PROCUREMENT PLAN (Textual Part) Project information: Country: Nigeria Project Name: Multi-Sectoral Crisis Recovery Project for North East Nigeria (MCRP) P- Number: P157891 Project Implementation Agency: MCRP PCU (Federal and States) Date of the Procurement Plan: Updated -December 22, 2017. Period covered by this Procurement Plan: From 01/12/2018 – 30/06/2019. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the FGN Public Procurement Act 2007; such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables. “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Specify for each: Goods: is not applicable for those contracts identified in the Procurement Plan tables; Works: is not applicable for those contracts identified in the Procurement Plan tables. Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. Other Relevant Procurement Information. 1. Prior Review Threshold for Goods, Works and Non-Consulting Services: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Prior Review Procurement Method Threshold (US$ Comments equivalent) ICB and LIB (Goods and services other than ≥ 5,000,000 ALL consultancy services) NCB (Goods, IT Systems and Non Consulting Services 100,000 < 5,000,000 NONE (NCB) ICB (Works) ≥ 20,000,000 ALL NCB (Works) 150,000 < 20,000,000 NONE Shopping-Goods ≤ 100,000 NONE Shopping-Works ≤ 150,000 NONE Based on Annual Training, Workshops, Study All Values Work Plans & Tours Budgets 2. Prequalification: Bidders for major works shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines, although it is not expected that there will be need for prequalification in the procurement arrangements for the MCRP. MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 2 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT 3. Proposed Procedures for CDD Components (as per paragraph. 6.52 of the Procurement Regulations): Shall apply. 4. Reference to the Project Implementation Manual: Shall apply. 5. Any Other Special Procurement Arrangements: Not Applicable 6. Procurement Packages (Goods and Works) indicating Bank’s Prior and Post Review. MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 3 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT a. Summary of Procurement of Goods: 1 2 3 4 5 6 Review by Estimated Ref. Packag Bank Commen Description Cost (US$ No. es (Prior / ts Million) Post) Total NCB 12.82 43 Post (Goods) Total RfQ (Goods/Non 0.04 1 Post Consulting Services) Procurement of Goods with Selection Methods and Time Schedule (Please see Annex I). b. Summary of Procurement of Civil Works 1 2 3 4 5 6 Review by Estimated Ref. Bank Commen Description Cost (US$ Packages No. (Prior / ts Million) Post) Total NCB 23.59 64 Post (Works) Total RfQ 2.29 20 Post (Works) Procurement of Civil Works with Selection Methods and Time Schedule (Please see Annex II). c. Summary of Procurement of Non- Consulting Services (TBD) 1 2 3 4 5 6 Review by Estimated Ref. Bank Commen Description Cost (US$ Packages No. (Prior / ts Million) Post) Total NCB 0.175 2 Post MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 4 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT 7. Prior Review Threshold for Consultancies: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Prior Review Selection Method Comments Threshold (USD) Consultant Services-QCBS- International 1. Consulting Services ≥ 300,000 ALL 2. Engineering and Construction ≥ 500,000 Supervision Consultant Services-QCBS < 300,000.00 NONE Consultant Services-CQS < 300,000.00 NONE Consultant Services-lC >300,000.00 ALL Consultant Services-lC <300,000.00 NONE Consultant Services- Single Source All Values ALL Selection Note: All ToRs to be prior review QCBS = Quality and Cost Based Selection SSS = Single Source Selection CQ = Consultant Qualification LCS = Least Cost Selection IC = Individual Consultant 8. Short list comprising entirely of National Consultants: Short list of consultants for services, estimated to cost less than $300,000.00 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. a. Summary of Consultancies 1 2 3 4 5 6 Ref. Description Estimate Package Review by Comment No. d Cost s Bank s (US$ (Prior/Post Million) ) Summary of number of 5.72 7 Prior contracts that will be let under International QCBS Summary of number of 6.45 16 Post contracts that will be let under National QCBS Summary of number of 1.74 30 Post contracts that will be let under CQS Summary of number of 0.35 3 Post contracts that will be let under MOU MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 5 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Summary of number of 0.021 3 Post contracts that will be let under Individual Consultancies MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 6 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Estimated Estimated Prior Number of Amount in Investable or Expected Procureme Pre- USD (Over Amount Post Bid- Description (List of Componen nt Procureme qualificati the Project for 18 Revie Opening Contracts) t/Sector Packages nt Method on Life) months w Date WORKS BORNO Construction Of 18-No Double Classroom Blocks in Ngohi, Biji-Biji, Ngulde, C2/Educati Post Tue-19-Jun- Rumirgo, Chul on 3 NCB No 708,196.72 354,098.36 Review 18 Construction Of 10- No. Double Classroom Block - C2/Educati Post Tue-19-Jun- Bama (Banki Town) on 2 NCB No 393,442.62 314,754.10 Review 18 Reconstruction Of 39- No. Double Classroom Block in C2/Educati Post Damasak, Mobbar on 4 NCB No 575,409.84 71,926.23 Review Tue-24-Jul-18 Construction Of 15- No. Double Classroom Block - C2/Educati Post Gajibo, Logomane (Dikwa) on 2 NCB No 590,163.93 147,540.98 Review Tue-24-Jul-18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 7 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Construction Of 25 No. Double Classroom Block C2/Educati Post GUZAMALA on 2 NCB No 983,606.56 245,901.64 Review Tue-24-Jul-18 Construction Of 20- No. Double Classroom Block - Kukawa Town, Baga, Cross- C2/Educati Post Tue-18-Sep- Kauwa on 2 NCB No 786,885.25 196,721.31 Review 18 Construction Of 10- No. Double Classroom Block - C2/Educati Post Tue-18-Sep- Monguno on 1 NCB No 393,442.62 98,360.66 Review 18 Construction Of 4- No. Double Classroom Block in C2/Educati Post Tue-20-Nov- Ajiri. Mafa on 1 NCB No 157,377.05 39,344.26 Review 18 Renovation Of 20- No. Double Classroom Blockin C2/Educati Post Tue-20-Nov- Damboa Town -Abadam on 2 NCB No 295,081.97 73,770.49 Review 18 Renovation Of 31- No. Double Classroom Block - C2/Educati Post Tue-23-Oct- Bama on 2 NCB No 457,377.05 114,344.26 Review 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 8 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Construction Of 3-No. C2/Educati Post Tue-18-Sep- Educational Office -Kukawa on 1 NCB No 196,721.31 98,360.66 Review 18 Construction Of 2-No. Educational Office - C2/Educati Post Tue-20-Nov- Konduga on 1 NCB No 131,147.54 32,786.89 Review 18 Construction Of 2-No. Educational Office -Hawul C2/Educati Post Tue-23-Oct- Sakwa, Kwajafa on 1 NCB No 131,147.54 32,786.89 Review 18 Construction Of 4-No Vip C2/Educati Post Tue-18-Dec- Toilets -Askira-Uba on 1 RfQ No 59,016.39 47,213.11 Review 18 Construction Of 4-No Vip C2/Educati Post Tue-18-Dec- Toilets -Mafa on 1 RfQ No 59,016.39 47,213.11 Review 18 Construction Of 5-No Vip C2/Educati Post Tue-18-Dec- Toilets -Monguno on 1 RfQ No 73,770.49 59,016.39 Review 18 Renovation Of 1-No. Educational Office - C2/Educati Post Tue-18-Dec- Damboa on 1 RfQ No 18,032.79 4,508.20 Review 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 9 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Renovation Of 1-No. Educational Office and 1- No. Principal's Quarters - Benisheik, Kaga- Benisheik, C2/Educati Post Tue-23-Oct- Kaga on 1 RfQ No 42,622.95 16,803.28 Review 18 Rehabilitation of 66KM C2/Transpo 1,223,144. Prior Tue-27-Feb- Maiduguri to Bama road rt 1 NCB No 9,785,152.68 08 Review 18 Rehabilitation of 1 Ngala C2/Transpo Prior Tue-27-Feb- Bridge rt 1 NCB No 2,295,081.97 483,983.71 Review 18 C2/Transpo Post Tue-27-Feb- Rehabilitation of Biu bridge rt 1 NCB No 902,111.48 73,770.49 Review 18 Construction of galameri- dusuman-zabarmari- C2/Transpo Prior Tue-27-Feb- gongulong feeder road rt 1 NCB No 1,104,625.69 59,016.39 Review 18 RehabilitatIon of 3 General Hospital in ABADAM, ASKIRA UBA, KALA-BALGEe and Rehabilitation of Prior Tue-27-Mar- comprehensive Healthcare C2/Health 3 NCB No 1,555,779.01 986,195.83 Review 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 10 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT center (Civil Works, Solar Borehole, Fence & Security Post) Construction of PHC for 15 2,254,098. Prior Tue-27-Mar- LGAs C2/Health 5 NCB No 3,606,557.38 36 Review 18 Rehabilitation of Borno C2/Educati Post Tue-24-Apr- State Library on 2 NCB No 557,377.05 34,426.23 Review 18 Rehabilitation of Umar Ibn C2/Educati Post Tue-24-Apr- Ibrahim college Bama on 2 NCB No 557,377.05 278,688.52 Review 18 Construction of Solar Powered Boreholes (2Nos) in Umar Ibn Ibrahim college Bama Solar Lighting System to Borno C2/Educati Post Tue-24-Apr- Library on 1 NCB No 196,721.31 98,360.66 Review 18 Rehabilitation of Court Buildings in Bama Gwoza C2/Public Post Tue-22-May- Dikwa Mobbar Buildings 4 RfQ No 393,442.62 49,180.33 Review 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 11 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Rehabilitation of Local Govt Secretariats in Kukawa, Monguno, biu ,Abadam, Kala-Balge, Marte, C2/Public 1,229,508. Post Tue-05-Jun- Magumeri, Guzamala Buildings 8 RfQ No 1,967,213.11 20 Review 18 Rehabilitation of Traditional Rulers' Konduga , Monguno, Kukawa, Nganzai, Baga, Marte, Ngala, Abadam, Guzamala, C2/Public Post Tue-05-Jun- Kwajafa, Kumshe Buildings 6 RfQ No 1,442,622.95 180,327.87 Review 18 Provision of Community Resource Centres in 20 C2/Public Post LGAs Buildings 10 NCB No 2,295,081.97 860,655.74 Review Thu-05-Jul-18 Construction of Handpump Wells in Bama (3) Chibok (5), Biu (5), Mafa(3), Hawul (5), Askira/Uba(5), Konduga(4), Jere(5) Dikwa Post Fri-03-Aug- (3), Gwoza(5), C2/WASH 10 RfQ No 140,983.61 35,245.90 Review 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 12 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Construction of Solar Powered Boreholes in Askira Uba Gwoza(4),Bama(4), Ngala(3), Damboa(3) Jere(4),Kukawa(3), Biu(2),Konduga(3), Gubio(3), Askira/Uba(3), Magumeri(3), Marte(3), Mobbar(3), Monguno(3), Dikwa(2), Mafa(3), Abadam(3), Nganzai(3), Guzamala(3), Kaga(2), Chibok(2), Kala/Balge(3), Hawul(2)(To include 2Nos 5,000lt Plastic water tanks on a 1.5m raised platform , five fetching points/tap gallery, chain link 3,501,639. Post Wed-25-Jul- perimeter fence) C2/WASH 14 NCB No 4,668,852.46 34 Review 18 REHABILITATION OF LOCAL GOVERNMENT LODGES (Marte, Kaga, Chibok, Magumeri, Gwoza, Kala- Balge, Ngala, Guzamala, Abadam, Hawul, C2/Public Post Tue-21-Aug- Askira/Uba, Bama) Buildings 6 NCB No 1,311,475.41 786,885 Review 18 Rehabilitationof Traditional Rulers' Buildings Bama, Konduga, Gwoza ,Kareto, C2/Public Post Damboa , Monguno, Buildings 11 RfQ No 1,442,622.95 180,327.87 Review Thu-26-Jul-18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 13 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Kukawa, Askira-Uba , Dikwa, Baga, Marte REHABILITATION OF MINISTRY BUILDING (Ngala, C2/Public Post Tue-21-Aug- Monguno) Buildings 2 NCB No 276,577 Review 18 CONSTRUCTION OF SANITATION FACILITIES IN 21 LOCAL GOVERNMENT AREAS.ABADAM (6) ASKIRA(6) BAMA(6) BIU(6) CHIBOK(6) DAMBOA(6) DIKWA(6) GUBIO(6) GWOZA(6) JERE(6) KAGA(6) KALA-BALGE(6) KONDUGA(6) KUKAWA(6) MAFA(5) MOBBAR(6) MONGUNO(6) MARTE(6) NGALA(6) NGANZAI(6) Post Wed-19-Sep- MAGUMERI(6) C2/WASH 21 NCB No 781,517 Review 18 REHABILITATION OF EXISTING NON- FUNCTIONAL BOREHOLES ABADAM (1) ASKIRA UBA (2) BIU (2) DIKWA (1) Post Tue-18-Sep- GUBIO (1) GUZAMALA (1) C2/WASH 6 NCB No 258,525 Review 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 14 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT JERE (2) KALA BALGE (1) MAFA (2) MAGUMERI (1) MARTE (2) MOBBAR (1) NGALA (1) NGANZAI (1) Rehabilitation of 8 blocks of Laborataries (Umar Ibn C1/Educati Post Tue-18-Sep- Ibrahim college Bama) on 1 NCB No 262,295 Review 18 ADAMAWA Rehabilitation of Gulak Post Mon-14-May- Water Supply System C2/Water 1 NCB No 179,190.16 134,392.62 Review 18 Rehabilitation of Hong Post Mon-14-May- Water Supply System C2/Water 1 NCB No 116,646.90 87,485.18 Review 18 Rehabilitation of Michika Post Mon-14-May- Water supply system C2/Water 1 NCB No 138,193.44 103,645.08 Review 18 Rehabilitation of Uba Water Post Tue-15-May- Supply system C2/Water 1 NCB No 71,967.21 71,967.21 Review 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 15 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Rehabilitation of exisitng Water Supply sources in Post Tue-15-May- Gombi C2/Water 1 NCB No 30,475.41 30,475.41 Review 18 Construction of Uba New Post Mon-28-May- Water Supply Project C2/Water 1 NCB No 721,222.95 108,183.44 Review 18 Pella New Water Supply Post Mon-28-May- Project C2/Water 1 NCB No 555,289.34 83,293.40 Review 18 Construction of Hong New Post Mon-28-May- Water supply project C2/Water 1 NCB No 1,256,442.62 188,466.39 Review 18 Construction of Michika Post Tue-29-May- New Water supply project C2/Water 1 NCB No 1,189,261.84 178,389.28 Review 18 Construction GOMBI NEW Post Tue-29-May- WATER SUPPLY PROJECT C2/Water 1 NCB No 915,241.80 137,286.27 Review 18 Installation of 12 nos. Solar Boreholes (in secondary schools)- GSS Gombi, GDSS Garkida, GSS Hong, GDSS Pella, GSSS Uba, Post Thu-10-May- GJSS Uba, GDSS Garaha, C2/Water 1 NCB No 377,609.70 75,521.94 Review 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 16 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT GDSS Kwarhi, GDSS Za'ah, GSS Madagli, GSS Shuwa, GSS Gulak, GCSS Shuwa Installation of 37 Nos Solar Boreholes in 37 Health Centers in 7 Local Post Thu-10-May- Governments Areas C2/Water 4 NCB No 1,164,296.59 291,074.15 Review 18 Construction of 295Nos Hand Powered Bore Holes (in 2 primary schools per 35 wards, 35 Markets, 35 Motor parls and 155 Communities across 7 Post Thu-03-May- LGAs) C2/Water 4 NCB No 1,257,377.05 503,483.61 Review 18 Construction of VIP Latrines of 3-Comp (2 Blks Post Tue-14-Aug- in 24 pri sch) C2/WASH 3 RfQ No 212,459.02 79,672.13 Review 18 VIP Latrine of 3-Comp (2 Post Tue-14-Aug- Blks in 26 Markets) C2/WASH 3 RfQ No 230,163.93 92,065.57 Review 18 VIP Latrine of 3-Comp (2 Post Tue-14-Aug- Blks in 26 Motor Parks) C2/WASH 3 RfQ No 230,163.93 92,065.57 Review 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 17 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Rehabilitation of Lokwa C2/Transpo Post Mon-11-Jun- Bridge Mubi rt 1 NCB No 475,143.96 356,357.97 Review 18 Reconstruction of Main Road - Bangshika Road C2/Transpo Prior Mon-11-Jun- 2.5Km rt 1 NCB No 1,019,295.08 127,411.89 Review 18 Rehabilitation of Mubi Bazza Road with a spur to C2/Transpo 1,255,469. Prior Mon-11-Jun- Mayo Bani 45Km rt 1 NCB No 8,369,796.72 51 Review 18 Rehabilitation of PHC, Construction of Perimeter Fence and Staff Quarters (Civil Works, Solar Borehole, Fence & Security C2/Educati Prior Tue-10-Apr- Post) in 7 Communities on 7 NCB No 1,139,130.43 451,779.49 Review 18 Rehabilitation of Cottage Post Tue-10-Apr- Hospital C2/Health 1 NCB No 451,768.85 192,001.76 Review 18 Establishment of Trauma Post Thu-17-May- Center @ general hospital C2/Health 1 RfQ No 65,194.96 65,194.96 Review 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 18 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Renovation of GSS in 10 Towns (Gombi, Hong, Uba, Shuwa, Michika, Bazza, Mubi 1, Maiha, Madagali, C2/Educati Post Mubi North) on 10 NCB No 2,305,292.65 442,327.22 Review Tue-10-Jul-18 Renovation of 25Nos C2/Educati Post Primary School over 7 LGAs on 4 NCB No 865,747.88 324,655.45 Review Tue-10-Jul-18 Rehabilitation of Local Government Secretariat - C2/Public Post Thu-07-Jun- Song Buildings 1 NCB No 288,590.56 144,295.28 Review 18 Rehabilitation of Local Government Secretariat - C2/Public Post Thu-07-Jun- Madagali Buildings 1 NCB No 315,082.89 157,541.44 Review 18 Rehabilitation of District Head's Palace in 5 Communities (Uba, Gella, Gombi, Maiha/Pakka, C2/Public Post Thu-07-Jun- Gulak) Buildings 5 NCB No 422,463.57 158,423.84 Review 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 19 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT YOBE Conversion of Motorised Boreholes (28 Communities in Gulani and Damaturu) into Solar Post Mon-26-Mar- Powered C2/Water 1 NCB No 334,013.66 250,510.24 Review 18 Conversion of existing Motorized powered Borehole without Overhead tank into solar powered (Gujba, Gulani, Yunusari, Damaturu,& Post Mon-26-Mar- Geidam ) C2/Water 1 NCB No 277,532.56 208,149.42 Review 18 Conversion of existing Motorized powered Borehole into solar powered and construction of New Overhead tank (Gujba, Gulani, Yunusari, Post Mon-26-Mar- Damaturu,& Geidam) C2/Water 2 NCB No 542,490.73 406,868.05 Review 18 Drilling of New Solar Powered Boreholes in Gujba, Gulani, Yunusari, Damaturu, Fika, Potiskum, Post Mon-02-Apr- Geidam & Fune C2/Water 2 NCB No 878,917.25 329,593.97 Review 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 20 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Rehabilitation of Solar Powered Boreholes in Gulani, Gujba and Post Mon-02-Apr- Damaturu C2/Water 1 NCB No 244,228.65 183,171.49 Review 18 Construction & Upgrade of Post Wed-24-Oct- 33 nos. PHC Centres C2/Health 5 NCB No 5,386,554.10 538,655.41 Review 18 Reconstruction of Vandalized 3 Nos Post Wed-09-May- Immunization Offices C2/Health 1 RfQ No 68,618.27 68,618.27 Review 18 Renovation of 1No. General Post Mon-03-Sep- Hospital in Buni Yadi C2/Health 1 RfQ No 88,524.59 44,262.30 Review 18 Construction of 1No. Student Hostel each in College of Nursing and Midwifery Damaturu and College of Health Sciences Post Wed-22-Aug- and Technology, Nguru C2/Health 2 NCB No 983,606.56 245,901.64 Review 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 21 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Renovation of Govt Secondary Schools in Goniri,Bara, Bularafa, ,Kananma, Damagum, Buni Yadi, Kukuwa, Gujba and C2/Educati Post Mon-09-Apr- Best Center in Goniri on 5 NCB No 2,001,760.77 800,704.31 Review 18 Renovation of Dokshi C2/Educati Post Mon-09-Apr- Primary school, Gulani on 1 NCB No 168,034.42 67,213.77 Review 18 Rehabilitation of Local Government Office Secretariat in Gujba and C2/Public Post Wed-09-May- Potiskum Buildings 2 NCB No 472,529.40 75,459.62 Review 18 Rehabilitation of Development Offices in Gujba , Gulani, Yunusari & C2/Public Post Wed-09-May- Geidam Buildings 1 RfQ No 62,203.18 15,550.80 Review 18 Provision of Community Resource Centres in all 17 C2/Public Post Wed-23-May- LGAs Buildings 5 NCB No 1,950,819.67 731,557.38 Review 18 Rehabilitation of Audit C2/Public Post Wed-26-Sep- Office Buildings 1 RfQ No 63,078.12 15,769.53 Review 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 22 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Rehabilitation of Zonal C2/Public Post Wed-26-Sep- Statistical Office Buildings 1 RfQ No 50,491.80 25,245.90 Review 18 Rehabilitation ofCultural Buildings (District Head's Palace) in Buni Yadi and C2/Public Post Mon-27-Aug- Damagum Buildings 2 NCB No 446,682.62 111,670.66 Review 18 Rehabilitation of Government Buildings; C2/Public Post Mon-11-Jun- Agency for Mass Literacy Buildings 1 RfQ No 121,445.24 60,722.62 Review 18 Rehabilitation of Government Buildings; C2/Public Post Mon-11-Jun- Town Engineers Office Buildings 1 RfQ No 121,445.24 60,722.62 Review 18 GOODS BORNO Supply of Returnee C1/Transiti Resettlement Kits Bama, onal 2,216,737. Tue-13-Feb- Dikwa, Gwoza, Ngala, Support 4 NCB No 2,216,737.30 30 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 23 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Monguno, Damboa, Gudumbali, Mobbar, Kala Balge) Supply of Agricultural Support kits with Seeds, Fertilizers and Small Work Farm Tools (Bama, Biu, Gwoza, Ngala, Monguno, C1/Transiti Damboa, Askira, Mobbar, onal Tue-13-Feb- Kukawa) Support 3 NCB No 681,729.10 681,729.10 Post 18 Supply of Small Animals (Bama, Mafa, Gwoza, Ngala, Monguno, Damboa, C1/Transiti Chibok, Nganzai, Kala onal Tue-20-Feb- Balge) Support 3 NCB No 788,935.25 788,935.25 Post 18 Supply of Non-agricultural Livelihood Kits (Bama, Dikwa, Gwoza, Ngala, C1/Transiti Monguno, Damboa, Chibok, onal Tue-13-Feb- Mobbar, Hawul Support 2 NCB No 227,377.05 227,377.05 Post 18 C1/Transiti Supply of Skills Acquisition onal Tue-20-Feb- Start up Kits Support 3 NCB No 737,704.92 387,295.08 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 24 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Supply of solar electrification to 3 GENERAL HOSPITALS in ABADAM, GWOZA and KALA-BALGE and five Comprehensive Health Centre in Abadam, 2 in Gwoza, Kala-Balge, Askira - Tue-01-Jan- Uba C2/Health 3 NCB No 670,553.40 516,770.59 Post 19 Supply of Medical Equipment For 3General Hospitals in ABADAM, ASKIRA UBA, and KALA- Tue-15-Jan- BALGE C2/Health 3 NCB No 590,163.93 73,770.49 Post 19 Supply of Essential Drugs/Medical Consumables For 3 General Hospitals in HAWUL, Tue-05-Mar- MOBBAR AND DAMBOA C2/Health 3 NCB No 472,131.15 59,016.39 Post 19 Supply of Medical Equipment for Comprehensive Health Wed-09-Jan- Centers (Gwoza- Izge) C2/Health 1 NCB No 245,901.64 30,737.70 Post 19 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 25 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Supply of Essential Drugs/Medical Consumables for Comprehensive Health Tue-05-Feb- Center (Gwoza-izge) C2/Health 1 NCB No 236,065.57 29,508.20 Post 19 Supply of Medical Equipment to 15 PHCs to (Ngala, Nganzai Kukawa, Biu, Konduga, Gubio, Askira/Uba, Guzamala, Bama, Jere, Marte, Mobbar, Dikwa, Tue-15-Jan- Mafa, Abadam) C2/Health 2 NCB No 983,606.56 122,950.82 Post 19 Supply of Essential Drugs to 15 PHCs (Ngala, Nganzai Kukawa, Biu, Konduga, Gubio, Askira/Uba, Guzamala, Bama, Jere, Marte, Mobbar, Dikwa, Tue-05-Feb- Mafa, Abadam) C2/Health 2 NCB No 786,885.25 98,360.66 Post 19 Supply and Installation of Solar Inverters in 15 PHCs in (Ngala, Nganzai Kukawa, Biu, Konduga, Gubio, Askira/Uba, Guzamala, Bama, Jere, Marte, Mobbar, Tue-06-Mar- Dikwa, Mafa, Abadam) C2/Health 1 NCB No 262,295.08 65,573.77 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 26 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Furniture for Library/ Offices in the Borno State Library and Furniture for 15 blocks of classrooms in Umar Ibn ibrahim college C2/Educati Tue-19-Mar- Bama on 2 NCB No 491,803.28 245,901.64 Post 19 Books and other learning Materials including elibrary C2/Educati Tue-19-Mar- in the Borno State library on 1 NCB No 262,295.08 131,147.54 Post 19 Suppy of Computers and other accessories to the Borno State Library , Maiduguri and Umar Ibn C2/Educati Tue-19-Mar- ibrahim college Bama on 2 RfQ No 81,967.21 40,983.61 Post 19 Supply of Medical Equipment TO 3 Comprehensive Health centers IN HAWUL, MOBBAR AND DAMBOA Tue-06-Mar- (Kwajafa, Kareto, Damboa) C2/Health 1 NCB No 196,721.31 49,180.33 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 27 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Installation of solar inverters for PHC Gwoza( Tue-06-Mar- Izge) C2/Health 1 NCB No 13,114.75 13,114.75 Post 18 ADAMAWA C1/Transiti Supply of Returnee onal Mon-19-Mar- Resettlement Kits Support 2 NCB No 490,780.33 490,780.33 Post 18 Supply of Agricultural Support kits with Seeds, C1/Transiti Fertilizers and Small Work onal 1,496,508. Mon-19-Mar- Farm Tools Support 7 NCB No 1,496,508.20 20 Prior 18 C1/Transiti onal Thu-19-Apr- Supply of Small Animals Support 1 NCB No 182,950.82 182,950.82 Post 18 C1/Transiti Supply of Non-agricultural onal Mon-19-Mar- Livelihood Kits Support 1 NCB No 213,442.62 213,442.62 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 28 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT C1/Transiti Start up kits for quick to onal Mon-19-Mar- market trading Support 1 NCB No 114,754.10 114,754.10 Post 18 Housing Refurbishment Returnee Packs for Voluntary Returnees across C1/Transiti the 7 LGAs being onal Thu-14-Jun- rehabilitated. Support 2 NCB No 390,163.93 331,639.34 Post 18 Supply of Medical Equipment to PHCs in 7 communities and Cottage Hospital in Gulak C2/Health 2 NCB No 344,262.30 43,032.79 Post Thu-19-Jul-18 Supply of Essential Drugs/Medical Consumable to PHCs in 7 Communities and Cottage Hospital in Thu-01-Nov- Gulak C2/Health 2 NCB No 452,459.02 108,196.72 Post 18 Installation of Solar Inverters in 7 Rehabilitated PHCs, Cottage Hospital in Mon-06-Aug- Gulak C2/Health 3 NCB No 268,861.16 18,852.46 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 29 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Equipping of Trauma Center @ Michika General Mon-06-Aug- hospital C2/Health 1 NCB No 214,142.46 80,303.42 Post 18 Supply of Furniture to C2/Educati Thu-29-Mar- Primary Schools in 7 LGAs on 1 NCB No 245,901.64 30,737.70 Post 18 Supply of Books and Teaching/Learning Materials to Primary C2/Educati Thu-29-Mar- Schools in 7 LGAs on 1 NCB No 327,868.85 122,950.82 Post 18 Establishment of spare part supply chain/buffer Mon-16-Apr- stock for Water Facilities C2/WASH 1 NCB No 114,754.10 86,065.57 Post 18 Train the Trainer/User Workshops (i.e. 2 per LGA) for VLOM (Village Level Operation and Maintenance) WASHCOMS, (WASH Committees at LGA Level, WASH Units @ LGAs, VHPs (Voluntary Hygiene Promoters) State/LGA Govt Tue-24-Apr- Officials. C2/WASH 1 NCB No 72,131.15 54,098.36 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 30 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT YOBE C1/Transiti Supply of Non Food Items onal Wed-21-Mar- (NFIs) Kits Support 3 NCB No 559,213.11 559,213.11 Post 18 C1/Transiti Supply of Agricultural kits onal 1,048,940. Wed-21-Mar- with seeds, oil, small tools Support 3 NCB No 1,048,940.98 98 Post 18 C1/Transiti onal Mon-23-Apr- Supply of Small Animals Support 3 NCB No 688,524.59 688,524.59 Post 18 C1/Transiti Non-agricultural Livelihood onal Mon-26-Mar- kits Support 2 NCB No 352,295.08 352,295.08 Post 18 C1/Transiti Supply of Skills Acquisition onal Wed-21-Mar- Start up Kits Support 3 NCB No 786,885.25 550,819.67 Post 18 Procure and distribute Plumpy Nuts for Wed-25-Apr- malnourished children in C2/Health 1 NCB No 215,438.65 32,315.80 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 31 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Gujba, Geidam and Yunusari LGAs Equipping of Trauma Mon-12-Feb- Center C2/Health 1 NCB No 214,147.54 53,536.89 Post 18 Supply of Students Textbooks and Teachers' C2/Educati Mon-17-Sep- Guides on 1 NCB No 284,062.30 71,015.57 Post 18 Supply of Laboratory Equipment Physics. C2/Educati Mon-17-Sep- Chemistry & Biology on 1 NCB No 213,114.75 53,278.69 Post 18 C2/Educati Mon-17-Sep- Supply of School Furniture on 3 NCB No 804,885.25 201,221.31 Post 18 CONSULTING SERVICES BORNO Skills Acquisition Training C1/Transiti (3Nos Consultancies across onal Mon-09-Jul- 10 LGAs) Support 3 QCBS No 491,803.28 258,196.72 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 32 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Specialized psycho-social support responding to C1/Commu needs (3Nos Consultancies nity Wed-28-Mar- across 10 LGAs) Resilience 3 QCBS No 826,229.51 619,672.13 Post 18 Consultancy for the Mobilisation and Organisation of Civic Education with Cultural and Recreational activities at Community Level with programs that respond to needs as prioritized by community based diagnosis (3Nos C1/Commu Consultancies across 10 nity Wed-11-Apr- LGAs) Resilience 3 QCBS No 442,622.95 265,573.77 Post 18 Consultancy for Sensitization, Community Mobilization and formation of peace groups within 7 Communities(establishmen t of community platforms to discuss community needs, grievances; and C1/Commu redress mechanisms. (1No nity Mon-30-Apr- Consultancy) Resilience 1 QCBS No 531,147.54 318,688.52 Prior 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 33 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Consultancy for Post- C1/Commu Conflict Transitional Justice nity Mon-21-May- and Accountability Resilience 1 QCBS No 147,540.98 88,524.59 Post 18 Statewide sponsorship for Radio Programming for Peacebuilding Campaign and Content for dissemination (focusing on deradicalisation, grievance C1/Commu redress and peacebuilding nity Mon-04-Jun- outreach themes) Resilience 1 CQS No 475,409.84 178,278.69 Prior 18 Consultancy for Educational campaigns for the prevention of mine and unexploded ordinance accidents /Mobilisation and Sensitization Campaign on Mine Action (Unexploded C1/Commu Ordnances) (1No nity Mon-04-Jun- Consultancy) Resilience 1 QCBS No 442,622.95 354,098.36 Prior 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 34 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Consultancy for Leadership Accountability and Transparency Training Programme (NELATTP) Targeting 20 LGA Staff and State Ministry Personal per LGA - Development of a transparency and accountability Local Governance Model through community participation C1/Commu (social accountability nity Fri-25-May- mechanisms) Resilience 1 CQS No 88,524.59 55,327.87 Post 18 Consultancy for Registration, Mapping and C1/Strengt Profiling of all local hening government structures and Local existing capacities State Governanc Fri-25-May- Wide e 1 CQS No 49,180.33 30,737.70 Post 18 Consultancy to provide C1/Strengt Capacity building of LG hening Officers for economic Local planning and policy Governanc Fri-25-May- development e CQS No 88,524.59 55,327.87 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 35 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT C1/Strengt hening Capacity building for LG Local officials on programme Governanc Fri-25-May- design and implementation e CQS No 88,524.59 55,327.87 Post 18 Capacity building of LG C1/Strengt Officers for local hening governments on budget Local planning and execution, Governanc Fri-25-May- monitoring and reporting e 1 CQS No 88,524.59 55,327.87 Post 18 Capacity building of LG Officers for strategic communications C1/Strengt (Legislative Advocacy, hening Media relations, Local Stakeholder Management Governanc Fri-25-May- etc). e CQS No 88,524.59 55,327.87 Post 18 Capacity Building for 10 Local Government C1/Strengt Emergency Management hening Responders in Displaced Local and Transitional Local Governanc Fri-25-May- Government Officials e 1 CQS No 203,278.69 152,459.02 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 36 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Sensitization, training (especially on Identification, Documentation, Tracing and Reunification and follow up) and coaching for state and non-state partners on case management of UASC C1/Program (Unaccompanied and Support to Fri-25-May- Separated Children) UASC 1 MOU No 73,770.49 59,016.39 Post 18 Training for officials of relevant State MDAs on C1/Program effective approaches to Support to Thu-28-Jun- UASC UASC 1 IC No 16,393.44 13,114.75 Post 18 Teacher Training and C1/Educati Fri-25-May- Recertification on 1 MOU No 442,622.95 77,459.02 Post 18 Training of Community Health Workers (CHeWs, VHWs, Midwives) to Staff Targeted Health Facilities (3Nos consultancies across the state. Amount Inclusive of Workshop and per diem Mon-29-Apr- payments) C1/Health 3 QCBS No 796,721.31 298,770.49 Post 19 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 37 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Sensitization and Mobilisation for Health (Outreach Programs) in 27 LGAs (Over 10 Fri-25-May- engagements) C1/Health 10 CQS No 708,196.72 265,573.77 Post 18 Identification and training of Village Levels Mechanics and Local Area Mechanics on Operation and Maintenance of existing Hand Pump and Solar powered Borehole for effective utilization and Fri-25-May- management. C2/WASH 1 CQS No 98,360.66 73,770.49 Post 18 ADAMAWA Refresher Training of Existing Extension Workers C1/Transiti to support Livelihoods onal Thu-10-May- Projects Support 1 CQS No 65,573.77 65,573.77 Post 18 Training of affected farmers to apply inputs and access targeted C1/Transiti agricultural value chains onal Thu-21-Jun- and agribusiness skills Support 1 CQS No 167,216.39 167,216.39 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 38 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Establishment of Returnees Resettlement Registry at each LGA for Sensitization, Mobilisation and Logistics support for Safe and C1/Transiti Voluntary returns to 7 onal Thu-24-May- LGAs being rehabilitated Support 1 CQS No 61,565.57 49,252.46 Post 18 Consultancy to provide C1/Transiti Training for Bio Data onal Thu-10-May- Registration Support Support 1 IC No 1,377.05 1,101.64 Post 18 Consultancy for Sensitization, Community Mobilization and formation of peace groups within 7 Communities(establishmen t of community platforms to discuss community C1/Commu needs, grievances; and nity Mon-04-Jun- redress mechanisms Resilience 1 QCBS No 344,262.30 206,557.38 Prior 18 Diagnosis of community- specific reconciliation, peacebuilding and social C1/Commu cohesion needs and nity Thu-03-May- consequent development Resilience 2 QCBS No 344,262.30 206,557.38 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 39 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT of Civil Education Programs using Cultural and Recreational activities at Community Level (2Nos Consultancies) Provision of specialized psycho-social assessment and support responding to needs through group support, recreational, customary and socializing activities, referrals etc C1/Commu (3Nos Consultancies across nity Mon-11-Jun- the affected areas) Resilience 3 QCBS No 642,622.95 481,967.21 Post 18 Sensitization and Mobilisation Programs for Awareness against Stigmatization of Woman and Children associated C1/Commu with armed groups. (1No nity Mon-04-Jun- Consultancy) Resilience 1 QCBS No 413,114.75 247,868.85 Prior 18 Consultancy for Mediation and Alternate Dispute Resolution Capacity C1/Commu Building within the nity Mon-18-Jun- Community Leadership and Resilience 3 QCBS No 425,960.66 255,576.39 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 40 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Governance Structures (3Nos Consultancies acrossthe state) C1/Citizen- Consultancy for Leadership Governmen Accountability and t Transparency Training Relationshi Thu-10-May- Programme p Building 1 CQS No 72,131.15 45,081.97 Post 18 Registration, Mapping and C1/Strengt Profiling of all local hening government structures and Local existing capacities State Governanc Mon-28-May- Wide e 1 CQS No 39,344.26 24,590.16 Post 18 C1/Strengt Capacity building of LG hening Officers for economic Local planning and policy Governanc Mon-28-May- development e 1 CQS No 72,131.15 45,081.97 Post 18 C1/Strengt hening Capacity building for Local programme design and Governanc Mon-28-May- implementation e 1 CQS No 72,131.15 45,081.97 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 41 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Capacity building of LG C1/Strengt Officers for local hening governments on budget Local planning and execution, Governanc Mon-28-May- monitoring and reporting e 1 CQS No 72,131.15 45,081.97 Post 18 Capacity building of LG Officers for strategic communications C1/Strengt (Legislative Advocacy, hening Media relations, Local Stakeholder Management Governanc Thu-21-Jun- etc). e 1 CQS No 72,131.15 45,081.97 Post 18 Hygiene Promotion Mon-17-Sep- Sensitization/Mobilization C2/WASH 1 IC No 9,180.33 6,885.25 Post 18 Hygiene Promotion Mon-12-Nov- Campaign C2/WASH 1 CQS No 85,677.59 64,258.20 Post 18 Training of Community Health Workers (CHeWs) to Staff Targeted Health Thu-13-Dec- Facilities C2/Health 1 CQS No 68,852.46 55,081.97 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 42 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Sensitization and Mobilisation for Health Mon-17-Sep- (Outreach Programs) C2/Health 1 CQS No 183,606.56 146,885.25 Post 18 Mobilization and Sensitization for Children C2/Educati Thu-31-May- Education on 1 CQS No 206,557.38 206,557.38 Post 18 Teacher Training and Recertification ( Primary C2/Educati Thu-13-Dec- and Secondary Schools ) on 1 CQS No 360,655.74 360,656.74 Prior 18 YOBE Skills Acquisition Training C1/Transiti 3 Nos Consultancies across onal Wed-25-Apr- 8 LGAs) Support 3 QCBS No 524,590.16 367,213.11 Post 18 Consultancy for Sensitization, Community Mobilization and formation of peace groups within 15 C1/Peace Wed-23-May- Communities Building 1 QCBS No 491,803.28 319,672.13 Prior 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 43 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Diagnosis of community- specific reconciliation, peacebuilding and social cohesion needs and consequentt development of Civil Education Programs using Cultural and Recreational activities at C1/Peace Mon-04-Jun- Community Level Building 1 CQS No 49,180.33 31,967.21 Post 18 Consultancy for Mediation and Alternate Dispute Resolution Capacity Building within the Community Leadership and C1/Peace Mon-04-Jun- Governance Structures Building 1 CQS No 177,049.18 115,081.97 Post 18 Radio programs on mine awareness, dispute resolution in Hausa, Kanuri C1/Peace Wed-25-Jul- and Fulfulde Building 1 CQS No 280,719.92 105,269.97 Post 18 Provision of specialized psycho-social assessment and support responding to needs (3 Nos Consultancies C1/Peace Wed-20-Jun- across 8 LGAs) Building 3 QCBS No 625,822.95 438,076.07 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 44 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Mapping and profiling of local government C1/Strengt structures and hening communities in places of Local both displacement and Governanc Thu-28-Jun- origin e 1 CQS No 39,344.26 39,344.26 Post 18 Establishment of C1/Strengt community platforms to hening discuss community needs, Local grievances; and building a Governanc Wed-06-Jun- bottom-up planning model e 1 CQS No 74,948.93 59,959.14 Post 18 Development of a transparency and accountability model C1/Strengt through community hening participation (social Local accountability Governanc Wed-06-Jun- mechanisms) e 1 CQS No 47,377.05 37,901.64 Post 18 C1/Strengt Capacity building of LG hening Officers for economic Local planning and policy Governanc Thu-28-Jun- development e 1 CQS No 55,737.70 44,590.16 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 45 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT C1/Strengt hening Capacity building for Local programme design and Governanc Thu-28-Jun- implementation e 1 CQS No 55,737.70 44,590.16 Post 18 Capacity building of LG C1/Strengt Officers for local hening governments on budget Local planning and execution, Governanc Thu-28-Jun- monitoring and reporting e 1 CQS No 55,737.70 44,590.16 Post 18 Capacity building of LG Officers for strategic communications C1/Strengt (Legislative Advocacy, hening Media relations, Local Stakeholder Management Governanc etc). e 1 CQS No 55,737.70 44,590.16 Post Thu-26-Jul-18 Sensitization, training (especially on Identification, Documentation, Tracing and Reunification and follow up) and coaching for state and non-state C1/Program partners on case Support on Thu-07-Jun- management of UASC UASC 1 CQS No 52,459.02 41,967.21 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 46 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Training for officials of C1/Program relevant MDAs on effective Support on Thu-28-Jun- approaches to UASC UASC 1 CQS No 8,196.72 6,557.38 Post 18 Menstrual Hygiene Management to support Women and Girls of productive ages to effectively maintain their Thu-17-May- menstrual hygiene C2/WASH 1 QCBS No 110,163.93 41,311.48 Post 18 Community Led Total Sanitation (CLTS) Implementation in Thu-31-May- communities C2/WASH 1 QCBS No 220,327.87 82,622.95 Post 18 Community Management training of entire Communities in the 8 proposed LGAs to effectively manage their Water, Sanitation and Mon-18-Jun- Hygiene Facilities C2/WASH 3 QCBS No 293,770.49 110,163.93 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 47 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Identification and training of Village Levels Mechanics and Local Area Mechanics on Operation and Maintenance of existing Hand Pump and Solar powered Borehole for effective utilization and Thu-17-May- management. C2/WASH 1 CQS No 98,360.66 61,475.41 Post 18 Water Safety Plan implementation in the entire Communities of the Mon-16-Jul- four LGAs. C2/WASH 1 CQS No 112,459.02 84,344.26 Post 18 Integrated Outreach Services (Up to 5 activities Thu-17-May- envisaged) C2/Health 5 QCBS No 344,262.30 129,098.36 Post 18 Training of Community Health Workers (CHeWs, VHWs, Midwives) to Staff Thu-15-Nov- Targeted Health Facilities C2/Health 1 QCBS No 501,639.34 376,229.51 Prior 18 Teacher Training and C2/Educati Mon-26-Nov- Recertification in all LGAs on 1 MOU No 278,688.52 209,016.39 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 48 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT PCNI NERSP PMC CELL Project Wide Project C3/Technic Management Consultancy al 2,000,000. Wed-11-Apr- Firm Assistance 1 QCBS No 3,000,000.00 00 Prior 18 Consultancy services for immediate- and medium- term implementation capacity building (4 C3/Technic separate Consultancies al Thu-03-May- Envisaged) Assistance 4 CQS No 536,393.44 268,196.72 Prior 18 Consultancy Services for C3/Technic Monitoring and Evaluation al Baseline Study Assistance 1 QCBS No 177,049.18 177,049.18 Post Fri-27-Apr-18 Consultancy services for setting up citizen engagement and third C3/Technic party monitoring al mechanisms Assistance 1 CQS No 177,049.00 59,016.33 Post Fri-06-Apr-18 Consultancy Services for C3/Technic Environmental Impact al Assessment Assistance 1 QCBS No 39,344.26 39,344.26 Post Fri-13-Apr-18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 49 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT NON- CONSULTING SERVICES ADAMAWA Door to Door Collection of Thu-24-May- Solid waste in 7 LGAs C2/WASH 1 NCB No 236,065.57 88,524.59 Post 18 Disposal of Waste from Door to Door Collection in Tue-13-Feb- 7 LGAs C2/WASH 1 NCB No 229,508.20 86,065.57 Post 18 OPERATIONAL COSTS PCNI NERSP PMC CELL PMC Software, Intranet and C3/Operati Tools onal Costs 3 RfQ No 159,240.16 159,240.16 Post Fri-27-Apr-18 Video Conferencing C3/Operati Thu-25-Jan- Equipment onal Costs 1 RfQ No 131,147.54 131,147.54 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 50 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT C3/Operati Tue-27-Mar- Office Vehicles onal Costs 1 RfQ No 344,265.00 344,265.00 Post 18 BORNO STATE Procurement of 12 laptop computers, 12 laserjet printers, 4 photocopiers, 3 desktops, 15 desktops for work stations, 2 deskjet printers, HP Scanjet C3/Operati scanner onal Costs 1 RfQ No 159,240.16 159,240.16 Post Fri-27-Apr-18 Procurement of video conference equipment and C3/Operati internet connectivity onal Costs 1 RfQ No 65,574.00 65,574.00 Post Fri-27-Apr-18 Procurement of Office C3/Operati Tue-27-Mar- Furniture onal Costs 1 NCB No 32,786.89 32,786.89 Post 18 Procurement of 1 Video C3/Operati Wed-28-Mar- Camera, 2 DLSR Cameras, onal Costs 1 RfQ No 7,000.00 7,000.00 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 51 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Procurement of 100KVA sound proof Generator, C3/Operati Sun-20-May- 10KVA Inverter System onal Costs 1 RfQ No 42,623.00 42,623.00 Post 18 Procurement of Office Vehicles - 2 Toyota Prado Jeep, 3 Toyota Hilux, 1 C3/Operati Wed-14-Mar- Toyota Corolla onal Costs 1 NCB No 448,525.00 448,525.00 Post 18 ADAMAWA STATE Procurement of computers, printers and other C3/Operati Wed-28-Mar- accessories onal Costs 1 RfQ No 24,131.15 24,131.15 Post 18 Procurement of video conference equipment and C3/Operati Wed-28-Mar- internet connectivity onal Costs 1 RfQ No 65,574.00 65,574.00 Post 18 Procurement of Office C3/Operati Tue-27-Mar- Furniture onal Costs 1 NCB No 32,786.89 32,786.89 Post 18 Procurement of 1 Video C3/Operati Wed-28-Mar- Camera, 2 DLSR Cameras, onal Costs 1 RfQ No 20,327.87 20,327.87 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 52 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Procurement of 100KVA sound proof Generator, C3/Operati Mon-26-Mar- 10KVA Inverter System onal Costs 1 RfQ No 42,623.00 42,623.00 Post 18 Procurement of Office Vehicles - 2 Toyota Prado Jeep, 3 Toyota Hilux, 1 C3/Operati Tue-27-Mar- Toyota Corolla onal Costs 1 RfQ No 518,033.00 518,033.00 Post 18 YOBE STATE Procurement of computers, printers and other C3/Operati Wed-28-Mar- accessories onal Costs 1 RfQ No 24,131.15 24,131.15 Post 18 Procurement of video conference equipment and C3/Operati Wed-28-Mar- internet connectivity onal Costs 1 RfQ No 65,574.00 65,574.00 Post 18 Procurement of Office C3/Operati Tue-27-Mar- Furniture onal Costs 1 NCB No 32,786.89 32,786.89 Post 18 Procurement of 1 Video C3/Operati Wed-28-Mar- Camera, 2 DLSR Cameras, onal Costs 1 RfQ No 20,327.87 20,327.87 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 53 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Procurement of 100KVA sound proof Generator, C3/Operati Mon-26-Mar- 10KVA Inverter System onal Costs 1 RfQ No 42,623.00 42,623.00 Post 18 Procurement of Office C3/Operati Tue-27-Mar- Vehicles onal Costs 1 RfQ No 468,852.46 468,852.46 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 54 PROCUREMENT Nigeria : Multi-Sectoral Crisis Recovery Project for North Eastern Nigeria PLAN General Information Country: Nigeria Bank’s Approval Date of the Original Procurement Plan: 2018-06-05 2021-05-10 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P157891 GPN Date: Project Name: Multi-Sectoral Crisis Recovery Project for North Eastern Nigeria Loan / Credit No: IDA / 59880 Borno MCRP Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned NG-BORNO MCRP-58897-CW- Infrastructure Rehabilitation Pending RFB / Renovation Of 31- No. Single Stage - One 2019-07- IDA / 59880 and Service Delivery Post Request for Bids Open - National 457,377.00 0.00 Implementat 2018-10-08 2018-10-13 2018-11-24 2018-12-24 2019-01-28 Double Classroom Block - Envelope 27 Restoration & Improvement ion Bama NG-BORNO MCRP-57818-CW- Infrastructure Rehabilitation Under RFQ / Rehabilitation of Court Request for Single Stage - One 2019-01- IDA / 59880 and Service Delivery Post Open - National 393,443.00 0.00 Implementat 2018-05-12 2018-07-07 Buildings in Bama Gwoza Quotations Envelope 03 Restoration & Improvement ion Dikwa Mobbar NG-BORNO MCRP-58384-CW- Pending RFQ / Rehabilitation of Strengthening Peace Building, Request for Single Stage - One 2019-04- IDA / 59880 Post Open - National 276,578.00 0.00 Implementat 2018-08-20 2018-10-15 Ministry Building (Ngala, Stability and Social Cohesion Quotations Envelope 13 ion Monguno) NG-BORNO MCRP-58804-CW- RFQ / Rehabilitation of Existing Non-Functional Boreholes Abadam (1) Askira Infrastructure Rehabilitation Request for Single Stage - One 2019-05- Uba (2) Biu (2) Dikwa (1) IDA / 59880 and Service Delivery Post Open - National 25,852.46 22,161.59 Completed 2018-09-17 2018-11-12 2019-12-10 Quotations Envelope 11 Gubio (1) Guzamala (1) Jere Restoration & Improvement (2) Kala Balge (1) Mafa (2) Magumeri (1) Marte (2) Mobbar (1) Ngala (1) Nganzai (1) NG-BORNO MCRP-58797-CW- Infrastructure Rehabilitation Request for Single Stage - One 2019-04- RFQ / Reconstruction of Post IDA / 59880 and Service Delivery Post Open - National 163,934.00 0.00 Canceled 2018-08-20 2018-10-15 Quotations Envelope 13 Office (Bama) Restoration & Improvement NG-BORNO MCRP-58769-CW- Infrastructure Rehabilitation Request for Single Stage - One 2019-08- RFQ / Construction Of 5-No IDA / 59880 and Service Delivery Post Open - National 73,770.00 0.00 Canceled 2018-12-08 2019-02-02 Quotations Envelope 01 Vip Toilets -Monguno Restoration & Improvement NG-BORNO MCRP-58402-CW- Infrastructure Rehabilitation Request for Single Stage - One 2019-08- RFQ / Renovation Of 1-No. IDA / 59880 and Service Delivery Post Open - National 18,033.00 0.00 Canceled 2018-12-08 2019-02-02 Quotations Envelope 01 Educational Office -Damboa Restoration & Improvement NG-BORNO MCRP-55929-CW- RFQ / Construction of Handpump Wells in Bama (3) Infrastructure Rehabilitation Request for Single Stage - One 2019-03- Chibok (5), Biu (5), Mafa(3), IDA / 59880 and Service Delivery Post Limited 140,984.00 0.00 Canceled 2018-07-24 2018-09-18 Quotations Envelope 17 Hawul (5), Askira/Uba(5), Restoration & Improvement Konduga(4), Jere(5) Dikwa (3), Gwoza(5), NG-BORNO MCRP-58026-CW- Infrastructure Rehabilitation RFQ / Construction Of 4- No. Request for Single Stage - One 2019-07- IDA / 59880 and Service Delivery Post Open - National 157,377.00 0.00 Canceled 2018-11-10 2019-01-05 Double Classroom Block in Quotations Envelope 04 Restoration & Improvement Ajiri. Mafa NG-BORNO MCRP-55956-CW- Infrastructure Rehabilitation Request for Single Stage - One 2019-05- RFQ / Construction Of 3-No. IDA / 59880 and Service Delivery Post Limited 196,721.00 0.00 Canceled 2018-09-08 2018-11-03 Quotations Envelope 02 Educational Office -Kukawa Restoration & Improvement NG-BORNO MCRP-58801-CW- RFQ / Construction of Solar Infrastructure Rehabilitation Powered Boreholes (2Nos) in Request for Single Stage - One 2018-12- IDA / 59880 and Service Delivery Post Open - National 196,721.00 0.00 Canceled 2018-04-14 2018-06-09 Umar Ibn Ibrahim college Quotations Envelope 06 Restoration & Improvement Bama Solar Lighting System to Borno Library NG-BORNO MCRP-58893-CW- Infrastructure Rehabilitation Request for Single Stage - One 2019-08- RFQ / Construction Of 4-No IDA / 59880 and Service Delivery Post Open - National 59,016.00 0.00 Canceled 2018-12-08 2019-02-02 Quotations Envelope 01 Vip Toilets -Mafa Restoration & Improvement NG-BORNO MCRP-56416-CW- Infrastructure Rehabilitation RFQ / Construction Of 2-No. Request for Single Stage - One 2019-06- IDA / 59880 and Service Delivery Post Limited 131,148.00 0.00 Canceled 2018-10-13 2018-12-08 Educational Office -Hawul Quotations Envelope 06 Restoration & Improvement Sakwa, Kwajafa NG-BORNO MCRP-58803-CW- Infrastructure Rehabilitation Pending RFB / RehabilitatIon of 3 Request for Single Stage - One 2019-06- IDA / 59880 and Service Delivery Post Open - National 1,476,727.00 0.00 Implementat 2018-10-17 2018-12-12 General Hospital in (ABADAM, Quotations Envelope 10 Restoration & Improvement ion ASKIRA UBA & KALA-BALGE) NG-BORNO MCRP-58871-CW- RFB / Rehabilitation of Local Infrastructure Rehabilitation Under Request for Single Stage - One 2019-05- Govt Secretariats of 8 Local IDA / 59880 and Service Delivery Post Open - National 2,622,951.00 0.00 Implementat 2018-09-17 2018-11-12 Quotations Envelope 11 Government Areas of Borno Restoration & Improvement ion State NG-BORNO MCRP-57851-CW- RFB / Construction of new Infrastructure Rehabilitation Under Request for Single Stage - One 2019-05- Solar Powered Boreholes in 27 IDA / 59880 and Service Delivery Post Open - National 3,514,754.00 0.00 Implementat 2018-09-17 2018-11-12 Quotations Envelope 11 Local Government Areas of Restoration & Improvement ion Borno State NG-BORNO MCRP-58350-CW- Infrastructure Rehabilitation RFB / REHABILITATION OF 10 Request for Single Stage - One 2019-05- IDA / 59880 and Service Delivery Post Open - National 1,311,475.47 257,374.29 Completed 2018-09-12 2018-11-07 2018-10-12 LOCAL GOVERNMENT LODGES Quotations Envelope 06 Restoration & Improvement in Borno State Page 1 NG-BORNO MCRP-56722-CW- RFQ / Renovation Of 1-No. Infrastructure Rehabilitation Request for Single Stage - One 2019-08- Educational Office in Mafa IDA / 59880 and Service Delivery Post Limited 65,674.00 104,759.75 Completed 2018-12-15 2019-06-03 2019-02-09 2019-06-25 Quotations Envelope 08 Local Government Area of Restoration & Improvement Borno State NG-BORNO MCRP-58891-CW- RFB / Rehabilitation of Primary Infrastructure Rehabilitation Pending Health Care Center in 15 Local Request for Single Stage - One 2019-06- IDA / 59880 and Service Delivery Post Open - National 2,459,016.00 0.00 Implementat 2018-10-21 2018-12-16 Government Areas of the 3 Quotations Envelope 14 Restoration & Improvement ion Senatorial districts of Borno State NG-BORNO MCRP-58035-CW- Infrastructure Rehabilitation Request for Single Stage - One 2019-05- RFB / Rehabilitation of Borno IDA / 59880 and Service Delivery Post Open - National 131,148.00 287,546.62 Completed 2018-09-22 2018-11-17 2019-07-24 Quotations Envelope 16 State Library in Maiduguri Restoration & Improvement NG-BORNO MCRP-57567-CW- RFQ / Solar Lighting System to Infrastructure Rehabilitation Pending Request for Single Stage - One 2019-05- Umar Ibrahim College Library IDA / 59880 and Service Delivery Post Limited 98,361.00 0.00 Implementat 2018-10-02 2018-11-27 Quotations Envelope 26 Bama and Borno State Library Restoration & Improvement ion Maiduguri NG-BORNO MCRP-58781-CW- RFQ / Rehabilitation of Umar Infrastructure Rehabilitation Pending Request for Single Stage - One 2019-05- Ibn Ibrahim college Library in IDA / 59880 and Service Delivery Post Open - National 262,295.00 0.00 Implementat 2018-09-17 2018-11-12 Quotations Envelope 11 Bama Local Government Area Restoration & Improvement ion of Borno State NG-BORNO MCRP-58768-CW- RFQ / Construction Of 18-No. Infrastructure Rehabilitation Request for Single Stage - One 2019-05- Double Classroom Blocks in IDA / 59880 and Service Delivery Post Open - National 708,197.00 133,222.10 Completed 2018-09-24 2018-11-19 2018-10-24 Quotations Envelope 18 Askira/Uba Local Government Restoration & Improvement Area of Borno State NG-BORNO MCRP-73721-CW- RFQ / Reconstruction of Local Infrastructure Rehabilitation Request for Single Stage - One 2019-05- Education Authorities Offices IDA / 59880 and Service Delivery Post Open - National 983,607.00 100,066.50 Completed 2018-09-17 2018-11-12 2019-06-27 Quotations Envelope 11 in 9 Local Governments of Restoration & Improvement Borno State BOMCRP/RFB/CW/001/019 / Infrastructure Rehabilitation Pending Single Stage - One 2019-08- Rehabilitation of 1 Ngala IDA / 59880 and Service Delivery Post Request for Bids Open - National 2,295,081.00 0.00 Implementat 2019-03-05 2019-03-10 2019-04-09 2019-04-19 2019-05-03 Envelope 31 Bridge Restoration & Improvement ion NG-BORNO MCRP-58400-CW- RFQ / Renovation of 1-No. Infrastructure Rehabilitation Request for Single Stage - One 2019-09- Principal's Quarters in Kaga IDA / 59880 and Service Delivery Post Open - National 18,291.00 20,565.87 Completed 2019-06-01 2019-07-05 2019-07-05 Quotations Envelope 03 Local Government Area of Restoration & Improvement Borno State BOMCRP/RFB/CW/035/019 / Infrastructure Rehabilitation Under Rehabilitation of Single Stage - One 2020-01- IDA / 59880 and Service Delivery Post Request for Bids Open - National 2,465,483.00 0.00 Implementat 2019-05-15 2019-05-20 2019-06-19 2019-07-03 2019-07-17 Comprehensive Health Center Envelope 13 Restoration & Improvement ion in (CHC) in 15 LGAs NG-BORNO MCRP-58394-CW- Infrastructure Rehabilitation RFQ / Construction Of 12-No Request for Single Stage - One 2020-04- IDA / 59880 and Service Delivery Post Open - National 133,137.00 59,741.05 Completed 2019-08-11 2019-10-06 2019-07-05 Vip Toilets Mafa (4), Askira- Quotations Envelope 03 Restoration & Improvement Uba (4), Monguno (4) (3LOTS) NG-BORNO MCRP-58024-CW- RFQ / Reconstruction Of 18- Infrastructure Rehabilitation No. Double Classroom Blocks Request for Single Stage - One 2019-05- IDA / 59880 and Service Delivery Post Open - National 453,235.00 771,542.71 Completed 2018-10-02 2018-11-27 2019-07-26 in Bama and Mafa Local Quotations Envelope 26 Restoration & Improvement Government Areas of Borno State Infrastructure Rehabilitation Pending BOMCRP/RFB/CW/002/019 / Single Stage - One 2020-03- IDA / 59880 and Service Delivery Post Request for Bids Open - National 902,111.00 0.00 Implementat 2019-09-12 2019-09-17 2019-10-17 2019-10-31 2019-11-14 Rehabilitation of Biu bridge Envelope 13 Restoration & Improvement ion BOMCRP/RFB/CW/004/019 / Infrastructure Rehabilitation Single Stage - One 2021-04- Rehabilitation of 66KM IDA / 59880 and Service Delivery Prior Request for Bids Open - National 9,785,153.00 0.00 Canceled 2019-08-05 2020-01-22 2019-08-10 2020-01-29 2019-09-09 2020-03-03 2019-09-23 2019-10-07 Envelope 07 Maiduguri to Bama Road Restoration & Improvement NG-BORNO MCRP-52157-CW- Infrastructure Rehabilitation RFB / Rehabilitation of Request for Single Stage - One 2019-05- IDA / 59880 and Service Delivery Post Open - National 2,295,082.00 645,978.75 Completed 2018-09-17 2018-11-12 2019-06-27 Community Resource Centres Quotations Envelope 11 Restoration & Improvement in Borno State NG-BORNO MCRP-130200- Infrastructure Rehabilitation Pending CW-RFQ / Construction of 15- Request for Single Stage - One 2019-12- IDA / 59880 and Service Delivery Post Limited 590,164.00 0.00 Implementat 2019-09-20 2019-10-12 No. Double Classroom Block Quotations Envelope 11 Restoration & Improvement ion Dikwa NG-BORNO MCRP-130203- Infrastructure Rehabilitation Pending CW-RFQ / Construction of 20- Request for Single Stage - One 2019-12- IDA / 59880 and Service Delivery Post Limited 393,443.00 0.00 Implementat 2019-09-22 2019-10-14 No.Double Classroom Block at Quotations Envelope 13 Restoration & Improvement ion Kukawa NG-BORNO MCRP-130206- Infrastructure Rehabilitation Pending CW-RFQ / Renovation of 20- Request for Single Stage - One 2019-12- IDA / 59880 and Service Delivery Post Limited 327,869.00 0.00 Implementat 2019-09-18 2019-10-10 No. 20 Double Classroom Quotations Envelope 09 Restoration & Improvement ion Block at Abadam NG-BORNO MCRP-130211- Infrastructure Rehabilitation Pending CW-RFQ / Rehabilitation of 8 Request for Single Stage - One 2019-12- IDA / 59880 and Service Delivery Post Limited 262,295.00 0.00 Implementat 2019-09-21 2019-10-13 Blocks of Laboratories at Quotations Envelope 12 Restoration & Improvement ion Umar Ibn Ibrahim College Bama NG-BORNO MCRP-130217- Infrastructure Rehabilitation CW-RFQ / Rehabilitation of Request for Single Stage - One 2019-12- IDA / 59880 and Service Delivery Post Limited 131,148.00 76,005.59 Completed 2019-09-25 2019-06-03 2019-10-18 2019-06-20 Library at Umar Ibn Ibrahim Quotations Envelope 17 Restoration & Improvement College Bama NG-BORNO MCRP-130219- CW-RFQ / Construction of Infrastructure Rehabilitation Pending Request for Single Stage - One 2019-12- Solar Powered Boreholes IDA / 59880 and Service Delivery Post Limited 98,361.00 0.00 Implementat 2019-09-29 2019-10-21 Quotations Envelope 20 (2No.) at Umar Ibn Ibrahim Restoration & Improvement ion College Bama Page 2 NG-BORNO MCRP-130225- Infrastructure Rehabilitation Pending Request for Single Stage - One 2019-12- CW-RFQ / Rehabilitation of 1 IDA / 59880 and Service Delivery Post Limited 492,243.00 0.00 Implementat 2019-09-29 2019-10-21 Quotations Envelope 20 of 3 General Hospital Restoration & Improvement ion NG-BORNO MCRP-130234- Infrastructure Rehabilitation CW-RFQ / Supply of Medical Request for Single Stage - One 2019-11- IDA / 59880 and Service Delivery Post Limited 590,164.00 521,591.33 Completed 2019-09-19 2019-07-12 2019-10-11 2019-08-01 Equipment to 3 General Quotations Envelope 10 Restoration & Improvement Hospitals NG-BORNO MCRP-130253- CW-RFQ / Rehabilitation of Infrastructure Rehabilitation Pending Comprehensive Health Care Request for Single Stage - One 2019-12- IDA / 59880 and Service Delivery Post Limited 79,051.00 0.00 Implementat 2019-09-27 2019-10-20 Center (CivilWorks, Solar Quotations Envelope 19 Restoration & Improvement ion Borehole, Fence & Security Post) at CHC Izge, Gwoza NG-BORNO MCRP-133224- Infrastructure Rehabilitation Request for Single Stage - One 2020-01- CW-RFQ / Rehabilitation of IDA / 59880 and Service Delivery Post Limited 196,721.00 56,074.13 Completed 2019-11-06 2020-07-03 2019-11-28 2020-07-24 Quotations Envelope 27 Court Building Restoration & Improvement NG-BORNO MCRP-133225- Infrastructure Rehabilitation CW-RFQ / Rehabilitation of Request for Single Stage - One 2020-01- IDA / 59880 and Service Delivery Post Limited 721,311.00 264,975.56 Completed 2019-10-13 2019-10-04 2019-11-04 2019-10-24 Traditional Rulers Building (11 Quotations Envelope 03 Restoration & Improvement LGAs) NG-BORNO MCRP-133227- Infrastructure Rehabilitation Pending CW-RFQ / Construction of Request for Single Stage - One 2020-01- IDA / 59880 and Service Delivery Post Limited 140,984.00 0.00 Implementat 2019-10-17 2019-11-09 New hand Pumps Water Quotations Envelope 08 Restoration & Improvement ion Sources NG-BORNO MCRP-133228- Infrastructure Rehabilitation Pending CW-RFQ / Construction of Request for Single Stage - One 2020-01- IDA / 59880 and Service Delivery Post Limited 390,760.00 0.00 Implementat 2019-10-24 2019-11-15 Sanitation Facilities in 21 Quotations Envelope 14 Restoration & Improvement ion LGAs NG-BORNO MCRP-133229- Infrastructure Rehabilitation Pending CW-RFQ / Establishment of Request for Single Stage - One 2020-01- IDA / 59880 and Service Delivery Post Limited 447,835.00 0.00 Implementat 2019-11-02 2019-11-23 Sanitation Facilities across Quotations Envelope 22 Restoration & Improvement ion Host Communities in 11 LGAs NG-BORNO MCRP-133230- Infrastructure Rehabilitation CW-RFQ / Rehabilitation of Request for Single Stage - One 2020-01- IDA / 59880 and Service Delivery Post Limited 129,262.00 56,840.24 Completed 2019-10-30 2019-12-06 2019-11-21 2019-12-27 Existing Non-Functional Quotations Envelope 20 Restoration & Improvement Boreholes BORNO/MCRP/CW/RFQ/100/ 20 / Construction of Double Infrastructure Rehabilitation Pending Request for Single Stage - One 2020-10- Classroom Blocks at IDA / 59880 and Service Delivery Post Limited 175,419.00 0.00 Implementat 2020-04-07 2020-04-28 Quotations Envelope 25 Askira/Uba Local Government Restoration & Improvement ion Area of Borno State BORNO/MCRP/CW/RFQ/101/ 20 / Construction of Double Infrastructure Rehabilitation Pending Request for Single Stage - One 2020-10- Classroom Blocks at Banki IDA / 59880 and Service Delivery Post Limited 97,455.00 0.00 Implementat 2020-04-08 2020-04-29 Quotations Envelope 26 Town of Bama Local Restoration & Improvement ion Government Area BORNO/MCRP/CW/RFQ/103/ 20 / Construction of Double Infrastructure Rehabilitation Pending Request for Single Stage - One 2020-10- Classroom Blocks at Damasak IDA / 59880 and Service Delivery Post Limited 191,803.00 0.00 Implementat 2020-04-08 2020-04-29 Quotations Envelope 26 Town of Mobbar Local Restoration & Improvement ion Government Area BORNO/MCRP/CW/RFQ/104/ 20 / Construction of Double Infrastructure Rehabilitation Request for Single Stage - One 2020-10- Classroom Blocks at Kukawa IDA / 59880 and Service Delivery Post Limited 393,443.00 381,946.31 Signed 2020-04-08 2020-07-27 2020-04-29 2020-08-13 Quotations Envelope 26 Local Government Area of Restoration & Improvement Borno State BORNO/MCRP/CW/RFQ/105/ 20 / Construction of Double Infrastructure Rehabilitation Pending Request for Single Stage - One 2020-10- Classroom Blocks at Ajiri IDA / 59880 and Service Delivery Post Limited 78,430.00 0.00 Implementat 2020-04-11 2020-05-02 Quotations Envelope 29 Community of Mafa Local Restoration & Improvement ion Government Area BORNO/MCRP/CW/RFQ/106/ Infrastructure Rehabilitation Pending 20 / Renovation of Double Request for Single Stage - One 2020-10- IDA / 59880 and Service Delivery Post Limited 327,869.00 0.00 Implementat 2020-04-10 2020-05-01 Classroom Blocks at Abadam Quotations Envelope 28 Restoration & Improvement ion Local Government Area BORNO/MCRP/CW/RFQ/107/ 20 / Renovation of Double Infrastructure Rehabilitation Pending Request for Single Stage - One 2020-10- Classroom Blocks at Bama IDA / 59880 and Service Delivery Post Limited 132,787.00 0.00 Implementat 2020-04-12 2020-05-03 Quotations Envelope 30 Town, Bama Local Restoration & Improvement ion Government Area of Borno State BORNO/MCRP/CW/RFQ/109 / Renovation of Educational Infrastructure Rehabilitation Request for Single Stage - One 2020-11- Office at Damboa Local IDA / 59880 and Service Delivery Post Limited 18,033.00 92,528.54 Completed 2020-04-19 2019-07-17 2020-05-10 2019-06-25 Quotations Envelope 06 Government Area of Borno Restoration & Improvement State BORNO/MCRP/CW/RFQ/110/ Infrastructure Rehabilitation Pending 20 / Renovation of Request for Single Stage - One 2020-11- IDA / 59880 and Service Delivery Post Limited 18,033.00 0.00 Implementat 2020-04-18 2020-05-09 Educational Office Kaga Local Quotations Envelope 05 Restoration & Improvement ion Government Area of Borno State BORNO/MCRP/CW/RFQ/111 / Rehabilitation of Primary Infrastructure Rehabilitation Request for Single Stage - One 2020-11- Healthcare Centers in selected IDA / 59880 and Service Delivery Post Limited 1,225,870.00 82,775.24 Completed 2020-04-23 2019-09-02 2020-05-14 2019-09-23 Quotations Envelope 10 Local Government Areas of Restoration & Improvement Borno State BORNO/MCRP/CW/RFQ/112/ 20 / Rehabilitation of Court Infrastructure Rehabilitation Buildings at Bama, Gwoza, Request for Single Stage - One 2020-12- IDA / 59880 and Service Delivery Post Limited 196,721.00 83,961.86 Completed 2020-05-28 2020-07-06 2020-06-18 2020-07-24 Dikwa and Mobbar Local Quotations Envelope 15 Restoration & Improvement Government Areas of Borno State Page 3 BORNO/MCRP/CW/RFQ/113/ 20 / Rehabilitation of Infrastructure Rehabilitation Request for Single Stage - One 2020-12- Traditional Rulers Building in IDA / 59880 and Service Delivery Post Limited 721,312.00 69,919.00 Completed 2020-05-14 2020-02-18 2020-06-04 2020-03-10 Quotations Envelope 01 selected Local Government Restoration & Improvement Areas of Borno State BORNO/MCRP/CW/RFQ/116/ 20 / Rehabilitation of existing Infrastructure Rehabilitation Request for Single Stage - One 2020-09- Non-Functional Boreholes in IDA / 59880 and Service Delivery Post Limited 129,262.00 93,386.86 Completed 2020-06-04 2020-09-29 2020-06-25 2020-10-19 Quotations Envelope 23 selected Local Government Restoration & Improvement Areas of Borno State BORNO/MCRP/CW/RFQ/118/ Infrastructure Rehabilitation 20 / Reconstruction of 60 Request for Single Stage - One 1,520,034.1 2020-11- IDA / 59880 and Service Delivery Post Limited 1,972,386.00 Completed 2020-05-09 2020-12-20 2020-05-30 2020-01-09 Nos. Double Classroom Blocks Quotations Envelope 4 26 Restoration & Improvement in Jere Local Government Area BORNO/MCRP/CW/RFQ/119/ 20 / Reconstruction of 30 Infrastructure Rehabilitation Nos. Double Classroom Blocks Request for Single Stage - One 2020-12- IDA / 59880 and Service Delivery Post Limited 986,193.00 396,674.96 Signed 2020-05-15 2020-07-07 2020-06-05 2020-07-28 in Pulka, Gwoza Local Quotations Envelope 02 Restoration & Improvement Government Area of Borno State BORNO/MCRP/CW/RFQ/120/ 20 / Reconstruction of Infrastructure Rehabilitation Perimeter Fence, Gate and Request for Single Stage - One 2020-12- IDA / 59880 and Service Delivery Post Limited 821,827.00 761,174.22 Completed 2020-05-17 2020-03-06 2020-06-07 2020-03-27 Generators Houses at Borno Quotations Envelope 04 Restoration & Improvement State College of Basic Studies (BOCOBS) Bama BORNO/MCRP/CW/RFQ/126/ 20 / Establishment of Infrastructure Rehabilitation Request for Single Stage - One 1,364,155.1 2020-12- Vocational Training Center in IDA / 59880 and Service Delivery Post Limited 1,700,000.00 Completed 2020-05-31 2020-01-07 2020-06-21 2020-01-27 Quotations Envelope 3 18 Monguno Local Government Restoration & Improvement Area of Borno State BORNO/MCRP/CW/RFQ/121 / Establishment of Water Infrastructure Rehabilitation Request for Single Stage - One 2020-12- Works Facilities at Pulka, IDA / 59880 and Service Delivery Post Limited 842,209.00 353,549.05 Completed 2020-05-21 2019-12-23 2020-06-11 2020-01-13 Quotations Envelope 08 Gwoza Local Government Area Restoration & Improvement of Borno State BORNO/MCRP/CW/RFQ/108/ 20 / Construction of Infrastructure Rehabilitation Educational Office at Kukawa, Request for Single Stage - One 2020-11- IDA / 59880 and Service Delivery Post Limited 193,259.00 134,120.37 Completed 2020-04-19 2020-07-09 2020-05-10 2020-07-29 Hawul and Konduga Local Quotations Envelope 06 Restoration & Improvement Government Areas of Borno State BORNO/MCRP/CW/RFQ/117/ 20 / Rehabilitation of Roads Infrastructure Rehabilitation Request for Single Stage - One 4,745,074.6 2020-11- in Jiddari Polo ward of Jere IDA / 59880 and Service Delivery Post Limited 1,981,391.00 Signed 2020-04-15 2020-02-25 2020-05-06 2020-03-13 Quotations Envelope 2 02 Local Government Area of Restoration & Improvement Borno State BORN/MCRP/CW/RFQ/114/20 / Construction of Sanitation Infrastructure Rehabilitation Pending Request for Single Stage - One 2020-12- Facilities in selected Local IDA / 59880 and Service Delivery Post Limited 543,505.00 0.00 Implementat 2020-05-15 2020-06-05 Quotations Envelope 02 Government Areas of Borno Restoration & Improvement ion State BORNO/MCRP/CW/RFQ/115,2 0 / Establishment of Infrastructure Rehabilitation Sanitation Facilities across Request for Single Stage - One 2020-12- IDA / 59880 and Service Delivery Post Limited 290,760.00 80,455.59 Completed 2020-05-20 2020-01-07 2020-06-10 2020-01-27 Host Communities in selected Quotations Envelope 07 Restoration & Improvement Local Government Areas of Borno State BORNO/MCRP/CW/RFB/122/2 0 / Rehabilitation of 4.197km Infrastructure Rehabilitation Pending Single Stage - One 2021-08- Monguno Township Roads, IDA / 59880 and Service Delivery Prior Request for Bids Limited 5,215,385.00 0.00 Implementat 2020-10-15 2020-10-20 2020-12-01 2020-12-31 2021-02-04 Envelope 03 Monguno Local Government Restoration & Improvement ion Area of Borno State BOMCRP/CW/RFB/05/2020 / Infrastructure Rehabilitation Single Stage - One 13,442,899.6 2022-09- Rehsbilitation of 66Km IDA / 59880 and Service Delivery Prior Request for Bids Limited 0.00 Canceled 2020-08-17 2020-08-21 2020-08-22 2020-09-21 2020-09-22 2020-10-02 Envelope 0 22 Maiduguri - Bama Road Restoration & Improvement BOMCRP/CW/DIR/001/20 / Infrastructure Rehabilitation 13,442,899.6 12,717,711. 2023-04- Rehabilitation of 66km IDA / 59880 and Service Delivery Prior Direct Selection Direct Signed 2020-10-02 2020-09-30 2020-10-04 2020-10-02 2020-10-17 2020-12-24 0 49 20 Maiduguri-Bama Road Restoration & Improvement BOMCRP/RFB/CW/003/019 / Infrastructure Rehabilitation Construction of Galameri- Single Stage - One 2020-02- IDA / 59880 and Service Delivery Post Request for Bids Open - National 1,104,626.00 0.00 Canceled 2019-08-05 2021-01-13 2019-08-10 2019-09-09 2019-09-23 2019-10-07 Dusuman-Zabarmari- Envelope 05 Restoration & Improvement Gungulong Feeder Road BOMCRP/CW/DIR/002/2020 Request for / REHABILITATION OF 4.17km Infrastructure Rehabilitation Quotations - Small Pending 2022-11- MONGUNO TOWNSHIP ROAD, IDA / 59880 and Service Delivery Post Direct Selection Direct Works 5,215,385.00 0.00 Implementat 2021-05-03 2021-05-05 2021-05-15 13 IN MONGUNO LOCAL Restoration & Improvement (Emergency) SPD - ion GOVERNMENT AREA Non Competitive GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-BORNO MCRP-52158-GO- RFQ / Supply and Installation of Solar Inverters in 15 Primary Health Cares in Infrastructure Rehabilitation Pending Request for Single Stage - One (Ngala, Nganzai Kukawa, Biu, IDA / 59880 and Service Delivery Post Open - National 262,295.00 0.00 Implementati 2019-02-24 2019-04-21 2019-10-18 Quotations Envelope Konduga, Gubio, Askira/Uba, Restoration & Improvement on Guzamala, Bama, Jere, Marte, Mobbar, Dikwa, Mafa, Abadam) Page 4 NG-BORNO MCRP-58049-GO- RFQ / Suppy of Computers Infrastructure Rehabilitation Under and other accessories to the Request for Single Stage - One IDA / 59880 and Service Delivery Post Open - National 81,967.00 0.00 Implementati 2019-03-09 2019-05-04 2019-10-31 Borno State Library , Quotations Envelope Restoration & Improvement on Maiduguri and Umar Ibn ibrahim college Bama NG-BORNO MCRP-55919-GO- RFB / Supply of non food item Strengthening Peace Building, Request for Single Stage - One Kits for household support for IDA / 59880 Post Open - National 2,216,691.00 414,196.65 Completed 2018-08-29 2018-10-24 2019-02-05 2019-04-22 2018-10-24 Stability and Social Cohesion Quotations Envelope 9 Local Government Areas of Borno State NG-BORNO MCRP-58782-GO- RFB / Supply of Agricultural Support kits with Seeds, Strengthening Peace Building, Request for Single Stage - One Fertilizers and Small Work IDA / 59880 Post Open - National 681,729.00 190,176.53 Completed 2018-08-29 2018-10-24 2018-09-05 2019-04-22 2018-09-10 Stability and Social Cohesion Quotations Envelope Farm Tools for 9 Local Government Areas of Borno State NG-BORNO MCRP-55925-GO- RFB / Supply of Small Animals Strengthening Peace Building, Request for Single Stage - One IDA / 59880 Post Open - National 788,935.00 352,563.75 Completed 2018-08-29 2018-10-24 2018-10-15 2019-04-22 2018-10-30 for 9 Local Government Areas Stability and Social Cohesion Quotations Envelope of Borno State NG-BORNO MCRP-58006-GO- RFB / Supply of Non- Strengthening Peace Building, Request for Single Stage - One agricultural Livelihood Kits to IDA / 59880 Post Open - National 758,525.00 487,381.13 Completed 2018-08-29 2018-10-24 2018-10-11 2019-04-22 2018-10-17 Stability and Social Cohesion Quotations Envelope 9 Local Government Areas of Borno State NG-BORNO MCRP-58872-GO- RFQ / Books and other Infrastructure Rehabilitation Pending Request for Single Stage - One learning Materials including IDA / 59880 and Service Delivery Post Open - National 131,147.54 0.00 Implementati 2019-03-09 2019-05-04 2019-10-31 Quotations Envelope elibrary in the Borno State Restoration & Improvement on library NG-BORNO MCRP-58404-GO- RFB / Procurement of 2 Technical Assistance and Single Stage - One IDA / 59880 Post Request for Bids Open - National 448,525.00 0.00 Canceled 2018-04-16 2019-02-06 2018-04-21 2018-06-02 2018-07-18 2018-07-02 2019-02-06 2018-08-06 2019-02-02 Toyota Prado Jeep, 3 Toyota Project Management Support Envelope Hilux, 1 Toyota Corolla NG-BORNO MCRP-58381-GO- RFQ / Procurement of 100KVA Technical Assistance and Request for Single Stage - One IDA / 59880 Post Open - National 42,623.00 0.00 Canceled 2018-04-14 2018-06-09 2018-12-06 sound proof Generator, Project Management Support Quotations Envelope 10KVA Inverter System NG-BORNO MCRP-58351-GO- RFB / Supply of broadcasting equipment to selected Radio Station for content Strengthening Peace Building, Single Stage - One dissemination towards IDA / 59880 Post Request for Bids Open - National 262,295.00 0.00 Canceled 2018-04-20 2018-04-25 2018-06-06 2018-07-06 2018-08-10 2019-02-06 Stability and Social Cohesion Envelope deradicalisation, grievance redress and peacebuilding media outreach campaign to target LGAs. NG-BORNO MCRP-58380-GO- Technical Assistance and Request for Single Stage - One RFQ / Procurement of 1 Video IDA / 59880 Post Open - National 7,000.00 0.00 Canceled 2018-04-18 2018-06-13 2018-12-10 Project Management Support Quotations Envelope Camera, 2 DLSR Cameras, NG-BORNO MCRP-52708-GO- RFB / Furniture for Library/ Infrastructure Rehabilitation Offices in the Borno State Single Stage - Two IDA / 59880 and Service Delivery Post Request for Bids Open - National 491,803.00 0.00 Canceled 2019-07-16 2019-07-21 2019-09-01 2019-11-14 2019-12-19 2020-06-16 Library and Furniture for 15 Envelope Restoration & Improvement blocks of classrooms in Umar Ibn ibrahim college Bama NG-BORNO MCRP-58807-GO- RFQ / Rehabilitation of Comprehensive Healthcare Infrastructure Rehabilitation Center (Civil Works, Solar Request for Single Stage - One IDA / 59880 and Service Delivery Post Open - National 79,051.00 67,027.47 Completed 2018-11-05 2018-12-31 2019-04-29 2019-06-29 2019-12-05 Borehole, Fence & Security Quotations Envelope Restoration & Improvement Post) in Izge town of Gwoza Local Government Area of Borno State. BOMCRP/RFQ/CW/034/019 / Infrastructure Rehabilitation Pending Supply of Medical equipment Request for Single Stage - One IDA / 59880 and Service Delivery Post Limited 591,716.00 0.00 Implementati 2019-03-02 2019-04-06 2019-04-20 to 1 of 3 (Lassa) General Quotations Envelope Restoration & Improvement on Hospitals NG-BORNO MCRP-58008-GO- RFQ / Statewide sponsorship for Radio Programming for Peacebuilding Campaign/Content on Strengthening Peace Building, Request for Single Stage - One IDA / 59880 Post Open - National 475,410.00 0.00 Canceled 2018-10-24 2018-12-19 2019-06-17 deradicalisation, grievance Stability and Social Cohesion Quotations Envelope redress and cultural/religious tolerance in 27 Local Government Areas of Borno State. NG-BORNO MCRP-130187- Infrastructure Rehabilitation Request for Single Stage - One GO-RFQ / Supply of Teaching IDA / 59880 and Service Delivery Post Limited 1,154,098.00 967,362.59 Completed 2019-09-11 2019-06-04 2019-10-02 2019-06-24 2019-12-31 2019-07-03 Quotations Envelope Materials (22 Communities) Restoration & Improvement NG-BORNO MCRP-130189- Infrastructure Rehabilitation Pending Request for Single Stage - One GO-RFQ / Supply of IDA / 59880 and Service Delivery Post Limited 432,787.00 0.00 Implementati 2019-09-14 2019-10-06 2020-01-04 Quotations Envelope Laboratory Equipment Restoration & Improvement on NG-BORNO MCRP-130192- Infrastructure Rehabilitation Request for Single Stage - One GO-RFQ / Supply of First aid IDA / 59880 and Service Delivery Post Limited 144,262.00 133,307.89 Completed 2019-09-14 2019-12-27 2019-10-05 2020-01-17 2019-12-04 2020-02-18 Quotations Envelope Kits Restoration & Improvement NG-BORNO MCRP-130193- Infrastructure Rehabilitation Request for Single Stage - One GO-RFQ / Procurement of IDA / 59880 and Service Delivery Post Limited 442,623.00 401,290.82 Completed 2019-09-18 2019-07-05 2019-10-11 2019-07-26 2019-12-10 2020-02-20 Quotations Envelope Furniture Restoration & Improvement NG-BORNO MCRP-130209- Infrastructure Rehabilitation GO-RFQ / Furniture for 15 Request for Single Stage - One IDA / 59880 and Service Delivery Post Limited 245,902.00 479,285.03 Completed 2019-09-22 2020-01-07 2019-10-14 2020-01-29 2019-12-13 2020-03-20 Blocks of Classrooms at Umar Quotations Envelope Restoration & Improvement Ibn Ibrahim College Bama Page 5 NG-BORNO MCRP-130215- GO-RFQ / Supply of Infrastructure Rehabilitation Pending Request for Single Stage - One Computers and other IDA / 59880 and Service Delivery Post Limited 40,984.00 0.00 Implementati 2019-09-25 2019-10-17 2019-11-16 Quotations Envelope accessories to Umar Ibn Restoration & Improvement on Ibrahim College Bama NG-BORNO MCRP-130227- Infrastructure Rehabilitation GO-RFQ / Provisions for Solar Request for Single Stage - One IDA / 59880 and Service Delivery Post Limited 604,980.00 544,223.65 Completed 2019-09-26 2019-07-16 2019-10-17 2019-08-05 2019-11-26 2019-08-22 electrification to 3 General Quotations Envelope Restoration & Improvement Hospitals NG-BORNO MCRP-130243- Infrastructure Rehabilitation GO-RFQ / Supply of Essential Request for Single Stage - One IDA / 59880 and Service Delivery Post Limited 472,131.00 405,142.20 Completed 2019-09-28 2019-07-29 2019-10-21 2019-08-15 2019-11-20 2019-09-09 Drugs/Medical Consumables Quotations Envelope Restoration & Improvement to 3 General Hospitals NG-BORNO MCRP-133078- Infrastructure Rehabilitation Pending GO-RFQ / Installation of Solar Request for Single Stage - One IDA / 59880 and Service Delivery Post Limited 13,115.00 0.00 Implementati 2019-10-02 2019-10-24 2019-12-03 Inverters at CHC Izge, Gwoza Quotations Envelope Restoration & Improvement on LGA NG-BORNO MCRP-133079- Infrastructure Rehabilitation GO-RFQ / Supply of Medical Request for Single Stage - One IDA / 59880 and Service Delivery Post Limited 49,180.00 48,000.86 Completed 2019-09-29 2020-06-24 2019-10-21 2020-07-14 2019-12-20 2020-08-06 equipment to Izge CHC, Quotations Envelope Restoration & Improvement Gwoza LGA NG-BORNO MCRP-133085- Infrastructure Rehabilitation Pending GO-RFQ / Supply of Essential Request for Single Stage - One IDA / 59880 and Service Delivery Post Limited 78,689.00 0.00 Implementati 2019-09-29 2019-10-21 2019-12-20 Drugs/Medical Consumables Quotations Envelope Restoration & Improvement on to CHC Izge,Gwoza LGA NG-BORNO MCRP-133088- GO-RFQ / Supply of Medical Infrastructure Rehabilitation Pending equipment to 3 Request for Single Stage - One IDA / 59880 and Service Delivery Post Limited 196,721.00 0.00 Implementati 2019-09-25 2019-10-16 2019-11-30 Comprehensive Health Quotations Envelope Restoration & Improvement on Centers (Hawul, Mobbar and Damboa) NG-BORNO MCRP-133090- GO-RFQ / Supply Essential Infrastructure Rehabilitation Request for Single Stage - One Drugs/Medical Consumables IDA / 59880 and Service Delivery Post Limited 157,377.00 179,495.82 Completed 2019-10-06 2020-03-04 2019-10-28 2020-03-24 2019-12-12 2020-04-08 Quotations Envelope to 3 Comprehensive Health Restoration & Improvement Centers NG-BORNO MCRP-133095- Infrastructure Rehabilitation Request for Single Stage - One GO-RFQ / Supply of Medical IDA / 59880 and Service Delivery Post Limited 184,426.00 636,589.86 Completed 2019-10-09 2020-07-10 2019-10-31 2020-08-03 2019-12-30 2020-08-20 Quotations Envelope Equipment to 15 PHCs Restoration & Improvement NG-BORNO MCRP-133221- Infrastructure Rehabilitation Request for Single Stage - One GO-RFQ / Supply of Essential IDA / 59880 and Service Delivery Post Limited 147,541.00 94,876.36 Completed 2019-10-13 2020-10-13 2019-11-04 2020-11-02 2020-01-03 2020-11-19 Quotations Envelope Drugs to 15 PHCs Restoration & Improvement NG-BORNO MCRP-133222- Infrastructure Rehabilitation Pending Request for Single Stage - One GO-RFQ / Installation of Solar IDA / 59880 and Service Delivery Post Limited 49,180.00 0.00 Implementati 2019-10-02 2019-10-24 2019-12-23 Quotations Envelope Inverters to 15 PHCs Restoration & Improvement on BORNO/MCRP/GO/RFQ/50/20 Infrastructure Rehabilitation Request for Single Stage - One / Procurement of Furniture for IDA / 59880 and Service Delivery Post Limited 245,902.00 320,175.05 Completed 2020-04-12 2020-02-20 2020-05-02 2020-03-10 2020-06-01 2020-04-02 Quotations Envelope Library/Offices in Maiduguri Restoration & Improvement BORNO/MCRP/GO/RFQ/51/20 / Procurement of Books and Infrastructure Rehabilitation Pending Request for Single Stage - One other learning materials IDA / 59880 and Service Delivery Post Limited 131,148.00 0.00 Implementati 2020-04-08 2020-04-29 2020-05-29 Quotations Envelope including E-Library at Restoration & Improvement on Maiduguri, Borno State BORNO/MCRP/GO/RFQ/53/20 Infrastructure Rehabilitation Pending Request for Single Stage - One / Procurement of Computers IDA / 59880 and Service Delivery Post Limited 40,984.00 0.00 Implementati 2020-04-15 2020-05-06 2020-06-15 Quotations Envelope and accessories Restoration & Improvement on BORNO/MCRP/GO/RFQ/54/20 Infrastructure Rehabilitation Pending / Installation of Solar Lighting Request for Single Stage - One IDA / 59880 and Service Delivery Post Limited 12,020.00 0.00 Implementati 2020-04-17 2020-05-08 2020-06-27 System for Library at Quotations Envelope Restoration & Improvement on Maiduguri Borno State BORNO/MCRP/GO/RFQ/55/20 / Supply of Medical Infrastructure Rehabilitation Request for Single Stage - One Equipment to Primary IDA / 59880 and Service Delivery Post Limited 231,982.00 284,337.26 Completed 2020-05-02 2020-09-30 2020-05-23 2020-10-20 2020-07-22 2020-11-06 Quotations Envelope Healthcare Centers in selected Restoration & Improvement Local Government Areas of Borno State BORNO/MCRP/GO/RFQ/56/20 / Supply of Essential Drugs to Infrastructure Rehabilitation Request for Single Stage - One Primary Healthcare Centers in IDA / 59880 and Service Delivery Post Limited 132,787.00 427,444.16 Completed 2020-04-30 2019-11-01 2020-05-21 2019-11-22 2020-06-30 2019-12-17 Quotations Envelope selected Local Government Restoration & Improvement Areas of Borno State BORNO/MCRP/GO/RFQ/57/20 / Installation of Solar Inverters Infrastructure Rehabilitation Pending Request for Single Stage - One in Primary Healthcare Centers IDA / 59880 and Service Delivery Post Limited 147,541.00 0.00 Implementati 2020-04-30 2020-05-20 2020-06-29 Quotations Envelope in selected Local Government Restoration & Improvement on Areas of Borno State BORNO/MCRP/GO/RFQ/59/20 Infrastructure Rehabilitation / Provision of Instructional Request for Single Stage - One IDA / 59880 and Service Delivery Post Limited 493,096.00 782,803.01 Completed 2020-05-28 2020-12-11 2020-06-18 2020-12-31 2020-12-15 2021-01-15 Materials to Schools in Borno Quotations Envelope Restoration & Improvement State BORNO/MCRP/GO/RFQ/61/20 Infrastructure Rehabilitation Request for Single Stage - One / Provision of Furniture for IDA / 59880 and Service Delivery Post Limited 657,462.00 120,500.42 Completed 2020-05-31 2020-08-11 2020-06-21 2020-09-01 2020-12-18 2020-09-18 Quotations Envelope Schools in Borno State Restoration & Improvement BORNO/MCRP/GO/RFQ/62/20 Infrastructure Rehabilitation Pending / Provision of Hospital Request for Single Stage - One IDA / 59880 and Service Delivery Post Limited 987,515.00 0.00 Implementati 2020-05-28 2020-06-18 2020-12-15 Equipment for Tertiary Health Quotations Envelope Restoration & Improvement on Center (Borno State University) BORNO/MCRP/GO/RFQ/63/20 Infrastructure Rehabilitation / Provision of Furniture to Request for Single Stage - One IDA / 59880 and Service Delivery Post Limited 500,000.00 623,855.70 Completed 2020-05-28 2020-05-08 2020-06-18 2020-06-01 2020-12-15 2020-06-23 Primary Healthcare Centers in Quotations Envelope Restoration & Improvement Borno State Page 6 BORNO/MCRP/GO/RFQ/58/20 Strengthening Peace Building, Request for Single Stage - One IDA / 59880 Post Limited 2,200,000.00 162,792.85 Completed 2020-04-22 2020-10-27 2020-05-14 2020-11-16 2020-08-12 2020-12-07 / Supply of non Food item Kits Stability and Social Cohesion Quotations Envelope NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-BORNO MCRP-58894-CS- QCBS / Specialized psycho- social support responding to Consultant Strengthening Peace Building, rapid assessment needs/gaps IDA / 59880 Post Qualification Open - National 825,230.00 374,263.02 Completed 2018-09-21 2019-07-01 2018-10-12 2019-10-17 2018-11-25 2019-07-03 2018-12-25 2019-07-23 2019-01-29 2019-07-29 2019-07-28 2019-10-11 Stability and Social Cohesion and pop to intervene in 27 Selection Local Government Areas of Borno State. NG-BORNO MCRP-58895-CS- CQS / Consultancy for the Mobilisation and Organisation Consultant of Civic Education with Strengthening Peace Building, Pending IDA / 59880 Post Qualification Open - National 442,623.00 0.00 2018-09-21 2018-10-12 2018-11-25 2018-12-25 2019-01-29 2019-07-28 Cultural and Recreational Stability and Social Cohesion Implementation Selection activities with 27 Local Government Areas of Borno State NG-BORNO MCRP-53660-CS- CQS / Consultancy for Sensitization, Community Consultant Mobilization and formation of Strengthening Peace Building, Under IDA / 59880 Post Qualification Open - National 531,148.00 0.00 2018-09-21 2018-10-12 2018-11-25 2018-12-25 2019-01-29 2019-07-28 peace groups within affected Stability and Social Cohesion Implementation Selection Communities in 7 Local Government Areas of Borno State NG-BORNO MCRP-58889-CS- CQS / Capacity Building for 10 Consultant Local Government Emergency Strengthening Peace Building, IDA / 59880 Post Qualification Open - National 203,279.00 0.00 Canceled 2019-04-18 2019-04-18 2019-04-18 2019-04-18 2019-04-18 2019-04-18 Management Responders in Stability and Social Cohesion Selection Displaced and Transitional Local Government Officials NG-BORNO MCRP-58864-CS- Consultant CQS / Training for officials of Strengthening Peace Building, IDA / 59880 Post Qualification Open - National 16,393.00 0.00 Canceled 2018-06-11 2018-07-02 2018-08-15 2018-09-14 2018-10-19 2019-04-17 relevant State MDAs on Stability and Social Cohesion Selection effective approaches to UASC NG-BORNO MCRP-58382-CS- CQS / Consultancy to provide Consultant Capacity building of LG Strengthening Peace Building, IDA / 59880 Post Qualification Open - National 88,525.00 0.00 Canceled 2018-07-02 2018-07-23 2018-09-05 2018-10-05 2018-11-09 2019-05-08 Officers for economic Stability and Social Cohesion Selection planning and policy development NG-BORNO MCRP-58040-CS- CQS / Capacity building of LG Consultant Officers for local governments Strengthening Peace Building, IDA / 59880 Post Qualification Open - National 88,525.00 0.00 Canceled 2018-05-25 2018-06-15 2018-07-29 2018-08-28 2018-10-02 2019-03-31 on budget planning and Stability and Social Cohesion Selection execution, monitoring and reporting NG-BORNO MCRP-58752-CS- Consultant CQS / Consultancy for Post- Strengthening Peace Building, IDA / 59880 Post Qualification Open - National 147,541.00 0.00 Canceled 2018-04-02 2018-04-23 2018-06-06 2018-07-06 2018-08-10 2019-02-06 Conflict Transitional Justice Stability and Social Cohesion Selection and Accountability NG-BORNO MCRP-53657-CS- CQS / Sensitization, training (especially on Identification, Documentation, Tracing and Consultant Reunification and follow up) Strengthening Peace Building, IDA / 59880 Post Qualification Open - National 73,770.00 0.00 Canceled 2018-06-11 2018-07-02 2018-08-15 2018-09-14 2018-10-19 2019-04-17 and coaching for state and Stability and Social Cohesion Selection non-state partners on case management of UASC (Unaccompanied and Separated Children) NG-BORNO MCRP-58439-CS- Infrastructure Rehabilitation Consultant QCBS / Sensitization and Pending IDA / 59880 and Service Delivery Post Qualification Open - National 524,590.00 0.00 2018-09-10 2018-10-01 2018-11-14 2018-12-14 2019-01-18 2019-07-17 Mobilisation for Health Implementation Restoration & Improvement Selection (Outreach Programs) NG-BORNO MCRP-53655-CS- QCBS / Training of Community Health Workers (CHeWs, VHWs, Midwives) to Infrastructure Rehabilitation Quality And Cost- Under Staff Targeted Health Facilities IDA / 59880 and Service Delivery Post Open - National 531,148.00 0.00 2019-03-18 2019-04-08 2019-05-22 2019-06-19 2019-07-19 2019-08-23 2019-09-27 2020-09-26 Based Selection Implementation (3Nos consultancies across Restoration & Improvement the state. Amount Inclusive of Workshop and per diem payments) NG-BORNO MCRP-57816-CS- CQS / Consultancy for Educational Campaigns, Consultant Mobilization and Sensitization Strengthening Peace Building, IDA / 59880 Post Qualification Open - National 442,623.00 225,180.00 Completed 2018-09-03 2019-02-12 2018-09-24 2018-11-07 2019-02-12 2018-12-07 2019-02-12 2019-01-11 2018-10-16 2019-07-10 2018-12-24 on Mine Actions & Stability and Social Cohesion Selection Unexploded Ordinances in 27 Local Government Areas of Borno State Page 7 NG-BORNO MCRP-73783-CS- CQS / Consultancy for Mediation and Alternate Consultant Strengthening Peace Building, Dispute Resolution Capacity IDA / 59880 Post Qualification Open - National 147,541.00 139,085.49 Completed 2018-11-05 2019-02-12 2018-11-26 2019-01-09 2019-02-12 2019-02-08 2018-10-16 2019-03-15 2018-10-17 2019-09-11 2018-12-03 Stability and Social Cohesion Building for peace groups in Selection 27 Local Govenrment Areas of Borno State BOMCRP/CQS/CS/008/019 / Capacity building of LG Consultant Officers for Strategic Strengthening Peace Building, IDA / 59880 Post Qualification Open - National 22,189.00 37,457.33 Completed 2019-04-09 2019-03-19 2019-04-23 2019-05-03 2019-03-26 2019-05-10 2019-04-15 2019-05-24 2019-04-18 2019-06-07 2019-06-07 Communications (Legislative Stability and Social Cohesion Selection Advocacy, Media relations, Stakeholder Management etc) BOMCRP/CQS/CS/007/019 / Capacity building of LG Consultant Strengthening Peace Building, Under Officers for budget planning, IDA / 59880 Post Qualification Open - National 44,379.00 0.00 2019-04-09 2019-02-22 2019-04-23 2019-05-07 2019-05-14 2019-05-28 2019-06-11 Stability and Social Cohesion Implementation execution, monitoring and Selection reporting BOMCRP/CQS/CS/009/019 / Capacity building for 10 Local Consultant Government Emergency Strengthening Peace Building, IDA / 59880 Post Qualification Open - National 50,953.00 86,180.00 Completed 2019-04-09 2018-09-20 2019-04-23 2019-05-07 2018-10-11 2019-05-14 2018-10-14 2019-05-22 2018-10-17 2019-06-05 2019-01-03 Management Res ponders in Stability and Social Cohesion Selection Displaced and Transitional Local Government Officials BOMCRP/CQS/CS/010/019 / Sensitization, training on identification, Documentation, Consultant Tracing, Reunification, Follow Strengthening Peace Building, IDA / 59880 Post Qualification Open - National 29,586.00 81,257.63 Completed 2019-04-09 2019-08-08 2019-04-23 2019-11-21 2019-05-07 2019-10-14 2019-05-14 2019-09-05 2019-05-28 2019-11-07 2019-06-11 2019-12-09 up and coaching for case Stability and Social Cohesion Selection management of UASC (Unaccompanied and Separated Children) BOMCRP/CQS/CS/033/019 / Identification and training of Village Levels Mechanics and Local area Mechanics in 21 Infrastructure Rehabilitation Consultant Pending LGAs on operation and IDA / 59880 and Service Delivery Post Qualification Open - National 73,964.00 0.00 2019-10-10 2019-10-24 2019-11-14 2019-11-21 2019-12-05 2019-12-19 Implementation maintenance of existing Hand Restoration & Improvement Selection pump and Solar powered Borehole for effective utilization and management NG-BORNO MCRP-73723-CS- CQS / Statewide sponsorship for Radio Programming for Peacebuilding Consultant Campaign/Content on Strengthening Peace Building, IDA / 59880 Post Qualification Open - National 360,782.00 97,154.27 Completed 2019-03-18 2019-05-09 2019-04-01 2019-04-22 2019-04-03 2019-04-29 2019-04-22 2019-05-13 2019-04-25 2019-11-09 2020-04-08 deradicalization, grievance Stability and Social Cohesion Selection redress and cultural/religious tolerance in 27 Local Government Areas of Borno State BOMCRP/CQS/CS/020/019 / Infrastructure Rehabilitation Consultant Under Teacher Training and IDA / 59880 and Service Delivery Post Qualification Open - National 177,515.00 0.00 2019-09-02 2019-10-02 2019-09-16 2019-10-07 2019-10-14 2019-10-28 2019-11-27 Implementation Recertification Restoration & Improvement Selection NG-BORNO MCRP-120946- CS-CQS / Engagement of Infrastructure Rehabilitation Consultant Consultant to Design and IDA / 59880 and Service Delivery Post Qualification Open - National 310,965.63 261,765.85 Completed 2019-09-02 2019-05-13 2019-09-09 2019-10-16 2019-09-18 2019-05-20 2019-09-19 2019-06-04 2019-09-21 2019-06-05 2019-10-21 2019-08-27 Supervise for Borno PCU 66km Restoration & Improvement Selection Maiduguri-Bama Road NG-BORNO MCRP-120952- CS-CQS / Engagement of Safeguard Consultant to Infrastructure Rehabilitation Consultant Pending produce ESIA for Borno PCU IDA / 59880 and Service Delivery Post Qualification Open - National 9,819.97 0.00 2019-09-02 2019-09-09 2019-09-18 2019-09-19 2019-09-21 2019-10-21 Implementation Gongulong-Zabarmari- Restoration & Improvement Selection Dusuman-Galamari-feeder Road NG-BORNO MCRP-120951- CS-CQS / Engagement of Consultant to Design and Infrastructure Rehabilitation Consultant Supervise for Borno PCU IDA / 59880 and Service Delivery Post Qualification Open - National 49,099.84 41,510.55 Completed 2019-09-02 2019-05-01 2019-09-09 2019-10-15 2019-09-18 2019-05-14 2019-09-19 2019-06-03 2019-09-21 2019-06-10 2019-10-21 2019-07-08 Gongulong-Zabarmari- Restoration & Improvement Selection Duduman-Galamari-feeder Road NG-BORNO MCRP-120950- CS-CQS / Engagement of Infrastructure Rehabilitation Consultant Safeguard Consultant to IDA / 59880 and Service Delivery Post Qualification Open - National 49,099.84 109,131.56 Completed 2019-09-02 2019-08-08 2019-09-09 2019-11-21 2019-09-18 2019-09-26 2019-09-19 2019-10-16 2019-09-21 2019-10-21 2019-10-21 2020-06-08 produce ESIAand RAP for Restoration & Improvement Selection Borno PCU 66km Maiduguri- Bama Road BORNO/MCRP/CS/CQS/59/20 / Training on Value addition Consultant for Women drying fish, Strengthening Peace Building, Pending IDA / 59880 Post Qualification Limited 132,478.00 0.00 2020-05-04 2020-05-14 2020-05-16 2020-05-21 2020-08-19 pepper, tomato, okro and Stability and Social Cohesion Implementation Selection other products using solar tent dryer BORNO/MCRP/CS/CQS/50 / Training of Community Health Consultant Strengthening Peace Building, Pending Workers (CHeWs, VHWs, IDA / 59880 Post Qualification Limited 164,787.00 0.00 2020-04-20 2020-05-04 2020-05-06 2020-05-11 2020-06-10 Stability and Social Cohesion Implementation Midwives) of Targeted Health Selection Facilities BORN/MCRP/CS/CQS/54/20 Consultant / Silage, Pellet and Strengthening Peace Building, Pending IDA / 59880 Post Qualification Limited 137,248.00 0.00 2020-04-27 2020-05-07 2020-05-09 2020-05-14 2020-08-12 Concentrate Feed Making Stability and Social Cohesion Implementation Selection Technology BORNO/MCRP/CS/CQS/55/20 Consultant Strengthening Peace Building, Pending / Pasture Production and hay IDA / 59880 Post Qualification Limited 143,675.00 0.00 2020-04-27 2020-05-07 2020-05-09 2020-05-14 2020-08-12 Stability and Social Cohesion Implementation making technology Selection BORNO/MCRP/CS/CQS/56/20 Consultant Strengthening Peace Building, Pending / Artificial Insemination IDA / 59880 Post Qualification Limited 133,957.00 0.00 2020-04-29 2020-05-09 2020-05-11 2020-05-16 2020-08-14 Stability and Social Cohesion Implementation Technicians Technology Selection Page 8 BORNO/MCRP/CS/CQS/57/20 / Training of extension agents on Climate Smart Agriculture Consultant Strengthening Peace Building, Pending (CAS) concept to sustainably IDA / 59880 Post Qualification Limited 147,126.00 0.00 2020-04-22 2020-05-02 2020-05-04 2020-05-09 2020-08-07 Stability and Social Cohesion Implementation increase productivity, enhance Selection resilience and reduce/remove green house gas emission BORNO/MCRP/CS/CQS/54/20 Consultant Strengthening Peace Building, Pending / Regenerative Agriculture IDA / 59880 Post Qualification Limited 131,525.00 0.00 2020-04-24 2020-05-08 2020-05-10 2020-05-15 2020-08-13 Stability and Social Cohesion Implementation and Composting Technology Selection BORNO/MCRP/CS/CQS/60/20 / Provision of Specialized psyco-social support Consultant Strengthening Peace Building, Pending responding to needs (group IDA / 59880 Post Qualification Limited 228,904.00 0.00 2020-05-04 2020-05-14 2020-05-16 2020-05-21 2020-08-19 Stability and Social Cohesion Implementation support, recreational, Selection customary and socializing activities referrals) BORNO/MCRP/CS/CQS/51/20 / Sensitization for Health Consultant Strengthening Peace Building, Pending (Outreach Programs) in 27 IDA / 59880 Post Qualification Limited 261,519.00 0.00 2020-05-04 2020-05-18 2020-05-21 2020-05-27 2020-06-26 Stability and Social Cohesion Implementation Local Government Areas of Selection Borno State BORNO/MCRP/CS/CQS/58/20 / Capacity Building of Consultant Strengthening Peace Building, Pending Smallholder farmers on IDA / 59880 Post Qualification Limited 137,264.00 0.00 2020-04-30 2020-05-10 2020-05-12 2020-05-17 2020-08-15 Stability and Social Cohesion Implementation Fertilizer and Pesticides Selection technologies BORNO/MCRP/CS/CQS/52/20 Consultant Strengthening Peace Building, Pending / Rainwater Harvesting for Dry IDA / 59880 Post Qualification Limited 134,944.00 0.00 2020-04-20 2020-04-22 2020-05-02 2020-05-06 2020-08-04 Stability and Social Cohesion Implementation Season Irrigation Farming Selection INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-BORNO MCRP-58865-CS- INDV / Consultancy for Registration, Mapping and Individual Profiling of all local Strengthening Peace Building, Pending IDA / 59880 Post Consultant Open - National 49,180.00 0.00 2018-11-05 2018-11-05 2018-11-05 2018-11-05 2018-11-05 government structures and Stability and Social Cohesion Implementation Selection existing capacities State Wide in 27 Local Government Areas of Borno State BOMCRP-CS-CDS-02-20 / Infrastructure Rehabilitation SUPERVISION OF Pending IDA / 59880 and Service Delivery Post Direct Selection Direct 260,000.00 0.00 2021-05-03 2021-05-08 2021-05-17 2023-11-03 REHABILITATION OF 66KM Implementation Restoration & Improvement MAIDUGURI-BAMA ROAD Page 9