The World Bank                                                                                    Implementation Status & Results Report
         College Education Development Project (P154577)



College Education Development Project (P154577)


 SOUTH ASIA | Bangladesh | Education Global Practice |
 IBRD/IDA | Investment Project Financing | FY 2016 | Seq No: 12 | ARCHIVED on 10-Nov-2021 | ISR48854 |


 Implementing Agencies: People's Republic of Bangladesh, National University, Ministry of Education, University Grants Commission



 Key Dates


  Key Project Dates

   Bank Approval Date: 03-Jun-2016                                           Effectiveness Date: 13-Oct-2016
   Planned Mid Term Review Date: 13-Jan-2019                                 Actual Mid-Term Review Date: 14-Jan-2019
   Original Closing Date: 30-Jun-2022                                        Revised Closing Date: 31-Dec-2023
 pdoTable

 Project Development Objectives

  Project Development Objective (from Project Appraisal Document)
  The project development objectives are to strengthen the strategic planning and management capacity of the college education subsector and to
  improve the teaching and learning environment of participating colleges.

  Has the Project Development Objective been changed since Board Approval of the Project Objective?
  No


 Components Table

 Name
 Component 1: Strengtheing the strategic planning and management capacity:(Cost $43.00 M)
 Component 2: Improving the teaching and learning environment in participating colleges:(Cost $47.00 M)
 Component 3: Project Management, communication and monitoring and evaluation:(Cost $10.00 M)

 Overall Ratings

 Name                                                                      Previous Rating                         Current Rating

 Progress towards achievement of PDO                                       Satisfactory                           Satisfactory
 Overall Implementation Progress (IP)                                      Moderately Satisfactory                Satisfactory
 Overall Risk Rating                                                       Substantial                            Substantial


 Implementation Status and Key Decisions

  This ISR is based on the 8th Implementation Support Mission from October 18-21, 2021, which was conducted virtually.
  Overall Implementation Status: The project has successfully responded to the COVID-induced college closures and lockdowns to accelerate the
  implementation. The overall project implementation progress is satisfactory as the project sustains good progress across the components.
  Pandemic response measures taken by the project include the introduction of online teacher training programs, online consultations and workshops
  for the development of the Strategic Plan, and online capacity building and grant supervision of colleges.
  Key progress over the past six months include (a) a draft Strategic Plan is being prepared based on six completed background studies; (b)
  Institutional Development Grant (IDG) implementation accelerated through central procurement and intensive college-level support at 120 colleges;
  (c) nearly 880 teachers and managers have been trained under TC partnership and NU’s subject-based training, using both face-to-face and online
  delivery modes. Key overall challenges discussed are (a) further acceleration and quality assurance of teacher training programs in hybrid mode;



11/10/2021                                                                                                                 Page 1 of 8
            The World Bank                                                                                      Implementation Status & Results Report
            College Education Development Project (P154577)



  (b) implementation of the Strategic Plan for the College Subsector; and (c) enactment of Non-government Teacher Selection Commission (NTSC)
  Act.
  The following key activities need to be expedited to further improve the implementation progress: (a) online/hybrid teacher training for Future Leader
  and Teacher cohorts and NU’s subject-based training; and (b) college-level IDG implementation.
  Disbursement: The total project cost is US$130 million (IDA: US$100 million, and GoB: US$30 million). The IDA credit consists of the DLI amount
  of US$90 million and Investment Project Financing (IPF) of US$10 million. The actual disbursement from IDA Credit as of October 20, 2021, is
  US$43.1 million, including US$40 million from DLIs and US$3.1 million from the IPF.
  Achievements of Disbursement-Linked Indicators (DLIs): In FY22, the project is expected to achieve Disbursement Linked Results (DLRs)
  worth a total of around US$20 million. DLRs with a total value of US$7 million have been achieved and will be claimed by November 30, 2021.
  College Re-opening: All colleges were closed for 1.5 years from March 17, 2020, to October 20, 2021 and resumed classes on October 21, 2021.
  They intensively engaged in catching up with academic activities, which may have some impacts on the project activities. The project continues to
  operate in online/hybrid modalities to manage the COVID-19 related risks.




  Risks


 Systematic Operations Risk-rating Tool


  Risk Category                                                Rating at Approval             Previous Rating                Current Rating

  Political and Governance                                     High                          Substantial                   Substantial
  Macroeconomic                                                Moderate                      Moderate                      Moderate
  Sector Strategies and Policies                               Substantial                   Moderate                      Moderate
  Technical Design of Project or Program                       Moderate                      Moderate                      Moderate
  Institutional Capacity for Implementation and
                                                               Substantial                   Moderate                      Moderate
  Sustainability
  Fiduciary                                                    Substantial                   Substantial                   Substantial
  Environment and Social                                       Moderate                      Moderate                      Moderate
  Stakeholders                                                 Moderate                      Moderate                      Moderate
  Other                                                        --                             Moderate                      Moderate
  Overall                                                      Substantial                   Substantial                   Substantial



  Results


 PDO Indicators by Objectives / Outcomes



   To strengthen the strategic planning and management capacity of the college education subsector

    IN01057633
    ►Sector strategy and action plan developed, and the initial implementation started (Text, Custom, PBC)

                                       Baseline                     Actual (Previous)            Actual (Current)            End Target
                                       No strategic plan is                                                                  MOE prepared an
                                                                    Six background studies       The first draft strategic
    Value                              available for the tertiary                                                            investment plan for
                                                                    completed                    plan prepared;
                                       college subsector.                                                                    quality enhancement


11/10/2021                                                                                                                      Page 2 of 8
           The World Bank                                                                                 Implementation Status & Results Report
           College Education Development Project (P154577)



                                                                                            consultation             of college education in
                                                                                            workshops carried out    line with the college
                                                                                                                     sub-sector strategic
                                                                                                                     plan.
    Date                             03-Oct-2016                  31-Dec-2020               31-Oct-2021              31-Dec-2023

    IN01057635
    ►Government college teacher vacancies filled (Text, Custom, PBC)

                                      Baseline                    Actual (Previous)         Actual (Current)          End Target
                                                                  MoE has filled 4,300      MoE has filled 4,300
                                     Vacancies:                   government teacher        government teacher       MoE has completed a
    Value                            2,700                        vacancies; MoE has        vacancies; MoE has       needs assessment for
                                                                  undertaken a teacher      undertaken a teacher     teacher posts.
                                                                  needs assessment          needs assessment
    Date                             03-Oct-2016                  30-Sep-2020               31-Oct-2021              31-Dec-2020



   To improve the teaching and learning environment of participating colleges

   IN01057634
   ►Number of teachers and managers in Honours and Masters colleges trained in subject and pedagogical training under the Project (Text,
   Custom, PBC)

                                      Baseline                    Actual (Previous)         Actual (Current)         End Target
                                                                                                                     5,000 college teachers
                                                                  414 teachers and          874 teachers and
    Value                            0.00                                                                            and managers are
                                                                  managers trained          managers trained
                                                                                                                     trained.
    Date                             03-Oct-2016                  31-Dec-2020               31-Oct-2021              31-Dec-2023

    IN01057651
    ►Teaching and learning environment at Honours and Masters colleges upgraded (% of IDP activity milestones achieved) (Number, Custom)

                                      Baseline                    Actual (Previous)         Actual (Current)          End Target

    Value                            0.00                         0.00                      26.00                     70.00

    Date                             03-Oct-2016                  30-Sep-2020               31-Oct-2021              31-Dec-2023
                                      Performance contracts have been signed with 122 colleges in June 2019. All procurement plans have
   Comments:                          been approved.



 Intermediate Results Indicators by Components



   Component 2: Improving the teaching and learning environment in participating colleges

    IN01057653
    ►Number of colleges which completed self-assessment for quality assurance (Number, Custom)

                                      Baseline                    Actual (Previous)         Actual (Current)          End Target

    Value                            0.00                         0.00                      0.00                      30.00

    Date                             03-Oct-2016                  30-Sep-2020               31-Oct-2021              31-Dec-2023


11/10/2021                                                                                                               Page 3 of 8
           The World Bank                                                                                       Implementation Status & Results Report
           College Education Development Project (P154577)



                                      The project is developing a guideline for undertaking self-assessment activities for colleges.
   Comments:

   IN01057655
   ►Increased satisfaction levels of students and teachers of grant supported colleges about teaching and learning environment (targets set by
   % increase) (Text, Custom)

                                     Baseline                     Actual (Previous)             Actual (Current)           End Target
                                                                                                                           Student:
                                                                  ToR for Mid-term                                         Teacher:
                                                                                                A firm is being
    Value                            n.a                          Satisfaction Survey                                      (30% increase from
                                                                                                recruited
                                                                  prepared                                                 the baseline)


    Date                             03-Oct-2016                  30-Sep-2020                   31-Oct-2021                31-Dec-2023

                                      [Baseline in 2019] Student: 2.634 Teacher: 2.424
   Comments:



   Component 1: Strengtheing the strategic planning and management capacity

    IN01057652
    ►Students benefiting from direct interventions to enhance learning (Number, Corporate)

                                     Baseline                     Actual (Previous)             Actual (Current)            End Target

    Value                            0.00                         2,000,000.00                  2,000,000.00                2,100,000.00

    Date                             03-Oct-2016                  30-Sep-2020                   31-Oct-2021                31-Dec-2023

     IN01057657
     Students benefiting from direct interventions to enhance learning - Female (Number, Corporate Supplement)

                                    Baseline                     Actual (Previous)             Actual (Current)            End Target

     Value                          0.00                         929,000.00                    929,000.00                  1,071,000.00

    IN01057658
    ►Management in the participating colleges strengthened (% of grant supported colleges publish timely annual reports) (Percentage, Custom)

                                     Baseline                     Actual (Previous)             Actual (Current)            End Target

    Value                            0.00                         0.00                          19.20                       80.00

    Date                             03-Oct-2016                  30-Sep-2020                   31-Oct-2021                31-Dec-2023

                                      A total of US$5 million has been disbursed to the beneficiary colleges.
   Comments:



   Component 3: Project Management, communication and monitoring and evaluation

    IN01057654
    ►PMU is fully operational (Yes/No, Custom)

                                     Baseline                     Actual (Previous)             Actual (Current)            End Target

    Value                            No                           Yes                           Yes                         Yes

    Date                             03-Oct-2016                  30-Sep-2020                   31-Oct-2021                31-Dec-2023



11/10/2021                                                                                                                     Page 4 of 8
           The World Bank                                                                                      Implementation Status & Results Report
           College Education Development Project (P154577)



                                      Being fully operational is defined as having met three of the following four conditions: (a) Staffing (70
                                      percent of PMU staff are in place); (b) Procurement (at least 70 percent of the procurement was
   Comments:                          completed as intended in the Procurement Plan); (c) M&E (at least 70 percent of the intended reports
                                      published and activities completed); and (d) FM (the previous IUFR is completed in time).

    IN01057656
    ►Midterm and follow-up tracer study conducted (Text, Custom)

                                      Baseline                     Actual (Previous)             Actual (Current)           End Target
                                                                   Study underway,
                                                                                                 Mid-term study             Follow-up Tracer study
    Value                             n.a                          expected to be
                                                                                                 completed                  conducted
                                                                   completed by June 2021
    Date                              03-Oct-2016                  30-Sep-2020                   31-Oct-2021                31-Dec-2023

    IN01057659
    ►Web-based Project Management Information System (PMIS) is established and regularly updated. (Text, Custom)

                                      Baseline                     Actual (Previous)             Actual (Current)           End Target
                                                                   70% of the development        PMIS fully functional
                                                                                                                            PMIS fully functional
    Value                             n.a                          work of PMIS has been         and user trainng is
                                                                                                                            and regularly updated
                                                                   completed                     ongoing
    Date                              03-Oct-2016                  30-Sep-2020                   31-Oct-2021                31-Dec-2023

    IN01057660
    ►Awareness raising activities are regularly conducted. (Number, Custom)

                                      Baseline                     Actual (Previous)             Actual (Current)           End Target

    Value                             0.00                         38.00                         38.00                      16.00

    Date                              03-Oct-2016                  30-Sep-2020                   31-Oct-2021                31-Dec-2023



 Performance-Based Conditions




   IN01057661
    ►PBC 1 Sector strategy and action plan developed, and the initial implementation started (Text, Output, 16,000,000.00, 25.00%)

                                                                                                                             Year 7 (Jan-Dec
                                 Baseline                       Actual (Previous)             Actual (Current)               2023)
                                                                                              The first draft strategic
                                 No strategic plan is
                                                                Six background studies        plan prepared;
    Value                        available for the tertiary                                                                  --
                                                                completed                     consultation workshops
                                 college subsector.
                                                                                              carried out
    Date                         --                             31-Dec-2020                   31-Oct-2021                    --




   IN01057662
    ►PBC 2 Government college teacher vacancies filled (Text, Output, 18,000,000.00, 66.67%)


11/10/2021                                                                                                                        Page 5 of 8
           The World Bank                                                                              Implementation Status & Results Report
           College Education Development Project (P154577)




                                                                                                                    Year 7 (Jan-Dec
                                 Baseline                    Actual (Previous)          Actual (Current)            2023)
                                                             MoE has filled 3,500       MoE has filled 4,300
                                 Vacancies:                  government teacher         government teacher
    Value                        2,700                       vacancies; MoE has         vacancies; MoE has          --
                                                             undertaken a teacher       undertaken a teacher
                                                             needs assessment           needs assessment
    Date                         --                          30-Sep-2020                31-Oct-2021                 --




   IN01057663
    ►PBC 3 Improvement of teacher management system for nongovernment colleges (Text, Output, 9,000,000.00, 66.67%)

                                                                                                                    Year 7 (Jan-Dec
                                 Baseline                    Actual (Previous)          Actual (Current)            2023)
                                                             Draft Act is being         Draft NTSC Act is being
    Value                        n/a                         processed for approval     processed by MoE for        -
                                                             by the ministry            approval by the Cabinet
    Date                         --                          31-Dec-2020                31-Oct-2021                 --




   IN01057664
   ►PBC 4 Improved teaching and learning environment in selected government and non-government colleges (Text, Output, 25,000,000.00,
   24.00%)

                                                                                                                    Year 7 (Jan-Dec
                                 Baseline                    Actual (Previous)          Actual (Current)            2023)
                                                                                                                    On average 90% of
                                                                                                                    the total allocated
                                                             15% disbursed; FY21
                                                                                        Around 30% of the total     budget of the
                                 No competitive funding to   procurement plans worth
    Value                                                                               grant budget has been       competitive funding
                                 colleges in Bangladesh      BDT3 billion approved by
                                                                                        utilized by October 2021    is utilized in
                                                             the project.
                                                                                                                    accordance with the
                                                                                                                    operation manual
    Date                         --                          31-Dec-2020                31-Oct-2021                 --




   IN01057665
   ►PBC 5 Number of teachers and managers in Honours and Masters colleges trained in subject and pedagogical training under the Project
   (Text, Output, 16,000,000.00, 37.50%)

                                                                                                                    Year 7 (Jan-Dec
                                 Baseline                    Actual (Previous)          Actual (Current)            2023)
                                                             414 teachers and           874 teachers and
    Value                        0.00                                                                               --
                                                             managers trained           managers trained

    Date                         --                          31-Dec-2020                31-Oct-2021                 --




11/10/2021                                                                                                               Page 6 of 8
           The World Bank                                                                                        Implementation Status & Results Report
           College Education Development Project (P154577)



   IN01057666
   ►PBC 6 COVID-19 Response: Establishment of Online Learning Platform for Building Resilience of College Education (Text, Output,
   6,000,000.00, 0.00%)

                                                                                                                               Year 7 (Jan-Dec
                                 Baseline                          Actual (Previous)             Actual (Current)              2023)
                                 No LMS available for                                            The tenders for LMS and
                                                                   ToRs for LMS and
                                 courses of colleges                                             content development will
    Value                                                          content development                                         -
                                 affiliated with the National                                    be initiated by November
                                                                   drafted
                                 University                                                      30, 2021
    Date                         --                                31-Dec-2020                   31-Oct-2021                   --



 Data on Financial Performance


 Disbursements (by loan)

 Project       Loan/Credit/TF    Status       Currency          Original   Revised       Cancelled     Disbursed       Undisbursed                % Disbursed


 P154577       IDA-58410         Effective    USD               100.00      100.00             0.00         43.11            56.42                       43%


 Key Dates (by loan)

 Project        Loan/Credit/TF    Status       Approval Date        Signing Date       Effectiveness Date      Orig. Closing Date      Rev. Closing Date

 P154577        IDA-58410         Effective    03-Jun-2016          08-Sep-2016        13-Oct-2016             30-Jun-2022             31-Dec-2023


Cumulative Disbursements




11/10/2021                                                                                                                          Page 7 of 8
          The World Bank                                                                           Implementation Status & Results Report
          College Education Development Project (P154577)



 PBC Disbursement

                                                                                  Achievement   Disbursed amount in     Disbursement %
 PBC ID                   PBC Type   Description            Coc      PBC Amount
                                                                                  Status        Coc                     for PBC




  Restructuring History


  Level 2 Approved on 01-May-2019 ,Level 2 Approved on 14-Jun-2021


  Related Project(s)


 There are no related projects.