The World Bank                                                                                                                                             Report No: ISR12992


                                                                                                   Implementation Status & Results
                                                                                                          China
                                                                                Shanxi Coal Bed Methane Development and Utilization (P100968)
Public Disclosure Copy




                         Operation Name: Shanxi Coal Bed Methane Development and Utilization                Project Stage:   Implementation         Seq.No: 7      Status: ARCHIVED    Archive Date:    18-Dec-2013
                                          (P100968)
                                                                              Country: China                                         Approval FY:        2009
                         Product Line: IBRD/IDA                               Region: EAST ASIA AND PACIFIC                          Lending Instrument: Specific Investment Loan
                         Implementing Agency(ies):

                         Key Dates
                         Board Approval Date      19-May-2009         Original Closing Date 31-Dec-2014            Planned Mid Term Review Date 26-Nov-2012                Last Archived ISR Date 24-Jun-2013
                         Effectiveness Date       18-Sep-2009         Revised Closing Date 31-Dec-2014             Actual Mid Term Review Date       26-Nov-2012

                         Project Development Objectives
                         Project Development Objective (from Project Appraisal Document)

                         The development objective of the project is to increase the production and utilization of CBM/CMM to replace coal as a fuel for thermal use and to reduce GHGs and local
                         air pollutants associated with coal combustion. The project development objective will be achieved by (a) enhancing the subsector➢❨ s policy framework and
                         institutional capacity, and (b) supporting the exploration, production and liquefaction of CBM to increase market access.
                         Has the Project Development Objective been changed since Board Approval of the Project?

                            Yes           No

                         Component(s)
                         Component Name                                                                                                          Component Cost
                         CBM and LNG Development                                                                                                          178.60
                         Institutional Strengthening and Capacity Building                                                                                  1.70

                         Overall Ratings
Public Disclosure Copy




                                                                  Previous Rating                       Current Rating
                         Progress towards achievement of PDO      Moderately Satisfactory               Moderately Satisfactory
                         Overall Implementation Progress (IP)     Moderately Satisfactory               Moderately Satisfactory
                         Overall Risk Rating                                                            Substantial

                         Implementation Status Overview
                         Progress has been continuous made in the project implementation since the April 2013 mission: (i) the operation of the first LCBM train has been started; (ii) the procurement of the
                         2nd LCBM train is ongoing but delayed - the contract with a project management company is signed to facilitate the project company to procure the EPC package of the 2nd train,
                         and the revised bidding document is to be submitted for the Bank review in December 2013; (iii) the construction of 20 testing wells has been completed, and the 2nd batch of a total
                         150 wells has been initiated.


                                                                                                                                                                                                          Page 1 of 4
                             The World Bank                                                                                                                                      Report No: ISR12992




                         The project restructuring to extend the closing date by 1.5 years, from December 31, 2014 to June 30, 2016 has been approved by the Bank though the counter-signing is ongoing.
                         The PDO is likely to be met.
Public Disclosure Copy




                         Locations
                         Country                                             First Administrative Division                    Location                               Planned                  Actual
                         China                                               Shanxi Sheng                                     Jincheng Shi


                         Results
                         Project Development Objective Indicators
                         Indicator Name                                 Core Unit of Measure                       Baseline                   Current                            End Target
                         Total amount of CBM/CMM produced and                  Cubic Meter(m3)          Value      300000000.00               6900000000.00                      2000000000.00
                         captured in Shanxi annually                                                    Date       31-Dec-2008                31-Dec-2012                        31-Dec-2014
                                                                                                        Comments                              source: Shanxi DRC
                                                                                                                                              CBM: 2.5 bm3
                                                                                                                                              CMM: 4.4 bm3
                         Total amount of CBM/CMM utilized in Shanxi            Cubic Meter(m3)          Value      200000000.00               3400000000.00                      1500000000.00
                         annually                                                                       Date       31-Dec-2008                31-Dec-2012                        31-Dec-2014
                                                                                                        Comments                              source: Shanxi DRC
                                                                                                                                              CBM: 2.0 bm3
                                                                                                                                              CMM: 1.4 bm3

                         Intermediate Results Indicators
                         Indicator Name                                 Core Unit of Measure                       Baseline                   Current                            End Target
                         The volume of CBM produced annually                   Cubic Meter(m3)          Value      0.00                       0.00                               250000000.00
                                                                                                        Date       31-Dec-2008                31-Dec-2011                        31-Dec-2014
                                                                                                        Comments                              The construction of the CBM
Public Disclosure Copy




                                                                                                                                              drilling component is not
                                                                                                                                              started yet.
                         The volumn of LNG produced annually                   Metric ton               Value      0.00                       0.00                               200000.00
                                                                                                        Date       31-Dec-2008                31-Dec-2011                        31-Dec-2014
                                                                                                        Comments                              The first LNG train is still
                                                                                                                                              under construction. It is
                                                                                                                                              expected that its operation will
                                                                                                                                              be started in October 2012.




                                                                                                                                                                                                       Page 2 of 4
                             The World Bank                                                                                                                              Report No: ISR12992



                         The number of staff-week trained for both                   Number            Value      0.00                  440.00                           300.00
                         SECBMIH and Shanxi Province                                                   Date       31-Dec-2008           31-Dec-2011                      31-Dec-2014
                                                                                                       Comments                         staff-weeks
Public Disclosure Copy




                         The studies completed and reports produced                  Number            Value                            0.00
                                                                                                       Date                             31-Dec-2012                      31-Dec-2014
                                                                                                       Comments                         Studies were initiated but not
                                                                                                                                        completed.
                         New policy incentives and rules formulated and              Number            Value                            0.00
                         implemented                                                                   Date                             31-Dec-2011                      31-Dec-2014
                                                                                                       Comments
                         CBM/CMM data and information inventory                      Yes/No            Value                            No
                         system developed                                                              Date                             31-Dec-2011                      31-Dec-2014
                                                                                                       Comments
                         SECBMIH's Financial Sustainability - DSC                    Number            Value                                                             1.40
                         Ratio                                                                         Date                             31-Dec-2011                      31-Dec-2014
                                                                                                       Comments                         not available yet. This is
                                                                                                                                        required to be calculated on
                                                                                                                                        annual basis, and included in
                                                                                                                                        the progress report.
                         SECBMIH's Financial Sustainability - Rate of                Percentage        Value                                                             9.00
                         Return on equity                                                              Date                             31-Dec-2012                      31-Dec-2014
                                                                                                       Comments                         not available yet. This is
                                                                                                                                        required to be calculated on
                                                                                                                                        annual basis, and included in
                                                                                                                                        the progress report.
                         SECBMIH's Financial Sustainability - Ratio of               Number            Value                                                             1.10
                         current assets to current liabilities                                         Date                             31-Dec-2012                      31-Dec-2014
                                                                                                       Comments                         not available yet. This is
Public Disclosure Copy




                                                                                                                                        required to be calculated on
                                                                                                                                        annual basis, and included in
                                                                                                                                        the progress report.


                         Data on Financial Performance (as of 03-Sep-2013)
                         Financial Agreement(s) Key Dates
                         Project              Ln/Cr/Tf                   Status               Approval Date        Signing Date   Effectiveness Date      Original Closing Date   Revised Closing Date
                         P100968              IBRD-77050                 Effective            19-May-2009          02-Jul-2009    18-Sep-2009             31-Dec-2014             31-Dec-2014




                                                                                                                                                                                           Page 3 of 4
                             The World Bank                                                                                                                                     Report No: ISR12992


                         Disbursements (in Millions)
                         Project               Ln/Cr/Tf              Status              Currency   Original           Revised           Cancelled          Disbursed            Undisbursed      % Disbursed
                         P100968               IBRD-77050            Effective           USD                   80.00             80.00               0.00               22.68             57.32         28.00
Public Disclosure Copy




                         Disbursement Graph




                         Key Decisions Regarding Implementation
                         The next supervision is scheduled in the week of December 16, 2013.

                         Restructuring History
                         CD Decision on 18-Nov-2013
Public Disclosure Copy




                         Related Projects
                         There are no related projects.