The World Bank Report No: ISR12992 Implementation Status & Results China Shanxi Coal Bed Methane Development and Utilization (P100968) Public Disclosure Copy Operation Name: Shanxi Coal Bed Methane Development and Utilization Project Stage: Implementation Seq.No: 7 Status: ARCHIVED Archive Date: 18-Dec-2013 (P100968) Country: China Approval FY: 2009 Product Line: IBRD/IDA Region: EAST ASIA AND PACIFIC Lending Instrument: Specific Investment Loan Implementing Agency(ies): Key Dates Board Approval Date 19-May-2009 Original Closing Date 31-Dec-2014 Planned Mid Term Review Date 26-Nov-2012 Last Archived ISR Date 24-Jun-2013 Effectiveness Date 18-Sep-2009 Revised Closing Date 31-Dec-2014 Actual Mid Term Review Date 26-Nov-2012 Project Development Objectives Project Development Objective (from Project Appraisal Document) The development objective of the project is to increase the production and utilization of CBM/CMM to replace coal as a fuel for thermal use and to reduce GHGs and local air pollutants associated with coal combustion. The project development objective will be achieved by (a) enhancing the subsector➢❨ s policy framework and institutional capacity, and (b) supporting the exploration, production and liquefaction of CBM to increase market access. Has the Project Development Objective been changed since Board Approval of the Project? Yes No Component(s) Component Name Component Cost CBM and LNG Development 178.60 Institutional Strengthening and Capacity Building 1.70 Overall Ratings Public Disclosure Copy Previous Rating Current Rating Progress towards achievement of PDO Moderately Satisfactory Moderately Satisfactory Overall Implementation Progress (IP) Moderately Satisfactory Moderately Satisfactory Overall Risk Rating Substantial Implementation Status Overview Progress has been continuous made in the project implementation since the April 2013 mission: (i) the operation of the first LCBM train has been started; (ii) the procurement of the 2nd LCBM train is ongoing but delayed - the contract with a project management company is signed to facilitate the project company to procure the EPC package of the 2nd train, and the revised bidding document is to be submitted for the Bank review in December 2013; (iii) the construction of 20 testing wells has been completed, and the 2nd batch of a total 150 wells has been initiated. Page 1 of 4 The World Bank Report No: ISR12992 The project restructuring to extend the closing date by 1.5 years, from December 31, 2014 to June 30, 2016 has been approved by the Bank though the counter-signing is ongoing. The PDO is likely to be met. Public Disclosure Copy Locations Country First Administrative Division Location Planned Actual China Shanxi Sheng Jincheng Shi Results Project Development Objective Indicators Indicator Name Core Unit of Measure Baseline Current End Target Total amount of CBM/CMM produced and Cubic Meter(m3) Value 300000000.00 6900000000.00 2000000000.00 captured in Shanxi annually Date 31-Dec-2008 31-Dec-2012 31-Dec-2014 Comments source: Shanxi DRC CBM: 2.5 bm3 CMM: 4.4 bm3 Total amount of CBM/CMM utilized in Shanxi Cubic Meter(m3) Value 200000000.00 3400000000.00 1500000000.00 annually Date 31-Dec-2008 31-Dec-2012 31-Dec-2014 Comments source: Shanxi DRC CBM: 2.0 bm3 CMM: 1.4 bm3 Intermediate Results Indicators Indicator Name Core Unit of Measure Baseline Current End Target The volume of CBM produced annually Cubic Meter(m3) Value 0.00 0.00 250000000.00 Date 31-Dec-2008 31-Dec-2011 31-Dec-2014 Comments The construction of the CBM Public Disclosure Copy drilling component is not started yet. The volumn of LNG produced annually Metric ton Value 0.00 0.00 200000.00 Date 31-Dec-2008 31-Dec-2011 31-Dec-2014 Comments The first LNG train is still under construction. It is expected that its operation will be started in October 2012. Page 2 of 4 The World Bank Report No: ISR12992 The number of staff-week trained for both Number Value 0.00 440.00 300.00 SECBMIH and Shanxi Province Date 31-Dec-2008 31-Dec-2011 31-Dec-2014 Comments staff-weeks Public Disclosure Copy The studies completed and reports produced Number Value 0.00 Date 31-Dec-2012 31-Dec-2014 Comments Studies were initiated but not completed. New policy incentives and rules formulated and Number Value 0.00 implemented Date 31-Dec-2011 31-Dec-2014 Comments CBM/CMM data and information inventory Yes/No Value No system developed Date 31-Dec-2011 31-Dec-2014 Comments SECBMIH's Financial Sustainability - DSC Number Value 1.40 Ratio Date 31-Dec-2011 31-Dec-2014 Comments not available yet. This is required to be calculated on annual basis, and included in the progress report. SECBMIH's Financial Sustainability - Rate of Percentage Value 9.00 Return on equity Date 31-Dec-2012 31-Dec-2014 Comments not available yet. This is required to be calculated on annual basis, and included in the progress report. SECBMIH's Financial Sustainability - Ratio of Number Value 1.10 current assets to current liabilities Date 31-Dec-2012 31-Dec-2014 Comments not available yet. This is Public Disclosure Copy required to be calculated on annual basis, and included in the progress report. Data on Financial Performance (as of 03-Sep-2013) Financial Agreement(s) Key Dates Project Ln/Cr/Tf Status Approval Date Signing Date Effectiveness Date Original Closing Date Revised Closing Date P100968 IBRD-77050 Effective 19-May-2009 02-Jul-2009 18-Sep-2009 31-Dec-2014 31-Dec-2014 Page 3 of 4 The World Bank Report No: ISR12992 Disbursements (in Millions) Project Ln/Cr/Tf Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P100968 IBRD-77050 Effective USD 80.00 80.00 0.00 22.68 57.32 28.00 Public Disclosure Copy Disbursement Graph Key Decisions Regarding Implementation The next supervision is scheduled in the week of December 16, 2013. Restructuring History CD Decision on 18-Nov-2013 Public Disclosure Copy Related Projects There are no related projects. Page 4 of 4