The World Bank
        Tunisia Northern Tunis Wastewater Project (P117082)




                                                                                REPORT NO.: RES35587




                                              RESTRUCTURING PAPER

                                                       ON A

                                       PROPOSED PROJECT RESTRUCTURING

                                                      OF THE
                                 TUNISIA NORTHERN TUNIS WASTEWATER PROJECT
                                           APPROVED ON JUNE 17, 2010
                                                      TO THE

                                  OFFICE NATIONAL DE L'ASSAINISSEMENT (ONAS)




                                                December 10, 2019



WATER

MIDDLE EAST AND NORTH AFRICA




                                Regional Vice President:   Ferid Belhaj
                                      Country Director:    Jesko S. Hantschel
                                      Regional Director:   Ayat Soliman
                            Practice Manager/Manager:      Carmen Nonay
                                     Task Team Leader:     Zael G. Sanz
          The World Bank
          Tunisia Northern Tunis Wastewater Project (P117082)



ABBREVIATIONS AND ACRONYMS

CRDA              Agricultural Development Regional Commission (Commission Régionale de
                  Développement Agricole)
EIB               European Investment Bank
ERR               Economic Rate of Return
ESIA              Environmental and Social Impact Assessment
ESMP              Environmental and Social Management Plan
FM                Financial Management
GDA               Agricultural Development Group (Groupement de Développement Agricole)
GEF               Global Environment Fund
GEO               Global Environment Objective
IBRD              International Bank for Reconstruction and Development
ICT               Information and communication technology
IP                Implementation Progress
ISR               Implementation Status and Results Report
LAP               Land Acquisition Plan
mg/l              Milligrams per liter
mL                milliliters
m3/day            Cubic meters per day
m3/year           Cubic meters per year
NPV               Net Present Value
O&M               Operation and Maintenance
ONAS              Tunisia’s National Sanitation Office (Office National de l’Assainissement)
OPRC              Operational Procurement Review Committee
PDO               Project Development Objective
PPP               Public-Private Partnership
PS                Pumping Stations
STEG              Tunisia’s National Electricity and Gas Utility
TND               Tunisian Dinar
TSS               Total Suspended Solids
TWW               Treated Wastewater
US$               United States Dollar
WWTP              Wastewater Treatment Plant
           The World Bank
           Tunisia Northern Tunis Wastewater Project (P117082)




BASIC DATA


Product Information

Project ID                                                   Financing Instrument
P117082                                                       Investment Project Financing

Original EA Category                                         Current EA Category
Full Assessment (A)                                          Full Assessment (A)

Approval Date                                                Current Closing Date
17-Jun-2010                                                  31-Dec-2019


Organizations

Borrower                                                      Responsible Agency
Office National de l'Assainissement (ONAS)                    Office National de l'Assainissement (ONAS)



Project Development Objective (PDO)
Original PDO
The project development objectives of the Project are to: (a) provide an environmentally safe disposal system for the
treated wastewater which will not be reused in agriculture in the North of Tunis; and (b) increase the quantity and
quality of treated wastewatermade available to farmers to encourage its reuse in agriculture in the Borj Touil area.
Current PDO
The project development objective is to provide an environmentally safe disposal system for the treated wastewater in
the North of Tunis, and increase availability for its reuse in the Project Area.
OPS_TABLE_PDO_CURRENTPDO
Summary Status of Financing
                                                                                      Net
Ln/Cr/Tf                  Approval        Signing Effectiveness        Closing Commitment Disbursed Undisbursed

IBRD-86440            31-Aug-2016 30-Nov-2016 22-May-2017 31-Dec-2019                   18.00        3.77         14.25
IBRD-79170             17-Jun-2010   07-Oct-2010   14-Apr-2011 31-Dec-2019              39.40       39.40               0
TF-96891               07-Oct-2010   07-Oct-2010   14-Apr-2011    30-Jun-2016            8.03        8.03               0
        The World Bank
        Tunisia Northern Tunis Wastewater Project (P117082)


Policy Waiver(s)

Does this restructuring trigger the need for any policy waiver(s)?
No
             The World Bank
             Tunisia Northern Tunis Wastewater Project (P117082)



    I. PROJECT STATUS AND RATIONALE FOR RESTRUCTURING

    A. Introduction
      1. This Restructuring Paper proposes to extend by 18 months the closing date of Additional Loan IBRD 8644-TN
      associated with the Northern Tunis Wastewater Project (P117082). The extension will allow to incorporate under the
      scope of the “Part A” component the activities listed below, as well as help finalize the engineering designs and studies
      currently being developed under “Part C” of the Project:
      (i)      The procurement and installation of a pipeline to replace an open-air treated effluent canal situated upstream of
               the Project area. This is a critical component of the transfer system to provide an environmentally safe disposal
               system for the treated wastewater in Northern Tunis. These works were originally meant to be co-financed by the
               European Investment Bank (EIB) and the National Sanitation Office (ONAS) and would now be incorporated into
               the project scope with continued financial support from the EIB1;
      (ii)     Repair works, replacement and maintenance of equipment associated with wastewater treatment plants (WWTP)
               and pumping stations within the same wastewater collection and transfer system; and
      2. The implementation of these activities is critical to ensure the sustainability of the results achieved by the
      Project. These new activities would be financed by the remaining uncommitted balance of the additional financing
      loan approved in 2016. Due to the depreciation of the Tunisian dinar over the last few years (including by 21 percent
      and 11 percent, against the Euro and US$, respectively, since the approval of the Additional Loan in August 2016), the
      Project has accumulated savings of about US$13 million. This balance is enough to cover the costs associated with the
      new activities.
      3. This would be the first extension of the Additional Loan. The Additional Loan would be extended from December
      31, 2019 to June 30, 2021 to allow sufficient time for the above-mentioned activities to be completed.
      4. Other proposed changes. Concurrently with the closing date extension, the Project will be restructured to:
      (i) update the Results Framework; (ii) revise the project description of activities and costs; (iii) revise the disbursement
      estimates and implementation schedule; (iv) update the economic, financial, technical, social and environmental
      analysis to incorporate aspects related to the new activities added to the scope of the Project; and (v) the partial
      reallocation of IBRD loan proceeds from disbursement category 1 to a newly created category 3 earmarked for the co-
      financing of activities described in paragraph 1.i. above.

    B. Background
      5. The existing system of WWTPs in Northern Tunis is saturated, and discharges 70 million cubic meters of low-
      quality treated wastewater (TWW) into the El Khelij open-air canal. As it flows through the canal, this TWW is mixed
      with stormwater, irrigation drainage, local discharge of untreated wastewater, and unregulated solid waste disposal.
      Consequently, TWW quality further deteriorates as it runs along the canal, resulting in adverse social and economic
      impacts in the Project area. The canal then flows along the residential areas of the increasingly urbanizing city of
      Raoued, before reaching the shoreline and discharging into the Gulf of Tunis, thereby contaminating Raoued Beach.
      6. To address this issue, ONAS developed a program tackling the different links of the sanitation chain in the
      Northern Tunis urban area. The different projects and activities included in the program are described here below:
      (i)      Implementation of urgent repairs and rehabilitation works on the WWTPs and wastewater pumping stations
               of the Northern Tunis wastewater treatment system. This treatment hub comprises the WWTPs of Choutrana

1The Project would cover the 50 percent originally meant to be covered by ONAS counterpart funding, with the remaining 50 percent
still financed through the EIB loan.
             The World Bank
             Tunisia Northern Tunis Wastewater Project (P117082)


                I, Choutrana II, Côtière Nord and Charguia. Some key pieces of equipment of these facilities and of many of
                their associated pumping stations must be repaired or replaced in order to ensure an acceptable level of TWW
                quality for downstream users and discharge points. While some of these works are under implementation as
                part of projects financed by other financial partners, others were originally meant to be funded with fiscal
                resources. The implementation of the latter has not yet started as allocations from the National Treasury were
                postponed due to the deterioration of the fiscal situation in Tunisia.
    (ii)        Replacement of the open-air canal between the treatment hub and the existing pumping station operated by
                the Ariana Agricultural Development Regional Commission (CRDA) by a double TWW transmission pipeline.
                TWW from this treatment hub is currently discharged into the 4.3-kilometer open-air canal which ends at an
                existing pumping station operated by the Ariana CRDA for reuse in the nearby irrigation perimeter. This canal
                is to be replaced by a double transmission pipeline, which construction was to be co-financed by the EIB (50
                percent) and the Tunisian Government with fiscal resources (50 percent). Goods, works and services required
                for the implementation of these activities have already been procured. Approximately 60 percent of the pipes
                have already been delivered to the site and the contractor was recently mobilized to start installation. So far
                only 200 meters of pipes have been laid.
    (iii)       Covering of the existing canal between the CRDA pumping station and the existing discharge point into the
                Oued El Khelij. These works had already been completed by ONAS when the Project was designed.
    (iv)        Construction of a TWW transmission pipeline between the discharge point into the Oued El Khelij and a storage
                TWW basin. This two-compartment storage basin was built to both facilitate future TWW reuse in the Borj
                Touil irrigation perimeter, as well as to regulate the flow of TWW to be discharged into the Gulf of Tunis
                through the submarine outfall. The installation of the 2-kilometer conveyance pipes, as well as the
                construction of the storage basin and the associated pumping station were financed under the Project (under
                the “Part A” component) and are now fully completed and operational.
    (v)         Construction of a TWW effluent submarine outfall. TWW is conveyed from the storage basin’s pumping station
                through a 4-kilometer pressure pipeline to the headworks chamber of the 6-kilometer outfall. Both the outfall
                and pressure pipeline are financed under the Project (under the “Part B” component), have been completed
                and are fully operational.
    7. Table 1 summarizes the scope and implementation status of the different major infrastructure components of
    the program developed by ONAS to enhance the performance of the Northern Tunis wastewater treatment system,
    indicating which of said components are financed under the Project and the source of funding for those that are not.
TABLE ERROR! NO TEXT OF SPECIFIED STYLE IN DOCUMENT.: INFRASTRUCTURE COMPONENTS, SOURCE OF FINANCING AND IMPLEMENTATION STATUS

      Scope of the Program for the enhancement of the performance         Originally expected
                                                                                                    Implementation status
           of the Northern Tunis wastewater treatment system               source of funding
            Urgent repairs and rehabilitation of WWTPs and pumping
                                                                           Fiscal Resources            Not yet procured
                                    stations
            TWW transmission pipeline between Choutrana WWTP and          EIB loan and fiscal         Procured and under
                        Ariana CRDA pumping station                       resources (50/50)             implementation
            Covering of the TWW canal between Ariana CRDA pumping
                                                                           Fiscal resources               Completed
                             station and Oued El Khelij
      TWW transmission pipeline between Oued El Khelij and the new
                                                                         IBRD Project (Part A)            Completed
                          TWW storage basin
               TWW storage basin and associated pumping station          IBRD Project (Part A)            Completed
        The World Bank
        Tunisia Northern Tunis Wastewater Project (P117082)



            TWW pressure pipeline and submarine outfall              IBRD Project (Part B)            Completed

C. Project status
  8. As highlighted, all infrastructure construction activities originally included under the IBRD-financed Northern
  Tunis Wastewater Project have been completed. The Project was approved on June 17, 2010 and became effective
  on April 14, 2011. Project funds amount to US$65.43 million (US$39.40 million under Loan 7917-TN, US$8.03 million
  under GEF Grant TF096891, and US$18.00 million under Additional Loan 8644-TN), which, with the addition of
  US$7.57 million in taxes financed by ONAS, amount to a total project cost of US$73.00 million. The Additional Loan
  was approved on August 31, 2016 and became effective on March 30, 2017. The original closing date was December
  31, 2015, and the Original Loan (7917-TN) was extended twice to June 30, 2017, as well as to December 31, 2019. The
  closing date for the Additional Loan is also December 31, 2019. The Original Loan is now fully disbursed and will not
  be further extended. The GEF Grant was extended once to June 30, 2016 and is now fully disbursed and closed.
  9. The Project Development Objective (PDO) is to provide an environmentally safe disposal system for the treated
  wastewater in the North of Tunis and increase availability for its reuse in the Project Area. Similarly, the Project’s
  Global Environment Objective (GEO) was to support increasing the reuse of treated wastewater in agriculture, thereby
  reducing treated wastewater discharge from Greater Tunis into the Gulf of Tunis, an environmentally sensitive area
  of the Mediterranean Sea. The Project includes three components, namely “Part A: Transfer of treated wastewater to
  increase availability for its reuse”, “Part B: Improvement of the discharge of the remaining TWW in the Mediterranean
  Sea” and “Part C: Monitoring and capacity strengthening”.
  10. The Project also finances the implementation of TWW reuse pilot, which is now completed. In order to minimize
  the flow of TWW discharged through the outfall, the Project seeks to increase the reuse of TWW prior to its discharge,
  in particular by farmers in the contiguous Borj Touil area, as well as developers and municipalities. To achieve this, the
  Project aims to tap into unmet demand for better quality and reliability of TWW and finances a small-scale reuse pilot
  in the Sidi Amor area to test coordination mechanisms among stakeholders involved in TWW at a local scale (ONAS,
  CRDA, Agricultural Development Groups or GDAs, as well as farmers) and create the conditions for increased uptake
  by farmers. The Sidi Amor pilot is financed under Part A of the Project, it is currently operational and meeting
  applicable effluent quality standards for agricultural reuse.
  11. All related technical assistance, supervision of works, water quality monitoring and capacity strengthening
  activities are included under Part C of the Project. This includes consulting services for the development of ONAS’
  commercial information system, the design studies for a future WWTP in Northern Tunis, as well as for a future marine
  outfall in Southern Tunis. Activities under this component are still ongoing and are expected to be completed by
  October 2020.
  12. Progress towards achievement of PDO and progress towards achievement of GEO are Satisfactory. The extent
  to which the PDO is achieved is assessed through five PDO indicators: (i) Number of direct project’s beneficiaries (end
  target: 50,000); (ii) Average annual volume of TWW made available for reuse (end target 3 million m3/year);
  (iii) Average annual concentration of total suspended solids (TSS) in TWW made available at the storage basin (end
  target below 30 mg/L); (iv) Percentage of seawater samples at Raoued Beach complying with imperative norms in
  total coliforms and fecal coliforms (end target 90%); and (v) Average annual count of fecal coliforms in seawater
  samples in the surrounding of the outfall (end target below 2,000 counts per 100 mL).
  13. The achievement of the end targets set for four of the five PDO indicators has already been confirmed, with the
  verification on the fifth indicator pending on the collection of the required data. While the TSS concentration at the
  TWW storage basin is still to be assessed, according to the first two seawater quality monitoring campaigns performed
  after the commissioning of the works, 100 percent of the seawater samples collected and tested presented total and
  fecal coliforms concentrations below the thresholds set by the applicable Tunisian norm (NT.106.002), i.e. 10,000 and
        The World Bank
        Tunisia Northern Tunis Wastewater Project (P117082)


  2,000 counts per 100 mL respectively. This has a direct positive impact on the population living in the vicinity of the
  Raoued beach that, along with the community neighboring the TWW open-air canal that was replaced by a
  transmission pipeline under the Project, amounts to more than 50,000 people. Moreover, that’s to the reuse pilot
  implemented under the project, the Sidi Amor GDA and farmers of the Borj Touil perimeter have gained access to a
  reliable source of reclaimed water that allowed them to put 7.5 hectares under irrigation.
  14. Overall Implementation Progress (IP) rating stands at Moderately Satisfactory due to delays in implementing
  Financial Management (FM) and safeguards-related actions identified during supervision missions. For FM, after
  some delays in the preparation of the audit reports on the implementing entity (ONAS) and the Project, these have
  been finally submitted to the Bank and were found to be acceptable. As of today, there are no overdue Project audit
  reports. Consequently, FM rating was upgraded from Moderately Unsatisfactory to Moderately Satisfactory in the last
  Implementation Status and Results Report (ISR). As for safeguards, the current overall rating is Moderately Satisfactory
  due to (i) delays in the construction of a fence and adoption of erosion control and flood protection measures in the
  Sidi Amor pilot site; and (ii) delays in the processing of the compensatory payment due to the former owner of the
  plot of land where the TWW storage basin has been constructed (these delays are due to factors beyond the control
  of the implementing agency). The contract for the fencing of the Sidi Amor site was finally signed on September 2,
  2019 and works are expected to be finalized by February 2020. Regarding the second point, it should be highlighted
  that the concerned plot was acquired in 2014 in compliance with OP 4.12 and in accordance with the Land Acquisition
  Plan (LAP). While the current land owners (2) have not yet been compensated as the resolution of an ongoing title
  dispute follows due process (with close monitoring by ONAS and support by the Bank), the final court hearing on the
  case is scheduled for December 2019. The full compensation amount is in escrow waiting for the final resolution of
  the case.
  15. Disbursements currently stand at 73 percent total (69 percent of loans and 100 percent of GEF grant). As
  explained above, due to the considerable depreciation of the Tunisian dinar over the last few years, the Project has
  accumulated savings of about US$13 million. This restructuring proposes to take advantage of these savings to
  incorporate to the scope of the Project those activities considered under the wider program developed by ONAS to
  enhance the performance of the Northern Tunis wastewater treatment system (described in section B above) that
  were originally meant to be totally or partially funded with fiscal resources, i.e. : (i) Implementation of urgent repairs
  and rehabilitation activities on the WWTPs and wastewater pumping stations of the Northern Tunis wastewater
  treatment hub (originally meant to be totally financed by ONAS with fiscal resources); and (ii) the replacement of the
  open-air canal between the treatment hub and the Ariana CRDA pumping station by a TWW transmission pipeline
  (originally meant to be co-financed by ONAS with fiscal resources and through an EIB loan -50/50-, now to be co-
  financed by the IBRD under the project and by the EIB loan -50/50-).

D. Rationale for restructuring
  16. As explained above, sustainability of the results achieved by the Project is contingent on the completion of all
  upstream activities considered under ONAS’ program for Northern Tunis. The rehabilitation and maintenance of
  equipment in the various WWTPs and pumping stations of the Northern Tunis wastewater management system is key
  to improving treatment performance and therefore to keep pollutant concentrations in the effluent to be reused—or
  discharged through the submarine outfall constructed under the Project—below applicable thresholds in the years to
  come. On the other hand, having TWW conveyed through an open-air canal generates a significant risk of
  recontamination of the treated effluent and important health concerns in communities crossed by the canal.
  17. Due to the deterioration of the economic context in Tunisia, ONAS has requested the support of the World Bank
  to finance upstream activities that were originally meant to be funded with fiscal resources. The Project was
  originally designed to be executed in parallel with foreseen activities upstream, i.e. WWTPs and pumping stations’
  upgrade and maintenance activities (to be financed under existing ONAS and various donor projects), as well as the
       The World Bank
       Tunisia Northern Tunis Wastewater Project (P117082)


  replacement of the open-air canal between the Northern Tunis treatment hub and the CRDA pumping station with a
  pipeline (to be financed by the EIB under a 50/50 co-financing arrangement with ONAS). While some progress has
  been made with the former, a number of WWTPs and pumping stations still require equipment rehabilitation and
  maintenance in order to ensure that TWW enters the sanitation chain with a quality suitable for reuse and disposal.
  As for the pipeline, delays in the procurement of the materials and associated works have led to the non-availability
  of timely counterpart funding from ONAS, and their incorporation into the Project scope was thus requested to
  complement EIB financing. Nevertheless, a project closing date extension of 18 months is required in order to
  complete the installation of the pipeline.

II. DESCRIPTION OF PROPOSED CHANGES

A. Results Framework
  18. The Results Framework has been modified to reflect the incorporation of the new activities under the project
  scope. The following changes were introduced: (i) the intermediate-level indicator “Length of pipe installed” target
  was updated to take into account the 4.3-kilometer pipeline to be installed between the Northern Tunis treatment
  hub and the Ariana CRDA pumping station (the revised end target would be 16.3 km); and (ii) a new intermediate-
  level indicator, “Number of WWTPs and pumping stations in the Northern Tunis system benefitting from equipment
  rehabilitation and maintenance”, was introduced (end target 6). PDO-level indicators and their targets will remain the
  same, as they mostly relate to water quality in the Gulf of Tunis and are already dependent on all of the sanitation
  chain building blocks being completed. In addition, the PDO-level “Direct project beneficiaries” indicator will also
  remain unchanged as the original and new project activities benefit the same population of neighboring areas, as well
  as a smaller number of farmers in the Borj Touil area.

B. Components and Costs
  19. Part A (“Transfer of treated wastewater to increase availability for its reuse”) will be updated to incorporate
  the new activities, whereas Part B (“Improvement of the discharge of the remaining TWW in the Mediterranean Sea”)
  and Part C (“Monitoring and capacity strengthening”) will remain unchanged in terms of scope. US$ 13 million will be
  reallocated from Part B to Part A to cover incremental cost associated with the new activities. Updated component
  costs reflecting the actual costs of completed activities, as well as the estimated costs associated with the new
  activities are detailed in Table 2 and in Section IV (Detailed change(s)).
                                            TABLE 2: PROJECT COMPONENTS, ACTIVITIES AND BUDGET

                                                                                                     Original        Revised
   Component                   Main activities                                                        budget         budget
                                                                                                   (US$ million)   US$ million)
                               - Urgent repairs and rehabilitation of WWTPs and pumping stations
                                 in the Northern wastewater treatment system (new)
   Part A: Transfer of
                               - TWW transmission pipeline between Choutrana WWTP and Ariana
   treated wastewater to
                                 CRDA pumping station (new)                                             12             25
   increase availability for
                               - TWW transmission pipeline between Oued El Khelij and the new
   its reuse
                                 TWW storage basin (existing)
                               - TWW storage basin and associated pumping station (existing)
   Part B: Improvement
   of the discharge of the     - TWW pressure pipeline and submarine outfall (existing)                 55             42
   remaining TWW in the
   Mediterranean Sea
    The World Bank
    Tunisia Northern Tunis Wastewater Project (P117082)


                         - Technical assistance for supervision of works and environmental
                           and water quality monitoring systems in the Project area (existing)
                         - Consultant services for the reinforcement of human and technical
Part C: Monitoring and     resources (existing)
                                                                                                 6   6
capacity strengthening   - Design studies: future WWTP in the North of Tunis (existing)
                         - Design studies: transfer of TWW in the South of Tunis (existing)
                         - Develop and implement a new commercial information system for
                           ONAS
           The World Bank
           Tunisia Northern Tunis Wastewater Project (P117082)


    C. Reallocation between disbursement categories
      20. A new disbursement category will be created for payments related to the goods and works contracts that will
      be co-financed with the EIB. Before the restructuring, all Project expenditures under the additional loan approved in
      2016 – i.e. the source of financing for the proposed new activities – were included under one category (Category 1),
      except for expenditures related to the payment of the Additional Loan front-end fee, that were included under
      Category 2. As part of the restructuring, EUR8.4 million will be reallocated from Category 1 to this new Category 3,
      which funds will be earmarked for the payments due to the pipe supplier and the contractor hired for the replacement
      of the remaining segment of the open-air treated effluent canal by a double transmission pipeline.

    D. Disbursement estimates and implementation schedule
      21. The closing date of the Project and of the Additional Financing Loan (IBRD 8644-TN) will be extended by 18
      months, from December 31, 2019 to June 30, 2021. This would allow for the development of new activities
      incorporated to the scope of the Project under Part A and for the completion of ongoing activities under Part C.
      Disbursement projections have been revised accordingly and can be found below in Section IV “Detailed Change(s)”.

    E. Economic and Financial Analysis
      22. Although proposed new activities will generate additional positive externalities, these have not been quantified
      because of lack of appropriate data and methodological limitations. New activities included under Part A of the
      project will contribute to further improve the quality of the treated wastewater effluent of the Northern treatment
      hub, and therefore they will contribute to the six categories of benefits that were analyzed as part of the economic
      analysis performed for the appraisal stage. These six categories are: (i) benefits for local tourism (reduction in
      transport costs of local population to more distant beaches); (ii) benefits from international tourism (with foreign
      tourists spending more nights in the Gammarth area); (iii) increased revenues from fisheries (due to overall
      improvement in marine biotopes); (iv) reduction in public health hazards (due both to poor quality of seawater in the
      Northern Tunis area, and contamination of local population living nearby the currently open sewage canal);
      (v) improvement of the quality of life and landscape surrounding the Raoued beach, where the wastewater is currently
      discharged (as measured by an increase in real estate rental costs in the area); and (vi) increased treated wastewater
      reuse potential in the Borj Touil area.
      23. Nonetheless, the estimated value of expected benefits was updated to take into consideration inflation and a
      discount rate of 6 percent2. The resulting economic value of expected benefits is TND 42 million per year.
      24. The cost-benefit analysis was adjusted to consider actual costs associated with completed activities, costs
      budgeted for new activities and inflation. As a result, total economic cost of the investment now stands at about TND
      142.1 million (compared with TND 104.2 million in the analysis performed during the appraisal of the additional
      financing). The annual average operating cost of the wastewater infrastructure has been estimated at TND 0.71 million
      per year. In addition to the updated economic costs, the disbursement phase of the Project has been extended from
      5 to 8 years to reflect the new elements of the Project.
      The updated economic analysis shows that the Project remains economically justified, as it yields a Net Present
      Value (NPV) of about TND 173 million (2019 TND) over 25 years, a Present Value benefit/cost ratio of about 254
      percent, associated with an Economic Rate of Return (ERR) of 13.7 percent, which is consistent with the ERR at
      appraisal of the additional financing (17.5 percent). This ERR is a satisfactory value for an environmental project which
      also generates many positive externalities which have not been accounted for in the calculations.

2 The present analysis uses a discount rate of 6 percent (compared to 8 percent in the original analysis), as per the 2016
recommendations of the World Bank’s Sustainable Development Chief Economist.
       The World Bank
       Tunisia Northern Tunis Wastewater Project (P117082)


  25. The sustainability of the transfer infrastructure built under the Project is contingent on the continued
  improvement of ONAS's broader financial performance. The level of cost recovery of the operation and maintenance
  (O&M) costs of ONAS, which draws its revenues mainly from the sanitation tariff collected through water bills, has
  remained steady in recent years. Full cost recovery is reached thanks to the Government’s commitment to cover the
  remaining operating deficit through an annual transfer of funds. In addition, the Council of Ministers approved on July
  27, 2018 tariff increases aiming at ensuring that ONAS can cover 100 percent of its O&M by 2029. The Council
  approved an annual increase of 11 percent from 2020 to 2025 (i.e. 3 percent more than what had already been
  approved back in 2017) and 6.3 percent annually from 2025 to 2029. While these increases need to be effectively put
  in place every year, it shows an important level of commitment from the Government in bringing sustainability to the
  sanitation sector and will boost ONAS’s capacity to operate and maintain the Project’s infrastructure sustainably.
  26. The World Bank closely monitors the financial sustainability of ONAS, as its working and current ratios remain
  compliant with the Project’s specific financial covenants, while continuing to engage with ONAS on its long-term
  strategy, and the potential of its resources to achieve its vision and objectives. In particular, the World Bank is currently
  supporting ONAS in Tunisia’s strategic shift towards public-private partnerships (PPP), through the Tunisia Sanitation
  PPP Support Project (P162957) under preparation, as the most efficient and sustainable way to upgrade, improve and
  properly manage its wastewater collection and treatment system.

F. Technical Analysis
  27. Rehabilitation of WWTPs and pumping stations of the Northern Tunis wastewater treatment system. Under
  the scope of the “Part A” component, the Project will finance the procurement of key electromechanical equipment
  required to ensure the correct and continuous operation of WWTPs integrating the Northern Tunis treatment hub and
  associated wastewater pumping stations. The goods to be procured are meant to serve as spare parts or to replace
  key pieces of equipment that, as confirmed by the due diligence performed by the World Bank, have reached the end
  of their lifespan or are not in good operating condition. This includes the equipment of the Charguia, Choutrana I and
  Choutrana II WWTPs and the Montplaisir, X3 El Kram, SP5 Lac, Chatt Ghaba and Tunis Nord pumping stations (PS).
  28. Replacement of the open-air canal between the treatment hub and the Ariana CRDA pumping station by a
  double TWW transmission pipeline (aggregated costs US$17 million, 50 percent IBRD and 50 percent EIB). The open-
  air canal will be replaced by two parallel TWW transmission pipelines: (i) one transporting TWW of lower quality
  coming from the Choutrana I and Cotière Nord WWTPs (91,000 m3/day) that does not consistently meet applicable
  quality standards for irrigation; and (ii) one transporting TWW of greater quality coming from Choutrana II and
  Charguia (90,000 m3/day). Only the latter will be connected to the Ariana CRDA pumping station, from where 20
  percent of the flow will be pumped for reuse at the Borj Touil irrigation perimeter. These two new 2,000mm-diameter
  reinforced concrete pipelines will be fed by a new pumping station located in the vicinity of the Choutrana I WWTP.
  29. The soundness of the design proposed for this new infrastructure was already assessed at the appraisal stage
  despite not being part of the original scope of Project. Indeed, the technical due diligence performed at appraisal
  had to look not just at infrastructure components included in the project scope, but also at critical elements of the
  wastewater collection, treatment and conveyance system located upstream, and which could affect the ability of the
  project to deliver the expected results.
  30. The construction of this new transmission pipeline is already ongoing. As explained above, this activity was
  meant to be financed by the EIB and ONAS and is being incorporated into the scope of the Project, through which the
  IBRD will finance the 50 percent that was originally to be covered by ONAS. Contracts for the supply of pipeline
  materials and for the pipeline installation works were signed on May 2016 and September 2018, respectively. As of
  today, approximately 60 percent of the pipe material has been delivered on site. The contractor responsible for
  installation works and for the construction of the pumping station has been mobilized and has started site clearing
       The World Bank
       Tunisia Northern Tunis Wastewater Project (P117082)


  and earthwork activities. So far only around 200 meters of pipes have been laid. Based on site inspections performed
  by the team, and information shared by ONAS and the EIB, no incident has occurred on site and the contractor is
  performing the works according to applicable standards and to the satisfaction of the owner and the financier.
  31. Due diligence was conducted to ensure the alignment of these two contracts and their respective procurement
  processes with applicable World Bank Procurement Policies. The procurement of the pipeline materials and
  associated installation works was finalized in May 2016 and September 2018, respectively, under EIB procurement
  rules. At World Bank request, ONAS, the EIB and the concerned supplier and contractor have agreed to amend the
  corresponding contracts to ensure alignment with World Bank policies and procedures, including those related to
  procurement, integrity and environmental and social safeguards. On the other hand, ONAS and EIB also confirmed
  that: (i) there are no major issues related to the status of the works or the performance of the contractors; and (ii)
  that there are no ongoing investigations or other integrity concerns related to the contracts, including any
  subcontracts.

G. Implementation arrangements.
  32. Implementation arrangements will remain unchanged. For the two ongoing contracts that will be co-financed by
  the EIB and IBRD, once the restructuring is effective, invoices issued under these two contracts will be fully paid with
  IBRD load proceeds until the accumulated amount paid from each of the two financing sources (EIB and IBRD loans)
  are equalized. Payments due from that point onwards will be made from both sources keeping the 50/50 “pari passu”
  rate. As of today, 44 percent the financial resources allocated by the EIB for this activity have already been disbursed.
  ONAS, EIB and IBRD also agreed that no-objections for issues related to these two contracts would be requested by
  ONAS to the two institutions, but granted by IBRD on behalf of both, after internal coordination.

H. Social and Environmental Analysis
  33. The Project is a Category A operation. The Restructuring will not trigger new safeguards policies or change
  safeguard categories, which remains at Category A. Nonetheless, new activities to be incorporated into the scope of
  the Project as part of the restructuring could be considered as Category B, as evidenced by the environmental
  screening performed by the Bank.
  34. The Environmental and Social Impact Assessment (ESIA) of the Project has been updated to reflect the current
  project implementation status and to incorporate under its scope the activity related to the replacement of the
  remaining segment of the open-air TWW canal by the transmission pipeline. The updated version of the ESIA, which
  includes an Environmental and Social Management Plan (ESMP) covering concerned activities, was disclosed on ONAS
  website and on the external site of the World Bank on December 3, 2019 and December 5, 2019, respectively.
  35. Two stand-alone ESMPs have been prepared by ONAS to cover activities related to the repair and replacement
  of electromechanical equipment in select WWTPs and pumping stations, respectively. These ESMPs address the risks
  identified through the screening performed by the Bank in collaboration with ONAS; have been disclosed on December
  6, 2019 and will be incorporated to the concerned contractual documents before the launching of the corresponding
  bidding processes.
  36. The expected impacts of the new proposed activities are mainly positive. The repair and replacement of
  electromechanical equipment in WWTPs and pumping stations will further improve the quality of the treated
  wastewater effluent. On the other hand, the replacement of the open-air canal by the transmission pipeline will
  contribute to maintaining the quality of the TWW along its itinerary from Choutrana WWTP to the sea, improve the
  social and environmental living environment of residents around the open-air canal and upgrade land values around
  the El Khelij canal.
        The World Bank
        Tunisia Northern Tunis Wastewater Project (P117082)


  37. Negative impacts are linked to occupational and community Health and Safety and are time limited to the
  pipeline construction and equipment replacement phase. The updated version of the ESIA covering activities related
  to the replacement of the remaining segment of the open-air canal, identified all impacts linked to the generation of
  dust, noise, waste, hazardous waste and health and safety of workers and population, as well as proposed adequate
  mitigation measures. The ESIA proposed specific mitigation measures in the ESMP for biological (potentially
  pathogenic micro-organisms) and chemical risks related to the work environment because of the existence of the
  TWW in the open-air canal from the Choutrana WWTP, as well as the need to maintain the functionality of the TWW
  transfer system during the entire construction phase. As for activities related to the replacement of electromechanical
  equipment in pumping stations and WWTPs, risks identified as part of the screening exercise relate mainly to
  occupational health and safety. On this regard, it should be highlighted that both the updated version of the ESIA and
  the two stand-alone ESMP contemplate the obligation of the contractors to notify ONAS within 24 hours of the
  occurrence of an event involving any significant social, labor, health and safety, security or environmental incident,
  accident, or circumstance involving the Project, project workers and/or local communities. Likewise, as per the provisions
  of the amended loan agreement, ONAS shall notify the Bank within five days of the occurrence of such event.
  38. No involuntary resettlement, land taking, or economic displacement is expected associated to the
  implementation of new activities incorporated to the scope of the Project. Electromechanical equipment
  replacement activities will take place within the limits of WWTPs and pumping station facilities. Construction activities
  outside these facilities will be confined to the right-of-way of the canal, which belongs to the State and is
  encroachment-free.
  39. Safeguards-related clauses of the ongoing pipeline construction contract were amended to ensure enforcement
  and compliance with the provisions of the updated version of the ESIA and World Bank Safeguard Policies. The
  contract has been amended to refer to the final version of the ESIA as a contractual document, and to ensure
  alignment with World Bank Safeguard Policies and with the standard safeguard-related clauses of the General
  Conditions of Contracts that are adopted when standard WB bidding documents are used.



III. SUMMARY OF CHANGES

                                                                      Changed                        Not Changed
Results Framework                                                         ✔
Components and Cost                                                       ✔
Loan Closing Date(s)                                                      ✔
Reallocation between Disbursement Categories                              ✔
Disbursements Arrangements                                                ✔
Disbursement Estimates                                                    ✔
Implementation Schedule                                                   ✔
Economic and Financial Analysis                                           ✔
Technical Analysis                                                        ✔
Social Analysis                                                           ✔
                                         The World Bank
                                         Tunisia Northern Tunis Wastewater Project (P117082)



  Environmental Analysis                                                                             ✔
  Implementing Agency                                                                                                               ✔
  DDO Status                                                                                                                        ✔
  Project's Development Objectives                                                                                                  ✔
  Cancellations Proposed                                                                                                            ✔
  Overall Risk Rating                                                                                                               ✔
  Safeguard Policies Triggered                                                                                                      ✔
  EA category                                                                                                                       ✔
  Legal Covenants                                                                                                                   ✔
  Institutional Arrangements                                                                                                        ✔
  Financial Management                                                                                                              ✔
  Procurement                                                                                                                       ✔
  Other Change(s)                                                                                                                   ✔


IV. DETAILED CHANGE(S)


  OPS_DETAILEDCHANGES_COMPONENTS_TABLE




  COMPONENTS
                                                                        Current
  Current                                                                                         Proposed                                Proposed
                                                                           Cost          Action
  Component Name                                                                                  Component Name                        Cost (US$M)
                                                                        (US$M)
  Part A: transfer of treated                                                                     Part A: transfer of treated
  wastewater (TWW) to increase                                            12.00         Revised   wastewater (TWW) to increase                25.00
  availability for its reuse                                                                      availability for its reuse
  Part B: improvement of the                                                                      Part B: improvement of the
  discharge of the remaining TWW                                          55.00         Revised   discharge of the remaining                  42.00
  in the Mediterranean Sea                                                                        TWW in the Mediterranean Sea
  Part C: monitoring and capacity                                                                 Part C: monitoring and capacity
                                                                            6.00     No Change                                                 6.00
  strengthening                                                                                   strengthening
   TOTAL                                                                  73.00                                                               73.00


OPS_DETAILEDCHANGES_LOANCLOSING_TABLE
                                                   The World Bank
                                                   Tunisia Northern Tunis Wastewater Project (P117082)



        LOAN CLOSING DATE(S)

                                                                                      Original                  Revised Proposed            Proposed Deadline
      Ln/Cr/Tf                                                  Status                Closing                 Closing(s) Closing               for Withdrawal
                                                                                                                                                  Applications
                                                                                                        30-Jun-2017, 31-
      IBRD-79170                                                Effective        31-Dec-2015                             31-Dec-2019               30-Apr-2020
                                                                                                               Dec-2019
      IBRD-86440                                                Effective        31-Dec-2019                               30-Jun-2021             30-Oct-2021
                                                                                                  30-Jun-2016, 31-Jan-
      TF-96891                                                  Closed           31-Dec-2015
                                                                                                                 2017
OPS_DETAILEDCHANGES_REALLOCATION _TABLE




          REALLOCATION BETWEEN DISBURSEMENT CATEGORIES

                                                                                                                                           Financing %
                                                    Current Allocation          Actuals + Committed            Proposed Allocation
                                                                                                                                           (Type Total)
                                                                                                                                         Current     Proposed

          IBRD-86440-001                                    |   Currency: EUR

         iLap Category Sequence No: 1                                              Current Expenditure Category: GD;WRK; CS

                                                        16,159,500.00                  1,832,808.87                   7,759,500.00       100.00           100.00


         iLap Category Sequence No: 3                                              Current Expenditure Category: GD;WRK

                                                                   0.00                          0.00                 8,400,000.00                           100


          Total                                         16,159,500.00                  1,832,808.87                  16,159,500.00

          OPS_DETAILEDCHANGES_DISBURSEMENT_TABLE




          DISBURSEMENT ESTIMATES

          Change in Disbursement Estimates
          Yes

                 Year                                                                                            Current                           Proposed
                 0000                                                                                               0.00                                  0.00

                 2010                                                                                               0.00                                  0.00

                 2011                                                                                               0.00                                  0.00

                 2012                                                                                               0.00                                  0.00
           The World Bank
           Tunisia Northern Tunis Wastewater Project (P117082)



    2013                                                           150,000.00      140,466.18

    2014                                                          3,000,000.00    3,037,422.12

    2015                                                           980,000.00      969,991.70

    2016                                                          3,500,000.00    3,516,907.75

    2017                                                         15,000,000.00   12,747,230.81

    2018                                                         16,000,000.00   18,320,243.04

    2019                                                         17,000,000.00    6,837,738.40

    2020                                                          1,770,000.00    9,000,000.00

    2021                                                                  0.00   10,860,000.00

.
                                The World Bank
                                Tunisia Northern Tunis Wastewater Project (P117082)



.
                                                                                        Results framework
                                                                                        COUNTRY: Tunisia
                                                                            Tunisia Northern Tunis Wastewater Project

    Project Development Objectives(s)
    The project development objective is to provide an environmentally safe disposal system for the treated wastewater in the North of Tunis, and increase
    availability for its reuse in the Project Area.

    Project Development Objective Indicators by Objectives/ Outcomes
    RESULT_FRAME_TBL_PDO




                                        Indicator Name                   DLI    Baseline                                 End Target


    Provide an environmentally safe disposal system for wastewater treatment in the North of Tunis

    Direct project beneficiaries (Number)                                      0.00                                     50,000.00

                     Female beneficiaries (Percentage)                         0.00                                     50.00
    Percentage of seawater samples at Raoued Beach complying
    with imperative norms in total coliforms and fecal coliforms
                                                                               80.00                                    90.00
    (respectively 10,000 TC/100ml and 2,000 FC/100ml).
    (Percentage)
    Average annual count of fecal coliforms in seawater samples in
                                                                               200.00                                   2,000.00
    the surrounding of the outfall (Number)
    Increase availability of wastewater for its reuse in the Project Area
    Average annual volume of TWW made available to farmers,
    developers or municipalities in the vicinity of the Project (Cubic         0.00                                     3,000,000.00
    Meter(m3))
    Average annual concentration of suspended solids in TWW made
                                                                               120.00                                   30.00
    available at the El Hissiene basin (Percentage)

     PDO Table SPACE
                      The World Bank
                      Tunisia Northern Tunis Wastewater Project (P117082)




Intermediate Results Indicators by Components
RESULT_FRAME_TBL_IO




                            Indicator Name                         DLI    Baseline     End Target


Part A: transfer of treated wastewater (TWW) to increase availability for its reuse

Length of pipe installed (Meter(m))                                      0.00         16,300.00

Action: This indicator has been Revised

Average annual count of fecal coliforms in seawater samples at
                                                                         450.00       100.00
Raoued beach (Number)
Number of WWTPs and pumping stations in the Northern Tunis
system benefiting from equipment rehabilitation and                      0.00         6.00
maintenance (Number)

Action: This indicator is New

Part B: improvement of the discharge of the remaining TWW in the Mediterranean Sea
Average annual concentration of suspended solids in TWW made
                                                                         120.00       30.00
available at the Sidi Amor reuse pilot (Microgram/m3)
Average annual concentration of suspended solids in TWW at the
                                                                         120.00       30.00
entry point of the transfer system (Microgram/m3)
Percentage of TWW (not reused) from Northern Tunis WWTP
                                                                         0.00         95.00
discharged at the submarine outfall (Percentage)
Part C: monitoring and capacity strengthening
Grievances registered related to delivery of project benefits
                                                                         0.00         75.00
addressed (%) (Percentage)

IO Table SPACE
The World Bank
Tunisia Northern Tunis Wastewater Project (P117082)