Public Disclosure Copy The World Bank Implementation Status & Results Report Rural Alliances Project II (P127743) Rural Alliances Project II (P127743) LATIN AMERICA AND CARIBBEAN | Bolivia | Agriculture and Rural Development Global Practice | IBRD/IDA | Specific Investment Loan | FY 2013 | Seq No: 5 | ARCHIVED on 26-Apr-2015 | ISR18857 | Implementing Agencies: EMPODERAR Key Dates Key Project Dates Board Approval date:23-Oct-2012 Effectiveness Date:09-May-2013 Planned Mid Term Review Date:04-May-2015 Actual Mid-Term Review Date:-- Original Closing Date:30-Nov-2017 Revised Closing Date:30-Nov-2017 Project Development Objectives Project Development Objective (from Project Appraisal Document) The objective of the Project is to improve accessibility to markets for small rural producers in the Selected Areas by: (a) promoting productive alliances between different small rural producer organizations and purchasers; (b) empowering rural producers through the establishment and strengthening of self-managed grass-root organizations; (c) increasing access to productive assets, technologyand financial services; (d) promoting more effective, responsive and accountable service organizations at the local level; and (e)enhancing environmental sustainability of productive practices. The Project is a follow on operation to the successful PAR I, whichtested the model for improving market access. Has the Project Development Objective been changed since Board Approval of the Project Objective? No PHRPDODEL Components Name Institutional Strengthening:(Cost $3.79 M) Implementation of Rural Alliances:(Cost $52.05 M) Project Management, Monitoring and Evaluation:(Cost $8.70 M) Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO  Satisfactory  Satisfactory Overall Implementation Progress (IP)  Satisfactory  Satisfactory Overall Risk Rating  --  Moderate 4/26/2015 Page 1 of 9 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Rural Alliances Project II (P127743) Implementation Status and Key Decisions The last mission took place on September 2014. The ISR #4 was filed in October 2014 and this ISR is being only partially updated to avoid a stale status after six month from archiving sequence 5. The next supervision mission, which will be a mid term review, will take place from May 4 to 14 2015, and after the MTR a full ISR will be submitted. Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance  --  --  Moderate Macroeconomic  --  --  Low Sector Strategies and Policies  --  --  Moderate Technical Design of Project or Program  --  --  Low Institutional Capacity for Implementation and Sustainability  --  --  Moderate Fiduciary  --  --  Moderate Environment and Social  --  --  Moderate Stakeholders  --  --  Low Other  --  --  -- Overall  --  --  Moderate Results Project Development Objective Indicators PHINDPDOTBL  Increase in the average volume of sales of the product(s) involved in the alliances (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 50.00 Date 15-Jan-2013 22-Sep-2014 22-Sep-2014 18-Aug-2017 4/26/2015 Page 2 of 9 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Rural Alliances Project II (P127743) PHINDPDOTBL  Producer organizations that register income and costs, and are accountable to their members (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 80.00 Date 15-Jan-2013 22-Sep-2014 22-Sep-2014 18-Aug-2017 PHINDPDOTBL  Producer organizations that maintain or improve their commercial relations (alliances) for at least two productive cycles (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 70.00 Date 15-Jan-2013 22-Sep-2014 22-Sep-2014 18-Aug-2017 Overall Comments Intermediate Results Indicators PHINDIRITBL  1.1 Producer organizations that receive assistance to be formalized (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 60.00 60.00 300.00 Date 15-Jan-2013 22-Sep-2014 22-Sep-2014 31-Aug-2016 4/26/2015 Page 3 of 9 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Rural Alliances Project II (P127743) PHINDIRITBL  1.2 Alliances with signed financing agreement for integral support (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 31.00 31.00 645.00 Date 15-Jan-2013 22-Sep-2014 22-Sep-2014 31-Aug-2016 PHINDIRITBL  1.3 Alliances with signed financing agreement for technical assistance (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 100.00 Date 15-Jan-2013 22-Sep-2014 22-Sep-2014 31-Aug-2016 PHINDIRITBL  1.4 Public investment subprojects with signed financing agreement (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 26.00 Date 15-Jan-2013 22-Sep-2014 22-Sep-2014 31-Aug-2016 PHINDIRITBL  1.5 Organizations’ members that receive managerial training (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 124.00 124.00 4305.00 Date 15-Jan-2013 22-Sep-2014 22-Sep-2014 30-Jun-2017 4/26/2015 Page 4 of 9 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Rural Alliances Project II (P127743) PHINDIRITBL  1.5.1 Women that receive managerial training (Percentage, Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 30.00 Date 15-Jan-2013 22-Sep-2014 22-Sep-2014 30-Jun-2017 PHINDIRITBL  2.1 Supported alliances that fulfill their commercial aims in the framework of agreed arrangements (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 85.00 Date 15-Jan-2013 22-Sep-2014 22-Sep-2014 18-Aug-2017 PHINDIRITBL  2.2 Households in alliances that receive financing support (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 858.00 858.00 25000.00 Date 15-Jan-2013 22-Sep-2014 22-Sep-2014 18-Aug-2017 PHINDIRITBL  SPO households represented by women that receive financing support (Percentage, Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 30.00 Date 15-Jan-2013 22-Sep-2014 22-Sep-2014 18-Aug-2017 4/26/2015 Page 5 of 9 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Rural Alliances Project II (P127743) PHINDIRITBL  2.3 Producer organizations that obtain positive net incremental real income from alliance product(s) (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 80.00 Date 15-Jan-2013 22-Sep-2014 22-Sep-2014 18-Aug-2017 PHINDIRITBL  2.4 Producer organizations whose leaders are periodically accountable to their members (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 80.00 Date 15-Jan-2013 21-Feb-2014 21-Feb-2014 18-Aug-2017 PHINDIRITBL  2.5 Executed public investment subprojects (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 26.00 Date 15-Jan-2013 21-Feb-2014 21-Feb-2014 18-Aug-2017 PHINDIRITBL  2.6 Households that benefit from public investment subprojects (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 10100.00 Date 15-Jan-2013 22-Sep-2014 22-Sep-2014 18-Aug-2017 4/26/2015 Page 6 of 9 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Rural Alliances Project II (P127743) PHINDIRITBL  2.7 Alliances that apply environmental measures satisfactorily (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 80.00 Date 15-Jan-2013 22-Sep-2014 22-Sep-2014 18-Aug-2017 PHINDIRITBL  3.1 Level of financial execution of the Project's Annual Operational Plan (POA) (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 42.00 42.00 80.00 Date 15-Jan-2013 22-Sep-2014 22-Sep-2014 18-Aug-2017 PHINDIRITBL  3.2 Producer Organization Subprojects without delays in the verification of expenses (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 90.00 90.00 85.00 Date 15-Jan-2013 22-Sep-2014 22-Sep-2014 30-Jun-2017 PHINDIRITBL  3.3 Project's Public Information System installed and operating (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target Value -- No No yes Date 15-Jan-2013 22-Sep-2014 22-Sep-2014 15-Mar-2017 Overall Comments Data on Financial Performance 4/26/2015 Page 7 of 9 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Rural Alliances Project II (P127743) Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed Disbursed P127743 IDA-51700 Effective XDR 32.90 32.90 0.00 7.12 25.78 22% Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P127743 IDA-51700 Effective 23-Oct-2012 12-Dec-2012 09-May-2013 30-Nov-2017 30-Nov-2017 Cumulative Disbursements Restructuring History There has been no restructuring to date. Related Project(s) There are no related projects. 4/26/2015 Page 8 of 9 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Rural Alliances Project II (P127743) 4/26/2015 Page 9 of 9 Public Disclosure Copy