PROCUREMENT PLAN (Textual Part) Project information: Country: Afghanistan Project name: Cities Investment Program (CIP) Project ID: P160619 Project Implementation agency: Deputy Ministry for Municipalities (DMM) IDLG Date of the Procurement Plan: 28 October 2019 Period covered by this Procurement Plan: The Procurement plan covers the period of 6 Months Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the Model Procurement Documents agreed by the bank shall be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Procurement Law of the Islamic Republic of Afghanistan dated 27/06/13965 (September 17, 2016) published in the Official Gazette No.1223, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following NPP Conditions for Afghanistan: 1. The eligibility of bidders shall be as defined under Section III of the World Bank Procurement Regulations for IPF Borrowers (Procurement Regulations). Accordingly, no bidder or potential bidder shall be declared ineligible for contracts financed by the Bank for reasons other than those provided in Section III of the Procurement Regulations (PR). 2. Only the model bidding documents acceptable to the World Bank shall be used for all national open competitive procurement. 3. The bidding documents shall require that bidders/proposers submitting bids/proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. 4. There shall be no negotiations of contract price at post contract stage or termination of the contract - on grounds of operation of Price Adjustment stipulated in a signed contract exceeding a specified percentage. 5. No preference of any kind shall be given to national bidders in the bidding process. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Specify for each Goods: [is not applicable/ is applicable for those contracts identified in the Procurement Plan tables]; NA Works: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables]; NA Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. “Not Applicable” Other Relevant Procurement Information. Also Project beyond the threshold of the First Grade Award Authorities will be facilitated by National Procurement Authority( NPA). PROCUREMENT Afghanistan : Cities Investment Program PLAN General Information Country: Afghanistan Bank’s Approval Date of the Original Procurement Plan: 2019-11-04 2020-11-25 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P160619 GPN Date: 2019-07-08 Project Name: Cities Investment Program Loan / Credit No: IDA / D4140 I Executing Agency(ies): ndependent Directorate of local governance-CIP WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned AF-IDLG-CIP-139982-CW- RFB / HRT-PP 08- Component 1: Rehabilitate Single Stage - One 2021-07- IDA / D4140 Post Request for Bids Open - National 433,776.00 323,064.82 Signed 2020-04-15 2020-02-23 2020-04-20 2020-06-01 2020-03-23 2020-07-01 2020-06-01 2020-08-05 2020-06-28 Construction of Salakhi ha Municipal Infrastructure Envelope 01 Asphalt Road in District 3 AF-IDLG-CIP-139983-CW- RFB / (HRT-PP-20) CONSTRUCTION OF SAYED AKHTAR AGHA ROAD PROJECT Component 1: Rehabilitate Single Stage - One 2021-05- IDA / D4140 Post Request for Bids Open - National 861,602.00 586,905.03 Signed 2020-04-20 2020-02-10 2020-04-25 2020-06-06 2020-02-10 2020-07-06 2020-05-06 2020-08-10 2020-06-01 in District 11 (HRT-PP-02) Municipal Infrastructure Envelope 07 CONSTRUCTION OF ZAINUL ABBEDIN ROAD PROJECT in District 6 ( 2 Lots) AF-IDLG-CIP-139987-CW- RFB / MZR-PP 26- Construction of Kart -e-Sulh Component 1: Rehabilitate Single Stage - One 2021-02- 3 Asphalt Road and MZR-PP IDA / D4140 Post Request for Bids Open - National 515,674.00 572,955.16 Signed 2020-02-29 2020-02-17 2020-03-05 2020-03-19 2020-04-16 2020-03-17 2020-05-16 2020-06-08 2020-06-20 2020-06-28 Municipal Infrastructure Envelope 15 27- Construction of North of Amani Project's Asphalt Road in District 7 ( 2 Lots) AF-IDLG-CIP-139989-CW- RFB / KND-PP 19- Construction of Yaklang Road in District 7 and KND-PP 20- Component 1: Rehabilitate Single Stage - One 1,286,214.2 2021-01- IDA / D4140 Post Request for Bids Open - National 1,353,891.00 Signed 2020-03-15 2020-02-22 2020-03-20 2020-05-01 2020-03-22 2020-05-31 2020-06-16 2020-07-05 2020-07-28 Construction of Mer Bazaar Municipal Infrastructure Envelope 4 31 Road start from Mirwais Main Road to Mer Bazaar High School ( 2 Lots) AF-IDLG-CIP-140098-CW- RFB / KST-PP-10- Construction of C-reserve Component 1: Rehabilitate Single Stage - One 2020-12- area Asphalt Road in District 4 IDA / D4140 Post Request for Bids Open - National 1,183,254.00 0.00 Canceled 2020-01-25 2020-01-30 2020-03-12 2020-04-11 2020-05-16 Municipal Infrastructure Envelope 12 and KST-PP-09- Construction of Asphalt Roads in District 2 and 3 (2 Lots) AF-IDLG-CIP-140111-CW- RFB / JBD-PP 14- Construction of Asphalt Roads Component 1: Rehabilitate Single Stage - One 2021-04- IDA / D4140 Post Request for Bids Open - National 1,033,209.00 0.00 Canceled 2020-03-25 2020-03-30 2020-05-11 2020-06-10 2020-07-15 in District 2 and JBD-PP 17- Municipal Infrastructure Envelope 11 Construction of Asphalt Roads in District 4 ( 2 Lots) AF-IDLG-CIP-141482-CW- RFB / KND-PP 15- Component 1: Rehabilitate Single Stage - One 2021-01- IDA / D4140 Post Request for Bids Open - National 722,951.00 580,563.22 Signed 2020-03-10 2020-04-22 2020-03-15 2020-04-26 2020-05-21 2020-05-26 2020-07-21 2020-06-30 2020-08-27 Construction of Bypass road, Municipal Infrastructure Envelope 26 side ditches in district 3 AF-IDLG-CIP-143184-CW- RFQ / Rehabilitation /repairing of existing facilities Component 4: Project Request for Single Stage - One 2020-03- IDA / D4140 Post Limited 30,000.00 0.00 Canceled 2019-12-05 2020-01-30 ( warehouse , driver rooms Implementation Management Quotations Envelope 15 and toilets for guards , Drivers and costumers) AF-IDLG-CIP-162457-CW- RFB / CONSTRUCTION OF Component 1: Rehabilitate Single Stage - One 2021-02- 1200 FAMILY PHASE-A ROADS IDA / D4140 Post Request for Bids Open - National 396,465.00 263,274.50 Signed 2020-04-15 2020-04-03 2020-04-20 2020-06-01 2020-06-02 2020-07-01 2020-07-21 2020-08-05 2020-08-27 Municipal Infrastructure Envelope 01 (KHST-PP-02) in Khost Province AF-IDLG-CIP-140096-CW- RFB / KST-PP-08- Component 1: Rehabilitate Single Stage - One 2021-01- IDA / D4140 Post Request for Bids Open - National 845,350.00 734,763.25 Signed 2020-01-15 2020-02-11 2020-01-20 2020-03-02 2020-03-12 2020-04-01 2020-04-06 2020-05-06 2020-06-07 Construction of Madikhel Municipal Infrastructure Envelope 31 Asphalt Road in District 1 AF-IDLG-CIP-139985-CW- RFB / MZR-PP 23- Construction of Baba Yadgar Tertiary Road in District 4 and Component 1: Rehabilitate Single Stage - One 2021-03- IDA / D4140 Post Request for Bids Open - National 812,746.00 0.00 Canceled 2020-02-25 2019-12-16 2020-03-01 2020-04-12 2020-02-05 2020-05-12 2020-04-14 2020-06-16 MZR-PP 08- Construction of Municipal Infrastructure Envelope 13 Ota Qul & Ghulam Sakhi Khan Bagh Asphalt Streets in District 3 ( 2 Lots) AF-IDLG-CIP-169362-CW- RFB / MZR-PP 23- Construction of Baba Yadgar Tertiary Road in District 4 and Component 1: Rehabilitate Single Stage - One 2021-03- IDA / D4140 Post Request for Bids Open - National 812,746.00 586,555.66 Signed 2020-05-23 2020-05-06 2020-05-28 2020-07-09 2020-06-04 2020-08-08 2020-07-18 2020-09-12 2020-08-29 MZR-PP 08- Construction of Municipal Infrastructure Envelope 11 Ota Qul & Ghulam Sakhi Khan Bagh Asphalt Streets in District 3 ( 2 Lots) AF-IDLG-CIP-180516-CW- RFB / Rebid of Construction of Asphalt Roads in District 2 JBD- Component 1: Rehabilitate Single Stage - One 2021-06- IDA / D4140 Post Request for Bids Open - National 1,035,217.43 838,225.75 Signed 2020-08-17 2020-07-19 2020-08-22 2020-07-20 2020-10-03 2020-08-17 2020-11-02 2020-09-27 2020-12-07 2020-11-10 PP 14 and JBD-PP 17- Municipal Infrastructure Envelope 05 Construction of Asphalt Roads in District 4 (2 Lots). Page 1 AF-IDLG-CIP-180530-CW- RFB / Rebid of Construction of Asphalt Roads in District 2 Component 1: Rehabilitate Single Stage - One 2021-06- KST-PP-09 and Construction IDA / D4140 Post Request for Bids Open - National 1,183,253.78 907,090.22 Signed 2020-08-16 2020-07-22 2020-08-21 2020-07-25 2020-10-02 2020-08-20 2020-11-01 2020-10-11 2020-12-06 2020-11-10 Municipal Infrastructure Envelope 04 of C-reserve area Asphalt Road in District 4 KST-PP-10 in Khost Province. AF-IDLG-CIP-179178-CW- RFQ / Median and sidewalk Component 1: Rehabilitate Request for Single Stage - One 2021-03- construction, Ahmadshahi IDA / D4140 Post Open - National 95,548.00 0.00 Canceled 2020-07-30 2020-09-24 Municipal Infrastructure Quotations Envelope 23 Jada in district 14 Ahmad Shahi Jada- Kandahar Porvince AF-EZ-KAR_IDLG-CIP PIU- 147071-CW-RFB-15 / Pending Construction of Haji Aziz Component 1: Rehabilitate 2021-01- IDA / D4140 Post Direct Selection Direct 439,976.60 0.00 Implementat 2020-06-10 2020-06-15 2020-07-20 Road (KND-PP-21) District-5 Municipal Infrastructure 16 ion Kandahar City, Kandahar Province AF-IDLG-CIP-179193-CW- RFQ / Canal Cleaning (Pathaw Component 1: Rehabilitate Request for Single Stage - One 2021-03- IDA / D4140 Post Open - National 79,200.00 0.00 Canceled 2020-08-01 2020-09-26 canal) in district 2 and 3 - Municipal Infrastructure Quotations Envelope 25 Kandahar Porvince AF-IDLG-CIP-179258-CW- RFQ / Municipality Main Building Repairing (PVC Component 1: Rehabilitate Request for Single Stage - One 2021-03- IDA / D4140 Post Open - National 31,840.00 0.00 Canceled 2020-08-02 2020-09-27 doors+ Windows+ painting Municipal Infrastructure Quotations Envelope 26 etc) in Distrct 2 Municipality Main Building Khost Province AF-IDLG-CIP-179280-CW- RFQ / Stone Masonry wall Component 1: Rehabilitate Request for Single Stage - One 2021-04- repair and grill installation for IDA / D4140 Post Open - National 8,250.00 0.00 Canceled 2020-08-22 2020-10-17 Municipal Infrastructure Quotations Envelope 15 recreation park (2750) in District 4 Khost Province AF-IDLG-CIP-179284-CW- RFQ / Boundary wall Component 1: Rehabilitate Request for Single Stage - One 2021-04- construction of Park-1 in C IDA / D4140 Post Open - National 25,580.00 0.00 Canceled 2020-08-21 2020-10-16 Municipal Infrastructure Quotations Envelope 14 Families (136m) in District 4 Khost Province AF-IDLG-CIP-179286-CW- RFQ / Boundary wall Component 1: Rehabilitate Request for Single Stage - One 2021-04- construction of Park-3 in C IDA / D4140 Post Open - National 32,128.00 0.00 Canceled 2020-08-15 2020-10-10 Municipal Infrastructure Quotations Envelope 08 Families (126m) in District 4 Khost Province AF-IDLG-CIP-179238-CW- RFQ / Construction of Parks ( Gul Hussain and Mohammad Component 1: Rehabilitate Request for Single Stage - One 2021-03- IDA / D4140 Post Open - National 38,555.00 0.00 Canceled 2020-08-03 2020-09-28 Saeed) in district 1 Gul Municipal Infrastructure Quotations Envelope 27 Hussain and Mohammad Saeed Jalal Abad Province AF-IDLG-CIP-179251-CW- RFQ / District 1 Municipality Component 1: Rehabilitate Request for Single Stage - One 2021-03- IDA / D4140 Post Open - National 23,940.00 0.00 Canceled 2020-08-03 2020-09-28 building Rehabilitation District Municipal Infrastructure Quotations Envelope 27 1, Municipality Khost Province AF-IDLG-CIP-179165-CW- RFQ / Median Construction of Component 1: Rehabilitate Request for Single Stage - One 2021-03- Kandahar and Herat main IDA / D4140 Post Open - National 92,337.00 0.00 Canceled 2020-07-30 2020-09-24 Municipal Infrastructure Quotations Envelope 23 road in district 8 Kandahar Herat main road Kandahar Porvince AF-IDLG-CIP-179229-CW- RFQ / Side walk construction Component 1: Rehabilitate Request for Single Stage - One 2021-03- (Mosaic), Serajul Emara in IDA / D4140 Post Open - National 90,428.00 0.00 Canceled 2020-07-25 2020-09-19 Municipal Infrastructure Quotations Envelope 18 district 1 Serajul Emara Jalal Abad Province AF-IDLG-CIP-179236-CW- RFQ / Construction of Parks Component 1: Rehabilitate Request for Single Stage - One 2021-03- (Dawlat Sha and Kochai) in IDA / D4140 Post Open - National 38,555.00 0.00 Canceled 2020-08-05 2020-09-30 Municipal Infrastructure Quotations Envelope 29 district 2 Dawlat Sha and Kochai Jalal Abad Province AF-IDLG-CIP-179234-CW- RFQ / Trash Bins installation Component 1: Rehabilitate Request for Single Stage - One 2021-03- IDA / D4140 Post Open - National 60,389.00 0.00 Canceled 2020-08-04 2020-09-29 in District-1,2,3,4,5 & 7 Jalal Municipal Infrastructure Quotations Envelope 28 Abad Province AF-EZ-KAR_IDLG-CIP PIU- 147077-CW-RFB-13 / CONSTRUCTION OF Component 1: Rehabilitate 2021-01- IDA / D4140 Post Direct Selection Direct 363,679.00 284,026.82 Signed 2020-06-10 2020-06-10 2020-06-15 2020-04-11 2020-07-20 2020-05-28 CONCRETE STREETS AT Municipal Infrastructure 16 JALALABAD PROVINCE IN SINGLE LOT AF-IDLG-CIP-179254-CW- RFQ / Sidewalk construction Component 1: Rehabilitate Request for Single Stage - One 2021-03- (Mosaic) (2230m) in Distrct 4 IDA / D4140 Post Open - National 98,343.00 0.00 Canceled 2020-08-02 2020-09-27 Municipal Infrastructure Quotations Envelope 26 in 1200 Families, Phase A Khost Province AF-IDLG-CIP-179266-CW- RFQ / City drain cleaning and Component 1: Rehabilitate Request for Single Stage - One 2021-03- Repairing of damaged IDA / D4140 Post Open - National 25,300.00 0.00 Canceled 2020-07-31 2020-09-25 Municipal Infrastructure Quotations Envelope 24 concrete (1400m) in District 1 and 2 and 3 Khost city AF-IDLG-CIP-179293-CW- RFQ / Boundary wall Component 1: Rehabilitate Request for Single Stage - One 2021-04- construction of Matun Mina IDA / D4140 Post Open - National 25,041.00 0.00 Canceled 2020-08-20 2020-10-15 Municipal Infrastructure Quotations Envelope 13 Park(86m) in District 5 Khost Province Page 2 AF-IDLG-CIP-179301-CW- RFQ / Canal Cleaning Component 1: Rehabilitate Request for Single Stage - One 2021-04- IDA / D4140 Post Open - National 25,300.00 0.00 Canceled 2020-09-02 2020-10-28 (600mx20mx1m) in District 2 Municipal Infrastructure Quotations Envelope 26 and 10 Herat City AF-IDLG-CIP-179310-CW- RFQ / Canal Cleaning from Angor Bagh to Chaparhar old Component 1: Rehabilitate Request for Single Stage - One 2021-04- IDA / D4140 Post Open - National 4,493.00 0.00 Canceled 2020-08-29 2020-10-24 Hada in district 4 Angor Municipal Infrastructure Quotations Envelope 22 Bagh to Chaparhar old Hada Jalal Abad Province AF-IDLG-CIP-179296-CW- RFQ / Side walk construction Component 1: Rehabilitate Request for Single Stage - One 2021-04- IDA / D4140 Post Open - National 96,750.00 0.00 Canceled 2020-08-28 2020-10-23 in District 1, 2,3, 4,5,6,7, 8, 9, Municipal Infrastructure Quotations Envelope 21 11& 15 Herat City AF-IDLG-CIP-179205-CW- RFQ / Construction of boundary wall for new Component 1: Rehabilitate Request for Single Stage - One 2021-03- IDA / D4140 Post Open - National 97,709.00 0.00 Canceled 2020-07-31 2020-09-25 Municipality building in Municipal Infrastructure Quotations Envelope 24 district 11 Aino Mina - Kandahar Province AF-IDLG-CIP-179237-CW- RFQ / Construction of Parks Component 1: Rehabilitate Request for Single Stage - One 2021-03- (Sabawon and Haji Zahir) in IDA / D4140 Post Open - National 38,555.00 0.00 Canceled 2020-08-04 2020-09-29 Municipal Infrastructure Quotations Envelope 28 district 2 Sabawon and Haji Zahir Jalal Abad Province AF-IDLG-CIP-179270-CW- RFQ / Canal Cleaning of Component 1: Rehabilitate Request for Single Stage - One 2021-03- IDA / D4140 Post Open - National 1,750.00 0.00 Canceled 2020-07-26 2020-09-20 Rogha Kalai (700) in Distrct 4 Municipal Infrastructure Quotations Envelope 19 Khost Province AF-IDLG-CIP-179272-CW- RFQ / Construction of RCC Component 1: Rehabilitate Request for Single Stage - One 2021-03- Trash or Garbage Bins in IDA / D4140 Post Open - National 43,842.00 0.00 Canceled 2020-07-26 2020-09-20 Municipal Infrastructure Quotations Envelope 19 District 1,2,3,4,5,6, &7 Khost Province AF-IDLG-CIP-179276-CW- RFQ / Sidewalk construction Component 1: Rehabilitate Request for Single Stage - One 2021-03- (Mosaic) (1600m) in District IDA / D4140 Post Open - National 35,280.00 0.00 Canceled 2020-08-01 2020-09-26 Municipal Infrastructure Quotations Envelope 25 Four 1200 Families, Phase A Khost Province AF-IDLG-CIP-179290-CW- RFQ / Boundary wall Component 1: Rehabilitate Request for Single Stage - One 2021-04- construction of Park-2 in C IDA / D4140 Post Open - National 36,360.00 0.00 Canceled 2020-08-16 2020-10-11 Municipal Infrastructure Quotations Envelope 09 Families (196m) in District 4 Khost Province AF-IDLG-CIP-179312-CW- RFQ / Construction of Parks Component 1: Rehabilitate Request for Single Stage - One 2021-04- (2) Near Momand Hospital in IDA / D4140 Post Open - National 3,855.00 0.00 Canceled 2020-08-27 2020-10-22 Municipal Infrastructure Quotations Envelope 20 district 2 Near Momand Hospital Jalal Abad Province AF-IDLG-CIP-179174-CW- RFQ / Median Construction on Component 1: Rehabilitate Request for Single Stage - One 2021-03- Kandahar and Herat main IDA / D4140 Post Open - National 93,270.00 0.00 Canceled 2020-07-27 2020-09-21 Municipal Infrastructure Quotations Envelope 20 road in district 8 Kandahar Herat main road- Kandahar Porvince AF-IDLG-CIP-179190-CW- RFQ / Canal Cleaning (Pathaw Component 1: Rehabilitate Request for Single Stage - One 2021-03- IDA / D4140 Post Open - National 87,120.00 0.00 Canceled 2020-07-30 2020-09-24 canal) in District 1- Kandahar Municipal Infrastructure Quotations Envelope 23 Porvince AF-IDLG-CIP-180116-CW- RFQ / Canal Cleaning Component 1: Rehabilitate Request for Single Stage - One 2021-03- IDA / D4140 Post Open - National 96,750.00 0.00 Canceled 2020-07-27 2020-09-21 (600mx20mx1m) in District 8 Municipal Infrastructure Quotations Envelope 20 & 15 Herat City AF-IDLG-CIP-179243-CW- Under RFQ / Road graveling Matun Component 1: Rehabilitate Request for Single Stage - One 2021-03- IDA / D4140 Post Open - National 61,469.00 0.00 Implementat 2020-08-02 2020-09-27 Mina (4000m) in Distrct 5 Municipal Infrastructure Quotations Envelope 26 ion Matun Mina Khost Province AF-IDLG-CIP-179257-CW- Under RFQ / Road graveling (1250) Component 1: Rehabilitate Request for Single Stage - One 2021-03- IDA / D4140 Post Open - National 11,225.00 0.00 Implementat 2020-08-04 2020-09-29 Matun in Distrct 3 Matun Municipal Infrastructure Quotations Envelope 28 ion Khost Province AF-IDLG-CIP-179261-CW- RFQ / Road graveling Khalise Component 1: Rehabilitate Request for Single Stage - One 2021-03- IDA / D4140 Post Open - National 12,778.00 0.00 Canceled 2020-07-27 2020-09-21 Kalai (1451m) in District 2 Municipal Infrastructure Quotations Envelope 20 Khost Province AF-IDLG-CIP-179265-CW- RFQ / Road graveling, Manni Component 1: Rehabilitate Request for Single Stage - One 2021-03- IDA / D4140 Post Open - National 18,348.00 0.00 Canceled 2020-08-05 2020-09-30 Kalai (1742m) in Distrct 9 Municipal Infrastructure Quotations Envelope 29 Khost Province AF-IDLG-CIP-179269-CW- RFQ / Canal Cleaning of Component 1: Rehabilitate Request for Single Stage - One 2021-03- IDA / D4140 Post Open - National 57,950.00 0.00 Canceled 2020-07-26 2020-09-20 Matun Tapa in District 4 Municipal Infrastructure Quotations Envelope 19 Khost Province AF-IDLG-CIP-179306-CW- RFQ / Drainage Cleaning Component 1: Rehabilitate Request for Single Stage - One 2021-04- IDA / D4140 Post Open - National 8,752.00 0.00 Canceled 2020-08-28 2020-10-23 (7000m) in district 4 Mazar Municipal Infrastructure Quotations Envelope 21 Province AF-IDLG-CIP-179304-CW- RFQ / Drainage Cleaning Component 1: Rehabilitate Request for Single Stage - One 2021-04- IDA / D4140 Post Open - National 4,809.00 0.00 Canceled 2020-09-02 2020-10-28 (3800m) in district 1 Mazar Municipal Infrastructure Quotations Envelope 26 Province Page 3 AF-IDLG-CIP-193759-CW- RFB / CONSTRUCTION OF Component 1: Rehabilitate Single Stage - One 2021-07- SAID AKHTAR AGHA ASPHALT IDA / D4140 Post Request for Bids Open - National 220,330.90 200,284.25 Signed 2020-09-26 2020-05-17 2020-10-01 2020-11-12 2020-06-15 2020-12-12 2020-09-02 2021-01-16 2020-10-15 Municipal Infrastructure Envelope 15 ROAD IN DISTRICT 11, HERAT PORVINCE (PP-20) AF-IDLG-CIP-179210-CW- Under RFQ / 6km Road Graveling in Component 1: Rehabilitate Request for Single Stage - One 2021-03- IDA / D4140 Post Open - National 67,498.00 0.00 Implementat 2020-08-05 2020-09-30 Nangarhar Province Qyamudin Municipal Infrastructure Quotations Envelope 29 ion Village AF-IDLG-CIP-179221-CW- Under RFQ / 6km Road Graveling in Component 1: Rehabilitate Request for Single Stage - One 2021-03- IDA / D4140 Post Open - National 67,498.00 0.00 Implementat 2020-07-31 2020-09-25 Nangarhar Province Samarkhil Municipal Infrastructure Quotations Envelope 24 ion Graveyard AF-IDLG-CIP-179227-CW- Under RFQ / 6km Road Graveling at Component 1: Rehabilitate Request for Single Stage - One 2021-03- IDA / D4140 Post Open - National 67,498.00 0.00 Implementat 2020-08-03 2020-09-28 district 6 - Najuml Jihad Town Municipal Infrastructure Quotations Envelope 27 ion of Nangarhar Province AF-IDLG-CIP-179231-CW- Under RFQ / 3km Canal Cleaning at Component 1: Rehabilitate Request for Single Stage - One 2021-03- IDA / D4140 Post Open - National 54,146.00 0.00 Implementat 2020-07-27 2020-09-21 district 4 - Angurbagh to Municipal Infrastructure Quotations Envelope 20 ion Airport- Nangarhar Province AF-IDLG-CIP-195941-CW- Component 1: Rehabilitate Request for Single Stage - One 2021-07- RFQ / Canal Cleaning in Herat IDA / D4140 Post Open - National 67,970.00 0.00 Canceled 2020-11-28 2021-01-24 Municipal Infrastructure Quotations Envelope 23 Province in district 2 & 10 AF-IDLG-CIP-195947-CW- Component 1: Rehabilitate Request for Single Stage - One 2021-07- RFQ / Canal Cleaning in Herat IDA / D4140 Post Open - National 76,970.00 0.00 Canceled 2020-11-30 2021-01-25 Municipal Infrastructure Quotations Envelope 24 Province in district 8 & 15 AF-IDLG-CIP-200287-CW- Under RFQ / 5.6 Km Road Median Component 1: Rehabilitate Request for Single Stage - One 2021-07- IDA / D4140 Post Open - National 42,342.00 0.00 Implementat 2020-11-23 2021-01-18 Leveling in Balkh Province Municipal Infrastructure Quotations Envelope 17 ion Mazar-i-Sharif in district 2 &9 AF-IDLG-CIP-200288-CW- Under RFQ / 6km Drain Cleaning in Component 1: Rehabilitate Request for Single Stage - One 2021-07- IDA / D4140 Post Open - National 7,948.00 0.00 Implementat 2020-11-21 2021-01-16 Balkh Province Mazar-i-Sharif Municipal Infrastructure Quotations Envelope 15 ion in district 3&8 AF-IDLG-CIP-200290-CW- RFQ / 4km Nahre Shahy Canal Under Component 1: Rehabilitate Request for Single Stage - One 2021-07- Cleaning in Balkh Province IDA / D4140 Post Open - National 59,942.00 0.00 Implementat 2020-11-26 2021-01-21 Municipal Infrastructure Quotations Envelope 20 Mazar-i-Sharif in districts ion 1,6,10,11 AF-IDLG-CIP-200292-CW- Under RFQ / 6km Drain Cleaning in Component 1: Rehabilitate Request for Single Stage - One 2021-07- IDA / D4140 Post Open - National 7,948.20 0.00 Implementat 2020-11-28 2021-01-23 Balkh Province Mazar-i-Sharif Municipal Infrastructure Quotations Envelope 22 ion in district 2 &9 AF-IDLG-CIP-200293-CW- Under RFQ / 14km Drain Cleaning in Component 1: Rehabilitate Request for Single Stage - One 2021-07- IDA / D4140 Post Open - National 18,377.00 0.00 Implementat 2020-12-04 2021-01-29 Balkh Province Mazar-i-Sharif Municipal Infrastructure Quotations Envelope 28 ion in district 5th AF-IDLG-CIP-200294-CW- Under RFQ / 2.5km Road Median Component 1: Rehabilitate Request for Single Stage - One 2021-07- IDA / D4140 Post Open - National 19,315.41 0.00 Implementat 2020-11-19 2021-01-14 Leveling in Balkh Province Municipal Infrastructure Quotations Envelope 13 ion Mazar-i-Sharif in district 4,9 AF-IDLG-CIP-200295-CW- RFQ / 1.2km Road gravelling Component 1: Rehabilitate Request for Single Stage - One 2021-07- IDA / D4140 Post Open - National 32,643.53 0.00 Canceled 2020-12-04 2021-01-29 in Balkh Province Mazar-i- Municipal Infrastructure Quotations Envelope 28 Sharif in district 9 AF-IDLG-CIP-200296-CW- RFQ / 9.820Km Road Component 1: Rehabilitate Request for Single Stage - One 2021-07- IDA / D4140 Post Open - National 93,292.12 0.00 Canceled 2020-12-03 2021-01-28 gravelling in Balkh Province Municipal Infrastructure Quotations Envelope 27 Mazar-i-Sharif in district 5 AF-IDLG-CIP-200298-CW- RFQ / 10.224km Road Component 1: Rehabilitate Request for Single Stage - One 2021-07- IDA / D4140 Post Open - National 97,124.37 0.00 Canceled 2020-11-20 2021-01-15 gravelling in Balkh Province Municipal Infrastructure Quotations Envelope 14 Mazar-i-Sharif in district 10 AF-IDLG-CIP-200299-CW- RFQ / 10.855km Road Component 1: Rehabilitate Request for Single Stage - One 2021-07- IDA / D4140 Post Open - National 94,602.24 0.00 Canceled 2020-11-30 2021-01-25 gravelling in Balkh Province Municipal Infrastructure Quotations Envelope 24 Mazar-i-Sharif in distirc 5 AF-IDLG-CIP-200300-CW- RFQ / 10.711km Road Component 1: Rehabilitate Request for Single Stage - One 2021-07- IDA / D4140 Post Open - National 93,348.73 0.00 Canceled 2020-11-14 2021-01-09 gravelling in Balkh Province Municipal Infrastructure Quotations Envelope 08 Mazar-i-Sharif in district 7 AF-IDLG-CIP-200301-CW- RFQ / 10.010km Road Component 1: Rehabilitate Request for Single Stage - One 2021-07- IDA / D4140 Post Open - National 95,094.09 0.00 Canceled 2020-12-04 2021-01-29 gravelling in Balkh Province Municipal Infrastructure Quotations Envelope 28 Mazar-i-Sharif in district 9 AF-IDLG-CIP-200302-CW- RFQ / 2.130km Road Component 1: Rehabilitate Request for Single Stage - One 2021-07- IDA / D4140 Post Open - National 30,129.86 0.00 Canceled 2020-12-03 2021-01-28 gravelling in Balkh Province Municipal Infrastructure Quotations Envelope 27 Mazar-i-Sharif in district 12 AF-IDLG-CIP-200303-CW- RFQ / 0.887km Road Component 1: Rehabilitate Request for Single Stage - One 2021-07- IDA / D4140 Post Open - National 12,620.51 0.00 Canceled 2020-12-04 2021-01-29 gravelling in Balkh Province Municipal Infrastructure Quotations Envelope 28 Mazar-i-Sharif in district 7 AF-IDLG-CIP-200304-CW- RFQ / 1.784Km Road Component 1: Rehabilitate Request for Single Stage - One 2021-07- IDA / D4140 Post Open - National 25,256.00 0.00 Canceled 2020-12-01 2021-01-26 gravelling in Balkh Province Municipal Infrastructure Quotations Envelope 25 Mazar-i-Sharif in district 12 Page 4 AF-IDLG-CIP-200305-CW- RFQ / 9.301km Road Component 1: Rehabilitate Request for Single Stage - One 2021-07- IDA / D4140 Post Open - National 97,545.51 0.00 Canceled 2020-12-05 2021-01-30 gravelling in Balkh Province Municipal Infrastructure Quotations Envelope 29 Mazar-i-Sharif in district 12 AF-IDLG-CIP-200306-CW- RFQ / 2.217km Road Component 1: Rehabilitate Request for Single Stage - One 2021-07- IDA / D4140 Post Open - National 25,084.73 0.00 Canceled 2020-11-27 2021-01-22 gravelling in Balkh Province Municipal Infrastructure Quotations Envelope 21 Mazar-i-Sharif in district 12 AF-IDLG-CIP-200307-CW- RFQ / 2.295km Road Component 1: Rehabilitate Request for Single Stage - One 2021-07- IDA / D4140 Post Open - National 27,176.80 0.00 Canceled 2020-11-29 2021-01-24 gravelling in Balkh Province Municipal Infrastructure Quotations Envelope 23 Mazar-i-Sharif in district 12 AF-IDLG-CIP-200308-CW- RFQ / 9.951km Road Component 1: Rehabilitate Request for Single Stage - One 2021-07- IDA / D4140 Post Open - National 58,482.55 0.00 Canceled 2020-12-03 2021-01-28 gravelling in Balkh Province Municipal Infrastructure Quotations Envelope 27 Mazar-i-Sharif in district 5 AF-IDLG-CIP-200309-CW- RFQ / 3.232km Road Component 1: Rehabilitate Request for Single Stage - One 2021-07- IDA / D4140 Post Open - National 38,221.01 0.00 Canceled 2020-11-26 2021-01-21 gravelling in Balkh Province Municipal Infrastructure Quotations Envelope 20 Mazar-i-Sharif in district 11 AF-IDLG-CIP-200310-CW- RFQ / 2.152km Road Component 1: Rehabilitate Request for Single Stage - One 2021-07- IDA / D4140 Post Open - National 26,728.37 0.00 Canceled 2020-11-21 2021-01-16 gravelling in Balkh Province Municipal Infrastructure Quotations Envelope 15 Mazar-i-Sharif in district 11 AF-IDLG-CIP-200311-CW- RFQ / 4.85KM Road gravelling Component 1: Rehabilitate Request for Single Stage - One 2021-07- IDA / D4140 Post Open - National 54,726.99 0.00 Canceled 2020-12-05 2021-01-30 in Balkh Province Mazar-i- Municipal Infrastructure Quotations Envelope 29 Sharif in district 11 AF-IDLG-CIP-205874-CW- Pending RFB / Construction of Children Component 1: Rehabilitate Single Stage - One 2021-12- IDA / D4140 Post Request for Bids Open - National 254,885.00 0.00 Implementat 2021-02-23 2021-02-28 2021-04-11 2021-05-11 2021-06-15 Park in District 5, Khost Municipal Infrastructure Envelope 12 ion Province (KST-PP-05) AF-IDLG-CIP-205877-CW- Pending RFB / Construction of Bus Component 1: Rehabilitate Single Stage - One 2021-12- IDA / D4140 Post Request for Bids Open - National 571,545.00 0.00 Implementat 2021-02-20 2021-02-25 2021-04-08 2021-05-08 2021-06-12 stop in Herat City District 1 Municipal Infrastructure Envelope 09 ion and 12 (HRT-PP-09) AF-IDLG-CIP-205878-CW- RFB / Improvement of Jada Pending Component 1: Rehabilitate Single Stage - One 2021-12- Road Park for women and IDA / D4140 Post Request for Bids Open - National 430,690.00 0.00 Implementat 2021-03-07 2021-03-12 2021-04-23 2021-05-23 2021-06-27 Municipal Infrastructure Envelope 24 children in Kandahar City ion District 9 (KND-PP-07) AF-IDLG-CIP-205879-CW- RFB / Development of Bagh-e- Pending Component 1: Rehabilitate Single Stage - One 2022-01- Zanana (Female Garden) in IDA / D4140 Post Request for Bids Open - National 32,250.00 0.00 Implementat 2021-03-28 2021-04-02 2021-05-14 2021-06-13 2021-07-18 Municipal Infrastructure Envelope 14 Mazar-e- Sharif City District ion 10 (MZR-PP-17) GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual AF-IDLG-CIP-139959-GO- RFQ / Office Furniture and Component 4: Project Request for Single Stage - One fixture for City Investment IDA / D4140 Post Open - National 16,633.00 8,126.72 Signed 2019-12-26 2020-02-20 2019-12-07 2020-04-05 Implementation Management Quotations Envelope Program (CIP) main office setup AF-IDLG-CIP-142171-GO- Component 4: Project Request for Single Stage - One RFQ / Safety Equipment for IDA / D4140 Post Limited 25,000.00 14,217.63 Signed 2020-03-26 2020-03-25 2020-05-21 2020-03-28 2020-06-20 Implementation Management Quotations Envelope CIP security enhancement AF-IDLG-CIP-139954-GO- Pending Component 4: Project Request for Single Stage - One RFQ / ICT Equipment for CIP IDA / D4140 Post Open - National 48,539.00 0.00 Implementati 2019-12-20 2020-02-14 2020-04-14 Implementation Management Quotations Envelope main office setup on AF-IDLG-CIP-139965-GO- Component 4: Project Request for Single Stage - One RFQ / Office Equipment for IDA / D4140 Post Open - National 11,626.00 2,583.94 Signed 2020-01-04 2020-02-29 2020-03-21 2020-03-30 Implementation Management Quotations Envelope CIP main office setup AF-IDLG-CIP-181592-GO- Under RFQ / ICT Equipment for CIP Component 4: Project Request for Single Stage - One IDA / D4140 Post Open - National 47,968.00 0.00 Implementati 2020-09-27 2020-07-28 2020-11-22 2021-05-21 main office and 5 Provincial Implementation Management Quotations Envelope on offices AF-IDLG-CIP-181593-GO- RFQ / Furniture for CIP Main Under Component 4: Project Request for Single Stage - One Office Meeting Room and IDA / D4140 Post Open - National 18,838.00 0.00 Implementati 2020-09-18 2020-07-28 2020-11-13 2021-05-12 Implementation Management Quotations Envelope Furniture for 5 Provincial on Offices AF-IDLG-CIP-196427-GO- Component 3: Improve the Pending Request for Single Stage - One RFQ / Furniture for CIP Main IDA / D4140 Municipal Management Post Open - National 4,844.16 0.00 Implementati 2020-11-04 2020-12-07 2021-01-14 Quotations Envelope Office Framework on AF-IDLG-CIP-199088-GO- RFQ / Samsung mobile model Pending Component 1: Rehabilitate Request for Single Stage - One A21s, Model 2020, RAM 6GB, IDA / D4140 Post Open - National 1,400.00 0.00 Implementati 2020-11-02 2020-12-01 2021-01-03 Municipal Infrastructure Quotations Envelope Camera 48MP, Battery on 5000mAh AF-IDLG-CIP-199089-GO- Pending Component 1: Rehabilitate Request for Single Stage - One RFQ / Safety and Security IDA / D4140 Post Open - National 8,747.00 0.00 Implementati 2020-11-14 2021-01-09 2021-07-08 Municipal Infrastructure Quotations Envelope Instrument for CIP building on Page 5 AF-IDLG-CIP-199093-GO- Pending Component 1: Rehabilitate Request for Single Stage - One RFQ / ICT Equipment for CIP IDA / D4140 Post Open - National 17,123.00 0.00 Implementati 2020-11-26 2021-01-21 2021-07-20 Municipal Infrastructure Quotations Envelope main office on NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual AF-IDLG-CIP-150668-NC- Component 3: Improve the Under RFB / Design and Single Stage - One IDA / D4140 Municipal Management Post Request for Bids Open - National 4,500.00 0.00 Implementati 2020-02-08 2020-10-19 2020-02-13 2020-03-26 2020-04-25 2020-05-30 2020-09-27 Establishment Online Dynamic Envelope Framework on Web Application AF-IDLG-CIP-196429-NC- RFQ / Design and Component 3: Improve the Pending Request for Single Stage - One Establishment Online Dynamic IDA / D4140 Municipal Management Post Open - National 5,850.00 0.00 Implementati 2020-11-04 2020-12-09 2021-01-18 Quotations Envelope Web Application for Kabul CIP Framework on main office CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual AF-IDLG-CIP-162471-CS- Component 2: Strengthen INDV / "Preparing Own Source Quality And Cost- IDA / D4140 the Municipal Finance Prior Open - International 329,259.00 0.00 Canceled 2020-05-24 2020-04-13 2020-06-14 2020-07-28 2020-08-25 2020-09-24 2020-10-29 2020-12-03 2021-12-03 Revenue Enhancement Based Selection Framework Strategies (OSR) AF-IDLG-CIP-170106-CS- Component 2: Strengthen QCBS / Preparing Own Source Quality And Cost- Under IDA / D4140 the Municipal Finance Post Open 329,259.00 0.00 2020-05-27 2020-05-07 2020-06-17 2020-05-09 2020-07-31 2020-08-28 2020-09-27 2020-11-01 2020-12-06 2021-12-06 Revenue Enhancement Based Selection Implementation Framework Strategies (OSR) AF-IDLG-CIP-178824-CS- CQS / Baseline Assessment for Implementation of Component 2: Strengthen Consultant Under Municipal Finance IDA / D4140 the Municipal Finance Post Qualification Limited 37,245.00 0.00 2020-08-30 2020-07-08 2020-09-13 2020-09-28 2020-10-13 2020-11-17 2021-05-16 Implementation Management Information Framework Selection System in Five Provincial Capital Cities. Component 3: Improve the Consultant AF-IDLG-CIP-183942-CS- Under IDA / D4140 Municipal Management Post Qualification Open - International 126,000.00 0.00 2020-09-14 2020-07-26 2020-10-05 2020-08-17 2020-11-18 2020-10-22 2020-12-18 2021-01-22 2021-07-21 CQS / Verification Agent Implementation Framework Selection INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual AF-IDLG-CIP-195763-CS- Component 3: Improve the Individual INDV / AFMIS Technical IT Pending IDA / D4140 Municipal Management Post Consultant Open 16,500.00 0.00 2020-10-10 2020-11-01 2020-11-07 2020-11-18 2020-12-27 Advisors/Consultant (Kabul), Implementation Framework Selection Grade C) for one year AF-IDLG-CIP-195818-CS- Individual Component 1: Rehabilitate INDV / Senior Civil Engineer IDA / D4140 Post Consultant Open 10,000.00 0.00 Canceled 2020-10-24 2020-11-22 2020-11-26 2020-12-04 2021-01-14 Municipal Infrastructure (Kabul), Grade B Selection AF-IDLG-CIP-195926-CS- Component 3: Improve the Individual INDV / AFMIS Technical IT Pending IDA / D4140 Municipal Management Post Consultant Open 16,500.00 0.00 2020-11-08 2020-12-03 2020-12-06 2020-12-13 2021-01-18 Advisors/Consultant (Herat), Implementation Framework Selection Grade C AF-IDLG-CIP-195927-CS- Component 3: Improve the Individual INDV / AFMIS Technical IT Pending IDA / D4140 Municipal Management Post Consultant Open 16,500.00 0.00 2020-11-15 2020-12-11 2020-12-15 2020-12-23 2021-01-30 Advisors/Consultant (Balkh), Implementation Framework Selection Grade C AF-IDLG-CIP-195928-CS- Component 3: Improve the Individual INDV / AFMIS Technical IT Pending IDA / D4140 Municipal Management Post Consultant Open 16,500.00 0.00 2020-11-20 2020-12-17 2020-12-20 2020-12-29 2021-02-06 Advisors/Consultant Implementation Framework Selection (Kandahar), Grade C AF-IDLG-CIP-195929-CS- Component 3: Improve the Individual INDV / AFMIS Technical IT Pending IDA / D4140 Municipal Management Post Consultant Open 16,500.00 0.00 2020-11-22 2020-12-21 2020-12-24 2020-12-31 2021-02-08 Advisors/Consultant (Khost), Implementation Framework Selection Grade C AF-IDLG-CIP-195930-CS- Component 3: Improve the Individual INDV / AFMIS Technical IT Pending IDA / D4140 Municipal Management Post Consultant Open 16,500.00 0.00 2020-11-27 2020-12-26 2020-12-29 2021-01-05 2021-02-13 Advisors/Consultant Implementation Framework Selection (Nangahar), Grade C AF-IDLG-CIP-195931-CS- Individual Component 1: Rehabilitate INDV / Senior Civil Engineer IDA / D4140 Post Consultant Open 10,000.00 0.00 Canceled 2020-10-25 2020-11-23 2020-11-26 2020-12-02 2021-01-10 Municipal Infrastructure (Kabul), Grade B Selection AF-IDLG-CIP-195933-CS- Individual Component 1: Rehabilitate INDV / Survey Engineer IDA / D4140 Post Consultant Open 10,000.00 0.00 Canceled 2020-10-27 2020-11-25 2020-11-29 2020-12-06 2021-01-14 Municipal Infrastructure (Kabul), Grade C Selection AF-IDLG-CIP-195935-CS- Individual INDV / AFMIS Senior Financial Component 1: Rehabilitate Pending IDA / D4140 Post Consultant Open 16,500.00 0.00 2020-11-26 2020-12-25 2020-12-28 2021-01-05 2021-02-13 Advisors/Consultant Municipal Infrastructure Implementation Selection (Nangrahar), Grade C AF-IDLG-CIP-195936-CS- Component 3: Improve the Individual INDV / AFMIS Senior Financial Pending IDA / D4140 Municipal Management Post Consultant Open 16,500.00 0.00 2020-09-24 2020-10-23 2020-10-26 2020-11-02 2020-12-11 Advisors/Consultant (Herat), Implementation Framework Selection Grade C Page 6 AF-IDLG-CIP-195937-CS- Component 3: Improve the Individual INDV / AFMIS Senior Financial Pending IDA / D4140 Municipal Management Post Consultant Open 16,500.00 0.00 2020-09-24 2020-10-23 2020-10-26 2020-11-02 2020-12-11 Advisors/Consultant (Balkh), Implementation Framework Selection Grade C AF-IDLG-CIP-195939-CS- Component 3: Improve the Individual INDV / AFMIS Senior Financial Pending IDA / D4140 Municipal Management Post Consultant Open 16,500.00 0.00 2020-09-24 2020-10-23 2020-10-26 2020-11-02 2020-12-11 Advisors/Consultant Implementation Framework Selection (Kandahar), Grade C AF-IDLG-CIP-195940-CS- Component 3: Improve the Individual INDV / AFMIS Senior Financial Pending IDA / D4140 Municipal Management Post Consultant Open 16,500.00 0.00 2020-09-24 2020-10-23 2020-10-27 2020-11-02 2020-12-11 Advisors/Consultant (Khost), Implementation Framework Selection Grade C AF-IDLG-CIP-199127-CS- Individual Component 1: Rehabilitate INDV / Senior Civil Engineer IDA / D4140 Post Consultant Limited 10,000.00 0.00 Under Review 2020-11-18 2020-08-23 2020-11-23 2020-12-14 2021-01-18 2021-07-17 Municipal Infrastructure (Kabul), Grade B Selection AF-IDLG-CIP-199129-CS- Individual Component 1: Rehabilitate Under INDV / Senior Civil Engineer IDA / D4140 Post Consultant Limited 10,000.00 0.00 2020-11-24 2020-08-23 2020-11-29 2020-11-08 2020-12-20 2021-01-24 2021-07-23 Municipal Infrastructure Implementation (Kabul), Grade B Selection AF-IDLG-CIP-199130-CS- Individual Component 1: Rehabilitate Pending INDV / Survey Engineer IDA / D4140 Post Consultant Limited 10,000.00 0.00 2020-10-30 2020-11-04 2020-11-25 2020-12-30 2021-06-28 Municipal Infrastructure Implementation (Kabul), Grade C Selection Page 7