Page 1 Procurement Plan B&H Federation of B&H Republic Srpska R Croatia Subcomponent 1.1. Institution and Capacity Building 1.1.a Support and equipment for the river basin management authorities left blank 1.1.a.1 Water management office in Mostar left blank left blank left blank 0 0 0 1.1.a.1.1 Procurement of IT equipment for PIT of FBiH G Sh Prior Sep-09 Oct-09 Oct-09 Nov-09 Dec-09 Contract is finished and paid 1.1.a.2. Water management PIT office in Trebinje left blank 1.1.a.2.1 Procurement of IT equipment for PIT of RS G left blank left blank left blank 0 0 0 Sh Prior Jan-10 Feb-10 Feb-10 Feb-10 Mar-10 Contract is finished and paid 1.1.a.2.2 Procurement of office furniture for PIT of RS G left blank left blank left blank 0 0 0 Sh Prior Dec-09 25.01.2010. Jan-10 Feb-10 Feb-10 Contract is finished and paid 1.1.b Support for operation of ISWC and TWG left blank 1.1.b1.1 Meetings organization TR left blank left blank left blank 0 0 left blank Other Post Feb-11 Dec-11 Estimated amount for 2011: B&H: 24.375 Croatia: 8.125 1.1.b1.2 Study tours TR left blank left blank left blank 0 0 left blank Other Post Feb-11 Dec-11 Estimated amount for 2011: B&H: 24.375 Croatia: 8.125 1.1.c Training on preparation of river basin management plans and implementation of the EU WFD left blank 1.1.c.1 Series of workshops related to the implementation of EU WFD TR left blank left blank left blank 0 0 left blank Other Post May-11 Aug-12 Estimated amount for 2011: B&H: 25.875 Croatia: 8.625 1.1.c.2 Workshops series related to the Water Conflicts and Negotiations Techniques TR left blank left blank left blank 0 0 left blank Other Post May-11 Aug-12 Estimated amount for 2011: B&H: 36.000 Croatia: 12.000 STATUS PROJECT DESCRIPTION Packages Post / Prior I ssue COMPONENT 1: Improved Transboundary Water Resource Management Total Cost estimated in US$ C tr Completed Bids received GEF in US$ Type PROCUREMENT PLAN for Neretva and Trebisnjica Management Project - updated on February 08,2011 Procurement method Item No. GEF Distribution C tr. Signed E valuation 1/10 Page 2 Procurement Plan B&H Federation of B&H Republic Srpska R Croatia STATUS PROJECT DESCRIPTION Packages Post / Prior I ssue Total Cost estimated in US$ C tr Completed Bids received GEF in US$ Type PROCUREMENT PLAN for Neretva and Trebisnjica Management Project - updated on February 08,2011 Procurement method Item No. GEF Distribution C tr. Signed E valuation 1.1.d Design of a set of appropriate regional coordination procedures for transboundary water resource management CS left blank left blank left blank 0 0 left blank IC Post Nov-11 Dec-11 Jan-12 Feb-12 Sep-12 Item 1.1.d will be implemented in 2012. TOR will be prepared by FBIH PIT untill the end of September 2011 1.1.e Identification of necessary additional policy and institutional reforms to facilitate enhanced transboundary management tools CS left blank left blank left blank 0 0 left blank IC Post Nov-11 Dec-11 Jan-12 Feb-12 Sep-12 Item 1.1.e will be implemented in 2012. TOR will be prepared by FBIH PIT untill the end of September 2011 Total 1.1. left blank left blank left blank 0 0 left blank 2/10 Page 3 Procurement Plan B&H Federation of B&H Republic Srpska R Croatia STATUS PROJECT DESCRIPTION Packages Post / Prior I ssue Total Cost estimated in US$ C tr Completed Bids received GEF in US$ Type PROCUREMENT PLAN for Neretva and Trebisnjica Management Project - updated on February 08,2011 Procurement method Item No. GEF Distribution C tr. Signed E valuation Subcomponent 1.2. Measurement, monitoring and information management 1.2.a-1 Technical assistance regarding analyses of equipment and expansion of the existing network of water measurement and monitoring stations CS left blank left blank left blank 0 0 left blank IC Post Mar-11 Apr-11 May-11 Jun-11 Aug-11 TOR is under preparation 1.2.a-2 Monitoring equipment G left blank 0 0 0 0 0 ICB Prior Oct-11 Dec-11 Jan-12 Feb-12 Aug-12 Develop basin-wide water information system including GIS system, equipment and training left blank Sep-10 Oct-10 Feb-11 Feb-11 May-11 Contract Negotiation will be held on February 10,2011 1.2.b-2 Establishment of GIS data foundation for WIS G left blank left blank left blank 0 0 left blank Sh Prior Jul-11 Aug-11 Sep-11 Oct-11 Dec-11 left blank left blank left blank left blank left blank left blank Subcomponent 1.3. River basin management planning 1.3. Preparation of River Basin Management Plan CS left blank left blank left blank 0 0 left blank QCBS Prior Jun-09 Mar-10 Apr-10 Sep-10 Dec-13 Contract is signed on September 30, 2010 by JV: Elektroprojekt Croatia and Zavod za vodoprivredu Bijeljina in amount of: USD 1,294,880.00 - B&H: USD 997,057.60 R CR: USD 297,822.40 left blank left blank 0 0 0 left blank left blank left blank left blank left blank left blank left blank left blank Total 1.3. 0 Prior 0 1.2.b-1 Total 1.2. CQ left blank left blank left blank CS Subtotal COMPONENT 1 3/10 Page 4 Procurement Plan B&H Federation of B&H Republic Srpska R Croatia STATUS PROJECT DESCRIPTION Packages Post / Prior I ssue Total Cost estimated in US$ C tr Completed Bids received GEF in US$ Type PROCUREMENT PLAN for Neretva and Trebisnjica Management Project - updated on February 08,2011 Procurement method Item No. GEF Distribution C tr. Signed E valuation Subcomponent 2.1. Improved management and use of water-dependent ecosystems 2.1.a Improved wetlands management in Hutovo Blato Nature Park left blank left blank 0 left blank 0 0 M 2.1.a-1 Development of a Physical Plan and Management Plan for the "Hutovo Blato" Nature Park CS left blank left blank 0 left blank 0 0 QCBS Prior Mar-11 May-11 Jun-11 Jul-11 Jul-12 1) Draft ToR has been prepared. It should be approved by two cantonal Ministries (MCESP and MMTE) and after that sent for WB No. 2.1.a-2 Monitoring and Biodiversity Inventory for the "Hutovo Blato" Nature Park CS left blank left blank 0 left blank 0 0 CQ Prior Jun-10 Aug-10 Oct-10 Nov-10 Nov-11 Contract has been signed on November 29, 2010 by JV IGH-Mostar, B&H +OIKON Zagreb, RC in the amount of: 50.000 USD. 2.1.a-3 Wastewater Treatment Plant for the Facilities within "Hutovo Blato" Nature Park CS left blank left blank 0 left blank 0 0 IC Prior Feb-11 Mar-11 Mar-11 Mar-11 Jun-11 ToR has been prepared by FPIT. The WB gave comments and sugesstion. The revision of ToR is on-going. 2.1.a-4 Wastewater Treatment Plant for the Facilities within "Hutovo Blato" Nature Park W left blank left blank 0 left blank 0 0 NCB Post Jul-11 Aug-11 Sep-11 Oct-11 Mar-12 2.1.b Improved use of wetlands sites for tourism - eco-trail with information center at Bacina lakes 2.1.b-1 Development of a Bike and Hike Trail around Bacina Lake CS left blank left blank 0 0 0 left blank CQ Post Apr-10 Jun-10 Jun-10 Jul-10 Oct-10 Contract complited - in the preparation annex of contract for Main design for bridge. Lack of funds - 15.300$ should be transferred from poz. 1.3. 2.1.b-2 Construction of a Bike and Hike Trail around Bacina Lake W left blank left blank 0 0 0 left blank NCB Prior May-11 Jun-11 Jul-11 Sep-11 Apr-12 2.1.b-3 Construction of toilet for visitors of Vjetrenica cave W left blank left blank 0 left blank 0 0 NCB Post Mar-11 Apr-11 May-11 Jun-11 Sep-11 The project for construction of toilet has been preparad by Municipality. COMPONENT 2:Improved management and use of wetlands ecosystems 4/10 Page 5 Procurement Plan B&H Federation of B&H Republic Srpska R Croatia STATUS PROJECT DESCRIPTION Packages Post / Prior I ssue Total Cost estimated in US$ C tr Completed Bids received GEF in US$ Type PROCUREMENT PLAN for Neretva and Trebisnjica Management Project - updated on February 08,2011 Procurement method Item No. GEF Distribution C tr. Signed E valuation 2.1.c Increased understanding of values of wetlands and their resources 2.1.c. 1-1 Completion and Display of the Flora and Fauna exhibit within the Museum of Herzegovina-Trebinje CS left blank left blank 0 0 left blank 0 CQ Post Jun-10 Jul-10 Aug-10 Aug-10 Sep-10 Preparation of project documentation of rehabilatation of roof Museum of Herzegovina, contract is signed with PUT INZINJERING 2.1.c. 1-2 Completion and Display of the Flora and Fauna Exhibit Within the Museum of Herzegovina – Trebinje left blank 0 0 left blank 0 Post Sep-10 Oct-10 Nov-10 Nov-10 Jan-11 2.1.c. 1-3 Completion and Display of the Flora and Fauna Exhibit Within the Museum of Herzegovina – Trebinje left blank 0 0 left blank 0 Post Sep-10 Oct-10 Nov-10 Nov-10 Jan-11 2.1.c.2-1 Rehabilitation of the Bird Museum of the Neretva Delta and Educational / Research Center in Metkovic G 0 0 0 0 0 Sh Post This activity will be dropped. Funds are transferred to 2.1.e-3 Irrigation Pilot Project-goods 2.1.c.2-2 Rehabilitation of the Bird Museum of the Neretva Delta and Educational / Research Center in Metkovic W 0 0 0 0 0 NCB Prior This activity will be dropped. Funds are transferred to 2.1.b-2 Construction of a Bike and Hike Trail around Bacina Lake (works) 2.1.d-1 Improved wetlands management in five croatian PAs CS left blank left blank 0 0 0 left blank CQ Prior Jul-09 Sep-09 Oct-09 Dec-09 Dec-10 Contract complited 2.1.d-2 Improved wetlands management in five croatian PAs W left blank left blank 0 0 0 left blank NCB Prior If necessary, funds will be transferred to 2.1.e-2 Irrigation Pilot Project-construction 2.1.e-1 Reduction of salt water intrusion CS 0 0 0 2.1.e-1-1 Level of Salinity and Sustainable Use of Soil in the Lower Neretva Region CS left blank left blank 0 0 0 left blank CQ Prior Jul-09 Sep-09 Oct-09 Dec-09 Feb-11 Ongoing CQ left blank 2.1.c.3. Transboundary Newsletter Promoting Environmental Protection “Naša Neretva” Dec-10 Jul-10 CS left blank 0 Responsibility:Joint activitiy of RC and FB&H.Contract has been signed on December 22, 2010 by Association NGO "Lijepa Naša" B&H+ "Modrozelena zadruga branitelja", RC, in the amount of: FB&H KM 43.010,37 -B&H and KM 36.761,00 -RC Post Aug-10 Oct-10 Dec-13 We agreed the total amount for goods provide to the works and signed the contract with firm for reconstruction roof Museum, contract is signed with HERC GRADNJABAM 79.268,67 left blank W NCB left blank left blank 0 5/10 Page 6 Procurement Plan B&H Federation of B&H Republic Srpska R Croatia STATUS PROJECT DESCRIPTION Packages Post / Prior I ssue Total Cost estimated in US$ C tr Completed Bids received GEF in US$ Type PROCUREMENT PLAN for Neretva and Trebisnjica Management Project - updated on February 08,2011 Procurement method Item No. GEF Distribution C tr. Signed E valuation 2.1.e-1-2 Feasibility Study with Sociological Assessment, Environmental Management Plan, and Preliminary Design for Selected Location of an Irrigation Pilot Project CS left blank left blank 0 0 0 left blank CQ Prior Nov-09 Nov-09 Mar-10 Jun-10 Apr-11 Ongoing 2.1.e-1-3 Environmental Assessment CS left blank left blank 0 0 0 left blank CQ Prior Mar-11 Apr-11 May-11 Jun-11 Aug-11 Lack of funds - 10.000$ should be transferred from poz. 1.3. 2.1.e-1-4 Preparation of detailed designs CS left blank left blank 0 0 0 left blank CQ Prior Mar-11 Apr-11 May-11 Jun-11 Aug-11 Lack of funds - 32.000$ should be transferred from poz. 1.3. 2.1.e-2-1 Irrigation Pilot Project-construction W left blank left blank 0 0 0 left blank NCB Post Sep-11 Oct-11 Nov-11 Dec-11 Jun-13 2.1.e-3-2 Irrigation Pilot Project-goods G left blank left blank 0 0 0 left blank ICB Prior Sep-11 Oct-11 Nov-11 Dec-11 Dec-12 Total 2.1. left blank left blank left blank left blank left blank Subcomponent 2.2. Water management infrastructure 2.2.a-1 Improved water management on the Krupa River within the Hutovo Blato Nature Park G lef blank left blank 0 lef blank 0 0 Sh Prior Apr-11 May-11 Jun-11 Jul-11 Dec-11 2.2.a-2 Improved water management on the Krupa River within the Hutovo Blato Nature Park W lef blank lef blank 0 lef blank 0 0 NCB Post Apr-11 May-11 Jun-11 Jul-11 Dec-11 Total 2.2. lef blank lef blank lef blank lef blank lef blank Subcomponent 2.3. Improved operation of reservoirs, HPPs and dams 2.3.a Conduct a study to determine the minimum environmental flow CS lef blank lef blank 0 lef blank lef blank lef blank QCBS Prior Feb-11 Apr-11 Jun-11 Jul-11 May-12 1)TOR is under preparation 2) Procurement procedure is responsibility of PMT in MOFTER 2.3.b Develop and implement mathematical models for hydrological predictions, HPP operations, forecasting and decision making and prepare a plan, guidelines and training program for optimal management of HPPs multi-purpose reservoirs CS lef blank lef blank lef blank 0 0 lef blank QCBS Prior Jun-11 Aug-11 Oct-11 Nov-11 Nov-12 TOR will be prepred by PIT RS (Minutes from Meeting held on December 1.2010. in MOFTER 2.3.c-1 Establishment of seismological monitoring of the dam Alagovac CS lef blank lef blank 0 0 lef blank 0 IC Post Feb-11 Apr-11 May-11 Jun-11 Jul-11 6/10 Page 7 Procurement Plan B&H Federation of B&H Republic Srpska R Croatia STATUS PROJECT DESCRIPTION Packages Post / Prior I ssue Total Cost estimated in US$ C tr Completed Bids received GEF in US$ Type PROCUREMENT PLAN for Neretva and Trebisnjica Management Project - updated on February 08,2011 Procurement method Item No. GEF Distribution C tr. Signed E valuation 2.3.c-2 Establishment of seizmological monitoring of the dam Alagovac G lef blank lef blank 0 0 lef blank 0 ICB Prior Jun-11 Jul-11 Aug-11 Sep-11 Feb-12 lef blank 0 lef blank 0 lef blank 0 lef blank lef blank lef blank lef blank lef blank left blank Total 2.3. Subtotal COMPONENT 2 7/10 Page 8 Procurement Plan B&H Federation of B&H Republic Srpska R Croatia STATUS PROJECT DESCRIPTION Packages Post / Prior I ssue Total Cost estimated in US$ C tr Completed Bids received GEF in US$ Type PROCUREMENT PLAN for Neretva and Trebisnjica Management Project - updated on February 08,2011 Procurement method Item No. GEF Distribution C tr. Signed E valuation 3.1. Municipal wastewater treatment imrovements 3.1.a Bileca municipality wastewater treatment system W lef t blank left blank 0 0 left blank 0 ICB Prior May-10 Jun-10 Jul-10 Oct-10 Mar-12 Contract signed and ongoing 3.1.a-1 Translation of BoQ Bileca WWTS CS lef t blank left blank 0 0 left blank 0 DC Prior Sep-09 Oct-09 Oct-09 Nov-09 Dec-09 Contract complited 3.1.a-2 Environment Impact Assessment CS left blank left blank 0 0 left blank 0 Post Mar-10 April-10 May-10 May-10 Jun-10 Contract complited 3.1.a-3 Supervision of works on the Construction of the tretmant plant urban area domestic and industrial wastewater CS left blank left blank 0 0 left blank 0 Prior Oct-10 Mar-12 Contract signed and ongoing 3.1.b Konjic municipality wastewater treatment system W left blank left blank 0 left blank 0 0 ICB Prior Sep-11 Oct-11 Nov-11 Dec-11 Dec-12 The main project design for WWTP financed by Municipality has not been completed yet. 3.1.c Ljubuski municipality wastewater treatment system W left blank left blank 0 left blank 0 0 ICB Prior Sep-11 Oct-11 Nov-11 Dec-11 Dec-12 The main project design for recons. and exten. Of WWTP financed by Municipality has not been completed yet. 3.1.e WWTP upgrade in Nevesinje Municipality W left blank left blank 0 left blank 0 NCB Post Apr-11 May-11 Jun-11 Aug-11 Feb-12 3.1.f WWTP upgrade in Trebinje Municipality G left blank left blank 0 0 left blank 0 DC Prior Jul-10 Aug-10 Sep-10 Nov-10 May-11 Contract complited 3.2. Industrial wastewater treatment improvements 3.2.a-1 Upgrade to wastewater treatment system to a metallurgy company in Konjic G left blank left blank 0 left blankt 0 0 ICB Prior Sep-11 Oct-11 Nov-11 Dec-11 Jul-12 The main design financed by beneficary is in final phase. 3.2.a-2 Upgrade to wastewater treatment system to a metallurgy company in Konjic W left blank left blank 0 left blankt 0 0 NCB Prior Sep-11 Oct-11 Nov-11 Dec-11 Jul-12 The main design financed by beneficary is in final phase. Total 3.2. left blank left blank 0 left blank left blank 0 Subcomponent 4.1. Scientific community involvement Total 3.1. COMPONENT 4: Public participation and awareness Subtotal COMPONENT 3 COMPONENT 3: High priority investments for water pollution control 8/10 Page 9 Procurement Plan B&H Federation of B&H Republic Srpska R Croatia STATUS PROJECT DESCRIPTION Packages Post / Prior I ssue Total Cost estimated in US$ C tr Completed Bids received GEF in US$ Type PROCUREMENT PLAN for Neretva and Trebisnjica Management Project - updated on February 08,2011 Procurement method Item No. GEF Distribution C tr. Signed E valuation 4.1.a 3 annual workshops TR left blank left blank 0 left blank left blank left blank OTHER Post Feb-11 Dec-13 Estimated amount for 2011: FB&H: 15.000 RS: 7.500 Croatia: 7.500 4.2.a Training and facilitation for community involvement in RMBP TR left blank left blank 0 left blank left blank left blank CQ Post May-11 Dec-11 Estimated amount for 2011: FB&H: 12.500 RS: 6.250 Croatia: 6.250 4.2.b Support to local NGOs activities - Grants program GR left blank left blank 0 left blank left blank left blank Grant Post Jun-10 Sep-10 4.2.c Support community based demonstration projects GR left blank left blank 0 left blank left blank left blank Grant Post Jun-10 Sep-10 4.3.a Project management staff CS left blank left blank left blank left blank left blank left blank 4.3.a-1 Preparation of Terms of reference for CS Develop and implement mathematical models for hydrological predictions, HPP operations, forecasting and decision making and prepare a plan, guidelines and training program for optimal management of HPPs multi- purpose reservoirs (Item 2.3.b in PP) CS IC Post Apr-11 May-11 May-11 Jun-11 Aug-11 4.3.b Operating costs OC left blank left blank left blank left blank left blank left blank 0 4.4.a Office equipment & vehicles left blank left blank 0 4.4.a.1 Procurement of vehicles G left blank left blank 0 left blank 0 0 Sh Post Dec-2009 Dec-2009 Jan-10 Feb-10 Apr-10 Contract complited 4.4.b Office equipment & vehicles left blank left blank Post Jan-10 Feb-10 Feb-10 Mar-10 Apr-10 4.4.b.1 Procurement of ofice furniture G left blank left blank 0 0 left blank 0 Sh Post Jan-10 Feb-10 Feb-10 Mar-10 Apr-10 Contract complited 4.4.c Office equipment & vehicles G left blank left blank 0 0 0 left blank Sh Post Mar-11 Mar-11 Apr-11 May-11 Jul-11 CS Subcomponent 4.2. Civil society participation Subcomponent 4.3. Project Management Subcomponent 4.5. Audit of the Project (included in 4.3.a) 9/10 Page 10 Procurement Plan B&H Federation of B&H Republic Srpska R Croatia STATUS PROJECT DESCRIPTION Packages Post / Prior I ssue Total Cost estimated in US$ C tr Completed Bids received GEF in US$ Type PROCUREMENT PLAN for Neretva and Trebisnjica Management Project - updated on February 08,2011 Procurement method Item No. GEF Distribution C tr. Signed E valuation left blank left blank left blank left blank left blank left blank left blank left blank left blank left blank left blank procurement ongoing contract signed left blank left blank contract complited Total Subtotal COMPONENT 4 10/10