PROCUREMENT PLAN Project information: Cambodia- Higher Education Improvement Project (HEIP), IDA Credit No: 6221-KH and Project IDA No: P162971 Project Implementation agency: Mistry of Education Youth and Sport (MoYES) Date of the Procurement Plan: 06 November 2018 Period covered by this Procurement Plan: The procurement period of project covered from year November 2018 to May 2020 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in accordance with the Royal Kingdom of Cambodia’s Updated Procurement Manual for All Externally Financed Projects/Programs (“Procurement Manual”), promulgated through the Sub- decree 74 dated May 22, 2012, which is issued pursuant to Article 3 of the Kingdom of Cambodia’s Law on Public Procurement dated January 14, 2012., such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. i. Procurement shall be open to eligible firms from any country; ii. The request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti- Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights as per attached format; iii. Each Project shall put in place an effective complaints review system that includes review by the implementing agency and subsequent review by another party not involved in the in the procurement process, if not satisfied with the review of the implementing agency. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables. Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Not Applicable Other Relevant Procurement Information. PROCUREMENT Cambodia : Cambodia Higher Education Improvement Project PLAN General Information Country: Cambodia Bank’s Approval Date of the Original Procurement Plan: 2018-11-12 2021-02-02 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P162971 GPN Date: 2018-11-06 Project Name: Cambodia Higher Education Improvement Project Loan / Credit No: IDA / 62210 M Executing Agency(ies): inistry of Education Youth and Sport WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned MOEYS-HEIP-NS-W-001 / Component 1: Improving Pending Construction of Business Request for Single Stage - One 2020-10- IDA / 62210 Teaching and Learning Post Open - National 200,000.00 0.00 Implementat 2019-12-25 2020-02-05 Incubation Center for Royal Quotations Envelope 02 Capacity ion University of Agriculture MOEYS-HEIP-NCB-W-001 / Component 1: Improving Pending Construction of Student's New Single Stage - One 2021-08- IDA / 62210 Teaching and Learning Post Request for Bids Open - National 1,200,000.00 0.00 Implementat 2019-11-02 2019-11-07 2019-12-19 2020-01-18 2020-02-08 Accommodation Building for Envelope 01 Capacity ion ITC MOEYS-HEIP-NCB-W-003 / Component 1: Improving Pending Single Stage - One 2021-06- Construction of Incubation IDA / 62210 Teaching and Learning Post Request for Bids Open - National 600,000.00 0.00 Implementat 2020-03-16 2020-03-21 2020-05-02 2020-06-01 2020-06-22 Envelope 17 center for RUPP Capacity ion MOEYS-HEIP-NS-W-005 / Component 1: Improving Pending Request for Single Stage - One 2020-02- Renovation of laboratories for IDA / 62210 Teaching and Learning Post Open - National 165,000.00 0.00 Implementat 2019-07-13 2019-08-24 Quotations Envelope 20 RUPP. Capacity ion MOEYS-HEIP-NS-W-008 / Component 1: Improving Pending Request for Single Stage - One 2021-12- Construction for Clean Room IDA / 62210 Teaching and Learning Post Open - National 200,000.00 0.00 Implementat 2021-05-07 2021-06-18 Quotations Envelope 18 infrastructures for RUPP. Capacity ion MOEYS-HEIP-NCB-W-004 / Construction of Research building, Student Component 2: Improving Pending Single Stage - One 2020-09- accommodation at Research IDA / 62210 Research in STEM and Post Request for Bids Open - National 900,000.00 0.00 Implementat 2019-12-02 2019-12-07 2020-01-18 2020-02-17 2020-03-09 Envelope 05 and Training Farm (RTF) and Agriculture ion supportive environment STEM building for UBB MOEYS-HEIP-NS-W-011 / Component 1: Improving Pending Request for Single Stage - One 2019-10- Renovation of learning IDA / 62210 Teaching and Learning Post Open - National 86,000.00 0.00 Implementat 2019-03-23 2019-05-04 Quotations Envelope 31 environment facilities for UBB. Capacity ion MOEYS-HEIP-ICB-W-001 / Construction of 2 New Component 1: Improving Pending Classroom Buildings for SRU & Single Stage - One 10,285,000.0 2021-11- IDA / 62210 Teaching and Learning Prior Request for Bids Open - International 0.00 Implementat 2019-09-01 2019-09-06 2019-10-21 2019-11-20 2019-12-11 RUA, and 3 Student Envelope 0 30 Capacity ion Dormitories Building for RUA & RUPP. MOEYS-HEIP-ICB-W-002 / Construction of new ITC Campus, Foundation work (Pile penetration, Pile Cap and Component 1: Improving Pending Construction ground floor, Single Stage - One 2022-02- IDA / 62210 Teaching and Learning Prior Request for Bids Open - International 7,800,000.00 0.00 Implementat 2019-11-01 2019-11-06 2019-12-18 2020-01-17 2020-02-07 1,2,3,4,5 and roof floors, Envelope 06 Capacity ion Finish work (Partition wall, window, door, toilet decoration, MMI-Electric & sanitary, and Landscape). MOEYS-HEIP-NS-W-002 / Component 1: Improving Request for Single Stage - One 2020-08- Renovation Work for Updating IDA / 62210 Teaching and Learning Post Open - National 36,000.00 0.00 Canceled 2020-03-21 2020-05-02 Quotations Envelope 30 Library at ITC Capacity MOEYS-HEIP-NS-W-012 / Component 2: Improving Under Renovation for Science Labs at Single Stage - One 2020-02- IDA / 62210 Research in STEM and Post Request for Bids Open - National 115,000.00 0.00 Implementat 2019-08-20 2020-06-10 2019-08-25 2019-09-29 2020-07-28 2019-10-14 2019-10-30 Building A for RUPP for 1st Envelope 27 Agriculture ion Year MOEYS-HEIP-NS-W-003 / Component 1: Improving Request for Single Stage - One 2019-06- Renovation Work for Updating IDA / 62210 Teaching and Learning Post Open - National 67,000.00 0.00 Canceled 2019-01-06 2019-02-17 Quotations Envelope 17 Library at ITC Capacity MOEYS-HEIP-NS-W-034 / Component 2: Improving Renovation of administrative Request for Single Stage - One 2019-11- IDA / 62210 Research in STEM and Post Open - National 107,370.00 94,967.59 Signed 2019-07-05 2019-08-05 2019-12-19 offices, auditorium, and Quotations Envelope 03 Agriculture research lab MOEYS-HEIP-NS-W-035 / Component 1: Improving Under Lab and office renovation for Request for Single Stage - One 2020-03- IDA / 62210 Teaching and Learning Post Open - National 207,000.00 0.00 Implementat 2019-08-06 2019-11-01 Faculty of Engineering (RUPP) Quotations Envelope 01 Capacity ion year I Component 1: Improving Pending MOEYS-HEIP-NS-W-36 / Request for Single Stage - One 2021-04- IDA / 62210 Teaching and Learning Post Open - National 100,000.00 0.00 Implementat 2020-08-17 2020-10-12 Renovation Laboratory for ITC Quotations Envelope 10 Capacity ion MOEYS-HEIP-NS-W-37 / Component 1: Improving Construction entrance Road, Request for Single Stage - One 2021-04- IDA / 62210 Teaching and Learning Post Open - National 197,893.00 184,830.66 Signed 2020-08-25 2020-10-20 2020-10-27 Land Fill, Digging ponds and Quotations Envelope 18 Capacity stream/creek MOEYS-HEIP-NS-W-38 / Construction Small House for Component 1: Improving Pending Keeping Materials, Office, Lab Request for Single Stage - One 2021-05- IDA / 62210 Teaching and Learning Post Open - National 198,168.00 0.00 Implementat 2020-09-25 2020-11-20 and Academic Building, Quotations Envelope 19 Capacity ion Irrigation basin andWater Closet for public Page 1 MOEYS-HEIP-NS-W-39 / Construction Small House for Component 1: Improving Pending Keeping Materials, Office, Lab Request for Single Stage - One 2021-06- IDA / 62210 Teaching and Learning Post Open - National 103,950.00 0.00 Implementat 2020-10-25 2020-12-20 and Academic Building, Quotations Envelope 18 Capacity ion Irrigation basin andWater Closet for public MOEYS-HEIP-NS-W-004 / Component 1: Improving Pending Construction of incubation Request for Single Stage - One 2020-10- IDA / 62210 Teaching and Learning Post Open - National 60,000.00 0.00 Implementat 2020-02-22 2020-04-04 center for students to startup Quotations Envelope 01 Capacity ion for SRU. MOEYS-HEIP-NS-W-004(1) / Component 1: Improving Pending Single Stage - One 2021-02- New Workshop Building for M IDA / 62210 Teaching and Learning Post Request for Bids Open - National 350,000.00 0.00 Implementat 2020-08-20 2020-08-25 2020-09-15 2020-09-29 2020-10-27 Envelope 24 E for SRU Capacity ion MOEYS-HEIP-NS-W-41 / Laboratory Renovation and Component 1: Improving Pending Request for Single Stage - One 2021-04- greenhouse setup for plant IDA / 62210 Teaching and Learning Post Open - National 75,600.00 0.00 Implementat 2020-08-17 2020-10-12 Quotations Envelope 10 biotech and pesticide residue Capacity ion research project MOEYS-HEIP-NS-W-40 / Installation of drainage Component 1: Improving Pending Request for Single Stage - One 2021-06- system, Plastic Houses for IDA / 62210 Teaching and Learning Post Open - National 93,001.00 0.00 Implementat 2020-10-25 2020-12-20 Quotations Envelope 18 farm stations, Plastic Houses Capacity ion for farmers and Water meter MOEYS-HEIP-NCB-W-002 / Component 2: Improving Single Stage - One 2020-08- Construction of Agriculture IDA / 62210 Research in STEM and Post Request for Bids Open - National 500,000.00 0.00 Canceled 2019-09-09 2019-09-14 2019-10-26 2019-11-25 2019-12-16 Envelope 12 Extension Station for SRU. Agriculture MOEYS-HEIP-NS-W-010 / Component 1: Improving Request for Single Stage - One 2020-12- Construction of Science Labs IDA / 62210 Teaching and Learning Post Open - National 115,000.00 0.00 Canceled 2020-05-23 2020-07-04 Quotations Envelope 31 at Building A for RUPP. Capacity MOEYS-HEIP-NS-W-011 A / Component 2: Improving Lab and office renovation for Single Stage - One 2021-05- IDA / 62210 Research in STEM and Post Request for Bids Open - National 123,000.00 0.00 Canceled 2020-10-01 2020-10-06 2020-11-17 2020-12-17 2021-01-21 Faculty of Engineering (RUPP) Envelope 21 Agriculture for Year II MOEYS-HEIP-NCB-W-007 / Advance Applied Nonmaterial Component 2: Improving Single Stage - One 2021-03- Research Lab with Clean IDA / 62210 Research in STEM and Post Request for Bids Open - National 400,000.00 0.00 Canceled 2020-08-05 2020-08-10 2020-09-21 2020-10-21 2020-11-05 Envelope 05 Booth (standard Lab) at STEM Agriculture building MOEYS-HEIP-NS-W-013 / Component 2: Improving Renovation for Science Labs at Single Stage - One 2021-03- IDA / 62210 Research in STEM and Post Request for Bids Open - National 115,000.00 0.00 Canceled 2020-08-31 2020-09-05 2020-10-10 2020-10-25 2020-11-06 Building A for RUPP for 2nd Envelope 06 Agriculture Year MOEYS-HEIP-NS-W-014 / Component 2: Improving Renovate Lab at STEM Building Request for Single Stage - One 2021-03- IDA / 62210 Research in STEM and Post Open - National 65,000.00 0.00 Canceled 2020-09-05 2020-10-31 (4th-6th floor at STEM Quotations Envelope 10 Agriculture Building) MOEYS-HEIP-NS-W-006 / Component 1: Improving Request for Single Stage - One 2020-12- Renovation of laboratories for IDA / 62210 Teaching and Learning Post Open - National 165,000.00 0.00 Canceled 2020-04-27 2020-06-08 Quotations Envelope 05 RUPP. Capacity MOEYS-HEIP-NS-W-007 / Component 1: Improving Request for Single Stage - One 2020-12- Construction of Clean Room IDA / 62210 Teaching and Learning Post Open - National 200,000.00 0.00 Canceled 2020-04-27 2020-06-08 Quotations Envelope 05 infrastructures for RUPP. Capacity MOEYS-HEIP-NS-W-009 / Component 1: Improving Request for Single Stage - One 2020-02- Construction of Science Labs IDA / 62210 Teaching and Learning Post Open - National 115,000.00 0.00 Canceled 2019-07-13 2019-08-24 Quotations Envelope 20 at Building A for RUPP. Capacity MOEYS-HEIP-W-DS-01 / Component 1: Improving Pending 2020-11- Small renovation works (With IDA / 62210 Teaching and Learning Post Direct Selection Direct 23,500.00 0.00 Implementat 2020-08-05 2020-08-10 2020-08-29 27 4 packages) Capacity ion GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MOEYS-HEIP-NCB-G-001 / Component 1: Improving Pending Single Stage - One Procurement of Furniture for IDA / 62210 Teaching and Learning Post Request for Bids Open - National 190,000.00 0.00 Implementati 2020-02-21 2020-02-26 2020-03-27 2020-05-11 2020-06-15 2020-10-13 Envelope Student Dormitory for RUA Capacity on Component 1: Improving Pending MOEYS-HEIP-NCB-G-002 / Single Stage - One IDA / 62210 Teaching and Learning Post Request for Bids Open - National 300,000.00 0.00 Implementati 2020-02-05 2020-02-10 2020-03-23 2020-04-22 2020-05-13 2020-11-09 Laboratory Furniture for RUA Envelope Capacity on MOEYS-HEIP-NS-G-001 / Component 1: Improving Pending Goods for Establish data Request for Single Stage - One IDA / 62210 Teaching and Learning Post Open - National 72,000.00 0.00 Implementati 2021-05-06 2021-06-17 2021-12-14 center,2 Servers (primary and Quotations Envelope Capacity on backup) for ITC MOEYS-HEIP-NCB-G-006 / Component 1: Improving Pending Single Stage - One Computer Lab, Lab facilities IDA / 62210 Teaching and Learning Post Request for Bids Open - National 600,000.00 0.00 Implementati 2021-03-01 2021-03-06 2021-04-17 2021-05-17 2021-06-07 2021-12-04 Envelope for ITC Capacity on MOEYS-HEIP-NS-G-002 / Component 1: Improving Pending Request for Single Stage - One Teaching and Learning IDA / 62210 Teaching and Learning Post Open - National 60,000.00 0.00 Implementati 2021-03-06 2021-04-17 2021-07-16 Quotations Envelope Materials for ITC Capacity on MOEYS-HEIP-NS-G-004 / Component 1: Improving Pending Developing Management Request for Single Stage - One IDA / 62210 Teaching and Learning Post Open - National 100,000.00 0.00 Implementati 2019-07-06 2019-08-17 2019-11-15 Information Systems (MIS) for Quotations Envelope Capacity on RUPP Page 2 Component 1: Improving Under MOEYS-HEIP-NCB-G-013 / Single Stage - One IDA / 62210 Teaching and Learning Post Request for Bids Open - National 342,000.00 0.00 Implementati 2019-02-01 2020-01-31 2019-02-06 2019-03-20 2020-04-10 2019-04-19 2019-05-10 2019-08-08 Office furniture for RUPP Envelope Capacity on MOEYS-HEIP-NCB-G-014 / Component 1: Improving Pending Single Stage - One Dormitory Furniture for RUPP IDA / 62210 Teaching and Learning Post Request for Bids Open - National 436,000.00 0.00 Implementati 2019-02-01 2019-02-06 2019-03-20 2019-04-19 2019-05-10 2019-08-08 Envelope and ITC Capacity on MOEYS-HEIP-NCB-G-015 / Furniture for Student Component 1: Improving Pending accommodation at Research Single Stage - One IDA / 62210 Teaching and Learning Post Request for Bids Open - National 190,000.00 0.00 Implementati 2021-03-01 2021-03-06 2021-04-17 2021-05-17 2021-06-07 2021-09-05 and Training Farm (RTF) and Envelope Capacity on Agribusiness incubator for students for UBB MOEYS-HEIP-NS-G-006 / Component 1: Improving Procurement of 05 Motorcycle Request for Single Stage - One IDA / 62210 Teaching and Learning Post Open - National 10,000.00 8,210.00 Signed 2019-01-06 2019-02-17 2019-04-01 2019-03-19 for Admin, M&E, PU, DoF & Quotations Envelope Capacity DoC MOEYS-HEIP-NCB-G-017 / Component 1: Improving Single Stage - One Office Equipment & Furniture IDA / 62210 Teaching and Learning Post Request for Bids Open - National 116,700.00 108,972.00 Signed 2018-12-02 2019-02-11 2018-12-07 2019-01-18 2019-03-11 2019-02-17 2019-06-05 2019-03-10 2019-06-20 2019-06-08 2019-08-26 Envelope for PU, DoF, PMT, DGHE & Capacity DoC MOEYS-HEIP-NS-G-007 / Component 1: Improving Request for Single Stage - One Supply of 6 packages of Sage IDA / 62210 Teaching and Learning Post Open - National 72,000.00 11,100.00 Signed 2018-12-07 2019-01-18 2019-04-18 2019-04-18 Quotations Envelope 50 Premium Accounting Capacity Component 1: Improving MOEYS-HEIP-NCB-G-007 / Single Stage - One IDA / 62210 Teaching and Learning Post Request for Bids Open - National 730,000.00 511,491.00 Completed 2018-12-02 2019-02-01 2018-12-07 2019-06-18 2019-01-18 2019-08-16 2019-02-17 2019-08-15 2019-03-10 2019-09-10 2019-06-08 2019-10-11 Procurement of 13 Vehicles Envelope Capacity MOEYS-HEIP-NCB-G-003 / Component 1: Improving Equipment for Improve Single Stage - One IDA / 62210 Teaching and Learning Post Request for Bids Open - National 360,000.00 0.00 Canceled 2019-02-05 2019-02-10 2019-03-24 2019-04-23 2019-05-14 2019-11-10 Reading, communication Envelope Capacity facilities for RUA MOEYS-HEIP-NCB-G-005 / Furniture (Lab table, Desk, chair, cabinet, drawer, Component 1: Improving Pending Projector, electric screen, Single Stage - One IDA / 62210 Teaching and Learning Post Request for Bids Open - National 550,000.00 0.00 Implementati 2022-05-25 2022-05-30 2022-06-29 2022-07-17 2022-08-07 2022-11-05 printer, whiteboard, Envelope Capacity on photocopy machine, Desktops computer, air-con etc.) for ITC MOEYS-HEIP-NCB-G-008 / Component 1: Improving Pending Single Stage - One Furniture for new Building in IDA / 62210 Teaching and Learning Post Request for Bids Open - National 200,000.00 0.00 Implementati 2021-08-13 2021-08-18 2021-09-17 2021-10-07 2021-10-28 2021-12-28 Envelope SRU Capacity on MOEYS-HEIP-NCB-G-009 / Component 1: Improving Pending Equipment for Science and Single Stage - One IDA / 62210 Teaching and Learning Post Request for Bids Open - National 150,000.00 0.00 Implementati 2021-07-13 2021-07-18 2021-08-17 2021-09-07 2021-09-28 2021-12-28 Technology and Engineering Envelope Capacity on for SRU MOEYS-HEIP-ICB-G-001 / Lab equipment and material Component 1: Improving Single Stage - One for 3 departments (Bio- IDA / 62210 Teaching and Learning Prior Request for Bids Open - International 2,740,000.00 0.00 Canceled 2020-05-21 2020-05-26 2020-07-07 2020-08-06 2020-08-27 2020-11-25 Envelope engineering, TEED, ITE) in Capacity RUPP MOEYS-HEIP-ICB-G-002 / Component 1: Improving Equipment and material for Single Stage - One IDA / 62210 Teaching and Learning Post Request for Bids Open - International 1,590,000.00 0.00 Canceled 2019-07-01 2019-07-06 2019-08-17 2019-09-16 2019-10-07 2020-01-05 13 Labs of Science program Envelope Capacity for five years. MOEYS-HEIP-NCB-G-016 / Component 1: Improving Single Stage - One Procurement of STEM IDA / 62210 Teaching and Learning Post Request for Bids Open - National 370,000.00 0.00 Canceled 2019-07-01 2019-07-06 2019-08-17 2019-09-16 2019-10-07 2020-01-05 Envelope Research Equipment for UBB Capacity MOEYS-HEIP-NS-G-005 / Supportive learning Component 1: Improving Pending Request for Single Stage - One environment - Library IDA / 62210 Teaching and Learning Post Open - National 93,000.00 0.00 Implementati 2020-03-07 2020-05-01 2020-07-30 Quotations Envelope Development Textbooks for Capacity on UBB MOEYS-HEIP-NS-G-008 / Component 2: Improving Pending STEM Research Equipmement Request for Single Stage - One IDA / 62210 Research in STEM and Post Open - National 87,450.00 0.00 Implementati 2019-07-06 2019-10-02 2020-01-05 for University of Battambang's Quotations Envelope Agriculture on Students -Year 1 MOEYS-HEIP-NCB-G-018 / Component 2: Improving Pending STEM Research Equipment for Single Stage - One IDA / 62210 Research in STEM and Post Request for Bids Open - National 282,550.00 0.00 Implementati 2022-03-01 2022-03-06 2022-04-20 2022-05-30 2022-07-07 2022-10-05 University of Battambang- Envelope Agriculture on Year 3 (2022) MOEYS-HEIP-NCB-G-019 / IT equipment for office rooms, Component 1: Improving data and e-learning center, Single Stage - One IDA / 62210 Teaching and Learning Post Request for Bids Open - National 491,573.00 413,341.48 Signed 2019-06-18 2020-01-31 2019-06-23 2019-07-28 2020-04-10 2019-08-27 2020-06-30 2019-09-18 2020-07-08 2019-12-17 incubation center, LBE lab, Envelope Capacity Fab-lab, conference room, and smart classroom MOEYS-HEIP-NS-G-009 / Office equipment for office rooms, data and e-learning Component 1: Improving Request for Single Stage - One center, incubation center, LBE IDA / 62210 Teaching and Learning Post Open - National 49,964.00 39,862.90 Signed 2019-06-23 2019-08-14 2019-12-06 2019-10-13 Quotations Envelope lab, Fab lab, conference room, Capacity and smart classroom (Air- Conditioner,Table,Chair.........) MOEYS-HEIP-NS-G-010 / Component 1: Improving Request for Single Stage - One 'Lab equipment for LBE labs IDA / 62210 Teaching and Learning Post Open - National 16,743.00 38,324.00 Signed 2019-06-25 2019-08-10 2020-08-27 2019-10-14 Quotations Envelope and Fab-lab Capacity MOEYS-HEIP-NS-G-011 / Component 1: Improving Request for Single Stage - One 'Curtain for administrative IDA / 62210 Teaching and Learning Post Open - National 5,570.00 7,225.00 Signed 2019-07-04 2019-08-28 2019-12-06 2019-10-07 Quotations Envelope offices and LBE lab Capacity Page 3 MOEYS-HEIP-NS-G-012 / Stationary (1-Whiteboard Component 1: Improving Pending Request for Single Stage - One glass for classroom and 2- IDA / 62210 Teaching and Learning Post Open - National 52,600.00 0.00 Implementati 2019-07-04 2019-08-28 2019-10-07 Quotations Envelope 'Books for library and Capacity on graduate school) MOEYS-HEIP-NS-G-013 / Component 1: Improving Pending Request for Single Stage - One Equipment for Library at ITC IDA / 62210 Teaching and Learning Post Open - National 36,000.00 0.00 Implementati 2020-03-21 2020-05-02 2020-08-03 Quotations Envelope at 3rd year (New Campus) Capacity on MOEYS-HEIP-NS-G-014 / Software(1-Software development for accounting system, human resource management system, and Component 1: Improving Pending Request for Single Stage - One fixed asset system and 2- IDA / 62210 Teaching and Learning Post Open - National 47,000.00 0.00 Implementati 2019-07-04 2019-08-09 2019-10-23 Quotations Envelope Software solution architect Capacity on and development of student online interface, online data management system and website) MOEYS-HEIP-NS-G-015 / IT Component 1: Improving Pending Request for Single Stage - One Equipment, Furniture, Books IDA / 62210 Teaching and Learning Post Open - National 36,000.00 0.00 Implementati 2022-03-29 2022-04-27 2022-07-26 Quotations Envelope for library at ITC Capacity on MOEYS-HEIP-NCB-G-020 / RUA-IT facilities and accessories for learning Component 1: Improving facility improvement,LMLA Single Stage - One IDA / 62210 Teaching and Learning Post Request for Bids Open - National 192,250.00 181,214.00 Signed 2019-06-19 2020-01-31 2019-06-22 2019-07-27 2020-04-10 2019-08-06 2020-06-30 2019-08-19 2020-07-08 2019-10-18 lab, Envelope Capacity e-goernance, PMT, and Improving communication in year1 MOEYS-HEIP-NS-G-016 / RUA-IT facilities and Component 1: Improving Pending accessories for learning Request for Single Stage - One IDA / 62210 Teaching and Learning Post Open - National 29,000.00 0.00 Implementati 2021-01-22 2021-03-03 2021-05-21 facility improvement, and Quotations Envelope Capacity on Improving communication in year3 MOEYS-HEIP-NS-G-017 / IT equipment with system for Component 1: Improving Pending Request for Single Stage - One RUA accounting software and IDA / 62210 Teaching and Learning Post Open - National 45,000.00 0.00 Implementati 2021-01-22 2021-03-03 2021-08-30 Quotations Envelope improving student,staff and Capacity on lecturer portals in year3 MOEYS-HEIP-NS-G-018 / 3- RUA-IT equipment with Component 1: Improving Request for Single Stage - One system for tracer study IDA / 62210 Teaching and Learning Post Open - National 49,500.00 85,500.00 Signed 2019-09-21 2019-11-02 2020-12-28 2020-04-30 Quotations Envelope records and public and Capacity restricted acess in year1 MOEYS-HEIP-NS-G-020 / Component 1: Improving RUA-Laboratory equipments Request for Single Stage - One IDA / 62210 Teaching and Learning Post Open - National 93,600.00 83,627.59 Signed 2019-07-13 2019-08-22 2019-10-03 2019-12-20 and accessories for VM Lab Quotations Envelope Capacity and FY lab in year1 MOEYS-HEIP-NCB-G-021 / Component 1: Improving Pending RUA-Laboratory equipments Single Stage - One IDA / 62210 Teaching and Learning Post Request for Bids Open - National 118,000.00 0.00 Implementati 2021-02-10 2021-02-15 2021-03-29 2021-04-08 2021-04-26 2021-08-24 and accessories for Agro-in Envelope Capacity on Lab and VM lab in year3 MOEYS-HEIP-NS-G-022 / Component 1: Improving Request for Single Stage - One Electric generator 12KVA for IDA / 62210 Teaching and Learning Post Open - National 15,000.00 15,730.00 Signed 2019-11-07 2019-12-09 2020-04-20 2020-02-07 Quotations Envelope RUA in Year 1 Capacity MOEYS-HEIP-NS-G-023 / Component 1: Improving Pending Request for Single Stage - One Electric generator 500KVA for IDA / 62210 Teaching and Learning Post Open - National 100,000.00 0.00 Implementati 2021-01-29 2021-03-13 2021-07-11 Quotations Envelope RUA in year 3 Capacity on MOEYS-HEIP-NS-G-024 / Component 1: Improving Improvement reading material Request for Single Stage - One IDA / 62210 Teaching and Learning Post Open - National 20,000.00 19,420.50 Signed 2019-11-09 2019-12-09 2020-04-20 2020-02-07 (Textbook and Manual) for Quotations Envelope Capacity RUA in Year 1 MOEYS-HEIP-NS-G-025 / Component 1: Improving RUA-Furniture for lerning Request for Single Stage - One IDA / 62210 Teaching and Learning Post Open - National 16,900.00 19,420.50 Signed 2019-06-11 2019-07-22 2020-04-20 2019-08-31 facilities improvement , PMT Quotations Envelope Capacity and LMLA lab in year1 MOEYS-HEIP-NS-G-026 / RUA-Furniture and Component 1: Improving Pending Request for Single Stage - One accessories (for business IDA / 62210 Teaching and Learning Post Open - National 40,000.00 0.00 Implementati 2020-03-22 2020-05-01 2020-06-15 Quotations Envelope incubation center building) for Capacity on RUA at year 3 MOEYS-HEIP-NS-G-027 / Purchase tables and chairs to Component 1: Improving Pending Request for Single Stage - One set up small private study IDA / 62210 Teaching and Learning Post Open - National 24,400.00 0.00 Implementati 2019-07-06 2019-09-22 2019-12-30 Quotations Envelope area around UBB pond area Capacity on and in building for students MOEYS-HEIP-NS-G-028 / Teaching Equipment for Component 1: Improving Under Request for Single Stage - One teaching and learning (TV 64 IDA / 62210 Teaching and Learning Post Open - National 38,500.00 0.00 Implementati 2019-07-06 2019-08-15 2019-11-13 Quotations Envelope inch for slides, Air Capacity on conditioners in classroom) MOEYS-HEIP-NS-G-029 / Agriculture laboratories Component 1: Improving Pending Request for Single Stage - One equipments(Food processing IDA / 62210 Teaching and Learning Post Open - National 99,000.00 0.00 Implementati 2019-08-06 2019-09-15 2019-12-14 Quotations Envelope Lab,animal scient lab,Micro Capacity on lab, Tissue culture ,103unit) MOEYS-HEIP-NS-G-030 / Component 1: Improving Under Materials and Equipment for Request for Single Stage - One IDA / 62210 Teaching and Learning Post Open - National 50,450.00 0.00 Implementati 2019-07-06 2019-08-30 2019-11-28 project team (computers, Quotations Envelope Capacity on printer, desk and chairs ) Page 4 MOEYS-HEIP-NS-G-031 / Component 1: Improving Pending Request for Single Stage - One Research Equipment for Sub- IDA / 62210 Teaching and Learning Post Open - National 15,000.00 0.00 Implementati 2019-08-06 2019-10-01 2019-12-30 Quotations Envelope Project Capacity on MOEYS-HEIP-NS-G-032 / Office Equipment and Software for : Lot1: QA implementation andAccounting and finance office, Component 1: Improving Under Request for Single Stage - One Lot2: Video conference IDA / 62210 Teaching and Learning Post Open - National 79,000.00 0.00 Implementati 2019-11-15 2019-12-28 2020-03-23 Quotations Envelope system for online training and Capacity on meeting with partners and Equipment the needed hardware for the system, Lot3: Management information Syst MOEYS-HEIP-ICB-G-003 / Lab equipment and material for years 1 (Lab equipment and material for Bio- Component 1: Improving Pending engineering in RUPP for years Single Stage - One IDA / 62210 Teaching and Learning Prior Request for Bids Open - International 2,765,850.00 0.00 Implementati 2019-10-14 2019-10-19 2019-12-03 2019-12-18 2020-01-10 2020-03-10 1, Lab equipment and Envelope Capacity on material for TEED in RUPP for years 1, Lab equipment and material for ITE in RUPP for years 1 (IT) MOEYS-HEIP-ICB-G-004 / Lab equipment and material (Lab equipment and material for TEED in RUPP for years 3 Component 1: Improving Pending (Telecom) , Lab Equipment Single Stage - One IDA / 62210 Teaching and Learning Prior Request for Bids Open - International 1,587,000.00 0.00 Implementati 2020-07-14 2020-07-19 2020-08-30 2020-09-09 2020-09-29 2020-11-28 and material for Electrical Envelope Capacity on Engineering for Year 3, Lab Equipment and materials for Logistic Engineering for year 3, Lab Equipment and materia MOEYS-HEIP-NCB-G-021 A / Lab equipment and material (Lab equipment and material for TEED in RUPP for years 3 Component 1: Improving Pending (Telecom) , Lab Equipment Single Stage - One IDA / 62210 Teaching and Learning Post Request for Bids Open - National 530,100.00 0.00 Implementati 2020-07-14 2020-07-19 2020-08-30 2020-09-29 2020-10-28 2020-12-27 and material for Electrical Envelope Capacity on Engineering for Year 3, Lab Equipment and materials for Logistic Engineering for year 3, Lab Equipment and materia MOEYS-HEIP-ICB-G-005 / Lab Equipment for Advanced (Lab Equipment for Advanced Component 1: Improving Pending Research (Env.), Lab Single Stage - One IDA / 62210 Teaching and Learning Prior Request for Bids Open - International 1,147,666.00 0.00 Implementati 2019-09-15 2019-09-20 2019-11-01 2019-12-01 2020-01-05 2020-03-05 Equipment for Advanced Envelope Capacity on Research (Physics), Lab Equipment for Advanced Research (Chemistry) MOEYS-HEIP-ICB-G-006 / Lab Equipment for Advanced( Component 1: Improving Pending Single Stage - One Lab Equipment for Advance IDA / 62210 Teaching and Learning Prior Request for Bids Open - International 1,062,950.00 0.00 Implementati 2020-02-22 2020-02-27 2020-03-02 2020-03-22 2020-05-01 2020-06-30 Envelope Research in Y2, Photonics and Capacity on applications Equipment MOEYS-HEIP-NCB-G-022 / Lab Furniture (Lab Furniture for Science at Building A of RUPP Y1 (11 Labs), Lab Component 1: Improving Under Furniture for Science at Single Stage - One IDA / 62210 Teaching and Learning Post Request for Bids Open - National 750,000.00 0.00 Implementati 2019-07-30 2020-07-22 2019-08-04 2019-09-15 2020-10-23 2019-10-20 2019-11-24 2020-01-23 Building A of RUPP Y2 (11 Envelope Capacity on Labs), Lab Furniture for 4th- 6th Floor at STEM Building, Lab Furniture for Faculty of Engineering (RUPP) MOEYS-HEIP-NCB-G-024 / Teaching and Learning Materials (ICT Equipment for teaching and learning (Social Component 1: Improving Under Science, Science and Graduate Single Stage - One IDA / 62210 Teaching and Learning Post Request for Bids Open - National 133,246.00 0.00 Implementati 2019-10-14 2020-10-01 2019-10-19 2019-11-20 2020-12-08 2019-12-05 2019-12-18 2020-02-16 School, Equipment & materials Envelope Capacity on for designing and printing Civil Servants' Automation Card(1 Desktop Computer for designing, 1 printing machine, MOEYS-HEIP-NS-G-033 / Component 1: Improving Pending Request for Single Stage - One Buying Microscope 30 units IDA / 62210 Teaching and Learning Post Open - National 45,000.00 0.00 Implementati 2019-11-03 2020-01-06 2020-02-25 Quotations Envelope (Biology) Capacity on MOEYS-HEIP-NCB-G-025 / Component 1: Improving Pending Single Stage - One Furniture and Equipment for IDA / 62210 Teaching and Learning Post Request for Bids Open - National 390,000.00 0.00 Implementati 2021-07-03 2021-07-08 2021-08-19 2021-09-18 2021-10-22 2022-01-20 Envelope Incubation center for RUPP Capacity on MOEYS-HEIP-NS-G-036 / Component 1: Improving Request for Single Stage - One Supply and Delivery fo 01 Bus IDA / 62210 Teaching and Learning Post Open - National 100,000.00 46,000.00 Signed 2019-12-15 2020-01-23 2020-04-27 2020-04-22 Quotations Envelope (with 29 seats) Capacity MOEYS-HEIP-G-037 / IT Component 2: Improving related equipment for data Request for Single Stage - One IDA / 62210 Research in STEM and Post Open - National 31,187.00 28,589.80 Signed 2020-05-15 2020-06-24 2020-07-28 2020-08-23 collection and analysis for 7 Quotations Envelope Agriculture research projects (for RUA) MOEYS-HEIP-G-038 / Laboratory Equipment and Component 2: Improving Request for Single Stage - One consumables for VM and IDA / 62210 Research in STEM and Post Open - National 86,804.00 72,338.38 Signed 2020-05-15 2020-06-24 2020-07-31 2020-08-23 Quotations Envelope LMLA research and food Agriculture processing (for RUA) MOEYS-HEIP-G-039 / Component 2: Improving Request for Single Stage - One Laboratory equipment for IDA / 62210 Research in STEM and Post Open - National 98,820.00 71,321.91 Signed 2020-05-15 2020-06-24 2020-07-31 2020-08-23 Quotations Envelope tissue culture (for RUA) Agriculture Page 5 MOEYS-HEIP-NS-G-40 / Component 1: Improving Under "Office Equipment for ACC Request for Single Stage - One IDA / 62210 Teaching and Learning Post Open - National 28,000.00 0.00 Implementati 2020-07-15 2020-09-09 2020-11-08 ($20,000) and for DSR Quotations Envelope Capacity on ($8,000)" Component 1: Improving Pending MOEYS-HEIP-NS-G-41 / Request for Single Stage - One IDA / 62210 Teaching and Learning Post Open - National 2,000.00 0.00 Implementati 2020-07-15 2020-09-09 2020-11-08 Office Furniture for DSR Quotations Envelope Capacity on MOEYS-HEIP-NCB-G-26 / "Supply and Delivery of 5 Pick- up Track: Component 1: Improving Single Stage - One 1 Unit for ITC ($30,000) IDA / 62210 Teaching and Learning Post Request for Bids Open - National 175,000.00 131,050.00 Signed 2020-07-10 2020-07-22 2020-07-15 2020-08-26 2020-10-01 2020-09-25 2020-11-11 2020-10-30 2020-12-07 2020-12-29 Envelope 2 Unit for ACC (for 1 Van Capacity 55,000 and 1 pick-up 30,000) 2 Unit for DSR ($60,000)" MOEYS-HEIP-NCB-G-27 / Development and aplication of Component 1: Improving Under Single Stage - One MIS to Store and Manageer IDA / 62210 Teaching and Learning Post Request for Bids Open - National 150,000.00 0.00 Implementati 2020-07-10 2020-10-01 2020-07-15 2020-08-26 2020-11-26 2020-09-25 2020-10-30 2021-04-28 Envelope Data related to ACC system Capacity on and accreditation activities MOEYS-HEIP-NS-G-42 / Component 1: Improving Request for Single Stage - One Computer Lap​ for Science and IDA / 62210 Teaching and Learning Post Open - National 40,000.00 32,599.60 Signed 2020-07-06 2020-08-31 2020-09-04 2020-11-29 Quotations Envelope Technology Capacity MOEYS-HEIP-NS-G-43 / Component 1: Improving Request for Single Stage - One Laptops and printers for IDA / 62210 Teaching and Learning Post Open - National 4,600.00 4,961.00 Signed 2020-07-06 2020-08-31 2020-10-27 2020-10-30 Quotations Envelope research Capacity MOEYS-HEIP-NS-G-44 / Component 1: Improving Pending Request for Single Stage - One Pumping machine, and power IDA / 62210 Teaching and Learning Post Open - National 2,500.00 0.00 Implementati 2020-07-06 2020-08-31 2020-10-30 Quotations Envelope tiller Capacity on Component 1: Improving Pending MOEYS-HEIP-NS-G-45 / Request for Single Stage - One IDA / 62210 Teaching and Learning Post Open - National 4,500.00 0.00 Implementati 2020-10-25 2020-12-20 2021-02-18 Water Stations and Tester Quotations Envelope Capacity on Component 1: Improving Pending MOEYS-HEIP-NS-G-46 / Request for Single Stage - One IDA / 62210 Teaching and Learning Post Open - National 6,435.00 0.00 Implementati 2020-07-06 2020-08-31 2020-11-29 Buying Books Quotations Envelope Capacity on MOEYS-HEIP-NS-G-47 / Component 1: Improving Pending Office Equipment, Software Request for Single Stage - One IDA / 62210 Teaching and Learning Post Open - National 52,122.00 0.00 Implementati 2020-07-06 2020-08-31 2020-11-29 and Refrigerator for Quotations Envelope Capacity on Researcher Component 1: Improving Pending MOEYS-HEIP-NS-G-48 / Lab Request for Single Stage - One IDA / 62210 Teaching and Learning Post Open - National 73,055.00 0.00 Implementati 2020-07-06 2020-08-31 2020-11-29 Acessories Quotations Envelope Capacity on Component 1: Improving Pending MOEYS-HEIP-NS-G-49 / Request for Single Stage - One IDA / 62210 Teaching and Learning Post Open - National 73,055.00 0.00 Implementati 2020-07-06 2020-08-31 2020-11-29 Research Equipment Quotations Envelope Capacity on Component 1: Improving Pending MOEYS-HEIP-NS-G-50 / Request for Single Stage - One IDA / 62210 Teaching and Learning Post Open - National 75,315.00 0.00 Implementati 2020-07-06 2020-08-31 2020-11-29 Research Comsumable Quotations Envelope Capacity on MOEYS-HEIP-NS-G-51 / Component 1: Improving Pending Request for Single Stage - One Research Connsumble IDA / 62210 Teaching and Learning Post Open - National 35,956.00 0.00 Implementati 2021-04-04 2021-05-30 2021-08-28 Quotations Envelope (Standard) Capacity on MOEYS-HEIP-NCB-G-29 / IT Component 1: Improving Single Stage - One Facilities and Accessories/ IT IDA / 62210 Teaching and Learning Post Request for Bids Open - National 119,830.00 92,914.80 Signed 2020-07-01 2020-07-22 2020-07-06 2020-08-17 2020-09-08 2020-09-16 2020-11-11 2020-10-21 2020-12-02 2021-04-19 Envelope Equipment (Research Project) Capacity Component 1: Improving Pending MOEYS-HEIP-NS-G-52 / Request for Single Stage - One IDA / 62210 Teaching and Learning Post Open - National 3,946.00 0.00 Implementati 2020-07-06 2020-08-31 2020-10-30 Digital Professional Camera Quotations Envelope Capacity on MOEYS-HEIP-NS-G-53 / Component 1: Improving Pending Request for Single Stage - One Analysing and Measurement IDA / 62210 Teaching and Learning Post Open - National 19,600.00 0.00 Implementati 2020-07-06 2020-08-31 2020-11-29 Quotations Envelope Equipment Capacity on Component 1: Improving Pending MOEYS-HEIP-NS-G-54 / Request for Single Stage - One IDA / 62210 Teaching and Learning Post Open - National 20,400.00 0.00 Implementati 2020-07-15 2020-09-09 2020-12-08 Consumable and Reagents Quotations Envelope Capacity on Component 1: Improving Under MOEYS-HEIP-NCB-G-30 / Single Stage - One IDA / 62210 Teaching and Learning Post Request for Bids Open - National 414,200.00 0.00 Implementati 2020-07-01 2020-07-22 2020-07-06 2020-08-17 2020-11-24 2020-09-16 2020-10-21 2020-10-30 Equipment for Rice Products Envelope Capacity on MOEYS-HEIP-NS-G-55 / Raw Component 1: Improving Pending Request for Single Stage - One Material for Experiment and IDA / 62210 Teaching and Learning Post Open - National 45,950.00 0.00 Implementati 2020-07-06 2020-08-31 2020-11-29 Quotations Envelope Lab Equipments Capacity on MOEYS-HEIP-NS-G-56 / Lab Component 1: Improving Pending Request for Single Stage - One Equipment and Materials for IDA / 62210 Teaching and Learning Post Open - National 94,000.00 0.00 Implementati 2020-07-06 2020-08-31 2020-11-29 Quotations Envelope Experiment on Pesticides Capacity on MOEYS-HEIP-NS-G-57 / Component 1: Improving Pending Request for Single Stage - One Experiment Equipment for dry IDA / 62210 Teaching and Learning Post Open - National 89,900.00 0.00 Implementati 2020-07-06 2020-08-31 2020-11-29 Quotations Envelope agricultural products Capacity on MOEYS-HEIP-NS-G-58 / 3D Component 1: Improving Pending Request for Single Stage - One Printer and Accessories, 3D IDA / 62210 Teaching and Learning Post Open - National 11,000.00 0.00 Implementati 2020-07-06 2020-08-31 2020-09-06 Quotations Envelope Printer and 3D Printer Capacity on Filament MOEYS-HEIP-NCB-G-31 / Component 1: Improving Under Single Stage - One Electronic apparatus and tools IDA / 62210 Teaching and Learning Post Request for Bids Open - National 245,700.00 0.00 Implementati 2020-08-10 2020-07-22 2020-08-15 2020-09-26 2020-11-24 2020-10-26 2020-11-30 2021-02-28 Envelope for automation lab Capacity on MOEYS-HEIP-NS-G-59 / Component 1: Improving Pending Request for Single Stage - One Mechanical tools for lab and IDA / 62210 Teaching and Learning Post Open - National 11,000.00 0.00 Implementati 2020-08-15 2020-10-10 2021-01-08 Quotations Envelope experiments Capacity on Page 6 MOEYS-HEIP-NS-G-60 / Q- Component 1: Improving Pending Request for Single Stage - One Brain System (Quanser) and IDA / 62210 Teaching and Learning Post Open - National 16,800.00 0.00 Implementati 2020-09-04 2020-10-30 2021-01-28 Quotations Envelope Camera (Quanser) Capacity on MOEYS-HEIP-NS-G-61 / Component 1: Improving Pending Request for Single Stage - One Electronic apparatus and IDA / 62210 Teaching and Learning Post Open - National 81,125.00 0.00 Implementati 2020-09-04 2020-10-30 2021-01-28 Quotations Envelope mechanical equipment Capacity on Component 1: Improving Pending MOEYS-HEIP-NS-G-62 / Request for Single Stage - One IDA / 62210 Teaching and Learning Post Open - National 7,000.00 0.00 Implementati 2020-07-06 2020-08-31 2020-10-30 Potassium nitrate salt Quotations Envelope Capacity on Component 1: Improving Pending MOEYS-HEIP-NS-G-63 / Request for Single Stage - One IDA / 62210 Teaching and Learning Post Open - National 18,760.00 0.00 Implementati 2020-07-06 2020-08-31 2020-11-29 Glass samples Quotations Envelope Capacity on MOEYS-HEIP-NS-G-64 / Component 1: Improving Pending Request for Single Stage - One Equipment's and materials for IDA / 62210 Teaching and Learning Post Open - National 28,500.00 0.00 Implementati 2020-08-10 2020-10-05 2021-01-03 Quotations Envelope experiment on soy saucce Capacity on MOEYS-HEIP-NS-G-65 / Component 1: Improving Pending Request for Single Stage - One Chemical Reagents for IDA / 62210 Teaching and Learning Post Open - National 6,199.00 0.00 Implementati 2020-08-30 2020-10-25 2021-01-23 Quotations Envelope experiments Capacity on MOEYS-HEIP-NS-G-66 / Component 1: Improving Pending Request for Single Stage - One Experimental Equipment for IDA / 62210 Teaching and Learning Post Open - National 96,100.00 0.00 Implementati 2020-08-30 2020-10-25 2021-01-23 Quotations Envelope testing on rubber samples Capacity on MOEYS-HEIP-NCB-G-32 / Component 1: Improving Under Single Stage - One Equipment for production IDA / 62210 Teaching and Learning Post Request for Bids Open - National 154,160.00 0.00 Implementati 2020-08-25 2020-07-22 2020-08-30 2020-10-11 2020-11-24 2020-11-10 2020-12-15 2021-06-13 Envelope rubber processing Capacity on Component 1: Improving Pending MOEYS-HEIP-NS-G-67 / Auto Request for Single Stage - One IDA / 62210 Teaching and Learning Post Open - National 4,000.00 0.00 Implementati 2020-08-30 2020-10-25 2021-01-23 voltage regulator Quotations Envelope Capacity on Component 1: Improving Pending MOEYS-HEIP-NS-G-68 / Lab Request for Single Stage - One IDA / 62210 Teaching and Learning Post Open - National 6,600.00 0.00 Implementati 2020-08-30 2020-10-25 2021-01-23 equipment and materials Quotations Envelope Capacity on Component 1: Improving Pending MOEYS-HEIP-NS-G-69 / Request for Single Stage - One IDA / 62210 Teaching and Learning Post Open - National 42,000.00 0.00 Implementati 2020-07-01 2020-08-26 2020-11-24 Equipment for ceramic Lab Quotations Envelope Capacity on MOEYS-HEIP-NCB-G-33 / Component 1: Improving Single Stage - One Universal Testing Machine IDA / 62210 Teaching and Learning Post Request for Bids Open - National 190,000.00 171,711.17 Signed 2020-06-26 2020-07-22 2020-07-01 2020-08-12 2020-09-08 2020-09-11 2020-11-17 2020-10-16 2020-12-02 2021-01-14 Envelope (set) Capacity Component 1: Improving Pending MOEYS-HEIP-NS-G-70 / Lab Request for Single Stage - One IDA / 62210 Teaching and Learning Post Open - National 5,500.00 0.00 Implementati 2020-07-06 2020-08-31 2020-11-29 Furniture Quotations Envelope Capacity on Component 1: Improving Pending MOEYS-HEIP-NS-G-71 / Request for Single Stage - One IDA / 62210 Teaching and Learning Post Open - National 10,000.00 0.00 Implementati 2020-07-06 2020-08-31 2020-11-29 Equipment maintenance Quotations Envelope Capacity on MOEYS-HEIP-NS-G-72 / Component 1: Improving Pending Request for Single Stage - One Make promotion video for ITC IDA / 62210 Teaching and Learning Post Open - National 16,000.00 0.00 Implementati 2020-09-06 2020-11-01 2021-01-30 Quotations Envelope and UIL Capacity on MOEYS-HEIP-NS-G-73 / Component 1: Improving Pending Request for Single Stage - One Equipment and Installation for IDA / 62210 Teaching and Learning Post Open - National 3,600.00 0.00 Implementati 2020-09-06 2020-11-01 2021-01-30 Quotations Envelope Practice Language Lab Capacity on MOEYS-HEIP-NS-G-74 / Component 1: Improving Pending Request for Single Stage - One Equipment for prototype Lab IDA / 62210 Teaching and Learning Post Open - National 10,000.00 0.00 Implementati 2020-09-06 2020-11-01 2021-01-30 Quotations Envelope for food processing Capacity on MOEYS-HEIP-NCB-G-004 A / Classroom furniture and office Component 1: Improving Pending Single Stage - One (for Complex building) and IDA / 62210 Teaching and Learning Post Request for Bids Open - National 550,000.00 0.00 Implementati 2022-12-15 2022-12-20 2023-01-31 2023-03-02 2023-04-06 2023-07-05 Envelope business incubation centers Capacity on for ITC MOEYS-HEIP-NCB-G-004 B / Component 1: Improving Pending Single Stage - One Classroom furniture and office IDA / 62210 Teaching and Learning Post Request for Bids Open - National 312,000.00 0.00 Implementati 2022-12-15 2022-12-20 2023-01-31 2023-03-02 2023-04-06 2023-07-05 Envelope (for Complex building) ITC Capacity on MOEYS-HEIP-NS-G-76 / IT Component 1: Improving Request for Single Stage - One Equipment for learning IDA / 62210 Teaching and Learning Post Open - National 83,400.00 68,566.00 Signed 2020-07-09 2020-09-03 2020-09-08 2020-12-02 Quotations Envelope facilities and Epidemiology lab Capacity MOEYS-HEIP-NS-G-77 / Component 1: Improving Pending Laboratory for foundation Request for Single Stage - One IDA / 62210 Teaching and Learning Post Open - National 36,000.00 0.00 Implementati 2021-05-06 2021-07-01 2021-09-29 year and veterinary medicine Quotations Envelope Capacity on learning practice Component 1: Improving Pending MOEYS-HEIP-NS-G-78 / Text Request for Single Stage - One IDA / 62210 Teaching and Learning Post Open - National 50,000.00 0.00 Implementati 2021-07-06 2021-08-31 2021-11-29 book for Library and faculties Quotations Envelope Capacity on MOEYS-HEIP-NCB-G-34 / Component 1: Improving Under Single Stage - One Lab equipment and IDA / 62210 Teaching and Learning Post Request for Bids Open - National 174,670.00 0.00 Implementati 2020-07-01 2020-10-01 2020-07-06 2020-08-17 2020-11-17 2020-09-16 2020-10-21 2021-04-19 Envelope consumable for food biotec Capacity on MOEYS-HEIP-NS-G-79 / Component 1: Improving Request for Single Stage - One Electronic generator for food IDA / 62210 Teaching and Learning Post Open - National 30,000.00 27,593.50 Signed 2020-07-06 2020-08-31 2020-10-19 2020-11-29 Quotations Envelope biotech research Capacity MOEYS-HEIP-NS-G-80 / Twin- Component 1: Improving Request for Single Stage - One screw extruder, injection IDA / 62210 Teaching and Learning Post Open - National 87,250.00 78,123.20 Signed 2020-07-06 2020-08-31 2020-09-08 2020-11-29 Quotations Envelope machine, oven Capacity MOEYS-HEIP-NS-G-81 / Component 1: Improving Laboratory Equipment and Request for Single Stage - One IDA / 62210 Teaching and Learning Post Open - National 81,333.00 67,068.02 Signed 2020-07-20 2020-09-14 2020-09-08 2020-12-13 cconsumable for tissutre Quotations Envelope Capacity culture and food biotec Y1 Page 7 MOEYS-HEIP-NCB-G-35 / Component 1: Improving Under Lab equipment for pesticide Single Stage - One IDA / 62210 Teaching and Learning Post Request for Bids Open - National 414,500.00 0.00 Implementati 2020-07-01 2020-10-01 2020-07-06 2020-08-17 2020-11-27 2020-09-16 2020-10-21 2021-01-19 and heavimetal residual in Envelope Capacity on plant products MOEYS-HEIP-NS-G-82 / Laboratory Furniture for Component 1: Improving Pending Request for Single Stage - One research project on tisue IDA / 62210 Teaching and Learning Post Open - National 34,000.00 0.00 Implementati 2020-07-10 2020-09-04 2020-12-03 Quotations Envelope culture, food biotec and Capacity on pesticide residual MOEYS-HEIP-NS-G-83 / Component 1: Improving Pending Laboratory and consumable Request for Single Stage - One IDA / 62210 Teaching and Learning Post Open - National 64,935.00 0.00 Implementati 2020-12-06 2021-01-31 2021-05-01 for bacterial culture and food Quotations Envelope Capacity on processing Year 2 MOEYS-HEIP-NS-G-84 / Component 1: Improving Pending Laboratory equipment for Request for Single Stage - One IDA / 62210 Teaching and Learning Post Open - National 85,735.00 0.00 Implementati 2020-12-06 2021-01-31 2021-05-01 DNA and PCR and consumable Quotations Envelope Capacity on for DNA and pCR MOEYS-HEIP-NS-G-85 / Component 1: Improving Pending consumable for detecting Request for Single Stage - One IDA / 62210 Teaching and Learning Post Open - National 18,300.00 0.00 Implementati 2021-06-06 2021-08-01 2021-10-30 pesticide, heavy metal residue Quotations Envelope Capacity on year 2 MOEYS-HEIP-NS-G-86 / Laboratory Equipment and Component 1: Improving Pending Request for Single Stage - One consumable for tissutre IDA / 62210 Teaching and Learning Post Open - National 51,150.00 0.00 Implementati 2021-06-06 2021-08-01 2021-10-30 Quotations Envelope culture and food biotec, food Capacity on processing Y2 MOEYS-HEIP-NS-G-003 / E- Component 1: Improving Request for Single Stage - One learning Lab equipment for IDA / 62210 Teaching and Learning Post Open - National 20,000.00 0.00 Canceled 2020-05-06 2020-06-17 2020-09-15 Quotations Envelope Social Science for RUPP Capacity MOEYS-HEIP-NCB-G-010 / Component 2: Improving Offices equipment at STEM Single Stage - One IDA / 62210 Research in STEM and Post Request for Bids Open - National 420,000.00 0.00 Canceled 2020-05-21 2020-05-26 2020-07-07 2020-08-06 2020-08-27 2020-11-25 Building (21 offices from 4th Envelope Agriculture to 6th floors) for RUPP MOEYS-HEIP-NCB-G-011 / Component 1: Improving Single Stage - One Furniture and Equipment for IDA / 62210 Teaching and Learning Post Request for Bids Open - National 390,000.00 0.00 Canceled 2019-02-01 2019-02-06 2019-03-20 2019-04-19 2019-05-10 2019-08-08 Envelope Incubation center for RUPP Capacity Component 1: Improving MOEYS-HEIP-NCB-G-012 / Single Stage - One IDA / 62210 Teaching and Learning Post Request for Bids Open - National 364,000.00 0.00 Canceled 2019-02-01 2019-02-06 2019-03-20 2019-04-19 2019-05-10 2019-08-08 Lab furniture for RUPP Envelope Capacity MOEYS-HEIP-NCB-G-013-A / Office Furniture(1-Office Furniture for RUPP and 2- Furniture for office rooms, Component 1: Improving Single Stage - One classroom, data and e- IDA / 62210 Teaching and Learning Post Request for Bids Open - National 655,789.00 0.00 Canceled 2019-10-14 2020-01-31 2019-10-19 2019-11-18 2020-04-10 2019-12-08 2020-01-01 2020-03-31 Envelope learning center, incubation Capacity center, LBE lab, Fab lab, conference room, and smart classroom-ITC) MOEYS-HEIP-NCB-G-023 / Office Furniture( Office Furniture for Faculty of Engineering (RUPP), Office Equipment for Faculty of Component 2: Improving Single Stage - One Engineering (RUPP), Office IDA / 62210 Research in STEM and Post Request for Bids Open - National 762,000.00 0.00 Canceled 2019-08-24 2019-08-29 2019-10-10 2019-10-30 2019-11-28 2020-01-27 Envelope Furniture and equipment for Agriculture Faculty of Engineering (RUPP) for Year II, Office Furniture at STEM Building MOEYS-HEIP-NCB-G-004 / Classroom furniture and office Component 1: Improving Single Stage - One (for Complex building) and IDA / 62210 Teaching and Learning Post Request for Bids Open - National 862,000.00 0.00 Canceled 2022-03-25 2022-03-30 2022-05-04 2022-05-18 2022-06-07 2022-09-05 Envelope business incubation centers Capacity for RUA and ITC at Year 2 MOEYS-HEIP-NS-G-019 / 4- Component 1: Improving IT equipment with system for Request for Single Stage - One IDA / 62210 Teaching and Learning Post Open - National 23,000.00 0.00 Canceled 2020-01-28 2020-03-06 2020-08-25 RUA Journal online Quotations Envelope Capacity management in year2 MOEYS-HEIP-G-DS-01 / Component 1: Improving Pending Office Equipment (With 24 IDA / 62210 Teaching and Learning Post Direct Selection Direct 132,461.00 0.00 Implementati 2020-08-05 2020-08-10 2020-08-29 2020-10-28 items) Capacity on MOEYS-HEIP-G-DS-02 / Component 1: Improving Pending Equipement for Video IDA / 62210 Teaching and Learning Post Direct Selection Direct 54,200.00 0.00 Implementati 2020-08-05 2020-08-10 2020-08-29 2020-10-28 Conference Room (With 5 Capacity on packages) MOEYS-HEIP-G-DS-03 / Component 1: Improving Pending Media Equipment (with 19 IDA / 62210 Teaching and Learning Post Direct Selection Direct 55,204.00 0.00 Implementati 2020-08-05 2020-08-10 2020-08-29 2020-10-28 items) Capacity on MOEYS-HEIP-NCB-G-023A / Component 2: Improving Under Single Stage - One Office Furniture for STEAM IDA / 62210 Research in STEM and Post Request for Bids Open - National 288,938.00 0.00 Implementati 2020-09-03 2020-07-22 2020-09-08 2020-10-13 2020-10-23 2020-11-17 2020-12-08 2021-02-06 Envelope Building of RUPP Agriculture on MOEYS-HEIP-NCB-G-023B / Component 2: Improving Single Stage - One Office Equipment for STEAM IDA / 62210 Research in STEM and Post Request for Bids Open - National 363,462.00 205,550.95 Signed 2020-09-03 2020-07-22 2020-09-08 2020-10-13 2020-10-01 2020-11-17 2020-12-11 2020-12-08 2020-12-23 2021-02-06 Envelope Bulilding of RUPP Agriculture MOEYS-HEIP-RE-DC-G-004 / Component 3: Strengthen Pending External hard disks 4TB for IDA / 62210 Sectoral Governance and Post Direct Selection Direct 47,000.00 0.00 Implementati 2020-10-18 2020-10-23 2020-11-27 2020-12-27 Central Departments, PoE and Project Management on DoE (235 pieces). MOEYS-HEIP-NS-G-032-1 / Component 1: Improving Under Video conference system and Request for Single Stage - One IDA / 62210 Teaching and Learning Post Open - National 55,000.00 0.00 Implementati 2020-10-22 2020-11-22 2021-02-20 Managment information Quotations Envelope Capacity on system for SRU Page 8 MOEYS-HEIP-NS-G-082 / Component 3: Strengthen Supply delivery and Request for Single Stage - One IDA / 62210 Sectoral Governance and Post Open - National 29,852.00 28,980.00 Signed 2020-11-21 2021-01-11 2020-10-26 2021-02-25 installation of office furniture Quotations Envelope Project Management for DGHE. MOEYS-HEIP-NCB-G-036 / Component 3: Strengthen Pending Supply delivery and Request for Single Stage - One IDA / 62210 Sectoral Governance and Post Open - National 145,818.70 0.00 Implementati 2020-11-21 2021-01-22 2021-03-08 installation of office Quotations Envelope Project Management on equipment for DGHE. NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MOEYS-HEIP-QCBS-01 / Selection of Consulting Firm Component 3: Strengthen for technical design and Quality And Cost- IDA / 62210 Sectoral Governance and Prior Open - National 1,133,000.00 0.00 Canceled 2019-01-01 2019-02-13 2019-01-22 2019-03-05 2019-03-07 2020-01-01 2019-04-04 2020-02-13 2019-05-04 2019-06-08 2019-07-06 2022-07-05 supervision for construction Based Selection Project Management of new buildings at RUA,SRU, RUPP , ITC and UBB MOEYS-HEIP-QBS-01 / Firm Component 3: Strengthen Quality Based Under to Provide Design and IDA / 62210 Sectoral Governance and Prior Open - International 1,605,938.00 0.00 2020-03-23 2020-03-30 2020-04-06 2020-04-21 2020-04-23 2020-07-30 2020-05-21 2020-09-09 2020-05-31 2020-11-11 2020-06-10 2020-06-27 2022-12-14 Selection Implementation Supervision Services Project Management MOEYS-HEIP-IC-17 / International Technical Component 1: Improving Consultant Advisor for Promoting IDA / 62210 Teaching and Learning Post Qualification Open - International 35,000.00 33,621.44 Signed 2020-04-06 2020-03-06 2020-04-27 2020-05-22 2020-06-30 2020-06-01 2020-07-29 2020-06-13 2020-09-03 2020-11-10 Research and Development, Capacity Selection Period: 5 months (ITC) MOEYS-HEIP-IC-18 / International Technical Component 1: Improving Consultant Advisor for University- Under IDA / 62210 Teaching and Learning Post Qualification Open - International 15,000.00 0.00 2020-04-06 2020-03-26 2020-04-27 2020-11-05 2020-05-22 2020-06-01 2020-06-13 2020-09-11 Business Development Plan, Implementation Capacity Selection Contract Period: 3 months (ITC) MOEYS-HEIP-QBS-02 / An Component 1: Improving Consultant Under Environmental and Social IDA / 62210 Teaching and Learning Post Qualification Open - National 40,000.00 0.00 2020-08-02 2020-08-24 2020-08-23 2020-10-06 2020-11-05 2020-12-10 2021-04-09 Implementation Impact Assessment (ESIA) Capacity Selection INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MOEYS-HEIP-IC-04 / Selection of National Component 3: Strengthen Individual Technical Advisor for Project IDA / 62210 Sectoral Governance and Prior Consultant Open 360,000.00 262,647.00 Signed 2018-12-03 2019-01-21 2019-08-08 2019-01-28 2019-08-11 2019-02-18 2019-08-15 2024-04-12 management (National Project Management Selection Individual Consultant) MOEYS-HEIP-IC-08 / Component 2: Improving Individual Selection of Silk innovation Under IDA / 62210 Research in STEM and Post Consultant Open 90,000.00 0.00 2019-01-01 2020-10-01 2019-02-19 2019-02-26 2019-03-19 2024-02-21 specialist for RUPP (National Implementation Agriculture Selection Individual Consultant) MOEYS-HEIP-IC-012 / Selection of International Component 3: Strengthen Individual Technical Advisor for Support IDA / 62210 Sectoral Governance and Prior Consultant Open 858,000.00 306,979.20 Signed 2018-12-03 2019-01-06 2019-01-21 2019-06-24 2019-01-28 2019-08-07 2019-02-18 2019-08-15 2024-07-21 Implementation for STEM Project Management Selection (International Individual Consultant) MOEYS-HEIP-IC-010 / Selection of International Component 3: Strengthen Individual Technical Advisor for Project IDA / 62210 Sectoral Governance and Prior Consultant Open 936,000.00 0.00 Canceled 2018-12-05 2019-01-11 2019-01-23 2019-06-24 2019-01-30 2019-02-20 2024-01-25 management for (International Project Management Selection Individual Consultant) MOEYS-HEIP-IC-02 / Component 1: Improving Individual Recruitment of National IDA / 62210 Teaching and Learning Post Consultant Open 84,000.00 143,205.00 Signed 2018-12-03 2019-01-16 2019-01-21 2019-03-19 2019-01-28 2019-03-19 2019-02-11 2019-04-24 2023-01-21 Procurement Consultant Capacity Selection (Individual Consultant) MOEYS-HEIP-IC-03 / Selection of National Component 1: Improving Individual Under Financial Management IDA / 62210 Teaching and Learning Post Consultant Open 84,000.00 0.00 2018-12-03 2018-08-16 2019-01-21 2019-03-11 2019-01-28 2019-03-19 2019-02-18 2020-06-12 Implementation Consultant (National Capacity Selection Individual Consultant) MOEYS-HEIP-IC-09 / Component 3: Strengthen Individual Selection of National IDA / 62210 Sectoral Governance and Prior Consultant Open 335,000.00 271,790.00 Signed 2019-01-01 2019-02-19 2019-06-24 2019-03-12 2019-08-07 2019-04-02 2019-08-15 2024-03-06 Consultant for Governance Project Management Selection Policy and Planning MOEYS-HEIP-IC-011 / Selection of International Component 3: Strengthen Individual Technical Advisor for Pending IDA / 62210 Sectoral Governance and Post Consultant Open 143,000.00 0.00 2018-12-03 2019-01-21 2019-01-28 2019-02-18 2020-01-14 developing Master Plan for Implementation Project Management Selection Human resource (International Individual Consultant) MOEYS-HEIP-IC-14 / Component 3: Strengthen Individual National Technical Advisor to IDA / 62210 Sectoral Governance and Post Consultant Open 210,000.00 335,040.00 Signed 2019-09-15 2019-08-26 2019-11-03 2019-10-25 2019-11-24 2019-10-25 2019-12-29 2019-10-31 2024-02-06 Support Private Higher Project Management Selection Education Institution Program Page 9 MOEYS-HEIP-IC-15 / International Technical Component 3: Strengthen Individual Advisor to Support Private IDA / 62210 Sectoral Governance and Post Consultant Open 156,000.00 226,700.00 Signed 2019-09-15 2019-08-26 2019-11-03 2019-10-25 2019-11-24 2019-10-25 2019-12-29 2019-11-26 2020-12-28 Higher Education Institution Project Management Selection Program MOEYS-HEIP-IC-16 / NATIONAL CONSULTANT Component 1: Improving Individual ARCHITECT TO DESIGN AND IDA / 62210 Teaching and Learning Post Consultant Open 30,000.00 31,700.00 Signed 2019-09-02 2019-08-26 2019-10-06 2019-10-25 2019-10-16 2019-10-25 2019-11-04 2019-10-31 2020-10-29 SUPERVISE Capacity Selection THE RENOVATION/ CIVIL WORK FOR FIVE HEIs MOEYS-HEIP-IC-010 (1) / International Technical Component 3: Strengthen Individual Advisor for Supporting Higher IDA / 62210 Sectoral Governance and Prior Consultant Open 468,000.00 364,140.00 Signed 2019-12-12 2019-12-19 2020-02-05 2020-04-06 2020-02-26 2020-05-20 2020-03-16 2020-05-22 2023-03-01 Education Partnership Project Management Selection Program and Development MOEYS-HEIP-IC-010 (2) / Component 3: Strengthen Individual International Technical IDA / 62210 Sectoral Governance and Prior Consultant Open 460,000.00 112,100.00 Signed 2019-12-12 2020-01-06 2020-02-05 2020-04-06 2020-02-26 2020-04-24 2020-03-16 2020-04-27 2023-12-26 Advisor for Project Project Management Selection Management and Coordination MOEYS-HEIP-IC-04 (1) / Component 3: Strengthen Individual National Technical Advisor for Under IDA / 62210 Sectoral Governance and Post Consultant Open 260,000.00 0.00 2020-03-25 2020-03-19 2020-04-23 2020-04-30 2020-05-10 2023-04-25 Project management (National Implementation Project Management Selection Individual Consultant) MOEYS-HEIP-IC-16(1) / NATIONAL CONSULTANT Component 1: Improving Individual ARCHITECT TO DESIGN AND IDA / 62210 Teaching and Learning Post Consultant Open 30,000.00 33,080.00 Signed 2020-03-25 2020-03-18 2020-04-01 2020-03-26 2020-04-11 2020-03-26 2020-04-23 2020-04-01 2021-04-18 SUPERVISION THE Capacity Selection RENOVATION/ CIVIL WORK FOR HEIs Component 1: Improving Individual MOEYS-HEIP-IC-02(1) / IDA / 62210 Teaching and Learning Post Consultant Open 43,200.00 15,820.00 Signed 2020-03-25 2020-04-13 2020-04-01 2020-07-22 2020-04-11 2020-07-29 2020-04-25 2020-08-05 2022-04-15 Procurement Assistant Capacity Selection MOEYS-HEIP-IC-19 / National Technical Assistant Component 1: Improving Individual Under for Project Management and IDA / 62210 Teaching and Learning Post Consultant Open 96,000.00 0.00 2020-04-06 2020-03-26 2020-05-12 2020-05-22 2020-06-05 2024-05-15 Implementation Administration, Contract Capacity Selection Period: 48 months (ITC ) MOEYS-HEIP-IC-20 / National Technical Assistant Component 1: Improving Individual Under for Partnership Management IDA / 62210 Teaching and Learning Post Consultant Open 96,000.00 0.00 2020-04-06 2020-03-06 2020-05-12 2020-05-22 2020-06-05 2024-05-15 Implementation and Coordination, Contract Capacity Selection Period: 48 months (ITC) MOEYS-HEIP-IC-21 / National Quality Assurance Component 1: Improving Individual officer for Higher Education Pending IDA / 62210 Teaching and Learning Post Consultant Open 96,000.00 0.00 2020-04-06 2020-05-12 2020-05-22 2020-06-05 2024-05-15 Partnership Programs, Implementation Capacity Selection Contract Period: 48 months (ITC) MOEYS-HEIP-IC-23 / Component 1: Improving Individual National Research Project Pending IDA / 62210 Teaching and Learning Post Consultant Open 96,000.00 0.00 2020-04-06 2020-05-12 2020-05-22 2020-06-05 2024-05-15 Consultant, Contract Period: Implementation Capacity Selection 48 months (ITC) MOEYS-HEIP-IC-22 / National Procurement Component 1: Improving Individual Assistant, Contract Period: 24 IDA / 62210 Teaching and Learning Post Consultant Open 48,000.00 15,820.00 Signed 2020-04-06 2020-04-13 2020-05-12 2020-07-22 2020-05-22 2020-07-29 2020-06-05 2020-08-05 2022-05-26 months with a total estimated Capacity Selection cost of $ 48,000.00 (ITC) MOEYS-HEIP-IC-24 / Component 1: Improving Individual National Technical for Chief of Under IDA / 62210 Teaching and Learning Post Consultant Open 34,800.00 0.00 2020-07-01 2020-09-09 2020-08-19 2020-09-09 2020-10-14 2020-10-17 Operation (12 months) for Implementation Capacity Selection RUPP MOEYS-HEIP-IC-25 / Component 1: Improving Individual Under National Technical for Finance IDA / 62210 Teaching and Learning Post Consultant Open 34,800.00 0.00 2020-07-01 2020-09-09 2020-08-19 2020-09-09 2020-10-14 2021-10-14 Implementation (12 months) for RUPP Capacity Selection MOEYS-HEIP-IC-05 / Selection of National Technical Advisor for Component 3: Strengthen Individual developing Master Plan for IDA / 62210 Sectoral Governance and Post Consultant Open 55,000.00 0.00 Canceled 2018-12-03 2019-01-21 2019-01-28 2019-02-18 2020-01-14 Human resource for STEM Project Management Selection (National Individual Consultant) MOEYS-HEIP-IC-06 / Selection of National Component 3: Strengthen Individual Technical Advisor for IDA / 62210 Sectoral Governance and Post Consultant Open 60,000.00 0.00 Canceled 2019-08-01 2019-09-19 2019-10-10 2019-10-31 2020-10-30 Developing and conduct Project Management Selection Tracer Study MOEYS-HEIP-IC-07 / Selection of National Component 3: Strengthen Individual Technical Advisor for IDA / 62210 Sectoral Governance and Prior Consultant Open 300,000.00 0.00 Canceled 2019-10-15 2019-12-03 2019-12-10 2019-12-31 2024-12-04 Developing and conduct Policy Project Management Selection Analysis (National individual Consultant) MOEYS-HEIP-IC-13 / Selection of International Component 3: Strengthen Individual Technical Advisor for IDA / 62210 Sectoral Governance and Prior Consultant Open 720,000.00 0.00 Canceled 2018-12-03 2019-01-21 2019-02-11 2019-03-04 2023-02-11 Research (International Project Management Selection Individual Consultant) MOEYS-HEIP-IC-01 / Selection of Project Component 1: Improving Individual Management Technical IDA / 62210 Teaching and Learning Post Consultant Open 56,000.00 0.00 Canceled 2019-01-01 2019-06-05 2019-02-19 2019-03-12 2019-04-02 2021-07-20 Assistant for Royal University Capacity Selection of Phnom Penh (National Individual Consultant) Page 10 MOEYS-HEIP-IC-DS-01 / LMS Component 1: Improving Pending Administrator for 8 months IDA / 62210 Teaching and Learning Post Direct Selection Direct 18,000.00 0.00 2020-08-05 2020-08-15 2020-10-03 2021-01-01 Implementation For ITC Capacity MOEYS-HEIP-IC-DS-02 / Component 1: Improving Pending Network and system engineer IDA / 62210 Teaching and Learning Post Direct Selection Direct 3,000.00 0.00 2020-08-05 2020-08-15 2020-10-03 2021-01-01 Implementation for 4 months for ITC Capacity MOEYS-HEIP-IC-DS-03 / Component 1: Improving Procurement Assistant to Pending IDA / 62210 Teaching and Learning Post Direct Selection Direct 24,000.00 0.00 2020-08-05 2020-08-15 2020-10-03 2021-01-01 facilitate timely procurement Implementation Capacity of goods works and services MOEYS-HEIP-IC-016(2) / NATIONAL INDIVIDUAL CONSULTANT ARCHITECT TO Component 1: Improving Individual SUPPLY DESIGN AND Under IDA / 62210 Teaching and Learning Post Consultant Open 37,000.00 0.00 2020-10-16 2020-07-16 2020-11-11 2020-11-21 2020-12-03 2021-11-28 SUPERVISION SERVICES FOR Implementation Capacity Selection RENOVATION/ CIVIL WORKS AT SELECTED HIGHER EDUCATION INSTITUTIONS MOEYS-HEIP-IC-024 / NATIONAL TECHNICAL Component 2: Improving Individual ADVISOR ON RESEARCH & Pending IDA / 62210 Research in STEM and Post Consultant Open 140,000.00 0.00 2021-01-01 2021-02-19 2021-03-12 2021-04-16 2024-03-31 DEVELOPMENT (R&D) IN THE Implementation Agriculture Selection HIGHER EDUCATION SUB- SECTOR (for DSR, 36 months) Page 11