Page 1 i Restructuring Status: Archived Restructuring Type: Level two Last modified on date : 11/23/2010 1. Basic Information Project ID & Name P110555: EERAP - ENERGY EMERGENCY Country Tajikistan Task Team Leader Mirlan Aldayarov Sector Manager/Director Ranjit J. Lamech Country Director Motoo Konishi Original Board Approval Date 05/01/2008 Original Closing Date: 12/31/2010 Current Closing Date 12/31/2012 Proposed Closing Date [if applicable] EA Category B-Partial Assessment Revised EA Category B-Partial Assessment-Partial Assessment EA Completion Date Revised EA Completion Date 2. Revised Financing Plan (US$m) Source Original Revised BORR 0.00 0.00 IDA 0.00 6.50 IDAT 6.50 0.00 Total 6.50 6.50 3. Borrower Organization Department Location Ministry of Finance Tajikistan 4. Implementing Agency Organization Department Location OSHPC Barki Tajik SUE TajikGas 58239 V2 Page 2 ii 5. Disbursement Estimates (US$m) Actual amount disbursed as of 12/02/2010 8.75 Fiscal Year Annual Cumulative 2010 0.00 8.75 Total 8.75 6. Policy Exceptions and Safeguard Policies Does the restructured project require any exceptions to Bank policies? N Does the restructured projects trigger any new safeguard policies? If yes, please select from the checklist below and update ISDS accordingly before submitting the package. N 7a. Project Development Objectives/Outcomes Original/Current Project Development Objectives/Outcomes The development objective of the project is urgently increase the volume and reliability of the national energy supply, especially in the winter season by supporting the implementation of the Recipient's Energy Emergency Mitigation Plan (EEMAP). 7b. Revised Project Development Objectives/Outcomes [if applicable]