Public Disclosure Copy The World Bank Implementation Status & Results Report Project Preparation Technical Assitance Facility Project (P118610) Project Preparation Technical Assitance Facility Project (P118610) EAST ASIA AND PACIFIC | Vietnam | Transport & ICT Global Practice | IBRD/IDA | Technical Assistance Loan | FY 2010 | Seq No: 11 | ARCHIVED on 17-Nov-2016 | ISR25722 | Implementing Agencies: MPI Key Dates Key Project Dates Bank Approval Date:24-Jun-2010 Effectiveness Date:13-Oct-2010 Planned Mid Term Review Date:08-Apr-2013 Actual Mid-Term Review Date:15-Apr-2013 Original Closing Date:31-Dec-2015 Revised Closing Date:31-Oct-2017 Project Development Objectives Project Development Objective (from Project Appraisal Document) The Project Development Objective is that Government agencies have increased capacity to plan and prepare public investments efficiently and to international quality standards. Project outcomes will include: (a) improved quality at entry, (b) shortened preparation periods and time to realize project benefits, (c) increased capacity within government agencies and the national consulting industry to produce project preparation documents of good quality, to an acceptable schedule. Has the Project Development Objective been changed since Board Approval of the Project Objective? No PHRPDODEL Components Name Component A: Project Preparation Facility:(Cost $94.70 M) Component B: Project Preparation Support and Capacity Building:(Cost $4.70 M) Component C: Incremental Operating Costs and Project Management Expenses:(Cost $0.60 M) Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO  Moderately Satisfactory  Moderately Satisfactory Overall Implementation Progress (IP)  Moderately Satisfactory  Moderately Satisfactory Overall Risk Rating  Moderate  Moderate 11/17/2016 Page 1 of 6 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Project Preparation Technical Assitance Facility Project (P118610) Implementation Status and Key Decisions Project Development Objectives (to increase the capacity of Government entities to plan and prepare public investments efficiently and to international quality standards) remain highly relevant, especially in the context of reduced ODA and concerns about management of ODA in Vietnam. Overall progress has significantly improved, with the project being extended to 31 October 2017 and cancelled an amount of US$11.428 million. Eighteen out of 22 subprojects have been successfully completed by end 2015. US$47.73 million has been disbursed, amounting to 59.6% of the commitment. Through supports under the project, KPIs are meeting the annual targets, with 8 sub-projects having completed 30% detailed designs before Board approval, and 26 detailed design packages having been implemented following international standards for environment and social safeguards. Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance  --  Moderate  Moderate Macroeconomic  --  Moderate  Moderate Sector Strategies and Policies  --  Moderate  Moderate Technical Design of Project or Program  --  Moderate  Moderate Institutional Capacity for Implementation and Sustainability  --  Substantial  Substantial Fiduciary  --  Moderate  Moderate Environment and Social  --  Moderate  Moderate Stakeholders  --  Moderate  Moderate Other  --  --  -- Overall  --  Moderate  Moderate Results Project Development Objective Indicators PHINDPDOTBL Time taken to complete international procurement packages related to civil works in PPTAF financed activities (Months, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 30.00 -- 14.90 12.00 Date 31-Mar-2010 -- 31-Oct-2016 31-Oct-2017 11/17/2016 Page 2 of 6 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Project Preparation Technical Assitance Facility Project (P118610) PHINDPDOTBL  Average time taken from effectiveness to first disbursement from Effectiveness for projects that have used PPTAF funds (Months, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 21.60 -- 6.10 6.00 Date 31-Mar-2010 -- 31-Oct-2016 31-Oct-2017 PHINDPDOTBL  Percentage of PPTAF financed Sub-projects with 30 percent of detailed designs completed before Board approval (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 8.00 36.00 41.00 Date 18-May-2010 03-Mar-2016 31-Oct-2016 31-Oct-2017 PHINDPDOTBL  Percentage of PPTAF financed sub-projects with the "quality of detailed design activities meeting international standards" (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 26.00 0.00 70.00 Date 24-May-2010 03-Mar-2016 03-Mar-2016 31-Oct-2017 Overall Comments Intermediate Results Indicators PHINDIRITBL  Time taken to achieve first disbursement from Effectiveness for projects that have used PPTAF funds (Months, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 21.60 6.00 6.10 6.00 Date 18-Mar-2010 03-Mar-2016 03-Oct-2016 31-Oct-2017 11/17/2016 Page 3 of 6 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Project Preparation Technical Assitance Facility Project (P118610) PHINDIRITBL  Number of PPTAF financed PMUs with experience on WB policies and guidelines before Board approval (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 20.00 22.00 10.00 Date 18-Mar-2010 03-Mar-2016 03-Mar-2016 31-Oct-2017 PHINDIRITBL  Quality of Detailed Design activities financed by PPTAF that met international standards (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target to be evaluated at end to be evaluated at end of to be defined of project, based on the project, based on the during the M&E Value Quality Assessment targets defined during targets defined during support mission the M&E support the M&E support in May 2016. mission in May 2016. mission in May 2016. Date 18-Mar-2010 03-Mar-2016 03-Mar-2016 31-Oct-2017 PHINDIRITBL Time taken to complete international procurement packages related to civil works in PPTAF financed activities (Months, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 30.00 13.60 14.90 12.00 Date 18-May-2010 03-Mar-2016 03-Oct-2016 31-Oct-2017 PHINDIRITBL  Number of officials and project staff under PPTAF financed sub-projects trained on WB fiduciary requirements (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 10.00 430.00 457.00 300.00 Date 18-May-2010 03-Mar-2016 03-Oct-2016 31-Oct-2017 11/17/2016 Page 4 of 6 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Project Preparation Technical Assitance Facility Project (P118610) PHINDIRITBL  Inputs to the development of draft Planning Law (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value N Y Y Y Date 18-May-2010 03-Mar-2016 03-Oct-2016 31-Oct-2017 Overall Comments Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed Disbursed P118610 IDA-47790 Effective XDR 66.20 57.96 8.24 34.59 23.37 60% Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P118610 IDA-47790 Effective 24-Jun-2010 15-Jul-2010 13-Oct-2010 31-Dec-2015 31-Oct-2017 Cumulative Disbursements 11/17/2016 Page 5 of 6 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Project Preparation Technical Assitance Facility Project (P118610) Restructuring History Level 2 Approved on 12-May-2014 ,Level 2 Approved on 28-Dec-2015 Related Project(s) There are no related projects. 11/17/2016 Page 6 of 6 Public Disclosure Copy