6-Months Procurement Plan for OGSTEP PPA General: Project Information:. OGUN STATE ECONOMIC TRANSFORMATION PROJECT (OGSTEP) Project Implementation Agency: UNDER THE SUPERVISION OF MINISTRY OF BUDGET AND PLANNING Date of the Procurement Plan: June 16, 2020 Period covered by this Procurement Plan: April to September 2020 I. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers”, July 2016 (Revised November 2017) (“Procurement Regulations”), the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. II. Bank’s Standard Procurement Documents: The Bank’s Standard Procurement Documents shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. III. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Nigeria Public Procurement Act 2007 and the Regulations, 2016, such arrangements shall be subject to paragraph 5.3 and 5.4 of the Procurement Regulations and the following conditions: o There should be no mandatory requirements for inclusion of local experts and firms for the consulting assignments; o There should be no exclusive preference based on threshold prescribed in PPA and credit and its Regulations; o Negotiations with the lowest evaluated bidder to reduce price in the case of goods, works and non-consulting services where competitive methods have been used shall not be allowed; 1 o The fixed budget method shall not be used for goods, works and non- consulting services; o Established and approved procurement standards by the government may be used, provided that they are not restrictive When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. In accordance with paragraph 5.4(c) and 5.5 of the Procurement Regulations, the request for bids/request for proposals/request for quotations document shall require that Bidders/Proposers submitting Bids/Proposals/quotations present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. The form of the Letter of Acceptance is attached in Appendix 1. IV. Prequalification: Applicable (May be applicable at the Federal for high value Consultant Assignments V. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable VI. Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations: Not Applicable VII. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Not Applicable Domestic preference is not applicable for National Open Competitive Procurement VIII. Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is: Not Applicable IX. Other Relevant Procurement Information: Not Applicable 2 3 X. Threshold for Prior Review, Procurement Approaches and Methods – Goods, Works and Non- Consulting Services Procurement Approaches and Methods (US$ millions) Category Open Open National Request for Quotation International (RfQ) Works, Turnkey, and ≥5 <5 ≤ 0.2 S&I of Plant and Equipment Goods, IT, and non- ≥5 <0.5 ≤ 0.1 consulting services Post Review: All contracts not subject to prior review shall be subject to post review. XI. Summary of the procurement packages for Goods, Works and Non-Consulting Services: S Contract Implem Estimate Revie Market Selecti Evaluati Procurem Prequ Domest Expect Expect r. Description enting d Cost w by Approa on on ent alifica ic ed ed N Agency (US$) Bank ch Metho Options Process tion Prefere date date of o (Prior (Open- d (Most (Single (Yes/ nce of bid/ Contra / Nationa (RFP, Advanta stage- No) (Yes/No propos ct Post) l/ RFB, geous single ) al Signat Limited RFQ, Bid, envelope openin ure etc.) DS BAFO, etc.) g etc.) Rated Criteria etc.) GOODS 1 Procurement of OGSTEP 61,508.33 Post Limited RFQ Most Single No No 20-06- 20-06-25 laptops, Advanta stage- 04 modems, ext geous single HDD, USB Bid envelope drives, modems, desktops, software, UPS and stabilizers, Color LaserJet printers, 4 S Contract Implem Estimate Revie Market Selecti Evaluati Procurem Prequ Domest Expect Expect r. Description enting d Cost w by Approa on on ent alifica ic ed ed N Agency (US$) Bank ch Metho Options Process tion Prefere date date of o (Prior (Open- d (Most (Single (Yes/ nce of bid/ Contra / Nationa (RFP, Advanta stage- No) (Yes/No propos ct Post) l/ RFB, geous single ) al Signat Limited RFQ, Bid, envelope openin ure etc.) DS BAFO, etc.) g etc.) Rated Criteria etc.) LaserJet printers, muti- media projectors with screen, Photocopiers, Electronic Interactive Boards, Android tablets 2 Procurement of OGSTEP 8,083.33 Post Limited RFQ Most Single No No 20-07- 20-08-03 4 No. 1.5HP Advanta stage- 13 split unit air geous single conditioners, 6 Bid envelope No. 2Tons standing air conditioners, 5 No. fridge, 4 No. Standing fan 3 Televisions, OGSTEP 26,888.89 Post Limited RFQ Most Single No No 20-07- 20-08-10 Satellite Advanta stage- 20 Television geous single decoder (DSTV Bid envelope or its equivalent) plus installation and 6 months subscription, PABX - Inter- comm for the one floor, CCTV - Securtity 5 S Contract Implem Estimate Revie Market Selecti Evaluati Procurem Prequ Domest Expect Expect r. Description enting d Cost w by Approa on on ent alifica ic ed ed N Agency (US$) Bank ch Metho Options Process tion Prefere date date of o (Prior (Open- d (Most (Single (Yes/ nce of bid/ Contra / Nationa (RFP, Advanta stage- No) (Yes/No propos ct Post) l/ RFB, geous single ) al Signat Limited RFQ, Bid, envelope openin ure etc.) DS BAFO, etc.) g etc.) Rated Criteria etc.) Camera + installation, Internet Services, virtual meeting platform 4 Procurement of OGSTEP 27,777.78 Post Limited RFQ Most Single No No 20-06- 20-06-23 1no 100KVA Advanta stage- 02 Diesel geous single Generator Bid envelope (super silent) for PIU 5 Procurement of OGSTEP 277777.7 Post Limited RFQ Most Single No No 20-06- 20-06-23 4no Project 8 Advanta stage- 02 Vehicles 8no geous single 4x4 wheel Bid envelope drive (1PIU, 1 AGRIC, 2 BEE&IPA) 6 Procurement of OGSTEP 40,541.67 Post Limited RFQ Most Single No No 20-08- 20-08-24 office furniture Advanta stage- 03 for PIU and geous single other sectors Bid envelope 7 *Procurement OGSTEP 10,000 Post Limited DIR BAFO Single No No 20-07- 20-08-10 of IPA E- stage- 27 Learning tool single (single source) envelope 8 *Procurement OGSTEP 6,000 Post Limited DIR BAFO Single No No 20-08- 20-08-26 of CRM (single stage- 05 source) and single training envelope 9 Procure OGSTEP 21,311.47 Post Limited RFQ Most Single No No 20-07- 20-08-03 storage Advanta stage- 13 6 S Contract Implem Estimate Revie Market Selecti Evaluati Procurem Prequ Domest Expect Expect r. Description enting d Cost w by Approa on on ent alifica ic ed ed N Agency (US$) Bank ch Metho Options Process tion Prefere date date of o (Prior (Open- d (Most (Single (Yes/ nce of bid/ Contra / Nationa (RFP, Advanta stage- No) (Yes/No propos ct Post) l/ RFB, geous single ) al Signat Limited RFQ, Bid, envelope openin ure etc.) DS BAFO, etc.) g etc.) Rated Criteria etc.) solutions for geous single Deeds & Lands Bid envelope Registry and Archives Records 1 Upgrade of IT OGSTEP 20,582.24 Post Limited RFQ Most Single No No 20-07- 20-08-10 0 infrastructure Advanta stage- 20 in Budget and geous single Planning Bid envelope 1 Printing of IPA OGSTEP 1,315.79 Post Limited RFQ Most Single No No 20-08- 20-09-09 1 Law Advanta stage- 19 geous single Bid envelope 1 Production of OGSTEP 49,180.33 Post Limited RFQ Most Single No No 20-08- 20-09-11 2 revised Rules & Advanta stage- 28 Regulations for geous single BLS Bid envelope Total Goods 550,967 .61 *These two were merged into a package before, but because it has now become very clear that they cannot be executed at the same time, I had to separate them. WORKS Total works NON-CONSULTING SERVICES 7 S Contract Implem Estimate Revie Market Selecti Evaluati Procurem Prequ Domest Expect Expect r. Description enting d Cost w by Approa on on ent alifica ic ed ed N Agency (US$) Bank ch Metho Options Process tion Prefere date date of o (Prior (Open- d (Most (Single (Yes/ nce of bid/ Contra / Nationa (RFP, Advanta stage- No) (Yes/No propos ct Post) l/ RFB, geous single ) al Signat Limited RFQ, Bid, envelope openin ure etc.) DS BAFO, etc.) g etc.) Rated Criteria etc.) Note: Based on Liberia’s specific needs and circumstances, shopping threshold for the purchase of vehicles and fuel may be increased up to US$500,000. Thresholds for Prior Review, Selection Approaches and Methods – Consulting Services Category Prior Review Short List of National Consultants (US$ millions) Consulting Engineering and Construction Supervision Services Consultants (Firms) ≥ 0.5 ≤ 0.1 ≤ 0.2 Individual Consultants ≥ 0.2 n.a. n.a. Note: Consultancy services estimated to cost equivalent to US$ 300,000 and above per contract shall be advertised in the United Nations Development Business (UNDB) online in addition to advertising in national newspaper(s) of wide circulation and/or regional newspaper. XI. Summary of the procurement packages for Consulting Services -Planned for the first 18 months after project effectiveness): Sr. Contract Implem Estimate Revie Market Selection Shortlisti Expected Expected No Description enting d Cost w by Approach Method ng date of bid/ date of Agency (US$) Bank (Open - (QCBS, FBS, (Yes/ No) proposal Contract (Prior/ International LCBS, QBS, opening Signature Post) / National/ CQS, DS etc.) etc.) 8 Sr. Contract Implem Estimate Revie Market Selection Shortlisti Expected Expected No Description enting d Cost w by Approach Method ng date of bid/ date of Agency (US$) Bank (Open - (QCBS, FBS, (Yes/ No) proposal Contract (Prior/ International LCBS, QBS, opening Signature Post) / National/ CQS, DS etc.) etc.) 1 MTEF Preparation OGSTEP 40,131.58 Post Open National LCBS YES 20-08-11 20-09-15 including data gathering and validation, current state assessment, sectorial stakeholder consultation, framework design and a validation workshop 2 Design, hosting OGSTEP 26,315.79 Post Limited INDV No 20-08-10 20-09-15 and maintenance of OGSTEP website and mobile application 3 Conduct of OGSTEP 104,955.2 Post Open National CQS Yes 20-05-27 20-06-24 baseline study, 6 needs assessment and foundation skills for STEM teachers 4 Consultancy on OGSTEP 27,631.58 Post Open National LCBS Yes 20-10-28 21-01-04 assessment for the rehabilitation of Technical Colleges 5 Feasibility studies OGSTEP 91,313.42 Post Open National LCBS Yes 20-05-27 20-06-24 and baseline survey for non- formal and traditional apprenticeship Development program 6 Assessment of OGSTEP 83,947.37 Post Open National LCBS Yes 20-10-02 21-01-09 EMIS at State, LGA and school level and improved 9 Sr. Contract Implem Estimate Revie Market Selection Shortlisti Expected Expected No Description enting d Cost w by Approach Method ng date of bid/ date of Agency (US$) Bank (Open - (QCBS, FBS, (Yes/ No) proposal Contract (Prior/ International LCBS, QBS, opening Signature Post) / National/ CQS, DS etc.) etc.) design outline 7 Recruitment of OGSTEP 42,174.30 Post Open National CQS Yes 20-09-30 20-11-20 Business Environment Expert Consultant to conduct process maps and roadmaps 8 Recruitment of OGSTEP 53,846.43 Post Open National CQS Yes 20-09-16 20-11-06 Consultant to create regulatory framework for OGBEC/BES 9 Engagement of OGSTEP 121,393.4 Post Open National LCBS Yes 20-03-19 20-05-08 Consultant to 5 Conduct Benchmarking Exercise 10 Engagement of OGSTEP 23,809.54 Post Open National LCBS Yes 20-10-14 21-01-22 Consultant for the Capacity building of staff (Ministry of Industry, Trade & Investment and OgunInvest) 11 Recruitment of OGSTEP 8,084.13 Post Open National INDV Yes 20-08-18 20-09-29 Ogun Invest Board trainer, Delivery of training to Ogun Invest Board 12 Technical Training OGSTEP 7,000 Post Open National INDV Yes 20-07-13 20-08-31 for OgunInvest - Business and Investment Research & Reporting and Industry value chain analysis 10 Sr. Contract Implem Estimate Revie Market Selection Shortlisti Expected Expected No Description enting d Cost w by Approach Method ng date of bid/ date of Agency (US$) Bank (Open - (QCBS, FBS, (Yes/ No) proposal Contract (Prior/ International LCBS, QBS, opening Signature Post) / National/ CQS, DS etc.) etc.) 13 Recruit and OGSTEP 24,584.13 Post Open National INDV Yes 20-09-01 20-10-13 appoint Baseline Survey Consultant 14 Recruitment of OGSTEP 34,961.19 Post Open National INDV Yes 20-08-28 20-10-09 Legal Policy Consultant 15 Recruitment of OGSTEP 18,568 Post Open National INDV Yes 20-07-18 20-08-29 Physical Planning Law review consultant 16 Diagnostic Lands OGSTEP 84,142 Post Open National LCBS Yes 20-09-30 21-01-08 Compensation & Analysis, Review, of Current Land Administration/Pro cess Flow, Current Cost, Recommendation and Implementation of Improved Land Administration 17 Review of Current OGSTEP 36,494 Post Open National INDV Yes 20-07-25 20-09-07 Survey Administration/Pro cess Flow, Current Cost, Recommendation and Implementation of Improved Land Administration 18 Assessment of OGSTEP 52,174 Post Open National LCBS Yes 20-09-28 21-01-05 existing gaps and areas of potential improvement in the investment legal & regulatory 11 Sr. Contract Implem Estimate Revie Market Selection Shortlisti Expected Expected No Description enting d Cost w by Approach Method ng date of bid/ date of Agency (US$) Bank (Open - (QCBS, FBS, (Yes/ No) proposal Contract (Prior/ International LCBS, QBS, opening Signature Post) / National/ CQS, DS etc.) etc.) framework 19 Sector Scan OGSTEP 9,000 Post Open National INDV Yes 20-10-07 20-11-13 Validation 20 Analysis of growth OGSTEP 49,000 Post Open National INDV Yes 20-10-05 20-11-11 potential and investment landscape in key economic sectors 21 Recruitment of OGSTEP 52,174.30 Post Open National INDV Yes 20-07-20 20-08-31 Communication Strategy Consultant for IPA 22 Transaction OGSTEP 190,300.0 Prior Open National CQS Yes 20-11-03 20-12-28 Advisor to prepare 0 competitive selection of private industrial development and management 23 Farm & farmers OGSTEP 94,736.84 Post Open National CQS Yes 20-07-21 20-09-10 registration, including Geo- tagging using digital tools & database development 24 Engagement of OGSTEP 47,368.42 Post Open National CQS Yes 20-07-23 20-09-15 Consultant for In- depth analysis of priority value chains 25 Engagement of OGSTEP 47,368.42 Post Open National CQS Yes 20-07-24 20-09-16 Consultant for Verification for Agric. Clusters, Roads Etc 26 Engagement of OGSTEP 94,736.84 Post Open National LCBS Yes 20-09-28 21-01-05 Consultant for 12 Sr. Contract Implem Estimate Revie Market Selection Shortlisti Expected Expected No Description enting d Cost w by Approach Method ng date of bid/ date of Agency (US$) Bank (Open - (QCBS, FBS, (Yes/ No) proposal Contract (Prior/ International LCBS, QBS, opening Signature Post) / National/ CQS, DS etc.) etc.) Baseline Studies - Agric 27 Engagement of OGSTEP 9,210.53 Post Open National LCBS Yes 20-10-23 21-01-05 External Auditor 28 Engagement of OGSTEP 47,368.42 Post Open National INDV Yes 20-05-04 20-06-09 key project staff / Consultants (PIU) - Environmental Safeguard Specialist 29 Engagement of OGSTEP 31,578.95 Post Open National INDV Yes 20-05-04 20-06-09 key project staff / Consultants (PIU) - Social Safeguard Specialist 30 Engagement of OGSTEP 31,578.95 Post Open National INDV Yes 20-05-04 20-06-09 key project staff / Consultants (PIU) - Gender Specialist 31 Engagement of OGSTEP 31,578.95 Post Open National INDV Yes 20-05-04 20-06-09 key project staff / Consultants (PIU) - Procurement Specialist 32 Engagement of OGSTEP 31,578.95 Post Open National INDV Yes 20-05-04 20-06-09 key project staff / Consultants (PIU) - M&E Specialist 33 Engagement of OGSTEP 31,578.95 Post Open National INDV Yes 20-05-04 20-06-09 key project staff / Consultants (Agric – Sector Technical Team) - Agribusiness Specialist - Senior level 34 Engagement of OGSTEP 31,578.95 Post Open National INDV Yes 20-05-04 20-06-09 key project staff / 13 Sr. Contract Implem Estimate Revie Market Selection Shortlisti Expected Expected No Description enting d Cost w by Approach Method ng date of bid/ date of Agency (US$) Bank (Open - (QCBS, FBS, (Yes/ No) proposal Contract (Prior/ International LCBS, QBS, opening Signature Post) / National/ CQS, DS etc.) etc.) Consultants (Agric – Sector Technical Team) - Environmental Specialist 35 Engagement of OGSTEP 31,578.95 Post Open National INDV Yes 20-05-04 20-06-09 key project staff / Consultants (Agric – Sector Technical Team) - Social Specialist 36 Engagement of OGSTEP 47,368.42 Post Open National INDV Yes 20-05-04 20-06-09 key project staff / Consultants (Agric – Sector Technical Team) - FRILIA Specialist (FIRM) 37 Engagement of OGSTEP 31,578.95 Post Open National INDV Yes 20-05-04 20-06-09 key project staff / Consultants (Skills Development – Sector Technical Team) - Skills Development Specialist 38 Engagement of OGSTEP 31,578.95 Post Open National INDV Yes 20-05-04 20-06-09 key project staff / Consultants (Skills Development – Sector Technical Team) - TVET Specialist 39 Engagement of OGSTEP 31,578.95 Post Open National INDV Yes 20-05-04 20-06-09 key project staff / Consultants (Business Environment – Sector Technical 14 Sr. Contract Implem Estimate Revie Market Selection Shortlisti Expected Expected No Description enting d Cost w by Approach Method ng date of bid/ date of Agency (US$) Bank (Open - (QCBS, FBS, (Yes/ No) proposal Contract (Prior/ International LCBS, QBS, opening Signature Post) / National/ CQS, DS etc.) etc.) Team) - Industrial Estate Specialist 40 Engagement of OGSTEP 47,368.42 Post Open National CQS Yes 20-05-04 20-06-09 key project staff / Consultants (Business Environment – Sector Technical Team) - Business Environment Specialist (FIRM) 41 Engagement of OGSTEP 47,368.42 Post Open National CQS Yes 20-05-04 20-06-09 key project staff / Consultants (Business Environment – Sector Technical Team) - Consultant for the assessment of the Survey Department (FIRM) 42 Engagement of OGSTEP 61,666.67 Post Open National CQS Yes 20-09-16 20-11-06 Value Chain Development Firms (VCDF) - AGRIC 43 Engagement of OGSTEP 5,263.00 Post Open National INDV Yes 20-09-07 20-10-19 Media consultant for the production of Jingles on Radio and TV, Interviews - AGRIC 44 Engagement of OGSTEP 29,000.00 Post Open National INDV Yes 20-08-31 20-10-20 Consultant for Investor expansion survey 45 Deep dives OGSTEP 20,000.00 Post Open National INDV Yes 20-08-22 20-10-03 15 Sr. Contract Implem Estimate Revie Market Selection Shortlisti Expected Expected No Description enting d Cost w by Approach Method ng date of bid/ date of Agency (US$) Bank (Open - (QCBS, FBS, (Yes/ No) proposal Contract (Prior/ International LCBS, QBS, opening Signature Post) / National/ CQS, DS etc.) etc.) Total 2,096,61 4.37 16 Appendix 1 Letter of Acceptance of the World Bank’s Anti-Corruption Guidelines and Sanctions Framework Date: Invitation of Bids/Proposals No.__________ To: ___________________________________________________________________________ We, along with our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not) consultants and personnel, acknowledge and agree to abide by the World Bank’s policy regarding Fraud and Corruption (corrupt, fraudulent, collusive, coercive, and obstructive practices), as set out and defined in the World Bank’s Anti-Corruption Guidelines1 in connection with the procurement and execution of the contract (in case of award), including any amendments thereto. We declare and warrant that we, along our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not), consultants and personnel, , are not subject to, and are not controlled by any entity or individual that is subject to, a temporary suspension, early temporary suspension, or debarment imposed by a member of the World Bank Group, including, inter alia, a cross-debarment imposed by the World Bank Group as agreed with other international financial institutions (including multilateral development banks), or through the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement. Further, we are not ineligible under the laws or official regulations of [Insert name of Employer as per bidding document] or pursuant to a decision of the United Nations Security Council. We confirm our understanding of the consequences of not complying with the World Bank’s Anti-Corruption Guidelines, which may include the following: a. rejection of our Proposal/Bid for award of contract; b. in the case of award, termination of the contract, without prejudice to any other remedy for breach of contract; and c. sanctions, pursuant to the Bank’s Anti-corruption Guidelines and in accordance with its prevailing sanctions policies and procedures as set forth in the Bank’s Sanctions Framework. This may include a public declaration of ineligibility, either indefinitely or for a stated period of time, (i) to be awarded or otherwise benefit from a Bank- financed contract, financially or in any other manner;2 (ii) to be a nominated3 sub- 1Guidelines on Preventing and Combating Fraud and Corruption in Projects Financed by International Bank for Reconstruction and Development Loans and the International Development Agency Credits and Grants, dated October 15, 2006, and revised in January 2011 and July 2016, as they may be revised from time to time. 2 For the avoidance of doubt, a sanctioned party’s ineligibility to be awarded a contract shall include, without limitation, (i) applying for pre-qualification, expressing interest in a consultancy, and bidding, either directly or as a nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider, in respect of such contract, and (ii) entering into an addendum or amendment introducing a material modification to any existing contract. 17 contractor, consultant, manufacturer or supplier, or service provider of an otherwise eligible firm being awarded a Bank-financed contract; and (iii) to receive the proceeds of any loan made by the Bank or otherwise to participate further in the preparation or implementation of any Bank-financed project. We understand that we may be declared ineligible as set out above upon: a. completion of World Bank Group sanctions proceedings according to its prevailing sanctions procedures; b. cross-debarment as agreed with other international financial institutions (including multilateral development banks); c. the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement; or d. temporary suspension or early temporary suspension in connection with an ongoing World Bank Group sanctions proceeding. For avoidance of doubt, the foregoing effects of ineligibility do not extend to a sanctioned firm’s or individual’s execution of its ongoing Bank-financed contracts (or its ongoing sub-agreements under such contracts) that are not the subject of a material modification, as determined by the Bank. We shall permit, and shall cause our sub-contractors, sub-consultants, agents (whether declared or not), personnel, consultants, service providers or suppliers, to permit the Bank to inspect4 all accounts, records, and other documents relating to the procurement process and/or contract execution (in the case of award), and to have them audited by auditors appointed by the Bank. We agree to preserve all accounts, records, and other documents (whether in hard copy or electronic format) related to the procurement and execution of the contract. Name of the Bidder/Consultant: Name of the person duly authorized to sign the Bid/Proposal on behalf of the Bidder/Consultant: 3 A nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider (different names are used depending on the particular bidding document) is one which has been: (i) included by the bidder in its pre-qualification application or bid because it brings specific and critical experience and know-how that allow the bidder to meet the qualification requirements for the particular bid; or (ii) appointed by the Borrower. 4 Inspections in this context are usually investigative (i.e., forensic) in nature: they involve fact-finding activities undertaken by the Bank or persons appointed by the Bank to address specific matters related to investigations/audits, such as evaluating the veracity of an allegation of possible Fraud and Corruption, through the appropriate mechanisms. Such activity includes but is not limited to accessing and examining a firm's or individual's financial records and information, and making copies thereof as relevant; accessing and examining any other documents, data, and information (whether in hard copy or electronic format) deemed relevant for the investigation/audit, and making copies thereof as relevant; interviewing staff and other relevant individuals; performing physical inspections and site visits; and obtaining third-party verification of information. 18 Title of the person signing the Letter: 19 PROCUREMENT Nigeria : Ogun State Economic Transformation Project PLAN General Information Country: Nigeria Bank’s Approval Date of the Original Procurement Plan: 2020-06-23 2021-10-18 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P164031 GPN Date: Project Name: Ogun State Economic Transformation Project Loan / Credit No: IDA / V1860, IDA / 65240 OGSTEP Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual OG/GO/PPA/02/2020 / Procurement of Office Strengthening the capacity of equipment - 4 No. 1.5HP Pending the government to implement Request for Single Stage - One split unit air conditioners, 6 IDA / V1860 Post Limited 8,083.33 0.00 Implementati 2020-06-27 2020-08-22 2021-02-18 the State’s economic Quotations Envelope No. 2Tons standing air on transformation agenda conditioners, 5 No. fridge, 4 No. Standing fan OG/GO/PPA/03/2020 / Procurement of 7 No. Televisions, 2 No. Satelite Television decoder (DSTV or Strengthening the capacity of its equivalent) plus Pending the government to implement Request for Single Stage - One installation and 6 months IDA / V1860 Post Limited 26,888.89 0.00 Implementati 2020-07-04 2020-08-29 2021-02-25 the State’s economic Quotations Envelope subscription, PABX - Inter- on transformation agenda comm for one floor, CCTV - Securtity Camera + installation, Internet Services, virtual meeting platform OG/GO/PPA/06/2020 / Strengthening the capacity of Pending Procurement of office the government to implement Request for Single Stage - One IDA / V1860 Post Limited 40,541.67 0.00 Implementati 2020-07-18 2020-09-12 2021-03-11 furniture for PIU and other the State’s economic Quotations Envelope on sectors transformation agenda Results based financing to OG/GO/PPA/09/2020 / improve the business- Pending Procure storage solutions for enabling environment and Request for Single Stage - One IDA / V1860 Post Limited 21,311.47 0.00 Implementati 2020-06-29 2020-08-24 2021-02-20 Deeds & Lands Registry and foster private sector Quotations Envelope on Archives Records participation in the agri-f ood and skills sectors Strengthening the capacity of OG/GO/PPA/10/2020 / Pending the government to implement Request for Single Stage - One Upgrade of IT infrastructure in IDA / V1860 Post Limited 20,582.24 0.00 Implementati 2020-07-06 2020-08-31 2021-02-27 the State’s economic Quotations Envelope Budget and Planning on transformation agenda Results based financing to improve the business- Pending OG/GO/PPA/11/2020 / enabling environment and Request for Single Stage - One IDA / V1860 Post Limited 1,315.79 0.00 Implementati 2020-08-05 2020-09-30 2021-03-29 Printing of IPA Law foster private sector Quotations Envelope on participation in the agri-f ood and skills sectors Results based financing to improve the business- OG/GO/PPA/12/2020 / Pending enabling environment and Request for Single Stage - One Production of revised Rules & IDA / V1860 Post Limited 49,180.33 0.00 Implementati 2020-08-15 2020-10-10 2021-04-08 foster private sector Quotations Envelope Regulations for BLS on participation in the agri-f ood and skills sectors Results based financing to improve the business- OG/GO/PPA/08/2020 / Under enabling environment and Procurement of CRM (single IDA / V1860 Post Direct Selection Direct 6,000.00 0.00 Implementati 2020-07-29 2020-06-04 2020-08-03 2020-09-04 2020-09-07 2021-03-06 foster private sector source) and hands-on training on participation in the agri-f ood and skills sectors Results based financing to improve the business- OG/GO/PPA/07/2020 / Pending enabling environment and Procurement of IPA E- IDA / V1860 Post Direct Selection Direct 10,000.00 0.00 Implementati 2020-07-20 2020-07-25 2020-08-29 2021-02-25 foster private sector Learning tool (single source) on participation in the agri-f ood and skills sectors OG/GO/SDS/02/2021 / Supply, install and Results based financing to commissioning of EMIS improve the business- Pending equipment including capacity enabling environment and Single Stage - One IDA / 65240 Post Request for Bids Limited 1,100,000.00 0.00 Implementati 2021-08-29 2021-09-03 2021-10-15 2021-11-14 2021-12-19 2022-06-17 building on EMIS (Including foster private sector Envelope on equipment for EMIS system participation in the agri-f ood servers laptops hubs network and skills sectors devices etc NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Results based financing to OG/NC/PIU/01/2021 / improve the business- Pending Procurement of Flexible enabling environment and Request for Single Stage - One IDA / 65240 Post Limited 40,000.00 0.00 Implementati 2021-08-24 2021-10-08 2022-04-06 Accounting Software for foster private sector Quotations Envelope on Project Financial Management participation in the agri-f ood and skills sectors Page 1 CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual OG/CS/PPA/01/2020 / MTEF Preparation includng data gathering and validation, Strengthening the capacity of Consultant current state assessment, the government to implement Pending IDA / V1860 Post Qualification Limited 40,131.58 0.00 2020-06-28 2020-07-12 2020-08-11 2020-09-15 2021-03-14 sectorial stakeholder the State’s economic Implementation Selection consultantion, framework transformation agenda design and a validation workshop OG/CS/PPA/04/2020 / Strengthening the capacity of Consultancy on assessment the government to implement Least Cost Pending IDA / V1860 Post Open - National 27,631.58 0.00 2020-07-27 2020-08-17 2020-09-30 2020-10-28 2020-11-27 2021-01-01 2021-02-05 2021-08-04 for the rehabilitation of the State’s economic Selection Implementation Technical Colleges transformation agenda OG/CS/PPA/06/2020 / Strengthening the capacity of Assessment of EMIS at State, the government to implement Least Cost Under IDA / V1860 Post Open - National 83,947.37 0.00 2020-06-30 2020-07-20 2020-07-21 2020-09-02 2020-09-03 2021-04-15 2020-10-01 2020-10-31 2020-12-05 2021-01-09 2021-07-08 LGA and school level and the State’s economic Selection Implementation improved design outline transformation agenda Results based financing to OG/CS/PPA/07/2020 / improve the business- Recruitment of Business Consultant enabling environment and Under Environment Expert to IDA / V1860 Post Qualification Open - National 42,174.30 0.00 2020-07-13 2020-07-20 2020-08-03 2020-09-02 2020-09-16 2020-06-16 2020-10-16 2020-11-20 2021-05-19 foster private sector Implementation conduct process maps and Selection participation in the agri-f ood roadmaps and skills sectors Results based financing to OG/CS/PPA/08/2020 / improve the business- Consultant Recruitment of Consultant to enabling environment and Under IDA / V1860 Post Qualification Open - National 53,846.43 0.00 2020-06-29 2020-07-20 2020-07-20 2020-09-02 2020-09-02 2020-10-02 2020-11-06 2021-05-05 create regulatory framework foster private sector Implementation Selection for OGBEC/BES participation in the agri-f ood and skills sectors Results based financing to OG/CS/PPA/10/2020 / improve the business- Engagement of Consultant for enabling environment and Least Cost Pending the Capacity building of staff IDA / V1860 Post Open - National 23,809.54 0.00 2020-07-13 2020-08-03 2020-09-16 2020-10-14 2020-11-13 2020-12-18 2021-01-22 2021-07-21 foster private sector Selection Implementation (Ministry of Industry, Trade & participation in the agri-f ood Investment and OgunInvest) and skills sectors OG/CS/PPA/16/2020 / Diagnostic Lands Results based financing to Compensation & Analysis, improve the business- Review, of Current Land enabling environment and Least Cost Under Administration/Process Flow, IDA / V1860 Post Open - National 84,141.52 0.00 2020-06-29 2020-07-20 2020-07-20 2020-09-02 2020-09-30 2020-10-30 2020-12-04 2021-01-08 2021-07-07 foster private sector Selection Implementation Current Cost, participation in the agri-f ood Recommendation and and skills sectors Implementation of Improved Land Administration OG/CS/PPA/18/2020 / Results based financing to Assessment of existing gaps improve the business- and areas of potential enabling environment and Least Cost Pending IDA / V1860 Post Open - National 52,174.30 0.00 2020-06-26 2020-07-17 2020-08-30 2020-09-27 2020-10-27 2020-12-01 2021-01-05 2021-07-04 improvement in the foster private sector Selection Implementation investment legal & regulatory participation in the agri-f ood framework and skills sectors Results based financing to OG/CS/PPA/23/2020 / Farm improve the business- & farmers registration, Consultant enabling environment and Under including Geo-tagging using IDA / V1860 Post Qualification Limited 94,736.84 0.00 2020-06-23 2020-07-20 2020-07-07 2021-04-14 2020-08-06 2020-09-10 2021-03-09 foster private sector Implementation digital tools & database Selection participation in the agri-f ood development and skills sectors Results based financing to OG/CS/PPA/24/2020 / improve the business- Consultant Engagement of Consultant for enabling environment and Under IDA / V1860 Post Qualification Limited 47,368.42 0.00 2020-06-25 2020-07-20 2020-07-09 2021-03-04 2020-08-08 2020-09-12 2021-03-11 In-depth analysis of priority foster private sector Implementation Selection value chains participation in the agri-f ood and skills sectors Results based financing to OG/CS/PPA/25/2020 / improve the business- Consultant Engagement of Consultant for enabling environment and Under IDA / V1860 Post Qualification Limited 47,368.42 0.00 2020-06-25 2020-07-20 2020-07-09 2021-04-14 2020-08-08 2020-09-12 2021-03-11 Verification for Agric. foster private sector Implementation Selection Clusters, Roads Etc participation in the agri-f ood and skills sectors Results based financing to improve the business- OG/CS/PPA/26/2020 / enabling environment and Least Cost Under Engagement of Consultant for IDA / V1860 Post Open - National 94,736.84 0.00 2020-06-25 2020-07-20 2020-07-16 2020-09-02 2020-08-29 2020-09-26 2020-10-26 2020-11-30 2021-01-04 2021-07-03 foster private sector Selection Implementation Baseline Studies - Agric participation in the agri-f ood and skills sectors Strengthening the capacity of OG/CS/PPA/27/2020 / the government to implement Least Cost Under Engagement of External IDA / V1860 Post Open - National 9,210.53 0.00 2020-06-22 2020-07-20 2020-07-13 2020-08-26 2020-09-23 2020-10-23 2020-11-27 2021-01-01 2021-06-30 the State’s economic Selection Implementation Auditor transformation agenda Results based financing to improve the business- OG/CS/PPA/43/2020 / Consultant enabling environment and Under Engagement of Value Chain IDA / V1860 Post Qualification Open - National 61,666.67 0.00 2020-06-29 2020-07-20 2020-07-20 2020-09-02 2020-09-02 2020-10-02 2020-11-06 2021-05-05 foster private sector Implementation Development Firms (VCDF) Selection participation in the agri-f ood and skills sectors OG/CS/PPA/22/2020 / Results based financing to Transaction Advisor to improve the business- Consultant prepare competitive selection enabling environment and Under IDA / V1860 Post Qualification Open - National 190,300.00 0.00 2020-08-17 2020-09-08 2020-09-07 2020-10-21 2020-11-20 2020-12-25 2021-06-23 of private industrial foster private sector Implementation Selection development and participation in the agri-f ood management and skills sectors Page 2 OG/CS/PPA/47/2020 / Engagement of Independent Strengthening the capacity of Verification Agency to Consultant the government to implement Under undertake independent IDA / V1860 Post Qualification Open - National 47,368.42 0.00 2020-07-20 2020-07-20 2020-08-10 2020-09-02 2020-09-23 2021-01-15 2020-10-23 2020-11-27 2021-05-26 the State’s economic Implementation verification of OGSTEP Selection transformation agenda program disbursement linked indicators (DLIs) Results based financing to OG/CS/AGR/01/2021 / improve the business- Consultant Consultancy for the enabling environment and Pending IDA / 65240 Post Qualification Open - National 300,000.00 0.00 2021-08-29 2021-09-28 2021-11-11 2021-12-11 2022-01-15 2022-07-14 engagement of four (4) VCDFs foster private sector Implementation Selection for 2022, 2nd batch participation in the agri-f ood and skills sectors OG/CS/AGR/03/2021 / Results based financing to Consultancy to carry out improve the business- feasibility studies including Consultant enabling environment and Pending ESIA on construction of 1,000 IDA / 65240 Post Qualification Open - National 150,000.00 0.00 2021-08-02 2021-08-23 2021-10-06 2021-11-05 2021-12-10 2022-06-08 foster private sector Implementation ha of small-scale irrigation Selection participation in the agri-f ood land and rehabilitation of and skills sectors 40km feeder road. Results based financing to OG/CS/AGR/05/2021 / improve the business- Consultancy to support and Consultant enabling environment and Pending provide Technical Assistance IDA / 65240 Post Qualification Open - National 100,000.00 0.00 2021-08-30 2021-09-20 2021-11-03 2021-12-03 2022-01-07 2022-07-06 foster private sector Implementation for the Project on Agriculture Selection participation in the agri-f ood FRILIA and skills sectors OG/CS/SDS/02/2021 / Results based financing to Consultancy to Develop improve the business- Consultant Competence-Based enabling environment and Pending IDA / 65240 Post Qualification Limited 107,628.00 0.00 2021-08-12 2021-08-26 2021-09-25 2021-10-30 2022-04-28 Curriculum for 10 New foster private sector Implementation Selection Courses for 8 Technical participation in the agri-f ood Colleges in Ogun State and skills sectors OG/CS/SDS/03/2021 / Consultancy for the development of recruitment Results based financing to policy and practices for the improve the business- Ogun State Technical and Consultant enabling environment and Pending Vocational Education Board IDA / 65240 Post Qualification Open - National 106,000.00 0.00 2021-08-27 2021-09-17 2021-10-31 2021-11-30 2022-01-04 2022-07-03 foster private sector Implementation (OGTVEB), development of Selection participation in the agri-f ood Human Resources Policy for and skills sectors Ogun Skills Fund and development of governing policy for the Ogun State Tec INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual OG/CS/PPA/02/2020 / Strengthening the capacity of Design, hosting and Individual the government to implement Pending maintenance of OGSTEP IDA / V1860 Post Consultant Limited 26,315.79 0.00 2020-07-13 2020-07-18 2020-08-08 2020-09-12 2021-03-11 the State’s economic Implementation website and mobile Selection transformation agenda application Results based financing to OG/CS/PPA/11/2020 / improve the business- Individual Recruitment of Ogun Invest enabling environment and Pending IDA / V1860 Post Consultant Limited 8,084.13 0.00 2020-07-27 2020-08-01 2020-08-22 2020-09-26 2021-03-25 Board trainer, Delivery of foster private sector Implementation Selection training to Ogun Invest Board participation in the agri-f ood and skills sectors OG/CS/PPA/12/2020 / Results based financing to Technical Training for improve the business- Individual OgunInvest - Business and enabling environment and Pending IDA / V1860 Post Consultant Limited 7,000.00 0.00 2020-06-30 2020-07-05 2020-07-26 2020-08-30 2021-02-26 Investment Research & foster private sector Implementation Selection Reporting and Industry value participation in the agri-f ood chain analysis and skills sectors Results based financing to improve the business- OG/CS/PPA/13/2020 / Individual enabling environment and Pending Recruit and appoint Baseline IDA / V1860 Post Consultant Open 24,584.13 0.00 2020-06-30 2020-08-18 2020-09-08 2020-10-13 2021-04-11 foster private sector Implementation Survey Consultant Selection participation in the agri-f ood and skills sectors Results based financing to improve the business- OG/CS/PPA/14/2020 / Individual enabling environment and Under Recruitment of Legal Policy IDA / V1860 Post Consultant Open 34,961.19 0.00 2020-06-26 2020-07-20 2020-08-14 2020-09-04 2020-10-09 2021-04-07 foster private sector Implementation Consultant Selection participation in the agri-f ood and skills sectors OG/CS/PPA/17/2020 / Results based financing to Review of Current Survey improve the business- Administration/Process Flow, Individual enabling environment and Pending Current Cost, IDA / V1860 Post Consultant Limited 36,494.30 0.00 2020-07-06 2020-07-11 2020-08-01 2020-09-05 2021-03-04 foster private sector Implementation Recommendation and Selection participation in the agri-f ood Implementation of Improved and skills sectors Land Administration Results based financing to improve the business- Individual OG/CS/PPA/19/2020 / enabling environment and Pending IDA / V1860 Post Consultant Open 9,000.00 0.00 2020-07-31 2020-09-18 2020-10-09 2020-11-13 2021-05-12 Sector Scan Validation foster private sector Implementation Selection participation in the agri-f ood and skills sectors Results based financing to OG/CS/PPA/20/2020 / improve the business- Individual Analysis of growth potential enabling environment and Pending IDA / V1860 Post Consultant Open 49,000.00 0.00 2020-08-03 2020-09-21 2020-10-12 2020-11-16 2021-05-15 and investment landscape in foster private sector Implementation Selection key economic sectors participation in the agri-f ood and skills sectors Page 3 Results based financing to OG/CS/PPA/44/2020 / improve the business- Engagement of Media Individual enabling environment and Pending consultant for the production IDA / V1860 Post Consultant Limited 5,263.00 0.00 2020-06-29 2020-07-04 2020-07-25 2020-08-29 2021-02-25 foster private sector Implementation of Jingles on Radio and TV, Selection participation in the agri-f ood Interviews - AGRIC and skills sectors Results based financing to OG/CS/PPA/21/2020 / improve the business- Individual Recruitment of enabling environment and Under IDA / V1860 Post Consultant Limited 52,174.30 0.00 2020-06-30 2020-07-20 2020-07-05 2020-07-26 2020-08-30 2021-02-26 Communication Strategy foster private sector Implementation Selection Consultant for IPA participation in the agri-f ood and skills sectors Results based financing to improve the business- OG/CS/PPA/45/2020 / Individual enabling environment and Pending Engagement of Consultant for IDA / V1860 Post Consultant Limited 29,000.00 0.00 2020-08-17 2020-08-22 2020-09-12 2020-10-17 2021-04-15 foster private sector Implementation Investor expansion survey Selection participation in the agri-f ood and skills sectors Results based financing to improve the business- Individual OG/CS/PPA/46/2020 / Deep enabling environment and Pending IDA / V1860 Post Consultant Limited 20,000.00 0.00 2020-08-03 2020-08-08 2020-08-29 2020-10-03 2021-04-01 dives foster private sector Implementation Selection participation in the agri-f ood and skills sectors Results based financing to OG/CS/PPA/35/2020 / improve the business- Engagement of key project Individual enabling environment and Under staff / Consultants (Agric – IDA / V1860 Post Consultant Open 31,578.95 0.00 2020-07-20 2020-03-02 2020-09-07 2020-09-28 2020-11-02 2021-05-01 foster private sector Implementation Sector Technical Team) - Selection participation in the agri-f ood Environmental Specialist and skills sectors Results based financing to OG/CS/PPA/36/2020 / improve the business- Engagement of key project Individual enabling environment and Under staff / Consultants (Agric – IDA / V1860 Post Consultant Open 31,578.95 0.00 2020-07-20 2020-03-02 2020-09-07 2020-09-28 2020-11-02 2021-05-01 foster private sector Implementation Sector Technical Team) - Selection participation in the agri-f ood Social Specialist and skills sectors Results based financing to OG/CS/PPA/37/2020 / improve the business- Engagement of key project Individual enabling environment and Under staff / Consultants (Agric – IDA / V1860 Post Consultant Open 31,578.95 0.00 2020-07-20 2020-04-06 2020-09-07 2021-04-15 2020-09-28 2020-11-02 2021-05-01 foster private sector Implementation Sector Technical Team) - Selection participation in the agri-f ood FRILIA Specialist and skills sectors OG/CS/PPA/40/2020 / Results based financing to Engagement of key project improve the business- Individual staff / Consultants (Business enabling environment and Under IDA / V1860 Post Consultant Open 31,578.95 0.00 2020-07-20 2020-03-26 2020-09-07 2020-09-28 2020-11-02 2021-05-01 Environment – Sector foster private sector Implementation Selection Technical Team) - Industrial participation in the agri-f ood Estate Specialist and skills sectors OG/CS/PPA/31/2020 / Strengthening the capacity of Individual Engagement of key project the government to implement Under IDA / V1860 Prior Consultant Open 31,578.95 0.00 2020-07-20 2020-08-26 2020-09-07 2020-09-28 2020-11-02 2021-05-01 staff / Consultants (PIU) - the State’s economic Implementation Selection Procurement Specialist transformation agenda OG/CS/PPA/32/2020 / Strengthening the capacity of Individual Engagement of key project the government to implement Under IDA / V1860 Prior Consultant Open 31,578.95 0.00 2020-07-20 2020-09-02 2020-09-07 2020-09-28 2020-11-02 2021-05-01 staff / Consultants (PIU) - the State’s economic Implementation Selection Procurement Reform Specialist transformation agenda Results based financing to OG/CS/PPA/15/2020 / improve the business- Individual Recruitment of Physical enabling environment and IDA / V1860 Post Consultant Limited 18,567.74 0.00 Canceled 2020-06-29 2020-07-04 2020-07-25 2020-08-29 2021-02-25 Planning Law review foster private sector Selection consultant participation in the agri-f ood and skills sectors Results based financing to improve the business- OG/CS/PPA/52/2020 / Individual enabling environment and Under Engagement of Project IDA / V1860 Post Consultant Open 75,000.00 0.00 2021-01-14 2021-01-15 2021-03-03 2021-03-09 2021-04-13 2021-10-10 foster private sector Implementation Manager - Agriculture Selection participation in the agri-f ood and skills sectors Results based financing to improve the business- OG/CS/PPA/53/2020 / Individual enabling environment and Under Engagement of Project IDA / V1860 Post Consultant Open 75,000.00 0.00 2021-01-14 2021-01-15 2021-02-27 2021-03-05 2021-04-09 2021-10-06 foster private sector Implementation Manager - Skills Development Selection participation in the agri-f ood and skills sectors Results based financing to OG/CS/PPA/54/2020 / improve the business- Individual Engagement of Project enabling environment and Under IDA / V1860 Post Consultant Open 75,000.00 0.00 2021-01-14 2021-01-15 2021-03-03 2021-03-09 2021-04-13 2021-10-10 Manager - Business Enabling foster private sector Implementation Selection Environment (BEE) participation in the agri-f ood and skills sectors Results based financing to OG/CS/PPA/48/2020 / improve the business- Consultancy to prepare the Individual enabling environment and Under Stakeholder Engagement Plan IDA / V1860 Post Consultant Open 80,000.00 0.00 2021-01-18 2021-01-18 2021-03-10 2021-04-15 2021-03-24 2021-04-26 2021-08-31 foster private sector Implementation (SEP) and Grievance Redress Selection participation in the agri-f ood Mechanism (GRM) and skills sectors Results based financing to improve the business- OG/CS/AGR/06/2021 / Individual enabling environment and Pending Recruitment of Project IDA / 65240 Post Consultant Open 60,000.00 0.00 2021-08-18 2021-10-06 2021-10-27 2021-12-01 2022-05-30 foster private sector Implementation Manager for the Agric Sector Selection participation in the agri-f ood and skills sectors Results based financing to improve the business- OG/CS/BEE/01/2021 / Individual enabling environment and Pending Recruitment of Project IDA / 65240 Post Consultant Open 60,000.00 0.00 2021-08-18 2021-10-06 2021-10-27 2021-12-01 2022-05-30 foster private sector Implementation Manager for the BEE Sector Selection participation in the agri-f ood and skills sectors Page 4 Results based financing to improve the business- OG/CS/PIU/05/2021 / Individual enabling environment and Pending Engagement of Gender IDA / 65240 Post Consultant Open 33,000.00 0.00 2021-08-23 2021-10-11 2021-11-01 2021-12-06 2022-06-04 foster private sector Implementation Assitant support Specialist Selection participation in the agri-f ood and skills sectors Page 5