The World Bank                                                                                     Implementation Status & Results Report
            Food Security and Agriculture Productivity Project (P155513)



Food Security and Agriculture Productivity Project (P155513)


 SOUTH ASIA | Bhutan | Agriculture and Food Global Practice |
 Recipient Executed Activities | Investment Project Financing | FY 2017 | Seq No: 8 | ARCHIVED on 20-Sep-2021 | ISR47859 |


 Implementing Agencies: Ministry of Agriculture and Forests, Ministry of Finance, Department of Public Accounts



 Key Dates


  Key Project Dates

   Bank Approval Date: 27-Apr-2017                                              Effectiveness Date: 08-Aug-2017
   Planned Mid Term Review Date: 20-Oct-2020                                    Actual Mid-Term Review Date: 30-Oct-2020
   Original Closing Date: 30-Dec-2024                                           Revised Closing Date: 30-Dec-2024
 pdoTable

 Project Development Objectives

  Project Development Objective (from Project Appraisal Document)
  The Project Development Objective (PDO) is to increase agricultural productivity and enhance access to markets for farmers in selected gewogs in
  south-west Bhutan.

  Has the Project Development Objective been changed since Board Approval of the Project Objective?
  No


 Components Table

 Name
 Component 1:Strengthening Farmer and Producer Groups:(Cost $1.24 M)
 Component 2: Enhancing Farmer Productivity:(Cost $8.03 M)
 Component 3: Enhancing Access to Markets:(Cost $2.42 M)
 Component 4: Project Management:(Cost $0.95 M)

 Overall Ratings

 Name                                                                         Previous Rating                          Current Rating

 Progress towards achievement of PDO                                          Satisfactory                            Moderately Satisfactory
 Overall Implementation Progress (IP)                                         Satisfactory                            Moderately Satisfactory
 Overall Risk Rating                                                          Moderate                                Moderate


 Implementation Status and Key Decisions

  The Additional Financing of USD 4.64 million to respond to COVID-19 had been approved in July 2021 and signed in August 2021.The Bank team
  reviewed the overall financial and physical progress of the project. The current disbursement is USD 7.41 million or 59 percent of the total grants
  (original and AF), or 93 percent of the original grant. The current expenditure is USD 6.06 million or 48 percent of total grants. The project has made
  considerable achievement on outcome indicators. With respect to PDO indicator 1 (productivity of targeted crops increased by at least 20 percent in
  project areas), the project has achieved 20 percent by midterm, exceeding the pre-AF end of project (EOP) target. With respect to PDO indicator 2
  (increase in both volume and value of produce marketed by at least 20 percent), the project has achieved 8 percent volume increase and 17
  percent value increase, meeting or exceeding expected achievement at midterm. With respect to PDO indicator 3 (number of direct project
  beneficiaries), the project has now reached 7,523 beneficiary households, or 63 percent of the total targeted households.
  Agreement was reached to focus attention on the following actions:


9/20/2021                                                                                                                       Page 1 of 9
            The World Bank                                                                                       Implementation Status & Results Report
            Food Security and Agriculture Productivity Project (P155513)



      1.      Fast-track the implementation of the Additional Financing activities to aid in mitigation of and recovery from the negative impacts of
              COVID-19.
      2.      Finalize the development of the group monitoring database and household-level database of project benefits; and ensure that these are
              leveraged to enhance the activities around strengthening/forming famer and producer groups, and to promote the equitable distribution of
              project benefits.
      3.      Realign the BCC content towards agriculture and household diets, clarify the role of the CRPs and enhance their training and incentives,
              and fast-track the BCC roll-out.
      4.      Monitor closely the finalization of key infrastructure under Component 2 (irrigation distribution networks) and Component 3 (farmer sales
              outlets or FSOs), with close attention to COVID-19 constraints.
      5.      Address key procurement constraints, including the hiring of a new Procurement Specialist via the FAO-TA and the designation of an
              RGoB official to support the procurement activities under FSAPP.
      6.      Streamline various data collection exercises including the fielding of the annual outcomes survey (AOS), the use of the RNR Statistics
              data, and the roll-out of the WB-IFPRI independent impact evaluation.




  Risks


 Systematic Operations Risk-rating Tool


  Risk Category                                                Rating at Approval              Previous Rating               Current Rating

  Political and Governance                                     Low                            Low                          Low
  Macroeconomic                                                Low                            Low                          Low
  Sector Strategies and Policies                               Moderate                       Moderate                     Moderate
  Technical Design of Project or Program                       Moderate                       Moderate                     Moderate
  Institutional Capacity for Implementation and
                                                               Moderate                       Moderate                     Moderate
  Sustainability
  Fiduciary                                                    Moderate                       Moderate                     Moderate
  Environment and Social                                       Moderate                       Moderate                     Moderate
  Stakeholders                                                 Low                            Low                          Low
  Other                                                        Low                            Low                          Low
  Overall                                                      Moderate                       Moderate                     Moderate



  Results


 PDO Indicators by Objectives / Outcomes



   Enhance productivity and marketable surplus

    IN01027504
    ►Productivity of targeted crops increased by at least 25 percent in project areas (Percentage, Custom)

                                         Baseline                     Actual (Previous)           Actual (Current)           End Target

    Value                                0.00                         20.00                       20.00                      25.00



9/20/2021                                                                                                                       Page 2 of 9
            The World Bank                                                                                 Implementation Status & Results Report
            Food Security and Agriculture Productivity Project (P155513)




    Date                                27-Apr-2017                 15-Feb-2021              15-Feb-2021              30-Dec-2024

    IN01027505
    ►Increase in volume of produce marketed by at least 25 percent (Percentage, Custom)

                                        Baseline                    Actual (Previous)        Actual (Current)          End Target

    Value                               0.00                        8.00                     8.00                      25.00

    Date                                27-Apr-2017                 15-Feb-2021              15-Feb-2021              30-Dec-2024

    IN01027556
    ►Increase in value of produce marketed by at least 25 percent (Percentage, Custom)

                                        Baseline                    Actual (Previous)        Actual (Current)          End Target

    Value                               0.00                        17.00                    17.00                     25.00

    Date                                27-Apr-2017                 15-Feb-2021              15-Feb-2021              30-Dec-2024

    IN01027557
    ►Number of direct project beneficiaries (Number, Custom)

                                        Baseline                    Actual (Previous)        Actual (Current)          End Target

    Value                               0.00                        6,526.00                 7,523.00                  11,938.00

    Date                                27-Apr-2017                 15-Feb-2021              01-Jul-2021              30-Dec-2024

     IN01027558
     Female Beneficiaries (Percentage, Custom Supplement)

                                      Baseline                     Actual (Previous)        Actual (Current)          End Target

     Value                            0.00                         29.00                    29.00                     34.00



 Intermediate Results Indicators by Components



   Strengthening farmers and producers groups

    IN01027561
    ►1.1 Number of beneficiary groups receiving technical trainings and other capacity building support (Number, Custom)

                                        Baseline                    Actual (Previous)        Actual (Current)          End Target

    Value                               0.00                        89.00                    97.00                     310.00

    Date                                27-Apr-2017                 30-Nov-2020              01-Jul-2021              30-Dec-2024

   IN01027566
   ►1.2 Number of farmers who are members of an association including producer groups, cooperatives etc. (disaggregated by gender) –
   GAFSP Core Indicator # 14 (Number, Custom)

                                        Baseline                    Actual (Previous)        Actual (Current)          End Target




9/20/2021                                                                                                                  Page 3 of 9
            The World Bank                                                                               Implementation Status & Results Report
            Food Security and Agriculture Productivity Project (P155513)




    Value                               0.00                        4,498.00               4,665.00                  11,788.00

    Date                                27-Apr-2017                 30-Nov-2020            01-Jul-2021              30-Dec-2024

     IN01027569
     Number of Female members of an association including producer groups, cooperatives etc (Number, Custom Breakdown)

                                      Baseline                     Actual (Previous)      Actual (Current)          End Target

     Value                            0.00                         1,349.00               1,470.00                  4,008.00

     Date                             27-Apr-2017                  15-Feb-2021            01-Jul-2021               30-Dec-2024

   IN01027571
   ►1.3 Number of people receiving improved nutrition services and products through the project - GAFSP Core Indicator # 11 (new GAFSP
   indicators) (Number, Custom)

                                        Baseline                    Actual (Previous)       Actual (Current)         End Target

    Value                               0.00                        1,207.00               1,647.00                  6,000.00

    Date                                27-Apr-2017                 30-Nov-2020            01-Jul-2021              30-Dec-2024

     IN01027573
     1.3.1 Number of people who received nutrition counseling/education (Number, Custom Supplement)

                                      Baseline                     Actual (Previous)      Actual (Current)          End Target

     Value                            0.00                         738.00                 738.00                    2,000.00

     IN01027576
     1.3.2 Number of people receiving extension support for nutrition-relevant techniques (Number, Custom Supplement)

                                      Baseline                     Actual (Previous)      Actual (Current)          End Target

     Value                            0.00                         38.00                  479.00                    4,000.00

     IN01027578
     Number of Females beneficiaries receiving improved nutrition services and products through the project-GAFSP Core Indicator # 11 (new
     GAFSP indicators) (Number, Custom Breakdown)

                                      Baseline                     Actual (Previous)      Actual (Current)          End Target

     Value                            0.00                         1,383.00               749.00                    2,400.00

     Date                             27-Apr-2017                  31-Dec-2019            01-Jul-2021               30-Dec-2024


   Enhancing farmer productivity

    IN01027562
    ►2.1 Targeted crop area provided with irrigation – GAFSP CI # 6 (Number, Custom)

                                        Baseline                    Actual (Previous)       Actual (Current)         End Target

    Value                               0.00                        2,191.00               2,193.00                  2,244.00

    Date                                27-Apr-2017                 15-Feb-2021            01-Jul-2021              30-Dec-2024

     IN01027564
     Area covered by Flood Irrigation (Number, Custom Breakdown)


9/20/2021                                                                                                                Page 4 of 9
            The World Bank                                                                                 Implementation Status & Results Report
            Food Security and Agriculture Productivity Project (P155513)




                                      Baseline                     Actual (Previous)       Actual (Current)           End Target

     Value                            0.00                         1,914.00                1,914.00                   1,914.00

     Date                             27-Apr-2017                  15-Feb-2021             15-Feb-2021                30-Dec-2024

     IN01027568
     Area covered by Micro Irrigation (Number, Custom Breakdown)

                                      Baseline                     Actual (Previous)       Actual (Current)           End Target

     Value                            0.00                         277.00                  279.00                     330.00

     Date                             27-Apr-2017                  15-Feb-2021             01-Jul-2021                30-Dec-2024

    IN01027577
    ►2.2 Number of water users with new/improved irrigation services – GAFSP Core Indicator # 8 (Number, Custom)

                                        Baseline                    Actual (Previous)        Actual (Current)          End Target

    Value                               0.00                        975.00                   1,062.00                  2,767.00

    Date                                27-Apr-2017                 15-Feb-2021              01-Jul-2021              30-Dec-2024

     IN01027579
     New users with Flood Irrigation (Number, Custom Supplement)

                                      Baseline                     Actual (Previous)       Actual (Current)           End Target

     Value                            0.00                         744.00                  744.00                     744.00

     IN01027580
     New users with Micro Irrigation (Number, Custom Supplement)

                                      Baseline                     Actual (Previous)       Actual (Current)           End Target

     Value                            0.00                         231.00                  318.00                     2,023.00

   IN01027581
   ►2.3 Number of farmers who have adopted an improved agricultural technology promoted by the project in targeted project areas (Number,
   Custom)

                                        Baseline                    Actual (Previous)        Actual (Current)          End Target

    Value                               0.00                        2,708.00                 3,582.00                  11,938.00

    Date                                27-Apr-2017                 15-Feb-2021              01-Jul-2021              30-Dec-2024

     IN01027582
     Number of Female farmers who have adopted an improved agricultural technology promoted by the project in targeted project areas
     (Number, Custom Breakdown)

                                      Baseline                     Actual (Previous)       Actual (Current)           End Target

     Value                            0.00                         1,120.00                1,376.00                   4,059.00

     Date                             27-Apr-2017                  15-Feb-2021             01-Jul-2021                30-Dec-2024

    IN01027583
    ►2.4 Total land area under cultivation for citrus and cardamom increased by 6 percent (Percentage, Custom)



9/20/2021                                                                                                                 Page 5 of 9
            The World Bank                                                                                   Implementation Status & Results Report
            Food Security and Agriculture Productivity Project (P155513)




                                        Baseline                    Actual (Previous)          Actual (Current)          End Target

    Value                               0.00                        5.50                       5.50                      6.00

    Date                                27-Apr-2017                 15-Feb-2021                15-Feb-2021              30-Dec-2024

     IN01027584
     Cardamom- cultivated area (Number, Custom Supplement)

                                      Baseline                     Actual (Previous)       Actual (Current)             End Target

     Value                            1,140.00                     1,195.00                1,195.00                     1,208.00

     IN01027585
     Citrus- cultivated area (Number, Custom Supplement)

                                      Baseline                     Actual (Previous)       Actual (Current)             End Target

     Value                            3,744.00                     3,931.00                3,931.00                     3,968.00

   IN01027586
   ►2.5 Number of beneficiaries reached, who have been helped to cope with impact of climate change; GAFSP Core Indicator # 1 (Number,
   Custom)

                                        Baseline                    Actual (Previous)          Actual (Current)          End Target

    Value                               0.00                        0.00                       0.00                      1,500.00

    Date                                27-Apr-2017                 30-Dec-2020                30-Dec-2020              30-Dec-2024

     IN01027587
     Number of female beneficiaries reached, who have been helped to cope with impact of climate change (Number, Custom Supplement)

                                      Baseline                     Actual (Previous)       Actual (Current)             End Target

     Value                            0.00                         0.00                    0.00                         510.00


   Enhancing access to markets

    IN01027559
    ►3.1 Number of beneficiaries of project supported market infrastructure (Number, Custom)

                                        Baseline                    Actual (Previous)          Actual (Current)          End Target

    Value                               0.00                        49.00                      49.00                     59.00

    Date                                27-Apr-2017                 30-Nov-2020                30-Nov-2020              30-Dec-2024

    IN01027563
    ►3.2 Number of producer groups receiving market information (Number, Custom)

                                        Baseline                    Actual (Previous)          Actual (Current)          End Target

    Value                               0.00                        30.00                      30.00                     40.00

    Date                                27-Apr-2017                 30-Nov-2020                30-Nov-2020              30-Dec-2024

    IN01027567
    ►3.3 Number of farmer groups linked to schools (Number, Custom)


9/20/2021                                                                                                                   Page 6 of 9
            The World Bank                                                                                     Implementation Status & Results Report
            Food Security and Agriculture Productivity Project (P155513)




                                        Baseline                    Actual (Previous)            Actual (Current)          End Target

    Value                               0.00                        20.00                        23.00                     25.00

    Date                                27-Apr-2017                 30-Nov-2020                  01-Jul-2021               30-Dec-2024

    IN01027574
    ►3.5 Proportion of beneficiaries with medium or high (>7) Household Dietary Diversity Score (Percentage, Custom)

                                        Baseline                    Actual (Previous)            Actual (Current)          End Target

    Value                               50.00                       50.00                        50.00                     70.00

    Date                                27-Apr-2017                 27-Apr-2017                  27-Apr-2017               30-Dec-2024

   IN01027575
   ►3.6 Number of post-harvest facilities constructed and or rehabilitated includes markets, agro-processing/storage/quality control facilities
   (Number, Custom)

                                        Baseline                    Actual (Previous)            Actual (Current)          End Target

    Value                               0.00                        13.00                        13.00                     32.00

    Date                                27-Apr-2017                 15-Feb-2021                  15-Feb-2021               30-Dec-2024



   Project Management

    IN01027560
    ►4.1 Learning notes or case studies published and disseminated (Number, Custom)

                                        Baseline                    Actual (Previous)            Actual (Current)          End Target

    Value                               0.00                        0.00                         0.00                      4.00

    Date                                27-Apr-2017                 30-Nov-2020                  30-Nov-2020               30-Dec-2024

    IN01027565
    ►4.2 Progress reports satisfactory (Text, Custom)

                                        Baseline                    Actual (Previous)            Actual (Current)          End Target
                                                                                                 Progress Reports are
                                                                    Progress Reports are
                                                                                                 submitted biannually      Accurate and timely
    Value                               reports prepared            submitted biannually and
                                                                                                 and current till June     reports
                                                                    current till June 2020
                                                                                                 2020
    Date                                27-Apr-2017                 30-Nov-2020                  01-Jul-2021               30-Dec-2024

    IN01027570
    ►4.3 Procurement satisfactory (Text, Custom)

                                        Baseline                    Actual (Previous)            Actual (Current)          End Target
                                                                                                                           Contracts awarded
    Value                               reports prepared            Yes                          Yes                       and completed on
                                                                                                                           schedule.
    Date                                27-Apr-2017                 30-Nov-2020                  01-Jul-2021               30-Dec-2024

    IN01027572


9/20/2021                                                                                                                      Page 7 of 9
            The World Bank                                                                                          Implementation Status & Results Report
            Food Security and Agriculture Productivity Project (P155513)




    ►4.4 Percentage of beneficiaries satisfied with services provided by the project. (Percentage, Custom)

                                        Baseline                      Actual (Previous)               Actual (Current)          End Target

    Value                               0.00                         40.00                            40.00                     50.00

    Date                                27-Apr-2017                  30-Nov-2020                      30-Nov-2020              30-Dec-2022



 Performance-Based Conditions



 Data on Financial Performance


 Disbursements (by loan)

 Project        Loan/Credit/TF     Status       Currency        Original     Revised      Cancelled      Disbursed       Undisbursed               % Disbursed


 P155513        TF-A4224           Effective    USD                8.00         8.00           0.00            7.41             0.59                      93%

 P155513        TF-B6044           Effective    USD                4.64         4.64           0.00            0.00             4.64                     0%%


 Key Dates (by loan)

 Project         Loan/Credit/TF     Status      Approval Date       Signing Date       Effectiveness Date       Orig. Closing Date      Rev. Closing Date

 P155513         TF-A4224           Effective   27-Apr-2017         18-May-2017        08-Aug-2017              30-Dec-2022             30-Dec-2024
 P155513         TF-B6044           Effective   15-Jul-2021         07-Aug-2021        07-Aug-2021              30-Dec-2024             30-Dec-2024


Cumulative Disbursements




9/20/2021                                                                                                                            Page 8 of 9
            The World Bank                                                                               Implementation Status & Results Report
            Food Security and Agriculture Productivity Project (P155513)




 PBC Disbursement

                                                                                        Achievement   Disbursed amount in     Disbursement %
 PBC ID                      PBC Type    Description            Coc        PBC Amount
                                                                                        Status        Coc                     for PBC




  Restructuring History


  There has been no restructuring to date.


  Related Project(s)


 P175717-Additional Financing for Food Security and Agriculture Productivity Project




9/20/2021                                                                                                               Page 9 of 9