E4484 V1




  Conservancy Adaptation
   Project: Pre-Investment
                   Studies



 Task 4: Coastal Lowlands Drainage Analysis
                    and Works Identification
   Environmental Assessment for Civil Works
                            September 2013

Ministry of Agriculture, Government of Guyana
Conservancy Adaptation
Project: Pre-Investment
Studies
Task 4: Coastal Lowlands
270299         EVT             EES            01              A
Document9
20 February 2013
Environmental     Assessment for Civil Works
Conservancy Adaptation Project
Environmental and Social Management Plan
September 2013



Ministry of Agriculture, Government of Guyana




Mott MacDonald, c/o The British High Commission, 44 Main Street, Georgetown




Mott    MacDonald,    Demeter     House,   Station  Road,   Cambridge         CB1   2RS,   United   Kingdom
T +44 (0)1223 463500 F +44 (0)1223 461007 W www.mottmac.com
Conservancy Adaptation Project: Pre-Investment Studies
Coastal Lolands Environmental Assessment for Civil Works



Issue and revision record
Revision           Date                  Originator         Checker          Approver          Description
A                  16-Sept-13            H Singh            M Taylor         Raymond           Task 4 Deliverable 8
                                                                             Latchmansingh     Final Draft Submission




This document is issued for the party which commissioned it and     We accept no responsibility for the consequences of this
for specific purposes connected with the above-captioned project    document being relied upon by any other party, or being used
only. It should not be relied upon by any other party or used for   for any other purpose, or containing any error or omission
any other purpose.                                                  which is due to an error or omission in data supplied to us by
                                                                    other parties.

                                                                    This document contains confidential information and proprietary
                                                                    intellectual property. It should not be shown to other parties
                                                                    without consent from us and from the party which
                                                                    commissioned it..




270299/EVT/EES/01/A 20 February 2013
Document9
Conservancy Adaptation Project: Pre-Investment Studies
Coastal Lolands Environmental Assessment for Civil Works



Contents

Chapter     Title                                                                                      Page


Executive Summary                                                                                            i


1           Introduction                                                                                    1
1.1         Introduction to the Conservancy Adaptation Project: Pre-Investment Studies _____________________ 1
1.2         Background _______________________________________________________________________ 1
1.3         Project and Task Objectives ___________________________________________________________ 1
1.4         Description of Works and Alternatives Considered _________________________________________ 1
1.4.1       Prioritisation of Drainage Regimes ______________________________________________________ 1
1.4.2       Intervention Options Considered _______________________________________________________ 2
1.4.3       Intervention Options Modelled for Each Area ______________________________________________ 4
1.5         Description of Construction Works to be Undertaken ________________________________________ 6
1.5.1       Summary of Improvement Works Proposed under CAP: Pre-Investment Studies __________________ 6
1.5.2       Liliendaal _________________________________________________________________________ 7
1.5.3       Ogle _____________________________________________________________________________ 8
1.5.4       Montrose La Resouvenir _____________________________________________________________ 9
1.5.5       Mon Repos Annandale ______________________________________________________________ 10
1.5.6       Enterprise Paradise ________________________________________________________________ 11
1.5.7       Beehive _________________________________________________________________________ 12
1.6         EA Methodology ___________________________________________________________________ 13


2           Legal Framework                                                                                14
2.1         Introduction_______________________________________________________________________            14
2.2         Policies __________________________________________________________________________            14
2.2.1       Constitution ______________________________________________________________________            14
2.2.2       National Development Strategy (2001-2010) _____________________________________________        14
2.2.3       National Environmental Action Plan (NEAP) _____________________________________________        14
2.2.4       National Land Use Policy (LUP) _______________________________________________________         15
2.2.5       Low Carbon Development Strategy ____________________________________________________           15
2.3         Legislation _______________________________________________________________________            15
2.3.1       National Drainage and Irrigation Authority (NDIA) Act ______________________________________   15
2.3.2       Environmental Protection Act _________________________________________________________         15
2.3.3       Environmental Protection Regulations __________________________________________________        16
2.3.4       National Environmental Standards _____________________________________________________         16
2.3.5       Occupational Health and Safety Act ____________________________________________________        16
2.4         Institutional Framework _____________________________________________________________          16
2.4.1       National Drainage and Irrigation Authority _______________________________________________     16
2.4.2       Hydro-meteorological Service ________________________________________________________          17
2.4.3       Environmental Protection Agency _____________________________________________________          17
2.4.4       Guyana Lands and Surveys Commission (GLSC) _________________________________________           17


3           Description of Existing Environment                                                            19
3.1         Physical _________________________________________________________________________             19
3.1.1       Description of Coastal Plain __________________________________________________________        19
3.1.2       Physical Characteristics _____________________________________________________________         19
3.1.2.1     Soils ____________________________________________________________________________             19
3.1.2.2     Hydrology/Drainage ________________________________________________________________            20
3.1.3       Climate __________________________________________________________________________             20

270299/EVT/EES/HYES/28/A
Conservancy Adaptation Project: Pre-Investment Studies
Coastal Lolands Environmental Assessment for Civil Works




3.1.3.1     Climate __________________________________________________________________________             20
3.2         Biological ________________________________________________________________________            21
3.2.1       General Description ________________________________________________________________           21
3.2.2       Flora ____________________________________________________________________________             21
3.2.3       Fauna ___________________________________________________________________________              22
3.2.4       Socio-Economic ___________________________________________________________________             22


4           Analysis of Impacts and Possible Mitigations                                                   27
4.1         Potential Environmental and Social Impacts _____________________________________________       27
4.2         Construction Phase – Impacts ________________________________________________________          30
4.2.1       Impacts on the Physical Environment___________________________________________________         30
4.2.1.1     Land/Soil ________________________________________________________________________             30
4.2.1.2     Water ___________________________________________________________________________              31
4.2.1.3     Air ______________________________________________________________________________             33
4.2.2       Impacts to the Biological Environment __________________________________________________       34
4.2.2.1     Flora ____________________________________________________________________________             34
4.2.2.2     Fauna ___________________________________________________________________________              35
4.2.3       Impacts to the Socio-Economic Environment _____________________________________________        35
4.2.3.1     Displacement and Relocation _________________________________________________________          35
4.2.3.2     Drainage _________________________________________________________________________             36
4.2.3.3     Flooding _________________________________________________________________________             36
4.2.3.4     Employment ______________________________________________________________________              36
4.2.3.5     Health and Safety __________________________________________________________________           36
4.3         Potential Impacts during the Operational Phase __________________________________________      37
4.3.1       Maintenance Activities ______________________________________________________________          37


5           Environmental Management Plan                                                                  38
5.1         Environmental Management Organisation _______________________________________________          38
5.2         Responsibility _____________________________________________________________________           39
5.3         Roles and Responsibilities ___________________________________________________________         39
5.3.1       Environmental Officer/Monitor ________________________________________________________         39
5.3.2       Supervisor’s (NDIA) Representative ____________________________________________________        39
5.3.3       Contractor Representative ___________________________________________________________          40
5.3.4       Project Site Meetings._______________________________________________________________          40
5.3.5       Reporting Criteria and Frequency _____________________________________________________         40
5.3.6       Construction Activity to be Assessed ___________________________________________________       41
5.3.7       Assessments _____________________________________________________________________              41
5.3.8       Compliant /Non-compliant Criteria _____________________________________________________        41
5.3.9       Stop Work Authorisation _____________________________________________________________          41
5.3.10      General Environmental Monitor Activities and Deliverables __________________________________   42
5.4         Environmental Assessments _________________________________________________________            42
5.4.1       Pre-Construction/Construction Phase __________________________________________________         42
5.4.2       Post Construction Phase Assessment __________________________________________________          43
5.4.2.1     Reporting ________________________________________________________________________             44
5.4.2.2     Services not provided by the General Environmental Monitor ________________________________    44
5.4.3       Environmental Protection Agency _____________________________________________________          44


6           Proposed Mitigation Measures                                                                   45
6.1         Impact Mitigation __________________________________________________________________           45
6.1.1       Erosion and Compaction ____________________________________________________________            45
6.1.2       Fisheries and Watercourses __________________________________________________________          46
6.1.3       Dewatering _______________________________________________________________________             46


270299/EVT/EES/HYES/28/A
Conservancy Adaptation Project: Pre-Investment Studies
Coastal Lolands Environmental Assessment for Civil Works




6.1.4       Noise ___________________________________________________________________________                  46
6.1.5       Dust ____________________________________________________________________________                  47
6.1.6       Fuel, Lubricants and Chemicals _______________________________________________________             47
6.1.7       Waste Management ________________________________________________________________                  47
6.1.8       Health and Safety __________________________________________________________________               47
6.2         Specific Management Plans __________________________________________________________               48
6.2.1       Erosion and Sediment Control Plan ____________________________________________________             48
6.2.1.1     Purpose and Scope ________________________________________________________________                 48
6.2.1.2     Sediment Control and Water Quality ___________________________________________________             48
6.2.1.3     Riparian Areas ____________________________________________________________________                48
6.3         Erosion Control ____________________________________________________________________               48
6.4         Sediment Control __________________________________________________________________                49
6.4.1       Culvert/Bridges Sites _______________________________________________________________              50
6.4.2       Flooding _________________________________________________________________________                 50
6.5         Specific Areas of Concern ___________________________________________________________              50
6.5.1       Erosion and Sediment Control Recommendations for Specific Areas __________________________         50
6.5.1.1     Environmentally Sensitive Area _______________________________________________________             50
6.6         Grading and Topsoil Protection _______________________________________________________             50
6.7         Waste Management Plan ____________________________________________________________                 51
6.7.1       Purpose and Scope ________________________________________________________________                 51
6.7.2       Waste Management Practices ________________________________________________________                51
6.7.2.1     Open burning _____________________________________________________________________                 52
6.7.2.2     Strippings ________________________________________________________________________                52
6.7.2.3     Waste Oils and Special Wastes _______________________________________________________              52
6.7.2.4     Concrete Wastes __________________________________________________________________                 52
6.7.2.5     Food Waste ______________________________________________________________________                  53
6.8         Fuel and Lubricants Management _____________________________________________________               53
6.8.1       Purpose and Scope ________________________________________________________________                 53
6.8.2       Spill Response Plan ________________________________________________________________               53
6.8.3       Reporting of Spills _________________________________________________________________              53
6.8.4       Minor Spills _______________________________________________________________________               54
6.8.5       Major Spills _______________________________________________________________________               54
6.8.6       Spill Response Equipment ___________________________________________________________               54
6.9         Spill Conditions ____________________________________________________________________              54
6.9.1       Solid Material Spill in a Dry Area ______________________________________________________          54
6.9.2       Liquid Material Spill in a Dry Area______________________________________________________          54
6.9.3       Solid Material Spill in an Area Wet from Rain _____________________________________________        54
6.9.4       Liquid Material Spill in an Area Wet from Rain ____________________________________________        55
6.9.5       Solid or Liquid spill in a Drainage Ditch _________________________________________________        55
6.10        Specific Materials on Construction Projects ______________________________________________         55
6.10.1      Petrol/Gasoline ____________________________________________________________________               55
6.10.2      The initial response to petrol/gasoline spill will be: _________________________________________   55
6.10.3      In the event of a fire, the response will be: _______________________________________________      55
6.10.4      Petrol/ gasoline can be disposed of in the following manner: _________________________________     56
6.10.5      Other Fuels and Petroleum Products ___________________________________________________             56
6.10.6      Fuel spills on land will be responded to by the following procedures: __________________________   56
6.10.7      Fire response methods for diesel fuel include: ____________________________________________        56
6.10.8      Concrete and/or Concrete Wastewater _________________________________________________              57
6.10.9      Acid Spills ________________________________________________________________________               57
6.11        Traffic Management Plan ____________________________________________________________               58
6.12        Closure Plan ______________________________________________________________________                60
6.16        Community Relations _______________________________________________________________                60
6.17        Workers Training Program ___________________________________________________________               60



270299/EVT/EES/HYES/28/A
Conservancy Adaptation Project: Pre-Investment Studies
Coastal Lolands Environmental Assessment for Civil Works




7             Health, Safety and Welfare during Construction                                                    61
7.1           Management of Health and Safety _____________________________________________________             61
7.1.1         Health and Safety Plan ______________________________________________________________             61
7.1.2         Health and Safety Risk Assessment and Identification of Mitigation Measures ___________________   61
7.1.3         Health and Safety Training for Workers _________________________________________________          62
7.1.4         Site Inductions ____________________________________________________________________              63


8             References                                                                                        64


Appendices                                                                                                  65
Appendix A.   Example Forms ___________________________________________________________________                 66
A.1.          Daily Environmental Inspection Summary - Construction ____________________________________        66
A.2.          Weekly Environmental Inspection Summary - Construction __________________________________         68
A.3.          Monthly Environmental Inspection Summary - Construction _________________________________         70
A.4.          Quarterly Environmental Inspection Summary - Construction ________________________________        72
A.5.          Corrective Action Report ____________________________________________________________             73
A.6.          Post Environmental Inspection Summary - Construction ____________________________________         74
Appendix B.   Example Health and Safety Risk Assessment ____________________________________________            76
Appendix C.   Correspondence Regarding Drainage Regime Modelling ___________________________________            82




270299/EVT/EES/HYES/28/A
Conservancy Adaptation Project: Pre-Investment Studies
Coastal Lolands Environmental Assessment for Civil Works



Acronyms

ECD             East Coast Demerara
EIA             Environmental Impact Assessment
EMC             Environmental Management Consultants
EMP             Environmental Management Plan
EPA             Environmental Protection Agency
GD              Georgetown Datum
GFC             Guyana Forestry Commission
GLSC            Guyana Lands and Surveys Commission
GNBS            Guyana National Bureau of Standards
GoG             Government of Guyana
GPL             Guyana Power and Light Company
GTT             Guyana Telephone and Telegraph Company
GWI             Guyana Water Incorporated
LCDS            Low Carbon Development Strategy
LUP             Land Use Policy
MoA             Ministry of Agriculture
MoPWC           Ministry of Public Works and Communications
NARI            National Agricultural Research Institute
NBAP            National Biodiversity Action Plan
NDC             Neighbourhood Democratic Council
NDIA            National Drainage and Irrigation Authority
NDS             National Development Strategy
NEAP            National Environmental Action Plan
NICIL           National Industrial and Commercial Investments Limited
PPE             Personal Protective Equipment
RDC             Regional Democratic Council




270299/EVT/EES/HYES/28/A
Conservancy Adaptation Project: Pre-Investment Studies
Coastal Lolands Environmental Assessment for Civil Works



Executive Summary

The Global Environmental Facility (GEF), under the Special Climate Change Fund (SCCF), have
provided the grant which has funded the Conservancy Adaptation Project: Pre-Investment Studies.
The project aims to strengthen government and donor understanding of the East Demerara Water
Conservancy (EDWC) system and coastal drainage patterns through the integration of advanced
mapping and engineering analysis. The project also aims to carry out the design of infrastructure
investments to improve drainage performance within the Region 4 coastal lowlands, to improve the
stability of the EDWC dam, to strengthen the institutional capacity for managing water and floodwater
levels, and to guide interventions to reduce Guyana’s vulnerability to floods.

A key challenge facing the country, particularly residents living on the coast is the management of its
poor drainage infrastructure for flood control. Over the last decade, extreme weather conditions have
become more frequent and the prognosis is for this trend to continue. Over the two years from 2004 to
2006, flood events slowed agricultural production and personal losses have been significant. There
are severe limitations in the ability to prevent flooding and manage flood waters and the impact of land
use changes has clearly damaged the flood control drainage infrastructure. At present, flood control is
managed on an emergency basis and control efforts focused on responding to immediate needs
rather than the development of long-term control strategies.

The objective of the Conservancy Adaptation Project: Pre-Investment Studies is to: ‘help the GoG
adapt to global climate changes by reducing the country’s vulnerability to catastrophic flooding.
Specific project objectives include: …. c) identifying key drainage regimes for follow-on intervention….’

The objective of Task 4: Coastal Lowlands Drainage Analysis and Works Identification is to ‘provide a
comprehensive model and framework of evaluation for the management of flood waters and seek to
define the existing drainage system and recommend interventions designed to mitigate future
flooding.’

The project is expected to provide a number of long and short terms benefits including a reduction in
flooding potential and subsequent loss of livelihood. An assessment has been carried out on the
impacts of the project on the environment. Physical, biological and social mitigation measures have
been provided to lessen or reduce the impacts of the project. Negative impacts of the project include
dust and noise nuisance, minor disturbance to drainage and irrigation, traffic and nearby residents and
the possibility of erosion, sedimentation. Negative impacts are short term and are limited to the
construction phase of the project. Overall the projects benefits will be positive, the project will improve
the existing drainage infrastructure and create short term employment and also create other spin off
economic benefits.

Mitigation measures are presented to address the negative externalities of the project and a
monitoring framework is provided to guide the execution of the EMP (Section 5). Overall the project
will ‘help the GoG adapt to global climate changes by reducing the country’s vulnerability to
catastrophic flooding’.




     270299/EVT/EES/01/A 20 February 2013
i    Document9
Conservancy Adaptation Project: Pre-Investment Studies
Coastal Lolands Environmental Assessment for Civil Works



1        Introduction

1.1      Introduction to the Conservancy Adaptation Project: Pre-Investment Studies

The Global Environmental Facility (GEF), under the Special Climate Change Fund (SCCF), has provided
the grant which has funded the Conservancy Adaptation Project: Pre-Investment Studies. The project
aims to strengthen government and donor understanding of the East Demerara Water Conservancy
(EDWC) system and coastal drainage patterns through the integration of advanced mapping and
engineering analysis. The project also aims to carry out the design of infrastructure investments to improve
drainage performance within the Region 4 coastal lowlands, to improve the stability of the EDWC dam, to
strengthen the institutional capacity for managing water and floodwater levels, and to guide interventions to
reduce Guyana’s vulnerability to floods.

1.2      Background

The coastal strip of Region 4 is very low-lying, with ground levels up to 1.8m below mean sea level. It has
been estimated that sea level in the area is rising at a rate of 1cm a year and this, combined with the high
foreshore levels and mobile sand banks local to the coast, is making the area ever more reliant on pumped
drainage to outlet the accumulated rain water.

The drainage systems currently in operation in the area were designed and implemented in order to
provide drainage for the cane fields to the south of the urbanised areas. They were never intended as
urban drainage systems, and as more housing developments have been constructed in the area the
existing drainage systems have been subject to severe stress. This has meant that there is now frequent
incidence of flooding in the urban areas.

1.3      Project and Task Objectives

The objective of the Conservancy Adaptation Project: Pre-Investment Studies is to: ‘help the GoG adapt to
global climate changes by reducing the country’s vulnerability to catastrophic flooding. Specific project
objectives include: …. c) identifying key drainage regimes for follow-on intervention….’

The objective of Task 4: Coastal Lowlands Drainage Analysis and Works Identification is to ‘provide a
comprehensive model and framework of evaluation for the management of flood waters and seek to define
the existing drainage system and recommend interventions designed to mitigate future flooding.’

1.4      Description of Works and Alternatives Considered

1.4.1    Prioritisation of Drainage Regimes

In order to prioritise key areas for analysis and to rationalise the amount of modelling the GoG requested
that the drainage areas along the East Coast Demerara would be subject to a multi criterion analysis in
order to determine priority areas for further study. This process has been reported in the CAP: Pre-
Investment Studies Task 4 Selection Document, Issue B, April 2012. As a result of this process the
following drainage regimes were taken forward for further study, as agreed with the GoG (see Appendix
C).
1. Liliendaal             (Liliendaal Drainage Area Model)
2. Ogle                   (Ogle Drainage Area Model)



270299/EVT/EES/HYES/28/A                         1
Conservancy Adaptation Project: Pre-Investment Studies
Coastal Lolands Environmental Assessment for Civil Works



3.    Montrose             (Montrose Drainage Area Model)
4.    Sparendaam           (Montrose Drainage Area Model)
5.    Mon Repos            (Mon Repos Drainage Area Model)
6.    Annandale            (Mon Repos Drainage Area Model)
7.    Strathspey           (Enterprise Drainage Area Model)
8.    Enterprise           (Enterprise Drainage Area Model)
9.    Paradise             (Enterprise Drainage Area Model)
10.   Beehive              (Beehive Drainage Area Model)
11.   Clonbrook            (Beehive Drainage Area Model)

In order to account for cross linkages between adjacent regimes, these eleven drainage regimes were
combined to form six drainage areas for the purposes of modelling.

Once the baseline hydraulic models for these areas had been developed (see CAP: Pre-Investment
Studies Task 4 Modelling Report, Issue B, February 2013), several options were considered for
interventions to improve the existing drainage relief systems.

The Terms of Reference states that: ‘the contractor shall develop and test using the model a series of
recommendations for 10 to 15 drainage works in Region 4, designed to mitigate potential future regional
flooding, prioritize these works, cost and develop contractor terms of reference for the execution of these
works. Works and designs shall be developed to maximise the use of existing structures and systems,
gravity-based drainage methods, and to minimize the use of pumps as drainage control where possible.
The works selected shall seek to avoid involuntary relocation of affected individuals and shall strictly avoid
any projects that may require interventions to the EDWC dam.’

1.4.2     Intervention Options Considered

For each of the drainage regimes the following intervention options were considered:
1. Increased gravity outfall capacity
2. Increased pump capacity
3. Excavation to increase capacity of primary drains
4. Reconstruction of culverts to remove local constrictions on primary drains
5. Creation of additional flood storage
6. Separation of urban and agricultural drainage

Each drainage area was considered in turn and the relative merit of each of the above options was
considered. Specific options for model testing were then developed for each drainage area, and refined
following initial model test run results.

Increased Gravity Outfall Capacity

The Terms of Reference state that: ‘the contractor shall model the system assuming a 0.5m rise in mean
sea level anticipating continued effects of global climate change.’ As such, with the tidal window for gravity
discharge of drainage waters already short, the possibility for gravity drainage becomes unfeasible in
almost all areas along the coast. Initial inspection of the drainage area models showed that Enterprise is
the only area in which increased gravity drainage was a viable option. For Enterprise Drainage Area we
did take the increased capacity of the gravity outfall forward to further study using the model, but it was
shown to be less effective than other options for the improvement of the drainage relief capacity.




270299/EVT/EES/HYES/28/A                          2
Conservancy Adaptation Project: Pre-Investment Studies
Coastal Lolands Environmental Assessment for Civil Works



Increased Pump Capacity

The pumps currently in operation along the coast of Region 4 typically have a capacity such that they are
able to discharge around flow comparable with a daily rainfall of around 54mm/day. (Liliendaal is slightly
higher at 76mm/day). This is consistent with a 1 in 5 year event. Providing a level of service for a 1:5
year event would be generally considered acceptable for agricultural areas, but for urbanised areas where
flooding can be tolerated less often, a 1 in 50 year event is more appropriate. As such a considerable
increase in pumping capacity would be required to achieve a level of service of 1 in 50 years.

For this reason, despite the caution against providing additional pumping stated in the Terms of Reference,
with increased gravity outfall rendered unfeasible with the onerous climate change criteria we have had to
consider the option of additional pump capacity in all areas, though we have sought to reduce the extent to
which this is used as much as possible.

Excavation to Increase the Capacity of Primary Drains

The baseline models were used to identify any evidence of constrictions to flow caused by undersized
primary drains. This information, in conjunction with anecdotal evidence from stakeholder discussions,
was used to identify specific drains, which were increased in the model to determine the effect of these
channel widenings on the overall discharge characteristics of the area.

It should be noted that while seemingly a simple and obvious solution, channel widenings of this nature are
in practice costly and difficult to carry out. In some instances where space is constrained they can lead to
land ownership issues. These considerations have been taken into account while assessing the different
options tested by the models.

Reconstruction of Culverts to Remove Local Constrictions on Primary Drains

The model was also used to identify localised constrictions, such as undersized culverts and bridges, and
verified with site surveys and anecdotal evidence from stakeholders. The effect of increasing capacity at
these constrictions was tested using the model. In practice the culverts identified were often those
associated with the main Railway and Public Roads. As such the costs of diverting traffic was built into the
associated costs when determining the feasibility of carrying out these works.

Creation of Additional Flood Storage

By creating storage upstream of the pumped or gravity outlet it is often possible to reduce the required
peak flow drainage capacity, allowing the accumulated rainfall to be discharged into the Atlantic more
slowly without causing flooding. The creation of flood storage areas has been considered in most areas,
however the dense ongoing development of the East Coast Demerara has meant that available space for
such storage ponds has been hard to identify.

While this is often a relatively inexpensive and effective option, it will have an inevitable consequence on
development planning in the area, as areas designated for flood storage will not be available for
development. This has been considered when assessing possible options for drainage improvements in
each area.

Separation of Urban and Agricultural Drainage

As noted above, it is generally recognised that short term flooding can be tolerated more often in
agricultural areas than in urban areas. It is general international practice to design agricultural drainage




270299/EVT/EES/HYES/28/A                         3
Conservancy Adaptation Project: Pre-Investment Studies
Coastal Lolands Environmental Assessment for Civil Works



systems to a level of service sufficient to discharge the 1 in 5 year event, but to apply more onerous
conditions, such as the 1 in 25, 1 in 50 or even 1 in 100 year events to drainage systems for urban areas.

As such we have looked at the option of restricting the flow from the agricultural areas to an amount
sufficient to discharge the 1 in 5 year accumulated rainfall. This will mean that in more extreme events
flooding will be permitted within the agricultural areas. These constrictions would be supplemented with
improvements to the downstream drainage systems so that a greater level of service could be achieved in
the urbanised areas.

It should be noted that this option should not lead to more frequent flooding in the agricultural areas, but
will lead to significantly less flooding in the urban areas.

This option has generally been found to be very effective, and is also comparably inexpensive and would
lead to less necessity for the addition of more pump capacity. However, it is recognised that it may be
initially unpopular with farmers and other stakeholders, so that while it would be technically a very good
alternative, a good deal of preparatory work would be required before implementation to ensure it is
accepted by all stakeholders. It is also worth noting that it would be more effective and less costly if one
project to separate the urban and agricultural drainage all the way along the coast could be carried out as
a single holistic project.

1.4.3    Intervention Options Modelled for Each Area

The specific options for each area which were taken forward to further study using the hydraulic models
were developed following inspection of the baseline model results. They were then assessed in terms of
the urbanised area which would currently be inundated during the 1 in 50 year event, but would remain dry
following the implementation of the proposed intervention option. This area was compared with the cost of
implementation to give a cost per urbanised hectare benefited.

Table 1.1 shows the options which were assessed using the hydraulic models. Those options highlighted
in yellow are the ones which would create the greatest benefit (in terms of urbanised area which would
remain un-inundated) for the least cost. These are the options which we recommend are taken forward to
design and implementation.




270299/EVT/EES/HYES/28/A                         4
Conservancy Adaptation Project: Pre-Investment Studies
Coastal Lolands Environmental Assessment for Civil Works



Table 1.1:  Summary of Options Modelled
 Drainage      Options
 Areas         Option 1               Option 2                 Option 3                Option 4                Option 5               Option 6
               Additional Pumping     Additional Pumping
                                                               No Additional Pumping
               (8.5m3/s)              (4.5m3/s)
               Increased culvert      Increased culvert        Increased culvert
 Liliendaal
               capacities             capacities               capacities
                                      Channel widening         Channel widening
                                      Additional storage       Additional storage
                                                               Additional Pumping      Additional Pumping
               Additional Pumping      Additional Pumping
 Ogle                                                          (6m3/s)                 (10m3/s)
               (6m3/s)                 (10m3/s)
                                                               Culvert Improvements    Culvert Improvements
                                       Additional Pumping                              Additional Pumping
 Montrose                                                      No Additional Pumping
               Additional Pumping      (14m3/s)                                        (14m3/s)
 La
               (14m3/s)                                        Restriction of          Restriction of
 Resouvenir                            Offline Storage
                                                               Agricultural Drainage   Agricultural Drainage
               Additional Pumping      Additional Pumping      Additional Pumping      Additional Pumping
               (12m3/s)                (7.5m3/s)               (12m3/s)                (10m3/s)
 Mon Repos     Small Channel           Restriction of          Small Channel           Small Channel
 Annandale     Modifications           Agricultural Drainage   Modifications           Modifications
                                                               Widening façade drain   Widening façade drain
                                                               to increase storage     to increase storage
               Additional Pumping      Additional Pumping
                                                               (Option 2b in Report)   (Option 2c in Report)   (Option 3 in Report)   (Option 4 in Report)
               (38m3/s)                (38m3/s)
                                                               Additional Pumping      Additional Pumping      No additional          Additional Pumping
 Enterprise    Channel Modifications   Channel Modifications
                                                               (24m3/s)                (29m3/s)                pumping                (13m3/s)
 Paradise
                                       Offline Storage         Channel Modifications   Channel Modifications   Additional Kokers      Channel Modifications
                                                                                                                                       Restriction of
                                                               Offline Storage         Offline Storage
                                                                                                                                      Agricultural Drainage
                                       Additional Pumping                              Additional Pumping      Additional Pumping
                                                               No Additional Pumping
                                       (8.5m3/s)                                       (4.25m3/s)              (12.75m3/s)
 Beehive       Additional Pumping                                                                              Channel
                                       Channel Modfications    Channel Modifications   Channel Modifications
 Clonbrook     (4.25m3/s)                                                                                      Modifications
                                                               Restriction of          Restriction of
                                                                                                               Offline Storage
                                                               Agricultural Drainage   Agricultural Drainage




270299/EVT/EES/HYES/28/A                            5
Conservancy Adaptation Project: Pre-Investment Studies
Coastal Lolands Environmental Assessment for Civil Works




1.5          Description of Construction Works to be Undertaken

1.5.1        Summary of Improvement Works Proposed under CAP: Pre-Investment Studies

The following table shows the works identified as being required to improve the drainage conditions along
the coast, and those which will be designed under the current CAP.

Table 1.2:     Table of Works Required in Coastal Areas




Source:   MM




270299/EVT/EES/HYES/28/A                             6
Conservancy Adaptation Project: Pre-Investment Studies
Coastal Lolands Environmental Assessment for Civil Works




1.5.2      Liliendaal

The proposed works at Liliendaal include the following:
   Construction of new pump station adjacent to existing Liliendaal Pump Station

Figure 1.1:   General Arrangement of Proposed Works at Liliendaal




Source:   CEMCO




270299/EVT/EES/HYES/28/A                            7
Conservancy Adaptation Project: Pre-Investment Studies
Coastal Lolands Environmental Assessment for Civil Works




1.5.3     Ogle

The proposed works at Ogle include the following:
   Construction of new pump station adjacent to existing Ogle Pump Station
   Heightening of embankments either side of channel downstream of Pump Station

Figure 1.2:    General Arrangement of Proposed Works at Ogle




Source:   MM




270299/EVT/EES/HYES/28/A                            8
Conservancy Adaptation Project: Pre-Investment Studies
Coastal Lolands Environmental Assessment for Civil Works




1.5.4     Montrose La Resouvenir

The proposed works at Montrose include the following:
   Restriction of Agricultural Drainage

Figure 1.3:    General Arrangement of Proposed Works at Montrose




Source:   MM




270299/EVT/EES/HYES/28/A                           9
Conservancy Adaptation Project: Pre-Investment Studies
Coastal Lolands Environmental Assessment for Civil Works




1.5.5     Mon Repos Annandale

The proposed works at Mon Repos Annandale include the following:
   Construction of new pump station adjacent
   Restriction of Agricultural Drainage

Figure 1.4:    General Arrangement of Proposed Works at Mon Repos Annandale




Source:   MM




270299/EVT/EES/HYES/28/A                           10
Conservancy Adaptation Project: Pre-Investment Studies
Coastal Lolands Environmental Assessment for Civil Works




1.5.6     Enterprise Paradise

The proposed works at Enterprise Paradise include the following:
                                                                                               3
   introduction of two new pumping stations (Location 1 and Location 2) with capacities of 1.5m /s and
       3
   9m /s respectively
                                                                                                    3
   increase in the pumping capacity of the Hope pumping station (Location 3) with additional 1.5m /s
   capacity
   complete separation of urban and agricultural drainage areas with agricultural areas served by the
   existing Strathspey and Foulis pumping stations
   channel modifications to feed new and modified pump stations

Figure 1.5:    General Arrangement of Proposed Works at Enterprise Paradise




Source:   MM




270299/EVT/EES/HYES/28/A                            11
Conservancy Adaptation Project: Pre-Investment Studies
Coastal Lolands Environmental Assessment for Civil Works




1.5.7     Beehive

The proposed works at Enterprise Paradise include the following:
  no increase in pumping capacity
  widening and deepening of the main drain leading to the pumping station
  restriction of discharge from vegetated areas to a drainage rate to 40 mm/day both with and without
  additional pump

Figure 1.6:   General Arrangement of Proposed Works at Beehive




270299/EVT/EES/HYES/28/A                          12
Conservancy Adaptation Project: Pre-Investment Studies
Coastal Lolands Environmental Assessment for Civil Works




1.6      EA Methodology

This EA has been prepared using the national guidelines for preparation of Environmental Impacts
Assessments as set out by the EPA.

The methodology applied for this project may be loosely categorised as follows.
   Site Reconnaissance Visits
   Discussions with various stakeholders (residents, officials, and other groups)
   Review of Secondary sources of information
   Observation of Land Use in the project area of influence.
   Assessment of Environmental impacts of implementing project and recommended actions associated
   with projects of similar nature.
   Assess alternative options to this project.
   Review all relevant laws and guidelines that define the implementation of the project.




270299/EVT/EES/HYES/28/A                      13
Conservancy Adaptation Project: Pre-Investment Studies
Coastal Lolands Environmental Assessment for Civil Works



2         Legal Framework

2.1       Introduction

Several policies, laws and regulations specific to areas of environmental management will bear on the
construction activities for the coastal lowlands as proposed by the Conservancy Adaptation Project: Pre-
Investment Studies. As a matter of policy, the Environmental Protection Agency requires an environmental
permit for projects listed in the fourth schedule of the EPA Act (1996) that would have a significant impact
on the environment. As such there is a statutory requirement for conducting an EIA for this project. In this
section the relevant policies, statutory requirement and guideline that would impact on the environmental
assessment process of this proposed project are outlined.

2.2       Policies

2.2.1     Constitution

The need for a national environmental policy for Guyana has its foundations within the 1980 Constitution in
Articles 2:25 and 2:36.

Article 2:25 of the Constitution states that “every citizen has a duty to participate in activities to improve the
environment and protect the health of the nation”. And Article 2:36 states that “in the interest of the present
and future generations the state will protect rational use of its flora and fauna and will take all appropriate
measures to conserve and improve the environment”.

2.2.2     National Development Strategy (2001-2010)

GoG’s policy commitment to environmental management and sustainable development is emphasised in
the National Development Strategy (NDS). The NDS supports an accelerated growth process involving the
participation of the wider society, as well as, defining the need for environmental protection to be treated as
a cross-sectoral issue applied to all aspects of the development process.

2.2.3     National Environmental Action Plan (NEAP)

The GoG’s environmental policy was first identified within the National Environmental Action Plan (NEAP)
(1994). The plan presented a 12-point National Environmental Policy reflecting sound principles of
environmental management and the ideal of sustainable development. A programme of action over a 3-
year period was identified to address priority environmental issues.

The second NEAP (2001-2005) is a continuation of NEAP (1994), setting out the “environmental
development strategy for Guyana for the next five years” and “a framework for integrating cross-sectoral
environmental concerns in the broader context of the country’s economic and social development
programme”. The Action Plan outlines a further commitment to sustainable development and a thematic
approach to environmental protection. The implementation strategy for NEAP involves the identification of
programme areas according to sectors and cross-sectors and tools and actions for implementation.




270299/EVT/EES/HYES/28/A                            14
Conservancy Adaptation Project: Pre-Investment Studies
Coastal Lolands Environmental Assessment for Civil Works




2.2.4    National Land Use Policy (LUP)

The National Land Use Policy (LUP) aims to streamline land use planning and to create conditions
necessary to achieve types of land uses which are sustainable, socially desirable and environmentally
compatible. The LUP and the National Land Use Plan are prepared by the Guyana Lands and Surveys
commission (GLSC).

The Commission aims to also prepare regional plans for specific Administrative Regions of Guyana. To-
date the Commission has prepared two (2) Regional Land Use Plans: (i) Region 6 – East Berbice Regional
Land Use Plan; and (ii) Region 9 – Rupununi Sub Region 1. Additionally, Corridor Land Use Plans for the
Lethem – Linden and Linden to Soesdyke road corridors have been prepared.

2.2.5    Low Carbon Development Strategy

The Government of Guyana in 2009 launched a Low Carbon Development Strategy (LCDS). The LCDS
aims to transform Guyana’s current economy to that of a “low carbon economy” while addressing issues
related to climate change through a compensatory scheme by marketing Guyana’s standing forest. The
strategy is built on Guyana’s vision to encourage investments/economic development while protecting and
maintaining its forest cover. The strategy has three pillars: (i) investment in low carbon economic
infrastructure; (ii) investment and employment in low carbon economic sectors; and (ii) investment in
communities and human capital.

2.3      Legislation

2.3.1    National Drainage and Irrigation Authority (NDIA) Act

The Drainage and Irrigation Act of 2004 provided for the establishment of NDIA. NDIA is the regulatory and
co-ordinating agency responsible for the operation, maintenance, control and management of the drainage
and irrigation and flood control system and works and harmonising of activities to enhance agricultural
production. The Act provides mechanisms for ensuring that existing drainage and irrigation system and
flood control and any new expansion that are done, are operated and maintained in a sustainable manner.
The Act also allows for public participation in the planning, management and operation of drainage and
irrigation facilities through Water Users’ Associations and promotes and encourages the involvement of the
private sector in the construction, management, operation and maintenance of drainage and irrigation and
flood control systems. The NDIA Act also provides for cost recovery for the sustainable management of
primary and secondary elements of drainage and irrigation systems and flood control. Generally, the Act
provides for the development of an institutional structure in terms of water resources management strategy
and water use planning for the primary purpose of locating, evaluating, conserving and distributing water
resources of the country for agricultural purposes.

2.3.2    Environmental Protection Act

The Environmental Protection Act of 1996 is the first comprehensive environmental legislation in Guyana.
The Act established the EPA. The goal of the Act is to “provide for the management, conservation,
protection and improvement of the environment, the prevention and/or control of pollution, the assessment
of the impact of economic development on the environment, the sustainable use of natural resources and
for matters incidental thereto connected therewith”. The EP Act gives the EPA the mandate for the
coordination of environmental management and outlines the legal process for undertaking sustainable and
effective management of the natural environment.




270299/EVT/EES/HYES/28/A                        15
Conservancy Adaptation Project: Pre-Investment Studies
Coastal Lolands Environmental Assessment for Civil Works



The EPA administers the EIA process set out in Part IV of the Act. The Act requires that an EIA be
conducted prior to authorization of any project, which may significantly affect the environment. The Act also
requires measures to be implemented to prevent environmental pollution. Part V Section 19 (1) states that
“A person shall not (a) Undertake an activity that causes or is likely to cause pollution of the environment
unless the person takes all reasonable and practicable measures to prevent or minimize any resulting
adverse effect; (b) Discharge or cause or permit the entry into the environment of any contaminant in any
amount, concentration or level in excess of that prescribed by the regulations or stipulated by an
environmental authorization.” A nature would require environmental authorization under the EP Act.

2.3.3    Environmental Protection Regulations

The Environmental Protection Regulations, made under the Environmental Protection Act, were gazetted
in 2000. These regulations govern Water Quality, Noise, Air Quality and Hazardous Waste Management
and are aimed at preventing pollution by regulating discharges and emissions. These pollution
management regulations will regulate and control the activities of developmental projects such as forestry
operations during construction and operation. Under the Noise Management Regulation, persons cannot
carry out activities above the established noise limits without prior approval from The EPA. The Water
Quality Regulation protects Guyana’s water by controlling discharges of waste matter into any of the
coastal and inland waters or land. The Hazardous Waste Management Regulation protects Guyana’s
environment from hazardous waste generated including industrial waste, clinical wastes from hospitals,
etc. The Air Quality Regulations requires emissions to be below a level so as to not affect the health of
plants, animals and humans.

2.3.4    National Environmental Standards

The Environmental Protection Regulations requires the EPA to develop limits for various parameters. The
EPA has so far, in collaboration with the Guyana National Bureau Standards (GNBS), developed the
following standards and which are applicable to this project and should be complied with:
     Interim Guideline for Industrial Effluent Discharge into the Environment. (Water Quality Standard); and
     Interim Guideline for Noise Emission into the Environment. (Noise Standard).

2.3.5    Occupational Health and Safety Act

This Act deals with the regulation and registration of workplaces and the occupational health and safety of
workers. It gives authorisation for occupational health and safety inspectors to enter and inspect
workplaces. Under this Act the employer has a responsibility of ensuring workers health and safety is
maintained. The Act requires the employer to display publicly an abstract of the Act, and other sections
addressing various issues addressed in the Act. Construction workers are required to be trained and be
equipped with the necessary personal protective equipment.

2.4      Institutional Framework

There are a number of Government Agencies and Institutions that have some oversight regarding the
construction of the EDWC northern relief channel. These agencies are discussed below:

2.4.1    National Drainage and Irrigation Authority

The NDIA was established by the NDIA Act of 2004. The NDIA has a major role to play regarding the
country’s drainage, irrigation and flood control facilities and agricultural production. The NDIA is
responsible for coordinating the operation and maintenance of drainage and irrigation activities including



270299/EVT/EES/HYES/28/A                         16
Conservancy Adaptation Project: Pre-Investment Studies
Coastal Lolands Environmental Assessment for Civil Works



managing, operating and maintaining of drainage and irrigation systems and related access roads and
facilities. The NDIA is also responsible for the development of programmes and plans to locate, evaluate,
conserve and distribute water resources for agricultural development and for the efficient management,
operation, evaluation and monitoring of drainage and irrigation systems. Importantly, the Authority is
responsible for the development of procedures, norms, standards including irrigation and environmental as
well as operation schedules for the efficient operation and maintenance of the drainage and irrigation
systems.

2.4.2     Hydro-meteorological Service

The Hydro-meteorological Service (HYDROMET) is a department under the Ministry of Agriculture.
HYDROMET operates the National Meteorological Station Network (NMSN) and the National Hydrological
Station Network (NHSN) and evaluates the climate and water resources. HYDROMET collect baseline
data and archive information on Guyana's weather and climate and provide meteorological, hydrological
and oceanographic services. The agency provides information to those agencies that are planning and
designing agricultural and water development projects, and maintaining the sea defences. It also serves as
a warning system for the country and supports national and international obligations.

2.4.3     Environmental Protection Agency

The EPA was established under the Environmental Protection Act of 1996. The Agency is governed by a
Board of Directors, but falls under the direct supervision of the Office of the President. In Sec. 4 (1) (a), of
the Act, the EPA is given the mandate to “take such steps as are necessary for the effective management
of the natural environment so as to ensure conservation, protection and sustainable use of its natural
resources”. In addition the Agency is given the overall responsibility to:
    Take necessary steps for effective management of the natural environment to ensure conservation,
    protection and sustainable use of its natural resources;
    Ensure that any developmental activity, which may cause an adverse effect on the natural
    environment, is assessed before such activity is commenced;
    Coordinate and maintain a programme for the conservation of biological diversity and its sustainable
    use; and
    Coordinate the establishment of national parks and protected areas system and a wildlife protection
    management programme.

2.4.4     Guyana Lands and Surveys Commission (GLSC)

GLSC has the overall responsibility for land use planning and land administration. The Commission was
established under the GLSC Act, Act No. 15 of 1999 in June 2001. The Commission envisions becoming a
self-sustaining organization by 2010 with a mission “to effectively and efficiently administer lands for the
benefit of our clients and National Development”.

The GLSC has three main operational divisions: (i) Land Administration (ii) Land Information and Mapping
(iii) Surveys. The General Administrative Divisions, which include support and control, are administered by
(i) Office of the Commissioner (ii) Corporate Affairs. The functions of the Commission, as stipulated by the
Guyana Lands and Surveys Commission Act, 1999, include the following:
      To have charge of and act as guardian over all public lands, rivers and creeks of Guyana.
      To receive and evaluate offers to purchase or let public lands and to issue, for and on behalf of the
      President, grants, leases and permits to occupy such lands, in accordance with any law regulating the
      administration and disposition of public lands.
      To establish and maintain liaison between all the agencies involved in the registration and storage of
      records relating to public land in any tenure, including the registration of deeds and title to land.



270299/EVT/EES/HYES/28/A                           17
Conservancy Adaptation Project: Pre-Investment Studies
Coastal Lolands Environmental Assessment for Civil Works



   To formulate policy on geographic and land information, and set standards in relation to digital data,
   establish the framework for a national network of geographic information systems, and develop and
   maintain a parcel-based land information system.
   To initiate studies into and formulate policy on the development of public lands, including the feasibility
   of specific land development projects.
   To establish and maintain liaison with the responsible agencies to promote and monitor, in relation to
   public lands, the provision and maintenance of drainage and irrigation systems, access roads and
   other infrastructure, through such measures as may be appropriate.
   To compile and maintain an inventory of all the land resources of Guyana, their quality degree, pattern
   of utilization and related matters.
   To prepare land use plans for Guyana or any part of Guyana, except any municipality which is subject
   to a planning scheme (or interim development control pending the preparation of a planning scheme)
   under the Town and Country Planning Act.
   To advise Government on policy relating to public lands, land surveys and any other matters related to
   the functions of the Commission.




270299/EVT/EES/HYES/28/A                         18
Conservancy Adaptation Project: Pre-Investment Studies
Coastal Lolands Environmental Assessment for Civil Works



3         Description of Existing Environment

3.1       Physical

3.1.1     Description of Coastal Plain

With a 430km Atlantic coastline on the northeast, the coastal plain accounts for 5% of the country’s total
land mass and is home to 90% of its inhabitants. The coastal plain is made up largely of alluvial mud
swept out to sea by the Amazon River, carried north by ocean currents, and deposited on the Guyanese
shores. Rich clay of great fertility, this mud overlays the white sands and clays formed from the erosion of
the interior bedrock and carried seaward by the rivers of Guyana. Guyana has no well-defined shoreline or
sandy beaches. Approaching the ocean, the land gradually loses elevation until it includes many areas of
marsh and swamp. Seaward from the vegetation line is a region of mud flats, shallow brown water, and
sandbars. The coastal area is protected by a combination of natural and man-made sea defence
structures, mud banks, mangrove forests and sand flats, all of which protects from inundation and flooding.

3.1.2     Physical Characteristics

3.1.2.1   Soils

The coastal strip of Region 4 is located within the Coastal Plain of Guyana where the soils range from
predominantly alluvial deposits over organic material and silts comprising the Demerara Formation to the
White Sand plateau at the Cheddi Jagan International Airport and Timehri.

There are four main types of soil on the coastal plain (Bernard, 1999):
   Clays (found near the sea ; known as frontland or marine clays);
   Silty clays (found along major rivers);
   Histosols (known as pegasse in Guyana; found along the coast in swampy areas particularly in the
   Demerara and Essequibo areas ); and,
   Areas of mixed soils (includes clays, silts, laterites, podsols, histosols, regosols).

The soil capability of the soils in the coastal plain is considered to be of good to moderate fertility for
agriculture. These soils typically require both drainage and irrigation through an intricate system of
drainage and irrigation canals which lead to sluices.

Soils in the study area are typically frontland or marine clays near the existing road, and closer to the
conservancy histosols (pegasse).

 Soil Type            Characteristics
 Mara Clay            Poorly drained soil developed from relatively old marine sediments. It occurs in depressions and
                      is characterized by a shallow peat deposit over thick dark grey clay underlain by greenish grey
                      clay subsoil.
                      Poorly drained soil developed in river alluvium. The alluvium may have been deposited over
 Brickery Clay        fluviomarine sediments. It is characterized by a thin dark grey clay surface over grey clay subsoil
                      mottled with brownish yellow, yellowish red, and brown. The substratum is soft greenish grey clay,
                      which may contain numerous bits of partially decomposed organic matter. The soil is strongly
                      acid, slowly permeable and has a moderate level of fertility.
                      Poorly drained soil developed in river alluvium. It is characterized by a thin dark grey clay surface
 Tuschen Clay         over a grey to greenish grey clay subsoil with mottles of brownish yellow, yellowish red and
                      brown. The soil is strongly acid, slowly permeable and has a moderate level of fertility.




270299/EVT/EES/HYES/28/A                              19
Conservancy Adaptation Project: Pre-Investment Studies
Coastal Lolands Environmental Assessment for Civil Works




 Soil Type              Characteristics
                        Poorly drained organic soil occurring in depression areas. The soil consists of well decomposed
 Lama Muck              muck underlain by dark reddish brown peat. The substratum is greenish grey soft clay.

 Organic         Soil   The area linking the Demerara Clays and White Sand area is a transition zone comprising organic
 (Pegasse)              soils referred to as ‘pegasse.’ These deep organic soils have poor natural drainage capability;
                        with low fertility and permeability. There may also be pockets of soils containing toxic salts which
                        are often associated with the organic or mineral soils (British Guiana Soil Survey Project: FAO
                        1966).
                        With proper drainage management, including heavy applications of lime, fertilizers these soils
                        may be induced to produce moderate agricultural yields from certain shallow rooted crops such as
                        ground provisions, vegetables, bananas and coffee.


 White         Sands    The southern boundary of the study area is situated on what is commonly termed the “white sand
 Plateau                area” and is the beginning of the geological formation referred to as the White Sand Plateau. This
                        physiographic unit is composed of Pliocene and Pleistocene deposits of sands and clays inter-
                        bedded with kaolinite clay and bauxite. The surface is composed of a combination of white quartz
                        and brown loamy sands and clays.
                        The soils of the southern study area boundary consist almost entirely of quartz sand, a material
                        which is unconsolidated and subject to leaching. The area at the junction of the Soesdyke –
                        Linden Highway and the EBD is undulating with moderate slopes that when stripped of vegetation
                        is prone to erosion. These soils are extremely fragile,
                        poorly drained and low infertility. They do support vegetation but this is due to highly efficient root
                        systems and a closed nutrient cycle. The white sand areas support limited subsistence cultivation
                        of citrus, pineapples, cassava and vegetables.



Clays are the most fertile soils within the study area and have been exploited for agricultural purposes,
principally sugar cane.

3.1.2.2    Hydrology/Drainage

The hydrology of the site is largely controlled by its situation in the low coastal plain. The soils within the
general area are likely to be clay rich, with poor internal drainage. Much of the area is under agricultural
activities and as such there is a network of drainage and irrigation facilities. There are also drainage
systems in the residential areas. Generally, drainage along the East Coast Demerara area is done by
canals which empty into the Atlantic Ocean and is regulated by sluices. The pattern of settlement andother
activities such as agriculture along this area resulted in the construction of numerous drainage ditches
which lead into these main canals.

3.1.3      Climate

3.1.3.1    Climate

Guyana has a tropical climate with almost uniformly high temperatures and humidity, and much rainfall.
Seasonal variations in temperature are slight, particularly along the coast. Although the temperature never
gets dangerously high, the combination of heat and humidity can at times seem oppressive. The entire
area is under the influence of the northeast trade winds, and during the midday and afternoon sea breezes
brings relief to the coast. Temperatures in Georgetown are quite constant, with an average high of 32°C
and an average low of 24°C in the hottest month (July), and an average range of 29°C to 23°C in February,
the coolest month. The highest temperature ever recorded in the capital was 34°C and the lowest only
20°C. Humidity averages 70 percent year-round. Locations in the interior, away from the moderating
influence of the ocean, experience slightly wider variations in daily temperature, and night time readings as
low as 12°C have been recorded. Humidity in the interior is also slightly lower, averaging around 60
percent.




270299/EVT/EES/HYES/28/A                                20
Conservancy Adaptation Project: Pre-Investment Studies
Coastal Lolands Environmental Assessment for Civil Works



Rainfall is heaviest in the northwest and lightest in the southeast and interior. Annual averages on the
coast near the Venezuelan border are near 250 centimetres, farther east at New Amsterdam 200
centimetres, and 150 centimetres in southern Guyana's Rupununi Savannah. Areas on the northeast sides
of mountains that catch the trade winds average as much as 350 centimetres of precipitation annually.
Although rain falls throughout the year, about 50 percent of the annual total arrives in the summer rainy
season that extends from May to the end of July along the coast and from April through September farther
inland. Coastal areas have a second rainy season from November through January. Rain generally falls in
heavy afternoon showers or thunderstorms. Overcast days are rare; most days include four to eight hours
of sunshine from morning through early afternoon.

3.2      Biological

3.2.1    General Description

The proposed development works will entail several civil works projects along the East Coast Demerara.
These will include the following:
   Excavation and modification of drains
   Raising of embankments near the sea wall
   Construction of new pump stations
   Construction of new embankment between urban and agricultural areas
   Construction of flow constricting structures on agricultural drains
   Reconstruction of road culverts or bridges

The stretch of area between Crown Dam and the EDWC is characterised by seasonally flooded swamp
savannah vegetation consisting mainly of grasses, i.e. Palms and secondary forest ‘indicator’ vegetation
such as, Congo Pump and Black Sage.

The project site including the savannah swamp lands areas are highly disturbed environs with significant
amounts of habitat loss/stress already experienced as a result of human interactions/encroachment. As a
consequence, the existing biological realm of the area is predominated by species that adapts well to
changing environments. It is therefore expected that there will be a rapid recovery of habitats and
associated biodiversity owing to species adaptability to the habitat stresses that will ensue from proposed
project works. However, this scenario assumes that appropriate mitigation to negate impacts associated
with the proposed development will be implemented.

3.2.2    Flora

Along the existing canals and embankments and areas where rehabilitation works are to be done
comprises of secondary ‘disturbed’ vegetation, primarily of common weeds, shrubs, herbaceous plants and
trees including domesticated crops. Species found at the site are very common and can be found
throughout the Coastal Plain. Species such as the tree types and grasses found along the Canal
embankment are important for embankment stability and act as a ‘prevention mechanism’ against soil
erosion. These species also provide a habitat for many faunal species serving as roosting and breeding
sites for birds, insects and other fauna. Biodiversity in the area also support the existing farming
community through the provision of pertinent ecosystem services such as pollination, water catchments,
etc. Consequently, it is crucial that proposed works are done in a manner to allow natural re-vegetation of
these species or ensure that re-vegetation is done along the embankments and contiguous areas after
works.




270299/EVT/EES/HYES/28/A                        21
Conservancy Adaptation Project: Pre-Investment Studies
Coastal Lolands Environmental Assessment for Civil Works




3.2.3    Fauna

Fauna observed is typical of areas where human disturbances are frequent. Like the flora, the fauna are
very common and can be found throughout the Coastal Plain especially on abandoned and open lands.
Even though common within the coastal realm, faunal diversity in the area is sparse primarily due to heavy
habitat disturbance. However, faunal diversity is comparatively richer in the mangrove foreshore and
savannah swamp habitats. Faunal diversity observed at the site consisted primarily of highly mobile
species that adapts easily to changing environments. Species observed are nevertheless confined to micro
habitats fragmented by urban structures such as the ECD Public Road, the sea wall, existing canals,
housing communities, etc. Most avian species observed were transient, with a home range spanning the
project site.

As outlined earlier, there are no endangered species noted at the site and none of the species identified
were listed on the IUCN species listings or restricted by the CITIES listings. Habitat loss will be the major
impact on faunal diversity. In its present condition, existing habitats are severely stressed by human
activity. As such, it is crucial that habitat destruction is minimized and that proposed works are done in a
manner that allows natural regeneration/resuscitation of habitats and/or to ensure that re-vegetation is
done along embankments and contiguous area after works are completed.

3.2.4    Socio-Economic

Human settlement and infrastructure is concentrated in the reclaimed coastal plain where approximately 90
percent of the population resides. The population is distributed in locations determined by the availability of
suitable land for housing and services. The areas of the Essequibo Islands – West Demerara (Region 3),
Demerara – Mahaica (Region 4) and the Mahaica – Berbice (Region 5) are the most densely populated
areas, with the majority of Guyana’s citizens located in Region 4. The highest population densities are
found in the vicinity of the capital, Georgetown, and adjoining areas due to its proximity to the agricultural
zone and access to port facilities. The project area falls within the region 4 area. The Demerara-Mahaica
Region extends East of the Demerara River to the Western bank of the Mahaica River, and is
predominantly low coastal plain, with a small portion of the hilly sand and clay region further inland.

The population is concentrated along the coastland, particularly in Georgetown, the capital city, which has
a population of 133,000. The population of Region Four is 310,320, with over 104, 429 persons employed
in various sectors. Guyana's administrative and commercial activities are concentrated in this Region,
especially in and around Georgetown, the main port. There are many sugar estates, such as Diamond,
Enmore and La Bonne Intention, owned and controlled by the Guyana Sugar Corporation (GUYSUCO).




270299/EVT/EES/HYES/28/A                          22
Conservancy Adaptation Project: Pre-Investment Studies
Coastal Lolands Environmental Assessment for Civil Works




Table 3.1:    Population Distribution by Gender and Region




Source:   National Census 2002




270299/EVT/EES/HYES/28/A                            23
Conservancy Adaptation Project: Pre-Investment Studies
Coastal Lolands Environmental Assessment for Civil Works




Table 3.2:    Population and Employment Distribution




Source:   National Census 2002




270299/EVT/EES/HYES/28/A                               24
Conservancy Adaptation Project: Pre-Investment Studies
Coastal Lolands Environmental Assessment for Civil Works




Figure 3.1:   Regional Population Distribution




Source:   National Census 2002


The project area comprises a mix of land use and land tenure. It is a mixed of residential and commercial
small businesses, schools, and places of worship and agricultural land use. The project area falls with the
Better Hope, Buxton-Foulis and Clonbrook Neighbourhood Democratic Councils.

A key challenge facing the country, particularly residents living on the coast is the management of its poor
drainage infrastructure for flood control. Over the last decade, extreme weather conditions have become
more frequent and the prognosis is for this trend to continue. Over the two years (2004 – 2006), flood
events slowed agricultural production and personal losses have been significant. There are severe
limitations in the ability to prevent flooding and manage flood waters and the impact of land use changes
has clearly damaged the flood control drainage infrastructure. At present, flood control is managed on an
emergency basis and control efforts focused on responding to immediate needs rather than the
development of long-term control strategies.

Flooding is becoming more frequent. The majority of Guyana’s population lives along this reclaimed
coastal plain which is also the area where most agricultural activities are located. Unmanaged regional
development has exacerbated the flood control problem as development has altered or interdicted water
control systems without a sound understanding of the systemic impacts of these changes. In many cases,
activities such as backfilling canals and cuts in the levies have changed the functional dynamics of the
system.

The project takes a two pronged approach to improving flood protection in Guyana. First, critical near-term
civil works will be carried out to increase the drainage relief capacity of the EDWC.



270299/EVT/EES/HYES/28/A                         25
Conservancy Adaptation Project: Pre-Investment Studies
Coastal Lolands Environmental Assessment for Civil Works



This will allow the GoG to more effectively manage conservancy water levels during times of intense
rainfall. Activities to be carried out include improving the Cuhna canal discharge characteristics and
changing the internal flow dynamics of the EDWC system to allow for greater flows to the Demerara River
and away from the Mahaica-Mahaicony river system.




270299/EVT/EES/HYES/28/A                       26
Conservancy Adaptation Project: Pre-Investment Studies
Coastal Lolands Environmental Assessment for Civil Works



4            Analysis of Potential Impacts

4.1          Potential Environmental and Social Impacts

This section of the report identifies the potential environmental and social impacts associated with the
construction works proposed under Task 4: Coastal Lowlands Drainage Analysis and Works Identification
of the Conservancy Adaptation Project: Pre-Investment Studies and the feasible mitigation measures
and/or preventative actions that can be implemented to address the identified issues.

The potential impacts are described based on the bio-physical and socio-economic effects during the
construction and operational phases of the project. A Social Impact Assessment was also conducted and
is presented in this section. The significance of the impact is based on the degree and duration, high
probability of occurrence and its effect on sensitive receptors. Significance is determined by:
    Magnitude and extent
    Reversibility
    Longevity
    Probability of occurrence

The impacts identified in this section are based, mainly, on those that arise during the construction phase
of the project.

The table below summarises those impacts which have been identified during the design phase of this
project. These are discussed further in the following sections.

Table 4.1:    Summary of Potential Environmental and Social Impacts

Conditions                            Environmental Impact                     Significance

Construction Phase

Physical Environment

Environmental Aspect: Land/Soil

Construction     of   the   project   Loss of land through direct land take.   Lo, Irr, LT, UM, Un, Sig.
components

Land clearing                         Removal of shrub type vegetation and     Lo, Irr, LT, UM, Un,
                                      grassed areas, where necessary, to       Insig.
                                      widen existing drainage canals,
                                      construct culverts and to construct
                                      pump houses and ancillary facilities.

Operation of machines                 Compaction of soil from operation of     Lo, Rev, LT, Un, UM,
                                      heavy-duty machines to facilitate        Insig
                                      widening of drainage channels and
                                      construction of pump houses.




270299/EVT/EES/HYES/28/A                            27
Conservancy Adaptation Project: Pre-Investment Studies
Coastal Lolands Environmental Assessment for Civil Works




Conditions                           Environmental Impact                         Significance

Construction Phase

Disposal      of     materials       Improper disposal of silt and                Lo, Irr, LT, UM, Un,
(sediments and vegetation)           vegetation removed from excavation           Insig.
                                     works.


Storage of fuel and re-fuelling of   Fuel and/or oil spill from the operation     Lo, ST, Irr, Av, M, Sig
equipment.                           of heavy-duty machines can cause
                                     water and soil contamination.




Environmental Aspect: Emissions to Water

Fuel spills                          Water     contamination   from    fuel/oil   Ex, Irr, LT, Av, M, Sig
                                     spills.

Erosion and Sedimentation            From      material   stockpiles and          Ex, Rev, ST, Av, M, Sig
                                     excavated materials resulting in an
                                     increase in sediment loading in the
                                     existing drainage channels.

Waste disposal                       Improper solid waste disposal by             Ex, Rev, LT, Av, M, Sig
                                     workers such as food wrappers, boxes
                                     etc and also construction waste
                                     materail.

Environmental Aspect: Emissions to Air

Operation   of    heavy-duty         Noise from the operation of machinery        Lo, Rev, ST, Av, M,
machines and equipment               and construction activities.                 Insig

Operation  of   heavy        duty    Fumes from the            operation of       Lo, Rev, ST, Av, M,
machines and equipment               machinery      used       during    the      Insig
                                     construction period.

Operation of machines, storage       Dust from      construction activities,      Lo, Rev, ST, Av, M, Sig
of materials and construction        material and    waste stockpiles and
activities                           movement of     heavy duty equipment
                                     can affect     workers and nearby
                                     residents.

Biological Environment

Flora                                Habitat        loss,         destruction,    Lo, Irr, LT, Un, UM,
                                     fragmentation due to land clearing as        Insig
                                     a result of construction activities.



270299/EVT/EES/HYES/28/A                            28
Conservancy Adaptation Project: Pre-Investment Studies
Coastal Lolands Environmental Assessment for Civil Works




Conditions                       Environmental Impact                        Significance

Construction Phase

Fauna                            Habitat        loss,         destruction,   Lo, Irr, LT, Un, UM,
                                 fragmentation due to land clearing as       Insig
                                 a result of construction activities.

Socio-economic Environment

Environmental Aspect: Risks in the Working Environment

Employees’ safety can be         Employees at risk from accidents and        Lo, ST, A, Irr, M, Insig
compromised      during the      excessive noise from the operation of
operation of machines.           heavy-duty machines.

Relocation                       Residents located within the vicinity of    Lo, Un, ST, Sig, UM, Irr
                                 secondary drains will be affected; a
                                 few bridges may be relocated.

Drainage and Irrigation          The facilities which provides these         Lo, Un, ST, Sig, UM,
                                 services will be disrupted                  Rev

Flooding                         Potential     for    flooding     during    Lo, M, ST, InSig,, Rev
                                 construction.

Employment                       Overall short-term        increase     in   Ex, Rev, ST, Av, M, Sig
                                 employment.                                 (Positive)

Operational Phase: Maintenance Activities

Periodic  de-silting of the      Risks of accidents to workers and           Lo, ST, A, Irr, M, Insig
drainage channels to remove      exposure to excessive noise from the
sediments and weeds.             operation of heavy-duty machines.

                                 Fuel spills from the operation of           Ex, Irr, LT, Av, M, Sig
                                 machines may contaminate water and
                                 soil.

Vegetative removal to maintain   Continuous habitat disturbance.             Lo, Irr, LT, Un, UM,
drainage              channel                                                Insig
embankments.

Flooding                         Breaches along the embankment               Lo, M, ST, Sig, UM, Rev

Impact Significance Parameters
   Lo – Localised            Ex – Extensive             Rev – Reversible           Irr. - Irreversible
   ST – Short Term           LT – Long Term             Av. – Avoidable            Un – Unavoidable
   Sig. – Significant        Insig. – Insignificant     M. – Mitigable             UM – Unmitigable




270299/EVT/EES/HYES/28/A                        29
Conservancy Adaptation Project: Pre-Investment Studies
Coastal Lolands Environmental Assessment for Civil Works




4.2        Construction Phase – Impacts

The main activities associated with the project during the construction phase are described in detail in
Section 1.5. Construction activities will directly or indirectly affect the physical and social environment.
Potential impacts are listed in the matrix above and highlights the potential/predicted impacts, their
associated magnitude, importance and timeframe during the construction phase of the project

4.2.1      Impacts on the Physical Environment

4.2.1.1    Land/Soil

Potential Impact

Minor clearing of vegetation is necessary to facilitate widening of drainage channels. Construction of
culverts along drainage channels that are to be widened will result in minor clearance of vegetative shrub.

The environmental impacts that are likely to result from the aforementioned activities are:
   Loss of land due to expansion of channels (land take)
   Clearing of vegetation and soil disturbance to facilitate the expansion of the drainage channels,
   excavation works, embankment construction and construction of structures can cause some level of
   erosion;
   Compaction of soil from the constant movement of heavy machinery within the project area and the
   wider surroundings.
   Fuel and/or oil spill from the operation of heavy-duty machines can cause soil contamination;
   Improper disposal of excavated material; and

Analysis

Land utilised by the proposed project will be un-available to other uses, though generally the expected land
take will be minimal and involves expansion of existing drainage channels and will not affect other
productive use. The project area lies entirely within Government of Guyana owned land.

The removal of existing vegetative cover hastens the erosion process by exposing soils to the elements.
Soil disturbance can also contribute to erosion. To minimise this effect, and avoid extensive surface run-
off, activities should be scheduled to occur during the dry season. Slopes on the embankments would be
constructed to the appropriate degree to allow for adequate runoff and prevention of erosion.

The constant use and movement of heavy duty machines and equipment over exposed soil can result in
soil compaction; this can eventually lead to ponding during periods of heavy rainfall. Compaction also
makes regeneration of vegetation difficult. To avoid or minimize this effect, most of the construction
activities should be concentrated to the dry season/period.




270299/EVT/EES/HYES/28/A                         30
Conservancy Adaptation Project: Pre-Investment Studies
Coastal Lolands Environmental Assessment for Civil Works




Figure 4.1:   Access Dams in State of Disrepair (Buxton)




Source:   CEMCO


Constant traversing of vehicles through the site can further degrade the existing roads as shown in plate 1.

Management and Storage of fuel and lubricants on site can pose a major environmental problem. Leakage
from equipment, refuelling and servicing of machines in the field can result in fuel/oil spills. Workers
negligence and inadequate storage facilities can contribute to these spills which can contaminate the soil.

4.2.1.2    Water

Potential Impact

The surface water quality can become contaminated or affected from potential threats as those listed
below due to construction activities.
    Water contamination from sedimentation;
    Water contamination from fuel/oil spills;
    Blockage of existing drainage system/outfall structures from erosion and sedimentation; and
    Improper solid waste disposal by workers such as food wrappers, boxes etc.

Analysis

Construction works will be undertaken directly in the drainage channels, this will potentially increase
sedimentation. Also there are existing waterways at the pump stations that can be further polluted. During
the construction phase, fuel will be stored on site temporarily and will be moved to other areas as the work
progresses, therefore limiting the option of constructing the required “Bunded Area” to store fuel. Improper
storage and handling can result in water contamination.




270299/EVT/EES/HYES/28/A                             31
Conservancy Adaptation Project: Pre-Investment Studies
Coastal Lolands Environmental Assessment for Civil Works




Figure 4.2:   Enmore Pump Station. There is potential impact on water quality in this case




Source:   CEMCO


Spilled material can be easily leached into ground water causing contamination. Given the nature of the
construction operation it is not envisaged that a large quantity of fuel will be stored on site. Fuel will be
transported to the site as needed. It is recommended that all temporary storage tanks/containers will be
elevated to detect any leaks which may occur. Bund trays can be used to ensure any soiled fuel is
captured offloading or refuelling activites. An empty sealed container should be kept on siteFuel should be
stored in sealed containers and should not be filled to capacity; this will reduce the likelihood of spillage
during transportation. In addition, care will be taken during the re-fuelling process and when transporting
fuel from the storage tanks/trucks to the machines to avoid unnecessary spills and reduce the risk
associated with contamination. All fuel storage containers should be regularly inspected for leaks. Regular
maintenance of machines and equipment must be carried out to ensure proper functioning as this reduces
the potential for oil leaks. A maintenance schedule as well a system to check fuel storage containers
should be developed.

Materials eroded from the embankment and construction materials and waste debris stockpiles can end up
in existing waterways resulting in sedimentation. Materials stockpiles will have to be located away from
water bodies and drains. Designated areas for storage of material should be identified. Waste debris,
especially construction waste, should not be stockpiled on site for prolonged periods and should be
removed in a timely manner. Any blockage of waterways as a result of sedimentation should be removed
immediately.

The improper management of solid waste can affect water quality. Solid waste can often end up in water
bodies as a result of direct dumping which can lead to contamination and blockage. During the



270299/EVT/EES/HYES/28/A                              32
Conservancy Adaptation Project: Pre-Investment Studies
Coastal Lolands Environmental Assessment for Civil Works



construction phase, care must be taken by all workers to dispose of any solid waste material generated in
keeping with the procedures outlined in this EA.

4.2.1.3    Air

Potential Impact

During the construction phase there are several activities which can affect the air quality in the project
area. However, the level of impact will be localised, short-term and insignificant. These impacts are more
likely to affect construction workers and residents living nearby; particularly in the Enterprise, Liliendaal
and Buxton area, residents are located nearby.

Figure 4.3:   Houses in proximity to Site (Buxton)




Source:   CEMCO


These impacts can be mitigated by utilising best construction practices. The following impacts can
potentially arise as a result of the project.
    Noise from the operation of machinery.
    Rehabilitation of identified structures.
    Fumes from the operation of machinery used during the de-silting process, re-routing of the canal,
    rehabilitation of the sluice and construction of the bridge; and
    Dust from moving of earth, equipment and stockpiles.

Analysis

Construction activities will generate significant levels of noise. The operation of heavy duty machines and
equipment may generate noise levels above the alert threshold of 86 decibels and hazard threshold of 95
decibels. Nevertheless, measures must be in place, as recommended by the EPA, to reduce the noise
level from construction activities for workers and other persons on-site and are detailed in Section 6 of this
report. Equipment and machinery will be fitted with mufflers to reduce the noise emanating.




270299/EVT/EES/HYES/28/A                             33
Conservancy Adaptation Project: Pre-Investment Studies
Coastal Lolands Environmental Assessment for Civil Works



The operation of the machines and equipment will also generate fumes which may have some effect on
the air quality in the surrounding area. However, the level of impact will be localised, short-term and
insignificant, to the point of negligible.

Dust will be generated from earth movement activities and the movement of equipment over dry areas.
Construction material stockpiles such as sand can become airborne and contribute to a dust nuisance.
Construction activities such as demolition and removal of existing structures can increase dust nuisance.
The use of cement products increase dust levels in the immediate area, transportation of material to site
can however impact the wider public. Since the project site is located away from housing development, the
potential for dust nuisance is not great. However, measures (mainly wetting the site frequently, covering or
soaking stockpiles), would be implemented to reduce this impact. Dry areas will be soaked as necessary,
depending on the weather condition. All trucks transporting construction materials to the site would be
covered to prevent fugitive dust from escaping into the environment.

4.2.2      Impacts to the Biological Environment

4.2.2.1    Flora

Potential Impact

The potential impact on the flora in the project is:
   Direct loss due to removal to facilitate construction.
   Damage to flora during construction work as a result of machinery working in close proximity.

Analysis

The project area is located within communities and is covered predominantly by secondary vegetation and
indicates a highly human disturbed area. No rare, threatened or endangered species were found within the
area. Vegetation removal is essential to facilitate construction of a new embankment and various other
aspects of project and, therefore, unavoidable. The area of immediate influence consists of shrub-like
vegetation, aquatic species and tree type vegetation can be found. Most of the vegetation which will be lost
is the type which is common within and around the project area and can also be found throughout the
coastal area of Guyana. As such this impact is deemed insignificant.

Figure 4.4:   Typical Coastal Vegetation (Annandale)




Source:   CEMCO




270299/EVT/EES/HYES/28/A                               34
Conservancy Adaptation Project: Pre-Investment Studies
Coastal Lolands Environmental Assessment for Civil Works



4.2.2.2    Fauna

Potential Impact

The potential impact on the fauna in the project environment is:
   Habitat loss, destruction, due to land clearing as a result of construction activities.
   Migration of faunal species due to the presence of human and machinery.

Analysis

The faunal diversity in the area is sparse and most species observed during the field exercise were
domestic animals. Although a small portion of land area will be taken up by the project and some
vegetation will be removed, there is available within the project environment enough land to support these
animals. Therefore, the impact of habitat disruption on the biological environment will be localised and
insignificant especially given that this area has been highly disturbed.

4.2.3      Impacts to the Socio-Economic Environment

4.2.3.1    Displacement and Relocation

Potential Impact

The Project may result in some level of relocation/displacement of access and bridges, no relocation of
houses will be done to accommodate the works. In the good-hope area in particular, the access to the
work area is shared with fisherfolk and boatbuilders.

Figure 4.5:   Access to Pump Station shared with Fisherfolk (Good Hope)




Source:   CEMCO




270299/EVT/EES/HYES/28/A                            35
Conservancy Adaptation Project: Pre-Investment Studies
Coastal Lolands Environmental Assessment for Civil Works



4.2.3.2    Drainage

Potential Impact

Disruption to drainage regime of the coastal areas.

Analysis

Work to the Drainage channels will be executed using best engineering methods, alternative diversions will
be identified to dewater sites in cases where relief structures will be programmed so as to avoid disruption
to the drainage regime of the coastal areas.

4.2.3.3    Flooding

Potential Impact

Widening of existing canals will not impact greatly on drainage. Replacement of culverts and related
structures may cause minor drainage issues, mainly reduced flow, this however is not likely to cause
flooding.

Figure 4.6:   Typical Drainage Channel / Culvert that will be Widened




Source:   CEMCO


4.2.3.4    Employment

Potential Impact

Construction activities will have a positive impact on employment within the wider area.

Analysis

Construction will be done utilising contractors for different aspect of the project. Construction activities will
require the employment of skilled and unskilled labour. This provides an opportunity for local individuals to
be employed and thus results in an increase income for those persons.

4.2.3.5    Health and Safety

The potential risks to the health and safety of workers and the public during the construction phase are
discussed in Section 7. A design stage risk assessment has been carried out and is presented in Appendix
B.




270299/EVT/EES/HYES/28/A                              36
Conservancy Adaptation Project: Pre-Investment Studies
Coastal Lolands Environmental Assessment for Civil Works




4.3        Potential Impacts during the Operational Phase

4.3.1      Maintenance Activities

Potential Impact

The key activities during this phase are those associated with continuous maintenance of the structures
that will be rehabilitated and drainage channels that have been widened. The potential impacts associated
with these activities are:

      Risks of accidents to workers and exposure to excessive noise from the operation of heavy-duty
      machines;
      Fuel spills from the operation of machines may contaminate water and soil; and
      Continuous habitat disturbance.

Analysis

Maintenance of the proposed drainage system will entail activities designed to keep the drainage channel
clear and the structures in good working conditions. These include manual and mechanical vegetation
management and removal, mechanical desilting of channels and especially outfalls, greasing of pulleys,
winches and cables for the sluice, and normal preventive maintenance. Although these activities have low
environmental impacts, they have the potential for localised negative impacts if good practices are not
followed, in particular proper disposal of used oils, careful re-fuelling practices, as well as, health and
safety issues such as risks of accidents to works and exposure to excessive noise from the operation of
machinery and equipment. Impacts to the surrounding biological environment are also localised and
insignificant given that the area is under direct human influence.




270299/EVT/EES/HYES/28/A                        37
Conservancy Adaptation Project: Pre-Investment Studies
Coastal Lolands Environmental Assessment for Civil Works



5         Environmental Management Plan

5.1       Environmental Management Organisation

To accomplish a successful environmental management program the Contractor, the client and the EPA
must establish an effective organisation and reporting procedure. In order to do this the following
measures should be carried out.

a) During the pre-construction meeting, the environmental management measures will be discussed with
the successful Contractor. This meeting will include representatives from the Ministry of Agriculture, NDIA,
engineering and environmental sections and the Contractor, as well as the proposed Environmental
Monitor. In addition, the Environmental Protection Agency should be invited to attend.

b) All necessary permits, licences and approvals will be obtained and copies will be on site prior to the start
of construction. Furthermore, all work will be undertaken in a manner consistent with the conditions of all
permits, licences and approvals.

c) An Environmental Management Plan (EMP) should be included in the Contractor QA/QC Plan and form
the framework for the contract/bidding documents so as to ensure that the recommended measures are
implemented by the Contractor. The Contractors EMP shall be based on guidance given in this document.

This EMP will identify activities to be undertaken in an effort to mitigate the principal adverse effects of the
project. The Plan will describe the way in which the main environmental impacts of the project can be
managed, and prescribes appropriate mitigation measures to be adopted during the rehabilitation and
construction activities as well as the operational life of the project. These impacts were identified and
discussed in section 5 of this document and their significance has been taken as a function of the following
criteria:
     Magnitude and extent.
     Reversibility.
     Longevity.
     Probability of occurrence.

The objectives of the EMP will be to:

Set out measures and strategies to address the environmental issues related to the rehabilitation and
construction as well as operational activities of the project. Formulate a monitoring plan to ensure that the
activities are executed in accordance with these environmental requirements and to establish the impacts
of the project with a view to implementing any necessary further action to minimise negative impacts.

This EMP will consist of the following:
    Mitigation Plan
    Monitoring Plan
    Emergency Response Plan

Since both the rehabilitation and construction activities will be undertaken simultaneously the mitigation
measures for potential impacts are discussed together.

d) The Contractor at the outset of construction, prepare a waste management strategy providing a plan of
action for the reuse, recycling and disposal of all types of waste material generated during construction as



270299/EVT/EES/HYES/28/A                           38
Conservancy Adaptation Project: Pre-Investment Studies
Coastal Lolands Environmental Assessment for Civil Works



well as during the post-construction period (demolition of construction related facilities). The objective of
the strategy will be to minimise disposal through maximisation of reuse and recycling opportunities.

e) The Contractor at the outset of construction prepare an emergency response plan which will encompass
the objective and direction provided in the spill contingency plan, this plan shall comprise procedure for
notification and reporting of spills, establishment of an emergency response team.

5.2      Responsibility

It has not been agreed, as of the date of this report, whether the NDIA or a Contractor will have primary
responsibility for the execution of these works. Whichever organisation carries out the works will be
assisted by Supervising Consultants in the form of a Consultancy Firm will be contracted to oversee the
implementation of the Project. The Supervising Consultants will ensure the requirements of the EMP are
implemented.

The environmental requirements would be communicated to any contractor or sub-contractor utilised in the
execution of the Project.

5.3      Roles and Responsibilities

5.3.1    Environmental Officer/Monitor

The Environmental Officer/Monitor should be accountable to the Supervisor’s Representative and to
proactively advise the Contractors Representative on environmental protection measures during
construction. Duties include:
1. Environmental monitoring and assessments
2. Acting as a resource and provide guidance to the Contractor on environmental issues, proactive
    mitigation measures and innovative technology
3. Communicating with Environmental agencies as required
4. Participating in weekly onsite project meetings
5. Reporting recommendations and weekly summaries to the Supervisor’s Representative
6. Assisting with an assessment for all non-compliance events
7. Assessing preventative plans for re-occurrence of adverse events, and follow-up on recommendations
8. Conducting preliminary assessments of proposed design changes to evaluate potential changes to
    environmental design components and preliminary impact (positive or negative) overview
9. Immediate reporting of non-compliance events to the Supervisor’s Representative
10. Producing stop work orders.

5.3.2    Supervisor’s (NDIA) Representative

The Supervisor’s Representative is accountable to the Contracting Authority. Specific duties of the
Supervisor’s Representative pertaining to environmental protection include:
1. Meeting weekly with the Environmental officer/Monitor to review past environmental recommendations
   and project schedule
2. Providing schedules to address assessment recommendations and outstanding works
3. Ensuring environmental issues are dealt with in a timely manner and producing a plan to prevent
   reoccurrence
4. Ensuring non-compliance events are immediately brought into compliance
5. Reporting non-compliance events to the Environmental Officer/Monitor




270299/EVT/EES/HYES/28/A                         39
Conservancy Adaptation Project: Pre-Investment Studies
Coastal Lolands Environmental Assessment for Civil Works



6. Discussing potential design changes or changes to the EMP with the Environmental Officer/Monitor
   prior to undertaking the change
7. Producing stop work orders, as required.

5.3.3    Contractor Representative

The Contractor Representative is accountable to the Contracting Authority. Specific duties of thee
Contractor representative pertaining to environmental protection include:
1. Meeting weekly with the Environmental Officer/monitor to review past environmental issues,
   assessment recommendations, and project schedule
2. Providing schedules to address assessment recommendations and outstanding works
3. Ensuring construction is coordinated according to the environmental concerns
4. Requesting advice on environmental interests from the Environmental Officer/Monitor
5. Ensuring environmental issues are dealt with in a timely manner and producing a plan to prevent
   reoccurrence
6. Ensuring non-compliance events are immediately brought into compliance
7. Reporting non-compliance events to the Environmental Officer/Monitor
8. Discussing potential design changes or changes to the Environmental Management and Monitoring
   Plan with the Environmental Officer/Monitor prior to undertaking the change.

5.3.4    Project Site Meetings.

The Environmental Officer/Monitor should be involved in regular project meetings with the Supervisor’s
Representative, and the Contractors Representative. The purpose of such regular meetings should be to
outline the schedule of upcoming construction and proposed activities, and to review the activities of the
previous week.

In the event that the Environmental Officer/Monitor or Supervisor’s Representative deem the compliance
regarding environmental requirements to be inadequate at any time during the Project, the frequency of the
weekly or biweekly regular meetings should be increased accordingly until the Environmental
Officer/Monitor is satisfied with the implemented changes.

5.3.5    Reporting Criteria and Frequency

To facilitate efficient communications, the on-site Environmental Officer/Monitor should report and
communicate with the Environmental Agencies.

The Environmental Officer/Monitor should keep written records and photographic records where
applicable, of all mitigation activities, compensation works, and construction task assessments and
communications regulatory personnel. Weekly summary reports should be submitted to the Supervisor’s
Representative and should include:
   Number and type of work assessments
   Quality of construction work and work techniques or mitigation recommendations
   Follow-up on previous recommendations
   Outstanding environmental works
   Proactive measures taken to protect the environment
   Other environmental issues
   Communications with environmental agencies
   Areas of work scheduled for upcoming week
   Proposed changes to design




270299/EVT/EES/HYES/28/A                        40
Conservancy Adaptation Project: Pre-Investment Studies
Coastal Lolands Environmental Assessment for Civil Works



If a special event occurs, the Environmental Officer/Monitor should immediately report the event to the
Supervisor’s Representative. Subsequent reporting should include event details, quality assurance and
prevention plans. If an event results in a spill, the spill response plan should be activated.

5.3.6    Construction Activity to be Assessed

All aspects and phases of construction are to be assessed including planning, scheduling, methodology,
and mitigation. Daily planning, scheduling and construction techniques should be discussed and assessed
by the Environmental Officer/Monitor.

5.3.7    Assessments

The Environmental Officer/Monitor should record assessments in written format and photographically
where applicable. Individual records should be maintained for each environmental section and for each
springs/wells compensation sites. Specific activities are to have individual assessment records on file,
including any recommendations for follow-up.

Copies of assessment records should be forwarded, as completed, to the Supervisor’s Representative,
highlighting outstanding works, substandard works requiring improvement, and construction technique
recommendations.

The Supervisor’s Representative should provide a written response, within 2 days detailing the schedule to
accommodate substandard or outstanding works. Recommendations should be discussed at the next
weekly meeting.

5.3.8    Compliant /Non-compliant Criteria

A non-compliant activity is any activity that does not comply with the requirements of the Environmental
Management and Monitoring Plan, the Special Specifications for the Project, permits, approvals and
authorizations, and environmental regulations and acts, regardless of due diligence and mitigation
activities.

If a non-compliant activity is detected or reported, the activity creating the non-compliance should cease,
and efforts should be undertaken to rectify the non-compliance. The Environmental Officer/Monitor should
assess all non-compliance activities and assist the Contractor in returning the activity back into
compliance.

The Contractor, in consultation with the Environmental Officer/Monitor, should prepare a prevention plan
designed to prevent reoccurrence of non-compliant activities.

The Environmental Officer/Monitor should conduct follow-up assessments on all previously non-compliant
activities to assure changes have been made to ensure environmental protection. Follow-up assessments
should be submitted to the Supervisor’s Representative and the Contracting Authority.

5.3.9    Stop Work Authorisation

Persons with Stop Work Authorisation are the primarily Supervisor’s Representative and subsequently the
Environmental Officer/Monitor. Stop Work Authorizations are to be used only after all other efforts, such as
dialogue with the Contractor and assessment reports, have been employed in an attempt to return a non-
compliant or potentially non-compliant activity back into compliance. Although both parties are authorized
to issue Stop Work Orders for a particular adverse activity, whenever possible, the Environmental



270299/EVT/EES/HYES/28/A                         41
Conservancy Adaptation Project: Pre-Investment Studies
Coastal Lolands Environmental Assessment for Civil Works



Officer/Monitor should request the Supervisor’s Representative to undertake this Management. If the
Supervisor’s Representative is not available, or is unresponsive to this request, the Environmental
Officer/Monitor should issue the Stop Work Order.

Stop Work Orders should be in writing. Stop Work Orders for environmental protection, or any issued by
the Environmental Officer/Monitor must immediately be communicated with the Contracting Authority.

5.3.10 General Environmental Monitor Activities and Deliverables

The activities of the environmental monitoring services should be comprised of routine activity
assessments, potential environmental protection activities, unanticipated activity assessments, meetings
and reporting, resource assistance and environmental protection.

Routine activity assessments, potential environmental protection activities, meetings and reporting are
based on scheduled construction activities. Unanticipated activity assessments are those construction
activities that are not planned or scheduled and include activities such as spills and uncontrolled
environmental releases, weather influenced activities, field changes, etc.

The Environmental Officer/Monitor services should also act as an environmental protection resource for
the Contractor, participating in training, modifying construction techniques, providing recommendations,
and assisting in preventative planning toward environmental protection.

The Environmental Officer/Monitor should be expected to participate in weekly Contractor meetings to
discuss project schedule, changes, recommendations, works in environmentally sensitive areas, etc.

5.4        Environmental Assessments

5.4.1      Pre-Construction/Construction Phase

A pre-construction report should be prepared by the Consultant before the commencement of construction.
This assessment should take the form of a small audit to detail characteristics of the environment in the
construction and related areas. This should include a photo log and sketches of area. This report can be
used to monitor construction impact on the environment.

The following items should be monitored during the construction phase.

      General Site condition

Routine assessment of general site conditions, visual inspection of construction staging area to ensure that
EMP is being implemented.

      Fuel and Hazardous Material Storage Areas

Routine assessments of fuel and hazardous material storage and general housekeeping practices are to
be undertaken on an informal base throughout construction.

      Noise and Dust

Monitoring of noise and dust nuisances and measures implemented to mitigate those nuisances.

      Waste Management



270299/EVT/EES/HYES/28/A                         42
Conservancy Adaptation Project: Pre-Investment Studies
Coastal Lolands Environmental Assessment for Civil Works



Assessment/Monitoring of waste collection and disposal practices and general housekeeping on site.

   Public Complaints.

Assessment of public complaints and follow up

   Watercourse Crossings

Equipment crossings of the drains (channels) are to be monitored for best management practices such as
bank erosion reduction, sedimentation, etc.

   Flag Riparian Zones

The Environmental Officer/Monitor is responsible to flag all riparian zones simultaneous to the construction
contractor project layout, prior to clearing and grubbing operations.

   Drainage

All channels, drains and River are to be monitored as and when required, to assure clearing and grubbing
activities, and erosion control measures, are undertaken in accordance with the environmental
management plan.

   Sediment Control Monitoring

Sediment control should be monitored to ensure water quality protection during all phases of construction.

   Flora and Fauna

The effect of construction on vegetation clearance and also impact on water bodies and aquatic
environment should be assessed.

5.4.2    Post Construction Phase Assessment

Construction site and staging area shall be cleared, all structures dismantled and restored to its original
stage as far a practicable as possible. Within one month of completion of construction the Environmental
Inspector shall prepare the post construction report and shall be forwarded to the NDIA Environmental
Engineer and the Contractor Environmental Office. The following items should be inspected/monitored.

   Site cleanup.

All waste materials should be removed and all existing structures that are not part of the works removed.

   Grading and slope stabilization done.
   Erosion control measures in place, sedimentation identified and recovered.
   Re-vegetation around construction sites to avoid erosion

Monitoring Plan

Monitoring is an integral part of effective implementation of the Environmental Management Plan. The
Consultant environmental Inspector should visit all construction area on a daily basis to ensure that
mitigation action area implemented.




270299/EVT/EES/HYES/28/A                         43
Conservancy Adaptation Project: Pre-Investment Studies
Coastal Lolands Environmental Assessment for Civil Works



The main environmental issues to be monitored are water quality, erosion and sedimentation. A each
construction site it is important to carry out water quality test (pH and Turbidity), these tests should be done
prior to construction to establish benchmark data, during construction to assess the impacts and after the
completion of construction.

5.4.2.1   Reporting

The Environmental Officer/Monitor should provide:

    Weekly summary reports of assessments detailing
    – Number and type of work assessments
    – Recommendations and follow-ups
    – Unanticipated activities
    – Proposed design changes
    – Summary of meeting issues
    – Other environmental issues

    Monthly Reports detailing:
    – Environmental construction works to date
    – Outstanding environmental construction works
    – Planned environmental construction works
    – Quality of work and work technique or mitigation recommendations
    – Environmental assessment work projection for the upcoming month
    – Proactive measures taken to protect the environment
    – Communications with environmental agencies
    – Other environmental issues

The Environmental Officer/Monitor should also maintain a daily diary containing details of events,
assessments undertaken, communications, and other relevant items. The diary should be delivered to the
Supervisor’s Representative at the end of each construction season, or at the year's end.

5.4.2.2   Services not provided by the General Environmental Monitor

Environmental monitoring service is not responsible to undertake environmental mitigation activities that
are normally performed by the Contractor. Such activities include, but not limited to:
    Sediment control structure implementation, inspections and maintenance
    Mitigation activities required due to weather
    Returning non-compliance activities back into compliance
    Spill control and clean up

5.4.3     Environmental Protection Agency

The EPA main role is to ensure that the project is implemented and the project is in compliance with
environmental laws, standards and regulations. The EPA will receive quarterly reports from the MPW&C
Engineer during construction and post construction. The EPA is also responsible for periodic monitoring of
the project.




270299/EVT/EES/HYES/28/A                           44
Conservancy Adaptation Project: Pre-Investment Studies
Coastal Lolands Environmental Assessment for Civil Works



6         Proposed Mitigation Measures

6.1       Impact Mitigation

The following mitigation measures have been identified to prevent, minimise and manage the adverse
environmental impacts discussed in Section 4. These measures are outlined below and should be included
in the Contractors EMP.

General

The Contractor executing construction works is required to:
   dispose of sewage, refuse and chemical wastes in a manner approved by all authorities having
   jurisdiction;
   conduct all operations in such a manner that there are no unauthorised discharges of any sort (liquid or
   solid) into waterways given that most of the works will be executed within or adjacent to drainage
   channels;
   undertake work in compliance with the plans approved by NDIA/EPA, and shall not undertake work not
   on the approved plans;
   ensure that habitat areas that are not within the work site are protected from disturbance; and
   Ensure that appropriate spill kits are available.
   When night work is authorised by the Consulting Engineer, the Contractor shall provide adequate
   lighting where work is being executed at night and shall provide and install any additional lighting as
   required by the Consultant in order to gain access or to supervise the works and carry out testing or
   examination of material.
   The Contractor shall ensure that access is provided to all properties adjacent to the site for the duration
   of the contract
   The Contractor shall acquaint himself with the position of all existing services such as sewers, surface
   water drains, cables for electricity and telephone and lighting poles, water mains and the likes before
   commencing excavation or other work likely to affect the utilities.

6.1.1     Erosion and Compaction

The following measures should be implemented to reduce the impact of erosion and sedimentation
activities:
    Minimise removal of vegetation to areas where it is absolutely necessary.
    Encourage natural re-vegetation in areas where possible to prevent soil exposure.
    Monitor areas of exposed soil during periods of heavy rainfall.
    Slopes should be constructed at the recommended angle to prevent collapse.
    Use appropriate machines for all earth works.
    Designate routes for heavy duty equipment to prevent compaction of soil.
    If ponding is observed due to compaction, it may be necessary to scarify the topsoil.
    Consider the weather pattern before initiating major earthworks. Earthworks should be avoided during
    periods of heavy rainfall.
    The area around the inlet and outlet of the culvert under the bridge will have to be stabilised as soon as
    possible to minimise erosion around the culvert.
    Cofferdams and other appropriate measures should be used to prevent water from entering working
    areas so as to prevent breaches from occurring.




270299/EVT/EES/HYES/28/A                          45
Conservancy Adaptation Project: Pre-Investment Studies
Coastal Lolands Environmental Assessment for Civil Works



During operation, routine maintenance activities will be conducted as necessary. Maintenance would
include:
    Routine inspection to drainage channels and structures
    Routine cleaning of channels
    Routine cleaning of embankments

6.1.2     Fisheries and Watercourses

In order to protect fish, fish habitat, water courses and the quality of water used for domestic and irrigation
purposes, the following should be implemented. CONTRACTOR shall:
    minimise and contain suspended sediment within the immediate zone of construction;
    undertake appropriate containment measures during concrete pours to ensure that uncured concrete
    or concrete leach ate does not enter any watercourse or drainage; and,
    ensure that water intakes or drainage channels for domestic and irrigation purposes are protected from
    damage at all times.
    Avoid disruption of sluices and impact to hydraulics, drainage shall be controlled and monitored during
    construction to maintain proper water levels through adequate structural support systems. Waterbodies
    should be free of obstruction and normal flow of water maintained.
    All waste storage stockpiles or stockpiled material shall not be placed within 10m of any watercourse
    and shall have a toe berm construction around.
    Significant volumes of dewatering effluent (greater than 3 litres/second) shall be discharged into a “filter
    bag” that’s designed to retain or filter sediment while gradually releasing water.

6.1.3     Dewatering

    The discharge of dewatering effluent can result in scouring and erosion at point of discharge as well as
    sediment loading to watercourses and drains.
    The Contractor shall keep the whole works free from water and provide all dams, cofferdams, pumping,
    piling and temporary drains necessary for this purpose.
    Significant volumes of dewatering effluent greater than 50 gallons per minute shall be discharged into a
    filter bag that is a geotextile bag to retain or filter out sediments.

6.1.4     Noise

As identified in the impact section, noise will be a significant environmental impact that requires mitigation.
The EPA, in collaboration with GNBS, has developed Guidelines for Noise Emission into the Environment.
The Standard specifies noise limits for construction activities both for daytime and during the night. The
daytime limit (06:00hr – 18:00hr) is 86 dB while the limit in the night is 75dB. Given the proximity of
residents to the activities locations noise can be a minor.

However, to comply with the National Standard and reduce this impact the following are measures should
be implemented:
    Provide hearing protection to workers exposed to high noise levels such as those involved in
    demolition.
    Provide earplugs for employees who operate heavy duty machines.
    Employees working in high noise levels areas should be mandated to wear earmuffs or earplugs as
    required.
    Ensure that machinery and equipment are working efficiently and have installed the required muffler
    devices.
    Schedule activities to daytime to reduce noise nuisance to nearby residents.




270299/EVT/EES/HYES/28/A                           46
Conservancy Adaptation Project: Pre-Investment Studies
Coastal Lolands Environmental Assessment for Civil Works




6.1.5    Dust

Dust, though localised, is a potential impact that would require some level of mitigation as outlined in
Section 5. The following measures should be implemented to reduce the impact of dust on the
environment:
   Personnel working in dusty environments should be required to use respirators.
   During dry periods it may be necessary to soak routes traversed by vehicles and equipment. Dry areas
   should be soaked as necessary, depending on the weather condition.
   Materials should be transported to site as needed thus resulting in small stockpiles.
   All trucks transporting construction materials should be covered.
   If necessary, the stockpile would also be soaked with water periodically.
   The burning of construction waste and cleared vegetation should be prohibited to avoid smoke
   nuisance.

6.1.6    Fuel, Lubricants and Chemicals

Fuel and lubricants are classified as hazardous materials and require special consideration in terms of
transportation, storage and handling. The following measures should be implemented to ensure the risks of
contamination of soil or water from spillages are minimised:
    Since the construction activities would be temporary and fuel storage will be moved as activities
    progress, it would not be feasible to construct proper facility for fuel storage. As such, it is
    recommended that fuel be transported to the site as needed or in small quantities.
    Fuel which will require storage should be sited a safe distance from waterways, site offices and work
    areas and should be elevated to detect any leaks.
    Care should be taken to prevent spillage and leakage of fuel during off loading and refuelling. When
    refuelling is completed, all nozzles, hoses and other materials should be stored in a proper manner to
    avoid spills.
    Drip pans can be placed under the fuel/vehicle coupling when vehicle tanks are being filled. This
    should prevent the possible contamination from leakage of fuel.
    Regular maintenance of machinery should be done to avoid leakages.
    Spill kits should be made available in the event of spillages.
    Workers, mechanics and other staff should be trained on the proper use of these kits.
    Adequate signage should be installed in fuel storage areas such as No Smoking and Flammable
    Materials.
    Fuel storage tanks/containers should be monitored for leaks.
    Fire containment measures such as extinguishers or sand buckets should be place in fuel storage/re-
    fuelling areas.
    The on-site fuelling area should be deemed a ‘no smoking’ zone and all staff required to turn off cell
    phones when in that general vicinity.

6.1.7    Waste Management

Several types of waste can be generated from the various activities that would require different methods of
disposal. Domestic and construction waste will be disposed of at the Lusignan Dumpsite.

6.1.8    Health and Safety

In Section 7 the management of Health and Safety during the construction phase is discussed, based on
the risk assessment included in Appendix B.




270299/EVT/EES/HYES/28/A                        47
Conservancy Adaptation Project: Pre-Investment Studies
Coastal Lolands Environmental Assessment for Civil Works




6.2       Specific Management Plans

6.2.1     Erosion and Sediment Control Plan

6.2.1.1   Purpose and Scope

This Plan describes environmental protection measures to prevent erosion and sedimentation.

Protection measures to control sediment and runoff and specific sediment and drainage control plans for
all areas of disturbance are contained herein.

6.2.1.2   Sediment Control and Water Quality

Works will be planned, scheduled and performed in such a manner that the quality of water flowing from
the site is at all times acceptable. Conditions will be maintained to protect the aquatic environment of
watercourses not only during construction, but also during periods of suspended construction activity.

Permanent and temporary soil erosion control features will be constructed at the earliest practicable time,
and will be inspected daily during adverse weather conditions or when construction operations are
proceeding in Environmentally Sensitive Areas. Control measures will be capable of continuous operation
during working and non-working hours, and are subject to approval by the Supervisors’ Representative.

During periods of inclement weather, operations will cease, or construction methods will be modified or re-
located to an alternative site within the project area to avoid situation of watercourses.

The Environmental Officer/Monitor will conduct regular water quality monitoring for changes in turbidity as
result of construction as part of the quality assurance program.

The installation of culverts will be conducted in the dry whenever possible to reduce the risk of
sedimentation to local springs and wells that provide water to local households.

During preparation of stream diversions, culvert installations and other dewatering where drainage could
readily reach a watercourse, all effluent and silt-laden water will be discharged to a sediment control pond,
or alternate sediment control method for removal of sediment prior to its release into that watercourse. This
requirement also applies to the control of discharge resulting from curing areas of recent concrete pours for
bridges or drainage structure headwalls. The direct discharge via seepage of untreated, silt-laden water or
other deleterious substance into any watercourse is prohibited.

6.2.1.3   Riparian Areas

Maintaining adequate buffer zones and employing sediment control measures will protect riparian areas.

6.3       Erosion Control

Once construction has begun, erosion control is the first step in effective management of sediment. While
erosion is a natural process that shapes the landscape, construction can accelerate the process and cause
significant volumes of material to be transported and potentially adversely impact aquatic resources.
Therefore, sites at risk for shallow slope movement will be identified and appropriate control measures
applied to minimize the potential of slope movement. Effective and proactive erosion control is more
effective than sediment interception and trapping.




270299/EVT/EES/HYES/28/A                         48
Conservancy Adaptation Project: Pre-Investment Studies
Coastal Lolands Environmental Assessment for Civil Works



The following steps to effectively control erosion are:
   Schedule construction activities at sensitive sites for times when the risk is minimal.
   Inlet and outlets of drainage culverts will be stabilized as per construction drawings as soon as the
   culvert is installed to minimise erosion around the culvert.
   Where possible construction activities in areas of high erosion potential will be planned for the driest
   season of the year.
   Equipment movement in erosion prone areas during periods of heavy precipitation will be restricted.
   Retain as much existing vegetation as possible.
   Construction drawings will identify areas of clearing and grubbing and designed to minimise the loss of
   vegetation;
   Clearing of vegetation will be minimised at equipment storage and marshalling areas and at borrow
   and other material storage areas avoid exposing sensitive soils;
   The RoW clearing and grubbing boundaries will be flagged to ensure areas are not unnecessarily
   cleared.
   Re-vegetate/protect cleared areas and bare soils
   Protect temporary fills, stockpiles or exposed soils adjacent to drains, streams and canals with slope
   blankets or covers. Plastic sheeting, geotextiles and other manufactured products can be used as
   covers. Angular rocks may be suitable in protecting sensitive soils. All stockpile shall have a toe berm
   and should not be located within 10m of the watercourse.
   Use mulches and other organic stabilizers to minimise erosion until re-vegetation can be re-established
   Divert runoff away from cleared areas
   Minimise the flow of water onto cleared areas;
   Isolate cleared areas;
   Retain natural drainage patterns wherever possible;
   Establish permanent erosion control as soon as possible

The most important aspect of erosion control is to apply permanent stabilisation and re-vegetation as soon
as possible. As soon as areas are graded to final slope lines and levels, and construction traffic no longer
needs to access an area, permanent erosion control measures will be put in place.

6.4      Sediment Control

During construction it is often impossible to protect all newly exposed soils from erosion; therefore it is
important to also apply sediment control measures at the same time as the erosion controls. Sediment
control typically focuses on managing water run-off from erosion prone areas. Water carrying sediment
must be directed away from entering waters that provide domestic and irrigation needs and contain aquatic
organisms or the water must be treated before it is released into such waters. Steps to control sediment
include:
    Control and collect runoff from erosion prone areas
    Minimise runoff velocities and erosive energy;
    Maximise the length of flow paths for precipitation or surface runoff to minimize energy of flow or
    employ structures such as check dams and ditch blocks.
    Discharge sediment-laden waters to re-vegetated areas where sediment can be filtered out before the
    water reaches any watercourses.
    Retain sediments on site with sediment control structures.
    Use correctly installed silt fences and other barriers;
    Provide bed-load clean-outs at culverts and ditches;
    Construct sediment traps in areas where ditch water must be intercepted to ensure sediment is not
    transported into watercourses;
    Construct sediment traps of sufficient size to handle the anticipated runoff.
    Regularly monitor erosion and sediment control measures to ensure that they are working effectively;



270299/EVT/EES/HYES/28/A                         49
Conservancy Adaptation Project: Pre-Investment Studies
Coastal Lolands Environmental Assessment for Civil Works



      Additional checks are required after rain events;
      Maintenance of sediment control devices includes the removal of accumulated sediments to maintain
      collection capacity;
      Have extra geo-textile (silt fencing), and /or gravel on hand to repair or install new sediment control
      structures as required.

6.4.1      Culvert/Bridges Sites

      Minimise clearing of banks and stabilize exposed slopes.
      Ditch water will be directed to vegetated areas or into sediment traps to filter out the sediment before it
      reaches developed areas.



6.4.2      Flooding

Cofferdams constructed to facilitate rehabilitation of culverts can impede drainage flow, in some cases
where there is excessive rainfall, minor flooding can result. The following mitigation impacts should be
implemented.

      Routine inspection to canal and cofferdams for possibility of rise in water level and breaches in
      cofferdam.
      Routine cleaning of connected channels that assist with drainage
      Identification of alternative drainage to divert water to.
      Mobile pumps of sufficient capacity should always be present on site to facilitate dewatering.
      In cases where there is no option to divert water, HDPE pipes can be used to facilitate flow of water.
      Constant monitoring of drains that are interconnected especially in areas that are highly populated to
      ensure that water levels are at minimal.

6.5        Specific Areas of Concern

6.5.1      Erosion and Sediment Control Recommendations for Specific Areas

The following are preliminary recommendations for erosion and sediment controls for the sensitive areas.
In some cases more detailed plans will be required prior to construction, and if necessary, will be
developed with input from the Contractor, Environmental Monitor and the Supervisors’ Representative.

6.5.1.1    Environmentally Sensitive Area

      “Close cutting” of the vegetation as opposed to clearing.
      Erosion and sediment control are a priority in these areas
      Pre-construction planning and a site review with Environmental Monitor will be required before
      construction activities take place.
      Water from construction areas along the upslope side of the road must not be allowed to flow directly
      onto cane fields and farm land.
      Ditches will be developed on the upslope side along with sediment traps to prevent sediment entering
      the cane fields

6.6        Grading and Topsoil Protection

      Excavated material not to be reused shall be stored at temporary sites




270299/EVT/EES/HYES/28/A                            50
Conservancy Adaptation Project: Pre-Investment Studies
Coastal Lolands Environmental Assessment for Civil Works



      Excess materials shall be placed in piles from which it may be replaced into its original position.
      Stockpiles shall not be placed within 10 m of any water body.
      Topsoil and subsoil shall be stripped and stockpiled separately to avoid mixing.
      In areas where soils are not to be removed, the grassed vegetative layer shall be maintained, where
      possible, to protect soils from compaction and erosion
      Topsoil shall be spread to a uniform depth of 5cm on designated areas. Areas where topsoil is to be
      placed shall be fine graded to a uniform surface. It shall be free of all vegetation and other debris, and
      free of stones, which would not be covered by the depth of topsoil of 5cm.
      Where excess topsoil is generated, that is not required for restoration of the construction area, this
      excess topsoil should be donated to the Local Government Authorities, as represented by the
      Neighbourhood Democratic Council for their use and distribution to local landowners.

6.7        Waste Management Plan

6.7.1      Purpose and Scope

This plan will ensure that waste generated during construction is handled in a way that protects the
environment and complies with applicable regulations. The following are some of the materials that can be
expected to generate during construction:

      Vegetation strippings
      Concrete forms
      Dimension lumber
      Packing materials
      Containers for various construction materials (e.g. asphalt, concrete and steel)
      Pallets
      Plastics
      Waste oil, filters, lubricants and hydraulic fluids
      Concrete
      Food
      Sewage

The plan addresses open burning, refuse disposal, recycling, reuse, sewage disposal, and camp (yard)
waste disposal practices.

6.7.2      Waste Management Practices

All organic and inorganic materials will be placed and/or disposed of so as not to directly or indirectly
impact any watercourse or groundwater. The placement and disposal of all such products and materials
will be done in an environmentally acceptable manner. Suitable landfill sites should be identified and
approved by the N.D.C for disposing of construction waste.

Any waste material that is inadvertently disposed in or adjacent to watercourses or other designated
environmentally sensitive areas will be removed immediately in a manner that minimises adverse impacts,
and the original drainage pattern will be restored.

All wastes which are not designated, as combustible waste to be burned on-site, will be recycled, disposed
of in an approved landfill, or shipped to an approved disposal facility.

Construction debris will not be allowed to accumulate on the construction site but will be collected promptly
and regularly removed from the site. Waste materials will be placed and stored in suitable containers.



270299/EVT/EES/HYES/28/A                            51
Conservancy Adaptation Project: Pre-Investment Studies
Coastal Lolands Environmental Assessment for Civil Works



Storage areas and containers will be maintained in a sanitary condition and covered to prevent spreading
of wastes by water, wind or animals.

Solids, sludges and other pollutants generated as a result of construction or removed during the course of
treatment or control of wastewaters will be disposed of in a manner that prevents their direct or indirect
discharge to any watercourse or ground waters.

6.7.2.1   Open burning

Open burning of wood debris generated by land clearing will be conducted in accordance with the
Standard and Special Specifications.

Open burning must be planned so that it does not adversely affect local residents during their daily lives.

Burning methods will be employed that will prevent heat or smoke damage to all vegetation that has been
designated for preservation. The use of waste oil and/or tires as fire accelerators is not permitted. Burning
pits will not be located within 50 m of any watercourse, wetland or other Environmentally Sensitive Area, or
in areas where ditches are to be constructed.

In situations where the material generated as a result of clearing and/or grubbing may not be burned on-
site, the disposal method must be approved by the Supervisor’s Representative or the Environmental
Officer/ Monitor.

6.7.2.2   Strippings

All waste and surplus material will be disposed in designated and approved areas. Not less than fifteen
days prior to disposing of any waste or surplus material, the Environmental Officer/Monitor will be provided
the locations, nature of the material being disposed, and stabilization technique.

Excavated material will be properly drained, spread and trimmed to a stable slope not exceeding 1.5 to 1,
in a manner which minimises disturbance of watercourses and vegetated areas. All waste sites will be re-
vegetated immediately after creation of the waste disposal site, or else suitable temporary erosion control
measures, such as tarps or plastic will be used until re-vegetation is undertaken.

6.7.2.3   Waste Oils and Special Wastes

Waste oils, special wastes, and refuse generated during the servicing of equipment (e.g., air and oil filters,
hydraulic fluids, petroleum products) will be stored, transported and disposed of in accordance with
regulations and the contract Specifications, and will not be disposed of by dilution, burial or incineration.

Where possible, waste oil, lubricants and other waste materials generated during the servicing of
equipment and machinery will be recycled. The dumping of oil or other deleterious materials on the ground
or in a watercourse is strictly prohibited.

Refuse generated during the servicing of equipment will be removed from the site and disposed of in an
approved facility.

6.7.2.4   Concrete Wastes

Fresh concrete or cement will be isolated from any designated watercourse for 48 hours after placement.
Containers or trucks carrying cement or fresh concrete will be washed at a site approved by the




270299/EVT/EES/HYES/28/A                          52
Conservancy Adaptation Project: Pre-Investment Studies
Coastal Lolands Environmental Assessment for Civil Works



Supervisor’s Representative. Concrete waste, including wastewaters from batching or cleaning, will only be
disposed of at approved and designated disposal sites. All cement-contaminated wastewater from cleaning
or mixing is to be considered toxic, and must be prevented from entering any watercourse for at least 48
hours to allow the water to reach neutral pH.

6.7.2.5   Food Waste

All food wastes will be collected and stored in containers and either incinerated daily or regularly
transported to the nearest operating landfill.

6.8       Fuel and Lubricants Management

Spill Contingency and Response Plan

6.8.1     Purpose and Scope

This document describes spill contingency measures and response plan for this Project. The plan is
designed to reduce impacts to the environment in the event of a spill through ensuring materials are
available and established procedures are followed.

The purpose of the spill contingency plan is to provide a course of action, which will be implemented to
allow a prompt and orderly response to spills that may occur during construction. A spill of any liquid, solid
or gaseous substance, which could impair the usefulness of the land, water or air where it is released will
be responded to by the procedures outlined in the contingency plan. The main objectives of the Spill
Contingency Plan are:
    To reduce the risk of harmful exposure to individuals and the surrounding environment;
    To clearly outline the action to take if a spill will occur; and,
    To ensure that project staff is aware of the correct response required.

“Spill “consists of unauthorised release or discharge into the environment of a substance in an amount
equal to or greater than the specified amount, or the uncontrolled release of any deleterious substance to
the environment. All spills will require immediate action as necessary, with priorities for:
    Protecting lives and preventing injuries;
    Protecting the environment; and,
    Protecting property.

This plan is intended to provide guidance in the event of a spill. The areas of responsibility of the various
personnel who will be directly involved are outlined to provide clear direction of what each person will be
doing at the time of an emergency. The Environmental Officer/ Monitor in consultation with the Supervising
Consultant will review this plan regularly. The review date will be recorded and kept on file.

6.8.2     Spill Response Plan

This section is designed to provide the reader with the methods of handling spills and the reporting
procedures required.

6.8.3     Reporting of Spills

All spills major or minor must be reported. Workers are to report all spills to their supervisor or
Environmental Officer/Monitor who will in turn report to the Supervising Consultant.




270299/EVT/EES/HYES/28/A                          53
Conservancy Adaptation Project: Pre-Investment Studies
Coastal Lolands Environmental Assessment for Civil Works




6.8.4      Minor Spills

Minor spills are those that can be easily and safely handled by those people in the area, and generally by
the person(s) initiating the spill. These spills are generally within confined areas, are small in nature, have
minimal health and safety risks, and have no chance of migrating into the environment.

6.8.5      Major Spills

These would be spills of greater potential than minor spills and have potential health and safety risks.
When in doubt, treat the spill as major. The Supervising Consultant must be contacted with the following
information:
    The person’s name and telephone number;
    The name and telephone number of the person who caused the spill;
    The location and time of the spill;
    The type and quantity of the substance spilled;
    The cause and effect of the spill;
    Details of action taken or proposed to stop, contain and minimize the effects of the spill;
    A description of the spill location and of the area surrounding the spill;
    Details of further action contemplated or required.

6.8.6      Spill Response Equipment

Spill response equipment will be provided and located in a designated spill response storage facility.

Any operations adjacent to a watercourse will have a spill kit present. Any used spill abatement and clean-
up materials will be promptly replaced.

6.9        Spill Conditions

6.9.1      Solid Material Spill in a Dry Area

      Clean up and recover material with protective gear.
      Detoxify the area.
      Store/transport recovered material and review the mode of disposal.

6.9.2      Liquid Material Spill in a Dry Area

      Contain spill using earthen berms.
      Clean up and recover material with protective gear. Material recovery may utilize pumps or
      absorbents as appropriate for type of spill.
      Detoxify area.
      Store/transport recovered material and review the mode of disposal.

6.9.3      Solid Material Spill in an Area Wet from Rain

      Cover material with plastic.
      Isolate any drainage from the spill area, if possible, using earthen berms.
      Notify downstream users if appropriate.
      Clean up and recover material using protective gear.
      Store/transport recovered material and review the mode of disposal.



270299/EVT/EES/HYES/28/A                            54
Conservancy Adaptation Project: Pre-Investment Studies
Coastal Lolands Environmental Assessment for Civil Works




6.9.4    Liquid Material Spill in an Area Wet from Rain

   Contain the spill using earth berms.
   Isolate drainage, if possible, using earth berms
   Notify downstream water users, if appropriate.
   Clean up and recover material using protective gear. Material recovery may utilize pumps or
   absorbents as appropriate for the type of spill.
   Detoxify the area.
   Store/transport recovered material and review the mode of disposal.

6.9.5    Solid or Liquid spill in a Drainage Ditch

   Contain the spill by placing an earth berm across the ditch as far downstream of the spill as possible;
   Isolate drainage, if possible using berm.
   Store/transport recovered material and review the mode of disposal

6.10     Specific Materials on Construction Projects

The following response actions are outlined for specific spills that, however unlikely, could occur during
road construction.

6.10.1 Petrol/Gasoline

Petrol/gasoline may be stored on-site for use in light vehicles. A list of the hazards associated with
petrol/gasoline, spill response, fire response and recovery methods are listed below. Varsol spills will be
treated as petrol/gasoline spills. Petrol/gasoline is:
    Highly flammable;
    Explosive when in a vapour form;
    Easily ignited by flame or spark; lighter than water (floats on water);
    Toxic to humans by ingestion and by aspiration; and
    Toxic to fish and other aquatic organisms

6.10.2 The initial response to petrol/gasoline spill will be:

   Stop the flow at the source if possible;
   Eliminate all possible sources of ignition (e.g., extinguish cigarettes, shut off motors);
   Evacuate danger area
   Carefully consider the hazards and merits of trying to contain the spill. Contain only if it is safe to do so
   and obvious benefit of containment is apparent (e.g., contain if flowing towards a water course).
   Otherwise leave gasoline to spread and evaporate.
   Notify the Environmental Officer/Monitor/ or the Supervisor’s Representative.

6.10.3 In the event of a fire, the response will be:

   Use CO2, dry chemical, foam or water spray (fog);
   Use jet streams to wash away burning gasoline;
   Divert the gasoline to an open area and let it burn off under control;
   Use water to cool tank surfaces;
   Be aware of re-ignition if the fire is put out before all the gasoline is consumed.




270299/EVT/EES/HYES/28/A                          55
Conservancy Adaptation Project: Pre-Investment Studies
Coastal Lolands Environmental Assessment for Civil Works



Petrol/gasoline can be recovered in the following manner:

    Unburned gasoline can be soaked up by sand and peat moss or by commercial sorbents;
    If necessary, contaminated soil will be excavated;
    Gasoline entering the ground can be recovered by digging sumps or trenches and pumping from below
    the water table

6.10.4 Petrol/ gasoline can be disposed of in the following manner:

Evaporation or incineration under controlled circumstances.

6.10.5 Other Fuels and Petroleum Products

Fuel and petroleum products spills will be contained using local earth materials and/or sandbags. Spill
clean-up equipment specifically designed for petroleum products are to be located at camp (will one be
established) and in the Maintenance Shop.

Spills or leaks of all light and medium oils, including fuel oil at storage facilities, will be responded to by the
following these steps:

    Identify the source of the leak or spill;
    Stop flow if possible
    Eliminate open flame ignition processes
    Contain the spill
    Notify the Supervising Consultant
    Initiate Spill Response Plan
    In the event of a tank rupture, the containment berm is designed to contain the full capacity of the tank.
    This will allow the oil to be contained and pumped out of the area into salvage tanks. Contaminated soil
    from the site will be excavated and transported to a treatment facility or treated onsite by air sparging.
    Spilled diesel fuel can be recovered by commercial sorbents or by sand, straw or peat moss. If
    necessary, contaminated soil will be excavated. Digging sumps or trenches and pumping from below
    the water table can recover Diesel fuel saturated soil.

6.10.6 Fuel spills on land will be responded to by the following procedures:

    Construct a earth berm down slope of the running or seeping fluid;
    Plastic tarps may be placed at the base of the berm to allow the fuel to pool on the plastic for easy
    capture with absorbent pads;
    Pads may be squeezed into empty drums and re-used;
    Larger pools can be pumped back into drums;
    Special care will be taken to prevent the fuel from entering a body of water where it will; have greater
    negative impact;
    Contaminated soil and vegetation may have to be removed and disposed of.

6.10.7 Fire response methods for diesel fuel include:

    CO2, dry chemical, foam, or water spray;
    Water to cool tank surfaces;
    Diversion of the diesel to an open area and let it burn off under control;
    Awareness of re-ignition if the fire is put before all the diesel fuel is consumed.




270299/EVT/EES/HYES/28/A                            56
Conservancy Adaptation Project: Pre-Investment Studies
Coastal Lolands Environmental Assessment for Civil Works



Fuel spills on water must be contained immediately to restrict the extent of the floating fuel. The methods,
which may be used to contain fuel oil, include:

   Booms deployed to contain the spill area;
   Absorbent pads used to capture small spills on water;
   A skimmer to recover oil contained by the boom and then pump the recovered fuel into empty fuel
   drums; and
   Culverts (CMP’s or plastic) to permit water flow while capturing and collecting fuel. The culvert can be
   surrounded with absorbent material to capture any fuel on the water surface.

6.10.8 Concrete and/or Concrete Wastewater

During any concrete pour within 15 metres of, or in work areas below, the high water level of any
watercourse, carbon dioxide cylinders will be ready for use in the event of concrete or concrete-leachate
discharges into the watercourse. The carbon dioxide will be used to neutralise any concrete leachate that
is inadvertently discharged into the watercourse.

6.10.9 Acid Spills

Spills of acid will be contained using sandbags and neutralization can be accomplished using either soda
ash or lime. Both the sandbags and lime will be stored at the maintenance yard. Following neutralisation,
the area must be carefully flushed with water.

Note: Prior to using water in any clean-up, consult the guidelines for the specific chemical, as appropriate
use of water may be severely hazardous.

Any water used for flushing a spill will be contained, recovered and disposed of in an approved manner.

Mock Spill activity will be conducted.

A minor spill will be staged and spill response and clean up mechanism will be demonstrated. The
following key steps will be outlined/demonstrated during the exercise:

Marked the area to conduct exercise.
   Spill Waste In marked area.
   Spill was identified.
   Notify the Consulting Engineer
   Use of protective gears (gloves, goggles and rubber boots) to clean up and recover the material.
   Apply absorbent pad to absorb spilled liquid.
   Remove recovered material (contaminated soil) using a shovel.
   Remove the portion of the contaminated soil and place in heavy duty garbage bags.
   Store spilled material in a sealed five gallon container.
   Transport to the Site Office and store securely.
   Dispose material at the Haags Bosch Landfill site.

Discussion of use and importance of the following Basic Safety Gears will be identified and use was
demonstrated.
    Safety Vests
    Helmets
    Safety Boots
    Goggles



270299/EVT/EES/HYES/28/A                         57
Conservancy Adaptation Project: Pre-Investment Studies
Coastal Lolands Environmental Assessment for Civil Works



   Gloves
   Dust masks
   Fire Extinguishers.

6.11     Traffic Management Plan

In cases where construction works ( culverts or bridges) bypass roadways or secondary roads that are
frequently used by motorists the following traffic management strategies should be
implemented.Throughout the course of the works the Contractor will be responsible for the safety of all
persons present on the site of the works. As such, the Contractor will ensure, as far as is reasonably
practicable and to the satisfaction of the engineer, the health, safety and welfare of employees, including
those of sub-contractors and all other persons on the site. The responsibilities undertaken will include.

    (a) The execution of suitable arrangements for ensuring safety and absence of risks to health in
        connection with use, handling, storage, transport and disposal of articles and substances;
    (b) The provision of protective clothing and equipment, first aid stations with such personnel, and
        equipment necessary and the required information, instruction, training and supervision to ensure
        the health and safety at work of all persons employed on the works, all in accordance with
        applicable laws;
    (c) Designation as a safety officer one of his senior staff who has specific knowledge of safety
        regulations, and experience of safety precautions on similar works and who will advise on all
        matters affecting the safety of workmen and on measures to be taken to promote such safety;
    (d) The provision and maintenance of access to all places on the site in a condition that is safe and
        without risk of injury;
    (e) The provision of adequate waterborne sanitation, refuse collection and disposal complying with all
        applicable laws and bye-laws and to the satisfaction of the engineer, for all houses, offices,
        workshops, and laboratories erected on the cap site or sites;
    (f) The provision and maintenance of an adequate number of portable toilets and other sanitary
        arrangements at sites where work is in progress and the execution of appropriate measures in
        consultation with the appropriate Public Health Authority to control within the site, mosquitoes, flies
        and pests including the application of suitable chemicals to breeding areas.

General Provisions

The Contractor is required to conduct activities in a manner that ensures the safety and convenience of the
public and protects the residents and property adjacent to the site.
   Throughout the project the Contractor shall ensure that the public road remains open and available for
   use in good condition and that delays to traffic are minimized.
   The Contractor shall keep existing roads open to traffic during construction operations but ensure that
   one lane is available for access.
   The Contractor shall keep roads and sidewalks affected by the activities free from soil and material
   spillage and ensure that construction areas can accommodate traffic safely at all times. The Contractor
   is required to erect and maintain signs, barricades, and other traffic control devices as may be required
   to guide traffic inside and outside work areas and as indicated by the Manual of Uniform Traffic Control
   Devices, Part 6- Temporary Traffic control or as by directed by the Engineer. The Contractor, will
   replace traffic control devices that become lost, stolen, destroyed or deemed unacceptable while their
   use is required.
   During non-working hours and following completion of a particular construction operation, all warning
   signs, except those necessary for public safety, will be removed. Retro-reflective and painted surface
   on signs barricades, and other devices will be kept clean, in a good state of repair and retain their




270299/EVT/EES/HYES/28/A                          58
Conservancy Adaptation Project: Pre-Investment Studies
Coastal Lolands Environmental Assessment for Civil Works



    retro-reflective ability at all times. Sizes, colours, messages and locations will all be to the approval of
    the engineer.
    The Contractor shall take care at all times to ensure the convenience and safety of residents along and
    adjacent to the road and any public highway affected by the works. Access to property adjacent to any
    work site will be maintained at all times.

Obstruction of Traffic

The Contractor will ensure that the flow of traffic is unimpeded by construction-related activities. Two lanes
of traffic will be maintained at all times. In cases where it is absolutely necessary to close the road to
facilitate the works, the contractor will ensure that closure of one lane is done .

The lane width will be increased by temporarily grading and backfilling the existing road shoulder on both
sides of the carriageway. Temporary road surfacing material will be used to widen the road shoulder. All
diversions, widened shoulders will be maintained throughout the duration of construction works. If the
option of widening the carriageway is not feasible in areas of limited space the option of diverting traffic
through the secondary roads in the project area will be explored.

Construction and Advisory Signs

The contractor is required to supply, install, maintain and remove of all works-related signs. All signs will be
made in accordance to the Manual of Uniform Traffic Control Devices (MUTCD).Sign panels will be orange
with black legend and be mounted on stands. The location and type of each sign will depend on the area of
placement.

Flagmen

At each construction site traffic flow should be guided by flagmen with STOP/GO signs when necessary. At
the site traffic flow will be two-directional.

Lighting

Any existing roadway lighting that is disturbed during construction will be replaced with sufficient temporary
lighting to illuminate the same roadway surface. Adequate lighting will be provided for approved night
works to ensure the safety of road users and construction workers.

Access to Residents

The Contractor shall ensure that access to residences is adequately maintained in cases where access is
affected by construction works. If access fall within the construction zone that is demarcated, the
Contractor will ensure that access to the property is maintained by temporarily removing barricades. In
cases where bridges are demolished to facilitate the works, the contractor will provide suitable alternative
arrangements to allow access to properties.

Public Information Plan

The public will be informed through selective media of the project, duration and implementation phase.
Road users will be informed of possible traffic disruption and the importance of exercising caution in order
to minimize accidents. The NDCs will be engaged throughout the duration of the project to ensure
information is communicated to the communities. Residents living in close proximity to the works will be




270299/EVT/EES/HYES/28/A                           59
Conservancy Adaptation Project: Pre-Investment Studies
Coastal Lolands Environmental Assessment for Civil Works



informed of the project, the duration of the construction, possible inconveniences and measures that will be
implemented to lessen impacts.

Community Engagement

Contractors should engage affected stakeholders throughout the construction period to ensure that issues
that arise as a result of the works are addressed. Community meetings will be held periodically as the
works progresses. Contact information of staff members will be provided to community member to ensure
that issues are reported and addressed promptly.

6.12     Closure Plan

   Upon completion of construction, the Contractor shall demolish wholly or in part, remove and dispose
   of all buildings, structures, pipe culverts, fences, barriers and other obstruction that is not to remain on
   site to an approved landfill site.
   The Contractor shall arrange for disconnecting water supply and electricity supply.
   He shall remove all temporary drains, backfill trenches, fill in any pits created.
   The site and all staging area shall be restored as far as practicable to its original state and be left in a
   neat and tidy condition.
   The Contractor is responsible for producing a waste management plan of which the dismantling of
   construction site will have to be outlined in terms of disposal of materials.

6.16     Community Relations

Throughout the project area there are inhabitants that are likely to be affected by the project, residents
should be kept informed of ongoing activities at all times, and consulted about any works which would
impact their land or access to services, including irrigation supply. Any adverse impact to their land or
irrigation supply will be mitigated as described in the sections above. A grievance mechanism should be
set up that outlines the framework for addressing issues on site.

6.17     Workers Training Program

All employees directly and in-directly involved in the construction of the proposed culverts shall be trained.
This training program should aim to train and familiarize workers with the Environmental Management
plan, the implementation of the plan and application of the mitigation measures. Workers should receive
basic health and safety training to ensure that accident levels and mishaps on the construction site are
kept top the minimal level. The traffic management plan should be discussed in detail with the designated
traffic office and other ej.mployees responsible for traffic management, to ensure that effective traffic
control mechanisms are in place and a free flow of traffic is maintained at all times. Safety of road users
and construction employees is an important issue that need special consideration and training in traffic
management will assist in implementing the Traffic management Plan.

All construction workers should be familiar with the construction impact and preventative measure
identified in this EMP as it related to waste management, general construction, water management,
erosion and sedimentation control, dust and noise pollution, flora and fauna protection.




270299/EVT/EES/HYES/28/A                          60
Conservancy Adaptation Project: Pre-Investment Studies
Coastal Lolands Environmental Assessment for Civil Works



7            Health, Safety and Welfare during
             Construction
7.1          Management of Health and Safety

7.1.1        Health and Safety Plan

Under the specifications the Contractor will be required to propose a Health and Safety Plan which will
outline their strategy for ensuring the safety of all stakeholders in the vicinity of the construction site. This
should comply with all guidelines outlined in the Occupational Health and Safety Act, as well as the
recommendations listed below.

Consideration should be given to the following measures to manage health and safety during the
construction phase in the Health and Safety Plan.
   Designation of a person on staff with responsibilities for Occupational Health and Safety.
   Risk assessment with mitigation measures as discussed below.
   Protocol for training and toolbox talks for all site personnel.
   Protocol for talking through risk assessment with site personnel, and having all site personnel sign risk
   assessment to agree to follow mitigation measures.
   Reporting procedures for near misses, accidents and dangerous actions.
   Commitment to ensure all PPE, first aid equipment, and safety equipment are provided in accordance
   with the risk assessment.
   Procedures for site inductions to be given to site visitors.

7.1.2        Health and Safety Risk Assessment and Identification of Mitigation Measures

Key to the development of the Health and Safety Plan is the production of a comprehensive risk
assessment. As a minimum the risks and mitigations given in the example risk assessment included in
Appendix B must be included.

In determining the mitigations for risks identified, the Contractor should consider that risk control measures
should preferably be collective rather than personal. In descending order of effectiveness, the hierarchy of
                     1
risk control involves :
1. changes that eliminate a hazard
2. substitution of less hazardous methodology
3. enclosure – isolation, barriers, guarding or segregation, all of which are designed to separate people
     from the hazard
4. reduced exposure – changes that reduce the time individuals are exposed to a risk, or the number of
     people exposed
5. safe systems of work, together with suitable training and supervision
6. written procedures, and the provision of information, instruction, warnings, signs and/or labels
7. use of personal protective equipment (PPE)

In preparation of the risk assessment the Contractor must consider measures to ensure the safety of all
persons within the vicinity of the works. Examples of risks and mitigations to be considered are listed
below:
    Provision and maintenance of construction sites that are lighted, safe and without risks to health.


1
    CDM 2007 Construction Work Sector Guidance for Designers Section 1.4.7



270299/EVT/EES/HYES/28/A                                  61
Conservancy Adaptation Project: Pre-Investment Studies
Coastal Lolands Environmental Assessment for Civil Works



   Provision of signage and fencing to stop access to work site by members of the general public.
   The execution of suitable arrangements for ensuring safety and absence of risks to health in
   connection with the use, handling, storage, transport and disposal of articles and substances
   Provision and maintenance of access to all places on site is in a condition that is safe and without risk
   of injury.
   Provision of protective clothing and safety gear (hard hats, hearing protection, goggles and other
   devices for activities).
   Provision of First Aids Kits.
   Arrangements for transfer to nearby hospital to deal with emergencies.
   Provision and maintenance of adequate sanitation, refuse collection and waste disposal.
   Provision of continuous supply of fresh water on site.
   Designation of a safety officer of one of the Contractors senior staff who will have specific experience
   and knowledge of safety regulations on similar projects.

7.1.3    Health and Safety Training for Workers

All employees will undergo Health and Safety Training prior to commencement of constructions. Training
sessions will also be ongoing throughout the construction phase to ensure full compliance with the
approved Health and Safety Plan. The risk assessment will be discussed with all staff to ensure
prescribed procedures and recommendations are clear.

Key points to be covered in training of all site workers
   Obligations on employee as regards adherence to risk assessment and hazard reporting
   Risks posed by Site Conditions and Climate
   Behaviour on site
   Communication with the Public.
   Emergency Response (Fire, Health, Spills)
   Spill Response Mechanism
   Waste Management.
   Traffic Safety and Management
   Working hours and breaks

Discussion of use and importance of the following safety equipment will be identified and demonstrated.
    High visibility clothing
    Hard hats
    Steel toe-capped boots
    Goggles
    Gloves
    Dust masks
    Fire Extinguishers.

Key points to be covered in training of machinery operatives
   Qualifications and licences required for all operatives of heavy machinery
   Safe systems of work to protect operatives, site workers, public and property
   Use of banksmen at all times
   Ground conditions at work site
   Areas to be avoided
   Methods of working to ensure safety in poor ground conditions
   Working hours and breaks
   Carriage of passengers
   Use of seat belts



270299/EVT/EES/HYES/28/A                        62
Conservancy Adaptation Project: Pre-Investment Studies
Coastal Lolands Environmental Assessment for Civil Works



   Use of PPE
   Use of fire extinguishers and spill kits
   Smoking
   No operative to operate heavy machinery while under the influence of alcohol
   No operative to operate heavy machinery while excessively tired
   Use of mobile phones while operating machinery
   Maintenance of equipment

7.1.4    Site Inductions

All persons who have not undergone training as described above must be given a site induction before
entering the work site. Key points to be addressed in this induction include:
     Talking through and signing off on relevant parts of the risk assessment,
     Particular hazards relevant to visitor
     Behaviour on site
     Wearing of PPE
     Location of First Aid and Safety Equipment
     Introduction to nominated safety officer
     Entry and exit routes




270299/EVT/EES/HYES/28/A                       63
Conservancy Adaptation Project: Pre-Investment Studies
Coastal Lolands Environmental Assessment for Civil Works



8        References

1. SNC. Lavalin International, May, 2001.Mahaica-Rosignol Road-Design and Feasibility Study
   Environmental Management Plan.
2. NDLEA-CEMCO 2006. Berbice River Bridge Environmental and Social Impact Assessment.
3. NDLEA-CEMCO 2007. Berbice River Bridge. Environmental Management Plan.
4. WSP imc in assoc with CEMCO Inc, April,2008, Economic Analysis, Environmental Assessment and
   Design Studies .Lot 2B Transport Infrastructure Rehabilitation Programme Feasibility Report.
5. WSP imc in assoc with CEMCO Inc, April,2008, Economic Analysis, Environmental Assessment and
   Design Studies .Lot 2B Transport Infrastructure Rehabilitation Inception Report.
6. WSP imc in assoc with CEMCO Inc, March, 2008, Economic Analysis, Environmental Assessment and
   Design Studies. Lot 2B Transport Infrastructure Rehabilitation. Condition Study Report of Structure in
   Lot 2B.
7. EMC- 2011. East Demerara Water Conservancy Northern Relief Structure- Environmental
   Management Plan.




270299/EVT/EES/HYES/28/A                       64
Conservancy Adaptation Project: Pre-Investment Studies
Coastal Lolands Environmental Assessment for Civil Works



Appendices

 Appendix A.               Example Forms                                        66

 Appendix B.               Example Health and Safety Risk Assessment            76

 Appendix C.               Correspondence Regarding Drainage Regime Modelling   82




270299/EVT/EES/HYES/28/A                      65
Conservancy Adaptation Project: Pre-Investment Studies
Coastal Lolands Environmental Assessment for Civil Works




Appendix A. Example Forms

   A.1. Daily Environmental Inspection Summary - Construction

National Drainage and Irrigation Authority.

Ministry of Agriculture.

PROJECT: Conservancy Adaptation Project – Coastal Civil Works

DAILY ENVIRONMENTAL INSPECTION SUMMARY-CONSTRUCTION

Location(Chainage) ---------------- to------------------

Inspection Date:

DAY OF:

General                                          Yes        No   N/A

    Sand Bags, silt fencing and
    absorbent material readily available
    for emergency.
    Erosion and sediment control
    measures in place
    Dust control measures in place.
    All workers outfitted with necessary
    PPE.
    First Aid Kits on site
    Spill kits on site
    All warning signs in place.

Waste and Spills Management
  Garbage ,scrap material and waste
  collected in suitable receptacles
  No servicing or refilling with 30 m of
  watercourse
  Spill containment material available
  on site
  Vegetation material gathered for
  removal
  Waste construction stockpile not
  older than 30 days.
  Drip pans available in site

Erosion and Sediment Control
   Stockpiles do not interfere with
   surface drainage




270299/EVT/EES/HYES/28/A                               66
Conservancy Adaptation Project: Pre-Investment Studies
Coastal Lolands Environmental Assessment for Civil Works



   Stockpiles protected from wind and
   water erosion
   Silt fencing/trenching/berming in
   place
   Stockpiles not located within 10m of
   watercourses.

Water Management
   Watercourse flow maintained
   No equipment, waste material or
   construction material stored within 10
   m of watercourse
   Site dewatering pump outlets to
   vegetated area and not within 10 m
   of watercourse.

Other Observation/Comments




Issues Raised




Environmental Inspector’s Signature                        Date:




270299/EVT/EES/HYES/28/A                      67
Conservancy Adaptation Project: Pre-Investment Studies
Coastal Lolands Environmental Assessment for Civil Works




  A.2. Weekly Environmental Inspection Summary - Construction

National Drainage and Irrigation Authority. Ministry of Agriculture.

PROJECT: Conservancy Adaptation Project – Coastal Civil Works

WEEKLY ENVIRONMENTAL INSPECTION SUMMARY-CONSTRUCTION

Location(Chainage) ---------------- to------------------

Inspection Date:

WEEK OF:

Summary of Works completed:

Contractor:




Consultant:




Summary of Construction Activities and Site Conditions during the Week.




Environmental Management
   Onsite Traffic/Traffic Management




    Waste Management/Housekeeping


Safety Equipment/Spill Kits



Dust and Noise




Fuel Spills




270299/EVT/EES/HYES/28/A                              68
Conservancy Adaptation Project: Pre-Investment Studies
Coastal Lolands Environmental Assessment for Civil Works



Sediment and Erosion Control



Dredging and Disposal



Public Complaints



Health, Safety and First Aid




   Accidents/Near Misses/Lost Time




Licenses – Permits




Outstanding Corrective Actions (attach extra sheets if necessary)




Location:

Action Item and Status:




Issues Raised:




Environmental Inspector’s Signature:                        Date:




270299/EVT/EES/HYES/28/A                      69
Conservancy Adaptation Project: Pre-Investment Studies
Coastal Lolands Environmental Assessment for Civil Works




  A.3. Monthly Environmental Inspection Summary - Construction

National Drainage and Irrigation Authority. Ministry of Agriculture.

PROJECT: Conservancy Adaptation Project – Coastal Civil Works

MONTLY ENVIRONMENTAL INSPECTION SUMMARY-CONSTRUCTION

Location(Chainage) ---------------- to------------------

Inspection Date:

MONTH OF: .

Summary of Works completed:

Contractor:




Consultant:




Summary of Construction Activities and Site Conditions during the Week.




Environmental Management


    Onsite Traffic/Traffic Management


    Waste Management/Housekeeping


Safety Equipment/Spill Kits



Dust and Noise




Fuel Spills


Sediment and Erosion Control




270299/EVT/EES/HYES/28/A                              70
Conservancy Adaptation Project: Pre-Investment Studies
Coastal Lolands Environmental Assessment for Civil Works



Dredging and Disposal



Public Complaints



Health, Safety and First Aid




   Accidents/Near Misses/Lost Time




Licenses – Permits




Outstanding Corrective Actions (attach extra sheets if necessary)




Location:




Action Item and Status:




Issues Raised:




270299/EVT/EES/HYES/28/A                      71
Conservancy Adaptation Project: Pre-Investment Studies
Coastal Lolands Environmental Assessment for Civil Works




 A.4. Quarterly Environmental Inspection Summary - Construction

Environmental Inspector’s Signature:                          Date:

National Drainage and Irrigation Authority. Ministry of Agriculture.

PROJECT: Conservancy Adaptation Project – Coastal Civil Works

QUARTERLY ENVIRONMENTAL INSPECTION SUMMARY-CONSTRUCTION

MONTH/YEAR:




Summary of Construction Activities/Progress:

Contractor:




Summary of Major Environmental Issues :




Summary of Environmental Mitigation.


Public Complaints




Outstanding Corrective Actions (attach extra sheets if necessary)




Location:




Issues Raised:




Environmental Inspector’s Signature:                          Date:




270299/EVT/EES/HYES/28/A                      72
Conservancy Adaptation Project: Pre-Investment Studies
Coastal Lolands Environmental Assessment for Civil Works




   A.5. Corrective Action Report

National Drainage and Irrigation Authority. Ministry of Agriculture.

PROJECT: Conservancy Adaptation Project – Dam Feasibility and Rehabilitation of Structures.

CORRECTIVE ACTION REPORT

Location (Chainage) ---------------- to------------------

Inspection Date:




Nature of Non-compliance (attach inspectors report):




Description of Corrective action Taken (attach Photo) :




Environmental Inspector’s Signature:                          Date:




270299/EVT/EES/HYES/28/A                              73
Conservancy Adaptation Project: Pre-Investment Studies
Coastal Lolands Environmental Assessment for Civil Works




 A.6. Post Environmental Inspection Summary - Construction

National Drainage and Irrigation Authority. Ministry of Agriculture.

PROJECT: Conservancy Adaptation Project – Coastal Civil Works

POST ENVIRONMENTAL INSPECTION SUMMARY-CONSTRUCTION

Location(Chainage) ---------------- to------------------

Inspection Date:




General                                     Yes        No   N/A

   Sand Bags, silt fencing and
   absorbent material removed where
   not protecting exposed slopes.
   Erosion and sediment control
   measures effectively prevents
   sedimentation.
   All services disconnected, buildings
   dismantled.

Waste and Spills Management
   Garbage, scrap material and waste
   collected in suitable receptacles are
   removed from site.
   All spill kits removed.
   Vegetation material removed
   Waste construction stockpile have
   been removed and graded.

Erosion and Sediment Control
   Surface drainage around stockpiles
   restored to pre-construction condition
   Exposed slopes graded to present
   erosion
   Toe berms or sandbags in place
   where slopes are not stable.

Water Management
   Watercourse flow maintained and
   free of obstruction.



Other Observation/Comments




270299/EVT/EES/HYES/28/A                          74
Conservancy Adaptation Project: Pre-Investment Studies
Coastal Lolands Environmental Assessment for Civil Works




Issues Raised




Environmental Inspector’s Signature                        Date:




270299/EVT/EES/HYES/28/A                      75
Conservancy Adaptation Project: Pre-Investment Studies
Coastal Lolands Environmental Assessment for Civil Works



Appendix B. Example Health and Safety Risk Assessment


Health & Safety Risk
Assessment
Project Title          Conservancy Adaptation Project                          Project Number                                   xxxxxx
Project Manager*       xxxxxx                                                  Project Director*                                xxxxx
Work Activities        Civil Works to Region 4 Drainage Regimes



                                                                                                                    Can the                                                                            Responsibility
                                                                                                                                                                                                                        Action
                                                                  Persons at   Initial risk                         hazard be                                     Residual risk                        for
Hazard / Aspect (1)    Consequence / Impact (2)                                                                                 Control measures (6)                                                                    completed/
                                                                  risk (3)     level (4)                            avoided?                                      level (7)                            implementing
                                                                                                                                                                                                                        due (9)
                                                                                                                    (5)                                                                                (8)




                                                                                                       Risk Level




                                                                                                                                                                                          Risk Level
                                                                                          Likelihood




                                                                                                                                                                             Likelihood
                                                                               Severity




                                                                                                                                                                  Severity
                                                                                                                    Y/N




                       There may be local levels of biological
                                                                                                                                Adequate, easily accessible,                                           Contractor
Working Near Water -   contamination which could lead to          All site
                                                                               3          1            M            Y           safe drinking water should be     3          1            M            Project          Ongoing
Sickness               sickness, such as leptospirosis, if        personnel
                                                                                                                                provided to all site personnel                                         Manager
                       ingested.



                       Soft, uncompacted and ill-defined bank
                       conditions and extensive working near                                                                    The wearing of buoyancy aides
                                                                                                                                                                                                       Contractor
Working Near Water -   water increase the probability of site     All site                                                      should be enforced for all site
                                                                               3          2            H            N                                             3          1            M            Project          Ongoing
Drowning               personnel falling into the deep            personnel                                                     personnel. Lone working
                                                                                                                                                                                                       Manager
                       perimeter channel or shallower                                                                           should not be permitted.
                       downstream channels




270299/EVT/EES/HYES/28/A                               76
Conservancy Adaptation Project: Pre-Investment Studies
Coastal Lolands Environmental Assessment for Civil Works


                                                                                                    All operators must be well
                                                                                                    trained. Banksmen must be
                             Soft, uneven ground conditions
Operating Earth Moving                                                                              used at all times. Hazardous                   Contractor
                             increase likelihood of plant toppling,     All site
Plant - Injury from                                                                 3   2   H   N   ground conditions should be        3   1   M   Project      Ongoing
                             leading to injury of operator or nearby    personnel
Toppling Plant                                                                                      identified and discussed with                  Manager
                             personnel
                                                                                                    operator at start of each
                                                                                                    operation
                                                                                                    All operators must be well
                                                                                                    trained. Banksmen must be
                             Soft, uneven ground conditions and
                                                                                                    used at all times. Hazardous                   Contractor
Operating Earth Moving       proximity to channels increase             Plant
                                                                                    3   2   H   N   ground conditions should be        3   1   M   Project      Ongoing
Plant - Drowning             likelihood of plant toppling into water,   operators
                                                                                                    identified and discussed with                  Manager
                             trapping operator underwater
                                                                                                    operator at start of each
                                                                                                    operation
                                                                                                    All operators must be qualified,
                                                                                                    licensed and well trained.
                                                                                                    Banksmen must be used at all
                                                                                                    times. All personnel entering
                                                                                                    site should be briefed on
                             Volume of earth moving activities
Operating Earth Moving                                                                              hazards. Wearing of                            Contractor
                             required increases likelihood of bucket    All site
Plant - injury from plant                                                           3   2   H   N   appropriate PPE, including         3   1   M   Project      Ongoing
                             or body of machine striking site           personnel
striking site personnel                                                                             high-vis and hard hats, should                 Manager
                             personnel
                                                                                                    be enforced for all personal
                                                                                                    entering site. No person who is
                                                                                                    under the influence of alcohol
                                                                                                    or excessively tired is
                                                                                                    permitted to operate machinery
                                                                                                    All operators and drivers must
                                                                                                    be well trained. Banksmen
                                                                                                    must be used at all times. All
                                                                                                    personnel entering site should                 Contractor
Site Traffic - Injury from   Scale of operation increases likelihood    All site
                                                                                    3   2   H   N   be briefed on hazards.             3   1   M   Project      Ongoing
collision                    of traffic collision                       personnel
                                                                                                    Wearing of appropriate PPE,                    Manager
                                                                                                    including high-vis and hard
                                                                                                    hats, should be enforced for all
                                                                                                    personal entering site.

                             Poor ground conditions and high water                                  All site personnel to be briefed               Contractor
                                                                        All site
Excavation Collapse          table increase likelihood of injury or                 3   2   H   N   on risk. All excavations to be     3   1   M   Project      Ongoing
                                                                        personnel
                             death following collapse of excavations                                properly shored up.                            Manager

                             Poor and uneven ground conditions                                      All site personnel to be briefed               Contractor
                                                                        All site
Slips, trips and falls       increase likelihood of injury following                3   2   H   N   on risk. Appropriate footwear      3   1   M   Project      Ongoing
                                                                        personnel
                             slips, trips and falls                                                 to be worn at all times.                       Manager




270299/EVT/EES/HYES/28/A                                       77
Conservancy Adaptation Project: Pre-Investment Studies
Coastal Lolands Environmental Assessment for Civil Works


                                                                                                      All site personnel to be briefed
                                                                                                      on risk. Appropriate PPE,
                             Concrete work during structure                                           including gloves and boots, to                   Contractor
                                                                          All site
Chemical burns               rehabilitation could lead to chemical                    3   2   H   N   be worn at all times. Washing        3   1   M   Project      Ongoing
                                                                          personnel
                             burns from cement                                                        facilities to be provided. Eye                   Manager
                                                                                                      wash to be made available and
                                                                                                      readily accessible.
                                                                                                      All site personnel to be briefed
                                                                                                      on risk. Contractor to provide
                                                                                                      suitable method statements.
                             Rehabilitation of Structures, particularly
                                                                                                      Appropriate scaffolding to be                    Contractor
Working from Height -        the operating machinery and access           All site
                                                                                      3   2   H   N   provided. Appropriate PPE,           3   1   M   Project      Ongoing
Injury from Falls            improvements, will lead to working from      personnel
                                                                                                      including harnesses if specified                 Manager
                             height
                                                                                                      in method statements, to be
                                                                                                      worn at all times. No lone
                                                                                                      working to be permitted.
                                                                                                      All site personnel to be briefed
                                                                                                      on risk. Contractor to provide
                             Rehabilitation of Structures, particularly
Working from Height -                                                                                 suitable method statements.                      Contractor
                             the operating machinery and access           All site
Injury from dropped                                                                   3   2   H   N   Appropriate scaffolding to be        3   1   M   Project      Ongoing
                             improvements, will lead to working from      personnel
objects                                                                                               provided with footboards.                        Manager
                             height
                                                                                                      Wearing of hard hats to be
                                                                                                      enforced for all site personnel.
                                                                                                      All site personnel to be briefed
                                                                                                      on risk. All site personnel to
Working in Hostile                                                                                    wear hard hats. Plenty of
                                                                                                                                                       Contractor
Environments - Injury or     Hot sunny weather increases risk of          All site                    drinking water to be available
                                                                                      2   2   M   Y                                        2   1   L   Project      Ongoing
Ill Health from Hot          burns, sun-stroke and dehydration            personnel                   and easily accessible. Sun
                                                                                                                                                       Manager
Conditions                                                                                            cream to be made available.
                                                                                                      Working hours to be restricted
                                                                                                      and breaks to be programmed.
                                                                                                      All site personnel to be briefed
Working in Hostile                                                                                    on risk and response. Medical
Environments - Injury or                                                                              officer with first aid training to               Contractor
                             Hostile fauna include bees, snakes,          All site
Ill Health following bites                                                            2   2   M   Y   be nominated. No lone                2   1   L   Project      Ongoing
                             tarantulas, ants, caiman and piranha.        personnel
or stings from Hostile                                                                                working to be carried out.                       Manager
Fauna                                                                                                 Vehicles to be available for
                                                                                                      transfer to hospital.




270299/EVT/EES/HYES/28/A                                      78
Conservancy Adaptation Project: Pre-Investment Studies
Coastal Lolands Environmental Assessment for Civil Works




Guidelines on how to complete the HRSA
Project
1. Record the hazard or aspect, e.g. exposure to noise, entering a confined space,
etc
2. Identify the worst-case effect of the hazard
3. Identify who could be affected by the risk, e.g. Project Team, Sub-consultants/contractors, Members of the
public, etc
4. Evaluate the level of risk for each hazard, by identifying its severity of harm and likelihood, using the risk matrix shown below
5. Ascertain if high risk, can hazard be avoided?
6. Identify control measures, noting that each hazard may require more than one control
measure
7. Evaluate the level of risk for each hazard, taking into account the effect of the control measure(s)
8. Identify who is responsible for implementing or ensuring that the control measures have been implemented
9. Record the date the actions completed or due


 Severity of Harm                                                   Likelihood                                                          Risk Level
                                        Severity                                                                          Probability                Probability Index
                                        Index                                                                             Index         Severity
                                                                                                                                        Index         1     2     3
 Death or major injury                       3                      Harm is certain or near certain to occur                     3           1        L     L     M
 Lost time injury or illness                 2                      Harm is likely to occur                                      2           2        L     M     H
 All other injuries or illnesses             1                      Harm is unlikely                                             1           3        M     H     H



Record of Health & Safety Risk Assessment

Completed by:                xxxxx                                        Approved:                       xxxxx

                                                                          (Project
(Project Manager)*           xxxxxx                                       Director)*                      xxxxx

Date:                                                             xxxxx   Date:




270299/EVT/EES/HYES/28/A                                     79
Conservancy Adaptation Project: Pre-Investment Studies
Coastal Lolands Environmental Assessment for Civil Works




270299/EVT/EES/HYES/28/A                     80
Conservancy Adaptation Project: Pre-Investment Studies
Coastal Lolands Environmental Assessment for Civil Works




270299/EVT/EES/HYES/28/A                      81
Conservancy Adaptation Project: Pre-Investment Studies
Coastal Lolands Environmental Assessment for Civil Works



Appendix C. Correspondence Regarding
            Drainage Regime Modelling




270299/EVT/EES/HYES/28/A                      82
Conservancy Adaptation Project: Pre-Investment Studies
Coastal Lolands Environmental Assessment for Civil Works




270299/EVT/EES/HYES/28/A                      83