         The World Bank                                                                               Implementation Status & Results Report
         Coal-Fired Generation Rehabilitation (P100101)


Coal-Fired Generation Rehabilitation (P100101)

SOUTH ASIA | India | Energy & Extractives Global Practice |
IBRD/IDA | Specific Investment Loan | FY 2009 | Seq No: 15 | ARCHIVED on 20-Apr-2017 | ISR27621 |


Implementing Agencies:




 Key Dates

  Key Project Dates

   Bank Approval Date:18-Jun-2009                                              Effectiveness Date:19-Mar-2010
   Planned Mid Term Review Date:04-Jun-2012                                    Actual Mid-Term Review Date:09-Jul-2012
   Original Closing Date:30-Nov-2014                                           Revised Closing Date:29-Nov-2017




Project Development Objectives

  Coal-Fired Generation Rehabilitation (P100101)
  Project Development Objective (from Project Appraisal Document)
  The objective of the project is to improve energy efficiency of selected coal-fired power generation units through renovation and modernization
  (R&M) and improved operations and maintenance (O&M).

  Has the Project Development Objective been changed since Board Approval of the Project Objective?
  No




  Coal-Fired Generation Rehabilitation (P100531)
  Global Environmental Objective (from Project Appraisal Document)
  A significant co-benefit of improving energy efficiency of the selected coal-fired power generation units is the reduction of greenhouse gas
  emissions per kilowatt hour of electricity generated.

  Has the Global Environmental Objective been changed since Board Approval of the Project Objective?
  No




Components

Name
Component 1: Energy Efficiency R&M Pilots--IBRD:(Cost $136.16 M)
Component 1: Energy Efficiency R&M Pilots--GEF:(Cost $37.90 M)
Component 2: Technical Assistance--GEF:(Cost $7.50 M)




4/20/2017                                                     Public Disclosure Copy                                                       Page 1 of 8
                                                             Public Disclosure Copy

        The World Bank                                                                               Implementation Status & Results Report
        Coal-Fired Generation Rehabilitation (P100101)



Overall Ratings
Name                                                                        Previous Rating                           Current Rating

Progress towards achievement of PDO                                          Moderately Unsatisfactory                Moderately Unsatisfactory
Overall Implementation Progress (IP)                                         Moderately Unsatisfactory                Moderately Unsatisfactory
Overall Risk Rating                                                          Moderate                                 Moderate


 Implementation Status and Key Decisions

 WBPDCL - The unit was synchronized in October 2015, and the commercial operation started in November 2015 after significant delays of about 18
 months (from the original schedule) mainly due to technical surprises and contractual issues between main package (BTG) contractor (M/s Doosan)
 and its sub-contractors. As some technical and operational issues have been there during the operation of the Unit, the main contractor (M/s Doosan)
 had undertaken the shutdown of the Unit from June 17, 2016 to complete all the pending works and the Unit was successfully synchronized again on
 July 19, 2016. Its running at its full capacity since then (during peak hours) .


 Mahagenco (MSPGCL) - The R&M works at Koradi TPS is behind schedule. The Unit was handed over to the main contractor (M/s BHEL) in August
 2015 for initiating the R&M works. With regard to project execution, the two major packages (BTG and electrical) have been awarded and the
 contractors (M/s BHEL and M/s ABB, respectively) are on board. The expected date of commissioning of R&M assets at Koradi TPS is now being
 estimated at July 2017. The Bank task team is closely monitoring the situation in Koradi with regular follow-ups and visits


 The TA work with HPGCL, WBPDCL, Mahagenco and CEA has been on track. As noted in the earlier update, a high-level roundtable with relevant
 sector stakeholders was organized by WBPDCL on April 4, 2016 in Kolkata to share the lessons learned, discuss about the experience from the R&M
 pilots, and assess the future role and benefits of pursuing R&M of old thermal power stations in India. A similar workshop will be organized upon
 completion of R&M works at Koradi as well. In addition, a South-South Knowledge Exchange Visit to South Africa was organized by WBPDCL from
 May 15-25, 2016 for officials from WBPDCL, MoP, Mahagenco, and HPGCL, to learn and understand more about R&M, related practices and similar
 experiences in South Africa.


 Restructuring of the project was carried out to extend the loan (and grant) closing date extension by one year, that is, till November 29, 2017, based
 on the request from the Government of India on October 26, 2016.




 Risks

 Systematic Operations Risk-rating Tool

 Risk Category                                              Rating at Approval               Previous Rating               Current Rating

 Political and Governance                                    --                              Moderate                     Moderate
 Macroeconomic                                               --                              Moderate                     Moderate
 Sector Strategies and Policies                              --                              Moderate                     Moderate
 Technical Design of Project or Program                      --                              Substantial                  Substantial
 Institutional Capacity for Implementation and
 Sustainability
                                                             --                              Moderate                     Moderate
 Fiduciary                                                   --                              Moderate                     Moderate
 Environment and Social                                      --                              Moderate                     Moderate


4/20/2017                                                    Public Disclosure Copy                                                        Page 2 of 8
                                                                Public Disclosure Copy

               The World Bank                                                                           Implementation Status & Results Report
               Coal-Fired Generation Rehabilitation (P100101)


 Stakeholders                                                    --                              Moderate                  Moderate
 Other                                                           --                              --                        --
 Overall                                                         --                              Moderate                  Moderate


 Results

 Project Development Objective Indicators
 PHINDPDOTBL




          Generation Capacity of Conventional Generation constructed under the project (Megawatt, Core)


                                               Baseline                      Actual (Previous)          Actual (Current)           End Target

         Value                                 0.00                          0.00                       0.00                       0.00

         Date                                  22-May-2009                   03-Aug-2016                03-Aug-2016                29-Nov-2017


 PHINDPDOTBL




          Unit-5, Bandel Thermal Power Plant, West Bengal: Reduction in Specific Coal Consumption (Kg/kWh) (Text, Custom)


                                               Baseline                      Actual (Previous)          Actual (Current)           End Target

         Value                                 0.684 kg/kWh                  0.00                       0.00                       0.602 kg/kWh

         Date                                  22-May-2009                   03-Aug-2016                03-Aug-2016                29-Nov-2017


         Comments
         Even though Unit-5 of Bandel TPS was synchronized in October 2015 and full load of 215 MW was achieved in November 2015, there were
         some pending works to be completed for conducting reliability run and performance guarantee (PG) test. These works stand completed
         now and the unit was successfully synchronized again on July 19, 2016. Upon completion of these tests, the unit was declared as
         commissioned and the outputs are monitored at the site and reported to the World Bank. Additional information will be collected during the
         proposed implementation support mission in April-May 2017.




 PHINDPDOTBL




          Unit-5, Bandel Thermal Power Plant, West Bengal: Reduction in Specific Oil Consumption (ml/kWh) (Text, Custom)


                                               Baseline                      Actual (Previous)          Actual (Current)           End Target

         Value                                 2.50                          0.00                       0.00                       2.00

         Date                                  22-May-2009                   03-Aug-2016                03-Aug-2016                29-Nov-2017


         Comments


4/20/2017                                                       Public Disclosure Copy                                                     Page 3 of 8
                                                                Public Disclosure Copy

               The World Bank                                                                          Implementation Status & Results Report
               Coal-Fired Generation Rehabilitation (P100101)



         Even though Unit-5 of Bandel TPS was synchronized in October 2015 and full load of 215 MW was achieved in November 2015, there were
         some pending works to be completed for conducting reliability run and performance guarantee (PG) test. These works stand completed
         now and the unit was successfully synchronized again on July 19, 2016. Upon completion of these tests, the unit was declared as
         commissioned and the outputs are monitored at the site and reported to the World Bank. Additional information will be collected during the
         proposed implementation support mission in April-May 2017.




 PHINDPDOTBL




          Unit-6, Koradi Thermal Power Plant, Maharashtra: Reduction in Specific Coal Consumption (Kg/kWh) (Text, Custom)


                                               Baseline                      Actual (Previous)         Actual (Current)            End Target

         Value                                 0.703 kg/kWh                  0.00                      0.00                        0.605 kg/kWh

         Date                                  22-May-2009                   03-Aug-2016               03-Aug-2016                 29-Nov-2017


 PHINDPDOTBL




          Unit-6, Koradi Thermal Power Plant, Maharashtra, Reduction in Specific Oil consumption (ml/kWh) (Text, Custom)


                                               Baseline                      Actual (Previous)         Actual (Current)            End Target

         Value                                 2.27 ml/kWh                   0.00                      0.00                        2.00

         Date                                  22-May-2009                   03-Aug-2016               03-Aug-2016                 29-Nov-2017




 Overall Comments




 Global Environmental Objective Indicators


 Overall CommentsPHGEOCMTS




 Intermediate Results Indicators




4/20/2017                                                       Public Disclosure Copy                                                     Page 4 of 8
                                                                      Public Disclosure Copy

                   The World Bank                                                                            Implementation Status & Results Report
                   Coal-Fired Generation Rehabilitation (P100101)

 PHINDIRITBL




              Component 1: Number of contracts awarded (Text, Custom)

                                                     Baseline                      Actual (Previous)         Actual (Current)            End Target

               Value                                 0.00                          7.00                      7.00                        7.00

               Date                                  22-May-2009                   03-Aug-2016               03-Aug-2016                 29-Nov-2017




 PHINDIRITBL




            Component 1: Capacity rehabilitated and modernized with focus on energy efficiency, financed under this project (MW,
           cumulative) (Text, Custom)

                                                     Baseline                      Actual (Previous)         Actual (Current)            End Target

               Value                                 0.00                          210.00                    210.00                      420.00

               Date                                  22-May-2009                   03-Aug-2016               03-Aug-2016                 29-Nov-2017


               Comments
               Even though Unit-5 of Bandel TPS was synchronized in October 2015 and full load of 215 MW was achieved in November 2015, there were
               some pending works to be completed for conducting reliability run and performance guarantee (PG) test. These works stand completed
               now and the unit was successfully synchronized again on July 19, 2016. Upon completion of these tests, the unit was declared as
               commissioned and the outputs are monitored at the site and reported to the World Bank. Additional information will be collected during the
               proposed implementation support mission in April-May 2017.




 PHINDIRITBL




            Component 2: Cumulative number of Units for which R&M procurement process is initiated at the National Level (Text,
           Custom)

                                                     Baseline                      Actual (Previous)         Actual (Current)            End Target

               Value                                 N.A.                          2.00                      2.00                        2.00

               Date                                  22-May-2009                   03-Aug-2016               03-Aug-2016                 29-Nov-2017




4/20/2017                                                             Public Disclosure Copy                                                      Page 5 of 8
                                                                      Public Disclosure Copy

                   The World Bank                                                                           Implementation Status & Results Report
                   Coal-Fired Generation Rehabilitation (P100101)

 PHINDIRITBL




              Component 2: Cumulative number of energy audit reports with baseline performance information (Text, Custom)

                                                     Baseline                     Actual (Previous)          Actual (Current)           End Target

               Value                                 N.A.                         8.00                       8.00                       8.00

               Date                                  22-May-2009                  03-Aug-2016                03-Aug-2016                29-Nov-2017




 PHINDIRITBL




            Component 2: Cumulative number of R&M detailed project reports (DPRs) with investment plans optimized for energy
           efficiency (Text, Custom)

                                                     Baseline                     Actual (Previous)          Actual (Current)           End Target

               Value                                 N.A.                         4.00                       4.00                       8.00

               Date                                  22-May-2009                  03-Aug-2016                03-Aug-2016                29-Nov-2017


               Comments
               As per Mahagenco’s letter dated June 27, 2016, the Board of Directors of Mahagenco has decided not to undertake any R&M works till
               successful completion of R&M works at Unit-6, Koradi TPS. Hence, the DPRs for various units (210MW, Unit-2, Bhusawal TPS; 210MW,
               Unit-3, Parli TPS; 210MW, Units 1&2, Chandrapur TPS) are yet to be finalized. DPR for 110MW, Units 3&4 for Panipat TPS were short-
               closed by HPGCL in November 2015. Hence, the progress against this indicator has increased from 2 (in the last mission) to 4 currently




 PHINDIRITBL




            Component 2: Cumulative number of barrier reduction studies/technical assistance interventions undertaken by CEA under
           Bank project (Text, Custom)

                                                     Baseline                     Actual (Previous)          Actual (Current)           End Target

               Value                                 N.A.                         2.00                       2.00                       4.00

               Date                                  22-May-2009                  03-Aug-2016                03-Aug-2016                29-Nov-2017



 PHINDIRITBL




            Component 2: Cumulative number of utilities in which implementation of agreed O&M and Institutional Strengthening Programs
           is completed (Text, Custom)

                                                     Baseline                     Actual (Previous)          Actual (Current)           End Target

               Value                                 N.A.                         2.00                       2.00                       3.00

               Date                                  22-May-2009                  03-Aug-2016                03-Aug-2016                29-Nov-2017




4/20/2017                                                             Public Disclosure Copy                                                    Page 6 of 8
                                                          Public Disclosure Copy

           The World Bank                                                                          Implementation Status & Results Report
           Coal-Fired Generation Rehabilitation (P100101)



 Overall Comments




 Data on Financial Performance

Disbursements (by loan)

 Project       Loan/Credit/TF   Status      Currency      Original   Revised          Cancelled   Disbursed     Undisbursed                Disbursed

 P100101       IBRD-76870       Effective   USD             180.00    136.16              43.84         80.52           55.64                        59%

 P100101       TF-58018         Closed      USD               1.00          0.74           0.26          0.74            0.00                   100%

 P100531       TF-94676         Effective   USD              45.40      45.40              0.00         20.98           24.42                        46%


Key Dates (by loan)
 Project       Loan/Credit/TF   Status      Approval Date     Signing Date         Effectiveness Date    Orig. Closing Date     Rev. Closing Date

 P100101       IBRD-76870       Effective   18-Jun-2009       17-Dec-2009          19-Mar-2010           30-Nov-2014            29-Nov-2017
 P100101       TF-58018         Closed      06-Jul-2007       06-Jul-2007          06-Jul-2007           28-Mar-2008            10-Dec-2009
 P100531       TF-94676         Effective   17-Dec-2009       17-Dec-2009          19-Mar-2010           30-Nov-2014            29-Nov-2017



Cumulative Disbursements




4/20/2017                                                 Public Disclosure Copy                                                       Page 7 of 8
                                                       Public Disclosure Copy

        The World Bank                                                                     Implementation Status & Results Report
        Coal-Fired Generation Rehabilitation (P100101)




 Restructuring History

 Level 2 Approved on 21-Apr-2014 ,Level 2 Approved on 29-Sep-2014 ,Level 2 Approved on 28-Nov-2016