun-13 NA 30-Jun-13 29-Jul-13 19-Aug-13 NA 26-Aug-13 02-Sep-13 09-Sep-13 NA 16-Sep-13 16-Sep-13 13-Jul-14 A P 03-Mar-13 17-Mar-13 24-Mar-13 07-Apr-13 21-Apr-13 NA 28-Apr-13 NA 01-May-13 30-May-13 20-Jun-13 NA 27-Jun-13 04-Jul-13 11-Jul-13 NA 18-Jul-13 18-Jul-13 14-May-14 10 4.2.2 Local Technical Consultant / Middle West Bank R QCBS Post MDTF 02-May-13 16-May-13 23-May-13 06-Jun-13 20-Jun-13 NA 27-Jun-13 NA 30-Jun-13 29-Jul-13 19-Aug-13 NA 26-Aug-13 02-Sep-13 09-Sep-13 NA 16-Sep-13 16-Sep-13 13-Jul-14 A P 03-Mar-13 17-Mar-13 24-Mar-13 07-Apr-13 21-Apr-13 NA 28-Apr-13 NA 01-May-13 30-May-13 20-Jun-13 NA 27-Jun-13 04-Jul-13 11-Jul-13 NA 18-Jul-13 18-Jul-13 14-May-14 11 4.2.3 Local Technical Consultant / South West Bank R QCBS Post MDTF 02-May-13 16-May-13 23-May-13 06-Jun-13 20-Jun-13 NA 27-Jun-13 NA 30-Jun-13 29-Jul-13 19-Aug-13 NA 26-Aug-13 02-Sep-13 09-Sep-13 NA 16-Sep-13 16-Sep-13 13-Jul-14 A P 03-Mar-13 17-Mar-13 24-Mar-13 07-Apr-13 21-Apr-13 NA 28-Apr-13 NA 01-May-13 30-May-13 20-Jun-13 NA 27-Jun-13 04-Jul-13 11-Jul-13 NA 18-Jul-13 18-Jul-13 14-May-14 12 4.2.4 Local Technical Consultant / Gaza R QCBS Post MDTF 02-May-13 16-May-13 23-May-13 06-Jun-13 20-Jun-13 NA 27-Jun-13 NA 30-Jun-13 29-Jul-13 19-Aug-13 NA 26-Aug-13 02-Sep-13 09-Sep-13 NA 16-Sep-13 16-Sep-13 13-Jul-14 A 4.3 Monitoring and Evaluation P 01-Jul-14 15-Jul-14 22-Jul-14 05-Aug-14 19-Aug-14 NA 24-Aug-14 NA 27-Aug-14 25-Sep-14 16-Oct-14 NA 23-Oct-14 30-Oct-14 06-Nov-14 NA 13-Nov-14 13-Nov-14 11-Feb-15 Direct Beneficiaries, Clients and Citizens Satisfaction Assessment (End 13 4.3.1 R QCBS Post WB of Cycle 1) A R A WB Procurement Pl Country: WEST BANK AND GAZA Project: MDP Phase II Cycle I Category: Consultancy Services No. Component Reference Description Stat. 3 Capacity Building 3.1 Capacity Building for Municipalities 3.1.1 Improved Financial management Integrated Financial Management Information System 3.1.1.1 (IFMIS) P 14 3.1.1.1.1 Supporting Municipalities in Implementing IFMIS R A P Improve revenue management (awareness campaign and 15 3.1.1.1.2 R internal management procedures at the municipalities) A 3.1.4 Operation and Maintenance P 16 3.1.4.2 Coaching on the O&M manual-Gaza R A 4 Program Management 4.3 Monitoring and Evaluation P Technical Compliance Audit and Usability Assessment of MDPI-W1 17 4.3.2 R Subprojects (by End of Cycle 1) A P 18 4.3.3 Municipal Ranking Update (End of Cycle 1) R A R A WB Procurement Plan Cost Cost Financier Est. Est. Rev Select. Prior/ Donor Method Prep. Of TOR Financier NO Post (US $) (Euro) 186,300 135,000 186,300 135,000 103,500 75,000 103,500 75,000 01-Aug-13 15-Aug-13 75,900 55,000 QCBS Post KFW 01-Sep-13 15-Sep-13 27,600 20,000 CQS Post KFW 82,800 60,000 01-Aug-13 15-Aug-13 82,800 60,000 QCBS Post KFW 82,800 60,000 82,800 60,000 3-Jan-16 10-Jan-16 27,600 20,000 I.C Post KFW 1-Jul-14 8-Jul-14 55,200 40,000 QCBS Post KFW Revised Actual World Bank Financier Prep. of Financier Issue of RFP / Sub. of REOI ADV. Sub. of EOIs Short List NO RFP NO Invitations Proposals 22-Aug-13 05-Sep-13 19-Sep-13 NA 24-Sep-13 NA 29-Sep-13 28-Oct-13 22-Sep-13 06-Oct-13 20-Oct-13 NA 27-Oct-13 NA 30-Oct-13 13-Nov-13 22-Aug-13 05-Sep-13 19-Sep-13 NA 24-Sep-13 NA 29-Sep-13 28-Oct-13 14-Jan-16 28-Jan-16 6-Feb-16 NA NA NA NA NA 13-Jul-14 27-Jul-14 6-Aug-14 NA 10-Aug-14 NA 14-Aug-14 11-Sep-14 Schedule Technical Open. of Fin. Invitation Neg./ Draft Evaluation/ Financier NO Financier NO Contract Amount Proposals for Neg. Contract Interview ` 18-Nov-13 NA 25-Nov-13 02-Dec-13 09-Dec-13 NA 27-Nov-13 NA NA 04-Dec-13 11-Dec-13 NA ` 18-Nov-13 NA 25-Nov-13 02-Dec-13 09-Dec-13 NA ` 13-Feb-16 NA NA 20-Feb-16 23-Feb-16 NA 2-Oct-14 NA 9-Oct-14 16-Oct-14 20-Oct-14 NA Contract Completion Start Date Signing Date 16-Dec-13 16-Dec-13 16-Mar-14 18-Dec-13 18-Dec-13 15-Aug-14 16-Dec-13 16-Dec-13 16-Mar-14 27-Feb-16 27-Feb-16 12-May-16 23-Oct-14 23-Oct-14 06-Jan-15 Comments WB is currently working in pilot municipalities to finalize the TOR Procurement Pl Country: WEST BANK AND GAZA Project: MDP Phase II Cycle I Category: Consultancy Services No. Component Reference Description Stat. 3 Capacity Building 3.1 Capacity Building for Municipalities 3.1.1 Improved Financial management 3.1.1.2 Fixed Assets Registration and Valuation (FARV) P Support in Preparing Fixed Assets Registration and Valuation R 19 3.1.1.2.2 (FARV)-Gaza A Roll out of Financial Procedure Manual (FPM), budgets 3.1.1.3 preparation and external audit P Coaching Municipalities on applying FPM , on budget Preparation , R 20 3.1.1.3.1 on external audit A 3.1.2 Strategic Development and Investment Plans (SDIP) 3.1.2.1 Develop SDIP's for Municipalities P Strategic development and investments plans SDIPs -Support in SDIP 21 3.1.2.1.1 Implementation of phase 4&5-GAZA. Strategic development and investments plans SDIPs -Support in SDIP R 21 3.1.2.1.1 Implementation of phase 4&5-GAZA. A P Strategic development and investments plans SDIPs -support in R 22 3.1.2.1.2 Implementation of phase 1, 2&3 A 3.1.4 Operation and Maintenance P 23 3.1.4.1 Coaching on the O&M manual-West Bank R A R A WB Procurement Plan Cost Cost Financier Est. Est. Rev Select. Prior/ Donor Method Prep. Of TOR Financier NO Post (US $) (Euro) 496,800 360,000 496,800 360,000 110,400 80,000 110,400 80,000 01-Sep-13 15-Sep-13 110,400 80,000 QCBS Post GIZ 16,560 12,000 01-Aug-13 15-Aug-13 16,560 12,000 CQS Post GIZ 138,000 100,000 138,000 100,000 01-Jul-13 15-Jul-13 55,200 40,000 QCBS Post GIZ 55,200 40,000 QCBS Post GIZ 01-Jul-13 15-Jul-13 82,800 60,000 QCBS Post GIZ 248,400 180,000 01-Aug-13 15-Aug-13 248,400 180,000 QCBS Post GIZ Revised Actual World Bank Financier Prep. of Financier Issue of RFP / Sub. of REOI ADV. Sub. of EOIs Short List NO RFP NO Invitations Proposals 22-Sep-13 06-Oct-13 20-Oct-13 NA 24-Oct-13 NA 29-Oct-13 27-Nov-13 22-Aug-13 05-Sep-13 19-Sep-13 NA 26-Sep-13 NA 29-Sep-13 13-Oct-13 22-Jul-13 05-Aug-13 19-Aug-13 NA 25-Aug-13 NA 28-Aug-13 26-Sep-13 22-Jul-13 05-Aug-13 19-Aug-13 NA 25-Aug-13 NA 28-Aug-13 26-Sep-13 22-Aug-13 05-Sep-13 19-Sep-13 NA 24-Sep-13 NA 29-Sep-13 28-Oct-13 Schedule Technical Open. of Fin. Invitation Neg./ Draft Evaluation/ Financier NO Financier NO Contract Amount Proposals for Neg. Contract Interview ` 18-Dec-13 NA 25-Dec-13 01-Jan-14 08-Jan-14 NA 27-Oct-13 NA NA 03-Nov-13 10-Nov-13 NA 17-Oct-13 NA 24-Oct-13 31-Oct-13 07-Nov-13 NA 17-Oct-13 NA 24-Oct-13 31-Oct-13 07-Nov-13 NA ` 18-Nov-13 NA 25-Nov-13 02-Dec-13 09-Dec-13 NA Contract Completion Start Date Signing Date 15-Jan-14 15-Jan-14 15-Apr-14 17-Nov-13 17-Nov-13 15-Jul-14 14-Nov-13 14-Nov-13 12-Jul-14 14-Nov-13 14-Nov-13 12-Jul-14 16-Dec-13 16-Dec-13 16-Mar-14 Comments Procurement Pl Country: WEST BANK AND GAZA Project: MDP Phase II Cycle I Category: Consultancy Services No. Component Reference Description Stat. 3 Capacity Building to Municipalities & MDLF 3.2 Capacity Building for MDLF as of Strategic Plan 3.2.2 E - MDLF P R 24 3.2.2.3 Developing MDLF Web applications A P R 25 3.2.2.4 Upgrading MDLF IT Infrastructure A R A WB Procurement Plan Cost Cost Financier Est. Est. Rev Select. Prior/ Donor Method Prep. Of TOR Financier NO Post (US $) (Euro) 37,260 27,000 37,260 27,000 37,260 27,000 02-Jun-13 16-Jun-13 27,600 20,000 CQS Post AFD 2-Jun-13 9-Jun-13 9,660 7,000 I.C Post AFD Revised Actual World Bank Financier Prep. of Financier Issue of RFP / Sub. of REOI ADV. Sub. of EOIs Short List NO RFP NO Invitations Proposals 23-Jun-13 07-Jul-13 21-Jul-13 NA 28-Jul-13 NA 31-Jul-13 14-Aug-13 12-Jun-13 26-Jun-13 3-Jul-13 NA NA NA NA NA Schedule Technical Open. of Fin. Invitation Neg./ Draft Evaluation/ Financier NO Financier NO Contract Amount Proposals for Neg. Contract Interview 28-Aug-13 NA NA 04-Sep-13 11-Sep-13 NA 10-Jul-13 NA NA 17-Jul-13 21-Jul-13 NA Contract Completion Start Date Signing Date 18-Sep-13 18-Sep-13 16-May-14 24-Jul-13 24-Jul-13 22-Sep-13 Comments Procurement Pl Country: WEST BANK AND GAZA Project: MDP Phase II Cycle I Category: Consultancy Services No. Component Reference Description Stat. 3 Capacity Building 3.1 Capacity Building for Municipalities 3.1.2 Strategic Development and Investment Plans (SDIP) 3.1.2.1 Develop SDIP's for Municipalities P Strategic development and investments plans SDIPs -Support in SDIP R 26 3.1.2.1.3 Implementation of phase 4&5-West Bank A 3.1.3 Citizen Service Center R 3.1.3.1 Establishing Citizen Service Center P 27 3.1.3.1.6 Institutional Assessment and Business Process Management R A 3.1.5 Citizenship, Communication and outreach guidance P 28 3.1.5.1 Develop Citizenship ,Communication and Outreach guidance 28 3.1.5.1 Develop Citizenship ,Communication and Outreach guidance R A R A WB Procurement Plan Cost Cost Financier Est. Est. Rev Select. Prior/ Donor Method Prep. Of TOR Financier NO Post (US $) (Euro) 331,200 240,000 331,200 240,000 234,600 170,000 234,600 170,000 01-Jul-13 15-Jul-13 234,600 170,000 QCBS Post SDC 55200 40,000 55,200 40,000 1-Aug-13 8-Aug-13 55,200 40,000 I.C Post SDC 41,400 30,000 01-Sep-13 15-Sep-13 41,400 30,000 CQS Post SDC 41,400 30,000 CQS Post SDC Revised Actual World Bank Financier Prep. of Financier Issue of RFP / Sub. of REOI ADV. Sub. of EOIs Short List NO RFP NO Invitations Proposals 22-Jul-13 05-Aug-13 19-Aug-13 NA 25-Aug-13 NA 28-Aug-13 26-Sep-13 11-Aug-13 25-Aug-13 1-Sep-13 NA NA NA NA NA 22-Sep-13 06-Oct-13 20-Oct-13 NA 27-Oct-13 NA 30-Oct-13 13-Nov-13 Schedule Technical Open. of Fin. Invitation Neg./ Draft Evaluation/ Financier NO Financier NO Contract Amount Proposals for Neg. Contract Interview ` 17-Oct-13 NA 24-Oct-13 31-Oct-13 07-Nov-13 NA 8-Sep-13 NA NA 15-Sep-13 18-Sep-13 NA 27-Nov-13 NA NA 04-Dec-13 11-Dec-13 NA Contract Completion Start Date Signing Date 14-Nov-13 14-Nov-13 12-Jul-14 21-Sep-13 21-Sep-13 20-Nov-13 18-Dec-13 18-Dec-13 15-Aug-14 Comments