Public Disclosure Copy

        The World Bank                                             Implementation Status & Results Report
        ROAD REHABILITATION AND MAINTENANCE PROJECT PHASE II (P106596)


ROAD REHABILITATION AND MAINTENANCE PROJECT PHASE II (P106596)

AFRICA | Zambia | Transport & ICT Global Practice |
IBRD/IDA | Adaptable Program Loan | FY 2010 | Seq No: 12 | ARCHIVED on 22-Oct-2015 | ISR21113 |


Implementing Agencies:




Key Dates

  Key Project Dates

  Board Approval date:16-Oct-2009                                             Effectiveness Date:30-Mar-2010
  Planned Mid Term Review Date:30-Sep-2013                                    Actual Mid-Term Review Date:29-Nov-2013
  Original Closing Date:30-Jun-2014                                           Revised Closing Date:30-Apr-2016




Project Development Objectives

 Project Development Objective (from Project Appraisal Document)
 The overarching goal of the Road Rehabilitation and Maintenance Project (RRMP) is to stimulate economic growth and contribute to poverty
 reduction through appropriate investment in road infrastructure, adequate policy and institutional reforms, and enhanced road sector management.
 The specific objective of RRMP Phase II is to preserve road assets in target transport corridor and improve transport safety and connectivity in
 target areas.


 Has the Project Development Objective been changed since Board Approval of the Project Objective?
 No

 PHRPDODEL



Components

Name
Component 1: Civil works for road improvement:(Cost $62.43 M)
Component 2: Engineering and technical services:(Cost $6.20 M)
Component 3: Institutional development and capacity building:(Cost $1.66 M)
Component 4: Road safety:(Cost $2.90 M)
Component 5: Mobility improvement:(Cost $1.81 M)



Overall Ratings
Name                                                                      Previous Rating                         Current Rating

Progress towards achievement of PDO                                        Satisfactory                           Satisfactory



10/22/2015                                                                                                                            Page 1 of 9
                                                         Public Disclosure Copy
                                                          Public Disclosure Copy

         The World Bank                                             Implementation Status & Results Report
         ROAD REHABILITATION AND MAINTENANCE PROJECT PHASE II (P106596)


Overall Implementation Progress (IP)                                        Moderately Satisfactory                 Moderately Satisfactory
Overall Risk Rating                                                         Moderate                                Moderate


Implementation Status and Key Decisions

 Implementation rate is overall on track and there are no outstanding decisions. Rehabilitation of Lusaka - Kafue Road had been completed and
 Mufuchani Bridge construction was advancing well, with the main structural elements (foundations, piers, and deck) in place. All the available funds
 under the US$ 75 million credit had either been disbursed or committed. The period between now and the credit closing date (April 30, 2016) is
 considered sufficient to complete the most of the outstanding activities. The two notable subcomponents under Capacity Building that continue to
 experience delays are the Accident Information System under RTSA, and review of the Transport sector policy under the Ministry of Transport.




Risks

 Systematic Operations Risk-rating Tool

 Risk Category                                              Rating at Approval              Previous Rating              Current Rating

 Political and Governance                                    --                             Moderate                    Moderate
 Macroeconomic                                               --                             Moderate                    Moderate
 Sector Strategies and Policies                              --                             Moderate                    Moderate
 Technical Design of Project or Program                      --                             Low                         Low
 Institutional Capacity for Implementation and
 Sustainability
                                                             --                             Moderate                    Moderate
 Fiduciary                                                   --                             Low                         Low
 Environment and Social                                      --                             Low                         Low
 Stakeholders                                                --                             Low                         Low
 Other                                                       --                             --                          --

10/22/2015                                                                                                                               Page 2 of 9
                                                          Public Disclosure Copy
                                                              Public Disclosure Copy

               The World Bank                                             Implementation Status & Results Report
               ROAD REHABILITATION AND MAINTENANCE PROJECT PHASE II (P106596)


 Overall                                                         --                               Moderate                Moderate


Results

 Project Development Objective Indicators
 PHINDPDOTBL




          Roads in good and fair condition as a share of total classified roads (Percentage, Core)


                                               Baseline                       Actual (Previous)         Actual (Current)        End Target

         Value                                 50.00                          90.00                     65.00                   80.00

         Date                                  30-Oct-2009                    13-Mar-2015               24-Jul-2015             30-Apr-2016


         Comments
         The indicator had previously been based on the condition of Lusaka- Chirundu Road. This has been corrected. Based on RDA's
         2013 road condition survey, out of the 29,088 km of Trunk, Main, District, Urban and Primary Feeder roads assessed, 18,939 km or
         65% of the surveyed length, were in Good and Fair condition. This proportion is adopted as a reasonable indicators of the
         condition of the entire road network of 67,631 km. The indicator will be updated after RDA’s 2014 condition survey, but it is
         unlikely to reach the 80% target. It is to be noted that the project did not directly support the improvement of the road network
         condition.



 PHINDPDOTBL




          Size of the total classified network (Kilometers, Core Supplement)



                                               Baseline                       Actual (Previous)         Actual (Current)        End Target

         Value                                 67000.00                       67671.00                  67671.00                67631.00




 PHINDPDOTBL




          Share of rural population with access to an all-season road (Percentage, Core)


                                               Baseline                       Actual (Previous)         Actual (Current)        End Target

         Value                                 --                             50.00                     50.00                   60.00

         Date                                  --                             13-Mar-2015               24-Jul-2015             30-Apr-2016


         Comments
         The 50% target will be achieved after completion of ongoing works in Kalabo District




10/22/2015                                                                                                                              Page 3 of 9
                                                              Public Disclosure Copy
                                                              Public Disclosure Copy

               The World Bank                                             Implementation Status & Results Report
               ROAD REHABILITATION AND MAINTENANCE PROJECT PHASE II (P106596)

 PHINDPDOTBL




          Number of rural people with access to an all-season road (Number, Core Supplement)



                                               Baseline                       Actual (Previous)   Actual (Current)          End Target

         Value                                 --                             5000.00             5000.00                   7080.00




 PHINDPDOTBL




          Roads rehabilitated, Non-rural (Kilometers, Core)


                                               Baseline                       Actual (Previous)   Actual (Current)          End Target

         Value                                 0.00                           50.00               50.00                     50.00

         Date                                  30-Oct-2009                    13-Mar-2015         24-Jul-2015               30-Apr-2016


         Comments
         The 50% target will be achieved after completion of ongoing works in Kalabo District



 PHINDPDOTBL




          Total annual number of road fatalities in Lusaka and Copperbelt provinces (Number, Custom)


                                               Baseline                       Actual (Previous)   Actual (Current)          End Target

         Value                                 714.00                         805.00              802.00                    900.00

         Date                                  27-Oct-2009                    13-Mar-2015         24-Jul-2015               30-Apr-2016


         Comments
         The target has been exceeded i.e. the fatalities are lower than the target. The update of 802 road fatalities in Lusaka and
         Copperbelt provinces is taken from the Zambia Police Service 2014 Annual Traffic Accident Report found at
         http://zambianroadsafety.org/zambia-police-2014-annual-traffic-accidnet/. The report records fatalities in Lusaka as 447 and those
         in Copperbelt as 355




 Overall Comments

 Intermediate Results Indicators




10/22/2015                                                                                                                            Page 4 of 9
                                                              Public Disclosure Copy
                                                                     Public Disclosure Copy

                   The World Bank                                             Implementation Status & Results Report
                   ROAD REHABILITATION AND MAINTENANCE PROJECT PHASE II (P106596)

 PHINDIRITBL




              Total number of small bridges rehabilitated in the 3 targeted districts (Number, Custom)

                                                      Baseline                      Actual (Previous)          Actual (Current)             End Target

               Value                                  0.00                          10.00                      6.00                         6.00

               Date                                   --                            13-Mar-2015                24-Jul-2015                  30-Apr-2016


               Comments
               At project restructuring in May 2014, the End Target was revised from 10 to 6 small bridges in view of the reduction of supported
               districts from 5 to 3. The original five districts were Chibombo, Mpongwe, Zambezi, Kalabo and Sinazongwe. The last two are
               funded by GRZ. The reduction in actual number reflects the work in the three districts of Chibombo, Mpongwe, and Zambezi. The
               final numbers will be provided after receipt of the completion report. The wording of the indicator was also changed to reflect that
               only three of the original five districts were being supported by the Bank.


 PHINDIRITBL




              Kilometers of roads benefitting from spot improvements in the targeted 3 districts (Kilometers, Custom)

                                                      Baseline                      Actual (Previous)          Actual (Current)             End Target

               Value                                  0.00                          60.00                      60.00                        72.00

               Date                                   --                            13-Mar-2015                24-Jul-2015                  30-Apr-2016


               Comments
               The End target was amended to 72 kilometers. The wording of the indicator was also worded to reflect that only three of the original five
               districts were being supported by the Bank. Indicator to be revised after receipt of MLGH's activity completion report


 PHINDIRITBL




              Number of people reached by HIV/AIDS awareness campaigns (Number, Custom)

                                                      Baseline                      Actual (Previous)          Actual (Current)             End Target

               Value                                  0.00                          1500.00                    1500.00                      5000.00

               Date                                   --                            13-Mar-2015                13-Mar-2015                  30-Jun-2014


               Comments
               The report received from MTWSC on HIV/AIDs component was incomplete. A revised report was expected on Oct. 26, 2015 after which the
               current number will be revised.




10/22/2015                                                                                                                                            Page 5 of 9
                                                                     Public Disclosure Copy
                                                                     Public Disclosure Copy

                   The World Bank                                             Implementation Status & Results Report
                   ROAD REHABILITATION AND MAINTENANCE PROJECT PHASE II (P106596)

 PHINDIRITBL




              Number of private and commercial vehicle undergoing technical inspections in Lusaka (Number, Custom)

                                                      Baseline                       Actual (Previous)          Actual (Current)            End Target

               Value                                  0.00                           400.00                     0.00                        100000.00

               Date                                   --                             13-Mar-2015                24-Jul-2015                 30-Jun-2014


               Comments
               This indicator was deleted following the restructuring of May 2014. It will therefore be deleted in the next sequence (Seq No. 19) of the ISR


 PHINDIRITBL




              Number of school children trained annually at the road safety school part in Lusaka (Number, Custom)

                                                      Baseline                       Actual (Previous)          Actual (Current)            End Target

               Value                                  0.00                           0.00                       0.00                        30000.00

               Date                                   --                             13-Mar-2015                24-Jul-2015                 30-Apr-2016


               Comments
               Implementation of the school park was delayed by lack of an appropriate property in Lusaka. It has not yet commenced. RTSA was still
               procuring the consultancy services. The plan is to complete the works by March 31, 2016. Furthermore, the credit would only fund a portion
               of the school facility.


 PHINDIRITBL




              Number of vehicles crossing the Mufuchani bridge annually (Number, Custom)

                                                      Baseline                       Actual (Previous)          Actual (Current)            End Target

               Value                                  0.00                           0.00                       0.00                        60000.00

               Date                                   --                             13-Mar-2015                13-Mar-2015                 30-Apr-2016


               Comments
               Construction of the bridge was proceeding satisfactorily. The planned completion date is January 31, 2016




10/22/2015                                                                                                                                          Page 6 of 9
                                                                     Public Disclosure Copy
                                                                     Public Disclosure Copy

                   The World Bank                                             Implementation Status & Results Report
                   ROAD REHABILITATION AND MAINTENANCE PROJECT PHASE II (P106596)

 PHINDIRITBL




              Compliance rate with Road Sector Goverance Plan (Percentage, Custom)

                                                     Baseline                      Actual (Previous)          Actual (Current)            End Target

               Value                                 0.00                          70.00                      90.00                       90.00

               Date                                  --                            13-Mar-2015                13-Mar-2015                 30-Apr-2016


               Comments
               All the 12 actions listed in the Road Sector Governance Plan have been accomplished. Regarding the involvement of local communities in
               the supervision of RDA projects, RDA chose to involved the local media instead. RDA's 2013 Annual Report states that "Thirteen media
               tours were conducted during the year under review. Media institutions that took part in the media tours included Zambia National
               Broadcasting Corporation (ZNBC), Muvi Television, Prime Television, Radio Phoenix, Times of Zambia, Zambia Daily Mail, The Post
               Newspaper and Community Radio Stations."


 PHINDIRITBL




              RDA Procurement process compliance rate with international standards (Percentage, Custom)

                                                     Baseline                      Actual (Previous)          Actual (Current)            End Target

               Value                                 72.00                         72.00                      90.00                       90.00

               Date                                  27-Oct-2009                   13-Mar-2015                13-Mar-2015                 30-Apr-2016


               Comments
               RDA has a procurement department that prepares procurement plans and follows procedures and guidelines set in RDA legislation and
               guidleines as well as ZPPA Act. This is confirmed in the 2013 Annual Report at http://www.rda.org.zm/index.php/reports/annual-reports


 PHINDIRITBL




            Number of trucks subjected to annual axle load check at locations financed by the project (Copperbelt and Eastern Provinces )
           (Number, Custom)

                                                     Baseline                      Actual (Previous)          Actual (Current)            End Target

               Value                                 0.00                          0.00                       0.00                        100000.00

               Date                                  --                            13-Mar-2015                13-Mar-2015                 30-Apr-2016


               Comments
               The project supported the design of two weighbridges but due to shortage of funds it will finance the construction of only one - Chongwe
               Weighbridge in Eastern Province, as reflected in the Project Restricting Paper of May 16, 2014. RDA had undertaken to fund
               the construction of the other weighbridge and therefore the target of 100,000 trucks was maintained. Work on Chongwe weighbridge is still
               ongoing with the target completion date of January 31, 2016. RDA funded weighbridge is unlikely to be completed by project closing
               date. After completion of Chongwe weighbridge, it expected that half of the initial axle load checks i.e. 50,000 trucks will be fully met.




10/22/2015                                                                                                                                        Page 7 of 9
                                                                     Public Disclosure Copy
                                                                      Public Disclosure Copy

                   The World Bank                                             Implementation Status & Results Report
                   ROAD REHABILITATION AND MAINTENANCE PROJECT PHASE II (P106596)

 PHINDIRITBL




              Annual road fatalities per 10,000 registered vehicles (Number, Custom)

                                                      Baseline                     Actual (Previous)         Actual (Current)             End Target

               Value                                  48.00                        50.00                     31.00                        36.00

               Date                                   27-Oct-2009                  13-Mar-2015               13-Mar-2015                  30-Apr-2016


               Comments
               The target has been exceeded. The "current" number of 31.00 deaths per 10,000 vehicles is derived from the Zambia Police
               Service 2014 Annual Traffic Accident Report found at http://zambianroadsafety.org/zambia-police-2014-annual-traffic-accidnet/ .
               The report provides the total number of registered vehicles in Zambia as 605,636 and the total fatalities for 2014 as 1,858.




 Overall Comments



 Data on Financial Performance

Disbursements (by loan)

 Project                Loan/Credit/TF    Status        Currency        Original   Revised     Cancelled    Disbursed      Undisbursed                  Disbursed

 P106596                IDA-46540         Effective     XDR               48.30      48.30           0.00         45.13            3.17                         93%


Key Dates (by loan)
 Project                Loan/Credit/TF    Status        Approval Date      Signing Date      Effectiveness Date    Orig. Closing Date     Rev. Closing Date

 P106596                IDA-46540         Effective     16-Oct-2009        25-Nov-2009       30-Mar-2010           30-Jun-2014            30-Apr-2016



Cumulative Disbursements




10/22/2015                                                                                                                                        Page 8 of 9
                                                                      Public Disclosure Copy
                                          Public Disclosure Copy

        The World Bank                                             Implementation Status & Results Report
        ROAD REHABILITATION AND MAINTENANCE PROJECT PHASE II (P106596)




 Restructuring History

 Level Approved on 30-May-2014




 Related Project(s)

There are no related projects.




10/22/2015                                                                                       Page 9 of 9
                                          Public Disclosure Copy