Page 1 i Restructuring Status: Archived Restructuring Type: Level two Last modified on date : 02/02/2011 1. Basic Information Project ID & Name P090666 : ECSEE APL3 - BiH Country Bosnia and Herzegovina Task Team Leader Mohinder P. Gulati Sector Manager/Director Ranjit J. Lamech Country Director Jane Armitage Original Board Approval Date 06/16/2006 Original Closing Date: 12/31/2010 Current Closing Date 06/30/2012 Proposed Closing Date [if applicable] EA Category B - Partial Assessment Revised EA Category B - Partial Assessment - Partial Assessment EA Completion Date 03/24/2006 Revised EA Completion Date 2. Revised Financing Plan (US$ m ) Source Original Revised BORR 8.64 8.64 EBRD 66.98 66.98 EUIB 115.90 115.90 IDA 36.00 36.00 KFW 44.89 44.89 Total 272.41 272.41 3. Borrower Organization Department Location Bosnia and Herzegovina Bosnia and Herzegovina 4. Implementing Agency Organization Department Location Page 2 ii 5. Disbursement Estimates (US$m) Actual amount disbursed as of 02/08/2011 18.80 Fiscal Year Annual Cumulative 2011 0.00 18.80 Total 18.80 6 . Policy Exceptions and Safeguard Policies Does the restructured project require any exceptions to Bank policies? N Does the restructured projects trigger any new safeguard policies? If yes, please select from the checklist below and update ISDS accordingly before submitting the package. N 7a. Project Development Objectives/Outcomes Original/Current Project Development Objectives/Outcomes The countries of South East Europe, including Bosnia and Herzegovina, and the European Commission are cooperating to develop a regional energy market, the Energy Community of South East Europe (ECSEE) and integrate it into the internal energy market of the European Union. The objective of the project is to facilitate BiH's participation in ECSEE through investments to: (i) improve dam safety; (ii) reduce adverse environmental impacts at thermal power stations; (iii) replace ageing existing facilities and equipment at hydropower and thermal power stations; (iv) rehabilitate distribution systems and introduce distribution Supervisory Control and Data Acquisition (SCADA) systems, (v) establish a market operation system, (vi) provide hardware and software to im prove the financial management information systems of the Elektroprivredas; and through technical assistance to facilitate project implementation, and determine the best way to reduce sulfur dioxide and nitrogen oxide emissions at a power plant. 7b. Revised Project Development Objectives/Outcomes [ if applicable]