Restructuring Status: Archived Restructuring Type: Level two Last modified on date : 12/19/2011 1. Basic Information Project ID & Name P075163: HAZ MITIG Country Romania Task Team Leader Gabriel Ionita Sector Manager/Director Stephen George Karam Country Director Peter C. Harrold Original Board Approval Date 05/20/2004 Original Closing Date: 12/31/2009 Current Closing Date 12/20/2011 Proposed Closing Date [if applicable] 06/30/2012 EA Category B-Partial Assessment Revised EA Category B-Partial Assessment-Partial Assessment EA Completion Date 03/15/2003 Revised EA Completion Date 2. Revised Financing Plan (US$m) Source Original Revised BORR 46.66 46.66 IBRD 150.00 143.32 Total 196.66 189.98 3. Borrower Organization Department Location Ministry of Public Finance Romania 4. Implementing Agency Organization Department Location National Agency of Mineral PMU Romania Resources Ministry of Regional Development PMU Romania and Tourism Ministry of Administration and PMU Romania Interior Ministry of Environment and PMU Romania Forests ii 5. Disbursement Estimates (US$m) Actual amount disbursed as of 12/20/2011 116.99 Fiscal Year Annual Cumulative 2011 5.00 121.99 2012 21.33 143.32 Total 143.32 6. Policy Exceptions and Safeguard Policies Does the restructured project require any exceptions to Bank policies? N Does the restructured projects trigger any new safeguard policies? If yes, please select N from the checklist below and update ISDS accordingly before submitting the package. 7a. Project Development Objectives/Outcomes Original/Current Project Development Objectives/Outcomes The overall objective of the project is to assist the Government of Romania in reducing the environmental, social, and economic vulnerability to natural disasters and catastrophic mining accidental spills of pollutants through: (i) strengthening the institutional and technical capacity for disaster management and emergency response through upgrading communication and information systems; (ii) implementing specific risk reduction investments for floods, landslides and earthquakes; (iii) improving the safety of selected water-retention dams; and (iv) improving on a pilot basis the management and safety of tailings dams and waste dump facilities. 7b. Revised Project Development Objectives/Outcomes [if applicable] iii