Sample Procurement Plan (Text in italic font is meant for instruction to staff and should be deleted in the final version of the PP) (This is only a sample with the minimum content that is required to be included in the PAD. The detailed procurement plan is still mandatory for disclosure on the Bank’s website in accordance with the guidelines. The initial procurement plan will cover the first 18 months of the project and then updated annually or earlier as necessary). I. General 1. Bank’s approval Date of the procurement Plan [Original: December 2007]: Revision 15 of Updated Procurement Plan, June 2010] 2. Date of General Procurement Notice: Dec 24, 2006 3. Period covered by this procurement plan: The procurement period of project covered from year June 2010 to December 2012 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: [Thresholds for applicable procurement methods (not limited to the list below) will be determined by the Procurement Specialist /Procurement Accredited Staff based on the assessment of the implementing agency’s capacity.] Procurement Method Prior Review Threshold Comments US$ 1. ICB and LIB (Goods) Above US$ 500,000 All 2. NCB (Goods) Above US$ 100,000 First contract 3. ICB (Works) Above US$ 15 million All 4. NCB (Works) Above US$ 5 million All 5. (Non-Consultant Services) Below US$ 100,000 First contract [Add other methods if necessary] 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: [Refer to the relevant CDD project implementation document approved by the Bank or delete if not applicable] 4. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan Project XYZ 04/01/2010 issued by July 9, 2010 5. Any Other Special Procurement Arrangements: [including advance procurement and retroactive financing, if applicable] 5 ICB works packages will be financed under retroactive financing 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness ( including those that are subject to retroactive financing and advanced procurement) [List the Packages which require Bank’s prior review first and then the other packages] 1 2 3 4 5 6 7 Ref. Description Estimated Packages Domest Review Comments No. Cost ic by Bank US$ Prefere (Prior / Post) million nce (yes/no) Summary of 82 5 No Prior the ICB (Works) Summary of 43.77 15 No Prior the ICB (Goods) Summary of 64.53 18 No Post 1st the NCB contract (Works) for Prior Review Summary of 1.86 4 No Post 1st the NCB contract (Goods) for Prior Review Summary of 0.45 1 No Prior the ICB (Non- Consultant Services) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Threshold Comments 1. Competitive Methods (Firms) Above US$ 100,000 2. Single Source (Firms) All 3. Individual Above US$ 50,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise July 9, 2010 entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: [including advance procurement and retroactive financing, if applicable or delete if not applicable] 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description of Estimated Packages Review Comments Assignment Cost by Bank US$ (Prior / million Post) Summary of 4.17 7 Prior number of contracts that will be let under QCBS Summary of 0.83 1 Prior CQS number of contracts that will be let under other methods July 9, 2010 PROCUREMENT Cote d'Ivoire : Agriculture Sector Support Project PLAN General Information Country: Cote d'Ivoire Banks Approval Date of the Original Procurement Plan: 2018-06-12 Revised Plan Date(s): (comma delineated, leave blank if none) 2018-06-12 Project ID: P119308 GPN Date: Project Name: Agriculture Sector Support Project Loan / Credit No: IDA / H8750, IDA / 52970 Executing Agency(ies): Project Coordination Unit of Support to the Agricultural Sector WORKS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 3: Support to the cotton sector and Promotion of cashew processing in Central CI-UC-PSAC-52698-CW-DIR / and Northern Cote dIvoire Pending Entente directe avec l'entreprise IDA / H8750 Prior Direct Selection Direct 232,000.00 0.00 2018-03-07 2018-03-12 2018-04-16 2018-10-13 Component1: Promotion of Implementation ITA public-private partnership for sustainable cocoa development in South-West Cote d'Ivoire Component 2: Support to CI-UC-PSAC-63190-CW-RFB / smallholder rubber and oil palm Single Stage - Two Pending Travaux d'entretien en RLEP de IDA / H8750 Post Request for Bids Open - National 1,110,000.00 0.00 2017-01-23 2017-01-28 2017-03-11 2017-05-24 2017-06-28 2017-12-25 extension in South-East Cote Envelope Implementation 370 KM region du SUD COMOE dIvoire CI-UC-PSAC-63210-CW-RFB / Component 2: Support to Travaux en RLTPC sur 110 Km smallholder rubber and oil palm Single Stage - Two Pending IDA / H8750 Post Request for Bids Open - National 1,920,000.00 0.00 2017-04-07 2017-04-12 2017-05-24 2017-08-06 2017-09-10 2018-03-09 dans les regiosndu Sud Comoé extension in South-East Cote Envelope Implementation et de la Mé dIvoire CI-UC-PSAC-63222-CW-RFB / Component 2: Support to Travaux en RLEP sur 693 Km smallholder rubber and oil palm Single Stage - Two Pending IDA / H8750 Post Request for Bids Open - National 693,300.00 0.00 2017-11-24 2017-11-29 2018-01-10 2018-03-25 2018-04-29 2018-10-26 dans les regions du Sud Comoé extension in South-East Cote Envelope Implementation et de la m2 dIvoire CI-UC-PSAC-64088-CW-RFP / Component1: Promotion of Réalisation de 15 forages HV à public-private partnership for Request for Pending IDA / H8750 Post Open - National Multi Stage 180,000.00 0.00 2015-01-10 2015-01-15 2015-03-26 2015-07-08 2015-08-12 2017-02-02 é uiper de pompes à motricité q sustainable cocoa development Proposals Implementation humaine in South-West Cote d'Ivoire GOODS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 2: Support to CI-UC-PSAC-52701-GO-RFQ / smallholder rubber and oil palm Request for Single Stage - One Pending Acquisition de fournitures de IDA / H8750 Post Open - National 8,000.00 0.00 2018-06-22 2018-08-17 2019-02-13 extension in South-East Cote Quotations Envelope Implementation bureau au titre de la gestion 2018 dIvoire Component 2: Support to CI-UC-PSAC-52726-GO-RFQ / smallholder rubber and oil palm Request for Single Stage - One Pending Acquisition de consommables IDA / H8750 Post Open - National 12,000.00 0.00 2018-02-25 2018-04-22 2018-10-19 extension in South-East Cote Quotations Envelope Implementation informatiques dIvoire CI-UC-PSAC-52741-GO-RFQ / Acquisition d'ordinateurs Component 2: Support to (portables, de bureau et smallholder rubber and oil palm Request for Single Stage - One Pending IDA / H8750 Post Open - National 94,000.00 0.00 2018-02-25 2018-04-22 2018-10-19 imprimantes) pour la saisie des extension in South-East Cote Quotations Envelope Implementation données à l'entrée des usines et dIvoire autres points accès CI-UC-PSAC-52686-GO-DIR / Component4: Project Pending Entente Directe avec l'entreprise IDA / H8750 Implementation and support to Prior Direct Selection Direct 26,000.00 0.00 2018-03-15 2018-03-15 2018-04-19 2018-10-16 Implementation TOTAL sector coordination CI-UC-PSAC-52750-GO-DIR / Component 2: Support to Acquisition et installation de smallholder rubber and oil palm Pending poste de serveur informatique et IDA / H8750 Post Direct Selection Direct 8,000.00 0.00 2018-02-20 2018-02-25 2018-04-01 2018-09-28 extension in South-East Cote Implementation é uipements licences, routeurs q dIvoire de sécurité et matériel CI-UC-PSAC-52792-GO-RFQ / Component 2: Support to Confection de support de smallholder rubber and oil palm Request for Single Stage - One Pending communication (affiches,, IDA / H8750 Post Open - National 45,200.00 0.00 2018-03-17 2018-05-12 2018-11-08 extension in South-East Cote Quotations Envelope Implementation gadgets, tee-shirts, casquettes, dIvoire polos, macarons et autres etc...) Component 2: Support to CI-UC-PSAC-52796-GO-RFQ / smallholder rubber and oil palm Request for Single Stage - One Pending Confection de panneaux, pour les IDA / H8750 Post Open - National 28,000.00 0.00 2018-03-17 2018-05-12 2018-11-08 extension in South-East Cote Quotations Envelope Implementation é iciaires du Projet bénf dIvoire CI-UC-PSAC-64054-GO-RFQ / Component1: Promotion of Acquisition de matériels de public-private partnership for Request for Single Stage - One Pending IDA / H8750 Post Open - National 99,000.00 0.00 2018-05-06 2018-07-13 2019-01-09 contrôle et d'analyse pour sustainable cocoa development Quotations Envelope Implementation l'USCOOP-NAWA in South-West Cote d'Ivoire CI-UC-PSAC-64081-GO-RFP / Component1: Promotion of Acquisition de matériels public-private partnership for Request for Single Stage - One Pending IDA / H8750 Post Open - National 80,000.00 0.00 2018-05-09 2018-05-14 2018-05-30 2018-06-29 2018-08-03 2019-01-30 informatiques pour l'USCOOP- sustainable cocoa development Proposals Envelope Implementation Nawa in South-West Cote d'Ivoire CI-UC-PSAC-64074-GO-RFQ / Component1: Promotion of Acquisition de matériels & public-private partnership for Request for Single Stage - One Pending IDA / H8750 Post Open - National 14,000.00 0.00 2018-06-06 2018-08-01 2019-01-28 mobiliers de bureau pour sustainable cocoa development Quotations Envelope Implementation l'USCOOP-Nawa in South-West Cote d'Ivoire Page 1 CI-UC-PSAC-64052-GO-RFQ / Component1: Promotion of Fourniture et pose de 15 pompes public-private partnership for Request for Single Stage - One Pending IDA / H8750 Post Open - National 75,000.00 0.00 2016-01-12 2016-06-27 2016-12-24 à motricité humaine dans la sustainable cocoa development Quotations Envelope Implementation région de la Nawa in South-West Cote d'Ivoire Component1: Promotion of CI-UC-PSAC-64066-GO-RFQ / public-private partnership for Request for Single Stage - One Pending Acquisition de matériels de IDA / H8750 Post Open - National 285,000.00 0.00 2018-06-06 2018-08-01 2019-01-28 sustainable cocoa development Quotations Envelope Implementation transport pour l'USCOOP-Nawa in South-West Cote d'Ivoire CI-UC-PSAC-64084-GO-RFP / Component1: Promotion of Impression et reproduction en public-private partnership for Request for Single Stage - One Pending 500 exemplaires du document de IDA / H8750 Post Open - National 26,400.00 0.00 2018-05-30 2018-06-04 2018-07-16 2018-08-15 2018-09-19 2019-03-18 sustainable cocoa development Proposals Envelope Implementation é ence des indicateurs de réfr in South-West Cote d'Ivoire durabilité des projets CI-UC-PSAC-64085-GO-RFP / Impression et reproduction en 500 exemplaires du guide des Component1: Promotion of bonnes pratiques pour la mise en public-private partnership for Request for Single Stage - One Pending IDA / H8750 Post Open - National 14,000.00 0.00 2018-04-18 2018-04-23 2018-05-21 2018-06-20 2018-07-25 2019-01-21 place des infrastructures dans sustainable cocoa development Proposals Envelope Implementation les communautés productrices in South-West Cote d'Ivoire de Café et de Cacao en Côte d'Ivoire. CI-UC-PSAC-64087-GO-DIR / Component1: Promotion of Acquisition de logiciel de gestion public-private partnership for Pending des marchés TOMMARCHE IDA / H8750 Post Direct Selection Direct 25,690.00 0.00 2018-05-30 2018-06-04 2018-07-09 2019-01-05 sustainable cocoa development Implementation multiprojets pour le Conseil du in South-West Cote d'Ivoire Café-Cacao NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CI-UC-PSAC-52805-NC-DIR / Component 2: Support to Acquisition et Equipements de smallholder rubber and oil palm Pending sites de traitement de données IDA / H8750 Post Direct Selection Direct 12,000.00 0.00 2018-03-12 2018-03-17 2018-04-21 2018-10-18 extension in South-East Cote Implementation (60 clés connexion de dIvoire compagnie télp é honie mobile) CI-UC-PSAC-52800-NC-DIR / Component 2: Support to Acquisition d'un Hébergement du smallholder rubber and oil palm Pending IDA / H8750 Post Direct Selection Direct 12,000.00 0.00 2018-03-12 2018-03-17 2018-04-21 2018-10-18 site de collecte et de traitement extension in South-East Cote Implementation des données dIvoire CI-UC-PSAC-63186-NC-DIR / Location de véhicules dans le Component 2: Support to cadre du suivi et de la mise en smallholder rubber and oil palm Request for Single Stage - One Pending IDA / H8750 Post Open - National 51,000.00 0.00 2015-01-10 2015-01-15 2015-02-26 2015-03-28 2015-05-02 2015-10-29 oeuvre de l'opération extension in South-East Cote Proposals Envelope Implementation d'identification des producteurs dIvoire réuni au sein du COP HEVEA Component 2: Support to CI-UC-PSAC-63178-NC-DIR / smallholder rubber and oil palm Pending Entente directe avec SIFCOM IDA / H8750 Prior Direct Selection Direct 4,590.00 0.00 2017-09-03 2017-09-08 2017-10-13 2018-10-08 extension in South-East Cote Implementation ASSUR dIvoire CONSULTING FIRMS Activity Reference No. / Combined Evaluation Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Technical Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CI-UC-PSAC-51768-CS-NPO / Component 2: Support to Convention APROMAC PSAC IDA / H8750 smallholder rubber and oil palm Non-Profit Pending Prior Direct 1,010,833.00 0.00 2016-01-22 2016-02-23 2016-05-11 2016-05-11 relatif au versement des fonds de IDA / 52970 extension in South-East Cote Organizations Implementation l'APROMAC par le PSAC dIvoire CI-UC-PSAC-52839-CS-CQS / Component 2: Support to Recruter un opérateur technique Consultant smallholder rubber and oil palm Pending pour le recensement des IDA / H8750 Post Qualification Open - National 300,000.00 0.00 2018-02-28 2018-03-21 2018-05-04 2018-06-03 2018-07-08 2019-01-04 extension in South-East Cote Implementation opérateurs et la géolocalisation Selection dIvoire des parcelles CI-UC-PSAC-63343-CS-CQS / Component 2: Support to Recrutement d'un Consultant Consultant smallholder rubber and oil palm Pending Firme pour l'élaboration du listing IDA / H8750 Post Qualification Open - National 94,000.00 0.00 2018-06-01 2018-06-22 2018-08-05 2018-09-04 2018-10-09 2019-04-07 extension in South-East Cote Implementation é ectoral des producteurs de l Selection dIvoire caoutchouc CI-UC-PSAC-63338-CS-CQS / Recrutement de Cabinets pour le suivi et le contrôle technique, Component 2: Support to Consultant environnemental et social des smallholder rubber and oil palm Pending IDA / H8750 Post Qualification Open - National 78,400.00 0.00 2016-10-12 2017-08-08 2017-09-21 2017-10-21 2017-11-25 2018-05-24 travaux d'entretien par RLEP de extension in South-East Cote Implementation Selection 692, km de routes rurales dans dIvoire les régions du Sud Comoé et de la Mé CI-UC-PSAC-63333-CS-CQS / Recrutement d'un Cabinet pour le suivi et le contrôle technique, Component 2: Support to environnemental et social des Consultant smallholder rubber and oil palm Pending travaux du Programme 2016 de IDA / H8750 Post Qualification Open - National 176,000.00 0.00 2017-03-22 2017-04-12 2017-05-26 2017-06-25 2017-07-30 2018-01-26 extension in South-East Cote Implementation RLTPC de 110 km de routes Selection dIvoire rurales à réhabiliter dans les régions du Sud Comoé et de la Mé CI-UC-PSAC-63359-CS-CQS / Recrutement de deux Cabinets pour le suivi et le contrôle Component 2: Support to technique, environnemental et Consultant smallholder rubber and oil palm Pending social de la 2ème passe des IDA / H8750 Post Qualification Open - National 100,000.00 0.00 2017-10-30 2017-11-20 2018-01-03 2018-02-02 2018-03-09 2018-09-05 extension in South-East Cote Implementation travaux d'entretien par RLEP de Selection dIvoire 692, km de routes rurales dans les régions du Sud Comoé et de la Mé Page 2 CI-UC-PSAC-64092-CS-CQS / Component1: Promotion of Consultant Sélection d'un consultant pour la public-private partnership for Pending IDA / H8750 Post Qualification Open - National 90,000.00 0.00 2018-06-29 2018-07-20 2018-09-02 2018-10-02 2018-11-06 2019-05-05 conception et la mise en Ruvre sustainable cocoa development Implementation Selection d'un système d'alerte précoce in South-West Cote d'Ivoire CI-UC-PSAC-66074-CS-CQS / Component1: Promotion of Consultant Recrutement d'un cabinet pour la public-private partnership for Pending IDA / H8750 Post Qualification Open - National 100,000.00 0.00 2016-01-07 2016-01-28 2016-03-12 2016-04-11 2016-05-16 2016-11-12 é aluation du réalisation de la pré-v sustainable cocoa development Implementation Selection projet PSAC (enquête de suivi) in South-West Cote d'Ivoire CI-UC-PSAC-64099-CS-CQS / Component1: Promotion of Recrutement d'un Cabinet pour le Consultant public-private partnership for Pending diagnostic de quarante-huit (48) IDA / H8750 Post Qualification Open - National 400,000.00 0.00 2018-05-31 2018-06-21 2018-08-04 2018-09-03 2018-10-08 2019-04-06 sustainable cocoa development Implementation é sociéts coopératives membres Selection in South-West Cote d'Ivoire de l'UCOOPEXCI. CI-UC-PSAC-64100-CS-CQS / Component1: Promotion of Consultant Recrutement d'un cabinet pour la public-private partnership for Pending IDA / H8750 Post Qualification Open - National 60,000.00 0.00 2018-06-19 2018-07-10 2018-08-23 2018-09-22 2018-10-27 2019-04-25 réalisation d'un film institutionnel sustainable cocoa development Implementation Selection sur les acquis du PSAC. in South-West Cote d'Ivoire INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Contract Type Estimated Actual Amount Draft Negotiated Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 3: Support to the CI-UC-PSAC-52700-CS-CDS / cotton sector and Promotion of Pending Gré à gré avec le groupement IDA / H8750 Prior Direct Selection Direct 20,000.00 0.00 2018-02-15 2018-02-25 2018-05-01 2018-10-28 cashew processing in Central Implementation S2IC/AC3E and Northern Cote dIvoire CI-UC-PSAC-52812-CS-CDS / Recrutement de cabinets techniques pour l'appui à la mise en Suvre du plan d'appui aux 11 Component 2: Support to é sociéts coopératives (mission 1, smallholder rubber and oil palm Pending IDA / H8750 Prior Direct Selection Direct 670,000.00 0.00 2018-03-08 2018-03-18 2018-05-22 2018-11-18 2 et 3) extension in South-East Cote Implementation ED dIvoire -Le Mont Horeb -SONET-CI -AMB consulting CI-UC-PSAC-52936-CS-INDV / Component 2: Support to Recrutement d'un consultant smallholder rubber and oil palm Individual Consultant Pending IDA / H8750 Post Open 30,000.00 0.00 2018-03-12 2018-04-30 2018-05-21 2018-06-25 2018-12-22 pour l'Etude de capitalisation du extension in South-East Cote Selection Implementation programme plant mis en Suvre dIvoire CI-UC-PSAC-52965-CS-CDS / Component 2: Support to Recrutement d'un consultant smallholder rubber and oil palm Pending pour la Formation des IDA / H8750 Post Direct Selection Direct 30,000.00 0.00 2018-03-07 2018-03-17 2018-05-21 2018-11-17 extension in South-East Cote Implementation pépiniéristes à la production de dIvoire plants de qualité CI-UC-PSAC-52975-CS-CDS / Component 2: Support to Recrutement de consultants smallholder rubber and oil palm Pending individuels pour l'étude de IDA / H8750 Post Direct Selection Direct 32,000.00 0.00 2015-12-17 2015-12-27 2016-03-01 2016-08-28 extension in South-East Cote Implementation dimensionnement de réseau dIvoire d'irrigation CI-UC-PSAC-52913-CS-INDV / Recrutement d'un consultant individuel pour l'appui à Component 2: Support to l'actualisation du mécanisme de smallholder rubber and oil palm Individual Consultant Pending IDA / H8750 Post Open 20,000.00 0.00 2018-02-19 2018-04-09 2018-04-30 2018-06-04 2018-12-01 fixation de prix et à l'élaboration extension in South-East Cote Selection Implementation du cahier de charge pour la mise dIvoire en place d'un mécanisme de traçabilité de flux CI-UC-PSAC-52969-CS-INDV / Component 2: Support to Recrutement d'un consultant smallholder rubber and oil palm Individual Consultant Pending IDA / H8750 Post Open 16,000.00 0.00 2018-03-08 2018-04-26 2018-05-17 2018-06-21 2018-12-18 pour la Formation sur la gestion extension in South-East Cote Selection Implementation des pestes et pesticides dIvoire CI-UC-PSAC-63353-CS-CDS / Recrutement d'un Consultant Component 2: Support to individuel pour la certification de smallholder rubber and oil palm Pending l'opération d'identification des IDA / H8750 Post Direct Selection Direct 20,000.00 0.00 2018-06-01 2018-06-11 2018-08-15 2019-02-11 extension in South-East Cote Implementation producteurs d'hévaé regroupés au dIvoire sein du COP HEVEA de l'APROMAC CI-UC-PSAC-64090-CS-INDV / Recrutement d'un consultant Component1: Promotion of individuel pour l'analyse des public-private partnership for Individual Consultant Pending IDA / H8750 Post Open 75,000.00 0.00 2018-08-02 2018-09-20 2018-10-11 2018-11-15 2019-05-14 expériences de financement des sustainable cocoa development Selection Implementation intrants et propositions d'un in South-West Cote d'Ivoire mécanisme de financements CI-UC-PSAC-64101-CS-CDS / Component1: Promotion of Recrutement d'un cabinet pour la public-private partnership for Pending formation des experts du Conseil IDA / H8750 Post Direct Selection Direct 100,000.00 0.00 2018-06-12 2018-06-22 2018-08-26 2019-02-22 sustainable cocoa development Implementation et de formateurs de cabinets sur in South-West Cote d'Ivoire les outils Scope Insight CI-UC-PSAC-64098-CS-CDS / Component1: Promotion of Recrutement d'un cabinet pour public-private partnership for Pending l'accompagnement financier et IDA / H8750 Post Direct Selection Direct 100,000.00 0.00 2015-12-15 2015-12-25 2016-02-28 2016-08-26 sustainable cocoa development Implementation comptable de l'Union des in South-West Cote d'Ivoire coopératives de la NAWA CI-UC-PSAC-66075-CS-CDS / Recrutement d'un Cabinet pour la Component1: Promotion of é formation de 25 (sociéts public-private partnership for Pending coopératives dans le IDA / H8750 Prior Direct Selection Direct 230,000.00 0.00 2018-06-24 2018-07-04 2018-09-07 2019-03-06 sustainable cocoa development Implementation département de Méagui (Région in South-West Cote d'Ivoire de la NAWA) ED (LE MONT HOREB) Page 3 CI-UC-PSAC-66076-CS-CDS / Recrutement d'un Cabinet po ur la formation de 20 société Component1: Promotion of s coopératives dans le départ IDA / H8750 public-private partnership for Prior Direct Selection Direct 180,000.00 0.00 Pending 2018-06-25 2018-07-05 2018-09-08 2019-03-07 sustainable cocoa development Implementation ement de Buyo (Région de la in South-West Cote d'Ivoire NAWA) ED (CB SYSTEM) CI-UC-PSAC-66077-CS-CDS / Recrutement d'un Cabinet pour la Component1: Promotion of é formation de 25 sociéts public-private partnership for Pending coopératives dans le IDA / H8750 Prior Direct Selection Direct 230,000.00 0.00 2018-06-25 2018-07-05 2018-09-08 2019-03-07 sustainable cocoa development Implementation département de Soubré (Région in South-West Cote d'Ivoire de la NAWA) ED (AMB CONSULTING) CI-UC-PSAC-66080-CS-CDS / Recrutement d'un Cabinet pour la Component1: Promotion of é formation de 20 sociéts public-private partnership for Pending coopératives dans le IDA / H8750 Prior Direct Selection Direct 180,000.00 0.00 2018-06-25 2018-07-05 2018-09-08 2019-03-07 sustainable cocoa development Implementation département de Guéyo (Région in South-West Cote d'Ivoire de la NAWA) ED (AUREX CONSEIL) Page 4