Page  1
PROJECT INFORMATION DOCUMENT (PID) 
CONCEPT STAGE 
Report No.:  AB2952 
Project Name 
Irrigation Development Additional Financing 
Region 
EUROPE AND CENTRAL ASIA 
Sector 
Irrigation and drainage (100%) 
Project ID 
P105171 
Borrower(s) 
REPUBLIC OF ARMENIA 
Implementing Agency 
State Committee for Water Management 
Environment Category 
[
]
A
[X] B   [ ] C   [ ] FI   [ ] TBD (to be determined) 
Date PID Prepared 
March 7, 2007 
Estimated Date of 
Appraisal Authorization 
April 23, 2007 
Estimated Date of Board 
Approval 
June 7, 2007 
1.  Key development issues and rationale for Bank involvement 
 
The additional financing is being requested for the purposes described in OP/BP 13.20, which 
are �implementation of 
additional or expanded activities
 that scale up a project�s impact and 
effectiveness�. 
 
As per OP 13.20, the Bank may provide additional financing under the following conditions, 
which are all currently met by the Irrigation Development Project (approved August 30, 2001), 
namely: 
 
�
The project has had an important developmental and institutional impact on Armenia.  
Starting as a pilot program, the Government became convinced of its efficacy, and 
proceeded to roll out a system of 52 Water User Associations (WUAs) throughout the 
country.  To date, irrigated land has increased by about 20%, water losses and energy 
consumption have been significantly reduced, and cost recovery in operations and 
maintenance has risen dramatically. 
 
�
The Implementation Status Report (ISR) ratings from the project�s start, and including 
the most recent 12 month period, have always been �satisfactory� or better, for both 
Implementation Progress (IP) and Development Objectives (DOs). 
 
�
The borrower is deeply committed to the project.  The project was an essential element in 
helping Armenia to establish Water Users Associations (WUAs) throughout the country 
and the Government continues to seek Bank involvement in this sub-sector.  
 
�
All project activities are being implemented by a very competent and highly effective 
Project Implementation Unit (PIU) under the leadership of a capable PIU Director. 
 
Page  2
2. Proposed objective(s) 
 
The additional funds would be provided within the context of the current Development Objective 
of the Irrigation Development Project
�enhancing the profitability and sustainability of irrigated 
agriculture
�
and would simply expand an existing component under the IDP, i.e., the funding 
scheme for rehabilitating tertiary canals.  The expanded activities are of the same nature as those 
already under implementation.  The magnitude and scope could be easily accommodated within 
the context of the existing project without modification of the current implementation 
mechanisms or arrangements.  The activities will be completed within two years of the original 
closing date.  
 
The target goals of the project would need to be only modestly adjusted, mainly increased.  The 
amount of irrigated land and water savings would be increased.  The additional time involved for 
implementation would also enable monitoring a higher level of cost-recovery over time. 
 
(a) 
Increase average farm income in project area;  
(b) 
Increase level and efficacy of O&M activities;  
(c) 
Promote community driven development in the irrigation sub-sector. 
 
3. Preliminary description 
 
Following a preliminary discussion with the Bank team on February 5, 2007, the Government 
requested Additional Financing of US$5.0 million to be used primarily for continuing the 
financing of rehabilitation works on tertiary level irrigation canals.   
 
The need for rehabilitation works of tertiary canals remains high, highlighted by the fact that the 
State Committee for Water Management (SCWM) currently has received an additional sixty two 
proposals for rehabilitation works of tertiaries from WUAs that can not be satisfied due to lack of 
funds under the project. The SCWM has indicated that those additional proposals, if 
implemented, would cover 204 km of tertiary level canals that can provide irrigation water for 
more than 18,000 hectares. The total estimated amount needed for funding these proposals is 
about US$ 10.0 million.  
 
The credit for IDP would therefore increase from about US$ 25.0 million to about US$ 30.0 
million, and  would close in two years as currently scheduled (the closing date has been extended 
by two years, from March 31, 2007 to March 31, 2009, to allow implementation of the additional 
rehabilitation works). 
 
An alternative that could have been considered would have been a full follow-on project at this 
time.  Indeed the original PAD envisaged a phase II program of about $35 million.  However, 
since then several new donors have become involved in the sector.  The Millennium Challenge 
Corporation (MCC) signed a compact in 2006 with Armenia, which could provide about $100 
million for irrigation works.  Also, Armenia recently joined the Asian Development Bank, and 
the ADB is exploring the possibility of supporting the rural sector (although its precise 
interventions are not yet determined).  Funds from both of these new sources have not yet started 
Page  3
flowing and the Government would like to proceed with priority activities under the current IDA 
project to maintain continuity.   The above donors have also indicated their interest in having 
IDA remain engaged in the sector for at least the next few years given our leadership to date in 
institutional and policy issues in the irrigation sector.   
 
This approach to extending the current project by two years with a smaller additional funding has 
therefore been endorsed by the Government and IDA and is provided for in the CAS Progress 
Report which will be discussed by the Board on March 8 2007.   The CAS Progress Report 
indicates that further involvement of IDA in this sector will need to be carefully considered in 
the next CAS, in light of partnership activities.  
 
4.  Safeguard policies that might apply 
[Guideline:  Refer to section 5 of the PCN.  Which safeguard policies might apply to the project 
and in what ways?  What actions might be needed during project preparation to assess 
safeguard issues and prepare to mitigate them?]
 
The project has no unresolved fiduciary, environmental, international waterways, dam safety or 
other safeguard problems.  The proposed additional financing will not raise the environmental 
category of the project nor trigger any new safeguards. The existing Environmental Management 
Plan (EMP) will continue to be applied. To date, compliance with the EMP has been satisfactory. 
 
5. Tentative financing 
Source: ($m.) 
BORROWER/RECIPIENT 0 
International Development Association (IDA) 
5 
Local Farmer Organizations 
.85 
 Total 
5.85 
 
6. Contact point 
Contact: Giuseppe Fantozzi 
Title: Sr Operations Off. 
Tel: 5795+202 
Fax:  
Email: Gfantozzi@worldbank.org 
Location: Rome, Italy (IBRD)